## Figures reported in this filing

Standardized XBRL line items for the period ended 2011-03-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2011-01-01 to 2011-03-31 | $14.91bn | us-gaap:Revenues |
| Cost of revenue | 3 months, 2011-01-01 to 2011-03-31 | $12.05bn | us-gaap:CostOfRevenue |
| Gross profit | 3 months, 2011-01-01 to 2011-03-31 | $2.86bn | us-gaap:GrossProfit |
| Research and development | 3 months, 2011-01-01 to 2011-03-31 | $1.06bn | us-gaap:ResearchAndDevelopmentExpense |
| Operating income | 3 months, 2011-01-01 to 2011-03-31 | $1.00bn | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months, 2011-01-01 to 2011-03-31 | $295.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2011-01-01 to 2011-03-31 | $586.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2011-01-01 to 2011-03-31 | $0.78 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2011-01-01 to 2011-03-31 | $0.79 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2011-01-01 to 2011-03-31 | 749,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months, 2011-01-01 to 2011-03-31 | −$953.0m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months, 2011-01-01 to 2011-03-31 | $417.0m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 3 months, 2011-01-01 to 2011-03-31 | $309.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2011-03-31 | $5.67bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2011-03-31 | $41.01bn | us-gaap:AssetsCurrent |
| Total assets | at 2011-03-31 | $68.76bn | us-gaap:Assets |
| Current liabilities | at 2011-03-31 | $35.26bn | us-gaap:LiabilitiesCurrent |
| Current portion of debt | at 2011-03-31 | $966.0m | us-gaap:DebtCurrent |
| Shareholders' equity | at 2011-03-31 | $3.91bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 40,044 characters.

### Consolidated Operating Results

The following table summarizes key indicators of consolidated results of operations:

*(Dollars in millions, except per share data)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$14,910** | $15,216 |
| Earnings from operations | **$1,000** | $1,174 |
| Operating margins | **6.7%** | 7.7% |
| Effective income tax rate | **33.4%** | 50.6% |
| Net earnings from continuing operations | **$588** | $519 |
| Diluted earnings per share | **$0.78** | $0.70 |

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$310,731** | $303,955 |
| Unobligated backlog | **18,285** | 16,871 |

### Revenues

The following table summarizes revenues:

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Commercial Airplanes | **$7,118** | $7,468 |
| Boeing Defense, Space & Security | **7,617** | 7,613 |
| Boeing Capital Corporation | **143** | 162 |
| Other segment | **36** | 36 |
| Unallocated items and eliminations | **(4)** | (63) |
| Total | **$14,910** | $15,216 |

Revenues for the three months ended March 31, 2011 decreased by $306 million or 2% compared with the same period in 2010. Commercial Airplanes revenues decreased by $350 million or 5%, due to lower new airplane deliveries in the first quarter of 2011 compared with the same period in the prior year, partially offset by increases in the commercial aviation services business. Boeing Defense, Space & Security (BDS) revenues increased by $4 million due to higher revenues in the Boeing Military Aircraft (BMA) segment offset by lower revenues in the Global Services & Support (GS&S) segment.

### Earnings From Operations

The following table summarizes earnings from operations:

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Commercial Airplanes | **$509** | $679 |
| Boeing Defense, Space & Security | **671** | 664 |
| Boeing Capital Corporation | **52** | 46 |
| Other segment | **(22)** | (50) |
| Unallocated items and eliminations | **(210)** | (165) |
| Total | **$1,000** | $1,174 |

26

Operating earnings for the three months ended March 31, 2011 decreased by $174 million compared with the same period in 2010. Commercial Airplanes earnings decreased by $170 million primarily due to lower new airplane deliveries. BDS earnings increased by $7 million with higher earnings in the BMA segment offset by lower earnings in the N&SS and GS&S segments. Unallocated items and eliminations changed by $45 million reflecting higher pension costs which were partially offset by deferred compensation and share based plan expense.

The most significant expense items not allocated to segments are shown in the following table:

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Share-based plans | **$(22)** | $(47) |
| Deferred compensation | **(50)** | (81) |
| Pension | **(95)** | 21 |
| Postretirement | **(19)** | (11) |
| Eliminations and other | **(24)** | (47) |
| Total | **$(210)** | $(165) |

Unallocated pension costs for the three months ended March 31, 2011 increased by $116 million compared with the same period in 2010 reflecting higher amortization of prior actuarial losses, lower discount rates and C-17 related pension curtailment charges.

Unallocated pension and other postretirement expense represents the difference between costs recognized under Generally Accepted Accounting Principles in the United States of America in the condensed consolidated financial statements and federal cost accounting standards required to be utilized by our business segments for U.S. government contracting purposes. We recorded net periodic benefit cost related to pensions and other postretirement benefits of $764 million and $469 million for the three months ended March 31, 2011 and 2010. Not all net periodic benefit cost is recognized in earnings in the period incurred. A portion of net periodic benefit cost is allocated to production as product cost and a portion remains in inventory at the end of the reporting period. Earnings from operations included the following net periodic benefit cost allocated to business segments and Unallocated items and eliminations:

*(Dollars in millions)*

| Three months ended March 31, | Pension 2011 | 2010 | Other Postretirement Benefits 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Allocated to business segments | **$(431)** | $(305) | **$(143)** | $(112) |
| Unallocated items and eliminations | **(95)** | 21 | **(19)** | (11) |
| Total | **$(526)** | $(284) | **$(162)** | $(123) |

27

### Other Earnings Items

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| **Earnings from operations** | **$1,000** | $1,174 |
| Other income/(expense), net | **13** | (2) |
| Interest and debt expense | **(130)** | (122) |
| **Earnings before income taxes** | **883** | 1,050 |
| Income tax expense | **(295)** | (531) |
| **Net earnings from continuing operations** | **$588** | $519 |

The effective tax rates were 33.4% and 50.6% for the three months ended March 31, 2011 and 2010. The decrease in the effective tax rate compared with the same period of the prior year was primarily due to an income tax charge of $150 million recorded during the first quarter of 2010 as a result of the Patient Protection and Affordable Care Act, as modified by the Health Care and Education Reconciliation Act of 2010. The decrease was also due to U.S. research and development tax credit benefits that exist in 2011, but did not exist in the first quarter of 2010. In December 2010, the research and development tax credit was retroactively renewed for 2010 and extended through December 31, 2011.

For additional discussion related to Income Taxes, see Note 3 to our Condensed Consolidated Financial Statements.

Contractual backlog of unfilled orders excludes purchase options, announced orders for which definitive contracts have not been executed and unobligated U.S. and non-U.S. government contract funding. The increase in contractual backlog during the three months ended March 31, 2011 compared with December 31, 2010 was primarily due to Commercial Airplanes orders in excess of revenues.

Unobligated backlog includes U.S. and foreign government definitive contracts for which funding has not been authorized. The increase in unobligated backlog during the three months ended March 31, 2011 is due to the U.S. Air Force (USAF) contract for the KC-46A Tanker partially offset by funding of existing multi-year contracts including the F/A-18 and Brigade Combat Team Modernization (BCTM) programs.

### Additional Considerations

**KC-46A Tanker** On February 24, 2011, we were awarded a contract from the USAF to design, develop, manufacture and deliver 4 next generation aerial refueling tankers. The KC-46A Tanker will be a derivative of our 767 commercial aircraft. This initial contract is a fixed-price incentive firm contract, valued at $4.4 billion and involves highly complex designs. Changes to our estimated cost to perform the work could result in a material charge. This contract contains production options. If all options under the contract are exercised, we expect to deliver 179 aircraft for a total expected contract value of approximately $30 billion. For segment reporting purposes, backlog, revenues and costs will be recorded in the Commercial Airplanes and BMA segments.

### Segment Results of Operations

### Commercial Airplanes

### Business Environment and Trends

**Airline Industry Environment** Recent events, primarily political turmoil in the Middle East and North Africa and devastation from Japan’s earthquake, have increased downside risk to the 2011 global economic and airline industry outlooks. In addition to significant disruptions to airline operations in the affected regions, airlines around the world are being negatively impacted by the resulting higher oil prices. Higher oil prices increase airline fuel expenses and put downward pressure on air travel demand due to impacts on economic growth and airfares. As a result, uncertainty about the near term airline industry financial outlook has increased.

**Supply Chain** Some of our suppliers have operations in Japan. We have not experienced any interruptions to aircraft production and delivery due to parts shortages or other impacts related to the Japanese earthquake. We are monitoring the situation closely.

### Operating Results

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$7,118** | $7,468 |
| Earnings from operations | **$509** | $679 |
| Operating margins | **7.2%** | 9.1% |

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$260,858** | $255,591 |
| Unobligated backlog | **2,436** | 49 |

### Revenues

Year over year changes in Revenue are shown in the following table:

*(Dollars in millions)*

|  | March 31, 2011 vs. March 31, 2010 |
| --- | ---: |
| New airplane sales | $(553) |
| Commercial aviation services | 205 |
| Other | (2) |
| Total | $(350) |

Revenues for the three months ended March 31, 2011 decreased by $350 million or 5% compared with the same period of 2010. This decrease in new airplane revenues is primarily due to lower deliveries on the 777 program reflecting the current production rate of 5 aircraft per month which compares with a production rate of 7 aircraft per month in last year’s quarter. The increase in revenues from commercial aviation services was driven by increased sales of spares.

Commercial jet aircraft deliveries, including intercompany deliveries, were as follows:

|  |  |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| **Program** | **737** | **747** | **767** | **777** | **Total** |
| Deliveries during the first quarter of 2011 | 87 |  | 4 | 13 | 104 |
| Deliveries during the first quarter of 2010 | 86 |  | 3 | 19 | 108 |
| Cumulative deliveries as of 3/31/2011 | 3,593 | 1,418 | 998 | 923 |  |
| Cumulative deliveries as of 12/31/2010 | 3,506 | 1,418 | 994 | 910 |  |

### Earnings From Operations

Earnings from operations for the three months ended March 31, 2011 decreased by $170 million and operating margins decreased by 1.9 percentage points to 7.2% compared with the same period of 2010. This decrease was primarily due to lower new airplane deliveries which reduced 2011 earnings by $152 million. Higher research and development cost of $88 million, reflecting planned spending on our development programs was mostly offset by an increase in earnings from commercial aviation services.

The increase in contractual backlog during the three months ended March 31, 2011 was due to orders in excess of revenues and changes in projected revenue escalation, partially reduced by cancellations of orders. A number of our customers may have contractual remedies that may be implicated by program delays. We continue to address customer claims and requests for other contractual relief as they arise. However, once orders are included in firm backlog, orders remain in backlog until canceled or fulfilled, although the value of orders is adjusted as changes to price and schedule are agreed to with customers. The increase in unobligated backlog represents Commercial Airplanes’ share of the USAF contract for the KC-46A Tanker.

### Accounting Quantity

The following table provides details of the accounting quantities and firm orders by program. Cumulative firm orders represent the cumulative number of commercial jet aircraft deliveries plus undelivered firm orders.

|  | Program |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| **As of 3/31/2011** | **737** | **747** | **767** | **777** | **787** |
| Program accounting quantities | **5,600** | **1,524** | **1,048** | **1,200** | **\*** |
| Undelivered units under firm orders | **2,162** | **109** | **53** | **286** | **835** |
| Cumulative firm orders | **5,755** | **1,527** | **1,051** | **1,209** | **835** |
|  | Program |  |  |  |  |
| As of 12/31/2010 | 737 | 747 | 767 | 777 | 787 |
| Program accounting quantities | 5,000 | 1,524 | 1,048 | 1,150 | \* |
| Undelivered units under firm orders | 2,186 | 107 | 50 | 253 | 847 |
| Cumulative firm orders | 5,692 | 1,525 | 1,044 | 1,163 | 847 |

\* A final determination of the initial accounting quantity for the 787 program will be made in the quarter of first airplane delivery, targeted for the third quarter of 2011.

**737 Program** The accounting quantity for the 737 program increased by 600 units during the three months ended March 31, 2011 reflecting the current backlog and continued demand for delivery positions as well as previously announced production rate increases from 31.5 aircraft per month in 2011 to 35 aircraft per month in 2012 and 38 aircraft per month beginning in 2013.

**747 Program** There was no change to the accounting quantity for the 747 program during the three months ended March 31, 2011. Flight testing of the 747-8 Freighter continued with five test aircraft and we continue to expect certification and first delivery in the middle of 2011. We are currently producing 747-8 airplanes and until completion of our flight test program, there is risk that additional items may be identified that require further modifications or other changes to those aircraft we have produced. On March 19, 2010, we announced that we will accelerate, from mid-2013 to mid-2012, a planned production rate increase from 1.5 to 2 airplanes per month. First flight of the 747-8 Intercontinental passenger derivative occurred on March 20, 2011. Certification and first delivery of the Intercontinental is expected in the fourth quarter of 2011. Schedule and other risks inherent in the demanding flight test and certification phases of program development remain.

**767 Program** There was no change in the accounting quantity for the 767 program during the three months ended March 31, 2011.

**777 Program** The accounting quantity for the 777 program increased by 50 units during the three months ended March 31, 2011 due to the program’s normal progress of obtaining additional orders and delivering aircraft. We are continuing to work toward a planned production rate increase from 5 to 7 airplanes per month beginning in June 2011.

**787 Program** Flight testing continues with six flight test aircraft. A limited amount of testing is also being performed on two production-configured airplanes prior to first delivery. On January 18, 2011, we announced that the expected date of first delivery had been moved to the third quarter of 2011 due to the flight testing and certification delays.

A number of engineering and other design changes have been identified in conjunction with the flight test program that are being incorporated into our production system and on aircraft already completed. As we continue to produce 787 airplanes throughout the flight test program, there is risk that additional items will be identified requiring further modifications or other changes to airplanes we have already produced or are near completion.

We continue to monitor and address challenges associated with assembly of airplanes including management of our extended global supply chain, incorporation of design changes into aircraft in various stages of assembly, completion and integration of traveled work as well as weight and systems integration. For example, during 2010 we delayed some 787 component deliveries to reduce out–of-sequence work moving into final assembly at our Everett factory and improve supply chain efficiency.

We are working toward planned increases in 787 production rates as well as the timely introduction of the 787-9 derivative. Such efforts include the construction of a second assembly line in North Charleston, South Carolina and establishing transitional surge capacity at our Everett, Washington location. On July 1, 2010, we completed firm configuration of the 787-9 airplane and first delivery of that model is scheduled for late 2013.

We continue to work with our customers and suppliers to assess the specific impacts of schedule changes, including delivery delays and supplier assertions. Efforts continue to ensure we remain focused on satisfying customer mission and performance needs in light of the anticipated weight of their respective aircraft. A number of our customers have contractual remedies for schedule delays and/or performance. We continue to address customer and supplier claims and requests for other contractual relief as brought forth.

During 2009, we concluded that the first three flight-test 787 aircraft could not be sold as previously anticipated due to the inordinate amount of rework and unique and extensive modifications made to those aircraft. As a result, costs associated with these airplanes were included in research and development expense. We believe that the other three 787 flight test aircraft are commercially saleable and we continue to include costs related to those airplanes in program inventory at March 31, 2011. If we determine that one or more of the other aircraft cannot be sold, we may incur additional charges.

Our current assessment is that the program is not in a reach-forward loss position, however the cumulative impacts of the production challenges, schedule delays and customer and supplier impacts have created significant pressure on program profitability and we expect to record zero margin on our initial deliveries. We continue to implement mitigation plans and cost-reduction efforts to address this pressure.

### Additional Considerations

The 787 and 747-8 programs highlight the risks inherent in new airplane programs and new derivative airplanes, particularly as the 787-8, 747-8 Freighter and the 747-8 Intercontinental continue the demanding flight test and certification phases of program development. Development also continues on the 787-9. Costs related to development of new programs and derivative airplanes are expensed as incurred. Costs to produce new aircraft are included in inventory and accounted for using program accounting. Airplane programs have risk for reach-forward losses if our estimated production costs exceed our estimated program revenues for the accounting quantity. Generally commercial airplanes are sold on a firm fixed-price basis with an indexed price escalation clause and are often sold several years before scheduled delivery. Each customer purchase agreement contains an escalation clause to account for the effects of economic fluctuations over the period of time from airplane sale to airplane delivery. A price escalation formula based on pre-defined factors is used to determine the final price of the airplane at the time of customer delivery. While firm fixed-price contracts allow us to benefit from cost savings, they also expose us to the risk of cost overruns. Many new airplanes and derivatives have highly complex designs, utilize exotic materials and require extensive coordination and integration with supplier partners. As technical or quality issues arise, such as issues experienced on the 787 and 747-8 programs, we may experience schedule delays and higher costs to complete new programs and derivative aircraft. Additionally, price escalation factors may also impact margins by reducing the estimated price of airplanes delivered in the future. There are other factors that could also result in lower margins or a material charge if a program has or is determined to have reach-forward losses. These include: changes to the program accounting quantity, customer and model mix, production costs and rates, capital expenditures and other costs associated with increasing or adding new production capacity, learning curve, anticipated cost reductions, flight test and certification schedules, costs, schedule and demand for derivative airplanes and status of customer claims, supplier assertions and other contractual negotiations. While we believe the cost and revenue estimates incorporated in the financial statements are appropriate, the technical complexity of these programs creates financial risk as additional completion costs may become necessary or scheduled delivery dates could be extended, which could trigger termination provisions, order cancellations or other financially significant exposure.

### Boeing Defense, Space & Security

### Operating Results

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$7,617** | $7,613 |
| Earnings from operations | **$671** | $664 |
| Operating margins | **8.8%** | 8.7% |

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$49,873** | $48,364 |
| Unobligated backlog | **15,849** | 16,822 |

### Revenues

BDS revenues for the three months ended March 31, 2011 increased by $4 million compared with the same period in 2010. The increase was due to higher revenues in the BMA segment offset by lower revenues in the GS&S segment.

### Earnings From Operations

BDS operating earnings for the three months ended March 31, 2011 increased $7 million and operating margins increased 0.1% to 8.8% compared with the same period in 2010. Higher earnings in the BMA segment more than offset lower earnings in the N&SS and GS&S segments.

### Backlog

BDS total backlog increased 1% in 2011, from $65,186 million to $65,722 million, primarily due to BDS’s share of the USAF contract for the KC-46A Tanker and a contract award for P-8A low rate initial production. The increase was partially offset by current year deliveries and sales on multi-year contracts awarded in prior years.

For further details on the changes between periods, refer to the discussions of the individual segments below.

### Additional Considerations

Our business includes a variety of development programs which have complex design and technical challenges. Many of these programs have cost-type contracting arrangements. In these cases the associated financial risks are primarily in lower profit rates or program cancellation if milestones and technical progress are not accomplished. Examples of these programs include Family of Beyond Line-of-Sight Terminals, BCTM, Ground-based Midcourse Defense (GMD), P-8A Poseidon and Proprietary programs.

Some of our development programs are contracted on a fixed-price basis. Many of these programs have highly complex designs. As technical or quality issues arise, we may experience schedule delays and cost impacts, which could increase our estimated cost to perform the work or reduce our estimated price, either of which could result in a material charge. These programs are ongoing, and while we believe the cost and fee estimates incorporated in the financial statements are appropriate, the technical complexity of these programs creates financial risk as additional completion costs may become necessary or scheduled delivery dates could be extended, which could trigger termination provisions, the loss of satellite in-orbit incentive payments, or other financially significant exposure. These programs have risk for reach-forward losses if our estimated costs exceed our estimated contract revenues. Examples of our fixed-price development programs include Airborne Early Warning and Control (AEW&C), P-8I, KC-46A Tanker, KC-767 International Tanker and commercial and military satellites.

### Boeing Military Aircraft

### Operating Results

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$3,392** | $3,241 |
| Earnings from operations | **$369** | $270 |
| Operating margins | **10.9%** | 8.3% |

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$26,510** | $25,094 |
| Unobligated backlog | **7,905** | 8,297 |

### Revenues

BMA revenues for the three months ended March 31, 2011 increased by $151 million or 5% compared with the same period in 2010, primarily due to higher deliveries.

Deliveries of units for new-build production aircraft, excluding remanufactures and modifications, were as follows:

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| F/A-18 Models | **13** | 13 |
| F-15E Eagle | **4** | 3 |
| C-17 Globemaster | **3** | 3 |
| CH-47 Chinook | **7** | 2 |
| KC-767 International Tanker | **1** |  |
| AH-64 Apache |  | 4 |
| Total new-build production aircraft | **28** | 25 |

### Earnings From Operations

BMA operating earnings for the three months ended March 31, 2011 increased by $99 million or 37% compared with the same period in 2010, primarily due to higher earnings on the Global Strike programs and lower research and development costs.

BMA total backlog was $34,415 million at March 31, 2011, an increase of 3% from December 31, 2010, primarily due to BDS’s share of the USAF contract for the KC-46A Tanker and a contract award for P-8A low rate initial production. The increase was partially offset by current year deliveries and sales on multi-year contracts awarded in prior years.

### Additional Considerations

**AEW&C** The AEW&C development program, also known as Wedgetail in Australia, Peace Eagle in Turkey and Peace Eye in the Republic of Korea, consists of 737-700 aircraft outfitted with a variety of command and control and advanced radar systems, some of which have never been installed on an airplane before. Four Wedgetail aircraft were delivered to Australia with initial customer acceptance in 2010 and the final two Wedgetail aircraft are scheduled for delivery in 2011 with initial customer acceptance in 2011. Final customer acceptance for all six Wedgetail aircraft is scheduled to be completed during the first quarter of 2012. In January 2011, the Peace Eagle program began the formal test phase. The Peace Eye program entered its formal test phase in April 2011. These are advanced and complex fixed-price development programs involving technical challenges at the individual subsystem level and in the overall integration of these subsystems into a reliable and effective operational capability. We believe that the cost and revenue estimates incorporated in the financial statements are appropriate; however, the technical complexity of the programs creates financial risk as additional completion costs may be necessary or scheduled delivery dates could be delayed either of which could result in lower margins or additional material charges.

**KC-767 International Tanker** We delivered the first of four aircraft to the Italian Air Force in December 2010 and the second in March 2011. We believe the revenue and cost estimates incorporated in the financial statements are appropriate, however, the technical complexity of the program creates financial risk as additional completion and development costs may be necessary or remaining scheduled delivery dates could be delayed either of which could result in additional material changes.

**C-17 and F-15** See the discussion of the C-17 and F-15 programs in Note 8 to our Condensed Consolidated Financial Statements.

### Network & Space Systems

### Operating Results

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$2,349** | $2,323 |
| Earnings from operations | **$143** | $174 |
| Operating margins | **6.1%** | 7.5% |

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$9,479** | $9,586 |
| Unobligated backlog | **7,719** | 8,435 |

### Revenues

N&SS revenues for the three months ended March 31, 2011 increased by $26 million or 1% compared with the same period in 2010. The increase is due to sales of Delta inventory to United Launch Alliance (ULA) offset by lower revenues on several satellite programs.

### Earnings From Operations

N&SS operating earnings for the three months ended March 31, 2011 decreased by $31 million or 18% compared with the same period in 2010. The decrease in earnings is primarily due to lower earnings on several satellite programs.

N&SS total backlog was $17,198 million at March 31, 2011 a decrease of 5% from December 31, 2010 primarily due to revenues recognized on multi-year contracts awarded in prior years including the BCTM and GMD programs.

### Additional Considerations

**United Launch Alliance** On December 1, 2006, we and Lockheed Martin Corporation (Lockheed) created a 50/50 joint venture named United Launch Alliance L.L.C. ULA combines the production, engineering, test and launch operations associated with U.S. government launches of Boeing Delta and Lockheed Atlas rockets. See the discussion of Indemnifications to ULA and Financing Commitments in Note 8 and 9 of our Condensed Consolidated Financial Statements.

**Sea Launch** See the discussion of the Sea Launch receivables in Note 7 to our Condensed Consolidated Financial Statements.

**Satellites** See the discussions of Boeing Satellite Systems International, Inc. in Note 14 to our Condensed Consolidated Financial Statements.

### Global Services & Support

### Operating Results

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$1,876** | $2,049 |
| Earnings from operations | **$159** | $220 |
| Operating margins | **8.5%** | 10.7% |

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$13,884** | $13,684 |
| Unobligated backlog | **225** | 90 |

### Revenues

GS&S revenues for the three months ended March 31, 2011 decreased by $173 million or 8% compared with the same period in 2010. The decrease was primarily due to the conclusion of our KC-10 support program in 2010 and lower volume in several Integrated Logistics and Training Systems & Services programs.

### Earnings From Operations

GS&S operating earnings for the three months ended March 31, 2011 decreased $61 million compared with the same period in 2010 due to lower segment revenues and unfavorable performance adjustments on Maintenance, Modifications and Upgrades programs.

GS&S total backlog was $14,109 million at March 31, 2011, an increase of 2% from December 31, 2010, primarily due to a contract award for P-8A support and training.

### Boeing Capital Corporation

### Operating Results

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$143** | $162 |
| Earnings from operations | **$52** | $46 |
| Operating margins | **36%** | 28% |

### Revenues

Boeing Capital Corporation (BCC) segment revenues consist principally of lease income from equipment under operating lease and interest from financing receivables and notes. BCC’s revenues for the three months ended March 31, 2011, decreased $19 million compared with the same period in 2010 primarily due to lower interest income on notes receivable resulting from a lower weighted average notes receivable balance and lower operating lease income from a smaller portfolio of equipment under operating leases.

### Earnings From Operations

BCC’s operating earnings are presented net of interest expense, provision for losses, asset impairment expense, depreciation on leased equipment and other operating expenses. Operating earnings for the three months ended March 31, 2011 increased by $6 million compared with the same period in 2010 primarily due to lower interest expense, lower depreciation expense and a recovery of losses partially offset by lower revenues.

### Financial Position

The following table presents selected financial data for BCC:

*(Dollars in millions)*

|  | March 31 2011 | December 31 2010 |
| --- | ---: | ---: |
| BCC customer financing and investment portfolio | **$4,540** | $4,694 |
| Valuation allowance as a % of total receivables | **3.7%** | 3.8% |
| Debt | **$2,649** | $3,446 |
| Debt-to-equity ratio | **5.0-to-1** | 5.0-to-1 |

BCC’s customer financing and investment portfolio at March 31, 2011 decreased from December 31, 2010 due to normal portfolio run-off and asset sales. At March 31, 2011 and December 31, 2010, BCC had $556 million and $583 million of assets that were held for sale or re-lease, of which $8 million and $28 million had either executed term sheets with deposits or firm contracts to be sold or placed on lease. Additionally, aircraft subject to leases with a carrying value of approximately $248 million are scheduled to be returned off lease in the next 12 months. These aircraft are being remarketed or the leases are being extended and approximately $161 million of such aircraft had either executed term sheets with deposits or firm contracts at March 31, 2011.

BCC enters into certain transactions with the Other segment in the form of intercompany guarantees and other subsidies that mitigate the effects of certain credit quality or asset impairment issues on the BCC segment.

### Restructurings and Restructuring Requests

From time to time, certain customers have requested a restructuring of their transactions with BCC. As of March 31, 2011, BCC has not reached agreement on any restructuring requests that would have a material adverse effect on its earnings, cash flows and/or financial position.

### Southwest/AirTran Merger

On September 26, 2010, Southwest Airlines Co. (Southwest) and AirTran Holdings, Inc. (AirTran) entered into an Agreement and Plan of Merger, whereby Southwest will acquire, subject to certain conditions, all of the outstanding common stock of AirTran. AirTran, together with its subsidiaries, represents approximately 27% of our gross customer financing portfolio carrying value, consisting principally of 717 aircraft. AirTran is the largest customer in terms of BCC’s segment revenue and customer financing portfolio carrying value.

### Other Segment

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Revenues | **$36** | $36 |
| Loss from operations | **(22)** | (50) |

Other segment losses for three months ended March 31, 2011 decreased by $28 million compared with the same period in 2010 primarily due to lower expenses recognized in the Other segment relating to environmental remediation.

### Liquidity and Capital Resources

### Cash Flow Summary

*(Dollars in millions)*

|  | Three months ended March 31 2011 | 2010 |
| --- | ---: | ---: |
| Net earnings | **$586** | $519 |
| Non-cash items | **524** | 529 |
| Changes in working capital | **(2,063)** | (1,333) |
| Net cash used by operating activities | **(953)** | (285) |
| Net cash provided/(used) by investing activities | **2,707** | (4,041) |
| Net cash used by financing activities | **(1,468)** | (347) |
| Effect of exchange rate changes on cash and cash equivalents | **25** | (25) |
| Net increase/(decrease) in cash and cash equivalents | **311** | (4,698) |
| Cash and cash equivalents at beginning of year | **5,359** | 9,215 |
| Cash and cash equivalents at end of period | **$5,670** | $4,517 |

38

**Operating Activities** Net cash used by operating activities of $953 million during the three months ended March 31, 2011 increased by $668 million compared with the same period in 2010 primarily due to the continued growth in inventory as we prepare for first deliveries and production ramp up of the 787 and 747-8 airplanes.

**Investing Activities** Cash provided by investing activities totaled $2,707 million during the three months ended March 31, 2011 compared with $4,041 million used during the same period in 2010, largely due to changes in investments which primarily consist of time deposits. Net proceeds from investments were $3,057 million in 2011 compared with net contributions to investments of $3,834 million in 2010. We expect capital spending in 2011 to be higher than 2010 due to the ongoing construction of a 787 final assembly line in North Charleston, South Carolina, investment to support commercial airplane production rate increases and ongoing capital improvements.

**Financing Activities** Cash used by financing activities totaled $1,468 million during the three months ended March 31, 2011 compared with $347 million used during the three months ended March 31, 2010.

During the three months ended March 31, 2011, we repaid $812 million of debt, including scheduled repayments of $786 million of debt held at BCC. The recorded balance of debt as of March 31, 2011 was $11,689 million, of which $966 million was classified as short-term. This includes $2,649 million of debt recorded at BCC, of which $789 million was classified as short-term.

During the three months ended March 31, 2011, we did not repurchase any shares through our open market share repurchase program and had 226,439 shares transferred to us from employees for tax withholding.

**Capital Resources** We have substantial borrowing capacity. Any future borrowings may affect our credit ratings and are subject to various debt covenants as described below. We and BCC have commercial paper programs that continue to serve as significant potential sources of short-term liquidity. As of March 31, 2011, neither we nor BCC had any commercial paper borrowings outstanding. Currently, we have $4,376 million ($1,500 million exclusively available for BCC) of unused borrowing on revolving credit line agreements. We anticipate that these credit lines will primarily serve as backup liquidity to support possible commercial paper borrowings.

In the event we require additional funding to support strategic business opportunities, our commercial aircraft financing commitments, unfavorable resolution of litigation or other loss contingencies, or other business requirements, we expect to meet increased funding requirements by issuing commercial paper or term debt. We believe our ability to access external capital resources should be sufficient to satisfy existing short-term and long-term commitments and plans, and also to provide adequate financial flexibility to take advantage of potential strategic business opportunities should they arise within the next year. However, there can be no assurance of the cost or availability of future borrowings, if any, under our commercial paper program, in the debt markets or our credit facilities.

As of March 31, 2011, we were in compliance with the covenants for our debt and credit facilities. The most restrictive covenants include a limitation on mortgage debt and sale and leaseback transactions as a percentage of consolidated net tangible assets (as defined in the credit agreements), and a limitation on consolidated debt as a percentage of total capital (as defined). When considering debt covenants, we continue to have substantial borrowing capacity.

### Off-Balance Sheet Arrangements

We are a party to certain off-balance sheet arrangements including certain guarantees. For discussion of these arrangements, see Note 9 to our Condensed Consolidated Financial Statements.

### Contingent Obligations

We have significant contingent obligations that arise in the ordinary course of business, which include the following:

**Legal** Various legal proceedings, claims and investigations are pending against us. Legal contingencies are discussed in Note 14 to our Condensed Consolidated Financial Statements, including our contesting the default termination of the A-12 aircraft, certain employment and benefits litigation, litigation/arbitration involving BSSI programs and civil securities litigation relating to disclosures concerning the 787 program.

**Environmental Remediation** We are involved with various environmental remediation activities and have recorded a liability of $712 million at March 31, 2011. For additional information, see Note 8 to our Condensed Consolidated Financial Statements.

**Income Taxes** We have recorded a net liability of $1,195 million at March 31, 2011 for uncertain tax positions. For further discussion of income taxes, see Note 3 to our Condensed Consolidated Financial Statements.

## Controls and procedures

As filed, 1,014 characters.

(a) Disclosure Controls and Procedures.

Our Chief Executive Officer and Chief Financial Officer have evaluated our disclosure controls and procedures as of March 31, 2011 and have concluded that these disclosure controls and procedures are effective to ensure that information required to be disclosed by us in the reports that we file or submit under the Securities Exchange Act of 1934, as amended, is recorded, processed, summarized and reported within the time periods specified in the Commission’s rules and forms and is accumulated and communicated to our management, including the Chief Executive Officer and Chief Financial Officer, as appropriate to allow timely decisions regarding required disclosure.

(b) Changes in Internal Control Over Financial Reporting.

There were no changes in our internal control over financial reporting that occurred during the first quarter of 2011 that have materially affected or are reasonably likely to materially affect our internal control over financial reporting.

## Risk factors

As filed, 181 characters.

There have been no material changes in our risk factors from those disclosed in Part I, Item 1A. Risk Factors in our Annual Report on Form 10-K for the year ended December 31, 2010.

Filed Apr 27, 2011.
Source: SEC EDGAR, the filing index for accession 0001193125-11-111215. Last ingested by Listed: Nov 14, 2026, 13:59 ET. No prices; not investment advice.