# BWX Technologies, Inc.: Form 10-Q for the period ended Sep 30, 2013

- Company: [BWX Technologies, Inc.](/companies/bwxt.md) (CIK 1486957)
- Form: 10-Q
- Filed: 2013-11-12
- Accepted by EDGAR: Nov 12, 2013, 16:09 ET
- Period: 2013-09-30
- Accession: 0001193125-13-438253
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/1486957/000119312513438253/d602934d10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/1486957/000119312513438253/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2013-09-30.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2013-07-01 to 2013-09-30 | $774.8m | us-gaap:Revenues |
| Revenue | 9 months, 2013-01-01 to 2013-09-30 | $2.47bn | us-gaap:Revenues |
| Cost of revenue | 3 months, 2013-07-01 to 2013-09-30 | $578.4m | us-gaap:CostOfRevenue |
| Cost of revenue | 9 months, 2013-01-01 to 2013-09-30 | $1.88bn | us-gaap:CostOfRevenue |
| Research and development | 3 months, 2013-07-01 to 2013-09-30 | $23.8m | us-gaap:ResearchAndDevelopmentExpense |
| Research and development | 9 months, 2013-01-01 to 2013-09-30 | $53.0m | us-gaap:ResearchAndDevelopmentExpense |
| Selling, general and administrative | 3 months, 2013-07-01 to 2013-09-30 | $102.6m | us-gaap:SellingGeneralAndAdministrativeExpense |
| Selling, general and administrative | 9 months, 2013-01-01 to 2013-09-30 | $313.1m | us-gaap:SellingGeneralAndAdministrativeExpense |
| Operating income | 3 months, 2013-07-01 to 2013-09-30 | $82.1m | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months, 2013-01-01 to 2013-09-30 | $241.0m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months, 2013-07-01 to 2013-09-30 | $631.0k | us-gaap:InterestExpense |
| Interest expense | 9 months, 2013-01-01 to 2013-09-30 | $2.2m | us-gaap:InterestExpense |
| Income tax | 3 months, 2013-07-01 to 2013-09-30 | $24.4m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months, 2013-01-01 to 2013-09-30 | $70.2m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2013-07-01 to 2013-09-30 | $60.4m | us-gaap:NetIncomeLoss |
| Net income | 9 months, 2013-01-01 to 2013-09-30 | $180.5m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2013-07-01 to 2013-09-30 | $0.54 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months, 2013-01-01 to 2013-09-30 | $1.60 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months, 2013-07-01 to 2013-09-30 | $0.54 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months, 2013-01-01 to 2013-09-30 | $1.61 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months, 2013-07-01 to 2013-09-30 | 111,749,381 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months, 2013-01-01 to 2013-09-30 | 113,049,700 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months, 2013-01-01 to 2013-09-30 | −$6.0m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months, 2013-01-01 to 2013-09-30 | $45.3m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 9 months, 2013-01-01 to 2013-09-30 | $27.1m | us-gaap:PaymentsOfDividendsCommonStock |
| Share repurchases | 9 months, 2013-01-01 to 2013-09-30 | $140.1m | us-gaap:PaymentsForRepurchaseOfCommonStock |
| Cash and equivalents | at 2013-09-30 | $219.8m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2013-09-30 | $1.43bn | us-gaap:AssetsCurrent |
| Total assets | at 2013-09-30 | $2.74bn | us-gaap:Assets |
| Current liabilities | at 2013-09-30 | $991.8m | us-gaap:LiabilitiesCurrent |
| Long-term debt | at 2013-09-30 | $276.0k | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | at 2013-09-30 | $4.8m | us-gaap:DebtCurrent |
| Shareholders' equity | at 2013-09-30 | $1.02bn | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 49,318 characters.

CAUTIONARY STATEMENT CONCERNING FORWARD-LOOKING STATEMENTS

The following information should be read in conjunction with the unaudited condensed consolidated financial statements and the notes thereto included under Item 1 of this report and the audited consolidated and combined financial statements and the related notes and Item 7 “Management’s Discussion and Analysis of Financial Condition and Results of Operations” included in our annual report on Form 10-K for the year ended December 31, 2012 (our “2012 10-K”).

In this quarterly report on Form 10-Q, unless the context otherwise indicates, “we,” “us” and “our” mean The Babcock & Wilcox Company (“B&W”) and its consolidated subsidiaries.

We are including the following discussion to inform our existing and potential security holders generally of some of the risks and uncertainties that can affect our company and to avail ourselves of the “safe harbor” protection for forward-looking statements provided by federal securities law, including Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”).

From time to time, our management or persons acting on our behalf make forward-looking statements to inform existing and potential security holders about our company. These statements may include projections and estimates concerning the timing and success of specific projects and our future backlog, revenues, income and capital spending. Forward-looking statements are generally accompanied by words such as “estimate,” “project,” “predict,” “believe,” “expect,” “anticipate,” “plan,” “goal” or other words that convey the uncertainty of future events or outcomes. In addition, sometimes we will specifically describe a statement as being a forward-looking statement and refer to this cautionary statement.

These forward looking statements include, but are not limited to, statements that relate to, or statements that are subject to risks, contingencies or uncertainties that relate to:

- our business strategy;
- future levels of revenues (including our backlog and project claims to the extent either may be viewed as an indicator of future revenues), operating margins, income from operations, net income or earnings per share;
- anticipated levels of demand for our products and services;
- future levels of research and development, capital, environmental or maintenance expenditures;
- our beliefs regarding the timing and effects on our businesses of certain environmental and tax legislation, rules or regulations;
- the success or timing of completion of ongoing or anticipated capital or maintenance projects;
- expectations regarding the acquisition or divestiture of assets and businesses;
- our share repurchase or other return of capital activities;
- our ability to maintain appropriate insurance and indemnities;
- the potential effects of judicial or other proceedings, including tax audits, on our business or businesses, financial condition, results of operations and cash flows;
- the anticipated effects of actions of third parties such as competitors, or federal, foreign, state or local regulatory authorities, or plaintiffs in litigation;
- the effective date and expected impact of accounting pronouncements;
- our plans regarding the design, research and development, financing and deployment of the B&W mPowerTM reactor; and
- anticipated benefits, timing and changes associated with cost reduction and efficiency improvement activities.

In addition, various statements in this quarterly report on Form 10-Q, including those that express a belief, expectation or intention, as well as those that are not statements of historical fact, are forward-looking statements.

These forward-looking statements speak only as of the date of this report; we disclaim any obligation to update these statements unless required by securities law, and we caution you not to rely on them unduly. We have based these forward-looking statements on our current expectations and assumptions about future events. While our management considers these expectations and assumptions to be reasonable, they are inherently subject to significant business, economic, competitive, regulatory and other risks, contingencies and uncertainties, most of which are difficult to predict and many of which are beyond our control. These risks, contingencies and uncertainties relate to, among other matters, the following:

- general economic and business conditions;
- general developments in the industries in which we are involved;
- decisions on spending and trends by power-generating companies and by the U.S. Government, including the automatic budget cuts (or sequestration) established by the Budget Control Act of 2011;
- the highly competitive nature of our businesses;
- cancellations of and adjustments to backlog and the resulting impact from using backlog as an indicator of future earnings;
- our ability to perform projects on time, in accordance with the schedules established by the applicable contracts with customers;
- the ability of our suppliers to deliver raw materials in sufficient quantities and in a timely manner;
- volatility and uncertainty of the credit markets;
- our ability to comply with covenants in our credit agreements and other debt instruments and the availability, terms and deployment of capital;
- the impact of our unfunded pension liabilities on liquidity, and our ability to fund such liabilities in the future, including our ability to continue being reimbursed by the U.S. Government for a portion of our pension funding obligations, which is contingent on maintaining our government contracts;
- the continued availability of qualified personnel;
- the operating risks normally incident to our lines of business, including the potential impact of project losses and liquidated damages;
- changes in, or our failure or inability to comply with, government regulations;
- adverse outcomes from legal and regulatory proceedings;
- impact of potential regional, national and/or global requirements to significantly limit or reduce greenhouse gas emissions in the future;
- our ability to successfully manage research and development projects and costs, including our efforts to develop the mPower Plant based on B&W mPowerTM technology;
- our ability to continue to obtain funding for our B&W mPowerTM technology under the Cooperative Agreement with the U.S. Department of Energy (“DOE”);
- impact of potential regulatory and industry response affecting the timing and cost of future nuclear development as a result of the damage caused by the March 11, 2011 earthquakes and tsunami on certain of Japan’s nuclear facilities;
- changes in, and liabilities relating to, existing or future environmental regulatory matters;
- rapid technological changes;
- the consequences of significant changes in interest rates and currency exchange rates;
- results of tax audits, including a determination by the IRS that the spin-off or certain transactions should be treated as a taxable transaction, and the realization of deferred tax assets;
- our ability to manage our capital structure, including our access to capital, credit ratings, debt and ability to raise additional financing;
- difficulties we may encounter in obtaining regulatory or other necessary approvals of any strategic transactions;
- the risks associated with integrating businesses we acquire;
- our ability to realize adequate returns and related dividends on our investments in unconsolidated affiliates;
- our ability to maintain operational support for our information systems against service outages and data corruption, as well as protection against cyber-based network security breaches and theft of data;
- social, political and economic situations in foreign countries where we do business;
- the possibilities of war, other armed conflicts or terrorist attacks;
- the effects of asserted and unasserted claims;
- our ability to obtain and maintain surety bonds, letters of credit and similar financing;
- our ability to obtain and maintain builder’s risk, liability, property and other insurance in amounts and on terms we consider adequate and at rates that we consider economical;
- our ability to successfully develop competitive new technologies and products;
- the aggregated risks retained in our captive insurance subsidiary; and
- the impact of the loss of insurance rights as part of the Chapter 11 bankruptcy settlement concluded in 2006 involving several of our subsidiaries.

We believe the items we have outlined above are important factors that could cause estimates in our financial statements to differ materially from actual results and those expressed in a forward-looking statement made in this report or elsewhere by us or on our behalf. We have discussed many of these factors in more detail elsewhere in this report and in Item 1A in our 2012 10-K. These factors are not necessarily all the factors that could affect us. Unpredictable or unanticipated factors we have not discussed in this report could also have material adverse effects on actual results of matters that are the subject of our forward-looking statements. We do not intend to update our description of important factors each time a potential important factor arises, except as required by applicable securities laws and regulations. We advise our security holders that they should (1) be aware that factors not referred to above could affect the accuracy of our forward-looking statements and (2) use caution and common sense when considering our forward-looking statements.

GENERAL

We operate in five segments: Power Generation, Nuclear Operations, Technical Services, Nuclear Energy and mPower. Prior to 2013, we reported four segments: Power Generation, Nuclear Operations, Technical Services and Nuclear Energy. Our small modular nuclear reactor business previously included in our Nuclear Energy segment is now being reported as a separate segment, mPower. The change in our reportable segments had no impact on our previously reported results of operations, financial condition or cash flows. For additional information regarding our change to the segments, see Note 1 to the condensed consolidated financial statements in this report.

### Business Segments

In general, we operate in capital-intensive industries and rely on large contracts for a substantial amount of our revenues. We are currently exploring growth strategies across our segments through acquisitions to expand and complement our existing businesses. As we pursue these opportunities, we expect they would be funded by cash on hand, external financing (including debt), equity or some combination thereof.

### Power Generation Segment

Our Power Generation segment’s overall activity depends mainly on the capital expenditures of electric power generating companies and other steam-using industries. Several factors influence these expenditures, including:

- prices for electricity, along with the cost of production and distribution;
- prices for coal and natural gas and other sources used to produce electricity;
- demand for electricity, paper and other end products of steam-generating facilities;
- availability of other sources of electricity, paper or other end products;
- requirements for environmental improvements;
- impact of potential regional, state, national and/or global requirements to significantly limit or reduce greenhouse gas emissions in the future;
- level of capacity utilization at operating power plants, paper mills and other steam-using facilities;
- requirements for maintenance and upkeep at operating power plants and paper mills to comply with environmental regulations and combat the accumulated effects of wear and tear;
- ability of electric power generating companies and other steam users to raise capital; and
- relative prices of fuels used in boilers, compared to prices for fuels used in gas turbines and other alternative forms of generation.

Our Power Generation segment plans to continue efforts to expand international offerings through organic growth and potential partnering arrangements or acquisitions.

### Nuclear Operations Segment

The revenues of our Nuclear Operations segment are largely a function of defense spending by the U.S. Government. As a supplier of major nuclear components for certain U.S. Government programs, this segment is a significant participant in the defense industry.

The collective bargaining agreement covering approximately 350 employees at our Barberton, Ohio manufacturing facility has expired. As of September 30, 2013, these employees continued to work under the terms of the expired contract while we negotiate a new agreement and we continue to remain focused on meeting our customer’s needs. It is difficult to predict the outcome of these negotiations as of the date of this report. For additional discussion of risks associated with labor union negotiations, see the detailed risk factors contained in Item 1A of our 2012 10-K.

### Technical Services Segment

The revenues and equity in income of investees of our Technical Services segment are largely a function of spending by the U.S. Government and the performance scores we and our consortium partners earn in managing and operating high-consequence operations at U.S. nuclear weapons sites and national laboratories. With its specialized capabilities of full life-cycle management of special nuclear materials, facilities and technologies, our Technical Services segment participates in the cleanup, operation and management of the nuclear sites and weapons complexes maintained by the DOE.

On April 29, 2013, the Government Accountability Office (“GAO”) announced that it sustained the protest filed by our joint venture, Nuclear Production Partners, LLC, regarding the procurement decision for the combined management and operating contract at the Y-12 National Security Complex and Pantex Plant. On June 17, 2013, Nuclear Production Partners, LLC filed a new protest with the GAO expressing concern over the fairness of the procurement and selection process and the form and scope of the revised request for proposals issued to bidders on June 6, 2013. On September 24, 2013, portions of this protest were dismissed as premature. However, the GAO did deny the assertion that the National Nuclear Security Administration (“NNSA”) should be required to amend the solicitation to reflect changes that have occurred due to the passage of time. On November 1, 2013, we received notification that Nuclear Production Partners, LLC was not selected by NNSA in the re-affirmed procurement decision. We will evaluate information received during the NNSA debriefing process to determine our next steps. In the meantime, we will continue to manage these sites under existing contracts through our joint ventures and during any transition period, which has yet to be determined.

### Nuclear Energy Segment

Our Nuclear Energy segment’s overall activity depends mainly on the demand and competitiveness of nuclear energy. The activity of this segment depends on capital expenditures and maintenance spending of nuclear utilities.

### mPower Segment

This segment is actively developing the B&W mPowerTM reactor and the associated mPower Plant through its majority-owned joint venture, Generation mPower LLC (“GmP”). Its activity is a function of research and development efforts for the B&W mPowerTM reactor and the potential orders to be generated from various mPower deployment initiatives. As part of this initiative, we have been selected to receive funding and have signed a Cooperative Agreement with the DOE under its Small Modular Reactor Licensing Technical Support Program (“Funding Program”), which is expected to provide financial assistance initially totaling at least $150 million for small modular reactor (“SMR”) design engineering and licensing activities supporting a planned commercial operating date for the first mPower Plant by 2022.

The Funding Program is a cost-sharing award that requires us to use the DOE funds to cover first-of-a-kind engineering costs associated with SMR design certification and licensing efforts. The DOE will provide cost reimbursement for up to 50%, subject to the overall size of the award, of qualified expenditures incurred during the period from April 1, 2013 to March 31, 2018. The DOE has authorized $99.3 million of funding for this award program as of September 30, 2013. The remaining anticipated DOE funding has not yet been authorized and is subject to Congressional appropriations. The Cooperative Agreement also provides for reimbursement of pre-award costs incurred from October 1, 2012 to March 31, 2013. During the three and nine months ended September 30, 2013, we recognized $16.4 million and $54.2 million, respectively, of the cost-sharing award, including $21.5 million of pre-award cost reimbursement, as a reduction of research and development costs on our condensed consolidated statements of income.

### Global Competitiveness Initiative

We launched the Global Competitiveness Initiative (“GCI”) in the third quarter of 2012 to enhance competitiveness, better position B&W for growth, and improve profitability. We have identified a wide range of cost reduction activities including operational and functional efficiency improvements, organizational design changes, and manufacturing optimization. Once fully executed, these actions are expected to produce at least $60 million to $70 million in annual savings. The majority of the annual savings are expected to result from efficiency improvements that are planned to be completed by the end of 2013. The balance of the cost savings relates to manufacturing initiatives that are expected to be completed by mid-2015. In order to achieve these savings, we expect to incur total restructuring charges (cash and non-cash) not to exceed $60 million. We incurred $25.5 million of costs associated with GCI for the nine months ended September 30, 2013.

For a summary of the critical accounting policies and estimates that we use in the preparation of our unaudited condensed consolidated financial statements, see Item 7 “Management’s Discussion and Analysis of Financial Condition and Results of Operations” in our 2012 10-K. There have been no material changes to these policies during the nine months ended September 30, 2013, except as disclosed in Note 1 of the notes to the condensed consolidated financial statements included in this report.

### Accounting for Contracts

As of September 30, 2013, in accordance with the percentage-of-completion method of accounting, we have provided for our estimated costs to complete all of our ongoing contracts. However, it is possible that current estimates could change due to unforeseen events, which could result in adjustments to overall contract costs. A principal risk on fixed-priced contracts is that revenue from the customer is insufficient to cover increases in our costs. It is possible that current estimates could materially change for various reasons, including, but not limited to, fluctuations in forecasted labor productivity or steel and other raw material prices. In some instances, we guarantee completion dates related to our projects or provide performance guarantees. Increases in costs on our fixed-price contracts could have a material adverse impact on our consolidated results of operations, financial condition and cash flows. Alternatively, reductions in overall contract costs at completion could materially improve our consolidated results of operations, financial condition and cash flows. In the nine months ended September 30, 2013 and 2012, we recognized changes in estimate related to long-term contracts accounted for on the percentage-of-completion basis, which increased operating income by approximately $11.9 million and $75.6 million, respectively. Included in the nine months ended September 30, 2013 were contract losses totaling $30.2 million for additional estimated costs to complete a project in our Power Generation segment. These losses are in addition to contract losses recorded for this project during 2012. In addition, in the nine months ended September 30, 2012, we recognized revenues totaling $18.4 million attributable to the settlement of a contract claim related to a condenser replacement contract in our Nuclear Energy segment.

Some of our contracts contain provisions that require us to pay liquidated damages if we are responsible for the failure to meet specified contractual milestone dates and the applicable customer asserts a claim under these provisions. These contracts define the conditions and timing under which our customers may make claims against us for liquidated damages. In the majority of cases in which we have had potential exposure for liquidated damages, such damages ultimately were determined not to be caused by our actions or were not otherwise asserted by our customers. Accordingly, we do not accrue liabilities for liquidated damages unless probable and estimable. As of September 30, 2013, we had not accrued for approximately $3.0 million of potential liquidated damages that are reasonably possible to be asserted based upon our current expectations of the time to complete a certain project.

RESULTS OF OPERATIONS – THREE MONTHS ENDED SEPTEMBER 30, 2013 VS. THREE MONTHS ENDED SEPTEMBER 30, 2012

#### The Babcock & Wilcox Company (Consolidated)

Consolidated revenues decreased 4.1%, or $32.8 million, to $774.8 million in the three months ended September 30, 2013 compared to $807.6 million for the corresponding period in 2012 primarily due to decreases in revenues from our Nuclear Energy segment totaling $22.5 million. We also experienced decreases in revenues in our Nuclear Operations and Technical Services segments totaling $2.4 million and $0.8 million, respectively.

Consolidated operating income decreased $2.3 million to $82.1 million in the three months ended September 30, 2013 from $84.4 million for the corresponding period in 2012. Operating income for the three months ended September 30, 2013 includes special charges for restructuring activities totaling $4.8 million related to the initiative we launched to enhance competitiveness, better position B&W for growth, and improve profitability. These costs consist of approximately $0.7 million of employee termination benefits, $2.5 million of consulting and other program administrative costs, and $1.6 million of facility consolidation charges due to planned reorganization of manufacturing activities. Operating income in our Power Generation and Nuclear Energy segments decreased by $2.3 million and $9.5 million, respectively. These decreases in operating income were partially offset by increases in our Nuclear Operations, Technical Services and mPower segments of $6.9 million, $6.7 million and $2.0 million, respectively. We also had higher unallocated corporate expenses totaling $1.3 million for the 2013 period as compared to 2012.

#### Power Generation

Revenues were flat at $427.0 million in the three months ended September 30, 2013 compared to $426.4 million in the corresponding period of 2012. Revenues for our aftermarket services business increased $45.3 million, which were offset by a decrease in our new build steam environmental equipment business of $32.9 million and a decrease in our new build steam generation systems business of $15.4 million. The increase in aftermarket services was primarily due to construction activity on a boiler retrofit project and a higher level of industrial plant maintenance outage services. The decrease in revenues from the new build businesses were due to the decline in project activities related to the advancement of various projects.

Operating income decreased $2.3 million to $38.3 million in the three months ended September 30, 2013 compared to $40.6 million in the corresponding period of 2012. The decrease in operating income is primarily attributable to lower margins on construction and outage maintenance services when compared to the project mix in the prior period and a lower level of net favorable project close-outs as compared to the prior period. The decrease was partially offset by lower overhead costs and a $3.1 million reduction in selling, general and administrative expenses due to ongoing cost reduction initiatives.

#### Nuclear Operations

Revenues decreased 0.8%, or $2.4 million, to $282.1 million in the three months ended September 30, 2013 compared to $284.5 million in the corresponding period of 2012, primarily attributable to decreased activity in the manufacturing of nuclear components for U.S. Government programs totaling $9.8 million, partially offset by increased activity in our naval nuclear fuel and downblending activities totaling $7.4 million.

Operating income increased $6.9 million to $63.8 million in the three months ended September 30, 2013 compared to $56.9 million in the corresponding period in 2012, primarily due to increased income associated with naval nuclear fuel and downblending activities totaling $4.1 million. Income from the manufacturing of nuclear components for U.S. Government programs increased $2.8 million. These increases are related to improved contract performance associated with contract cost reductions.

#### Technical Services

Revenues decreased 3.1%, or $0.8 million, to $25.2 million in the three months ended September 30, 2013 compared to $26.0 million for the corresponding period of 2012, primarily attributable to lower reimbursable costs at our Naval Reactor decommissioning and decontamination project.

Operating income increased $6.7 million to $18.4 million in the three months ended September 30, 2013 compared to $11.7 million for the corresponding period of 2012. This increase is primarily attributable to improved project performance resulting in higher estimated award fees and $1.8 million of lower selling, general, and administrative expenses compared to the corresponding period of 2012 primarily due to timing of new proposals resulting in lower business development expenses.

#### Nuclear Energy

Revenues decreased 30.0%, or $22.5 million, to $52.5 million in the three months ended September 30, 2013 compared to $75.0 million in the corresponding period of 2012, primarily attributable to decreased activity in our nuclear services and nuclear equipment businesses of $39.2 million associated with the completion of several large contracts that were ongoing in the same period of the prior year. This decline in revenue was partially offset by increased project activities associated with a contract in our nuclear projects business.

Operating income decreased $9.5 million to $0.0 million in the three months ended September 30, 2013 compared to $9.5 million in the corresponding period of 2012, attributable to the decline in revenue noted above and lower margins due to unfavorable project mix compared to the prior period, which was partially offset by $4.0 million of warranty improvements associated with favorable warranty experience.

#### mPower

Operating income increased $2.0 million to a loss of $25.6 million in the three months ended September 30, 2013 compared to a loss of $27.6 million in the corresponding period of 2012. Research and development activities related to the continued development of the B&W mPower™ reactor increased by $13.5 million, offset by the recognition of $16.4 million of the cost-sharing award from the DOE under the Cooperative Agreement as a reduction of research and development costs. There was no cost-sharing award recognized within the corresponding period of 2012. Selling, general, and administrative expenses increased by $0.8 million compared to the corresponding period of 2012.

#### Corporate

Unallocated corporate expenses increased $1.3 million to $8.0 million for the three months ended September 30, 2013, as compared to $6.7 million for the corresponding period in 2012, mainly due to increased corporate business development costs, partially offset by the realization of benefits associated with GCI initiatives.

#### Other Income Statement Items

Other – net increased by $26.8 million to expense of $0.5 million for the three months ended September 30, 2013 as compared to expense of $27.3 million for the corresponding period in 2012, primarily due to the impairment of our USEC investment in the corresponding 2012 period totaling $27.0 million.

#### Provision for Income Taxes

The provision for income taxes increased $17.1 million to $24.4 million, as compared to $7.3 million for the corresponding period of 2012, while our income before provision for income taxes increased $24.9 million. Accordingly, our effective tax rate for the three months ended September 30, 2013 was approximately 30.0% as compared to 12.8% for the three months ended September 30, 2012. The effective tax rate for the three month period in 2013 was higher than the effective tax rate for the comparable period in 2012 primarily due to the 2012 recognition of $25.3 million of previously unrecognized tax benefits for which the statute of limitations had expired and a $27 million impairment charge for which no associated tax benefit was recognized.

RESULTS OF OPERATIONS – NINE MONTHS ENDED SEPTEMBER 30, 2013 VS. NINE MONTHS ENDED SEPTEMBER 30, 2012

#### The Babcock & Wilcox Company (Consolidated)

Consolidated revenues increased 1.7%, or $40.3 million, to $2,466.4 million in the nine months ended September 30, 2013 compared to $2,426.1 million for the corresponding period in 2012 due to increases in revenues from our Nuclear Operations and Power Generation segments totaling $74.2 million and $21.9 million, respectively. These increases were partially offset by decreased revenues in our Nuclear Energy and Technical Services segments totaling $49.7 million and $1.4 million, respectively.

Consolidated operating income decreased $39.9 million to $241.0 million in the nine months ended September 30, 2013 from $280.9 million for the corresponding period in 2012. Operating income for the nine months ended September 30, 2013 includes special charges for restructuring activities totaling $25.5 million related to the initiative we launched to enhance competitiveness, better position B&W for growth, and improve profitability. These costs consist of approximately $15.8 million of employee termination benefits, $8.1 million of consulting and other program administrative costs and $1.6 million of facility consolidation charges due to planned reorganization of manufacturing activities. Operating income in our Power Generation and Nuclear Energy segments decreased by

$36.0 million and $31.3 million, respectively. These decreases were partially offset by an increase in our mPower, Nuclear Operations, and Technical Services segments totaling $34.6 million, $17.2 million and $2.2 million, respectively. We also had higher unallocated corporate expenses totaling $0.9 million for the 2013 period as compared to 2012.

#### Power Generation

Revenues increased 1.6%, or $21.9 million, to $1,359.6 million in the nine months ended September 30, 2013 compared to $1,337.7 million in the corresponding period of 2012. The increase is principally driven by a $46.7 million increase in revenues from our new build environmental equipment business due to ongoing engineering, procurement and construction activities on projects as a result of the previously enacted environmental rules and regulations. Revenues in our new build steam generation systems business decreased $35.2 million, due to decreased activities on waste-to-energy and industrial boiler projects, as well as the impact of revised percentage-of-completion estimates for a project in which we recognized contract losses in the second quarter of 2013. Revenues in our aftermarket services business increased $5.5 million as an increase in boiler-related aftermarket retrofit projects, parts and services offset a decrease in environmental retrofit activity.

Operating income decreased $36.0 million to $102.2 million in the nine months ended September 30, 2013 compared to $138.2 million in the corresponding period of 2012, primarily due to contract losses totaling $30.2 million recorded in the second quarter of 2013 for additional estimated costs to complete a new build steam generation systems project experiencing unforeseen worksite conditions. These losses are in addition to contract losses recorded for this project during the fourth quarter of 2012. The income associated with the increase in revenues is offset by more competitive profit margins and a lower level of net favorable project close-outs than compared to the prior period. These decreases in income were partially offset by decreased overhead costs and a $7.4 million reduction in selling, general and administrative expenses due to ongoing cost reduction initiatives.

#### Nuclear Operations

Revenues increased 9.3%, or $74.2 million, to $874.2 million in the nine months ended September 30, 2013 compared to $800.0 million in the corresponding period of 2012, primarily attributable to increased activity related to the manufacturing of nuclear components for U.S. Government programs totaling $49.2 million and increased activity in our naval nuclear fuel and downblending activities totaling $25.0 million.

Operating income increased $17.2 million to $184.3 million in the nine months ended September 30, 2013 compared to $167.1 million in the corresponding period in 2012, primarily due to increased income associated with naval nuclear fuel and downblending activities of $12.0 million. Income related to manufacturing of nuclear components for U.S. Government programs increased $5.2 million compared to 2012.

#### Technical Services

Revenues decreased 1.8%, or $1.4 million, to $77.9 million in the nine months ended September 30, 2013 compared to $79.3 million for the corresponding period of 2012, primarily attributable to lower reimbursable costs at our Naval Reactor decommissioning and decontamination project.

Operating income increased $2.2 million to $47.8 million in the nine months ended September 30, 2013 compared to $45.6 million for the corresponding period of 2012. This increase is attributable to improved project performance resulting in higher estimated award fees, fees from a new project award, and lower selling, general and administrative expenses of $4.2 million compared to the corresponding period of 2012 primarily due to timing of new proposals resulting in lower business development expenses. These increases were partially offset by costs related to restructuring of a contract and a $1.2 million gain realized in the prior period from the sale of our interest in a joint venture associated with the management and operations of the Strategic Petroleum Reserve.

#### Nuclear Energy

Revenues decreased 21.7%, or $49.7 million, to $179.2 million in the nine months ended September 30, 2013 compared to $228.9 million in the corresponding period of 2012. The decrease in revenues is primarily attributable to decreased activity in our nuclear services and nuclear equipment businesses of $48.8 million associated with the completion of several large contracts that were ongoing in the same period of the prior year and $18.4 million of revenue recorded in the prior year related to the settlement agreement reached with Energy Northwest related to a condenser replacement project at Columbia Generating Station in 2011. This decline in revenue was partially offset by increased project activities associated with an ongoing long-term project in our nuclear projects business.

Operating income decreased $31.3 million to $10.2 million in the nine months ended September 30, 2013 compared to $41.5 million in the corresponding period of 2012, primarily attributable to $18.1 million (net of related expenses) recognized in the nine months ended September 30, 2012 associated with the Energy Northwest settlement agreement discussed above. In addition, operating income also decreased as a result of the completion in 2012 of several large contracts noted above. These decreases were partially offset by $6.1 million of warranty improvements associated with favorable warranty experience.

#### mPower

Operating income increased $34.6 million to a loss of $53.6 million in the nine months ended September 30, 2013 compared to a loss of $88.2 million in the corresponding period of 2012. Research and development activities related to the continued development of the B&W mPower™ reactor increased by $16.2 million, offset by the recognition of $54.2 million of the cost-sharing award from the DOE under the Cooperative Agreement as a reduction of research and development costs. The cost-sharing amount recognized includes $21.5 million of pre-award cost reimbursement for the period from October 2012 through March 2013. Selling, general, and administrative expenses increased by $3.0 million compared to the corresponding period of 2012.

#### Corporate

Unallocated corporate expenses increased $0.9 million to $24.3 million for the nine months ended September 30, 2013, as compared to $23.4 million for the corresponding period in 2012, due to increased corporate development and cyber security upgrade costs, partially offset by the realization of benefits associated with GCI initiatives.

#### Other Income Statement Items

Other – net increased by $25.9 million to income of $1.9 million for the nine months ended September 30, 2013 as compared to expense of $24.0 million for the corresponding period in 2012, primarily due to the impairment of our USEC investment in the 2012 period totaling $27.0 million.

#### Provision for Income Taxes

The provision for income taxes decreased $4.4 million to $70.2 million, as compared to $74.6 million for the corresponding period of 2012, while our income before provision for income taxes decreased $13.5 million. Accordingly, our effective tax rate for the nine months ended September 30, 2013 was approximately 29.0% as compared to 29.2% for the nine months ended September 30, 2012. The effective tax rate for the nine month period in 2013 included certain tax benefits associated with 2012 R&D tax credits and foreign income exclusions related to the provisions of the American Taxpayer Relief Act of 2012, which was enacted on January 2, 2013. The effective tax rate in 2012 was impacted by the recognition of $25.3 million of previously unrecognized tax benefits related to the expiration of the statute of limitations in certain jurisdictions and a $27 million impairment charge for which no associated tax benefit was recognized.

#### Backlog

Backlog is not a measure recognized by generally accepted accounting principles. It is possible that our methodology for determining backlog may not be comparable to methods used by other companies. We generally include expected revenue in our backlog when we receive written confirmation from our customers. We are subject to the budgetary and appropriation cycle of the U.S. Government as it relates to our Nuclear Operations and Technical Services segments. Backlog may not be indicative of future operating results and projects in our backlog may be cancelled, modified or otherwise altered by customers.

|  | September 30, 2013 (Unaudited) (In millions) | December 31, 2012 |
| --- | ---: | ---: |
| Power Generation | $2,176 | $2,483 |
| Nuclear Operations | 2,530 | 2,984 |
| Technical Services | 16 | 4 |
| Nuclear Energy | 186 | 276 |
| mPower | 2 | 2 |
| Total Backlog | $4,910 | $5,749 |

We do not include the value of our unconsolidated joint venture contracts in backlog. These unconsolidated joint ventures are included in our Power Generation, Technical Services, and Nuclear Energy segments.

Of the September 30, 2013 backlog, we expect to recognize revenues as follows:

|  | 2013 (Unaudited) (In approximate millions) | 2014 | Thereafter | Total |
| --- | ---: | ---: | ---: | ---: |
| Power Generation | $345 | $585 | $1,246 | $2,176 |
| Nuclear Operations | 275 | 845 | 1,410 | 2,530 |
| Technical Services | 16 | — | — | 16 |
| Nuclear Energy | 70 | 60 | 56 | 186 |
| mPower | 2 | — | — | 2 |
| Total Backlog | $708 | $1,490 | $2,712 | $4,910 |

At September 30, 2013, Power Generation backlog with the U.S. Government was $39.5 million, all of which was fully funded.

At September 30, 2013, Nuclear Operations backlog with the U.S. Government was $2.5 billion, of which $181.9 million had not yet been funded.

At September 30, 2013, Technical Services backlog with the U.S. Government was $15.4 million, all of which was fully funded.

At September 30, 2013, Nuclear Energy and mPower had no backlog with the U.S. Government.

#### Liquidity and Capital Resources

#### Credit Facility

On June 8, 2012, B&W entered into an Amended and Restated Credit Agreement (the “Credit Agreement”) with a syndicate of lenders and letter of credit issuers, and Bank of America, N.A., as administrative agent which amends and restates our previous Credit Agreement dated May 3, 2010. The Credit Agreement provides for revolving credit borrowings and issuances of letters of credit in an aggregate outstanding amount of up to $700 million and is scheduled to mature June 8, 2017. The proceeds of the Credit Agreement are available for working capital needs and other general corporate purposes. The Credit Agreement includes procedures for additional financial institutions to become lenders, or for any existing lender to increase its commitment thereunder, subject to an aggregate maximum of $1.0 billion for all revolving loan and letter of credit commitments.

The Credit Agreement is guaranteed by substantially all of B&W’s wholly owned domestic subsidiaries. Obligations under the Credit Agreement are secured by first-priority liens on certain assets owned by B&W and the guarantors (other than subsidiaries comprising our Nuclear Operations and Technical Services segments). If the corporate family rating of B&W and its subsidiaries from Moody’s is Baa3 or better (with a stable outlook or better), the corporate rating of B&W and its subsidiaries from Standard & Poor’s is BBB- or better (with a stable outlook or better), and other conditions are met, the liens securing obligations under the Credit Agreement will be released, subject to reinstatement upon the terms set forth in the Credit Agreement.

The Credit Agreement requires only interest payments on a periodic basis until maturity. We may prepay all loans under the Credit Agreement at any time without premium or penalty (other than customary LIBOR breakage costs), subject to certain notice requirements.

The Credit Agreement contains customary financial covenants relating to leverage and interest coverage and includes covenants that restrict, among other things, debt incurrence, liens, investments, acquisitions, asset dispositions, dividends, prepayments of subordinated debt and mergers. At September 30, 2013, we were in compliance with all of the covenants set forth in the Credit Agreement.

Loans outstanding under the Credit Agreement bear interest at our option at either the Eurocurrency rate plus a margin ranging from 1.25% to 2.25% per year or the base rate (the highest of the Federal Funds rate plus 0.50%, the one month Eurocurrency rate plus 1.0%, or the administrative agent’s prime rate) plus a margin ranging from 0.25% to 1.25% per year. The applicable margin for revolving loans varies depending on the credit ratings of the Credit Agreement. Under the Credit Agreement, we are charged a commitment fee on the unused portion of the Credit Agreement and that fee varies between 0.225% and 0.350% per year depending on the credit ratings of the Credit Agreement. Additionally, we are charged a letter of credit fee of between 1.25% and 2.25% per year with respect to the amount of each financial letter of credit issued under the Credit Agreement and a letter of credit fee of between 0.80% and 1.25% per year with respect to the amount of each performance letter of credit issued under the Credit Agreement, in each case depending on the credit ratings of the Credit Agreement. We also pay customary fronting fees and other fees and expenses in connection with the issuance of letters of credit under the Credit Agreement. In connection with entering into the Credit Agreement, we paid upfront fees to the lenders thereunder, and arrangement and other fees to the arrangers and agents of the Credit Agreement. At September 30, 2013, there were no borrowings outstanding and letters of credit issued under the Credit Agreement totaled $146.2 million, resulting in $553.8 million available for borrowings or to meet letter of credit requirements. The applicable interest rate at September 30, 2013 under this facility was 3.75% per year for revolving loans.

Based on the current credit ratings of the Credit Agreement, the applicable margin for Eurocurrency loans is 1.50%, the applicable margin for base rate loans is 0.50%, the letter of credit fee for financial letters of credit is 1.50%, the letter of credit fee for performance letters of credit is 0.875%, and the commitment fee for unused portions of the Credit Agreement is 0.25%. The Credit Agreement does not have a floor for the base rate or the Eurocurrency rate.

The Credit Agreement generally includes customary events of default for a secured credit facility. If any default occurs under the Credit Agreement, or if we are unable to make any of the representations and warranties in the Credit Agreement, we will be unable to borrow funds or have letters of credit issued under the Credit Agreement.

#### Other Arrangements

Certain subsidiaries in our Power Generation segment have credit arrangements with various commercial banks and other financial institutions for the issuance of bank guarantees in association with contracting activity. The aggregate value of all such bank guarantees as of September 30, 2013 was $87.4 million.

B&W and certain of its subsidiaries have jointly executed general agreements of indemnity in favor of surety underwriters relating to surety bonds those underwriters issue in support of some of our contracting activity. As of September 30, 2013, bonds issued and outstanding under these arrangements in support of contracts totaled approximately $435.7 million.

#### Other

In aggregate, our cash and cash equivalents, restricted cash and cash equivalents and investments decreased by $221.1 million to $319.2 million at September 30, 2013 from $540.3 million at December 31, 2012 primarily due to the items discussed below.

Our net cash used in operations was $6.0 million in the nine months ended September 30, 2013, compared to cash used in operations of $79.2 million for the nine months ended September 30, 2012. This decrease in cash used in operations was primarily attributable to reduced pension plan funding.

Our net cash provided by investing activities increased by $143.0 million to cash provided by investing activities of $7.9 million in the nine months ended September 30, 2013 from cash used in investing activities of $135.1 million in the nine months ended September 30, 2012. This increase in net cash provided by investing activities was primarily attributable to higher net purchases of available-for-sale securities in the prior year.

Our net cash used in financing activities increased by $159.9 million to $163.3 million in the nine months ended September 30, 2013 from $3.4 million for the nine months ended September 30, 2012. This increase in net cash used in financing activities was primarily attributable to the repurchase of common shares and dividends paid in the current period.

At September 30, 2013, we had restricted cash and cash equivalents totaling approximately $49.3 million, $3.3 million of which was held in restricted foreign accounts, $3.0 million of which was held for future decommissioning of facilities (which we include in other assets on our condensed consolidated balance sheets), $43.0 million of which was held to meet reinsurance reserve requirements of our captive insurer (in lieu of long-term investments).

At September 30, 2013, we had investments with a fair value of $50.1 million. Our investment portfolio consists primarily of investments in government obligations and short-term commercial paper. Our investments are classified as available-for-sale and are carried at fair value with unrealized gains and losses, net of tax, reported as a component of other comprehensive loss.

#### Foreign Operations

Included in our total unrestricted cash and cash equivalents at September 30, 2013 is approximately $165.7 million held by foreign subsidiaries, which represents approximately 75% of our total unrestricted cash and cash equivalents. In general, these resources are not available to fund our U.S. operations unless the funds are repatriated to the U.S., which would expose us to taxes we presently have not accrued in our results of operations. We presently have no plans to repatriate these funds to the U.S. as the liquidity generated by our U.S. operations is sufficient to meet the cash requirements of our U.S. operations.

See Note 1 in our unaudited condensed consolidated financial statements included in this report for information on new and recently adopted accounting standards.

## Market risk

As filed, 127 characters.

Our exposures to market risks have not changed materially from those disclosed in Item 7A included in Part II of our 2012 10-K.

## Controls and procedures

As filed, 1,981 characters.

As of the end of the period covered by this quarterly report, we carried out an evaluation, under the supervision and with the participation of our management, including our Chief Executive Officer and Chief Financial Officer, of the effectiveness of the design and operation of our disclosure controls and procedures (as that term is defined in Rules 13a-15(e) and 15d-15(e) adopted by the SEC under the Securities Exchange Act of 1934, as amended (the “Exchange Act”)). Our disclosure controls and procedures were developed through a process in which our management applied its judgment in assessing the costs and benefits of such controls and procedures, which, by their nature, can provide only reasonable assurance regarding the control objectives. You should note that the design of any system of disclosure controls and procedures is based in part upon various assumptions about the likelihood of future events, and we cannot assure you that any design will succeed in achieving its stated goals under all potential future conditions, regardless of how remote. Based on the evaluation referred to above, our Chief

Executive Officer and Chief Financial Officer concluded that the design and operation of our disclosure controls and procedures are effective as of September 30, 2013 to provide reasonable assurance that information required to be disclosed by us in the reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the rules and forms of the Securities and Exchange Commission, and such information is accumulated and communicated to management as appropriate to allow timely decisions regarding disclosure. There has been no change in our internal control over financial reporting during the three months ended September 30, 2013 that has materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.

PART II

OTHER INFORMATION

## Risk factors

As filed, 2,414 characters.

In addition to the risk factor below and the other information in this report, the other factors presented in Item 1A. Risk Factors in our annual report on Form 10-K for the year ended December 31, 2012 are some of the factors that could materially affect our business, financial condition or future results.

***Obtaining DOE funding for our B&W mPower technology under the Cooperative Agreement is subject to future government appropriations and the ability of Babcock & Wilcox mPower, Inc. (“B&W mPower”) to comply with the terms of the Cooperative Agreement. B&W mPower’s inability to obtain continued funding under the Cooperative Agreement could impair or delay funding of our SMR research and development activities.***

On April 12, 2013, B&W mPower, our wholly owned subsidiary, entered into a Cooperative Agreement establishing the terms and conditions of a funding award expected to initially total at least $150 million under the DOE SMR Licensing Technical Support Program.

Under the Cooperative Agreement, the DOE will provide incremental cost reimbursements for up to 50%, subject to the overall size of the award, of qualified expenditures incurred in connection with the development and commercialization of the SMR technology. The total estimated qualifying project costs during the five-year term of the funding program are approximately $765.8 million. Only a portion of the funding award has been authorized by the DOE, with the remaining amount subject to future Congressional appropriations. Our ability to obtain continued funding under the Cooperative Agreement is also dependent, in part, on our ability to perform our obligations under the Cooperative Agreement (including achieving specified milestones). In addition, the DOE may elect to not extend funding beyond the end of the then-current budget period (which is expected to occur on or about each anniversary of the date of the Cooperative Agreement). Lastly, either the DOE or B&W mPower may terminate the Cooperative Agreement at any time upon defined notice periods. Such a termination would eliminate the DOE’s obligation to continue funding under the award program. If we do not receive, or experience delays in obtaining, continued award program funding due to lack of Congressional appropriations or the other reasons described above, funding of our related research and development activities could be impaired or delayed.

Filed Nov 12, 2013.
Source: SEC EDGAR, the filing index for accession 0001193125-13-438253. Last ingested by Listed: Nov 14, 2026, 19:14 ET. No prices; not investment advice.