## Risk factors

As filed, 66,441 characters.

*This report contains “forward-looking statements” within the meaning of the federal securities laws. Forward-looking statements are all statements other than statements of historical facts, such as statements regarding anticipated production volumes, unit net cash costs, sales volumes, ore grades, milling rates, commodity prices, development and capital expenditures, mine production and development plans, availability of power, water, labor and equipment, environmental reclamation and closure cost and plans, environmental liabilities and expenditures, litigation liabilities and expenses, dividend payments, reserve estimates, political, economic and social conditions in our areas of operations and exploration efforts and results. Except for our ongoing obligations under the federal securities laws, we do not intend, and we undertake no obligation, to update or revise any forward-looking statements. Readers are cautioned that forward-looking statements are not guarantees of future performance and actual results may differ materially from those projected, anticipated or assumed in the forward-looking statements. Important factors that could cause our actual results to differ materially from those anticipated in the forward-looking statements include the following.*

### Financial risks

***Extended declines in the market prices of copper, gold and/or molybdenum could continue to adversely affect our earnings and cash flows and, if sustained, could eventually adversely affect our ability to repay debt. Fluctuations in the market prices of copper, gold and molybdenum can cause significant volatility in our financial performance and can adversely affect the trading prices of our debt and equity securities.***

Our earnings and cash flows are affected significantly by the market prices of copper and, to a lesser extent, gold and molybdenum. The world market prices of these commodities have fluctuated historically and are affected by numerous factors beyond our control. Copper prices have declined significantly from their recent historically high levels. Exchange inventories have increased significantly since the first half of 2008. After averaging $3.61 per pound for the first nine months of 2008, London Metal Exchange (LME) spot copper prices declined to a four-year low of $1.26 per pound in December 2008 and the LME spot copper price closed at $1.41 per pound on January 30, 2009. The price of molybdenum averaging approximately $33 per pound for the first nine months of 2008, declining to a four-year low of $8.75 per pound in November 2008 and was $9.30 per pound on January 30, 2009. Gold prices averaged approximately $872 per ounce for 2008 and closed at $920 per ounce on January 30, 2009. An extended decline in the market price of these commodities could (1) adversely affect our earnings and cash flows, (2) adversely affect our ability to repay our debt and meet our other fixed obligations, and (3) depress the trading prices of our common and preferred stock and of our publicly traded debt securities.

In addition, substantially all of our copper concentrate sales and some of our copper cathode sales are provisionally priced at the time of shipment, subject to final pricing at a specified future date based on LME or New York Merchantile Exchange (COMEX) prices on that date. Accordingly, in times of falling copper prices, our revenues during a quarter are negatively affected by lower prices received for sales priced at current market rates and also from a decrease related to the final pricing of provisionally priced sales in prior periods.

If the market prices for the metals we produce fall below our production costs for a sustained period of time, we may have to further revise our operating plans, including further curtailing production, reducing operating costs and capital expenditures and discontinuing certain exploration and development programs. We may be unable to decrease our costs in an amount sufficient to offset reductions in revenues, and may incur losses.

World copper prices have historically fluctuated widely. During the three years ended December 31, 2008, LME daily closing spot prices ranged from $1.26 to $4.08 per pound for copper. World copper prices are affected by numerous factors beyond our control, including:

- the strength of the U.S. economy and the economies of other industrialized and developing nations, including China, which has become the largest consumer of refined copper in the world;
- available supplies of copper from mine production and inventories;
- sales by holders and producers of copper;
- demand for industrial products containing copper;
- investment activity, including speculation, in copper as a commodity;
- the availability and cost of substitute materials; and
- currency exchange fluctuations, including the relative strength or weakness of the U.S. dollar.

World gold prices have historically fluctuated widely. During the three years ended December 31, 2008, the daily closing prices on the London spot market ranged from $525 to $1,011 per ounce for gold. World gold prices are affected by numerous factors beyond our control, including:

- the strength of the U.S. economy and the economies of other industrialized and developing nations, including China;
- global or regional political or economic crises;
- the relative strength of the U.S. dollar and other currencies;
- expectations with respect to the rate of inflation;
- interest rates;
- purchases and sales of gold by central banks and other holders;
- demand for jewelry containing gold; and
- investment activity, including speculation, in gold as a commodity.

Molybdenum prices also fluctuate widely. Molybdenum demand depends primarily on the global steel industry, which uses the metal as a hardening and corrosion inhibiting agent. Approximately 80 percent of molybdenum production is used in this application. The remainder is used in specialty chemical applications such as catalysts, water treatment agents and lubricants. Approximately 50 percent of global molybdenum production is a by-product of copper mining, which is relatively insensitive to molybdenum prices. Decreased demand for molybdenum during the fourth quarter of 2008 resulted in a sudden and sharp decline in molybdenum prices. During the three years ended December 31, 2008, the *Metals Week* Dealer Oxide weekly average price for molybdenum ranged from $8.75 to $33.88 per pound. Molybdenum prices are affected by numerous factors beyond our control, including:

- the worldwide balance of molybdenum demand and supply;
- rates of global economic growth, especially construction and infrastructure activity that requires significant amounts of steel;
- the volume of molybdenum produced as a by-product of copper production;
- inventory levels;
- currency exchange fluctuations, including the relative strength or weakness of the U.S. dollar; and
- production costs of U.S. and foreign competitors.

***The agreements governing our indebtedness require us to meet certain financial tests and other covenants and as a result may limit our flexibility in the operation of our business and our ability to pay dividends on our common stock.***

We incurred significant debt to fund a portion of the cash consideration paid to acquire Phelps Dodge. As of December 31, 2008, the outstanding principal amount of our indebtedness was $7.4 billion. The agreements governing our indebtedness restrict, subject to certain exceptions, our ability to:

- incur additional indebtedness;
- engage in transactions with affiliates;
- create liens on our assets;
- make payments in respect of equity issued by us or our subsidiaries, including the payment of dividends on our common stock;
- make investments in, or loans, to entities that we do not control, including joint ventures;
- sell assets;
- merge with or into other companies;
- enter into sale and leaseback transactions;
- enter into unrelated businesses;
- enter into agreements or arrangements that restrict the ability of certain of our subsidiaries to pay dividends or other distributions;
- prepay indebtedness; and
- enter into hedging transactions other than in the ordinary course of business.

In addition, our senior credit facilities require that we meet certain financial tests at any time that borrowings are outstanding under our revolving credit facility, including a leverage ratio test (Total Debt to Consolidated EBITDA, as those terms are defined in the facility, for the preceding four quarters cannot exceed 5.0 to 1.0 on the last day of any fiscal quarter) and a secured leverage ratio test (Total Secured Debt to Consolidated EBITDA, as those terms are defined in the facility, for the preceding four quarters cannot exceed 3.0 to 1.0 on the last day of any fiscal quarter). During periods in which copper, gold or molybdenum prices or production volumes, or other conditions reflect the adverse impact of cyclical market trends or other factors, we may not be able to comply with the applicable financial covenants.

Our senior credit facilities, the $6.0 billion 8.25%, 8.375%, and floating rate senior notes and the 6⅞% senior notes contain covenants that limit our ability to make certain payments. These restrictions vary among the instruments, but generally limit our ability to pay certain dividends on common and preferred stock, repurchase or redeem common and preferred equity, prepay subordinated debt and make certain investments. At December 31, 2008, the most restrictive of these covenants allowed for such payments up to a limit that exceeded $5 billion.

Our obligations under our senior credit facilities are (i) guaranteed by substantially all of our domestic subsidiaries and (ii) secured by a pledge of (a) 100 percent of the equity in substantially all of our domestic subsidiaries and (b) 66.5 percent of the equity in substantially all of our first tier foreign subsidiaries.

Any failure to comply with the restrictions of our senior credit facilities, senior notes or any agreement governing our other indebtedness, after giving effect to any applicable grace period, may result in an event of default. Such default may allow the creditors to accelerate the related debt, which may trigger cross-acceleration or cross-default provisions in other debt agreements. Our assets and cash flow would not be sufficient to fully repay borrowings under our debt instruments that are accelerated upon an event of default.

If we are unable to repay, refinance or restructure our indebtedness under, or amend the covenants contained in, our senior credit agreements at maturity or in the event of a default, the lenders under our senior credit facilities could terminate their commitments thereunder, cease making further loans, declare all borrowings outstanding (together with accrued interest and other fees) immediately due and payable and institute foreclosure proceedings against the security. Any such actions could negatively affect our financial condition and results of operations.

***Under U.S. federal and state laws that require closure and reclamation plans for our mines, we are required to provide financial assurance sufficient to allow a third party to implement those plans if we are unable to do so. The U.S. Environmental Protection Agency (EPA) and state agencies may seek financial*** assurance for ***investigation and remediation actions taken under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) or equivalent state regulations. The failure to comply with these requirements could have a material adverse effect on us.***

We are required by U.S. federal and state laws to provide financial assurance sufficient to allow a third party to implement approved closure and reclamation plans if we are unable to do so. These laws are complex and vary from jurisdiction to jurisdiction. The laws govern the determination of the scope and cost of the closure and reclamation obligations and the amount and forms of financial assurance.

As of December 31, 2008, our financial assurance obligations associated with closure and reclamation costs totaled approximately $715 million, of which approximately $425 million was in the form of parent company guarantees and financial capability demonstrations. Our ability to continue to provide financial assurance in the form of parent guarantees and financial capability demonstrations in New Mexico and Arizona depends on our ability to meet financial tests. Certain of the ratios in these tests are significantly more rigorous for companies that do not have an investment grade rating from a state-approved ratings service. We are currently rated investment grade by Standard & Poor’s and Fitch, but are not rated investment grade by Moody’s. If we fail to maintain our investment grade rating, we would be subject to these alternate tests, and as a result, the regulatory agencies may require us to provide alternative forms of financial assurance to fully satisfy our financial assurance obligations, such as letters of credit, surety bonds or collateral. Depending on our financial condition and market conditions, these other forms of financial assurance may be difficult or costly to provide. Issuance of letters of credit under our credit facilities would reduce our available liquidity. Failure to provide the required financial assurance could result in the closure of mines. As of December 31, 2008, we have limited financial assurance obligations associated with CERCLA-related actions, although EPA and certain states are currently considering increasing the use of financial assurance requirements. For additional information, see the risk factor “Mine closure regulations impose substantial costs on our operations” below.

***We need significant amounts of cash to service our debt. If we are unable to generate sufficient cash to service our debt, our financial condition and results of operations could be negatively affected.***

We must generate sufficient amounts of cash to service and repay our debt. Our ability to generate cash will be affected by general economic, financial, competitive, legislative, regulatory and other factors that are beyond our control. Future borrowings may not be available to us under our senior credit facilities or from the capital markets in amounts sufficient to pay our obligations as they mature or to fund other liquidity needs. If we are not able to obtain such borrowings or generate sufficient cash from operations to service and repay our indebtedness, we will need to refinance our indebtedness to avoid any default. Such refinancing may not be available on favorable terms or at all. The inability to service, repay or refinance our indebtedness could negatively affect our financial condition and results of operations.

***Our indebtedness, as well as the current global recession, disruption in financial markets and lower copper and/or molybdenum prices generally, could, among other things, impede our access to capital or increase our cost of capital, which would have an adverse effect on our ability to fund our working capital and other capital requirements.***

As of December 31, 2008, the outstanding principal amount of our debt was approximately $7.4 billion. The widely reported domestic and global recession, the associated low copper and molybdenum prices, and the unprecedented levels of disruption and continuing illiquidity in the credit markets have had an adverse effect on our operating results and financial condition, and if sustained or worsened such adverse effects could continue or worsen. Disruptions in the credit and financial markets have adversely affected financial institutions, inhibited lending and limited access to capital and credit for many companies, including ours. These disruptions have made it difficult for us to obtain, or increase our cost of obtaining, capital and financing for our operations and have limited our flexibility to plan for, or react to, changes in our business and the markets in which we operate. If these conditions persist or worsen, they could, among other things, make it difficult for us to finance our working capital requirements and service our existing debt.

If future financing is not available to us when required, as a result of limited access to the credit markets or otherwise, or is not available on acceptable terms, we may be unable to invest needed capital for our development and exploration programs, take advantage of business opportunities or respond to competitive pressures, any of which could have an adverse effect on our operating results and financial condition.

***Movements in foreign currency exchange rates or interest rates could negatively affect our operating results.***

Substantially all of our revenues and a significant portion of our costs are denominated in U.S. dollars; however, some of our costs, and certain of our asset and liability accounts, are denominated in Indonesian rupiah, Chilean pesos, Peruvian nuevos soles, Australian dollars, Euros and other foreign currencies. As a result, we will be generally less profitable when the U.S. dollar weakens in relation to these foreign currencies.

As of December 31, 2008, approximately 20 percent of our outstanding debt was subject to variable interest rates. Increases in these rates will increase our interest costs and reduce our profits and operating cash flows.

From time to time, we may implement currency or interest rate hedges intended to reduce our exposure to changes in foreign currency exchange or interest rates. However, our hedging strategies may not be successful, and any of our unhedged foreign exchange or interest payments will continue to be subject to market fluctuations.

### Operational risks

***The volume and grade of ore reserves that we recover and our rate of production may be more or less than anticipated.***

Our ore reserve amounts are determined in accordance with established mining industry practices and standards, and are estimates of the mineral deposits that can be recovered economically and legally based on currently available data. Estimates of recoverable proven and probable reserves are subject to considerable uncertainty. Ore bodies may not conform to standard geological expectations, and estimates may change as new data becomes available. Because ore bodies do not contain uniform grades and types of minerals, our metal recovery rates will vary from time to time.

Additionally, because the determination of reserves is based partially on estimates of future selling prices, a sustained decrease in such prices may result in a reduction in economically recoverable ore reserves. These factors may result in variations in the volumes of mineral reserves that we report from period to period.

There are also uncertainties inherent in estimating quantities of ore reserves and copper recovered from stockpiles. The quantity of copper contained in mill and leach stockpiles is based on surveyed volumes of mined material and daily production records. The volume and grade of ore reserves recovered, rates of production and recovered copper from stockpiles may be less than anticipated.

***We must continually replace reserves depleted by production. Our exploration activities may not result in additional discoveries.***

Our ability to replenish our ore reserves is important to our long-term viability. Produced ore reserves must be replaced by further delineation of existing ore bodies or by locating new deposits in order to maintain production levels over the long term. Exploration is highly speculative in nature. Our exploration projects involve many risks, require substantial expenditures and may not result in the discovery of sufficient additional mineral deposits that can be mined profitably. Once a site with mineralization is discovered, it may take several years from the initial phases of drilling until production is possible, during which time the economic feasibility of production may change. Substantial expenditures are required to establish recoverable proven and probable reserves and to construct mining and processing facilities. As a result, there is no assurance that current or future exploration programs will be successful. There is a risk that depletion of reserves will not be offset by discoveries or acquisitions.

***Our business is subject to operational risks that are generally outside of our control and could adversely affect our business.***

Mines by their nature are subject to many operational risks and factors that are generally outside of our control and could adversely affect our business, operating results and cash flows. These operational risks and factors include the following:

- unanticipated ground and water conditions;
- adverse claims to water rights and shortages of water to which we have rights;
- adjacent land ownership that results in constraints on current or future mine operations;
- geological problems, including earthquakes and other natural disasters;
- metallurgical and other processing problems;
- the occurrence of unusual weather or operating conditions and other force majeure events;
- lower than expected ore grades or recovery rates;
- accidents;
- delays in the receipt of or failure to receive necessary government permits;
- the results of litigation, including appeals of agency decisions;
- uncertainty of exploration and development;
- delays in transportation;
- interruption of energy supply;
- labor disputes;
- inability to obtain satisfactory insurance coverage; and
- the failure of equipment or processes to operate in accordance with specifications or expectations.

***Continuation of our mining production is dependent on the availability of a sufficient water supply to support our mining operations.***

Our mining operations require significant quantities of water for mining, ore processing and related support facilities. Our operations in North and South America are in areas where water is scarce and competition among users for continuing access to water is significant. Continuous production at our mines is dependent on our ability to maintain our water rights and claims and defeat claims adverse to our current water uses in legal proceedings. At our U.S. operations, under state law, our water rights give us only the right to use public waters for a statutorily defined beneficial use at a designated location. In Arizona, we are a participant in two active general stream adjudications in which for over 30 years the State of Arizona has been attempting to quantify and prioritize surface water claims in two of the state’s largest river systems that include three of our operating mines (Morenci, Sierrita and Safford) and which may also affect our Arizona mine at Bagdad. Groundwater is not subject to adjudication in Arizona, but is subject to the doctrine of reasonable use, which requires balancing the utility of the use against the gravity of the harm to others who have rights in the same aquifer; however, wells may be subject to adjudication to the extent they are found to produce or affect surface water. In Colorado, our surface water and groundwater rights are subject to adjudication and we are involved in legal proceedings to resolve disputes regarding priority of administration of rights, including priority of some of our rights for the Climax mine. Our surface water and groundwater rights are fully licensed or have been fully adjudicated in New Mexico.

In South America, water for our mining operations at Candelaria and Ojos del Salado is drawn from the Copiapo River aquifer. Because of rapid depletion of this aquifer in recent years, ongoing studies are addressing the adequacy of this water supply for our mining operations at these sites and a project to pump effluent from a nearby sewerage treatment plant as an alternate water source is being explored. At El Abra, regulatory agencies continue to evaluate the potential hydrologic and ecologic effects from our groundwater pumping at the Salar de

Ascotán, with a pending agency determination on the adequacy of our mitigation management plan for this area.

Although each operation currently has sufficient water rights and claims to cover its operational demands, we cannot predict the potential outcome of pending or future legal proceedings on our water rights, claims and uses. The loss of some or all water rights for any of our mines, in whole or in part, or shortages of water to which we have rights could require us to curtail or shut down mining production and could prevent us from pursuing expansion opportunities. Additionally, we have not yet secured adequate water rights to support all of our potential expansion projects, and our inability to secure those rights could prevent us from pursuing some of those opportunities.

### An interruption of energy supply could adversely affect our mining operations.

Our mining operations and development projects require significant amounts of energy. Our principal energy sources are electricity, purchased petroleum products, natural gas and coal. Our South America mining operations receive electrical power under long-term contracts with local energy companies. Our Africa development project, Tenke Fungurume, has entered into long-term power supply and infrastructure funding agreements with the state-owned electric utility company serving the Katanga province of the Democratic Republic of Congo. A disruption in the transmission of energy, inadequate energy transmission infrastructure, or the termination of any of our energy supply contracts could interrupt our energy supply and adversely affect our operations.

### Increased production costs could reduce our profitability and cash flow.

Energy represents a significant portion of our production costs. An inability to procure sufficient energy at reasonable prices could adversely affect our profits, cash flow and growth opportunities. Our production costs are also affected by the prices of commodities we consume or use in our operations, such as sulfuric acid, grinding media, steel, reagents, liners, explosives and diluents. The prices of such commodities are influenced by supply and demand trends affecting the mining industry in general and other factors outside our control and such prices are at times subject to volatile movements. Although our cash costs increased significantly in 2008, principally for energy and sulfuric acid, these costs began to decrease in the fourth quarter of 2008 as a result of the recent sharp declines in prices of energy, steel and sulfuric acid. Future increases in the cost of these commodities could make our operations less profitable. Increases in the costs of commodities that we consume or use may also significantly affect the capital costs of new projects.

***In addition to the usual risks encountered in the mining industry, our Indonesia operations involve additional risks because they are located on unusually difficult terrain in a very remote area.***

Our Grasberg mining operations are located in steep mountainous terrain in a very remote area in Indonesia. Because of these conditions, we have had to overcome special engineering difficulties and develop extensive infrastructure facilities. In addition, the area receives considerable rainfall, which has led to periodic floods and mudslides. The mine site is also in an active seismic area and has experienced earth tremors from time to time. Our insurance may not sufficiently cover an unexpected natural or operating disaster.

On October 9, 2003, a slippage of material occurred in a section of the Grasberg open pit, resulting in eight fatalities. On December 12, 2003, a debris flow involving a relatively small amount of loose material occurred in the same section of the open pit resulting in only minor property damage. The events caused us to alter our short-term mine sequencing plans, which adversely affected our 2003 and 2004 production. We resumed normal production activities in the second quarter of 2004.

On March 23, 2006, a mud/topsoil slide involving approximately 75,000 metric tons of material occurred from a mountain ridge above service facilities supporting PT Freeport Indonesia’s mining facilities. Regrettably, three contract workers were fatally injured in the event. The material damaged a mess hall and an adjacent area. As a result of investigations by PT Freeport Indonesia and the Indonesian Department of Energy and Mineral Resources, we conducted geotechnical studies to identify and address any potential hazards to workers and facilities from slides. The existing early warning system for potential slides, based upon rainfall and other factors, has also been expanded.

On September 10, 2008, a small scale failure encompassing approximately 75,000 metric tons of material occurred at our Grasberg open pit. There were no injuries or property damage. The event caused a delay in our access to the high-grade section of the open pit and, as a result, a portion of the metal expected to be mined in the second half of 2008 was deferred to future periods.

No assurance can be given that similar events will not occur in the future.

***Development projects are inherently risky and may require more capital than anticipated, which could adversely affect our business. In addition, our most significant development project, Tenke Fungurume, is located in a remote area of the Democratic Republic of Congo.***

There are many risks and uncertainties inherent in all development projects, including our significant future development of underground mines at the Grasberg minerals district and our Tenke Fungurume project. The economic feasibility of development projects is based on many factors, including the accuracy of estimated reserves, metallurgical recoveries, capital and operating costs and future prices of the relevant minerals. The capital expenditures and time required to develop new mines or other projects are considerable, and changes in costs or construction schedules can affect project economics. Thus it is possible that actual costs and economic returns may differ materially from our estimates.

New development projects have no operating history upon which to base estimates of future cash flow. These development projects also require the successful completion of feasibility studies, acquisition of governmental permits, acquisition of land, power and water and ensuring that appropriate community infrastructure is developed by third parties to support such projects. It is possible that we could fail to obtain the government approvals necessary for the operation of a project, in which case, the project may not proceed, either on its original timing or at all. It is not unusual for new mining operations to experience unexpected problems during the start-up phase, resulting in delays in producing revenue and increases in invested capital.

Our Tenke Fungurume project is located in a remote area of the Democratic Republic of Congo and is subject to additional challenges due to:

- severely limited infrastructure, including road and rail access;
- limited and possibly unreliable energy supply;
- security risks; and
- limited health care in an area plagued by disease and other potential endemic health issues, including malaria.

Consequently, our Tenke Fungurume development project may be substantially affected by factors beyond our control, which could increase the cost of the project and adversely affect its ultimate contribution to our operating results.

### Environmental risks

***Our domestic and international operations are subject to complex and evolving environmental laws and regulations, and compliance with environmental and regulatory requirements involves significant costs.***

Our ongoing mining operations and exploration activities, both in the U.S. and elsewhere, are subject to extensive laws and regulations governing exploration, development, production, occupational health, mine safety, toxic substances, waste disposal, protection and remediation of the environment, protection of endangered and protected species, and other related matters. Compliance with these laws and regulations imposes substantial costs and we expect these costs to continue to increase in the future because of increased regulatory enforcement, increased demand for remediation services and shortages of equipment, supplies, labor and other factors. The Federal Clean Air Act has had a significant impact, particularly on our domestic smelter and power plants. Any change in waste management regulation of the mining industry under the Federal Resource Conservation and Recovery Act could have a significant impact, both on operational compliance and closure costs. In addition, environmental laws and regulations may change in ways that could adversely affect our operations or expansion opportunities.

***In addition to compliance with environmental regulation at our operating sites, we incur significant costs for remediating environmental conditions on properties that have not been operated in many years.***

Phelps Dodge Corporation, now named Freeport-McMoRan Corporation, and many of its affiliates and predecessor companies have been involved in mining, milling, and manufacturing in the U.S. for more than a century. Activities that occurred in the late 19th century and the 20th century prior to the advent of modern environmental laws were not subject to environmental regulation and were conducted before American industrial companies understood the long-term effects of their operations on the surrounding environment. With the passage of CERCLA in 1980, companies like Phelps Dodge became legally responsible for environmental remediation on properties previously owned or operated by them, irrespective of when the damage to the environment occurred or who caused it. That liability is often shared on a joint and several basis with all other owners and operators, meaning that each owner or operator of the property is fully responsible for the clean-up, although in many cases some or all of the other historical owners or operators no longer exist, do not have the financial ability to respond or cannot be found. As a result, because of our acquisition of Phelps Dodge in 2007, many of the subsidiary companies we now own are responsible for a wide variety of environmental remediation projects throughout the U.S., and we expect to spend substantial sums annually for many years to address these remediation issues. We are also subject to claims where the release of hazardous substances is alleged to have damaged natural resources. As of December 31, 2008, we had more than 100 active remediation projects in the U.S. in approximately 25 states.

We incurred aggregate environmental capital expenditure and other environmental costs, including joint venture partners’ share, totaling $468 million in 2008, $320 million in 2007 and $63 million in 2006. Refer to Note 15 – “Contingencies” for more information on our environmental liabilities.

***An adverse ruling in one or more pending legal proceedings involving environmental matters could have a material adverse effect on us.***

As described in our Securities and Exchange Commission (SEC) filings, we are a defendant in numerous and in some cases significant litigation involving environmental cleanup costs, alleged environmental toxic torts and interpretations of environmental regulations. An adverse ruling in one or more of these matters could have a material adverse effect on our results of operations, financial condition and cash flow.

### Mine closure regulations impose substantial costs on our operations.

Our domestic operations are subject to various federal and state permitting requirements that include mine closure and mined-land reclamation obligations. These requirements are complex and vary depending upon the jurisdiction. The laws govern the determination of the scope and cost of the closure and reclamation obligations and the amount and forms of financial assurance sufficient to allow a third party to meet the obligations of those plans if we are unable to do so. In general, our domestic mines are required to review estimated closure and reclamation costs on either a periodic basis or at the time of significant permit modifications and post increasing amounts of financial assurance as required.

In addition, our international mines are subject to various mine closure and mined-land reclamation laws, and there have recently been significant changes in closure and reclamation programs in both Peru and Chile that impose more stringent obligations on us for closure and reclamation. Updated closure plans for our three Chilean operations were submitted to the government in February 2009.

Our asset retirement obligations as of December 31, 2008, determined as required by Statement of Financial Accounting Standards No. 143, “Asset Retirement Obligations,” totaled approximately $712 million (including approximately $42 million for the current portion). At December 31, 2008, we had accrued reclamation and closure costs of $372 million for our New Mexico operations, $164 million for our Arizona operations and $83 million for PT Freeport Indonesia. Asset retirement obligation cost estimates may increase or decrease significantly in the future as a result of changes in regulations, engineering designs and technology, permit modifications or updates, mine plans, cost of inflation or other factors and as actual reclamation spending occurs.

***Regulation of greenhouse gas emissions effects and climate change issues may adversely affect our operations and markets.***

Energy is a significant input to our mining and processing operations. Our principal energy sources are electricity, purchased petroleum products, natural gas and coal. Many scientists believe that emissions from the combustion of carbon-based fuels contribute to greenhouse effects and therefore potentially to climate change.

A number of governments or governmental bodies have introduced or are contemplating regulatory changes in response to the potential impacts of climate change. The December 1997 Kyoto Protocol established a set of greenhouse gas emission targets for developed countries that have ratified the Protocol. Although the Kyoto Protocol has not been ratified by the U.S., several states have initiated legislative action on climate change. Climate change legislation has been introduced in, but not yet passed by the U.S. Congress. Many believe that federal climate change legislation is very likely to become effective in the next few years, which will result in increased future energy and compliance costs. From a medium and long-term perspective, we are likely to see an increase in costs relating to our assets that emit significant amounts of greenhouse gases as a result of regulatory initiatives in the U.S. and other countries in which we operate. These regulatory initiatives will be either voluntary or mandatory and may impact our operations directly or through our suppliers or customers. Assessments of the potential impact of future climate change regulation are uncertain, given the wide scope of potential regulatory change in countries in which we operate.

The potential physical impacts of climate change on our operations are highly uncertain, and would be particular to the geographic circumstances. These may include changes in rainfall patterns, water shortages, changing sea levels, changing storm patterns and intensities, and changing temperatures. These effects may adversely impact the cost, production and financial performance of our operations.

***Our operating, inactive and historical domestic mining sites and facilities may be subject to future regulation of radioactive materials that are commonly associated with, or result from, our mining operations.***

A number of federal and state agencies are considering new regulations to characterize, regulate and remediate potential workplace exposures and environmental impacts of radioactive materials commonly associated with mining operations. For example, the EPA could promulgate rules to regulate technologically enhanced naturally occurring radioactive materials (TENORM) and their impacts at mining operations. In addition, several states are promulgating groundwater quality compliance and remediation standards for radioactive materials, including uranium. Radioactive materials can be associated with copper mineral deposits, including both our current and discontinued operations. Consequently, our copper operations may generate, concentrate or release radioactive materials that may subject our operations to new and increased regulation. The impact of such future regulation on our operating, closure, reclamation, and remediation costs is uncertain.

***Our mining operations in Indonesia create difficult and costly environmental challenges, and future changes in environmental laws, or unanticipated environmental impacts from those operations, could require us to incur increased costs.***

Mining operations on the scale of our operations in Papua involve significant environmental risks and challenges. Our primary challenge is to dispose of the large amount of crushed and ground rock material, called tailings, that results from the process by which we physically separate the copper-, gold- and silver-bearing materials from the ore that we mine. Our tailings management plan, which has been approved by the Government of Indonesia, uses the river system near our mine to transport the tailings to the lowlands where the tailings and natural sediments are deposited in a controlled area contained within an engineered levee system that will be revegetated.

Another major environmental challenge is managing overburden, which is the rock that must be moved aside in the mining process in order to reach the ore. In the presence of air, water and naturally occurring bacteria, some overburden can cause acid rock drainage, or acidic water containing dissolved metals which, if not properly managed, can have a negative impact on the environment.

Certain Indonesian governmental officials have from time to time raised issues with respect to our tailings and overburden management plans, including a suggestion that we implement a pipeline system rather than our river deposition system for tailings disposal. Because our mining operations are remotely located in steep mountainous terrain and in an active seismic area, a pipeline system would be costly, difficult to construct and maintain, and more prone to catastrophic failure, and could therefore involve significant potentially adverse environmental issues. Based on our own studies and others conducted by third parties, we do not believe that a pipeline system is necessary or practical.

In connection with obtaining our environmental approvals from the Indonesian government, we committed to perform a one-time environmental risk assessment on the impacts of our tailings management plan. We completed this extensive environmental risk assessment with more than 90 scientific studies conducted over four years and submitted it to the Indonesian government in December 2002. We developed the risk assessment study with input from an independent review panel, which included representatives from the Indonesian government, academia and non-governmental organizations. The risks that we identified during this process were in line with our impact projections of the tailings management program contained in our environmental approval documents.

In 2005, PT Freeport Indonesia agreed to participate in the Government of Indonesia’s PROPER (Program for Pollution Control, Evaluation and Rating) program. In March 2006, the Indonesian Ministry of Environment announced the preliminary results of its PROPER environmental management audit, acknowledging the effectiveness of PT Freeport Indonesia’s environmental management practices in some areas while making several suggestions for improvement in others.

### International risks

***Our operations outside of the U.S. are subject to political, social and geographic risks of doing business in foreign countries.***

We are a global mining company with substantial assets located outside of the U.S. We conduct international mining operations in Indonesia, Chile and Peru. We also have a significant development project in the Democratic Republic of Congo, which is expected to begin production in 2009. Accordingly, our business may be adversely affected by political, economic and social uncertainties in each of these countries, in addition to the usual risks associated with conducting business in foreign countries. Such risks include (1) forced modification of existing contracts, (2) expropriation, (3) changes in a country’s laws and policies, including those relating to labor, taxation, royalties, divestment, imports, exports, trade regulations, currency and environmental matters, (4) political instability and civil strife, (5) exchange controls, and (6) the risk of having to submit to the jurisdiction of a foreign court or arbitration panel or having to enforce the judgment of a foreign court or arbitration panel against a sovereign nation within its own territory. Our insurance does not cover most losses caused by these risks.

In December 2008, we were notified by Peruvian tax authorities of their intent to assess mining royalties related to the minerals processed by the Cerro Verde concentrator. The amount claimed to be due through December 2007 is approximately $33 million. We believe our royalty obligations with respect to all minerals extracted at Cerro Verde are subject to our existing stability agreement, regardless of the processing method applied after extraction, and believe that Cerro Verde owes no royalties with respect to minerals processed through our concentrator. We intend to work cooperatively with the authorities in Peru to resolve this matter.

***Because our Grasberg minerals district in Papua, Indonesia remains our most significant operating asset, our business may continue to be adversely affected by Indonesian political, economic and social uncertainties.***

Indonesia has faced political, economic and social uncertainties, including separatist movements and civil and religious strife in a number of provinces. In particular, several separatist groups are opposing Indonesian rule over the province of Papua, where our Grasberg minerals district is located, and have sought political independence for the province. In response, Indonesia enacted regional autonomy laws, which became effective January 1, 2001. The manner in which the new laws are being implemented and the degree of political and economic autonomy that they may bring to individual provinces, including Papua, are uncertain and are ongoing issues in Indonesian politics. In Papua, there have been sporadic attacks on civilians by separatists and sporadic but highly publicized conflicts between separatists and the Indonesian military. Social, economic and political instability in Papua could materially and adversely affect us if it results in damage to our property or interruption of our activities.

Maintaining a good working relationship with the Indonesian government is important to us because our mining operations there are among Indonesia’s most significant business enterprises and are conducted pursuant to a Contract of Work with the Indonesian government. Partially because of their significance to Indonesia’s economy, the environmentally sensitive area in which they are located, and the number of people employed, our operations are occasionally the subject of criticism in the Indonesian press and in political debates, and have been the target of protests and occasional violence. In October 2004, Susilo Bambang Yudhoyono was elected as President of Indonesia in the nation's first direct Presidential election. Indonesia has a Presidential election scheduled for July 2009. While we intend to continue to maintain positive working relationships with the Indonesian government, we cannot predict the impact that the 2009 elections will have on our relationships.

Grasberg operated at reduced mining and milling rates during a four-day period from April 18, 2007 to April 21, 2007, as a result of peaceful protests by certain workers regarding benefits. The protests ended on April 21 with an agreement on a framework for minimum wages for its workers and Grasberg returned to normal operations. The impacts to production were not significant. Illegal miners have continued to operate along the river designated to transport the tailings from the mill to the lowlands in PT Freeport Indonesia’s government-approved tailings management area. The illegal miners who have trespassed from time to time in the area of our facilities have clashed with police who have attempted to move them away from our facilities. In 2006, the illegal miners temporarily blocked the road leading to the Grasberg mine and mill in protest, and PT Freeport Indonesia temporarily suspended mining and milling operations as a precautionary measure.

We cannot predict whether additional incidents will occur that could disrupt our Indonesian operations, or whether similar incidents may occur in other countries that could affect our other operations. If additional protests or other disruptive incidents occur at any of our facilities, they could adversely affect our business and profitability in ways that we cannot predict at this time.

***We do not expect to mine all of our Indonesian ore reserves before the initial term of our Contract of Work in Indonesia expires.***

All of our Indonesian proven and probable ore reserves, including the Grasberg deposit, are located in Block A. The initial term of our Contract of Work covering these ore reserves expires at the end of 2021. We can extend this term for two successive 10-year periods, subject to the approval of the Indonesian government, which under our Contract of Work cannot be withheld or delayed unreasonably. Our ore reserves reflect estimates of minerals that can be recovered through the end of 2041 (i.e., through the expiration of the two 10-year extensions) and our current mine plan has been developed, and our operations are based on the assumption that we will receive the two 10-year extensions. As a result, we will not mine all of these ore reserves during the current term of our Contract of Work, and there can be no assurance that the Indonesian government will approve the extensions. Prior to the end of 2021, we expect to mine approximately 35 percent of aggregate proven and probable recoverable ore at December 31, 2008, representing approximately 42 percent of PT Freeport Indonesia’s share of recoverable copper reserves and approximately 56 percent of its share of recoverable gold reserves.

***Our Contracts of Work in Indonesia are subject to termination if we do not comply with our contractual obligations, and if a dispute arises, we may have to submit to the jurisdiction of a foreign court or arbitration panel.***

PT Freeport Indonesia’s Contract of Work and other Contracts of Work in which we have an interest were entered into under Indonesia’s 1967 Foreign Capital Investment Law, which provides guarantees of remittance rights and protection against nationalization. Our Contracts of Work can be terminated by the Government of Indonesia if we do not satisfy our contractual obligations, which include the payment of royalties and taxes to the government and the satisfaction of certain mining, environmental, safety and health requirements.

At times, certain government officials and others in Indonesia have questioned the validity of contracts entered into by the Government of Indonesia prior to May 1998 (i.e., during the Suharto regime, which lasted over 30 years), including PT Freeport Indonesia’s Contract of Work, which was signed in December 1991. We cannot assure you that the validity of, or our compliance with, the Contracts of Work will not be challenged for political or other reasons. PT Freeport Indonesia’s Contract of Work and our other Contracts of Work require that disputes with the Indonesian government be submitted to international arbitration. Consequently, if a dispute arises under the Contracts of Work, we face the risk of having to submit to the jurisdiction of a foreign court or arbitration panel, and if we prevail in such a dispute, we will face the additional risk of having to enforce the judgment of a foreign court or arbitration panel against Indonesia within its own territory.

Indonesian government officials have periodically undertaken reviews regarding our compliance with Indonesian environmental laws and regulations and the terms of the Contracts of Work. In 2006, the Government of Indonesia created a joint team for “Periodic Evaluation on Implementation of the PT-FI Contract of Work (COW)” to conduct an evaluation every five years. The team consists of five working groups, whose members are from relevant ministries or agencies, covering production, state revenues, community development, environmental issues and security issues. We have conducted numerous meetings with these groups. The joint team has indicated that it will issue a report. While we believe that we comply with PT Freeport Indonesia’s Contract of Work in all material respects, we cannot assure you that the report will support that conclusion. Separately, the Indonesian House of Representatives created a working committee on PT Freeport Indonesia. Members of this group have also visited our operations and held a number of hearings in Jakarta. We will continue to work with these groups to respond to their questions about our operations and our compliance with PT Freeport Indonesia’s Contract of Work.

***Any suspension of required activities under our Contracts of Work requires the consent of the Indonesian government.***

Our Contracts of Work permits us to suspend certain contractually required activities, including exploration, for a period of one year by making a written request to the Indonesian government. These requests are subject to the approval of the Indonesian government and are renewable annually. If we do not request a suspension or are denied a suspension, then we are required to continue our activities under the Contract of Work or potentially be declared in default. Moreover, if a suspension continues for more than one year for reasons other than force majeure and the Indonesian government has not approved such continuation, then the government would be entitled to declare a default under the Contract of Work.

We suspended our field exploration activities outside of Block A in recent years because of safety and security issues and regulatory uncertainty relating to a possible conflict between our mining and exploration rights in certain forest areas and an Indonesian Forestry law enacted in 1999 prohibiting open-pit mining in forest preservation areas. In 2001, we requested and received from the Government of Indonesia, formal temporary suspensions of our obligations under the Contracts of Work in all areas outside of Block A. Recent Indonesian legislation permits open-pit mining in PT Freeport Indonesia’s Block B area, subject to certain requirements. Following an assessment of these requirements and a review of security issues, in 2007 we resumed exploration activities in certain prospective Contract of Work areas outside of Block A.

***Our Tenke Fungurume development project is located in the Democratic Republic of Congo, and our business may be adversely affected by political, economic and social instability in the Democratic Republic of Congo.***

Our most significant development project, Tenke Fungurume, is located in the Democratic Republic of Congo, a nation that since 1960 has undergone outbreaks of political violence, changes in national leadership and financial crisis. These factors heighten the risk of abrupt changes in the national policy towards foreign investors, which in turn could result in unilateral modification of concessions or contracts, increased taxation, denial of permits or permit renewals or expropriation of assets. Our ability to continue development is currently subject to an ongoing review of all mining contracts by the Ministry of Mines (Ministry) in the Democratic Republic of Congo, the outcome of which cannot be predicted. We received notification on February 20, 2008 that the Ministry wishes to renegotiate several material provisions of our mining concessions. We believe that the terms of the concessions are fair and that they were negotiated transparently and are legally binding. However, we cannot predict whether the Government of the Democratic Republic of Congo will respect our contract rights. Other political, economic and social risks that are outside of our control and could adversely affect our business include:

- political risks associated with the limited tenure of the newly elected government;
- cancellation or renegotiation of mining contracts by the government;
- royalty and tax increases or claims by governmental entities, including retroactive claims;
- security risks due to the remote location and violence in the northeastern provinces of the Democratic Republic of Congo;
- risk of loss of property due to expropriation or nationalization of property; and
- risk of loss due to civil strife, acts of war, guerrilla activities, insurrection and terrorism.

Consequently, our Tenke Fungurume development project may be substantially affected by factors beyond our control, any of which could adversely affect our financial position or results of operations.

***Terrorist attacks throughout the world and the potential for additional future terrorist acts have created economic and political uncertainties that could materially and adversely affect our business.***

On August 31, 2002, three people were killed and 11 others were wounded in an ambush by a group of unidentified assailants on the road near Tembagapura, the mining town where the majority of PT Freeport Indonesia’s personnel reside. The assailants shot at several vehicles transporting international contract teachers from our school in Tembagapura, their family members and other contractors to PT Freeport Indonesia. The U.S. Federal Bureau of Investigation (FBI) investigated the incident, which resulted in the U.S. indictment of an alleged operational commander of the Free Papua Movement/National Freedom Force. In January 2006, Indonesian police, accompanied by FBI agents, arrested the alleged operational commander and 11 other Papuans. In November 2006, verdicts and sentencing were announced for seven of those accused in the August 2002 shooting, including a life sentence for the confessed leader of the attack.

On October 12, 2002, a bombing killed 202 people in the Indonesian province of Bali, which is 1,500 miles west of our mining and milling operations. Indonesian authorities arrested 35 people in connection with this bombing and 29 of those arrested have been tried and convicted. On August 5, 2003, 12 people were killed and over 100 were injured by a car bomb detonated outside of the JW Marriott Hotel in Jakarta, Indonesia. On September 9, 2004, 11 people were killed and over 200 injured by a car bomb detonated in front of the Australian embassy in Jakarta. On October 1, 2005, three suicide bombers killed 19 people and wounded over 100 in Bali. The same international terrorist organizations are suspected in each of these incidents. In November 2005, Indonesian police raided a house in East Java that resulted in the death of other accused terrorists linked to the bombings discussed above. Our mining and milling operations were not interrupted by these incidents, but PT Freeport Indonesia’s corporate office in Jakarta had to relocate for several months following the bombing in front of the Australian embassy. In addition to the Bali, JW Marriott Hotel and Australian embassy bombings, there have been anti-American demonstrations in certain sections of Indonesia reportedly led by radical Islamic activists.

No assurance can be given that additional terrorist incidents will not occur. If there were to be additional violence, it could materially and adversely affect our business in ways that we cannot predict at this time.

### Other risks

***If market prices for our commodities decline, the carrying values of inventories and long-lived assets may be further impaired, which could require charges to operating income that could be material.***

In the fourth quarter of 2008, we recorded significant charges to reduce the carrying values of inventories and long-lived assets, and to eliminate goodwill. Further declines in the market price of copper, among other factors, may cause us to record additional lower of cost or market inventory adjustments and may also require us to further write down the carrying value of long-lived assets, which would potentially have a material adverse impact on our results of operations and shareholders' equity, but would have no effect on cash flows.

***Unanticipated litigation or negative developments in pending litigation could have a material adverse effect on our results of operations and financial condition.***

We are a party to the litigation described in our SEC filings and a number of other litigation matters, including asbestos exposure cases, disputes over the allocation of environmental remediation obligations at Superfund and other sites, disputes over water rights and disputes with regulatory authorities. The outcome of litigation is inherently uncertain and adverse developments or outcomes can result in significant monetary damages, penalties or injunctive relief against us, limitations on our property rights, or regulatory interpretations that increase our operating costs. If any of these disputes results in a substantial monetary judgment against us or an adverse legal interpretation, is settled on unfavorable terms, or otherwise affects our operations, it could have a material adverse effect on our operating results and financial condition.

***We depend on our senior management team and other key employees, and the loss of any of these employees could adversely affect our business.***

Our success depends in part on our ability to attract, retain and motivate senior management and other key employees. Achieving this objective may be difficult due to many factors, including fluctuations in global economic and industry conditions, competitors’ hiring practices, cost reduction activities, and the effectiveness of our compensation programs. Competition for qualified personnel can be very intense. We must continue to recruit, retain and motivate senior management and other key employees sufficient to maintain our current business and support our future projects. A loss of such personnel could prevent us from capitalizing on business opportunities, and our operating results could be adversely affected.

#### Our holding company structure may impact your ability to receive dividends.

We are a holding company with no material assets other than the capital stock of our subsidiaries. As a result, our ability to repay our indebtedness and pay dividends is dependent on the generation of cash flow by our subsidiaries and their ability to make such cash available to us, by dividend, loan, debt repayment or otherwise. Our subsidiaries do not have any obligation to make funds available to us to repay our indebtedness or pay dividends. Dividends from subsidiaries that are not wholly owned are shared with other equity owners. In addition, cash at our international operations is subject to foreign withholding taxes upon repatriation into the U.S.

In addition, our subsidiaries may not be able to, or be permitted to, make distributions to enable us to repay our indebtedness or pay dividends. Each of our subsidiaries is a distinct legal entity and, under certain circumstances, legal and contractual restrictions, as well as the financial condition and operating requirements of our subsidiaries, may limit our ability to obtain cash from our subsidiaries. Our rights to participate in any distribution of our subsidiaries’ assets upon their liquidation, reorganization or insolvency would generally be subject to the prior claims of the subsidiaries’ creditors, including any trade creditors and preferred stockholders.

***Anti-takeover provisions in our charter documents and Delaware law may make an acquisition of us more difficult.***

Anti-takeover provisions in our charter documents and Delaware law may make an acquisition of us more difficult. These provisions:

- authorize our board of directors to issue preferred stock without stockholder approval and to designate the rights, preferences and privileges of each class; if issued, such preferred stock would increase the number of outstanding shares of our capital stock and could include terms that may deter an acquisition of us;
- establish advance notice requirements for nominations to the board of directors or for proposals that can be acted on at stockholder meetings;
- limit who may call stockholder meetings; and
- require the approval of the holders of two thirds of our outstanding common stock to enter into certain business combination transactions, subject to certain exceptions, including if the consideration to be received by our common stockholders in the transaction is deemed to be a fair price.

These provisions may discourage potential takeover attempts, discourage bids for our common stock at a premium over market price or adversely affect the market price of, and the voting and other rights of the holders of, our common stock. These provisions could also discourage proxy contests and make it more difficult for stockholders to elect directors other than the candidates nominated by our board of directors.

In addition, because we are incorporated in Delaware, we are governed by the provisions of Section 203 of the Delaware General Corporation Law, which may prohibit large stockholders from consummating a merger with, or acquisition of, us.

These provisions may deter an acquisition of us that might otherwise be attractive to stockholders.

## Legal proceedings

As filed, 10,935 characters.

We are involved from time to time in various legal proceedings of a character normally incident to the ordinary course of our business. We believe that potential liability in such proceedings would not have a material adverse effect on our financial condition or results of operations. We maintain liability insurance to cover some, but not all, potential liabilities normally incident to the ordinary course of our business as well as other insurance coverage customary in our business, with coverage limits that we deem prudent.

### Environmental Proceedings

Pinal Creek. We are a party to Pinal Creek Group, et al. v. Newmont Mining Corporation, et al., United States District Court, District of Arizona, Case No. CIV 91-1764 PHX DAE (LOA), filed on May 1, 1991. The Pinal Creek site located near Miami, Arizona, was listed under the Arizona Department of Environmental Quality’s (ADEQ) Water Quality Assurance Revolving Fund program in 1989 for contamination in the shallow alluvial aquifers within the Pinal Creek drainage near Miami, Arizona. Since that time, environmental remediation has been performed by members of the Pinal Creek Group (PCG), consisting of Phelps Dodge Miami, Inc. (Miami) (a wholly owned subsidiary of Freeport-McMoRan Corporation, formerly Phelps Dodge Corporation) and two other companies. In 1998, the District Court approved a Consent Decree between the PCG members and the state of Arizona resolving all matters related to an enforcement action contemplated by the state of Arizona against the PCG members with respect to groundwater. The Consent Decree committed the PCG members to complete the remediation work outlined in the Consent Decree. That work continues at this time pursuant to the Consent Decree and consistent with state law and the National Contingency Plan prepared by the U.S. Environmental Protection Agency (EPA) under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).

Remediation has been proceeding pursuant to an interim allocation of cost sharing among the members of the PCG, with Miami’s interim allocation being approximately two-thirds; however, there are significant disagreements among the members of the PCG regarding the allocation of the cost of remediation, and other members allege that Miami should be responsible for substantially all of the costs. Discovery disputes resulted in a sanctions order against Miami that included significant evidentiary restrictions on Miami’s case. The trial on the allocation issue will be scheduled after the final determination of Miami’s pending interlocutory appeal of a trial court ruling on the liability standard that should apply to one of the remaining defendants. A final determination of the allocation, if different from the interim allocation, would likely result in a “true up” payment with respect to the remediation that has already been completed from the party found to be responsible for a higher proportion than the interim allocation, and would establish the cost-sharing proportions for the remainder of the clean up. The overall cost of the clean up is expected to be significant.

Blackwell, Oklahoma Litigation. On April 14, 2008, a purported class action was filed in the District Court of Kay County, Oklahoma against us, and several direct and indirect subsidiaries, including Blackwell Zinc Company (BZC), and several other parties, entitled Coffey, et al., Plaintiffs, v. Freeport-McMoRan Copper & Gold, Inc., et al., Defendants, Kay County, Oklahoma District Court, Case No. CJ-2008-68. The suit alleges that the operations of BZC’s zinc smelter in Blackwell, Oklahoma, from 1918 to 1974 resulted in contamination of the soils and groundwater in Blackwell and the surrounding area. Unspecified compensatory and punitive damages are sought on behalf of the putative class members for alleged diminution in property values. There is also a request for an order compelling remediation of alleged contaminated properties and the establishment of a monetary fund to monitor the present and future health of the putative class members. We intend to defend this matter vigorously. For more information about our remediation activities in Blackwell, Oklahoma, refer to Note 15 – “Contingencies – Environmental and Asset Retirement Obligations.”

Arizona Notice of Violation (NOV) – Sierrita operations. In September and October 2006, ADEQ issued two NOVs to the Phelps Dodge Sierrita, Inc. (Sierrita) operations in southeastern Arizona. The two NOVs alleged certain visibility and permit violations associated with dust emissions from Sierrita’s tailing facility during high-wind events. Sierrita responded to the NOVs by acknowledging that dust likely did exceed a visibility standard, but denying the other allegations, and by implementing dust control response actions that ADEQ has accepted. In January 2009, Sierrita and ADEQ agreed to a consent decree that will be entered in court to settle the matter. The consent decree obligates Sierrita to pay a $45,000 fine and $60,000 for a supplemental environmental project.

New Mexico Environment Department – Chino Mines. On October 24, 2007, Chino Mines Co. (Chino) notified New Mexico Environment Department (NMED) that heavy rains during July, August and September led to a release of diluted leach solutions through a storm water outfall to an ephemeral stream on Chino’s property. Chino sent a follow up notice to NMED on November 7, 2007, which identified the interim corrective actions taken as a result of the discharge. On February 28, 2008, Chino received a proposed Administrative Compliance Order, which included a demand for civil penalties in the amount of $276,600 for violation of legal requirements in connection with Chino’s management of the solutions. Chino is engaged in settlement discussions with NMED.

### Asbestos Claims

Since approximately 1990, Phelps Dodge and various subsidiaries have been named as defendants in a large number of product liability or premises lawsuits claiming injury from exposure to asbestos contained in electrical wire products produced or marketed many years ago, or from asbestos at certain Phelps Dodge properties. Based on information available to us to date, we believe our liability, if any, in these matters will not have a material adverse effect, either individually or in the aggregate, upon our business, financial condition, liquidity, results of operations or cash flow. There can be no assurance, however, that future developments will not alter this conclusion.

### Water Rights

Water law in the western U.S. is generally based on the doctrine of prior appropriation (first in time, first in right) and permits the water right holder the right to use public waters for a statutorily defined beneficial use, at a designated location. Our operations in the western U.S. require water for mining, ore processing and related support facilities. Continuous operation of these mines is dependent on our ability to maintain our water rights and claims. The loss of water rights, in whole or in part, could have a significant adverse affect on our mining operations.

Two water rights adjudications have been initiated in the State of Arizona in order to quantify and prioritize all surface water claims in two of the State’s river systems that include three of our operating mines: Morenci, Sierrita and Safford and which may affect our Bagdad, Arizona mine. These adjudications have proceeded for many years, and we cannot predict when they will be concluded, but the loss of water claims in these legal proceedings could have a significant adverse affect on the operations of these mines.

In Re the General Adjudication of All Rights to Use Water in the Little Colorado Water System and Sources, Apache County, Superior Court, No. 6417, filed on or about February 17, 1978. The principal parties, in addition to us, include: the State of Arizona; the Salt River Project; the Arizona Public Service Company; the Navajo Nation, the Hopi Indian Tribe; the San Juan Southern Paiute Tribe; and the United States on its own behalf, on behalf of those Indian tribes, and on behalf of the White Mountain Apache Tribe.

In Re The General Adjudication of All Rights to Use Water in the Gila River System and Sources,

Maricopa County, Superior Court, Cause Nos. W-1 (Salt), W-2 (Verde), W-3 (Upper Gila), and W-4 (San Pedro), filed on February 17, 1978. The principal parties, in addition to us, include: the State of Arizona; the Gila Valley Irrigation District; the San Carlos Irrigation and Drainage District; the Salt River Project; the San Carlos Apache Tribe; the Gila River Indian Community; and the United States on behalf of those Tribes, on its own behalf, and on behalf of the White Mountain Apache Tribe, the Fort McDowell Mohave-Apache Indian Community, the Salt River Pima-Maricopa Indian Community, and the Payson Community of Yavapai Apache Indians.

In 1998, we entered into a water rights settlement agreement with the Gila River Indian Community (GRIC), which was later included in a comprehensive water rights settlement under the Arizona Water Settlements Act of 2004. The GRIC settlement is subject to contingencies that must be met before the agreement is fully effective, and the comprehensive settlement has been challenged by other parties. If we are unable to resolve the contingencies in the GRIC settlement and defeat the third-party challenges, our water rights in the Gila River watershed could be diminished, and our operations at Morenci, Sierrita and Safford could be adversely affected.

Prior to January 1, 1983, various Indian tribes filed suits in the U.S. District Court in Arizona claiming superior rights to water being used by many other water users, including us, and claiming damages for prior use in derogation of their allegedly superior rights. These federal proceedings have been stayed pending the Arizona

Superior Court adjudications.

United States v. Gila Valley Irrigation District, United States District Court, District of Arizona, was initiated in 1925 by the United States to settle conflicting claims to water rights in portions of the Gila River watershed. A decree settling the claims of various parties was entered in 1935, after Morenci had been dismissed from the case without prejudice. In 1988, the Gila River Indian Community intervened, challenging uses of water in the Gila River watershed, which may impact water that we have the right to divert annually from Eagle Creek, Chase Creek or the San Francisco River for operation of our Morenci mine, pursuant to decreed rights and an agreement between us and the Gila Valley Irrigation District. Our Morenci operations also purchased farm lands with water rights in 1997, 1998 and 2008 that are subject to this proceeding. Impairment of our water claims in the Gila River watershed could adversely affect the operations of our Morenci and Safford mines.

## Controls and procedures

As filed, 1,014 characters.

(a) Evaluation of disclosure controls and procedures. Our chief executive officer and chief financial officer, with the participation of management, have evaluated the effectiveness of our “disclosure controls and procedures” (as defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934) as of the end of the period covered by this annual report on Form 10-K. Based on their evaluation, they have concluded that our disclosure controls and procedures are effective as of the end of the period covered by this report.

(b) Changes in internal controls. There has been no change in our internal control over financial reporting that occurred during the fourth quarter that has materially affected, or is reasonably likely to materially affect our internal control over financial reporting.

(c) Management’s annual report on internal control over financial reporting and the report thereon of Ernst & Young LLP are included herein under Item 8. “Financial Statements and Supplemental Data.”

Filed Feb 26, 2009.