Management's discussion and analysis

As filed, 51,354 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Forward Looking Statements

This Quarterly Report on Form 10-Q for the quarterly period ended September 30, 2010 (“Third Quarter 2010 Report”) contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), which are subject to the “safe harbor” created by those sections. Forward-looking statements include information concerning our possible or assumed future results of operations, business strategies, financing plans, competitive position, industry environment, potential growth opportunities, the effects of regulation and the economy, generally. Forward-looking statements include all statements that are not historical facts and can be identified by terms such as “anticipates,” “believes,” “could,” “estimates,” “expects,” “intends, “may,” “plans,” “potential,” “predicts,” “projects,” “should,” “will,” “would” or similar expressions.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. We discuss many of these risks in detail in Part I, Item 1A “Risk Factors” of our Annual Report on Form 10-K for the year ended December 31, 2009 and our other filings with the Securities and Exchange Commission (“SEC”). Also, forward-looking statements represent our management’s beliefs and assumptions only as of the date of this Third Quarter 2010 Report. You should read this Third Quarter 2010 Report, our Annual Report on Form 10-K for the year ended December 31, 2009 and our other filings with the SEC completely and with the understanding that our actual future results may be materially different from what we expect.

Given these uncertainties, you should not place undue reliance on these forward-looking statements. We assume no obligation to update these forward-looking statements publicly, or to update the reasons actual results could differ materially from those anticipated in any forward-looking statements, even if new information becomes available.

The following discussion and analysis should be read in conjunction with the unaudited financial statements and notes thereto included in Part 1, Item 1 of this Third Quarter 2010 Report.

Introduction

Primoris Services Corporation is a holding company with various subsidiaries that cumulatively form a diversified construction company providing a wide range of construction and product engineering services. These services include fabrication, maintenance, replacement and other services to major public utilities, petrochemical companies, energy companies, municipalities and other customers. Our activities are performed primarily in the Southeast and Southwest United States, primarily in Louisiana and California, with strategic presences in Florida, Texas and Canada.

We install, replace, repair and rehabilitate natural gas, refined product, water and wastewater pipeline systems, and also construct mechanical facilities and other structures, including power plants, petrochemical facilities, refineries and parking structures. In addition, we provide maintenance services, including inspection, overhaul and emergency repair services, to cogeneration plants, refineries and similar mechanical facilities.

Through our acquisition of James Construction Group, LLC (“JCG”) in December 2009, we provide services in heavy civil construction projects, including highway and bridge construction, concrete paving, levee construction, airport runway and taxiway construction and marine facility construction. JCG’s infrastructure and maintenance division provides large earthwork and site development, landfill construction, site remediation and mining support services. JCG’s industrial division, with a client base comprised primarily of private industrial companies, provides all phases of civil and structural construction, mechanical equipment erection, process pipe installation and boiler, furnace and heater installation and repair.

Through our subsidiary Onquest, Inc. (“Onquest”), we provide product engineering and design services for fired heaters and furnaces primarily used in refinery applications. Through our subsidiary Cardinal Contractors, Inc., we construct water and wastewater facilities primarily in Florida.

On July 1, 2010, we acquired a 50% membership interest in WesPac Energy LLC (“WesPac”), which develops pipeline and terminal projects in the United States, Canada and Mexico. The investment is being accounted for under the equity method and is recorded as an investment in non-consolidated entities on our balance sheet.

We make our press releases, our Annual Reports on Form 10-K, our Quarterly Reports on Form 10-Q, our Current Reports on Form 8-K and all other required filings with the SEC available, free of charge through our Internet Web site, as reasonably practical after they are electronically filed with, or furnished to, the SEC. Our principal executive offices are located at 26000 Commercentre Drive, Lake Forest, California 92630, and our telephone number is (949) 598-9242. Our Web site address is www.prim.com (http://www.prim.com). The information on our Internet Web site is neither part of nor incorporated by reference into this Third Quarter 2010 Report.

We provide services in three segments: the East Construction Services segment, the West Construction Services segment and the Engineering segment.

In prior periods, the Company reported two operating segments: the Construction Services segment and the Engineering segment. As a result of the acquisition of JCG and changes in the management structure, the Company changed the reportable operating segments on January 1, 2010, by separating the former Construction Services segment into two separate segments. The prior year information for the Construction Services segment has been reclassified into the two new segments. The three segments are outlined as follows:

The East Construction Services segment incorporates the JCG construction services business, located primarily in the southern United States, specializing in highway, industrial and environmental projects. The East Construction Services segment also consists of the businesses located in the Gulf Coast region of the United States that were formerly a part of the Construction Services segment, including Cardinal Contractors, Inc., Cardinal Mechanical, L.P. and Cravens Services, Inc. The East Construction Services segment provides a range of services that include:

  • Heavy civil construction projects including highway and bridge construction, paving, levee construction, airport runway and taxiway construction and marine facility construction;
  • Providing large earthwork and site development, site remediation and mining support services;
  • General construction and construction management of facilities and plants dedicated to water treatment, water reclamation and wastewater treatment and related systems; and
  • Providing installation and maintenance of infrastructure projects.

The West Construction Services segment includes construction services performed in the western United States, primarily in the states of California and Nevada. The entities that are included in West Construction Services include ARB, ARB Structures, Inc., and Stellaris, LLC. The West Construction Services segment provides a range of services that include:

  • Providing installation of underground pipeline, cable and conduits for entities primarily in the petroleum, petrochemical and gas industries and projects with water/wastewater distribution requirements;
  • Providing installation and maintenance of industrial facilities for entities in the power, petroleum and petrochemical industries;
  • Providing installation of complex commercial and industrial cast-in-place structures; and
  • Providing other earthwork, site development and remediation work.

The Engineering segment includes the results of Onquest and Born Heaters Canada, ULC (“Born Heaters”). The Engineering segment provides services that include:

  • Designing, supplying and installing high-performance furnaces, heaters, burner management systems and related combustion and process technologies for clients in the oil refining, petrochemical and power generation industries; and
  • Furnishing turn-key project management with technical expertise and the ability to deliver custom product engineering solutions worldwide.

The following table provides the historical revenues for the previously reported quarters for 2009 into the three new operating segments.

Segment: Three Months Ended March 31, 2009 (Thousands) June 30, 2009 September 30, 2009 December 31, 2009 Total 2009
East Construction Services $14,739 $13,459 $13,830 $26,987 $69,015
West Construction Services 90,044 92,788 80,933 76,456 340,221
Engineering 18,767 13,363 11,848 13,796 57,774
$123,550 $119,610 $106,611 $117,239 $467,010

Material trends and uncertainties

We generate our revenue from both large and small construction and product engineering projects. The award of these contracts is dependent on a number of factors, many of which are not within our control. Business in the construction industry is cyclical. We depend in part on spending by companies in the energy and oil and gas industries, as well as on municipal water and wastewater customers. Over the past few years, we have benefited from demand for more efficient and more environmentally friendly energy and power facilities and from the strength of the oil and gas industry.

Current economic conditions in the United States have affected our business during the past year, especially in our Industrial business in California and our water and wastewater business in Florida. While we currently have adequate backlog and projects to bid, we are uncertain as to how the current economy will impact our clients. Factors outside of our control may affect the number and size of contracts awarded to us in any particular period. It is possible that the current uncertainty for our business will continue as the impact of the American Recovery and Reinvestment Act (“ARRA”) of 2009 wanes and Federal highway funding legislation continues to be nearly non-existent.

Seasonality and cyclicality

Our operating results can be subject to seasonal and cyclical variations. Weather, particularly rain, can impact our ability to perform construction work. Our clients’ budget cycles also may have an impact on the timing of project awards. Accordingly, our financial condition and operating results may vary from quarter-to-quarter. Absent the awarding of a large project, the combination of weather and budget cycles suggest that revenues tend to be lowest in the first quarter of the year.

Results of operations

Revenues, gross profit, operating income and net income for the three months ended September 30, 2010 and 2009 were as follows:

(Thousands, except per share amounts)

(Thousands, except per share amounts)

Three Months Ended September 30, 2010 % of Revenue 2009 % of Revenue
Revenues $230,357 100.0% $106,611 100.0%
Gross profit 27,880 12.1% 20,154 18.9%
Selling, general and administrative expense 14,580 6.3% 7,266 6.8%
Operating income 13,300 5.8% 12,888 12.1%
Other income (expense) (81) 0.0% 961 0.9%
Income before income taxes 13,219 5.8% 13,849 13.0%
Income tax provision (5,642) (2.5)% (5,123) (4.8)%
Net income from continuing operations $7,577 3.3% $8,726 8.2%

Revenues, gross profit, operating income and net income for the nine months ended September 30, 2010 and 2009 were as follows:

(Thousands, except per share amounts)

(Thousands, except per share amounts)

Nine Months Ended September 30, 2010 % of Revenue 2009 % of Revenue
Revenues $608,526 100.0% $349,771 100.0%
Gross profit 78,989 13.0% 55,403 15.8%
Selling, general and administrative expense 43,849 7.2% 22,825 6.5%
Operating income 35,140 5.8% 32,578 9.3%
Other income (expense) 4 —% 4,466 1.3%
Income before income taxes 35,144 5.8% 37,044 10.6%
Income tax provision (13,782) (2.3)% (14,077) (4.0)%
Net income from continuing operations $21,362 3.5% $22,967 6.6%

Revenues for the three months ended September 30, 2010 were $230.4 million, an increase of $123.7 million or 116.1%, compared to the same period in 2009. The increase in revenues was due primarily to the acquisition of JCG and Cravens in the fourth quarter 2009, which contributed $120.2 million for the three months ended September 30, 2010. Revenues for the nine months ended September 30, 2010 were $608.5 million, an increase of $258.8 million, or 74.0%, compared to the same period in 2009. The acquired businesses contributed $329.1 million for the nine months ended September 30, 2010. Excluding the impact of the acquired businesses, revenues for the three months ended September 30, 2010 increased by $3.6 million, and declined by $70.3 million for the nine months ended September 30, 2010, compared to the same period a year ago. The decreased revenues were across most business lines, but especially in oil and gas pipeline, parking structures and industrial projects in the West Construction segment. This reflects the impact of a significant decrease of projects that were awarded in 2009.

Gross profit increased by $7.7 million, or 38.3% for the three months ended September 30, 2010 and increased by $23.6 million, or 42.6%, for the nine months ended September 30, 2010 compared to the same periods in 2009. This was due primarily to a $12.3 million and $34.3 million profit contribution from our recent acquisitions in the East Construction Services segment for the three and nine months ended September 30, 2010, respectively.

Gross profit as a percent of revenues decreased to 12.1% for the three months ended September 30, 2010 and 13.0% for the nine months ended September 30, 2010, respectively, compared to 18.9% and 15.8% in the same periods of 2009, respectively. The margins were primarily impacted by the typically lower margin percentages on JCG’s heavy civil projects and the lower utilization of equipment and manpower in the West Construction segment.

Geographic areas financial information

Revenue by geographic area for the nine months ended September 30, 2010 and 2009 was as follows:

Country: Nine Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
United States $593,458 97.5% $332,952 95.2%
Non—United States 15,068 2.5% 16,519 4.8%
Total revenues $608,526 100.0% $349,771 100.0%

All non-United States revenue has been generated in the Engineering Segment. The table above reflects non-United States revenues generated through our Canadian subsidiary, Born Heaters Canada, ULC.

Segment results

The following discusses the significant factors contributing to the results of our operating segments.

East Construction Services Segment

Revenue and gross profit for the East Construction Services segment for the three and nine months ended September 30, 2010 and 2009 were as follows:

East Construction Services Three Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
Revenue $126,876 $13,830
Gross profit 12,889 10.2% 1,383 10.0%
East Construction Services Nine Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
Revenue $351,583 $42,028
Gross profit 36,103 10.3% 4,441 10.6%

Revenue for the East Construction Services segment increased by $113.0 million and $309.6 million, respectively, for the three and nine months ended September 30, 2010 compared to the same periods in 2009. This increase was due to the addition of $120.2 million and $329.1 million in revenues attributable to the acquisition of JCG and Cravens in the fourth quarter 2009. This was partially offset by $7.2 million and $19.5 million decrease in revenue for the three and nine month periods ended September 30, 2010, primarily as a result of reduced revenues on Florida water and wastewater projects.

Gross profit for the East Construction Services segment increased by $11.5 million and $31.7 million for the three and nine months ended September 30, 2010, respectively, primarily as a result of the $12.2 million and $33.0 million gross margin contribution from the JCG acquisition compared to those of the water and wastewater projects in the same periods in 2009, respectively. Included in the gross profit amount is intangible amortization expense related to the JCG acquisition of $0.5 million for the three months and $1.7 million for the nine months ended September 30, 2010, respectively.

Gross profit as a percent of revenues increased to 10.2% during the three months ended September 30, 2010 from 10.0% in the prior year quarter, reflecting the increased margin percentages realized on JCG projects. For the nine months ended September 30, 2010, gross profit as a percent of revenues decreased to 10.3% compared to 10.6% in the same period in the prior year due to the typically lower margin percentages on JGC’s projects.

West Construction Services Segment

Revenue and gross profit for the West Construction Services segment for the three and nine months ended September 30, 2010 and 2009 were as follows:

West Construction Services Three Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
Revenue $86,594 $80,933
Gross profit 12,689 14.7% 17,449 21.6%
West Construction Services Nine Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
Revenue $216,302 $263,765
Gross profit 35,081 16.2% 46,664 17.7%

Revenue for the West Construction Services segment increased by $5.7 million, or 7.0%, and decreased by $47.5 million, or 18.0%, respectively, for the three and nine months ended September 30, 2010 compared to the same periods in 2009. The increase in the quarter ended September 30, 2010 as compared to the same period in 2009, was due to an increase in California underground water and sewer project work of $10.1 million, partially offset by a decrease in activity in the horizontal directional drilling projects and parking structure business. The decrease for the nine months ended September 30, 2010, as compared to the same period in 2009, was primarily due to a decline in project revenues from oil and gas pipelines of $20.8 million, power plant projects of $12.3 million and parking structure projects of $14.7 million.

Gross profit for the West Construction Services decreased by $4.8 million, or 27.3%, for the three months ended September 30, 2010 primarily as a result of a decline in gross profit of $2.0 million related to oil and gas pipeline projects and a decline of gross profit of $1.7 million in power plant projects, because of high profit margins in the same period of 2009. Gross profit for the nine months ended September 30, 2010 decreased by $11.6 million, or 24.8%, compared to the same period in 2009. Lower business volume accounts for $7.7 million of the gross profit decrease. The balance of the decrease was due to lower equipment and manpower utilization, primarily in the first quarter of 2010.

Gross profit as a percent of revenues decreased to 14.7% during the three months ended September 30, 2010 from 21.6% in the prior year quarter, reflecting high margins in the third quarter of 2009 primarily as a result of the completion of several higher margin projects in the previous year. For the nine months ended September 30, 2010, gross profit as a percent of revenues decreased to 16.2% compared to 17.7% in the same period in the prior year primarily due to the completion of several higher margin projects in the third quarter 2009.

Engineering Segment

Revenue and gross profit for the Engineering segment for the three and nine months ended September 30, 2010 and 2009 were as follows:

Engineering Three Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
Revenue $16,887 $11,848
Gross profit 2,302 13.6% 1,322 11.2%
Engineering Nine Months Ended September 30, 2010 (Thousands) % of Revenue 2009 (Thousands) % of Revenue
Revenue $40,641 $43,978
Gross profit 7,805 19.2% 4,299 9.8%

24

Revenue for the Engineering segment increased by $5.0 million, or 42.5%, for the three months ended September 30, 2010, compared to the same period in 2009, due to several new projects begun in the first six months of 2010. Revenue for the nine months ended September 30, 2010 decreased by $3.3 million, or 7.6%, compared to the same period in 2009. This decrease was due to slower activity in the first and second quarters of 2010, compared to the same periods in 2009.

Gross profit for the Engineering segment for the three months ended September 30, 2010 increased to $2.3 million from $1.3 million for the same period in 2009, an increase of $1.0 million. Gross margin as a percent of revenues was 13.6% compared to 11.2% for the same period in 2009. The increase was due primarily to the contribution from several higher than historical margin projects for the three months ended September 30, 2010.

Gross profit for the nine months ended September 30, 2010 increased $3.5 million over the same period in 2009, with gross profit as a percent of revenues increasing to 19.2% from 9.8% in the prior year. A significant portion of the increase was due to improvements in the final costs of several complex projects completed in 2010 compared to the estimated costs for these projects identified in the prior year. These improvements resulted in a favorable impact to gross profit of $1.9 million for the nine months ended September 30, 2010. Excluding the impact of these projects, gross profit for the current nine month period was $5.9 million, a net decrease of $0.3 million compared to the same period in the prior year. Excluding the impact of the reversal, gross profit as a percentage of revenues was 14.6% for the nine months ended September 30, 2010 compared to 14.0% for the same period in 2009.

Selling, general and administrative expenses

Selling, general and administrative expenses (“SG&A”) increased $7.3 million, or 100.7%, for the three months ended September 30, 2010 compared to the same period in 2009. Of the increased amount, approximately $5.7 million was added by the acquisitions of JCG and Cravens, including $0.9 million for amortization of intangible assets. The balance of the increase of $1.6 million was due primarily to recording $0.1 million gain on the sale of equipment during the three months ended September 30, 2010 compared to $1.7 million recorded during the same period in 2009.

SG&A increased by $21.0 million, or 92.1%, for the nine months ended September 30, 2010 compared to the same period in 2009. A total of $16.4 million of the increase was due to the acquisitions of JGC and Cravens during the fourth quarter of 2009, including $2.6 million for amortization of intangible assets. The remaining increase of $4.6 million was primarily due to lower overhead recovery allocation of $2.0 million as a result of reduced Engineering and non-JCG East Construction Segment activities, decreased gain on the sale of equipment of $1.9 million, and increased professional fees incurred as a result of the acquisitions of JCG of $1.0 million.

SG&A as a percentage of revenue decreased to 6.3% for the three months ended September 30, 2010, from 6.8% for the same period in 2009 and increased to 7.2% for the nine months ended September 30, 2010 compared to 6.5% for the same period in the prior year. Excluding the impact of amortization of intangible assets for the 2009 acquisitions, SG&A as a percentage of revenues was 5.9% and 6.8% for the three and nine months ending September 30, 2010, respectively.

Other income and expense

Non-operating income and expense items for the three and nine months ended September 30, 2010 and 2009 were as follows:

Other income (expense) Three Months Ended September 30, 2010 (Thousands) 2009
Income from non-consolidated investments $1,366 $1,439
Foreign exchange gain (loss) 80 (170)
Other income (expense) (333) —
Interest income 151 90
Interest (expense) (1,345) (398)
Total other income $(81) $961
Other income (expense) Nine Months Ended September 30, 2010 (Thousands) 2009
Income from non-consolidated investments $4,090 $5,342
Foreign exchange gain 266 33
Other expense (964) —
Interest income 484 554
Interest expense (3,872) (1,463)
Total other income $4 $4,466

25

For the three months ended September 30, 2010, income from non-consolidated joint ventures was $1.4 million which was primarily due to income from the St.-Bernard Levee Partners joint venture, a construction project near New Orleans, Louisiana. Income from non-consolidated joint ventures for the same period in 2009 amounted to $1.4 million, which consisted of income of $1.5 million from the Otay Mesa Power Partners (“OMPP”) joint venture, a power plant construction project near San Diego, California and a loss of $0.1 million from All Day Electric, an electrical construction company in Northern California.

Income from non-consolidated joint ventures for the nine months ended September 30, 2010 of $4.1 million included $4.4 million from the St.-Bernard Levee Partners joint venture, a loss of $0.1 million for All Day Electric, and $0.1 million loss from Wespac Energy, a developer of pipeline and terminal projects in which the Company acquired a 50% interest in July 2010. Income for the same period in 2009 was $5.3 million, which included $6.5 million from the OMPP joint venture, reduced by a loss of $0.2 million from All Day Electric and the $1.0 million reserve recorded for a foreign operation which was sold in the fourth quarter of 2009.

Foreign exchange gains for both the nine months ended September 30, 2010 and for the same period in 2009 reflect currency exchange fluctuations of the United States dollar compared to the Canadian dollar. Our contracts in Calgary, Canada are sold based on United States dollars, but a portion of the work is paid for with Canadian dollars, which can create a currency exchange difference.

Other expense reflects the change in the estimated fair value of the contingent earnout liabilities resulting from the acquisitions of JCG and Cravens in the fourth quarter 2009, which amounted to an expense of $0.3 million for the three months and $1.0 million during the nine months ended September 30, 2010, respectively.

For the three and nine months ended September 30, 2010, interest expense was $1.3 million and $3.9 million, respectively, compared to $0.4 million and $1.5 million for the same periods in 2009. The increase over both the prior periods was due primarily to interest payments due on the subordinated debt related to the JCG acquisition.

Provision for income taxes

Our provision for income tax increased $0.5 million for the three months ended September 30, 2010 to $5.6 million, and decreased $0.3 million for the nine months ended September 30, 2010 to $13.8 million, compared to the same periods in 2009. The tax rate applied in the three months ended September 30, 2010 was 42.7% as compared to 37.0% for the same period in 2009, and 39.2% for the nine months ended September 30, 2010 compared to 38.0% for the same period in 2009. A change in tax rates used depends on a combination of factors, including our estimated full year results and assumptions of our mix of revenues and profits in the various tax jurisdictions throughout the USA and Canada. Additionally, for the three months ended September 30, 2010, we recorded a one time tax charge of $0.8 million. This charge consists of truing up the tax returns filed for the year ended December 31, 2009 and calculating the look back interest payable on completed lump-sum projects with a sales price in excess of $1 million, and duration of more than two years.

Liquidity and Capital Resources

Liquidity represents our ability to pay our liabilities when they become due, fund business operations and meet our contractual obligations. Our primary sources of liquidity are our cash balances at the beginning of each period and our net cash flow. In addition to cash flow from operations, we have availability under our lines of credit to augment liquidity needs. In order to maintain sufficient liquidity, we evaluate our working capital requirements on a regular basis. We may elect to raise additional capital by issuing common stock, convertible notes, term debt or increasing our credit facility as necessary to fund our operations or to fund the acquisition of new businesses.

At September 30, 2010, our balance sheet included net cash and investments of $107.6 million, consisting of net cash of $81.6 million, and $26.0 million in short-term investments. We currently have the following credit facilities:

  • a $20 million credit facility which expires on October 28, 2013, under which we can issue letters of credit for up to $15 million. At September 30, 2010, we have issued letters of credit of $4.3 million on this facility, resulting in $15.7 million in available borrowing capacity;
  • a credit facility of $15 million, with the full borrowing amount available at September 30, 2010, which expires on October 27, 2011; and
  • a $10 million (Canadian dollars) facility for commercial letters of credit in Canada with an expiration date of December 31, 2012. At September 30, 2010, $5.0 million of letters of credit (Canadian dollars) were outstanding, with $5.0 million available under this credit facility for additional letters of credit.

Cash Flows

Cash flows during the nine months ended September 30, 2010 and 2009 are summarized as follows:

Change in cash: Nine Months Ended September 30, 2010 (Thousands) 2009
Net cash provided by operating activities $10,121 $22,326
Net cash used in investing activities (29,480) 5,193
Net cash provided by (used in) financing activities 11,823 (18,190)
Net cash used by discontinued operations (874) (2,920)
Net change in cash $(8,410) $6,409

Operating activities

The source of our cash flow from operating activities and the use of a portion of that cash in our operations for the nine months ended September 30, 2010 and 2009 were as follows:

Operating Activities: Nine Months Ended September 30, 2010 (Thousands) 2009
Operating Income $35,140 $32,578
Depreciation 12,575 5,918
Amortization of intangible assets 4,291 28
Gain on sale of property and equipment (1,352) (3,183)
Net deferred tax (1,598) (591)
Changes in assets and liabilities (30,511) (871)
Non-consolidated entity distributions 8,480 3,400
Foreign exchange gain 266 33
Other income (expense) (964) —
Change in contingent earnout liabilities 964 —
Interest income 484 554
Interest expense (3,872) (1,463)
Provision for income taxes (13,782) (14,077)
Net cash provided by operating activities $10,121 $22,326

Cash flow provided by operating activities for the nine months ended September 30, 2010 decreased by $12.2 million compared to the same period in 2009 due primarily to the increased use of cash related to changes in assets and liabilities of $29.5 million. This was partially offset by an increase in depreciation and amortization of intangible assets of $10.9 million as a result of the contribution of the JCG acquisition and interest expense of $2.4 million.

The changes in assets and liabilities decreased operating cash flow by $30.5 million in the nine months ended September 30, 2010, primarily as a result of the acquisition of JCG. The JCG acquisition increased accounts receivable by $35.4 million, offset by a $9.1 million increase in accounts payable, for a net increase of working capital of $26.3 million.

The components of the $30.5 million change in assets and liabilities, including the impact of the JCG acquisition, are included in the consolidated statements of cash flow. The following summarizes the significant changes:

  • a $40.5 million increase in accounts receivable. At September 30, 2010, accounts receivable represented 27.9% of total assets. We continue to have an excellent collection history for our receivables and have certain lien rights that can provide additional security for collection;
  • a $14.2 million increase in accounts payable (including $9.1 million increase due to the JCG acquisition);
  • costs and estimated earnings in excess of billings increased by $11.9 million;
  • billings in excess of costs and estimated earnings increased by $8.3 million;
  • inventory, prepaid expenses and other current assets increased by $4.7 million;
  • other long-term liabilities increased by $4.0 million;
  • accrued expenses and other current liabilities increased by $2.4 million; and
  • a $2.3 million increase in customer retention deposits.

Investing activities

During the nine month ended September 30, 2010, we purchased property and equipment for $17.8 million in cash, compared to $8.0 million during the same period in 2009. These purchases were principally for construction equipment, including the purchase of an equipment yard for $7.3 million in the Los Angeles area. We believe the ownership of equipment is generally preferable to renting equipment on a project by project basis, as ownership helps to ensure the equipment is available for our workloads when needed. In addition, ownership has historically resulted in lower overall equipment costs.

As part of our cash management program, we sold $4.1 million in short term investments during the nine months ended September 30, 2010. Our short term investments consist primarily of CDs purchased through the CDARS (Certificate of Deposit Account Registry Service) program to provide FDIC backing of the CDs.

In July 2010, we acquired a 50% interest in Wespac Energy, LLC for $18.1 million, which develops pipeline and terminal projects in the United States, Canada and Mexico. The investment is being accounted for under the equity method and is included on the balance sheet as investment in non-consolidated entities at September 30, 2010.

Financing activities

Financing activities provided $11.8 million of cash during the nine months ended September 30, 2010. Significant transactions using cash flows from financing activities included:

  • Proceeds from $20.0 million in long term debt for equipment financing. We secured these borrowings with existing equipment.
  • Cash distributions of $2.0 million were paid to the former members of JCG in January 2010. We provided this distribution to the former members of JCG, principally to allow them to pay their personal income tax liability stemming from the JCG profits prior to the December 2009 acquisition. This final distribution to the former members of JCG was made in accordance with the terms of the acquisition agreement.
  • $10.1 million in repayment of long-term debt and capital leases during the nine months ended September 30, 2010.
  • $10.4 million in payment of the subordinated note related to the JCG acquisition.
  • $3.2 million was paid as dividends to our stockholders during the nine months ended September 30, 2010, representing an annualized dividend rate of $0.10 per share of common stock (or $0.075 per share of common stock for the nine months ended September 30, 2010).
  • $17.8 million was received upon the conversion of warrants to common stock during the nine months ended September 30, 2010.

Capital requirements

We believe that we will be able to support our ongoing working capital needs for the next twelve months using cash on hand, short term investments, operating cash flows and the availability under our existing credit facilities.

Common stock

On July 31, 2008, the Company completed the merger (“Merger”) of Rhapsody Acquisition Corp. (the Company’s former name) and Primoris Corporation, a privately held Nevada corporation (“Former Primoris”). The July 2008 merger agreement provided that the Former Primoris stockholders would receive up to an additional 5.0 million shares of the Company’s common stock, contingent upon the combined company attaining certain financial targets in 2008 and 2009. The Company achieved the specified financial milestones for both 2009 and 2008. As a result, 2.5 million shares of common stock were issued to Former Primoris stockholders in March 2009 and 2.5 million shares of common stock were issued to Former Primoris stockholders in March 2010.

As part of the consideration for the acquisition of JCG, the Company issued 81,852.78 shares of Preferred Stock to JCG’s former members. On April 12, 2010, at a special meeting of the stockholders, the stockholders approved the conversion of the 81,852.78 shares of Preferred Stock into an aggregate of 8.18 million shares of common stock.

At September 30, 2010, there were 806,870 warrants outstanding to purchase the Company’s common stock. Each warrant entitled the holder to purchase one share of common stock at a price of $5.00 per share and was exercisable at any time on or prior to October 2, 2010 at 5:00 PM EDT (“Warrant”), unless earlier redeemed by the Company. From July 1, 2010 through September 30, 2010, a total of 2,742,154 warrants were exercised, with an additional 773,126 warrants exercised on October 1, 2010, resulting in cash proceeds paid to the Company of $17,576,400. The remaining 33,744 warrants expired unexercised on October 2, 2010.

On September 7, 2010, the Company adopted a Rule 10b5-1 trading plan with a broker to facilitate the repurchase of Warrants. From September 7, 2010 through the plan termination date of September 28, 2010, the broker completed the repurchase of 245,846 Warrants in accordance with the plan for $277,000.

At September 30, 2010, the Company had 450,000 Unit Purchase Options (“UPO”) outstanding. Each UPO entitled the holder to purchase one unit, comprised of one share of common stock and one Warrant, at a price of $8.80 per unit. The Warrants underlying the UPO’s also expired on October 2, 2010. As a result, the UPO’s, which will expire on October 2, 2011, now entitle the holder to purchase one share of common stock at a price of $8.80 per share.

Credit agreements

On October 28, 2009, we entered into a Loan and Security Agreement (the “Agreement”) with The PrivateBank and Trust Company (the “Lender”) for a revolving line of credit in the total aggregate amount of $35.0 million. The Agreement was amended on September 30, 2010 to extend the maturity dates of the two revolving loans provided under the Agreement. The maturity dates, as amended, are as follows:

  • a revolving loan in the amount of $20.0 million (the “Revolving Loan A”), with a maturity date of October 26, 2013; and
  • a revolving loan in the amount of $15.0 million (the “Revolving Loan B”), with a maturity date of October 26, 2011.

The Lender has agreed to issue for our account letters of credit of up to $15.0 million under Revolving Loan A. At September 30, 2010 and December 31, 2009, total commercial letters of credit outstanding under Revolving Loan A totaled $4.3 million and $0.85 million, respectively. There were no other borrowings under these two lines during the nine months ended September 30, 2010, leaving available borrowing capacity under Revolving Loan A at $15.7 million and $15.0 million under Revolving Loan B. The letters of credit may from time to time cover the risk of insurance deductible programs and can be drawn upon by the insurance company if we fail to pay the deductible of certain insurance policies in case of a claim.

The principal amount of each of Revolving Loan A and Revolving Loan B will bear interest at either: (i) LIBOR plus an applicable margin as specified in the Agreement, or (ii) the prime rate announced by the Lender plus an applicable margin as specified in the Agreement. The principal amount of any loan bearing interest at LIBOR plus an applicable margin may not be prepaid at any time without being subject to certain penalties. There is no prepayment penalty for any loan bearing interest at the prime rate announced by the Lender plus an applicable margin.

All loans made by the Lender under the Agreement are secured by our assets, including, among others, our cash, inventory, goods, equipment (excluding equipment subject to certain permitted liens) and accounts receivable. Certain of our subsidiaries have executed joint and several guaranties in favor of the Lender for all amounts under the Agreement. The Agreement and the line of credit facilities contain various restrictive covenants, including, among others, restrictions on investments, capital expenditures, minimum tangible net worth and debt service coverage requirements. The Company was in compliance with its restrictive covenants as of September 30, 2010.

In January 2008, the Company entered into a credit facility (as amended) for purposes of issuing commercial letters of credit in Canada, for an amount of up to $10.0 million in Canadian dollars. The credit facility with a Canadian bank is for a term of 5 years, and provides for an annual fee of 1% for any issued and outstanding commercial letters of credit. Letters of credit can be denominated in either Canadian or U.S. dollars. At September 30, 2010, total commercial letters of credit outstanding under this credit facility totaled $5.0 million in Canadian dollars and $5.5 million in Canadian dollars at December 31, 2009. As of September 30, 2010, the available borrowing capacity under this credit facility was $5.0 million in Canadian dollars.

Born Heaters Canada, one of our subsidiaries, has entered into contracts for the delivery of engineered equipment, which require letters of credit. These letters of credit may be drawn upon by the client in instances where Born Heaters Canada fails to provide the contracted services or equipment. Most of these letters of credit are for Canadian exports, of which 90% is guaranteed by the Economic Development Bank of Canada against “unfair” calling.

At the time of the JCG acquisition on December 18, 2009, the Company assumed outstanding letters of credit of $5.6 million under an amended credit agreement that expired on February 28, 2010. Upon termination of the credit agreement, the Company made a cash deposit as replacement for the letters of credit, and is recorded as a prepaid asset on the Company’s balance sheet.

Related party transactions

We have entered into various transactions with Stockdale Investment Group, Inc. (“SIGI”). Brian Pratt, one of our largest stockholders and our Chief Executive Officer, President and Chairman of the Board of Directors, holds a majority interest in SIGI and is the chairman and a director of SIGI. In addition, John M. Perisich, our Senior Vice President and General Counsel, is secretary of SIGI.

We lease properties located in Bakersfield, Pittsburg and San Dimas, California, and in Pasadena, Texas for SIGI. During the nine months ended September 30, 2010 and 2009, we paid $0.67 million and $0.61 million, respectively, in lease payments to SIGI for the use of these properties. These leases with SIGI were entered into on similar terms that we believe would have been negotiated with an independent third party. Also, SIGI occupies certain space in our corporate offices and pays a pro rata portion of facility costs based on square footage occupied.

We lease a property from Roger Newnham, a manager at our subsidiary, Born Heaters Canada. The property is located in Calgary, Canada. During the nine months ended September 30, 2010 and 2009, we paid $0.19 million and $0.26 million, respectively, in lease payments to Mr. Newnham for the use of this property. The three-year lease for the Calgary property began in October 2005 and has been renewed and extended until December 31, 2014.

We own several non-consolidated investments and we recognized revenues on work performed for those joint ventures. ARB recognized $0.08 million and $13.2 million in project revenues during the nine months ended September 30, 2010 and 2009, respectively, on the OMPP joint venture. ARB also recognized $1.3 million and $1.0 million in project revenues during the nine months ended September 30, 2010 and 2009, respectively on the All Day joint venture.

Contractual obligations

At September 30, 2010, we had $54.7 million of outstanding debt and capital lease obligations, and $43.1 million of subordinated debt.

A summary of contractual obligations at September 30, 2010 were as follows:

Payments due by period Total (Thousands) 1 Year 2-3 Years 4-5 Years After 5 Years
Debt and capital lease obligations $54,660 $12,047 $24,462 $15,334 $2,817
Interest on debt and capital lease obligations 6,531 2,500 3,177 731 123
Subordinated debt 43,116 23,952 19,164 — —
Interest on subordinated debt 3,201 1,886 1,315 — —
Equipment operating leases 5,565 3,928 1,637 — —
Real property leases 11,123 1,900 2,506 1,916 4,801
Real property leases—related parties 7,254 1,138 2,372 1,985 1,758
$131,450 $47,351 $54,633 $19,966 $9,499
Stand-by letters of credit $9,292 $2,147 $3,383 $3,762 $—

The interest amount above represents interest payments for our fixed rate debt assuming that principal payments are made as originally scheduled.

Off balance sheet transactions

The following represent transactions, obligations or relationships that could be considered material off-balance sheet arrangements.

  • Letters of credit issued under our lines of credit. At September 30, 2010, we had letters of credit outstanding of $9.3 million.
  • Equipment operating leases with a balance of $5.6 million at September 30, 2010.
  • In the ordinary course of our business, we may be required by our customers to post surety bid or completion bonds in connection with services that we provide. At September 30, 2010 we had $902.4 million in outstanding bonds.

Backlog

In the industries in which we operate, backlog can be considered an indicator of potential future performance because it represents a portion of the future revenue stream. Different companies in our industry define backlog differently. We consider backlog as the anticipated revenue from the uncompleted portions of existing contracts. We calculate backlog differently for different types of contracts. For our fixed price and fixed unit price contracts, we include the full remaining portion of the contract in our calculation. We do not include time-and-equipment, time-and-materials and cost-plus contracts in the calculation of backlog, as their ultimate revenue amount is difficult to determine.

Any contract, including fixed price contracts, may be terminated by our customers on relatively short notice. In the event of a project cancellation, we may be reimbursed for certain costs, but typically, we have no contractual right to the total revenues reflected in backlog. Projects may remain in backlog for extended periods of time, especially with the longer-term nature of the JCG heavy civil highway projects.

At September 30, 2010, our total backlog was $967.5 million representing an increase of $172.1 million, or 21.6%, from our total backlog of $795.4 million at December 31, 2009. We expect that approximately $187.3 million, or 19.4%, of the total backlog at September 30, 2010, will be recognized as revenue during the remainder of 2010, with $107.2 million expected for the East Construction segment, $67.6 million for the West Construction segment and $12.5 million for the Engineering segment.

Backlog by operating segment at September 30, 2010 and December 31, 2009 was as follows:

Segment: September 30, 2010 Amount (Thousands, except % amounts) Percentage As Adjusted (1) December 31, 2009 Amount Percentage As Reported December 31, 2009 Amount Percentage
East Construction Services $649,355 67.1% $572,545 74.8% $572,545 72.0%
West Construction Services 271,149 28.0% 136,722 17.9% 166,822 21.0%
Engineering 47,026 4.9% 56,012 7.3% 56,012 7.0%
$967,530 100.0% $765,279 100.0% $795,379 100.0%

(1) In July 2009, we announced demobilization of a construction project at Chevron Corp’s Richmond Refinery located on Contra Costa, California. The project was performed under a contract from Praxair, Inc. At December 31, 2009, approximately $40 million was included in the backlog amount shown for West Construction Services segment.

In April 2010, the California Court of Appeals ruled that there were deficiencies in the Environment Impact Report for the project, and at the same time, Praxair, Inc. provided us with a notice of termination for the project. In accordance with the terms of our contract, the project converted from a fixed price contract to a reimbursed cost plus margin contract. Due to the termination, we adjusted our cost estimates for the contract and reduced the contingent amounts normally associated with fixed price contracts, which resulted in a reduction of approximately $30 million in our backlog amount at December 31, 2009, as set forth in the table above. In the nine months ended September 30, 2010, we recognized revenues of $10.1 million related to this project and at September 30, 2010 have a remaining backlog amount of $0.01 million for this project.

In accordance with the terms of the contract, Praxair, Inc. has engaged a firm to perform an audit of the costs related to the project. We do not anticipate that the results of the audit will have a material impact on our financial condition, results of operations and cash flows.

Our backlog at any point in time may not accurately represent the revenue that we expect to realize during any period. Additionally, our backlog at the end of the period may not be indicative of the revenue we expect to earn over the course of the following twelve months.

Market risk

As filed, 1,429 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

In the ordinary course of business, we are exposed to risks related to market conditions. These risks primarily include fluctuations in foreign currency exchange rates, interest rates and commodity prices. We may seek to manage these risks through the use of financial derivative instruments. These instruments may include foreign currency exchange contracts and interest rate swaps.

We do not execute transactions or use financial derivative instruments for trading or speculative purposes. We enter into transactions with counter parties that are generally financial institutions in a matter to limit significant exposure with any one party.

The carrying amounts for cash and cash equivalents, accounts receivable, long-term debt and accounts payable and accrued liabilities shown in the consolidated balance sheets approximate fair value at September 30, 2010 and December 31, 2009 due to the generally short maturities of these items. At September 30, 2010, we invested primarily in short-term dollar denominated bank deposits. We expect to hold our investments to maturity.

At September 30, 2010, all of our long-term debt was under fixed interest rates.

At September 30, 2010, we had no derivative financial instrument for the purpose of hedging future currency exchange rates in Canadian dollars. We intend to continue to hedge foreign currency risks in those situations where we believe such transactions are prudent.

Controls and procedures

As filed, 1,844 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Disclosure Controls and Procedures

As of September 30, 2010, we carried out an evaluation, under the supervision and with the participation of our management, including our chief executive officer (“CEO”) and chief financial officer (“CFO”), of the effectiveness of the design and operation of our “disclosure controls and procedures”, as such term is defined under Exchange Act Rules 13a-15(e) and 15d-15(e).

Based on this evaluation, our CEO and CFO concluded that, at September 30, 2010, the disclosure controls and procedures were effective at the reasonable assurance level to ensure that information required to be disclosed by us in the reports we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the rules and forms of the SEC, and accumulated and communicated to our management, including our CEO and CFO, as appropriate to allow timely decisions regarding required disclosure.

In designing and evaluating the disclosure controls and procedures, our management recognized that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objectives and in reaching a reasonable level of assurance our management necessarily was required to apply its judgment in evaluating the cost-benefit relationship of possible controls and procedures. The Company’s disclosure controls and procedures are designed to provide reasonable assurance of achieving their stated objectives.

Changes in Internal Control Over Financial Reporting

During the last fiscal quarter ended September 30, 2010, there were no changes in our internal control over financial reporting that materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.

Risk factors

As filed, 610 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

In addition to the other information set forth in this Report, you should carefully consider the factors discussed in the section entitled “ Risk Factors “ in our Annual Report on Form 10-K for the year ended December 31, 2009, which to our knowledge have not materially changed. Those risks, which could materially affect our business, financial condition or future results, are not the only risks we face. Additional risks and uncertainties not currently known to us or that we currently deem to be immaterial also may materially adversely affect our business, financial condition and/or operating results.

Source: SEC EDGAR, the filing index for accession 0001104659-10-057108. Last ingested by Listed: Nov 13, 2026, 16:58 ET. Listed shows no prices and gives no investment advice.