# American Electric Power Co Inc: Form 10-Q for the period ended Jun 30, 2010

- Company: [American Electric Power Co Inc](/companies/aep.md) (CIK 4904)
- Form: 10-Q
- Filed: 2010-07-30
- Accepted by EDGAR: Jul 30, 2010, 17:31 ET
- Period: 2010-06-30
- Accession: 0000004904-10-000112
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/4904/000000490410000112/q210aep10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/4904/000000490410000112/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2010-06-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2010-04-01 to 2010-06-30 | $3.36bn | us-gaap:Revenues |
| Revenue | 6 months, 2010-01-01 to 2010-06-30 | $6.93bn | us-gaap:Revenues |
| Operating income | 3 months, 2010-04-01 to 2010-06-30 | $394.0m | us-gaap:OperatingIncomeLoss |
| Operating income | 6 months, 2010-01-01 to 2010-06-30 | $1.15bn | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2010-04-01 to 2010-06-30 | $249.0m | us-gaap:InterestExpense |
| Interest expense | 6 months, 2010-01-01 to 2010-06-30 | $499.0m | us-gaap:InterestExpense |
| Income tax | 3 months, 2010-04-01 to 2010-06-30 | $65.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 6 months, 2010-01-01 to 2010-06-30 | $272.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2010-04-01 to 2010-06-30 | $136.0m | us-gaap:NetIncomeLoss |
| Net income | 6 months, 2010-01-01 to 2010-06-30 | $481.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2010-04-01 to 2010-06-30 | $0.28 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 6 months, 2010-01-01 to 2010-06-30 | $1.00 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2010-04-01 to 2010-06-30 | $0.28 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 6 months, 2010-01-01 to 2010-06-30 | $1.00 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2010-04-01 to 2010-06-30 | 479,176,543 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 6 months, 2010-01-01 to 2010-06-30 | 479,012,304 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 6 months, 2010-01-01 to 2010-06-30 | $582.0m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 6 months, 2010-01-01 to 2010-06-30 | $12.0m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 6 months, 2010-01-01 to 2010-06-30 | $399.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2010-06-30 | $838.0m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2010-06-30 | $5.79bn | us-gaap:AssetsCurrent |
| Total assets | at 2010-06-30 | $49.94bn | us-gaap:Assets |
| Current liabilities | at 2010-06-30 | $5.78bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2010-06-30 | $36.61bn | us-gaap:Liabilities |
| Long-term debt | at 2010-06-30 | $16.30bn | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2010-06-30 | $1.04bn | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | at 2010-06-30 | $1.47bn | us-gaap:ShortTermBorrowings |
| Shareholders' equity | at 2010-06-30 | $13.27bn | us-gaap:StockholdersEquity |
| Shares outstanding | at 2010-06-30 | 479,437,027,000,000 shares | dei:EntityCommonStockSharesOutstanding |

## Management's discussion and analysis

As filed, 1,124 characters.

The following table provides information about purchases by AEP or its publicly-traded subsidiaries during the quarter ended June 30, 2010 of equity securities that are registered by AEP or its publicly-traded subsidiaries pursuant to Section 12 of the Exchange Act:

ISSUER PURCHASES OF EQUITY SECURITIES

| Period | Total Number of Shares Purchased |  | Average Price Paid per Share | Total Number of Shares Purchased as Part of Publicly Announced Plans or Programs | Maximum Number (or Approximate Dollar Value) of Shares that May Yet Be Purchased Under the Plans or Programs |
| --- | ---: | --- | ---: | ---: | ---: |
| 04/01/10 – 04/30/10 | 3,759 | (a) | $80.00 | - | $- |
| 05/01/10 – 05/31/10 | 2 | (b) | 66.75 | - | - |
| 06/01/10 – 06/30/10 | - |  | - | - | - |

(a) PSO purchased 3,759 shares of its 4.24% cumulative preferred stock in a privately-negotiated transaction outside of an announced program.

(b) I&M purchased 1 share of its 4.125% cumulative preferred stock and OPCo purchased 1 share of its 4.50% cumulative preferred stock in privately-negotiated transactions outside of an announced program.

235

## Risk factors

As filed, 9,868 characters.

Our Annual Report on Form 10-K for the year ended December 31, 2009 includes a detailed discussion of our risk factors. The information presented below amends and restates in their entirety certain of those risk factors that have been updated and should be read in conjunction with the risk factors and information disclosed in our 2009 Annual Report on Form 10-K.

### General Risks of Our Regulated Operations

**We may not fully recover all of the investment in and expenses related to the Turk Plant.** *(Applies to AEP and SWEPCo)*

In June 2010, the APSC issued an order which reversed and set aside the previously granted CECPN. SWEPCo filed a notice with the APSC of its intent to proceed with construction of the Turk Plant but that SWEPCo no longer intends to pursue a CECPN to seek recovery of the originally approved 88 MW portion of Turk Plant costs in Arkansas retail rates. The parties that successfully challenged the granting of the CECPN filed a complaint with the Federal District Court for the Western District of Arkansas seeking an injunction to stop construction of the Turk Plant asserting claims of violations of federal and state laws.

In November 2008, SWEPCo received its required air permit approval from the Arkansas Department of Environmental Quality and commenced construction at the site. The Arkansas Pollution Control and Ecology Commission (APCEC) upheld the air permit. In February 2010, the parties who unsuccessfully appealed the air permit to the APCEC filed a notice of appeal with the Circuit Court of Hempstead County, Arkansas.

The wetlands permit was issued by the U.S. Army Corps of Engineers in December 2009. In February 2010, the Sierra Club, the Audubon Society and others filed a complaint in the Federal District Court for the Western District of Arkansas against the U.S. Army Corps of Engineers challenging the process used and the terms of the permit issued to SWEPCo authorizing certain wetland and stream impacts.

In January 2009, SWEPCO was granted CECPNs by the APSC to build three transmission lines and facilities authorized by the SPP and needed to transmit power from the Turk Plant. Intervenors appealed the CECPN decisions in April 2009 to the Arkansas Court of Appeals. In July 2010, the Hempsted County Hunting Club and other appellants filed with the Arkansas Court of Appeals emergency motions to stay the transmission CECPNs to prohibit SWEPCo from taking ownership of private property and undertaking construction of the transmission lines.

If SWEPCo is unable to complete the Turk Plant construction and place the Turk Plant in service or if SWEPCo cannot recover all of its investment in and expenses related to the Turk Plant, it would reduce future net income and cash flows and impact financial condition.

**Ohio may require us to refund fuel costs that we have collected.** *(Applies to OPCo)*

As required under the ESP orders, the PUCO selected an outside consultant to conduct the audit of the FAC for the period of January 2009 through December 2009. In May 2010, the outside consultant provided their confidential audit report of the FAC audit to the PUCO. The audit report included a recommendation that the PUCO should review whether any proceeds from a 2008 coal contract settlement agreement which totaled $72 million should reduce OPCo’s FAC under-recovery balance. Of the total proceeds, approximately $58 million was recognized as a reduction to fuel expense prior to 2009 and $14 million will reduce fuel expense in 2009 and 2010. If the PUCO orders any portion of the $58 million previously recognized gains be used to reduce the current year FAC deferral, it would reduce future net income and cash flows and impact financial condition.

**Ohio may require us to refund rider revenue that we have collected.** *(Applies to CSPCo and OPCo)*

The Industrial Energy Users-Ohio filed a notice of appeal of the 2009 and 2010 PUCO-approved Economic Development Rider (EDR) with the Supreme Court of Ohio. As of June 30, 2010, CSPCo and OPCo have incurred $32 million and $23 million, respectively, in EDR costs including carrying costs. Of these costs, CSPCo and OPCo have collected $16 million and $12 million, respectively, through the EDR, which CSPCo and OPCo began collecting in January 2010. The remaining $16 million and $11 million for CSPCo and OPCo, respectively, are recorded as EDR regulatory assets. If CSPCo and OPCo are not ultimately permitted to recover their deferrals or are required to refund revenue collected, it would reduce future net income and cash flows and impact financial condition.

**Texas may require us to refund fuel costs that we have collected.** *(Applies to SWEPCo)*

In May 2010, various intervenors, including the PUCT staff, filed testimony recommending disallowances ranging from $3 million to $30 million in SWEPCo’s $755 million fuel and purchase power costs reconciliation for the period January 2006 through March 2009. If the PUCT disallows any portion of SWEPCo’s fuel and purchase power costs, it could reduce future net income and cash flows and possibly impact financial condition.

**Our request for rate recovery in West Virginia may not be approved in its entirety.** *(Applies to AEP and APCo)*

In May 2010, APCo and WPCo filed a request with the WVPSC to increase annual base rates by $156 million based on an 11.75% return on common equity to be effective March 2011. If the WVPSC denies all or part of the requested rate recovery, it could reduce future net income and cash flows.

**Oklahoma may require us to refund fuel costs that we have collected.** *(Applies to PSO)*

In July 2009, the OCC initiated a proceeding to review PSO’s fuel and purchased power adjustment clause for the calendar year 2008 and also initiated a prudence review of the related costs. In March 2010, the Oklahoma Attorney General and the OIEC recommended the fuel clause adjustment rider be amended so that the shareholder’s portion of off-system sales margins sharing decrease from 25% to 10%. The OIEC also recommended that the OCC conduct a comprehensive review of all affiliate transactions during 2007 and 2008. In July 2010, additional testimony regarding the 2007 transfer of ERCOT trading contracts to AEP Energy Partners was filed. Included in this testimony were unquantified refund recommendations relating to re-pricing of contract transactions. If the OCC were to issue an unfavorable decision, it would reduce future net income and cash flows and impact financial condition.

**Our request for rate recovery in Oklahoma may not be approved in its entirety.** *(Applies to AEP and PSO)*

In July 2010, PSO filed a request with the OCC to increase annual rates by $82 million, including $30 million that is currently being recovered through a rider. The requested increase includes a $24 million increase in depreciation and an 11.5% return on common equity. If the OCC denies all or part of the requested rate recovery, it could reduce future net income and cash flows.

### Risks Related to Owning and Operating Generation Assets and Selling Power

### We may not fully recover the costs of repairing or replacing damaged equipment in Cook Plant Unit 1 and may be required to pay additional

#### accidental outage insurance proceeds to ratepayers. (Applies to AEP and I&M)

Cook Plant Unit 1 is a 1,084 MW nuclear generating unit located in Bridgman, Michigan. In September 2008, I&M shut down Unit 1 due to turbine vibrations, caused by blade failure, which resulted in significant turbine damage and a small fire on the electric generator. Unit 1 resumed operations in December 2009 at slightly reduced power, but repair of the property damage and replacement of the turbine rotors and other equipment are estimated to cost approximately $395 million. Management believes that I&M should recover a significant portion of these costs through the turbine vendor’s warranty, insurance and the regulatory process.

In March 2009, the IURC approved a settlement agreement with intervenors to collect a prior under-recovered fuel balance. Under the settlement agreement, a subdocket was established to consider issues relating to the Unit 1 shutdown including the treatment of the accidental outage insurance proceeds. Separately, in March 2010, I&M filed its 2009 PSCR reconciliation with the MPSC. The filing included an adjustment related to the incremental fuel cost of replacement power due to the Cook Plant Unit 1 outage. If any fuel clause revenues or accidental outage insurance proceeds have to be refunded, it would reduce future net income and cash flows and impact financial condition.

**Financial derivatives reforms could increase the liquidity needs and costs of our commercial trading operations.** *(Applies to each registrant.)*

In July 2010, federal legislation was enacted to reform financial markets that significantly alter how over-the-counter (OTC) derivatives are regulated. The law increased regulatory oversight of OTC energy derivatives, including (1) requiring standardized OTC derivatives to be traded on registered exchanges regulated by the Commodity Futures Trading Commission (CFTC), (2) imposing new and potentially higher capital and margin requirements and (3) authorizing the establishment of overall volume and position limits. The law gives the CFTC authority to exempt end users of energy commodities which could reduce, but not eliminate, the applicability of these measures to us and other end users. These requirements could cause our OTC transactions to be more costly and have an adverse effect on our liquidity due to additional capital requirements. In addition, as these reforms aim to standardize OTC products it could limit the effectiveness of our hedging programs because we would have less ability to tailor OTC derivatives to match the precise risk we are seeking to protect.

Filed Jul 30, 2010.
Source: SEC EDGAR, the filing index for accession 0000004904-10-000112. Last ingested by Listed: Nov 10, 2026, 00:43 ET. No prices; not investment advice.