# Public Service Enterprise Group Inc: Form 10-Q for the period ended Sep 30, 2016

- Company: [Public Service Enterprise Group Inc](/companies/peg.md) (CIK 788784)
- Form: 10-Q
- Filed: 2016-10-31
- Accepted by EDGAR: Oct 31, 2016, 17:28 ET
- Period: 2016-09-30
- Accession: 0000788784-16-000038
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/788784/000078878416000038/pseg-9302016xq3.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/788784/000078878416000038/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2016-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2016-07-01 to 2016-09-30 | $2.45bn | us-gaap:Revenues |
| Revenue | 9 months, 2016-01-01 to 2016-09-30 | $6.97bn | us-gaap:Revenues |
| Operating income | 3 months, 2016-07-01 to 2016-09-30 | $577.0m | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2016-01-01 to 2016-09-30 | $1.75bn | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2016-07-01 to 2016-09-30 | $99.0m | us-gaap:InterestExpense |
| Interest expense | 9 months, 2016-01-01 to 2016-09-30 | $288.0m | us-gaap:InterestExpense |
| Income tax | 3 months, 2016-07-01 to 2016-09-30 | $188.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2016-01-01 to 2016-09-30 | $562.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2016-07-01 to 2016-09-30 | $327.0m | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2016-01-01 to 2016-09-30 | $985.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2016-07-01 to 2016-09-30 | $0.64 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2016-01-01 to 2016-09-30 | $1.94 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2016-07-01 to 2016-09-30 | $0.65 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2016-01-01 to 2016-09-30 | $1.95 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2016-07-01 to 2016-09-30 | 508,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2016-01-01 to 2016-09-30 | 508,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2016-01-01 to 2016-09-30 | $2.76bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2016-01-01 to 2016-09-30 | $2.98bn | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 3 months, 2016-07-01 to 2016-09-30 | $207.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Dividends paid | 9 months, 2016-01-01 to 2016-09-30 | $622.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2016-09-30 | $450.0m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2016-09-30 | $3.21bn | us-gaap:AssetsCurrent |
| Total assets | at 2016-09-30 | $39.49bn | us-gaap:Assets |
| Current liabilities | at 2016-09-30 | $2.80bn | us-gaap:LiabilitiesCurrent |
| Long-term debt | at 2016-09-30 | $10.70bn | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2016-09-30 | $0 | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | at 2016-09-30 | $255.0m | us-gaap:CommercialPaper |
| Shareholders' equity | at 2016-09-30 | $13.48bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 65,431 characters.

This combined MD&A is separately filed by Public Service Enterprise Group Incorporated (PSEG), Public Service Electric and Gas Company (PSE&G) and PSEG Power LLC (Power). Information contained herein relating to any individual company is filed by such company on its own behalf. PSE&G and Power each make representations only as to itself and make no representations whatsoever as to any other company.

PSEG’s business consists of two reportable segments, our principal direct wholly owned subsidiaries, which are:

- **PSE&G,** our public utility company which is engaged principally in the transmission of electricity and distribution of electricity and natural gas in certain areas of New Jersey. PSE&G is subject to regulation by the New Jersey Board of Public Utilities (BPU) and the Federal Energy Regulatory Commission (FERC). PSE&G also invests in solar generation projects and has implemented energy efficiency and demand response programs in New Jersey, which are regulated by the BPU, and
- **Power,** our multi-regional, wholesale energy supply company that integrates its generating asset operations and gas supply commitments with its wholesale energy, fuel supply and energy transacting functions primarily in the Northeast and Mid-Atlantic United States through its principal direct wholly owned subsidiaries. Power’s subsidiaries are subject to regulation by FERC, the Nuclear Regulatory Commission (NRC), the Environmental Protection Agency (EPA), and the states in which they operate.

PSEG’s other direct wholly owned subsidiaries are: PSEG Energy Holdings L.L.C. (Energy Holdings), which earns its revenues primarily from its portfolio of lease investments; PSEG Long Island LLC (PSEG LI), which operates the Long Island Power Authority’s (LIPA) transmission and distribution (T&D) system under a contractual agreement; and PSEG Services Corporation (Services), which provides us and these operating subsidiaries with certain management, administrative and general services at cost.

Our business discussion in Part I, Item 1. Business of our 2015 Annual Report on 10-K (Form 10-K) provides a review of the regions and markets where we operate and compete, as well as our strategy for conducting our businesses within these markets, focusing on operational excellence, financial strength and making disciplined investments. Our risk factor discussion in Part I, Item 1A. Risk Factors of Form 10-K provides information about factors that could have a material adverse impact on our businesses. The following supplements that discussion and the discussion included in the Executive Overview of 2015 and Future Outlook provided in Item 7 in our Form 10-K by describing significant events and business developments that have occurred during 2016 and changes to the key factors that we expect may drive our future performance. The following discussion refers to the Condensed Consolidated Financial Statements (Statements) and the Related Notes to Condensed Consolidated Financial Statements (Notes). This discussion should be read in conjunction with such Statements, Notes and the 2015 Form 10-K.

### EXECUTIVE OVERVIEW OF 2016 AND FUTURE OUTLOOK

Our business plan is designed to achieve growth while managing the risks associated with fluctuating commodity prices and changes in customer demand. We continue our focus on operational excellence, financial strength and disciplined investment. These guiding principles have provided the base from which we have been able to execute our strategic initiatives, including:

- improving utility operations through growth in investment in T&D and other infrastructure projects designed to enhance resiliency, and
- maintaining and expanding a reliable generation fleet with the flexibility to utilize a diverse mix of fuels which allows us to respond to market volatility and capitalize on opportunities as they arise.

### Financial Results

The results for PSEG, PSE&G and Power for the three months and nine months ended September 30, 2016 and 2015 are presented as follows:

| Earnings | Three Months Ended September 30, 2016 Millions | 2015 | Nine Months Ended September 30, 2016 | 2015 |
| --- | ---: | ---: | ---: | ---: |
| PSE&G | $255 | $222 | $696 | $631 |
| Power (A) (B) | 139 | 206 | 320 | 707 |
| Other (C) | (67) | 11 | (31) | 32 |
| **PSEG Net Income** | **$327** | **$439** | **$985** | **$1,370** |
| **PSEG Net Income Per Share (Diluted)** | **$0.64** | **$0.87** | **$1.94** | **$2.70** |

(A) Includes after-tax expenses of $67 million related to the early retirement of Power’s Hudson and Mercer coal/gas generation plants in the three months and nine months ended September 30, 2016. See Item 1. Note 3. Early Plant Retirements for additional information.

(B) Includes an after-tax insurance recovery for Superstorm Sandy of $102 million in the nine months ended September 30, 2015.

(C) Other includes activities at the parent company, PSEG LI, and Energy Holdings as well as intercompany eliminations. Energy Holdings recorded an after-tax impairment of $86 million related to its investments in NRG REMA, LLC’s leveraged leases in the three months and nine months ended September 30, 2016. See Item 1. Note 6. Financing Receivables for further information.

Power’s results above include the realized gains, losses and earnings on the Nuclear Decommissioning Trust (NDT) Fund and other related NDT activity and the impacts of non-trading mark-to-market (MTM) activity, which consist of the financial impact from positions with future delivery dates.

The variances in our Net Income include the changes related to NDT and MTM shown in the following table:

|  | Three Months Ended September 30, 2016 Millions, after tax | 2015 | Nine Months Ended September 30, 2016 | 2015 |
| --- | ---: | ---: | ---: | ---: |
| NDT Fund Income (Expense) (A) (B) | $2 | $(14) | $(4) | $(11) |
| Non-Trading MTM Gains (Losses) (C) | $34 | $50 | $(54) | $58 |

(A) NDT Fund Income (Expense) includes the realized gains and losses, interest and dividend income and other costs related to the NDT Fund which are recorded in Other Income and Deductions, and impairments on certain NDT securities recorded as Other-Than-Temporary Impairments. Interest accretion expense on Power’s nuclear Asset Retirement Obligation (ARO) is recorded in Operation and Maintenance (O&M) Expense and the depreciation related to the ARO asset is recorded in Depreciation and Amortization Expense.

(B) Net of tax (expense) benefit of $(2) million, $10 million, $0 million and $3 million for the three and nine months ended September 30, 2016 and 2015, respectively.

(C) Net of tax (expense) benefit of $(24) million, $(34) million, $37 million and $(40) million for the three and nine months ended September 30, 2016 and 2015, respectively.

Our $112 million decrease in Net Income for the three months ended September 30, 2016 was driven primarily by

- an impairment related to investments in certain leveraged leases at Energy Holdings (See Item 1. Note 6. Financing Receivables),
- charges related to the early retirement of two coal/gas generation units at Power (See Item 1. Note 3. Early Plant Retirements), and
- lower volumes of energy sold at lower average realized prices and lower capacity revenues, primarily in the PJM Interconnection, L.L.C. (PJM) region.

These decreases were partially offset by

- higher revenues due to increased investments in transmission projects,
- higher electricity sales under non-BGS wholesale load contracts in PJM and New England (NE) and higher volumes of electricity sold at higher prices under our Basic Generation Service (BGS) contracts, and
- lower other-than-temporary impairments of the NDT Fund.

Our $385 million decrease in Net Income for the nine months ended September 30, 2016 was driven primarily by

- the aforementioned charges in the 2016 third quarter for the early retirement of the two coal/gas generation units at Power,
- MTM losses in 2016 as compared to MTM gains in 2015,
- lower volumes of energy sold at lower average realized sales prices,
- lower capacity and operating reserve revenues in PJM,
- higher 2016 congestion costs in PJM as a result of credits received in 2015 due to extremely colder weather,
- lower volumes of gas sold at lower average prices under the Basic Gas Supply Service (BGSS) contract,
- insurance recoveries received primarily by Power in 2015 related to Superstorm Sandy, and
- the aforementioned third quarter 2016 impairment on leveraged leases at Energy Holdings.

These decreases were partially offset by

- lower generation costs driven by lower fuel costs, particularly for natural gas, and reduced generation output at Power,
- higher costs incurred at Power for planned outages in 2015, and
- higher revenues due to increased investments in transmission projects.

During the first nine months of 2016, we maintained a strong balance sheet. We continued to effectively deploy capital without the need for additional equity, while our solid credit ratings aided our ability to access capital and credit markets. The greater emphasis on capital spending for projects on which we receive contemporaneous returns at PSE&G, our regulated utility, in recent years has yielded strong results and allowed us to increase our dividend. These actions to transition our business to meet market conditions and investor expectations reflect our multi-year, long-term approach to managing our company. Our focus has been to invest capital in T&D and other infrastructure projects aimed at maintaining service reliability to our customers and bolstering our system resiliency. At Power, our merchant generator, we strive to improve performance and reduce costs in order to enhance the value of our generation fleet in light of low gas prices, environmental considerations and competitive market forces that reward efficiency and reliability.

At PSE&G, in 2016 we continue to make investments to improve the resiliency of our gas and electric distribution system as part of our Energy Strong program that was approved by the BPU in 2014 and to seek recovery on such investments. We also commenced modernizing PSE&G’s gas distribution systems as part of our Gas System Modernization Program (GSMP) that was approved by the BPU in late 2015. Over the past few years, these types of investments have altered our business mix to reflect a higher percentage of earnings contribution by PSE&G. In 2017, as a result of our Energy Strong Order from the BPU, we will be required to file a Distribution rate case proceeding. We cannot predict the impact such proceeding will have on our distribution business.

Despite the unseasonable warm winter weather patterns in 2016, Power’s results benefited from access to natural gas supplies through existing firm pipeline transportation contracts. Power manages these contracts for the benefit of PSE&G’s customers through the BGSS arrangement. The contracts are sized to provide for delivery of a reliable gas supply to PSE&G customers on peak winter days. When pipeline capacity beyond the customers’ needs is available, Power can use it to make third party sales and supply gas to its generating units in New Jersey. Alternatively, gas supply and pipeline capacity constraints could adversely impact our ability to meet the needs of our utility customers and generating units. Power’s strategic hedging practices and ability to capitalize on market opportunities help it to balance some of the volatility of the merchant power business.

Our recent investments in the latter half of 2015 and early 2016 in Keys Energy Center (Keys), Sewaren 7 and Bridgeport Harbor Station 5 (BH5) reflect our recognition of the value of opportunistic growth in the Power business. These additions to our fleet both expand our geographic diversity and adjust our fuel mix and are expected to contribute to the overall efficiency of operations.

Since 2013, eight nuclear generating stations in the United States have closed or announced early retirement due to economic reasons, and four additional stations have been announced as being at risk for early retirement. This situation is generally due to low natural gas prices resulting from the growth of shale gas production since 2007, the continuing cost of regulatory compliance for nuclear facilities and both federal and state-level policies that provide credits to renewable energy such as wind and solar, but do not apply to nuclear generating stations. These trends have significantly reduced the revenues to nuclear generating stations while simultaneously raising the unit cost of production. This may result in the electric generation industry experiencing a shift from nuclear generation to natural gas-fired generation, creating greater reliance on natural gas pipelines for delivery and less diversity of the generation fleet.

If trends noted above continue or worsen, our nuclear generating units could cease being economically competitive which may cause us to retire such units prior to the end of their useful lives. The costs associated with any such retirement, which may include, among other things, accelerated depreciation and amortization or impairment charges, accelerated asset retirement costs, severance costs and environmental remediation costs, could be material. We continue to advocate for sound policies that recognize nuclear power as a source of clean energy and an important part of a diverse and reliable energy portfolio.

### Regulatory, Legislative and Other Developments

In our pursuit of operational excellence, financial strength and disciplined investment, we closely monitor and engage with stakeholders on significant regulatory and legislative developments. Transmission planning rules and wholesale power market design are of particular importance to our results and we continue to advocate for policies and rules that promote fair and efficient electricity markets.

### Transmission

In April 2013, PJM initiated its first “open window” solicitation process to allow both incumbents and non-incumbents the opportunity to submit transmission project proposals to address identified high voltage issues in New Jersey. In February 2016, FERC issued an order granting PSE&G’s request that it be permitted to seek recovery of 100% of its portion of prudently incurred Artificial Island project costs if the project is cancelled for reasons beyond PSE&G’s control. In April 2016, PSE&G accepted construction responsibility for three components of the Artificial Island project that PJM assigned to us. On August 5, 2016, PJM announced that it has suspended the Artificial Island transmission project and is performing a comprehensive analysis to determine a future course of action, which is expected to be completed by February 2017. We may also from time to time have opportunities to submit transmission project proposals in regions where we are not the incumbent. However, there can be no assurance that any such proposals would be successful.

In April 2016, PJM filed at FERC to incorporate a voltage threshold into PJM’s Regional Transmission Expansion Plan (RTEP) process to exempt, except under certain circumstances, reliability violations on facilities below 200 kV from PJM’s proposal window process. We generally support this reform as a measure to improve the efficiency of the open window procedure that will permit transmission developers to focus on the projects most likely to benefit from a competitive process.

There are several matters pending before FERC that concern the allocation of costs associated with transmission projects being constructed by PSE&G. Regardless of how these proceedings are resolved, PSE&G’s ability to recover the costs of these projects will not be affected. However, the result of these proceedings could ultimately impact the amount of costs borne by ratepayers in New Jersey and may cause increased scrutiny regarding PSE&G’s future capital investments. In addition, as a basic generation service (BGS) supplier, Power provides services that include specified transmission costs. If the allocation of the costs associated with the transmission projects were to increase these BGS-related transmission costs, BGS suppliers may be entitled to an adjustment, subject to BPU approval. We do not believe that these matters will have a material effect on Power’s business or results of operations.

Several complaints have been filed and several remain pending at FERC against transmission owners around the country, challenging those transmission owners’ base return on equity (ROE). Certain of those complaints have resulted in decisions and others have been settled, resulting in reductions of those transmission owners’ base ROEs. While we are not the subject of a challenge to the ROE employed in PSE&G’s transmission formula rate, the results of these other proceedings could set precedents for other transmission owners with formula rates in place, including PSE&G.

### Wholesale Power Market Design

Capacity market design, including the Reliability Pricing Model (RPM) in PJM, remains an important focus for us. In June 2015, FERC conditionally accepted a proposal from PJM for a capacity performance product to include generators, Demand Response and energy efficiency providers, which will be required to perform during emergency conditions, as a supplement to the base capacity product. The proposal included enhanced performance-based incentives and penalties. We believe that the auction pricing adequately reflects the increased costs that could result from operating under more stringent rules for generation availability. Based on the auction results, the capacity performance mechanism appears to have provided the opportunity for enhanced capacity market revenue streams for Power, but future impacts cannot be assured. Further, there may be requirements for additional investment and there are additional performance and financial risks. Appeals of FERC’s capacity performance orders are pending.

In May 2016, PJM announced the results of the RPM capacity auction for the 2019-2020 delivery year. Power cleared 8,895 MW of its generating capacity at an average price of $116 per MW-day for the 2019-2020 delivery period. Of the cleared capacity, Power believes that nearly all is compliant with PJM’s capacity performance requirements. In the two prior capacity auctions covering the 2017-2018 and 2018-2019 delivery years, Power cleared approximately 8,700 MW at average prices of $177 per MW-day and $215 per MW-day, respectively. Prices in the most recent auction reflect PJM’s downwardly-revised demand forecast, changes in the emergency transfer limits due to transmission expansion and the effects of both the new generation and uncleared generation from the prior year’s auction.

As a result of the efforts of certain entities in PJM to obtain financial support arrangements from their state commission, a group of suppliers requested that FERC direct PJM to expand the currently effective “minimum offer price rule” to apply to certain existing units seeking subsidies. The suppliers’ request was intended to avoid a scenario where the subsidized generators would submit bids into the PJM capacity market that did not reflect their actual costs of operation and could artificially suppress capacity market prices. We are currently awaiting FERC action on the suppliers’ request and cannot predict the outcome of the proceeding. See Part II, Item 5. Other Information—Federal Regulation—Capacity Market Issues—PJM for additional information.

### Environmental Regulation

We continue to advocate for the development and implementation of fair and reasonable rules by the EPA and state environmental regulators. In particular, section 316(b) of the Federal Water Pollution Control Act (FWPCA) requires that cooling water intake structures, which are a significant part of the generation of electricity at steam-electric generating stations, reflect the best technology available for minimizing adverse environmental impacts. Implementation of Section 316(b) and related state regulations could adversely impact future nuclear and fossil operations and costs. See Item 1. Note 9. Commitments and Contingent Liabilities for further information.

In October 2015, the EPA published the Clean Power Plan (CPP), a greenhouse gas emissions regulation under the Clean Air Act (CAA) for existing power plants. The regulation establishes state-specific emission targets based on implementation of the best systems of emission reduction. We continue to work with FERC and other federal and state regulators, as well as industry partners, to determine the potential impact of these regulations.

The U.S. Supreme Court’s February 2016 decision to stay the implementation of the CPP will delay deadlines for submission of state requests for extensions and final plans. If the CPP is upheld, new deadlines will need to be established and the effective date of the compliance period may be impacted.

We are subject to liability under environmental laws for the costs of remediating environmental contamination of property now or formerly owned by us and of property contaminated by hazardous substances that we generated. In particular, the historic operations of PSEG companies and the operations of numerous other companies along the Passaic and Hackensack Rivers are alleged by Federal and State agencies to have discharged substantial contamination into the Passaic River/Newark Bay Complex in violation of various statutes. We are also currently involved in a number of proceedings relating to sites where other hazardous substances may have been discharged and may be subject to additional proceedings in the future, and the costs of any such remediation efforts could be material.

For further information regarding the matters described above as well as other matters that may impact our financial condition and results of operations, see Item 1. Note 9. Commitments and Contingent Liabilities.

### FERC Compliance

Since September 2014, FERC Staff has been conducting a preliminary non-public investigation regarding errors in the calculation of certain components of Power’s cost-based bids for its New Jersey fossil generating units in the PJM energy market and the quantity of energy that Power offered into the energy market for its fossil peaking units compared to the amounts for which Power was compensated in the capacity market for those units. This investigation is ongoing. The amounts of potential disgorgement and other potential penalties that we may incur span a wide range depending on the success of our legal arguments. If our legal arguments do not prevail, in whole or in part with FERC or in a judicial challenge that we may choose to pursue, it is likely that Power would record losses that would be material to PSEG’s and Power’s results of operations in the quarterly and annual periods in which they are recorded. For additional information, see Item 1. Note 9. Commitments and Contingent Liabilities.

### Early Retirement of Hudson and Mercer Units

In October 2016, Power determined it will cease generation operations of the existing coal/gas units at the Hudson and Mercer generating stations on June 1, 2017. The exact timing of the early retirement of these units will be reviewed for reliability impacts by PJM, and may be impacted by operational and other conditions that could subsequently arise. The decision to retire the Hudson and Mercer units will have a material effect on PSEG’s and Power’s results of operations. In the third quarter of 2016, PSEG and Power recognized one-time pre-tax charges in Energy Costs, Operation and Maintenance and Depreciation and Amortization of $62 million, $48 million and $4 million, respectively, related to coal inventory adjustments, capacity penalties, materials and supplies inventory reserve adjustments for parts that cannot be used at other generating units, employee-related severance benefits costs, construction work in progress impairments, and asset retirement obligation (ARO) adjustments, among other shut down items. In addition to these one-time charges, Power will recognize incremental Depreciation and Amortization during the remainder of 2016 of $568 million and $946 million into 2017 due to the significant shortening of the expected economic useful lives of Hudson and Mercer. Additional employee-related salary continuance and severance costs and various miscellaneous costs may also be incurred during the period prior to retirement. Finally, Power currently anticipates using the sites for alternative industrial activity. However, if Power determines not to use the sites for alternative industrial activity, the early retirement of the units at such sites would trigger investigation and possible remediation of identified environmental contamination. The amounts for any such environmental investigation or remediation are not currently probable or estimable but may be material. For additional information, including our estimated costs through 2017, see Item 1. Note 3. Early Plant Retirements.

The primary factors considered during our annual five-year strategic planning process that contributed to the decision to retire these units early include significant declines in revenues and margin caused by a sustained period of depressed wholesale power prices and reduced capacity factors caused by lower natural gas prices making coal generation less economically competitive than natural gas-fired generation. Despite experiencing recent warmer than normal weather in PJM this summer, Power did not experience the usual increase in electricity prices in PJM as it had in past hot summers. This trend has a further adverse economic impact to these units because they generally dispatch and earn energy margin on peak hot and cold days. In addition, the upcoming PJM capacity auction in May 2017 will be the first to require all generating units to meet the increased operating performance standards of PJM’s new capacity performance construct. Power determined that the costs to upgrade the existing units at the Hudson and Mercer stations to be able to comply with these higher reliability standards are too significant and not economic given current market conditions.

In addition, PSEG and Power continue to monitor their other coal assets, including the Keystone, Conemaugh and Bridgeport Harbor generating stations, to ensure their economic viability through the end of their designated useful lives. The precise timing of a change in useful lives may be dependent upon events out of PSEG’s and Power’s control and may impact our ability to operate or maintain certain assets in the future. These generating stations may be impacted by factors such as environmental legislation, co-owner capital requirements and continued depressed wholesale power prices or capacity factors, among other things. Any early retirement of our other coal units before the end of their current estimated useful lives may have a material adverse impact on PSEG’s and Power’s future financial results.

### Leveraged Lease Impairments

During the third quarter of 2016, Energy Holdings completed its annual review of estimated residual values embedded in the NRG REMA, LLC (REMA) leveraged leases. The outcome indicated that the revised residual value estimates were lower than the recorded residual values and the decline was deemed to be other than temporary due to the adverse economic conditions experienced by coal generation in PJM, as discussed in Note 3. Early Plant Retirements, negatively impacting the economic outlook of the leased assets. As a result, a pre-tax write-down of $137 million was reflected in Operating Revenues in the quarter ended September 30, 2016, calculated by comparing the gross investment in the leases before and after the revised residual estimates. There can be no assurance that a continuation or worsening of the adverse economic conditions would not lead to additional write-downs at any of our other generation units in our leveraged lease portfolio, and such write-downs could be material.

Additional facilities in our leveraged lease portfolio include the Joliet facility, which has converted to natural gas. The coal-fired units at the Shawville generating facility are expected to return to service in the fall of 2016 with the ability to use natural gas. However, these units may have higher operating costs and fuel consumption as well as longer start-up times compared to newer combined cycle gas units. As a result, these facilities may not be as economically competitive as newer combined cycle gas units and could continue to be adversely impacted by the same economic conditions experienced by coal generation facilities, which could require Energy Holdings to write down the residual value of the leveraged leases associated with these facilities.

REMA’s parent company, GenOn Energy, Inc. (GenOn), reported in August 2016 that it did not expect to have sufficient liquidity to repay their senior unsecured notes due in June 2017. Although all lease payments are current, PSEG cannot predict the outcome of GenOn’s efforts to restructure its portfolio and improve its liquidity and the possible related impact on REMA. PSEG continues to monitor any changes to REMA’s and GenOn’s status and potential impacts on Energy Holdings’ lease investments, which could include further write-downs of the values of Energy Holdings’ leveraged leases.

### Salem Operations

The previously announced bolt replacement at Salem Unit 1 was completed and the unit returned to service on July 30, 2016. We expect to continue to inspect and replace degraded bolts at both Salem units over the next several refueling outage cycles. We are participating with the Electric Power Research Institute, the Nuclear Energy Institute and other operators of similarly-designed pressurized water reactors in developing a strategy to maintain the long-term health of the reactor vessel internals.

Extension of the Salem Unit 1 outage into July and an unplanned outage at Salem Unit 2 due to transformer issues reduced output from the Salem units in the third quarter, which was partially offset by increased production at our Hope Creek and Peach Bottom units. As a result, our nuclear capacity factor for the nine months ended September 30, 2016 was 88%.

### Operational Excellence

We emphasize operational performance while developing opportunities in both our competitive and regulated businesses. Flexibility in our generating fleet has allowed us to take advantage of opportunities in a rapidly evolving market as we remain diligent in managing costs. For the first nine months of 2016, our

- diverse fuel mix and dispatch flexibility allowed us to generate approximately 40 terra-watt hours while addressing fuel availability and price volatility and compensating for the extended outages at our Salem units, and
- combined cycle fleet produced 13 terawatt hours at an average capacity factor of 63%.

### Financial Strength

Our financial strength is predicated on a solid balance sheet, positive operating cash flow and reasonable risk-adjusted returns on increased investment. Our financial position remained strong during the first nine months of 2016 as we

- had cash on hand of $450 million as of September 30, 2016,
- maintained solid investment grade credit ratings, and
- increased our indicative annual dividend for 2016 to $1.64 per share.

We expect to be able to fund our planned capital requirements, as described in Liquidity and Capital Resources, without the issuance of new equity.

### Disciplined Investment

We utilize rigorous investment criteria when deploying capital and seek to invest in areas that complement our existing business and provide reasonable risk-adjusted returns. These areas include upgrading our energy infrastructure, responding to trends in environmental protection and providing new energy supplies in domestic markets with growing demand. In the first nine months of 2016, we

- made additional investments in transmission infrastructure projects,
- began executing our GSMP and continued executing Energy Strong and other existing BPU-approved utility programs,
- commenced construction of our Keys and Sewaren 7 generation projects for targeted commercial operation in 2018 and announced our plan to construct BH5 and commence operations in mid-2019, and
- acquired three solar energy projects totaling 100 MW-direct current. Two of these projects are already in service in North Carolina and Colorado. The third project is in Colorado and expected to be in service by year end.

### Future Outlook

Our future success will depend on our ability to continue to maintain strong operational and financial performance in a slow-growing economy and a cost-constrained environment with low gas prices, to capitalize on or otherwise address appropriately regulatory and legislative developments that impact our business and to respond to the issues and challenges described below. In order to do this, we must continue to:

- focus on controlling costs while maintaining safety and reliability and complying with applicable standards and requirements,
- successfully manage our energy obligations and re-contract our open supply positions in response to changes in demand,
- execute our utility capital investment program, including our Energy Strong program, GSMP and other investments for growth that yield contemporaneous and reasonable risk-adjusted returns, while enhancing the resiliency of our infrastructure and maintaining the reliability of the service we provide to our customers,
- effectively manage construction of our Keys, Sewaren 7, BH5 and other generation projects,
- advocate for measures to ensure the implementation by PJM and FERC of market design and transmission planning rules that continue to promote fair and efficient electricity markets,
- engage multiple stakeholders, including regulators, government officials, customers and investors, and
- successfully operate the LIPA T&D system and manage LIPA’s fuel supply and generation dispatch obligations.

For 2016 and beyond, the key issues and challenges we expect our business to confront include:

- regulatory and political uncertainty, both with regard to future energy policy, design of energy and capacity markets, transmission policy and environmental regulation, as well as with respect to the outcome of any legal, regulatory or other proceeding, settlement, investigation or claim, applicable to us and/or the energy industry,
- fair and timely rate relief from the BPU and FERC for recovery of costs and return on investments, including with respect to our base rate case which must be filed with the BPU no later than November 1, 2017,
- uncertainty in the slowly improving national and regional economic recovery, continuing customer conservation efforts, changes in energy usage patterns and evolving technologies, which impact customer behaviors and demand,
- the potential for continued reductions in demand and sustained lower natural gas and electricity prices, both at market hubs and the locations where we operate,
- the impact of lower natural gas prices and increasing environmental compliance costs on the competitiveness of our nuclear and remaining coal-fired generation plants, and the potential for retirement of such plants earlier than their current useful lives,
- delays and other obstacles that might arise in connection with the construction of our T&D, generation and other development projects, including in connection with permitting and regulatory approvals,
- maintaining a diverse mix of fuels to mitigate risks associated with fuel price volatility and market demand cycles, and
- FERC Staff’s continuing investigation of certain of Power’s New Jersey fossil generating unit bids in the PJM energy market.

Our primary investment opportunities are in two areas: our regulated utility business and our merchant power business. We continually assess a broad range of strategic options to maximize long-term stockholder value. In assessing our options, we consider a wide variety of factors, including the performance and prospects of our businesses; the views of investors, regulators and rating agencies; our existing indebtedness and restrictions it imposes; and tax considerations, among other things. Strategic options available to us include:

- the acquisition, construction or disposition of transmission and distribution facilities and/or generation units,
- the disposition or reorganization of our merchant generation business or other existing businesses or the acquisition or development of new businesses,
- the expansion of our geographic footprint,
- continued or expanded participation in solar, demand response and energy efficiency programs, and
- investments in capital improvements and additions, including the installation of environmental upgrades and retrofits, improvements to system resiliency, modernizing existing infrastructure and participation in transmission projects through FERC’s “open window” solicitation process.

We continue to actively explore opportunities in the retail energy marketing business, which we believe would complement our existing wholesale marketing business. Our entry into the retail energy marketing business is subject to market conditions and regulatory approval, among other things.

There can be no assurance, however, that we will successfully develop and execute any of the strategic options noted above, or any additional options we may consider in the future. The execution of any such strategic plan may not have the expected benefits or may have unexpected adverse consequences.

### RESULTS OF OPERATIONS

### PSEG

Our results of operations are primarily comprised of the results of operations of our principal operating subsidiaries, PSE&G and Power, excluding charges related to intercompany transactions, which are eliminated in consolidation. For additional information on intercompany transactions, see Item 1. Note 18. Related-Party Transactions.

|  | Three Months Ended September 30, 2016 Millions | 2015 | Increase/ (Decrease) September 30, 2016 vs. 2015 Millions% |  | Nine Months Ended 2016 Millions | 2015 | Increase/ (Decrease) 2016 vs. 2015 Millions% |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| Operating Revenues | $2,450 | $2,688 | $(238) | (9) | $6,971 | $8,137 | $(1,166) | (14) |
| Energy Costs | 866 | 815 | 51 | 6 | 2,326 | 2,577 | (251) | (10) |
| Operation and Maintenance | 776 | 746 | 30 | 4 | 2,215 | 2,170 | 45 | 2 |
| Depreciation and Amortization | 231 | 313 | (82) | (26) | 679 | 960 | (281) | (29) |
| Income from Equity Method Investments | 3 | 3 | — | — | 9 | 10 | (1) | (10) |
| Other Income (Deductions) | 39 | 33 | 6 | 18 | 100 | 135 | (35) | (26) |
| Other-Than-Temporary Impairments | 5 | 30 | (25) | (83) | 25 | 45 | (20) | (44) |
| Interest Expense | 99 | 96 | 3 | 3 | 288 | 291 | (3) | (1) |
| Income Tax Expense | 188 | 285 | (97) | (34) | 562 | 869 | (307) | (35) |

The following discussions for PSE&G and Power provide a detailed explanation of their respective variances.

### PSE&G

|  | Three Months Ended September 30, 2016 Millions | 2015 | Increase/ (Decrease) September 30, 2016 vs. 2015 Millions% |  | Nine Months Ended 2016 Millions | 2015 | Increase/ (Decrease) 2016 vs. 2015 Millions% |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| Operating Revenues | $1,684 | $1,766 | $(82) | (5) | $4,746 | $5,234 | $(488) | (9) |
| Energy Costs | 721 | 740 | (19) | (3) | 1,979 | 2,176 | (197) | (9) |
| Operation and Maintenance | 376 | 391 | (15) | (4) | 1,110 | 1,171 | (61) | (5) |
| Depreciation and Amortization | 137 | 231 | (94) | (41) | 412 | 712 | (300) | (42) |
| Other Income (Deductions) | 21 | 22 | (1) | (5) | 58 | 57 | 1 | 2 |
| Interest Expense | 72 | 67 | 5 | 7 | 214 | 203 | 11 | 5 |
| Income Tax Expense | 144 | 137 | 7 | 5 | 393 | 398 | (5) | (1) |

### Three Months Ended September 30, 2016 as Compared to 2015

**Operating Revenues** decreased $82 million due to changes in delivery, commodity, clause and other operating revenues.

***Delivery Revenues*** increased $57 million due primarily to an increase in transmission revenues.

- Transmission revenues were $50 million higher due to increased capital investments.
- Electric distribution revenues increased $8 million due primarily to $12 million in higher sales volumes and $12 million due to the inclusion of Energy Strong in base rates, partially offset by lower Green Program Recovery Charges (GPRC) of $16 million.

***Commodity Revenue*** decreased $19 million as a result of $14 million of lower Gas revenues and $5 million of lower Electric revenues. Commodity revenue for both gas and electric is entirely offset with the change in Energy Costs. PSE&G earns no margin on the provision of BGSS and BGS to retail customers.

- Gas revenues decreased $14 million due to $25 million of lower BGSS sales volumes, partially offset by $11 million in higher prices.
- Electric revenues decreased $5 million due primarily to $17 million of lower revenues from collections of Non-Utility Generation Charges (NGC) and a decrease of $14 million due to lower volumes of Non-Utility Generation (NUG) energy sold at lower prices. These decreases were partially offset by a $26 million increase in BGS revenues due to higher sales volumes.

***Clause Revenues*** decreased $121 million due primarily to lower Securitization Transition Charges (STC) of $118 million. The STC reduction was a result of rate reductions due to the completion of securitization collections in 2015. The changes in the STC amounts are entirely offset by decreases in the amortization of Regulatory Assets and related costs in O&M, Depreciation and Amortization and Interest Expense. PSE&G does not earn margin on STC collections.

### Operating Expenses

**Energy Costs** decreased $19 million. This is entirely offset by the change in Commodity Revenue.

**Operation and Maintenance** decreased $15 million, of which the most significant components were

- a $23 million net reduction in costs related to various clause mechanisms, including SBC and STC, and GPRC, and
- a $2 million decrease in pension and OPEB costs, net of capitalized amounts,
- partially offset by a net increase of $10 million in operating expenses, including increases in appliance service costs, gas distribution costs and electric distribution corrective maintenance.

**Depreciation and Amortization** decreased $94 million due to a decrease of $114 million in amortization of Regulatory Assets primarily as a result of the completion of the amortization of the securitization charges in 2015 (which is completely offset in STC Revenues), partially offset by an $18 million increase in depreciation due to additional plant in service.

**Interest Expense** increased $5 million due primarily to an increase of $7 million due to net debt issuances in 2015 and 2016, partially offset by a $2 million decrease due to the redemption of securitization debt in 2015.

**Income Tax Expense** increased $7 million due primarily to higher pre-tax income, partially offset by plant-related items and uncertain tax positions.

### Nine Months Ended September 30, 2016 as Compared to 2015

**Operating Revenues** decreased $488 million due to changes in delivery, commodity, clause and other operating revenues.

***Delivery Revenues*** increased $116 million due primarily to an increase in transmission revenues.

- Transmission revenues were $152 million higher due to increased capital investments.
- Electric distribution revenues decreased $30 million due primarily to lower GPRC of $42 million and a $4 million decrease due to lower sales volumes partially offset by $16 million increase due to the inclusion of Energy Strong in base rates.
- Gas distribution revenues decreased $6 million due primarily to $75 million of lower delivery volumes and lower GPRC of $7 million due to lower sales volumes from warmer winter weather. These decreases were almost entirely offset by $64 million in higher Weather Normalization Clause revenue and a $12 million increase due to the inclusion of Energy Strong in base rates effective September 1, 2015.

***Commodity Revenue*** decreased $197 million as a result of lower Gas and Electric revenues. Commodity revenue for both gas and electric is entirely offset with decreased Energy Costs. PSE&G earns no margin on the provision of BGSS and BGS to retail customers.

- Gas revenues decreased $108 million due primarily to lower BGSS sales volumes.
- Electric revenues decreased $89 million due primarily to $43 million of lower revenues from collections of NGC, a decrease of $31 million due to lower volumes of NUG energy sold and a $15 million or 1% decrease in BGS revenues due primarily to lower sales volumes.

***Clause Revenues*** decreased $402 million due primarily to lower STC of $370 million, lower SBC of $38 million and $9 million of lower SPRC, partially offset by higher Margin Adjustment Clause (MAC) revenue of $15 million. The STC reduction is a result of rate reductions due to the completion of securitization collections in 2015. The changes in the STC, SBC, SPRC and MAC amounts are entirely offset by decreases in the amortization of Regulatory Assets and related costs in O&M, Depreciation and Amortization and Interest Expense. PSE&G does not earn margin on STC, SBC, SPRC or MAC collections.

### Operating Expenses

**Energy Costs** decreased $197 million. This is entirely offset by the change in Commodity Revenue.

**Operation and Maintenance** decreased $61 million, of which the most significant components were

- a $95 million net reduction in costs related to various clause mechanisms, including SBC, SPRC, STC and MAC, and GPRC, and
- a $10 million decrease in pension and OPEB costs, net of capitalized amounts,
- partially offset by $10 million of storm insurance recovery proceeds received in 2015,
- an $8 million increase in electric distribution corrective maintenance,
- a $5 million increase in vegetation management,
- a $5 million increase in transmission related maintenance and
- a $16 million increase in operating expenses, including $3 million increases related to both appliance service costs and gas distribution costs.

**Depreciation and Amortization** decreased $300 million due to a decrease of $353 million in amortization of Regulatory Assets primarily as a result of the completion of the amortization of the securitization charges in 2015 (which is completely offset in STC Revenues), partially offset by a $49 million increase in depreciation due to additional plant in service.

**Interest Expense** increased $11 million due primarily to an increase of $20 million due to net debt issuances in 2015 and 2016, partially offset by a $10 million decrease due to the redemption of securitization debt in 2015.

**Income Tax Expense** decreased $5 million due primarily to uncertain tax positions, plant-related and other flow through items, partially offset by higher pre-tax income.

### Power

|  | Three Months Ended September 30, 2016 Millions | 2015 | Increase/ (Decrease) September 30, 2016 vs. 2015 Millions% |  | Nine Months Ended 2016 Millions | 2015 | Increase/ (Decrease) 2016 vs. 2015 Millions% |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| Operating Revenues | $1,075 | $1,096 | $(21) | (2) | $3,102 | $3,846 | $(744) | (19) |
| Energy Costs | 462 | 367 | 95 | 26 | 1,481 | 1,669 | (188) | (11) |
| Operation and Maintenance | 289 | 263 | 26 | 10 | 807 | 748 | 59 | 8 |
| Depreciation and Amortization | 86 | 75 | 11 | 15 | 245 | 226 | 19 | 8 |
| Income from Equity Method Investments | 3 | 3 | — | — | 9 | 11 | (2) | (18) |
| Other Income (Deductions) | 17 | 11 | 6 | 55 | 41 | 77 | (36) | (47) |
| Other-Than-Temporary Impairments | 5 | 30 | (25) | (83) | 25 | 45 | (20) | (44) |
| Interest Expense | 24 | 30 | (6) | (20) | 66 | 94 | (28) | (30) |
| Income Tax Expense | 90 | 139 | (49) | (35) | 208 | 445 | (237) | (53) |

### Three Months Ended September 30, 2016 as Compared to 2015

**Operating Revenues** decreased $21 million due to changes in generation, gas supply and other revenues.

***Generation Revenues*** decreased $23 million due primarily to

- a decrease of $73 million in energy sales volumes and lower average realized prices, primarily in the PJM region, and
- a decrease of $24 million in capacity revenue, primarily in the PJM region,
- partially offset by a net increase of $44 million in electricity sold under non-BGS wholesale load contracts in the PJM and NE regions due to higher volumes sold partially offset by lower average prices, and
- an increase of $24 million in electricity sold under our BGS contracts due primarily to higher volumes as a result of warmer weather, coupled with higher average prices.

### Operating Expenses

**Energy Costs** represent the cost of generation, which includes fuel costs for generation as well as purchased energy in the market, and gas purchases to meet Power’s obligation under its BGSS contract with PSE&G. Energy Costs increased $95 million due primarily to

***Generation costs*** increased $93 million due to

- a $62 million charge associated with the announced early retirement of the coal/gas Mercer and Hudson generation units, primarily related to a coal inventory write-down of $57 million,
- an increase of $32 million due to MTM losses in 2016 as compared to MTM gains in 2015. Of this amount, $25 million was due to lower gains on positions reclassified to realized upon settlement this year compared to last year, and
- an increase of $13 million due to increases in purchases of renewable energy credits and energy to serve load contracts,
- partially offset by a decrease of $20 million due primarily to lower natural gas costs reflecting lower average realized prices.

**Operation and Maintenance** increased $26 million due primarily to

- $48 million of charges related to the early retirement of the Hudson and Mercer units,
- partially offset by a net decrease of $18 million due to the timing of a planned outage at our 50%-owned Peach Bottom nuclear plant.

**Depreciation and Amortization** increased $11 million due primarily to

- a $7 million increase due primarily to a higher nuclear asset base, and
- $4 million of accelerated depreciation on asset retirement costs from previously retired assets at the Hudson and Mercer plants.

**Other Income (Deductions)** increased $6 million due primarily to lower net realized losses from the NDT Fund in 2016.

**Other-Than-Temporary Impairments** decreased $25 million due to lower impairments of equity securities in the NDT Fund in 2016.

**Interest Expense** decreased $6 million due primarily to higher capitalized interest in 2016.

**Income Tax Expense** decreased $49 million in 2016 due primarily to lower pre-tax income.

### Nine Months Ended September 30, 2016 as Compared to 2015

**Operating Revenues** decreased $744 million due to changes in generation, gas supply and other revenues.

***Generation Revenues*** decreased $497 million due primarily to

- a decrease of $213 million in energy sales volumes in the PJM, NE and New York (NY) regions due primarily to milder weather and lower average realized prices,
- a decrease of $166 million due to MTM losses in 2016 as compared to MTM gains in 2015. Of this amount, $127 million was due to higher gains on positions reclassified to realized upon settlement this year compared to last year. Also contributing to the decrease were lower MTM gains of $39 million due to minor changes in forward power prices this year compared to last year,
- a net decrease of $113 million primarily in the PJM region due to lower capacity revenue resulting from the retirement of older peaking units in June 2015, coupled with lower operating reserve revenue, and
- a net decrease of $10 million in electricity sold under our BGS contracts due primarily to lower volumes as a result of milder weather, partially offset by higher average prices.

***Gas Supply Revenues*** decreased $248 million due primarily to

- a decrease of $241 million in sales under the BGSS contract, substantially comprised of lower sales volumes due to warmer average temperatures in the 2016 winter heating season, coupled with lower average sales prices, and
- a net decrease of $7 million in sales to third party customers, of which $45 million was due to lower average prices, partially offset by $38 million of higher volumes sold.

### Operating Expenses

**Energy Costs** represent the cost of generation, which includes fuel costs for generation as well as purchased energy in the market, and gas purchases to meet Power’s obligation under its BGSS contract with PSE&G. Energy Costs decreased $188 million due to

***Generation costs*** decreased $67 million due primarily to

- lower fuel costs of $287 million reflecting lower average realized prices for natural gas and the utilization of lower volumes of fuel,
- partially offset by higher congestion costs in PJM of $137 million, mainly as a result of credits received in the prior year due to extremely cold winter weather,
- a $62 million charge associated with the announced early retirement of the Mercer and Hudson units, primarily related to a coal inventory write-down of $57 million, and
- a net increase of $15 million due to lower MTM gains in 2016 as compared to 2015. Of this amount, $10 million was due to lower gains on positions reclassified to realized upon settlement this year compared to last year.

***Gas costs*** decreased $121 million mainly related to

- a decrease of $142 million related to sales under the BGSS contract due primarily to lower volumes sold due to warmer average temperatures during the 2016 winter heating season and lower average gas costs,
- partially offset by a net increase of $21 million related to sales to third parties due primarily to an increase in volumes sold.

**Operation and Maintenance** increased $59 million due primarily to

- $145 million of insurance recoveries received in 2015 related to Superstorm Sandy,
- $48 million of charges related to early retirement of the Hudson and Mercer units,
- partially offset by a net decrease of $75 million related to our fossil plants, largely due to higher costs incurred in 2015 for our planned major outages at the Bethlehem Energy Center and Bergen generating plants, and
- a net decrease of $58 million related to our nuclear plants due primarily to a planned outage at our 100%-owned Hope Creek plant and our 50%-owned Peach Bottom plant in 2015, partly offset in 2016 by an extended refueling outage at our 57%-owned Salem Unit 1 plant.

**Depreciation and Amortization** increased $19 million due primarily to

- a $12 million increase due primarily to a higher nuclear asset base,
- $4 million of accelerated depreciation on asset retirement costs from previously retired assets at the Hudson and Mercer plants, and
- $3 million of higher depreciation due to new solar projects.

**Other Income (Deductions)** decreased $36 million due primarily to $28 million of insurance recoveries received in 2015 related to Superstorm Sandy and lower net realized gains from the NDT Fund in 2016.

**Other-Than-Temporary Impairments** decreased $20 million due to lower impairments of equity securities in the NDT Fund in 2016.

**Interest Expense** decreased $28 million due primarily to higher capitalized interest in 2016 and the maturity of $300 million of 5.50% Senior Notes in December 2015, partially offset by the issuance of $700 million of 3.00% Senior Notes in June 2016.

**Income Tax Expense** decreased $237 million in 2016 due primarily to lower pre-tax income.

### LIQUIDITY AND CAPITAL RESOURCES

The following discussion of our liquidity and capital resources is on a consolidated basis, noting the uses and contributions, where material, of our two direct major operating subsidiaries.

### Operating Cash Flows

We expect operating cash flows combined with cash on hand and financing activities to be sufficient to fund planned capital expenditures and shareholder dividend payments.

For the nine months ended September 30, 2016, our operating cash flow decreased $467 million as compared to the same period in 2015. The net change was due primarily to the net changes from PSE&G and Power as discussed below.

### PSE&G

PSE&G’s operating cash flow decreased $117 million from $1,518 million to $1,401 million for the nine months ended September 30, 2016, as compared to the same period in 2015, due primarily to a decrease of $113 million due to a change in regulatory deferrals, a $64 million decrease due to higher vendor payments and a decrease due to the completion of securitization collections in 2015. These amounts were partially offset by higher earnings and higher tax refunds in 2016.

### Power

Power’s operating cash flow decreased $298 million from $1,558 million to $1,260 million for the nine months ended September 30, 2016, as compared to the same period in 2015, primarily due to lower earnings, a $140 million decrease from fuels, materials and supplies, and a $146 million increase in margin deposit requirements, partially offset by a reduction in tax payments.

### Short-Term Liquidity

PSEG meets its short-term liquidity requirements, as well as those of Power, primarily with cash and through the issuance of commercial paper. PSE&G maintains its own separate commercial paper program to meet its short-term liquidity requirements. Each commercial paper program is fully back-stopped by its own separate credit facilities.

We continually monitor our liquidity and seek to add capacity as needed to meet our liquidity requirements. Each of our credit facilities is restricted as to availability and use to the specific companies as listed below; however, if necessary, the PSEG facilities can also be used to support our subsidiaries’ liquidity needs. Our total credit facilities and available liquidity as of September 30, 2016 were as follows:

| Company/Facility Total Facility | As of September 30, 2016 Millions | Usage | Available Liquidity |
| --- | ---: | ---: | ---: |
| PSEG | $1,000 | $265 | $735 |
| PSE&G | 600 | 14 | 586 |
| Power | 2,553 | 205 | 2,348 |
| **Total** | **$4,153** | **$484** | **$3,669** |

As of September 30, 2016, our credit facility capacity was in excess of our projected maximum liquidity requirements over our 12 month planning horizon. Our maximum liquidity requirements are based on stress scenarios that incorporate changes in commodity prices and the potential impact of Power losing its investment grade credit rating, which would represent a three level downgrade from its current S&P and Moody’s ratings. In the event of a deterioration of Power’s credit rating certain of Power’s agreements allow the counterparty to demand further performance assurance. The potential additional collateral that we would be required to post under these agreements if Power were to lose its investment grade credit rating was approximately $807 million and $864 million as of September 30, 2016 and December 31, 2015, respectively. The early retirement of Power’s Hudson and Mercer coal/gas generation units is not expected to have a material impact on Power’s debt covenant ratios or its ability to obtain credit facilities. See Item 1. Note 3. Early Plant Retirements.

As of September 30, 2016, PSEG’s credit facilities are primarily available to back-stop its Commercial Paper Program under which PSEG had $255 million outstanding. PSE&G’s credit facility primary use is to support its Commercial Paper Program under which as of September 30, 2016, no amounts were outstanding. Most of our credit facilities expire in 2019 and 2020.

For additional information, see Item 1.Note 10. Debt and Credit Facilities.

### Long-Term Debt Financing

For a discussion of our long-term debt transactions during 2016, see Item 1. Note 10. Debt and Credit Facilities.

### Common Stock Dividends

On July 19, 2016, our Board of Directors approved a quarterly dividend of $0.41 per share of common stock for the third quarter of 2016. This reflects an indicative annual dividend rate of $1.64 per share. We expect to continue to pay cash dividends on our common stock; however, the declaration and payment of future dividends to holders of our common stock will be at the discretion of the Board of Directors and will depend upon many factors, including our financial condition, earnings, capital requirements of our businesses, alternate investment opportunities, legal requirements, regulatory constraints, industry practice and other factors that the Board of Directors deems relevant. For additional information related to cash dividends on our common stock, see Item 1. Note 16. Earnings Per Share (EPS) and Dividends.

### Credit Ratings

If the rating agencies lower or withdraw our credit ratings, such revisions may adversely affect the market price of our securities and serve to materially increase our cost of capital and limit access to capital. Credit Ratings shown are for securities that we typically issue. Outlooks are shown for Corporate Credit Ratings (S&P) and Issuer Credit Ratings (Moody’s) and can be Stable, Negative, or Positive. There is no assurance that the ratings will continue for any given period of time or that they will not be revised by the rating agencies, if, in their respective judgments, circumstances warrant. Each rating given by an agency should be evaluated independently of the other agencies’ ratings. The ratings should not be construed as an indication to buy, hold or sell any security.

In January 2016, S&P published updated research reports on PSEG and PSE&G and the existing ratings and outlooks were unchanged. In June 2016, Moody’s published credit opinions on Power and PSE&G and the existing ratings and outlooks were unchanged. In June 2016, S&P published an updated research report on Power and the existing rating and outlook were unchanged. In September 2016, Moody’s published an updated research report on PSEG and the existing rating and outlook were unchanged.

|  | Moody’s (A) | S&P (B) |
| --- | --- | --- |
| **PSEG** |  |  |
| Outlook | **Positive** | **Stable** |
| Commercial Paper | P2 | A2 |
| **PSE&G** |  |  |
| Outlook | **Stable** | **Stable** |
| Mortgage Bonds | Aa3 | A |
| Commercial Paper | P1 | A2 |
| **Power** |  |  |
| Outlook | **Stable** | **Stable** |
| Senior Notes | Baa1 | BBB+ |

(A) Moody’s ratings range from Aaa (highest) to C (lowest) for long-term securities and P1 (highest) to NP (lowest) for short-term securities.

(B) S&P ratings range from AAA (highest) to D (lowest) for long-term securities and A1 (highest) to D (lowest) for short-term securities. The Corporate Credit Rating outlook does not apply to PSEG’s or PSE&G’s Commercial Paper Rating or PSE&G’s Mortgage Bond rating.

### CAPITAL REQUIREMENTS

We expect that all of our capital requirements over the next three years will come from a combination of internally generated funds and external debt financing. There were no material changes to our projected capital expenditures at Power and Services as compared to amounts disclosed in our 2015 Form 10-K.

### PSEG

In July 2016, PSEG partnered with Vectren Corporation on a FERC 1000 proposal to construct, own and operate a twenty mile, 345 kilovolt transmission line in the midwest region served by the Midcontinent Independent System Operator (MISO). MISO estimated the project would cost approximately $60 million and would go in service in 2021. MISO is expected to select a proposal in December 2016. This project is not included in PSEG’s projected capital expenditures.

### PSE&G

PSE&G increased its estimate of its capital expenditure program as reported in our 2015 Form 10-K by approximately $300 million from $8.3 billion to $8.6 billion primarily to address new business requests and replace aging equipment and infrastructure.

In August 2016, PSE&G filed a petition with the BPU requesting approval of the $268 million investment and an associated cost recovery mechanism to develop a project where PSE&G would rebuild New Jersey Transit’s Mason substation and related facilities in Kearny, NJ. This is not included in PSE&G’s projected capital expenditures.

On October 20, 2016, PSE&G submitted a settlement agreement to the BPU providing for an extension of the existing landfill/brownfield solar program to construct up to 33 MW of grid connected facilities with projected capital expenditures of approximately $80 million through May 2020. This extension is pending approval by the BPU. This is not included in PSE&G’s projected capital expenditures.

During the nine months ended September 30, 2016, PSE&G made capital expenditures of $2,035 million, primarily for transmission and distribution system reliability. This does not include expenditures for cost of removal, net of salvage, of $109 million, which are included in operating cash flows.

### Power

During the nine months ended September 30, 2016, Power made capital expenditures of $767 million, excluding $156 million for nuclear fuel, primarily related to our Keys, Sewaren 7, BH5 and other generation projects.

### ACCOUNTING MATTERS

For information related to recent accounting matters, see Item 1. Note 2. Recent Accounting Standards.

## Market risk

As filed, 3,230 characters.

The risk inherent in our market-risk sensitive instruments and positions is the potential loss arising from adverse changes in commodity prices, equity security prices and interest rates as discussed in the Notes to Condensed Consolidated Financial Statements. It is our policy to use derivatives to manage risk consistent with business plans and prudent practices. We have a Risk Management Committee comprised of executive officers who utilize a risk oversight function to ensure compliance with our corporate policies and risk management practices.

Additionally, we are exposed to counterparty credit losses in the event of non-performance or non-payment. We have a credit management process, which is used to assess, monitor and mitigate counterparty exposure. In the event of non-performance or non-payment by a major counterparty, there may be a material adverse impact on our financial condition, results of operations or net cash flows.

### Commodity Contracts

The availability and price of energy-related commodities are subject to fluctuations from factors such as weather, environmental policies, changes in supply and demand, state and federal regulatory policies, market rules and other events. To reduce price risk caused by market fluctuations, we enter into supply contracts and derivative contracts, including forwards, futures, swaps and options with approved counterparties. These contracts, in conjunction with physical sales and other services, help reduce risk and optimize the value of owned electric generation capacity.

### Value-at-Risk (VaR) Models

VaR represents the potential losses, under normal market conditions, for instruments or portfolios due to changes in market factors, for a specified time period and confidence level. We estimate VaR across our commodity businesses.

MTM VaR consists of MTM derivatives that are economic hedges, some of which qualify for hedge accounting. The MTM VaR calculation does not include market risks associated with activities that are subject to accrual accounting, primarily our generating facilities and some load serving activities.

The VaR models used are variance/covariance models adjusted for the change of positions with 95% and 99.5% confidence levels and a one-day holding period for the MTM activities. The models assume no new positions throughout the holding periods; however, we actively manage our portfolio.

From July through September 2016, MTM VaR remained relatively stable between low of $11 million to high of $16 million at 95% confidence level. The range of VaR was narrower for the three months ended September 30, 2016 as compared with the year ended December 31, 2015.

| 95% Confidence Level, Loss could exceed VaR one day in 20 days | MTM VaR Three Months Ended September 30, 2016 Millions | Year Ended December 31, 2015 |
| --- | ---: | ---: |
| Period End | $11 | $24 |
| Average for the Period | $13 | $17 |
| High | $16 | $40 |
| Low | $11 | $8 |
| **99.5% Confidence Level, Loss could exceed VaR one day in 200 days** |  |  |
| Period End | $17 | $38 |
| Average for the Period | $21 | $26 |
| High | $25 | $63 |
| Low | $17 | $12 |

See Item 1. Note 11. Financial Risk Management Activities for a discussion of credit risk.

## Controls and procedures

As filed, 1,734 characters.

### Disclosure Controls and Procedures

We have established and maintain disclosure controls and procedures as defined under Rule 13a-15(e) and 15d-15(e) promulgated under the Securities Exchange Act of 1934, as amended (the “Exchange Act”) that are designed to provide reasonable assurance that information required to be disclosed in the reports that are filed or submitted under the Exchange Act is recorded, processed, summarized and reported and is accumulated and communicated to the Chief Executive Officer (CEO) and Chief Financial Officer (CFO) of each respective company, as appropriate, by others within the entities to allow timely decisions regarding required disclosure. We have established a disclosure committee which includes several key management employees and which reports directly to the CFO and CEO of each of Public Service Enterprise Group Incorporated, Public Service Electric and Gas Company and PSEG Power LLC. The committee monitors and evaluates the effectiveness of these disclosure controls and procedures. The CFO and CEO of each of Public Service Enterprise Group Incorporated, Public Service Electric and Gas Company and PSEG Power LLC have evaluated the effectiveness of the disclosure controls and procedures and, based on this evaluation, have concluded that disclosure controls and procedures at each respective company were effective at a reasonable assurance level as of the end of the period covered by the report.

### Internal Controls

There have been no changes in internal control over financial reporting that occurred during the third quarter of 2016 that have materially affected, or are reasonably likely to materially affect, each registrant’s internal control over financial reporting.

## Risk factors

As filed, 126 characters.

There are no additional Risk Factors to be added to those disclosed in Part I, Item 1A of our 2015 Annual Report on Form 10-K.

Filed Oct 31, 2016.
Source: SEC EDGAR, the filing index for accession 0000788784-16-000038. Last ingested by Listed: Nov 6, 2026, 17:31 ET. No prices; not investment advice.