# Energy Fuels Inc: Form 10-K for the period ended Dec 31, 2020

- Company: [Energy Fuels Inc](/companies/uuuu.md) (CIK 1385849)
- Form: 10-K
- Filed: 2021-03-22
- Accepted by EDGAR: Mar 22, 2021, 06:31 ET
- Period: 2020-12-31
- Accession: 0001385849-21-000027
- Inline XBRL: yes
- Main document: https://www.sec.gov/Archives/edgar/data/1385849/000138584921000027/efr-20201231.htm
- All documents and exhibits: https://www.sec.gov/Archives/edgar/data/1385849/000138584921000027/

## Figures reported in this filing

Standardized XBRL line items for the period ended 2020-12-31.

| Line item | Period | Value | XBRL concept |
| --- | --- | ---: | --- |
| Revenue | 3 months, 2020-10-01 to 2020-12-31 | $384.0k | us-gaap:Revenues |
| Revenue | 12 months, 2020-01-01 to 2020-12-31 | $1.7m | us-gaap:Revenues |
| Cost of revenue | 12 months, 2020-01-01 to 2020-12-31 | $0 | us-gaap:CostOfRevenue |
| Gross profit | 3 months, 2020-10-01 to 2020-12-31 | $384.0k | us-gaap:GrossProfit |
| Operating income | 12 months, 2020-01-01 to 2020-12-31 | −$24.6m | us-gaap:OperatingIncomeLoss |
| Interest expense | 12 months, 2020-01-01 to 2020-12-31 | $952.0k | us-gaap:InterestExpense |
| Income tax | 12 months, 2020-01-01 to 2020-12-31 | $0 | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months, 2020-10-01 to 2020-12-31 | −$5.1m | us-gaap:NetIncomeLoss |
| Net income | 12 months, 2020-01-01 to 2020-12-31 | −$27.9m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months, 2020-10-01 to 2020-12-31 | −$0.04 | us-gaap:EarningsPerShareBasicAndDiluted |
| Operating cash flow | 12 months, 2020-01-01 to 2020-12-31 | −$32.2m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 12 months, 2020-01-01 to 2020-12-31 | $627.0k | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | at 2020-12-31 | $20.2m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | at 2020-12-31 | $52.5m | us-gaap:AssetsCurrent |
| Total assets | at 2020-12-31 | $183.2m | us-gaap:Assets |
| Current liabilities | at 2020-12-31 | $12.3m | us-gaap:LiabilitiesCurrent |
| Total liabilities | at 2020-12-31 | $25.7m | us-gaap:Liabilities |
| Current portion of debt | at 2020-12-31 | $0 | us-gaap:LongTermDebtCurrent |
| Shareholders' equity | at 2020-12-31 | $153.8m | us-gaap:StockholdersEquity |

## Business

As filed, 88,947 characters.

### General Development of the Business

#### Corporate Structure

The Company is an Ontario corporation with its corporate offices located in Lakewood, Colorado (a city in the Denver metropolitan area). It was incorporated on June 24, 1987 in the Province of Alberta under the name “368408 Alberta Inc.” In October 1987, 368408 Alberta Inc. changed its name to “Trevco Oil & Gas Ltd.” In May 1990, Trevco Oil & Gas Ltd. changed its name to “Trev Corp.” In August 1994, Trev Corp. changed its name to “Orogrande Resources Inc.” In April 2001, Orogrande Resources Inc. changed its name to “Volcanic Metals Exploration Inc.” On September 2, 2005, the Company was continued under the *Business Corporations Act* (Ontario). On March 26, 2006, Volcanic Metals Exploration Inc. acquired 100% of the outstanding shares of “Energy Fuels Resources Corporation.” On May 26, 2006, Volcanic Metals Exploration Inc. changed its name to “Energy Fuels Inc.” On November 5, 2013, the Company amended its Articles to consolidate its issued and outstanding Common Shares on the basis of one post-consolidation Common Share for every 50 pre-consolidation Common Shares (the “**Consolidation”).**

All of the Company’s assets, management and employees are located in the western United States. The Company’s assets, which include uranium, vanadium and REE extraction, recovery, permitting, evaluation and exploration assets, are held directly and indirectly, as the case may be, by the Company’s wholly-owned subsidiaries Energy Fuels Holdings Corp. (“**EF Holdings”**) and Strathmore Minerals Corp. (“**Strathmore”**). All of the Company’s employees are employed by its subsidiary Energy Fuels Resources (USA) Inc. (“**EFUSA”**), a wholly-owned subsidiary of EF Holdings, which also serves as operator of all of the Company’s properties. A diagram depicting the organizational structure of the Company and its active subsidiaries, including the name, U.S. state or Canadian province of incorporation, and proportion of ownership interest of each, is included as Exhibit 21.1 to this Annual Report. Energy Fuels also owns a number of inactive subsidiaries which have no material assets or liabilities and do not engage in any material business activities.

Each of the Company’s subsidiaries has its principal place of business and corporate office at 225 Union Blvd., Suite 600, Lakewood, Colorado 80228, USA, though additional support offices are located onsite or in close proximity to the Mill and ISR facilities. The registered office of EFUSA and principal place of business for the Company is at 225 Union Blvd., Suite 600, Lakewood, Colorado 80228, USA, and the registered office of the Company is located at 82 Richmond Street East, Suite 308 Toronto, Ontario, M5C 1P1, Canada. The Company’s website address is www.energyfuels.com.

The primary trading market for Energy Fuels’ common shares (the “**Common Shares”**) is the NYSE American under the trading symbol “**UUUU,”** and the Company’s Common Shares are also listed on the TSX under the trading symbol “**EFR.”** Energy Fuels is a U.S. domestic issuer for SEC reporting purposes and, in addition, is a reporting issuer in all of the Canadian provinces. Certain warrants issued by the Company are listed on the NYSE American under the symbol “**UUUU-WT”** and are also listed on the TSX under the symbol “**EFR.WT.”** Options on Energy Fuels’ Common Shares are traded on The Chicago Board Options Exchange. The Designated Primary Market Maker for the options is Group One Trading, LP. Citadel Securities is the Company’s Market Maker on the NYSE American.

In addition, the Company holds 9,439,857 shares of Virginia Energy Resources Inc. (TSXV:VUI; OTCQX:VEGYF) currently representing an approximate 16.5% equity interest in that company.

#### Business Overview

Energy Fuels is engaged in conventional and ISR uranium extraction and recovery, along with the exploration, permitting, and evaluation of uranium properties in the United States. The Company also extracts and recovers vanadium as market conditions warrant and is also planning to commence the commercial production of REE carbonate in 2021, another byproduct of the uranium recovery process. Energy Fuels owns the Nichols Ranch Uranium Recovery Facility in Wyoming (the “**Nichols Ranch Project”**), which is a uranium recovery facility with a licensed capacity of 2 million pounds of U3O8 per year, and the Alta Mesa Project in Texas (the “**Alta Mesa Project”**), which is a fully-permitted ISR uranium production facility with a licensed capacity of 1.5 million pounds of U3O8 per year, both of which are currently on standby. In addition, Energy Fuels owns the White Mesa Mill, which is the only conventional uranium and vanadium recovery facility operating in the United States with a licensed capacity of over 8 million pounds of U3O8 per year. In addition to uranium, the Mill can also recover vanadium as a co-product of mineralized material produced from certain of its projects in Colorado and Utah and from time to time from solutions in its tailings impoundment system, as market conditions warrant, as well as an REE carbonate from various uranium- and REE-bearing ores. The Company also owns uranium and uranium/vanadium properties and projects in various stages of exploration, permitting, and evaluation, as well as fully-permitted uranium and uranium/vanadium projects on standby. In addition, Energy Fuels recovers uranium from other uranium-bearing materials not derived from conventional material, referred to as “alternate feed materials,” at its White Mesa Mill.

#### ISR Operations

The Company conducts its ISR activities through (i) its Nichols Ranch Project in northeast Wyoming, which it acquired in June 2015 through its acquisition of Uranerz Energy Corporation (“**Uranerz”**), and (ii) its Alta Mesa Project in south Texas, which the Company acquired in June 2016 through its acquisition of Mesteña Uranium, LLC (“**Mesteña”)**, which is now named EFR Alta Mesa LLC (“**EFR Alta Mesa”).**

The Nichols Ranch Project includes: (i) a licensed and operating ISR processing facility (the “**Nichols Ranch Plant”**); (ii) licensed and operating ISR wellfields (the “**Nichols Ranch Wellfields”**); (iii) additional licensed ISR wellfields planned for future production (the “**Jane Dough Property”**), and; (iv) a licensed satellite ISR uranium project (the “**Hank Project”**), which will include an ISR satellite processing plant (the “**Hank Satellite Plant”**) that, when constructed, will produce loaded-resin, and associated planned wellfields (the “**Hank Property”**). See “*The Nichols Ranch ISR Project”* under Item 2 below. Also through the acquisition of Uranerz, the Company acquired the West North Butte property (the “**West North Butte Property”**), the North Rolling Pin property (the “**North Rolling Pin Property”**), and the Reno Creek property (the “**Reno Creek Property”**), as well as the Arkose Mining Venture (the “**Arkose Mining Venture”**), which is a joint venture of Wyoming ISR properties held 81% by Energy Fuels. The Company subsequently sold the Reno Creek Property to Uranium Energy Corp. in May 2018. See “*Non-Material Mineral Properties - Other ISR Projects”* under Item 2, below.

The Nichols Ranch Project is an ISR facility currently on standby that recovers uranium through a series of injection and recovery wells. Using groundwater fortified with oxygen and sodium bicarbonate, uranium is dissolved within a deposit. The uranium-bearing groundwater is then collected in a series of recovery wells and pumped to the Nichols Ranch Plant where the uranium is extracted from the water. The Nichols Ranch Plant creates a yellowcake slurry that is transported by truck to the White Mesa Mill, where it is dried and packaged into drums that are shipped to uranium conversion facilities.

Construction of the Nichols Ranch Plant, other than the elution, drying and packaging circuits, was completed in 2013, and it commenced uranium recovery activities in the second quarter of 2014. In September of 2015, the Company commenced construction of an elution circuit at the Nichols Ranch Plant, which was completed and began operations in February 2016. For the year ended December 31, 2020, the Company recovered approximately 6,000 pounds of U3O8 from the Nichols Ranch Project. The Company expects to recover limited quantities of U3O8 from the Nichols Ranch Project in 2021. See “*Outlook: ISR Activities.”*

The Alta Mesa Project is a fully licensed, permitted and constructed ISR processing facility that has an operating capacity of 1.5 million pounds of uranium per year and comprises a total of 195,501 contiguous acres of land. The Alta Mesa Project is currently on standby and ready to resume production as market conditions warrant. It is expected to be able to reach commercial production levels with limited required capital within approximately twelve months of a production decision. See “*The Alta Mesa Project”* under Item 2, below.

#### Conventional Operations

The Company conducts its conventional uranium, REE and vanadium extraction and recovery activities through its White Mesa Mill, which is the only operating conventional uranium, REE and vanadium processing facility in the United States. The White Mesa Mill located near Blanding, Utah, is centrally located such that it can be fed by a number of the Company’s uranium and uranium/vanadium projects in Colorado, Utah, Arizona and New Mexico, as well as by ore purchases or toll milling arrangements with third parties in the region as market conditions warrant.

The White Mesa Mill is licensed to process 2,000 tons of mineralized material per day. It is primarily a uranium recovery facility but can also recover REEs and vanadium. In addition, the Mill can recycle other uranium-bearing materials not derived from conventional ore, referred to as “alternate feed materials,” for the recovery of uranium, alone or in combination with other metals. In this regard, the Company is currently evaluating a number of potential alternate feed materials for the recovery of REEs in addition to uranium.

The White Mesa Mill has historically operated on a campaign basis, whereby mineral processing occurs as mill feed, contract requirements, as market conditions warrant. Over the years, the Company’s own, and third-party owned, conventional uranium properties in Utah, Colorado, Arizona and New Mexico have been both active and on standby in response to changing market conditions. From 2007 through 2014, running on a campaign basis, the White Mesa Mill recovered on average over 1 million pounds of U3O8 per year from conventional sources, including its La Sal Project, Daneros Project, and Tony M property in Utah; its Arizona 1 Project and Pinenut Project (which is currently almost fully reclaimed) in Arizona; and alternate feed materials. During 2016, the Mill recovered a total of 680,000 pounds of U3O8, of which 433,000 pounds were recovered from conventional materials from the Company’s Pinenut Project and 248,000 pounds from processing alternate feed materials. During 2017, the Mill recovered 310,000 pounds of U3O8 from processing pond solutions and 1,000,000 pounds from processing alternate feed materials, of which a total of 360,000 pounds were for the Company’s account and 950,000 pounds were for the account of third parties. During 2018, the Mill recovered 215,719 pounds of U3O8 from processing pond solutions and 561,628 pounds from processing alternate feed materials, of which a total of 82,709 pounds were for the Company’s account and 448,919 pounds were for the account of third parties under a tolling arrangement. In late 2018, the White Mesa Mill shifted to producing vanadium from pond solutions and, during 2019, 1,807,732 pounds of V2O5 were produced from pond solutions for its own account, and no uranium was produced at the Mill. During 2020, the Company recovered approximately 190,500 pounds of U3O8 at the White Mesa Mill from in-circuit uranium inventories extracted from the recent vanadium pond-return campaign, and from alternate feed materials, as well as approximately 67,000 pounds of V2O5 from in-process solutions from the recent vanadium pond-return campaign. In addition, the Company produced, using its existing infrastructure and pursuant to its existing Radioactive Materials License and Groundwater Discharge Permit, an REE carbonate concentrate on a pilot scale at the Mill from a sample of monazite sands from a third-party supplier – the first such initiative in North America in over 20 years. See “*Outlook: Conventional Extraction and Recovery Activities.”*

During 2021, the Company expects to recover approximately 46,400 pounds of U3O8 at the White Mesa Mill, including uranium recovered through the processing of REE- and uranium-bearing natural monazite ore. The Company also expects to commence commercial production of a mixed REE carbonate in 2021 and to produce approximately 3,000 tons of mixed REE carbonate at the Mill. Subject to successfully ramping-up production of a salable product during 2021, the Company expects to sell some or all of this intermediate REE product to REE separation facilities outside the U.S. To the extent not sold, the Company expects to stockpile mixed REE carbonate at the Mill for future separation and other downstream REE processing at the Mill or elsewhere. See “*Outlook: Rare Earth Sales.”*

In addition, the Company currently has approximately 126,800 pounds of U3O8 contained in stockpiled alternate feed material and ore inventory that can be recovered in the future for the proposed U.S. Uranium Reserve or as general market conditions warrant. In addition, there remains an estimated 1.5-3 million pounds of solubilized recoverable V2O5 inventory remaining in the tailings facility awaiting future recovery, as market conditions may warrant. See “*Outlook: Conventional Extraction and Recovery Activities.”*

The Company continues to receive and process alternate feed materials at the White Mesa Mill, including low-grade ore from the cleanup of a conventional mine in northwest New Mexico. At the Company’s permitted Pinyon Plain Project (formerly, the “Canyon Project”), standby and environmental compliance activities continued during 2020, including submission of an application to replace the Company’s existing General Permit with an Individual Permit, as issued by the Arizona Department of Environmental Quality. The timing to extract and process mineralized material from the Pinyon Plain Project will be based on market conditions, available financing, and sales requirements. The Company’s Pinenut Project, where mineral extraction activities occurred until September 2015, is now depleted and has been almost fully reclaimed, with only a two-acre disturbance associated with a monitor well still remaining. The Company also pursued a small-scale test mining campaign targeting vanadium at its La Sal Complex in 2018 and early 2019, along with rehabilitation of existing mine workings, which ceased in early 2020. All of the Company’s other conventional properties and projects are currently in the permitting process or on standby pending improvements in market conditions. No third-party conventional properties are active at this time.

The Company also owns the Sheep Mountain Project (the “**Sheep Mountain Project”**), which is a conventional uranium extraction project located in Wyoming. Due to its distance from the White Mesa Mill, the Sheep Mountain Project is not expected to be a source of feed material for the Mill. The Sheep Mountain Project consists of permitted open pit and underground extraction components (the “**Sheep Mountain Extraction Operation”**) and a planned processing facility to process extracted mineralized material (the “**Sheep Mountain Processing Operation”**), which has not yet been permitted.

The Company’s principal conventional properties include the following:

- the White Mesa Mill, a 2,000 ton per day uranium and vanadium processing facility located near Blanding, Utah, held through the Company’s subsidiary EFR White Mesa LLC. See “*The White Mesa Mill”* under Item 2, below;
- the Arizona Strip uranium properties located in north central Arizona, including: the Pinyon Plain Project, which is a fully-permitted uranium project with all surface facilities and a shaft in place (see “*The Pinyon Plain Project”* under Item 2, below);
- the Wate project (the “**Wate Project”**), which is a uranium deposit in the permitting stage; the Arizona 1 project (the “**Arizona 1 Project”**), which is a fully-permitted uranium project on standby; and the EZ properties (“**EZ Properties”**), which are uranium deposits in the exploration and evaluation stage. All of the Company’s Arizona Strip properties are held by the Company’s subsidiary EFR Arizona Strip LLC, with the exception of the Wate Project, which is held by the Company’s subsidiary Wate Mining Company LLC. See “*Non-Material Mineral Properties – Other Conventional Projects – Arizona Strip”* under Item 2, below;
- the Roca Honda Uranium Project (the “**Roca Honda Project”**), which is located near the town of Grants, New Mexico, held by the Company’s subsidiaries Strathmore Resources (US), Ltd. and Roca Honda Resources LLC. See “*The Roca Honda Project”* under Item 2, below;
- the Sheep Mountain Project, which is a uranium project located near Jeffrey City, Wyoming, including permitted open pit and underground components held by the Company’s subsidiary Energy Fuels Wyoming Inc. See “*The Sheep Mountain Project”* under Item 2, below;
- the Henry Mountains Complex of uranium projects (the “**Henry Mountains Complex”**), which is located in south central Utah near the town of Ticaboo, which is comprised of the Tony M Property (the “**Tony M Property”**) and the Bullfrog Property (the “**Bullfrog Property”**), and which are held by the Company’s subsidiary EFR Henry Mountains LLC. See “*The Henry Mountains Complex”* under Item 2, below;
- the La Sal complex of uranium and uranium/vanadium projects (the “**La Sal Project”**) (see “*The La Sal Project”* under Item 2, below), the Whirlwind uranium/vanadium project (the “**Whirlwind Project”**), and the Sage Plain uranium/vanadium project (the “**Sage Plain Project”**), all of which are located near the Colorado/Utah border (the “**Colorado Plateau”**) and, in addition to nearby exploration properties, are held by the Company’s subsidiary EFR Colorado Plateau LLC. See “*Non-Material Mineral Properties – Other Conventional Projects – Colorado Plateau”* under Item 2, below;
- the Daneros Uranium Project (the “**Daneros Project”**) located in the White Canyon District in southeastern Utah, which is held by the Company’s subsidiary EFR White Canyon Corp. See “*The Daneros Project”* under Item 2, below; and
- a number of non-core uranium properties, which are held in various of the Company’s subsidiaries. See “*Non-Material Mineral Properties”* under Item 2, below.

#### Mineral Exploration

Energy Fuels holds a number of exploration properties in the Colorado Plateau, White Canyon, Grants, Arizona Strip, and Powder River Basin Districts. Energy Fuels conducted intermittent exploration drilling on numerous projects in the period from February 2007 through December 2013. Several of those projects have been abandoned or sold. No further exploration drilling has been performed at these properties since 2013. See “*Non-Material Mineral Properties”* under Item 2, below.

#### Potential Sale of Certain Non-Core Assets

The Company is in discussions with several parties to potentially sell certain of its non-core assets, including the Tony M Mine, Daneros Mine and Rim Mine, although there are currently no binding offers, and there can be no assurance at this time that a sale will be completed.

#### The Company’s Rare Earth Elements Business

On December 14, 2020, the Company announced it entered into a three-year supply agreement with The Chemours Company (NYSE: CC) (“**Chemours”**) to acquire a minimum of 2,500 tons per year of natural monazite sands, one of the highest-grade REE ores in the world, from Chemours’ Offerman Mineral Sand Plant located in Georgia. The Company expects to process this monazite at the Mill, starting in 2021, to recover the contained uranium and to produce a marketable mixed REE carbonate as a step toward re-establishing a fully-integrated U.S. REE supply chain.

On March 1, 2021, the Company and Neo Performance Materials (“**Neo”**) jointly announced that they had entered into an agreement in principle, subject to completion of definitive agreements, under which Energy Fuels will process natural monazite sands into an REE Carbonate beginning in March or April 2021 and ship a portion of that production to Neo's rare earth separations facility in Sillamäe, Estonia ("**Silmet**"). Neo will then process the REE Carbonate into separated rare earth materials for use in rare earth permanent magnets and other rare earth-based advanced materials. Silmet is the only operational rare earth separations facility in Europe and has been separating rare earths into commercial value-added products for more than 50 years. Implementation of this initiative is subject to successful ramp-up to commercial-scale operations, execution of definitive agreements, and optimization of the companies' production processes.

Upon a successful ramp-up of this program, the Company will be the first U.S. company in several years to produce a marketable mixed REE concentrate ready for separation on a commercial scale. The Company estimates that the amount of REEs contained in the monazite sands to be supplied by Chemours will equal close to 10% of total current U.S. REE demand, as contained in end-use products.

The Company expects to recover uranium from the monazite sands and produce a commercially salable mixed REE carbonate containing approximately 71% total rare earth oxide (“**TREO”**) on a dry basis. This REE product will be ready for REE separation, which is the next step in producing usable REE products. The Company is also in discussions with other entities to acquire additional supplies of natural monazite sands and is working with the U.S. Department of Energy (“**DOE”**) to evaluate the potential to process other types of REE and uranium bearing ores at the Mill produced from coal-based resources. Because the Company is obtaining monazite from existing mining facilities in Georgia (and potentially elsewhere) and utilizing its existing Mill, it will avoid the significant time and cost required to license and develop new facilities, which the Company believes may, in time, result in among the lowest-cost REE production in the western world. In addition, since the monazite sands are currently being separated from other mineral sands in Georgia and elsewhere, the Company will only incur the cost to acquire the monazite, thereby avoiding mining costs and associated risks. The Company expects to sell some or all of its mixed REE carbonate to Neo and to potentially other buyers in Europe and/or Asia until an REE separation facility is established in the U.S., after which it expects to sell its REE carbonate to buyers in both the U.S. and Europe. The Company is also evaluating the potential to perform REE separation, and potentially other downstream REE activities, including metal-making and alloying, in the future at the Mill or elsewhere in the U.S.

The Company’s mixed REE carbonate production from monazite sand ores is expected to utilize only a very small amount of the Mill’s ore production capacity. The Company expects to acquire a minimum 2,500 tons of monazite sands in 2021 from Chemours, alone, and has a goal to increase production in the future to approximately 15,000 tons or more of monazite sands per year. For comparison, the Mill is licensed and designed to process 2,000 tons of ore *per day* on average, or 720,000 tons of ore per year. Therefore, 2,500 tons of monazite per year represents less than 0.4% of the Mill’s ore throughput capacity, and 15,000 tons would represent approximately 2% of its capacity. If the Company is successful in securing 15,000 tons of ore similar to the Chemours monazite, the Company would be able to produce approximately 50% of current U.S. REE demand in a mixed REE carbonate. Furthermore, since monazite is typically comprised of approximately 55% recoverable uranium and REEs, the total volume of resulting waste is significantly lower than for most other Mill feeds. The Company currently has 1.5 million tons of existing capacity in its fully-constructed 1,000-year design tailings impoundments. Therefore, the annual waste streams from monazite ore processing are expected to represent less than 1% of existing tailings capacity.

REEs are a group of 17 chemical elements (the 15 elements in the lanthanum series, plus yttrium and scandium) that have a variety of industrial, energy, and defense uses, including automotive components, communications technology, clean energy production, consumer electronics, defense systems, advanced magnets, lasers and numerous other applications.

Typical natural monazite sands from the southeast U.S. average about 55% TREO and 0.20% uranium, which is the typical grade of uranium found in uranium mines that have historically fed the Mill. Of the 55% TREO typically found in the monazite sands, the neodymium and praseodymium (“**NdPr”**) comprise approximately 22% of the TREO. NdPr are among the most valuable of the REEs, as they are the key ingredient in the manufacture of high-strength permanent magnets which are essential to the lightweight and powerful motors required in electric vehicles (“**EVs”**) and permanent magnet wind turbines used for renewable energy generation, as well as to an array of other modern technologies, including mobile devices and defense applications. The Company is primarily focused on NdPr and, to a lesser extent, La, Ce and Sm.

The REE supply chain starts at the mine. REEs are mined both as a primary target and as a byproduct, which is the case for Chemours’ Offerman Mineral Sand Plant, where the natural monazite sands are physically separated from the other mined sands mined by Chemours. Mining creates an ore, which in the case of the Chemours material is the natural monazite sands that are physically separated from the other mined mineral sands. The ore will then go through a process of cracking and cleaning at the Mill that may include acids or caustic solutions, elevated temperature, and pressure to recover the uranium and free the REEs from the mineral matrix. After removal of the uranium, which will be sold into the commercial nuclear fuel cycle for the creation of carbon-free nuclear energy, this solution will be cleaned from any remaining deleterious elements (including remaining radioactive elements) and made into an REE carbonate, which will be in a form acceptable as a solvent extraction (“**SX”**) feedstock ready for separation. Solvent extraction facilities will then use solvents and a series of mixer-settlers for the separation of the rare earths in the REE carbonate from each other and to create the desired purified REEs (often as oxides) for the market or particular end user. REE oxides are typically sold to various markets, depending on the use. REE oxides can be made into REE metals and metal alloys, which are used for magnets and other applications. At this time, the Mill intends to produce an REE carbonate, which it intends to sell to Neo and potentially other third-party separation facilities for separation into individual REEs. The Mill is evaluating the potential to perform REE separation, and potentially other downstream REE activities, including metal-making and alloying, in the future at the Mill or elsewhere in the United States.

According to a 2017 report by the United States Geological Survey (“**USGS”**), China has controlled more than 90% of the global supply of REEs since the late 1990s and has placed restrictions on REE exports since 2010. While China consumes the most REEs in its manufacturing industries, much of it is consumed in the manufacture of end-use goods for export and by non-Chinese companies operating within China. REE separation facilities are additionally located in Vietnam, India, as well as Silmet in Estonia and use a variety of feedstocks and sources, with small-scale or experimental operational facilities located elsewhere (Russia included). The REE industry was primarily based on material extracted from monazites from 1891-1965, and monazites continued to provide substantial material through the late 1990s. The subsequent decline in monazite production stemmed from increased environmental concerns related to handling radioactivity and the resulting waste, with facilities struggling to adequately address the ore’s uranium and thorium content and stringent licensing requirements. The Mill, however, is licensed to process uranium and thorium-bearing materials and does not face those issues.

More recently, China began importing monazite and recovering its uranium as a feed source for the nuclear industry, while concurrently producing REE concentrate as a feed source for the REE industry. The Company sees its production of REE carbonate as the first step in an effort to restore the rare earth supply chain in the U.S., where one currently does not exist. Multiple potential domestic sources of mined mineral sands, including monazites, exist in North America and are potential feedstocks for the Mill; in addition, there is one producer of REEs from hard rock mining in California, which currently ships its material to China. On a global level, there is a potential to acquire natural monazite sands from the following locations: Australia, South Africa, Madagascar, Philippines, Indonesia, Brazil, Malaysia, Thailand, India, Russia, and others.

There are a number of risks inherent to the Company’s REE activities. See “*Item 1A. Risk Factors”* under Item 1A, below.

#### Development of the Business -- Major Transactions over the Past Five Years

Over the past five years, the Company has completed the following major transactions:

- In June 2015, the Company acquired all of the outstanding shares of Uranerz. Under that transaction, the Company acquired the Nichols Ranch Project, the Hank Project, the Reno Creek Property, the West North Butte Property, the North Rolling Pin Property, the Company’s interest in the Arkose Mining Venture, uranium sales contracts, and other assets, as well as the shares of Uranerz, which holds those assets;
- In two separate transactions in February and November of 2015, the Company acquired 100% ownership of the Wate Project through the acquisition of Wate Mining Company LLC;
- In June 2016, the Company acquired EFR Alta Mesa and its primary asset, the Alta Mesa Project;
- In May 2018, the Company sold its non-core Reno Creek Property to Uranium Energy Corp.; and
- In August 2018, the Company acquired royalties on the Nichols Ranch Project, along with royalties on several operating, standby and advanced-stage ISR projects in Wyoming owned and operated by Power Resources, Inc., a wholly-owned subsidiary of Cameco Corporation.

#### 2020 Corporate Developments

On February 10, 2020, the federal executive Budget was published for fiscal year 2021 (October 1, 2020 through September 30, 2021). The Budget “Supports Nuclear Fuel Cycle Capabilities,” and stated that “\[o\]n July 12, 2019, the President determined that ‘...the United States uranium industry faces significant challenges in producing uranium domestically and that this is an issue of national security.’ The President’s Budget establishes a U.S. Uranium Reserve to provide additional assurances of availability of uranium in the event of a market disruption.” Table 25-1 of the Budget sought congressional appropriations of $150 million per year over the next 10 years (totaling $1.5 billion over that time frame) for uranium purchases. For fiscal 2021 (October 1, 2020 through September 30, 2021), the Budget sought an appropriation of $150 million, “to remain available until expended,” as the appropriation for the first year of this 10-year program. On December 27, 2020, the U.S. Congress signed into law the COVID-Relief and Omnibus Spending Bill, which includes $75 million for the establishment of a strategic U.S. Uranium Reserve. Because the U.S. Uranium Reserve has yet to be established for the United States at this time, however, there can be no certainty as to the outcome of a U.S. Uranium Reserve, if any, including the process for and details of its development, or for any further evaluations by the U.S. Nuclear Fuel Working Group established in July 2019 to “develop recommendations for reviving and expanding domestic nuclear fuel production.”

On February 20, 2020, the Company closed a bought deal public offering of Common Shares made pursuant to an underwriting agreement dated February 13, 2020 between the Company and a syndicate of underwriters led by Cantor Fitzgerald & Co. as lead underwriter and sole book-runner, and H.C. Wainwright & Co., LLC, Eight Capital, Haywood Securities Inc. and Roth Capital Partners, LLC (the “**Offering”**). Pursuant to the Offering, the Company issued an aggregate of 11,300,000 Common Shares at a price of $1.47 per share for gross proceeds of $16.61 million. The Company received net proceeds, after commissions and fees, of $15.14 million from the Offering.

On February 28, 2020, the Company filed an updated technical report, including a Preliminary Feasibility Study (“**PFS”**), for its Sheep Mountain Project in Fremont County, Wyoming on SEDAR in accordance with National Instrument 43-101 – *Standards of Disclosure for Mineral Projects* and in accordance with Canadian Institute Mining’s (“**CIM”)** *Best Practice Guidelines for the Estimation of Mineral Resources and Mineral Reserves.* The technical report, entitled *Sheep Mountain Uranium Project, Fremont County, Wyoming, USA, Updated Preliminary Feasibility Study, National Instrument 43-101*

*Technical Report, Amended and Restated* and dated February 28, 2020, was authored by Douglas L. Beahm, P.E., P.G., Principal Engineer of BRS Inc., who is independent of the Company and a Qualified Person pursuant to NI 43-101. The updated PFS incorporated recent changes in CIM mineral resource requirements and changes in the Sheep Mountain Project mine plan.

On May 6, 2020, the Company announced that it has entered into an agreement to acquire from GeoInstruments Logging LLC all of its Prompt Fission Neutron (“**PFN”**) technology and equipment, including all of its related intellectual property, which will give Energy Fuels the exclusive right to use, license, and service this particular PFN technology globally. PFN is critical to successful uranium production particularly from many ISR deposits, as it more accurately measures downhole in-situ U3O8 ore grade versus traditional Total Gamma and Spectral Gamma methods. The acquisition closed in late July 2020.

On July 14, 2020, the Company redeemed Cdn$10.43 million principal amount of the Cdn$20.86 million Convertible Debentures. The Convertible Debentures were redeemable for an amount equal to 101% of the aggregate principal amount plus accrued and unpaid interest thereon, up to but excluding July 14, 2020. On October 6, 2020, the Company redeemed the remaining Cdn$10.43 million principal amount of the Cdn$10.43 million Convertible Debentures outstanding. The Convertible Debentures were redeemable for an amount equal to 101% of the aggregate principal amount plus accrued and unpaid interest thereon, up to but excluding October 6, 2020. The Convertible Debentures were measured at fair value based on the closing price on the TSX (a Level 1 measurement) and changes were recognized in earnings. As a result of the final redemption, no Convertible Debentures remain outstanding. The Convertible Debentures are no longer subject to the terms of the Indenture, and cease to be listed on the TSX. The Company currently has no other remaining short- or long-term debt.

On August 20, 2020, the Company announced a number of changes to its management team in order to reduce costs, flatten the organizational structure, and focus on the ongoing growth of a new generation of U.S. uranium and RE professionals, including: i) the departure of Paul Goranson as Chief Operating Officer, effective August 31, 2020; ii) the departure of Matthew Tarnowski as Chief Accounting Officer, effective October 31, 2020; iii) the promotion of Scott Bakken to Vice President, Regulatory Affairs, effective September 1, 2020; iv) the promotion of Dee Ann Nazarenus to Vice President, Human Resources and Administration, effective September 1, 2020; and v) the hiring of Sarai Luksch as Controller, effective September 1, 2020.

On September 21, 2020, the Company announced that it had been advised by the DOE Office of Fossil Energy and the National Energy Technology Laboratory that Energy Fuels was awarded a contract, working with a team from the Pennsylvania State University (“**Penn State”**), to evaluate and develop a conceptual design to allow for the commercial production of mixed rare earth oxides from coal-based resources in an environmentally benign fashion. The award includes an option, at the DOE’s election, for Energy Fuels to complete a feasibility study on this initiative.

On November 3, 2020, the Company announced that it had produced at the Company’s White Mesa Mill, using its existing infrastructure and pursuant to its existing Radioactive Materials License and Groundwater Discharge Permit, an REE carbonate concentrate on a pilot scale from a sample of monazite sands from a third-party supplier – the first such initiative in North America in over 20 years. Then, on December 14, 2020, the Company announced that it had entered into a three-year supply agreement with Chemours to acquire a minimum of 2,500 tons per year of natural monazite sands, which the Company plans to process at the Mill starting in 2021 to recover the contained uranium and produce a marketable mixed REE carbonate, as a key effort toward re-establishing a fully-integrated U.S. REE supply chain (see “ITEM 1. DESCRIPTION OF BUSINESS: *The Company’s Rare Earth Elements Business”).*

On December 21, 2020, the Company announced the publication of its first Sustainability Report, along with its Climate Change Policy, Human Rights Policy and Vendor Code of Conduct, which together with its other policies describe the Company’s ongoing commitment to the environment, worker health, public safety and social responsibility, including its important role in combating global climate change through producing and recycling carbon-free energy resources.

On December 31, 2020, the Company announced that it filed with the SEC a prospectus supplement to its effective U.S. registration statement on Form S-3 in order to renew its ATM program. Under the renewed ATM program the Company may, at its discretion from time to time, sell up to an additional $35 million of common shares, with sales only being made on the NYSE American at then-prevailing market prices, or any other existing trading market of the common shares in the United States.

Effective March 18, 2021, the Company filed a new base shelf registration statement on Form S-3 with the SEC allowing the Company to issue common shares, warrants, subscription receipts, preferred shares, debt securities, or any combination of such securities as units, in amounts, and at prices, and on terms to be determined based on market conditions at the time of sale, and as set forth in an accompanying prospectus supplement, for an aggregate offering amount of up to US$300 million during the

36-month period that the statement remains effective. On March l6, 2021, the Company received a receipt for a corresponding base shelf prospectus in Canada for an aggregate offering amount in Canada of up to US$300 million.

#### 2021 Corporate Developments

From January 1, 2021 through March 18, 2021, the Company issued 5.50 million Common Shares at an average price of $5.53 for net proceeds of $29.70 million using the ATM.

On March 1, 2021, the Company and Neo Performance Materials (“**Neo”**) jointly announced that they had entered into an agreement in principle, subject to completion of definitive agreements, under which Energy Fuels will process natural monazite sands into an REE Carbonate beginning in March or April 2021 and ship a portion of that production to Neo's rare earth separations facility in Sillamäe, Estonia ("**Silmet**"). Neo will then process the REE Carbonate into separated rare earth materials for use in rare earth permanent magnets and other rare earth-based advanced materials. Silmet is the only operational rare earth separations facility in Europe and has been separating rare earths into commercial value-added products for more than 50 years. Implementation of this initiative is subject to successful ramp-up to commercial-scale operations, execution of definitive agreements, and optimization of the companies' production processes (see “ITEM 1. DESCRIPTION OF BUSINESS: *The Company’s Rare Earth Elements Business”).*

#### Company Strategy

Energy Fuels intends to continue to strengthen its position as a leading uranium extraction and recovery company in the United States, supporting that goal through uranium recovery, alternate feed materials processing, third-party processing, and potential land clean-up work. In addition, the Company produces vanadium along with uranium from certain of its properties, as market conditions warrant. The Company also expects to commence commercial production of an REE carbonate in 2021, along with uranium from monazite sands, as well as uranium from alternate feed materials and other ores. See “*The Rare Earth Element Market,”* below. Through the operating White Mesa Mill, the Nichols Ranch Project and Alta Mesa Project, which are both currently on standby, the Company’s large uranium and vanadium resource base, and existing conventional projects on standby, under construction, and in permitting, the Company’s strategy is to maintain and increase its ability to increase uranium production in improved market conditions.

As a result of the foregoing, we intend to engage in the following activities:

- In response to the proposed establishment of a U.S. Uranium Reserve, the Company intends to evaluate activities aimed towards increasing uranium production at all or some of our production facilities, including the currently operating White Mesa Mill, as well as the Nichols Ranch ISR Facility, Alta Mesa ISR Facility, La Sal Complex, and the Pinyon Plain Mine, all of which are currently on standby, as market conditions may warrant. The Company may commence these activities prior to such establishment, recognizing that there can be no guarantee that the U.S. Uranium Reserve will ever come to fruition or that the implementation details, if they occur, will be satisfactory, and that the outcomes of this process are therefore uncertain.
- Continue to pursue U.S. government support for U.S. uranium production, such as the Company’s recent efforts to help secure a renewal of the Russian Suspension Agreement, including support for the establishment of a U.S. Uranium Reserve and any future recommendations from the U.S. Nuclear Fuel Working Group or other remedies;
- Continue the Company’s ongoing REE initiatives for the production of a REE carbonate concentrate from monazite sands sourced from third-party suppliers, with the potential to enter into one or more joint ventures for the construction of an onsite REE separation facility at the Company’s Mill site and the development of a fully-integrated U.S. REE supply chain (see “ITEM 1. DESCRIPTION OF BUSINESS: *The Company’s Rare Earth Elements Business”)*, above;
- Defer further wellfield development at Nichols Ranch until uranium prices improve;
- Continue alternate feed processing, as well as pursue additional alternate feed materials (including potential rare-earth bearing alternate feed materials), third-party processing and other sources of feed for the Mill (including potential material generated from land cleanup work) and, when market conditions warrant, pursue the recovery of uranium and/or vanadium dissolved in the Mill’s pond solutions;
- Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and ongoing or new regulatory requirements, continue to carry out engineering, procurement and construction management activities at the Pinyon Plain Project in 2021, and maintain the property on standby until uranium prices improve;
- Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve, continue to maintain standby projects and facilities (including the Pinyon Plain Project, Alta Mesa Project, the La Sal Project and the Daneros Project) in a state of readiness for the purpose of restarting mining activities, as market conditions may warrant. At this time, subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve, all of the Company’s conventional projects are expected to remain on standby until market conditions warrant restarting mining activities, or are in the evaluation or permitting process;
- Continue permitting activities for the Roca Honda Project through the end of 2021;
- Continue to evaluate the sale of non-core assets that the Company does not believe contribute to shareholder value in order to reduce costs and/or receive sales proceeds; and
- Continue to pursue additional cost cutting measures.

#### Uranium Sales

As a result of current uranium market conditions, both ISR and conventional uranium recovery have been maintained at reduced levels until such time as market conditions improve sufficiently, either as a result of any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve or through improved market fundamentals.

The Company has not entered into uranium sales commitments for 2021 as of the date of this Annual Report; therefore, subject to any actions the Company may take in response to the proposed U.S. Uranium Reserve or improved market conditions, all 2021 uranium production is expected to be added to existing inventories. Energy Fuels’ significant uranium inventory provides the Company with financial flexibility, and the Company believes its existing inventories and new production may be worth significantly more in the future as a result of government uranium purchases for the proposed Uranium Reserve or otherwise. However, if suitable uranium price increases are observed in 2021, or if cash needs arise, the Company may elect to complete some discretionary uranium sales in 2021.

### Overview of Uranium Market

The primary commercial use of uranium is to fuel nuclear power plants for the generation of carbon- and emission-free electricity.

According to the World Nuclear Association (“**WNA”**), as of January 2021, there were 442 operable nuclear reactors world-wide, which required approximately 177 million pounds of U3O8 fuel at full operation. Worldwide, there are currently 53 new reactors under construction with an additional 98 reactors on order or in the planning stage and 326 which have been proposed.

According to data from TradeTech LLC (“**TradeTech”**), the world continues to require more uranium than it produces from primary extraction. The gap between demand and primary supply is filled by stockpiled inventories and secondary supplies.

According to the WNA, the United States currently has 94 operating reactors, two reactors under construction, and another 21 reactors on order, planned or proposed. According to the Nuclear Energy Institute (“**NEI”**), in 2019 the United States produced approximately 19.7% of its electricity from nuclear technology, while achieving an average capacity factor of 93%, leading all other carbon-free sources by a wide margin. In addition, in 2019, nuclear energy avoided 476 million metric tonnes of carbon dioxide emissions. According to the U.S. Energy Information Administration (“**EIA”**), U.S. utilities purchased approximately 48.3 million pounds of U3O8 in 2019. However, through March 31,2020 (the latest data available), the U.S. only produced approximately 8,098 pounds of U3O8; June 30, 2020 and September 30, 2020 data were withheld due to confidentiality concerns, which the Company believes are the result of low production figures.

Uranium is not traded on an open market or organized commodity exchange such as the London Metal Exchange, although the New York Mercantile Exchange provides financially-settled uranium futures contracts. Typically, buyers and sellers negotiate transactions privately and directly. Spot uranium transactions typically involve deliveries that occur immediately and up to 12 months in the future. Term uranium transactions typically involve deliveries that occur more than 12 months in the future, with long-term transactions involving delivery terms of at least three years. Uranium prices, both spot and term, are published by two independent market consulting firms, TradeTech and The Ux Consulting Company (“**Ux”**), on a weekly and monthly basis. Other brokers, including Uranium Markets LLC, Evolution Markets Inc. and Numerco Ltd., also publish daily broker average uranium prices.

The spot and term prices of uranium are influenced by a number of global factors. For example, both the spot and term prices of uranium were negatively impacted by the accident at the Fukushima Daiichi Nuclear Plant in March 2011. The events at Fukushima created heightened concerns regarding the safety of nuclear plants and led to both temporary and permanent closures of nuclear plants around the world. The Fukushima incident has created downward pressure on uranium prices over the past nine years, which is still being felt today. In contrast, China is pursuing an aggressive nuclear program, with 49 units now operating, 16 new units under construction, 39 units which are planned, and 168 units that have been proposed, according to January 2021 WNA data.

Historically, most nuclear utilities have sought to purchase a portion of their uranium needs through mid- and long-term supply contracts, while other portions are bought on the spot market. According to EIA data, in 2019, U.S. utilities purchased 22% of their uranium on the spot market with the remaining 78% purchased under mid- and long-term contracts. Buyers seek to balance the security of supply with the opportunity to take advantage of lower prices. For this reason, both buyers and sellers track current spot and term prices for uranium carefully, make considered projections as to future prices, and negotiate with one another on transactions which each deems favorable to their respective interests.

The graph, below, shows the monthly spot (blue line) and long-term (red line) uranium price from August 1969 until January 2021 (table labeled in 2-year increments, so 2021 does not appear on the axis, though its data is incorporated) as reported by TradeTech (not adjusted for inflation):

To give a more recent perspective, the graph below shows the monthly spot (blue line) and long-term (red line) uranium price from January 2016 until January 2021 as reported by TradeTech (not adjusted for inflation):

According to monthly price data from TradeTech, uranium prices during 2020 were up $5.55, or 22% for the year. Monthly spot prices began the year at $24.85 per pound of U3O8 on December 31, 2019 and ended the year at $30.40 per pound, reaching a high of $33.85 per pound for the month of May 2020 and a low of $24.85 per pound at the beginning of the year (as of December 31, 2019). According to Trade Tech, the spot price was $27.40 per pound on March 12, 2021. TradeTech price data also indicated that long-term U3O8 prices began 2019 at $33.00 per pound and ended 2020 at $37.00 per pound. The high long-term price for 2020 was $39.00 per pound for the months of May and June, and the low long-term price was $33.00 per pound for the months of January and February. The long-term price at March 12, 2021 was $35.00 per pound. The Company believes the weak uranium markets are the result of excess uranium supplies caused by large quantities of state-owned uranium extraction in Kazakhstan and elsewhere, secondary uranium extraction and excess inventories, the availability of low-priced spot material, excess enrichment causing underfeeding and tails re-enrichment, insufficient production cut-backs especially from state-owned and state-subsidized uranium and uranium fuel entities, premature reactor closures, and continued weak uranium demand.

### Uranium Market Outlook and Uranium Marketing Strategy

World demand for clean, reliable, and affordable baseload electricity is growing. As a result of the expected growth of nuclear energy and the depletion of existing uranium mines, the Company believes the long-term fundamentals of the uranium industry remain positive. The Company believes prices must rise to higher levels to support the new primary production that will be required to meet the increasing demand we expect to see as more nuclear units are constructed around the world, and as primary mine production drops due to depletion of resources, low prices, and temporary shutdowns caused by the novel coronavirus (“**COVID-19”**) pandemic. According to TradeTech, world uranium requirements continue to exceed primary mine production, with the gap being bridged by secondary supplies and excess uranium inventories in various forms that have already been mined. In addition, it is the Company's belief that additional mine production cutbacks will be required to bring the market into balance in the short and medium terms. However, a large portion of global uranium production is state-owned and state-subsidized, and therefore not subject to normal market fundamentals. It is for this reason that the Company supports the creation of the proposed U.S. Uranium Reserve to ensure the U.S. has sufficient uranium mining capacity to meet national security and energy security needs. The Company estimates that, for 2020, well less than 1% of U.S. reactor demand was met by new production from U.S. uranium mines. The Company has believed for several years that market forces will cause uranium prices, and long-term contracting levels in particular, to return to levels that are sufficient to incentivize new mine production. However, it is the Company’s belief that secondary supplies, inventories, and non-free market forces have delayed this recovery.

The Company believes prices likely hit a bottom in 2016, and despite continued market uncertainty in 2020, the lows of 2016 have not been repeated since. During 2020, the COVID-19 pandemic caused uranium prices to rise significantly as several large mines temporarily ceased operations, including Cameco Corporation's Cigar Lake and mines in Kazakhstan. Uranium spot prices began the year at $24.85 per pound, and prices were relatively flat for the first two months of the year with the price on February 29, 2020 having risen $0.05 to $24.90 per pound (TradeTech, The Nuclear Review, December 2020). By March, the COVID-19 pandemic caused “widespread security of supply concerns … as several producers took preventative action to forestall the spread of the novel coronavirus through their businesses,” including Kazatomprom (Kazakhstan), Cameco (Canada), and China National Nuclear Corporation (Namibia). By April 30, 2020, the spot price had risen over 35% versus February levels to $33.75 per pound (*Ibid*). According to TradeTech, “the trajectory had its roots in a supply and demand picture that saw existing and emerging annual production levels decline well below reactor requirements” (*Ibid*). By May and into the second and third quarters, the spot price volatility subsided, and the monthly spot price of uranium sat at $29.90 per pound at the end of October 2020 (TradeTech, NMR, October 31, 2020). According to TradeTech, 2020 spot volumes reached near-record levels, totaling almost 62.5 million pounds of uranium. In other developments, U.S. uranium production dropped a further 76% to only 190,000 pounds in 2019 versus 2018 and BHP abandoned Olympic Dam expansion plans (TradeTech, The Nuclear Review, December 2020). In addition, Rio Tinto ceased production at its Ranger mine in early January 2021 (Mining.com, Australia’s Ranger uranium mine ceased production, January 7, 2020). On the policy front, the U.S. Congress funded $75 million for fiscal year 2021 for the establishment of a national uranium reserve, which was signed into law by the President in late-December (TradeTech, The Nuclear Review, December 2020). In addition, the U.S. and Russia agreed to extend the Russian Suspension Agreement which limits the amount of Russian uranium that can enter the U.S. (*Ibid).*

The Company believes that certain uranium supply and demand fundamentals are pointing to higher prices in the future, including significant production cuts and increased demand from utilities, financial entities, traders, and producers. However, the Company also believes that while uranium market conditions have improved in 2020, they still remain weak primarily as a result of excess uranium supplies caused by large quantities of secondary uranium supplies, excess inventories, and thus far insufficient primary production cut-backs, particularly from state-owned enterprises.

In the short- and medium-terms, market challenges remain. The world continues to be oversupplied with uranium, and there remains a great deal of uncertainty in uranium prices regarding the timing and level of the recovery, as fundamental, political, technical, and other factors could cause prices to be significantly above or below currently expected ranges.

The Company’s marketing strategy is to seek a base of earnings and cash flow through sales of a portion of its uranium into term contracts, to the extent such contracts are available at satisfactory prices, which has not been the case in recent years. To gain exposure to increasing uranium prices, the Company seeks to sell a portion of its planned uranium extraction into contracts with market-related formulas, if available at satisfactory prices, and through future spot and term sales. Further exposure to increasing uranium prices can be generated through the Company’s ability to bring additional uranium extraction online in the future in response to increasing prices, which can be sold on a market-related or fixed basis at then prevailing prices.

During 2020, the Company did not complete any material uranium sales. It has maintained its uranium inventory for future sales, in anticipation of higher uranium prices in the future, either as a result of U.S. government purchases for the proposed U.S. Uranium Reserve or due to improved market fundamentals.

The Company completed the remaining uranium deliveries under all its long-term contracts in 2018. Therefore, all of the Company’s current uranium production and inventory is 100% unhedged, and all uranium sales in 2021 and beyond will be made on the spot market or pursuant to new long-term contracts to the extent such contracts may be available on satisfactory terms. While the Company does not currently forecast the need to complete any spot sales in 2021 for cash generation purposes, uranium inventories, along with expected uranium production in 2021, are expected to provide the Company with the flexibility to complete spot sales in 2021 in response to the proposed establishment of a U.S. Uranium Reserve, or otherwise if market conditions warrant.

### The Rare Earth Element Market

In 2020, the Company began evaluating the potential to process REEs at the White Mesa Mill. By October, the Company had produced a mixed REE carbonate, ready for separation, on a pilot scale from natural monazite ore. In December 2020, the Company announced that it had entered into an agreement with Chemours to acquire a minimum quantity of 2,500 tons of natural monazite ore per year for three years starting in 2021. The Company is currently evaluating selling all or a portion of the resulting carbonate to a buyer in Europe and/or stockpiling it for future separation at the Mill.

REEs are used in a variety of clean energy and advanced technologies. According to Roskill, most demand for REE’s is in the form of separated REEs, “as most end-use applications require only one or two separated rare earth compounds or products.” (Roskill, Rare Earths, Outlook to 2030, 20th Edition). The REE market is dominated by China, and according to 2018 data, controlled 68% of global primary production, 100% of global secondary production, and nearly all production of the “heavy” REEs, including terbium and dysprosium (Adames Intelligence).

The main uses for REEs include: (i) battery alloys; (ii) catalysts; (iii) ceramics, pigments and glazes; (iv) glass polishing powders and additives; (v) metallurgy and alloys; (vi) permanent magnets; (vii) phosphors; and (viii) others (Adames Intelligence). By volume, REEs permanent magnets (neodymium (Nd), praseodymium (Pr), dysprosium (Dy), and terbium (Tb)) and catalysts (cerium (Ce) and lanthanum (La) comprised 60% of total consumption, but over 90% of the value consumed.

REEs are comprised of 15 chemical elements, plus scandium (Sc) and yttrium (Y). Plus, each individual REE may transact in a number of forms. Therefore, there is no single price for REEs, but numerous prices for individual REE oxides and compounds. The primary value that the Company expects to generate in the short- to medium-term will come from NdPr, Ce, and La. According to data from Asian Metal, NdPr oxide mid-point prices in China rose approximately 45% during 2020 from 282,500 RMB per metric tonne to 411,500 RMB per metric tonne. Ce oxide prices in Europe dropped 9% from $2.30/kg to $2.10/kg. La oxide prices in China dropped 18% from $1,830 per metric tonne to $1,495 per metric tonne.

As demand for clean energy technologies, including electric vehicles, renewable energy systems, and batteries, along with other advanced technologies, increases in the coming years, the Company expects demand and prices for REEs, particularly the ones mentioned above, to increase. Expected increases in supply sources for REEs are also expected to increase with expected rising REE prices, which is expected to have a moderating impact on price increases.

### The Vanadium Market

The White Mesa Mill has historically recovered vanadium along with uranium from certain of its properties on the Colorado Plateau, including from the La Sal Project and Rim Mine, as well as from properties owned by third-parties on the Colorado Plateau through toll milling and similar arrangements, when the price of vanadium has been high enough to justify its recovery.

In December 2018, the Company commenced a campaign to recover V2O5 from existing tailings pond solutions at the Company’s White Mesa Mill, which resulted from past mineral processing operations. In early January 2019, the Company produced its first batches of vanadium concentrate, also known as “black flake.” This was Energy Fuels’ first vanadium production since 2013, and the first time the Company recovered vanadium from tailings pond solutions at the Mill. The Company produced vanadium through the end of 2019, recovering approximately 1.8 million pounds of high-quality V2O5 under this campaign, at which point production ceased due to weak vanadium market conditions. The Company did not sell material quantities of vanadium during 2020, and as of December 31, 2020, the Company holds approximately 1,672,000 pounds of vanadium in inventory.

Vanadium is a metallic element that, when converted into ferrovanadium (“**FeV”**) (an alloy of vanadium and iron), is used primarily as an additive to strengthen and harden steel. According to market consultant Roskill, over 90% of FeV is used in the steel industry. In addition, vanadium is used in the aerospace and chemical industries, and continues to see interest in energy storage technologies, including vanadium redox flow batteries. China is the largest global producer of vanadium, with additional production coming from Russia, South Africa, and Brazil (Roskill). Following a dramatic spike in prices in 2018, vanadium (as V2O5) prices were down sharply in 2019, with mid-point spot prices in Europe beginning the year at $15.50 per pound, and ending the year at $5.33 per pound, reaching a high of $17.38 per pound in February 2018 (Metal Bulletin) and a low of $4.73 per pound in October 2019. During 2020, vanadium prices rose slightly to $5.40 by the end of the year. The high spot price for the year was $7.13 per pound on February 14, 2020, and the low price for vanadium in 2020 was $5.10 per pound on November 6, 2020. As at March 12, 2021, Vanadium prices were $8.33 per pound.

According to Metal Bulletin, vanadium prices rose dramatically in the second half of 2018 due to anticipated increased demand in China which implemented new standards requiring increased quantities of vanadium in rebar. However, in late-2018, prices began to drop sharply “when market participants realized the enforcement of the revised rebar policy was not as stringent as had been expected and after steel mills increased their use of ferro-niobium to reduce consumption of more costly vanadium.” (Metal Bulletin, January 20, 2020). According to Roskill, 2020 was “characterized by an economic de-synchronisation between China and the rest of the world, with a wide divergence in terms of steel consumption and production.” (Roskill, Vanadium, niobium: Markets in 2020 – a China story, December 22, 2020). China’s steel production reached an all-time high due to stimulus and infrastructure spending, while the rest of the world suffered under COVID lockdowns (*Ibid*). Vanadium prices were supported in China due to “reverse substitution away from niobium.” (*Ibid*). Further Roskill projects tighter supply and higher demand for vanadium in 2021 and into 2022 as lockdowns are relaxed and vaccines become more widely distributed (*Ibid).*

During January 2020, Energy Fuels produced approximately 67,000 pounds of vanadium, as production was wound down from 2019. The Company did not sell any quantities of vanadium in 2020. The Company held approximately 1,672,000 pounds of vanadium in inventory at the end of 2020. Vanadium markets can be volatile; therefore, the Company expects to hold and sell this inventory into stronger markets in the future, or as cash requirements arise.

### Competition

The uranium industry is highly competitive. The Company competes with mining and exploration companies for uranium sales, the acquisition of uranium mineral properties, and the procurement of equipment, materials and personnel necessary to explore, develop, and extract uranium from such properties. There is competition for a limited number of uranium acquisition opportunities, including competition with other companies having substantially greater financial resources, staff and facilities than the Company. As a result, the Company may encounter challenges in acquiring attractive properties, and exploring and advancing properties currently in the Company’s portfolio. In addition, Energy Fuels competes with other uranium recovery companies, along with traders, brokers, financial institutions, converters, enrichers, and other market actors, including some that are state-owned and state-subsidized, for uranium sales. Due to the Company’s limited capital and personnel and the relative size of its operations, the Company may be at a competitive disadvantage compared to some other companies with regards to exploration and, if warranted, development of mining properties and securing uranium sales. The Company believes that competition for acquiring mineral prospects and completing uranium sales will continue to be intense in the future.

The availability of funds for exploration, evaluation, permitting and construction of uranium projects is limited, and the Company may find it difficult to compete on an international scale with larger and more established uranium exploration and production companies for capital. The Company’s inability to continue exploration, advancement, and the acquisition of new properties due to lack of funding could have a material adverse effect on the Company’s future operations and financial position.

However, the Company believes it has a competitive advantage over its peers in the U.S. domestic uranium space to the extent it has diversified business opportunities, including its ability to produce vanadium as market conditions may warrant, its ability to recycle uranium through its alternate feed materials processing business, and its ability to recover REE carbonate, along with uranium, from monazite sand ores.

### Government Regulation

The Company’s properties and facilities are subject to extensive laws and regulations which are overseen and enforced by multiple federal, state and local authorities. These laws govern exploration, construction, extraction, recovery, processing, exports, various taxes, labor standards, occupational health and safety, waste disposal, protection and remediation of the environment, protection of endangered and protected species, toxic and hazardous substances, and other matters. Uranium minerals exploration, extraction, recovery, and processing are also subject to risks and liabilities associated with the perceived potential for impacts to the environment and disposal of waste products occurring as a result of such activities.

Compliance with these laws and regulations may impose substantial costs on the Company and will subject the Company to significant potential liabilities. Changes in these regulations could require the Company to expend significant resources to comply with new laws or regulations or changes to current requirements and could have a material adverse effect on the Company’s business operations. However, compliance with government regulations generally, including but not limited to environmental regulations, is an integral part of the Company’s day-to-day business and impacts virtually all of the Company’s capital expenditure and operating decisions at its facilities, as the Company’s facilities and operations must comply with this extensive array of environmental, health and safety laws and regulations. The costs of compliance with these laws and regulations are therefore well understood and assumed by the Company in all of its capital budgeting decisions, project analyses and cost and earnings projections. As all of the Company’s competitors in the uranium mining industry in the U.S. face the same or similar regulatory requirements, the Company does not believe its need to comply with this extensive array of laws and regulations materially affects the Company’s competitive position within the U.S. uranium mining industry.

### Environmental Regulations

Exploration, development, and extraction activities are subject to environmental regulations which may prevent or delay the continuance of our activities. In general, our exploration, evaluation, and extraction activities are subject to federal and state laws and regulations relating to environmental quality and pollution control. Such laws and regulations increase the costs of these activities and may prevent or delay the commencement or continuance of a given operation. Specifically, we are subject to legislation regarding emissions into the environment, water discharges, and storage and disposition of hazardous wastes. In addition, legislation has been enacted which requires facility sites to be reclaimed in accordance with such legislation. Compliance with these laws and regulations has not had a material effect on our operations or financial condition to date.

Uranium milling in the U.S. is primarily regulated by the United States Nuclear Regulatory Commission (the “**NRC”**) pursuant to the *Atomic Energy Act of 1954*, as amended. Its primary function is to ensure the protection of employees, the public, and the environment from radioactive materials, and it also regulates most aspects of the uranium recovery process. The NRC regulations pertaining to uranium recovery facilities are codified in Title 10 of the Code of Federal Regulations.

On August 16, 2004, the State of Utah became an Agreement State for the regulation of uranium mills. This means that the primary regulator for the White Mesa Mill is now the State of Utah Department of Environmental Quality (“**UDEQ”**) rather than the NRC. At that time, the Mill’s NRC Source Material License was transferred to the State of Utah and became a Radioactive Materials License (the “**Radioactive Materials License”**), which was renewed in January 2018 as Amendment #8 (Renewal), then reissued as a Revised Renewal on February 16, 2018, by UDEQ’s Division of Waste Management and Radiation Control (“**DWMRC”**). On April 15, 2020, the DWMRC reissued the License as Amendment #9 with an amended Condition 9.7, which was revised for the purpose of incorporating into the Radioactive Materials License applicable State of Utah requirements relating to antiquities, historic site and Native American grave protections and repatriation, as these requirements had previously been expressed in terms of equivalent provisions of federal law. Two alternate feed Applications for Amendment are currently pending approval by the DWMRC. The State of Utah incorporates, through its own regulations or by reference, all aspects of Title 10 pertaining to uranium recovery facilities. When the State of Utah became an Agreement State, it required that a Groundwater Discharge Permit (“**GWDP”**) be put in place for the White Mesa Mill. The GWDP is required for all similar facilities in the State of Utah, and specifically tailors the implementation of the state groundwater regulations to the Mill site. The State of Utah requires that every operating uranium mill have a GWDP, regardless of whether the facility discharges to groundwater. The GWDP for the Mill was finalized and implemented in March 2005, then renewed in January 2018 and modified as of March 8, 2021. The White Mesa Mill also maintains a permit approval for air emissions with the UDEQ, Division of Air Quality.

Conventional uranium extraction is subject to regulation by a number of agencies including: (1) local county and municipal government agencies; (2) the applicable state divisions responsible for mining and protecting the environment within Utah, Colorado, Arizona, New Mexico, Texas and Wyoming; (3) the Bureau of Land Management (the “**BLM”**) and the United States Forest Service (the “**USFS”**) on public lands under their jurisdiction; (4) the U.S. Mine Safety and Health Administration (“**MSHA”**); (5) the United States Environmental Protection Agency (the “**EPA”**) for radon emissions from underground mines; and (6) other federal agencies, including without limitation the U.S. Fish and Wildlife Service (“**USFW”**), U.S. Army Corps of Engineers (“**USACE”**), and United States Department of Energy (“**DOE”**), where certain conditions exist. In addition, a uranium processing facility at the Sheep Mountain Project, if and when constructed, will be subject to regulation under the NRC, as a uranium processing facility and for permanent disposal of the resulting tailings.

The provisions of the Atomic Energy Act and its regulations that are applicable to uranium milling also apply to our ISR facilities in Wyoming and Texas. The Nichols Ranch Project and the Alta Mesa Project each have a Source Material License. The Nichols Ranch Source Material License was originally issued by the NRC; however, the State of Wyoming became an NRC Agreement State on September 30, 2018 and the Wyoming Department of Environmental Quality (“**WDEQ”**) - Land Quality Division (“**WDEQ-LQD”**) subsequently assumed all management and oversight functions. Texas, an NRC Agreement State since 1963, issued the Alta Mesa Source Material License through its Texas Commission on Environmental Quality (“**TCEQ”**). ISR facilities are also regulated by the State of Wyoming and State of Texas, respectively, and the EPA under the Clean Water Act, the Clean Air Act and the Resource Conservation and Recovery Act. In addition, ISR wellfields require an Underground Injection Control (“**UIC”**) Permit under the Safe Drinking Water Act, as administered by the EPA. ISR operations are subject to regulations by the U.S. Occupational, Safety and Health Administration (“**OSHA”**), rather than MSHA.

Reclamation bonds or the equivalent have been posted for each of the Company’s material properties that have structures or facilities. Energy Fuels is required to have export licenses issued by the NRC for its uranium exports, unless otherwise permissible pursuant to the White Mesa Mill’s existing Radioactive Materials License due to the nature of the material in question. Such licenses are obtained by the Company as required.

### Land Tenure

The Company’s land holdings are held either by leases from the fee simple owners (private parties or the State) or unpatented mining claims located on property owned and managed by the U.S. Federal Government. Annual fees must be paid to maintain unpatented mining claims, but work expenditures are not required. Holders of unpatented mining claims are generally granted surface access to conduct mineral exploration and extraction activities. However, additional permits and plans are generally required prior to conducting exploration or mining activities on such claims.

On July 9, 2009, BLM issued a Notice of Proposed Withdrawal (“**2009 Notice”**) under which it proposed that a total of approximately one million acres of public lands around the Grand Canyon National Park be withdrawn from location and entry under the Mining Law of 1872 (the “**Mining Law”**), subject to valid existing rights. In the 2009 Notice, BLM stated that the purpose of the withdrawal, if determined to be appropriate, would be to protect the Grand Canyon watershed from any adverse effects of locatable hardrock mineral exploration and mining. The 2009 Notice segregated the lands from location and entry under the mining laws for up to two years to allow time for various studies and analyses, including appropriate NEPA analysis. In order to allow more time for BLM to complete its NEPA analysis, the U.S. Department of the Interior (the “**DOI”**) published Public Land Order 7773 on June 21, 2011, which effected a six-month emergency withdrawal of the area. The emergency withdrawal prevented the lands from being open to location and entry under the Mining Law upon expiration of the two-year segregation while the DOI completed the decision–making process on the proposed withdrawal. The emergency withdrawal was effective from July 21, 2011 to January 20, 2012. During the two-year segregation and six-month emergency withdrawal, the BLM, along with its cooperating agencies, completed various studies and analyses of resources in the withdrawal area, including an Environmental Impact Statement (“**EIS”**) under the National Environmental Policy Act (“**NEPA”**). These studies and analyses were undertaken to provide the basis for the final decision regarding whether to proceed with the proposed withdrawal or to select an alternative action. Based on this analysis, on January 9, 2012, the DOI announced its final decision to withdraw from location and entry under the Mining Law, subject to valid existing rights, the total of approximately one million acres of lands originally proposed in the 2009 Notice (the “**Withdrawn Lands”**), for a 20-year period. Lawsuits challenging this decision were filed by various industry groups and interested parties. In addition, legislation has been proposed in both the U.S. House of Representatives and U.S. Senate, which would make the withdrawal permanent, subject to preexisting rights. The Company will track the progress of this legislation.

As a result of the 2009 withdrawal from location and entry, no new mining claims may be staked on the Withdrawn Lands and no new Plans of Operations may be approved, other than Plans of Operations on mining claims that were valid at the time of withdrawal and that remain valid at the time of plan approval. Case law indicates that a miner establishes valid Congressionally provided rights under the Mining Law through certain unilateral acts, and that such acts are presumptively recognized as valid claims in which the holder has valid existing rights unless and until the DOI or U.S. Federal Courts declare otherwise.

However, the Bureau of Land Management (the “**BLM”**) and USFS, each at their discretion, may perform a mineral examination and Mineral Report, which involves an economic evaluation of a project, in order to reflect an agency’s belief about certain mining claims that may be used in support of a future mining claim contest on the validity of existing rights. All the Company’s properties located on the Arizona Strip, with the exception of its Wate property and certain exploration properties held by the Company’s subsidiary, Arizona Strip Partners LLC, are located within the Withdrawn Lands. A mineral examination on the Company’s EZ Project will need to be completed by BLM, in conjunction with its review of the Company’s proposed Plan of Operations for that project. Mineral examinations were not required for the Company’s Arizona 1 and Pinenut projects, which had previously approved Plans of Operations and were previously active. Although the Company’s Pinyon Plain Project also has an approved Plan of Operations, and a mineral examination is not required, the USFS voluntarily performed a mineral examination on that Project in 2012 in order to clarify the agency’s own position on the underlying claims and concluded that the Pinyon Plain Project’s claims constituted valid existing rights (“**VERs”**). The USFS also concluded that no additional approvals were required on the Pinyon Plain Project that would trigger any further NEPA analysis as a major federal action.

The Company believes that all its material projects within the Withdrawn Lands are on valid mining claims that will each withstand a mineral examination. However, market conditions may postpone or prevent the performance of mineral examinations on certain properties and, if a mineral examination is performed on a property, there can be no guarantee that the mineral examination would not result in one of more of the Company’s mining claims being deemed invalid and/or that ongoing litigation challenging the validity of a VER determination would not result in the overturn of such determination, either of which could prevent a project from proceeding.

Former President Obama additionally designated the Bears Ears National Monument by executive order in December of 2016, which comprised 1.35 million acres of land in San Juan County, Utah. The designated land included a portion of County Road 258, which the Company relies on for access to its Daneros Project, and a property boundary that abutted the boundary of the White Mesa Mill and encompassed two water sampling sites the Company monitors for the Mill. In December 2017, former President Trump issued a Proclamation that amended former President Obama’s 2016 Proclamation and reduced the monument to two parcels encompassing a total of 201,876 acres, releasing 1.15 million acres. That Proclamation has been challenged in Federal Court. The closest boundaries of the reduced monument to any of the Company’s operations are approximately 6 miles from the White Mesa Mill and approximately 15 miles from the Daneros Project. On December 23, 2017, the Company issued a press release reiterating its past and present support of Bears Ears National Monument, and clarifying that the Company sought only minor adjustments to the original boundaries of the monument to prevent the boundary from directly abutting some of its existing operations, which were very minor adjustments, insignificant compared to the original size of the monument, and not a reflection of now former President Trump’s total reduction. However, it is possible that the Daneros Project and/or the White Mesa Mill could become subject to additional requirements, restrictions and costs if the original designation is upheld in Court, or reinstated by President Biden.

### Employees

As of the date of this Annual Report, the Company and its subsidiaries have approximately 94 full-time employees, all of whom are employed through the Company’s wholly owned, indirectly held subsidiary Energy Fuels Resources (USA) Inc. We operate in established mining areas where we have found sufficient available personnel for our business plans.

The Company is dependent on key personnel and qualified and experienced employees to conduct its business, given its diversified business opportunities, including its ability to produce vanadium as market conditions may warrant, its ability to recycle uranium through its alternate feed materials processing business, and its ability to recover REE carbonate, along with uranium, from monazite sand ores, all of which businesses are currently unique to the Company among its peers. The Company’s compensation plans, including its Omnibus Equity Incentive Compensation Plan are designed to address the attraction and retention of personnel, through the grant of equity incentives, in addition to cash salaries. This allows the Company to provide attractive incentive packages to its employees, while at the same time preserving its cash resources during times of low commodity prices and standby operations at a number of its facilities. Further, under these plans, all equity compensation granted to employees vests over time, thereby providing a retention incentive for key employees. The Company also has a succession plan designed to identify and address gaps and risks associated with succession of key employees. In addition, as part of the Company’s ongoing efforts to develop and retain key employees, on August 20, 2020, the Company announced a number of changes to its management team in order to reduce costs, flatten the organizational structure, and focus on the ongoing growth of a new generation of U.S. uranium and REE professionals (See “*2020 Corporate Developments”).*

### Available Information

Detailed information about us is or will be contained in our annual reports on Form 10-K, current reports on Form 8-K, proxy statements and other reports, and amendments to those reports, that we file with or furnish to the SEC. The Company is a U.S. Domestic Issuer for SEC purposes, most of its shareholders are U.S. residents, the Company is required to report its financial results under U.S. GAAP and its primary trading market is the NYSE American. However, prior to January 1, 2016, we were a foreign private issuer subject to limited periodic disclosure and current reporting requirements of the United States Securities Exchange Act of 1934, as amended (the “**Exchange Act”**), so we did not file Forms 10-K or 10-Q prior to January 2016. All such Forms 10-K and 10-Q filed after January 1, 2016 are available free of charge on our website, www.energyfuels.com, as soon as reasonably practicable after we electronically file such reports with or furnish such reports to the SEC. However, our website and any contents thereof should not be considered to be incorporated by reference into this document. In addition, all public filings, including Insider Reports, of the Company can be found on the SEC’s Electronic Data Gathering, Analysis, and Retrieval (“**EDGAR”**) platform, and on the Ontario Securities Commission’s System for Electronic Document Analysis and Retrieval (“**SEDAR”**) and System of Electronic Disclosure by Insiders (“**SEDI”**). We will furnish copies of such reports free of charge upon written request to our Investor Relations department. You can contact our Investor Relations department at:

225 Union Blvd., Suite 600

Lakewood, Colorado, 80228

Tel: 303.974.2140

Fax: 303.974.2141

Toll Free: 1.888.864.2125

E-mail: investorinfo@energyfuels.com

Additionally, our Code of Ethics, Corporate Governance Manual, Articles of Incorporation and Bylaws, Charters of the Audit, Compensation, Governance & Nominating, and Environment, Health & Safety Committees, and certain Company policies are available on our website. We will furnish copies of such information free of charge upon written request to our Investor Relations department.

## Risk factors

As filed, 97,952 characters.

The following information pertains to the outlook and conditions currently known to Energy Fuels that could have a material impact on the financial condition of Energy Fuels. Other factors may arise in the future that are currently not foreseen by management of Energy Fuels that may present additional risks in the future, including risks which the Company currently feels are immaterial. Current and prospective security holders of Energy Fuels should carefully consider these risk factors.

Our failure to successfully address any of the risks and uncertainties described below could have a material adverse effect on our business, financial condition and/or results of operations, and the trading price of our Common Shares may fluctuate widely. We cannot assure you that we will successfully or fully address these risks or other unknown risks that may affect our business.

#### Risks Related to our Industry

***We are subject to the risks normally encountered by companies in the mineral extraction industry.***

We are subject to the risks normally encountered by companies in the mineral extraction industry, such as:

- the discovery of unusual, or unexpected geological formations;
- accidental fires, floods, earthquakes, volcanic eruptions, and other natural disasters;
- unplanned power outages and water shortages;
- controlling water and other similar mining hazards;
- operating labor disruptions and labor disputes;
- the ability to obtain suitable or adequate machinery, equipment, or labor;
- our liability for potential pollution or other hazards; and
- other known and unknown risks involved in the conduct of exploration, development, and operation of mines, extraction and recovery facilities, and mills, along with the market for uranium and vanadium.

The development of mineral properties is affected by many factors, including, but not limited to: the cost of operations; variations in the grade of mineralized material; fluctuations in metal markets; costs of extraction and processing equipment; availability of equipment and labor; labor costs and possible labor strikes; government regulations, including without limitation, regulations relating to taxes, royalties, allowable extraction or production, importing and exporting of minerals; foreign exchange; employment; worker safety; transportation; and environmental protection.

***Our results of operations are significantly affected by the market price of uranium, vanadium and rare earth elements, which are cyclical and subject to substantial price fluctuations.***

Our earnings and operating cash flow are and will be particularly sensitive to the long- and short-term changes in the market price of uranium, vanadium and REEs. Among other factors, these prices also affect the value of our resources, reserves, and inventories, as well as the market price of our Common Shares.

Market prices are affected by numerous factors beyond our control. With respect to uranium, such factors include, among others: demand for nuclear power; political and economic conditions in uranium producing and consuming countries; public and political response to a nuclear incident; reprocessing of used reactor fuel, the re-enrichment of depleted uranium tails and the enricher practice of underfeeding; sales of excess civilian and military inventories (including from the dismantling of nuclear weapons; the premature decommissioning of nuclear power plants; and from the build-up of Japanese utility uranium inventories as a result of the Fukushima incident) by governments and industry participants; uranium supply, including the supply from other secondary sources; production levels and costs of production, and government actions such as, potentially, those planned in the 2021 Budget and those taken pursuant to the 2021 Omnibus Spending Bill that appropriates funding for the proposed U.S. Uranium Reserve. With respect to vanadium, such factors include, among others: demand for steel; the potential for vanadium to be used in advanced battery technologies; political and economic conditions in vanadium producing and consuming countries; world production levels; and costs of production. With respect to REEs, such factors include, among others: demand for REEs; political and economic conditions in REE producing and consuming countries; REE-bearing ore supply from secondary sources; international interest in the purchase of REE carbonate, absent a U.S.-based separation facility; public and political response to REE initiatives at the White Mesa Mill; governmental investment in domestic REE infrastructure; world production levels; costs of production; risks associated with foreign governmental actions, policies, laws, rules and regulations, and foreign state subsidized enterprises, with respect to REE production and sales, which could impact REE prices available to the Company and impact our access to world and domestic markets for the supply of REE-bearing ores and the sale of REE carbonate and other REE products and services to world and domestic markets; and other government actions, including licensing and import requirements.

Other factors relating to the price of uranium, vanadium and REEs include: levels of supply and demand for a broad range of industrial products; substitution of new or different products in critical applications for our existing products; expectations with respect to the rate of inflation; the relative strength of the U.S. dollar and of certain other currencies; interest rates; global or regional political or economic crises; regional and global economic conditions; and sales of uranium, vanadium and REE carbonate by holders in response to such factors. If prices are below our cash costs of extraction or recovery and remain at such levels for any sustained period, we may determine that it is not economically feasible to continue commercial extraction, recovery or processing at any or all of our projects or other facilities and may also be required to look for alternatives other than cash flow to maintain our liquidity until prices recover. Our expected levels of uranium recovery and business activity are dependent on our expectation and the industry’s expectations of uranium, vanadium and REE prices, which may not be realized or may change. In the event we conclude that a significant deterioration in expected future uranium prices has occurred, we will assess whether an impairment allowance is necessary which, if required, could be material.

The recent fluctuations in the price of many commodities is an example of a situation over which we have no control, and which could materially adversely affect us in a manner for which we may not be able to compensate. There can be no assurance that the price of any minerals recovered from or processed at our properties will be such that any deposits can be operated at a profit.

Our profitability is directly related to the market price of uranium, vanadium and REEs recovered. We may, from time to time, undertake commodity and currency hedging programs, with the intention of maintaining adequate cash flows and profitability to contribute to the long-term viability of the business. We anticipate selling forward in the ordinary course of business if, and when, we have sufficient assets and recovery to support forward sale arrangements, and forward sale arrangements are available on suitable terms. There are, however, risks associated with forward sale programs. If we do not have sufficient recovered product to meet our forward sale commitments, we may have to buy or borrow (for later delivery back from recovered product) sufficient product in the spot market to deliver under the forward sales contracts, possibly at higher prices than provided for in the forward sales contracts, or potentially default on such deliveries. In addition, under forward contracts, we may be forced to sell at prices that are lower than the prices that may be available on the spot market when such deliveries are completed. Although we may employ various pricing mechanisms within our sales contracts to manage our exposure to price fluctuations, there can be no assurance that such mechanisms will be successful. There can also be no assurance that we will be able to enter into term contracts for future sales of uranium, vanadium or REE carbonate at prices or in quantities that would allow us to successfully manage our exposure to price fluctuations.

***Our properties do not contain Mineral Reserves under SEC Industry Guide 7, and many of the Company’s properties, projects, and facilities are not economic at today’s commodity prices.***

Our properties do not contain any mineral reserves under SEC Industry Guide 7 (see “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Reserve and Mineral Resource Estimates”*). At current uranium and vanadium prices, many of our properties, projects, and facilities are not economic for uranium or vanadium extraction, recovery, or processing. At our Pinyon Plain Project, we are currently evaluating the possibility of recovering copper as a byproduct along with uranium and the impact of any recovered copper on the economics of that project at current uranium prices. We intend to continue to hold, and in certain cases advance, a number of those properties, projects, and facilities in anticipation of possible future increases in the prices of uranium and/or vanadium, as the case may be. However, there can be no assurance that uranium and/or vanadium prices will ever, or within a reasonable time period, increase to the levels required to advance those properties or, in the case of projects or facilities on standby, to resume exploration, extraction, recovery, or processing activities at those projects or facilities. Similarly, there can be no assurance that the value of any copper recovered as a byproduct at the Pinyon Plain Project will be sufficient to advance that project without increases in the price of uranium and/or copper. We continue to hold such properties, projects, and facilities because we believe that uranium and/or vanadium prices are likely to rise to such levels within a reasonable time period and that the Company could be able to demonstrate a significant copper credit at the Pinyon Plain Project, and the ability to maintain scalability as commodity prices increase is a key component of our business strategy. However, as there is a cost associated with holding and in some cases maintaining on standby such properties, projects, or facilities, we continuously evaluate, on a case-by-case basis, such costs against the prospects for price increases, and may from time to time sell, drop or reclaim any such properties, projects, or facilities. We have currently identified a number of non-core properties and projects that we may sell, drop, or reclaim depending on current market conditions.

***Exploration, development, extraction, mining, recovery and milling of minerals, and the transportation and handling of the products recovered, are subject to extensive federal, state and local laws and regulations.***

These regulations govern, among other things; acquisition of the property or mineral interests; maintenance of claims; tenure; expropriation; prospecting; exploration; development; construction; extraction and mining; recovery, processing, milling and production; price controls; exports; imports; taxes and royalties; labor standards; occupational health; waste disposal; toxic substances; water use; land use; Native American consultations and accommodations; environmental protection and remediation; endangered and protected species; mine, mill and other facility decommissioning and reclamation; mine safety; transportation safety and emergency response; and other matters. Compliance with such laws and regulations has increased the costs of exploring, drilling, developing, constructing, operating and closing of our mines, mills, plants and other extraction, recovery and processing facilities. It is possible that, in the future, the costs, delays and other effects associated with such laws and regulations may impact our decision as to whether to operate existing mines or facilities, or, with respect to exploration, development or construction properties, whether to proceed with exploration, development or construction, or that such laws and regulations may result in our incurring significant costs to remediate or decommission properties that do not comply with applicable environmental standards at such time. We expend significant financial and managerial resources to comply with such laws and regulations. We anticipate continuing to do so as the historic trend toward stricter government regulation may continue. There can be no assurance that future changes in applicable laws and regulations will not adversely affect our activities, operations or financial condition. New laws and regulations, amendments to existing laws and regulations or more stringent implementation of existing laws and regulations, including through stricter license and permit conditions, could have a material adverse impact on us, increase costs, cause a reduction in levels of, or suspension of, extraction or recovery and/or delay or prevent the construction or development of new mineral extraction properties.

Mineral extraction is subject to potential risks and liabilities associated with impacts to the environment and the disposal of waste products occurring as a result of mineral exploration, extraction, mining, recovery and production. Environmental liability may result from mining or mineral extraction activities conducted by others prior to our ownership of a property. Failure to comply with applicable laws, regulations and permitting requirements may result in enforcement actions. These actions may result in orders issued by regulatory or judicial authorities causing activities or operations to cease or be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment or remedial actions. Companies engaged in uranium exploration operations may be required to compensate others who suffer loss or damage by reason of such activities and may have civil or criminal fines or penalties imposed for violations of applicable laws or regulations. Should we be unable to fully fund the cost of remedying an environmental problem, the Company might be required to suspend activities or operations, declare bankruptcy, or enter into interim compliance measures pending completion of the required remedy, which could have a material adverse effect on the Company. To the extent that we are subject to uninsured environmental liabilities, the payment of such liabilities would reduce otherwise available earnings and could have a material adverse effect on us. In addition, we do not have coverage for environmental losses generally or for certain other risks as such coverage cannot be purchased at a commercially reasonable cost. Compliance with applicable environmental laws and regulations requires significant expenditures and increases mine and facility, construction, development and operating costs.

While the very heart of our business – uranium production, which is the fuel for carbon-free, emission-free baseload nuclear power – and our recycling programs, help address global climate change and reduce air pollution, the world’s focus on addressing climate change will require the Company to continue to conduct all of its operations in a manner that minimizes the use of resources, including the unnecessary use of energy resources, in order to continue to minimize air emissions at our facilities, which can also increase mine and facility, construction, development and operating costs. Regulatory and environmental standards may also change over time to address global climate change, which could further increase these costs.

With the recent change in administration, there is a risk that the new administration will not support mining, uranium mining, nuclear energy or other aspects of our business, including: not supporting the proposed establishment of a U.S. Uranium Reserve included in the COVID-Relief and Omnibus Spending Bill passed by the U.S. Congress in December 2020, or any or all of the other recommendations of the U.S. Nuclear Fuel Working Group; and limiting, restricting or preventing the use of public lands for mining and other activities.

Worldwide demand for uranium is directly tied to the demand for electricity produced by the nuclear power industry, which is also subject to extensive government regulation and policies. The development of mineral properties and related facilities is contingent upon governmental approvals that are complex and time consuming to obtain and which, depending upon the location of the project, involve multiple governmental agencies. The duration and success of such approvals are subject to many variables outside of our control. Any significant delays in obtaining or renewing such permits or licenses in the future could have a material adverse effect on us. In addition, the international marketing of uranium is subject to governmental policies and certain trade restrictions, such as those imposed by the suspension agreement between the United States and Russia. Changes in these policies and restrictions may adversely impact our business.

***Public acceptance of nuclear energy and competition from other energy sources is unknown.***

Growth of the uranium and nuclear industry will depend upon continued and increased acceptance of nuclear technology as an economic means of generating electricity. Because of unique political, technological and environmental factors that affect the nuclear industry, including the risk of a nuclear incident, the industry is subject to public opinion risks that could have an adverse impact on the demand for nuclear power and increase the regulation of the nuclear power industry. Nuclear energy competes with other sources of energy, including oil, natural gas, coal, hydro-electricity and renewable energy sources. These other energy sources are to some extent interchangeable with nuclear energy, particularly over the longer term. Sustained lower prices of oil, natural gas, coal and hydroelectricity may result in lower demand for uranium concentrates. Increased government regulation and technical requirements may make nuclear uneconomic, resulting in lower demand for uranium concentrates. Technical advancements and government subsidies in renewable and other alternate forms of energy, such as wind and solar power, could make these forms of energy more commercially viable and put additional pressure on the demand for uranium concentrates.

***Unfavorable media coverage of mining or nuclear energy could negatively affect our business.***

The Company is subject to media coverage relating to mining and the production of uranium and other forms of nuclear energy, some of which can be inaccurate, non-objective or politically motivated. As a result, the Company is frequently required to address or respond to such media coverage, which can be costly and time-consuming for the Company. Such inaccurate and non-objective media coverage can also negatively impact public perception of the Company’s activities, the market for the Company’s securities, government relations, permitting activities and legal challenges.

### The uranium industry is highly competitive.

The international uranium industry, including the supply of uranium concentrates, is competitive. We market uranium in direct competition with supplies available from a relatively small number of uranium mining companies, from nationalized uranium companies, from uranium produced as a byproduct of other mining operations, from excess inventories, including inventories made available from decommissioning of nuclear weapons, from reprocessed uranium and plutonium, from used reactor fuel, and from the use of excess Russian enrichment capacity to re-enrich depleted uranium tails. A large quantity of current world production is foreign state subsidized and appears to be relatively inelastic, in that uranium market prices appear to have little effect on the quantity supplied. In the case of foreign state subsidized production, uranium production may not be fully subject to market factors and may be sold at prices that may be less than the cost of production. The supply of uranium from Russia is, to some extent, impeded by a number of international trade agreements and policies. These agreements and any similar future agreements, governmental policies or trade restrictions are beyond our control and may affect the supply of uranium available in the United States and Europe.

We compete with other mining companies and individuals for capital, mineral resources and reserves, and other mining assets, which may increase the cost of acquiring suitable claims, properties and assets, and we also compete with other mining companies to attract and retain key executives, employees and consultants. In addition, there are relatively few customers for uranium. There can be no assurance that we will continue to be able to compete successfully with our competitors in acquiring such properties and assets or in attracting and retaining skilled and experienced employees.

### Mining operations involve a high degree of risk.

The exploration, construction, development, operation, and other activities associated with mineral projects, along with the expansion of existing recovery operations and mining activities and restarting of projects, involve significant risks, including financial, technical, and regulatory risk. Development or advancement of any of the exploration properties in which we have an interest will only follow upon obtaining satisfactory exploration results, project permitting and licensing, and financing. The exploration, construction, development, operation and other activities associated with mineral projects involves significant financial risks over an extended period of time, which even a combination of careful evaluation, experience and knowledge may not eliminate. While discovery of a mine or other facility may result in substantial rewards, few properties which are explored are ultimately developed into producing mines or extraction or recovery facilities. Major expenses may be required to establish mineral resources and mineral reserves by drilling and to finance, permit, license, and construct extraction, mining, recovery and processing facilities. It is impossible to ensure that the current or proposed exploration, permitting, construction, or development programs on our mineral properties will result in a profitable commercial extraction, mining, or recovery operations.

Whether a mineral deposit will be commercially viable depends on a number of factors, which include, among other things: the accuracy of resource and reserve estimates; the particular attributes of the deposit, such as its size, geology and grade; the ability to economically recover commercial quantities of the minerals; proximity to infrastructure and availability of personnel; financing costs; governmental regulations, including regulations relating to prices, taxes, royalties; the potential for litigation; land use; importing and exporting; and environmental and cultural protection. The construction, development, expansion and restarting of projects are also subject to: the successful completion of engineering studies; the issuance of necessary governmental permits; the availability of adequate financing; engineering and construction timetables and capital costs being correctly estimated for our projects, including restarting projects on standby; and such construction timetables and capital costs not being affected by unforeseen circumstances. The effect of these factors cannot be accurately predicted, but the combination of these factors, along with others, may result in our not receiving an adequate return on invested capital.

It is possible that actual costs and economic returns of current and new extraction, mining, or recovery operations may differ materially from our best estimates. It is not unusual in the mining industry for new mining operations and facilities to experience unexpected problems during the start-up phase, take much longer than originally anticipated to bring into a recovery or producing phase, require more capital than anticipated, operate at a higher cost than expected, and/or have reclamation liabilities which are higher than expected.

There can be no assurance that as the Company mines its properties, or disposes of properties, the reduction of existing mineral resources through depletion or sales, will be replaced with new resources of comparable value.

***There is uncertainty in the estimation of mineral reserves and mineral resources.***

Our properties do not contain any mineral “reserves” as defined under Industry Guide 7. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Reserve and Mineral Resource Estimates.”*

Mineral reserves and resources are statistical estimates of mineral content pursuant to Canadian National Instrument 43-101, based on limited information acquired through drilling and other sampling methods, and require judgmental interpretations of geology. Successful extraction requires safe and efficient mining and processing. Our mineral reserves and resources are estimates, and no assurance can be given that the estimated reserves and resources are accurate or that the indicated level of uranium or vanadium will be produced economically or otherwise. Such estimates are, in large part, based on interpretations of geological data obtained from drill holes and other sampling techniques. Actual mineralization or formations may be different from those predicted. Further, it may take many years from the initial phase of drilling before production is possible, and during that time the economic feasibility of exploiting a discovery may change.

Mineral reserve and resource estimates for properties that have not commenced extraction, production or recovery are based, in many instances, on limited and widely spaced drill-hole information, which is not necessarily indicative of the conditions between and around drill holes. Accordingly, such mineral resource and reserve estimates may require revision as more drilling information becomes available or as actual extraction, production or recovery experience is gained. It should not be assumed that all or any part of our mineral resources constitutes, or will be converted into, “reserves.” Market price fluctuations of uranium or vanadium as applicable, as well as increased production and capital costs or reduced recovery rates, may render our proven and probable reserves unprofitable to develop at a particular site or sites for periods of time or may render mineral reserves containing relatively lower grade mineralization uneconomic.

### Opposition to mining may disrupt our business activities.

In recent years, governmental agencies, non-governmental organizations, individuals, communities and courts have become more vocal and active with respect to their opposition to certain mining and business activities including with respect to production and uranium recovery at our facilities, such as the White Mesa Mill and the Pinyon Plain Project. This opposition may take on forms such as road blockades, applications for injunctions seeking to cease certain construction, development, extraction, mining and/or milling or recovery activities, refusals to grant access to lands or to sell lands on commercially viable terms, lawsuits for damages or to revoke or modify licenses and permits, issuances of unfavorable laws and regulations, and other rulings contrary to our interests. These actions can occur in response to current activities or in respect of mines or facilities that are decades old. In addition, these actions can occur in response to our activities or the activities of other unrelated entities. Opposition to our activities may also result from general opposition to nuclear energy and mining. Opposition to our business activities are beyond our control. Any opposition to our business activities may cause a disruption to our business activities and may result in increased costs, and this could have a material adverse effect on our business and financial condition.

### We are subject to technical innovation and obsolescence in the uranium industry.

Requirements for our products and services may be affected by technological changes in nuclear reactors, enrichment, and used uranium fuel reprocessing. These technological changes could reduce the demand for uranium. The cost competitiveness of our operations may be impacted through the development and commercialization of other uranium mining, milling, processing and other technologies. As a result, our competitors may adopt technological advancements that give them an advantage over the Company.

***Mining, extraction, recovery, processing, construction, development, and exploration activities depend, to a substantial degree, on adequate infrastructure.***

Reliable roads, bridges, power sources, and water supply are important determinants affecting capital and operating costs. We consider the existing infrastructure to be adequate to support our proposed operations and activities. However, unusual or infrequent weather phenomena including drought, sabotage, government, or other interference in the maintenance or provision of such infrastructure could adversely affect our operations and activities, financial condition and results of operations.

***Mining, mineral extraction, recovery and milling are subject to a high degree of risk, and we are not insured to cover against all potential risks.***

Our operations and activities are subject to all of the hazards and risks normally incidental to exploration, construction, development, extraction and mining of mineral properties, and recovery, processing and milling, including: environmental hazards; industrial accidents; labor disputes, disturbances and unavailability of skilled labor; encountering unusual or unexpected geologic formations; rock bursts, pressures, cave-ins, flooding; periodic interruptions due to inclement or hazardous weather conditions; technological and processing problems, including unanticipated metallurgical difficulties, ground control problems, process upsets and equipment malfunctions; the availability and/or fluctuations in the costs of raw materials and consumables used in our production and recovery processes; the ability to procure mining and other equipment and operating and other supplies in sufficient quantities and on a timely basis; and other extraction, mining, recovery, milling, and processing risks, as well as risks associated with our dependence on third parties in the provision of transportation and other critical services. Many of the foregoing risks and hazards could result in damage to, or destruction of, our mineral properties or processing or recovery facilities, personal injury or death, environmental damage, delays in or interruption of or cessation of extraction, mining, production and recovery from our mines or processing facilities or in our exploration, construction or development activities, delay in or inability to receive regulatory approvals to transport our uranium concentrates, or costs, monetary losses and potential legal liability and adverse governmental action. In addition, due to the radioactive nature of the materials handled in uranium extraction, mining, recovery, and processing, additional costs and risks are incurred by us on a regular and ongoing basis.

While we may obtain insurance against certain risks in such amounts as we consider adequate, the nature of these risks are such that liabilities could exceed policy limits or could be excluded from coverage. There are also risks against which we cannot insure or against which we may elect not to insure. The potential costs which could be associated with any liabilities not covered by insurance or in excess of insurance coverage or compliance with applicable laws and regulations may cause substantial delays and require significant capital outlays, adversely affecting our future earnings, financial position and competitive position. No assurance can be given that such insurance will continue to be available or will be available at economically feasible premiums or that it will provide sufficient coverage for losses related to these or other risks and hazards. This lack of insurance coverage could result in material economic harm to us.

### Risks associated with our REE business.

There are a number of risks inherent to our REE activities, which include the following:

- The risk of achieving and maintaining an adequate supply of monazite sands for processing at the White Mesa Mill. The Company does not currently own its own monazite-bearing mines and is completely dependent on contractual arrangements for its REE feed sources. There can be no guarantee that the Company will be able to secure adequate monazite supply over the long-term at suitable prices. In addition, the price the Company may be required to pay for monazite sands is subject to the risk of influence by foreign policy and/or foreign state-owned enterprises. We will evaluate potential joint ventures with mine owners but there can be no guarantee that any joint ventures can be realized on acceptable terms. Further, to the extent the Company is required to purchase monazite ore sources and rely on REE separation facilities located outside the United States, we may be at a transportation cost disadvantage compared to processing facilities in China or elsewhere that may be closer to potential ore sources and/or REE separation facilities;
- The risk of being able to contract to sell the White Mesa Mill’s REE product at satisfactory prices. The Company intends to secure potential sales contracts with one or more REE separation facilities for the sale of the REE carbonate produced at the Mill, but there can be no guarantee that any such contracts will be entered into on satisfactory terms, or at all, in the future. If the Company is not able to secure adequate contracts for the sale of its REE carbonate, we may be required to hold our carbonate in inventory until it can be sold at reasonable prices, which would require the commitment of the Company’s cash resources while the REE product is being held in inventory. We would also bear the risk that the REE product may not be able to be sold at reasonable prices in the future, either due to a lack of a market for the purchase of our REE carbonate, and/or a reduction in REE commodity prices and hence a reduction in the value of the carbonate. We anticipate that the U.S. government may take steps to support the development of a U.S.

supply chain for REEs through price support or other mechanisms, but there can be no guarantee that any such support will be given, or if given, would benefit the Company.

- The risk of process failures in the production of REE carbonates such as the ability of the Company to produce REE Carbonate to meet commercial specifications on a commercial scale at acceptable costs, which could delay the expected commencement of commercial production of REE carbonate at the Mill in 2021 or prevent the commercial production of REE carbonate cost-competitively or at all;
- The risk that we may not be able to increase our sources of natural monazite sands or other ores in amounts sufficient to result in cost competitive production of REE carbonate at the Mill;
- The inability of the Company to successfully or cost-competitively process other types of REE and uranium bearing ores at the Mill produced from coal-based resources;
- The inability of the Company to construct and operate an REE separation facility, and potentially other downstream REE activities, including metal-making and alloying, in the future at the Mill or elsewhere in the United States; and
- The risk of permit and license challenges or the failure to obtain any needed permit or license amendments. The Mill can produce REE carbonate, along with uranium, from natural uranium- and REE-bearing monazite sand ores, but additional licensing may be required to permit and construct a separation facility and potential REE metal and metal alloy facilities at the Mill. The existing licensing regime and any new permits or licenses or amendments that may be required are subject to challenge, which could delay or prevent existing production or any new construction, as well as any separation and other activities.

#### Risks Relating to our Regulatory Environment

***The SEC’s adoption of the “Modernization of Property Disclosures for Mining Registrants” creates uncertainty related to the Company’s existing NI 43-101 reserves and resources and may result in increased compliance costs for the Company.***

The New Rule will rescind Industry Guide 7 when all registrants are required to comply with the new rules. The New Rule will require the Company to disclose specific information related to its material mining operations including concerning its mineral resources and mineral reserves. While the New Rule has similarities with NI 43-101, the Company may be required to update or revise all existing technical reports which may result in revisions (either upward or downward) to the Company’s reserves and resources. In addition, the New Rule is subject to unknown interpretations, which could require the Company to incur substantial costs associated with compliance. If the Company fails to come into compliance with the New Rule, it could be subject to enforcement actions by the SEC. The Company cannot predict the nature of any future enforcement, interpretation, or application of the New Rule. Any further revisions to, or interpretations of, the New Rule could result in the Company incurring unforeseen costs associated with compliance.

***We are a “smaller reporting company” and, therefore, certain reduced disclosure and other requirements are available to us.***

Currently, we are a “smaller reporting company” meaning we have (i) less than $100 million in annual revenues and our public float is less than $700 million or (ii) we have a public float less than $250 million. As a “smaller reporting company,” we may provide certain scaled disclosures, although the Company has elected not to avail itself of all of the scaled disclosure options available to “smaller reporting companies” at this time.

***Our future business and results of operations face uncertainties as a result of any action or inaction of the U.S. Government pursuant to the 2021 Omnibus Spending Bill that appropriates funding for a proposed U.S. Uranium Reserve, and any further evaluations by the U.S. Nuclear Fuel Working Group.***

On December 27, 2020, the COVID-Relief and Omnibus Spending Bill, which includes $75 million for the proposed establishment of a strategic U.S. Uranium Reserve, was signed into law. Because the U.S. Uranium Reserve has yet to be established at this time, however, there can be no certainty as to the outcome of a Uranium Reserve, if any, including the process for and details of its development, or for any further evaluations of the U.S. Nuclear Fuel Working Group established in July 2019 to “develop recommendations for reviving and expanding domestic nuclear fuel production.” If the required appropriations passed by Congress are deferred, or if they are implemented in a way that does not provide the required support for the Company’s activities, and uranium and vanadium markets do not improve and/or the Company’s REE initiatives are not adequate to otherwise sustain the Company’s other business activities, we may further reduce our operational activities and monetize certain non-core conventional mining assets as required in order to minimize our cash expenditures while preserving our core asset base for increased production in the future as market conditions may warrant.

***Participation in Industry Trade Petition and related activities could have negative repercussions.***

The Company previously participated in the filing of a Petition for Relief with the U.S. Department of Commerce (“**DOC”**) under Section 232 of the Trade Expansion Act of 1962 (as amended) From Imports of Uranium Products that Threaten U.S. National Security (the “**Section 232 Petition”**), which resulted in the establishment of the Working Group on July 12, 2019 to study U.S. nuclear fuel production, including uranium mining, in order “to develop recommendations for reviving and expanding domestic nuclear fuel production” and to “reinvigorate the entire nuclear fuel supply chain, consistent with United States national security and nonproliferation goals.” Based on recommendations from the Working Group, the U.S. Congress included in its COVID-Relief and Omnibus Spending Bill, which was signed into law on December 27, 2020, $75 million for the proposed establishment of a strategic U.S. Uranium Reserve. See “*Proposed Establishment of a U.S. Uranium Reserve and Working Group Update.”*

Although the Company believes this bipartisan appropriation is a significant accomplishment that will ultimately strengthen the U.S. uranium mining industry, bolster national defense, and improve supply diversification for U.S. utilities and their customers, there is a risk that such funds will not be allocated in a way that benefits the Company, a risk that the proposed U.S. Uranium Reserve will not be established, or will see a delay in its establishment, and the potential for negative responses or repercussions to these activities from various special interest groups, government entities, consumers of uranium and participants in other phases of the nuclear fuel cycle, both domestically and abroad, which could have a negative impact on the Company and its operations. In addition, the costs of pursuing such actions have been and could continue to be significant. It should also be noted that there can be no certainty as to the any further recommendations of the Working Group, and therefore its influence on the U.S. Congress and uranium industry going forward is uncertain.

***Participation in the renewal of the Russian Suspension Agreement and related activities could have negative repercussions.***

In October 2020, the DOC and State Atomic Energy Corporation Rosatom, on behalf of the Government of the Russian Federation, signed an amendment (the “**Amendment”**) to the “*Agreement Suspending the Antidumping Investigation on Uranium from the Russian Federation”* (the “**Agreement”**), thereby extending limitations on the import of Russian low-enriched uranium into the U.S. for use as fuel for nuclear reactors until the year 2040 and tightening restrictions in order to close loopholes identified in the original Agreement. The Company participated with the DOC in its efforts to secure the Amendment as an advocate for domestic uranium producers, which has the potential for negative responses or repercussions to these activities from various special interest groups, government entities, consumers of uranium and participants in other phases of the nuclear fuel cycle, both domestically and abroad, which could have a negative impact on the Company and its operations.

***Our business is subject to extensive environmental regulations that may make exploring, mining, or related activities expensive, and which may change at any time.***

We are required to comply with environmental protection laws and regulations and permitting requirements promulgated by federal agencies and various states and counties in which we operate and conduct our activities, in connection with extraction, mining, recovery and milling operations. The uranium industry is subject not only to the worker health and safety and environmental risks associated with all mining activities, but also to additional risks uniquely associated with uranium extraction, mining, recovery, and milling. We expend significant resources, both financial and managerial, to comply with these laws and regulations. The possibility of more stringent regulations exists in the areas of worker health and safety, storage of hazardous materials, standards for heavy equipment used in extraction, mining, recovery or milling, the disposition of wastes, the decommissioning and reclamation of exploration, extraction, mining, recovery, milling and in-situ sites, climate change and other environmental matters, each of which could have a material adverse effect on the cost or the viability of a particular project.

We cannot predict what environmental legislation, regulations or policies will be enacted or adopted in the future or how future laws and regulations will be administered or interpreted. The recent trend in environmental legislation and regulation is generally toward stricter standards, and this trend is likely to continue in the future. This recent trend includes, without limitation, laws and regulations relating to air and water quality, mine and other facility reclamation, waste handling and disposal, the protection of certain species and the preservation of certain lands. These regulations may require the acquisition of permits or other authorizations for certain activities. These laws and regulations may also limit or prohibit activities on certain lands. Compliance with more stringent laws and regulations, as well as potentially more vigorous enforcement policies, stricter interpretation of existing laws and stricter permit and license conditions, may necessitate significant capital outlays, may materially affect our results of operations and business or may cause material changes or delays in our intended activities. There can be no assurance of our continued compliance or ability to meet stricter environmental laws and regulations and permit or license conditions. Delays in obtaining permits and licenses could impact expected production levels or increases in expected uranium extraction levels.

Our operations may require additional analysis in the future including environmental, cultural, and social impact and other related studies. Certain activities require the submission and approval of environmental impact assessments. We cannot provide assurance that we will be able to obtain or maintain all necessary permits that may be required to continue operations or exploration and development of our properties or, if feasible, to commence construction, development, operation or other activities relating to mining facilities at such properties on terms that enable operations or activities to be conducted at economically justifiable costs. If we are unable to obtain or maintain, licenses, permits or other rights for construction or development of our properties, or otherwise fail to manage adequately future environmental issues, our uranium recovery operations and mining activities could be materially and adversely affected.

In December 2016, former President Obama designated the Bears Ears National Monument by executive order, which comprises 1.35 million acres of land in San Juan County, Utah. As originally mapped, the monument boundary was on the western property line of the White Mesa Mill, and the western monument boundary was very close to the permit boundary of the Daneros Mine, which could impact access to the mine. A National Monument created on land where our projects are sited, or near the Company’s projects, along with any resulting changes to rules or regulations, could significantly adversely impact any of our material projects and could have a material adverse impact on the Company.

The former Trump administration subsequently modified the designation of the Bears Ears National Monument on December 4, 2017 through Presidential Proclamation, which took effect on February 2, 2018. The revised boundaries have been moved well away from the White Mesa Mill property boundary as well as the Daneros Mine permit boundary. This revision of the monument boundaries is currently under legal challenge, but the Company does not expect that action to interfere with its operations or activities. Under the current administration, there is a risk that the boundaries of the monument may be changed, including changed to their original locations abutting the White Mesa Mill property boundary and close to the permit boundary of the Daneros Mine, which could adversely impact those properties.

***The new or lasting impacts of the USMCA (formerly NAFTA) on the Company remain unclear, and any action by President Biden to withdraw from or materially modify certain other international trade agreements in the future could adversely affect our business, financial condition and results of operations, to the extent dependent on the jurisdiction of our incorporation.***

Although our primary trading market is the NYSE American, we have a majority of U.S. resident shareholders, are a U.S. Domestic Issuer for SEC purposes, and all of our assets, operations and employees are in the U.S., the Company is incorporated in Ontario, Canada. On September 30, 2018, trade representatives acting on behalf of the U.S., Mexico and Canada renegotiated the terms of the North American Free Trade Agreement (“**NAFTA”**) in what is known as the United States-Mexico-Canada Agreement (“**USMCA”**), which entered into force on July 1, 2020 after being approved by the U.S. Congress. At this time, the new or lasting impacts of the USMCA on the Company remain unclear. In addition, if President Biden takes action to withdraw from or materially modify certain other international trade agreements, and such actions depend on the jurisdiction of our incorporation, then our business, financial condition and results of operations could possibly be adversely affected, depending on the nature of the action.

***Possible amendments to the General Mining Law could make it more difficult or impossible for us to execute our business plan.***

Members of the United States Congress have repeatedly introduced bills which would supplant or alter the provisions of the United States Mining Law of 1872, as amended. Such bills have proposed, among other things, to (i) either eliminate or greatly limit the right to a mineral patent; (ii) significantly alter the laws and regulations relating to uranium mineral development and recovery from unpatented and patented mining claims; (iii) impose a federal royalty on production from unpatented mining claims; (iv) impose time limits on the effectiveness of plans of operation that may not coincide with mine or facility life; (v) impose more stringent environmental compliance and reclamation requirements on activities on unpatented mining claims; (vi) establish a mechanism that would allow states, localities and Native American tribes to petition for the withdrawal of identified tracts of federal land from the operation of the U.S. general mining laws; and (vii) allow for administrative determinations that mining or similar activities would not be allowed in situations where undue degradation of the federal lands in question could not be prevented. If enacted, such legislation could change the cost of holding unpatented mining claims and could significantly impact our ability to develop locatable mineral resources on our patented and unpatented mining claims. Although it is impossible to predict at this point what any legislated royalties might be, enactment could adversely affect the potential for construction and development and the economics of existing operating mines and facilities. Passage of such legislation could adversely affect our financial performance.

In addition to the withdrawal noted in the previous risk factor, there are currently other designated or proposed withdrawals of federal lands for the purposes of mineral location and development and proposed designations of national monuments which would have a similar effect as a withdrawal. While such proposals are not yet final and would require further federal action, if they were to occur, it is uncertain whether any such withdrawals or designations would affect in any manner our current mineral projects.

#### Risks Related to Our Business

***Because the probability of an individual prospect ever having “reserves” as defined by the SEC Industry Guide 7 is not known, our properties may not contain any “reserves,” and any funds spent on exploration may be lost.***

We have no “reserves” as defined by SEC Industry Guide 7. Because the probability of an individual prospect ever having “reserves” as defined by SEC Industry Guide 7 is uncertain, our properties may not contain any “reserves,” and any funds spent on exploration, construction, development, extraction, and recovery may be lost. We do not know with certainty that economically recoverable uranium exists on any of our properties as defined by SEC Industry Guide 7. Further, although we are undertaking uranium extraction activities at our White Mesa Mill, our lack of established reserves means that we are uncertain as to our ability to continue to generate revenue from our operations. We may never discover uranium in commercially exploitable quantities and any identified deposit may never qualify as a commercially mineable “reserve.” We will continue to attempt to acquire the surface and mineral rights on lands that we think are geologically favorable or where we have historical information in our possession that indicates uranium mineralization might be present.

The exploration and, if warranted, construction relating to or development of mineral deposits involves significant financial and other risks over an extended period of time, which even a combination of careful evaluation, experience and knowledge may not eliminate. Few properties which are explored are ultimately developed into producing mines. Major expenditures are required to establish reserves by drilling and to construct mining and processing facilities at a site. Our uranium properties are all classified under SEC Industry Guide 7 to be at the “exploration” stage and do not contain any “reserves” at this time. It is impossible to ensure that the current or proposed exploration programs and other activities on properties in which we have an interest will result in the delineation of mineral “reserves” or in profitable commercial operations. Our operations and activities are subject to the hazards and risks normally incident to exploration and production of uranium, precious and base metals, any of which could result in damage to life or property, environmental damage and possible legal liability for such damage. While we may obtain insurance against certain risks, the nature of these risks is such that liabilities could exceed policy limits or could be excluded from coverage. There are also risks against which we cannot insure or against which we may elect not to insure. The potential costs which could be associated with any liabilities not covered by insurance, or in excess of insurance coverage, or compliance with applicable laws and regulations may cause substantial delays and require significant capital outlays, adversely affecting our future earnings and competitive position and, potentially our financial viability.

***The White Mesa Mill has historically been run on a campaign basis as sufficient feed materials are available, and there can be no assurance that sufficient mill feed will be available in the future to sustain future campaigns.***

The White Mesa Mill has historically operated on a campaign basis, whereby mineral processing occurs as mill feed, cash needs, contract requirements, and/or market conditions may warrant. Each milling campaign is subject to receipt of sufficient mill feed that would allow us to operate the Mill on a profitable basis and/or recover a portion of its standby costs.

At current uranium and vanadium prices, none of the Company’s conventional mines were active in 2020; all such conventional properties are either on standby, in the evaluation and permitting phase, or inactive, and no third-party conventional properties are operating to provide mill feed. In times of depressed commodity prices, when conventional mine production is on standby, the Mill has relied primarily on processing alternate feed materials. The Company continuously seeks to identify and secure additional alternate feed materials and other sources of mill feed, such as materials from the clean-up of abandoned uranium mine sites. The Company is also in the process of ramping up for the planned commercial production of REE carbonate at the Mill in 2021. However, there can be no assurance that sufficient conventional ores, alternate feed materials, suitable tailings pond solutions and/or other sources of mill feed will be available in the future, or that our planned production of REE carbonate will be successful, so as to allow us to operate the White Mesa Mill on a profitable basis and/or recover a portion of the Mill’s standby costs at any time.

***Our prior term sales contracts for a portion of our recovered uranium have expired, with no new long-term contracts for the sale of uranium or vanadium made in 2020 or to date in 2021, and there can be no guarantee that we will be able to enter into new term sales contracts in the future on suitable terms and conditions.***

All the Company’s existing long-term sales contracts for a portion of our recovered uranium expired following the Company’s final April 1, 2018 deliveries. The Company did not enter into any new long-term contracts for the sale of uranium or vanadium in 2019, 2020 or, as of the date of this Form 10-K, in 2021, and there can be no guarantee that the Company will be able to enter into long-term contracts for the delivery of a sufficient amount of uranium, vanadium or REE carbonate at satisfactory prices in the future. The failure to enter into new term sales contracts on suitable terms could adversely impact our operations and mining activity decisions and resulting cash flows and income.

***Vanadium mineral resource estimates for the La Sal Complex are based in part on the Company’s White Mesa Mill production records.***

For the Company’s La Sal Complex uranium-vanadium property, vanadium assay results are not available for all drill holes such that the vanadium mineral resource estimate is in part based on a ratio of vanadium to uranium supported by actual mill production records from the Company’s White Mesa Mill. There is a risk that the use of a ratio based on mill production records may increase the potential uncertainty in vanadium grades.

***We may be unable to timely pay our outstanding debt obligations, which may result in us losing some of our assets covered by mortgage and/or other security arrangements, and which may adversely affect our assets, results of operations, and future prospects.***

We may from time to time enter into arrangements to borrow money in order to fund our operations and expansion plans, and such arrangements may include covenants that restrict our business in some way. We may also from time to time acquire properties whereby certain payment obligations owed to the seller are paid by us over time, with the seller’s sole remedy for non-payment by us being re-acquisition of the property. Events may occur in the future, including events out of our control that would cause us to fail to satisfy our debt or financing instruments. In such circumstances, or if we were to default on our obligations under such debt or financing instruments, the amounts drawn in accordance with the underlying agreements may become due and payable before the agreed maturity date, and we may not have the financial resources to repay such amounts when due.

Although most, but not all, of our reclamation obligations are bonded, and cash and other assets have been reserved to secure a portion but not all of this bonded amount, to the extent the bonded amounts are not fully collateralized, we will be required to provide additional cash to perform our reclamation obligations when they occur. In addition, the bonding companies have the right to require increases in collateral at any time, failure of which would constitute a default under the bonds. In such circumstances, we may not have the financial resources to perform such reclamation obligations or to increase such collateral when due.

***We may need additional financing in connection with the implementation of our business and strategic plans from time to time.***

The exploration, construction and development of mineral properties and the ongoing operation of mines and other facilities requires a substantial amount of capital and may depend on our ability to obtain financing through joint ventures, debt financing, equity financing or other means. We may accordingly need further capital in order to take advantage of further opportunities or acquisitions. Our financial condition, general market conditions, volatile uranium and vanadium markets, volatile interest rates, legal claims against us, a significant disruption to our business or operations, or other factors may make it difficult to secure financing necessary for the expansion of mining activities or to take advantage of opportunities for acquisitions. Further, continuing volatility in the credit markets may increase costs associated with debt instruments due to increased spreads over relevant interest rate benchmarks, or may affect our ability, or the ability of third parties we seek to do business with, to access those markets. Continued volatility in equity markets, specifically including energy and commodity markets, may increase the costs associated with equity financings due to a low share price, and the potential need to offer higher discounts and other value (e.g., warrants). There is no assurance that we will be successful in obtaining required financing as and when needed on acceptable terms, if at all.

***We have experienced negative cash flows from operations and may need additional financing in connection with the implementation of our business and strategic plans from time to time.***

The Company has had negative cash flow from operations in prior years, and at low commodity prices a number of our mining properties will be on standby, making it less likely that the Company will be able to generate positive cash flows from operations. If the Company cannot generate positive cash flows from operations, its ability to fund its operations and implement its business plans may depend on its ability to obtain financing through joint ventures, debt financing, equity financing or other means. There can be no assurance that we will be able to achieve and maintain positive cash flow from operations to fund our financing needs. Further, if cash flows from operations are negative, there is no assurance that the Company will be able to raise additional funds, if needed, or that if any such additional funds are raised, that the Company will be able to raise such funds on commercially attractive terms. If we do not achieve positive cash flows or are unable to raise additional funds when needed, we may not be able to continue to fund our operations.

***We are subject to costs associated with decommissioning and reclamation of our properties.***

As owner and operator of the White Mesa Mill, the Nichols Ranch Project, the Alta Mesa Project, and numerous uranium and uranium/vanadium projects and other facilities located in the United States and certain permitting, construction, development and exploration properties, and for so long as we remain an owner thereof, we are obligated to eventually reclaim or participate in the reclamation of such properties. Most, but not all, of our reclamation obligations are bonded, and cash and other assets have been reserved to secure a portion, but not all, of this bonded amount. Although our financial statements will record a liability for the asset retirement obligation, and the bonding requirements are generally periodically reviewed by applicable regulatory authorities, there can be no assurance or guarantee that the ultimate cost of such reclamation obligations will not exceed the estimated liability to be provided on our financial statements. Further, to the extent the bonded amounts are not fully collateralized, we will be required to come up with additional cash to perform our reclamation obligations when they occur.

Decommissioning plans for our properties have been filed with applicable regulatory authorities. These regulatory authorities have accepted the decommissioning plans in concept, not upon a detailed performance forecast, which has not yet been generated. Over time, further regulatory review of the decommissioning plans may result in additional decommissioning requirements, associated costs and the requirement to provide additional financial assurances, including as our properties approach or go into decommissioning. It is not possible to predict what level of decommissioning and reclamation (and financial assurances relating thereto) may be required in the future by regulatory authorities.

### Our mineral properties may be subject to defects in title.

We have investigated our rights to explore and exploit all of our material properties and, to the best of our knowledge, those rights are in good standing. However, no assurance can be given that such rights will not be revoked, or significantly altered, to our detriment. There can also be no assurance that our rights will not be challenged or impugned by third parties, including by governments, surface owners, and non-governmental organizations.

The validity of unpatented mining claims on U.S. public lands is sometimes difficult to confirm and may be contested. Due to the extensive requirements and associated expense required to obtain and maintain mining rights on U.S. public lands, our properties are subject to various title uncertainties which are common to the industry with the attendant risk that there may be defects in title. In addition, the Secretary of the Interior has withdrawn certain lands around the Grand Canyon National Park from location and entry under the Mining Laws. All of our material Arizona Strip properties, other than the Wate Property, are located on these withdrawn lands. No new mining claims may be filed on the withdrawn lands and no new plans of operations may be approved, other than plans of operations on mining claims that were valid at the time of withdrawal and that remain valid at the time of plan approval. Whether or not a mining claim is valid must be determined by a mineral examination conducted by BLM or USFS, as applicable. The mineral examination, which involves an economic evaluation of a project, must demonstrate the existence of a locatable mineral resource and that the mineral resource constitutes discovery of a valuable mineral deposit. We believe that all of our material Arizona Strip projects are on valid mining claims that would withstand a mineral examination. Further, our Arizona 1 Project has an approved PO which, absent modification, would not require a mineral examination. Although our Pinyon Plain Project also has an approved PO, which, absent modification, would not require a mineral examination, the USFS performed a mineral examination at that mine in 2012, and concluded that the underlying mining claims are valid existing rights (a decision which is involved in a current court challenge). However, market conditions may postpone or prevent the performance of mineral examinations on certain other properties and, if a mineral examination is performed on a property, there can be no guarantee that the mineral examination would not result in one or more of our mining claims being considered invalid, which could prevent a project from proceeding.

Certain of our properties, or significant portions thereof, are mineral leases that have fixed terms, both with State and private parties. Certain of our properties are subject to other agreements that may affect our ability to explore, permit, develop and operate them, including surface use, access and other agreements. There can be no guarantee that we will be able to renew or extend such leases and agreements on favorable terms or at all. The failure to renew any such leases or agreements could have a material adverse effect on our operations.

***Because we may be unable to secure access rights to certain of our properties, we may be unable to explore and/or advance such properties.***

We are currently in the process of negotiating and clarifying access rights to certain of our properties, such as the Roca Honda Project and the Wate Project, with private landholders. There can be no guarantee that we will be able to negotiate or clarify such access rights on favorable terms, or at all. The failure to negotiate or clarify such access rights on suitable terms could have a material adverse effect on our operations.

### We are subject to foreign currency risks.

Our operations are subject to foreign currency fluctuations. Our operating expenses and revenues are primarily incurred in U.S. dollars, while some of our cash balances and expenses are measured in Canadian dollars. The fluctuation of the Canadian dollar in relation to the U.S. dollar will consequently have an impact on our profitability and may also affect the value of our assets and shareholders’ equity. In addition, any strengthening of the U.S. dollar relative to other currencies makes our mineral extraction and recovery less competitive in relation to similar activities in other countries. Any strengthening of the U.S. dollar in relation to the currencies of other countries can have a material impact on our cash flows and profitability and affect the value of our assets and shareholders’ equity.

### We may not realize the anticipated benefits of previous acquisitions.

We may not realize the anticipated benefits of acquiring: the Sheep Mountain Project in 2012; Denison Mines Corp.’s U.S. Mining Division in 2012, including the White Mesa Mill, certain of the Arizona Strip Properties, the Henry Mountains Complex, the La Sal Project, and the Daneros Project; Strathmore in 2013, including the Roca Honda Project; Uranerz in 2015, including the Nichols Ranch Project; and EFR Alta Mesa in 2016, including the Alta Mesa Project, due to integration, operational and uranium market challenges. Decreases in commodity prices have required us to place or maintain a number of acquired properties and facilities on standby and to defer permitting and construction and development activities on certain other acquired assets, until market conditions warrant otherwise, and, in some cases, we have elected to sell or abandon certain of these properties at a loss. Our success following those acquisitions will depend in large part on the success of our management in integrating the acquired assets into the Company. Our failure to achieve such integration and to mine or advance such assets could result in our failure to realize the anticipated benefits of those acquisitions and could impair our results of operations, profitability and financial results.

***We prepare estimates of future uranium extraction and recovery, and there are no assurances that such estimates will be achieved.***

We may from time to time prepare estimates of future uranium extraction and recovery, or increases in uranium extraction and recovery, for particular operations, or relating to our ability to increase uranium extraction and recovery in response to increases in commodity prices, as market conditions warrant or otherwise. No assurance can be given that any such extraction and recovery estimates will be achieved, nor can assurance be given that extraction or recovery increases will be achieved in a cost effective or timely manner. Failure to achieve extraction and recovery estimates or failure to achieve extraction and recovery in a cost effective or timely manner could have an adverse impact on our future cash flows, earnings, results of operations and financial condition. These estimates are based on, among other things, the following factors: the accuracy of mineral resource and reserve estimates; the accuracy of assumptions regarding ground conditions and physical characteristics of mineralized materials, such as hardness and presence or absence of particular metallurgical characteristics; the accuracy of estimated rates and costs of extraction, recovery and processing; assumptions as to future commodity prices; assumptions relating to changes in laws, regulations or policies, or lack thereof, that could impact the cost and time required to obtain regulatory approvals, licenses and permits; assumptions relating to obtaining required licenses and permits in a timely manner, including the time required to satisfy environmental analyses, consultations and public input processes; assumptions relating to challenges to or delays in the licensing and permitting process; and assumptions regarding any appeals or lack thereof, or injunctions or lack thereof, relating to any approvals, licenses or permits.

Our actual uranium extraction and recovery may vary from estimates for a variety of reasons, including, among others: actual mineralized material extracted, mined or recovered varying from estimates of grade, tonnage, dilution and metallurgical and other characteristics; short term operating factors relating to the mineral resources and reserves, such as the need for sequential construction or development of mineralized materials or deposits and the processing of new or different mineral grades; risk and hazards associated with extraction, mining and recovery; natural phenomena, such as inclement weather conditions, underground floods, earthquakes, pit wall failures and cave-ins; unexpected labor shortages or strikes; varying conditions in the commodities markets; and delays in obtaining or denial, challenges or appeals of regulatory approvals, licenses and permits or renewals of existing approvals, licenses or permits.

In addition, the Company is evaluating recovering copper at the White Mesa Mill as a byproduct with uranium from its Pinyon Plain Project. There can be no assurance that this evaluation will result in the Mill being able to recover copper at the Mill as a byproduct on an economic basis.

***We depend on the issuance of license amendments and renewals which cannot be guaranteed.***

We maintain regulatory licenses and permits in order to operate our White Mesa Mill, Nichols Ranch Project and Alta Mesa Project, all of which are subject to renewal from time to time and are required in order to operate in compliance with applicable laws and regulations. In addition, depending on our business requirements, it may be necessary or desirable to seek amendments to one or more of our licenses or permits from time to time. While we have been successful in renewing our licenses and permits on a timely basis in the past and in obtaining such amendments as have been necessary or desirable, there can be no assurance that such license and permit renewals and amendments will be issued by applicable regulatory authorities on a timely basis or at all in the future.

***We will need to continuously add to our mineral reserve and resource base and to our alternate feed materials.***

Our properties do not contain any mineral reserves under SEC Industry Guide 7. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Reserve and Mineral Resource Estimates.”*

Our material mineral resources are located at the Nichols Ranch Project, the Alta Mesa Project, the Pinyon Plain Project, the Roca Honda Project, the Sheep Mountain Project, the Henry Mountains Complex, the La Sal Project, and the Daneros Project. These projects are our primary sources (and potential sources) of current and future uranium concentrates. Unless other mineral resources or reserves are discovered or extensions to existing resource bodies are found, our sources of extraction, production and recovery for uranium concentrates will decrease over time as our current mineral resources are depleted. There can be no assurance that our future exploration, construction, development and acquisition efforts will be successful in replenishing our mineral resources or finding or developing reserves. In addition, while we believe that many of our properties will eventually engage in extraction or mining activities, there can be no assurance that they will be placed into such activities, or that they will be able to replace current extraction or mining activities.

We also recover uranium from processing alternate feed materials at our White Mesa Mill. There can be no assurance that additional sources of alternate feed materials will be forthcoming in the future on commercially acceptable terms or otherwise, or that we will be successful in receiving all required regulatory approvals, licenses and permits on a timely basis to allow for the receipt and processing of any such alternate feed materials.

***Our sales of uranium, vanadium and REE products expose us to the risk of non-payment.***

Our sales of uranium, vanadium and REE products expose us to the risk of non-payment. We manage this risk by monitoring the credit worthiness of our customers and requiring prepayment or other forms of payment security from customers with an unacceptable level of credit risk. Most of the Company’s sales are to major nuclear utilities, which pose a relatively low risk of non-payment due to their large size and capitalization.

### We are dependent on key personnel and qualified and experienced employees.

Our success will largely depend on the efforts and abilities of certain senior officers and key employees, some of whom are approaching retirement. Certain of these individuals have significant experience in the uranium industry. The number of individuals with significant experience in this industry is small. While we do not foresee any reason why such officers and key employees will not remain with us, other than through retirement, if for any reason they do not, we could be adversely affected. We have not purchased key person life insurance for any of these individuals, other than for our Chief Executive Officer.

Our compensation programs include cash and equity incentive compensation components designed to attract and retain qualified personnel, which, in the case of our equity incentive programs, contain vesting requirements which also help retain qualified personnel. Further, all of the Company’s current executive officers have, and all future executive officers are expected to have, employment agreements with the Company, which also serve to attract and retain qualified personnel. In addition, the Company prioritizes the development of its existing management personnel and the advancement of existing personnel to fill vacancies as they arise, which the Company believes is an important element in developing, attracting and retaining the most qualified management personnel.

Nevertheless, our success will depend on the availability of qualified and experienced employees to work in our operations and our ability to develop, attract and retain such employees. The number of individuals with relevant mining and operational experience in this industry, especially the U.S. uranium industry, is small.

***We have identified material weaknesses in our internal controls over financial reporting. If we are unable to implement and maintain effective internal controls over financial reporting in the future, investors may lose confidence in the accuracy and completeness of our financial reports and the market price of our common stock may be negatively affected.***

As a public company, we are required to maintain internal controls over financial reporting and to report any material weaknesses in such internal controls. A material weakness is a deficiency, or a combination of deficiencies, in financial reporting such that there is a reasonable possibility that a material misstatement of a company’s annual or interim financial statements will not be presented or detected on a timely basis. Section 404 of the Sarbanes-Oxley Act of 2002 (the ‘‘**Sarbanes-Oxley Act’’**) requires that we evaluate and determine the effectiveness of our internal controls over financial reporting and provide a management report on the internal controls over financial reporting. Such report must also be attested to by our independent registered public accounting firm.

In late 2019, we identified material weaknesses in our internal controls over financial reporting related to the Company’s risk assessment process not adequately identifying (1) risks of misstatement due to error and fraud related to our financial reporting processes; and (2) risks related to the use of information technology (IT) systems as part of our financial reporting processes and designing adequate controls to address those risks. As a consequence of the ineffective risk assessment process, the Company did not design, implement, and maintain effective control activities at the transaction level over significant accounts to mitigate the risk of material misstatement in our financial reporting processes. With the oversight of senior management, the Company has concluded that it has remediated the underlying causes of these material weaknesses, primarily through: the development and implementation of improvements to our risk assessment process designed to ensure that risks of misstatement due to error and fraud related to our financial reporting processes are adequately identified; the development and implementation of adequate controls designed to address risks related to the use of IT systems as part of our financial reporting processes; and the development and implementation of controls responsive to the identified risks.

However, if we are unable to comply with the requirements of Section 404 of the Sarbanes-Oxley Act in a timely manner in the future, or if we are unable to assert in the future that our internal controls over financial reporting are effective, or if our independent registered public accounting firm is unable to express an unqualified opinion as to the effectiveness of our internal controls over financial reporting if required in the future, then future material weaknesses may be identified, and investors may lose confidence in the accuracy and completeness of our financial reports and the market price of our common stock could be negatively affected.

### We are dependent on business partners, government and third-party consents.

We have a number of joint ventures and other business relationships from time to time relating to our properties and projects, including key projects, such as the Arkose Mining Venture, which can restrict our ability to act unilaterally with respect to those projects in certain circumstances. There can be no assurances that we will be able to maintain relationships with our joint venture and business partners to allow for satisfactory exploration, permitting, construction, development, extraction, mining, recovery or milling relating to any such projects. Our operations and activities are also dependent from time to time on receiving government and other third-party consents and approvals. There can be no assurances that all such consents and approvals will be forthcoming when required.

***Certain of our directors may be in a position of conflict of interest with respect to the Company due to their relationship with other resource companies.***

Some of our directors are also directors of other companies that are similarly engaged in the business of acquiring, exploring and developing natural resource properties. Such associations may give rise to conflicts of interest from time to time. In particular, one of the consequences will be that corporate opportunities presented to a director may be offered to another company or companies with which the director is associated and may not be presented or made available to us. Our directors are required by law to act honestly and in good faith with a view to the best interests of the Company, to disclose any interest which they may have in any project or opportunity of the Company, and to abstain from voting on such matter. Conflicts of interest that arise will be subject to and governed by the procedures prescribed in our Code of Ethics and by the *Business Corporations Act* (Ontario).

***Our relationship with our employees may be impacted by changes in labor relations.***

None of our operations or activities currently directly employ unionized workers who work under collective agreements. However, there can be no assurance that our employees or the employees of our contractors will not become unionized in the future, which may impact our operations and activities. Any lengthy work stoppages may have a material adverse impact on our future cash flows, earnings, results of operations and financial condition.

***U.S. investors may have difficulty bringing actions and enforcing judgments under U.S. securities laws against an Ontario corporation.***

Although our primary trading market is the NYSE American, we have a majority of U.S. resident shareholders, are a U.S. Domestic Issuer for SEC purposes, and all of our assets, operations and employees are in the U.S., the Company was incorporated in Ontario, and as a result, investors in the United States or in other jurisdictions outside of Canada may have difficulty bringing actions and enforcing judgments against us, our directors, our executive officers and some of the experts named in this Annual Report on Form 10-K based on civil liabilities provisions of the federal securities laws or other laws of the United States or any state thereof or the equivalent laws of other jurisdictions of residence.

### An information security incident, including a cybersecurity breach, could have a negative impact to the Company’s business or reputation

To meet business objectives, the Company relies on both internal information technology (IT) systems and networks, and those of third parties and their vendors, to process and store sensitive data, including confidential research, business plans, financial information, process technology, intellectual property, and personal data that may be subject to legal protection. The extensive information security and cybersecurity threats, which affect companies globally, pose a risk to the security and availability of these IT systems and networks, and the confidentiality, integrity, and availability of the Company’s sensitive data. The Company continually assesses these threats and makes investments to increase internal protection, detection, and response capabilities, as well as ensure the Company’s third party providers have required capabilities and controls, to address this risk. In addition, we provide confidential and proprietary information to our third-party business partners in certain cases where doing so is necessary to conduct our business. While we obtain assurances from those parties that they have systems and processes in place to protect such data, and where applicable, that they will take steps to assure the protections of such data by third parties, nonetheless those partners may also be subject to data intrusion or otherwise compromise the protection of such data. Any compromise of the confidential data of our customers, consumers, suppliers, partners, employees or ourselves, or failure to prevent or mitigate the loss of or damage to this data through breach of our information technology systems or other means could substantially disrupt our operations, harm our customers, consumers, employees and other business partners, damage our reputation, violate applicable laws and regulations, subject us to potentially significant costs and liabilities and result in a loss of business that could be material. To date, the Company has not experienced any material impact to the business or operations resulting from information or cybersecurity attacks; however, because of the frequently changing attack techniques, along with the increased volume and sophistication of the attacks, there is the potential for the Company to be adversely impacted. The Company may not maintain cybersecurity insurance in the event of an information security or cyber incident with sufficient coverage to cover all financial losses, or at all.

#### General Risk Factors

### We are subject to global economic risks.

In the event of a general economic downturn or a recession, there can be no assurance that our business, financial condition, and results of operations would not be materially adversely affected. During the global financial crisis of 2007-2008, economic problems in the U.S. and Eurozone caused deterioration in the global economy, as numerous commercial and financial enterprises either went into bankruptcy or creditor protection or had to be rescued by governmental authorities. Access to public financing was negatively impacted by sub-prime mortgage defaults in the U.S., the liquidity crisis affecting the asset-backed commercial paper and collateralized debt obligation markets, and massive investment losses by banks with resultant recapitalization efforts. Moreover, the occurrence of unforeseen or extended catastrophic events, including in particular the COVID-19 pandemic, and the emergence of a future pandemic or other widespread health emergency (or concerns over the possibility of such an emergency), could create economic and financial disruptions. These types of challenges can impact commodity prices, including for uranium, vanadium and REEs, as well as currencies and global debt and stock markets. As a result of the ongoing COVID-19 pandemic, or in the case of a future pandemic or other widespread health emergency, quarantine or other requirements or circumstances may require the Company to change the way it conducts its business and operations, including require the Company to reduce or cease operations at some or all of its facilities for an indeterminate period of time. Furthermore, our critical supply chains may similarly be disrupted for an indeterminate amount of time. All of these factors could have a material impact on the Company’s business, operations, personnel and financial condition.

These types of challenges may impact our ability to obtain equity, debt, or other financing on terms commercially reasonable to us, or at all. Additionally, these types of factors, as well as other related factors, may cause decreases in asset values that are deemed to be other than temporary, which may result in impairment losses. If these types of challenges occur, or if there is a material deterioration in general business and economic conditions, our operations could be adversely impacted, and the trading price of our securities could be adversely affected.

### COVID-19

The Company continues to evaluate the effects of the global COVID-19 pandemic on the Company’s business objectives, projections and workforce, To date, although the Company has made operational adjustments since the onset of the pandemic to ensure its workforce remains protected, the Company has not been required to shut down any operations as a result of COVID-19. None of these operational adjustments have been material to the Company. The Company has evaluated any potential shutdown of Company production facilities as a result of COVID-19, and has determined that any such shutdown could be accommodated by the Company in a manner consistent with a typical shutdown of Company production facilities as a result of depressed commodity prices. Nevertheless, circumstances could change in the future, which could create economic and financial disruptions and require the Company to reduce or cease operations at some or all of its facilities for an indeterminate period of time, and which could have a material impact on the Company’s business, operations, personnel and financial condition.

### The price of our Common Shares is subject to volatility.

Securities of mining companies have experienced substantial volatility and downward pressure in the recent past, often based on factors unrelated to the financial performance or prospects of the companies involved. These factors include macroeconomic conditions in North America and globally, and market perceptions of the attractiveness of particular industries. The price of our securities is also likely to be significantly affected by short-term changes in uranium and vanadium prices, changes in industry forecasts of uranium and vanadium prices, other mineral prices including oil and natural gas, currency exchange fluctuation, or in our financial condition or results of operations as reflected in our periodic earnings reports. Other factors unrelated to our performance that may have an effect on the price of our securities include the following: the extent of research coverage available to investors concerning our business may be limited if investment banks with research capabilities do not follow our securities; adverse proxy voting recommendations or limited portrayals of the Company’s business, operations or executive compensation practices made to shareholders by shareholder advisory firms resulting from their use of general-purpose formulas that are not suited to the Company’s business, operations or practices, and that may counteract the Company’s substantive disclosures, which often include detailed analyses specific to the Company and which are capable of mitigating apparent market concerns; lessening in trading volume and general market interest in our securities may affect an investor's ability to trade significant numbers of our securities; the size of our public float and the exclusion from market indices may limit the ability of some institutions to invest in our securities; and a substantial decline in the price of our securities that persists for a significant period of time could cause our securities to be delisted from an exchange, further reducing market liquidity. Our exclusion from certain market indices may reduce market liquidity or the price of our securities. If an active market for our securities does not continue, the liquidity of an investor's investment may be limited, and the price of our securities may decline. If an active market does not exist, investors may lose their entire investment. As a result of any of these factors, the market price of our securities at any given point in time may not accurately reflect our long-term value. Securities class-action litigation often has been brought against companies in periods of volatility in the market price of their securities and following major corporate transactions or mergers and acquisitions. We may in the future be the target of similar litigation. Securities litigation could result in substantial costs and damages and divert management's attention and resources.

***The issuance of additional Common Shares may impact the trading price of our Common Shares.***

In times of depressed commodity prices, such as exist at this time, the Company may be required to raise additional capital to meet its liquidity requirements, through the issuance of additional common shares under our ATM program or otherwise, and/or dispose of assets. If we raise additional funding by issuing additional equity securities or securities convertible, exercisable, or exchangeable for equity securities, such financing may substantially dilute the interests of our shareholders and reduce the value of their investment. Similar dilution could result from the sale of assets to meet liquidity requirements.

***We are subject to litigation and other legal proceedings arising in the normal course of business and may be involved in disputes with other parties in the future which may result in litigation.***

The causes of potential future litigation and legal proceedings cannot be known and may arise from, among other things, business activities, environmental laws, permitting and licensing activities, volatility in stock prices, or alleged failure to comply with disclosure obligations. The results of litigation and proceedings cannot be predicted with certainty and may include injunctions pending the outcome of such litigation and proceedings. Failure to resolve any such disputes favorably may have a material adverse impact on our financial performance, cash flow and results of operations.

***If we fail to maintain an effective system of internal controls, we may not be able to accurately report financial results or prevent fraud.***

Internal controls over financial reporting are procedures designed to provide reasonable assurance that transactions are properly authorized, assets are safeguarded against unauthorized or improper use, and transactions are properly recorded and reported. Disclosure controls and procedures are designed to ensure that information required to be disclosed by a company in reports filed with securities regulatory agencies is recorded, processed, summarized, and reported on a timely basis and is accumulated and communicated to a company’s management, including its chief executive officer and chief financial officer, as appropriate, to allow timely decisions regarding required disclosure. A control system, no matter how well designed and operated, can provide only reasonable, not absolute, assurance with respect to the reliability of reporting, including financial reporting and financial statement preparation.

## Properties

As filed, 288,345 characters.

**Cautionary Note to United States Investors:** Information contained in this item differs from the disclosure requirements of the SEC applicable to U.S.-incorporated domestic issuers. This Item 2 and other sections of this Annual Report contain the terms “measured mineral resources,” “indicated mineral resources,” “inferred mineral resources,” “proven mineral reserves,” and “probable mineral reserves” as defined in accordance with NI 43-101. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* at the beginning of this Annual Report for definitions and further discussion on the differences between terms under NI 43-101 and SEC Industry Guide 7.

### Overview

Energy Fuels is engaged in conventional and ISR uranium extraction and recovery, along with the exploration, permitting and evaluation of uranium properties in the United States.

#### ISR Uranium Activities

The Company conducts its ISR recovery activities through its Nichols Ranch Project in northeast Wyoming, which it acquired in June 2015 through the acquisition of Uranerz, and its Alta Mesa Project in south Texas, which it acquired in June 2016 through the acquisition of EFR Alta Mesa.

The Nichols Ranch Project includes: (i) the Nichols Ranch Plant; (ii) the Nichols Ranch Wellfields; (iii) the Jane Dough Property; and (iv) the Hank Project, which includes the permitted but not constructed Hank Satellite Plant and the Hank Property. See “*The Nichols Ranch ISR Project.”* The Company also acquired through the acquisition of Uranerz the Reno Creek Property (which it has since sold), the West North Butte Property, the North Rolling Pin Property, and the Arkose Mining Venture, a joint venture of ISR properties held 81% by Energy Fuels. See “*Non-Material Mineral Properties - Other ISR Projects.”* Nichols Ranch is currently winding down production from its existing wellfields, which are expected to be depleted by the end of the first quarter of 2021. In order for Nichols Ranch to engage in future uranium production, the Company will need to incur capital expenditures to develop additional wellfields. A decision to commence development will be made if the Company decides to take action in response to the proposed establishment of a U.S. Uranium Reserve or uranium prices otherwise improve to a point where economic feasibility of the Nichols Ranch Project is realized.

The Alta Mesa Project has a fully-licensed and constructed ISR uranium recovery plant, with a design capacity of 1.5 million pounds of uranium concentrate per year. In order for Alta Mesa to engage in future uranium production, the Company will need to incur capital expenditures to develop wellfields. A decision to commence development will be made if the Company decides to take action in response to the proposed establishment of a U.S. Uranium Reserve or uranium prices otherwise improve to a point where the economic feasibility of the Alta Mesa Project is realized.

#### Conventional Uranium Activities

The Company conducts its conventional uranium extraction and recovery activities through its White Mesa Mill, which is the only operating conventional uranium mill in the United States. The White Mesa Mill located near Blanding, Utah is centrally located such that it can be fed by a number of the Company’s uranium and uranium/vanadium projects in Colorado, Utah, Arizona and New Mexico, as well as by ore purchase or toll milling arrangements with third party miners in the region, as market conditions warrant. The Company also owns the Sheep Mountain Project in Wyoming, which is a conventional uranium project. Due to its distance from the White Mesa Mill, the Sheep Mountain Project is not expected to be a source of feed material for the Mill. The Sheep Mountain Project consists of the Sheep Mountain Extraction Operation (both open pit and underground), which is permitted, and the proposed Sheep Mountain Processing Operation (heap leach), which is not permitted at this time.

In November 2020, the Company officially changed the name of its Canyon Project to the Pinyon Plain Project. No material changes have taken place at the Pinyon Plain Project, and the land position and disclosed mineral resources remain the same. The NI 43-101 technical report that the information in this 10-K is based upon still contains Canyon Mine in the title. All references to the Project in this document have been changed from Canyon Mine to Pinyon Plain, except when directly referencing its technical report.

The Company’s principal conventional properties include the following:

- the White Mesa Mill. See “*The White Mesa Mill”;*
- the Pinyon Plain Project (formerly the Canyon Project). See “*The Pinyon Plain Project”;*
- the Roca Honda Project. See “*The Roca Honda Project”;*
- the Sheep Mountain Project. See “*The Sheep Mountain Project”;*
- the Henry Mountains Complex comprised of the Tony M Property and the Bullfrog Property. See “*The Henry Mountains Complex”;*
- the La Sal Project. See “*The La Sal Project”;*
- the Daneros Project. See “*The Daneros Project”;*
- the Arizona Strip uranium properties located in north-central Arizona, including: the Arizona 1 Project, the Wate Project, and EZ Project. See “*Non-Material Mineral Properties – Other Conventional Projects – Arizona Strip”*; and
- The Colorado Plateau uranium properties located in the Four Corners region of Colorado and Utah, including the Whirlwind Project and the Sage Plain Project. See “*Non-Material Mineral Properties – Other Conventional Projects – Colorado Plateau.”*

The White Mesa Mill is licensed to process 2,000 tons of mineralized material per day. It is primarily a uranium recovery facility but can also recover vanadium and REEs. In addition, the Mill can recycle other uranium-bearing materials not derived from conventional ore, referred to as “alternate feed materials,” for the recovery of uranium, alone or in combination with other metals. In this regard, the Company is currently evaluating a number of potential alternate feed materials for the recovery of uranium. The White Mesa Mill is also currently receiving low-grade mineralized material from the cleanup of a conventional mine in northwest New Mexico and is pursuing other opportunities to process mineralized materials from the clean-up of abandoned uranium mines on the Navajo Reservation and in the four corners area of the United States.

The material projects are shown on the map above and are described in further detail below. Properties that the Company does not consider material are summarized at the end of this Item 2.

### Uranium and Vanadium Recovery History

The following tables show the mineralized material processed and pounds of uranium and vanadium recovered from the Company’s projects and facilities from January 1, 2016 to December 31, 2020:(1)

#### Recovery History (1)

*Alternate Feed Materials(2)*

| Project or Source Tons (000) | 2020 NA(2) | 2019 NA(2) | 2018 NA(2) | 2017 NA(2) | 2016 NA(2) |
| --- | --- | --- | --- | --- | ---: |
| Ave. % U3O8 | NA(2) | NA(2) | NA(2) | 18.86% | 27.98% |
| Recovered Pounds U3O8 (000) | 144(3) | --- | 561(3) | 1,004(3) | 172(3) |
| Tailings Solution Recycle & In-Circuit Material(4) |  |  |  |  |  |
| Recovered Pounds U3O8 (000) | 47 | --- | 216 | 308 | 77 |
| Recovered Pounds V2O5 (000) | 67 | 1,807 | --- | --- | --- |
| Conventional Feed Materials |  |  |  |  |  |
| Tons (000) | --- | --- | --- | --- | 45 |
| Contained Grade % U3O8 | --- | --- | --- | --- | 0.5% |
| Recovered Pounds U3O8 (000) | --- | --- | --- | --- | 431 |
| Nichols Ranch(5) |  |  |  |  |  |
| Recovered Pounds U3O8 (000) | 6 | 70 | 140 | 259 | 335 |
| Alta Mesa |  |  |  |  |  |
| Recovered Pounds (000) | --- | --- | --- | --- | --- |
| **Total Pounds of U3O8 Recovered (000)** | **197** | **70** | **917** | **1,571** | **1,015** |
| **Total Pounds of V2O5 Recovered (000)** | **67** | **1,807** | --- | --- | --- |

### Notes:

(1) Mineralized material is shown as being processed and pounds recovered during the year in which the materials were processed at the White Mesa Mill or at the Nichols Ranch Plant, which is not necessarily the year in which the materials were extracted from the project facilities.

(2) All alternate feed materials were processed at the White Mesa Mill. A number of different alternate feed materials were processed during the period 2016 – 2020. The table shows the average uranium grades and the total pounds recovered from all alternate feed materials processed at the Mill during each of the years in that period. Because of the variability in uranium grades, pounds recovered is considered to be the relevant metric and tons fed is not considered to be relevant.

(3) The 144,000 pounds recovered in 2020 include nil pounds recovered for the accounts of third parties. The 561,000 pounds recovered in 2018 from alternate feed materials include 424,000 pounds recovered for the accounts of third parties. The 1,004,000 pounds recovered in 2017 include 952,000 pounds recovered for the accounts of third parties; and the 172,000 pounds recovered in 2016 include nil pounds recovered for the accounts of third parties.

(4) Pounds contained in tailings solutions containing previously unrecovered uranium and vanadium, together with in-circuit mineralized material from previous conventional mine material processing, were recovered at the White Mesa Mill, though tons and grade are not available because they cannot be tied to any specific source.

(5) Uranium recovery commenced at the Nichols Ranch Project on April 17, 2014. Because the Nichols Ranch Project uses ISR instead of conventional extraction methods, grade and tons of mineralized material are inapplicable to the Nichols Ranch Project.

#### Mineral Extraction

The following table shows the extraction history from 2016 to December 31, 2020 from the mineral properties currently owned by the Company:

*Nichols Ranch*

| Project(1) | 2020 | 2019 | 2018 | 2017 | 2016 |
| --- | ---: | ---: | ---: | ---: | ---: |
| Pounds (000) | 6 | 70 | 140 | 259 | 335 |

### Notes:

(1) All properties reported in this table were owned by the Company on December 31, 2020 and continue to be owned by the Company. Nichols Ranch was acquired by the Company in June 2015 as part of the Uranerz acquisition. Properties sold or otherwise disposed of are not included in this table.

### Summary of Mineral Reserves and Resources

Daniel Kapostasy, a Professional Geologist licensed in Wyoming (PG-6778) and in Utah (10110615-2250), employed as the Company’s Manager of Technical Services, is responsible for the disclosure of scientific or technical information concerning mineral projects in this Annual Report.

The following tables show the Company’s estimate of Mineral Reserves and Mineral Resources as of December 31, 2020. NI 43-101 requires mineral companies to disclose Mineral Reserves and Mineral Resources using the subcategories of Proven Mineral Reserves, Probable Mineral Reserves, Measured Mineral Resources, Indicated Mineral Resources and Inferred Mineral Resources. The Company reports Mineral Reserves and Mineral Resources separately. Properties sold or otherwise disposed of, or committed to be sold or otherwise disposed of, during 2019 or 2020 are not included in the table. Except as stated below, the Mineral Reserve and Mineral Resource information shown below is as reported in the various technical reports prepared in accordance with NI 43-101 (the “**Technical Reports”**) by qualified persons employed by Peters Geosciences, BRS Inc., SRK Consulting (U.S.) Inc., and Roscoe Postle Associates Inc. See “*Mineral Projects.”* The table below also reflects the Company’s adjustments to the resources as of December 31, 2020 at the properties where exploration and well installation drilling and/or extraction were in progress in 2020 – notably, at the Nichols Ranch Project. Note that the name of the Canyon Mine was changed to “Pinyon Plain Mine” in 2020. As no material changes have taken place at the Pinyon Plain as of the date of this Annual Report, the technical report has not been updated and still contains Canyon Mine in its title.

#### Mineral Reserve Estimates - Uranium(1)(2)(3)(4)(5)(6)

| Tons (000) | Proven Mineral Reserves Grade % eU3O8 | Pounds eU3O8 (000) | Tons (000) | Probable Mineral Reserves Grade % eU3O8 | Pounds eU3O8 (000) |  |
| --- | --- | --- | --- | ---: | ---: | ---: |
| Sheep Mountain - Congo Pit | --- | --- | --- | 3,955 | 0.115% | 9,117 |
| Sheep Mountain - Underground | --- | --- | --- | 3,498 | 0.132% | 9,248 |
| **Total Mineral Reserves** | --- | --- | --- | **7,453** | **0.123%** | **18,365** |

51

### Notes:

(1) The Mineral Reserve estimate for the Sheep Mountain Project is based on a technical report titled “*Sheep Mountain Uranium Project, Fremont County, Wyoming, USA, Updated Preliminary Feasibility Study, National Instrument 43-101 Technical Report, Amended and Restated”* dated February 28, 2020, prepared by Douglas L. Beahm, P.E., P.G., Principal Engineer of BRS Inc. in accordance with NI 43-101.

(2) The Mineral Reserve estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7.

(3) Mineral Reserves are estimated at a uranium grade x thickness (G.T.) cut-off grade of 0.10 G.T. (2 ft. of 0.05% eU3O8) for the Congo Pit and 0.45 G.T. (6 ft. of 0.075% eU3O8) for Sheep Underground.

(4) Mineral Reserves are estimated using a long-term uranium price of $60 per pound U3O8.

(5) Numbers may not add due to rounding.

(6) The Mineral Reserves are fully included in the total Mineral Resources shown below.

#### Mineral Resource Estimates – Uranium(1)(2)(3)(4)

*ISR Properties*

| Tons (000) | Measured Mineral Resources Grade % eU3O8 | Pounds eU3O8 (000) |  | Tons (000) | Indicated Mineral Resources Grade % eU3O8 | Pounds eU3O8 (000) |  | Tons (000) | Inferred Mineral Resources Grade % eU3O8 | Pounds eU3O8 (000) |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| Nichols Ranch(5) | 280 | 0.140% | 784 |  | 2,471 | 0.111% | 5,501 |  | 561 | 0.099% | 1,112 |
| Alta Mesa(6) | 123 | 0.151% | 371 | 1,512 | 0.107% | 3,246 | 6,964 | 0.120% | 16,794 |  |  |
| Other Powder River Basin Properties(7) | 310 | 0.062% | 387 | 1,198 | 0.130% | 3,115 | 2,823 | 0.106% | 6,008 |  |  |
| **ISR Subtotal** |  |  | **1,548** |  |  | **11,862** |  |  | **23,914** |  |  |
| **Conventional Properties** |  |  |  |  |  |  |  |  |  |  |  |
| Pinyon Plain(8) | 6 | 0.43% | 56 |  | 132 | 0.90% | 2,378 |  | 18 | 0.38% | 134 |
| Roca Honda(9) | 208 | 0.48% | 1,984 | 1,303 | 0.48% | 12,580 | 1,198 | 0.47% | 11,206 |  |  |
| Sheep Mountain(10) | --- | --- | --- | 11,662 | 0.12% | 27,935 | --- | --- | --- |  |  |
| Henry Mountains(11) | --- | --- | --- | 2,410 | 0.27% | 12,800 | 1,610 | 0.25% | 8,080 |  |  |
| La Sal(12) | 1,009 | 0.18% | 3,732 | 132 | 0.14% | 367 | 185 | 0.10% | 362 |  |  |
| Daneros | --- | --- | --- | 20 | 0.36% | 142 | 7 | 0.37% | 52 |  |  |
| Other Properties(13) | 240 | 0.16% | 772 | 201 | 0.28% | 1,122 | 742 | 0.35% | 5,248 |  |  |
| **Conventional Subtotal** |  |  | **6,544** |  |  | **57,324** |  |  | **25,082** |  |  |
| **Total Mineral Resources (eU3O8)** |  |  | **8,092** |  |  |  | **69,185** |  |  |  | **48,996** |

### Notes:

(1) The Mineral Resource estimates in this table comply with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7. Mineral resources that are not reserves do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

(2) Mineral Resources were estimated at various %eU3O8 or G.T. cut-off grades. Details regarding cut-off grade calculations for each project are given in the project’s respective section below.

(3) Mineral Resources were estimated at various long-term uranium prices. The specific long-term uranium price for each project is given in the project’s respective section below.

(4) Numbers may not add due to rounding.

(5) The numbers shown represent Energy Fuels share of the Nichols Ranch Project, which is less than 100% due to a portion that is held by the Arkose Mining Venture. The total Nichols Ranch Project Mineral Resources (100%) are shown in the Nichols Ranch section of this report, and include 0.86 million, 6.2 million, and 1.2 million pounds of measured mineral resources, indicated mineral resources, and inferred mineral resources, respectively. The Nichols Ranch Project is comprised of three properties: the Nichols Ranch Wellfield, the Hank Property and the Jane Dough Property. A portion of the Jane Dough Property is held through the Arkose Mining Venture, in which the Company has an 81% interest. The Mineral Resources shown in the table differ from those in the 2015 Nichols Ranch Technical Report due to adjustments made by the Company by subtracting recovered material (1,073,156 pounds) and adding additional resources discovered by drilling during well field installation (162,500 pounds). Nichols Ranch ISR began producing on April 15, 2014. Approximately 200,000 pounds were produced that year. The total production from Nichols Ranch is now 1,273,192 pounds eU3O8.

(6) Includes Alta Mesa and Mesteña Grande.

(7) The other Powder River Basin ISR properties include: the North Rolling Pin Property, the West North Butte Property, the East North Butte property, the Willow Creek property, and the East Buck, Little Butte, Sand Rock and South Doughstick properties in the Arkose Joint Venture. The Mineral Resources for the Arkose properties are included in the table as 81% of the total, which is Energy Fuels share.

(8) The name of the Canyon Mine was changed to “Pinyon Plain Mine” in 2020.

(9) The numbers do not include the historical resource estimate for the Adjacent Roca Honda Properties. See “*The Roca Honda Project,”* below.

(10) The Sheep Mountain Indicated Mineral Resource fully includes the Probable Mineral Reserves calculated in accordance with NI 43-101 of 18,365,000 pounds of eU3O8 in 7,453,000 tons at a grade of 0.123%. Such mineral resources do not constitute reserves under SEC Industry Guide 7.

(11) The Henry Mountains Complex includes the Tony M, Southwest, Indian Bench and Copper Bench properties.

(12) The La Sal Project includes the Energy Queen, Redd Block, Beaver, and Pandora properties.

(13) This includes all conventional Non-Material properties, including: Wate, EZ Project, Whirlwind, and the retained portion of Sage Plain.

#### Mineral Resource Estimate – Vanadium(1)(2)(3)(4)(5)

| Tons (000) | Measured Mineral Resources Grade % V2O5 | Pounds V2O5 (000) |  | Tons (000) | Indicated Mineral Resources Grade % V2O5 | Pounds V2O5 (000) |  | Tons (000) | Inferred Mineral Resources Grade % V2O5 | Pounds V2O5 (000) |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| La Sal(6) | 1,009 | 0.97% | 19,596 |  | 132 | 0.73% | 1,930 |  | 185 | 0.51% | 1,902 |
| Other Properties(7) | 240 | 1.32% | 6,350 | 201 | 0.94% | 3,797 | 447 | 0.74% | 6,660 |  |  |
| **Total Mineral Resources (V2O5)** |  |  | **25,946** |  |  |  | **5,727** |  |  |  | **8,562** |

### Notes:

(1) The Mineral Resource estimates in this table comply with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7. Mineral resources that are not reserves do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

(2) Mineral Resources were estimated at various %U3O8 or G.T. cut-off grades. Details regarding cut-off grade calculations for each project are given in the project’s respective section below.

(3) Mineral Resources were estimated at various long-term uranium prices. The specific long-term uranium price for each project is given in the project’s respective section below.

(4) Various vanadium to uranium ratios were used to calculate the vanadium grades and pounds given in the table. The specific ratio used for each project is given in the project’s respective section below.

(5) Numbers may not add due to rounding.

(6) The La Sal Project includes the Energy Queen, Redd Block, Beaver, and Pandora properties.

(7) Other Properties includes Whirlwind and the retained portion of Sage Plain.

#### Mineral Resource Estimate – Copper(1)(2)(3)(4)(5)(6)(7)

| Tons (000) | Measured Mineral Resources Grade % Cu | Pounds Cu (000) | Tons (000) | Indicated Mineral Resources Grade % Cu | Pounds Cu (000) | Tons (000) | Inferred Mineral Resources Grade % Cu | Pounds Cu (000) |  |
| --- | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: | ---: |
| Pinyon Plain | 6 | 9.29% | 1,203 | 94 | 5.70% | 10,736 | 5 | 5.90% | 570 |
| **Total Mineral Resources (Cu)** |  |  | **1,203** |  |  | **10,736** |  |  | **570** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7. Mineral resources that are not reserves do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

(2) For the Main and Main-Lower zones of the Pinyon Plain Mine, a 0.36% uranium equivalent cut-off grade (% U3O8 Eq) was applied to account for both the copper and uranium mineralization. In all other zones, only uranium was reported and a 0.29% U3O8 cut-off grade was applied. (The %U3O8 Eq grade term is not the same as the eU3O8 % grade term with indicates probe rather than assay data listed elsewhere in this report. For details see the Canyon Technical Report (as defined below; now the Pinyon Plain Project)).

(3) Mineral Resources are estimated using a long-term uranium price of $60 per pound and a Copper price of $3.50 per lb.

(4) A copper to U3O8 conversion factor of 18.19 was used for converting copper grades to equivalent U3O8 grades (U3O8 Eq) for cut-off grade evaluation and reporting.

(5) Numbers may not add due to rounding.

(6) For Pinyon Plain, Mineral Resource tonnages of uranium and copper cannot be added as they overlap in the Main and Main-Lower Zones.

(7) The name of the Canyon Mine was changed to “Pinyon Plain Mine” in 2020.

### The Nichols Ranch Project

Unless stated otherwise, the following description of the Nichols Ranch Project is derived from a technical report titled “*Nichols Ranch Uranium Project, 43-101 Technical Report, Preliminary Economic Assessment”* dated February 28, 2015, prepared by Douglas L. Beahm, P.E., P.G. of BRS Inc. and Paul Goranson, P.E., former Chief Operating Officer of the Company, in accordance with NI 43-101 (the “**Nichols Ranch Technical Report”**). The Nichols Ranch Technical Report includes an updated NI 43-101 mineral resource estimate and the results of a Preliminary Economic Assessment (“**PEA”**) for the uranium resources identified to date at the Nichols Ranch Project. Each of the authors is a “qualified person” within the meaning of NI 43-101, and Mr. Beahm is “independent” of the Company within the meaning of NI 43-101. Because the independent author of the Nichols Ranch Technical Report assumed overall responsibility for all items of the technical report, the report is therefore an independent technical report under NI 43-101. The Nichols Ranch Technical Report is available on SEDAR at www.sedar.com. The Nichols Ranch Project does not have known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite currently ongoing uranium recovery activities.

The Nichols Ranch Project is an ISR uranium recovery project, which the Company acquired in June 2015 through the acquisition of Uranerz. It is located in the Powder River Basin of northeast Wyoming. The Nichols Ranch Project includes: (i) the Nichols Ranch Plant; (ii) the Nichols Ranch Wellfield; (iii) the Jane Dough Property; and (iv) the Hank Project, which includes the planned Hank Satellite Plant and the Hank Property. The Nichols Ranch Project is an ISR project; it is not an underground or open pit project.

A map of the Nichols Ranch Project, including the Nichols Ranch Plant, the Nichols Ranch Wellfield, the Jane Dough Property and the Hank Property is shown below:

The Nichols Ranch Project is a fully permitted and licensed ISR facility that recovers uranium through a series of injection and recovery wells. Using groundwater fortified with oxygen and sodium bicarbonate, uranium is dissolved within a deposit. The groundwater is then collected in a series of recovery wells and pumped to the Nichols Ranch Plant. The Nichols Ranch Plant creates a yellowcake slurry that is transported by truck to the White Mesa Mill where it is dried and packaged into drums that are later shipped to a conversion facility.

The original plan for the Nichols Ranch Project included the construction of an ISR processing facility and a second uranium recovery and extraction facility at the Hank Project. The Company’s current extraction plan for the Nichols Ranch Project is now divided into three separate areas, being (i) the Nichols Ranch Wellfield, (ii) the Jane Dough Property, and (iii) the Hank Property. The Nichols Ranch Wellfield is, and the Jane Dough Property is expected to be, directly connected to the Nichols Ranch Plant via pipeline. The Hank Project is expected to consist of a uranium extraction and recovery facility that will create a loaded resin that will be trucked to the Nichols Ranch Plant for elution. The Nichols Ranch Wellfield consists of two production areas: Production Area #1 and Production Area #2. The Nichols Ranch Wellfield also includes the two deep disposal wells that are permitted and constructed for the Nichols Ranch Project. The Jane Dough Property is adjacent to the Nichols Ranch Wellfield to the south and contains certain properties that are 100% owned by Energy Fuels and other properties that are held in the Arkose Mining Venture, in which the Company owns an 81% interest. The Jane Dough Property contains two fully licensed and permitted extraction areas. The Hank Project is 100% owned by Energy Fuels and is located approximately six miles east of the Nichols Ranch Wellfield. The Hank Satellite Plant is fully licensed and permitted to be constructed and operate as a satellite to the Nichols Ranch Plant, and the Hank Property contains two targeted extraction areas.

Construction of the Nichols Ranch Plant was substantially completed in 2013, and extraction commenced in the second quarter of 2014 after final NRC inspections were completed. The Jane Dough Property described above has two fully licensed and permitted extraction areas. The Company completed construction of an elution and precipitation circuit at the Nichols Ranch Plant in early February 2016. Yellowcake slurry is now transported from the Nichols Ranch Plant to the White Mesa Mill for drying and packaging. However, the Nichols Ranch Plant is currently licensed to allow for the construction and operation of a drying and packaging circuit should conditions warrant.

The Nichols Ranch Project does not have known “reserves” under SEC Industry Guide 7 and is therefore considered under SEC Industry Guide 7 definitions to be “exploratory” in nature. During 2020, a total of approximately 6,000 pounds of U3O8 were recovered from the Nichols Ranch Project and nil pounds of mineralized material were added through drilling.

#### Accessibility, Local Resources, Physiography and Infrastructure

The Nichols Ranch Project site is located approximately 50 road miles southwest of Gillette, Wyoming and 76 road miles northeast of Casper, Wyoming in portions of Campbell and Johnson Counties, Wyoming in the Townships 41 to 45 North and Ranges 73 to 77 West. It is accessed from State Highway 50 from the east or State Highway 387 from the south, and various internal gravel-surface county and private roads. The city of Casper is located along Interstate 25, approximately one hour by air from either Denver, Colorado or Salt Lake City, Utah. The Nichols Ranch Project is accessible via two-wheel drive vehicle on existing county and/or private gravel and dirt roads.

The Nichols Ranch Project is located within the Wyoming Basin physiographic province in the central portion of the Powder River Basin, within the Pumpkin Buttes Mining District. The Pumpkin Buttes are a series of small buttes rising several hundred feet above the surrounding plains. Portions of the Powder River Basin properties are located east, west and south of these buttes. The cap rocks on top of the buttes are erosional remnants of the Tertiary White River Formation that is believed to have overlain the majority of the Powder River Basin. The volcanic tuffs in the White River Formation have been cited as a source of uranium in this basin.

The area in which the Powder River Basin properties is located is a low lying plain, and elevations range from approximately 4,390 feet (1,440 meters) in the northwest to approximately 5,450 feet (1,790 meters) in the southeast. Historically and currently, the land is used for livestock and wildlife grazing. Vegetation is characteristically sagebrush grassland with some pines on elevated terrain and some deciduous trees within drainages.

The climate is semi-arid and receives an annual precipitation of approximately 9.4 inches, the most falling in the form of late autumnal to early spring snows. The summer months are usually hot, dry and clear except for infrequent heavy rains. Cold, wind and snow/blizzards can make winter exploration work in this area difficult but not impossible. The weather may limit the time periods for capital construction but should not have any significant adverse impacts on the operation of an ISR facility.

Infrastructure at the site of the Nichols Ranch Project is predominantly related to local oil, gas, and coal bed methane exploration and development. Mineralized locations could affect future siting of wellfields and processing facilities. Generally, the proximity of the Nichols Ranch Project to paved roads is beneficial with respect to transportation of equipment, supplies, personnel and product to and from the property. Power transmission lines are located on or near parts of the property. The Company has secured power from the local electrical service provider to accommodate all operational needs. Water is available from wells developed at planned facility locations, and water for ISR operations comes from the operation itself, i.e. the extracted groundwater. Therefore, the basic infrastructure (power, water and transportation) that is required to support an ISR mining operation is located within reasonable proximity to the Nichols Ranch Project.

#### Ownership

The Company’s property interests vary widely, and include unpatented mining claims, private and state leasehold interests and surface use rights. Some agreements renew annually, some renew automatically when mineral extraction has commenced, and some are agreements for fixed terms. For the property agreements that expire in 2021, the Company may negotiate new agreements for only those acres that are within permit boundaries or critical project areas. Leases outside of such desired project areas may be allowed to expire, although the Company may seek to negotiate new agreements for those dropped properties in the future should market conditions warrant. The Company does not expect that the expiry of any property interests in 2021 and beyond, nor the forfeiture of any unpatented mining claims in 2021, will have a material effect on the Company’s ability to continue exploration and extraction activities on these properties.

Unpatented lode mining claims are located on minerals owned by the federal government and open to location, with the surface being owned by either the federal government or private individuals. In addition, the unpatented lode mining claims are recorded in the appropriate county and filed with the state office of the BLM. The unpatented lode claims do not have an expiration date. However, affidavits must be filed annually with the BLM and respective county recorder’s offices in order to maintain the claims’ validity. All of the unpatented lode mining claims have annual filing requirements ($165 per claim) with the BLM, to be paid on or before September 1 of each year. Most of the above-mentioned unpatented lode mining claims are located on Stock Raising Homestead land where the United States government has issued a patent for the surface to an individual and reserved the minerals to the United States government subject to the location rights by claimants as set forth in the federal Mining Act of 1872.

Leasehold interests are subject to the various terms as set forth in the applicable leases. The state leases and leases on fee mineral lands usually have annual payments, royalty obligations, and the terms of the leases vary, but for the most part can be extended by production (as defined in the leases). The fee surface and mineral leases apply only to uranium and other fissionable minerals and typically have a 10-year term with the right to extend the leases with production (as defined in the leases). Commingling of extraction from adjacent lands is allowable under the fee mineral leases.

Surface rights under applicable laws allow for exploration disturbance, road construction and facility siting. The claimant must first notify the surface owner of its intention to locate unpatented lode mining claims on the owner’s surface and then reach an agreement with the surface owner to pay for damages caused by the claimant’s operations. If an agreement cannot be reached, the claimant may post a bond with the BLM to cover the amount of the damages caused by the claimant’s operations. Surface use agreements were negotiated with various surface owners that provide the Company with all required surface access for the Nichols Ranch Project. The surface use agreements typically provide for reimbursement to the surface owner of actual damages resulting from operations.

#### Nichols Ranch Plant – 100% Energy Fuels

The Nichols Ranch Plant is located on the Nichols Ranch Project property pursuant to the surface use agreements described below.

#### Nichols Ranch Wellfield – 100% Energy Fuels

The Nichols Ranch Project, which includes the Nichols Ranch Plant and the Nichols Ranch Wellfield mining permit area, consists of 36 unpatented lode mining claims, two fee surface and mineral leases, and one surface use agreement encompassing approximately 920 acres. The Nichols Ranch Wellfield permit boundary encompasses approximately 1,120 acres. There is a portion of the Nichols Ranch Wellfield that includes private (fee) mineral that is subject to a royalty payable to the fee mineral owners under the fee leases. The royalty is a sliding scale of 6 to 8 percent, depending on the price of uranium. The primary term of the leases would have expired in 2017; however, they are held by production (as defined in the leases). The primary term of the surface use agreement would have expired in 2016, however the term has been held by production.

#### Hank Property – 100% Energy Fuels

The Hank Project, for which the Company has received a license to construct and operate a satellite plant to the Nichols Ranch Plant (known as the Hank Satellite Plant), consists of 66 unpatented lode mining claims and one surface use agreement encompassing approximately 1,393 acres. Two fee leases were allowed to expire in 2016, as they were not deemed to be significant to the project. The Hank Project permit boundary encompasses approximately 2,250 acres.

#### Jane Dough Property (Jane Dough/Doughstick – 100% Energy Fuels; North Jane and S. Doughstick – 100% Arkose Mining Venture, held 81% by Energy Fuels)

In 2017, the Company received its license amendment from the NRC, which includes the Jane Dough Property in the Nichols Ranch Project permit area, and combines the Jane Dough/Doughstick, North Jane and S. Doughstick properties consisting of 117 unpatented lode mining claims, 16 mineral leases, and three surface use agreements encompassing approximately 3,121 acres. Operating interests in the Jane Dough Property includes Energy Fuels’ 100% owned property and 81% from the two properties held by the Arkose Mining Venture. The Jane Dough Property permit amendment encompasses approximately 3,680 acres. The fee land in the project is covered by mineral leases some of which have annual payments and some of which are five-year paid-up leases. The mineral leases have primary terms of ten years and can be held by ongoing uranium extraction (as defined in the leases). Some of the leases expired in 2019. The fee surface is covered by three separate surface use agreements, which include damage payments paid on an annual basis. The mining leases have a variety of royalty payments based on a fixed rate, a two-tier system, or a sliding scale system.

One of the leases has a fixed royalty rate of 4% of the gross proceeds. Two of the leases have a two-tier royalty based on the price of U3O8 at the time of the sale, and they are 6% for a U3O8 price less than $75 per pound, and 8% for a U3O8 price equal to or greater than $75 per pound. Five of the leases have a sliding scale royalty that runs from a low of 2% at a U3O8 price of $25 per pound up to a high of 10% for a U3O8 price of equal to or greater than $100 per pound. Four leases have a sliding scale royalty that runs from a low of 4% at a U3O8 price of $40 per pound up to a high of 10% for a U3O8 price of equal to or greater than $100 per pound. Four of the leases have a sliding scale royalty that runs from a low of 4.5% at a U3O8 price of $49.99 up to a high of 10% for a U3O8 price of equal to or greater than $100 per pound. There are twenty (20) unpatented mining claims located in Section 32, Township 43 North, Range 76 West that have an overriding royalty interest of 0.25%. This overriding royalty interest is based on production of uranium on said claims. Two of the surface use agreements have a two-tiered royalty based on the sales price of the U3O8 received by

Uranerz, and they are 1% for a sales price of less than $50 per pound; and 2% for a sales price of equal to or greater than $50 per pound.

#### Uranium Severance Tax

The Company is required to pay a standard uranium industry severance tax of approximately 4% of sales and an ad valorem tax (annual property tax based on assessed values) to the State of Wyoming, in addition to various maintenance, land impact and access fees and other consideration to surface owners.

#### Permitting and Licensing

Energy Fuels has received all regulatory approvals necessary to conduct extraction and uranium processing activities at the Nichols Ranch Plant and Nichols Ranch Wellfield. In December 2010, Uranerz received its Permit to Mine for the Nichols Ranch Project from the WDEQ-LQD. In July 2011, Uranerz received a Source Material License from the NRC for the Nichols Ranch Plant and Nichols Ranch Wellfield, and construction of the Nichols Ranch Plant immediately began. Effective September 30, 2018, the State of Wyoming became an Agreement State under the Atomic Energy Act (as amended) for the regulation of uranium mills and uranium ISR facilities, and regulation of the Source Material License was transferred from the NRC to WDED-LQD.

Both the state and federal agencies analyzed all environmental aspects of the Nichols Ranch Project including reclamation of the land surface following extraction operations and restoration of impacted ground water. Workplace safety and the safety of the public are also closely monitored by regulatory agencies. We have posted a reclamation bond with the regulatory agencies in an amount of $6.8 million to cover the total estimated cost of reclamation by a third party as a requirement of the licenses.

The various state and federal permits and licenses that were required and have been obtained for the Nichols Ranch Project, exclusive of the expansion to the Jane Dough Property, are summarized below:

#### Primary Permits and Licenses for the Nichols Ranch Project (Nichols Ranch and Hank Units Only)

|  |  |  |
| --- | --- | --- |
| Permit, License, or Approval Name | Agency | Status |
| Source Material License | NRC (2011); WDEQ-LQD (2018) | Obtained |
| Permit to Mine (UIC Permit) | WDEQ-LQD | Obtained |
| Aquifer Exemption | WDEQ-LQD; EPA | Obtained |
| Permit to Appropriate Groundwater | WSEO | Obtained |
| Wellfield Authorization | WDEQ-LQD | Obtained |
| Class I UIC Deep Disposal Well Permits | WDEQ-WQD | Obtained |
| WYPDES | WDEQ- WQD | Obtained |
| Plan of Operations (Hank Unit only) | BLM | Obtained |
| Air Quality Permit | WDEQ-AQD | Obtained |

**Notes:** NRC - Nuclear Regulatory Commission

EPA - Environmental Protection Agency

UIC - Underground Injection Control

WDEQ-LQD - Wyoming Department of Environmental Quality Land Quality Division

WDEQ-WQD - Wyoming Department of Environmental Quality Water Quality Division

WDEQ-AQD - Wyoming Department of Environmental Quality Air Quality Division

WSEO - State Engineer’s Office

WYPDES - Wyoming Pollutant Discharge Elimination System

Under the licensed plan, the Nichols Ranch Plant has been built, and a satellite processing facility is licensed for the Hank Project. In 2017, the NRC approved a source material license amendment to add the Jane Dough Property to the existing license for the Nichols Ranch Project, and the Wyoming Department of Environmental Quality approved an amendment to our Permit to Mine to incorporate the Jane Dough Property. The Jane Dough Property is now fully licensed and permitted as part of the Nichols Ranch Project. The Jane Dough Property is adjacent to the Nichols Ranch Wellfield and is expected to share its infrastructure. We are now able to bring the Jane Dough Property into extraction operations before the Hank Project. Due to its close proximity, extracted solutions from the Jane Dough Property may be delivered directly to our Nichols Ranch Plant by pipeline, thus eliminating the need for a larger capital outlay to construct a satellite plant as is planned for the Hank Project. The Jane Dough Property includes the Doughstick, South Doughstick and North Jane properties. Additional wellfields may be added to the extraction operations plan as the Company continues to assess geological data.

#### Geology

The Nichols Ranch Project is located in the Powder River Basin. The mineralized trends within the Nichols Ranch Project are alteration-reduction trends hosted in the Eocene age channel sands that lie at depths of approximately 300 to 1,100 feet from the surface. Roll front deposits of uranium bearing material are anticipated to occur within these properties. An alteration-reduction trend is a natural chemical boundary trend line in a sandstone aquifer where reduced (non-oxidized) sand is in contact with altered (oxidized) sand. Uranium mineralization may be found along the trend line.

The properties in the Nichols Ranch Project contain alteration-reduction trends hosted in Eocene age channel sands. Alteration-reduction trends in the Pumpkin Buttes Mining District are typically composed of multiple, stacked roll front deposits that often contain associated uranium mineralization. A stacked roll front is a type of uranium occurrence found in thick sandstone where a number of mineralization trends are stacked on top of each other. Uranium mineralization within and adjacent to the Nichols Ranch Project are found in the Eocene Wasatch Formation (“**Wasatch”**). The Wasatch is a fluvial deposit composed of arkosic sandstones that are typically 25% or more feldspar grains and indicates a source rock where chemical weathering was not extreme, and the sediments have not been transported far. A fluvial deposit is a deposit of uranium mineralization found in sandstones that originated from sediments laid down by streams and rivers. The arkosic sandstone is a type of sandstone that contains a high percentage of feldspar grains. The medium grain size and relatively good sorting of this sediment implies water transportation, probably in a meandering river/stream system. The Wasatch Formation is interlaid with sandstones, claystones, siltstones, carbonaceous shale, and thin coal seams that overlie the Paleocene Fort Union Formation, another fluvial sedimentary unit.

#### History

The Nichols Ranch Project is located within the Pumpkin Buttes Mining District, which was the first commercial uranium extraction district in Wyoming. Uranium was first discovered in the Pumpkin Buttes in 1951. Intermittent uranium extraction from about 55 small mines occurred through 1967 producing 36,737 tons of material containing 208,143 pounds of uranium. This early mining activity focused on shallow oxidized deposits exploited by small open pit mines. The material was generally transported to the Atomic Energy Commission (“**AEC”**) buying station in Edgemont, South Dakota. Modern mining in the district has focused on deeper reduced deposits, including facilities operated by Cameco Corporation and Uranium One Inc.

The properties included in the Nichols Ranch Project were originally part of a large exploration area encompassing Townships 33 through 50 North of Ranges 69 through 79 West, on the 6th principal meridian. In 1966, Mountain West Mines Inc. (“**MWM,”** subsequently known as Excalibur Industries) began a successful drilling exploration program in a portion of this area. In 1967, MWM entered into an agreement with Cleveland-Cliffs Iron Company (“**CCI”**) for further exploration and an option if suitable resources were found. CCI exercised its option in 1976 with plans to begin underground mining operations in the vicinity of North Butte. Changing economic conditions and the introduction of ISR mining technology reportedly ended much of CCI’s interest in the area. By the late 1980’s, CCI began selling select properties or allowing them to revert to the federal government.

Between 1968 and 1980, CCI drilled 117 holes and installed 3 water wells on the Nichols Ranch Project area. Texas Eastern Nuclear Inc. in 1985 completed limited drilling and exploration on the property (approximately 28 borings) and in early 1990s Kerr McGee Corporation and Rio Algom Mining Corporation also completed limited drilling in the area.

#### Mineralization

The targeted mineralized zones for the Nichols Ranch Wellfield in the A Sand unit are 300 to 700 feet below the surface and occur in two long narrow trends meeting at the nose. The nose is in the northwest corner of the deposit where the two narrow trends meet to form the tip of the geochemical front. The Hank Project’s two targeted mineralized zones in the F Sand unit range from 200 to 600 feet below the ground surface depending on the topography and changes in the formation’s elevation and stratigraphic horizon. The targeted mineralization zone for the Jane Dough Property is the A Sand unit, the same as Nichols Ranch, at depths of 300 to 750 feet below the surface.

#### Mineral Resource Estimates

BRS prepared an updated NI 43-101 compliant Mineral Resource estimate for the Nichols Ranch Project in the Nichols Ranch Technical Report. The updated Mineral Resource estimate is effective as of January 1, 2015 and is summarized in the table below. Mineral Resources were estimated using the GT Contour method. The primary data used in evaluation are equivalent uranium values as quantified by downhole geophysical logging reported as %e U3O8. Radiometric equilibrium was evaluated and a disequilibrium factor (“**DEF”**) of 1 was used. The minimum uranium grade included in the estimate was 0.02% eU3O8. A minimum grade of 0.02% U3O8 and GT (grade x thickness) of 0.20 were used in the resource calculations. Mineral resources are reported at a cutoff of 0.20 GT, which is the cutoff applied at the Nichols Ranch Project. The table below provides a summary of Mineral Resources by classification following CIM guidelines. There are no Mineral Reserves on the property at this time. BRS noted that it is not aware of any known environmental, permitting, legal, title, taxation, socioeconomic, marketing, political, or other relevant factors that could materially affect the current resource estimate.

#### Nichols Ranch Remaining Mineral Resources – Uranium(1)(2)(3)(4)(5)(6)

| Classification | Property | Tons (000) | Grade % eU3O8 | Pounds eU3O8 (000) | Energy Fuels Pounds (000)(6) |
| --- | ---: | ---: | ---: | ---: | ---: |
| Nichols Ranch Measured Resources (M) | Nichols Ranch | 280 | 0.140% | 784 | 784 |
| Nichols Ranch Indicated Resources (I) | Nichols Ranch | 428 | 0.126% | 1,079 | 1,079 |
| Hank | 450 | 0.095% | 855 | 855 |  |
| Jane Dough | 1,892 | 0.112% | 4,237 | 3,567 |  |
| **Nichols Ranch Total (M & I)** |  | **3,050** | **0.115%** | **6,955** | **6,285** |
| Nichols Ranch Inferred Resources | Nichols Ranch | --- | --- | --- | --- |
| Hank | 423 | 0.095 | 803 | 803 |  |
| Jane Dough | 170 | 0.112 | 381 | 309 |  |
| **Nichols Ranch Inferred Total** |  | **593** | **0.100%** | **1,184** | **1,112** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

(2) Remaining Mineral Resource includes reduction for production of 1,073,156 pounds from December 31, 2014 through December 31, 2020.

(3) Nichols Ranch ISR began producing on April 15, 2014. Approximately 200,000 pounds were produced that year. The total production from Nichols Ranch is now 1,273,192 pounds eU3O8.

(4) Mineral Resources are estimated at a uranium grade x thickness (G.T.) cut-off grade of 0.20 G.T. (minimum 0.02% eU3O8).

(5) Mineral Resources are estimated using a long-term uranium price of $65 per pound.

(6) Numbers may not add due to rounding.

(7) “**Energy Fuels Pounds”** represent 100% of Nichols Ranch and Hank, and 81% of the Company's share of the portion of Jane Dough held by the Arkose Mining Venture.

Information shown in the table above differs from the disclosure requirements of the SEC. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

#### Activities Subsequent to Nichols Ranch Technical Report

Subsequent to the completion of the Nichols Ranch Technical Report, the Company has continued to operate and advance the Nichols Ranch Project, as described below. The information contained in this subsection entitled “*Activities Subsequent to Nichols Ranch Technical Report”* was prepared by the Company and has not been reviewed or confirmed by the authors of the Nichols Ranch Technical Report.

#### Wellfield Development and Exploration Completed by Energy Fuels

Prior to its acquisition by Energy Fuels in June 2015, Uranerz drilled 257 exploration holes, including three core holes and three water wells at the Nichols Ranch Project during 2006 and 2007 and 25 exploration holes and seven wells in 2009. In addition,

Uranerz drilled 61 exploratory holes and seven wells within the Hank Property during 2006 and 2007 and eight additional wells in 2009. There has been no new drilling activity at the Hank Project since 2009. Uranerz drilled 691 exploration holes and 29 wells for baseline monitoring at the Jane Dough Property. There has been no new drilling at the Jane Dough Property since 2010.

Uranerz drilled a total of 78 rotary drill holes on the Hank Property, Nichols Ranch Wellfield, and Jane Dough Property during 2006, with 46 holes demonstrating uranium mineralization. During 2006, environmental permitting activities also continued at the Hank Property and Nichols Ranch Wellfields with the completion of a total of five hydrogeologic test wells, and the drilling of six core holes. The core was submitted for laboratory testing to support permitting requirements as well as to define resource disequilibrium attributes.

From February 19 to December 20, 2007, Uranerz drilled a total of 486 uranium trend delineation holes and eight hydrologic sampling wells on the Nichols Ranch Project, utilizing as many as three drill rigs and one electric log probing unit. This represents a total of approximately 300,000 feet of drilling with an average depth of 617 feet per hole. A total of 214 delineation holes were drilled on Nichols Ranch in 2007. In the final months of the 2007 drilling program, exploration efforts focused on the Hank Property and Nichols Ranch Wellfield to facilitate sub-surface geologic mapping with cross sections and to refine previous geologic models delineating known trends of uranium mineralization.

During 2008, no new exploration work was undertaken at the Nichols Ranch Wellfield.

During 2009, 51 delineation holes were drilled at the Nichols Ranch Wellfield, including the Doughstick and North Nichols Ranch properties. The purpose of this drilling was primarily to prepare for the installation of baseline monitor wells for the planned Nichols Ranch Plant. Additional drilling was carried out on the Doughstick properties.

During 2011, 38 delineation holes were drilled in 2011 on the Nichols Ranch Wellfield. The purpose of this drilling was for final delineation drilling prior to beginning the monitor well and extraction well installation in Production Area #1 of the Nichols Ranch Wellfield.

During 2012, Uranerz engaged in drilling exploration efforts and wellfield installation at Production Area #1 at the Nichols Ranch Wellfield. At Production Area #1, 263 extraction wells were cased and cemented. The extraction wells were connected to header houses with buried feeder lines. It was planned that initial extraction should begin with four header houses. Three header houses were set on their foundations in 2012 and connected to individual extraction wells.

The Uranerz 2013 and 2014 drilling programs at the Nichols Ranch Wellfield were restricted to adding extraction and monitor wells. No new exploration drilling was conducted.

During 2015, Uranerz engaged in drilling delineation efforts and wellfield installation at Production Area #1 of the Nichols Ranch Wellfield, where 283 extraction wells were cased and cemented. At Production Area #2 of the Nichols Ranch Wellfield, 51 monitor wells were cased and cemented. The extraction wells were connected to header houses with buried feeder lines. Initial extraction at the Nichols Ranch Wellfield began with four header houses. In 2015, two additional header houses (#5 and #6) were set on their foundations and connected to the individual extraction wells.

In 2016, the Company completed drilling 12 delineation holes and drilling and casing of 86 extraction wells in Header Houses #7 and #8 in Production Area #1. Header House #7 was turned on in March of 2016 and Header House #8 was turned on in June of 2016. In Production Area #2, 133 extraction and injection wells were drilled and cased.

Header House #9 was completed and turned on in March of 2017. No drilling or other development activities were performed since 2017.

#### Current Status of Wellfields

All the currently planned and permitted wellfields are in Production Areas #1 and #2 of the Nichols Ranch Wellfield. The Nichols Ranch Wellfield is expected to have a total of 13 header-houses, with Production Area #1 comprising header-houses 1 through 8, and Production Area #2 comprising header-houses 9 through 13. Each of the two planned Nichols Ranch Wellfield Production Areas will include a number of injection wells, recovery wells, monitoring wells, header houses and associated piping and power supply. Header houses will be located within the Production Areas and will distribute recovered fluids from recovery wells to trunk lines, and injection fluids from the processing facility through the trunk lines to injection wells. See the map below illustrating Production Areas #1 and #2, and the plant.

The first five header houses and their respective wellfields in Production Area #1 at the Nichols Ranch Wellfield were installed and extracting uranium at the time we acquired Uranerz in June 2015. Header house #6 was turned on in November 2015. The Company placed the 7th and 8th header-houses on-line in March and July 2016, respectively, thereby completing development of Production Area #1. In February 2017 we completed construction on our 9th header-house, marking the beginning of development in Production Area #2. Uranium recovery operations from Production Area #2 commenced in March of 2017. Nichols Ranch is currently on standby and is engaged in reduced uranium recovery activities in Production Area #1 and Production Area #2. In order for Nichols Ranch to engage in future uranium production, the Company will need to incur capital expenditures to develop additional wellfields.

#### Nichols Ranch Plant

In 2014, construction of the Nichols Ranch Plant was completed. The Nichols Ranch Plant is licensed to produce up to two million pounds of uranium per year through three major processing solution circuits: (i) a recovery and extraction circuit; (ii) an elution circuit; and (iii) a yellowcake production circuit. The Nichols Ranch Plant is currently constructed and operated with the recovery and extraction circuit and the elution circuit installed. We retain the ability to construct and operate a yellowcake drying and packaging circuit at the Nichols Ranch Plant at a later date if desired.

The Nichols Ranch Plant is currently on standby, but is still processing uranium-bearing wellfield solutions from Production Areas #1 and #2 of the Nichols Ranch Wellfield. Yellowcake slurry, produced at the Nichols Ranch Plant, is shipped by truck from the Nichols Ranch Project to the White Mesa Mill where it is dried and packaged in drums as uranium concentrate product. Prior to the completion of the elution circuit in February 2016, loaded resin was transported by truck to a third-party facility for elution, drying and packaging, under a toll processing arrangement.

In August 2020, deep disposal well #1 (NICH-DW-1) was placed back into operation after a successful work-over.

The Nichols Ranch Plant was acquired by the Company on June 18, 2015 through the acquisition of Uranerz. As of December 31, 2020, the total cost attributable to the Nichols Ranch Plant on the Company’s financial statements was $29.21 million.

#### The Company’s Planned Work

Nichols Ranch is currently on standby, with its existing wellfields having been depleted as of the end of the first quarter of 2020. In order for Nichols Ranch to engage in future uranium production, the Company will need to incur capital expenditures to develop additional wellfields. A decision to commence development will be made if the Company decides to take action in response to the proposed establishment of a U.S. Uranium Reserve or uranium prices otherwise improve to a point where the economic feasibility of the Nichols Ranch Project is realized.

As a result of the Company’s WDEQ license and permit amendment approvals, it is now possible to expand extraction operations to the Jane Dough Property before expanding to the Hank Project.

The Hank Project, including the permitted but not constructed Hank Satellite Plant and planned Hank wellfield, is currently licensed as a satellite uranium extraction and recovery facility, with loaded resin from the satellite facility, when constructed, expected to be transported by truck to the Nichols Ranch Plant for elution. Construction activities at the Hank Project will not commence until market conditions warrant. In the future, we will consider whether to amend our current license for the Hank Project to include a pipeline to our Nichols Ranch Plant, which would replace or eliminate the currently permitted satellite ion exchange recovery facility. If market conditions warrant construction activities at the Hank Project, our extraction plan for the Hank Property will likewise target two planned extraction areas. Should market conditions warrant, the Jane Dough and Hank Properties would be expected to follow a similar construction, extraction, and restoration schedule as outlined above for the Nichols Ranch Wellfield extraction areas.

### The Alta Mesa Project

Unless stated otherwise, the following description of the Alta Mesa Project is derived from a technical report titled, “*Alta Mesa Uranium Project, Alta Mesa and Mesteña Grande Mineral Resources and Exploration Target, Technical Report National Instrument 43-101”* dated July 19, 2016, prepared by Mr. Douglas Beahm, P.E., P.G. of BRS Inc. in accordance with NI 43-101 (the “**Alta Mesa Technical Report”**). The author is a “qualified person” within the meaning of NI 43-101, and because the sole author is “independent” of the Company within the meaning of NI 43-101 the report is therefore considered an independent technical report under NI 43-101. The Alta Mesa Technical Report is available on SEDAR at www.sedar.com. The Alta Mesa Project does not have any known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite its history of uranium recovery activities. No current preliminary economic assessment, pre-feasibility study or feasibility study has been completed.

The Alta Mesa Project is a fully-licensed ISR uranium recovery facility that the Company acquired in June 2016 through the acquisition of EFR Alta Mesa LLC (previously named Mesteña Uranium LLC). It is located in South Texas and is currently on standby. The Alta Mesa Project is not an underground or open pit project.

The Alta Mesa central processing facility and mine office is located at 755 CR 315, Encino, Texas 78353, in Brooks County, Texas, at approximately 26° 54’ 08” North Longitude and 98° 18’ 54” West Latitude. The site is located approximately 11 miles west of the intersection of US 281 and Ranch Road 755, which is 22 miles south of Falfurrias, Texas.

The Project is located within a portion of the private land holdings of the Jones Ranch, founded in 1897. The ranch comprises approximately 380,000 acres. The ranch holdings include surface and mineral rights including oil and gas and other minerals including uranium. Active uses of the lands in addition to uranium exploration and production activities include agricultural use (cattle), oil and gas development, and private hunting.

The Project consists of Uranium Mining Leases for uranium ISR mining (4,598 acres) and Mineral Options (195,501 acres) comprising some 200,099 total acres. The Project is defined as constituting two distinct project areas with sufficient drilling to define resources. These two areas are subdivided, as listed below and illustrated on the map on the following page:

- The Alta Mesa project area, Brooks County, Texas, comprising 16,010 acres, including,
- The Alta Mesa mine area and central processing facility
- South Alta Mesa
- Indigo Snake
- The Mesteña Grande project area, Jim Hogg County, Texas, comprising 47,088 acres, including,
- Mesteña Grande Goliad
- Mesteña Grande North
- Mesteña Grande Central
- Mesteña Grande Alta Vista
- El Sordo

The remaining 137,002 acres lack sufficient exploration drilling to define any resources at this time.

#### Accessibility, Local Resources, Physiography and Infrastructure

The Project is located primarily in Brooks and Jim Hogg counties, Texas, with the central processing facility in Brooks County. Brooks County is generally rural and according to the 2010 United States Census, there were 7,223 people living in the county. The population density was 8 people per square mile. Most of the workers for the operation are from the local area and nearby communities such as Kingsville, Texas approximately 40 miles from the site. Some staff members commute from Corpus Christi, Texas approximately 90 miles from the site.

The Project is located in the coastal plain of the Gulf of Mexico. Topography of the lower Gulf Coast is relatively flat, whereas the upper Gulf Coast, including most of the current and past mining operations of the South Texas Uranium Province, generally has low relief, rolling plains, except where it is locally dissected by rivers and streams. Elevations range from sea level to about 800 ft. in the southwest. Three major rivers from south to north are: the Nueces River, which flows into Corpus Christi Bay, and the San Antonio and Guadalupe Rivers, which flow into San Antonio Bay southeast of the city of Victoria.

The Project is accessible year-round. The site is located approximately 11 miles west of the intersection of US Highway 281 (paved) and Ranch Road 755 (paved), 22 miles south of Falfurrias, Texas. Commercial airlines serve San Antonio, Corpus Christi and Harligen. Many of the local communities have small airfields and there are numerous private airfields in the region.

In general, the climate is warm and dry, with hot summers and relatively mild winters. However, the region is strongly influenced by its proximity to the Gulf of Mexico and, as a result, has a much more marine-type climate than the rest of Texas, which is more typically continental. Monthly mean temperatures in the region range from 55oF in January to 96oF in August. The area rarely experiences freezing conditions and, as a result, the majority of the processing facility and infrastructure is located outdoors. Wellfield piping and distribution lines do not require burial for frost protection. Annual precipitation ranges from 20 to 35 inches regionally. Primary risk for severe weather is related to heavy thunderstorms and the effects of hurricanes along the Gulf Coast.

Local infrastructure includes electricity service, which is adequate for mine and mineral processing activities. The Alta Mesa facility also has telephone and internet service in the form of a T-1 fiber optics line. The plant has an automated control and monitoring system, which allows remote monitoring of the facility, and includes fail safe systems, which can shut down portions of the system in the event of an upset condition. The facility is fully secured with on-site and remote monitoring. Water supply for the Project is from established and permitted local wells. Liquid waste from the processing facility is disposed of via deep well injection through two permitted Class I UIC disposal wells. Solid waste from the processing facilities is disposed of off-site at licensed disposal facilities. No tailings or other related waste disposal facilities are needed.

The Project is located on an operating cattle ranch. In addition, there is significant local oil and gas development and production. The Alta Mesa area was first developed as an oilfield in the 1930s with production ongoing, primarily for natural gas. Other land uses include farming and recreational uses, such as hunting.

The area is regionally classified as a coastal sand plain. Brooks County comprises 942 square miles of brushy mesquite land. The level to undulating soils are poorly drained, dark and loamy or sandy; isolated dunes are found. In the northeast corner of the county the soils are light-colored and loamy at the surface and clayey beneath.

The mineral leases and options described below include provisions for reasonable use of the land surface for the purposes of ISR mining and mineral processing. Alta Mesa is a fully licensed, operable facility with sufficient sources of power, water, and waste disposal facilities for operations and aquifer restoration. While the current staff level has been reduced, sufficient local personnel are available for mine operations.

#### Ownership

Mineral ownership in Texas is a private estate. Private title to all land in Texas emanates from a grant by the sovereign of the soil (successively, Spain, Mexico, the Republic of Texas, and the state of Texas). By a provision of the Texas Constitution the state released to the owner of the soil all mines and mineral substances therein. Under the Relinquishment Act of 1919, as subsequently amended, the surface owner is made the agent of the state for the leasing of such lands, and both the surface owner and the state receive a fractional interest in the proceeds of the leasing and production of minerals.

The Project consists of a private Uranium Solution Mining Lease (4,598 acres) and Options (195,501 acres) for uranium comprising some 200,100 total acres consisting of acreage associated with currently approved mining permits issued by the Texas Commission on Environmental Quality and 9 prospect areas.

The Uranium Solution Mining Lease, originally dated June 1, 2004, covers approximately 4,575 acres out of the “La Mesteñas” Ysidro Garcia Survey, A-218, Brooks County, Texas and “Las Mesteñas Y Gonzalena” Rafael Garcia Salinas Survey, A-480, Brooks County, Texas (description corrected in a later amendment). This original Uranium Solution Mining Lease has been superseded by the Amended and Restated Uranium Solution Mining Lease dated June 16, 2016, as part of the share purchase agreement between the Company and the various former holders of the Alta Mesa Project. The Lease now covers uranium, thorium, vanadium, molybdenum, other fissionable minerals, and associated minerals and materials under 4,597.67 acres. The term of the amended lease is fifteen (15) years commencing on June 16, 2016 or so long as the lessee is continuously engaged in any mining, development, production, processing, treating, restoration or reclamation operations on the leased premises. The amended lease can be extended by the Lessee for an additional 15 years upon payment of a stipulated cash payment. The lease includes provisions for royalty payments on the net proceeds (less allowable deductions) received by the Lessee. The royalty payment is 7.5% of Market Value of Product sold at a uranium price greater than $95.00 per pound, 6.25% of Market Value of Product sold at a uranium price greater than $65.00 and up to and including $95.00 per pound, and 3.125% of the Market Value of Product sold at a uranium price of $65.00 or less per pound.

The Uranium Testing Permit and Lease Option Agreement, originally dated August 1, 2006, covers all of the land containing mineral potential as identified through exploration efforts and covers uranium, thorium, vanadium, molybdenum, and all other fissionable materials, compounds, solutions, mixtures, and source materials, has been superseded by the Amended and Restated Uranium Testing and Lease Option Agreement dated June 16, 2016, as part of the share purchase agreement between the Company and the various holders of the Alta Mesa Project. It now covers some 195,501.03 acres. The term of the amended lease and option agreement is for eight years commencing June 16, 2016. The amended lease and option agreement can be extended by the grantee for an additional seven years. Certain payments by the Grantee to the Grantor are required prior to year three of the initial eight-year lease. The amended Lease Option Agreement provides for designating acreage to be leased for production by making certain payments to the Grantor (cash or stock). If acreage designation occurs within the first three years of the initial eight-year lease, the payments will be deducted from the certain payments required by year three in the lease option agreement. The Grantor then has sixty business days to execute and return the lease.

Amended surface use agreements have been entered in to with all surface owners on the various prospect areas as part of the Membership Interest purchase agreement between the Company and the various former holders of the Alta Mesa Project. These amended agreements, unchanged from those originally entered in to on June 1, 2004, provide, among other things, for stipulated damages to be paid for certain activities related to the exploration and production of Uranium. Specifically, the agreements call for Consumer Price Index adjusted payments for the following disturbances: exploratory test holes, development test holes, monitor wells, new roads, and related surface disturbances. The lease also outlines an annual payment schedule for land taken out of agricultural use around the area of a deep disposal well, land otherwise taken out of agricultural use, and pipelines constructed outside of the production area.

Surface rights are expressly stated in the lease and in general provide the lessee with the right to ingress and egress, and the right to use so much of the surface and subsurface of the leased premises as reasonably necessary for ISR mining. Open pit and/or strip mining is prohibited by the lease.

Ad valorem tax rates per $100 of taxable value applicable to tangible property for 2016 were as follows:

Brooks County 0.743829

Brooks County Rd and Bridge 0.150000

Brooks County ISD 1.572555

Brooks County FM FC 0.098837

Brush Country Groundwater 0.026020

\[*See map below\]*

#### Permitting and Licensing

The Alta Mesa Project area is fully permitted for ISR mining and recovery of uranium. The table below summarizes the current permits held by EFR Alta Mesa. Similar permits would be required for the Mesteña Grande project area depending upon the nature of operations and their integration with the Alta Mesa facility.

#### Primary Permits and Licenses for the Alta Mesa Project

| Permit, License or Approval Name | Agency | Status |
| --- | --- | --- |
| Radioactive Material License | TCEQ | Obtained |
| Class III UIC Mine Area Permit | TCEQ | Obtained |
| Aquifer Exemption | TCEQ | Obtained |
| Production Area Authorization | TCEQ | Obtained |
| Class I UIC Deep Disposal Well Permits | TCEQ | Obtained |

### Notes:

TCEQ - Texas Commission on Environmental Quality

UIC - Underground Injection Control

The ISR processing facility at Alta Mesa has an operating capacity of 1.5 million pounds of uranium per year. Primary regulatory authority resides with the State of Texas. Financial assurance instruments are held by the state for completed wells, ISR mining, and uranium processing to ensure reclamation and restoration of the affected lands and aquifers in accordance with state regulations and permit requirements.

#### History

Alta Mesa was first discovered in the mid-1970s by Chevron Resources as a result of researching oil and gas logs for natural gamma geophysical signatures. Chevron controlled the Alta Mesa portion of the project through June of 1985 when they returned the mineral lease due to Chevron exiting the uranium business. Chevron reportedly drilled a total of 360 holes inclusive of exploration drilling, coring, and well completion during a four-year period from 1981 through 1984. In July of 1988 Total Minerals Incorporated (“**Total”**) executed a lease agreement for the Alta Mesa portion of the project. Total also engaged Uranium Resources Incorporated (“**URI”**) to complete a feasibility study for the project. The Total mineral lease was terminated as a result of the French Government requiring Total to sell all their uranium assets to Cogema.

Subsequently, the Project was evaluated by Cogema in 1994 and later by URI. URI held the mineral lease and obtained the Radioactive Material License during the period of 1996 through 1998. EFR Alta Mesa (previously named Mesteña Uranium LLC) was formed in 1999 and continued permitting activities in April of 2000 and completed licensing in 2003. Plant construction at Alta Mesa began in 2004 with initial production in the 4th quarter of 2005. The Project produced approximately 4.6 million pounds of uranium oxide between 2005 and 2013 via ISR mining. The facility was in production from 2005 until primary production ceased in February 2013. The Project operated in a groundwater clean-up mode until February 2015; therefore, any uranium mined since 2013 remains as in-circuit inventory.

#### Geology

The Alta Mesa Project is located within the Texas Gulf Coast along a belt of Tertiary and Quaternary sedimentary formations. The Project is located within the South Texas Uranium Province, which is known to contain more than 100 uranium deposits that were developed in the second half of the 20th century.

Regionally, uranium deposits are hosted by four formations:

- Miocene/Pliocene Goliad Formation, consisting of fluvial deposits, mostly unconsolidated sands.
- Miocene Oakville Formation, consisting of fluvial deposits (sands, some clay).
- Oligocene/Miocene Catahoula Formation, consisting of fluvial deposits, mostly sands, clay, and clastic volcanic rich sediments.
- The Jackson Group consisting of fluvial deposits sands, silt, clay, and lignite.

At the Alta Mesa Project, in order of importance, uranium is hosted by the Goliad, Oakville, and Catahoula formations.

South Texas uranium deposits are sandstone roll-front uranium deposits. The key components in the formation of roll-front type mineralization include:

- A permeable host formation:
- Sandstone units of the Goliad, Oakville, and Catahoula formations.
- A source of soluble uranium:
- Volcanic ash-fall tuffs coincidental with Catahoula deposition containing elevated concentration of uranium is the probable source of uranium deposits for the South Texas Uranium Province.
- Oxidizing ground waters to leach and transport the uranium:
- Ground waters regionally tend to be oxidizing and slightly alkaline.
- Adequate reductant within the host formation:
- Conditions resulting from periodic H2S gas migrating along faults and subsequent iron sulfide (pyrite) precipitation created local reducing conditions.
- Time sufficient to concentrate the uranium at the oxidation/reduction interface:
- Uranium precipitates from solution at the oxidation/reduction boundary (REDOX) as uraninite which is dominant (UO2, uranium oxide) or coffinite (USiO4, uranium silicate).
- The geohydrologic regime of the region has been stable over millions of years with ground water movement controlled primarily by high-permeability channels within the predominantly sandstone formations of the Tertiary.

The structural map of the Gulf Coast area is dominated by an abundance of growth faults that trend with, or are slightly oblique to, stratigraphic strike, which is roughly parallel to the Gulf of Mexico. In addition, local structural features such as salt domes influence the distribution and deposition of uranium mineralization potentially through various mechanisms including effects on ground water flow and the introduction of additional reductant via the migration of H2S gas along the faulting related to the salt dome intrusion. This mechanism is thought to be of importance at Alta Mesa.

#### Mineralization

The Alta Mesa Project is located in the South Texas Uranium Province. Mineralization within the South Texas Uranium Province is interpreted to be dominantly roll-front type mineralization and primarily of epigenetic origin. Roll-fronts are formed along an interface between oxidizing ground water solutions, which encounter reducing conditions within the host sandstone unit. This boundary between oxidizing and reducing conditions is often referred to as the REDOX interface or front. Mineralization tends to be very continuous.

Within the Alta Mesa portion of the Project, Quaternary formations are exposed at the surface. These are conformably underlain by the Goliad Formation, the primary uranium host. Alta Mesa ISR mine units have exploited uranium mineralization in the Goliad C sands within wellfields PAA-1, PAA-2, PAA-3, PAA-4, and PAA-6. The B sand was targeted in wellfield PAA-5. Mineral resources have been estimated for the A, B, C, and D sands. Exploration targets in the South Alta Mesa area lie within successively deeper D, E, F, G, and H sands of the Goliad.

Within the Mesteña Grande portion of the project, mineralization is also present in the Goliad Formation but is dominantly found in the Oakville Formation. In the western portion of Mesteña Grande mineralization is found in the Catahoula Formation. Mineral resources have been estimated for all areas within the Mesteña Grande portion of the project.

#### Present Condition of the Property and Work Completed to Date

The Alta Mesa Project produced approximately 4.6 million pounds of uranium oxide between 2005 and 2013 via In Situ Recovery mining. The facility was in production from 2005 until primary production ceased in February 2013. The Project operated in a groundwater clean-up mode until February 2015; therefore, any uranium mined since 2013 remains as in-circuit inventory. The first wellfield (PAA-1) has undergone restoration, and the groundwater has been released by the State of Texas. In 2018, all of the cased wells associated with PAA-1 were plugged as per permit requirements. All other wellfields are being maintained by a small bleed (less than 100 gpm) for permit compliance. The bleed solutions are disposed of in the deep disposal wells.

Drill data is available for a total of 10,744 drill holes of which approximately 3,000 are within existing wellfields. The primary assay data for the Project is downhole geophysical log data. EFR Alta Mesa relied entirely on prompt-fission-neutron (“**PFN”**) logging for uranium grade assay and used natural gamma logging to screen intervals for PFN logging. Of the 10,744 drill holes in the Alta Mesa database, PFN logging was not available for only 7.2% of the drill holes. For the Mesteña Grande portion of the Project, all 460 drill holes were completed by EFR Alta Mesa and all gamma intercepts greater than 0.02 % eU3O8 were logged by PFN.

For determination of uranium grade, EFR Alta Mesa LLC relied on PFN log data for 92.8% of the data, which is a direct measurement of uranium content and not an equivalent radiometric assay. As a result, assessment of disequilibrium factor (“**DEF”**) is not applicable.

In 2019, the Company performed significant surface decommissioning work in PAA-1. The Project was maintained in a standby mode during 2020.

As of December 31, 2020, the total cost attributable to the Alta Mesa Project on the Company’s financial statements was $13.63 million.

Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions, the Company expects to continue to keep the Alta Mesa Project on standby until such time as improvements in uranium market conditions are observed or suitable sales contracts can be procured. Alta Mesa is capable of resuming production within a relatively short period of time after a positive production decision by the Company, with only minimal capital requirements.

#### Mineral Resource Estimates

Mineral resources have been estimated for both the Alta Mesa and Mesteña Grande areas by Douglas Beahm of BRS Inc. in accordance with CIM standards and definitions and are summarized in the respective tables below. Mineral Resources for the Alta Mesa Project are estimated by classifications, meeting CIM standards and definitions as measured, indicated, and inferred mineral resources, at a 0.30 GT cutoff.

There are no Mineral Reserves on the property at this time. Mr. Beahm of BRS Inc. noted that he is not aware of any known environmental, permitting, legal, title, taxation, socioeconomic, marketing, political, or other relevant factors that could materially affect the current resource estimate.

#### Alta Mesa and Mesteña Grande Resource Summary

#### Alta Mesa and Mesteña Grande Mineral Resources – Uranium(1)(2)(3)(4)

| Classification | Tons (000) | Grade % eU3O8 | Pounds eU3O8 (000) |
| --- | ---: | ---: | ---: |
| Total Measured Resources (M)(5) | 123 | 0.151% | 371 |
| Alta Mesa Indicated Resources (I) | 1,393 | 0.106% | 2,959 |
| Mesteña Grande Indicated Resources (I) | 119 | 0.120% | 287 |
| **Total (M & I)** | **1,635** | **0.111%** | **3,617** |
| Alta Mesa Inferred Resources | 1,230 | 0.128% | 3,192 |
| Mesteña Grande Inferred Resources | 5,733 | 0.119% | 13,601 |
| **Total Inferred Resources** | **6,963** | **0.121%** | **16,793** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources are estimated at a uranium grade x thickness (G.T.) cut-off grade of 0.30 G.T. (minimum 0.02% eU3O8).

(3) Mineral Resources are estimated using a long-term uranium price of $65 per pound.

(4) Numbers may not add due to rounding.

(5) The Total Measured Mineral Resource is that portion of the in-place mineral resource that is estimated to be recoverable within existing wellfields. Wellfield recovery factors have not been applied to indicated and inferred mineral resources.

### The White Mesa Mill

#### General

The White Mesa Mill is a fully licensed uranium and vanadium processing facility located in southeastern Utah, approximately six miles south of the city of Blanding, Utah. It is within trucking distance of the Company’s conventional properties in Utah, Colorado, Arizona and New Mexico, including the Pinyon Plain Project, the Roca Honda Project, the Henry Mountains Complex, the La Sal Project and the Daneros Project. The Mill is the only fully operational and licensed conventional uranium mill in the U.S. It is capable of functioning independently of off-site support except for commercial power from Rocky Mountain Power and as-needed supplemental water supply from the City of Blanding, Utah, and the San Juan Water Conservancy District. The White Mesa Mill is a uranium processing and recovery facility. It is not an underground or open pit project.

The Mill is licensed to process an average of 2,000 tons of ore per day and to extract over 8.0 million pounds of U3O8 per year. In addition to the conventional circuit, the Mill has a separate vanadium by-product recovery circuit.

In addition to the Mill processing equipment, which includes the grinding and leaching circuits, CCD (liquid–solid separation), solvent extraction, and precipitation and drying circuits, the Mill has several days of reagent storage for sulfuric acid, ammonia, salt, soda ash, caustic soda, ammonium sulfate, flocculants, kerosene, amines, and liquefied natural gas.

The on-site infrastructure also includes a stockpile area capable of storing up to 450,000 tons of mineralized material, and existing tailings capacity of approximately 3.5 million tons of solids. In addition, the Mill has approximately 90 acres of evaporation capacity.

Synthetic lined cells are used to contain tailings and solutions for evaporation. The Company operates two tailings cells and one or more evaporation ponds during normal operations. As each tailings cell is filled, the water is drawn off and pumped to an evaporation pond and the tailings solids are allowed to dry. As each tailings cell reaches final capacity, reclamation begins with the placement of interim cover over the tailings. Additional cells are excavated, and the overburden is used to reclaim previous cells. In this way, there is an ongoing reclamation process.

When in full operation, the Mill employs approximately 150 people, which is reduced to approximately 110 people when the vanadium circuit is not being operated.

#### Alternate Feed Materials

The Mill License (defined below) also gives the Company the right to process other uranium-bearing materials known as “*alternate feed materials”* pursuant to an Alternate Feed Guidance published by the NRC. Alternate feed materials are uranium-bearing materials, usually classified as waste products by the generators of the materials, which can be recycled by the Mill for the recovery of U3O8. The Mill License does not permit the processing of uranium-bearing materials that have undergone enrichment. Requiring a routine amendment to the Mill License for each different alternate feed material, the Company can process these uranium-bearing materials and recover uranium, in some cases, at a fraction of the cost of processing conventionally mined material. In other cases, the generators of the alternate feed materials are willing to pay a recycling fee to the Company to process these materials to recover uranium and then dispose of the remaining by-product in the Mill’s licensed tailings cells, rather than directly disposing of the materials at a disposal site. By working with the Company and taking the recycling approach, the suppliers of alternate feed materials can significantly reduce their remediation costs, as there are only a limited number of disposal sites for such materials in the United States. Alternate feed materials are particularly attractive to Energy Fuels because they carry no associated mining costs.

Throughout its history, the Mill has received 17 license amendments, authorizing it to process 20 different alternate feed materials. Of these amendments, eleven have involved the processing of feeds provided by nuclear fuel cycle facilities and private industry, and one has involved the processing of material from the DOE. These twelve feed materials have been relatively high in uranium content and relatively low in volume. The remaining five amendments have allowed the Mill to process uranium-bearing soils from former defense sites, known as FUSRAP sites, which were being remediated by the U.S. Army Corps of Engineers. These materials are typically relatively low in uranium content but relatively high in volume.

The Mill has a separate circuit for processing certain types of alternate feed materials, which was built in 2009. This circuit enables the Mill to process both conventionally mined material and alternate feed materials simultaneously.

#### Rare Earth Elements

In 2020, the Company began utilizing the Mill to process REEs from a monazite feed source. Monazite is typically produced as part of heavy-mineral sand mining operations and contains elevated quantities of the rare earth suite of elements as well as uranium and thorium. The Mill is uniquely suited to process monazite and extract both the REEs as well as the uranium and safely dispose of the thorium. The Mill processed approximately four metric tons of monazite in 2020 and produced an on-spec rare earth carbonate, which can be sold to a rare earth separations facility.

#### Accessibility, Local Resources, Physiography and Infrastructure

The Mill is located in central San Juan County, Utah, approximately six miles (9.5 km) south of the city of Blanding. It can be reached by taking a private road for approximately 0.5 miles west of U.S. Highway 191.

The climate of southeastern Utah is classified as dry to arid continental. Although varying somewhat with elevation and terrain, the climate in the vicinity of the Mill can be considered as semi-arid with normal annual precipitation of about 13.4 inches. The weather in the Blanding area is typified by warm summers and cold winters. The mean annual temperature in Blanding is about 50° (F). Winds are usually light to moderate in the area during all seasons, although occasional stronger winds may occur in the late winter and spring.

The Mill site is located on a gently sloping mesa that, from the air, appears similar to a peninsula, as it is surrounded by steep canyons and washes and is connected to the Abajo Mountains to the north by a narrow neck of land. On the mesa, the topography is relatively flat, sloping at less than one (1) percent to the south and nearly horizontal from east to west.

The natural vegetation presently occurring within a 25-mile (40-km) radius of the Mill site is very similar to that of the region, characterized by pinyon-juniper woodland integrating with big sagebrush (Artemisia tridentata) communities.

Off-site infrastructure includes paved highway access from U.S. Highway 191, and rights-of-way for commercial power and a water supply pipeline from Recapture Reservoir, which brings up to 1,000 acre-feet of water per year to the Mill site. The Mill also has four deep (2,000+ foot) water supply wells, which are available to supply process water during normal operations.

#### Ownership

The White Mesa Mill is located on 4,816 acres of private land owned in fee by Energy Fuels. This land is located in Township 37S and 38S Range 22E Salt Lake Principal Meridian. Energy Fuels also holds 253 acres of mill site claims and a 320-acre Utah state lease. No facilities are planned on the mill site claims or leased land, which are used as a buffer to the operations.

All operations authorized by the Mill’s License are conducted within the confines of the existing site boundary. The milling facility currently occupies approximately 50 acres and the current tailings disposal cells encompass another 250 acres.

#### Permitting and Licensing

The White Mesa Mill holds a Radioactive Materials License through the State of Utah (the “**Mill License”**). Uranium milling in the U.S. is primarily regulated by the NRC pursuant to the Atomic Energy Act of 1954, as amended. The NRC’s primary function is to ensure the protection of employees, the public and the environment from radioactive materials, and it also regulates most aspects of the uranium recovery process. The NRC regulations pertaining to uranium recovery facilities are codified in Title 10 of the Code of Federal Regulations. These regulations also apply to our ISR facilities in Wyoming and Texas.

On August 16, 2004, the State of Utah became an Agreement State for the regulation of uranium mills. This means that the primary regulator for the White Mesa Mill is the UDEQ rather than the NRC. At that time, the Source Material License, which was previously issued and regulated by the NRC, was transferred to the State and became a Radioactive Materials License. The State of Utah incorporates, through its own regulations or by reference, all aspects of Title 10 pertaining to uranium recovery facilities. The Mill License was due for renewal on March 31, 2007. Energy Fuels’ predecessor timely submitted its application for renewal of the license on February 28, 2007. The renewed license was issued by UDEQ on January 19, 2018 then reissued on February 16, 2018 for a period of ten years, after which another application for renewal will need to be submitted. During the review period for each application for renewal, the Mill can continue to operate under its then existing license until such time as the renewed license is issued. The Mill’s license was initially issued in 1980 and was also renewed in 1987 and 1997.

When the State of Utah became an Agreement State, it required that a GWDP be put in place for the White Mesa Mill. The GWDP is required for all similar facilities in the State of Utah, and effects the State groundwater regulations to the Mill site. The State of Utah requires that every operating uranium mill have a GWDP, regardless of whether the facility discharges to groundwater. The GWDP for the Mill was finalized and implemented in March 2005. The GWDP required that the Mill add over 40 additional monitoring parameters and 15 additional monitoring wells at the site. The GWDP came up for renewal in 2010, at which time an application for renewal was timely submitted. The renewed GWDP was issued by UDEQ on January 19, 2018 for a period of five years, after which another application for renewal will need to be submitted. During the review period for each application for renewal, the Mill can continue to operate under its then existing GWDP until such time as the renewed GWDP is issued. The White Mesa Mill also maintains a permit for air emissions with the UDEQ, Division of Air Quality.

The White Mesa Mill is subject to decommissioning liabilities. Energy Fuels, as part of the Mill License, is required to annually review its estimate for the decommissioning of the White Mesa Mill site and submit it to UDEQ for approval. The estimate of closure costs for the Mill is $20.5 million as of December 31, 2020, and financial assurances are in place for the total amount. However, there can be no assurance that the ultimate cost of such reclamation obligations will not exceed the estimated liability contained in the Company’s financial statements.

#### History

The Mill was originally constructed and owned by Energy Fuels Nuclear, Inc. (“**EFN”**) and its affiliates (no relation to the Company). It was licensed by the NRC and commenced operations in June 1980. In 1984, EFN transferred a 70% interest in the Mill to UMETCO Minerals Corp., a subsidiary of Union Carbide Corporation (“**UMETCO”**). UMETCO became the operator of the Mill in 1984 and continued to be the operator until 1994, at which time UMETCO transferred its interest in the Mill back to EFN and its affiliates. The Mill was acquired by Denison Mines Corp. (“**Denison”**), then named International Uranium Corporation (“**IUC”**) and its affiliates in 1997 and was operated by Denison until it was acquired by the Company in June 2012. From the original commissioning in 1980 through December 31, 2020, the Mill has recovered a total of approximately 40 million pounds of U3O8 and 46 million pounds of vanadium.

In late 2006, Denison began a program to refurbish the Mill. The refurbishment program included the purchase of mobile equipment, restoration of the vanadium roasting, fusion and packaging circuits, replacement of major pumps and component drives, modernization of the Mill’s instrumentation and process control systems, and completion of relining tailings Cell 4A. The total cost of the refurbishment program was approximately $31.0 million and was completed in 2008.

The White Mesa Mill has historically operated on a campaign basis. In 2008, the Mill began processing uranium/vanadium conventional mined material, extracting uranium concentrate in the form of U3O8, and vanadium in the form of V2O5. Mineral processing continued through the end of March 2009, at which time maintenance activities were performed at the Mill. Mineral processing recommenced near the end of April 2009 but was discontinued due to a decline in uranium prices at the time. The Mill began mineral processing again in March 2010 and continued through June 2011. Conventional processing recommenced in November 2011 and continued until early March 2012, at which time it ceased for routine maintenance. Conventional mineral processing recommenced at the Mill in August 2012 and continued until early June 2013. Mineral processing began again in May 2014 and continued through August 2014. The alternate feed circuit processed materials from January through December 2014 and continued processing alternate feed materials through December 2015. In 2016, the Company continued processing several alternate feed materials and processed 45,057 tons of mineralized material from its Pinenut mine. In 2017 and 2018, the Mill continued processing alternate feed materials as well as the recovery of uranium from pond solutions at the site. In 2020, Mill activities focused solely on processing alternate feed materials and uranium and vanadium recovery from pond solutions at the site.

Energy Fuels acquired the Mill from Denison Mines Corp. on June 29, 2012. All mineral processing after that date has been for the account of Energy Fuels.

*Alternate Feed Materials(2)*

| Project or Source Tons (000) | 2020 NA(2) | 2019 NA(2) | 2018 NA(2) | 2017 NA(2) | 2016 NA(2) |
| --- | --- | --- | --- | --- | ---: |
| Ave. % U3O8 | NA(2) | NA(2) | NA(2) | 18.86% | 27.98% |
| Recovered Pounds U3O8 (000) | 144(3) | --- | 561(3) | 1,004(3) | 172(3) |
| Tailing Solution Recycle & In-Circuit Material(4) |  |  |  |  |  |
| Recovered Pounds U3O8 (000) | 47 | --- | 216 | 308 | 77 |
| Recovered Pounds V2O5 (000) | 67 | 1,807 | --- | --- | --- |
| Conventional Feed Materials |  |  |  |  |  |
| Tons (000) | --- | --- | --- | --- | 45 |
| Contained Grade % U3O8 | --- | --- | --- | --- | 0.5% |
| Recovered Pounds U3O8 (000) | --- | --- | --- | --- | 431 |
| Nichols Ranch(5) |  |  |  |  |  |
| Recovered Pounds U3O8 (000) | 6 | 70 | 140 | 259 | 335 |
| Alta Mesa |  |  |  |  |  |
| Recovered Pounds U3O8 (000) | --- | --- | --- | --- | --- |
| **Total Pounds of U3O8 Recovered (000)** | **197** | **70** | **917** | **1,571** | **1,015** |
| **Total Pounds of V2O5 Recovered (000)** | **67** | **1,807** | **---** | **---** | **---** |

### Notes:

(1) Mineralized material is shown as being processed and pounds recovered during the year in which the materials were processed at the White Mesa Mill or at the Nichols Ranch Plant, which is not necessarily the year in which the materials were extracted from the project facilities.

(2) All alternate feed materials were processed at the White Mesa Mill. A number of different alternate feed materials were processed during the period 2016 – 2020. The table shows the average uranium grades and the total pounds recovered from all alternate feed materials processed at the Mill during each of the years in that period. Because of the variability in uranium grades, pounds recovered is considered to be the relevant metric and tons fed is not considered to be relevant.

(3) 144,000 pounds recovered in 2020 include nil pounds recovered for the accounts of third parties; the 561,000 pounds recovered in 2018 from alternate feed materials include 424,000 pounds recovered for the accounts of third parties; the 1,004,000 pounds recovered in 2017 include 952,000 pounds recovered for the accounts of third parties; and the 172,000 pounds recovered in 2016 include nil pounds recovered for the accounts of third parties.

(4) Pounds contained in tailings solutions containing previously unrecovered uranium and vanadium, together with in-circuit mineralized material from previous conventional mine material processing, were recovered at the White Mesa Mill, though tons and grade are not available because they cannot be tied to any specific source.

(5) Uranium recovery commenced at the Nichols Ranch Project on April 17, 2014. Because the Nichols Ranch Project uses ISR instead of conventional extraction methods, grade and tons of mineralized material are inapplicable to the Nichols Ranch Project.

#### Present Condition of the Property

#### Planned Operations and Maintenance

The White Mesa Mill operated the alternate feed circuit throughout 2014 and 2015 and stopped processing materials in July of 2016. The White Mesa Mill processed conventional mineralized material in the second and third quarter of 2016 and processed alternate feed materials during the remainder of the year. In 2017 and 2018, the Mill processed only alternate feed materials and recovered uranium from pond solutions at the site. The White Mesa Mill recovered no pounds of U3O8 during 2019, and operations focused solely on vanadium recovery from dissolved vanadium in the Mill’s tailings management system not recovered from previous processing activities (“**Pond Return”**). The White Mesa Mill recovered approximately 67,000 pounds of V2O5 in 2020 from Pond Return. Of these 67,000 pounds of V2O5, all were for the account of the Company. During 2020, the Company recovered approximately 190,000 pounds of U3O8 from the processing of alternate feed materials and Pond Return. The Company also recovered approximately 68,000 pounds of V2O5 from Pond Returns. In 2020, the Company also began processing an REE feed at a pilot scale. The Company produced approximately 4 metric tons of rare earth carbonate. The Mill operations registered zero lost time accidents in 2017, 2018, 2019 and 2020.

#### Environmental Matters

Prior to Energy Fuels’ acquisition of the Mill from Denison, chloroform in the shallow aquifer at the White Mesa Mill site was discovered. The chloroform appears to have resulted from the operation of a temporary laboratory facility that was located at the site prior to and during the construction of the Mill, and from septic drain fields that were used for laboratory and sanitary wastes prior to construction of the Mill’s tailings cells. In April 2003, Denison commenced an interim remedial program of pumping the chloroform affected water from the groundwater to the Mill’s tailings system. This action enabled Energy Fuels to begin cleanup of the affected areas and to take a further step towards resolution of this outstanding issue. Pumping from the wells continued through 2015. On September 14, 2015, the State of Utah approved a long-term Corrective Action Plan (“**CAP”**) for cleanup of the chloroform, which involves continued pumping of the affected water to the Mill’s tailings system. While the investigations to date indicate that this chloroform appears to be contained in a manageable area, the scope and costs of final remediation have not yet been determined and could be significant.

Prior to Energy Fuels’ acquisition of the Mill from Denison, elevated concentrations of nitrate and chloride were observed in some of the monitoring wells at the White Mesa Mill site in 2008, a number of which are upgradient of the Mill’s tailings cells. Pursuant to a Stipulated Consent Agreement with UDEQ, Denison retained INTERA, Inc., an independent professional engineering firm, to investigate these elevated concentrations and to prepare a Contamination Investigation Report for submittal to UDEQ. The investigation was completed in 2009, and the Contamination Investigation Report was submitted to UDEQ in January 2010. INTERA concluded in the Report that: (1) the nitrate and chloride are co-extensive and appear to originally come from the same source; and (2) the source is upgradient of the Mill property and is not the result of Mill activities. UDEQ reviewed the Report and concluded that further investigations were required before it could determine the source of the contamination and the responsibility for cleanup. Such investigations were performed in 2010 and 2011 but were considered inconclusive by UDEQ. As a result, after the investigations, it was determined that there are site conditions that make it difficult to ascertain the source(s) of contamination at the site, and that it was not possible at that time to determine the source(s), causes(s), attribution, magnitude(s) of contribution, and proportion(s) of the local nitrate and chloride in groundwater. For those reasons, UDEQ decided that it could not eliminate Mill activities as a potential cause, either in full or in part, of the contamination. The Company and UDEQ have therefore agreed that resources are better spent in developing a CAP, rather than continuing with further investigations as to the source(s) and attribution of the groundwater contamination. Pursuant to a revised Stipulated Consent Agreement, Denison submitted a draft CAP for remediation of the contamination to UDEQ in November 2011. The CAP proposed a program of pumping the nitrate contaminated groundwater to the Mill’s tailings cells, similar to the chloroform remedial program. UDEQ approved the CAP on December 12, 2012. In accordance with the CAP, in 2013 the Company commenced pumping nitrate/chloride contaminated water from four monitoring wells for use in Mill processing or discharge into the Mill’s process or tailings cells. In December 2017 the Mill filed its first CACME, required under the CAP every five years. By letter dated June 22, 2018, the DWMRC requested the implementation of Phase III actions specified in the CAP. Phase III actions include modeling, and study of plume dynamics and assessment of future actions if any. The Phase III report was submitted to DWMRC in December 2018 and is currently under review by DWMRC. Although the contamination appears to be contained in a manageable area, the scope and costs of final remediation have not yet been determined and could be significant.

During 2011, 2012, and 2013, the White Mesa Mill reported consecutive exceedances of groundwater compliance limits (“**GWCLs”**) under the Mill’s GWDP for several constituents in several wells, and there are decreasing trends in pH in a number of wells across the site that have caused the pH in a number of compliance monitoring wells to have dropped below their GWCLs. These exceedances and pH trends include wells that are up-gradient of the Mill facilities, far down-gradient of the Mill site and at the site itself. These consecutive exceedances of GWCLs have resulted in violations of the GWDP. Source Assessment Reports were submitted in 2012 and 2013 addressing each exceedance and the decreasing trends in pH at the site. UDEQ has accepted the Source Assessment Reports and has concluded that such exceedances and decreasing trends in pH are due to natural background influences at the site. The renewed GWDP, issued on January 19, 2018, has revised GWCLs which are intended to account for these background influences and put those constituents, including pH at the site, back into compliance.

#### Total Cost of Project

The White Mesa Mill was acquired by the Company in June 2012, through the acquisition of the US Mining Division from Denison. The cost of the White Mesa Mill has been fully impaired, and as of December 31, 2020, the total cost attributable to the White Mesa Mill and its associated equipment on the financial statements of the Company was nil.

During 2021, the Company expects to recovery approximately 45,000 pounds of U3O8 at the Mill. These pounds will be a result of processing rare earth bearing uranium ore as well as alternate feed materials. A rare earth carbonate product is also planned to be produced during 2021. Total rare earth carbonate production is expected to be in the range of 2,000-3,000 tons. Evaluation and piloting of rare earth separation processes is also expected. Low grade uranium ore will continue to be received at the Mill from a clean-up mine site in New Mexico. Approximately 20,000 tons of this material is expected during 2021. No vanadium production is planned during 2021.

### The Pinyon Plain Project (formerly the Canyon Project)

Except as noted, the following technical and scientific description of the Pinyon Plain Project is based on a technical report titled “*Technical Report on the Canyon Project, Coconino County, Arizona, U.S.A.,”* dated October 6, 2017 prepared by Mark B. Mathisen, C.P.G., Valerie Wilson, M.Sc., P.Geo, and Jeffrey L. Woods, QP MMSA, SME of Roscoe Postle Associates (“**RPA”**) in accordance with NI 43-101 (the “**Canyon Technical Report”**). Note that the name of the Canyon Mine was changed to the Pinyon Plain Mine in November 2020. Each of the authors of the Canyon Technical Report is a “qualified person” and is “independent” of the Company within the meaning of NI 43-101. The Canyon Technical Report is available on SEDAR at www.sedar.com. The Pinyon Plain Project does not have known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite currently ongoing development activities.

The Pinyon Plain Project is a fully constructed and partially developed underground uranium project with a head frame, a hoist, a compressor and a completed shaft. The site is located south of Grand Canyon National Park, in Sections 19 and 20, T29N, R03E, GSRM, Coconino County, Arizona, 153 miles north of Phoenix, 86 miles northwest of Flagstaff and seven miles south of Tusayan, Arizona in the Kaibab National Forest. The Pinyon Plain Project was acquired by Energy Fuels in its June 2012 acquisition of Denison’s U.S. Mining Division.

The Pinyon Plain Project is located in the Arizona Strip mining district. The Arizona Strip is an area largely bounded on the north by the Arizona/Utah state line; on the east by the Colorado River and Marble Canyon; on the west by the Grand Wash Cliffs; and on the south by a midpoint between the city of Flagstaff and the Grand Canyon. The area encompasses approximately 13,000 square miles. Uranium-bearing material from the Arizona Strip mines is hauled by truck to the White Mesa Mill where it is processed. The

Company’s Arizona 1, Pinenut (now in reclamation) and EZ Projects are located north of the Grand Canyon. The Pinyon Plain Project and Wate Project are located south of the Grand Canyon. The Pinyon Plain Project is 325 road miles from the White Mesa Mill.

Access to the Pinyon Plain Project site is via State Highway 64 to within five miles of the mine site, then over unsurfaced public Forest Service roads. The Atchison, Topeka and Santa Fe railway line passes east-west 50 miles south of the site at Williams, and a spur of the railway, which passes 10 miles west of the Pinyon Plain Project site, services the Grand Canyon National Park. Airports at Flagstaff, Phoenix, and Tusayan provide air access to the area.

Climate in northern Arizona is semi-arid, with cold winters and hot summers. January temperatures range from approximately 7° F to 57° F and July temperatures range from approximately 52° F to 97° F. Annual precipitation, in the form of rain and occasional snow, is approximately 12 inches. Vegetation on the plateaus is primarily open piñon juniper woodland and shrubs. Mining operations can be conducted on a year-round basis.

The community of Tusayan, seven miles northwest of the Pinyon Plain Project, provides much of the housing and other facilities for people who work within Grand Canyon National Park. The seasonal population typically ranges from approximately 500 to 1,000 people. A clinic run by a Phoenix hospital is operated at Grand Canyon Village inside the national park, as well as a K-12 grade school with a capacity of 250 students. Williams, a rural community 44 miles south of the site at Interstate 40, has a population of approximately 2,500 people. Williams relies heavily on tourism to maintain its economy, but many people are also involved in agriculture and forestry. The town offers an elementary, middle and high school, an emergency medical center, shopping and a variety of community services. Although housing is available, a lack of adequate water supplies limits housing construction.

Flagstaff, 56 miles southeast of the Pinyon Plain Project, is a full-service city with a population of 70,000 and is the regional trade center for northern Arizona.

Arizona, and particularly Coconino County, is among the fastest growing areas in the United States, due to the climate, landscape diversity, and economic and recreational opportunities. Resources and services are often stretched to meet the needs of the growing population.

Personnel for future mining operations are expected to be sourced from the nearby towns of Williams and Flagstaff, as well as other underground mining districts in the western United States.

In addition to the mine shaft, existing mine infrastructure includes surface maintenance shops, employee offices and change rooms, a water well, an evaporation pond, explosives magazines, a water tank, fuel tanks, and rock stockpile pads. Electrical power is available through an existing power line that ends at the site.

Northern Arizona is part of the Colorado Plateau, a region of the western United States characterized by semi-arid, high-altitude, gently sloping plateaus dissected by steep walled canyons, volcanic mountain peaks, and extensive erosional escarpments. The Pinyon Plain Project is located on the Coconino Plateau within the Colorado Plateau, at an elevation of approximately 6,500 feet.

#### Ownership

The Pinyon Plain Project is held by Energy Fuels on nine unpatented claims (Canyon 64-66, 74-76, and 84-86) located on land managed by the USFS. A uranium royalty on the Pinyon Plain Project was retained at one time by the successors to Gulf Oil Company; however, the current status of the royalty is under investigation by the Company. If valid, the royalty rate is a 3.5% weighted average price tied to the Atomic Energy Commission Circular 5.

Holding costs for the Pinyon Plain Project are minimal and consist entirely of annual fees for unpatented mining claims ($165 per claim per year) and county filing fees (approximately $10 per claim per year). Unpatented mining claims expire annually but are subject to indefinite annual renewal by filing the appropriate documents and paying the fees described above. In addition, holders of unpatented mining claims on USFS lands are generally granted surface access rights by the USFS to conduct mineral exploration and mining activities.

#### Permitting and Licensing

The Pinyon Plain Project is located on public lands managed by the USFS and has an approved Plan of Operations (“**POO”**) with the USFS. In 2020, the Company submitted a clean closure plan to the USFS to provide a description of how the Company will reclaim the mine to clean closure standards after the cessation of mining operations, as contemplated in the USFS-approved POO, Record of Decision and modifications to the reclamation plan contained in Appendix B of the Environmental Impact Statement. The clean closure plan included an update to the reclamation cost estimate, resulting in an increase from $461,245 to $1,407,235. In September 2009, the groundwater General Aquifer Protection Permit (“**APP”**) was obtained for the water storage pond from the Arizona Department of Environmental Quality (“**ADEQ”**). This permit was up for renewal in 2019, and an application for renewal was timely submitted by the Company in 2019. General APPs were also obtained from ADEQ for the development rock stockpile and intermediate ore stockpile in December 2011 and renewed in 2018. At the request of the ADEQ, the three General APPs are currently being consolidated into an Individual APP. An application for coverage under the Individual APP was submitted to ADEQ in November 2020. An Air Quality Permit was issued by the ADEQ in March 2011, renewed in 2016 and amended in 2017. The Company received EPA’s approval under the Clean Air Act National Emissions Standard for Hazardous Air Pollutants for the Pinyon Plain Project in September of 2015.

Development of uranium-bearing breccia pipes of the Arizona Strip requires minimal surface disturbance, typically less than 20 acres total. Thus, the overall environmental impact is minimal. Nevertheless, the areas in the general vicinity of the Grand Canyon can be environmentally sensitive in many ways and so the permitting, development, and operation of a uranium extraction facility in this area remains a contentious issue. In 2009, as described below, over one million acres of federal land were withdrawn from mineral location, subject to valid existing rights. Reclamation at the Pinyon Plain Project is bonded at its total expected cost.

#### Geological Setting

Parts of two distinct physiographic provinces are found within Arizona: the Basin and Range province in the southern and western edge of the state, and the Colorado Plateau province in most of northern and central Arizona. The Arizona Strip lies within the Colorado Plateau province.

Surface exposures within the Arizona Strip reveal sedimentary and volcanic rocks ranging in age from upper Paleozoic to Quaternary; the area is largely underlain by Mississippian through Triassic sedimentary rocks. However, exposed within the Grand Canyon are older rocks reaching Precambrian in age.

Paleozoic sedimentary rocks of northern Arizona are host to thousands of breccia pipes. These deposits are known to extend from the Mississippian Redwall Limestone to the Triassic Chinle Formation, which makes up approximately 4,000 feet of section. However, because of erosion and other factors, no single deposit has been observed cutting through the entire section. No deposit is known to occur above the Chinle Formation or below the Redwall Limestone.

Breccia pipes within the Arizona Strip are vertical or near vertical, circular to elliptical bodies of broken rock. Broken rock is comprised of slabs and rotated angular blocks and fragments of surrounding and stratigraphically higher formations. Surrounding the blocks and slabs making up the breccia is a matrix of fine material comprised of surrounding and overlying rock from various formations. The matrix has largely been cemented by silicification and calcification for the most part.

Breccia pipes are typically comprised of three interrelated features: a basinal or structurally shallow depression at surface (designated by some as a collapse cone); a breccia pipe that underlies the structural depression; and annular fracture rings, which occur outside of but at the margin of the pipes. Annular fracture rings are commonly, but not always, mineralized. The structural depression may be up to 0.5 miles or more in diameter, whereas the breccia pipe diameters range up to about 600 feet; the normal range is 200 feet to 300 feet.

Mineralized breccia pipes found to date appear to occur in clusters or trends. Spacing between breccia pipes ranges from hundreds of feet within a cluster to several miles within a trend. Pipe location may have been controlled by deep seated faults, but karstification of the Redwall Limestone in Mississippian and Permian times is considered to have initiated formation of the numerous and widespread breccia pipes in the region.

At the Pinyon Plain deposit, the surface expression of the pipe is a broad shallow depression in the Permian Kaibab Formation. The pipe is essentially vertical with an average diameter of less than 200 feet, but it is considerably narrower through the Coconino and Hermit horizons (80 feet). The cross-sectional area is probably between 20,000 and 25,000 square feet. The pipe extends for at least 2,300 feet from the Toroweap limestone to the upper Redwall horizons. The ultimate depth of the deposit is unknown.

Mineralization extends over approximately 1,500 vertical feet, with higher-grade mineralization found mainly in the Coconino, Hermit, and Esplanade horizons and at the margins of the pipe in fracture zones. Sulfide zones are found scattered throughout the pipe but are especially concentrated (sulfide cap) near the Toroweap Coconino contact where the cap averages 20 feet thick and consists of pyrite and bravoite, an iron-nickel sulfide. The mineralized assemblage consists of uranium-pyrite-hematite with massive copper sulfide mineralization common in and near the higher-grade zone. The strongest mineralization appears to occur in the lower Hermit-upper Esplanade horizons in an annular fracture zone.

#### History

Uranium exploration and mining of breccia pipe uranium deposits started in 1951 when a geologist employed by the U.S. Geological Survey noted uranium ore on the dump of an old copper prospect on the South Rim of the Grand Canyon of Northern Arizona. The prospect was inside the Grand Canyon National Park, but on fee land that predated the park. A mining firm acquired the prospect and mined this significant high-grade uranium deposit, called the Orphan Mine. By the time mining ended in the early 1960s, 4.26 million pounds of U3O8 and some minor amounts of copper and silver had been produced.

After the discovery of the first deposit in the 1950s, an extensive search for other deposits was made by the government and industry, but only a few low-grade prospects were found. Exploration started again in the early 1970s. In the mid-1970s, Western Nuclear Inc. (“**Western Nuclear”**) acquired the Hack Canyon prospect located approximately 25 miles north of the Grand Canyon and found high grade uranium mineralization offsetting an old shallow copper/uranium site. Soon thereafter, a second deposit was found approximately one mile away. EFN acquired the Hack Canyon property from Western Nuclear in December 1980. Construction promptly commenced, and the Hack Canyon mine was in production by the end of 1981.

The Pinyon Plain deposit is located on mining claims that EFN acquired from Gulf Mineral Resources Company (“**Gulf”**) in 1982. Gulf drilled eight exploration holes at the site from 1978 through May 1982 but found only low-grade uranium in this pipe. Additional drilling completed by EFN in 1983 identified a major deposit. EFN drilled a further 30 holes from May 1983 through April 1985 to delineate the uranium mineralization and to determine placement of the shaft and water supply well. Additional drilling of six holes was completed in 1994, but construction at the site was discontinued as a result of low uranium prices at that time.

EFN identified and investigated more than 4,000 circular features in northern Arizona. Approximately 110 of the most prospective features were explored by deep drilling, and approximately 50% of those were shown to contain some uranium mineralization. Ultimately, nine deposits were deemed worthy of development. Total mine production resulting from the EFN breccia pipes in the years 1980 through 1991 was approximately 19.1million pounds U3O8 at an average grade of just over 0.60% U3O8.

Most of the EFN assets were acquired by Denison (then named International Uranium Corp., or IUC) in 1997, then by the Company in June 2012 upon acquisition of the US Mining Division. Since then, Energy Fuels has maintained ownership of the Pinyon Plain Project.

Denison did not conduct any surface drilling or other form of surface exploration on the project. The Company only conducted underground drilling based on surface exploration from previous owners. Historically, exploration for breccia pipes in northern Arizona typically begins with a search for surface expressions of circular features. The search actually conducted was aided by geologic mapping, Landsat aerial photography, thermal infrared imagery, geochemical testing, and certain geophysical methods such as resistivity, Very Low Frequency (“**VLF”**), and time domain electromagnetics. Other techniques tested include geobotany, microbiology, and biogeochemistry. All of these methods were utilized to identify surface expressions of breccia pipes. The key element of the process was to zero in on the throat of the pipe as a locus for drilling from the surface since the throat is usually associated directly with the center of the collapse.

#### Mineralization

Mineralization extends vertically both inside and outside the pipe over approximately 1,500 vertical feet, but high-grade mineralization has been found mainly in the collapsed portions of the Coconino, Hermit, and Esplanade horizons and at the margins of the pipe in fracture zones. Sulfide zones are found scattered throughout the pipe but are especially concentrated (within a sulfide cap) near the Toroweap-Coconino contact, where the cap averages 20 feet thick and consists of pyrite and bravoite, and iron-nickel sulfide. The mineralization assemblage consists of uranium-pyrite-hematite with massive copper sulfide mineralization common in and near high-grade zones. The strongest mineralization appears to occur in the lower Hermit-upper Esplanade horizons in an annular fracture zone.

The two metals of interest within the Pinyon Plain breccia pipe are uranium and copper. Since the rocks making up the breccia within the pipe are all sedimentary rocks, mineralization typically occurs within the matrix material (primarily sand) surrounding the larger clasts.

Uranium mineralization at Pinyon Plain is concentrated in six stratigraphic levels or zones (Cap, Upper, Main, Main-Lower, Juniper I, and Juniper II) within a collapse structure ranging from 80 feet to 230 feet wide with a vertical extension from a depth of 650 feet to over 2,100 feet, resulting in approximately 1,450 feet of mineralization. Intercepts range widely up to several tens of feet with grades in excess of 1.0% U3O8.

Consistent with other breccia pipe deposits, uranium at the Pinyon Plain Project occurs largely as blebs, streaks, small veins, and fine disseminations of uraninite/pitchblende (UO2). Mineralization is mainly confined to matrix material, but may extend into clasts and larger breccia fragments, particularly where these fragments are composed of Coconino sandstone. Uranium mineralization occurs primarily as uraninite and various uranium phase minerals with lesser amounts of brannerite and uranospinite.

Copper mineralization occurs in concentrations within the Main and Main-Lower zones that have a reasonable prospect for eventual economic extraction. It is also present in the Juniper zones, but at much lower concentrations than the Main Zone.

Mineralization can be disseminated throughout the matrix material (commonly replacing calcite cement) with higher-grade mineralization typically occurring as vug fills, blebs, or streaks within the matrix and sometimes zoning the breccia clasts. The highest-grade copper mineralization either completely replaces the matrix cement or replaces the matrix material all together. Copper mineralization occurs primarily as tennantite, chalcocite and bornite with lesser amounts of covellite. Pyrite and sphalerite are also found throughout the pipe. Silver is commonly associated with the copper mineralization in the main zone. Assay values of silver in excess of one ounce per ton are common where copper grades are high. Arsenic is present where tennantite mineralization occurs. Additionally, lower quantities of Zn, Pb, Mo, Co, Ni, and V are present and scattered throughout the pipe.

#### Mineral Resource Estimate

Mineral Resource estimates were prepared for the Pinyon Plain deposit using both historical surface drill hole gamma and assay data and gamma and assay data collected during underground drilling in 2016 and 2017. A model of the breccia pipe host was constructed based on drill logs and constrains the Mineral Resource. Mineralization wireframes for U3O8 were based on assays and gamma data at a nominal cut-off grade of 0.15%. Low and high-grade copper wireframes were based on nominal cutoff grades of

1% and 8% respectively. Values for U3O8 and copper were interpolated into blocks using inverse distance squared or ordinary kriging. Resources are presented a 0.36% U3O8 Eq equivalent cut-off grade for zones that contain both uranium and copper mineralization (Main and Main-Lower) and at a 0.29% U3O8 Eq cut-off grade for zones that contain only uranium mineralization (Cap, Upper, Juniper I, and Juniper II).

There are no Mineral Reserves estimated at the Pinyon Plain deposit at this time. Additional underground drilling conducted by the Company in 2016 and 2017 allowed for the classification of measured and indicated mineral resources, and the inclusion of a copper Mineral Resource. In October 2017, RPA estimated the Mineral Resources for both uranium and copper, shown in the following tables.

#### Pinyon Plain Project Mineral Resources – Uranium(1)(2)(3)(4)(5)(6)(7)

| Classification Zone Cut-off Grade % U3O8 Eq | Tons (000) | Grade % U3O8 | Pounds U3O8 (000) |
| --- | ---: | ---: | ---: |
| Pinyon Plain Measured Resources (M) Main 0.36 | 6 | 0.43% | 56 |
| Pinyon Plain Indicated Resources (I) Main 0.36 | 94 | 0.89% | 1,669 |
| Juniper I 0.29 38 | 0.94% | 709 |  |
| **Total (M & I)** | **139** | **0.88%** | **2,434** |
| Pinyon Plain Inferred Resources Cap 0.29 | --- | --- | --- |
| Upper 0.29 9 | 0.43% | 78 |  |
| Main-Lower 0.36 5 | 0.20% | 20 |  |
| Juniper I 0.29 2 | 0.57% | 25 |  |
| Juniper II 0.26 1 | 0.35% | 9 |  |
| **Total Inferred Resources** | **18** | **0.38%** | **134** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

(2) For the Main and Main-Lower zones, a 0.36% uranium equivalent cut-off grade (% U3O8 Eq) was applied to account for both the copper and uranium mineralization. In all other zones, only uranium was reported using a 0.29% U3O8 cut-off grade (the %U3O8 Eq grade term is not the same as the eU3O8 % grade term with indicates probe rather than assay data listed elsewhere in this report. For details see the Canyon Technical Report).

(3) Mineral Resources are estimated using a long-term uranium price of $60 per pound and a copper price of $3.50 per pound.

(4) A copper to U3O8 conversion factor of 18.19 was used for converting copper grades to equivalent U3O8 grades (U3O8 Eq) for cut-off grade evaluation and reporting for the Main and Main-Lower zones.

(5) Process recoveries used were 96% for U3O8 and 90% for Cu, based on preliminary metallurgical test work.

(6) Numbers may not add due to rounding.

(7) Tonnages of uranium and copper cannot be added as they overlap in the Main and Main-Lower zones.

#### Pinyon Plain Project Mineral Resources – Copper(1)(2)(3)(4)(5)(6)(7)

| Classification | Zone | Cut-off Grade % U3O8 Eq | Tons (000) | Grade % Cu | Pounds Cu (000) |
| --- | --- | ---: | ---: | ---: | ---: |
| Pinyon Plain Measured Resources (M) | Main | 0.36 | 6 | 9.29% | 1203 |
| Pinyon Plain Indicated Resources (I) | Main | 0.36 | 94 | 5.70% | 10,736 |
| **Total (M & I)** | **Main** | **0.36** | **101** | **5.93%** | **11,939** |
| **Pinyon Plain Inferred Resources** | **Main-Lower** | **0.36** | **5** | **5.90%** | **570** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources.”*

(2) Mineral Resources are estimated at a uranium equivalent (%U3O8 Eq) cut-off grade of 0.36% U3O8 Eq.

(3) Mineral Resources are estimated using a long-term uranium price of $60 per pound and a copper price of $3.50 per lb.

(4) A copper to U3O8 conversion factor of 18.19 was used for converting copper grades to equivalent U3O8 grades (U3O8 Eq) for cut-off grade evaluation and reporting.

(5) Process recoveries used were 96% for U3O8 and 90% for Cu, based on preliminary metallurgical test work.

(6) Numbers may not add due to rounding.

(7) Tonnages of uranium and copper cannot be added as they overlap in the Main and Main-Lower Zones.

Two cut-off grades were used for the resource estimate. For the uranium and copper bearing zones, a 0.36% uranium equivalent (%U3O8 Eq) cut-off grade was used. For the uranium-only zones, a 0.29% eU3O8 cut-off grade was used. The two cut-off grades account for separate process campaigns with different unit costs.

#### Present Condition of the Property and Work Completed to Date

At the Pinyon Plain Project, all surface facilities are in place. During 2017, an underground drilling program was completed, shaft sinking continued, and a large water tank was installed. The shaft sinking was completed by mid-March 2018. The depth of the shaft is approximately 1,470 feet below ground surface. Shaft stations are developed at depths of 1,000 feet (elevation 5,506 feet above sea level), 1,220 feet (elevation 5,286) and 1,400 feet (elevation 5,106).

During 2018, bench scale and pilot plant scale metallurgical test work was carried out by Hazen Research (“**HAZEN”**) in Golden, Colorado. The copper is expected to be processed using roasting, followed by acid leach and solvent extraction. Acid leach followed by solvent extraction is the current process used for uranium recovery. Following solvent extraction, a saleable copper product is expected to be produced by electro-winning. To recover copper from the Pinyon Plain mineralized material, some modifications to White Mesa Mill process circuits are required. The copper modifications are expected to include using the existing vanadium solvent extraction circuit for copper extraction, the addition of a roaster to improve copper recovery, and the addition of an electro-winning circuit. Bench and pilot scale test work done by HAZEN in 2018 indicates that acid leaching after roasting pre-treatment is expected to result in satisfactory copper and uranium recoveries.

During 2019, a 1,000,000-gallon water tank was installed, in addition to the existing 400,000-gallon tank installed in 2017. These above-ground storage tanks are used for operational flexibility and extra water storage capacity during winter months. Three floating, downcasting, enhanced evaporators were installed in the Non-Stormwater Impoundment to aid in evaporation. The tanks and evaporators are part of Energy Fuels’ water balance management practices at the site.

During 2020, a fourth floating, down-casting, enhanced evaporator was installed at the site to increase the operational flexibility of the water balance management practices. Additionally, a water capture and pumping system was installed in the shaft to segregate unimpacted water and store it for beneficial use.

The Pinyon Plain Project was acquired by the Company in June 2012 through the acquisition of the U.S. Mining Division from Denison. The cost of the Pinyon Plain Project has been fully impaired and, as of December 31, 2020, the total cost attributable to the Pinyon Plain Project and its associated equipment on the financial statements of the Company was nil.

In 2021, the Company plans to install a portable water treatment plant at its Pinyon Plain Project. Additional work, outside of additional evaluation work and engineering is subject to general market conditions during 2021. The timing of the Company’s plans to extract and process mineralized material from the Pinyon Plain Project will be based on market conditions, available financing, and sales requirements.

### The Roca Honda Project

Except as noted concerning land tenure and permitting efforts, the following technical and scientific description of the Roca Honda Project is based on a technical report titled “*Technical Report on the Roca Honda Project, McKinley County, State of New Mexico, U.S.A.”* dated October 27, 2016, prepared by Robert Michaud, P.Eng., Stuart E. Collins, P.E., and Mark B. Mathisen, C.P.G., all of RPA and Harold Roberts, then Executive Vice President of the Company and now a Consultant, in accordance with NI 43-101 (the “**Roca Honda Technical Report”**). The purpose of the Roca Honda Technical Report was to update the Preliminary Economic Assessment (“**PEA”**) of the Project in light of changes in the Project ownership interest and the acquisition of additional mineral property. Each of the authors of the Roca Honda Technical Report is a “qualified person” and all but one is “independent” of the Company within the meaning of NI 43-101. Harold R. Roberts, P.E., was Executive Vice President, Conventional Operations of the Company at the time he co-authored the PEA; however, the independent authors of the Report have assumed overall responsibility for all items of the technical report, and the Report is therefore an independent technical report under NI 43-101. The Roca Honda Technical Report is available on SEDAR at www.sedar.com and on EDGAR at www.sec.gov. The Roca Honda Project does not have known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite currently ongoing permitting activities.

The Company acquired a majority of the Roca Honda Project on August 29, 2013 as a result of its acquisition of Strathmore. Certain adjacent properties (the “**Adjacent Properties”**) (which now form part of the Roca Honda Project) were later acquired by the Company from Uranium Resources, Inc. (“**URI”**) in June 2015.

The Roca Honda Project is an underground uranium project that is being permitted by the Company’s wholly-owned subsidiary, Strathmore Resources, U.S. Ltd. as operator of Roca Honda Resources, LLC (“**RHR”**). RHR was established on July 26, 2007, when Strathmore formed a limited liability company with Sumitomo Corporation (“**Sumitomo”**) and transferred the property to RHR. Strathmore purchased Sumitomo's 40% interest in RHR on May 27, 2016. The Roca Honda Project is located approximately three miles northwest of the community of San Mateo, New Mexico near the southern boundary of McKinley County and north of the Cibola County boundary, and approximately 22 miles by road northeast of Grants, New Mexico. The property is located in the east part of the Ambrosia Lake subdistrict of the Grants Mineral Belt in northwest New Mexico and comprises nearly all of Sections 5, 6, 8, 9, 10, and a narrow strip of Section 11, the New Mexico State Lease, consisting of Section 16, and the fee mineral interest in Section 17, all in Township 13 North – Range 8 West (T13N-R8W), New Mexico Principal Meridian. Mineralized material from the Roca Honda Project will be shipped by highway truck to the Company’s White Mesa Mill, where it will be processed for the recovery of uranium. The Roca Honda Project does not have known reserves and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature.

The Roca Honda property is located approximately 17 miles (22 miles by road) northeast of Grants, New Mexico. The southern part of the property, which is on Sections 16 and 17, can be reached by traveling north from Milan, New Mexico on State Highway 605 toward the town of San Mateo to mile marker 18 and then north on a private gravel road. Access rights from Highway 605 onto Section 16 have been subject to temporary agreements with the surface owner, Fernandez Company, the latest of which expired on December 31, 2015. When the Company acquired the mineral rights to Section 17 in the URI transaction, it acquired surface access rights to Section 17 and Section 16, which the Company believes provides all necessary access. The Company is in discussions with the surface owner to determine whether any further access rights may be required.

The north part of the project can be reached by traveling 23.5 miles from Milan, New Mexico on paved public Highway 605, and then west on USFS roads to the southeast corner of Section 10. There are numerous drill roads that provide access to different portions of Sections 9 and 10, many of which will require maintenance. Old drill roads were previously established across the property, and an electrical line transects the northern half of Section 16 in the project area. The line continues along the west side of the project area into Section 17, where it terminates, and on the east side of Section 16 through the northwest quarter of Section 15 and along the southern section boundary of Section 10. There is a concrete lined, 14-foot diameter, 1,478-foot-deep shaft, which was sunk by Kerr-McGee on Section 17 (the “**Existing Shaft”**). The Existing Shaft would need to be completed to a final depth of approximately 1,600 feet for use in future mine activities. No milling operations are expected to occur on the site.

The climate in the Roca Honda Project area may be classified as arid to semi-arid continental, characterized by cool, dry winters, and warm, dry summers. On average, the Roca Honda property receives approximately 11 inches of precipitation annually, most of which occurs during thunderstorms in July and August. Grants, New Mexico has an annual average temperature of 50°F, with an average summer high of 87°F and low of 52°F, and average winter high of 47°F and low of 18°F. Year-round operations are expected.

The community of Grants, New Mexico, located in Cibola County, is the largest community near the Roca Honda Project. As of the 2010 census, there are 9,182 people residing in Grants, where supplies can be obtained, and personnel experienced in underground mining, construction and mineral processing are available.

The Roca Honda Project area is sparsely populated, rural and largely undeveloped. The predominant land uses include low density grazing and cultivation, and recreational activities such as hiking, sightseeing, and seasonal hunting. The Roca Honda property has moderately rough topography in Sections 9 and 10 and consists of shaley slopes below ledge-forming sandstone beds, as mesas, that dip 7° to 11° northeast. Elevations range from 7,100 feet to 7,800 feet. Section 9 consists mostly of steep slopes in the west and south, with a large sandstone mesa in the north central part. Section 10 consists mostly of the dip-slope of a sandstone bed that dips from 8° to 11° east. Sections 16 and 17 have less topographic relief, with elevations ranging from 7,100 to 7,300 feet and easterly dipping slopes. Vegetation in the Roca Honda Project area consists of grasses, piñon pine and juniper trees.

#### Ownership

Prior to May 27, 2016, the Roca Honda Project (excluding the Adjacent Properties) was held by RHR, a joint venture owned by Energy Fuels’ wholly-owned subsidiary Strathmore Resources, (US) Ltd. (60%) and Sumitomo’s subsidiaries SC Clean Energy and Summit New Energy Holding, LLC (together, 40%). On May 27, 2016 the Company acquired Sumitomo’s 40% interest in RHR, and the Roca Honda Project is now held entirely by our wholly-owned subsidiary, Strathmore Resources, (US) Ltd. As consideration for the 40% interest, the Company issued to Sumitomo 1,212,173 Common Shares of the Company and agreed to pay $4.5 million of cash upon the first commercial production of uranium from the Roca Honda Project. The Adjacent Properties were acquired by the Company from URI in June 2015.

The Roca Honda property covers an area of 4,440 acres and includes 63 unpatented lode mining claims in Sections 9 and 10, 64 unpatented claims in Sections 5 and 6, 36 unpatented claims in Section 8, one adjoining New Mexico State General Mining Lease in Section 16, and the fee minerals interest in all of Section 17. The mining claims also extend onto a 9.4-acre narrow strip of Section 11. The New Mexico State Lease was acquired by David Miller (the former Strathmore CEO) on November 30, 2004, and subsequently transferred to Strathmore. Strathmore then relinquished the Lease and acquired it again in December 2015 (State Mining Lease No. HG-0133) for a new 15-year term expiring on December 14, 2030. The “Roca Honda” Claims in Sections 5 and 6 were staked by Miller and Associates in September 2004 and assigned to RHR on August 28, 2013. Strathmore acquired the Adjacent Properties, comprised of the “Roca Honda” claims in Section 8 and the fee mineral interest in Section 17 on June 26, 2015 from URI.

The State Mining Lease (No. HG-0133) issued by the New Mexico State Land Office for Section 16 covers an area of 638 acres. The surface of Section 16 is leased to Fernandez as rangeland for grazing. The area covered by the Fernandez lease is also referred to as “Lee Ranch.” The Mining Lease has a primary, secondary, tertiary, and quaternary term, each with rentals to be paid in advance, and will not expire until December 14, 2030. The holding cost for the lease is $10 per acre annually.

The State lease stipulates a 5% gross returns royalty to the State of New Mexico “less actual and reasonable transportation and smelting or reduction costs, up to 50% of the gross returns” for production of uranium, which is designated a “special mineral” in the lease. New Mexico mining and private royalties on value of minerals extracted are shown below:

- Section 9 Gross Royalty (1%); and
- Section 16 New Mexico State Lease Royalty (5%).

Under the rights acquired in the URI transaction, a gross royalty of 1% is payable to the surface owner.

#### Permitting and Licensing

The Roca Honda Project is at an advanced stage of permitting. A Draft EIS was completed by the USFS in February 2013. In March 2015 the USFS initiated the scoping process for a new mine dewatering alternative to be addressed in a Supplement to the Draft EIS. In September 2016, an additional scoping process to incorporate Section 17 (the “**Adjacent Properties”**) and development drilling into the mine plan was initiated by the USFS. The Supplement to the Draft EIS is expected to be completed during late 2021 or early 2022 with a Final EIS and RoD scheduled to be completed in 2022.

Other major permits required for the Roca Honda Project include a Permit to Mine to be issued by the New Mexico Mining and Minerals Division, a Discharge Permit issued by the New Mexico Environment Department, and a Mine Dewatering Permit issued by the New Mexico State Engineer’s Office. The Mine Dewatering Permit was approved in December 2013 but appealed by the Acoma Pueblo in January 2014. RHR subsequently proposed a new alternative for discharging treated mine water that would benefit a number of downstream users including the Acoma Pueblo. The Acoma Pueblo agreed to withdraw the dewatering permit appeal in March 2015. The dewatering permit will need to be revised to reflect a higher dewatering rate with the addition of Section 17 to the mine plan.

The two other major permits that are in the agency review stage are the Discharge Permit, which is expected to be issued in late 2022, and the Permit to Mine, which is expected to be issued in 2022 following approval of the Final EIS by the USFS. Permit approvals from the USACE and the EPA are also required for discharge of treated mine water associated with mine activities. An application for the USACE permit has been submitted and the permit is expected prior to issuance of the Permit to Mine in 2022. An application for the EPA permit has also been submitted, however; the previous application is expected to be withdrawn and a new application submitted during 2021. The EPA permit for discharge of treated mine water is expected prior to issuance of the Permit to Mine in 2022. EPA approval under the Clean Air Act National Emissions Standard for Hazardous Air Pollutants will also be required prior to mining.

As the project has not yet been developed or operated, we are not aware of any environmental liabilities of any significance.

No permitting is required to start milling the Roca Honda Project material at the White Mesa Mill. The White Mesa Mill is fully permitted with the State of Utah and has all the necessary operating licenses for a conventional uranium mill. As additional tailings storage capacity may eventually be required at the Mill over the life of the mine, an Amendment to the White Mesa Mill’s Radioactive Materials License issued by the Utah Division of Waste Management and Radiation Control will be required in due course to construct additional tailing cells, if and when required.

#### Geological Setting

The Roca Honda Project area is located in the southeast part of the Ambrosia Lake sub-district of the Grants uranium district and is near the boundary between the Chaco slope and the Acoma sag tectonic features. This sub-district is in the southeastern part of the Colorado Plateau physiographic province and is mostly on the south flank (referred to as the Chaco slope) of the San Juan Basin.

Rocks exposed in the Ambrosia Lake sub-district of the Grants Mineral Belt, which includes the Roca Honda Project area, comprise marine and non-marine sediments of Late Cretaceous age, unconformably overlying the uranium-bearing Upper Jurassic Morrison Formation. The uppermost sequence of conformable strata consists of the Mesaverde Group, Mancos Shale, and Dakota Sandstone. All rocks that outcrop at the Roca Honda Project area are of Late Cretaceous age.

The uranium found in the Roca Honda Project area is contained within five sandstone units of the Westwater Canyon Member. Zones of mineralization vary from approximately one foot to 30 feet thick, 100 feet to 600 feet wide, and 200 feet to 3,000 feet in length. Uranium mineralization in the Project area trends west-northwest, consistent with trends of the fluvial sedimentary structures of the Westwater Canyon Member, and the general trend of mineralization across the Ambrosia Lake sub-district.

Core recovery from the 2007 drilling program indicates that uranium occurs in sandstones with large amounts of organic/high carbon material. Non-mineralized host rock is much lighter (light brown to light gray) and has background to slightly elevated radiometric readings.

#### History

Kerr-McGee Oil Industries, Inc. (“**Kerr-McGee”**) staked the Roca Honda Project unpatented mining claims in Sections 9 and 10 in June 1965. Kerr-McGee, its subsidiaries, and successor in interest Rio Algom had held the claims until the property was acquired by Strathmore on March 12, 2004. Energy Fuels acquired a 100% interest in Strathmore in September 2013, assuming Strathmore’s

60% ownership interest in RHR and becoming the project operator. Strathmore purchased Sumitomo’s 40% interest in RHR on May 27, 2016.

Drilling on the property began in 1966. Kerr-McGee performed a number of rotary drill hole exploration programs from 1966 to 1985. In Section 9, the first drill hole was completed in July 1966. Discovery was made in drill hole number 7 completed on August 2, 1970, which encountered mineralization at a depth of 1,900 feet. From 1966 to 1982, a total of 187 drill holes were completed for a total of 388,374 feet.

In Section 10, the first hole was drilled in October 1967. Discovery was made in drill hole number 6 completed on March 19, 1974, which encountered mineralization at a depth of 2,318 feet. From 1967 to 1985, a total of 175 drill holes were completed for a total of 459,535 feet.

In Section 16, the first drilling was in the 1950s by Rare Metals, which drilled 13 holes, including two that intercepted high-grade uranium mineralization at depths of 1,531 feet and 1,566 feet. No records of the total drilled footage were located. Subsequently, Western Nuclear acquired a mining lease for Section 16 from the State and began drilling in 1968, with the first drill hole completed on August 17, 1968. The second drill hole intercepted high-grade uranium mineralization at a depth of 1,587 feet. From 1968 through September 1970, Western Nuclear drilled 63 holes totaling 121,164 feet, not including six abandoned holes totaling 7,835 feet. Two of the drill holes reported cored intervals, but the cores and analyses were not available. From the late 1960s to the early 1980s, a total of 725 drill holes totaling over 1,425,000 feet were completed on the six Sections (5, 6, 8, 9, 10 and 16) of the Roca Honda property. More than 500 holes totaling over 841,900 feet were also drilled in Section 17 by Kerr-McGee and Western Nuclear. In June 2015, Energy Fuels acquired a 100% interest in the mineral properties controlled by URI (Sections 8 and 17).

RHR drilled four pilot holes on Section 16, of which three were completed as monitor wells totaling 8,050 feet for environmental baseline and monitoring purposes in Section 16 from June through November 2007. One drill hole was located outside of known mineralization, and three holes were located within mineralized areas. The entire thickness of the Westwater Sandstone, except for zones with no recovery, was cored in the pilot holes for these wells. The cores are PQ diameter (3.345 inches) and were taken principally for laboratory testing of hydraulic conductivity, effective porosity, density, and chemical analysis.

In November 2011, a core hole was drilled at the Section 16 shaft location. The hole was drilled to a depth of 2,053 feet. Core was tested for numerous geotechnical properties.

No historic mineral extraction has occurred on the property.

#### Mineralization

Uranium mineralization consists of unidentifiable organic-uranium oxide complexes. The uranium in the project area is dark gray to black in color and is found between depths of approximately 1,450 feet and 2,600 feet below the surface.

Primary mineralization predates, and is not related to, present structural features. There is a possibility of some redistribution and stack mineralization along faults; however, it appears that most of the Roca Honda Project mineralization is primary.

Paleochannels that contain quartz-rich, arkosic, fluvial sandstones are the primary mineralization control associated with this trend. Previous mining operations within the immediate area suggest that faults in the Roca Honda Project area associated with the San Mateo fault zone post-date the emplacement of uranium. Therefore, it may be expected that mineralized zones in the Roca Honda Project area are offset by faults.

The mineralization is typically confined to sandstones in the Westwater Canyon Member, although there is some overlap into the shales that divide the sandstones and some minor extension (less than 10 feet) into the underlying Recapture Member. The mineralization is contained in the Westwater Canyon Member sandstones across the Project area, but in Sections 9 and 16, the mineralization is typically found in the upper sandstones (A, B1, and B2), as it is in Section 17, also. In Section 10, the A and B1 sandstones pinch out in some areas due to thickening of the overlying Brushy Basin Member. Mineralization is in the middle and western portions of Section 10 and is typically in the lower sandstones (sands C and D).

Sedimentary features may exhibit control on a small scale. At the nearby Johnny M mine, a sandstone scour feature truncates underlying black mineralization, indicating nearly syngenetic deposition of uranium mineralization with the sandstone beds.

#### Mineral Resource Estimates

RPA prepared an updated PEA in 2016, which contains an NI 43-101 compliant Mineral Resource estimate for the Roca Honda Project. Mineral Resources are constrained by wire frames generated around individual mineralized zones within five sand horizons designated as A, B1, B2, C, and D sands.

#### Roca Honda Mineral Resources – Uranium(1)(2)(3)(4)

| Classification | Tons (000) | Grade % eU3O8 | Pounds eU3O8 (000) |
| --- | ---: | ---: | ---: |
| Roca Honda Measured Resources (M) | 208 | 0.477% | 1,984 |
| Roca Honda Indicated Resources (I) | 1,303 | 0.483% | 12,580 |
| **Roca Honda Total (M & I)** | **1,511** | **0.482%** | **14,564** |
| **Roca Honda Inferred Resources** | **1,198** | **0.468%** | **11,206** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not reserves do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources are estimated at a uranium cut-off grade of 0.19% eU3O8.

(3) Mineral Resources are estimated using a long-term uranium price of $65 per pound U3O8.

(4) Numbers may not add due to rounding.

Energy Fuels acquired the mineral rights to the Section 17 property adjacent to its main Roca Honda project in 2015. An historical estimate for the Section 17 property was completed by URI in 2007. URI estimated that the Section 17 property contained approximately 510,000 tons at a grade of 0.37% U3O8 for 3.8 million pounds of uranium. This historical estimate is based on over 500 surface drill holes and was calculated using the circle tangent method. A density of 15 cu feet per ton was used.

RPA and the Company do not consider this historical estimate to be current mineral resources or reserves as defined under NI 43-101. While Energy Fuels has reviewed all drill hole data associated with this estimate, a qualified person has not done sufficient work to classify this historical resource as current mineral resources or mineral reserves in accordance with NI 43-101. This historical estimate was unclassified. The Company believes this historical estimate is relevant, as the methodology was well documented and utilized industry standard practice. However, the methodologies used do not reflect current best industry practices. The Company does not consider these historical estimates to be equivalent to current mineral resources or mineral reserves as defined in NI 43-101, nor has the Company completed sufficient work to confirm a NI 43-101 compliant resource. Therefore, the historical estimates cannot, and should not, be relied upon as NI 43-101 resources or reserves.

#### Present Condition of the Property and Work Completed to Date

Old drill roads were previously established across the property, and an electrical line transects the northern half of Section 16 in the project area. The line continues along the west side of the project area into Section 17, where it terminates, and on the east side of Section 16 through the northwest quarter of Section 15 and along the southern section boundary of Section 10. Three monitor water wells were drilled by RHR in 2007 and are located on Section 16. Other items installed by RHR include a permanent electrical weather station and a high-volume TSP and PM10 air samplers. Three, dry man-made impoundments are also located on Section 16. More than 400 historic drill exploration holes were completed on the property from the late 1960s to the early 1980s. Except for the existing shaft on Section 17, there are no mine workings, existing tailings ponds, waste deposits or other improvements or facilities at the site.

No additional exploration work has been conducted on the Roca Honda Project since November 2011, when a core drill hole was completed at the proposed shaft location in Section 16 for geotechnical studies.

The Roca Honda Project was acquired by the Company in August 2013, through the Company’s acquisition of Strathmore. As of December 31, 2020, the total cost attributable to the Roca Honda Project on the financial statements of the Company was $22.1 million.

Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions, the Company intends to continue its permitting and related activities at the Roca Honda Project during 2021. Permitting efforts in 2021 include the integration of the Adjacent Roca Honda Properties into the permitting efforts underway for the Roca Honda Project properties, including the submittal of a revised National Pollutant Discharge Elimination System (“**NPDES”**) permit application to the EPA and continuation of the Supplement to the Draft EIS through the USFS.

### The Sheep Mountain Project

Unless indicated otherwise, the Sheep Mountain Project technical information included in this Report on Form 10-K is based on a technical report entitled “*Sheep Mountain Uranium Project, Fremont County, Wyoming, USA, Updated Preliminary Feasibility Study, National Instrument 43-101 Technical Report, Amended and Restated”* dated February 28, 2020, prepared by Douglas L. Beahm, P.E., P.G., Principal Engineer of BRS Inc. in accordance with NI 43-101 (the “**Sheep Mountain Technical Report”**). Douglas L. Beahm is a “qualified person” and is “independent” of the Company within the meaning of NI 43-101. The Mineral Resource and Mineral Reserve estimates set out in the Sheep Mountain Technical Report were updated in 2019 to reflect current guidance for prospects for eventual economic extraction. The updated Mineral Resource and Mineral Reserve estimates are summarized in an updated technical report which was filed on SEDAR on February 28, 2020 and available at www.sedar.com. The technical report was updated to account for permitting changes to the Project that were made after 2012, and to update the Mineral Resource estimate based on current guidance for prospects for eventual economic extraction. The resource associated with the Sun-Mc area was removed from this update as it does not meet guidance for prospects for eventual economic extraction at $60 per pound U3O8. The resource given in the 2012 Technical Report should now be considered historical in nature. The Sun-Mc resource was never part of the mine plan, and therefore does not impact the economics in the updated Sheep Mountain Technical Report.

#### Project Description and Location

The Sheep Mountain Project is an underground and open pit uranium project. The Sheep Mountain Project was acquired on February 29, 2012, as a result of the Company’s acquisition of Titan Uranium Inc. (“**Titan”**). The Sheep Mountain Project is located eight miles south of Jeffrey City, Wyoming within the Wyoming Basin physiographic province at the northern edge of the Great Divide Basin in central Wyoming. The Project is located throughout portions of Sections 8, 9, 15, 16, 17, 20, 21, 22, 27, 28, 29, 30, 31, 32, and 33, Township 28 North, Range 92 West.

The Sheep Mountain Project includes the Congo Pit, comprised of the Congo, North Gap, and South Congo areas, a proposed heap leach facility, and the reopening of the existing underground facility (the “**Sheep Underground”**), which includes the Sheep I and Sheep II underground areas. Although alternatives were considered in the past, the current recommended recovery method is the processing of extracted materials via an on-site heap leach facility. Material from the underground and open pit operations are expected to be commingled at the stockpile site located near the underground portal and in close proximity to the pit. At the stockpile, the mineralized material will be sized if needed, blended, and then conveyed via a covered overland conveyor system to the heap leach pad where it will be stacked on a double lined pad for leaching. The primary lixiviant will be sulfuric acid. Concentrated leach solution will be collected by gravity in a double lined collection pond and then transferred to the mineral processing facility for extraction and drying. The final product produced will be uranium concentrate (U3O8, also known as “**yellowcake”**). Energy Fuels owns the White Mesa Mill and the Nichols Ranch Plant, which creates the option to transport loaded resin to either of those facilities for stripping, and to the White Mesa Mill for drying, and packaging of yellowcake.

The preferred alternative for the development of the Sheep Mountain Project is the concurrent operation of the open pit and underground mining operations with onsite uranium processing and recovery at the heap leach facility. A preliminary feasibility study (“**PFS”**) for the project has been completed in accordance with NI 43-101, which includes the preliminary design and sequencing of the open pit and underground operations and the heap leach mineral processing facility. Designs and sequencing are inclusive of pre-production, production, and decommissioning and reclamation. The currently planned mine life of the open pit is 12 years with an additional four years allotted for mine closure and reclamation. The currently planned mine life of the underground is 12 years, including one year for development of the primary decline.

The current design for the Congo Pit includes typical highwall heights in the range of 100 to 400 feet and reaches a maximum depth of 600 feet in localized areas in the southeast pit corner. The open pit design employs similar design parameters and mining equipment configurations to those used successfully in past Wyoming conventional uranium operations. Highwall design is based upon the performance of past projects in the Sheep Mountain and Gas Hills districts and includes an average highwall slope of 0.7:1, which reflects the average of a 10-foot bench width and 50-foot wall at a 0.5:1 slope.

The underground mining method proposed is a modified room and pillar method, based on past success in the area, but utilizing modern equipment such as jumbo drills and 7 cubic-yard scooptrams for haulage. A new double entry decline will be constructed starting at the Paydirt Pit and ending below the deposit. Haulage from the facility will be accomplished via a 36-inch conveyor within one of the double declines. The existing shafts will be used for ventilation purposes only, with exhaust fans mounted at both locations. If the existing borehole ventilation shafts can be rehabilitated, they will be used as intake shafts.

In 2013, the Company submitted a revised PO to the BLM, which included redesign of the heap leach processing area and the option to potentially transport the mineralized material to an off-site processing facility. The revision to the PO is expected to provide more flexibility in processing the resources extracted from the Sheep Mountain Project. A RoD giving BLM’s final approval of the revised PO was issued on January 6, 2017.

#### Accessibility, Climate, Local Resources, Infrastructure and Physiography

The Sheep Mountain Project is located at approximate Latitude 42°24’ North and Longitude 107° 49’ West within the Wyoming Basin physiographic province in the Great Divide Basin at the northern edge of the Great Divide Basin. The project is approximately eight miles south of Jeffrey City, Wyoming. The nearest commercial airport is located in Riverton, Wyoming approximately 56 miles from Jeffrey City on a paved two-lane state highway. The project is accessible via 2-wheel drive on existing county and two-track roads.

The Sheep Mountain Project falls within the inter-mountain semi-desert weather province, with average maximum temperatures ranging from 31.1 °F (January and December) to 84.9 °F (July), average minimum temperatures ranging from 9.1 °F (January) to 49.2 °F (July), and average total monthly precipitation ranging from 0.36 inches (January) to 2.04 inches (May). The topography consists of rounded hills with moderate to steep slopes. Elevations range from 6,600 feet to 8,000 feet above sea level. The ground is sparsely vegetated with sage and grasses and occasional small to medium sized pine trees at higher elevations. Year-round operations are contemplated for the Sheep Mountain Project.

Telephone, electric and natural gas service adequate for the planned extraction and mineral processing operations have been established at the Sheep Mountain Project. Electric service and a waterline have been extended via right-of-way issued by the BLM in 2011 to the existing Sheep 1 and 2 shafts. Adequate water rights are held by the Company for planned extraction and mineral processing operations but need to be updated with the Wyoming State Engineer with respect to type of industrial use, points of diversion, and points of use.

We believe that sufficient surface rights are in place for the contemplated operations, including tailings storage areas, waste disposal, and heap leach pads.

#### Ownership

The mineral properties at the Sheep Mountain Project are comprised of 218 unpatented mining claims (subsequent to the date of the Sheep Mountain Technical Report, the Company added 13 claims to the 179 reported in the Sheep Mountain Technical Report) on land administered by the BLM; approximately 640 acres of State of Wyoming leases; and approximately 630 acres of private leases on fee lands. In February 2012, Energy Fuels purchased 320 acres of private surface overlaying some of the federal minerals covered by 18 of the claims. The purchased parcel includes the SW¼ SW¼ Section 28 and SE¼, E½ SW¼, and NW¼ SW¼ Section 29, T28N, R92W. A final payment of $5,000 was made in January 2016 for the purchased parcel. The combination of land holdings (including the 13 new claims) comprises approximately 4,675 acres and gives Energy Fuels mineral rights to resources as defined in the Congo Pit and the Sheep Underground areas. After the 2012 Technical Report, the Company increased the Sheep

Mountain property size by 26 unpatented mining claims (approximately 520 acres) through the acquisition of Strathmore. These contiguous claims form a larger buffer, with potential for additional uranium resources, along the west side of the Project. The current total land position is approximately 5,195 acres.

To maintain these mineral rights, the Company must comply with the lease provisions, including annual payments with respect to the State of Wyoming leases; private leases; BLM and Fremont County, as well as Wyoming filing and/or annual payment requirements to maintain the validity of the unpatented mining lode claims as follows. Mining claims are subject to annual filing requirements and payment of a fee of $165 per claim. Unpatented mining claims expire annually but are subject to indefinite annual renewal by filing appropriate documents and paying the fees described above. ML 0-15536 will expire on 1/1/2024. Annual Payments to maintain ML 0-15536 are $2,560 per year. The original private lease dated November 20, 2975 between McIntosh Cattle Company and Western Nuclear Inc. (the “Private Lease”) expired 11/20/2015. Properties covered by the Private Lease include: Township 28 North, Range 92 West, 6th PM; Section 20: S½SW¼; Section 29: NW¼, SW¼SW¼; Section 30: SE¼NE¼, E½SE¼; Section 31: E½NE¼; Section 32: E½NE¼; Section 33: S½NW¼. Since the date of the Sheep Mountain Technical Report, the Company no longer holds the Private Lease, however a Surface Owner’s Agreement (originally dated January 27, 1970, as amended on April 14, 1981 and ratified by assignees on April 16, 2007) covering the same parcels and a few select claims in the Sun-Mc area is still in effect. It carries a 2% mine value royalty for any material extracted from the subject lands, but no other payment obligations.

The Sheep Mountain Project is subject to an overall sliding scale royalty of 1% to 4% due to Western Nuclear, based on the Nuclear Exchange Corporation Exchange (“**NUEXCO”**) Value. This royalty is currently at its maximum rate of 4%. Under Wyoming State Lease ML 0-15536, there is a royalty of 5% of the quantity or gross realization value of the U3O8, based on the total arms-length consideration received for uranium products sold.

Uranium mining in Wyoming is subject to both a gross products tax (county) and a mineral severance tax (state). At the federal level: aggregate corporate profit from mining ventures is taxable at corporate income tax rates, i.e., individual mining projects are not assessed federal income tax but, rather, the corporate entity is assessed as a whole. For mineral properties, depletion tax credits are available on a cost or percentage basis (whichever is greater). The percentage depletion tax credit for uranium is 22%, among the highest for mineral commodities, IRS Pub. 535.

#### Permitting and Licensing

In June 2010, Titan commenced baseline environmental studies to support an application to the NRC for a Source Material and Byproduct Material License (the “**License”**) for operation of a heap leach facility. Work was also initiated on a revision to the existing WDEQ Mine Permit, as well as a PO for the BLM. Baseline studies included wildlife and vegetation surveys, air quality and meteorological monitoring, ground and surface water monitoring, radiological monitoring, and cultural resource surveys.

Submission of the PO to the BLM was made in June 2011. The PO was accepted as complete by the BLM, and an EIS was initiated in August 2011. Energy Fuels revised the PO in July 2012, consistent with the modified plan presented in the Sheep Mountain Technical Report. In July 2013, the PO was again revised to reflect a new waste rock disposal layout for the open pit mine and an improved and more economical heap leach and processing facility. The revised PO also included the option of transporting mineralized material off-site for processing. The Final EIS was completed in August of 2016. On January 6, 2017, the BLM issued its RoD and approved the PO.

In October 2011, Titan submitted a draft revision to its existing Mine Permit 381C to WDEQ. WDEQ then provided Titan with review comments as part of its “courtesy review.” The proposed permit amendment was revised and resubmitted in January 2014. In July 2015, the revision was approved by WDEQ. The revision includes expansion of surface and underground mining operations and an updated reclamation plan consistent with current reclamation practices.

Development of an application to the NRC for a license to construct and operate the uranium recovery facility has been taken to an advanced stage of preparation. This license would allow Energy Fuels to process the mineralized material into yellowcake at the Sheep Mountain Project site. The draft application to NRC for a Source Material License was reviewed in detail by the NRC in October 2011. The NRC audit report identified areas where additional information should be provided. Effective September 30, 2018, the State of Wyoming became an Agreement State under the Atomic Energy Act (as amended) for the regulation of uranium mills and heap leach facilities, and authorization for the Source Material and Byproduct Material License was transferred from the NRC to WDEQ-LQD. The review and approval process for this license is anticipated to take approximately four years from the date submitted to the WDEQ-LQD. Submittal of the license application to the WDEQ-LQD is on hold pending the Company’s evaluation of off-site processing options for this project, and whether or not to proceed with an on-site uranium recovery facility, pending improvements in uranium market conditions.

The heap leach facility has been permitted by the State of Wyoming through issuance of the Mine Permit and by the BLM, yet still requires licensing by the WDEQ-LQD. Mining could commence at this time under the existing RoD and Mine Permit, but the mined ore would need to be processed at a licensed off-site processing facility under a toll-milling or other arrangement.

#### Geological Setting

A primary component of the geology for the Sheep Mountain Project is the Battle Spring Formation. Battle Spring is Eocene in age. Prior to deposition of the Battle Spring Formation and subsequent younger Tertiary formations, underlying Paleocene, Cretaceous, and older formations were deformed during the Laramide Orogeny. During the Laramide Orogeny, faults, including the Emigrant Thrust Fault at the northern end of the project area, were active and displaced sediments by over 20,000 feet. Coincident with this mountain building event, Paleocene and older formations were folded in a series of echelon anticlines and synclines, generally trending from southeast to northwest. The Battle Spring Formation was deposited unconformably on an erosional landscape influenced by these pre-depositional features. Initial stream channels transporting clastic sediments from the Granite Mountains formed in the synclinal valleys.

The geologic setting of the Sheep Mountain Project is important in that it controlled uranium mineralization by focusing movement of the groundwaters, which emplaced the uranium into the stream channels, which had developed on the pre-tertiary landscape. The Battle Spring Formation and associated mineralization at the Sheep Mountain Project is bounded to the east by the western flank of the Sheep Mountain Syncline and to the west by the Spring Creek Anticline. To the north the system is cut off by erosion. To the south the Battle Spring continues into the northern portions of the Great Divide Basin.

Mineralization occurs throughout the lower A Member of the Battle Spring Formation and is locally up to 1,500 feet thick. The upper B Member is present only in portions of the project and may be up to 500 feet thick. Although arkosic sandstone is the preferred host, uranium has been extracted from all lithologies. Grade and thickness are extremely variable depending on whether the samples are taken from the nose or the tails of a roll front. Typically, the deposits range from 50 feet to 200 feet along a strike, five feet to eight feet in height, and 20 feet to 100 feet in width. Deposits in the Sheep Mountain Project area occur in stacked horizons from 7,127 feet in elevation down to 6,050 feet in elevation.

#### History

The Sheep Mountain Project was acquired by Energy Fuels on February 29, 2012, as a result of the Company’s acquisition of Titan, which is now a wholly owned subsidiary of Energy Fuels. Titan acquired the Sheep Mountain Project in two transactions in 2009. A 50% working interest was acquired when Titan completed a business combination with Uranium Power Corp. (“**UPC”**) on July 31, 2009. UPC is now a wholly-owned subsidiary of Energy Fuels. At that time, UPC and UPC’s U.S. subsidiary UPC Uranium (USA) Inc. (now known as Energy Fuels Wyoming Inc.) became wholly-owned subsidiaries of Titan. The remaining 50% of the Sheep Mountain Project was owned by Uranium One Inc. (“**U1”**) which was UPC’s joint venture partner for the project. On October 1, 2009, Titan acquired U1’s 50% interest, giving Titan a 100% interest in the Sheep Mountain Project. On February 29, 2012, Energy Fuels acquired Titan and its subsidiaries, at which point the Sheep Mountain Project became 100% owned by the Company.

The Sheep Mountain Project was operated as an underground and open pit mine at various times in the 1970s and 1980s. 5,063,813 tons of mineralized material were mined and milled, yielding 17,385,116 pounds of uranium at an average grade of 0.17% U3O8. Mining was suspended in 1988 and the project has been on care and maintenance since that time.

Uranium was first discovered in the Crooks Gap District, which includes the Sheep Mountain Project, in 1953. While the original discoveries were aided by aerial and ground radiometric surveys, exploration activities were primarily related to drilling and exploratory trenching. Three companies dominated the district by the mid-1950s: Western Nuclear Inc. (“**Western Nuclear”**), Phelps Dodge Corporation (“**Phelps Dodge”**), and Continental Uranium Corporation (“**Continental”**). Western Nuclear built the Split Rock mill at Jeffrey City in 1957 and initiated production from the Paydirt pit in 1961, Golden Goose 1 in 1966, and Golden Goose 2 in 1970. Phelps Dodge was the principal shareholder and operator of the Green Mountain Uranium Corporation’s Ravine Mine, which began production in 1956. Continental developed the Seismic Pit in 1956, the Seismic Mine in 1957, the Reserve Mine in 1961, and the Congo Decline in 1968. In 1967, Continental acquired the Phelps Dodge properties and in 1972, Western Nuclear acquired all of Continental’s Crooks Gap holdings. During the mid-1970’s Phelps Dodge acquired an interest in Western Nuclear, which began work on the Sheep Mountain I in 1974, the McIntosh Pit in 1975, and Sheep Mountain II in 1976. Western Nuclear ceased production from the area in 1982. Western Nuclear production from the Sheep Mountain I is reported to have been 312,701 tons at 0.107% U3O8. Subsequent to the closure of the Sheep Mountain I by Western Nuclear, during April to September 1987, Pathfinder Mines Corporation (“**Pathfinder”**) mined a reported 12,959 tons, containing 39,898 pounds of uranium at an average grade of 0.154% U3O8 from Sheep Mountain I. U.S. Energy-Crested Corp. (“**USECC”**) acquired the properties from Western Nuclear in 1988, and during May to October 1988, USECC mined 23,000 tons from Sheep Mountain I, recovering 100,000 pounds of uranium for a mill head grade of 0.216% U3O8. The material was processed at Pathfinder’s Shirley Basin mill, 130 miles east of the Project. The Sheep Mountain I mine was allowed to flood in April 2007. UPC (then known as Bell Coast Capital) acquired a 50% interest in the property from USECC in late 2007. USECC later sold all of its uranium assets to U1. Titan acquired UPC’s 50% interest in the property when it acquired UPC by a plan of arrangement in July 2009. Titan acquired U1’s interest in the Sheep Mountain Project in September 2009.

During the National Uranium Resource Evaluation (“**NURE”**) program conducted by the DOE in the late 1970s and early 1980s, the project area and vicinity were evaluated. This evaluation included aerial gamma, magnetic, and gravimetric surveys, soil and surface water geochemical surveys and sampling, and geologic studies and classification of environments favorable for uranium mineralization.

Approximately 4,000 holes were drilled in the project area prior to 1988, most of which were open-hole rotary drilling, reliant upon down-hole geophysical logging to determine equivalent uranium grade % eU3O8.

However, some core drilling for chemical analysis was also completed. The drill maps show hole locations at the surface and downhole drift, the thickness and radiometric grade of uranium measured in weight percent U3O8, elevation to the bottom of the mineralized intercept, collar elevation, and elevation of the bottom of the hole.

In 2006, UPC completed a drilling program consisting of 19 holes totaling 12,072 feet. Two of the 19 holes were located in Section 28 for the purpose of confirming the mineralization within the Sheep Underground mine area. The remaining 17 holes were completed in the planned Congo Pit to test both shallow mineralization and to explore a deeper mineralized horizon. Such 2006 drilling efforts confirmed the presence of mineralization in the shallow horizons of the Congo Pit area, leading to the identification and extension of roll front mineralization in the 58 sand along strike.

Following the acquisition of UPC by Titan, five holes were drilled in the Congo Pit area in 2009 for a total of 1,700 feet. In situ mineral grades for 2009 drilling were determined by geophysical logging including both conventional gamma logging and state of the art Uranium Spectrum Analysis Tool. In 2010, Titan also drilled 62 exploratory drill holes and 5 monitor wells in the Congo Pit area, followed by an additional 73 exploratory drill holes and 5 monitor wells in 2011. There were a total of 140 exploration holes drilled between 2009 and 2011 totaling approximately 44,000 feet.

No relevant exploration work, other than this drilling, has been conducted on the property in recent years. The project is located within a brownfield site, which has experienced past mine production and extensive exploration and development drilling. The initial discovery was based on aerial and ground radiometric surveys in the 1950s, but since that time exploratory work on the site has been primarily drilling.

#### Mineralization

Most of the mineralization in the Crooks Gap District occurs in roll-front deposits. Roll fronts have an erratic linear distribution but are usually concordant with the bedding. Deposits have been discovered from the surface down to a depth of 1,500 feet. The two major uranium minerals are uranophane and autunite. Exploration drilling indicated that the deeper roll-type deposits are concentrated in synclinal troughs in the lower Battle Spring Formation. Three possible sources for uranium have been suggested: post-Eocene tuffaceous sediments, leached Battle Spring arkoses, and Precambrian granites. Structural controls of uranium occurrences along roll fronts include carbonaceous siltstone beds that provide a local reducing environment for precipitation of uranium-bearing minerals, and abrupt changes in permeability along faults, where impermeable gouge is in contact with permeable sandstones. Uranium has also been localized along the edges of stream channels and at contacts with carbonaceous shales.

#### Mineral Resource and Mineral Reserve Estimates

#### Mineral Resources

The Mineral Resource estimates for the Sheep Mountain Project as set out in the Sheep Mountain Technical Report are summarized in the following table. The Mineral Resource estimates presented herein have been completed in accordance with CIM Standards and NI 43-101. Based on the drill density, the apparent continuity of the mineralization along trends, geologic correlation and modeling of the deposit, a review of historic mining with respect to current resource projections, and verification drilling, the Mineral Resource estimate herein meets CIM criteria as an Indicated Mineral Resource. These Indicated Mineral Resources are not Reserves within the meaning of SEC Industry Guide 7. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above. Below is a summary of the total Indicated Mineral Resources(1) estimated for the Sheep Mountain Project as of April 8, 2019. This Mineral Resource estimate was updated and revised to reflect a lower assumed long-term uranium price per pound U3O8 than what was used in the previous (April 2012) estimate. This updated estimate is summarized in an updated version of the technical report, which was filed on SEDAR on February 28, 2020. This updated Mineral Resource estimate is lower than the estimate in the April 2012 report.

#### Sheep Mountain Mineral Resources – Uranium(1)(2)(3)(4)

| Classification Zone G.T. Cut-off Sheep Mountain Measured Resources (M) --- --- | Tons (000) --- | Grade % eU3O8 --- | Pounds eU3O8 (000) --- |
| --- | ---: | ---: | ---: |
| Sheep Mountain Indicated Resources (I) Sheep Underground 0.3 | 5,547 | 0.117% | 13,032 |
| Congo Pit Area 0.1 6,116 | 0.122% | 14,903 |  |
| **Total (M & I)(5)** | **11,663** | **0.12%** | **27,935** |
| **Sheep Mountain Inferred Resources** **---** **---** | **---** | **---** | **---** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7. Mineral resources that are not reserves do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources are estimated at a uranium grade x thickness (G.T.) cut-off grade of 0.10 G.T. (2 ft. of 0.05% eU3O8 for the Congo Pit and 0.30 G.T. (6 ft. of 0.05% eU3O8) for the Sheep Underground.

(3) Numbers may not add due to rounding.

(4) Mineral Resources are estimated using a long-term uranium price of $60 per pound U3O8.

(5) The decrease in the indicated resource from April 2012 is due to a decrease in the price used in cutoff grade calculations ($65 to $60 per pound U3O8). The decreases in the resource include approximately 93,000 tons from the Sheep Underground, 60,000 tons from the Congo Pit Area and all 1,080,000 tons from the Sun-Mc Area. The Sun-Mc resource given in the 2012 PFS should now be considered historical in nature.

This mineral resource estimate removes those portions of the resource that fall within the historic limits in the Congo Pit. It is estimated that some 25% of the initial resource estimate and the total reported mined tonnage from the historic Sheep I underground mine was removed. From a review of the Sheep I and II existing mine workings, it was apparent that little or no mineralized material was mined at the historic Sheep II and that only development work was completed. Estimated mineral resources for potential open pit areas were diluted to a minimum mining thickness of two feet and a cutoff grade of 0.05% U3O8, which equates to a 0.10 GT cutoff. The cutoff of 0.10 GT used for estimating the Mineral Resources for the open pit areas is the same cutoff value as that used for estimating the Mineral Reserves at a $60/lb. uranium price. The cutoff of 0.30 GT used for estimating the Mineral Resources for Sheep Underground is lower than the 0.45 GT cutoff used for estimating the Mineral Reserves at a $60/lb. uranium price. Some of the Mineral Resources fall outside of the mine plan, whereas all of the Mineral Reserves fall within the mine plan. Those portions of the mineral resource outside the current mine plans which do not demonstrate reasonable prospects for eventual economic extraction have been removed from the mineral resource estimate in compliance with current 43-101 regulations and CIM guidance.

#### Mineral Reserves

The estimate of mineral reserves for the Sheep underground extraction area is set out in the Sheep Mountain Technical Report. With respect to the open pit mineral reserves, mineral resources for the Congo, North Gap, and South Congo areas were combined into a single comprehensive mineral resource model. Open pit mine designs and sequencing was completed for all areas, and the resultant mineral reserve estimate reflects the current open pit mine designs and economic evaluations. These reserves have been calculated in accordance with NI 43-101 and should not be considered to meet the definition of “reserves” within the meaning of SEC Industry Guide 7. Resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

Below is a summary of the total Probable Mineral Reserve estimate for the Sheep Mountain Project as calculated in accordance with NI 43-101:

#### Sheep Mountain Mineral Reserves – Uranium(1)(2)(3)(4)(5)

| Classification Zone G.T. Cut-off Sheep Mountain Proven Reserves --- --- | Tons (000) --- | Grade % eU3O8 --- | Pounds eU3O8 (000) --- |
| --- | ---: | ---: | ---: |
| Sheep Mountain Probable Reserves Open Pit 0.1 | 3,955 | 0.115% | 9,117 |
| Underground 0.45 3,498 | 0.132% | 9,248 |  |
| **Total Proven and Probable Reserves** | **7,453** | **0.123%** | **18,365** |

### Notes:

(1) The Mineral Reserve estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7.

(2) Mineral Reserves are estimated at a uranium grade x thickness (G.T.) cut-off grade of 0.10 G.T. (2 ft. of 0.05% eU3O8) for the Congo Pit and 0.45 G.T. (6 ft. of 0.075% eU3O8) for Sheep Underground.

(3) Mineral Reserves are estimated using a long-term uranium price of $60 per pound U3O8.

(4) Numbers may not add due to rounding.

(5) The Mineral Reserves are fully included in the total Mineral Resources shown above.

The Probable Mineral Reserve is that portion of the Indicated Mineral Resource that is economic under the estimated costs and assumed pricing conditions. The cutoff grade of 0.075% eU3O8 at a minimum mining height of 2 foot equates to a 0.10 GT cutoff for the Congo Pit. The cutoff grade of 0.075% eU3O8 at a minimum mining height of 6 feet equals a 0.45 GT cutoff used for the Sheep underground extraction area. The cutoff grade was determined based on an assumed uranium price of $60 per pound U3O8.

#### Present Condition of the Property and Work Completed to Date

The Sheep Mountain Project includes the Congo Pit, a proposed heap leach, and the planned reopening of the existing Sheep Underground mining facility. Mineral Extraction at the Sheep Underground mining facility was suspended in 1988 and the project has been on care and maintenance since that time.

The Sheep Mountain Project does not currently have a processing facility. Transportation of mineralized materials to the White Mesa Mill is not economic at current uranium prices. As a result, it will be necessary to permit and construct a heap leach processing facility at the site or make arrangements to process Sheep Mountain mineralized materials at a third-party processing facility.

The Company is subject to liabilities for mine reclamation at the Sheep Mountain project. The Company maintains a bond in the amount of $950,000 with the State of Wyoming as security for these liabilities. The Company files an annual report with the State of Wyoming, and the amount of the bond may be adjusted annually to ensure sufficient surety is in place to cover the full cost of reclamation. The Company’s reclamation of the exploration drilling performed by Titan was deemed complete in October 2014; the drilling permit was terminated, and that bond was fully released.

The Sheep Mountain Project was acquired by the Company in February 2012, through the Company’s acquisition of Titan. As of December 31, 2020, the total cost attributable to the Sheep Mountain Project on the financial statements of the Company was $34.18 million.

The Company will continue to evaluate its options for processing Sheep Mountain mineralized material, including continuing to pursue permitting for a heap leach facility at the site, or determining whether arrangements can be made to process Sheep Mountain mineralized materials at a third-party processing facility. Submittal of the license application to the WDEQ-LQD for a heap leach processing facility at the site is on hold pending the Company’s evaluation of off-site processing options for this project. The project is currently on standby, pending completion of the evaluation of the processing options for the Project and improvement in market conditions. Additional work is subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions.

### The Henry Mountains Complex

Except as noted below concerning the land and permitting efforts, the following technical and scientific description of the Henry Mountains Complex is based on the technical report dated June 27, 2012 titled “*Technical Report on the Henry Mountains Complex Uranium Property, Utah, U.S.A.,”* prepared by William E. Roscoe, Ph.D., P.Eng., Douglas H. Underhill, Ph.D., C.P.G. and Thomas C. Pool, P.E. of Roscoe Postle Associates Inc. (“**RPA”**) in accordance with NI 43-101 (the “**Henry Mountains Technical Report”**). Each of the authors of the Henry Mountains Technical Report is “independent” of Energy Fuels and a “qualified person” for purposes of NI 43-101. The report contains mineral resource estimates for the Indian Bench, Copper Bench, Southwest and Tony M deposits. The Henry Mountains Technical Report is available on SEDAR at www.sedar.com and on EDGAR at www.sec.gov. The Henry Mountains Complex does not have known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite uranium extraction activities occurring at the Tony M deposits as recently as 2008.

The Henry Mountains Complex is an underground project comprised of the Bullfrog Property, hosting the Indian Bench and the Copper Bench deposits, and the Tony M Property, hosting the Southwest deposit and the Tony M deposit and associated mineral extraction facilities. The Henry Mountains Complex is located in eastern Garfield County, Utah.

Road access to the Henry Mountains Complex is by paved Highway 276, running between Hanksville and Bullfrog Basin Marina, Utah. An unimproved gravel road maintained by Garfield County extends west from Highway 276, passing by the portal of the Tony M Property, and continuing northerly across the property, the northern end of which is crossed by another county road. The property is located in a relatively remote area of Utah with limited infrastructure. The town site of Ticaboo, Utah is located approximately five miles south of the property. Ticaboo has been used to provide housing and municipal services for Tony M Property staff. The next closest community is Hanksville, Utah, a small town of a few hundred people located approximately 40 miles north of the property. During operation of the Tony M Property, electricity was generated locally. Materials and supplies are transported to the site by truck - a drive of approximately 275 miles from Salt Lake City or 190 miles from Grand Junction, Colorado. The distance to the White Mesa Mill from the Tony M Property is approximately 117 miles.

The climate is distinctly arid with an average annual precipitation of approximately eight inches, in addition to approximately12 inches of snow. The vegetation consists primarily of small plants including some major varieties of blackbrush, sagebrush, and rabbit brush. A few small junipers are also present. Relief over the combined Henry Mountains Complex is approximately 2,250 feet (the technical report erroneously reported 800 feet). The elevation on the property ranges from 4,550 feet above sea level at the portal of the Tony M Property, which is near the southern end of the property, to 6,800 feet above sea level at the northern end of the property. The terrain is typical canyon lands topography, with some areas deeply dissected by gullies and headwalls of canyons and the rest consisting of gently undulating gravel benches covering the northern part of the project area. The terrain in several parts of the property is particularly rugged and inaccessible and is the primary reason for the irregular pattern of surface drill holes in parts of the property.

#### Ownership

The Henry Mountains Complex is 100% owned by Energy Fuels and was acquired from Denison Mines Corp. and its affiliates in June 2012. The project consists of one Utah State Mineral Lease for Section 16, Township 35 South, Range 11 East (T35S R11E), Salt Lake Meridian (“**SLM”**), and 202 unpatented federal lode mining claims. The latter consist of 137 B.F., 19 Bull, 19 Star, two Frog claims (comprising the Bullfrog Property), and 17 TIC and eight Ticaboo claims, including fractions (comprising the Tony M property). The claims and state lease comprise one contiguous property located in T34S, R11E and T35S, R11E, SLM. The Utah State Section 16 includes 638.54 acres, and the 202 unpatented lode mining claims consist of about 3,667.18 acres (not specified in the technical report), for a total land holding of 4,305.72 acres. The surface rights are owned by the federal government, administered by the BLM, with the exception of the State lease, which has associated state surface rights.

There is no royalty burden for the 185 claims that comprise the Bullfrog Property, as well as for the Ticaboo claims. All unpatented mining claims are subject to an annual federal mining claim maintenance fee of $165 per claim plus approximately $10 per claim for county filing fees. The 17 TIC claims are held by Energy Fuels, subject to an annual advance minimum royalty. The uranium production royalty burden is 4% yellowcake gross value less taxes and certain other deductions. The vanadium production royalty burden is 2% gross value less certain deductions. The Utah State Lease carries an annual rental of $640, plus an escalating annual advance minimum royalty based on the uranium spot price. Since the technical report was written, the State lease was renewed in 2015 for an additional 10-year term, which can be extended. Other changes in the renewed lease include reducing annual advanced royalty payments and crediting the advanced royalty against the production royalty for the year in which it is paid plus any amount paid in the five prior years. The uranium royalty on the State lease is 8% of gross value less certain deductions. The vanadium royalty on the State lease is 4% of gross value less certain deductions.

#### Permitting

Tony M Property:

The original Tony M Property mine permit was allowed to lapse. Subsequently the previous operator, Denison, filed for exploration permits with the Utah Division of Oil, Gas and Mining (“**UDOGM”**) and the BLM. These permits were granted by UDOGM and the BLM on December 2, 2005 and March 6, 2006, respectively, which enabled Denison to regain access, inspect and begin rehabilitation of the Tony M underground workings. Denison also began the permitting process for the Tony M Property. The permit application was submitted in November 2006 and a RoD and approved PO were received in September 2007.

The PO was challenged by the Center for Water Advocacy and the Utah Chapter of the Sierra Club, which requested a Utah State BLM Director Review and a stay of the decision approving the Final PO for the Tony M Property. On November 21, 2007, the BLM State Director issued a decision vacating the previously issued permit and remanded the case to the Field Office in order that the EA for the Tony M Mine PO could be amended and a new RoD issued. As a result of this decision to vacate and renew, the request for stay was considered moot. The new decision was issued by the BLM on November 23, 2007 approving the PO for the project. The new decision was once again appealed by the Center for Water Advocacy and the Utah Chapter of the Sierra Club. The Utah State Director issued a decision denying the appeal and upholding the PO on February 19, 2008. In addition to the PO and Finding of No Significant Impact (“**FONSI”**) from the BLM, major permits for the Tony M property include an approved Large Mine permit with UDOGM, and an approved ground water discharge permit with the Utah Division of Water Quality (“**DWQ”**). A reclamation bond of $708,537 is in place.

Permit applications for a Phase 2 expansion were submitted to the BLM and UDOGM in 2008, but Denison subsequently requested that BLM and UDOGM review of the applications be deferred given the market conditions at that time.

Bullfrog Property:

Although the Company has completed initial environmental baseline studies and mine plans for permitting purposes at the Bullfrog Property, the submittal of permit applications has been deferred pending more favorable market conditions.

#### Geologic Setting

Exposed rocks in the project area are Jurassic and Cretaceous in age. Host rocks for the Copper Bench-Indian Bench and Tony M-Southwest uranium-vanadium deposits are Upper Jurassic sandstones of the Salt Wash Member of the Morrison Formation. This formation is located within the Colorado Plateau. Early Tertiary fluvial and lacustrine sedimentation within the deeper parts of local basins was followed in mid-Tertiary time by laccolithic intrusion and extensive volcanism. Intrusions of diorite and monazite porphyry penetrated the sediments at several sites to form the laccolithic mountains of the central Colorado Plateau.

The Morrison Formation is a complex fluvial deposit of Late Jurassic age. In outcrop, the Salt Wash is exposed as one or more massive, ledge-forming sandstones, generally interbedded with laterally persistent siltstones or mudstones. The lower Salt Wash is approximately 150 feet thick in the Project area, thinning and becoming less sandy northward from the project area. Sandstones comprise 80% of the sequence, with siltstones and mudstones making up the remainder. Significant uranium mineralization occurs only in this lower unit.

#### History

In 1970 and 1971, Rioamex Corporation conducted a 40-hole drilling program in an east-west zone extending across the southerly end of the Bullfrog Property and the northerly end of the Tony M and adjacent Frank M properties. Some of these holes intercepted significant uranium mineralization. The Bullfrog deposit was initially explored by Exxon Minerals Company (“**Exxon”**), while the Tony M deposit was explored and advanced by Plateau Resources Ltd. (“**Plateau”**), a subsidiary of Consumers Power Company (“**Consumers”**) of Michigan.

In February 1977, drilling commenced in what was to become the Tony M deposit. Subsequently, Plateau drilled more than 2,000 rotary drill holes totaling about 1,000,000 feet. Over 1,200 holes were drilled in the Tony M area. Following the discovery of the Tony M deposit in 1977, Plateau developed the Tony M Property from September 1, 1977, to about May 1984, at which time mining activities were suspended. By January 31, 1983, over 18 miles of underground workings were developed at the Tony M Property, and a total of approximately 237,000 tons of mineralized material was extracted with an average grade of 0.121% U3O8 containing about 573,500 pounds U3O8. The underground workings at the Tony M Property are accessed via two parallel declines extending about 10,200 ft. into the deposit. The underground workings were allowed to flood after mining activities were suspended in 1984. The southern one-half of the underground workings remained dry, as they are located above the static water table.

Exxon commenced drilling on the Bullfrog Property in 1977. Before it sold the property to Atlas in July 1982, Exxon had drilled 1,782 holes. From July 1982 to July 1983, Atlas completed 112 drill holes delineating the Southwest and Copper Bench deposits on approximately 100-foot centers. After July 1983, Atlas completed an additional 49 core hole drilling program throughout the Bullfrog Property, as well as a 133 rotary drill hole program to delineate the Indian Bench deposit on approximately 200-foot centers. In total, 2,232 drill holes were completed on the Bullfrog Property.

The Southwest and Copper Bench deposits are delineated by drilling on approximately 125-foot centers. The Indian Bench deposit is delineated by drilling on approximately 200-foot centers. In some areas, the rugged terrain made access difficult, resulting in an irregular drill pattern. Records indicate that 81 core holes were drilled in the Southwest, Copper Bench, and Indian Bench deposits, while 25 core holes were drilled in the vicinity of the Tony M deposit. The core holes provided samples of the mineralized zone for chemical and amenability testing.

Denison acquired the Bullfrog Property when it purchased most of the assets of EFN in 1997. In February 2005, Denison acquired the Tony M Property bringing it under common ownership with the Bullfrog Property. Following rehabilitation work at the Tony M Property and re-establishment of surface facilities in 2006, Denison received operational permits, reopened the Tony M underground workings and commenced mining activities in September 2007. This work included a long-hole drilling program to discover and delineate mineralization within about 100 feet of underground workings. In November 2008, Denison announced that mining activities at the Tony M Property would be suspended due to uranium and economic market conditions. During its September 2007 to December 2008 reactivation, cleanup and mining activities, Denison extracted 162,384 tons of mineralized material at radiometric grade of 0.131% containing 429,112 pounds U3O8 from within existing workings and from the previously stockpiled material. This material was trucked to the White Mesa Mill for processing. In June 2012, Energy Fuels acquired all of Denison’s uranium properties in the United States, including the Henry Mountains Complex.

No mine development has been conducted on the Southwest portion of the Tony M-Southwest deposit or on the Copper Bench-Indian Bench deposit located further north. Energy Fuels has carried out no exploration work on the Henry Mountains Complex.

#### Mineralization

Uranium mineralization in the Henry Mountains Complex is hosted by favorable sandstone horizons containing detrital organic debris. Mineralization primarily consists of coffinite, with minor uraninite, which usually occurs in close association with vanadium mineralization. Mineralization occurs as intergranular disseminations, as well as coatings and/or cement on and between sand grains and organic debris. Vanadium occurs as montroseite (hydrous vanadium oxide) and vanadium chlorite in primary mineralized zones located below the water table (i.e., the northernmost portion of the Tony M deposit). Historic production records from the AEC for the South Henry Mountains district suggest that the vanadium content of the district is relatively low. Based on the review of the available analyses, RPA is of the opinion that the V2O5:U3O8 ratio ranges from about 1.3:1 to about 2.0:1 in the Henry Mountains Complex deposits.

The Henry Mountains Complex vanadium-uranium deposits consist of two extensive elongate, tabular zones containing a large concentration of mineralization. The Tony M–Southwest deposit extends for a distance of approximately 2.5 miles along a north-south trend and has a maximum width of approximately 3,000 feet. The larger Copper Bench-Indian Bench deposit extends approximately 3.5 miles along a northwesterly trend to the northeast of the Tony M–Southwest deposit.

#### Mineral Resource Estimates

Denison estimated the Mineral Resources of the Tony M-Southwest deposit in 2009 using the GT contour method, and EFN estimated the Mineral Resources of the Copper Bench-Indian Bench deposit in 1993 by EFN using the polygonal block method. These Mineral Resources are not Reserves within the meaning of SEC Industry Guide 7.

#### Henry Mountains Complex Mineral Resources – Uranium(1)(2)(3)(4)

| Classification Zone Henry Mountains Measured Resources (M) --- | Tons (000) --- | Grade % eU3O8 --- | Pounds eU3O8 (000) --- |
| --- | ---: | ---: | ---: |
| Henry Mountains Indicated Resources (I) Tony M(2) | 1,030 | 0.24% | 4,830 |
| Southwest(2) 660 | 0.25% | 3,300 |  |
| Indian Bench(3) 220 | 0.40% | 1,740 |  |
| Copper Bench(3) 500 | 0.29% | 2,930 |  |
| **Total (M & I)** | **2,410** | **0.27%** | **12,800** |
| Henry Mountains Inferred Resources Tony M(2) | 650 | 0.17% | 2,170 |
| Southwest(2) 210 | 0.14% | 580 |  |
| Indian Bench(3) 250 | 0.42% | 2,090 |  |
| Copper Bench(3) 500 | 0.32% | 3,240 |  |
| **Total Inferred Resources** | **1,610** | **0.25%** | **8,080** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101 and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources for Tony M and Southwest are estimated at a uranium grade x thickness (G.T.) cut-off of 0.20 G.T. (2 ft. of 0.10% eU3O8). This cut-off is estimated using a long-term uranium price of $60 per pound U3O8.

(3) Mineral Resources for Indian Bench and Copper Bench are estimated at a uranium grade x thickness (G.T.) cut-off grade 0.80 G.T. (4 ft. of 0.20% eU3O8). This cut-off is estimated using a long-term uranium price of $40 per pound U3O8.

(4) Numbers may not add due to rounding.

The EFN resource estimate was audited by RPA and accepted as a current Mineral Resource estimate for Energy Fuels under NI 43-101 requirements.

#### Present Condition of the Property and Work Completed to Date

The following section has been prepared by the Company and is not based exclusively on the Henry Mountains Technical Report.

The Tony M Property was developed from 1977 to 1983 with a double entry system including two parallel declines spaced 50 feet apart. The declines measure 9 feet by 12 feet in cross- section, have crosscuts on 50-foot centers, have a minus 3% grade, serve as the primary fresh air intake, and are 10,200 feet in length. By January 31, 1983, over 18 miles of underground workings had been developed at the Tony M Property. The underground workings were allowed to flood after mining activities were suspended in 1984. The southern one-half of the underground workings remained dry, as they are located above the static water table.

The underground workings were planned as a random room and pillar approach with pillar extraction by a retreat system. Mining equipment consisted of slushers and rubber-tired, five- to ten-ton capacity load-haul-dump units. Exhaust ventilation was provided by five bored ventilation shafts, six feet in diameter, each with a 75-HP exhaust fan mounted at the shaft collar.

By early 2007, work on reactivating the Tony M Property was carried out by Denison, and surface and underground rehabilitation and repairs were conducted. Surface facilities to support mining activities were constructed, including administration and maintenance facilities, site power and communications, and an evaporation pond for evaporation of water from the underground workings. Worker housing was established in the town of Ticaboo, Utah. As rehabilitation work advanced, ventilation was re-established. The water level in the underground workings rose to historic pre-mining activity levels, and upon reaching the flooded workings, dewatering activities were also initiated. During the rehabilitation work, limited amounts of “cleanup mineralized material” were removed. As areas of the underground workings were made ready for mining activities, extraction of mineralized materials increased steadily. Dewatering continued at an average rate of 125 gallons per minute during these activities. Denison placed the Tony M Property on temporary closure status at the end of November 2008, and dewatering activities ceased. The project is being maintained in a state ready to resume operations as market conditions warrant. All Company housing and property in Ticaboo have been sold by Energy Fuels.

There is no existing infrastructure on the Bullfrog Property.

The Henry Mountains Complex was acquired by the Company in June 2012, through the acquisition of the U.S. Mining Division from Denison. The cost of the Henry Mountains Complex has been fully impaired, and as of December 31, 2020, the total cost attributable to the Henry Mountains Complex and its associated equipment on the financial statements of the Company was nil.

During 2021, the Company is conducting care and maintenance activities at the Tony M property in order to maintain it on standby. No work is planned for the Bullfrog (Indian and Copper Bench) portions of the Henry Mountains Project. Additional work is subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions.

### The La Sal Project

Unless otherwise stated concerning land tenure, permitting efforts, and La Sal Project activities in 2018-2019, the following technical and scientific description of the La Sal Project is derived from a technical report titled “*Technical Report on La Sal District Project (Including the Pandora, Beaver, and Energy Queen Projects), San Juan County, Utah, U.S.A.,”* dated March 25, 2014, prepared by Douglas C. Peters, CPG, of Peters Geosciences, in accordance with NI 43-101 (the “**La Sal Technical Report”**). The La Sal Technical Report includes an updated NI 43-101 compliant Mineral Resource estimate. The author of the La Sal Technical Report is a “qualified person” and “independent” of the Company within the meaning of NI 43-101. A copy of the La Sal Technical Report is available on SEDAR at www.sedar.com and on EDGAR at www.sec.gov. The La Sal Project does not have known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite uranium extraction activities occurring as recently as 2012.

#### Project Description & Location

The La Sal Project is an underground project that consists of four mineral properties within close proximity of one another, including (from east-to-west) the Pandora (Snowball) Property, the Beaver (La Sal) Property, the Redd Block Property, and the Energy Queen Property. The La Sal Project is located in San Juan County, Utah near the town of La Sal. Other properties within the La Sal Project (but not described in the La Sal Technical Report) include the Pine Ridge property, east of the Pandora property, and unpatented mining claims west of the Energy Queen Property.

The La Sal trend, which includes the La Sal Project, has a long history of uranium and vanadium production. Deposits from this district have been successfully milled at several historic mills in the region including Union Carbide’s mill at Uravan, Colorado (through its subsidiary Umetco Minerals Corporation, the Climax Uranium Mill in Grand Junction, Colorado, the Atlas Mill at Moab, Utah and Energy Fuels’ White Mesa Mill near Blanding, Utah.

Commercial operations at the La Sal Project are currently on standby. Shallower mineral resources are accessed via the La Sal and Pandora declines, while the deeper resources are accessed via the Beaver and Energy Queen Shafts. The resource is mined utilizing split-shooting and random room and pillar mining methods, which have proven successful within the La Sal Complex over the last 40 years, and regionally over the last 70. Split-shooting is used because the Salt Wash deposits are typically thinner than the minimum underground height needed for personnel and equipment access. The split-shooting mining method allows for mineralized material and waste material to be mined separately.

The La Sal Project is easily accessed from the all-weather Utah State Highway 46. Utah 46 enters the project land near the southwest corner of ML-49313 (Section 36, T28S, R24E) about three miles east of the intersection of Utah 46 with U.S. Highway 191 at La Sal Junction. Utah 46 stays within or very near the project land for the next 9 miles to the east. All State and U.S. highways in this area are paved roads.

The area is semi-arid. Temperatures range between an average low of 41°F to an average high of 72°F. Less than ten inches of precipitation falls per year. Winters are not severe, although there are numerous snowstorms, the temperature drops below 0°F at times, and snow can accumulate to over a foot in the lower areas and more than two feet at times on Pine Ridge. The region of the La Sal Project central area is characterized by a broad shallow valley of hay fields and pasture lands at an elevation between 6,400 and 7,000 feet. Hills cut by small canyons occur at the west end and even higher elevations of about 7,800 feet are reached at Pine Ridge on the east end. All elevations within four miles of the center and west end of the property support moderate growths of sage and rabbitbrush along with other brush, forbs, cactus, yucca, and grasses. Higher elevations contain juniper and piñon pine in the rocky soils along with scrub oak, aspen, and Ponderosa pine on Pine Ridge to the east.

La Sal, Utah is a small town, currently home to about 200 people. It has been a hub to area ranchers, uranium and copper miners, and oil and gas workers for many years. Larger population centers of Moab and Monticello, Utah are 22 miles north and 34 miles south, respectively, from La Sal Junction on Highway 191. Before the cessation of mining activities at the Beaver and Pandora Properties in late 2012, many of the workers also came from the Nucla-Naturita and the Dove Creek areas of Colorado, each about 55 miles away to the east and south, respectively. Larger cities with industrial supply houses include Cortez, Colorado about 100 miles to the south and Grand Junction, Colorado about 140 miles to the north.

Electric transmission and distribution lines exist throughout the project area, of sufficient size to supply the load the projects demanded in the past. Several substations exist, and the electricity supply is adequate for additional demand. Natural gas is also available for any future production needs.

#### Ownership

The La Sal Project is held by Energy Fuels’ subsidiary, EFR Colorado Plateau LLC, under private surface use and access leases, private mineral leases, Utah State Mineral Leases, San Juan County surface use, access and mineral leases. The Company currently owns or controls 209 unpatented mining claims on land managed by the BLM or USFS that are either owned by Energy Fuels (80 claims) or leased by Energy Fuels (129 claims) remain. The total land package now consists of approximately 9,450 acres. The unpatented claims cover about 3,350 acres, the seven Utah State leases total approximately 2,182 acres, the San Juan County leased land contains just over 263 acres, and the six separate surface access and nine private parcel mineral leases apply to a total of 3,655 acres. The property covers all, or parts of the following Sections: Sections 31, 32, and 33, T28S, R25E; Sections 4, 5, 6, and 7, T29S, R25E; Sections 25, 26, 31, 32, 33, 34, 35, and 36, T28S, R24E; Sections 1, 2, 3, 4, 5, 6, 7, 11, and 12, T29S, R24E; Section 36, T28S, R23E; and Sections 1, and 12, T29S, R23E, SLBM, San Juan County, Utah.

Annual holding costs consist of rental fees to the BLM at $165 per year per claim, due on or before September 1st each year. An affidavit of the payment to the BLM must be filed with the appropriate County each year for a nominal fee of about $10 per claim. This applies to all unpatented claims whether owned or leased by Energy Fuels. Annual holding costs for State leases and private leases vary, ranging between $500 and $13,500 for State Leases and $480 and $29,000 for private leases. The Company is also required to pay production royalties at varying rates for unpatented mining claims and private leases. The Utah State production royalties are fixed at 8% on uranium and 4% on vanadium.

The Company generally has entered into surface access agreements sufficient to allow access for its mining activities.

#### Permitting

Mineral extraction facilities on private and public lands in Utah require an approved Notice of Intent (“**NOI”**) with the UDOGM. If the facility generates water, a ground water discharge permit is required for the treatment plant and ponds, and a surface water discharge permit is required for discharge of treated water. Both permits are issued through the DWQ. Air permits for air emissions including radon are issued by the Utah Division of Air Quality (“**UDAQ”**). Water well permits, water rights, and stream alteration permits are also issued through the DWQ. On federal land, all the state permits listed above are required, as well as a Plan of Operations approved through a NEPA review by the responsible federal land managing agency.

The Company’s mineral facilities at the La Sal Project are all existing facilities in historic mining areas, and approvals by the BLM and USFS have been obtained under EAs and FONSIs under NEPA. The Energy Queen and Redd Block IV Properties are located on private land and were permitted with UDOGM in the early 1980s by Union Carbide. The Energy Queen Property was developed and has conducted mineral extraction, but the Redd Block IV Property was discontinued soon after the start of construction. A mine and reclamation plan amendment for the Energy Queen Property was approved by the UDOGM on September 22, 2009. This amendment allows the Company to install water treatment and other new surface facilities to support extraction of up to 250 tons per day of mineralized materials. Water discharge permits to allow initial and ongoing discharge of water from underground workings were also approved by the DWQ in 2009 and renewed most recently in 2018. Energy Fuels initiated permitting plans for additional facility expansion in 2012, but then deferred these plans when the Redd Block IV resource was acquired in the Denison acquisition. As market conditions may warrant, the Company intends to perform engineering studies to determine if the Redd Block IV resource can be extracted from the Energy Queen shaft and surface facilities. If this proves to be the case, the Energy Queen UDOGM permit would be updated to include the Redd Block IV area as well as other resources that have been acquired since the 2009 amendment. A Small Source Exemption that is in place for air emissions would also need to be replaced with an air permit because of the increased surface disturbance.

Existing mining operations at the Pandora, Beaver, La Sal and Snowball Properties are fully permitted with the State of Utah, the BLM, and the USFS. In order to allow expansion of the existing mines, Energy Fuels has obtained regulatory approvals for expansion of the Pandora, Beaver, and La Sal operations through the UDOGM, the BLM, and the USFS. In late 2014, an EA, draft

Decision Notice and FONSI were issued for public comment. In March 2015, in response to an objection filed by an environmental interest group, the USFS ruled that additional analysis was required before a modified Plan of Operations and EA could be approved for the proposed expansion. An expanded EA was finalized by the USFS and BLM in September 2017 and forwarded to Washington DC offices of the BLM for approval. On February 23, 2018, the BLM and USFS issued the EA, Decision Record (BLM)/Decision Notice (USFS), and FONSI approving the expansion, conditional upon the Company incorporating certain specific requirements into the Plan of Operations amendment and having the required reclamation bond in place. On September 26, 2018, the USFS approved the Plan of Operations amendment and surety bond. In November 2020, the Large Mine permit expansion was approved through UDOGM. All other regulatory approvals needed for project expansion, including an air emissions permit, are in place.

#### Geologic Setting

The Colorado Plateau covers nearly 130,000 square miles in the Four Corners region of the U.S. The La Sal Project and other properties held by Energy Fuels lie in the Canyon Lands Section in the central and east-central part of the Colorado Plateau in Utah and Colorado. The Colorado Plateau’s basement rocks are mostly Proterozoic metamorphics and igneous intrusions. The area was relatively stable throughout much of the Paleozoic and Mesozoic Eras with minor uplifts, subsidences, and tiltings resulting in fairly flat-lying sedimentary rocks ranging from evaporites, limestones, and marine clastic sediments, through eolian sandstones, to detritus of fluvial systems.

The significant uranium deposits in the La Sal Project occur in the late Jurassic Morrison Formation. The Morrison comprises two members in the La Sal area. The lower member, the Salt Wash, is the main uranium host. The upper part of the Morrison is the Brushy Basin Member; it is from 350 to 450 feet thick. The Salt Wash, approximately 300 feet thick, consists of about equal amounts of fluvial sandstones and mudstones deposited by meandering river systems flowing generally toward the east. The Brushy Basin was deposited mostly on a large mud flat, probably with many lakes and streams. Much of the material deposited to form the Brushy Basin originated from volcanic activity to the west. The majority of the recovered uranium has come from the upper sandstones of the Salt Wash Member known as the Top Rim (historically referred to as the “**ore-bearing sandstone,”** or “**OBSS”**), which ranges from about 60 feet to 100 feet thick.

Light-brown and gray sandstones and conglomerates of the 200-foot thick Cretaceous Burro Canyon Formation overlie the Brushy Basin. These crop out in the eastern part of the La Sal Project (over the Pine Ridge, Pandora, and La Sal/Snowball properties). This formation contains interbedded green and purplish mudstones with a few thin limestone beds. The Burro Canyon Formation is exposed covering the Brushy Basin at the west end of the La Sal Project, on the State sections and claims west of the Energy Queen. Locally, silicification altered the limestones to chert and some of the sandstones to orthoquartzite. Orthoquartzite cobbles and boulders litter the Brushy Basin slopes. In the central part of the La Sal Project (Beaver, Redd Block, and Energy Queen), the Burro Canyon is covered by a layer of alluvium and gravels shed from the La Sal Mountains to the north. These gravels vary in thickness from a thin veneer to over 120 feet thick.

The La Sal District uranium-vanadium deposits are similar to those elsewhere in the Uravan Mineral Belt. Host rocks within the areas surrounding the La Sal Project consist of oxidized sediments of the Morrison Formation, exhibiting red, hematite-rich clastic rocks. Individual deposits are localized in areas of reduced, gray sandstone and gray or green mudstone. The Morrison sediments accumulated as oxidized detritus in the fluvial environment. However, there were isolated environments where reduced conditions existed, such as oxbow lakes and carbon-rich point bars. During early burial and diagenesis, the through-flowing ground water within the large, saturated pile of Salt Wash and Brushy Basin material remained oxidized, thereby transporting uranium in solution. When the uranium-rich waters encountered the zones of trapped reduced waters, the uranium precipitated. Therefore, deposits vary greatly in thickness, grade, size, and shape. Vanadium may have been leached from iron-titanium mineral grains and subsequently deposited along with, or prior, to the uranium.

#### History

Numerous underground mines near located outcrops in the eastern part of the La Sal trend (in the La Sal Creek Canyon District) were mined for vanadium during the early 1900s. Sometime after World War II (approximately 1948-1954), exploration work on Morrison Formation outcrops in the west end of the district resulted in the discovery of the Rattlesnake mine (open pit) two miles west-southwest of the Energy Queen shaft. Deeper deposits of the central La Sal trend (in the area of the La Sal Project) were discovered in the 1960s and developed for production in the 1970s through vertical shafts and declines. The La Sal Project and La Sal Creek District production, through 1980, amounted to about 6,426,000 pounds U3O8 (average grade of 0.32% U3O8) and nearly 29,000,000 pounds V2O5 (average grade of 1.46%). Most production in the district was derived from fluvial sandstones, mainly in the upper part of the Salt Wash Member of the Morrison Formation of Jurassic age.

The Pandora Property was operated by Atlas Minerals in the 1970s and early 1980s. Umetco Minerals (Union Carbide) operated the Snowball, La Sal, and Beaver properties during the same time period. The Energy Queen property, then known as the Hecla Shaft, was started in 1979 by the Union Carbide/Hecla Joint Venture. The Energy Queen stopped mining activities in 1983 due to low uranium prices. GEUMCO (General Electric Uranium Mining Company) operated the Pine Ridge property in the late 1970s, producing from a sandstone lens in the Brushy Basin Member of the Morrison Formation. Pine Ridge was acquired by Minerals Recovery Corporation in 1981, which developed a decline to the Salt Wash Member of the Morrison Formation, but halted mining activities before any significant extraction of mineralized materials. A small project conducted mining activities in the eastern part of Section 2 (ML-49596) during the early 1980s. The amount of uranium extracted from this project is unknown. Low uranium and vanadium prices forced all mining activities throughout the district to cease around 1991. Mineralized materials from these projects have been successfully processed at the Company’s currently operating White Mesa Mill, and the now dismantled Uravan Mill (Umetco) and Moab Mill (Atlas).

Denison (previously named International Uranium Corporation, or “**IUC”**) began mining activities at the Pandora Property in 2006 and later from the Beaver shaft and La Sal decline. From 2007 to 2013, 446,000 tons of mineralized material were mined from the La Sal Complex and processed at the White Mesa Mill. This material had an average grade of 0.20% U3O8 and 1.02% V2O5 and contained 1,774,000 pounds of uranium and 9,098,000 pounds of vanadium.

From 2008 through mid-2012, Denison drilled 225 exploration and infill (confirmation) holes in the project area. Energy Fuels drilled another 27 holes on the Energy Queen Property and the State land to the northwest of the Energy Queen Property from 2007 through 2012. Due to declining uranium prices, mining activities ceased in October 2012 at the Beaver/La Sal Property and in December 2012 at the Pandora Property. Both projects were put on a standby status and are currently maintained in conditions that would allow them to be placed back into production within a few months’ time.

In 2018, the La Sal Decline was rehabilitated. Also, a test-mining program was started in October 2018 to determine the effectiveness of hand-held x-ray fluorescence (“**XRF”**) assays for vanadium grade control. Test-mining began in the La Sal/Beaver portion of the project area and progressed into the Pandora mine. In total, approximately 12,000 tons of ore were mined and vanadium grade control using XRF technology was confirmed. Confirmation was done by comparing the XRF results to chemical assays. The program also included the rehabilitation of significant portions of the La Sal and Pandora mines to access areas included in the test-mining program.

The Company owns the data on over 4,500 surface and underground drill holes within the boundary of the property held as the La Sal Project.

#### Mineralization

The uranium- and vanadium-bearing minerals occur as fine-grained coatings on the detrital grains, filling pore spaces between sand grains, and replacing some carbonaceous material and detrital quartz and feldspar grains. The primary uranium mineral is uraninite (pitchblende) (“**UO2”**) with minor amounts of coffinite (“**USiO4OH”**). Montroseite (“**VOOH”**) is the primary vanadium mineral, along with vanadium clays and hydromica. Traces of metallic sulfides occur. In outcrops and shallow oxidized areas of older mines in the surrounding areas, the minerals now exposed are the calcium and potassium uranyl vanadates, tyuyamunite, and carnotite.

Some stoping areas in the Beaver/La Sal and Pandora/Snowball Properties are well over 1,000 feet long and several hundred feet wide. The Indicated Mineral Resources of the Redd Block and Energy Queen Properties identified through drilling are of similar size. Individual mineralized beds vary from several inches to over 6 feet in thickness. Throughout much of the La Sal district there are three horizons in the Top Rim that host the mineralization, which are 25-40 feet apart.

Kovschak and Nylund (1981) report no apparent disequilibrium problems in the other mining episodes of the La Sal area. Mining activities and milling by Denison and Energy Fuels shows that well-calibrated gamma probes equate well to the mill head grades indicating no significant disequilibrium exists. This is generally true of the Salt Wash uranium deposits due to the age of the mineralization and the hydrologic history of the host rocks. Therefore, Energy Fuels has no reason to anticipate any disequilibrium conditions within the unmined portions of the deposits on the project property.

#### Mineral Resources Estimates

Since the La Sal Project covers a length of ten miles and includes several project sites and facilities, the La Sal Project was divided into four blocks: Pandora, Beaver/La Sal, Redd Block and Energy Queen. The mineral resource estimation for the La Sal Project is based on the gamma logs from 1,993 historic rotary drill and core holes, 247 holes drilled by Energy Fuels and Denison from 2007 to 2012, and approximately 500 underground long holes. Mineral Resource estimates have been calculated using a modified polygonal method. The mineralization in the La Sal Project is interpreted as being hosted in the Top Rim sandstone of the Salt Wash Member of the Morison Formation. Total thickness of the host sandstone is between 60 and 100 feet.

#### La Sal Mineral Resources – Uranium and Vanadium(1)(2)(3)(4)(5)

| Classification Zone | Tons (000) | Grade % eU3O8 | Pounds eU3O8 (000) | Grade % V2O5 | Pounds V2O5 (000) |
| --- | ---: | ---: | ---: | ---: | ---: |
| La Sal Measured Resources (M) Energy Queen | 262 | 0.19% | 971 | 0.97% | 5,100 |
| Redd Block 336 | 0.19% | 1,260 | 0.98% | 6,615 |  |
| Beaver/La Sal 215 | 0.19% | 800 | 0.98% | 4,199 |  |
| Pandora 196 | 0.18% | 701 | 0.94% | 3,682 |  |
| La Sal Indicated Resources (I) Energy Queen | 81 | 0.17% | 268 | 0.87% | 1,409 |
| Redd Block 35 | 0.07% | 47 | 0.35% | 249 |  |
| Beaver/La Sal 9 | 0.18% | 33 | 0.96% | 173 |  |
| Pandora 7 | 0.14% | 19 | 0.73% | 99 |  |
| **Total (M & I)** | **1,142** | **0.18%** | **4,100** | **0.94%** | **21,525** |
| La Sal Inferred Resources Energy Queen | 43 | 0.09% | 79 | 0.48% | 417 |
| Redd Block 95 | 0.09% | 171 | 0.47% | 900 |  |
| Beaver/La Sal 29 | 0.11% | 67 | 0.60% | 352 |  |
| Pandora 18 | 0.12% | 44 | 0.66% | 232 |  |
| **Total Inferred Resources** | **185** | **0.10%** | **362** | **0.51%** | **1,902** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources are estimated at a uranium grade x thickness (G.T.) cut-off of 0.20 G.T. (2 ft. of 0.10% eU3O8).

(3) Mineral Resources are estimated using a long-term uranium price of $65 per pound U3O8 and a vanadium price of $6.50 per pound V2O5.

(4) The average V2O5:U3O8 ratio used for estimating the vanadium Mineral Resources is 5.25:1. This value was based on historical milling of the mineralized material at White Mesa Mill.

(5) Numbers may not add due to rounding.

#### Present Condition of the Property and Work Completed to Date

Permanent structures existing at the Energy Queen Property include the head frame and a metal building containing an office, shop, showers, warehouse, and the hoist. The compressor is located in a separate building. One cased vertical ventilation hole was established into the underground working level. A small water treatment building and settling ponds are located on the San Juan County land in Section 5. In the past, water was treated with barium chloride to remove radium.

The Beaver and La Sal Properties are accessed through the La Sal decline with rubber-tired equipment. The principal shop, offices, and warehouse facilities used by all properties in the district are housed at the surface facilities of the La Sal decline. There are large fenced-in yards, as well as buildings for equipment and supply storage. It is used as a central receiving site for bulk and large orders, which are then distributed to the other Energy Fuels’ properties in the district and other parts of the region. The shop areas include facilities specific to electrical equipment, drills, mobile diesel equipment, and welding. Engineering, geology, safety, environmental, and supervisory and clerk offices are also located near the La Sal decline, in addition to staff and underground crew’s dry rooms. Ample stockpile space is available for easy truck load-out for transporting mineralized material to the White Mesa Mill. Electrical lines and substations exist and are adequately sized for any future extraction potential of the Mineral Resources. The Beaver and La Sal Properties are dry, so no water treatment facilities are needed.

The surface infrastructure at the Beaver shaft location consists of the hoist house, hoist, and head frame. The shaft is 690 feet deep to the underground haulage level and 750 feet in total depth. There are three loading pockets, two of 70-ton capacity and one of 90-ton capacity. This arrangement allows for separation of mineralized material and waste. The skips dump into a surface bin from which the mineralized material is trucked a short distance to a stockpile and subsequently loaded into highway trucks for haulage to the White Mesa Mill. The shaft conveyance system is certified for man trips, although the routine access for personnel is through the La Sal decline. Another building houses the compressors, which supply compressed air for the underground workings in the Beaver Project. Power lines and substations are in place. The Beaver Property is dry underground; therefore, no water treatment facilities exist.

Access into the Pandora Property is through a decline with rubber-tired equipment. Surface facilities here are less than at the other projects. They consist of a small office and shop buildings. A third building is used for storage of materials and equipment. Power lines exist to the property with enough capacity for the required load of potential future mining activities. The Pandora Property is dry underground.

In 1980, Umetco planned to sink another shaft to access the Redd Block Mineral Resources. The project did not progress far due to low uranium prices. The infrastructure at the Redd Block Property associated with a possible new shaft consists of a cleared and leveled site large enough for future construction of all surface facilities needed to support the mining operation. The power line and transformers are installed, and the concrete base for a compressor building has been poured. As mining activities progress, the water table in the Salt Wash sandstone host horizon will be encountered between the west side of the Beaver Property and the east end of the Redd Block area. Seven monitor wells were installed by Denison around this proposed shaft site.

Five surety bonds, totaling $1,186,700 have been posted with regulatory authorities to secure reclamation at the various project facilities.

Starting in April 2018, the Company began a process to rehabilitate the La Sal Complex so that it would be ready to go back into production as market conditions warrant. Work completed between April 2018 and December 2019, when the mine was placed back into standby status, included rehabilitating both the La Sal and Pandora declines, rehabilitating main haulage ways and working areas, unplugging and lining a vent raise, and mining approximately 12,000 tons of mineralized material as part of a test-mining program. Additionally, 30 surface exploration drill holes and 5,200 feet of underground core were drilled between January and May 2019. Of the 30 surface drill holes, 6 intercepted relatively high-grade mineralization. High-grade intercepts are given in the table below.

| Hole No. | Intercept Length (ft.) | Uranium Avg. Grade (%U3O8) | Uranium GT (Grade x Thickness) | Vanadium Avg. Grade (%V2O5) | Ratio (V2O5:U3O8) |
| --- | ---: | ---: | ---: | ---: | --- |
| LS-2019-002 | 2.5 | 0.452 | 1.13 | 4.835 | 10.7:1 |
| LS-2019-004 | 3.5 | 0.322 | 1.13 | 2.738 | 8.5:1 |
| LS-2019-005 | 2 | 0.261 | 0.52 | 0.223 | 0.9:1 |
| LS-2019-014 | 2 | 0.067 | 0.13 | 1.583 | 23.6:1 |
| LS-2019-029(1) | 5.5 | 0.221 | 1.22 | N/A | N/A |

### Notes:

(1) No core was recovered from hole LS-2019-029 and therefore a vanadium grade is not available. The %U3O8 grade given is an equivalent U3O8 grade (%eU3O8) and is calculated from a downhole gamma probe and not chemical assay.

Note that the 12,000 tons mined has not yet been processed and has not been deducted from the La Sal resources presented above. The Company considers the quantity too small to be considered material.

The Company acquired the Energy Queen Property in December 2006. The remainder of the La Sal Project was acquired by the Company in June 2012, through the acquisition of the Denison US Mining Division. The cost of the La Sal Project has been fully impaired, and as of December 31, 2020, the total cost attributable to the La Sal Project and its associated equipment on the financial statements of the Company was nil.

Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions, work planned for 2021 includes continuing care and maintenance activities on the properties within the La Sal Project, pending improvements in the uranium and/or vanadium price. Reclamation work at the abandoned Snowball portal is scheduled for the first nine months of 2021.

### The Daneros Project

Unless otherwise stated concerning land tenure and permitting efforts, the following scientific and technical description of the Daneros Project is derived from a technical report titled “*Updated Report on The Daneros Mine Project, San Juan County, Utah, U.S.A.,”* dated March 2, 2018, prepared by Douglas C. Peters, Certified Professional Geologist, of Peters Geosciences, Golden, Colorado (now located in Lakewood, Colorado) in accordance with NI 43-101 (the “**Daneros Mine Technical Report”**). The author of the Daneros Mine Technical Report is a “qualified person” and is “independent” of the Company within the meaning of NI 43-101. The Daneros Mine Technical Report is available on SEDAR at www.sedar.com and on EDGAR at www.sec.gov. The Daneros Project does not have known “reserves” and is therefore considered under SEC Industry Guide 7 definitions to be exploratory in nature, despite uranium extraction occurring as recently as 2012.

#### Project Description and Location

The Daneros Project is an underground project located in the Red Canyon portion of the White Canyon District in San Juan County, Utah, approximately 65 miles west of the White Mesa Mill. The Company holds a 100% interest in various groups of mining claims, including Daneros and adjoining historical sites, which can be developed in conjunction with the Daneros Project.

The previous owner of the Daneros Project, Utah Energy Corporation (“**UEC”**) gathered the necessary environmental data and obtained the approvals to open an underground uranium project in May 2009. UEC commenced active mining activities, including constructing a decline into the main Daneros deposit. The first loads of mineralized material from the Daneros Project were delivered to the White Mesa Mill in December 2009, and a toll milling campaign was conducted in the second half of 2010. The Daneros Project was acquired by the Company in June 2012 along with all of Denison’s U.S. Mining Division. Prior to being placed on standby in October 2012, mineralized material from the Daneros Project was delivered to the White Mesa Mill and processed for Energy Fuels’ account.

The extraction of all resources in the Daneros Project is by conventional underground mining methods, which have been used successfully in the region for over 70 years. Because the Shinarump uranium deposits have irregular shapes and are constrained within several flat or slightly dipping horizons, random room and pillar mining has proven successful in extracting the mineral resource. The use of rubber-tired equipment allows the workers to follow the mineralized material easily in the slight dips and to ramp up or down to the other horizons. The deposit is accessed from the surface through a 450-foot decline at a gradient of -15%. The Shinarump deposits are usually thinner than the underground height needed for personnel and equipment access. Therefore, the mineralized material is extracted by a split-shooting method. The project also employs an underground long-hole exploration drilling program, reaching out as much as 400 feet ahead of and adjacent to the workings, as guided by the project geologist.

The Daneros Project is located 3.3 miles southwest of Fry Canyon, Utah and is accessed via Radium King Road, which is maintained by San Juan County, and located approximately 13 miles south of Utah Highway 95. A series of bulldozed tracks and drill roads provide access throughout the project area, but access to the mesa tops is very limited. Electric power is generated on site. The shipping distance from the Daneros Project to the White Mesa Mill is about 65 miles.

The semi-arid climate of the White Canyon area is characterized by large daily and yearly temperature ranges and total annual precipitation of approximately 10 to 16 inches, mostly as sporadic, intense summer thunderstorms typical of the Colorado Plateau region. Winter snowfall is moderate and rarely stays on the ground very long. Weather conditions pose no impediment to year-round operations.

Apart from previous mining activities, the only commercial land use purposes are cattle grazing and tourism activities, such as hiking and mountain biking. Due to a shortage of water and thin soils, much of the White Canyon area is unsuitable for agriculture.

The project area is remotely located relative to water and power infrastructure. During operations, workers reside primarily in camp trailers in Fry Canyon, or they commute from Blanding, Utah 65-miles to the east. Blanding is a town large enough to host regional industrial activities, including stores and supply houses of sufficient size and inventory to meet most of the needs of an operation the size of the Daneros Project.

The Project is located along a north-south trending canyon, which is a tributary to Red Canyon, also known as Bullseye Canyon. The Red Canyon drainage flows westerly for approximately 25 miles to the Colorado River where it joins Lake Powell at the head of Good Hope Bay. The project portal area comprises steeply sloping, rocky ground and scree along the eastern slope of Bullseye Canyon. Very steep to vertical, and at times overhanging, cliffs 400 feet high rise from the slope about 250 feet above the portal.

Vegetation in the project area consists of sagebrush, juniper and piñon in the hills and slopes, while desert grasses, forbs, and shrubs are evident within the valley floors and on the mesa tops. Elevations in the region range from about 5,300 feet at the Fry Canyon townsite to over 7,000 feet on the surrounding mesa tops. The project portal is at about 5,750 feet above sea level.

#### Ownership

The Daneros Project is owned by the Company’s subsidiary EFR White Canyon Corp. The property consists of 141 unpatented mining claims located on federal land administered by the BLM in San Juan County, Utah, plus the State lease. The total Project area is approximately 3,072 acres. The property lies in Sections 1, (11, and 12 were dropped in 2014) T37S, R15E, SLM, Sections (4 dropped in 2014), 5, 6, 7, 8, (10, 11, 15, 17 dropped in 2014), and 18, T37S, R16E (and Section 31 and 33, T36S, R16E dropped in 2014).

The mining claims are maintained by making annual payments of $165 per claim to the BLM due September 1st each year, along with a nominal filing fee paid to the county within 30 days of the BLM filing of about $10 per claim. Work expenditures are not required. Holders of unpatented mining claims are generally granted surface access to conduct mineral exploration and mining activities. However, additional mine permits and plans are generally required prior to conducting exploration or mining activities on such claims.

A number of the claims bear production royalties. Claims hosting the Daneros deposit are subject to royalties ranging between 15% of “market value” of the mineralized material and 2.5% of gross proceeds as described in further detail in the Daneros Mine Technical report. Other claims are owned by the Company without encumbrances. The State lease carries the standard Utah royalty of 8% on uranium and 4% on vanadium.

Sufficient surface rights are in place for planned mining activities and waste storage. Since no milling activities are contemplated on the Daneros Project, no areas are required for tailings storage, heap leach pads, or processing plant sites.

#### Permitting

The primary permits required for mining activities at the Daneros Project include a mine permit issued by UDOGM and a Plan of Operations (“**PO”**) approved by the BLM under the NEPA review process. UEC submitted a PO for the Daneros Mine in 2008 that proposed a seven-year life of mine with production of up to 100,000 tons of mineralized material within a 4.5-acre disturbed area footprint. In 2012, the BLM issued an EA based on the 2008 PO that was subject to public review and comment. Following approval of the PO, an appeal was filed by Uranium Watch and associated environmental interest groups. The appeal was denied by the Utah BLM State office, then appealed to the Department of Interior Board of Land Appeals (“**IBLA”**) and denied by IBLA in September of 2012.

In early 2013, an amended PO and a Large Mine NOI were submitted to the BLM and UDOGM, respectively. The modified PO would allow production of up to 500,000 tons of mineralized material over a 20-year period and an expansion of the disturbed area footprint to 46 acres. An EA was issued for public comment in July 2016 and finalized by the BLM in late 2016. With the designation of the Bears Ears National Monument (“**BENM”**) in December 2016, the BLM essentially suspended review while they considered if expanded mining operations, now adjacent to the monument, might adversely affect the monument. In September 2017, an updated EA that determined there would be no new impacts to the monument was forwarded to BLM Washington for approval. Since then, the BENM boundaries were modified by Presidential Executive Order, and the Daneros mine would be at least 15 miles from the nearest boundary. The EA, FONSI and PO amendment were issued by BLM on February 23, 2018. Following approval of the modified PO, an appeal was filed by the Grand Canyon Trust and Southern Utah Wilderness Alliance. The appeal is currently being considered by the IBLA.

Daneros was initially permitted by the UDOGM under a Small Mine Permit approved in 2009. The NOI for a Large Mining permit was submitted to UDOGM in early 2013. In 2015, UDOGM concluded its technical and administrative reviews of the application.

Approval of the NOI has been pending BLM approval of the EA and Decision Notice, which were issued on February 23, 2018, subject to certain specified requirements. As a result of the BLM’s approval in 2018, pending a favorable outcome on the ongoing appeal through the IBLA, the Company expects UDOGM approval of the modified PO and Large Mine permit later in 2021.

#### Geological Setting

Major uranium deposits of the east-central Colorado Plateau district occur principally in two fluvial sandstone sequences. The older is located at or near the base of the Upper Triassic Chinle Formation and the other occurs in the Late Jurassic Salt Wash Member of the Morrison Formation. The main uranium-bearing unit at the Daneros Project and throughout the White Canyon district is the fluvial Shinarump Member, a basal, sandstone-conglomerate sequence deposited in a complex stream system, which unconformably overlies and locally scours into oxidized sedimentary units of the Moenkopi Formation.

The Shinarump Member consists of predominantly trough-crossbedded, coarse-grained sandstone and minor gray, carbonaceous mudstone and is interpreted as a valley-fill sequence overlain by deposits of a braided stream system. Uranium mineralization appears to be related to low-energy depositional environments in that uranium is localized in fluvial sandstones that lie beneath organic-rich lacustrine-marsh mudstones and carbonaceous delta-front sediments. The reducing environment preserved in these facies played an important role in the localization of uranium.

Uranium deposits consist of closely-spaced, lenticular mineralized pods which are generally concordant with bedding in paleochannel sediments. Single mineralized pods range from a few feet to a few hundred feet in length and from less than one to more than 10 feet in thickness. Deposits range in size from a few tons to more than 600,000 tons. The Shinarump deposits generally have low vanadium content and are therefore not processed for vanadium.

The uranium deposit at the Daneros Project, like nearly all others in the White Canyon district, is in the lower part of the Shinarump, especially where it has scoured into the Moenkopi. The lithology, facies, sedimentary structures, and locations within the channel deposits were important in controlling the migration of fluids and localization of the deposits. Coarser-grained rock is more favorable than fine-grained sand or silt units. Most of the uranium mineralization overlies the impermeable siltstones of the Moenkopi or local siltstone lenses internal of the Shinarump. The lateral edges of channels where they are bounded by mudstones are also favorable locations for mineralization. Historical production from the White Canyon District exceeds 11 million pounds of U3O8.

#### History

The White Canyon mining district has a long history of exploration and mining. From 1949-1987 production from the district was 2,259,822 tons at an average grade of 0.24% U3O8 for a total of 11,069,032 pounds placing it second, behind Lisbon Valley, for uranium production from the Chinle Formation on the Colorado Plateau.

Exploration for uranium has been going on in the White Canyon area since the late 1940s. Prospectors used Geiger counters to investigate outcrops of the Shinarump Sandstone. Past exploration is closely tied to the AEC buying program, the market price of uranium, and the opening and closing of several processing facilities in the region.

The properties in the Daneros Project area remained idle until 1946. From 1948 until 1951, White Canyon and the nearby Red Canyon and Deer Flat areas were subject to intense exploration. The AEC ore procurement program ended on December 31, 1970, and during the early 1970s minimal production was recorded from the district.

Production from the district increased again by 1974 when the demand for uranium increased due to nuclear power generation. Exploration and production once again increased in the White Canyon District. In 1974, Utah Power and Light Company (“**UP&L”**) began to acquire properties in the White Canyon district, which included a 100% interest in the Spook-Bullseye property and a 60% interest in the Lark-Royal property both located near the Daneros Project in Red Canyon.

Between 1975 and 1985, UP&L conducted several phases of drilling leading to definition of the Lark, Royal, and Bullseye deposits near the modern day Daneros Project. UP&L drilled 595 diamond drill holes with an average depth of 510 feet and, following industry standard procedures, logged all holes using down-hole geophysical (gamma) probes to identify radioactive horizons. Anomalous horizons were sampled and analyzed for uranium.

UP&L never started mining activities in the White Canyon district, due to the collapse of the uranium price by 1982. By 1987, the last mines in the White Canyon district closed due to declining economics, socio-political factors and competition from lower cost producers. Following 1987, the properties were idle, and little or no exploration activity took place in the White Canyon district.

In 1993 UP&L dropped its mining claims in the White Canyon District. In October 1993, Eugene and Merwin Shumway staked the Daneros claims that covered the deposits UP&L had discovered. Eugene and Merwin Shumway quitclaimed their claims to Wilene and Mike Shumway, Terry Leach, and James Lammert in March 1994. No exploration or development took place between 1994 and

2005\. From 2005 to 2007, these individuals began acquiring properties with known historic mineral deposits in the White Canyon district.

In 2007, Utah Commodities Pty, Ltd. who later changed its name to White Canyon Uranium Limited (“**WCUL”**), which operated in the United States through its wholly owned subsidiary, UEC, acquired a 100% interest in the Daneros claims from those individuals.

In December 2008, WCUL purchased 33 additional claims, known as the Lark-Royal Project, an extension of the Daneros Project, from Uranium One.

WCUL began drilling programs in Bullseye Canyon during 2007. The first program drilled 8 holes within the five Daneros claims. A second program in 2008 drilled 16 diamond drill holes and one rotary drill hole. Finally, a third program, also in 2008, drilled 11 diamond drill holes and 9 rotary drill holes. The success of this drilling provided the basis for mineral resource estimates relied upon by WCUL to commence mining activities at the Daneros Project.

The Daneros Project was constructed and uranium bearing material was extracted by WCUL through its subsidiary UEC. WCUL gathered the necessary environmental data and submitted applications for approvals to open an underground facility at Daneros. A PO was submitted to the BLM and was approved in May 2009, following which UEC commenced active construction at the project, including driving a decline into the main deposit at Daneros. The first loads of mineralized material from the Daneros Project were delivered to the White Mesa Mill in December 2009, which was then operated by Denison Mines. In January 2010, Denison entered into a toll milling agreement with UEC, which was then a wholly-owned subsidiary of WCUL.

In 2011, Denison acquired all of the issued and outstanding shares of WCUL, including all shares of UEC. In June 2012, Energy Fuels acquired all of the issued and outstanding shares of WCUL as part of its acquisition of the U.S. Mining Division from Denison, which included the Daneros Project and all of the shares of UEC (now known as EFR White Canyon Corp.). Following the acquisition, the Company kept the project in operation until placing it on standby in October 2012 after the Daneros Project Technical Report was written. Between 2009 and 2013, 121,000 tons of mineralized material, with an average grade of 0.26% U3O8 and containing 629,000 pounds of uranium, were mined at Daneros and processed at the White Mesa Mill.

#### Mineralization

Uraninite (pitchblende) is by far the dominant primary uranium mineral in the Shinarump deposits. It occurs as distinct grains, fine-grained coatings on and pore-fillings between detrital quartz grains, partial replacement of feldspar grains, and as replacement in carbonized wood and other remains of organic matter. Metallic sulfide minerals are often abundant. Where secondary oxidation has occurred, minor amounts of uranyl carbonates, sulfates, and phosphates are found. The source of the uranium is not well established. Overlying shaley units of the Chinle contain clays derived from volcanic ash that is uraniferous. The source area of the arkosic sediments was also a uranium-rich province.

#### Daneros Mineral Resources – Uranium(1)(2)(3)(4)(5)

| Classification Daneros Measured Resources (M) | Tons (000) --- | Grade % eU3O8 --- | Pounds eU3O8 (000) --- |
| --- | ---: | ---: | ---: |
| Daneros Indicated Resources (I) | 20 | 0.36% | 142 |
| **Daneros Total (M & I)** | **20** | **0.36%** | **142** |
| **Daneros Inferred Resources** | **7** | **0.37%** | **52** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources are estimated at a uranium cut-off grade of 0.23% eU3O8.

(3) Mineral Resources are estimated using a long-term uranium price of $55 per pound.

(4) Numbers may not add due to rounding.

(5) This Mineral Resource accounts for all material mined through October 2012, when Daneros was placed on standby.

#### Additional Historical Resources

The Daneros property contains three historical mines, which produced in the early days of mining in the White Canyon District. These mines are the Lark/Bullseye, the Royal and the Spook. An historical resource estimate for the Lark mine was completed by UP&L in 1974. UP&L estimated that the Lark mine contained approximately 45,000 tons at a grade of 0.30% U3O8 for 265,000 pounds of uranium. This historical resource estimate is based on both surface and underground long-hole drilling. Areas of influence are defined by connecting surface holes that are less than 100 feet apart and to the mineralized extent of a long hole.

Peters Geosciences and the Company do not consider this historical resource estimate to be current mineral resources or reserves as defined under NI 43-101. Energy Fuels has reviewed a limited amount of data in connection with this historical estimate. Readers should be cautioned that a qualified person has not done sufficient work to classify this historical estimate to current mineral resource or mineral reserve standards in accordance with NI 43-101. This historical resource estimate was classified as “Indicated Resources.” However, this category was applied without using applicable mining standards and economics and should not be considered reserves by industry definition. The Company believes this historical estimate is relevant and reliable, as the methodology was well documented and utilized industry standard practice at the time. However, the methodologies used do not reflect current best industry practices and, thus, the Company does not consider these historical estimates to be equivalent to current mineral resources or mineral reserves as defined in NI 43-101, nor has the Company completed sufficient work to confirm a NI 43-101 compliant resource. Therefore, the historical estimates cannot, and should not, be relied upon as NI 43-101 resources or reserves.

#### Present Condition of Property and Work Completed to Date

The Daneros Project is fully permitted and constructed. The facilities consist of a modular trailer for the project office, two reinforced portals to access the underground workings, a generator building, and an equipment storage and maintenance building. The deposit is accessed from the surface through a 450-foot-long decline at a gradient of -15%. Two ventilation shafts daylight on the topographic bench above the underground workings.

The Daneros Project was acquired by the Company in June 2012, through the acquisition of the Denison US Mining Division. The cost of the Daneros Project has been fully impaired, and as of December 31, 2020, the total cost attributable to the Daneros Project and its associated equipment on the financial statements of the Company was nil.

The Company has no plans to perform any exploration or development work at Daneros during 2021 and will continue to maintain the Project on standby status. Permit defenses are ongoing as described above. Additional work at Daneros is subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions.

### Non-Material Mineral Properties

This section describes certain non-material mineral properties held by the Company. As these projects are not considered material to the Company’s business, the Company may choose to pursue or to take under consideration the potential sale, joint venture, trade or other transaction involving one or more of these projects.

The Company holds the following non-material mineral properties:

#### Other ISR Projects

The Company’s Properties located in the Powder River Basin, Wyoming, are as follows:

The Company’s properties in the Powder River Basin of Wyoming, but outside of the Nichols Ranch Project, include 12,480 acres owned 100% by the Company through its wholly owned subsidiary, Uranerz. These properties include: the North Rolling Pin Property, the West North Butte Property, the Collins Draw, Willow Creek, East Nichols, North Nichols, Verna Ann, and Niles Ranch properties. The Company, through Uranerz, also holds an 81% interest in the Arkose Joint Venture, which holds 42,952 acres in the Powder River Basin. In May 2018, the Company sold its interest in the Reno Creek property. See Item 1, above.

In general, these ISR projects are located in basins containing sandstones of Tertiary age with known uranium mineralization. Limited exploration was conducted by Uranerz on each project except for Verna Ann and Niles Ranch.

#### Wholly-owned Powder River Basin ISR Mineral Resources

Through its wholly owned subsidiary, Uranerz, the Company owns properties in the Powder River Basin of Wyoming, but outside of the Nichols Ranch Project, comprising a total of 19,801 acres. These properties include: the North Rolling Pin Property, the West North Butte Property, and the Collins Draw, Willow Creek, East Nichols, North Nichols, Verna Ann, and Niles Ranch properties.

The North Rolling Pin property is discussed in the Company’s historical technical report titled, “*Technical Report West North Butte Satellite Properties Campbell County, Wyoming, U.S.A.,”* dated December 9, 2008 and available on SEDAR at www.sedar.com. The West North Butte satellite properties include West North Butte, East North Butte, and Willow Creek, and are described in the Technical Report titled “*Technical Report North Rolling Pin Property Campbell County, Wyoming, U.S.A.”* dated June 4, 2010 and available on SEDAR at www.sedar.com. Neither property is considered material at this time.

Except as noted, the following description of these properties is based on the foregoing technical reports.

#### Wholly-owned Powder River Basin ISR Mineral Resources(1)(2)(3)(4)

| Classification | Property | Tons (000) | Grade % eU3O8 | Pounds eU3O8 (000) |
| --- | --- | ---: | ---: | ---: |
| Powder River Basin Measured Resources (M) | North Rolling Pin | 310 | 0.062% | 387 |
| Powder River Basin Indicated Resources (I) | North Rolling Pin | 272 | 0.051% | 278 |
| West North Butte | 926 | 0.153% | 2,837 |  |
| **Total (M & I)** |  | **1,508** | **0.116%** | **3,502** |
| Powder River Basin Inferred Resources | North Rolling Pin | 39 | 0.042% | 33 |
| West North Butte | 1,117 | 0.120% | 2,682 |  |
| **Total Inferred Resources** |  | **1,156** | **0.117%** | **2,714** |

### Notes:

(1) The Mineral Resource estimate in this table were prepared in accordance with the requirements of NI 43-101 in place as of the publication dates for the above-referenced Technical Reports, and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above. The Technical Reports for West North Butte and North Rolling Pin are considered by the Company to be historical in nature, and have not been updated to incorporate any regulations under NI 43-10 subsequently promulgated, as neither property is considered material to the Company, and no new material scientific or technical information concerning them has become available since the dates originally published.

(2) Mineral Resources are estimated at a uranium grade x thickness (G.T.) of 0.20 G.T.

(3) Mineral Resources are estimated using a long-term uranium price of $65 per pound U3O8.

(4) Numbers may not add due to rounding.

Arkose Joint Venture, Powder River Basin, Wyoming:

The Company, through its wholly owned subsidiary Uranerz, holds an undivided 81% interest in the Arkose Joint Venture, which holds an additional 46,748 acres in the Powder River Basin. Uranerz completed the acquisition of its interest in the Arkose Joint Venture mineral properties on January 15, 2008. This acquisition was completed pursuant to a purchase and sale agreement previously announced on September 19, 2007 between Uranerz, NAMMCO, Steven C. Kirkwood, Robert W. Kirkwood and Stephen L. Payne (collectively, the “**NAMMCO Sellers”).**

In connection with the acquisition of its interest in the Arkose Joint Venture, Uranerz entered into a venture agreement dated January 15, 2008 (the “**Venture Agreement”**) with United Nuclear, LLC (“**United Nuclear”**), a limited liability company wholly owned by the NAMMCO Sellers and their designee under the purchase and sale agreement. Under the Venture Agreement, United Nuclear retained its nineteen percent (19%) working interest in the Arkose Joint Venture, and Uranerz assumed operations and management responsibilities of the Venture. Uranerz and United Nuclear agreed to contribute funds to programs and budgets approved under the Arkose Mining Venture in accordance with their respective interests in the Venture.

The Arkose Mining Venture includes the following property units on which Uranerz has conducted exploration:

- North Jane\*
- South Doughstick
- Cedar Canyon
- East Buck
- South Collins Draw
- Sand Rock
- Little Butte
- Beecher Draw
- Monument
- Stage

\*Now included in the Nichols Ranch Project as part of the Jane Dough Property.

Except as noted, the following description of the Arkose Joint Venture properties is based on a technical report titled “*Arkose Uranium Project Mineral Resource and Exploration Target, 43-101 Technical Report”* dated February 28, 2015, prepared by Douglas L. Beahm, P.E., P.G. of BRS Inc. in accordance with NI 43-101 (the “**Arkose Technical Report”**). Mr. Beahm is a “qualified person” and is “independent” of the Company within the meaning of NI 43-101. The Arkose Technical Report is available on SEDAR at www.sedar.com.

In September 2016, the Arkose Joint Venture elected to forfeit 190 unpatented lode mining claims covering 3,925 acres from its Kermit property and 144 claims covering 2,975 acres from its Lone Bull property, which constitute all of the Arkose claims in those projects. In addition, four mineral leases comprising 592 acres in the East Buck project were allowed to expire in 2016 without attempting to negotiate extensions to those leases. In 2017, mineral leases in the Monument, Cedar Canyon, Sand Rock, East Buck and House Creek projects were allowed to expire; however, the expiry of those property interests did not materially affect the Company's ability to continue exploration and extraction activities on its properties.

The Arkose Joint Venture properties are comprised of unpatented lode mining claims, state leases and fee (private) mineral leases, summarized as follows as of December 31, 2018:

| Property Composition Ownership Interest(1) | Number of Claims/Leases | Acreage (Approximate) |
| --- | ---: | ---: |
| Unpatented Lode Mining Claims 81% | 1,709 | 28,599 |
| State Leases 81% | 1 | 518 |
| Fee (private) Mineral Leases 81% | 7 | 6,256 |
| **TOTAL** | **1,717** | **35,373** |

### Notes:

(1) Subject to royalties.

#### Arkose JV-owned Powder River Basin ISR Mineral Resources (1), (2), (3), (4)

| Classification Property Arkose JV Measured Resources (M) --- Arkose JV Indicated Resources (I) --- Total (M & I) | Tons (000) --- --- --- | Grade % eU3O8 --- --- --- | Pounds eU3O8 (000) --- --- --- | Energy Fuels Pounds eU3O8 (000)(5) --- --- --- |
| --- | ---: | ---: | ---: | ---: |
| Arkose JV Inferred Resources East Buck | 656 | 0.110% | 1.436 | 1,163 |
| Little Butte 1,021 | 0.090% | 1.752 | 1,419 |  |
| Sand Rock 184 | 0.100% | 381 | 309 |  |
| South Doughstick 197 | 0.130% | 497 | 402 |  |
| **Total Inferred Resources** | **2,058** | **0.099%** | **4,066** | **3,293** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent reserves under SEC Industry Guide 7. Mineral resources that are not reserves do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources for the Arkose JV are estimated at a uranium grade x thickness (G.T.) cut-off of 0.20 G.T. (minimum grade of 0.02% eU3O8).

(3) Mineral Resources are estimated using a long-term uranium price of $65 per pound.

(4) Numbers may not add due to rounding.

(5) “**Energy Fuels Pounds”** represent the 81% Company share of the Arkose Mining Venture properties.

#### Other Conventional Projects

#### Arizona Strip

The Pinenut Project has been reclaimed except for a two-acre disturbance associated with a monitor well. Mineral extraction at the Company’s Arizona 1 Project commenced in December 2009 and continued until the project was placed on standby in February 2014 due to the depletion of the readily available resources. The Wate Project and EZ Project are in the evaluation stage. Permitting at the Wate Project and the EZ Project is currently on hold. A description of the Wate Project can be found in the NI 43-101 report titled “*NI 43-101 Technical Report on Resources Wate Uranium Breccia Pipe-Northern Arizona, USA”* dated March 10, 2015, prepared by Allan Moran and Frank A. Daviess of SRK Consulting (U.S.) Inc. and available on www.sedar.com and on EDGAR at www.sec.gov. The EZ Project is described in the technical report titled “*Technical Report on the EZ1 and EZ2 Breccia Pipes, Arizona Strip District, U.S.A.”* dated June 27, 2012, prepared by Christopher Moreton of RPA, among others, and available on www.sedar.com and on EDGAR at www.sec.gov.

#### Other Arizona Strip Properties Mineral Resources – Uranium(1)(4)(5)

| Classification Property Arizona Strip Measured Resources (M) --- Arizona Strip Indicated Resources (I) --- Total (M & I) | Tons (000) --- --- --- | Grade % eU3O8 --- --- --- | Pounds eU3O8 (000) --- --- --- |
| --- | ---: | ---: | ---: |
| Arizona Strip Inferred Resources Wate(2) | 71 | 0.79% | 1,118 |
| EZ1 and EZ2(3) 224 | 0.47% | 2,105 |  |
| **Total Inferred Resources** | **295** | **0.55%** | **3,223** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves”

do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources for Wate are estimated at a uranium cut-off grade of 0.15% eU3O8 and for EZ1 and EZ2 are estimated at a uranium cut-off grade of 0.20% eU3O8.

(3) Mineral Resources for Wate are estimated using a long-term uranium price of $38 per pound U3O8, and for EZ1 and EZ2 are estimated using a long-term uranium price of $53 per pound U3O8.

(4) The Mineral Resources do not include any remaining resources for Arizona 1, because those given in the “*Technical Report on the Arizona Strip Uranium Project, Arizona, U.S.A.”* dated June 27, 2012 do not adequately address changes to the resource as a result of mining and the addition of potential additional mineralization as a result of underground drilling associated with mining activities.

(5) Numbers may not add due to rounding.

#### Colorado Plateau

As a result of declining uranium prices, the Rim property (the “**Rim Property”**) was placed on standby in March 2009, by the previous operator, Denison. The Company has maintained the property such that it can be restarted with relatively little effort or development costs. The Rim Property is located 15 miles northeast of Monticello, Utah in San Juan County. The property consists of 26 unpatented lode mining claims, a private lease, and a Utah State Mineral Lease totaling about 1,100 acres. No exploration is planned for 2021.

The Whirlwind Project comprises 126 unpatented lode mining claims covered by three Mineral Leases and a Utah State Mineral Lease of 320 acres for a total acreage of about 2,800 acres. The property size (as reported in the NI 43-101 report “*Updated Technical Report on Energy Fuels Resources Corporation’s Whirlwind Property (Including Whirlwind, Far West, and Crosswind Claim Groups and Utah Metalliferous Minerals Lease ML-49312) Mesa County, Colorado and Grand County, Utah,”* dated March 15, 2011, prepared by Douglas C. Peters of Peters Geosciences, and available on www.sedar.com) has been reduced since the acquisition. The retained property continues to cover the known mineralized areas that are described in the Technical Report. The Whirlwind Project straddles the Utah/Colorado state line 4.5 miles southwest of Gateway, Colorado. The Whirlwind Project was refurbished by the Company in 2008 and remains on standby status. Exploration drill projects were conducted in 2007, 2008, 2009, 2010, 2011 and 2012. No exploration is planned for 2021. Evaluation of the property in 2019 indicated that the existing decline, rehabilitated in 2008, is in need of some rehabilitation work. Rehabilitation work on the decline has been postponed until market conditions improve.

The Sage Plain Project is a uranium/vanadium property in the evaluation stage. It is located in southeast Utah about 15 miles northeast of Monticello, Utah in the southwest continuation of the Uravan Mineral Belt. The project area includes one historic property, the Calliham Mine, which was operated by Atlas Minerals in the 1980s and briefly by Umetco Minerals Corp. in the early 1990s. The Calliham closed due to low uranium prices. The current Sage Plain landholdings consist of two fee mineral leases covering about 960 acres (Calliham and Crain) and a Utah State lease of 640 acres. A third fee mineral lease (Skidmore) has been terminated since the preparation of the Technical Report “Updated Technical Report on Sage Plain Project (Including the Calliham Mine) San Juan County, Utah, U.S.A.” dated March 18, 2015, prepared by Douglas C. Peters of Peters Geosciences. No exploration is planned for 2021.

#### Other Colorado Plateau Properties Mineral Resources – Uranium and Vanadium(1)(5)

| Classification Property | Tons (000) | Grade % eU3O8 | Pounds eU3O8 (000) | Grade % V2O5 | Pounds V2O5 (000) |
| --- | ---: | ---: | ---: | ---: | ---: |
| Colorado Plateau Measured Resources (M) Sage Plain(2)(4) | 240 | 0.16% | 772 | 1.32% | 6,350 |
| Colorado Plateau Indicated Resources (I) Sage Plain(2)(4) | 13 | 0.10% | 26 | 0.77% | 199 |
| Whirlwind(3) 188 | 0.29% | 1,095 | 0.96% | 3,598 |  |
| **Total (M & I)** | **441** | **0.21%** | **1,894** | **1.15%** | **10,147** |
| Colorado Plateau Inferred Resources Sage Plain(2)(4) | 10 | 0.13% | 25 | 0.94% | 188 |
| Whirlwind(3) 437 | 0.23% | 2,000 | 0.74% | 6,472 |  |
| **Total Inferred Resources** | **447** | **0.23%** | **2,025** | **0.74%** | **6,660** |

### Notes:

(1) The Mineral Resource estimate in this table complies with the requirements of NI 43-101, and the classifications comply with CIM definition standards and do not represent “reserves” under SEC Industry Guide 7. Mineral resources that are not “reserves” do not have demonstrated economic viability. See “*Cautionary Note to United States Investors Concerning Disclosure of Mineral Resources,”* above.

(2) Mineral Resources for Sage Plain are estimated at a uranium cut-off grade of 0.10% eU3O8. This cut-off grade is based on using a long-term uranium price of $63 per pound U3O8 and a vanadium price of $6.75 per pound V2O5.Where vanadium assay data is available, that information is used to estimate the vanadium Mineral Resource. Where assay data is not available an average V2O5:U3O8 ratio of 8.6:1 is used to estimate the vanadium Mineral Resource.

(3) Mineral Resources for Whirlwind are estimated at a uranium cut-off grade of 0.06% eU3O8. This cut-off grade is based on using a long-term uranium price of $77.50 per pound U3O8 and a vanadium price of $7.50 per pound V2O5. Vanadium grades are based on assays where taken, and otherwise estimated at the average V2O5:U3O8 ratio of 3.24:1.

(4) The Mineral Resources given for Sage Plain differ from those given in the “*Updated Technical Report on Sage Plain Project (Including the Calliham Mine), San Juan County, Utah, U.S.A.”* dated March 18, 2015. The Skidmore Lease portion of the property was dropped in 2016 and that Mineral Resource has been subtracted from that shown in the table.

(5) Numbers may not add due to rounding.

#### Exploration Properties

#### DOE Lease Tracts

The Company currently holds eight DOE uranium lease tracts in the Uravan Mineral Belt portion of Mesa, Montrose, and San Miguel Counties, Colorado. The tracts are designated C-SR-12, C-SR-16A, C-AM-19, C-AM-20, C-CM-24, C-G-26, and C-G-27. A Federal Court Order in 2011 halted all physical work on these tracts until the DOE completed a full EIS on its Uranium Leasing Program. The Final EIS was made available and the RoD was published in the Federal Register on May 12, 2014. The DOE’s preferred alternative is to resume the leasing program essentially as it was before the lawsuit. On March 18, 2019, the U.S. District Court officially dissolved the injunction and ordered the case closed. New 10-year leases were executed by the Company of the above-mentioned lease tracts on January 6, 2020. Physical work on the lease tracts including both exploration drilling and mining is now allowed. All activities will be permitted through the DOE and the State of Colorado. At this time, the Company has no plans to conduct physical work on the properties. Prior to the 2011 stay, the Company conducted drilling on C-CM-24 and C-G-26.

## Legal proceedings

As filed, 8,658 characters.

Other than routine litigation incidental to our business, or as described below, the Company is not currently a party to any material pending legal proceedings that management believes would be likely to have a material adverse effect on our financial position, results of operations or cash flows.

### White Mesa Mill

In 2013, the Ute Mountain Ute Tribe filed a Petition to Intervene and Request for Agency Action challenging the Corrective Action Plan approved by the UDEQ relating to nitrate contamination in the shallow aquifer at the White Mesa Mill. The challenge is currently being evaluated and may involve the appointment of an administrative law judge to hear the matter. The Company does not consider this action to have any merit. If the petition is successful, the likely outcome would be a requirement to modify or replace the existing Corrective Action Plan. At this time, the Company does not believe any such modification or replacement would materially affect its financial position, results of operations or cash flows. However, the scope and costs of remediation under a revised or replacement Corrective Action Plan have not yet been determined and could be significant.

On January 19, 2018, the UDEQ renewed, and on February 16, 2018 reissued, the Radioactive Materials License for another ten years and GWDP for another five years, after which further applications for renewal of the Radioactive Materials License and GWDP will need to be submitted. During the review period for each application for renewal, the Mill can continue to operate under its existing Radioactive Materials License and GWDP until such time as the renewed Radioactive Materials License or GWDP is issued. In March 2019, the DWMRC issued a revised GWDP to incorporate the addition of Dissolved Oxygen into the list of field parameters measured during groundwater sampling. Additionally, DWMRC modified Ground Water Compliance Limits for several wells as a result of their acceptance of several source assessment reports. The source assessment reports concluded that the previous exceedances in the wells were due to natural background influences or well construction abnormalities and were not a concern. Most recently, the GWDP was revised again in March 2021 to delete references to certain completed requirements from Part I.H. (Completed Compliance Schedules) of the GWDP, to add certain new required compliance schedules to the same section, and make other regulatory amendments and adjustments, including modification of select Groundwater Compliance Limits, for certain monitoring constituents, in certain and rigorously evaluated monitoring wells, as required by the GWDP.

In 2018, the Grand Canyon Trust, Ute Mountain Ute Tribe and Uranium Watch (collectively, the “ **Mill Plaintiffs”**) filed Petitions for Review challenging UDEQ’s renewal of the Radioactive Materials License and GWDP and Requests for Appointment of an Administrative Law Judge, which they later agreed to suspend pursuant to a Stipulation and Agreement with UDEQ, effective June 4, 2018. The Company and Mill Plaintiffs held multiple discussions over the course of 2018 and 2019 in an effort to settle the dispute outside of any judicial proceeding. On February 1, 2019, the Mill Plaintiffs submitted to the Company their proposal for reaching a settlement agreement. The proposal remains under consideration by the Company, which may choose to submit a counterproposal constituting the Company’s final position on all disputed matters if it determines that meaningful settlement can be reached by the parties. The Company does not consider these challenges to have any merit and, if a settlement cannot be reached, intends to participate with UDEQ in defending against the challenges. If the challenges are successful, the likely outcome would be a requirement to modify the renewed Radioactive Materials License and/or GWDP. At this time, the Company does not believe any such modification would materially affect our financial position, results of operations or cash flows.

### Pinyon Plain Project

In March, 2013, the Center for Biological Diversity, the Grand Canyon Trust, the Sierra Club and the Havasupai Tribe (the “**Pinyon Plaintiffs”**) filed a complaint in the U.S. District Court for the District of Arizona (the “**District Court”**) against the USFS Forest Supervisor for the Kaibab National Forest and the USFS seeking an order (a) declaring that the USFS failed to comply with environmental, mining, public land, and historic preservation laws in relation to our Pinyon Plain Project (formerly known as the “Canyon Project”), (b) setting aside any approvals regarding exploration and mining operations at the Pinyon Plain Project, and (c) directing operations to cease at the Pinyon Plain Project and enjoining the USFS from allowing any further exploration or mining-related activities at the Pinyon Plain Project until the USFS fully complies with all applicable laws. In April 2013, the Pinyon Plaintiffs filed a Motion for Preliminary Injunction, which was denied by the District Court in September 2013. On April 7, 2015, the District Court issued its final ruling on the merits in favor of the Defendants and the Company and against the Pinyon Plaintiffs on all counts. The Pinyon Plaintiffs appealed the District Court’s ruling on the merits to the United States Ninth Circuit Court of Appeals (the “**Ninth Circuit”**) and filed motions for an injunction pending appeal with the District Court. Those motions for an injunction pending appeal were denied by the District Court on May 26, 2015. Thereafter, Pinyon Plaintiffs filed urgent motions for an injunction pending appeal with the Ninth Circuit, which were denied on June 30, 2015.

The hearing on the merits at the Ninth Circuit was held on December 15, 2016. On December 12, 2017, the Company received a favorable ruling from the Ninth Circuit on the appeal of the merits on the Pinyon Plain Mine litigation. The Pinyon Plaintiffs petitioned the Ninth Circuit for a rehearing *en banc* and, on October 25, 2018, the Ninth Circuit panel withdrew its prior opinion and filed a new opinion affirming, with one exception, the District Court’s decision. The Ninth Circuit panel reversed itself on its prudential standing analysis as applied to the fourth claim on “valid existing rights,” having initially determined that the Pinyon Plaintiffs lacked standing under the Mining Act of 1872. The panel remanded the claim back to the District Court to hear on the merits. On September 11, 2019, the Pinyon Plaintiffs filed their Motion for Summary Judgment and Memorandum in Support with the District Court, after which the Company filed its Intervenors-Defendants’ Motion for Summary Judgment on October 23, 2019. On November 15, 2019, the Pinyon Plaintiffs filed their Reply in Support of their Motion for Summary Judgment.

On May 22, 2020, the District Court issued its final order in favor of the Company and the USFS. The Pinyon Plaintiffs were afforded 60 days in which to file an appeal with the Ninth Circuit, during which they filed their Notice of Appeal from a Judgment or Order of a United States District Court. The Ninth Circuit subsequently issued a Time Schedule Order setting due dates for the parties’ briefs and actions required to perfect the appeal. The Pinyon Plaintiffs filed their Appellant’s Opening Brief with the Ninth Circuit on December 22, 2020, and the USFS and Company’s respective Answering Briefs are due April 5, 2021 following a grant of extension. As a part of the appeal, the Company may be required to maintain the Pinyon Plain Project on standby pending resolution of the matter. Such a prolonged delay of mining activities could have a significant impact on our future operations.

### Daneros Mine

On February 23, 2018, the BLM issued the Environmental Assessment (“**EA”**), Decision Record and FONSI for the Mine Plan of Operations Modification for the Daneros Mine. On March 29, 2018, the Southern Utah Wilderness Alliance and Grand Canyon Trust (together the “**Daneros Appellants”**) filed a Notice of Appeal to the IBLA regarding the BLM’s Decision Record and FONSI and also challenging the underlying EA. In April 2018, the Company filed a Motion to Intervene with the IBLA, requesting that the Company be allowed intervention as a full party to this appeal, which was subsequently granted.

This matter has been briefed and remains under consideration by IBLA at this time. The Company does not consider these challenges to have any merit; however, the scope and costs of amending or redoing the EA have not yet been determined and could be significant.

## Management's discussion and analysis

As filed, 68,097 characters.

The following discussion and analysis should be read in conjunction with our financial statements for the three years ended December 31, 2020 and the related notes thereto. This Discussion and Analysis contains forward-looking statements that involve risks, uncertainties, and assumptions. Our actual results may differ materially from those anticipated in these forward-looking statements as a result of many factors, including, but not limited to, those set forth under the section heading “Item 1A. Risk Factors” and elsewhere in this Annual Report. See section heading “Cautionary Statement Regarding Forward-Looking Statements.”

### Outlook

#### Overview

In response to the proposed establishment of a strategic national U.S. Uranium Reserve program, the Company is evaluating activities aimed towards increasing uranium production at all or some of our production facilities, including the currently operating White Mesa Mill, as well as the Alta Mesa ISR Facility, the Nichols Ranch ISR Facility, the La Sal Complex and Pinyon Plain Mine, which are currently on standby. The Company may commence such activities, prior to the implementation of all program details, recognizing that there can be no guarantee that the program details will be satisfactory and that the timing and outcome of this process is therefore uncertain, or as market conditions may warrant. Alternatively, the Company may defer commencing any such activities until further clarification is obtained, or as market conditions otherwise warrant. No decisions on any project-specific actions have been made at this time.

During 2021 the Company expects to recover uranium at the White Mesa Mill from pond-returns and from alternate feed materials. The vanadium pond-return campaign that was conducted in 2019 was brought to a close in early 2020. The Company also expects to produce mixed REE carbonate from natural monazite ore during 2021, subject to successful ramp-up. The Company does not plan to extract and/or recover any amounts of uranium of any significance from its Nichols Ranch Project in 2021, which was placed on standby in the second quarter of 2020 due to the depletion of its existing wellfields. Uranium recovery is expected to be maintained at reduced levels, as a result of current uranium market conditions, until such time when market conditions improve sufficiently. Until such time that improvement in uranium market conditions is observed or suitable sales contracts can be entered into, the Company expects to defer further wellfield development at its Nichols Ranch Project and maintain that project on standby. In addition, the Company expects to keep the Alta Mesa Project and its conventional mining properties on standby.

The Company is also seeking new sources of revenue, including its emerging REE business, as well as new sources of alternate feed materials and new fee processing opportunities at the White Mesa Mill that can be processed under existing market conditions (i.e., without reliance on current uranium sales prices). The Company will also continue its support of U.S. governmental activities to support the U.S. uranium mining industry, including the proposed establishment of a U.S. Uranium Reserve. In addition, the Company is in discussions to potentially sell certain of its non-core properties, although there are currently no binding offers, and there can be no assurance that a sale will be completed or that we will be successful in completing a sale on acceptable terms. The Company will evaluate additional acquisition and disposition opportunities that may arise.

#### Extraction and Recovery Activities Overview

During the year ended December 31, 2020, the Company recovered approximately 196,500 pounds of U3O8, all of which were for the account of the Company. The Company also recovered approximately 67,000 pounds of V2O5, all of which were for the account of the Company. The Company expects to recover approximately 30,000 to 60,000 pounds of U3O8 in the year ending December 31, 2021 for its own account. The Company expects to produce no vanadium. In 2021, the Company also expects to produce approximately 2,000 to 3,000 tons of mixed REE carbonate at the mill, containing approximately 1,000 to 1,600 tons of total rare earth oxides (“**TREO”).**

The Company has strategically opted not to enter into any uranium sales commitments for 2021. Therefore, subject to the proposed establishment of a U.S. Uranium Reserve and general market conditions, all 2021 uranium production is expected to be added to existing inventories, which inventories are expected to total approximately 720,000 to 750,000 pounds of U3O8 at year-end. Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve or improvements in general market conditions, both ISR and conventional uranium extraction and/or recovery is expected to continue to be maintained at reduced levels until such time that improvements in uranium market conditions are observed or suitable sales contracts can be entered into. All V2O5 inventory is expected to be sold on the spot market if prices rise significantly above current levels, but otherwise maintained in inventory. The Company expects to sell all or a portion of its mixed REE carbonate to global separation facilities and/or to stockpile it for future separation at the Mill or elsewhere.

#### ISR Activities

We extracted and recovered approximately 6,000 pounds of U3O8 from the Nichols Ranch Project for the year ended December 31, 2020. The Company expects to produce insignificant quantities of U3O8 in the year ending December 31, 2021 from Nichols Ranch.

As of December 31, 2020, the Nichols Ranch wellfields had nine header houses that previously extracted uranium, and which are now depleted. Until such time as improvement in uranium market conditions is observed, the proposed U.S. Uranium Reserve is established, and/or suitable sales contracts can be procured, the Company expects to defer development of further header houses at its Nichols Ranch Project. The Company currently holds 34 fully-permitted, undeveloped wellfields at Nichols Ranch, including four additional wellfields at the Nichols Ranch wellfields, 22 wellfields at the adjacent Jane Dough wellfields, and eight wellfields at the Hank Project, which is fully permitted to be constructed as a satellite facility to the Nichols Ranch Plant.

The Company expects to continue to keep the Alta Mesa Project on standby until such time as improvements in uranium market conditions are observed, the proposed U.S. Uranium Reserve is established, and/or suitable sales contracts can be procured.

#### Conventional Activities

#### Conventional Extraction and Recovery Activities

During the year ended December 31, 2020, the White Mesa Mill recovered approximately 190,500 pounds of U3O8 and approximately 67,000 pounds of V2O5. The Mill also focused on developing its REE recovery business. During 2021, the Company expects to recover approximately 30,000 to 60,000 pounds of U3O8 at the White Mesa Mill, including uranium recovered through the processing of REE- and uranium-bearing natural monazite ore. The Company also expects to produce approximately 2,000 to 3,000 tons of mixed REE carbonate at the Mill, containing approximately 1,000 to 1,600 tons TREO. The Company currently has approximately 127,000 pounds of U3O8 contained in stockpiled alternate feed material and ore inventory that can be recovered in the future for the U.S. uranium reserve or as general market conditions warrant. In addition, there remains an estimated 1.5-3 million pounds of solubilized recoverable V2O5 inventory remaining in the tailings facility awaiting future recovery, as market conditions may warrant.

The White Mesa Mill has historically operated on a campaign basis whereby uranium and/or vanadium recovery is scheduled as mill feed, cash needs, contract requirements, and/or market conditions may warrant. The Company currently expects that planned uranium production from alternate feed materials, processing natural monazite ore for the recovery of uranium and REEs, and receipt of uranium-bearing materials from mine cleanup activities will keep the Mill in operation through 2021 and beyond. The Company is also actively pursuing opportunities to process additional sources of natural monazite ore, new and additional alternate feed material sources, and new and additional low-grade ore from third parties in connection with various uranium clean-up requirements. Successful results from these activities would allow the Mill to extend operations well into 2022 and beyond.

However, if at any time the Company is unable to justify full operation of the Mill, the Company would place uranium, REE and/or vanadium recovery activities at the Mill on standby at that time. While on standby, the Mill would continue to dry and package material from the Nichols Ranch Plant, if operating, and continue to receive and stockpile alternate feed materials for future milling campaigns. Each future milling campaign would be subject to receipt of sufficient mill feed and resulting cash flow that would allow the Company to operate the Mill on a profitable basis or to recover all or a portion of the Mill's standby costs.

#### Conventional Standby, Permitting and Evaluation Activities

During the year ended December 31, 2020, standby and environmental compliance activities occurred at the Pinyon Plain Project. Subject to any actions the Company may take in response to the proposed establishment of a U.S. Uranium Reserve and general market conditions, during 2021, the Company plans to continue carrying out engineering, metallurgical testing, procurement and construction management activities at its Pinyon Plain Project. The timing of the Company’s plans to extract and process mineralized materials from this project will be based on the results of this additional evaluation work, along with market conditions, available financing, sales requirements, and/or permits required for copper recovery at the Mill.

The Company is selectively advancing certain permits at its other major conventional uranium projects, such as the Roca Honda Project, a large, high-grade conventional project in New Mexico. The Company will also maintain required permits at the Company’s conventional projects, including the Sheep Mountain Project, La Sal Complex, and the Whirlwind mines. In addition, the Company will continue to evaluate the Bullfrog Property at its Henry Mountains Project. Expenditures for certain of these projects have been adjusted to coincide with expected dates of price recoveries based on the Company’s forecasts. All of these projects serve as important pipeline assets for the Company’s future conventional production capabilities, as market conditions warrant. The Company is also in discussions to potentially sell the Tony M, Daneros, Rim and other non-core conventional assets.

#### Uranium Sales

During the year ended December 31, 2020, the Company completed no sales of uranium. The Company currently has no remaining contracts, and therefore all existing uranium inventory and future production is fully unhedged to future uranium price changes.

#### Vanadium Sales

During 2020, the Company completed no sales of vanadium. The Company expects to sell finished vanadium product when justified into the metallurgical industry, as well as other markets that demand a higher purity product, including the aerospace, chemical, and potentially the vanadium battery industries. The Company expects to sell to a diverse group of customers in order to maximize revenues and profits. The vanadium produced in the recent pond return campaign was a high-purity vanadium product of 99.6%-99.7% V2O5. The Company believes there may be opportunities to sell certain quantities of this high-purity material at a premium to reported spot prices. The Company may also retain vanadium product in inventory for future sale, depending on vanadium spot prices and general market conditions.

#### Rare Earth Sales

The Company expects to commence commercial production of a mixed REE carbonate in 2021. Subject to successfully ramping-up production of a salable product during 2021, the Company expects to sell some or all of this intermediate REE product to Neo’s Silmet separation facility in Europe and potentially to other REE separation facilities outside the U.S. To the extent not sold, the Company expects to stockpile mixed REE carbonate at the Mill for future separation and other downstream REE processing at the Mill or elsewhere. See “ITEM 1 DESCRIPTION OF BUSINESS: *The Company’s Rare Earth Element Business,* above and *Update on Rare Earth Element Initiative,”* below.

The Company also continues to pursue new sources of revenue, including additional alternate feed materials and other sources of feed for the White Mesa Mill.

#### COVID-19

The Company continues to evaluate the effects of the global COVID-19 pandemic on the Company’s business objectives, projections and workforce. Due to the current uncertainty, the Company is continuing its cost-cutting measures, while retaining the operational readiness of the Company’s core production assets. The Company is also continuing to work to secure U.S. government support for U.S. uranium miners. To date, although the Company has made operational adjustments since the onset of the pandemic to ensure its workforce remains protected, the Company has not been required to shut down any operations as a result of COVID-19. None of these operational adjustments have been material to the Company. The Company has evaluated any potential shutdown of Company production facilities as a result of COVID-19, and has determined that any such shutdown could be accommodated by the Company in a manner consistent with a typical shutdown of Company production facilities as a result of depressed commodity prices. Management believes the Company is well-capitalized and will be able to withstand facility shutdowns or depressed share prices as a result of COVID-19 for at least the next twelve months.

#### Bought Deal Financing

On February 20, 2020, the Company closed a bought deal public offering of Common Shares made pursuant to an underwriting agreement dated February 13, 2020 between the Company and a syndicate of underwriters led by Cantor Fitzgerald & Co. as lead underwriter and sole book-runner, and H.C. Wainwright & Co., LLC, Eight Capital, Haywood Securities Inc. and Roth Capital Partners, LLC (the “**Offering”**). Pursuant to the Offering, the Company issued an aggregate of 11,300,000 Common Shares at a price of $1.47 per share for gross proceeds of $16.61 million. The Company received net proceeds, after commissions and fees, of $15.14 million from the Offering.

#### Full Redemption of Convertible Debentures

On July 14, 2020, the Company redeemed Cdn$10.43 million principal amount of the Cdn$20.86 million Convertible Debentures then outstanding for approximately $7.78 million. The Convertible Debentures were redeemable for an amount equal to 101% of principal plus accrued and unpaid interest thereon, up to but excluding July 14, 2020. On October 6, 2020, the Company redeemed the remaining Cdn$10.43 million principal amount of the Convertible Debentures then outstanding for approximately $7.82 million. The Convertible Debentures were redeemable for an amount equal to 101% of principal plus accrued and unpaid interest thereon, up to but excluding October 6, 2020. As a result of the final redemption, no Convertible Debentures are outstanding or subject to the terms of the Indenture, and the Convertible Debentures have ceased to be listed on the TSX. See “*Note 11 to the Financial Statements: Loans and Borrowings.”* The Company decided to redeem all of the Convertible Debentures prior to maturity because the U.S.-Canada currency exchange rate was favorable, the Company had sufficient cash available, and the Company avoided approximately US$0.46 million in interest payments in 2020 by doing so. By proactively managing its outstanding indebtedness in this way, the Company was able to redeem the Convertible Debentures on the Company’s own timing and terms and with minimal market disruption. The Company currently has no other remaining short- or long-term debt.

#### Agreement to Acquire Prompt Fission Neutron (PFN) Borehole Logging Technology and Equipment

On May 6, 2020, the Company announced it had entered into an agreement to acquire from GeoInstruments Logging LLC (“**GIL”**) all of its Prompt Fission Neutron (“**PFN”**) technology and equipment, including all of its related intellectual property, giving Energy Fuels the exclusive right to use, license, and service this particular PFN technology globally. PFN is critical to successful uranium production particularly from many *in situ* recovery (“**ISR”**) deposits, as it more accurately measures downhole in-situ U3O8 ore grade versus traditional Total Gamma and Spectral Gamma methods. On July 31, 2020, the parties closed the transaction and all such equipment and technology was transferred to the Company.

The PFN equipment and technology acquired by Energy Fuels includes: four (4) PFN tools; nine (9) gamma tools; two (2) low-mileage, heavy-duty logging trucks with logging and associated equipment; power supplies, computers, communication, and other technology; and all associated intellectual property, and the sole right to utilize and license the acquired PFN technology globally. The total consideration paid by Energy Fuels to GIL was $0.5 million cash.

Energy Fuels currently has some PFN equipment in various states of repair, which it has used for its mining operations in the past, as do other companies in the U.S. and around the world. With the acquisition of this additional PFN equipment and technology from GIL, Energy Fuels is not only able to utilize the additional equipment to ramp-up production from its ISR properties more quickly and efficiently in the event of improved market conditions, but has also secured the ability to service, repair and maintain PFN equipment currently held by the Company and others, as well as license this technology to others in the future.

#### Update on Rare Earth Element Initiative

On April 13, 2020, the Company announced its intent to enter the REE market following several months of review and testing, including discussions with various technical experts and the U.S. government. The U.S. government is actively seeking a domestic source of REE minerals, which are needed for national defense among other applications.

REEs are a group of 17 chemical elements (the 15 elements in the lanthanum series, plus yttrium and scandium) that have a variety of industrial, energy, military and defense uses, including automotive components, communications technology, clean energy production, consumer electronics, defense systems, advanced magnets, lasers and numerous other applications. According to a 2017 report by the United States Geological Survey (“**USGS”**), China has controlled more than 90% of the global supply of REEs since the late-1990s and has placed restrictions on REE exports since 2010.

Energy Fuels believes the White Mesa Mill is uniquely suited to potentially receive and process a number of different types of ores for the recovery of REEs (along with uranium), which, if achievable on a commercial basis and subject to the receipt of any required license or permit amendments, would eliminate the current need to ship those ores to China for processing. If successful, the Company expects to offer customers tolling or processing arrangements at the White Mesa Mill.

On May 21, 2020, the Company announced it had entered into consulting agreements with Constantine Karayannopoulos and Brock O’Kelley, two REE industry experts who each have decades of experience producing commercially viable rare earth products, to aid in the development and implementation of commercial and technical REE strategies for the Company’s REE program. A chemical engineer by training with more than 25 years of experience in the rare earth industry, Mr. Karayannopoulos, was at the time of the announcement Chair of Neo Performance Materials (TSX:NEO) (“**Neo”**), one of the world’s leading producers of advanced industrial materials, including rare earth-based engineered products, for multiple global markets. Mr. O’Kelley played a key role in the operation of the Mountain Pass, California rare earth processing facility during the 1990s and 2000s. Both are industry veterans with extensive knowledge of REE processing facility design, start-up, operations, and downstream value-added manufacturing of advanced REE products. On July 7, 2020, Mr. Karayannopoulos was reappointed as President and CEO of Neo. As a result of his new executive roles with Neo, his consulting agreement with the Company ended on August 6, 2020. On July 31, 2020, the Company entered into a non-exclusive Letter of Intent with Neo, under which: (i) Mr. Karayannopoulos and other Neo personnel will continue to assist Energy Fuels in developing commercial and technical aspects of the Company’s REE strategy, including the potential production of a rare earth oxide concentrate at the Mill that can be sold to REE separation facilities; and (ii) the Company and Neo will work together toward potentially creating a longer term mutually beneficial relationship, which may involve commitments to buy and sell all or a portion of the REE concentrate produced at the Mill or other commercial arrangements.

On December 14, 2020, the Company announced it entered into a three-year supply agreement with The Chemours Company (NYSE: CC) (“**Chemours”**) to acquire a minimum of 2,500 tons per year of natural monazite sands, one of the highest-grade REE ores in the world, from Chemours’ Offerman Mineral Sand Plant located in Georgia. The Company expects to process this monazite at the Mill, starting in 2021, to recover the contained uranium and to produce a marketable mixed REE carbonate as a step toward re-establishing a fully-integrated U.S. REE supply chain.

On March 1, 2021, the Company and Neo jointly announced that they had entered into an agreement in principle, subject to completion of definitive agreements, under which Energy Fuels will process natural monazite sands into an REE Carbonate beginning in March or April 2021 and ship a portion of that production to Neo's rare earth separations facility in Sillamäe, Estonia ("**Silmet**"). Neo will then process the REE Carbonate into separated rare earth materials for use in rare earth permanent magnets and other rare earth-based advanced materials. Silmet is the only operational rare earth separations facility in Europe and has been separating rare earths into commercial value-added products for more than 50 years. Implementation of this initiative is subject to successful ramp-up to commercial-scale operations, execution of definitive agreements, and optimization of the companies' production processes.

Upon a successful ramp-up of this program, the Company will be the first U.S. company in several years to produce a marketable mixed REE concentrate ready for separation on a commercial scale. The Company estimates that the amount of REEs contained in the monazite sands to be supplied by Chemours will equal close to 10% of total current U.S. REE demand, as contained in end-use products.

Removal and recovery of the uranium and other radionuclides from rare earth ores is a key aspect of Energy Fuels’ value proposition, as many REE separation and recovery facilities are not able to handle those radionuclides from a technical or regulatory standpoint. The White Mesa Mill has a 40-year history of responsibly handling, processing and recycling uranium bearing materials. Therefore, it has the potential to provide a crucial link in a commercially viable U.S. REE supply chain. See ITEM 1 DESCRIPTION OF BUSINESS: *The Company’s Rare Earth Element Business,* above.

#### Proposed Establishment of a U.S. Uranium Reserve and U.S. Nuclear Fuel Working Group Update

On January 16, 2018, the Company participated in the joint filing of a Petition for Relief under Section 232 of the Trade Expansion Act of 1962 (as amended) from Imports of Uranium Products that Threaten National Security (the “**Petition”**). The Petition describes how uranium and nuclear fuel from state-owned and state-subsidized enterprises in Russia, Kazakhstan, Uzbekistan and China are believed to represent a threat to U.S. national security.

On July 18, 2018, the U.S. Department of Commerce (“**DOC”**) initiated an investigation in response to the Petition (the “**Section 232 Investigation”).**

On April 14, 2019, the DOC completed the Section 232 Investigation, and the Secretary of Commerce submitted a report to the former President of the United States containing his findings (the “**Section 232 Report”).**

On July 12, 2019, in response to the Section 232 Report, former President Trump issued a memorandum, where he stated that “I agree with the Secretary that the United States uranium industry faces significant challenges in producing uranium domestically and that this is an issue of national security.” In order “to address the concerns identified by the Secretary regarding domestic uranium production and to ensure a comprehensive review of the entire domestic nuclear supply chain,” former President Trump formed the U.S. Nuclear Fuel Working Group (the “**Working Group”**) to “examine the current state of domestic nuclear fuel production to reinvigorate the entire nuclear fuel supply chain, consistent with United States national security and nonproliferation goals.” Former President Trump instructed the Working Group to “develop recommendations for reviving and expanding domestic nuclear fuel production,” and to submit a report to him within 90 days “setting forth the Working Group’s findings and making recommendations to further enable domestic nuclear fuel production if needed.”

On February 10, 2020, the federal executive Budget for fiscal year 2021 (October 1, 2020 through September 30, 2021) (the “**Budget”**) was published. The Budget “Supports Nuclear Fuel Cycle Capabilities,” and states that “\[o\]n July 12, 2019, the \[former\] President determined that ‘...the United States uranium industry faces significant challenges in producing uranium domestically and that this is an issue of national security.’ The Budget establishes a U.S. Uranium Reserve to provide additional assurances of availability of uranium in the event of a market disruption.” Table 25-1 of the Budget sought congressional appropriations of $150 million per year over the next 10 years (totaling $1.5 billion over that time frame) for domestic uranium purchases. For fiscal 2021 (October 1, 2020 through September 30, 2021), the Budget sought an appropriation of $150 million, “to remain available until expended,” as the appropriation for the first year of the 10-year program. The Budget further stated that “Establishing a Uranium Reserve provides assurance of availability of uranium in the event of a market disruption and supports strategic U.S. fuel cycle capabilities. This action addresses immediate challenges to the production of domestic uranium and reflects the Administration’s Nuclear Fuel Working Group (NFWG) priorities. The NFWG will continue to evaluate issues related to uranium supply chain and fuel supply.”

On April 23, 2020, the Working Group published its report: Restoring America’s Competitive Nuclear Energy Advantage: A strategy to assure U.S. national security. This comprehensive strategy sought to revive and strengthen U.S. nuclear fuel capabilities, starting with uranium mining, with the goals of supporting U.S. energy and national security, preventing geopolitical adversaries (particularly those in Russia) from using their nuclear capabilities to influence the U.S. and the world, and promoting global non-proliferation objectives and nuclear safety. The report stated that “the clear outcome of the Working Group’s efforts is confirmation that it is in the nation’s national security interests to preserve the assets and investments of the entire U.S. nuclear enterprise and to revitalize the sector to regain U.S. global nuclear leadership.” The report recommended government purchases to establish a Uranium Reserve, as contemplated by the Budget, and other actions aimed to strengthen the entire nuclear fuel cycle.

On December 27, 2020, the COVID-Relief and Omnibus Spending Bill, which includes $75 million for the proposed establishment of a strategic U.S. Uranium Reserve, was signed into law by the United States Congress. This key funding opens the door for the U.S. government to purchase domestically-produced uranium to guard against potential commercial and national security risks presented by the country’s near-total reliance on foreign imports of uranium. The Company stands ready to benefit from this program through sales out of its existing uranium inventories and future production from its mines and facilities. However, because the U.S. Uranium Reserve has yet to be established at this time, the details of implementation of activities pursuant to the new law have not yet been defined. As a result, there can be no certainty as to the outcome of a U.S. Uranium Reserve, if any, including the process for and details of its development, and any resulting support for the Company’s ongoing and planned activities, or for any further evaluations of the Working Group.

If the uranium and vanadium markets or general market conditions do not improve, whether as a result of the establishment of a U.S. Uranium Reserve or otherwise, the Company may further reduce its operational activities as required in order to minimize its cash expenditures while preserving its core asset base for increased production in the future, as market conditions may warrant.

#### The Company’s Plans in Response to the Proposed U.S. Uranium Reserve

In response to the proposed establishment of a U.S. Uranium Reserve, the Company is evaluating activities aimed towards increasing uranium production at all or some of its production facilities, subject to general market conditions. No decisions on any project-specific actions to be taken in response to the proposed establishment of a U.S. Uranium Reserve have been made at this time.

#### Renewal of the Russian Suspension Agreement

On September 14, 2020, the DOC announced that it had obtained Russia's agreement to extend limits on uranium imports into the U.S. from Russia through 2040 under an extended Russian Suspension Agreement. This is an important step toward maintaining the long-term health of the U.S. uranium mining industry. The DOC won important concessions from Russia, including lower quotas starting in the mid-2020s, allowing only a portion of the quotas to be used for the sale of U3O8 and conversion into the U.S., and strict controls on Russian enrichment service contracts, reducing U.S. dependence on Russian uranium in the long term. While the extended Russian Suspension Agreement is an important step toward maintaining the long-term health of the U.S. uranium mining industry, it does not supplant the need for the establishment of a Uranium Reserve as proposed in the COVID-Relief and Omnibus Spending Bill and as recommended by the Working Group.

#### Management Streamlining

On August 20, 2020, the Company announced that it was making a number of changes to its management team in order to reduce costs, flatten the organizational structure, and focus on the ongoing growth of a new generation of U.S. uranium and REE professionals, including the following, effective September 1, 2020: (a) Mr. Scott Bakken, former Senior Director, Regulatory Affairs, became the Vice President, Regulatory Affairs, responsible for permitting and regulatory matters relating to all of the Company’s operations, both conventional and ISR, and also for overall worker health and safety matters at the Company; (b) Mr. Bernard Bonifas, former Director, Wyoming Operations, became the Director, ISR Operations, responsible for all of the Company’s ISR operations, including its Nichols Ranch ISR project in Wyoming and its Alta Mesa ISR project in Texas; (c) Ms. Sarai Luksch, CPA, joined the Company as Controller; (d) Ms. Dee Ann Nazarenus, former Director, Human Resources & Administration, became the Vice President, Human Resources & Administration, responsible for planning, developing, organizing, implementing, directing and evaluating all human resource functions of the Company, and directing and managing all administrative functions of the Company; and (e) Mr. Logan Shumway, former Manager of the Company’s

White Mesa Mill, became the Director, Conventional Operations, responsible for overseeing the advancement of the Company’s REE objectives, in addition to being responsible for overall White Mesa Mill management. In addition, and in support of the objective to reduce costs, effective as of August 31, 2020, former Chief Operating Officer, Mr. W. Paul Goranson left the Company to pursue other opportunities, and effective as of October 31, 2020, former Chief Accounting Officer, Mr. Matthew Tarnowski, left the Company to pursue other opportunities.

#### Continued Efforts to Minimize Costs

The Company will continue to seek ways to minimize the costs of maintaining its critical properties in a state of readiness for potential improvements in market conditions, and is evaluating whether additional cost-cutting measures may be warranted at this time as a result of general market conditions, such as the possibility of monetizing non-core conventional assets of the Company. See “ITEM 1 DESCRIPTION OF BUSINESS: *Potential Sale of Non-Core Assets,”* above.

### Results of Operations

The following table summarizes the results of operations for the years ended December 31, 2020, 2019 and 2018 (in thousands of dollars):

| Revenues | Years ended December 31, 2020 | 2019 | 2018 |
| --- | ---: | ---: | ---: |
| Uranium concentrates | $— | $66 | $30,789 |
| Vanadium concentrates | — | 2,237 | — |
| Alternate feed materials processing and other | 1,658 | 3,562 | 932 |
| **Total revenues** | 1,658 | 5,865 | 31,721 |
| **Costs and expenses applicable to revenues** |  |  |  |
| Costs and expenses applicable to uranium concentrates | — | 63 | 14,752 |
| Costs and expenses applicable to vanadium concentrates | — | 1,805 | — |
| Costs and expenses applicable to alternate feed materials and other | — | 2,079 | — |
| **Total costs and expenses applicable to revenues** | — | 3,947 | 14,752 |
| Impairment of inventories | 1,644 | 14,351 | 4,579 |
| **Gross profit (loss)** | 14 | (12,433) | 12,390 |
| **Other operating costs** |  |  |  |
| Development, permitting and land holding | 4,333 | 9,180 | 9,912 |
| Standby costs | 4,015 | 2,584 | 5,112 |
| Accretion of asset retirement obligation | 1,911 | 1,931 | 1,835 |
| **Total other operating costs** | 10,259 | 13,695 | 16,859 |
| **Selling, general and administration** |  |  |  |
| Selling costs | 38 | 190 | 183 |
| Intangible asset amortization | — | — | 2,502 |
| General and administration | 14,344 | 14,263 | 14,158 |
| **Total selling, general and administration** | 14,382 | 14,453 | 16,843 |
| **Total operating loss** | (24,627) | (40,581) | (21,312) |
| Interest expense | (952) | (1,491) | (1,722) |
| Other income (loss) | (2,293) | 3,978 | (2,328) |
| **Net loss** | $(27,872) | $(38,094) | $(25,362) |
| **Basic and diluted net loss per share** | $(0.23) | $(0.40) | $(0.30) |

### Results of Operations

### Year ended December 31, 2020 compared to year ended December 31, 2019

For the year ended December 31, 2020 the Company recorded a net loss of $27.87 million or $0.23 per share compared with a net loss of $38.09 million or $0.40 per share for the year ended December 31, 2019.

For the year ended December 31, 2020, the Company recorded an operating loss of $24.63 million compared with an operating loss of $40.58 million for the year ended December 31, 2019.

### Revenues

Previously, the Company’s revenues from uranium were based on delivery schedules under long-term contracts, which could vary from quarter to quarter. As of December 31, 2018, the Company no longer had any uranium sales contacts. Any future sales of uranium will be subject to sale in the spot market until a time when the Company can agree to terms for long-term sales contracts or potentially pursuant to direct government purchases as contemplated by the Budget. In the year ended December 31, 2019, the Company initiated the selling of vanadium recovered from Pond Return at the White Mesa Mill under a Sales and Agency Agreement appointing an exclusive sales and marketing agent for all vanadium pentoxide produced by the Company.

Revenues for the year ended December 31, 2020 totaled $1.66 million, all of which were related to fees for ore received from a third-party uranium mine.

Revenues for the year ended December 31, 2019 totaled $5.87 million, of which $2.24 million was related to sales of approximately 202,000 pounds of vanadium concentrates and $3.56 million was related to toll processing of uranium concentrates and fees for ore received from third-party uranium mines.

### Operating Expenses

#### Uranium and Vanadium recovered and costs and expenses applicable to revenue

In the year ended December 31, 2020, the Company recovered approximately 6,000 pounds of U3O8 from ISR recovery activities for the Company’s own account and approximately 67,000 pounds of V2O5 from Pond Return. The Company recovered approximately 190,500 pounds of U3O8 from the pond solutions and alternate feed materials at the White Mesa Mill.

In the year ended December 31, 2019, the Company recovered approximately 70,000 pounds of U3O8 from ISR recovery activities for the Company’s own account and approximately 1,807,000 pounds of V2O5 from Pond Returns.

There are no costs and expenses applicable to revenue for the year ended December 31, 2020 as the Company did not make any concentrate sales of U3O8 or V2O5 and only collected a fee to receive ore from a third-party uranium mine for which the Company incurred *de minimis* costs, compared with $3.95 million for the year ended December 31, 2019. Costs and expenses applicable to revenue for the year ended December 31, 2019 consisted of $1.81 million from V2O5 and $2.08 million related to alternate feed materials.

### Other Operating Costs and Expenses

#### Development, permitting and land holding

For the year ended December 31, 2020, the Company spent $4.33 million for development of the Company’s properties, which did not include costs associated with the V2O5 test-mining program at the La Sal Project, and significantly less costs associated with V2O5 production at the White Mesa Mill, as were incurred during the year ended December 31, 2019. As a result of a downward revision to the Company's asset retirement obligation estimates, approximately $0.85 million was recorded as an offset to these expenses. For the year ended December 31, 2019, we spent $9.18 million primarily due to the development of the V2O5 test-mining program at the La Sal Project as well as expenses associated with ramping up V2O5 production at the White Mesa Mill.

While we expect the amounts relative to the items listed above have added future value to the Company, we expense these amounts as we do not have proven or probable reserves at any of the Company’s projects under SEC Industry Guide 7.

#### Standby costs

The Company’s La Sal, Daneros, and Arizona 1 Projects were on standby during the three years ended December 31, 2020. In the beginning of 2018 as well as the beginning of 2020, the White Mesa Mill was operated at lower levels of uranium recovery, including prolonged periods of standby. Costs related to the care and maintenance of the standby mines, along with standby costs incurred while the White Mesa Mill was operating at low levels of uranium recovery or on standby, are expensed.

For the year ended December 31, 2020, standby costs totaled $4.02 million compared with $2.58 million in the prior year. The increase is primarily related to a reduction in recovery activities at Nichols Ranch as it was placed on standby during the quarter ended June 30, 2020, and prolonged periods of standby at the Mill. As a result of a downward revision to the Company's asset retirement obligation estimates, approximately $7.00 million was recorded as an offset to these expenses.

#### Accretion

Accretion related to the asset retirement obligation for the Company’s properties decreased for the year ended December 31, 2020 to $1.91 million compared with the prior year of $1.93 million, primarily due to changes in timing of estimated reclamation activities at some of the Company's projects.

#### Selling, General, and Administrative

Selling, general and administrative expenses include costs associated with marketing uranium, corporate, general and administrative costs and intangible asset amortization from favorable contracts. Selling, general and administrative expenses consist primarily of payroll and related expenses for personnel, contract and professional services, share-based compensation expense and other overhead expenditures. Selling, general and administrative expenses totaled $14.38 million for the year ended December 31, 2020 compared to $14.45 million for the year ended December 31, 2019. For the year ended December 31, 2020, the Company incurred approximately $1.04 million in one-time management streamlining restructuring expenses.

### Impairment of Inventories

For the years ended December 31, 2020 and 2019, the Company recognized $1.64 million and $14.35 million, respectively, in impairment charges related to inventory to value such inventory at the lower of cost and net realizable value. The impairment of inventories is due to continued lower uranium and vanadium prices versus our cost to produce. The decrease in impairment charges for the year ended December 31, 2020 was primarily related to lower production levels as well as improved uranium prices.

### Interest Expense and Other Income and Expenses

#### Interest Expense

Interest expense for the year ended December 31, 2020 was $0.95 million compared with $1.49 million in the prior year due to early redemption of the Convertible Debentures prior to maturity.

#### Other income and expense

For the year ended December 31, 2020, other expenses net of other income totaled $2.29 million. These amounts primarily consist of a mark-to-market loss on the increase in fair value of warrant liabilities of $5.44 million, offset by a $1.84 million mark-to-market gain on investments accounted for at fair value, a gain on foreign exchange of $0.77 million, a mark-to-market gain on the change in the fair value of the Convertible Debentures of $0.16 million, interest income of $0.15 million, and other of $0.23 million.

For the year ended December 31, 2019, other income net of other expenses totaled $3.98 million. These amounts primarily consist of a gain on the change in the mark-to-market values of the Convertible Debentures of $0.29 million, a gain on the decrease in value of warrant liabilities of $3.73 million, and interest income of $0.48 million, offset by $0.15 million loss in investments accounted for at fair value and other of $0.32 million.

### Results of Operations

### Year ended December 31, 2019 compared to year ended December 31, 2018

For the year ended December 31, 2019 the Company recorded a net loss of $38.09 million or $0.40 per share compared with a net loss of $25.36 million or $0.30 per share for the year ended December 31, 2018.

For the year ended December 31, 2019, the Company recorded an operating loss of $40.58 million compared with an operating loss of $21.31 million for the year ended December 31, 2018.

### Revenues

The Company’s revenues from uranium were previously based on delivery schedules under long-term contracts, which could vary from quarter to quarter. As of December 31, 2018, the Company no longer has any uranium sales contacts. Any future sales of uranium will be subject to sale in the spot market until a time when the Company can agree to terms for long-term sales contracts or potentially pursuant to direct government purchases as contemplated by the proposed Uranium Reserve. In the year ended December 31, 2019, the Company initiated the selling of vanadium recovered from its pond solution at the White Mesa Mill under a Sales and Agency Agreement appointing an exclusive sales and marketing agent for all vanadium pentoxide produced by the Company.

Revenues for the year ended December 31, 2019 totaled $5.87 million, of which $2.24 million was related to sales of approximately 202,000 pounds of vanadium concentrates and $3.56 million was related to toll processing of uranium concentrates and fees for ore received from third-party uranium mines.

Revenues for the year ended December 31, 2018 totaled $31.72 million, of which $30.79 million was related to sales of 650,000 pounds of U3O8, which included the sale of 450,000 pounds of U3O8 pursuant to term contracts at an average price of

$57.24 per pound and the sale of 200,000 pounds of U3O8 into contracts based on spot market prices at an average price of $25.16 per pound.

### Operating Expenses

#### Uranium and Vanadium recovered and costs and expenses applicable to revenue

In the year ended December 31, 2019, the Company recovered approximately 70,000 pounds of U3O8 from ISR recovery activities for the Company’s own account and approximately 1,807,000 pounds of V2O5 from Pond Returns.

In the year ended December 31, 2018, the Company recovered 917,000 pounds of U3O8 of which 493,000 pounds were for the Company’s own account and 424,000 pounds were for the account of a tolling customer. Of the 493,000 pounds recovered for its own account, 137,000 pounds were from alternate feed sources, 216,000 pounds were from uranium recovered from existing tailings pond solutions at the White Mesa Mill, and 140,000 pounds were from ISR recovery activities.

Costs and expenses applicable to revenue for the year ended December 31, 2019 totaled $3.95 million, compared with $14.75 million for the year ended December 31, 2018. Included in cost and expenses applicable to revenue is $2.08 million and nil related to toll processing and other for the years ended December 31, 2019 and 2018, respectively. Costs and expenses applicable to revenue for the year ended December 31, 2019 consisted of $1.81 million from V2O5 and $2.08 million related to alternate feed materials. All costs and expenses applicable to revenue for 2018 were related to uranium concentrates.

### Other Operating Costs and Expenses

#### Development, permitting and land holding

For the year ended December 31, 2019, the Company spent $9.18 million for development of the Company’s properties. This is primarily due to the development of the V2O5 test-mining program at the La Sal Project as well as expenses associated with ramping up V2O5 production at the White Mesa Mill.

For the year ended December 31, 2018, we spent $9.91 million for development, permitting and land holding, comprised of the acquisition of royalties, the development of the Pinyon Plain Project and permitting and land holding costs related to the Pinyon Plain Project, development of the V2O5 test mining program at the La Sal Project as well as expenses associated with preparing the White Mesa Mill for V2O5 production.

While we expect the amounts relative to the items listed above have added future value to the Company, we expense these amounts as we do not have proven or probable reserves at any of the Company’s projects under SEC Industry Guide 7.

#### Standby costs

The Company’s La Sal, Daneros, and Arizona 1 Projects were on standby during the three years ended December 31, 2019. In the beginning of 2018, the White Mesa Mill was operated at lower levels of uranium recovery, including prolonged periods of standby. Costs related to the care and maintenance of the standby mines, along with standby costs incurred while the White Mesa Mill was operating at low levels of uranium recovery or on standby, are expensed.

For the year ended December 31, 2019, standby costs totaled $2.58 million compared with $5.11 million in the prior year. The decrease is primarily related to vanadium recovery activities at the White Mesa Mill.

#### Accretion

Accretion related to the asset retirement obligation for the Company’s properties increased for the year ended December 31, 2019 to $1.93 million compared with the prior year of $1.84 million, primarily due to normal accretion activity.

#### Selling, General, and Administrative

Selling, general and administrative expenses include costs associated with marketing uranium, corporate and general and administrative costs and intangible asset amortization from favorable contracts. Selling, general and administrative expenses consist primarily of payroll and related expenses for personnel, contract and professional services, share-based compensation expense and other overhead expenditures. Selling, general and administrative expenses totaled $14.45 million for the year ended December 31, 2019 compared to $16.84 million for the year ended December 31, 2018. The decrease is a result of the Company not recognizing any intangible amortization cost from favorable contracts in the year ended December 31, 2019 as the Company does not have any additional contract sales, offset by an increase in spending on the Section 232 Petition and related Working Group activities of $0.77 million.

### Impairment of Inventories

For the year ended December 31, 2019, the Company recognized $14.35 million in impairment charges related to inventory to value such inventory at the lower of cost and net realizable value, and included in impairment charges were depreciation expenses of $2.09 million. The impairment of inventories is due to continued lower uranium prices versus our cost to produce at the Nichols Ranch Project of $4.48 million, the decrease in the market price of vanadium recovered from Pond Return of $8.62 million and the decrease in the market price of vanadium in the La Sal stockpile of $1.25 million. For the year ended December 31, 2018, the Company recognized $4.58 million in inventory impairment due to continued lower uranium prices versus our cost to produce at the Nichols Ranch Project. Included in impairment were depreciation expenses of $2.05 million.

### Interest Expense and Other Income and Expenses

#### Interest Expense

Interest expense for the year ended December 31, 2019 was $1.49 million compared with $1.72 million in the prior year due to lower principal amounts from the repayment of Wyoming revenue bond loan and the put option conversion of the Convertible Debentures.

#### Other income and expense

For the year ended December 31, 2019, other income and expense totaled $3.98 million income, net. These amounts primarily consist of a gain on the change in the mark-to-market values of the Convertible Debentures of $0.29 million, a gain on the decrease in value of warrant liabilities of $3.73 million, and interest income of $0.48 million, offset by $0.15 million loss in investments accounted for at fair value and other of $0.32 million.

For the year ended December 31, 2018, other income and expense totaled $2.33 million expense, net. These amounts consist of a loss for the change in fair value of derivative liabilities of $3.47 million and a loss in the mark-to-market values of the Company's Convertible Debentures of $0.61 million, partially offset by interest income of $0.34 million, sales of surplus assets of $0.29 million, gain of assets held for sale of $0.34 million and a $0.77 million increase in the value of investments accounted for at fair value.

### LIQUIDITY AND CAPITAL RESOURCES

### Funding of major business and property acquisitions

Over the past eight years the Company has funded major business and property acquisitions with capital provided by issuances of its Common Shares. In 2012, we acquired Titan Uranium Inc. and the U.S. Mining Division of Denison Mines Corp., in 2013 we acquired Strathmore Minerals Corp, in 2015 we acquired Uranerz and in 2016 we acquired Mesteña, each in exchange for newly issued shares.

We intend to continue to acquire assets utilizing Common Shares when we can do so under attractive terms.

### Shares issued for cash

On December 23, 2016, the Company filed a prospectus supplement in both Canada and the United States to its Canadian base shelf prospectus and U.S. registration statement on Form S-3, which enabled the Company, at its discretion from time to time, to sell up to $20 million worth of Common Shares by way of an “at-the-market” offering (the “**ATM”**). On December 29, 2017, the Company filed a prospectus supplement to its U.S. registration statement, qualifying for distribution up to $30.00 million in additional Common Shares under the ATM. On November 5, 2018, the Company filed a prospectus supplement to its U.S. registration statement, qualifying for distribution up to $24.50 million in aggregate Common Shares under the ATM. Then, on the same date, the Company filed a base shelf prospectus whereby the Company may sell any combination of the “Securities” as defined thereunder in one or more offerings up to an initial aggregate offering amount of $150.00 million. On May 5, 2019, the prospectus supplement to its U.S. registration statement expired, and was replaced on May 7, 2019 by a new prospectus supplement in the same amount, qualifying for distribution up to $24.50 million in aggregate Common Shares under the ATM. On December 31, 2019, the Company filed a prospectus supplement to its U.S. registration statement, qualifying for distribution up to $30.00 million in additional Common Shares under the ATM. On December 31, 2020, the Company filed a prospectus supplement to its U.S. registration statement, qualifying for distribution up to $35.00 million in additional Common Shares under the ATM.

On February 20, 2020, the Company closed a bought deal public offering of common shares made pursuant to an underwriting agreement dated February 13, 2020 between the Company and a syndicate of underwriters led by Cantor Fitzgerald & Co. as lead underwriter and sole book-runner, and H.C. Wainwright & Co., LLC, Eight Capital, Haywood Securities Inc. and Roth Capital Partners, LLC (the "**Offering**"). Pursuant to the Offering, the Company issued an aggregate of 11,300,000 common shares at a price of $1.47 per share for gross proceeds of $16.61 million. The Company received net proceeds, after commissions and fees, of $15.14 million from the Offering (see “*Note 12 to the Financial Statements: Capital Stock”).*

From January 1, 2021 through March 18, 2021, the Company issued 5.50 million Common Shares at a weighted-average price of $5.53 for net proceeds of $29.70 million using the ATM.

### Working capital at December 31, 2020 and future requirements for funds

At December 31, 2020, the Company had working capital of $40.16 million, including $20.17 million in cash, $2.25 million of marketable securities, approximately 690,700 pounds of uranium finished goods inventory and approximately 1,672,000 pounds of vanadium finished goods inventory. The Company believes it has sufficient cash and resources to carry out its business plan for at least the next twelve months.

The Company is actively focused on its forward-looking liquidity needs, especially in light of the current depressed uranium markets. The Company is evaluating its ongoing fixed cost structure as well as decisions related to project retention, advancement and development. If current uranium prices persist for any extended period of time, the Company will likely be required to raise capital or take other measures to fund its ongoing operations. Significant development activities, if warranted, will require that we arrange for financing in advance of planned expenditures. In addition, we expect to continue to augment our current financial resources with external financing as our long-term business needs require. We cannot provide any assurance that we will pursue any of these transactions or that we will be successful in completing them on acceptable terms or at all.

The Company manages liquidity risk through the management of its working capital and its capital structure.

### Cash and cash flows

#### Year ended December 31, 2020

Cash, cash equivalents and restricted cash were $40.99 million at December 31, 2020, compared to $32.89 million at December 31, 2019. The increase of $8.09 million was due primarily to cash provided by financing activities of $36.58 million, cash provided by investing activities of $3.58 million, offset by cash used in operating activities of $32.18 million and loss on foreign exchange on cash held in foreign currencies of $0.11 million.

Net cash used in operating activities of $32.18 million is comprised of the net loss of $27.87 million for the period adjusted for non-cash items and for changes in working capital items. Significant items not involving cash were $2.70 million of depreciation and amortization of property, plant and equipment, $1.64 million impairment on inventory, share-based compensation expense of $2.60 million, a $5.44 million change in warrant liabilities, accretion of asset retirement obligation (“**ARO”**) of $1.91 million, offset by a revision of ARO of $7.85 million, unrealized foreign exchange gain of $1.05 million, other non-cash expenses of $0.71 million and a $0.16 million change in value of the Convertible Debentures. Other items include an increase in inventories of $6.10 million and a decrease in accounts payable and accrued liabilities of $3.08 million, partially offset by a decrease in trade and other receivables of $0.19 million and a decrease in prepaid expenses and other assets of $0.15 million.

Net cash provided by investing activities was $3.58 million comprised of $4.21 million cash received from maturities of marketable securities partially offset by $0.63 million cash used for the purchase of mineral properties and property, plant and equipment.

Net cash provided by financing activities totaled $36.58 million consisting of $52.39 million net proceeds from the issuance of Common Shares from a public offering and the issuance of shares under the Company's ATM facility, $0.49 million cash received from exercise of stock options, and $0.13 million cash received from non-controlling interest, partially offset by $16.02 million to repay loans and borrowings and $0.42 million cash paid to fund employee income tax withholding due upon vesting of restricted stock units.

#### Year ended December 31, 2019

Cash, cash equivalents and restricted cash were $32.89 million at December 31, 2019, compared to $34.29 million at December 31, 2018. The decrease of $1.40 million was due primarily to cash provided by financing activities of $20.36 million, cash provided by investing activities of $22.58 million, offset by cash used in operating activities of $44.38 million and loss on foreign exchange on cash held in foreign currencies of $0.04 million.

Net cash used in operating activities of $44.38 million is comprised of the net loss of $38.09 million for the period adjusted for non-cash items and for changes in working capital items. Significant items not involving cash were $1.21 million of depreciation and amortization of property, plant and equipment, $14.35 million impairment on inventory, share-based compensation expense of $3.77 million, accretion of asset retirement obligation of $1.93 million, other non-cash expenses of

$2.31 million, unrealized foreign exchange loss of $0.08 million, a decrease in prepaid expenses and other assets of $0.01 million, offset by an increase in inventories of $18.53 million, a decrease in trade and other receivables of $0.06 million, a decrease in accounts payable and accrued liabilities of $3.20 million, $3.73 million change in warrant liabilities, $0.29 million change in value of the Convertible Debentures, non-cash standby costs of $1.42 million and changes in deferred revenue of $2.72 million.

Net cash provided by investing activities was $22.58 million related to cash received from the sale and maturities of marketable securities.

Net cash provided by financing activities totaled $20.36 million consisting of $19.68 million proceeds from the issuance of stock using the Company’s ATM offering, $0.80 million in proceeds from notes payable and $0.15 million cash received from exercise of stock options, partially offset by $0.32 million to repay loans and borrowings.

### Off-Balance Sheet Arrangements

We have no off-balance sheet arrangements required to be disclosed in this annual report on Form 10-K.

### Contractual Obligations

The following table summarizes our contractual obligations as of December 31, 2020.

|  | Payments Due by Period - $000 Total | Less than 1 year | 1 - 3 years | 3 - 5 years | More than 5 years |
| --- | ---: | ---: | ---: | ---: | ---: |
| Operating lease obligations | $841 | $343 | $498 | $— | $— |
| Decommissioning liabilities (undiscounted) | 41,953 | 131 | 2,280 | 13,469 | 26,073 |
| **Total contractual obligations** | $42,794 | $474 | $2,778 | $13,469 | $26,073 |

In addition, the Company entered into commitments with federal and state agencies and private individuals to lease surface and mineral rights. These leases are renewable annually and are expected to total $1.51 million for the year ended December 31, 2021.

### Critical accounting estimates and judgments

The preparation of these consolidated financial statements in accordance with U.S. GAAP requires the use of certain critical accounting estimates and judgments that affect the amounts reported. It also requires management to exercise judgment in applying the Company’s accounting policies. These judgments and estimates are based on management’s best knowledge of the relevant facts and circumstances taking into account previous experience. Although the Company regularly reviews the estimates and judgments made that affect these financial statements, actual results may be materially different.

Significant estimates made by management include:

#### a. Exploration Stage

SEC Industry Guide 7 defines a reserve as “that part of a mineral deposit which could be economically and legally extracted or produced at the time of the reserve determination.” The classification of a reserve must be evidenced by a bankable feasibility study using the latest three-year price average. While the Company has established the existence of mineral resources and has successfully extracted and recovered saleable uranium from certain of these resources, the Company has not established proven or probable reserves, as defined under SEC Industry Guide 7, for these operations or any of its uranium projects. As a result, the Company is in the Exploration Stage as defined under Industry Guide 7. Furthermore, the Company has no plans to establish proven or probable reserves for any of its uranium projects.

While in the Exploration Stage, among other things, the Company must expense all amounts that would normally be capitalized and subsequently depreciated or depleted over the life of the mining operation on properties that have proven or probable reserves. Items such as the construction of wellfields and related header houses, additions to our recovery facilities and advancement of properties will all be expensed in the period incurred. As a result, the Company’s consolidated financial statements may not be directly comparable to the financial statements of mining companies in the development or production stages.

#### b. Resource estimates utilized

The Company utilizes estimates of its mineral resources based on information compiled by appropriately qualified persons. The information relating to the geological data on the size, depth and shape of the deposits requires complex geological judgments to interpret the data. The estimation of future cash flows related to resources is based upon factors such as estimates of future uranium prices, future construction and operating costs along with geological assumptions and judgments made in estimating the size and grade of the resource. Changes in the mineral resource estimates may impact the carrying value of mining and recovery assets, goodwill, reclamation and remediation obligations and depreciation and impairment.

#### c. Depreciation of mining and recovery assets acquired

For mining and recovery assets actively extracting and recovering uranium we depreciate the acquisition costs of the mining and recovery assets on a straight-line basis over our estimated lives of the mining and recovery assets. The process of estimating the useful life of the mining and recovery assets requires significant judgment in evaluating and assessing available geological, geophysical, engineering and economic data, projected rates of extraction and recovery, estimated commodity price forecasts and the timing of future expenditures, all of which are, by their very nature, subject to interpretation and uncertainty.

Changes in these estimates may materially impact the carrying value of the Company’s mining and recovery assets and the recorded amount of depreciation.

#### d. Impairment testing of mining and recovery assets

The Company undertakes a review of the carrying values of its mining and recovery assets whenever events or changes in circumstances indicate that their carrying values may exceed their estimated net recoverable amounts determined by reference to estimated future operating results and net cash flows. An impairment loss is recognized when the carrying value of a mining or recovery asset is not recoverable based on this analysis. In undertaking this review, the management of the Company is required to make significant estimates of, among other things, future production and sale volumes, forecast commodity prices, future operating and capital costs and reclamation costs to the end of the mining asset’s life. These estimates are subject to various risks and uncertainties, which may ultimately have an impact on the expected recoverability of the carrying values of mining and recovery assets.

#### e. Asset retirement obligations

Asset retirement obligations are recorded as a liability when an asset that will require reclamation and remediation is initially acquired. For disturbances created on a property owned that will require future reclamation and remediation the Company records asset retirement obligations for such disturbance when occurred. The Company has accrued its best estimate of its share of the cost to decommission its mining and milling properties in accordance with existing laws, contracts and other policies. The estimate of future costs involves a number of estimates relating to timing, type of costs, mine closure plans, and review of potential methods and technical advancements. Furthermore, due to uncertainties concerning environmental remediation, the ultimate cost of the Company’s decommissioning liability could differ from amounts provided. The estimate of the Company’s obligation is subject to change due to amendments to applicable laws and regulations and as new information concerning the Company’s operations becomes available. The Company is not able to determine the impact on its financial position, if any, of environmental laws and regulations that may be enacted in the future. Additionally, the expected cash flows in the future are discounted at the Company’s estimated cost of capital based on the periods the Company expects to complete the reclamation and remediation activities. Differences in the expected periods of reclamation or in the discount rates used could have a material difference in the actual settlement of the obligations compared with the amounts provided.

## Market risk

As filed, 3,958 characters.

The Company is exposed to risks associated with commodity prices, interest rates and credit. Commodity price risk is defined as the potential loss that we may incur as a result of changes in the market value of uranium. Interest rate risk results from our debt and equity instruments that we issue to provide financing and liquidity for our business. Credit risk arises from the extension of credit throughout all aspects of our business. Industry-wide risks can also affect our general ability to finance exploration, and development of exploitable resources; such effects are not predictable or quantifiable. Market risk is the risk to the Company of adverse financial impact due to change in the fair value or future cash flows of financial instruments as a result of fluctuations in interest rates and foreign currency exchange rates.

### Commodity Price Risk

The Company is subject to market risk related to the market price of U3O8. All of the Company’s existing long-term contracts expired following the Company’s 2018 deliveries, and all uranium sales after 2018 will be required to be made at spot prices until the Company enters into new long-term contracts at satisfactory prices in the future. Future revenue will be affected by both spot and long-term U3O8 price fluctuations which are beyond our control, including: the demand for nuclear power; political and economic conditions; governmental legislation in uranium producing and consuming countries; and production levels and costs of production of other producing companies. The Company continuously monitors the market to determine its level of extraction and recovery of uranium in the future.

### Interest Rate Risk

The Company is exposed to interest rate risk on its cash equivalents, deposits, and restricted cash. Our interest income is earned in United States dollars and is not subject to interest rate risk. The Company does not use derivatives to manage interest rate risk.

### Currency Risk

The foreign exchange risk relates to the risk that the value of financial commitments, recognized assets or liabilities will fluctuate due to changes in foreign currency rates. The Company does not use any derivative instruments to reduce its exposure to fluctuations in foreign currency exchange rates. As the U.S. Dollar is the functional currency of our U.S. operations, the currency risk has been reduced. We maintain a nominal balance in foreign currency, resulting in a low currency risk relative to our cash balances.

The following table summarizes, in United States dollar equivalents, the Company’s major foreign currency (Cdn$) exposures as of December 31, 2020 ($000):

|  |  |
| --- | ---: |
| Cash and cash equivalents | $4,198 |
| Accounts payable and accrued liabilities | (426) |
| Total | $3,772 |

The table below summarizes a sensitivity analysis for significant unsettled currency risk exposure with respect to our financial instruments as of December 31, 2020 with all other variables held constant. It shows how net income would have been affected by changes in the relevant risk variables that were reasonably possible at that date ($000).

|  | Change for Sensitivity Analysis +1% change in | Increase (Decrease) in Other Comprehensive Income |
| --- | --- | ---: |
| Strengthening net earnings | U.S. dollar | $48 |
|  | -1% change in |  |
| Weakening net earnings | U.S. dollar | $(48) |

### Credit Risk

Credit risk relates to cash and cash equivalents, trade, and other receivables that arise from the possibility that any counterparty to an instrument fails to perform. The Company only transacts with highly-rated counterparties and a limit on contingent exposure has been established for any counterparty based on that counterparty’s credit rating. The Company’s sales are attributable mainly to large utilities. As of December 31, 2020, the Company’s maximum exposure to credit risk was the carrying value of cash and cash equivalents and trade receivables.

## Controls and procedures

As filed, 3,779 characters.

### Evaluation of Disclosure Controls and Procedures

As of the end of the period covered by this Annual Report on Form 10-K, an evaluation was carried out under the supervision of and with the participation of the Company’s management, including the Chief Executive Officer (“**CEO”**) and Chief Financial Officer (“**CFO”**), of the effectiveness of the design and operation of the Company’s disclosure controls and procedures (as defined in Rule 13a – 15(e) and Rule 15d – 15(e) under the Exchange Act). Based on that evaluation, the CEO and the CFO have concluded that as of the end of the period covered by this Annual Report on Form 10-K, the Company’s disclosure controls and procedures were effective in ensuring that: (i) information required to be disclosed by the Company in reports that it files or submits to the SEC under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in applicable rules and forms; and (ii) material information required to be disclosed in its reports filed under the Exchange Act is accumulated and communicated to its management, including its CEO and CFO, as appropriate, to allow for accurate and timely decisions regarding required disclosure.

It should be noted that while the CEO and CFO believe that the Company’s disclosure controls and procedures provide a reasonable level of assurance that they are effective, they do not expect that the Company’s disclosure controls and procedures or internal control over financial reporting will prevent all errors and fraud. A control system, no matter how well conceived or operated, can provide only reasonable, not absolute, assurance that the objectives of the control system are met.

### Management’s Report on Internal Control over Financial Reporting

Management is responsible for establishing and maintaining adequate internal control over financial reporting, as defined in Rule 13a-15(f) under the Exchange Act. The Company’s management has employed a framework consistent with Exchange Act Rule 13a-15(c), to evaluate the Company’s internal control over financial reporting described below. A company’s internal control over financial reporting is a process designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles.

The senior executive officers, including the Company’s CEO and CFO, conducted an evaluation of the effectiveness, design and operation of the Company’s internal control over financial reporting as of December 31, 2020, based on the criteria established in *Internal Control – Integrated Framework* issued by the Committee of Sponsoring Organizations of the Treadway Commission 2013 framework. This evaluation included review of the documentation of controls, evaluation of the design effectiveness of controls, testing of the operating effectiveness of controls and a conclusion on this evaluation. Based on this evaluation, management has concluded that the material weaknesses in internal controls identified in the Company’s Form 10-K for the year ended December 31, 2019 have been remediated and that the Company’s internal control over financial reporting was effective as of December 31, 2020 based on those criteria. This Annual Report does not include an attestation report of our independent registered public accounting firm as it is not required.

### Changes in Internal Control Over Financial Reporting

During the quarter ended December 31, 2020, there were no changes in the Company’s internal control over financial reporting

that materially affected, or are likely to materially affect, the Company’s internal control over financial reporting.

Filed Mar 22, 2021.
Source: SEC EDGAR, the filing index for accession 0001385849-21-000027. Last ingested by Listed: Nov 15, 2026, 02:25 ET. No prices; not investment advice.