# Freeport-Mcmoran Inc: Form 10-K for the period ended Dec 31, 2009

- Company: [Freeport-Mcmoran Inc](/companies/fcx.md) (CIK 831259)
- Form: 10-K
- Filed: 2010-02-26
- Accepted by EDGAR: Feb 26, 2010, 20:12 ET
- Period: 2009-12-31
- Accession: 0000831259-10-000010
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/831259/000083125910000010/fcx123109-10k.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/831259/000083125910000010/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2009-12-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Cost of revenue | 12 months, 2009-01-01 to 2009-12-31 | $8.05bn | us-gaap:CostOfRevenue |
| Selling, general and administrative | 12 months, 2009-01-01 to 2009-12-31 | $321.0m | us-gaap:SellingGeneralAndAdministrativeExpense |
| Operating income | 12 months, 2009-01-01 to 2009-12-31 | $6.50bn | us-gaap:OperatingIncomeLoss |
| Income tax | 12 months, 2009-01-01 to 2009-12-31 | $2.31bn | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 12 months, 2009-01-01 to 2009-12-31 | $3.53bn | us-gaap:ProfitLoss |
| Diluted EPS | 12 months, 2009-01-01 to 2009-12-31 | $5.86 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 12 months, 2009-01-01 to 2009-12-31 | $6.10 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 12 months, 2009-01-01 to 2009-12-31 | 469,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 12 months, 2009-01-01 to 2009-12-31 | $4.40bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Dividends paid | 12 months, 2009-01-01 to 2009-12-31 | $0 | us-gaap:PaymentsOfDividendsCommonStock |
| Share repurchases | 12 months, 2009-01-01 to 2009-12-31 | $0 | us-gaap:PaymentsForRepurchaseOfCommonStock |
| Cash and equivalents | at 2009-12-31 | $2.66bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2009-12-31 | $7.43bn | us-gaap:AssetsCurrent |
| Total assets | at 2009-12-31 | $26.00bn | us-gaap:Assets |
| Current liabilities | at 2009-12-31 | $3.00bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2009-12-31 | $15.24bn | us-gaap:Liabilities |
| Long-term debt | at 2009-12-31 | $6.33bn | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2009-12-31 | $16.0m | us-gaap:DebtCurrent |
| Shareholders' equity | at 2009-12-31 | $9.12bn | us-gaap:StockholdersEquity |

## Risk factors

As filed, 78,748 characters.

*This report contains “forward-looking statements” within the meaning of the federal securities laws. Forward-looking statements are all statements other than statements of historical facts, such as statements regarding anticipated production volumes, unit net cash costs, sales volumes, ore grades, milling rates, commodity prices, development and capital expenditures, mine production and development plans, availability of power, water, labor and equipment, environmental reclamation and closure costs and plans, environmental liabilities and expenditures, litigation expense and results, dividend payments, reserve estimates, exploration efforts and results, operating cash flows, copper, gold, molybdenum and cobalt price changes, deferred intercompany profit impacts on financial results, and anticipated political, economic and social conditions in our areas of operations. We undertake no obligation, to update or revise any forward-looking statements. Readers are cautioned that forward-looking statements are not guarantees of future performance and actual results may differ materially from those projected, anticipated or assumed in the forward-looking statements. Important factors that could cause our actual results to differ materially from those anticipated in the forward-looking statements include the following.*

### Financial risks

***Extended declines in the market prices of copper, gold and/or molybdenum could adversely affect our earnings and cash flows and, if sustained, could adversely affect our ability to repay debt. Fluctuations in the market prices of copper, gold or molybdenum can cause significant volatility in our financial performance and adversely affect the trading prices of our debt and equity securities.***

Our earnings and cash flows are affected significantly by the market prices of copper and, to a lesser extent, gold and molybdenum. The world market prices of these commodities have fluctuated historically and are affected by numerous factors beyond our control. For information about movements in the market prices of these commodities, refer to Item 7. “Management’s Discussion and Analysis of Financial Condition and Results of Operations – Copper, Gold and Molybdenum Markets.” An extended decline in the market prices of these commodities could (1) adversely affect our earnings and cash flows, (2) adversely affect our ability to repay our debt and meet our other fixed obligations, and (3) depress the trading prices of our common and preferred stock and of our publicly traded debt securities.

In addition, substantially all of our copper concentrate sales and some of our copper cathode sales are provisionally priced at the time of shipment. The provisional prices are finalized in a contractually specified future period (generally one to four months from the shipment date) based primarily on quoted London Metal Exchange (LME) prices. Accordingly, in times of falling copper prices, our revenues are negatively affected by lower prices received for contracts priced at current market rates and also from a decrease related to the final pricing of provisionally priced sales pursuant to contracts entered into in prior periods; in times of rising copper prices, the opposite occurs.

There continues to be uncertainty in the global economy, which could negatively affect the market prices of commodities, including the metals that we produce. If market prices for the metals we produce decline for a sustained period of time, we may have to revise our operating plans, including curtailing production, reducing operating costs and capital expenditures and discontinuing certain exploration and development programs. We may be unable to decrease our costs in an amount sufficient to offset reductions in revenues, and may incur losses.

World copper prices have historically fluctuated widely. During the three years ended December 31, 2009, LME daily closing spot prices ranged from $1.26 to $4.08 per pound for copper. The LME spot copper price closed at $3.11 per pound on January 29, 2010. World copper prices are affected by numerous factors beyond our control, including:

- the strength of the U.S. economy and the economies of other industrialized and developing nations, including China, which has become the largest consumer of refined copper in the world;
- available supplies of copper from mine production and inventories;
- sales by holders and producers of copper;
- demand for industrial products containing copper;
- investment activity, including speculation, in copper as a commodity;
- the availability and cost of substitute materials; and
- currency exchange fluctuations, including the relative strength or weakness of the U.S. dollar.

World gold prices have historically fluctuated widely. During the three years ended December 31, 2009, the daily closing prices on the London spot market ranged from $608 to $1,213 per ounce for gold. London gold prices closed at $1,079 per ounce on January 29, 2010. World gold prices are affected by numerous factors beyond our control, including:

- the strength of the U.S. economy and the economies of other industrialized and developing nations, including China;
- global or regional political or economic crises;
- the relative strength or weakness of the U.S. dollar and other currencies;
- expectations with respect to the rate of inflation;
- interest rates;
- purchases and sales of gold by governments, central banks and other holders;
- demand for jewelry containing gold; and
- investment activity, including speculation, in gold as a commodity.

Molybdenum prices also fluctuate widely. Molybdenum demand depends primarily on the global steel industry, which uses the metal as a hardening and corrosion inhibiting agent. Approximately 80 percent of molybdenum production is used in this application. The remainder is used in specialty chemical applications such as catalysts, water treatment agents and lubricants. Approximately 50 percent of global molybdenum production is a by-product of copper mining, which is relatively insensitive to molybdenum prices. During the three years ended December 31, 2009, the *Metals Week* Dealer Oxide weekly average price for molybdenum ranged from $7.83 to $33.88 per pound. The *Metals Week* Molybdenum Dealer Oxide weekly average price was $14.88 per pound on January 29, 2010. Molybdenum prices are affected by numerous factors beyond our control, including:

- the worldwide balance of molybdenum demand and supply;
- rates of global economic growth, especially construction and infrastructure activity that requires significant amounts of steel;
- the volume of molybdenum produced as a by-product of copper production;
- inventory levels;
- currency exchange fluctuations, including the relative strength or weakness of the U.S. dollar; and
- production costs of U.S. and foreign competitors.

***The agreements governing our indebtedness require us to meet certain financial tests and other covenants and as a result may limit our flexibility in the operation of our business and our ability to pay dividends on our common stock.***

We incurred significant debt to fund a portion of the cash consideration paid to acquire Phelps Dodge Corporation (Phelps Dodge). As of December 31, 2009, the outstanding principal amount of our indebtedness was $6.3 billion. The agreements governing our indebtedness restrict, subject to certain exceptions, our ability to:

- incur additional indebtedness;
- engage in transactions with affiliates;
- create liens on our assets;
- make payments in respect of equity issued by us or our subsidiaries, including the payment of dividends on our common stock;
- make investments in, or loans, to entities that we do not control, including joint ventures;
- sell assets;
- merge with or into other companies;
- enter into sale and leaseback transactions;
- enter into unrelated businesses;
- enter into agreements or arrangements that restrict the ability of certain of our subsidiaries to pay dividends or other distributions;
- prepay indebtedness; and
- enter into hedging transactions other than in the ordinary course of business.

In April 2008, Standard & Poor’s Rating Services (S&P) and Fitch Ratings raised our corporate credit rating and the ratings on our unsecured debt to BBB- (investment grade). As a result of the upgrade of our unsecured debt to investment grade by S&P, the restrictions contained in our 8.375%, 8.25% and floating rate senior notes on incurring debt, making restricted payments and selling assets were suspended.

In addition, our senior revolving credit facilities require that we meet certain financial tests at any time that borrowings are outstanding under these facilities, including a leverage ratio test (Total Debt to Consolidated EBITDA, as those terms are defined in the facility, for the preceding four quarters cannot exceed 5.0 to 1.0 on the last day of any fiscal quarter) and a secured leverage ratio test (Total Secured Debt to Consolidated EBITDA, as those terms are defined in the facility, for the preceding four quarters cannot exceed 3.0 to 1.0 on the last day of any fiscal quarter). During periods in which copper, gold or molybdenum prices or production volumes, or other conditions reflect the adverse impact of cyclical market trends or other factors, we may not be able to comply with the applicable financial covenants.

Our senior revolving credit facilities and our 8.375%, 8.25% and floating rate senior notes contain covenants that limit our ability to make certain payments. These restrictions vary among the instruments, but generally limit our ability to pay certain dividends on common and preferred stock, repurchase or redeem common and preferred equity, prepay subordinated debt and make certain investments. To the extent the rating is downgraded below investment grade, these covenants in our 8.375%, 8.25% and floating rate senior notes would again become effective. At December 31, 2009, the most restrictive of these covenants related to restricted payments allowed for payments up to approximately $7.6 billion.

Our obligations under our senior credit facilities are (1) guaranteed by substantially all of our domestic subsidiaries and (2) secured by a pledge of (a) 100 percent of the equity in substantially all of our domestic subsidiaries and (b) 66.5 percent of the equity in substantially all of our first tier foreign subsidiaries.

Any failure to comply with the restrictions of our senior credit facilities, senior notes or any agreement governing our other indebtedness, after giving effect to any applicable grace period, may result in an event of default. Such default may allow the creditors to accelerate the related debt, which may trigger cross-acceleration or cross-default provisions in other debt agreements. We would not be able to fully repay when due borrowings under our debt instruments that are accelerated upon an event of default.

If we are unable to repay, refinance or restructure our indebtedness under, or amend the covenants contained in, our senior credit agreements at maturity or in the event of a default, the lenders under our senior credit facilities could terminate their commitments thereunder, cease making further loans, declare all borrowings outstanding (together with accrued interest and other fees) immediately due and payable and institute foreclosure proceedings against the collateral. Any such actions could negatively affect our financial condition and results of operations.

***Under U.S. federal and state laws that require closure and reclamation plans for our mines, we are required to provide financial assurance sufficient to allow a third party to implement those plans if we are unable to do so. The U.S. Environmental Protection Agency (EPA) and state agencies may seek financial assurance for investigation and remediation actions taken under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) or equivalent state regulations. The failure to comply with these requirements could have a material adverse effect on us.***

We are required by U.S. federal and state laws to provide financial assurance sufficient to allow a third party to implement approved closure and reclamation plans if we are unable to do so. These laws are complex and vary from jurisdiction to jurisdiction. The laws govern the determination of the scope and cost of the closure and reclamation obligations and the amount and forms of financial assurance.

In July 2009, EPA published a Priority Notice of Action identifying classes of facilities within the hardrock mining industry for which the agency will develop financial responsibility requirements. It is uncertain how the new requirements will affect the amount and form of our existing and future financial assurance obligations.

As of December 31, 2009, our financial assurance obligations associated with closure and reclamation costs totaled approximately $710 million, of which approximately $414 million was in the form of parent company guarantees and financial capability demonstrations. Our ability to continue to provide financial assurance in the form of parent guarantees and financial capability demonstrations in New Mexico and Arizona depends on our ability to meet financial tests. Certain of the ratios in these tests are significantly more rigorous for companies that do not have an investment grade rating from a state-approved ratings service. We are currently rated investment grade by Standard & Poor’s and Fitch, but are not rated investment grade by Moody’s. If we fail to maintain our investment grade rating, we would be subject to these alternate tests, in which case, the regulatory agencies may require us to provide alternative forms of financial assurance to fully satisfy our financial assurance obligations, such as letters of credit, surety bonds or collateral. Depending on our financial condition and market conditions, these other forms of financial assurance may be difficult or costly to provide. Issuance of letters of credit under our credit facilities would reduce our available liquidity. Failure to provide the required financial assurance could result in the closure of mines. As of December 31, 2009, we have limited financial assurance obligations associated with CERCLA-related actions, although EPA and certain states are currently considering increasing the use of financial assurance requirements. For additional information, see the risk factor “Mine closure regulations impose substantial costs on our operations” below.

***We need significant amounts of cash to service our debt. If we are unable to generate sufficient cash to service our debt, our financial condition and results of operations could be negatively affected.***

As of December 31, 2009, the outstanding principal amount of our debt was $6.3 billion. We must generate sufficient amounts of cash to service and repay our debt. Our ability to generate cash will be affected by general economic, financial, competitive, legislative, regulatory and other factors that are beyond our control. Future borrowings may not be available to us under our senior credit facilities or from the capital markets in amounts sufficient to pay our obligations as they mature or to fund other liquidity needs. In addition, disruptions in the credit and financial markets, such as those beginning in late 2008, can constrain our access to capital and increase its cost. The inability to service, repay or refinance our indebtedness could negatively affect our financial condition and results of operations.

If future financing is not available to us when required, as a result of limited access to the credit markets or otherwise, or is not available on acceptable terms, we may be unable to invest needed capital for our development and exploration programs, take advantage of business opportunities or respond to competitive pressures, any of which could have an adverse effect on our operating results and financial condition.

***Movements in foreign currency exchange rates or interest rates could negatively affect our operating results.***

Substantially all of our revenues and a significant portion of our costs are denominated in U.S. dollars; however, some costs, and certain asset and liability accounts are denominated in local currencies, including the Indonesian rupiah, Australian dollar, Chilean peso, Peruvian nuevos sol and euro. As a result, our results are adversely affected when the U.S. dollar weakens in relation to those foreign currencies.

At December 31, 2009, approximately 19 percent of our outstanding debt was subject to variable interest rates. Increases in these rates will increase our interest costs and reduce our profits and operating cash flows.

From time to time, we may implement currency or interest rate hedges intended to reduce our exposure to changes in foreign currency exchange or interest rates. However, our hedging strategies may not be successful, and any of our unhedged foreign exchange or interest payments will continue to be subject to market fluctuations.

### Operational risks

***The volume and grade of ore reserves that we recover and our rate of production may be more or less than anticipated.***

Our ore reserve amounts are determined in accordance with established mining industry practices and standards, and are estimates of the mineral deposits that can be recovered economically and legally based on currently available data. Estimates of recoverable proven and probable reserves are subject to considerable uncertainty. Ore bodies may not conform to standard geological expectations, and estimates may change as new data becomes available. Because ore bodies do not contain uniform grades and types of minerals, our metal recovery rates will vary from time to time.

Additionally, because the determination of reserves is based partially on estimates of future selling prices, a sustained decrease in such prices may result in a reduction in economically recoverable ore reserves. These factors may result in variations in the volumes of mineral reserves that we report from period to period.

There are also uncertainties inherent in estimating quantities of ore reserves and copper recovered from stockpiles. The quantity of copper contained in mill and leach stockpiles is based on surveyed volumes of mined material and daily production records. The volume and grade of ore reserves recovered, rates of production and recovered copper from stockpiles may be less than anticipated.

***We must continually replace reserves depleted by production. Our exploration activities may not result in additional discoveries.***

Our ability to replenish our ore reserves is important to our long-term viability. Produced ore reserves must be replaced by further delineation of existing ore bodies or by locating new deposits in order to maintain production levels over the long term. Open-pit operations at Grasberg are expected to continue through mid 2016, at which time underground mining operations are scheduled to begin at our Grasberg Block Cave mine, which is under development. Production at the DOZ mine is expected to continue through 2020 and we plan to ramp up production at our Deep Mill Level Zone (DMLZ) block cave mine, which is currently under development, beginning in 2015. In addition, oxide copper production at El Abra is expected to decline over the next several years and production from the sulfide ore is expected to begin in 2012.

Exploration is highly speculative in nature. Our exploration projects involve many risks, require substantial expenditures and may not result in the discovery of sufficient additional mineral deposits that can be mined profitably. Once a site with mineralization is discovered, it may take several years from the initial phases of drilling until production is possible, during which time the economic feasibility of production may change. Substantial expenditures are required to establish recoverable proven and probable reserves and to construct mining and processing facilities. As a result, there is no assurance that current or future exploration programs will be successful. There is a risk that depletion of reserves will not be offset by discoveries or acquisitions.

***Development projects are inherently risky and may require more capital than anticipated, which could adversely affect our business.***

There are many risks and uncertainties inherent in all development projects, including our significant future development of underground mines at the Grasberg minerals district and our development of a large sulfide deposit at El Abra. The economic feasibility of development projects is based on many factors, including the accuracy of estimated reserves, metallurgical recoveries, capital and operating costs and future prices of the relevant minerals. The capital expenditures and time required to develop new mines or other projects are considerable, and changes in costs or construction schedules can affect project economics. Moreover, underground mining is generally more expensive than surface mining as a result of higher capital costs, including costs for modern mining equipment and construction of extensive ventilation systems. Thus it is possible that actual costs and economic returns may differ materially from our estimates.

New development projects have no operating history upon which to base estimates of future cash flow. These development projects also require the successful completion of feasibility studies, acquisition of governmental permits, acquisition of land, power and water, and ensuring that appropriate community infrastructure is developed by third parties to support such projects. It is possible that we could fail to obtain the government approvals necessary for the operation of a project, in which case, the project may not proceed, either on its original timing or at all. It is not unusual for new mining operations to experience unexpected problems during the start-up phase, resulting in delays in producing revenue and increases in invested capital.

The development of underground mines is subject to additional risks, including the following:

- Unanticipated geologic, geotechnical and hydrogeologic conditions;
- Challenges related to hiring and training the personnel required for the ramp-up in underground mining activities;
- Larger than expected dilution of ore associated with block caving and stoping mining methods; and
- Unanticipated delays in the development of major access and supporting infrastructure due to engineering changes, late delivery of critical components and longer than planned construction periods.

Some of these risks could result in a delay to production start-up and a loss or reduction in minable tons. There can be no assurance that the occurrence of such events or conditions would not have a material adverse impact on our business and results of operations.

***Our business is subject to operational risks that could adversely affect our business.***

Mines by their nature are subject to many operational risks, some of which are outside of our control. These operational risks, which could adversely affect our business, operating results and cash flows, include the following:

- earthquakes, floods and other natural disasters;
- the occurrence of unusual weather or operating conditions and other force majeure events;
- the failure of equipment or processes to operate in accordance with specifications, design or expectations;
- accidents;
- wall failures and rock slides in our open pit mines, and structural collapses in our underground mines;
- problems associated with the construction and management of large impoundments containing tailings or other viscous or semi-solid materials, some of which also contain mineral and chemical contaminants, such as structural failures or leakages;
- interruption of energy supply;
- lower than expected ore grades or recovery rates;
- metallurgical and other processing problems;
- unanticipated ground and water conditions;
- adverse claims to water rights and shortages of water to which we have rights;
- adjacent land ownership or usage that results in constraints on current or future mine operations;
- delays in the receipt of or failure to receive necessary government permits;
- delays in transportation and disruptions of supply routes;
- labor disputes; and
- the inability to obtain satisfactory insurance coverage.

The failure to adequately manage some of these risks could result in significant personal injury, loss of life, property damage and damage to the environment, both on and outside our operating sites, as well as damage to production facilities and delays in production.

***Continuation of our mining production is dependent on the availability of a sufficient water supply to support our mining operations.***

Our mining operations require significant quantities of water for mining, ore processing and related support facilities. Our operations in North and South America are in areas where water is scarce and competition among users for continuing access to water is significant. Continuous production at our mines is dependent on our ability to maintain our water rights and claims and defeat claims adverse to our current water uses in legal proceedings. At our U.S. operations, under state law, our water rights give us only the right to use public waters for a statutorily defined beneficial use at a designated location. In Arizona, we are a participant in two active general stream adjudications in which for over 30 years the State of Arizona has been attempting to quantify and prioritize surface water claims in two of the state’s largest river systems that affect four of our operating mines (Morenci, Sierrita, Miami and Safford). These legal proceedings may also affect our Arizona mine at Bagdad. Groundwater is not subject to adjudication in Arizona, but is subject to the doctrine of reasonable use, which requires balancing the utility of the use against the gravity of the harm to others who have rights in the same aquifer; however, wells may be subject to adjudication to the extent they are found to produce or affect surface water. In Colorado, our surface water and groundwater rights are subject to adjudication and we are involved in legal proceedings to resolve disputes regarding priority of administration of rights, including priority of some of our rights for the Climax mine. Our surface water and groundwater rights are fully licensed or have been fully adjudicated in New Mexico.

In South America, water for our mining operations at Candelaria and Ojos del Salado is drawn from the Copiapó River aquifer. Because of rapid depletion of this aquifer in recent years, ongoing studies are assessing the available supply for our mining operations at these sites. Due to anticipated shortages in this water resource, plans are in place to develop new supplementary water supplies. Construction is under way to convey treated effluent from a nearby sewage treatment plant to the mine and permitting has begun to construct both a desalination plant near the Pacific Ocean to treat seawater and a pipeline to convey the desalinated water to the Candelaria mine.

Water for our El Abra mining operations in Chile comes from the continued pumping of groundwater from the Salar de Ascotán pursuant to regulatory approval. At El Abra, hydrogeologic studies are ongoing to obtain regulatory approval for the continued pumping of groundwater from the Salar de Ascotán to process sulfide ore. We expect that the amount of water needed to develop the sulfide ore project will represent a significant increase over current volumes used in processing the oxide ore. El Abra is working closely with regulatory authorities to meet these requirements. Failure to obtain the necessary regulatory approval or receipt of approval in a less than desired amount could adversely affect our development of the sulfide ore project as planned.

Water for our Cerro Verde mining operations in Peru comes from a series of storage reservoirs on the Rio Chili watershed that collect water primarily from seasonal precipitation. Our Cerro Verde mining operations recently constructed several new water reservoirs on the Rio Chili watershed to obtain more water rights and to expand storage capacity. Due to occasional drought and possible effects of climate change reducing precipitation levels, temporary supply shortages are possible that could affect our operations as currently planned.

Although each operation currently has sufficient water rights and claims to cover its operational demands, we cannot predict the potential outcome of pending or future legal proceedings on our water rights, claims and uses. The loss of some or all water rights for any of our mines, in whole or in part, or shortages of water to which we have rights could require us to curtail or shut down mining production and could prevent us from pursuing expansion opportunities.

### An interruption of energy supply could adversely affect our mining operations.

Our mining operations and development projects require significant amounts of energy. Our principal energy sources are electricity, purchased petroleum products, natural gas and coal. Our South America mining operations receive electrical power under long-term contracts with local energy companies. Our Africa mining operation has entered into long-term power supply and infrastructure funding agreements with the state-owned electric utility company serving the Katanga province of the Democratic Republic of Congo (DRC). A disruption in the transmission of energy, inadequate energy transmission infrastructure, or the termination of any of our energy supply contracts could interrupt our energy supply and adversely affect our operations.

### Increased production costs could reduce our profitability and cash flow.

Energy represents a significant portion of our production costs. An inability to procure sufficient energy at reasonable prices could adversely affect our profits, cash flow and growth opportunities. Our production costs are also affected by the prices of commodities we consume or use in our operations, such as sulphuric acid, grinding media, steel, reagents, liners, explosives and diluents. The prices of such commodities are influenced by supply and demand trends affecting the mining industry in general and other factors outside our control and such prices are at times subject to volatile movements. Increases in the cost of these commodities could make our operations less profitable. Increases in the costs of commodities that we consume or use may also significantly affect the capital costs of new projects.

***In addition to the usual risks encountered in the mining industry, our Indonesia operations involve additional risks because they are located on unusually difficult terrain in a very remote area.***

Our Grasberg mining operations are located in steep mountainous terrain in a very remote area in Indonesia. Because of these conditions, we have had to overcome special engineering difficulties and develop extensive infrastructure facilities. In addition, the area receives considerable rainfall, which has led to periodic floods and mudslides. The mine site is also in an active seismic area and has experienced earth tremors from time to time. Our insurance may not sufficiently cover an unexpected natural or operating disaster.

On October 9, 2003, a slippage of material occurred in a section of the Grasberg open pit, resulting in eight fatalities. On December 12, 2003, a debris flow involving a relatively small amount of loose material occurred in the same section of the open pit resulting in only minor property damage. The events caused us to alter our short-term mine sequencing plans, which adversely affected our 2003 and 2004 production. We resumed normal production activities in the second quarter of 2004.

On March 23, 2006, a mud/topsoil slide involving approximately 75,000 metric tons of material occurred from a mountain ridge above service facilities supporting PT Freeport Indonesia’s mining facilities. Three contract workers were fatally injured in the event. The material damaged a mess hall and an adjacent area. As a result of investigations by PT Freeport Indonesia and the Indonesian Department of Energy and Mineral Resources, we conducted geotechnical studies to identify and address any potential hazards to workers and facilities from slides. The existing early warning system for potential slides, based upon rainfall and other factors, has also been expanded.

On September 10, 2008, a small scale failure encompassing approximately 75,000 metric tons of material occurred at our Grasberg open pit. There were no injuries or property damage. The event caused a delay in our access to the high-grade section of the open pit and, as a result, a portion of the metal expected to be mined in the second half of 2008 was deferred to future periods.

No assurance can be given that similar events will not occur in the future.

***Our Africa mining operation, Tenke Fungurume, involves additional risks because it is located in a remote area of the DRC.***

Our Africa mining operation is located in a remote area of the DRC and is subject to additional challenges, including:

- severely limited infrastructure, including road, bridge and rail access that is in disrepair and receives minimal maintenance;
- limited and possibly unreliable energy supply from antiquated equipment and from power distribution corridors that are not maintained;
- challenges in obtaining experienced personnel;
- security risks; and
- limited health care in an area plagued by disease and other potential endemic health issues, including malaria and cholera.

For example, due to limited rail access, we currently truck a significant portion of the production from our Africa mining operation approximately 1,900 miles to ports in South Africa. Our Africa mining operation and future development may be substantially affected by factors beyond our control, which could adversely affect their contribution to our operating results and increase the cost of future development.

### Environmental risks

***Our domestic and international operations are subject to complex and evolving environmental laws and regulations, and compliance with environmental and regulatory requirements involves significant costs.***

Our ongoing mining operations and exploration activities, both in the U.S. and elsewhere, are subject to extensive laws and regulations governing exploration, development, production, occupational health, mine safety, toxic substances, waste disposal, protection and remediation of the environment, protection of endangered and protected species, and other related matters. Compliance with these laws and regulations imposes substantial costs and we expect these costs to continue to increase in the future because of increased regulatory enforcement, increased demand for remediation services and shortages of equipment, supplies, labor and other factors. The Federal Clean Air Act has had a significant impact, particularly on our domestic smelter and power plants. Any change in waste management regulation of the mining industry under the Federal Resource Conservation and Recovery Act could have a significant impact, both on operational compliance and closure costs. In addition, environmental laws and regulations may change in ways that could substantially increase compliance costs or adversely affect our operations or expansion opportunities.

***In addition to compliance with environmental regulation at our operating sites, we incur significant costs for remediating environmental conditions on properties that have not been operated in many years.***

Freeport-McMoRan Corporation (FMC, formerly Phelps Dodge Corporation), and many of its affiliates and predecessor companies have been involved in mining, milling, and manufacturing in the U.S. for more than a century. Activities that occurred in the late 19th century and the 20th century prior to the advent of modern environmental laws were not subject to environmental regulation and were conducted before American industrial companies understood the long-term effects of their operations on the surrounding environment. With the passage of CERCLA in 1980, companies like Phelps Dodge became legally responsible for environmental remediation on properties previously owned or operated by them, irrespective of when the damage to the environment occurred or who caused it. That liability is often shared on a joint and several basis with all other owners and operators, meaning that each owner or operator of the property is fully responsible for the clean-up, although in many cases some or all of the other historical owners or operators no longer exist, do not have the financial ability to respond or cannot be found. As a result, because of our acquisition of Phelps Dodge in 2007, many of the subsidiary companies we now own are responsible for a wide variety of environmental remediation projects throughout the U.S., and we expect to spend substantial sums annually for many years to address these remediation issues. We are also subject to claims where the release of hazardous substances is alleged to have damaged natural resources. As of December 31, 2009, we had more than 100 active remediation projects in the U.S. in approximately 25 states.

We incurred aggregate environmental capital expenditure and other environmental costs, (including our joint venture partners’ shares), to comply with applicable environmental laws and regulations that affect our operations of $289 million in 2009, $377 million in 2008 and $280 million in 2007. For 2010, we expect to incur approximately $426 million of aggregate environmental capital expenditures and other environmental costs, which are part of our overall 2010 operating budget.

At December 31, 2009, $1.5 billion of environmental obligations were recorded in our consolidated balance sheet. Our environmental obligation estimates are based upon (1) our knowledge and beliefs about complex scientific and historical facts and circumstances that in many cases involve events that occurred many decades ago, (2) our beliefs and assumptions regarding the nature, extent and duration of remediation activities that we will be required to undertake the estimated costs of those activities, which are subject to varying interpretations, and (3) our beliefs regarding the requirements that are imposed on us by existing laws and regulations and, in some cases, the expected clarification of uncertain regulatory requirements that could materially affect our environmental obligation estimates. Significant adjustments to these estimates are likely to occur in the future as additional information becomes available. The actual environmental costs ultimately may exceed our current and future accruals for these costs, and any such changes could be material. Refer to Note 14 for more information on our environmental obligations.

***An adverse ruling in one or more pending legal proceedings involving environmental matters could have a material adverse effect on us.***

As described in our Securities and Exchange Commission (SEC) filings, we are a defendant in numerous and in some cases significant litigation involving environmental cleanup costs, alleged environmental toxic torts and interpretations of environmental regulations. An adverse ruling in one or more of these matters could have a material adverse effect on our results of operations, financial condition and cash flow.

### Mine closure regulations impose substantial costs on our operations.

Our domestic operations are subject to various federal and state permitting requirements that include mine closure and mined-land reclamation obligations. These requirements are complex and vary depending upon the jurisdiction. The laws govern the determination of the scope and cost of the closure and reclamation obligations and the amount and forms of financial assurance sufficient to allow a third party to meet the obligations of those plans if we are unable to do so. In general, our domestic mines are required to review estimated closure and reclamation costs on either a periodic basis or at the time of significant permit modifications and post increasing amounts of financial assurance as required.

In addition, our international mines are subject to various mine closure and mined-land reclamation laws, and there have recently been significant changes in closure and reclamation programs in both Peru and Chile that impose more stringent obligations on us for closure and reclamation. Updated closure plans for our three Chilean operations were submitted to the government in February 2009 and the Peruvian government approved Cerro Verde’s closure plan in October 2009.

Our asset retirement obligations (AROs), determined as required by generally accepted accounting principles (GAAP) in the U.S. totaled $731 million (including approximately $46 million for the current portion) at December 31, 2009. At December 31, 2009, we had accrued reclamation and closure costs of $351 million for our New Mexico operations, $187 million for our Arizona operations and $102 million for PT Freeport Indonesia. ARO cost estimates may increase or decrease significantly in the future as a result of changes in regulations, engineering designs and technology, permit modifications or updates, mine plans, cost of inflation or other factors and as actual reclamation spending occurs.

***Regulation of greenhouse gas emissions and climate change issues may increase our costs and adversely affect our operations and markets.***

Many scientists believe that emissions from the combustion of carbon-based fuels contribute to greenhouse effects and therefore potentially to climate change. In 2009, our worldwide total greenhouse gas emissions, measured as carbon dioxide equivalent emissions, were 8.9 million metric tons, nearly equally divided between direct and indirect emissions. Most of our direct emissions are from fuel combustion in haul trucks, followed by the combustion of fuels to provide energy for roasting, smelting and other processes. Indirect emissions are generally the emissions of outside providers from whom we purchase electricity for use in our operations. Approximately 19 percent of our direct emissions are in North America and 68 percent in Indonesia, and approximately 60 percent of our indirect emissions are in North America and 38 percent in South America.

A number of governments have introduced or are contemplating regulatory changes regarding greenhouse gas emissions. For example, in the U.S., the EPA issued final regulations in September 2009 requiring mandatory monitoring and reporting of greenhouse gas emissions in specified circumstances, commencing in 2010. Our Morenci mine, Miami smelter and El Paso refinery will likely be required to report their emissions under this program. In December 2009, the EPA issued findings under the Clean Air Act that the current and projected concentrations of greenhouse gases in the atmosphere threaten public health and welfare. While the findings themselves do not impose any requirements, they form the basis for future regulation of our greenhouse gas emissions in the U.S. In June 2009, the U.S. House of Representatives passed the American Clean Energy and Security Act of 2009 (ACES), also known as the Waxman-Markey Bill, which proposes to impose a “cap and trade” program aimed at reducing greenhouse gas emissions. Several states have also initiated action on their own or as part of regional organizations, such as the Western Climate Initiative, to limit emissions of greenhouse gases. The U.S. may also become a party to international agreements to reduce greenhouse gas emissions, which could lead to new regulations affecting our U.S. operations. The December 1997 Kyoto Protocol established a set of greenhouse gas emission targets for developed countries that have ratified the Protocol. Although the Kyoto Protocol, which expires in 2012, has not been ratified by the U.S., the U.S. continues to participate in global climate summits that may lead to an agreement in the future.

We actively pursue ways to improve the energy efficiency of our operations and reduce greenhouse gas emissions. In 2009, we formed a multi-departmental task force to focus our efforts on these topics. In addition, since 2006, we have participated in the Carbon Disclosure Project, which is a voluntary initiative that promotes standardized reporting of greenhouse gas emissions and reduction efforts. From a medium and long-term perspective, we are likely to see an increase in costs relating to our assets that emit significant amounts of greenhouse gases as a result of regulatory initiatives in the U.S. and other countries in which we operate. In addition, the cost of electricity that we purchase from others may increase, if they incur increased costs from the regulation of their greenhouse gas emissions. We cannot predict the magnitude of any increased costs at this time, given the wide scope of potential regulatory changes in the many countries in which we operate.

The potential physical impacts of climate change on our operations are highly uncertain, and would be particular to the geographic circumstances. These may include changes in rainfall patterns, water shortages, changing sea levels, changing storm patterns and intensities, and changing temperatures. These effects may adversely impact the cost, production and financial performance of our operations.

***Our operating, inactive and historical U.S. mining sites and facilities may be subject to future regulation of radioactive materials that are commonly associated with, or result from, our mining operations.***

A number of federal and state agencies are considering new regulations to characterize, regulate and remediate potential workplace exposures and environmental impacts of radioactive materials commonly associated with mining operations. For example, the EPA could promulgate rules to regulate technologically enhanced naturally occurring radioactive materials (TENORM) and their impacts at mining operations. In addition, several states are promulgating groundwater quality compliance and remediation standards for radioactive materials, including uranium. Radioactive materials can be associated with copper mineral deposits, including both our current and discontinued operations. Consequently, our copper operations may generate, concentrate or release radioactive materials that may subject our operations to new and increased regulation. The impact of such future regulation on our operating, closure, reclamation, and remediation costs is uncertain.

***Our Indonesia mining operations create difficult and costly environmental challenges, and future changes in environmental laws, or unanticipated environmental impacts from those operations, could require us to incur increased costs.***

Mining operations on the scale of our operations in Papua involve significant environmental risks and challenges. Our primary challenge is to dispose of the large amount of crushed and ground rock material, called tailings, that results from the process by which we physically separate the copper-, gold- and silver-bearing materials from the ore that we mine. Our tailings management plan, which has been approved by the Government of Indonesia, uses the river system near our mine to transport the tailings to an engineered area in the lowlands where the tailings and natural sediments are managed in a deposition area. Lateral levees have been engineered and constructed to limit and help contain the footprint of tailings impact in the lowlands.

Another major environmental challenge is managing overburden, which is the rock that must be moved aside in the mining process in order to reach the ore. In the presence of air, water and naturally occurring bacteria, some overburden can generate acid rock drainage, or acidic water containing dissolved metals which, if not properly managed, can have a negative impact on the environment.

Certain Indonesian governmental officials have from time to time raised questions with respect to our tailings and overburden management plans, including a suggestion that we implement a pipeline system rather than our river transport system for tailings management and disposition. Because our mining operations are remotely located in steep mountainous terrain and in an active seismic area, a pipeline system would be costly, difficult to construct and maintain, and more prone to catastrophic failure, and could therefore involve significant potentially adverse environmental issues. Based on our own studies and others conducted by third parties, we do not believe that a pipeline system is necessary or practical.

In connection with obtaining our environmental approvals from the Indonesian government, we committed to perform a one-time environmental risk assessment on the impacts of our tailings management plan. We completed this extensive environmental risk assessment with more than 90 scientific studies conducted over four years and submitted it to the Indonesian government in December 2002. We developed the risk assessment study using internationally recognized methods with input from an independent review panel, which included representatives from the Indonesian government, academia and non-governmental organizations. The risks identified during this process were in line with our impact projections of the tailings management program contained in our environmental approval documents.

Since 2005, PT Freeport Indonesia has participated in the Government of Indonesia’s PROPER (Program for Pollution Control, Evaluation and Rating) program. In October 2009, the Indonesian Ministry of Environment announced the latest results of its PROPER environmental management audit, and gave PT Freeport Indonesia a Blue rating acknowledging PT Freeport Indonesia’s environmental management practices as being in compliance with the laws and regulations in Indonesia and also making several recommendations for improvement.

### International risks

***Our International operations are subject to political, social and geographic risks of doing business in foreign countries.***

We are a global mining company with substantial assets located outside of the U.S. We conduct international mining operations in Indonesia, Peru, Chile and the Democratic Republic of Congo. Accordingly, our business may be adversely affected by political, economic and social uncertainties in each of these countries, in addition to the usual risks associated with conducting business in foreign countries. Such risks include (1) renegotiation, cancellation or forced modification of existing contracts, (2) expropriation or nationalization of property, (3) changes in a foreign country’s laws, regulations and policies, including those relating to labor, taxation, royalties, divestment, imports, exports, trade regulations, currency and environmental matters, (4) political instability, bribery, extortion, corruption, civil strife, acts of war, guerilla activities, insurrection and terrorism, (5) foreign exchange controls, and (6) the risk of having to submit to the jurisdiction of a foreign court or arbitration panel or having to enforce the judgment of a foreign court or arbitration panel against a sovereign nation within its own territory. Our insurance does not cover most losses caused by these risks. Consequently, our exploration, development and production activities outside of the U.S. could be substantially affected by factors beyond our control, some of which could materially adversely affect our financial position or results of operations.

In December 2009, PT Freeport Indonesia was notified by the Large Taxpayer’s Office of the Government of Indonesia that PT Freeport Indonesia is obligated to pay value added taxes on certain goods imported after the year 2000. The amount of taxes and penalties would be significant. PT Freeport Indonesia believes that pursuant to the terms of its Contract of Work, it is only required to pay value added taxes on these types of goods imported after December 30, 2009. PT Freeport Indonesia is working cooperatively with the applicable government authorities to resolve this matter.

In December 2008, our Cerro Verde mining operation in Peru was notified by Peruvian revenue authorities of their intent to assess mining royalties related to minerals processed by the Cerro Verde concentrator. In August 2009, Cerro Verde received a formal assessment in the amount of approximately $50 million in connection with its alleged obligations for mining royalties and fines for the period from October 2006 to December 2007. Cerro Verde is challenging this assessment as it believes that royalty obligations with respect to all minerals extracted are governed by its existing stability agreement, regardless of the processing method applied after extraction, and believes that it owes no royalties with respect to minerals processed through its concentrator. We are working cooperatively with the Peruvian authorities to resolve this matter.

***Because our Grasberg minerals district in Papua, Indonesia remains our most significant operating asset, our business may continue to be adversely affected by Indonesian political, economic and social uncertainties.***

Indonesia has faced political, economic and social uncertainties, including separatist movements and civil and religious strife in a number of provinces. In particular, several separatist groups are opposing Indonesian rule over the province of Papua, where our Grasberg minerals district is located, and have sought political independence for the province. In response, Indonesia enacted regional autonomy laws, which became effective January 1, 2001. The manner in which the new laws are being implemented and the degree of political and economic autonomy that they may bring to individual provinces, including Papua, are uncertain and are ongoing issues in Indonesian politics. In Papua, there have been sporadic attacks on civilians by separatists and sporadic but highly publicized conflicts between separatists and the Indonesian military. Social, economic and political instability in Papua could materially and adversely affect us if it results in damage to our property or interruption of our activities.

Maintaining a good working relationship with the Indonesian government is important to us because our mining operations there are among Indonesia’s most significant business enterprises and are conducted pursuant to a Contract of Work with the Indonesian government. Partially because of their significance to Indonesia’s economy, the environmentally sensitive area in which they are located, and the number of people employed, our operations are occasionally the subject of criticism in the Indonesian press and in political debates, and have been the target of protests and occasional violence.

Since July 2009, there has been a series of shooting incidents along the road leading to our mining and milling operations at our Grasberg mining complex (including an incident in January 2010). In connection with these incidents, there have been three fatalities (including one PT Freeport Indonesia employee, a security contractor and an Indonesian policeman) and several injuries. The Indonesian government has responded with additional security forces and has expressed a strong commitment to protect the safety of the community and of our operations. The investigation of these matters is continuing, and we have taken precautionary measures, including limiting use of the road to secured convoys. Our mining and milling activities have continued uninterrupted; however, prolonged limitations on access to the road could adversely affect operations at the mine. In response to these events, PT Freeport Indonesia is currently reviewing security plans with the Indonesian authorities.

Grasberg operated at reduced mining and milling rates during a four-day period from April 18, 2007 to April 21, 2007, as a result of peaceful protests by certain workers regarding benefits. The protests ended on April 21 with an agreement on a framework for minimum wages for its workers and Grasberg returned to normal operations. The impacts to production were not significant. Illegal miners have continued to operate along the river designated to transport the tailings from the mill to the lowlands in PT Freeport Indonesia’s government-approved tailings management area. The illegal miners who have trespassed from time to time in the area of our facilities have clashed with police who have attempted to move them away from our facilities. In 2006, the illegal miners temporarily blocked the road leading to the Grasberg mine and mill in protest, and PT Freeport Indonesia temporarily suspended mining and milling operations as a precautionary measure.

We cannot predict whether additional incidents will occur that could disrupt our Indonesian operations, or whether similar incidents may occur in other countries that could affect our other operations. If additional protests or other disruptive incidents occur at any of our facilities, they could adversely affect our business and profitability in ways that we cannot predict at this time.

***We do not expect to mine all of our Indonesian ore reserves before the initial term of our Contract of Work in Indonesia expires.***

All of our Indonesian proven and probable ore reserves, including the Grasberg deposit, are located in Block A. The initial term of our Contract of Work covering these ore reserves expires at the end of 2021. We can extend this term for two successive 10-year periods, subject to the approval of the Indonesian government, which under our Contract of Work cannot be withheld or delayed unreasonably. Our ore reserves reflect estimates of minerals that can be recovered through the end of 2041 (i.e., through the expiration of the two 10-year extensions) and our current mine plan has been developed, and our operations are based on the assumption that we will receive the two 10-year extensions. As a result, we will not mine all of these ore reserves during the current term of our Contract of Work, and there can be no assurance that the Indonesian government will approve the extensions. Prior to the end of 2021, we expect to mine approximately 33 percent of aggregate proven and probable recoverable ore at December 31, 2009, representing approximately 39 percent of PT Freeport Indonesia’s share of recoverable copper reserves and approximately 52 percent of its share of recoverable gold reserves.

In 2008, Indonesia enacted a new mining law, which will operate under a licensing system as opposed to the contract of work system that applies to PT Freeport Indonesia. In 2010, the Government of Indonesia promulgated regulations under the 2008 mining law and certain provisions address existing contracts of work. The regulations provide that contracts of work will continue to be honored until their expiration. However, the regulations attempt to apply certain provisions of the new law to any extension periods of contracts of work even though our Contract of Work provides for two ten-year extension periods under the existing terms of the Contract of Work.

***Our Contracts of Work in Indonesia are subject to termination if we do not comply with our contractual obligations, and if a dispute arises, we may have to submit to the jurisdiction of a foreign court or arbitration panel.***

PT Freeport Indonesia’s Contract of Work and other Contracts of Work in which we have an interest were entered into under Indonesia’s 1967 Foreign Capital Investment Law, which provides guarantees of remittance rights and protection against nationalization. Our Contracts of Work can be terminated by the Government of Indonesia if we do not satisfy our contractual obligations, which include the payment of royalties and taxes to the government and the satisfaction of certain mining, environmental, safety and health requirements.

Certain forestry laws and designations as well as prevailing environmental laws and regulations may conflict with or overlap with the mining rights established under our Contract of Work. Although our Contract of Work grants to PT Freeport Indonesia the unencumbered right to operate in accordance with the Contract of Work, certain government agencies could seek to impose additional restrictions on PT Freeport Indonesia that could affect exploration and operating requirements.

At times, certain government officials and others in Indonesia have questioned the validity of contracts entered into by the Government of Indonesia prior to May 1998 (i.e., during the Suharto regime, which lasted over 30 years), including PT Freeport Indonesia’s Contract of Work, which was signed in December 1991. We cannot assure you that the validity of, or our compliance with, the Contracts of Work will not be challenged for political or other reasons. PT Freeport Indonesia’s Contract of Work and our other Contracts of Work require that disputes with the Indonesian government be submitted to international arbitration. Consequently, if a dispute arises under the Contracts of Work, we face the risk of having to submit to the jurisdiction of a foreign court or arbitration panel, and if we prevail in such a dispute, we will face the additional risk of having to enforce the judgment of a foreign court or arbitration panel against Indonesia within its own territory.

Indonesian government officials have periodically undertaken reviews regarding our compliance with Indonesian environmental laws and regulations and the terms of the Contracts of Work. In 2006, the Government of Indonesia created a joint team for “Periodic Evaluation on Implementation of the PT-FI Contract of Work (COW)” to conduct an evaluation every five years. The team consists of five working groups, whose members are from relevant ministries or agencies, covering production, state revenues, community development, environmental issues and security issues. We have conducted numerous meetings with these groups. The joint team has indicated that it will issue a report. While we believe that we comply with PT Freeport Indonesia’s Contract of Work in all material respects, we cannot assure you that the report will support that conclusion. Separately, the Indonesian House of Representatives created a working committee on PT Freeport Indonesia. Members of this group have also visited our operations and held a number of hearings in Jakarta. We will continue to work with these groups to respond to their questions about our operations and our compliance with PT Freeport Indonesia’s Contract of Work.

***Any suspension of required activities under our Contracts of Work requires the consent of the Indonesian government.***

Our Contracts of Work permit us to suspend certain contractually required activities, including exploration, for a period of one year by making a written request to the Indonesian government. These requests are subject to the approval of the Indonesian government and are renewable annually. If we do not request a suspension or are denied a suspension, then we are required to continue our activities under the Contract of Work or potentially be declared in default. Moreover, if a suspension continues for more than one year for reasons other than force majeure and the Indonesian government has not approved such continuation, then the government would be entitled to declare a default under the Contract of Work.

We suspended our field exploration activities outside of Block A in recent years because of safety and security issues and regulatory uncertainty relating to a possible conflict between our mining and exploration rights in certain forest areas and an Indonesian Forestry law enacted in 1999 prohibiting open-pit mining in forest preservation areas. In 2001, we requested and received from the Government of Indonesia, formal temporary suspensions of our obligations under the Contracts of Work in all areas outside of Block A. Recent Indonesian legislation permits open-pit mining in PT Freeport Indonesia’s Block B area, subject to certain requirements. Following an assessment of these requirements and a review of security issues, in 2007 we resumed exploration activities in certain prospective Contract of Work areas outside of Block A.

***Our Tenke Fungurume mining operation is located in the Katanga province of the DRC, and may be adversely affected by political, economic and social instability in the DRC.***

During 2009, we completed construction activities for the initial Tenke Fungurume development project, which is located in the DRC. Since 1960, the DRC has undergone outbreaks of violence, changes in national leadership and financial crisis. These factors heighten the risk of abrupt changes in the national policy towards foreign investors, which in turn could result in unilateral modification of concessions or contracts, increased taxation, denial of permits or permit renewals or expropriation of assets. Our ability to continue mining operations and future development is currently subject to an ongoing review of our mining convention which was part of a review of all mining contracts by the Ministry of Mines (Ministry) in the DRC, the outcome of which cannot be predicted. We received notification on February 20, 2008, that the Ministry wishes to renegotiate several material provisions of our mining concessions. We believe that the terms of the concessions are fair and that they were negotiated transparently and are legally binding. However, we cannot predict whether the Government of the DRC will respect our contract rights.

In July 2009, Tenke Fungurume was advised that the Minister of Justice in the DRC authorized an inquiry regarding the alleged misappropriation of public funds in connection with the securing of labor and immigration authorizations and the payment of associated fees for the Tenke Fungurume project. Several government officials and three Tenke Fungurume employees were arrested. In October 2009, the three Tenke Fungurume employees were tried and acquitted. One government official, the head of immigration in the Katanga province, was sentenced to five years imprisonment on charges of embezzlement. The office of the Attorney General of the DRC has filed a notice of appeal of the judgment, the implications of which are not yet clear.

In July 2009, Tenke Fungurume entered into a settlement agreement with DRC tax authorities in connection with an administrative audit regarding the payment of fees for work permits and visas for its foreign workers and subcontractors, including short-term workers. Pursuant to the agreement, which covers the period from January 2007 to the date of the settlement, Tenke Fungurume paid approximately $16 million in fees and penalties. The procedures associated with obtaining labor and immigration authorizations for short-term workers on a timely basis are not clearly established in the DRC, and Tenke Fungurume continues to work proactively and cooperatively with the tax authorities to establish approved procedures for doing so consistent with its mining convention and local law.

Other political, economic and social risks that are generally outside of our control and could adversely affect our business include:

- political risks associated with the relatively recent establishment of the present government;
- cancellation or renegotiation of mining contracts by the government;
- legal and regulatory uncertainties, governmental corruption and bribery;
- royalty and tax increases or claims by governmental entities, including retroactive claims;
- security risks due to the remote location in the southern DRC and violence in the northeastern provinces of the DRC;
- risk of loss of property due to expropriation or nationalization of property; and
- risk of loss due to civil strife, acts of war, guerrilla activities, insurrection and terrorism.

Consequently, our Tenke Fungurume mining operations and future development projects may be substantially affected by factors beyond our control, any of which could adversely affect our financial position or results of operations.

***Terrorist attacks and violence near our operations and throughout the world and the potential for additional future terrorist acts and violence have created economic and political uncertainties that could materially and adversely affect our business.***

On July 17, 2009, two suicide bombers set off explosions inside of the JW Marriott and Ritz-Carlton hotels in Jakarta, Indonesia, that are reported to have killed nine people and injured 53 others. Two of our Indonesian-based executives were injured in the incident.

On July 8, 2009, a small group of individuals created a disturbance on the road leading to our mining and milling operations at our Grasberg mining complex and vandalized vehicles and small buildings. There were no injuries. For more information about a series of shooting incidents near our Grasberg mining complex, see the risk factor “Because our Grasberg minerals district in Papua, Indonesia remains our most significant operating asset, our business may continue to be adversely affected by Indonesian political, economic and social uncertainties” above.

On August 31, 2002, three people were killed and 11 others were wounded in an ambush by a group of unidentified assailants on the road near Tembagapura, the mining town where the majority of PT Freeport Indonesia’s personnel reside. The assailants shot at several vehicles transporting international contract teachers from our school in Tembagapura, their family members and other contractors to PT Freeport Indonesia. The U.S. Federal Bureau of Investigation (FBI) investigated the incident, which resulted in the U.S. indictment of an alleged operational commander of the Free Papua Movement/National Freedom Force. In January 2006, Indonesian police, accompanied by FBI agents, arrested the alleged operational commander and 11 other Papuans. In November 2006, verdicts and sentencing were announced for seven of those accused in the August 2002 shooting, including a life sentence for the confessed leader of the attack.

On October 12, 2002, a bombing killed 202 people in the Indonesian province of Bali, which is 1,500 miles west of our mining and milling operations. Indonesian authorities arrested 35 people in connection with this bombing and 29 of those arrested have been tried and convicted. On August 5, 2003, 12 people were killed and over 100 were injured by a car bomb detonated outside of the JW Marriott Hotel in Jakarta, Indonesia. On September 9, 2004, 11 people were killed and over 200 injured by a car bomb detonated in front of the Australian embassy in Jakarta. On October 1, 2005, three suicide bombers killed 19 people and wounded over 100 in Bali. The same international terrorist organizations are suspected in each of these incidents. In November 2005, Indonesian police raided a house in East Java that resulted in the death of other accused terrorists linked to the bombings discussed above. Our mining and milling operations were not interrupted by these incidents, but PT Freeport Indonesia’s corporate office in Jakarta had to relocate for several months following the bombing in front of the Australian embassy. In addition to the Bali, JW Marriott Hotel and Australian embassy bombings, there have been anti-American demonstrations in certain sections of Indonesia reportedly led by radical Islamic activists.

No assurance can be given that additional terrorist incidents and acts of violence will not occur. If there were to be additional violence, it could materially and adversely affect our business in ways that we cannot predict at this time.

### Other risks

***If market prices for our commodities decline, the carrying values of inventories and long-lived assets may be further impaired, which could require charges to operating income that could be material.***

During fourth-quarter 2008, we concluded that the then-current economic environment and significant declines in copper and molybdenum prices represented significant adverse changes in our business requiring us to evaluate our long-lived assets and goodwill for impairment. As a result, we recorded impairment charges totaling $16.9 billion ($12.6 billion to net loss attributable to FCX common stockholders). Additionally, the declines in copper and molybdenum prices in late 2008 resulted in lower of cost or market (LCM) inventory charges totaling $782 million ($479 million to net loss attributable to FCX common stockholders) in 2008. Additional LCM charges associated with molybdenum inventories totaling $19 million ($15 million to net income attributable to FCX common stockholders) were recorded in first-quarter 2009. Declines in the market price of copper, among other factors, may cause us to record additional LCM inventory adjustments and may also require us to further write down the carrying value of long-lived assets, which would potentially have a material adverse impact on our results of operations and stockholders' equity, but would have no effect on cash flows.

***Unanticipated litigation or negative developments in pending litigation could have a material adverse effect on our results of operations and financial condition.***

We are a party to the litigation described in our SEC filings and a number of other litigation matters, including asbestos exposure cases, disputes over the allocation of environmental remediation obligations at Superfund and other sites, disputes over water rights and disputes with regulatory authorities. The outcome of litigation is inherently uncertain and adverse developments or outcomes can result in significant monetary damages, penalties or injunctive relief against us, limitations on our property rights, or regulatory interpretations that increase our operating costs. If any of these disputes results in a substantial monetary judgment against us or an adverse legal interpretation, is settled on unfavorable terms, or otherwise affects our operations, it could have a material adverse effect on our operating results and financial condition.

***We depend on our senior management team and other key employees, and the loss of any of these employees could adversely affect our business.***

Our success depends in part on our ability to attract, retain and motivate senior management and other key employees. Achieving this objective may be difficult due to many factors, including fluctuations in global economic and industry conditions, competitors’ hiring practices, cost reduction activities, and the effectiveness of our compensation programs. Competition for qualified personnel can be very intense. We must continue to recruit, retain and motivate senior management and other key employees sufficient to maintain our current business and support our future projects. A loss of such personnel could prevent us from capitalizing on business opportunities, and our operating results could be adversely affected.

#### Our holding company structure may impact your ability to receive dividends.

We are a holding company with no material assets other than the capital stock of our subsidiaries. As a result, our ability to repay our indebtedness and pay dividends is dependent on the generation of cash flow by our subsidiaries and their ability to make such cash available to us, by dividend, loan, debt repayment or otherwise. Our subsidiaries do not have any obligation to make funds available to us to repay our indebtedness or pay dividends. Dividends from subsidiaries that are not wholly owned are shared with other equity owners. In addition, cash at our international operations is subject to foreign withholding taxes upon repatriation into the U.S.

In addition, our subsidiaries may not be able to, or be permitted to, make distributions to enable us to repay our indebtedness or pay dividends. Each of our subsidiaries is a distinct legal entity and, under certain circumstances, legal and contractual restrictions, as well as the financial condition and operating requirements of our subsidiaries, may limit our ability to obtain cash from our subsidiaries. Our rights to participate in any distribution of our subsidiaries’ assets upon their liquidation, reorganization or insolvency would generally be subject to the prior claims of the subsidiaries’ creditors, including any trade creditors and preferred stockholders.

***Anti-takeover provisions in our charter documents and Delaware law may make an acquisition of us more difficult.***

Anti-takeover provisions in our charter documents and Delaware law may make an acquisition of us more difficult. These provisions:

- authorize our board of directors to issue preferred stock without stockholder approval and to designate the rights, preferences and privileges of each class; if issued, such preferred stock would increase the number of outstanding shares of our capital stock and could include terms that may deter an acquisition of us;
- establish advance notice requirements for nominations to the board of directors or for proposals that can be acted on at stockholder meetings;
- limit who may call stockholder meetings; and
- require the approval of the holders of two thirds of our outstanding common stock to enter into certain business combination transactions, subject to certain exceptions, including if the consideration to be received by our common stockholders in the transaction is deemed to be a fair price.

These provisions may discourage potential takeover attempts, discourage bids for our common stock at a premium over market price or adversely affect the market price of, and the voting and other rights of the holders of, our common stock. These provisions could also discourage proxy contests and make it more difficult for stockholders to elect directors other than the candidates nominated by our board of directors.

In addition, because we are incorporated in Delaware, we are governed by the provisions of Section 203 of the Delaware General Corporation Law, which may prohibit large stockholders from consummating a merger with, or acquisition of, us.

These provisions may deter an acquisition of us that might otherwise be attractive to stockholders.

## Legal proceedings

As filed, 11,123 characters.

We are involved in various legal proceedings that arise in the ordinary course of our business or are associated with environmental issues arising from legacy operations conducted over the years by Phelps Dodge and its affiliates. We do not believe that our potential liability in any such proceeding should have a material adverse effect on our business, financial condition or results of operations. We maintain liability insurance to cover some, but not all, potential liabilities normally incident to the ordinary course of our business as well as other insurance coverage customary in our business, with coverage limits that we deem prudent.

### Environmental Proceedings

Pinal Creek. We are a party to litigation entitled Pinal Creek Group, et al. v. Newmont Mining Corporation, et al., United States District Court, District of Arizona, Case No. CIV 91-1764 PHX DAE (LOA), filed on May 1, 1991. The Pinal Creek site located near Miami, Arizona, was listed under the Arizona Department of Environmental Quality’s (ADEQ) Water Quality Assurance Revolving Fund program in 1989 for contamination in the shallow alluvial aquifers within the Pinal Creek drainage near Miami, Arizona. Since that time, environmental remediation has been performed by members of the Pinal Creek Group (PCG), consisting of Phelps Dodge Miami, Inc. (Miami) (a wholly owned subsidiary of Freeport-McMoRan Corporation, formerly Phelps Dodge Corporation) and two other companies. In 1998, the District Court approved a Consent Decree between the PCG members and the state of Arizona resolving all matters related to an enforcement action contemplated by the state of Arizona against the PCG members with respect to groundwater contamination. The Consent Decree committed the PCG members to complete the remediation work outlined in the Consent Decree, and that work continues at this time and is expected to continue for many years in the future.

Remediation costs have been paid pursuant to an interim cost sharing allocation among the members of the PCG, with Miami’s interim allocation being approximately two-thirds. However, there have been significant disagreements among the members of the PCG regarding the cost allocation, with other members alleging in the federal court proceeding that Miami should be responsible for substantially all of the costs. In February 2010, we settled those disagreements and the associated litigation. Pursuant to the settlement agreement, Miami paid $40 million to other members of the PCG to settle the allocation of previously incurred costs, and agreed to take full responsibility for future groundwater remediation at the Pinal Creek site, with limited exceptions. The settlement did not result in an adjustment of the related environmental reserve reflected in our financial statements.

Blackwell, Oklahoma Litigation. On April 14, 2008, a purported class action was filed in the District Court of Kay County, Oklahoma against us and several of our direct and indirect subsidiaries, including Blackwell Zinc Company (BZC) (Coffey, et al., v. Freeport-McMoRan Copper & Gold, Inc., et al., Kay County, Oklahoma District Court, Case No. CJ-2008-68). This suit alleges that the operations of BZC’s zinc smelter in Blackwell, Oklahoma, from 1918 to 1974 resulted in contamination of the soils and groundwater in Blackwell and the surrounding area. Unspecified compensatory and punitive damages are sought on behalf of the putative class members, consisting of current and former residents and property owners, for alleged diminution in property values. There is also a request for an order compelling remediation of allegedly contaminated properties and the establishment of a monetary fund to monitor the present and future health of the putative class members.

On December 7, 2009, 18 individuals filed a related suit (Brown et al. v. Freeport-McMoRan Copper & Gold Inc. et al., Kay County, Oklahoma District Court, Case No. CJ-2009-213), alleging personal injuries resulting from exposure to lead and seeking compensatory and punitive damages. We intend to defend both of these matters vigorously. For more information about our remediation activities in Blackwell, Oklahoma, refer to Note 14.

On October 15, 2009, the City of Blackwell and the Blackwell Municipal Authority filed an action against us and several of our direct and indirect subsidiaries, including BZC (City of Blackwell et al. v. Freeport-McMoRan Copper & Gold, Inc. et al., Kay County, Oklahoma District Court, Case No. CJ-2009-15B). The suit alleged that the operations of BZC’s zinc smelter resulted in contamination of soils and groundwater in the City of Blackwell. The plaintiffs alleged nuisance, trespass, negligence, and unjust enrichment and claimed unspecified actual, equitable (for unjust enrichment) and punitive damages. In February 2010, we reached a partial settlement with the City of Blackwell and the Blackwell Municipal Authority by paying $54 million to settle all of the claims except for future damages relating to the potential failure of our groundwater remediation system (which is under construction) to prevent contamination from entering the City of Blackwell’s wastewater treatment system.

Arizona Department of Environmental Quality – Morenci. In October 2008, Freeport-McMoRan Morenci Inc. (Morenci) notified state and federal authorities that it accidentally released electrolyte solution from its solution extraction and electrowinning (SX/EW) operation into Lower Chase Creek, an ephemeral stream that is normally dry. Morenci conducted a thorough cleanup of the spill and later provided authorities with information on corrective actions implemented in response to the spill. On January 16, 2009, Morenci received Notices of Violation (NOVs) from the Arizona Department of Environmental Quality alleging that the spill resulted in violations of the Arizona Pollutant Discharge Elimination System and Aquifer Protection Programs. Morenci also received a letter dated January 28, 2010, from the Arizona Attorney General’s office advising Morenci that the State of Arizona intends to file a civil enforcement action. Morenci intends to meet with the Arizona Attorney General’s office to discuss a potential settlement and expects to reach an agreement that includes payment of an appropriate civil penalty, which may exceed $100,000, and possible additional corrective actions to those previously implemented.

### Asbestos Claims

Since approximately 1990, Phelps Dodge and various subsidiaries have been named as defendants in a large number of lawsuits claiming personal injury from exposure to asbestos contained in electrical wire products produced or marketed by Phelps Dodge affiliates many years ago, or from asbestos contained in buildings and facilities located at properties owned or operated by Phelps Dodge affiliates.

### Water Rights

Water law in the western U.S. is generally based on the doctrine of prior appropriation (first in time, first in right) and permits the water right holder the right to use public waters for a statutorily defined beneficial use, at a designated location. Our operations in the western U.S. require water for mining, ore processing and related support facilities. Continuous operation of these mines is dependent on our ability to maintain our water rights and claims. The loss of water rights, in whole or in part, could have a significant adverse affect on our mining operations.

Two water rights adjudications have been initiated in the State of Arizona in order to quantify and prioritize all surface water claims in two of the State’s river systems that include four of our operating mines (Morenci, Sierrita, Miami and Safford). These legal proceedings may also affect our Bagdad, Arizona mine. These adjudications have been under way for many years, and we cannot predict when they will be concluded.

In Re the General Adjudication of All Rights to Use Water in the Little Colorado Water System and Sources, Apache County, Superior Court, No. 6417, filed on or about February 17, 1978. The principal parties, in addition to us, include: the State of Arizona; the Salt River Project; the Arizona Public Service Company; the Navajo Nation, the Hopi Indian Tribe; the San Juan Southern Paiute Tribe; and the United States on its own behalf, on behalf of those Indian tribes, and on behalf of the White Mountain Apache Tribe.

In Re The General Adjudication of All Rights to Use Water in the Gila River System and Sources,

Maricopa County, Superior Court, Cause Nos. W-1 (Salt), W-2 (Verde), W-3 (Upper Gila), and W-4 (San Pedro), filed on February 17, 1978. The principal parties, in addition to us, include: the State of Arizona; the Gila Valley Irrigation District; the San Carlos Irrigation and Drainage District; the Salt River Project; the San Carlos Apache Tribe; the Gila River Indian Community; and the United States on behalf of those Tribes, on its own behalf, and on behalf of the White Mountain Apache Tribe, the Fort McDowell Mohave-Apache Indian Community, the Salt River Pima-Maricopa Indian Community, and the Payson Community of Yavapai Apache Indians.

In 1998, we entered into a water rights settlement agreement with the Gila River Indian Community (GRIC), which was later included in a comprehensive water rights settlement under the Arizona Water Settlements Act of 2004. The GRIC settlement is subject to contingencies, and the comprehensive settlement has been challenged by other parties. If we are unable to resolve the contingencies in the GRIC settlement and defeat the third-party challenges, our water rights in the Gila River watershed could be diminished, and our operations at Morenci, Sierrita, Miami and Safford could be adversely affected.

Prior to January 1, 1983, various Indian tribes filed suits in the U.S. District Court in Arizona claiming superior rights to water being used by many other water users, including us, and claiming damages for prior use in derogation of their allegedly superior rights. These federal proceedings have been stayed pending the Arizona Superior Court adjudications.

United States v. Gila Valley Irrigation District, United States District Court, District of Arizona, was initiated in 1925 by the United States to settle conflicting claims to water rights in portions of the Gila River watershed. A decree settling the claims of various parties was entered in 1935, after Morenci had been dismissed from the case without prejudice. In 1988, the Gila River Indian Community intervened, challenging uses of water in the Gila River watershed, which may impact water that we have the right to divert annually from Eagle Creek, Chase Creek or the San Francisco River for operation of our Morenci mine, pursuant to decreed rights and an agreement between us and the Gila Valley Irrigation District. Our Morenci operations also purchased farm lands with water rights in 1997, 1998 and 2008 that could be affected by the outcome of this proceeding. Impairment of our water claims in the Gila River watershed could adversely affect the operations of our Morenci and Safford mines.

## Management's discussion and analysis

As filed, 188,568 characters.

### MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

### OVERVIEW and OUTLOOK

*In Management’s Discussion and Analysis of Financial Condition and Results of Operations, “we,” “us” and “our” refer to Freeport-McMoRan Copper & Gold Inc. (FCX) and its consolidated subsidiaries. The results of operations reported and summarized below are not necessarily indicative of future operating results (refer to “Cautionary Statement” for further discussion). In particular, the financial results for 2007 include the operations of Phelps Dodge Corporation (Phelps Dodge) from March 20, 2007, through December 31, 2007, not the full twelve-month period because of the accounting treatment for the acquisition. References to “Notes” are Notes included in our “Notes to Consolidated Financial Statements.” Throughout Management's Discussion and Analysis of Financial Condition and Results of Operations all references to earnings or losses per share are on a diluted basis, unless otherwise noted.*

We are one of the world’s largest copper, gold and molybdenum mining companies in terms of reserves and production. Our portfolio of assets includes the Grasberg minerals district in Indonesia, which contains the largest single recoverable copper reserve and the largest single gold reserve of any mine in the world based on the latest available reserve data provided by third-party industry consultants; significant mining operations in North and South America; and the Tenke Fungurume minerals district in the Democratic Republic of Congo (DRC). We also operate Atlantic Copper, our wholly owned copper smelting and refining unit in Spain.

During 2009, approximately 61 percent of our consolidated copper production was from our Grasberg, Morenci and Cerro Verde mines, and more than half of our mined copper was sold in concentrate, approximately 25 percent as cathodes and approximately 21 percent as rod (principally from our North America operations). We also produce gold as a by-product at our copper mines, primarily at the Grasberg minerals district in Indonesia, which accounted for approximately 96 percent of our consolidated gold production for 2009. For 2009, approximately half of our consolidated molybdenum production was from the Henderson molybdenum mine and approximately 46 percent was produced as a by-product at our North America copper mines. Refer to “Operations” for further discussion of our mining operations.

The dramatic declines in copper and molybdenum prices in late 2008 and the deterioration of the economic and credit environment limited our ability to invest in growth projects and required us to make adjustments to our near-term plans in late 2008 and early 2009 (refer to Note 2 for further discussion). However, during 2009 copper prices improved from the January 2009 low of $1.38 per pound. Rising copper prices, along with higher volumes from the Grasberg mine and a lower cost structure at the North America copper mines, have enabled us to enhance our financial and liquidity position during 2009, allowing us to manage volatile conditions effectively, reduce debt and reinstate cash dividends to shareholders, while maintaining our future growth opportunities. In addition, we have announced initiatives to resume certain project development activities that were deferred in late 2008 (refer to “Current Development Projects” for further discussion).

At December 31, 2009, we had $2.7 billion in consolidated cash ($2.2 billion of which was available to our parent company). We had no borrowings and $39 million of letters of credit issued under our $1.5 billion revolving credit facilities, resulting in availability of approximately $1.5 billion ($961 million of which could be used for additional letters of credit). Our long-term debt at December 31, 2009, was $6.3 billion. Although we have no significant debt maturities in the near-term (refer to “Capital Resources and Liquidity”), during 2009, we repaid $1.0 billion in debt in advance of scheduled maturities (refer to Note 10). From January 1, 2010, to February 25, 2010, we have made additional open-market debt purchases totaling $269 million for $293 million (refer to Note 23). We may consider additional opportunities to prepay debt in advance of scheduled maturities or redeem our currently redeemable Senior Floating Rate Notes.

We view the long-term outlook for our business positively, supported by limitations on supplies of copper and by the requirements for copper in the world’s economy and will continue to adjust our operating strategy as market conditions change. Refer to “Consolidated Results” for further discussion of our consolidated financial results for the years ended December 31, 2009, 2008 and 2007.

### Outlook

Following are our actual consolidated sales volumes for 2009 and our projected consolidated sales volumes for 2010:

| Copper (billions of recoverable pounds): | 2009 (Actual) | 2010 (Projected) |  |
| --- | ---: | ---: | --- |
| North America copper mines | 1.2 | 1.0 |  |
| South America copper mines | 1.4 | 1.3 |  |
| Indonesia mining | 1.4 | 1.2 |  |
| Africa mining | 0.1 | 0.2 |  |
|  | 4.1 | 3.8 | a |
| Gold (millions of recoverable ounces): |  |  |  |
| Indonesia mining | 2.5 | 1.7 |  |
| South America copper mines | 0.1 | 0.1 |  |
|  | 2.6 | 1.8 |  |
| Molybdenum (millions of recoverable pounds)b | 58 | 60 |  |

a. Represents the sum of projected copper sales volumes before rounding.

b. Includes sales of molybdenum produced as a by-product at our North and South America copper mines.

Estimated sales volumes of approximately 3.8 billion pounds of copper for 2010 are lower than 2009 sales of 4.1 billion pounds primarily because of lower volumes in Indonesia as a result of transitioning to a lower-grade section of the Grasberg open pit during 2010 and at our North America copper mines reflecting the impact of reduced 2009 mining activities on 2010 leaching operations. Estimated sales volumes of approximately 1.8 million ounces of gold for 2010 are lower than 2009 sales of 2.6 million ounces as a result of transitioning to a lower-grade section of the Grasberg open pit during 2010. Estimated sales volumes of approximately 60 million pounds of molybdenum for 2010 approximate 2009 sales of 58 million pounds. Our projected sales volumes for 2010 depend on the achievement of targeted mining rates, the successful operation of production facilities, the impact of weather conditions and other factors.

Assuming average prices of $3.25 per pound of copper, $1,100 per ounce of gold and $12 per pound of molybdenum for 2010, we estimate our consolidated unit net cash costs (net of by-product credits and excluding Africa mining) for our copper mining operations would average approximately $0.86 per pound in 2010, compared with $0.55 per pound in 2009. Average unit net cash costs for 2010 are estimated to be higher than 2009 as a result of lower projected 2010 copper and gold sales volumes from Grasberg, combined with increases in commodity-based input costs and foreign currency exchange rates. Consolidated unit net cash costs would be impacted by approximately $0.025 per pound for each $50 per ounce change in gold prices and approximately $0.01 per pound for each $1 per pound change in molybdenum prices.

Consolidated revenues, operating cash flows and net income vary significantly with fluctuations in the market prices of copper, gold and molybdenum, sales volumes and other factors. Based on the above projected consolidated sales volumes and assuming average prices of $3.25 per pound of copper, $1,100 per ounce of gold and $12 per pound of molybdenum in 2010, our consolidated operating cash flows would approximate $5.3 billion in 2010, net of an estimated $0.4 billion for working capital requirements. Operating cash flows for 2010 would be impacted by approximately $260 million for each $0.10 per pound change in copper prices, $50 million for each $50 per ounce change in gold prices and $45 million for each $1 per pound change in molybdenum prices.

Capital expenditures for 2010 are expected to approximate $1.7 billion, including $0.9 billion for sustaining capital and $0.8 billion for major projects. For 2009, capital expenditures totaled $1.6 billion, which included $0.8 billion for major projects, $0.6 billion for sustaining capital and $0.2 billion for a property acquisition adjacent to our Sierrita mine. We have announced initiatives to resume certain project development activities that were deferred in late 2008 (refer to “Current Development Projects” for further discussion). A number of studies are under way, which may result in increased capital spending programs.

### COPPER, GOLD AND MOLYBDENUM MARKETS

The graphs below illustrate the movements in metals prices from January 2000 through January 2010. World prices for copper, gold and molybdenum have fluctuated significantly during this period. The London Metal Exchange (LME) spot copper price varied from a low of $0.60 per pound in 2001 to a high of $4.08 per pound in 2008, the London gold price fluctuated from a low of $256 per ounce in 2001 to a high of $1,213 per ounce in 2009, and the *Metals Week* Molybdenum Dealer Oxide weekly average price ranged from a low of $2.19 per pound in 2000 to a high of $39.25 per pound in 2005. Copper, gold and molybdenum prices are affected by numerous factors beyond our control as described further in our “Risk Factors” contained in Part I, Item 1A of our Form 10-K for the year ended December 31, 2009.

\* Excludes Shanghai stocks, producer, consumer and merchant stocks.

The graph above presents LME spot copper prices and reported stocks of copper at the LME and the New York Mercantile Exchange (COMEX) from January 2000 through January 2010. From 2006 through most of 2008, disruptions associated with strikes and other operational issues, combined with growing demand from China and other emerging economies resulted in low levels of inventory. Beginning in late 2008, slowing consumption led to increases in inventory levels; however, China’s increased buying activity contributed to a decline in exchange inventories during the first half of 2009. After reaching a low for the year in July 2009, inventories grew during the second half of 2009 with combined LME and COMEX stocks totaling approximately 592 thousand metric tons, or approximately two weeks of global consumption, at December 31, 2009.

Turmoil in the United States (U.S.) financial markets and concerns about the global economy negatively impacted copper prices in late 2008, which declined to a four-year low of $1.26 per pound in December 2008; however, copper prices improved during 2009 as a result of strong Chinese import activity and supply limitations. During 2009, LME spot copper prices ranged from $1.38 per pound to $3.33 per pound, averaged $2.34 per pound and closed at $3.33 per pound on December 31, 2009. While the near-term outlook is uncertain, we believe the underlying fundamentals of the copper business remain positive, supported by limited supplies from existing mines and the absence of significant new development projects. Future copper prices are expected to be volatile and are likely to be influenced by demand from China, economic activity in the U.S. and other industrialized countries, the timing of the development of new supplies of copper and production levels of mines and copper smelters. The LME spot copper price closed at $3.11 per pound on January 29, 2010.

The graph above presents London gold prices from January 2000 through January 2010. Growing investment demand and a weak U.S. dollar have continued to support gold prices, which reached a new record high of $1,213 per ounce in December 2009. During 2009, gold prices ranged from approximately $810 per ounce to $1,213 per ounce, averaged approximately $972 per ounce and closed at $1,104 per ounce on December 31, 2009. London gold prices closed at $1,079 per ounce on January 29, 2010.

The graph above presents *Metals Week* Molybdenum Dealer Oxide weekly average prices from January 2000 through January 2010. In late 2008, molybdenum prices declined significantly as a result of the financial market turmoil and a decline in demand; however, molybdenum prices improved during 2009 supported by Chinese imports and supply reductions. During 2009, the weekly average price of molybdenum ranged from $7.83 per pound to $18.00 per pound, averaged $11.08 per pound and was $11.75 per pound on December 31, 2009. The *Metals Week* Molybdenum Dealer Oxide weekly average price was $14.88 per pound on January 29, 2010.

### CRITICAL ACCOUNTING ESTIMATES

Management’s Discussion and Analysis of Financial Condition and Results of Operations is based on our consolidated financial statements, which have been prepared in conformity with generally accepted accounting principles (GAAP) in the U.S. The preparation of these statements requires that we make estimates and assumptions that affect the reported amounts of assets, liabilities, revenues and expenses. We base these estimates on historical experience and on assumptions that we consider reasonable under the circumstances; however, reported results could differ from those based on the current estimates under different assumptions or conditions. The areas requiring the use of management’s estimates are also discussed in Note 1 under the subheading “Use of Estimates.” Management has reviewed the following discussion of its development and selection of critical accounting estimates with the Audit Committee of our Board of Directors.

*Mineral Reserves.* Recoverable proven and probable reserves are the part of a mineral deposit that can be economically and legally extracted or produced at the time of the reserve determination. The determination of reserves involves numerous uncertainties with respect to the ultimate geology of the ore bodies, including quantities, grades and recovery rates. Estimating the quantity and grade of reserves requires us to determine the size, shape and depth of our ore bodies by analyzing geological data, such as samplings of drill holes, tunnels and other underground workings. In addition to the geology of our mines, assumptions are required to determine the economic feasibility of mining these reserves, including estimates of future commodity prices and demand, the mining methods we use and the related costs incurred to develop and mine our reserves. Our estimates of recoverable proven and probable reserves are the responsibility of our employees, and a majority of these estimates have been reviewed and verified by independent experts in mining, geology and reserve determination.

The following table summarizes changes in our estimated consolidated recoverable proven and probable copper, gold and molybdenum reserves during 2008 and 2009:

|  | Copper (billion pounds) | Gold (million ounces) | Molybdenum (billion pounds) |
| --- | ---: | ---: | ---: |
| Consolidated reserves at December 31, 2007 | 93.2 | 41.0 | 2.04 |
| Net additions/revisions | 12.8 | 0.3 | 0.51 |
| Production | (4.0) | (1.3) | (0.07) |
| Consolidated reserves at December 31, 2008 | 102.0 | 40.0 | 2.48 |
| Net additions/revisions | 6.3 | (0.1) | 0.16 |
| Production | (4.1) | (2.7) | (0.05) |
| Consolidated reserves at December 31, 2009 | 104.2 | 37.2 | 2.59 |

Net additions to recoverable proven and probable copper reserves during 2008 included additions of 7.5 billion pounds at the Cerro Verde mine in South America, 3.9 billion pounds at our North America copper mines and 1.6 billion pounds at the Tenke Fungurume mine, partially offset by revisions at other mines. Net additions for 2008 replaced over 300 percent of our 2008 copper production. Net additions to recoverable copper reserves during 2009 include additions of 1.7 billion pounds at our North America copper mines, 3.0 billion pounds at our Cerro Verde mine in South America and 2.6 billion pounds at the Tenke Fungurume mine, partially offset by revisions at other mines. Net additions for 2009 replaced approximately 150 percent of current year copper production. Net additions to recoverable copper reserves reflect analysis of exploratory data gained through core drilling undertaken in 2007 and 2008, as well as exploration activities during 2009. Refer to Note 21 for further information regarding estimated recoverable proven and probable reserves.

As discussed in Note 1, we depreciate our life-of-mine mining and milling assets and values assigned to proven and probable reserves using the unit-of-production (UOP) method based on our estimated recoverable proven and probable reserves, and also have other assets that are depreciated on a straight-line basis over their estimated useful lives. Because the economic assumptions used to estimate reserves change from period to period and additional geological data is generated during the course of operations, estimates of reserves may change, which could have a significant impact on our results of operations, including changes to prospective depreciation rates and asset carrying values. Based on projected copper sales volumes for 2010 (refer to “Overview and Outlook”), if estimated copper reserves at our mines were 10 percent higher at December 31, 2009, we estimate that our annual depreciation, depletion and amortization expense for 2010 would decrease by $31 million ($15 million to net income attributable to FCX common stockholders), and a 10 percent decrease in copper reserves would increase depreciation, depletion and amortization expense by $38 million ($18 million to net income attributable to FCX common stockholders). We perform annual assessments of our existing assets in connection with the review of mine operating and development plans. If it is determined that assigned asset lives do not reflect the expected remaining period of benefit, any change could affect prospective depreciation rates.

At December 31, 2009, our long-lived assets include amounts assigned to proven and probable reserves totaling $4.3 billion. As discussed in Note 1, we review and evaluate our long-lived assets for impairment when events or changes in circumstances indicate that the related carrying amount of such assets may not be recoverable, and changes to our estimates of recoverable proven and probable reserves could have an impact on our assessment of asset recoverability.

*Impairment of Assets.* We evaluate our long-lived assets (to be held and used) for impairment when events or changes in circumstances indicate that the related carrying amount of such assets may not be recoverable. In evaluating our long-lived assets for recoverability, estimates of after-tax undiscounted future cash flows of our individual mining operations are used, with impairment losses measured by reference to fair value. As quoted market prices are unavailable for our individual mining operations, fair value is determined through the use of discounted estimated future cash flows. The estimated cash flows used to assess recoverability of our long-lived assets and measure fair value of our mining operations are derived from current business plans, which are developed using near-term price forecasts reflective of the current price environment and management’s projections for long-term average metal prices. In addition to near and long-term metal price assumptions, other key estimates include commodity-based and other input costs; proven and probable reserves, including any costs to develop the reserves and the timing of producing the reserves; and the use of appropriate escalation and discount rates.

Because the cash flows used to assess recoverability of our long-lived assets and measure fair value of our mining operations require us to make several estimates and assumptions that are subject to risk and uncertainty, changes in these estimates and assumptions could result in the impairment of our long-lived assets values. Events that could result in impairment of our long-lived assets include, but are not limited to, (i) decreases in future metal prices, (ii) decreases in estimated recoverable proven and probable reserves and (iii) any event that might otherwise have a material adverse effect on mine site production levels or costs.

During fourth-quarter 2008, we concluded that the then-current economic environment and significant declines in copper and molybdenum prices represented significant adverse changes in our business, and therefore, evaluated our long-lived assets for impairment. Projected metal prices represented the most significant assumption used in the cash flow estimates to assess recoverability and measure fair value of our individual mining operations. At the time of the March 2007 acquisition of Phelps Dodge, metal price projections used to value the net assets acquired ranged from near-term prices of $2.98 per pound for copper declining over an eight-year period to $1.20 per pound and $26.20 per pound for molybdenum declining over a five-year period to $8.00 per pound; our December 31, 2008, impairment evaluations were based on price assumptions reflecting prevailing copper futures prices for three years, which ranged from approximately $1.40 per pound to $1.50 per pound, and a long-term average price of $1.60 per pound. Molybdenum prices were assumed to average $8.00 per pound. Our evaluation resulted in the recognition of asset impairment charges totaling $10.9 billion ($6.6 billion to net loss attributable to FCX common stockholders or $17.34 per share) for 2008. Refer to Note 2 for further discussion of these asset impairment charges.

Additionally, goodwill was recorded in connection with the March 2007 acquisition of Phelps Dodge and was assigned to the reporting units, or individual mines, that were expected to benefit from the business combination. Goodwill is required to be evaluated at least annually and at any other time if an event or change in circumstances indicates that the fair value of a reporting unit is below its carrying amount. Our annual goodwill impairment test was performed in fourth-quarter 2008, which resulted in the full impairment of goodwill and the recognition of charges totaling $6.0 billion ($6.0 billion to net loss attributable to FCX common stockholders or $15.69 per share). Refer to Note 6 for further discussion.

*Recoverable Copper.* We record, as inventory, applicable costs for copper contained in mill and leach stockpiles that are expected to be processed in the future based on proven processing technologies. Mill and leach stockpiles are evaluated periodically to ensure that they are stated at the lower of cost or market (refer to Note 4 for discussion of lower of cost or market (LCM) inventory adjustments recorded in 2009 and 2008). Accounting for recoverable copper from mill and leach stockpiles represents a critical accounting estimate because (i) it is generally impracticable to determine copper contained in mill and leach stockpiles by physical count, and therefore, requires management to employ reasonable estimation methods and (ii) recovery rates from leach stockpiles can vary significantly. The quantity of material delivered to mill and leach stockpiles is based on surveyed volumes of mined material and daily production records. Sampling and assaying of blasthole cuttings determine the estimated copper grade contained in the material delivered to the mill and leach stockpiles.

Expected copper recovery rates for mill stockpiles are determined by metallurgical testing. The recoverable copper in mill stockpiles, once entered into the production process, can be extracted into copper concentrate almost immediately.

Expected copper recovery rates for leach stockpiles are determined using small-scale laboratory tests, small- to large-scale column testing (which simulates the production-scale process), historical trends and other factors, including mineralogy of the ore and rock type. Ultimate recovery of copper contained in leach stockpiles can vary significantly from a low percentage to more than 90 percent depending on several variables, including type of copper recovery, mineralogy and particle size of the rock. For newly placed material on active stockpiles, as much as 70 percent of the copper ultimately recoverable may be extracted during the first year, and the remaining copper may be recovered over many years.

Processes and recovery rates are monitored regularly, and recovery rate estimates are adjusted periodically as additional information becomes available and as related technology changes. At December 31, 2009, estimated recoverable copper was 2.7 billion pounds in leach stockpiles (with a carrying value of $1.5 billion) and 1.3 billion pounds in mill stockpiles (with a carrying value of $488 million).

*Reclamation and Closure Costs.* Reclamation is an ongoing activity that occurs throughout the life of a mine. We record the fair value of our estimated asset retirement obligations (AROs) associated with tangible long-lived assets in the period incurred. Fair value is measured as the present value of cash flow estimates after considering inflation and then applying a market risk premium. Our cost estimates are reflected on a third-party cost basis and comply with our legal obligation to retire tangible long-lived assets in the period incurred. These cost estimates may differ from financial assurance cost estimates for reclamation activities because of a variety of factors, including obtaining updated cost estimates for reclamation activities, the timing of reclamation activities, changes in scope and the exclusion of certain costs not considered reclamation and closure costs. Refer to Note 1 for further discussion of our accounting policy for reclamation and closure costs.

Generally, ARO activities are specified by regulations or in permits issued by the relevant governing authority, and management judgment is required to estimate the extent and timing of expenditures based on life-of-mine planning. Accounting for reclamation and closure costs represents a critical accounting estimate because (i) we will not incur most of these costs for a number of years, requiring us to make estimates over a long period, (ii) reclamation and closure laws and regulations could change in the future and/or circumstances affecting our operations could change, either of which could result in significant changes to our current plans, (iii) calculating the fair value of our AROs requires management to estimate projected cash flows, make long-term assumptions about inflation rates, determine our credit-adjusted, risk-free interest rates and determine market risk premiums that are appropriate for our operations and (iv) given the magnitude of our estimated reclamation and closure costs, changes in any or all of these estimates could have a significant impact on our results of operations.

At least annually, we review our ARO estimates for changes in the projected timing of certain reclamation costs, changes in cost estimates, and additional AROs incurred during the period. Following is a summary of changes in our AROs for the years ended December 31, 2009, 2008 and 2007 (in millions):

|  | 2009 | 2008 | 2007 |
| --- | ---: | ---: | ---: |
| Balance at beginning of year | $712 | $728 | $30 |
| Liabilities assumed in the acquisition of Phelps Dodge | – | – | 531 a |
| Liabilities incurred | 12 | 5 | 1 |
| Revisions to cash flow estimates | (17) | 21 | 179 b |
| Accretion expense | 52 | 51 | 27 |
| Spending | (28) | (91) | (40) |
| Foreign currency translation adjustment | – | (2) | – |
| Balance at end of year | $731 | $712 | $728 |

a. The fair value of AROs assumed in the acquisition of Phelps Dodge was estimated based on projected cash flows, an estimated long-term annual inflation rate of 2.4 percent, a discount rate based on FCX’s estimated credit-adjusted, risk-free interest rate of 7.8 percent and a market risk premium of 10 percent to reflect what a third-party might require to assume these AROs.

b. During 2007, Chino and Tyrone each submitted updated third-party closure cost estimates to the state of New Mexico as part of the permit renewal process. As a result, we revised our cash flow estimates and increased our ARO by $95 million for

Chino and $45 million for Tyrone. During 2009, Tyrone filed an appeal regarding the point of groundwater withdrawal. Finalized closure plan requirements, including those resulting from resolution of the appeal, may result in additional adjustments. Additionally, PT Freeport Indonesia updated its cost estimates primarily for changes to its plans for the treatment of acidic water, resulting in an increase of $33 million.

Refer to Note 14 for further discussion of reclamation and closure costs.

*Environmental Obligations.* Our mining, exploration, production and historical operating activities are subject to stringent laws and regulations governing the protection of the environment, and compliance with those laws requires significant expenditures. Environmental expenditures for closed facilities and closed portions of operating facilities are expensed or capitalized depending upon their future economic benefits. The general guidance provided by U.S. GAAP requires that liabilities for contingencies be recorded when it is probable that a liability has been incurred and the amount can be reasonably estimated. Refer to Note 1 for discussion of our accounting policy for environmental expenditures.

Accounting for environmental obligations represents a critical accounting estimate because changes to environmental laws and regulations and/or circumstances affecting our operations, could result in significant changes to our estimates, which could have a significant impact on our results of operations. We review changes in facts and circumstances associated with the environmental obligations on a quarterly basis. Judgments and estimates are based upon available facts, existing technology, presently enacted laws and regulations, remediation experience, whether or not we are a potentially responsible party (PRP), the ability of other PRPs to pay their allocated portions and take into consideration reasonably possible outcomes. Our cost estimates can change substantially as additional information becomes available regarding the nature or extent of site contamination, required remediation methods and actions by or against governmental agencies or private parties.

At December 31, 2009, environmental obligations recorded in our consolidated balance sheets totaled approximately $1.5 billion, which reflect obligations for environmental liabilities attributed to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) or analogous state programs and for estimated future costs associated with environmental matters at closed facilities and closed portions of certain operating facilities.

Following is a summary of changes in our estimated environmental obligations for the years ended December 31, 2009, 2008 and 2007 (in millions):

|  | 2009 | 2008 | 2007 |
| --- | ---: | ---: | ---: |
| Balance at beginning of year | $1,401 | $1,268 | $– |
| Liabilities assumed in the acquisition of Phelps Dodge | – | 117 | 1,334 |
| Accretion expensea | 102 | 95 | – |
| Additions | 40 | 36 | 6 |
| Reductions | (3) | (1) | (1) |
| Spending | (76) | (114) | (71) |
| Balance at end of year | $1,464 | $1,401 | $1,268 |

a. Represents accretion of the fair values of environmental obligations assumed in the acquisition of Phelps Dodge, which were determined on a discounted cash flow basis.

Refer to Note 14 for further discussion of environmental obligations.

*Deferred Taxes.* In preparing our annual consolidated financial statements, we estimate the actual amount of taxes currently payable or receivable as well as deferred tax assets and liabilities attributable to temporary differences between the financial statement carrying amounts of existing assets and liabilities and their respective tax bases. Deferred income tax assets and liabilities are measured using enacted tax rates expected to apply to taxable income in the years in which these temporary differences are expected to be recovered or settled. The effect on deferred tax assets and liabilities of a change in tax rates or laws is recognized in income in the period in which such changes are enacted.

A valuation allowance is provided for those deferred tax assets for which it is more likely than not that the related benefits will not be realized. In determining the amount of the valuation allowance, we consider estimated future taxable income as well as feasible tax planning strategies in each jurisdiction. If we determine that we will not realize all or a portion of our deferred tax assets, we will increase our valuation allowance. Conversely, if we determine that we will ultimately be able to realize all or a portion of the related benefits for which a valuation allowance has been provided, all or a portion of the related valuation allowance will be reduced.

At December 31, 2009, our valuation allowances totaled $2.2 billion and covered all of our U.S. foreign tax credit carryforwards and U.S. state net operating loss carryforwards, and a portion of our foreign net operating loss carryforwards and U.S. minimum tax credit carryforwards. This valuation allowance includes $44 million relating to tax benefits that, if recognized, would be credited directly to contributed capital. At December 31, 2008, our valuation allowances totaled $1.8 billion and covered all of our U.S. foreign tax credit carryforwards, U.S. minimum tax credit carryforwards, foreign net operating loss carryforwards and U.S. state net operating loss carryforwards, and also covered a portion of our net U.S. deferred tax assets. The $394 million increase in the valuation allowance during 2009 was primarily the result of an increase to the foreign tax credit carryforwards. Refer to Note 13 for further discussion.

### CONSOLIDATED RESULTS

| Financial Data (in millions, except per share amounts) | Years Ended December 31, 2009 |  | 2008 | 2007 |  |
| --- | ---: | --- | ---: | ---: | --- |
| Revenuesa | $15,040 | b | $17,796 b | $16,939 | b,c |
| Operating income (loss) | 6,503 | b | (12,710 )b,d,e | 6,555 | b,c,e |
| Income (loss) from continuing operations | 3,534 |  | (10,450) | 3,733 |  |
| Net income (loss) | 3,534 |  | (10,450) | 3,779 |  |
| Net income attributable to noncontrolling interests | 785 |  | 617 | 802 |  |
| Net income (loss) attributable to FCX common stockholdersf | 2,527 | g,h | (11,341 )d,e,h | 2,769 | c,e,h |
| Diluted net income (loss) per share attributable to FCX common |  |  |  |  |  |
| stockholders: |  |  |  |  |  |
| Continuing operations | $5.86 |  | $(29.72) | $7.41 |  |
| Discontinued operations | – |  | – | 0.09 |  |
| Diluted net income (loss) | $5.86 | g,h | $(29.72 )d,e,h | $7.50 | c,e,h |
| Diluted weighted-average common shares outstandingi | 469 |  | 382 | 397 |  |
| **Mining Operating Data** |  |  |  |  |  |
| Copper (recoverable) |  |  |  |  |  |
| Production (millions of pounds) | 4,103 |  | 4,030 | 3,367 |  |
| Sales, excluding purchases (millions of pounds) | 4,111 |  | 4,066 | 3,357 |  |
| Average realized price per pound | $2.60 |  | $2.69 | $3.29 | c |
| Site production and delivery costs per poundj | $1.12 |  | $1.51 | $1.18 |  |
| Unit net cash costs per poundj | $0.55 |  | $1.16 | $0.76 |  |
| Gold (recoverable) |  |  |  |  |  |
| Production (thousands of ounces) | 2,664 |  | 1,291 | 2,308 |  |
| Sales, excluding purchases (thousands of ounces) | 2,639 |  | 1,314 | 2,298 |  |
| Average realized price per ounce | $993 |  | $861 | $682 |  |
| Molybdenum (recoverable) |  |  |  |  |  |
| Production (millions of pounds) | 54 |  | 73 | 56 |  |
| Sales, excluding purchases (millions of pounds) | 58 |  | 71 | 52 |  |
| Average realized price per pound | $12.36 |  | $30.55 | $26.81 |  |

a. Includes the impact of adjustments to provisionally priced concentrate and cathode sales recognized in prior periods. Refer to “Revenues” and “Disclosures About Market Risks – Commodity Price Risk” for further discussion.

b. Following is a summary of revenues by operating division (in millions):

|  | Years Ended December 31, 2009 | 2008 | 2007 |
| --- | ---: | ---: | ---: |
| North America copper mines | $3,235 | $5,265 | $4,093 |
| South America copper mines | 3,839 | 4,166 | 3,879 |
| Indonesia mining | 5,908 | 3,412 | 4,808 |
| Africa mining | 389 | – | – |
| Molybdenum | 847 | 2,488 | 1,746 |
| Rod & Refining | 3,356 | 5,557 | 5,140 |
| Atlantic Copper Smelting & Refining | 1,892 | 2,341 | 2,388 |
| Corporate, other & eliminations | (4,426) | (5,433) | (5,115) |
| Total FCX revenues | $15,040 | $17,796 | $16,939 |

75

Following is a summary of operating income (loss) by operating division (in millions):

|  | Years Ended December 31, 2009 | 2008 | 2007 |
| --- | ---: | ---: | ---: |
| North America copper mines | $1,020 | $(11,522) | $1,428 |
| South America copper mines | 2,001 | (694) | 2,224 |
| Indonesia mining | 4,034 | 1,307 | 3,033 |
| Africa mining | 8 | (26) | (12) |
| Molybdenum | 126 | (1,473) | 353 |
| Rod & Refining | 14 | 2 | 14 |
| Atlantic Copper Smelting & Refining | (56) | 10 | 3 |
| Corporate, other & eliminations | (644) | (314) | (488) |
| Total FCX operating income (loss) | $6,503 | $(12,710) | $6,555 |

Refer to Note 20 for further discussion of our operating divisions and business segments.

c. Includes charges to revenues for mark-to-market accounting adjustments on the 2007 copper price protection program totaling $175 million ($106 million to net income attributable to FCX common stockholders or $0.27 per share) and a reduction in 2007 average realized copper prices of $0.05 per pound.

d. Includes long-lived asset impairments and other charges totaling $11.0 billion ($6.7 billion to net loss attributable to FCX common stockholders or $17.52 per share), goodwill impairment charges totaling $6.0 billion ($6.0 billion to net loss attributable to FCX common stockholders or $15.69 per share), and charges for LCM inventory adjustments totaling $782 million ($479 million to net loss attributable to FCX common stockholders or $1.26 per share). Refer to Notes 2 and 6 and “Critical Accounting Estimates – Asset Impairments” for further discussion.

e. Includes the impacts of purchase accounting fair value adjustments associated with the acquisition of Phelps Dodge, which were primarily because of increased carrying values of acquired property, plant and equipment and metal inventories, including mill and leach stockpiles, and also includes amounts for non-operating income and expense mostly related to accretion of the fair values of assumed environmental obligations (determined on a discounted cash flow basis). These impacts totaled $1.1 billion, including $1.0 billion to operating loss and $93 million for non-operating income and expenses, ($679 million to net loss attributable to FCX common stockholders or $1.78 per share) in 2008 and $1.3 billion to operating income ($793 million to net income attributable to FCX common stockholders or $2.00 per share) in 2007. Refer to Note 20 for a summary of the impacts of purchase accounting fair value adjustments on our business segments for the years ended December 31, 2008 and 2007.

f. After noncontrolling interests and preferred dividends.

g. Includes charges of $43 million ($0.09 per share) for the partial settlement of the City of Blackwell lawsuit (see Note 14), and also includes a favorable adjustment to income tax expense totaling $43 million ($0.09 per share) resulting from the completion of a review of U.S. deferred income tax accounts.

h. Includes net losses on early extinguishment and conversions of debt totaling $43 million ($0.09 per share) in 2009 associated with the redemption of our $340 million of 6⅞% Senior Notes and open-market purchases of our 8.25% Senior Notes, our 8.375% Senior Notes and our 8¾% Senior Notes, $5 million ($0.01 per share) in 2008 associated with an open-market purchase of our 9½% Senior Notes and $132 million ($0.33 per share) in 2007 primarily related to premiums paid and the accelerated recognition of deferred financing costs associated with early repayments of debt. Refer to Note 10 for further discussion.

i. As applicable, reflects assumed conversion of our 5½% Convertible Perpetual Preferred Stock (which converted into 17.9 million shares of FCX common stock in September 2009) and 6¾% Mandatory Convertible Preferred Stock (refer to Note 12). In addition, the 2009 period includes the effects of the 26.8 million shares of common stock we sold in February 2009. Common shares outstanding on December 31, 2009, totaled 430 million.

j. Reflects per pound weighted average production and delivery costs and unit net cash costs (net of by-product credits) for all copper mines, excluding net noncash and nonrecurring costs and Africa mining. For reconciliations of the per pound costs by operating division to production and delivery costs applicable to sales reported in our consolidated financial statements, refer to “Operations – Unit Net Cash Costs” and to “Product Revenues and Production Costs.”

### Revenues

Consolidated revenues include the sale of copper concentrates, copper cathodes, copper rod, molybdenum, gold and other metals by our North and South America copper mines, the sale of copper concentrates (which also contain significant quantities of gold and silver) by our Indonesia mining operation, the sale of copper cathodes and cobalt hydroxide by our Africa mining operation, the sale of molybdenum in various forms by our Molybdenum operations, and the sale of copper cathodes, copper anodes, and gold in anodes and slimes by Atlantic Copper. Our mining revenues for 2009 include sales of copper (approximately 75 percent), gold (approximately 17 percent) and molybdenum (approximately 5 percent).

Consolidated revenues totaled $15.0 billion in 2009, compared with $17.8 billion in 2008 and $16.9 billion in 2007. Following is a summary of year-to-year changes in our consolidated revenues (in millions):

|  | 2009 | 2008 |
| --- | ---: | ---: |
| Consolidated revenues – prior year | $17,796 | $16,939 |
| Higher (lower) sales volumes from mining operations: |  |  |
| Copper | 121 | 2,367 |
| Gold | 1,141 | (671) |
| Molybdenum | (395) | 505 |
| Higher (lower) price realizations from mining operations: |  |  |
| Copper | (288) | (2,631) |
| Gold | 349 | 235 |
| Molybdenum | (1,056) | 266 |
| Lower purchased copper and molybdenum | (1,414) | (5) |
| (Lower) higher adjustments, primarily for prior year provisionally priced sales | (239) | 309 |
| Lower Atlantic Copper revenues | (449) | (47) |
| Impact of the 2007 copper price protection program | – | 175 |
| Other, including intercompany eliminations | (526) | 354 |
| Consolidated revenues – current year | $15,040 | $17,796 |

#### 2009 Compared with 2008

Consolidated sales volumes totaled 4.1 billion pounds of copper, 2.6 million ounces of gold and 58 million pounds of molybdenum in 2009, compared with 4.1 billion pounds of copper, 1.3 million ounces of gold and 71 million pounds of molybdenum in 2008. Higher copper sales volumes in 2009, when compared with 2008 (45 million pounds), primarily resulted from mining in a higher grade section of the Grasberg open pit and the contribution of 2009 sales volumes from the Tenke Fungurume mine, partly offset by lower sales volumes as a result of production curtailments at the North America copper mines and lower ore grades at Candelaria. Mining in a higher-grade section of the Grasberg open pit also resulted in substantially higher gold sales volumes in 2009. Lower molybdenum sales volumes in 2009 reflected reduced demand in the metallurgical and chemical sectors. Refer to “Operations” for further discussion of sales volumes at our operating divisions.

Consolidated revenues in 2009 were also impacted by lower copper and molybdenum prices compared to 2008. Realized copper prices decreased in 2009 to an average of $2.60 per pound, compared with $2.69 per pound in 2008. More significantly, realized molybdenum prices decreased to an average of $12.36 per pound in 2009, compared with $30.55 per pound in 2008. Partly offsetting lower copper and molybdenum prices were higher realized gold prices, which increased to an average of $993 per ounce in 2009, compared with $861 per ounce in 2008.

We primarily purchase copper cathode to be processed by our Rod and Refining segment when production from our North America copper mines does not meet customer demand. Accordingly, the decrease in purchased copper for 2009, compared to 2008, resulted from lower demand.

Under the long-established structure of sales agreements prevalent in the industry, substantially all of our concentrate and cathode sales are provisionally priced at the time of shipment. The provisional prices are finalized in a contractually specified future period (generally one to four months from the shipment date) based primarily on quoted LME prices (refer to “Disclosures About Market Risks – Commodity Price Risk” for further discussion). Adjustments to the December 31, 2008, provisionally priced copper sales resulted in a net increase to consolidated revenues of $132 million ($61 million to net income attributable to FCX common stockholders or

$0.13 per share) in 2009, compared with an increase of $268 million ($114 million to net loss attributable to FCX common stockholders or $0.30 per share) in 2008.

#### 2008 Compared with 2007

Consolidated sales volumes in 2008 totaled 4.1 billion pounds of copper, 1.3 million ounces of gold and 71 million pounds of molybdenum, compared with 3.4 billion pounds of copper, 2.3 million ounces of gold and 52 million pounds of molybdenum in 2007. Higher copper and molybdenum sales volumes in 2008 reflected a full twelve months of sales at our North and South America copper mines and Molybdenum operations, compared with 2007, which included sales from these operations beginning March 20, 2007. Higher copper sales volumes in 2008 also reflected additional copper production from the Safford mine, which began production in December 2007, and higher production from the Cerro Verde concentrator, which reached design capacity in mid-2007. Gold sales volumes for 2008 were lower than in 2007 because of mining in a lower-grade section of the Grasberg open pit during the first nine months of 2008, which resulted in lower grades and recovery rates. Refer to “Operations” for further discussion of sales volumes at our operating divisions.

Realized copper prices decreased in 2008 to an average of $2.69 per pound, compared with $3.34 per pound (excluding the impact from the 2007 copper price protection program) in 2007. Realized gold and molybdenum prices increased in 2008 to an average of $861 per ounce for gold and $30.55 per pound for molybdenum, compared with $682 per ounce for gold and $26.81 per pound for molybdenum in 2007.

Adjustments to the December 31, 2007, provisionally priced copper sales increased consolidated revenues by $268 million ($114 million to net loss attributable to FCX common stockholders or $0.30 per share) in 2008, compared with a decrease of $42 million ($18 million to net income attributable to FCX common stockholders or $0.05 per share) in 2007.

On limited past occasions, in response to market conditions, we have entered into copper and gold price protection contracts for a portion of our expected future mine production to mitigate the risk of adverse price fluctuations. Also, in connection with the Phelps Dodge acquisition, we assumed the 2007 copper price protection program, which resulted in charges to revenues in 2007 totaling $175 million ($106 million to net income attributable to FCX common stockholders or $0.27 per share). The 2007 copper price protection program matured on December 31, 2007. We do not currently intend to enter into similar hedging programs in the future.

### Production and Delivery Costs

#### 2009 Compared with 2008

Consolidated production and delivery costs totaled $7.0 billion in 2009 compared with $10.4 billion in 2008. Lower production and delivery costs for 2009 primarily reflect the effects of lower operating rates at our North America copper mines, lower commodity-based input costs and lower purchases of copper.

Our copper mining operations require significant energy, principally electricity, diesel, coal and natural gas. Commodity-based input costs began declining in late 2008 and we realized the benefits of these declines in 2009. Excluding Africa mining, energy costs approximated 20 percent of our consolidated copper production costs in 2009, compared with approximately 25 percent in 2008, and included purchases of approximately 190 million gallons of diesel fuel, 5,700 gigawatt hours of electricity at our North and South America mines (we generate all of our power at our Indonesia mining operation), 800 thousand metric tons of coal for our coal power plant in Indonesia, and 1 million MMBTU (million british thermal units) of natural gas at certain of our North America mines. For 2010, we estimate energy costs, excluding Africa mining, will approximate 22 percent of our consolidated copper production costs.

Consolidated unit site production and delivery costs for our copper mining operations, excluding net noncash and nonrecurring costs and Africa mining, averaged $1.12 per pound of copper in 2009, compared with $1.51 per pound of copper in 2008. Lower site production and delivery costs in 2009 reflected higher copper ore grades at Grasberg, reduced operating rates at our North America copper mines to suspend production of high-cost incremental volumes, achievement of cost savings initiatives and operating efficiencies, and lower energy and other commodity-based input costs. Refer to “Operations – Unit Net Cash Costs” for further discussion of unit net cash costs associated with our operating divisions, and to “Product Revenues and Production Costs” for reconciliations of per pound costs by operating division to production and delivery costs applicable to sales reported in our consolidated financial statements. We will incorporate Africa mining in our consolidated unit net cash cost disclosures upon completion of ramp-up activities, which is expected in 2010.

#### 2008 Compared with 2007

Consolidated production and delivery costs totaled $10.4 billion in 2008 compared with $8.5 billion in 2007. Higher production and delivery costs for 2008 reflect a full year of costs associated with our acquired copper and molybdenum operations in North and South America and the impact of higher costs, principally for commodity-based input costs such as energy and sulphuric acid. Partly offsetting these higher costs were $656 million of lower purchase accounting impacts associated with increased inventory values that were mostly realized in 2007.

### Depreciation, Depletion and Amortization

#### 2009 Compared with 2008

Consolidated depreciation, depletion and amortization expense totaled $1.0 billion in 2009 compared with $1.8 billion in 2008. The decrease in depreciation, depletion and amortization expense reflected the impact of long-lived asset impairments recognized at December 31, 2008 (refer to “Critical Accounting Estimates – Impairments of Assets” for further discussion).

#### 2008 Compared with 2007

Consolidated depreciation, depletion and amortization expense totaled $1.8 billion in 2008 compared with $1.2 billion in 2007. The increase in depreciation, depletion and amortization expense reflected higher purchase accounting impacts of $293 million primarily related to a full twelve months in 2008, and also reflected higher depreciation expense under the unit-of-production method resulting from a full year of production from our North and South America copper mines in 2008.

### LCM Inventory Adjustments

Inventories are required to be recorded at the lower of cost or market. In first-quarter 2009, we recognized charges of $19 million ($15 million to net income attributable to FCX common stockholders or $0.03 per share) for lower of cost or market (LCM) molybdenum inventory adjustments. There were no further LCM inventory adjustments recorded subsequent to first-quarter 2009.

In 2008, we recorded LCM inventory adjustments totaling $782 million ($479 million to net loss attributable to FCX common stockholders or $1.26 per share). Inventories acquired in connection with the acquisition of Phelps Dodge (including long-term mill and leach stockpiles) were recorded at fair value using near-term price forecasts reflecting the then-current price environment and management’s projections for long-term average metal prices. The charges recognized in 2008 were based on prevailing copper futures prices for three years, which ranged from approximately $1.40 per pound to $1.50 per pound, and a long-term average price of $1.60 per pound. Molybdenum prices were assumed to average $8.00 per pound.

### Selling, General and Administrative Expenses

#### 2009 Compared with 2008

Consolidated selling, general and administrative expenses totaled $321 million in 2009 compared with $269 million in 2008. Higher selling, general and administrative expenses primarily reflected a net increase in incentive compensation costs, partly offset by reductions associated with administrative costs savings initiatives.

#### 2008 Compared with 2007

Consolidated selling, general and administrative expenses totaled $269 million in 2008 compared with $466 million in 2007. Lower selling, general and administrative expenses primarily reflected lower incentive compensation costs in 2008 because of weaker financial results.

### Exploration and Research Expenses

Exploration activities are being conducted near our existing mines with a focus on opportunities to expand reserves that will support additional future production capacity in the large mineral districts where we currently operate. Significantly expanded drilling activities during 2007 and 2008 were successful in providing reserve additions and in identifying potential additional ore adjacent to existing ore bodies. Results indicate opportunities for future potential reserve additions at Morenci, Sierrita and Bagdad in North America, at Cerro Verde in South America and in the Tenke Fungurume district.

Consolidated exploration and research expenses totaled $90 million in 2009, $292 million in 2008 and $145 million in 2007. Throughout most of 2008, expenditures primarily reflected increased exploration efforts in North America and also in Africa, including targets outside the area of initial development at Tenke Fungurume. However, in response to weak market conditions at the end of 2008, we revised operating plans to significantly reduce exploration costs in 2009. During 2009, we focused on analyzing exploration data gained through the core drilling previously undertaken in addition to conducting new activities. For 2010, exploration expenditures are expected to approximate $100 million. Exploration activities will continue to focus on the potential in our existing mineral districts.

### Long-Lived Asset Impairments and Other Charges

During 2009, net restructuring and other charges totaled $77 million ($61 million to net income attributable to FCX common stockholders or $0.13 per share), which included charges of $54 million ($43 million to net income or $0.09 per share) associated with the partial settlement of the City of Blackwell lawsuit.

During 2008, we recognized charges totaling $11.0 billion ($6.7 billion to net loss attributable to FCX common stockholders or $17.52 per share) for long-lived asset impairments and other charges. During fourth-quarter 2008, we concluded that the declines in copper and molybdenum prices and the deterioration of the economic environment represented significant adverse changes in the business, and therefore evaluated our long-lived assets for impairment as of December 31, 2008, which resulted in the recognition of asset impairment charges totaling $10.9 billion ($6.6 billion to net loss attributable to FCX common stockholders or $17.34 per share). In addition, during fourth-quarter 2008, we recorded net restructuring and other charges totaling $111 million ($67 million to net loss attributable to FCX common stockholders or $0.18 per share) associated with our revised operating plans, including contract termination costs, other project cancellation costs, employee severance and benefits and special retirement benefits and curtailments.

Refer to Note 2 for further discussion of these charges.

### Goodwill Impairment

Our annual impairment test of goodwill at December 31, 2008, resulted in the recognition of goodwill impairment charges totaling $6.0 billion ($6.0 billion to net loss attributable to FCX common stockholders or $15.69 per share). Refer to Note 6 for further discussion.

### Interest Expense, Net

Consolidated interest expense (before capitalization) totaled $664 million in 2009, $706 million in 2008 and $660 million in 2007. Lower interest expense in 2009, compared with 2008, primarily reflected net repayments of debt and lower interest rates on our variable-rate debt during 2009. Higher interest expense in 2008, compared with 2007, primarily reflected the impacts associated with accretion of the fair values of environmental obligations (determined on a discounted cash flow basis) assumed in the acquisition of Phelps Dodge, partly offset by lower interest expense associated with net repayments of debt during 2007. Refer to “Capital Resources and Liquidity – Financing Activities” for discussion of debt repayments.

Capitalized interest is primarily related to our development projects and totaled $78 million in 2009, $122 million in 2008 and $147 million in 2007. The decrease in capitalized interest in 2009 primarily reflects the substantial completion of development activities at our Tenke Fungurume mine. Refer to “Current Development Projects” for further discussion.

### Losses on Early Extinguishment of Debt

During 2009, we recorded losses on early extinguishment of debt totaling $48 million ($43 million to net income attributable to FCX common stockholders or $0.09 per share), including $14 million ($13 million to net income attributable to FCX common stockholders) associated with the redemption of our $340 million of 6⅞% Senior Notes and $34 million ($30 million to net income attributable to FCX common stockholders) for open-market purchases of our 8.25% Senior Notes, 8.375% Senior Notes and 8¾% Senior Notes.

During 2008, we recorded net losses on early extinguishment of debt totaling $6 million ($5 million to net loss attributable to FCX common stockholders or $0.01 per share) associated with an open-market purchase of $33 million of our 9½% Senior Notes.

During 2007, we recorded net losses on early extinguishment of debt totaling $173 million ($132 million to net income attributable to FCX common stockholders or $0.33 per share) primarily related to the accelerated recognition of deferred financing costs associated with early repayment of amounts under the $11.5 billion senior credit facility, including the refinancing of the Tranche B term loan. Also included was $17 million ($10 million to net income attributable to FCX common stockholders or $0.02 per share) related to premiums paid and the accelerated recognition of deferred financing costs associated with the May 2007 redemption of our 10⅛% Senior Notes.

Refer to Note 10 for further discussion of these transactions.

### Gains on Sales of Assets

Gains on sales of assets totaled $13 million ($8 million to net loss attributable to FCX common stockholders or $0.02 per share) in 2008 and $85 million ($52 million to net income attributable to FCX common stockholders or $0.13 per share) in 2007 primarily associated with sales of marketable securities.

### Other (Expense) Income, Net

Other (expense) income, net, totaled $(53) million in 2009, $(22) million in 2008 and $157 million in 2007. The decrease in 2009, compared with 2008, primarily related to lower interest income ($46 million). The decrease in 2008, compared with 2007, primarily related to lower interest income ($82 million) and higher foreign currency exchange losses ($64 million) mostly associated with estimated Chilean tax payments.

### (Provision for) Benefit from Income Taxes

Our income tax provision for 2009 resulted from taxes on international operations ($2.3 billion) and U.S. operations ($35 million). Our effective tax rate is sensitive to changes in commodity prices and the mix of income between U.S. and international operations. The difference between our consolidated effective income tax rate of 40 percent in 2009 and the U.S. federal statutory rate of 35 percent primarily was attributable to the high proportion of income earned in Indonesia, which was taxed at an effective tax rate of 42 percent.

Our benefit from income taxes in 2008 resulted from U.S. operations ($3.4 billion), partly offset by taxes on international operations ($604 million). The difference between our consolidated effective income tax rate of 21 percent in 2008 and the U.S. federal statutory rate of 35 percent primarily was attributable to goodwill impairment charges, which were non-deductible for tax purposes, and the recognition of a valuation allowance against U.S. federal alternative minimum tax credits, partly offset by benefits for percentage depletion and U.S. state income taxes.

A summary of the approximate amounts in the calculation of our consolidated (provision for) benefit from income taxes for 2009 and 2008 follows (in millions, except percentages):

|  | Year Ended December 31, 2009 Income (Loss)a | Effective Tax Rate | Income Tax (Provision) Benefit | Year Ended December 31, 2008 Income (Loss)a | Effective Tax Rate | Income Tax (Provision) Benefit |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| U.S. | $117 | 70% | $(82) | $1,258 | 15% | $(191) |
| South America | 2,010 | 32% | (650) | 1,752 | 32% | (553) |
| Indonesia | 4,000 | 42% | (1,697) | 1,432 | 43% | (612) |
| Africa | (60) | 25% | 15 | (187) | 35% | 66 |
| Asset impairment charges | – | N/A | – | (10,867) | 39% | 4,212 |
| Goodwill impairment charges | – | N/A | – | (5,987) | N/A | – |
| LCM inventory adjustments | (19) | 20% | 4 | (782) | 38% | 299 |
| Eliminations and other | (232) | N/A | 60 | 72 | N/A | (18) |
| Adjustments | N/A | N/A | 43 b | N/A | N/A | (359 )c |
| Consolidated FCX | $5,816 | 40% | $(2,307) | $(13,309) | 21% | $2,844 |

a. Represents income (loss) from continuing operations (by geographic location) before income taxes and equity in affiliated companies’ net earnings.

b. Includes a favorable adjustment totaling $43 million resulting from completion of a review of U.S. deferred income tax accounts.

c. Represents an adjustment to establish a valuation allowance against U.S. federal alternative minimum tax credits.

Our estimated consolidated effective tax rate for 2010 will vary with commodity price changes and the mix of income from international and U.S. operations. Assuming average prices of $3.25 per pound for copper, $1,100 per ounce for gold, $12 per pound for molybdenum and current sales estimates, we estimate our annual consolidated effective tax rate will approximate 37 percent; however, the rate would range from approximately 40 percent at $2.50 per pound for copper to approximately 37 percent at $3.50 per pound for copper.

Our income tax provision from continuing operations in 2007 resulted from taxes on international operations ($2.2 billion) and U.S. operations ($215 million). The difference between our consolidated effective income tax rate of 39 percent for 2007 and the U.S. federal statutory rate of 35 percent primarily was attributable to (i) withholding taxes related to earnings from Indonesia and South America mining operations, (ii) a U.S. foreign tax credit limitation and (iii) an adjustment associated with the reversal of the Phelps Dodge indefinite reinvestment assertion on certain earnings in South America, partly offset by a U.S. benefit for percentage depletion and an international tax rate differential.

A summary of the approximate amounts in the calculation of our consolidated provision for income taxes for 2007 follows (in millions, except percentages):

|  | Year Ended December 31, 2007 Income (Loss)a | Effective Tax Rate | Income Tax Provision |
| --- | ---: | ---: | ---: |
| U.S. | $976 | 22% | $(215) |
| South America | 2,254 | 33% | (742) |
| Indonesia | 2,860 | 46% | (1,326) |
| Africa | (3) | NM\* | (4) |
| Eliminations and other | 24 | N/A | (2) |
| Adjustments | N/A | N/A | (111 )b |
| Consolidated FCX | $6,111 | 39% | $(2,400) |

\* NM = Not meaningful

a. Represents income from continuing operations (by geographic location) before income taxes and equity in affiliated companies’ net earnings.

b. Represents an adjustment for a one-time charge associated with the reversal of the Phelps Dodge indefinite reinvestment assertion on certain earnings in South America. This adjustment was fully offset by a reduction in noncontrolling interests’ share of net income.

Refer to Note 13 for further discussion of income taxes.

### OPERATIONS

*For comparative purposes, certain of the operating data included in this section for our North America copper mines, South America copper mines and Molybdenum operations for the year 2007, combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.*

### North America Copper Mines

We currently have six operating copper mines in North America – Morenci, Sierrita, Bagdad, Safford and Miami in Arizona, and Tyrone in New Mexico. All of these mining operations are wholly owned, except for Morenci, an unincorporated joint venture, in which we own an 85 percent undivided interest.

The North America copper mines include open-pit mining, sulfide ore concentrating, leaching and solution extraction/electrowinning (SX/EW) operations. In addition to copper, the Morenci, Sierrita and Bagdad mines produce molybdenum as a by-product. A majority of the copper produced at our North America copper mines is cast into copper rod by our Rod & Refining operations. Rod and wire sales to outside wire and cable manufacturers represented approximately 72 percent of North America copper sales in 2009. The remainder of our North America copper sales is primarily in the form of copper cathode or copper concentrate. Refer to Note 20 for further discussion of our reportable segment in the North America copper mines division.

In response to weak market conditions, operating plans at our North America copper mines were revised at the end of 2008 and in early 2009 primarily to reflect curtailed production rates, capital cost reductions and the incorporation of reduced input costs (refer to Note 2 for further discussion). In October 2009, we announced initiatives to resume limited mining activities at the Miami mine in Arizona. This project, which was deferred in late 2008, will improve efficiencies of ongoing reclamation projects associated with historical mining operations at the site. In addition, we are initiating activities to restart the Morenci mill, which was temporarily idled in February 2009, to process available sulfide material currently being mined. Refer to “Current Development Projects” for further discussion of these development projects. Operating plans at our North America copper mines continue to be reviewed and additional adjustments will be made in response to changes in market conditions.

In December 2009, we purchased property adjacent to our Sierrita operations, which includes the Twin Buttes copper mine, that ceased operations in 1994 (refer to “Current Development Projects” for further discussion).

Operating Data. Following is summary operating data for the North America copper mines for the years ended December 31, 2009, 2008 and 2007. The operating data for 2007 combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.

| Operating Data, Net of Joint Venture Interest Copper (millions of recoverable pounds) | 2009 | 2008 | 2007a |  |
| --- | ---: | ---: | ---: | --- |
| Production | 1,147 | 1,430 | 1,320 |  |
| Sales, excluding purchases | 1,187 | 1,434 | 1,332 |  |
| Average realized price per pound | $2.38 | $3.07 | $3.10 | b |
| Molybdenum (millions of recoverable pounds) |  |  |  |  |
| Productionc | 25 | 30 | 30 |  |
| **100% Operating Data** |  |  |  |  |
| SX/EW operations |  |  |  |  |
| Leach ore placed in stockpiles (metric tons per day) | 589,400 | 1,095,200 | 798,200 |  |
| Average copper ore grade (percent) | 0.29 | 0.22 | 0.23 |  |
| Copper production (millions of recoverable pounds) | 859 | 943 | 940 |  |
| Mill operations |  |  |  |  |
| Ore milled (metric tons per day) | 169,900 | 249,600 | 223,800 |  |
| Average ore grade (percent): |  |  |  |  |
| Copper | 0.33 | 0.40 | 0.35 |  |
| Molybdenum | 0.02 | 0.02 | 0.02 |  |
| Copper recovery rate (percent) | 86.0 | 82.9 | 84.5 |  |
| Production (millions of recoverable pounds): |  |  |  |  |
| Copper | 364 | 599 | 501 |  |
| Molybdenum | 25 | 30 | 30 |  |

a. The North America copper mines’ operating data for 2007 combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.

b. Amount was $3.25 per pound of copper before charges for mark-to-market accounting adjustments on the 2007 copper price protection program.

c. Reflects by-product molybdenum production from the North America copper mines. Sales of by-product molybdenum are reflected in the Molybdenum division.

#### 2009 Compared with 2008

Copper sales volumes from our North America copper mines decreased to 1.2 billion pounds in 2009, compared with 1.4 billion pounds in 2008. Certain of our North America copper mines continue to operate at reduced rates in response to reduced demand for copper in the western world. Copper sales volumes from our North America copper mines are expected to approximate 1.0 billion pounds in 2010 which reflects the impacts of reduced 2009 mining activities on 2010 leaching operations. By-product molybdenum production from our North America copper mines is expected to approximate 30 million pounds in 2010.

#### 2008 Compared with 2007

Copper sales from the North America mines increased to 1.4 billion pounds in 2008, compared with 1.3 billion pounds for the combined year 2007, primarily reflecting additional copper production from the Safford mine, which began production in December 2007 and was ramping up to design capacity during 2008 before operating plans were revised in fourth-quarter 2008 to curtail production.

Unit Net Cash Costs. Unit net cash costs per pound of copper is a measure intended to provide investors with information about the cash-generating capacity of our mining operations expressed on a basis relating to the primary metal product for our respective operations. We use this measure for the same purpose and for monitoring operating performance by our mining operations. This information differs from measures of performance determined in accordance with U.S. GAAP and should not be considered in isolation or as a substitute for measures of performance determined in accordance with U.S. GAAP. This measure is presented by other mining companies, although our measure may not be comparable to similarly titled measures reported by other companies.

#### Gross Profit per Pound of Copper and Molybdenum

The following tables summarize unit net cash costs and gross profit per pound at the North America copper mines for the years ended December 31, 2009 and 2008, and for the period March 20, 2007, through December 31, 2007. Refer to “Product Revenues and Production Costs” for an explanation of the “by-product” and “co-product” methods and a reconciliation of unit net cash costs per pound to production and delivery costs applicable to sales reported in our consolidated financial statements.

#### 2009 Compared with 2008

|  | 2009 By- Product Method | Co-Product Method Copper | Molyb- denuma | 2008 By- Product Method | Co-Product Method Copper | Molyb- denuma |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $2.38 | $2.38 | $10.96 | $3.07 | $3.07 | $30.25 |
| Site production and delivery, before net noncash |  |  |  |  |  |  |
| and nonrecurring costs shown below | 1.25 | 1.15 | 5.67 | 1.88 | 1.63 | 12.67 |
| By-product creditsa | (0.23) | – | – | (0.64) | – | – |
| Treatment charges | 0.09 | 0.09 | – | 0.09 | 0.09 | – |
| Unit net cash costs | 1.11 | 1.24 | 5.67 | 1.33 | 1.72 | 12.67 |
| Depreciation, depletion and amortization | 0.22 | 0.21 | 0.40 | 0.53 | 0.46 | 2.81 |
| Noncash and nonrecurring costs, net | 0.11 | 0.11 | 0.07 | 0.52 | 0.49 | 1.34 |
| Total unit costs | 1.44 | 1.56 | 6.14 | 2.38 | 2.67 | 16.82 |
| Revenue adjustments, primarily for hedging | 0.08 | 0.08 | – | (0.05) | (0.05) | – |
| Idle facility and other non-inventoriable costs | (0.08) | (0.08) | – | (0.06) | (0.06) | (0.05) |
| Gross profit per pound | $0.94 | $0.82 | $4.82 | $0.58 | $0.29 | $13.38 |
| Copper sales (millions of recoverable pounds) | 1,185 | 1,185 |  | 1,430 | 1,430 |  |
| Molybdenum sales (millions of recoverable pounds)b |  |  | 25 |  |  | 30 |

a. Molybdenum by-product credits and revenues reflect volumes produced at market-based pricing and also include tolling revenues at Sierrita.

b. Reflects molybdenum produced by the North America copper mines.

Unit net cash costs (net of by-product credits) for our North America copper mines decreased to $1.11 per pound of copper in 2009, compared with $1.33 per pound in 2008, primarily reflecting a net decrease in site production and delivery costs ($0.63 per pound) associated with cost reduction and efficiency efforts, including the impact of lower operating rates and reduced input costs (principally for energy), partly offset by changes in inventory, which reflects the impact of historical higher cost production on inventory carrying values. The decrease in site production and delivery costs was partly offset by lower molybdenum credits ($0.41 per pound) primarily resulting from lower molybdenum prices and sales volumes.

Our operating North America copper mines have varying cost structures because of differences in ore grades and ore characteristics, processing costs, by-products and other factors. During 2009, unit net cash costs for the North America copper mines ranged from a net cost of $0.91 per pound to $1.66 per pound at the individual mines and averaged $1.11 per pound. Based on current operating plans and assuming achievement of current sales estimates and average prices of $12 per pound of molybdenum for 2010, we estimate that average unit net cash costs (net of by-product credits) for our North America copper mines would approximate $1.23 per pound of copper in 2010. Unit net cash costs for 2010 are expected to be higher, compared with 2009, primarily because of higher input costs and lower volumes, partly offset by higher molybdenum credits. Each $1 per pound change in the average molybdenum price during the year would have an approximate $0.02 per pound impact on the North America copper mines’ 2010 unit net cash costs.

The decrease in depreciation, depletion and amortization in 2009, compared with 2008, primarily reflected the impact of the long-lived asset impairment charges recognized in fourth-quarter 2008 (refer to Note 2 for further discussion).

Noncash and nonrecurring costs consist of items such as LCM inventory adjustments and other unusual charges. Noncash and nonrecurring costs for 2008 include charges for LCM inventory adjustments, which totaled $661 million, or $0.46 per pound in 2008; there were no LCM copper inventory adjustments recorded at the North America mines in 2009.

Revenue adjustments primarily reflect unrealized gains (losses) on copper derivative contracts entered into with our U.S. copper rod customers, which allow us to receive market prices in the month of shipment while the customer pays the fixed price they requested (refer to Note 16 for further discussion).

#### 2008 Compared with 2007

|  | 2008 By- Product Method | Co-Product Method Copper | Molyb- denumb | 2007a By- Product Method | Co-Product Method Copper | Molyb- denumb |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $3.07 | $3.07 | $30.25 | $3.40 | $3.40 | $30.69 |
| Site production and delivery, before net noncash |  |  |  |  |  |  |
| and nonrecurring costs shown below | 1.88 | 1.63 | 12.67 | 1.46 | 1.25 | 10.85 |
| By-product creditsb | (0.64) | – | – | (0.69) | – | – |
| Treatment charges | 0.09 | 0.09 | – | 0.10 | 0.10 | – |
| Unit net cash costs | 1.33 | 1.72 | 12.67 | 0.87 | 1.35 | 10.85 |
| Depreciation, depletion and amortization | 0.53 | 0.46 | 2.81 | 0.47 | 0.40 | 2.89 |
| Noncash and nonrecurring costs, net | 0.52 | 0.49 | 1.34 | 0.35 | 0.33 | 0.15 |
| Total unit costs | 2.38 | 2.67 | 16.82 | 1.69 | 2.08 | 13.89 |
| Revenue adjustments, primarily for hedging | (0.05) | (0.05) | – | (0.20) | (0.20) | – |
| Idle facility and other non-inventoriable costs | (0.06) | (0.06) | (0.05) | (0.05) | (0.05) | (0.03) |
| Gross profit per pound | $0.58 | $0.29 | $13.38 | $1.46 | $1.07 | $16.77 |
| Copper sales (millions of recoverable pounds) | 1,430 | 1,430 |  | 1,038 | 1,038 |  |
| Molybdenum sales (millions of recoverable pounds)c |  |  | 30 |  |  | 23 |

a. Reflects the period from March 20, 2007, through December 31, 2007.

b. Molybdenum by-product credits and revenues reflect volumes produced at market-based pricing and also include tolling revenues at Sierrita.

c. Reflects molybdenum produced by the North America copper mines.

Unit net cash costs (net of by-product credits) for our North America copper mines increased to $1.33 per pound of copper in 2008, compared with $0.87 per pound of copper for the period March 20, 2007, through December 31, 2007, primarily reflecting production cost increases associated with higher mining costs and milling rates, higher energy costs and costs of other consumables and higher costs associated with Safford as the mine ramped up to full production rates.

The increase in noncash and nonrecurring costs for 2008 primarily reflected charges for LCM inventory adjustments in 2008 totaling $661 million ($0.46 per pound), partly offset by lower purchase accounting impacts related to increased carrying values of acquired inventory, which totaled $24 million ($0.02 per pound) in 2008 and $344 million ($0.33 per pound) in 2007.

Revenue adjustments primarily reflect unrealized losses on copper derivative contracts entered into with our U.S. copper rod customers. In 2007, revenue adjustments also reflected mark-to-market accounting adjustments on the 2007 copper price protection program totaling $175 million ($0.17 per pound).

### South America Copper Mines

We have four operating copper mines in South America – Cerro Verde in Peru, and Candelaria, Ojos del Salado and El Abra in Chile. We own a 53.56 percent interest in Cerro Verde, an 80 percent interest in both Candelaria and Ojos del Salado and a 51 percent interest in El Abra.

The South America copper mines include open-pit and underground mining, sulfide ore concentrating, leaching and SX/EW operations. In addition to copper, the Cerro Verde mine produces molybdenum concentrates as a by-product, and the Candelaria and Ojos del Salado mines produce gold and silver as by-products. Production from our South America copper mines is sold as copper concentrate or copper cathode under long-term contracts. Beginning in 2008, our South America copper mines began selling a portion of their copper concentrate and cathode inventories to Atlantic Copper, an affiliated smelter. Refer to Note 20 for further discussion of our reportable segment in the South America copper mines division.

In response to weak market conditions, operating plans at our South America copper mines were revised at the end of 2008 primarily to reflect the incorporation of reduced input costs and a reduction in capital spending plans. We also temporarily curtailed the molybdenum circuit at Cerro Verde (which resumed in September 2009). In October 2009, we announced initiatives to resume certain project development activities, including development of sulfide ores at El Abra and an expansion of the Cerro Verde concentrator (refer to “Current Development Projects” for further discussion).

Refer to Note 14 for information on contingencies at our South America copper mines.

Operating Data. Following is summary operating data for the South America copper mines for the years ended December 31, 2009, 2008 and 2007. The below operating data for 2007 combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.

| Copper (millions of recoverable pounds) | 2009 | 2008 | 2007a |
| --- | ---: | ---: | ---: |
| Production | 1,390 | 1,506 | 1,413 |
| Sales | 1,394 | 1,521 | 1,399 |
| Average realized price per pound | $2.70 | $2.57 | $3.25 |
| Gold (thousands of recoverable ounces) |  |  |  |
| Production | 92 | 114 | 116 |
| Sales | 90 | 116 | 114 |
| Average realized price per ounce | $982 | $853 | $683 |
| Molybdenum (millions of recoverable pounds) |  |  |  |
| Productionb | 2 | 3 | 1 |
| SX/EW operations |  |  |  |
| Leach ore placed in stockpiles (metric tons per day) | 258,200 | 279,700 | 289,100 |
| Average copper ore grade (percent) | 0.45 | 0.45 | 0.43 |
| Copper production (millions of recoverable pounds) | 565 | 560 | 569 |
| Mill operations |  |  |  |
| Ore milled (metric tons per day) | 181,300 | 181,400 | 167,900 |
| Average ore grade:c |  |  |  |
| Copper (percent) | 0.66 | 0.75 | 0.74 |
| Molybdenum (percent) | 0.02 | 0.02 | 0.02 |
| Copper recovery rate (percent) | 88.9 | 89.2 | 87.1 |
| Production: |  |  |  |
| Copper (millions of recoverable pounds) | 825 | 946 | 844 |
| Gold (thousands of recoverable ounces) | 92 | 114 | 116 |
| Molybdenum (millions of recoverable pounds) | 2 | 3 | 1 |

a. The South America copper mines’ operating data for 2007 combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.

b. Reflects by-product molybdenum production from our Cerro Verde copper mine. Sales of by-product molybdenum are reflected in the Molybdenum segment.

c. Average ore grades of gold produced at our South America mines rounds to less than 0.001 grams per metric ton.

#### 2009 Compared with 2008

Copper sales volumes from the South America copper mines decreased to 1.4 billion pounds in 2009, compared with 1.5 billion for the year 2008, primarily reflecting lower ore grades at Candelaria and downtime for mill maintenance at Cerro Verde. Consolidated sales volumes from our South America copper mines are expected to approximate 1.3 billion pounds of copper and 100 thousand ounces of gold in 2010. Projected copper sales volumes for 2010 are lower than 2009 primarily because of the impact of anticipated lower ore grades at El Abra.

#### 2008 Compared with 2007

Copper sales volumes from the South America copper mines increased to 1.5 billion pounds in 2008, compared with 1.4 billion pounds for the combined year 2007, primarily reflecting higher production from the Cerro Verde concentrator, which reached design capacity in mid-2007.

Unit Net Cash Costs. Unit net cash costs per pound of copper is a measure intended to provide investors with information about the cash-generating capacity of our mining operations expressed on a basis relating to the primary metal product for our respective operations. We use this measure for the same purpose and for monitoring operating performance by our mining operations. This information differs from measures of performance determined in accordance with U.S. GAAP and should not be considered in isolation or as a substitute for measures of performance determined in accordance with U.S. GAAP. This measure is presented by other mining companies, although our measure may not be comparable to similarly titled measures reported by other companies.

#### Gross Profit per Pound of Copper

The following tables summarize unit net cash costs and gross profit per pound at the South America copper mines for the years ended December 31, 2009 and 2008, and for the period March 20, 2007, through December 31, 2007. The below tables reflect unit net cash costs per pound of copper under the by-product and co-product methods as the South America copper mines also had small amounts of molybdenum, gold and silver sales. Refer to “Product Revenues and Production Costs” for an explanation of the “by-product” and “co-product” methods and a reconciliation of unit net cash costs per pound to production and delivery costs applicable to sales reported in our consolidated financial statements.

#### 2009 Compared with 2008

|  | 2009 By-Product Method | Co-Product Method | 2008 By-Product Method | Co-Product Method |
| --- | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $2.70 | $2.70 | $2.57 | $2.57 |
| Site production and delivery, before net noncash |  |  |  |  |
| and nonrecurring costs shown below | 1.08 | 1.02 | 1.13 | 1.07 |
| By-product credits | (0.11) | – | (0.13) | – |
| Treatment charges | 0.15 | 0.15 | 0.14 | 0.14 |
| Unit net cash costs | 1.12 | 1.17 | 1.14 | 1.21 |
| Depreciation, depletion and amortization | 0.20 | 0.19 | 0.33 | 0.32 |
| Noncash and nonrecurring costs, net | 0.02 | 0.02 | 0.07 | 0.06 |
| Total unit costs | 1.34 | 1.38 | 1.54 | 1.59 |
| Revenue adjustments, primarily for pricing on |  |  |  |  |
| prior year open sales | 0.08 | 0.08 | 0.15 | 0.15 |
| Other non-inventoriable costs | (0.02) | (0.02) | (0.02) | (0.02) |
| Gross profit per pound | $1.42 | $1.38 | $1.16 | $1.11 |
| Copper sales (millions of recoverable pounds) | 1,394 | 1,394 | 1,521 | 1,521 |

Unit net cash costs (net of by-product credits) for our South America copper mines decreased to $1.12 per pound of copper in 2009, compared with $1.14 per pound in 2008, primarily reflecting lower site production and delivery costs ($0.05 per pound) associated with lower input costs (primarily for energy).

Our South America copper mines have varying cost structures because of differences in ore grades and ore characteristics, processing costs, by-products and other factors. During 2009, unit net cash costs for the South America copper mines ranged from $1.01 per pound to $1.24 per pound at the individual mines and averaged $1.12 per pound. Assuming achievement of current sales volumes estimates and estimates for commodity-based inputs, we estimate that average unit net cash costs (net of by-product credits) for our South America copper mines would approximate $1.20 per pound of copper in 2010. Unit net cash costs for 2010 are expected to be higher, than in 2009, primarily because of lower volumes and the impact of foreign currency exchange rates, partly offset by lower sulphuric acid costs.

The decrease in depreciation, depletion and amortization in 2009, compared with 2008, primarily reflected the impact of the long-lived asset impairment charges recognized in fourth-quarter 2008 (refer to Note 2 for further discussion of these impairment charges).

#### 2008 Compared with 2007

|  | 2008 By-Product Method | Co-Product Method | 2007a By-Product Method | Co-Product Method |
| --- | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $2.57 | $2.57 | $3.30 | $3.30 |
| Site production and delivery, before net noncash |  |  |  |  |
| and nonrecurring costs shown below | 1.13 | 1.07 | 0.92 | 0.88 |
| By-product credits | (0.13) | – | (0.09) | – |
| Treatment charges | 0.14 | 0.14 | 0.20 | 0.20 |
| Unit net cash costs | 1.14 | 1.21 | 1.03 | 1.08 |
| Depreciation, depletion and amortization | 0.33 | 0.32 | 0.32 | 0.32 |
| Noncash and nonrecurring costs, net | 0.07 | 0.06 | 0.14 | 0.14 |
| Total unit costs | 1.54 | 1.59 | 1.49 | 1.54 |
| Revenue adjustments, primarily for pricing on |  |  |  |  |
| prior year open sales | 0.15 | 0.15 | 0.06 | 0.06 |
| Idle facility and other non-inventoriable costs | (0.02) | (0.02) | (0.02) | (0.02) |
| Gross profit per pound | $1.16 | $1.11 | $1.85 | $1.80 |
| Copper sales (millions of recoverable pounds) | 1,521 | 1,521 | 1,177 | 1,177 |

a. Reflects the period from March 20, 2007, through December 31, 2007.

Unit net cash costs (net of by-product credits) increased to $1.14 per pound of copper in 2008, compared with $1.03 per pound for the period March 20, 2007, through December 31, 2007, reflecting production cost increases associated with higher mining costs and milling rates and higher energy, sulphuric acid and other commodity-based input costs. These increases were partly offset by higher volumes, higher by-product credits and lower treatment charges during 2008.

The change in noncash and nonrecurring costs for 2008 primarily reflects lower purchase accounting impacts related to increased carrying values of acquired inventory, which totaled $46 million ($0.03 per pound) in 2008 and $169 million ($0.14 per pound) in 2007.

### Indonesia Mining

Indonesia mining includes PT Freeport Indonesia’s Grasberg minerals district. We own 90.64 percent of PT Freeport Indonesia, including 9.36 percent owned through our wholly owned subsidiary, PT Indocopper Investama.

PT Freeport Indonesia produces copper concentrates, which contain significant quantities of gold and silver. Substantially all of PT Freeport Indonesia’s copper concentrates are sold under long-term contracts, approximately one-half of its concentrate production is sold to affiliated smelters, Atlantic Copper and PT Smelting (PT Freeport Indonesia’s 25-percent owned copper smelter and refinery in Indonesia – refer to Note 3 for further discussion), and the remainder to other customers.

PT Freeport Indonesia operates under an agreement, called a Contract of Work, with the Government of Indonesia that allows us to conduct exploration, mining and production activities in a 24,700-acre area called Block A located in Papua, Indonesia (refer to Note 15 for further discussion). Under the Contract of Work, PT Freeport Indonesia also conducts exploration activities in an approximate 500,000-acre area called Block B in Papua. All of PT Freeport Indonesia’s proven and probable mineral reserves and current mining operations, including the Grasberg minerals district, are located in Block A.

We have established certain unincorporated joint ventures with Rio Tinto plc (Rio Tinto), an international mining company with headquarters in London, England. Pursuant to the joint venture agreement, Rio Tinto has a 40 percent interest in certain assets and future production exceeding specified annual amounts of copper, gold and silver through 2021 in Block A of PT Freeport Indonesia’s Contract of Work, and, after 2021, a 40 percent interest in all production from Block A. Refer to Note 3 for further discussion of joint ventures with Rio Tinto.

As originally reported in January 2006, we received and responded to requests for U.S. governmental authorities related to PT Freeport Indonesia’s support of Indonesian security institutions. In May 2009, we were notified by the SEC that the U.S. government’s investigation has been completed and no action has been recommended.

Since July 2009, there have been a series of shooting incidents along the road leading to our mining and milling operations at the Grasberg mining complex, including an incident in January 2010. In connection with these incidents, there have been three fatalities (including a PT Freeport Indonesia employee, a security contractor and an Indonesian policeman) and several injuries. The Indonesian government has responded with additional security forces and expressed a strong commitment to protect the safety of the community and our operations. The investigation of these matters is continuing, and we have taken precautionary measures, including limiting use of the road to secured convoys. Our mining and milling activities have continued uninterrupted; however, prolonged limitations on access to the road could adversely affect operations at the mine. See “Risk Factors” contained in Part I, Item 1A of our Form 10-K for the year ended December 31, 2009, for further discussion of these matters.

Refer to Note 14 for information on contingencies at our Indonesia mining operations.

Operating Data. Following is summary operating data for our Indonesia mining operations for the years ended December 31, 2009, 2008 and 2007:

| Consolidated Operating Data, Net of Joint Venture Interest Copper (millions of recoverable pounds) | 2009 | 2008 | 2007 |
| --- | ---: | ---: | ---: |
| Production | 1,412 | 1,094 | 1,151 |
| Sales | 1,400 | 1,111 | 1,131 |
| Average realized price per pound | $2.65 | $2.36 | $3.32 |
| Gold (thousands of recoverable ounces) |  |  |  |
| Production | 2,568 | 1,163 | 2,198 |
| Sales | 2,543 | 1,182 | 2,185 |
| Average realized price per ounce | $994 | $861 | $681 |
| **100% Operating Data** |  |  |  |
| Ore milled (metric tons per day): |  |  |  |
| Grasberg open pita | 166,300 | 129,800 | 159,100 |
| Deep Ore Zone (DOZ) underground minea | 72,000 | 63,100 | 53,500 |
| Total | 238,300 | 192,900 | 212,600 |
| Average ore grade: |  |  |  |
| Copper (percent) | 0.98 | 0.83 | 0.82 |
| Gold (grams per metric ton) | 1.30 | 0.66 | 1.24 |
| Recovery rates (percent): |  |  |  |
| Copper | 90.6 | 90.1 | 90.5 |
| Gold | 83.7 | 79.9 | 86.2 |
| Production (recoverable): |  |  |  |
| Copper (millions of pounds) | 1,641 | 1,109 | 1,211 |
| Gold (thousands of ounces) | 2,984 | 1,163 | 2,608 |

a. Amounts represent the approximate average daily throughput processed at PT Freeport Indonesia’s mill facilities from each producing mine.

#### 2009 Compared with 2008

At the Grasberg mine, the sequencing in mining areas with varying ore grades causes fluctuations in the timing of ore production resulting in varying quarterly and annual sales of copper and gold. PT Freeport Indonesia’s share of sales increased to 1.4 billion pounds of copper and 2.5 million ounces of gold in 2009, compared with 1.1 billion pounds of copper and 1.2 million ounces of gold in 2008, as a result of mining in a higher grade section of the Grasberg open pit during 2009, including accelerated mining of a higher grade section that was previously scheduled to be mined in future periods. PT Freeport Indonesia’s sales for 2010 are expected to approximate 1.2 billion pounds of copper and 1.7 million ounces of gold, which is lower than 2009 volumes, as a result of transitioning to a lower grade section of the Grasberg open pit in 2010. Anticipated changes in ore grades throughout the year are expected to result in variability in quarterly volumes. Approximately 60 percent of PT Freeport Indonesia’s copper and gold production is expected in the second half of 2010.

#### 2008 Compared with 2007

PT Freeport Indonesia’s share of sales totaled 1.1 billion pounds of copper and 1.2 million ounces of gold in 2008, compared with 1.1 billion pounds of copper and 2.2 million ounces of gold in 2007. Lower gold sales volumes in 2008 resulted from mining in a lower-grade section of the Grasberg open pit during the first nine months of 2008.

Unit Net Cash Costs. Unit net cash costs per pound of copper is a measure intended to provide investors with information about the cash-generating capacity of our mining operations expressed on a basis relating to the primary metal product for our respective operations. We use this measure for the same purpose and for monitoring operating performance by our mining operations. This information differs from measures of performance determined in accordance with U.S. GAAP and should not be considered in isolation or as a substitute for measures of performance determined in accordance with U.S. GAAP. This measure is presented by other mining companies, although our measure may not be comparable to similarly titled measures reported by other companies.

#### Gross Profit per Pound of Copper/per Ounce of Gold

The following tables summarize the unit net cash (credits) costs and gross profit per pound of copper and per ounce of gold at our Indonesia mining operations for the years ended December 31, 2009, 2008 and 2007. Refer to “Production Revenues and Production Costs” for an explanation of “by-product” and “co-product” methods and a reconciliation of unit net cash costs per pound to production and delivery costs applicable to sales reported in our consolidated financial statements.

#### 2009 Compared with 2008

|  | 2009 By- Product Method | Co-Product Method Copper | Gold | 2008 By- Product Method | Co-Product Method Copper | Gold |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues, after adjustments shown below | $2.65 | $2.65 | $993.72 | $2.36 | $2.36 | $861.43 |
| Site production and delivery, before net noncash |  |  |  |  |  |  |
| and nonrecurring costs shown below | 1.05 | 0.62 | 231.57 | 1.59 | 1.13 | 412.72 |
| Gold and silver credits | (1.86) | – | – | (0.97) | – | – |
| Treatment charges | 0.22 | 0.13 | 49.18 | 0.24 | 0.17 | 62.69 |
| Royalty on metals | 0.10 | 0.06 | 23.18 | 0.10 | 0.07 | 26.50 |
| Unit net cash (credits) costs | (0.49) | 0.81 | 303.93 | 0.96 | 1.37 | 501.91 |
| Depreciation and amortization | 0.20 | 0.11 | 43.36 | 0.20 | 0.14 | 52.09 |
| Noncash and nonrecurring costs, net | 0.03 | 0.02 | 5.93 | 0.03 | 0.02 | 7.18 |
| Total unit (credits) costs | (0.26) | 0.94 | 353.22 | 1.19 | 1.53 | 561.18 |
| Revenue adjustments, primarily for pricing on |  |  |  |  |  |  |
| prior year open sales | 0.04 | 0.04 | 2.12 | 0.09 | 0.09 | 5.86 |
| PT Smelting intercompany profit | (0.04) | (0.02) | (8.45) | 0.01 | 0.01 | 4.18 |
| Gross profit per pound/ounce | $2.91 | $1.73 | $634.17 | $1.27 | $0.93 | $310.29 |
| Consolidated sales |  |  |  |  |  |  |
| Copper (millions of recoverable pounds) | 1,400 | 1,400 |  | 1,111 | 1,111 |  |
| Gold (thousands of recoverable ounces) |  |  | 2,543 |  |  | 1,182 |

Because of the fixed nature of a large portion of PT Freeport Indonesia’s costs, unit costs vary significantly from period to period depending on volumes of copper and gold sold during the period. Unit net cash costs (net of gold and silver credits) decreased to a net credit of $0.49 per pound of copper in 2009, compared with a net cost of $0.96 per pound in 2008, reflecting higher gold and silver credits ($0.89 per pound) resulting from higher gold sales volumes and prices in 2009, and lower site production and delivery costs ($0.54 per pound) primarily associated with higher copper sales volumes and lower commodity-based input costs.

Treatment charges vary with the volume of metals sold and the price of copper, and royalties vary with the volume of metals sold and the prices of copper and gold.

Because the majority of PT Freeport Indonesia’s costs are fixed, unit costs vary with volumes sold and the price of gold. Assuming achievement of current sales volume estimates, average gold prices of $1,100 per ounce in 2010, and estimates for energy costs, currency exchange rates and other cost factors, we estimate that average unit net cash costs for PT Freeport Indonesia (net of gold and silver credits) would approximate $0.21 per pound of copper in 2010. Unit net cash costs for 2010 are expected to be higher, compared with 2009, primarily because of lower projected sales volumes and higher commodity-based input costs. Each $50 per ounce change in average gold prices during the year would have an approximate $0.07 per pound impact on PT Freeport Indonesia’s 2010 unit net cash costs.

#### 2008 Compared with 2007

|  | 2008 By- Product Method | Co-Product Method Copper | Gold | 2007 By- Product Method | Co-Product Method Copper | Gold |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Revenues, after adjustments shown below | $2.36 | $2.36 | $861.43 | $3.32 | $3.32 | $680.74 |
| Site production and delivery, before net noncash |  |  |  |  |  |  |
| and nonrecurring costs shown below | 1.59 | 1.13 | 412.72 | 1.19 | 0.85 | 172.23 |
| Gold and silver credits | (0.97) | – | – | (1.36) | – | – |
| Treatment charges | 0.24 | 0.17 | 62.69 | 0.34 | 0.24 | 49.45 |
| Royalty on metals | 0.10 | 0.07 | 26.50 | 0.12 | 0.08 | 17.05 |
| Unit net cash costs | 0.96 | 1.37 | 501.91 | 0.29 | 1.17 | 238.73 |
| Depreciation and amortization | 0.20 | 0.14 | 52.09 | 0.17 | 0.12 | 25.54 |
| Noncash and nonrecurring costs, net | 0.03 | 0.02 | 7.18 | 0.04 | 0.03 | 5.90 |
| Total unit costs | 1.19 | 1.53 | 561.18 | 0.50 | 1.32 | 270.17 |
| Revenue adjustments, primarily for pricing on |  |  |  |  |  |  |
| prior year open sales | 0.09 | 0.09 | 5.86 | 0.03 | 0.03 | 1.07 |
| PT Smelting intercompany profit | 0.01 | 0.01 | 4.18 | 0.01 | 0.01 | 1.71 |
| Gross profit per pound/ounce | $1.27 | $0.93 | $310.29 | $2.86 | $2.04 | $413.35 |
| Consolidated sales |  |  |  |  |  |  |
| Copper (millions of recoverable pounds) | 1,111 | 1,111 |  | 1,131 | 1,131 |  |
| Gold (thousands of recoverable ounces) |  |  | 1,182 |  |  | 2,185 |

Unit net cash costs (net of gold and silver credits) increased to $0.96 per pound of copper in 2008, compared with $0.29 per pound in 2007, reflecting lower gold and silver credits associated with lower gold volumes in 2008, higher input costs, including higher mining rates and energy costs, and also reflected the impact of changes in cost sharing with our joint venture partner. Partly offsetting these increases were lower treatment charges, which vary with the volume of metals sold and the price of copper.

### Africa Mining

Africa mining includes the Tenke Fungurume (Tenke) copper and cobalt mining concessions in the Katanga province of the DRC. We own an effective 57.75 percent interest in Tenke and are the operator of the project. The Tenke mine includes open-pit mining, leaching and SX/EW operations. Copper production from the Tenke mine is sold as copper cathode. In addition to copper, the Tenke mine produces cobalt hydroxide.

Construction activities for the initial development project are complete. Copper production commenced in March 2009 and Tenke achieved targeted copper production rates in September 2009. Start-up and quality issues continue to be addressed in the cobalt circuit and sustained targeted production rates are expected to be reached during 2010. Current operations are designed to produce approximately 250 million pounds of copper and 18 million pounds of cobalt per year. Refer to “Current Development Projects” for further discussion of the Tenke Fungurume project.

We are continuing to work cooperatively with the DRC government to resolve the ongoing contract review but cannot predict the timing or the outcome of this process. The contract review process has not affected our development schedule and we are continuing to operate pursuant to the terms of our contract. We believe that the contract is fair and equitable, complies with Congolese law and is enforceable without modifications. Refer to Note 15 for further discussion. See “Risk Factors” contained in Part I, Item 1A of our Form 10-K for the year ended December 31, 2009, for further discussion of these matters.

Operating Data. Following is summary operating data for our Africa mining operations for the year ended December 31, 2009.

| Copper (millions of recoverable pounds) | 2009a |
| --- | ---: |
| Production | 154 |
| Sales | 130 |
| Average realized price per pound | $2.85 |
| Ore milled (metric tons per day) | 7,300 |
| Average ore grade (percent) | 3.69 |
| Copper recovery rate (percent) | 92.1 |

a. Results for 2009 represent mining operations which began production in March 2009.

Tenke’s sales volumes are expected to approximate 240 million pounds of copper and over 20 million pounds of cobalt for the year 2010. The high grades of copper and cobalt in the ore at the Tenke mine are expected to result in an attractive cost structure once the full operation reaches design capacity. Upon reaching design capacity in the copper and cobalt circuits and assuming average cobalt prices of $10 per pound, average unit net cash costs for Tenke are targeted to be $0.50 per pound of copper. Each $2 per pound change in average cobalt prices would have an approximate $0.12 per pound impact on Tenke’s unit net cash costs. We will incorporate Tenke in our consolidated unit net cash cost disclosure upon completion of ramp-up activities, expected during 2010.

Pursuant to our agreement with Lundin Mining Corporation (Lundin), we were responsible for funding our share (70 percent) of project development costs and 100 percent of certain cost overruns on the initial Tenke Fungurume project. We and Lundin will be repaid our advances prior to distributions to shareholders of Tenke Fungurume. Accordingly, we will receive a disproportionate share of cash flow until the cost overrun financing and advances are repaid.

### Molybdenum

Our Molybdenum operation is an integrated producer of molybdenum, with mining, sulfide ore concentrating, roasting and processing facilities that produce high-purity, molybdenum-based chemicals, molybdenum metal powder and metallurgical products, which are sold to customers around the world, and includes the wholly owned Henderson molybdenum mine in Colorado and related conversion facilities. The Henderson underground mine produces high-purity, chemical-grade molybdenum concentrates, which are typically further processed into value-added molybdenum chemical products. The Molybdenum operation also includes the wholly owned Climax molybdenum mine in Colorado, which has been on care-and-maintenance status since 1995; a sales company that purchases and sells molybdenum from our Henderson mine and from our North and South America copper mines that produce molybdenum as a by-product; and related conversion facilities that, at times, roast and/or process material on a toll basis. Toll arrangements require the tolling customer to deliver appropriate molybdenum-bearing material to our facilities for processing into a product that is returned to the customer, who pays us for processing their material into the specified products.

In response to market conditions during fourth-quarter 2008, we suspended construction activities associated with the project to restart the Climax molybdenum mine, which would have an annual capacity of 30 million pounds with expansion options. We will continue to monitor market conditions to determine timing for restarting construction of this project; once a decision is made to resume construction activities, the project could be completed within 18 months. Estimated remaining costs for the project approximate $350 million.

Operating Data. Following is summary operating data for the Molybdenum operations for the years ended December 31, 2009, 2008 and 2007. The operating data for 2007 combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.

| Molybdenum (millions of recoverable pounds) | 2009 | 2008 | 2007a |
| --- | ---: | ---: | ---: |
| Productionb | 27 | 40 | 39 |
| Sales, excluding purchasesc | 58 | 71 | 69 |
| Average realized price per pound | $12.36 | $30.55 | $25.87 |
| **Henderson molybdenum mine** |  |  |  |
| Ore milled (metric tons per day) | 14,900 | 24,100 | 24,000 |
| Average molybdenum ore grade (percent) | 0.25 | 0.23 | 0.23 |
| Molybdenum production (millions of recoverable pounds) | 27 | 40 | 39 |

a. The Molybdenum operating data for 2007 combines our historical data beginning March 20, 2007, with Phelps Dodge pre-acquisition data through March 19, 2007. As the pre-acquisition data represents the results of these operations under Phelps Dodge management, such combined data is not necessarily indicative of what past results would have been under FCX management or of future operating results.

b. Reflects production at the Henderson molybdenum mine.

c. Includes sales of molybdenum produced as a by-product at our North and South America copper mines.

Beginning in fourth-quarter 2008, molybdenum markets were significantly affected by the downturn in economic conditions, which required us to operate the Henderson molybdenum mine at reduced rates during 2009. However, conditions have begun to improve and as a result Henderson was operating at 80 percent capacity at December 31, 2009, compared with 60 percent capacity during most of 2009. Molybdenum sales volumes decreased to 58 million pounds in 2009, compared with 71 million pounds in 2008, because of lower demand. For 2010, molybdenum sales volumes are expected to approximate 60 million pounds. We will continue to review operating plans and adjust operating rates to reflect market conditions.

Unit Net Cash Costs. Unit net cash costs per pound of molybdenum is a measure intended to provide investors with information about the cash-generating capacity of our mining operations expressed on a basis relating to the primary metal product for our respective operations. We use this measure for the same purpose and for monitoring operating performance by our mining operations. This information differs from measures of performance determined in accordance with U.S. GAAP and should not be considered in isolation or as a substitute for measures of performance determined in accordance with U.S. GAAP. This measure is presented by other mining companies, although our measure may not be comparable to similarly titled measures reported by other companies.

#### Gross Profit per Pound of Molybdenum

The following tables summarize the unit net cash costs and gross profit per pound of molybdenum at our Henderson molybdenum mine for the years ended December 31, 2009 and 2008, and for the period March 20, 2007, through December 31, 2007. Refer to “Product Revenues and Production Costs” for a reconciliation of unit net cash costs per pound to production and delivery costs applicable to sales reported in our consolidated financial statements.

|  | 2009 | 2008 |  | 2007a |
| --- | ---: | ---: | --- | ---: |
| Revenues | $11.69 | $29.27 |  | $27.12 |
| Site production and delivery, before net noncash |  |  |  |  |
| and nonrecurring costs shown below | 5.44 | 5.36 |  | 4.37 |
| Unit net cash costs | 5.44 | 5.36 |  | 4.37 |
| Depreciation, depletion and amortization | 0.98 | 4.25 |  | 2.55 |
| Noncash and nonrecurring costs, net | 0.03 | 0.18 | b | 0.05 |
| Total unit costs | 6.45 | 9.79 |  | 6.97 |
| Gross profit per poundc | $5.24 | $19.48 |  | $20.15 |
| Molybdenum sales (millions of recoverable pounds)d | 27 | 40 |  | 31 |

93 a. Reflects the period from March 20, 2007, through December 31, 2007.

b. Includes charges of $0.03 per pound in 2008 associated with LCM inventory adjustments.

c. Gross profit reflects sales of Henderson products based on volumes produced at market-based pricing. On a consolidated basis, the Molybdenum segment includes profits on sales as they are made to third parties and realizations based on actual contract terms. As a result, the actual gross profit realized will differ from the amounts reported in this table.

d. Reflects molybdenum produced by the Henderson molybdenum mine.

Henderson’s unit net cash costs were $5.44 per pound of molybdenum in 2009, $5.36 per pound in 2008 and $4.37 per pound in 2007. Henderson’s unit net cash costs were unfavorably impacted in 2009 by lower production volumes, partly offset by the impact of cost reduction efforts. Higher costs in 2008, compared with 2007, primarily reflected higher input costs, including outside services, supplies and energy.

Assuming achievement of current 2010 sales estimates, we estimate that the 2010 average unit net cash costs for Henderson would approximate $5.50 per pound of molybdenum.

The decrease in Henderson’s depreciation, depletion and amortization in 2009, compared with 2008, reflects the impact of long-lived asset impairment charges recognized in fourth-quarter 2008 (refer to Note 2 for further discussion).

The increase in Henderson’s depreciation, depletion and amortization in 2008, compared with 2007, primarily reflected changes in purchase accounting impacts associated with adjustments to the estimated fair values of acquired property, plant and equipment, which were based on preliminary estimates in 2007 and finalized in first-quarter 2008.

### Atlantic Copper Smelting & Refining

Atlantic Copper, our wholly owned subsidiary located in Spain, smelts and refines copper concentrates and markets refined copper and precious metals in slimes. PT Freeport Indonesia sells copper concentrate and the South America copper mines sell copper concentrate and copper cathode to Atlantic Copper. Through downstream integration, we are assured placement of a significant portion of our concentrate production. During 2009, Atlantic Copper purchased approximately 35 percent of its concentrate requirements from PT Freeport Indonesia and approximately 25 percent from our South America mines.

Smelting and refining charges consist of a base rate and, in certain contracts, price participation based on copper prices. Treatment charges for smelting and refining copper concentrates represent a cost to PT Freeport Indonesia and our South America copper mines and income to Atlantic Copper and PT Smelting, our 25 percent owned smelter and refinery in Gresik, Indonesia. Thus, higher treatment and refining charges benefit our smelter operations at Atlantic Copper and adversely affect our mining operations in Indonesia and South America. Our North America copper mines are not significantly affected by changes in treatment and refining charges because these operations are fully integrated with our Miami smelter located in Arizona.

Atlantic Copper had an operating loss of $56 million in 2009 compared to operating income of $10 million in 2008 and $3 million in 2007. The decrease in Atlantic Copper’s operating results during 2009 primarily reflected lower sulphuric acid revenues resulting from lower prices.

We defer recognizing profits on PT Freeport Indonesia’s and our South America copper mines’ sales to Atlantic Copper and on 25 percent of PT Freeport Indonesia’s sales to PT Smelting until final sales to third parties occur. Changes in these net deferrals resulted in net reductions to net income attributable to FCX common stockholders totaling $109 million ($0.23 per share) in 2009, compared with net additions of $65 million ($0.17 per share) in 2008 and $8 million ($0.02 per share) in 2007. At December 31, 2009, our net deferred profits on PT Freeport Indonesia’s and the South America copper mines’ inventories at Atlantic Copper and PT Smelting to be recognized in future periods’ net income after taxes and noncontrolling interests totaled $137 million.

### CURRENT DEVELOPMENT PROJECTS

We have several projects and potential opportunities to expand our production volumes, extend mine lives and develop large-scale ore bodies. During fourth-quarter 2008, we deferred several project development activities because of the downturn in global economic conditions. Major development projects for 2009 consisted of underground development in the Grasberg minerals district and the Tenke Fungurume project (for which construction activities on the initial project are complete). During fourth-quarter 2009, we announced that we are resuming certain project development activities. Capital spending plans will continue to be reviewed and adjusted in response to changes in market conditions.

### North America Copper Mines

Miami Restart. During fourth-quarter 2009, we initiated plans to restart limited mining activities at the Miami copper mine in Arizona, which will improve efficiencies of ongoing reclamation projects associated with historical mining operations at the site. During the approximate five-year mine life, we expect to ramp up production to approximately 100 million pounds of copper per year by the second half of 2011. The capital investment for this project is expected to approximate $40 million, which is lower that the initial estimate of $100 million because we intend to transfer existing mining equipment from other North America sites, rather than purchasing new equipment.

Morenci Mill Restart. We are initiating activities to restart the Morenci mill in Arizona, which was temporarily idled in February 2009 in response to market conditions, to process available sulfide material currently being mined. Copper concentrate production is expected to begin in second-quarter 2010, with mill throughput initially expected to approximate 30,000 metric tons per day, or approximately 60 percent of total mill capacity.

Twin Buttes. In December 2009, we purchased property adjacent to our Sierrita operations primarily from Twin Buttes Properties, Inc. for $200 million. The property includes the Twin Buttes copper mine, which ceased operations in 1994 and contains mineralized material of approximately 0.7 billion metric tons with average grades of 0.43 percent for copper and 0.024 percent for molybdenum. The purchase provides significant synergies in the Sierrita district, including the potential for expanded mining activities and access to material that can be used for Sierrita tailings and stockpile reclamation purposes. We plan to conduct studies to incorporate the Twin Buttes resources in our future plans to determine the optimum development plans for the district.

### South America Copper Mines

El Abra Sulfide Ore. We have resumed construction activities associated with the development of a large sulfide deposit at El Abra that will extend the mine life by over ten years. Production from the sulfide ore, which will ramp-up to approximately 300 million pounds of copper per year, is expected to begin in 2012 and will replace the current oxide ore copper production that is expected to decline over the next several years. The project will use a portion of the existing facilities to process the additional sulfide ore. The total aggregate capital investment for this project (which has been updated to incorporate recent foreign currency exchange rates and other cost increases) is expected to total $700 million through 2015, of which approximately $500 million is for the initial phase of the project that is expected to be completed in 2012. Aggregate project costs of $75 million have been incurred as of December 31, 2009 (most of which were incurred prior to the end of 2008).

Cerro Verde Expansion. We have commenced a project to optimize throughput at the existing Cerro Verde concentrator. This project, which is expected to be completed by the end of 2010, is designed to add 30 million pounds of additional copper production per year by increasing mill throughput from 108,000 metric tons of ore per day to 120,000 metric tons of ore per day. The aggregate capital investment for this project is expected to total approximately $50 million. We continue to study the potential for a major expansion at Cerro Verde.

### Indonesia

We have several projects in progress in the Grasberg minerals district, including development of the large-scale, high-grade underground ore bodies located beneath and adjacent to the Grasberg open pit. In addition, we have completed the feasibility study for the Deep Mill Level Zone (DMLZ). Based on current estimates, we expect aggregate expenditures for underground mine development in the Grasberg minerals district to average approximately $450 million annually during the next 15 years. These costs will be shared with Rio Tinto in accordance with our joint venture agreement. Considering the long-term nature and large size of these projects, actual costs could differ materially from these estimates.

In addition to the mine development costs above, our current mine development plans include approximately $3 billion of capital expenditures at our processing facilities to optimize the handling of underground ore types once Grasberg open-pit operations cease. Substantially all of these expenditures will be made between 2017 and 2029. We continue to review our mine development and processing plans to maximize the value of our reserves.

The following discussion provides additional information on these current projects, including the continued development of the Common Infrastructure project, the Grasberg Block Cave and Big Gossan underground mines, a further expansion of the DOZ underground mine and development of the DMLZ ore body.

Common Infrastructure and Grasberg Block Cave. In 2004, PT Freeport Indonesia commenced its Common Infrastructure project to provide access to its large undeveloped underground ore bodies located in the Grasberg minerals district through a tunnel system located approximately 400 meters deeper than its existing underground tunnel system. In addition to providing access to our underground ore bodies, the tunnel system will enable PT Freeport Indonesia to conduct future exploration in prospective areas associated with currently identified ore bodies. The tunnel system has reached the Big Gossan terminal and we are proceeding with development of the lower Big Gossan infrastructure. We have also advanced development of the Grasberg spur and have completed the tunneling required to reach the Grasberg underground ore body. During 2009, we continued development of the Grasberg Block Cave terminal infrastructure and mine access.

In 2008, we completed the feasibility study for the development of the Grasberg Block Cave underground mine, which accounts for over one-third of our reserves in Indonesia. Production at the Grasberg Block Cave mine is currently scheduled to commence at the end of mining the Grasberg open pit, which is expected to continue until mid-2016. The timing of the underground Grasberg Block Cave mine development will continue to be assessed.

Based on the 2008 feasibility study, aggregate mine development capital for the Grasberg Block Cave mine and associated Common Infrastructure is expected to approximate $3.6 billion to be incurred between 2008 and 2021, with PT Freeport Indonesia’s share totaling approximately $3.4 billion. These estimates are higher than the aggregate $3.1 billion previously reported as certain costs previously considered as operating in the feasibility study were determined to be capital costs to conform with our current accounting policies for underground mines. Aggregate project costs totaling $127 million have been incurred through December 31, 2009, of which $83 million was incurred during 2009. Targeted production rates once the Grasberg Block Cave mining operation reaches full capacity are expected to approximate 150,000 metric tons of ore per day.

Big Gossan. The Big Gossan underground mine is a high-grade deposit located near PT Freeport Indonesia’s existing milling complex. The Big Gossan mine is being developed as an open-stope mine with backfill consisting of mill tailings and cement, an established mining methodology expected to be higher cost than the block-cave method used at the DOZ mine. Production is designed to ramp up to 7,000 metric tons of ore per day by late 2012 (equal to average annual aggregate incremental production of 125 million pounds of copper and 65,000 ounces of gold, with PT Freeport Indonesia receiving 60 percent of these amounts). The aggregate capital investment for this project is currently estimated at approximately $480 million, of which $377 million has been incurred through December 31, 2009, including $41 million during 2009.

DOZ Expansion. In mid-2007, PT Freeport Indonesia completed an expansion of the DOZ underground operation to allow a sustained rate of 50,000 metric tons of ore per day. PT Freeport Indonesia’s further expansion of the DOZ mine to 80,000 metric tons of ore per day is substantially complete. The capital cost for this expansion approximated $100 million, with PT Freeport Indonesia’s 60 percent share totaling approximately $60 million. The success of the development of the DOZ mine, one of the world’s largest underground mines, provides confidence in the future development of PT Freeport Indonesia’s large-scale undeveloped underground ore bodies.

DMLZ. The DMLZ ore body lies below the DOZ mine at the 2,590-meter elevation and represents the downward continuation of mineralization in the Ertsberg East Skarn system and neighboring Ertsberg porphyry. The DMLZ feasibility study was completed in fourth-quarter 2009. We plan to mine the ore body using a block-cave method with production beginning in 2020, near completion of mining at the DOZ. Drilling efforts continue to determine the extent of this ore body. We continue to develop the Common Infrastructure project and tunnels from mill level. In 2009, we completed a portion of the spur to the DMLZ mine and reached the edge of the DMLZ terminal. Aggregate mine development capital costs for the DMLZ are expected to approximate $2.1 billion with PT Freeport Indonesia’s share totaling approximately $1.2 billion, which are expected to be incurred from 2009 to 2020. Aggregate project costs totaling $25 million have been incurred through December 31, 2009. Targeted production rates once the DMLZ mining operation reaches full capacity are expected to approximate 80,000 metric tons of ore per day.

### Africa Mining

Tenke Fungurume. Construction activities for the approximate $2 billion initial project are complete. Copper production commenced in March 2009 and achieved targeted copper production rates in September 2009. Start-up and quality issues continue to be addressed in the cobalt circuit and sustained targeted production rates are expected to be reached during 2010. Current operations are designed to produce approximately 250 million pounds of copper and 18 million pounds of cobalt per year.

The initial Tenke Fungurume project was designed and constructed in a world-class fashion, using modern technology and following international standards for environmental management, occupational safety and social responsibility. The facilities include impermeable lined tailing storage and waste-water treatment ponds, and we have made significant investments in infrastructure in the region, including a national road and improvements in power generation and transmission systems. Our social programs include local micro-enterprise businesses, agricultural capacity building initiatives, malaria abatement, potable drinking water wells, new medical facilities and several new schools. The project will continue to provide important benefits to the Congolese through employment and the provision of local services and to the DRC government through substantial tax, royalty and dividend payments.

We continue to engage in drilling activities, exploration analyses and metallurgical testing to evaluate the potential of this highly prospective district. These analyses are being incorporated in future plans to evaluate opportunities for expansion. In our recoverable proven and probable reserve estimates for 2009, we were successful in adding 2.6 billion pounds of copper reserves and 0.08 billion pounds of cobalt reserves. Recoverable proven and probable reserves at December 31, 2009, approximate 135 million metric tons of ore with average grades of 3.13 percent for copper and 0.33 percent for cobalt, which equates to recoverable reserves of 8.4 billion pounds of copper and 0.78 billion pounds of cobalt.

We commenced a feasibility study in fourth-quarter 2009 to evaluate a second phase of the project, which would include optimizing the current plant and potentially increasing capacity by approximately 50 percent. The feasibility study is expected to be completed by mid-year 2010.

### CAPITAL RESOURCES AND LIQUIDITY

Our operating cash flows vary with prices realized from copper, gold and molybdenum sales, our production levels, production costs, cash payments for income taxes and interest, other working capital changes and other factors. As a result of weak economic conditions, we revised our operating plans at the end of 2008 and in early 2009 to protect liquidity while preserving our large mineral resources and growth options for the longer term (refer to Note 2 for further discussion). However, strong operating performance and rising copper prices have enabled us to enhance our financial and liquidity position during 2009, allowing us to manage volatile conditions effectively, reduce debt and reinstate cash dividends to shareholders, while maintaining our future growth opportunities. In addition, we have announced initiatives to resume certain project development activities that were deferred in late 2008 (refer to “Current Development Projects” for further discussion). We view the long-term outlook for our business positively, supported by limitations on supplies of copper and by the requirement for copper in the world’s economy and will continue to adjust our operating strategy as market conditions change.

Based on current mine plans and subject to future copper, gold and molybdenum prices, we expect estimated 2010 operating cash flows to be greater than our budgeted capital expenditures, expected debt payments, dividends, noncontrolling interest distributions and other cash requirements.

### Cash and Cash Equivalents

At December 31, 2009, we had consolidated cash and cash equivalents of $2.7 billion. The following table reflects the U.S. and international components of consolidated cash and cash equivalents at December 31, 2009 and 2008 (in millions):

|  | 2009 | 2008 |
| --- | ---: | ---: |
| Cash at domestic companiesa | $1,522 | $95 |
| Cash at international operations | 1,134 | 777 |
| Total consolidated cash and cash equivalents | 2,656 | 872 |
| Less: Noncontrolling interests’ share | (300) | (267) |
| Cash, net of noncontrolling interests’ share | 2,356 | 605 |
| Less: Withholding taxes and other | (171) | (151) |
| Net cash available to FCX | $2,185 | $454 |

97 a. Includes cash at our parent company and North America operations.

### Operating Activities

During 2009, we generated operating cash flows totaling $4.4 billion, net of $770 million used for working capital requirements, which included approximately $600 million related to settlement of final pricing with customers on 2008 provisionally priced copper sales. Operating cash flows in 2008 totaled $3.4 billion, net of $965 million used for working capital requirements, which included $598 million to settle the 2007 copper price protection program contract, and operating cash flows in 2007 totaled $6.2 billion, including $1.1 billion from working capital sources.

Operating cash flows for 2009 were higher than in 2008 primarily because of lower operating costs and higher gold prices and sales volumes. Operating cash flows for 2008 were lower than in 2007 primarily because of higher operating costs and higher working capital requirements.

Consolidated revenues, operating cash flows and net income vary significantly with fluctuations in the market prices of copper, gold and molybdenum, sales volumes and other factors. Refer to “Overview and Outlook” for further discussion of projected 2010 operating cash flows.

### Investing Activities

Capital Expenditures. Capital expenditures, including capitalized interest, totaled $1.6 billion in 2009 (including $1.0 billion for major projects and a property acquisition), $2.7 billion in 2008 (including $1.6 billion for major projects) and $1.8 billion in 2007 (including $0.8 billion for major projects). The decrease in capital expenditures in 2009, compared with 2008, primarily reflected the effects of the decision to defer capital spending for several projects, lower capital spending for the initial Tenke Fungurume development project (for which construction activities are complete) and reduced spending for sustaining capital. The increase in capital expenditures in 2008, compared with 2007, primarily reflected higher costs associated with our major development projects.

During fourth-quarter 2009, we announced initiatives to resume certain project development activities that were deferred in late 2008 (refer to “Current Development Projects” for further discussion of these projects). Capital spending plans will continue to be reviewed and adjusted in response to changes in market conditions and other factors. Refer to “Overview and Outlook” for further discussion of projected 2010 capital expenditures.

Other Investing Activities. During 2008, our global reclamation and remediation trusts decreased by $430 million resulting primarily from reimbursement of previously incurred costs for reclamation and environmental activities.

On March 19, 2007, we issued 136.9 million shares of common stock and paid $13.9 billion (net of cash acquired) to acquire Phelps Dodge (refer to Note 18 for further discussion).

During 2007, we received net proceeds of $597 million associated with the sale of Phelps Dodge International Corporation (PDIC) (refer to Note 19 for further discussion), and also received proceeds totaling $260 million primarily related to sales of marketable securities.

### Financing Activities

Equity and Debt Transactions. In February 2009, we completed a public offering of 26.8 million shares of our common stock at an average price of $28.00 per share, which generated gross proceeds of $750 million (net proceeds of approximately $740 million). Net proceeds were used for general corporate purposes, including the repayment of amounts outstanding under our revolving credit facilities, working capital and capital expenditures.

In December 2008, through privately negotiated transactions, we induced conversion of 0.3 million shares of our 5½% Convertible Perpetual Preferred Stock into 5.8 million shares of FCX common stock. To induce conversion of these shares, we issued to the holders an additional 1.0 million shares of FCX common stock valued at $22 million. In September 2009, we called for the redemption of the remaining 0.8 million shares of our 5½% Convertible Perpetual Preferred Stock, which converted into 17.9 million shares of FCX common stock; the remaining 1,025 shares were redeemed for approximately $1 million in cash. Refer to Note 12 for further discussion of these transactions.

In July 2008, our Board of Directors (the Board) approved an increase in the open-market share purchase program for up to 30 million shares. During third-quarter 2008, we purchased 6.3 million shares of our common stock for $500 million ($79.15 per share average) under this program; however, because of financial market turmoil and the declines in copper and molybdenum prices, in September 2008, we suspended purchases of our common stock under the program. There are 23.7 million shares remaining under this program, and the timing of future purchases of our common stock is dependent on many factors, including our operating results; cash flows and financial position; copper, gold and molybdenum prices; the price of our common shares; and general economic and market conditions.

At December 31, 2009, we had 430 million common shares outstanding; assuming conversion of our 6¾% Mandatory Convertible Preferred Stock, which automatically converts on May 1, 2010, we would have between 469 and 477 million common shares outstanding, depending on the applicable average market price of our common stock (refer to Note 12 for further discussion).

Total debt approximated $6.3 billion at December 31, 2009, $7.4 billion at December 31, 2008, and $7.2 billion at December 31, 2007.

We have revolving credit facilities available through March 2012, which are composed of (i) a $1.0 billion revolving credit facility available to FCX and (ii) a $0.5 billion revolving credit facility available to both FCX and PT Freeport Indonesia. Interest on the revolving credit facilities accrues at the London Interbank Offered Rate (LIBOR) plus 1.00 percent, subject to an increase or decrease in the interest rate margin based on the credit ratings assigned by Standard & Poor’s Rating Services and Moody’s Investor Services. At December 31, 2009, we had no borrowings and $39 million of letters of credit issued under the facilities, resulting in availability of approximately $1.5 billion ($961 million of which could be used for additional letters of credit). The revolving credit facilities contain restrictions on the amount available for dividend payments, purchases of our common stock and certain debt prepayments (refer to Note 10 for further discussion). However, these restrictions do not apply as long as availability under the revolvers plus domestic cash exceeds $750 million. At December 31, 2009, we had availability under the revolvers plus available domestic cash (as defined by the revolving credit facility) totaling approximately $3.4 billion.

In addition, the indenture governing our senior notes used to finance the Phelps Dodge acquisition contains restrictions on incurring debt, making restricted payments and selling assets (refer to Note 10 for further discussion). In April 2008, Standard & Poor’s Rating Services and Fitch Ratings raised our corporate credit rating and the ratings on our unsecured debt to BBB- (investment grade). As a result of the upgrade of our unsecured debt to investment grade, these covenants are currently suspended. However, to the extent the rating is downgraded below investment grade, the covenants would again become effective.

During 2009, we repaid $1.0 billion in debt, including $727 million of senior debt at a cost of $768 million, consisting of the August 2009 redemption of 6⅞% Senior Notes and the open market purchases of our 8.25% Senior Notes, our 8.375% Senior Notes and our 8¾% Senior Notes (refer to Note 10 for further discussion of these transactions). These transactions will result in annual interest cost savings of approximately $56 million. Losses on early extinguishment of debt totaled $48 million ($43 million to net income attributable to FCX common stockholders or $0.09 per share) for 2009.

From January 1, 2010, through February 25, 2010, we repaid an additional $269 million of our 8.25% Senior Notes and our 8.375% Senior Notes through open-market purchases at a cost of $293 million. Losses on early extinguishment of debt are expected to total $27 million in first-quarter 2010 for these 2010 transactions.

In February 2008, we purchased, in an open market transaction, $33 million of our 9½% Senior Notes for $46 million.

As shown in the summary table below, we have no significant debt maturities in the near term; however, we may consider additional opportunities to prepay debt in advance of scheduled maturities or redeem our currently redeemable Senior Floating Rate Notes (in millions).

|  | 2010 | 2011 | 2012 | 2013 | 2014 | Thereafter |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Senior notes | $– | $89 | $– | $– | $– | $6,064 |
| Equipment loans and other | 16 | 4 | 14 | 1 | 1 | 157 |
|  | $16 | $93 | $14 | $1 | $1 | $6,221 |

March 2007 Acquisition of Phelps Dodge. In connection with financing the acquisition of Phelps Dodge, we used $2.5 billion of available cash (including acquired cash) and funded the remainder with term loan borrowings totaling $10.0 billion under a new $11.5 billion senior credit facility and from the offering of $6.0 billion in senior notes (which generated net proceeds of $5.9 billion). Following the close of the acquisition of Phelps Dodge and in accordance with our plan to reduce debt, during 2007, we fully repaid the $10.0 billion in term loans (including incremental borrowings and payments of approximately $2.5 billion) using a combination of equity proceeds and internally generated cash flows. The equity transactions included the sale of 47.15 million shares of common stock at $61.25 per share for net proceeds of $2.8 billion and 28.75 million shares of 6¾% Mandatory Convertible Preferred Stock for net proceeds of $2.8 billion. In addition to repaying the term loans, we had net repayments of other debt totaling $325 million in 2007.

Cash Dividends. The declaration and payment of dividends is at the discretion of the Board. The amount of our cash dividend on our common stock is dependent upon our financial results, cash requirements, future prospects and other factors deemed relevant by the Board. In December 2007, the Board increased the annual cash dividend on our common stock from $1.25 per share to $1.75 per share, and again in July 2008 to $2.00 per share. Because of the deterioration in copper and molybdenum prices and in general economic conditions, in December 2008, the Board suspended the cash dividend on our common stock; accordingly, there were no common stock dividends paid in 2009, compared with $693 million ($1.8125 per share) in 2008 and $421 million ($1.25 per share) in 2007. In October 2009, the Board reinstated an annual cash dividend on our common stock of $0.60 per share. On December 30, 2009, FCX declared a quarterly dividend of $0.15 per share, which was paid on February 1, 2010, to common shareholders of record at the close of business on January 15, 2010. The Board will continue to review our financial policy on an ongoing basis.

Preferred stock dividends paid totaled $229 million in 2009, $255 million in 2008 and $175 million in 2007 representing dividends on our 5½% Convertible Perpetual Preferred Stock and 6¾% Mandatory Convertible Preferred Stock (refer to Note 12 for further discussion). On December 30, 2009, FCX declared a regular quarterly dividend of $1.6785 per share on our 6¾% Mandatory Convertible Preferred Stock, which was paid on February 1, 2010, to shareholders of record at the close of business on January 15, 2010. On May 1, 2010, our 6¾% Mandatory Convertible Preferred Stock will automatically convert into between 39 million and 47 million shares of FCX common stock, depending on the applicable average market price of our common stock (refer to Note 12 for further discussion).

Cash dividends and distributions paid to noncontrolling interests totaled $535 million in 2009, $730 million in 2008 and $967 million in 2007, reflecting dividends and distributions paid to the noncontrolling interest owners of PT Freeport Indonesia and our South America copper mines.

### OTHER CONTRACTUAL OBLIGATIONS

In addition to debt maturities, we have other contractual obligations, which we expect to fund with projected operating cash flows, availability under our revolving credit facilities or future financing transactions, if necessary. A summary of these various obligations at December 31, 2009, follows (in millions):

|  | Total | 2010 | 2011 to 2012 | 2013 to 2014 | Thereafter |
| --- | ---: | ---: | ---: | ---: | ---: |
| Scheduled interest payment obligationsa | $3,669 | $471 | $931 | $927 | $1,340 |
| Reclamation and environmental obligationsb | 4,849 | 206 | 312 | 249 | 4,082 |
| Take-or-pay contractsc | 2,447 | 1,390 | 675 | 242 | 140 |
| Operating lease obligations | 198 | 27 | 47 | 25 | 99 |
| Atlantic Copper obligation to insurance companyd | 72 | 10 | 20 | 20 | 22 |
| PT Freeport Indonesia mine closure and reclamation funde | 18 | 1 | 1 | 1 | 15 |
| Total contractual cash obligationsf | $11,253 | $2,105 | $1,986 | $1,464 | $5,698 |

a. Scheduled interest payment obligations were calculated using stated coupon rates for fixed-rate debt and interest rates applicable at December 31, 2009, for variable-rate debt.

b. Represents estimated cash payments, on an undiscounted and unescalated basis, associated with reclamation and environmental activities. The timing and the amount of these payments could change as a result of changes in regulatory requirements, changes in scope and costs of reclamation activities and as actual spending occurs. Refer to Note 14 for additional discussion of environmental and reclamation matters.

c. Represents contractual obligations for purchases of goods or services that are defined by us as agreements that are enforceable and legally binding and that specify all significant terms. Take-or-pay contracts primarily comprise the procurement of copper concentrates and cathodes ($1.9 billion), transportation ($227 million) and oxygen ($178 million). Some of our take-or-pay contracts are settled based on the prevailing market rate for the service or commodity purchased, and in some cases, the amount of the actual obligation may change over time because of market conditions. Obligations for copper concentrates and cathodes provide for deliveries of specified volumes, at market-based prices, primarily to Atlantic Copper and the North America copper mines. Transportation obligations are primarily for South

America contracted ocean freight rates and for North America natural gas transportation. Oxygen obligations provide for deliveries of specified volumes, at fixed prices, primarily to Atlantic Copper.

d. In August 2002, Atlantic Copper complied with Spanish legislation by agreeing to fund 7.2 million euros annually for 15 years to an approved insurance company for an estimated 72 million euro contractual obligation to supplement amounts paid to certain retired employees. Atlantic Copper had $58 million recorded for this obligation at December 31, 2009.

e. Represents PT Freeport Indonesia’s commitments to contribute amounts to a cash fund designed to accumulate at least $100 million, including interest, by the end of our Indonesian mining activities to pay for mine closure and reclamation.

f. This table excludes certain other obligations in our consolidated balance sheets, including estimated funding for pension obligations as the funding may vary from year-to-year based on changes in the fair value of plan assets and actuarial assumptions and accrued liabilities totaling $157 million that relate to unrecognized tax benefits where the timing of settlement is not determinable. This table also excludes purchase orders for the purchase of inventory and other goods and services, as purchase orders typically represent authorizations to purchase rather than binding agreements.

In addition to our debt maturities and other contractual obligations, we have other commitments, which we expect to fund with projected operating cash flows, available credit facilities or future financing transactions, if necessary. These include (i) PT Freeport Indonesia’s commitment to provide one percent of its annual revenue for the development of the local people in its area of operations through the Freeport Partnership Fund for Community Development, (ii) Cerro Verde’s local mining fund contributions equal to 3.75 percent of after-tax profits, (iii) Tenke Fungurume’s commitment to provide 0.3 percent of its annual revenue for the development of the local people in its area of operations and (iv) other commercial commitments, including standby letters of credit, surety bonds and guarantees (refer to Notes 14 and 15 for further discussion).

### ENVIRONMENTAL AND RECLAMATION MATTERS

### Environmental

The cost of complying with environmental laws is a fundamental and substantial cost of our business. We had $1.5 billion at December 31, 2009, and $1.4 billion at December 31, 2008, recorded in our consolidated balance sheets for environmental obligations attributed to CERCLA or analogous state programs and for estimated future costs associated with environmental matters at closed facilities and closed portions of certain operating facilities. Refer to Note 14 for further information about environmental regulation, including significant environmental matters.

During 2009, we incurred environmental capital expenditures and other environmental costs (including our joint venture partners’ shares) of $289 million for programs to comply with applicable environmental laws and regulations that affect our operations, compared to $377 million in 2008 and $280 million in 2007 (which included $188 million incurred from March 20, 2007, through December 31, 2007, related to the acquired Phelps Dodge operations). The decrease in environmental capital spending for 2009, compared with 2008, primarily related to completion of large projects in 2008, combined with reduced discretionary spending and extended project timelines. The increase in environmental capital spending for 2008, compared with 2007, primarily related to a full twelve months of Phelps Dodge expenditures in 2008, combined with increased expenditures for accelerated remediation efforts. For 2010, we expect to incur approximately $400 million of aggregate environmental capital expenditures and other environmental costs, which are part of our overall 2010 operating budget. Projected environmental capital expenditures and other environmental costs for 2010 include a $40 million payment for settlement of litigation associated with Pinal Creek (refer to Note 14) made in 2010 and increases in discretionary project spending carried over from 2009.

### Asset Retirement Obligations

We recognize AROs as liabilities when incurred, with the initial measurement at fair value. These liabilities, which are initially estimated based on discounted cash flow estimates, are accreted to full value over time through charges to income. Reclamation costs for future disturbances are recorded as an ARO in the period of disturbance. Our cost estimates are reflected on a third-party cost basis and comply with our legal obligation to retire tangible, long-lived assets. We had recorded AROs totaling $731 million at December 31, 2009, and $712 million at December 31, 2008, in current and long-term liabilities on the consolidated balance sheets. Spending on AROs totaled $28 million in 2009, $91 million in 2008 and $40 million in 2007. The decrease in ARO spending for 2009, compared with 2008, primarily related to extended project timelines which resulted in reduced required expenditures for 2009. The increase in ARO spending for 2008, compared with 2007, primarily related to a full twelve months of Phelps Dodge expenditures in 2008, combined with increased spending for large projects in 2008. For 2010, we expect to incur approximately $38 million for aggregate ARO payments. Refer to Note 14 for further discussion of reclamation and closure costs.

### DISCLOSURES ABOUT MARKET RISKS

### Commodity Price Risk

Our consolidated revenues include the sale of copper concentrates, copper cathodes, copper rod, molybdenum, gold and other metals by our North and South America copper mines, the sale of copper concentrates (which also contain significant quantities of gold and silver) by our Indonesia mining operation, the sale of copper cathodes and cobalt hydroxide by our Africa mining operations, the sale of molybdenum in various forms by our Molybdenum operations, and the sale of copper cathodes, copper anodes and gold in anodes and slimes by Atlantic Copper. Consolidated revenues, operating cash flows and net income vary significantly with fluctuations in the market prices of copper, gold and molybdenum, sales volumes and other factors. Based on projected 2010 consolidated sales volumes and assuming average prices of $3.25 per pound of copper, $1,100 per ounce of gold and $12 per pound of molybdenum for the year, our consolidated operating cash flows for 2010 would approximate $5.3 billion, net of an estimated $0.4 billion of working capital requirements. Operating cash flows would be impacted by approximately $260 million for each $0.10 per pound change in copper prices, $50 million for each $50 per ounce change in gold prices and $45 million for each $1 per pound change in molybdenum prices.

For 2009, more than half of our mined copper was sold in concentrate, approximately 25 percent as cathodes and approximately 21 percent as rod (principally from our North America operations). Substantially all concentrate and cathode sales contracts provide final copper pricing in a specified future period (generally one to four months from the shipment date) based primarily on quoted LME prices. We receive market prices based on prices in the specified future period, which results in price fluctuations recorded through revenues until the date of settlement. We record revenues and invoice customers at the time of shipment based on then-current LME prices, which results in an embedded derivative on our provisional priced concentrate and cathode sales that is adjusted to fair value through earnings each period, using the period-end forward prices, until the date of final pricing. To the extent final prices are higher or lower than what was recorded on a provisional basis, an increase or decrease to revenues is recorded each reporting period until the date of final pricing. Accordingly, in times of rising copper prices, our revenues benefit from higher prices received for contracts priced at current market rates and also from an increase related to the final pricing of provisionally priced sales pursuant to contracts entered into in prior years; in times of falling copper prices, the opposite occurs.

At December 31, 2008, we had provisionally priced copper sales totaling 508 million pounds at our copper mining operations (net of intercompany sales and noncontrolling interests) recorded at an average of $1.39 per pound. Consolidated revenues for 2009 include net additions for adjustments related to these prior year copper sales of $132 million ($61 million to net income attributable to FCX common stockholders or $0.13 per share), compared with an increase of $268 million ($114 million to net loss attributable to FCX common stockholders or $0.30 per share) in 2008 and a decrease of $42 million ($18 million to net income attributable to FCX common stockholders or $0.05 per share) in 2007.

At December 31, 2009, we had provisionally priced copper sales totaling 378 million pounds of copper at our copper mining operations (net of intercompany sales and noncontrolling interests) recorded at an average price of $3.34 per pound, subject to final pricing over the next several months. We estimate that each $0.05 change in the price realized from the December 31, 2009, provisional price recorded would have a net impact on our 2010 consolidated revenues of approximately $25 million ($12 million to net income attributable to FCX common stockholders). The LME spot copper price closed at $3.11 per pound on January 29, 2010.

On limited past occasions, in response to market conditions, we have entered into copper and gold price protection contracts for a portion of our expected future mine production to mitigate the risk of adverse price fluctuations. We do not currently intend to enter into similar hedging programs in the future.

### Foreign Currency Exchange Risk

The functional currency for most of our operations is the U.S. dollar. All of our revenues and a significant portion of our costs are denominated in U.S. dollars; however, some costs and certain assets and liability accounts are denominated in local currencies, including the Indonesian rupiah, Australian dollar, Chilean peso, Peruvian nuevo sol and euro. Generally, our results are positively affected when the U.S. dollar strengthens in relation to those foreign currencies and adversely affected when the U.S. dollar weakens in relation to those foreign currencies. Following is a summary of estimated annual payments and the impact of changes in foreign currency rates on our annual operating costs:

| Indonesia | Exchange Rate per $1 at December 31, 2009 | 2008 | 2007 | Estimated Annual Payments (in local currency) | (in millions)a | 10% Change in Exchange Rate (in millions)b Increase | Decrease |
| --- | ---: | ---: | ---: | --- | ---: | ---: | ---: |
| Rupiah | 9,420 | 10,850 | 9,390 | 2.5 trillion | $265 | $(24) | $30 |
| Australian dollar | 1.12 | 1.43 | 1.14 | 200 million | $178 | $(16) | $20 |
| **South America** |  |  |  |  |  |  |  |
| Chilean peso | 506 | 648 | 498 | 250 billion | $494 | $(45) | $55 |
| Peruvian nuevo sol | 2.89 | 3.17 | 3.05 | 250 million | $87 | $(8) | $10 |
| **Atlantic Copper** |  |  |  |  |  |  |  |
| Euro | 0.69 | 0.72 | 0.68 | 120 million | $173 | $(16) | $19 |

a. Based on December 31, 2009, exchange rates.

b. Reflects the estimated impact on annual operating costs assuming a 10 percent increase or decrease in the exchange rate reported at December 31, 2009.

### Interest Rate Risk

At December 31, 2009, we had total debt of $6.3 billion, of which approximately 19 percent was variable-rate debt with interest rates based on LIBOR or the Euro Interbank Offered Rate (EURIBOR). The table below presents average interest rates for our scheduled maturities of principal for our outstanding debt and the related fair values at December 31, 2009 (in millions, except percentages):

|  | 2010 | 2011 | 2012 | 2013 | 2014 | Thereafter | Fair Value |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| Fixed-rate debt | $– | $89 | $1 | $1 | $1 | $5,066 | $5,552 |
| Average interest rate | – | 8.7% | 5.8% | 5.7% | 5.7% | 8.3% | 8.3% |
| Variable-rate debt | $16 | $4 | $13 | $– | $– | $1,155 | $1,183 |
| Average interest rate | 1.4% | 2.1% | 1.0% | – | – | 4.3% | 4.2% |

### NEW ACCOUNTING STANDARDS

We do not expect the impact of recently issued accounting standards to have a significant impact on our future financial statements and disclosures.

### OFF-BALANCE SHEET ARRANGEMENTS

Refer to Note 15 for information on off-balance sheet arrangements.

### PRODUCT REVENUES AND PRODUCTION COSTS

Unit net cash costs per pound of copper and molybdenum are measures intended to provide investors with information about the cash-generating capacity of our mining operations expressed on a basis relating to the primary metal product for the respective operations. We use this measure for the same purpose and for monitoring operating performance by our mining operations. This information differs from measures of performance determined in accordance with U.S. GAAP and should not be considered in isolation or as a substitute for measures of performance determined in accordance with U.S. GAAP. This measure is presented by other mining companies, although our measure may not be comparable to similarly titled measures reported by other companies.

We present gross profit per pound of copper using both a “by-product” method and a “co-product” method. We use the by-product method in our presentation of gross profit per pound of copper because (i) the majority of our revenues are copper revenues, (ii) we mine ore, which contains copper, gold, molybdenum and other metals, (iii) it is not possible to specifically assign all of our costs to revenues from the copper, gold, molybdenum and other metals we produce, (iv) it is the method used to compare mining operations in certain industry publications and (v) it is the method used by our management and Board of Directors to monitor operations. In the co-product method presentation below, costs are allocated to the different products based on their relative revenue values, which will vary to the extent our metals sales volumes and realized prices change.

In both the by-product and the co-product method calculations, we show adjustments to copper revenues for prior period open sales as separate line items. Because the copper pricing adjustments do not result from current period sales, we have reflected these separately from revenues on current period sales. Noncash and nonrecurring costs consist of items such as LCM inventory adjustments, stock-based compensation costs, write-offs of equipment or unusual charges. They are removed from site production and delivery costs in the calculation of unit net cash costs. Gold, molybdenum and other metal revenues at copper mines are reflected as credits against site production and delivery costs in the by-product method. Presentations under both the by-product and co-product methods are shown below together with reconciliations to amounts reported in our consolidated financial statements.

### North America Copper Mines Product Revenues and Production Costs

*(In millions)*

| Year Ended December 31, 2009 | By-Product Method | Co-Product Method Copper | Molybdenuma | Otherb | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $2,823 | $2,823 | $274 | $45 | $3,142 |
| Site production and delivery, before net noncash |  |  |  |  |  |
| and nonrecurring costs shown below | 1,483 | 1,364 | 142 | 22 | 1,528 |
| By-product creditsa | (274) | – | – | – | – |
| Treatment charges | 102 | 100 | – | 2 | 102 |
| Net cash costs | 1,311 | 1,464 | 142 | 24 | 1,630 |
| Depreciation, depletion and amortization | 264 | 251 | 10 | 3 | 264 |
| Noncash and nonrecurring costs, net | 129 | 127 | 2 | – | 129 |
| Total costs | 1,704 | 1,842 | 154 | 27 | 2,023 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales and hedging | 92 | 92 | – | – | 92 |
| Idle facility and other non-inventoriable costs | (100) | (100) | – | – | (100) |
| Gross profit | $1,111 | $973 | $120 | $18 | $1,111 |
| Reconciliation to Amounts Reported |  |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |  |
|  |  | Production | Depletion and |  |  |
|  | Revenues | and Delivery | Amortization |  |  |
| Totals presented above | $3,142 | $1,528 | $264 |  |  |
| Net noncash and nonrecurring costs per above | N/A | 129 | N/A |  |  |
| Treatment charges per above | N/A | 102 | N/A |  |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales and hedging per above | 92 | N/A | N/A |  |  |
| Eliminations and other | 1 | 152 | 16 |  |  |
| North America copper mines | 3,235 | 1,911 | 280 |  |  |
| South America copper mines | 3,839 | 1,563 | 275 |  |  |
| Indonesia mining | 5,908 | 1,505 | 275 |  |  |
| Africa mining | 389 | 315 | 66 |  |  |
| Molybdenum | 847 | 660 c | 49 |  |  |
| Rod & Refining | 3,356 | 3,336 | 8 |  |  |
| Atlantic Copper Smelting & Refining | 1,892 | 1,895 | 36 |  |  |
| Corporate, other & eliminations | (4,426) | (4,150) | 25 |  |  |
| As reported in FCX’s consolidated financial statements | $15,040 | $7,035 c | $1,014 |  |  |

a. Molybdenum by-product credits and revenues reflect volumes produced at market-based pricing and also include tolling revenues at Sierrita.

b. Includes gold and silver product revenues and production costs.

c. Includes LCM molybdenum inventory adjustments of $19 million.

### North America Copper Mines Product Revenues and Production Costs (continued)

*(In millions)*

| Year Ended December 31, 2008 | By-Product Method | Co-Product Method Copper | Molybdenuma | Otherb | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $4,382 | $4,382 | $892 | $72 | $5,346 |
| Site production and delivery, before net noncash |  |  |  |  |  |
| and nonrecurring costs shown below | 2,681 | 2,326 | 374 | 35 | 2,735 |
| By-product creditsa | (910) | – | – | – | – |
| Treatment charges | 134 | 130 | – | 4 | 134 |
| Net cash costs | 1,905 | 2,456 | 374 | 39 | 2,869 |
| Depreciation, depletion and amortization | 753 | 664 | 83 | 6 | 753 |
| Noncash and nonrecurring costs, net | 743 c | 701 | 39 | 3 | 743 |
| Total costs | 3,401 | 3,821 | 496 | 48 | 4,365 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales and hedging | (71) | (71) | – | – | (71) |
| Idle facility and other non-inventoriable costs | (85) | (83) | (2) | – | (85) |
| Gross profit | $825 | $407 | $394 | $24 | $825 |
| Reconciliation to Amounts Reported |  |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |  |
|  |  | Production | Depletion and |  |  |
|  | Revenues | and Delivery | Amortization |  |  |
| Totals presented above | $5,346 | $2,735 | $753 |  |  |
| Net noncash and nonrecurring costs per above | N/A | 743 c | N/A |  |  |
| Treatment charges per above | N/A | 134 | N/A |  |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales and hedging per above | (71) | N/A | N/A |  |  |
| Eliminations and other | (10) | 96 | 17 |  |  |
| North America copper mines | 5,265 | 3,708 | 770 |  |  |
| South America copper mines | 4,166 | 1,854 | 511 |  |  |
| Indonesia mining | 3,412 | 1,792 | 222 |  |  |
| Africa mining | – | 16 | 6 |  |  |
| Molybdenum | 2,488 | 1,629 | 192 |  |  |
| Rod & Refining | 5,557 | 5,527 | 8 |  |  |
| Atlantic Copper Smelting & Refining | 2,341 | 2,276 | 35 |  |  |
| Corporate, other & eliminations | (5,433) | (5,604) | 38 |  |  |
| As reported in FCX’s consolidated financial statements | $17,796 | $11,198 d | $1,782 |  |  |

a. Molybdenum by-product credits and revenues reflect volumes produced at market-based pricing and also include tolling revenues at Sierrita.

b. Includes gold and silver product revenues and production costs.

c. Includes charges totaling $661 million for LCM inventory adjustments.

d. Includes LCM inventory adjustments of $782 million.

### North America Copper Mines Product Revenues and Production Costs (continued)

*(In millions)*

| March 20, 2007, through December 31, 2007a | By-Product Method | Co-Product Method Copper | Molybdenumb | Otherc | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $3,526 | $3,526 | $717 | $47 | $4,290 |
| Site production and delivery, before net noncash |  |  |  |  |  |
| and nonrecurring costs shown below | 1,516 | 1,296 | 253 | 18 | 1,567 |
| By-product creditsb | (713) | – | – | – | – |
| Treatment charges | 100 | 98 | – | 2 | 100 |
| Net cash costs | 903 | 1,394 | 253 | 20 | 1,667 |
| Depreciation, depletion and amortization | 487 | 418 | 67 | 2 | 487 |
| Noncash and nonrecurring costs, net | 361 | 341 | 4 | 16 | 361 |
| Total costs | 1,751 | 2,153 | 324 | 38 | 2,515 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales and hedging | (203) | (203) | – | – | (203) |
| Idle facility and other non-inventoriable costs | (56) | (55) | (1) | – | (56) |
| Gross profit | $1,516 | $1,115 | $392 | $9 | $1,516 |
| Reconciliation to Amounts Reported for the Year Ended December 31, 2007 |  |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |  |
|  |  | Production | Depletion and |  |  |
|  | Revenues | and Delivery | Amortization |  |  |
| Totals presented above | $4,290 | $1,567 | $487 |  |  |
| Net noncash and nonrecurring costs per above | N/A | 361 | N/A |  |  |
| Treatment charges per above | N/A | 100 | N/A |  |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales and hedging per above | (203) | N/A | N/A |  |  |
| Eliminations and other | 6 | 138 | 12 |  |  |
| North America copper mines | 4,093 | 2,166 | 499 |  |  |
| South America copper mines | 3,879 | 1,277 | 378 |  |  |
| Indonesia mining | 4,808 | 1,388 | 199 |  |  |
| Africa mining | – | 10 | 2 |  |  |
| Molybdenum | 1,746 | 1,287 | 94 |  |  |
| Rod & Refining | 5,140 | 5,119 | 7 |  |  |
| Atlantic Copper Smelting & Refining | 2,388 | 2,329 | 36 |  |  |
| Corporate, other & eliminations | (5,115) | (5,049) | 31 |  |  |
| As reported in FCX’s consolidated financial statements | $16,939 | $8,527 | $1,246 |  |  |

a. Reflects the results of the North America copper mines under FCX management.

b. Molybdenum by-product credits and revenues reflect volumes produced at market-based pricing and also include tolling revenues at Sierrita.

c. Includes gold and silver product revenues and production costs.

### South America Copper Mines Product Revenues and Production Costs

*(In millions)*

| Year Ended December 31, 2009 | By-Product Method | Co-Product Method Copper | Other a | Total |
| --- | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $3,768 | $3,768 | $167 | $3,935 |
| Site production and delivery, before net noncash |  |  |  |  |
| and nonrecurring costs shown below | 1,512 | 1,429 | 91 | 1,520 |
| By-product credits | (159) | – | – | – |
| Treatment charges | 206 | 206 | – | 206 |
| Net cash costs | 1,559 | 1,635 | 91 | 1,726 |
| Depreciation, depletion and amortization | 275 | 267 | 8 | 275 |
| Noncash and nonrecurring costs, net | 28 | 28 | – | 28 |
| Total costs | 1,862 | 1,930 | 99 | 2,029 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |
| period open sales | 109 | 109 | – | 109 |
| Other non-inventoriable costs | (31) | (26) | (5) | (31) |
| Gross profit | $1,984 | $1,921 | $63 | $1,984 |
| Reconciliation to Amounts Reported |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |
|  |  | Production | Depletion and |  |
|  | Revenues | and Delivery | Amortization |  |
| Totals presented above | $3,935 | $1,520 | $275 |  |
| Net noncash and nonrecurring costs per above | N/A | 28 | N/A |  |
| Less: Treatment charges per above | (206) | N/A | N/A |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |
| period open sales per above | 109 | N/A | N/A |  |
| Eliminations and other | 1 | 15 | – |  |
| South America copper mines | 3,839 | 1,563 | 275 |  |
| North America copper mines | 3,235 | 1,911 | 280 |  |
| Indonesia mining | 5,908 | 1,505 | 275 |  |
| Africa mining | 389 | 315 | 66 |  |
| Molybdenum | 847 | 660 b | 49 |  |
| Rod & Refining | 3,356 | 3,336 | 8 |  |
| Atlantic Copper Smelting & Refining | 1,892 | 1,895 | 36 |  |
| Corporate, other & eliminations | (4,426) | (4,150) | 25 |  |
| As reported in FCX’s consolidated financial statements | $15,040 | $7,035 b | $1,014 |  |

a. Includes gold, silver and molybdenum product revenues and production costs.

b. Includes LCM molybdenum inventory adjustments of $19 million.

### South America Copper Mines Product Revenues and Production Costs (continued)

*(In millions)*

| Year Ended December 31, 2008 | By-Product Method | Co-Product Method Copper | Other a | Total |
| --- | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $3,910 | $3,910 | $216 | $4,126 |
| Site production and delivery, before net noncash |  |  |  |  |
| and nonrecurring costs shown below | 1,711 | 1,631 | 102 | 1,733 |
| By-product credits | (194) | – | – | – |
| Treatment charges | 211 | 211 | – | 211 |
| Net cash costs | 1,728 | 1,842 | 102 | 1,944 |
| Depreciation, depletion and amortization | 508 | 483 | 25 | 508 |
| Noncash and nonrecurring costs, net | 103 b | 100 | 3 | 103 |
| Total costs | 2,339 | 2,425 | 130 | 2,555 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |
| period open sales | 230 | 230 | – | 230 |
| Other non-inventoriable costs | (37) | (34) | (3) | (37) |
| Gross profit | $1,764 | $1,681 | $83 | $1,764 |
| Reconciliation to Amounts Reported |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |
|  |  | Production | Depletion and |  |
|  | Revenues | and Delivery | Amortization |  |
| Totals presented above | $4,126 | $1,733 | $508 |  |
| Net noncash and nonrecurring costs per above | N/A | 103 b | N/A |  |
| Less: Treatment charges per above | (211) | N/A | N/A |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |
| period open sales per above | 230 | N/A | N/A |  |
| Eliminations and other | 21 | 18 | 3 |  |
| South America copper mines | 4,166 | 1,854 | 511 |  |
| North America copper mines | 5,265 | 3,708 | 770 |  |
| Indonesia mining | 3,412 | 1,792 | 222 |  |
| Africa mining | – | 16 | 6 |  |
| Molybdenum | 2,488 | 1,629 | 192 |  |
| Rod & Refining | 5,557 | 5,527 | 8 |  |
| Atlantic Copper Smelting & Refining | 2,341 | 2,276 | 35 |  |
| Corporate, other & eliminations | (5,433) | (5,604) | 38 |  |
| As reported in FCX’s consolidated financial statements | $17,796 | $11,198 c | $1,782 |  |

a. Includes gold, silver and molybdenum product revenues and production costs.

b. Includes charges totaling $10 million for LCM inventory adjustments.

c. Includes LCM inventory adjustments of $782 million.

### South America Copper Mines Product Revenues and Production Costs (continued)

*(In millions)*

| March 20, 2007, through December 31, 2007a | By-Product Method | Co-Product Method Copper | Other b | Total |
| --- | ---: | ---: | ---: | ---: |
| Revenues, excluding adjustments shown below | $3,882 | $3,882 | $123 | $4,005 |
| Site production and delivery, before net noncash |  |  |  |  |
| and nonrecurring costs shown below | 1,078 | 1,040 | 52 | 1,092 |
| By-product credits | (109) | – | – | – |
| Treatment charges | 240 | 239 | 1 | 240 |
| Net cash costs | 1,209 | 1,279 | 53 | 1,332 |
| Depreciation, depletion and amortization | 377 | 364 | 13 | 377 |
| Noncash and nonrecurring costs, net | 171 | 170 | 1 | 171 |
| Total costs | 1,757 | 1,813 | 67 | 1,880 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |
| period open sales | 75 | 75 | – | 75 |
| Other non-inventoriable costs | (28) | (27) | (1) | (28) |
| Gross profit | $2,172 | $2,117 | $55 | $2,172 |
| Reconciliation to Amounts Reported for the Year Ended December 31, 2007 |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |
|  |  | Production | Depletion and |  |
|  | Revenues | and Delivery | Amortization |  |
| Totals presented above | $4,005 | $1,092 | $377 |  |
| Net noncash and nonrecurring costs per above | N/A | 171 | N/A |  |
| Less: Treatment charges per above | (240) | N/A | N/A |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |
| period open sales per above | 75 | N/A | N/A |  |
| Eliminations and other | 39 | 14 | 1 |  |
| South America copper mines | 3,879 | 1,277 | 378 |  |
| North America copper mines | 4,093 | 2,166 | 499 |  |
| Indonesia mining | 4,808 | 1,388 | 199 |  |
| Africa mining | – | 10 | 2 |  |
| Molybdenum | 1,746 | 1,287 | 94 |  |
| Rod & Refining | 5,140 | 5,119 | 7 |  |
| Atlantic Copper Smelting & Refining | 2,388 | 2,329 | 36 |  |
| Corporate, other & eliminations | (5,115) | (5,049) | 31 |  |
| As reported in FCX’s consolidated financial statements | $16,939 | $8,527 | $1,246 |  |

a. Reflects the results of the South America copper mines under FCX management.

b. Includes gold, silver and molybdenum product revenues and production costs.

### Indonesia Mining Product Revenues and Production Costs

*(In millions)*

| Year Ended December 31, 2009 | By-Product Method | Co-Product Method Copper | Gold | Silver | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| Revenues, after adjustments shown below | $3,708 | $3,708 | $2,532 | $74 | $6,314 |
| Site production and delivery, before net noncash |  |  |  |  |  |
| and nonrecurring costs shown below | 1,468 | 862 | 589 | 17 | 1,468 |
| Gold and silver credits | (2,606) | – | – | – | – |
| Treatment charges | 312 | 183 | 125 | 4 | 312 |
| Royalty on metals | 147 | 86 | 59 | 2 | 147 |
| Net cash costs | (679) | 1,131 | 773 | 23 | 1,927 |
| Depreciation and amortization | 275 | 162 | 110 | 3 | 275 |
| Noncash and nonrecurring costs, net | 37 | 22 | 15 | – | 37 |
| Total costs | (367) | 1,315 | 898 | 26 | 2,239 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales | 53 | 53 | – | – | 53 |
| PT Smelting intercompany profit | (54) | (32) | (21) | (1) | (54) |
| Gross profit | $4,074 | $2,414 | $1,613 | $47 | $4,074 |
| Reconciliation to Amounts Reported |  |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |  |
|  |  | Production | Depletion and |  |  |
|  | Revenues | and Delivery | Amortization |  |  |
| Totals presented above | $6,314 | $1,468 | $275 |  |  |
| Net noncash and nonrecurring costs per above | N/A | 37 | N/A |  |  |
| Less: Treatment charges per above | (312) | N/A | N/A |  |  |
| Less: Royalty per above | (147) | N/A | N/A |  |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales per above | 53 | N/A | N/A |  |  |
| Indonesia mining | 5,908 | 1,505 | 275 |  |  |
| North America copper mines | 3,235 | 1,911 | 280 |  |  |
| South America copper mines | 3,839 | 1,563 | 275 |  |  |
| Africa mining | 389 | 315 | 66 |  |  |
| Molybdenum | 847 | 660 a | 49 |  |  |
| Rod & Refining | 3,356 | 3,336 | 8 |  |  |
| Atlantic Copper Smelting & Refining | 1,892 | 1,895 | 36 |  |  |
| Corporate, other & eliminations | (4,426) | (4,150) | 25 |  |  |
| As reported in FCX’s consolidated financial statements | $15,040 | $7,035 a | $1,014 |  |  |

a. Includes LCM molybdenum inventory adjustments of $19 million.

### Indonesia Mining Product Revenues and Production Costs (continued)

*(In millions)*

| Year Ended December 31, 2008 | By-Product Method | Co-Product Method Copper | Gold | Silver | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| Revenues, after adjustments shown below | $2,628 | $2,628 | $1,025 | $50 | $3,703 |
| Site production and delivery, before net noncash |  |  |  |  |  |
| and nonrecurring costs shown below | 1,762 | 1,252 | 487 | 23 | 1,762 |
| Gold and silver credits | (1,075) | – | – | – | – |
| Treatment charges | 268 | 190 | 74 | 4 | 268 |
| Royalty on metals | 113 | 80 | 31 | 2 | 113 |
| Net cash costs | 1,068 | 1,522 | 592 | 29 | 2,143 |
| Depreciation and amortization | 222 | 158 | 61 | 3 | 222 |
| Noncash and nonrecurring costs, net | 30 | 22 | 8 | – | 30 |
| Total costs | 1,320 | 1,702 | 661 | 32 | 2,395 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales | 90 | 90 | – | – | 90 |
| PT Smelting intercompany profit | 17 | 12 | 5 | – | 17 |
| Gross profit | $1,415 | $1,028 | $369 | $18 | $1,415 |
| Reconciliation to Amounts Reported |  |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |  |
|  |  | Production | Depletion and |  |  |
|  | Revenues | and Delivery | Amortization |  |  |
| Totals presented above | $3,703 | $1,762 | $222 |  |  |
| Net noncash and nonrecurring costs per above | N/A | 30 | N/A |  |  |
| Less: Treatment charges per above | (268) | N/A | N/A |  |  |
| Less: Royalty per above | (113) | N/A | N/A |  |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales per above | 90 | N/A | N/A |  |  |
| Indonesia mining | 3,412 | 1,792 | 222 |  |  |
| North America copper mines | 5,265 | 3,708 | 770 |  |  |
| South America copper mines | 4,166 | 1,854 | 511 |  |  |
| Africa mining | – | 16 | 6 |  |  |
| Molybdenum | 2,488 | 1,629 | 192 |  |  |
| Rod & Refining | 5,557 | 5,527 | 8 |  |  |
| Atlantic Copper Smelting & Refining | 2,341 | 2,276 | 35 |  |  |
| Corporate, other & eliminations | (5,433) | (5,604) | 38 |  |  |
| As reported in FCX’s consolidated financial statements | $17,796 | $11,198 a | $1,782 |  |  |

a. Includes LCM inventory adjustments of $782 million.

### Indonesia Mining Product Revenues and Production Costs (continued)

*(In millions)*

| Year Ended December 31, 2007 | By-Product Method | Co-Product Method Copper | Gold | Silver | Total |
| --- | ---: | ---: | ---: | ---: | ---: |
| Revenues, after adjustments shown below | $3,777 | $3,777 | $1,490 | $48 | $5,315 |
| Site production and delivery, before net noncash |  |  |  |  |  |
| and nonrecurring costs shown below | 1,342 | 954 | 376 | 12 | 1,342 |
| Gold and silver credits | (1,538) | – | – | – | – |
| Treatment charges | 385 | 274 | 108 | 3 | 385 |
| Royalty on metals | 133 | 94 | 38 | 1 | 133 |
| Net cash costs | 322 | 1,322 | 522 | 16 | 1,860 |
| Depreciation and amortization | 199 | 141 | 56 | 2 | 199 |
| Noncash and nonrecurring costs, net | 46 | 33 | 12 | 1 | 46 |
| Total costs | 567 | 1,496 | 590 | 19 | 2,105 |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales | 11 | 11 | – | – | 11 |
| PT Smelting intercompany profit | 13 | 10 | 3 | – | 13 |
| Gross profit | $3,234 | $2,302 | $903 | $29 | $3,234 |
| Reconciliation to Amounts Reported |  |  |  |  |  |
| (In millions) |  |  | Depreciation, |  |  |
|  |  | Production | Depletion and |  |  |
|  | Revenues | and Delivery | Amortization |  |  |
| Totals presented above | $5,315 | $1,342 | $199 |  |  |
| Net noncash and nonrecurring costs per above | N/A | 46 | N/A |  |  |
| Less: Treatment charges per above | (385) | N/A | N/A |  |  |
| Less: Royalty per above | (133) | N/A | N/A |  |  |
| Revenue adjustments, primarily for pricing on prior |  |  |  |  |  |
| period open sales per above | 11 | N/A | N/A |  |  |
| Indonesia mining | 4,808 | 1,388 | 199 |  |  |
| North America copper mines | 4,093 | 2,166 | 499 |  |  |
| South America copper mines | 3,879 | 1,277 | 378 |  |  |
| Africa mining | – | 10 | 2 |  |  |
| Molybdenum | 1,746 | 1,287 | 94 |  |  |
| Rod & Refining | 5,140 | 5,119 | 7 |  |  |
| Atlantic Copper Smelting & Refining | 2,388 | 2,329 | 36 |  |  |
| Corporate, other & eliminations | (5,115) | (5,049) | 31 |  |  |
| As reported in FCX’s consolidated financial statements | $16,939 | $8,527 | $1,246 |  |  |

113

### Henderson Molybdenum Mine Product Revenues and Production Costs

*(In millions)*

|  | Years Ended December 31, 2009 | 2008 | 2007 a |
| --- | ---: | ---: | ---: |
| Revenues | $317 | $1,182 | $853 |
| Site production and delivery, before net noncash |  |  |  |
| and nonrecurring costs shown below | 148 | 216 | 137 |
| Net cash costs | 148 | 216 | 137 |
| Depreciation, depletion and amortization | 26 | 172 | 80 |
| Noncash and nonrecurring costs, net | 1 | 7 b | 2 |
| Total costs | 175 | 395 | 219 |
| Gross profitc | $142 | $787 | $634 |
| Reconciliation to Amounts Reported |  | Production | Depreciation, |
| (In millions) |  | and | Depletion and |
|  | Revenues | Delivery | Amortization |
| Year Ended December 31, 2009 |  |  |  |
| Totals presented above | $317 | $148 | $26 |
| Net noncash and nonrecurring costs per above | N/A | 1 | N/A |
| Henderson mine | 317 | 149 | 26 |
| Other molybdenum operations and eliminationsd | 530 | 511 e | 23 |
| Molybdenum | 847 | 660 | 49 |
| North America copper mines | 3,235 | 1,911 | 280 |
| South America copper mines | 3,839 | 1,563 | 275 |
| Indonesia mining | 5,908 | 1,505 | 275 |
| Africa mining | 389 | 315 | 66 |
| Rod & Refining | 3,356 | 3,336 | 8 |
| Atlantic Copper Smelting & Refining | 1,892 | 1,895 | 36 |
| Corporate, other & eliminations | (4,426) | (4,150) | 25 |
| As reported in FCX’s consolidated financial statements | $15,040 | $7,035 e | $1,014 |
| Year Ended December 31, 2008 |  |  |  |
| Totals presented above | $1,182 | $216 | $172 |
| Net noncash and nonrecurring costs per above | N/A | 7 b | N/A |
| Henderson mine | 1,182 | 223 | 172 |
| Other molybdenum operations and eliminationsd | 1,306 | 1,406 e | 20 |
| Molybdenum | 2,488 | 1,629 | 192 |
| North America copper mines | 5,265 | 3,708 | 770 |
| South America copper mines | 4,166 | 1,854 | 511 |
| Indonesia mining | 3,412 | 1,792 | 222 |
| Africa mining | – | 16 | 6 |
| Rod & Refining | 5,557 | 5,527 | 8 |
| Atlantic Copper Smelting & Refining | 2,341 | 2,276 | 35 |
| Corporate, other & eliminations | (5,433) | (5,604) | 38 |
| As reported in FCX’s consolidated financial statements | $17,796 | $11,198 f | $1,782 |
| Year Ended December 31, 2007 |  |  |  |
| Totals presented above | $853 | $137 | $80 |
| Net noncash and nonrecurring costs per above | N/A | 2 | N/A |
| Henderson mine | 853 | 139 | 80 |
| Other molybdenum operations and eliminationsd | 893 | 1,148 | 14 |
| Molybdenum | 1,746 | 1,287 | 94 |
| North America copper mines | 4,093 | 2,166 | 499 |
| South America copper mines | 3,879 | 1,277 | 378 |
| Indonesia mining | 4,808 | 1,388 | 199 |
| Africa mining | – | 10 | 2 |
| Rod & Refining | 5,140 | 5,119 | 7 |
| Atlantic Copper Smelting & Refining | 2,388 | 2,329 | 36 |
| Corporate, other & eliminations | (5,115) | (5,049) | 31 |
| As reported in FCX’s consolidated financial statements | $16,939 | $8,527 | $1,246 |

a. Reflects the period from March 20, 2007, through December 31, 2007, which represents the results of the Henderson molybdenum mine under FCX management.

b. Includes charges totaling $1 million for LCM inventory adjustments.

c. Gross profit reflects sales of Henderson products based on volumes produced at market-based pricing. On a consolidated basis, the Molybdenum segment includes profits on sales as they are made to third parties and realizations based on actual contract terms. As a result, the actual gross profit realized will differ from the amounts reported in this table.

d. Primarily includes amounts associated with the molybdenum sales company, which includes sales of molybdenum produced as a by-product at our North and South America copper mines.

e. Includes LCM molybdenum inventory adjustments of $19 million in 2009 and $100 million in 2008.

f. Includes LCM inventory adjustments of $782 million.

### CAUTIONARY STATEMENT

Our discussion and analysis contains forward-looking statements in which we discuss factors we believe may affect our performance in the future. Forward-looking statements are all statements other than historical facts, such as statements regarding projected ore grades and milling rates, production and sales volumes, unit net cash costs, operating cash flows, capital expenditures, mine production and development plans, availability of power, water, labor and equipment, anticipated environmental reclamation and closure costs and plans, environmental liabilities, the impact of copper, gold, molybdenum and cobalt price changes, reserve estimates, the impact of deferred intercompany profits on earnings, liquidity, other financial commitments and tax rates, potential prepayments of debt and future dividend payments.

Our discussion and analysis also includes forward-looking statements regarding mineralized material not included in reserves. The mineralized material described in our discussion and analysis will not qualify as reserves until comprehensive engineering studies establish their economic feasibility. Accordingly, no assurance can be given that the estimated mineralized material not included in reserves will become proven and probable reserves.

Accuracy of the forward-looking statements depends on assumptions about events that change over time and is thus susceptible to periodic change based on actual experience and new developments. We caution readers that we assume no obligation to update the forward-looking statements in this discussion and analysis and we do not intend to update the forward-looking statements more frequently than quarterly.

Additionally, important factors that might cause future results to differ from results anticipated by forward-looking statements include mine sequencing, production rates, industry risks, commodity prices, political risks, the potential effects of violence in Indonesia, potential outcomes of the contract review process in the Democratic Republic of Congo, weather-related risks, labor relations, currency translation risks and other factors described in more detail under the heading “Risk Factors” in our annual report on Form 10-K for the year ended December 31, 2009.

## Controls and procedures

As filed, 1,014 characters.

(a) Evaluation of disclosure controls and procedures. Our chief executive officer and chief financial officer, with the participation of management, have evaluated the effectiveness of our “disclosure controls and procedures” (as defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934) as of the end of the period covered by this annual report on Form 10-K. Based on their evaluation, they have concluded that our disclosure controls and procedures are effective as of the end of the period covered by this report.

(b) Changes in internal controls. There has been no change in our internal control over financial reporting that occurred during the fourth quarter that has materially affected, or is reasonably likely to materially affect our internal control over financial reporting.

(c) Management’s annual report on internal control over financial reporting and the report thereon of Ernst & Young LLP are included herein under Item 8. “Financial Statements and Supplemental Data.”

Filed Feb 26, 2010.
Source: SEC EDGAR, the filing index for accession 0000831259-10-000010. Last ingested by Listed: Nov 6, 2026, 13:42 ET. No prices; not investment advice.