# Coeur Mining, Inc.: Form 10-Q for the period ended Jun 30, 2018

- Company: [Coeur Mining, Inc.](/companies/cde.md) (CIK 215466)
- Form: 10-Q
- Filed: 2018-07-25
- Accepted by EDGAR: Jul 25, 2018, 16:46 ET
- Period: 2018-06-30
- Accession: 0000215466-18-000118
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/215466/000021546618000118/cde-06301810q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/215466/000021546618000118/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2018-06-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Cost of revenue | 3 months, 2018-04-01 to 2018-06-30 | $108.2m | us-gaap:CostOfGoodsSold |
| Cost of revenue | 6 months, 2018-01-01 to 2018-06-30 | $207.6m | us-gaap:CostOfGoodsSold |
| Interest expense | 3 months, 2018-04-01 to 2018-06-30 | $6.0m | us-gaap:InterestExpense |
| Interest expense | 6 months, 2018-01-01 to 2018-06-30 | $12.0m | us-gaap:InterestExpense |
| Income tax | 3 months, 2018-04-01 to 2018-06-30 | $3.7m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 6 months, 2018-01-01 to 2018-06-30 | $15.7m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2018-04-01 to 2018-06-30 | $2.9m | us-gaap:NetIncomeLoss |
| Net income | 6 months, 2018-01-01 to 2018-06-30 | $4.2m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2018-04-01 to 2018-06-30 | $0.02 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 6 months, 2018-01-01 to 2018-06-30 | $0.02 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2018-04-01 to 2018-06-30 | $0.02 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 6 months, 2018-01-01 to 2018-06-30 | $0.02 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2018-04-01 to 2018-06-30 | 187,488,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 6 months, 2018-01-01 to 2018-06-30 | 187,557,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months, 2018-04-01 to 2018-06-30 | −$1.3m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Operating cash flow | 6 months, 2018-01-01 to 2018-06-30 | $11.6m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months, 2018-04-01 to 2018-06-30 | $41.2m | us-gaap:PaymentsToAcquireProductiveAssets |
| Capital expenditure | 6 months, 2018-01-01 to 2018-06-30 | $83.5m | us-gaap:PaymentsToAcquireProductiveAssets |
| Cash and equivalents | at 2018-06-30 | $123.5m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2018-06-30 | $313.6m | us-gaap:AssetsCurrent |
| Total assets | at 2018-06-30 | $1.64bn | us-gaap:Assets |
| Current liabilities | at 2018-06-30 | $140.6m | us-gaap:LiabilitiesCurrent |
| Current portion of debt | at 2018-06-30 | $21.7m | us-gaap:DebtCurrent |
| Shareholders' equity | at 2018-06-30 | $818.8m | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 65,409 characters.

The following Management’s Discussion and Analysis (“MD&A”) provides information that management believes is relevant to an assessment and understanding of the consolidated financial condition and results of operations of Coeur Mining, Inc. and its subsidiaries (collectively the “Company”, “our”, or “we”). We use certain non-GAAP financial performance measures in our MD&A. For a detailed description of these measures, please see “Non-GAAP Financial Performance Measures” at the end of this item. We provide certain operational and financial data on a silver equivalent basis, converting gold to silver at a historical 60:1 ratio of silver ounces to gold ounces, unless otherwise noted. We also provide realized silver equivalent data determined by average spot silver and gold prices during the relevant period.

### Overview

We are a gold, silver, zinc and lead producer with mines located in the United States, Mexico and Canada and exploration projects in the United States and Mexico. The Palmarejo complex, Rochester, Kensington and Wharf mines constitute our principal sources of revenue.

In October 2017, the Company added a new mine to Coeur’s North America-focused platform with the acquisition of the high-grade silver-zinc-lead Silvertip mine located in northern British Columbia, Canada. The Silvertip mine commenced milling in the first quarter of 2018, and is expected to commence commercial production in the third quarter of 2018. In February 2018, the Company completed the Manquiri Divestiture, which we determined to represent a strategic shift to a North America-focused mining portfolio with a major effect on the Company’s results and operations; therefore, San Bartolomé’s results of operations are reported as discontinued operations for all periods presented. In the following discussion and analysis, the operating statistics, results of operations, cash flows and financial condition that we present and discuss are those of our continuing operations unless otherwise indicated.

The Company's strategy is to discover, acquire, develop and operate low-cost silver and gold mines, which may include base metals such as zinc and lead, that produce long-term cash flow, provide opportunities for growth through continued exploration, and generate superior and sustainable returns for stockholders. Management focuses on maximizing net cash flow through identifying and implementing revenue enhancement opportunities, reducing operating and non-operating costs, exercising consistent capital discipline, and managing working capital efficiently.

### Second Quarter Highlights

- Production from continuing operations of 8.8 million silver equivalent ounces, consisting of 3.2 million silver ounces and 94,052 gold ounces
- Sales from continuing operations of 8.9 million silver equivalent ounces, consisting of 3.2 million silver ounces and 94,455 gold ounces
- Net income from continuing operations of $2.9 million, or $0.02 per share, and adjusted net income of $1.1 million, or $0.01 per share, (see “Non-GAAP Financial Performance Measures”)
- Costs applicable to sales from continuing operations were $8.29 per average spot silver equivalent ounce ($9.47 per silver equivalent ounce) and $1,040 per gold equivalent ounce (see “Non-GAAP Financial Performance Measures”)
- All-in sustaining costs from continuing operations were $14.73 per average spot silver equivalent ounce ($17.71 per silver equivalent ounce) (see “Non-GAAP Financial Performance Measures”)
- Operating cash flow used in continuing operations of $1.3 million and adjusted EBITDA from continuing operations of $48.4 million (see “Non-GAAP Financial Performance Measures”)
- Cash and cash equivalents of $123.5 million at June 30, 2018

### Selected Financial and Operating Results

*In thousands*

| Financial Results from Continuing Operations: | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Revenue | $169,987 | $149,540 | $333,254 | $335,094 |
| Net income (loss) | $2,930 | $(9,995) | $3,621 | $8,304 |
| Net income (loss) per share, diluted | $0.02 | $(0.06) | $0.02 | $0.05 |
| Adjusted net income (loss)(1) | $1,061 | $(1,343) | $1,403 | $5,423 |
| Adjusted net income (loss) per share, diluted(1) | $0.01 | $(0.01) | $0.01 | $0.03 |
| EBITDA(1) | $42,124 | $23,356 | $91,506 | $94,805 |
| Adjusted EBITDA(1) | $48,431 | $31,920 | $97,157 | $86,434 |
| **Operating Results from Continuing Operations:** |  |  |  |  |
| Silver ounces produced | 3,203,899 | 2,690,421 | 6,386,009 | 5,408,290 |
| Gold ounces produced | 94,052 | 82,819 | 179,435 | 171,037 |
| Silver equivalent ounces produced | 8,847,019 | 7,659,561 | 17,152,109 | 15,670,510 |
| Silver ounces sold | 3,202,804 | 2,688,790 | 6,363,717 | 6,014,496 |
| Gold ounces sold | 94,455 | 86,194 | 181,608 | 197,068 |
| Silver equivalent ounces sold | 8,870,100 | 7,860,417 | 17,260,190 | 17,838,597 |
| Average realized price per silver ounce | $16.48 | $16.95 | $16.59 | $17.25 |
| Average realized price per gold ounce | $1,241 | $1,206 | $1,254 | $1,174 |
| Costs applicable to sales per silver equivalent ounce(1) | $9.47 | $12.11 | $9.62 | $11.25 |
| Costs applicable to sales per average spot silver equivalent ounce(1) | $8.29 | $11.04 | $8.42 | $10.31 |
| Costs applicable to sales per gold equivalent ounce(1) | $1,040 | $866 | $1,007 | $825 |
| All-in sustaining costs per silver equivalent ounce(1) | $17.71 | $17.90 | $17.53 | $16.15 |
| All-in sustaining costs per average spot silver equivalent ounce(1) | $14.73 | $15.66 | $14.58 | $14.34 |
| **Financial and Operating Results from Discontinued Operations:(2)** |  |  |  |  |
| Income (loss) from discontinued operations | $— | $(960) | $550 | $(596) |
| Silver ounces produced | — | 1,284,561 | 643,078 | 2,499,068 |
| Gold ounces produced | — | — | 78 | — |
| Silver equivalent ounces produced | — | 1,284,561 | 647,758 | 2,499,068 |
| Silver ounces sold | — | 1,398,038 | 704,479 | 2,546,044 |
| Gold ounces sold | — | — | 292 | — |
| Silver equivalent ounces sold | — | 1,398,038 | 721,999 | 2,546,044 |

(1) See “Non-GAAP Financial Performance Measures.”

(2) Reported production and financial results include operations through February 28, 2018.

### Consolidated Financial Results

### Three Months Ended June 30, 2018 compared to Three Months Ended June 30, 2017

### Net Income (Loss) from Continuing Operations

Net income from continuing operations was $2.9 million, or $0.02 per share, compared to net loss of $10.0 million, or $0.06 per share. The increase in net income from continuing operations is due to higher ounces sold and a higher operating margin per consolidated silver equivalent ounce and a $9.3 million loss on debt extinguishment in the second quarter of 2017, partially offset by higher interest expense and a $2.3 million gain on the repurchase of the Rochester royalty obligation in the second quarter of 2017.

### Revenue

Revenue was higher due to higher silver and gold production and an increase in average realized gold prices of 3%, partially offset by a decrease in average realized silver prices of 3%. The Company sold 3.2 million silver ounces and 94,455 gold ounces, compared to sales of 2.7 million silver ounces and 86,194 gold ounces. Gold contributed 69% of sales and silver contributed 31%, compared to 70% of sales from gold and 30% from silver.

### Costs Applicable to Sales

Costs applicable to sales increased due to higher silver and gold ounces sold and higher costs applicable to sales per gold equivalent ounce, partially offset by lower costs applicable to sales per silver equivalent ounce. For a complete discussion of costs applicable to sales, see *Results of Operations* below.

### Amortization

Amortization decreased $1.3 million, or 4%, due to higher life of mine reserves and lower ounces sold at Kensington.

### Expenses

General and administrative expenses increased $0.6 million, or 9%, primarily due to higher compensation costs.

Exploration expense decreased $1.4 million, or 18%, primarily due to a drilling campaign at La Preciosa in the three months ended June 30, 2017.

Pre-development, reclamation, and other expenses decreased $0.5 million, or 11%, due to lower transaction-related costs and reduced activity at La Preciosa.

### Other Income and Expenses

During the second quarter of 2017, the Company incurred a $9.3 million loss in connection with the repurchase of the 7.875% Senior Notes due 2021 (the “2021 Senior Notes”) concurrent with the completed offering of the 2024 Senior Notes.

Non-cash fair value adjustments, net, were a loss of $2.5 million compared to a gain of $0.3 million, due to unrealized losses of $8.0 million and realized gains of $5.5 million on equity securities. Effective January 1, 2018, as a result of ASU 2016-01, changes in the fair value of equity investments are recognized as fair value adjustments instead of other comprehensive income (loss) in the Condensed Consolidated Statements of Comprehensive Income (Loss).

Interest expense (net of capitalized interest of $0.2 million) increased to $6.0 million from $3.7 million, due to higher average debt levels related to the 2024 Senior Notes and the Facility.

Other, net decreased to $0.5 million, primarily due to a $2.3 million gain on the repurchase of the Rochester royalty obligation in the second quarter of 2017.

### Income and Mining Taxes

During the second quarter of 2018, the Company reported estimated income and mining tax expense of approximately $3.7 million resulting in an effective tax rate of 55.9%. This compares to estimated income tax benefit of $1.1 million for an effective tax rate of 10.1% during the second quarter of 2017.

The following table summarizes the components of the Company’s income (loss) before tax and income and mining tax (expense) benefit:

*In thousands*

|  | Three months ended June 30, 2018 Income (loss) before tax | Tax (expense) benefit | 2017 Income (loss) before tax | Tax (expense) benefit |
| --- | ---: | ---: | ---: | ---: |
| United States | $(11,334) | $(2,309) | $(6,563) | $2,315 |
| Argentina | (180) | (108) | (129) | 945 |
| Canada | (2,155) | 1,199 | 6 | 940 |
| Mexico | 20,542 | (2,499) | (2,195) | (4,766) |
| Other jurisdictions | (226) | — | (2,241) | 1,693 |
|  | $6,647 | $(3,717) | $(11,122) | $1,127 |

The Company’s effective income and mining tax rate is a function of the combined effective tax rates and foreign exchange rates in the jurisdictions in which it operates. Variations in the jurisdictional mix of income and loss and foreign exchange rates result in significant fluctuations in the consolidated effective tax rate, along with mining taxes, uncertain tax positions, and a full valuation allowance on deferred tax assets related to losses in the United States and certain foreign jurisdictions. Fluctuations in foreign exchange rates on deferred tax balances decreased income and mining tax expense by $4.5 million and increased income and mining tax expense by $3.0 million for the three months ended June 30, 2018 and 2017, respectively, predominantly due to the Mexican Peso.

A valuation allowance is provided for deferred tax assets for which it is more likely than not that the related tax benefits will not be realized. The Company analyzes its deferred tax assets and, if it is determined that the Company will not realize all or a portion of its deferred tax assets, it will record or increase a valuation allowance. Conversely, if it is determined that the Company will ultimately be more likely than not able to realize all or a portion of the related benefits for which a valuation allowance has been provided, all or a portion of the related valuation allowance will be reduced. There are a number of factors that impact the Company’s ability to realize its deferred tax assets.

### Six Months Ended June 30, 2018 compared to Six Months Ended June 30, 2017

### Net Income (Loss) from Continuing Operations

Net income from continuing operations was $3.6 million, or $0.02 per share, compared to net income of $8.3 million, or $0.05 per share. The decrease in net income from continuing operations is due to a $21.1 million gain on the sale of the Joaquin project and a $2.3 million gain on the repurchase of the Rochester royalty obligation in 2017, partially offset by a higher operating margin per consolidated silver equivalent ounce during the first half of 2018 and a $9.3 million loss on debt extinguishment in 2017.

### Revenue

Revenue was lower resulting from holdover gold ounces from 2016 that were sold in the first quarter of 2017 and a decrease in average realized silver prices of 4%, partially offset by higher silver ounces sold and an increase in average realized gold prices of 7%. The Company sold 6.4 million silver ounces and 181,608 gold ounces, compared to sales of 6.0 million silver ounces and 197,068 gold ounces. Gold contributed 68% of sales and silver contributed 32%, compared to 69% of sales from gold and 31% from silver.

### Costs Applicable to Sales

Costs applicable to sales decreased primarily due to lower costs applicable to sales per silver equivalent ounce at Palmarejo, partially offset by higher costs applicable to sales per gold equivalent ounce. For a complete discussion of costs applicable to sales, see *Results of Operations* below.

### Amortization

Amortization decreased $9.2 million or 13%, due to higher life of mine reserves at Kensington and Palmarejo and lower ounces sold at Kensington.

### Expenses

General and administrative expenses decreased $0.7 million or 4%, primarily due to lower professional service costs.

Exploration expense remained comparable at $13.1 million.

Pre-development, reclamation, and other expenses decreased $0.1 million or 1%, due to lower transaction-related costs and reduced activity at La Preciosa.

### Other Income and Expenses

During the second half of 2017, the Company incurred a $9.3 million loss in connection with the repurchase of the 2021 7.875% Senior Notes concurrent with the completed offering of the 2024 5.875% Senior Notes.

Non-cash fair value adjustments, net, were a gain of $2.2 million compared to a loss of $0.9 million due to unrealized losses of $3.2 million and realized gains of $5.2 million on equity securities and a favorable fair value adjustment on zinc hedges. Effective January 1, 2018, as a result of ASU 2016-01, changes in the fair value of equity investments are recognized as fair value adjustments instead of other comprehensive income (loss) in the Condensed Consolidated Statements of Comprehensive Income (Loss).

Interest expense (net of capitalized interest of $0.3 million) increased to $12.0 million from $7.3 million, due to higher average debt levels related to the 2024 Senior Notes and the Facility.

Other, net decreased to $1.1 million, primarily due to a $21.1 million gain on the sale of the Joaquin project and a $2.3 million gain on the repurchase of the Rochester royalty obligation in 2017.

### Income and Mining Taxes

During the first half of 2018, the Company reported estimated income and mining tax expense of approximately $15.7 million resulting in an effective tax rate of 81.2%. This compares to estimated income tax expense of $9.8 million for an effective tax rate of 54.0% during the half quarter of 2017.

The following table summarizes the components of the Company’s income (loss) before tax and income and mining tax (expense) benefit:

*In thousands*

|  | Six months ended June 30, 2018 Income (loss) before tax | Tax (expense) benefit | 2017 Income (loss) before tax | Tax (expense) benefit |
| --- | ---: | ---: | ---: | ---: |
| United States | $(10,147) | $(1,792) | $14,090 | $213 |
| Argentina | 74 | (97) | (457) | 2,070 |
| Canada | (3,909) | 2,044 | 8 | 908 |
| Mexico | 33,669 | (15,821) | 6,455 | (14,689) |
| Other jurisdictions | (400) | — | (2,041) | 1,747 |
|  | $19,287 | $(15,666) | $18,055 | $(9,751) |

The Company’s effective income and mining tax rate is a function of the combined effective tax rates and foreign exchange rates in the jurisdictions in which it operates. Variations in the jurisdictional mix of income and loss and foreign exchange rates result in significant fluctuations in the consolidated effective tax rate, along with income and mining taxes, uncertain tax positions, and a full valuation allowance on deferred tax assets related to losses in the United States and certain foreign jurisdictions. Fluctuations in foreign exchange rates on deferred tax balances decreased income and mining tax expense by $0.9 million and increased income and mining tax expense by $8.6 million for the six months ended June 30, 2018 and 2017, respectively. The 2018 fluctuation was predominantly due to the Canadian Dollar and the 2017 fluctuation was predominantly due to the Mexican Peso.

A valuation allowance is provided for deferred tax assets for which it is more likely than not that the related tax benefits will not be realized. The Company analyzes its deferred tax assets and, if it is determined that the Company will not realize all or a portion of its deferred tax assets, it will record or increase a valuation allowance. Conversely, if it is determined that the Company will ultimately be more likely than not able to realize all or a portion of the related benefits for which a valuation allowance has been provided, all or a portion of the related valuation allowance will be reduced. There are a number of factors that impact the Company’s ability to realize its deferred tax assets.

### Income (loss) from Discontinued Operations

In respect of San Bartolomé’s operating results, income increased $1.1 million, due to a $1.5 million gain on the sale of San Bartolomé in 2018, partially offset by lower production and higher unit costs.

### 2018 Outlook

Coeur's 2018 production guidance has been revised to reflect higher expected silver and gold production at Palmarejo due to higher-than-projected grades during the first half of the year. The Company’s cost guidance has been reduced to account for strong first half cost performance at Palmarejo, timing of anticipated commercial production at Silvertip and accelerated investment in near-mine exploration.

### 2018 Production Outlook

|  | Silver (K oz) | Gold (oz) | Zinc (K lbs) | Lead (K lbs) | Silver Equivalent1 (K oz) |
| --- | --- | --- | ---: | ---: | --- |
| **Palmarejo** | 7,500 - 7,900 | 115,000 - 120,000 | — | — | 14,400 - 15,100 |
| **Rochester** | 4,200 - 4,700 | 45,000 - 50,000 | — | — | 6,900 - 7,700 |
| **Kensington** | — | 115,000 - 120,000 | — | — | 6,900 - 7,200 |
| **Wharf** | — | 85,000 - 90,000 | — | — | 5,100 - 5,400 |
| **Silvertip** | 1,500 - 2,000 | — | 23,000 - 28,000 | 23,000 - 28,000 | 4,030 - 5,080 |
| **Total** | 13,200 - 14,600 | 360,000 - 380,000 | 23,000 - 28,000 | 23,000 - 28,000 | 37,330 - 40,480 |

### 2018 Cost Outlook

|  | Previous Guidance | Current Guidance |
| --- | --- | --- |
| **(dollars in millions, except per ounce amounts)** | **60:1** | **60:1** |
| **CAS per AgEqOz1 – Palmarejo** | $10.50 - $11.00 | $9.00 - $9.50 |
| **CAS per AgEqOz1 – Rochester** | $13.25 - $13.75 | $13.25 - $13.75 |
| **CAS per AuOz1 – Kensington** | $900 - $950 | $900 - $950 |
| **CAS per AuEqOz1 – Wharf** | $850 - $900 | $850 - $900 |
| **CAS per AgEqOz1 – Silvertip** | $15.00 - $15.50 | $15.00 - $15.50 |
| **Capital Expenditures** | $120 - $140 | $130 - $150 |
| **General and Administrative Expenses** | $32 - $34 | $32 - $34 |
| **Exploration Expense** | $20 - $25 | $25 - $30 |
| **AISC per AgEqOz1 from continuing operations** | $17.50 - $18.00 | $17.25 - $17.75 |

### Results of Continuing Operations

The Company produced 3.2 million ounces of silver and 94,052 ounces of gold in the three months ended June 30, 2018, compared to 2.7 million ounces of silver and 82,819 ounces of gold in the three months ended June 30, 2017. Silver production increased 19% due to higher grade and mill throughput at Palmarejo, partially offset by lower placed tons at Rochester. Gold production increased 14% due to higher grades at Palmarejo and Rochester, higher mill throughput at Palmarejo, and timing of leach pad recoveries at Wharf, partially offset by lower grade at Kensington.

The Company produced 6.4 million ounces of silver and 179,435 ounces of gold in the six months ended June 30, 2018, compared to 5.4 million ounces of silver and 171,037 ounces of gold in the six months ended June 30, 2017. Silver production increased 18% due to higher grade and mill throughput at Palmarejo. Gold production increased 5% due to higher grades at Palmarejo and Rochester and higher mill throughput at Palmarejo, partially offset by lower grade at Kensington.

Costs applicable to sales were $8.29 per average spot silver equivalent ounce ($9.47 per silver equivalent ounce) and $1,040 per gold equivalent ounce in the three months ended June 30, 2018 compared to $11.04 per average spot silver equivalent ounce ($12.11 per silver equivalent ounce) and $866 per gold equivalent ounce in the three months ended June 30, 2017. Costs applicable to sales per silver equivalent ounce decreased 22% due to lower unit costs at Palmarejo while costs applicable to sales per gold equivalent ounce increased 20% in the three months ended June 30, 2018 due to higher unit costs at Kensington and Wharf.

Costs applicable to sales were $8.42 per average spot silver equivalent ounce ($9.62 per silver equivalent ounce) and $1,007 per gold equivalent ounce in the six months ended June 30, 2018 compared to $10.31 per average spot silver equivalent ounce ($11.25 per silver equivalent ounce) and $825 per gold equivalent ounce in the six months ended June 30, 2017. Costs applicable to sales per silver equivalent ounce decreased 14% due to lower unit costs at Palmarejo while costs applicable to sales per gold equivalent ounce increased 22% in the six months ended June 30, 2018 due to higher unit costs at Kensington and Wharf.

All-in sustaining costs were $14.73 per average spot silver equivalent ounce ($17.71 per silver equivalent ounce) in the three months ended June 30, 2018, compared to $15.66 per average spot silver equivalent ounce ($17.90 per silver equivalent ounce) in the three months ended June 30, 2017. The 1% decrease was primarily due to lower costs applicable to sales per consolidated silver equivalent ounce, partially offset by higher sustaining capital related to underground development at Palmarejo and Kensington.

All-in sustaining costs were $14.58 per average spot silver equivalent ounce ($17.53 per silver equivalent ounce) in the six months ended June 30, 2018, compared to $14.34 per average spot silver equivalent ounce ($16.15 per silver equivalent ounce) in the six months ended June 30, 2017. The 9% increase was primarily due to higher sustaining capital related to underground development at Palmarejo and Kensington and higher exploration costs, partially offset by lower costs applicable to sales per consolidated silver equivalent ounce.

### Palmarejo

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Tons milled | 344,073 | 335,428 | 703,966 | 695,811 |
| Silver ounces produced | 2,065,523 | 1,456,821 | 4,078,762 | 2,987,362 |
| Gold ounces produced | 33,702 | 24,292 | 63,598 | 55,084 |
| Silver equivalent ounces produced | 4,087,643 | 2,914,341 | 7,894,642 | 6,292,402 |
| Costs applicable to sales per silver equivalent oz(1) | $7.65 | $11.31 | $7.82 | $10.36 |
| Costs applicable to sales per average spot silver equivalent oz(1) | $6.65 | $10.20 | $6.79 | $9.40 |

(1) See Non-GAAP Financial Performance Measures.

#### Three Months Ended June 30, 2018 compared to Three Months Ended June 30, 2017

Silver equivalent production increased 40% due to higher mining rates from Independencia and higher silver and gold grade. Metal sales were $70.7 million, or 41% of Coeur’s metal sales, compared with $53.2 million, or 35% of Coeur’s metal sales. Costs applicable to sales per ounce decreased 32% as a result of higher production. Amortization remained comparable at $14.6 million primarily due to higher life of mine reserves, partially offset by higher production driven by higher grades. Capital expenditures decreased to $9.5 million due to less underground development at Guadalupe and Independencia.

#### Six Months Ended June 30, 2018 compared to Six Months Ended June 30, 2017

Silver equivalent production increased 25% due to higher mining rates from Independencia and higher silver and gold grade, partially offset by lower silver and gold recovery. Metal sales were $140.8 million, or 42% of Coeur’s metal sales, compared with $130.9 million, or 40% of Coeur’s metal sales. Costs applicable to sales per ounce decreased 25% as a result of higher production. Amortization decreased to $31.0 million compared to $34.6 million, primarily due to higher life of mine reserves, partially offset by higher production. Capital expenditures increased to $18.8 million due to underground development at Guadalupe and Independencia.

### Rochester

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Tons placed | 4,083,028 | 4,493,100 | 8,434,159 | 8,006,808 |
| Silver ounces produced | 1,125,074 | 1,156,341 | 2,282,100 | 2,283,663 |
| Gold ounces produced | 12,273 | 10,745 | 23,760 | 21,101 |
| Silver equivalent ounces produced | 1,861,454 | 1,801,041 | 3,707,700 | 3,549,723 |
| Costs applicable to sales per silver equivalent oz(1) | $13.44 | $13.62 | $13.51 | $13.05 |
| Costs applicable to sales per average spot silver equivalent oz(1) | $11.94 | $12.63 | $12.03 | $12.17 |

(1) See Non-GAAP Financial Performance Measures.

#### Three Months Ended June 30, 2018 compared to Three Months Ended June 30, 2017

Silver equivalent production increased 3% due to higher silver and gold grade, partially offset by lower tons placed. Metal sales were $33.7 million, or 20% of Coeur’s metal sales, compared with $32.8 million, or 22% of Coeur’s metal sales. Costs applicable to sales per ounce were comparable. Amortization remained comparable at $4.8 million. Capital expenditures decreased to $0.7 million from $13.8 million due to the completion of the Stage IV leach pad expansion in 2017.

#### Six Months Ended June 30, 2018 compared to Six Months Ended June 30, 2017

Silver equivalent production increased 4% due to higher tons placed, partially offset by lower silver grade. Metal sales were $67.2 million, or 20% of Coeur’s metal sales, compared with $71.8 million, or 21% of Coeur’s metal sales. Costs applicable to sales per silver equivalent ounce increased 4% due to higher diesel, maintenance, and blasting costs. Amortization decreased to $9.6 million due to lower ounces sold. Capital expenditures decreased to $3.3 million compared to $24.4 million due to the completion of the Stage IV leach pad expansion in 2017.

### Wharf

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Tons placed | 1,075,820 | 993,167 | 2,152,215 | 2,285,348 |
| Gold ounces produced | 22,507 | 21,358 | 40,443 | 42,231 |
| Silver ounces produced | 13,302 | 12,587 | 25,147 | 32,652 |
| Gold equivalent ounces produced(1) | 22,729 | 21,568 | 40,862 | 42,775 |
| Costs applicable to sales per gold equivalent oz(1) | $827 | $734 | $847 | $696 |

(1) See Non-GAAP Financial Performance Measures.

#### Three Months Ended June 30, 2018 compared to Three Months Ended June 30, 2017

Gold equivalent production increased 5% due to the timing of leach pad recoveries. Metal sales were $29.8 million, or 18% of Coeur’s metal sales, compared to $27.0 million, or 18% of Coeur’s metal sales. Costs applicable to sales per gold equivalent ounce increased 13% due to lower production resulting from the completion of mining at the higher-grade Golden Reward deposit in 2017 and higher diesel costs. Amortization was $3.4 million compared to $2.5 million due to higher ounces sold. Capital expenditures decreased to $1.2 million.

#### Six Months Ended June 30, 2018 compared to Six Months Ended June 30, 2017

Gold equivalent production decreased 4% due to the timing of leach pad recoveries. Metal sales were $53.3 million, or 16% of Coeur’s metal sales, compared to $57.3 million, or 17% of Coeur’s metal sales. Costs applicable to sales per gold equivalent ounce increased 22% due to lower production resulting from the completion of mining at the higher-grade Golden Reward deposit in 2017, higher pad unloading costs, and higher diesel costs. Amortization remained comparable at $6.0 million. Capital expenditures decreased to $1.5 million.

### Kensington

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Tons milled | 168,751 | 163,163 | 327,457 | 329,058 |
| Gold ounces produced | 25,570 | 26,424 | 51,634 | 52,621 |
| Costs applicable to sales/oz(1) | $1,215 | $964 | $1,124 | $922 |

(1) See Non-GAAP Financial Performance Measures.

#### Three Months Ended June 30, 2018 compared to Three Months Ended June 30, 2017

Gold production decreased 3% due to lower grade. Metal sales were $35.7 million, or 21% of Coeur’s metal sales, compared to $35.6 million, or 24% of Coeur’s metal sales. Costs applicable to sales per ounce were 26% higher, primarily due to lower production, higher diesel costs, and higher contract mining costs. Amortization decreased to $6.4 million from $8.3 million due to higher life of mine reserves and lower ounces sold. Capital expenditures increased to $10.7 million due to expansion of the site power plant.

#### Six Months Ended June 30, 2018 compared to Six Months Ended June 30, 2017

Gold production remained comparable. Metal sales were $72.0 million, or 22% of Coeur’s metal sales, compared to $73.5 million, or 22% of Coeur’s metal sales. Costs applicable to sales per ounce were 22% higher, primarily due to lower production, higher diesel costs, and higher contract mining costs. Amortization decreased to $13.2 million from $17.5 million due to higher life of mine reserves and lower ounces sold. Capital expenditures increased to $22.1 million due to expansion of the site power plant.

### Endeavor Silver Stream

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Tons milled | — | 88,565 | — | 133,905 |
| Silver ounces produced | — | 64,672 | — | 104,613 |
| Costs applicable to sales/oz(1) | $— | $7.06 | $— | 7.12 |

(1) See Non-GAAP Financial Performance Measures.

In July 2017, the Company sold the Endeavor Silver Stream and our remaining portfolio of royalties for total consideration of $13.0 million to Metalla Royalty & Streaming Ltd. Reported production and financial results include operations through May 2017 in accordance with the terms of the sale agreement.

### Liquidity and Capital Resources

Cash and cash equivalents decreased $68.5 million in the six months ended June 30, 2018 as a result of pre-production capital expenditures to advance Silvertip toward commercial production, income and mining tax payments at Palmarejo and an increase in inventories, partially offset by a higher operating margin per consolidated silver equivalent ounce.

### Cash Provided by (Used in) Operating Activities from Continuing Operations

Net cash used in operating activities for the three months ended June 30, 2018 was $1.3 million compared to net cash provided by operating activities of $24.1 million for the three months ended June 30, 2017. Net cash provided by operating activities for the six months ended June 30, 2018 was $14.2 million compared to $68.0 million for the six months ended June 30, 2017. Net cash provided by (used in) operating activities was impacted by the following key factors for the applicable periods:

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Consolidated silver equivalent ounces sold | 8,870,100 | 7,860,417 | 17,260,190 | 17,838,597 |
| Average realized price per consolidated silver equivalent ounce | $19.16 | $19.02 | $19.31 | $18.78 |
| Costs applicable to sales per consolidated silver equivalent ounce (1) | (12.20) | (13.01) | (12.03) | (12.15) |
| Operating margin per consolidated silver equivalent ounce | $6.96 | $6.01 | $7.28 | $6.63 |

(1) See Non-GAAP Financial Performance Measures.

*In thousands*

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Cash flow before changes in operating assets and liabilities | $41,496 | $27,235 | $74,936 | $70,524 |
| Changes in operating assets and liabilities: |  |  |  |  |
| Receivables | (8,888) | (2,215) | (10,579) | 3,465 |
| Prepaid expenses and other | 8,126 | 4,061 | 2,491 | (845) |
| Inventories | (2,766) | (4,809) | (11,474) | 10,362 |
| Accounts payable and accrued liabilities | (39,262) | (167) | (41,127) | (15,466) |
| Cash provided by continuing operating activities | $(1,294) | $24,105 | $14,247 | $68,040 |

Cash used in operating activities decreased $25.4 million for the three months ended June 30, 2018 compared to the three months ended June 30, 2017, primarily due to income and mining tax payments at Palmarejo, partially offset by higher silver equivalent ounces sold and a higher operating margin per consolidated silver equivalent ounce. Revenue for the three months ended June 30, 2018 increased $20.4 million, $18.7 million of which was due to higher silver equivalent ounces sold and $1.7 million due to higher average realized prices. The $42.8 million working capital increase in the three months ended June 30, 2018 was primarily due to the timing of income and mining tax payments at Palmarejo and the timing of accounts receivable and VAT collections, partially offset by a decrease in prepaid assets, compared to the $3.1 million working capital increase in the three months ended June 30, 2017, which was primarily due to an increase of inventories and accounts receivable.

Cash provided by operating activities decreased $53.8 million for the six months ended June 30, 2018 compared to the six months ended June 30, 2017, primarily due to income and mining tax payments at Palmarejo, lower silver equivalent ounces sold and an increase in inventories, partially offset by a higher operating margin per consolidated silver equivalent ounce. Revenue for the six months ended June 30, 2018 decreased $1.8 million, $13.6 million of which was due to lower silver equivalent ounces sold, partially offset by $11.7 million due to higher average realized prices. The $60.7 million working capital increase in the six months ended June 30, 2018 was primarily due to the timing of income and mining tax payments at Palmarejo, an increase in inventories and the timing on accounts receivable and VAT collections, compared to the $2.5 million working capital increase in the six months ended June 30, 2017, which was primarily due to a reduction of inventories carried over from the fourth quarter of 2016 and the collection of accounts receivable, partially offset by the timing of payments.

### Cash (Used in) Investing Activities from Continuing Operations

Net cash used in investing activities in the three months ended June 30, 2018 was $30.0 million compared to net cash used in investing activities of $44.8 million in the three months ended June 30, 2017, primarily due to the proceeds from the sale of strategic equity investments, partially offset by capital expenditures at Silvertip, and the acquisition of strategic equity investments in 2017. The Company had capital expenditures of $41.2 million in the three months ended June 30, 2018 compared with $37.1 million in the three months ended June 30, 2017. Capital expenditures in the three months ended June 30, 2018 were primarily related to pre-production capital spending at Silvertip and underground development at Silvertip, Palmarejo, and Kensington. Capital expenditures in the three months ended June 30, 2017 were primarily related to underground development at Palmarejo and Kensington and the Stage IV leach pad expansion at Rochester.

Net cash used in investing activities in the six months ended June 30, 2018 was $71.1 million compared to net cash used in investing activities of $44.4 million in the six months ended June 30, 2017, primarily due to capital expenditures at Silvertip and the proceeds from the sale of the Joaquin project in the first quarter of 2017. The Company had capital expenditures of $83.5 million in the six months ended June 30, 2018 compared with $60.7 million in the six months ended June 30, 2017. Capital expenditures in the six months ended June 30, 2018 were primarily related to pre-production capital spending at Silvertip and underground development at Silvertip, Palmarejo, and Kensington. Capital expenditures in the six months ended June 30, 2017 were primarily related to underground development at Palmarejo and Kensington and the Stage IV leach pad expansion at Rochester.

### Cash Provided by (Used in) Financing Activities from Continuing Operations

Net cash used in financing activities in the three months ended June 30, 2018 was $4.6 million compared to net cash provided by financing activities of $55.6 million in the three months ended June 30, 2017. During the three months ended June 30, 2017, the Company received net proceeds of approximately $245.0 million from the issuance of the 2024 Senior Notes, partially offset by the repurchase of the 2021 Senior Notes for $185.5 million, including premiums.

Net cash used in financing activities in the six months ended June 30, 2018 was $12.7 million compared to net cash provided by financing activities of $49.1 million in the six months ended June 30, 2017. During the six months ended June 30, 2018, the Company drew $15.0 million from the Facility to repay Silvertip’s debt obligation. In addition, the Company had higher tax withholdings on vested stock-based compensation awards. During the six months ended June 30, 2017, the Company received net proceeds of approximately $245.0 million from the issuance of the 2024 Senior Notes, partially offset by the repurchase of the 2021 Senior Notes for $185.5 million, including premiums.

### Critical Accounting Policies and Accounting Developments

Please see Note 2 – SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES contained in the Company’s Form

10-K for the year ended December 31, 2017 (the “2017 10-K”) and in Note 2 - SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES contain in this Report for the Company’s critical accounting policies and estimates.

### Revenue Recognition

On January 1, 2018, the Company adopted the updated revenue guidance applicable under ASC 606 - “*Revenue from Contracts with Customers”*. The new guidance creates a five-step framework to determine revenue recognition:

1\. Identify the contract with the customer

2\. Identify the performance obligations

3\. Determine the transaction price

4\. Allocate the transaction price to the performance obligations

5\. Recognize revenue when (or as) the entity satisfies a performance obligation

The Company produces doré and concentrate that is shipped to third-party refiners and smelters, respectively, for processing. The Company enters into contracts to sell its metal to various third-party customers which may include the refiners and smelters that process the doré and concentrate. The Company’s performance obligation in these transactions is generally the transfer of metal to the customer.

In the case of doré shipments, the Company generally sells refined metal at market prices agreed upon by both parties. The Company also has the right, but not the obligation, to sell a portion of the anticipated refined metal in advance of being fully refined. When the Company sells refined metal or advanced metal, the performance obligation is satisfied when the metal is delivered to the customer. *Revenue* and *Costs Applicable to Sales* are recorded on a gross basis under these contracts at the time the performance obligation is satisfied.

Under the Company’s concentrate sales contracts with third-party smelters, metal prices are set on a specified future quotational period, typically one to three months, after the shipment date based on market prices. When the Company sells gold concentrate to the third-party smelters, the performance obligation is satisfied when the concentrate is loaded onto the third-party shipping vessel. The contracts, in general, provide for provisional payment based upon provisional assays and historical metal prices. Final settlement is based on the applicable price for the specified future quotational period and generally occurs three to six months after shipment. The Company’s provisionally priced sales contain an embedded derivative that is required to be separated from the host contract for accounting purposes. The host contract is the receivable from the sale of concentrates measured at the forward price at the time of sale. The embedded derivative does not qualify for hedge accounting and is adjusted to fair value through revenue each period until the date of final metal settlement.

The Company also sells concentrate under off-take agreements to third-party customers that are responsible for arranging the smelting of the concentrate. Prices are can either be fixed or based on a quotational period. The quotational period varies by contract, but is generally a one-month period following the shipment of the concentrate. The performance obligation is satisfied when the concentrate is loaded onto the third-party shipping vessel. The off-take agreement allows for the Company to sell concentrate in advance of shipment and results in the customer taking ownership of the concentrate prior to shipment.

The Company recognizes revenue from concentrate sales, net of treatment and refining charges, when it satisfies the performance obligation of transferring control of the concentrate to the customer.

For doré and off-take sales, the Company may incur a finance charge related to advance sales that is not considered significant and, as such, is not considered a separate performance obligation. In addition, the Company has elected to treat freight costs as a fulfillment cost under ASC 606 and not as a separate performance obligation.

The Company’s streaming agreement with a subsidiary of Franco-Nevada commenced in 2016 with a $20.0 million deposit paid by Franco-Nevada in exchange for the right and obligation to purchase 50% of a portion of Palmarejo gold production at the lesser of $800 or market price per ounce. Because there is no minimum obligation associated with this deposit, it is not considered financing, and each shipment is considered to be a separate performance obligation. The streaming agreement represents a contract liability under ASC 606, which requires the Company to ratably recognize a portion of the deposit as revenue for each gold ounce delivered to Franco-Nevada.

### Other Liquidity Matters

We believe that our liquidity and capital resources from U.S. operations are adequate to fund our U.S. operations and corporate activities. The Company has asserted indefinite reinvestment of earnings from its Mexican operations as determined by management’s judgment about and intentions concerning the future operations of the Company. The Company does not believe that the amounts reinvested will have a material impact on liquidity.

In order to reduce future cash interest payments and/or amounts due at maturity or upon redemption, from time to time we may repurchase certain of our debt securities for cash or in exchange for other securities, which may include secured or unsecured notes or equity, in each case in open market or privately negotiated transactions. We regularly engage in conversations with our bondholders and evaluate any such transactions in light of prevailing market conditions, liquidity requirements, contractual restrictions, and other factors. The amounts involved may be significant and any such transactions may occur at a substantial discount to the debt securities’ face amount.

### Non-GAAP Financial Performance Measures

Non-GAAP financial measures are intended to provide additional information only and do not have any standard meaning prescribed by generally accepted accounting principles (“GAAP”). Unless otherwise noted, we present the Non-GAAP financial measures of our continuing operations in the tables below. For additional information regarding our discontinued operations, see Note 21 -- to the Condensed Consolidated Financial Statements. These measures should not be considered in isolation or as a substitute for performance measures prepared in accordance with GAAP.

### Adjusted Net Income (Loss)

Management uses *Adjusted net income (loss)* to evaluate the Company’s operating performance, and to plan and forecast its operations. The Company believes the use of *Adjusted net income (loss)* reflects the underlying operating performance of our core mining business and allows investors and analysts to compare results of the Company to similar results of other mining companies. Management’s determination of the components of *Adjusted net income (loss*) are evaluated periodically and is based, in part, on a review of non-GAAP financial measures used by mining industry analysts. The tax effect of adjustments are based on statutory tax rates and the Company’s tax attributes, including the impact through the Company’s valuation allowance. The combined effective rate of tax adjustments may not be consistent with the statutory tax rates or the Company’s effective tax rate due to jurisdictional tax attributes and related valuation allowance impacts which may minimize the tax effect of certain adjustments and may not apply to gains and losses equally. *Adjusted net income (loss)* is reconciled to *Net income (loss)* in the table below:

*In thousands except per share amounts*

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Net income (loss) | $2,930 | $(10,955) | $4,171 | $7,708 |
| (Income) loss from discontinued operations, net of tax | — | 960 | (550) | 596 |
| Fair value adjustments, net | 2,462 | (336) | (2,192) | 864 |
| Impairment of equity and debt securities | — | 305 | — | 426 |
| Gain on sale of Joaquin project | — | — | — | (21,138) |
| (Gain) loss on sale of assets and securities | (586) | (513) | (345) | 1,553 |
| Gain on repurchase of Rochester royalty | — | (2,332) | — | (2,332) |
| (Gain) loss on debt extinguishment | — | 9,342 | — | 9,342 |
| Mexico inflation adjustment | (1,939) | — | (1,939) | — |
| Interest income on notes receivables | (573) | — | (821) | — |
| Foreign exchange loss (gain) | (1,233) | 2,186 | 3,079 | 6,597 |
| Tax effect of adjustments(1) | — | — | — | 1,807 |
| **Adjusted net income (loss)** | $1,061 | $(1,343) | $1,403 | $5,423 |
| **Adjusted net income (loss) per share - Basic** | $0.01 | $(0.01) | $0.01 | $0.03 |
| **Adjusted net income (loss) per share - Diluted** | $0.01 | $(0.01) | $0.01 | $0.03 |

(1) For the six months ended June 30, 2017, tax effect of adjustments of $1.8 million (-16%) is primarily related to a taxable gain on the sale of the Joaquin project.

### EBITDA and Adjusted EBITDA

Management uses *EBITDA* to evaluate the Company’s operating performance, to plan and forecast its operations, and assess leverage levels and liquidity measures. The Company believes the use of *EBITDA* reflects the underlying operating performance of our core mining business and allows investors and analysts to compare results of the Company to similar results of other mining companies. *Adjusted EBITDA* is a measure used in the 2024 Senior Notes Indenture and the Facility to determine our ability to make certain payments and incur additional indebtedness. *EBITDA* and *Adjusted EBITDA* do not represent, and should not be considered an alternative to, *Net income (Loss)* or *Cash Flow from Operations* as determined under GAAP. Other companies may calculate *Adjusted EBITDA* differently and those calculations may not be comparable to our presentation. *Adjusted EBITDA* is reconciled to *Net income (loss)* in the table below:

*In thousands except per share amounts*

|  | Three months ended June 30, 2018 | 2017 | Six months ended June 30, 2018 | 2017 |
| --- | ---: | ---: | ---: | ---: |
| Net income (loss) | $2,930 | $(10,955) | $4,171 | $7,708 |
| (Income) loss from discontinued operations, net of tax | — | 960 | (550) | 596 |
| Interest expense, net of capitalized interest | 6,018 | 3,744 | 11,983 | 7,323 |
| Income tax provision (benefit) | 3,717 | (1,127) | 15,666 | 9,751 |
| Amortization | 29,459 | 30,734 | 60,236 | 69,427 |
| **EBITDA** | 42,124 | 23,356 | 91,506 | 94,805 |
| Fair value adjustments, net | 2,462 | (336) | (2,192) | 864 |
| Impairment of equity and debt securities | — | 305 | — | 426 |
| Foreign exchange (gain) loss | 3,309 | (786) | 3,979 | (1,992) |
| Gain on sale of Joaquin project | — | — | — | (21,138) |
| (Gain) loss on sale of assets and securities | (586) | (513) | (345) | 1,553 |
| Gain on repurchase of Rochester royalty | — | (2,332) | — | (2,332) |
| Loss on debt extinguishment | — | 9,342 | — | 9,342 |
| Mexico inflation adjustment | (1,939) | — | (1,939) | — |
| Interest income on notes receivables | (573) | — | (821) | — |
| Asset retirement obligation accretion | 2,817 | 2,169 | 5,486 | 4,285 |
| Inventory adjustments and write-downs | 817 | 715 | 1,483 | 621 |
| **Adjusted EBITDA** | $48,431 | $31,920 | $97,157 | $86,434 |

### Costs Applicable to Sales and All-in Sustaining Costs

Management uses *Costs applicable to sales (“*CAS”) and *All-in sustaining costs (“*AISC”) to evaluate the Company’s current operating performance and life of mine performance from discovery through reclamation. We believe these measures assist analysts, investors and other stakeholders in understanding the costs associated with producing silver and gold, assessing our operating performance and ability to generate free cash flow from operations and sustaining production. These measures may not be indicative of operating profit or cash flow from operations as determined under GAAP. Management believes converting the benefit from selling gold into silver equivalent ounces best allows management, analysts, investors and other stakeholders to evaluate the operating performance of the Company. Other companies may calculate CAS and AISC differently as a result of reflecting the benefit from selling non-silver metals as a by-product credit rather than converting to silver equivalent ounces, differences in the determination of sustaining capital expenditures, and differences in underlying accounting principles and accounting frameworks such as in International Financial Reporting Standards.

### Three Months Ended June 30, 2018

*In thousands except per ounce amounts*

| Silver Palmarejo Rochester | Total | Gold Kensington | Wharf | Total | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| **Costs applicable to sales, including amortization (U.S. GAAP)** $44,943 $29,244 | $74,187 | $40,668 | $22,611 | $63,279 | $137,466 |
| **Amortization** 14,633 4,793 | 19,426 | 6,441 | 3,353 | 9,794 | 29,220 |
| **Costs applicable to sales** $30,310 $24,451 | $54,761 | $34,227 | $19,258 | $53,485 | $108,246 |
| **Silver equivalent ounces sold** 3,964,208 1,819,072 | 5,783,280 |  |  |  | 8,870,100 |
| **Gold equivalent ounces sold** |  | 28,165 | 23,282 | 51,447 |  |
| **Costs applicable to sales per ounce** $7.65 $13.44 | **$9.47** | $1,215 | $827 | **$1,040** | $12.20 |
| **Costs applicable to sales per average spot ounce** $6.65 $11.94 | **$8.29** |  |  |  | $10.15 |
| **Costs applicable to sales** |  |  |  |  | $108,246 |
| **Treatment and refining costs** |  |  |  |  | 1,046 |
| **Sustaining capital(1)** |  |  |  |  | 28,571 |
| **General and administrative** |  |  |  |  | 7,650 |
| **Exploration** |  |  |  |  | 6,429 |
| **Reclamation** |  |  |  |  | 4,667 |
| **Project/pre-development costs** |  |  |  |  | 517 |
| **All-in sustaining costs** |  |  |  |  | **$157,126** |
| **Silver equivalent ounces sold** |  |  |  |  | 5,783,280 |
| **Kensington and Wharf silver equivalent ounces sold** |  |  |  |  | 3,086,820 |
| **Consolidated silver equivalent ounces sold** |  |  |  |  | 8,870,100 |
| **All-in sustaining costs per silver equivalent ounce** |  |  |  |  | **$17.71** |
| **Consolidated silver equivalent ounces sold (average spot)** |  |  |  |  | 10,667,255 |
| **All-in sustaining costs per average spot silver equivalent ounce** |  |  |  |  | **$14.73** |

(1) Excludes development capital for Jualin and Silvertip.

### Three Months Ended June 30, 2017

*In thousands except per ounce amounts*

| Silver Palmarejo Rochester | Endeavor | Total | Gold Kensington | Wharf | Total | Total |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| **Costs applicable to sales, including amortization (U.S. GAAP)** $48,325 $29,099 | $586 | $78,010 | $36,335 | $18,317 | $54,652 | $132,662 |
| **Amortization** 14,431 4,938 | 168 | 19,537 | 8,347 | 2,549 | 10,896 | 30,433 |
| **Costs applicable to sales** $33,894 $24,161 | $418 | $58,473 | $27,988 | $15,768 | $43,756 | $102,229 |
| **Silver equivalent ounces sold** 2,995,623 1,774,000 | 59,234 | 4,828,857 |  |  |  | 7,860,417 |
| **Gold equivalent ounces sold** |  |  | 29,031 | 21,495 | 50,526 |  |
| **Costs applicable to sales per ounce** $11.31 $13.62 | $7.06 | **$12.11** | $964 | $734 | **$866** | $13.01 |
| **Costs applicable to sales per average spot ounce** $10.20 $12.63 |  | **$11.04** |  |  |  | $11.38 |
| **Costs applicable to sales** |  |  |  |  |  | $102,229 |
| **Treatment and refining costs** |  |  |  |  |  | 1,288 |
| **Sustaining capital(1)** |  |  |  |  |  | 17,173 |
| **General and administrative** |  |  |  |  |  | 7,025 |
| **Exploration** |  |  |  |  |  | 7,813 |
| **Reclamation** |  |  |  |  |  | 3,581 |
| **Project/pre-development costs** |  |  |  |  |  | 1,677 |
| **All-in sustaining costs** |  |  |  |  |  | **$140,786** |
| **Silver equivalent ounces sold** |  |  |  |  |  | 4,828,857 |
| **Kensington and Wharf silver equivalent ounces sold** |  |  |  |  |  | 3,031,560 |
| **Consolidated silver equivalent ounces sold** |  |  |  |  |  | 7,860,417 |
| **All-in sustaining costs per silver equivalent ounce** |  |  |  |  |  | **$17.90** |
| **Consolidated silver equivalent ounces sold (average spot)** |  |  |  |  |  | 8,990,166 |
| **All-in sustaining costs per average spot silver equivalent ounce** |  |  |  |  |  | **$15.66** |

(1) Excludes development capital for Jualin, Guadalupe South Portal and Rochester expansion permitting.

### Six Months Ended June 30, 2018

*In thousands except per ounce amounts*

| Silver Palmarejo Rochester | Total | Gold Kensington | Wharf | Total | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| **Costs applicable to sales, including amortization (U.S. GAAP)** $92,364 $58,380 | $150,744 | $76,015 | $40,577 | $116,592 | $267,336 |
| **Amortization** 30,958 9,624 | 40,582 | 13,158 | 6,010 | 19,168 | 59,750 |
| **Costs applicable to sales** $61,406 $48,756 | $110,162 | $62,857 | $34,567 | $97,424 | $207,586 |
| **Silver equivalent ounces sold** 7,848,191 3,608,079 | 11,456,270 |  |  |  | 17,260,190 |
| **Gold equivalent ounces sold** |  | 55,928 | 40,804 | 96,732 |  |
| **Costs applicable to sales per ounce** $7.82 $13.51 | **$9.62** | $1,124 | $847 | **$1,007** | $12.03 |
| **Costs applicable to sales per average spot ounce** $6.79 $12.03 | **$8.42** |  |  |  | $10.01 |
| **Costs applicable to sales** |  |  |  |  | $207,586 |
| **Treatment and refining costs** |  |  |  |  | 2,241 |
| **Sustaining capital(1)** |  |  |  |  | 51,960 |
| **General and administrative** |  |  |  |  | 16,454 |
| **Exploration** |  |  |  |  | 13,112 |
| **Reclamation** |  |  |  |  | 9,199 |
| **Project/pre-development costs** |  |  |  |  | 1,938 |
| **All-in sustaining costs** |  |  |  |  | **$302,490** |
| **Silver equivalent ounces sold** |  |  |  |  | 11,456,270 |
| **Kensington and Wharf silver equivalent ounces sold** |  |  |  |  | 5,803,920 |
| **Consolidated silver equivalent ounces sold** |  |  |  |  | 17,260,190 |
| **All-in sustaining costs per silver equivalent ounce** |  |  |  |  | **$17.53** |
| **Consolidated silver equivalent ounces sold (average spot)** |  |  |  |  | 20,739,781 |
| **All-in sustaining costs per average spot silver equivalent ounce** |  |  |  |  | **$14.58** |

(1) Excludes development capital for Jualin and Silvertip.

### Six Months Ended June 30, 2017

*In thousands except per ounce amounts*

| Silver Palmarejo Rochester | Endeavor | Total | Gold Kensington | Wharf | Total | Total |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| **Costs applicable to sales, including amortization (U.S. GAAP)** $111,476 $61,354 | $986 | $173,816 | $73,956 | $37,748 | $111,704 | $285,520 |
| **Amortization** 34,581 10,754 | 281 | 45,616 | 17,525 | 5,660 | 23,185 | 68,801 |
| **Costs applicable to sales** $76,895 $50,600 | $705 | $128,200 | $56,431 | $32,088 | $88,519 | $216,719 |
| **Silver equivalent ounces sold** 7,422,969 3,878,209 | 98,999 | 11,400,177 |  |  |  | 17,838,597 |
| **Gold equivalent ounces sold** |  |  | 61,175 | 46,132 | 107,307 |  |
| **Costs applicable to sales per ounce** $10.36 $13.05 | $7.12 | **$11.25** | $922 | $696 | **$825** | $12.15 |
| **Costs applicable to sales per average spot ounce** $9.40 $12.17 |  | **$10.31** |  |  |  | $10.78 |
| **Costs applicable to sales** |  |  |  |  |  | $216,719 |
| **Treatment and refining costs** |  |  |  |  |  | 2,904 |
| **Sustaining capital(1)** |  |  |  |  |  | 28,365 |
| **General and administrative** |  |  |  |  |  | 17,150 |
| **Exploration** |  |  |  |  |  | 13,065 |
| **Reclamation** |  |  |  |  |  | 6,920 |
| **Project/pre-development costs** |  |  |  |  |  | 3,096 |
| **All-in sustaining costs** |  |  |  |  |  | **$288,219** |
| **Silver equivalent ounces sold** |  |  |  |  |  | 11,400,177 |
| **Kensington and Wharf silver equivalent ounces sold** |  |  |  |  |  | 6,438,420 |
| **Consolidated silver equivalent ounces sold** |  |  |  |  |  | 17,838,597 |
| **All-in sustaining costs per silver equivalent ounce** |  |  |  |  |  | **$16.15** |
| **Consolidated silver equivalent ounces sold (average spot)** |  |  |  |  |  | 20,098,954 |
| **All-in sustaining costs per average spot silver equivalent ounce** |  |  |  |  |  | **$14.34** |

(1) Excludes development capital for Jualin, Guadalupe South Portal and Rochester expansion permitting.

### Reconciliation of All-in Sustaining Costs per Silver Equivalent Ounce for Revised 2018 Guidance

*In thousands except per ounce amounts*

| Silver Palmarejo Rochester Silvertip | Total Silver | Gold Kensington | Wharf | Total Gold | Total Combined |
| --- | ---: | ---: | ---: | ---: | ---: |
| **Costs applicable to sales, including amortization (U.S. GAAP)** $200,000 $116,300 $55,600 | $371,900 | $146,100 | $89,700 | $235,800 | $607,700 |
| **Amortization** 65,000 18,900 14,000 | 97,900 | 40,400 | 12,100 | 52,500 | 150,400 |
| **Costs applicable to sales** $135,000 $97,400 $41,600 | $274,000 | $105,700 | $77,600 | $183,300 | $457,300 |
| **Silver equivalent ounces sold** 14,800,000 7,300,000 2,700,000 | 24,800,000 |  |  |  | 37,100,000 |
| **Gold equivalent ounces sold** |  | 117,500 | 87,500 | 205,000 |  |
| **Costs applicable to sales per ounce** **$9.00 - $9.50** **$13.25 - $13.75** **$15.00 - $15.50** |  | **$900 - $950** | **$850 - $900** |  |  |
| **Costs applicable to sales** |  |  |  |  | $457,300 |
| **Treatment and refining costs** |  |  |  |  | 9,000 |
| **Sustaining capital, including capital lease payments** |  |  |  |  | 105,000 |
| **General and administrative** |  |  |  |  | 33,000 |
| **Exploration** |  |  |  |  | 26,000 |
| **Reclamation** |  |  |  |  | 15,700 |
| **Project/pre-development costs** |  |  |  |  | 2,900 |
| **All-in sustaining costs** |  |  |  |  | $648,900 |
| **Silver equivalent ounces sold** |  |  |  |  | 24,800,000 |
| **Kensington and Wharf silver equivalent ounces sold** |  |  |  |  | 12,300,000 |
| **Consolidated silver equivalent ounces sold** |  |  |  |  | 37,100,000 |
| **All-in sustaining costs per silver equivalent ounce** |  |  |  |  | **$17.25 - $17.75** |

### Reconciliation of All-in Sustaining Costs per Silver Equivalent Ounce for Previous 2018 Guidance

*In thousands except per ounce amounts*

| Silver Palmarejo Rochester Silvertip | Total Silver | Gold Kensington | Wharf | Total Gold | Total Combined |
| --- | ---: | ---: | ---: | ---: | ---: |
| **Costs applicable to sales, including amortization (U.S. GAAP)** $208,000 $116,300 $88,000 | $412,300 | $146,100 | $89,700 | $235,800 | $648,100 |
| **Amortization** 63,300 18,900 20,000 | 102,200 | 40,400 | 12,100 | 52,500 | 154,700 |
| **Costs applicable to sales** $144,700 $97,400 $68,000 | $310,100 | $105,700 | $77,600 | $183,300 | $493,400 |
| **Silver equivalent ounces sold** 13,700,000 7,300,000 4,500,000 | 25,500,000 |  |  |  | 37,800,000 |
| **Gold equivalent ounces sold** |  | 117,500 | 87,500 | 205,000 |  |
| **Costs applicable to sales per ounce** **$10.50 - $11.00** **$13.25 - $13.75** **$15.00 - $15.50** |  | **$900 - $950** | **$850 - $900** |  |  |
| **Costs applicable to sales** |  |  |  |  | $493,400 |
| **Treatment and refining costs** |  |  |  |  | 12,000 |
| **Sustaining capital, including capital lease payments** |  |  |  |  | 100,000 |
| **General and administrative** |  |  |  |  | 33,000 |
| **Exploration** |  |  |  |  | 22,000 |
| **Reclamation** |  |  |  |  | 15,700 |
| **Project/pre-development costs** |  |  |  |  | 2,900 |
| **All-in sustaining costs** |  |  |  |  | $679,000 |
| **Silver equivalent ounces sold** |  |  |  |  | 25,500,000 |
| **Kensington and Wharf silver equivalent ounces sold** |  |  |  |  | 12,300,000 |
| **Consolidated silver equivalent ounces sold** |  |  |  |  | 37,800,000 |
| **All-in sustaining costs per silver equivalent ounce** |  |  |  |  | **$17.50 - $18.00** |

54

### Cautionary Statement Concerning Forward-Looking Statements

This report contains numerous forward-looking statements within the meaning of Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”) relating to the Company’s gold, silver, zinc and lead mining business, including statements regarding, estimated production, costs, capital expenditures, contingent payments for the Silvertip acquisition, timing of commercial production at Silvertip, expenses, metals prices, sufficiency of assets, ability to discharge liabilities, liquidity management, financing needs, environmental compliance expenditures, risk management strategies, cost reduction initiatives, capital discipline, and initiatives to maximize net cash flow, enhance revenues, reduce operating and non-operating costs, and manage working capital efficiently. Such forward-looking statements are identified by the use of words such as “believes,” “intends,” “expects,” “hopes,” “may,” “should,” “plan,” “projected,” “contemplates,” “anticipates” or similar words. Actual results could differ materially from those projected in the forward-looking statements. The factors that could cause actual results to differ materially from those projected in the forward-looking statements include (i) the risk factors set forth in the “Risk Factors” section of the 2017 10-K, the Company’s Form 10-Q for the quarterly period ended March 31, 2018 and in this Management’s Discussion and Analysis of Financial Condition and Results of Operations, (ii) the risk that commercial production at Silvertip will be delayed, (iii) the risks and hazards inherent in the mining business (including risks inherent in developing large-scale mining projects, environmental hazards, industrial accidents, weather or geologically related conditions), (iv) changes in the market prices of gold, silver, zinc and lead and a sustained lower price environment, (v) the uncertainties inherent in the Company’s production, exploratory and developmental activities, including risks relating to permitting and regulatory delays, ground conditions and grade variability, (vi) any future labor disputes or work stoppages (involving the Company and its subsidiaries or third parties), (vii) the uncertainties inherent in the estimation of gold, silver, zinc and lead reserves and mineralized material, (viii) changes that could result from the Company’s future acquisition of new mining properties or businesses, (ix) the loss of access to any third-party smelter to whom the Company markets silver and gold, (x) the effects of environmental and other governmental regulations, (xi) the risks inherent in the ownership or operation of or investment in mining properties or businesses in foreign countries, and (xii) the Company’s ability to raise additional financing necessary to conduct its business, make payments or refinance its debt. Readers are cautioned not to put undue reliance on forward-looking statements. The Company disclaims any intent or obligation to update publicly these forward-looking statements, whether as a result of new information, future events or otherwise.

## Market risk

As filed, 5,215 characters.

The Company is exposed to various market risks as a part of its operations and engages in risk management strategies to mitigate these risks. The Company continually evaluates the potential benefits of engaging in these strategies based on current market conditions. The Company does not actively engage in the practice of trading derivative instruments for profit. Additional information about the Company’s derivative financial instruments may be found in Note 11 -- Derivative Financial Instruments in the notes to the condensed consolidated financial statements. This discussion of the Company’s market risk assessments contains “forward looking statements”. For additional information regarding forward-looking statements and risks and uncertainties that could impact the Company, please refer to Item 2 of this Report - Cautionary Statement Concerning Forward-Looking Statements. Actual results and actions could differ materially from those discussed below.

### Gold, Silver, Zinc and Lead Prices

Gold, silver, zinc, and lead prices may fluctuate widely due to numerous factors, such as U.S. dollar strength or weakness, demand, investor sentiment, inflation or deflation, and global mine production. The Company’s profitability and cash flow may be significantly impacted by changes in the market price of gold, silver, zinc, and lead.

### Gold, Silver, Zinc and Lead Hedging

To mitigate the risks associated with gold, silver, zinc and lead price fluctuations, the Company may enter into option contracts to hedge future production. The Company had outstanding Asian put and call option contracts in net-zero-cost collar contracts on zinc at June 30, 2018. The weighted average strike prices on the put and call contracts are $3,000 and $4,050 per metric ton, respectively. The contracts are generally net cash settled and, if the price of zinc at the time of the expiration is between the put and call prices, would expire at no cost to the Company. At June 30, 2018, the fair market value of the put and call zero cost collar contracts was a net asset of $0.4 million. During the six months ended June 30, 2018, the Company recorded unrealized gains of $0.4 million related to outstanding options which were included in *Fair value adjustments, net.*

### Provisional Silver and Gold Sales

The Company enters into sales contracts with third-party smelters and refiners which, in some cases, provide for a provisional payment based upon preliminary assays and quoted metal prices. The provisionally priced sales contracts contain an embedded derivative that is required to be separated from the host contract. Depending on the difference between the price at the time of sale and the final settlement price, embedded derivatives are recorded as either a derivative asset or liability. The embedded derivatives do not qualify for hedge accounting and, as a result, are marked to the market gold and silver price at the end of each period from the provisional sale date to the date of final settlement. The mark-to-market gains and losses are recorded in earnings. Changes in silver and gold prices resulted in provisional pricing mark-to-market losses of $0.3 million and $20 thousand in the three and six months ended June 30, 2018, respectively.

At June 30, 2018, the Company had outstanding provisionally priced sales of 35,787 ounces of gold at an average price of $1,299. A 10% change in realized gold price would cause revenue to vary by $4.6 million.

### Foreign Currency

The Company operates, or has mineral interests, in several foreign countries including Canada, Mexico, and New Zealand, which exposes it to foreign currency exchange rate risks. Foreign currency exchange rates are influenced by world market factors beyond the Company’s control such as supply and demand for U.S. and foreign currencies and related monetary and fiscal policies. Fluctuations in local currency exchange rates in relation to the U.S. dollar may significantly impact profitability and cash flow.

### Foreign Exchange Hedging

To manage foreign currency risk, the Company may enter into foreign exchange forward and/or option contracts when the Company believes such contracts would be beneficial. The Company had no outstanding foreign exchange contracts at June 30, 2018.

### Interest Rates

### Interest Rate Hedging

We may use financial instruments to manage exposures to changes in interest rates on loans, which exposes us to credit risk and market risk. Credit risk is the failure of the counterparty to perform under the terms of the derivative contract. When the fair value of a derivative contract is positive, the counterparty owes us, which creates credit risk for us. When the fair value of a derivative contract is negative, we owe the counterparty and, therefore, it does not pose credit risk. We seek to minimize the credit risk in derivative instruments by entering into transactions with what we believe are high-quality counterparties. Market risk is the adverse effect on the value of a financial instrument that results from a change in interest rates. The Company had an outstanding interest rate swap whereby the Company receives a variable rate in exchange for a floating rate at June 30, 2018.

## Controls and procedures

As filed, 2,011 characters.

(a) ***Disclosure Controls and Procedures***

As of the end of the period covered by this quarterly report, the Company carried out an evaluation, under the supervision and with the participation of the Company’s management, including its Chief Executive Officer and Chief Financial Officer, of the effectiveness of the design and operation of the Company’s disclosure controls and procedures (as such term is defined in Rules 13a-15(e) and 15d-15(e) of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), and management necessarily applied its judgment in assessing the costs and benefits of such controls and procedures, which by their nature, can provide only reasonable assurance regarding management’s control objectives. The design of any system of controls is based in part upon certain assumptions about the likelihood of future events. Based upon the foregoing, the Company’s Chief Executive Officer and Chief Financial Officer concluded that the Company’s disclosure controls and procedures were effective and operating to provide reasonable assurance that information required to be disclosed by it in the reports it files or submits under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms, and to provide reasonable assurance that such information is accumulated and communicated to the Company’s management, including its Chief Executive Officer and Chief Financial Officer, as appropriate to allow timely decisions regarding required disclosure.

(b) ***Management’s Report on Internal Control Over Financial Reporting***

Based on an evaluation by the Company’s Chief Executive Officer and Chief Financial Officer, such officers concluded

that there was no change in the Company’s internal control over financial reporting during the three months ended June 30, 2018 that has materially affected, or is reasonably likely to materially affect, the Company’s internal control over financial reporting.

## Risk factors

As filed, 440 characters.

Item 1A -- Risk Factors of the 2017 10-K and the Company’s Quarterly Report on Form 10-Q filed on April 25, 2018 set forth information relating to important risks and uncertainties that could materially adversely affect the Company’s business, financial condition or operating results. Additional risks and uncertainties that the Company does not presently know or that it currently deems immaterial also may impair our business operations.

Filed Jul 25, 2018.
Source: SEC EDGAR, the filing index for accession 0000215466-18-000118. Last ingested by Listed: Nov 14, 2026, 12:15 ET. No prices; not investment advice.