## Figures reported in this filing

Standardized XBRL line items for the period ended 2011-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2011-07-01 to 2011-09-30 | $17.73bn | us-gaap:Revenues |
| Revenue | 9 months, 2011-01-01 to 2011-09-30 | $49.18bn | us-gaap:Revenues |
| Cost of revenue | 3 months, 2011-07-01 to 2011-09-30 | $14.36bn | us-gaap:CostOfRevenue |
| Cost of revenue | 9 months, 2011-01-01 to 2011-09-30 | $39.61bn | us-gaap:CostOfRevenue |
| Gross profit | 3 months, 2011-07-01 to 2011-09-30 | $3.37bn | us-gaap:GrossProfit |
| Gross profit | 9 months, 2011-01-01 to 2011-09-30 | $9.57bn | us-gaap:GrossProfit |
| Research and development | 3 months, 2011-07-01 to 2011-09-30 | $901.0m | us-gaap:ResearchAndDevelopmentExpense |
| Research and development | 9 months, 2011-01-01 to 2011-09-30 | $3.00bn | us-gaap:ResearchAndDevelopmentExpense |
| Operating income | 3 months, 2011-07-01 to 2011-09-30 | $1.71bn | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2011-01-01 to 2011-09-30 | $4.25bn | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months, 2011-07-01 to 2011-09-30 | $548.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2011-01-01 to 2011-09-30 | $1.32bn | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2011-07-01 to 2011-09-30 | $1.10bn | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2011-01-01 to 2011-09-30 | $2.63bn | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2011-07-01 to 2011-09-30 | $1.46 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2011-01-01 to 2011-09-30 | $3.49 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2011-07-01 to 2011-09-30 | $1.47 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2011-01-01 to 2011-09-30 | $3.52 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2011-07-01 to 2011-09-30 | 753,900,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2011-01-01 to 2011-09-30 | 751,800,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2011-01-01 to 2011-09-30 | $1.09bn | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2011-01-01 to 2011-09-30 | $1.14bn | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2011-01-01 to 2011-09-30 | $932.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | at 2011-09-30 | $5.95bn | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2011-09-30 | $46.35bn | us-gaap:AssetsCurrent |
| Total assets | at 2011-09-30 | $74.16bn | us-gaap:Assets |
| Current liabilities | at 2011-09-30 | $37.59bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2011-09-30 | $68.10bn | us-gaap:Liabilities |
| Current portion of debt | at 2011-09-30 | $1.60bn | us-gaap:DebtCurrent |
| Shareholders' equity | at 2011-09-30 | $5.97bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 50,090 characters.

### Consolidated Operating Results

The following table summarizes key indicators of consolidated results of operations:

*(Dollars in millions, except per share data)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$49,180** | $47,756 | **$17,727** | $16,967 |
| Earnings from operations | **$4,247** | $3,868 | **$1,714** | $1,387 |
| Operating margins | **8.6%** | 8.1% | **9.7%** | 8.2% |
| Effective income tax rate | **33.6%** | 38.8% | **33.4%** | 32.7% |
| Net earnings from continuing operations | **$2,624** | $2,145 | **$1,094** | $837 |
| Diluted earnings per share | **$3.49** | $2.89 | **$1.46** | $1.12 |

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$316,859** | $303,955 |
| Unobligated backlog | **14,727** | 16,871 |

### Revenues

The following table summarizes revenues:

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Commercial Airplanes | **$25,476** | $23,650 | **$9,515** | $8,749 |
| Boeing Defense, Space & Security | **23,505** | 23,778 | **8,200** | 8,182 |
| Boeing Capital Corporation | **416** | 494 | **126** | 170 |
| Other segment | **107** | 107 | **33** | 27 |
| Unallocated items and eliminations | **(324)** | (273) | **(147)** | (161) |
| Total | **$49,180** | $47,756 | **$17,727** | $16,967 |

Revenues for the nine and three months ended September 30, 2011 increased by $1,424 million and $760 million or 3% and 4% compared with the same periods in 2010. Commercial Airplanes revenues increased by $1,826 million and $766 million or 8% and 9% primarily due to higher new airplane and commercial aviation services sales. Boeing Defense, Space & Security (BDS) revenues decreased by $273 million for the nine months and increased by $18 million for the three months compared with the same periods in the prior year. The nine month decrease was primarily due to lower revenues in the Network & Space Systems (N&SS) and Global Services & Support (GS&S) segments, partially offset by higher revenues in the Boeing Military Aircraft (BMA) segment. The three month increase was due to higher BMA revenues partially offset by lower revenues in the N&SS and GS&S segments.

### Earnings From Operations

The following table summarizes earnings from operations:

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Commercial Airplanes | **$2,514** | $2,379 | **$1,085** | $1,017 |
| Boeing Defense, Space & Security | **2,293** | 2,059 | **824** | 684 |
| Boeing Capital Corporation | **133** | 146 | **19** | 45 |
| Other segment | **11** | (254) | **92** | (132) |
| Unallocated items and eliminations | **(704)** | (462) | **(306)** | (227) |
| Total | **$4,247** | $3,868 | **$1,714** | $1,387 |

Earnings from operations for the nine and three months ended September 30, 2011 increased by $379 million and $327 million compared with the same periods in 2010. Commercial Airplanes earnings from operations for the nine months ended September 30, 2011 increased by $135 million. This increase was primarily due to earnings from higher revenues on new airplane deliveries and commercial aviation services, partially offset by increases in research and development. Commercial Airplanes earnings from operations for the three months ended September 30, 2011 increased by $68 million. The increase was primarily due to earnings from higher revenues on new airplane deliveries and a reduction in research and development costs related to certifications of the 747-8 Freighter and 787-8, partially offset by increases in period costs associated with business growth. BDS earnings increased by $234 million and $140 million compared with the same periods in 2010. The increase for the nine months was primarily due to higher earnings in the BMA and N&SS segments. The increase for the three months was due to higher earnings in all three BDS segments. Unallocated items and eliminations changed by $242 million and $79 million reflecting higher pension and postretirement costs partially offset by lower share-based plan expense and deferred compensation costs.

The most significant expense items not allocated to segments are shown in the following table:

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Share-based plans | **$(63)** | $(112) | **$(19)** | $(22) |
| Deferred compensation | **4** | (84) | **64** | (47) |
| Pension | **(216)** | 64 | **(58)** | 21 |
| Postretirement | **(208)** | (36) | **(175)** | (12) |
| Eliminations and other | **(221)** | (294) | **(118)** | (167) |
| Total | **$(704)** | $(462) | **$(306)** | $(227) |

Deferred compensation expense decreased by $88 million and $111 million for the nine and three months ended September 30, 2011 compared with the same periods in 2010. The year over year changes are primarily driven by changes in our stock price and broad stock market conditions.

Eliminations and other expense for the nine and three months ended September 30, 2011 decreased by $73 million and $49 million compared with the same periods in 2010, primarily due to the timing of intercompany allocations.

Unallocated pension costs for the nine and three months ended September 30, 2011 increased by $280 million and $79 million compared with the same periods in 2010. The increase for the nine months reflects higher amortization of prior actuarial losses, lower discount rates and C-17 related pension curtailment charges. The increase for the three months reflects higher amortization of prior actuarial losses and lower discount rates. The increase in unallocated postretirement expense for the nine and three months ended September 30, 2011 includes $161 million of additional expense recorded during the quarter due to an adjustment primarily related to prior years’ accumulated postretirement benefit obligations. See the discussion of the postretirement liability understatement in Note 11 to our Condensed Consolidated Financial Statements.

Unallocated pension and other postretirement expense represents the difference between costs recognized under Generally Accepted Accounting Principles in the United States of America in the condensed consolidated financial statements and federal cost accounting standards required to be utilized by our business segments for U.S. government contracting purposes. We recorded net periodic benefit cost related to pensions and other postretirement benefits of $2,400 million and $911 million for the nine and three months ended September 30, 2011 and $1,430 million and $463 million for the nine and three months ended September 30, 2010. Not all net periodic benefit cost is recognized in earnings in the period incurred. A portion of net periodic benefit cost is allocated to production as product cost and a portion remains in inventory at the end of the reporting period. Earnings from operations included the following net periodic benefit cost allocated to business segments and Unallocated items and eliminations:

*(Dollars in millions)*

| Pension Plans | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Allocated to business segments | **$(1,088)** | $(911) | **$(331)** | $(301) |
| Other unallocated items and eliminations | **(216)** | 64 | **(58)** | 21 |
| Total | **$(1,304)** | $(847) | **$(389)** | $(280) |

*(Dollars in millions)*

| Other Postretirement Benefit Plans | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Allocated to business segments | **$(353)** | $(340) | **$(106)** | **$(112)** |
| Other unallocated items and eliminations | **(208)** | (36) | **(175)** | **(12)** |
| Total | **$(561)** | $(376) | **$(281)** | **$(124)** |

### Other Earnings Items

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| **Earnings from operations** | **$4,247** | $3,868 | **$1,714** | $1,387 |
| Other income/(expense), net | **76** | 20 | **49** | (13) |
| Interest and debt expense | **(374)** | (384) | **(121)** | (130) |
| **Earnings before income taxes** | **3,949** | 3,504 | **1,642** | 1,244 |
| Income tax expense | **(1,325)** | (1,359) | **(548)** | (407) |
| **Net earnings from continuing operations** | **$2,624** | $2,145 | **$1,094** | $837 |

The increase in Other income is primarily due to gains on foreign exchange contracts.

The effective tax rates were 33.6% and 33.4% for the nine and three months ended September 30, 2011 and 38.8% and 32.7% for the same periods in the prior year. The decrease in the effective tax rate for the nine months as compared with the prior year was primarily due to an income tax charge of $150 million recorded during the first quarter of 2010 as a result of the Patient Protection and

Affordable Care Act, as modified by the Health Care and Education Reconciliation Act of 2010. The decrease in the effective tax rate for the nine months as compared with the prior year was also due to U.S. research and development tax credit benefits that exist in 2011, but did not exist as of September 30, 2010. In December 2010, the research and development tax credit was retroactively renewed for 2010 and extended through December 31, 2011.

For additional discussion related to Income Taxes, see Note 3 to our Condensed Consolidated Financial Statements.

Contractual backlog of unfilled orders excludes purchase options, announced orders for which definitive contracts have not been executed and unobligated U.S. and non-U.S. government contract funding. The increase in contractual backlog during the nine months ended September 30, 2011 compared with December 31, 2010 was primarily due to Commercial Airplanes.

Unobligated backlog includes U.S. and foreign government definitive contracts for which funding has not been authorized. The decrease in unobligated backlog during the nine months ended September 30, 2011 was due to funding of existing multi-year contracts and partial terminations for convenience by the U.S. Army of the Brigade Combat Team Modernization (BCTM) program, partially offset by the U.S. Air Force (USAF) contract for the KC-46A Tanker.

### Additional Considerations

**KC-46A Tanker** On February 24, 2011, we were awarded a contract from the USAF to design, develop, manufacture and deliver 4 next generation aerial refueling tankers. The KC-46A Tanker will be a derivative of our 767 commercial aircraft. This contract is a fixed-price incentive firm contract, valued at $4.9 billion and involves highly complex designs. Changes to our estimated cost to perform the work could result in a material charge. This contract contains production options. If all options under the contract are exercised, we expect to deliver 179 aircraft for a total expected contract value of approximately $30 billion. For segment reporting purposes, backlog, revenues and costs are recorded in the Commercial Airplanes and BMA segments.

### Segment Results of Operations

### Commercial Airplanes

### Business Environment and Trends

**Airline Industry Environment** Global economic uncertainty, as well as factors such as political turmoil in the Middle East, the March 2011 natural disasters in Japan, the European sovereign debt crisis, deficit reduction challenges in the U.S., and high fuel prices continue to impact airline traffic and costs. Due in large part to these factors, net profits for the global airline industry are expected to total $7 billion in 2011, reduced from $18 billion in 2010. In the face of these challenges, passenger traffic has been more resilient than air cargo traffic. While the European sovereign debt crisis may result in reduced levels of commercial bank financing for aircraft, we expect increases from other sources of financing, such as capital markets, lessors, and regional banks.

The long-term outlook for the industry remains positive due to the fundamental drivers of air travel growth: economic growth and the increasing propensity to travel due to increased trade, globalization and improved airline services driven by liberalization of air traffic rights between countries. Our 20-year forecast is for a long-term average growth rate of 5%—6% per year for passenger and cargo traffic based on a projected average annual worldwide real economic growth rate of 3%. Based on long-term global economic growth projections, and factoring in increased utilization of the worldwide airplane fleet and requirements to replace older airplanes, we project a $4.0 trillion market for 33,500 new airplanes over the next 20 years.

### Operating Results

*(Dollars in millions)*

|  | September 30 Nine months ended September 30 2011 | September 30 2010 | September 30 Three months ended September 30 2011 | September 30 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$25,476** | $23,650 | **$9,515** | $8,749 |
| Earnings from operations | **$2,514** | $2,379 | **$1,085** | $1,017 |
| Operating margins | **9.9%** | 10.1% | **11.4%** | 11.6% |

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$270,289** | $255,591 |
| Unobligated backlog | **2,190** | 49 |

### Revenues

Year over year changes in Revenue are shown in the following table:

*(Dollars in millions)*

|  | Nine months ended September 30, 2011 vs. September 30, 2010 | Three months ended September 30, 2011 vs. September 30, 2010 |
| --- | ---: | ---: |
| New airplane sales | $1,363 | $750 |
| Commercial aviation services | 464 | 42 |
| Other | (1) | (26) |
| Total | $1,826 | $766 |

Revenues for the nine and three months ended September 30, 2011 increased by $1,826 million and $766 million or 8% and 9% compared with the same periods of 2010 primarily due to higher new airplane and commercial aviation services sales.

Commercial jet aircraft deliveries, including intercompany deliveries, were as follows:

|  |  |  |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: |
| **Program** | **737** | **747** | **767** | **777** | **787** | **Total** |
| Deliveries during the first nine months of 2011 | 281 |  | 14 | 53 | 1 | 349 |
| Deliveries during the first nine months of 2010 | 281 |  | 9 | 56 |  | 346 |
| Deliveries during the third quarter of 2011 | 100 |  | 5 | 21 | 1 | 127 |
| Deliveries during the third quarter of 2010 | 100 |  | 3 | 21 |  | 124 |
| Cumulative deliveries as of 9/30/2011 | 3,787 | 1,418 | 1,008 | 963 | 1 |  |
| Cumulative deliveries as of 12/31/2010 | 3,506 | 1,418 | 994 | 910 |  |  |

### Earnings From Operations

Earnings from operations for the nine months ended September 30, 2011 increased by $135 million. This increase was primarily due to earnings from higher revenues on new airplane deliveries and commercial aviation services, partially offset by increases in period costs associated with business growth and increases in research and development.

Earnings from operations for the three months ended September 30, 2011 increased by $68 million. The increase was primarily due to earnings from higher revenues on new airplane deliveries and a reduction in research and development cost related to certifications of the 747-8 Freighter and 787-8, partially offset by increases in period costs associated with business growth.

The increase in contractual backlog during the nine months ended September 30, 2011 was due to net orders in excess of revenues and changes in projected revenue escalation. A number of our customers may have contractual remedies that may be implicated by program delays. We continue to address customer claims and requests for other contractual relief as they arise. However, once orders are included in firm backlog, orders remain in backlog until canceled or fulfilled, although the value of orders is adjusted as changes to price and schedule are agreed to with customers. The increase in unobligated backlog represents Commercial Airplanes’ share of the USAF contract for the KC-46A Tanker.

### Accounting Quantity

The following table provides details of the accounting quantities and firm orders by program. Cumulative firm orders represent the cumulative number of commercial jet aircraft deliveries plus undelivered firm orders.

|  | Program |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| **As of 9/30/2011** | **737** | **747** | **767** | **777** | **787** |
| Program accounting quantities | **5,600** | **1,549** | **1,060** | **1,300** | **1,100** |
| Undelivered units under firm orders | **2,215** | **111** | **49** | **325** | **820** |
| Cumulative firm orders | **6,002** | **1,529** | **1,057** | **1,288** | **821** |

|  | Program |  |  |  |  |
| --- | ---: | ---: | ---: | ---: | ---: |
| As of 12/31/2010 | 737 | 747 | 767 | 777 | 787 |
| Program accounting quantities | 5,000 | 1,524 | 1,048 | 1,150 | \* |
| Undelivered units under firm orders | 2,186 | 107 | 50 | 253 | 847 |
| Cumulative firm orders | 5,692 | 1,525 | 1,044 | 1,163 | 847 |

\* The initial accounting quantity for the 787 program was established in the third quarter of 2011.

**737 Program** The accounting quantity for the 737 program was unchanged for the three months ended September 30, 2011, and increased by 600 units during the nine months ended September 30, 2011 to reflect the current backlog and continued demand. During 2010, we announced plans to increase monthly production from 31.5 to 35 airplanes per month beginning in 2012 and a further increase to 38 airplanes per month beginning in 2013. On June 15, 2011, to address continued demand for delivery positions, we announced plans to increase production of the 737 to 42 aircraft per month beginning in 2014. On August 30, 2011, we announced the launch of the 737 MAX, the new engine variant of the 737.

**747 Program** The accounting quantity for the 747 program was unchanged for the three months ended September 30, 2011 and increased by 25 units during the nine months ended September 30, 2011. The 747-8 Freighter was certified during the third quarter and first delivery occurred in October 2011. First flight of the 747-8 Intercontinental passenger derivative occurred on March 20, 2011. The 747-8 Intercontinental remains on track for certification in the fourth quarter. First delivery is now scheduled for first quarter 2012 due to a delay in flight testing and the time required to incorporate all flight test driven changes. In addition to continuing flight testing and certification efforts on the 747-8 Intercontinental, we remain focused on incorporating engineering and design changes identified during flight testing into aircraft completed prior to certification, achieving a planned increase in 747 production rate from 1.5 to 2 airplanes per month in mid-2012, reducing out-of-sequence work and improving supply chain efficiency. If risks associated with these activities cannot be mitigated it could result in customer claims and/or supplier assertions and/or result in an additional reach-forward loss. We continue to implement mitigation plans and cost-reduction efforts to improve program profitability and address program risks.

**767 Program** The accounting quantity for the 767 program was unchanged for the three months ended September 30, 2011 and increased by 12 units during the nine months ended September 30, 2011 due to the program’s normal progress of obtaining additional orders and delivering aircraft.

**777 Program** The accounting quantity for the 777 program increased by 50 and 150 units during the three and nine months ended September 30, 2011 due to the program’s normal progress of obtaining additional orders and delivering aircraft. As planned, the 777 program’s first delivery at 7 airplanes per month from 5 per month occurred in June 2011.

**787 Program** We completed initial type certification flight testing activities and received design and production certifications for the 787-8 during the third quarter of 2011. We delivered the first 787 airplane in September 2011.

We continue to monitor and address challenges associated with aircraft assembly, including management of our extended global supply chain, incorporation of design changes into aircraft in various stages of assembly, completion and integration of traveled work as well as weight and systems integration. For example, in 2011 we delayed production rate increases and some 787 component deliveries to reduce out-of-sequence work moving into final assembly at our Everett factory and improve supply chain efficiency. In addition, a number of engineering and other design changes identified during flight testing are being incorporated on aircraft completed prior to certification.

We remain focused on achieving planned increases in 787 production rates while continuing to satisfy customer mission and performance requirements. We currently expect to increase production of 787 aircraft to 10 aircraft per month by late 2013. Our efforts to achieve planned production rate targets include improving the production system, coordinating rate increases with suppliers, the start-up of the second assembly line in North Charleston, South Carolina and establishing transitional surge capacity at our Everett location. With successful completion of the 787-9 critical design review we have assessed the schedule and first delivery is now expected in early 2014, although we continue to look for opportunities to regain schedule. In addition, we continue to work with our customers and suppliers to assess the specific impacts of prior schedule changes, including requests for contractual relief related to delivery delays and supplier assertions.

During 2009, we concluded that the first three flight-test 787 aircraft could not be sold as previously anticipated due to the inordinate amount of rework and unique and extensive modifications made to those aircraft. As a result, costs associated with these airplanes were included in research and development expense. We believe that the other three 787 flight test aircraft are commercially saleable and we continue to include costs related to those airplanes in program inventory at September 30, 2011. If we determine that one or more of the other aircraft cannot be sold, we may incur additional charges.

This quarter we established an initial accounting quantity of 1,100 units, representing approximately 10 years of production at planned production rates. The cumulative impacts of production challenges, change incorporation, schedule delays and customer and supplier impacts have created significant pressure on program profitability and therefore we have recorded a low margin on our initial delivery. Future production challenges, including not meeting one or more planned production rate increases going forward, or introducing the 787-9 derivative as scheduled, could result in additional customer claims and/or supplier assertions as well as result in further pressures on program profitability and/or a reach-forward loss. We continue to implement mitigation plans and cost-reduction efforts to improve program profitability and address program risks.

### Additional Considerations

The 787 and 747-8 programs highlight the risks inherent in new airplane programs and new derivative airplanes. Development continues on the 787-9. In the third quarter of 2011 we launched a variant of the 737 that will feature new more fuel efficient engines – the 737 MAX. Costs related to development of new programs and derivative airplanes are expensed as incurred. Costs to produce new aircraft are included in inventory and accounted for using program accounting. Airplane programs have risk for reach-forward losses if our estimated production costs exceed our estimated program revenues for the accounting quantity. Generally commercial airplanes are sold on a firm fixed-price basis with an indexed price escalation clause and are often sold several years before scheduled delivery. Each customer purchase agreement contains an escalation clause to account for the effects of economic fluctuations over the period of time from airplane sale to airplane delivery. A price escalation formula based on pre-defined factors is used to determine the final price of the airplane at the time of customer delivery. While firm fixed-price contracts allow us to benefit from cost savings, they also expose us to the risk of cost overruns. Many new airplanes and derivatives have highly complex designs, utilize exotic materials and require extensive coordination and integration with supplier partners. As technical or quality issues arise, such as issues experienced on the 787 and 747-8 programs, we may experience schedule delays and higher costs to complete new programs and derivative aircraft. Additionally, price escalation factors may also impact margins by reducing the estimated price of airplanes delivered in the future. There are other factors that could also result in lower margins or a material charge if a program has or is determined to have reach-forward losses. These include: changes to the program accounting quantity, customer and model mix, production costs and rates, capital expenditures and other costs associated with increasing or adding new production capacity, learning curve, anticipated cost reductions, flight test and certification schedules, costs, schedule and demand for derivative airplanes and status of customer claims, supplier assertions and other contractual negotiations. While we believe the cost and revenue estimates incorporated in the financial statements are appropriate, the technical complexity of these programs creates financial risk as additional completion costs may become necessary or scheduled delivery dates could be extended, which could trigger termination provisions, order cancellations or other financially significant exposure.

### Boeing Defense, Space & Security

### Operating Results

*(Dollars in millions)*

|  | September 30 Nine months ended September 30 2011 | September 30 2010 | September 30 Three months ended September 30 2011 | September 30 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$23,505** | $23,778 | **$8,200** | $8,182 |
| Earnings from operations | **$2,293** | $2,059 | **$824** | $684 |
| Operating margins | **9.8%** | 8.7% | **10.0%** | 8.4% |

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$46,570** | $48,364 |
| Unobligated backlog | **12,536** | 16,822 |

### Revenues

BDS revenues for the nine and three months ended September 30, 2011 decreased by $273 million and increased by $18 million or 1% and materially unchanged compared with the same periods in 2010. In both periods revenues were lower in the N&SS and GS&S segments and higher in the BMA segment.

### Earnings From Operations

BDS operating earnings for the nine and three months ended September 30, 2011 increased by $234 million and $140 million compared with the same periods in 2010. The increase for the nine months was primarily due to higher earnings in the BMA and N&SS segments. The increase for the three months was due to higher earnings in all three BDS segments.

BDS total backlog decreased 9% in 2011, from $65,186 million at December 31, 2010 to $59,106 million at September 30, 2011, due to current year deliveries, sales on multi-year contracts awarded in prior years and partial terminations for convenience by the U.S. Army of the BCTM program, partially offset by new orders.

For further details on the changes between periods, refer to the discussions of the individual segments below.

### Additional Considerations

Our business includes a variety of development programs which have complex design and technical challenges. Many of these programs have cost-type contracting arrangements. In these cases the associated financial risks are primarily in lower profit rates or program cancellation if milestones and technical progress are not accomplished. Examples of these programs include Family of Beyond Line-of-Sight Terminals, BCTM, Ground-based Midcourse Defense (GMD), P-8A Poseidon and Proprietary programs.

Some of our development programs are contracted on a fixed-price basis. Many of these programs have highly complex designs. As technical or quality issues arise, we may experience schedule delays and cost impacts, which could increase our estimated cost to perform the work or reduce our estimated price, either of which could result in a material charge. These programs are ongoing, and while we believe the cost and fee estimates incorporated in the financial statements are appropriate, the technical complexity of these programs creates financial risk as additional completion costs may become necessary or scheduled delivery dates could be extended, which could trigger termination provisions, the loss of satellite in-orbit incentive payments, or other financially significant exposure. These programs have risk for reach-forward losses if our estimated costs exceed our estimated contract revenues. Examples of our fixed-price development programs include Airborne Early Warning and Control (AEW&C), P-8I, KC-46A Tanker, KC-767 International Tanker and commercial and military satellites.

### Boeing Military Aircraft

### Operating Results

*(Dollars in millions)*

|  | September 30 Nine months ended September 30 2011 | September 30 2010 | September 30 Three months ended September 30 2011 | September 30 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$10,998** | $10,611 | **$3,964** | $3,790 |
| Earnings from operations | **$1,152** | $935 | **$397** | $312 |
| Operating margins | **10.5%** | 8.8% | **10.0%** | 8.2% |

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$24,191** | $25,094 |
| Unobligated backlog | **8,432** | 8,297 |

### Revenues

BMA revenues for the nine and three months ended September 30, 2011 increased by $387 million and $174 million, increases of 4% and 5% compared with the same periods in 2010. The increases were primarily due to higher AEW&C and C-17 revenues partially offset by lower revenues on the F-22, F/A-18 and Apache programs. AEW&C revenues increased in 2011 primarily due to delivery of the first Peace Eye aircraft, while the C-17 increase reflects a change in delivery mix and lower 2010 C-17 deliveries due to a second quarter 2010 labor strike.

Deliveries of units for new-build production aircraft, excluding remanufactures and modifications, were as follows:

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| F/A-18 Models | **38** | 39 | **13** | 15 |
| F-15E Eagle | **11** | 10 | **3** | 3 |
| C-17 Globemaster | **11** | 10 | **4** | 4 |
| AH-64 Apache |  | 11 |  | 2 |
| CH-47 Chinook | **22** | 13 | **6** | 5 |
| AEW&C | **2** | 3 | **2** |  |
| KC-767 International Tanker | **1** |  |  |  |
| Total new-build production aircraft | **85** | 86 | **28** | 29 |

### Earnings From Operations

BMA operating earnings for the nine and three months ended September 30, 2011 increased by $217 million and $85 million, increases of 23% and 27% compared with the same periods in 2010. The increase for the nine month period was partially due to higher C-17 revenues and lower research and development costs, partially offset by lower earnings on the F-22 and Apache programs. The increase for the three month period was primarily due to improved earnings on the C-17 program and earnings on the Peace Eye delivery, partially offset by lower earnings on F/A-18, F-22 and Apache programs. Operating earnings for the nine and three month periods in 2010 were negatively impacted by charges recorded on the KC-767 International Tanker program, while operating earnings in 2010 and 2011 were reduced by charges recorded on the AEW&C program.

### Backlog

BMA total backlog was $32,623 million at September 30, 2011 a decrease of 2% from December 31, 2010 primarily due to current year deliveries and sales on multi-year contracts awarded in prior years partially offset by BMA’s share of the USAF contract awards for the KC-46A Tanker and P-8A.

### Additional Considerations

**AEW&C** The AEW&C development program, also known as Wedgetail in Australia, Peace Eagle in Turkey and Peace Eye in the Republic of Korea, consists of 737-700 aircraft outfitted with a variety of command and control and advanced radar systems, some of which have never been installed on an airplane before. A total of five Wedgetail aircraft have been delivered to Australia with initial customer acceptance. Four were delivered in 2010 and one in September 2011. The final Wedgetail aircraft is scheduled for delivery with initial customer acceptance in the first quarter of 2012. Final customer acceptance for all six Wedgetail aircraft is also scheduled to be completed during the first quarter of 2012. In January 2011, the Peace Eagle program began the formal test phase. The first Peace Eye aircraft was delivered to the Republic of Korea in September 2011. These are advanced and complex fixed-price development programs involving technical challenges at the individual subsystem level and in the overall integration of these subsystems into a reliable and effective operational capability. We believe that the cost and revenue estimates incorporated in the financial statements are appropriate;

however, the technical complexity of the programs creates financial risk as additional completion costs may be necessary or scheduled delivery dates could be delayed, either of which could result in lower margins or additional material charges.

**KC-767 International Tanker** We delivered the first of four aircraft to the Italian Air Force in December 2010 and the second in March 2011. We believe the revenue and cost estimates incorporated in the financial statements are appropriate; however, the technical complexity of the program creates financial risk as additional completion and development costs may be necessary or remaining scheduled delivery dates could be delayed, either of which could result in additional material changes.

**C-17 and F-15** See the discussion of the C-17 and F-15 programs in Note 8 to our Condensed Consolidated Financial Statements.

### Network & Space Systems

### Operating Results

*(Dollars in millions)*

|  | September 30 Nine months ended September 30 2011 | September 30 2010 | September 30 Three months ended September 30 2011 | September 30 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$6,706** | $7,021 | **$2,276** | $2,344 |
| Earnings from operations | **$520** | $493 | **$179** | $152 |
| Operating margins | **7.8%** | 7.0% | **7.9%** | 6.5% |

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$9,451** | $9,586 |
| Unobligated backlog | **3,892** | 8,435 |

### Revenues

N&SS revenues for the nine and three months ended September 30, 2011 decreased by $315 million and $68 million, decreases of 4% and 3% compared with the same periods in 2010. The decrease for the nine months was primarily due to lower BCTM, SBInet and GMD revenues, partially offset by higher sales of Delta inventory to United Launch Alliance (ULA), revenues of Argon ST, Inc. acquired in August 2010 and higher satellite revenues. The decrease for the three months was primarily due to lower BCTM, SBInet and GMD revenues, partially offset by higher sales of Delta inventory to ULA and higher satellite revenues.

### Earnings From Operations

N&SS operating earnings for the nine and three months ended September 30, 2011 each increased by $27 million, increases of 5% and 18% compared with the same periods in 2010. The increase for the nine months was due to higher earnings from our investment in ULA and a gain from a property sale partially offset by lower earnings on the BCTM and GMD programs. The increase for the three months was primarily due to higher earnings on several satellite programs, partially offset by lower earnings on the BCTM and GMD programs and lower income from our investments in joint ventures.

N&SS total backlog was $13,343 million at September 30, 2011, a decrease of 26% from December 31, 2010 primarily due to partial terminations for convenience by the U.S. Army of the BCTM program and revenues recognized on multi-year contracts awarded in prior years.

### Additional Considerations

**United Launch Alliance** See the discussion of Commitments to ULA and Indemnifications to ULA in Notes 8 and 9 to our Condensed Consolidated Financial Statements.

**Sea Launch** See the discussion of the Sea Launch receivables in Note 7 to our Condensed Consolidated Financial Statements.

**Satellites** See the discussions of Boeing Satellite Systems International, Inc. in Note 15 to our Condensed Consolidated Financial Statements.

### Global Services & Support

### Operating Results

*(Dollars in millions)*

|  | September 30 Nine months ended September 30 2011 | September 30 2010 | September 30 Three months ended September 30 2011 | September 30 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$5,801** | $6,146 | **$1,960** | $2,048 |
| Earnings from operations | **$621** | $631 | **$248** | $220 |
| Operating margins | **10.7%** | 10.3% | **12.7%** | 10.7% |

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| Contractual backlog | **$12,928** | $13,684 |
| Unobligated backlog | **212** | 90 |

### Revenues

GS&S revenues for the nine and three months ended September 30, 2011 decreased by $345 million and $88 million compared with the same periods in 2010. The 6% decrease for the nine months was primarily due to the conclusion of our KC-10 support program in 2010 and lower 2011 deliveries and volume in several Training Systems & Services (TS&S) and Integrated Logistics (IL) programs. The 4% decrease for the three months was primarily due to lower 2011 deliveries and volume in several TS&S and IL programs. These decreases were partially offset by higher international revenues.

### Earnings From Operations

GS&S operating earnings for the nine and three months ended September 30, 2011 decreased by $10 million and increased by $28 million compared with the same periods in 2010. The decrease for the nine months was primarily due to lower revenues. The increase for the three months was primarily due to unfavorable performance adjustments on several IL programs in 2010.

GS&S total backlog was $13,140 million at September 30, 2011, a decrease of 5% from December 31, 2010, primarily due to revenues recognized on multi-year contracts awarded in prior years on several IL programs, partially offset by a TS&S contract award on the P-8A program.

### Boeing Capital Corporation

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$416** | $494 | **$126** | $170 |
| Earnings from operations | **$133** | $146 | **$19** | $45 |
| Operating margins | **32%** | 30% | **15%** | 26% |

### Revenues

Boeing Capital Corporation (BCC) segment revenues consist principally of lease income from equipment under operating lease and interest from financing receivables and notes. BCC’s revenues for the nine and three months ended September 30, 2011 decreased $78 million and $44 million compared with the same periods in 2010 primarily due to lower interest income on notes receivable resulting from a lower weighted average notes receivable balance and lower operating lease income from a smaller portfolio of equipment under operating leases as a result of return of aircraft and lower lease rates on re-leased aircraft.

### Earnings From Operations

BCC’s operating earnings are presented net of interest expense, provision for losses, asset impairment expense, depreciation on leased equipment and other operating expenses. Operating earnings for the nine and three months ended September 30, 2011 decreased by $13 million and $26 million compared with the same periods in 2010 primarily due to lower revenues and higher asset impairment expense partially offset by lower interest expense, lower depreciation expense and a reduction in the allowance for losses.

### Financial Position

The following table presents selected financial data for BCC:

*(Dollars in millions)*

|  | September 30 2011 | December 31 2010 |
| --- | ---: | ---: |
| BCC customer financing and investment portfolio | **$4,342** | $4,694 |
| Valuation allowance as a % of total receivables | **2.4%** | 3.8% |
| Debt | **$3,407** | $3,446 |
| Debt-to-equity ratio | **6.2-to-1** | 5.0-to-1 |

BCC’s customer financing and investment portfolio at September 30, 2011 decreased from December 31, 2010 due to normal portfolio run-off and asset sales, partially offset by the origination of notes receivable. At September 30, 2011 and December 31, 2010, BCC had $541 million and $583 million of assets that were held for sale or re-lease, of which $485 million and $28 million had either executed term sheets with deposits or firm contracts to be sold or placed on lease. Additionally, aircraft subject to leases with a carrying value of approximately $105 million are scheduled to be returned off lease in the next 12 months. These aircraft are being remarketed or we are seeking to have the leases extended.

BCC enters into certain transactions with the Other segment in the form of intercompany guarantees and other subsidies that mitigate the effects of certain credit quality or asset impairment issues on the BCC segment.

### Restructurings and Restructuring Requests

From time to time, certain customers have requested a restructuring of their transactions with BCC. As of September 30, 2011, BCC has not reached agreement on any restructuring requests that would have a material effect on our earnings, cash flows and/or financial position.

On May 2, 2011, Southwest Airlines Co. (Southwest) completed its acquisition of AirTran Holdings, Inc. AirTran Holdings’ successor entity (AirTran) and its subsidiaries represent approximately 27% of our gross customer financing portfolio carrying value, consisting principally of 717 aircraft. AirTran is the largest customer in terms of BCC’s segment revenue and customer financing portfolio carrying value. We continue to evaluate the impact of the AirTran/Southwest merger, and Southwest’s continuing efforts to integrate the two operations, on our business. At September 30, 2011 we assigned an upgraded internal credit rating category of BB to our receivables with AirTran.

### Other Segment

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 | Three months ended September 30 2011 | 2010 |
| --- | ---: | ---: | ---: | ---: |
| Revenues | **$107** | $107 | **$33** | $27 |
| Earnings/(loss) from operations | **11** | (254) | **92** | (132) |

Other segment earnings for the nine and three months ended September 30, 2011 increased by $265 million and $224 million compared with the same periods in 2010, primarily due to a reduction in the allowance for losses on receivables.

### Liquidity and Capital Resources

### Cash Flow Summary

*(Dollars in millions)*

|  | Nine months ended September 30 2011 | 2010 |
| --- | ---: | ---: |
| Net earnings | **$2,625** | $2,143 |
| Non-cash items | **1,510** | 1,688 |
| Changes in working capital | **(3,043)** | (1,995) |
| Net cash provided by operating activities | **1,092** | 1,836 |
| Net cash provided/(used) by investing activities | **856** | (6,480) |
| Net cash used by financing activities | **(1,354)** | (1,645) |
| Effect of exchange rate changes on cash and cash equivalents | **1** | (62) |
| Net increase/(decrease) in cash and cash equivalents | **595** | (6,351) |
| Cash and cash equivalents at beginning of year | **5,359** | 9,215 |
| Cash and cash equivalents at end of period | **$5,954** | $2,864 |

**Operating Activities** Net cash provided by operating activities of $1,092 million during the nine months ended September 30, 2011 decreased by $744 million compared with the same period in 2010 primarily due to continued growth in inventory as we prepare for deliveries and production ramp-up of the 787 and 747-8 airplanes partially offset by increases in advances and accounts payable.

**Investing Activities** Cash provided by investing activities of $856 million during the nine months ended September 30, 2011 increased by $7,336 million compared with the same period in 2010, largely due to changes in investments which primarily consist of time deposits. Net proceeds from investments were $1,917 million in 2011 compared with net contributions to investments of $5,088 million in 2010. Capital spending in 2011 is higher than 2010 due to the construction of a 787 final assembly line in North Charleston, South Carolina, investment to support commercial airplane production rate increases and ongoing capital improvements.

**Financing Activities** Cash used by financing activities totaled $1,354 million during the nine months ended September 30, 2011 compared with $1,645 million used during the nine months ended September 30, 2010.

During the three months ended September 30, 2011, proceeds from BCC borrowings amounted to $745 million and during the nine months ended September 30, 2011, we repaid $895 million of debt, including scheduled repayments of $794 million of debt held at BCC. The recorded balance of debt as of September 30, 2011 was $12,380 million, of which $1,603 million was classified as short-term. This includes $3,407 million of debt recorded at BCC, of which $834 million was classified as short-term.

During the nine months ended September 30, 2011, we did not repurchase any shares through our open market share repurchase program and had 304,304 shares transferred to us from employees for tax withholding.

**Capital Resources** We have substantial borrowing capacity. Any future borrowings may affect our credit ratings and are subject to various debt covenants as described below. We and BCC have commercial paper programs that continue to serve as significant potential sources of short-term liquidity. As of September 30, 2011, neither we nor BCC had any commercial paper borrowings outstanding. Currently, we have $4,376 million ($1,500 million exclusively available for BCC) of unused borrowing on revolving credit line agreements. We anticipate that these credit lines will primarily serve as backup liquidity to support possible commercial paper borrowings.

Financing commitments totaled $15,624 million and $9,865 million as of September 30, 2011 and December 31, 2010. We anticipate that we will not be required to fund a significant portion of our financing commitments as we continue to work with third party financiers to provide alternative financing to customers. Historically, we have not been required to fund significant amounts of outstanding commitments. However, there can be no assurances that we will not be required to fund greater amounts than historically required.

In the event we require additional funding to support strategic business opportunities, our commercial aircraft financing commitments, unfavorable resolution of litigation or other loss contingencies, or other business requirements, we expect to meet increased funding requirements by issuing commercial paper or term debt. We believe our ability to access external capital resources should be sufficient to satisfy existing short-term and long-term commitments and plans, and also to provide adequate financial flexibility to take advantage of potential strategic business opportunities should they arise within the next year. However, there can be no assurance of the cost or availability of future borrowings, if any, under our commercial paper program, in the debt markets or our credit facilities.

As of September 30, 2011, we were in compliance with the covenants for our debt and credit facilities. The most restrictive covenants include a limitation on mortgage debt and sale and leaseback transactions as a percentage of consolidated net tangible assets (as defined in the credit agreements), and a limitation on consolidated debt as a percentage of total capital (as defined). When considering debt covenants, we continue to have substantial borrowing capacity.

### Off-Balance Sheet Arrangements

We are a party to certain off-balance sheet arrangements including certain guarantees. For discussion of these arrangements, see Note 9 to our Condensed Consolidated Financial Statements.

### Contingent Obligations

We have significant contingent obligations that arise in the ordinary course of business, which include the following:

**Legal** Various legal proceedings, claims and investigations are pending against us. Legal contingencies are discussed in Note 15 to our Condensed Consolidated Financial Statements, including our contesting the default termination of the A-12 aircraft, certain employment, labor and benefits litigation, litigation/arbitration involving BSSI programs and civil securities litigation relating to disclosures concerning the 787 program.

**Environmental Remediation** We are involved with various environmental remediation activities and have recorded a liability of $787 million at September 30, 2011. For additional information, see Note 8 to our Condensed Consolidated Financial Statements.

**Income Taxes** We have recorded a net liability of $1,273 million at September 30, 2011 for uncertain tax positions. For further discussion of income taxes, see Note 3 to our Condensed Consolidated Financial Statements.

## Controls and procedures

As filed, 1,018 characters.

(a) Disclosure Controls and Procedures.

Our Chief Executive Officer and Chief Financial Officer have evaluated our disclosure controls and procedures as of September 30, 2011 and have concluded that these disclosure controls and procedures are effective to ensure that information required to be disclosed by us in the reports that we file or submit under the Securities Exchange Act of 1934, as amended, is recorded, processed, summarized and reported within the time periods specified in the Commission’s rules and forms and is accumulated and communicated to our management, including the Chief Executive Officer and Chief Financial Officer, as appropriate to allow timely decisions regarding required disclosure.

(b) Changes in Internal Control Over Financial Reporting.

There were no changes in our internal control over financial reporting that occurred during the third quarter of 2011 that have materially affected or are reasonably likely to materially affect our internal control over financial reporting.

## Risk factors

As filed, 181 characters.

There have been no material changes in our risk factors from those disclosed in Part I, Item 1A. Risk Factors in our Annual Report on Form 10-K for the year ended December 31, 2010.

Filed Oct 26, 2011.
Source: SEC EDGAR, the filing index for accession 0001193125-11-281613. Last ingested by Listed: Nov 14, 2026, 13:59 ET. No prices; not investment advice.