## Figures reported in this filing

Standardized XBRL line items for the period ended 2020-03-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2020-01-01 to 2020-03-31 | $1.25bn | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Cost of revenue | 3 months, 2020-01-01 to 2020-03-31 | $1.14bn | us-gaap:CostOfGoodsAndServicesSold |
| Gross profit | 3 months, 2020-01-01 to 2020-03-31 | $111.1m | us-gaap:GrossProfit |
| Operating income | 3 months, 2020-01-01 to 2020-03-31 | $47.2m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2020-01-01 to 2020-03-31 | $16.4m | us-gaap:InterestExpense |
| Income tax | 3 months, 2020-01-01 to 2020-03-31 | $5.1m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2020-01-01 to 2020-03-31 | $17.4m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2020-01-01 to 2020-03-31 | $0.34 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2020-01-01 to 2020-03-31 | $0.35 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2020-01-01 to 2020-03-31 | 50,836,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months, 2020-01-01 to 2020-03-31 | −$34.0m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months, 2020-01-01 to 2020-03-31 | $11.7m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | at 2020-03-31 | $198.1m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2020-03-31 | $3.72bn | us-gaap:AssetsCurrent |
| Total assets | at 2020-03-31 | $4.69bn | us-gaap:Assets |
| Current liabilities | at 2020-03-31 | $2.29bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2020-03-31 | $3.24bn | us-gaap:Liabilities |
| Long-term debt | at 2020-03-31 | $717.4m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2020-03-31 | $185.0m | us-gaap:DebtCurrent |
| Shareholders' equity | at 2020-03-31 | $1.46bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 32,893 characters.

The following discusses our financial position as of March 31, 2020 and the results of our operations for the three months ended March 31, 2020 and should be read in conjunction with other information, including the unaudited Condensed Consolidated Financial Statements and notes included in Part I, Item 1, Financial Information, of this Quarterly Report on Form 10-Q, the audited consolidated financial statements and accompanying notes to our Annual Report on Form 10-K for the year ended December 31, 2019, and the information contained under the heading “Risk Factors” in our Annual Report on Form 10-K for the year ended December 31, 2019 and in Part II, Item 1A below.

### Forward-Looking Statements

This Quarterly Report on Form 10-Q, including the “Management’s Discussion and Analysis of Financial Condition and Results of Operations,” contains forward-looking statements regarding future events and our future results, which are intended to be covered by the safe harbor provision for forward-looking statements provided by the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical facts are statements that could be deemed forward-looking statements. Words such as “achieve,” “anticipate,” “assumes,” “believes,” “continue,” “could,” “estimate,” “expects,” “forecast,” “hope,” “intend,” “may,” “plan,” “potential,” “predict,” “should,” “will,” “would,” variations of such words and similar expressions are intended to identify such forward-looking statements. In addition, any statements that refer to projections of our future financial performance, our anticipated growth and trends in our businesses, and other characterizations of future events or circumstances are forward-looking statements. Although such statements are based on currently available financial and economic data as well as management’s estimates and expectations, forward-looking statements are inherently uncertain and involve risks and uncertainties that could cause our actual results to differ materially from what may be inferred from the forward-looking statements. Therefore, actual results may differ materially and adversely from those expressed in any forward-looking statements. Factors potentially contributing to such differences include, among others:

The impact of the COVID-19 pandemic and related events that are beyond our control, including possible effects on our business and operations, customers and suppliers, and employees, contractors and subcontractors, which could affect adversely our projects and the geographic regions in which we conduct business;

A significant slowdown or decline in economic conditions;

Revisions of estimates of contract risks, revenue or costs; the timing of new awards; or the pace of project execution may result in losses or lower than anticipated profit;

Unfavorable outcomes of existing or future litigation or dispute resolution proceedings against customers (project owners, developers, general contractors, etc.), subcontractors or suppliers, as well as failure to promptly recover significant working capital invested in projects subject to such matters;

The requirement to perform extra, or change order, work resulting in disputes or claims or adversely affecting our working capital, profits and cash flows;

Risks and other uncertainties associated with assumptions and estimates used to prepare financial statements;

Inability to retain key members of our management, to hire and retain personnel required to complete projects or implement succession plans for key officers;

Failure to meet contractual schedule requirements, which could result in higher costs and reduced profits or, in some cases, exposure to financial liability for liquidated damages and/or damages to customers;

Failure to meet our obligations under our debt agreements;

Decreases in the level of government spending for infrastructure and other public projects;

Downgrades in our credit ratings;

Failure of our joint venture partners to perform their venture obligations, which could impose additional financial and performance obligations on us, resulting in reduced profits or losses;

Client cancellations of, or reductions in scope under, contracts reported in our backlog;

Increased competition and failure to secure new contracts;

Impairment of our goodwill or other indefinite-lived intangible assets;

The impact of inclement weather conditions on projects;

Possible systems and information technology interruptions, including due to cyberattack, systems failures or other similar events;

Failure to comply with laws and regulations related to government contracts;

Potential dilutive impact of our Convertible Notes in our diluted earnings per share calculation;

Economic, political and other risks, including civil unrest, security issues, labor conditions, corruption and other unforeseeable events in countries where we do business, resulting in unanticipated losses;

Uncertainty from the expected discontinuance of the London Interbank Offered Rate and transition to any other interest rate benchmark; and

Conversion of our outstanding Convertible Notes that could dilute ownership interests of existing stockholders and could adversely affect the market price of our common stock.

### Executive Overview

### COVID-19 Update

In the first quarter of 2020, a novel strain of coronavirus, COVID-19, was declared a pandemic. Efforts in the United States to prevent the spread of COVID-19 and mitigate its impacts intensified during March 2020. All 50 states in the United States have declared states of emergency, and various countries around the world, including the United States, have taken steps to restrict travel. Many states and cities within the United States have also enacted temporary closures of businesses, issued stay-at-home orders and taken other restrictive measures in response to the pandemic. These actions and measures have been changing frequently, and often on a daily basis.

For the three months ended March 31, 2020, the COVID-19 pandemic did not have a significant impact on our business. The vast majority of our projects have been considered essential business activities, which has allowed our projects to continue while implementing new health and safety requirements. However, some of our projects, primarily for private (commercial) customers in our Building and Specialty Contractors segments, have experienced or continue to experience temporary suspensions or reduced project activities as a result of the COVID-19 pandemic. The greatest financial impact to the Company thus far has been in New York and California, primarily due to temporary suspensions, the impact of new social distancing and other health and safety requirements, and in some cases employee and subcontractor absences.

Due to the fluidity of the COVID-19 pandemic, uncertainties as to its scope and duration, and ongoing changes in the way that governments, businesses and individuals react and respond to the pandemic, the Company is unable at this time to accurately predict the pandemic’s future impact on the Company’s business, results of operations, financial condition or liquidity. Among other things, governments could prohibit the continuation of certain projects that to date have been designated as “essential” or could impose health, safety and other operational requirements on such projects that could result in delays to or suspensions of such projects. In addition, employees and contractors working on such projects could be unable or unwilling to continue working on them, perhaps for extended periods. The COVID-19 pandemic also could negatively affect the ability of counterparties or joint venture partners to make required payments on a timely basis or at all.

### Operating Results

Consolidated revenue for the three months ended March 31, 2020 was $1.3 billion, up 30% compared to $1.0 billion for the same period in 2019. The strong growth was mostly attributable to increased activities on various infrastructure projects in the Civil and Specialty Contractors segments.

Income from construction operations for the first quarter of 2020 was $47.2 million, more than double when compared to $22.9 million for the same period in 2019. The increase was primarily driven by improved performance on various projects in New York in the Specialty Contractors segment, as well as contributions associated with volume growth across all segments.

The effective tax rate was 16.4% for the three months ended March 31, 2020, compared to 31.7% for the comparable period in 2019. See *Corporate, Tax and Other Matters* below for a discussion of the changes in the effective tax rate.

Diluted earnings per share for the three months ended March 31, 2020 was $0.34 compared to a loss per share of $0.01 for the same quarter of 2019. The increase was primarily due to the factors discussed above that drove the increases in revenue and income from construction operations.

Consolidated new awards for the three months ended March 31, 2020 totaled $0.6 billion compared to $3.2 billion for the same period in 2019. The lower volume of new awards in the current year period was due to the timing of bidding for and awards of prospective project opportunities, which the Company expects will occur later in 2020, whereas the prior year period included a record volume of new awards. The Specialty Contractors and Building segments were the primary contributors to the new award activity in the first quarter of 2020. The most significant new awards were three military projects in North Carolina and Florida collectively totaling $133 million and a $64 million mining project in Alabama.

Consolidated backlog as of March 31, 2020 was $10.6 billion compared to $11.2 billion at December 31, 2019. Backlog declined in the first quarter of 2020 as a result of revenue not being fully offset by the volume of new awards. As of March 31, 2020, the mix of backlog by segment was approximately 54% for Civil, 24% for Building and 22% for Specialty Contractors.

The following table presents the Company’s backlog by business segment, reflecting changes from December 31, 2019 to March 31, 2020:

*(in millions)*

|  | Backlog at December 31, 2019 | New Awards(a) | Revenue Recognized | Backlog at March 31, 2020(b) |
| --- | ---: | ---: | ---: | ---: |
| Civil | $6,037.2 | $178.5 | $(486.6) | $5,729.1 |
| Building | 2,790.3 | 183.0 | (481.8) | 2,491.5 |
| Specialty Contractors | 2,393.6 | 225.7 | (282.3) | 2,337.0 |
| Total | $11,221.1 | $587.2 | $(1,250.7) | $10,557.6 |

(a) New awards consist of the original contract price of projects added to backlog plus or minus subsequent changes to the estimated total contract price of existing contracts.

(b) Backlog may differ from the transaction prices allocated to the remaining performance obligations as disclosed in Note 3 of the Notes to Condensed Consolidated Financial Statements. Such differences relate to the timing of executing a formal contract or receiving a notice to proceed. More specifically, backlog sometimes may include awards for which a contract has not yet been executed or a notice to proceed has not been issued, but for which there are no remaining major uncertainties that the project will proceed (e.g., adequate funding is in place).

While we did not experience significant adverse impacts to our business related to the COVID-19 pandemic in the first quarter of 2020, the situation remains fluid and uncertain, and therefore, the Company cannot assess the degree to which it might experience future adverse impacts. The general outlook for the Company’s growth in 2020 and over the next several years remains favorable, particularly in the Civil and Specialty Contractors segments, but the impact of the COVID-19 pandemic could adversely impact future performance and operations. In addition, the Company’s pace of growth could be impacted by project delays or the timing of project commencements, ramp-up activities and completions, as the Company has experienced in recent years. We anticipate that we will continue to win our share of significant new awards resulting from long-term capital spending plans by state, local and federal customers, as well as bipartisan support for infrastructure investments and limited competition for some of the largest project opportunities. In recent elections, voters in numerous states approved dozens of long-term transportation funding measures totaling approximately $200 billion in long-term funding. The largest of these were in Los Angeles County, where Measure M, a half-cent sales tax increase, was approved and is expected to generate $120 billion of funding over 40 years, and in Seattle, Washington, where Sound Transit 3 was passed and is expected to generate $54 billion of funding over 25 years. As state and local governments respond to the economic burdens of the COVID-19 pandemic, they may delay or cancel planned infrastructure investments. They also may face reduced revenues from income and sales taxes, fuel taxes and tolls. The extent of such effects, their duration, and how state and local governments will respond remains uncertain, just as the scope and duration of the COVID-19 pandemic remains uncertain. The possibility of additional federal financial assistance or stimulus programs directed toward assisting state and local governments or specifically targeting significant investments in infrastructure have been discussed as possible additional pieces of the federal government’s ongoing response to the COVID-19 pandemic. Such additional federal financial assistance or stimulus programs could favorably impact the Company’s current work and prospective opportunities. However, the timing and significance of such additional federal government actions, if any, remain uncertain. In addition, several large, long-duration civil infrastructure programs with which we are already involved continue to progress. Finally, the COVID-19 pandemic’s dramatic impact on the U.S. economy has led to interest rates that once again are at record low levels and may be conducive to continued, and potentially increased, spending on infrastructure projects.

For a more detailed discussion of operating performance of each business segment, corporate general and administrative expenses and other items, see *Results of Segment Operations, Corporate, Tax and Other Matters* and *Liquidity and Capital Resources* below.

### Results of Segment Operations

The results of our Civil, Building and Specialty Contractors segments are discussed below.

### Civil Segment

Revenue and income from construction operations for the Civil segment are summarized as follows:

*(in millions)*

|  | Three Months Ended March 31, 2020 | 2019 |
| --- | ---: | ---: |
| Revenue | $486.6 | $333.5 |
| Income from construction operations | 46.1 | 41.8 |

Revenue for the three months ended March 31, 2020 increased 46% compared to the same period in 2019. The revenue growth was primarily due to increased project execution activities on several mass-transit projects in California, Minnesota and New York.

Income from construction operations for the three months ended March 31, 2020 increased 10% compared to the same period in 2019, primarily because of the absence of a prior year immaterial favorable adjustment on a project in California, but also due to the impact of incremental non-cash amortization expense related to the increased equity interest in a joint venture that the Company acquired in the fourth quarter of 2019.

Operating margin was 9.5% for the three months ended March 31, 2020 compared to 12.5% for the same period in 2019. The operating margin decrease was primarily attributable to the factors mentioned above that drove the changes in revenue and income from construction operations.

New awards in the Civil segment totaled $179 million for the three months ended March 31, 2020 compared to $1.7 billion for the same period in 2019. The lower volume of new awards in the current year period was due to the timing of bidding for and awards of prospective project opportunities, which the Company expects will occur later in 2020, whereas the prior year period included several new awards, most notably the $1.4 billion Purple Line Section 3 Stations project in California. The Civil segment’s most significant new award in the first quarter of 2020 was a $64 million mining project in Alabama. Several large Civil segment opportunities are expected to bid and potentially be awarded to the Company later this year.

Backlog for the Civil segment was $5.7 billion as of March 31, 2020 compared to $6.5 billion as of March 31, 2019. The higher backlog in the prior year period was primarily driven by the Purple Line Section 3 Stations project mentioned above. The decrease in backlog when compared to the prior year period was the result of strong revenue growth for the segment that was not fully offset by new awards. The segment continues to experience strong demand reflected in a large, multi-year pipeline of prospective projects, substantial anticipated funding from various voter-approved transportation measures and public agencies’ long-term spending plans. The Civil segment is well-positioned to continue capturing its share of these prospective projects.

### Building Segment

Revenue and income from construction operations for the Building segment are summarized as follows:

*(in millions)*

|  | Three Months Ended March 31, 2020 | 2019 |
| --- | ---: | ---: |
| Revenue | $481.8 | $433.5 |
| Income from construction operations | 3.5 | 3.1 |

Revenue for the three months ended March 31, 2020 increased 11% compared to the same period in 2019. The revenue growth was primarily due to increased project execution activities on a hospitality and gaming project in Oklahoma.

Income from construction operations for the three months ended March 31, 2020 increased 12% compared to the same period in 2019, consistent with the revenue growth and, in particular, the increased activities on the hospitality and gaming project mentioned above.

Operating margin was 0.7% for the three months ended March 31, 2020 compared to 0.7% for the same period in 2019. Both periods were negatively impacted by immaterial project adjustments on certain projects as they progressed towards completion.

New awards in the Building segment totaled $183 million for the three months ended March 31, 2020 compared to $1.1 billion for the same period in 2019. The lower volume of new awards in the first quarter of 2020 was due to the timing of prospective project opportunities, which are expected to be awarded later in the year, whereas the first quarter of 2019 included several sizeable new awards, such as the Choctaw Casino and Resort project in Oklahoma, a large hospitality and gaming project in California and the Southland Gaming Casino and Hotel project in Arkansas. Significant new awards and contract adjustments in the first quarter of 2020 included three military projects in North Carolina and Florida collectively totaling $133 million.

Backlog for the Building segment was $2.5 billion as of March 31, 2020 compared to $3.0 billion as of March 31, 2019. The decrease was driven by revenue growth for the segment that was not fully offset by new awards. The Building segment continues to have a large volume of prospective projects across various end markets and geographic locations. Barring any adverse impacts from the COVID-19 pandemic, demand for our building construction services is expected to continue due to ongoing customer spending supported by a favorable interest rate environment.

### Specialty Contractors Segment

Revenue and income (loss) from construction operations for the Specialty Contractors segment are summarized as follows:

*(in millions)*

|  | Three Months Ended March 31, 2020 | 2019 |
| --- | ---: | ---: |
| Revenue | $282.3 | $191.5 |
| Income (loss) from construction operations | 8.3 | (7.5) |

Revenue for the first quarter of 2020 increased 47% compared to the first quarter of 2019. The revenue growth was principally driven by increased project execution activities on the Newark Airport Terminal One project in New Jersey and certain electrical and mechanical projects in New York.

Income from construction operations for the first quarter of 2020 was $8.3 million compared to a loss from construction operations of $7.5 million for the three months ended March 31, 2019. The increase in income from construction operations was primarily driven by the volume changes mentioned above in the explanation for the revenue growth, as well as the absence of prior year unfavorable closeout adjustments on certain electrical and mechanical projects in New York totaling $13.6 million, none of which were individually material.

Operating margin was 2.9% for the three months ended March 31, 2020 compared to (3.9)% for the same period in 2019. The margin change was mainly attributable to the aforementioned drivers of the increases in revenue and income (loss) from construction operations.

New awards in the Specialty Contractors segment totaled $226 million for the three months ended March 31, 2020 compared to $479 million for the same period in 2019.

Backlog for the Specialty Contractors segment was $2.3 billion as of March 31, 2020, up 11% compared to $2.1 billion as of March 31, 2019. The growth was driven by strong demand from public and private customers for our electrical and mechanical services on numerous civil and building projects. The Specialty Contractors segment continues to be increasingly focused on servicing the Company’s growing backlog of large Civil and Building segment projects, but it also remains well-positioned to capture its share of new projects for external customers, leveraging the size and scale of our business units that operate in New York, Texas, Florida and California and the strong reputation held by these business units for high-quality work on large, complex projects.

### Corporate, Tax and Other Matters

### Corporate General and Administrative Expenses

Corporate general and administrative expenses were $10.7 million during the three months ended March 31, 2020 compared to $14.8 million during the three months ended March 31, 2019. The decrease was primarily due to lower compensation-related expenses.

### Other Income, Net, Interest Expense and Income Tax Expense

*(in millions)*

|  | Three Months Ended March 31, 2020 | 2019 |
| --- | ---: | ---: |
| Other income, net | $0.5 | $0.4 |
| Interest expense | (16.4) | (16.4) |
| Income tax expense | (5.1) | (2.2) |

The effective income tax rate for the three months ended March 31, 2020 was 16.4% compared to 31.7% for the same period in 2019. The decrease in the effective income tax rate for the 2020 period primarily reflects the favorable impact of the 2019 net operating loss (“NOL”), which is allowed to be carried back up to five years as a result of the Coronavirus Aid, Relief, and Economic Security Act (“CARES Act”), enacted on March 27, 2020. Under the CARES Act, the Company’s NOL generated in 2019 may be carried back to tax years when the federal statutory tax rate was 35% rather than the current rate of 21%, consequently generating a larger tax benefit from the NOL than that recognized prior to the enactment of the CARES Act. The favorable impact resulting from the enactment of the CARES Act was partially offset by the unfavorable impact of the vesting of restricted stock units for which a large portion of the share-based compensation expense recognized in prior periods will not be deductible for income tax purposes. For a further discussion of income taxes, refer to Note 7 of the Notes to Condensed Consolidated Financial Statements.

### Liquidity and Capital Resources

Liquidity is provided by available cash and cash equivalents, cash generated from operations, credit facilities and access to capital markets. We have a committed line of credit totaling $350 million, which may be used for revolving loans, letters of credit and/or general purposes. We believe that cash generated from operations, along with our unused credit capacity of $175 million and available cash balances as of March 31, 2020, will be sufficient to fund any working capital needs for the next 12 months, provided that we are not adversely impacted by unanticipated future events, including the COVID-19 pandemic as discussed in *COVID-19 Update* above. In addition, liquidity will be positively impacted in 2020 by certain provisions of the CARES Act, which will enable the Company to accelerate the collection of tax refunds associated with the 2019 NOL carryback and allow the deferral of certain 2020 Social Security payroll tax liabilities until the end of 2021 and 2022. As discussed in the section entitled *Debt* below, we intend to seek to repurchase the Convertible Notes in 2020 using available liquidity. Subject to certain limitations, we are permitted to utilize available credit capacity from our 2017 Credit Facility to repurchase the Convertible Notes. Alternatively, we may pursue amendment of the 2017 Credit Facility and/or exchange the Convertible Notes.

### Cash and Working Capital

Cash and cash equivalents were $198.1 million as of March 31, 2020 compared to $193.7 million as of December 31, 2019. Cash immediately available for general corporate purposes was $80.9 million and $43.8 million as of March 31, 2020 and December 31, 2019, respectively, with the remainder being amounts held by our consolidated joint ventures and also our proportionate share of cash held by our unconsolidated joint ventures. Cash held by our joint ventures was available only for joint venture-related uses, including distributions to joint venture partners. In addition, our restricted cash and restricted investments, held primarily to secure insurance-related contingent obligations, totaled $81.4 million as of March 31, 2020 compared to $79.4 million as of December 31, 2019.

During the three months ended March 31, 2020, net cash used in operating activities was $34.0 million due primarily to investments in project working capital partially offset by cash generated from earnings sources. The change in working capital primarily reflects an increase in accounts receivable due to timing of collections, partially offset by an increase in accounts payable due to timing of payments to suppliers and subcontractors. During the three months ended March 31, 2019, net cash used in operating activities was $124.8 million due primarily to investments in project working capital that exceeded cash generated from earnings sources. The change in working capital primarily reflected an increase in accounts receivable due to timing of collections.

Cash flow from operating activities increased $90.8 million when comparing the first three months of 2020 with the same period of 2019. The improvement in the 2020 period primarily reflects a current year increase in accounts payable compared to a decrease in the prior year due to favorable timing of payments to suppliers and subcontractors, along with a larger increase in billings in excess of costs and estimated earnings, partially offset by a larger increase in accounts receivable in the current year period.

Cash used for investing activities during the first three months of 2020 and 2019 was $14.6 million and $19.2 million, respectively, primarily due to the acquisition of property and equipment for projects and investment in securities.

For the first three months of 2020, net cash provided by financing activities was $50.6 million, which was primarily driven by increased net borrowings of $64.8 million partially offset by $13.5 million of cash distributions to noncontrolling interests. Net cash provided by financing activities for the comparable period in 2019 was $130.7 million, which was primarily driven by increased net borrowings of $134.3 million.

At March 31, 2020, we had working capital of $1.4 billion, a ratio of current assets to current liabilities of 1.62 and a ratio of debt to equity of 0.63, compared to working capital of $1.4 billion, a ratio of current assets to current liabilities of 1.66 and a ratio of debt to equity of 0.58 at December 31, 2019.

### Debt

Summarized below are the key terms of the 2017 Credit Facility as of March 31, 2020. For additional information regarding our outstanding debt, refer to Note 9 of the Notes to Condensed Consolidated Financial Statements, as applicable.

#### 2017 Credit Facility

On April 20, 2017, we entered into a credit agreement (the “2017 Credit Facility”) with SunTrust Bank, now known as Truist Bank, as Administrative Agent, Swing Line Lender and L/C Issuer and a syndicate of other lenders. The 2017 Credit Facility provides for a $350 million revolving credit facility (the “2017 Revolver”) and a sublimit for the issuance of letters of credit and swingline loans up to the aggregate amount of $150 million and $10 million, respectively, both maturing on April 20, 2022 unless any of the Convertible Notes are outstanding on December 17, 2020, in which case all such borrowings will mature on December 17, 2020 (the “spring-forward provision”), provided however (i) if the Convertible Notes are refinanced in full with the proceeds of permitted refinancing indebtedness in accordance with the terms of the 2017 Credit Facility, the maturity date for the 2017 Credit Facility will remain April 20, 2022 and (ii) if the Company issues “New Convertible Notes” (as defined in the 2017 Credit Facility) and retires the Convertible Notes in full, the maturity date for the 2017 Credit Facility will be the earlier of (x) April 20, 2022 or (y) 90 days prior to the maturity date for such New Convertible Notes. The 2017 Credit Facility also permits additional borrowings in an aggregate amount of $150 million, which can be in the form of increased capacity on the 2017 Revolver or the establishment of one or more term loans. On May 7, 2019, certain provisions of the 2017 Credit Facility were amended, including setting the maximum leverage ratio at 3.50:1.00. For additional information regarding the terms of our 2017 Credit Facility, refer to Note 9 of the Notes to Condensed Consolidated Financial Statements.

As a result of the spring-forward provision mentioned above, the facility will mature on December 17, 2020 if the Convertible Notes remain outstanding at that time. The Company does not have call rights that allow it to unilaterally redeem the Convertible Notes. However, the Company intends to seek to repurchase the Convertible Notes in 2020 using available liquidity. Subject to certain limitations, the Company is permitted to utilize available credit capacity from the 2017 Credit Facility to repurchase the Convertible Notes. Alternatively, the Company may pursue amendment of the 2017 Credit Facility and/or exchange the Convertible Notes. The Company continues to assess its various alternatives to determine the financial strategy best suited to the Company’s needs and that will provide the most favorable terms, taking into account the Company’s liquidity requirements and anticipated cash flows. Due to the spring-forward provision in the 2017 Credit Facility, all borrowings under the facility are included in “Current maturities of long-term debt” on the Condensed Consolidated Balance Sheet as of March 31, 2020.

The table below presents our actual and required consolidated fixed charge coverage ratio and consolidated leverage ratio under the 2017 Credit Facility for the period, which are calculated on a rolling four-quarter basis:

|  | Twelve Months Ended March 31, 2020 |  |
| --- | --- | --- |
|  | **Actual** | **Required** |
| Fixed charge coverage ratio | 3.58 to 1.00 | \> or = 1.25 : 1.00 |
| Leverage ratio | 2.88 to 1.00 | \< or = 3.50 : 1.00 |

As of March 31, 2020, we were in compliance and expect to continue to be in compliance with the covenants under the 2017 Credit Facility.

### Contractual Obligations

There have been no material changes in our contractual obligations from those described in our Annual Report on Form 10-K for the year ended December 31, 2019.

### Off-Balance Sheet Arrangements

None.

### Critical Accounting Policies

Our significant accounting policies are described in Note 1 of the Notes to Consolidated Financial Statements included in our Annual Report on Form 10-K for the year ended December 31, 2019. Our critical accounting policies are also identified and discussed in Item 7 of our Annual Report on Form 10-K for the year ended December 31, 2019. See Note 8 of the Notes to Condensed Consolidated Financial Statements for a detailed discussion of our accounting policies related to goodwill.

### Recently Issued Accounting Pronouncements

See Note 2 of the Notes to Condensed Consolidated Financial Statements.

## Market risk

As filed, 167 characters.

There has been no material change in our exposure to market risk from that described in Item 7A of our Annual Report on Form 10-K for the year ended December 31, 2019.

## Controls and procedures

As filed, 1,542 characters.

### Disclosure Controls and Procedures

An evaluation of the effectiveness of the design and operation of our disclosure controls and procedures as defined by Rule 13a-15(e) under the Securities Exchange Act of 1934, as amended (“Exchange Act”), as of the end of the period covered by this Quarterly Report on Form 10-Q was made under the supervision and with the participation of our management, including our Chief Executive Officer and Chief Financial Officer. Based upon that evaluation, the Chief Executive Officer and Chief Financial Officer concluded that the Company’s disclosure controls and procedures (a) were effective to ensure that information we are required to disclose in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in Securities and Exchange Commission rules and forms and (b) include, without limitation, controls and procedures designed to ensure that information required to be disclosed by us in reports filed or submitted under the Exchange Act is accumulated and communicated to our management, including our Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.

### Changes in Internal Control Over Financial Reporting

There were no changes in our internal control over financial reporting during the period covered by this report that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.

## Risk factors

As filed, 4,019 characters.

The risk factor discussed below is intended to supplement the risk factors previously disclosed in our Annual Report on Form 10-K for the year ended December 31, 2019.

**The COVID-19 pandemic could adversely impact our business, financial condition or results of operations.**

The COVID-19 pandemic has created volatility, uncertainty and economic disruption for the Company, our customers, subcontractors and suppliers, and the markets in which we do business. The scope and impact of the COVID-19 pandemic changed quickly during the first few months of 2020, and shelter-in-place rules and other limitations on conducting business generally did not come into effect in geographies where we do business until March 2020. Even where such rules and limitations have been implemented, only certain projects, primarily for private (commercial) customers in our Building and Specialty Contractors segments, have experienced temporary delays. The vast majority of the Company’s projects, especially in the Civil segment, have been designated as essential business, which allows the Company to continue work on those projects. Consequently, the Company’s operations were not significantly impacted during the three months ended March 31, 2020. However, health and economic conditions in the United States have continued to change, and in many instances have worsened, and changing conditions as well as the reactions of government and customers to such changes could adversely affect our business, possibly for a sustained period. It is too early to assess the full impact that the COVID-19 pandemic, and the actions taken in response to it, will have on our employees, our operating segments and practices, our customers, subcontractors and suppliers, and the regions that we serve, or on our financial condition and results of operations as a whole.

The full impact depends on many factors that are uncertain or not yet identifiable, and in many cases are out of our control. These factors could include, among other things: (1) the duration of the COVID-19 pandemic and the types and magnitude of adverse impacts on the U.S. and global economies; (2) the health and welfare of our employees, and those of our customers, subcontractors and suppliers; (3) evolving business and government actions in response to the pandemic, including stay-at-home measures, changes to what are considered “essential” businesses, social distancing measures, travel bans and additional health and safety requirements that we may be required to observe in order to continue working on our projects; (4) the varying impact that the pandemic may have on industries we serve and on government spending for infrastructure projects, including reduced government spending on infrastructure as a result of lower revenues from taxes and tolls; (5) the response of our customers or prospective customers to the pandemic, including delays, stoppages or terminations of existing projects or potential new awards; (6) increases in our receivables if our customers fail to pay, delay making payments, request financial concessions or if we experience delays in resolving claims and disputes (e.g., delays in court proceedings or settlement discussions); (7) limitations and higher costs associated with obtaining financing; (8) potential challenges with suppliers that could limit the availability or cost of materials; (9) potential interruptions to our information systems and technology or breaches in our data security due to increasing use of remote communications and access; and (10) the timing of finding effective treatments, a vaccine or a cure for COVID-19. Such events may result in fewer projects or delays in projects or bidding opportunities. Any of these events and others we have not yet identified could cause or contribute to the risks and uncertainties facing the Company and our customers and could materially adversely affect our business or portions thereof, and our financial condition, results of operations and/or stock price.

Filed May 6, 2020.
Source: SEC EDGAR, the filing index for accession 0000077543-20-000025. Last ingested by Listed: Nov 15, 2026, 00:46 ET. No prices; not investment advice.