# Tutor Perini Corp: Form 10-Q for the period ended Jun 30, 2015

- Company: [Tutor Perini Corp](/companies/tpc.md) (CIK 77543)
- Form: 10-Q
- Filed: 2015-08-06
- Accepted by EDGAR: Aug 6, 2015, 17:06 ET
- Period: 2015-06-30
- Accession: 0000077543-15-000050
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/77543/000007754315000050/tpc-20150630x10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/77543/000007754315000050/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2015-06-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Gross profit | 3 months, 2015-04-01 to 2015-06-30 | $98.6m | us-gaap:GrossProfit |
| Gross profit | 6 months, 2015-01-01 to 2015-06-30 | $189.4m | us-gaap:GrossProfit |
| Operating income | 3 months, 2015-04-01 to 2015-06-30 | $30.9m | us-gaap:OperatingIncomeLoss |
| Operating income | 6 months, 2015-01-01 to 2015-06-30 | $51.0m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2015-04-01 to 2015-06-30 | $11.0m | us-gaap:InterestExpense |
| Interest expense | 6 months, 2015-01-01 to 2015-06-30 | $22.1m | us-gaap:InterestExpense |
| Income tax | 3 months, 2015-04-01 to 2015-06-30 | $8.2m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 6 months, 2015-01-01 to 2015-06-30 | $11.3m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2015-04-01 to 2015-06-30 | $11.8m | us-gaap:NetIncomeLoss |
| Net income | 6 months, 2015-01-01 to 2015-06-30 | $16.9m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2015-04-01 to 2015-06-30 | $0.24 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 6 months, 2015-01-01 to 2015-06-30 | $0.34 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2015-04-01 to 2015-06-30 | $0.24 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 6 months, 2015-01-01 to 2015-06-30 | $0.35 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2015-04-01 to 2015-06-30 | 49,828,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 6 months, 2015-01-01 to 2015-06-30 | 49,688,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 6 months, 2015-01-01 to 2015-06-30 | −$31.8m | us-gaap:NetCashProvidedByUsedInOperatingActivitiesContinuingOperations |
| Capital expenditure | 6 months, 2015-01-01 to 2015-06-30 | $29.5m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | at 2015-06-30 | $106.9m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2015-06-30 | $2.64bn | us-gaap:AssetsCurrent |
| Total assets | at 2015-06-30 | $3.94bn | us-gaap:Assets |
| Current liabilities | at 2015-06-30 | $1.48bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2015-06-30 | $2.55bn | us-gaap:Liabilities |
| Long-term debt | at 2015-06-30 | $806.7m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2015-06-30 | $86.1m | us-gaap:LongTermDebtCurrent |
| Shareholders' equity | at 2015-06-30 | $1.39bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 35,673 characters.

The following discusses our financial position at June 30, 2015 and the results of our operations for the three and six months ended June 30, 2015 and should be read in conjunction with: (1) the unaudited consolidated condensed financial statements and notes contained herein, and (2) the audited consolidated financial statements and accompanying notes to our Annual Report on Form 10-K for the fiscal year ended December 31, 2014.

### Overview

We were incorporated in 1918 as a successor to businesses that had been engaged in providing construction services since 1894. We provide diversified general contracting, construction management and design-build services to private customers and public agencies throughout the world. Our construction business is conducted through three basic segments or operations: Civil, Building, and Specialty Contractors. Our Civil segment specializes in public works construction and the repair, replacement and reconstruction of infrastructure, including highways, bridges, mass-transit systems and water and wastewater treatment facilities, primarily in the western, midwestern, northeastern, and mid-Atlantic regions of the United States. Our Building segment has significant experience providing services to a number of specialized building markets, including the hospitality and gaming, transportation, healthcare, municipal and commercial offices, sports and entertainment, educational, correctional facilities, biotech, pharmaceutical and high-tech markets. Our Specialty Contractors segment specializes in plumbing, HVAC, electrical, mechanical, and pneumatically placed concrete for a full range of civil and building construction projects in the industrial, commercial, hospitality and gaming, and transportation end markets, among others.

The contracting and management services that we provide consist of general contracting, pre-construction planning and comprehensive management services, including planning and scheduling the manpower, equipment, materials and subcontractors required for the timely completion of a project in accordance with the terms and specifications contained in a construction contract. We also offer self-performed construction services including site work, concrete forming and placement, steel erection, electrical, mechanical, plumbing, and HVAC. We provide these services by using traditional general contracting arrangements, such as fixed price, guaranteed maximum price and cost plus fee contracts and, to a lesser extent, construction management or design-build contracting arrangements. We occasionally enter into joint venture arrangements with other contractors for certain construction projects. Each of the joint venture participants is usually committed to supply a predetermined percentage of capital, as required, and to share in a predetermined percentage of the income or loss of the project. Generally, each joint venture participant is fully liable for the obligations of the joint venture.

We believe our leadership position as the contractor of choice for large, complex civil and building projects will support our long-term backlog growth. We continue to strategically focus on growing our business by pursuing and obtaining higher-margin public works projects and building projects on an opportunistic basis. In addition, we continue to leverage our unique, substantial self-performance and schedule control capabilities to obtain additional large-scale civil and building awards. We have capitalized on this leadership position and these synergies with various recent significant new awards and pending awards (see *Backlog Analysis* on page 34).

The following tables set forth our consolidated condensed statement of operations:

*(In thousands)*

*(In thousands)*

|  | Consolidated Results of Operations Three Months Ended June 30, 2015 | 2014 | % Change Favorable (Unfavorable) 2015 vs 2014 | Six Months Ended June 30, 2015 | 2014 | % Change Favorable (Unfavorable) 2015 vs 2014 |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $1,312,438 | $1,084,510 | 21.0% | $2,378,903 | $2,039,743 | 16.6% |
| Cost of operations | 1,213,818 | 954,979 | (27.1)% | 2,189,524 | 1,804,865 | (21.3)% |
| Gross profit | 98,620 | 129,531 | (23.9)% | 189,379 | 234,878 | (19.4)% |
| General and administrative expenses | 67,739 | 64,088 | (5.7)% | 138,414 | 127,938 | (8.2)% |
| Income from construction operations | 30,881 | 65,443 | (52.8)% | 50,965 | 106,940 | (52.3)% |
| Other income (expense), net | 100 | (6,974) | 101.4% | (655) | (10,347) | 93.7% |
| Interest expense | (10,989) | (10,857) | (1.2)% | (22,113) | (21,688) | (2.0)% |
| Income before income taxes | 19,992 | 47,612 | (58.0)% | 28,197 | 74,905 | (62.4)% |
| Provision for income taxes | (8,215) | (19,067) | 56.9% | (11,294) | (30,421) | 62.9% |
| Net income (loss) | $11,777 | $28,545 | (58.7)% | $16,903 | $44,484 | (62.0)% |

|  | Consolidated Results of Operations Three Months Ended June 30, 2015 (As a percentage of Revenues) | 2014 | Six Months Ended June 30, 2015 (As a percentage of Revenues) | 2014 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | 100.0% | 100.0% | 100.0% | 100.0% |
| Cost of operations | 92.5% | 88.1% | 92.0% | 88.5% |
| Gross profit | 7.5% | 11.9% | 8.0% | 11.5% |
| General and administrative expenses | 5.2% | 5.9% | 5.8% | 6.3% |
| Income from construction operations | 2.4% | 6.0% | 2.1% | 5.2% |
| Other income (expense), net | 0.0% | (0.6)% | (0.0)% | (0.5)% |
| Interest expense | (0.8)% | (1.0)% | (0.9)% | (1.1)% |
| Income (loss) before income taxes | 1.5% | 4.4% | 1.2% | 3.6% |
| (Provision) benefit for income taxes | (0.6)% | (1.8)% | (0.5)% | (1.5)% |
| Net income (loss) | 0.9% | 2.6% | 0.7% | 2.1% |

Revenues were $1,312.4 million and $2,378.9 million for the three and six months ended June 30, 2015 compared to $1,084.5 million and $2,039.7 million for the same periods in 2014. Income from construction operations was $30.9 million and $51.0 million for the three and six months ended June 30, 2015 compared to $65.4 million and $106.9 million for the same periods in 2014. Net income for the three and six months ended June 30, 2015 was $11.8 million and $16.9 million compared to $28.5 million and $44.5 million for the same periods in 2014. Basic and diluted earnings per share (“EPS”) were both $0.24 for the three months ended June 30, 2015, compared to basic and diluted EPS of $0.59 and $0.58 for the same period in 2014. Basic and diluted EPS were $0.35 and $0.34 for the six months ended June 30, 2015, compared to basic and diluted EPS of $0.92 and $0.91 for the same period in 2014.

Revenues increased approximately $227.9 million, or 21.0%, and $339.2 million, or 16.6%, during the three and six months ended June 30, 2015 compared to the same periods in 2014. The increase was due primarily to increased activity on a runway reconstruction project in New York, various bridge projects in the Midwest, mass-transit projects in New York and California, various building projects in California, and hospitality and gaming projects in Mississippi and California. The increase was partially offset by decreased activity on various smaller electrical projects in the southern U.S. and certain tunnel projects on the West Coast.

The decrease in net income for the three and six months ended June 30, 2015 compared to the same periods in 2014, was due primarily to a combination of net favorable adjustments to the estimated recoveries on two Civil projects in the second quarter of 2014 and an unfavorable adjustment in the second quarter of 2015 to the estimated cost to complete for an office building project on the East Coast. To a lesser extent, the decrease was also due to the decreased activity on certain tunnel projects on the West Coast and certain higher-margin projects.

At June 30, 2015, working capital was $1,158.7 million, an increase of $44.7 million from $1,114.0 million at December 31, 2014.

### Backlog Analysis

Our backlog of uncompleted construction work at June 30, 2015 was approximately $7.7 billion compared to $7.8 billion at December 31, 2014. During the first six months of 2015, we booked various new awards and adjustments to existing contracts into backlog across each of our business segments. Significant new awards and adjustments included $455 million of initial funding for a technology research and development facility project and $72 million of incremental funding for a biotechnology facility project in California; a $239 million hospitality building project, a $117 million mixed-use building project, and a $58 million highway improvement project in Pennsylvania; three electrical projects totaling $97 million and a $56 million tunnel project in New York; and a $50 million educational building project in Mississippi.

In addition to our existing backlog, we continue to have a significant volume of pending contract awards, including up to $2.3 billion in various future phases of the Hudson Yards project, approximately $1.0 billion for five building projects in California, and approximately $1.0 billion in various other contracts. We anticipate booking many of these and other pending awards into backlog over the next several quarters. We continue tracking several large-scale civil and building prospects for both public and private sector customers as we further leverage our self-performance and schedule control capabilities.

The following table provides an analysis of our backlog by business segment for June 30, 2015:

*(in millions)*

|  | Backlog at December 31, 2014 | New Business Awarded (a) | Revenues Recognized | Backlog at June 30, 2015 |
| --- | ---: | ---: | ---: | ---: |
| Civil | $3,563.2 | $474.3 | $(908.9) | $3,128.6 |
| Building | 2,187.8 | 1,145.6 | (850.2) | 2,483.2 |
| Specialty Contractors | 2,080.7 | 676.8 | (619.8) | 2,137.7 |
| Total | $7,831.7 | $2,296.7 | $(2,378.9) | $7,749.5 |

(a) New business awarded consists of the original contract price of projects added to our backlog plus or minus subsequent changes to the estimated total contract price of existing contracts.

### Critical Accounting Policies

Our significant accounting policies are described in Note 1 — *Description of Business and Summary of Significant Accounting Policies* of the Notes to Consolidated Financial Statements in Part IV, Item 15. *Exhibits and Financial Statement Schedules*, included in our Annual Report on Form 10-K for the fiscal year ended December 31, 2014. Our critical accounting policies are also identified and discussed in Item 7. *Management’s Discussion and Analysis of Financial Condition and Results of Operations* of our Annual Report on Form 10-K for the fiscal year ended December 31, 2014.

### Recently Issued Accounting Pronouncements

In May 2014, the FASB issued Accounting Standards Update (“ASU”) ASU No. 2014-09, *Revenue from Contracts with Customers (Topic 606),* which supersedes the revenue recognition requirements in ASC 605, *Revenue Recognition*. This ASU addresses when an entity should recognize revenue to depict the transfer of promised goods or services to customers in an amount that reflects the consideration to which the entity expects to be entitled in exchange for those goods or services. In July 2015, FASB delayed the effective date by one year and is effective for annual reporting periods beginning after December 15, 2017, including interim periods within that reporting period, using one of two retrospective application methods. Early application would be permitted only as of annual reporting periods beginning after December 15, 2016, including interim periods within that reporting period. The Company is currently evaluating the effect that the adoption of this ASU will have on its financial statements.

In June 2014, the FASB issued ASU No. 2014-12, *Compensation — Stock Compensation (Topic 718): Accounting for Share-Based Payments When the Terms of an Award Provide That a Performance Target Could Be Achieved after the Requisite Service Period*, clarifying the recognition timing of expense associated with certain performance based stock awards when the performance target that affects vesting could be achieved after the requisite service period. This ASU is an update to FASB ASC Topic 718 and is effective for fiscal years, and interim periods within those years, beginning after December 15, 2015 with earlier adoption permitted. The adoption of this guidance is not expected to have a material impact on the Company’s financial statements.

In February 2015, the FASB issued ASU No. 2015-02, *Consolidation (Topic 810)*. The goal of this ASU is to reduce the potentially distortive impact on reporting entities’ consolidated financial statements resulting from the consolidation of certain legal entities, including joint ventures and variable interest entities. This ASU is effective for fiscal years, and interim periods within those years, beginning after December 15, 2015. The adoption of this guidance is not expected to have a material impact on the Company’s financial statements.

In April 2015, the FASB issued ASU 2015-03, *Interest – Imputation of Interest (Subtopic 835-30).* This ASU requires that debt issuance costs related to a recognized debt liability be presented in the balance sheet as a direct deduction from the carrying amount of that debt liability, consistent with debt discounts. This ASU is effective for fiscal years, and interim periods within those years, beginning after December 15, 2015. The adoption of this ASU is not expected to have a material impact on the Company’s financial statements.

### Use of and changes in estimates

The Company’s construction business involves making significant estimates and assumptions in the normal course of business relating to its contracts and its joint venture contracts. Management focuses on evaluating the performance of contracts individually. These estimates can vary in the normal course of business as projects progress, when estimated productivity assumptions change based on experience to date and uncertainties are resolved. Change orders and claims, as well as changes in related estimates of costs to complete, are considered revisions in estimates. The Company uses the cumulative catch-up method applicable to construction contract accounting to account for revisions in estimates. The impact on operating margin in a reporting period and future periods from a change in estimate will depend on the stage of contract completion.

During the three months ended June 30, 2015, the Company’s results of operations were negatively impacted because of an unfavorable change in the estimated cost to complete for a certain Building segment project. This change in estimate resulted in a $14.7 million decrease in income from construction operations, an $8.7 million decrease in net income, and a $0.17 decrease in diluted EPS during the three months ended June 30, 2015.

During the three months ended June 30, 2014, the Company’s results of operations were positively impacted by a net $14.8 million because of changes in the estimated cost recovery on two Civil segment projects based on certain legal rulings issued during the period. One project had a favorable ruling, resulting in a $24.2 million increase, and the second project had an unfavorable ruling, resulting in a $9.4 million decrease. Together, these changes in estimates resulted in a $14.8 million increase in income from construction operations, an $8.8 million increase in net income, and an $0.18 increase in diluted EPS during the three and six months ended June 30, 2014.

These changes were the only changes in estimates considered material to the Company’s results of operations during the periods presented herein.

### Results of Operations

### Comparison of the Three and Six Months Ended June 30, 2015 with the Three and Six Months Ended June 30, 2014

### Revenues

The following table summarizes our revenues by business segment with the prior year.

*(dollars in millions)*

|  | Revenues for the Three Months Ended June 30, 2015 | 2014 | $ Change | % Change |
| --- | ---: | ---: | ---: | ---: |
| Civil | $534.2 | $390.5 | $143.7 | 36.8% |
| Building | 451.4 | 372.0 | 79.4 | 21.3% |
| Specialty Contractors | 326.8 | 322.0 | 4.8 | 1.5% |
| Total | $1,312.4 | $1,084.5 | $227.9 | 21.0% |
|  | **Revenues for the** |  |  |  |
|  | **Six Months Ended June 30,** |  |  |  |
| **(dollars in millions)** | **2015** | **2014** | **$ Change** | **% Change** |
| Civil | $908.9 | $755.7 | $153.2 | 20.3% |
| Building | 850.2 | 669.9 | 180.3 | 26.9% |
| Specialty Contractors | 619.8 | 614.1 | 5.7 | 0.9% |
| Total | $2,378.9 | $2,039.7 | $339.2 | 16.6% |

35

#### Civil Segment

Civil segment revenues increased $143.7 million, or 36.8%, and 153.2 million, or 20.3%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The increase was due primarily to increased activity on a runway reconstruction project in New York, various bridge projects in the Midwest, and mass-transit projects in New York and California. The increase was partially offset by decreased activity on certain tunnel projects on the West Coast and on certain higher-margin projects.

#### Building Segment

Building segment revenues increased $79.4 million, or 21.3%, and $180.3 million, or 26.9%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The increase was due primarily to increased activity on various building projects in California, and hospitality and gaming projects in Mississippi and California. The increase was partially offset by decreased activity due to a multi-unit residential project in Pennsylvania that completed last year.

#### Specialty Contractors Segment

Specialty Contractors segment revenues increased $4.8 million, or 1.5%, and $5.7 million, or 0.9%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The increase was due primarily to increased activity on mass-transit and other electrical and mechanical projects in New York (including at Hudson Yards). The increase was partially offset by decreased activity on various smaller electrical projects in the southern U.S., electrical projects at the World Trade Center and mechanical projects at the United Nations in New York, and two signal system modernization projects in New York.

### Income from Construction Operations

The following table summarizes our income from construction operations by business segment.

*(dollars in millions)*

|  | Income from Construction Operations and Operating Margins Three Months Ended June 30, 2015 2014 Amount Margin Amount Margin | Change in Amount Margin $%% |
| --- | ---: | ---: |
| Civil | $46.3 8.7% $58.0 14.8% | $(11.7) (20.2)% (6.1)% |
| Building | (12.5) (2.8)% 7.7 2.0% | (20.2) (262.3)% (4.8)% |
| Specialty Contractors | 13.7 4.2% 12.6 3.9% | 1.1 8.7% 0.3% |
|  | 47.5 3.6% 78.3 7.2% | (30.8) (39.3)% (3.6)% |
| Corporate | (16.6) (1.2)% (12.9) (1.2)% | (3.7) (28.7)% —% |
| Income from construction operations | $30.9 2.4% $65.4 6.0% | $(34.5) (52.8)% (3.6)% |
|  | **Income from Construction Operations** |  |
|  | **and Operating Margins** |  |
|  | **Six Months Ended June 30,** | **Change in** |
|  | **2015** **2014** | **Amount** **Margin** |
| **(dollars in millions)** | **Amount** **Margin** **Amount** **Margin** | **$%%** |
| Civil | $76.9 8.5% $102.3 13.5% | $(25.4) (24.8)% (5.0)% |
| Building | (14.9) (1.8)% 9.5 1.4% | (24.4) (256.8)% (3.2)% |
| Specialty Contractors | 24.3 3.9% 20.5 3.3% | 3.8 18.5% 0.6% |
|  | 86.3 3.6% 132.3 6.5% | (46.0) (34.8)% (2.9)% |
| Corporate | (35.3) (1.5)% (25.4) (1.3)% | (9.9) (39.0)% (0.2)% |
| Income from construction operations | $51.0 2.1% $106.9 5.2% | $(55.9) (52.3)% (3.1)% |

#### Civil Segment

Civil segment income from construction operations decreased $11.7 million, or 20.2%, and $25.4 million, or 24.8%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The decrease was due primarily to net favorable adjustments to the estimated recoveries on two projects in the second quarter of 2014, based on legal rulings issued during that period. The decrease was also due to the decreased activity on certain tunnel projects on the West Coast and certain higher-margin projects, as discussed above under *Revenues.*

Civil segment operating margin declined to 8.7% and 8.5% for the three and six months ended June 30, 2015 compared to 14.8% and 13.5% for the same periods in 2014. The reduction in Civil segment operating margin was due primarily to the reasons discussed in the preceding paragraph.

#### Building Segment

Building segment income from construction operations decreased $20.2 million, or 262.3%, and $24.4 million, or 256.8%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The decrease was due primarily to an unfavorable adjustment in the second quarter of 2015 to the estimated cost to complete for a certain office building project on the East Coast, as well as favorable project adjustments in the second quarter of 2014 on three projects, including an electrical project in Afghanistan.

Building segment operating margin declined to -2.8% and -1.8% for the three and six months ended June 30, 2015 compared to 2.0% and 1.4% for the same periods in 2014. The reduction in Building segment operating margin was due primarily to the reasons discussed in the preceding paragraph.

#### Specialty Contractors Segment

Specialty Contractors segment income from construction operations increased $1.1 million, or 8.7%, and $3.8 million, or 18.5%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The increase was due primarily to the volume changes discussed above under *Revenues.*

Specialty Contractors segment operating margin increased to 4.2% and 3.9% for the three and six months ended June 30, 2015 compared to 3.9% and 3.3% for the same periods in 2014. The increase in Specialty Contractors segment operating margin was due primarily to the reasons discussed in the preceding paragraph.

#### Corporate

Corporate general and administrative expenses increased $3.7 million, or 28.7%, and $9.9 million, or 39.0%, for the three and six months ended June 30, 2015 compared to the same periods in 2014. The increase for the second quarter was primarily due to higher legal related expenses, depreciation, and the timing of employee health benefit expenses. The increase for the six months ended June 30, 2015 was primarily due to the preceding reasons, as well as increased performance-based incentive compensation expense.

### Consolidated Other Income, Interest Expense and Provision for Income Taxes

*(dollars in millions)*

| Three Months Ended | June 30, 2015 | June 30, 2014 | $ Change | % Change |
| --- | ---: | ---: | ---: | ---: |
| Other income (expense), net | $0.1 | $(7.0) | $7.1 | (101.4)% |
| Interest expense | 11.0 | 10.9 | 0.1 | 0.9% |
| Provision for income taxes | 8.2 | 19.1 | (10.9) | (57.1)% |
| **(dollars in millions)** | **June 30, 2015** | **June 30, 2014** | **$ Change** | **% Change** |
| **Six Months Ended** |  |  |  |  |
| Other income (expense), net | $(0.7) | $(10.3) | $9.6 | (93.2)% |
| Interest expense | 22.1 | 21.7 | 0.4 | 1.8% |
| Provision for income taxes | 11.3 | 30.4 | (19.1) | (62.8)% |

Other income (expense), net improved $7.1 million and $9.6 million for the three and six months ended June 30, 2015 compared to the same periods in 2014. This was primarily due to a reduction in expense recognized for changes in contingent consideration liabilities associated with historical acquisitions. Additionally, there were losses recognized on the sale of our auction rate securities and expenses related to the refinancing of our credit facility in the second quarter of 2014.

Interest expense increased $0.1 million and $0.4 million for the three and six months ended June 30, 2015 compared to the same periods in 2014.

Provision for income taxes was $8.2 million and $11.3 million for three and six months ended June 30, 2015 compared to income tax provision of $19.1 million and $30.4 million for the same periods in 2014. The effective income tax rate was 41.1% and 40.1% for the three and six months ended June 30, 2015 compared to 40.0% and 40.6% for the same periods in 2014. The changes in the effective tax rate for the three and six months ended June 30, 2015 compared to the same periods in 2014, were primarily due to increased activities in higher tax rate jurisdictions. The remaining changes are a result of discrete tax item adjustments.

### Liquidity and Capital Resources

### Cash and Working Capital

At June 30, 2015 and December 31, 2014, cash held by us and available for general corporate purposes was $48.4 million and $40.8 million, respectively. Our proportionate share of cash held by joint ventures and available only for joint venture-related uses, including distributions to joint venture partners, was $58.5 million and $94.7 million at June 30, 2015 and December 31, 2014, respectively, and our restricted cash was $39.5 million and $44.4 million at June 30, 2015 and December 31, 2014, respectively. We believe that our cash flows will be sufficient to satisfy our currently anticipated cash requirements through at least the next 12 months.

We do not believe that it is likely we will be called upon to contribute significant additional capital in the event of default by any of our partners. We require each partner in the joint ventures in which we participate to accept joint and several responsibility for all obligations of the joint venture. Prior to forming a joint venture, we conduct a thorough analysis of the prospective partner to determine its capabilities, specifically relating to construction expertise, track record for delivering a quality product on time, reputation in the industry, as well as financial strength and available liquidity. We utilize a number of resources to verify a potential joint venture partner’s financial condition, including credit rating reports and financial information contained in its audited financial statements. We specifically review a potential partner’s available liquidity and bonding capacity. In the event we are concerned with the financial viability of a potential partner, we will require substantial initial cash contributions upon inception of the joint venture to mitigate the risk that we would be required to cover a disproportionate share of the joint venture’s future cash needs.

The majority of our joint venture contracts are for various government agencies that typically require the joint venture and/or our partners to complete a thorough pre-qualification process. This pre-qualification process typically includes the verification of each partner’s financial condition and capacity to perform the work, as well as the issuance of performance bonds by surety companies who also independently verify each partner’s financial condition.

A summary of cash flows for each of the six months ended June 30, 2015 and 2014 is set forth below:

*(in millions)*

| Cash flows from: | Six Months Ended June 30, 2015 | 2014 |
| --- | ---: | ---: |
| Operating activities | $(31.7) | $(61.4) |
| Investing activities | (23.5) | 19.6 |
| Financing activities | 26.6 | 61.7 |
| Net (decrease) increase in cash | (28.6) | 19.9 |
| Cash at beginning of year | 135.5 | 119.9 |
| Cash at end of period | $106.9 | $139.8 |

During the six months ended June 30, 2015, we used $31.7 million in cash from operating activities. In the first quarter of 2015 we received full and final payments related to settlements reached on the MGM City Center matter and on a separate more recently completed building project. Because of strong collections in December 2014, we were required to make substantial payments to subcontractors and other vendors early in the first quarter of 2015. We funded significant working capital associated with unapproved change orders and receivables resulting from higher revenue on building and civil projects partially offset by increased accounts payable. We used $23.5 million in cash from investing activities, due primarily to the acquisition of property and equipment of $29.5 million offset by the sale of property and construction equipment of $1.1 million. We received $26.6 million in cash from financing activities, due primarily to increased borrowings under our Credit Facility offset by cash used for scheduled debt repayments.

At June 30, 2015, we had working capital of $1,158.7 million, a ratio of current assets to current liabilities of 1.78, and a ratio of debt to equity of 0.64 compared to working capital of $1,114.0 million, a ratio of current assets to current liabilities of 1.82 and a ratio of debt to equity of 0.63 at December 31, 2014.

### Long-term Debt

Debt was $892.8 million at June 30, 2015, an increase of $27.4 million from $865.4 million at December 31, 2014, due primarily to a net increase in borrowings of $55.0 million on the revolving line of credit offset by net reductions of $27.6 million in other debt. We utilized the revolving facility for outstanding letters of credit in the amount of $0.2 million. Accordingly, at June 30, 2015, we had $114.8 million available to borrow under our credit agreement. We believe that our financial position and credit arrangements are sufficient to support our current backlog and anticipated new work.

Excluding the outstanding borrowings of $185.0 million on our revolving line of credit, the unsecured senior notes of $298.9 million and our $235.0 million term loan, the remaining balance of $173.9 million of our outstanding debt is generally secured by the underlying assets. Our debt to equity ratio was 0.64 as of June 30, 2015 compared to 0.63 as of December 31, 2014.

On June 5, 2014, the Company entered into the Credit Facility, restructuring its former $300 million revolving credit facility and $200 million Term Loan. All outstanding amounts under the Fifth Amended and Restated Credit Agreement were repaid in full using proceeds of the Credit Facility. The new agreement provides for a $300 million revolving credit facility (the “Revolving Credit Facility”) and a $250 million term loan (the “Term Loan”) with Bank of America, N.A. as administrative agent, Swing Line Lender and L/C Issuer and a syndicate of other lenders. The Term Loan principal is to be repaid on a quarterly basis, with 6.0% of the original total outstanding principal repaid in year 1, 9.0% in year 2, 12.0% in year 3, 15.0% in year 4 and 13.5% in year 5 along with a balloon payment of the remaining 44.5%. Borrowings under the Revolving Credit Facility will bear interest based either on Bank of America’s prime lending rate or the London Interbank Offered Rate (“LIBOR”) plus an applicable margin. Borrowings under the Term Loan bear interest based on LIBOR plus an applicable margin. Included in the Credit Facility is a special provision allowing an additional accordion provision, which the Company may opt to utilize at a future date to increase either the Revolving Credit Facility or establish one or more new term loan commitments, up to an aggregate amount not to exceed $300 million. The Credit Facility provides a sublimit for the issuance of letters of credit up to the aggregate amount of $150 million. Both the Revolving Credit Facility and the Term Loan mature on June 5, 2019.

As of the filing date of this Form 10-Q, we are in compliance and expect to continue to be in compliance with the financial covenants under the Credit Facility.

There were no other material changes in our contractual obligations during the three months ended June 30, 2015.

### Off-Balance Sheet Arrangements

We do not have financial partnerships with unconsolidated entities, such as entities often referred to as structured finance or special purpose entities which are often established for the purpose of facilitating off-balance sheet arrangements or other contractually narrow or limited purposes, except that we participate in one variable interest entity. This entity does not have and is not reasonably likely to have a material current or future effect on our financial condition, changes in financial condition, revenues or expenses, results of operations, liquidity, capital expenditures or capital resources. Accordingly, we are not exposed to any financing, liquidity, market or credit risk that could arise from such relationships.

### Forward-looking Statements

The statements contained in this Management’s Discussion and Analysis of the Consolidated Condensed Financial Statements on Form 10-Q that are not purely historical are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934, including without limitation, statements regarding our management’s expectations, hopes, beliefs, intentions or strategies regarding the future. These forward-looking statements are based on our current expectations and beliefs concerning future developments and their potential effects on us. Our expectations, beliefs and projections are expressed in good faith and we believe there is a reasonable basis for them. There can be no assurance that future developments affecting us will be those that we have anticipated. These forward-looking statements involve a number of risks, uncertainties (some of which are beyond our control) or other assumptions that may cause actual results or performance to be materially different from those expressed or implied by such forward-looking statements. These risks and uncertainties include, but are not limited to:

- our ability to win new contracts and convert backlog into revenue;
- our ability to successfully and timely complete construction projects;
- our ability to realize the anticipated economic and business benefits of our acquisitions and our strategy to assemble and operate a Specialty Contractors business segment;
- the potential delay, suspension, termination or reduction in scope of a construction project;
- the continuing validity of the underlying assumptions and estimates of total forecasted project revenues, costs and profits and project schedules;
- the outcomes of pending or future litigation, arbitration or other dispute resolution proceedings;
- the availability of borrowed funds on terms acceptable to us;
- the ability to retain certain members of management;
- the ability to obtain surety bonds to secure our performance under certain construction contracts;
- possible labor disputes or work stoppages within the construction industry;
- changes in federal and state appropriations for infrastructure projects and the impact of changing economic conditions on federal, state and local funding for infrastructure projects;
- possible changes or developments in international or domestic political, social, economic, business, industry, market and regulatory conditions or circumstances;
- actions taken or not taken by third parties including our customers, suppliers, business partners, and competitors and legislative, regulatory, judicial and other governmental authorities and officials; and
- other risks and uncertainties discussed under the heading “Risk Factors” in our Annual Report on Form 10-K for the year ended December 31, 2014 filed with the Securities and Exchange Commission on February 26, 2015.

We undertake no obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as may be required under applicable securities laws.

## Market risk

As filed, 239 characters.

There has been no material change in our exposure to market risk from that described in Item 7A of our Annual Report on Form 10-K for the year ended December 31, 2014, filed with the Securities and Exchange Commission on February 26, 2015.

## Controls and procedures

As filed, 1,543 characters.

### Disclosure Controls and Procedures

An evaluation of the effectiveness of the design and operation of our disclosure controls and procedures as defined by Rule 13a-15(e) under the Securities Exchange Act of 1934, as amended (“Exchange Act”), as of the end of the period covered by this Quarterly Report on Form 10-Q was made under the supervision and with the participation of our management, including our Chief Executive Officer and Chief Financial Officer. Based upon that evaluation, the Chief Executive Officer and Chief Financial Officer concluded that the Company’s disclosure controls and procedures (a) were effective to ensure that information we are required to disclose in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in Securities and Exchange Commission rules and forms and (b) include, without limitation, controls and procedures designed to ensure that information required to be disclosed by us in reports filed or submitted under the Exchange Act is accumulated and communicated to our management, including our Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.

### Changes in Internal Controls Over Financial Reporting

There were no changes in our internal control over financial reporting during the period covered by this report that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.

## Risk factors

As filed, 245 characters.