Management's discussion and analysis
As filed, 35,797 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
The following discusses our financial position as of March 31, 2022 and the results of our operations for the three months ended March 31, 2022 and should be read in conjunction with other information, including the unaudited Condensed Consolidated Financial Statements and notes included in Part I, Item 1, Financial Information, of this Quarterly Report on Form 10‑Q, the audited consolidated financial statements and accompanying notes to our Annual Report on Form 10‑K for the year ended December 31, 2021, and the information contained under the heading “Risk Factors” in our Annual Report on Form 10‑K for the year ended December 31, 2021 and in Part II, Item 1A below.
Forward-Looking Statements
This Quarterly Report on Form 10‑Q, including the “Management’s Discussion and Analysis of Financial Condition and Results of Operations,” contains forward-looking statements regarding future events and our future results, which are intended to be covered by the safe harbor provision for forward-looking statements provided by the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical facts are statements that could be deemed forward-looking statements. Words such as “achieve,” “anticipate,” “assumes,” “believes,” “continue,” “could,” “estimate,” “expects,” “forecast,” “hope,” “intend,” “may,” “plan,” “potential,” “predict,” “should,” “will,” “would,” variations of such words and similar expressions are intended to identify such forward-looking statements. In addition, any statements that refer to projections of our future financial performance, our anticipated growth and trends in our businesses, and other characterizations of future events or circumstances are forward-looking statements. Although such statements are based on currently available financial and economic data, as well as management’s estimates and expectations, forward-looking statements are inherently uncertain and involve risks and uncertainties that could cause our actual results to differ materially from what may be inferred from the forward-looking statements. Therefore, actual results may differ materially and adversely from those expressed in any forward-looking statements. Factors potentially contributing to such differences include, among others:
- Revisions of estimates of contract risks, revenue or costs; economic factors such as inflation; the timing of new awards; or the pace of project execution, which may result in losses or lower than anticipated profit;
- Unfavorable outcomes of existing or future litigation or dispute resolution proceedings against us or customers (project owners, developers, general contractors, etc.), subcontractors or suppliers, as well as failure to promptly recover significant working capital invested in projects subject to such matters;
- Contract requirements to perform extra work beyond the initial project scope, which has and in the future could result in disputes or claims and adversely affect our working capital, profits and cash flows;
- A significant slowdown or decline in economic conditions;
- Increased competition and failure to secure new contracts;
- Risks and other uncertainties associated with assumptions and estimates used to prepare our financial statements;
- Failure to meet contractual schedule requirements, which could result in higher costs and reduced profits or, in some cases, exposure to financial liability for liquidated damages and/or damages to customers, as well as damage to our reputation;
- Inability to attract and retain our key officers, and to adequately plan for their succession, and hire and retain personnel required to execute and perform on our contracts;
- The COVID-19 pandemic, which has adversely impacted, and could continue to adversely impact, our business, financial condition and results of operations by, among other things, delaying the timing of project bids and/or awards and the timing of dispute resolutions and associated collections;
- Risks related to our international operations, such as uncertainty of U.S. Government funding, as well as economic, political, regulatory and other risks, including risks of loss due to acts of war, civil unrest, security issues, labor conditions, corruption and other unforeseeable events in countries where we do business, resulting in unanticipated losses;
- Possible systems and information technology interruptions and breaches in data security and/or privacy;
- Client cancellations of, or reductions in scope under, contracts reported in our backlog;
- Failure of our joint venture partners to perform their venture obligations, which could impose additional financial and performance obligations on us, resulting in reduced profits or losses and/or reputational harm;
- The impact of inclement weather conditions on projects;
- Decreases in the level of government spending for infrastructure and other public projects;
- Risks related to government contracts and related procurement regulations;
- Securities litigation and/or shareholder activism;
- Violations of the U.S. Foreign Corrupt Practices Act and similar worldwide anti-bribery laws;
- Adverse health events, such as an epidemic or another pandemic;
- Physical and regulatory risks related to climate change;
- Failure to meet our obligations under our debt agreements;
- Downgrades in our credit ratings;
- Impairment of our goodwill or other indefinite-lived intangible assets; and
- The exertion of influence over the Company by our chairman and chief executive officer due to his position and significant ownership interest.
Executive Overview
COVID-19 Update
Since its onset in early 2020, the COVID-19 pandemic has caused occasional temporary shortages in available manpower, reductions in field labor productivity, other inefficiencies, delays to project schedules and deferrals of project execution. As a result, we continue to incur incremental costs, much of which we are seeking to recover from our customers as allowed by contractual terms. The relief sought from customers, together with certain incremental project opportunities that resulted from the pandemic, has helped to mitigate the pandemic's negative impact on our financial results. In addition, we have experienced delays in certain legal proceedings, as various courts and arbitrators process a large backlog of cases that were impacted by the pandemic. The COVID-19 pandemic has also hindered the Company’s ability to resolve unapproved work, resulting in the need for the Company to temporarily fund certain project costs that historically would have been promptly negotiated, billed to and collected from customers. These delays in resolving and recovering on such claims have adversely affected our liquidity and financial results since the onset of the pandemic. However, in the latter part of 2021 and the first quarter of 2022, we began to see the scheduling of settlement conferences and trial dates and made progress in resolving certain project disputes and change orders.
Throughout 2020 and much of 2021, the pandemic also adversely affected the volume and timing of our new awards, which has negatively impacted our backlog and operating results. The resulting negative impact in the first quarter of 2022 is expected to continue due to previously limited bidding and proposal opportunities, as well as the relatively lower volume of new awards in 2020 and much of 2021. In addition, many of our state and local government customers’ revenue sources have been negatively impacted by the pandemic due to a reduction of commuter and business travel, including curtailed ridership on mass-transit systems (buses, subways, trains, etc.), travel on commercial airlines and driving by the general public. These impacts have resulted in reduced fare and toll collections, lower fuel tax receipts and reduced airport and other facility usage fees. The significant revenue reductions experienced by some of our customers have adversely impacted their ability to pay the Company on a timely basis for amounts due, although these impacts have begun to moderate. The potential for continued or new pandemic-related delays in project bids and awards could result in lower-than-expected revenue and earnings until such time as the substantial funding relating to the recently enacted federal infrastructure legislation is distributed to existing and potential customers.
Due to the continued fluidity of the COVID-19 pandemic, uncertainties as to its scope and duration, and ongoing changes in the way that governments, businesses and individuals respond to the pandemic, the Company is unable at this time to accurately predict the pandemic’s future impact on the Company’s business, results of operations, financial condition or liquidity.
Operating Results
Consolidated revenue for the three months ended March 31, 2022 was $1.0 billion compared to $1.2 billion for the same period in 2021. The decrease was primarily due to reduced project execution activities on a completed technology project and a mass-transit project that is nearing completion, both in California, as well as the impact of an adverse legal ruling on a dispute related to a completed Civil segment bridge project in New York and the temporary unfavorable impact from the successful negotiation of certain change orders on another Civil segment mass-transit project in California. The decrease was also due to lower project execution activities in the Northeast, partially offset by certain projects in California and the Midwest. The COVID-19 pandemic resulted in delays in new awards, which negatively impacted revenue for the first quarter of both 2022 and 2021.
Loss from construction operations for the first quarter of 2022 was $9.9 million compared to income from construction operations of $49.7 million for the same period in 2021. The change was partially attributable to the impacts of the above-mentioned adverse legal ruling, which resulted in a non-cash, pre-tax charge of $25.5 million. The decrease was also driven by a temporary unfavorable impact to current-period earnings of $17.6 million on a Civil segment mass-transit project in California, as a result of the successful negotiation of significant lower margin (and lower risk) change orders that increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage. This temporary reduction to earnings is expected to reverse itself over the remaining life of the project. In addition, the decrease was also attributable to the revenue decline discussed above.
The effective tax rate was 17.1% for the three months ended March 31, 2022 compared to 21.7% for the comparable period in 2021. See Corporate, Tax and Other Matters below for a discussion of the change in the effective tax rate.
The loss per common share for the three months ended March 31, 2022 was $0.42 compared to diluted earnings per common share of $0.31 for the same period in 2021. The loss per common share for the first quarter of 2022 compared to the earnings per common share for the same period in 2021 was primarily due to the factors discussed above that led to the change in income (loss) from construction operations.
Consolidated new awards for the three months ended March 31, 2022 totaled $996 million, up modestly compared to $959 million for the same period in 2021. The Civil and Building segments were the primary contributors to the new award activity in the first quarter of 2022. The most significant new awards in the first quarter of 2022 included a $260 million gas pipeline project in British Columbia, Canada, and $121 million of additional funding for a mass-transit project in California, both in the Civil segment; and four Building segment projects in California totaling $251 million.
Consolidated backlog as of March 31, 2022 was $8.3 billion, up slightly compared to $8.2 billion as of December 31, 2021. As of March 31, 2022, the mix of backlog by segment was approximately 56% for Civil, 28% for Building and 16% for Specialty Contractors.
The following table presents the Company’s backlog by business segment, reflecting changes from December 31, 2021 to March 31, 2022:
(in millions)
| Backlog at December 31, 2021 | New Awards(a) | Revenue Recognized | Backlog at March 31, 2022(b) | |
|---|---|---|---|---|
| Civil | $4,553.5 | $447.0 | $(390.9) | $4,609.6 |
| Building | 2,308.9 | 325.2 | (330.6) | 2,303.5 |
| Specialty Contractors | 1,373.2 | 224.2 | (230.7) | 1,366.7 |
| Total | $8,235.6 | $996.4 | $(952.2) | $8,279.8 |
(a) New awards consist of the original contract price of projects added to backlog plus or minus subsequent changes to the estimated total contract price of existing contracts.
(b) Backlog may differ from the transaction prices allocated to the remaining performance obligations as disclosed in Note 2 of the Notes to Condensed Consolidated Financial Statements. Such differences relate to the timing of executing a formal contract or receiving a notice to proceed. More specifically, backlog sometimes may include awards for which a contract has not yet been executed or a notice to proceed has not been issued, but for which there are no remaining major uncertainties that the project will proceed (e.g., adequate funding is in place).
The outlook for the Company’s growth over the next several years remains favorable, but the impact of the COVID-19 pandemic could again adversely affect performance and operations, and the amount and timing of new work awarded. In addition, the Company’s growth could be impacted by future project delays or the timing of project awards, commencements, ramp-up activities and completions. We anticipate that we will continue to win our share of significant new awards resulting from long-term capital spending plans by state, local and federal customers, as well as limited competition for some of the largest project opportunities.
In elections over the past several years, voters in numerous states approved dozens of long-term transportation funding measures totaling approximately $200 billion in long-term funding. The largest of these was in Los Angeles County, where Measure M, a half-cent sales tax increase, was approved and is expected to generate $120 billion of funding over 40 years. In addition, California's Senate Bill 1, which was signed into law in 2017, is providing an average of $5.4 billion annually through 2027 for various transportation, mass-transit and bridge projects. Despite recent increases, which had been anticipated, interest rates still remain relatively attractive, which may be conducive to continued and increased spending on infrastructure projects. However, if borrowing rates continue to increase significantly, they could reach levels that may begin to negatively impact infrastructure demand, although this is more likely to impact Building segment projects, as those projects tend to be more directly correlated to economic conditions.
The Infrastructure Investment and Jobs Act (“IIJA”) was enacted into law on November 15, 2021, and it provides for $1.2 trillion of federal infrastructure funding, including $550 billion in new spending for improvements to the country’s surface-transportation network and enhancements to core infrastructure. The IIJA marks the largest federal investment in public transit ever, the single largest dedicated bridge investment since the construction of the interstate highway system and the largest federal investment in passenger rail since the creation of Amtrak, all in addition to providing for regular annual spending for numerous infrastructure projects. This significant incremental funding is anticipated to be spent over the next 10 years, and much of it is allocated for investment in end markets that are directly aligned with the Company’s market focus. Accordingly, the Company believes that this significant level of sustained, incremental funding will favorably impact the Company’s current work and prospective opportunities over the next decade once it begins flowing to customers.
The Company had certain large Civil segment projects in the Northeast that were completed or were nearing completion in 2021. The Company is pursuing several large prospective projects in various locations, including the Northeast, the West Coast and Guam, which are expected to be bid and/or awarded in 2022 and 2023. However, the timing and magnitude of revenue contributions from these prospective projects may not fully offset revenue reductions associated with the projects that have been completed or are nearing completion. In addition, as discussed above, the COVID-19 pandemic has resulted in, and could again result in, delays in the bidding and awarding of certain projects that the Company is pursuing, which may further delay large, new revenue streams.
For a more detailed discussion of operating performance of each business segment, corporate general and administrative expenses and other items, see Results of Segment Operations, Corporate, Tax and Other Matters and Liquidity and Capital Resources below.
Results of Segment Operations
The results of our Civil, Building and Specialty Contractors segments are discussed below.
Civil Segment
Revenue and income (loss) from construction operations for the Civil segment are summarized as follows:
(in millions)
| Three Months Ended March 31, 2022 | 2021 | |
|---|---|---|
| Revenue | $390.8 | $475.6 |
| Income (loss) from construction operations | (1.0) | 50.1 |
Revenue for the three months ended March 31, 2022 decreased 18% compared to the same period in 2021. The largest contributing factor to the decrease was reduced project execution activities on a mass-transit project in California that is nearing completion. The decrease was also due to the impact of the adverse legal ruling on a dispute related to a bridge project in New York and the temporary unfavorable impact from the successful negotiation of certain change orders on another Civil segment mass-transit project in California. Revenue for the first quarters of 2022 and 2021 also was reduced by the aforementioned COVID-19 impacts.
Loss from construction operations for the three months ended March 31, 2022 was $1.0 million compared to income from construction operations of $50.1 million for the same period in 2021. The decrease was primarily due to the impact of the aforementioned adverse legal ruling on a dispute related to a bridge project in New York that resulted in a non-cash, pre-tax charge of $25.5 million, as well as the aforementioned temporary unfavorable impact of $17.6 million on a Civil segment mass-transit project in California, both as discussed in the section entitled Executive Overview. The decrease was also a result of the revenue reductions discussed above.
Operating margin was (0.2)% and 10.5% for the three months ended March 31, 2022 and 2021, respectively. The operating margin decrease was due to the above-mentioned factors that drove the changes in revenue and income from construction operations.
New awards in the Civil segment totaled $447 million for the first quarter of 2022 compared to $457 million for the same period in 2021. The most significant new awards in the first quarter of 2022 included a $260 million gas pipeline project in British Columbia, Canada, and $121 million of additional funding for a mass-transit project in California. The COVID-19 pandemic has resulted in significant revenue shortfalls for many state and local government agencies since 2020, and it could continue to cause deferrals or cancellations of certain new projects, depending on the allocation and prioritization of state and local funding, as well as the availability, timing and magnitude of funding from the federal government, including anticipated funding from the recently enacted IIJA.
Backlog for the Civil segment was $4.6 billion as of March 31, 2022 compared to $4.8 billion as of March 31, 2021, with the modest decline due to revenue that exceeded the volume of new awards over the comparative period, as new awards for the segment have been negatively impacted by the COVID-19 pandemic. The segment continues to experience strong demand reflected in a large, multi-year pipeline of prospective projects, supported by substantial anticipated funding from various voter- approved transportation measures and the IIJA, and by public agencies’ long-term spending plans. The Civil segment is well-positioned to capture its share of these prospective projects, but the timing of new awards remains uncertain.
Building Segment
Revenue and income from construction operations for the Building segment are summarized as follows:
(in millions)
| Three Months Ended March 31, 2022 | 2021 | |
|---|---|---|
| Revenue | $330.6 | $407.2 |
| Income from construction operations | 9.5 | 11.2 |
Revenue for the three months ended March 31, 2022 decreased 19% compared to the same period in 2021, primarily due to reduced project execution activities on various projects in California that are substantially complete, partially offset by contributions from certain newer projects in California. Revenue for the first quarters of 2022 and 2021 also was reduced by the aforementioned COVID-19 impacts.
Income from construction operations for the three months ended March 31, 2022 decreased 16% compared to the same period in 2021. The decrease was primarily due to the revenue reductions mentioned above.
Operating margin was 2.9% for the three months ended March 31, 2022, essentially level compared to 2.8% for the same period in 2021.
New awards in the Building segment totaled $325 million for the first quarter of 2022 compared to $344 million for the same period in 2021. The most significant new awards in the first quarter of 2022 included two health care projects, an educational project and an entertainment venue project, all in California, totaling $251 million.
Backlog for the Building segment was $2.3 billion as of March 31, 2022 compared to $1.6 billion as of March 31, 2021. The increase was primarily driven by two large new awards that were booked into backlog in the third quarter of 2021. The Building segment continues to have a large volume of prospective projects across various end markets and geographic locations. We expect continued strong demand as economic conditions remain conducive to customer spending on new building facilities and renovations to existing buildings, supported by a still relatively favorable interest rate environment. However, the COVID-19 pandemic has resulted in, and could again result in, reduced demand for our building construction services, as could significantly higher interest rates.
Specialty Contractors Segment
Revenue and income (loss) from construction operations for the Specialty Contractors segment are summarized as follows:
(in millions)
| Three Months Ended March 31, 2022 | 2021 | |
|---|---|---|
| Revenue | $230.7 | $324.8 |
| Income (loss) from construction operations | (3.9) | 1.3 |
Revenue for the three months ended March 31, 2022 decreased 29% compared to the same period in 2021. The decrease was principally driven by reduced project execution activities on various electrical and mechanical projects in the Northeast. Revenue for the first quarters of 2022 and 2021 also was reduced by the aforementioned COVID-19 impacts.
Loss from construction operations for the three months ended March 31, 2022 was $3.9 million compared to income from construction operations of $1.3 million for the comparable period in 2021. The change was primarily due to lower profitability and reduced project execution activities in the Northeast, including the electrical and mechanical components of a transportation project that is nearing completion.
Operating margin was (1.7)% and 0.4% for the three months ended March 31, 2022 and 2021, respectively. The change in operating margin was principally due to the aforementioned factors that drove the changes in revenue and income (loss) from construction operations.
New awards in the Specialty Contractors segment totaled $224 million for the first quarter of 2022 compared to $158 million for the same period in 2021. The COVID-19 pandemic has resulted in, and could continue to result in, reduced demand from certain commercial and government customers that have been experiencing funding constraints.
Backlog for the Specialty Contractors segment was $1.4 billion as of March 31, 2022 compared to $1.7 billion as of March 31, 2021, with the decline due to revenue that exceeded the volume of new awards over the comparative period, as new awards for the segment have been negatively impacted by the COVID-19 pandemic. The Specialty Contractors segment continues to be increasingly focused on servicing the Company’s backlog of large Civil and Building segment projects, particularly in the Northeast and California. In addition, the segment remains well-positioned to capture its share of new projects for external customers, leveraging the size and scale of our business units that operate in New York, Texas, Florida and California and the strong reputation held by these business units for high-quality work on large, complex projects.
Corporate, Tax and Other Matters
Corporate General and Administrative Expenses
Corporate general and administrative expenses were $14.5 million and $12.9 million during the three months ended March 31, 2022 and 2021, respectively. The increase in the three months ended March 31, 2022 was primarily due to higher compensation-related expenses compared to the same period in 2021.
Other Income, Net, Interest Expense and Income Tax (Expense) Benefit
(in millions)
| Three Months Ended March 31, 2022 | 2021 | |
|---|---|---|
| Other income, net | $3.7 | $0.2 |
| Interest expense | (16.5) | (17.8) |
| Income tax (expense) benefit | 3.9 | (7.0) |
Other income, net improved by $3.5 million for the three months ended March 31, 2022 compared to the same period in 2021. The improvement in the 2022 period was primarily due to interest earned on federal income tax receivable balances.
Interest expense decreased $1.3 million for the three months ended March 31, 2022 compared to the same period in 2021. The decrease in the 2022 period was primarily due to the absence of amortization of discount and debt issuance costs on convertible notes that were repaid in 2021.
The effective tax rate was 17.1% and 21.7% for the three months ended March 31, 2022 and 2021, respectively. The lower effective income tax rate for the three months ended March 31, 2022 was primarily due to earnings attributable to non-controlling interests, for which income taxes are not the responsibility of the Company, and share-based compensation adjustments in the 2022 period. For a further discussion of income taxes, refer to Note 6 of the Notes to Condensed Consolidated Financial Statements.
Liquidity and Capital Resources
Liquidity is provided by available cash and cash equivalents, cash generated from operations, credit facilities and access to capital markets. We have a committed line of credit totaling $175 million, which may be used for revolving loans, letters of credit and/or general purposes. We believe that cash generated from operations, along with our unused credit capacity of $134 million and available cash balances as of March 31, 2022, will be sufficient to fund any working capital needs and debt maturities for the next 12 months and beyond, provided that we are not adversely impacted by unanticipated future events, including further impacts related to the COVID-19 pandemic as discussed above in Executive Overview - COVID-19 Update. Liquidity has been, and could continue to be, adversely impacted by our inability to collect cash due to the follow-on impacts of COVID-19, which have constrained certain customers’ funding sources and delayed their ability to make payments on approved contract work. In addition, as discussed above in Executive Overview - COVID-19 Update, the COVID-19 pandemic delayed court and arbitration schedules and also hindered the Company’s ability to resolve certain unapproved work. We believe that future funding from the IIJA and increasing revenue to government customers as travel and commuting levels rise, as discussed above, could offset or mitigate future negative impacts from COVID-19, though it remains difficult to predict any of these factors. Furthermore, the bottleneck of accumulated court and arbitration proceedings that has grown during the pandemic has recently begun to alleviate with certain settlement conferences and trial dates now scheduled. In addition, certain disputes and related collection delays were resolved during the latter part of 2021 and the first quarter of 2022. We experienced substantially improved operating cash flows in the first quarter of 2022, and also anticipate improved operating cash generation for the remainder of 2022 compared to 2021, based on projected cash collections, both from project execution activities and the resolution of various other outstanding claims and change orders.
Cash and Working Capital
Cash and cash equivalents were $316.5 million as of March 31, 2022 compared to $202.2 million as of December 31, 2021. Cash immediately available for general corporate purposes was $75.8 million and $60.2 million as of March 31, 2022 and December 31, 2021, respectively, with the remainder being amounts held by our consolidated joint ventures and also our proportionate share of cash held by our unconsolidated joint ventures. Cash held by our joint ventures was available only for joint venture-related uses, including distributions to joint venture partners. In addition, our restricted cash and restricted investments totaled $89.9 million as of March 31, 2022 compared to $93.6 million as of December 31, 2021. Restricted cash and restricted investments at March 31, 2022 were primarily held to secure insurance-related contingent obligations.
During the three months ended March 31, 2022, net cash provided by operating activities was $120.7 million, which was the largest first-quarter operating cash flow since the merger between Tutor-Saliba Corporation and Perini Corporation in 2008. This increase was substantially due to a decrease in investments in project working capital. The decrease in investments in project working capital was primarily due to an improved collection cycle, as reflected by increases in billings in excess of costs and estimated earnings, and decreases in accounts receivable and retention receivable. During the three months ended March 31, 2021, net cash used in operating activities was $46.7 million, due primarily to investments in project working capital partially offset by cash generated from earnings sources. The increase in working capital for the first three months of 2021 primarily reflects a decrease in accounts payable due to timing of payments to suppliers and subcontractors and a decrease in accrued expenses and other current liabilities, partially offset by a decrease in accounts receivable due to the timing of collections.
Cash flow from operating activities increased $167.5 million when comparing the first three months of 2022 with the same period in 2021. The significant increase was primarily driven by an improved cash collection cycle, including collections associated with the recent resolution of certain project change orders that were previously disputed and that had previously required a use of cash. The increase in cash flow from operating activities was also due to an increase in accounts payable compared to a decrease in the prior year due to timing of payments to vendors and subcontractors. Despite the increase in accounts payable in the first quarter of 2022, the balance as of March 31, 2022 was $157.2 million lower compared to the balance as of March 31, 2021.
Net cash used in investing activities during the first three months of 2022 was $14.9 million primarily due to the acquisition of property and equipment for projects totaling $12.0 million, as well as net cash used in investment transactions of $4.3 million. Net cash used in investing activities during the first three months of 2021 was $5.4 million primarily due to the acquisition of property and equipment for projects totaling $9.8 million, partially offset by net cash provided from investment transactions of $4.0 million.
Net cash provided by financing activities was $4.1 million for the first three months of 2022, which was primarily driven by $8.6 million of net proceeds from borrowings, partially offset by $3.5 million of net distributions to noncontrolling interests. Net cash provided by financing activities for the comparable period in 2021 was $1.1 million.
At March 31, 2022, we had working capital of $2.1 billion, a ratio of current assets to current liabilities of 2.12 and a ratio of debt to equity of 0.61, compared to working capital of $2.1 billion, a ratio of current assets to current liabilities of 2.17 and a ratio of debt to equity of 0.59 at December 31, 2021.
Debt
2020 Credit Agreement
On August 18, 2020, the Company entered into a credit agreement (the “2020 Credit Agreement”) with BMO Harris Bank N.A., as Administrative Agent, Swing Line Lender and L/C Issuer and other lenders. The 2020 Credit Agreement provides for a $425.0 million term loan B facility (the “Term Loan B”) and a $175.0 million revolving credit facility (the “2020 Revolver”), with sublimits for the issuance of letters of credit and swing line loans up to the aggregate amounts of $75.0 million and $10.0 million, respectively. The Term Loan B will mature on August 18, 2027 and the 2020 Revolver will mature on August 18, 2025, in each case, unless any of the 2017 Senior Notes are outstanding on January 30, 2025 (which is 91 days prior to the maturity of the 2017 Senior Notes), in which case, both the Term Loan B and the 2020 Revolver will mature on January 30, 2025 (subject to certain further exceptions). For more information regarding the terms of our 2020 Credit Agreement, refer to Note 8 of the Notes to Condensed Consolidated Financial Statements.
The table below presents our actual and required consolidated first lien net leverage ratio under the 2020 Credit Agreement for the period, which is calculated on a rolling four-quarter basis:
| Trailing Four Fiscal Quarters Ended | ||
|---|---|---|
| March 31, 2022 | ||
| Actual | Required | |
| First lien net leverage ratio | 1.35 to 1.00 | ≤ 2.25 : 1.00 |
As of March 31, 2022, we were in compliance and expect to continue to be in compliance with the covenants under the 2020 Credit Agreement.
Contractual Obligations
There have been no material changes in our contractual obligations from those described in our Annual Report on Form 10‑K for the year ended December 31, 2021.
Critical Accounting Policies and Estimates
Our significant accounting policies are described in Note 1 of the Notes to Consolidated Financial Statements included in our Annual Report on Form 10‑K for the year ended December 31, 2021. Our critical accounting estimates are also identified and discussed in Part II, Item 7 of our Annual Report on Form 10‑K for the year ended December 31, 2021.
Recently Issued Accounting Pronouncements
There were no new accounting pronouncements issued by the Financial Accounting Standards Board during the three months ended March 31, 2022 and through the date of filing of this report that had or are expected to have a material impact on the Company’s financial position, results of operations or cash flows.
Market risk
As filed, 176 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
There has been no material change in our exposure to market risk from that described in Part II, Item 7A of our Annual Report on Form 10‑K for the year ended December 31, 2021.
Controls and procedures
As filed, 1,542 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Disclosure Controls and Procedures
An evaluation of the effectiveness of the design and operation of our disclosure controls and procedures as defined by Rule 13a-15(e) under the Securities Exchange Act of 1934, as amended (“Exchange Act”), as of the end of the period covered by this Quarterly Report on Form 10‑Q was made under the supervision and with the participation of our management, including our Chief Executive Officer and Chief Financial Officer. Based upon that evaluation, the Chief Executive Officer and Chief Financial Officer concluded that the Company’s disclosure controls and procedures (a) were effective to ensure that information we are required to disclose in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in Securities and Exchange Commission rules and forms and (b) include, without limitation, controls and procedures designed to ensure that information required to be disclosed by us in reports filed or submitted under the Exchange Act is accumulated and communicated to our management, including our Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.
Changes in Internal Control Over Financial Reporting
There were no changes in our internal control over financial reporting during the period covered by this report that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.
Risk factors
As filed, 140 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
There have been no material changes to our risk factors as disclosed in our Annual Report on Form 10-K for the year ended December 31, 2021.
Figures reported in this filing
Standardized line items from the XBRL in this filing, for the period ended 2022-03-31. Comparative periods it repeats are left out.
| Line item | Period | Value | XBRL concept |
|---|---|---|---|
| Revenue | 3 months2022-01-01 to 2022-03-31 | $952.2m | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Cost of revenue | 3 months2022-01-01 to 2022-03-31 | $901.8m | us-gaap:CostOfGoodsAndServicesSold |
| Gross profit | 3 months2022-01-01 to 2022-03-31 | $50.3m | us-gaap:GrossProfit |
| Operating income | 3 months2022-01-01 to 2022-03-31 | −$9.9m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months2022-01-01 to 2022-03-31 | $16.5m | us-gaap:InterestExpense |
| Income tax | 3 months2022-01-01 to 2022-03-31 | −$3.9m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months2022-01-01 to 2022-03-31 | −$21.6m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months2022-01-01 to 2022-03-31 | −$0.42 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months2022-01-01 to 2022-03-31 | −$0.42 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months2022-01-01 to 2022-03-31 | 51,107,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months2022-01-01 to 2022-03-31 | $120.7m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months2022-01-01 to 2022-03-31 | $12.0m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | At period end2022-03-31 | $316.5m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | At period end2022-03-31 | $3.93bn | us-gaap:AssetsCurrent |
| Total assets | At period end2022-03-31 | $4.79bn | us-gaap:Assets |
| Current liabilities | At period end2022-03-31 | $1.86bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | At period end2022-03-31 | $3.15bn | us-gaap:Liabilities |
| Long-term debt | At period end2022-03-31 | $979.8m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | At period end2022-03-31 | $23.3m | us-gaap:DebtCurrent |
| Shareholders' equity | At period end2022-03-31 | $1.63bn | us-gaap:StockholdersEquity |