Alliant Energy Corp: Form 10-Q for the period ended Jun 30, 2013
Filed with the SEC on Aug 2, 2013 and accepted by EDGAR at Aug 2, 2013, 20:06 ET.
Management's discussion and analysis
As filed, 113,952 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
This MDA includes information relating to Alliant Energy, IPL and WPL, as well as Resources and Corporate Services. Where appropriate, information relating to a specific entity has been segregated and labeled as such. The following discussion and analysis should be read in conjunction with the Condensed Consolidated Financial Statements and the Combined Notes to Condensed Consolidated Financial Statements included in this report as well as the financial statements, notes and MDA included in the 2012 Form 10-K. Unless otherwise noted, all “per share” references in this MDA refer to earnings per diluted share.
CONTENTS OF MDA
Alliant Energy’s, IPL’s and WPL’s MDA consists of the following information:
- Executive Summary
- Strategic Overview
- Rate Matters
- Environmental Matters
- Legislative Matters
- Alliant Energy’s Results of Operations
- IPL’s Results of Operations
- WPL’s Results of Operations
- Liquidity and Capital Resources
- Other Matters
- Market Risk Sensitive Instruments and Positions
- Critical Accounting Policies and Estimates
- Other Future Considerations
EXECUTIVE SUMMARY
Description of Business
General - Alliant Energy is an investor-owned public utility holding company whose primary subsidiaries are IPL, WPL, Resources and Corporate Services. IPL is a public utility engaged principally in the generation and distribution of electricity and the distribution and transportation of natural gas in selective markets in Iowa and southern Minnesota. WPL is a public utility engaged principally in the generation and distribution of electricity and the distribution and transportation of natural gas in selective markets in southern and central Wisconsin. WPL also owns an approximate 16% interest in ATC, a transmission-only utility operating principally in Wisconsin, Michigan, Illinois and Minnesota. Resources is the parent company for Alliant Energy’s non-regulated businesses. Corporate Services provides administrative services to Alliant Energy and its subsidiaries. An illustration of Alliant Energy’s primary businesses is shown below.
| Alliant Energy | |
| Utility and Corporate Services | Non-regulated and Parent |
| - Electric and gas services in IA (IPL) | - Transportation (Resources) |
| - Electric and gas services in WI (WPL) | - Non-regulated Generation (Resources) |
| - 16% interest in ATC (WPL) | - Parent Company |
| - Electric and gas services in MN (IPL) | |
| - Corporate Services |
Financial Results - Alliant Energy’s net income and EPS attributable to Alliant Energy common shareowners for the second quarter were as follows (dollars in millions, except per share amounts):
| Continuing operations: | 2013 Income (Loss) | EPS | 2012 Income | EPS |
|---|---|---|---|---|
| Utility and Corporate Services | $58.4 | $0.52 | $54.0 | $0.49 |
| Non-regulated and parent | 7.5 | 0.07 | 11.5 | 0.11 |
| Income from continuing operations | 65.9 | 0.59 | 65.5 | 0.60 |
| Income (loss) from discontinued operations | (0.6) | — | 0.4 | — |
| Net income | $65.3 | $0.59 | $65.9 | $0.60 |
The table above includes utility and Corporate Services, and non-regulated and parent EPS from continuing operations, which are non-GAAP financial measures. Alliant Energy believes utility and Corporate Services, and non-regulated and parent EPS from continuing operations are useful to investors because they facilitate an understanding of segment performance and trends and provide additional information about Alliant Energy’s operations on a basis consistent with the measures that management uses to manage its operations and evaluate its performance. Alliant Energy’s management also uses utility and Corporate Services EPS from continuing operations to determine performance-based compensation.
Utility and Corporate Services - Higher income from continuing operations in the second quarter of 2013 compared to the second quarter of 2012 was primarily due to:
- $0.11 per share of purchased electric capacity expense related to the Riverside Energy Center (Riverside) PPA recorded in the second quarter of 2012;
- $0.03 per share from the revenue requirement adjustment related to certain IPL tax benefits in the second quarter of 2013; and
- $0.03 per share of lower energy conservation cost recovery amortizations at WPL in the second quarter of 2013 compared to the second quarter of 2012.
These items were partially offset by:
- an estimated $0.04 per share decrease in revenues from changes in electric and gas sales in the second quarter of 2013 compared to the second quarter of 2012 due to weather conditions;
- $0.04 per share of higher depreciation expense in the second quarter of 2013 compared to the second quarter of 2012, primarily due to WPL’s acquisition of Riverside in December 2012; and
- $0.02 per share of regulatory-related credits from WPL’s 2013/2014 test period rate case decision in the second quarter of 2012.
Non-regulated and parent - Lower income from continuing operations in the second quarter of 2013 compared to the second quarter of 2012 was primarily due to a $0.01 per share decrease related to the impact of IPL’s electric and gas tax benefit riders at the parent company in the second quarter of 2013 compared to the second quarter of 2012 and $0.01 per share of losses incurred at the Franklin County wind project in the second quarter of 2013.
Refer to “Alliant Energy’s Results of Operations,” “IPL’s Results of Operations” and “WPL’s Results of Operations” for additional details regarding the various factors impacting their respective earnings during the second quarters of 2013 and 2012.
Strategic Overview
Alliant Energy’s, IPL’s and WPL’s strategic plan focuses on their core business of delivering regulated electric and natural gas service in Iowa, Wisconsin and Minnesota. The strategic plan is built upon three key elements: competitive costs, safe and reliable service and balanced generation. Key strategic plan developments impacting Alliant Energy, IPL and WPL during 2013 include the following. Refer to “Strategic Overview” for a more detailed discussion of strategic plan developments.
- January 2013 - The IUB issued an order allowing IPL to move forward with a proposed PPA that was recently negotiated with NextEra Energy Resources, LLC, a subsidiary of NextEra Energy, Inc., for the purchase of capacity and energy generated by DAEC located near Palo, Iowa for a term of 2014 through 2025. The new DAEC PPA was completed in March 2013.
- April 2013 - WPL announced its current environmental compliance plans include installing an SCR at Columbia Unit 2 to reduce NOx emissions at the facility. The SCR is expected to support compliance obligations for current and anticipated air quality regulatory requirements, including CAIR, a modified Cross-State Air Pollution Rule (CSAPR) or some alternative to these rules that may be implemented, and the Wisconsin RACT Rule. WPL currently expects to file a Certificate of Authority (CA) application with the PSCW in the second quarter of 2014 for the SCR at Columbia Unit 2.
- April 2013 - IPL and the OCA filed a settlement agreement with the IUB, resolving all issues between the parties regarding the appropriate rate-making principles for the Marshalltown Generating Station (Marshalltown). In addition, the OCA agreed that IPL satisfied conditions precedent for rate-making principles. The proposed settlement agreement includes an 11% return on common equity for the depreciable life of Marshalltown and a 10.3% return on common equity for the calculation of allowance for funds used during construction (AFUDC) related to Marshalltown. The proposed settlement agreement also reflects IPL’s requested fixed cost cap of $700 million, excluding AFUDC and transmission upgrade costs. Any costs incurred in excess of the cost cap are expected to be incorporated into rates if determined to be reasonable and prudent. IPL and the OCA agreed to defer the decision regarding the application of double leverage until the next retail electric base rate case or other proceeding. The proposed settlement regarding the appropriate rate-making principles for Marshalltown is subject to approval by the IUB.
- June 2013 - WPL received an order from the PSCW approving WPL’s CA application to install a scrubber and baghouse system at Edgewater Unit 5 to reduce SO2 and mercury emissions at the generating facility. WPL currently expects to begin construction of the project in 2014 and place it in service in 2016.
Rate Matters
Alliant Energy’s utility subsidiaries, IPL and WPL, are subject to federal regulation by FERC, which has jurisdiction over wholesale electric rates, and state regulation in Iowa, Wisconsin and Minnesota for retail utility rates. Key regulatory developments impacting Alliant Energy, IPL and WPL during 2013 include the following. Refer to “Rate Matters” for a more detailed discussion of regulatory developments.
- January 2013 - The IUB authorized IPL to recover the Iowa retail portion of the costs of its proposed DAEC PPA from Iowa retail electric customers through the energy adjustment clause beginning February 22, 2014. The IUB is encouraging IPL to continue discussions with parties to the proposed DAEC PPA proceeding to resolve concerns expressed by such parties during the proceeding. If IPL is unable to reach an agreement with the parties to resolve their
concerns, IPL commits to file an Iowa retail electric base rate case in the first quarter of 2014 and agrees to subject its Iowa retail electric base rates to potential refund beginning February 22, 2014 if the IUB orders a rate decrease from such rate case. If IPL does not file an Iowa retail electric base rate case in the first quarter of 2014, the amount of costs IPL will be allowed to recover from its Iowa electric retail customers through the energy adjustment clause will be reduced by $12 million each month from February 22, 2014 until temporary rates are set in IPL’s next Iowa retail electric base rate proceeding.
- February 2013 - IPL received an order from the IUB approving the final amount of the regulatory liability from tax benefits for the electric tax benefit rider and a $24 million revenue requirement adjustment to be recognized during 2013.
- May 2013 - FERC issued an order accepting WPL’s request for new depreciation rates associated with the acquisition of Riverside effective January 1, 2013.
- July 2013 - WPL filed a request with the PSCW to increase annual rates for WPL’s retail electric customers by $31 million, or approximately 3%, to reflect anticipated increases in retail electric fuel-related costs in 2014. Any rate changes granted from this request are expected to be effective on January 1, 2014.
- July 2013 - Based on a decision by the PSCW, WPL plans to refund $12 million to its retail electric customers in the third quarter of 2013 for over-collection of fuel-related costs for 2012.
Environmental Matters
Alliant Energy, IPL and WPL are subject to regulation of environmental matters by various federal, state and local authorities. Key environmental developments during 2013 that may impact Alliant Energy, IPL and WPL include the following. Refer to “Environmental Matters” for a more detailed discussion of environmental developments.
- April 2013 - WPL, along with the other owners of Edgewater and Columbia, entered into a Consent Decree with the EPA and the Sierra Club to resolve certain alleged air permitting violations, while admitting no liability. The Consent Decree was approved by the Court in June 2013 thereby resolving the related claims and requiring the installation of certain emission controls systems.
- June 2013 - The EPA issued proposed effluent limitation guidelines for public comment. The proposed guidelines would require changes to discharge limits for wastewater from steam EGUs. Compliance with these proposed guidelines would be required after July 1, 2017 but before July 1, 2022, depending on each facility’s wastewater permit cycle for existing steam EGUs and immediately upon operation for new steam EGUs constructed after the issuance of the final guidelines.
- June 2013 - President Obama announced plans to address climate change and issued a memorandum directing the EPA to proceed with rules to reduce carbon emissions from new and existing fossil-fueled EGUs. The EPA is currently expected to issue revised proposed NSPS for GHG for new EGUs by September 20, 2013. A date for finalizing these standards has not yet been established. The EPA is expected to issue final NSPS for GHG for existing EGUs by June 1, 2015, which would provide guidelines that states must follow to achieve required GHG reductions. SIPs that provide details of how these guidelines are to be met will be required from state agencies by June 30, 2016.
Legislative Matters
Alliant Energy, IPL and WPL monitor various legislative developments, including those relating to energy, tax, financial and other matters. Recent key legislative developments impacting Alliant Energy, IPL and WPL during 2013 include:
- January 2013 - The ATR Act was enacted. The most significant provision of the ATR Act for Alliant Energy, IPL and WPL relates to the extension of bonus depreciation deductions for certain expenditures for property that are incurred through December 31, 2013.
Liquidity and Capital Resources
Based on their current liquidity positions and capital structures, Alliant Energy, IPL and WPL believe they will be able to secure the additional capital required to implement their strategic plan and to meet their long-term contractual obligations. Key financing developments impacting Alliant Energy, IPL and WPL during 2013 include the following. Refer to “Liquidity and Capital Resources” for a more detailed discussion of financing developments.
- March 2013 - IPL issued 8,000,000 shares of 5.1% cumulative preferred stock and received proceeds of $200 million. The proceeds were used by IPL to redeem all 6,000,000 outstanding shares of its 8.375% cumulative preferred stock for $150 million, reduce commercial paper classified as long-term debt by $40 million and for other general corporate purposes.
- March 2013 - WPL redeemed all 1,049,225 outstanding shares of its 4.40% through 6.50% cumulative preferred stock for $61 million.
- June 2013 - At June 30, 2013, Alliant Energy and its subsidiaries had $722 million of available capacity under their revolving credit facilities, $15 million of available capacity at IPL under its sales of accounts receivable program and $12 million of cash and cash equivalents.
Other Matters
Other key developments in 2013 that could impact Alliant Energy’s, IPL’s or WPL’s future financial condition or results of operations include the following. Refer to “Other Matters” for a more detailed discussion of potential impacts to future financial condition and results of operations.
- March 2013 - Midcontinent Independent System Operator, Inc. (MISO) completed a definitive planning phase study for Bent Tree and determined the transmission system upgrades completed in 2011 and 2012 were required network upgrades. In July 2013, FERC issued an order requiring changes to ITC Midwest LLC’s (ITC’s) Attachment “FF” tariff. As a result, WPL is uncertain whether it will be reimbursed by ITC for 100% of the related transmission upgrade costs.
- April 2013 - IPL and MidAmerican Energy Company (MidAmerican) filed a joint Notice of Appeal with the Iowa Supreme Court related to the Polk County Iowa District Court’s (District Court’s) March 2013 ruling, which found Eagle Point Solar (Eagle Point) is not a public utility and could sell directly to the City of Dubuque the power generated by a 175 kilowatt solar unit installed on the City’s property. The District Court decision is currently stayed. Alliant Energy and IPL are unable to determine how this District Court ruling may impact the level of third-party solar development in IPL’s service territory and resulting impact on future demand of electricity by IPL’s customers.
- April 2013 - IPL and Jo-Carroll Energy, Inc. (Jo-Carroll) reached a settlement regarding pending litigation and executed an amended agreement, which FERC approved in May 2013. Key terms of the amended agreement include: (1) the amended agreement will no longer include an early termination rate comparison provision, which under the original agreement allowed Jo-Carroll to terminate such agreement with two year’s prior notice if certain energy price conditions existed; (2) the amended agreement has an initial term through at least April 1, 2018 and provides IPL or Jo-Carroll the right to terminate the amended agreement any time after April 1, 2018 with a four-year prior written notice; and (3) Jo-Carroll can source up to 10 MW of its electricity demand through its own generation.
- May 2013 - FERC ordered MISO and various transmission owners, including ITC and ATC, to make certain changes to their Attachment “O” protocols related to transmission service rates. A compliance filing is due to FERC in September 2013. Alliant Energy, IPL and WPL are currently unable to determine what impacts the changes in protocols will have on their future electric transmission service charges.
- July 2013 - FERC issued an order requiring MISO, on behalf of ITC, to revise ITC’s Attachment “FF” tariff to conform to the MISO Attachment “FF” tariff. Alliant Energy and IPL are currently uncertain whether the FERC order will be appealed. Assuming the FERC order is not appealed, MISO is currently expected to submit a filing in August 2013 that proposes tariff revisions, which are expected to be effective as of the date of the July 2013 order. These tariff revisions ordered by FERC are expected to impact the future amount of electric transmission service costs billed by ITC to IPL. Alliant Energy and IPL currently expect to pass on the Iowa retail portion of any changes in electric transmission service costs billed by ITC to IPL from the revision in ITC’s Attachment “FF” tariff to its electric retail customers in Iowa through the transmission cost recovery rider.
STRATEGIC OVERVIEW
A summary of Alliant Energy’s, IPL’s and WPL’s strategic overview is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K, except as described below.
Generation Plans -
Natural Gas-Fired Generation -
IPL’s Proposed Construction of Marshalltown - In November 2012, IPL filed for regulatory approvals to construct an approximate 600 MW natural gas-fired combined-cycle electric generating facility in Marshalltown, Iowa, referred to as Marshalltown. In April 2013, IPL and the OCA filed a settlement agreement with the IUB regarding the appropriate rate-making principles for Marshalltown. In addition, the OCA agreed that IPL satisfied conditions precedent for rate-making principles. The proposed settlement agreement includes an 11% return on common equity for the depreciable life of Marshalltown and a 10.3% return on common equity for the calculation of AFUDC related to Marshalltown. The proposed settlement agreement also reflects IPL’s requested fixed cost cap of $700 million, excluding AFUDC and transmission upgrade costs. Any costs incurred in excess of the cost cap are expected to be incorporated into rates if determined to be reasonable and prudent. IPL and the OCA agreed to defer the decision regarding the application of double leverage until the next retail electric base rate case or other proceeding. The proposed settlement regarding the appropriate rate-making principles for Marshalltown is subject to approval by the IUB. IPL expects to receive decisions on its Application for a Generation Facility Citing Certificate and advanced rate-making principles by the end of 2013.
In July 2013, FERC issued an order requiring MISO, on behalf of ITC, to revise ITC’s Attachment “FF” tariff to conform to the MISO Attachment “FF” tariff. Based on cost estimates provided by MISO included in an initial System Planning and Analysis Study and revisions required by the current FERC order, IPL’s portion of transmission upgrade costs related to Marshalltown will be approximately $150 million, excluding AFUDC.
Coal-Fired Generation -
Generation Improvement Projects - In July 2013, WPL filed a CA application with the PSCW for performance and reliability improvements at Columbia Units 1 and 2. WPL’s portion of the capital expenditures for the projects, excluding AFUDC, is currently estimated to be between $55 million and $65 million. These capital expenditures were previously included in WPL’s anticipated construction and acquisition expenditures reported in the 2012 Form 10-K. WPL currently expects a decision from the PSCW regarding these generation performance improvement projects by the third quarter of 2014. Subject to regulatory approval of the projects and the timing of such approvals, WPL expects to begin construction in the first half of 2015 and place them in service by 2017.
Plant Retirement - In June 2013, IPL retired Lansing Unit 3, which did not have a significant net book value.
Nuclear Generation -
IPL’s DAEC PPA - Refer to “Rate Matters” for discussion of IPL’s new DAEC PPA for a term of 2014 through 2025, which was completed in March 2013.
Environmental Compliance Plans - Alliant Energy, IPL and WPL have developed environmental compliance plans to help ensure cost effective compliance with current and proposed environmental laws and regulations. The following table provides current estimates of capital expenditures planned for 2013 through 2016 as well as the total project costs for emission controls projects included in Alliant Energy’s, IPL’s and WPL’s current environmental compliance plans (in millions):
| Generating Unit IPL: | Expected In-service Date | Technology (a) | 2013 | 2014 | 2015 | 2016 | Total Project Cost |
|---|---|---|---|---|---|---|---|
| George Neal Units 3 & 4 (b) | 2013/2014 | Scrubber & Baghouse | $60 | $30 | $— | $— | $120-$140 |
| Ottumwa Unit 1 | 2014 | Scrubber & Baghouse | 65 | 25 | — | — | 150-170 |
| Lansing Unit 4 | 2015 | Scrubber | 15 | 30 | 10 | — | 50-60 |
| Other | Various | 45 | 35 | 5 | 5 | ||
| 185 | 120 | 15 | 5 | ||||
| WPL: | |||||||
| Columbia Units 1 & 2 | 2014 | Scrubber & Baghouse | 145 | 20 | — | — | 280-310 |
| Edgewater Unit 5 | 2016 | Scrubber & Baghouse | 15 | 70 | 185 | 140 | 390-430 |
| Columbia Unit 2 | 2018 | SCR | — | — | — | 20 | 100-125 |
| Other | Various | 10 | — | — | — | ||
| 170 | 90 | 185 | 160 | ||||
| Alliant Energy | $355 | $210 | $200 | $165 |
(a) SCR is a post-combustion process that injects ammonia or urea into the stream of gases leaving the generating facility boiler to convert NOx emissions into nitrogen and water. The use of a catalyst enhances the effectiveness of the conversion, enabling NOx emissions reductions of up to 90%.
Baghouse, including carbon injection, is a post-combustion process that injects carbon particles into the stream of gases leaving the generating facility boiler to facilitate the capture of mercury in filters or bags. This process can remove more than 85% of mercury emissions.
Scrubber is a post-combustion process that injects lime or lime slurry into the stream of gases leaving the generating facility boiler to remove SO2 and other acid gases (including hydrochloric acid) and capture them in a solid or liquid waste by-product. A scrubber typically removes more than 90% of the SO2 emissions.
(b) George Neal Units 3 and 4 are operated by MidAmerican. IPL owns a 28% interest in George Neal Unit 3 and a 25.695% interest in George Neal Unit 4.
These capital expenditure estimates represent IPL’s or WPL’s respective portion of the total escalated capital expenditures and exclude AFUDC, if applicable. Capital expenditure estimates are subject to change based on future changes to plant-specific costs of emission controls technologies and environmental requirements.
IPL’s Emission Controls Projects - In February 2013, the IUB approved IPL’s most recent Emissions Plan and Budget (EPB), which includes the emission controls projects for Ottumwa Unit 1 and Lansing Unit 4 listed in the above table. MidAmerican’s most recent EPB has also been approved by the IUB, which includes the emission controls projects for George Neal Units 3 and 4 listed in the above table.
WPL’s Emission Controls Projects -
Edgewater Unit 5 - In June 2013, WPL received an order from the PSCW approving WPL’s CA application to install a scrubber and baghouse system at Edgewater Unit 5 to reduce SO2 and mercury emissions at the generating facility. WPL currently expects to begin construction of the project in 2014 and place it in service in 2016. The scrubber and baghouse system is expected to support compliance obligations for current and anticipated air quality regulatory requirements, including CAIR, a modified CSAPR or some alternative to these rules that may be implemented, the Utility MACT Rule and the Wisconsin State Mercury Rule.
Columbia Unit 2 - WPL currently expects to file a CA application with the PSCW in the second quarter of 2014 to install an SCR at Columbia Unit 2 to reduce NOx emissions at the facility. The SCR is expected to support compliance obligations for current and anticipated air quality regulatory requirements, including CAIR, a modified CSAPR or some alternative to these rules that may be implemented, and the Wisconsin RACT Rule.
Refer to Note 12(c) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of a Consent Decree approved by the Court in June 2013, which includes a requirement for WPL to install emission controls systems at certain of its EGUs.
Energy Efficiency Programs -
IPL Energy Efficiency Plan (EEP) - In November 2012, IPL filed an EEP for 2014 through 2018 with the IUB. The EEP includes IPL spending approximately $400 million for electric and natural gas energy efficiency programs in Iowa from 2014 through 2018, and is expected to conserve electric and gas usage equal to that of more than 100,000 homes. In July 2013, IPL reached a partial settlement with the OCA, among others, agreeing to the $400 million of spending proposed in IPL’s EEP for 2014 through 2018. The IUB is currently expected to make a decision on the partial settlement and IPL’s EEP for 2014 through 2018 by the end of 2013. To the extent approved by the IUB, costs associated with executing the EEP are recovered from Iowa retail electric and gas customers through an additional tariff called an Energy Efficiency Cost Recovery factor and therefore are not expected to have a material impact on Alliant Energy’s and IPL’s financial condition or results of operations.
RATE MATTERS
A summary of Alliant Energy’s, IPL’s and WPL’s rate matters is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K, except as described below.
WPL’s Retail Fuel-related Rate Filings -
2014 Test Year - In July 2013, WPL filed a request with the PSCW to increase annual rates for WPL’s retail electric customers by $31 million, or approximately 3%, to reflect anticipated increases in retail electric fuel-related costs in 2014. Any rate changes granted from this request are expected to be effective on January 1, 2014.
2012 Test Year - Retail fuel-related costs incurred by WPL in 2012 were lower than retail fuel-related costs used to determine rates for such period resulting in an over-collection of fuel-related costs for 2012 of approximately $17 million (including $11 million outside the approved range for 2012). As of June 30, 2013 and December 31, 2012, both Alliant Energy and WPL recorded $12 million (includes interest) and $11 million, respectively, in regulatory liabilities on their Condensed Consolidated Balance Sheets for refunds related to the over-collection of fuel-related costs for 2012. Based on a decision by the PSCW in July 2013, WPL plans to refund $12 million to its retail electric customers in the third quarter of 2013 for these over-collections, including interest.
Potential Future IPL Retail Electric Base Rate Case - In January 2013, the IUB issued an order allowing IPL to proceed with its proposed DAEC PPA for a term of 2014 through 2025 and authorized IPL to recover the Iowa retail portion of the costs of such PPA from Iowa retail electric customers through the energy adjustment clause beginning February 22, 2014. The January 2013 order encourages IPL to continue discussions with parties to the proposed DAEC PPA proceeding to resolve concerns expressed by such parties during the proceeding regarding rate impacts beginning in 2014. If IPL is unable to reach an agreement with the parties to resolve their concerns, IPL commits to file an Iowa retail electric base rate case in the first quarter of 2014 and agrees to subject its Iowa retail electric base rates to potential refund beginning February 22, 2014 if the IUB orders a rate decrease from such rate case. If IPL does not file an Iowa retail electric base rate case in the first quarter of 2014, the amount of costs IPL will be allowed to recover from its Iowa electric retail customers through the energy adjustment clause will be reduced by $12 million each month from February 22, 2014 until temporary rates are set in IPL’s next Iowa retail electric base rate proceeding. In March 2013, the IUB issued an order denying a motion for reconsideration filed by one of the parties that participated in the proceeding for the new DAEC PPA. Following the IUB’s
March 2013 order, IPL gave notice to NextEra Energy Resources, LLC that the resolution of this matter satisfied all conditions precedent of the new DAEC PPA, which was completed in March 2013. IPL has had, and will continue to have, discussions with other parties regarding resolution of the issues identified during the DAEC PPA proceeding.
System Support Resource (SSR) - In certain instances, market participants that desire to retire or suspend operations of owned EGUs may be notified by MISO that the EGU is needed to maintain system reliability. When an EGU is required to continue to operate for system reliability, the market participant may enter into an SSR agreement and negotiate an annual revenue requirement with MISO. The annual revenue requirement for the SSR is subject to FERC approval and is assigned to load serving entities that benefit from the continued operation of the EGU. In April 2013, the PSCW issued an order allowing investor-owned Wisconsin utilities to defer SSR costs incurred through December 31, 2015. While the amount of SSR costs WPL will incur is uncertain, the amount is not expected to have a significant impact on its financial condition or results of operations.
WPL Depreciation Study - In May 2013, FERC issued an order accepting WPL’s request for new depreciation rates associated with the acquisition of Riverside effective January 1, 2013.
ENVIRONMENTAL MATTERS
A summary of Alliant Energy’s, IPL’s and WPL’s environmental matters is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K, except as described below.
Air Quality -
Air Permitting Violation Claims - Refer to Note 12(c) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of a Consent Decree approved by the Court in June 2013 and WPL’s obligations thereunder. The Consent Decree resolves an NOV issued by the EPA in 2009 and complaints filed by the Sierra Club in 2010 regarding alleged air permitting violations at Columbia, Edgewater and Nelson Dewey.
Air Permit Renewal Challenges -
Columbia - In 2011, the Sierra Club filed a lawsuit against the EPA with the Court seeking to have the EPA take over the Title V air permit process for Columbia based on what the Sierra Club asserts was unreasonable delay in reconsideration of such air permit. In June 2013, the Court approved a related Consent Decree, thereby resolving this matter.
Edgewater - In 2010, WPL received a copy of a notice of intent to sue by the Sierra Club against the EPA based on what the Sierra Club asserts was unreasonable delay in the EPA performing its duties related to the reconsideration of the Edgewater Title V air permit. In March 2013, the Wisconsin Department of Natural Resources (DNR) issued a revised air permit for Edgewater, superseding the previous air permit, thereby resolving this matter.
Nelson Dewey - In 2010, the Sierra Club petitioned the EPA and the Wisconsin DNR to reopen and correct a Nelson Dewey air permit issued in 2008 based on allegations by the Sierra Club that certain modifications were made at the facility without complying with the PSD program requirements. In June 2013, the Court approved a related Consent Decree, thereby resolving this matter.
Water Quality -
Effluent Limitation Guidelines - In June 2013, the EPA issued proposed effluent limitation guidelines for public comment. The proposed guidelines would require changes to discharge limits for wastewater from steam EGUs. IPL and WPL have identified ten (Ottumwa Unit 1, Prairie Creek Units 3-4, Fox Lake Units 1 and 3, Lansing Unit 4, Dubuque Units 3-4, M.L. Kapp Unit 2, Burlington Unit 1, Sutherland Units 1 and 3, George Neal Units 3-4 and Louisa Unit 1) and three (Columbia Units 1-2, Nelson Dewey Units 1-2 and Edgewater Units 3-5) existing steam EGUs, respectively, that are expected to be impacted by these guidelines. In addition, Marshalltown, if constructed, is expected to be impacted by these guidelines. Based on information in the proposed guidelines, IPL and WPL are currently unable to determine if two (Prairie Creek Unit 1, Emery Units 1-3) and one (Riverside Units 1-3) existing steam EGUs, respectively, may be impacted. Compliance with these proposed guidelines would be required after July 1, 2017 but before July 1, 2022, depending on each facility’s wastewater permit cycle for existing steam EGUs and immediately upon operation for new steam EGUs constructed after the issuance of the final guidelines. Given that the EPA has not yet issued final guidelines, Alliant Energy, IPL and WPL are currently unable to predict with certainty the impact of these guidelines on their financial condition and results of operations, but believe the expenditures to comply with these guidelines could be significant.
Land and Solid Waste -
MGP Sites - Refer to Note 12(e) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of IPL’s and WPL’s MGP sites.
GHG Emissions -
EPA NSPS for GHG Emissions from Electric Utilities - In June 2013, President Obama announced plans to address climate change and issued a memorandum directing the EPA to proceed with rules to reduce carbon emissions from new and existing fossil-fueled EGUs. The EPA is currently expected to issue revised proposed NSPS for GHG for new EGUs by September 20, 2013. A date for finalizing these standards has not yet been established. The EPA is expected to issue proposed and final NSPS for GHG for existing EGUs by June 1, 2014 and June 1, 2015, respectively, which would provide guidelines that states must follow to achieve required GHG reductions. SIPs that provide details of how these guidelines are to be met will be required from state agencies by June 30, 2016. The President’s memorandum does not provide details on the expected level of required GHG reductions or compliance deadlines to meet the final standards. Accordingly, the implications of the EPA’s NSPS for GHG emissions from new and existing EGUs remains highly uncertain. Alliant Energy, IPL and WPL are currently unable to predict with certainty the final outcome of these standards, but expect that expenditures to comply with any regulations to reduce GHG emissions could be significant.
LEGISLATIVE MATTERS
A summary of Alliant Energy’s, IPL’s and WPL’s legislative matters is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K.
ALLIANT ENERGY’S RESULTS OF OPERATIONS
Overview - Second Quarter Results - Refer to “Executive Summary” for an overview of Alliant Energy’s second quarter 2013 and 2012 earnings and the various components of Alliant Energy’s business. Additional details of Alliant Energy’s earnings for the three and six months ended June 30, 2013 and 2012 are discussed below.
Utility Electric Margins - Electric margins are defined as electric operating revenues less electric production fuel, energy purchases and purchased electric capacity expenses. Management believes that electric margins provide a more meaningful basis for evaluating utility operations than electric operating revenues since electric production fuel, energy purchases and purchased electric capacity expenses are generally passed through to customers, and therefore, result in changes to electric operating revenues that are comparable to changes in electric production fuel, energy purchases and purchased electric capacity expenses.
Second Quarter 2013 vs. Second Quarter 2012 Summary - Electric margins and MWh sales for Alliant Energy for the three months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | MWhs Sold (MWhs in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $218.8 | $224.3 | (2%) | 1,698 | 1,734 | (2%) |
| Commercial | 148.4 | 146.3 | 1% | 1,503 | 1,534 | (2%) |
| Industrial | 180.4 | 183.4 | (2%) | 2,887 | 2,864 | 1% |
| Retail subtotal | 547.6 | 554.0 | (1%) | 6,088 | 6,132 | (1%) |
| Sales for resale: | ||||||
| Wholesale | 45.2 | 43.7 | 3% | 833 | 778 | 7% |
| Bulk power and other | 5.1 | 3.0 | 70% | 285 | 362 | (21%) |
| Other | 14.2 | 11.9 | 19% | 43 | 37 | 16% |
| Total revenues/sales | 612.1 | 612.6 | —% | 7,249 | 7,309 | (1%) |
| Electric production fuel expense | 86.2 | 67.8 | 27% | |||
| Energy purchases expense | 71.8 | 101.1 | (29%) | |||
| Purchased electric capacity expense | 52.0 | 70.7 | (26%) | |||
| Electric margins (a) | $402.1 | $373.0 | 8% |
48
(a) Includes $20 million of credits on Iowa retail electric customers’ bills for both the second quarters of 2013 and 2012 resulting from IPL’s electric tax benefit rider. IPL’s electric tax benefit rider is expected to result in reductions in electric revenues that are offset by reductions in income tax expense for the years ended December 31, 2013 and 2012.
Electric margins increased $29 million, or 8%, primarily due to $20 million of purchased electric capacity expenses at WPL in the second quarter of 2012 related to the Riverside PPA, which terminated in conjunction with WPL’s acquisition of Riverside in December 2012, $15 million of higher revenues at IPL related to changes in recovery of transmission costs related to the transmission rider and $5 million of revenues at IPL in the second quarter of 2013 due to the revenue requirement adjustment related to certain tax benefits from tax accounting method changes. These items were partially offset by an estimated $10 million decrease in electric margins from changes in sales caused by weather conditions in Alliant Energy’s service territories. Estimated increases to Alliant Energy’s electric margins from the impacts of weather during the second quarters of 2013 and 2012 were $3 million and $13 million, respectively. The higher transmission rider revenues were offset by higher electric transmission service expenses.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Electric margins and MWh sales for Alliant Energy for the six months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | MWhs Sold (MWhs in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $466.9 | $442.5 | 6% | 3,747 | 3,597 | 4% |
| Commercial | 295.6 | 279.2 | 6% | 3,048 | 3,049 | —% |
| Industrial | 356.2 | 347.4 | 3% | 5,584 | 5,679 | (2%) |
| Retail subtotal | 1,118.7 | 1,069.1 | 5% | 12,379 | 12,325 | —% |
| Sales for resale: | ||||||
| Wholesale | 92.3 | 87.0 | 6% | 1,717 | 1,535 | 12% |
| Bulk power and other | 8.3 | 5.8 | 43% | 436 | 447 | (2%) |
| Other | 26.0 | 23.1 | 13% | 83 | 74 | 12% |
| Total revenues/sales | 1,245.3 | 1,185.0 | 5% | 14,615 | 14,381 | 2% |
| Electric production fuel expense | 200.1 | 138.7 | 44% | |||
| Energy purchases expense | 137.0 | 190.1 | (28%) | |||
| Purchased electric capacity expense | 109.0 | 132.2 | (18%) | |||
| Electric margins (a) | $799.2 | $724.0 | 10% |
(a) Includes $38 million and $40 million of credits on Iowa retail electric customers’ bills for the six months ended June 30, 2013 and 2012, respectively, resulting from IPL’s electric tax benefit rider. IPL’s electric tax benefit rider is expected to result in reductions in electric revenues that are offset by reductions in income tax expense for the years ended December 31, 2013 and 2012.
Electric margins increased $75 million, or 10%, primarily due to $34 million of higher revenues at IPL related to changes in recovery of transmission costs related to the transmission rider, $26 million of purchased electric capacity expenses at WPL for the six months ended June 30, 2012 related to the Riverside PPA, which terminated in conjunction with WPL’s acquisition of Riverside in December 2012, $11 million of revenues at IPL for the six months ended June 30, 2013 due to the revenue requirement adjustment related to certain tax benefits from tax accounting method changes and an estimated $5 million increase in electric margins from changes in sales caused by weather conditions in Alliant Energy’s service territories. Estimated increases to Alliant Energy’s electric margins from the impacts of weather during the six months ended June 30, 2013 and 2012 were $6 million and $1 million, respectively. The higher transmission rider revenues were offset by higher electric transmission service expenses.
Weather Conditions - Heating degree days (HDD) and cooling degree days (CDD) in Alliant Energy’s service territories for the three and six months ended June 30 were as follows:
| HDD (a): | Three Months Actual 2013 | 2012 | Normal | Six Months Actual 2013 | 2012 | Normal |
|---|---|---|---|---|---|---|
| Cedar Rapids, Iowa (IPL) | 775 | 510 | 700 | 4,296 | 3,202 | 4,125 |
| Madison, Wisconsin (WPL) | 897 | 652 | 836 | 4,642 | 3,369 | 4,347 |
| CDD (a): | ||||||
| Cedar Rapids, Iowa (IPL) | 246 | 317 | 221 | 246 | 345 | 222 |
| Madison, Wisconsin (WPL) | 190 | 310 | 176 | 190 | 336 | 176 |
(a) HDD and CDD are calculated using a simple average of the high and low temperatures each day compared to a 65-degree base. Normal degree days are calculated using a rolling 20-year average of historical HDD and CDD.
Electric Production Fuel and Energy Purchases (Fuel-related) Cost Recoveries - Alliant Energy burns coal and other fossil fuels to produce electricity at its generating facilities. The cost of fossil fuels used during each period is included in electric production fuel expense. Alliant Energy also purchases electricity to meet the demand of its customers and charges these costs to energy purchases expense. Alliant Energy’s electric production fuel expense increased $18 million or 27%, and $61 million or 44%, for the three- and six-month periods, respectively. Alliant Energy’s energy purchases expense decreased $29 million or 29%, and $53 million or 28%, for the three- and six-month periods, respectively. Higher MISO dispatch of WPL’s generating facilities for the three and six months ended June 30, 2013 compared to the same periods in 2012 resulted in an increase in electric production fuel expense and a decrease in energy purchases expense for Alliant Energy and WPL. Changes in the under-/over-collection of fuel-related costs at IPL decreased electric production fuel expense for the three-month period for Alliant Energy and IPL. The impact of changes in electricity volumes generated from Alliant Energy’s generating facilities was largely offset by the impact of the changes in energy volumes purchased and changes in bulk power sales volumes discussed below.
Due to IPL’s rate recovery mechanisms for fuel-related costs, changes in fuel-related costs resulted in comparable changes in electric revenues and, therefore, did not have a significant impact on IPL’s electric margins. WPL’s rate recovery mechanism for wholesale fuel-related costs also provides for adjustments to its wholesale electric rates for changes in commodity costs, thereby mitigating impacts of changes to commodity costs on its electric margins.
WPL’s retail fuel-related costs incurred during the three and six months ended June 30, 2013 and 2012 were lower than the forecasted fuel-related costs used to set retail rates during such periods. WPL estimates the lower than forecasted retail fuel-related costs increased electric margins by approximately $1 million and $2 million during the three and six months ended June 30, 2013, respectively, and approximately $2 million and $3 million during the three and six months ended June 30, 2012, respectively.
Purchased Electric Capacity Expenses - Alliant Energy enters into PPAs to help meet the electricity demand of IPL’s and WPL’s customers. Certain of these PPAs include minimum payments for IPL’s and WPL’s rights to electric generating capacity. The Riverside PPA terminated in conjunction with WPL’s acquisition of Riverside in December 2012. Details of purchased electric capacity expense included in the utility electric margins table above for the three and six months ended June 30 were as follows (in millions):
| Three Months 2013 | 2012 | Six Months 2013 | 2012 | |
|---|---|---|---|---|
| DAEC PPA (IPL) | $36 | $36 | $77 | $76 |
| Kewaunee PPA (WPL) | 15 | 14 | 31 | 29 |
| Riverside PPA (WPL) | — | 20 | — | 26 |
| Other | 1 | 1 | 1 | 1 |
| $52 | $71 | $109 | $132 |
Sales Trends - Retail sales volumes decreased 1% in the second quarter of 2013 and were relatively flat for the six months ended June 30, 2013 compared to the same periods in 2012. The decrease in retail sales volumes in the second quarter of 2013 was primarily due to the warm weather conditions during the second quarter of 2012. Retail sales volumes during the six months ended June 30, 2013 were relatively flat due to increased sales volumes caused by changes in weather conditions in Alliant Energy’s service territories, substantially offset by an extra day of sales during the first quarter of 2012 due to the leap year and a decrease in industrial sales volumes at IPL in 2013 due to lower co-generation customer requirements.
Wholesale sales volumes increased 7% and 12% for the three and six months ended June 30, 2013 compared to the same periods in 2012, respectively, primarily due to the impact of changes in sales to WPL’s partial-requirement wholesale customers that have contractual options to be served by WPL, other power supply sources or the MISO market.
Bulk power and other revenue increases were largely due to changes in revenues from sales in the wholesale energy markets operated by MISO and PJM Interconnection, LLC. These changes are impacted by several factors, including the availability and dispatch of Alliant Energy’s generating facilities and electricity demand within these wholesale energy markets. Changes in bulk power and other sales revenues were offset by changes in fuel-related costs and therefore did not have a significant impact on electric margins.
Refer to Note 2 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of IPL’s revenue requirement adjustment, which became effective in January 2013, and WPL retail rate cases, including a retail electric base rate freeze at WPL through December 31, 2014 and a retail fuel-related rate filing at WPL filed in July 2013. Refer to “Rate Matters” for discussion of a potential future IPL retail electric base rate case filing. Refer to “Other Future Considerations” for discussion of litigation related to a renewable power developer seeking to distribute energy in IPL’s service territory, which may impact IPL’s future electric sales, and an amended agreement with a large IPL wholesale electric customer.
Utility Gas Margins - Gas margins are defined as gas operating revenues less cost of gas sold. Management believes that gas margins provide a more meaningful basis for evaluating utility operations than gas operating revenues since cost of gas sold is generally passed through to customers, and, therefore, results in changes to gas operating revenues that are comparable to changes in cost of gas sold.
Second Quarter 2013 vs. Second Quarter 2012 Summary - Gas margins and Dth sales for Alliant Energy for the three months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | Dths Sold (Dths in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $41.1 | $27.4 | 50% | 4,377 | 2,761 | 59% |
| Commercial | 21.9 | 13.6 | 61% | 3,185 | 2,283 | 40% |
| Industrial | 3.5 | 1.9 | 84% | 640 | 463 | 38% |
| Retail subtotal | 66.5 | 42.9 | 55% | 8,202 | 5,507 | 49% |
| Transportation/other | 6.9 | 7.1 | (3%) | 13,035 | 13,888 | (6%) |
| Total revenues/sales | 73.4 | 50.0 | 47% | 21,237 | 19,395 | 9% |
| Cost of gas sold | 38.9 | 18.6 | 109% | |||
| Gas margins (a) | $34.5 | $31.4 | 10% |
(a) Includes $3 million of credits on Iowa retail gas customers’ bills for the second quarter of 2013 resulting from IPL’s gas tax benefit rider. IPL’s gas tax benefit rider is expected to result in reductions in gas revenues that are offset by reductions in income tax expense for the year ended December 31, 2013.
Gas margins increased $3 million, or 10%, primarily due to an estimated $3 million increase in gas margins from changes in sales caused by weather conditions in Alliant Energy’s service territories, $3 million of higher revenues due to the impact of IPL’s retail gas base rate increase effective in January 2013, $2 million of higher energy conservation revenues at IPL and an increase in weather-normalized retail sales volumes at WPL. Estimated increases (decreases) to Alliant Energy’s gas margins from the impacts of weather during the second quarters of 2013 and 2012 were $1 million and ($2) million, respectively. These items were partially offset by $3 million of lower revenues due to the impact of WPL’s retail gas base rate decrease effective in January 2013 and $3 million of decreased revenues in the second quarter of 2013 due to credits on Iowa retail gas customers’ bills resulting from the gas tax benefit rider at IPL. Changes in energy conservation revenues at IPL were mostly offset by changes in energy conservation expenses at IPL included in other operation and maintenance expenses.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Gas margins and Dth sales for Alliant Energy for the six months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | Dths Sold (Dths in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $158.9 | $125.9 | 26% | 18,263 | 13,288 | 37% |
| Commercial | 86.5 | 68.8 | 26% | 12,152 | 9,386 | 29% |
| Industrial | 9.7 | 7.8 | 24% | 1,636 | 1,415 | 16% |
| Retail subtotal | 255.1 | 202.5 | 26% | 32,051 | 24,089 | 33% |
| Transportation/other | 15.6 | 14.6 | 7% | 29,494 | 27,008 | 9% |
| Total revenues/sales | 270.7 | 217.1 | 25% | 61,545 | 51,097 | 20% |
| Cost of gas sold | 166.9 | 123.4 | 35% | |||
| Gas margins (a) | $103.8 | $93.7 | 11% |
(a) Includes $5 million of credits on Iowa retail gas customers’ bills for the six months ended June 30, 2013 resulting from IPL’s gas tax benefit rider. IPL’s gas tax benefit rider is expected to result in reductions in gas revenues that are offset by reductions in income tax expense for the year ended December 31, 2013.
Gas margins increased $10 million, or 11%, primarily due to an estimated $14 million increase in gas margins from changes in sales caused by weather conditions in Alliant Energy’s service territories, $5 million of higher revenues due to the impact of IPL’s retail gas base rate increase effective in January 2013, $4 million of higher energy conservation revenues at IPL and an increase in weather-normalized retail sales volumes at WPL. Estimated increases (decreases) to Alliant Energy’s gas margins from the impacts of weather during the six months ended June 30, 2013 and 2012 were $2 million and ($12) million, respectively. These items were partially offset by $9 million of lower revenues due to the impact of WPL’s retail gas base rate decrease effective in January 2013 and $5 million of decreased revenues during the six months ended June 30, 2013 due to credits on Iowa retail gas customers’ bills resulting from the gas tax benefit rider at IPL. Changes in energy conservation revenues at IPL were mostly offset by changes in energy conservation expenses at IPL included in other operation and maintenance expenses.
Refer to “Utility Electric Margins” for details of Alliant Energy’s HDD data. Refer to Note 2 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of retail base rate changes at IPL and WPL effective in January 2013. Refer to Note 1(b) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of IPL’s gas tax benefit rider.
Utility Other Revenues - Other revenues for the utilities increased $4 million and $8 million for the three- and six-month periods, respectively, primarily due to higher coal sales at WPL. Changes in utility other revenues were largely offset by related changes in utility other operation and maintenance expenses.
Electric Transmission Service Expense -
Second Quarter 2013 vs. Second Quarter 2012 Summary - Alliant Energy’s electric transmission service expense for the utilities increased $20 million for the three-month period primarily due to $9 million of higher electric transmission service costs billed by ITC to IPL during the second quarter of 2013 compared to the same period in 2012 due to an increase in transmission service rates and $8 million of changes in the under-/over-collection of electric transmission service expenses through the transmission cost rider at IPL. IPL is currently recovering the Iowa retail portion of these increased electric transmission service costs from its retail electric customers in Iowa through the transmission cost rider resulting in an offsetting increase in electric revenues.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Alliant Energy’s electric transmission service expense for the utilities increased $43 million for the six-month period primarily due to $18 million of higher electric transmission service costs billed by ITC to IPL during the six months ended June 30, 2013 compared to the same period in 2012 due to an increase in transmission service rates, $18 million of changes in the under-/over-collection of electric transmission service expenses through the transmission cost rider at IPL and $3 million of higher electric transmission service costs billed by ATC to WPL during the six months ended June 30, 2013 compared to the same period in 2012 due to a modest increase in transmission service rates.
Utility Other Operation and Maintenance Expenses - Alliant Energy’s other operation and maintenance expenses for the utilities for the three- and six-month periods were as follows (amounts represent variances between the periods in millions):
Second Quarter 2013 vs. Second Quarter 2012 Summary:
| Alliant Energy | IPL | WPL | |
|---|---|---|---|
| Regulatory-related credits from WPL’s 2013/2014 rate case decision recorded in the second quarter of 2012 (a) | $5 | $— | $5 |
| Higher generation operation and maintenance expenses at WPL (b) | 4 | — | 4 |
| Higher expenses related to coal sales at WPL (c) | 3 | — | 3 |
| Lower energy conservation cost recovery amortizations at WPL (d) | (5) | — | (5) |
| Other | 2 | (1) | 3 |
| $9 | ($1) | $10 |
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary:
| Alliant Energy | IPL | WPL | |
|---|---|---|---|
| Higher generation operation and maintenance expenses at WPL (b) | $6 | $— | $6 |
| Higher expenses related to coal sales at WPL (c) | 5 | — | 5 |
| Regulatory-related credits from WPL’s 2013/2014 rate case decision recorded in the second quarter of 2012 (a) | 5 | — | 5 |
| Higher allocated cost of capital charges from Corporate Services (e) | 3 | 2 | 1 |
| Higher energy conservation expenses at IPL (f) | 2 | 2 | — |
| Lower energy conservation cost recovery amortizations at WPL (d) | (10) | — | (10) |
| Other | (1) | (1) | — |
| $10 | $3 | $7 |
(a) Refer to Note 1(b) of the “Combined Notes to Condensed Consolidated Financial Statements” for details of regulatory-related credits recorded by Alliant Energy and WPL in the second quarter of 2012 due to the PSCW’s order in July 2012 for WPL’s 2013/2014 test period electric and gas base rate case.
(b) Resulting from the timing of maintenance projects at WPL’s electric generating facilities, and additional operation and maintenance expenses related to Riverside, which was acquired in December 2012.
(c) Changes in expenses related to coal sales at WPL were largely offset by changes in coal sales revenue at WPL.
(d) The PSCW order in July 2012 for WPL’s 2013/2014 test period electric and gas base rate case authorized lower energy conservation cost recovery amortizations effective January 2013.
(e) Cost of capital charges allocated by Corporate Services to IPL and WPL in accordance with a new service agreement implemented during 2012.
(f) Changes in energy conservation expenses at IPL were largely offset by changes in electric and gas energy conservation revenues at IPL.
Depreciation and Amortization Expenses - Depreciation and amortization expenses increased $12 million and $22 million for the three- and six-month periods, respectively, primarily due to depreciation expense at WPL related to Riverside, which was acquired in December 2012, WPL’s SCR project at Edgewater Unit 5, which was placed in service in the fourth quarter of 2012, and new depreciation rates implemented by WPL effective January 2013.
Interest Expense - Alliant Energy’s interest expense increased $4 million and $8 million for the three- and six-month periods, respectively, primarily due to $1 million and $3 million of interest expense, respectively, recorded in 2013 for WPL’s 2.25% debentures issued in November 2012 to fund a portion of the purchase price of Riverside, and $1 million and $3 million of capitalized interest, respectively, recognized in 2012 for the Franklin County wind project.
AFUDC - AFUDC increased $2 million and $4 million for the three- and six-month periods, respectively, primarily due to AFUDC recognized in 2013 for IPL’s emission controls projects at Ottumwa Unit 1 and George Neal Units 3 and 4.
Income Taxes - Details of the effective income tax rates for Alliant Energy’s continuing operations during the three and six months ended June 30 were as follows:
| Three Months 2013 | 2012 | Six Months 2013 | 2012 | |
|---|---|---|---|---|
| Statutory federal income tax rate | 35.0% | 35.0% | 35.0% | 35.0% |
| IPL’s tax benefit riders | (11.7) | (11.7) | (12.3) | (11.9) |
| Production tax credits | (7.9) | (6.3) | (7.7) | (6.6) |
| Effect of rate-making on property-related differences | (6.4) | (4.0) | (5.6) | (3.6) |
| State apportionment changes | — | — | — | 9.7 |
| Other items, net | 4.3 | 6.5 | 3.6 | 5.7 |
| Overall income tax rate | 13.3% | 19.5% | 13.0% | 28.3% |
Refer to Note 4 of the “Combined Notes to Condensed Consolidated Financial Statements” for additional discussion of IPL’s tax benefit riders, production tax credits, the effect of rate-making on property-related differences and state apportionment changes.
Income (Loss) from Discontinued Operations, Net of Tax - Refer to Note 14 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of Alliant Energy’s discontinued operations.
Preferred Dividend Requirements of Subsidiaries - Preferred dividend requirements of subsidiaries increased $5 million for the six-month period primarily due to IPL and WPL recording charges of $5 million and $1 million in the first quarter of 2013, respectively, related to the redemption of preferred stock. Refer to Note 7 of the “Combined Notes to Condensed Consolidated Financial Statements” for additional discussion of IPL’s and WPL’s preferred stock transactions.
IPL’S RESULTS OF OPERATIONS
Overview - Second Quarter Results - Earnings available for common stock increased $6 million primarily due to the revenue requirement adjustment related to certain tax benefits from tax accounting method changes resulting in higher electric revenues recorded in the second quarter of 2013 compared to the second quarter of 2012, the impact of a retail gas base rate increase effective in January 2013 and AFUDC recognized in the second quarter of 2013 for emission controls projects at Ottumwa Unit 1 and George Neal Units 3 and 4.
Electric Margins - Electric margins are defined as electric operating revenues less electric production fuel, energy purchases and purchased electric capacity expenses. Management believes that electric margins provide a more meaningful basis for evaluating utility operations than electric operating revenues since electric production fuel, energy purchases and purchased electric capacity expenses are generally passed through to customers, and, therefore, result in changes to electric operating revenues that are comparable to changes in electric production fuel, energy purchases and purchased electric capacity expenses.
Second Quarter 2013 vs. Second Quarter 2012 Summary - Electric margins and MWh sales for IPL for the three months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | MWhs Sold (MWhs in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $121.7 | $120.4 | 1% | 922 | 922 | —% |
| Commercial | 91.3 | 86.4 | 6% | 958 | 977 | (2%) |
| Industrial | 101.1 | 98.6 | 3% | 1,772 | 1,759 | 1% |
| Retail subtotal | 314.1 | 305.4 | 3% | 3,652 | 3,658 | —% |
| Sales for resale: | ||||||
| Wholesale | 7.1 | 7.0 | 1% | 104 | 103 | 1% |
| Bulk power and other | — | 1.7 | (100%) | 63 | 64 | (2%) |
| Other | 8.4 | 6.9 | 22% | 21 | 21 | —% |
| Total revenues/sales | 329.6 | 321.0 | 3% | 3,840 | 3,846 | —% |
| Electric production fuel expense | 27.0 | 38.2 | (29%) | |||
| Energy purchases expense | 47.9 | 43.8 | 9% | |||
| Purchased electric capacity expense | 36.2 | 36.0 | 1% | |||
| Electric margins (a) | $218.5 | $203.0 | 8% |
(a) Includes $20 million of credits on Iowa retail electric customers’ bills for both the second quarters of 2013 and 2012 resulting from the electric tax benefit rider. The electric tax benefit rider is expected to result in reductions in electric revenues that are offset by reductions in income tax expense for the years ended December 31, 2013 and 2012.
Electric margins increased $16 million, or 8%, primarily due to $15 million of higher revenues related to changes in recovery of transmission costs related to the transmission rider and $5 million of revenues in the second quarter of 2013 due to the revenue requirement adjustment related to certain tax benefits from tax accounting method changes. These items were partially offset by an estimated $4 million decrease in electric margins from changes in sales caused by weather conditions in IPL’s service territory. Estimated increases to IPL’s electric margins from the impacts of weather during the second quarters of 2013 and 2012 were $2 million and $6 million, respectively. The higher transmission rider revenues were offset by higher electric transmission service expenses.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Electric margins and MWh sales for IPL for the six months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | MWhs Sold (MWhs in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $262.0 | $236.0 | 11% | 2,058 | 1,943 | 6% |
| Commercial | 183.1 | 161.9 | 13% | 1,945 | 1,930 | 1% |
| Industrial | 204.0 | 185.8 | 10% | 3,425 | 3,518 | (3%) |
| Retail subtotal | 649.1 | 583.7 | 11% | 7,428 | 7,391 | 1% |
| Sales for resale: | ||||||
| Wholesale | 14.4 | 13.1 | 10% | 207 | 202 | 2% |
| Bulk power and other | 0.5 | 3.1 | (84%) | 90 | 109 | (17%) |
| Other | 15.8 | 14.2 | 11% | 41 | 41 | —% |
| Total revenues/sales | 679.8 | 614.1 | 11% | 7,766 | 7,743 | —% |
| Electric production fuel expense | 81.4 | 71.1 | 14% | |||
| Energy purchases expense | 90.2 | 85.0 | 6% | |||
| Purchased electric capacity expense | 77.6 | 77.0 | 1% | |||
| Electric margins (a) | $430.6 | $381.0 | 13% |
(a) Includes $38 million and $40 million of credits on Iowa retail electric customers’ bills for the six months ended June 30, 2013 and 2012, respectively, resulting from the electric tax benefit rider. The electric tax benefit rider is expected to result in reductions in electric revenues that are offset by reductions in income tax expense for the years ended December 31, 2013 and 2012.
Electric margins increased $50 million, or 13%, primarily due to $34 million of higher revenues related to changes in recovery of transmission costs related to the transmission rider, $11 million of revenues during the six months ended June 30, 2013 due to the revenue requirement adjustment related to certain tax benefits from tax accounting method changes and an estimated $5 million increase in electric margins from changes in sales caused by weather conditions in IPL’s service territory. Estimated increases (decreases) to IPL’s electric margins from the impacts of weather during the six months ended June 30, 2013 and 2012 were $3 million and ($2) million, respectively. The higher transmission rider revenues were offset by higher electric transmission service expenses.
Refer to “Alliant Energy’s Results of Operations - Utility Electric Margins” for details on IPL’s HDD and CDD data, purchased electric capacity expenses, recoveries of electric production fuel and energy purchases expenses, and sales trends. Refer to “Rate Matters” for discussion of a potential future IPL retail electric base rate case filing. Refer to Note 2 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of IPL’s revenue requirement adjustment, which became effective in January 2013.
Gas Margins - Gas margins are defined as gas operating revenues less cost of gas sold. Management believes that gas margins provide a more meaningful basis for evaluating utility operations than gas operating revenues since cost of gas sold is generally passed through to customers, and, therefore, results in changes to gas operating revenues that are comparable to changes in cost of gas sold.
Second Quarter 2013 vs. Second Quarter 2012 Summary - Gas margins and Dth sales for IPL for the three months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | Dths Sold (Dths in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $22.9 | $14.5 | 58% | 2,355 | 1,325 | 78% |
| Commercial | 11.8 | 6.9 | 71% | 1,659 | 1,058 | 57% |
| Industrial | 2.8 | 1.4 | 100% | 502 | 364 | 38% |
| Retail subtotal | 37.5 | 22.8 | 64% | 4,516 | 2,747 | 64% |
| Transportation/other | 4.5 | 4.0 | 13% | 7,413 | 7,203 | 3% |
| Total revenues/sales | 42.0 | 26.8 | 57% | 11,929 | 9,950 | 20% |
| Cost of gas sold | 21.8 | 10.3 | 112% | |||
| Gas margins (a) | $20.2 | $16.5 | 22% |
(a) Includes $3 million of credits on Iowa retail gas customers’ bills for the second quarter of 2013 resulting from the gas tax benefit rider. The gas tax benefit rider is expected to result in reductions in gas revenues that are offset by reductions in income tax expense for the year ended December 31, 2013.
Gas margins increased $4 million, or 22%, largely due to $3 million of higher revenues due to the impact of IPL’s retail gas base rate increase effective in January 2013, an estimated $2 million increase in gas margins from changes in sales caused by weather conditions in IPL’s service territory and $2 million of higher energy conservation revenues. Estimated increases (decreases) to IPL’s gas margins from the impacts of weather during the second quarters of 2013 and 2012 were $1 million and ($1) million, respectively. These items were partially offset by $3 million of decreased revenues in the second quarter of 2013 due to credits on Iowa retail gas customers’ bills resulting from the gas tax benefit rider. Changes in energy conservation revenues were mostly offset by changes in energy conservation expenses in other operation and maintenance expenses.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Gas margins and Dth sales for IPL for the six months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | Dths Sold (Dths in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $91.4 | $68.3 | 34% | 10,324 | 7,316 | 41% |
| Commercial | 48.2 | 37.4 | 29% | 6,618 | 5,092 | 30% |
| Industrial | 6.8 | 5.6 | 21% | 1,160 | 1,074 | 8% |
| Retail subtotal | 146.4 | 111.3 | 32% | 18,102 | 13,482 | 34% |
| Transportation/other | 9.9 | 8.3 | 19% | 15,971 | 15,096 | 6% |
| Total revenues/sales | 156.3 | 119.6 | 31% | 34,073 | 28,578 | 19% |
| Cost of gas sold | 93.9 | 67.6 | 39% | |||
| Gas margins (a) | $62.4 | $52.0 | 20% |
(a) Includes $5 million of credits on Iowa retail gas customers’ bills for the six months ended June 30, 2013 resulting from the gas tax benefit rider. The gas tax benefit rider is expected to result in reductions in gas revenues that are offset by reductions in income tax expense for the year ended December 31, 2013.
Gas margins increased $10 million, or 20%, largely due to an estimated $7 million increase in gas margins from changes in sales caused by weather conditions in IPL’s service territory, $5 million of higher revenues due to the impact of IPL’s retail gas base rate increase effective in January 2013 and $4 million of higher energy conservation revenues. Estimated increases (decreases) to IPL’s gas margins from the impacts of weather during the six months ended June 30, 2013 and 2012 were $1 million and ($6) million, respectively. These items were partially offset by $5 million of decreased revenues during the six months ended June 30, 2013 due to credits on Iowa retail gas customers’ bills resulting from the gas tax benefit rider. Changes in energy conservation revenues were mostly offset by changes in energy conservation expenses in other operation and maintenance expenses.
Refer to “Alliant Energy’s Results of Operations - Utility Electric Margins” for details of IPL’s HDD data. Refer to Note 2 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of the gas base rate increase effective in January 2013 for IPL’s Iowa retail customers. Refer to Note 1(b) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of IPL’s gas tax benefit rider.
Electric Transmission Service Expense -
Second Quarter 2013 vs. Second Quarter 2012 Summary - Electric transmission service expense increased $19 million for the three-month period primarily due to $9 million of higher electric transmission service costs billed by ITC to IPL during the second quarter of 2013 compared to the same period in 2012 due to an increase in transmission service rates and $8 million of changes in the under-/over-collection of electric transmission service expenses through the transmission cost rider. IPL is currently recovering the Iowa retail portion of these increased electric transmission service costs from its retail electric customers in Iowa through the transmission cost rider resulting in an offsetting increase in electric revenues.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Electric transmission service expense increased $38 million for the six-month period primarily due to $18 million of higher electric transmission service costs billed by ITC to IPL during the six months ended June 30, 2013 compared to the same period in 2012 due to an increase in transmission service rates and $18 million of changes in the under-/over-collection of electric transmission service expenses through the transmission cost rider.
Other Operation and Maintenance Expenses -
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Other operation and maintenance expenses increased $3 million for the six-month period primarily due to $2 million of higher energy conservation expenses and $2 million of higher allocated cost of capital charges from Corporate Services. Changes in energy conservation expenses were largely offset by changes in electric and gas energy conservation revenues.
Refer to “Alliant Energy’s Results of Operations - Utility Other Operation and Maintenance Expenses” for additional details of IPL’s other operation and maintenance expenses.
AFUDC - AFUDC increased $3 million and $5 million for the three- and six-month periods, respectively, primarily due to AFUDC recognized in 2013 for IPL’s emission controls projects at Ottumwa Unit 1 and George Neal Units 3 and 4.
Income Taxes - Details of IPL’s effective income tax rates during the three and six months ended June 30 were as follows:
| Three Months 2013 | 2012 | Six Months 2013 | 2012 | |
|---|---|---|---|---|
| Statutory federal income tax rate | 35.0% | 35.0% | 35.0% | 35.0% |
| Tax benefit riders | (33.3) | (34.9) | (35.6) | (35.5) |
| Effect of rate-making on property-related differences | (17.4) | (8.1) | (15.5) | (7.7) |
| Production tax credits | (10.5) | (8.6) | (10.1) | (8.9) |
| State apportionment changes | — | — | — | 34.6 |
| Other items, net | 1.5 | 4.6 | 1.9 | 5.1 |
| Overall income tax rate | (24.7%) | (12.0%) | (24.3%) | 22.6% |
Refer to Note 4 of the “Combined Notes to Condensed Consolidated Financial Statements” for additional discussion of the tax benefit riders, effect of rate-making on property-related differences, production tax credits and state apportionment changes.
Preferred Dividend Requirements - Preferred dividend requirements increased $5 million for the six-month period primarily due to IPL recording charges of $5 million in the first quarter of 2013 related to the redemption of preferred stock. Refer to Note 7 of the “Combined Notes to Condensed Consolidated Financial Statements” for additional discussion of IPL’s preferred stock transactions.
WPL’S RESULTS OF OPERATIONS
Overview - Second Quarter Results - WPL’s earnings available for common stock decreased $1 million primarily due to higher depreciation expense largely due to the purchase of Riverside in December 2012, lower retail electric sales due to unseasonably warm weather conditions in WPL’s service territory in the second quarter of 2012, regulatory-related credits from WPL’s 2013/2014 rate case decision recorded in the second quarter of 2012 and higher generation operation and maintenance expenses. These items were substantially offset by purchased electric capacity expense related to the Riverside PPA in the second quarter of 2012 and lower energy conservation cost recovery amortizations.
Electric Margins - Electric margins are defined as electric operating revenues less electric production fuel, energy purchases and purchased electric capacity expenses. Management believes that electric margins provide a more meaningful basis for evaluating utility operations than electric operating revenues since electric production fuel, energy purchases and purchased electric capacity expenses are generally passed through to customers, and, therefore, result in changes to electric operating revenues that are comparable to changes in electric production fuel, energy purchases and purchased electric capacity expenses.
Second Quarter 2013 vs. Second Quarter 2012 Summary - Electric margins and MWh sales for WPL for the three months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | MWhs Sold (MWhs in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $97.1 | $103.9 | (7%) | 776 | 812 | (4%) |
| Commercial | 57.1 | 59.9 | (5%) | 545 | 557 | (2%) |
| Industrial | 79.3 | 84.8 | (6%) | 1,115 | 1,105 | 1% |
| Retail subtotal | 233.5 | 248.6 | (6%) | 2,436 | 2,474 | (2%) |
| Sales for resale: | ||||||
| Wholesale | 38.1 | 36.7 | 4% | 729 | 675 | 8% |
| Bulk power and other | 5.1 | 1.3 | 292% | 222 | 298 | (26%) |
| Other | 5.8 | 5.0 | 16% | 22 | 16 | 38% |
| Total revenues/sales | 282.5 | 291.6 | (3%) | 3,409 | 3,463 | (2%) |
| Electric production fuel expense | 59.2 | 29.6 | 100% | |||
| Energy purchases expense | 23.9 | 57.3 | (58%) | |||
| Purchased electric capacity expense | 15.8 | 34.7 | (54%) | |||
| Electric margins | $183.6 | $170.0 | 8% |
58
Electric margins increased $14 million, or 8%, primarily due to $20 million of purchased electric capacity expenses in the second quarter of 2012 related to the Riverside PPA, which terminated in conjunction with WPL’s acquisition of Riverside in December 2012. This item was partially offset by an estimated $6 million decrease in electric margins from changes in sales caused by weather conditions in WPL’s service territory. Estimated increases to WPL’s electric margins from the impacts of weather during the second quarters of 2013 and 2012 were $1 million and $7 million, respectively.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Electric margins and MWh sales for WPL for the six months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | MWhs Sold (MWhs in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $204.9 | $206.5 | (1%) | 1,689 | 1,654 | 2% |
| Commercial | 112.5 | 117.3 | (4%) | 1,103 | 1,119 | (1%) |
| Industrial | 152.2 | 161.6 | (6%) | 2,159 | 2,161 | —% |
| Retail subtotal | 469.6 | 485.4 | (3%) | 4,951 | 4,934 | —% |
| Sales for resale: | ||||||
| Wholesale | 77.9 | 73.9 | 5% | 1,510 | 1,333 | 13% |
| Bulk power and other | 7.8 | 2.7 | 189% | 346 | 338 | 2% |
| Other | 10.2 | 8.9 | 15% | 42 | 33 | 27% |
| Total revenues/sales | 565.5 | 570.9 | (1%) | 6,849 | 6,638 | 3% |
| Electric production fuel expense | 118.7 | 67.6 | 76% | |||
| Energy purchases expense | 46.8 | 105.1 | (55%) | |||
| Purchased electric capacity expense | 31.4 | 55.2 | (43%) | |||
| Electric margins | $368.6 | $343.0 | 7% |
Electric margins increased $26 million, or 7%, primarily due to $26 million of purchased electric capacity expenses during the six months ended June 30, 2012 related to the Riverside PPA, which terminated in conjunction with WPL’s acquisition of Riverside in December 2012.
Refer to “Alliant Energy’s Results of Operations - Utility Electric Margins” for details of WPL’s HDD and CDD data, purchased electric capacity expenses, recoveries of electric production fuel and energy purchases expenses, and sales trends. Refer to Note 2 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of retail rate cases, including a retail electric base rate freeze by WPL through December 31, 2014 and a retail fuel-related rate filing at WPL filed in July 2013.
Gas Margins - Gas margins are defined as gas operating revenues less cost of gas sold. Management believes that gas margins provide a more meaningful basis for evaluating utility operations than gas operating revenues since cost of gas sold is generally passed through to customers, and, therefore, results in changes to gas operating revenues that are comparable to changes in cost of gas sold.
Second Quarter 2013 vs. Second Quarter 2012 Summary - Gas margins and Dth sales for WPL for the three months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | Dths Sold (Dths in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $18.2 | $12.9 | 41% | 2,022 | 1,436 | 41% |
| Commercial | 10.1 | 6.7 | 51% | 1,526 | 1,225 | 25% |
| Industrial | 0.7 | 0.5 | 40% | 138 | 99 | 39% |
| Retail subtotal | 29.0 | 20.1 | 44% | 3,686 | 2,760 | 34% |
| Transportation/other | 2.4 | 3.1 | (23%) | 5,622 | 6,685 | (16%) |
| Total revenues/sales | 31.4 | 23.2 | 35% | 9,308 | 9,445 | (1%) |
| Cost of gas sold | 17.1 | 8.3 | 106% | |||
| Gas margins | $14.3 | $14.9 | (4%) |
59
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Gas margins and Dth sales for WPL for the six months ended June 30 were as follows:
| Revenues and Costs (dollars in millions) 2013 | 2012 | Change | Dths Sold (Dths in thousands) 2013 | 2012 | Change | |
|---|---|---|---|---|---|---|
| Residential | $67.5 | $57.6 | 17% | 7,939 | 5,972 | 33% |
| Commercial | 38.3 | 31.4 | 22% | 5,534 | 4,294 | 29% |
| Industrial | 2.9 | 2.2 | 32% | 476 | 341 | 40% |
| Retail subtotal | 108.7 | 91.2 | 19% | 13,949 | 10,607 | 32% |
| Transportation/other | 5.7 | 6.3 | (10%) | 13,523 | 11,912 | 14% |
| Total revenues/sales | 114.4 | 97.5 | 17% | 27,472 | 22,519 | 22% |
| Cost of gas sold | 73.0 | 55.8 | 31% | |||
| Margins | $41.4 | $41.7 | (1%) |
Gas margins decreased 1% largely due to $9 million of lower revenues due to the impact of WPL’s retail gas base rate decrease effective in January 2013. This item was substantially offset by an estimated $7 million increase in gas margins from changes in sales caused by weather conditions in WPL’s service territory and an increase in weather-normalized retail sales volumes. Estimated increases (decreases) to WPL’s gas margins from the impacts of weather during the six months ended June 30, 2013 and 2012 were $1 million and ($6) million, respectively.
Refer to “Alliant Energy’s Results of Operations - Utility Electric Margins” for WPL’s HDD data. Refer to Note 2 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of retail rate cases, including a retail gas base rate decrease effective in January 2013.
Other Revenues - Other revenues increased $5 million and $8 million for the three- and six-month periods, respectively, primarily due to higher coal sales. Changes in other revenues were largely offset by related changes in other operation and maintenance expenses.
Electric Transmission Service Expense -
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Electric transmission service expense increased $5 million for the six-month period primarily due to $3 million of higher electric transmission service costs billed by ATC to WPL during the six months ended June 30, 2013 compared to the same period in 2012 due to an increase in transmission service rates.
Other Operation and Maintenance Expenses -
Second Quarter 2013 vs. Second Quarter 2012 Summary - Other operation and maintenance expenses increased $10 million for the three-month period primarily due to $5 million of regulatory-related credits from WPL’s 2013/2014 rate case decision recorded in the second quarter of 2012, $4 million of higher generation operation and maintenance expenses, $3 million of higher expenses related to coal sales and higher other administrative and general expenses. These items were partially offset by $5 million of lower energy conservation cost recovery amortizations. Changes in expenses related to coal sales were largely offset by changes in coal sales revenue.
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 Summary - Other operation and maintenance expenses increased $7 million for the six-month period primarily due to $6 million of higher generation operation and maintenance expenses, $5 million of higher expenses related to coal sales, $5 million of regulatory-related credits from WPL’s 2013/2014 rate case decision recorded in the second quarter of 2012 and $1 million of higher allocated cost of capital charges from Corporate Services. These items were partially offset by $10 million of lower energy conservation cost recovery amortizations. Changes in expenses related to coal sales were largely offset by changes in coal sales revenue.
Refer to “Alliant Energy’s Results of Operations - Utility Other Operation and Maintenance Expenses” for additional details of WPL’s other operation and maintenance expenses.
Depreciation and Amortization Expenses - Depreciation and amortization expenses increased $10 million and $17 million for the three- and six-month periods, respectively, primarily due to depreciation expense related to WPL’s acquisition of Riverside in December 2012, WPL’s SCR project at Edgewater Unit 5, which was placed in service in the fourth quarter of 2012, and new depreciation rates implemented by WPL effective in January 2013.
Interest Expense - Interest expense increased $1 million and $3 million for the three- and six-month periods, respectively, primarily due to $1 million and $3 million of interest expense, respectively, recorded in 2013 for WPL’s 2.25% debentures issued in November 2012 to fund a portion of the purchase price of Riverside.
Income Taxes - Details of WPL’s effective income tax rates during the three and six months ended June 30 were as follows:
| Three Months 2013 | 2012 | Six Months 2013 | 2012 | |
|---|---|---|---|---|
| Statutory federal income tax rate | 35.0% | 35.0% | 35.0% | 35.0% |
| Production tax credits | (7.2) | (6.5) | (7.0) | (6.4) |
| State apportionment changes | — | — | — | 6.2 |
| Other items, net | 5.3 | 6.1 | 4.5 | 4.6 |
| Overall income tax rate | 33.1% | 34.6% | 32.5% | 39.4% |
Refer to Note 4 of the “Combined Notes to Condensed Consolidated Financial Statements” for additional discussion of production tax credits and state apportionment changes.
LIQUIDITY AND CAPITAL RESOURCES
A summary of Alliant Energy’s, IPL’s and WPL’s liquidity and capital resources matters is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K, except as described below.
Liquidity Position - At June 30, 2013, Alliant Energy had $12 million of cash and cash equivalents, $722 million ($226 million at the parent company, $245 million at IPL and $251 million at WPL) of available capacity under their revolving credit facilities and $15 million of available capacity at IPL under its sales of accounts receivable program.
Capital Structures - Capital structures at June 30, 2013 were as follows (dollars in millions):
| Alliant Energy (Consolidated) | IPL | WPL | ||||
|---|---|---|---|---|---|---|
| Common equity | $3,160.5 | 47% | $1,555.9 | 50% | $1,601.1 | 52% |
| Preferred stock | 200.0 | 3% | 200.0 | 6% | — | —% |
| Noncontrolling interest | 1.8 | —% | — | —% | — | —% |
| Long-term debt (incl. current maturities) | 3,142.9 | 47% | 1,364.7 | 44% | 1,331.9 | 43% |
| Short-term debt | 223.1 | 3% | — | —% | 148.9 | 5% |
| $6,728.3 | 100% | $3,120.6 | 100% | $3,081.9 | 100% |
Cash Flows - Selected information from the Condensed Consolidated Statements of Cash Flows was as follows (in millions):
| Alliant Energy 2013 | 2012 | IPL 2013 | 2012 | WPL 2013 | 2012 | |
|---|---|---|---|---|---|---|
| Cash and cash equivalents, January 1 | $21.2 | $11.4 | $4.5 | $2.1 | $0.7 | $2.7 |
| Cash flows from (used for): | ||||||
| Operating activities | 423.3 | 339.2 | 173.7 | 76.4 | 225.2 | 181.9 |
| Investing activities | (322.2) | (321.8) | (189.8) | (120.3) | (164.3) | (133.4) |
| Financing activities | (110.8) | 2.0 | 16.7 | 44.6 | (59.1) | (48.7) |
| Net increase (decrease) | (9.7) | 19.4 | 0.6 | 0.7 | 1.8 | (0.2) |
| Cash and cash equivalents, June 30 | $11.5 | $30.8 | $5.1 | $2.8 | $2.5 | $2.5 |
Operating Activities -
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 - Alliant Energy’s cash flows from operating activities increased $84 million primarily due to the timing of electric fuel-related, natural gas and transmission cost recoveries at IPL, $32 million of higher cash flows from changes in the level of IPL’s accounts receivable sold during the six months ended June 30, 2013 compared to the same period in 2012, $26 million of purchased electric capacity payments by WPL during the six months ended June 30, 2012 related to the Riverside PPA and increased collections from IPL’s and WPL’s customers during the six months ended June 30, 2013 caused by the weather impacts on electric and gas retail sales. These items were partially offset by $69 million of cash flows from operations at RMT during the six months ended June 30, 2012 due to changes in working capital requirements associated with renewable energy projects.
IPL’s cash flows from operating activities increased $97 million primarily due to the timing of electric fuel-related, natural gas and transmission cost recoveries, $32 million of higher cash flows from changes in the level of accounts receivable sold during the six months ended June 30, 2013 compared to the same period in 2012 and increased collections from customers during the six months ended June 30, 2013 caused by the weather impacts on electric and gas retail sales. These items were partially offset by $18 million of lower cash flows from income tax payments during the six months ended June 30, 2013 and income tax refunds during the six months ended June 30, 2012.
WPL’s cash flows from operating activities increased $43 million primarily due to $26 million of purchased electric capacity payments during the six months ended June 30, 2012 related to the Riverside PPA, $7 million of lower income tax payments during the six months ended June 30, 2013 compared to the same period in 2012, and increased collections from customers during the six months ended June 30, 2013 caused by the weather impacts on electric and gas retail sales.
Electric Fuel-related, Natural Gas and Transmission Cost Recoveries - IPL has cost recovery mechanisms applicable for its retail electric and gas customers to provide for subsequent adjustments to its electric and gas rates for changes in electric fuel-related and natural gas costs. IPL also has a cost recovery mechanism applicable for its Iowa retail electric customers to provide for subsequent adjustments to its electric rates for changes in electric transmission service expenses. Changes in the timing of IPL’s electric fuel-related, natural gas and transmission cost recoveries resulted in $51 million of higher cash flows from operations for Alliant Energy and IPL during the six months ended June 30, 2013 compared to the same period in 2012.
RMT’s Working Capital Requirements - Cash flows from operations at RMT decreased significantly during the six months ended June 30, 2013 compared to the same period in 2012 largely due to amounts collected during the six months ended June 30, 2012 for customers’ large renewable energy projects completed in late 2011 and early 2012. In January 2013, Alliant Energy sold RMT.
Investing Activities -
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 - Alliant Energy’s cash flows used for investing activities were relatively flat primarily due to $94 million of higher utility construction expenditures, offset by a $62 million cash grant Alliant Energy received during the six months ended June 30, 2013 related to its Franklin County wind project and expenditures of $48 million during the six months ended June 30, 2012 for Corporate Services’ purchase of its corporate headquarters building at the expiration of the lease term. The higher utility construction expenditures were largely due to expenditures for emission controls projects at WPL’s Columbia Units 1 and 2, IPL’s Ottumwa Unit 1 and IPL’s George Neal Units 3 and 4 during the six months ended June 30, 2013, partially offset by expenditures during the six months ended June 30, 2012 for the emission controls project at WPL’s Edgewater Unit 5. Refer to Note 3(b) for further discussion of the Franklin County wind project cash grant.
IPL’s cash flows used for investing activities increased $70 million due to $70 million of higher construction expenditures. The higher construction expenditures were largely due to expenditures for emission controls projects at Ottumwa Unit 1 and George Neal Units 3 and 4 during the six months ended June 30, 2013.
WPL’s cash flows used for investing activities increased $31 million primarily due to $24 million of higher construction expenditures. The higher construction expenditures were largely due to expenditures for emission controls projects at Columbia Units 1 and 2 during the six months ended June 30, 2013, partially offset by expenditures during the six months ended June 30, 2012 for the emission controls project at Edgewater Unit 5.
Financing Activities -
Six Months Ended June 30, 2013 vs. Six Months Ended June 30, 2012 - Alliant Energy’s cash flows used for financing activities increased $113 million primarily due to payments of $211 million to redeem IPL’s and WPL’s cumulative preferred stock in March 2013 and net changes in the amount of commercial paper outstanding at Alliant Energy, IPL and WPL. These items were partially offset by $200 million of proceeds from IPL’s issuance of cumulative preferred stock in March 2013.
IPL’s cash flows from financing activities decreased $28 million primarily due to payments of $150 million to redeem cumulative preferred stock in March 2013 and changes in the amount of commercial paper outstanding. These items were partially offset by $200 million of proceeds from the issuance of cumulative preferred stock in March 2013.
WPL’s cash flows used for financing activities increased $10 million primarily due to payments of $61 million to redeem cumulative preferred stock in March 2013, partially offset by changes in the amount of commercial paper outstanding.
FERC and Public Utility Holding Company Act Financing Authorizations - In October 2011, IPL received authorization from FERC for $750 million of long-term debt securities issuances, $750 million of short-term debt securities outstanding (including borrowings from its parent, with $695 million of remaining authority as of June 30, 2013) and $200 million of preferred stock issuances through 2013 (with $0 remaining authority as of June 30, 2013).
Shelf Registrations - Alliant Energy, IPL and WPL have current shelf registration statements with the Securities and Exchange Commission for availability through December 2014 as follows:
| Alliant Energy | IPL | WPL | |
| Aggregate amount available as of June 30, 2013 | Unspecified | $600 million | $550 million |
| Securities available to be issued | Common stock, debt and other securities | Preferred stock and debt securities | Preferred stock and debt securities |
Common Stock Issuances and Capital Contributions - Refer to Note 5(b) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of Alliant Energy’s common stock issuances during the six months ended June 30, 2013 under its equity-based compensation plans for employees. Refer to Note 6 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of capital contributions from Alliant Energy to IPL, and payments of common stock dividends by IPL and WPL to their parent company during the six months ended June 30, 2013.
Preferred Stock Issuance and Redemptions - Refer to Note 7 of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of IPL’s and WPL’s preferred stock redemptions and IPL’s issuance of preferred stock in March 2013.
Short-term Debt - Alliant Energy’s, IPL’s and WPL’s credit facility agreements each contain a covenant, which requires the entities to maintain certain debt-to-capital ratios in order to borrow under the credit facilities. The required debt-to-capital ratios compared to the actual debt-to-capital ratios at June 30, 2013 were as follows:
| Requirement | Alliant Energy Less than 65% | IPL Less than 58% | WPL Less than 58% |
|---|---|---|---|
| Status at June 30, 2013 | 50% | 44% | 50% |
Refer to Note 8(a) of the “Combined Notes to Condensed Consolidated Financial Statements” for additional information on short-term debt.
Long-term Debt - Refer to Note 8(b) of the “Combined Notes to Condensed Consolidated Financial Statements” for discussion of $55 million of commercial paper outstanding at June 30, 2013 classified as long-term debt.
Off-Balance Sheet Arrangements - A summary of Alliant Energy’s off-balance sheet arrangements is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K, except as described below. Refer to Note 3(a) of the “Combined Notes to Condensed Consolidated Financial Statements” for information regarding IPL’s sales of accounts receivable program. Refer to Note 12(d) of the “Combined Notes to Condensed Consolidated Financial Statements” for information regarding various guarantees and indemnifications related to Alliant Energy’s prior divestiture activities.
Certain Financial Commitments -
Contractual Obligations - A summary of Alliant Energy’s, IPL’s and WPL’s contractual obligations is included in the 2012 Form 10-K and has not changed materially from the items reported in the 2012 Form 10-K, except for the items described in Notes 8, 12(a) and 12(b) of the “Combined Notes to Condensed Consolidated Financial Statements.”
OTHER MATTERS
Market Risk Sensitive Instruments and Positions - Alliant Energy’s, IPL’s and WPL’s primary market risk exposures are associated with commodity prices, investment prices and interest rates. Alliant Energy, IPL and WPL have risk management policies to monitor and assist in mitigating these market risks and use derivative instruments to manage some of the exposures. A summary of Alliant Energy’s, IPL’s and WPL’s market risks is included in the 2012 Form 10-K and such market risks have not changed materially from those reported in the 2012 Form 10-K, except as described below.
Commodity Price - Refer to “Rate Matters” for discussion of refunds recorded by Alliant Energy and WPL as of June 30, 2013 related to the over-collection of fuel-related costs for 2012.
Critical Accounting Policies and Estimates - A summary of Alliant Energy’s, IPL’s and WPL’s critical accounting policies and estimates is included in the 2012 Form 10-K and such policies and estimates have not changed materially from those reported in the 2012 Form 10-K, except as described below.
Contingencies - Alliant Energy, IPL and WPL make assumptions and judgments each reporting period regarding the future outcome of contingent events and record loss contingency amounts for any contingent events that are both probable and reasonably estimated based upon current available information. Note 12 of the “Combined Notes to Condensed Consolidated Financial Statements” provides discussion of contingencies assessed at June 30, 2013 including various pending legal proceedings, guarantees and indemnifications that may have a material impact on Alliant Energy’s, IPL’s and WPL’s financial condition and results of operations.
Regulatory Assets and Regulatory Liabilities - Alliant Energy, IPL and WPL make assumptions and judgments each reporting period regarding whether their regulatory assets are probable of future recovery and their regulatory liabilities are probable future obligations. Note 1(b) of the “Combined Notes to Condensed Consolidated Financial Statements” provides details of the nature and amounts of Alliant Energy’s, IPL’s and WPL’s regulatory assets and regulatory liabilities assessed at June 30, 2013 as well as material changes to their regulatory assets and regulatory liabilities during the six months ended June 30, 2013.
Long-Lived Assets - Alliant Energy, IPL and WPL complete periodic assessments regarding the recoverability of certain long-lived assets when factors indicate the carrying value of such assets may be impaired or such assets are planned to be sold. These assessments require significant assumptions and judgments by management. The long-lived assets assessed for impairment generally include assets within their non-regulated operations that are proposed to be sold or are generating operating losses, and certain long-lived assets within their regulated operations that may not be fully recovered from IPL’s and WPL’s customers as a result of regulatory decisions in the future.
Resources’ Franklin County Wind Project - Note 3(b) of the “Combined Notes to Condensed Consolidated Financial Statements” provides discussion of a $62 million cash grant received in March 2013 for the Franklin County wind project, which is one of Resources’ long-lived assets subject to periodic recoverability assessments. As of June 30, 2013, the carrying value of the Franklin County wind project was $145 million and was recorded in “Non-regulated Generation property, plant and equipment” on Alliant Energy’s Condensed Consolidated Balance Sheet.
WPL’s Bent Tree - Phase I Wind Project - Certain transmission system upgrade costs incurred by WPL in 2011 and 2012 related to its Bent Tree - Phase I wind project have also been subject to periodic recoverability assessments. Reimbursement of these transmission system upgrade costs pursuant to ITC’s Attachment “FF” tariff is dependent on MISO completing a definitive planning phase study and identifying the upgrades as required network upgrades under a Facility Construction Agreement that WPL entered into with ITC and MISO. In March 2013, MISO completed the definitive planning phase study for Bent Tree and determined the transmission system upgrades completed in 2011 and 2012 were required network upgrades. In July 2013, FERC issued an order requiring changes to ITC’s Attachment “FF” tariff. As a result, WPL is uncertain whether it will be reimbursed by ITC for 100% of the related transmission upgrade costs. Alliant Energy and WPL could record an impairment of these costs if WPL does not qualify for reimbursement under ITC’s Attachment “FF” tariff and if WPL is not able to recover these costs from its electric customers. As of June 30, 2013, Alliant Energy and WPL recorded $14 million in “Deferred charges and other” on their Condensed Consolidated Balance Sheets related to the project constructed by ITC. Refer to “Other Future Considerations - Electric Transmission Service Charges” for further discussion of ITC’s Attachment “FF” tariff.
Unbilled Revenues - Alliant Energy, IPL and WPL make assumptions and judgments each reporting period to estimate their amount of unbilled revenues. At June 30, 2013, unbilled revenues related to Alliant Energy’s utility operations were $147 million ($78 million at IPL and $69 million at WPL). Note 3(a) of the “Combined Notes to Condensed Consolidated Financial Statements” provides discussion of IPL’s unbilled revenues as of June 30, 2013 sold to a third-party financial institution related to its sales of accounts receivable program.
Pensions and Other Postretirement Benefits - Alliant Energy, IPL and WPL make assumptions and judgments periodically to estimate the obligations and costs related to their retirement plans. Note 5(a) of the “Combined Notes to Condensed Consolidated Financial Statements” provides additional details of pension and other postretirement benefits plans. Note 12
(c) of the “Combined Notes to Condensed Consolidated Financial Statements” provides recent developments of the class-action lawsuit filed against the Cash Balance Plan in 2008.
Income Taxes - Alliant Energy, IPL and WPL make assumptions and judgments each reporting period to estimate their income tax assets, liabilities, benefits and expenses. Alliant Energy’s, IPL’s and WPL’s critical assumptions and judgments for the second quarter of 2013 include projections of future taxable income used to determine their ability to utilize net operating losses and credit carryforwards prior to their expiration and the states in which such future taxable income will be apportioned. Alliant Energy’s and IPL’s critical assumptions and judgments also include projections of qualifying repairs expenditures and allocation of mixed service costs due to the impact of Iowa rate-making principles on such property-related differences. Note 4 of the “Combined Notes to Condensed Consolidated Financial Statements” provides additional details of income taxes.
Other Future Considerations - In addition to items discussed earlier in MDA, the “Combined Notes to Consolidated Financial Statements” in Item 1 and “Risk Factors” in Item 1A, the following items could impact Alliant Energy’s, IPL’s or WPL’s future financial condition or results of operations:
Electric Transmission Service Charges - IPL and WPL currently receive substantially all their transmission services from ITC and ATC, respectively. The annual transmission service rates that ITC or ATC charges their customers are calculated each calendar year using a FERC-approved cost of service formula rate template referred to as Attachment “O.” Because Attachment “O” is a FERC-approved formula rate, ITC and ATC can implement new rates each calendar year without filing a request with FERC. However, new rates are subject to challenge by FERC if the rates proposed by ITC or ATC are determined by FERC to be unjust or unreasonable or another mechanism is determined by FERC to be just and reasonable. In 2012, IPL filed comments related to ITC’s Attachment “O” protocols. In May 2013, FERC issued an order that determined the Attachment “O” protocols to be insufficient. FERC ordered MISO and the impacted transmission owners, including ITC and ATC, to make certain changes to their protocols. A compliance filing is due to FERC in September 2013. Alliant Energy, IPL and WPL are currently unable to determine what impacts the changes in protocols will have on their future electric transmission service charges.
ITC’s Attachment “FF” Tariff - In September 2012, IPL filed a complaint with FERC regarding ITC’s Attachment “FF” tariff. In the complaint, IPL alleged that its customers have made payments of $32 million in incremental costs for the period 2008 through 2011 under ITC’s Attachment “FF” tariff as compared to costs that would have been charged under the version of the Attachment “FF” tariff applicable in the majority of the MISO pricing zones (MISO Attachment “FF” tariff) without obtaining equal benefits. The complaint filed with FERC also included estimates that IPL’s customers could make aggregate payments of $138 million in incremental costs for the period 2012 through 2016 under ITC’s existing Attachment “FF” tariff as compared to the costs that would be charged under the MISO Attachment “FF” tariff. IPL requested that FERC investigate ITC’s Attachment “FF” tariff, establish a refund date of September 14, 2012 with respect to the complaint, and establish hearing procedures. IPL also requested that if FERC determines that ITC’s Attachment “FF” tariff is unjust and unreasonable then it should require ITC to file revisions to conform its Attachment “FF” tariff to the MISO Attachment “FF” tariff, which is applicable in the majority of the other pricing zones. In October 2012, ITC filed a response to IPL’s complaint. In July 2013, FERC issued an order requiring MISO, on behalf of ITC, to revise ITC’s Attachment “FF” tariff to conform to the MISO Attachment “FF” tariff. Alliant Energy and IPL are currently uncertain whether the FERC order will be appealed. Assuming the FERC order is not appealed, MISO is currently expected to submit a filing in August 2013 that proposes tariff revisions, which are expected to be effective as of the date of the July 2013 order. These tariff revisions ordered by FERC are expected to impact the future amount of electric transmission service costs billed by ITC to IPL. Alliant Energy and IPL currently expect to pass on the Iowa retail portion of any changes in electric transmission service costs billed by ITC to IPL from the revision in ITC’s Attachment “FF” tariff to its electric retail customers in Iowa through the transmission cost recovery rider.
Sales Trends - In January 2012, Eagle Point filed a Petition for Declaratory Order requesting the IUB declare Eagle Point is not a public utility subject to the service territory laws in Iowa. Specifically, Eagle Point sought to sell directly to the City of Dubuque the power generated by a 175 kilowatt solar unit installed on the City’s property. IPL, MidAmerican, the Iowa Association of Electric Cooperatives, a coalition of solar power advocates, and the OCA actively participated in the related IUB proceeding. In April 2012, the IUB issued an order finding that Eagle Point’s proposed arrangement would make it a public utility operating in IPL’s exclusive service territory in violation of Iowa’s service territory laws. In May 2012, Eagle Point requested review of the IUB’s April 2012 order from the Polk County, Iowa District Court (District Court). In March 2013, the District Court issued a ruling that vacated the IUB’s decision, and found Eagle Point did not constitute a public utility and could enter into its proposed direct sales arrangement with the City of Dubuque. In April 2013, IPL and MidAmerican filed a joint Notice of Appeal with the Iowa Supreme Court. The IUB and the Iowa Association of Electric
Cooperatives also filed Notices of Appeal with the Iowa Supreme Court, and Eagle Point submitted a Notice of Cross-Appeal. The District Court decision is currently stayed. Alliant Energy and IPL are unable to determine how this District Court ruling may impact the level of third-party solar development in IPL’s service territory and resulting impact on future demand of electricity by IPL’s customers.
In July 2012, Jo-Carroll filed a complaint in the U.S. District Court for the Northern District of Illinois Western Division against IPL seeking declaratory relief from a wholesale power supply agreement between the parties dated May 1, 2008. Jo-Carroll’s complaint was filed to invoke an early termination provision of the agreement. In April 2013, IPL and Jo-Carroll reached a settlement regarding the litigation and executed an amended agreement, which FERC approved in May 2013. In June 2013, the U.S. District Court for the Northern District of Illinois Western Division dismissed the case, thereby resolving this matter. Key terms of the amended agreement include: (1) the amended agreement will no longer include an early termination rate comparison provision, which under the original agreement allowed Jo-Carroll to terminate such agreement with two year’s prior notice if certain energy price conditions existed; (2) the amended agreement has an initial term through at least April 1, 2018 and provides IPL or Jo-Carroll the right to terminate the amended agreement any time after April 1, 2018 with a four-year prior written notice; and (3) Jo-Carroll can source up to 10 MW of its electricity demand through its own generation. Sales to Jo-Carroll represented 2% of IPL’s total electric sales in 2012.
Market risk
As filed, 148 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Quantitative and Qualitative Disclosures About Market Risk are reported in “Other Matters - Market Risk Sensitive Instruments and Positions” in MDA.
Controls and procedures
As filed, 959 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Alliant Energy’s, IPL’s and WPL’s management evaluated, with the participation of each of Alliant Energy’s, IPL’s and WPL’s Chief Executive Officer (CEO), Chief Financial Officer (CFO) and Disclosure Committee, the effectiveness of the design and operation of Alliant Energy’s, IPL’s and WPL’s disclosure controls and procedures (as defined in Rule 13a-15(e) of the Securities Exchange Act of 1934) as of June 30, 2013 pursuant to the requirements of the Securities Exchange Act of 1934. Based on their evaluation, the CEO and the CFO concluded that Alliant Energy’s, IPL’s and WPL’s disclosure controls and procedures were effective as of June 30, 2013.
There was no change in Alliant Energy’s, IPL’s and WPL’s internal control over financial reporting that occurred during the quarter ended June 30, 2013 that has materially affected, or is reasonably likely to materially affect, Alliant Energy’s, IPL’s or WPL’s internal control over financial reporting.
Risk factors
As filed, 201 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
A summary of Alliant Energy’s, IPL’s and WPL’s risk factors is included in Item 1A in the 2012 Form 10-K and such risk factors have not changed materially from the items reported in the 2012 Form 10-K.
Figures reported in this filing
Standardized line items from the XBRL in this filing, for the period ended 2013-06-30. Comparative periods it repeats are left out.
| Line item | Period | Value | XBRL concept |
|---|---|---|---|
| Revenue | 3 months2013-04-01 to 2013-06-30 | $718.0m | us-gaap:Revenues |
| Revenue | 6 months2013-01-01 to 2013-06-30 | $1.58bn | us-gaap:Revenues |
| Operating income | 3 months2013-04-01 to 2013-06-30 | $103.2m | us-gaap:OperatingIncomeLoss |
| Operating income | 6 months2013-01-01 to 2013-06-30 | $223.9m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months2013-04-01 to 2013-06-30 | $42.5m | us-gaap:InterestExpense |
| Interest expense | 6 months2013-01-01 to 2013-06-30 | $85.1m | us-gaap:InterestExpense |
| Income tax | 3 months2013-04-01 to 2013-06-30 | $10.5m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 6 months2013-01-01 to 2013-06-30 | $22.6m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months2013-04-01 to 2013-06-30 | $67.8m | us-gaap:NetIncomeLoss |
| Net income | 6 months2013-01-01 to 2013-06-30 | $147.9m | us-gaap:NetIncomeLoss |
| Diluted EPS | 6 months2013-01-01 to 2013-06-30 | $1.22 | us-gaap:EarningsPerShareBasicAndDiluted |
| Diluted shares (weighted) | 3 months2013-04-01 to 2013-06-30 | 110,780,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 6 months2013-01-01 to 2013-06-30 | 110,778,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 6 months2013-01-01 to 2013-06-30 | $423.3m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Dividends paid | 6 months2013-01-01 to 2013-06-30 | $104.2m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | At period end2013-06-30 | $11.5m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | At period end2013-06-30 | $893.4m | us-gaap:AssetsCurrent |
| Total assets | At period end2013-06-30 | $10.89bn | us-gaap:Assets |
| Current liabilities | At period end2013-06-30 | $1.07bn | us-gaap:LiabilitiesCurrent |
| Long-term debt | At period end2013-06-30 | $3.14bn | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | At period end2013-06-30 | $1.5m | us-gaap:LongTermDebtCurrent |
| Short-term borrowings | At period end2013-06-30 | $223.1m | us-gaap:CommercialPaper |
| Shareholders' equity | At period end2013-06-30 | $3.16bn | us-gaap:StockholdersEquity |
| Shares outstanding | At period end2013-06-30 | 110,943,669 shares | dei:EntityCommonStockSharesOutstanding |
Source: SEC EDGAR, the filing index for accession 0000352541-13-000020. Last ingested by Listed: Nov 6, 2026, 14:16 ET. Listed shows no prices and gives no investment advice.