# MGE Energy Inc: Form 10-Q for the period ended Sep 30, 2022

- Company: [MGE Energy Inc](/companies/mgee.md) (CIK 1161728)
- Form: 10-Q
- Filed: 2022-11-03
- Accepted by EDGAR: Nov 3, 2022, 11:12 ET
- Period: 2022-09-30
- Accession: 0000950170-22-021653
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/1161728/000095017022021653/mgee-20220930.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/1161728/000095017022021653/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2022-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Operating income | 3 months, 2022-07-01 to 2022-09-30 | $42.5m | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2022-01-01 to 2022-09-30 | $109.8m | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months, 2022-07-01 to 2022-09-30 | $8.2m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2022-01-01 to 2022-09-30 | $21.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2022-07-01 to 2022-09-30 | $33.7m | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2022-01-01 to 2022-09-30 | $89.9m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2022-07-01 to 2022-09-30 | $0.93 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2022-01-01 to 2022-09-30 | $2.49 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2022-07-01 to 2022-09-30 | $0.93 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2022-01-01 to 2022-09-30 | $2.49 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2022-07-01 to 2022-09-30 | 36,176,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2022-01-01 to 2022-09-30 | 36,174,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2022-01-01 to 2022-09-30 | $144.3m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2022-01-01 to 2022-09-30 | $133.4m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2022-01-01 to 2022-09-30 | $42.8m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2022-09-30 | $10.6m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2022-09-30 | $199.8m | us-gaap:AssetsCurrent |
| Total assets | at 2022-09-30 | $2.47bn | us-gaap:Assets |
| Current liabilities | at 2022-09-30 | $194.8m | us-gaap:LiabilitiesCurrent |
| Long-term debt | at 2022-09-30 | $561.6m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2022-09-30 | $54.3m | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | at 2022-09-30 | $40.0m | us-gaap:ShortTermBorrowings |
| Shareholders' equity | at 2022-09-30 | $1.08bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 63,296 characters.

### General

MGE Energy is an investor-owned public utility holding company operating through subsidiaries in five business segments:

- Regulated electric utility operations, conducted through MGE,
- Regulated gas utility operations, conducted through MGE,
- Nonregulated energy operations, conducted through MGE Power and its subsidiaries,
- Transmission investments, representing our equity investment in ATC and ATC Holdco, and
- All other, which includes corporate operations and services.

Our principal subsidiary is MGE, which generates and distributes electric energy, distributes natural gas, and represents a majority portion of our assets, liabilities, revenues, and expenses. MGE generates, purchases, and distributes electricity to approximately 159,000 customers in Dane County, Wisconsin, including the city of Madison, and purchases and distributes natural gas to approximately 169,000 customers in the Wisconsin counties of Columbia, Crawford, Dane, Iowa, Juneau, Monroe, and Vernon.

Our nonregulated energy operations own interests in electric generating capacity that is leased to MGE. The ownership/leasing structure was adopted under applicable state regulatory guidelines for MGE's participation in these generation facilities, consisting principally of a stable return on the equity investment in the new generation facilities over the term of the related leases. The nonregulated energy operations include an ownership interest in two coal-fired generating units in Oak Creek, Wisconsin and a partial ownership of a cogeneration project on the UW-Madison campus. A third party operates the units in Oak Creek, and MGE operates the cogeneration project. Due to the nature of MGE's participation in these facilities, the results of MGE Energy's nonregulated operations are also consolidated into MGE's consolidated financial position and results of operations under applicable accounting standards.

### Executive Overview

Our primary focus today and for the foreseeable future is our core utility customers at MGE as well as creating long-term value for our shareholders. MGE continues to face the challenge of providing its customers with reliable power at competitive prices. MGE works on meeting this challenge by investing in more efficient generation projects, including renewable energy sources. As we work toward achieving 80% carbon reduction by 2030 (from 2005 levels), MGE continues to examine and pursue opportunities to reduce the proportion that coal generation represents in its generation mix, as evidenced by its most recent announcements of the retirement of Columbia (a coal generation plant), the planned change in the Elm Road Units fuel source from coal to natural gas, and its growing ownership of renewable generation sources. MGE will continue to focus on growing earnings while controlling operating and fuel costs. MGE's goal is to provide safe and efficient operations in addition to providing customer value. We believe it is critical to maintain a strong credit rating consistent with financial strength in MGE in order to accomplish these goals.

We principally earn revenue and generate cash from operations by providing electric and natural gas utility services, including electric power generation and electric power and gas distribution. The earnings and cash flows from the utility business are sensitive to various external factors, including:

- Weather, and its impact on customer sales,
- Economic conditions, including current business activity and employment and their impact on customer demand,
- Regulation and regulatory issues, and their impact on the timing and recovery of costs,
- Energy commodity prices, including natural gas prices,
- Equity price risk pertaining to pension related assets,
- Credit market conditions, including interest rates and our debt credit rating,
- Environmental laws and regulations, including adopted and pending environmental rule changes,
- Impacts on activity arising from COVID-19 and its variants, including government restrictions on activity,

increased employee health and welfare costs, precautions for dealing with members of the public, and supply chain disruptions, and

- Other factors listed in "Item 1A. Risk Factors" in our 2021 Annual Report on Form 10-K.

During the three months ended September 30, 2022, MGE Energy's earnings were $33.7 million or $0.93 per share compared to $34.9 million or $0.97 per share during the same period in the prior year. MGE's earnings during the three months ended September 30, 2022, were $27.2 million compared to $27.4 million during the same period in the prior year.

During the nine months ended September 30, 2022, MGE Energy's earnings were $89.9 million or $2.49 per share compared to $92.7 million or $2.56 per share during the same period in the prior year. MGE's earnings during the nine months ended September 30, 2022, were $68.5 million compared to $70.8 million during the same period in the prior year.

MGE Energy's net income was derived from our business segments as follows:

*(In millions)*

| Business Segment: | Three Months Ended September 30, 2022 | 2021 | Nine Months Ended September 30, 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Electric Utility | $27.6 | $27.8 | $55.2 | $60.0 |
| Gas Utility | (0.4) | (0.2) | 12.8 | 11.6 |
| Nonregulated Energy | 5.6 | 5.4 | 16.5 | 15.9 |
| Transmission Investments | 1.1 | 1.8 | 4.8 | 5.4 |
| All Other | (0.2) | 0.1 | 0.6 | (0.2) |
| Net Income | $33.7 | $34.9 | $89.9 | $92.7 |

Our net income during the three and nine months ended September 30, 2022, compared to the same periods in the prior year primarily reflects the effects of the following factors:

#### Electric Utility

An increase in electric investments contributed to earnings for 2022. Timing of 2021 depreciation and other operations and maintenance costs contributed to higher earnings in 2021. Depreciation and operations and maintenance costs increased during the remainder of 2021 and into 2022 after significant capital projects were completed. The new customer information system went live in September 2021 and Badger Hollow I was completed in November 2021. MGE received approval to recover 100% AFUDC during construction of these projects.

#### Gas Utility

An increase in gas investments contributed to increased earnings for 2022. Higher gas retail sales resulting from colder weather in the first half of 2022 contributed to higher earnings for the nine months ended September 30, 2022. Heating degree days (a measure for determining the impact of weather during the heating season) increased by approximately 7% in the first nine months of 2022 compared to the same period in the prior year.

#### Transmission Investments

In September 2022, our share of ATC's earnings reflected an estimated possible loss of approximately $0.8 million, inclusive of interest and net of tax, related to the August 2022 developments in the MISO transmission owners complaints on authorized return on equity. See additional information in "Other Matters" below.

The following developments affected the first nine months of 2022:

2022/2023 Rate Settlement Agreement: In December 2021, the PSCW approved a settlement agreement for MGE's 2022 rate case. The settlement agreement provides for an 8.81% increase to electric rates and a 2.15% increase to gas rates for 2022. As part of that settlement agreement, the PSCW approved a 0.96% increase in 2023 gas rates and a potential 2023 electric rate change to be addressed through a limited rate case reopener. See "Other Matters" below for additional information on the 2022/2023 rate case settlement.

Utility Solar: Large solar generation projects were recently completed or are under construction, as shown in the following table. Incurred costs are reflected in "Property, plant, and equipment, net" for projects placed in service, or "Construction work in progress" for projects under construction on the consolidated balance sheets.

| Project | Ownership Interest | Share of Generation | Share of Estimated Costs(a) | Costs Incurred as of September 30, 2022(a) | Estimated Date of Commercial Operation |
| --- | ---: | --- | --- | --- | --- |
| Red Barn | 10% | 9.16MW | $18 million | $0.6 million | Early 2023 |
| Badger Hollow II | 33% | 50 MW | $76 million | $46.8 million(b)(c) | First Half of 2023 |
| Paris | 10% | 31 MW | $51 million | $21.8 million(b) | 2023(d) |

(a) Excluding AFUDC.

(b) MGE received specific approval to recover 100% AFUDC on Badger Hollow II and Paris. After tax, MGE recognized $1.9 million and $0.3 million of AFUDC equity through September 30, 2022, on Badger Hollow II and Paris, respectively, during construction. AFUDC has been excluded from the costs incurred in the table above.

(c) Includes an allocation of common facilities at Badger Hollow placed in service in November 2021.

(d) Battery storage timing to be determined.

Deferred Fuel Costs: MGE has under-recovered fuel costs through the nine months ended September 30, 2022. As of September 30, 2022, MGE had deferred $4.4 million of 2022 fuel costs. Coal transportation constraints resulted in reduced generation at Columbia, which required MGE to purchase power in the market at higher cost. We may continue to see increased fuel costs in the near term because of these coal transportation constraints. These costs will be subject to the PSCW's annual review of 2022 fuel costs, expected to be completed during 2023. See Footnote 9.b. of the Notes to Consolidated Financial Statements in this Report for further information regarding fuel cost proceedings.

In the near term, several items may affect us, including:

2021 Annual Fuel Proceeding: MGE under-recovered fuel costs in 2021. As of December 31, 2021, MGE had deferred $3.3 million of 2021 fuel costs. In August 2022, the PSCW issued a final decision in the 2021 fuel rules proceedings for MGE to include the recovery of these costs as part of the 2023 electric limited rate case reopener. There was no change to the costs to be recovered in the fuel rule proceedings from the amount MGE deferred in the previous year.

2023 Electric Limited Rate Case Reopener: In April 2022, MGE filed with the PSCW a proposed electric limited rate case reopener. The limited rate case reopener proposes a 4.38% increase to electric rates for 2023. See "Other Matters" below for additional information on the 2023 electric limited rate case reopener.

ATC Return on Equity: As discussed in "Other Matters" below, ATC's authorized ROE, which is used in calculating its rates and revenues, is the subject of a challenge before FERC. A decrease in ATC's ROE could result in lower equity earnings and distributions from ATC in the future. We derived approximately 5.1% and 5.7% of our net income during the nine months ended September 30, 2022 and 2021, respectively, from our investment in ATC.

Environmental Initiatives: There are proposed legislative rules and initiatives involving matters related to air emissions, water effluent, hazardous materials, and greenhouse gases, all of which affect generation plant capital expenditures and operating costs as well as future operational planning. Legislation and rulemaking addressing climate change and related matters could significantly affect the costs of owning and operating fossil-fueled generating plants. We would expect to seek and receive recovery of any such costs in rates. However, it is difficult to estimate the amount of such costs due to the uncertainty as to the timing and form of any legislation or rules, and the scope and time of the recovery of costs in rates, which may occur after those costs have been incurred and paid.

Future Generation – 80% carbon reduction target by 2030 (from 2005 levels): MGE has outlined initiatives to achieve our raised target.

- *Transitioning away from coal.* Columbia: In February 2021, MGE, along with the other plant co-owners, announced plans to retire the two-unit coal-fired Columbia generating plant near Portage, Wisconsin. MGE currently owns 19% of the facility. The co-owners initially intended to retire Unit 1 by the end of

2023 and Unit 2 by the end of 2024. In June 2022, the target retirement date for both Units was updated to June 2026 after consideration by the owners of supply chain disruptions impacting the completion dates of current and planned renewable generation projects and the impact of those delays upon energy supply availability, reliability and cost. The postponement is not expected to affect MGE's goal to achieve 80% carbon reduction by 2030. Final timing and retirement dates for Units 1 and 2 are subject to change depending on operational, regulatory, and other factors. MGE continues to evaluate additional investments to replace the generation from Columbia while maintaining electric service reliability. These investments include cost-effective, clean energy projects to help achieve MGE's carbon reduction goals.

Elm Road Units: In November 2021, MGE announced plans to end the use of coal as a primary fuel at the Elm Road Units and transition the plant to natural gas. MGE is a minority owner of Elm Road, owning 8.33%. The approximately 1,230 MW coal-fired plant is co-owned by WEC Energy Group, whose subsidiary serves as operator, and by WPPI Energy, Inc. Transition plans and costs will be subject to PSCW approval. MGE's remaining use of coal is expected to be further reduced as the Elm Road Units transition to natural gas. By the end of 2030, MGE expects coal to be used only as a backup fuel at the Elm Road Units. This transition will help MGE meet its 2030 carbon reduction goals. By 2035, MGE expects that the Elm Road Units will be fully transitioned away from coal, which will eliminate coal as an internal generation source for MGE.

- *Growing renewable generation.* MGE is seeking to acquire a joint interest in several renewable generation projects. See the 2022-2025 capital expenditures forecast included under "Liquidity and Capital Resources" below for information on these projects.
- *Natural gas as a fuel source.* West Riverside: MGE is seeking approval for a sale and purchase of ownership interest in West Riverside. See the 2022-2025 capital expenditures forecast included under "Liquidity and Capital Resources" below for information on West Riverside.

Solar Procurement Disruptions – Import Regulations: In June 2021, the U.S. Customs and Border Protection (CBP) issued a Withhold Release Order (WRO) against silica-based products made by Hoshine Silicon Industry Co. Ltd., a company located in China's Xinjiang Uyghur Autonomous Region. As a result of this WRO, CBP is holding many solar panels imported into the United States until importers can prove that the panels do not contain materials originating from this region. The Uyghur Forced Labor Protection Act, a federal law that became effective on June 21, 2022, further established that all goods mined, produced, or manufactured wholly or in part in Xinjiang or by certain defined entities are prohibited from U.S. importation. MGE is currently assessing the potential impact of these disruptions on current and future solar projects which may result in an increase in costs or delays in construction timelines. In the event that such disruptions cause costs to exceed the levels approved for specific projects, we expect to file a notification with the PSCW and expect to request recovery of any increases in MGE’s next rate proceeding.

Solar Procurement Disruptions – Solar Tariff Investigation: In March 2022, the U.S. Department of Commerce (USDOC) announced a solar tariff investigation on solar panels from four Southeast Asian countries. This investigation could result in additional tariffs on solar panels. In June 2022, the USDOC issued a 24-month exemption from tariffs for solar panel and module imports from these four countries. MGE is currently assessing the potential impact of these disruptions on current and future solar projects which may result in an increase in costs or delays in construction timelines. In the event that such disruptions cause costs to exceed the levels approved for specific projects, we expect to file a notification with the PSCW and expect to request recovery of any increases in MGE’s next rate proceeding.

COVID-19 Update: MGE Energy continues to provide safe and reliable service to our customers despite the challenges presented by the COVID-19 and its variants. We have operated continuously throughout the pandemic and suffered no material disruptions in service or employment. We continue to monitor potential disruptions or constraints in materials and supplies from key suppliers and as well as macroeconomic trends, such as inflation. We could experience increased costs and delays in our ability to perform certain maintenance and capital project activities. We cannot estimate with any degree of certainty the actual impact of COVID-19 and associated governmental regulations may have on future results of operations, financial position, and liquidity. See Item 1A. "Risk Factors" "Pandemic virus or diseases, including COVID-19, could have a material adverse effect on our business, financial condition and liquidity" in our 2021 Annual Report on Form 10-K for a description of risk.

The following discussion is based on the business segments as discussed in Footnote 14 of the Notes to Consolidated Financial Statements in this Report.

### Results of Operations

### Three Months Ended September 30, 2022 and 2021

### Electric sales and revenues

The following table compares MGE's electric revenues and electric kWh sales by customer class for each of the periods indicated:

*(In thousands, except CDD)*

|  | Revenues Three Months Ended September 30, 2022 | 2021 | % Change | Sales (kWh) Three Months Ended September 30, 2022 | 2021 | % Change |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $45,154 | $44,398 | 1.7% | 252,457 | 263,833 | (4.3)% |
| Commercial | 65,468 | 60,996 | 7.3% | 495,135 | 500,434 | (1.1)% |
| Industrial | 3,912 | 3,380 | 15.7% | 41,304 | 42,400 | (2.6)% |
| Other-retail/municipal | 10,010 | 9,478 | 5.6% | 104,548 | 106,919 | (2.2)% |
| Total retail | 124,544 | 118,252 | 5.3% | 893,444 | 913,586 | (2.2)% |
| Sales to the market | 7,858 | 3,071 | n.m.% | 48,632 | 67,536 | (28.0)% |
| Other | 474 | 316 | 50.0% | — | — | —% |
| Total | $132,876 | $121,639 | 9.2% | 942,076 | 981,122 | (4.0)% |
| Cooling degree days (normal 500) |  |  |  | 507 | 511 | (0.8)% |

n.m. not meaningful

Electric revenue increased $11.2 million during the three months ended September 30, 2022, compared to the same period in 2021, due to the following:

*(In millions)*

|  |  |
| --- | ---: |
| Rate changes | $7.8 |
| Sales to the market | 4.8 |
| Revenue subject to refund, net | 0.4 |
| Other | 0.4 |
| Decrease in residential volume | (1.6) |
| Net decrease in commercial, industrial and other-retail/municipal volume | (0.6) |
| Total | $11.2 |

- *Rate changes.* In December 2021, the PSCW authorized MGE to increase 2022 rates for retail electric customers by approximately 8.81%. Rates charged to retail customers during the three months ended September 30, 2022 were $7.8 million higher than those charged during the same period in the prior year. See Footnote 9 of the Notes to Consolidated Financial Statements in this Report for further information on rate increase. Any increase in rates associated with fuel or purchase power costs are generally offset in fuel and purchased power costs and do not have a significant impact on net income.
- *Sales to the market.* Sales to the market typically occur when MGE has more generation and purchases in the MISO market than are needed for its customer demand. The excess electricity is then sold to other utilities or power marketers in the MISO market. During the three months ended September 30, 2022, sales were made at higher market prices and partially offset by decreased market volume compared to the same period in the prior year, reflecting a decrease in sales. The revenue generated from these sales is included in fuel rules monitored costs. See fuel rules discussion in Footnote 9 of the Notes to Consolidated Financial Statements.
- *Revenue subject to refund.* For cost recovery mechanisms, any over-collection of revenues resulting from costs authorized to be collected from customers in rates exceeding actual costs is recorded as a reduction of revenue in the period incurred, as the over-collection is expected to be refunded to customers in a subsequent period. In the year the over-collection is refunded, rates are reduced and offset as revenue

subject to refund. There is no net income impact in the year the costs are refunded.

- *Residential volume.* During the three months ended September 30, 2022, residential sales decreased by approximately 4% compared to the same period in the prior year. This decrease was driven by a shift in usage patterns reflecting a reduction in remote work associated with the COVID-19 pandemic.

### Electric fuel and purchased power

*(In millions)*

|  | Three Months Ended September 30, 2022 | 2021 | $ Change |
| --- | ---: | ---: | ---: |
| Fuel for electric generation | $21.0 | $18.5 | $2.5 |
| Purchased power | 9.6 | 8.6 | 1.0 |

The $2.5 million increase in fuel for electric generation was due to an approximately 29% increase in the average cost offset by an approximately 12% decrease in internal generation. Coal transportation constraints resulted in reduced generation at Columbia, which required MGE to purchase power in the market at higher cost.

The $1.0 million increase in purchased power was due to an approximately 40% increase in market purchases as a result of lower internal generation.

Fuel and purchased power costs are generally offset by electric revenue and do not have a significant impact on net income. MGE expects to seek and receive recovery of fuel and purchased power costs outside the fuel rules bandwidth in customer rates. See Footnote 9 of the Notes to Consolidated Financial Statements in this Report for further information on the fuel rules bandwidth.

### Gas deliveries and revenues

The following table compares MGE's gas revenues and gas therms delivered by customer class for each of the periods indicated:

*(In thousands, except HDD and average*

| rate per therm of retail customer) | Revenues Three Months Ended September 30, 2022 | 2021 | % Change | Therms Delivered Three Months Ended September 30, 2022 | 2021 | % Change |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $17,167 | $14,643 | 17.2% | 6,166 | 5,987 | 3.0% |
| Commercial/Industrial | 11,490 | 8,069 | 42.4% | 9,555 | 8,889 | 7.5% |
| Total retail | 28,657 | 22,712 | 26.2% | 15,721 | 14,876 | 5.7% |
| Gas transportation | 1,588 | 1,256 | 26.4% | 15,183 | 15,212 | (0.2)% |
| Other | 65 | 52 | 25.0% | — | — | —% |
| Total | $30,310 | $24,020 | 26.2% | 30,904 | 30,088 | 2.7% |
| Heating degree days (normal 134) |  |  |  | 135 | 50 | 170.0% |
| Average rate per therm of retail customer | $1.823 | $1.527 | 19.4% |  |  |  |

Gas revenue increased $6.3 million during the three months ended September 30, 2022, compared to the same period in 2021, due to the following:

*(In millions)*

|  |  |
| --- | ---: |
| Rate changes | $3.9 |
| Increase in volume | 2.0 |
| Other | 0.4 |
| Total | $6.3 |

- *Rate changes.* In December 2021, the PSCW authorized MGE to increase 2022 rates for retail gas customers by approximately 2.15%.

MGE recovers the cost of natural gas in its gas segment through the purchased gas adjustment clause (PGA). Under the PGA, MGE is able to pass through to its gas customers the cost of gas. Changes in PGA recoveries affect revenues but do not change net income in view of the pass-through treatment of the costs. Payments for natural gas increased driving higher rates during the three months ended September 30, 2022.

The average retail rate per therm for the three months ended 2022, increased approximately 19% compared to 2021, reflecting a $5.7 million increase in natural gas commodity costs (recovered through the PGA).

- *Volume.* For 2022, retail gas deliveries increased approximately 6% compared to the same period in the prior year primarily related to favorable weather conditions in September 2022.

### Cost of gas sold

A $5.7 million increase in cost of gas sold driven by higher cost per therm of gas. Average cost per therm increased approximately 62%. MGE recovers the cost of natural gas in its gas segment through the PGA as described under gas deliveries and revenue above.

### Consolidated operations and maintenance expenses

During the three months ended September 30, 2022, operations and maintenance expenses increased $0.7 million, compared to the same period in the prior year. The following contributed to the net change:

*(In millions)*

|  |  |
| --- | ---: |
| Increased customer accounts costs | $0.5 |
| Increased electric production expenses | 0.4 |
| Increased transmission costs | 0.3 |
| Decreased other expenses | (0.5) |
| Total | $0.7 |

### Consolidated depreciation expense

Electric depreciation expense increased $1.7 million and gas depreciation expense increased $0.7 million during the three months ended September 30, 2022, compared to the same period in the prior year. MGE placed Badger Hollow I in service in November 2021. The timing of the in-service date contributed to the increase in electric depreciation expense. The new customer information system went live in September 2021, which increased depreciation expense for both electric and gas in 2022.

### Nonregulated Energy Operations - MGE Energy and MGE

The nonregulated energy operations are conducted through MGE Energy's subsidiaries: MGE Power Elm Road (the Elm Road Units) and MGE Power West Campus (WCCF), which have been formed to own and lease electric generating capacity to assist MGE. During the three months ended September 30, 2022 and 2021, net income at the nonregulated energy operations segment was $5.6 million and $5.4 million, respectively.

### Transmission Investment Operations - MGE Energy

The transmission investment segment holds our interest in ATC and ATC Holdco, and its income reflects our equity in the earnings of those investments. ATC Holdco was formed in December 2016 to pursue transmission development opportunities that typically have long development and investment lead times before becoming operational. ATC Holdco's transmission development activities have been suspended for the near term. During the three months ended September 30, 2022 and 2021, other income at the transmission investment segment primarily reflects ATC's operations and was $1.5 million and $2.5 million, respectively. In August 2022, the U.S. Court of Appeals for the D.C. Circuit vacated the underlying FERC orders regarding methodology for setting authorized return on equity resulting in an additional estimated possible loss. See Footnote 3 of the Notes to Consolidated Financial Statements in this Report and "Other Matters" below for additional information concerning ATC and summarized financial information regarding ATC.

### Consolidated Income Taxes - MGE Energy and MGE

In 2022, the effective electric tax rate increased as a result of the return of electric excess deferred taxes related to the 2017 Tax Act not governed by IRS normalization rules in 2021. These costs were recorded as a regulatory liability in the year of remeasurement. See Footnote 4 of the Notes to Consolidated Financial Statements in this Report for the effective tax rate reconciliation.

### Noncontrolling Interest, Net of Tax - MGE

Noncontrolling interest, net of tax, reflects the accounting required for MGE Energy's interest in MGE Power Elm Road (the Elm Road Units) and MGE Power West Campus (WCCF). MGE Energy owns 100% of MGE Power Elm Road and MGE Power West Campus. They are not owned by MGE. Due to the contractual agreements for these projects with MGE, the entities are considered VIEs with respect to MGE and their results are consolidated with those of MGE, the primary beneficiary of the VIEs. The following table shows MGE Energy's noncontrolling interest, net of tax, reflected on MGE's consolidated statement of income:

*(In millions)*

|  | Three Months Ended September 30, 2022 | 2021 |
| --- | ---: | ---: |
| MGE Power Elm Road | $3.8 | $3.8 |
| MGE Power West Campus | 1.8 | 1.8 |

### Nine Months Ended September 30, 2022 and 2021

### Electric sales and revenues

The following table compares MGE's electric revenues and electric kWh sales by customer class for each of the periods indicated:

*(In thousands, except CDD)*

|  | Revenues Nine Months Ended September 30, 2022 | 2021 | % Change | Sales (kWh) Nine Months Ended September 30, 2022 | 2021 | % Change |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $123,183 | $117,229 | 5.1% | 679,308 | 693,739 | (2.1)% |
| Commercial | 177,877 | 161,270 | 10.3% | 1,368,060 | 1,352,091 | 1.2% |
| Industrial | 10,535 | 9,469 | 11.3% | 120,827 | 122,493 | (1.4)% |
| Other-retail/municipal | 28,215 | 26,340 | 7.1% | 276,843 | 276,950 | —% |
| Total retail | 339,810 | 314,308 | 8.1% | 2,445,038 | 2,445,273 | —% |
| Sales to the market | 13,938 | 8,854 | 57.4% | 121,848 | 201,902 | (39.6)% |
| Other revenues | 1,167 | 948 | 23.1% | — | — | —% |
| Total | $354,915 | $324,110 | 9.5% | 2,566,886 | 2,647,175 | (3.0)% |
| Cooling degree days (normal 690) |  |  |  | 784 | 820 | (4.4)% |

Electric revenue increased $30.8 million during the nine months ended September 30, 2022, compared to the same period in 2021, due to the following:

*(In millions)*

|  |  |
| --- | ---: |
| Rate changes | $27.7 |
| Sales to the market | 5.1 |
| Customer fixed and demand charges | 2.2 |
| Net increase in commercial, industrial and other-retail/municipal volume | 0.7 |
| Other | 0.2 |
| Revenue subject to refund, net | (3.2) |
| Decrease in residential volume | (1.9) |
| Total | $30.8 |

- *Rate changes.* In December 2021, the PSCW authorized MGE to increase 2022 rates for retail electric customers by approximately 8.81%. Rates charged to retail customers during the nine months ended September 30, 2022 were $27.7 million higher than those charged during the same period in the prior year.

See Footnote 9 of the Notes to Consolidated Financial Statements in this Report for further information on rate increase. Any increase in rates associated with fuel or purchase power costs are generally offset in fuel and purchased power costs and do not have a significant impact on net income.

- *Sales to the market.* Sales to the market typically occur when MGE has more generation and purchases in the MISO market than are needed for its customer demand. The excess electricity is then sold to other utilities or power marketers in the MISO market. During the nine months ended September 30, 2022, sales were made at higher market prices and partially offset by decreased market volume compared to the same period in the prior year, reflecting a decrease in sales. The revenue generated from these sales is included in fuel rules monitored costs. See fuel rules discussion in Footnote 9 of the Notes to Consolidated Financial Statements.
- *Customer fixed and demand charges.* During the nine months ended September 30, 2022, fixed and demand charges increased $2.2 million primarily attributable to the increase in demand charges for commercial customers.
- *Revenue subject to refund.* For cost recovery mechanisms, any over-collection of revenues resulting from costs authorized to be collected from customers in rates exceeding actual costs is recorded as a reduction of revenue in the period incurred, as the over-collection is expected to be refunded to customers in a subsequent period. In the year the over-collection is refunded, rates are reduced and offset as revenue subject to refund. There is no net income impact in the year the costs are refunded.
- *Residential volume.* During the nine months ended September 30, 2022, there was an approximately 2% decrease in residential volume driven by a shift in usage patterns reflecting a reduction in remote work associated with the COVID-19 pandemic.

### Electric fuel and purchased power

*(In millions)*

|  | Nine Months Ended September 30, 2022 | 2021 | $ Change |
| --- | ---: | ---: | ---: |
| Fuel for electric generation | $48.4 | $42.6 | $5.8 |
| Purchased power | 35.8 | 28.9 | 6.9 |

The $5.8 million increase in fuel for electric generation was due to an approximately 31% increase in the average cost offset by an approximately 13% decrease in internal generation. Coal transportation constraints resulted in reduced generation at Columbia, which required MGE to purchase power in the market at higher cost.

The $6.9 million increase in purchased power was due to an approximately 43% increase in market purchases as a result of lower internal generation.

Fuel and purchased power costs are generally offset by electric revenue and do not have a significant impact on net income. MGE expects to seek and receive recovery of fuel and purchased power costs outside the fuel rules bandwidth in customer rates. See Footnote 9 of the Notes to Consolidated Financial Statements in this Report for further information on the fuel rules bandwidth.

### Gas deliveries and revenues

The following table compares MGE's gas revenues and gas therms delivered by customer class for each of the periods indicated:

*(In thousands, except HDD and average*

| rate per therm of retail customer) | Revenues Nine Months Ended September 30, 2022 | 2021 | % Change | Therms Delivered Nine Months Ended September 30, 2022 | 2021 | % Change |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $97,498 | $72,286 | 34.9% | 77,091 | 68,791 | 12.1% |
| Commercial/Industrial | 66,913 | 42,972 | 55.7% | 73,349 | 64,179 | 14.3% |
| Total retail | 164,411 | 115,258 | 42.6% | 150,440 | 132,970 | 13.1% |
| Gas transportation | 4,804 | 4,589 | 4.7% | 58,059 | 55,150 | 5.3% |
| Other revenues | 90 | 97 | (7.2)% | — | — | —% |
| Total | $169,305 | $119,944 | 41.2% | 208,499 | 188,120 | 10.8% |
| Heating degree days (normal 4,479) |  |  |  | 4,723 | 4,404 | 7.2% |
| Average rate per therm of retail customer | $1.093 | $0.867 | 26.1% |  |  |  |

Gas revenue increased $49.4 million during the nine months ended September 30, 2022, compared to the same period in 2021, due to the following:

*(In millions)*

|  |  |
| --- | ---: |
| Rate changes | $38.2 |
| Increase in volume | 9.9 |
| Other | 1.3 |
| Total | $49.4 |

- *Rate changes.* In December 2021, the PSCW authorized MGE to increase 2022 rates for retail gas customers by approximately 2.15%.

MGE recovers the cost of natural gas in its gas segment through the purchased gas adjustment clause (PGA). Under the PGA, MGE is able to pass through to its gas customers the cost of gas. Changes in PGA recoveries affect revenues but do not change net income in view of the pass-through treatment of the costs. Payments for natural gas increased driving higher rates during the nine months ended September 30, 2022.

The average retail rate per therm for the nine months ended 2022, increased approximately 26% compared to 2021, reflecting a $42.9 million increase in natural gas commodity costs (recovered through the PGA).

- *Volume.* For 2022, retail gas deliveries increased approximately 13% compared to the same period in the prior year primarily related to favorable weather conditions in the current year.
- *Other.* Other revenues increased primarily related to increase in gas customers in 2022 increasing revenue recorded for fixed customer charge compared to the same period in the prior year.

### Cost of gas sold

The $42.9 million increase in cost of gas sold was driven by higher cost per therm of gas. Average cost per therm increased approximately 56%. An increase in volume of approximately 12% also contributed to the increase in cost. MGE recovers the cost of natural gas in its gas segment through the PGA as described under gas deliveries and revenue above.

### Consolidated operations and maintenance expenses

During the nine months ended September 30, 2022, operations and maintenance expenses increased $6.1 million, compared to the same period in the prior year. The following contributed to the net change:

*(In millions)*

|  |  |
| --- | ---: |
| Increased administrative and general costs | $4.2 |
| Increased customer accounts costs | 2.6 |
| Increased electric distribution expenses | 0.5 |
| Increased other expenses | 0.5 |
| Decreased electric production expenses | (1.3) |
| Decreased customer services | (0.4) |
| Total | $6.1 |

- Increased administration and general costs are primarily related to increase in pension and OPEB service costs.
- Increased customer accounts costs are related to increased costs associated with the new customer information system, which went live in September 2021.
- Decreased electric production expenses are primarily related to lower Columbia costs. A $2.6 million additional expense was recorded in 2021 for Columbia inventory obsolescence and employee severance reserves associated with the Columbia retirement. MGE expects to request PSCW approval for regulatory recovery of these costs at a future date. The decrease in costs is offset by increased maintenance costs for Blount, Saratoga, Two Creeks, and Badger Hollow I.

### Consolidated depreciation expense

Electric depreciation expense increased $5.7 million and gas depreciation expense increased $2.2 million during the nine months ended September 30, 2022, compared to the same period in the prior year. MGE placed Badger Hollow I in service in November 2021. The timing of the in-service date contributed to the increase in electric depreciation expense. The new customer information system went live in September 2021, which increased depreciation expense for both electric and gas in 2022.

### Electric and gas other income

Electric other income increased $2.3 million and gas other income increased $3.7 million during the nine months ended September 30, 2022, compared to the same period in the prior year, primarily related to the collection in 2021 of the deferred pension and other postretirement other than service costs from 2019.

### Nonregulated Energy Operations - MGE Energy and MGE

The nonregulated energy operations are conducted through MGE Energy's subsidiaries: MGE Power Elm Road (the Elm Road Units) and MGE Power West Campus (WCCF), which have been formed to own and lease electric generating capacity to assist MGE. During the nine months ended September 30, 2022 and 2021, net income at the nonregulated energy operations segment was $16.5 million and $15.9 million, respectively.

### Transmission Investment Operations - MGE Energy

The transmission investment segment holds our interest in ATC and ATC Holdco, and its income reflects our equity in the earnings of those investments. ATC Holdco was formed in December 2016 to pursue transmission development opportunities that typically have long development and investment lead times before becoming operational. ATC Holdco's transmission development activities have been suspended for the near term. During the nine months ended September 30, 2022 and 2021, other income at the transmission investment segment primarily reflects ATC's operations and was $6.6 million and $7.4 million, respectively. In August 2022, the U.S. Court of Appeals for the D.C. Circuit vacated the underlying FERC orders regarding methodology for setting authorized return on equity resulting in an additional estimated possible loss. See Footnote 3 of the Notes to Consolidated Financial Statements in this Report and "Other Matters" below for additional information concerning ATC and summarized financial information regarding ATC.

### Consolidated Income Taxes - MGE Energy and MGE

In 2022, the effective electric tax rate increased as a result of the return of electric excess deferred taxes related to the 2017 Tax Act not governed by IRS normalization rules in 2021. These costs were recorded as a regulatory liability in the year of remeasurement. See Footnote 4 of the Notes to Consolidated Financial Statements in this Report for the effective tax rate reconciliation.

### Noncontrolling Interest, Net of Tax - MGE

Noncontrolling interest, net of tax, reflects the accounting required for MGE Energy's interest in MGE Power Elm Road (the Elm Road Units) and MGE Power West Campus (WCCF). MGE Energy owns 100% of MGE Power Elm Road and MGE Power West Campus. They are not owned by MGE. Due to the contractual agreements for these projects with MGE, the entities are considered VIEs with respect to MGE and their results are consolidated with those of MGE, the primary beneficiary of the VIEs. The following table shows MGE Energy's noncontrolling interest, net of tax, reflected on MGE's consolidated statement of income:

*(In millions)*

|  | Nine Months Ended September 30, 2022 | 2021 |
| --- | ---: | ---: |
| MGE Power Elm Road | $10.5 | $11.4 |
| MGE Power West Campus | 5.4 | 5.4 |

### Contractual Obligations and Commercial Commitments - MGE Energy and MGE

There were no material changes, other than from the normal course of business, to MGE Energy's and MGE's contractual obligations (representing cash obligations that are considered to be firm commitments) and commercial commitments (representing commitments triggered by future events) during the nine months ended September 30, 2022, except as noted below. Further discussion of the contractual obligations and commercial commitments is included in Footnote 16 of the Notes to Consolidated Financial Statements and "Contractual Obligations and Commercial Commitments for MGE Energy and MGE" under "Management's Discussion and Analysis of Financial Condition and Results of Operations" in the 2021 Annual Report on Form 10-K.

### Purchase Contracts – MGE Energy and MGE

See Footnote 8.c. of Notes to Consolidated Financial Statements in this Report for a description of commitments as of September 30, 2022, that MGE Energy and MGE have entered with respect to various commodity supply and transportation contracts to meet their obligations to deliver electricity and natural gas to customers.

### Long-term Debt – MGE Energy and MGE

In November 2022, MGE entered into a private placement Note Purchase Agreement in which it committed to issue $75 million of new long-term debt. See Footnote 6.c. of Notes to Consolidated Financial Statements in this Report for further information on long-term debt issuance.

### Liquidity and Capital Resources

MGE Energy and MGE expect to have adequate liquidity to support future operations and capital expenditures over the next twelve months. Available resources include cash and cash equivalents, operating cash flows, liquid assets, borrowing working capacity under revolving credit facilities, and access to equity and debt capital markets. MGE Energy expects to generate funds from operations and both long-term and short-term debt financing. See "Credit Facilities" under Part II, Item 7, Management's Discussion and Analysis of Financial Condition and Results of Operations – Liquidity and Capital Resources in the 2021 Annual Report on Form 10-K for information regarding MGE Energy's and MGE's credit facilities.

### Cash Flows

The following summarizes cash flows for MGE Energy and MGE during the nine months ended September 30, 2022 and 2021:

*(In thousands)*

| Cash provided by (used for): | MGE Energy 2022 | 2021 | MGE 2022 | 2021 |
| --- | ---: | ---: | ---: | ---: |
| Operating activities | $144,282 | $141,297 | $141,786 | $135,451 |
| Investing activities | (137,219) | (118,347) | (134,089) | (115,591) |
| Financing activities | (12,663) | 1,656 | (8,400) | 31,930 |

### Cash Provided by Operating Activities

### MGE Energy

MGE Energy's consolidated net cash provided by operating activities is derived mainly from the electric and gas operations of its principal subsidiary, MGE.

Cash provided by operating activities during the nine months ended September 30, 2022, was $144.3 million, an increase of $3.0 million when compared to the same period in the prior year.

MGE Energy's net income decreased $2.8 million during the nine months ended September 30, 2022, when compared to the same period in the prior year.

MGE Energy's federal and state taxes paid decreased $3.0 million during the nine months ended September 30, 2022, when compared to the prior year.

Working capital accounts (excluding prepaid and accrued taxes) resulted in $17.7 million in cash used for operating activities during the nine months ended September 30, 2022. Working capital accounts were impacted by increased gas inventory driven by the increase in cost of gas and decreased other current liabilities, partially offset by decreased unbilled revenues.

Working capital accounts (excluding prepaid and accrued taxes) resulted in $9.1 million in cash used for operating activities during the nine months ended September 30, 2021. Actual purchased gas costs were $6.3 million higher than the amount collected in rates primarily due to the extreme cold weather experienced in the U.S. in February 2021. These costs were deferred as a regulatory asset and recovered throughout 2021. In addition, working capital accounts were impacted by increased accounts receivable and increased inventories, partially offset by increased other current liabilities, decreased unbilled revenues, and increased accounts payable.

Hosted software asset expenditures during the nine months ended September 30, 2022, were $0.5 million. This amount represents a decrease of $2.5 million of cash used when compared to the prior year.

### MGE

Cash provided by operating activities during the nine months ended September 30, 2022, was $141.8 million, an increase of $6.3 million when compared to the same period in the prior year.

Net income decreased $3.0 million during the nine months ended September 30, 2022, when compared to the same period in the prior year.

MGE's federal and state taxes paid decreased $4.2 million during the nine months ended September 30, 2022, when compared to the prior year.

Working capital accounts (excluding prepaid and accrued taxes) resulted in $15.3 million in cash used for operating activities during the nine months ended September 30, 2022. Working capital accounts were impacted by increased gas inventory driven by the increase in cost of gas and decreased current liabilities, partially offset by decreased unbilled revenues.

Working capital accounts (excluding prepaid and accrued taxes) resulted in $9.1 million in cash used for operating activities during the nine months ended September 30, 2021. Actual purchased gas costs were $6.3 million higher than the amount collected in rates primarily due to the extreme cold weather experienced in the U.S. in February 2021. These costs were deferred as a regulatory asset and recovered throughout 2021. In addition, working capital accounts were impacted by increased accounts receivable and increased inventories, partially offset by increased other current liabilities, decreased unbilled revenues, and increased accounts payable.

Hosted software asset expenditures during the nine months ended September 30, 2022, were $0.5 million. This amount represents a decrease of $2.5 million of cash used when compared to the prior year.

### Capital Requirements and Investing Activities

### MGE Energy

MGE Energy's cash used for investing activities increased $18.9 million during the nine months ended September 30, 2022, when compared to the same period in the prior year.

Capital expenditures during the nine months ended September 30, 2022, were $133.4 million. This amount represents an increase of $19.3 million from the expenditures made in the same period in the prior year. This increase primarily reflects the increase of expenditures for Badger Hollow II and Paris.

Proceeds from the sale of investments decreased $0.8 million during the nine months ended September 30, 2022, when compared to the same period in the prior year.

### MGE

MGE's cash used for investing activities increased $18.5 million during the nine months ended September 30, 2022, when compared to the same period in the prior year.

Capital expenditures during the nine months ended September 30, 2022, were $133.4 million. This amount represents an increase of $19.3 million from the expenditures made in the same period in the prior year. This increase primarily reflects the increase of expenditures for Badger Hollow II and Paris.

### Capital Expenditures

The following table shows MGE Energy's forecasted capital expenditures for 2022 through 2025:

*(In thousands)*

|  | Forecasted 2022(a) | 2023 | 2024 | 2025 |
| --- | ---: | ---: | ---: | ---: |
| Electric | $138,200 | $181,000 | $185,100 | $174,400 |
| Gas | 25,300 | 26,200 | 25,600 | 23,200 |
| Utility plant total | 163,500 | 207,200 | 210,700 | 197,600 |
| Nonregulated | 7,700 | 7,900 | 7,800 | 6,100 |
| MGE Energy total | $171,200 | $215,100 | $218,500 | $203,700 |

(a) Includes actual capital expenditures already incurred in 2022 and estimated capital expenditures for the remainder of the year.

Forecasted capital expenditures are based upon management's assumptions with respect to future events, including the timing and amount of expenditures associated with environmental compliance initiatives, legislative and regulatory action, supply chain and market disruptions, customer demand and support for electrification and renewable energy resources, energy conservation programs, load growth, the timing of any required regulatory approvals, and the adequacy of rate recovery. Actual events may differ materially from these assumptions and result in material changes to those forecasted amounts.

MGE is targeting at least 80% carbon reduction from electric generation by 2030 (from 2005 levels) and net-zero carbon electricity by 2050. Solar, wind, and battery storage projects are a major step toward deep decarbonization and greater use of clean energy sources in pursuit of our goal. MGE continues to evaluate solar, wind, and battery storage projects that align with its goals as legacy fossil fuel-fired facilities are retired. The target early retirement date for Columbia is June 2026. MGE has included forecasted capital expenditures for the years 2022 through 2025 for projects to replace Columbia's generation. Additional replacement capital expenditures are expected to continue beyond 2025.

Our forecasted capital expenditures reflect the following significant renewable projects that are proposed or currently under construction:

| Project | Source | Ownership Interest | Share of Generation/ Battery Storage | Share of Estimated Costs(c) | Estimated Date of Commercial Operation |
| --- | --- | ---: | --- | --- | --- |
| Red Barn(a) | Wind | 10% | 9.16MW | $18 million(e) | Early 2023 |
| Badger Hollow II(a) | Solar | 33% | 50 MW | $76 million(d)(e) | First Half of 2023 |
| Paris(a) | Solar/Battery | 10% | 31 MW | $51 million(d)(e) | 2023(f) |
| Darien(b) | Solar/Battery | 10% | 25MW/7.5MW | $45 million(d) | 2024(f) |
| Koshkonong(b) | Solar/Battery | 10% | 30MW/16.5MW | $65 million(d) | 2025(f) |

(a) Approved by the PSCW.

(b) Pending approval by the PSCW. There is no certainty that this project will be approved by the PSCW.

(c) Excluding AFUDC.

(d) Requested, in the case of projects pending PSCW approval, or received, in the case of Badger Hollow II and Paris, approval to recover 100% AFUDC.

(e) See Footnote 12 of Notes to Consolidated Financial Statements in the Report for information on costs incurred.

(f) Battery storage timing to be determined.

In 2022, MGE notified the PSCW of increases in projected costs at Badger Hollow II and Paris. The main drivers were increases in the costs of key commodities, labor, and solar modules resulting from supply chain and market disruptions. See Footnote 12 of Notes to Consolidated Financial Statements in this Report for more information on these projects. Furthermore, solar procurement disruptions have also shifted construction timelines for Darien and Koshkonong. Projected completion dates of these projects are one year later than originally anticipated. MGE continues to assess the potential impact of these disruptions on current and future solar projects which may result in an increase in costs or delays in construction timelines. See further information on procurement disruptions discussed earlier under "Executive Overview."

West Riverside: In 2016, MGE entered into an agreement with WPL under which MGE may acquire up to 50 MW of capacity in a gas-fired generating plant constructed by WPL at its West Riverside Energy Center in Beloit, Wisconsin, during the five-year period following the in-service date of the plant. The plant was placed in service in May 2020. In January 2022, MGE, along with joint applicants, filed an application with the PSCW requesting approval for a sale and purchase of ownership interests in West Riverside. If approved, MGE's share of West Riverside will be 25 MW at a purchase price of approximately $25 million. The closing and actual transfer of ownership is expected to occur in March 2023. MGE also retains the option to purchase an additional 25 MW of capacity from West Riverside until May 2025. MGE currently expects to exercise this option in a future period.

Electric and Gas Distribution: In 2022 through 2025, electric and gas capital expenditures include investment in enhanced metering solutions to provide customers with more timely and detailed energy use information. Investments in advanced metering infrastructure will provide additional benefits including outage and demand response and automated meter reading capabilities. Forecasted capital expenditures in those years is approximately $24 million.

### Cash Used for/Provided by Financing Activities

### MGE Energy

Cash used for MGE Energy's financing activities was $12.7 million during the nine months ended September 30, 2022, compared to cash proceeds of $1.7 million for the same period in the prior year.

During the nine months ended September 30, 2022, dividends paid were $42.8 million compared to $40.8 million in the prior year. The increase reflected a higher dividend rate per share ($1.183 vs. $1.128).

During the nine months ended September 30, 2021, MGE borrowed $100.0 million of senior unsecured notes which was used to assist with financing additional capital expenditures and other corporate obligations. There were no long-term debt borrowings during the nine months ended September 30, 2022.

During the nine months ended September 30, 2022, net short-term debt borrowings were $34.5 million, compared to $52.5 million of repayments in the same period in the prior year.

### MGE

During the nine months ended September 30, 2022, cash used for MGE's financing activities was $8.4 million, compared to cash proceeds of $31.9 million for the same period in the prior year.

Cash dividends to parent (MGE Energy) were $21.0 million during the nine months ended September 30, 2022. There were no cash dividends to parent in the same period in the prior year.

Distributions to parent from noncontrolling interest, which represent distributions from MGE Power Elm Road and MGE Power West Campus to MGE Energy, were $17.5 million during the nine months ended September 30, 2022, compared to $10.5 million in the same period in the prior year.

During the nine months ended September 30, 2021, MGE borrowed $100.0 million of senior unsecured notes which was used to assist with financing additional capital expenditures and other corporate obligations. There were no long-term debt borrowings during the nine months ended September 30, 2022.

During the nine months ended September 30, 2022, net short-term debt borrowings were $34.5 million, compared to $52.5 million of repayments in the same period in the prior year.

### Capitalization Ratios

MGE Energy's capitalization ratios were as follows:

|  | MGE Energy September 30, 2022 | December 31, 2021 |
| --- | ---: | ---: |
| Common shareholders' equity | 62.1% | 62.2% |
| Long-term debt(a) | 35.6% | 37.5% |
| Short-term debt | 2.3% | 0.3% |

(a) Includes the current portion of long-term debt.

### Credit Ratings

MGE Energy's and MGE's access to the capital markets, including, in the case of MGE, the commercial paper market, and their respective financing costs in those markets, may depend on the credit ratings of the entity that is accessing the capital markets.

None of MGE Energy's or MGE's borrowing is subject to default or prepayment as a result of a downgrading of credit ratings, although a downgrading of MGE's credit ratings would increase fees and interest charges under both MGE Energy's and MGE's credit agreements.

### Environmental Matters

See the discussion of environmental matters included in the 2021 Annual Report on Form 10-K, as updated by Footnote 8.a. of Notes to Consolidated Financial Statements in this Report.

### Other Matters

### Rate Matters

In December 2021, the PSCW approved a settlement agreement for MGE's 2022 rate case. The settlement agreement provides for an 8.81% increase to electric rates and a 2.15% increase to gas rates for 2022. As part of that settlement agreement, the PSCW approved a 0.96% increase in 2023 gas rates and a potential 2023 electric rate change to be addressed through a limited rate case reopener.

In April 2022, MGE filed with the PSCW a limited rate reopener proposing a 4.38% increase to electric rates for 2023.

Details related to MGE's 2022/2023 approved settlement agreement and pending electric limited reopener:

*(Dollars in thousands)*

|  | Authorized Average Rate Base(a) | Authorized Average CWIP(b) | Authorized Return on Common Equity(c) | Common Equity Component of Regulatory Capital Structure | Effective Date |
| --- | ---: | ---: | ---: | ---: | --- |
| Electric (2022 Test Period) | $1,044,362 | $19,976 | 9.8% | 55.63% | 1/1/2022 |
| Gas (2022 Test Period) | $299,319 | $11,410 | 9.8% | 55.63% | 1/1/2022 |
| Electric (2023 Test Period)(d) | $1,159,155 | $19,976 | 9.8% | 55.63% | 1/1/2023 |
| Gas (2023 Test Period) | $312,270 | $8,228 | 9.8% | 55.63% | 1/1/2023 |

(a) Average rate base amounts reflect MGE's allocated share of rate base and do not include construction work in progress (CWIP) or a cash working capital allowance and were calculated using a forecasted 13-month average for the test periods. The PSCW provides a return on selected CWIP and a cash working capital allowance by adjusting the percentage return on rate base.

(b) 50% of the forecasted 13-month average CWIP for the test periods which earns an AFUDC return. Projects eligible to earn 100% AFUDC are excluded from this balance and discussed further in the Management Discussion and Analysis of Financial Condition and Results of Operations - Executive Overview section.

(c) Authorized returns on common equity may not be indicative of actual returns earned or projections of future returns, as actual returns will be affected by the volume of electricity or gas sold.

(d) Pending approval by the PSCW.

See Footnote 9 of Notes to Consolidated Financial Statements in this Report for further discussion of rate proceedings.

### ATC

MISO transmission owners, including ATC, are involved in two complaints filed at FERC by several parties challenging that the base ROE in effect for MISO transmission owners, including ATC, was no longer just and reasonable. Each complaint provided for a 15-month statutory refund period: November 12, 2013 through February 11, 2015 (the "First Complaint Period") and February 12, 2015 through May 11, 2016 (the "Second Complaint Period").

In May 2020, FERC issued an order further refining the methodology for setting authorized ROE. This refined methodology increased the authorized ROE from 9.88% to 10.02%. This base ROE is effective for the First Complaint Period and for all periods following September 2016. This order also dismissed the second complaint. Accordingly, no refunds were ordered for the Second Complaint Period.

As a result of the May 2020 FERC order, our share of ATC's earnings reflected a $0.6 million reduction of our reserve. Additionally, our share of ATC's earnings reflected the derecognition of a possible refund related to the Second Complaint Period as ATC considered such a refund to be no longer probable. However, due to pending requests for rehearing, a loss related to the 2015 complaint remains possible. Our share of the estimated refund for the Second Complaint Period is approximately $2.3 million. MGE has not recorded a possible loss for the Second Complaint Period.

Several petitions for review of FERC’s prior orders were filed with the U.S. Court of Appeals for the D.C. Circuit (the "Court") and an oral argument was held in November 2021. In August 2022, the Court ruled that four of the five arguments made by the complaining parties were unpersuasive. However, the Court agreed that FERC’s decision to reintroduce a risk-premium model into its ROE methodology was arbitrary and capricious. The Court vacated the underlying orders for the First Complaint Period and remanded to FERC for further proceedings. In September 2022, our share of ATC's earnings reflected an estimated possible loss of approximately $0.8 million, inclusive of interest and net of tax, for a possible additional refund for the First Complaint Period and for the period following the Second Complaint Period. Although the Court agreed that FERC was correct to use the base ROE established in the first complaint to adjudicate the second, and that FERC was right to dismiss the second complaint, the second complaint was also remanded for FERC to reopen proceedings. Any reduction in ATC's ROE could result in lower equity earnings and distributions from ATC in the future.

We derived approximately 5.1% and 5.7% of our net income during the nine months ended September 30, 2022 and 2021, respectively, from our investment in ATC.

### Inflation Reduction Act

In August 2022, the Inflation Reduction Act (IRA) was signed into law. Among other provisions, the IRA: extends current PTC and ITC for renewable technologies (e.g., wind and solar); restores full value of the PTC and ITC for qualifying facilities placed into service after 2021 that satisfy prevailing wage and apprenticeship requirements; creates a PTC for solar, clean hydrogen and nuclear; establishes an ITC for energy storage, microgrids, and interconnection facilities; and allows companies to monetize or sell credits to unrelated parties. In addition, the IRA created a new corporate alternative minimum tax (AMT). MGE Energy does not expect to be subject to the AMT in the near term. Implementation of IRA provisions is subject to the issuance of additional guidance by the U.S. Treasury Department. While the final impact cannot be determined at this time, the IRA is not expected to have a material impact on MGE Energy and MGE for the year ending December 31, 2022.

### Adoption of Accounting Principles and Recently Issued Accounting Pronouncements

See Footnote 2 of Notes to Consolidated Financial Statements in this Report for discussion of new accounting pronouncements.

## Market risk

As filed, 699 characters.

There were no material changes to the market risks disclosed in Item 7A. Quantitative and Qualitative Disclosures About Market Risk in our 2021 Annual Report on Form 10-K, except as noted below.

### Equity Price Risk - Pension-Related Assets

MGE currently funds its liabilities related to employee benefits through trust funds. These funds, which include investments in debt and equity securities, are managed by various third-party investment managers. Changes in the market value of these investments can have an impact on the future expenses related to these liabilities. The value of employee benefit plan assets has declined by approximately 23% during the nine months ended September 30, 2022.

## Controls and procedures

As filed, 2,227 characters.

During the third quarter of 2022, each registrant's management, including the principal executive officer and principal financial officer, evaluated its disclosure controls and procedures related to the recording, processing, summarization, and reporting of information in its periodic reports that it files with the SEC. These disclosure controls and procedures have been designed to ensure that material information relating to that registrant, including its subsidiaries, is accumulated and made known to that registrant's management, including these officers, by other employees of that registrant and its subsidiaries as appropriate to allow timely decisions regarding required disclosure, and that this information is recorded, processed, summarized, evaluated, and reported, as applicable, within the time periods specified in the SEC's rules and forms. The evaluations take into account changes in the internal and external operating environments that may impact those controls and procedures. Due to the inherent limitations of control systems, not all misstatements may be detected. These inherent limitations include the realities that judgments in decision making can be faulty and breakdowns can occur because of simple error or mistake. Additionally, controls can be circumvented by the individual acts of some persons, by collusion of two or more people, or by management override of the control. Also, MGE Energy does not control or manage certain of its unconsolidated entities and thus, its access and ability to apply its procedures to those entities is more limited than is the case for its consolidated subsidiaries.

As of September 30, 2022, each registrant's principal executive officer and principal financial officer concluded that its disclosure controls and procedures were effective. Each registrant intends to strive continually to improve its disclosure controls and procedures to enhance the quality of its financial reporting.

During the quarter ended September 30, 2022, there were no changes in either registrant's internal controls over financial reporting that materially affected, or are reasonably likely to affect materially, that registrant's internal control over financial reporting.

## Risk factors

As filed, 127 characters.

There were no material changes from the risk factors disclosed in Item 1A. Risk Factors in our 2021 Annual Report on Form 10-K.

Filed Nov 3, 2022.
Source: SEC EDGAR, the filing index for accession 0000950170-22-021653. Last ingested by Listed: Nov 5, 2026, 13:34 ET. No prices; not investment advice.