## Figures reported in this filing

Standardized XBRL line items for the period ended 2022-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2022-07-01 to 2022-09-30 | CAD 5.35bn | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Revenue | 9 months, 2022-01-01 to 2022-09-30 | CAD 17.01bn | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Cost of revenue | 3 months, 2022-07-01 to 2022-09-30 | CAD 6.63bn | us-gaap:CostOfRevenue |
| Cost of revenue | 9 months, 2022-01-01 to 2022-09-30 | CAD 25.01bn | us-gaap:CostOfRevenue |
| Operating income | 3 months, 2022-07-01 to 2022-09-30 | CAD 1.78bn | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2022-01-01 to 2022-09-30 | CAD 5.72bn | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2022-07-01 to 2022-09-30 | CAD 806.0m | us-gaap:InterestExpense |
| Interest expense | 9 months, 2022-01-01 to 2022-09-30 | CAD 2.32bn | us-gaap:InterestExpense |
| Income tax | 3 months, 2022-07-01 to 2022-09-30 | CAD 318.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2022-01-01 to 2022-09-30 | CAD 1.04bn | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2022-07-01 to 2022-09-30 | CAD 1.36bn | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2022-01-01 to 2022-09-30 | CAD 3.99bn | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2022-07-01 to 2022-09-30 | CAD 0.63 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2022-01-01 to 2022-09-30 | CAD 1.80 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2022-07-01 to 2022-09-30 | CAD 0.63 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2022-01-01 to 2022-09-30 | CAD 1.80 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2022-07-01 to 2022-09-30 | 2,028,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2022-01-01 to 2022-09-30 | 2,029,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2022-01-01 to 2022-09-30 | CAD 7.62bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2022-01-01 to 2022-09-30 | CAD 3.20bn | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2022-01-01 to 2022-09-30 | CAD 5.23bn | us-gaap:PaymentsOfDividendsCommonStock |
| Share repurchases | 9 months, 2022-01-01 to 2022-09-30 | CAD 151.0m | us-gaap:PaymentsForRepurchaseOfCommonStock |
| Cash and equivalents | at 2022-09-30 | CAD 1.02bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2022-09-30 | CAD 10.81bn | us-gaap:AssetsCurrent |
| Total assets | at 2022-09-30 | CAD 181.78bn | us-gaap:Assets |
| Current liabilities | at 2022-09-30 | CAD 17.91bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2022-09-30 | CAD 114.34bn | us-gaap:Liabilities |
| Short-term borrowings | at 2022-09-30 | CAD 1.88bn | us-gaap:ShortTermBorrowings |
| Shareholders' equity | at 2022-09-30 | CAD 64.83bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 70,667 characters.

### INTRODUCTION

The following discussion and analysis of our financial condition and results of operations is based on and should be read in conjunction with our interim consolidated financial statements and the accompanying notes included in Part I. *Item 1. Financial Statements* of this quarterly report on Form 10-Q and our consolidated financial statements and the accompanying notes included in Part II. *Item 8. Financial Statements and Supplementary Data* of our annual report on Form 10-K for the year ended December 31, 2021.

We continue to qualify as a foreign private issuer for purposes of the United States Securities Exchange Act of 1934, as amended (Exchange Act), as determined annually as of the end of our second fiscal quarter. We intend to continue to file annual reports on Form 10-K, quarterly reports on Form 10-Q and current reports on Form 8-K with the United States (US) Securities and Exchange Commission (SEC) instead of filing the reporting forms available to foreign private issuers. We also intend to maintain our Form S-3 registration statements.

### RECENT DEVELOPMENTS

### Joint Venture Merger Transaction to Advance US Gulf Coast Oil Strategy

On August 17, 2022, we completed a joint venture merger transaction with Phillips 66 (P66) resulting in a single joint venture, DCP Midstream LLC, holding both Enbridge Inc.'s (Enbridge) and P66's indirect ownership interests in Gray Oak Pipeline, LLC (Gray Oak) and DCP Midstream, LP (DCP), as well as an agreement to realign our respective economic and governance interests in the underlying business operations. Our indirect economic interest in Gray Oak has increased to 58.5% from 22.8% and we will assume operatorship of Gray Oak in the second quarter of 2023. Simultaneously, our indirect economic interest in DCP has been reduced to 13.2% from 28.3%. We received approximately $522 million (US$404 million) in cash proceeds and recorded an accounting gain of $1.1 billion (US$832 million) on the Consolidated Statements of Earnings as a result of the transaction.

### Acquisition of Tri Global Energy LLC

On September 27, 2022, we acquired Tri Global Energy LLC (TGE), a leading US renewable power project developer, for approximately US$270 million in cash and assumed debt. The acquisition of TGE enhances our renewable power platform and further builds on our inventory of North American growth opportunities.

### Athabasca Indigenous Investments Partnership

On October 5, 2022, we completed a transaction with Athabasca Indigenous Investments Limited Partnership (Aii), a newly created entity representing 23 First Nation and Métis communities, pursuant to which Aii acquired an 11.6% non-operating interest in seven Regional Oil Sands pipelines in northern Alberta for $1.1 billion.

### CEO Transition

On October 3, 2022, we announced Al Monaco's retirement as President and Chief Executive Officer and from our Board of Directors effective January 1, 2023. Concurrent with this announcement, the Board of Directors appointed Greg Ebel, currently Chair of our Board of Directors, to succeed Mr. Monaco as President and Chief Executive Officer. Mr. Ebel will also continue as a member of the Board of Directors. A new independent Board Chair will be named prior to January 1, 2023. To support Mr. Ebel through the transition, Mr. Monaco will serve as an advisor to March 1, 2023.

### GAS TRANSMISSION AND MIDSTREAM RATE PROCEEDINGS

### Texas Eastern Transmission

Texas Eastern Transmission, LP (Texas Eastern) filed two rate cases in the third quarter of 2021. These two rate proceedings have since been consolidated and settlement negotiations began during the first quarter of 2022. An uncontested settlement in principle was reached on July 7, 2022. Texas Eastern filed an uncontested Stipulation and Agreement on September 8, 2022 to resolve all issues from the rate proceeding. The comment and reply period ended October 11, 2022 and the Stipulation and Agreement is now with the Federal Energy Regulatory Commission for approval.

### Maritimes & Northeast Pipeline

In December 2021, the Canada Energy Regulator (CER) approved interim rates for the Canadian portion of Maritimes & Northeast (M&N) Pipeline effective January 1, 2022, which were based on the negotiated 2022 rates in the 2022-2023 settlement agreement and unanimously supported by shippers. The 2022-2023 M&N Canada settlement agreement was approved by the CER in February 2022.

### British Columbia Pipeline

The settlement agreement for our British Columbia Pipeline (BC Pipeline) System expired in December 2021. The CER has approved 2022 interim tolls for BC Pipeline effective January 1, 2022. In August 2022, an agreement in principle was reached with BC Pipeline shippers on a 2022-2026 rate settlement, and we expect a settlement agreement to be executed with shippers and filed with the CER in the fourth quarter of 2022.

### GAS DISTRIBUTION AND STORAGE RATE APPLICATIONS

### 2022 Rate Application

In June 2021, Enbridge Gas Inc. (Enbridge Gas) filed Phase 1 of the application with the Ontario Energy Board (OEB) for the setting of rates for 2022 (the 2022 Application). The 2022 Application was filed in accordance with the parameters of Enbridge Gas' OEB approved Price Cap Incentive Regulation (IR) rate setting mechanism and represents the fourth year of a five-year term. In October 2021, the OEB approved a Phase 1 Settlement Proposal and Interim Rate Order effective January 1, 2022. In April 2022, the OEB issued its decision on Phase 2 of the 2022 Application filed in October 2021, addressing incremental capital module (ICM) funding requirements, under which $127 million of Enbridge Gas' requested capital funding was approved and incorporated into final rates, effective July 1, 2022.

### 2023 Rate Application

In June 2022, Enbridge Gas filed Phase 1 of the application with the OEB for the setting of rates for 2023 (the 2023 Application). The 2023 Application was filed in accordance with the parameters of Enbridge Gas' approved Price Cap IR rate setting mechanism and represents the final year of a five-year term. In November 2022, the OEB approved the Phase 1 Settlement Proposal and Interim Rate Order effective January 1, 2023. In addition, Enbridge Gas does not anticipate 2023 capital investments to require incremental funding during the final year of its current Price Cap IR term, and as such Enbridge Gas will not be making a Phase 2 ICM request as part of the 2023 Application.

### Incentive Regulation Rate Application

In October 2022, Enbridge Gas filed its application to establish a 2024 through 2028 IR rate setting framework. The application and framework seeks approval to establish 2024 base rates on a cost of service basis and to establish a price cap rate setting mechanism to be used for the remainder of the IR term (2025 – 2028). An OEB decision is expected on the application in the second half of 2023.

### Purchase Gas Variance

The Purchase Gas Variance Account (PGVA) captures the difference between actual and forecasted natural gas prices reflected in rates. Account balances are typically recovered or refunded over a prospective 12-month period through Quarterly Rate Adjustment Mechanism (QRAM) applications.

In March and June 2022, the OEB approved Enbridge Gas' April 1, 2022 and July 1, 2022 QRAM applications, respectively. Due to the significant increase in natural gas prices, the approvals have also included rate mitigation plans intended to ease bill impacts to ratepayers. Specifically, the approved rate mitigation plans extended the PGVA recovery period from 12 months to 24 months in both applications. As an additional mitigation measure, as part of the April 1, 2022 QRAM, a portion of the PGVA balance was deferred for recovery, which was subsequently approved for recovery as part of the July 1, 2022 QRAM. The October 1, 2022 QRAM application was filed and approved by the OEB with no adjustments to the prior period rate mitigation plans and it did not include any additional rate mitigation measures.

As at September 30, 2022, Enbridge Gas' PGVA balance was $693 million.

### FINANCING UPDATE

On January 19, 2022, we closed a $750 million private placement of non-call 10-year fixed-to-fixed subordinated notes which mature on January 19, 2082. The net proceeds from the offering were used to redeem Preference Shares, Series 17 at par on March 1, 2022.

On February 17, 2022, we closed a three tranche offering of aggregate US$1.5 billion senior notes consisting of US$600 million two-year floating rate notes, US$400 million two-year notes and US$500 million three-year notes. Each tranche is payable semi-annually in arrears and matures on February 16, 2024, February 16, 2024 and February 14, 2025, respectively.

On May 17, 2022, we entered into a three year term loan with a syndicate of Japanese banks for approximately $806 million (¥84.8 billion), which will mature in May 2025 and replaces the approximately $499 million (¥52.5 billion) term loan that matured in May 2022. Additionally, on May 24, 2022, we entered into a 364-day term loan for approximately $1.9 billion, which will mature in May 2023.

In July and August 2022, we increased our credit facilities by approximately $641 million.

On August 17, 2022, Enbridge Gas closed a $650 million dual-tranche medium-term note offering in the Canadian debt capital markets, split evenly across a 10-year tranche and a 30-year tranche, payable semi-annually in arrears due August 17, 2032 and August 17, 2052, respectively.

On September 20, 2022, we closed a US$1.1 billion dual-tranche hybrid note offering consisting of 60-year non-call 5-year fixed-to-fixed subordinated notes and 60-year non-call 10-year fixed-to-fixed subordinated notes, both of which mature on January 15, 2083.

These financing activities, in combination with the financing activities executed in 2021, provide significant liquidity that we expect will enable us to fund our current portfolio of capital projects without requiring access to the capital markets for the next 12 months should market access be restricted or pricing be unattractive. Refer to *Liquidity and Capital Resources.*

As at September 30, 2022, after adjusting for the impact of floating-to-fixed interest rate swap hedges, approximately 10% of our total debt is exposed to floating rates. Refer to Part I. *Item I. Financial Statements - Note 9. Risk Management and Financial Instruments* for more information on our interest rate hedging program.

### RESULTS OF OPERATIONS

| (millions of Canadian dollars) Segment earnings/(loss) before interest, income taxes and depreciation and amortization1 | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Liquids Pipelines | **1,946** | 1,673 | **6,093** | 5,756 |
| Gas Transmission and Midstream | **2,251** | 884 | **4,384** | 2,725 |
| Gas Distribution and Storage | **286** | 282 | **1,368** | 1,374 |
| Renewable Power Generation | **105** | 91 | **389** | 362 |
| Energy Services | **(70)** | (204) | **(348)** | (379) |
| Eliminations and Other | **(935)** | (121) | **(1,284)** | 191 |
| **Earnings before interest, income taxes and depreciation and amortization1** | **3,583** | 2,605 | **10,602** | 10,029 |
| Depreciation and amortization | **(1,076)** | (944) | **(3,195)** | (2,805) |
| Interest expense | **(806)** | (648) | **(2,316)** | (1,923) |
| Income tax expense | **(318)** | (199) | **(1,044)** | (952) |
| Earnings attributable to noncontrolling interests | **(21)** | (34) | **(61)** | (93) |
| Preference share dividends | **(83)** | (98) | **(330)** | (280) |
| **Earnings attributable to common shareholders** | **1,279** | 682 | **3,656** | 3,976 |
| Earnings per common share attributable to common shareholders | **0.63** | 0.34 | **1.80** | 1.97 |
| Diluted earnings per common share attributable to common shareholders | **0.63** | 0.34 | **1.80** | 1.96 |

*1Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

### EARNINGS ATTRIBUTABLE TO COMMON SHAREHOLDERS

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

Earnings attributable to common shareholders were positively impacted by $415 million due to certain infrequent or other non-operating factors, primarily explained by the following:

- a gain of $1,076 million ($732 million after-tax) on the closing of the joint venture merger transaction with P66 realigning our indirect economic interests in Gray Oak and DCP;
- a deferred tax benefit of $95 million recognized in the quarter as a result of the reduced Pennsylvania state corporate income tax;
- the absence of the $111 million ($83 million after-tax) impairment loss in 2021 to our investment in the PennEast Pipeline Company, LLC (PennEast) pipeline project after a decision by project partners to cease development;
- a net positive adjustment of $85 million ($75 million after-tax) due to the release of reserves associated with our enterprise insurance strategy; and
- non-cash, unrealized gains of $58 million ($44 million after-tax) in 2022, compared with unrealized losses of $88 million ($67 million after-tax) in 2021, reflecting the revaluation of derivatives used to manage the profitability of transportation and storage transactions, as well as manage the exposure to movements in commodity prices; partially offset by
- non-cash, net unrealized derivative fair value losses of $1,334 million ($1,021 million after-tax) in 2022, compared with unrealized losses of $436 million ($332 million after-tax) in 2021, reflecting changes in the mark-to-market value of derivative financial instruments used to manage foreign exchange risks.

The non-cash, unrealized derivative fair value gains and losses discussed above generally arise as a result of our comprehensive economic hedging program to mitigate foreign exchange and commodity price risks. This program creates volatility in reported short-term earnings through the recognition of unrealized non-cash gains and losses on derivative instruments used to hedge these risks. Over the long-term, we believe our hedging program supports the reliable cash flows and dividend growth upon which our investor value proposition is based.

After taking into consideration the factors above, the remaining $182 million increase in earnings attributable to common shareholders is primarily explained by:

- higher throughput within our Liquids Pipelines segment driven by higher demand and incremental Line 3 Replacement (L3R) capacity that came into service October 2021;
- increased earnings within our Liquids Pipelines segment from the implementation of the full L3R surcharge when compared to the lower surcharge on the Canadian portion of the project in effect prior to October 2021, as well as from new export assets acquired in October 2021;
- increased earnings from our Gas Transmission and Midstream segment primarily as a result of higher commodity prices benefiting our investments in DCP and Aux Sable Midstream LLC (Aux Sable), as well as higher contributions from projects placed into service in November 2021; and
- recognition of revenues attributable to the Texas Eastern rate case resulting from an uncontested Stipulation and Agreement; partially offset by
- higher interest expense primarily due to reduced capitalized interest associated with the US portion of the L3R Project placed into service in the fourth quarter of 2021, as well as higher average principal and higher interest rates; and
- higher depreciation and amortization expense as a result of several projects placed into service in the fourth quarter of 2021, as well as for new export assets acquired in October 2021.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

Earnings attributable to common shareholders were negatively impacted by $566 million due to certain infrequent or other non-operating factors, primarily explained by the following:

- non-cash, net unrealized derivative fair value losses of $1,751 million ($1,340 million after-tax) in 2022, compared with unrealized gains of $85 million ($65 million after-tax) in 2021, reflecting changes in the mark-to-market value of derivative financial instruments used to manage foreign exchange risks;
- a net negative adjustment to crude oil and natural gas inventories in our Energy Services business segment of $67 million ($50 million after-tax);
- the absence in 2022 of a $57 million ($43 million after-tax) property tax settlement received in 2021 related to the resolution of Minnesota property tax appeals for 2012-2018;
- an impairment of $44 million ($34 million after-tax) for lease assets due to office relocation plans; and
- an asset impairment loss of $40 million ($30 million after-tax) relating to MacKay River line within our Alberta Regional Oil Sands System; partially offset by
- a gain of $1,076 million ($732 million after-tax) on the closing of the joint venture merger transaction with P66 realigning our indirect economic interests in Gray Oak and DCP;
- a deferred tax benefit of $95 million recognized in the quarter as a result of the reduced Pennsylvania state corporate income tax;
- non-cash, unrealized gains of $22 million ($17 million after-tax) in 2022, compared with unrealized losses of $102 million ($78 million after-tax) in 2021, reflecting the revaluation of derivatives used to manage the profitability of transportation and storage transactions, as well as manage the exposure to movements in commodity prices; and
- a non-cash, net negative equity earnings adjustment of $30 million ($22 million after-tax) in 2022, compared to a net negative adjustment of $104 million ($79 million after-tax) in 2021 relating to our share of changes in the mark-to-market value of derivative financial instruments of our equity method investees, DCP and Aux Sable.

After taking into consideration the factors above, the remaining $246 million increase in earnings attributable to common shareholders is primarily explained by the following significant business factors:

- higher throughput within our Liquids Pipelines segment driven by higher demand and incremental L3R capacity that came into service October 2021;
- increased earnings within our Liquids Pipelines segment from the implementation of the full L3R surcharge when compared to the lower surcharge on the Canadian portion of the project in effect prior to October 2021, as well as from new export assets acquired in October 2021;
- increased earnings from our Gas Transmission and Midstream segment primarily as a result of higher commodity prices benefiting our investments in DCP and Aux Sable, as well as higher contributions from projects placed into service in November 2021; and
- recognition of revenues attributable to the Texas Eastern rate case resulting from an uncontested Stipulation and Agreement; partially offset by
- the recognition of a provision against the interim Mainline International Joint Tariff (IJT) for barrels shipped in 2022;
- higher interest expense primarily due to higher average principal and higher interest rates, as well as reduced capitalized interest associated with the US portion of the L3R Project placed into service in the fourth quarter of 2021; and
- higher depreciation and amortization expense as a result of several projects placed into service in the fourth quarter of 2021, as well as for new export assets acquired in October 2021.

### BUSINESS SEGMENTS

### LIQUIDS PIPELINES

| (millions of Canadian dollars) | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Earnings before interest, income taxes and depreciation and amortization1 | **1,946** | 1,673 | **6,093** | 5,756 |

*1Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

EBITDA was negatively impacted by $98 million due to certain infrequent or other non-operating factors, primarily explained by non-cash, net unrealized losses of $290 million in 2022, compared with unrealized losses of $222 million in 2021, reflecting net fair value gains and losses arising from changes in the mark-to-market value of derivative financial instruments used to manage foreign exchange risks.

After taking into consideration the factors above, the remaining $371 million increase is primarily explained by the following significant business factors:

- higher Mainline System ex-Gretna average throughput of 3.0 million barrels per day (mmbpd) in 2022 as compared to 2.7 mmbpd in 2021 driven by higher demand and incremental L3R capacity that came into service October 2021;
- implementation of the full L3R surcharge when compared to the lower surcharge on the Canadian portion of the project in effect prior to October 2021;
- higher contributions from the Gulf Coast and Mid-Continent System due primarily to the acquisition of the Enbridge Ingleside Energy Center (EIEC) and related assets in the fourth quarter of 2021, as well as higher volumes from our Flanagan South Pipeline (FSP), and increased indirect economic interest in the Gray Oak pipeline during the third quarter of 2022;
- higher contributions from the Bakken System due to higher volumes; and
- the favorable effect of translating US dollar EBITDA at a higher average exchange rate in 2022 compared to the same period in 2021; partially offset by
- the recognition of a provision against the interim Mainline IJT for barrels shipped in 2022;
- lower contributions from the Seaway Crude Pipeline System, as well as from the Cushing and Hardisty storage assets as a result of lower demand; and
- higher power costs as a result of increased volumes and power prices.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

EBITDA was negatively impacted by $621 million due to certain infrequent or other non-operating factors, primarily explained by the following:

- non-cash, net unrealized losses of $364 million in 2022, compared with unrealized gains of $84 million in 2021, reflecting net fair value gains and losses arising from changes in the mark-to-market value of derivative financial instruments used to manage foreign exchange risks;
- an asset impairment loss of $40 million relating to MacKay River line within our Alberta Regional Oil Sands System; and
- the absence in 2022 of a $57 million property tax settlement received in 2021 related to the resolution of Minnesota property tax appeals for 2012-2018.

After taking into consideration the factors above, the remaining $958 million increase is primarily explained by the following significant business factors:

- higher Mainline System ex-Gretna average throughput of 2.9 mmbpd in 2022 as compared to 2.7 mmbpd in 2021 driven by higher demand and incremental L3R capacity that came into service October 2021;
- implementation of the full L3R surcharge when compared to the lower surcharge on the Canadian portion of the project in effect prior to October 2021;
- higher contributions from the Gulf Coast and Mid-Continent System due primarily to the acquisition of the EIEC and related assets in the fourth quarter of 2021, as well as higher volumes from FSP, and increased indirect economic interest in the Gray Oak pipeline during the third quarter of 2022;
- higher contributions from the Bakken System due to higher volumes; and
- the favorable effect of translating US dollar EBITDA at a higher average exchange rate in 2022 compared to the same period in 2021; partially offset by
- the recognition of a provision against the interim Mainline IJT for barrels shipped in 2022;
- lower contributions from the Seaway Crude Pipeline System, as well as from the Cushing and Hardisty storage assets as a result of lower demand; and
- higher power costs as a result of increased volumes and power prices.

### GAS TRANSMISSION AND MIDSTREAM

| (millions of Canadian dollars) | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Earnings before interest, income taxes and depreciation and amortization1 | **2,251** | 884 | **4,384** | 2,725 |

*1Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

EBITDA was positively impacted by $1,195 million due to certain infrequent or other non-operating factors, primarily explained by the following:

- a gain of $1,076 million on the closing of the joint venture merger transaction with P66 realigning our indirect economic interests in Gray Oak and DCP; and
- the absence of the $111 million impairment loss in 2021 to our investment in the PennEast pipeline project after a decision by project partners to cease development.

The remaining $172 million increase is primarily explained by the following significant business factors:

- contributions from the T-South and Spruce Ridge expansion projects after service commenced in November 2021;
- higher AECO-Chicago basis differential and lower costs benefiting earnings from our investment in Alliance Pipeline (Alliance);
- higher commodity prices benefiting our DCP and Aux Sable joint ventures;
- recognition of revenues attributable to the Texas Eastern rate case resulting from an uncontested Stipulation and Agreement;
- contributions from the Cameron Extension, Middlesex Extension, and the Appalachia to Market projects placed into service in the fourth quarter of 2021; and
- the favorable effect of translating US dollar EBITDA at a higher average exchange rate in 2022 compared to the same period in 2021; partially offset by
- a reduction in earnings from our investment in DCP as a result of our decreased interest due to the joint venture merger transaction with P66 that closed during the quarter.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

EBITDA was positively impacted by $1,287 million due to certain infrequent or other non-operating factors, primarily explained by the following:

- a gain of $1,076 million on the closing of the joint venture merger transaction with P66 realigning our indirect economic interests in Gray Oak and DCP;
- the absence of the $111 million impairment loss in 2021 to our investment in the PennEast pipeline project after a decision by project partners to cease development; and
- a non-cash, net negative equity earnings adjustment of $30 million in 2022, compared to a net negative adjustment of $104 million in 2021 relating to our share of changes in the mark-to-market value of derivative financial instruments of our equity method investees, DCP and Aux Sable.

The remaining $372 million increase is primarily explained by the following significant business factors:

- higher commodity prices benefiting our DCP and Aux Sable joint ventures;
- higher AECO-Chicago basis differential and lower costs benefiting earnings from our investment in Alliance;
- contributions from the T-South and Spruce Ridge expansion projects after service commenced in November 2021;
- recognition of revenues attributable to the Texas Eastern rate case resulting from an uncontested Stipulation and Agreement;
- contributions from the Cameron Extension, Middlesex Extension, and the Appalachia to Market projects placed into service in the fourth quarter of 2021; and
- the favorable effect of translating US dollar EBITDA at a higher average exchange rate in 2022 compared to the same period in 2021; partially offset by
- higher operating costs; and
- a reduction in earnings from our investment in DCP, as a result of our decreased interest due to the joint venture merger transaction with P66 that closed during the quarter.

### GAS DISTRIBUTION AND STORAGE

| (millions of Canadian dollars) | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Earnings before interest, income taxes and depreciation and amortization1 | **286** | 282 | **1,368** | 1,374 |

*1Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

EBITDA remained consistent year over year for the same three-month period due to higher distribution charges at Enbridge Gas, resulting from increases in rates and customer base, that were offset by higher operating and administrative costs related to higher maintenance and integrity spend, as well as timing of expenditures.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

EBITDA was negatively impacted by $6 million primarily explained by:

- the absence of earnings from Noverco Inc. due to the sale of our minority investment in December 2021; and
- higher operating costs at Enbridge Gas largely driven by higher maintenance and integrity spend, as well as the timing of expenditures; partially offset by
- higher distribution charges at Enbridge Gas resulting from increases in rates and customer base, as well as higher demand in the contract market; and
- when compared with the normal weather forecast embedded in rates, colder than normal weather in 2022 positively impacted Enbridge Gas 2022 EBITDA by approximately $28 million while warmer than normal weather in 2021 negatively impacted 2021 EBITDA by approximately $24 million.

### RENEWABLE POWER GENERATION

| (millions of Canadian dollars) | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Earnings before interest, income taxes and depreciation and amortization1 | **105** | 91 | **389** | 362 |

*1 Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

EBITDA was positively impacted by $14 million primarily due to higher energy pricing at European offshore wind facilities.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

EBITDA was positively impacted by $27 million primarily due to the following significant business factors:

- stronger wind resources at Canadian and US onshore wind facilities;
- higher energy pricing at European offshore wind facilities; and
- the absence in 2022 of the adverse effects from the major winter storm in Texas during February 2021; partially offset by
- the absence in 2022 of a promote fee received in the first quarter of 2021 associated with the closing of the sale of 49% of our interest in three European offshore wind projects to Canada Pension Plan Investment Board.

### ENERGY SERVICES

| (millions of Canadian dollars) | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Loss before interest, income taxes and depreciation and amortization1 | **(70)** | (204) | **(348)** | (379) |

*1Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

EBITDA from Energy Services is dependent on market conditions and results achieved in one period may not be indicative of results to be achieved in future periods.

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

EBITDA was positively impacted by $150 million due to certain non-operating factors, primarily explained by non-cash, unrealized gains of $58 million in 2022, compared with unrealized losses of $88 million in 2021, reflecting the revaluation of derivatives used to manage the profitability of transportation and storage transactions, as well as to manage the exposure to movements in commodity prices.

After taking into consideration the factor above, the remaining $16 million decrease is primarily explained by more pronounced market structure backwardation and significant compression of location differentials in certain markets as compared to the same period of 2021.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

EBITDA was positively impacted by $56 million due to certain non-operating factors, primarily explained by:

- non-cash, unrealized gains of $22 million in 2022, compared with unrealized losses of $102 million in 2021, reflecting the revaluation of derivatives used to manage the profitability of transportation and storage transactions, as well as manage the exposure to movements in commodity prices; partially offset by
- a net negative adjustment to crude oil and natural gas inventories of $67 million.

After taking into consideration the factors above, the remaining $25 million decrease is primarily explained by the following significant business factors:

- more pronounced market structure backwardation and significant compression of location differentials in certain markets as compared to the same period of 2021; partially offset by
- the absence in 2022 of adverse impacts from the major winter storm experienced across the US Midwest during February 2021.

### ELIMINATIONS AND OTHER

| (millions of Canadian dollars) | Three months ended September 30, 2022 | 2021 | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Earnings/(loss) before interest, income taxes and depreciation and amortization1 | **(935)** | (121) | **(1,284)** | 191 |

*1 Non-GAAP financial measure. Please refer to* Non-GAAP and Other Financial Measures.

Eliminations and Other includes operating and administrative costs and the impact of foreign exchange hedge settlements, which are not allocated to business segments. Eliminations and Other also includes the impact of new business development activities and corporate investments.

### Three months ended September 30, 2022, compared with the three months ended September 30, 2021

EBITDA was negatively impacted by $755 million due to certain infrequent or non-operating factors, primarily explained by:

- non-cash, net unrealized losses of $1,046 million in 2022, compared with unrealized losses of $214 million in 2021, reflecting the change in the mark-to-market value of derivative financial instruments used to manage foreign exchange risk; partially offset by
- a net positive adjustment of $85 million due to the release of reserves associated with our enterprise insurance strategy.

After taking into consideration the non-operating factors above, the remaining $59 million decrease is primarily explained by lower realized foreign exchange gains on hedge settlements in 2022, as well as the timing of certain operating and administrative cost recoveries from the business units.

### Nine months ended September 30, 2022, compared with the nine months ended September 30, 2021

EBITDA was negatively impacted by $1,446 million due to certain infrequent or non-operating factors, primarily explained by:

- non-cash, net unrealized losses of $1,393 million in 2022, compared with unrealized losses of $17 million in 2021, reflecting the change in the mark-to-market value of derivative financial instruments used to manage foreign exchange risk;
- an impairment of $44 million for lease assets due to office relocation plans in Houston; and
- a net negative expense of $15 million associated with our enterprise insurance strategy.

After taking into consideration the non-operating factors above, the remaining $29 million decrease is primarily explained by the timing of certain operating and administrative cost recoveries from the business units, partially offset by higher realized foreign exchange gains on hedge settlements in 2022.

### GROWTH PROJECTS - COMMERCIALLY SECURED PROJECTS

The following table summarizes the status of our significant commercially secured projects, organized by business segment:

| (Canadian dollars, unless stated otherwise) GAS TRANSMISSION AND MIDSTREAM |  | Enbridge's Ownership Interest | Estimated Capital Cost1 | Expenditures to Date2 | Status2 | Expected In-Service Date |
| --- | --- | ---: | --- | --- | --- | --- |
| 1. | Gulfstream Phase VI | 50% | US$0.1 billion | US$0.1 billion | Complete | In-service |
| 2. | Vito Gas & Oil | 100% | US$0.3 billion | US$0.2 billion | Under construction | 4Q - 2022 |
| 3. | Texas Eastern Venice Extension Project3 | 100% | US$0.4 billion | No significant expenditures to date | Pre-construction | 2023 - 2024 |
| 4. | Texas Eastern Modernization | 100% | US$0.4 billion | No significant expenditures to date | Pre-construction | 2024 - 2025 |
| 5. | Appalachia to Market II | 100% | US$0.1 billion | No significant expenditures to date | Pre-construction | 2025 |
| 6. | T-North Expansion | 100% | $1.2 billion | No significant expenditures to date | Pre-construction | 2026 |
| 7. | Woodfibre LNG4 | 30% | US$1.5 billion | No significant expenditures to date | Pre-construction | 2027 |
| 8. | T-South Expansion | 100% | $3.6 billion | No significant expenditures to date | Pre-construction | 2028 |
| **GAS DISTRIBUTION AND STORAGE** |  |  |  |  |  |  |
| 9. | Storage Enhancements5 | 100% | $0.1 billion | $0.1 billion | Under construction | 4Q - 2022 |
| 10. | System Enhancement Project | 100% | $0.1 billion | $0.1 billion | Under construction | 4Q - 2022 |
| 11. | Natural Gas Expansion Program6 | 100% | $0.1 billion | No significant expenditures to date | Pre-construction | 2022 - 2027 |
| 12. | Panhandle Regional Expansion | 100% | $0.3 billion | No significant expenditures to date | Pre-construction | 2023 - 2024 |
| **RENEWABLE POWER GENERATION** |  |  |  |  |  |  |
| 13. | East-West Tie Line | 25% | $0.2 billion | $0.2 billion | Complete | In-service |
| 14. | Saint-Nazaire France Offshore Wind Project7 | 25.5% | $0.9 billion | $0.7 billion | Under construction | 4Q - 2022 |
| (€0.6 billion) | (€0.5 billion) |  |  |  |  |  |
| 15. | Fécamp Offshore Wind Project8 | 17.9% | $0.7 billion | $0.3 billion | Under construction | 2023 |
| (€0.5 billion) | (€0.2 billion) |  |  |  |  |  |
| 16. | Provence Grand Large Floating Offshore Wind Project8 | 25% | $0.1 billion | $0.1 billion | Under construction | 2023 |
| (€0.1 billion) | (€0.1 billion) |  |  |  |  |  |
| 17. | Solar Self-Power Projects | 100% | US$0.2 billion | US$0.1 billion | Under construction | 2023 - 2024 |
| 18 | Calvados Offshore Wind Project7 | 21.7% | $0.9 billion | $0.3 billion | Under construction | 2025 |
| (€0.6 billion) | (€0.2 billion) |  |  |  |  |  |

*1These amounts are estimates and are subject to upward or downward adjustment based on various factors. Where appropriate, the amounts reflect our share of joint venture projects.*

*2Expenditures to date and status of the project are determined as at September 30, 2022.*

*3This includes the Gator Express Project with an estimated capital cost of $31 million.*

*4Our equity contribution is US $0.9 billion, with the remainder of the project financed through non-recourse project level debt.*

#### 5The Storage Enhancements project commenced service on October 4, 2022.

*6Represents Phase 2 of the Natural Gas Expansion Program and the estimated capital cost is presented net of the maximum funding assistance we expect to receive from the Government of Ontario. The expected in-service dates represent the expected completion dates of the leave to construct requirements.*

*7Our equity contribution is $0.2 billion for each project, with the remainder of each project financed through non-recourse project level debt.*

*8Our equity contribution is $0.1 billion for each project, with the remainder of each project financed through non-recourse project level debt.*

A full description of each of our projects is provided in our annual report on Form 10-K for the year ended December 31, 2021. Significant updates that have occurred since the date of filing of our Form 10-K are discussed below.

### GAS TRANSMISSION AND MIDSTREAM

- **Texas Eastern Venice Extension Project –** A reversal and expansion of Texas Eastern’s Line 40 from its existing New Roads compressor station to a new delivery point with the proposed Gator Express pipeline just south of Texas Eastern’s Larose compressor station. The project is expected to deliver 1.5 billion cubic feet per day (bcf/d) of natural gas to Venture Global Plaquemines LNG, LLC’s LNG export facility located in Plaquemines Parish, Louisiana and is underpinned by long-term take or pay contracts.
- **T-North Expansion –** An expansion of Westcoast Energy Inc.'s (WEI) BC Pipeline in northern BC that includes pipeline looping, additional compressor units and other ancillary station modifications to support 535 million cubic feet per day (MMcf/d) of additional capacity. The project will be underpinned by a cost-of-service commercial model with a target in-service date of 2026.
- **Woodfibre LNG –** Construction of liquefaction and floating storage facilities in Squamish, BC, as well as an expansion of the BC Pipeline System. The project is expected to be placed into service in 2027.
- **T-South Expansion –** An expansion of WEI's BC Pipeline's T-South section that includes pipeline looping, additional compressor units and other ancillary station modifications to support 300 MMcf/d of additional capacity. The project is expected to be placed in service in 2028 and will be underpinned by a cost-of-service commercial model.

### GAS DISTRIBUTION AND STORAGE

- **Panhandle Regional Expansion Project –** Expansion of the Panhandle Transmission System, which supplies natural gas from the Dawn Hub to customers in Southern Ontario west of Dawn. The project consists of construction on Panhandle Loop and Leamington interconnect, and is expected to receive a full cost-of-service regulated return upon OEB approval with target in-service dates of November 2023 and November 2024.
- **System Enhancement Project –** On May 3, 2022, the OEB issued a Decision and Order denying the leave to construct application for the St. Laurent project. Subsequent to this decision, Enbridge Gas has continued to assess the condition of the line through integrity work, ensuring the ongoing safety and reliability of the line. As a result, the project has been excluded from the *Growth Projects* table.

### RENEWABLE POWER GENERATION

- **Calvados Offshore Wind Project –** The Calvados Offshore Wind Project has experienced modest schedule pressures. The revised expected in-service date is 2025.
- **Solar Self-Power Projects –** The Solar Self-Power Projects have experienced modest schedule pressures. The revised expected in-service date is 2023-2024.

### OTHER ANNOUNCED PROJECTS UNDER DEVELOPMENT

The following projects have been announced by us during the quarter, but have not yet met our criteria to be classified as commercially secured:

### GAS TRANSMISSION AND MIDSTREAM

- **Valley Crossing Expansion Project –** On January 10, 2022, we executed a precedent agreement with Texas LNG Brownsville LLC (Texas LNG) under which, via an expansion of our Valley Crossing Pipeline, we will provide 0.72 bcf/d firm transportation capacity to Texas LNG’s proposed LNG liquefaction and export facility in the Port of Brownsville, Texas for a term of at least 20 years. Expansion of the pipeline will be subject to Texas LNG’s export facility reaching a final investment decision.

We also have a portfolio of additional projects under development that have not yet progressed to the point of securement.

### LIQUIDITY AND CAPITAL RESOURCES

The maintenance of financial strength and flexibility is fundamental to our growth strategy, particularly in light of the significant number and size of capital projects currently secured or under development. Access to timely funding from capital markets could be limited by factors outside our control, including but not limited to financial market volatility resulting from economic and political events both inside and outside North America. To mitigate such risks, we actively manage financial plans and strategies to help ensure we maintain sufficient liquidity to meet routine operating and future capital requirements.

In the near term, we generally expect to utilize cash from operations together with commercial paper issuance and/or credit facility draws and the proceeds of capital market offerings to fund liabilities as they become due, finance capital expenditures, fund debt retirements, share redemptions, execute share repurchases under our normal course issuer bid (NCIB) and pay common and preference share dividends. We target to maintain sufficient liquidity through securement of committed credit facilities with a diversified group of banks and financial institutions to enable us to fund all anticipated requirements for approximately one year without accessing the capital markets.

We have signed capital obligation contracts for the purchase of services, pipe and other materials totaling approximately $1.1 billion, which are expected to be paid over the next five years.

Our financing plan is regularly updated to reflect evolving capital requirements and financial market conditions and identifies a variety of potential sources of debt and equity funding alternatives. Our current financing plan does not include any issuances of additional common equity.

### CAPITAL MARKET ACCESS

We ensure ready access to capital markets, subject to market conditions, through maintenance of shelf prospectuses that allow for issuance of long-term debt, equity and other forms of long-term capital when market conditions are attractive.

### Credit Facilities and Liquidity

To ensure ongoing liquidity and to mitigate the risk of capital market disruption, we maintain ready access to funds through committed bank credit facilities and actively manage our bank funding sources to optimize pricing and other terms. The following table provides details of our committed credit facilities as at September 30, 2022:

| (millions of Canadian dollars) | Maturity1 | Total Facilities | Draws2 | Available |
| --- | --- | ---: | ---: | ---: |
| Enbridge Inc. | 2023-2027 | **10,949** | **9,451** | **1,498** |
| Enbridge (U.S.) Inc. | 2024-2027 | **8,245** | **3,909** | **4,336** |
| Enbridge Pipelines Inc. | 2024 | **2,000** | **858** | **1,142** |
| Enbridge Gas Inc. | 2024 | **2,000** | **1,885** | **115** |
| Total committed credit facilities |  | **23,194** | **16,103** | **7,091** |

*1Maturity date is inclusive of the one-year term out option for certain credit facilities.*

*2Includes facility draws and commercial paper issuances that are back-stopped by credit facilities.*

On February 10, 2022, we renewed our three year $1.0 billion sustainability-linked credit facility, extending the maturity date out to July 2025.

On May 17, 2022, we entered into a three year term loan with a syndicate of Japanese banks for approximately $806 million (¥84.8 billion), which will mature in May 2025 and replaces the approximately $499 million (¥52.5 billion) term loan that matured in May 2022. Additionally, on May 24, 2022, we entered into a 364-day term loan for approximately $1.9 billion, which will mature in May 2023.

On June 23, 2022, we renewed approximately $5.5 billion of our 364-day extendible credit facilities to July 2024, which includes a one-year term out provision from July 2023.

In July and August 2022, we renewed $12.7 billion of our credit facilities, extending the maturity dates of our 364-day credit facilities to July 2024, inclusive of a one-year term out provision from July 2023, and our five year facilities out to July 2027. As a part of the renewals, we increased our credit facilities by approximately $641 million.

In addition to the committed credit facilities noted above, we maintain $1.3 billion of uncommitted demand letter of credit facilities, of which $780 million was unutilized as at September 30, 2022. As at December 31, 2021, we had $1.3 billion of uncommitted demand letter of credit facilities, of which $854 million was unutilized.

As at September 30, 2022, our net available liquidity totaled $8.1 billion (December 31, 2021 - $6.5 billion), consisting of available credit facilities of $7.1 billion (December 31, 2021 - $6.2 billion) and was inclusive of unrestricted cash and cash equivalents of $1.0 billion (December 31, 2021 - $286 million) as reported in the Consolidated Statements of Financial Position.

Our credit facility agreements and term debt indentures include standard events of default and covenant provisions whereby accelerated repayment and/or termination of the agreements may result if we are to default on payment or violate certain covenants. As at September 30, 2022, we are in compliance with all covenant provisions.

### LONG-TERM DEBT ISSUANCES

During the nine months ended September 30, 2022, we completed the following long-term debt issuances totaling $1.4 billion and US$2.6 billion:

| Company Issue Date (millions of Canadian dollars unless otherwise stated) Enbridge Inc. |  | Principal Amount |
| --- | ---: | --- |
| January 2022 | 5.00% fixed-to-fixed subordinated notes due January 20821 | $750 |
| February 2022 | Floating rate senior notes due February 20242 | US$600 |
| February 2022 | 2.15% senior notes due February 2024 | US$400 |
| February 2022 | 2.50% senior notes due February 2025 | US$500 |
| September 2022 | 7.38% fixed-to-fixed subordinated notes due January 20833 | US$500 |
| September 2022 | 7.63% fixed-to-fixed subordinated notes due January 20834 | US$600 |
| Enbridge Gas Inc. |  |  |
| August 2022 | 4.15% medium-term notes due August 2032 | $325 |
| August 2022 | 4.55% medium-term notes due August 2052 | $325 |

*1For the initial 10 years, the notes carry a fixed interest rate. At year 10, the interest rate will be reset to equal to the Five-Year Government of Canada bond yield plus a margin of 3.54%. Subsequent to year 10, every five years, the Five Year Government of Canada bond yield is reset. At year 30, the interest rate will be reset to equal to the Five-Year Government of Canada bond yield plus a margin of 4.29%.*

*2Notes carry an interest rate set to equal the Secured Overnight Financing Rate plus a margin of 63 basis points.*

*3For the initial five years, the notes carry a fixed interest rate. At year five the interest rate will be set to equal to the Five-Year US Treasury rate plus a margin of 3.71%. At year 10, the interest rate will be reset to equal the Five-Year US Treasury rate plus a margin of 3.96%. Subsequent to year 10, every five years, the Five Year US Treasury rate is reset. At year 25, the interest rate will be reset to equal to the Five-Year US Treasury rate plus a margin of 4.71%.*

*4For the initial 10 years, the notes carry a fixed interest rate. At year 10, the interest rate will be reset to equal to the Five-Year US Treasury rate plus a margin of 4.42%. Subsequent to year 10, every five years, the Five-Year US Treasury rate will be reset. At year 30, the interest rate will be reset to equal to the Five-Year US Treasury rate plus a margin of 5.17%.*

### LONG-TERM DEBT REPAYMENTS

During the nine months ended September 30, 2022, we completed the following long-term debt repayments totaling US$1.5 billion and $0.3 billion:

| Company Repayment Date (millions of Canadian dollars unless otherwise stated) Enbridge Inc. February 2022 | Floating rate notes1 |  | Principal Amount US$750 |
| --- | ---: | --- | ---: |
| February 2022 | 4.85% | medium-term notes | $200 |
| July 2022 | 2.90% | senior notes due July 2022 | US$700 |
| Enbridge Gas Inc. |  |  |  |
| April 2022 | 4.85% | medium-term notes | $125 |
| Enbridge Pipelines (Southern Lights) L.L.C. |  |  |  |
| June 2022 | 3.98% | senior notes | US$34 |
| Enbridge Southern Lights LP |  |  |  |
| June 2022 | 4.01% | senior notes | $9 |

*1Notes carried an interest rate set to equal the three-month London Interbank Offered Rate plus a margin of 50 basis points.*

Strong internal cash flow, ready access to liquidity from diversified sources and a stable business model have enabled us to manage our credit profile. We actively monitor and manage key financial metrics with the objective of sustaining investment grade credit ratings from the major credit rating agencies and ongoing access to bank funding and term debt capital on attractive terms. Key measures of financial strength that are closely managed include the ability to service debt obligations from operating cash flow and the ratio of debt to EBITDA.

There are no material restrictions on our cash. Total restricted cash of $36 million, as reported on the Consolidated Statements of Financial Position, primarily includes cash collateral, future pipeline abandonment costs collected and held in trust, amounts received in respect of specific shipper commitments and capital projects. Cash and cash equivalents held by certain subsidiaries may not be readily accessible for alternative uses by us.

Excluding current maturities of long-term debt, as at September 30, 2022 and December 31, 2021, we had negative working capital position of $0.7 billion and $3.1 billion. In both periods, the major contributing factor to the negative working capital position was the ongoing funding of our growth capital program. We maintain significant liquidity in the form of committed credit facilities and other sources as previously discussed, which enable the funding of liabilities as they become due.

### SOURCES AND USES OF CASH

| (millions of Canadian dollars) | Nine months ended September 30, 2022 | 2021 |
| --- | ---: | ---: |
| Operating activities | **7,617** | 7,366 |
| Investing activities | **(3,158)** | (5,907) |
| Financing activities | **(3,785)** | (1,422) |
| Effect of translation of foreign denominated cash and cash equivalents and restricted cash | **63** | (12) |
| Net change in cash and cash equivalents and restricted cash | **737** | 25 |

Significant sources and uses of cash for the nine months ended September 30, 2022 and 2021 are summarized below:

### Operating Activities

Typically, the primary factors impacting cash flow from operating activities period-over-period include changes in our operating assets and liabilities in the normal course due to various factors, including the impact of fluctuations in commodity prices and activity levels on working capital within our business segments, the timing of tax payments, as well as timing of cash receipts and payments generally. Cash provided by operating activities is also impacted by changes in earnings and certain infrequent or other non-operating factors, as discussed under *Results of Operations.*

### Investing Activities

Cash used in investing activities primarily relates to capital expenditures to execute our capital program, which is further described in *Growth Projects - Commercially Secured Projects*. The timing of project approval, construction and in-service dates impacts the timing of cash requirements. Factors impacting the decrease in cash used in investing activities period-over-period primarily include:

- lower capital expenditures due to the US L3R Program that was placed into service in the fourth quarter of 2021; and
- proceeds from the completion of a joint venture merger transaction for DCP Midstream LLC in August 2022.

The factors above were partially offset by:

- increased contributions made to our equity investment in Bakken Pipeline System due to debt servicing requirements;
- our acquisition of TGE in September 2022; and
- increased investments held by our wholly-owned captive insurance subsidiaries.

### Financing Activities

Cash used in financing activities primarily relates to issuances and repayments of external debt, as well as transactions with our common and preference shareholders relating to dividends, share issuances, share redemptions and common share repurchases under our NCIB. Cash flow from financing activities is also impacted by changes in distributions to, and contributions from, noncontrolling interests. Factors impacting the increase in cash used in financing activities period-over-period primarily include:

- the redemption of Preference Shares, Series 17 and Series J in the first and second quarters of 2022, respectively;
- lower long-term debt issuances and higher long-term debt repayments in 2022, when compared to the same period in 2021;
- the repurchase and cancellation of 2,737,965 common shares under our NCIB for approximately $151 million during the period; and
- common share dividend payments increased period-over-period primarily due to the 3% increase in our common share dividend rate.

The factors above were partially offset by:

- net commercial paper and credit facility draws in 2022 when compared to net repayments in the same period in 2021;
- higher short-term borrowings in 2022 when compared to the same period in 2021; and
- the absence of the redemption of WEI's preferred shares in the first quarter of 2021.

### SUMMARIZED FINANCIAL INFORMATION

On January 22, 2019, Enbridge entered into supplemental indentures with its wholly-owned subsidiaries, Spectra Energy Partners, LP (SEP) and Enbridge Energy Partners, L.P. (EEP) (the Partnerships), pursuant to which Enbridge fully and unconditionally guaranteed, on a senior unsecured basis, the payment obligations of the Partnerships with respect to the outstanding series of notes issued under the respective indentures of the Partnerships. Concurrently, the Partnerships entered into a subsidiary guarantee agreement pursuant to which they fully and unconditionally guaranteed, on a senior unsecured basis, the outstanding series of senior notes of Enbridge. The Partnerships have also entered into supplemental indentures with Enbridge pursuant to which the Partnerships have issued full and unconditional guarantees, on a senior unsecured basis, of senior notes issued by Enbridge subsequent to January 22, 2019. As a result of the guarantees, holders of any of the outstanding guaranteed notes of the Partnerships (the Guaranteed Partnership Notes) are in the same position with respect to the net assets, income and cash flows of Enbridge as holders of Enbridge's outstanding guaranteed notes (the Guaranteed Enbridge Notes), and vice versa. Other than the Partnerships, Enbridge subsidiaries (including the subsidiaries of the Partnerships, collectively, the Subsidiary Non-Guarantors), are not parties to the subsidiary guarantee agreement and have not otherwise guaranteed any of Enbridge's outstanding series of senior notes.

### Consenting SEP notes and EEP notes under Guarantee

| SEP Notes1 | EEP Notes2 |
| --- | --- |
| 4.750% Senior Notes due 2024 | 5.875% Notes due 2025 |
| 3.500% Senior Notes due 2025 | 5.950% Notes due 2033 |
| 3.375% Senior Notes due 2026 | 6.300% Notes due 2034 |
| 5.950% Senior Notes due 2043 | 7.500% Notes due 2038 |
| 4.500% Senior Notes due 2045 | 5.500% Notes due 2040 |
|  | 7.375% Notes due 2045 |

*1As at September 30, 2022, the aggregate outstanding principal amount of SEP notes was approximately US$3.2 billion.*

*2As at September 30, 2022, the aggregate outstanding principal amount of EEP notes was approximately US$2.4 billion.*

### Enbridge Notes under Guarantees

| USD Denominated1 | CAD Denominated2 |
| --- | --- |
| Floating Rate Senior Notes due 2023 | 3.190% Senior Notes due 2022 |
| Floating Rate Senior Notes due 2024 | 3.940% Senior Notes due 2023 |
| 4.000% Senior Notes due 2023 | 3.940% Senior Notes due 2023 |
| 0.550% Senior Notes due 2023 | 3.950% Senior Notes due 2024 |
| 3.500% Senior Notes due 2024 | 2.440% Senior Notes due 2025 |
| 2.150% Senior Notes due 2024 | 3.200% Senior Notes due 2027 |
| 2.500% Senior Notes due 2025 | 6.100% Senior Notes due 2028 |
| 2.500% Senior Notes due 2025 | 2.990% Senior Notes due 2029 |
| 4.250% Senior Notes due 2026 | 7.220% Senior Notes due 2030 |
| 1.600% Senior Notes due 2026 | 7.200% Senior Notes due 2032 |
| 3.700% Senior Notes due 2027 | 3.100% Sustainability-Linked Senior Notes due 2033 |
| 3.125% Senior Notes due 2029 | 5.570% Senior Notes due 2035 |
| 2.500% Sustainability-Linked Senior Notes due 2033 | 5.750% Senior Notes due 2039 |
| 4.500% Senior Notes due 2044 | 5.120% Senior Notes due 2040 |
| 5.500% Senior Notes due 2046 | 4.240% Senior Notes due 2042 |
| 4.000% Senior Notes due 2049 | 4.570% Senior Notes due 2044 |
| 3.400% Senior Notes due 2051 | 4.870% Senior Notes due 2044 |
|  | 4.100% Senior Notes due 2051 |
|  | 4.560% Senior Notes due 2064 |

*1As at September 30, 2022, the aggregate outstanding principal amount of the Enbridge US dollar denominated notes was approximately US$11.0 billion.*

*2As at September 30, 2022, the aggregate outstanding principal amount of the Enbridge Canadian dollar denominated notes was approximately $9.0 billion.*

Rule 3-10 of the US SEC Regulation S-X provides an exemption from the reporting requirements of the Exchange Act for fully consolidated subsidiary issuers of guaranteed securities and subsidiary guarantors and allows for summarized financial information in lieu of filing separate financial statements for each of the Partnerships.

The following Summarized Combined Statement of Earnings and Summarized Combined Statements of Financial Position combines the balances of EEP, SEP and Enbridge.

### Summarized Combined Statement of Earnings

| Nine months ended September 30, (millions of Canadian dollars) | 2022 |
| --- | ---: |
| Operating loss | **(124)** |
| Earnings | **333** |
| Earnings attributable to common shareholders | **3** |

57

### Summarized Combined Statements of Financial Position

| (millions of Canadian dollars) | September 30, 2022 | December 31, 2021 |
| --- | ---: | ---: |
| Accounts receivable from affiliates | **2,482** | 3,442 |
| Short-term loans receivable from affiliates | **8,613** | 4,947 |
| Other current assets | **433** | 605 |
| Long-term loans receivable from affiliates | **45,857** | 51,983 |
| Other long-term assets | **4,609** | 3,732 |
| Accounts payable to affiliates | **1,339** | 1,982 |
| Short-term loans payable to affiliates | **3,368** | 2,891 |
| Other current liabilities | **6,097** | 8,110 |
| Long-term loans payable to affiliates | **39,208** | 41,370 |
| Other long-term liabilities | **48,842** | 41,353 |

The Guaranteed Enbridge Notes and the Guaranteed Partnership Notes are structurally subordinated to the indebtedness of the Subsidiary Non-Guarantors in respect of the assets of those Subsidiary Non-Guarantors.

Under US bankruptcy law and comparable provisions of state fraudulent transfer laws, a guarantee can be voided, or claims may be subordinated to all other debts of that guarantor if, among other things, the guarantor, at the time the indebtedness evidenced by its guarantee or, in some states, when payments become due under the guarantee:

- received less than reasonably equivalent value or fair consideration for the incurrence of the guarantee and was insolvent or rendered insolvent by reason of such incurrence;
- was engaged in a business or transaction for which the guarantor’s remaining assets constituted unreasonably small capital; or
- intended to incur, or believed that it would incur, debts beyond its ability to pay those debts as they mature.

The guarantees of the Guaranteed Enbridge Notes contain provisions to limit the maximum amount of liability that the Partnerships could incur without causing the incurrence of obligations under the guarantee to be a fraudulent conveyance or fraudulent transfer under US federal or state law.

Each of the Partnerships is entitled to a right of contribution from the other Partnership for 50% of all payments, damages and expenses incurred by that Partnership in discharging its obligations under the guarantees for the Guaranteed Enbridge Notes.

Under the terms of the guarantee agreement and applicable supplemental indentures, the guarantees of either of the Partnerships of any Guaranteed Enbridge Notes will be unconditionally released and discharged automatically upon the occurrence of any of the following events:

- any direct or indirect sale, exchange or transfer, whether by way of merger, sale or transfer of equity interests or otherwise, to any person that is not an affiliate of Enbridge, of any of Enbridge’s direct or indirect limited partnership of other equity interests in that Partnership as a result of which the Partnership ceases to be a consolidated subsidiary of Enbridge;
- the merger of that Partnership into Enbridge or the other Partnership or the liquidation and dissolution of that Partnership;
- the repayment in full or discharge or defeasance of those Guaranteed Enbridge Notes, as contemplated by the applicable indenture or guarantee agreement;
- with respect to EEP, the repayment in full or discharge or defeasance of each of the consenting EEP notes listed above;
- with respect to SEP, the repayment in full or discharge or defeasance of each of the consenting SEP notes listed above; or
- with respect to any series of Guaranteed Enbridge Notes, with the consent of holders of at least a majority of the outstanding principal amount of that series of Guaranteed Enbridge Notes.

The guarantee obligations of Enbridge will terminate with respect to any series of Guaranteed Partnership Notes if that series is discharged or defeased.

The Partnerships also guarantee the obligations of Enbridge under its existing credit facilities.

### LEGAL AND OTHER UPDATES

### LIQUIDS PIPELINES

### Line 5 Easement

On July 23, 2019, the Bad River Band of the Lake Superior Tribe of Chippewa Indians (the Band) filed a complaint in the United States District Court for the Western District of Wisconsin (the Court) over our Line 5 pipeline and right-of-way across the Bad River Reservation (the Reservation). Only a small portion of the total easements across 12 miles of the Reservation are at issue. The Band alleges that our continued use of Line 5 to transport crude oil and related liquids across the Reservation is a public nuisance under federal and state law and that the pipeline is in trespass on certain tracts of land in which the Band possesses ownership interests. The complaint seeks an order prohibiting us from using Line 5 to transport crude oil and related liquids across the Reservation and requiring removal of the pipeline from the Reservation. Subsequently amended versions of the complaint also seek recovery of profits-based damages based on an unjust enrichment theory. Enbridge has responded to each claim in the initial and amended complaints with an answer, defenses and counterclaims.

On August 29, 2022, the Government of Canada released a statement formally invoking the dispute settlement provisions of the 1977 Transit Pipelines Treaty in respect of this litigation; reiterating its concerns about the uninterrupted transmission of hydrocarbons through Line 5. On September 7, 2022, the Court issued a decision on cross-motions for summary judgment. The Court determined that the Band’s nuisance claim raised factual issues that could not be resolved on summary judgment. The Court further determined that Enbridge is in trespass on certain tracts on the Reservation and that the Band is entitled to some measure of profits-based damages and to an injunction, with the level of damages and scope of the injunction to be determined at trial, which occurred between October 24 and November 1, 2022. While the Court reserved judgment at the conclusion of the trial, the summary judgment decision and subsequent pre-trial decisions provide that the Court will assess trespass damages calculated using a pro-rata share of Enbridge’s profits from the operation of the pipeline attributable to the 12 disputed parcels compared to the pipeline as a whole rather than the profits associated with the entire length of the pipeline, as the Band sought. The Court has also stated that any injunction will not result in the immediate closure of the pipeline but also will not allow the pipeline to operate indefinitely.

### Michigan Line 5 Dual Pipelines - Straits of Mackinac Easement

In 2019, the Michigan Attorney General (AG) filed a complaint in the Michigan Ingham County Circuit Court (the Circuit Court) that requests the Circuit Court to declare the easement granted in 1953 that we have for the operation of Line 5 in the Straits of Mackinac (the Straits) to be invalid and to prohibit continued operation of Line 5 in the Straits. On December 15, 2021, we removed the case to the US District Court in the Western District of Michigan (US District Court), where it was assigned to Judge Janet T. Neff. The removal of the AG’s case to federal court follows a November 16, 2021 ruling which held that the similar (and now dismissed) 2020 lawsuit brought by the Governor of Michigan to force Line 5’s shutdown raised important federal issues that should be heard in federal court. On December 21, 2021, the AG made a request to file a remand motion and on December 28, 2021, we responded to her request to file that motion. On January 5, 2022, the court issued an Order allowing the AG to file a motion to remand the 2019 case. The AG’s motion and brief were filed on January 14, 2022, and our response was filed on February 11, 2022. The motion was fully briefed in March 2022. On August 18, 2022, Judge Neff denied the AG’s motion to remand which now remains in the US District Court. On August 30, 2022, the AG filed a motion to certify the US District Court’s August 18 Order to pursue an appeal on the jurisdictional issue, which Enbridge opposed. We anticipate a decision on the jurisdictional issue in 2022.

### OTHER LITIGATION

We and our subsidiaries are involved in various other legal and regulatory actions and proceedings which arise in the normal course of business, including interventions in regulatory proceedings and challenges to regulatory approvals and permits. While the final outcome of such actions and proceedings cannot be predicted with certainty, management believes that the resolution of such actions and proceedings will not have a material impact on our consolidated financial position or results of operations.

### TAX MATTERS

We and our subsidiaries maintain tax liabilities related to uncertain tax positions. While fully supportable in our view, these tax positions, if challenged by tax authorities, may not be fully sustained on review.

### CHANGES IN ACCOUNTING POLICIES

Refer to Part I. *Item 1. Financial Statements - Note 2. Changes in Accounting Policies.*

## Market risk

As filed, 272 characters.

Our exposure to market risk is described in Part II. *Item 7A. Quantitative and Qualitative Disclosures About Market Risk* of our annual report on Form 10-K for the year ended December 31, 2021. We believe our exposure to market risk has not changed materially since then.

## Controls and procedures

As filed, 2,040 characters.

### Evaluation of Disclosure Controls and Procedures

Disclosure controls and procedures are controls and other procedures that are designed to ensure that information required to be disclosed by us in the reports we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified by the SEC's rules and forms. Disclosure controls and procedures include, without limitation, controls and procedures designed to provide reasonable assurance that information required to be disclosed by us in the reports we file or submit under the Exchange Act is accumulated and communicated to management, including the Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.

Under the supervision of and with the participation of management, including the Chief Executive Officer and Chief Financial Officer, we have evaluated the effectiveness of our disclosure controls and procedures (as such term is defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act) as at September 30, 2022, and based upon this evaluation, the Chief Executive Officer and Chief Financial Officer have concluded that these controls and procedures are effective in ensuring that information required to be disclosed by us in reports that we file with or submit to the SEC and the Canadian Securities Administrators is recorded, processed, summarized and reported within the time periods required.

### Changes in Internal Control over Financial Reporting

Under the supervision of and with the participation of management, including the Chief Executive Officer and Chief Financial Officer, we have evaluated changes in internal control over financial reporting (as such term is defined in Rules 13a-15(f) and 15d-15(f) under the Exchange Act) that occurred during the fiscal quarter ended September 30, 2022 and found no change that has materially affected, or is reasonably likely to materially affect, internal control over financial reporting.

## Risk factors

As filed, 370 characters.

In addition to the other information set forth in this report, careful consideration should be given to the factors discussed in Part I. *Item 1A. Risk Factors* of our annual report on Form 10-K for the year ended December 31, 2021, which could materially affect our financial condition or future results. There have been no material modifications to those risk factors.

Filed Nov 4, 2022.
Source: SEC EDGAR, the filing index for accession 0000895728-22-000033. Last ingested by Listed: Nov 14, 2026, 20:51 ET. No prices; not investment advice.