# VSE Corp: Form 10-Q for the period ended Sep 30, 2011

- Company: [VSE Corp](/companies/vsec.md) (CIK 102752)
- Form: 10-Q
- Filed: 2011-10-31
- Accepted by EDGAR: Oct 28, 2011, 20:25 ET
- Period: 2011-09-30
- Accession: 0000102752-11-000059
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/102752/000010275211000059/vseform10q3_2011.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/102752/000010275211000059/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2011-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2011-07-01 to 2011-09-30 | $159.9m | us-gaap:SalesRevenueNet |
| Revenue | 9 months, 2011-01-01 to 2011-09-30 | $469.7m | us-gaap:SalesRevenueNet |
| Cost of revenue | 3 months, 2011-07-01 to 2011-09-30 | −$31.1m | us-gaap:CostOfGoodsSold |
| Cost of revenue | 9 months, 2011-01-01 to 2011-09-30 | −$44.9m | us-gaap:CostOfGoodsSold |
| Selling, general and administrative | 3 months, 2011-07-01 to 2011-09-30 | $1.2m | us-gaap:SellingGeneralAndAdministrativeExpense |
| Selling, general and administrative | 9 months, 2011-01-01 to 2011-09-30 | $4.0m | us-gaap:SellingGeneralAndAdministrativeExpense |
| Operating income | 3 months, 2011-07-01 to 2011-09-30 | $11.4m | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2011-01-01 to 2011-09-30 | $25.6m | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months, 2011-07-01 to 2011-09-30 | $3.9m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2011-01-01 to 2011-09-30 | $9.1m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2011-07-01 to 2011-09-30 | $6.1m | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2011-01-01 to 2011-09-30 | $14.5m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2011-07-01 to 2011-09-30 | $1.17 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2011-01-01 to 2011-09-30 | $2.77 | us-gaap:EarningsPerShareDiluted |
| Operating cash flow | 9 months, 2011-01-01 to 2011-09-30 | $30.7m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2011-01-01 to 2011-09-30 | $3.8m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2011-01-01 to 2011-09-30 | $993.0k | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2011-09-30 | $316.0k | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2011-09-30 | $174.8m | us-gaap:AssetsCurrent |
| Total assets | at 2011-09-30 | $439.0m | us-gaap:Assets |
| Current liabilities | at 2011-09-30 | $106.2m | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2011-09-30 | $301.5m | us-gaap:Liabilities |
| Long-term debt | at 2011-09-30 | $145.7m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2011-09-30 | $18.8m | us-gaap:LongTermDebtCurrent |
| Shareholders' equity | at 2011-09-30 | $137.6m | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 43,150 characters.

### Executive Overview

### Organization

Our business is focused on providing sustainment services for U.S. Department of Defense ("DoD") legacy systems and equipment and professional services to DoD and Federal Civilian agencies, including the United States Postal Service (“USPS”). Our operations consist primarily of logistics, engineering, equipment refurbishment, supply chain management, IT solutions, health care IT, construction management and consulting services performed on a contract basis. Substantially all of our contracts are with United States Government (“government”) agencies and other government prime contractors.

Our business is managed under operating groups consisting of one or more divisions or wholly owned subsidiaries that perform our services. Our Federal Group operations are conducted by our Communications and Engineering Division ("CED"), Engineering and Logistics Division ("ELD"), Field Support Services Division (“FSS”), and Systems Engineering Division ("SED"). Our International Group operations are conducted by our GLOBAL Division ("GLOBAL") and Fleet Maintenance Division ("FMD"). Our IT, Energy and Management Consulting Group operations are conducted by our wholly owned subsidiaries Energetics Incorporated ("Energetics"), G&B Solutions, Inc. (“G&B”), and, since August 19, 2010, Akimeka, LLC (“Akimeka”). Our Infrastructure Group operations are conducted by our wholly owned subsidiary Integrated Concepts and Research Corporation (“ICRC”). Our Supply Chain Management Group operations are conducted by our wholly owned subsidiary Wheeler Bros., Inc. (“WBI”), which we acquired on June 6, 2011.

### Segments

Our operations are conducted within five reportable segments aligned with our management groups: 1) Federal; 2) International; 3) IT, Energy and Management Consulting; 4) Infrastructure; and 5) Supply Chain Management.

**Federal Group -** Our Federal Group provides engineering, technical, management, and integrated logistics support services to U.S. military branches and other government agencies.

**CED -** CED manages our execution of programs under large omnibus contracts which support clients across DoD and the government. We have managed significant revenue generating delivery orders under the U.S. Army CECOM Rapid Response (“R2”) Program in 2011 and 2010, including our CED Assured Mobility Systems Program, under which we provided technical support services in support of U.S. Army PM Assured Mobility Systems and U.S. Army Tank-automotive and Armaments Command (“TACOM”), and our RCV Modernization Program, under which we performed maintenance work on U.S. Army Route Clearance Vehicles in Kuwait. A substantial portion of our revenue on the R2 Program resulted from the pass-through of subcontractor support services that have a low profit margin. Our contract supporting the R2 Program expired in January 2011. In July 2010, we received one of several new multiple award omnibus contracts to continue work under the R2 replacement program known as Rapid Response-Third Generation (“R2-3G”) over a five-year period of performance. While the R2-3G contract gives us the opportunity to pursue follow-on work from the original R2 contract and new work, future revenue levels from this contract cannot be determined with certainty and revenue recorded on this contract through September 30, 2011 has been minimal.

**ELD -** ELD provides full life cycle engineering, logistics, maintenance and refurbishment services to extend and enhance the life of existing vehicles and equipment. ELD’s largest program supports the U. S. Army Reserve, and ELD also provides support to the U.S. Army. Core competencies include combat and combat service support system conversions, technical research, sustainment and re-engineering, system integration and configuration management.

**FSS -** FSS provides worldwide field maintenance and logistics support services for a wide variety of military vehicles and equipment, including performance of organizational, intermediate and specialized depot-level maintenance. FSS principally supports the U.S. Army and Marine Corps by providing specialized Field Service Representatives (“FSR”) and Field Support Teams (“FST”) in areas of combat operations and austere environments.

**SED -** SED provides comprehensive systems and software engineering, logistics, and prototyping services to DoD. Our services offered through SED principally support U.S. Army, Air Force, and Marine Corps combat and combat support systems. SED’s core competencies include: systems technical support, configuration management and life cycle support for wheeled and tracked vehicles and ground support equipment; obsolescence management, service life extension, and technology insertion programs; and technical documentation and data packages.

**International Group -** Our International Group provides engineering, industrial, logistics and foreign military sales services to the U.S. military and other government agencies.

**GLOBAL -** Through GLOBAL, we provide assistance to the U.S. Navy in executing its Foreign Military Sales (“FMS”) Program for surface ships sold, leased or granted to foreign countries. GLOBAL provides program management, engineering, technical support, logistics services for ship reactivations and transfers and follow-on technical support. In September 2011, GLOBAL was awarded a successor contract to continue this program work. The successor contract is a one year contract with a maximum potential value of $277 million and four one-year options, which, if exercised, would bring the cumulative five-year maximum potential value of this contract to $1.5 billion. In October 2011, a protest to the award of the contract was filed with the U.S. Government Accountability Office (GAO), and as a result, the performance of the awarded contract is subject to an automatic stay pending the outcome of the protest. Our work continues under the predecessor contract, but the level of effort may be constrained until the protest is resolved. GAO protests are generally resolved in no more than 100 days. We believe that the contract has been properly awarded and that there is no merit to the protest.

**FMD -** FMD provides field engineering, logistics, maintenance, and information technology services to the U.S. Navy and Air Force, including fleet-wide ship and aircraft support programs. FMD’s expertise includes ship repair and modernization, ship systems installations, ordnance engineering and logistics, facility operations, war reserve materials management, and IT systems integration. FMD also provides aircraft sustainment and maintenance services to the United States Air Force under the Contract Field Teams (“CFT”) Program.

**Seized Asset Programs –** Our International Group also provides management, maintenance, storage and disposal support for seized and forfeited general property programs for the U.S. Department of Treasury (“Treasury”) and the U.S. Department of Justice, Bureau of Alcohol, Tobacco, Firearms and Explosives (“ATF”). Our cost plus incentive fee contract to support the Treasury program ended September 30, 2010 and the Department of Treasury has awarded us interim contract coverage through October 31, 2011 to continue providing services under the program. The ATF seized asset work was formerly performed under the Treasury contract, but in September 2010, ATF awarded a 10-year contract to our GLOBAL division to provide these services.

**IT, Energy and Management Consulting Group –** The IT, Energy and Management Consulting Group provides technical and consulting services primarily to various DoD and civilian government agencies.

**Energetics -** Energetics provides technical, policy, and management support in the areas of energy efficiency, sustainable energy supply, grid modernization, climate change mitigation, and infrastructure protection and resilience. Energetics supports all aspects of R&D program management, including technical and engineering analysis, strategic and collaborative planning, technology road-mapping, program evaluation and metrics, technical communications, and market transformation. Customers include the U.S. Department of Energy and its laboratories, the U.S. Department of Homeland Security, the U.S. Department of Commerce, and others.

**G&B –** G&B is an established information technology integrator providing service to many government agencies, including the Departments of Homeland Security, Interior, Labor, Agriculture, Housing and Urban Development, Health and Human Services, and Defense; the Social Security Administration; and the National Institutes of Health. G&B’s core expertise lies in enterprise architecture development, information assurance/business continuity, security risk management, program and portfolio management, network IT services, systems design and integration, data center consolidation and management, program management and quality assurance services, and product and process improvement using Lean Six Sigma and other methodologies.

**Akimeka** - Akimeka provides the DoD’s health services and logistics sector with innovative IT solutions that meet high-priority challenges. Akimeka has a technical team skilled at developing information technology (IT) health care solutions within government systems and protocols. Akimeka offers solutions in fields that include medical logistics, medical command and control, e-health, information assurance, and public safety. Most of Akimeka’s customers are in the military health system.

**Infrastructure Group –** This group consists of our ICRC subsidiary, which is engaged principally in providing engineering and transportation infrastructure services and construction management services primarily to Federal Civilian agencies. ICRC’s largest contract is with the U.S. Department of Transportation Maritime Administration for services performed on the Port of Anchorage Intermodal Expansion Project in Alaska (the "PIEP"). Seasonal variability at this location and work constraints imposed by the intermittent presence of endangered species and environmental and other factors result in fluctuations in revenues from the PIEP.

**Supply Chain Management Group –** This group consists of our WBI subsidiary, acquired in June 2011, which supplies vehicle parts primarily to government clients through a managed inventory program to USPS and direct sales to other clients, including DoD.

*Concentration of Revenues*

*(in thousands)*

*For the Nine months ended September 30,*

| Source of Revenue | 2011 Revenues% |  | 2010 Revenues% |  |
| --- | ---: | ---: | ---: | ---: |
| CED Assured Mobility Systems | $59,191 | 13 | $129,105 | 20 |
| GLOBAL FMS | 78,425 | 17 | 95,432 | 14 |
| ELD US Army Reserve | 48,580 | 10 | 45,394 | 7 |
| Treasury/ATF Seized Asset Programs | 29,956 | 6 | 37,790 | 6 |
| PIEP Contract | 20,303 | 4 | 34,869 | 5 |
| USPS NOA | 41,613 | 9 | - | - |
| RCV Modernization | 1,250 | - | 50,030 | 8 |
| Other | 190,395 | 41 | 260,972 | 40 |
| Total Revenues | $469,713 | 100 | $653,592 | 100 |

### Management Outlook

Certain events and conditions related to our business continue to present challenges with respect to sustaining our revenue levels and have combined to cause a decline in revenues in 2011. Federal budgets have been strained, government spending priorities have been changing, and there has been an increasing government emphasis on oversight activities at the expense of contract administration efforts. This is affecting the timeliness of awards and the funding of new and existing contracts in our markets, impacting the flow of work to federal contractors, causing increased competition in the federal marketplace, and resulting in a sharp increase in protests of government contract awards. Additionally, global economic conditions and political factors and the winding down and phase out of our R2 Program have affected our international work. While our government clients continue to face pressures that will challenge our ability to grow revenues, we are taking steps to diversify our business and make it more efficient.

During this period of challenge to our revenue levels, we have become leaner and more efficient, and prepared ourselves to pursue a broader range of market offerings, a more diverse client base, and more profitable work. We have kept our cost structure in balance by reducing costs as necessary in a timely manner to preserve our competitiveness and profitability. We have increased our employee workforce in our more profitable markets and identified and pursued new markets and clients through our existing businesses and acquisitions. We have built more robust capabilities in our IT offerings and have acquired a supply chain management offering. Additionally, the expiration of the R2 contract concludes a program on which we recognized a significant amount of revenue from the pass-through of subcontractor work at what was essentially our cost with very little or no profit, although it has absorbed certain indirect costs. While this decrease of subcontractor pass-through has negatively impacted our revenues, a greater reliance on direct labor revenue has improved our profit margins.

The acquisition of WBI in the second quarter of 2011 has positioned us for improvement in our profit margins, diversification of our product offerings and customer base, and more balance between the services we provide to DoD and Federal Civilian government agencies. WBI gives us a well established supply chain management capability and we expect it to add revenues and profits. WBI’s capabilities, when combined with our existing client relationships, present us with potential for future revenue growth in the DoD supply chain management market. Conversely, WBI’s relationship with the USPS, combined with our existing capabilities, also presents opportunities to leverage our legacy vehicle life extension services to a new client. These synergies have already produced results with the award of a contract from the USPS to develop and deliver a more fuel efficient repowered gasoline prototype delivery vehicle for testing within a six-month period.

The acquisition of Akimeka in 2010 increased our range of market offerings and diversified of our client base. The DoD health-related information technology services performed by Akimeka provide us with access to an expanding DoD health-related market. When combined with G&B and Energetics, we have a solid core of high level professional providers of in-demand IT and energy and management consulting services that we believe will continue to provide exceptional performance to our clients, contribute to our revenues, and improve corporate profit margins. We believe the government’s focus will continue to include emphasis on information technology, energy and management consulting, and DoD legacy systems sustainment. The government is also striving for budget efficiencies from better IT infrastructure and information management, and will be seeking innovative solutions to accomplish government cost reductions. The composition of our workforce and the services we offer are well aligned to respond to these areas of emphasis.

Our work on the GLOBAL FMS Program has presented certain challenges in 2011. FMS Program services provided to Egypt have typically accounted for approximately $50 million to $60 million in revenue annually. Due to the shutdown of certain government services and to living and working environment dangers associated with severe domestic and political unrest in Egypt, most of our work efforts performed in Egypt on the FMS Program were suspended in January 2011. As conditions stabilized, we transitioned most of our workforce back into Egypt. The duration of the disruption of our work in Egypt was temporary and reduced some of our revenues for 2011. Due to the uncertain conditions in Egypt, we cannot predict if and when future disruptions may occur or the potential impact of such disruptions on our 2011 and future financial operations.

Our employee workforce has declined slightly in 2011, primarily attributable to the expiration of the RCV Modernization Program and the completion of several task orders on our Contract Field Teams (“CFT”) Program. Government funding issues contributed to the employee decline to a lesser extent. The decline in our workforce was partially offset by the acquisition of 184 WBI employees and an increase in ICRC’s construction services workforce. As of September 30, 2011, our employee count was 2,746, compared to 2,897 as of December 31, 2010.

### Bookings and Funded Backlog

Revenues in our industry depend on contract funding (“bookings”), and funded contract backlog is an indicator of potential future revenues. Set forth below is a summary of our bookings and revenues for the nine months ended September 30, 2011 and 2010, and funded contract backlog as of September 30, 2011 and 2010:

*(in millions)*

|  | 2011 | 2010 |
| --- | ---: | ---: |
| Bookings | $396 | $673 |
| Revenues | $470 | $654 |
| Funded Contract Backlog | $305 | $493 |

We have not included approximately $21 million of funding received in the bookings and funded contract backlog amounts above for 2011 on contract awards that are currently under protest.

### Recent Accounting Pronouncements

In September 2011, the FASB issued an accounting update that gives companies the option to make a qualitative evaluation about the likelihood of goodwill impairment. Companies will be required to perform the two-step impairment test only if it concludes that the fair value of a reporting unit is more likely than not, less than its carrying value. The accounting update is effective for annual and interim goodwill impairment tests performed for fiscal years beginning after December 15, 2011, with early adoption permitted. We are evaluating the adoption of the accounting update for our goodwill impairment test to be performed as of October 1, 2011.

In June 2011, the FASB issued amendments to disclosure requirements for presentation of comprehensive income. This guidance, effective for the interim and annual periods beginning on or after December 15, 2011 (early adoption is permitted), requires presentation of total comprehensive income, the components of net income, and the components of other comprehensive income either in a single continuous statement of comprehensive income or in two separate but consecutive statements. The implementation of this amended accounting guidance is not expected to have a material impact on our consolidated financial position and results of operations.

### Critical Accounting Policies

Our consolidated financial statements are prepared in accordance with accounting principles generally accepted in the United States, which require us to make estimates and assumptions.

Please refer to our Annual Report on Form 10-K for the year ended December 31, 2010 filed with the SEC on March 2, 2011 for a full discussion of our critical accounting policies.

We have made the following addition to our critical accounting policies as a result of the acquisition of WBI.

### Revenue Recognition

Substantially all of the revenues for WBI result from supplying vehicle parts to clients. We recognize revenue from the sale of vehicle parts when the product is delivered to the customer. Revenues from sales are presented net of allowances for estimated sales returns, which are based on historical return rates.

### Revenue by Contract Type

Our revenues by contract type were as follows (in thousands):

|  | Nine months ended September 30, |  |
| --- | ---: | ---: |
| Contract Type | 2011% | 2010% |
| Cost-type | $138,497 30 | $182,754 28 |
| Time and materials | 221,862 47 | 430,067 66 |
| Fixed-price | 109,354 23 | 40,771 6 |
|  | $469,713 100 | $653,592 100 |

A significant portion of our time and materials revenues in 2010 were from the CED R2 contract, which expired in January 2011. WBI’s revenues are classified as fixed-price revenue. Accordingly, the percentages of work performed by contract type will differ in 2011 as compared to 2010.

### Results of Operations

The results of operations are as follows (in thousands):

|  | Three months ended September 30, 2011 | 2010 | Nine months ended September 30, 2011 | 2010 | Change Three Months | Nine Months |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $159,923 | $212,943 | $469,713 | $653,592 | $(53,020) | $(183,879) |
| Contract costs | 147,316 | 200,248 | 440,174 | 621,538 | (52,932) | (181,364) |
| Selling, general and administrative expenses | 1,220 | 850 | 3,970 | 1,605 | 370 | 2,365 |
| Operating Income | 11,387 | 11,845 | 25,569 | 30,449 | (458) | (4,880) |
| Interest expense, net | 1,377 | 61 | 1,961 | 75 | 1,316 | 1.886 |
| Income before income taxes | 10,010 | 11,784 | 23,608 | 30,374 | (1,774) | (6,766) |
| Provision for income taxes | 3,890 | 4,566 | 9,105 | 11,655 | (676) | (2,550) |
| Net Income | $6,120 | $7,218 | $14,503 | $18,719 | $(1,098) | $(4,216) |

Our revenues decreased approximately $53 million, or 25%, for the three months ended September 30, 2011, as compared to the same period of 2010. Revenues decreased approximately $184 million, or 28%, for the nine months ended September 30, 2011, as compared to the same period of 2010. Revenues for our Federal, International, and Infrastructure Groups declined for the third quarter and first nine months of 2011. Revenues for our IT, Energy and Management Consulting Group increased for the third quarter and first nine months of 2011. We began recording revenues for our Supply Chain Management Group upon the acquisition of WBI in June 2011.

Our operating income decreased approximately $458 thousand, or 4% for the three months ended September 30, 2011, as compared to the same period of 2010. Operating income decreased approximately $4.9 million, or 16% for the nine months ended September 30, 2011, as compared to the same period of 2010. Operating income for our Federal Group and International Group declined for the third quarter and first nine months of 2011. Operating income for our IT, Energy and Management Consulting Group decreased for the third quarter and increased for the first nine months of 2011. Operating income for our Infrastructure Group increased for the third quarter and first nine months of 2011. Our Supply Chain Management Group began generating operating income upon the acquisition of WBI in June 2011.

Changes in revenues and income are further discussed in the summaries of our segment results that follow.

Selling, general and administrative expenses consist primarily of costs and expenses that are not chargeable or reimbursable on our operating unit contracts. These expenses increased in 2011 as compared to 2010 primarily due to costs associated with the acquisition of WBI in the second quarter and to expenses associated with a work share agreement with a subcontractor and legal fees associated with protested contract awards in the third quarter.

Our effective income tax rates for the nine months ended September 30, 2011 and 2010 were 38.6% and 38.4%, respectively.

### Federal Group Results

The results of operations for our Federal Group are as follows (in thousands):

|  | Three months ended September 30, 2011 | 2010 | Nine months ended September 30, 2011 | 2010 | Change Three Months | Nine Months |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $36,479 | $103,274 | $155,574 | $361,795 | $(66,795) | $(206,221) |
| Operating Income | $1,153 | $5,593 | $5,914 | $16,436 | $(4,440) | $(10,522) |
| Profit percentage | 3.2% | 5.4% | 3.8% | 4.5% |  |  |

Revenues for our Federal Group decreased approximately $67 million or 65%, for the three months ended September 30, 2011 as compared to the same period for the prior year. Revenues decreased approximately $206 million or 57%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. The decreases in revenues for this segment resulted primarily from a decrease in revenues associated with our expiring R2 contract of approximately $58 million in the third quarter and approximately $189 million in the first nine months of 2011. Revenues on other contracts associated with our FSS services declined approximately $3.8 million for the third quarter and approximately $14.4 million for the first nine months of 2011. Revenues on other contracts associated with our SED services declined approximately $3.6 million for the third quarter and approximately $6.7 million for the first nine months of 2011.

Operating income for our Federal Group decreased approximately $4.4 million, or 79% for the three months ended September 30, 2011, as compared to the same period for the prior year. Operating income decreased approximately $10.5 million or 64%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. The decline in operating income is due to declines in profits associated with work on our expiring RCV Modernization Program on our R2 contract of approximately $121 thousand for the third quarter and approximately $2.4 million for the first nine months of 2011, and to declines in profits on other contracts. Profits on other contracts associated with our FSS services declined approximately $1.6 million for the third quarter and approximately $3.6 million for the first nine months of 2011. Profits on other contracts associated with our SED services declined by approximately $1.3 million for the third quarter and approximately $1.7 million for the first nine months of 2011. Profits on ELD’s services declined approximately $1.3 million for the third quarter and approximately $1.9 million for the first nine months of 2011.

### International Group Results

The results of operations for our International Group are as follows (in thousands):

|  | Three months ended September 30, 2011 | 2010 | Nine months ended September 30, 2011 | 2010 | Change Three Months | Nine Months |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $51,290 | $64,686 | $157,682 | $186,873 | $(13,396) | $(29,191) |
| Operating Income | $222 | $3,688 | $3,938 | $7,571 | $(3,466) | $(3,633) |
| Profit percentage | 0.4% | 5.7% | 2.5% | 4.1% |  |  |

Revenues for our International Group decreased approximately $13 million, or 21%, for the three months ended September 30, 2011 as compared to the same period for the prior year. Revenues decreased approximately $29 million or 16%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. The largest impacts on revenues for this group for the third quarter were a decline of approximately $8.6 million in revenues associated with the GLOBAL FMS Program, and a decline of approximately $4.7 million in revenues associated with the Seized Asset Programs. The largest impacts on revenues for this group for the nine month period were a decline of approximately $16 million in revenues associated with the GLOBAL FMS Program and a decline of approximately $7.8 million in revenues associated with the Seized Asset Programs.

Operating income for our International Group decreased approximately $3.5 million, or 94%, for the three months ended September 30, 2011 as compared to the same period for the prior year. Operating income decreased approximately $3.6 million or 48%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. The decline in operating income is primarily due to differences in the amount and timing of fee income recognized on the Seized Asset Programs. Under the cost plus incentive fee contract to support the Treasury Seized Asset Program that ended September 30, 2010, we recognized incentive fee of approximately $3.2 million in the third quarter of 2010 that was based on a twelve-month assessment ending September 30, 2010. The interim contract under which we performed work in 2011 is a cost plus fixed fee contract for which a lesser fee is earned and recognized as work is performed. Accordingly, there is no twelve-month fee recognition in 2011. A loss of $750 thousand associated with a work share agreement with a subcontractor also contributed to the decline in operating income for the third quarter. Profit margins in this group can vary due to fluctuations in contract activity and the timing of contract award fees associated with the GLOBAL FMS Program.

### IT, Energy and Management Consulting Group Results

The results of operations for our IT, Energy and Management Consulting Group are as follows (in thousands):

|  | Three months ended September 30, 2011 | 2010 | Nine months ended September 30, 2011 | 2010 | Change Three Months | Nine Months |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $25,905 | $25,831 | $80,871 | $67,459 | $74 | $13,412 |
| Operating Income | $3,079 | $3,534 | $9,206 | $7,968 | $(455) | $1,238 |
| Profit percentage | 11.9% | 13.7% | 11.4% | 11.8% |  |  |

Revenues for our IT, Energy and Management Consulting Group were substantially unchanged for the three months ended September 30, 2011, as compared to the same period for the prior year. Revenues increased approximately $13 million or 20%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. The increase for the nine month period resulted primarily from the inclusion of revenues of Akimeka, acquired in August 2010, in our 2011 operating results for the full period as compared to only a partial period in 2010. Akimeka revenues were approximately $7.3 million for the third quarter and $22.7 million for the first nine months of 2011. Revenues for Energetics declined approximately $1.1 million for the third quarter and increased approximately $533 thousand for the nine-month period. Revenues for G&B declined approximately $1.5 million for the third quarter and approximately $5.1 million for the nine-month period.

Operating income for this segment decreased approximately $455 thousand, or 13%, for the three months ended September 30, 2010, as compared to the same period for the prior year. Operating income increased approximately $1.2 million or 16%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. The increases for the nine-month period resulted primarily from the inclusion of revenues of Akimeka, acquired in August 2010, in our 2011 operating results for the full period as compared to only a partial period in 2010. Operating income for Energetics decreased approximately $352 thousand for the third quarter and increased approximately $499 thousand for the nine-month period. Operating income for G&B decreased approximately $343 thousand for the third quarter and approximately $1.3 million for the nine-month period.

### Infrastructure Group Results

The results of operations for our Infrastructure Group are as follows (in thousands):

|  | Three months ended September 30, 2011 | 2010 | Nine months ended September 30, 2011 | 2010 | Change Three Months | Nine Months |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $9,815 | $19,152 | $28,476 | $37,465 | $(9,337) | $(8,989) |
| Operating Income (Loss) | $159 | $(73) | $605 | $396 | $232 | $209 |
| Profit percentage | 1.6% | (0.4)% | 2.1% | 1.1% |  |  |

Revenues for this group declined approximately $9.3 million, or 49%, for the three months ended September 30, 2011, as compared to the same period for the prior year. Revenues declined approximately $9 million or 24%, for the nine months ended September 30, 2011 as compared to the same period for the prior year. Operating income for this segment increased approximately $232 thousand for the three months ended September 30, 2011, as compared to the same period for the prior year. Operating income increased approximately $209 thousand or 53%, for the nine months ended September 30, 2011 as compared to the same period for the prior year.

Changes in revenues and operating income for this segment are primarily attributable to revenue and profit activity on the PIEP. Work on this program is performed in Alaska and the level of work performed is subject to seasonal influences and differences in weather patterns during a season as compared to the same period in a prior year. During 2011, our customer has experienced delays in funding and defining the scope of work, which have contributed to our decreased revenue levels for this segment. During 2010, our customer funded the cost of certain work we performed on this project, but has not funded fees normally associated with this work pending resolution of environmental and technical issues impacting the work. Accordingly, we have not recognized fee for most of the work on this project performed in the second half of 2010. We are currently in discussions with our customer regarding resolution of the fee issue. If the fee on this work is funded, we could recognize additional revenue and operating income as high as approximately $2.2 million, which includes base and award fee.

### Supply Chain Management Group Results

The results of operations for our Supply Chain Management Group are as follows (in thousands):

|  | Three months ended September 30, 2011 | 2010 | Nine months ended September 30, 2011 | 2010 | Change Three Months | Nine Months |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues | $36,434 | $- | $47,110 | $- | $36,434 | $47,110 |
| Operating Income | $6,896 | $- | $8,823 | $- | $6,896 | $8,823 |
| Profit percentage | 18.9% |  | 18.7% |  |  |  |

This group was established and began contributing to our operating results upon our acquisition of WBI on June 6, 2011.

### Financial Condition

There has been no material adverse change in our financial condition in the first nine months of 2011. Our capital structure has changed as a result of the WBI acquisition and associated bank financing. Our bank debt increased by approximately $147 million as of September 30, 2011 compared to December 31, 2010. Changes to other asset and liability accounts were due primarily to our earnings, our level of business activity, contract delivery schedules, subcontractor and vendor payments required to perform our work, and the timing of associated billings to and collections from our customers.

### Liquidity and Capital Resources

### Cash Flows

Cash and cash equivalents decreased approximately $5.4 million during the first nine months of 2011.

Cash provided by operating activities increased approximately $20.7 million in the first nine months of 2011 as compared to the same period of 2010. This resulted from a decrease of approximately $4.2 million in cash provided by net income, an increase of approximately $2.7 million in cash from an increase in depreciation and amortization and other non-cash operating activities, and an increase of approximately $22.2 million in cash due to changes in the levels of working capital components. Of these working capital components, our largest asset is our accounts receivable and our largest liability is our accounts payable. A significant portion of our accounts receivable and accounts payable result from the use of subcontractors to perform work on our contracts and from the purchase of materials to fulfill our contract requirements. Our levels of accounts receivable and accounts payable may fluctuate significantly depending on the timing of the government services ordered, government funding delays, the timing of billings received from subcontractors and materials vendors, and the timing of payments received from government customers in payment of these services. Such timing differences may cause significant increases and decreases in our accounts receivable and accounts payable in short time periods.

We used approximately $145 million more cash in investing activities in the first nine months of 2011 as compared to the same period of 2010. Our most significant investing activity in 2011 was the acquisition of WBI for approximately $175 million.

Cash provided by financing activities increased approximately $125 million in the first nine months of 2011 as compared to the same period of 2010. This was primarily due to bank borrowing to finance our acquisition of WBI in 2011.

We paid quarterly cash dividends totaling $0.19 per share during the first three quarters of 2011. Pursuant to our loan agreement, our payment of cash dividends is subject to annual rate restrictions of $0.60 per share. We have paid cash dividends each year since 1973.

### Liquidity

Our internal sources of liquidity are primarily from operating activities, specifically from changes in the level of revenues and associated accounts receivable and accounts payable, and from profitability. Significant increases or decreases in revenues and accounts receivable and accounts payable can cause significant increases or decreases in internal liquidity. Our accounts receivable and accounts payable levels can be affected by changes in the level of the work we perform, by the timing of large materials purchases and subcontractor efforts used in our contracts, and by government delays in the award of contractual coverage and funding and payments. Government funding delays have caused delays in our ability to invoice for revenues earned, resulting in a negative impact on our days sales outstanding in 2011.

We also purchase property and equipment and invest in expansion, improvement, and maintenance of our operational and administrative facilities. From time to time, we may also invest in the acquisition of other companies. Our acquisitions of Akimeka in 2010 and WBI in 2011 required a significant use of our cash.

Our external financing consists of a loan agreement entered into in June 2011 with a group of banks to make the WBI acquisition and provide working capital for our continuing operations. The new loan agreement, which expires in June 2016, replaced a previous loan agreement and consists of a term loan, revolving loans, and letters of credit.

The term loan requires payments in quarterly installments based on an accelerating amortization schedule, with 15% of the original $125 million principal amount due in 2012 and 2013, 20% due in each of 2014 and 2015, and 30% due in 2016. The amount of term loan borrowings outstanding as of September 30, 2011 is approximately $115.6 million.

The maximum amount of credit available to us from the banking group for revolving loans and letters of credit as of September 30, 2011 was $125 million and under the loan agreement we may elect to increase this maximum availability up to $175 million. We may borrow and repay the revolving loan borrowings as our cash flows require or permit. We pay an unused commitment fee and fees on letters of credit that are issued. We had approximately $48.8 million in revolving loan amounts outstanding and $5 million of letters of credit outstanding as of September 30, 2011. During 2011, the highest outstanding revolving loan amount was $80 million, immediately after the WBI acquisition, and the lowest was $0, immediately before the WBI acquisition. The timing of certain payments made and collections received associated with our subcontractor and materials requirements and other operating expenses can cause fluctuations in our outstanding revolving loan amounts. Delays in government funding of our work performed can also cause additional borrowing requirements.

We pay interest on the term loan borrowings and revolving loan borrowings at LIBOR plus a base margin or at a base rate (typically the prime rate) plus a base margin. The LIBOR base margin as of September 30, 2011 is 2.25% and the base rate base margin as of September 30, 2011 is 0.5%. The base margins decline in steps as our Total Funded Debt/EBITDA Ratio declines. As of September 30, 2011, interest rates on portions of our outstanding debt ranged from 2.48% to 3.75%. The effective interest rate on our aggregate outstanding debt as of September 30, 2011 was 2.87%.

The loan agreement contains collateral provisions requiring VSE to provide security interest in its assets, restrictive covenants, other affirmative and negative covenants, and subjects us to certain conditions and limitations. Restrictive covenants include a maximum Total Funded Debt/EBITDA Ratio, which decreases over time, and a minimum Fixed Charge Coverage Ratio. We were in compliance with required ratios and other terms and conditions at September 30, 2011.

|  |  |  |
| --- | --- | --- |
|  | Current Maximum Ratio | Actual Ratio |
| Total Funded Debt/EBITDA Ratio | 3.50 to 1 | 2.56 to 1 |

|  |  |  |
| --- | --- | --- |
|  | Minimum Ratio | Actual Ratio |
| Fixed Charge Coverage Ratio | 1.20 to 1 | 2.12 to 1 |

We currently do not use public debt security financing.

### Inflation and Pricing

Most of our contracts provide for estimates of future labor costs to be escalated for any option periods, while the non-labor costs in our contracts are normally considered reimbursable at cost. Our property and equipment consists principally of computer systems equipment, furniture and fixtures, shop and warehouse equipment, and land and improvements. We do not expect the overall impact of inflation on replacement costs of our property and equipment to be material to our future results of operations or financial condition.

### Disclosures About Market Risk

### Interest Rates

Our bank loans provide available borrowing to us at variable interest rates. Accordingly, future interest rate changes could potentially put us at risk for a material adverse impact on future earnings and cash flows. To mitigate the risks associated with future interest rate movements, in July 2011 we employed interest rate hedges to fix the rate on a significant portion of our outstanding borrowings for various periods of time. While the immediate result of fixing these rates is an increase in the net effective rate as compared to the effective interest rate on our aggregate outstanding debt prior to July 2011, the fixed rates will protect us against future interest rate increases.

In July 2011, we entered into a three-year amortizing LIBOR interest rate swap on the term loan with a notional amount of $101 million. The swap amount amortizes as the term loan amortizes, with reductions in the swap amount occurring on the same dates and for approximately the same amounts as term loan principal repayments. With the swap in place, we will pay an effective rate on the hedged term debt of 0.56% plus our base margin from July 2011 through June 2012, and an effective rate of 1.615% plus our base margin from July 2012 through June 2014. The amount of swapped term loan debt outstanding as of September 30, 2011 is $96.3 million.

In July 2011, we entered into a two-year LIBOR interest rate swap on the revolving loan debt with a notional amount of $40 million. The swap amount declines to $20 million in June 2012, and expires in June 2013. With the swap in place, we will pay an effective rate on the hedged term debt of 0.7775% plus our base margin during the two years.

## Market risk

As filed, 133 characters.

See “Disclosures About Market Risk” in Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations.

## Controls and procedures

As filed, 1,295 characters.

As of the end of the period covered by this report, based on management's evaluation, with the participation of our Chief Executive Officer and Chief Financial Officer, of the effectiveness of the disclosure controls and procedures (as defined in Rules 13a-15(e) or 15d - 15(e) under the Securities Exchange Act of 1934, as amended) our Chief Executive Officer and Chief Financial Officer have concluded that our disclosure controls and procedures are effective in ensuring that information required to be disclosed by us in reports filed or submitted under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the Securities and Exchange Commission's rules and forms, and that information required to be disclosed by us in the reports that we file or submit under the Exchange Act is accumulated and communicated to our management, including our principal executive and principal financial officers, or persons performing similar functions, as appropriate to allow timely decisions regarding required disclosure.

There was no change in our internal control over financial reporting during our third quarter of fiscal 2011 that has materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.

Filed Oct 31, 2011.
Source: SEC EDGAR, the filing index for accession 0000102752-11-000059. Last ingested by Listed: Nov 5, 2026, 19:54 ET. No prices; not investment advice.