Tutor Perini Corp: Form 10-Q for the period ended Mar 31, 2023
Filed with the SEC on May 4, 2023 and accepted by EDGAR at May 4, 2023, 17:09 ET.
Management's discussion and analysis
As filed, 43,528 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
The following discussion and analysis of our financial position as of March 31, 2023 and the results of our operations for the three months ended March 31, 2023 should be read in conjunction with other information, including the unaudited Condensed Consolidated Financial Statements and notes included in Part I, Item 1, Financial Information, of this Quarterly Report on Form 10‑Q, the audited consolidated financial statements and accompanying notes to our Annual Report on Form 10‑K for the year ended December 31, 2022, and the information contained under the heading “Risk Factors” in our Annual Report on Form 10‑K for the year ended December 31, 2022 and in Part II, Item 1A below.
Forward-Looking Statements
This Quarterly Report on Form 10‑Q, including the “Management’s Discussion and Analysis of Financial Condition and Results of Operations,” contains forward-looking statements regarding future events and our future results, which are intended to be covered by the safe harbor provision for forward-looking statements provided by the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical facts are statements that could be deemed forward-looking statements. Words such as “achieve,” “anticipate,” “assumes,” “believes,” “continue,” “could,” “estimate,” “expects,” “forecast,” “hope,” “intend,” “may,” “plan,” “potential,” “predict,” “should,” “will,” “would,” variations of such words and similar expressions are intended to identify such forward-looking statements. In addition, any statements that refer to projections of our future financial performance, our anticipated growth and trends in our businesses, and other characterizations of future events or circumstances are forward-looking statements. Although such statements are based on currently available financial and economic data, as well as management’s estimates and expectations, forward-looking statements are inherently uncertain and involve risks and uncertainties that could cause our actual results to differ materially from what may be inferred from the forward-looking statements. Therefore, actual results may differ materially and adversely from those expressed in any forward-looking statements. Factors potentially contributing to such differences include, among others:
- Revisions of estimates of contract risks, revenue or costs; economic factors such as inflation; the timing of new awards; or the pace of project execution, which has resulted and may continue to result in losses or lower than anticipated profit;
- Unfavorable outcomes of existing or future litigation or dispute resolution proceedings against us or customers (project owners, developers, general contractors, etc.), subcontractors or suppliers, as well as failure to promptly recover significant working capital invested in projects subject to such matters;
- A significant slowdown or decline in economic conditions, such as those presented during a recession;
- Increased competition and failure to secure new contracts;
- Contract requirements to perform extra work beyond the initial project scope, which has and in the future could result in disputes or claims and adversely affect our working capital, profits and cash flows;
- Risks and other uncertainties associated with assumptions and estimates used to prepare our financial statements;
- Failure to meet contractual schedule requirements, which could result in higher costs and reduced profits or, in some cases, exposure to financial liability for liquidated damages and/or damages to customers, as well as damage to our reputation;
- Inability to attract and retain our key officers, and to adequately plan for their succession, and hire and retain personnel required to execute and perform on our contracts;
- Risks related to our international operations, such as uncertainty of U.S. government funding, as well as economic, political, regulatory and other risks, including risks of loss due to acts of war, labor conditions and other unforeseeable events in countries where we do business, which could adversely affect our revenue and earnings;
- Decreases in the level of government spending for infrastructure and other public projects;
- An inability to obtain bonding could have a negative impact on our operations and results;
- Possible systems and information technology interruptions and breaches in data security and/or privacy;
- Downgrades in our credit ratings;
- Failure to meet our obligations under our debt agreements, especially in a high interest rate environment;
- Failure of our joint venture partners to perform their venture obligations, which could impose additional financial and performance obligations on us, resulting in reduced profits or losses and/or reputational harm;
- The impact of inclement weather conditions on projects;
- Risks related to government contracts and related procurement regulations;
- Client cancellations of, or reductions in scope under, contracts reported in our backlog;
- Significant fluctuations in the market price of our common stock, which could result in substantial losses for stockholders and potentially subject us to securities litigation;
- Public health crises, such as the COVID-19 pandemic, have adversely impacted, and could in the future adversely impact, our business, financial condition and results of operations by, among other things, delaying the timing of project bids and/or awards and the timing of dispute resolutions and associated collections;
- Violations of the U.S. Foreign Corrupt Practices Act and similar worldwide anti-bribery laws;
- Physical and regulatory risks related to climate change;
- Impairment of our goodwill or other indefinite-lived intangible assets; and
- The exertion of influence over the Company by our chairman and chief executive officer due to his position and significant ownership interest.
Executive Overview
COVID-19 Update
During 2020 and 2021, the COVID-19 pandemic caused shut-downs or significant reductions in the operations of various courts and arbitration offices, which hindered the Company’s ability to resolve disputes related to unapproved work and resulted in the need for the Company to temporarily fund certain project costs that historically would have been promptly negotiated, billed to and collected from customers. This negative impact from the pandemic lessened in 2022 and remains low in 2023, with certain previously delayed disputes finally resolved and other settlement conferences and trial dates scheduled or being scheduled. Consequently, the Company expects to make substantial continued progress in the resolution of various disputes and unapproved change orders in 2023 and beyond.
Through the latter part of 2021, the pandemic also significantly delayed the bidding and awarding of various large prospective civil projects, which has affected the volume and timing of our new awards. The follow-on impact has been a substantial reduction in our backlog, revenue and income from construction operations over the past three years. For example, the Company’s consolidated backlog had been near a record level at $11.2 billion as of December 31, 2019, just prior to the onset of the COVID-19 pandemic, but has declined in each subsequent year, and was $7.9 billion as of March 31, 2023, a 29% decrease compared to the end of 2019. Similarly, revenue declined 29% from $5.3 billion for 2020 to $3.8 billion for 2022, though there were other factors that contributed to the revenue decline, particularly in 2022, as discussed in the Form 10-K filed for the year ended December 31, 2022. While the current impacts from the pandemic have lessened, the follow-on impact from delayed project bids and large contract awards continues to limit our backlog and operating results. In addition, many of our state and local government customers’ revenue sources were negatively impacted by the pandemic due to a reduction of commuter and business travel. The significant revenue reductions experienced by some of our customers have adversely impacted their ability to pay the Company on a timely basis for amounts due, although these impacts have continued to moderate.
Operating Results
Consolidated revenue for the three months ended March 31, 2023 was $776.3 million compared to $952.2 million for the same period in 2022. The decrease was largely due to reduced project execution activities on a transportation project in the Northeast that is nearing completion, which impacted all three segments, and an unfavorable adjustment of $83.6 million related to an adverse legal ruling on a completed mixed-use project in New York, which impacted the Building and Specialty Contractors segments, as previously reported on a Form 8-K filed on April 21, 2023. The decrease was also due to the temporary unfavorable impact from the successful negotiation of significant lower margin (and lower risk) change orders on a Civil segment mass-transit project in California. These approved change orders increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage as of March 31, 2023. This temporary reduction to earnings is expected to reverse itself over the remaining life of the project. In addition, the COVID-19 pandemic-induced customer budgetary constraints, combined with certain political and other factors, resulted in the Company not being awarded certain Civil segment projects over the last few years totaling more than $10.0 billion despite having been the low or preferred bidder. Not being awarded these projects also impacted revenue for the first quarters of both 2023 and 2022, and most of these projects are expected to be re-bid later in 2023 or in 2024. Furthermore, the Company was unsuccessful in its pursuit of certain large prospective Civil segment projects in the second half of 2021, which also unfavorably impacted revenue in both periods.
Loss from construction operations for the three months ended March 31, 2023 was $81.9 million compared to $9.9 million for the same period in 2022. The loss for the first quarter of 2023 was primarily due to the aforementioned unfavorable adjustment related to the adverse legal ruling on a completed mixed-use project in New York, which resulted in a non-cash, pre-tax charge of $83.6 million, of which $72.2 million impacted the Building segment and $11.4 million impacted the Specialty Contractors segment. The loss for the 2023 period was also due to the temporary unfavorable impact to current-period earnings of $28.0 million from the successful negotiation of significant lower margin (and lower risk) change orders in the first quarter of 2023 on a Civil segment mass-transit project in California. These approved change orders increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage as of March 31, 2023. This temporary reduction to earnings is expected to reverse itself over the remaining life of the project. The change between periods also reflected the absence of two prior-year unfavorable adjustments (a $25.5 million charge for an adverse legal ruling on a dispute related to a completed Civil segment bridge project in New York and a temporary unfavorable impact of $17.6 million that resulted from the successful negotiation of significant lower margin and lower risk change orders in the first quarter of 2022 on the same Civil segment mass-transit project in California mentioned above).
The effective tax rate was 49.6% for the three months ended March 31, 2023 compared to 17.1% for the comparable period in 2022. See Corporate, Tax and Other Matters below for a discussion of the change in the effective tax rate.
Diluted loss per common share for the three months ended March 31, 2023 was $0.95 compared to diluted loss per common share of $0.42 for the same period in 2022. The larger diluted loss per common share in 2023 was primarily due to the factors discussed above that led to the change in loss from construction operations.
Consolidated new awards for the three months ended March 31, 2023 totaled $767 million compared to $996 million for the same period in 2022. The Civil and Building segments were the primary contributors to the new award activity in the first quarter of 2023. The most significant new awards and contract adjustments in the first quarter of 2023 included $224 million of additional funding for a mass-transit project in California; a $91 million educational facility project in California; a $75 million military facility renovation project in Colorado; a $62 million bridge repair project in Minnesota; and $56 million of additional funding for a healthcare project in California. Subsequently, in the second quarter of 2023, the Company was awarded more than $3.2 billion of new projects, including the $2.95 billion Brooklyn Jail design-build project in New York, and a $222 million construction project at Tinian International Airport in the Commonwealth of Northern Mariana Islands.
Consolidated backlog as of March 31, 2023 was $7.9 billion, level compared to backlog as of December 31, 2022. As of March 31, 2023, the mix of backlog by segment was approximately 56% for Civil, 28% for Building and 16% for Specialty Contractors. The Company expects to report a substantially larger backlog at June 30, 2023, as a result of the significant new second quarter 2023 awards mentioned above.
The following table presents the Company’s backlog by business segment, reflecting changes from December 31, 2022 to March 31, 2023:
(in millions)
| Backlog at December 31, 2022 | New Awards(a) | Revenue Recognized | Backlog at March 31, 2023(b) | |
|---|---|---|---|---|
| Civil | $4,416.3 | $379.1 | $(349.9) | $4,445.5 |
| Building | 2,223.6 | 233.5 | (229.6) | 2,227.5 |
| Specialty Contractors | 1,289.2 | 154.1 | (196.8) | 1,246.5 |
| Total | $7,929.1 | $766.7 | $(776.3) | $7,919.5 |
(a) New awards consist of the original contract price of projects added to backlog plus or minus subsequent changes to the estimated total contract price of existing contracts.
(b) Backlog may differ from the transaction prices allocated to the remaining performance obligations as disclosed in Note 2 of the Notes to Condensed Consolidated Financial Statements. Such differences relate to the timing of executing a formal contract or receiving a notice to proceed. More specifically, backlog sometimes may include awards for which a contract has not yet been executed or a notice to proceed has not been issued, but for which there are no remaining major uncertainties that we will proceed with our work on the project (e.g., adequate funding is in place, we have received a notice of intent to award a contract, etc.).
The outlook for the Company’s growth over the next several years remains favorable, but it could be negatively impacted by project delays or the timing of project bids, awards, commencements, ramp-up activities and completions, as well as by continuing adverse follow-on impacts of the COVID-19 pandemic. We anticipate that we will continue to win our share of significant new awards resulting from long-term capital spending plans by state, local and federal customers, as well as limited competition for some of the largest project opportunities.
In elections over the past decade, voters in 44 states have approved 85% of nearly 3,000 state and local ballot measures, raising an estimated $342 billion in new and renewed revenue funding for transportation investments. The largest of these was in Los Angeles County, where Measure M, a half-cent sales tax increase, was approved in 2016. Funding from this measure is already flowing to some of the Company’s current and prospective projects, and overall the measure is expected to generate $120 billion of funding over 40 years. Interest rates have risen over the past year, as anticipated, but are still at levels which we believe remain conducive to continued spending on various types of projects. However, if borrowing rates continue to increase, they could reach levels that may negatively impact demand, particularly for certain Building segment end markets which tend to be more closely correlated to economic conditions.
The bipartisan Infrastructure Investment and Jobs Act of 2021 (the “Bipartisan Infrastructure Law” or “BIL”) was enacted into law on November 15, 2021, and it provides for $1.2 trillion of federal infrastructure funding, including $550 billion in new spending for improvements to the country’s surface-transportation network and enhancements to core infrastructure. The law marks the largest federal investment in public transit ever, the single largest dedicated bridge investment since the construction of the interstate highway system and the largest federal investment in passenger rail since the creation of Amtrak, all in addition to providing for regular annual spending for numerous infrastructure projects. This significant incremental funding is anticipated to be spent over the next 10 years, and much of it is allocated for investment in end markets that are directly aligned with the Company’s market focus. Accordingly, the Company believes that this significant level of sustained, incremental funding will favorably impact the Company’s current work and prospective opportunities over the next decade, as initial funds have begun flowing to project owners and substantially increased funding from the BIL is expected to occur over the next several years.
For a more detailed discussion of operating performance of each business segment, corporate general and administrative expenses and other items, see Results of Segment Operations, Corporate, Tax and Other Matters and Liquidity and Capital Resources below.
Results of Segment Operations
The results of our Civil, Building and Specialty Contractors segments are discussed below.
Civil Segment
Revenue and income (loss) from construction operations for the Civil segment are summarized as follows:
(in millions)
| Three Months Ended March 31, 2023 | 2022 | |
|---|---|---|
| Revenue | $349.9 | $390.8 |
| Income (loss) from construction operations | 18.0 | (1.0) |
Revenue for the three months ended March 31, 2023 decreased 10% compared to the same period in 2022. The decrease was primarily due to reduced project execution activities on a transportation project in the Northeast and two mass-transit projects in California, all of which are completed or nearing completion. In addition, the decrease for the three months ended March 31, 2023 reflects the temporary unfavorable impact of the successful negotiation of significant lower margin (and lower risk) change orders on a mass-transit project in California. These approved change orders increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage as of March 31, 2023. This temporary reduction to earnings is expected to reverse itself over the remaining life of the project. The decrease in revenue for the first quarter of 2023 also reflected the absence of unfavorable adjustments recognized in the first quarter of 2022 due to an adverse legal ruling on a dispute related to a bridge project in New York and the temporary unfavorable impact in the first quarter of 2022 from the successful negotiation of significant lower margin (and lower risk) change orders on the same mass-transit project in California discussed above. Revenue for both periods was also adversely impacted by the follow-on impacts of the COVID-19 pandemic, which delayed bidding activities and awards of certain new projects during 2020 and much of 2021 and negatively impacted revenue for the first quarters of both 2023 and 2022. Revenue for both periods was also adversely impacted by the Company’s lack of success in its pursuit of certain large prospective Civil segment projects in the second half of 2021 and certain projects totaling more than $10.0 billion for which the Company was the low or preferred bidder but no contract was awarded over the last few years due to customer budget constraints.
Despite the above-mentioned revenue decline, income from construction operations for the three months ended March 31, 2023 was $18.0 million compared to loss from construction operations of $1.0 million for the same period in 2022. The increase was primarily driven by the absence of the prior-year pre-tax charge of $25.5 million that resulted from the aforementioned legal ruling on a dispute related to a bridge project in New York, as well as the absence of the prior-year unfavorable pre-tax impact of $17.6 million from the successful negotiation of lower margin (and lower risk) change orders on the same mass-transit project in California as mentioned above. The increase was partially offset by the temporary unfavorable pre-tax impact of $28.0 million from the successful negotiation of significant lower margin (and lower risk) change orders in the first quarter of 2023 on the same mass-transit project in California. These approved change orders increased the project’s overall estimated profit but reduced the project’s percentage of completion and overall margin percentage, the impact of which is expected to reverse itself over the remaining life of the project.
Operating margin was 5.1% and (0.2)% for the three months ended March 31, 2023 and 2022, respectively. The increase in operating margin was principally due to the above-mentioned factors that drove the changes in revenue and income (loss) from construction operations.
New awards in the Civil segment totaled $379 million for the first quarter of 2023 compared to $447 million for the same period in 2022. The most significant new awards and contract adjustments in the first quarter of 2023 included $224 million of additional funding for a mass-transit project in California and a $62 million bridge repair project in Minnesota. The COVID-19 pandemic has caused significant revenue shortfalls for certain state and local government agencies since 2020. In addition, the timing and magnitude of federal, state and local funding, including anticipated contributions from the BIL, is uncertain, which could result in delays in the bidding and awarding of certain large new projects.
Backlog for the Civil segment was $4.4 billion as of March 31, 2023 compared to $4.6 billion as of March 31, 2022. The segment continues to experience strong demand reflected in a large, multi-year pipeline of prospective projects, supported by substantial anticipated funding from various voter-approved transportation measures and the BIL, and by public agencies’ long-term spending plans. The Civil segment is well-positioned to capture its share of these prospective projects, but the timing of new awards remains uncertain.
Building Segment
Revenue and income (loss) from construction operations for the Building segment are summarized as follows:
(in millions)
| Three Months Ended March 31, 2023 | 2022 | |
|---|---|---|
| Revenue | $229.6 | $330.6 |
| Income (loss) from construction operations | (70.2) | 9.5 |
Revenue for the three months ended March 31, 2023 decreased 31% compared to the same period in 2022, primarily due to the aforementioned unfavorable adjustment related to the adverse legal ruling on a completed mixed-use project in New York. The revenue reduction was also due to reduced project execution activities on certain projects in California, Arkansas and the Northeast that are complete or substantially complete, partially offset by contributions from certain newer projects in California, Oklahoma, Florida and Mississippi. Revenue for both periods was further reduced by the follow-on impacts of the COVID-19 pandemic, which delayed certain project bids and awards in 2020 and 2021.
Loss from construction operations for the three months ended March 31, 2023 was $70.2 million compared to income from construction operations of $9.5 million for the same period in 2022. The decrease was primarily due to the aforementioned unfavorable adjustment related to the adverse legal ruling on a completed mixed-use project in New York that resulted in a non-cash, pre-tax charge of $83.6 million, of which $72.2 million impacted the Building segment.
Operating margin was (30.6)% and 2.9% for the three months ended March 31, 2023 and 2022, respectively. The change in operating margin was principally due to the aforementioned factors that drove the reductions in revenue and income (loss) from construction operations.
New awards in the Building segment totaled $234 million for the first quarter of 2023 compared to $325 million for the same period in 2022. The most significant new awards in the first quarter of 2023 included a $91 million educational facility project in California, a $75 million military facility renovation project in Colorado and $56 million of additional funding for a healthcare project in California. The lingering effects of the COVID-19 pandemic, including the proliferation of remote and hybrid work for many businesses, as well as slowing economic conditions caused by higher inflation and rising interest rates, could continue to result in certain delayed or even canceled Building segment project opportunities, particularly in the corporate office end market. However, other Building segment end markets, such as correctional facilities, health care, education, and hospitality and gaming, continue to show strong demand for new and renovated facilities.
Backlog for the Building segment was $2.2 billion as of March 31, 2023, down slightly compared to $2.3 billion as of March 31, 2022. The Building segment continues to have a large volume of prospective projects across various end markets and geographic locations, as noted above.
Specialty Contractors Segment
Revenue and loss from construction operations for the Specialty Contractors segment are summarized as follows:
(in millions)
| Three Months Ended March 31, 2023 | 2022 | |
|---|---|---|
| Revenue | $196.8 | $230.7 |
| Loss from construction operations | (12.4) | (3.9) |
Revenue for the three months ended March 31, 2023 decreased 15% compared to the same period in 2022, principally due to reduced project execution activities on the electrical component of a transportation project in the Northeast that is nearing completion, partially offset by contributions from an industrial facility project in Arizona. The aforementioned adverse legal ruling on a completed mixed-use project in New York also contributed to the revenue decline. Revenue for the period was also reduced by the follow-on impacts of the COVID-19 pandemic, which delayed certain project bids and awards in 2020 and 2021.
Loss from construction operations for the three months ended March 31, 2023 was $12.4 million compared to $3.9 million for the same period in 2022. The larger loss for the first quarter of 2023 was principally due to the aforementioned unfavorable adjustment related to the adverse legal ruling on a completed mixed-use project in New York that resulted in a non-cash, pre-tax charge of $83.6 million, of which $11.4 million impacted the Specialty Contractors segment.
Operating margin was (6.3)% and (1.7)% for the three months ended March 31, 2023 and 2022, respectively. The change in operating margin was principally due to the aforementioned factors that drove the changes in revenue and loss from construction operations.
New awards in the Specialty Contractors segment totaled $154 million for the first quarter of 2023 compared to $224 million for the same period in 2022. The COVID-19 pandemic has resulted in, and could continue to result in, reduced demand from certain customers, particularly in New York, that continue to experience funding constraints.
Backlog for the Specialty Contractors segment was $1.2 billion as of March 31, 2023 compared to $1.4 billion as of March 31, 2022. The Specialty Contractors segment continues to be increasingly focused on servicing the Company’s current and prospective large Civil and Building segment projects, particularly in the Northeast and California. In addition, the segment remains well-positioned to capture its share of new projects, leveraging the size and scale of our business units that operate in New York, Texas, Florida and California and the strong reputation held by these business units for high-quality work on large, complex projects.
Corporate, Tax and Other Matters
Corporate General and Administrative Expenses
Corporate general and administrative expenses were $16.4 million and $14.5 million during the three months ended March 31, 2023 and 2022, respectively. The increase in the three months ended March 31, 2023 was primarily due to higher compensation-related expenses compared to the same period in 2022.
Other Income, Net, Interest Expense and Income Tax Benefit
(in millions)
| Three Months Ended March 31, 2023 | 2022 | |
|---|---|---|
| Other income, net | $6.4 | $3.7 |
| Interest expense | (21.5) | (16.5) |
| Income tax benefit | 48.1 | 3.9 |
Other income, net for the three months ended March 31, 2023 increased by $2.7 million compared to the same period in 2022, primarily due to a gain on sale of property in the 2023 period.
Interest expense for the three months ended March 31, 2023 increased by $5.0 million compared to the same period in 2022. The increase for the three months ended March 31, 2023 was substantially due to higher interest rates on the Term Loan B and the Revolver, as defined below in Liquidity and Capital Resources.
The effective income tax rate was 49.6% for the three months ended March 31, 2023. The effective income tax rate for the 2023 period was higher than the 21% federal statutory rate primarily due to the pre-tax loss for the period and projected for the year. In periods reporting pre-tax losses, a tax benefit increases the effective income tax rate because it increases the tax benefit generated from the pre-tax loss. The tax benefits that caused a higher effective tax rate were primarily the earnings attributable to noncontrolling interests (for which income taxes are not the responsibility of the Company) and state income taxes (net of the federal tax benefit), partially offset by non-deductible expenses.
The effective income tax rate was 17.1% for the three months ended March 31, 2022. The effective tax rate for the three months ended March 31, 2022, was lower than the 21% federal statutory rate. The Company incurred a pre-tax loss for the quarter, but projected a pre-tax profit for the year and, as a result, tax benefits reduced the effective tax rate. The effective income tax rate was lower than the 21% federal statutory rate primarily due to earnings attributable to noncontrolling interests, for which income taxes are not the responsibility of the Company, partially offset by state income taxes (net of the federal tax benefit).
Liquidity and Capital Resources
Liquidity is provided by available cash and cash equivalents, cash generated from operations, credit facilities and access to capital markets. We have a committed line of credit totaling $175 million, which may be used for revolving loans, letters of credit and/or general purposes. We believe that cash generated from operations, along with our unused credit capacity of $145 million and available cash balances as of March 31, 2023, will be sufficient to fund working capital needs and debt maturities for the next 12 months and beyond, including the prepayment of $44.0 million on the Term Loan B that was made, as required, in April 2023 due to a prepayment obligation in the Credit Agreement as a result of the Company generating “excess” cash flow in 2022, as discussed below in Debt. Despite our record operating cash flow in 2022 and relatively strong operating cash flow for the three months ended March 31, 2023 (as discussed below in Cash and Working Capital), liquidity has been and could continue to be negatively affected by the follow-on impacts of the COVID-19 pandemic, which induced customer budgetary constraints and delayed bidding activities and awards of certain large civil projects. We are also still pursuing COVID-19-related cost recoveries from certain customers. Our liquidity was also adversely impacted by the Company’s lack of success in its pursuit of certain large prospective Civil segment projects in the second half of 2021, as well as by instances where the Company was not awarded certain Civil segment projects totaling more than $10.0 billion over the last few years due to customer budget constraints, despite being the low or preferred bidder. In addition, as discussed above in Executive Overview - COVID-19 Update, the COVID-19 pandemic delayed court and arbitration schedules and also hindered the Company’s ability to resolve certain unapproved work. We believe that future funding from the BIL and increasing revenue to government customers as travel and commuting levels rise, as discussed above, could offset or mitigate these and other possible lingering future negative impacts from the COVID-19 pandemic, though it remains difficult to predict any of these factors. Furthermore, the backlog of accumulated court and arbitration proceedings that grew as a result of the pandemic during 2020 and 2021 has begun to recede, with certain disputes having been resolved in 2022 and 2023 with other settlement conferences and trial dates now scheduled or being scheduled. In addition, certain disputes and related collection delays were resolved during the latter part of 2021, as well as during 2022 and 2023. We experienced a record operating cash flow in 2022 and strong operating cash flow for the first quarter of 2023 (whereas typically the Company’s first quarter operating cash flow is negative due to the seasonality of the business), and we expect strong operating cash flows to continue for the remainder of 2023, based on projected cash collections, both from project execution activities and the resolution of additional outstanding claims and unapproved change orders.
Cash and Working Capital
Cash and cash equivalents were $282.7 million as of March 31, 2023 compared to $259.4 million as of December 31, 2022. Cash immediately available for general corporate purposes was $63.9 million and $47.7 million as of March 31, 2023 and December 31, 2022, respectively, with the remainder being amounts held by our consolidated joint ventures and also our proportionate share of cash held by our unconsolidated joint ventures. Cash held by our joint ventures is available only for joint venture-related uses, including distributions to joint venture partners. In addition, our restricted cash and restricted investments totaled $108.2 million as of March 31, 2023 compared to $106.0 million as of December 31, 2022. Restricted cash and restricted investments at March 31, 2023 were primarily held to secure insurance-related contingent obligations.
During the three months ended March 31, 2023, net cash provided by operating activities was $21.3 million. The net cash provided by operating activities was primarily due to a decrease in investments in project working capital, partially offset by cash utilized by earnings sources. The decrease in investments in project working capital was primarily due to a decrease in costs and estimated earnings in excess of billings (“CIE”) and decreases in accounts receivable and retention receivable that resulted from improved collection activity. During the three months ended March 31, 2022, net cash provided by operating activities was $120.7 million, which was the largest first quarter operating cash flow since the merger between Tutor-Saliba Corporation and Perini Corporation in 2008. This net cash provided by operating activities was primarily due to a decrease in investments in project working capital. The decrease in investments in project working capital was primarily due to improved collection activity, as reflected by increases in billing in excess of costs and estimated earnings (“BIE”), and decreases in accounts receivable and retention receivable.
Cash flow from operating activities decreased $99.4 million when comparing the first three months of 2023 with the same period in 2022. The decrease in cash flow from operating activities for the first three months of 2023 compared to the first three months of 2022 primarily resulted from cash utilized by earnings sources in the current year compared to cash generated by earnings sources in the prior year, partially offset by a larger current-year decrease in investment in working capital compared to last year. The larger decrease in investment in working capital in the 2023 period was primarily driven by a larger current-year decrease in CIE compared to the prior year, a current-year decrease in other current assets compared to a prior year increase (primarily due to prepaid income taxes) and a smaller current-year decrease in accounts payable retention compared to the prior year, partially offset by a smaller current-year increase in BIE and a current-year decrease in accounts payable compared to an increase in the prior year due to timing of payments to vendors and subcontractors. Both periods were positively impacted by collections associated with previously disputed matters.
Net cash used in investing activities during the first three months of 2023 was $6.9 million, primarily due to the acquisition of property and equipment (i.e., capital expenditures) totaling $17.8 million, partially offset by proceeds from the sale of property and equipment of $6.5 million and net proceeds from investment transactions of $4.4 million. Net cash used in investing activities during the first three months of 2022 was $14.9 million primarily due to the acquisition of property and equipment (i.e., capital expenditures) totaling $12.0 million, as well as net cash used in investment transactions of $4.3 million.
Net cash provided by financing activities was $14.4 million for the first three months of 2023, which was primarily driven by $21.4 million of net proceeds from borrowings, partially offset by $6.5 million of net distributions to noncontrolling interests. Net cash provided by financing activities was $4.1 million for the first three months of 2022, which was primarily driven by $8.6 million of net proceeds from borrowings, partially offset by $3.5 million of net distributions to noncontrolling interests.
At March 31, 2023, we had working capital of $1.6 billion, a ratio of current assets to current liabilities of 1.82 and a ratio of debt to equity of 0.71, compared to working capital of $1.7 billion, a ratio of current assets to current liabilities of 1.87 and a ratio of debt to equity of 0.66 at December 31, 2022.
Debt
2020 Credit Agreement
On August 18, 2020, the Company entered into a credit agreement (the “2020 Credit Agreement”) with BMO Harris Bank N.A., as Administrative Agent, Swing Line Lender and L/C Issuer and other lenders. The 2020 Credit Agreement provides for a $425.0 million term loan B facility (the “Term Loan B”) and a $175.0 million revolving credit facility (the “Revolver”), with sublimits for the issuance of letters of credit and swing line loans up to the aggregate amounts of $75.0 million and $10.0 million, respectively. The Term Loan B will mature on August 18, 2027 and the Revolver will mature on August 18, 2025, in each case, unless any of the 2017 Senior Notes are outstanding on January 30, 2025 (which is 91 days prior to the maturity of the 2017 Senior Notes), in which case, both the Term Loan B and the Revolver will mature on January 30, 2025 (subject to certain further exceptions).
The 2020 Credit Agreement requires the Company to make prepayments on the Term Loan B in connection with certain asset sales, receipts of insurance proceeds, incurrences of certain indebtedness and annual excess cash flow (in each case, subject to certain customary exceptions). Included in current maturities of long-term debt in the accompanying Condensed Consolidated Balance Sheets is a $44.0 million prepayment of principal on the Term Loan B that was made in April 2023. The prepayment resulted from our record operating cash flow in 2022, which produced “excess” cash flow under the terms of the 2020 Credit Agreement, as discussed above.
Borrowings under the 2020 Credit Agreement bear interest at variable rates, which have increased since the latter part of 2022 due to changes in market conditions that resulted in increases in LIBOR, in the case of the Term Loan B, and the administrative agent’s prime lending rate, in the case of the Revolver. Effective May 2, 2023, the 2020 Credit Agreement was amended to transition the Company’s original LIBOR option in respect of the Term Loan B to Adjusted Term SOFR. The average borrowing rates on the Term Loan B and the Revolver for the three months ended March 31, 2023 were approximately 9.4% and 11.6%, respectively. At March 31, 2023, the borrowing rates on the Term Loan B and the Revolver were 9.6% and 11.8%, respectively. For more information regarding the terms of our 2020 Credit Agreement, refer to Note 8 of the Notes to Condensed Consolidated Financial Statements.
The table below presents our actual and required first lien net leverage ratio under the 2020 Credit Agreement for the period, which is calculated on a rolling four-quarter basis:
| Trailing Four Fiscal Quarters Ended | ||
|---|---|---|
| March 31, 2023 | ||
| Actual | Required | |
| First lien net leverage ratio | 3.50 to 1.00 | ≤ 3.75 : 1.00 |
On October 31, 2022, the 2020 Credit Agreement was amended to increase the maximum First Lien Net Leverage Ratio covenant level for certain fiscal quarters. On March 10, 2023, the 2020 Credit Agreement was further amended to set the maximum First Lien Net Leverage Ratio covenant level to 3.50:1.00, effective the fiscal quarter ended December 31, 2022, and increasing to 3.75:1.00 for the fiscal quarter ending March 31, 2023 and subsequently stepping down to 3.00:1.00 for the fiscal quarter ending June 30, 2023, 2.50:1.00 for the fiscal quarter ending September 30, 2023 and 2.25:1.00 for the fiscal quarter ending December 31, 2023 and each fiscal quarter thereafter. As of March 31, 2023, we were in compliance and expect to continue to be in compliance with the covenants under the 2020 Credit Agreement.
Contractual Obligations
There have been no material changes in our contractual obligations from those described in our Annual Report on Form 10‑K for the year ended December 31, 2022.
Critical Accounting Policies and Estimates
Our significant accounting policies are described in Note 1 of the Notes to Consolidated Financial Statements included in our Annual Report on Form 10‑K for the year ended December 31, 2022. Our critical accounting estimates are also identified and discussed in Part II, Item 7 of our Annual Report on Form 10‑K for the year ended December 31, 2022.
Recently Issued Accounting Pronouncements
There were no new accounting pronouncements issued by the Financial Accounting Standards Board during the three months ended March 31, 2023 and through the date of filing of this report that had or are expected to have a material impact on the Company’s financial position, results of operations or cash flows.
Market risk
As filed, 176 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
There has been no material change in our exposure to market risk from that described in Part II, Item 7A of our Annual Report on Form 10‑K for the year ended December 31, 2022.
Controls and procedures
As filed, 1,542 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Disclosure Controls and Procedures
An evaluation of the effectiveness of the design and operation of our disclosure controls and procedures as defined by Rule 13a-15(e) under the Securities Exchange Act of 1934, as amended (“Exchange Act”), as of the end of the period covered by this Quarterly Report on Form 10‑Q was made under the supervision and with the participation of our management, including our Chief Executive Officer and Chief Financial Officer. Based upon that evaluation, the Chief Executive Officer and Chief Financial Officer concluded that the Company’s disclosure controls and procedures (a) were effective to ensure that information we are required to disclose in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in Securities and Exchange Commission rules and forms and (b) include, without limitation, controls and procedures designed to ensure that information required to be disclosed by us in reports filed or submitted under the Exchange Act is accumulated and communicated to our management, including our Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.
Changes in Internal Control Over Financial Reporting
There were no changes in our internal control over financial reporting during the period covered by this report that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.
Risk factors
As filed, 140 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
There have been no material changes to our risk factors as disclosed in our Annual Report on Form 10-K for the year ended December 31, 2022.
Figures reported in this filing
Standardized line items from the XBRL in this filing, for the period ended 2023-03-31. Comparative periods it repeats are left out.
| Line item | Period | Value | XBRL concept |
|---|---|---|---|
| Revenue | 3 months2023-01-01 to 2023-03-31 | $776.3m | us-gaap:RevenueFromContractWithCustomerExcludingAssessedTax |
| Cost of revenue | 3 months2023-01-01 to 2023-03-31 | $800.5m | us-gaap:CostOfGoodsAndServicesSold |
| Gross profit | 3 months2023-01-01 to 2023-03-31 | −$24.2m | us-gaap:GrossProfit |
| Operating income | 3 months2023-01-01 to 2023-03-31 | −$81.9m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months2023-01-01 to 2023-03-31 | $21.5m | us-gaap:InterestExpense |
| Income tax | 3 months2023-01-01 to 2023-03-31 | −$48.1m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months2023-01-01 to 2023-03-31 | −$49.2m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months2023-01-01 to 2023-03-31 | −$0.95 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months2023-01-01 to 2023-03-31 | −$0.95 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months2023-01-01 to 2023-03-31 | 51,551,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months2023-01-01 to 2023-03-31 | $21.3m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 3 months2023-01-01 to 2023-03-31 | $17.8m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Cash and equivalents | At period end2023-03-31 | $282.7m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | At period end2023-03-31 | $3.53bn | us-gaap:AssetsCurrent |
| Total assets | At period end2023-03-31 | $4.48bn | us-gaap:Assets |
| Current liabilities | At period end2023-03-31 | $1.93bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | At period end2023-03-31 | $3.09bn | us-gaap:Liabilities |
| Long-term debt | At period end2023-03-31 | $914.5m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | At period end2023-03-31 | $66.2m | us-gaap:DebtCurrent |
| Shareholders' equity | At period end2023-03-31 | $1.40bn | us-gaap:StockholdersEquity |
Source: SEC EDGAR, the filing index for accession 0000077543-23-000076. Last ingested by Listed: Nov 15, 2026, 00:46 ET. Listed shows no prices and gives no investment advice.