# Sterling Infrastructure, Inc.: Form 10-Q for the period ended Mar 31, 2009

- Company: [Sterling Infrastructure, Inc.](/companies/strl.md) (CIK 874238)
- Form: 10-Q
- Filed: 2009-05-11
- Accepted by EDGAR: May 11, 2009, 08:35 ET
- Period: 2009-03-31
- Accession: 0000874238-09-000013
- Inline XBRL: no
- Main document: https://www.sec.gov/Archives/edgar/data/874238/000087423809000013/form10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/874238/000087423809000013/

## Management's discussion and analysis

As filed, 31,697 characters.

### Forward Looking Statements

This Quarterly Report on Form 10-Q includes certain statements that are, or may be deemed to be, “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended, (the “Exchange Act”). These forward-looking statements may be found throughout this report, including in this “Management’s Discussion and Analysis of Financial Condition and Results of Operations” and in “Risk Factors”, below and relate to matters such as our industry, business strategy, goals and expectations concerning our market position, contract backlog, future operations, margins, profitability, capital expenditures, liquidity and capital resources and other financial and operating information. We use the words “anticipate,” “assume,” “believe,” “budget,” “continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “will,” “future” and similar terms and phrases to identify forward-looking statements in this report.

Forward-looking statements reflect our current expectations regarding future events, results or outcomes. These expectations may or may not be realized. Some of these expectations may be based upon assumptions or judgments that prove to be incorrect. In addition, our business and operations involve numerous risks and uncertainties, many of which are beyond our control, which could result in our expectations not being realized or otherwise could materially affect our financial condition, results of operations and cash flows.

Actual events, results and outcomes may differ materially from our expectations due to a variety of factors. Although it is not possible to identify all of these factors, they include, among others, the following:

- changes in general economic conditions, in federal, state and local government funding for infrastructure services and in those governments' laws and regulations;
- delays or difficulties related to the completion of our projects, including additional costs, reductions in revenues or the payment of liquidated damages or obtaining required governmental permits and approvals;
- actions of suppliers, subcontractors, customers, competitors, banks, surety companies and others which are beyond our control including suppliers' and subcontractors' failure to perform;
- the effects of estimates inherent in our percentage-of-completion accounting policies including onsite conditions that differ materially from those assumed in our original bid, contract modifications, mechanical problems with our machinery or equipment and effects of other risks discussed in this document;
- cost escalations associated with our fixed-unit-price contracts, including changes in availability, proximity and cost of materials such as steel, concrete, aggregates, oil, fuel and other construction materials and cost escalations associated with subcontractors and labor;
- our dependence on a few significant customers;
- adverse weather conditions; although we prepare our budgets and bid contracts based on historical rain and snowfall patterns, the incidence of rain, snow, hurricanes, etc., may differ materially from these expectations;
- the presence of competitors with greater financial resources and the impact of competitive services and pricing;
- our ability to successfully identify, finance, complete and integrate acquisitions;
- citations issued by any governmental authority, including the Occupational Safety and Health Administration; and
- the current instability of financial institutions could cause losses on our cash and cash equivalents and short-term investments.

Stockholders and potential investors are urged to carefully consider these factors and the other factors described under “Risk Factors” in Item 1A of the Company’s Annual Report on Form 10-K for the year ended December 31, 2008 in evaluating any forward-looking statements and are cautioned not to place undue reliance on these forward-looking statements. Although we believe that our plans, intentions and expectations reflected in or suggested by the forward-looking statements that we make in this report are reasonable, we can provide no assurance that such plans, intentions or expectations will be achieved.

Any forward-looking statements included in this report are made only as of the date of this report, and we undertake no obligation to update any information contained in this report or to publicly release the results of any revisions to any forward-looking statements that may be made to reflect events or circumstances that occur, or that we become aware of, after the date of this report, except as may be required by applicable securities laws.

### Overview

Sterling Construction Company, Inc. (“Sterling” or “the Company”) operates in one segment, heavy civil construction, through Texas Sterling Construction Co., ("TSC"), Road and Highway Builders, LLC ("RHB"), Road and Highway Builders Inc. ("RHB Inc") and Road and Highway Builders of California, Inc ("RHB Cal") that specialize in the building, reconstruction and repair of transportation and water infrastructure in large and growing population markets in Texas and Nevada. Our transportation infrastructure projects include highways, roads, bridges and light rail, and our water infrastructure projects include water, wastewater and storm drainage systems. We provide general contracting services primarily to public sector clients utilizing our own employees and equipment for activities including excavating, paving, pipe installation and asphalt and concrete placement. We purchase the necessary materials for our contracts, perform approximately three-quarters of the work required by our contracts with our own crews, and generally engage subcontractors only for ancillary services.

For a more detailed discussion of the Company's business, readers of this report are urged to review Item 1, Business, of the Company's Annual Report on Form 10-K for the year ended December 31, 2008.

### Material Changes in Financial Condition

At March 31, 2009, there had been no material changes in the Company’s financial condition since December 31, 2008, as discussed in Item 7 of the Company’s Annual Report on Form 10-K for the year ended December 31, 2008.

### Results of Operations

### Three months ended March 31, 2009 compared with three months ended March 31, 2008

| (dollar amounts in thousands) (unaudited): | 2009 | 2008 | % change |
| --- | ---: | ---: | ---: |
| Revenues | $94,866 | $84,926 | 11.7% |
| Gross profit | 11,811 | 8,101 | 45.8% |
| **Gross margin** | **12.5%** | **9.5%** | **31.6%** |
| General, administrative and other expenses | (3,127) | (3,458) | (9.6%) |
| Operating income | 8,684 | 4,643 | 87.0% |
| **Operating margin** | **9.2%** | **5.5%** | **67.3%** |
| Interest income, net | 101 | 157 | (35.7%) |
| Income before taxes and earnings attributable to the noncontrolling interest | 8,785 | 4,800 | 83.0% |
| Income taxes | (2,919) | (1,591) | 83.5% |
| Net income attributable to the noncontrolling interest in earnings of subsidiary | (301) | (92) | 227.2% |
| Net income attributable to Sterling common stockholders | $5,565 | $3,117 | 78.5% |

14

#### Revenues

Revenues for the first quarter of 2009 increased $9.9 million or 11.7% over the comparable quarter in 2008. A majority of the increase was due to the amount of revenues earned by our Nevada operations in the first quarter of 2009 vs. the comparable quarter in 2008. The increase in revenues in Nevada is primarily due to projects being performed in 2009 in Southern Nevada where the weather is less seasonal than in Northern Nevada where our Nevada projects were principally located in 2008.

#### Backlog

At the end of the first quarter of the current year, our backlog of construction projects was $385 million, as compared to $448 million as of December 31, 2008 and $485 million at the end of the first quarter of 2008. In the first quarter of 2009, we were awarded or were the apparent low bidder on $32 million of new contracts. At March 31, 2009, we had $12 million in backlog which had not been officially awarded to us. Historically, subsequent non-award of such low bids has not had an adverse effect on the Company’s backlog or financial condition.

While our business does not include residential and commercial infrastructure work, the severe fall-off in new projects in those markets in Nevada and to a lesser extent in Texas, has resulted in some residential and commercial infrastructure contractors bidding on public sector transportation and water infrastructure projects, thus increasing competition and creating downward pressure on bid prices in our markets. These and other factors could adversely affect our ability to maintain or increase our backlog through successful bids for new projects and could adversely affect the profitability of new projects that we do obtain through successful bids.

Recent reductions in miles driven in the U.S. and more fuel efficient vehicles are reducing federal and state gasoline taxes and tolls collected. Additionally, the current credit crisis may limit the amount of state and local bonds that can be sold at reasonable terms. Further, the nationwide decline in home sales, the increase in foreclosures and a prolonged recession may result in decreases in user fees and property and sales taxes. These and other factors could adversely affect transportation and water infrastructure capital expenditures in our markets.

In February 2009, the American Recovery and Reinvestment Act ("ARRA") was signed into law which provides stimulus funds of $2.25 billion in Texas and $200 million in Nevada for the construction of highway and bridges over the years 2009 and 2010. These stimulus funds have funded or partially funded certain projects in April 2009 lettings by the Texas Department of Transportation ("TXDOT") and may increase the number or projects, and margins thereon, that we bid the rest of this year and in 2010.

#### Gross profit

During 2008 and 2009, we have had approximately 60 contracts-in-progress at any one time of various sizes, expected different profitability and in various stages of completion. The nearer a contract progresses toward completion, the more visibility we have in refining our estimate of total revenues (including incentives and delay penalties), costs and gross profit. Thus gross profit as a percent of revenues can increase or decrease from comparable and sequential quarters–to–quarters due to which contracts are just commencing or are at a more advanced stage of completion.

The increase in gross profit of $3.7 million or 45.8% in the first quarter of 2009 over the comparable quarter in 2008 was due in part to the increase in revenues of our Nevada operations in 2009 and in part to the mix in the stage of completion and profitability of certain contracts at March 31, 2009 as discussed above. The gross margin of 12.5% in the first quarter of 2009 may not be indicative of the gross margins that the Company will achieve in subsequent quarters of 2009.

#### General and administrative expenses, net of other income

General and administrative expenses, net of other income, decreased by $331,000 in the first quarter of 2009 versus 2008, primarily due to lower bonus accruals and depreciation charged to G&A, offset by an increase in accruals for external and internal audit services in the first quarter of 2009 versus the comparable period in 2008. As a percent of revenues, G&A, net of other income, was 3.3% for the first quarter of 2009 versus 4.1% of revenues for the comparable prior year quarter. General and administrative expenses and other income do not vary directly with the volume of work performed on contracts.

#### Operating income

Operating income increased $4.0 million in the first quarter of 2009 over 2008, due to the factors discussed above regarding gross profit and general and administrative expenses.

#### Income taxes

Our effective income tax rate for the first quarter of 2009 was 33.2% compared to 33.1% for the first quarter of 2008 and varied from the statutory rate as a result of various miscellaneous permanent differences, including the portion of earnings of a subsidiary taxed to the noncontrolling interest owner offset by the revised Texas franchise tax.

### Liquidity and Capital Resources

#### Cash Flows

The following table sets forth our cash flows for the three months ended March 31, 2009 and 2008 (in thousands) (unaudited):

|  | Three months ended March 31 2009 | 2008 |
| --- | ---: | ---: |
| Cash and cash equivalents at end of period | $57,712 | $55,305 |
| Net cash provided by (used in): |  |  |
| Operating activities | 5,057 | 656 |
| Investing activities | 3,115 | (4,225) |
| Financing activities | (5,765) | (4,878) |
| Increase (decrease) in cash and cash equivalents | $2,407 | $(8,447) |
| Capital expenditures | $1,598 | $4,467 |
| Working capital at end of period | $98,924 | $80,797 |

#### Operating Activities

Significant non-cash items included in operating activities are:

- depreciation and amortization, which for the first three months of the current year totaled $3.6 million, an increase of $0.3 million from last year, as a result of the continued increase in the size of our construction fleet in recent years; and
- deferred tax expense of $2.2 million in 2009 versus $1.2 million in 2008, respectively, mainly attributable to accelerated depreciation methods used on equipment for tax purposes and amortization for tax return purposes of goodwill.

Besides net income of $5.6 million attributable to Sterling's common stockholders and the non-cash items discussed above, significant components of cash flow are as follows:

- contracts receivable and costs and estimated earnings in excess of billings increased by $11.2 million in the first three months of 2009 due in part to the increase in revenues of $9.9 million, and in part due to the timing of billings to customers, as compared to an increase of $0.7 million in those accounts in 2008; and
- the increase in billings in excess of costs and estimated earnings on uncompleted contracts of $5.0 million as of March 31, 2009, versus a decrease of $1.4 million as of March 31, 2008, which reflects the increase in volume of work being performed and timing of billings to customers.

#### Investing activities

Expenditures for the replacement of certain equipment and to expand our construction fleet and office and shop facilities totaled $1.6 million in the first three months of 2009, compared with a total of $4.5 million of property and equipment purchases in the same period last year. Capital equipment is acquired as needed to support work crews required by increased backlog and to replace retiring equipment. We plan to continue the replacement of equipment over the remainder of the year as required. The decrease in capital expenditures in 2009 was principally due to management's cautious view regarding certain of the Company's markets and current economic uncertainties. Unless such facts change, management expects capital expenditures in 2009 to be less than in 2008.

Also during the three months ended March 31, 2009 and 2008, the Company had net sales of short-term securities of $4.6 million and $54,000, respectively.

#### Financing activities

Financing activities in the first three months of 2009 and 2008 primarily reflect a reduction of $5.0 in borrowings in each of those periods under our $75.0 million Credit Facility. The amount of borrowings under the Credit Facility is based on the Company's expectations of working capital requirements.

### Liquidity

The level of working capital for our construction business varies due to fluctuations in:

- customer receivables and contract retentions;
- costs and estimated earnings in excess of billings;
- billings in excess of costs and estimated earnings;
- the size and status of contract mobilization payments and progress billings;
- the amounts owed to suppliers and subcontractors.

Some of these fluctuations can be significant.

As of March 31, 2009, we had working capital of $98.9 million, an increase of $3.8 million over December 31, 2008. Working capital is an important element in expanding our bonding capacity, which enables us to bid on larger and longer duration projects. The increase in working capital was mainly the result of net income plus depreciation and deferred tax expense totaling $11.3 million reduced by purchases of property and equipment of $1.6 million and net repayment of debt of $5.0 million.

The Company believes that it has sufficient liquid financial resources, including the unused portion of its Credit Facility, to fund its requirements for the next twelve months of operations, including its bonding requirements, and expects no other material changes in its liquidity.

### Sources of Capital

In addition to our available cash and cash equivalents balances and cash provided by operations, we use borrowings under our Credit Facility with Comerica Bank to finance our capital expenditures and working capital needs.

In October 2007, we entered into a new Credit Facility with Comerica Bank which matures October 31, 2012. The Credit Facility allows for borrowings of up to $75.0 million and is secured by all assets of the Company, other than proceeds and other rights under our construction contracts which are pledged to our bond surety. At March 31, 2009, the aggregate borrowings outstanding under the Credit Facility were $50.0 million, and the aggregate amount of letters of credit outstanding under the Credit Facility was $1.8 million, which reduces availability under the Credit Facility. Availability under the Credit Facility was therefore $23.2 million at March 31, 2009.

The Credit Facility requires the payment of a quarterly commitment fee of 0.25% per annum of the unused portion of the Credit Facility. At our election, the loans under the Credit Facility bear interest at either a LIBOR-based interest rate or a prime-based interest rate. The average interest rate on funds borrowed under the Credit Facility during the three months ended March 31, 2009 was approximately 3.25%. The Credit Facility is subject to our compliance with certain covenants, including financial covenants at quarter-end relating to fixed charges, leverage, tangible net worth, asset coverage and consolidated net losses. We were in compliance with all of these covenants at March 31, 2009.

The financial markets have recently experienced substantial volatility as a result of disruptions in the credit markets. However, to date we have experienced no difficulty in borrowing under our Credit Facility and no change in its terms.

### Inflation

Until the first nine months of 2008, inflation had not had a material impact on our financial results; however, that year's increases in oil and fuel prices affected our cost of operations. Subsequent to September 30, 2008, the prices we have paid for oil and fuel have decreased. Anticipated cost increases and reductions are considered in our bids to customers on proposed new construction projects.

Where we are the successful bidder on a project, we execute purchase orders with material suppliers and contracts with subcontractors covering the prices of most materials and services, other than oil and fuel products, thereby mitigating future price increases and supply disruptions. These purchase orders and contracts do not contain quantity guarantees and we have no obligation for materials and services beyond those required to complete the contracts with our customers. There can be no assurance that oil and fuel used in our business will be adequately covered by the estimated escalation we have included in our bids or that all of our vendors will fulfill their pricing and supply commitments under their purchase orders and contracts with the Company. We adjust our total estimated costs on our projects where we believe it is probable that we will have cost increases which will not be recovered from customers, vendors or re-engineering.

### Our Markets

We operate in the heavy civil construction segment for infrastructure projects in Texas and Nevada, specializing in transportation and water infrastructure. RHB Cal has bid on construction projects in California, but has not been awarded any such projects.

Demand for transportation and water infrastructure depends on a variety of factors, including overall population growth, economic expansion and the vitality of the market areas in which we operate, as well as unique local topographical, structural and environmental issues. In addition to these factors, demand for the replacement of infrastructure is driven by the general aging of infrastructure and the need for technical improvements to achieve more efficient or safer use of infrastructure and resources. Funding for this infrastructure depends on federal, state and local authorizations.

According to the 2006 census, Texas is the second largest state in population in the U.S. with 23.5 million people and a population growth of 12.7% since 2000, almost double the 6.4% growth rate for the U.S. as a whole over the same period. Three of the 10 largest cities in the U.S. are located in Texas and we have operating divisions in each of those cities: Houston, Dallas/Ft. Worth and San Antonio. Nevada has undergone even more rapid growth, with the state’s population expanding 24.9% since 2000 to 2.5 million people in 2006.

Our highway and bridge work is generally funded through federal and state authorizations. The federal government enacted the SAFETEA-LU bill in 2005, which authorized $286 billion for transportation spending through 2009. Of this total, the Texas Department of Transportation (“TXDOT”) and the Nevada Department of Transportation (“NDOT”) were originally allocated approximately $14.5 billion and $1.3 billion, respectively, over the five years of the authorization. Actual SAFETEA-LU appropriations have been somewhat reduced from the original allocations. The USDOT proposed budget under SAFETEA-LU for the Federal-Aid Highways Program requests $39.4 billion of federal financial assistance to the States for 2009 versus actual appropriations of $41.2 billion for 2008 and $38.0 billion for 2007. A successor federal funding program has not yet been passed by Congress; however, the President's proposed budget for 2010 includes $72.5 billion for the U.S. Department of Transportation which would include funding to the States for highway and bridge construction.

On February 17, 2009 the American Recovery and Reinvestment Act ("economic-stimulus legislation") was enacted by the federal government that authorizes $26.7 billion for highway and bridge construction. A significant portion of these funds will be used for ready-to-go, quick spending highway projects for which contracts can be awarded quickly. States are required, subject to certain exceptions, to obligate 50 percent of the apportionment within 120 days of the date of apportionment or lose the funds not obligated in that period of time. States would be further required to obligate the second 50 percent of their apportionment within one year of the initial apportionment. The highway funds apportioned to Texas and Nevada approximated $2.3 billion and $0.2 billion, respectively.

In January, 2009, the 2030 Committee, appointed by TXDOT at the request of the Governor of the State of Texas, submitted its draft report of the transportation needs of Texas. The report indicated that the population of Texas is projected to grow at close to twice the U.S. rate with the population of Texas growing from 23.5 million in 2006 to between 30.5 million and 40.5 million in 2030. The report stated that "With this population increase expected by 2030, transportation modes, costs and congestion are considered a possible roadblock to Texas' projected growth and prosperity."

The report further indicated that Texas needs to spend approximately $313.0 billion (in 2008 dollars) over the 22 year period from 2009 through 2030 to prevent worsening congestion and maintain economic competitiveness on its urban highways and roads, improve congestion/safety and partial connectivity on its rural highways and bridge replacement.

While TXDOT officials have indicated potential short-term funding shortfalls and reductions in spending on transportation, the TXDOT budget for 2009 for transportation construction projects is $3.5 billion, including stimulus funds, versus estimated expenditures of $2.1 billion in 2008 and actual expenditures of $2.7 billion in 2007.

The Texas Senate has passed legislation that would fund $8.1 billion for highway and bridge construction in the 2010-11 biennium and the Texas House Committee substitute bill for the Senate legislation includes $6.1 billion ($4.0 billion in 2010 and $2.1 billion in 2011) for such construction in the 2010-11 biennium. TXDOT had requested approximately $7.2 billion ($4.5 billion in 2010 and $2.7 billion in 2011), including stimulus funds, for such construction in the biennium. The Senate and House bills must be negotiated, submitted to both chambers for final approval and signed into law by the Governor before such legislation becomes effective.

Additionally, the House legislation permits TXDOT to expend during the 2010-11 biennium the proceeds of the $5.0 billion Proposition 12 General Obligation Bonds approved by the voters of the State of Texas in November 2007 if TXDOT meets certain conditions set out in the legislation, including the written approval of the Legislative Budget Board and the Governor.

NDOT transportation construction expenditures totaled $449.2 million in 2006 and $455.5 million in 2007. NDOT’s budget for 2008 and 2009 includes $355.0 million and $420.9 million for transportation capital expenditures, respectively. Projections by NDOT for 2010 and 2011 transportation capital expenditures are $400 million each year. NDOT has stated that Nevada’s highway system needs are expected to be $11 billion by 2015; however, it has also stated that Nevada is currently facing a $3.8 billion shortfall (in 2006 dollars) for the 10 largest projects planned for completion in 2015.

In summary, aggregate contract lettings, including stimulus funds, would be $3.5 billion in 2009 and $4.0 billion in 2010 in Texas based on the lower proposed appropriations of the Texas House and $521 million in 2009 and $500 million in 2010 in Nevada, based on the currently proposed NDOT budgets and strategic plans. The amounts for Texas are before any funds that may be spent from the Texas General Obligation Bond approved by the voters in 2007.

In Texas, substantial funds for transportation infrastructure spending are also being provided by toll road and regional mobility authorities for the construction of toll roads.

Our water and wastewater, underground utility, light-rail transit and non-highway paving work is generally funded by municipalities and other local authorities. While the size and growth rates of these markets is difficult to compute as a whole, given the number of municipalities, the differences in funding sources and variations in local budgets, management estimates that the municipal markets in which we operate are providing funding in excess of $1 billion annually. Two of the many municipalities that we perform work for are discussed below:

The City of Houston estimated expenditures for 2008 on storm drainage, street and traffic, waste water and water capital improvements were $721 million.

The most recently adopted five-year plan includes $612 million in 2009, $557 million in 2010 and $504 million in 2011 for such improvements and projects; however, prior to the recent enactment of the federal government's economic-stimulus legislation, the Mayor of the City of Houston indicated he would defer $200 million of the 2009 improvements to future years.

The City of San Antonio has adopted a six-year capital improvement plan for 2009 through 2014, which includes $415 million for streets ($124 million in 2009) and $228 million for drainage ($103 million in 2009). The expenditures will be partially funded by the $550 million bond program that the voters of the City of San Antonio approved in May 2007. Included in those bonds was $307 million for streets, bridges and sidewalks improvements and $152 million for drainage improvements to be built over the period 2007 through 2012.

We also do work for other cities, counties, business area redevelopment authorities and regional authorities in Texas which have substantial water and transportation infrastructure spending budgets.

In addition, while we currently have no municipal contracts in the City of Las Vegas, that City’s capital improvement plan proposes expenditures for public works of $807 million for the years 2009 through 2013, including $311 million in 2009. The City Council of Las Vegas recently directed the city staff to delay capital improvement projects that will require additional staffing for one to two years which may cause significant deferrals of construction projects. However, management believes there will be opportunities for the Company to bid on and obtain municipal work in Las Vegas as well as Reno and Carson City.

While our business does not include residential and commercial infrastructure work, the severe fall-off in new projects in those markets in Nevada and to a lesser extent in Texas, has caused a softer bidding climate in our infrastructure markets and has caused some residential and commercial infrastructure contractors to bid on public sector transportation and water infrastructure projects, thus increasing competition and creating downward pressure on bid prices in our markets. These and other factors could adversely affect our ability to maintain or increase our backlog through successful bids for new projects and could adversely affect the profitability of new projects that we do obtain through successful bids.

Recent reductions in miles driven in the U.S. and more fuel efficient vehicles are reducing the amount of federal and state gasoline taxes and tolls collected. Additionally, the current credit crisis may limit the amount of state and local bonds that can be sold at reasonable terms. Further, the nationwide decline in home sales, the increase in foreclosures and a prolonged recession may result in decreases in user fees and property and sales taxes. These and other factors could adversely affect transportation and water infrastructure capital expenditures in our markets.

Due to increased competition the Company has submitted some of its more recent bids at margins that are lower than bids submitted in the latter half of 2008. The resulting lower margin jobs may affect gross margins recognized in the financial statements for several quarters subsequent to March 31, 2009. Assuming TXDOT moves forward in 2009 with its planned level of spending, we expect to have bidding opportunities that could allow our gross profit margins to return to historic levels.

While the bidding climate varies by locality, we continue to bid projects that fit our expertise and current criteria for potential revenues and gross margins after giving consideration to resource utilization, degree of difficulty in the projects, amount of subcontracts and materials and project competition. Our markets are softer and more competitive in the current economic climate. Management believes that the Company has the resources and experience to continue to compete successfully for projects as they become available.

## Market risk

As filed, 1,630 characters.

Changes in interest rates are one of our sources of market risks. At March 31, 2009, $50 million of our outstanding indebtedness was at floating interest rates. Based on our average debt outstanding during 2009, we estimate that an increase of 1.0% in the interest rate would have resulted in an increase in our interest expense of approximately $1,000 in the first quarter of 2009.

To manage risks of changes in material prices and subcontracting costs used in tendering bids for construction contracts, we obtain firm price quotations from our suppliers, except for fuel, and subcontractors before submitting a bid. These quotations do not include any quantity guarantees, and we have no obligation for materials or subcontract services beyond those required to complete the respective contracts that we are awarded for which quotations have been provided.

During 2009, we commenced a strategy of investing in certain securities, the assets of which are a crude oil commodity pool. We believe that the gains and losses on these securities will tend to offset increases and decreases in the price we pay for diesel and gasoline fuel and reduce the volatility of such fuel costs in our operations. At March 31, 2009, he Company has invested $2.4 million in such securities which had a quoted market value of $2.3 million. While the Company had an unrealized loss of $0.1 million on these securities for the first quarter of 2009, the price of diesel fuel and gasoline also declined during that period. The Company will continue to evaluate this strategy, however, there can be no assurance that this strategy will be successful.

## Controls and procedures

As filed, 2,102 characters.

### Evaluation of Disclosure Controls and Procedures

Disclosure controls and procedures include, without limitation, controls and procedures designed to ensure that information required to be disclosed by an issuer in the reports that it files or submits under the Securities and Exchange Act of 1934 is accumulated and communicated to the issuer’s management, including the principal executive and principal financial officers, or persons performing similar functions, as appropriate to allow timely decisions regarding required disclosure.

The Company’s principal executive officer and principal financial officer reviewed and evaluated the Company’s disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934). Based on that evaluation, the Company’s principal executive officer and principal financial officer concluded that the Company’s disclosure controls and procedures were effective at March 31, 2009 to ensure that the information required to be disclosed by the Company in this Quarterly Report on Form 10-Q is recorded, processed, summarized and reported within the time periods specified in the Securities and Exchange Commission’s rules and forms and is accumulated and communicated to the Company's management including the principal executive and principal financial officer as appropriate to allow timely decisions regarding required disclosure.

### Changes in Internal Control over Financial Reporting

There were no changes during the three months ended March 31, 2009 that have materially affected, or are reasonably likely to materially affect the Company’s internal controls over financial reporting.

### Inherent Limitations on Effectiveness of Controls

Internal controls over financial reporting may not prevent or detect all errors and all fraud. Also, projections of any evaluation of effectiveness of internal controls to future periods are subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate.

## Risk factors

As filed, 176 characters.

There have not been any material changes from the risk factors previously disclosed in Item 1A of the Company’s Annual Report on Form 10-K for the year ended December 31, 2008.

Filed May 11, 2009.
Source: SEC EDGAR, the filing index for accession 0000874238-09-000013. Last ingested by Listed: Nov 5, 2026, 14:02 ET. No prices; not investment advice.