Novagold Resources Inc: Form 10-K for the period ended Nov 30, 2013

Filed with the SEC on Feb 12, 2014 and accepted by EDGAR at Feb 12, 2014, 01:38 ET.

Share

Business

As filed, 17,001 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Overview

We operate in the gold mining industry, primarily focused on advancing permitting on the Donlin Gold project in Alaska. The Donlin Gold project is held by Donlin Gold LLC (“Donlin Gold”), a limited liability company owned equally by wholly-owned subsidiaries of NOVAGOLD and Barrick Gold Corporation (“Barrick”). We are also committed to maximizing the value of our interest in the Galore Creek copper-gold-silver project in British Columbia, Canada. The Galore Creek project is held by a partnership owned equally by wholly-owned subsidiaries of NOVAGOLD and Teck Resources Limited (“Teck”). We are currently exploring opportunities to sell, in whole or in part, our interest in the Galore Creek project.

We do not produce gold or any other minerals, and do not currently generate operating earnings. Through 2013, funding to explore our gold properties and to operate the Company was acquired primarily through equity financings consisting of public offerings of our common shares and warrants and through debt financing consisting of convertible notes. We expect to continue to raise capital through additional equity and/or debt financings, through the exercise of stock options, and otherwise.

We were incorporated by memorandum of association on December 5, 1984, under the Companies Act (Nova Scotia) as 1562756 Nova Scotia Limited. On January 14, 1985, we changed our name to NovaCan Mining Resources (l985) Limited and on March 20, 1987, we changed our name to NOVAGOLD RESOURCES INC. On May 29, 2013, our shareholders approved the continuance of the corporation into British Columbia. Subsequently, we filed the necessary documents in Nova Scotia and British Columbia and effective as of June 10, 2013 we continued under the Business Corporations Act (British Columbia). The current addresses, telephone and facsimile numbers of our offices are:

Executive office Registered and records office
201 South Main Street, Suite 400 789 West Pender Street, Suite 720
Salt Lake City, Utah, USA 84111 Vancouver, BC, V6C 1H2
Telephone (801) 639-0511 Facsimile (604) 669-6272
Facsimile (801) 649-0509 Toll free 1(866) 669-6227

13

Corporate Structure

As of November 30, 2013, we had the following material, direct and indirect, wholly-owned subsidiaries: NOVAGOLD Resources Alaska, Inc., NOVAGOLD USA Holdings Inc., NOVAGOLD USA, Inc., NOVAGOLD (Bermuda) Alaska Limited, NOVAGOLD Resources (Bermuda) Limited and NOVAGOLD Canada Inc.

The following chart depicts the corporate structure of the Company together with the jurisdiction of incorporation of each of our material subsidiaries and related holding companies. All ownership is 100% unless otherwise indicated.

Employees

As of November 30, 2013, we had 14 full-time employees. We also use consultants with specific skills to assist with various aspects of project evaluation, engineering and corporate governance.

Segment and Geographical Information

We operate in a single reportable operating segment, being the exploration and development of mineral properties. Our long-lived assets are geographically distributed as shown in the following table. We did not have revenue from continuing operations in any of the periods shown below.

Long-lived assets

($ thousands) At November 30, 2013 2012 2011
Canada $367,712 $407,037 $410,923
United States 4,435 7,451 34,794
Other — 513 500
$372,147 $415,001 $446,217

Recent Developments

Donlin Gold Project

During the year ended November 30, 2013, Donlin Gold continued to advance permitting of the Donlin Gold project. The Donlin Gold Board of Directors approved Donlin Gold project’s Second Updated Feasibility Study (“Donlin Gold FS”) in August 2012 and Donlin Gold subsequently submitted a Plan of Operations and Wetlands Permit Application under Section 404 of the U.S. Clean Water Act to the U.S. Army Corps of Engineers (the “Corps”), formally initiating the permitting process. This permit application triggered the process of preparing an Environmental Impact Statement (EIS) under the National Environmental Policy Act (NEPA). The Corps, which is the lead agency for the NEPA process, selected URS Alaska Inc. (URS), an independent contractor to prepare the EIS.

On December 14, 2012, the Notice of Intent for the EIS was published in the Federal Register by the Corps, which initiated the public scoping process. In the first quarter of 2013, public scoping meetings were held in villages and communities in Western Alaska and Anchorage to help identify the questions and concerns of the villages and communities in the region which will be addressed in the EIS. On March 29, 2013, the public scoping period ended and in May 2013, URS issued a draft scoping summary document for review by the Corps and other entities participating as cooperating agencies in the EIS process (the “Cooperating Agencies”). During the second quarter of 2013, Donlin Gold delivered to the Corps a comprehensive Environmental Evaluation Document (EED) that provides detailed information on the baseline studies and analyses that have been completed for the proposed project. The EED also describes the detailed project options that Donlin Gold considered in the development of the proposed project design. The EED is being used by URS and the Cooperating Agencies to support ongoing alternatives development for the EIS. In March 2013, URS issued a preliminary review of the available baseline data identifying additional environmental, social, and cultural resource data that must be compiled for the EIS. During the remainder of 2013, Donlin Gold worked to address the remaining data needs for the EIS. Throughout 2013, Donlin Gold also continued to provide application materials and maintained ongoing dialogue with the agencies that will issue the key permits and authorizations needed for the Donlin Gold project, including the air quality, water discharge, dam safety, wetlands, water use, fish habitat, and pipeline permits. Donlin Gold completed all required field work as planned.

The Corps and URS are working towards planned issuance of the Preliminary Draft Environmental Impact Statement (PDEIS) for Cooperating Agency review in late 2014 issuance of the draft EIS for public comment in 2015, and issuance of the final EIS and associated record of decision in 2016. A schedule of the Corps’ time table for the EIS process at the Donlin Gold project can be found on their website at www.donlingoldeis.com (http://www.donlingoldeis.com).

An extensive list of additional federal and state government permits and approvals must be obtained before the Donlin Gold project can commence construction. Preparation of the applications for many of these permits and approvals requires additional, more detailed engineering that were not part of the Donlin Gold FS. Completion of this engineering will require a significant investment of funds, time, and other resources by Donlin Gold and its contractors. Also, the Donlin Gold board must approve a construction program and budget before construction of the Donlin Gold project can begin. The timing of the required engineering work, of the Donlin Gold board’s approval of a construction program and budget, as well as the receipt of all required governmental permits and approvals will determine whether and when construction of the Donlin Gold project will begin. Project delays also could occur as a result of public opposition, limitations in regulatory staff resources during regulatory review, or project changes made by Donlin Gold.

Our share of funding for Donlin Gold in 2013 was $12.2 million for permitting, community engagement and development efforts. Donlin Gold has approved a 2014 work program of approximately $24 million, of which our 50% share is approximately $12 million. The 2014 work program and budget includes funds to advance the permitting process through completion of the PDEIS in late 2014, and receipt of comments from the Federal and State agencies on the PDEIS in preparation for issuance of the draft EIS in 2015. In addition, Donlin Gold will continue to maintain its engagement with communities in the Yukon-Kuskokwim region.

For further information, see section Item 2, Properties – Donlin Gold Project, below.

Galore Creek Project

On February 25, 2013, we announced the results of a 27,873-meter resource in-fill and geotechnical drilling program conducted during 2012 at Galore Creek. The 2012 in-fill drilling campaign confirmed previously reported drill results and demonstrated the potential for a substantial extension of the mineralized area beyond the limits of the current Pre-Feasibility Study (PFS) pit. Additionally, Galore Creek Mining Corporation (GCMC) made a new discovery called the Legacy zone, a 700-meter long mineralized zone, as defined by the 2012 drill program, located adjacent to the Central Pit.

An 11,600 meter drilling program was completed by GCMC in the third quarter of 2013 to further define the extent of the Legacy zone mineralization. The 2013 in-fill drill program confirmed significant mineralization at the Legacy zone and provided sufficient data to proceed with additional technical studies in support of mine planning. Our share of funding for Galore Creek in 2013 was $6.6 million, which primarily funded exploration drilling, administrative expenses, environmental monitoring, and site care and maintenance costs. GCMC has approved a 2014 work program and budget of approximately $5 million, of which our 50% share is approximately $2.5 million. The 2014 work program and budget includes funds to advance the project toward next-level mine planning and design based on the data generated by the 2012 and 2013 drilling programs.

Based on the results of the 2014 work program, NOVAGOLD and Teck will evaluate the opportunities to further advance development of the Galore Creek project, including the potential timeline for completing a full feasibility study for the project. In the meantime, we will continue to evaluate opportunities to monetize the value of the asset.

For further information, see Item 2, Properties – Galore Creek Project, below.

Other Developments

On December 31, 2012, Electrum Strategic Resources L.P. (“Electrum”) exercised its remaining 31,337,278 common share purchase warrants at C$1.479 per share for proceeds of C$46.4 million. As a result of the exercise of these warrants, Electrum and GRAT Holdings LLC, an Electrum affiliate, now hold 84,569,479 common shares, representing approximately 27.2% of our outstanding common shares. In January 2013, all remaining 5,192,308 common share purchase warrants outstanding were exercised at $1.50 per share for proceeds of $7.8 million.

On May 2, 2013, we purchased $72.8 million of the principal amount of our $95.0 million outstanding 5.5% convertible notes due May 1, 2015 (the “Notes”) pursuant to the terms of the indenture governing the Notes, which provided holders of the Notes the opportunity to require us to purchase for cash all or a portion of their Notes on May 1, 2013. In September 2013, we accepted the offer from a number of holders of the Notes to repurchase an additional $6.4 million of the Notes. Following our purchase of the Notes, $15.8 million principal amount of the Notes remain outstanding and due on May 1, 2015. As a result of our purchases of the Notes, our interest payments for the remaining term of the Notes decreased from $7.4 million to $1.2 million. The terms and other provisions of the indenture governing the Notes remain unchanged.

For further information, see Item 7, Management’s Discussion and Analysis of Financial Condition and Results of Operations – Financial Position, Liquidity and Capital Resources, below.

Reclamation

We will generally be required to mitigate long-term environmental impacts by stabilizing, contouring, re-sloping and re-vegetating various portions of a site after mining and mineral processing operations are completed. These reclamation efforts will be conducted in accordance with detailed plans, which must be reviewed and approved by the appropriate regulatory agencies. In addition, financial assurance acceptable to the regulatory authority with jurisdiction over reclamation must be provided in an amount that the authority determines to be sufficient to allow the authority to implement the reclamation plan in the event that we fail to complete the work as provided in the plan.

Government and Environmental Regulations

Our exploration and development activities are subject to various national, state, provincial and local laws and regulations in the United States and Canada, which govern prospecting, development, mining, production, exports, taxes, labor standards, occupational health, waste disposal, protection of the environment, mine safety, hazardous substances and other matters. We have obtained or have pending applications for those licenses, permits or other authorizations currently required to conduct our exploration and development programs. We believe that we are in compliance in all material respects with applicable mining, health, safety and environmental statutes and regulations in the United States and Canada. There are no current orders or directions relating to us with respect to the foregoing laws and regulations. For a more detailed discussion of the various government laws and regulations applicable to our operations and potential negative effects of these laws and regulations, see Item 1A, Risk Factors, below.

Competition

We compete with other mineral resource exploration and development companies for financing, technical expertise and the acquisition of mineral properties. Many of the companies with whom we compete have greater financial and technical resources. Accordingly, these competitors may be able to spend greater amounts on the acquisition, exploration and development of mineral properties. This competition could adversely impact our ability to finance further exploration and to obtain the financing necessary for us to develop our mineral properties.

Availability of Raw Materials and Skilled Employees

Most aspects of our business require specialized skills and knowledge. Such skills and knowledge include the areas of geology, drilling, metallurgy, mine planning, logistical planning, preparation of feasibility studies, permitting, construction and operation of a mine, financing and accounting. Historically, we have found that we can locate and retain appropriate employees and consultants and we believe we will continue to be able to do so.

All of the raw materials we require to carry on our business are readily available through normal supply or business contracting channels in the United States and Canada. Historically, we have been able to secure the appropriate equipment and supplies required to conduct our contemplated programs. As a result, we do not believe that we will experience any shortages of required equipment or supplies in the foreseeable future.

Seasonality

Our business is seasonal as mineral exploration and development activities take place in southwestern Alaska and northern British Columbia. Due to the northern climate, work on the Donlin Gold and Galore Creek projects can be limited due to excessive snow cover and cold temperatures. In general, surface work often is limited to late spring through early fall, although work in some locations, which may more efficiently be accessed while frozen, occurs in the winter.

Gold Price History

The price of gold is volatile and is affected by numerous factors all of which are beyond our control, such as the sale or purchase of gold by various central banks and financial institutions, inflation, recession, fluctuation in the relative values of the U.S. dollar and foreign currencies, changes in global and regional gold demand in addition to international and national political and economic conditions.

The following table presents the high, low and average afternoon fixed prices in U.S. dollars for an ounce of gold on the London Bullion Market over the past five calendar years:

Year High Low Average
2009 $1,213 $810 $972
2010 $1,421 $1,058 $1,225
2011 $1,895 $1,319 $1,571
2012 $1,792 $1,540 $1,669
2013 $1,694 $1,192 $1,411
2014 (to January 31) $1,267 $1,221 $1,245

Data Source: www.kitco.com (http://www.kitco.com)

Available Information

We make available, free of charge, on or through our website, at www.novagold.com (http://www.novagold.com) our Annual Report on Form 10-K, our quarterly reports on Form 10-Q and our current reports on Form 8-K and amendments to those reports filed or furnished pursuant to Section 13(a) or 15(d) of the U.S. Securities Exchange Act of 1934. Our website and the information contained therein or connected thereto are not intended to be, and are not incorporated into this Annual Report on Form 10-K.

Risk factors

As filed, 70,637 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

You should carefully consider the following risk factors in addition to the other information included in this Annual Report on Form 10-K. Each of these risk factors could adversely affect our business, operating results and financial condition, as well as adversely affect the value of an investment in our common shares. The risks described below are not the only ones facing the Company. Additional risks that we are not presently aware of, or that we currently believe are immaterial, may also adversely affect our business, operating results and financial condition. We cannot assure you that we will successfully address these risks or that other unknown risks exist or may arise that may affect our business.

An investment in our securities is speculative and involves a high degree of risk due to the nature of our business and the present stage of exploration and development of our mineral properties. The following risk factors, as well as risks not currently known to us, could materially adversely affect our future business, operations and financial condition and could cause them to differ materially from the estimates described in the forward-looking statements relating to us.

Risks Related to Our Business

We have no history of commercially producing precious or base metals from our mineral exploration properties and there can be no assurance that we will successfully establish mining operations or profitably produce precious or base metals.

None of our mineral properties are in production, we have no history of commercially producing precious or base metals from our current portfolio of mineral properties, and we have no ongoing mining operations or revenue from mining operations. Mineral exploration and development involves a high degree of risk and few properties that are explored are ultimately developed into producing mines. None of our mineral properties are currently under construction. The future development of any mineral properties found to be economically feasible will require obtaining permits and financing and the construction and operation of mines, processing plants and related infrastructure. As a result, we are subject to all of the risks associated with establishing new mining operations and business enterprises, including:

  • the timing and cost, which can be considerable, of the construction of mining and processing facilities and related infrastructure;
  • the availability and cost of skilled labor and mining equipment;
  • the availability and cost of appropriate smelting and/or refining arrangements;
  • the need to obtain necessary environmental and other governmental approvals and permits, and the timing and conditions of those approvals and permits;
  • the availability and cost of funds to finance construction and development activities;
  • potential opposition from non-governmental organizations, environmental groups or local groups which may delay or prevent development activities; and
  • potential increases in construction and operating costs due to changes in the cost of labor, fuel, power, materials and supplies, services, and foreign exchange rates.

The costs, timing and complexities of mine construction and development are increased by the remote location of our mineral properties, with additional challenges related thereto, including access, water and power supply, and other support infrastructure. Cost estimates may increase significantly as more detailed engineering work and studies are completed on a project. New mining operations commonly experience unexpected costs, problems and delays during development, construction, and mine start-up. In addition, delays in the commencement of mineral production often occur. Accordingly, there are no assurances that our activities will result in profitable mining operations, or that we will successfully establish mining operations, or profitably produce precious or base metals at any of our mineral properties.

In addition, there is no assurance that our mineral exploration activities will result in any discoveries of new bodies of ore. If further mineralization is discovered there is also no assurance that the mineralized material would be economical for commercial production. Discovery of mineral deposits is dependent upon a number of factors and significantly influenced by the technical skill of the exploration personnel involved. The commercial viability of a mineral deposit is also dependent upon a number of factors which are beyond our control, including the attributes of the deposit, commodity prices, government policies and regulation, and environmental protection requirements.

We have a history of net losses and expect losses to continue for the foreseeable future.

We have a history of net losses and, although we achieved a net profit of $64.8 million for the fiscal year ended November 30, 2011, primarily as a result of our deconsolidation of the Galore Creek Partnership, we expect to incur net losses for the foreseeable future. As of November 30, 2013, our historical net losses totaled approximately $1.6 billion. None of our mineral properties have advanced to the commercial production stage and we have no history of earnings or cash flow from operations. We expect to continue to incur net losses unless and until such time as one or more of our projects enters into commercial production and generate sufficient revenues to fund continuing operations or until such time as we are able to offset our expenses against the sale of one or more of our mineral properties, if applicable. The development of our mineral properties to achieve production will require the commitment of substantial financial resources. The amount and timing of expenditures will depend on a number of factors, including the progress of ongoing exploration and development, the results of consultants’ analyses and recommendations, the rate at which operating losses are incurred, the process of obtaining required government permits and approvals, the availability and cost of financing, the participation of our partners, and the execution of any sale or joint venture agreements with strategic partners. These factors, and others, are beyond our control. There is no assurance that we will be profitable in the future.

Our ability to continue the exploration, permitting, development, and construction of the Donlin Gold and Galore Creek projects, and to continue as a going concern, will depend in part on our ability to obtain suitable financing.

We have limited financial resources. We will need external financing to develop and construct the Donlin Gold project and, if applicable, the Galore Creek project. On December 5, 2011, we announced the total capital cost estimate for the Donlin Gold project was approximately $6.7 billion including costs related to the natural gas pipeline (100% basis). Our failure to obtain sufficient financing could result in the delay or indefinite postponement of exploration, development, construction, or production at the Donlin Gold project or any or all of our other mineral properties. The cost and terms of such financing may significantly reduce the expected benefits from new developments and/or render such developments uneconomic. There can be no assurance that additional capital or other types of financing will be available when needed or that, if available, the terms of such financing will be favorable. Our failure to obtain financing could have a material adverse effect on our growth strategy and results of operations and financial condition. In addition, we may have to sell one or more of our mineral properties.

We intend to fund our plan of operations from working capital, the proceeds of financings, and the potential sale of our interest in the Galore Creek project. In the future, our ability to continue our exploration, permitting, development, and construction activities, if any, will depend in part on our ability to obtain suitable financing. If we raise additional funding by issuing additional equity securities or other securities that are convertible into equity securities, such financings may substantially dilute the interest of existing or future shareholders. Sales or issuances of a substantial number of securities, or the perception that such sales could occur, may adversely affect the prevailing market price for our common shares. With any additional sale or issuance of equity securities, investors will suffer dilution of their voting power and may experience dilution in our earnings per share.

There can be no assurance that we will commence production at any of our mineral properties or generate sufficient revenues to meet our obligations as they become due or obtain necessary financing on acceptable terms, if at all. Our failure to meet our ongoing obligations on a timely basis could result in the loss or substantial dilution of our interests (as existing or as proposed to be acquired) in our mineral properties. In addition, should we incur significant losses in future periods, we may be unable to continue as a going concern, and realization of assets and settlement of liabilities in other than the normal course of business may be at amounts materially different than our estimates.

Actual capital costs, operating costs, production and economic returns may differ significantly from those we have anticipated and there are no assurances that any future development activities will result in profitable mining operations.

The capital costs to take our projects into production may be significantly higher than anticipated. Escalation of costs was a significant factor in the decision to suspend construction at the Galore Creek project in 2007. On December 5, 2011, we announced the total capital cost estimate for the Donlin Gold project of approximately $6.7 billion including costs related to the natural gas pipeline (100% basis). The previous capital cost estimate for the project released in April 2009 was $4.5 billion which did not include the cost of a natural gas pipeline.

None of our mineral properties have an operating history upon which we can base estimates of future operating costs. Decisions about the development of these and other mineral properties will ultimately be based upon feasibility studies. Feasibility studies derive estimates of cash operating costs based upon, among other things:

  • anticipated tonnage, grades and metallurgical characteristics of the ore to be mined and processed;
  • anticipated recovery rates of gold, copper and other metals from the ore;
  • cash operating costs of comparable facilities and equipment; and
  • anticipated climatic conditions.

Capital costs, operating costs, production and economic returns, and other estimates contained in studies or estimates prepared by or for us may differ significantly from those anticipated by our current studies and estimates, and there can be no assurance that our actual operating costs will not be higher than currently anticipated.

Changes in the market price of gold, copper and other metals, which in the past have fluctuated widely, affect our financial condition.

Our profitability and long-term viability depend, in large part, upon the market price of gold, copper and other metals and minerals produced from our mineral properties. The market price of gold and other metals is volatile and is impacted by numerous factors beyond our control, including:

  • global or regional consumption patterns;
  • expectations with respect to the rate of inflation;
  • the relative strength of the U.S. dollar and certain other currencies;
  • interest rates;
  • global or regional political or economic conditions, including interest rates and currency values;
  • supply and demand for jewelry and industrial products containing metals; and
  • sales by central banks and other holders, speculators and producers of metals in response to any of the above factors.

We cannot predict the effect of these factors on metal prices. A decrease in the market price of gold, copper and other metals could affect our ability to finance the development of the Donlin Gold and Galore Creek projects, and the exploration and development of other mineral properties held by us, which would have a material adverse effect on our financial condition and results of operations. There can be no assurance that the market price of gold, copper and other metals will remain at current levels or that such prices will improve. In particular, an increase in worldwide supply, and consequent downward pressure on prices, may result over the longer term from increased production from the development of new or expansion of existing mines. There is no assurance that if commercial quantities of gold, copper and other metals are discovered, that a profitable market may exist or continue to exist for a production decision to be made or for the ultimate sale of the metals.

General economic conditions may adversely affect our growth, future profitability and ability to finance.

The unprecedented events in global financial markets in the past several years have had a profound impact on the global economy. Many industries, including the mining industry, are impacted by these market conditions. Some of the key impacts of the recent financial market turmoil include contraction in credit markets resulting in a widening of credit risk, devaluations, high volatility in global equity, commodity, foreign exchange and precious metal markets and a lack of market liquidity. During 2013, the price of gold declined by 28%, the largest annual decline since 1981, ending a 12-year period of annual price increases. The price of gold mining company equities also experienced significant declines.

Continued lower or a worsening of gold prices or slowdown in the financial markets or other economic conditions, including but not limited to, consumer spending, employment rates, business conditions, inflation, fuel and energy costs, consumer debt levels, lack of available credit, the state of the financial markets, interest rates and tax rates, may adversely affect our growth and ability to finance. Specifically:

  • the global economic recovery could make other investment sectors more attractive, thereby affecting the cost and availability of financing to us and our ability to achieve our business plan;
  • the volatility of metal prices would impact the economic viability of our mineral properties and any future revenues, profits, losses and cash flow;
  • negative economic pressures could adversely impact demand for future production from our mineral properties;
  • construction related costs could increase and adversely affect the economics of any of our projects;
  • volatile energy, commodity and consumables prices and currency exchange rates would impact our future production costs; and
  • the devaluation and volatility of global stock markets would impact the valuation of our equity and other securities.

We have a limited property portfolio

At present, our only material mineral properties are the interests that we hold in the Donlin Gold and Galore Creek projects. Unless we acquire or develop additional mineral properties, we will be solely dependent upon these properties. If no additional mineral properties are acquired by us, any adverse development affecting our operations and further development at either or both of the Donlin Gold and Galore Creek projects may have a material adverse effect on our financial condition and results of operations.

We are dependent on third parties that participate in or are responsible for exploration and development of our properties.

Our success depends on the efforts and expertise of third parties with whom we have contracted. With respect to each of the Donlin Gold and Galore Creek projects, we hold a 50% interest and the remaining 50% interest is held by a third party that is not under our control or direction. We are dependent on such third parties for accurate information relating to our mineral properties and related assets and the progress and development of such properties and assets. Third parties may also have different priorities which could impact the timing and cost of development of either or both of the Donlin Gold and Galore Creek projects. A third party may also be in default of its agreement with us, without our knowledge, which may put the mineral property and related assets at risk. The existence or occurrence of one or more of the following circumstances and events could have a material adverse impact on our ability to achieve our business plan, profitability, or the viability of our interests held with third parties, which could have a material adverse impact on our business, future cash flows, earnings, results of operations and financial condition: (i) disagreement with our business partners on how to develop and operate the mineral properties efficiently; (ii) inability to exert influence over certain strategic decisions made in respect of jointly held mineral properties; (iii) inability of our business partners to meet their obligations to the joint business or third parties; and (iv) litigation with our business partners regarding joint business matters.

We require various permits to conduct our current and anticipated future operations, and delays or a failure to obtain such permits, or a failure to comply with the terms of any such permits that we have obtained, could have a material adverse impact on us.

Our current and anticipated future operations, including further exploration and development activities and commencement of production on our mineral properties, require permits from various United States and Canadian federal, state, provincial, territorial and local governmental authorities. There can be no assurance that all permits that we require for the construction of mining facilities and to conduct mining operations will be obtainable on reasonable terms, or at all. Delays or a failure to obtain such permits, or a failure to comply with the terms of any such permits that we have obtained, could have a material adverse impact on us.

The duration and success of efforts to obtain and renew permits are contingent upon many variables not within our control. Shortage of qualified and experienced personnel in the various levels of government could result in delays or inefficiencies. Backlog within the permitting agencies could affect the permitting timeline of the various projects. Other factors that could affect the permitting timeline include (i) the number of other large-scale projects currently in a more advanced stage of development which could slow down the review process and (ii) significant public response regarding a specific project. As well, it can be difficult to assess what specific permitting requirements will ultimately apply to each of the projects.

The figures for our mineral resources and mineral reserves are estimates based on interpretation and assumptions and may yield less mineral production under actual conditions than is currently estimated.

Unless otherwise indicated, mineralization figures presented in this Annual Report on Form 10-K and in our other filings with securities regulatory authorities, press releases and other public statements that may be made from time to time are based upon estimates made by our personnel and independent geologists. These estimates use mining terms as defined in accordance with Canadian NI 43-101 and CIM Definition Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended. These definitions differ from the definitions in the SEC Industry Guide 7. For further information, see Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above. In addition, these estimates are imprecise and depend upon geologic interpretation and statistical inferences drawn from drilling and sampling analysis, which may prove to be unreliable. There can be no assurance that:

  • these estimates will be accurate;
  • mineral reserve, mineral resource or other mineralization figures will be accurate; or
  • this mineralization could be mined or processed profitably.

Because we have not commenced commercial production at any of our mineral properties, mineralization estimates for our properties may require adjustments or downward revisions based upon further exploration or development work, actual production experience, or changes in the price of gold, copper or other metals. In addition, the grade of ore ultimately mined, if any, may differ from that indicated by drilling results. There can be no assurance that percentage of minerals recovered in small-scale tests will be duplicated in large-scale tests under on-site conditions or at production scale.

The SEC does not permit mining companies in their filings with the SEC to disclose estimates other than mineral reserves. However, because we are a Canadian company, we also prepare and file reports in accordance with Canadian disclosure requirements. These disclosures contain resource estimates, which are required by Canada’s NI 43-101.

Mineral resource estimates for mineral properties that have not commenced production are based, in many instances, on limited and widely spaced drill hole information, which is not necessarily indicative of the conditions between and around drill holes. Accordingly, such mineral resource estimates may require revision as more drilling information becomes available or as actual production experience is gained. No assurance can be given that any part or all of our mineral resources constitute or will be converted into reserves.

The estimating of mineral reserves and mineral resources is a subjective process that relies on the judgment of the persons preparing the estimates. The process relies on the quantity and quality of available data and is based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. By their nature, mineral resource and reserve estimates are imprecise and depend, to a certain extent, upon analysis of drilling results and statistical inferences that may ultimately prove to be inaccurate. There can be no assurances that actual results will meet the estimates contained in studies.

Estimated mineral reserves or mineral resources may have to be recalculated based on changes in metal prices, further exploration or development activity, or actual production experience. In addition, if production costs increase, recovery rates decrease, if applicable laws and regulations are adversely changed, there is no assurance that the anticipated level of recovery will be realized or that mineral reserves or mineral resources as currently reported can be mined or processed profitably. This could materially and adversely affect estimates of the volume or grade of mineralization, estimated recovery rates or other important factors that influence mineral reserve or mineral resource estimates. The extent to which mineral resources may ultimately be reclassified as mineral reserves is dependent upon the demonstration of their profitable recovery. Any material changes in mineral resource estimates and grades of mineralization will affect the economic viability of placing a mineral property into production and a mineral property’s return on capital. We cannot provide assurance that mineralization identified at our mineral properties can or will be mined or processed profitably.

The resource and reserve estimates contained in this Annual Report on Form 10-K have been determined and valued based on assumed future prices, cut-off grades and operating costs that may prove to be inaccurate. Extended declines in market prices for gold, silver and copper may render portions of our mineralization uneconomic and result in reduced reported mineralization. Any material reductions in estimates of mineralization, or of our ability to extract this mineralization, could have a material adverse effect on our ability to implement our growth strategy, the results of operations or our financial condition.

We have established the presence of proven and probable reserves at our Donlin Gold and Galore Creek projects. There can be no assurance that any resource estimates for our mineral projects will ultimately be reclassified as mineral reserves. There can be no assurance that subsequent testing or future studies will establish proven and probable mineral reserves at our other mineral properties, if any. The failure to establish proven and probable mineral reserves could restrict our ability to successfully implement our strategies for long-term growth and could impact future cash flows, earnings, results of operation and financial condition.

Significant uncertainty exists related to inferred mineral resources.

There is a risk that inferred mineral resources referred to in this Annual Report on Form 10-K cannot be converted into measured or indicated mineral resources. Due to the uncertainty relating to inferred mineral resources, there is no assurance that inferred mineral resources will be upgraded to resources with sufficient geological and grade continuity to constitute measured and indicated resources as a result of continued exploration.

The proposed sale of Galore Creek may not occur.

Part of our current business strategy is to sell our 50% interest in the Galore Creek Partnership. Our management expects to continue to evaluate disposition opportunities on a regular basis and intends to pursue opportunities that management believes are in our long-term best interests. Competition in the mining business for limited sources of capital could adversely impact our ability to dispose of our interest in the Galore Creek Partnership and as a result we may not be successful in identifying a purchaser or in obtaining an offer at an acceptable price and on acceptable terms and conditions. As a result, there is no assurance that we will be able to dispose of our interest in the Galore Creek Partnership; in which case we expect to continue with the joint development of the Galore Creek project through the Galore Creek Partnership, which would result in increased capital requirements for us to fund our portion of project development.

Lack of infrastructure could delay or prevent us from developing advanced projects.

Completion of the development of the Donlin Gold and Galore Creek projects is subject to various requirements, including the availability and timing of acceptable arrangements for power, water, transportation, access and facilities. The lack of availability on acceptable terms or the delay in the availability of any one or more of these items could prevent or delay development of these projects. There can be no assurance that adequate infrastructure, including access and power supply, will be built, that it will be built in a timely manner or that the cost of such infrastructure will be reasonable or that it will be sufficient to satisfy the requirements of the projects. If adequate infrastructure is not available in a timely manner, there can be no assurance that:

  • the development of our mineral properties will be commenced or completed on a timely basis, if at all;
  • the resulting operations will achieve the anticipated production volume; or
  • the construction costs and ongoing operating costs associated with the development of our mineral properties will not be higher than anticipated.

Access to the Donlin Gold and Galore Creek projects is limited and there is no infrastructure in the respective areas. At the Donlin Gold project, an approximately 500-kilometer long natural gas pipeline is needed to supply fuel to the generating plant proposed to provide power for the project. The proposed pipeline would traverse generally undeveloped areas in Alaska that are difficult to access. Terrain, geologic conditions, ground conditions, steep slopes, weather, and other natural conditions that are beyond our control, along the pipeline route present design, permitting, construction, and operational challenges for the project. Cost and schedule estimates may increase significantly as more detailed engineering work, geotechnical and geological studies are completed.

Title and other rights to our mineral properties are subject to agreements with other parties.

The subsurface mineral and surface rights at the Donlin Gold project are owned by Calista Corporation and The Kuskokwim Corporation, respectively, two Native Alaska corporations. Donlin Gold operates on these lands pursuant to a Mining Lease with Calista Corporation and a Surface Use Agreement with The Kuskokwim Corporation. The ability of Donlin Gold to continue to explore and develop the Donlin Gold project depends upon its continued compliance with the terms and conditions of the Mining Lease and Surface Use Agreement. Furthermore, our ability to continue to explore and develop other mineral properties may be subject to agreements with other third parties, including agreements with native corporations and first nations, for instance.

Mining is inherently dangerous and subject to conditions or events beyond our control, which could have a material adverse effect on our business.

Mining involves various types of risks and hazards, including:

  • environmental hazards;
  • industrial accidents;
  • metallurgical and other processing problems;
  • unusual or unexpected geologic formations and conditions;
  • structural cave-ins or slides;
  • flooding;
  • fires;
  • power outages;
  • labor disruptions;
  • explosions;
  • landslides and avalanches;
  • mechanical equipment and facility performance problems;
  • availability of materials and equipment;
  • metals losses; and
  • periodic interruptions due to inclement or hazardous weather conditions.

These risks could result in damage to, or destruction of, mineral properties, production facilities or other properties; personal injury or death, including to employees; environmental damage; delays in construction or mining operations; increased production costs; asset write downs; monetary losses; and possible legal liability. We may not be able to obtain insurance to cover these risks at economically feasible premiums or at all. Insurance against certain environmental risks, including potential liability for pollution or other hazards as a result of the disposal of waste products occurring from mineral production, is not generally available to us or to other companies within the mining industry. We may suffer a material adverse impact on our business if we incur losses related to any significant events that are not covered by our insurance policies.

Exploration, construction and production activities may be limited or delayed by inclement weather and shortened exploration, construction, development and operating seasons. For example, Donlin Gold proposes to transport the bulk of the supplies required to operate the Donlin Gold project to the site from ports in the United States and Canada. This would require the supplies to be transported by barge on the Kuskokwim River which is free of ice and open for barge traffic for a limited period each year. Delays in the ice breakup or early freeze-up, low flow levels and water depths, or other conditions affecting the Kuskokwim River could delay or prevent Donlin Gold from transporting supplies to the site. Any such interference with the delivery of needed supplies to the Donlin Gold project could adversely affect the construction or operation of the project or the cost of constructing or operating the project which, in turn, would adversely affect our business.

We are subject to significant governmental regulation.

Our operations and exploration and development activities in Canada and the United States are subject to extensive federal, state, provincial, territorial and local laws and regulations governing various matters, including:

  • environmental protection;
  • management and use of toxic substances and explosives;
  • management of tailings and other wastes generated by our operations;
  • management of natural resources;
  • exploration and development of mines, production and post-closure reclamation;
  • exports;
  • price controls;
  • taxation and mining royalties;
  • regulations concerning business dealings with native groups;
  • availability and use of water resources;
  • labor standards and occupational health and safety, including mine safety; and
  • preservation of historic and cultural resources.

Failure to comply with applicable laws and regulations may result in civil or criminal fines or penalties or enforcement actions, including orders issued by regulatory or judicial authorities enjoining, curtailing or closing operations or requiring corrective measures, installation of additional equipment or remedial actions, any of which could result in us incurring significant expenditures. We may also be required to compensate private parties suffering loss or damage by reason of a breach of such laws, regulations or permitting requirements. It is also possible that future laws and regulations, or a more stringent enforcement of current laws and regulations by governmental authorities, could cause additional expense, capital expenditures, restrictions on or suspensions of our operations and delays in the exploration and development of our mineral properties.

Our activities are subject to environmental laws and regulations that may increase our costs of doing business and restrict our operations.

All of our exploration, potential development and production activities in Canada and the United States are subject to regulation by governmental agencies under various environmental laws. To the extent that we conduct exploration activities or undertake new mining activities in other foreign countries, we will also be subject to environmental laws and regulations in those jurisdictions. These laws address emissions into the air, discharges into water, management of waste, management of hazardous substances, use of water, protection of natural resources, antiquities and endangered species, and reclamation of lands disturbed by mining operations. Environmental legislation continues to evolve and the trend has been toward stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of proposed projects and increasing responsibility for companies and their officers, directors and employees. Compliance with environmental laws and regulations may require significant capital outlays on our behalf and may cause material changes or delays in our intended activities. There can be no assurance that future changes in environmental regulations will not adversely affect our business, and it is possible that future changes in these laws or regulations could have a significant adverse impact on some portion of our business, causing us to re-evaluate those activities at that time.

Environmental hazards may exist on our mineral properties that are unknown to us at the present time, and that have been caused by previous owners or operators or that may have occurred naturally. We may be liable for remediating such damage.

Failure to comply with applicable environmental laws, regulations and permitting requirements may result in enforcement actions thereunder, including orders issued by regulatory or judicial authorities, causing operations to cease or to be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment or remedial actions.

Our majority shareholder has significant influence on us and may also affect the market price and liquidity of our Securities.

Electrum Strategic Resources L.P. and its affiliate GRAT Holdings LLC hold in the aggregate 27.2% of our issued and outstanding common shares. On December 31, 2013 Electrum exercised the entirety of its remaining share purchase warrants. Accordingly, Electrum and its affiliates will have significant influence in determining the outcome of any corporate transaction or other matter submitted to the shareholders for approval, including mergers, consolidations and the sale of all or substantially all of our assets and other significant corporate actions. Unless full participation of all shareholders takes place in such shareholder meetings, Electrum and its affiliates may be able to approve such matters itself. The concentration of ownership of the common shares by Electrum and its affiliates may: (i) delay or deter a change of control of the Company; (ii) deprive shareholders of an opportunity to receive a premium for their common shares as part of a sale of the Company; and (iii) affect the market price and liquidity of the common shares. In conjunction with the January 22, 2009 financing, we provided Electrum with the right to designate an observer at all meetings of the Board of Directors and any committee thereof so long as Electrum and its affiliates hold not less than 15% of our common shares. Electrum designated Igor Levental as its observer at our Board of Directors meetings. In July 2010, Igor Levental was appointed to our Board of Directors. In November 2011, Dr. Thomas S. Kaplan, was appointed Chairman of our Board. Dr. Kaplan is also the Chairman and Chief Executive Officer of The Electrum Group LLC, an investment advisor that manages Electrum’s investments. As long as Electrum and its affiliates maintain its shareholdings in the Company, Electrum will have significant influence in determining the members of the Board of Directors. Without the consent of Electrum, we could be prevented from entering into transactions that are otherwise beneficial to us. The interests of Electrum and its affiliates may differ from or be adverse to the interests of our other shareholders. The effect of these rights and Electrum’s influence may impact the price that investors are willing to pay for our shares. If Electrum or its affiliates sell a substantial number of our common shares in the public market, the market price of the common shares could fall. The perception among the public that these sales will occur could also contribute to a decline in the market price of our common shares.

Some of the directors have conflicts of interest as a result of their involvement with other natural resource companies.

Certain of our directors also serve as directors, or have significant shareholdings in, other companies involved in natural resource exploration and development or mining-related activities. To the extent that such other companies may participate in ventures in which we may participate in, or in ventures which we may seek to participate in, the directors may have a conflict of interest. In all cases where the directors have an interest in other companies, such other companies may also compete with us for the acquisition of mineral property investments. Such conflicts of the directors may result in a material and adverse effect on our profitability, results of operation and financial condition. As a result of these conflicts of interest, we may miss the opportunity to participate in certain transactions, which may have a material adverse effect on our financial position or future business prospects.

There is uncertainty related to unsettled aboriginal rights and title in British Columbia and this may adversely impact our operations and profit.

Native land claims in British Columbia remain the subject of active debate and litigation. The Galore Creek project lies within the traditional territory of the Tahltan Nation and the Tahltan, like the majority of British Columbia’s First Nations, have not concluded a comprehensive treaty or land claims settlement regarding their traditional territories. There can be no guarantee that the unsettled nature of land claims in British Columbia will not create delays in project approval or unexpected interruptions in project progress, or result in additional costs to advance the project.

Opposition to our operations from local stakeholders or non-governmental organizations could have a material adverse effect on us.

There is an increasing level of public concern relating to the effect of mining production on its surroundings, communities and environment. Local communities and non-governmental organizations (NGOs), some of which oppose resource development, are often vocal critics of the mining industry. While we seek to operate in a socially responsible manner, opposition to extractive industries or our operations specifically or adverse publicity generated by local communities or NGOs related to extractive industries, or our operations specifically, could have an adverse effect on our reputation and financial condition or our relationships with the communities in which we operate. As a result of such opposition or adverse publicity, we may be unable to obtain permits necessary for our operations or to continue our operations as planned or at all.

We have ongoing reclamation on some of our mineral properties and may be required to fund additional work that could have a material adverse effect on our financial position.

Land reclamation requirements are generally imposed on mineral exploration companies (as well as companies with mining operations) in order to minimize long term effects of land disturbance. Reclamation may include requirements to:

  • treat ground and surface water to drinking water standards;
  • control dispersion of potentially deleterious effluents;
  • reasonably re-establish pre-disturbance land forms and vegetation; and
  • provide adequate financial assurance to ensure required reclamation of land affected by our activities.

We have been carrying out certain remediation of land disturbed by previous exploration activities at the Donlin Gold and Galore Creek projects. Exploration and other activities at the Donlin Gold and Galore Creek projects have created disturbance that must be reclaimed. The initial access road construction at the Galore Creek project also would need to be reclaimed, if the Galore Creek project is not developed. Financial resources spent on reclamation might otherwise be spent on further exploration and development programs. In addition, regulatory changes could increase our obligations to perform reclamation and mine closure activities. There can be no assurance that we will not be required to fund additional reclamation work at these sites that could have a material adverse effect on our financial position.

An event of default under the Notes may significantly reduce our liquidity and adversely affect our business.

Under the base indenture and supplemental indenture governing the Notes, we made various covenants to the trustee on behalf of the holders of the Notes, including to make payments of interest and principal when due and, upon undergoing a fundamental change, to offer to purchase all of the outstanding Notes. The indenture is available for review on SEDAR at www.sedar.com (http://www.sedar.com) and on EDGAR at www.sec.gov (http://www.sec.gov).

If there is an event of default under the Notes, the principal amount of the Notes, plus accrued and unpaid interest, if any, may be declared immediately due and payable. If such an event occurs, we could be negatively impacted financially. At November 30, 2013, the principal amount remaining on the Notes was $15.8 million which is due May 1, 2015.

We are exposed to credit, liquidity, interest rate and currency risk.

Credit risk is the risk of an unexpected loss if a customer or third party to a financial instrument fails to meet its contractual obligations. Our cash equivalents and term deposit investments are held through large Canadian financial institutions with high investment-grade ratings. These investments mature at various dates over the current operating period. The carrying amount of financial assets recorded in the financial statements, net of any allowances for losses, represents our maximum exposure to credit risk.

Liquidity risk is the risk that we will not be able to meet our financial obligations as they come due. We manage liquidity risk through the management of our capital structure and financial leverage. Accounts payable, accrued liabilities and coupon interest on the convertible notes are due within one year from the balance sheet date.

Interest rate risk is the risk that the fair value or future cash flows of a financial instrument will fluctuate because of changes in market interest rates. The risk that we will realize a loss as a result of a decline in the fair value of the term deposit investments is limited because these investments have an original term of less than one year and are generally held to maturity. In respect of financial liabilities, the Notes are not subject to interest rate risk because they are at fixed rates. The promissory note owed to Barrick is variable with the U.S. prime rate. Based on the amount owing on the promissory note as of November 30, 2013, and assuming that all other variables remain constant, a 1% change in the U.S. prime rate would result in an increase/decrease of $0.7 million in the interest accrued by us per annum. For more detail with respect to the promissory note, see Item 2, Donlin Gold Project, Alaska, below.

We are exposed to the financial risk related to the fluctuation of foreign exchange rates. We operate in Canada and the United States and a portion of our expenses are incurred in Canadian dollars. A significant change in the currency exchange rate between the Canadian dollar relative to the U.S. dollar could have an effect on our results of operations, financial position or cash flows. We have not hedged our exposure to currency fluctuations. Based on our net exposures as of November 30, 2013, and assuming that all other variables remain constant, a 5% depreciation or appreciation of the Canadian dollar against the U.S. dollar would result in an increase/decrease of $3.5 million in our consolidated comprehensive income (loss).

Our insurance will not cover all of the potential risks associated with mining operations.

Our business is subject to a number of risks and hazards generally including adverse environmental conditions, industrial accidents, labor disputes, unusual or unexpected geological conditions, ground or slope failures, cave-ins, changes in the regulatory environment and natural phenomena, such as inclement weather conditions, floods, hurricanes and earthquakes. Such occurrences could result in damage to mineral properties or production facilities, personal injury or death, environmental damage to our properties or the property of others, delays in construction or mining, monetary losses and possible legal liability.

Although we maintain insurance to protect against certain risks in such amounts as we consider reasonable, our insurance will not cover all the potential risks associated with a mining company’s operations. We may also be unable to maintain insurance to cover these risks at economically feasible premiums. Insurance coverage may not continue to be available or may not be adequate to cover any resulting liability. Moreover, insurance against risks such as loss of title to mineral property, environmental pollution, or other hazards as a result of exploration and production is not generally available to us or to other companies in the mining industry on acceptable terms. We might also become subject to liability for pollution or other hazards which may not be insured against or which we may elect not to insure against because of premium costs or other reasons. Losses from these events may cause us to incur significant costs that could have a material adverse effect on our financial performance and results of operations.

Title and other rights to our mineral properties cannot be guaranteed and may be subject to prior unregistered agreements, transfers or claims and other defects.

We cannot guarantee that title to our mineral properties will not be challenged. We may not have, or may not be able to obtain, all necessary surface rights to develop a mineral property. Title insurance is generally not available for mineral properties and our ability to ensure that we have obtained secure claim to individual mineral properties or mining concessions may be severely constrained. Our mineral properties may be subject to prior unregistered agreements, transfers or claims, and title may be affected by, among other things, undetected defects. We have not conducted surveys of all of the mineral properties in which we hold direct or indirect interests. A successful challenge to the precise area and location of these mineral properties could result in us being unable to operate on our mineral properties as permitted or being unable to enforce our rights with respect to our mineral properties. This could result in us not being compensated for our prior investment relating to the mineral property.

Rising metal prices encourages mining exploration, development and construction activity, which in the past has increased demand for and cost of contract mining services and equipment.

Increases in metal prices tend to encourage increases in mining exploration, development and construction activities. During past expansions, demand for and the cost of contract exploration, development and construction services and equipment have increased as well. Increased demand for and cost of services and equipment could cause project costs to increase materially, resulting in delays if services or equipment cannot be obtained in a timely manner due to inadequate availability, and increased potential for scheduling difficulties and cost increases due to the need to coordinate the availability of services or equipment, any of which could materially increase project exploration, development or construction costs, result in project delays, or both. Increased costs were a significant factor in the decision to suspend construction at the Galore Creek project in 2007 and there can be no assurance that increased costs may not adversely affect our development of our mineral properties in the future.

Increased competition could adversely affect our ability to attract necessary capital funding or acquire suitable producing properties or prospects for mineral exploration in the future.

The mining industry is intensely competitive. Significant competition exists for the acquisition of mineral properties producing or capable of producing metals. We may be at a competitive disadvantage in acquiring additional mineral properties because we must compete with other individuals and companies, many of which have greater financial resources, operational experience and technical capabilities than us or are further advanced in their development or are significantly larger and have access to greater mineral reserves, for the acquisition of mineral claims, leases and other mineral interests. We may also encounter increasing competition from other mining companies in our efforts to hire experienced mining professionals. Increased competition could adversely affect our ability to attract necessary capital funding or acquire suitable producing properties or prospects for mineral exploration in the future. If we are unsuccessful in acquiring additional mineral properties or qualified personnel, we will not be able to grow at the rate we desire, or at all.

We may experience difficulty attracting and retaining qualified management and technical personnel to meet the needs of our anticipated growth, and the failure to manage our growth effectively could have a material adverse effect on our business and financial condition.

We are dependent on the services of key executives including our President and Chief Executive Officer and other highly skilled and experienced executives and personnel focused on managing our interests and the advancement of the Donlin Gold and Galore Creek projects, in addition to the identification of new opportunities for growth and funding. Due to our relatively small size, the loss of these persons or our inability to attract and retain additional highly skilled employees required for the development of our activities may have a material adverse effect on our business or future operations.

We do not currently intend to use forward sales arrangements to protect against low commodity prices; therefore, our operating results are exposed to the impact of any significant drop in commodity prices.

We do not currently intend to enter into forward sales arrangements to reduce the risk of exposure to volatility in commodity prices. Accordingly, our future operations are exposed to the impact of any significant decrease in commodity prices. If such prices decrease significantly at a time when we are producing, we would realize reduced revenues. While it is not our current intention to enter into forward sales arrangements, we are not restricted from entering into forward sales arrangements at a future date.

There can be no assurance that we will successfully acquire additional mineral rights.

Most exploration projects do not result in the discovery of commercially mineable ore deposits and no assurance can be given that any particular level of recovery of ore reserves will be realized or that any identified mineral deposit will ever qualify as a commercially mineable (or viable) ore body which can be legally and economically exploited. Estimates of reserves, mineral deposits and production costs can also be affected by such factors as environmental permitting regulations and requirements, weather, environmental factors, unforeseen technical difficulties, unusual or unexpected geological formations and work interruptions. If current exploration programs do not result in the discovery of commercial ore, we may need to write-off part or all of our investment in existing exploration stage properties, and may need to acquire additional mineral properties. Material changes in ore reserves, grades, stripping ratios or recovery rates may affect the economic viability of any project.

Our future growth and productivity will depend, in part, on our ability to identify and acquire additional mineral rights, and on the costs and results of continued exploration and development programs. Mineral exploration is highly speculative in nature and is frequently non-productive. Substantial expenditures are required to:

  • establish ore reserves through drilling and metallurgical and other testing techniques;
  • determine metal content and metallurgical recovery processes to extract metal from the ore; and
  • permit, construct, renovate or expand mining and processing facilities.

In addition, if we discover a mineral deposit, it would take several years from the initial phases of exploration until production is possible. During this time, the economic feasibility of production may change. As a result of these uncertainties, there can be no assurance that we will successfully acquire additional mineral rights.

We may experience problems integrating new acquisitions into existing operations, which could have a material adverse effect on us.

We may make selected acquisitions in the future, with a focus on late-stage development projects. Our success at completing any acquisitions will depend on a number of factors, including, but not limited to:

  • identifying acquisitions that fit our business strategy;
  • accurately assessing the value, strengths, weaknesses, contingent and other liabilities and potential profitability of acquisition candidates;
  • negotiating acceptable terms with the seller of the business or mineral property to be acquired; and
  • obtaining approval from regulatory authorities in the jurisdictions of the business or mineral property to be acquired.

If we do make further acquisitions, any positive effect on our results will depend on a variety of factors, including, but not limited to:

  • assimilating the operations of an acquired business or mineral property in a timely and efficient manner;
  • maintaining our financial and strategic focus while integrating the acquired business or mineral property;
  • achieving identified and anticipated operating and financial synergies;
  • unanticipated costs;
  • diversion of management attention from existing business;
  • potential loss of key employees or key employees of any business acquired;
  • unanticipated changes in business, industry or general economic conditions that affect the assumptions underlying the acquisition;
  • decline in the value of acquired mineral properties, companies or securities;
  • implementing uniform standards, controls, procedures and policies at the acquired business, as appropriate; and
  • to the extent that we make an acquisition outside of markets in which it has previously operated, conducting and managing operations in a new operating environment.

Acquiring additional businesses or mineral properties could place increased pressure on our cash flow if such acquisitions involve a cash consideration. The integration of our existing operations with any acquired business will require significant expenditures of time, attention and funds. Achievement of the benefits expected from consolidation would require us to incur significant costs in connection with, among other things, implementing financial and planning systems. We may not be able to integrate the operations of a recently acquired business or restructure our previously existing business operations without encountering difficulties and delays. In addition, this integration may require significant attention from our management team, which may detract attention from our day-to-day operations. Over the short-term, difficulties associated with integration could have a material adverse effect on our business, operating results, financial condition and the price of our common shares. In addition, the acquisition of mineral properties may subject us to unforeseen liabilities, including environmental liabilities, which could have a material adverse effect on us. There can be no assurance that any future acquisitions will be successfully integrated into our existing operations and such acquisition may result in a material adverse effect on our financial condition.

In addition, we anticipate that as we bring our mineral properties into production and as we acquire additional mineral rights, we will experience significant growth in our operations. We expect this growth to create new positions and responsibilities for management and technical personnel and to increase demands on our operating and financial systems. There can be no assurance that we will successfully meet these demands and effectively attract and retain additional qualified personnel to manage our anticipated growth. The failure to attract such qualified personnel to manage growth effectively could have a material adverse effect on our business, financial condition and results of operations.

We may have unknown liabilities in connection with acquisitions.

As part of our acquisitions, we have assumed liabilities and risks. While we conducted due diligence, there may be liabilities or risks that we failed, or were unable, to discover in the course of performing the due diligence investigations or for which we were not indemnified. Any such liabilities, individually or in the aggregate, could have a material adverse effect on our financial position and results of operations.

We may be subject to legal proceedings.

Due to the nature of our business, we may be subject to a variety of regulatory investigations, claims, lawsuits and other proceedings in the ordinary course of our business. The results of these legal proceedings cannot be predicted with certainty due to the uncertainty inherent in litigation, including the effects of discovery of new evidence or advancement of new legal theories, the difficulty of predicting decisions of judges and juries and the possibility that decisions may be reversed on appeal. There can be no assurances that these matters will not have a material adverse effect on our business.

Global climate change is an international concern, and could impact our ability to conduct future operations.

Global climate change is an international issue and receives an enormous amount of publicity. We would expect that the imposition of international treaties or U.S. or Canadian federal, state, provincial or local laws or regulations pertaining to mandatory reductions in energy consumption or emissions of greenhouse gasses could affect the feasibility of mining projects and increase operating costs.

Our projects are not directly threatened by current predictions of sea level rise because all of them are located inland at elevations from 100 meters to 4,000 meters above sea level. However, changes in sea levels could affect ocean transportation and shipping facilities, which would be used to transport supplies, equipment and personnel to our projects and products from those projects to world markets.

Extreme weather events (such as increased frequency or intensity of hurricanes, increased snow pack, prolonged drought) have the potential to disrupt operations at our projects. Where appropriate, our projects have developed emergency plans for managing extreme weather conditions; however, extended disruptions to supply lines due to extreme weather could result in interruption of activities at the project sites, delay or increase the cost of construction of the projects, or otherwise adversely affect our business.

We may fail to achieve and maintain the adequacy of internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act.

We have documented and tested our internal control procedures in order to satisfy the requirements of Section 404 of the Sarbanes-Oxley Act (SOX). SOX requires an annual assessment by management of the effectiveness of our internal control over financial reporting and an attestation report by our independent auditors addressing this assessment. At November 30, 2013, management concluded that our internal control over financial reporting was effective. We may in the future fail to achieve and maintain the adequacy of our internal control over financial reporting, as such standards are modified, supplemented or amended from time to time, and we may not be able to ensure that we can conclude on an ongoing basis that we have effective internal controls over financial reporting in accordance with Section 404 of SOX. Our failure to satisfy the requirements of Section 404 of SOX on an ongoing, timely basis could result in the loss of investor confidence in the reliability of our financial statements, which in turn could harm our business and negatively impact the trading price of our shares. In addition, any failure to implement required new or improved controls, or difficulties encountered in their implementation, could harm our operating results or cause us to fail to meet our reporting obligations. Future acquisitions of companies may provide us with challenges in implementing the required processes, procedures and controls in our acquired operations. Acquired companies may not have disclosure control and procedures or internal control over financial reporting that are as thorough or effective as those required by securities laws currently applicable to us.

No evaluation can provide complete assurance that our internal control over financial reporting will detect or uncover all failures of persons within the Company to disclose material information otherwise required to be reported. The effectiveness of our internal controls and procedures could also be limited by simple errors or faulty judgments. In addition, should we expand in the future, the challenges involved in implementing appropriate internal controls over financial reporting will increase and will require that we continue to improve our internal controls over financial reporting. Although we intend to devote substantial time and incur substantial costs, as necessary, to ensure compliance, we cannot be certain that we will be successful in complying with Section 404 of SOX on an ongoing basis.

We are subject to increased regulatory compliance costs relating to the Dodd-Frank Act.

In July 2010, the “Dodd-Frank Wall Street Reform and Consumer Protection Act” (“Dodd-Frank Act”) was enacted, representing an overhaul of the framework for regulation of U.S. financial markets. The Dodd-Frank Act calls for various regulatory agencies, including the SEC and the Commodities Futures Trading Commission, to establish regulations for implementation of many of the provisions of the Dodd-Frank Act, and we anticipate that these new regulations will provide additional clarity regarding the extent of the impact of this legislation on us. If our efforts to comply with new laws, regulations and standards differ from the activities intended by regulatory or governing bodies due to ambiguities related to practice, regulatory authorities may initiate legal proceedings against us and our business may be harmed. Dodd-Frank also requires companies in the mining industry to disclose substantial additional information in their periodic reports filed with the SEC about safety issues relating to their mining operations and will require us to disclose on an annual basis, once a final rule becomes effective, certain payments made by us, our subsidiaries or entities we control, to the U.S. government and foreign governments, including sub-national governments. This heightened scrutiny could generate negative publicity for the mining industry, increase the cost of compliance with mining regulations or result in the passage of new laws and regulations, any of which could negatively affect our business results. We may also need to incur additional costs and invest additional resources, including management’s time, in order to comply with the new regulations and anticipated additional reporting and disclosure obligations. While we are not able to assess the full impact of the Dodd-Frank Act until all the implementing regulations have been adopted, based on the information available to us at this time, we do not believe provisions of the regulations implementing the Dodd-Frank Act will have a material adverse effect on our financial position, results of operations or cash flows.

Acquiring, holding or disposing of our securities may have tax consequences under the laws of Canada and the United States that are not disclosed in this Annual Report on Form 10-K and, in particular, potential investors should be aware that we believe we are likely a “passive foreign investment company” under the U.S. Internal Revenue Code, which may have adverse tax consequences for investors in the United States.

Acquiring, holding or disposing of our securities may have tax consequences under the laws of Canada and the United States that are not disclosed in this Annual Report on Form 10-K. In particular, potential investors that are U.S. taxpayers should be aware that we may be considered a “passive foreign investment company” under Section 1297(a) of the U.S. Internal Revenue Code (a PFIC). We believe that we were likely a PFIC for our tax year ended November 30, 2013 and may be a PFIC for our current and future tax years. PFIC classification is fundamentally factual in nature, generally cannot be determined until the close of the tax year in question, and is determined annually. Additionally, the analysis depends, in part, on the application of complex U.S. federal income tax rules, which are subject to differing interpretations. In any tax year in which we are a PFIC, a U.S. taxpayer will be required to file an annual report with the Internal Revenue Service containing such information as Treasury Regulations or other tax rules may require.

Any gain recognized on the sale of common shares of a PFIC and any excess distributions paid on the common shares of a PFIC must be ratably allocated to each day in a U.S. taxpayer’s holding period for the common shares. The amount of any such gain or excess distribution allocated to prior years of such U.S. taxpayer’s holding period for the common shares generally will be subject to U.S. federal income tax at the highest tax applicable to ordinary income in each such prior year, and the U.S. taxpayer will be required to pay interest on the resulting tax liability for each such prior year, calculated as if such tax liability had been due in each such prior year.

Alternatively, a U.S. taxpayer that makes a timely “QEF election” generally will be subject to U.S. federal income tax on such U.S. taxpayer’s pro rata share of our “net capital gain” and “ordinary earnings” (calculated under U.S. federal income tax rules), regardless of whether such amounts are actually distributed by us. U.S. taxpayers should be aware that there can be no assurance that we will satisfy record-keeping requirements or that we will supply U.S. taxpayers with required information under the QEF rules, in event that we are a PFIC and a U.S. taxpayer wishes to make a QEF election. As a second alternative, a U.S. taxpayer may make a “mark-to-market election” if we are a PFIC and the common shares are marketable stock. A U.S. taxpayer that makes a mark-to-market election generally will include in gross income, for each taxable year in which we are a PFIC, an amount equal to the excess, if any, of (a) the fair market value of the common shares as of the close of such taxable year over (b) such U.S. taxpayer’s tax basis in such common shares.

Investors should consult their tax advisors as to the tax consequences of an investment in our securities.

We are a Canadian company and U.S. investors may have difficulty bringing actions and enforcing judgments under U.S. securities laws.

Investors in the United States or in other jurisdictions outside of Canada may have difficulty bringing actions and enforcing judgments against us, our directors, our executive officers and some of the experts named in this Annual Report on Form 10-K based on civil liabilities provisions of the federal securities laws or other laws of the United States or any state thereof or the equivalent laws of other jurisdictions of residence.

Properties

As filed, 101,399 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following descriptions summarize selected information about our 50% interest in the Donlin Gold project located in Alaska, USA and our 50% interest in the Galore Creek project located in British Columbia, Canada. Both of these mineral projects are without known reserves, as defined under SEC Industry Guide 7. The disclosure in this Annual Report on Form 10-K of a scientific or technical nature for our mineral properties is based on the following technical reports prepared in accordance with NI 43-101:

(i) “Donlin Creek Gold Project Alaska, USA, NI 43-101 Technical Report on Second Updated Feasibility Study” (“Donlin Gold FS”) for the Donlin Gold project in southwestern Alaska, USA, effective date November 18, 2011 and amended and filed on January 20, 2012. The independent technical report was prepared for NOVAGOLD by Kirk Hanson, P.E., Gordon Seibel, R.M. SME., and Tony Lipiec, P.Eng., all of whom are Qualified Persons as defined in NI 43-101. The Donlin Gold FS has been filed with the securities regulatory authorities in each province of Canada and with the SEC. Portions of the following information are based on assumptions, qualifications and procedures that are not fully described herein. References should be made to the full text of the Donlin Gold FS which is available for review on EDGAR at www.sec.gov (http://www.sec.gov) and on SEDAR at www.sedar.com (http://www.sedar.com).

(ii) “Galore Creek Copper-Gold Project NI 43-101 Technical Report on Pre-Feasibility Study, British Columbia – Canada” (the PFS) for the Galore Creek project in northwestern British Columbia, Canada, effective date July 27, 2011 and filed on September 12, 2011. The independent technical report was prepared for GCMC, NOVAGOLD and Teck Resources Inc. (“Teck”) by Robert Gill, P.Eng., Jay Melnyk, P.Eng., Greg Wortman, P.Eng., Greg Kulla, P.Geo., and Dana Rogers, P.E., all of whom are Qualified Persons as defined in NI 43-101. The PFS has been filed with the securities regulatory authorities in each province of Canada and with the SEC. Portions of the following information are based on assumptions, qualifications and procedures which are not fully described herein. References should be made to the full text of the PFS which is available for review on EDGAR at www.sec.gov (http://www.sec.gov) and on SEDAR at www.sedar.com (http://www.sedar.com). Heather White, B.Sc., P.Eng., who is a consultant to the Company and a "qualified person" under the NI 43-101, has approved the scientific and technical information included in this Annual Report on Form 10-K related to: (1) Donlin Gold since the issuance of the technical report filed on January 23, 2012, and (2) Galore Creek since the issuance of the technical report filed on September 12, 2011.

Cautionary Note to U.S. Investors: This section and other sections of this Annual Report on Form 10-K contain the terms “measured mineral resources,” “indicated mineral resources,” “inferred mineral resources,” “proven mineral reserves,” and “probable mineral reserves” as defined in accordance with NI 43-101. Please note the following regarding these terms:

“Proven mineral reserves” and “probable mineral reserves” – The definitions of proven and probable mineral reserves used in NI 43-101 differ from the definitions for “proven reserves” and “probable reserves” as found in SEC Industry Guide 7. Accordingly, our disclosures of mineral reserves herein may not be comparable to information from U.S. companies subject to reporting and disclosure requirements of the SEC.

“Measured mineral resources” and “indicated mineral resources” – we advise U.S. investors that although these terms are recognized and required by Canadian regulations, these terms are not defined in SEC Industry Guide 7 and the SEC does not normally permit such terms to be used in reports and registration statements filed with the SEC. U.S. investors are cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into reserves.

“Inferred mineral resources” – we advise U.S. investors that although this term is recognized by Canadian regulations, the SEC does not recognize it. “Inferred mineral resources” have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of a feasibility study or prefeasibility study, except in rare cases. The SEC normally only permits an issuer to report mineralization that does not constitute “reserves” as in-place tonnage and grade without reference to unit measures. U.S. investors are cautioned not to assume that any part or all of an inferred mineral resource exists or is economically or legally minable.

Donlin Gold Project, Alaska

The Donlin Gold project is an advanced-stage gold project held by Donlin Gold, a limited liability company that is owned 50% by our wholly-owned subsidiary, NOVAGOLD Resources Alaska, Inc. and 50% by Barrick’s wholly-owned subsidiary, Barrick Gold U.S. Inc. The Donlin Gold project is located in southwestern Alaska on private, Alaska Native-owned mineral and surface land and Alaska state mining claims. The 81,361 acre (32,926 hectare) property hosts a gold deposit currently estimated at 33.8 million ounces of proven and probable reserves averaging 2.09 grams per tonne. We believe that significant exploration potential remains in the Donlin Gold district, with prospects to increase mine life and/or justify future production expansions.

We entered into a limited liability company agreement with Barrick (“LLC Agreement”) dated December 1, 2007 that provided for the creation of Donlin Gold, which is jointly owned by us and Barrick on a 50/50 basis. Pursuant to the LLC Agreement, we agreed to reimburse Barrick out of future mine production cash flow for a portion of Barrick’s prior expenditures in the Donlin Gold project. As of November 30, 2013, the promissory note, including accrued interest, amounted to approximately $71.7 million. Funding is currently shared by both parties on a 50/50 basis.

Except for the information contained under the heading “Item 1, Recent Developments – Donlin Gold” or as otherwise stated, the scientific and technical information regarding the Donlin Gold project in this Annual Report on Form 10-K is based on the Donlin Gold FS.

Property Description and Location

The Donlin Gold property is located in the Kuskokwim region of southwestern Alaska. The property is under lease (the “Mining Lease”) for subsurface rights from Calista Corporation (“Calista”) and surface rights (the “Surface Use Agreement”) from The Kuskokwim Corporation (TKC), two Alaska Native corporations. Calista is one of 13 regional Alaska Native corporations established as part of the Alaska Native Claims Settlement Act of 1971 (ANCSA) and under ANCSA has title to the subsurface estate in the region. TKC was formed in 1977 when the ANCSA village corporations of Lower Kalskag, Upper Kalskag, Aniak, Chuathbaluk, Napaimute, Crooked Creek, Red Devil, Georgetown, Sleetmute and Stony River, which are located along the middle region of the Kuskokwim River, merged. Under ANCSA, TKC has title to extensive surface estate in the region, including most of the project lands.

Other lands required for offsite infrastructure, such as the Jungjuk port site, the road to the port site and gas pipeline are categorized as Native, State of Alaska conveyed, or Bureau of Land Management (BLM) lands. Rights-of-way will be required from other Alaska Native corporations, the state of Alaska and BLM for the road and pipeline alignments that cross Native corporation, state and federal lands.

Permits

Donlin Gold has maintained all of the necessary permits for exploration, camp facilities, and related activities. These permits are active with the Alaska Department of Natural Resources (hard rock exploration, temporary water use), the U.S. Army Corps of Engineers (individual 404 and nationwide 26), U.S. Bureau of Land Management (rights-of-way), Alaska State Department of Conservation (wastewater, drinking water, food handling), the Alaska Department of Fish and Game (title 16 – fish), Federal Aviation Administration (airport), and other State, Federal and private entities. Current permits have allowed exploration and associated feasibility study supporting test work to be conducted under appropriate state and federal laws.

On August 7, 2012, we announced that Donlin Gold commenced permitting of the project by submitting a draft Plan of Operations and Section 404 of the U.S. Clean Water Act draft permit application to federal and state regulators. The Section 404 permit application initiated the environmental review process under NEPA which involves preparation of an EIS. The Corps selected URS, an independent contractor to prepare the EIS. The Notice of Intent for the EIS was published in the Federal Register on December 14, 2012 and the NEPA public scoping process was completed March 29, 2013. During the remainder of 2013, Donlin Gold worked to address the remaining data needs for the EIS. Throughout 2013, Donlin Gold also continued to provide application materials and maintained ongoing dialogue with the agencies that will issue the key permits and authorizations needed for the Donlin Gold project, including the air quality, water discharge, dam safety, wetlands, water use, fish habitat, and pipeline permits. The Corps and the NEPA contractor are working towards planned issuance of a preliminary draft EIS for agency review in late 2014.

An extensive list of additional federal and state government permits and approvals must be obtained before the Donlin Gold project can commence construction. Preparation of the applications for many of these permits and approvals requires additional, more detailed engineering that was not part of the Donlin Gold FS. Completion of this engineering will require a significant investment of funds, time, and other resources by Donlin Gold and its contractors. Also, the Donlin Gold board must approve a construction program and budget before construction of the Donlin Gold project can begin. The timing of the required engineering work, of the Donlin Gold board’s approval of a construction program and budget, as well as the receipt of all required governmental permits and approvals will determine whether and when construction of the Donlin Gold project will begin. Project delays also could occur as a result of public opposition, limitations in regulatory staff resources during regulatory review, or project changes made by Donlin Gold.

Mineral Tenure

The Mining Lease currently includes mineral rights leased from Calista, which holds the subsurface (mineral) estate for Native-owned lands in the region. The leased land is believed to contain 20,101 hectares (49,671 acres). Calista also owns the surface estate on a portion of these lands. The Surface Use Agreement with TKC, which owns the surface estate of the remaining lands, grants non-exclusive surface use rights to Donlin Gold for mining activities. All of the lands subject to the Mining Lease and Surface Use Agreement have been conveyed to Calista and TKC by the Federal Government. Donlin Gold is engaged in negotiations with TKC regarding amendments to the Surface Use Agreement.

In addition to the leased land, Donlin Gold holds 242 State of Alaska mineral claims comprising 12,853 hectares (31,760 acres) in the Kuskokwim and Mt. McKinley recording districts primarily surrounding the lands subject to the Mining Lease and Surface Use Agreement. Of the Alaska mineral claims, 3 claims are on state selected lands; 158 claims are tentatively approved for conveyance from the Federal to State government subject to official surveying. These claims have not been legally surveyed. All claims are either 16.2 hectares (40 acres) or 64.8 hectares (160 acres) in size.

Accessibility and Climate

The Donlin Gold property is located in southwestern Alaska, approximately 20 kilometers north of the village of Crooked Creek on the Kuskokwim River. The Kuskokwim River is a regional transportation route and is serviced by commercial barge lines. A 25 kilometer long winter road, designated as an Alaska State Highway route and transportation corridor, accesses the property from the barge landing at the village of Crooked Creek. The Donlin Gold project currently has an all-season, soft-sided camp with facilities to house up to 150 people. An adjacent 1,500 meter long airstrip is capable of handling aircraft as large as C-130 Hercules (42,000 pounds or 19,050 kilograms), allowing efficient shipment of personnel, some heavy equipment, and supplies. The Donlin Gold project can be reached directly by charter air facilities out of both Anchorage, 450 kilometers to the east and Aniak, 80 kilometers to the west.

The project area is one of low topographic relief on the western flank of the Kuskokwim Mountains. Elevations range from 150 meters to 640 meters. Ridges are well rounded and easily accessible by all-terrain vehicle. Hillsides are forested with black spruce, tamarack, alder, birch and larch. Soft muskeg and discontinuous permafrost are common in poorly drained areas at lower elevations. The area has a relatively dry interior continental climate with typically less than 50 cm (20 inches) total annual precipitation. Summer temperatures are relatively warm and may reach nearly 30°C (83°F). Minimum temperatures may fall to well below -42°C (-45°F) during the cold winter months.

The Donlin Gold project is currently isolated from power and other public infrastructure. Sufficient space is available to house the various facilities, including personnel housing, stockpiles and processing plants. Ample water supply is available from surface and subsurface sources. Power is produced by on-site generators.

Exploration History

Year Company Work Performed Results
1909 to 1956 Various prospectors and placer miners Gold discovered in 1909. Placer mining by hand, underground, and hydraulic methods. Total placer gold production of approximately 30,000 ounces.
1970s to present Robert Lyman and heirs Resumed sluice mining in Donlin Gold area and placer mined Snow Gulch. First year of mining Snow Gulch produced best results, with 800 ounces of gold recovered. Donlin Gold has obtained an agreement with the Lyman family to consolidate the land package around the proposed mine.
1974, 1975 Resource Associates of Alaska (RAA) Regional mineral potential evaluation for Calista. Soil grid and three bulldozer trenches dug in Snow Gulch area. Soil, rock, and vein samples have anomalous gold values. Trench rock sample results range from 2 to 20 grams per tonne gold.
1984 to 1987 Calista Corporation Minor work. Geologists from various mining companies, including Cominco and Kennecott, visit the property.
1986 Lyman Resources Auger drilling for placer evaluation finds abundant gray, sulfide rich clay near Quartz Gulch. Assays of cuttings average over 7 grams per tonne gold. Initial discovery of Far Side (“Carolyn”) prospect.
1987 Calista Corporation Rock sampling of ridge tops and auger drill sampling of Far Side prospect. Anomalous gold values from auger holes: best result = 9.7 grams per tonne gold.
1988 to 1989 Western Gold Exploration and Mining Co. (WestGold) Airborne geophysics, geological mapping, and soil sampling over most of the project area. Total of 13,525 meters of D9 Cat trenching at all prospects. Over 15,000 soil, rock chip, and auger samples collected. Drilling included 3,106 feet of AX core drilling, 404 meters in 239 auger holes, and 10,423 meters of RC drilling (125 holes). First metallurgical tests and petrographic work. Initial work identified eight prospects with encouraging geology (Snow, Dome, Quartz, Carolyn, Queen, Upper Lewis, Lower Lewis, and Rochelieu). Drilling at most of these prospects led to identification of the Lewis areas as having the best bulk-mineable potential. Mineral resource estimate completed.
1993 Teck Exploration Ltd. D-9 Cat trenching (1,400 meters) and two 500 meter soil lines in Lewis area. Petrographic, fluid inclusion, and metallurgical work. Identified new mineralized areas, updated Mineral resource estimate.
1995 to 2000 Placer Dome 87,383 meters of core, 11,909 meters of RC drilling and 8,493 meters of trenching. Environmental monitoring and assessment. Drilled the American Creek magnetic anomaly (ACMA), discovered the ACMA deposit. Numerous mineral resource estimation iterations.
2001 to 2002 NOVAGOLD 46,495 meters of core, 38,022 meters of RC drilling, 89.5 meters of geotechnical drilling, and 268 meters of water monitoring holes. Filed a preliminary assessment report on the project. Updated resource estimate.

35

Year Company Worked Performed Results
2003 to 2005 Donlin Gold Joint Venture 25,448 meters of core and 5,979 meters of RC drilling. Calcium carbonate exploration drilling; IP lines for facility condemnation studies. Infill drilled throughout the resource area. Discovered a calcium carbonate resource. Poor quality IP data.
2006 Donlin Gold Joint Venture 92,804 meters of core drilling to support mineral resource classification conversion, slope stability, metallurgy, waste rock, carbonate exploration, facilities and port road studies. Geological model and mineral resource update.
2007 Donlin Gold Joint Venture Core drilling totaled 75,257 meters and included resource delineation, geotechnical and engineering, and carbonate exploration. 13 RC holes for monitor wells and pit pump tests totaled 1,043 meters. Improved pit slope parameters, positive hydrogeological results. Carbonate exploration was negative. Updated mineral resource estimate. Completed feasibility study with positive results.
2008 Donlin Gold LLC 108 core holes totaling 33,425 meters for exploration and facility related geotechnical and condemnation studies. Updated resource models. Metallurgical test work: flotation variability and CN leach. 54 test pits and 37 auger holes were also completed for overburden characterization. Resource expansion indicated for East ACMA. CN leach resource potential indicated for the main resource area, Snow, and Dome prospects. Facility sites successfully condemned. Updated resource estimates utilizing applicable data through 2007.
2009 Donlin Gold LLC 19 geotechnical core holes totaling 950 meters in facility sites and to address hydrology.
2010 Donlin Gold LLC Six geotechnical core holes totaling 2,090 meters to evaluate slope stability of expanded pit. Also drilled 90 auger holes totaling 585 meters and dug 59 test pits to further evaluate overburden conditions and gravel supplies within tailings storage facility (TSF) area. Pit slope stability of new pit design remained acceptable. Construction suitability of surficial materials in TSF is evaluated.

Geology

Regional Geology

The Kuskokwim region of southwestern Alaska is predominately underlain by rocks of the Upper Cretaceous Kuskokwim Group that filled a subsided northeast-trending strike-slip basin between a series of amalgamated terranes. Intermediate composition volcano-plutonic complexes intrude and overlie Kuskokwim Group rocks throughout the region.

Local Geology

The Donlin Gold deposits lie between two regional, northeast-trending, right lateral fault systems: the Denali-Farewell fault system to the south and the Iditarod-Nixon Fork fault system to the north. Undivided Kuskokwim Group sedimentary rocks and granite porphyry complexes are the main rock units.

Property Geology

Greywacke is dominant in the northern part of the area (“northern resource area” comprising Lewis, Queen, Rochelieu, and Akivik), while shale-rich units are common in the southern part of the area (“southern resource area” comprising South Lewis and ACMA).

Gold deposits are associated with an extensive Late Cretaceous–Early Tertiary gold–arsenic–antimony–mercury hydrothermal system. Gold-bearing zones exhibit strong structural and host rock control along north–northeast-trending fracture zones and are best developed where those zones intersect relatively competent host rocks. Mineralized material is most abundant in intrusive dikes and sills, but sedimentary rocks are also mineralized within strong fracture zones.

Geotechnical and Hydrology

A number of geotechnical and hydrological studies have been completed in support of feasibility and environmental reports for Donlin Gold.

Rowland Engineering Consultants performed the geotechnical assessments for the engineering to support design of the port site, airstrip, plant site and interconnecting roads. BGC, Inc. performed geotechnical analyses for the design of the pit, waste rock facility, and tailings storage facility (TSF).

The site-wide hydrological model developed by BGC, is based on extensive drill data and climatic information for the area. BGC, Inc. and CEMI provided hydrologic studies, design criteria and associated test work for the water treatment plant requirements during construction, operations, and closure. Lorax Environmental performed water quality modeling for the post closure pit lake.

Exploration Potential

The mineral resource defined in the Donlin Gold FS is confined to a small portion of the property. We believe there is considerable potential to increase the mineral resources at the Donlin Gold project. Numerous other targets have been identified along the 8 kilometer mineralized gold trend, and are defined by surface sampling and various historical drill holes containing significant gold values.

Exploration potential in the vicinity of the open pit design in the Donlin Gold FS includes extensions along strike to the East ACMA, Lewis, and Crooked Creek areas. Mineralization remains open at depth under the current pit limits. Mineralization also remains open to the north of the planned pit and has been tested by shallow trenching and soil sampling, with limited drilling undertaken to date.

Exploration potential at the Donlin Gold project also exists outside the areas that have been the subject of the mine design in the Donlin Gold FS. Gold mineralization is associated with an overall north–northeasterly-trending high level dike/sill complex that has been outlined in the regional aero-magnetics as a magnetic low. The zone, approximately 8 kilometers long, and 4 kilometers wide, consists of a northern, dike-dominated area, and a southern, more sill-dominated area.

Mineralization

Southeast-dipping north-northeast-oriented fracture zones are the primary control on gold bearing vein distribution within the north-northeast mineralized corridors. Composite vein zones or mineralized corridors range up to 30 meters in width and extend for hundreds of meters along strike. Intrusive rocks and to a lesser extent competent massive greywacke are the most favored host rocks, and act as a secondary control on the mineralization. Gold distribution in the deposit closely mimics the intrusive rocks, which contain about 74% of the mineral resource identified in the Donlin Gold FS. Structural zones in competent sedimentary units account for the remaining 26%.

Gold-bearing sulfides occur in both veins and disseminated zones in mafic igneous bodies, rhyodacite dikes and sills, and sedimentary rocks. Quartz-carbonate-sulfide (pyrite, stibnite, and arsenopyrite) veins are the primary mineralized features, but gold also occurs in thin, discontinuous sulfide fracture fillings.

Minor Elements and Deleterious Materials

The most abundant minor elements associated with gold-bearing material are iron, arsenic, antimony, and sulfur. They are contained primarily in the mineral suite associated with hydrothermal deposition of gold, including pyrite, arsenopyrite, realgar, native arsenic, and stibnite. Minor hydrothermal pyrrhotite, marcasite and syngenetic or sedimentary pyrite, also account for some of the iron and sulfur.

Three elements that have particular processing significance are mercury, chlorine, and fluorine. Graphitic carbon and carbonate minerals also would negatively affect the metallurgical process.

Metallurgy

Sufficient metallurgical testwork was completed under the direction of Barrick personnel to support the Donlin Gold FS. Gold is mainly carried by arsenopyrite. Variation is observed in processing behavior between intrusive rocks and sedimentary rocks, but less so between the geographical sources.

Process testing generated development of the following conceptual flowsheet:

  • concentration by flotation;
  • high pressure oxidation in an autoclave;
  • carbon-in-leach (“CIL”) cyanidation of the oxidized concentrate;
  • carbon strip and regeneration circuits;
  • gold electrowinning; and
  • refining and production of doré bars.

This processing concept incorporates proven commercial unit operations.

Reserve and Resource Estimate

The mineral reserves for the Donlin Gold project were classified using criteria appropriate under the CIM Definition Standards with an effective date of July 11, 2011. The mineral reserves are summarized in the table below.

Proven and Probable Mineral Reserve Estimate

Reserve Category Tonnes (thousands) Gold Grade (grams/tonne) Contained Gold (thousands of ounces)
Proven 7,683 2.32 573
Probable 497,128 2.08 33,276
Proven and probable 504,811 2.09 33,849

Notes:

(1) Mineral reserves are contained within Measured and Indicated pit designs, and supported by a mine plan, featuring variable throughput rates, stockpiling and cut-off optimization. The pit designs and mine plan were optimized on diluted grades using the following economic and technical parameters: Metal price for gold of $975 per ounce; reference mining cost of $1.67 per tonne incremented $0.0031 per tonne per meter with depth from the 220 meter elevation (equates to an average mining cost of $2.14 per tonne), variable processing cost based on the formula 2.1874 x (S%) + 10.65 for each $ per tonne processed; general and administrative cost of $2.27 per tonne processed; stockpile rehandle costs of $0.19 per tonne processed assuming that 45% of mill feed is rehandled; variable recoveries by rock type, ranging from 86.66% in shale to 94.17% in intrusive rocks in the Akivik domain; refining and freight charges of $1.78 per ounce gold; royalty considerations of 4.5%; and variable pit slope angles, ranging from 23º to 43º. The Mineral Reserves are reported in accordance with NI 43-101, which differs from Industry Guide 7. The project is without known reserves under SEC Industry Guide 7. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(2) Mineral reserves are reported using an optimized net sales return value based on the following equation: net sales return = Gold grade * Recovery * ($975 – (1.78 + ($975 – 1.78) * 0.045)) – (10.65 + 2.1874 * (S%) + 2.27 + 0.19) and reported in $ per tonne.

(3) The life of mine strip ratio is 5.48. The assumed life-of-mine throughput rate is 53,500 tonnes per day.

(4) Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content.

(5) Mineral reserves are reported on a 100% basis. NOVAGOLD and Barrick each own 50% of the Donlin Gold project. Tonnage and grade measurements are in metric units. Contained gold ounces are reported as troy ounces.

Mineral reserves have been estimated using a long-term gold price assumption of $975 per ounce. Mineral resources are based on a Whittle™ pit optimized for all measured, indicated, and inferred blocks assuming a gold selling price of $1,200 per ounce and are inclusive of reserves.

Mineral resources were classified using criteria appropriate under the CIM Definition Standards by application of the NSR-based cut-off grade that incorporated mining and recovery parameters, and constraint of the mineral resources to a pit shell based on commodity prices. The mineral resources have an effective date of July 11, 2011. The mineral resources are summarized in the table below.

Measured and Indicated Resources Estimate (inclusive of reserves)

Resource Category Tonnes (thousands) Gold Grade (grams/tonne) Contained Gold (thousands of ounces)
Measured 7,731 2.52 626
Indicated 533,607 2.24 38,380
Measured and indicated 541,337 2.24 39,007

Notes:

(1) Mineral resources that are not mineral reserves do not have demonstrated economic viability. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(2) Mineral resources are inclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(3) Mineral resources are contained within a conceptual measured, indicated and inferred optimized pit shell using the following assumptions: gold price of $1,200 per ounce; variable process cost based on 2.1874 * (sulfur grade) + 10.65; administration cost of $2.29 per tonne; refining, freight & marketing (selling costs) of $1.85 per ounce recovered; stockpile re-handle costs of $0.20 per tonne processed assuming that 45% of mill feed is re-handled; variable royalty rate, based on royalty of 4.5% * (Gold price – selling cost).

(4) Mineral resources have been estimated using a constant net sales return cut-off of $0.001 per tonne milled. The net sales return cut-off was calculated using the formula: NSR = Gold grade * Recovery * ($1,200 – (1.85 + ($1,200 – 1.85) * 0.045)) – (10.65 + 2.1874 * (S%) + 2.29 + 0.20) and reported in $ per tonne.

(5) Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content.

(6) Tonnage and grade measurements are in metric units. Contained gold ounces are reported as troy ounces. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

Inferred Mineral Resource Estimate

Resource Category Tonnes (thousands) Gold Grade (grams/tonne) Contained Gold (thousands of ounces)
Inferred 92,216 2.02 5,993

Notes:

(1) Inferred resources are in addition to measured and indicated resources. Inferred resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher category. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(2) Tonnage and grade measurements are in metric units. Contained gold ounces are reported as troy ounces. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

Feasibility Study and Updates

On December 5, 2011, we announced the results of the Donlin Gold FS which revised the previous 2009 feasibility study with updated mineral reserves and resources, capital costs and operating cost estimates. The Donlin Gold FS also utilizes natural gas as the primary power generation fuel source for the project rather than the original diesel option. Based on the Donlin Gold FS, the project is expected to be a conventional truck-and-shovel open-pit operation. The mine life is estimated to be 27 years based on a nominal processing rate of 59,000 tons (53,500 tonnes) per day. During the first five years of full operation, expected production averages 1.46 million ounces of gold annually and an average of 1.13 million ounces of gold per year over its projected 27 year mine life. The total capital cost estimate for the Donlin Gold project is approximately $6.7 billion including costs related to the natural gas pipeline and a contingency of $984 million. The project’s estimated after-tax net present value at a 5% discount rate (“NPV5%”) is $547 million using the base case gold price of $1,200 per ounce. The internal rate of return (IRR) at the same gold price is 6.0%.

Base Case Project Sensitivity to Gold Price

Gold ($ per ounce) LOM Cash Flow ($ million) Jan 2014 NPV5% ($ million) Jan 2014 IRR (%)
$700 $(5,690) $(4,917) —
$800 $(2,838) $(3,637) —
$900 $(45) $(2,374) —
$1,000 $2,143 $(1,342) 2.3
$1,100 $4,191 $(385) 4.3
$1,200 $6,197 $547 6.0
$1,300 $8,187 $1,465 7.5
$1,400 $10,166 $2,375 8.9
$1,500 $11,631 $3,147 10.2
$1,600 $13,092 $3,862 11.2
$1,700 $14,616 $4,581 12.3
$1,800 $16,156 $5,296 13.2
$1,900 $17.699 $6,010 14.2
$2,000 $19,248 $6,722 15.1

Summary of Key Evaluation Metrics (Base Case at $1,200 per ounce gold)

Total tonnes mined (million) 3,270
Ore tonnes treated (million) 505
Strip ratio (waste tonnes per ore tonne) 5.48
Gold ounces recovered (million) 30.4
Gold recovery (%) 89.8%
($ million)
Gold, net revenue $36,445
Less:
Mining (8,200)
Processing (7,808)
G&A, community, refining & land (3,241)
Costs applicable to sales(1) (19,249)
Initial capital (6,679)
Sustaining capital (1,505)
Total capital (8,184)
Income taxes (2,748)
Reclamation trust fund (274)
Total costs (30,455)
Total cash flow(2) $6,197
Payback period (years) 9.2
Operation life (years) 27
Jan 2014 NPV5%(3) ($ million) $547
Jan 2014 IRR 6.0%

Notes:

(1) Costs applicable to sales (US GAAP), excluding Depreciation and Reclamation costs.

(2) Cash flow after-tax excludes sunk costs.

(3) Reference dates for discounted cash flow metrics are January 1, 2014 and exclude funds expended before that date.

Operating Cost Estimates

$ per ounce $ per tonne milled
Mining cost $270 $16.24
Process cost 257 15.47
G&A, community, refining & land 107 6.42
$634 $38.13

Capital Cost Estimates

($ million)
Mining $345
Site preparation /roads 236
Process facilities 1,326
Tailings 120
Utilities (including natural gas pipeline) 1,302
Ancillary buildings 304
Off-site facilities 243
Total direct costs 3,876
Owners’ costs 414
Indirect costs 1,405
Contingency 984
Total indirect and contingency 2,803
Total project cost $6,679

Sustaining capital requirements are estimated at $1,505 million over the life of the mine.

Planned Mining Operations

The Donlin Gold project will be mined by a conventional truck-and-shovel operation. Initial pioneering and pit development will be undertaken to remove overburden, develop mine access roads suitable for large mining equipment, and “face-up” the initial pit into productive set-ups for the large shovel and mining equipment.

Large hydraulic shovels mining the full 12 meter benches will be the primary loading equipment in zones of waste and steeply dipping ore. The same primary shovels will be used on the 6 meter split benches, thereby avoiding the need for a mixed fleet of hydraulic shovels. Large 360 tonne capacity haul trucks will be used for transporting both ore and waste out of the pit.

Blast hole drilling in predominantly waste areas will be performed with nominal 251 millimeters diameter production drills. Ore zones will be drilled on a single 12 meter bench with 200 millimeter diameter holes or a single 6 meter bench with 140 millimeter diameter holes, depending on the size and continuity of the ore blocks outlined by grade control drilling.

Support equipment will be used for road, bench, and dump maintenance and miscellaneous projects.

Planned Process Operations

The Donlin Gold project ore will be processed by crushing and grinding, sulfide flotation concentration, autoclave pressure oxidation (POX), carbon-in-leach (CIL) cyanide leaching, electrowinning, and refining to produce doré bars on site.

Due to gold being associated with sulfide mineralization, primarily arsenopyrite and pyrite, the ore is considered refractory and requires POX pre-treatment to liberate the gold prior to CIL leaching. Sulfide flotation concentration is required prior to POX to concentrate the sulfide content to a level sufficient to fuel the POX operation.

Concentrate is recovered from the primary rougher flotation followed by regrinding of the tailings prior to secondary rougher flotation. The secondary rougher concentrate is processed through a cleaner-cleaner scavenger circuit producing a concentrate which is combined with the primary rougher concentrate for treatment by POX. The final tailings from the secondary rougher-flotation tailings is thickened, and due to their neutralizing potential, is then utilized to modify the pH of the POX discharge solution prior to being transported to the TSF.

The oxidized concentrate from the POX operation would then be cyanide leached in a conventional CIL circuit to produce a pregnant (gold-bearing) solution. Gold from the solution is adsorbed onto activated carbon, which is later stripped (gold desorbed from carbon) in an elution circuit. The pregnant solution after elution is fed through electrowinning (EW) cells, where cathodes are plated with gold-bearing materials, which are periodically removed, dried in retort, and melted in an induction furnace to produce doré bars.

Tailings from the CIL circuit would be treated in a cyanide detoxification process using SO2/air technology prior to being transported to the TSF.

Mercury naturally occurs in the Donlin Gold project ores and mercury abatement controls will be installed in six areas of the process facilities including POX, hot cure, EW, retort, refinery furnace, and carbon regeneration kiln. In these control systems, mercury will be collected for off-site shipment and management. Chemicals will be added to tailings to limit the potential for mercury releases from the TSF.

Proposed Production Plan and Schedule

Based on the Donlin Gold FS, the operating mine life is estimated to be 27 years with the nominal processing rate of 53,500 tonnes per day. Mine start-up was proposed to begin in 2020 based on a timeline of 3-4 years for project permitting and concurrent engineering and 3.5 to 4 years for construction. The Donlin Gold FS also assumed that project engineering would proceed in parallel with project permitting. In addition, the Donlin Gold board must approve a construction program and budget before construction of the Donlin Gold project can begin. The timing of the initiation of the required engineering work, of the Donlin Gold board’s approval of a construction program and budget, and receipt of all required governmental permits and approvals will determine whether and when construction of the Donlin Gold Project will begin.

Preproduction covers the first 15 months of the mine plan, when mining activities will focus on providing sufficient ore exposure for plant start-up. Ore mined during preproduction will be stockpiled and rehandled to the mill during operations. Average mine production increases progressively in the initial years from 350,000 to 417,000 tonnes per day. The peak rate of 437,000 tonnes per day is reached in Year 6.

Waste Rock Facility

Waste rock from open pit mining will be placed in an ex-pit waste rock facility in the American Creek Valley, east of the pit area, or in a backfill dump in the ACMA pit. The ultimate footprint of the facility covers an area of approximately 9 square kilometers. Approximately 2,232 million tonnes of waste rock and overburden will be placed in the facility, and 423 million tonnes will be placed in the ACMA pit backfill dump. Approximately 103 million tonnes of waste rock will be used for construction purposes, and 17 million tonnes of overburden will be stockpiled and used later for reclamation purposes.

The potential magnitude of flow in the American Creek drainage, as well as discharge from springs in the valley floors, warrants the construction of an engineered rock drain system below the waste rock facility, including connecting secondary rock (finger) drains in the smaller contributing drainages.

Waste rock will be characterized by its potential for acid generation and assigned reactivity categories. Non-acid-generating (NAG) rock will be placed directly in the waste rock facility, along with less reactive potentially acid-generating (PAG) rock, PAG5. Some of the more reactive PAG rock, PAG6, will be encapsulated in cells in the waste rock facility to prevent water infiltration through them. The most reactive PAG rock, PAG7, will be placed in the ACMA backfill dump beneath the ultimate pit lake water level.

Concurrent reclamation of the waste rock facility will be undertaken during operations.

Proposed Tailings Storage

The TSF in the Anaconda Creek basin will be a fully lined impoundment with cross valley dams at both the upstream (“upper dam” comprising upper north and upper south) and downstream (“main dam”) ends.

All tailings dams will be constructed of compacted rock fill using the downstream method with a composite liner on the upstream face. The tailings impoundment footprint will be lined with a linear low density polyethylene liner over a layer of broadly graded silty sand and gravel acting as low permeability bedding material and providing secondary containment. Material for construction will be sourced from the plant site and fuel farm during initial construction and from the open pit for the later raises during operations.

Other Dams

Water dams are required during the construction period and initial years of operation to protect the lined upstream faces of the upper north and south tailings starter dams from a significant flood event, to provide a reliable source of fresh water during operation of the process plant, and to minimize runoff to the TSF.

Current and Planned Infrastructure

Current site infrastructure comprises an all-season, soft-sided camp with facilities to house up to 150 people consisting of kitchen, living quarters, equipment shop, drill shack and other buildings required for support of year-round exploration activities.

There is sufficient area within the project area to host an open-pit mining operation, including the proposed open pit, waste rock facility, TSF and process facilities. Other planned site infrastructure comprises: access roads, airstrip, accommodation camp, plant site and fuel tank farm, primary and pebble crushers, coarse ore conveyor and coarse ore stockpile, concentrator, water treatment plants, dual-fired power plant, oxygen plant, boiler house, utility corridors and access walkways, waste and tailings storage facilities, truck shop, truck wash, workshops and vehicle repair facilities, assay laboratory, administration facilities and change rooms. Donlin Gold has secured the majority of the surface rights for the areas that may host these facilities.

In the nearby villages, Crooked Creek has approximately 140 residents and Aniak has a population of approximately 570. The workforce for the project would be sourced from the local area, from Alaskan regional centers and from other sources as required.

The project is a greenfield site. The on-site infrastructure for the project includes three main development sites in remote locations: the mine and plant site area (including the power plant), the permanent camp, and the airstrip. The plant site, power plant and fuel tank farm will be on a ridge above the proposed TSF. The layout of the plant site was designed to take maximum advantage of the natural topography. The layout also provides for efficient movement of equipment and material products around the site.

Planned Off-site Infrastructure

The off-site infrastructure for the project includes three main development sites in remote locations: the Jungjuk Port site and mine access road; the natural gas pipeline; and the Bethel port facilities. The Jungjuk Port site is situated on the Kuskokwim River near the mouth of Jungjuk Creek. A port-to-mine access road (Jungjuk Road) , approximately 44 kilometers long, will traverse varied terrain from the Jungjuk Port site to the mine site. A 4.8 kilometer long spur road will serve the project airstrip. The primary purpose of the road is to transport freight from the Jungjuk Port site to the mine mostly by conventional highway tractors and trailers. The natural gas pipeline is described under the Power heading below. The Bethel Port will be situated near the town of Bethel, a community of approximately 6,400 residents, that is the main port on the Kuskokwim River and is an administrative and transportation hub for the 56 villages in the Yukon-Kuskokwim Delta. The Port of Bethel is the northernmost medium-draft port in the United States and is served by ocean-going barges. The proposed port would serve as a trans-shipment point from ocean barges to river barges to supply the project during the summer.

Power

Natural gas will be delivered to site by an approximately 500-kilometer long 14-inch (356 millimeter) diameter pipeline to supply an on-site power generation facility. The Donlin Gold FS contemplates that the electric power for the site will be generated from a dual-fuelled, (natural gas and diesel) reciprocating engine power plant with a steam turbine utilizing waste heat recovery from the engines. The power plant consists of two equal halves, each consisting of six reciprocating engines, and a separate steam turbine. The total generation facility is nominally rated at 182 MW initially. This will increase to 215 MW after four years with the addition of two more gensets (one in each half) to allow for N+2 redundancy, thus permitting planned maintenance and predicted outages without cutting back production. Project optimization studies and detailed engineering may result in selection of a different power plant design based on capital and operating costs and operating efficiency considerations.

The natural gas pipeline is a lower-cost alternative to the previously considered barging of diesel fuel to site to generate electricity. The Donlin Gold FS operating costs are based on importing liquefied natural gas (LNG) by ship to Anchorage and total delivery costs to site which includes ship based regasification of the LNG and delivery from Anchorage to the Donlin Gold project via the pipeline.

The pipeline would commence at the west end of the Beluga Gas Field, approximately 48 kilometers northwest of Anchorage at a tie-in near Beluga located in the Matanuska-Susitna Borough and would run to the mine site. The pipeline would receive booster compression supplied by one compressor station located at approximately mile post 5. No additional compression along the pipeline route would be required. The pipeline would have capacity to transport approximately 2 million cubic meters per day of natural gas.

Water

Water requirements for the proposed project have been summarized in a draft Water Resources Management Plan, which is subject to review by State and Federal agencies. Water primarily will be sourced from the two drainages (American and Anaconda Creeks) within the mine footprint and pit dewatering. In some years, the water supply from these sources may not be able to meet the makeup water requirements for the plant. In these circumstances, additional water will be obtained primarily from a reservoir in Snow Gulch.

The source of water supply for the construction camp and, later, the plant site potable water systems is an array of eight deep wells south of Omega Gulch, near Crooked Creek. Water supply will be pumped to freshwater storage tanks, and will be treated prior to consumption.

Markets

The marketing plan is for the owners of Donlin Gold to take in kind their respective shares of the gold production, which they can then sell for their own benefit. Under the LLC Agreement, the manager shall give the members prompt notice in advance of the delivery date upon which their respective shares of gold production will be available.

Since there are a large number of available gold purchasers, the members should not be dependent upon the sale of gold to any one customer. Gold can be sold to various gold bullion dealers or smelters on a competitive basis at spot prices.

It is expected that selling contracts for our share of the gold production will be typical of, and consistent with, standard industry practice, and be similar to contracts for the supply of doré elsewhere in the world.

Taxation

Taxes that may be levied on the project can be summarized as follows:

  • Federal Income Tax – the greater of the U.S. Regular Tax of 35% or Alternative Minimum Tax of 20%.
  • Alaska State Income Tax – 9.4% of net income or Alternative Minimum Tax of 18% of Federal Alternative Minimum Tax.
  • Alaska State Mining License Tax – 7% of taxable mining income, less depletion. There is a 3.5-year tax holiday on the mining license tax.

Income tax becomes payable after deductions for capital allowances.

Financial Analysis

The total capital cost estimate for the Donlin Gold project is $6.7 billion including costs related to the natural gas pipeline and a contingency of $984 million. The project’s estimated after-tax net present value (NPV5%) is $547 million using the base case gold price of $1,200 per ounce, $4.58 billion using a gold price of $1,700 per ounce and $6.72 billion using a gold price of $2,000 per ounce. The corresponding IRR after-tax were estimated at 6.0%, 12.3% and 15.1%, respectively. The break-even gold price is $902 per ounce. In the Donlin Gold FS, the overall economic viability of the project was evaluated by both discounted and undiscounted cash flow analyses, based on the engineering studies and cost estimates discussed in this study. Assumptions in the model comprised:

  • For discounted cash flow (or NPV) purposes, the model is based from January 1, 2014. Estimates were prepared for all the individual elements of cash revenue and cash expenditures for ongoing operations.
  • Estimated cash flows from revenue are based on a gold price of $1,200 per ounce as provided by Donlin Gold. The pit has been optimized at a gold price of $975 per ounce, which was the guidance in effect at the time the pit optimization work was completed. At the effective date of the Donlin Gold FS, gold was trading at around $1,650 per ounce.
  • Gold recovery is estimated to average 89.8% over the LOM based on work and testing performed for feasibility study and feasibility study update purposes.
  • Doré refining and shipping charges were estimated at $1.02 per ounce based on actual refining charges for Barrick’s Goldstrike operations and a quotation for transportation and insurance costs from the Donlin Gold project site to a U.S.-based refinery. An additional 0.1% of gold produced from the mine is included in refining costs. This amount represents the refiner’s estimate of the loss of gold that will occur during the refining process.
  • The current hydrometallurgical process selection renders any contained silver into a greater refractory state, which provides less than 10% silver recovery through standard metal leaching. As a consequence, no silver credit was applied to the project.
  • Assets will be sold over the course of the mine life, when they are no longer required for project-based work, as well as at the end of the mine life. Total recovered value from these sales is estimated at approximately $23.0 million.
  • Reclamation and closure costs were estimated at $273.7 million to be funded over the construction and operating period to fund closure and post-closure activities.
  • Inventory is included in the financial model as cash outflows in the year before start-up of operations.

Current Activities

On December 14, 2012, the Notice of Intent for the EIS was published in the Federal Register by the Corps, which initiated the public scoping process. In the first quarter of 2013, public scoping meetings were held in villages and communities in Western Alaska and Anchorage to help identify the questions and concerns that should be addressed in the EIS. On March 29, 2013, the public scoping period ended and in May 2013, URS issued a draft scoping summary document for Cooperating Agency review. During the second quarter of 2013, Donlin Gold delivered the EED to the Corps that provides detailed information on the baseline studies and analyses that have been completed for the proposed project. The EED also describes the detailed project options that Donlin Gold considered in the development of the proposed project design. This is being used by URS and the Cooperating Agencies to support ongoing alternatives development for the EIS. In March 2013, URS issued a preliminary review of the available baseline data identifying the additional environmental, social, and cultural resource data to be compiled for the EIS. During the remainder of 2013, Donlin Gold worked to address the remaining data needs for the EIS. Throughout 2013, Donlin Gold also continued to provide application materials and maintained ongoing dialogue with the agencies that will issue the key permits and authorizations needed for the Donlin Gold project, including the air quality, water discharge, dam safety, wetlands, water use, fish habitat, and pipeline permits. Donlin Gold completed all required field work as planned.

Our share of funding for Donlin Gold in 2013 was $12.2 million for permitting, community engagement and development efforts. Donlin Gold has approved a 2014 work program of approximately $24 million, of which our 50% share is approximately $12 million. The 2014 work program and budget includes funds to continue to advance the permitting process through completion of the PDEIS in late 2014, and receipt of comments from the Federal and State agencies on the PDEIS in preparation for issuance of the draft EIS in 2015. In addition, Donlin Gold will continue to maintain its engagement with communities in the Yukon-Kuskokwim region.

An extensive list of additional federal and state government permits and approvals must be obtained before the Donlin Gold project can commence construction. Preparation of the applications for many of these permits and approvals requires additional, more detailed engineering that were not part of the Donlin Gold FS. Completion of this engineering will require a significant investment of funds, time, and other resources by Donlin Gold and its contractors. Also, the Donlin Gold board must approve a construction program and budget before construction of the Donlin Gold project can begin. The timing of the required engineering work, of the Donlin Gold board’s approval of a construction program and budget, as well as the receipt of all required governmental permits and approvals will determine whether and when construction of the Donlin Gold project will begin. Project delays also could occur as a result of public opposition, limitations in regulatory staff resources during regulatory review, or project changes made by Donlin Gold.

Galore Creek Project, British Columbia

Galore Creek Partnership

The Galore Creek project is a large copper-gold-silver project located in northwestern British Columbia, held by a partnership in which our wholly-owned subsidiary, NOVAGOLD Canada Inc., and Teck Metals Ltd. each own a 50% interest and is managed by GCMC. The Galore Creek property, as per the PFS, comprises 293,837 acres (118,912 hectares) and hosts a large, porphyry-related copper-gold-silver deposit. Funding is currently shared by both parties on a 50/50 basis.

On November 16, 2011, we announced that it we were evaluating opportunities to sell all or part of our 50% interest in the Galore Creek project. As of November 30, 2013, we had not received an offer for our 50% interest in the Galore Creek project.

Partnership History

On August 1, 2007, we entered into the Galore Creek Partnership Agreement with Teck (as amended on November 25, 2007 and on July 28, 2008, the “Partnership Agreement”) which formed the Galore Creek Partnership giving each of us a 50% interest in the Galore Creek project. The activities of the Galore Creek Partnership are being conducted by GCMC, an independent entity controlled equally by us and Teck, pursuant to the terms of the Partnership Agreement.

Under the Partnership Agreement, we contributed our assets in the Galore Creek project to the Galore Creek Partnership and Teck agreed to fund an initial contribution after which both partners would be equally responsible to fund the project going forward. In addition, under the terms of the Partnership Agreement, we would receive up to $50 million of preferential distributions once Galore Creek was fully operational, if partnership revenues exceeded certain established targets in the first year of commercial production.

On November 26, 2007, we announced that NOVAGOLD and Teck had reached the decision to suspend construction activities at the Galore Creek project. In light of these developments, we agreed with Teck to amend the terms of Teck’s earn-in obligations in connection with the Galore Creek project. Under the amended arrangements, Teck’s total earn-in was approximately C$403 million and we were to receive up to $25 million of preferential distributions once Galore Creek became fully operational, if Partnership revenues exceeded certain established targets in the first year of commercial production. Teck’s sole funding of project costs incurred after August 1, 2007 was to total C$264 million, and Teck agreed to invest an additional C$72 million in the Galore Creek Partnership to be used over the next five years, principally to reassess the project and evaluate alternative development strategies. NOVAGOLD and Teck were to fund the next C$100 million of project costs one-third and two-thirds respectively, and would fund costs proportionately thereafter.

On February 11, 2009, we agreed with Teck to further amend certain provisions of the Partnership Agreement relating to the Galore Creek project. The amendment confirmed that NOVAGOLD and Teck each continue to hold a 50% interest in the Galore Creek Partnership. Under the amended agreement, Teck agreed to fund 100% of Galore Creek project costs until the total amount contributed by Teck after November 1, 2008, together with approximately C$16 million previously contributed by Teck on optimization studies, equaled C$60 million. Teck would have a casting vote on the Galore Creek Partnership’s Management Committee with respect to the timing and nature of expenses to be solely funded by it. Following Teck’s C$60 million contribution, all further costs at the Galore Creek project would be funded by Teck and us in accordance with our respective Galore Creek Partnership interests and there would no longer be any casting vote for either party. The new funding arrangements replaced the funding arrangements agreed to by Teck and us in November 2007. Teck was the sole funding partner until June 22, 2011 when it completed its C$373 million earn-in obligation. Since that date, we have funded and will continue to fund Galore Creek project expenditures equally.

Except for the information under the headings “Galore Creek – Current Activities”, “Galore Creek – Project History, Drilling and Exploration, 2012 Program and 2013 Program” and “Galore Creek – Mineral Tenure”, or for information related to Copper Canyon or as otherwise stated or implied, the scientific and technical information regarding the Galore Creek project in this Annual Report on Form 10-K is based on the PFS.

Property Description and Location

The Galore Creek property is a large copper-gold-silver project located in northwestern British Columbia. The main Galore Creek property, which consists of the Southwest, Central, Junction and West Fork deposits, contains most of the project’s known resources. Under an option agreement originally with subsidiaries of Rio Tinto plc and Anglo American plc, the then shareholders of Stikine Copper Limited, the owner of the core mineral claims at the Galore Creek project, we could acquire 100% of such company. On June 1, 2007, we completed the exercise of our option pursuant to the Galore Creek Option Agreement to purchase 100% of Stikine Copper Limited by paying the final C$12.5 million of a C$20.3 million purchase price. Our financial earn-in requirements under the Galore Creek Option Agreement were satisfied and all of Stikine Copper’s assets were purchased by us and have been transferred to the Galore Creek Partnership.

The Partnership has a royalty agreement entitling the counterparty to a maximum annual net smelter royalty of 0.5% to 1.0%. The royalty is subject to positive future operating mine cash flow and is contingent upon reaching certain agreed financial targets.

Mineral Tenure

On May 23, 2007, we announced with Teck a 50/50 partnership to develop the Galore Creek project. On August 1, 2007 the Galore Creek Partnership was established to develop the Galore Creek project and GCMC, a jointly controlled operating company, was created. In October 2007, all Galore Creek claims held by our wholly-owned subsidiary, NOVAGOLD Canada Inc., were transferred to GCMC. GCMC currently holds 151,953 hectares (375,476 acres) of British Columbia provincial mineral claims in 344 tenures (the acquisition of additional acres since the issuance of the PFS has no material impact on reserves or resources stated in the PFS). Included in this total are the five Grace claims that were acquired by GCMC from Pioneer Metals Corporation on December 3, 2007. To date, BCLS legal surveys have been recorded on five Galore Creek mineral claims (516158, 516165, 516459, 516177, 516335) and on four Bob Quinn area claims (514548, 514551, 545723, 566898). The adjoining Copper Canyon property is owned by the Copper Canyon Partnership which is owned by two wholly-owned subsidiaries of NOVAGOLD, and is comprised of 12 claims totaling 11,344 hectares (28,032 acres).

Accessibility and Climate

The Galore Creek project is located approximately 70 kilometers west of the Bob Quinn airstrip on Highway 37 and 150 kilometers northeast of the port of Stewart, and 370 kilometers northwest of the town of Smithers, British Columbia, Canada. The town of Smithers is the nearest major supply center and has an airport with regularly scheduled flights to and from Vancouver, British Columbia. The project is located in the Stikine area. The nearest point on the Stikine River to the project is the mouth of the Anuk River, about 16 kilometers west of the camp. Most personnel, supplies, and equipment are staged from the Bob Quinn airstrip, on the Stewart-Cassiar Highway (Highway 37) and transported via helicopter to the Galore Creek camp. The Bob Quinn airstrip is serviced by contract flights from Smithers and Terrace, each of which has daily flights from Vancouver. Flight time from Vancouver to Smithers/Terrace is about 90 minutes, then an additional 45 minutes to Bob Quinn. The helicopter flight from Bob Quinn to the Galore Creek camp is about 30 minutes.

The Galore Creek project is located in the humid continental climate zone of coastal British Columbia and is characterized by cold winters and short, cool, summers. Within the Galore Creek valley, mean monthly temperatures range from 8.2ºC during the winter to 12.4ºC during the summer, with January and July typically being the coolest and warmest months, respectively. In the Upper West More Valley area, monthly average temperatures range from -8.9ºC in the winter to 7.9ºC in the summer. Precipitation begins to fall as snow in early October and continues until the end of May. The average precipitation for the whole Galore Creek valley watershed was estimated to be in the order of 3,000 millimeters. June and July tend to receive the least amount of precipitation on an annual basis (typically 40 to 60 millimeters of rain per month).

The project lies within a regional structure known as the Stikine Arch. Medium to steep slopes characterize the local terrain in the central and northern parts of the Galore Creek property. The surrounding topography is mountainous. The elevation of the tree line is variable, but alpine vegetation predominates above 1,100 meters. The forests below that elevation consist of Balsam fir, Sitka spruce and cedar. Alpine tundra is present at higher elevations.

The Galore Creek project is currently isolated from power and other public infrastructure and is currently not accessible by road. Because of glaciers covering the surrounding mountain passes, a large cross-section tunnel is needed to provide long-term vehicular access into the Galore Creek valley and for mobilization of individual component pieces of large mining equipment needed for mining the ore body using open pit methods. The time and cost for driving a tunnel in new and unexplored underground terrain is subject to many unknowns which could change the outcome significantly. The same surface constraints that preclude building a road into the site (i.e. severe topography, snowpack, glaciers and weather) also limit the amount of borehole information, geologic mapping and other site specific data that can be obtained so that subsurface conditions can be better understood before tunneling begins. Construction of the tunnel will most likely fall on the critical path for development of the mine and thus represents a significant cost and schedule risk for development of the Galore Creek project.

Within the land controlled by GCMC, there is sufficient area to allow for the construction of all project infrastructures as contemplated in the PFS. Except for the access corridor which is covered by the special use permit, all other infrastructure, including the processing plant and tailings area in West More and the Filter Plant Area near Kilometer 8 are located within GCMC’s mineral claims. GCMC intends to file for mining leases to secure the surface rights for these areas, which are held by the Crown. GCMC considers it a reasonable expectation that surface use rights will be granted to the project. Ample water supply is available from surface and subsurface sources.

Geological Setting

The main Galore Creek deposits lie in Stikinia, an accreted terrain composed of tectonically juxtaposed Mesozoic volcano-stratigraphic successions. The eastern boundary of the Coast Plutonic Complex lies about 7 kilometers west of the claim block. A suite of multiphase syenite intrusions cuts a section of flysch-basin sedimentary strata and alkaline volcanic rocks of the middle to upper Triassic Stuhini Group. The intrusive suite, centered in the West Fork area, forms a north-northeast-trending belt 5 kilometers long and 2 kilometers wide and contains stocks, dikes and extensive sills. The presence of numerous sub-volcanic syenite sills indicates that the intrusions formed at a structurally high level. The spatial and temporal association of the chemically similar intrusive and extrusive igneous rocks indicates that the Galore Creek area is probably an eroded volcanic center. The Galore Creek intrusions commonly follow two orientations, one northwest and the other northeast. Post-intrusion and post-ore faulting follows these same orientations. Regionally, the Stuhini section shows broad open folding. The mineralized section is less deformed, so it is unclear whether the deformation occurred prior to, during, or subsequent to mineralization.

Copper Canyon, a satellite copper-gold resource located 6 kilometers east of the Central Zone, shares a number of geological and geochemical similarities with the main deposits, including the occurrence of identical dike-rock types, a similar sulfide suite and occurrence within the same host volcano-stratigraphic succession. Regional stratigraphic relationships suggest that Copper Canyon represents a different volcanic edifice that is of the same age or date of origin as the Galore Creek deposits.

Mineralization

Mineralization at the Galore Creek project occurs primarily in altered Triassic alkalic lavas, volcano-sedimentary strata and, to a lesser degree, in alkalic intrusions. Twelve copper-gold-silver mineralized zones have been identified on the property. Alteration mineral assemblages at the Galore Creek project are somewhat unique due to the near total lack of quartz in the volcanic and intrusive host rocks. In general, the center of the district shows potassic alteration, including potassium-feldspar, biotite and magnetite, with local concentrations of garnet. Copper-sulfides are most closely associated with secondary biotite and magnetite. A propylitic assemblage, including epidote, chlorite and pyrite occurs outboard of the potassic assemblage.

Most of the mineralized zones contain evenly disseminated copper-sulfide with little apparent control by stockwork or larger scale veining. The sulfide assemblage generally includes chalcopyrite, bornite and pyrite. Uncertainty exists whether the pyrite is auriferous, but strong magnetite commonly occurs within gold-enriched zones. Higher gold values occur at the northern and southern ends of the Central deposit. These higher gold values generally occur along with elevated concentrations of bornite. Locally, as in the West Fork area, massive magnetite-bornite-chalcopyrite mineralization contains bonanza grades (>20% copper with significant precious metal values).

Mineralization at Copper Canyon occurs primarily in a sub-volcanic syenite intrusive complex. This host lithology defines the primary difference from the main Galore Creek deposits. Chalcopyrite forms the primary sulfide mineralogy; bornite is rare. As at the Galore Creek project, mineralization is evenly disseminated and shows no apparent association with veining. The periphery of known mineralization contains elevated gold/copper ratios along with relatively higher concentrations of pyrite. Copper mineralization appears to occur as an annular zone around a barren fluorine-rich diatreme breccia.

Metallurgy

The sulfide minerals at the Galore Creek project are predominately gold- and silver-bearing chalcopyrite, bornite and pyrite. A primary grind of 80% passing 200 microns provides sufficient rougher flotation liberation to separate the copper minerals from the pyrite and gangue. At this grind, the majority of the gold is either free or associated with the copper sulfides. The proposed treatment process uses conventional flotation to produce a precious-metal-bearing copper concentrate.

Project History, Drilling and Exploration

Drilling History

Since initial discovery of the Galore Creek property in 1960 through 2013, approximately 311,181 meters were drilled in 1,212 core holes on the property. Most of this work has focused on the Central zone, with lesser amounts of work on eleven other target areas. Some zones have received only reconnaissance drilling. During the 1970s, drilling was principally confined to the Central zone but nine holes were also drilled on the North Junction zone. Average core recovery in the Central zone was between 75 and 85% with the poorest recovery at depths between 60 and 90 meters where abundant open sheet fractures were encountered. At depths below 90 meters core recovery approached 100%. In the North Junction zone recovery averaged around 60% due to shattered and sheared sections encountered both near surface and at intervals throughout the holes. In 1989–1990, Mingold, an Anglo American subsidiary, drilled holes on the Southwest zone (eight holes, 1,026 meters), the North Rim showing (six holes, 546 meters), the Saddle zone (two holes, 226 meters) and two reconnaissance holes. The 1991 drill program was mainly directed at areas peripheral to the Central zone as well as exploration holes located in the Southwest, Butte, North Rim and Dry Creek zones. Only six holes were drilled within the Central zone itself.

The first drill program directed by us began in September 2003, and consisted of eight core holes targeting four broad areas of the deposit: the North Gold zone, South Gold zone, Central Replacement zone and Southwest zone. Drilling was focused on understanding the zonation and gold variability of the deposit. This program was responsible for the discovery of new mineralization, known as the Bountiful zone, found at depth below the South Gold Lens.

2006 Program

The 2006 drill program focused primarily on further definition of the deep Bountiful mineralization discovered in 2003, further resource definition along the western margin of the Central deposit and completion of condemnation drilling on the Grace claims in the planned tailings disposal site. The program drilled in excess of 36,200 meters in 67 drill holes and encountered significant new mineralization in Bountiful, in the high-wall of the Central deposit and down dip in the West Fork deposit. Additional geotechnical drilling in support of mine development was also completed.

Wide-spaced drilling in Bountiful defined a sub-horizontal zone occurring at roughly 300 meters depth and extending nearly 1,000 meters in the north-south direction and 700 meters in the east-west direction. Drilling indicates that typical widths in Bountiful are greater than 200 meters on average and up to 500 meters in a few exceptional intervals. Drilling at depth in the high-wall of the Central zone extended mineralization from the North Gold lens approximately 250 meters to the west. Additional drilling in the Dendritic Creek area about 750 meters south of the North Gold lens shows limited mineralization to the west and likely the limited loss of some previously inferred mineralization. Drilling down dip along the north-dipping West Fork deposit continued to expand mineralization to depth and toward the Bountiful and Southwest deposits.

2007 Program

The 2007 drilling program at the Galore Creek project completed 15,000 meters of follow-up and exploration drilling. Targets concentrated on optimization of the mine schedule by targeting shallow moderate-grade resources that could displace low-grade stockpile material in years seven to nine of operations. Additional exploration focused on scoping potentially high-grade underground scenarios that could increase the value of the project.

Drilling was carried out at three primary locations: Copper Canyon, the Grace Claims and the Lower Butte zone. Drilling at the Lower Butte zone suggests potential for resource additions. At the Copper Canyon deposit, drilling focused on testing up-slope historical soil anomalies, testing higher-grade targets discovered in 2006 and expanding on depth and lateral extensions of the current resource. As a result of the drilling at Copper Canyon, NOVAGOLD earned a 60% interest in the neighbouring project. Significant additional drilling was completed to test the geotechnical characteristics of planned pit slopes, waste and tailings storage and water diversion facilities.

2008 Program

The 2008 diamond drilling program at the Galore Creek project was carried out between June 25, 2008 and September 17, 2008. The program consisted of nine diamond drill holes totaling 2,050 meters. The main objectives of the program were to obtain important acid base accounting (ABA) data in the Central, Southwest, North Junction and Junction pits, to confirm legacy grades in the Junction pit, and to collect metallurgical data in the Central pit for engineering design. Seven drill holes totaling 1,297 meters targeted gaps in the ABA model, specifically along the pit boundaries of the Central (South Gold Lens), Southwest and North Junction pits and within the core of the Junction pit. Two drill holes totaling 752 meters were drilled for the purpose of collecting metallurgical data in the chalcopyrite-rich Central Replacement zone and the chalcopyrite-bornite-rich North Gold Lens.

2009 Program

There was no exploration program during 2009.

2010 Program

There were 9 drill holes, totaling 2,803 meters drilled into the Central zone during 2010 for resource infill and metallurgical testing purposes.

2011 Program

The 2011 drilling program included 10,000 meters of resource infill drilling to confirm previous results as well as to test the potential for upgrading and possible extensions of mineralization within the South Gold Lens and Bountiful areas of the Central pit.

2012 Program

The 2012 drilling program totaled 27,900 meters of resource infill and exploration drilling. The objective of the infill drilling was to increase resources and upgrade material in all categories. The exploration drilling resulted in the discovery of the Legacy zone adjacent to the Central reserve pit.

2013 Program

The 2013 drilling program totalled 11,649 meters of resource in-fill and exploration drilling, 9,157-meters of which targeted the Legacy zone. An additional 2,492 meters of exploration drilling was conducted to better understand geological features that could influence the mineralization in Legacy, identify mineralization trends, and explore possible extensions of known mineralized zones adjacent to Legacy. Sufficient drilling was carried out in 2012 and 2013 to support preparation of a new resource estimate. The 2013 program also demonstrated that the copper mineralization may extend beyond the initial Legacy discovery in the direction of the Bountiful mineralization. The mineralization remains open to the south, west, and at depth.

The Galore Creek project is host to seven under-explored copper-gold-silver prospects, five defined mineral resource areas, and numerous showings and conceptual target areas.

Sampling and Assaying

Historically from 1963 to 1991, drill core in mineralized zones was generally sampled in 3-meter intervals. The samples were tagged then split in half using a mechanical splitter. One half of the core was returned to the core box and the other half shipped to an outside laboratory for analysis. The core returned to the boxes remains on site as a record of the hole. Much of the core from the Central Zone was re-assayed as part of the 1991 exploration program. No site-specific standards, blanks or field duplicate samples were used in any of the previous exploration programs.

Sampling and assaying procedures used by us have been overseen by qualified professional geologists. All drill core from the 2003 through 2010 programs, except intervals of overburden and till material, were sampled. Drill core sampling occurred within a minimum of 1-meter and a maximum of 3-meter intervals. The core was cut in half using a diamond saw. Half of the core was taken as a sample and submitted to ALS Chemex Labs in Vancouver, British Columbia. The core that was returned to the box remains on site as a record of the hole. In addition to the core, control samples were inserted into the shipments at the approximate rate of one standard, one blank and one duplicate per 20 core samples. The placement of all control samples was essentially random within the 20-sample batch.

Assay analysis for the 2003 through 2007 programs was carried out by ALS Chemex Labs of Vancouver, British Columbia. Samples were logged into a tracking system on arrival at ALS Chemex, and weighed. Samples were then crushed, dried, and a 250 g split pulverized to greater than 85% passing 75 microns. Gold assays were determined using fire analysis followed by an AAS finish. The lower detection limit was 0.005 ppm Au; the upper limit was 1,000 ppm Au. An additional 34-element suite was assayed by ICP_AES methodology, following nitric acid aqua regia digestion. The copper analyses were completed by atomic absorption, following a triple acid digest. Sampling and assaying during the drilling from 2007 through 2013 used the same protocols as described above.

Construction

On June 5, 2007, we announced that we had received the necessary federal and provincial authorizations and permits to allow our Directors to approve the start of construction at the Galore Creek project. The Directors’ approval for construction activities was contingent on receiving full provincial and federal authorization for the project. Federal authorization was posted to the Canadian Environmental Assessment Registry on June 4, 2007.

On July 31, 2007, the provincial government announced the issuance of a Mines Act permit for the Galore Creek project for construction of the access tunnel. An interim permit issued on July 4, 2007 authorized limited blasting to prepare and stabilize the rock face of the tunnel, as well as preparatory work for the sediment ponds. Receipt of the new permit authorized completion of the access road and tunnel and authorized the start of earthworks in the Galore Creek valley.

Construction Suspension

On November 26, 2007, we announced that NOVAGOLD and Teck had reached the decision to suspend construction activities at the Galore Creek project. A review and completion of the first season of construction indicated substantially higher capital costs and a longer construction schedule for the project. This, combined with reduced operating margins as a result of the stronger Canadian dollar, would make the project, as conceived and permitted, uneconomic at what was considered then to be industry consensus long-term metal prices. NOVAGOLD and Teck continue to view the Galore Creek project as a substantial resource and are working to identify an alternative development strategy that may allow for the resumption of construction.

Prior to the suspension of construction, substantial work was completed at the Galore Creek project, including clearing 80% of the 135-kilometer road right-of-way, completing 66 kilometers of pioneer road, installing a number of key bridges and initiating work on the road access tunnel into the Galore Creek valley. During the construction suspension and optimization period, the partners have maintained and intend to continue to maintain the existing infrastructure.

While permits granted for the original project design remain in place, any alternative project design will require new or additional permits before construction can resume.

Pre-Feasibility Study

During 2010, GCMC had reviewed a number of optimization scenarios for the Galore Creek project with the objective of expanding throughput, relocating the project facilities to allow for easier construction and future expansion, and reducing the risks associated with construction and operations. Based on these studies, GCMC identified a preferred project design and commenced work on the PFS.

Primary changes to the project included:

  • Relocation of the tailings facility allowing for construction of a conventional tailings dam;
  • Relocation of the processing facilities allowing for future expansion;
  • Realignment of the tunnel and access road; and
  • Increase of daily throughput to approximately 90,000 tonnes per day.

Project plans envision the ore being crushed in the Galore Creek valley and then conveyed through the tunnel and along the access road to the processing plant. From there, concentrate would be piped along the remainder of the access road to Hwy 37. A trade off study will identify the best alternative for transport of concentrate to market. The project would primarily use electric power, with a power line built along the access road to tie into the 287-kV transmission line, that the British Columbia and Canadian governments have announced their intention to build. Some components of the revised Galore Creek mine plan, such as the mill and tailings location, would require new permits or amendments to existing permits. The majority of permits required for road construction remain in good standing. GCMC could continue with road and bridge work as the project moves through the feasibility stage, with the objective of shortening the construction timeline and reducing the need for helicopter support.

On July 27, 2011, we announced the results of the PFS for the Galore Creek project. The PFS estimates the Galore Creek project has proven and probable mineral reserves of 528 million tonnes grading 0.59% copper, 0.32 grams per tonne gold and 6.02 grams per tonne silver for estimated contained metal of 6.8 billion pounds of copper, 5.45 million ounces of gold and 102.1 million ounces of silver. In addition, the Galore Creek project has estimated measured and indicated mineral resources (exclusive of mineral reserves) of 286.7 million tonnes grading 0.33% copper, 0.27 grams per tonne gold and 3.64 grams/tonne silver for estimated contained metal of 2.07 billion pounds of copper, 2.53 million ounces of gold and 33.54 million ounces of silver, and estimated inferred mineral resources of 346.6 million tonnes grading 0.42% copper, 0.24 grams per tonne gold and 4.28 grams per tonne silver for estimated contained metal of 3.23 billion pounds of copper, 2.70 million ounces of gold and 47.73 million ounces of silver. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The PFS total capital cost estimate for the Galore Creek project was C$5.2 billion dollars. Capital costs are estimated with an accuracy range of +25% / -20% (including contingency). The project’s estimated net present value (NPV7%), using the PFS base case metal price assumptions set forth below, was assessed at C$837 million and C$137 million on a pre-tax and post-tax basis, respectively. The corresponding post-tax IRR of the project was estimated at 7.4%. Base case metal prices used in the PFS were $2.65 per pound copper, $1,100 per ounce gold and $18.50 per ounce silver with a foreign exchange rate of $0.91 = C$1.00.

Mining of the Galore Creek deposit is planned as a conventional truck-shovel open-pit mining operation with a nominal 95,000 tonne-per-day throughput. Life of mine throughput average is approximately 84,000 tonnes per day due to the milling circuit constraining throughput as harder rock is encountered deeper in the open pits. The current 528 million tonne mineral reserve estimate is expected to support a mine life of approximately 18 years. Using a conventional grinding and flotation circuit, the project would produce a high-quality copper concentrate with significant gold and silver credits.

Reserve and Resource Estimate

The proven and probable mineral reserve estimate for the Galore Creek project totals 528.0 million tonnes grading 0.59% copper, 0.32 grams per tonne gold and 6.02 grams per tonne silver for a total estimated metal content of 6.8 billion pounds of copper, 5.45 million ounces of gold and 102.1 million ounces of silver at an NSR cut-off grade of $10.08 per tonne.

Proven and Probable Mineral Reserve Estimate

Tonnes (million tonnes) Diluted Grade Cu (%) Au (g/t) Ag (g/t) Contained Cu (billion pounds) Contained Au (million ounces) Contained Ag (million ounces)
Proven 69.0 0.61 0.52 4.94 0.9 1.15 11.0
Probable 459.1 0.58 0.29 6.18 5.9 4.30 91.2
Proven and probable 528.0 0.59 0.32 6.02 6.8 5.45 102.1

Effective Date July 11, 2011, Jay Melnyk, P.Eng.

Notes:

(1) Mineral reserves are contained within measured and indicated pit designs, and supported by a mine plan, featuring variable throughput rates, stockpiling and cut-off optimization. The pit designs and mine plan were optimized on diluted grades using the following economic and technical parameters: Metal prices for copper, gold and silver of $2.50per pound, $1,050 per ounce, and $16.85 per ounce, respectively. Mining and ore based costs (process, G&A and mine general) of C$1.60 per tonne mined and C$10.08 per tonne milled respectively; an exchange rate of $0.91 to C$1.00; variable recovery versus head grade relationships for both oxidized and non-oxidized material; appropriate smelting, refining and transportation costs; and inter ramp pit slope angles varying from 42º to 55º. The mineral reserves are reported in accordance with NI 43-101, which differs from SEC Industry Guide 7. The project is without known reserves as defined under SEC Industry Guide 7. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(2) Mineral reserves are reported using a ‘cash flow grade’ ($NSR/SAG mill hour) cut-off which was varied from year to year in the scheduling process to optimize NPV. The cash flow grade is a function of the NSR ($ per tonne) and SAG mill throughput (tonnes per hour). The net smelter return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using the economic and technical parameters mentioned above. SAG throughputs were modeled by correlation with alteration types.

(3) The life of mine strip ratio is 2.16.

(4) Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content.

(5) Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

Resource Estimate

The measured and indicated mineral resource for the Galore Creek project (exclusive of mineral reserves) is estimated to total 286.7 million tonnes grading 0.33% copper, 0.27 grams per tonne gold and 3.64 grams per tonne silver for a total estimated metal content of 2,070 million pounds of copper, 2.53 million ounces of gold and 33.54 million ounces of silver at an NSR cut-off grade of C$10.08 per tonne.

The updated inferred mineral resource, excluding our 40% interest in the Copper Canyon project, is estimated to total 346.6 million tonnes grading 0.42% copper, 0.24 grams per tonne gold and 4.28 grams per tonne silver for a total estimated metal content of 3,230 million pounds of copper, 2.7 million ounces of gold and 47.7 million ounces of silver at an NSR cut-off grade of C$10.08 per tonne.

Measured and Indicated Resources Estimate (exclusive of reserves)

Tonnes (million tonnes) Cu Grade (%) Au Grade (g/t) Ag Grade (g/t) Contained Cu (billion pounds) Contained Au (million ounces) Contained Ag (million ounces)
Measured 39.5 0.25 0.39 2.58 0.22 0.50 3.27
Indicated 247.2 0.34 0.26 3.81 1.85 2.04 30.26
Measured and indicated 286.7 0.33 0.27 3.64 2.07 2.53 33.54

Effective Date July 11, 2011, G. Kulla, P.Geo.

Notes:

(1) Mineral resources are exclusive of Mineral reserves. Mineral resources that are not Mineral reserves do not have demonstrated economic viability. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(2) Mineral resources are contained within a conceptual measured, indicated and inferred optimized pit shell using the same economic and technical parameters as used for Mineral reserves. Tonnages are assigned based on proportion of the block below topography. The overburden/bedrock boundary has been assigned on a whole block basis. Commodity prices used to constrain the Mineral Resources are $2.50 per pound copper, $1,050 per ounce gold, and $16.85 per ounce silver.

(3) Mineral resources have been estimated using a constant NSR cut-off of $10.08 per tonne milled. The Net Smelter Return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Diluted Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using silver using the economic and technical parameters used for mineral reserves.

(4) Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content.

(5) Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds.

Inferred Mineral Resource Estimate

Tonnes (million tonnes) Cu Grade (%) Au Grade (g/t) Ag Grade (g/t) Contained Cu (billion pounds) Contained Au (million ounces) Contained Ag (million ounces)
Inferred 346.6 0.42 0.24 4.28 3.23 2.70 47.73

(1) Inferred resources are in addition to measured and indicated resources. Inferred resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher category. See Cautionary Note to U.S. Investors Regarding Estimates of Measured, Indicated and Inferred Resources and Proven and Probable Reserves, above.

(2) Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds.

A rigorous quality control and quality assurance protocol has been used on the project, including blank and reference samples with each batch of assays. All our drill samples were analyzed by fire assay and ICP at ALS Chemex Labs in Vancouver, British Columbia, Canada.

Environmental Assessment and Permitting

The Galore Creek environmental assessment process was initiated in February 2004. As part of the environmental assessment process, a series of public meetings was held in various communities in the Galore Creek region, with the public and regulator comment periods running from July 10, 2006 to September 8, 2006 and September 22, 2006, respectively. The Tahltan Central Council, which was actively engaged in the entire assessment process, submitted their comments to the British Columbia Environmental Assessment Office (BCEAO) on October 18, 2006, including a letter of support from the Chair of the Tahltan Central Council. The permitting process for the Galore Creek project progressed as expected resulting in the receipt of the Provincial Environmental Assessment Certificate in February 2007. Federal authorizations were received during the second quarter of 2007.

Although construction at the Galore Creek project was suspended in late 2007, the Canadian Federal and Provincial authorizations to proceed remain in good standing as do a majority of the key permits required to continue construction. Specifically, since the Province has determined substantial construction of the project was initiated, the previous environmental assessment certificate remains valid without a time limit.

The PFS project design and configuration is different from the design that was permitted under the original environmental assessment certificate and that received Federal approval. Some of the most significant changes are:

  • Better understanding of geochemistry, resulting in a different approach to waste rock and tailings management;
  • Simplified waste and water management strategy in the Galore Creek valley plant site and tailings relocated outside of the Galore Creek valley, in a new previously unaffected watershed (West More);
  • Deletion of a 30 kilometer section of access road down the Sphaler Valley to Porcupine and the Scott Simpson Valley, significantly reducing potential environmental impacts and geohazards;
  • Deletion of the airstrip that was to be constructed in the Porcupine Valley; and
  • Addition of new load-out facilities at the Port of Stewart.

While the PFS configuration is considered an improvement, with reduced overall environmental impacts, it is anticipated that a new environmental assessment process will be requested by the regulators to approve the changes. This will involve parallel and harmonized reviews by both the BCEAO and the Canadian Environmental Assessment Agency (CEAA). A comprehensive study report will be required through CEAA. It is anticipated that the entire environmental assessment review process would require approximately two years from submission of a project description to issuance of a new Environmental Assessment Certificate (by the provincial government) and a decision by the federal Minister of Environment.

The existing Special Use Permit (SUP) for construction of the access road remains valid as long as there are no proposed changes to the SUP, thereby permitting GCMC to resume construction of the access road without further permitting. Changes to the current SUP will ultimately be required around the tailings storage facility, plus a branch to the south portal of the tunnel to the Galore Creek valley. An amendment to make these changes will be applied for once the environmental assessment process has been completed.

Existing permits associated with the existing construction camps, including water use and waste discharge, will continue to be maintained. All other project permits will have to be applied for following completion of the environmental assessment process, although the time-critical permits, such as those needed for starting the tunneling can be prepared concurrent with the environmental assessment such that there should be little lag time following new environmental assessment certification before tunneling could begin.

Current Activities

The 2011 resource infill drilling program confirmed previous drill results produced by GCMC as well as the potential for substantial extension of mineralization beyond the limits of the reserve pits provided for in the PFS. Activities in 2012 included 27,000 meters of resource infill and exploration drilling as well as geotechnical, hydrogeological and overburden drilling to support future mine planning and engineering. The objective of the infill drilling was to increase resources and upgrade material in all categories. The exploration drilling resulted in the discovery of the Legacy zone adjacent to the Central reserve pit. Activities in 2013 included 11,600 meters of resource infill and exploration drilling. The 2013 program increased the drill density to a level required to support an inferred resource classification of the Legacy zone.

Our share of funding for the Galore Creek project in 2013 was $6.6 million, primarily for exploration drilling, environmental monitoring, administrative expenses and site care and maintenance costs. We jointly approved with Teck a 2014 work program of approximately $5 million, of which our 50% share is approximately $2.5 million. We agreed with Teck to incorporate the 2012 and 2013 results into a capital efficient work plan in 2014 that will advance the Galore Creek project toward a next-level mine planning and design. As such, the 2014 work plan includes technical studies in the areas of environmental and water management, as well as site layout. Although the Legacy zone is still open to the south, west and at depth, no drill program is planned for 2014. We will continue to evaluate opportunities to monetize the value of the asset.

Copper Canyon Acquisition

On May 20, 2011, we completed the acquisition of Copper Canyon Resources Ltd. (“Copper Canyon”) a junior exploration company whose principal asset was its 40% joint venture interest in the Copper Canyon copper-gold-silver property that is adjacent to the Galore Creek project. A wholly-owned subsidiary of NOVAGOLD held the remaining 60% joint venture interest in the Copper Canyon property which it agreed to transfer to the Galore Creek Partnership. Under the acquisition arrangement, we acquired all of the issued and outstanding common shares of Copper Canyon which we did not already hold. As a result, Copper Canyon became a wholly-owned subsidiary of us. We issued a total of 4,171,303 common shares under the arrangement, representing approximately 1.7% of the number of our common shares then outstanding and paid cash of C$2.6 million.

The Copper Canyon property is subject to a 2% NSR royalty which may be reduced to 0.5% by the payment of C$2.0 million to the royalty holder.

As filed, 654 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Periodically, we are a party to or otherwise involved in legal proceedings arising in the normal course of business. Management does not believe that there is any pending or threatened proceeding against the Company which, if determined adversely, would have a material adverse effect on our financial position, liquidity or results of operations. There are no material proceedings pursuant to which any of our directors, officers or affiliates or any owner of record or beneficial owner of more than 5% of our securities or any associate of any such director, officer or security holder is a party adverse to us or has a material interest adverse to us.

Management's discussion and analysis

As filed, 25,708 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following discussion and analysis of our financial condition and results of operations constitutes management’s review of the factors that affected our financial and operating performance for the years ended November 30, 2013, 2012 and 2011. This discussion should be read in conjunction with the consolidated financial statements and notes thereto contained elsewhere in this report.

Overview

Our operations primarily relate to the delivery of project milestones, including the achievement of various technical, environmental, sustainable development, economic and legal objectives, obtaining necessary permits, completion of feasibility studies, preparation of engineering designs and the financing to fund these objectives.

In 2013, we successfully delivered on the key goals established at the beginning of the year. Highlights of our accomplishments include:

Advancement of the Donlin Gold project

Permitting of the Donlin Gold project continued to advance:

  • The Notice of Intent to prepare an EIS was published by the Corps in the Federal Register in December 2012, commencing the public scoping process.
  • Public scoping meetings were held in 13 villages and communities in Western Alaska and in Anchorage to provide information and insight about the project.
  • A data gap analysis to address questions and concerns that arose from the scoping meetings was prepared.
  • EIS Scoping Summary report completed and made available to the public (www.donlingoldeis.com (http://www.donlingoldeis.com)).
  • Strong working relationships were maintained with the agencies and we continue to provide input throughout the permitting process.
  • Ongoing baseline data review was conducted including:

° follow-up technical workshops highlighting core components of baseline environmental and social studies; and

° completion of 2013 supplemental field studies.

  • EIS Alternatives Development occurred, including:

° reasonable range of alternatives that are feasible, practicable and permittable to address key issues (i.e.: power – gas pipeline vs. diesel) has been defined; and

° the initial screening of potential alternatives has been completed.

  • Preliminary Draft EIS preparation was commenced, initial draft chapters are in review by the Cooperating Agencies.
  • A strong safety record was maintained.
  • Several villages were engaged in work force development planning.
  • Donlin Gold was named “Employer of the Year” by the National Association of State Workforce Agencies.

Galore Creek project

The 2013 drilling program was completed under budget and exceeded program objectives with 11,600 meters drilled:

  • Significant intercepts encountered on follow-up drilling from the Legacy zone discovery in 2012, a 700-meter long mineralized zone, adjacent to the Central Pit.
  • Extensions of the Legacy zone mineralization were identified to the south, west and at depth and provided information that will be useful to assess its impact on future mine design.
  • Results from the 2012 and 2013 drilling programs will be incorporated into a capital efficient work plan for 2014 that will advance the project.

Strengthened our financial position

  • Reduced cash flow used in continuing operations to $19.5 million in 2013 from $28.6 million in 2012.
  • Our cash used in operations and funding of the Donlin Gold and Galore Creek projects totaled $38.3 million, $2.7 million lower than our budget of $41 million.
  • Received proceeds of $54.4 million upon exercise of the remainder of our outstanding warrants.
  • Completed a tender offer for our Notes and subsequently purchased additional Notes

° Reduced the principal obligation of the Notes from $95.0 million to $15.8 million.

° Reduced associated interest expense.

  • We have sufficient cash available to repay the remaining $15.8 million of the outstanding Notes due in May 2015 and to advance the Donlin Gold project through the remaining expected permitting process.

Outlook

Our goals for 2014 include:

  • Advance permitting of the Donlin Gold project.
  • Maintain a healthy balance sheet.
  • Undertake Galore Creek technical studies to build on successful 2012 and 2013 drill results.
  • Evaluate opportunities to monetize the value of Galore Creek.
  • Maintain an effective corporate social responsibility program.

We do not currently generate operating cash flows. At November 30, 2013, we had cash and cash equivalents of $81.3 million and term deposits of $110.0 million. At present, we believe that these balances are sufficient to cover the anticipated funding at the Donlin Gold and Galore Creek projects in addition to general and administrative costs through completion of permitting at the Donlin Gold project. Additional capital will be necessary if permits are received at the Donlin Gold project and a decision to commence construction is reached. Future financings to fund construction are anticipated through debt financing, equity financing, project specific debt, or other means. Our continued operations are dependent on our ability to obtain additional financing or to generate future cash flows. However, there can be no assurance that we will be successful in our efforts to raise additional capital. For further information, see section Item 1A, Risk Factors - Our ability to continue the exploration, permitting, development, and construction of the Donlin Gold and Galore Creek projects, and to continue as a going concern, will depend in part on our ability to obtain suitable financing, above. In 2014, we expect to spend approximately $15 million to fund our share of expenditures at the Donlin Gold and Galore Creek projects and $15 million for general and administrative costs, interest, working capital and other corporate purposes.

Summary of Consolidated Financial Performance

($ thousands, except per share)

Years ended November 30, 2013 2012 2011
Loss from operations $(55,776) $(79,942) $(115,996)
Income (loss) from continuing operations $(62,760) $(7,586) $78,235
Net income (loss) attributable to shareholders $(62,760) $(11,829) $64,767
Net income (loss) per common share
Basic $(0.20) $(0.05) $0.19
Diluted $(0.20) $(0.05) $0.07

61

Results of Operations

2013 compared to 2012

Loss from operations decreased 30% from $79.9 million in 2012 to $55.8 million in 2013. The decrease resulted from lower general and administrative expenses and a lower share of losses from equity investments in the Donlin Gold and Galore Creek projects. General and administrative expenses decreased 30% due to the corporate reorganization costs that were incurred in 2012 for severance and recruiting. Our share of losses at the Donlin Gold project decreased by $2.3 million, as 2013 activities were focused primarily on permitting. At the Galore Creek project, our share of losses decreased by $10.0 million due to a smaller drilling program that focused on the 2012 Legacy zone discovery.

Net loss attributable to shareholders increased from $11.8 million ($0.05 per share – basic) in 2012 to $62.7 million ($0.20 per share – basic) in 2013. In 2012, the fair value of U.S. dollar denominated warrants and the Notes decreased and we recorded a gain of $76.2 million compared to a gain of $1.4 million in 2013, partially offset by the $24.1 million reduction in the loss from operations in 2013 compared to 2012. We also had a $3.9 million tax expense in 2013 compared to a $7.7 million income tax recovery and a $4.2 million net loss from discontinued operations in 2012.

2012 compared to 2011

In 2011, the results of operations and presentation in the financial statements were impacted by the deconsolidation of the Galore Creek project. Teck earned its 50% interest in the Galore Creek project upon completion of its funding commitment of C$373.3 million in June 2011 (the “Reconsideration Event”). The Reconsideration Event resulted in a loss of our primary beneficiary status upon Teck completing its earn-in obligations under the Partnership Agreement. Prior to the completion of its earn-in, if Teck had failed to meet their obligations, we would have had the power to exercise control over the Partnership. Following the Reconsideration Event, we share joint control of the Galore Creek Partnership with Teck, costs are funded equally between the partners and we equity account for our investment.

We determined the fair value of the Partnership at the reconsideration date, deconsolidated the Galore Creek Partnership and subsequently equity accounted for our share of the investment. We determined that the fair value of the Galore Creek project was $354.4 million at May 31, 2011 using estimated discounted future cash flows. As a result, we recognized a gain of $154.2 million for the excess value over the book value of $200.2 million. The determination of the estimated fair value of the equity investment in the Galore Creek Partnership required management to make estimates and assumptions of future events. These estimates and assumptions affect the reported amount of the investment and the reported amount of the gain recognized upon fair valuing the equity investment in the Galore Creek Partnership. Significant assumptions included gold, copper and silver prices of $1,100 per ounce, $2.66 per pound, and $18.50 per ounce, respectively, and a 7% discount rate. Other estimates included future foreign exchange rates, various operational assumptions and metal recovery rates. Actual results could differ materially from those reported.

Loss from operations decreased 31% from $116.0 million in 2011 to $79.9 million in 2012. The decrease was primarily due to $39.6 million in write-downs related to power transmission rights and mobile equipment at the Galore Creek project. General and administrative costs increased by $12.9 million in 2012 as a result of the corporate reorganization which included severance and recruiting costs. Our share of losses at the Donlin Gold project decreased by $4.7 million as permitting activities commenced. At the Galore Creek project, our share of losses increased by $6.0 million due to an expanded drilling program which resulted in the Legacy zone discovery.

Net loss from discontinued operations in 2012 and 2011, includes the financial results associated with NovaCopper Inc. and the Ambler assets, and the former operations of Alaska Gold Company LLC (AGC) and the Rock Creek project. On April 30, 2012, we completed a plan of arrangement under the Companies Act (Nova Scotia) pursuant to which we spun-out NovaCopper Inc., a wholly-owned subsidiary of the Company which held the Ambler assets in Alaska, to our shareholders. On November 1, 2012, we completed the sale of our wholly owned subsidiary, AGC, which owns the Rock Creek project and other assets in and around Nome, Alaska to Bering Straits Native Corporation. The loss decreased from $33.1 million in 2011 to $4.2 million in 2012, primarily due to a partial year of expenses at Ambler due to the spin-out of NovaCopper Inc. and a write-down of inventory and reclamation expense at Rock Creek in 2011.

Net income attributable to shareholders decreased from $64.8 million ($0.19 per share – basic) in 2011 to a loss of $11.8 million ($0.05 per share – basic) in 2012. The decrease was due to the gain recognized in 2011 on deconsolidation of the Galore Creek Partnership, partially offset by the decrease in Loss from operations, the decrease in Net loss from discontinued operations and a $7.7 million deferred income tax recovery in 2012 compared to an expense of $15.4 million in 2011.

Liquidity, Capital Resources and Capital Requirements

($ thousands) Years ended November 30, 2013 2012 2011
Cash used in continuing operations $(19,491) $(28,570) $(27,731)
Cash used in investing activities of continuing operations $(128,846) $(34,842) $(41,279)
Cash provided from (used in) financing activities of continuing operations $(24,812) $323,585 $21,565
($ thousands) As of November 30, 2013 2012
Cash and cash equivalents $81,262 $254,667
Term deposits $110,000 $—

Cash and cash equivalents decreased by $173.4 million to $81.3 million at November 30, 2013 compared to $254.7 million at November 30, 2012. The decrease in cash is primarily related to the investment of $110.0 million in term deposits, $19.5 million used in operating activities, $18.8 million to fund Donlin Gold and Galore Creek and $79.2 million to repurchase Notes, partially offset by proceeds of $54.4 million from warrants exercised. We have sufficient working capital available to repay the remaining $15.8 million of outstanding Notes due in May 2015 and to advance the Donlin Gold project through the expected remaining permitting process.

2013 compared to 2012

Cash used in continuing operations decreased from $28.6 million in 2012, to $19.5 million in 2013. The decrease resulted from the successful reorganization of the Company in 2012 encompassing the spin-out of NovaCopper Inc., the sale of AGC, which included Rock Creek, as well as a reduction in corporate overhead and administrative costs. Interest payments were lower due to the $79.2 million repurchase of Notes in 2013. Cash used in discontinued operations in 2012 included $25.5 million in 2012 to fund the operations of NovaCopper Inc. and the Rock Creek project.

Cash used in investing activities of continuing operations in 2013 included an investment of $110.0 million in term deposits with original terms of six to nine months to earn a higher return while maintaining adequate liquidity. The U.S. dollar denominated term deposits are held at two major Canadian financial institutions. Cash funding of investments in affiliates decreased by $14.1 million due to lower project activity during permitting at the Donlin Gold project and a reduced exploration program at the Galore Creek project.

Cash used in financing activities of continuing operations in 2013 included the repurchase of $79.2 million of our Notes, partially offset by the receipt of $54.4 million in net proceeds from the exercise of all outstanding warrants. In 2012, we received net proceeds of $318.0 million from the completion of an equity financing of 35 million common shares at $9.50 per share and $5.6 million from the exercise of warrants. Cash used in financing activities of discontinued operations in 2012 included $40 million to fund the spin-out of NovaCopper Inc.

2012 compared to 2011

Cash used in continuing operations increased from $27.7 million in 2011, to $28.6 million in 2012. The increase resulted from reorganization costs including severance in 2012, partially offset by the inclusion of 100% of spending at the Galore Creek project in the first half of 2011, prior to deconsolidation. Cash used in discontinued operations increased from $22.0 million in 2011 to $25.5 million in 2012 to fund the operations of NovaCopper Inc. and the remediation of the Rock Creek project.

Cash used in investing activities of continuing operations in 2011 included $4.1 million for the acquisition of Copper Canyon. Cash funding of investments in affiliates increased by $1.7 million due to the expanded drilling program at the Galore Creek project that resulted in the discovery of the Legacy zone, partially offset by lower spending at the Donlin Gold project as permitting commenced in 2012. Cash provided from investing activities of discontinued operations resulted primarily from the sale of equipment at the Rock Creek project.

Cash used in financing activities of continuing operations in 2012 included net proceeds of $318.0 million from the completion of an equity financing and $5.6 million from the exercise of warrants and stock options. In 2011, we received proceeds of $14.2 million from the exercise of warrants and stock options and $7.4 million from Teck to fund the Galore Creek project prior to the completion of Teck’s earn-in on the project. Cash used in financing of discontinued operations included $40 million to fund the spin-out of NovaCopper Inc. in 2012 and $24.0 million to repay the Ambler note in 2011.

Contractual Obligations

Our contractual obligations as of November 30, 2013 were as follows:

($ thousands) Total Less than 1 year 1-3 years 3-5 years More than 5 years
Reclamation and remediation $861 $861 $— $— $—
Office and equipment leases 1,622 440 846 336 —
Convertible notes - principal 15,829 — 15,829 — —
Convertible notes - interest 1,306 871 435 — —
Promissory note 71,728 — — — 71,728

Off-Balance Sheet Arrangements

The Company does not have any material off-balance sheet arrangements required to be disclosed in this Annual Report on Form 10-K.

Outstanding share data

As of February 6, 2014, we had 317,297,868 common shares issued and outstanding. As of February 6, 2014, we had 13,950,134 stock options with a weighted-average exercise price of $5.71, 2,281,692 restricted share units and 134,090 deferred share units outstanding. Following the Company’s purchases of the Notes, $15,829 of the principal amount of the Notes remain outstanding and due on May 1, 2015 and 1,639,370 common shares remain issuable upon conversion.

Related party transactions

The Company provided exploration and management services to Donlin Gold for $258 in 2013, $236 in 2012 and $600 in 2011; office rental and services to Galore Creek for $423 in 2013, $796 in 2012 and $886 in 2011; and management and office administration services to NovaCopper Inc. for $168 in 2013 and $83 in 2012.

As of November 30, 2013, the Company has accounts receivable from Donlin Gold of $1,750 (2012: $nil) and from Galore Creek Galore Creek of $1,690 (2012: $138) included in other current assets and a receivable of $4,132 (2012: $4,417) from Galore Creek included in other long-term assets.

Fourth quarter results

During the fourth quarter of 2013, we incurred a net loss of $20.0 million compared to $30.2 milllion for the comparable period in 2012. The decrease in net loss in 2013 compared to 2012 was primarily due to a loss on derivative liabilities in 2012. We also incurred lower general and administrative expenses and interest expense in 2013, offset by increased defered income tax expense.

Accounting Developments

For a discussion of Recently Issued Accounting Pronouncements, see Note 2 to the Consolidated Financial Statements.

Critical Accounting Policies

We believe the following accounting policies are critical to our financial statements due to the degree of uncertainty regarding the estimates or assumptions involved and the magnitude of the asset, liability, revenue or expense being reported.

Investment in affiliates

Our investments in the Donlin Gold project and the Galore Creek project are accounted for using the equity method. The equity method is a basis of accounting for investments whereby the investment is initially recorded at cost and the carrying value is adjusted thereafter to include the investor’s pro rata share of post-acquisition earnings or losses of the investee, as computed by the consolidation method. Cash funding increases the carrying value of the investment. Profit distributions received or receivable from an investee reduce the carrying value of the investment.

These investments are non-publicly traded equity investees in advanced exploration projects. Therefore, we assess whether there has been a potential impairment triggering event for other-than-temporary impairment by testing the underlying assets of the equity investee for recoverability and assessing whether there has been a change in the development plan or strategy for the project. If we determine underlying assets are recoverable and no other potential impairment conditions are identified, then our investment in the equity investee is carried at cost. If the other underlying assets are not recoverable, we record an impairment charge equal to the difference between the carrying amount of the investee and its fair value. We determined fair value based on the present value of future cash flows expected to be generated by the project. If reliable cash flow information is not available, we determine fair value using a market comparable approach.

Mineral properties and exploration and evaluation expenditures

Mineral property acquisition costs, including directly related costs, are capitalized when incurred, and mineral property exploration and evaluation costs are expensed as incurred. Mine development costs include engineering and metallurgical studies, drilling and other related costs to delineate an ore body and the removal of overburden to initially expose an ore body at open pit surface mines. Capitalization of mine development project costs, that meet the definition of an asset, begins once mineralization is classified as proven and probable reserves as defined by SEC Industry Guide 7. Capitalized costs will be amortized using the units-of-production method over the estimated life of the proven and probable reserves. If mineral properties are subsequently abandoned or impaired, any unamortized costs will be charged to loss in that period.

The recoverability of the carrying values of our mineral properties is dependent upon economic reserves being discovered or developed on the properties, permitting, financing, start-up, and commercial production from, or the sale/lease of, or other strategic transactions related to these properties.

Income taxes

We account for income taxes under the asset and liability method. Deferred tax assets and liabilities are recognized for the future tax consequences attributable to differences between the financial statement carrying amounts of existing assets and liabilities and their respective tax bases. Deferred tax assets and liabilities are measured using enacted tax rates expected to apply to taxable income in the years in which those temporary differences are expected to be recovered or settled. Under the asset and liability method, the effect on deferred tax assets and liabilities of a change in tax rates is recognized in income in the period that includes the enactment date. A valuation allowance is recognized if it is more likely than not that some portion or the entire deferred tax asset will not be recognized.

Share-based compensation

We operate a stock option plan and a performance share unit plan, under which the entity receives services from employees as consideration for equity instruments (options or shares) of the Company. The fair value for the options and share units are recognized in earnings over the related service period. The total amount to be expensed related to options is determined by reference to the fair value of the options granted including any market performance conditions and the impact of any non-vesting conditions; and excluding the impact of any service and non-market performance vesting conditions.

The fair value of stock options is estimated at the time of grant using the Black‐Scholes option pricing model, and the fair value of the PSUs is measured at the grant date using a Monte Carlo simulation, which takes into account, as of the grant date, the fair market value of the shares, expected volatility, expected dividend yield and the risk‐free interest rate over the life of the PSU, to generate potential outcomes for stock prices which are used to estimate the probability of the PSUs vesting at the end of the performance measurement period.

We grant our board members deferred share units (DSUs), whereby each DSU entitles the directors to receive one common share of the Company when they retire from service with the Company. The fair value of the DSUs is measured at the date of the grant in amounts ranging from 50% to 100% of directors’ annual retainers at the election of the directors. The fair value is recognized in consolidated statement of income (loss) over the related service period.

Derivative Instruments

All financial instruments that meet the definition of a derivative are recorded on the balance sheet at fair value. Changes in the fair value of derivatives are recorded in the consolidated statements of income. Management applies judgment in estimating the fair value of instruments that are highly sensitive to assumptions regarding market volatilities, foreign currency exchange rates and interest rates. Variations in these factors could materially affect amounts credited or charged to earnings to reflect the changes in fair value of derivatives.

Net income (loss) per common share

Basic and diluted income (loss) per share is presented for Net income (loss) and for Income (loss) from continuing operations. Basic income (loss) per share is computed by dividing Net income (loss) or Income (loss) from continuing operations by the weighted-average number of outstanding common shares for the period, including the warrants and the convertible notes. Diluted income per share reflects the potential dilution that could occur if securities or other contracts that may require the issuance of common shares in the future were converted. Diluted income per share is computed by increasing the weighted-average number of outstanding common shares to include the additional common shares that would be outstanding after conversion and adjusting net income for changes that would result from the conversion. Only those securities or other contracts that result in a reduction in earnings per share are included in the calculation.

Market risk

As filed, 1,807 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Our financial instruments are exposed to certain financial risks, including currency, credit and interest rate risks.

Currency risk

We are exposed to financial risk related to the fluctuation of foreign exchange rates. We operate in Canada and the United States and a portion of our expenses are incurred in Canadian dollars. A significant change in the currency exchange rate between the Canadian dollar relative to the U.S. dollar could have an effect on our results of operations, financial position or cash flows.

We have not hedged our exposure to currency fluctuations. At November 30, 2013, we are exposed to currency risk through our investment in the Galore Creek project, mineral properties, deferred income taxes and cash balances held in Canadian dollars.

Based on the above net exposures as at November 30, 2013, and assuming that all other variables remain constant, a 1% depreciation or appreciation of the Canadian dollar against the U.S. dollar would result in an increase/decrease of $3.5 million in our consolidated comprehensive income (loss).

Credit risk

Concentration of credit risk exists with respect to our cash and cash equivalents and term deposit investments. All deposits are held through two large Canadian financial institutions with high investment-grade ratings and have maturities of less than one year.

Interest rate risk

The Notes are not subject to interest rate risk because they are at fixed rates. The interest rate on the promissory note owed to Barrick is variable with the U.S. prime rate. Based on the amount owing on the promissory note as at November 30, 2013, and assuming that all other variables remain constant, a 1% change in the U.S. prime rate would result in an increase/decrease of $0.7 million in the interest accrued by us per annum.

Controls and procedures

As filed, 3,173 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

An evaluation was performed under the supervision and with the participation of our management, including our principal executive officer and principal financial officer, of the effectiveness of our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934) as of the end of the period covered by this Annual Report on Form 10-K. Based on the foregoing, our management concluded that our disclosure controls and procedures are effective to ensure that information required to be disclosed by us in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the Securities and Exchange Commission rules and forms and such information is accumulated and communicated to our management, including our principal executive officer and principal financial officer, to allow timely decisions regarding required disclosure.

There was no change in our internal control over financial reporting that occurred during the quarter ended November 30, 2013 that has materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.

REPORT OF MANAGEMENT ON INTERNAL CONTROL OVER FINANCIAL REPORTING

Our management is responsible for establishing and maintaining adequate internal control over financial reporting for the Company. Internal control over financial reporting is a process to provide reasonable assurance regarding the reliability of our financial reporting and the preparation of financial statements for external purposes in accordance with accounting principles generally accepted in the United States of America. Internal control over financial reporting includes maintaining records that in reasonable detail accurately and fairly reflect our transactions; providing reasonable assurance that transactions are recorded as necessary for preparation of our financial statements; providing reasonable assurance that receipts and expenditures of our assets are made in accordance with management’s authorization; and providing reasonable assurance that unauthorized acquisition, use or disposition of our assets that could have a material effect on the financial statements would be prevented or detected on a timely basis. Because of its inherent limitations, internal control over financial reporting is not intended to provide absolute assurance that a misstatement of our financial statements would be prevented or detected.

Management conducted its evaluation of the effectiveness of our internal controls over financial reporting based on the framework in Internal Control — Integrated Framework issued in 2013 by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that our internal control over financial reporting was effective as of November 30, 2013.

The effectiveness of our assessment of internal control over financial reporting as of November 30, 2013 has been audited by PricewaterhouseCoopers LLP, an independent registered public accounting firm, as stated in their report which appears herein.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2013-11-30. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Operating income3 months2013-09-01 to 2013-11-30−$13.2mus-gaap:OperatingIncomeLoss
Operating income12 months2012-12-01 to 2013-11-30−$55.8mus-gaap:OperatingIncomeLoss
Interest expense12 months2012-12-01 to 2013-11-30$12.6mus-gaap:InterestExpense
Income tax12 months2012-12-01 to 2013-11-30$3.9mus-gaap:IncomeTaxExpenseBenefit
Net income3 months2013-09-01 to 2013-11-30−$19.2mus-gaap:NetIncomeLoss
Net income12 months2012-12-01 to 2013-11-30−$62.8mus-gaap:NetIncomeLoss
Diluted EPS3 months2013-09-01 to 2013-11-30−$0.06us-gaap:EarningsPerShareDiluted
Diluted EPS12 months2012-12-01 to 2013-11-30−$0.20us-gaap:EarningsPerShareDiluted
Basic EPS3 months2013-09-01 to 2013-11-30−$0.06us-gaap:EarningsPerShareBasic
Basic EPS12 months2012-12-01 to 2013-11-30−$0.20us-gaap:EarningsPerShareBasic
Diluted shares (weighted)12 months2012-12-01 to 2013-11-30313,372 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Capital expenditure12 months2012-12-01 to 2013-11-30$78.0kus-gaap:PaymentsToAcquirePropertyPlantAndEquipment
Cash and equivalentsAt period end2013-11-30$81.3mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2013-11-30$196.8mus-gaap:AssetsCurrent
Total assetsAt period end2013-11-30$578.7mus-gaap:Assets
Current liabilitiesAt period end2013-11-30$4.4mus-gaap:LiabilitiesCurrent
Total liabilitiesAt period end2013-11-30$113.0mus-gaap:Liabilities
Long-term debtAt period end2013-11-30$85.3mus-gaap:LongTermDebtNoncurrent
Shareholders' equityAt period end2013-11-30$465.6mus-gaap:StockholdersEquity
Shares outstandingAt period end2013-11-30316,661,692 sharesdei:EntityCommonStockSharesOutstanding

Source: SEC EDGAR, the filing index for accession 0001102624-14-000184. Last ingested by Listed: Nov 11, 2026, 03:11 ET. Listed shows no prices and gives no investment advice.