# MDU Resources Group Inc: Form 10-Q for the period ended Jun 30, 2013

- Company: [MDU Resources Group Inc](/companies/mdu.md) (CIK 67716)
- Form: 10-Q
- Filed: 2013-08-07
- Accepted by EDGAR: Aug 7, 2013, 12:15 ET
- Period: 2013-06-30
- Accession: 0000067716-13-000101
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/67716/000006771613000101/mduform10-q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/67716/000006771613000101/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2013-06-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2013-04-01 to 2013-06-30 | $1.06bn | us-gaap:Revenues |
| Revenue | 6 months, 2013-01-01 to 2013-06-30 | $1.99bn | us-gaap:Revenues |
| Operating income | 3 months, 2013-04-01 to 2013-06-30 | $91.4m | us-gaap:OperatingIncomeLoss |
| Operating income | 6 months, 2013-01-01 to 2013-06-30 | $195.9m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2013-04-01 to 2013-06-30 | $21.4m | us-gaap:InterestExpense |
| Interest expense | 6 months, 2013-01-01 to 2013-06-30 | $42.3m | us-gaap:InterestExpense |
| Income tax | 3 months, 2013-04-01 to 2013-06-30 | $25.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 6 months, 2013-01-01 to 2013-06-30 | $53.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 6 months, 2013-01-01 to 2013-06-30 | $102.8m | us-gaap:ProfitLoss |
| Diluted EPS | 3 months, 2013-04-01 to 2013-06-30 | $0.24 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 6 months, 2013-01-01 to 2013-06-30 | $0.54 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2013-04-01 to 2013-06-30 | $0.25 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 6 months, 2013-01-01 to 2013-06-30 | $0.54 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2013-04-01 to 2013-06-30 | 189,463,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 6 months, 2013-01-01 to 2013-06-30 | 189,460,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 6 months, 2013-01-01 to 2013-06-30 | $233.9m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 6 months, 2013-01-01 to 2013-06-30 | $431.4m | us-gaap:PaymentsToAcquireProductiveAssets |
| Dividends paid | 6 months, 2013-01-01 to 2013-06-30 | $32.9m | us-gaap:PaymentsOfDividends |
| Cash and equivalents | at 2013-06-30 | $115.0m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2013-06-30 | $1.29bn | us-gaap:AssetsCurrent |
| Total assets | at 2013-06-30 | $7.09bn | us-gaap:Assets |
| Current liabilities | at 2013-06-30 | $865.9m | us-gaap:LiabilitiesCurrent |
| Short-term borrowings | at 2013-06-30 | $31.6m | us-gaap:ShortTermBorrowings |
| Shareholders' equity | at 2013-06-30 | $2.68bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 65,978 characters.

### OVERVIEW

The Company's strategy is to apply its expertise in energy and transportation infrastructure industries to increase market share, increase profitability and enhance shareholder value through:

- Organic growth as well as a continued disciplined approach to the acquisition of well-managed companies and properties
- The elimination of system-wide cost redundancies through increased focus on integration of operations and standardization and consolidation of various support services and functions across companies within the organization
- The development of projects that are accretive to earnings per share and return on invested capital

The Company has capabilities to fund its growth and operations through various sources, including internally generated funds, commercial paper facilities, revolving credit facilities and the issuance from time to time of debt and equity securities. For more information on the Company's net capital expenditures, see Liquidity and Capital Commitments.

The key strategies for each of the Company's business segments and certain related business challenges are summarized below. For a summary of the Company's business segments, see Note 16.

### Key Strategies and Challenges

### Electric and Natural Gas Distribution

**Strategy** Provide competitively priced energy and related services to customers. The electric and natural gas distribution segments continually seek opportunities to retain, grow and expand their customer base through extensions of existing operations, including building and upgrading electric generation and transmission and natural gas systems, and through selected acquisitions of companies and properties at prices that will provide stable cash flows and an opportunity for the Company to earn a competitive return on investment.

**Challenges** Both segments are subject to extensive regulation in the state jurisdictions where they conduct operations with respect to costs and permitted returns on investment as well as subject to certain operational, system integrity and environmental regulations. These regulations can require substantial investment to upgrade facilities. The ability of these segments to grow through acquisitions is subject to significant competition. In addition, the ability of both segments to grow service territory and customer base is affected by the economic environment of the markets served and competition from other energy providers and fuels. The construction of any new electric generating facilities, transmission lines and other service facilities are subject to increasing cost and lead time, extensive permitting procedures, and federal and state legislative and regulatory initiatives, which will necessitate increases in electric energy prices. Legislative and regulatory initiatives to increase renewable energy resources and reduce GHG emissions could impact the price and demand for electricity and natural gas.

### Pipeline and Energy Services

**Strategy** Utilize the segment's existing expertise in energy infrastructure and related services to increase market share and profitability through optimization of existing operations, internal growth, and acquisitions of energy-related assets and companies. Incremental and new growth opportunities include: access to new energy sources for storage, gathering and transportation services; expansion of existing gathering, transmission and storage facilities; incremental expansion of pipeline capacity; expansion of midstream business to include liquid pipelines and processing/refining activities; and expansion of related energy services.

**Challenges** Challenges for this segment include: energy price volatility; natural gas basis differentials; environmental and regulatory requirements; recruitment and retention of a skilled workforce; and competition from other pipeline and energy services companies.

### Exploration and Production

**Strategy** Apply technology and utilize existing exploration and production expertise, with a focus on operated properties, to increase production and reserves from existing leaseholds, and to seek additional reserves and production opportunities both in new and existing areas to further expand the segment's asset base. By optimizing existing operations and taking advantage of new and incremental growth opportunities, this segment is focused on balancing the oil and natural gas commodity mix to maximize profitability with its goal to add value by increasing both reserves and production over the long term so as to generate competitive returns on investment.

**Challenges** Volatility in natural gas and oil prices; timely receipt of necessary permits and approvals; environmental and regulatory requirements; recruitment and retention of a skilled workforce; availability of drilling rigs, materials, auxiliary equipment and industry-related field services; inflationary pressure on development and operating costs; and competition from other exploration and production companies are ongoing challenges for this segment.

### Construction Materials and Contracting

**Strategy** Focus on high-growth strategic markets located near major transportation corridors and desirable mid-sized metropolitan areas; strengthen long-term, strategic aggregate reserve position through purchase and/or lease opportunities; enhance profitability through cost containment, margin discipline and vertical integration of the segment's operations; develop and recruit talented employees; and continue growth through organic and acquisition opportunities. Vertical integration allows the segment to manage operations from aggregate mining to final lay-down of concrete and asphalt, with control of and access to permitted aggregate reserves being significant. A key element of the Company's long-term strategy for this business is to further expand its market presence in the higher-margin materials business (rock, sand, gravel, liquid asphalt, asphalt concrete, ready-mixed concrete and related products), complementing and expanding on the Company's expertise.

**Challenges** Recruitment and retention of key personnel and volatility in the cost of raw materials such as diesel, gasoline, liquid asphalt, cement and steel, continue to be a concern. This business unit expects to continue cost containment efforts, positioning its operations for the resurgence in the private market, while continuing the emphasis on industrial, energy and public works projects.

### Construction Services

**Strategy** Provide a superior return on investment by: building new and strengthening existing customer relationships; effectively controlling costs; retaining, developing and recruiting talented employees; and focusing our efforts on projects that will permit higher margins while properly managing risk.

**Challenges** This segment operates in highly competitive markets with many jobs subject to competitive bidding. Maintenance of effective operational and cost controls, retention of key personnel, managing through downturns in the economy and effective management of working capital are ongoing challenges.

For more information on the risks and challenges the Company faces as it pursues its growth strategies and other factors that should be considered for a better understanding of the Company's financial condition, see Item 1A - Risk Factors, as well as Part I, Item 1A - Risk Factors in the 2012 Annual Report. For more information on each segment's key growth strategies, projections and certain assumptions, see Prospective Information. For information pertinent to various commitments and contingencies, see Notes to Consolidated Financial Statements.

### Earnings Overview

The following table summarizes the contribution to consolidated earnings by each of the Company's businesses.

*(Dollars in millions, where applicable)*

|  | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| **Electric** | $4.4 | $4.4 | $14.2 | $12.0 |
| **Natural gas distribution** | (5.9) | (6.4) | 26.6 | 19.1 |
| **Pipeline and energy services** | (6.4) | 15.8 | (4.1) | 18.6 |
| **Exploration and production** | 33.0 | 18.0 | 53.3 | 30.9 |
| **Construction materials and contracting** | 10.0 | 7.8 | (10.5) | (17.1) |
| **Construction services** | 12.9 | 8.7 | 24.6 | 20.1 |
| **Other** | .5 | .5 | 0.9 | 1.0 |
| **Intersegment eliminations** | (2.1) | — | (2.1) | — |
| **Earnings before discontinued operations** | 46.4 | 48.8 | 102.9 | 84.6 |
| **Income (loss) from discontinued operations, net of tax** | (.1) | 5.1 | (.2) | 5.0 |
| **Earnings on common stock** | $46.3 | $53.9 | $102.7 | $89.6 |
| **Earnings per common share - basic:** |  |  |  |  |
| **Earnings before discontinued operations** | $.25 | $.26 | $.54 | $.45 |
| **Discontinued operations, net of tax** | — | .03 | — | .02 |
| **Earnings per common share - basic** | $.25 | $.29 | $.54 | $.47 |
| **Earnings per common share - diluted:** |  |  |  |  |
| **Earnings before discontinued operations** | $.24 | $.26 | $.54 | $.45 |
| **Discontinued operations, net of tax** | — | .03 | — | .02 |
| **Earnings per common share - diluted** | $.24 | $.29 | $.54 | $.47 |

***Three Months Ended June 30, 2013 and 2012*** Consolidated earnings for the quarter ended June 30, 2013, decreased $7.6 million (14 percent) from the comparable prior period largely due to:

- Absence of a 2012 net benefit related to the natural gas gathering operations litigation of $15.0 million (after tax), as discussed in Note 19, as well as an impairment of coalbed natural gas gathering assets of $9.0 million (after tax) in 2013 compared to an impairment of $1.7 million (after tax) in 2012, at the pipeline and energy services business
- Loss from discontinued operations of $100,000 (after tax) compared to income from discontinued operations of $5.1 million (after tax) in 2012, as discussed in Note 10

Partially offsetting these decreases were:

- Increased oil production, higher average realized natural gas prices, as well as a higher unrealized gain on commodity derivatives of $8.2 million (after tax) compared to $3.0 million (after tax) in 2012, partially offset by higher depreciation, depletion and amortization expense and a lower realized gain on commodity derivatives at the exploration and production business
- Higher workloads and margins and higher equipment sales and rental margins, partially offset by higher general and administrative expense at the construction services business

***Six Months Ended June 30, 2013 and 2012*** Consolidated earnings for the six months ended June 30, 2013, increased $13.1 million (15 percent) from the comparable prior period largely due to:

- Increased oil production, higher average realized natural gas prices, as well as a higher unrealized gain on commodity derivatives of $4.6 million (after tax) compared to $500,000 (after tax) in 2012, partially offset by higher depreciation, depletion and amortization expense, decreased natural gas production, a lower realized gain on commodity derivatives, higher production taxes, as well as increased lease operating expenses at the exploration and production business
- Increased retail sales volumes and a gain on the sale of a nonregulated appliance service and repair business at the natural gas distribution business
- Higher asphalt, liquid asphalt oil, construction and ready-mixed concrete margins, partially offset by lower other product line margins at the construction materials and contracting business

Partially offsetting these increases was the absence of the 2012 net benefit of $15.0 million (after tax), as previously discussed, and the impairment of coalbed natural gas gathering assets of $9.0 million (after tax) in 2013, compared to an impairment of $1.7 million in 2012, at the pipeline and energy services business.

### FINANCIAL AND OPERATING DATA

Below are key financial and operating data for each of the Company's businesses.

### Electric

*(Dollars in millions, where applicable)*

|  | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| **Operating revenues** | $57.0 | $53.0 | $121.6 | $110.9 |
| **Operating expenses:** |  |  |  |  |
| Fuel and purchased power | 18.2 | 15.2 | 39.8 | 33.6 |
| Operation and maintenance | 20.5 | 19.1 | 36.8 | 35.3 |
| Depreciation, depletion and amortization | 7.9 | 8.0 | 16.5 | 16.1 |
| Taxes, other than income | 2.8 | 2.6 | 5.7 | 5.3 |
|  | 49.4 | 44.9 | 98.8 | 90.3 |
| **Operating income** | 7.6 | 8.1 | 22.8 | 20.6 |
| **Earnings** | $4.4 | $4.4 | $14.2 | $12.0 |
| **Retail sales (million kWh)** | 691.5 | 666.3 | 1,534.1 | 1,436.0 |
| **Sales for resale (million kWh)** | 8.8 | 1.0 | 16.2 | 2.9 |
| **Average cost of fuel and purchased power per kWh** | $.024 | $.021 | $.024 | $.022 |

***Three Months Ended June 30, 2013 and 2012*** Electric earnings decreased $9,000 due to:

- Higher operation and maintenance expense of $700,000 (after tax), including increased contract services at certain of the Company's electric generation stations and higher payroll-related costs, offset in part by lower benefit-related costs
- Increased taxes other than income of $200,000 (after tax), primarily related to higher property taxes

Largely offsetting these decreases were increased retail sales volumes of 4 percent, primarily to residential customers due to increased customer growth.

***Six Months Ended June 30, 2013 and 2012*** Electric earnings increased $2.2 million (19 percent) due to:

- Increased retail sales volumes of 7 percent, primarily to residential and small commercial and industrial customers due to increased customer growth, as well as weather variances from last year
- Higher other income, largely allowance for funds used during construction of $500,000

Partially offsetting these increases was higher operation and maintenance expense, which includes $600,000 (after tax) of expenses largely related to higher payroll-related costs, increased contract services, as well as higher material costs, offset in part by lower benefit-related costs.

### Natural Gas Distribution

*(Dollars in millions, where applicable)*

|  | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| **Operating revenues** | $127.6 | $116.8 | $459.3 | $424.7 |
| **Operating expenses:** |  |  |  |  |
| Purchased natural gas sold | 73.5 | 62.9 | 286.9 | 262.2 |
| Operation and maintenance | 35.7 | 35.9 | 69.9 | 71.1 |
| Depreciation, depletion and amortization | 12.4 | 11.3 | 24.5 | 22.5 |
| Taxes, other than income | 9.5 | 10.0 | 25.7 | 26.2 |
|  | 131.1 | 120.1 | 407.0 | 382.0 |
| **Operating income (loss)** | (3.5) | (3.3) | 52.3 | 42.7 |
| **Earnings (loss)** | $(5.9) | $(6.4) | $26.6 | $19.1 |
| **Volumes (MMdk):** |  |  |  |  |
| Sales | 15.3 | 13.4 | 60.2 | 52.1 |
| Transportation | 30.3 | 26.8 | 68.5 | 64.7 |
| **Total throughput** | 45.6 | 40.2 | 128.7 | 116.8 |
| **Degree days (% of normal)\*** |  |  |  |  |
| Montana-Dakota/Great Plains | 130% | 77% | 104% | 77% |
| Cascade | 82% | 94% | 93% | 99% |
| Intermountain | 99% | 97% | 110% | 94% |
| **Average cost of natural gas, including transportation, per dk** | $4.82 | $4.70 | $4.77 | $5.03 |
| \* Degree days are a measure of the daily temperature-related demand for energy for heating. |  |  |  |  |

***Three Months Ended June 30, 2013 and 2012*** The natural gas distribution business recognized a seasonal loss of $5.9 million compared to a seasonal loss of $6.4 million a year ago. The improvement was the result of:

- Increased retail sales volumes of 14 percent, largely resulting from colder weather than last year, partially offset by weather normalization adjustments in certain jurisdictions
- Lower net interest expense of $700,000 (after tax), primarily due to lower average interest rates

Partially offsetting these items were:

- Increased depreciation, depletion and amortization expense of $700,000 (after tax), primarily resulting from higher property, plant and equipment balances
- Lower other income of $400,000 (after tax), largely lower allowance for funds used during construction

***Six Months Ended June 30, 2013 and 2012*** Earnings at the natural gas distribution business increased $7.5 million (39 percent) due to:

- Increased retail sales volumes of 16 percent, largely resulting from colder weather than last year, partially offset by weather normalization adjustments in certain jurisdictions
- A $2.8 million (after tax) gain on the sale of Montana-Dakota's nonregulated appliance service and repair business
- Lower net interest expense of $1.2 million (after tax), as previously discussed

Partially offsetting these increases was increased depreciation, depletion and amortization expense of $1.2 million (after tax), as previously discussed.

### Pipeline and Energy Services

*(Dollars in millions)*

|  | Three Months Ended June 30, 2013 |  | 2012 |  | Six Months Ended June 30, 2013 |  | 2012 |  |
| --- | ---: | --- | ---: | --- | ---: | --- | ---: | --- |
| **Operating revenues** | $50.9 |  | $43.6 |  | $97.3 |  | $93.2 |  |
| **Operating expenses:** |  |  |  |  |  |  |  |  |
| Purchased natural gas sold | 15.8 |  | 8.5 |  | 28.6 |  | 24.6 |  |
| Operation and maintenance | 32.1 | \* | (1.4) | \*\* | 49.3 | \* | 15.6 | \*\* |
| Depreciation, depletion and amortization | 7.7 |  | 6.8 |  | 14.9 |  | 13.1 |  |
| Taxes, other than income | 3.5 |  | 3.5 |  | 6.9 |  | 6.9 |  |
|  | 59.1 |  | 17.4 |  | 99.7 |  | 60.2 |  |
| **Operating income (loss)** | (8.2) |  | 26.2 |  | (2.4) |  | 33.0 |  |
| **Earnings (loss)** | $(6.4) | \* | $15.8 | \*\* | $(4.1) | \* | $18.6 | \*\* |
| **Transportation volumes (MMdk)** | 40.3 |  | 36.8 |  | 77.1 |  | 68.8 |  |
| **Natural gas gathering volumes (MMdk)** | 10.0 |  | 11.6 |  | 19.9 |  | 25.8 |  |
| **Customer natural gas storage balance (MMdk):** |  |  |  |  |  |  |  |  |
| Beginning of period | 24.7 |  | 27.3 |  | 43.7 |  | 36.0 |  |
| Net injection (withdrawal) | .5 |  | 13.1 |  | (18.5) |  | 4.4 |  |
| End of period | 25.2 |  | 40.4 |  | 25.2 |  | 40.4 |  |
| \* Reflects an impairment of coalbed natural gas gathering assets of $14.5 million ($9.0 million after tax). \*\* Reflects a net benefit of $24.1 million ($15.0 million after tax) related to the natural gas gathering operations litigation, largely reflected in operation and maintenance expense, as discussed in Note 19, as well as an impairment of coalbed natural gas gathering assets of $2.7 million ($1.7 million after tax). |  |  |  |  |  |  |  |  |

***Three Months Ended June 30, 2013 and 2012*** The pipeline and energy services business recognized a loss of $6.4 million compared to earnings of $15.8 million for the comparable prior period due to:

- Absence of the 2012 net benefit of $15.0 million (after tax) related to the natural gas gathering operations litigation, as discussed in Note 19
- An impairment of coalbed natural gas gathering assets of $9.0 million (after tax) in 2013, compared to an impairment of $1.7 million (after tax) in 2012, largely resulting from low natural gas prices, as discussed in Note 5
- Lower storage services revenue of $1.0 million (after tax), largely due to lower average rates and lower average storage balances

These decreases were partially offset by lower operation and maintenance expense (excluding the asset impairments and net benefit related to the natural gas gathering operations litigation), as well as higher revenue associated with the Company's May 2012 acquisition of oil and natural gas gathering and processing assets.

Results also reflect higher operating revenues and higher purchased natural gas sold, both related to higher natural gas prices.

***Six Months Ended June 30, 2013 and 2012*** The pipeline and energy services business recognized a loss of $4.1 million compared to earnings of $18.6 million for the the comparable prior period largely due to:

- Absence of the 2012 net benefit of $15.0 million (after tax), as previously discussed
- An impairment of coalbed natural gas gathering assets of $9.0 million (after tax) in 2013, compared to an impairment of $1.7 million (after tax) in 2012, as previously discussed
- Lower earnings of $2.2 million (after tax) resulting from lower natural gas gathering volumes from existing operations, largely resulting from customers experiencing production curtailments, normal declines and deferral of natural gas development activity
- Lower storage services revenue of $900,000 (after tax), largely due to lower average rates

These decreases were partially offset by higher revenue associated with the Company's May 2012 acquisition of oil and natural gas gathering assets, as well as lower operation and maintenance expense, as previously discussed.

Results also reflect higher operating revenues and higher purchased natural gas sold, both related to higher natural gas prices.

### Exploration and Production

*(Dollars in millions, where applicable)*

| Operating revenues: | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| Oil | $105.9 | $70.9 | $205.9 | $142.2 |
| NGL | 6.2 | 7.1 | 13.7 | 16.8 |
| Natural gas | 23.2 | 12.0 | 42.4 | 31.5 |
| Realized gain on commodity derivatives | 1.3 | 11.1 | 5.6 | 14.6 |
| Unrealized gain on commodity derivatives | 13.0 | 4.8 | 7.2 | .7 |
|  | 149.6 | 105.9 | 274.8 | 205.8 |
| **Operating expenses:** |  |  |  |  |
| Operation and maintenance: |  |  |  |  |
| Lease operating costs | 22.0 | 19.0 | 42.8 | 37.5 |
| Gathering and transportation | 4.2 | 4.2 | 8.5 | 8.5 |
| Other | 10.3 | 9.5 | 20.4 | 18.7 |
| Depreciation, depletion and amortization | 45.1 | 34.4 | 88.3 | 71.2 |
| Taxes, other than income: |  |  |  |  |
| Production and property taxes | 12.3 | 8.7 | 23.9 | 18.3 |
| Other | .3 | .3 | .6 | .6 |
|  | 94.2 | 76.1 | 184.5 | 154.8 |
| **Operating income** | 55.4 | 29.8 | 90.3 | 51.0 |
| **Earnings** | $33.0 | $18.0 | $53.3 | $30.9 |
| **Production:** |  |  |  |  |
| Oil (MBbls) | 1,201 | 876 | 2,319 | 1,643 |
| NGL (MBbls) | 191 | 209 | 392 | 399 |
| Natural gas (MMcf) | 6,987 | 8,239 | 13,700 | 18,286 |
| Total production (MBOE) | 2,557 | 2,458 | 4,995 | 5,090 |
| **Average realized prices (excluding realized and unrealized gain on commodity derivatives):** |  |  |  |  |
| Oil (per Bbl) | $88.12 | $80.99 | $88.75 | $86.60 |
| NGL (per Bbl) | $32.26 | $33.77 | $34.86 | $41.91 |
| Natural gas (per Mcf) | $3.33 | $1.46 | $3.10 | $1.72 |
| **Average realized prices (including realized gain on commodity derivatives):** |  |  |  |  |
| Oil (per Bbl) | $90.55 | $83.06 | $91.18 | $85.73 |
| NGL (per Bbl) | $32.26 | $33.77 | $34.86 | $41.91 |
| Natural gas (per Mcf) | $3.09 | $2.59 | $3.09 | $2.60 |
| **Average depreciation, depletion and amortization rate, per BOE** | $16.90 | $13.32 | $16.90 | $13.32 |
| **Production costs, including taxes, per BOE:** |  |  |  |  |
| Lease operating costs | $8.59 | $7.74 | $8.57 | $7.37 |
| Gathering and transportation | 1.66 | 1.70 | 1.71 | 1.66 |
| Production and property taxes | 4.81 | 3.54 | 4.78 | 3.58 |
|  | $15.06 | $12.98 | $15.06 | $12.61 |

***Three Months Ended June 30, 2013 and 2012*** Exploration and production earnings increased $15.0 million (84 percent) due to:

- Increased oil production of 37 percent, primarily related to drilling activity in the Bakken area, as well as the Paradox Basin
- Higher average realized natural gas prices of 128 percent, excluding gain on commodity derivatives
- Unrealized gain on commodity derivatives of $8.2 million (after tax) compared to $3.0 million (after tax) in 2012
- Higher average realized oil prices of 9 percent, excluding gain on commodity derivatives

Partially offsetting these increases were:

- Higher depreciation, depletion and amortization expense of $6.7 million (after tax), largely due to higher depletion rates
- Lower realized gain on commodity derivatives of $6.2 million (after tax), due to higher commodity prices
- Decreased natural gas production of 15 percent, largely related to production curtailments, normal declines and deferral of certain natural gas development activity
- Higher production taxes of $2.2 million (after tax), primarily resulting from higher revenues
- Increased lease operating expenses of $1.9 million (after tax), largely related to higher costs in the Bakken area resulting from increased production volumes and higher workover costs, as well as higher costs in the Paradox Basin resulting from increased production volumes, partially offset by lower costs at certain natural gas properties where curtailments of production have occurred
- Higher net interest expense of $1.2 million (after tax), primarily due to lower capitalized interest and higher average borrowings

***Six Months Ended June 30, 2013 and 2012*** Exploration and production earnings increased $22.4 million (72 percent) due to:

- Increased oil production of 41 percent, as previously discussed
- Higher average realized natural gas prices of 80 percent, excluding gain on commodity derivatives
- Unrealized gain on commodity derivatives of $4.6 million (after tax) compared to $500,000 (after tax) in 2012
- Higher average realized oil prices of 2 percent, excluding gain on commodity derivatives

Partially offsetting these increases were:

- Higher depreciation, depletion and amortization expense of $10.7 million (after tax), as previously discussed
- Decreased natural gas production of 25 percent, as previously discussed
- Lower realized gain on commodity derivatives of $5.7 million (after tax), as previously discussed
- Higher production taxes of $3.5 million (after tax), as previously discussed
- Increased lease operating expenses of $3.3 million (after tax), as previously discussed
- Higher net interest expense of $2.2 million (after tax), primarily due to lower capitalized interest and higher average borrowings, partially offset by lower effective interest rates
- Lower average realized NGL prices of 17 percent
- Higher general and administrative expense of $1.0 million (after tax), including higher payroll-related costs

### Construction Materials and Contracting

*(Dollars in millions)*

|  | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| **Operating revenues** | $431.3 | $442.1 | $597.6 | $591.5 |
| **Operating expenses:** |  |  |  |  |
| Operation and maintenance | 381.2 | 396.7 | 547.9 | 553.7 |
| Depreciation, depletion and amortization | 18.7 | 19.8 | 37.7 | 39.6 |
| Taxes, other than income | 10.6 | 10.6 | 19.1 | 18.6 |
|  | 410.5 | 427.1 | 604.7 | 611.9 |
| **Operating income (loss)** | 20.8 | 15.0 | (7.1) | (20.4) |
| **Earnings (loss)** | $10.0 | $7.8 | $(10.5) | $(17.1) |
| **Sales (000's):** |  |  |  |  |
| Aggregates (tons) | 6,152 | 6,481 | 9,110 | 8,974 |
| Asphalt (tons) | 1,518 | 1,761 | 1,667 | 1,861 |
| Ready-mixed concrete (cubic yards) | 846 | 837 | 1,326 | 1,305 |

***Three Months Ended June 30, 2013 and 2012*** Earnings at the construction materials and contracting business increased $2.2 million (29 percent) due to:

- Higher earnings of $1.7 million (after tax) resulting from higher asphalt margins, primarily due to lower costs
- Higher earnings of $1.6 million (after tax) resulting from higher liquid asphalt oil margins, primarily due to higher volumes and lower costs
- Higher earnings of $1.1 million (after tax) resulting from higher ready-mixed concrete margins, primarily due to lower costs

Partially offsetting these increases were:

- Lower earnings of $1.6 million (after tax), resulting from lower aggregate margins, primarily due to lower volumes and higher costs
- Higher interest expense of $500,000 (after tax), resulting from higher average interest rates, as well as higher average borrowings

***Six Months Ended June 30, 2013 and 2012*** Construction materials and contracting experienced a loss of $10.5 million, which was a 38 percent improvement, resulting from:

- Higher earnings of $2.9 million (after tax) resulting from higher asphalt margins, as previously discussed
- Higher earnings of $1.9 million (after tax) resulting from higher liquid asphalt oil margins, as previously discussed
- Increased construction margins of $1.6 million (after tax)
- Higher earnings of $1.5 million (after tax) resulting from higher ready-mixed concrete margins, as previously discussed
- Lower selling, general and administrative costs of $1.2 million (after tax)

Partially offsetting the decreased loss were:

- Lower earnings of $1.4 million (after tax) resulting from lower other product line margins, primarily due to higher costs
- Higher interest expense of $1.0 million (after tax), as previously discussed

### Construction Services

*(In millions)*

|  | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| **Operating revenues** | $279.6 | $224.1 | $511.0 | $442.3 |
| **Operating expenses:** |  |  |  |  |
| Operation and maintenance | 245.9 | 198.6 | 444.3 | 386.6 |
| Depreciation, depletion and amortization | 3.0 | 2.8 | 6.0 | 5.5 |
| Taxes, other than income | 8.4 | 7.2 | 18.0 | 15.0 |
|  | 257.3 | 208.6 | 468.3 | 407.1 |
| **Operating income** | 22.3 | 15.5 | 42.7 | 35.2 |
| **Earnings** | $12.9 | $8.7 | $24.6 | $20.1 |

***Three Months Ended June 30, 2013 and 2012*** Construction services earnings increased $4.2 million (49 percent), primarily due to higher workloads and margins in all regions, as well as higher equipment sales and rental margins. These increases were partially offset by higher general and administrative expense of $1.1 million (after tax), including higher payroll-related costs.

***Six Months Ended June 30, 2013 and 2012*** Construction services earnings increased $4.5 million (22 percent), primarily due to higher workloads and margins in the Western region, as well as higher equipment sales and rental margins. These items were partially offset by higher general and administrative expense of $1.6 million (after tax), as well as lower margins in the Central region.

### Other

*(In millions)*

|  | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | --- | ---: | --- | ---: |
| **Operating revenues** | $2.3 | $2.5 | $4.5 | $4.6 |
| **Operating expenses:** |  |  |  |  |
| Operation and maintenance | 1.4 | 1.5 | 2.7 | 2.9 |
| Depreciation, depletion and amortization | .5 | .5 | 1.0 | 1.0 |
| Taxes, other than income | — | .1 | .1 | — |
|  | 1.9 | 2.1 | 3.8 | 3.9 |
| **Operating income** | .4 | .4 | .7 | .7 |
| **Income from continuing operations** | .5 | .5 | .9 | 1.0 |
| **Income (loss) from discontinued operations, net of tax** | (.1) | 5.1 | (.2) | 5.0 |
| **Earnings** | $.4 | $5.6 | $.7 | $6.0 |

***Three Months Ended June 30, 2013 and 2012*** Other earnings decreased $5.2 million, primarily due to a loss from discontinued operations of $100,000 (after tax) in 2013 compared to income from discontinued operations of $5.1 million (after tax) in 2012. This decrease is largely related to the absence of a net benefit in 2012, as discussed in Note 10.

***Six Months Ended June 30, 2013 and 2012*** Other earnings decreased $5.3 million, primarily due to a loss from discontinued operations of $200,000 (after tax) in 2013 compared to income from discontinued operations of $5.0 million (after tax) in 2012, as previously discussed.

### Intersegment Transactions

Amounts presented in the preceding tables will not agree with the Consolidated Statements of Income due to the Company's elimination of intersegment transactions. The amounts relating to these items are as follows:

*(In millions)*

| Intersegment transactions: | Three Months Ended June 30, 2013 | 2012 | Six Months Ended June 30, 2013 | 2012 |
| --- | ---: | ---: | ---: | ---: |
| Operating revenues | $37.7 | $20.0 | $73.9 | $52.2 |
| Purchased natural gas sold | 19.1 | 13.0 | 46.1 | 42.9 |
| Operation and maintenance | 15.2 | 7.0 | 24.4 | 9.3 |
| Income taxes | 1.4 | — | 1.4 | — |
| Earnings on common stock | 2.1 | — | 2.1 | — |

For more information on intersegment eliminations, see Note 16.

### PROSPECTIVE INFORMATION

The following information highlights the key growth strategies, projections and certain assumptions for the Company and its subsidiaries and other matters for certain of the Company's businesses. Many of these highlighted points are "forward-looking statements." There is no assurance that the Company's projections, including estimates for growth and changes in earnings, will in fact be achieved. Please refer to assumptions contained in this section, as well as the various important factors listed in Part II, Item 1A - Risk Factors, as well as Part I, Item 1A - Risk Factors in the 2012 Annual Report. Changes in such assumptions and factors could cause actual future results to differ materially from the Company's growth and earnings projections.

- Earnings per common share for 2013, diluted, are projected in the range of $1.30 to $1.40, excluding discontinued operations, the unrealized gain on commodity derivatives of $8.2 million (after tax) and the natural gas gathering asset impairment of $9.0 million (after tax). Including these adjustments, 2013 GAAP earnings guidance is in the same range. The unrealized commodity derivatives fair value is likely to fluctuate on a quarterly basis, which could cause the GAAP guidance range to change accordingly.
- The Company's long-term compound annual growth goals on earnings per share from operations are in the range of 7 to 10 percent.
- The Company continually seeks opportunities to expand through organic growth and strategic acquisitions.
- The Company focuses on creating value through vertical integration between its business units. For example, the pipeline and energy services business' partially owned diesel topping plant under construction in the Bakken region will have the construction materials and services business involved in constructing the facility, the exploration and production business supplying production to the plant, the pipeline transporting natural gas to the plant, and the utility supplying electricity.

### Electric and natural gas distribution

- The Company filed an application on June 14, 2013, for an advance determination of prudence with the NDPSC to add pollution control equipment at the Lewis & Clark generating station, as discussed in Note 18.
- The Company filed an application December 21, 2012, with the SDPUC for a natural gas rate increase, as discussed in Note 18.
- The Company filed an application September 26, 2012, with the MTPSC for a natural gas rate increase, as discussed in Note 18.
- The EPA approved the South Dakota Regional Haze Program, which requires the Big Stone Station to install and operate a BART air-quality control system to reduce emissions of particulate matter, sulfur dioxide and nitrogen oxides. The Company's share of the cost for the installation is estimated at $100 million and is expected to be complete in 2015. The NDPSC has approved advance determination of prudence for recovery of costs related to this system in electric rates charged to customers. The Company filed an application February 11, 2013, with the NDPSC for approval of an environmental cost recovery rider related to costs for the required environmental retrofit at the Big Stone Station, as discussed in Note 18.
- The Company plans to construct and operate an 88-MW simple-cycle natural gas turbine and associated facilities, with an estimated project cost of $86 million and a projected in-service date in third quarter 2014. It will be located on owned property that is adjacent to the Company's Heskett Generating Station near Mandan, North Dakota. The capacity is necessary to meet the requirements of the Company's integrated electric system customers and will be a partial replacement for third-party contract capacity expiring in 2015. Advance determination of prudence and a Certificate of Public Convenience and Necessity have been received from the NDPSC.
- Planned investments are approximately $75 million for 2013 to serve the growing electric and natural gas customer base associated with the Bakken oil development in western North Dakota and eastern Montana.
- Rate base growth is projected to be approximately 6 percent compounded annually over the next five years.
- The Company is analyzing potential projects for accommodating load growth in its industrial and agricultural sectors, with company- and customer-owned pipeline facilities designed to serve existing facilities served by fuel oil or propane, and to serve new customers. The Company is engaged in a 30-mile natural gas line project into the Hanford Nuclear Site in Washington.
- The Company is involved with a number of pipeline projects to enhance the reliability and deliverability of its system in the Pacific Northwest and Idaho.
- Opportunities associated with the potential development of high-voltage transmission lines and system enhancements targeted toward delivery of energy to major market areas are being pursued.

### Pipeline and energy services

- The Company, in conjunction with Calumet, has formed Dakota Prairie Refining to develop, build and operate a 20,000 barrel-per-day diesel topping plant in southwestern North Dakota. Construction began on the facility in late March 2013 and when complete will process Bakken crude and market the diesel within the Bakken region. Total project costs are estimated to be approximately $300 million, with a projected in-service date in late 2014.
- In May 2012, the Company purchased a 50 percent undivided interest in Whiting Oil and Gas Corporation's Pronghorn natural gas and oil midstream assets near Belfield, North Dakota, in the Bakken area. The Company invested approximately $100 million in 2012 including the purchase price. The Belfield natural gas processing plant has an inlet processing capacity of 35 MMcf per day. The Company will receive a full year of benefit from this acquisition in 2013.
- In August 2012, the Company placed in service approximately 13 miles of high-pressure transmission pipeline from the Stateline processing facilities in northwestern North Dakota to deliver natural gas into the Northern Border Pipeline, which is expected to result in increased transportation volumes for 2013.
- Dry natural gas gathering volumes are expected to be lower in 2013 compared to 2012 because of curtailments and the deferral of development activity by producers.
- The Company has an agreement to construct a pipeline in 2014 to connect the planned Garden Creek II gas processing plant in northwestern North Dakota to deliver natural gas into the Northern Border Pipeline.
- In May 2013, the Company announced plans for a proposed natural gas pipeline from far western North Dakota to western Minnesota to transport natural gas to markets in eastern North Dakota, Minnesota and Wisconsin. The pipeline would initially transport approximately 400 MMcf per day of natural gas and could be expanded to more than 500 MMcf per day. The project investment is estimated to be $650 million to $700 million. Long-term capacity commitments on the proposed pipeline will be sought during an open season expected to begin this fall. Following receipt of adequate capacity commitments and necessary permits and regulatory approvals, construction on the new pipeline would begin in early 2016 with completion expected by late 2016.
- The Company continues to pursue expansion of facilities and services offered to customers. Energy development within its geographic region, which includes portions of Colorado, Montana, North Dakota and Wyoming, is expanding, most notably the Bakken area of North Dakota and eastern Montana. The Company owns an extensive natural gas pipeline system in the Bakken area. Ongoing energy development is expected to have many direct and indirect benefits to this business.

### Exploration and production

- The Company expects to spend approximately $400 million in capital expenditures in 2013. With improving well cost efficiencies and having essentially completed the extensive 2012 exploration program, the capital program will focus on growth projects where the Company expects higher returns, namely the Bakken, Paradox Basin and Texas, as described below. The 2013 planned capital expenditure total does not include potential acquisitions.
- For 2013, the Company expects a 25 to 35 percent increase in oil production, a flat to slight decrease in NGL production, and a 15 to 25 percent decrease in natural gas production. The majority of the capital program is focused on growing oil production considering current relative commodity prices. The Company expects to return to some natural gas development when the commodity prices make it more profitable to do so.
- The Company has a total of four drilling rigs deployed on its acreage in the Bakken, Paradox and Texas areas.
- Bakken areas
- The Company owns a total of approximately 127,000 net acres of leaseholds in Mountrail, Stark and Richland counties.
- Capital expenditures are expected to total approximately $200 million in 2013. During second quarter 2013, the Company operated three rigs in the play and as drilling efficiencies have accelerated, two rigs are now being utilized.
- Net oil production for second quarter 2013, was more than 7,500 BOPD.
- In mid-July 2013, the first three-well pad in Mountrail county began producing. In the first 10 days of production, the pad averaged 2,770 BOPD gross, 1,160 BOPD net. The potential exists for 10 additional multi-well pads in Mountrail county.
- Paradox Basin, Utah
- The Company has approximately 92,000 net acres and also has an option to lease another 20,000 acres.
- Capital expenditures are expected to total $80 million in 2013. The Company expects to operate one rig throughout the year.
- Net oil production for second quarter 2013, was approximately 2,300 BOPD, up 44 percent from first quarter 2013.
- Following nine months of flowing at a constant 1,500 BOPD gross, the CCU 12-1 well recently came off its plateau rate and is still flowing at 1,100 BOPD. The well has flowed over 400 MBO on a cumulative basis and has a forecasted EUR of 1.2 to 1.4 MMBO. This well is amongst the best onshore oil wells drilled in the United States last year.
- The last three wells drilled are the CCU 18-1, CCU 13-1 and the CCU 17-1. The respective gross consistent flowing rates are 900 BOPD, 700 BOPD and 500 BOPD. Respective EURs are forecast at 500 to 700 MBO, 400 to 600 MBO and 400 to 600 MBO.
- The Company's understanding of this play and the quality of the play continues to improve. Accelerated development of the play will be largely dependent upon receiving sufficient permits to sustain a multi-rig program. It is anticipated that this field will play a key role in the Company's oil growth strategy.
- Texas
- The Company is targeting areas that have the potential for higher liquids content with approximately $35 million of capital planned for this year.
- Other opportunities
- Upon evaluation of wells drilled by the Company in Sioux County, Nebraska, the decision was made to decline an option to purchase acreage in the area at this time.
- The remaining forecasted 2013 capital has been allocated to other operated and non-operated opportunities.
- Earnings guidance reflects estimated average NYMEX index prices for August through December in the range of $90.00 to $100.00 per Bbl of crude oil, and $3.50 to $4.00 per Mcf of natural gas. Estimated prices for NGL are in the range of $30.00 to $45.00 per Bbl.
- For the last six months of 2013, the Company has derivative instruments for 11,000 BOPD utilizing swaps and costless collars with a weighted average price of $97.76 and $92.50/$107.03 (floor/ceiling) respectively, and 50,000 MMBtu of natural gas per day, with an additional 10,000 MMBtu per day for September through December, utilizing swaps at a weighted average price of $3.78.
- For the first six months of 2014, the Company has derivative instruments for 8,000 BOPD, and 2,000 BOPD for July through December, utilizing swaps with a weighted average price of $93.43, and for 2014 the Company has derivative instruments for 20,000 MMBtu of natural gas per day utilizing swaps at a weighted average price of $4.13.
- For 2015, the Company has a derivative instrument for 10,000 MMBtu of natural gas per day utilizing a swap at $4.2825.
- The commodity derivative instruments that are in place as of July 31, 2013, are summarized in the following chart:

| Commodity | Type | Index | Period Outstanding | Forward Notional Volume (Bbl/MMBtu) | Price (Per Bbl/MMBtu) |
| --- | --- | --- | --- | ---: | ---: |
| Crude Oil | Collar | NYMEX | 7/13 - 12/13 | 184,000 | $95.00-$117.00 |
| Crude Oil | Collar | NYMEX | 7/13 - 12/13 | 184,000 | $90.00-$97.05 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 92,000 | $95.00 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 92,000 | $95.30 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 92,000 | $100.00 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 92,000 | $100.02 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 184,000 | $102.00 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 184,000 | $104.00 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 184,000 | $98.00 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 92,000 | $94.15 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 92,000 | $94.00 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 184,000 | $97.45 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 184,000 | $94.15 |
| Crude Oil | Swap | NYMEX | 7/13 - 12/13 | 184,000 | $95.00 |
| Crude Oil | Swap | NYMEX | 1/14 - 6/14 | 181,000 | $95.15 |
| Crude Oil | Swap | NYMEX | 1/14 - 6/14 | 181,000 | $95.00 |
| Crude Oil | Swap | NYMEX | 1/14 - 6/14 | 181,000 | $90.00 |
| Crude Oil | Swap | NYMEX | 1/14 - 6/14 | 181,000 | $91.00 |
| Crude Oil | Swap | NYMEX | 1/14 - 6/14 | 181,000 | $92.00 |
| Crude Oil | Swap | NYMEX | 1/14 - 6/14 | 181,000 | $93.00 |
| Crude Oil | Swap | NYMEX | 1/14 - 12/14 | 365,000 | $94.05 |
| Crude Oil | Swap | NYMEX | 1/14 - 12/14 | 365,000 | $95.00 |
| Natural Gas | Swap | NYMEX | 7/13 - 12/13 | 1,840,000 | $3.76 |
| Natural Gas | Swap | NYMEX | 7/13 - 12/13 | 1,840,000 | $3.90 |
| Natural Gas | Swap | NYMEX | 7/13 - 12/13 | 1,840,000 | $4.00 |
| Natural Gas | Swap | NYMEX | 7/13 - 12/13 | 3,680,000 | $3.50 |
| Natural Gas | Swap | NYMEX | 9/13 - 12/14 | 4,870,000 | $4.13 |
| Natural Gas | Swap | NYMEX | 1/14 - 12/14 | 3,650,000 | $4.13 |
| Natural Gas | Swap | NYMEX | 1/15 - 12/15 | 3,650,000 | $4.2825 |

### Construction materials and contracting

- Approximate work backlog as of June 30, 2013, was $730 million, compared to $636 million a year ago. Private work represents 13 percent of construction backlog, up from 8 percent a year ago. Public work represents 87 percent of backlog. The backlog includes a variety of projects such as highway paving projects, airports, bridge work, reclamation and harbor expansions.
- The Company's approximate backlog in North Dakota was $165 million, compared to $83 million a year ago.
- Projected revenues included in the Company's 2013 earnings guidance are in the range of $1.6 billion to $1.7 billion.
- The Company anticipates margins in 2013 to be higher than 2012.
- The Company continues to pursue opportunities for expansion in energy projects such as refineries, transmission, wind towers and geothermal. Initiatives are aimed at capturing additional market share and expanding into new markets.
- As the country's sixth-largest sand and gravel producer, the Company will continue to strategically manage its 1.1 billion tons of aggregate reserves in all its markets, as well as take further advantage of being vertically integrated.
- Of the four labor contracts that Knife River was negotiating, as reported in Items 1 and 2 - Business and Properties - General in the 2012 Annual Report, all have been ratified.

### Construction services

- Approximate work backlog as of June 30, 2013, was $447 million, compared to $344 million a year ago. The backlog includes a variety of projects such as substation and line construction, solar and other commercial, institutional and industrial projects including refinery work.
- The Company has no backlog in North Dakota in 2013, compared to $3 million a year ago.
- Projected revenues included in the Company's 2013 earnings guidance are in the range of $1.0 billion to $1.1 billion.
- The Company anticipates higher workloads and comparable margins in 2013 compared to 2012.
- The Company continues to pursue opportunities for expansion in energy projects such as refineries, transmission, substations, utility services, as well as solar. Initiatives are aimed at capturing additional market share and expanding into new markets.

### NEW ACCOUNTING STANDARDS

For information regarding new accounting standards, see Note 8, which is incorporated by reference.

### CRITICAL ACCOUNTING POLICIES INVOLVING SIGNIFICANT ESTIMATES

The Company's critical accounting policies involving significant estimates include impairment testing of oil and natural gas properties, impairment testing of long-lived assets and intangibles, revenue recognition, pension and other postretirement benefits, and income taxes. There were no material changes in the Company's critical accounting policies involving significant estimates from those reported in the 2012 Annual Report. For more information on critical accounting policies involving significant estimates, see Part II, Item 7 in the 2012 Annual Report.

### LIQUIDITY AND CAPITAL COMMITMENTS

At June 30, 2013, the Company had cash and cash equivalents of $115.0 million and available capacity of $207.8 million under the outstanding credit facilities of the Company and its subsidiaries. The Company expects to meet its obligations for debt maturing within one year from various sources, including internally generated funds; the Company's credit facilities, as described later; and through the issuance of long-term debt and the Company's equity securities.

### Cash flows

***Operating activities*** The changes in cash flows from operating activities generally follow the results of operations as discussed in Financial and Operating Data and also are affected by changes in working capital.

Cash flows provided by operating activities in the first six months of 2013 increased $59.2 million from the comparable period in 2012, primarily due to higher cash flows from operations at the exploration and production business, partially offset by higher working capital requirements at the construction services business. Deferred income taxes decreased largely as a result of higher income taxes payable.

***Investing activities*** Cash flows used in investing activities in the first six months of 2013 decreased $3.1 million from the comparable period in 2012. The decrease was primarily due to lower acquisition-related capital expenditures, primarily at the pipeline and energy services business. Partially offsetting the decrease in cash flows used in investing activities was higher ongoing capital expenditures of $43.0 million, including the diesel topping plant at the pipeline and energy services business, as well as electric generation projects at the electric business.

***Financing activities*** Cash flows provided by financing activities in the first six months of 2013 increased $64.8 million from the comparable period in 2012, primarily due to higher issuance of long-term debt of $150.5 million, largely due to the issuance of $100.0 million of Senior Notes in February 2013; lower dividends paid of $30.7 million resulting from the Company accelerating the payment date for the quarterly common stock dividend from January 1, 2013 to December 31, 2012; as well as higher issuance of short-term borrowings of $29.6 million. Partially offsetting the increase in cash flows provided by financing activities was higher repayment of long-term debt of $155.9 million.

### Defined benefit pension plans

There were no material changes to the Company's qualified noncontributory defined benefit pension plans from those reported in the 2012 Annual Report. For more information, see Note 17 and Part II, Item 7 in the 2012 Annual Report.

### Capital expenditures

Net capital expenditures for the first six months of 2013 were $402.5 million and are estimated to be approximately $850 million for 2013. Estimated capital expenditures include:

- System upgrades
- Routine replacements
- Service extensions
- Routine equipment maintenance and replacements
- Buildings, land and building improvements
- Pipeline, gathering and other midstream projects
- Further development of existing properties, acquisition of additional leasehold acreage and exploratory drilling at the exploration and production segment
- Power generation and transmission opportunities, including certain costs for additional electric generating capacity
- Environmental upgrades
- The Company's proportionate share of the diesel topping plant at the pipeline and energy services segment
- Other growth opportunities

The Company continues to evaluate potential future acquisitions and other growth opportunities; however, they are dependent upon the availability of economic opportunities and, as a result, capital expenditures may vary significantly from the estimated 2013 capital expenditures referred to previously. The Company expects the 2013 estimated capital expenditures to be funded by various sources, including internally generated funds; the Company's credit facilities, as described later; and through the issuance of long-term debt and the Company's equity securities.

### Capital resources

Certain debt instruments of the Company and its subsidiaries, including those discussed later, contain restrictive covenants and cross-default provisions. In order to borrow under the respective credit agreements, the Company and its subsidiaries must be in compliance with the applicable covenants and certain other conditions, all of which the Company and its subsidiaries, as applicable, were in compliance with at June 30, 2013. In the event the Company and its subsidiaries do not comply with the applicable covenants and other conditions, alternative sources of funding may need to be pursued. For additional information on the covenants, certain other conditions and cross-default provisions, see Part II, Item 8 - Note 9, in the 2012 Annual Report.

The following table summarizes the outstanding credit facilities of the Company and its subsidiaries at June 30, 2013:

*(In millions)*

| Company | Facility |  | Facility Limit |  | Amount Outstanding |  | Letters of Credit |  | Expiration Date |
| --- | --- | --- | ---: | --- | ---: | --- | ---: | --- | --- |
| MDU Resources Group, Inc. | Commercial paper/ Revolving credit agreement | (a) | $125.0 |  | $55.5 | (b) | $— |  | 10/4/17 |
| Cascade Natural Gas Corporation | Revolving credit agreement |  | $50.0 | (c) | $31.6 |  | $2.2 | (d) | 7/9/18 |
| Intermountain Gas Company | Revolving credit agreement |  | $65.0 | (e) | $25.4 |  | $— |  | 7/13/18 |
| Centennial Energy Holdings, Inc. | Commercial paper/ Revolving credit agreement | (f) | $500.0 |  | $417.5 | (b) | $— |  | 6/8/17 |
| (a) The $125 million commercial paper program is supported by a revolving credit agreement with various banks totaling $125 million (provisions allow for increased borrowings, at the option of the Company on stated conditions, up to a maximum of $150 million). There were no amounts outstanding under the credit agreement. (b) Amount outstanding under commercial paper program. (c) Certain provisions allow for increased borrowings, up to a maximum of $75 million. (d) The outstanding letter of credit, as discussed in Note 19, reduces the amount available under the credit agreement. (e) Certain provisions allow for increased borrowings, up to a maximum of $90 million. (f) The $500 million commercial paper program is supported by a revolving credit agreement with various banks totaling $500 million (provisions allow for increased borrowings, at the option of Centennial on stated conditions, up to a maximum of $650 million). There were no amounts outstanding under the credit agreement. |  |  |  |  |  |  |  |  |  |

The Company's and Centennial's respective commercial paper programs are supported by revolving credit agreements. While the amount of commercial paper outstanding does not reduce available capacity under the respective revolving credit agreements, the Company and Centennial do not issue commercial paper in an aggregate amount exceeding the available capacity under their credit agreements. The commercial paper borrowings may vary during the period, largely the result of fluctuations in working capital requirements due to the seasonality of the construction businesses.

The following includes information related to the preceding table.

***MDU Resources Group, Inc.*** The Company's revolving credit agreement supports its commercial paper program. Commercial paper borrowings under this agreement are classified as long-term debt as they are intended to be refinanced on a long-term basis through continued commercial paper borrowings. The Company's objective is to maintain acceptable credit ratings in order to access the capital markets through the issuance of commercial paper. Downgrades in the Company's credit ratings have not limited, nor are currently expected to limit, the Company's ability to access the capital markets. If the Company were to experience a downgrade of its credit ratings, it may need to borrow under its credit agreement and may experience an increase in overall interest rates with respect to its cost of borrowings.

Prior to the maturity of the credit agreement, the Company expects that it will negotiate the extension or replacement of this agreement. If the Company is unable to successfully negotiate an extension of, or replacement for, the credit agreement, or if the fees on this facility become too expensive, which the Company does not currently anticipate, the Company would seek alternative funding.

Due to the $246.8 million after-tax noncash write-downs of oil and natural gas properties in 2012, earnings were insufficient by $19.8 million and $51.2 million to cover fixed charges for the 12 months ended June 30, 2013 and December 31, 2012, respectively. If the $246.8 million after-tax noncash write-downs were excluded, the coverage of fixed charges including preferred stock dividends would have been 4.5 times and 4.4 times for the 12 months ended June 30, 2013 and December 31, 2012, respectively.

The coverage of fixed charges including preferred stock dividends, that excludes the effect of the after-tax noncash write-downs of oil and natural gas properties is a non-GAAP financial measure. The Company believes that this non-GAAP financial measure is useful because the write-downs excluded are not indicative of the Company's cash flows available to meet its fixed charges obligations. The presentation of this additional information is not meant to be considered a substitute for the financial measure prepared in accordance with GAAP.

Total equity as a percent of total capitalization was 57 percent, 63 percent and 60 percent at June 30, 2013 and 2012 and December 31, 2012, respectively. This ratio is calculated as the Company's total equity, divided by the Company's total capital. Total capital is the Company's total debt, including short-term borrowings and long-term debt due within one year, plus total equity. This ratio indicates how a company is financing its operations, as well as its financial strength.

The Company currently has a shelf registration statement on file with the SEC, under which the Company may issue and sell any combination of common stock and debt securities. The Company may sell all or a portion of such securities if warranted by market conditions and the Company's capital requirements. Any public offer and sale of such securities will be made only by means of a prospectus meeting the requirements of the Securities Act and the rules and regulations thereunder. The Company's board of directors currently has authorized the issuance and sale of up to an aggregate of $1.0 billion worth of such securities. The Company's board of directors reviews this authorization on a periodic basis and the aggregate amount of securities authorized may be increased in the future.

***Cascade Natural Gas Corporation*** On July 9, 2013, Cascade entered into a revolving credit agreement which replaces the existing revolving credit agreement and extends the termination date to July 9, 2018. The credit agreement contains customary covenants and provisions, including a covenant of Cascade not to permit, at any time, the ratio of total debt to total capitalization to be greater than 65 percent. Other covenants include restrictions on the sale of certain assets, limitations on indebtedness and the making of certain investments.

Cascade's credit agreement also contains cross-default provisions. These provisions state that if Cascade fails to make any payment with respect to any indebtedness or contingent obligation, in excess of a specified amount, under any agreement that causes such indebtedness to be due prior to its stated maturity or the contingent obligation to become payable, Cascade will be in default under the revolving credit agreement.

***Intermountain Gas Company*** On July 15, 2013, Intermountain entered into a revolving credit agreement which replaces the existing revolving credit agreement and extends the termination date to July 13, 2018. The credit agreement contains customary covenants and provisions, including a covenant of Intermountain not to permit, at any time, the ratio of total debt to total capitalization to be greater than 65 percent. Other covenants include restrictions on the sale of certain assets, limitations on indebtedness and the making of certain investments.

Intermountain's credit agreement also contains cross-default provisions. These provisions state that if Intermountain fails to make any payment with respect to any indebtedness or contingent obligation, in excess of a specified amount, under any agreement that causes such indebtedness to be due prior to its stated maturity or the contingent obligation to become payable, or certain conditions result in an early termination date under any swap contract that is in excess of a specified amount, then Intermountain will be in default under the revolving credit agreement.

***Centennial Energy Holdings, Inc.*** Centennial's revolving credit agreement supports its commercial paper program. Commercial paper borrowings under this agreement are classified as long-term debt as they are intended to be refinanced on a long-term basis through continued commercial paper borrowings. Centennial's objective is to maintain acceptable credit ratings in order to access the capital markets through the issuance of commercial paper. Downgrades in Centennial's credit ratings have not limited, nor are currently expected to limit, Centennial's ability to access the capital markets. If Centennial were to experience a downgrade of its credit ratings, it may need to borrow under its credit agreement and may experience an increase in overall interest rates with respect to its cost of borrowings.

Prior to the maturity of the Centennial credit agreement, Centennial expects that it will negotiate the extension or replacement of this agreement, which provides credit support to access the capital markets. In the event Centennial is unable to successfully negotiate this agreement, or in the event the fees on this facility become too expensive, which Centennial does not currently anticipate, it would seek alternative funding.

Centennial entered into a note purchase agreement on June 27, 2013, and issued $50.0 million of Senior Notes with due dates ranging from June 2023 to June 2028 at a weighted average interest rate of 4.7 percent. Centennial contracted to issue an additional $25.0 million of Senior Notes under the agreement on November 1, 2013.

### Off balance sheet arrangements

In connection with the sale of the Brazilian Transmission Lines, Centennial has agreed to guarantee payment of any indemnity obligations of certain of the Company's indirect wholly owned subsidiaries who are the sellers in three purchase and sale agreements for periods ranging up to 10 years from the date of sale. The guarantees were required by the buyers as a condition to the sale of the Brazilian Transmission Lines.

Centennial continues to guarantee CEM's obligations under a construction contract for an electric generating facility near Hobbs, New Mexico. For more information, see Note 19.

### Contractual obligations and commercial commitments

There are no material changes in the Company's contractual obligations relating to estimated interest payments, operating leases, purchase commitments, derivatives, asset retirement obligations and minimum funding requirements for its defined benefit plans for 2013 from those reported in the 2012 Annual Report.

The Company's contractual obligations relating to long-term debt at June 30, 2013 increased $261.8 million or 15 percent from December 31, 2012. As of June 30, 2013, the Company's contractual obligations related to long-term debt aggregated $2,006.8 million. The scheduled amounts of redemption (for the twelve months ended June 30, of each year listed) aggregate $69.1 million in 2014; $57.2 million in 2015; $404.2 million in 2016; $533.5 million in 2017; $118.4 million in 2018; and $824.4 million thereafter.

For more information on the Company's uncertain tax positions, see Note 15.

For more information on contractual obligations and commercial commitments, see Part II, Item 7 in the 2012 Annual Report.

## Market risk

As filed, 2,173 characters.

The Company is exposed to the impact of market fluctuations associated with commodity prices, interest rates and foreign currency. The Company has policies and procedures to assist in controlling these market risks and utilizes derivatives to manage a portion of its risk.

For more information on derivative instruments and commodity price risk, see Part II, Item 7A in the 2012 Annual Report, the Consolidated Statements of Comprehensive Income and Note 13.

### Commodity price risk

Fidelity utilizes derivative instruments to manage a portion of the market risk associated with fluctuations in the price of oil and natural gas and basis differentials on forecasted sales of oil and natural gas production.

The following table summarizes derivative agreements entered into by Fidelity as of June 30, 2013. These agreements call for Fidelity to receive fixed prices and pay variable prices.

*(Forward notional volume and fair value in thousands)*

|  | Weighted Average Fixed Price (Per Bbl/MMBtu) | Forward Notional Volume (Bbl/MMBtu) | Fair Value |
| --- | ---: | ---: | ---: |
| Oil swap agreements maturing in 2013 | $97.76 | 1,656 | $4,347 |
| Oil swap agreements maturing in 2014 | $92.69 | 1,086 | $1,476 |
| Natural gas swap agreements maturing in 2013 | $3.78 | 10,420 | $1,157 |
| Natural gas swap agreements maturing in 2014 | $4.13 | 7,300 | $1,845 |
| Natural gas swap agreement maturing in 2015 | $4.28 | 3,650 | $518 |
|  | Weighted Average Floor/Ceiling Price (Per Bbl) | Forward Notional Volume (Bbl) | Fair Value |
| Oil collar agreements maturing in 2013 | $92.50/$107.03 | 368 | $513 |

### Interest rate risk

There were no material changes to interest rate risk faced by the Company from those reported in the 2012 Annual Report.

At June 30, 2013, the Company had no outstanding interest rate hedges.

### Foreign currency risk

The Company's equity method investment in ECTE is exposed to market risks from changes in foreign currency exchange rates between the U.S. dollar and the Brazilian Real. For more information, see Part II, Item 8 - Note 4 in the 2012 Annual Report.

At June 30, 2013, the Company had no outstanding foreign currency hedges.

## Controls and procedures

As filed, 1,866 characters.

The following information includes the evaluation of disclosure controls and procedures by the Company's chief executive officer and the chief financial officer, along with any significant changes in internal controls of the Company.

### Evaluation of disclosure controls and procedures

The term "disclosure controls and procedures" is defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act. The Company's disclosure controls and other procedures are designed to provide reasonable assurance that information required to be disclosed in the reports that the Company files or submits under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC's rules and forms. The Company's disclosure controls and procedures include controls and procedures designed to provide reasonable assurance that information required to be disclosed is accumulated and communicated to management, including the Company's chief executive officer and chief financial officer, to allow timely decisions regarding required disclosure. The Company's management, with the participation of the Company's chief executive officer and chief financial officer, has evaluated the effectiveness of the Company's disclosure controls and procedures. Based upon that evaluation, the chief executive officer and the chief financial officer have concluded that, as of the end of the period covered by this report, such controls and procedures were effective at a reasonable assurance level.

### Changes in internal controls

No change in the Company's internal control over financial reporting (as defined in Rules 13a-15(f) and 15d-15(f) under the Exchange Act) occurred during the quarter ended June 30, 2013, that has materially affected, or is reasonably likely to materially affect, the Company's internal control over financial reporting.

## Risk factors

As filed, 13,062 characters.

This Form 10-Q contains forward-looking statements within the meaning of Section 21E of the Exchange Act. Forward-looking statements are all statements other than statements of historical fact, including without limitation those statements that are identified by the words "anticipates," "estimates," "expects," "intends," "plans," "predicts" and similar expressions.

The Company is including the following factors and cautionary statements in this Form 10-Q to make applicable and to take advantage of the safe harbor provisions of the Private Securities Litigation Reform Act of 1995 for any forward-looking statements made by, or on behalf of, the Company. Forward-looking statements include statements concerning plans, objectives, goals, strategies, future events or performance, and underlying assumptions (many of which are based, in turn, upon further assumptions) and other statements that are other than statements of historical facts. From time to time, the Company may publish or otherwise make available forward-looking statements of this nature, including statements contained within Prospective Information. All these subsequent forward-looking statements, whether written or oral and whether made by or on behalf of the Company, also are expressly qualified by these factors and cautionary statements.

Forward-looking statements involve risks and uncertainties, which could cause actual results or outcomes to differ materially from those expressed. The Company's expectations, beliefs and projections are expressed in good faith and are believed by the Company to have a reasonable basis, including without limitation, management's examination of historical operating trends, data contained in the Company's records and other data available from third parties. Nonetheless, the Company's expectations, beliefs or projections may not be achieved or accomplished.

Any forward-looking statement contained in this document speaks only as of the date on which the statement is made, and the Company undertakes no obligation to update any forward-looking statement or statements to reflect events or circumstances that occur after the date on which the statement is made or to reflect the occurrence of unanticipated events. New factors emerge from time to time, and it is not possible for management to predict all of the factors, nor can it assess the effect of each factor on the Company's business or the extent to which any factor, or combination of factors, may cause actual results to differ materially from those contained in any forward-looking statement.

There are no material changes in the Company's risk factors from those reported in Part I, Item 1A - Risk Factors in the 2012 Annual Report other than the risk associated with the regulatory approval, permitting, construction, startup and/or operation of power generation facilities and the diesel topping plant; the risk related to environmental laws and regulations; and the risk associated with company operations that could be adversely impacted by global climate change initiatives to reduce GHG emissions. These factors and the other matters discussed herein are important factors that could cause actual results or outcomes for the Company to differ materially from those discussed in the forward-looking statements included elsewhere in this document.

### Economic Risks

***The regulatory approval, permitting, construction, startup and/or operation of power generation facilities and the diesel topping plant may involve unanticipated events or delays that could negatively impact the Company's business and its results of operations and cash flows.***

The construction, startup and operation of power generation facilities and the diesel topping plant involve many risks, which may include: delays; breakdown or failure of equipment; inability to obtain required governmental permits and approvals; inability to complete financing; inability to negotiate acceptable equipment acquisition, construction, fuel and crude oil supply, off-take, transmission, transportation or other material agreements; changes in markets and market prices for power, crude oil and refined products; cost increases; as well as the risk of performance below expected levels of output or efficiency. Such unanticipated events could negatively impact the Company's business, its results of operations and cash flows.

In March 2013, construction began on Dakota Prairie Refinery, which has a targeted in-service date in late 2014. The previously mentioned risks could negatively affect the results of operations and cash flows of the pipeline and energy services segment.

### Environmental Risks

***The Company's operations are subject to environmental laws and regulations that may increase costs of operations, impact or limit business plans, or expose the Company to environmental liabilities.***

The Company is subject to environmental laws and regulations affecting many aspects of its present and future operations, including air quality, water quality, waste management and other environmental considerations. These laws and regulations can result in increased capital, operating and other costs, cause delays as a result of litigation and administrative proceedings, and create compliance, remediation, containment, monitoring and reporting obligations, particularly with regard to laws relating to electric generation operations and oil and natural gas development. These laws and regulations generally require the Company to obtain and comply with a wide variety of environmental licenses, permits, inspections and other approvals. Although the Company strives to comply with all applicable environmental laws and regulations, public and private entities, as well as private individuals, may seek injunctive relief or other remedies to enforce applicable environmental laws and regulations with which they have differing interpretations of the Company's legal or regulatory compliance. The Company cannot predict the outcome (financial or operational) of any related litigation or administrative proceedings that may arise.

Existing environmental laws and regulations may be revised and new laws and regulations seeking to protect the environment may be adopted or become applicable to the Company. These laws and regulations could require the Company to limit the use or output of certain facilities, restrict the use of certain fuels, install pollution controls, remediate environmental contamination, remove or reduce environmental hazards, or prevent or limit the development of resources. Revised or additional laws and regulations that result in increased compliance costs or additional operating restrictions, particularly if those costs are not fully recoverable from customers, could have a material adverse effect on the Company's results of operations and cash flows.

The EPA has issued draft regulations that outline several possible approaches for coal combustion residuals management under the RCRA. One approach, designating coal ash as a hazardous waste, would significantly change the manner and increase the costs of managing coal ash at five plants that supply electricity to customers of Montana-Dakota. This designation also could significantly increase costs for Knife River, which beneficially uses fly ash as a cement replacement in ready-mixed concrete and road base applications.

In December 2011, the EPA finalized the Mercury and Air Toxics rule that will require reductions in mercury and other air emissions from coal- and oil-fired electric utility steam generating units. Montana-Dakota evaluated the pollution control technologies needed at its electric generation resources to comply with this final rule and determined that additional particulate matter control is required to control non-mercury metal emissions at the Lewis & Clark Station near Sidney, Montana. Controls must be installed by April 16, 2015, or April 16, 2016, if a one-year extension is granted for installation.

Hydraulic fracturing is an important common practice used by Fidelity that involves injecting water; sand; guar, a water thickening agent; and trace amounts of chemicals under pressure into rock formations to stimulate oil, NGL and natural gas production. Fidelity is following state regulations for well drilling and completion, including regulations related to hydraulic fracturing and disposing of recovered fluids. Fracturing fluid constituents are reported on state or national websites. The EPA is developing a study to review the potential effects of hydraulic fracturing on underground sources of drinking water; the results of that study could impact future legislation or regulation. The BLM has released draft well stimulation regulations for hydraulic fracturing operations. If implemented, the BLM regulations would only affect Fidelity's operations on BLM-administered lands. If adopted as proposed, the BLM regulations, along with other legislative initiatives and regulatory studies, proceedings or initiatives at federal or state agencies that focus on the hydraulic fracturing process, could result in additional compliance, reporting and disclosure requirements. Future legislation or regulation could increase compliance and operating costs, as well as delay or inhibit the Company's ability to develop its oil, NGL and natural gas reserves.

On August 16, 2012, the EPA published a final NSPS rule for the oil and natural gas industry. The NSPS rule phases in over two years. The first phase was effective October 15, 2012, and primarily covers natural gas wells that are hydraulically fractured. Under the new rule, gas vapors or emissions from the natural gas wells must be captured or combusted utilizing a high efficiency device. Additional reporting requirements and control devices covering oil and natural gas production equipment will be phased in for certain new oil and gas facilities with a final effective date of January 1, 2015. This new rule's impacts on Fidelity, WBI Energy Transmission and WBI Energy Midstream are not expected to be material and are likely to include implementation of recordkeeping, reporting and testing requirements and the acquisition and installation of required equipment.

***Initiatives to reduce GHG emissions could adversely impact the Company's operations.***

Concern that GHG emissions are contributing to global climate change has led to international, federal and state legislative and regulatory proposals to reduce or mitigate the effects of GHG emissions. On June 25, 2013, President Obama released his Climate Action Plan for the U.S. in which he states his goal to reduce GHG emissions "in the range of 17 percent" below 2005 levels by 2020. The president issued a memorandum to the EPA on the same day, instructing the EPA to re-propose the GHG NSPS rule for new electric generation units no later than September 20, 2013. This new rule will take the place of the rule proposed in 2012 for new electric generation units that the EPA did not finalize. The president also directed the EPA to develop a GHG NSPS standard for existing fossil fuel-fired electric generation units by June 1, 2014, with finalization by June 1, 2015. The president did not specify a GHG standard or the format of the standard.

The primary GHG emitted from the Company's operations is carbon dioxide from combustion of fossil fuels at Montana-Dakota's electric generating facilities, particularly its coal-fired facilities. Approximately 70 percent of Montana-Dakota's owned generating capacity and more than 90 percent of the electricity it generates is from coal-fired facilities. Montana-Dakota also owns approximately 100 MW of natural gas- and oil-fired peaking plants.

Montana-Dakota's existing electric generating facilities are expected to be subject to GHG laws or regulations within the next few years through a GHG NSPS for existing and modified units. Implementation of treaties, legislation or regulations to reduce GHG emissions could affect Montana-Dakota's electric utility operations by requiring expanded energy conservation efforts or increased development of renewable energy sources, as well as other mandates that could significantly increase capital expenditures and operating costs. If Montana-Dakota does not receive timely and full recovery of GHG emission compliance costs from its customers, then such costs could have an adverse impact on the results of its operations.

In addition to Montana-Dakota's electric generation operations, the GHG emissions from the Company's other operations are monitored, analyzed and reported as required in accordance with applicable laws and regulations. The Company monitors the development of GHG regulations and the potential for GHG regulations to impact all existing and future operations.

Due to the uncertain availability of technologies to control GHG emissions and the unknown obligations that potential GHG emission legislation or regulations may create, the Company cannot determine the potential financial impact on its operations.

Filed Aug 7, 2013.
Source: SEC EDGAR, the filing index for accession 0000067716-13-000101. Last ingested by Listed: Nov 24, 2026, 18:23 ET. No prices; not investment advice.