# Trilogy Metals Inc.: Form 10-Q for the period ended May 31, 2017

- Company: [Trilogy Metals Inc.](/companies/tmq.md) (CIK 1543418)
- Form: 10-Q
- Filed: 2017-06-28
- Accepted by EDGAR: Jun 28, 2017, 09:01 ET
- Period: 2017-05-31
- Accession: 0001279569-17-001341
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/1543418/000127956917001341/v469530_10q.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/1543418/000127956917001341/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2017-05-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Net income | 3 months, 2017-03-01 to 2017-05-31 | −$2.4m | us-gaap:NetIncomeLoss |
| Net income | 6 months, 2016-12-01 to 2017-05-31 | −$5.4m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2017-03-01 to 2017-05-31 | −$0.02 | us-gaap:EarningsPerShareBasicAndDiluted |
| Diluted EPS | 6 months, 2016-12-01 to 2017-05-31 | −$0.05 | us-gaap:EarningsPerShareBasicAndDiluted |
| Operating cash flow | 6 months, 2016-12-01 to 2017-05-31 | −$3.6m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 6 months, 2016-12-01 to 2017-05-31 | $16.0k | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | at 2017-05-31 | $14.5m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2017-05-31 | $21.3m | us-gaap:AssetsCurrent |
| Total assets | at 2017-05-31 | $52.4m | us-gaap:Assets |
| Current liabilities | at 2017-05-31 | $1.2m | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2017-05-31 | $11.2m | us-gaap:Liabilities |
| Shareholders' equity | at 2017-05-31 | $41.2m | us-gaap:StockholdersEquity |

## Management's discussion and analysis

As filed, 46,111 characters.

### Cautionary notes

### Forward-looking statements

*This Management’s Discussion and Analysis contains “forward-looking information” and “forward-looking statements” within the meaning of Section 27A of the U.S. Securities Act of 1933, as amended, Section 21E of the U.S. Securities Exchange Act of 1934, as amended (the “Exchange Act”), and Canadian securities laws. These forward-looking statements may include statements regarding outlook, perceived merit of properties, exploration results and budgets, mineral reserves and resource estimates, work programs, capital expenditures, operating costs, cash flow estimates, production estimates and similar statements relating to the economic viability of a project, timelines, strategic plans, statements relating to anticipated activity with respect to the Ambler Mining District Industrial Access Project, including the Company’s plans and expectations relating to its Upper Kobuk Mineral Projects, the adequacy of the Subscription Price to fund the UKMP through to feasibility and permitting of the first mine, the exercise of the option by South32, market prices for precious and base metals, or other statements that are not statements of fact. These statements relate to analyses and other information that are based on forecasts of future results, estimates of amounts not yet determinable and assumptions of management. Statements concerning mineral resource estimates may also be deemed to constitute “forward-looking statements” to the extent that they involve estimates of the mineralization that will be encountered if the property is developed.*

*Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, identified by words or phrases such as “expects”, “is expected”, “anticipates”, “believes”, “plans”, “projects”, “estimates”, “assumes”, “intends”, “strategy”, “goals”, “objectives”, “potential”, “possible” or variations thereof or stating that certain actions, events, conditions or results “may”, “could”, “would”, “should”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.*

*Forward-looking statements are based on a number of material assumptions, including those listed below, which could prove to be significantly incorrect:*

- *assumptions made in the interpretation of drill results, and of the geology, grade, and continuity of the Company’s mineral deposits;*
- *our ability to achieve production at any of the Company’s mineral exploration and development properties;*
- *our expected ability to develop adequate infrastructure and that the cost of doing so will be reasonable;*
- *assumptions that all necessary permits and governmental approvals will be obtained;*
- *estimated capital costs, operating costs, production and economic returns;*
- *estimated metal pricing, metallurgy, mineability, marketability and operating and capital costs, together with other assumptions underlying the Company’s resource and reserve estimates;*
- *continued good relationships with local communities and other stakeholders;*
- *our expectations regarding demand for equipment, skilled labour and services needed for exploration and development of mineral properties;*
- *assumptions regarding the merit of litigation; and*
- *that our activities will not be adversely disrupted or impeded by development, operating or regulatory risks.*

*Forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation:*

- *risks related to the inability to define proven and probable reserves;*
- *risks related to our ability to finance the development of our mineral properties through external financing, strategic alliances, the sale of property interests or otherwise;*
- *none of the Company’s mineral properties are in production or are under development;*
- *uncertainties relating to the assumptions underlying our resource estimates, such as metal pricing, metallurgy, mineability, marketability and operating and capital costs;*
- *risks related to lack of infrastructure including but not limited to the risk whether or not the AMDIAP will receive the requisite permits and, if it does, whether AIDEA will build the AMDIAP;*
- *uncertainty as to whether there will ever be production at the Company’s mineral exploration and development properties;*
- *uncertainty as to estimates of capital costs, operating costs, production and economic returns;*
- *risks related to our ability to commence production and generate material revenues or obtain adequate financing for our planned exploration and development activities;*
- *risks related to future sales or issuances of equity securities decreasing the value of existing Trilogy common shares, diluting voting power and reducing future earnings per share;*
- *risks related to market events and general economic conditions;*
- *uncertainty related to inferred mineral resources;*
- *uncertainty related to the economic projections contained herein derived from the Preliminary Economic Assessment titled “Preliminary Economic Assessment Report on the Arctic Project, Ambler Mining District, Northwest Alaska” dated effective September 12, 2013;*
- *risks related to inclement weather which may delay or hinder exploration activities at its mineral properties;*
- *risks and uncertainties relating to the interpretation of drill results, the geology, grade, and continuity of our mineral deposits;*
- *mining and development risks, including risks related to infrastructure, accidents, equipment breakdowns, labor disputes or other unanticipated difficulties with or interruptions in development, construction or production;*
- *the risk that permits and governmental approvals necessary to develop and operate mines at our mineral properties will not be available on a timely basis or at all;*
- *commodity price fluctuations;*
- *risks related to governmental regulation and permits, including environmental regulation, including the risk that more stringent requirements or standards may be adopted or applied due to circumstances unrelated to the Company and outside of its control;*
- *risks related to the need for reclamation activities on our properties and uncertainty of cost estimates related thereto;*
- *uncertainty related to title to our mineral properties;*
- *our history of losses and expectation of future losses;*
- *risks related to increases in demand for equipment, skilled labor and services needed for exploration and development of mineral properties, and related cost increases;*
- *our need to attract and retain qualified management and technical personnel;*
- *risks related to conflicts of interests of some of our directors;*
- *risks related to potential future litigation;*
- *risks related to the voting power of our major shareholders and the impact that a sale by such shareholders may have on our share price;*
- *risks related to global climate change;*
- *risks related to adverse publicity from non-governmental organizations;*
- *uncertainty as to the volatility in the price of the Company’s shares;*
- *the Company’s expectation of not paying cash dividends;*
- *adverse federal income tax consequences for U.S. shareholders should the Company be a passive foreign investment company;*
- *uncertainty as to our ability to maintain the adequacy of internal control over financial reporting as per the requirements of Section 404 of the Sarbanes-Oxley Act; and*
- *increased regulatory compliance costs, associated with rules and regulations promulgated by the United States Securities and Exchange Commission (the “SEC”), Canadian Securities Administrators, the NYSE-MKT, the TSX, and the Financial Accounting Standards Boards, and more specifically, our efforts to comply with the Dodd-Frank Wall Street Reform and Consumer Protection Act.*

*This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements. Forward-looking statements are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors, including, without limitation, those referred to in Trilogy’s Form 10-K dated February 2, 2017, filed with the Canadian securities regulatory authorities and the SEC, and other information released by Trilogy and filed with the appropriate regulatory agencies.*

*The Company’s forward-looking statements are based on the beliefs, expectations, and opinions of management on the date the statements are made, and the Company does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations or opinions should change, except as required by law. For the reasons set forth above, investors should not place undue reliance on forward-looking statements.*

### Cautionary note to United States investors

### Reserve and resource estimates

*This Management’s Discussion and Analysis has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of U.S. securities laws. Unless otherwise indicated, all resource and reserve estimates included in this Management’s Discussion and Analysis have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources and Mineral Reserves. NI 43-101 is a rule developed by the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Canadian standards, including NI 43-101, differ significantly from the requirements of the SEC, and resource and reserve information contained herein may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term “resource” does not equate to the term “reserves”. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. The SEC’s disclosure standards normally do not permit the inclusion of information concerning “measured mineral resources”, “indicated mineral resources” or “inferred mineral resources” or other descriptions of the amount of mineralization in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the SEC. Investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted into reserves. U.S. investors should also understand that “inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Under Canadian rules, estimated “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an “inferred mineral resource” exists or is economically or legally mineable. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute “reserves” by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of “reserves” are also not the same as those of the SEC, and reserves reported by the Company in compliance with NI 43-101 may not qualify as “reserves” under SEC standards. Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.*

### General

This Management’s Discussion and Analysis (“MD&A”) of Trilogy Metals Inc. (“Trilogy”, “Trilogy Metals”, “the Company” or “we”) is dated June 27, 2017 and provides an analysis of our unaudited interim financial results for the quarter ended May 31, 2017 compared to the quarter ended May 31, 2016.

The following information should be read in conjunction with our May 31, 2017 unaudited interim consolidated financial statements and related notes which were prepared in accordance with United States generally accepted accounting principles (“U.S. GAAP”). The MD&A should also be read in conjunction with our audited consolidated financial statements and related notes for the year ended November 30, 2016. A summary of the U.S. GAAP accounting policies are outlined in note 2 of the audited consolidated financial statements and note 2 of the interim consolidated financial statements. All amounts are in United States dollars unless otherwise stated. References to “Canadian dollars” and “C$” and “CDN$” are to the currency of Canada and references to “U.S. dollars”, “$” or “US$” are to the currency of the United States.

Andrew W. West, P.Geo., an employee and Exploration Manager for Trilogy, is a Qualified Person under National Instrument 43-101 - *Standards of Disclosure for Mineral Projects (“*NI 43-101”), and has approved the scientific and technical information in this MD&A.

Trilogy’s shares are listed on the Toronto Stock Exchange (“TSX”) and the NYSE-MKT under the symbol “TMQ”. Additional information related to Trilogy, including our annual report on Form 10-K, is available on SEDAR at www.sedar.com and on EDGAR at www.sec.gov.

### Description of business

We are a base metals exploration company focused on exploring and developing our mineral holdings in the Ambler mining district located in Alaska, U.S.A. We conduct our operations through a wholly-owned subsidiary, NovaCopper US Inc. which is doing business as Trilogy Metals US (“NovaCopper US”). Our Upper Kobuk Mineral Projects, (“UKMP” or “UKMP Projects”), consist of: i) the 100% owned Ambler lands which host the Arctic copper-zinc-lead-gold-silver Project; and ii) the Bornite lands being explored under a collaborative long-term agreement with NANA Regional Corporation, Inc. (“NANA”), a regional Alaska Native Corporation, which host the Bornite carbonate-hosted copper Project.

### Project activities

#### South32 Option Agreement

On April 10, 2017, Trilogy and NovaCopper US entered into an Option Agreement to form a Joint Venture with South32 Group Operations Pty Ltd. (“South32”) on the UKMP (“Option Agreement”). Under the terms of the Option Agreement, NovaCopper US granted South32 the right to form a 50/50 joint venture to hold all of NovaCopper US’ Alaskan assets. Upon exercise of the option, NovaCopper US will transfer its Alaskan assets, including the UKMP, and South32 will contribute a minimum of $150 million, to a newly formed and jointly held, limited liability company.

To maintain the option in good standing, South32 is required to fund a minimum of $10 million per year for up to a three year period, which funds will be used to execute a mutually agreed upon program at the UKMP. The funds provided by South32 may only be expended in accordance with an approved program by a newly formed technical committee with equal representation from Trilogy and South32. South32 may exercise its option at any time over the next three years to enter into the 50/50 joint venture. To subscribe for 50% of the JV, South32 will contribute a minimum of $150 million, plus any amounts NovaCopper US spends at the Arctic Project over the next three years, to a maximum of $5 million per year (the “Subscription Price”), less an amount of the initial funding contributed by South32.

#### Option Funding Phase

Provided that all the exploration data and information has been made available to South32 by no later than December 31 of each year, South32 must decide by the end of January of the following year whether; (i) to fund a further tranche of a minimum of $10 million, or (ii) to withdraw and not provide any further annual funding. If the election to fund a further tranche is not made in January, South32 has until the end of March to exercise the option to form the LLC and make the subscription payment. If South32 elects to exercise the option, the Subscription Price less certain deductions for initial funding shall be paid in one tranche within 45 business days. Should South32 not make its annual minimum payment or elect to withdraw, the option will lapse and South32 will have no claim to ownership or the funds it had already spent. The option payment for the first year has been paid by South32 to NovaCopper US and the funds will be used for a $10 million exploration program at the Bornite Project to be executed in 2017.

#### Subscription Funding Phase

At any time during the option funding phase of the agreement, South32 may elect to subscribe for a 50% interest in a newly formed LLC which will take transfer of, and hold, NovaCopper US’ Alaskan Assets. As part of the Subscription Price, South32 will match any spending expended by us at the Arctic Project over the next 3 years, to a cumulative maximum of $15 million. Depending on when the option is exercised, certain amounts of the Initial Funding will be deducted from the Subscription Price.

Trilogy estimates that the Subscription Price will fund the UKMP through feasibility and the permitting of the first mine to be developed in the Ambler mining district. Once the full amount of the subscription payment of approximately $150 million is expended, the parties will contribute funding pro rata, as contemplated by the operating agreement which will govern the LLC (the “LLC Agreement”). The LLC Agreement anticipates a General Manager, Chief Financial Officer and Chief Operating and Technical Officer to be appointed by the LLC’s Board, which will have equal representation from Trilogy and South32.

As the initial option payments are credited against the future subscription price upon exercise, we have accounted for the payment received as deferred consideration. At such time as the option is exercised, the initial payments received to that date will be recognized as part of the consideration received for our contribution of the Alaska assets, including the UKMP, into the joint venture. If South 32 withdraws from the Option Agreement, the consideration will be recognized in the statement of loss at that time.

#### Arctic Project

In April 2017, we released an updated resource estimate for the Arctic Project in preparation for the kick-off of a pre-feasibility study (the “Arctic PFS”) on the Arctic Project. We also announced the results of a metallurgical test work program using sample material from the Arctic deposit collected during the 2016 field season. This metallurgical test program was carried out as a follow-on program to confirm previous metallurgical results completed in 2012 and in support of advancing the project to PFS. The results demonstrate that excellent recoveries and clean concentrates of copper and zinc can be generated from the polymetallic copper-lead-zinc-gold-silver ores at Arctic. Concentrates of copper recovered an average of 91.7% of the copper and formed a concentrate averaging 28.7% copper metal. Concentrates of zinc recovered an average of 87.8% of the zinc and formed a concentrate averaging 60% zinc metal. Neither concentrate contains significant deleterious penalty metals and are considered excellent quality by world standards. The lead concentrate contains significant precious metals and is still undergoing further test work to determine optimal recoveries for lead, gold and silver.

In early June 2017, we announced the engagement of Ausenco Engineering Canada Inc. to prepare the Arctic PFS technical report anticipated to be complete in Q1, 2018. The Company has also engaged Amec Foster Wheeler to complete mine planning and SRK Consulting (Canada) Inc. to complete tailings and waste design, hydrology and environmental studies.

The field program for the Arctic PFS began in June and will continue through early August at the UKMP. We will be completing geotechnical drilling, hydrology installations, and test pits for site facility locations and mine design, and geophysical ground surveys to evaluate ground conditions. A significantly expanded environmental baseline program will be underway in 2017 to further the ongoing baseline data collection at the Arctic Project. Aquatics, avian and large mammal surveys will be continued and expanded, water balance programs will be expanded, and collection of data from the existing meteorological station will continue. The timing of the field program will provide the information required for completion of the PFS anticipated to be in Q1 2018.

#### Bornite Project

We are executing a $10 million program at the Bornite Project, funded by South32 per the Option Agreement. This year’s exploration at Bornite was approved by a joint Trilogy-South32 Technical Committee and is focused on drilling the extensions of mineralization last drilled by us in 2013.

During the 2013 exploration program at the Bornite Project, we completed 8,142 meters of drilling with 4,684 meters drilled at the Ruby Creek zone (a potential open pit resource) and 3,458 meters drilled at the South Reef zone (a potential underground resource). A series of press releases highlighted results of the drilling at Bornite starting with the Company’s press release dated October 7, 2013 where we highlighted drill hole RC13-224 which intersected two mineralized intervals, starting at 513.3 meters and ending at 754.6 meters (241.3 meter interval), for a combined 236.0 meter composite interval with a weighted average grade of 1.90% copper, and comprised of 229.4 meters at a grade of 1.73% copper and 6.6 meters at a grade of 7.70% copper.

This year’s exploration program at Bornite is one of the larger programs in the history of drilling at the Upper Kobuk Mineral Projects. With an approved budget of $10 million, we will be drilling approximately 12,000 meters at Bornite this field season to test the extension of the mineralization from the drill holes from our 2013 drill campaign along with a ground gravity survey, continuation of hydrology data collection and initiating metallurgy and acid based accounting for Bornite.

Drilling at the Bornite Project began in early June and is expected to be finished in late September with results released throughout the fall.

#### Ambler Mining District Industrial Access Project

In March 2017, we announced that the permitting process had advanced on the Ambler Mining District Industrial Access Project (“AMDIAP”) with the publishing of the Notice of Intent (“NOI”) by the Bureau of Land Management (“BLM”) on February 28, 2017 which is a significant milestone in the permitting process. The NOI initiates the permitting process under the National Environmental Policy Act (“NEPA”) for the preparation of an Environmental Impact Statement (“EIS”) on the AMDIAP. The BLM is the lead Federal agency for the EIS. This notice initiated the public scoping process for the EIS with comments due by May 30, 2017.

The Notice of Intent states that the various federal and state agencies intend to prepare an EIS for Federal authorization to construct and operate an approximately 211-mile long industrial access road in the southern Brooks Range foothills of Alaska, originating at the Dalton Highway and ending at the Ambler River and providing access to the Ambler Mining District. The BLM has announced the beginning of the EIS scoping process to solicit public comments and identify issues. The BLM intends to coordinate the development of the EIS with the National Park Service (“NPS”), which is in accordance with the Alaska National Interest Lands Conservation Act (“ANILCA”). The NPS is developing a separate environmental and economic analysis solely for the purpose of determining the most desirable route for that portion of the proposed road right-of-way that would cross the Gates of the Arctic National Preserve. More information on the AMDIAP and the ANILCA permitting process is available on AIDEA’s website at www.ambleraccess.org, which website is not incorporated by reference.

The AMDIAP is anticipated to provide surface access to the Ambler Mining District, long known to contain significant deposits of copper, lead, zinc, gold and silver and specifically including the Company’s UKMP.

We are also working closely with AIDEA to amend the Memorandum of Understanding (“MOU”), originally signed in 2013, as the industrial road route has been selected and permitting documents have been submitted to the relevant US federal agencies. We will work with AIDEA, as the proponent for the AMDIAP, to have direct input into the permitting process for the road and the ability to attend meetings with the BLM, as the lead federal agency for the EIS process.

### Corporate developments

#### Annual General Meeting

The Annual General Meeting was held on May 8, 2017. We are pleased to report all directors standing for nomination were resoundingly elected by the Shareholders of the Company.

### Outlook

Our 2017 program has a total budget of $17.1 million with $7.1 million to be expended during the fiscal year to advance the Arctic Project to pre-feasibility and $10.0 million for the exploration program at the Bornite Project. The Arctic PFS will be supported by information collected during the 2015 and 2016 field seasons as well as additional information to be collected during the 2017 summer field program. The completion of the 2017 field program will complete a staged three-year site investigation program where the first two years focused almost exclusively on collecting data in and around the proposed Arctic open-pit, and the third year focuses on infrastructure and mine design. The Arctic PFS is anticipated to be completed in Q1 2018.

The exploration program at the Bornite Project is an opportunity to potentially expand the resource at Bornite by drilling the extensions of mineralization last drilled by the Company in 2013. Approximately 12,000 meters will be drilled at Bornite which drilling will be focused entirely on testing the size and depth of the extension of the known deposit. Bornite currently has 5.5 billion pounds of copper inferred resource and 913 million pounds of copper indicated resource. Drilling at the Bornite Project commenced in early June and will continue through to late September with drill results anticipated to be released late in the summer and continue into the fall.

### Property review

Our principal assets, the UKMP Projects, are located in the Ambler mining district in Northwest Alaska. Our UKMP Projects comprise approximately 352,943 acres (142,831 hectares) consisting of the Ambler and Bornite lands.

### Arctic Project

The Ambler lands, which host a number of deposits, including the high-grade copper-zinc-lead-gold-silver Arctic Project, and other mineralized targets within a 100 kilometer long volcanogenic massive sulfide (“VMS”) belt, are owned by NovaCopper US. The Ambler lands are located in Northwestern Alaska and consist of 112,058 acres (45,348 hectares) of Federal patented mining claims and State of Alaska mining claims, within which VMS mineralization has been found.

We have recorded the Ambler lands as a mineral property with acquisition costs capitalized and exploration costs expensed in accordance with our accounting policies.

### Bornite Project

On October 19, 2011, NovaCopper US and NANA signed a collaborative agreement to explore and develop the Ambler mining district. Under the Exploration Agreement and Option to Lease (the “NANA Agreement”), we acquired, in exchange for, among other things, a $4.0 million cash payment to NANA, the exclusive right to explore the Bornite property and lands deeded to NANA through the Alaska Native Claims Settlement Act (“ANCSA”), located adjacent to the Arctic Project, and the non-exclusive right to access and entry onto NANA’s lands. The agreement establishes a framework for any future development of either the Bornite Project or the Arctic Project. Both projects are included as part of a larger area of interest set forth in the NANA Agreement. The agreement with NANA created a total land package incorporating our Ambler lands with the adjacent Bornite and ANCSA lands with a total area of approximately 352,900 acres (142,831 hectares).

Upon the decision to proceed with development of a mine within the area of interest, NANA maintains the right to purchase an ownership interest in the mine equal to between 16%-25% or retain a 15% net proceeds royalty which is payable after we have recovered certain historical costs, including capital and cost of capital. Should NANA elect to purchase an ownership interest in the mine, consideration will be payable based on the elected percentage purchased and all the costs incurred on the properties less $40.0 million, not to be less than zero. The parties would form a joint venture and be responsible for all future costs incurred in connection with the mine, including capital costs of the mine, based on each party’s pro-rata share.

NANA would also be granted a net smelter return royalty between 1% and 2.5% upon the execution of a mining lease or a surface use agreement, the amount of which is determined by the particular area of land from which production originates.

We have accounted for the Bornite property as a mineral property with acquisition costs capitalized and exploration costs expensed in accordance with our accounting policies.

### Summary of results

#### in thousands of dollars,

#### except for per share amounts

| Three months ended Selected expenses | May 31, 2017 $ | May 31, 2016 $ | Six months ended May 31, 2017 $ | May 31, 2016 $ |
| --- | ---: | ---: | ---: | ---: |
| General and administrative | 407 | 373 | 785 | 719 |
| Mineral properties expense | 1,297 | 457 | 1,936 | 990 |
| Professional fees | 193 | 210 | 318 | 346 |
| Salaries | 224 | 257 | 466 | 469 |
| Salaries – stock-based compensation | 106 | 116 | 499 | 398 |
| Unrealized (gain) loss on held for trading investments | (70) | - | 1,169 | - |
| Loss from continuing operations for the period | 2,390 | 1,460 | 5,387 | 2,983 |
| Loss from discontinued operations for the period | - | 187 | - | 359 |
| Loss and comprehensive loss for the period | 2,390 | 1,647 | 5,387 | 3,342 |
| Basic and diluted loss per common share | $0.02 | $0.01 | $0.05 | $0.03 |

For the three months ended May 31, 2017, Trilogy reported a net loss of $2.4 million (or $0.02 basic and diluted loss per common share) compared to a net loss of $1.6 million for the corresponding period in 2016 (or $0.01 basic and diluted loss per common share). This variance was primarily due to the size of the field programs at the UKMP in 2017 as well as the timing of the program. An increase of $840,000 of mineral property expenses occurred during the three months ended May 31, 2017 compared to the three months ended May 31, 2016. In 2017, the combined Arctic and Bornite field program began with drilling by early June compared to 2016 where the field program kicked off in early July. This earlier start resulted in an increased mineral property expense during the second quarter of 2017. Additionally, in preparation for the Arctic PFS study, an increased level of ongoing technical studies was occurring during the three months ended May 31, 2017 compared to the corresponding period in 2016.

Trilogy recognized a gain on held for trading investments of $70,000 during the three months ended May 31, 2017 due to an appreciation in the share price of Gold Mining Inc. (“GMI”). The investments consist of common shares and warrants in GMI acquired as consideration for the sale of Sunward Investments Limited (“Sunward”) and its Titiribi gold-copper exploration project in Colombia. Other minor differences noted for the comparable periods were i) a small increase in general and administrative expenses to support the increased field program at the UKMP; ii) a small decrease in professional fees due to lower activity in the second quarter of 2017 compared to 2016; and iii) a small decrease in salaries due to the continued depreciation of the Canadian dollar..

The basic and diluted loss per common share of $0.02 for the three months ended May 31, 2017 is increased from the basic and diluted loss per common share of $0.01 for the three months ended May 31, 2016 due to the increased loss as described above.

For the six months ended May 31, 2017, Trilogy reported a net loss of $5.4 million (or $0.05 basic and diluted loss per common share) compared to a net loss of $3.3 million for the corresponding period in 2016 (or $0.03 basic and diluted loss per common share). This variance was primarily due to an unrealized loss on investments on the GMI securities of $1.2 million classified as held for trading for which movements in the fair value of the investments are recorded through the statement of loss. There are no comparable amounts for the six months ended May 31, 2016 as the Company acquired the investments in September 2016.

Adjusting for the unrealized loss on held for trading investments, there is a loss from continued operations of $4.2 million for the six months ended May 31, 2017 compared to the loss from continuing operations of $3.0 million for the six months ended May 31, 2016. The remaining increase is due almost entirely to an increase of $1.0 in mineral properties expenses. We incurred $1.9 million in mineral properties expense for the six months ended May 31, 2017 compared to $1.0 million for the six months ended May 31, 2016. The increase in mineral property expenses in 2017 is due to the significantly increased size of the 2017 field program compared to the 2016 program as discussed above. The increase is also attributable to several ongoing engineering studies, specifically an updated 3D geology model and resource estimate for the Arctic deposit, metallurgical test programs on the Arctic and Bornite Projects, completion of a pre-feasibility level slope geotechnical and hydrology study on the Arctic deposit, and a review of the hydrogeological conditions at the Bornite property. Waste characterization is also continuing on the Arctic Project which began in 2016. General and administrative expenses, salaries, stock-based compensation, and professional fees continue to be at comparable levels in the periods presented.

The basic and diluted loss per common share of $0.05 for the six months ended May 31, 2017 is increased from the basic and diluted loss per common share of $0.03 for the six months ended May 31, 2016 due to the increased loss as described above.

### Selected financial data

### Quarterly information

#### in thousands of dollars,

#### except per share amounts

|  | Q2 2017 05/31/17 $ | Q1 2017 02/28/17 $ | Q4 2016 11/30/16 $ | Q3 2016 08/31/16 $ | Q2 2016 05/31/16 $ | Q1 2016 02/29/16 $ |  | Q4 2015 11/30/15 $ | Q3 2015 08/31/15 $ |
| --- | ---: | ---: | ---: | ---: | ---: | --- | ---: | ---: | ---: |
| Interest and other income | **12** | 11 | 10 | 15 | 18 |  | 18 | 12 | 8 |
| Mineral property expenses | **1,297** | 639 | 1,430 | 2,617 | 458 |  | 532 | 779 | 2,771 |
| Income (loss) from discontinued operations for the period | **-** | - | 4,561 | (352) | (187) |  | (172) | (200) | (198) |
| Earnings (loss) for the period | **(2,390)** | (2,996) | 2,025 | (3,544) | (1,648) |  | (1,695) | (2,090) | (4,162) |
| Earnings (loss) per common share – basic and diluted | **(0.02)** | (0.03) | 0.02 | (0.03) | (0.02) | ($ | 0.02) | (0.02) | (0.04) |

Factors that can cause fluctuations in our quarterly results include the length of the exploration field season at the properties, the type of program conducted, stock option vesting, and issuance of shares. Other factors that have caused fluctuations in the quarterly results that would not be expected to re-occur include the acquisition and disposition of Sunward and financing activities.

During the third quarter of 2015, we incurred mineral property expenses of $2.8 million as we completed our drilling program. We also incurred $0.2 million of discontinued operation costs operating Sunward. As a result, our loss for the third quarter ended August 31, 2015 is higher compared to previous quarter losses. Our net loss for the fourth quarter of 2015 of $2.1 million consists of $0.8 million in mineral property expenses incurred for assay costs and engineering studies conducted in the fall as well as $0.2 million in discontinued operation costs from Sunward.

Our loss for the first quarter ended February 29, 2016 is comparable to typical first quarter losses in that it consists mainly of mineral property expenses relating to engineering studies completed in advance of the 2016 field program. The loss is increased slightly due to costs related to operating Sunward of $0.2 million when compared to periods where Trilogy did not own Sunward. During the second quarter of 2016, we incurred $0.5 million in mineral property expenses due to field season starting up in the last month of the second quarter and $0.2 million in discontinued operations relating to Sunward. During the third quarter of 2016, we incurred mineral property expenses of $2.6 million as we completed our drilling program. As a result, our loss for the third quarter ended August 31, 2016 is higher compared to previous quarter losses and consistent with the spending in the third quarter of 2015. We recognized earnings for the fourth quarter of 2016 of $2.0 million due to the gain on the sale of Sunward. Adjusted for the discontinued operations, the fourth quarter periods are substantially comparable.

Our loss for the first quarter ended February 28, 2017 of $3.0 million is significantly increased compared to prior quarterly periods due to an unrealized loss on held for trading investments of $1.2 million. The investments are classified as held for trading for which changes in the fair value of the investments are recorded through the statement of loss. Our loss for the second quarter ended May 31, 2017 of $2.4 million is significantly increased from the comparable period due to a significant increase is the size of our field program resulting in increased mineral property expenses of $1.3 million.

### Liquidity and capital resources

At May 31, 2017, we had $14.5 million in cash and cash equivalents. We expended $3.6 million on operating activities during the six months ended May 31, 2017 compared with $3.1 million for operating activities for the same period in 2016. A majority of cash spent on operating activities during all periods was expended on mineral property expenses, general and administrative, salaries and professional fees. As at May 31, 2017, the Company continues to manage its cash expenditures and management believes that the working capital available is sufficient to meet its operational requirements for the next year. Management does expect to monetize its investments by selling shares of GMI in the next three to six months to assist in meeting its operational requirements. Future financings are anticipated through the sale of investments, equity financing, the exercise of mineral properties option, debt financing, convertible debt, or other means.

During the six months ended May 31, 2017, we received $10.0 million in funding from South32 for the exploration program at the Bornite Project which is categorized as an investing activity as the funds are being utilized on the UKMP. During the six months ended May 31, 2017, we generated $0.9 million in proceeds from the sale of investments. The proceeds were used for general operating activities. There was no comparable amount from investing activities in 2016 as we acquired the investments in September 2016.

We received $10.0 million from South32 for the first year program under the Option Agreement. As at May 31, 2017, the Company held $9.3 million in a segregated bank account for spending on the approved year 1 program at the Bornite Project. The Company is responsible for the disbursement of these funds in accordance with the approved program and budget and accordingly has not classified the funds as restricted cash.

During the six months ended May 31, 2017, $0.1 million was used in financing activities to pay statutory employee withholding taxes on Restricted Share Units that vested. There were no comparable amounts from financing activities in 2016.

### Contractual obligations

Contractually obligated cash flow requirements as at May 31, 2017 are as follows.

#### in thousands of dollars

|  | Total $ | \< 1 Year $ | 1–2 Years $ | 2–5 Years $ | Thereafter $ |
| --- | ---: | ---: | ---: | ---: | ---: |
| Accounts payable and accrued liabilities | 1,200 | 1,200 | - | - | - |
| Office lease | 1,282 | 77 | 164 | 534 | 507 |
|  | **2,482** | **1,277** | **164** | **534** | **507** |

On February 21, 2017, the Company entered into a lease for office space effective July 1, 2017 for a period of seven years with a total commitment of $1.3 million.

### Off-balance sheet arrangements

We have no material off-balance sheet arrangements. The Company has lease commitments for office spaces with a remaining total commitment of $1.3 million.

### Outstanding share data

At June 27, 2017, we had 105,554,489 common shares issued and outstanding. At June 27, 2017, we had outstanding 6,521,740 warrants with an exercise price of $1.60 each, 7,399,326 stock options with a weighted-average exercise price of $0.52, 997,631 DSUs, 600,002 RSUs, and 20,685 NovaGold DSUs for which the holder is entitled to receive one common share for every six NovaGold shares received. For additional information on NovaGold Arrangement Options and NovaGold DSUs, please refer to note 6 in our May 31, 2017 interim consolidated financial statements. Upon exercising all of the forgoing convertible securities, the Company would be required to issue aggregate of 15,522,146 common shares.

### New accounting pronouncements

Certain recent accounting pronouncements have been included under note 2 in our May 31, 2017 unaudited interim consolidated financial statements

### Critical accounting estimates

The most critical accounting estimates upon which our financial status depends are those requiring estimates of the recoverability of our capitalized mineral properties, impairment of long-lived assets, and valuation of stock-based compensation.

### Mineral properties and development costs

All direct costs related to the acquisition of mineral property interests are capitalized. The acquisition of title to mineral properties is a complicated and uncertain process. The Company has taken steps, in accordance with industry standards, to verify the title to mineral properties in which it has an interest. Although the Company has made efforts to ensure that legal title to its mining assets is properly recorded, there can be no assurance that such title will be secured indefinitely.

### Impairment of long-lived assets

Management assesses the possibility of impairment in the carrying value of its long-lived assets whenever events or circumstances indicate that the carrying amounts of the asset or asset group may not be recoverable. Significant judgments are made in assessing the possibility of impairment. Management considers several factors in considering if an indicator of impairment has occurred, including but not limited to, indications of value from external sources, significant changes in the legal, business or regulatory environment, and adverse changes in the use of physical condition of the asset. These factors are subjective and require consideration at each period end. If an indicator of impairment is determined to exist, management calculates the estimated undiscounted future net cash flows relating to the asset or asset group using estimated future prices, mineral resources, and operating, capital and reclamation costs. When the carrying value of an asset exceeds the related undiscounted cash flows, the asset is written down to its estimated fair value, which is usually determined using discounted future cash flows. Management’s estimates of mineral prices, mineral resources, foreign exchange rates, production levels and operating capital and reclamation costs are subject to risk and uncertainties that may affect the determination of the recoverability of the long-lived asset.

### Stock-based compensation

Compensation expense for options granted to employees, directors and certain service providers is determined based on estimated fair values of the options at the time of grant using the Black-Scholes option pricing model, which takes into account, as of the grant date, the fair market value of the shares, expected volatility, expected life, expected forfeiture rate, expected dividend yield and the risk-free interest rate over the expected life of the option. The use of the Black-Scholes option pricing model requires input estimation of the expected life of the option, volatility, and forfeiture rate which can have a significant impact on the valuation model, and resulting expense recorded.

### Additional information

Additional information regarding the Company, including our annual report on Form 10-K, is available on SEDAR at www.sedar.com and EDGAR at www.sec.gov and on our website at www.trilogymetals.com. Information contained on our website is not incorporated by reference.

## Market risk

As filed, 3,401 characters.

Our financial instruments consist of cash and cash equivalents, accounts receivable, deposits, investments, and accounts payable and accrued liabilities. The fair value of the financial instruments approximates their carrying value due to the short-term nature of their maturity. Our financial instruments initially measured at fair value and then held at amortized cost include cash and cash equivalents, accounts receivable, deposits, and accounts payable and accrued liabilities. Our investments are held for trading and are marked-to-market at each period end with changes in fair value recorded to the statement of loss. The South32 purchase option is a derivative financial liability measured at fair value with changes in value recorded to the statement of loss.

(e) Currency risk

Currency risk is the risk of a fluctuation in financial asset and liability settlement amounts due to a change in foreign exchange rates. We operate in the United States and Canada. Our exposure to currency risk at May 31, 2017 is limited to the Canadian dollar consisting of cash of CDN$1,471,000, accounts receivable of CDN$125,000, deposit amounts of CDN$116,000, investments of CDN$8,106,000 and accounts payable of CDN$442,000. Based on a 10% change in the US-Canadian exchange rate, assuming all other variables remain constant, the Company’s net loss would change by approximately $631,000.

(f) Credit risk

Credit risk is the risk of an unexpected loss if a customer or third party to a financial instrument fails to meet its contractual obligations. We hold cash and cash equivalents with Canadian Chartered financial institutions. Our accounts receivable consist of GST receivable from the Federal Government of Canada and other receivables for recoverable expenses. Our exposure to credit risk is equal to the balance of cash and cash equivalents and accounts receivable as recorded in the financial statements.

(g) Liquidity risk

Liquidity risk is the risk that we will encounter difficulties raising funds to meet our financial obligations as they fall due. We are in the exploration stage and do not have cash inflows from operations; therefore, we manage liquidity risk through the management of the capital structure and financial leverage. Future financings may be obtained through debt financing, equity financing, sales of investments, convertible debt, exercise of options, or other means. Continued operations are dependent on our ability to obtain additional financing or to generate future cash flows. Our contractually obligated cash flow is disclosed under the section titled “Contractual obligations.” Please see further discussion of our liquidity under “Liquidity and capital resources”

(h) Interest rate risk

Interest rate risk is the risk that the fair value or future cash flows of a financial instrument will fluctuate because of changes in market interest rates. We are exposed to interest rate risk with respect to interest earned on cash and cash equivalents. Based on balances as at May 31, 2017, a 1% change in interest rates would result in a change in net loss of $0.1 million, assuming all other variables remain constant.

As we are currently in the exploration phase none of our financial instruments are exposed to commodity price risk; however, our ability to obtain long-term financing and its economic viability could be affected by commodity price volatility.

## Controls and procedures

As filed, 1,617 characters.

Management, with the participation of our President and Chief Executive Officer and Chief Financial Officer, evaluated the effectiveness of our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) of the Exchange Act) as of May 31, 2017. On the basis of this review, our Chief Executive Officer and Chief Financial Officer concluded that our disclosure controls and procedures are effective to ensure that the information we are required to disclose in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the rules and forms of the SEC and to ensure that information required to be disclosed in the reports filed or submitted under the Exchange Act is accumulated and communicated to our management, including our President and Chief Executive Officer and Chief Financial Officer, as appropriate to allow timely decisions regarding required disclosure.

There have not been any changes in the Company’s internal control over financial reporting (as defined in Rules 13a-15(f) and 15d-15(f) promulgated by the SEC under the Exchange Act) during the Company’s most recently completed fiscal quarter that have materially affected, or are reasonably likely to materially affect the Company’s internal control over financial reporting. Any system of internal control over financial reporting, no matter how well designed, has inherent limitations. Therefore, even those systems determined to be effective can provide only reasonable assurance with respect to financial statement preparation and presentation.

## Risk factors

As filed, 452 characters.

Trilogy and its future business, operations and financial condition are subject to various risks and uncertainties due to the nature of its business and the present stage of exploration of its mineral properties. Certain of these risks and uncertainties are under the heading “Risk Factors” under Trilogy’s Form 10-K dated February 2, 2017, which is available on SEDAR at www.sedar.com, EDGAR at www.sec.gov and on our website at www.trilogymetals.com.

Filed Jun 28, 2017.