# Sterling Infrastructure, Inc.: Form 10-Q for the period ended Mar 31, 2012

- Company: [Sterling Infrastructure, Inc.](/companies/strl.md) (CIK 874238)
- Form: 10-Q
- Filed: 2012-05-09
- Accepted by EDGAR: May 9, 2012, 17:26 ET
- Period: 2012-03-31
- Accession: 0001140361-12-024059
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/874238/000114036112024059/form10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/874238/000114036112024059/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2012-03-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2012-01-01 to 2012-03-31 | $98.4m | us-gaap:Revenues |
| Cost of revenue | 3 months, 2012-01-01 to 2012-03-31 | $96.6m | us-gaap:CostOfGoodsSold |
| Gross profit | 3 months, 2012-01-01 to 2012-03-31 | $1.9m | us-gaap:GrossProfit |
| Operating income | 3 months, 2012-01-01 to 2012-03-31 | −$4.6m | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months, 2012-01-01 to 2012-03-31 | −$4.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2012-01-01 to 2012-03-31 | −$7.5m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2012-01-01 to 2012-03-31 | −$0.44 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2012-01-01 to 2012-03-31 | −$0.44 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2012-01-01 to 2012-03-31 | 16,322,477 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months, 2012-01-01 to 2012-03-31 | $1.4m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months, 2012-01-01 to 2012-03-31 | $5.9m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Share repurchases | 3 months, 2012-01-01 to 2012-03-31 | $0 | us-gaap:PaymentsForRepurchaseOfCommonStock |
| Cash and equivalents | at 2012-03-31 | $16.6m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2012-03-31 | $166.2m | us-gaap:AssetsCurrent |
| Total assets | at 2012-03-31 | $308.9m | us-gaap:Assets |
| Current liabilities | at 2012-03-31 | $74.1m | us-gaap:LiabilitiesCurrent |
| Long-term debt | at 2012-03-31 | $245.0k | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2012-03-31 | $573.0k | us-gaap:LongTermDebtCurrent |
| Shareholders' equity | at 2012-03-31 | $206.3m | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 46,665 characters.

### Cautionary Comment Regarding Forward-Looking Statements

This Report includes statements that are, or may be considered to be, “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, or the Securities Act, and Section 21E of the Securities Exchange Act of 1934, as amended, or the Exchange Act. These forward-looking statements are included throughout this Report, including in this section, “Management’s Discussion and Analysis of Financial Condition and Results of Operations,” and relate to matters such as our industry, business strategy, goals and expectations concerning our market position, future operations, margins, profitability, capital expenditures, liquidity and capital resources and other financial and operating information. We have used the words “anticipate,” “assume,” “believe,” “budget,” “continue,” “could,” “estimate,” “expect,” “forecast,” “future,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “will,” “would” and similar terms and phrases to identify forward-looking statements in this Report.

Forward-looking statements reflect our current expectations as of the date of this Report regarding future events, results or outcomes. These expectations may or may not be realized. Some of these expectations may be based upon assumptions or judgments that prove to be incorrect. In addition, our business and operations involve numerous risks and uncertainties, many of which are beyond our control, that could result in our expectations not being realized or otherwise could materially affect our financial condition, results of operations and cash flows.

Actual events, results and outcomes may differ materially from our expectations due to a variety of factors. Although it is not possible to identify all of these factors, they include, among others, the following:

- changes in general economic conditions, including recessions, reductions in federal, state and local government funding for infrastructure services and changes in those governments’ budgets, practices, laws and regulations;
- delays or difficulties related to the completion of our projects, including additional costs, reductions in revenues or the payment of liquidated damages, or delays or difficulties related to obtaining required governmental permits and approvals;
- actions of suppliers, subcontractors, design engineers, joint venture partners, customers, competitors, banks, surety companies and others which are beyond our control, including suppliers’, subcontractors’, and joint venture partners’ failure to perform;
- the effects of estimates inherent in our percentage-of-completion accounting policies, including onsite conditions that differ materially from those assumed in our original bid, contract modifications, mechanical problems with our machinery or equipment and effects of other risks discussed in this document;
- design/build contracts which subject us to the risk of design errors and omissions;
- cost escalations associated with our contracts, including changes in availability, proximity and cost of materials such as steel, cement, concrete, aggregates, oil, fuel and other construction materials, and cost escalations associated with subcontractors and labor;
- our dependence on a limited number of significant customers;
- adverse weather conditions; although we prepare our budgets and bid contracts based on historical rain and snowfall patterns, the incidence of rain, snow, hurricanes, etc., may differ materially from these expectations;
- the presence of competitors with greater financial resources or lower margin requirements than ours, and the impact of competitive bidders on our ability to obtain new backlog at reasonable margins acceptable to us;
- our ability to successfully identify, finance, complete and integrate acquisitions;
- citations issued by any governmental authority, including the Occupational Safety and Health Administration;
- federal, state and local environmental laws and regulations where non-compliance can result in penalties and/or termination of contracts as well as civil and criminal liability;
- the instability of certain financial institutions, which could cause losses on our cash and cash equivalents and short-term investments;
- adverse economic conditions in our markets; and
- the other factors discussed in more detail in our Annual Report on Form 10-K for the year ended December 31, 2011 (“2011 Form 10-K”) under “Item 1A. —Risk Factors.”

In reading this Report, you should consider these factors carefully in evaluating any forward-looking statements and you are cautioned not to place undue reliance on any forward-looking statements. Although we believe that our plans, intentions and expectations reflected in, or suggested by, the forward-looking statements that we make in this Report are reasonable, we can provide no assurance that they will be achieved.

*The forward-looking statements included in this Report are made only as of the date of this Report, and we undertake no obligation to update any information contained in this Report or to publicly release the results of any revisions to any forward-looking statements to reflect events or circumstances that occur, or that we become aware of after the date of this Report, except as may be required by applicable securities laws.*

### Overview

Sterling is a leading heavy civil construction company that specializes in the building, reconstruction and repair of transportation and water infrastructure. Transportation infrastructure projects include highways, roads, bridges, light rail and commuter rail. Water infrastructure projects include water, wastewater and storm drainage systems. Sterling provides general contracting services, including excavating, concrete and asphalt paving, installation of large-diameter water and wastewater distribution systems, construction of bridges and similar large structures, construction of light and commuter rail infrastructure, concrete and asphalt batch plant operations, concrete crushing and aggregates operations. Sterling performs the majority of the work required by its contracts with its own crews and equipment.

Sterling has grown its operations by expanding both its service profile and market areas. This involved adding services, such as concrete operations, in order to capture a greater percentage of available work in current and potential markets. It also involved strategically expanding operations, either by establishing a branch office in a new market, often after having successfully bid on and completed a project in that market, or by acquiring a company that gives us an immediate entry into a market. Sterling extended both its service profile and its geographic market reach with the 2009 acquisition of Ralph L. Wadsworth Construction Company, LLC (“RLW”), which has operations primarily in Utah, and the 2011 acquisitions of J. Banicki Construction, Inc. (“JBC”) and Myers & Sons Construction, L.P. (“Myers”) with operations in Arizona and California, respectively.

Sterling operates primarily in Texas, Utah, Nevada, Arizona and California, states that management believes benefit from both positive long-term demographic trends as well as a historical commitment to funding transportation and water infrastructure projects. Currently, the Company also has highway construction contracts in Hawaii, Montana and Louisiana. From 2005 to 2010, the populations of Texas, Utah, Nevada, Arizona and California grew 10.2%, 15.8%, 14.8%, 9.1% and 3.5%, respectively, compared to approximately 4.5% for the national average. While the near-term funding available to these markets is currently limited, management anticipates that long-term population growth and increases in required spending for infrastructure in these markets will positively affect business opportunities over the coming years.

For a more detailed discussion of the Company’s business, readers of this report are advised to review “Item 1, Business,” of the 2011 Form 10-K.

For purposes of the discussions which follow, “Current Quarter” refers to the three month period ended March 31, 2012 and “Prior Quarter” refers to the three month period ended March 31, 2011.

### Financial Results for 2010, 2011 and the Current Quarter, Operational Issues and Outlook for 2012 Financial Results

As discussed further in the 2011 Form 10-K, the Company’s 2011 results were well below those of 2010 as a result of a pre-tax charge of $67.0 million related to the impairment of goodwill and a decline in our overall margins which were adversely affected by production issues on a number of construction projects, primarily in the fourth quarter of 2011. These declines were in part a result of revisions to estimated profitability on construction projects, both favorable and unfavorable, which resulted in a net pre-tax charge of $11.8 million in 2011.

In the Current Quarter, the Company had an operating loss of $4.6 million, loss before income taxes and earnings attributable to noncontrolling interest owners of $3.8 million, net loss attributable to Sterling common stockholders of $7.5 million and net loss per diluted share attributable to Sterling common stockholders of $0.44. Included in the net loss attributable to Sterling common stockholders is additional earnings allocated to noncontrolling interest owners of $6.7 million, or $4.4 million net of tax, resulting from an amendment to the RLW member agreement to change the treatment of goodwill impairments for purposes of determining net income distributable to RLW’s members. This is discussed further in Note 8.

Although revenues for the Current Quarter decreased less than 1% from the Prior Quarter, our overall margins continued to be adversely affected by production issues which affected a number of construction projects. These declines in revenues and gross margins were in part a result of revisions to estimated profitability on certain construction projects, both favorable and unfavorable, which resulted in a net pre-tax charge of $3.9 million in the Current Quarter.

The majority of our revenues and backlog is derived from fixed unit price contracts. Some of our revenues are derived from lump sum contracts. Fixed unit price contracts require us to provide materials and services at a fixed unit price based on approved quantities irrespective of our actual per unit costs. Lump sum contracts require that the total amount of work be performed for a single price irrespective of our actual costs. As discussed in “Item 1A. Risk Factors” in the 2011 Form 10-K, we realize a profit on our contracts only if we accurately estimate our costs and then successfully control actual costs and avoid cost overruns, and our revenues exceed actual costs. If our cost estimates for a contract are inaccurate, or if we do not execute the contract within our cost estimates, then cost overruns may cause the contract not to be as profitable as we expected or result in a loss, negatively affecting our cash flow, earnings and financial position. While there are a number of factors which cause the costs incurred and gross profit realized on our contracts to vary, sometimes substantially, from our original projections, the primary factors which caused the net charge related to the revision in estimated revenues and gross profits in the Current Quarter were:

- conditions or contract requirements that differed from those assumed in the original bid or contract;
- increases in equipment costs;
- lower than expected productivity levels;
- failure by certain suppliers, subcontractors or customers to perform certain of their obligations;
- shortages in the availability of skilled workers in the geographic location of certain projects, especially due to the rapid expansion of our business in certain markets; and
- delays in quickly identifying and taking measures to address issues that arose during construction.

In view of the significant revisions to estimated gross profits on contracts identified in the fourth quarter of 2011, management undertook a thorough review and determined that some of these revisions related to prior periods, but the impact of revising these estimates would not have had a material impact on revenues or gross profit reported in those prior periods had the changes been made in the appropriate period. Management also determined that the procedures performed by operating personnel to make periodic revisions in estimates, and the reviews of those estimates by operations management, were not adequate or timely enough in some instances to ensure that a material impact on the financial statements resulting from such revisions in estimates would be recognized in the proper period. Management determined that this deficiency in our internal controls was such that a material misstatement of our annual or interim financial statements would not have been prevented or detected on a timely basis and, therefore, this deficiency constituted a material weakness as of December 31, 2011. Management has determined that this material weakness continued to exist as of March 31, 2012.

While the risks of cost overruns and changes in estimated contract revenues are an inherent part of the construction business, management believes that there are internal changes that we can make in order to improve the profitability of our projects, reduce the variability in profitability of our projects in the future and strengthen the internal control environment. We are undertaking changes in the following areas:

- changing roles and responsibilities to improve functional support and controls;
- developing management tools designed to improve the estimating process and increase the oversight of that process;
- implementing processes designed to better identify, evaluate and quantify risks for individual projects;
- improving the methodologies for allocating overhead, indirect costs and equipment costs to individual projects; and
- improving the timeliness and content of reporting available to operations management.

Although improvements have been made to the estimation process, there has not yet been an adequate period of time since the changes have been implemented to evaluate the effectiveness of these changes, and we have determined that the material weakness continues to exist as of March 31, 2012.

In addition to the factors discussed above which impact the profitability on individual projects, there are other factors which have adversely affected our ability to secure construction projects at favorable margins. Contracts for our highway and related bridge work are generally funded through federal and state authorizations. The federal government enacted the SAFETEA-LU bill in 2005, which authorized $244 billion for transportation spending through 2009. The SAFETEA-LU bill expired on September 30, 2009, and the federal government has been extending financial assistance to the states on an interim basis, most recently through June 30, 2012. However, the federal government has not enacted a long-term, multi-year highway bill with adequate funding to enable the states to know that funding will be sufficient for the states to award large, two to four-year highway and bridge construction contracts. We are unable to predict when or on what terms the federal government might ultimately enact long-term legislation similar to the SAFETEA-LU bill. The failure to enact a long-term, multi-year highway bill with adequate funding has adversely affected the levels of transportation and water infrastructure capital expenditures in our markets, reducing opportunities to replace backlog at reasonable margins and increasing competition for new projects.

While we expect that implementation of the internal changes discussed above will improve profitability in the future, we do not expect to see a substantial impact on our 2012 results. In addition, the continuing failure of the federal government to enact a long-term multi-year highway bill with adequate funding is expected to adversely affect infrastructure capital expenditures in all our markets in 2012, and we expect continued pressure on our gross margins on new contract awards until this situation is alleviated. Projects in our backlog generally take 12 to 36 months to complete, and we currently estimate that $565 million of our $868 million in backlog at March 31, 2012 will be constructed in the remainder of 2012. Based on our current estimates, the gross margin in our backlog for 2012 is lower than the gross margin of 8.0% realized in 2011, partly as a result of the operational issues in 2011 and the Current Quarter which resulted in the downward revisions of estimated gross profits on a number of construction projects that were in progress at December 31, 2011 and March 31, 2012 and partly as a result of competitive bidding pressures when the contracts were added to backlog.

We expect that revenues will increase more than 25% from 2011 to 2012 as a result of the higher backlog at the end of 2011 as compared to 2010, the impact of a full year of operations for JBC and Myers, both of which were acquired in August 2011, and contract awards of $194 million from January 1, 2012 through March 31, 2012. However, as discussed above, based on estimated gross margins in our current backlog, we expect our overall gross margins for 2012 to be lower than the 8.0% reported for 2011. As a result, we anticipate that our net income and diluted earnings per common share of stock attributable to Sterling common stockholders for the period from April 1, 2012 to December 31, 2012 will be comparable to the $5.9 million and $0.31 per share reported for the same period in 2011 (after excluding the $41.8 million and $2.55 per share impact of the goodwill impairment).

### Our Markets

Demand for transportation and water infrastructure depends on a variety of factors, including overall population growth, economic expansion and the vitality of the market areas in which we operate, as well as unique local topographical, structural and environmental issues. In addition to these factors, demand for the replacement of infrastructure is driven by the general aging of infrastructure and the need for technical improvements to achieve more efficient or safer use of infrastructure and resources. Funding for this infrastructure depends on federal, state and local governmental resources, budgets and authorizations. Each of these factors is discussed more fully in “Item 1. Business−Our Markets” in the 2011 Form 10-K.

According to 2010 U.S. Census Bureau information, Texas, Utah, Nevada, Arizona and California each experienced significant population growth from 2005 to 2010 and over the long-term these states are expected to continue to experience population increases from 25.1 million, 2.8 million, 2.7 million, 6.4 million and 37 million people in 2010, respectively, to populations of over 33 million, 3 million, 4 million, 10 million and 46 million, respectively, by 2030.

The U.S. Department of Transportation (“U.S.DOT”) had actual appropriations of $41.8 billion for federal highway financial assistance to the states for 2011, has authority to spend $41.5 billion in the fiscal year ending September 30, 2012 and has requested authority to spend $42.6 billion in the fiscal year ending September 30, 2013 for highways and bridges. Spending for fiscal year 2013 is subject to appropriations by the federal government.

In January 2009, the 2030 Committee, appointed by the Texas Department of Transportation (“TxDOT”) at the request of the Governor of the State of Texas, submitted its draft report of the transportation needs of Texas, which at that time had over 193,000 lane-miles and 50,000 bridges in its state highway system. The report stated that “With \[the\] population increase expected by 2030, transportation modes, costs and congestion are considered a possible roadblock to Texas’s projected growth and prosperity.” The report further indicated that Texas needs to spend approximately $315.0 billion (in 2008 dollars) for the period 2009 through 2030 to prevent worsening congestion and maintain economic competitiveness on its urban highways and roads, improve congestion/safety and partial connectivity on its rural highways, and to replace bridges.

In 2007, the voters of the State of Texas approved $5.0 billion of bonds for highway construction (“Prop 12 Bonds”) to be repaid out of the State's general funds. The transportation construction expenditures for 2010 and 2011 were partially funded by $2.0 billion of proceeds from the Prop 12 Bonds, and the budget for the biennium 2012-2013 includes the remaining $3.0 billion of proceeds from the Prop 12 Bonds.

TxDOT contract awards (“lettings”) for transportation construction projects are estimated to be $4.2 billion in 2012 and $4.1 billion in 2013, including a statewide and local portion of the Prop 12 Bonds discussed above.

In Texas, substantial funds for transportation infrastructure spending are also being provided by toll road and regional mobility authorities for construction of toll roads, which provides Sterling with additional construction contracting opportunities; however, such spending could be limited by federal, state and local funding limitations.

Spending for highway and bridge construction in Utah was $1.3 billion in 2011, and $700.9 million has been authorized for 2012. The details of the capital spending for 2013 have not been released; however the Utah Governor’s recommendation for total capital spending in 2013 is approximately $911 million compared with $1.4 billion recommended for 2012.

Nevada’s budget for construction of roadways and facilities is $377 million in 2012 and $369 million in 2013 compared with expenditures of between $300 million and $400 million in each of the 2010 and 2011 fiscal years.

Arizona’s expenditures for transportation construction were $326 million in 2011, appropriations are $326 million in 2012 and a budget of $332 million has been requested for 2013.

California’s transportation capital outlays and local assistance were $5.0 billion in 2011, while such expenditures are estimated to be $10.2 billion in 2012 and $6.2 billion in 2013. A substantial portion of the decrease between 2012 and 2013 is due to a reduction in expected Federal Trust highway funds.

Since 2008, the bidding environment in our markets has been much more competitive than in the past because of the following:

- Reduced federal, state and local spending on transportation and water-related infrastructure.
- Traditional competitors on larger transportation and water infrastructure projects appear to have been bidding at less than normal margins, sometimes at bid levels below our break-even pricing, in order to replenish their backlogs.
- While our business includes only minimal residential and commercial infrastructure work, the severe fall-off in new projects in those markets has resulted in some residential and commercial infrastructure contractors bidding on smaller public sector transportation and water infrastructure projects, sometimes at bid levels below our break-even pricing, thus increasing competition and creating downward pressure on bid prices in our markets.
- The entry of new competitors from other states.

These factors have limited our ability to replenish our backlog through successful bids for new projects and have compressed the profitability on many new projects where we submitted successful bids. While we have been more aggressive in bidding for some projects, we have not bid at prices where we anticipated we would incur loss margins in order to obtain new backlog. Nevertheless, in some instances we determined subsequent to the award that a job would most likely have a loss margin. Consistent with our policy, these losses are recorded when they become known.

Recent reductions in miles driven in the U.S. and more fuel efficient vehicles have reduced federal and state gasoline taxes and tolls collected. In addition, the federal government has been extending financial assistance to the states on an interim basis, most recently through June 30, 2012, and continued deferral of new funding legislation or reductions in federal funding may negatively impact the states’ highway and bridge construction contract awards for their fiscal years 2012 and beyond. We are unable to predict when or on what terms the federal government might enact long-term infrastructure funding legislation. The ongoing disagreements in Congress over balancing the federal budget in the short-term and long-term as well as reducing the federal deficit add to the uncertainties surrounding the renewal or enactment of federal highway funding legislation.

Further, the nationwide decline in home sales, the increase in foreclosures and the prolonged recession have resulted in decreases in property taxes and some other local taxes, which are among the sources of funding for municipal road, bridge and water infrastructure construction. Expenditures by municipalities may also be limited due to federal, state and local funding limitations in the current economic environment.

These and other factors have adversely affected the levels of transportation and water infrastructure capital awards and expenditures in our markets, reducing opportunities to replace backlog at reasonable margins and increasing competition for new projects. See “Recent Developments ― Financial Results for 2011, Operational Issues and Outlook for 2012 Financial Results” in the 2011 Form 10-K for further discussion of the impact on our financial results.

While we do expect that our markets will ultimately recover from the conditions described above and that our backlog and revenues will grow and gross margins, net income and earnings per share will return to levels more consistent with historical rates of return, we cannot predict the timing of such a return to historical normalcy in our markets. We believe that the Company is in sound financial condition and has the resources and management experience to weather current market conditions and to continue to compete successfully for projects as they become available at acceptable profit margin levels. See “Business−Markets,” “Business−Our Customers” and “Business−Competition” in the 2011 Form 10-K for a more detailed discussion of our markets and their funding sources.

### Results of Operations

#### Backlog at March 31, 2012

Backlog is our estimate of the revenues that we expect to earn in future periods on our construction projects. We generally add the anticipated revenue value of each new project to our backlog when management reasonably determines that we will be awarded the contract and there are no known impediments to being awarded the contract. As construction on our projects progresses, we also increase or decrease backlog to take into account our estimates of the effects of changes in estimated quantities, changed conditions, change orders and other variations from initially anticipated contract revenues, including completion penalties and incentives. During the Current Quarter, we were awarded or were the apparent low bidder on $194 million in contracts, and at March 31, 2012, our backlog of $868 million included approximately $11 million of expected revenues for which the contracts had not yet been officially awarded. Historically, very few contracts that we have added to backlog have not subsequently been awarded and these have not materially affected our results of operations or financial condition.

Substantially all of the contracts in our contract backlog may be canceled at the election of the customer; however, we have not been materially adversely affected by contract cancellations or modifications in the past.

#### Results of Operations for the Current Quarter as Compared to the Prior Quarter

|  | Three Months Ended March 31, |  |
| --- | ---: | ---: |
|  | **2012** | **2011%** |
|  | (Dollar amounts in thousands) |  |
| Revenues | $98,425 | 99,242 (0.8) |
| Gross profit | $1,873 | $7,599 (75.4) |
| General and administrative expenses | (7,666) | (6,056) 26.6 |
| Other income | 1,231 | 145 NM |
| Operating income (loss) | (4,562) | 1,688 NM |
| Gains (losses) on the sale of securities and other | 750 | (204) NM |
| Interest income | 416 | 378 10.1 |
| Interest expense | (385) | (214) 79.9 |
| Income (loss) before taxes | (3,781) | 1,648 NM |
| Income tax benefit (expense) | 3,976 | (166) NM |
| Net income | 195 | 1,482 NM |
| Net income attributable to noncontrolling interest in earnings of subsidiaries | (7,695) | (1,438) NM |
| Net income (loss) attributable to Sterling common stockholders | $(7,500) | $44 NM |
| Gross margin | 1.9% | 7.7% (75.3) |
| Operating margin | (4.6)% | 1.7% NM |

|  | Amount as of March 31, 2012 | December 31, 2011 |
| --- | ---: | ---: |
| Contract backlog, end of period | $868,000 | $741,000 |
| NM – Not meaningful. |  |  |

#### Revenues

Revenues were slightly lower for the Current Quarter compared with the Prior Quarter. While we had $11.9 million in revenues in Arizona and California attributable to JBC and Myers which were acquired on August 1, 2011, revenues from contracts in Texas, Nevada and Utah declined from the prior year. Most of the decline was in Texas.

#### Gross Profit

Gross profit decreased $5.7 million for the Current Quarter compared with the Prior Quarter and gross margins declined to 1.9% in the Current Quarter from 7.7% in the Prior Quarter due to net downward revisions of estimated revenues and gross profit on a number of construction projects, primarily in Texas. The net revisions to contract estimates were the result of different factors affecting various contracts, some positively and some negatively. While there are a number of factors which cause the costs incurred and gross profit realized on our contracts to vary, sometimes substantially, from our original projections, the primary factors which caused the net charge in the Current Quarter were:

- conditions or contract requirements that differed from those assumed in the original bid or contract;
- increases in equipment costs;
- lower than expected productivity levels;
- failure by certain suppliers, subcontractors or customers to perform certain of their obligations;
- shortages in the availability of skilled workers in the geographic location of certain projects, especially due to the rapid expansion of our business in certain markets; and
- delays in quickly identifying and taking measures to address issues which arose during construction.

At March 31, 2012, we had approximately 96 contracts-in-progress which were less than 90% complete of various sizes, of different expected profitability and in various stages of completion. The nearer a contract progresses toward completion, the more visibility we have in refining our estimate of total revenues (including incentives, delay penalties and change orders), costs and gross profit. Thus gross profit as a percent of revenues can increase or decrease from comparable and sequential quarters due to variations among contracts and depending upon the stage of completion of contracts.

#### General and administrative expenses, net of other income

General and administrative expenses for Current Quarter included general and administrative expenses for JBC and Myers which we acquired on August 1, 2011 as well as an increase in professional fees. As a percent of revenues, general and administrative expenses increased to 7.8% in the Current Quarter compared with 6.1% in the Prior Quarter.

#### Income taxes

Our effective income tax rates for the Current and Prior Quarters were 105.2% and 10.1%, respectively, and varied from the statutory rate primarily as a result of net income attributable to noncontrolling interest owners which is taxed to those owners rather than Sterling, the impact of applying the estimated overall effective rate for 2012 to Current Quarter pretax income in order to allocate the tax provision within the current annual period and the impact of nontaxable interest income. Excluding the impact of net income attributable to noncontrolling interest owners, our effective income tax rates for the Current and Prior Quarters were 34.0% and 40.6%, respectively.

#### Net income attributable to noncontrolling interests

The increase in net income attributable to noncontrolling interest owners in the Current Quarter compared with the Prior Quarter is primarily related to net income attributable to the 20% noncontrolling interest owners in RLW, our 80% owned subsidiary. As discussed further in Note 8 to the condensed consolidated financial statements, the members of RLW, including the Company, agreed to amend their operating agreement effective January 1, 2012 to provide that any goodwill impairment, including the 2011 fourth quarter goodwill impairment, is not to be allocated to RLW for the purpose of calculating the distributions to be made to the RLW noncontrolling interest holders. This amendment resulted in an increase in the net income attributable to RLW’s noncontrolling interests of $6,717,000 during the three months ended March 31, 2012. This increase is included in “Noncontrolling owners’ interests in earnings of subsidiaries and joint ventures” in the accompanying condensed consolidated statement of operations with an increase in the “Obligation for noncontrolling owners’ interests in subsidiaries and joint ventures” in the condensed consolidated balance sheet. This increase has a related tax impact of $2,351,000 which increased the tax benefit for the period.

### Historical Cash Flows

The following table sets forth information about our cash flows and liquidity (in thousands):

| Net cash provided by (used in): | Three Months Ended March 31, 2012 | 2011 |
| --- | ---: | ---: |
| Operating activities | $1,378 | $5,446 |
| Capital expenditures | (5,910) | (8,433) |
| Proceeds from sales of property and equipment | 3,306 | 182 |
| Net sales (purchases) of short-term securities | 1,546 | (30,152) |
| Financing activities | (81) | (4,114) |
| Total | $239 | $(37,071) |

|  | Amount as of March 31, 2012 | December 31, 2011 |
| --- | ---: | ---: |
| Cash and cash equivalents | $16,610 | $16,371 |
| Working capital | $92,134 | $94,738 |

#### Operating Activities

Significant non-cash items included in operating activities are:

- depreciation and amortization which increased to $4.5 million in the Current Quarter as compared to $4.2 million in the Prior Quarter as a result of an increase in capital expenditures as well as depreciation associated with JBC and Myers which were acquired August 1, 2011; and
- deferred tax benefit of $3.0 million in the Current Quarter is primarily attributable to the $2.4 million tax impact of the additional earnings to noncontrolling interest owners of $6.7 million discussed in Note 8; deferred tax expense of $1.3 million in the Prior Quarter is primarily the result of recognizing accelerated depreciation methods used on equipment for tax purposes as compared to straight-line depreciation used for financial reporting purposes and amortizing goodwill for tax return purposes but not for financial reporting purposes.

Besides the net income (loss) in the Current and Prior Quarters and the non-cash items discussed above, other significant components of cash flows from operations (which excludes the impact of changes attributable to the net assets of acquired companies) were:

- contracts receivable decreased by $2.0 million in the Current Quarter and $5.4 million in the Prior Quarter while the excess of billings over costs incurred and estimated earnings increased by $1.1 million in the Current Quarter and $4.6 million in the Prior Quarter;
- the increase in income tax receivable of $1.1 million in the Current Quarter is the result of estimated benefit from carrying back the tax net operating loss forecasted for 2012; the increase in income tax receivable of $2.9 million in the Prior Quarter is the result of estimated tax payments which were refunded in connection with the filing of our 2010 tax return;
- accounts payable increased by $4.8 million in the Current Quarter and decreased by $0.6 million in the Prior Quarter; and
- accrued compensation and other liabilities decreased by $2.3 million in the Current Quarter and increased by $0.4 million in the Prior Quarter.

#### Investing Activities

Capital equipment is acquired as needed to support increased levels of production activities and to replace retiring equipment. Expenditures for the replacement of certain equipment and to expand our construction fleet totaled $5.9 million for the Current Quarter. Proceeds from the sale of property and equipment totaled $3.3 million for the Current Quarter with an associated net gain of $1.2 million. For the year ended December 31, 2011, capital expenditures totaled $24.0 million while proceeds from the sale of property and equipment totaled $1.3 million. Management expects capital expenditures in 2012 to be higher than 2011 to support our higher level of operations and to replace equipment. In addition, proceeds from sales of property and equipment in the Current Quarter have been higher than in previous periods as management undertook a program to dispose of underutilized and aging equipment.

During the Current Quarter, the Company had net sales of short-term securities of $1.5 million as compared to net purchases of short-term securities of $30.2 million in the Prior Quarter. The net purchases in the Prior Quarter were primarily due to the investment of cash generated by operations, after capital expenditures.

#### Financing Activities

Financing activities in the Current Quarter consisted of drawdowns and repayments on the Credit Facility. Financing Activities in the Prior Quarter primarily reflect distributions to noncontrolling interest owners of $3.9 million. Subsequent to March 31, 2012, the members of RLW approved the distribution of net income for the three months ended December 31, 2011 in accordance with the RLW operating agreement as amended. The amount attributable to the noncontrolling interest owners was $765,000.

### Liquidity and Sources of Capital

The level of working capital for our construction business varies due to fluctuations in:

- customer receivables and contract retentions;
- costs and estimated earnings in excess of billings;
- billings in excess of costs and estimated earnings;
- investments in our unconsolidated construction joint ventures;
- the size and status of contract mobilization payments and progress billings; and
- the amounts owed to suppliers and subcontractors.

Some of these fluctuations can be significant. As of March 31, 2012, we had working capital of $92.1 million, a decrease of $2.6 million over December 31, 2011. The decrease in working capital of $2.6 million in the Current Quarter was the result of the following (in thousands):

|  |  |
| --- | ---: |
| Net income | $195 |
| Depreciation and amortization | 4,530 |
| Deferred tax benefit | (2,951) |
| Capital expenditures | (5,910) |
| Proceeds from sales of property and equipment, net of gain | 2,102 |
| Other | (570) |
| Total decrease in working capital | $(2,604) |

In addition to our available cash and cash equivalents, short term investments and cash provided by operations, from time to time we use borrowings under our $50.0 million Credit Facility with Comerica Bank to finance our capital expenditures and working capital needs. The Credit Facility has a maturity date of September 30, 2016. Subject to the conditions under the terms of the Credit Facility, including the financial covenants discussed below, up to $50 million in borrowings and letters of credit is available under the amended Credit Facility with, under certain circumstances, an optional increase of $50 million. Borrowings under the Credit Facility are secured by all assets of the Company, other than proceeds and other rights under our construction contracts which are pledged to our bond surety. At March 31, 2012, there were no borrowings outstanding under the Credit Facility; however, there was a letter of credit of $1.8 million outstanding which reduced availability under the Credit Facility to $48.2 million.

Average borrowings under the Credit Facility for the Current Quarter were $11,000 and the largest amount of borrowings under the Credit Facility was $1.0 million on February 23, 2012. Average borrowings under the Credit Facility for the fiscal year 2011 were $104,000, and the largest amount of borrowings under the Credit Facility was $8.0 million on September 30, 2011.

The Credit Facility is subject to our compliance with certain covenants, including financial covenants at quarter-end relating to leverage, tangible net worth, and asset coverage. The Credit Facility contains restrictions on our ability to:

- Make distributions or pay dividends;
- Incur liens and encumbrances;
- Incur further indebtedness;
- Guarantee obligations;
- Dispose of a material portion of assets or merge with a third party; and
- Make investments in securities.

To date the Company has not experienced any difficulty in borrowing under the Credit Facility, and the Company was in compliance with all covenants under the Credit Facility as of March 31, 2012.

Management believes that the Company has sufficient liquid financial resources, including the unused portion of its Credit Facility, to fund its requirements for the next twelve months of operations, including its bonding requirements, and the Company expects no material adverse change in its liquidity. Future developments or events, such as an increase in our level of purchases of equipment to support significantly higher backlog or an acquisition of another company could, however, affect our level of working capital and tangible net worth. See “Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operation−Sources of Capital” in the 2011 Form 10-K for further discussion of the covenants and restrictions under the Credit Facility.

### Inflation

Until 2008, inflation had not had a material impact on our financial results; however, that year’s increases in oil and fuel prices affected our cost of operations. While the prices we have paid for oil and fuel and, generally, for other materials have decreased since 2008, in 2011 we saw the prices of oil and fuel rise once again, and we have seen increases in steel prices in other years. Anticipated cost increases and reductions are considered in our bids to customers on proposed new construction projects.

In order to mitigate our exposure to increases in fuel prices, in April 2011, we commenced a program to hedge our exposure to increases in diesel fuel prices by entering into swap contracts for diesel fuel. We believe that the gains and losses on these contracts will tend to offset increases and decreases in the price we pay for diesel fuel and reduce the volatility of such fuel costs in our operations. As of March 31, 2012, we had diesel futures contracts for 660,000 gallons which fixed prices at an average of $3.14 per gallon. This compares to the March 31, 2012 price for off-road ultra-low sulfur diesel published by Platts of $3.24. We will continue to evaluate this strategy and may increase or decrease our commitments depending on our forecast of the diesel fuel market and other operational considerations. There can be no assurance that this strategy will be successful.

Where we are the successful bidder on a project, we execute purchase orders with material suppliers and contracts with subcontractors covering the prices of most materials and services, other than oil and fuel products, thereby mitigating future price increases and supply disruptions. These purchase orders and subcontracts do not contain quantity guarantees and we have no obligation to the suppliers or subcontractors for materials and services beyond those required to complete the contracts with our customers. There can be no assurance that increases in prices of oil and fuel used in our business will be adequately covered by the estimated escalation we have included in our bids or derivative contracts entered into to hedge against certain such increases, and there can be no assurance that all of our vendors will fulfill their pricing and supply commitments under their purchase orders and contracts with the Company. We adjust our total estimated costs on our projects when we believe it is probable that we will have cost increases which will not be recovered from customers, vendors or through project re-engineering.

### Off-Balance Sheet Arrangements and Joint Ventures

As discussed further in “Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operation−Off-Balance Sheet Arrangements and Joint Ventures” in the 2011 Form 10-K, we participate in various construction joint venture partnerships in order to share expertise, risk and resources for certain highly complex projects. The venture’s contract with the project owner typically requires joint and several liability among the joint venture partners. Although our agreements with our joint venture partners provide that each party will assume and fund its share of any losses resulting from a project, if one of our partners was unable to pay its share we would be fully liable for such share under our contract with the project owner. Circumstances that could lead to a loss under these guarantee arrangements include a partner’s inability to contribute additional funds to the venture in the event that the project incurred a loss or additional costs that we could incur should the partner fail to provide the services and resources toward project completion that had been committed to in the joint venture agreement.

At March 31, 2012, there was approximately $454.1 million of construction work to be completed on unconsolidated construction joint venture contracts, of which $112.4 million represented our proportionate share. Due to the joint and several liability under our joint venture arrangements, if one of our joint venture partners fails to perform, we and the remaining joint venture partners would be responsible for completion of the outstanding work. As of March 31, 2012, we are not aware of any situation that would require us to fulfill responsibilities of our joint venture partners pursuant to the joint and several liability under our contracts.

Off-balance sheet arrangements related to operating leases are discussed in “Contractual Obligations” in the 2011 Form 10-K.

## Market risk

As filed, 1,436 characters.

Changes in interest rates are one of our sources of market risks. Outstanding indebtedness under our Credit Facility bears interest at floating rates. The average borrowings under this facility during 2011 were $104,000. Based on our expected levels of borrowings for 2012, we do not expect that a change in our interest rate would have a material impact on our results from operations.

We are exposed to market risk from changes in commodity prices. In the normal course of business, we enter into derivative transactions, specifically cash flow hedges, to mitigate our exposure to diesel fuel commodity price movements. We do not participate in these transactions for trading or speculative purposes. While the use of these arrangements may limit the benefit to us of decreases in the prices of diesel fuel, it also limits the risk of adverse price movements. The following represents the outstanding contracts at March 31, 2012:

| Beginning | Ending | Price Per Gallon Range | Weighted Average | Remaining Volume (gallons) | Fair Value of Derivatives at March 31, 2012 (in thousands) |
| --- | --- | --- | ---: | ---: | ---: |
| April 1, 2012 | December 31, 2012 | 3.02 – 3.33 | 3.16 | 390,000 | 22 |
| January 1, 2013 | December 31, 2013 | 2.99 – 3.29 | 3.13 | 270,000 | 4 |
|  |  |  |  |  | $26 |

See “Inflation” above regarding risks associated with materials and fuel purchases required to complete our construction contracts.

## Controls and procedures

As filed, 2,567 characters.

### Evaluation of Disclosure Controls and Procedures

The Company’s principal executive officer and principal financial officer reviewed and evaluated the Company’s disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934) as of December 31, 2011. Based on the identification of a material weakness in our internal control over financial reporting described in “Management’s Report on Internal Control over Financial Reporting” in the 2011 Form 10-K, the Company’s principal executive officer and principal financial officer concluded that the Company’s disclosure controls and procedures were not effective at December 31, 2011 due to this material weakness. While some improvements have been made to the estimating process, there has not been an adequate period of time to evaluate the effectiveness of these changes, and the Company’s principal executive officer and principal financial officer are continuing to evaluate what, if any, additional changes should be made to the internal controls in order to address the material weakness. Furthermore, the Company’s principal executive officer and principal financial officer have determined that the previously reported material weakness continues to exist as of March 31, 2012 and that no other material weakness existed as of March 31, 2012.

### Changes in Internal Control over Financial Reporting

We maintain a system of internal control over financial reporting that is designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with accounting principles generally accepted in the United States. Based on the most recent evaluation, except for certain changes made related to the estimation of revenues and gross profits on construction projects, we have concluded that no significant changes in our internal control over financial reporting occurred during the three months ended March 31, 2012 that have materially affected or are reasonably likely to materially affect, our internal control over financial reporting.

### Inherent Limitations on Effectiveness of Controls

Internal control over financial reporting may not prevent or detect all errors and all fraud. Also, projections of any evaluation of effectiveness of internal control to future periods are subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate.

Filed May 9, 2012.
Source: SEC EDGAR, the filing index for accession 0001140361-12-024059. Last ingested by Listed: Nov 5, 2026, 14:02 ET. No prices; not investment advice.