# PG&E Corp: Form 10-Q for the period ended Sep 30, 2019

- Company: [PG&E Corp](/companies/pcg.md) (CIK 1004980)
- Form: 10-Q
- Filed: 2019-11-07
- Accepted by EDGAR: Nov 7, 2019, 08:51 ET
- Period: 2019-09-30
- Accession: 0001004980-19-000046
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/1004980/000100498019000046/pcg-20190930.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/1004980/000100498019000046/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2019-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2019-07-01 to 2019-09-30 | $4.43bn | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Revenue | 9 months, 2019-01-01 to 2019-09-30 | $12.39bn | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Operating income | 3 months, 2019-07-01 to 2019-09-30 | −$2.30bn | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2019-01-01 to 2019-09-30 | −$5.75bn | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2019-07-01 to 2019-09-30 | $52.0m | us-gaap:InterestExpense |
| Interest expense | 9 months, 2019-01-01 to 2019-09-30 | $215.0m | us-gaap:InterestExpense |
| Income tax | 3 months, 2019-07-01 to 2019-09-30 | −$729.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2019-01-01 to 2019-09-30 | −$1.93bn | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2019-07-01 to 2019-09-30 | −$1.62bn | us-gaap:ProfitLoss |
| Net income | 9 months, 2019-01-01 to 2019-09-30 | −$4.03bn | us-gaap:ProfitLoss |
| Diluted EPS | 3 months, 2019-07-01 to 2019-09-30 | −$3.06 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2019-01-01 to 2019-09-30 | −$7.65 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2019-07-01 to 2019-09-30 | −$3.06 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2019-01-01 to 2019-09-30 | −$7.65 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2019-07-01 to 2019-09-30 | 529,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2019-01-01 to 2019-09-30 | 528,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2019-01-01 to 2019-09-30 | $4.07bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2019-01-01 to 2019-09-30 | $4.19bn | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | at 2019-09-30 | $2.97bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2019-09-30 | $11.58bn | us-gaap:AssetsCurrent |
| Total assets | at 2019-09-30 | $85.71bn | us-gaap:Assets |
| Current liabilities | at 2019-09-30 | $6.47bn | us-gaap:LiabilitiesCurrent |
| Current portion of debt | at 2019-09-30 | $0 | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | at 2019-09-30 | $0 | us-gaap:ShortTermBorrowings |
| Shareholders' equity | at 2019-09-30 | $8.74bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 190,318 characters.

### OVERVIEW

PG&E Corporation is a holding company whose primary operating subsidiary is Pacific Gas and Electric Company, a public utility serving northern and central California. The Utility generates revenues mainly through the sale and delivery of electricity and natural gas to customers.

The Utility is regulated primarily by the CPUC and the FERC. The CPUC has jurisdiction over the rates, terms, and conditions of service for the Utility’s electricity and natural gas distribution operations, electric generation, and natural gas transportation and storage. The FERC has jurisdiction over the rates and terms and conditions of service governing the Utility’s electric transmission operations and interstate natural gas transportation contracts. The NRC oversees the licensing, construction, operation, and decommissioning of the Utility’s nuclear generation facilities. The Utility is also subject to the jurisdiction of other federal, state, and local governmental agencies.

This is a combined quarterly report of PG&E Corporation and the Utility and should be read in conjunction with each company’s separate Condensed Consolidated Financial Statements and the Notes to the Condensed Consolidated Financial Statements included in this quarterly report. It also should be read in conjunction with the 2018 Form 10-K.

### Chapter 11 Proceedings

On the Petition Date, PG&E Corporation and the Utility filed voluntary petitions for relief under Chapter 11 in the Bankruptcy Court. PG&E Corporation’s and the Utility’s Chapter 11 Cases are being jointly administered under the caption In re: PG&E Corporation and Pacific Gas and Electric Company, Case No. 19-30088 (DM). For additional information regarding the Chapter 11 Cases, refer to the website maintained by Prime Clerk, LLC, PG&E Corporation’s and the Utility’s claims and noticing agent, at http://restructuring.primeclerk.com/pge.

For more information about the Chapter 11 Cases, see “Item 1A. Risk Factors – Risks Related to Chapter 11 Proceedings and Liquidity” and “Item 7. MD&A – Chapter 11 Proceedings” in the 2018 Form 10-K and Notes 2 and 5 of the Notes to the Condensed Consolidated Financial Statements in Item 1 of this Form 10-Q.

### Going Concern

The accompanying Condensed Consolidated Financial Statements to this Form 10-Q have been prepared on a going concern basis, which contemplates the continuity of operations, the realization of assets and the satisfaction of liabilities in the normal course of business. However, PG&E Corporation and the Utility are facing extraordinary challenges relating to a series of catastrophic wildfires that occurred in Northern California in 2017 and 2018. As a result of these challenges, such realization of assets and satisfaction of liabilities are subject to uncertainty. For more information about the 2018 Camp fire and 2017 Northern California wildfires, see Note 10 of the Notes to the Condensed Consolidated Financial Statements and the 2018 Form 10-K.

Management has concluded that uncertainty regarding these matters raises substantial doubt about PG&E Corporation’s and the Utility’s ability to continue as going concerns, and their independent registered public accountants included an explanatory paragraph in their auditors’ reports relating to the consolidated balance sheets of PG&E Corporation and the Utility as of December 31, 2018 and 2017, and the related consolidated statements of income, comprehensive income, equity, and cash flows, for each of the three years in the period ended December 31, 2018, included in the 2018 Form 10-K, which stated certain conditions exist which raise substantial doubt about PG&E Corporation’s and the Utility’s ability to continue as going concerns in relation to the foregoing. The Condensed Consolidated Financial Statements do not include any adjustments that might result from the outcome of these uncertainties. For more information about these matters, see Notes 1 and 2 to the Condensed Consolidated Financial Statements and the 2018 Form 10-K.

### Summary of Changes in Net Income and Earnings per Share

PG&E Corporation’s net loss was $1.6 billion and $4.0 billion in the three and nine months ended September 30, 2019, respectively, compared to net income of $564 million and $22 million in the same periods in 2018. PG&E Corporation recognized charges of $526 million and $2.0 billion associated with the 2018 Camp fire and the 2017 Northern California wildfires, respectively, for the three months ended September 30, 2019, with no corresponding charges during the same period in 2018. PG&E Corporation recognized charges of $2.4 billion and $4.0 billion associated with the 2018 Camp fire and the 2017 Northern California wildfires, respectively, for the nine months ended September 30, 2019, compared to charges of $2.1 billion, net of probable insurance recoveries of $385 million, associated with the 2017 Northern California wildfires during the same period in 2018.

### Key Factors Affecting Financial Results

PG&E Corporation and the Utility believe that their financial condition, results of operations, liquidity, and cash flows may be materially affected by the following factors:

- *The Outcome of the Chapter 11 Cases.* For the duration of the Chapter 11 Cases, PG&E Corporation’s and the Utility’s business is subject to the risks and uncertainties of bankruptcy. For example, the Chapter 11 Cases could adversely affect the Utility’s relationships with suppliers and employees which, in turn, could adversely affect the value of the business and assets of PG&E Corporation and the Utility. PG&E Corporation and the Utility also have incurred and expect to continue to incur increased legal and other professional costs associated with the Chapter 11 Cases and the reorganization. At this time, it is not possible to predict with certainty the effect of the Chapter 11 Cases on their business or various creditors, or whether or when PG&E Corporation and the Utility will emerge from bankruptcy. PG&E Corporation’s and the Utility’s future financial condition, results of operations, liquidity and cash flows depend upon confirming, and successfully implementing, on a timely basis, a plan of reorganization. On October 9, 2019, the Bankruptcy Court entered an order granting the motion of the TCC and the Ad Hoc Noteholder Committee to terminate the exclusive rights of PG&E Corporation and the Utility to file a plan of reorganization as to the TCC and the Ad Hoc Noteholder Committee. On October 17, 2019, the TCC and the Ad Hoc Noteholder Committee filed the TCC/Ad Hoc Noteholder Plan. (See Note 2 of the Notes to the Condensed Consolidated Financial Statements in Item 1.) The resulting competing plan process could reduce the likelihood that the plan of reorganization that is ultimately approved by the CPUC and confirmed by the Bankruptcy Court is one filed by PG&E Corporation and the Utility and, in any event, could have a material effect on PG&E Corporation’s and the Utility’s ability to achieve confirmation of a plan of reorganization that would enable PG&E Corporation and the Utility to reach their stated goals.

If the TCC/Ad Hoc Noteholder Plan were consummated, holders of PG&E Corporation common stock would experience extreme dilution in their percentage ownership of PG&E Corporation and the value of their shares. Under the TCC/Ad Hoc Noteholder Plan, post-emergence, the pre-petition holders of PG&E Corporation common stock would hold approximately 0.1% of the total outstanding PG&E Corporation common stock (with the balance of the post-emergence PG&E Corporation common stock held (i) 59.3% by certain members of the Ad Hoc Noteholder Committee (with pre-emergence holders of PG&E Corporation common stock potentially being afforded the opportunity to make up to 5% of this investment through a rights offering) and (ii) 40.6% by one or both of the wildfire claimholder trusts). The TCC and Ad Hoc Noteholder Committee have requested that the Bankruptcy Court expedite the confirmation process of the TCC/Ad Hoc Noteholder Plan on a faster timetable than the Proposed Plan. As the TCC/Ad Hoc Noteholder Plan progresses through the Chapter 11 process, such progress could have a material adverse effect on PG&E Corporation’s stock price. Finally, it is possible that the changes in ownership contemplated by the TCC/Ad Hoc Noteholder Plan would result in an “ownership change” within the meaning of Section 382 of the Internal Revenue Code (and regulations thereunder), which could result in limitations on PG&E Corporation or the Utility to utilize their net operating loss carryforwards.

- *The Utility’s Ability to Fund Ongoing Operations and Other Capital Needs.* In connection with the Chapter 11 Cases, PG&E Corporation and the Utility entered into the DIP Credit Agreement, which was approved on a final basis on March 27, 2019. For the duration of the Chapter 11 Cases, PG&E Corporation and the Utility expect that the DIP Credit Agreement, together with cash on hand and cash flow from operations, will be the Utility’s primary source of capital to fund ongoing operations and other capital needs and that they will have limited, if any, access to additional financing. In the event that cash on hand, cash flow from operations, and availability under the DIP Credit Agreement are not sufficient to meet liquidity needs, PG&E Corporation and the Utility may be required to seek additional financing, and can provide no assurance that additional financing would be available or, if available, offered on acceptable terms. The amount of any such additional financing could be limited by negative covenants in the DIP Credit Agreement, which include restrictions on PG&E Corporation’s and the Utility’s ability to, among other things, incur additional indebtedness and create liens on assets.
- *The Impact of the 2018 Camp Fire and the 2017 Northern California Wildfires.* PG&E Corporation and the Utility face several uncertainties in connection with the 2018 Camp fire and 2017 Northern California wildfires, related to:
- the amount of possible loss related to third-party claims (as of September 30, 2019, the Utility had incurred aggregate losses of $20.4 billion for claims in connection with the 2018 Camp fire and the 2017 Northern California wildfires, which reflects the low end of the range of reasonably estimated probable losses and is subject to change based on additional information), which aggregate possible losses, if the Utility were found liable for certain or all of the costs, expenses and other losses in connection with the 2018 Camp fire and 2017 Northern California wildfires could exceed $30 billion (not including potential punitive damages, fines and penalties or damages related to future claims);
- whether, in light of the CPUC July 8, 2019 final decision in the CHT OIR that excludes companies in Chapter 11 from accessing the CHT, the Utility will be able to obtain a substantial recovery of costs related to the 2017 Northern California wildfires;
- the impact of investigations, including criminal, regulatory, and SEC investigations;
- the outcome of the 2017 Northern California Wildfires OII, and any resulting fines or penalties;
- fines or penalties, which could be material, if any regulatory or law enforcement agency were to bring an enforcement action, including a criminal proceeding, and determine that the Utility had failed to comply with applicable laws and regulations;
- the amount of punitive damages, fines and penalties, or damages in respect of future claims, which could be material;
- the applicability of the doctrine of inverse condemnation in the 2018 Camp fire and 2017 Northern California wildfires litigation, which the Utility is continuing to challenge by filing a brief on the inverse condemnation cause of action with the Bankruptcy Court on October 25, 2019;
- the applicability of other theories of liability, including negligence, related to the 2018 Camp fire and 2017 Northern California wildfire claims;
- the recoverability of the above-mentioned costs, even if a court decision imposes liability under the doctrine of inverse condemnation;
- the ability of PG&E Corporation and the Utility to finance costs, expenses and other possible losses in respect of claims related to the 2018 Camp fire and the 2017 Northern California wildfires, through securitization mechanisms or otherwise;
- the amount and recoverability of enhanced and accelerated inspection costs of the Utility’s electric transmission and distribution assets (the Utility incurred costs of $121 million and $606 million for enhanced and accelerated inspection and repair costs for the three and nine months ended September 30, 2019, respectively); and
- the amount and recoverability of clean-up and repair costs (the Utility incurred costs of $1.05 billion for clean-up and repair of the Utility’s facilities through September 30, 2019).

(See Notes 4 and 10 of the Notes to the Condensed Consolidated Financial Statements in Item 1 and Item 1A. Risk Factors in Part II.)

- *The Impact of the 2019 Kincade Fire.* Regardless of whether the Utility is determined to have caused the 2019 Kincade fire, the 2019 Kincade fire is expected to have numerous adverse consequences to PG&E Corporation and the Utility, including, among others:
- PG&E Corporation’s and the Utility’s ability to consummate the Proposed Plan by June 30, 2020 (or at all) could be impaired, and PG&E Corporation and the Utility may not be able to amend the Proposed Plan, or develop another alternative to the Proposed Plan, that could be confirmed by June 30, 2020 (or at all);
- depending on the number and type of structures damaged or destroyed by the 2019 Kincade fire or the amount of post-petition claims against PG&E Corporation or the Utility as a result of the 2019 Kincade fire, PG&E Corporation and the Utility may not be able to satisfy, or obtain a waiver of, the conditions precedent to the commitments under the Backstop Commitment Letters or the Debt Commitment Letters, or the Backstop Parties or the Commitment Parties, respectively, may have the right to terminate such commitments, which would jeopardize PG&E Corporation’s and the Utility’s ability to finance the Proposed Plan;
- PG&E Corporation and the Utility may not be able to obtain alternative financing to the transactions contemplated by the Backstop Commitment Letters and the Debt Commitment Letters, and may not be able to obtain financing for an alternative plan that may be proposed by PG&E Corporation and the Utility after the impact of the 2019 Kincade fire is better known;
- the Utility could be subject to significant liability in excess of insurance coverage that would be expected to have a material impact on PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, and cash flows;
- PG&E Corporation, which has experienced significant declines in stock price since the beginning of the 2019 Kincade fire, could fail to satisfy the continued listing criteria of the New York Stock Exchange, which could result in the suspension of trading of PG&E Corporation common stock or Utility preferred stock and delisting of such securities;
- the 2019 Kincade fire may have adverse consequences on the Utility’s probation proceeding, the Utility’s proceedings with the CPUC and FERC (including the 2017 Northern California Wildfires OII, the Safety Culture OII and the Chapter 11 Proceedings OII), the criminal investigation into the 2018 Camp fire and future regulatory proceedings, including future applications for the safety certification required by AB 1054;
- PG&E Corporation and the Utility may experience even greater difficulty in securing adequate insurance coverage for wildfire risks; and
- PG&E Corporation and the Utility expect to suffer additional reputational harm and face an even more challenging operating, political, and regulatory environment.
- *The Uncertainties in Connection with Any Future Wildfires, Wildfire Insurance, and AB 1054.* While PG&E Corporation and the Utility cannot predict the occurrence, timing or extent of damages in connection with future wildfires, factors such as environmental conditions (including weather and vegetation conditions) and the efficacy of wildfire risk mitigation initiatives are expected to influence the frequency and severity of future wildfires. Although the financial impact of future wildfires could be mitigated through insurance, the Utility may not be able to obtain sufficient wildfire insurance coverage at a reasonable cost, or at all, and any such coverage may include limitations that could result in substantial uninsured losses depending on the amount and type of damages resulting from covered events. In addition, the policy reforms contemplated by AB 1054 are likely to affect the financial impact of future wildfires on PG&E Corporation and the Utility should any such wildfires occur. The Wildfire Fund would be available to the Utility to pay eligible claims for liabilities arising from future wildfires and would serve as an alternative to traditional insurance products, provided that the Utility satisfies the numerous conditions to the Utility’s participation in the Wildfire Fund set forth in AB 1054 and that the Wildfire Fund has sufficient remaining funds.

However, the impact of AB 1054 on PG&E Corporation and the Utility is subject to numerous uncertainties, including the Utility’s eligibility to access relief under the Wildfire Fund (which is dependent on, among other things, the Chapter 11 Cases being resolved by June 30, 2020 pursuant to a plan or similar document not subject to a stay and the Utility making its initial contribution thereto), the Utility’s ability to demonstrate to the CPUC that wildfire-related costs paid from the Wildfire Fund were just and reasonable, and whether the benefits of participating in the Wildfire Fund ultimately outweigh its substantial costs. The Utility may not be able to finance its required contributions to the Wildfire Fund, which consist of an initial contribution of approximately $4.8 billion and annual contributions of approximately $193 million. Finally, even if the Utility satisfies the eligibility and other requirements set forth in AB 1054, for eligible claims against the Utility arising between July 12, 2019 and the Utility’s emergence from Chapter 11, the availability of the Wildfire Fund to pay such claims will be capped at 40% of the amount of such claims.

- *The AB 1054 Deadline of June 30, 2020.* In the event that PG&E Corporation and the Utility are unable to confirm a plan of reorganization by June 30, 2020, the Utility will not be eligible to participate in the Wildfire Fund established under AB 1054. In that scenario, the Utility (i) would be unable to seek payment from the Wildfire Fund for liabilities arising from wildfires occurring after the July 12, 2019 effective date of AB 1054 (which in the case of pre-emergence wildfires, such as the 2019 Kincade fire, would be limited to 40% of such liabilities), (ii) would not receive the benefit of the 20% disallowance cap contemplated by AB 1054, (iii) would not be required to make any contributions to the Wildfire Fund, (iv) in applications for cost recovery for wildfires occurring after July 12, 2019, would nevertheless be subject to review under the “just and reasonable” standard set forth in section 451.1 of the Public Utilities Code (i.e., the standard as modified by AB 1054) and (v) may be eligible to obtain the annual safety certifications contemplated by section 8389 of the Public Utilities Code (which has implications for the burden of proof in a proceeding for cost recovery under section 451.1 of the Public Utilities Code). Under certain circumstances, it is possible that a successor corporation to the Utility which is formed after July 12, 2019 could be authorized to participate in the Wildfire Fund if the administrator of the Wildfire Fund determines that such successor corporation meets the requirements for participation in the Wildfire Fund set forth in AB 1054. There can be no assurance that such a successor corporation would be authorized to participate in the Wildfire Fund or that, even if it were, that investors in PG&E Corporation common stock would own an interest in such successor corporation or otherwise directly or indirectly receive any benefits from such participation.
- *The Uncertainties Regarding the Impact of Recent and Future Public Safety Power Shutoffs.* The Utility’s wildfire risk mitigation initiatives involve substantial and ongoing expenditures and could involve other costs. The extent to which the Utility will be able to recover these expenditures and potential other costs through rates is uncertain. The PSPS program, one of the Utility’s wildfire risk mitigation initiatives outlined in the 2019 Wildfire Mitigation Plan, has been the subject of significant recent criticism, including from the California Governor and the CPUC. In connection with the PSPS event initiated on October 9, 2019, the California Governor suggested that PG&E Corporation and the Utility provide affected customers an automatic credit or rebate of $100 per residential customer and $250 per small business, to be funded by PG&E Corporation’s and the Utility’s shareholders. On October 29, 2019, PG&E Corporation and the Utility announced that they would issue such credits to customers with respect to the October 9, 2019 PSPS event. PG&E Corporation and the Utility estimate that such credit will result in an approximately $90 million charge for the fourth quarter of 2019. As of the date of this filing, PG&E Corporation and the Utility do not expect to issue any similar customer credits in connection with any other PSPS events (whether past events or in the future). If PG&E Corporation or the Utility were to issue any credits, rebates or other payments in connection with any other PSPS events (whether past events or in the future), the aggregate amount of any such credits, rebates, or other payments could be substantial and could have a material effect on PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows. In addition, the PSPS program has had an adverse impact on PG&E Corporation’s and the Utility’s reputation with customers, regulators and policymakers and future PSPS events may increase these negative perceptions. On October 28, 2019, the CPUC announced it would open a formal investigation of 2019 PSPS events, utility compliance with CPUC regulations and requirements, any resulting violations, and potential actions to ensure utilities are held accountable. PG&E Corporation and the Utility cannot predict the timing and outcome of such an investigation.
- *The Outcome of Other Enforcement, Litigation, and Regulatory Matters, and Other Government Proposals*. The Utility’s financial results may continue to be impacted by the outcome of other current and future enforcement, litigation (to the extent not stayed as a result of the Chapter 11 Cases), and regulatory matters, including those described above as well as the outcome of the Locate and Mark OII, the outcome of the Safety Culture OII, the outcome of phase two of the ex parte OII, the sentencing terms of the Utility’s January 27, 2017 federal criminal conviction, including the oversight of the Utility’s probation and the potential recommendations by the Monitor, and potential penalties in connection with the Utility’s safety and other self-reports. (See Note 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1.) In addition, the Utility’s business profile and financial results could be impacted by the outcome of recent calls for municipalization of part or all of the Utility’s businesses and offers by municipalities and other public entities to acquire the electric assets of the Utility within their respective jurisdictions. Finally, on November 1, 2019, the California Governor held a press conference covering various topics relevant to PG&E Corporation and the Utility. Among other statements, the California Governor noted that “If \[PG&E Corporation and the Utility\] are unable to secure \[their\] own fate and future . . . then the State will prepare itself as backup for a scenario where we do that job for them.” PG&E Corporation and the Utility cannot predict the nature, occurrence, timing or extent of any such “backup” scenario, and there can be no assurance that any such scenario would not involve significant ownership or management changes to PG&E Corporation or the Utility, including by the State of California.
- *The Timing and Outcome of Ratemaking Proceedings*. The Utility’s financial results may be impacted by the timing and outcome of its 2020 GRC, FERC TO18, TO19, and TO20 rate cases, 2020 cost of capital proceeding, and its ability to timely recover costs not currently in rates, including costs already incurred and future costs tracked in its CEMA, WEMA, FHPMA, WMPMA, and FRMMA that are incurred in connection with the Utility's 2019 Wildfire Mitigation Plan, the amount of which is substantial and is expected to increase. The outcome of regulatory proceedings can be affected by many factors, including intervening parties’ testimonies, potential rate impacts, the Utility’s reputation, the regulatory and political environments, and other factors. (See Notes 4 and 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1 and “Regulatory Matters” below.)
- *The Utility’s Compliance with the CPUC Capital Structure*. The CPUC’s capital structure decisions require the Utility to maintain a 52% equity ratio on average over the period that the authorized capital structure is in place, and to file an application for a waiver to the capital structure condition if an adverse financial event reduces its equity ratio by 1% or more. Due to the net charges recorded in connection with the 2018 Camp fire and the 2017 Northern California wildfires as of December 31, 2018, the Utility submitted to the CPUC an application for a waiver of the capital structure condition on February 28, 2019. The waiver is subject to CPUC approval. The CPUC’s decisions state that the Utility shall not be considered in violation of these conditions during the period the waiver application is pending resolution. The Utility is unable to predict the timing and outcome of its waiver application. (See “Regulatory Matters” below.)
- *Personnel Changes.* The Utility has recently experienced significant changes in leadership, in particular with the addition of a new Chief Executive Officer of the Utility, Andrew Vesey, and turnover at the position of head of gas operations. Although the appointment of Mr. Vesey is expected to bring strong leadership to both the gas and electric businesses, further management turnover may be disruptive to operations and impair PG&E Corporation’s and the Utility’s ability to execute their strategies and operational initiatives.

For more information about the factors and risks that could affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows, or that could cause future results to differ from historical results, see “Item 1A. Risk Factors” in this Form 10-Q and the 2018 Form 10-K. In addition, this quarterly report contains forward-looking statements that are necessarily subject to various risks and uncertainties. These statements reflect management’s judgment and opinions that are based on current estimates, expectations, and projections about future events and assumptions regarding these events and management’s knowledge of facts as of the date of this report. See the section entitled “Forward-Looking Statements” below for a list of some of the factors that may cause actual results to differ materially. PG&E Corporation and the Utility are not able to predict all the factors that may affect future results and do not undertake an obligation to update forward-looking statements, whether in response to new information, future events, or otherwise.

### RESULTS OF OPERATIONS

The consolidated results of operations consist primarily of results related to the Utility, which are discussed in the “Utility” section below. The following table provides a summary of net income (loss) for the three and nine months ended September 30, 2019 and 2018:

*(in millions)*

|  | Three Months Ended September 30, 2019 | 2018 | Nine Months Ended September 30, 2019 | 2018 |
| --- | ---: | ---: | ---: | ---: |
| Consolidated Total | $(1,619) | $564 | $(4,039) | $22 |
| PG&E Corporation | (6) | (4) | (2) | (15) |
| Utility | $(1,613) | $568 | $(4,037) | $37 |

PG&E Corporation’s net income (loss) primarily consists of income taxes, interest income on cash held, interest expense on long-term debt, and reorganization items.

### Utility

The table below shows certain items from the Utility’s Condensed Consolidated Statements of Income for the three and nine months ended September 30, 2019 and 2018. The table separately identifies the revenues and costs that impacted earnings from those that did not impact earnings. In general, expenses the Utility is authorized to pass through directly to customers (such as costs to purchase electricity and natural gas, as well as costs to fund public purpose programs), and the corresponding amount of revenues collected to recover those pass-through costs, do not impact earnings. In addition, expenses that have been specifically authorized (such as the payment of pension costs) and the corresponding revenues the Utility is authorized to collect to recover such costs do not impact earnings.

Revenues that impact earnings are primarily those that have been authorized by the CPUC and the FERC to recover the Utility’s costs to own and operate its assets and to provide the Utility an opportunity to earn its authorized rate of return on rate base. Expenses that impact earnings are primarily those that the Utility incurs to own and operate its assets.

*(in millions)*

|  | Three Months Ended September 30, 2019 Revenues/Costs: That Impacted Earnings | That Did Not Impact Earnings | Total Utility | Three Months Ended September 30, 2018 Revenues/Costs: That Impacted Earnings | That Did Not Impact Earnings | Total Utility |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Electric operating revenues | $2,232 | $1,322 | $3,554 | $1,996 | $1,471 | $3,467 |
| Natural gas operating revenues | 714 | 164 | 878 | 778 | 137 | 915 |
| **Total operating revenues** | **2,946** | **1,486** | **4,432** | **2,774** | **1,608** | **4,382** |
| Cost of electricity | — | 1,070 | 1,070 | — | 1,256 | 1,256 |
| Cost of natural gas | — | 68 | 68 | — | 69 | 69 |
| Operating and maintenance | 1,816 | 392 | 2,208 | 1,247 | 364 | 1,611 |
| Wildfire-related claims, net of insurance recoveries | 2,548 | — | 2,548 | (10) | — | (10) |
| Depreciation, amortization, and decommissioning | 840 | — | 840 | 759 | — | 759 |
| **Total operating expenses** | **5,204** | **1,530** | **6,734** | **1,996** | **1,689** | **3,685** |
| **Operating income (loss)** | **(2,258)** | **(44)** | **(2,302)** | **778** | **(81)** | **697** |
| Interest income | 18 | — | 18 | 14 | — | 14 |
| Interest expense | (52) | — | (52) | (229) | — | (229) |
| Other income, net | 13 | 44 | 57 | 22 | 81 | 103 |
| Reorganization items | (69) | — | (69) | — | — | — |
| Income (Loss) before income taxes | $(2,348) | $— | $(2,348) | $585 | $— | $585 |
| Income tax provision (benefit) (1) |  |  | (738) |  |  | 14 |
| Net income (loss) |  |  | (1,610) |  |  | 571 |
| Preferred stock dividend requirement |  |  | 3 |  |  | 3 |
| **Income (Loss) Attributable to Common Stock** |  |  | **$(1,613)** |  |  | **$568** |

(1) This item impacted earnings for the three months ended September 30, 2019 and 2018.

*(in millions)*

|  | Nine Months Ended September 30, 2019 Revenues/Costs: That Impacted Earnings | That Did Not Impact Earnings | Total Utility | Nine Months Ended September 30, 2018 Revenues/Costs: That Impacted Earnings | That Did Not Impact Earnings | Total Utility |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Electric operating revenues | $6,017 | $3,275 | $9,292 | $5,911 | $3,819 | $9,730 |
| Natural gas operating revenues | 2,300 | 794 | 3,094 | 2,268 | 674 | 2,942 |
| **Total operating revenues** | **8,317** | **4,069** | **12,386** | **8,179** | **4,493** | **12,672** |
| Cost of electricity | — | 2,506 | 2,506 | — | 3,038 | 3,038 |
| Cost of natural gas | — | 515 | 515 | — | 437 | 437 |
| Operating and maintenance | 5,071 | 1,181 | 6,252 | 3,742 | 1,260 | 5,002 |
| Wildfire-related claims, net of insurance recoveries | 6,448 | — | 6,448 | 2,108 | — | 2,108 |
| Depreciation, amortization, and decommissioning | 2,433 | — | 2,433 | 2,257 | — | 2,257 |
| **Total operating expenses** | **13,952** | **4,202** | **18,154** | **8,107** | **4,735** | **12,842** |
| **Operating income (loss)** | **(5,635)** | **(133)** | **(5,768)** | **72** | **(242)** | **(170)** |
| Interest income | 61 | — | 61 | 34 | — | 34 |
| Interest expense | (213) | — | (213) | (668) | — | (668) |
| Other income, net | 54 | 133 | 187 | 79 | 242 | 321 |
| Reorganization items | (237) | — | (237) | — | — | — |
| Loss before income taxes | $(5,970) | $— | $(5,970) | $(483) | $— | $(483) |
| Income tax provision (benefit) (1) |  |  | (1,943) |  |  | (530) |
| Net income (loss) |  |  | (4,027) |  |  | 47 |
| Preferred stock dividend requirement |  |  | 10 |  |  | 10 |
| **Income (Loss) Attributable to Common Stock** |  |  | **$(4,037)** |  |  | **$37** |

(1) This item impacted earnings for the nine months ended September 30, 2019 and 2018.

### Utility Revenues and Costs that Impacted Earnings

The following discussion presents the Utility’s operating results for the three and nine months ended September 30, 2019 and 2018, focusing on revenues and expenses that impacted earnings for these periods.

### Operating Revenues

The Utility’s electric and natural gas operating revenues that impacted earnings increased by $172 million, or 6%, and $138 million, or 2% in the three and nine months ended September 30, 2019, respectively, compared to the same periods in 2018, primarily due to additional base revenues authorized in the 2017 GRC and 2019 GT&S rate cases.

### Operating and Maintenance

The Utility’s operating and maintenance expenses that impacted earnings increased by $569 million, or 46%, in the three months ended September 30, 2019, compared to the same period in 2018, primarily due to $237 million in disallowed costs for previously incurred capital expenditures in excess of adopted amounts in the 2019 GT&S rate case, with no similar charges in the same period in 2018. Additionally, the Utility incurred $121 million in costs related to enhanced and accelerated inspections and repairs of transmission and distribution assets, with no similar charges in the same period in 2018. The Utility also incurred costs of $25 million and $15 million for legal and other costs and clean-up and repair costs, respectively, related to the 2018 Camp fire in the three months ended September 30, 2019, with no similar charges in the same period in 2018.

The Utility’s operating and maintenance expenses that impacted earnings increased by $1.3 billion, or 36%, in the nine months ended September 30, 2019, compared to the same period in 2018, primarily due to $606 million related to enhanced and accelerated inspections and repairs of transmission and distribution assets, with no similar charges in the same period in 2018. Additionally, the Utility incurred costs of $265 million and $57 million for clean-up and repair costs and legal and other costs, respectively, relating to the 2018 Camp fire for the nine months ended September 30, 2019, with no similar charges in the same period in 2018. The Utility also incurred $237 million in disallowed costs for previously incurred capital expenditures in excess of adopted amounts in the 2019 GT&S rate case, with no similar charges in the same period in 2018.

### Wildfire-related claims, net of insurance recoveries

Costs related to wildfires that impacted earnings increased by $2.6 billion, and $4.3 billion, in the three and nine months ended September 30, 2019, respectively, compared to the same periods in 2018. The Utility recognized pre-tax charges of $526 million and $2.0 billion associated with the 2018 Camp fire and 2017 Northern California wildfires, respectively, for the three months ended September 30, 2019, with no corresponding charges during the same period in 2018. The Utility recognized charges of $2.4 billion and $4.0 billion, associated with the 2018 Camp fire and the 2017 Northern California wildfires, respectively, for the nine months ended September 30, 2019, compared to charges of $2.1 billion, net of probable insurance recoveries of $385 million, associated with the 2017 Northern California wildfires during the same period in 2018.

(See “Item 1A. Risk Factors” in the 2018 Form 10-K and Note 10 of the Notes to the Condensed Consolidated Financial Statements in Item 1 of this Form 10-Q.)

### Depreciation, Amortization, and Decommissioning

The Utility’s depreciation, amortization, and decommissioning expenses that impacted earnings increased by $81 million, or 11%, and $176 million, or 8%, in the three and nine months ended September 30, 2019, respectively, compared to the same periods in 2018, primarily due to capital additions and an increase in depreciation rates associated with the 2019 GT&S rate case.

### Interest Income

There was no material change to interest income that impacted earnings for the periods presented.

### Interest Expense

Interest expense that impacted earnings decreased by $177 million, or 77%, and $455 million, or 68% in the three and nine months ended September 30, 2019, respectively, compared to the same periods in 2018, primarily due to the cessation of interest accruals on outstanding pre-petition debt beginning January 29, 2019 in connection with the Chapter 11 Cases.

### Other Income, Net

There were no material changes to other income, net, that impacted earnings for the periods presented.

### Reorganization items, net

Reorganization items, net increased by $69 million and $237 million in the three and nine months ended September 30, 2019, respectively, with no corresponding charges during the same periods in 2018. The Utility recognized $83 million and $278 million, respectively, of expenses directly associated with the Utility’s Chapter 11 filing in the three and nine months ended September 30, 2019, partially offset by interest income of $14 million and $41 million, respectively.

(See “Item 1A. Risk Factors” in the 2018 Form 10-K and Note 2 of the Notes to the Condensed Consolidated Financial Statements in Item 1 of this Form 10-Q.)

### Income Tax Provision (Benefit)

Income tax benefit increased by $752 million and $1.4 billion in the three and nine months ended September 30, 2019 as compared to the same periods in 2018. The increase in the income tax benefit was primarily the result of higher pre-tax loss in the three and nine months ended September 30, 2019, compared to the same periods in 2018.

The following table reconciles the income tax expense at the federal statutory rate to the income tax provision:

|  | Three Months Ended September 30, 2019 | 2018 | Nine Months Ended September 30, 2019 | 2018 |
| --- | ---: | ---: | ---: | ---: |
| Federal statutory income tax rate | 21.0% | 21.0% | 21.0% | 21.0% |
| Increase (decrease) in income tax rate resulting from: |  |  |  |  |
| State income tax (net of federal benefit) (1) | 7.5% | 2.1% | 7.6% | 22.8% |
| Effect of regulatory treatment of fixed asset differences (2) | 2.4% | (15.9)% | 3.8% | 56.4% |
| Tax credits | 0.1% | (0.5)% | 0.1% | 1.9% |
| Other, net | 0.4% | (4.2)% | 0.1% | 7.7% |
| **Effective tax rate** | **31.4%** | **2.5%** | **32.6%** | **109.8%** |

(1) Includes the effect of state flow-through ratemaking treatment.

(2) Includes the effect of federal flow-through ratemaking treatment for certain property-related costs as authorized by various CPUC decisions. All amounts are impacted by the level of income before income taxes. The various CPUC rate case decisions authorized revenue requirements that reflect flow-through ratemaking for temporary income tax differences attributable to repair costs and certain other property-related costs for federal tax purposes. For these temporary tax differences, PG&E Corporation and the Utility recognize the deferred tax impact in the current period and record offsetting regulatory assets and liabilities. Therefore, PG&E Corporation’s and the Utility’s effective tax rates are impacted as these differences arise and reverse. PG&E Corporation and the Utility recognize such differences as regulatory assets or liabilities as it is probable that these amounts will be recovered from or returned to customers in future rates. In 2018 and 2019, the amounts also reflect the impact of the amortization of excess deferred tax benefits to be refunded to customers as a result of the Tax Act passed in December 2017.

### Utility Revenues and Costs that Did Not Impact Earnings

Fluctuations in revenues that did not impact earnings are primarily driven by electricity and natural gas procurement costs. See below for more information.

### Cost of Electricity

The Utility’s cost of electricity includes the cost of power purchased from third parties (including renewable energy resources), transmission, fuel used in its own generation facilities, fuel supplied to other facilities under power purchase agreements, costs to comply with California’s cap-and-trade program, and realized gains and losses on price risk management activities. The costs also include net sales (Utility owned generation and third parties) in the CAISO electricity markets. (See Note 8 of the Notes to the Condensed Consolidated Financial Statements in Item 1.) The Utility’s total purchased power is driven by customer demand, net CAISO electricity market activities (purchases or sales), the availability of the Utility’s own generation facilities (including Diablo Canyon and its hydroelectric plants), and the cost-effectiveness of each source of electricity.

*(in millions)*

|  | Three Months Ended September 30, 2019 | 2018 | Nine Months Ended September 30, 2019 | 2018 |
| --- | ---: | ---: | ---: | ---: |
| Cost of purchased power, net (1) | $1,001 | $1,174 | $2,296 | $2,846 |
| Fuel used in generation facilities | 69 | 82 | 210 | 192 |
| **Total cost of electricity** | **$1,070** | **$1,256** | **$2,506** | **$3,038** |

(1) Cost of purchased power, net decreased for the three and nine months ended September 30, 2019, compared to the same periods in 2018, primarily due to lower Utility electric customer demand, driven by customer departures to CCAs and DA providers, and by higher net sales in the CAISO electricity markets.

### Cost of Natural Gas

The Utility’s cost of natural gas includes the costs of procurement, storage and transportation of natural gas, costs to comply with California’s cap-and-trade program, and realized gains and losses on price risk management activities. (See Note 8 of the Notes to the Condensed Consolidated Financial Statements in Item 1.) The Utility’s cost of natural gas is impacted by the market price of natural gas, changes in the cost of storage and transportation, and changes in customer demand.

*(in millions)*

|  | Three Months Ended September 30, 2019 | 2018 | Nine Months Ended September 30, 2019 | 2018 |
| --- | ---: | ---: | ---: | ---: |
| Cost of natural gas sold | $42 | $45 | $433 | $355 |
| Transportation cost of natural gas sold | 26 | 24 | 82 | 82 |
| **Total cost of natural gas** | **$68** | **$69** | **$515** | **$437** |

### Operating and Maintenance Expenses

The Utility’s operating expenses that did not impact earnings include certain costs that the Utility is authorized to recover as incurred such as pension contributions and public purpose programs costs. If the Utility were to spend more than authorized amounts, these expenses could have an impact to earnings.

### Other Income, Net

The Utility’s other income, net that did not impact earnings includes pension and other post-retirement benefit costs that fluctuate primarily from market and interest rate changes.

### LIQUIDITY AND FINANCIAL RESOURCES

### Overview

On the Petition Date, PG&E Corporation and the Utility filed voluntary petitions for relief under Chapter 11 in the Bankruptcy Court. In connection with the Chapter 11 Cases, PG&E Corporation and the Utility entered into the DIP Credit Agreement. The DIP Credit Agreement provides for $5.5 billion in senior secured superpriority debtor in possession credit facilities in the form of (i) a revolving credit facility in an aggregate amount of $3.5 billion (the “DIP Revolving Facility”), including a $1.5 billion letter of credit subfacility, (ii) a term loan facility in an aggregate principal amount of $1.5 billion (the “DIP Initial Term Loan Facility”) and (iii) a delayed draw term loan facility in an aggregate principal amount of $500 million (the “DIP Delayed Draw Term Loan Facility,” together with the DIP Revolving Facility and the DIP Initial Term Loan Facility, the “DIP Facilities”), subject to the terms and conditions set forth therein. On March 27, 2019, the Bankruptcy Court approved the DIP Facilities on a final basis, authorizing the Utility to borrow up to the remainder of the DIP Revolving Facility (including the remainder of the $1.5 billion letter of credit subfacility), the DIP Initial Term Loan Facility and the DIP Delayed Draw Term Loan Facility, in each case subject to the terms and conditions of the DIP Credit Agreement. (For more information on the DIP Credit Agreement, see “DIP Credit Agreement” below and Note 5 of the Notes to the Consolidated Financial Statements in Item 1.)

For the duration of the Chapter 11 Cases, the Utility’s ability to fund operations, finance capital expenditures and pay other ongoing expenses and make distributions to PG&E Corporation will primarily depend on the levels of its operating cash flows and availability under the DIP Credit Agreement. The Utility expects that the DIP Facilities will provide it with sufficient liquidity to fund its ongoing operations, including its ability to provide safe service to customers, during the Chapter 11 Cases. For the duration of the Chapter 11 Cases, PG&E Corporation’s ability to fund operations and pay other ongoing expenses will primarily depend on cash on hand and intercompany transfers. In the event that PG&E Corporation’s and the Utility’s capital needs increase materially due to unexpected events or transactions, additional financing outside of the DIP Facilities may be required, which would be subject to approval by the Bankruptcy Court. Such approval is not assured. For more information on PG&E Corporation’s and the Utility’s material commitments for capital expenditures, see “Regulatory Matters” below.

During 2018 and January 2019, PG&E Corporation’s and the Utility’s credit ratings were subject to multiple downgrades by Fitch, S&P and Moody’s including to ratings below investment grade and ultimately to “D” or low “C” ratings. In the first quarter of 2019, Moody’s and Fitch withdrew each of their credit ratings for PG&E Corporation and the Utility as a result of the Chapter 11 Cases. As a result of PG&E Corporation’s and the Utility’s credit ratings ceasing to be rated at investment grade, the Utility has been required to post additional collateral under its commodity purchase agreements and certain other obligations, and has been exposed to significant constraints on its customary trade credit. In addition, PG&E Corporation and the Utility may be required to post additional collateral in respect of certain other obligations, including workers’ compensation and environmental remediation obligations. (See Notes 8 and 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1.)

### Cash and Cash Equivalents

Cash and cash equivalents consist of cash and short-term, highly liquid investments with original maturities of three months or less. PG&E Corporation and the Utility maintain separate bank accounts and primarily invest their cash in money market funds.

### Financial Resources

### Acceleration of Pre-Petition Debt Obligations

The commencement of the Chapter 11 Cases constituted an event of default or termination event with respect to, and caused an automatic and immediate acceleration of, the Accelerated Direct Financial Obligations. Accordingly, as a result of the commencement of the Chapter 11 Cases, the principal amount of the Accelerated Direct Financial Obligations, together with accrued interest thereon, and in case of certain indebtedness, premium, if any, thereon, immediately became due and payable. However, any efforts to enforce such payment obligations are automatically stayed as of the Petition Date, and are subject to the applicable provisions of the Bankruptcy Code and orders of the Bankruptcy Court. The material Accelerated Direct Financial Obligations include the Utility’s outstanding senior notes, agreements in respect of certain series of pollution control bonds, and PG&E Corporation’s term loan facility, as well as short-term borrowings under PG&E Corporation’s and the Utility’s revolving credit facilities and the Utility’s term loan facility disclosed in Note 5 of the Notes to the Condensed Consolidated Financial Statements in Item 1.

### DIP Credit Agreement

On February 1, 2019, the Utility borrowed $350 million under the DIP Revolving Facility. On April 3, 2019, the Utility borrowed $1.5 billion under the DIP Initial Term Loan Facility and received the proceeds of such borrowing, net of original issue discount and repayment of the $350 million in outstanding borrowings under the DIP Revolving Facility. The DIP Initial Term Loan Facility matures on December 31, 2020 (subject to an extension option described further below) and bears interest at a spread of 225 basis points over LIBOR.

Borrowings under the DIP Facilities are senior secured obligations of the Utility, secured by substantially all of the Utility’s assets and entitled to superpriority administrative expense claim status in the Utility’s Chapter 11 Case. The Utility’s obligations under the DIP Facilities are guaranteed by PG&E Corporation, and such guarantee is a senior secured obligation of PG&E Corporation, secured by substantially all of PG&E Corporation’s assets and entitled to superpriority administrative expense claim status in PG&E Corporation’s Chapter 11 Case. The DIP Facilities will mature on December 31, 2020, subject to the Utility’s option to extend the maturity to December 31, 2021 if certain terms and conditions are satisfied, including the payment of an extension fee. The Utility paid customary fees and expenses in connection with obtaining the DIP Facilities.

As of November 5, 2019, the Utility had outstanding borrowings of $1.5 billion under the DIP Initial Term Loan Facility, no outstanding borrowings under the DIP Delayed Draw Term Loan Facility or the DIP Revolving Facility and $713 million in face amount of letters of credit outstanding under the DIP Revolving Facility. As of November 5, 2019, there were undrawn commitments of $500 million and $2.8 billion on the DIP Delayed Draw Term Loan Facility and the DIP Revolving Facility, respectively. Pursuant to the terms of the DIP Credit Agreement, until such time as the DIP Delayed Draw Term Loan Facility has been drawn in full, or the commitments in respect thereof have terminated or expired, further borrowings under the DIP Revolving Facility are not permitted.

### CPUC Authorization of DIP Credit Agreement

On January 28, 2019, the CPUC granted the Utility exemptions from the requirement of prior CPUC approval for issuance of debt instruments for the incurrence of the DIP financing. The CPUC also indicated its position that the exemptions do not extend to the transfer of ownership of any Utility asset that is pledged as part of the DIP financing and that in the event of the Utility’s default under the DIP financing, the Utility would need to seek the CPUC’s approval to execute such a transfer. Further, the CPUC indicated that the Utility’s “expenditure of the initial DIP financing funds for any purposes may not be recovered from ratepayers without Commission approval in a future application for rate recovery” and that the Utility “bears the burden of demonstrating the reasonableness of any expenditure.”

### Debt Commitment Letters

On October 11, 2019, PG&E Corporation and the Utility entered into the Debt Commitment Letters with the Commitment Parties, pursuant to which the Commitment Parties committed to provide $34.35 billion in bridge financing in the form of (a) a $27.35 billion senior secured bridge loan facility (the “OpCo Facility”) with the Utility or any domestic entity formed to hold all of the assets of the Utility upon emergence from bankruptcy as borrower thereunder and (b) a $7.0 billion senior unsecured bridge loan facility (together with the OpCo Facility, the “Facilities”) with PG&E Corporation or any domestic entity formed to hold all of the assets of PG&E Corporation upon emergence from bankruptcy as borrower thereunder, subject to the terms and conditions set forth therein. The commitments under the Debt Commitment Letters will expire on August 29, 2020, unless terminated earlier pursuant to the termination rights set forth in the Debt Commitment Letters. PG&E Corporation and the Utility will pay customary fees and expenses in connection with obtaining the Facilities. If the entire $34.35 billion of bridge commitments remain outstanding as of June 30, 2020, the aggregate commitment fees payable by PG&E Corporation and the Utility would be approximately $210 million.

In lieu of entering into the Facilities, PG&E Corporation and the Utility intend to obtain permanent financing on or prior to emergence from bankruptcy in the form of bank facilities, debt securities or a combination of the foregoing. (See "Plan of Reorganization, RSA, Equity Backstop Commitments and Debt Commitment Letters" in Note 2 of the Notes to the Condensed Consolidated Financial Statements in Item 1.)

On October 23, 2019, PG&E Corporation and the Utility filed a motion with the Bankruptcy Court seeking approval of the Backstop Commitment Letters, the Debt Commitment Letters and certain related matters. The hearing on PG&E Corporation’s and the Utility’s motion to approve the Backstop Commitment Letters, the Debt Commitment Letters and certain related matters is scheduled for November 19, 2019. PG&E Corporation and the Utility intend to seek an extension of the November 20, 2019 deadline for Bankruptcy Court approval of the Backstop Commitment Letters and the Debt Commitment Letters from the Backstop Parties and the Commitment Parties, respectively.

### Equity Financings

There were no issuances under the PG&E Corporation February 2017 equity distribution agreement for the nine months ended September 30, 2019.

During the nine months ended September 30, 2019, PG&E Corporation issued 8.9 million shares for cash proceeds of $85 million under the PG&E Corporation 401(k) plan. The proceeds from these sales were used for general corporate purposes. Beginning January 1, 2019, PG&E Corporation changed its default matching contributions under its 401(k) plan from PG&E Corporation common stock to cash. Beginning in March 2019, at PG&E Corporation’s directive, the 401(k) plan trustee began purchasing new shares in the PG&E Corporation common stock fund on the open market rather than directly from PG&E Corporation.

PG&E Corporation expects to issue new shares of PG&E Corporation common stock for up to $14.0 billion of proceeds at or prior to emergence from Chapter 11 in order to finance the Proposed Plan. The structure, terms and conditions of any such equity issuance are expected to be determined by PG&E Corporation and the Utility at a later time in the Chapter 11 process, subject to the terms and conditions of the Backstop Commitment Letters. There can be no assurance that any such equity offering would be successful. In the event that such equity offerings (together with additional permitted capital sources) do not raise at least $14.0 billion of proceeds in the aggregate or if PG&E Corporation and the Utility do not otherwise consummate such offerings, then PG&E Corporation and the Utility may draw on the Backstop Commitments for equity funding to finance the transactions contemplated by the Proposed Plan, subject to satisfaction or waiver by the Backstop Parties of the conditions set forth therein. (See "Plan of Reorganization, RSA, Equity Backstop Commitments and Debt Commitment Letters" in Note 2 of the Notes to the Condensed Consolidated Financial Statements in Item 1.)

### Dividends

On December 20, 2017, the Boards of Directors of PG&E Corporation and the Utility suspended quarterly cash dividends on both PG&E Corporation’s and the Utility’s common stock, beginning the fourth quarter of 2017, as well as the Utility’s preferred stock, beginning the three-month period ending January 31, 2018, due to the uncertainty related to the causes of and potential liabilities associated with the 2017 Northern California wildfires. PG&E Corporation does not expect to pay any cash dividends during the Chapter 11 Cases. (See Note 10 of the Notes to the Condensed Consolidated Financial Statements in Item 1.) Also, on April 3, 2019, the court overseeing the Utility’s probation issued an order imposing new conditions of probation, including forgoing issuing “any dividends until \[the Utility\] is in compliance with all applicable vegetation management requirements” under applicable law and the Utility’s wildfire mitigation plan. (See “U.S. District Court Matters and Probation” in Item 1. Legal Proceedings and Item 7. MD&A.)

### Utility Cash Flows

The Utility’s cash flows were as follows:

*(in millions)*

|  | Nine Months Ended September 30, 2019 | 2018 |
| --- | ---: | ---: |
| Net cash provided by operating activities | $4,078 | $4,184 |
| Net cash used in investing activities | (4,250) | (4,617) |
| Net cash provided by financing activities | 1,416 | 357 |
| **Net change in cash, cash equivalents and restricted cash** | **$1,244** | **$(76)** |

### Operating Activities

The Utility’s cash flows from operating activities primarily consist of receipts from customers less payments of operating expenses, other than expenses such as depreciation that do not require the use of cash. During the nine months ended September 30, 2019, net cash provided by operating activities decreased by $106 million compared to the same period in 2018. This decrease was primarily due to an increase in amounts paid for reorganization items, and enhanced and accelerated inspections and repairs of transmission and distribution assets in 2019, with no similar payments in 2018, partially offset by amounts not paid due to the automatic stay as of the Petition Date.

The Utility will continue to operate its business as a debtor in possession under the jurisdiction of the Bankruptcy Court and in accordance with applicable provisions of the Bankruptcy Code and the orders of the Bankruptcy Court. Future cash flow from operating activities will be affected by various ongoing activities, including:

- the timing and amounts of costs, including fines and penalties, that may be incurred in connection with current and future enforcement, litigation, and regulatory matters (see “Enforcement and Litigation Matters” in Note 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1 and Part II, Item 1. Legal Proceedings for more information);
- the timing and amount of premium payments related to wildfire insurance (see “Wildfire Insurance” in Note 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1 for more information);
- the Tax Act, which may accelerate the timing of federal tax payments and reduce revenue requirements, resulting in lower operating cash flows depending on the timing of wildfire payments;
- the timing and outcomes of the 2020 GRC, FERC TO18, TO19 and TO20 rate cases, 2020 Cost of Capital, NDCTP, and other ratemaking and regulatory proceedings; and
- the timing and amount of substantially increasing costs in connection with the 2019 Wildfire Mitigation Plan that are not currently being recovered in rates (see “Regulatory Matters” below for more information).

The Utility had material obligations outstanding as of the Petition Date, including claims related to the 2018 Camp fire and 2017 Northern California wildfires. Any efforts to enforce such payment obligations are automatically stayed as of the Petition Date, and are subject to the applicable provisions of the Bankruptcy Code and orders of the Bankruptcy Court. Future cash flows will be materially impacted by the timing and outcome of the Chapter 11 Cases.

### Investing Activities

Net cash used in investing activities decreased by $367 million during the nine months ended September 30, 2019 as compared to the same period in 2018. The Utility’s investing activities primarily consist of the construction of new and replacement facilities necessary to provide safe and reliable electricity and natural gas services to its customers. Cash used in investing activities also includes the proceeds from sales of nuclear decommissioning trust investments which are largely offset by the amount of cash used to purchase new nuclear decommissioning trust investments. The funds in the decommissioning trusts, along with accumulated earnings, are used exclusively for decommissioning and dismantling the Utility’s nuclear generation facilities.

The Utility’s capital expenditures were approximately $6.5 billion in 2018. Future cash flows used in investing activities are largely dependent on the timing and amount of capital expenditures. The Utility estimates that it will incur approximately $7.2 billion in capital expenditures in 2019, and between $5.7 billion and $7 billion annually from 2020 through 2023.

### Financing Activities

Net cash provided by financing activities increased by $1.1 billion during the nine months ended September 30, 2019 as compared to the same period in 2018. This increase was due to $1.5 billion of net borrowings under the DIP Initial Term Loan Facility in 2019, offset by $400 million of long-term debt that matured in 2018 with no corresponding activity in 2019.

Cash provided by or used in financing activities is driven by the Utility’s financing needs, which depend on the level of cash provided by or used in operating activities, the level of cash provided by or used in investing activities, the conditions in the capital markets, and the maturity date of existing debt instruments.

### ENFORCEMENT AND LITIGATION MATTERS

PG&E Corporation and the Utility have significant contingencies arising from their operations, including contingencies related to the enforcement and litigation matters described in Notes 10 and 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1. The outcome of these matters, individually or in the aggregate, could have a material effect on PG&E Corporation’s and the Utility’s financial condition, results of operations, and cash flows. In addition, PG&E Corporation and the Utility are involved in other enforcement and litigation matters described in the 2018 Form 10-K and “Part II. Other Information, Item 1. Legal Proceedings.”

### REGULATORY MATTERS

The Utility is subject to substantial regulation by the CPUC, the FERC, the NRC and other federal and state regulatory agencies. The resolutions of the proceedings described below and other proceedings may affect PG&E Corporation’s and the Utility’s financial condition, results of operations, and cash flows. Discussed below are significant regulatory developments that have occurred since filing the 2018 Form 10-K.

### Application for a Waiver of the Capital Structure Condition

The CPUC’s capital structure decisions require the Utility to maintain a 52% equity ratio on average over the period that the authorized capital structure is in place, and to file an application for a waiver to the capital structure condition if an adverse financial event reduces its equity ratio by 1% or more. The CPUC’s decisions state that the Utility shall not be considered in violation of these conditions during the period the waiver application is pending resolution. Due to the net charges recorded in connection with the 2018 Camp fire and the 2017 Northern California wildfires as of December 31, 2018, the Utility submitted to the CPUC an application for a waiver of the capital structure condition on February 28, 2019. The waiver is subject to CPUC approval. On April 30, 2019, the CPUC held a prehearing conference, and on May 29, 2019, the CPUC issued a scoping memo and ruling on issues for briefing. On August 27, 2019, the Utility filed a motion to update the record to reflect additional charges recorded as of June 30, 2019 for the 2017 Northern California wildfires and the 2018 Camp fire, of $3.9 billion, as the result of which, the Utility’s equity ratio declined to approximately 34% at June 30, 2019. The Utility filed its opening briefs with the CPUC on August 30, 2019. The Utility is unable to predict the timing and outcome of its waiver application.

### 2020 Cost of Capital Proceeding

On April 22, 2019, the Utility filed an application with the CPUC, requesting that the CPUC authorize the Utility's capital structure and rates of return for its electric generation, electric and natural gas distribution, and natural gas transmission and storage rate base beginning on January 1, 2020. In its application, the Utility requested that the CPUC approve the Utility’s proposed capital structure (i.e., the relative weightings of common equity, preferred equity, and debt), as well as the proposed return on equity, proposed cost of preferred stock, and proposed cost of debt. The Utility requested a 16% rate of return on equity for 2020, which reflected, among other things, the wildfire-related challenges that the Utility was facing. The Utility also proposed to amend its cost of capital application with an updated cost of capital if the CPUC or the California legislature implemented actions to materially reduce the challenges that investor-owned utilities face in California in connection with the extreme wildfire risk.

AB 1054, enacted on July 12, 2019, provides for the establishment of the Wildfire Fund that will be available for eligible electric utility companies to pay eligible claims for liabilities arising from wildfires occurring after July 12, 2019 that are caused by the applicable electric utility company’s equipment, subject to the terms and conditions of AB 1054. On July 23, 2019, the Utility notified the CPUC of its election to participate in the Wildfire Fund. The Utility’s participation in the Wildfire Fund is subject to the conditions and limitations set forth in AB 1054 and approval by the Bankruptcy Court.

As a result of the expected effects of AB 1054 on the Utility’s wildfire-related risk profile, on August 1, 2019, in a supplemental cost of capital testimony, the Utility proposed to revise its rate of return on equity to 12%.

The following table compares the cost of capital currently authorized in the Utility’s 2019 GT&S rate case and the 2017 GRC, with those requested in the Utility’s 2020 cost of capital application, as updated by the Utility’s August 1, 2019 testimony to reflect a revised rate of return on equity:

|  | 2019 Currently Authorized Cost | Capital Structure | Weighted Cost | 2020 Requested (as revised) Cost | Capital Structure | Weighted Cost |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Return on common equity | 10.25% | 52.00% | 5.33% | 12.00% | 52.00% | 6.24% |
| Preferred stock | 5.60% | 1.00% | 0.06% | 5.52% | 0.50% | 0.03% |
| Long-term debt | 4.89% | 47.00% | 2.30% | 5.16% | 47.50% | 2.45% |
| **Weighted average cost of capital** |  |  | **7.69%** |  |  | **8.72%** |

The proposed cost of capital and capital structure will be essential for the Utility to attract new investment capital to upgrade, maintain, and modernize its critical energy infrastructure. The Utility indicated in its application that, over the next four years (2019-2022), the Utility expects to fund up to $28 billion in energy infrastructure investments, including $21 billion in electric and gas safety, reliability and system hardening, $4 billion in new gas pipelines and electric powerlines, $1 billion in power generation, and $2 billion in information technology, equipment and facilities.

The Utility indicated in its supplemental cost of capital testimony that AB 1054 does not directly impact the Utility’s test year 2020 cost of debt. However, the cost of debt will be impacted by the Utility’s exit financing as part of its future Chapter 11 plan of reorganization. The supplemental cost of capital testimony did not address the Utility’s currently-effective formula rate for electric transmission rates, including the requested return on equity, which is pending at the FERC. The parties in the FERC proceeding are currently involved in settlement negotiations.

The CPUC is considering whether the Utility must file a new cost of capital application with the CPUC on or about the time it emerges from the Chapter 11 Cases. The Utility requested in its cost of capital application that the annual cost of capital adjustment mechanism be continued, although its normal operation could be superseded by a new cost of capital application. (The annual cost of capital adjustment mechanism is a tool to modify the cost of long-term debt and cost of equity authorized by the CPUC based on changes in interest rates.) The Utility is unable to predict the timing and outcome of this proceeding.

### Revenue Requirements

For 2020, the Utility expects that the proposed cost of capital, if adopted, would result in revenue requirement increases of approximately $271 million for electric generation and distribution and $74 million for gas distribution operations, assuming 2017 authorized rate base amounts. The revenues for the gas transmission and storage operations would increase by approximately $71 million, assuming 2020 authorized rate base amounts. However, if the CPUC subsequently approves different electric and gas rate base amounts for the Utility in its 2020 GRC, which is currently pending before the CPUC, the revenue requirement changes resulting from the Utility’s requested 2020 ROE may differ from the amounts reflected in this cost of capital application.

The following table compares the revenue requirement amounts currently authorized in the Utility’s 2019 GT&S rate case and the 2017 GRC, with those requested in the Utility’s 2020 cost of capital application, as updated to reflect a revised rate of return on equity submitted to the CPUC on August 1, 2019:

| Revenue Requirement (in millions) | Authorized in 2017 GRC and 2019 GT&S | Requested in 2020 Cost of Capital Application (as revised) |
| --- | ---: | ---: |
| Electric generation and distribution | $6,266 | $6,537 |
| Gas distribution | 1,739 | 1,813 |
| Gas transmission and storage | 1,431 | 1,502 |

As disclosed in “Application for a Waiver of the Capital Structure Condition” above, due to the net charges recorded in connection with the 2018 Camp fire and the 2017 Northern California wildfires as of December 31, 2018, on February 28, 2019, the Utility submitted to the CPUC an application for a waiver of the capital structure condition. The 2020 cost of capital application does not modify that request.

On July 2, 2019, the assigned commissioner issued a scoping memo and ruling that, among other things, consolidated the Utility’s cost of capital proceeding with the 2020 cost of capital applications submitted to the CPUC by Southern California Edison Company, San Diego Gas & Electric Company, and Southern California Gas Company. The scoping memo also identified the issues to be addressed within the proceeding and its schedule. On July 15, 2019, the assigned ALJ also issued a ruling directing the Utility and the other Applicants to submit supplemental testimony regarding AB 1054’s impact on financial risks and other issues within the scope of this proceeding by August 1, 2019. Rebuttal testimony was filed August 16, 2019, and additional rebuttal on testimony regarding the passage of AB 1054 was filed on August 21, 2019. A proposed decision is expected to be issued on November 27, 2019. The earliest a final decision would appear on the CPUC’s business meeting agenda is December 19, 2019. The Utility is unable to predict the timing and outcome of this proceeding.

### 2017 General Rate Case

On May 11, 2017, the CPUC issued a final decision in the Utility’s 2017 GRC, which determined the annual amount of base revenues (or “revenue requirements”) that the Utility is authorized to collect from customers from 2017 through 2019 to recover its anticipated costs for electric distribution, natural gas distribution, and electric generation operations and to provide the Utility an opportunity to earn its authorized rate of return. The final decision approved, with certain modifications, the settlement agreement that the Utility, PAO, TURN, and 12 other intervening parties jointly submitted to the CPUC on August 3, 2016. Consistent with the amounts proposed in the settlement agreement, the final decision approved a revenue requirement increase of $88 million for 2017, with additional increases of $444 million in 2018 and $361 million in 2019.

On September 24, 2018, the CPUC approved the Utility’s advice letter proposal to make a one-time reduction to revenues by approximately $21 million. This advice letter was directed by an ALJ ruling in response to the Utility’s $300 million expense reduction announcement in January 2017.

Also, as a result of the Tax Act, on March 30, 2018, the Utility submitted to the CPUC a PFM of the CPUC’s final decision in the 2017 GRC proposing to reduce revenue requirements by $267 million and $296 million for 2018 and 2019, respectively, and increase rate base by $199 million and $425 million for 2018 and 2019, respectively. On August 15, 2019, a final decision on the PFM was issued directing the Utility to consult with the CPUC’s Energy Division to ensure that its calculations include the cost of removal component of book depreciation when calculating the amortization of protected excess deferred income taxes using the ARAM and to quantify the amount of unprotected excess deferred taxes, which can be returned to ratepayers without following the ARAM. In compliance with the decision, on September 13, 2019, the Utility filed an advice letter with the revised calculations and the length of time the revenue requirement reductions would be amortized in rates. On October 17, 2019, the CPUC approved the Utility’s advice letter approving a revised computation of the effects of the Tax Act on the revenue requirements, resulting in a $282 million reduction to the 2018 revenue requirement and a $291 million reduction to the 2019 revenue requirement. The Utility will incorporate these revenue requirement reductions into rates beginning on January 1, 2020 and later in 2020 along with other anticipated changes, such as the 2020 GRC Phase 1. The IRS is expected to provide additional guidance on ARAM. This IRS guidance may impact the Utility’s calculation of the related revenue requirement. It is uncertain when the IRS guidance may be issued.

The Utility provided an update of the cost effectiveness study for the SmartMeterTM Upgrade project to the CPUC on July 10, 2017. On October 24, 2019, the CPUC adopted a final decision that finds (i) the July 10, 2017 study is a thorough and complete update of the cost-effectiveness of the project and (ii) the Utility should submit an updated version of the cost effectiveness study as a stand-alone exhibit in each GRC Phase I application that the Utility files in the future.

For more information on the 2017 GRC, see the 2018 Form 10-K.

### 2020 General Rate Case

On December 13, 2018, the Utility filed its 2020 GRC application with the CPUC. In the 2020 GRC, the Utility requested that the CPUC determine the annual amount of revenue requirements that the Utility will be authorized to collect from customers from 2020 through 2022 to recover its anticipated costs for electric distribution, natural gas distribution, and electric generation operations and to provide the Utility an opportunity to earn its authorized rate of return. The Utility’s request also reflects an updated capital forecast for 2018 and 2019. The 2020 GRC application also includes recorded costs for 2017 and updated forecasts for the proposed mitigations for the period 2018 through 2022 for the Utility’s top safety-related risks as presented in the Utility’s November 2017 Risk Assessment Mitigation Phase report.

For 2020, the Utility requested base revenues of $9.6 billion, an increase of $1.1 billion, or 12.4%, as compared to authorized base revenues for 2019. The requested weighted average rate base for 2020 is approximately $30 billion, which corresponds to an increase of $2.7 billion over the 2019 authorized rate base of $27.3 billion. The Utility also requested that the CPUC establish a ratemaking mechanism that would increase the Utility’s authorized revenues in 2021 and 2022 by $454 million and $486 million, respectively. Over the 2020-2022 GRC period, the Utility plans to make average annual capital investments of approximately $4.5 billion in electric distribution, natural gas distribution, and electric generation infrastructure, and to improve safety, reliability, and customer service.

| Line of Business: (in millions) | Amounts Requested in the GRC Application | Amounts Currently Authorized for 2019 (1) | Increase to 2019 Authorized Amounts |
| --- | ---: | ---: | ---: |
| Electric distribution | $5,113 | $4,364 | $749 |
| Gas distribution | 2,097 | 1,963 | 134 |
| Electric generation | 2,366 | 2,191 | 175 |
| **Total revenue requirements** | **$9,576** | **$8,518** | **$1,058** |

(1) These amounts include revenues from the Utility’s 2017 GRC decision adjusted for attrition year increases, cost of capital, and reductions due to the Tax Act.

| Cost Category: (in millions) | Amounts Requested in the GRC Application | Amounts Currently Authorized for 2019 (1) | Increase (Decrease) to 2019 Authorized Amounts (2) |
| --- | ---: | ---: | ---: |
| Operations and maintenance | $2,156 | $1,946 | $210 |
| Customer services | 319 | 338 | (19) |
| Administrative and general | 1,315 | 953 | 361 |
| Less: Revenue credits | (196) | (152) | (44) |
| Franchise fees, taxes other than income, and other adjustments | 236 | 181 | 55 |
| Depreciation, return, and income taxes | 5,747 | 5,252 | 495 |
| **Total revenue requirements (2)** | **$9,576** | **$8,518** | **$1,058** |

(1) These amounts include revenues from the Utility’s 2017 GRC decision adjusted for attrition year increases, cost of capital, and reductions due to the Tax Act.

(2) These amounts may appear not to tie due to small rounding differences.

| Revenue requirement drivers | Increase to 2019 Authorized Amounts |
| --- | ---: |
| Community Wildfire Safety Program | 6.8% |
| Liability insurance (1) | 3.2% |
| Core gas and electric operations | 2.4% |
| **Total proposed revenue requirement increase** | **12.4%** |

(1) The Utility’s GRC forecast indicates that future liability insurance premium costs will be approximately $355 million in 2020.

Among other things, the Utility proposed to invest a total of approximately $5 billion (including approximately $3 billion for capital expenditures) between 2018 and 2022 on CWSP measures. Through this program, the Utility proposes to bolster wildfire prevention, risk monitoring, and emergency response efforts, add new and enhanced safety measures, increase vegetation management, and harden its electric system to help further reduce wildfire risks.

In addition, the Utility requested authorization to establish several new balancing accounts, including:

- a two-way electric and gas Risk Transfer Balancing Account to record the difference between the amounts adopted for liability insurance premiums and the Utility’s actual costs; this two-way account would allow the Utility to pass-through actual insurance costs for up to $2 billion in coverage and return to customers any overcollection if forecast costs exceed actuals costs; and
- a two-way Wildfire Mitigation Balancing Account to recover expenses and capital expenditures associated with the Utility’s wildfire mitigation activities of up to 115% of the Utility’s expense and capital expenditures forecasts; this would include the costs associated with overhead system hardening, enhanced vegetation management, and other costs of wildfire mitigation activities. For expense and capital expenditures that exceed the 115% threshold, the proposed balancing account would allow the Utility to track those incremental costs and seek recovery. Costs incurred that exceed the 115% threshold would be subject to reasonableness review in a future GRC or separate application.

This GRC proposal did not request funding for potential lawsuits or claims resulting from the 2018 Camp fire and 2017 Northern California wildfires. Also, the Utility is not seeking recovery of compensation of PG&E Corporation’s and the Utility’s officers. In addition, the Chapter 11 Cases may require a change to the scope of work that the Utility proposes to accomplish in the 2020 GRC period.

In its application, the Utility requested that the CPUC issue a final decision by March 2020 and that the 2020 GRC revenue requirement be effective January 1, 2020. On March 8, 2019, the CPUC issued a ruling addressing the schedule and scope of the 2020 GRC. The ruling indicates a proposed decision will be issued in the first quarter of 2020.

On March 25, 2019, the Utility submitted an update to the 2020 forecasted capital request for its corporate real estate to $170 million, which is a 55% decrease from its original capital request of approximately $380 million. The cost reductions were due to changes in the Utility's real estate strategy.

On June 28, 2019, PAO submitted testimony recommending that the CPUC authorize a 2020 GRC revenue requirement of $503 million, or 5.9%, higher than the 2019 authorized level. PAO also recommended establishing a one-way balancing account for the Utility’s total GRC revenue requirement during the rate case term (2020 to 2022). On July 26, 2019, all other parties to the proceeding submitted testimony; none submitted an alternative revenue requirement recommendation.

On September 4, 2019, the Utility submitted its rebuttal testimony. In rebuttal testimony the Utility included updates to its CWSP and insurance proposals as follows:

- The Utility extended the timeline for its CWSP system hardening proposal from a 10-year program to a 14-year program and proposed to revise the number of overhead system hardening from 600 miles per year in 2020, 2021, and 2022 to 188 miles in 2020, 204 miles in 2021 and 376 miles in 2022.
- The Utility also updated its CWSP forecast to include undergrounding, which the Utility will consider on a project by project basis as part of its system hardening proposal.
- These revisions to the CWSP workplan result in an updated CWSP forecast of $4.2 billion from $4.1 billion for the period 2020 through 2022.
- The Utility revised its general liability insurance proposal to reduce the amount of general liability insurance coverage it may seek in a given year from $2 billion to $1.4 billion subject to the CPUC approving a self-insurance mechanism whereby the Utility would use any unspent revenues approved for liability insurance premiums to self-insure.

Evidentiary hearings occurred between September 23, 2019 and October 18, 2019. On November 1, 2019, the Utility submitted an update to its revenue requirement request to the CPUC. The revenue requirement update included errata, forecast updates disclosed throughout the proceeding, forecast concessions included in the Utility’s rebuttal testimony, and stipulations with various parties to the proceeding. The update reduced the Utility’s requested revenue requirement increases from $1.058 billion to $1.002 billion for test year 2020, from $454 million to $356 million for 2021, and from $486 million to $481 million for 2022. One additional day of evidentiary hearings was held on November 6, 2019. Opening briefs are due on November 22, 2019 and reply briefs are due on December 13, 2019.

On November 1, 2019, in accordance with AB 1054 and a ruling set forth by the assigned ALJs, the Utility submitted its proposal for removing from its revenue requirement request the forecasted equity return on its wildfire mitigations capital additions forecasts. The Utility estimated the reduction as $22 million in 2020, $57 million in 2021 and $105 million in 2022. These amounts will be adjusted to reflect the amounts approved by the CPUC in the final decision, including amounts adopted for 2021 and 2022.

The Utility cannot predict the timing and outcome of this matter.

For more information on the 2020 GRC, see the 2018 Form 10-K.

### 2015 Gas Transmission and Storage Rate Case

In its final decisions in the Utility’s 2015 GT&S rate case, the CPUC excluded from rate base $696 million of capital spending in 2011 through 2014. This was the amount recorded in excess of the amount adopted in the 2011 GT&S rate case. The decision permanently disallowed $120 million of that amount and ordered that the remaining $576 million be subject to an audit overseen by the CPUC staff, with the possibility that the Utility may seek recovery in a future proceeding. The Utility would be required to take a charge in the future if the CPUC’s audit of 2011 through 2014 capital spending resulted in additional permanent disallowance. The audit is still in process. The Utility cannot predict the timing and outcome of the audit.

As a result of the Tax Act, on March 30, 2018, the Utility submitted to the CPUC a PFM of the CPUC’s final decision in the 2015 GT&S rate case proposing to reduce revenue requirements by $58 million and increase rate base by $12 million for 2018 (excluding the impacts of an approximately $7 million increase in revenue requirement and a $60 million increase in rate base associated with the Utility’s private letter ruling advice letter approved by the CPUC on July 18, 2018). On August 15, 2019, a final decision on the PFM was issued directing the Utility to consult with the CPUC’s Energy Division to ensure that its calculations include the cost of removal component of book depreciation when calculating the amortization of protected excess deferred income taxes using the ARAM and to quantify the amount of unprotected excess deferred taxes, which can be returned to ratepayers without following the ARAM. In compliance with the decision, on September 13, 2019, the Utility filed an advice letter with the revised calculations and the length of time the revenue requirement reductions would be amortized in rates. On October 17, 2019, the CPUC approved the Utility’s advice letter approving a revised computation of the effects of the Tax Act on the revenue requirements, resulting in a $61 million reduction to the 2018 revenue requirement. The Utility will incorporate the revenue requirement reduction into rates beginning January 1, 2020. The IRS is expected to provide additional guidance on ARAM. This IRS guidance may impact the Utility's calculation of the related revenue requirement. It is uncertain when the IRS guidance may be issued.

For more information on the 2015 GT&S rate case, see the 2018 Form 10-K.

### 2019 Gas Transmission and Storage Rate Case

On September 12, 2019, the CPUC voted the final decision in the 2019 GT&S rate case of the Utility. By approving the decision, the CPUC adopted a 2019 revenue requirement of $1.332 billion compared to the Utility’s (revised) request of $1.485 billion. This corresponds to an increase of $31 million over the Utility’s 2018 authorized revenue requirement of $1.301 billion, compared to the $184 million increase requested by the Utility. The CPUC also adopted revenue requirements of $1.432 billion for 2020, $1.516 billion for 2021, and $1.580 billion for 2022, compared to the Utility’s request of $1.595 billion for 2020, $1.693 billion for 2021, and $1.679 billion for 2022.

The revenue requirement amounts requested by the Utility and the revenue requirement amounts in the decision are set forth in the following table:

| Revenue Requirement (in millions) | 2018 Currently Authorized | 2019 | 2020 | 2021 | 2022 |
| --- | ---: | ---: | ---: | ---: | ---: |
| Utility’s Request | $1,301 | $1,485 | $1,595 | $1,693 | $1,679 |
| Decision | $1,301 | $1,332 | $1,432 | $1,516 | $1,580 |

The decision removed from rate base approximately $304 million on a forecasted basis of pipeline replacement capital expenditures for the 2015-2018 period due to cost overruns; the Utility expects the final disallowance on a recorded cost basis to be approximately $237 million. Incorporating the forecast reduction, the decision adopted a rate base for 2019 of $4.46 billion, which corresponds to an increase of $0.75 billion over the 2018 adopted rate base of $3.71 billion. This is compared to the Utility’s rate base request of $4.75 billion for 2019. The decision adopted a rate base of $4.98 billion for 2020, $5.37 billion for 2021, and $5.71 billion for 2022.

The rate base amounts also exclude approximately $576 million of capital spending subject to audit by the CPUC (related to 2011 through 2014 expenditures in excess of amounts adopted in the 2011 GT&S rate case), pursuant to the 2015 GT&S rate case decision. The Utility is unable to predict whether the $576 million, or a portion thereof, will ultimately be approved by the CPUC and included in the Utility’s future rate base.

The decision adopted capital expenditures of $726 million for 2019, which corresponds to a decrease of $104 million over the Utility’s request of $830 million. The decision adopted a post-test year ratemaking joint stipulation proposed by the Utility and PAO. The joint stipulation results in adopted capital expenditures of $697 million in 2020, $597 million in 2021, and $570 million in 2022.

The decision adopted the Utility’s proposed Natural Gas Storage Strategy, with minor modifications related to the decommissioning or sale of the Utility’s Los Medanos and Pleasant Creek storage fields, and the decision adopted a two-way balancing account for storage costs, which will be subject to a reasonableness review in the next GT&S rate case. The decision retained a number of existing memorandum accounts and one-way balancing accounts, including a one-way expense balancing account for transmission integrity management, and adopted 19 new expense and capital one-way balancing and memorandum accounts.

The decision also resolved the second phase of this proceeding, addressing the removal of officer compensation costs from the revenue requirement, which is required by California Senate Bill 901. On this matter, the decision adopted the joint stipulation offered by the Utility, PAO and TURN that reduces the Utility’s requested 2019 GT&S operating expenses by $1.428 million and capital expenditures by $0.455 million.

On October 23, 2019, the Utility filed an application for rehearing with the CPUC requesting the rehearing of the final decision. Specifically, issues identified by the Utility include the adopted disallowance associated with vintage pipe replacement, reduction in the Utility’s expense forecast for in-line inspections, and establishment of a memo account for Internal Corrosion Direct Assessment. The Utility cannot predict the timing and outcome of this matter.

For more information on the 2019 GT&S rate case, see the 2018 Form 10-K.

### Transmission Owner Rate Cases

### Transmission Owner Rate Cases for 2015 and 2016 (the “TO16” and “TO17” rate cases, respectively)

On January 8, 2018, the Ninth Circuit Court of Appeals issued an opinion granting an appeal of FERC’s decisions in the TO16 and TO17 rate cases that had granted the Utility a 50 basis point ROE incentive adder for its continued participation in the CAISO. Those rate case decisions were remanded to FERC for further proceedings consistent with the Court of Appeals’ opinion. If FERC concluded on remand that the Utility should no longer be authorized to receive the 50 basis point ROE incentive adder, the Utility would incur a refund obligation of $1 million and $8.5 million for TO16 and TO17, respectively. Alternatively, if FERC again concluded that the Utility should receive the 50 basis point ROE incentive adder and provides the additional explanation that the Ninth Circuit found the FERC’s prior decisions lacked, then the Utility would not owe any refunds for this issue for TO16 or TO17.

On February 28, 2018, the Utility filed a motion to establish procedures on remand requesting a hearing and additional briefing on the issues identified in the Ninth Circuit Court’s opinion. On August 20, 2018, FERC issued an order granting the Utility’s motion to allow for additional briefing. The order also consolidated the TO18 rate case with TO16 and TO17 for this issue. The Utility filed briefs on September 19, 2018 and reply briefs on October 10, 2018. On July 18, 2019, FERC issued its order on remand reaffirming its prior grant of the Utility’s request for the 50 basis point ROE adder. On August 16, 2019, a number of parties filed for rehearing of that order on remand. In the absence of FERC action within 30 days from the date the rehearing request was filed, the request for rehearing would be deemed denied by operation of law. As a result, on September 16, 2019, FERC extended the amount of time to consider the request for rehearing by issuing a tolling order for the limited purpose of further consideration of the matters raised in the request.

### Transmission Owner Rate Case for 2017 (the “TO18” rate case)

On July 29, 2016, the Utility filed its TO18 rate case at the FERC requesting a 2017 retail electric transmission revenue requirement of $1.72 billion, a $387 million increase over the 2016 revenue requirement of $1.33 billion. The forecasted network transmission rate base for 2017 was $6.7 billion. The Utility sought a return on equity of 10.9%, which included an incentive component of 50 basis points for the Utility’s continuing participation in the CAISO. In the filing, the Utility forecasted that it would make investments of $1.30 billion in 2017 in various capital projects.

On September 30, 2016, the FERC issued an order accepting the Utility’s July 2016 filing and setting it for hearing, but held the hearing procedures in abeyance for settlement procedures. The order set an effective date for rates of March 1, 2017 and made the rates subject to refund following resolution of the case. On March 17, 2017, the FERC issued an order terminating the settlement procedures due to an impasse in the settlement negotiations reported by the parties. During the hearings held in January 2018, the Utility, intervenors, and the FERC trial staff, addressed questions relating to return on equity, capital structure, depreciation rates, capital additions, rate base, operating and maintenance expense, administrative and general expense, and the allocation of common, general and intangible costs.

Additionally, on March 31, 2017, intervenors in the TO18 rate case filed a complaint at the FERC alleging that the Utility failed to justify its proposed rate increase in the TO18 rate case. On November 16, 2017, the FERC dismissed the complaint. On December 18, 2017, the complainants filed a request for a rehearing of that order, which the FERC denied on May 17, 2018.

On October 1, 2018, the ALJ issued an initial decision in the TO18 rate case proposing a ROE of 9.13% compared to the Utility’s request of 10.90%, and an estimated composite depreciation rate of 2.96% compared to the Utility’s request of 3.25%. The ALJ also rejected the Utility’s method of allocating common plant between CPUC and FERC jurisdiction. In addition, the ALJ proposed to reduce forecasted capital and expense spending to actual costs incurred for the rate case period. Further, the ALJ proposed to remove certain items from the Utility’s rate base and revenue requirement. The Utility and intervenors filed initial briefs on October 31, 2018, and reply briefs on November 20, 2018, in response to the ALJ’s initial decision. The Utility expects FERC to issue a decision in late-2019, but expects one or more parties to seek rehearing of that decision and then appeal it to the courts. The Utility is unable to predict the timing of when a final decision will be issued.

### Transmission Owner Rate Case for 2018 (the “TO19” rate case)

On July 27, 2017, the Utility filed its TO19 rate case at the FERC requesting a 2018 retail electric transmission revenue requirement of $1.79 billion, a $74 million increase over the proposed 2017 revenue requirement of $1.72 billion. The forecasted network transmission rate base for 2018 was $6.9 billion. The Utility sought an ROE of 10.75%, which includes an incentive component of 50 basis points for the Utility’s continuing participation in the CAISO. In the filing, the Utility forecasted capital expenditures of approximately $1.4 billion. On September 28, 2017, the FERC issued an order accepting the Utility’s July 2017 filing, subject to hearing and refund, and established March 1, 2018 as the effective date for rate changes. FERC also ordered that the hearings be held in abeyance pending settlement discussion among the parties. On May 14, 2018, the Utility filed a proposal to reflect the impact of the Tax Act on its TO tariff rates effective March 1, 2018, in the resolution of the TO19 rate case. The tax impact reduces the TO19 requested revenue requirement from $1.79 billion to $1.66 billion.

On September 29, 2017, intervenors in the TO19 rate case filed a complaint at the FERC alleging that the Utility failed to justify its proposed rate increase in the TO19 rate case. On October 17, 2017, the Utility requested that the FERC dismiss the complaint. On May 17, 2018, the FERC issued an order setting the complaint for hearing, initiating settlement judge procedures, and consolidating with the TO19 proceeding.

On September 21, 2018, the Utility filed an all-party settlement with FERC in connection with TO19. As part of the settlement, the TO19 revenue requirement will be set at 98.85% of the revenue requirement for TO18 that will be determined upon the issuance of a final, non-appealable TO18 decision. Additionally, if FERC were to determine that the Utility was not entitled to the 50 basis point incentive adder for the Utility’s continued CAISO participation, then the Utility would be obligated to make a refund to customers of approximately $25 million. On December 20, 2018, FERC issued an order approving the all-party settlement. Additionally, on July 18, 2019, FERC issued an order on remand reaffirming its grant of the Utility’s request for the 50 basis point incentive adder for continued CAISO participation. On September 30, 2019, FERC issued an order on rehearing that denied a pending request for rehearing of the FERC’s decision granting the 50 basis point ROE adder in the TO19 proceeding.

### Transmission Owner Rate Case for 2019 (the “TO20” rate case)

On October 1, 2018, the Utility filed its TO20 rate case at FERC requesting approval of a formula rate for the costs associated with the Utility’s electric transmission facilities. On November 30, 2018, the FERC issued an order accepting the Utility’s October 2018 filing, subject to hearings and refund, and established May 1, 2019 as the effective date for rate changes. FERC also ordered that the hearings will be held in abeyance pending settlement discussions among the parties. The Utility is unable to predict the timing and outcome of settlement discussions.

The formula rate replaces the “stated rate” methodology that the Utility used in its previous TO rate case filings. The formula rate methodology still includes an authorized revenue requirement and rate base for a given year, but it also provides for an annual update of the following year’s revenue requirement and rates in accordance with the terms of the FERC-approved formula. Under the formula rate mechanism, transmission revenue requirements will be updated to the actual cost of service annually as part of the true-up process. Differences between amounts collected and determined under the formula rate will be either collected from or refunded to customers.

In the filing, the Utility forecasts a 2019 retail electric transmission revenue requirement of $1.96 billion. The proposed amount reflects an approximately 9.5% increase over the as-filed TO19 requested revenue requirement of $1.79 billion (a subsequent reduction to $1.66 billion was identified as a result of the Tax Act). The Utility forecasts that it will make investments of approximately $1.1 billion and $0.7 billion for 2018 and 2019, respectively, for various capital projects to be placed in service before the end of 2019. Including projects to be placed in service beyond 2019, the Utility forecasts total electric transmission capital expenditures of $1.4 billion in 2018 and $1.4 billion in 2019. The Utility’s forecasted rate base for 2019 is approximately $8 billion on a weighted average basis, compared to the Utility’s forecasted rate base of $6.9 billion in 2018. The Utility has requested that FERC approve a 12.5% return on equity (which includes an incentive component of 50 basis points for the Utility’s continuing participation in the CAISO), an increase from the 10.75% (also inclusive of a 50 basis point CAISO incentive adder) requested in its TO19 rate case. The parties conducted settlement conferences on March 14-15, 2019, June 13-14, 2019, August 13-14, 2019, and October 28-29, 2019.

On May 9, 2019, the Utility filed an application with the FERC requesting revisions to its TO20 rate case formula rate model to remove the impact of the non-cash wildfire-related charges on the ratio of common equity to total capital. The Utility indicates in its application that, because of the recording of the non-cash wildfire-related charges in connection with the 2017 Northern California wildfires and the 2018 Camp fire, the Utility’s financial statements reflected a ratio of common equity to total capital of approximately 41% as of December 31, 2018. The Utility indicates that the proposed revisions adjust the equity ratio to accurately reflect how the Utility financed the capital projects that are included in rate base. The Utility’s current rate base was financed with an equity ratio of approximately 52%, rather than the 41% equity ratio. In addition, on May 9, 2019, the Utility submitted a request to the FERC to exclude the wildfire charge from the Utility’s capital structure for the purpose of calculating its allowance for funds used during construction effective January 1, 2019.

On July 10, 2019, the FERC accepted the Utility’s revisions to the formula rate to become effective December 9, 2019, subject to refund, established hearing and settlement judge procedures, and reflected it with the Utility's TO20 case.

The Utility expects to file an annual update to its TO tariff on or before December 1 of each year beginning in December 2019, for rates and charges to become effective January 1 of the following year, consistent with the formula rate.

For more information on the TO rate cases, see the 2018 Form 10-K.

### Nuclear Decommissioning Cost Triennial Proceeding

The Utility expects that the decommissioning of Diablo Canyon will take many years after the expiration of its current operating licenses. Detailed studies of the cost to decommission the Utility’s nuclear generation facilities are conducted every three years in conjunction with the NDCTP. Actual decommissioning costs may vary from these estimates as a result of changes in assumptions such as regulatory requirements; technology; and costs of labor, materials, and equipment. The Utility recovers its revenue requirements for decommissioning costs from customers through a non-bypassable charge that the Utility expects will continue until those costs are fully recovered.

On December 13, 2018, the Utility submitted its 2018 NDCTP application, which includes a Diablo Canyon site-specific decommissioning cost estimate of $4.8 billion to decommission the Diablo Canyon facilities.

On February 14, 2019, the CPUC issued a scoping memo addressing the scope of the Utility’s 2018 NDCTP application to include the reasonableness of the Diablo Canyon decommissioning cost estimate, ratemaking proposals, proposed Diablo Canyon milestone framework, plans to address host community needs, reasonableness of Humboldt Bay Power Plant decommissioning costs, and reasonableness of performing Diablo Canyon planning activities pre-shutdown, including the proposed rate of recovery of these pre-planning activities addressed in the Utility’s application for authorization to establish the Diablo Canyon decommissioning planning memorandum account (the “Diablo Canyon DPM account application”).

On March 7, 2019, the CPUC amended the scoping memo to combine the Diablo Canyon DPM account application, which seeks authorization for the Utility to establish the Diablo Canyon Decommissioning Memorandum Account to track funding for Diablo Canyon pre-shutdown decommissioning planning activities, with the 2018 NDCTP. The CPUC approved the Utility to establish an interim mechanism to track decommissioning planning activity expenses in the Diablo Canyon Decommissioning Memorandum Account. Any Memorandum Account recovery of such expenses is subject to the authorization and approval of the CPUC, which will be discussed in this year’s NDCTP. The assigned ALJ deferred the decision of cost recovery until after the NRC addresses the Utility’s December 13, 2018 exemption request, in which the Utility requested an exemption to allow the Utility to withdraw from the NDT to fund decommissioning planning activities. The CPUC held public participation hearings on August 7 and 8, 2019 for residents and organizations in and near San Luis Obispo in connection with the Utility’s request.

On September 10, 2019, the NRC issued a letter granting the Utility’s request for an exemption and authorizing the Utility to access the NDT for up to $187.8 million on decommissioning planning activities. On October 4, 2019, the Utility submitted supplemental testimony to the NRC addressing how it proposes to modify its request in light of the NRC exemption and the Utility’s proposed disposition of and ratemaking treatment of the planned Baywood Feed, a 12-kilovolt transmission line.

Opening briefs are due November 21, 2019 and reply briefs are due on December 13, 2019.

The Utility seeks to collect $383.7 million and $3.9 million for the funding of the Diablo Canyon tax qualified trust and Humboldt Bay tax qualified trust, respectively, commencing January 1, 2020. Additionally, the Utility seeks cost recovery of pre-planning activities commencing January 1, 2020, of $30 million for the three-year period 2020 to 2022, and a $44 million revenue requirements for the two-year period 2023 to 2024; by an annual expense only balancing account. The Utility is also defending the reasonableness and prudence of the $398.4 million spent for Humboldt Bay Power Plant decommissioning project costs completed to date.

### Petition for Modification of CPUC Decision Approving Retirement of Diablo Canyon Power Plant

On June 20, 2016, the Utility entered into a joint proposal with certain parties, including the Alliance for Nuclear Responsibility, to retire Diablo Canyon’s two nuclear power reactor units at the expiration of their current operating licenses in 2024 and 2025. On January 11, 2018, the CPUC approved the planned retirement by 2024 and 2025, but required legislative authorization for certain key aspects of the joint proposal. On November 29, 2018, in response to SB 1090, the CPUC issued a further decision addressing the key remaining goals of the Diablo Canyon joint proposal agreement.

On October 1, 2019, the Alliance for Nuclear Responsibility filed a PFM of the CPUC’s January 11, 2018 decision approving the planned retirement of Diablo Canyon. The PFM argues that above-market costs attributable to Diablo Canyon under the Power Charge Indifference Adjustment methodology, when combined with decreasing bundled load by PG&E, create material changed circumstances that undermine the reasonableness of incurring costs to operate Diablo Canyon until its retirement. On October 31, 2019, the Utility filed a joint response with Friends of the Earth, Natural Resources Defense Council, Coalition of California Utility Employees, and IBEW Local 1245, which argued that modification of the CPUC's initial decision is not warranted and is not in the public interest.

For more information on the planned retirement of Diablo Canyon, see the 2018 Form 10-K.

### Wildfire Expense Memorandum Account

On June 21, 2018, the CPUC issued a decision granting the Utility’s request to establish a WEMA to track specific incremental wildfire liability costs effective as of July 26, 2017. In the WEMA, the Utility can record costs related to wildfires, including: (1) payments to satisfy wildfire claims, including any deductibles, co-insurance and other insurance expenses paid by the Utility but excluding costs that have already been forecasted and adopted in the Utility’s GRC; (2) outside legal costs incurred in the defense of wildfire claims; (3) insurance premium costs not in rates; and (4) the cost of financing these amounts. Insurance proceeds, as well as any payments received from third parties, or through FERC authorized rates, will be credited to the WEMA as they are received. The WEMA will not include the Utility’s costs for fire response and infrastructure costs, which are tracked in the CEMA. The decision does not grant the Utility rate recovery of any wildfire-related costs. Any such rate recovery would require CPUC authorization in a separate proceeding. (See Notes 4 and 10 of the Notes to the Condensed Consolidated Financial Statements in Item 1.)

As of September 30, 2019, the Condensed Consolidated Financial Statements include long-term regulatory assets of $143 million, consisting of insurance premium costs that are probable of recovery (see “Long-Term Regulatory Assets” in Note 4 of the Notes to the Condensed Consolidated Financial Statements in Item 1). Should PG&E Corporation and the Utility conclude in future periods that recovery of insurance premiums in excess of amounts included in authorized revenue requirements is no longer probable, PG&E Corporation and the Utility will record a charge in the period such conclusion is reached.

### Catastrophic Event Memorandum Account Applications

The CPUC allows utilities to recover the reasonable, incremental costs of responding to catastrophic events that have been declared a disaster or state of emergency by competent federal or state authorities through a CEMA. In 2014, the CPUC directed the Utility to perform additional fire prevention and vegetation management work in response to the severe drought in California. The costs associated with this work are also tracked in the CEMA. While the Utility believes such costs are recoverable through CEMA, its CEMA applications are subject to CPUC review and approval. For more information, see “Long-Term Regulatory Assets” in Note 4 of the Notes to the Condensed Consolidated Financial Statements in Item 1.

### 2019 CEMA Application

On September 13, 2019, the Utility submitted to the CPUC its 2019 CEMA application requesting cost recovery of $159.3 million in connection with thirteen catastrophic events that included twelve wildfires and one storm for declared emergencies from mid-2017 through 2018. The 2019 CEMA application does not include costs related to the 2015 Butte fire, the 2017 Northern California wildfires, or the 2018 Camp fire. A prehearing conference was held on November 4, 2019.

PG&E Corporation and the Utility are unable to predict the timing and outcome of this overall proceeding.

### 2018 CEMA Application

On March 30, 2018, the Utility submitted to the CPUC its 2018 CEMA application requesting cost recovery of $183 million in connection with seven catastrophic events that included fire and storm declared emergencies from mid-2016 through early 2017, as well as $405 million related to work performed in 2016 and 2017 to cut back or remove dead or dying trees that were exposed to years of drought conditions and bark beetle infestation. The 2018 CEMA application originally sought cost recovery of $555 million on a forecast basis, for additional tree mortality and fire risk mitigation work anticipated in 2018 and 2019, subject to true-up if actual costs were greater or less than the forecast. However, on April 25, 2019, the CPUC adopted a decision denying cost recovery on a forecast basis for the 2018 and 2019 costs requested.

On April 25, 2019, the CPUC approved the Utility’s request for interim rate relief, allowing for recovery of $373 million of costs (63% of the total costs incurred in 2016 and 2017), compared to $588 million requested by the Utility. The interim rate relief was implemented on October 1, 2019. Costs included in the interim rate relief are subject to audit and refund. On July 1, 2019, the Utility filed a motion requesting approval to: (i) revise the 2018 CEMA testimony and workpapers to exclude forecast costs, (ii) include 2018 recorded tree mortality and fire risk reduction costs, and (iii) assist with the hiring of an independent auditor for the recorded tree mortality costs included in the 2018 CEMA. The assigned commissioner and ALJs issued three separate rulings on July 31, 2019, granting the Utility’s requests pertaining to the removal of the forecast costs and revisions, the inclusion of 2018 recorded tree mortality costs, and directed the Utility to assist with the hiring of an independent auditor in conjunction with the CPUC Energy Division. On August 7, 2019, the Utility filed a Revised Application, Revised Testimony and Revised Workpapers, reflecting a new revenue requirement request of $669 million. The $669 million incorporates (i) the removal of forecast tree mortality costs (reduction of approximately $555 million); (ii) inclusion of the 2018 Tree Mortality and Fire Risk Reduction activities (increase of approximately $90 million); and (iii) other corrections and updates found since the filing (reduction of approximately $9 million), as compared to the Utility’s original request of $1.14 billion.

The 2018 CEMA application does not include costs related to the 2015 Butte fire, the 2017 Northern California wildfires, or the 2018 Camp fire.

PG&E Corporation and the Utility are unable to predict the timing and outcome of the overall proceeding.

### Fire Hazard Prevention Memorandum Account

The CPUC allows utilities to track and record costs associated with implementing regulations and requirements adopted to protect the public from potential fire hazards associated with overhead power line facilities and nearby aerial communication facilities that have not been previously authorized in another proceeding. The Utility currently is authorized to track such costs in the FHPMA through the end of 2019. While the Utility believes such costs are recoverable, rate recovery requires CPUC reasonableness review and authorization in a separate proceeding or through a GRC.

For the amount recorded to this memorandum account as of September 30, 2019, see “Long-Term Regulatory Assets” in Note 4 of the Notes to the Condensed Consolidated Financial Statements in Item 1.

### Fire Risk Mitigation Memorandum Account

On March 12, 2019, the CPUC approved the Utility’s FRMMA to track costs incurred beginning January 1, 2019, for fire risk mitigation activities that are not otherwise covered in revenue requirements. The FRMMA was authorized by SB 901 and AB 1054 to capture mitigation costs of activities not included in a CPUC approved Wildfire Mitigation Plan. The Utility has proposed that the FRMMA continue after the approval of its 2019 Wildfire Mitigation Plan to record costs of wildfire mitigation activities that were beyond the initial identified scope of work.

While the Utility intends to seek recovery of the FRMMA balance in a future application, rate recovery requires CPUC reasonableness review and authorization in a separate proceeding or through a GRC. PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows could be materially affected if the Utility is unable to timely recover costs in connection with the 2019 Wildfire Mitigation Plan recorded in the FRMMA, which the Utility expects will be substantial.

For the amount recorded to this memorandum account as of September 30, 2019, see “Long-Term Regulatory Assets” in Note 4 of the Notes to the Condensed Consolidated Financial Statements in Item 1.

### Wildfire Mitigation Plan Memorandum Account

On June 5, 2019, the Utility submitted an advice letter to establish the WMPMA (also called the Wildfire Plan Memorandum Account) effective May 30, 2019. The purpose of the WMPMA is to track costs incurred to implement the Utility’s Wildfire Mitigation Plan, as required by SB 901 and AB 1054. The WMPMA is required to be established upon approval of a utility’s wildfire mitigation plan to track costs incurred to implement the plan. The CPUC approved the memorandum account on August 5, 2019, so the Utility will record any costs incurred in implementing an approved Wildfire Mitigation Plan as of the effective date, June 5, 2019.

The Utility anticipates that the recovery of the costs recorded to the WMPMA would occur through a general rate case or future application at which time the CPUC would review the costs for reasonableness as required by SB 901. PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows could be materially affected if the Utility is unable to timely recover costs in connection with the 2019 Wildfire Mitigation Plan recorded in the WMPMA, which the Utility expects will be substantial.

For the amount recorded to this memorandum account as of September 30, 2019, see “Long-Term Regulatory Assets” in Note 4 of the Notes to the Condensed Consolidated Financial Statements in Item 1.

### Other Regulatory Proceedings

### 2019 Wildfire Mitigation Plan

On October 25, 2018, the CPUC opened an OIR to implement the provisions of SB 901 related to electric utility wildfire mitigation plans. This OIR provided guidance on the form and content of the initial wildfire mitigation plans, provided a venue for review of the initial plans, and developed and refined the content of and process for review and implementation of wildfire mitigation plans to be filed in future years. In this proceeding the CPUC will consider, among other things, how to interpret and apply SB 901’s list of required plan elements, as well as whether additional elements beyond those required in SB 901 should be included in the wildfire mitigation plans. SB 901 also requires, among other things, that such plans include a description of the preventive strategies and programs to be adopted by an electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including the consideration of dynamic climate change risks, plans for vegetation management, and plans for inspections of the electrical corporation’s electrical infrastructure. The scope of this proceeding does not include utility recovery of costs related to wildfire mitigation plans, which SB 901 requires to be addressed in separate rate recovery applications.

On February 6, 2019, the Utility filed its wildfire mitigation plan (the “2019 Wildfire Mitigation Plan”) with the CPUC. The 2019 Wildfire Mitigation Plan describes forecasted work and investments in 2019 that are designed to help further reduce the potential for wildfire ignitions associated with the Utility’s electrical equipment in high fire-threat areas. The 2019 Wildfire Mitigation Plan specifically addresses wildfire risk factors that occur most frequently and have potential to start or spread a fire. The 2019 Wildfire Mitigation Plan focuses on the measures the Utility proposes to take in 2019, but includes longer-term plans, while acknowledging that the Utility may modify these plans based upon new information or conditions as the Utility implements these measures. The new and ongoing safety measures being pursued include:

- installing nearly 600 new, high-definition cameras, made available to Cal Fire and local fire officials, in high fire-threat areas by 2022, increasing coverage across high fire-threat areas to more than 90%;
- adding approximately 1,300 additional new weather stations by 2022, at a density of one station roughly every 20 circuit miles in high fire-threat areas;
- conducting enhanced safety inspections of electric infrastructure in high-fire threat areas, including approximately 735,000 electric towers and poles across approximately 5,700 transmission line miles and 25,200 distribution line miles;
- further enhancing vegetation management efforts across high and extreme fire-threat areas to address vegetation that poses higher potential for wildfire risk, such as removing or trimming trees from particular “at-risk” tree species that have exhibited a higher pattern of failing;
- continuing to disable automatic reclosing in high fire-threat areas during wildfire season and periods of high fire-risk and upgrading reclosers and circuit breakers in high fire-threat areas with remote control capabilities;
- expanding the PSPS to include all transmission and distribution lines in Tier 2 and Tier 3 High Fire-Threat District areas;
- installing stronger and more resilient poles and covered power lines, including targeted undergrounding, starting in areas with the highest fire risk, ultimately upgrading and strengthening approximately 7,100 miles over the next 10 years; and
- partnering with additional communities in high fire-threat areas to create new resilience zones that can power central community resources during a PSPS.

On February 12, February 14, and April 25, 2019, the Utility filed amendments to the 2019 Wildfire Mitigation Plan with the CPUC to correct inadvertent errors in the cost table attached to the 2019 Wildfire Mitigation Plan; refine language in the 2019 Wildfire Mitigation Plan; and modify certain 2019 Wildfire Mitigation Plan targets in light of external conditions, enhance other targets based on early learnings, and clarify targets to minimize the potential for misinterpretation, respectively.

On May 30, 2019, the CPUC approved two decisions related to the Utility’s 2019 Wildfire Mitigation Plan. The first decision was specific to the Utility’s plan and generally approved the plan, subject to certain reporting, data gathering, and other requirements set forth in the decision. The Utility-specific decision did not approve the amendment filed by the Utility on April 25, 2019. The second decision was a guidance decision for all of the utilities that submitted wildfire mitigation plans. This guidance decision included additional reporting, data gathering, and other requirements and provided that the Utility’s April 25th amendment will be examined in Phase 2 of this proceeding.

On June 14, 2019, the assigned commissioner and ALJ issued a decision implementing Phase 2 of the OIR, announcing Phase 2 workshops to develop metrics and templates to evaluate the Utility’s 2019 Wildfire Mitigation Plan and report data consistently and a process for submission of the 2020 plans. The decision also announced that the CPUC would evaluate the Utility’s April 25th amendment in Phase 2, as well as the process for independent evaluation of the Utility’s compliance with its 2019 plan.

On August 23, 2019, the CPUC approved the Utility’s Initial Safety Certification, which under AB 1054 entitles the Utility to certain benefits, including eligibility for a cap on wildfire fund reimbursement and for a reformed prudent manager standard. The Utility satisfied the required elements for its Initial Safety Certificate, as follows: (i) the electrical corporation has an approved wildfire mitigation plan, (ii) the electrical corporation is in good standing, which can be satisfied by the electrical corporation having agreed to implement the findings of its most recent safety culture assessment, if applicable, (iii) the electrical corporation has established a safety committee of its board of directors composed of members with relevant safety experience, and (iv) the electrical corporation has established board-of-director-level reporting to the CPUC on safety issues. The Initial Safety Certification is valid for twelve months.

On September 18, 2019, the CPUC issued a scoping memo and ruling for Phase 2 setting the scope and procedural schedule. The scope of the proceeding will largely focus on the evaluation and enforcement of wildfire mitigation plans and the implementation of AB 1054 and AB 111. Parties have an opportunity to request the CPUC hold evidentiary hearings in this phase. If the CPUC allows, evidentiary hearings will begin December 9, 2019. The Utility currently expects to file its 2020 Wildfire Mitigation Plan in early 2020. The timing is subject to change.

PG&E Corporation and the Utility are unable to predict the timing and outcome of this proceeding. PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows could be materially affected if the Utility is unable to timely recover costs in connection with the 2019 Wildfire Mitigation Plan recorded in the FRMMA and WMPMA, which the Utility expects will be substantial.

### OIR Regarding Criteria and Methodology for Wildfire Cost Recovery Pursuant to Senate Bill 901

SB 901, signed into law on September 21, 2018, requires the CPUC to establish a CHT, directing the CPUC to limit certain disallowances in the aggregate, so that they do not exceed the maximum amount that the Utility can pay without harming ratepayers or materially impacting its ability to provide adequate and safe service. SB 901 also authorizes the CPUC to issue a financing order that permits recovery, through the issuance of recovery bonds (also referred to as “securitization”), of wildfire-related costs found to be just and reasonable by the CPUC and, only for the 2017 Northern California wildfires, any amounts in excess of the CHT. SB 901 does not authorize securitization with respect to possible 2018 Camp fire costs.

On January 10, 2019, the CPUC adopted an OIR, which establishes a process to develop criteria and a methodology to inform determinations of the CHT in future applications under Section 451.2(a) of the Public Utilities Code for recovery of costs related to the 2017 Northern California wildfires.

On March 29, 2019, the assigned commissioner issued a scoping memo, which confirmed that the CPUC in this proceeding would establish a CHT methodology applicable only to 2017 fires, to be invoked in connection with a future application for cost recovery, and would not determine a specific financial outcome in this proceeding.

On July 8, 2019, the CPUC issued a decision in the CHT proceeding. The CPUC decision provides that “\[a\]n electrical corporation that has filed for relief under chapter 11 of the Bankruptcy Code may not access the Stress Test to recover costs in an application under Section 451.2(b), because the Commission cannot determine the corporation’s ‘financial status,’ which includes, among other considerations, its capital structure, liquidity needs, and liabilities, as required by Section 451.2(b).” This determination effectively bars PG&E Corporation and the Utility from access to relief under the CHT during the pendency of the Chapter 11 Cases. On August 7, 2019, the Utility submitted to the CPUC an application for rehearing of the decision. The Utility indicated in its application, among other things, that the CPUC’s decision “is contrary to law because it bars a utility that has filed for Chapter 11 from accessing the CHT, requires a utility to file a cost recovery application before the CHT will be determined, and erects ratepayer protection mechanisms as an extra-statutory hurdle for accessing the CHT.” The Utility also argued that the CPUC should apply the CHT methodology to costs related to the 2018 Camp fire.

The decision otherwise adopts a methodology to determine the CHT based on: (1) the maximum additional debt that a utility can take on and maintain a minimum investment grade credit rating; (2) excess cash available to the utility; (3) a potential maximum regulatory adjustment of either 20% of the CHT or 5% of the total disallowed wildfire liabilities, whichever is greater; and (4) an adjustment to preserve for ratepayers any tax benefits associated with the CHT. The decision also requires a utility to include proposed ratepayer protection measures to mitigate harm to ratepayers as part of an application under section 451.2(b).

Failure to obtain a substantial or full recovery of costs related to wildfires could have a material effect on PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows.

### OII to Consider PG&E Corporation’s and the Utility’s Proposed Plan of Reorganization

On October 4, 2019, the CPUC issued an OII to consider the ratemaking and other implications “that will result from the confirmation of a plan of reorganization and other regulatory approvals necessary to resolve” the Chapter 11 Cases (the “Chapter 11 Proceedings OII”). The Chapter 11 Proceedings OII indicates that the proceeding will “afford parties the opportunity to be heard and comment on” any CPUC “regulatory review resulting from a proposed plan of reorganization (including any amendments) filed with the Commission, any proposed settlement agreement resolving \[the Chapter 11 Cases\] between PG&E and Commission staff filed in connection with a plan, any regulatory approvals required pursuant to Public Utilities Code Section 3292 in order for PG&E to become eligible to participate in the wildfire fund established pursuant to Assembly Bill 1054 (AB) 1054, any other regulatory approvals required by AB 1054, and any other matters that may need to be decided by \[the CPUC\] in connection with a plan.” The OII anticipates that the proceeding “will serve as a venue for review of a proposed plan and all attendant issues identified as within the scope of this proceeding.” The CPUC “expects to render its decision sufficiently in advance of the June 30, 2020 statutory deadline contained in AB 1054 to allow the Bankruptcy Court to address and approve any modifications made to the plan pursuant to Commission orders.”

On October 11, 2019, the Utility filed a response to the OII. In its response, among other things, the Utility proposed that an appropriate schedule for consideration of the Proposed Plan and the TCC/Ad Hoc Noteholder Plan would include evidentiary hearings in February and March of 2020, a proposed decision on each proposed plan by April 15, 2020 and final decisions by the CPUC on each proposed plan by May 14, 2020. The response explained the Utility's view that the TCC/Ad Hoc Noteholder Plan is significantly flawed and would be contrary to the public interest.

On October 18, 2019, other parties filed responses to the OII, including the Ad Hoc Noteholder Committee. In its response, the Ad Hoc Noteholder Committee argued that the TCC/Ad Hoc Noteholder Plan meets the requirements of AB 1054, that PG&E Corporation’s and the Utility’s Proposed Plan as well as the TCC/Ad Hoc Noteholder Plan constitute a change in control that should be subject to review under Public Utilities Code section 854, and that PG&E Corporation’s and the Utility’s previous changes in share ownership and management should also be evaluated under Public Utilities Code section 854.

The CPUC held a prehearing conference on October 23, 2019, at which the assigned ALJ reserved decision on scoping and scheduling issues.

The OII states that the CPUC preliminarily expects evidentiary hearings to be conducted, commencing no later than February 2020.

### Wildfire Fund Non-Bypassable Charge

In response to directives in AB 1054, on July 26, 2019, the CPUC opened a new rulemaking to consider the authorization of a non-bypassable charge to support the Wildfire Fund. On October 24, 2019, the CPUC issued a final decision finding that the imposition of the non-bypassable charge is just and reasonable. In addition, the decision affirmed that the Utility and its customers will not pay an allocated share of the adopted wildfire charge revenue requirement unless and until the Utility participates in the Wildfire Fund. The decision also continues the same allocation of the wildfire charge revenue requirement among the investor-owned utilities as previously adopted for the Department of Water Resources power and bond charge revenue requirements. The decision proposes revenue requirements for the Utility of $404.6 million, which is based on average annual collections and shall expire at the end of the year 2035.

### Transportation Electrification

California law SB 350 requires the CPUC, in consultation with the California Air Resources Board and the CEC, to direct electrical corporations to file applications for programs and investments to accelerate widespread TE. In September 2016, the CPUC directed the Utility and the other large IOUs to file TE applications that include both short-term projects (of up to $20 million in total) and two-to-five year programs with a requested revenue requirement determined by the Utility.

On May 31, 2018, the CPUC issued a final decision approving the Utility’s two-to-five year program proposals for actual expenditures up to approximately $269 million (including $198 million of capital expenditures), to support utility-owned make-ready infrastructure supporting public fast charging and medium to heavy-duty fleets. In the EV Fleet program, the Utility has a goal of providing make-ready infrastructure at 700 sites supporting 6,500 vehicles, conducting operation and maintenance of installed infrastructure, and educating customers on the benefits of electric vehicles. The final decision gives customers the option of self-funding, installing, owning, and maintaining the make-ready infrastructure installed beyond the customer meter in lieu of utility ownership, after which they would receive a utility rebate for a portion of those costs. The EV Fast Charge program has a goal to install utility-owned make-ready infrastructure at approximately 52 public charging sites amounting to roughly 234 DC fast chargers.

On December 19, 2018, the CPUC initiated a new Rulemaking for vehicle electrification matters (R.18-12-006). This new proceeding will include issues related to utility rate designs supporting transportation electrification and hydrogen fueling stations, a framework for IOUs’ transportation electrification investments, and vehicle-grid integration. A prehearing conference for this rulemaking was held on March 1, 2019. On May 2, 2019, the assigned commissioner issued a scoping memo and ruling for the proceeding, which sets forth the category, issues to be addressed, and schedule of the proceeding.

### Electric Distribution Resources Plan

As required by California law, on July 1, 2015, the Utility filed its proposed electric DRP for approval by the CPUC. The Utility’s DRP identifies its approach for identifying optimal locations on its electric distribution system for deployment of DERs. The Utility’s DRP approach is designed to allow distributed energy technologies to be integrated into the larger grid, while continuing to provide customers with safe, reliable, and affordable electric service.

As part of the Utility’s DRP approach, on June 1, 2018, the Utility filed its first annual distribution grid needs assessment report with the CPUC, and on September 4, 2018, the Utility filed its first distribution deferral opportunity report. The distribution deferral report proposes cost effective electric distribution investments that can be deferred through deployment of dispatchable third-party-owned DERs, or non-wire alternative solutions, to operate during specific grid events. The Utility convened a distribution planning advisory group comprised of CPUC staff, ratepayer and environmental advocates, and DER market participants, to review and provide advisory input to the Utility on its distribution deferral identification process and to identify distribution deferral opportunities. After incorporating the advisory group’s input, on November 28, 2018, the Utility filed a proposal with the CPUC for competitively procuring distribution services from third-party owned DERs to defer selected distribution projects. Following the CPUC’s approval of the Utility’s procurement plan on February 5, 2019, the Utility launched a competitive solicitation and is currently evaluating offers. The Utility’s next annual distribution grid was assessed and distribution deferral opportunity reports were filed and served on August 15, 2019. On November 15, 2019, the Utility will file a proposal with the CPUC for competitively procuring distribution services from third-party owned DERs to defer selected distribution projects.

On March 26, 2018, the CPUC issued a final decision requiring the Utility to include a grid modernization plan for integrating DERs in the Utility’s GRC. The grid modernization plan for DERs must include a narrative 10-year vision for investments needed to support DER growth, while ensuring safety and service reliability. On June 25, 2018, the Utility hosted a public grid modernization workshop for integrating DERs to provide a high-level overview of its vision and 10-year plan and incorporate stakeholder input. On December 13, 2018, the Utility filed its 2020 GRC Application, which includes the Utility’s grid modernization vision and plan. On June 28, 2019, PAO submitted testimony recommending changes to the Utility’s grid modernization vision and plan in the Utility’s 2020 GRC application. See summary of PAO’s overall 2020 GRC testimony in “2020 General Rate Case” above.

### OIR to Consider Strategies and Guidance for Climate Change Adaptation

On April 26, 2018, the CPUC opened an OIR to consider strategies for integrating climate change adaptation matters into relevant CPUC proceedings. On October 10, 2018, the CPUC issued a scoping memo, establishing two phases for this proceeding, and determined a procedural schedule. Scope of Phase 1 is on how to integrate climate change adaptation into the IOUs’ existing planning and operations to avoid or mitigate projected utility safety and reliability vulnerability to forecasted climate change impacts. Phase 2 will be scoped at a later time, but it is not expected to apply to the Utility. On October 24, 2019, the CPUC adopted a final decision extending the statutory deadline of this proceeding to September 30, 2020.

On September 16, 2019, the assigned commissioner issued a proposed decision in this proceeding addressing some of the issues scoped in Phase 1. On October 24, 2019, the CPUC adopted another final decision that defines climate change adaptation for California’s energy utilities as “adjustment in natural and human systems to a new or changing environment. Adaptation to climate change for energy utilities regulated by the CPUC refers to adjustment in utility systems using strategic and data-driven consideration of actual or expected climatic impacts and stimuli or their effects on utility planning, facilities maintenance and construction, and communications, to maintain safe, reliable, affordable and resilient operations.” In addition, the data guidance developed in the final decision applies to all climate impact, climate risk, and climate vulnerability analyses undertaken by the investor-owned utilities with respect to their infrastructure assets, operations, and customer impacts. Finally, the final decision requires the energy utilities to adhere to the same climate scenarios and projections used in the most recent California Statewide Climate Change Assessment when analyzing climate impacts, climate risk, and climate vulnerability of utility systems, operations, and customers.

The remaining issues in Phase 1 of this proceeding include guidance on how utilities should incorporate climate adaptation into their investment plans program design and operations; how climate change might affect vulnerable and disadvantaged communities; and into which specific commission proceedings and activities climate adaptation should be incorporated, including development of specific procedures. Such issues will be considered in a subsequent decision anticipated no earlier than mid-2020.

### OIR to Examine Utility De-energization of Power Lines in Dangerous Conditions

On December 13, 2018, the CPUC opened an OIR to examine the notification, mitigation, and reporting requirements on electric utilities when de-energizing power lines in case of dangerous conditions that threaten life or property in California. This proceeding has focused on the following issues:

- examining conditions in which proactive and planned de-energization is practiced;
- developing best practices and ensuring an orderly and effective set of criteria for evaluating de-energization programs;
- ensuring electric utilities coordinate with state and local level first responders, and align their systems with the Standardized Emergency Management System framework;
- mitigating the impact of de-energization on vulnerable populations;
- examining whether there are ways to reduce the need for de-energization;
- ensuring effective notice to affected stakeholders of possible de-energization and follow-up notice of actual de-energization; and
- ensuring consistency in notice and reporting of de-energization events.

On May 30, 2019, the CPUC approved a decision for phase one of this proceeding, which adopted de-energization communication and notification guidelines for the electric IOUs along with updates to requirements established in Resolution ESRB-8. The CPUC also provided clarity on phase two issues; however, a final determination of phase two issues will be conveyed in the phase two scoping memo. Phase two will take a more comprehensive look at de-energization practices, including mitigation, additional coordination across agencies, further refinements to findings in phase one, re-energization practices, and other matters.

On August 14, 2019, the former CPUC president issued a phase two scoping memo. However, subsequent to the October PSPS events, on November 1, 2019, the assigned ALJ issued a ruling suspending the schedule and scope of the proceeding and indicating that the current CPUC president will issue an amended phase two scoping memo in the near future in order to refocus the direction of the proceeding. The Utility is unable to predict the timing and outcome of this proceeding.

### OIR to Develop a Risk-Based Decision-Making Framework to Evaluate Safety and Reliability Improvements and Revise the GRC Plan

On October 4, 2019, the assigned commissioner issued a proposed decision that, if adopted, would provide for a four-year GRC cycle and combine the Utility’s future GRC and GT&S rate cases. Specifically, the current three-year GRC cycle would be changed to a four-year cycle, beginning with the Utility’s 2023 GRC. The proposed decision’s schedule would call for the RAMP submittal in March 2020, followed by the GRC application in March 2021.

As modified by the proposed decision, the filing date for GRC applications would be moved up six months from September 1 to March 1 of the year that is two years prior to the test year. This earlier submittal would be designed to provide additional time to the CPUC’s PAO to complete its review, and for the ALJ to prepare a proposed decision that could be voted upon prior to the test year. As mentioned above, the Utility would also be required to combine its currently-separate GRC and GT&S rate cases into a single rate case application beginning with its March 2020 RAMP submittal and the GRC application due to be filed in March 2021 for its 2023 test year.

The proposed decision would also deny a recommendation from the CPUC staff to open a new rulemaking to revisit its policies on the Utility’s recovery of income tax expenses and related rate base issues.

The Utility expects that a final decision could be issued, at the earliest, on November 7, 2019.

### LEGISLATIVE AND REGULATORY INITIATIVES

### Senate Bill 901

SB 901, signed into law on September 21, 2018, requires the CPUC to establish a CHT, directing the CPUC to limit certain disallowances in the aggregate, so that they do not exceed the CHT. SB 901 also authorizes the CPUC to issue a financing order that permits recovery, through the issuance of recovery bonds (also referred to as “securitization”), of wildfire-related costs found to be just and reasonable by the CPUC and, only for the 2017 Northern California wildfires, any amounts in excess of the CHT. SB 901 does not authorize securitization with respect to possible 2018 Camp fire costs.

On January 10, 2019, the CPUC adopted an OIR, which establishes a process to develop criteria and a methodology to inform determinations of the CHT in future applications under Section 451.2(a) of the Public Utilities Code for recovery of costs related to the 2017 Northern California wildfires. On March 29, 2019, the assigned commissioner issued a scoping memo, which confirmed that the CPUC in this proceeding would establish a CHT methodology applicable only to 2017 fires, to be invoked in connection with a future application for cost recovery, and would not determine a specific financial outcome in this proceeding. On July 8, 2019, the CPUC issued a decision in the OIR, which establishes a methodology to establish the CHT in future applications under Section 451.2(a), but determines that a utility that has filed for relief under Chapter 11 cannot access the CHT. On August 7, 2019, the Utility submitted to the CPUC an application for rehearing of the decision. The Utility indicated in its application, among other things, that the CPUC’s decision “is contrary to law because it bars a utility that has filed for Chapter 11 from accessing the CHT, requires a utility to file a cost recovery application before the CHT will be determined, and erects ratepayer protection mechanisms as an extra-statutory hurdle for accessing the CHT.” The Utility also argued that the CPUC should apply the CHT methodology to costs related to the 2018 Camp fire.

(See “Regulatory Matters - OIR to Implement Public Utilities Code Section 451.2 Regarding Criteria and Methodology for Wildfire Cost Recovery Pursuant to Senate Bill 901” above.)

In addition, SB 901 requires utilities to submit annual wildfire mitigation plans for approval by the CPUC on a schedule to be established by the CPUC. The wildfire mitigation plan must include the components specified in SB 901, such as identification and prioritization of wildfire risks, and drivers for those risks; plans for vegetation management; actions to harden the system, prepare for, and respond to events; and protocols for disabling reclosers and deenergizing the system. The CPUC has three months to approve a utility’s plan, with the ability to extend the deadline. The CPUC will conduct an annual compliance review, which will be supported by an independent evaluator’s report. The CPUC will complete the compliance review within 18 months. SB 901 establishes factors to be considered by the CPUC when setting penalties for failure to substantially comply with the plan. Costs associated with the wildfire mitigation plan are tracked in a memorandum account, and the costs of implementing the plan will be assessed in each utility’s GRC proceeding, or other application proceedings. The Utility is unable to predict the timing or outcome of the CPUC’s review of the wildfire mitigation plan, the results of the CPUC compliance review of wildfire mitigation plan implementation, or the timing or extent of cost recovery for wildfire mitigation plan activities.

### Assembly Bill 1054

On July 12, 2019, the California Governor signed into law AB 1054, a bill which provides for the establishment of a statewide fund that will be available for eligible electric utility companies to pay eligible claims for liabilities arising from wildfires occurring after July 12, 2019 that are caused by the applicable electric utility company’s equipment, subject to the terms and conditions of AB 1054. Eligible claims are claims for third party damages resulting from any such wildfires, limited to the portion of such claims that exceeds the greater of (i) $1.0 billion in the aggregate in any calendar year and (ii) the amount of insurance coverage required to be in place for the electric utility company pursuant to section 3293 of the Public Utilities Code, added by AB 1054.

Each of California’s large investor-owned electric utility companies that are not currently subject to Chapter 11 (Southern California Edison and San Diego Gas & Electric Company) has elected to participate in the Wildfire Fund to be established under AB 1054. On July 23, 2019, the Utility notified the CPUC of its intent to participate in the Wildfire Fund (which participation is subject to the conditions set forth in AB 1054, including those conditions outlined below).

The Wildfire Fund to be established under AB 1054 will be available for eligible electric utility companies to pay eligible claims for liabilities arising from wildfires occurring after July 12, 2019 that are caused by the applicable electric utility company’s equipment. Electric utility companies that draw from the fund will only be required to repay amounts that are determined by the CPUC in an application for cost recovery not to be just and reasonable, subject to a rolling three-year disallowance cap equal to 20% of the electric utility company’s transmission and distribution equity rate base. For the Utility, this disallowance cap is expected to be approximately $2.3 billion for the three-year period starting in 2019, subject to adjustment based on changes in the Utility’s total transmission and distribution equity rate base. The disallowance cap is inapplicable in certain circumstances, including if the Wildfire Fund administrator determines that the electric utility company’s actions or inactions that resulted in the applicable wildfire constituted “conscious or willful disregard for the rights and safety of others,” or the electric utility company fails to maintain a valid safety certification. Costs that the CPUC determines to be just and reasonable will not need to be repaid to the fund, resulting in a draw-down of the fund. The Wildfire Fund and disallowance cap will be terminated when the amounts therein are exhausted. The Wildfire Fund is expected to be capitalized with (i) $10.5 billion of proceeds of bonds supported by a 15-year extension of the Department of Water Resources charge to ratepayers, (ii) $7.5 billion in initial contributions from California’s three investor-owned electric utility companies and (iii) $300 million in annual contributions paid by California’s three investor-owned electric utility companies. The contributions from the investor-owned electric utility companies will be effectively borne by their respective shareholders, as they will not be permitted to recover these costs from ratepayers. The costs of the initial and annual contributions are allocated among the three investor-owned electric utility companies pursuant to a “Wildfire Fund allocation metric” set forth in AB 1054 based on land area in the applicable utility’s service territory classified as high fire threat districts and adjusted to account for risk mitigation efforts. The Utility’s initial Wildfire Fund allocation metric is expected to be 64.2% (representing an initial contribution of approximately $4.8 billion and annual contributions of approximately $193 million). In addition, all initial and annual contributions will be excluded from the measurement of the Utility’s authorized capital structure. The Wildfire Fund will only be available for payment of eligible claims so long as there are sufficient funds remaining in the Wildfire Fund. Such funds could be depleted more quickly than expected, including as a result of claims made by California’s other participating electric utility companies.

AB 1054 provides that the Wildfire Fund will be established when Southern California Edison and San Diego Gas & Electric Company provide their initial contributions. On September 11, 2019, Southern California Edison and San Diego Gas & Electric Company notified the CPUC that each had provided its respective initial contribution to the Wildfire Fund.

In order to participate in the Wildfire Fund, within 60 days of the effective date of AB 1054, the Utility must obtain the Bankruptcy Court’s approval of the Utility’s election to pay the initial and annual Wildfire Fund contributions upon emergence from Chapter 11. The Utility would then be required to pay its share of the initial contribution to the Wildfire Fund upon emergence from Chapter 11, and meet certain eligibility requirements listed below, in order to participate in the Wildfire Fund. In such event (assuming the Utility satisfies the eligibility and other requirements set forth in AB 1054), the Wildfire Fund will be available to the Utility to pay for eligible claims arising between the effective date of AB 1054 and the Utility’s emergence from Chapter 11, subject to a limit of 40% of the amount of such claims. The balance of any such claims would need to be addressed through the Chapter 11 Cases. There are several additional eligibility requirements for the Utility, including that by June 30, 2020, the following conditions are satisfied:

- the Utility’s Chapter 11 Case has been resolved pursuant to a plan of reorganization or similar document not subject to a stay;
- the Bankruptcy Court has determined that the resolution of the Utility’s Chapter 11 Case provides funding or otherwise provides for the satisfaction of any pre-petition wildfire claims asserted against the Utility in the Chapter 11 Case, in the amounts agreed upon in any settlement agreements, authorized by the Bankruptcy Court through an estimation process or otherwise allowed by the Bankruptcy Court;
- the CPUC has approved the Utility’s plan of reorganization and other documents resolving its Chapter 11 Case, including the Utility’s resulting governance structure as being acceptable in light of the Utility’s safety history, criminal probation, recent financial condition and other factors deemed relevant by the CPUC;
- the CPUC has determined that the Utility’s plan of reorganization and other documents resolving its Chapter 11 Case are (i) consistent with California’s climate goals as required pursuant to the California Renewables Portfolio Standard Program and related procurement requirements and (ii) neutral, on average, to the Utility’s ratepayers; and
- the CPUC has determined that the Utility’s plan of reorganization and other documents resolving its Chapter 11 Case recognize the contributions of ratepayers, if any, and compensate them accordingly through mechanisms approved by the CPUC, which may include sharing of value appreciation.

On August 23, 2019, the CPUC granted the Utility its Initial Safety Certification, which is valid for 12 months. While not a requirement for participation in the Wildfire Fund, a valid safety certification allows the Utility to benefit from AB 1054’s disallowance cap. (See “2019 Wildfire Mitigation Plan” above.)

On August 7, 2019, PG&E Corporation and the Utility submitted a motion with the Bankruptcy Court for the entry of an order authorizing PG&E Corporation and the Utility to participate in the Wildfire Fund and to make any initial and annual contributions to the Wildfire Fund upon emergence from Chapter 11. On August 26, 2019, the Bankruptcy Court entered an order granting such authorizations.

If the Utility satisfies the requirements to participate in the Wildfire Fund, the Utility will be required to fund its initial contribution upon its emergence from Chapter 11. The Utility’s required contributions to the Wildfire Fund will be substantial. Participation in the Wildfire Fund is expected to have a material impact on PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows. The Utility is currently evaluating the tax treatment of the required initial and annual contributions. The timing and amount of any potential charges associated with shareholder contributions would also depend on various factors, including the timing of resolution of the Chapter 11 Cases, the expected life of the Wildfire Fund, and the impact of future wildfires on the Wildfire Fund's claims passing capacity. The Proposed Plan filed with the Bankruptcy Court on September 23, 2019 would provide for the financing of such required contributions, but there can be no assurance that PG&E Corporation and the Utility will successfully consummate or implement any such plan, which will ultimately require Bankruptcy Court, creditor and regulatory approval. Further, there can be no assurance that the expected benefits of participating in the Wildfire Fund ultimately outweigh its substantial costs.

The Utility expects to record its required contributions as an asset and amortize the asset over the estimated life of the Wildfire Fund. The Wildfire Fund asset will be further adjusted for impairment as the assets are used to pay eligible claims, which will result in decreases to the assets available for coverage of future events. AB 1054 does not establish a definite term of the Wildfire Fund; therefore, this accounting treatment is subject to significant judgments and estimates. The assumptions create a high degree of uncertainty related to the estimated useful life of the Wildfire Fund. The most significant estimate is the number and severity of catastrophic fires that could occur in California within the participating electric utilities’ service territories during the term of the Wildfire Fund. The Utility intends to utilize historical, publicly available fire-loss data as a starting point; however, future fire-loss can be difficult to estimate due to uncertainties around the impacts of climate change, land use changes, and mitigation efforts by the California electric utility companies. Other assumptions include the estimated cost of wildfires caused by other electric utilities, the amount at which wildfire claims will be settled, the likely adjudication of the CPUC in cases of electric utility-caused wildfires, the level of future insurance coverage held by the electric utilities, and the future transmission and distribution equity rate base growth of other electric utilities. Significant changes in any of these estimates could materially impact the amortization period. There could also be a significant delay between the occurrence of a wildfire and the timing of which the Utility recognizes impairment for the reduction in future coverage, due to the lack of data available to the Utility following a catastrophic event, especially if the wildfire occurs in the service territory of another electric utility. As of September 30, 2019, the Utility has not reflected the required contributions in its Condensed Consolidated Financial Statements as it has not yet satisfied all of the Wildfire Fund eligibility criteria pursuant to AB 1054.

AB 1054 includes certain modifications to the “just and reasonable” standard to be utilized by the CPUC in determining applications for recovery of wildfire-related costs. These modifications will apply to wildfires occurring following the effective date of AB 1054. AB 1054 provides that costs and expenses arising from any such wildfires “are just and reasonable if the conduct of the electrical corporation related to the ignition was consistent with actions that a reasonable utility would have undertaken in good faith under similar circumstances, at the relevant point in time, and based on the information available to the electrical corporation at the relevant point of time.” Further, in applying such standard, the CPUC is directed to take into account factors “both within and beyond the utility’s control that may have exacerbated the costs and expenses, including humidity, temperature, and winds.” Finally, AB 1054 modifies the circumstances under which an electric utility company bears the burden of demonstrating that its conduct was reasonable in accordance with the above standard.

AB 1054 also provides that the first $5.0 billion expended in the aggregate by California’s three investor-owned electric utility companies on fire risk mitigation capital expenditures included in their respective approved wildfire mitigation plans will be excluded from their respective equity rate bases. The $5.0 billion of capital expenditures will be allocated among the investor-owned electric utility companies in accordance with their Wildfire Fund allocation metrics (described above). AB 1054 contemplates that such capital expenditures may be securitized through a customer charge.

### Power Charge Indifference Adjustment OIR

In 2017, the CPUC initiated the PCIA Rulemaking to make refinements to the PCIA, a cost recovery mechanism to ensure that customers that leave the Utility’s bundled service for a non-Utility provider pay their fair share of the above market costs associated with long-term power purchase commitments and utility-owned generation made on their behalf. The above market costs of the Utility’s generation portfolio are calculated using benchmarks for brown power, resource adequacy (RA) and renewable portfolio standard (RPS) attributes. On October 11, 2018, the CPUC approved a Phase 1 decision to modify the PCIA methodology establishing:

- calculation of the PCIA rate using benchmark values that more closely resemble actual market prices for RA and RPS;
- continued recovery of legacy utility-owned generation costs from CCA customers;
- elimination of the 10-year limit on PCIA cost recovery for post-2002 utility owned generation and certain storage costs; and
- an annual true-up of the PCIA rate based on actual market sales.

The Utility implemented a revised PCIA reflecting this decision in rates as of July 1, 2019.

On December 19, 2018, the CPUC initiated Phase 2 of the PCIA proceeding to address unresolved issues from Phase 1, separated into three Working Groups. In Working Group 1, the CPUC directed parties to (1) establish the method to annually update the RA and RPS price benchmarks, (2) determine the process for the annual true-up of PCIA rates to reflect actual market outcomes, and (3) determine the proper billing factors for setting the PCIA rate. A Proposed Decision was issued on September 6, 2019. On October 10, 2019, the CPUC approved a final decision that:

- approves a methodology for annually setting the price benchmark for RA and RPS based on market transactions of all load-serving entities occurring within the past 12 months;
- values any unsold RA and RPS transactions at zero for calculating the PCIA true-up at year end, meaning that bundled customers are not responsible for paying for RA and RPS attributes that are not needed for compliance; and
- establishes that the PCIA rates shall be calculated using the forecasted sales of customers in a particular billing group, rather than using system-level sales, to prevent a persistent undercollection of PCIA rates.

In Working Group 2, the CPUC ordered parties to develop a framework evaluating and approving a prepayment application, whereby departed load customers could eliminate their PCIA rate through an up-front payment. The working group is still discussing proposals. A proposed decision is expected in Q1 2020.

Lastly, in Working Group 3 the CPUC directed parties to develop structures and rules governing how the Utility addresses excess resources in its portfolio due to load loss to CCA and DA, including standards for active management of the utility’s portfolios. The working group is still discussing proposals. A proposed decision is expected in Q2 2020.

### ENVIRONMENTAL MATTERS

The Utility’s operations are subject to extensive federal, state, and local laws and permits relating to the protection of the environment and the safety and health of the Utility’s personnel and the public. These laws and requirements relate to a broad range of the Utility’s activities, including the remediation of hazardous wastes; the reporting and reduction of carbon dioxide and other GHG emissions; the discharge of pollutants into the air, water, and soil; the reporting of safety and reliability measures for natural gas storage facilities; and the transportation, handling, storage, and disposal of spent nuclear fuel. (See Note 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1 of this Form 10-Q, as well as “Item 1A. Risk Factors” and Note 14 of the Notes to the Consolidated Financial Statements in Item 8 of the 2018 Form 10-K.)

### CONTRACTUAL COMMITMENTS

PG&E Corporation and the Utility enter into contractual commitments in connection with future obligations that relate to purchases of electricity and natural gas for customers, purchases of transportation capacity, purchases of renewable energy, and purchases of fuel and transportation to support the Utility’s generation activities. (See “Purchase Commitments” in Note 11 of the Notes to the Condensed Consolidated Financial Statements in Item 1). Contractual commitments that relate to financing arrangements include long-term debt, preferred stock, and certain forms of regulatory financing. For more in-depth discussion about PG&E Corporation’s and the Utility’s contractual commitments, see “Liquidity and Financial Resources” above and MD&A “Contractual Commitments” in Item 7 of the 2018 Form 10-K.

### Off-Balance Sheet Arrangements

PG&E Corporation and the Utility do not have any off-balance sheet arrangements that have had, or are reasonably likely to have, a current or future material effect on their financial condition, changes in financial condition, revenues or expenses, results of operations, liquidity, capital expenditures, or capital resources, other than those discussed in Note 14 of the Notes to the Consolidated Financial Statements in Item 8 of the 2018 Form 10-K (the Utility’s commodity purchase agreements).

### RISK MANAGEMENT ACTIVITIES

PG&E Corporation, mainly through its ownership of the Utility, and the Utility are exposed to risks associated with adverse changes in commodity prices, interest rates, and counterparty credit.

The Utility actively manages market risk through risk management programs designed to support business objectives, discourage unauthorized risk-taking, reduce commodity cost volatility, and manage cash flows. The Utility uses derivative instruments only for risk mitigation purposes and not for speculative purposes. The Utility’s risk management activities include the use of physical and financial instruments such as forward contracts, futures, swaps, options, and other instruments and agreements, most of which are accounted for as derivative instruments. Some contracts are accounted for as leases. The Utility manages credit risk associated with its counterparties by assigning credit limits based on evaluations of their financial conditions, net worth, credit ratings, and other credit criteria as deemed appropriate. Credit limits and credit quality are monitored periodically. These activities are discussed in detail in the 2018 Form 10-K. There were no significant developments to the Utility’s and PG&E Corporation’s risk management activities during the nine months ended September 30, 2019.

### RECENT DEVELOPMENTS

### New Chief Executive Officer of the Utility and Board Members

On August 19, 2019, Andrew M. Vesey became the Chief Executive Officer and President of the Utility. On September 11, 2019, Mr. Vesey was elected to the Board of Directors of the Utility.

On October 11, 2019, William L. Smith and John M. Woolard were elected to the Boards of Directors of PG&E Corporation and the Utility.

### CRITICAL ACCOUNTING POLICIES

The preparation of the Condensed Consolidated Financial Statements in accordance with GAAP involves the use of estimates and assumptions that affect the recorded amounts of assets and liabilities as of the date of the Condensed Consolidated Financial Statements and the reported amounts of revenues and expenses during the reporting period. In addition to those items listed below, PG&E Corporation and the Utility consider their accounting policies for regulatory assets and liabilities, loss contingencies associated with environmental remediation liabilities and legal and regulatory matters, AROs, and pension and other post-retirement benefits plans to be critical accounting policies. These policies are considered critical accounting policies due, in part, to their complexity and because their application is relevant and material to the financial position and results of operations of PG&E Corporation and the Utility, and because these policies require the use of material judgments and estimates. Actual results may differ materially from these estimates. These accounting policies and their key characteristics are discussed in detail in the 2018 Form 10-K.

### Liabilities Subject to Compromise

As a result of the commencement of the Chapter 11 Cases, the payment of pre-petition liabilities is subject to compromise or other treatment pursuant to a plan of reorganization. The determination of how liabilities will ultimately be settled or treated cannot be made until the Bankruptcy Court confirms a Chapter 11 plan of reorganization and such plan becomes effective. Accordingly, the ultimate amount of such liabilities is not determinable at this time. GAAP requires pre-petition liabilities that are subject to compromise to be reported at the amounts expected to be allowed by the Bankruptcy Court, even if they may be settled for different amounts. The amounts currently classified as LSTC are preliminary and may be subject to future adjustments depending on Bankruptcy Court actions, further developments with respect to disputed claims, determinations of the secured status of certain claims, the values of any collateral securing such claims, rejection of executory contracts, continued reconciliation or other events.

### ACCOUNTING STANDARDS ISSUED BUT NOT YET ADOPTED

See the discussion above in Note 3 of the Notes to the Condensed Consolidated Financial Statements in Item 1.

### FORWARD-LOOKING STATEMENTS

This report contains forward-looking statements that are necessarily subject to various risks and uncertainties. These statements reflect management’s judgment and opinions that are based on current estimates, expectations, and projections about future events and assumptions regarding these events and management’s knowledge of facts as of the date of this report. These forward-looking statements relate to, among other matters, estimated losses, including penalties and fines, associated with various investigations and proceedings; forecasts of pipeline-related expenses that the Utility will not recover through rates; forecasts of capital expenditures; estimates and assumptions used in critical accounting policies, including those relating to regulatory assets and liabilities, environmental remediation, litigation, third-party claims, and other liabilities; and the level of future equity or debt issuances. These statements are also identified by words such as “assume,” “expect,” “intend,” “forecast,” “plan,” “project,” “believe,” “estimate,” “predict,” “anticipate,” “may,” “should,” “would,” “could,” “potential” and similar expressions. PG&E Corporation and the Utility are not able to predict all the factors that may affect future results. Some of the factors that could cause future results to differ materially from those expressed or implied by the forward-looking statements, or from historical results, include, but are not limited to:

- the risks and uncertainties associated with the Chapter 11 Cases, including, but not limited to, the ability to develop, consummate, and implement a plan of reorganization with respect to PG&E Corporation and the Utility, which could be adversely affected by the termination of the Exclusive Periods as to the TCC and the Ad Hoc Noteholder Committee; the ability to obtain applicable Bankruptcy Court, creditor or regulatory approvals; the effect of any alternative proposals, views or objections related to the plan of reorganization; potential complexities that may arise in connection with concurrent proceedings involving the Bankruptcy Court, the U.S. District Court, the California state court, the CPUC, and the FERC; increased costs related to the Chapter 11 Cases; the ability to obtain sufficient financing sources for ongoing and future operations; the ability to satisfy the conditions precedent to financing under the Backstop Commitment Letters and the Debt Commitment Letters and the risk that such agreements may be terminated; disruptions to PG&E Corporation’s and the Utility’s business and operations and the potential impact on regulatory compliance;
- whether, in light of the CPUC July 8, 2019 final decision in the CHT OIR that excludes companies in Chapter 11 from accessing the CHT, the Utility will be able to obtain a substantial recovery of costs related to the 2017 Northern California wildfires;
- restrictions on PG&E Corporation’s and the Utility’s ability to pursue strategic and operational initiatives for the duration of the Chapter 11 Cases;
- PG&E Corporation’s and the Utility’s historical financial information not being indicative of future financial performance as a result of the Chapter 11 Cases;
- the potential delay in emergence from bankruptcy if PG&E Corporation and the Utility are not able to develop and consummate a consensual plan of reorganization and are forced to engage in a contested proceeding;
- the possibility that the DIP Credit Agreement is not sufficient to fund PG&E Corporation’s and the Utility’s cash requirements through their emergence from bankruptcy;
- the possibility that PG&E Corporation and the Utility may not be able to obtain exit financing on favorable terms or at all;
- the impact of AB 1054 on potential losses in connection with future wildfires;
- the outcome of the U.S. District Court matters and probation;
- the impact of the 2018 Camp fire and the 2017 Northern California wildfires, including whether the Utility will be able to timely recover costs incurred in connection with the wildfires in excess of the Utility’s currently authorized revenue requirements; the timing and outcome of the remaining wildfire investigations and the extent to which the Utility will have liability associated with these fires; the timing and amount of insurance recoveries; the timing and outcome of the 2017 Northern California Wildfires OII and potential liabilities in connection with fines or penalties that could be imposed on the Utility if the CPUC or any other law enforcement agency were to bring an enforcement action, including a criminal proceeding, and determined that the Utility failed to comply with applicable laws and regulations;
- the risks and uncertainties associated with the 2019 Kincade fire;
- the timing and outcome of any potential settlement with holders of wildfire-related claims;
- the ability of PG&E Corporation and the Utility to finance costs, expenses and other possible losses in respect of claims related to the 2018 Camp fire and the 2017 Northern California wildfires, through securitization mechanisms or otherwise, which potential financings are not addressed by AB 1054 as it only applies to wildfires occurring after July 12, 2019;
- the timing and outcome of claims arising from the 2015 Butte fire, including claims by the OES; the timing and outcome of any proceeding to recover related costs in excess of insurance through rates; and whether any regulatory enforcement proceedings in connection with the 2015 Butte fire will be opened and any additional fines or penalties imposed on the Utility;
- whether PG&E Corporation and the Utility are able to successfully challenge the application of the doctrine of inverse condemnation to the 2018 Camp fire, the 2017 Northern California wildfires and the 2015 Butte fire;
- the timing and outcome of future regulatory and legislative developments in connection with SB 901, including future wildfire reforms, inverse condemnation reform, and other wildfire mitigation measures or other reforms targeted at the Utility;
- the outcome of the Utility’s CWSP that the Utility has developed in coordination with first responders, civic and community leaders, and customers, to help reduce wildfire threats and improve safety as a result of climate-driven wildfires and extreme weather, including the Utility’s ability to comply with the targets and metrics set forth in the 2019 Wildfire Mitigation Plan; and the cost of the program, including any costs in connection with PSPS events, and the timing and outcome of any proceeding to recover such cost through rates;
- whether the Utility will be able to obtain full recovery of its significantly increased insurance premiums, and the timing of any such recovery;
- whether the Utility can obtain wildfire insurance at a reasonable cost in the future, or at all, and whether insurance coverage is adequate for future losses or claims;
- increased employee attrition as a result of the filing of the Chapter 11 Cases;
- the timing and outcomes of the 2019 GT&S rate case, 2020 GRC, FERC TO18, TO19, and TO20 rate cases, 2018 CEMA, future applications for WEMA, FHPMA and FRMMA, future cost of capital proceeding, and other ratemaking and regulatory proceedings;
- the outcome of the probation and the monitorship imposed by the federal court after the Utility’s conviction in the federal criminal trial in 2017, the timing and outcomes of the debarment proceeding, potential reliability penalties or sanctions from the North American Electric Reliability Corporation, the SED’s unresolved enforcement matters relating to the Utility’s compliance with natural gas-related laws and regulations, and other investigations that have been or may be commenced relating to the Utility’s compliance with natural gas- and electric- related laws and regulations, ex parte communications, and the ultimate amount of fines, penalties, and remedial costs that the Utility may incur in connection with the outcomes;
- the effects on PG&E Corporation’s and the Utility’s reputations caused by matters such as the CPUC’s investigations of natural gas and electric incidents, the 2018 Camp fire and 2017 Northern California wildfires, locate and mark, improper communications between the CPUC and the Utility, the Utility’s ongoing enhanced and accelerated inspection of its electric transmission and distribution assets, and the implementation of the Utility’s PSPS program;
- the implementation of the Safety Culture OII decision approved on November 29, 2018, and the outcome of the proceeding, and future legislative or regulatory actions that may be taken, such as requiring the Utility to separate its electric and natural gas businesses, or restructure into separate entities, or undertake some other corporate restructuring, or transfer ownership of the Utility’s assets to municipalities or other public entities, or implement corporate governance changes;
- whether the Utility can control its costs within the authorized levels of spending, and timely recover its costs through rates; whether the Utility can continue implementing a streamlined organizational structure and achieve project savings, the extent to which the Utility incurs unrecoverable costs that are higher than the forecasts of such costs; and changes in cost forecasts or the scope and timing of planned work resulting from changes in customer demand for electricity and natural gas or other reasons;
- whether the Utility and its third-party vendors and contractors are able to protect the Utility’s operational networks and information technology systems from cyber- and physical attacks, or other internal or external hazards;
- the timing and outcome of the October 1, 2018 request for rehearing of FERC’s denial of the complaint filed by the CPUC and certain other parties that the Utility provide an open and transparent planning process for its capital transmission projects that do not go through the CAISO’s Transmission Planning Process to allow for greater participation and input from interested parties; and the timing and ultimate outcome of the Ninth Circuit Court of Appeals decision on January 8, 2018, to reverse FERC’s decision granting the Utility a 50 basis point ROE incentive adder for continued participation in the CAISO and remanding the case to FERC for further proceedings;
- the outcome of current and future self-reports, investigations, or other enforcement proceedings that could be commenced or notices of violation that could be issued relating to the Utility’s compliance with laws, rules, regulations, or orders applicable to its operations, including the construction, expansion, or replacement of its electric and gas facilities, electric grid reliability, inspection and maintenance practices, customer billing and privacy, physical and cybersecurity, environmental laws and regulations; and the outcome of existing and future SED notices of violations;
- the impact of environmental remediation laws, regulations, and orders; the ultimate amount of costs incurred to discharge the Utility’s known and unknown remediation obligations; and the extent to which the Utility is able to recover environmental costs in rates or from other sources;
- the impact of SB 100, which was signed into law on September 10, 2018, that increases the percentage from 50% to 60% of California’s electricity portfolio that must come from renewables by 2030; and establishes state policy that 100% of all retail electricity sales must come from renewable portfolio standard-eligible or carbon-free resources by 2045;
- how the CPUC and the California Air Resources Board implement state environmental laws relating to GHG, renewable energy targets, energy efficiency standards, DERs, EVs, and similar matters, including whether the Utility is able to continue recovering associated compliance costs, such as the cost of emission allowances and offsets under cap-and-trade regulations; and whether the Utility is able to timely recover its associated investment costs;
- the impact of the California governor’s executive order issued on January 26, 2018, to implement a new target of five million zero-emission vehicles on the road in California by 2030;
- the ultimate amount of unrecoverable environmental costs the Utility incurs associated with the Utility’s natural gas compressor station site located near Hinkley, California and the Utility’s fossil fuel-fired generation sites;
- the impact of new legislation or NRC regulations, recommendations, policies, decisions, or orders relating to the nuclear industry, including operations, seismic design, security, safety, relicensing, the storage of spent nuclear fuel, decommissioning, cooling water intake, or other issues; the impact of potential actions, such as legislation, taken by state agencies that may affect the Utility’s ability to continue operating Diablo Canyon until its planned retirement;
- the impact of wildfires, droughts, floods, or other weather-related conditions or events, climate change, natural disasters, acts of terrorism, war, vandalism (including cyber-attacks), downed power lines, and other events, that can cause unplanned outages, reduce generating output, disrupt the Utility’s service to customers, or damage or disrupt the facilities, operations, or information technology and systems owned by the Utility, its customers, or third parties on which the Utility relies, and the reparation and other costs that the Utility may incur in connection with such conditions or events; the impact of the adequacy of the Utility’s emergency preparedness; whether the Utility incurs liability to third parties for property damage or personal injury caused by such events; whether the Utility is subject to civil, criminal, or regulatory penalties in connection with such events; and whether the Utility’s insurance coverage is available for these types of claims and sufficient to cover the Utility’s liability;
- whether the Utility’s climate change adaptation strategies are successful;
- the breakdown or failure of equipment that can cause damages, including fires, and unplanned outages; and whether the Utility will be subject to investigations, penalties, and other costs in connection with such events;
- the impact that reductions in Utility customer demand for electricity and natural gas, driven by customer departures to CCAs and DA providers, have on the Utility’s ability to make and recover its investments through rates and earn its authorized return on equity, and whether the Utility is successful in addressing the impact of growing distributed and renewable generation resources, changing customer demand for its natural gas and electric services;
- the supply and price of electricity, natural gas, and nuclear fuel; the extent to which the Utility can manage and respond to the volatility of energy commodity prices; the ability of the Utility and its counterparties to post or return collateral in connection with price risk management activities; and whether the Utility is able to recover timely its electric generation and energy commodity costs through rates, including its renewable energy procurement costs;
- the amount and timing of charges reflecting probable liabilities for third-party claims; the extent to which costs incurred in connection with third-party claims or litigation can be recovered through insurance, rates, or from other third parties; and whether the Utility can continue to obtain adequate insurance coverage for future losses or claims, especially following a major event that causes widespread third-party losses;
- the ability of PG&E Corporation and the Utility to access capital markets and other sources of debt and equity financing in a timely manner and on acceptable terms;
- the impact of the regulation of utilities and their holding companies, including how the CPUC interprets and enforces the financial and other conditions imposed on PG&E Corporation when it became the Utility’s holding company, and whether the uncertainty in connection with the 2018 Camp fire and the 2017 Northern California wildfires, the ultimate outcomes of the CPUC’s pending investigations, and other enforcement matters will impact the Utility’s ability to make distributions to PG&E Corporation;
- the outcome of federal or state tax audits and the impact of any changes in federal or state tax laws, policies, regulations, or their interpretation;
- changes in the regulatory and economic environment, including potential changes affecting renewable energy sources and associated tax credits, as a result of the current federal administration; and
- the impact of changes in GAAP, standards, rules, or policies, including those related to regulatory accounting, and the impact of changes in their interpretation or application.

For more information about the significant risks that could affect the outcome of the forward-looking statements and PG&E Corporation’s and the Utility’s future financial condition, results of operations, liquidity, and cash flows, see Item 1A. Risk Factors below and a detailed discussion of these matters contained elsewhere in MD&A. PG&E Corporation and the Utility do not undertake any obligation to update forward-looking statements, whether in response to new information, future events, or otherwise.

PG&E Corporation and the Utility routinely provide links to the Utility’s principal regulatory proceedings before the CPUC and the FERC at http://investor.pgecorp.com, under the “Regulatory Filings” tab, so that such filings are available to investors upon filing with the relevant agency. PG&E Corporation and the Utility also routinely post or provide direct links to presentations, documents, and other information that may be of interest to investors at http://investor.pgecorp.com, under the “Chapter 11,” “Wildfire Updates” and “News & Events: Events & Presentations” tabs, respectively, in order to publicly disseminate such information. It is possible that any of these filings or information included therein could be deemed to be material information. The information contained on such website is not part of this or any other report that PG&E Corporation or the Utility files with, or furnishes to, the SEC. PG&E Corporation and the Utility are providing the address to this website solely for the information of investors and do not intend the address to be an active link.

## Market risk

As filed, 616 characters.

PG&E Corporation’s and the Utility’s primary market risk results from changes in energy commodity prices. PG&E Corporation and the Utility engage in price risk management activities for non-trading purposes only. Both PG&E Corporation and the Utility may engage in these price risk management activities using forward contracts, futures, options, and swaps to hedge the impact of market fluctuations on energy commodity prices and interest rates. (See the section above entitled “Risk Management Activities” in MD&A and in Note 8 and Note 9 of the Notes to the Condensed Consolidated Financial Statements in Item 1.)

## Controls and procedures

As filed, 1,207 characters.

Based on an evaluation of PG&E Corporation’s and the Utility’s disclosure controls and procedures as of September 30, 2019, PG&E Corporation’s and the Utility’s respective principal executive officers and principal financial officers have concluded that such controls and procedures are effective to ensure that information required to be disclosed by PG&E Corporation and the Utility in reports that the companies file or submit under the Securities Exchange Act of 1934, as amended, is (i) recorded, processed, summarized, and reported within the time periods specified in the SEC rules and forms, and (ii) accumulated and communicated to PG&E Corporation’s and the Utility’s management, including PG&E Corporation’s and the Utility’s respective principal executive officers and principal financial officers, or persons performing similar functions, as appropriate to allow timely decisions regarding required disclosure.

There were no changes in internal control over financial reporting that occurred during the quarter ended September 30, 2019, that have materially affected, or are reasonably likely to materially affect, PG&E Corporation’s or the Utility’s internal control over financial reporting.

## Risk factors

As filed, 13,348 characters.

For information about the significant risks that could affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows, see the section of the 2018 Form 10-K and PG&E Corporation’s and the Utility’s combined Quarterly Report on Form 10-Q for the quarterly period ended March 31, 2019 entitled “Risk Factors,” as supplemented below, and the section of this quarterly report entitled “Forward-Looking Statements.”

***PG&E Corporation’s and the Utility’s financial results could be materially affected as a result of legislative and regulatory developments.***

The Utility’s financial results could be materially affected as a result of SB 901 adopted in 2018 by the California legislature. In December 2018, the CPUC opened an OIR in connection with SB 901 that will adopt criteria and a methodology for use by the CPUC in future applications for cost recovery of wildfire costs. On July 8, 2019, the CPUC issued a decision in the CHT proceeding. The CPUC decision provides that “\[a\]n electrical corporation that has filed for relief under chapter 11 of the Bankruptcy Code may not access the Stress Test to recover costs in an application under Section 451.2(b), because the Commission cannot determine the corporation’s ‘financial status,’ which includes, among other considerations, its capital structure, liquidity needs, and liabilities, as required by Section 451.2(b).” This determination effectively bars PG&E Corporation and the Utility from access to relief under the CHT during the pendency of the Chapter 11 Cases. On August 7, 2019, the Utility submitted to the CPUC an application for rehearing of the decision. Failure to obtain a substantial or full recovery of costs related to wildfires could have a material effect on PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows. (See “Regulatory Matters - Other Regulatory Proceedings” in Item 2. MD&A.)

In addition, SB 901 requires utilities to submit annual wildfire mitigation plans for approval by the CPUC on a schedule to be established by the CPUC. SB 901 establishes factors to be considered by the CPUC when setting penalties for failure to substantially comply with the plan. The Utility is unable to predict the timing or outcome of the CPUC’s review of the wildfire mitigation plan, the results of the CPUC compliance review of wildfire mitigation plan implementation, or the timing or extent of cost recovery for wildfire mitigation plan activities. Failure to substantially comply with the plan could result in fines and other penalties imposed on the Utility that could be material. (See “Regulatory Matters – Other Regulatory Proceedings” in Item 2. MD&A.)

On July 12, 2019, the California Governor signed into law AB 1054, a bill which, among other policy reforms, provides for the establishment of a statewide fund that would be available for eligible electric utility companies to pay eligible claims for liabilities arising from wildfires occurring after July 12, 2019 that are caused by the applicable electric utility company’s equipment. Although PG&E Corporation and the Utility have delivered notice to the CPUC electing to participate in the Wildfire Fund, the impact of AB 1054 on PG&E Corporation and the Utility is subject to numerous uncertainties, including the Utility’s eligibility to access relief under the Wildfire Fund (which is dependent on, among other things, the Chapter 11 Cases being resolved by June 30, 2020 pursuant to a plan or similar document not subject to a stay and the Utility making its initial contribution thereto), the Utility’s ability to demonstrate to the CPUC that wildfire-related costs paid from the Wildfire Fund are just and reasonable, subject to a disallowance cap and that the Wildfire Fund has sufficient remaining funds. Failure to meet the eligibility conditions to access relief under the Wildfire Fund, including the Chapter 11 Cases being resolved by June 30, 2020 and the Utility making its initial contribution thereto, would preclude PG&E Corporation and the Utility from accessing the Wildfire Fund for future wildfire-related claims and any related benefits, including the disallowance cap.

The costs of participating in the Wildfire Fund (should the Utility be eligible to do so) are expected to exceed $6.7 billion. The Utility is currently evaluating the accounting and tax treatment of the required initial and annual contributions. The timing and amount of any potential charges associated with shareholder contributions would also depend on various factors, including the final determination of an allocation of contributions among the Utility and California’s other large electric utility companies (San Diego Gas & Electric Company and Southern California Edison Company) and the timing of resolution of the Chapter 11 Cases. In addition, there could also be a significant delay between the occurrence of a wildfire and the timing of which the Utility recognizes impairment for the reduction in future coverage, due to the lack of data available to the Utility following a catastrophic event, especially if the wildfire occurs in the service territory of another participating electric utility. Participation in the Wildfire Fund is expected to have a material impact on PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity and cash flows, and there can be no assurance that the benefits of participating in the Wildfire Fund ultimately outweigh these substantial costs.

Finally, AB 1054 does not apply to wildfires with an ignition date prior to the effective date of AB 1054. PG&E Corporation and the Utility may be dependent on additional legislative measures in order to facilitate the financing of costs, expenses and other possible losses in respect of claims related to the 2018 Camp fire and the 2017 Northern California wildfires. There can be no assurance that any such legislative measures will be enacted or enacted in a form that would materially address PG&E Corporation’s and the Utility’s financing needs.

Also, in June 2018, the State of California enacted the CCPA, which will come into effect on January 1, 2020, with a 12-month look-back period requiring compliance by January 1, 2019. On October 11, 2019, the State of California announced proposed regulations which provide guidance on the requirements of the CCPA. The CCPA requires companies that process information on California residents to make new disclosures to consumers about their data collection, use and sharing practices, allows consumers to opt out of certain data sharing with third parties and provides a new cause of action for data breaches. The CCPA provides for financial penalties in the event of non-compliance and statutory damages in the event of a data security breach. However, California legislators have stated that they intend to propose amendments to the CCPA, and it remains unclear what, if any, modifications will be made to the CCPA. Failure to comply with the CCPA could result in fines imposed on PG&E Corporation and the Utility that could be material.

***The Utility’s insurance coverage may not be sufficient to cover losses caused by an operating failure or catastrophic events, including severe weather events, or may not be available at a reasonable cost, or available at all.***

The Utility has experienced increased costs and difficulties in obtaining insurance coverage for wildfires and other risks that could arise from the Utility’s ordinary operations. PG&E Corporation, the Utility or its contractors and customers could continue to experience coverage reductions and/or increased insurance costs in future years. No assurance can be given that future losses will not exceed the limits of the Utility’s insurance coverage. Uninsured losses and increases in the cost of insurance may not be recoverable in customer rates. A loss that is not fully insured or cannot be recovered in customer rates could materially affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows.

As a result of the potential application to investor-owned utilities of a strict liability standard under the doctrine of inverse condemnation, recent losses recorded by insurance companies, the risk of increased wildfires including as a result of climate change, the 2018 Camp fire, the 2017 Northern California wildfires, and the 2015 Butte fire, the Utility may not be able to obtain sufficient insurance coverage in the future at a reasonable cost, or at all. In addition, the Utility is unable to predict whether it would be allowed to recover in rates the increased costs of insurance or the costs of any uninsured losses.

If the amount of insurance is insufficient or otherwise unavailable, or if the Utility is unable to obtain insurance at a reasonable cost or recover in rates the costs of any uninsured losses, PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows could be materially affected.

***PG&E Corporation’s and the Utility’s financial results could be materially affected as a result of the Utility’s implementation of its PSPS program.***

As outlined in the 2019 Wildfire Mitigation Plan, PG&E Corporation and the Utility have adopted the PSPS program to proactively de-energize lines that traverse areas under elevated and extreme risks for wildfire when forecasts predict extreme fire-threat conditions. Approximately 5.4 million electric customer premises may potentially be impacted by PSPS events.

Since September 2019, PG&E Corporation and the Utility have carried out several PSPS events. On October 9, 2019, PG&E Corporation and the Utility initiated a PSPS event that shut off power to approximately 738,000 customers in 34 counties across Northern and Central California. By October 12, 2019, all of the customers impacted had their power restored. In response, on October 14, 2019, the California Governor issued a letter to PG&E Corporation describing the “scope and duration” of the outage as “unacceptable” and stating that he had asked the CPUC to “conduct a comprehensive review” of this PSPS event. In addition, the Governor urged that PG&E Corporation and the Utility “provide affected customers an automatic credit or rebate of $100 per residential customer and $250 per small business” and that such rebates “should be funded by shareholders, not ratepayers.” Also on October 14, 2019, the CPUC published a letter to the Utility, in which it described the Utility’s “failures in execution,” combined with the magnitude of the October 9, 2019 PSPS event, as having created “an unacceptable situation that should never be repeated.” The CPUC directed the Utility to “perform an after-action review and take immediate corrective actions” detailed in the letter. On October 18, 2019, the CPUC held an emergency meeting that included, among other parties, certain directors and officers of PG&E Corporation and the Utility, to discuss the PSPS event and the Utility’s PSPS program. Separately, on October 14, 2019, the court overseeing the Utility’s probation issued a request for information on the October 9, 2019 PSPS event, asking the Utility to file a statement setting forth, among other information, “how many trees and limbs fell or blew onto the deenergized lines and how many of those would likely have caused arcing had the power been left on.” On October 28, 2019, the CPUC announced that it would open a formal investigation of 2019 PSPS events, utility compliance with CPUC regulations and requirements, any resulting violations, and potential actions to ensure utilities are held accountable.

PG&E Corporation and the Utility cannot predict the timing and outcome of such an investigation. PG&E Corporation and the Utility could be subject to additional investigations, regulatory proceedings or other enforcement actions as well as to litigation and claims by customers as a result of the Utility’s implementation of its PSPS program, including with respect to the October 9, 2019 PSPS event, which could result in fines, penalties, customer rebates or other payments. On October 29, 2019, PG&E Corporation and the Utility announced that they would issue credits to customers as suggested by the Governor with respect to the October 9, 2019 PSPS event. PG&E Corporation and the Utility estimate that such credit will result in an approximately $90 million charge for the fourth quarter of 2019. As of the date of this filing, PG&E Corporation and the Utility do not expect to issue any similar customer credits in connection with any other PSPS events (whether past events or in the future). The amount of any fines, penalties, customer rebates or other payments (if PG&E Corporation or the Utility were to issue any credits, rebates or other payments in connection with any other PSPS events (whether past events or in the future)) could have a material effect on PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows. In addition, the PSPS program has had an adverse impact on PG&E Corporation’s and the Utility’s reputation with customers, regulators and policymakers and future PSPS events may increase these negative perceptions.