## Management's discussion and analysis

As filed, 67,427 characters.

### General

MGE Energy is an investor-owned public utility holding company operating through subsidiaries in five business segments:

Electric utility operations, conducted through MGE,

Gas utility operations, conducted through MGE,

Nonregulated energy operations, conducted through MGE Power and its subsidiaries,

Transmission investments, representing our equity investment in ATC, and

All other, which includes corporate operations and services as well as certain construction services.

Our principal subsidiary is MGE, which generates and distributes electric energy, distributes natural gas, and represents a majority portion of our assets, liabilities, revenues, and expenses. MGE generates and distributes electricity to approximately 137,000 customers in Dane County, Wisconsin, including the city of Madison, and purchases and distributes natural gas to approximately 141,000 customers in the Wisconsin counties of Columbia, Crawford, Dane, Iowa, Juneau, Monroe, and Vernon.

Our nonregulated energy operations lease and own new electric generating capacity to assist MGE. The nonregulated energy operations include partial ownership of a cogeneration project on the UW-Madison campus and an undivided 8.33% ownership interest in each of two 615 MW generating units being constructed in Oak Creek, Wisconsin. These ownership interests are leased to MGE pursuant to long-term leases. MGE operates the cogeneration project, and a third party will operate the Elm Road units. The ownership/leasing structure was adopted to capture some advantages under then applicable state regulatory guidelines for MGE's participation in these generation facilities. Due to the nature of MGE's participation in these facilities, the results of our nonregulated operations are also consolidated into MGE's consolidated financial position and results of operations under applicable accounting standards.

Our primary focus today and for the foreseeable future is our core utility customers at MGE as well as creating long-term value for shareholders. MGE continues to face the challenge of providing its customers with reliable power at competitive prices. MGE plans to meet this challenge by investing in more efficient generation projects, including renewable energy sources. In the future, MGE will continue to focus on growing earnings while controlling operating and fuel costs. MGE will continue to maintain safe and efficient operations in addition to providing customer value. We believe it is critical to maintain a strong credit standing consistent with financial strength in MGE as well as the parent company in order to accomplish these goals.

### Overview

We earn our revenue and generate cash from operations by providing electric and natural gas utility services, including electric power generation and electric power and gas distribution. The earnings and cash flows from the utility business are sensitive to various external factors, including, but not limited to:

Weather, and its impact on customer sales of electricity and gas,

Economic conditions, including current business and financing conditions,

Regulation and regulatory issues,

Energy commodity prices,

Equity price risk pertaining to pension related assets,

Interest rates and our debt credit rating,

Environmental laws and regulations, including pending environmental rule changes,

Construction risk in connection with the Elm Road generating units,

and other factors listed in "Item 1A. Risk Factors" of our 2008 Annual Report on Form 10-K.

For the three months ended June 30, 2009, MGE Energy's earnings were $9.9 million or $0.43 per share compared to $10.6 million or $0.48 per share for the same period in the prior year. MGE's earnings for the three months ended June 30, 2009, were $6.1 million compared to $7.2 million for the same period in the prior year.

For the six months ended June 30, 2009, MGE Energy's earnings were $24.8 million or $1.08 per share compared to $24.4 million or $1.11 per share for the same period in the prior year. MGE's earnings for the six months ended June 30, 2009, were $17.4 million compared to $17.6 million for the same period in the prior year.

MGE Energy's income was derived from our business segments as follows:

*(In thousands)*

| Business Segment: | Three Months Ended June 30, 2009 | 2008 | Six Months Ended June 30, 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Electric Utility | $6,258 | $7,248 | $8,044 | $9,298 |
| Gas Utility | (631) | (499) | 8,364 | 7,282 |
| Nonregulated Energy | 2,790 | 2,483 | 5,504 | 5,143 |
| Transmission Investment | 1,209 | 1,019 | 2,395 | 1,980 |
| All Other | 267 | 306 | 538 | 691 |
| Net Income | $9,893 | $10,557 | $24,845 | $24,394 |

Our net income during the three months ended June 30, 2009, primarily reflects the effects of the following factors:

A 3.4% decrease in electric revenue reflecting lower demand and lower sales for resale due to decreased sales opportunities.

Higher nonregulated energy revenues primarily attributable to higher carrying costs being recognized for the Elm Road project. Carrying costs during construction of the nonregulated energy projects, related to the equity portion, are recognized over the period of time the costs are recovered in rates.

A $0.2 million increase in net income from our interest in ATC.

Our net income during the six months ended June 30, 2009, primarily reflects the effects of the following factors:

A 3.1% decrease in electric revenue reflecting lower demand and lower sales for resale due to decreased sales opportunities.

As a result of the GCIM, the gas utility received an additional benefit of $0.8 million from capacity release revenues and commodity savings for the six months ended June 30, 2009 when compared to the same period in the prior year.

In 2008, the gas utility had expensed a $1.5 million settlement (includes premium) associated with a weather hedge (heating degree collar) as a result of colder-than-normal weather. The gas utility had no weather hedges during 2009.

Higher nonregulated energy revenues primarily attributable to higher carrying costs being recognized for the Elm Road project. Carrying costs during construction of the nonregulated energy projects, related to the equity portion, are recognized over the period of time the costs are recovered in rates.

A $0.4 million increase in net income from our interest in ATC.

During 2009, the following events occurred:

ATC: MGE Transco contributed $1.6 million for voluntary capital contributions to ATC for the six months ended June 30, 2009. An additional voluntary capital contribution of $0.9 million was made in July 2009.

WCCF: The State of Wisconsin did not exercise its option under the WCCF Joint Ownership Agreement to acquire either a 45 MW interest in WCCF or enter into a purchase power agreement for 45 MW of capacity. This option expired in the second quarter of 2009.

Wind Development Rights: In June 2009, MGE Energy, through its subsidiary MAGAEL, LLC, entered into agreements to purchase land development rights, including but not limited to land option agreements, electrical interconnection rights, wind data, engineering plans, licenses, permits, and governmental approvals for two wind development sites. These wind development rights may potentially be used to develop wind farms in three counties in Iowa with a capacity up to approximately 175 MWs. These agreements do not obligate MGE Energy to construct at these locations in Iowa.

2009 Fuel Credit: In April 2009, MGE filed an application with the PSCW requesting a proposed credit of $0.00204 per kWh, due to a decrease in actual electric fuel costs, when compared to those fuel costs projected in MGE's most recent rate order. MGE estimates this credit would reduce electric revenues by $4.6 million for 2009. In May 2009, the PSCW approved the interim order authorizing MGE to implement the proposed credit, subject to refund with interest at 10.8% effective May 9, 2009 until the final PSCW order. In the three and six months ended June 30, 2009, this interim credit resulted in a $1.0 million and a $2.1 million reduction to electric revenues, respectively.

2008 Fuel Refund: As a result of lower than expected fuel and purchased power costs in 2008, a fuel refund was approved by the PSCW. The PSCW completed their audit and issued a final order in March 2009, which applied a $5.7 million refund to customers' accounts.

2010 Rate Filing: In April 2009, MGE filed an application with the PSCW requesting a 4.5% increase to electric rates and a 2.3% increase to gas rates for 2010. The proposed increases cover costs for MGE's share of the new Elm Road generating station, transmission reliability enhancements, as well as infrastructure additions to its gas delivery system.

In the near term, several items may affect us, including:

General economic conditions: Economic conditions both inside and outside our service area are expected to continue to affect the level of demand for our utility services and may affect the collection of our accounts receivable and the creditworthiness of counterparties with whom we do business. We have in place lines of credit aggregating $195 million for MGE Energy (including MGE) and $75 million for MGE to address our liquidity needs.

Elm Road Construction Claim: As described in Footnote 6, the project contractor for the Elm Road units has made claims against the units' owners for additional costs and for relief from the construction schedule. It is expected that these claims will be addressed through formal arbitration under the construction contract between the contractor and the project operator, ERS.

Environmental Initiatives: Various environmental rules or initiatives are in a state of flux as a result of court decisions and the change in the Presidential Administration. In addition, the U.S. House of Representatives has passed legislation intended to control greenhouse gas emissions. Such proposed legislation, rules and initiatives involve matters related to air emissions, water effluent and greenhouse gases, all of which affect generation plant capital expenditures and operating costs as well as future operational planning.

The following discussion is based on the business segments as discussed in Footnote 16.

### Three Months Ended June 30, 2009 and 2008

### Electric Utility Operations - MGE Energy and MGE

### Electric sales and revenues

The following table compares MGE's electric revenues and electric kWh sales by customer class for each of the periods indicated:

*(In thousands, except cooling degree days)*

| 2009 | Revenues Three Months Ended June 30, 2008 | % Change | 2009 | Sales Three Months Ended June 30, 2008 | % Change |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $24,947 | $25,432 | (1.9)% | 170,225 | 172,281 | (1.2)% |
| Commercial | 44,032 | 44,720 | (1.5)% | 429,881 | 439,140 | (2.1)% |
| Industrial | 5,996 | 6,278 | (4.5)% | 80,280 | 82,191 | (2.3)% |
| Other - retail/municipal | 8,112 | 8,289 | (2.1)% | 102,244 | 107,087 | (4.5)% |
| Total retail | 83,087 | 84,719 | (1.9)% | 782,630 | 800,699 | (2.3)% |
| Sales for resale | 504 | 1,532 | (67.1)% | 339 | 14,298 | (97.6)% |
| Other revenues | (2,393) | (2,220) | (7.8)% | - | - | - |
| Total | $81,198 | $84,031 | (3.4)% | 782,969 | 814,997 | (3.9)% |
| Cooling degree days (normal 173) |  |  |  | 146 | 113 | 29.2% |

Electric operating revenues decreased $2.8 million or 3.4% for the three months ended June 30, 2009, due to the following:

*(In millions)*

| Three months ended June 30, 2009 |  |
| --- | ---: |
| Volume | $(1.9) |
| Sales for resale | (1.0) |
| Rate changes | 0.3 |
| Other revenues | (0.2) |
| Total | $(2.8) |

*Volume*. During the three months ended June 30, 2009, there was a 2.3% decrease in total retail sales volumes compared to the same period in the prior year, reflecting reduced demand for service due to economic activity.

*Sales for resale*. Sales for resale represent wholesale sales made to third parties who are not ultimate users of the electricity. These sales may include spot market transactions on the markets operated by MISO or PJM. These sales may also include bilateral sales to other utilities or power marketers. Generating units are dispatched by MISO based on cost considerations as well as reliability of the system. Sales for resale typically occur when MGE has more generation and purchases online than is needed for its own system demand. The excess electricity is then sold to others in the market. For the three months ended June 30, 2009, sales for resale decreased $1.0 million when compared to the same period in the prior year, reflecting decreased opportunities for sales.

*Rates changes*. Rates charged to retail customers for the three months ended June 30, 2009, were 0.3% or $0.3 million higher than those charged during the same period in the prior year.

On December 18, 2008, under a limited reopener, the PSCW authorized MGE to decrease 2009 rates for retail electric customers by 0.74% or $2.7 million from 2008. The decrease in retail electric rates is driven by a decrease in fuel and purchased power costs, decrease in Elm Road costs and a decrease in ATC transmission costs. The PCSW also approved deferred accounting for incremental pension and other postretirement benefit costs above the levels currently included in rates.

In May 2009, the PSCW approved an interim order authorizing MGE to implement a credit of $0.00204 per kWh, due to a decrease in actual electric fuel costs, when compared to those fuel costs projected in MGE's most recent rate order. During the three months ended June 30, 2009, $0.9 million had been credited to electric customers.

In May 2008, the PSCW approved a $0.00239 per kWh interim fuel surcharge on MGE's electric rates to cover increased fuel and purchased power expenses. For the three months ended June 30, 2008, this interim surcharge resulted in a $1.2 million increase to electric rates.

*Other revenues.* Other electric revenues decreased $0.2 million for the three months ended June 30, 2009, compared to the same period in the prior year.

Other electric revenues reflect the elimination of WCCF and Elm Road carrying costs that were collected in electric rates, which are recognized as nonregulated energy operating revenues in our Nonregulated Energy Operations segment. The amount eliminated was $2.7 million for both the three months ended June 30, 2009 and 2008.

### Electric fuel and purchased power

As a result of more favorable prices for purchased power as compared to internal generation, power purchases were increased, and internal generation reduced, causing fuel for electric generation to decrease and purchased power expense to increase.

The expense for fuel for electric generation decreased $5.3 million or 41.7% during the three months ended June 30, 2009, compared to the same period in the prior year, reflecting the lower electric generation.

Purchased power expense increased by $6.1 million or 41.8% during the three months ended June 30, 2009, compared to the same period in the prior year. This increase in expense reflects an $8.3 million or 66.3% increase in the volume of power purchased offset by a $2.2 million or 14.7% decrease in the per-unit cost of purchased power.

### Electric operating and maintenance expenses

Electric operating and maintenance expenses decreased $2.3 million during the three months ended June 30, 2009, compared to the same period in 2008. The following changes contributed to the net change:

*(In millions)*

| Three months ended June 30, 2009 |  |
| --- | ---: |
| Decreased maintenance expenses | $(1.9) |
| Decreased production costs | (0.5) |
| Increased transmission costs | 0.4 |
| Decreased other expenses | (0.3) |
| Total | $(2.3) |

For the three months ended June 30, 2009, electric maintenance expenses decreased compared to the same period in the prior year. Decreased production costs were due to lower internal generation. In addition, transmission costs increased primarily due to network service fees pertaining to ATC.

### Gas Utility Operations - MGE Energy and MGE

### Gas deliveries and revenues

The following table compares MGE's gas revenues and gas therms delivered by customer class during each of the periods indicated:

*(In thousands, except HDD and average rate per therm of retail customer)*

| 2009 | Revenues Three Months Ended June 30, 2008 | % Change | 2009 | Therms Delivered Three Months Ended June 30, 2008 | % Change |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $13,482 | $19,817 | (32.0)% | 13,144 | 12,314 | 6.7% |
| Commercial/industrial | 9,781 | 17,233 | (43.2)% | 16,453 | 14,606 | 12.6% |
| Total retail | 23,263 | 37,050 | (37.2)% | 29,597 | 26,920 | 9.9% |
| Gas transportation | 609 | 610 | (0.2)% | 7,684 | 7,715 | (0.4)% |
| Other revenues | 161 | 1,260 | (87.2)% | - | - | - |
| Total | $24,033 | $38,920 | (38.3)% | 37,281 | 34,635 | 7.6% |
| Heating degree days (normal 858) |  |  |  | 842 | 847 | (0.6)% |
| Average rate per therm of retail customer |  |  |  | $0.786 | $1.376 | (42.9)% |

Gas revenues decreased $14.9 million or 38.3% for the three months ended June 30, 2009. These changes are related to the following factors:

*(In millions)*

| Three months ended June 30, 2009 |  |
| --- | ---: |
| Gas costs/rates | $(15.9) |
| Gas deliveries | 2.1 |
| Transportation and other effects | (1.1) |
| Total | $(14.9) |

*Gas costs/rates*. The average retail rate per therm for the three months ended June 30, 2009, decreased 42.9% compared to the same period in 2008 as a result of lower natural gas costs.

*Retail gas deliveries*. For the three months ended June 30, 2009, retail gas deliveries increased 9.9% compared to the prior period.

*Transportation and other revenues*. Transportation and other revenues decreased a total of $1.1 million primarily due to the impact of the MGE GCIM in 2008.

Under MGE's GCIM, if actual gas commodity savings and capacity release revenues are above or below a benchmark set by the PSCW, then MGE's gas sales service customers and shareholders share in any increased costs or savings per percentages set by the PSCW. For the three months ended June 30, 2009, shareholders did not receive a benefit from capacity release revenues and commodity savings under the GCIM compared to a $1.1 million benefit received for the three months ended June 30, 2008.

### Cost of gas sold

For the three months ended June 30, 2009, cost of gas sold decreased by $14.2 million, compared to the same period in the prior year. The cost per therm of natural gas decreased 54.4% which resulted in $14.6 million of reduced expense. This decrease is offset by a 1.6% increase in the volume of gas purchased which resulted in $0.4 million additional expense.

### Gas operating and maintenance expenses

Gas operating and maintenance expenses decreased $0.5 million for the three months ended June 30, 2009, compared to the same period a year ago. The decrease is primarily due to less administrative and general expenses.

### Nonregulated Energy Operations - MGE Energy and MGE

### Nonregulated energy operating revenues

Operating revenues from nonregulated energy operations increased $0.5 million for the three months ended June 30, 2009, when compared to the same period in the prior year. Operating revenues from nonregulated energy operations for both the three months ended June 30, 2009 and 2008, include $3.7 million in interdepartmental revenues related to a leasing arrangement between MGE and MGE Power West Campus. Upon consolidation, these interdepartmental revenues are eliminated.

MGE also received approval from the PSCW to collect carrying costs expected to be incurred by MGE Power Elm Road during construction of the Elm Road project. MGE estimates that the total carrying costs on the Elm Road project will be $59.0 million. A portion of this amount is being recognized over the period recovered in rates and a portion is being deferred and will be recognized over the period in which the facility is depreciated. For the three months ended June 30, 2009 and 2008, MGE Power Elm Road recognized $2.0 million and $1.5 million, respectively, related to carrying costs on the Elm Road project.

### Nonregulated energy interest expense, net

For the three months ended June 30, 2009 and 2008, interest expense, net at the nonregulated energy operations segment was $0.7 million and $0.6 million, respectively. Interest expense at the nonregulated energy segment for both the three months ended June 30, 2009 and 2008, includes $0.7 million in interest expense incurred on $50 million of long-term, fixed-rate borrowings at MGE Power West Campus.

Also included in the nonregulated interest expense is interdepartmental interest expense and capitalized interest at MGE Power Elm Road. During the three months ended June 30, 2009 and 2008, MGE Power Elm Road was charged $0.8 million and $1.2 million, respectively, in interest expense by Corporate on funds borrowed for the Elm Road Project. This expense is eliminated upon consolidation for MGE Energy only. The interest expense at MGE Power Elm Road is offset by $0.8 million and $1.2 million, respectively, in capitalized interest.

During the three months ended June 30, 2009 and 2008, MGE Power Elm Road recorded less than $0.1 million and $0.1 million, respectively, in interest income on cash advanced to Elm Road Services, LLC for construction of transmission equipment and work done by ATC related to the Elm Road project.

### Transmission Investment Operations - MGE Energy and MGE

### Transmission investment other income

For the three months ended June 30, 2009 and 2008, other income at the transmission investment segment was $2.0 million and $1.7 million, respectively. The transmission investment segment holds our interest in ATC, and its income reflects our equity in the earnings of ATC.

### All Other Nonregulated Operations - MGE Energy

All other interest income, net for both the three months ended June 30, 2009 and 2008, was $0.7 million. Interest income for the three months ended June 30, 2009, represents $0.8 million in interdepartmental interest income from MGE Power Elm Road, partially offset by $0.1 million in interest expense on short-term debt. Interest income for the three months ended June 30, 2008, represents $1.2 million in interdepartmental interest income from MGE Power Elm Road, partially offset by $0.5 million in interest expense on short-term debt. The interdepartmental interest income is eliminated upon consolidation.

### Consolidated Other General Taxes

MGE Energy's and MGE's other general taxes increased $0.2 million or 5.9% for the three months ended June 30, 2009, when compared to the same period in 2008, due to increased license fee tax. The annual license fee tax expense is based on the prior year's adjusted operating revenues. Tax rates have not increased.

### Consolidated Income Taxes

MGE Energy's effective income tax rate for the three months ended June 30, 2009, is 35.5% compared to 36.0% for the same period in 2008. MGE's effective income tax rate for the three months ended June 30, 2009, is 35.4% compared to 35.8% for the same period in the prior year. The lower tax rates for the three months ended June 30, 2009, are due primarily to an increase in federal tax credits from the production of electricity from wind energy. The tax credit for 2009 is expected to exceed the credit for 2008 mainly due to a full year of generation from the Top of Iowa III wind farm in 2009. In 2008, wind generation occurred for approximately ten months.

Under 2009 Wisconsin Act 2, effective for years beginning on or after January 1, 2009, Wisconsin requires corporations to use combined reporting to compute their Wisconsin income for income tax purposes. Formerly, Wisconsin law required each corporation in a combined group to file separate returns. The effect of the combined reporting statute in Wisconsin is not expected to make any significant changes to the effective income tax rate or the tax accrual.

### Noncontrolling Interest, Net of Tax

The noncontrolling interest, net of tax reflects the accounting required for MGE Energy's interest in the WCCF and Elm Road generating projects. MGE Energy owns 100% of MGE Power West Campus and MGE Power Elm Road; however, due to the leasing arrangements for these projects with MGE, the entities are considered VIEs under FIN 46(R) and their results are consolidated with those of MGE, the primary beneficiary of the VIEs. Also included in noncontrolling interest, net of tax is MGE Energy's interest in MGE Transco.

For the three months ended June 30, 2009, MGE Energy (through its wholly owned subsidiary MGE Power) earned $1.9 million and $1.2 million, net of tax, for its interest in MGE Power West Campus and MGE Power Elm Road, respectively. Additionally, MGE Energy earned $0.4 million, net of tax for its interest in MGE Transco. These amounts are recorded as noncontrolling interest expense, net of tax, on MGE's consolidated statement of income.

For the three months ended June 30, 2008, MGE Energy (through its wholly owned subsidiary MGE Power) had earned $1.9 million and $0.9 million, net of tax, for its interest in MGE Power West Campus and MGE Power Elm Road, respectively. Additionally, MGE Energy had earned $0.2 million, net of tax, for its interest in MGE Transco. These amounts are recorded as noncontrolling interest expense, net of tax, on MGE's consolidated statement of income.

### Six Months Ended June 30, 2009 and 2008

### Electric Utility Operations - MGE Energy and MGE

### Electric sales and revenues

The following table compares MGE's electric revenues and electric kWh sales by customer class for each of the periods indicated:

*(In thousands, except cooling degree days)*

| 2009 | Revenues Six Months Ended June 30, 2008 | % Change | 2009 | Sales Six Months Ended June 30, 2008 | % Change |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $52,882 | $55,104 | (4.0)% | 379,295 | 387,001 | (2.0)% |
| Commercial | 83,951 | 87,828 | (4.4)% | 866,649 | 889,019 | (2.5)% |
| Industrial | 9,433 | 10,303 | (8.4)% | 137,932 | 141,365 | (2.4)% |
| Other - retail/municipal | 14,367 | 15,008 | (4.3)% | 189,084 | 195,385 | (3.2)% |
| Total retail | 160,633 | 168,243 | (4.5)% | 1,572,960 | 1,612,770 | (2.5)% |
| Sales for resale | 964 | 2,792 | (65.5)% | 3,384 | 25,242 | (86.6)% |
| Other revenues | (272) | (4,565) | 94.0% | - | - | - |
| Total | $161,325 | $166,470 | (3.1)% | 1,576,344 | 1,638,012 | (3.8)% |
| Cooling degree days (normal 173) |  |  |  | 146 | 113 | 29.2% |

Electric operating revenues decreased $5.1 million or 3.1% for the six months ended June 30, 2009, due to the following:

*(In millions)*

| Six months ended June 30, 2009 |  |
| --- | ---: |
| Volume | $(4.1) |
| Rate changes | (3.5) |
| Sales for resale | (1.8) |
| Other revenues | 4.3 |
| Total | $(5.1) |

*Volume*. During the six months ended June 30, 2009, there was a 2.5% decrease in total retail sales volumes when compared to the same period in the prior year, reflecting reduced demand for service due to economic activity.

*Rates changes*. Rates charged to retail customers for the six months ended June 30, 2009, were 2.1% or $3.5 million lower than those charged during the same period in the prior year.

On December 18, 2008, under a limited reopener, the PSCW authorized MGE to decrease 2009 rates for retail electric customers by 0.74% or $2.7 million from 2008. The decrease in retail electric rates is driven by a decrease in fuel and purchased power costs, decrease in Elm Road costs and a decrease in ATC transmission costs. The PCSW also approved deferred accounting for incremental pension and other postretirement benefit costs above the levels currently included in rates.

As a result of lower than expected fuel and purchased power costs in 2008, a fuel refund was approved by the PSCW. In March 2009, the PSCW completed their audit of 2008 electric fuel costs and issued a final order approving the amount to be refunded to customers. A refund of $5.7 million (includes interest) was applied to customers' accounts in March 2009. See "Other revenues" discussion below for more information on this refund.

In May 2009, the PSCW approved an interim order authorizing MGE to implement a credit of $0.00204 per kWh, due to a decrease in actual electric fuel costs, when compared to those fuel costs projected in MGE's most recent rate order. During the six months ended June 30, 2009, $0.9 million had been credited to electric customers. See "Other revenues" discussion below for more information on this interim order.

*Sales for resale*. Sales for resale represent wholesale sales made to third parties who are not ultimate users of the electricity. These sales may include spot market transactions on the markets operated by MISO or PJM. These sales may also include bilateral sales to other utilities or power marketers. Generating units are dispatched by MISO based on cost considerations as well as reliability of the system. Sales for resale typically occur when MGE has more generation and purchases online than is needed for its own system demand. The excess electricity is then sold to others in the market. For the six months ended June 30, 2009, sales for resale decreased $1.8 million when compared to the same period in the prior year, reflecting decreased opportunities for sales.

*Other revenues.* Other electric revenues increased $4.3 million for the six months ended June 30, 2009, compared to the same period in the prior year.

During the six months ended June 30, 2009, MGE recorded $5.5 million in other electric revenues to offset the impact of the 2008 fuel refund credited to customers in March 2009. This refund reduced revenues during the twelve months ended December 31, 2008, and was returned to customers via a reduction in rates in March 2009.

Also included in other revenues for the six months ended June 30, 2009, is a $1.2 million projected refund which was accrued related to the May 2009 interim order.

Other electric revenues reflect the elimination of WCCF and Elm Road carrying costs that were collected in electric rates, which are recognized as nonregulated energy operating revenues in our Nonregulated Energy Operations segment. The amount eliminated was $5.4 million for both the six months ended June 30, 2009 and 2008.

### Electric fuel and purchased power

As a result of more favorable prices for purchased power as compared to internal generation, power purchases were increased, and internal generation reduced, causing fuel for electric generation to decrease and purchased power expense to increase.

The expense for fuel for electric generation decreased $11.6 million or 40.2% during the six months ended June 30, 2009, compared to the same period in the prior year. This decrease in expense reflects a $9.0 million decrease related to the lower electric generation and a $2.6 million decrease related to fuel cost.

Purchased power expense increased by $9.5 million or 26.1% during the six months ended June 30, 2009, compared to the same period in the prior year. This increase in expense reflects a $13.8 million or 43.1% increase in the volume of power purchased offset by a $4.3 million or 11.9% decrease in the per-unit cost of purchased power.

### Electric operating and maintenance expenses

Electric operating and maintenance expenses decreased $1.9 million during the six months ended June 30, 2009, compared to the same period in 2008. The following changes contributed to the net change:

*(In millions)*

| Six months ended June 30, 2009 |  |
| --- | ---: |
| Decreased maintenance expenses | $(1.5) |
| Decreased production costs | (1.1) |
| Increased transmission costs | 0.7 |
| Total | $(1.9) |

For the six months ended June 30, 2009, electric maintenance expenses decreased compared to the same period in the prior year. In addition production costs decreased due to lower internal generation. In addition, transmission costs increased primarily due to network service fees pertaining to ATC.

### Electric depreciation expense

Depreciation expense at the electric segment increased by $0.8 million for the six months ended June 30, 2009, when compared to the same period in the prior year.

### Gas Utility Operations - MGE Energy and MGE

### Gas deliveries and revenues

The following table compares MGE's gas revenues and gas therms delivered by customer class during each of the periods indicated:

*(In thousands, except HDD and average rate per therm of retail customer)*

| 2009 | Revenues Six Months Ended June 30, 2008 | % Change | 2009 | Therms Delivered Six Months Ended June 30, 2008 | % Change |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| Residential | $68,182 | $78,945 | (13.6)% | 59,684 | 60,912 | (2.0)% |
| Commercial/industrial | 50,856 | 62,410 | (18.5)% | 62,227 | 60,769 | 2.4% |
| Total retail | 119,038 | 141,355 | (15.8)% | 121,911 | 121,681 | 0.2% |
| Gas transportation | 1,578 | 1,569 | 0.6% | 20,676 | 20,243 | 2.1% |
| Other revenues | 2,237 | 1,480 | 51.1% | - | - | - |
| Total | $122,853 | $144,404 | (14.9)% | 142,587 | 141,924 | 0.5% |
| Heating degree days (normal 4,338) |  |  |  | 4,595 | 4,796 | (4.2)% |
| Average rate per therm of retail customer |  |  |  | $0.976 | $1.162 | (16.0)% |

Gas revenues decreased $21.6 million or 14.9% for the six months ended June 30, 2009. These changes are related to the following factors:

*(In millions)*

| Six months ended June 30, 2009 |  |
| --- | ---: |
| Gas costs/rates | $(22.6) |
| Transportation and other effects | 0.8 |
| Gas deliveries | 0.2 |
| Total | $(21.6) |

*Gas costs/rates*. The average retail rate per therm for the six months ended June 30, 2009, decreased 16.0% compared to the same period in 2008. The primary contributor to this decrease is lower natural gas costs.

*Transportation and other revenues*. Transportation and other revenues increased a total of $0.8 million primarily due to an increase in income realized under the GCIM.

Under MGE's GCIM, if actual gas commodity savings and capacity release revenues are above or below a benchmark set by the PSCW, then MGE's gas sales service customers and shareholders share in any increased costs or savings per percentages set by the PSCW. For the six months ended June 30, 2009 and 2008, shareholders received the benefit of $1.9 million and $1.1 million, respectively, from capacity release revenues and commodity savings under the GCIM.

*Retail gas deliveries*. There was a 0.2% increase in retail gas deliveries for the six months ended June 30, 2009.

### Cost of gas sold

For the six months ended June 30, 2009, cost of gas sold decreased by $21.8 million, compared to the same period in the prior year. The cost per therm of natural gas decreased 19.3% which resulted in $19.8 million of reduced expense. In addition, a 2.0% decrease in the volume of gas purchased resulted in $2.0 million less expense.

### Gas operating and maintenance expenses

Gas operating and maintenance expenses decreased $0.3 million for the six months ended June 30, 2009, compared to the same period a year ago. The decrease is primarily due to less administrative and general expenses.

### Other Income (Deductions), Net

Other income (deductions), net for the gas and electric segments increased $1.1 million for the six months ended June 30, 2009 compared to the same period in the prior year. In 2008, the gas utility had expensed a $1.5 million settlement (includes premium) associated with a weather hedge (heating degree collar) as a result of colder-than-normal weather. The gas utility had no weather hedges during 2009. Offsetting this change is a $0.4 million reduction in AFUDC-equity for the six months ended June 30, 2009 compared to the prior year.

### Nonregulated Energy Operations - MGE Energy and MGE

### Nonregulated energy operating revenues

Operating revenues from nonregulated energy operations increased $0.7 million for the six months ended June 30, 2009, when compared to the same period in the prior year. Operating revenues from nonregulated energy operations for both the six months ended June 30, 2009 and 2008, include $7.4 million in interdepartmental revenues related to a leasing arrangement between MGE and MGE Power West Campus. Upon consolidation, these interdepartmental revenues are eliminated.

MGE also received approval from the PSCW to collect carrying costs expected to be incurred by MGE Power Elm Road during construction of the Elm Road project. MGE estimates that the total carrying costs on the Elm Road project will be $59.0 million. A portion of this amount is being recognized over the period recovered in rates and a portion is being deferred and will be recognized over the period in which the facility is depreciated. For the six months ended June 30, 2009 and 2008, MGE Power Elm Road recognized $4.0 million and $3.3 million, respectively, related to carrying costs on the Elm Road project.

### Nonregulated energy interest expense, net

For both the six months ended June 30, 2009 and 2008, interest expense, net at the nonregulated energy operations segment was $1.3 million. Interest expense at the nonregulated energy segment for both the six months ended June 30, 2009 and 2008, includes $1.4 million in interest expense incurred on $50 million of long-term, fixed-rate borrowings at MGE Power West Campus.

Also included in the nonregulated interest expense is interdepartmental interest expense and capitalized interest at MGE Power Elm Road. During the six months ended June 30, 2009 and 2008, MGE Power Elm Road was charged $1.7 million and $2.3 million, respectively, in interest expense by Corporate on funds borrowed for the Elm Road Project. This expense is eliminated upon consolidation for MGE Energy only. The interest expense at MGE Power Elm Road is offset by $1.7 million and $2.3 million, respectively, in capitalized interest.

During both the six months ended June 30, 2009 and 2008, MGE Power Elm Road recorded $0.1 million in interest income on cash advanced to Elm Road Services, LLC for construction of transmission equipment and work done by ATC related to the Elm Road project.

### Transmission Investment Operations - MGE Energy and MGE

### Transmission investment other income

For the six months ended June 30, 2009 and 2008, other income at the transmission investment segment was $4.0 million and $3.3 million, respectively. The transmission investment segment holds our interest in ATC, and its income reflects our equity in the earnings of ATC.

### All Other Nonregulated Operations - MGE Energy

All other interest income, net for both the six months ended June 30, 2009 and 2008, was $1.4 million. Interest income for the six months ended June 30, 2009, represents $1.7 million in interdepartmental interest income from MGE Power Elm Road, partially offset by $0.3 million in interest expense on short-term debt. Interest income for the six months ended June 30, 2008, represents $2.3 million in interdepartmental interest income from MGE Power Elm Road, partially offset by $0.9 million in interest expense on short-term debt. The interdepartmental interest income is eliminated upon consolidation.

### Consolidated Other General Taxes

MGE Energy's and MGE's other general taxes increased $0.5 million or 6.2% for the six months ended June 30, 2009, when compared to the same period in 2008, due to increased license fee tax. The annual license fee tax expense is based on the prior year's adjusted operating revenues. Tax rates have not increased.

### Consolidated Income Taxes

MGE Energy's effective income tax rate for the six months ended June 30, 2009, is 35.1% compared to 35.7% for the same period in 2008. MGE's effective income tax rate for the six months ended June 30, 2009, is 34.9% compared to 35.6% for the same period in the prior year. The lower tax rates for the six months ended June 30, 2009, are due primarily to an increase in federal tax credits from the production of electricity from wind energy. The tax credit for 2009 is expected to exceed the credit for 2008 mainly due to a full year of generation from the Top of Iowa III wind farm in 2009. In 2008, wind generation occurred for approximately ten months.

Under 2009 Wisconsin Act 2, effective for years beginning on or after January 1, 2009, Wisconsin requires corporations to use combined reporting to compute their Wisconsin income for income tax purposes. Formerly, Wisconsin law required each corporation in a combined group to file separate returns. The effect of the combined reporting statute in Wisconsin is not expected to make any significant changes to the effective income tax rate or the tax accrual.

### Noncontrolling Interest, Net of Tax

The noncontrolling interest, net of tax reflects the accounting required for MGE Energy's interest in the WCCF and Elm Road generating projects. MGE Energy owns 100% of MGE Power West Campus and MGE Power Elm Road; however, due to the leasing arrangements for these projects with MGE, the entities are considered VIEs under FIN 46(R) and their results are consolidated with those of MGE, the primary beneficiary of the VIEs. Also included in noncontrolling interest, net of tax is MGE Energy's interest in MGE Transco.

For the six months ended June 30, 2009, MGE Energy (through its wholly owned subsidiary MGE Power) earned $3.8 million and $2.4 million, net of tax, for its interest in MGE Power West Campus and MGE Power Elm Road, respectively. Additionally, MGE Energy earned $0.7 million, net of tax for its interest in MGE Transco. These amounts are recorded as noncontrolling interest expense, net of tax, on MGE's consolidated statement of income.

For the six months ended June 30, 2008, MGE Energy (through its wholly owned subsidiary MGE Power) had earned $3.8 million and $2.1 million, net of tax, for its interest in MGE Power West Campus and MGE Power Elm Road, respectively. Additionally, MGE Energy had earned $0.3 million, net of tax, for its interest in MGE Transco. These amounts are recorded as noncontrolling interest expense, net of tax, on MGE's consolidated statement of income.

### Contractual Obligations and Commercial Commitments - MGE Energy and MGE

There were no material changes, other than from the normal course of business, to MGE Energy's and MGE's contractual obligations (representing cash obligations that are considered to be firm commitments) and commercial commitments (representing commitments triggered by future events) during the six months ended June 30, 2009, except as noted below. Further discussion of the contractual obligations and commercial commitments is included in Footnote 9 of this filing and Footnote 18 and "Contractual Obligations and Commercial Commitments for MGE Energy and MGE" under "Management's Discussion and Analysis of Financial Condition and Results of Operations" in MGE Energy's and MGE's 2008 Annual Report on Form 10-K.

### Columbia Environmental Matters - MGE Energy and MGE

As of June 30, 2009, MGE's share of various contractual commitments with vendors for environmental expenditures at Columbia is estimated to be $0.3 million for the remainder of 2009. These costs are expected to be capitalized and included in the consolidated balance sheet of MGE. See "Environmental Matters - Columbia" below for additional information regarding expected environmental expenditures at Columbia.

### Elm Road Construction - MGE Energy and MGE

In December 2008, we received notice from ERS that it had received a letter from Bechtel containing Bechtel's formal claim for schedule and cost relief on the construction of the Elm Road units. Bechtel has asserted two claims for cost and schedule relief in its letter to ERS. Although ERS is in the process of analyzing the claims and its responses to them, it has stated its belief that both claims are without merit. It has also stated its view that the only circumstances and events for which the Elm Road units' owners currently retain price adjustment risk under the contract are force majeure, wage escalation in excess of 4% annually as measured by published wage bulletins, delays caused by ERS, changes in scope or performance requested by ERS, and unforeseen sub-surface ground conditions. ERS has stated that it currently believes Bechtel was fully compensated for any and all impacts of the delayed start as indicated in certain change orders entered into between ERS and Bechtel prior to the start of construction of the Elm Road units. Furthermore, ERS has stated that it does not believe that the contract provides for relief based upon the cumulative impact of change orders. ERS invoked the dispute resolution process provided for in the contract in order to address the claims made by Bechtel under the contract. ERS and Bechtel agreed to combine these issues and Bechtel's claims into one mediation. Mediation was unsuccessful and therefore, both parties submitted the matter to binding arbitration pursuant to the contract. The arbitration is expected to be concluded in 2010. We are unable to predict the results of these claims or their effect on the costs recoverable under the existing facility leases, in the event that the outcome of the claims should cause total construction costs of the Elm Road units to exceed the amounts authorized in the PSCW order. Bechtel fell behind the revised target schedule in moving from construction to start-up, but developed a recovery plan and added resources in an effort to recover lost time. Bechtel has made, and continues to make, significant construction and start-up progress; however, at this time it has not fully kept pace with its revised schedule. See Footnote 6 for additional information regarding the claims made by Bechtel and the ERS response to those claims.

### Natural Gas Supply Contracts - MGE Energy and MGE.

MGE has natural gas supply commitments which include market-based pricing. Total natural gas supply commitments are estimated to be $16.9 million for the remainder of 2009, $23.8 million for 2010, and $0.6 million for 2011. Management expects to recover these costs in future customer rates.

### Wind Development Rights – MGE Energy.

In June 2009, MGE Energy, through its subsidiary MAGAEL, LLC, entered into agreements to purchase land development rights, including but not limited to land option agreements, electrical interconnection rights, wind data, engineering plans, licenses, permits, and governmental approvals for two wind development rights. An $0.8 million payment related to these agreements was made in 2009. Future payments related to these agreements are estimated to be $1.2 million in 2010, $0.8 million in 2011, $3.2 million in 2012, $0.4 million in 2013, $0.1 million in 2014, $1.7 million in 2015, and $0.4 million in 2016. These wind development rights may potentially be used to develop wind farms in three counties in Iowa with a capacity up to approximately 175 MWs. These agreements do not obligate MGE Energy to construct at these locations in Iowa.

### ATC Capital Commitment - MGE Energy and MGE.

On June 18, 2009, MGE Transco elected to participate in a voluntary capital call for ATC. As a result, MGE Transco contributed $0.9 million to ATC in July 2009. The amount and timing of future voluntary capital calls is uncertain and primarily dependent on the operations and expansion of ATC.

### Credit Facilities - MGE Energy and MGE

On March 31, 2009, MGE amended its existing credit agreement dated August 29, 2008, with JPMorgan Chase Bank, N.A., as lender, which provides MGE with a $20 million committed credit facility. The principal purpose of the amendment was to extend the expiration date of the original agreement from March 31, 2009, to March 30, 2010. The credit facility continues to be used as a backup facility to MGE's commercial paper program. As of June 30, 2009, no borrowings were outstanding under the credit facility. The amendment also changed the interest rate provisions of the original agreement. As amended, borrowings under the credit facility may bear interest at either (i) a LIBOR-based rate for an applicable interest period, plus 1.50% or (ii) an Alternate Base Rate, plus 1%. The Alternate Base Rate is defined as the greater of (1) JPMorgan Chase Bank, N.A.'s prime rate, (2) the Federal Funds Effective Rate (as defined in the original agreement) plus 0.50% and (3) the one-month LIBOR-based rate plus 1%. The amendment also changed the non-use fee to 0.150% per annum on the unused commitment under the credit facility.

### Liquidity and Capital Resources

### Cash Flows

The following summarizes cash flows during the six months ended June 30, 2009 and 2008, respectively:

*(In thousands)*

| Cash provided by/(used for): | MGE Energy 2009 | 2008 | MGE 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Operating activities | $82,644 | $62,519 | $82,467 | $62,696 |
| Investing activities | (37,513) | (61,789) | (36,484) | (61,798) |
| Financing activities | (40,888) | 947 | (41,371) | 477 |

### Cash Provided by Operating Activities

### MGE Energy

MGE Energy's consolidated net cash provided by operating activities is derived mainly from the electric and gas operations of its principal subsidiary, MGE.

Cash provided by operating activities for the six months ended June 30, 2009, was $82.6 million, an increase of $20.1 million when compared to the same period in the prior year primarily due to working capital changes.

MGE Energy's net income increased $0.5 million for the six months ended June 30, 2009, when compared to the same period in the prior year.

Deferred taxes increased $2.8 million for the six months ended June 30, 2009, compared to the six months ended June 30, 2008, primarily due to bonus tax depreciation allowed for Federal income tax purposes on certain property placed in service during 2009, as a result of the American Recovery and Reinvestment Act of 2009.

Working capital accounts resulted in $33.9 million in cash provided by operating activities for the six months ended June 30, 2009, compared to $15.2 million in cash provided by operating activities during the same period in the prior year. The increase in cash provided by working capital accounts is primarily attributable to lower accounts receivable and unbilled revenues balances.

Pension contribution resulted in an additional $2.2 million in cash used by operating activities for the six months ended June 30, 2009 when compared to the same period in the prior year. These contributions were made to comply with the Employee Retirement Income Security Act (ERISA) and the Pension Protection Act of 2006, and additional contributions were at management's discretion.

### MGE

Cash provided by operating activities for the six months ended June 30, 2009, was $82.5 million, an increase of $19.8 million when compared to the same period in the prior year primarily due to working capital changes.

Net income increased $0.6 million for the six months ended June 30, 2009, when compared to the same period in the prior year.

Deferred taxes increased $2.8 million for the six months ended June 30, 2009, compared to the six months ended June 30, 2008, primarily due to bonus tax depreciation allowed for Federal income tax purposes on certain property placed in service during 2009, as a result of the American Recovery and Reinvestment Act of 2009.

Working capital accounts resulted in $33.8 million in cash provided by operating activities for the six months ended June 30, 2009, compared to $15.4 million in cash provided by operating activities during the same period in the prior year. The increase in cash provided by working capital accounts is primarily attributable to lower accounts receivable and unbilled revenues balances.

Pension contribution resulted in an additional $2.2 million in cash used by operating activities for the six months ended June 30, 2009 when compared to the same period in the prior year. These contributions were made to comply with the Employee Retirement Income Security Act (ERISA) and the Pension Protection Act of 2006, and additional contributions were at management's discretion.

### Cash Used for Investing Activities

### MGE Energy

MGE Energy's cash used for investing activities decreased $24.3 million for the six months ended June 30, 2009, when compared to the same period in the prior year.

Capital expenditures for the six months ended June 30, 2009, were $34.8 million. This amount represents a $26.4 million decrease from the expenditures made in the same period in the prior year. This decrease is related to lower construction activity of $21.1 million related to Elm Road and a $7.0 million decrease of capital expenditures due to the completion in February 2008 of the Top of Iowa III wind generation project. These decreases were partially offset by an increase of $1.7 million in other utility capital expenditures.

During the six months ended June 30, 2009, MGE Transco made cash capital contributions, funded by MGE Energy, of $1.6 million to ATC compared to $1.3 million during the six months ended June 30, 2008.

### MGE

MGE's cash used for investing activities decreased $25.3 million for the six months ended June 30, 2009, when compared to the same period in the prior year.

Capital expenditures for the six months ended June 30, 2009, were $34.8 million. This amount represents a $26.4 million decrease from the expenditures made in the same period in the prior year. This decrease is related to lower construction activity of $21.1 million related to Elm Road and a $7.0 million decrease of capital expenditures due to the completion in February 2008 of the Top of Iowa III wind generation project. These decreases were partially offset by an increase of $1.7 million in other utility capital expenditures.

During the six months ended June 30, 2009, MGE Transco made cash capital contributions of $1.6 million to ATC compared to $1.3 million during the six months ended June 30, 2008.

### Cash (Used for) Provided by Financing Activities

### MGE Energy

Cash used for MGE Energy's financing activities was $40.9 million for the six months ended June 30, 2009, compared to $0.9 million of cash provided by MGE Energy's financing activities for the six months ended June 30, 2008.

MGE Energy received $6.3 million and $7.6 million in cash proceeds as the result of stock issued pursuant to the Stock Plan during the six months ended June 30, 2009 and 2008, respectively.

As of June 1, 2009, MGE Energy is purchasing stock for its Stock Plan from the open market rather than issuing new shares. All MGE Energy common stock shares under the Stock Plan are sold pursuant to a registration statement that has been filed with the SEC and is currently effective.

For the six months ended June 30, 2009, dividends paid were $16.7 million compared to $15.7 million for same period in the prior year. This increase was a result of higher dividend per share ($0.723 vs. $0.710) and an increase in the number of shares outstanding.

For the six months ended June 30, 2009, net short-term debt repayments were $30.5 million compared to net short-term borrowings of $9.0 million for the same period in the prior year.

### MGE

During the six months ended June 30, 2009, cash used for MGE's financing activities was $41.4 million compared to $0.5 million of cash provided by MGE's financing activities in the same period in the prior year.

For the six months ended June 30, 2009, net short-term debt repayments were $34.5 million compared to $18.0 million for the same period in the prior year.

Dividends paid from MGE to MGE Energy were $6.4 million for the six months ended June 30, 2009. No cash dividends were paid from MGE to MGE Energy for the six months ended June 30, 2008.

Equity contributions received by noncontrolling interest decreased $23.2 million as a result of MGE Power Elm Road requiring less funding for construction of property, plant and equipment.

### Capitalization Ratios

MGE Energy's capitalization ratios were as follows:

|  | MGE Energy June 30, 2009 | Dec. 31, 2008 |
| --- | ---: | ---: |
| Common shareholders' equity | 57.4% | 54.7% |
| Long-term debt | 31.7% | 31.1% |
| Short-term debt | 10.9% | 14.2% |

### MGE Energy's and MGE's Capital Requirements

As of June 30, 2009, MGE Energy had a working capital deficit (current liabilities exceeded current assets). This deficit is in part due to MGE Energy funding a portion of its capital commitments for the Elm Road project with short-term debt. MGE Energy intends to fund future capital commitments for the Elm Road project with funds generated from normal operations, the issuance of long-term debt, and short-term debt.

MGE Energy's and MGE's liquidity are primarily affected by their capital requirements. During the six months ended June 30, 2009, capital expenditures for MGE Energy and MGE totaled $34.8 million, which included $9.4 million of capital expenditures for Elm Road and $25.2 million of capital expenditures for utility operations.

The following table shows MGE's current credit ratings. The ratings presented reflect the current views of these rating agencies and are subject to change. MGE Energy is not yet rated because it has not issued any debt securities.

|  |  |  |
| --- | --- | --- |
|  | Standard & Poor's | Moody's |
| First Mortgage Bonds | AA- | Aa2 |
| Unsecured Medium Term Notes | AA- | Aa3 |
| Commercial Paper | A1+ | P1 |

A security rating is not a recommendation to buy, sell, or hold securities and may be subject to revision or withdrawal at any time by the assigning rating agency. MGE's access to the capital markets, including the commercial paper market and its financing costs in those markets, is dependent on its securities' ratings. None of MGE's borrowings is subject to default or prepayment due to downgrading of securities' ratings, although such a down grading could increase fees and interest charges under MGE Energy's and MGE's credit facilities.

### Environmental Matters

The following discussion is limited to updates or developments in environmental matters that occurred during the six months ended June 30, 2009. Further discussion of environmental matters is included in MGE Energy's and MGE's 2008 Annual Report on Form 10-K.

### Columbia

MGE and two other utilities jointly own Columbia, a coal-fired generating facility, which accounts for 225 MW (29%) of MGE's net generating capability. Various environmental initiatives are expected to result in significant additional operating and capital expenditures at Columbia. In April 2009, the owners filed a Certificate of Authority with the PSCW requesting authorization of an emissions reduction project. The operator's current estimates show that MGE's share of the capital expenditures required to comply with this environmental initiative will be approximately $140 million. According to the current estimate, compliance with this project is also expected to result in an increase to Columbia's ongoing operating expenses. MGE expects that the costs pertaining to this project will be fully recoverable through rates.

### Vacatur of CAMR and the Development of Maximum Achievable Control Standards for Electric Utilities

On February 9, 2009, the Justice Department, on behalf of the EPA, asked the U.S. Supreme Court to dismiss EPA's request (petition for certiorari) that the Court review the D.C. Circuit Court's vacatur of the Clean Air Mercury Rule (CAMR). This withdrawal paves the way for the EPA to develop Maximum Achievable Control Technology (MACT) standards for electric utilities. It is unclear at this time how quickly MACT standards will be created for electric utilities and how they will affect MGE's operations, however, earlier versions of the MACT rule for electric utilities focused on mercury emissions from electric utilities that burned oil and coal for distribution in commerce. The implementation of the MACT standards will likely affect our facilities that burn coal and oil, however, we are uncertain of the exact cost at this time.

### Global Climate Change Developments

#### EPA's Determination of Endangerment from Greenhouse Gases

On April 17, 2009, the EPA published a proposed finding that greenhouse gases ("GHGs") in the atmosphere endanger the public health and welfare of current and future generations. EPA further proposed finding that emission of these substances from new motor vehicles are contributing to this endangerment. Although EPA states that finalizing these findings will not in and of itself impose requirements on electric generating utilities, this endangerment finding would be the first step toward regulating GHGs from electric generating facilities under the Clean Air Act. At this time we cannot predict the likelihood nor the effect of such regulation on our generating facilities. MGE is already addressing its GHGs through voluntary actions, and MGE will continue to monitor proposed GHG legislation and regulatory developments.

#### EPA Rule on Greenhouse Gas Reporting

On March 10, 2009, the EPA signed the proposed mandatory GHG reporting rule (published in the Federal Register on April 10, 2009). The proposed rule requires reporting in 2011for emissions in 2010 from (1) specific source categories regardless of emissions levels (including MGE business activities such as electric production, fuel combustion, and propane and natural gas storage), and (2) facilities not specifically listed as source categories that emit 25,000 metric tons of GHG emissions (in carbon dioxide equivalents) per year. The proposed rule will require reporting of six GHG emission categories: carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O), hydrofluorocarbons (HFC), perfluorocarbons (PFC), sulfur hexafluoride (SF6), and other fluorinated gases. The proposed rule has not been finalized so it is difficult to assess at this time the exact impact on MGE. However, Wisconsin has already required larger electric generation facilities to report CO2 emissions for several years.

#### Proposed Climate Change Legislation

On June 26, 2009, the U.S. House of Representatives passed the American Clean Energy and Security Act of 2009 ("ACESA"). The proposed legislation has several titles that would collectively impact virtually all aspects of the economy, including electric and natural gas utilities.

The proposed legislation includes: (1) a "clean energy" title that, among other things, creates a nationwide combined efficiency and renewable electricity standard that requires 6 percent efficiency/renewables by 2012 increasing to 20 percent by 2020 and calls for increased research and development; (2) an "energy efficiency" title that increases energy efficiency across all sectors of the economy, including buildings, appliances, transportation, and industry; (3) a "global warming" title that calls for a cap-and-trade program that would reduce U.S. emissions of greenhouse gases economy-wide by 3 percent below 2005 levels in 2012, 20 percent below 2005 levels by 2020 and 83% below 2005 levels by 2050 and provides a methodology for distributing allowances to covered entities; and (4) a "transitioning" title that seeks to promote green jobs during the transition to a clean energy economy.

The U.S. Senate is considering proposed legislation. Any legislation passed by the Senate would need to be reconciled with the House legislation and signed by the President before it would become law.

MGE is a producer of GHG emissions, primarily from the fossil fuel generating facilities it utilizes to meet customers' energy needs, as well as from its natural gas pipeline system and fleet vehicles. Climate change and the regulatory response to it could significantly affect our operations in a number of ways, including but not limited to, increased operating costs and capital expenditures, restrictions on energy supply options, permitting difficulties and emission limits. However, the financial consequences of this compliance cannot be determined until final legislation is passed. MGE management would expect to seek and receive rate recovery of such compliance costs, yet the probability and specific impact of such regulation cannot be reasonably estimated at this time. MGE will continue to monitor proposed climate change legislation and regulation.

### Restructuring Activities

On January 19, 2006, MGE announced a plan, subject to certain conditions, that includes discontinuing coal use by the end of 2011 at Blount. The plant will continue to run on natural gas but will be reduced from its current approximate 190 MW capacity to 100 MW when coal burning is discontinued. MGE determined that certain employee positions will be eliminated as a result of this exit plan.

In March 2009, MGE received notification from MISO that in order to meet national electric system reliability standards, MGE will need to keep Blount available at full capacity until MISO declares that the 90 MW are no longer needed for system reliability. To comply with the MISO directive, MGE will delay plans for retiring 90 MW of generation equipment at Blount. The transition from burning coal to burning only natural gas will still occur by the end of 2011. After 2011, the entire plant will be operated exclusively on natural gas. MGE will be working with MISO to develop a detailed agreement for this continued operation, which among other things will include a mechanism for cost recovery. MGE management will also begin working on an implementation plan.

MGE has entered into agreements providing severance benefits to employees affected by the exit plan. In May 2009, renegotiated union agreements were ratified and resulted in changes to the involuntary and voluntary severance benefits. Estimated benefits expected to be paid are as follows: $0.1 million in 2010, $0.8 million in 2011, and $0.4 million in 2013.

MGE will recover in rates the costs associated with the discontinuance of coal at Blount. As such, the severance charges for these employees have been deferred and recognized on the consolidated balance sheet of MGE Energy and MGE as a regulatory asset.

### Other Regulatory Matters

### Fuel Credit

In April 2009, MGE filed an application with the PSCW requesting a proposed credit of $0.00204 per kWh, due to a decrease in actual electric fuel costs, when compared to those fuel costs projected in MGE's most recent rate order. MGE estimates this credit would reduce electric revenues by $4.6 million for 2009. This credit is based upon newly computed annual average fuel costs for 2009, using actual fuel costs for January, February and March and revised forecasts for April through December 2009. In May 2009, the PSCW approved the interim order authorizing MGE to implement the proposed credit, subject to refund with interest at 10.8% effective May 9, 2009 until the final PSCW order.

### Rate filing

In April 2009, MGE filed an application with the PSCW requesting a 4.5% increase to electric rates and a 2.3% increase to gas rates for 2010. The proposed increases cover costs for MGE's share of the new Elm Road generating station, transmission reliability enhancements, as well as infrastructure additions to its gas delivery system.

### New Accounting Principles

See Footnote 15 for discussion of new accounting pronouncements.

## Market risk

As filed, 9,796 characters.

MGE Energy and MGE are potentially exposed to market risk associated with interest rates, commodity prices, weather, and equity returns. MGE currently has no exposure to foreign currency risk. MGE manages some risk exposure through risk management policies and the use of derivative instruments. MGE's risk management policy prohibits speculative trading transactions. The recent uncertainty in the capital and credit markets has adversely affected the United States and global economies. Additional detail can be found in the Management Discussion and Analysis section of MGE Energy's and MGE's 2008 Annual Report on Form 10-K under " Recent Developments in the Capital and Credit Markets."

### Weather Risk

MGE's sales forecasts, used to establish rates, are set by the PSCW based upon estimated temperatures, which approximate 20-year historical averages. MGE's electric revenues are sensitive to the summer cooling season and, to some extent, to the winter heating season. A significant portion of MGE's gas system demand is driven by heating. MGE's gas revenues are collected under a combination of fixed and volumetric rates set by the PSCW based on "normal weather." As a result of weather-sensitive demand and volumetric rates, a portion of MGE's gas revenue is at risk for warmer-than-normal weather. MGE may use weather derivatives, pursuant to its risk management program, to reduce the impact of weather volatility on its gas revenues.

MGE may also be impacted by extreme weather conditions. Such conditions may restrict the operation of, or may damage, operating assets or may negatively impact the price of commodity and other costs.

A summary of actual weather information in the utility segment's service territory during the three and six months ended June 30, 2009, as measured by degree days, may be found in results of operations in this Report.

### Commodity Price Risk

MGE has commodity price risk exposure with respect to the price of natural gas, electricity, coal, emission credits, and oil. MGE employs established policies and procedures to reduce the market risks associated with changing commodity prices. MGE's commodity risks are somewhat mitigated by the current ratemaking process in place for recovering electric fuel cost, purchased energy costs, and the cost of natural gas. MGE's electric fuel costs are subject to fuel rules established by the PSCW.

MGE's electric operations burn natural gas in several of its peaking power plants or as a supplemental fuel at several coal-fired plants and, in many cases, the cost of purchased power is tied to the cost of natural gas. MGE bears significant regulatory risk for the recovery of such fuel and purchased power costs when they are higher than the base rate established in its current rate structure.

Under the electric fuel rules, MGE would be required to make a refund to customers if the fuel rules costs fall outside the lower end of the range and would be allowed to request a surcharge if the fuel rules costs exceeded the upper end of the range. The range is defined by the PSCW and has been modified throughout the years based on market conditions and other relevant factors. Currently, MGE is subject to a plus or minus 2% range. MGE assumes the risks and benefits of variances that are within the 2% bandwidth. For 2009, fuel and purchased power costs included in MGE's base fuel rates are $123.2 million. See Footnote 13.b. for additional information. MGE's gas segment is governed by the purchased gas adjustment clause (PGA). Under the PGA, MGE is able to pass through to customers the cost of gas, subject to certain limited incentives. Under both the electric fuel rules and PGA clause, MGE may include in the cost of fuel (natural gas or power) the costs and benefits of fuel price risk management tools implemented under the risk management plan approved by the PSCW.

MGE also reduces price risk caused by market fluctuations via physical contracts and financial derivative contracts, including futures, swaps, options, forwards, and other contractual commitments. The maximum length of time over which cash flows related to energy commodities can be hedged is two years.

At June 30, 2009, MGE has financial gas and electric commodity contracts to hedge commodity price risk in the gas and electric segments. These contracts are primarily comprised of exchange-traded option and future contracts to manage the cost of gas. MGE also holds FTRs which are used to hedge the risk of increased congestion charges. At June 30, 2009, the cost basis of these instruments exceeded their fair value by $7.8 million. Under the PGA clause and electric fuel rules, MGE may include in the costs of fuel (natural gas or power) the costs and benefits of the aforementioned fuel price risk management tools. Because these costs/benefits are recoverable, the related unrealized loss/gain has been deferred on the balance sheet as a regulatory asset/liability.

During 2009, MGE has also entered into futures and basis swaps to take advantage of physical and financial arbitrage opportunities between supply basins and pricing spreads between future months' gas supply. Until thresholds have been achieved, ratepayers receive 100% of the benefits or loss from these deals. If certain thresholds are achieved, MGE shareholders have the ability to receive 40% of the benefits or loss from these deals whereas ratepayers have the ability to receive 60% of the benefits or loss from these deals. At June 30, 2009, the fair value of these instruments exceeded their cost basis by less than $0.1 million.

MGE has also entered into a ten-year purchased power agreement which provides MGE with firm capacity and energy beginning June 1, 2012, and ending on May 31, 2022 (the "base term"). The agreement also allows MGE the option to purchase power during a period of time preceding the base term as well as an option to extend the contract after the base term. The agreement is a derivative contract and is recognized at its fair value on the balance sheet. The fair value of the contract at June 30, 2009, reflects a loss position of $9.6 million.

### Interest Rate Risk

Both MGE Energy and MGE have short-term borrowings at varying interest rates. MGE issues commercial paper for its short-term borrowings, while MGE Energy draws from its current credit facility to meet its short-term borrowing needs. Borrowing levels vary from period to period depending upon capital investments and other factors. Future short-term interest expense and payments will reflect both future short-term interest rates and borrowing levels. MGE Energy and MGE manage interest rate risk by limiting their variable rate exposure and continually monitoring the effects of market changes on interest rates. MGE is not exposed to changes in interest rates on a substantial portion of its long-term debt until that debt matures and is refinanced at market rates.

### Equity Price Risk - Pension-Related Assets

MGE currently funds its liabilities related to employee benefits through trust funds. These funds, which include investments in debt and equity securities, are managed by various investment managers. Changes in market value of these investments can have an impact on the future expenses related to these liabilities. The value of employee benefit plans trusts' assets have increased in value by approximately 5% during the six months ended June 30, 2009.

### Credit Risk - Counterparty

Credit risk is the loss that may result from counterparty nonperformance. MGE is exposed to credit risk primarily through its merchant energy business. MGE uses credit policies to manage its credit risk, which includes utilizing an established credit approval process, monitoring counterparty limits, employing credit mitigation measures such as collateral or prepayment arrangements, and using netting agreements.

Due to the possibility of extreme volatility in the prices of energy commodities and derivatives, the market value of contractual positions with individual counterparties could exceed established credit limits or collateral provided by those counterparties. If such a counterparty were then to fail to perform its obligations under its contract (for example, fail to deliver the electricity MGE originally contracted for), MGE could sustain a loss that could have a material impact on its financial results.

Additionally, if a counterparty were to default and MGE were to liquidate all contracts with that entity, MGE's credit loss would include the loss in value of mark-to-market contracts; the amount owed for settled transactions; and additional payments, if any, to settle unrealized losses on accrual contracts. As of June 30, 2009, no counterparties have defaulted.

MGE is obligated to provide service to all electric and gas customers within its respective franchised territories. MGE's franchised electric territory includes a 316 square-mile area in Dane County, Wisconsin, and MGE's franchised gas territory includes a service area covering 1,631 square miles in Wisconsin. Based on results for the year ended December 31, 2008, no one customer constituted more than 9% of total operating revenues for MGE Energy and MGE. Credit risk for electric and gas is managed by MGE's credit and collection policies, which are consistent with state regulatory requirements.

Cash, cash equivalents, and customer accounts receivable are the financial instruments that potentially subject MGE Energy and MGE to concentrations of credit risk. MGE Energy and MGE place their cash and cash equivalents with high credit-quality financial institutions. MGE has limited concentrations of credit risk from customer accounts receivable because of the large number of customers and relatively strong economy in its service territory.

## Controls and procedures

As filed, 2,070 characters.

During the second quarter of 2009, MGE Energy's management, including the principal executive officer and principal financial officer, evaluated its disclosure controls and procedures related to the recording, processing, summarization, and reporting of information in its periodic reports that it files with the SEC. These disclosure controls and procedures have been designed to ensure that material information relating to MGE Energy, including its subsidiaries, is accumulated and made known to MGE Energy's management, including these officers, by other employees of MGE Energy and its subsidiaries as appropriate to allow timely decisions regarding required disclosure, and that this information is recorded, processed, summarized, evaluated, and reported, as applicable, within the time periods specified in the SEC's rules and forms. Due to the inherent limitations of control systems, not all misstatements may be detected. These inherent limitations include the realities that judgments in decision making can be faulty and breakdowns can occur because of simple error or mistake. Additionally, controls can be circumvented by the individual acts of some persons, by collusion of two or more people, or by management override of the control. Also, MGE Energy does not control or manage certain of its unconsolidated entities and thus, its access and ability to apply its procedures to those entities is more limited than is the case for its consolidated subsidiaries.

As of June 30, 2009, MGE Energy's principal executive officer and the principal financial officer concluded that its disclosure controls and procedures were effective to accomplish their objectives. MGE Energy intends to continually strive to improve its disclosure controls and procedures to enhance the quality of its financial reporting.

During the quarter ended June 30, 2009, there were no changes in MGE Energy's internal controls over financial reporting that materially affected, or are reasonably likely to materially affect, MGE Energy's internal control over financial reporting.