# Public Service Enterprise Group Inc: Form 10-Q for the period ended Mar 31, 2019

- Company: [Public Service Enterprise Group Inc](/companies/peg.md) (CIK 788784)
- Form: 10-Q
- Filed: 2019-05-02
- Accepted by EDGAR: May 2, 2019, 16:51 ET
- Period: 2019-03-31
- Accession: 0000788784-19-000009
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/788784/000078878419000009/pseg-3312019q110xq.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/788784/000078878419000009/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2019-03-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2019-01-01 to 2019-03-31 | $2.98bn | us-gaap:Revenues |
| Cost of revenue | 3 months, 2019-01-01 to 2019-03-31 | $1.12bn | us-gaap:CostOfGoodsAndServicesSold |
| Operating income | 3 months, 2019-01-01 to 2019-03-31 | $786.0m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2019-01-01 to 2019-03-31 | $133.0m | us-gaap:InterestExpense |
| Income tax | 3 months, 2019-01-01 to 2019-03-31 | $149.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2019-01-01 to 2019-03-31 | $700.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2019-01-01 to 2019-03-31 | $1.38 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2019-01-01 to 2019-03-31 | $1.39 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2019-01-01 to 2019-03-31 | 507,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months, 2019-01-01 to 2019-03-31 | $1.22bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months, 2019-01-01 to 2019-03-31 | $795.0m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 3 months, 2019-01-01 to 2019-03-31 | $238.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2019-03-31 | $65.0m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2019-03-31 | $3.03bn | us-gaap:AssetsCurrent |
| Total assets | at 2019-03-31 | $45.76bn | us-gaap:Assets |
| Current liabilities | at 2019-03-31 | $4.47bn | us-gaap:LiabilitiesCurrent |
| Long-term debt | at 2019-03-31 | $13.22bn | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2019-03-31 | $900.0m | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | at 2019-03-31 | $1.15bn | us-gaap:CommercialPaper |
| Shareholders' equity | at 2019-03-31 | $14.81bn | us-gaap:StockholdersEquityIncludingPortionAttributableToNoncontrollingInterest |

## Management's discussion and analysis

As filed, 52,803 characters.

This combined MD&A is separately filed by Public Service Enterprise Group Incorporated (PSEG), Public Service Electric and Gas Company (PSE&G) and PSEG Power LLC (Power). Information contained herein relating to any individual company is filed by such company on its own behalf. PSE&G and Power each make representations only as to itself and make no representations whatsoever as to any other company.

PSEG’s business consists of two reportable segments, our principal direct wholly owned subsidiaries, which are:

- **PSE&G—**which is a public utility engaged principally in the transmission of electricity and distribution of electricity and natural gas in certain areas of New Jersey. PSE&G is subject to regulation by the New Jersey Board of Public Utilities (BPU) and the Federal Energy Regulatory Commission (FERC). PSE&G also invests in regulated solar generation projects and energy efficiency and related programs in New Jersey, which are regulated by the BPU, and
- **Power—**which is a multi-regional energy supply company that integrates the operations of its merchant nuclear and fossil generating assets with its power marketing businesses and fuel supply functions through competitive energy sales in well-developed energy markets primarily in the Northeast and Mid-Atlantic United States through its principal direct wholly owned subsidiaries. In addition, Power owns and operates solar generation in various states. Power’s subsidiaries are subject to regulation by FERC, the Nuclear Regulatory Commission (NRC), the Environmental Protection Agency (EPA) and the states in which they operate.

PSEG’s other direct wholly owned subsidiaries are: PSEG Long Island LLC (PSEG LI), which operates the Long Island Power Authority’s (LIPA) transmission and distribution (T&D) system under an Operations Services Agreement; PSEG Energy Holdings L.L.C. (Energy Holdings), which primarily has investments in leveraged leases; and PSEG Services Corporation (Services), which provides certain management, administrative and general services to PSEG and its subsidiaries at cost.

Our business discussion in Part I, Item 1. Business of our 2018 Annual Report on 10-K (Form 10-K) provides a review of the regions and markets where we operate and compete, as well as our strategy for conducting our businesses within these markets, focusing on operational excellence, financial strength and making disciplined investments. Our risk factor discussion in Part I, Item 1A. Risk Factors of Form 10-K provides information about factors that could have a material adverse impact on our businesses. The following supplements that discussion and the discussion included in the Executive Overview of 2018 and Future Outlook provided in Item 7 in our Form 10-K by describing significant events and business developments that have occurred during 2019 and changes to the key factors that we expect may drive our future performance. The following discussion refers to the Condensed Consolidated Financial Statements (Statements) and the Related Notes to Condensed Consolidated Financial Statements (Notes). This discussion should be read in conjunction with such Statements, Notes and the Form 10-K.

### EXECUTIVE OVERVIEW OF 2019 AND FUTURE OUTLOOK

Our business plan is designed to achieve growth while managing the risks associated with fluctuating commodity prices and changes in customer demand.

### PSE&G

At PSE&G, our focus is on enhancing reliability and resiliency of our T&D system, meeting customer expectations and supporting public policy objectives by investing capital in T&D infrastructure and clean energy programs. Over the past few years, our investments have altered our business mix to reflect a higher percentage of earnings contribution by PSE&G. Over the next five years, we expect to invest between $11 billion and $16 billion in our business which is expected to provide an annual rate base growth of 7%—9%.

In May 2018, we received approval for our Gas System Modernization Program II (GSMP II), an expanded, five-year program to invest $1.9 billion beginning in 2019 to replace approximately 875 miles of cast iron and unprotected steel mains in addition to other improvements to the gas system. Approximately $1.6 billion will be recovered through periodic rate roll-ins, with the remaining $300 million to be recovered through a future base rate proceeding. As part of the settlement, PSE&G agreed to file a base rate proceeding no later than five years from the commencement of the program, to maintain a base level of gas distribution capital expenditures of $155 million per year and to achieve certain leak reduction targets.

In June 2018, we filed for our Energy Strong Program II (ES II), a proposed five-year $2.5 billion program to harden, modernize and make our electric and gas distribution systems more resilient. The size and duration of ES II, as well as certain other elements of the program, are subject to BPU approval. The review process is expected to conclude in the third quarter of 2019.

In October 2018, we filed our proposed Clean Energy Future (CEF) program with the BPU, a six-year estimated $3.5 billion investment covering four programs; (i) an Energy Efficiency (EE) program totaling $2.5 billion of investment designed to achieve energy efficiency targets required under New Jersey’s Clean Energy law; (ii) an Electric Vehicle (EV) infrastructure program; (iii) an Energy Storage (ES) program and (iv) an Energy Cloud (EC) program which will include installing approximately two million electric smart meters and associated infrastructure. The review process for the CEF-EE program is expected to conclude by the third quarter of 2019. The CEF-EV/ES and CEF-EC programs will have separate procedural schedules.

In November 2018, the New Jersey Division of Rate Counsel (Rate Counsel) filed a motion to dismiss the CEF-EC filing on the basis that the BPU announced a moratorium on electric distribution companies’ advanced meter infrastructure programs. In December 2018, Rate Counsel filed a motion to stay the CEF-EV/ES filing, arguing that the BPU should conclude other regulatory proceedings addressing EVs and ES, including the new Energy Master Plan and initiatives required by the Clean Energy Act, before it rules on PSE&G’s program. We opposed Rate Counsel’s motions, asking for the BPU to permit these filings to proceed. There is no timetable for the BPU to decide on Rate Counsel’s motions.

We also continue to invest in transmission infrastructure in order to (i) maintain and enhance system integrity and grid reliability, grid security and safety, (ii) address an aging transmission infrastructure, (iii) leverage technology to improve the operation of the system, (iv) reduce transmission constraints, (v) meet growing demand and (vi) meet environmental requirements and standards set by various regulatory bodies. Our planned capital spending for transmission in 2019-2021 is $3.4 billion.

### Power

At Power, we strive to improve performance and reduce costs in order to optimize cash flow generation from our fleet in light of low wholesale power and gas prices, environmental considerations and competitive market forces that reward efficiency and reliability. Power continues to move its fleet toward improved efficiency and believes that its investment program enhances its competitive position with the addition of efficient, clean, reliable combined cycle gas turbine capacity. Our commitments for load, such as basic generation service (BGS) in New Jersey and other bilateral supply contracts, are backed by this generation or may be combined with the use of physical commodity purchases and financial instruments from the market to optimize the economic efficiency of serving our obligations. Power’s hedging practices and ability to capitalize on market opportunities help it to balance some of the volatility of the merchant power business. More than half of Power’s expected gross margin in 2019 relates to our hedging strategy, our expected revenues from the capacity market mechanisms and certain ancillary service payments such as reactive power.

In mid-2018, we commenced commercial operations of Keys Energy Center (Keys) and Sewaren 7. Construction continues on Bridgeport Harbor Station Unit 5 (BH5), which is targeted for commercial operation in mid-2019. Our investments in these units reflect our recognition of the value of opportunistic growth in the Power business. These additions to our fleet both expand our geographic diversity and adjust our fuel mix and enhance the environmental profile and overall efficiency of Power’s generation fleet.

### Operational Excellence

We emphasize operational performance while developing opportunities in both our competitive and regulated businesses. Flexibility in our generating fleet has allowed us to take advantage of opportunities in a rapidly evolving market as we remain diligent in managing costs. In the first three months of 2019, our

- utility continued its efforts to control costs while maintaining strong operational performance,
- diverse fuel mix and dispatch flexibility allowed us to generate approximately 14 terawatt hours while addressing fuel availability and price volatility, and
- total nuclear fleet achieved a capacity factor of 98.0%.

### Financial Strength

Our financial strength is predicated on a solid balance sheet, positive operating cash flow and reasonable risk-adjusted returns on increased investment. Our financial position remained strong during the first three months of 2019 as we

- maintained sufficient liquidity,
- maintained solid investment grade credit ratings, and
- increased our indicative annual dividend for 2019 to $1.88 per share.

We expect to be able to fund our planned capital requirements, as described in Liquidity and Capital Resources, and the impacts of the Tax Cuts and Jobs Act of 2017 (Tax Act) without the issuance of new equity. For additional information on the impacts of the Tax Act, see Tax Legislation below.

### Financial Results

As a result of the settlement of PSE&G’s distribution base rate proceeding in October 2018, with new rates effective November 1, 2018, PSE&G expects a net reduction in overall annual revenues of approximately $13 million. This is comprised of a $212 million increase in base revenues, including recovery of deferred storm costs, offset by the return of tax benefits of approximately $225 million. The tax benefits include the flow-back to customers of excess accumulated deferred income taxes resulting from the reduction of the federal income tax rates provided in the Tax Act as well as the accumulated deferred income taxes from previously realized tax repair deductions and tax benefits from future tax repair deductions as realized.

PSE&G also filed a revised 2019 Annual Transmission Formula Rate Update to include the refund of the approved excess deferred income tax benefits. The revised 2019 Annual Transmission Formula Rate, as filed with FERC in January 2019, decreases overall annual transmission revenues by approximately $54 million, subject to true-up.

The results for PSEG, PSE&G and Power for the three months ended March 31, 2019 and 2018 are presented as follows:

| Earnings (Losses) | Three Months Ended March 31, 2019 Millions | 2018 |
| --- | ---: | ---: |
| PSE&G | $403 | $319 |
| Power | 296 | 234 |
| Other (A) | 1 | 5 |
| **PSEG Net Income** | **$700** | **$558** |
| **PSEG Net Income Per Share (Diluted)** | **$1.38** | **$1.10** |

(A) Other includes after-tax activities at the parent company, PSEG LI, and Energy Holdings as well as intercompany eliminations.

Power’s results above include the Nuclear Decommissioning Trust (NDT) Fund activity and the impacts of non-trading commodity mark-to-market (MTM) activity, which consist of the financial impact from positions with future delivery dates.

The variances in our Net Income attributable to changes related to the NDT Fund and MTM are shown in the following table:

|  | Three Months Ended March 31, 2019 Millions, after tax | 2018 |
| --- | ---: | ---: |
| NDT Fund Income (Expense) (A) (B) | $76 | $(16) |
| Non-Trading MTM Gains (Losses) (C) | $76 | $85 |

(A) NDT Fund Income (Expense) includes gains and losses on NDT securities which are recorded in Net Gains (Losses) on Trust Investments. See Item 1. Note 9. Trust Investments for additional information. NDT Fund Income (Expense) also includes interest and dividend income and other costs related to the NDT Fund recorded in Other Income (Deductions), interest accretion expense on Power’s nuclear Asset Retirement Obligation (ARO) recorded in Operation and Maintenance (O&M) Expense and the depreciation related to the ARO asset recorded in Depreciation and Amortization (D&A) Expense.

(B) Net of tax (expense) benefit of $(51) million and $8 million for the three months ended March 31, 2019 and 2018, respectively.

(C) Net of tax expense of $(30) million and $(33) million for the three months ended March 31, 2019 and 2018, respectively.

Our $142 million increase in Net Income for the three months ended March 31, 2019 was driven largely by

- net unrealized gains in 2019 as compared to net unrealized losses in 2018 on equity securities in the NDT Fund at Power, and
- higher earnings due to investments in T&D programs and the favorable impact of new rates effective November 1, 2018 as a result of the BPU approval of our distribution base rate proceeding at PSE&G.

The greater emphasis on capital spending in recent years for projects on which we receive contemporaneous returns at PSE&G has yielded strong results, which when combined with the cash flow generated by Power, has allowed us to increase our dividend annually. These actions to meet customer needs, market conditions and investor expectations reflect our long-term approach to managing our company. We continue our focus on operational excellence, financial strength and disciplined investment. These guiding principles have provided the base from which we have been able to execute our strategic initiatives.

### Disciplined Investment

We utilize rigorous criteria when deploying capital and seek to invest in areas that complement our existing business and provide reasonable risk-adjusted returns. These areas include upgrading our energy infrastructure and improving our environmental footprint to align with public policy objectives. In the first three months of 2019, we

- made additional investments in T&D infrastructure projects,
- continued to execute our Energy Efficiency and other existing BPU-approved utility programs, and
- continued construction of our BH5 generation project, the final stage of our investment program in combined cycle gas turbines.

### Regulatory, Legislative and Other Developments

In our pursuit of operational excellence, financial strength and disciplined investment, we closely monitor and engage with stakeholders on significant regulatory and legislative developments. Transmission planning rules and wholesale power market design are of particular importance to our results and we continue to advocate for policies and rules that promote fair and efficient electricity markets. For additional information about regulatory, legislative and other developments that may affect us, see Part I, Item 1. Business—Regulatory Issues in our Form 10-K and Item 5. Other Information in this Quarterly Report on Form 10-Q.

### Transmission Planning

There are several matters pending before FERC that may impact the allocation of costs associated with transmission projects, including those being constructed by PSE&G. Regardless of how these proceedings are resolved, PSE&G’s ability to recover the costs of these projects will not be affected. However, the result of these proceedings could ultimately impact the amount of costs borne by customers in New Jersey. In addition, as a BGS supplier, Power provides services that include specified transmission costs. If the allocation of the costs associated with the transmission projects were to increase these BGS-related transmission costs, BGS suppliers would be entitled to recovery, subject to BPU approval. We do not believe that these matters will have a material effect on Power’s business or results of operations.

Several complaints have been filed and several remain pending at FERC against transmission owners around the country, challenging those transmission owners’ base return on equity (ROE). Certain of those complaints have resulted in decisions and others have been settled, resulting in reductions of those transmission owners’ base ROEs. The results of these other proceedings could set precedents for other transmission owners with formula rates in place, including PSE&G.

In October 2018, FERC issued an order establishing a new framework for determining whether a company’s ROE is unjust and unreasonable. FERC proposes to rely on financial models to establish a composite zone of reasonableness that will be used to determine whether an ROE complaint should be dismissed. If FERC determines that an ROE for a company is not just and reasonable, it intends to reset the ROE based on averaging the results of various financial models. We continue to analyze the potential impact of these methodologies and cannot predict the outcome of ongoing ROE proceedings.

In March 2019, FERC issued two Notices of Inquiry (NOI) that could affect a company’s ROE: (i) an NOI seeking comment on improvements to FERC’s electric transmission incentives policy to ensure that it appropriately encourages the development of the infrastructure needed to ensure grid reliability and reduce congestion to lower the cost of power for consumers (Incentive NOI), and (ii) an NOI seeking comments whether, and if so how, FERC should change its policies for establishing just and reasonable ROEs. The Incentive NOI is intended to examine whether existing incentives, such as the 50 basis point adder for Regional Transmission Organization membership, should continue to be granted and whether new incentives should be established.

### Wholesale Power Market Design

In June 2018, FERC issued an order finding that PJM’s current capacity market is not just and reasonable because it enabled state-supported resources to bid below their costs which resulted in suppressed clearing prices. In particular, FERC found that nuclear generating units that receive zero emission certificate payments were of concern. Depending on the outcome of this matter, our generating stations could also be impacted.

In October 2018, PJM filed with FERC to revise the shape of the Variable Resource Requirement (VRR) curve that will be implemented for the capacity auction to be held in August 2019. The VRR curve is the administratively determined demand curve that serves as one of the key elements for establishing the amount of generation capacity to be procured in the auction. PJM’s proposed tariff revisions will result in lower Cost of New Entry (CONE) values as compared to the currently effective VRR curve. PSEG protested PJM’s proposal on the grounds that it would result in understated prices for capacity relative to the cost of constructing a new reference generating unit and will result in prices that are unjust and unreasonable. In April 2019, FERC issued an Order approving PJM’s filing without modification and these changes are expected to be in place for the 2022/2023 PJM capacity auction to be held in August 2019.

### Environmental Regulation

We are subject to liability under environmental laws for the costs of remediating environmental contamination of property now or formerly owned by us and of property contaminated by hazardous substances that we generated. In particular, the historic operations of PSEG companies and the operations of numerous other companies along the Passaic and Hackensack Rivers are alleged by Federal and State agencies to have discharged substantial contamination into the Passaic River/Newark Bay Complex in violation of various statutes. We are also currently involved in a number of proceedings relating to sites where other hazardous substances may have been discharged and may be subject to additional proceedings in the future, and the costs of any such remediation efforts could be material.

In August 2018, the EPA released the proposed Affordable Clean Energy (ACE) rule as a replacement for the EPA’s Clean Power Plan. The proposed ACE rule gives states great flexibility to evaluate specific heat rate improvement technologies and practices to be applied at coal-fired electric generating units. States have three years from the date of finalization to submit a plan that establishes a standard of performance that reflects the degree of emission limitation through the application of heat rate improvement technologies and practices. We cannot estimate the impact of this action on our business or results of operations at this time.

For further information regarding the matters described above, as well as other matters that may impact our financial condition and results of operations, see Item 1. Note 11. Commitments and Contingent Liabilities.

### Nuclear

In May 2018, the governor of New Jersey signed legislation, referred to as the Zero Emission Certificate (ZEC) legislation, that recognizes that nuclear power is a critical component of New Jersey’s clean energy portfolio and an important element of a diverse energy generation portfolio that currently meets approximately 40 percent of New Jersey’s electric power needs. The ZEC legislation created a program administered by the BPU. The BPU established processes to provide for the purchase of ZECs from selected nuclear plants and recovery of those ZEC payments through a non-bypassable distribution charge (ZEC charge) in the amount of $0.004 per kilowatt-hour (which is equivalent to approximately $10 per megawatt hour (MWh)) in payments to selected nuclear plants.

In April 2019, Power’s Salem 1, Salem 2 and Hope Creek nuclear plants were awarded ZECs. As a result, the final “must-offer” exception requests and deactivation notices previously submitted to the PJM Independent Market Monitor and the PJM Office of Interconnection for the Salem and Hope Creek plants have been withdrawn. These nuclear plants are expected to receive ZEC revenue for approximately three years, through May 2022, and will be obligated to maintain operations, subject to exceptions specified in the ZEC legislation. Power anticipates it will recognize revenue monthly as the nuclear plants generate electricity and satisfy their performance obligations. The ZEC legislation requires nuclear plants to reapply for any subsequent three year periods. The ZEC payment may be adjusted by the BPU (a) at any time to offset environmental or fuel diversity payments that a selected nuclear plant may receive from another source or (b) at certain times specified in the ZEC legislation if the BPU determines that the purposes of the ZEC legislation can be achieved through a reduced charge that will nonetheless be sufficient to achieve the state’s air quality and other environmental objectives by preventing the retirement of nuclear plants. The financial condition of the plants may nonetheless be materially adversely impacted by potential changes to the capacity market construct being considered by FERC (absent sufficient capacity revenues provided under a program approved by the BPU in accordance with a FERC authorized capacity mechanism), and, in the case of the Salem nuclear plants, decisions by the EPA and state environmental regulators regarding the implementation of Section 316(b) of the Clean Water Act and related state regulations, or other factors. Absent a material financial change, these adverse impacts could still result in Power taking all necessary steps to retire all of these plants following the end of the initial three year term of the ZECs program. Retirement of these plants would result in a material adverse impact on PSEG’s and Power’s financial results.

In addition, in April 2019 Salem 1 began a scheduled refueling outage during which we planned to continue the replacement of degraded bolts inside the reactor vessel. Following an inspection and testing, it was revealed that a significantly larger number of bolts than initially anticipated will require replacement during this outage. As a result, we expect the duration of this outage to be longer than planned, which will impact Salem Unit 1’s production and margin, including the amount of ZEC payments received by Salem 1. Lower production at Salem 1 may be offset by increased production at our combined cycle generating stations.

### Fossil

PSEG and Power continue to monitor their other coal assets, including their interest in the Keystone and Conemaugh generating stations, to assess their economic viability through the end of their designated useful lives and their continued classification as held for use. The precise timing of a change in useful lives may be dependent upon events out of PSEG’s and Power’s control and may impact their ability to operate or maintain certain assets in the future. These generating stations may be impacted by factors such as environmental legislation, co-owner capital requirements and continued depressed wholesale power prices or capacity factors, among other things. Any early retirement or change in the classification as held for use of our remaining coal units may have a material adverse impact on PSEG’s and Power’s future financial results.

### California Solar Facilities

As part of its solar production portfolio, Power owns and operates two California-based solar facilities with an aggregate capacity of approximately 30 MW direct current whose output is sold to Pacific Gas and Electric Company (PG&E) under power purchase agreements (PPAs) with twenty year terms. The net book value of these solar facilities was approximately $57 million as of March 31, 2019. In January 2019, PG&E and its parent company PG&E Corporation filed for Chapter 11 bankruptcy protection. Power cannot predict the ultimate outcome that this bankruptcy proceeding will have on our ability to collect all of the revenues from these facilities due under the PPAs; however, any adverse changes to the terms of Power’s PPAs as a result of this bankruptcy proceeding could result in the future impairment of these assets in amounts up to their current net book value.

### Offshore Wind

In January 2018, the governor of New Jersey signed Executive Order No. 8 directing the BPU to begin the process of moving the state toward its 2030 goal of 3,500 MW of offshore wind energy generation. An initial solicitation was established for 1,100 MW of offshore wind, with bids due in December 2018. In connection with the bid submitted by Ocean Wind, LLC, a wholly owned subsidiary of Ørsted US Offshore Wind, referred to as the Ocean Wind project, PSEG agreed to provide energy management services and the potential lease of land for use in project development. We also retained an option to acquire an equity interest in the project. We expect to make a decision regarding an equity investment in the Ocean Wind project in the second half of 2019.

### Leveraged Leases

In December 2018, NRG REMA, LLC emerged from its in-court proceeding under Chapter 11 of the Bankruptcy Code. As a result of the restructuring, the remaining deferred tax liabilities related to the Keystone and Conemaugh lease investments were reclassified to current tax liabilities. PSEG expects to pay approximately $120 million to taxing authorities resulting from this restructuring activity.

Additional facilities in our leveraged lease portfolio include the Shawville, Joliet and Powerton generating facilities. Converted natural gas units such as Shawville and Joliet may have higher operating costs and fuel consumption, as well as longer start-up times, compared to newer combined cycle gas units. Powerton is a coal-fired generating facility in Illinois. Each of these three facilities may not be as economically competitive as newer combined cycle gas units and could continue to be adversely impacted by the same economic conditions experienced by other less efficient natural gas and coal generation facilities, which could require Energy Holdings to write down the residual value of the leveraged lease receivables associated with these facilities.

### Tax Legislation

The Tax Act, among other things, decreased the statutory U.S. corporate income tax rate from a maximum of 35% to 21%, effective January 1, 2018, and made certain changes to the bonus depreciation and interest disallowance rules.

In August 2018, the Internal Revenue Service (IRS) issued a Notice of Proposed Rulemaking (Notice) regarding the application of tax depreciation rules as amended by the Tax Act. While the Notice provides some guidance as to the application of the changes made by the Tax Act to the bonus depreciation rules, certain aspects remain unclear. Further, in November 2018 the IRS issued Proposed Regulations addressing the interest disallowance rules contained in the Tax Act. For non-regulated businesses, these rules set a cap on the amount of interest that can be deducted in a given year. Any amount that is disallowed can be carried forward indefinitely. For 2019, PSEG and Power expect that a portion of their interest will be disallowed in the current period but realized in future periods. However, certain aspects of the proposed regulations are unclear. Therefore, we recorded taxes based on our interpretation of the relevant statute. Such amounts are subject to change based on several factors, including but not limited to, the IRS and state taxing authorities issuing final guidance and/or further clarification. Any further guidance or clarification could impact PSEG’s, PSE&G’s and Power’s financial statements. For additional information, see Item 1. Note 16. Income Taxes.

In July 2018, the State of New Jersey made changes to its income tax laws, including imposing a temporary surtax of 2.5% effective January 1, 2018 and 2019 and 1.5% in 2020 and 2021, as well as requiring corporate taxpayers to file in a combined reporting group as defined under New Jersey law starting in 2019. Both provisions include an exemption for public utilities. We believe PSE&G meets the definition of a public utility and, therefore, will not be impacted by the temporary surtax or be included in the combined reporting group. We expect these new provisions to unfavorably affect our non-utility business. In accordance with accounting principles generally accepted in the United States for income taxes, deferred taxes are required to be measured at the enacted tax rate expected to apply to taxable income in the periods in which the deferred taxes are expected to settle. The newly enacted New Jersey tax legislation did not have a material impact on PSEG’s deferred income tax balance.

### Future Outlook

Our future success will depend on our ability to continue to maintain strong operational and financial performance in an environment with low gas prices, to capitalize on or otherwise address regulatory and legislative developments that impact our business and to respond to the issues and challenges described below. In order to do this, we must continue to:

- focus on controlling costs while maintaining safety, reliability and customer satisfaction and complying with applicable standards and requirements,
- successfully manage our energy obligations and re-contract our open supply positions in response to changes in prices and demand,
- obtain approval of and execute our utility capital investment program, including ES II, GSMP II, our CEF program and transmission and other investments that yield contemporaneous and reasonable risk-adjusted returns, while enhancing the resiliency of our infrastructure and maintaining the reliability of the service we provide to our customers,
- effectively complete construction of BH5,
- advocate for measures to ensure the implementation by PJM and FERC of market design and transmission planning rules that continue to promote fair and efficient electricity markets, including recognition of the cost of emissions,
- engage multiple stakeholders, including regulators, government officials, customers and investors, and
- successfully operate the LIPA T&D system and manage LIPA’s fuel supply and generation dispatch obligations.

In addition to the risks described elsewhere in this Form 10-Q and in our Form 10-K, for 2019 and beyond, the key issues and challenges we expect our business to confront include:

- regulatory and political uncertainty, both with regard to future energy policy, design of energy and capacity markets, transmission policy and environmental regulation, as well as with respect to the outcome of any legal, regulatory or other proceedings,
- the continuing impacts of the Tax Act and changes in state tax laws, and
- the impact of reductions in demand and lower natural gas and electricity prices and increasing environmental compliance costs.

We continually assess a broad range of strategic options to maximize long-term stockholder value. In assessing our options, we consider a wide variety of factors, including the performance and prospects of our businesses; the views of investors, regulators, customers and rating agencies; our existing indebtedness and restrictions it imposes; and tax considerations, among other things. Strategic options available to us include:

- the acquisition, construction or disposition of T&D facilities, clean energy investments and/or generation projects, including offshore wind opportunities,
- the disposition or reorganization of our merchant generation business or other existing businesses or the acquisition or development of new businesses,
- the expansion of our geographic footprint, including the operation of T&D facilities outside of our traditional service territory, and
- investments in capital improvements and additions, including the installation of environmental upgrades and retrofits, improvements to system resiliency, modernizing existing infrastructure and participation in transmission projects through FERC’s “open window” solicitation process.

There can be no assurance, however, that we will successfully develop and execute any of the strategic options noted above, or any additional options we may consider in the future. The execution of any such strategic plan may not have the expected benefits or may have unexpected adverse consequences.

### RESULTS OF OPERATIONS

### PSEG

Our results of operations are primarily comprised of the results of operations of our principal operating subsidiaries, PSE&G and Power, excluding charges related to intercompany transactions, which are eliminated in consolidation. For additional information on intercompany transactions, see Item 1. Note 20. Related-Party Transactions.

|  | Three Months Ended March 31, 2019 Millions | 2018 | Increase/ (Decrease) 2019 vs. 2018 Millions% |  |
| --- | ---: | ---: | ---: | ---: |
| Operating Revenues | $2,980 | $2,818 | $162 | 6 |
| Energy Costs | 1,124 | 952 | 172 | 18 |
| Operation and Maintenance | 756 | 754 | 2 | — |
| Depreciation and Amortization | 314 | 280 | 34 | 12 |
| Income from Equity Method Investments | 2 | 2 | — | — |
| Net Gains (Losses) on Trust Investments | 128 | (22) | 150 | N/A |
| Other Income (Deductions) | 33 | 32 | 1 | 3 |
| Non-Operating Pension and OPEB Credits (Costs) | 33 | 19 | 14 | 74 |
| Interest Expense | 133 | 103 | 30 | 29 |
| Income Tax Expense | 149 | 202 | (53) | (26) |

The following discussions for PSE&G and Power provide a detailed explanation of their respective variances.

### PSE&G

|  | Three Months Ended March 31, 2019 Millions | 2018 | Increase/ (Decrease) 2019 vs. 2018 Millions% |  |
| --- | ---: | ---: | ---: | ---: |
| Operating Revenues | $2,032 | $1,845 | $187 | 10 |
| Energy Costs | 947 | 782 | 165 | 21 |
| Operation and Maintenance | 408 | 391 | 17 | 4 |
| Depreciation and Amortization | 212 | 190 | 22 | 12 |
| Net Gains (Losses) on Trust Investments | 1 | — | 1 | N/A |
| Other Income (Deductions) | 19 | 20 | (1) | (5) |
| Non-Operating Pension and OPEB Credits (Costs) | 30 | 15 | 15 | 100 |
| Interest Expense | 87 | 81 | 6 | 7 |
| Income Tax Expense | 25 | 117 | (92) | (79) |

### Three Months Ended March 31, 2019 as Compared to 2018

**Operating Revenues** increased $187 million due to changes in delivery, commodity, clause and other operating revenues.

***Delivery Revenues*** decreased $22 million due primarily to

- Gas, Electric and Transmission revenue requirements were reduced by $129 million due to the flowback of excess deferred tax liabilities and tax repair-related accumulated deferred income tax benefits as a result of settlements with the BPU and FERC. This reduction is offset in Income Tax Expense.
- Gas distribution revenues increased $54 million due primarily to a $46 million increase due to the favorable impact of the distribution tariff rate effective November 2018, a $10 million increase from the inclusion of GSMP I in base rates,

and a $9 million increase due to higher sales volumes. These increases were partially offset by decreases in 2019 of $9 million in Weather Normalization Clause collections and $2 million in Green Program Recovery Charges (GPRC).

- Electric distribution revenues increased $29 million due to a $20 million increase resulting from the favorable impact of the distribution tariff rate, a $5 million increase due to higher sales volumes and a $4 million increase in GPRC collections.
- Transmission revenues were $24 million higher due to revenue requirements calculated through our transmission formula rate.

***Commodity Revenues*** increased $165 million as a result of higher Gas and Electric revenues. The changes in Commodity revenues for both gas and electric are entirely offset by the changes in Energy Costs. PSE&G earns no margin on the provision of basic gas supply service (BGSS) and BGS to retail customers.

- Gas commodity revenues increased $133 million due to higher BGSS prices of $94 million and higher BGSS sales volumes of $39 million.
- Electric commodity revenues increased $32 million due primarily to $21 million in higher BGS sales volumes and $15 million in higher BGS prices. These increases were partially offset by $2 million decreases in each of sales of solar renewable energy credits and the Non-Utility Generation Charge.

***Clause Revenues*** increased $47 million due to a $31 million increase in Tax Adjustment Credit (TAC) deferrals, higher Societal Benefit Charge (SBC) collections of $11 million and a $6 million increase in Margin Adjustment Clause (MAC) revenues. These increases were partially offset by a $1 million decrease in GPRC deferrals. The changes in the SBC and MAC collections and TAC and GPRC deferral amounts are entirely offset by changes in the amortization of Regulatory Assets and Regulatory Liabilities and related costs in O&M, D&A and Interest Expenses. PSE&G does not earn margin on SBC or MAC collections or on TAC or GPRC deferrals.

### Operating Expenses

**Energy Costs** increased $165 million. This is entirely offset by the change in Commodity Revenues.

**Operation and Maintenance** increased $17 million due primarily to a net $26 million increase in clause and renewable related expenditures. This increase was partially offset by a $9 million reduction in seasonal storm costs.

**Depreciation and Amortization** increased $22 million due primarily to a $17 million increase in depreciation related to additional plant placed into service, an increase of $3 million in the amortization of Regulatory Assets and a $2 million increase due to revised depreciation rates effective November 2018.

**Non-Operating Pension and OPEB Credits (Costs)** reflect an increase of $15 million in credits due to a $26 million decrease in the amortization of the prior service cost, partially offset by an $8 million reduction in the long-term expected return on plan assets, a $2 million increase in the amortization of the net unrecognized loss and a $1 million increase in interest cost.

**Interest Expense** increased $6 million due primarily related to net debt issuances in May and September 2018.

**Income Tax Expense** decreased $92 million due primarily to the flowback of excess deferred income tax liabilities and tax repair-related accumulated deferred income taxes.

### Power

|  | Three Months Ended March 31, 2019 Millions | 2018 | Increase/ (Decrease) 2019 vs. 2018 Millions% |  |
| --- | ---: | ---: | ---: | ---: |
| Operating Revenues | $1,416 | $1,403 | $13 | 1 |
| Energy Costs | 786 | 746 | 40 | 5 |
| Operation and Maintenance | 235 | 246 | (11) | (4) |
| Depreciation and Amortization | 94 | 82 | 12 | 15 |
| Income from Equity Method Investments | 2 | 2 | — | — |
| Net Gains (Losses) on Trust Investments | 126 | (22) | 148 | N/A |
| Other Income (Deductions) | 13 | 11 | 2 | 18 |
| Non-Operating Pension and OPEB Credits (Costs) | 3 | 4 | (1) | (25) |
| Interest Expense | 25 | 7 | 18 | N/A |
| Income Tax Expense (Benefit) | 124 | 83 | 41 | 49 |

### Three Months Ended March 31, 2019 as Compared to 2018

**Operating Revenues** increased $13 million due primarily to changes in generation and gas supply revenues.

***Gas Supply Revenues*** increased $37 million due primarily to

- an increase of $52 million in sales under the BGSS contract, of which $30 million was due to higher average sales prices and $22 million to an increase in sales volumes during the 2019 winter heating season,
- partially offset by a decrease of $18 million related to sales to third parties, of which $14 million was due to lower average sales prices and $4 million to lower volumes sold.

***Generation Revenues*** decreased $24 million due primarily to

- a net decrease of $44 million due to lower MTM gains in 2019 as compared to 2018. Of this amount, a $53 million decrease was due to gains on positions reclassified to realized upon settlement, partially offset by a $9 million increase from changes in forward prices this year as compared to last year, and
- a net decrease of $39 million in electricity sold under our BGS contracts due to lower volumes and lower prices,
- partially offset by a net increase of $48 million due primarily to higher volumes of electricity sold in the PJM region and under wholesale load contracts in the New England (NE) region, partially offset by lower average realized prices in the PJM region, and
- a net increase of $14 million in capacity revenues due primarily to an increase in auction prices in the PJM region.

### Operating Expenses

**Energy Costs** represent the cost of generation, which includes fuel costs for generation as well as purchased energy in the market, and gas purchases to meet Power’s obligation under its BGSS contract with PSE&G. Energy Costs increased $40 million due to

***Gas costs*** increased $41 million due mainly to

- an increase of $50 million related to sales under the BGSS contract, of which $33 million was due to an increase in the average cost of gas and $17 million to an increase in send-out volumes during the 2019 winter heating season,
- partially offset by a net decrease of $8 million related to sales to third parties due primarily to a decrease in volumes sold, partially offset by an increase in gas costs.

***Generation costs*** decreased $1 million due primarily to

- a decrease of $29 million due to MTM gains in 2019 as compared to losses in 2018 due to changes in forward prices, and
- a net decrease of $6 million from charges primarily related to additional retirement costs incurred in 2018 associated with early retirement of the Mercer and Hudson coal units,
- partially offset by higher fuel costs of $27 million, reflecting utilization of higher volumes of gas, primarily due to the commencement of commercial operations of Keys and Sewaren 7 fossil stations in mid-2018, coupled with higher prices of gas in the PJM region, partially offset by the utilization of lower volumes and gas prices in the New York region, lower volumes of oil in the PJM region, and lower coal prices in the PJM and NE regions, and
- a net increase of $7 million primarily due to higher volumes of energy purchased in the NE region to serve load obligations.

**Operation and Maintenance** decreased $11 million due primarily to

- a $14 million net decrease at our fossil plants, largely due to higher planned outage costs in 2018,
- partially offset by a net increase related to our nuclear plants, due primarily to planned outage costs incurred in 2019 for our 57%-owned Salem Unit 1 as compared to planned outage costs at our 100%-owned Hope Creek nuclear plant in 2018.

**Depreciation and Amortization** increased $12 million due primarily to Keys and Sewaren 7 fossil stations being placed into service.

**Net Gains (Losses) on Trust Investments** increased $148 million due primarily to a $133 million increase resulting from net unrealized gains in 2019 as compared to net unrealized losses in 2018 on equity investments in the NDT Fund and a $14 million increase in net realized gains on NDT Fund investments.

**Interest Expense** increased $18 million due primarily to $14 million in lower capitalized interest as a result of Keys and Sewaren 7 fossil stations being placed into service.

**Income Tax Expense (Benefit)** increased $41 million due primarily to higher pre-tax income in 2019, including income from the NDT qualified fund, which is subject to an additional trust tax.

### LIQUIDITY AND CAPITAL RESOURCES

The following discussion of our liquidity and capital resources is on a consolidated basis, noting the uses and contributions, where material, of our two direct major operating subsidiaries.

### Operating Cash Flows

We expect our operating cash flows combined with cash on hand and financing activities to be sufficient to fund capital expenditures and shareholder dividend payments.

For the three months ended March 31, 2019, our operating cash flow increased $78 million as compared to the same period in 2018. The net changes were primarily due to the net changes from our subsidiaries as discussed below.

### PSE&G

PSE&G’s operating cash flow decreased $57 million from $577 million to $520 million for the three months ended March 31, 2019, as compared to the same period in 2018, due primarily to a decrease of $143 million relating to accounts receivable and unbilled revenues due primarily to higher billings in 2019 reflecting increased prices and volumes and $96 million in increased vendor payments, offset by tax refunds in 2019, an increase of $75 million from a change in regulatory deferrals and higher earnings.

### Power

Power’s operating cash flow increased $184 million from $542 million to $726 million for the three months ended March 31, 2019, as compared to the same period in 2018, due to a decrease in margin deposit requirements of $165 million, a $56 million increase in fuels, materials and supplies and higher earnings, partially offset by a $59 million decrease from net collections of counterparty receivables.

### Short-Term Liquidity

PSEG meets its short-term liquidity requirements, as well as those of Power, primarily with cash and through the issuance of commercial paper. PSE&G maintains its own separate commercial paper program to meet its short-term liquidity requirements. Each commercial paper program is fully back-stopped by its own separate credit facilities.

We continually monitor our liquidity and seek to add capacity as needed to meet our liquidity requirements. Each of our credit facilities is restricted as to availability and use to the specific companies as listed below; however, if necessary, the PSEG facilities can also be used to support our subsidiaries’ liquidity needs.

Our total credit facilities and available liquidity as of March 31, 2019 were as follows:

| Company/Facility Total Facility | As of March 31, 2019 Millions | Usage | Available Liquidity |
| --- | ---: | ---: | ---: |
| PSEG | $1,500 | $802 | $698 |
| PSE&G | 600 | 380 | 220 |
| Power | 2,100 | 143 | 1,957 |
| **Total** | **$4,200** | **$1,325** | **$2,875** |

As of March 31, 2019, our credit facility capacity was in excess of our projected maximum liquidity requirements over our 12 month planning horizon. Our maximum liquidity requirements are based on stress scenarios that incorporate changes in commodity prices and the potential impact of Power losing its investment grade credit rating from S&P or Moody’s, which would represent a three level downgrade from its current S&P or Moody’s ratings. In the event of a deterioration of Power’s credit rating certain of Power’s agreements allow the counterparty to demand further performance assurance. The potential additional collateral that we would be required to post under these agreements if Power were to lose its investment grade credit rating was approximately $850 million and $857 million as of March 31, 2019 and December 31, 2018, respectively.

For additional information, see Item 1. Note 12. Debt and Credit Facilities.

### Long-Term Debt Financing

During the next twelve months, PSEG has $400 million of 1.60% Senior Notes maturing in November 2019. PSE&G has $250 million of 1.80% Medium Term Notes maturing in June 2019 and $250 million of 2.00% Medium Term Notes maturing in August 2019.

For additional information see Item 1. Note 12. Debt and Credit Facilities.

### Common Stock Dividends

On April 16, 2019, our Board of Directors declared a $0.47 dividend per share of common stock for the second quarter of 2019. This reflects an indicative annual dividend rate of $1.88 per share. We expect to continue to pay cash dividends on our common stock; however, the declaration and payment of future dividends to holders of our common stock will be at the discretion of the Board of Directors and will depend upon many factors, including our financial condition, earnings, capital requirements of our businesses, alternate investment opportunities, legal requirements, regulatory constraints, industry practice and other factors that the Board of Directors deems relevant. For additional information related to cash dividends on our common stock, see Item 1. Note 18. Earnings Per Share (EPS) and Dividends.

### Credit Ratings

If the rating agencies lower or withdraw our credit ratings, such revisions may adversely affect the market price of our securities and serve to materially increase our cost of capital and limit access to capital. Credit Ratings shown are for securities that we typically issue. Outlooks are shown for Corporate Credit Ratings (S&P) and Issuer Credit Ratings (Moody’s) and can be Stable, Negative, or Positive. There is no assurance that the ratings will continue for any given period of time or that they will not be revised by the rating agencies, if in their respective judgments, circumstances warrant. Each rating given by an agency should be evaluated independently of the other agencies’ ratings. The ratings should not be construed as an indication to buy, hold or sell any security.

|  | Moody’s (A) | S&P (B) |
| --- | --- | --- |
| **PSEG** |  |  |
| Outlook | **Stable** | **Stable** |
| Senior Notes | Baa1 | BBB |
| Commercial Paper | P2 | A2 |
| **PSE&G** |  |  |
| Outlook | **Stable** | **Stable** |
| Mortgage Bonds | Aa3 | A |
| Commercial Paper | P1 | A2 |
| **Power** |  |  |
| Outlook | **Stable** | **Stable** |
| Senior Notes | Baa1 | BBB+ |

(A) Moody’s ratings range from Aaa (highest) to C (lowest) for long-term securities and P1 (highest) to NP (lowest) for short-term securities.

(B) S&P ratings range from AAA (highest) to D (lowest) for long-term securities and A1 (highest) to D (lowest) for short-term securities.

### CAPITAL REQUIREMENTS

We expect that all of our capital requirements over the next three years will come from a combination of internally generated funds and external debt financing. There were no material changes to our projected capital expenditures as compared to amounts disclosed in our Form 10-K. See Executive Overview of 2019 and Future Outlook for additional information.

### PSE&G

During the three months ended March 31, 2019, PSE&G made capital expenditures of $630 million, primarily for T&D system reliability. This does not include expenditures for cost of removal, net of salvage, of $30 million, which are included in operating cash flows.

### Power

During the three months ended March 31, 2019, Power made capital expenditures of $156 million, excluding $11 million for nuclear fuel, primarily related to our BH5 and other generation projects.

### ACCOUNTING MATTERS

For information related to recent accounting matters, see Item 1. Note 2. Recent Accounting Standards.

## Market risk

As filed, 3,129 characters.

The risk inherent in our market-risk sensitive instruments and positions is the potential loss arising from adverse changes in commodity prices, equity security prices and interest rates as discussed in the Notes. It is our policy to use derivatives to manage risk consistent with business plans and prudent practices. We have a Risk Management Committee comprised of executive officers who utilize a risk oversight function to ensure compliance with our corporate policies and risk management practices.

Additionally, we are exposed to counterparty credit losses in the event of non-performance or non-payment. We have a credit management process, which is used to assess, monitor and mitigate counterparty exposure. In the event of non-performance or non-payment by a major counterparty, there may be a material adverse impact on our financial condition, results of operations or net cash flows.

### Commodity Contracts

The availability and price of energy-related commodities are subject to fluctuations from factors such as weather, environmental policies, changes in supply and demand, state and federal regulatory policies, market rules and other events. To reduce price risk caused by market fluctuations, we enter into supply contracts and derivative contracts, including forwards, futures, swaps and options with approved counterparties. These contracts, in conjunction with physical sales and other services, help reduce risk and optimize the value of owned electric generation capacity.

### Value-at-Risk (VaR) Models

VaR represents the potential losses, under normal market conditions, for instruments or portfolios due to changes in market factors, for a specified time period and confidence level. We estimate VaR across our commodity businesses.

MTM VaR consists of MTM derivatives that are economic hedges. The MTM VaR calculation does not include market risks associated with activities that are subject to accrual accounting, primarily our generating facilities and some load serving activities.

The VaR models used are variance/covariance models adjusted for the change of positions with 95% and 99.5% confidence levels and a one-day holding period for the MTM activities. The models assume no new positions throughout the holding periods; however, we actively manage our portfolio.

From January through March 2019, MTM VaR was relatively stable between a low of $6 million and a high of $35 million at the 95% confidence level. The range of VaR was narrower for the three months ended March 31, 2019 as compared with the year ended December 31, 2018.

| 95% Confidence Level, Loss could exceed VaR one day in 20 days | MTM VaR Three Months Ended March 31, 2019 Millions | Year Ended December 31, 2018 |
| --- | ---: | ---: |
| Period End | $8 | $21 |
| Average for the Period | $15 | $14 |
| High | $35 | $46 |
| Low | $6 | $6 |
| **99.5% Confidence Level, Loss could exceed VaR one day in 200 days** |  |  |
| Period End | $12 | $32 |
| Average for the Period | $23 | $22 |
| High | $54 | $72 |
| Low | $9 | $9 |

See Item 1. Note 13. Financial Risk Management Activities for a discussion of credit risk.

## Controls and procedures

As filed, 1,618 characters.

### Disclosure Controls and Procedures

### PSEG, PSE&G and Power

We have established and maintain disclosure controls and procedures as defined under Rule 13a-15(e) and 15d-15(e) promulgated under the Securities Exchange Act of 1934, as amended (the “Exchange Act”) that are designed to provide reasonable assurance that information required to be disclosed in the reports that are filed or submitted under the Exchange Act is recorded, processed, summarized and reported and is accumulated and communicated to the Chief Executive Officer (CEO) and Chief Financial Officer (CFO) of each respective company, as appropriate, by others within the entities to allow timely decisions regarding required disclosure. We have established a disclosure committee which includes several key management employees and which reports directly to the CFO and CEO of each of PSEG, PSE&G and Power. The committee monitors and evaluates the effectiveness of these disclosure controls and procedures. The CFO and CEO of each of PSEG, PSE&G and Power have evaluated the effectiveness of the disclosure controls and procedures and, based on this evaluation, have concluded that disclosure controls and procedures at each respective company were effective at a reasonable assurance level as of the end of the period covered by the report.

### Internal Controls

### PSEG, PSE&G and Power

There have been no changes in internal control over financial reporting that occurred during the first quarter of 2019 that have materially affected, or are reasonably likely to materially affect, each registrant’s internal control over financial reporting.

## Risk factors

As filed, 562 characters.

The discussion of our business and operations in this Quarterly Report on Form 10-Q should be read together with the risk factors contained in Part I, Item 1A of our Form 10-K, which describes various risks and uncertainties that could have a material adverse impact on our business, prospects, financial position, results of operations or cash flows and could cause results to differ materially from those expressed elsewhere in this report. There have been no material changes to the risk factors set forth in the above-referenced filings as of March 31, 2019.

Filed May 2, 2019.
Source: SEC EDGAR, the filing index for accession 0000788784-19-000009. Last ingested by Listed: Nov 6, 2026, 17:31 ET. No prices; not investment advice.