# Boeing Co: Form 10-Q for the period ended Sep 30, 2009

- Company: [Boeing Co](/companies/ba.md) (CIK 12927)
- Form: 10-Q
- Filed: 2009-10-21
- Accepted by EDGAR: Oct 21, 2009, 12:41 ET
- Period: 2009-09-30
- Accession: 0001193125-09-210918
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/12927/000119312509210918/d10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/12927/000119312509210918/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2009-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2009-07-01 to 2009-09-30 | $16.69bn | us-gaap:Revenues |
| Revenue | 9 months, 2009-01-01 to 2009-09-30 | $50.34bn | us-gaap:Revenues |
| Cost of revenue | 3 months, 2009-07-01 to 2009-09-30 | $14.48bn | us-gaap:CostOfRevenue |
| Cost of revenue | 9 months, 2009-01-01 to 2009-09-30 | $42.03bn | us-gaap:CostOfRevenue |
| Gross profit | 3 months, 2009-07-01 to 2009-09-30 | $2.21bn | us-gaap:GrossProfit |
| Gross profit | 9 months, 2009-01-01 to 2009-09-30 | $8.31bn | us-gaap:GrossProfit |
| Research and development | 3 months, 2009-07-01 to 2009-09-30 | $3.57bn | us-gaap:ResearchAndDevelopmentExpense |
| Research and development | 9 months, 2009-01-01 to 2009-09-30 | $5.50bn | us-gaap:ResearchAndDevelopmentExpense |
| Operating income | 3 months, 2009-07-01 to 2009-09-30 | −$2.15bn | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2009-01-01 to 2009-09-30 | $403.0m | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months, 2009-07-01 to 2009-09-30 | −$687.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2009-01-01 to 2009-09-30 | $129.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2009-07-01 to 2009-09-30 | −$1.56bn | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2009-01-01 to 2009-09-30 | $44.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2009-07-01 to 2009-09-30 | −$2.23 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2009-01-01 to 2009-09-30 | $0.06 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2009-07-01 to 2009-09-30 | −$2.23 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2009-01-01 to 2009-09-30 | $0.07 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2009-07-01 to 2009-09-30 | 701,300,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2009-01-01 to 2009-09-30 | 708,100,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2009-01-01 to 2009-09-30 | $2.39bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2009-01-01 to 2009-09-30 | $965.0m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2009-01-01 to 2009-09-30 | $915.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Share repurchases | 9 months, 2009-01-01 to 2009-09-30 | $50.0m | us-gaap:PaymentsForRepurchaseOfCommonStock |
| Cash and equivalents | at 2009-09-30 | $6.09bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2009-09-30 | $30.23bn | us-gaap:AssetsCurrent |
| Total assets | at 2009-09-30 | $58.67bn | us-gaap:Assets |
| Current liabilities | at 2009-09-30 | $32.05bn | us-gaap:LiabilitiesCurrent |
| Current portion of debt | at 2009-09-30 | $973.0m | us-gaap:DebtCurrent |
| Shareholders' equity | at 2009-09-30 | −$1.03bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 62,237 characters.

### Consolidated Operating Results

The following table summarizes key indicators of consolidated results of operations:

*(Dollars in millions, except per share data)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$50,344** | $48,245 | **$16,688** | $15,293 |
| Earnings/(loss) from operations | **$403** | $4,193 | **$(2,151)** | $1,147 |
| Operating margins | **0.8%** | 8.7% | **\<12.9%** | 7.5% |
| Effective income tax rate | **71.3%** | 36.4% | **30.6%** | 40.8% |
| Net earnings/(loss) from continuing operations | **$52** | $2,740 | **$(1,560)** | $683 |
| Diluted earnings/(loss) per share | **$0.06** | $3.76 | **$(2.23)** | $0.96 |

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| Contractual backlog | **$298,959** | $323,860 |
| Unobligated backlog | **21,054** | 28,165 |

### Revenues

The following table summarizes revenues:

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Commercial Airplanes | **$24,868** | $23,674 | **$7,883** | $6,946 |
| Integrated Defense Systems | **25,114** | 24,006 | **8,744** | 8,497 |
| Boeing Capital Corporation | **496** | 535 | **166** | 171 |
| Other segment | **125** | 527 | **51** | 300 |
| Unallocated items and eliminations | **(259)** | (497) | **(156)** | (621) |
| Revenues | **$50,344** | $48,245 | **$16,688** | $15,293 |

Revenues for the nine and three months ended September 30, 2009 increased by $2,099 million and $1,395 million, a 4% and 9% increase compared with the same periods in 2008. Commercial Airplanes revenues increased by $1,194 million and $937 million for the nine and three month periods compared with the same periods of the prior year primarily due to lower commercial airplane deliveries in 2008 due to a labor strike and supplier production challenges on customer furnished galleys for certain wide-body airplanes. The 2009 revenue increases from higher commercial airplanes deliveries were partially offset by decreases in commercial aviation services revenues and lower intercompany revenue in 2009 compared with 2008. Integrated Defense Systems (IDS) revenues increased by $1,108 million and $247 million primarily due to higher revenues in the Global Services and Support (GS&S) segment and the Boeing Military Aircraft (BMA) segment partially offset by lower Network and Space Systems revenues. Boeing Capital Corporation (BCC) revenues decreased by $39 million during the nine months primarily due to a decrease in the customer financing portfolio. Other segment revenues decreased by $402 million and $249 million partly due to higher revenues in the prior year from the sale of four C-17 aircraft held under operating lease. Lower Unallocated items and eliminations improved revenues by $238 million and $465 million primarily due to lower P-8A Poseidon program (P-8A) intercompany revenues recognized by Commercial Airplanes during the three months ended September 30, 2009 compared with the same periods in the prior year.

### Earnings from Operations

The following table summarizes earnings from operations:

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Commercial Airplanes | **$(1,603)** | $2,154 | **$(2,837)** | $394 |
| Integrated Defense Systems | **2,470** | 2,351 | **885** | 854 |
| Boeing Capital Corporation | **112** | 143 | **39** | 37 |
| Other segment | **(105)** | (233) | **(36)** | (48) |
| Unallocated items and eliminations | **(471)** | (222) | **(202)** | (90) |
| Earnings/(loss) from operations | **$403** | $4,193 | **$(2,151)** | $1,147 |

Operating earnings for the nine and three months ended September 30, 2009 decreased by $3,790 million and $3,298 million compared with the same periods in 2008. Commercial Airplanes earnings decreased by $3,757 million and $3,231 million primarily due to $2,619 million of costs related to the first three 787 flight test aircraft included in research and development expense as a result of our determination in August 2009 that these aircraft could not be sold. The earnings decrease is also attributable to reach forward losses on the 747 program which grew by $1,352 million and $1,005 million during the nine and three months ended September 30, 2009. Lower commercial aviation services and intercompany earnings also contributed to lower 2009 earnings. These decreases were partially offset by higher commercial airplane deliveries in 2009 compared with 2008. IDS earnings increased by $119 million during the nine months, primarily due to higher earnings in the BMA segment resulting from a charge of $248 million on the Airborne Early Warning & Control (AEW&C) program in the second quarter of 2008, partially offset by lower earnings in the Network & Space Systems (N&SS) segment. Increased earnings for the three months were due to higher earnings in the BMA segment, partially offset by lower earnings in the N&SS and GS&S segments. BCC operating earnings decreased $31 million for the nine months compared with the same period in 2008 reflecting lower revenues, higher impairment expense and a provision for losses, partially offset by lower interest expense. Other segment losses decreased by $128 million for the nine months compared with the same period in 2008 primarily due to recognition of pre-tax expense of $82 million in the second quarter of the prior year to increase the allowance for losses on customer financing receivables related to lower U.S. airline customer credit ratings.

The most significant expense items not allocated to segments are shown in the table below.

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Share-based plans | **$(140)** | $(115) | **$(24)** | $(70) |
| Deferred compensation | **(134)** | 136 | **(88)** | 55 |
| Other unallocated items and eliminations | **(205)** | 11 | **(97)** | (4) |
| Pension | **69** | (194) | **24** | (51) |
| Postretirement | **(61)** | (60) | **(17)** | (20) |
| Total | **$(471)** | $(222) | **$(202)** | $(90) |

30

Share-based plans expense in Unallocated items and eliminations is higher in the current year resulting from a decrease in the amount of intercompany allocations compared with the same periods in the prior year.

Deferred compensation expense increased by $270 million and $143 million for the nine and three months ended September 30, 2009 compared with the same periods in the prior year. The year-over-year increases are primarily driven by changes in our stock price and broad stock market conditions.

Other unallocated items and eliminations expense for the nine and three months ended September 30, 2009 increased by $216 million and $93 million compared with the same periods in 2008, primarily due to timing of intercompany expense allocations, elimination of profit on intercompany items and a more favorable insurance adjustment in the same periods of the prior year.

Unallocated pension and other postretirement expense represents the difference between costs recognized under Generally Accepted Accounting Principles in the consolidated financial statements and federal cost accounting standards required to be utilized by our business segments for U.S. government contracting purposes.

We recorded net periodic benefit cost related to pensions and other postretirement benefits of $1,356 million and $452 million for the nine and three months ended September 30, 2009 and $849 million and $283 million for the same periods of the prior year. The increase was primarily due to higher amortization of pension actuarial losses. Not all net periodic benefit cost is recognized in earnings in the period incurred because it is allocated to production as product costs and a portion remains in inventory at the end of the reporting period. A portion of pension and other postretirement expense is recorded in the business segments and the remainder is included in unallocated pension and other postretirement expense.

Earnings from operations included the following amounts allocated to business segments and Other unallocated items and eliminations.

*(Dollars in millions)*

| Pension Plans | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Net periodic benefit cost allocated to business segments | **(725)** | (389) | **(254)** | (125) |
| Net periodic benefit cost in Other unallocated items and eliminations | **69** | (194) | **24** | (51) |
| Net periodic benefit cost included in Earnings/(loss) from operations | **$(656)** | $(583) | **$(230)** | $(176) |

*(Dollars in millions)*

| Other Postretirement Benefit Plans | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Net periodic benefit cost allocated to business segments | **(405)** | (358) | **(146)** | (112) |
| Net periodic benefit cost in Other unallocated items and eliminations | **(61)** | (60) | **(17)** | (20) |
| Net periodic benefit cost included in Earnings/(loss) from operations | **$(466)** | $(418) | **$(163)** | $(132) |

31

### Other Earnings Items

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| **Earnings/(loss) from operations** | **$403** | $4,193 | **$(2,151)** | $1,147 |
| Other income/(loss), net | **7** | 257 | **(4)** | 55 |
| Interest and debt expense | **(229)** | (145) | **(92)** | (49) |
| **Earnings/(loss) before income taxes** | **181** | 4,305 | **(2,247)** | 1,153 |
| Income tax (expense)/benefit | **(129)** | (1,565) | **687** | (470) |
| **Net earnings/(loss) from continuing operations** | **$52** | $2,740 | **$(1,560)** | $683 |

Other income for the nine and three months ended September 30, 2009 decreased by $250 million and $59 million compared with the same periods in 2008 primarily driven by a reduction in investment income as a result of lower interest rates and lower investment balances. Interest and debt expense increased by $84 million and by $43 million due to additional debt issued in 2009.

For a discussion related to Income Taxes see Note 4.

### Backlog

Contractual backlog of unfilled orders excludes purchase options, announced orders for which definitive contracts have not been executed and unobligated U.S. and non-U.S. government contract funding. The decrease in contractual backlog during the nine months ended September 30, 2009 was primarily due to lower Commercial Airplanes backlog.

Unobligated backlog includes U.S. and foreign government definitive contracts for which funding has not been authorized. The decrease in unobligated backlog during the nine months ended September 30, 2009 is primarily due to a partial termination for convenience from the U.S. Army of the Future Combat Systems (FCS) System Development and Demonstration contract relating to Manned Ground Vehicles and associated systems and equipment and funding of existing multi-year contracts including the FCS, V-22, Chinook, Proprietary and Ground-Based Midcourse Defense (GMD) programs.

### Segment Results of Operations

### Commercial Airplanes

### Business Environment and Trends

After several months of rapid deterioration during the first half of 2009, world Gross Domestic Product (GDP) growth forecasts are stabilizing. These forecasts continue to project a slow global economic recovery with world real GDP contracting by over 2% in 2009 and remaining below long-term trend growth in 2010.

The sharp economic decline is causing passenger traffic to contract. The International Civil Aviation Organization estimates passenger traffic grew 1% in 2008 with first half growth running fairly close to long-term trend. This was followed by a significant decline in the second half of 2008. There is further downward pressure on 2009 traffic growth. Current forecasts for 2009 global passenger traffic growth are for mid-single digit contraction similar to previous downturns (-3% in 2001 and 1991) followed by moderate growth in 2010. Monthly statistics indicate that world traffic contracted at a pace of approximately 7% in the first half of 2009.

The unprecedented decline in world trade and sharp reduction in credit availability have hit air cargo more severely than passenger traffic. Although the rate of decline is stabilizing, air cargo contracted 25% in the first half of 2009 following a 6% decline in 2008. Full year 2009 air cargo traffic outlooks reflect the first contraction in global trade since 1982 with the International Air Transport Association (IATA) forecasting a 14% contraction in air cargo traffic.

The global airline profitability outlook has deteriorated significantly. Revenues have fallen faster than traffic as fuel surcharges have declined and airlines reduce fares to stimulate travel. In addition, premium class revenues have fallen more sharply than economy revenues due to cuts in business travel and business travelers buying down from premium cabins. Lower fuel prices and airline cost saving measures are only partially offsetting the decline in revenues. Following 2008 net losses of $17 billion, IATA now forecasts the global airline industry will lose $11 billion in 2009 and not return to profitability until 2011. In response to these large losses, airlines have raised $18 billion of cash from capital markets but the finances of many airlines remain under pressure.

In this challenging environment, airlines continue to adapt their operations to meet the realities of the market. Global passenger capacity was down about 3% in the first half of 2009. Capacity cuts are coming through a combination of frequency and route cuts in markets that are no longer profitable, lower daily airplane utilization (flight hours per day), and parking/scrapping of older generation airplanes. Airlines are also replacing older less fuel efficient airplanes, reducing non-fuel costs and finding new ways to partner through alliances or via mergers/acquisitions.

These conditions are causing customers to request cancellations, modifications, or rescheduling of their existing orders and advance payment schedules to meet revised fleet plans or address financing and cash flow issues. Whether such requests will result in a material adverse impact on our earnings, cash flow or financial position depends on a number of factors including the type of aircraft, how much compensation is paid to us for costs already incurred and our ability to reschedule other orders to replace those canceled, modified, or rescheduled.

Beyond the near-term market uncertainties, the long-term outlook for the industry remains resilient due to the fundamental drivers of air travel growth: economic growth and the increasing propensity to travel due to increased trade, globalization and improved airline services driven by liberalization of air traffic rights between countries. Our 20-year forecast is for a long-term average growth rate of 5% per year for passenger and cargo traffic based on a projected average annual worldwide real economic growth rate of 3%. Based on long-term global economic growth projections, and factoring in increased utilization of the worldwide airplane fleet and requirements to replace older airplanes, we project a $3.2 trillion market for 29,000 new airplanes over the next 20 years.

In 2009, in response to these market dynamics, we announced plans to reduce production rates on the 777 program and to delay planned increases to the production rates of the 747 and 767 programs. These changes are not expected to affect 2009 revenues but did reduce margins on airplane programs. Separately, changes in forecasted escalation price indices reduced margins on all programs for the nine months ended September 30, 2009. The reduction in these escalation indices had the effect of lowering estimated revenues for deliveries predominantly after 2009. The escalation indices are driven by commodity and other inflation price indices and could remain volatile in the current economic environment.

### Operating Results

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$24,868** | $23,674 | **$7,883** | $6,946 |
| (Loss)/earnings from operations | **$(1,603)** | $2,154 | **$(2,837)** | $394 |
| Operating margins | **-6.4%** | 9.1% | **-36.0%** | 5.7% |

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| Contractual backlog | **$253,938** | $278,575 |

### Revenues

Year over year changes in Revenue are shown in the following table:

*(Dollars in millions)*

|  | Nine months ended September 30, 2009 vs. September 30, 2008 | Three months ended September 30, 2009 vs. September 30, 2008 |
| --- | ---: | ---: |
| New airplane sales | $1,648 | $999 |
| Commercial aviation services business | (434) | (85) |
| Other | (20) | 23 |
| Total | $1,194 | $937 |

Revenues for the nine months ended September 30, 2009 increased by $1,194 million compared with the same period of 2008. This increase in revenues was primarily attributable to higher new airplane deliveries partially offset by lower commercial aviation services and intercompany revenues in 2009. The decrease in revenues from commercial aviation services business was driven by lower overall volume due to economic conditions.

Revenues for the three months ended September 30, 2009 increased by $937 million compared with the same period of 2008. This increase in revenue was primarily attributable to higher new airplane deliveries partially offset by lower commercial aviation services and intercompany revenues. The increase in new airplane deliveries reflects lower airplane deliveries in 2008 due to a labor strike and supplier production challenges on customer-furnished galleys for certain wide-body aircraft.

Commercial jet aircraft deliveries, including intercompany deliveries were as follows:

|  |  |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| **Program** | **737** | **747** | **767** | **777** | **Total** |
| Deliveries during the first nine months of 2009 | 280 | 6 | 10 | 63 | 359 |
| Deliveries during the first nine months of 2008 | 254 | 13 | 8 | 50 | 325 |
| Deliveries during the third quarter of 2009 | 90 |  | 4 | 19 | 113 |
| Deliveries during the third quarter of 2008 | 67 | 4 | 2 | 11 | 84 |
| Cumulative deliveries as of 9/30/2009 | 3,036 | 1,416 | 979 | 811 |  |
| Cumulative deliveries as of 12/31/2008 | 2,756 | 1,410 | 969 | 748 |  |

### Earnings from Operations

Earnings from operations for the nine and three months ended September 30, 2009 decreased by $3,757 million and $3,231 million primarily due to the reclassification from inventory to research and development expense of $2,481 million of costs related to the three 787 flight test aircraft. $138 million of costs incurred on the first three flight test aircraft incurred in August and September 2009 also increased research and development expense and reduced earnings. The earnings’ decrease is also attributable to reach forward losses on the 747 program which grew by $1,352 million in 2009, of which $1,005 million was recorded in the third quarter of 2009, primarily due to increased production costs and the difficult market conditions affecting the 747-8. The $2,619 million of costs included in research and development expense for the first three flight-test 787 airplanes was a result of our determination in August 2009 that these aircraft could not be sold and was primarily responsible for an increase in research and development expense of $2,534 million and $2,567 million. Lower commercial aviation services revenues and margins reduced earnings by $288 million and $119 million. Higher infrastructure cost allocations related to the 787 and 747-8 schedule delays announced in 2008 and infrastructure costs incurred during the 2008 IAM strike reduced earnings by $173 million and $28 million. These decreases were partially offset by increased earnings of $717 million and $473 million from new airplane deliveries offset by lower intercompany revenues. Additionally, period and other costs increased for the nine month period by $127 million but decreased for the three month period by $17 million.

### Backlog

The decrease in contractual backlog during the nine months ended September 30, 2009 compared with December 31, 2008 was due to deliveries in excess of orders, changes in projected revenue escalation and cancellations of orders.

A number of our customers may have contractual remedies that may be implicated by program delays. We continue to address customer claims and requests for other contractual relief as they arise. However, once orders are included in firm backlog, orders remain in backlog until canceled or fulfilled, although the value of orders is adjusted based upon changing revenue escalation assumptions and as changes to price and schedule are agreed to with customers.

### Accounting Quantity

The accounting quantities, undelivered units under firm orders and number of cumulative firm orders were as follows:

|  | Program |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| **As of 9/30/2009** | **737** | **747** | **767** | **777** | **787** |
| Program accounting quantities | **4,400** | **1,499** | **1,035** | **1,100** | **\*** |
| Undelivered units under firm orders1 | **2,118** | **107** | **57** | **303** | **850** |
| Cumulative firm orders2 | **5,154** | **1,523** | **1,036** | **1,114** |  |
|  | Program |  |  |  |  |
| As of 6/30/2009 | 737 | 747 | 767 | 777 | 787 |
| Program accounting quantities | 4,400 | 1,499 | 1,023 | 1,050 | \* |
| Undelivered units under firm orders1 | 2,137 | 107 | 61 | 314 | 850 |
| Cumulative firm orders2 | 5,083 | 1,523 | 1,036 | 1,106 |  |
|  | Program |  |  |  |  |
| As of 3/31/2009 | 737 | 747 | 767 | 777 | 787 |
| Program accounting quantities | 4,200 | 1,499 | 1,023 | 1,050 | \* |
| Undelivered units under firm orders1 | 2,203 | 110 | 67 | 331 | 878 |
| Cumulative firm orders2 | 5,050 | 1,524 | 1,039 | 1,102 |  |

35

|  | Program |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| As of 12/31/2008 | 737 | 747 | 767 | 777 | 787 |
| Program accounting quantities | 4,200 | 1,499 | 1,023 | 1,050 | \* |
| Undelivered units under firm orders1 | 2,270 | 114 | 70 | 350 | 910 |
| Cumulative firm orders2 | 5,026 | 1,524 | 1,039 | 1,098 |  |

\* The accounting quantity for the 787 program will be determined in the year of first airplane delivery.

1 Undelivered units are not adjusted for cancellations subsequent to September 30, 2009, June 30, 2009, March 31, 2009 and December 31, 2008.

2 Cumulative firm orders represent the cumulative number of commercial jet aircraft deliveries plus undelivered firm orders.

**737 Program** The accounting quantity for the 737 program increased by 200 units during the nine months ended September 30, 2009.

**747 Program** There was no change in the accounting quantity for the 747 program during the nine months ended September 30, 2009.

In the fourth quarter of 2008, we recorded a charge of $685 million to recognize a reach-forward loss. The charge was primarily related to higher than anticipated costs due to late changes to wing design which drove new load requirements into the fuselage and created other statement of work changes for our suppliers. During the first quarter of 2009, an additional charge of $347 million was recorded. This charge was primarily caused by a reduction in projected delivery price increases associated with escalation and an increase in estimated costs due to production rate changes.

During the three months ending September 30, 2009, we recorded an additional charge of $1,005 million. $643 million of the charge reflects higher estimated production costs, including both additional internal production costs and higher supplier expenses, attributable to greater than expected re-work and disruption in manufacturing due to late maturity of engineering designs. The remaining $362 million was primarily due to challenging market conditions and our related decision to defer a planned increase in the 747-8 production rate.

As announced on October 6, 2009, first flight of the 747-8 Freighter is expected to occur in the first quarter 2010 with the flight test program taking place in 2010. First delivery of the 747-8 Freighter is expected in the fourth quarter of 2010. First delivery of the Intercontinental passenger variant remains scheduled for the fourth quarter of 2011. A gap between the delivery of the last 747-400 and the first 747-8 will contribute to lower 747 program revenues until deliveries of the 747-8 begin.

**767 Program** The accounting quantity for the 767 program increased by 12 units during the three months ended September 30, 2009. In April 2009, we announced a delay in previous plans to increase production.

**777 Program** The accounting quantity for the 777 program increased by 50 units during the three months ended September 30, 2009. Delivery of the first 777 Freighter occurred in February 2009. In April 2009, we announced that we will lower the production rate on our 777 airplane program, affecting deliveries beginning in June 2010.

**787 Program** During the three months ended September 30, 2009, we concluded that the first three flight-test 787 aircraft could not be sold as previously anticipated due to the inordinate amount of rework and unique and extensive modifications made to those aircraft. Therefore costs of $2,481 million previously recorded as program inventory as of July 31, 2009 were reclassified to research and development expense. Costs incurred in August and September 2009 of $138 million related to these flight-test airplanes were also included in research and development expense. We believe that the other three additional 787 flight test aircraft are commercially saleable and we continue to include costs related to those aircraft in program inventory at September 30, 2009. If we determine that one or more of the other flight test aircraft cannot be sold we may incur additional charges.

We are currently implementing the aircraft modifications required in connection with the need to reinforce an area within the side-of-body section of the 787 aircraft, and we are in the final stages of assembly and planning for flight test. We continue to address other challenges associated with assembly of the initial airplanes, including management of our extended global supply chain, completion and integration of traveled work, weight and systems integration. We are also continuing efforts to satisfy customer mission and performance needs in light of the anticipated weight of their respective aircraft.

As announced on August 27, 2009, we currently expect the first flight of the 787 by the end of 2009 and first delivery in the fourth quarter of 2010. The new schedule reflects the required side-of-body modifications and the addition of several weeks of schedule margin to reduce flight test and certification risk. The current flight test and delivery schedules also reflect the cumulative impacts of disruption caused by the 2008 IAM strike, the requirement to replace certain fasteners in early production airplanes, parts unavailability, as well as the impact from the challenges mentioned in the paragraphs above. We continue to work with our customers and suppliers to assess the specific impacts of schedule changes, including delivery delays and supplier assertions associated with such changes. A number of our customers have contractual remedies for schedule delays and/or performance. We continue to address customer claims and requests for other contractual relief as they arise.

### Additional Considerations

The 787 and 747-8 programs highlight the risks that are always inherent in new airplane programs and new derivative airplanes, particularly as both the 747-8 and the 787 begin the flight test and certification phases of program development. Costs related to development of new programs and derivative airplanes are expensed as incurred. Costs to produce new aircraft are included in inventory and accounted for using program accounting. Airplane programs have risk for reach-forward losses if our estimated production costs exceed our estimated program revenues for the accounting quantity. Generally commercial airplanes are sold on a firm fixed-price basis with an indexed price escalation clause and are often sold several years before scheduled delivery. Each customer purchase agreement contains an escalation clause to account for the effects of economic fluctuations over the period of time from airplane sale to airplane delivery. A price escalation formula based on pre-defined factors is used to determine the final price of the airplane at the time of customer delivery. While firm fixed-price contracts allow us to benefit from cost savings, they also expose us to the risk of cost overruns. Many new airplanes and derivatives have highly complex designs, utilize exotic materials and require extensive coordination and integration with supplier partners. As technical or quality issues arise, such as issues experienced on the 787 and 747-8 programs, we may experience schedule delays and higher costs to complete new programs and derivative aircraft. Additionally, price escalation factors may also impact margins by reducing the estimated price of airplanes delivered in the future. Changes to the program accounting quantity, production costs and rates, costs associated with increasing production capacity, learning curve, anticipated cost reductions, flight test and certification schedules, costs and schedule for derivative airplanes, and status of customer claims, supplier assertions and other contractual negotiations could also result in lower margins or a material charge if the program has or is determined to have a reach-forward loss. While we believe the cost and revenue estimates incorporated in the financial statements are appropriate, the technical complexity of these programs creates financial risk as additional completion costs may become necessary or scheduled delivery dates could be extended, which could trigger termination provisions, order cancellations or other financially significant exposure.

### Integrated Defense Systems

### Business Environment and Trends

In April 2009, the U.S. Department of Defense (U.S. DoD) announced recommended changes for inclusion in the fiscal year 2010 budget. The President’s budget, submitted to Congress in May 2009, incorporated many of the U.S. DoD recommendations. If these changes are approved by Congress, future funding for a number of our programs including C-17, FCS, F-22, GMD and Transformational Satellite Communications System (TSAT) could be reduced. We will continue to evaluate the defense budget as it progresses through Congress.

### IDS Realignment

Effective January 1, 2009, certain programs were realigned between IDS segments. Business segment data for all periods presented have been adjusted to reflect the realignment. See Note 15.

### Operating Results

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$25,114** | $24,006 | **$8,744** | $8,497 |
| Earnings from operations | **$2,470** | $2,351 | **$885** | $854 |
| Operating margins | **9.8%** | 9.8% | **10.1%** | 10.1% |

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| Contractual backlog | **$45,020** | $45,285 |
| Unobligated backlog | **20,777** | 27,719 |

### Revenues

IDS revenues for the nine and three months ended September 30, 2009 increased by $1,108 million and $247 million, a 5% and 3% increase from the same periods in 2008, primarily due to higher revenues in the GS&S and BMA segments. IDS revenues for the three month period were impacted by lower N&SS segment revenues.

### Earnings from Operations

IDS operating earnings for the nine and three months ended September 30, 2009 increased by $119 million and $31 million. Operating margins remained constant for the nine and three month periods. Increased earnings for the nine months were due to higher earnings in the BMA segment primarily resulting from a charge of $248 million recorded in the second quarter of 2008 on the AEW&C program, partially offset by lower earnings in the N&SS segment. Increased earnings for the three months ended September 30, 2009 were primarily due to higher earnings in the BMA segment, partially offset by lower earnings in the N&SS and GS&S segments.

### Backlog

IDS total backlog was $65,797 million at September 30, 2009, lower by $7,207 million from $73,004 million at December 31, 2008. The decrease was partly due to a partial termination for convenience from the U.S. Army of the FCS System Development and Demonstration contract relating to Manned Ground Vehicles and associated systems and equipment and current year deliveries and sales on multi-year contracts awarded in prior years with the largest decreases in FCS, GMD and F/A-18 programs.

For further details on the changes between periods, refer to the discussions of the individual segments below.

### Additional Considerations

Our business includes a variety of development programs which have complex design and technical challenges. Many of these programs have cost-type contracting arrangements. In these cases the associated financial risks are primarily in lower profit rates or program cancellation if milestones and technical progress are not accomplished. Examples of these programs include Airborne Laser, EA-18G, Family of Beyond Line-of-Sight Terminals, FCS, GMD, Joint Tactical Radio System, P-8A and Proprietary programs.

Some of our development programs are contracted on a fixed-price basis. Many of these programs have highly complex designs. As technical or quality issues arise, we may experience schedule delays and cost impacts, which could increase our estimated cost to perform the work or reduce our estimated price, either of which could result in a material charge. These programs are ongoing, and while we believe the cost and fee estimates incorporated in the financial statements are appropriate, the technical complexity of these programs creates financial risk as additional completion costs may become necessary or scheduled delivery dates could be extended, which could trigger termination provisions, the loss of satellite in-orbit incentive payments, or other financially significant exposure. These programs have risk for reach-forward losses if our estimated costs exceed our estimated contract revenues. Examples of these programs include AEW&C, International KC-767 Tanker, commercial and military satellites, Vigilare and High Frequency Modernisation.

### Boeing Military Aircraft

### Operating Results

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$10,324** | $10,169 | **$3,951** | $3,702 |
| Earnings from operations | **$1,160** | $929 | **$486** | $388 |
| Operating margins | **11.2%** | 9.1% | **12.3%** | 10.5% |

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| Contractual backlog | **$26,112** | $25,710 |
| Unobligated backlog | **9,634** | 10,048 |

### Revenues

BMA revenues for the nine and three months ended September 30, 2009 increased $155 million and $249 million, a 2% and 7% increase compared with the same periods in 2008. The increase for the nine months was primarily due to higher deliveries and volume on several rotorcraft programs, partly offset by lower volume on several global strike and weapons programs. The increase for the three months was primarily due to higher deliveries.

Deliveries of units for new-build production aircraft, excluding remanufactures and modifications, were as follows:

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| F/A-18 Models | **36** | 33 | **13** | 12 |
| T-45TS Goshawk | **6** | 5 | **2** | 2 |
| F-15E Eagle | **10** | 11 | **4** | 7 |
| C-17 Globemaster | **12** | 12 | **5** | 4 |
| KC-767 Tanker | **1** | 2 |  |  |
| AH-64 Apache | **20** | 2 | **7** | 1 |
| CH-47 Chinook | **4** | 8 | **3** | 4 |
| Total new-build production aircraft | **89** | 73 | **34** | 30 |

### Earnings from Operations

BMA operating earnings for the nine and three months ended September 30, 2009 increased by $231 million and $98 million, increases of 25% from the same periods in 2008. The increase for the nine months was primarily due to a charge of $248 million recorded on the AEW&C program in the second quarter of 2008 and increased cost estimates related to the International Association of Machinists and Aerospace Workers strike in the third quarter of 2008, partly offset by changes in contract and delivery mix. Increased earnings for the three months ended September 30, 2009 were partly due to higher deliveries and volume, changes in contract and delivery mix and the aforementioned strike.

### Backlog

BMA total backlog was $35,746 million at September 30, 2009, virtually unchanged from December 31, 2008. Backlog increases due to current year orders for P-8 India, C-17 and Chinook aircraft were offset by revenues recognized on contracts received in prior years.

### Additional Considerations

Items which could have a future impact on BMA operations include the following:

**AEW&C** During 2006, we recorded charges of $770 million and during the second quarter of 2008, we recorded a charge of $248 million related to revised cost and revenue estimates to complete the AEW&C programs in Australia and Turkey. The 2008 charge, primarily related to our program in Australia, was due to subsystem development issues on the electronic warfare and ground support systems and the additional time required for integration testing. These factors required a revised delivery schedule for the Australian aircraft. These delays are not expected to affect delivery schedules to our other AEW&C customers. The AEW&C development program, also known as Wedgetail in Australia, Peace Eagle in Turkey and Peace Eye in the Republic of Korea, consists of a 737-700 aircraft outfitted with a variety of command and control and advanced radar systems, some of which have never been installed on an airplane before. Wedgetail includes six aircraft and Peace Eagle and Peace Eye include four aircraft each. These are advanced and complex fixed-price development programs involving technical challenges at the individual subsystem level and in the overall integration of these subsystems into a reliable and effective operational capability. We believe that the cost and revenue estimates incorporated in the financial statements are appropriate; however, the technical complexity of the programs creates financial risk as additional completion costs may be necessary or scheduled delivery dates could be delayed.

**International KC-767 Tanker Program** During the nine months ended September 30, 2009, the BMA segment recorded charges of $51 million related to this program. During the years ended December 31, 2008 and 2007, the BMA segment recorded charges of $85 million and $152 million related to this program. The 2007 charge was partially offset at the consolidated level. The International KC-767 Tanker program includes four aircraft for the Italian Air Force and four aircraft for the Japanese Air Self Defense Force. As of September 30, 2009, we delivered three tankers to Japan. These programs are ongoing, and while we believe the revenue and cost estimates incorporated in the financial statements are appropriate, the technical complexity of the programs creates financial risk as additional completion and development costs may be necessary or remaining scheduled delivery dates could be delayed.

**C-17** See the discussion of C-17 in Note 7 Liabilities, Commitments and Contingencies.

### Network and Space Systems

### Operating Results

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$8,492** | $8,485 | **$2,711** | $2,987 |
| Earnings from operations | **$698** | $806 | **$252** | $302 |
| Operating margins | **8.2%** | 9.5% | **9.3%** | 10.1% |

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| Contractual backlog | **$7,764** | $8,868 |
| Unobligated backlog | **10,662** | 16,981 |

### Revenues

N&SS revenues for the nine and three months ended September 30, 2009 increased by $7 million and decreased by $276 million, an increase of 0% and decrease of 9% compared with the same periods in 2008. The decrease for the three months is primarily due to lower volume on the SBInet, GMD and FCS programs, partly offset by higher volume on several satellite programs. In addition, revenues for the three months included a Delta II commercial launch in 2008.

### Earnings from Operations

N&SS operating earnings for the nine and three months ended September 30, 2009 decreased by $108 million and $50 million, a 13% and 17% decrease from the same periods in 2008. The decrease for the nine months is partly due to charges related to the Sea Launch bankruptcy. Earnings in first quarter of 2008 included a favorable settlement on a civil satellite program. The decrease for the three months was primarily due to lower revenues and change in contract mix.

### Backlog

N&SS total backlog was $18,426 million at September 30, 2009 a decrease of 29% from December 31, 2008. The decrease is primarily due to a partial termination for convenience from the U.S. Army of the FCS System Development and Demonstration contract relating to Manned Ground Vehicles and associated systems and equipment and revenues recognized on FCS, GMD, and Proprietary programs.

### Additional Considerations

Items which could have a future impact on N&SS operations include the following:

**Business Environment and Trends** In June 2009, we received a partial termination for convenience from the U.S. Army of the FCS System Development and Demonstration contract relating to Manned Ground Vehicles and associated systems and equipment. We believe the final restructured FCS contract will negatively impact revenue and earnings in the N&SS segment going forward. In addition, we completed the TSAT risk reduction and system definition contract in July 2009 and do not anticipate a future TSAT space segment program competition. As a result of lower than anticipated FCS, GMD and TSAT revenue and earnings, we tested N&SS goodwill for impairment as of September 30, 2009. No impairment was indicated by our test. Additional recommended budgetary changes, if included in the budget and approved by Congress, could further impact N&SS programs. We will monitor the defense budget as it progresses through Congress, evaluate its impact on our programs, and test for impairment as appropriate.

**United Launch Alliance** On December 1, 2006, we completed the transaction with Lockheed Martin Corporation (Lockheed) to create a 50/50 joint venture named United Launch Alliance L.L.C. (ULA). ULA combines the production, engineering, test and launch operations associated with U.S. government launches of Boeing Delta and Lockheed Atlas rockets. In connection with the transaction, we initially contributed net assets of $914 million at December 1, 2006. The book value of our investment exceeds our proportionate share of ULA’s net assets. This difference will be expensed ratably in future years. Based on the adjusted contributions and the conformed accounting policies established by ULA, this amortization is expected to be approximately $15 million annually for the next 15 years.

In connection with the formation of ULA, we each have agreed to extend a line of credit to ULA of up to $200 million to support its working capital requirements during the 5 year period following December 1, 2006. We and Lockheed transferred performance responsibility for certain U.S. government contracts to ULA as of the closing date. We and Lockheed agreed to jointly guarantee the performance of those contracts to the extent required by the U.S. government. We and Lockheed have also each committed to provide ULA with up to $122 million of additional capital contributions in the event ULA does not have sufficient funds to make a required payment to us under an inventory supply agreement. See Note 5.

We agreed to indemnify ULA through December 31, 2020 against potential non-recoverability and non-allowability of $1,360 million of Boeing Delta inventories included in contributed assets plus $1,860 million of inventory subject to an inventory supply agreement which ends on March 31, 2021. Since inception, ULA has sold $982 million of inventories that were contributed by us. As part of its integration, ULA is continuing to assess the future of the Delta II program beyond what is currently on contract. In the event ULA is unable to sell additional Delta II inventory, earnings could be reduced by up to $85 million.

We agreed to indemnify ULA against potential losses that ULA may incur in the event ULA is unable to obtain certain additional contract pricing from the USAF for four satellite missions. We believe ULA is entitled to additional contract pricing. In December 2008, ULA submitted a claim to the USAF to re-price the contract value for two of the four satellite missions covered by the indemnification. In March 2009, the USAF issued a denial of that claim and in June 2009, ULA filed an appeal. If ULA is unsuccessful obtaining additional pricing we may be responsible for some of the shortfall and may record up to $386 million in pre-tax losses associated with the four missions.

**Sea Launch** See the discussion of Sea Launch in Note 7 Liabilities, Commitments and Contingencies.

**Satellites** See the discussions of Boeing Satellite Systems International, Inc. (BSSI) in Note 14 Legal Proceedings and discussion of Satellite insurance risk in Note 7 Liabilities, Commitments and Contingencies.

### Global Services and Support

### Operating Results

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$6,298** | $5,352 | **$2,082** | $1,808 |
| Earnings from operations | **$612** | $616 | **$147** | $164 |
| Operating margins | **9.7%** | 11.5% | **7.1%** | 9.1% |

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| Contractual backlog | **$11,144** | $10,707 |
| Unobligated backlog | **481** | 690 |

### Revenues

GS&S revenues for the nine and three months ended September 30, 2009 increased by $946 million and $274 million, an increase of 18% and 15% compared with the same periods in 2008. The increases for both periods were primarily due to increased volume in the Integrated Logistics (IL) and Training Systems and Services.

### Earnings from Operations

GS&S operating earnings for the nine and three months ended September 30, 2009 decreased by $4 million and $17 million compared with the same periods in 2008. Overall GS&S operating margins for the nine and three months ended September 30, 2009 decreased by 1.8% and 2.0% primarily due a contract adjustment and changes in contract mix.

### Backlog

GS&S total backlog was $11,625 million at September 30, 2009, an increase of 2% from December 31, 2008. The increase was primarily due to significant growth in International Support Systems and Defense and Government Services divisions and partially offset by decreases in the IL and Maintenance, Modifications and Upgrades divisions.

### Boeing Capital Corporation

### Operating Results

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$496** | $535 | **$166** | $171 |
| Earnings from operations | **$112** | $143 | **$39** | $37 |
| Operating margins | **23%** | 27% | **23%** | 22% |

43

### Revenues

BCC segment revenues consist principally of lease income from equipment under operating lease and interest from financing receivables and notes. BCC’s revenues for the nine and three months ended September 30, 2009, decreased $39 million and $5 million when compared with the same periods in 2008 primarily due to lower operating lease income resulting from a smaller portfolio of equipment under operating leases as a result of the return of aircraft and asset dispositions.

### Operating Earnings

BCC’s operating earnings are presented net of interest expense, provision for (recovery of) losses, asset impairment expense, depreciation on leased equipment and other operating expenses. Operating earnings for the nine months ended September 30, 2009 decreased by $31 million due to lower revenues, higher impairment expense and a provision for losses partially offset by lower interest expense. Operating earnings for the three months ended September 30, 2009 increased $2 million due to lower interest expense partially offset by lower revenues, higher impairment expense and a provision for losses.

### Financial Position

The following table presents selected financial data for BCC:

*(Dollars in millions)*

|  | September 30 2009 | December 31 2008 |
| --- | ---: | ---: |
| BCC customer financing and investment portfolio | **$6,114** | $6,023 |
| Valuation allowance as a % of total receivables | **2.0%** | 2.1% |
| Debt | **$3,495** | $3,652 |
| Debt-to-equity ratio | **5.0-to-1** | 5.0-to-1 |

BCC’s customer financing and investment portfolio at September 30, 2009 increased from December 31, 2008 due to the origination of notes receivable partially offset by normal portfolio run-off. At September 30, 2009 and December 31, 2008, BCC had $460 million and $685 million of assets that were held for sale or re-lease, of which $431 million and $305 million had either executed term sheets with deposits or firm contracts to be sold or placed on lease. In March 2009, Mexicana Group committed to lease 25 717 aircraft, including 8 of which were placed on lease and 11 that were held for sale or re-lease at September 30, 2009. The remaining 6 aircraft are currently on lease with Midwest Airlines (Midwest) as of September 30, 2009. In May 2009, BCC agreed to a restructuring of lease terms with Midwest under which Midwest is scheduled to return the remaining aircraft by the end of the current year. We do not expect that the return of these aircraft as a result of this restructuring will have a material effect on our financial position, results of operations or cash flow. Aircraft subject to leases with a carrying value of approximately $346 million are scheduled to be returned off lease in the next 12 months. These aircraft are being remarketed or the leases are being extended and aircraft subject to leases with a carrying value of approximately $179 million had either executed term sheets with deposits or firm contracts at September 30, 2009.

### Restructurings and Restructuring Requests

As of September 30, 2009, BCC had received a number of requests from both domestic and foreign airlines to reduce lease or rental payments or to otherwise restructure obligations. Whether such requests will result in a material adverse impact on our earnings, cash flow or financial position depends on a number of factors including whether the request is granted, the type of aircraft, the collateral value and market rental rates of the returned aircraft.

### Other Segment

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 | Three months ended September 30 2009 | 2008 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$125** | $527 | **$51** | $300 |
| Loss from operations | **$(105)** | $(233) | **$(36)** | $(48) |

Revenues for the nine and three months ended September 30, 2009 decreased by $402 million and $249 million compared with the same periods of 2008 primarily due to the sale of 4 C-17 aircraft in 2008 held under operating lease, three of which were sold in the third quarter of 2008. Other segment losses for the nine and three months ended September 30, 2009 decreased by $128 million and $12 million compared with the same periods of 2008. The decrease for the nine months ended September 30, 2009 was primarily due to recognition of pre-tax expense of $82 million in the third quarter of 2008 to increase the allowance for losses on customer financing receivables related to lower U.S. airline customer credit ratings.

### Liquidity and Capital Resources

### Cash Flow Summary

*(Dollars in millions)*

|  | Nine months ended September 30 2009 | 2008 |
| --- | ---: | ---: |
| Net earnings | **$44** | $2,758 |
| Non-cash items | **1,668** | 1,288 |
| Changes in working capital | **679** | (2,806) |
| Net cash provided by operating activities | **2,391** | 1,240 |
| Net cash (used)/provided by investing activities | **(2,149)** | 173 |
| Net cash provided/(used) by financing activities | **2,545** | (4,243) |
| Effect of exchange rate changes on cash and cash equivalents | **40** | (26) |
| Net increase/(decrease) in cash and cash equivalents | **2,827** | (2,856) |
| Cash and cash equivalents at beginning of year | **3,268** | 7,042 |
| Cash and cash equivalents at end of period | **$6,095** | $4,186 |

**Operating Activities** Net cash provided by operating activities increased by $1,151 million to $2,391 million during the nine months ended September 30, 2009 compared with the nine months ended September 30, 2008. The increase versus the prior period reflects a lower rate of growth in working capital investments and lower pension contributions in 2009. The reclassification of costs related to the first three 787 flight test aircraft from inventory to research and development expense and reach forward losses on the 747 program reduced earnings and working capital balances but did not affect cash flows.

**Investing Activities** Cash used by investing activities totaled $2,149 million during the nine months ended September 30, 2009 compared with $173 million provided during the same period in 2008. In the nine months ended September 30, 2009, we made net contributions of $122 million to investments, while in the corresponding period in 2008, investments provided $2,027 million, representing a change of $2,149 million. On July 30, 2009, we acquired the business, assets and operations of Vought Aircraft

Industries, Inc.’s (Vought) 787 business conducted at North Charleston, SC and paid cash consideration at closing of $592 million, subject to a post-closing adjustment. On July 1, 2009, we paid $448 million to satisfy guarantees of Sea Launch indebtedness.

**Financing Activities** Cash provided by financing activities totaled $2,545 million during the nine months ended September 30, 2009 compared with $4,243 million used during the nine months ended September 30, 2008, primarily due to proceeds from borrowings of $3,772 million in 2009. There were no material debt issuances during the nine months ended September 30, 2008. There was a decrease in common shares repurchased of $2,533 million.

During the nine months ended September 30, 2009, we repaid $256 million of debt, including scheduled repayments of $241 million of debt held at BCC, excluding intercompany debt. The recorded balance of debt as of September 30, 2009 was $11,038 million, of which $973 million was classified as short-term. This includes $3,395 million of debt recorded at BCC, excluding intercompany debt, of which $926 million was classified as short-term.

During the nine months ended September 30, 2009, we repurchased 1,173,152 shares at an average price of $42.94 in our open market share repurchase program and 429,245 shares transferred to us from employees in satisfaction of minimum tax withholding obligations associated with the vesting of restricted stock during the period. During the nine months ended September 30, 2008, we repurchased 34,506,913 shares at an average price of $75.37 in our open market share repurchase program, 1,462,776 shares at an average price of $64.95 as part of the ShareValue Trust distribution, and 3,740 shares in stock swaps.

**Credit Ratings** Our credit ratings are summarized below:

|  | Fitch | Moody’s | Standard & Poor’s |
| --- | --- | --- | --- |
| Long-term: |  |  |  |
| Boeing/BCC | A+ | A2 | A |
| Short-term: |  |  |  |
| Boeing/BCC | F1 | P-1 | A-1 |

On January 29, 2009, Standard & Poor’s (S&P) affirmed Boeing’s and BCC’s A+ credit rating but changed its outlook from stable to negative, citing the challenging commercial aviation environment. On April 10, 2009, S&P placed Boeing’s and BCC’s A+ credit rating on credit watch with negative implications. The rating for short-term borrowing was reaffirmed at A-1. On April 30, 2009, Fitch Ratings affirmed Boeing’s and BCC’s A+ credit rating but changed its outlook from stable to negative. On July 29, 2009, S&P lowered Boeing’s and BCC’s long-term ratings from A+ to A. On October 14, 2009, Moody’s affirmed Boeing’s and BCC’s A2 and P-1 ratings, but changed its outlook from neutral to negative.

**Capital Resources** We believe we have substantial borrowing capability. We and BCC have commercial paper programs that continue to serve as significant potential sources of short-term liquidity. As of September 30, 2009, neither we nor BCC had any outstanding commercial paper issuances. Currently, we have $3,000 million ($1,500 million exclusively available for BCC) of unused borrowing on revolving credit line agreements. We anticipate that these credit lines will primarily serve as backup liquidity to support possible commercial paper borrowings in 2009. BCC has a $5,000 million shelf registration statement that was declared effective on November 12, 2008 under which it may offer debt securities. BCC has not issued any debt securities under this registration statement, and the entire $5,000 million remains available for issuance. In the event BCC elects to issue any debt securities under this registration statement, the availability of such funding will depend on investor demand and market conditions.

On March 9, 2009, we filed a public shelf registration with the U.S. Securities and Exchange Commission for the issuance of an indeterminate amount of debt securities and common stock. On March 13, 2009 and July, 28, 2009, we issued notes totaling $1,850 and $1,950 million under the registration statement. The net proceeds after deducting the discount, underwriting fees and issuance costs were $1,817 and $1,914 million.

We believe our ability to access external capital resources should be sufficient to satisfy existing short-term and long-term commitments and plans. In the event we require additional funding to support strategic business opportunities, commercial aircraft financing commitments, unfavorable resolution of loss contingencies, or other business requirements, we expect to meet increased funding requirements by issuing commercial paper or term debt. At this point in time, our access to liquidity sources has not been materially impacted by the current credit environment, and we do not expect that it will be materially impacted in the near future. There can be no assurance that the cost or availability of future borrowings, if any, under our commercial paper program, in the debt markets or our credit facilities will not be materially impacted by further capital market disruptions.

We had negative Shareholders’ equity as a result of the remeasurement of our pension assets and obligations at September 30, 2009 and December 31, 2008. We do not expect negative Shareholders’ equity to affect our ability to pay dividends or comply with debt covenants. However, additional deterioration in the funded status of our pension plans may result in a requirement to make additional contributions to those plans in future years.

Required pension contributions for U.S. and non-U.S. plans in 2009 are not expected to exceed $50 million. Through September 2009, we made pension contributions of $60 million. We expect to make a discretionary contribution to our pension plans during the fourth quarter of 2009. We are considering whether to make this contribution in cash or shares of Boeing stock. If we decide to contribute common stock the amount of the contribution could exceed our previously announced plan to contribute approximately $500 million to our pension plans in 2009.

As of September 30, 2009, we continue to be in full compliance with all covenants contained in our debt agreements.

### Off-Balance Sheet Arrangements

We are a party to certain off-balance sheet arrangements including certain guarantees. For discussion of these arrangements, see Note 8.

### Contingent Obligations

We have significant contingent obligations that arise in the ordinary course of business, which include the following:

**Legal** Various legal proceedings, claims and investigations are pending against us. Legal contingencies are discussed in Note 14, including our contesting the default termination of the A-12 aircraft, litigation/arbitration involving BSSI and employment and benefits litigation brought by several of our employees.

**Environmental Remediation** We are involved with various environmental remediation activities and have recorded a liability of $732 million at September 30, 2009. For additional information, see Note 7.

**Income Taxes** We have recorded a net liability of $1,662 million at September 30, 2009 for uncertain tax positions. For further discussion of income taxes, see Note 4.

## Controls and procedures

As filed, 1,170 characters.

(a) Disclosure Controls and Procedures.

Our Chief Executive Officer and Chief Financial Officer have evaluated our disclosure controls as of September 30, 2009 and have concluded that these disclosure controls and procedures are effective to ensure that information required to be disclosed by us in the reports that we file or submit under the Securities Exchange Act of 1934 is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms. These disclosure controls and procedures include, without limitation, controls and procedures designed to ensure that information required to be disclosed by us in the reports we file or submit is accumulated and communicated to management, including the Chief Executive Officer and Chief Financial Officer, as appropriate to allow timely decisions regarding required disclosure.

(b) Changes in Internal Control Over Financial Reporting.

There were no changes in our internal control over financial reporting that occurred during the third quarter of 2009 that have materially affected or are reasonably likely to materially affect our internal control over financial reporting.

## Risk factors

As filed, 335 characters.

There have been no material changes in our risk factors from those disclosed in Part I, Item 1A. Risk Factors in our Annual Report on Form 10-K for the year ended December 31, 2008, other than the risk factors updated in Part II, Item 1A, Risk Factors in our Quarterly Report on Form 10-Q for the quarterly period ended March 31, 2009.

Filed Oct 21, 2009.
Source: SEC EDGAR, the filing index for accession 0001193125-09-210918. Last ingested by Listed: Nov 26, 2026, 04:58 ET. No prices; not investment advice.