# Edison International: Form 10-Q for the period ended Sep 30, 2012

- Company: [Edison International](/companies/eix.md) (CIK 827052)
- Form: 10-Q
- Filed: 2012-11-01
- Accepted by EDGAR: Nov 1, 2012, 20:06 ET
- Period: 2012-09-30
- Accession: 0000827052-12-000096
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/827052/000082705212000096/eix2012q3.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/827052/000082705212000096/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2012-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2012-07-01 to 2012-09-30 | $4.07bn | us-gaap:Revenues |
| Revenue | 9 months, 2012-01-01 to 2012-09-30 | $9.80bn | us-gaap:Revenues |
| Operating income | 3 months, 2012-07-01 to 2012-09-30 | $636.0m | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2012-01-01 to 2012-09-30 | $1.29bn | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2012-07-01 to 2012-09-30 | $214.0m | us-gaap:InterestExpense |
| Interest expense | 9 months, 2012-01-01 to 2012-09-30 | $643.0m | us-gaap:InterestExpense |
| Income tax | 3 months, 2012-07-01 to 2012-09-30 | $181.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2012-01-01 to 2012-09-30 | $217.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2012-07-01 to 2012-09-30 | $190.0m | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2012-01-01 to 2012-09-30 | $357.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2012-07-01 to 2012-09-30 | $0.58 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2012-01-01 to 2012-09-30 | $1.09 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2012-07-01 to 2012-09-30 | $0.58 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2012-01-01 to 2012-09-30 | $1.09 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2012-07-01 to 2012-09-30 | 329,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2012-01-01 to 2012-09-30 | 328,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2012-01-01 to 2012-09-30 | $2.16bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2012-01-01 to 2012-09-30 | $3.37bn | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2012-01-01 to 2012-09-30 | $318.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2012-09-30 | $1.08bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2012-09-30 | $4.49bn | us-gaap:AssetsCurrent |
| Total assets | at 2012-09-30 | $50.55bn | us-gaap:Assets |
| Current liabilities | at 2012-09-30 | $4.27bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2012-09-30 | $38.52bn | us-gaap:Liabilities |
| Long-term debt | at 2012-09-30 | $13.71bn | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2012-09-30 | $565.0m | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | at 2012-09-30 | $429.0m | us-gaap:ShortTermBorrowings |
| Shareholders' equity | at 2012-09-30 | $12.02bn | us-gaap:StockholdersEquityIncludingPortionAttributableToNoncontrollingInterest |

## Management's discussion and analysis

As filed, 126,912 characters.

### FORWARD-LOOKING STATEMENTS

This quarterly report on Form 10-Q contains "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements reflect Edison International's current expectations and projections about future events based on Edison International's knowledge of present facts and circumstances and assumptions about future events and include any statement that does not directly relate to a historical or current fact. Other information distributed by Edison International that is incorporated in this report, or that refers to or incorporates this report, may also contain forward-looking statements. In this report and elsewhere, the words "expects," "believes," "anticipates," "estimates," "projects," "intends," "plans," "probable," "may," "will," "could," "would," "should," and variations of such words and similar expressions, or discussions of strategy or of plans, are intended to identify forward-looking statements. Such statements necessarily involve risks and uncertainties that could cause actual results to differ materially from those anticipated. Some of the risks, uncertainties and other important factors that could cause results to differ from those currently expected, or that otherwise could impact Edison International, include, but are not limited to:

- cost of capital and the ability of Edison International or its subsidiaries to borrow funds and access the capital markets on reasonable terms;
- environmental laws and regulations, at both state and federal levels, or changes in the application of those laws, that could require additional expenditures or otherwise affect the cost and manner of doing business, including compliance with CPS, CAIR and the MATS rule;
- ability of SCE to recover its costs in a timely manner from its customers through regulated rates;
- decisions and other actions by the CPUC, the FERC and other regulatory authorities and delays in regulatory actions;
- possible customer bypass or departure due to technological advancements or cumulative rate impacts that make self-generation or use of alternative energy sources economically viable;
- risks inherent in the construction of transmission and distribution infrastructure replacement and expansion projects, including those related to project site identification, public opposition, environmental mitigation, construction, permitting, power curtailment costs (payments due under power contracts in the event there is insufficient transmission to enable the acceptance of power delivery), and governmental approvals;
- risks associated with the operation of transmission and distribution assets and nuclear and other power generating facilities including: nuclear fuel storage issues, public safety issues, failure, availability, efficiency, output, cost of repairs and retrofits of equipment and availability and cost of spare parts;
- risk that Units 2 and/or Unit 3 at San Onofre may not recommence operations or may require extensive repairs or replacement of the steam generators; with the cost of the related outcome not being recoverable from SCE's supplier, insurance coverage or through regulatory processes;
- ability of EME to meet its liquidity requirements, restructure its debt obligations and stabilize its capital structure during periods of operating losses and capital spending programs;
- completion of the transactions for the divestiture of Homer City's leasehold interest and related assets and liabilities pursuant to the terms of the Homer City MTA between Homer City and GECC, and the timing and structure of such transactions;
- cost and availability of electricity, including the ability to procure sufficient resources to meet expected customer needs to replace power that would have been provided by San Onofre but for the current outage or in the event of other power plant outages or significant counterparty defaults under power-purchase agreements;
- changes in the fair value of investments and other assets;
- changes in interest rates and rates of inflation, including those rates which may be adjusted by public utility regulators;
- governmental, statutory, regulatory or administrative changes or initiatives affecting the electricity industry, including the market structure rules applicable to each market and price mitigation strategies adopted by Independent System Operators and Regional Transmission Organizations;
- availability and creditworthiness of counterparties and the resulting effects on liquidity in the power and fuel markets and/or the ability of counterparties to pay amounts owed in excess of collateral provided in support of their obligations;
- cost and availability of labor, equipment and materials;
- ability to obtain sufficient insurance, including insurance relating to SCE's nuclear facilities and wildfire-related liability, and to recover the costs of such insurance or in the absence of insurance the ability to recover uninsured losses;
- effects of legal proceedings, changes in or interpretations of tax laws, rates or policies;
- potential for penalties or disallowances caused by non-compliance with applicable laws and regulations;
- cost and availability of coal, natural gas, fuel oil, and nuclear fuel, and related transportation to the extent not recovered through regulated rate cost escalation provisions or balancing accounts;
- cost and availability of emission credits or allowances for emission credits;
- transmission congestion in and to each market area and the resulting differences in prices between delivery points;
- ability to provide sufficient collateral in support of hedging activities and power and fuel purchased;
- risk that competing transmission systems will be built by merchant transmission providers in SCE's service area; and
- weather conditions and natural disasters.

Additional information about risks and uncertainties, including more detail about the factors described above, is contained throughout this MD&A and in Edison International's 2011 Form 10-K, including the "Risk Factors" section in Part I, Item 1A. Readers are urged to read this entire report, including the information incorporated by reference, as well as the 2011 Form 10-K, and carefully consider the risks, uncertainties and other factors that affect Edison International's business. Forward-looking statements speak only as of the date they are made and Edison International is not obligated to publicly update or revise forward-looking statements. Readers should review future reports filed by Edison International with the U.S. Securities and Exchange Commission.

The MD&A for the three- and nine-month periods ended September 30, 2012 discusses material changes in the consolidated financial condition, results of operations and other developments of Edison International since December 31, 2011, and as compared to the three- and nine-month periods ended September 30, 2011. This discussion presumes that the reader has read or has access to Edison International's MD&A for the calendar year 2011 (the "year-ended 2011 MD&A"), which was included in the 2011 Form 10-K.

### EDISON INTERNATIONAL OVERVIEW

### Highlights of Operating Results

*(in millions)*

| Net Income (Loss) attributable to Edison International | Three months ended September 30, 2012 | 2011 | Change | Nine months ended September 30, 2012 | 2011 | Change |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| SCE | $363 | $406 | $(43) | $736 | $838 | $(102) |
| EMG | (137) | 33 | (170) | (331) | (17) | (314) |
| Edison International Parent and Other | (36) | (13) | (23) | (48) | (19) | (29) |
| Edison International Consolidated | 190 | 426 | (236) | 357 | 802 | (445) |
| Less: Non-Core Items |  |  |  |  |  |  |
| EMG – Gain on sale of lease interest | 31 | — | 31 | 31 | — | 31 |
| EME's discontinued operations | (76) | 15 | (91) | (129) | (3) | (126) |
| Total non-core items | (45) | 15 | (60) | (98) | (3) | (95) |
| Core Earnings (Losses) |  |  |  |  |  |  |
| SCE | 363 | 406 | (43) | 736 | 838 | (102) |
| EMG | (92) | 18 | (110) | (233) | (14) | (219) |
| Edison International Parent and Other | (36) | (13) | (23) | (48) | (19) | (29) |
| Edison International Consolidated | $235 | $411 | $(176) | $455 | $805 | $(350) |

Edison International's earnings are prepared in accordance with generally accepted accounting principles used in the United States. Management uses core earnings by principal operating subsidiary internally for financial planning and for analysis of performance. Core earnings (losses) by principal operating subsidiary are also used when communicating with analysts and investors regarding Edison International's earnings results to facilitate comparisons of the Company's performance from period to period. Core earnings (losses) are a non-GAAP financial measure and may not be comparable to those of other companies. Core earnings (losses) are defined as earnings attributable to Edison International shareholders less income or loss from discontinued operations and income or loss from significant discrete items that management does not consider representative of ongoing earnings, such as: exit activities, including lease terminations, sale of certain assets, early debt extinguishment costs and other activities that are no longer continuing; asset impairments and certain tax, regulatory or legal settlements or proceedings. EMG classified the results of Homer City, including the costs incurred in connection with the expected divestiture, as non-core for both the three and nine months ended 2012 and 2011 due to the plan described below to transition ownership of the leasehold interest to the owner-lessors.

SCE's 2012 core earnings decreased $43 million and $102 million for the quarter and year-to-date, respectively. Core earnings in both periods decreased primarily due to a delay in the 2012 CPUC General Rate Case decision as higher depreciation and net interest expenses are not being recovered in currently authorized revenue, as well as higher costs at San Onofre. SCE has incurred $48 million and $96 million of incremental steam generator inspection and repair costs related to outages at San Onofre for the quarter and year-to-date periods in 2012, respectively, and $30 million in severance costs. These costs were partially offset by other operations and maintenance cost reductions in both periods. The revenue requirement ultimately adopted by the CPUC will be retroactive to January 1, 2012.

EMG's 2012 core losses increased $110 million and $219 million for the quarter and year-to-date, respectively. The increase in core losses was primarily due to lower average realized energy and capacity prices and lower generation at the Midwest Generation plants, decreased earnings from natural gas-fired projects and lower income tax benefits.

Edison International Parent and Other core losses increased $23 million and $29 million for the quarter and year-to-date, respectively. The increase in core losses was primarily due to higher consolidated state income taxes.

Consolidated non-core items for 2012 and 2011 for Edison International included:

- $113 million pre-tax charge ($68 million after tax) associated with the divestiture by Homer City of substantially all of its remaining assets and certain specified liabilities. Pursuant to the Homer City MTA, beginning in the third quarter of 2012, Homer City met the definition of a discontinued operation and was classified separately in Edison International's consolidated statement of operations.
- In August 2012, Edison Capital sold its lease interest in Unit No. 2 of the Beaver Valley Nuclear Power Plant to a third party for $108 million and recorded a pre-tax gain of $65 million ($31 million after tax).

### Management Overview of SCE

### 2012 CPUC General Rate Case

As discussed in the year-ended 2011 MD&A, SCE's 2012 GRC application, which requested a 2012 base rate revenue requirement of $6.29 billion, has been under submission to the CPUC.

On October 19, 2012, the CPUC assigned administrative law judge issued a proposed decision, which, if adopted, would result in a 2012 base rate revenue requirement of $5.69 billion, a decrease of $601 million from SCE's requested revenue requirement, primarily related to decreases in operations and maintenance expenses with some plant-related capital reductions, including potential disallowances of recorded capital investments for specific projects. The proposed decision, if adopted, would result in an increase of approximately $400 million over currently authorized revenue. The proposed decision approves San Onofre costs subject to refund and reasonableness review and includes a requirement to track those costs in a memorandum account. See “—San Onofre” below for further information. The proposed decision also accepts SCE's requested rate-making treatment of tax repair deductions. See "Edison International Notes to Consolidated Financial Statements—Note 7. Income Taxes" for further discussion.

The proposed decision would allow a post-test year ratemaking methodology that escalates capital additions by 3.05% for 2013 and 2.93% for 2014. It would also allow operations and maintenance expense to be escalated for 2013 and 2014 through the use of various escalation factors for labor, non-labor and medical expenses. The methodology adopted in the proposed decision would result in a revenue requirement of $6.08 billion for 2013 and $6.43 billion for 2014.

SCE is currently recognizing revenue largely based on the 2011 authorized revenue requirement. The CPUC has authorized the establishment of a GRC memorandum account, which will make the 2012 revenue requirement ultimately adopted by the CPUC effective as of January 1, 2012.

SCE is required to file comments within 20 days of receiving the proposed decision. The final CPUC decision could result in material changes to the proposed decision. A final CPUC decision is expected by year end.

### 2013 Cost of Capital Application

In June 2012, the CPUC issued an order in the 2013 Cost of Capital proceeding consolidating SCE's 2013 application with the three other California investor-owned utilities' applications and splitting the proceeding into two phases. The first phase will address the 2013 ratemaking capital structure and cost of capital for the utilities and contemplates a final decision in December 2012. The second phase will consider whether the current multi-year mechanism should be continued or modified. A final decision for the second phase is expected in April 2013.

SCE's 2013 cost of capital application, which was filed in April 2012, requested a ratemaking capital structure of 43% long-term debt, 9% preferred equity and 48% common equity consistent with the current capital structure. In October 2012, SCE submitted an update to its requested cost of capital further reducing its current cost of capital as follows: cost of long-term debt from 6.22% to 5.49%, authorized cost of preferred equity from 6.01% to 5.79% and authorized return on common equity from 11.5% to 11.1%. The application also requested the continuation of the current multi-year mechanism, which would have retained the authorized capital structure through 2015 with annual adjustments of the cost components if certain thresholds are reached.

### San Onofre

#### Outage, Inspection and Repair Issues

As discussed in the 2011 Form 10-K, four replacement steam generators were installed at San Onofre Units 2 and 3 in 2010 and 2011, respectively. In the first quarter of 2012, a water leak suddenly occurred in one of the heat transfer tubes in San Onofre's Unit 3 steam generators. Unit 3 was safely taken off-line. At the time, San Onofre Unit 2 was off-line for a planned outage when areas of unexpected wear in some of its heat transfer tubes were found. Both Units have remained off-line for extensive inspections, testing and analysis of their steam generators. Each Unit will be restarted only when and if SCE determines that it is safe to do so and when start-up has been approved by the NRC pursuant to the terms of a Confirmatory Action Letter (“CAL”) issued by the NRC in March 2012. The CAL requires NRC permission to restart Unit 2 and Unit 3 and outlines actions SCE must complete before permission to restart either Unit may be sought. In October 2012, SCE submitted to the NRC a response to the CAL and restart plans for Unit 2 as described below.

Tube Leak and Repairs

The water leak in the Unit 3 steam generator was caused by excessive wear resulting from tube-to-tube contact in the area of the leak. During the inspection and testing of the Unit 3 steam generators, additional pressure tests of certain tubes were completed to determine the safety significance of the wear. Eight of the 129 tubes subjected to the additional tests failed the tests for structural integrity as a result of excessive wear, and the NRC was notified as required. The same areas were re-inspected in the Unit 2 steam generators using a more sensitive inspection method than had previously been employed, and similar wear from tube-to-tube contact was found on two tubes in one of the steam generators at wear levels below the detection capability of the initial inspection. Earlier tests performed on the Unit 2 steam generators during the planned outage additionally found levels of unexpected wear at points where some tubes were in contact with retainer bars of the tube support structure. Subsequent inspections on Unit 3 found similar tube-to-support structure wear.

As a result of these findings, SCE has plugged and removed from service all tubes showing excessive wear in each of the steam generators. In addition, SCE preventively plugged all tubes in contact with retainer bars or in the area of the tube bundles where tube-to-tube contact occurred. Each steam generator has over 9,700 heat transfer tubes and is designed to include sufficient tubes to accommodate a need to remove some from service for a variety of reasons, and the tubes that SCE has removed from service are within this margin.

A team of outside experts was assembled to assist SCE and Mitsubishi Heavy Industries, Inc. (“MHI”), the manufacturer of the steam generators, in the analysis of the causes of the tube-to-tube wear and potential remedial actions. As a result of their work, SCE understands that the tube-to-tube contact arises from excessive vibration of the tubes in certain areas of the steam generators. The excessive vibration that caused the tube-to-tube wear on Unit 3 resulted from a phenomenon called fluid elastic instability. This phenomenon arises from a combination of thermal hydraulic conditions (steam velocity and moisture content of the steam), and ineffectiveness of the tube supports in the areas where the vibration occurs. Unit 2 is susceptible to the same thermal hydraulic conditions as Unit 3, but the Unit 2 supports largely remained effective for the entire time that it operated as compared to Unit 3. This difference is likely the result of manufacturing differences between the pairs of steam generators in the two Units.

SCE's restart plans for Unit 2 and its response to the CAL are based on work done by engineering groups of three independent firms with expertise in steam generator design and manufacturing. Restart plans for only Unit 2 were submitted because of the extensive tube-to-tube wear in Unit 3, which was not experienced in Unit 2 (in which only one point of tube-to-tube wear between two tubes was identified). Using different methodologies, each independent outside engineering group concluded that it would be safe to restart Unit 2 and operate at a reduced power level (70%) for approximately five months, followed by a mid-cycle scheduled outage. The power level is being reduced to avoid the steam velocity and moisture content conditions that cause fluid elastic instability. The five month operating period is less than half the time Unit 3 operated and was validated by the independent experts as providing a safety margin to provide assurance of safe operation. In addition to these requirements, the restart plan covers repairs, corrective actions and operating parameters and also includes additional monitoring, detection and response activities.

Inasmuch as Unit 3 had much more tube-to-tube wear than Unit 2, it is not clear at this time whether Unit 3 will be able to restart without extensive additional repairs and corrective actions. Unit 3 will not restart this year and it is uncertain when or whether a restart plan will be submitted. The Unit 3 reactor is de-fueled and SCE is placing appropriate systems in a lay-up condition while analysis and testing continue. SCE is also engaged in the analysis of what repairs, if any, could be undertaken to restore the steam generators on both Units to their originally specified capabilities safely, but it has not determined what those repairs might be or whether the generators will need to be replaced for the Units to operate at their prior output levels. Each Unit will only be restarted when any necessary repairs and appropriate mitigation plans for that Unit are completed in accordance with the CAL, and the NRC and SCE are satisfied that it is safe to do so.

NRC Processes

The timing of restart of the Units will also be affected by the nature of and schedule for regulatory processes required by the NRC. There is no set or predetermined time period for approval of Unit 2's proposed restart, and, accordingly, there can be no assurance about the length of time the NRC may take to review SCE's request to restart or whether any such request would be granted in whole or in part.

The NRC will conduct one or more on-site inspections to verify that SCE has performed the actions described in the CAL response and will hold public meetings to discuss the CAL response as well as the results of the on-site inspections. There is no timeline for the NRC's review of the CAL response. It is also possible that one or more amendments to the NRC operating license for San Onofre might be required (whether or not as a prerequisite to return a Unit to safe operation). The NRC could also choose to impose additional processes and assessments that could result in significant costs or additional delay.

Following the failure of pressure tests on the eight tubes in Unit 3, the NRC launched an Augmented Inspection Team (“AIT”) to assess the tube failures and their causes, SCE's operation of the Units, and SCE's oversight of the design, fabrication, shipping, and construction process. In July 2012, the NRC issued a report providing the results of the AIT inspection. That report concluded that the replacement steam generators' design and configuration did not provide the necessary margin to prevent fluid elastic instability and that these deficiencies appear to be related to MHI's computer code used to model thermal hydraulic conditions in the steam generators. The report further stated that SCE was adequately pursuing the causes of the unexpected steam generator tube-to-tube degradation. The AIT report also identified a number of as-yet unresolved issues that are continuing to be examined. The unresolved issues include further evaluation of manufacturing differences between Unit 2 and Unit 3, with particular focus on the control of critical dimensions affecting the clearances between tubes and tube supports. The NRC will conduct subsequent inspections or reviews to determine what, if any, regulatory actions result from these unresolved items. Should the NRC find a deficiency in SCE's performance, SCE could be subject to additional NRC actions, and the findings could be taken into consideration in the CPUC regulatory proceedings described below.

CPUC Review

Under California Public Utilities Code Section 455.5, SCE is required to notify the CPUC if either of the San Onofre Units has been out of service for nine consecutive months (not including preplanned outages). SCE will provide such notice to the CPUC on November 1, 2012 for Unit 3 and expects to do so by December 6, 2012 for Unit 2. The CPUC is required within 45 days of SCE's notice for a particular Unit to initiate an investigation to determine whether to remove from customer rates some or the entire revenue requirement associated with the portion of the facility that is out of service. From the initiation date of the investigation, such rates are collected subject to refund. Under Section 455.5 any determination to adjust rates is made after hearings are conducted in connection with the utility's next general rate case. If, after investigation and hearings, the costs associated with a Unit are disallowed recovery because it is out of service and the Unit is subsequently returned to service, rates may be readjusted to reflect that return to service after 100 continuous hours of operation.

In October 2012, in advance of SCE's required notification under Section 455.5, the CPUC issued an order instituting investigation that will consolidate all San Onofre issues in related regulatory proceedings and consider appropriate cost recovery for all San Onofre costs, including among other costs, the cost of the steam generator replacement project, market power costs, capital and operations and maintenance costs, and seismic study costs. The order requires that all San Onofre-related costs incurred on and after January 1, 2012 be tracked in a memorandum account and, to the extent included in rates, collected subject to refund. The order also states that the CPUC will determine whether to order the immediate removal, effective as of the date of the order, of all costs related to San Onofre from SCE's rates, with placement of those costs in a deferred debit account pending the return of one or both Units to useful service, or other possible action. SCE will file its response to the order by November 26, 2012. SCE must also file testimony by December 10, 2012 detailing proposed rate adjustments due to the outages, including the amount of San Onofre costs in current rates, the amount to be removed, if any, the effective date, and related information. A pre-hearing conference will be scheduled early in 2013 after the issuance of a Scoping Memo by the Assigned Commissioner.

In parallel with the order instituting investigation, the 2012 GRC proposed decision would, if adopted, require SCE to track San Onofre-related costs in a memorandum account subject to refund, beginning January 1, 2012. SCE would be required by January 30, 2013 to file an application for reasonableness review of these costs and the proposed decision would allow that application to be consolidated with other proceedings. The 2012 GRC proposed decision also approves expenditures incurred through 2011 for the high pressure turbine project, but disallows recovery for post-2011 expenditures associated with the project and directs SCE to record those costs in either the memorandum account or seek future rate recovery in the next GRC. SCE anticipates that the inter-relationship between the Section 455.5 process and the issues to be reviewed in the investigation or pursuant to a final decision in the GRC will be addressed by the CPUC as it continues to develop the scope of the issues to be consolidated within the investigation.

In addition to the amounts for inspection and repair and market power costs discussed below, SCE has collected through customer rates an estimated $625 million of revenue through third quarter 2012 (based on current authorized revenue requirements) associated with the plant. SCE's total 2012 San Onofre annual revenue requirement, including the 2012 GRC proposed decision, is approximately $820 million, made up of $170 million in refueling outage, nuclear fuel and decommissioning costs and $650 million for its direct operating and maintenance costs, depreciation and return on its investment in San Onofre Unit 2, Unit 3 and related common plant. At September 30, 2012, SCE's rate base and net investment associated with San Onofre were as set forth in the following table:

*(in millions)*

| Net investment | Unit 2 | Unit 3 | Common Plant | Total |
| --- | ---: | ---: | ---: | ---: |
| Net plant in service | $593 | $418 | $261 | $1,272 |
| Materials and supplies | — | — | 99 | 99 |
| Construction work in progress | 77 | 141 | 76 | 294 |
| Nuclear fuel | 153 | 212 | 101 | 466 |
| Net investment | $823 | $771 | $537 | $2,131 |
| Rate base |  |  |  |  |
| Net plant in service | $593 | $418 | $261 | $1,272 |
| Materials and supplies | — | — | 99 | 99 |
| Accumulated deferred income taxes | (95) | (45) | (66) | (206) |
| Amounts in rate base | $498 | $373 | $294 | $1,165 |

In 2005, the CPUC authorized expenditures of approximately $525 million ($665 million after adjustment for inflation) for SCE's 78.21% share of San Onofre to purchase and install the four new steam generators in Units 2 and 3 and remove and dispose of their predecessors. SCE has spent $594 million through September 30, 2012 on the steam generator replacement project, including $95 million reflected in construction work in progress primarily related to the disposal of the replaced steam generators. Those expenditures remain subject to CPUC reasonableness review. Final costs for the project will not be known until after disposal of the original steam generators is completed.

As a result of outages associated with the steam generator inspection and repair, electric power and capacity normally provided by San Onofre are being purchased in the market by SCE (commencing on February 1 for Unit 3 and March 5 for Unit 2). Market costs through September 30, 2012 were approximately $221 million, net of avoided nuclear fuel costs, and are recoverable through the ERRA balancing account subject to CPUC reasonableness review. Because of the uncertainties associated with when and at what output levels the Units will or may be returned to service, total potential market power costs cannot be estimated at this time.

Through September 2012, SCE's share of incremental inspection and repair costs totaled $96 million for both Units. At September 30, 2012, the repairs to restart Unit 2 at the reduced power levels described above have been substantially completed. The costs for Unit 2 may increase following NRC review under the CAL and any new developments that may result from further analysis, testing and inspection, and there is no assurance that start-up of Unit 2 will occur as described above. Total incremental repair costs associated with returning Unit 3 to service, and returning both Units to service at originally specified capabilities safely, remain uncertain.

Contractual Matters

The steam generators were designed and supplied by MHI and are warranted for an initial period of 20 years from acceptance. MHI is contractually obligated to repair or replace defective items and to pay specified damages for certain repairs. SCE's purchase contract with MHI states that MHI's liability under the purchase agreement is limited to $138 million and excludes consequential damages, defined to include "the cost of replacement power." Such limitations in the contract are subject to applicable exceptions. In September 2012, SCE submitted an invoice to MHI for costs paid through June 30, 2012 in the amount of $45 million for both SCE's and the other co-owners' share of steam generator repair costs. SCE expects to continue to invoice MHI for costs incurred. No amounts have been recognized in the financial statements as of September 30, 2012.

San Onofre carries both property damage and outage insurance issued by Nuclear Electric Insurance Limited (“NEIL”) and has placed NEIL on notice of potential claims for loss recovery. The property damage policy (including excess coverage) provides insurance for certain costs and expenses resulting from “Accidental Property Damage” with a $2.5 million deductible and a $2.75 billion limit of liability. After a twelve week deductible period, the outage policy provides insurance for an outage caused by “Accidental Property Damage” of up to $3.5 million per week for each Unit (or $2.8 million per Unit per week if both Units are out because of the same "Accident"), with a $490 million limit for each Unit ($392 million each if both Units are out because of the same "Accident"). The NEIL policies have a number of exclusions and limitations that may reduce or eliminate coverage. For instance, coverage may be reduced or excluded if it is determined that the outage resulted from any condition which develops, progresses or changes over time, or from wear and tear. Further, costs to "make good" faulty workmanship or design and amounts collectible from third parties are excluded from the property damage policy. Proof of loss must be submitted within 12 months of the Accidental Property Damage under the property damage insurance and within 12 months of the end of the outage under the outage policy. In October 2012, SCE filed separate proofs of loss for Unit 2 and Unit 3 under the outage policy. Pursuant to these proofs of loss SCE is seeking the weekly indemnity amounts provided under the policy for each Unit. Because the outage is ongoing, SCE will supplement these proofs of loss in the future. No amounts have been recognized in SCE's financial statements, pending further actions by NEIL. To the extent any costs are recovered under the outage policy, SCE expects to refund those amounts to ratepayers through the ERRA balancing account. For further information, see "Edison International Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies."

SCE will pursue recoveries arising from available agreements, but there is no assurance that SCE will recover all of its applicable costs pursuant to these arrangements.

CAISO Summer Readiness Planning

In addition to providing up to 2,200 MW of electric power, San Onofre also provides significant reliability support to the electric grid, including support for grid voltage and stability. SCE continues to work with the CAISO to maintain grid reliability for summer 2013 and beyond while the San Onofre Units are out of service. SCE is supporting CAISO in its negotiations to obtain local grid voltage support. SCE has also accelerated certain transmission projects and will expand its demand response programs to help maintain grid reliability. The majority of these efforts are projects that are already included in SCE's capital expenditure plan, but their timing has been accelerated. In addition, SCE has proposed to the CAISO projects such as transmission line reconfiguration and installation of equipment to support voltage and stability. The projects, if approved could result in additional capital expenditures from $100 million to $125 million over the period 2013 – 2015.

#### Workforce Reduction

In August 2012, SCE announced plans for downsizing to bring the San Onofre organization and cost structure in line with industry peers. SCE plans to reduce the San Onofre workforce by 730 employees to 1,500 employees beginning in the fourth quarter of 2012 and continuing in 2013. At September 30, 2012, SCE had recorded $30 million in estimated cash severance costs (SCE's share) related to the non-represented employee workforce reduction.

### Capital Program

During the first nine months of 2012, SCE's capital investment program focused on maintaining reliability and expanding the capability of SCE's transmission and distribution system; upgrading and constructing new transmission lines and substations; installing digital meters; and replacing generation asset equipment. Total capital expenditures (including accruals) were $2.6 billion during the first nine months of 2012 compared to $2.5 billion during the same period in 2011. SCE expects that 2012 capital expenditures will be below the lower end of the previously projected $4.4 billion to $5.0 billion range due to the delay in the GRC decision, the delay related to the Tehachapi Project and outages at San Onofre. However, SCE continues to project that 2012 – 2014 total capital expenditures will be in the range of $11.8 billion to $13.2 billion. Actual capital spending will be affected by: changes in regulatory, environmental and engineering design requirements; permitting and project delays; cost and availability of labor, equipment and materials; outcome of the San Onofre mitigation plans; and other factors.

### Management Overview of EMG

### EME Liquidity and Restructuring Activities

EME's operating loss increased significantly in the nine months ended September 30, 2012 compared to the same period in 2011, primarily due to lower capacity and average realized energy prices, reduced generation and higher fuel prices at the Midwest Generation plants. The abundance of low-priced natural gas has continued to result in increased competition from natural gas-fired generating units in the markets in which Midwest Generation operates, and generation has been correspondingly affected. In addition, effective January 1, 2012, a favorable long-term rail contract that supplied Midwest Generation's fleet expired and was replaced by a higher priced contract.

At September 30, 2012, EME, and its subsidiaries without contractual dividend restrictions, had corporate cash and cash equivalents of $627 million, which includes Midwest Generation's cash and cash equivalents of $142 million. At September 30, 2012, EME had $3.7 billion of unsecured notes outstanding, $500 million of which mature in June 2013.

EME continues to experience operating losses due to low realized energy and capacity prices, high fuel costs and low generation at the Midwest Generation plants. Forward market prices indicate that these trends are expected to continue for a number of years. As a result, EME expects that it will incur further reductions in cash flow and losses in the current year and in subsequent years. A continuation of these adverse trends coupled with pending debt maturities and the need to retrofit its Midwest Generation plants to comply with governmental regulations will exhaust EME's liquidity. Consequently, EME has been considering all options available to it, including potential sales of assets, restructuring, reorganization of its capital structure, or conservation of cash that would be applied otherwise to the payment of obligations.

In June 2012, EME entered into non-disclosure and engagement agreements with advisors representing holders of a majority in principal amount of its unsecured bonds for the purpose of engaging in discussions with such advisors and Edison International regarding EME's financial condition. In October 2012, EME and Edison International entered into non-disclosure agreements with certain of the clients of such advisors to facilitate further discussions. Discussions with the bondholders' advisors have been ongoing. In addition, EME and Midwest Generation have entered into a non-disclosure agreement with an advisor representing a majority in principal amount of Midwest Generation's senior lease obligation bonds.

Based on current projections, EME is not expected to have sufficient liquidity to repay the $500 million debt obligation due in June 2013. On November 15, 2012, $97 million of interest payments are due on unsecured EME bonds maturing in 2017, 2019 and 2027, and there is no assurance payment will be made. EME's unsecured bonds generally provide for a 30-day grace period for interest payments. EME's failure to pay indebtedness under its unsecured bonds will likely result in EME's filing for protection under Chapter 11 of the U.S. Bankruptcy Code, which would trigger cross defaults under EME's guarantee of the lease obligations of Midwest Generation, as well as Midwest Generation's own obligations under the lease and under instruments governing the senior lease obligation bonds, and which could potentially give rise to counterparty rights and remedies under other documents.

Bankruptcy proceedings could lead to a change of control of EME, which would, among other things, result in the termination of EME's tax-allocation agreement. At September 30, 2012, EME had recognized $635 million of net tax benefits based on continued ownership by Edison International and inclusion of EME in the consolidated income tax returns of Edison International and its subsidiaries. If realization is unlikely, EME would record a valuation allowance to reduce the carrying value of these assets and record a material charge against earnings. The termination of the tax-allocation agreement could adversely affect EME's long-term liquidity because realization of the value of tax benefits generated by EME could be deferred until such time that EME, or a subsequent owner of EME, had the ability to utilize such benefits. There is no assurance as to when, or whether, this might occur.

Under the applicable accounting standards, Edison International would no longer consolidate EME for financial reporting purposes if it filed for bankruptcy under Chapter 11 of the U.S. Bankruptcy Code, as Edison International would no longer have a controlling financial interest for accounting purposes. In order to deconsolidate EME for financial reporting purposes, the carrying values of the assets and liabilities of EME would be removed from Edison International's consolidated balance sheets as of the bankruptcy filing date and the investment in EME would be recorded at its estimated fair value. Any loss would be recognized in an amount equal to the excess of the book value of Edison International's investment in EME over the fair value of such investment. At September 30, 2012, the book value of Edison International's investment in EME was $1.24 billion. Any amounts recorded as part of accumulated other comprehensive loss related to EME would be recognized as a loss upon deconsolidation. At September 30, 2012, the amount recorded as accumulated other comprehensive loss related to EME was $128 million. In addition, Edison International would record any liabilities due to EME and certain liabilities that are joint and several with EME, including liabilities for uncertain tax positions taken in consolidated or combined tax returns of Edison International that are otherwise not resolved through the tax-allocation agreement and certain retirement plans. Under current regulations, during bankruptcy, EME would continue to be consolidated with Edison International for federal income tax purposes until a change in ownership occurred.

The accompanying consolidated financial statements have been prepared assuming that EME will continue as a going concern. Financial statements prepared on this basis assume the realization of assets and the satisfaction of liabilities in the normal course of business for the 12-month period following the date of these financial statements. There is no assurance that EME will be able to continue as a going concern.

### Midwest Generation's Dependence on EME

Midwest Generation is largely dependent on EME to fund cash flow deficits and environmental retrofits. EME has no obligation to make capital contributions to Midwest Generation and may be unable to do so. Furthermore, Midwest Generation had $1.323 billion of notes receivable from EME at September 30, 2012 with payments used to meet its rent obligations under the Powerton and Joliet sale-leaseback agreements. If EME is unable to make payments on its notes,

Midwest Generation may in turn be unable to make rent payments under the Powerton-Joliet leases. Failure to pay rent would be an event of default under the Powerton-Joliet leases that could result in termination of the leases, loss of control over the use of the Powerton and Joliet Stations and a claim for termination value under the lease agreements. Accordingly, if Midwest Generation is unable to obtain financial support from EME or other sources, Midwest Generation may need to file for protection under Chapter 11 of the U.S. Bankruptcy Code. A bankruptcy of either EME or Midwest Generation would also be an event of default under the Powerton-Joliet leases.

### Midwest Generation Environmental Compliance Plans and Costs

During the third quarter of 2012, Midwest Generation continued to develop and implement a compliance program that includes the operation of ACI systems for mercury removal, upgrades to particulate removal systems and the use of dry sorbent injection, combined with the use of low sulfur PRB coal, to meet emissions limits for criteria pollutants, such as NOx and SO2 as well as for hazardous air pollutants, such as mercury, acid gas and non-mercury metals.

Apart from the Fisk and Crawford Stations, which ceased operations in September 2012, decisions whether or not to proceed with retrofitting of any particular remaining units to comply with CPS requirements for SO2 emissions, including those that have received permits, are subject to a number of factors, such as market conditions, regulatory and legislative developments, liquidity and forecasted commodity prices and capital and operating costs applicable at the time decisions are required or made. Midwest Generation may also elect to shut down units, instead of installing controls, to be in compliance with the CPS. Final decisions on whether to install controls, to install particular kinds of controls, and to actually expend capital or continue with the expenditure of capital will be made as required, subject to the requirements of the CPS and other applicable regulations. Units that are not retrofitted may continue to operate for as long as regulations and law allow.

Based on work to date, Midwest Generation estimates the remaining cost of retrofitting Powerton Units 5 and 6, Joliet Units 7 and 8 and Will County Units 3 and 4, using dry scrubbing with sodium-based sorbents and upgrading particulate removal systems, to be approximately $619 million at September 30, 2012. It is less likely that retrofits will be made to Joliet Unit 6 and the Waukegan Station. During the third quarter of 2012, the Pollution Control Board granted Midwest Generation's request to extend Waukegan Unit 7's unit specific retrofit requirements from December 31, 2013 to December 31, 2014. The estimated cost of retrofitting Joliet Unit 6, if made, would be approximately $75 million, while the estimated cost of retrofitting the Waukegan Station, if made, would be approximately $160 million. Final decisions to shut down units will be made in light of the timing requirements under the CPS and other applicable environmental regulations, based on the economic projections of those retrofits, on a unit-by-unit basis, at the time the decision is made. For further discussion related to the impairment policy on Midwest Generation's unit of account, refer to "Critical Accounting Estimates and Policies—Impairment of Long-Lived Assets" in the year-ended 2011 MD&A.

### Homer City Lease

On September 21, 2012, Homer City and an affiliate of GECC entered into the Homer City MTA for the divestiture by Homer City of substantially all of its remaining assets and certain specified liabilities. On October 3, 2012, GECC entered into a Plan Support Agreement (the PSA) with the holders of approximately 76% of the outstanding principal amount of the secured lease obligation bonds issued by Homer City Funding, LLC as part of the original sale-leaseback transaction. Under the PSA, the parties committed to support and implement a reorganization plan of Homer City Funding, LLC and to solicit votes on a prepackaged plan of reorganization under Chapter 11 of the U.S. Bankruptcy Code. On October 5, 2012, GECC commenced the solicitation. Homer City Funding, LLC is an affiliate of GECC and not related to Homer City or any other EME affiliate. In addition, Homer City received a forbearance of the $47 million senior rent payment that had been due October 1, 2012 and was granted a waiver of the $65 million equity rent payment that had been due April 1, 2012.

Completion of the Homer City MTA is subject to the satisfaction of a number of closing conditions, including the successful restructuring and reorganization of Homer City Funding, LLC and receipt of the regulatory approvals required for the transfer of the Homer City plant to GECC. If an agreement to modify the terms of the bonds is not approved and consummated or if other closing conditions of the Homer City MTA are not met, Homer City may become the subject of bankruptcy proceedings.

Beginning in the third quarter of 2012, Homer City met the definition of a discontinued operation and EME recorded a $113 million charge ($68 million after tax) to write down assets held for sale to net realizable value during the third quarter of 2012.

For further discussion, see "Edison International Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—Interim Financial Statements," "—Note 8. Compensation and Benefit Plans," and "—Note 18. Discontinued Operations."

### Environmental Developments

For a discussion of environmental developments, see "Edison International Notes to Consolidated Financial Statements—Note 10. Environmental Developments."

### SOUTHERN CALIFORNIA EDISON COMPANY

### RESULTS OF OPERATIONS

SCE's results of operations are derived mainly through two sources:

- Utility earning activities – representing revenue authorized by the CPUC and FERC which is intended to provide SCE a reasonable opportunity to recover its costs and earn a return on its net investment in generation, transmission and distribution assets. The annual revenue requirements are comprised of authorized operation and maintenance costs, depreciation, taxes and a return consistent with the capital structure. Also, included in utility earnings activities are revenues or penalties related to incentive mechanisms, other operating revenue, and regulatory charges or disallowances, if any.
- Utility cost-recovery activities – representing CPUC- and FERC-authorized balancing accounts which allow for recovery of specific project or program costs, subject to reasonableness review or compliance with upfront standards.

The following tables summarize SCE's results of operations for the periods indicated. The presentation below separately identifies utility earning activities and utility cost-recovery activities. Beginning in 2012, SCE classified revenues and costs related to programs that provide for recovery of actual costs plus a return on capital as utility earning activities. Previously, SCE classified the recovery of actual costs incurred under these programs as utility cost-recovery activities. The tables presented below reflect a reclassification of the revenues and costs for 2011 consistent with the presentation in 2012. The reclassification of revenues and costs had no impact on earnings.

During the first nine months of 2012, pending the outcome of the 2012 GRC, SCE recognized GRC-related revenue based on the 2011 authorized revenue requirement included in customer rates. This has resulted in a decrease in net income as higher depreciation and net interest expenses are not being recovered in currently authorized revenue. A GRC memorandum account has been established for SCE, which will make the 2012 revenue requirement ultimately adopted by the CPUC effective as of January 1, 2012. Recognition of the revenue for the period January 1, 2012 through the date of a final decision, as well as any delays in certain expenditures and changes in authorized treatment of specific costs, will impact the timing of earnings in 2012 (see "Edison International Overview—Management Overview of SCE—2012 CPUC General Rate Case" for further discussion).

### Three Months Ended September 30, 2012 versus September 30, 2011

*(in millions)*

|  | Three months ended September 30, 2012 Utility Earning Activities | Utility Cost- Recovery Activities | Total Consolidated | Three months ended September 30, 2011 Utility Earning Activities | Utility Cost- Recovery Activities | Total Consolidated |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| **Operating revenue** | $1,754 | $1,977 | $3,731 | $1,759 | $1,627 | $3,386 |
| Fuel and purchased power | — | 1,694 | 1,694 | — | 1,374 | 1,374 |
| Operations and maintenance | 623 | 283 | 906 | 566 | 253 | 819 |
| Depreciation decommissioning and amortization | 399 | — | 399 | 358 | — | 358 |
| Property taxes and other | 73 | — | 73 | 71 | — | 71 |
| **Total operating expenses** | 1,095 | 1,977 | 3,072 | 995 | 1,627 | 2,622 |
| **Operating income** | 659 | — | 659 | 764 | — | 764 |
| Net interest expense and other | (95) | — | (95) | (98) | — | (98) |
| **Income before income taxes** | 564 | — | 564 | 666 | — | 666 |
| Income tax expense | 176 | — | 176 | 245 | — | 245 |
| **Net income** | 388 | — | 388 | 421 | — | 421 |
| Dividends on preferred and preference stock | 25 | — | 25 | 15 | — | 15 |
| Net income available for common stock | $363 | $— | $363 | $406 | $— | $406 |
| Core Earnings1 |  |  | $363 |  |  | $406 |
| Non-Core Earnings |  |  | — |  |  | — |
| Total SCE GAAP Earnings |  |  | $363 |  |  | $406 |

1 See use of Non-GAAP financial measures in "Edison International Overview—Highlights of Operating Results."

### Utility Earning Activities

Utility earning activities were primarily affected by the following:

- Higher operations and maintenance expense of $57 million was primarily due to increased costs at San Onofre, including $48 million related to the steam generator inspection and repair at San Onofre and $30 million of estimated cash severance costs related to the planned San Onofre reduction in workforce; partially offset by lower operations and maintenance expenses. These increases were partially offset by EdisonSmartConnect® benefits realized and other cost savings and timing of expenses.
- Higher depreciation, decommissioning and amortization expense of $41 million was primarily related to increased generation, transmission and distribution investments, including capitalized software costs.
- Lower income taxes due to lower pre-tax income. See "—Income Taxes" below for more information.
- Higher preferred and preference stock dividends of $10 million related to new issuances in 2012.

### Utility Cost-Recovery Activities

Utility cost-recovery activities were primarily affected by the following:

- Higher fuel and purchased power expense of $320 million was primarily driven by the cost to replace CDWR contracts that expired in 2011, which were not previously recorded as an SCE cost but which were included as a separate component on customer bills (see "—Supplemental Operating Revenue Information" below) and $104 million of market costs net of lower nuclear fuel costs related to the outage at San Onofre in 2012 (see "Edison International Overview—Management Overview of SCE—San Onofre" for further information). These increases were partially offset by lower power prices in 2012.
- Higher operations and maintenance expense of $30 million was primarily due to increased energy efficiency program costs.

### Nine Months Ended September 30, 2012 versus September 30, 2011

*(in millions)*

|  | Nine months ended September 30, 2012 Utility Earning Activities | Utility Cost- Recovery Activities | Total Consolidated | Nine months ended September 30, 2011 Utility Earning Activities | Utility Cost- Recovery Activities | Total Consolidated |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| **Operating revenue** | $4,670 | $4,124 | $8,794 | $4,596 | $3,467 | $8,063 |
| Fuel and purchased power | — | 3,269 | 3,269 | — | 2,691 | 2,691 |
| Operations and maintenance | 1,774 | 848 | 2,622 | 1,675 | 775 | 2,450 |
| Depreciation decommissioning and amortization | 1,187 | — | 1,187 | 1,058 | — | 1,058 |
| Property taxes and other | 227 | 2 | 229 | 216 | 1 | 217 |
| **Total operating expenses** | 3,188 | 4,119 | 7,307 | 2,949 | 3,467 | 6,416 |
| **Operating income** | 1,482 | 5 | 1,487 | 1,647 | — | 1,647 |
| Net interest expense and other | (296) | (5) | (301) | (269) | — | (269) |
| **Income before income taxes** | 1,186 | — | 1,186 | 1,378 | — | 1,378 |
| Income tax expense | 384 | — | 384 | 496 | — | 496 |
| **Net income** | 802 | — | 802 | 882 | — | 882 |
| Dividends on preferred and preference stock | 66 | — | 66 | 44 | — | 44 |
| Net income available for common stock | $736 | $— | $736 | $838 | $— | $838 |
| Core Earnings1 |  |  | $736 |  |  | $838 |
| Non-Core Earnings |  |  | — |  |  | — |
| Total SCE GAAP Earnings |  |  | $736 |  |  | $838 |

1 See use of Non-GAAP financial measures in "Edison International Overview—Highlights of Operating Results."

### Utility Earning Activities

Utility earning activities were primarily affected by the following:

- Higher operating revenue of $74 million was primarily due to $80 million of increased revenue related to authorized CPUC projects not included in SCE's GRC process, including the EdisonSmartConnect® project and the Solar Photovoltaic project (approximately $65 million primarily recovered operations and maintenance and depreciation expense associated with the related CPUC projects). The change in revenue also reflects revenue recognized in 2012 related to the San Onofre Unit 2 scheduled outage costs. In December 2011, the CPUC authorized revenue requirements for 2012 refueling outages for San Onofre. These increases were partially offset by decreases in other operating revenue.
- Higher operation and maintenance expense of $99 million was primarily due to increased costs at San Onofre, including $96 million of costs related to the steam generator inspection and repair as well as $35 million related to the 2012 San Onofre Unit 2 scheduled maintenance and refueling outage and $30 million of estimated cash severance costs related to the planned San Onofre reduction in workforce (see "Edison International Overview—Management Overview of SCE—San Onofre" for further information); partially offset by lower operations and maintenance expenses. These increases were partially offset by EdisonSmartConnect® benefits realized and other cost savings and timing of expenses.
- Higher depreciation, decommissioning and amortization expense of $129 million was primarily related to increased generation, transmission and distribution investments, including capitalized software costs and CPUC capital-related projects discussed above.
- Higher net interest expense and other of $27 million was primarily due to higher outstanding balances on long-term debt.
- Lower income taxes due to lower pre-tax income. See "—Income Taxes" below for more information.
- Higher preferred and preference stock dividends of $22 million related to new issuances in 2012.

### Utility Cost-Recovery Activities

Utility cost-recovery activities were primarily affected by the following:

- Higher fuel and purchased power expense of $578 million was primarily driven by the cost to replace CDWR contracts that expired in 2011, which were not previously recorded as an SCE cost but which were included as a separate component on customer bills (see "—Supplemental Operating Revenue Information" below) and $221 million of market costs net of lower nuclear fuel costs related to the San Onofre outage in 2012 (see "Edison International Overview—Management Overview of SCE—San Onofre" for further information). These increases were partially offset by lower power prices in 2012.
- Higher operation and maintenance expense of $73 million was primarily due to increased pension contributions.

### Supplemental Operating Revenue Information

SCE's retail billed and unbilled revenue (excluding wholesale sales and balancing account over/undercollections) was $3.7 billion and $8.7 billion for the three- and nine-month periods ended September 30, 2012, respectively, compared to $3.3 billion and $7.8 billion for the respective periods in 2011. The increase in revenue reflects:

- A sales volume increase of $677 million and $1.4 billion for the three- and nine-month periods, respectively, primarily due to SCE providing power that was previously provided by CDWR contracts which expired in 2011. Prior to 2012, SCE remitted to CDWR and did not recognize as revenue the amounts that SCE billed and collected from its customers for the portion of electric power purchased and sold by the CDWR to SCE's customers.
- A rate decrease of $294 million and $502 million for the three- and nine-month periods, respectively, resulting from rate adjustments in June 2011 and August 2012, primarily reflecting lower forecasted fuel and purchased power costs and refunds to customers of overcollected fuel and power procurement-related costs.

As a result of the CPUC-authorized decoupling mechanism, SCE earnings are not affected by changes in retail electricity sales (see "Item 1. Business—Overview of Ratemaking Process" in the 2011 Form 10-K).

Due to warmer weather during the summer months and SCE's rate design, operating revenue during the third quarter of each year is generally higher than other quarters.

### Income Taxes

The table below provides a reconciliation of income tax expense computed at the federal statutory income tax rate to the income tax provision.

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| Income before income taxes | $564 | $666 | $1,186 | $1,378 |
| Provision for income tax at federal statutory rate of 35% | 197 | 233 | 415 | 482 |
| Increase (decrease) in income tax from: |  |  |  |  |
| State tax – net of federal benefit | 10 | 31 | 30 | 61 |
| Property-related | (19) | (18) | (39) | (38) |
| Other | (12) | (1) | (22) | (9) |
| Total income tax expense | $176 | $245 | $384 | $496 |
| Effective tax rate | 31% | 37% | 32% | 36% |

State income taxes were lower for both the three- and nine-month periods ended September 30, 2012 due to lower pre-tax income and higher benefits related to depreciation, cost of removal and repair deductions, including additional tax deductions reflected in SCE's 2011 tax returns.

For a discussion of the status of Edison International's income tax audits, see "Edison International Notes to Consolidated Financial Statements—Note 7. Income Taxes."

### LIQUIDITY AND CAPITAL RESOURCES

SCE's ability to operate its business, fund capital expenditures, and implement its business strategy are dependent upon its cash flow and access to the capital markets. SCE's overall cash flows fluctuate based on, among other things, its ability to recover its costs in a timely manner from its customers through regulated rates, changes in commodity prices and volumes, collateral requirements, interest and dividend payments to investors, and the outcome of tax and regulatory matters.

SCE expects to fund its 2012 obligations, capital expenditures and dividends through operating cash flows and capital market financings of debt and preferred equity, as needed. SCE also has availability under its credit facilities to meet operating and capital requirements.

### Available Liquidity

During the second quarter of 2012, SCE replaced its existing credit facilities scheduled to mature in early 2013 with a new $2.75 billion five-year revolving credit facility that matures May 2017. The following table summarizes the status of the SCE credit facility at September 30, 2012:

*(in millions)*

|  | Credit Facilities |
| --- | ---: |
| Commitment | $2,750 |
| Outstanding commercial paper supported by credit facilities | (380) |
| Outstanding letters of credit | (196) |
| Amount available | $2,174 |

### Debt Covenant

SCE has a debt covenant in its credit facility that limits its debt to total capitalization ratio to less than or equal to 0.65 to 1. At September 30, 2012, SCE's debt to total capitalization ratio was 0.46 to 1.

### Capital Investment Plan

### Transmission Projects - Tehachapi Project

As discussed in the year-ended 2011 MD&A, the CPUC requested that SCE provide information on potential new options for a portion of the Tehachapi Project, including traversing a state park, changing the nature of some of the towers and undergrounding lines. In July 2012, the Assigned Commissioner issued a ruling requesting SCE to further study and provide more detailed information by the end of February 2013 on two identified undergrounding options for a portion of the project. The ruling set forth a schedule for interested parties to also provide further information, briefing by all parties and evidentiary hearings. The order states that the construction of the affected portion of the project shall remain deferred until the CPUC makes a final determination regarding the options. Adoption of either of the two undergrounding options could create significant additional costs and delay the completion of the project. SCE is required to file revised cost estimates with the CPUC by the end of February 2013. As with all transmission investments, cost recovery will be subject to future rate proceedings.

### Regulatory Proceedings

### FERC Formula Rates

As discussed in the year-ended 2011 MD&A, the FERC has accepted, subject to refund and settlement procedures, SCE's request to implement formula rates as a means to determine SCE's FERC transmission revenue requirement effective January 1, 2012. SCE's request would result in a total 2012 FERC weighted average ROE of 11.1% including a base ROE of 9.93% and the previously authorized 50 basis point incentive for CAISO participation and individual authorized project incentives.

In September 2012, SCE filed its proposed formula rate update with the FERC. SCE's proposed request would implement a 2013 transmission revenue requirement of $900 million, representing an increase of $178 million or 25% over the 2012 revenue requirement. The increase is primarily due to higher FERC rate base from transmission investments, including projects under construction. Consistent with SCE's proposed formula rate methodology, the proposed revenue requirement utilizes the 2012 FERC authorized base ROE discussed above, which remains subject to refund and the ongoing settlement negotiations.

The formula rate mechanism, including the base ROE, is subject to final resolution as part of the settlement process or, if a settlement is not achieved, to determination by FERC in a litigated process. SCE and the other parties to the proceeding continue to engage in settlement negotiations.

### Dividend Restrictions

The CPUC regulates SCE's capital structure which limits the dividends it may pay Edison International. In SCE's most recent cost of capital proceeding, the CPUC set an authorized capital structure for SCE which included a common equity component of 48%. SCE may make distributions to Edison International as long as the common equity component of SCE's capital structure remains at or above the 48% authorized level on a 13-month weighted average basis. At September 30, 2012, SCE's 13-month weighted-average common equity component of total capitalization was 48.9% resulting in the capacity to pay $175 million in additional dividends to Edison International. During the first nine months of 2012, SCE made $349 million in dividend payments to its parent, Edison International.

### Margin and Collateral Deposits

Certain derivative instruments, power procurement contracts and other contractual arrangements contain collateral requirements. Future collateral requirements may differ from the requirements at September 30, 2012, due to the addition of incremental power and energy procurement contracts with collateral requirements, if any, and the impact of changes in wholesale power and natural gas prices on SCE's contractual obligations.

Some of the power procurement contracts contain provisions that require SCE to maintain an investment grade credit rating from the major credit rating agencies. If SCE's credit rating were to fall below investment grade, SCE may be required to pay the liability or post additional collateral.

The table below provides the amount of collateral posted by SCE to its counterparties as well as the potential collateral that would be required as of September 30, 2012.

*(in millions)*

|  |  |
| --- | ---: |
| Collateral posted as of September 30, 20121 | $249 |
| Incremental collateral requirements for power procurement contracts resulting from a potential downgrade of SCE's credit rating to below investment grade | 64 |
| Posted and potential collateral requirements2 | $313 |

1 Collateral provided to counterparties and other brokers consisted of $44 million of cash which was offset against net derivative liabilities on the consolidated balance sheets, $9 million of cash reflected in "Other current assets" on the consolidated balance sheets and $196 million in letters of credit.

2 Total posted and potential collateral requirements may increase by $14 million based on SCE's forward positions as of September 30, 2012 due to adverse market price movements over the remaining lives of the existing power procurement contracts using a 95% confidence level.

### Workers Compensation Self-Insurance Fund

For a discussion of potential collateral requirements related to its self-insured workers compensation plan, refer to "SCE: Liquidity and Capital Resources—Workers Compensation Self-Insurance Fund" in the year-ended 2011 MD&A.

### Historical Segment Cash Flows

The table below sets forth condensed historical cash flow information for SCE.

*(in millions)*

|  | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: |
| Net cash provided by operating activities | $2,656 | $2,272 |
| Net cash provided by financing activities | 636 | 672 |
| Net cash used by investing activities | (3,259) | (3,136) |
| Net increase (decrease) in cash and cash equivalents | $33 | $(192) |

### Net Cash Provided by Operating Activities

Net cash provided by operating activities increased $384 million in the first nine months of 2012 compared to the same period in 2011. The increase in cash flows provided by operating activities was primarily due to higher net tax receipts in 2012, the impact of higher costs at San Onofre and the timing of cash receipts and disbursements related to working capital items.

### Net Cash Provided by Financing Activities

The following table summarizes cash provided by financing activities for the nine months ended September 30, 2012 and 2011. Issuances of debt and preference stock are discussed in "Edison International Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements—Long-Term Debt" and "Note 12. Preferred and Preference Stock."

*(in millions)*

|  | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: |
| Issuances of first and refunding mortgage bonds, net | $391 | $492 |
| Net issuances of commercial paper1 | (45) | 550 |
| Issuances of preference stock, net | 804 | 123 |
| Payments of common stock dividends to Edison International | (349) | (345) |
| Redemptions of preference stock | (75) | — |
| Bonds purchased | — | (86) |
| Payments of preferred and preference stock dividends | (62) | (43) |
| Other | (28) | (19) |
| Net cash provided by financing activities | $636 | $672 |

1 Issuances of commercial paper are supported by SCE's credit facility.

The timing and amount of SCE's financing activities are largely driven by its capital program.

### Net Cash Used by Investing Activities

Cash flows from investing activities are primarily due to capital expenditures and funding of nuclear decommissioning trusts. Capital expenditures were $3.1 billion and $3.0 billion for the nine months ended September 30, 2012 and 2011, respectively (see "Liquidity and Capital Resources—Capital Investment Plan" in the year-ended 2011 MD&A for further information on capital expenditures). Net purchases of nuclear decommissioning trust investments and other were $164 million and $146 million for the nine months ended September 30, 2012 and 2011, respectively.

### Contractual Obligations and Contingencies

### Contractual Obligations

SCE has power purchase commitments which are discussed in "Edison International Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies."

### Contingencies

SCE has contingencies related to the San Onofre Outage, Inspection and Repair Issues, CPSD Investigations, Four Corners New Source Review Litigation, Nuclear Insurance, Wildfire Insurance and Spent Nuclear Fuel, which are discussed in "Edison International Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies."

#### Environmental Remediation

As of September 30, 2012, SCE had identified 25 material sites for remediation and recorded an estimated minimum liability of $113 million. SCE expects to recover 90% of its remediation costs at certain sites. See "Edison International Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies" for further discussion.

### MARKET RISK EXPOSURES

SCE's primary market risks include fluctuations in interest rates, commodity prices and volumes, and counterparty credit. Fluctuations in interest rates can affect earnings and cash flows. Fluctuations in commodity prices and volumes and counterparty credit losses may temporarily affect cash flows, but are not expected to affect earnings due to expected recovery through regulatory mechanisms. Derivative instruments are used, as appropriate, to manage market risks for customers and SCE. For a further discussion of SCE's market risk exposures, including commodity price risk, credit risk and interest rate risk, see "Edison International Notes to Consolidated Financial Statements—Note 6. Derivative Instruments and Hedging Activities" and "—Note 4. Fair Value Measurements."

### Commodity Price Risk

The fair value of outstanding derivative instruments used to mitigate SCE's exposure to commodity price risk was a net liability of $1.0 billion and $936 million at September 30, 2012 and December 31, 2011, respectively. To the extent San Onofre Unit 2 and Unit 3 are not operating, SCE may be exposed to market prices associated with replacement power costs. SCE's hedging program has taken this exposure into consideration and has entered into forward contracts to address projected market price variability. For further discussion of fair value measurements and the fair value hierarchy, see "Edison International Notes to Consolidated Financial Statements—Note 4. Fair Value Measurements."

### Credit Risk

Credit risk exposure from counterparties for power and gas trading activities is measured as the sum of net accounts receivable (accounts receivable less accounts payable) and the current fair value of net derivative assets (derivative assets less derivative liabilities) reflected on the consolidated balance sheets. SCE enters into master agreements which typically provide for a right of setoff. Accordingly, SCE's credit risk exposure from counterparties is based on a net exposure under these arrangements. SCE manages the credit risk on the portfolio for both rated and non-rated counterparties based on credit ratings using published ratings of counterparties and other publicly disclosed information, such as financial statements, regulatory filings, and press releases, to guide it in the process of setting credit levels, risk limits and contractual arrangements, including master netting agreements. As of September 30, 2012, the amount of balance sheet exposure as described above broken down by the credit ratings of SCE's counterparties, was as follows:

*(in millions)*

| S&P Credit Rating1 | September 30, 2012 Exposure2 | Collateral | Net Exposure |
| --- | ---: | ---: | ---: |
| A or higher | $101 | $— | $101 |
| Not rated3 | 5 | (1) | 4 |
| Total | $106 | $(1) | $105 |

1 SCE assigns a credit rating based on the lower of a counterparty's S&P or Moody's rating. For ease of reference, the above table uses the S&P classifications to summarize risk, but reflects the lower of the two credit ratings.

2 Exposure excludes amounts related to contracts classified as normal purchases and sales and non-derivative contractual commitments that are not recorded on the consolidated balance sheets, except for any related net accounts receivable.

3 The exposure in this category relates to long-term power purchase agreements. SCE's exposure is mitigated by regulatory treatment.

### EDISON MISSION GROUP

### RESULTS OF OPERATIONS

EMG primarily operates in one line of business, independent power production, through the subsidiaries of EMG's principal subsidiary, EME. The following table is a summary of competitive power generation results of operations for the periods indicated.

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| **Competitive power generation operating revenues** | $340 | $437 | $1,009 | $1,277 |
| Fuel | 188 | 162 | 458 | 402 |
| Operation and maintenance | 164 | 173 | 572 | 634 |
| Depreciation and amortization | 67 | 72 | 202 | 213 |
| (Gain) loss on sale of assets and other | (65) | — | (60) | 8 |
| **Total operating expenses** | 354 | 407 | 1,172 | 1,257 |
| **Operating income (loss)** | (14) | 30 | (163) | 20 |
| Interest and dividend income | 1 | 1 | 14 | 31 |
| Equity in income from unconsolidated affiliates – net | 25 | 56 | 42 | 68 |
| Other income, net | — | 1 | 1 | 7 |
| Interest expense | (83) | (81) | (253) | (243) |
| **Income (loss) from continuing operations before income taxes** | (71) | 7 | (359) | (117) |
| Income tax benefit | (15) | (11) | (169) | (102) |
| Income (loss) from continuing operations | (56) | 18 | (190) | (15) |
| Income (loss) from discontinued operations – net of tax | (76) | 15 | (129) | (3) |
| **Net income (loss)** | (132) | 33 | (319) | (18) |
| Other noncontrolling interests | 5 | — | 12 | (1) |
| **Net income (loss) available for common stock** | $(137) | $33 | $(331) | $(17) |
| Core income (loss)1 | $(92) | $18 | $(233) | $(14) |
| Non-Core losses: |  |  |  |  |
| Gain on sale of lease interest | 31 | — | 31 | — |
| Discontinued Operations | (76) | 15 | (129) | (3) |
| Total EMG GAAP Income (Loss) | $(137) | $33 | $(331) | $(17) |

1 See use of Non-GAAP financial measures in "Edison International Overview—Highlights of Operating Results."

EMG had a core loss in the third quarter of 2012 compared to core earnings in the third quarter of 2011 primarily due to the following pre-tax items:

- $117 million decrease in Midwest Generation results primarily due to lower capacity and average realized energy prices, reduced generation and higher fuel prices, partially offset by lower planned maintenance costs and lower depreciation.
- $29 million decrease in the Sunrise project results due to the transition off of a long-term power purchase agreement to merchant operations.
- $7 million decrease in renewable energy income primarily attributable to income allocated to third-party investors in Capistrano Wind Partners, partially offset by results of operations from projects that achieved commercial operations after the third quarter of 2011.

The third quarter core loss was partially offset by the following pre-tax item:

- $10 million increase in energy trading due to higher revenues from trading power and MISO congestion contracts.

EMG's core loss for the nine months ended September 30, 2012 increased compared to the nine months ended September 30, 2011 primarily due to the following pre-tax items:

- $257 million decrease in Midwest Generation results primarily due to lower capacity and average realized energy prices, reduced generation and higher fuel prices, partially offset by lower planned maintenance costs and lower depreciation.
- $19 million decrease in the Sunrise project results due to the transition off of a long-term power purchase agreement to merchant operations.
- $15 million lower income from distributions received from the Doga project.
- $10 million increase in interest expense primarily due to new project financings.
- $7 million decrease in renewable energy income was attributable to income allocated to Capistrano Wind Partners, partially offset by results of operations from projects that achieved commercial operations after the third quarter of 2011.

EMG's non-core items for the nine months ended September 30, 2012 included:

- $113 million pre-tax charge ($68 million after tax) associated with the divestiture by Homer City of substantially all of its remaining assets and certain specified liabilities. Pursuant to the Homer City MTA, beginning in the third quarter of 2012, Homer City met the definition of a discontinued operation and was classified separately in Edison International's consolidated statements of income.
- $65 million pre-tax gain ($31 million after tax) associated with the Edison Capital's sale of its lease interest in Unit No. 2 of the Beaver Valley Nuclear Power Plant.

### Adjusted Operating Income (Loss) ("AOI")—Overview

The following table shows the adjusted operating income (loss) (AOI) of EMG's projects:

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| Midwest Generation plants | $(48) | $69 | $(185) | $72 |
| Renewable energy projects | (9) | (2) | 36 | 43 |
| Energy trading | 21 | 11 | 70 | 67 |
| Big 4 projects | 25 | 26 | 33 | 37 |
| Sunrise | — | 29 | 9 | 28 |
| Doga | — | — | 11 | 26 |
| Westside projects | 2 | 1 | (1) | — |
| Leveraged lease income | 2 | 1 | 4 | 4 |
| Gain on sale of lease interest | 65 | — | 65 | — |
| Other projects | (1) | — | 5 | 10 |
| Other operating income | (1) | (1) | — | 1 |
|  | 56 | 134 | 47 | 288 |
| Corporate administrative and general | (34) | (32) | (104) | (101) |
| Corporate depreciation and amortization | (5) | (6) | (16) | (18) |
| AOI1 | $17 | $96 | $(73) | $169 |

1 AOI is equal to operating income (loss) under GAAP, plus equity in income (loss) of unconsolidated affiliates, dividend income from projects, production tax credits, other income and expenses, and net income (loss) attributable to noncontrolling interests. Production tax credits are recognized as wind energy is generated based on a per-kilowatt-hour rate prescribed in applicable federal and state statutes. AOI is a non-GAAP performance measure and may not be comparable to those of other companies. Management believes that inclusion of earnings of unconsolidated affiliates, dividend income from projects, production tax credits, other income and expenses, and net income (loss) attributable to noncontrolling interests in AOI is meaningful for investors as these components are integral to the operating results of EMG.

The following table reconciles AOI to operating income (loss) as reflected on EMG's consolidated statements of operations:

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| AOI | $17 | $96 | $(73) | $169 |
| Less: |  |  |  |  |
| Equity in income of unconsolidated affiliates | 25 | 56 | 42 | 68 |
| Dividend income from projects | — | — | 12 | 27 |
| Production tax credits | 12 | 10 | 48 | 47 |
| Other income (loss), net | (1) | — | — | 6 |
| Net (income) loss attributable to noncontrolling interests | (5) | — | (12) | 1 |
| Operating Income (Loss) | $(14) | $30 | $(163) | $20 |

66

### Adjusted Operating Income from Consolidated Operations

#### Midwest Generation Plants

The following table presents additional data for the Midwest Generation plants:

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| Operating Revenues | $253 | $366 | $699 | $997 |
| Operating Expenses |  |  |  |  |
| Fuel | 183 | 157 | 443 | 390 |
| Plant operations | 73 | 86 | 302 | 368 |
| Plant operating leases | 19 | 19 | 56 | 56 |
| Depreciation and amortization | 22 | 29 | 65 | 87 |
| Loss on disposal and asset impairments | — | — | 4 | 9 |
| Administrative and general | 4 | 6 | 14 | 17 |
| Total operating expenses | 301 | 297 | 884 | 927 |
| Operating Income (Loss) | (48) | 69 | (185) | 70 |
| Other Income | — | — | — | 2 |
| AOI | $(48) | $69 | $(185) | $72 |
| Statistics |  |  |  |  |
| Generation (in GWh) | 6,653 | 7,957 | 17,459 | 20,987 |

AOI from the Midwest Generation plants decreased $117 million for the third quarter of 2012 and $257 million for the nine months ended September 30, 2012 compared to the corresponding periods of 2011. The decreases in AOI were primarily attributable to lower capacity and average realized energy prices, reduced generation and higher fuel prices, partially offset by lower planned maintenance costs and lower depreciation. Reduced generation primarily resulted from lower economic dispatch.

Included in fuel costs were unrealized gains (losses) of $2 million and $(4) million during the third quarters of 2012 and 2011, respectively, and $(2) million and $(6) million for the nine months ended September 30, 2012 and 2011, respectively, due to oil futures contracts that were accounted for as economic hedges. These contracts were entered into as economic hedges of the variable fuel price component of rail transportation costs.

*Seasonality—Midwest Generation Coal Plants*

Due to fluctuations in electric demand resulting from warm weather during the summer months and cold weather during the winter months, electric revenues from the coal plants normally vary substantially on a seasonal basis. In addition, maintenance outages generally are scheduled during periods of lower projected electric demand (spring and fall), further reducing generation and increasing major maintenance costs which are recorded as an expense when incurred. Accordingly, income from the coal plants is seasonal and has significant variability from quarter to quarter. Seasonal fluctuations may also be affected by changes in market prices. For further discussion regarding market prices, see "EMG: Market Risk Exposures—Commodity Price Risk—Energy Price Risk."

#### Renewable Energy Projects

The following table presents additional data for EME's renewable energy projects:

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| Operating Revenues | $47 | $44 | $182 | $155 |
| Production Tax Credits | 12 | 10 | 48 | 47 |
|  | 59 | 54 | 230 | 202 |
| Operating Expenses |  |  |  |  |
| Plant operations | 23 | 20 | 63 | 56 |
| Depreciation and amortization | 38 | 35 | 116 | 103 |
| Administrative and general | — | 1 | 3 | 3 |
| Total operating expenses | 61 | 56 | 182 | 162 |
| Equity in income from unconsolidated affiliates | (2) | (1) | — | — |
| Other Income | — | — | — | 2 |
| Net Income Attributable to Noncontrolling Interests | (5) | 1 | (12) | 1 |
| AOI1 | $(9) | $(2) | $36 | $43 |
| Statistics |  |  |  |  |
| Generation (in GWh)2 | 1,049 | 953 | 4,346 | 3,893 |

1 AOI is equal to operating income (loss) under GAAP plus equity in income (loss) of unconsolidated affiliates, dividend income from projects, production tax credits, other income and expense, and net (income) loss attributable to noncontrolling interests. Production tax credits are recognized as wind energy is generated based upon a per-kilowatt-hour rate prescribed in applicable federal and state statutes. Under GAAP, production tax credits generated by wind projects are recorded as a reduction in income taxes. Accordingly, AOI represents a non-GAAP performance measure which may not be comparable to those of other companies. Management believes that inclusion of production tax credits in AOI for wind projects is meaningful for investors as federal and state subsidies are an integral part of the economics of these projects.

2 Includes renewable energy projects that are not consolidated by Edison International. Generation excluding unconsolidated projects was 902 GWh and 819 GWh in the third quarters of 2012 and 2011, respectively, and 3,761 GWh and 3,356 GWh in the nine months ended September 30, 2012 and 2011, respectively.

AOI from renewable energy projects decreased $7 million for both the three and nine months ended September 30, 2012 as compared to the corresponding periods of 2011. The decrease was primarily attributable to income allocated to third-party investors in Capistrano Wind Partners, partially offset by results of operations from projects that achieved commercial operations after the third quarter of 2011. For additional information, see "Edison International Notes to Consolidated Financial Statements—Note 3. Variable Interest Entities—Projects or Entities that are Consolidated—Capistrano Wind Equity Capital."

The following table reconciles AOI from EME's renewable energy projects to its operating income (loss) as included in EME's consolidated statements of operations:

*(in millions)*

|  | Three Months Ended September 30, 2012 | 2011 | Nine Months Ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| AOI | $(9) | $(2) | $36 | $43 |
| Less: |  |  |  |  |
| Equity in income of unconsolidated affiliates | (2) | (1) | — | — |
| Production tax credits | 12 | 10 | 48 | 47 |
| Other income | — | — | — | 2 |
| Net income (loss) attributable to noncontrolling interests | (5) | 1 | (12) | 1 |
| Operating Income (Loss) | $(14) | $(12) | $— | $(7) |

#### Energy Trading

AOI from energy trading activities increased $10 million for the three months ended September 30, 2012 as compared to the corresponding period of 2011. The increase was mainly due to higher revenues from trading power and MISO congestion contracts.

### Adjusted Operating Income from Other Projects

Doga. EME received a distribution from the Doga project of $11 million in the second quarter of 2012 compared to $26 million in the second quarter of 2011. Distributions in the second quarter of 2011 were higher due to release of funds from restricted cash once project debt obligations were repaid. AOI is recognized when cash is distributed as the Doga project is accounted for on the cost method.

Sunrise Project. AOI from the Sunrise project decreased $29 million and $19 million in the three and nine months ended September 30, 2012, respectively, compared to the corresponding periods of 2011. The decreases in AOI were due to the transition off of a long-term power purchase agreement to merchant operations. Sunrise will continue to operate as a merchant project unless a new power purchase agreement is executed. The profitability of Sunrise as a merchant generator is dependent on market prices for power and natural gas and future results may differ from historical earnings. For additional information, see "EMG: Market Risk Exposures—Commodity Price Risk."

Seasonality. EME's third quarter equity in income from its unconsolidated energy projects is normally higher than equity in income related to other quarters of the year due to seasonal fluctuations and higher energy contract prices during the summer months.

### Interest Income (Expense)

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| Interest income | $1 | $— | $2 | $2 |
| Interest expense, net of capitalized interest |  |  |  |  |
| EME debt | (65) | (66) | (198) | (191) |
| Nonrecourse debt | (18) | (15) | (55) | (52) |
|  | $(83) | $(81) | $(253) | $(243) |

EMG's interest expense increased $2 million and $10 million for the three and nine months ended September 30, 2012, respectively, compared to the corresponding periods of 2011. The 2012 increase in interest expense was primarily due to higher debt balances from new project financings partially offset by higher capitalized interest. Capitalized interest was

$9 million and $4 million for the third quarter of 2012 and 2011, respectively, and $22 million and $20 million for the nine months ended September 30, 2012 and 2011, respectively. The 2012 increase in capitalized interest was due to the Walnut Creek project construction.

### Income Taxes

The table below provides a reconciliation of income tax benefit computed at the federal statutory income tax rate:

*(in millions)*

|  | Three months ended September 30, 2012 | 2011 | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: | ---: | ---: |
| Income (loss) from continuing operations before income taxes | $(71) | $7 | $(359) | $(117) |
| Provision (benefit) for income tax benefit at federal statutory rate of 35% | $(25) | $2 | $(126) | $(42) |
| Increase (decrease) in income tax from: |  |  |  |  |
| State tax benefit – net of federal tax expense | 25 | 1 | 8 | (6) |
| Tax credits, net | (12) | (12) | (48) | (49) |
| Property-related | (1) | (1) | — | (4) |
| Taxes on income allocated to noncontrolling interests | (1) | — | (5) | (1) |
| Other | (1) | (1) | 2 | — |
| Total income tax benefit from continuing operations | $(15) | $(11) | $(169) | $(102) |
| Effective tax rate | 21% | \* | 47% | 87% |

***\**** Not meaningful

EMG's effective tax rates were impacted by production tax credits, estimated state income tax benefits allocated from Edison International, and taxes on income allocated to noncontrolling interests. Estimated state income tax benefits allocated from Edison International of $7 million and $5 million were recognized for the nine months ended September 30, 2012 and 2011, respectively. The benefit for state taxes was lower in 2012 due to an adjustment in state apportionment factors.

### Results of Discontinued Operations

Income (loss) from discontinued operations, net of tax, was $(76) million and $15 million for the third quarters ended September 30, 2012 and 2011, respectively and $(129) million and $(3) million for the nine months ended September 30, 2012 and 2011, respectively. Discontinued operations primarily reflects the results of Homer City. The decreases in earnings reflect a pre-tax charge of $113 million ($68 million after tax) recorded in the third quarter of 2012 associated with the planned divestiture of Homer City. In addition, Homer City's earnings were impacted by lower average realized energy prices and higher coal and emission allowance costs, partially offset by lower plant maintenance costs, as compared to the corresponding periods of 2011. For additional information, see "Edison International Notes to Consolidated Financial Statements—Note 18. Discontinued Operations."

### LIQUIDITY AND CAPITAL RESOURCES

### Available Liquidity

The following table summarizes available liquidity at September 30, 2012

*(in millions)*

|  | Cash and Cash Equivalents |
| --- | ---: |
| EME as a holding company | $325 |
| EME subsidiaries without contractual dividend restrictions |  |
| Midwest Generation | 142 |
| Other EME subsidiaries | 160 |
| EME corporate and Midwest Generation cash and cash equivalents | 627 |
| EME subsidiaries with contractual dividend restrictions |  |
| Other EME subsidiaries | 71 |
| Other EMG subsidiaries | 153 |
| Total | $851 |

See "Edison International Overview—Management Overview of EMG" for a discussion of EME's liquidity.

EME's approach to trading and risk management depends, in part, on the ability to use clearing brokers to enter into market transactions. As a result of its financial position, EME has limited access to enter into such transactions and has been subject to increased initial collateral and margin requirements. There is no assurance that EME will continue to be able to utilize clearing brokers. If EME becomes unable to utilize clearing brokers, it may seek to execute bilateral transactions with third parties which could be unavailable on commercially reasonable terms or at all.

EME, as a holding company, does not directly operate any revenue-producing generation facilities. EME relies on cash distributions and tax payments from its projects and tax benefits received under a tax-allocation agreement with Edison International to meet its obligations, including debt service obligations on long-term debt. The timing and amount of distributions from EME's subsidiaries may be restricted. For further details, including the current restrictions on distributions from the Homer City facility, see "—Debt Covenants and Dividend Restrictions."

### Capital Investment Plan

Forecasted capital expenditures through 2014 by EME's subsidiaries for existing projects and corporate activities are as follows:

*(in millions)*

| Midwest Generation Plants | October through December 2012 | 2013 | 2014 |
| --- | ---: | ---: | ---: |
| Environmental1 | $12 | $112 | $311 |
| Plant capital | 1 | 50 | 16 |
| Walnut Creek Project | 62 | 63 | — |
| Renewable Energy Projects | 50 | 1 | 2 |
| Other capital | 6 | 19 | 15 |
| Total | $131 | $245 | $344 |

1 For additional information, see "Edison International Overview—Management Overview of EMG—Midwest Generation Environmental Compliance Plans and Costs."

### Midwest Generation Capital Expenditures

Midwest Generation plants' forecasted environmental expenditures are based on retrofitting Powerton Units 5 and 6, Joliet Units 7 and 8 and Will County Units 3 and 4, using dry scrubbing with sodium-based sorbents and upgrading particulate removal systems to comply with CPS requirements for SO2 emissions and the US EPA's regulation on hazardous air pollutant emissions. Apart from the Fisk and Crawford Stations, which ceased operations in September 2012, decisions regarding whether or not to proceed with retrofitting any particular remaining units to comply with CPS requirements for SO2 emissions, including those that have received permits, are subject to a number of factors, such as market conditions, regulatory and legislative developments, liquidity and forecasted commodity prices and capital and operating costs applicable at the time decisions are required or made. Final decisions on whether to install controls, to install particular kinds of controls, and to actually expend capital or continue with the expenditure of capital will be made as required, subject to the requirements of the CPS and other applicable regulations. Furthermore, the timing of commencing capital projects may vary from the amounts set forth in the above table. For additional discussion, see "Edison International Overview—Management Overview of EMG—Midwest Generation Environmental Compliance Plans and Costs."

Plant capital expenditures for Midwest Generation includes capital projects for boiler and turbine controls, major boiler components and electrical systems.

### Historical Segment Cash Flows

The table below sets forth condensed historical cash flow information for EMG.

*(in millions)*

|  | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: |
| Operating cash flows from continuing operations | $(545) | $578 |
| Operating cash flows from discontinued operations | (5) | (14) |
| Net cash provided (used) by operating activities | (550) | 564 |
| Net cash provided by financing activities from continuing operations | 348 | 112 |
| Investing cash flows from continuing operations | (234) | (488) |
| Investing cash flows from discontinued operations | (19) | (10) |
| Net cash used by investing activities | (253) | (498) |
| Net increase (decrease) in cash and cash equivalents from continuing operations | $(431) | $202 |
| Net decrease in cash and cash equivalents from discontinued operations | $(24) | $(24) |

### Net Cash Provided (Used) by Operating Activities

The decrease in cash provided by operating activities from continuing operations in 2012 as compared to 2011 was primarily attributable to decreased operating income due to declining energy prices, increased operating costs and higher interest payments due to new energy project financings. The decrease was also attributable to EME tax-allocation payments made, net of receipts, of $168 million in 2012 compared to tax-allocation payments received, net of payments made, of $182 million in 2011. Operating cash flow was also impacted by timing of cash receipts and disbursements related to working capital items.

### Net Cash Provided by Financing Activities

The change in financing activities is primarily due to cash contributions from noncontrolling interests and the timing of financings and repayment of debt as summarized in the following table:

*(in millions)*

|  | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: |
| Cash contributions from noncontrolling interests | $238 | $— |
| Long-term debt financings |  |  |
| Renewable energy projects | — | 76 |
| Walnut Creek project | 154 | 92 |
| Short-term debt financings |  |  |
| Renewable energy projects | 21 | 32 |
| Debt repayments |  |  |
| Renewable energy projects | (23) | (78) |
| Other projects | (8) | (7) |
| Financing costs and others | (34) | (3) |
| Total cash provided by financing activities | $348 | $112 |

### Net Cash Used by Investing Activities

The change in investing activities is primarily due to the timing of capital expenditures and cash collateral to secure letter of credit facilities associated with the termination of EME's revolving credit facility. Changes in other investing activities are reflected in the following table:

*(in millions)*

| Capital expenditures Midwest Generation plants | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: |
| Environmental | $(17) | $(71) |
| Plant capital | (7) | (6) |
| Homer City plant |  |  |
| Environmental | (8) | — |
| Plant capital | (11) | (10) |
| Walnut Creek project | (159) | (166) |
| Renewable energy projects | (78) | (195) |
| Other capital expenditures | (5) | (8) |
| Proceeds from sale of lease interest, net | 107 | — |
| Investments in other assets | (9) | (29) |
| Collateral for letter of credit facilities | (51) | — |
| Other investing activities | (15) | (13) |
| Total cash used in investing activities | $(253) | $(498) |

73

### Credit Ratings

Credit ratings for EME and EMMT as of September 30, 2012 were as follows:

|  |  |  |  |
| --- | --- | --- | --- |
|  | Moody's Rating | S&P Rating | Fitch Rating |
| EME1 | Ca | CCC | C |
| EMMT | Not Rated | CCC | Not Rated |

1 Senior unsecured rating.

All the above ratings are on negative outlook. EME cannot provide assurance that its current credit ratings or the credit ratings of its subsidiaries will remain in effect for any given period of time or that one or more of these ratings will not be lowered. EME notes that these credit ratings are not recommendations to buy, sell or hold its securities and may be revised at any time by a rating agency.

EMG does not have any "rating triggers" contained in subsidiary financings that would result in a requirement to make equity contributions or provide additional financial support to its subsidiaries, including EMMT. However, coal contracts at Midwest Generation include provisions that provide the right to request additional collateral to support payment obligations for delivered coal and may vary based on Midwest Generation's credit ratings.

### Margin, Collateral Deposits and Other Credit Support for Energy Contracts

### Hedging Activities

To reduce its exposure to market risk, EME hedges a portion of its electricity price exposure through EMMT. In connection with entering into contracts, EMMT may be required to support its risk of nonperformance through parent guarantees, margining or other credit support. EME has entered into guarantees in support of EMMT's hedging and trading activities. However, EME has historically also provided collateral in the form of cash and letters of credit for the benefit of counterparties. For further details, see "Edison International Notes to Consolidated Financial Statements—Note 6. Derivative Instruments and Hedging Activities."

Future cash collateral requirements may be higher than the margin and collateral requirements at September 30, 2012, if wholesale energy prices change or if EMMT enters into additional transactions. EME estimates that margin and collateral requirements for energy and congestion contracts outstanding as of September 30, 2012 could increase by approximately $26 million over the remaining life of the contracts using a 95% confidence level.

### Intercompany Tax-Allocation Agreement

EMG and its subsidiaries, EME and Edison Capital, are included in the consolidated federal and combined state income tax returns of Edison International and are eligible to participate in tax-allocation payments with other subsidiaries of Edison International in circumstances where domestic tax losses are incurred. The right of EME and Edison Capital to receive and the amount of and timing of tax-allocation payments are dependent on the inclusion of EME and Edison Capital in the consolidated income tax returns of Edison International and its subsidiaries and other factors, including the consolidated taxable income of Edison International and its subsidiaries, the amount of net operating losses and other tax items of EMG's subsidiaries, and other subsidiaries of Edison International and specific procedures regarding allocation of state taxes. EMG receives tax-allocation payments for tax losses when and to the extent that the consolidated Edison International group generates sufficient taxable income in order to be able to utilize EMG's consolidated tax losses in the consolidated income tax returns for Edison International and its subsidiaries. Based on the application of the factors cited above, EMG is obligated during periods it generates taxable income to make payments under the tax-allocation agreements. Tax-allocation receipts and payments may also be affected by redetermination of utilization of net operating losses resulting from carryback of net operating losses on a consolidated basis or settlement of tax liabilities for prior periods. In September 2012, EME made a tax-allocation payment to Edison International of approximately $185 million related to the displacement, under the tax-allocation agreement, of tax benefits previously received for 2009 federal income taxes. Edison International expects to pay federal and state tax-allocation payments to EME during the next six months of approximately $160 million related to 2012 income taxes. The timing of the receipt of or payment of funds due under the tax-allocation agreement is dependent on future taxable income of Edison International. Estimates of future taxable income are uncertain and changes in estimates may have a material impact on the consolidated financial statements.

### Debt Covenants and Dividend Restrictions

For a description of the covenants binding EME's principal subsidiaries that may restrict the ability of those entities to make distributions to EME directly or indirectly through the other holding companies owned by EME, refer to "Debt Covenants and Dividend Restrictions " in the year-ended 2011 MD&A. Upon the expiration of the Midwest Generation credit facility on June 29, 2012, the debt-to-capitalization ratio as discussed in the Form 10-K is no longer required and Midwest Generation is also no longer contractually restricted in its ability to make distributions to EME. For further information, see "—Available Liquidity." Homer City is restricted from making distributions.

### EME's Senior Notes and Guaranty of Powerton-Joliet Leases

EME is restricted under applicable agreements from selling or disposing of assets, which includes distributions, if the aggregate net book value of all such sales and dispositions during the most recent 12-month period would exceed 10% of consolidated net tangible assets as defined in such agreements computed as of the end of the most recent fiscal quarter preceding the sale or disposition in question. At September 30, 2012, the maximum permissible sale or disposition of EME's assets was $727 million.

This limitation does not apply if the proceeds are invested in assets in similar or related lines of business of EME. Furthermore, EME may sell or otherwise dispose of assets in excess of such 10% limitation if the proceeds from such sales or dispositions, which are not reinvested as provided above, are retained as cash or cash equivalents or are used to repay debt.

### Contractual Obligations and Contingencies

### Contractual Obligations

#### Big Sky Turbine Financing

For a discussion of Big Sky Turbine Financing, see "Edison International Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements—Big Sky Turbine Financing."

#### Coal Transportation Agreements

For a discussion of Midwest Generation's coal transportation agreements, see "Edison International Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies—Coal Transportation Agreements."

#### Capital Commitments

For a discussion of capital commitments, see "Edison Mission Energy and Subsidiaries Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies—Capital Commitments."

### Contingencies

EME has contingencies related to the Midwest Generation New Source Review and other litigation, Homer City New Source Review and other litigation, and environmental remediation which are discussed in "Edison International Notes to Consolidated Financial Statements—Note 9. Commitments and Contingencies—Contingencies."

### Off-Balance Sheet Transactions

For a discussion of EME's off-balance sheet transactions, refer to "EMG: Liquidity and Capital Resources—Off-Balance Sheet Transactions" in the year-ended 2011 MD&A. There have been no significant developments with respect to off-balance sheet transactions that affect disclosures presented in the 2011 Form 10-K except as set forth in "Edison International Overview—Management Overview of EMG—Homer City Lease."

### Environmental Matters and Regulations

For a discussion of EMG's environmental matters, refer to "Environmental Regulation of Edison International and Subsidiaries" in Item 1 of Edison International's 2011 Form 10-K. There have been no significant developments with respect to environmental matters specifically affecting EMG since the filing of the 2011 Form 10-K, except as set forth in "Edison International Notes to Consolidated Financial Statements—Note 10. Environmental Developments."

### MARKET RISK EXPOSURES

For a detailed discussion of market risk exposures, including commodity price risk, credit risk and interest rate risk, refer to "EMG: Market Risk Exposures" in the year-ended 2011 MD&A.

### Derivative Instruments

### Fair Value Disclosures

In determining the fair value of EME's derivative positions, EME uses third-party market pricing where available. For further explanation of the fair value hierarchy and a discussion of EME's derivative instruments, see "Edison International Notes to Consolidated Financial Statements—Note 4. Fair Value Measurements" and "—Note 6. Derivative Instruments and Hedging Activities," respectively.

### Commodity Price Risk

***Ene***rgy Price Risk

Energy and capacity from the coal plants are sold under terms, including price, duration and quantity, arranged by EMMT with customers through a combination of bilateral agreements (resulting from negotiations or from auctions), forward energy sales and spot market sales. Power is sold into PJM at spot prices based upon locational marginal pricing. Energy from 428 MW of merchant renewable energy projects is sold in the energy markets, primarily at spot prices in PJM and ERCOT.

The following table depicts the average historical market prices for energy per megawatt-hour at the Northern Illinois Hub related to the Midwest Generation plants for the first nine months of 2012 and 2011:

|  | 24-Hour Average Historical Market Prices1 2012 | 2011 |
| --- | ---: | ---: |
| Northern Illinois Hub | $28.56 | $35.30 |

1 Energy prices were calculated at the Northern Illinois Hub using historical hourly day-ahead prices as published by PJM or provided on the PJM web-site.

The following table sets forth the forward market prices for energy per megawatt-hour as quoted for sales into the Northern Illinois Hub at September 30, 2012:

| 2012 | 24-Hour Forward Energy Prices1 Northern Illinois Hub |
| --- | ---: |
| October | $27.35 |
| November | 27.17 |
| December | 30.22 |
| 2013 calendar "strip"2 | $30.60 |
| 2014 calendar "strip"2 | $31.31 |

1 Energy prices were determined by obtaining broker quotes and information from other public sources relating to the Northern Illinois Hub delivery point.

2 Market price for energy purchases for the entire calendar year.

Power prices remained low in the first nine months of 2012 due to an abundance of low-priced natural gas and the sales volume from the Midwest Generation plants has been correspondingly affected. Forward market prices at the Northern Illinois Hub fluctuate as a result of a number of factors, including natural gas prices, transmission congestion, changes in market rules, electricity demand (which in turn is affected by weather, economic growth, and other factors), plant outages in the region, and the amount of existing and planned power plant capacity. The actual spot prices for electricity delivered by the Midwest Generation plants into these markets may vary materially from the forward market prices set forth in the preceding table.

EMMT engages in hedging activities for the coal plants to hedge the risk of future change in the price of electricity. The following table summarizes the hedge positions at September 30, 2012 for electricity expected to be generated during the remainder of 2012 and in 2013:

|  | 2012 MWh (in thousands) | Average price/ MWh1 | 2013 MWh (in thousands) | Average price/ MWh1 |
| --- | ---: | ---: | ---: | ---: |
| Midwest Generation plants2 | 2,028 | $37.53 | 3,615 | $36.55 |

1 The above hedge positions include forward contracts for the sale of power and futures contracts during different periods of the year and the day. Market prices tend to be higher during on-peak periods and during summer months, although there is significant variability of power prices during different periods of time. Accordingly, the above hedge positions are not directly comparable to the 24-hour Northern Illinois Hub prices set forth above.

2 Includes hedging transactions primarily at the Northern Illinois Hub and to a lesser extent the AEP/Dayton Hub, both in PJM, and the Indiana Hub in MISO.

### Sunrise Project

Beginning July 1, 2012, EME's 50% owned Sunrise project, which EME accounts for on the equity method, will operate as a merchant generator and sell power at spot prices from its 572 MW facility into the California ISO market, unless a power purchase agreement is obtained. Spot prices are currently expected to be between the price for the NP15 and SP15 trading locations in that market. As a gas-fired merchant generator, Sunrise purchases natural gas based on spot prices and, accordingly, the plant is dispatched in periods when the power prices exceed the cost of fuel and other variable operations and maintenance costs. Historically, Sunrise has operated more during the summer months due to higher demand driven by warm weather.

### Capacity Price Risk

Under the RPM, capacity commitments are made in advance to provide a long-term pricing signal for construction and maintenance of capacity resources. The following table summarizes the status of capacity sales for Midwest Generation at September 30, 2012:

|  | RPM Capacity Sold in Base Residual Auction MW | Price per MW-day | Other Capacity Purchases, Net of Sales1 MW | Average Price per MW-day | Aggregate Average Price per MW-day |
| --- | ---: | ---: | ---: | ---: | ---: |
| October 1, 2012 to May 31, 2013 | 4,704 | $16.46 | (450) | $15.67 | $16.54 |
| June 1, 2013 to May 31, 2014 | 4,650 | 27.73 | (2,430) | 7.01 | 50.40 |
| June 1, 2014 to May 31, 2015 | 4,625 | 125.99 | (700) | 5.54 | 147.47 |
| June 1, 2015 to May 31, 2016 | 3,620 | 136.00 | — | — | 136.00 |

1 Other capacity sales and purchases, net includes contracts executed in advance of the RPM base residual auction to hedge the price risk related to such auction, participation in RPM incremental auctions and other capacity transactions entered into to manage capacity risks.

The RPM auction capacity prices for the delivery period of October 1, 2012 to May 31, 2013 and June 1, 2013 to May 31, 2014 varied between different areas of PJM. In the western portion of PJM, affecting Midwest Generation, the prices of $16.46 per MW-day and $27.73 per MW-day were substantially lower than capacity prices in other areas.

Revenues from the sale of capacity from Midwest Generation beyond the periods set forth above will depend upon the amount of capacity available and future market prices either in PJM or nearby markets if those facilities have an opportunity to capture a higher value associated with those markets.

### Basis Risk

During the nine months ended September 30, 2012, day-ahead prices at the individual busbars of the Midwest Generation plants compared to the AEP/Dayton Hub, Indiana Hub (Cinergy Hub) and Northern Illinois Hub were on average lower by 6%, lower by 1% and higher by 1%, respectively. During the nine months ended September 30, 2011, day-ahead prices at the individual busbars of the Midwest Generation plants were lower compared to the AEP/Dayton Hub and Indiana Hub (Cinergy Hub) by an average of 12% and 2%, respectively. Differences in day-ahead pricing between the individual busbars of the Midwest Generation plants generally arise due to transmission congestion.

### Coal Price Risk

The Midwest Generation plants purchase coal primarily from the Southern PRB of Wyoming. Coal purchases are made under a variety of supply agreements. The following table summarizes the amount of coal under contract at September 30, 2012, for the remainder of 2012 and the following two years:

|  | October through December 2012 | 2013 | 2014 |
| --- | ---: | ---: | ---: |
| Amount of Coal Under Contract in Millions of Equivalent Tons1 | 4.9 | 11.1 | 9.8 |

1 The amount of coal under contract in equivalent tons is calculated based on contracted tons and applying an 8,800 Btu equivalent.

Midwest Generation is subject to price risk for purchases of coal that are not under contract. Market prices of PRB coal based on 8,800 Btu per pound heat content and 0.8 pounds of SO2 per MMBtu sulfur content decreased to a price of $9.20 per ton at September 28, 2012, compared to a price of $12.75 per ton at December 30, 2011, as reported by the EIA.

### Credit Risk

The credit risk exposure from counterparties of merchant energy hedging and trading activities is measured as the sum of net receivables (accounts receivable less accounts payable) and the current fair value of net derivative assets. EME's subsidiaries enter into master agreements and other arrangements in conducting such activities which typically provide for a right of setoff in the event of bankruptcy or default by the counterparty. At September 30, 2012, the balance sheet exposure as described above, by the credit ratings of EME's counterparties, was as follows:

*(in millions)*

| Credit Rating1 | September 30, 2012 Exposure2 | Collateral | Net Exposure |
| --- | ---: | ---: | ---: |
| A or higher | $91 | $— | $91 |
| A- | 8 | (8) | — |
| BBB+ | 4 | — | 4 |
| BBB | — | — | — |
| BBB- | — | — | — |
| Below investment grade | 29 | (29) | — |
| Total | $132 | $(37) | $95 |

1 EME assigns a credit rating based on the lower of a counterparty's S&P or Moody's rating. For ease of reference, the above table uses the S&P classifications to summarize risk, but reflects the lower of the two credit ratings.

2 Exposure excludes amounts related to contracts classified as normal purchase and sales and non-derivative contractual commitments that are not recorded on the consolidated balance sheet, except for any related accounts receivable.

The credit risk exposure set forth in the above table is composed of $64 million of net accounts receivable and payables and $68 million representing the fair value of derivative contracts. The exposure is based on master netting agreements with the related counterparties. Credit ratings may not be reflective of the actual related credit risks. In addition to the amounts set forth in the above table, EME's subsidiaries have posted a $79 million cash margin in the aggregate with PJM, NYISO,

MISO, clearing brokers and other counterparties to support hedging and trading activities. The margin posted to support these activities also exposes EME to credit risk of the related entities.

The Midwest Generation coal plants sell electric power generally into the PJM market by participating in PJM's capacity and energy markets or transacting in capacity and energy on a bilateral basis. Sales into PJM accounted for approximately 73% of EME's consolidated operating revenues for the nine months ended September 30, 2012. At September 30, 2012, EME's account receivable due from PJM was $53 million.

EME's turbine supply agreements contain significant suppliers' obligations related to the manufacturing and delivery of turbines, and payments, for delays in delivery and for failure to meet performance obligations and warranty agreements. EME's reliance on these contractual provisions is subject to credit risks. Generally, these are unsecured obligations of the turbine manufacturer. A material adverse development with respect to EME's turbine suppliers may have a material impact on EME's projects and development efforts. Two of EME's wind turbine suppliers, Suzlon and Clipper, are currently experiencing significant adverse credit and liquidity issues. As a result, EME's ability to enforce performance and warranty guarantees is subject to the credit risk of these counterparties.

### Interest Rate Risk

Interest rate changes can affect earnings and the cost of capital for capital improvements or new investments in power projects. EME mitigates the risk of interest rate fluctuations by arranging for fixed rate financing or variable rate financing with interest rate swaps, interest rate options or other hedging mechanisms for a number of its project financings. For further details, see "Edison International Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements" and "—Note 6. Derivative Instruments and Hedging Activities."

### EDISON INTERNATIONAL PARENT AND OTHER

### RESULTS OF OPERATIONS

Results of operations for Edison International Parent and Other includes amounts from other Edison International subsidiaries that are not significant as a reportable segment, as well as intercompany eliminations.

Edison International Parent and Other loss from continuing operations was $36 million and $13 million for the three- and nine-month periods ended September 30, 2012, respectively, compared to $48 million and $19 million for the same periods in 2011. In the third quarter of 2012, Edison International and EME recorded income tax charges of $13 million and $16 million, respectively, related to changes in California apportionment rates used in prior periods. The charges related to an update of Edison International's assessment of uncertain tax positions following a recent court case. In addition, Edison International updated its estimated long-term California apportionment rate applicable to consolidated deferred income taxes as a result of reductions in EME's projected sales resulting in income charges during the third quarter of $16 million.

### LIQUIDITY AND CAPITAL RESOURCES

Edison International Parent liquidity and its ability to pay operating expenses and dividends to common shareholders is dependent on dividends from SCE, tax-allocation payments under its tax-allocation agreements with its subsidiaries, and access to bank and capital markets.

During the second quarter of 2012, Edison International Parent replaced its credit facilities with a new $1.25 billion five-year revolving credit facility that matures May 2017. The following table summarizes the status of the Edison International Parent credit facility at September 30, 2012:

*(in millions)*

|  | Edison International (parent) |
| --- | ---: |
| Commitment | $1,250 |
| Outstanding borrowings | (28) |
| Amount available | $1,222 |

Edison International has a debt covenant in its credit facility that requires a consolidated debt to total capitalization ratio of less than or equal to 0.65 to 1. The ratio of debt to total capitalization is defined in the credit agreement and generally excludes the consolidated debt and total capital of EME. At September 30, 2012, Edison International's consolidated debt to total capitalization ratio was 0.48 to 1.

### Historical Segment Cash Flows

The table below sets forth condensed historical cash flow information for Edison International Parent and Other.

*(in millions)*

|  | Nine months ended September 30, 2012 | 2011 |
| --- | ---: | ---: |
| Net cash provided (used) by operating activities | $51 | $(13) |
| Net cash provided by financing activities | 36 | 21 |
| Net cash provided by investing activities | — | 1 |
| Net increase in cash and cash equivalents | $87 | $9 |

### Net Cash Used by Operating Activities

Net cash provided by operating activities primarily relate to interest, operating costs and income taxes of Edison International Parent. In addition to these factors, Edison International Parent funded a portion of the 2011 tax-allocation payments due by Edison Capital in consideration of an intercompany note receivable.

### Net Cash Provided by Financing Activities

Financing activities for the first nine months of 2012 were as follows:

- Paid $318 million of dividends to Edison International common shareholders.
- Received $349 million of dividend payments from SCE.

Financing activities for the first nine months of 2011 were as follows:

- Paid $313 million of dividends to Edison International common shareholders.
- Received $345 million of dividend payments from SCE.
- Repaid $9 million under Edison International's line of credit.

### EDISON INTERNATIONAL (CONSOLIDATED)

### LIQUIDITY AND CAPITAL RESOURCES

### Contractual Obligations

Significant changes with respect to Edison International (Consolidated) contractual obligations since the filing of the 2011 Form 10-K are discussed in "EMG: Liquidity and Capital Resources—Contractual Obligations" and "SCE: Liquidity and Capital Resources—Contractual Obligation."

### CRITICAL ACCOUNTING ESTIMATES AND POLICIES

For a discussion of Edison International's critical accounting estimates and policies, see "Critical Accounting Estimates and Policies" in the year-ended 2011 MD&A.

### NEW ACCOUNTING GUIDANCE

New accounting guidance is discussed in "Edison International Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—New Accounting Guidance."

## Market risk

As filed, 138 characters.

Information responding to Item 3 is included in the MD&A under the headings "SCE: Market Risk Exposures" and "EMG: Market Risk Exposures."

## Controls and procedures

As filed, 1,247 characters.

### Disclosure Controls and Procedures

Edison International's management, under the supervision and with the participation of the company's Chief Executive Officer and Chief Financial Officer, has evaluated the effectiveness of Edison International's disclosure controls and procedures (as that term is defined in Rules 13a-15(e) or 15d-15(e) under the Securities Exchange Act of 1934, as amended (the "Exchange Act")) as of the end of the third quarter of 2012. Based on that evaluation, the Chief Executive Officer and Chief Financial Officer concluded that, as of the end of the third quarter of 2012, Edison International's disclosure controls and procedures were effective.

### Changes in Internal Control Over Financial Reporting

There were no changes in Edison International’s internal control over financial reporting (as that term is defined in Rules 13a-15(f) or 15d-15(f) under the Exchange Act) during the third quarter of 2012 that have materially affected, or are reasonably likely to materially affect, Edison International’s internal control over financial reporting.

### Jointly Owned Utility Plant

Edison International's scope of evaluation of internal control over financial reporting includes its Jointly Owned Utility Projects.

Filed Nov 1, 2012.