Primoris Services Corp: Form 10-Q for the period ended Mar 31, 2016
Filed with the SEC on May 6, 2016 and accepted by EDGAR at May 6, 2016, 16:45 ET.
Management's discussion and analysis
As filed, 52,897 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Forward Looking Statements
This Quarterly Report on Form 10-Q for the quarterly period ended March 31, 2016 (“First Quarter 2016 Report”) contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), which are subject to the “safe harbor” created by those sections. Forward-looking statements include information concerning our possible or assumed future results of operations, business strategies, financing plans, competitive position, industry environment, potential growth opportunities, the effects of regulation and the economy, generally. Forward-looking statements include all statements that are not historical facts and can be identified by terms such as “anticipates”, “believes”, “could”, “estimates”, “expects”, “intends”, “may”, “plans”, “potential”, “predicts”, “projects”, “should”, “will”, “would” or similar expressions.
Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. We discuss many of these risks in detail in Part I, Item 1A “Risk Factors” of our Annual Report on Form 10-K for the year ended December 31, 2015 and our other filings with the Securities and Exchange Commission (“SEC”). You should read this First Quarter 2016 Report, our Annual Report on Form 10-K for the year ended December 31, 2015 and our other filings with the SEC completely and with the understanding that our actual future results may be materially different from what we expect.
Given these uncertainties, you should not place undue reliance on these forward-looking statements. Also, forward-looking statements represent our management’s beliefs and assumptions only as of the date of this First Quarter 2016 Report. We assume no obligation to update these forward-looking statements publicly, or to update the reasons actual results could differ materially from those anticipated in any forward-looking statements, even if new information becomes available.
The following discussion and analysis should be read in conjunction with the unaudited financial statements and the accompanying notes included in Part 1, Item 1 of this First Quarter 2016 Report and our Annual Report on Form 10-K for the year ended December 31, 2015.
Introduction
Primoris is a holding company of various subsidiaries, which form one of the larger publicly traded specialty contractors and infrastructure companies in the United States. Serving diverse end-markets, we provide a wide range of construction, fabrication, maintenance, replacement, water and wastewater, and engineering services to major public utilities, petrochemical companies, energy companies, municipalities, state departments of transportation and other customers. We install, replace, repair and rehabilitate natural gas, refined product, water and wastewater pipeline systems; large diameter gas and liquid pipeline facilities; and heavy civil projects, earthwork and site development. We also construct mechanical facilities and other structures, including power plants, petrochemical facilities, refineries, water and wastewater treatment facilities and parking structures. Finally, we provide specialized process and product engineering services.
We have longstanding customer relationships with major utility, refining, petrochemical, power and engineering companies. We have completed major underground and industrial projects for a number of large natural gas transmission and petrochemical companies in the western United States, as well as significant projects for our engineering customers. We enter into a large number of contracts each year and the projects can vary in length — from several weeks, to as long as 48 months for completion on larger projects. Although we have not been dependent upon any one customer in any year, a small number of customers tend to constitute a substantial portion of our total revenues.
We recognize revenues and profitability on our contracts depending on the type of contract. For our fixed price, or lump sum, contracts, we record revenue as the work progresses on a percentage-of-completion basis which means that we recognize revenue based on the percentage of costs incurred to date in proportion to the total estimated costs expected to complete the contract. Fixed price contracts may include retainage provisions under which customers withhold a percentage of the contract price until the project is complete. For our unit price, time and material, and cost-plus contracts, we recognize revenue as units are completed or services are performed.
The Company segregates its business into three operating segments, which include: The West Construction Services segment (“West segment”), the East Construction Services segment (“East segment”) and the Energy segment. The following is a brief description of each of our reportable segments and business activities.
The West segment includes the underground and industrial operations and construction services performed by ARB, Inc. (“ARB”), ARB Structures, Inc., Rockford Corporation (“Rockford”), Q3 Contracting, Inc. (“Q3C”), and Vadnais Trenchless
Services, Inc. (“Vadnais”). ARB and ARB Structures perform work primarily in California; while, Rockford operates throughout the United States and Q3C operates in Colorado and the upper Midwest United States. The segment also included two joint venture operations. The West segment consists of business headquartered primarily in the western United States.
The East segment includes the James Construction Group (“JCG”) Heavy Civil division, the JCG Infrastructure and Maintenance division, BW Primoris, LLC and Cardinal Contractors, Inc. construction business, located primarily in the southeastern United States and in the Gulf Coast region of the United States and includes heavy civil construction and infrastructure and maintenance operations.
The Energy segment businesses are located primarily in the southeastern United States and in the Gulf Coast region of the United States. The segment includes the operations of the Primoris Energy Services (“PES”) pipeline and gas facility construction and maintenance operations, the PES Industrial division, the Ram-Fab operations and the Primoris Aevenia, Inc. (“Aevenia”) operations. Additionally, the segment includes the OnQuest, Inc. (“OnQuest”) and OnQuest Canada, ULC operations for the design and installation of high-performance furnaces and heaters for the oil refining, petrochemical and power generation industries.
The following table lists the Company’s primary operating subsidiaries and their operating segment:
| Subsidiary | Operating Segment |
|---|---|
| ARB, Inc. (“ARB”) | West |
| ARB Structures, Inc. | West |
| Q3 Contracting, Inc. (“Q3C”) | West |
| Rockford Corporation (“Rockford”) | West |
| Vadnais Trenchless Services, Inc. (“Vadnais”) | West |
| Cardinal Contractors, Inc. | East |
| BW Primoris, LLC (“BWP”) | East |
| James Construction Group, LLC (“JCG”): | |
| JCG Heavy Civil Division | East |
| JCG Infrastructure and Maintenance Division | East |
| Primoris Energy Services Corporation (“PES”) | Energy |
| PES Pipeline Services | Energy |
| PES Industrial Division (formerly JCG Industrial Division) | Energy |
| OnQuest, Inc. | Energy |
| OnQuest, Canada, ULC | Energy |
| Primoris Aevenia, Inc. (“Aevenia”); acquired February 28, 2015 | Energy |
The Company owned 50% of the Blythe Power Constructors joint venture (“Blythe”) created for the installation of a parabolic trough solar field and steam generation system in California, and its operations have been included as part of the West segment. The project has been completed, the project warranty expired in May 2015 and dissolution of the joint venture was completed in the third quarter 2015.
The Company owns a 50% interest in two separate joint ventures, both formed in 2015 to engineer and construct gas-fired power generation facilities: Carlsbad Power Constructors joint venture (“Carlsbad”) and ARB Inc. & B&M Engineering Co. joint venture (“Wilmington”). Both projects are located in the Southern California area. The Carlsbad project is expected to be completed in 2017 and the Wilmington project in 2018. The joint venture operations are included as part of the West segment. As a result of determining that the Company is the primary beneficiary of the two VIE’s, the results of the Carlsbad and Wilmington joint ventures are consolidated in the Company’s financial statements.
On February 28, 2015, the Company acquired the net assets of Aevenia, Inc. for $22.3 million in cash, and established a new entity, Primoris Aevenia, Inc. (“Aevenia”), which operates as part of the Company’s Energy segment. Headquartered in Moorhead, Minnesota, Aevenia is an energy and electrical construction company. Aevenia specializes in overhead and underground line work, substations, telecom/fiber, and certain other client-specific on-demand call out services. The majority of their work is delivered under unit-price Master Services Agreements (“MSAs”). Aevenia has operations in Minnesota, North Dakota, South Dakota and Iowa. The Company believes there are opportunities for Aevenia to grow sales by performing in-house work for other Primoris subsidiaries and to expand the Company’s offerings to new geographies in the Midwest United States. On January 29, 2016, the Company acquired the net assets of Mueller Concrete Construction Company (“Mueller”) for $4.1 million. Mueller will operate as a division of Aevenia.
For some end markets we perform the same services in each of our West, East and Energy segments, while for other end markets, such as poured-in-place parking structures, only one of our segments currently serves the market. The following table shows the approximate percentage of revenues over three years derived from our major end-markets, with prior periods conformed to the current year market breakdown:
| Market | Twelve Months Ended March 2016 | Twelve Months Ended December 2015 | Twelve Months Ended March 2015 |
|---|---|---|---|
| Underground capital projects | 11% | 12% | 17% |
| Utility services | 34% | 34% | 30% |
| Industrial | 17% | 16% | 23% |
| Heavy Civil | 30% | 30% | 23% |
| Engineering | 3% | 4% | 4% |
| Other | 5% | 4% | 3% |
| Total | 100% | 100% | 100% |
Material trends and uncertainties
We generate our revenue from both large and small construction and engineering projects. The award of these contracts is dependent on many factors, most of which are not within our control. We depend in part on spending by companies in the energy and oil and gas industries, the gas utility industry, as well as municipal water and wastewater customers. Over the past several years, each segment has benefited from demand for more efficient and more environmentally friendly energy and power facilities, local highway and bridge needs and from the activity level in the oil and gas industry; however, each of these industries and the government agencies periodically are adversely affected by macroeconomic conditions. Economic factors outside of our control may affect the amount and size of contracts we are awarded in any particular period.
We closely monitor our customers to assess the effect that changes in economic, market and regulatory conditions may have on them. We have experienced reduced spending by some of our customers over the last several years, which we attribute to negative economic and market conditions, and we anticipate that these negative conditions may continue to affect demand for our services in the near-term. Major fluctuations in market prices of oil, gas and other fuel sources have affected demand for our services. The recent significant reduction in the price of oil, gas and liquid natural gas has created uncertainty with respect to demand for our oil and gas pipeline and roustabout services in the near term, with additional uncertainty resulting over the length of time that prices will remain depressed. We believe that our upstream operations, such as the construction of gathering lines within the oil shale formations will remain at lower levels for an extended period. While there was some improvement in the price of oil in the first quarter of 2016, the increase has not resulted in a significant change in the contracting activities of our customers. We believe that over time, the need for pipeline infrastructure for mid-stream and utility companies will result in a continuing need for our services, but the impact of the low oil prices and the bankruptcy of some smaller oil and gas producers may delay midstream pipeline opportunities. The continuing changes in the regulatory environment also affects the demand for our services, either by increasing our work or delaying projects. For example, the regulatory environment in California may well result in delays for the construction of gas-fired power plants while the regulators continue to search for significant renewable resources, but the renewable resources may also create a demand for our construction services. Finally, we believe that regulated utility customers will continue to invest in our maintenance and replacement services.
Seasonality, cyclicality and variability
Our results of operations are subject to quarterly variations. Some of the variation is the result of weather, particularly rain, ice and snow, which can impact our ability to perform construction services. While the majority of the Company’s work is in the southern half of the United States, these seasonal impacts affect revenues and profitability since gas and other utilities defer routine replacement and repair during their period of peak demand. Any quarter can be affected either negatively or positively by atypical weather patterns in any part of the country. In addition, demand for new projects tends to be lower during the early part of the year due to clients’ internal budget cycles. As a result, the Company usually experiences higher revenues and earnings in the third and fourth quarters of the year as compared to the first two quarters.
The Company is also dependent on large construction projects which tend not to be seasonal, but can fluctuate from year to year based on general economic conditions. Our business may be affected by declines or delays in new projects or by client project schedules. Because of the cyclical nature of our business, the financial results for any period may fluctuate from prior periods, and the Company’s financial condition and operating results may vary from quarter-to-quarter. Results from one quarter may not be indicative of its financial condition or operating results for any other quarter or for an entire year.
Critical Accounting Policies and Estimates
The preparation of financial statements in conformity with accounting principles generally accepted in the United States requires us to make estimates and assumptions that affect the reported amounts of assets and liabilities and the disclosure of contingent assets and liabilities as of the date of the financial statements and that affect the amounts of revenues and expenses reported for each period. These estimates and assumptions must be made because certain information that is used in the preparation of our financial statements cannot be calculated with a high degree of precision from data available, is dependent on future events, or is not capable of being readily calculated based on generally accepted methodologies. Often, these estimates are particularly difficult to determine, and we must exercise significant judgment. We use estimates in our assessments of revenue recognition under percentage-of-completion accounting, the allowance for doubtful accounts, useful lives of property and equipment, fair value assumptions in analyzing goodwill and long-lived asset impairments, self-insured claims liabilities and deferred income taxes. Actual results could differ significantly from our estimates, and our estimates could change if they were made under different assumptions or conditions.
As described in our Annual Report on Form 10-K for the year ended December 31, 2015, our critical accounting policies relate primarily to revenue recognition for fixed and unit price contracts, income taxes, goodwill, long-lived assets, reserves for uninsured risks and litigation and contingencies. There have been no material changes to our critical accounting policies since December 31, 2015.
Results of operations
Revenues, gross profit, operating income and net income for the three months ended March 31, 2016 and 2015 were as follows:
| Three Months Ended March 31, 2016 (Thousands) | % of Revenue | 2015 (Thousands) | % of Revenue | |
|---|---|---|---|---|
| Revenues | $430,446 | 100.0% | $392,780 | 100.0% |
| Gross profit | 39,277 | 9.1% | 38,005 | 9.7% |
| Selling, general and administrative expense | 32,658 | 7.6% | 33,760 | 8.6% |
| Operating income | 6,619 | 1.5% | 4,245 | 1.1% |
| Other income (expense) | (1,870) | (0.4)% | (1,518) | (0.4)% |
| Income before income taxes | 4,749 | 1.1% | 2,727 | 0.7% |
| Income tax provision | (1,833) | (0.4)% | (1,055) | (0.3)% |
| Net income | $2,916 | 0.7% | $1,672 | 0.4% |
| Net income attributable to noncontrolling interests | (223) | (0.1)% | — | —% |
| Net income attributable to Primoris | $2,693 | 0.6% | $1,672 | 0.4% |
Revenues
Revenues for the three months ended March 31, 2016 increased by $37.7 million, or 9.6% compared to the same period in 2015. Revenues increased in both the East and Energy segments while revenue decreased in the West segment. The East and Energy segments were not as significantly impacted by rainy weather in 2016 compared to the prior period and benefitted from a large construction project in southern Louisiana, in part resulting in increases in revenue compared to the decreases in the prior period with more severe, rainy weather. West segment revenues were impacted primarily by the prior year completion of a large Rockford pipeline project in the Houston area.
From an end-market perspective, our end-market revenues during the first quarter of 2016 compared to the prior year increased by $22.4 million for the industrial end-market, $9.5 million for the underground utility end-market, $20.1 million for the heavy civil end-market and $20.0 million for other markets. Revenues decreased by $20.7 million with underground capital end-market and by $13.6 million with the engineering end-market.
Gross Profit
For the three months ended March 31, 2016, gross profit grew slightly by $1.3 million, with the East and Energy segments increasing by $9.0 million as a result of the increased revenues, offset by a decrease of $7.7 million in the West segment. Gross profit as a percent of revenue decreased to 9.1% for the three months ended March 31, 2016, compared to 9.7% for the same period in 2015, reflecting the impact of changes in the mix of work done for two large utility customers in California.
Selling, general and administrative expenses
Selling, general and administrative expenses (“SG&A”) decreased $1.1 million, or 3.3%, for the three months ended March 31, 2016, compared to the same period in 2015. As a result of the completion of settlement discussions by the PLCA, the pension withdrawal liability was reduced by $0.8 million during the first quarter of 2016. Reductions in administration and payroll related expenses primarily accounted for the remainder of the decreased amount.
SG&A as a percentage of revenue for the three months ended March 31, 2016 decreased to 7.6% compared to 8.6% for the corresponding period in 2015 as a result of the decreases in SG&A expenses for the period.
Other income and expense
Non-operating income and expense items for the three months ended March 31, 2016 and 2015 were as follows:
| Three Months Ended March 31, 2016 (Thousands) | 2015 | |
|---|---|---|
| Foreign exchange gain | $359 | $436 |
| Other expense | — | (44) |
| Interest income | 39 | 12 |
| Interest expense | (2,268) | (1,922) |
| Total other income (expense) | $(1,870) | $(1,518) |
25
For the three months ended March 31, 2016, foreign exchange gains and losses reflect currency exchange fluctuations of the United States dollar compared to the Canadian dollar. Many of our contracts in Calgary, Canada are sold based on United States dollars, but a portion of the work is paid for with Canadian dollars creating a positive currency exchange difference as the value of the Canadian dollar is less than the US dollar.
Interest income is derived from interest earned on excess cash invested primarily in short term U.S. Treasury bills, backed by the federal government and other investments that may not be backed by the federal government.
The increase in interest expense for the three months ended March 31, 2016 is due to a higher debt level for equipment debt and senior secured notes.
Provision for income taxes
Our provision for income taxes increased $0.7 million for the three months ended March 31, 2016 to $1.8 million compared to $1.1 million in the same period in 2015 primarily as a result of higher income before taxes and a higher effective tax rate. The tax rate applied to income attributable to Primoris in the three months ended March 31, 2016 was 40.5%, compared to 38.7% for the same period in 2015. The 1.8% increase in the effective tax rate resulted primarily from the variability of state taxes and the partial non-deductibility of meals and incidental per diem expenses.
To determine our quarterly provision for income taxes, we use an estimated annual effective tax rate, which is based on expected annual income, statutory tax rates and tax planning opportunities available in the various jurisdictions in which we operate. Certain significant or unusual items are separately recognized in the quarter in which they occur and can be a source of variability in the effective tax rate from quarter to quarter.
Segment results
West Segment
Revenue and gross profit for the West segment for the three months ended March 31, 2016 and 2015 were as follows:
| Three Months Ended March 31, 2016 (Thousands) | % of Revenue | 2015 (Thousands) | % of Revenue | |
|---|---|---|---|---|
| Revenue | $165,955 | $186,385 | ||
| Gross profit | $13,798 | 8.3% | $21,464 | 11.5% |
Revenue for the West segment decreased by $20.4 million, or 11.0%, for the three months ended March 31, 2016, compared to the same period in 2015. The decrease was primarily the result of a decrease in volume at Rockford of $46.2 million, the result of the 2015 completion of an 88-mile pipeline project in the Houston, Texas area. The decrease was partially offset by increased revenues of $14.6 million at the ARB Structures division from the construction of several parking structures in southern California; increased revenues of $8.9 million at Q3C as the weather improved earlier in 2016 and increased revenue of $3.5 million at the ARB Underground division, primarily from work for its two largest utility customers.
Gross profit for the West segment decreased by $7.7 million, or 35.7%, during the three months ended March 31, 2016, compared to the same period in 2015. While the improved weather resulted in an increase of $2.6 million at Q3C, Rockford gross margin was reduced by $2.4 million, primarily from completion of the 88-mile pipeline project in the prior year. In addition, gross margin at the ARB Underground division was reduced by $4.4 million, primarily from a change in the mix of work done for its two largest utility customers. As occurs frequently in the first quarter of a year, this mix of work reflects a significant reduction in the higher margin work, such as pipeline integrity services. At the ARB Industrial division gross margin was reduced by $2.5 million, primarily from an increase in costs to complete a southern California power plant project during 2016.
Gross profit as a percentage of revenue decreased to 8.3% during the three months ended March 31, 2016, from 11.5% in the same period in 2015 primarily as a result of decreased margins at the entities discussed above.
East Segment
Revenue and gross profit for the East segment for the three months ended March 31, 2016 and 2015 were as follows:
| Three Months Ended March 31, 2016 (Thousands) | % of Revenue | 2015 (Thousands) | % of Revenue | |
|---|---|---|---|---|
| Revenue | $147,971 | $123,700 | ||
| Gross profit | $11,522 | 7.8% | $9,108 | 7.4% |
East Segment revenue increased by $24.3 million, or 19.6 %, for the three months ended March 31, 2016 compared to the same period in 2015. JCG’s Heavy Civil division revenue increased by $16.3 million as increases of $20.4 million from Texas DOT and municipal projects, $4.1 million from LA DOT projects and $3.2 million from Arkansas DOT projects were partially offset by a decrease of $13.1 million from MS DOT projects. Revenue at the JCG Infrastructure & Maintenance division increased by $3.1 million primarily as a result of an increase at a large petrochemical project in Louisiana. Cardinal Contractors revenue increased $3.8 million primarily from an increase in wastewater facility work in the Texas market.
Gross profit increased by $2.4 million or 26.5% for the three months ended March 31, 2016. The gross profit increase was primarily at JCG’s Infrastructure and Maintenance division, which increased $2.3 million. Some of the increase at both the JCG Heavy Civil division and Cardinal Contractors was for jobs for which loss provisions were recognized in earlier quarters, and as a result, for these jobs no gross margin is recognized in the current period.
Gross profit as a percent of revenues increased to 7.8% during the three months ended March 31, 2016 from 7.4% in the same period ended March 31, 2015 due to increased margins at the JCG Infrastructure and Maintenance division.
Energy Segment
Revenue and gross profit for the Energy segment for the three months ended March 31, 2016 and 2015 were as follows:
| Three Months Ended March 31, 2016 (Thousands) | % of Revenue | 2015 (Thousands) | % of Revenue | |
|---|---|---|---|---|
| Revenue | $116,520 | $82,695 | ||
| Gross profit | $13,957 | 12.0% | $7,433 | 9.0% |
Revenue for the Energy segment increased by $33.8 million, or 40.9%, for the three months ended March 31, 2016, compared to the same period in 2015. Revenues for the PES Pipeline division increased by $24.7 million primarily as a result of increased revenues from capital projects. The Industrial division of PES experienced an increase in revenues of $23.6 million as increased work on a petrochemical project in south Louisiana offset decreases from the completion of prior year projects. Revenues decreased at OnQuest by $13.6 million primarily as a result of the completion of an LNG project in the first quarter of 2015.
Gross profit for the Energy segment for the three months ended March 31, 2016 increased by $6.5 million or 87.8%, compared to the same period in 2015. The increase is mainly the result of the increased revenues from PES, offset by reduced gross profit on the decreased revenues at OnQuest.
Gross profit as a percent of revenues increased to 12.0% during the three months March 31, 2016, from 9.0% in the prior period, primarily from the impact of the south Louisiana project.
Geographic area financial information
The majority of the Company’s revenues are derived from customers in the United States with approximately 1% generated from sources outside of the United States.
Backlog
For companies in the construction industry, backlog can be an indicator of future revenue streams. Different companies define and calculate backlog in different manners. For the Company, backlog is defined as a combination of: (1) anticipated revenue from the uncompleted portions of existing contracts for which we have known revenue amounts such as for fixed price and fixed unit price contracts (“Fixed Backlog”), and (2) the estimated revenues on master service agreements (“MSA”) for the next four quarters (“MSA Backlog”). We normally do not include time-and-equipment, time-and-materials and cost reimbursable plus fee contracts in the calculation of backlog, since their ultimate revenue amount is difficult to estimate in advance. We will include these types of contracts in backlog if the customer specifies an anticipated revenue amount.
The two components of backlog, Fixed Backlog and MSA Backlog, are detailed below.
Fixed Backlog
Fixed Backlog by operating segment as of December 31, 2015 and March 31, 2016 and the changes in Fixed Backlog for the three months ended March 31, 2016 (in millions) are as follows:
| Segment | Beginning Fixed Backlog at December 31, 2015 | Contract Additions to Fixed Backlog | Revenue Recognized from Fixed Backlog | Ending Fixed Backlog at March 31, 2016 | Revenue Recognized from Non-Fixed Backlog Projects | Total Revenue for three months ended March 31, 2016 |
|---|---|---|---|---|---|---|
| West | $577.1 | $214.3 | $72.2 | $719.2 | $93.7 | $165.9 |
| East | 752.3 | 111.9 | 144.0 | 720.2 | 4.0 | 148.0 |
| Energy | 187.8 | 43.3 | 106.3 | 124.8 | 10.2 | 116.5 |
| Total | $1,517.2 | $369.5 | $322.5 | $1,564.2 | $107.9 | $430.4 |
Revenues recognized from non-Fixed Backlog projects shown above are generated by projects completed under time-and-equipment, time-and-materials and cost-reimbursable-plus-fee contracts or are revenue from the sale of construction materials, such as rock or asphalt to outside third parties.
As of March 31, 2016, our total Fixed Backlog was $1.56 billion representing an increase of $47.0 million, or 3.1% compared to the $1.52 billion as of December 31, 2015. We expect that approximately 67% of the total Fixed Backlog at March 31, 2016, will be recognized as revenue over the next four quarters, with approximately $522 million expected for the West segment, $404 million for the East segment and $122 million for the Energy segment.
MSA Backlog
The following table outlines historical MSA revenues for the past five quarters ($ in millions):
| Quarterly MSA Revenues | |
|---|---|
| First Quarter — 2015 | 90.7 |
| Second Quarter — 2015 | 134.1 |
| Third Quarter — 2015 | 175.6 |
| Fourth Quarter — 2015 | 164.7 |
| First Quarter — 2016 | 105.2 |
MSA Backlog includes anticipated MSA revenues for the next twelve months. We estimate MSA revenues based on historical trends, anticipated seasonal impacts and estimates of customer demand based on information from our customers.
The following table shows our estimated MSA Backlog at March 31, 2016 by operating segment (in millions):
| Segment: | MSA Backlog at March 31, 2016 |
|---|---|
| West | $564.6 |
| East | 4.0 |
| Energy | 61.9 |
| Total | $630.5 |
28
Total Backlog
The following table shows total backlog (Fixed Backlog plus MSA Backlog), by operating segment as of the quarter-end dates shown below (in millions):
| Segment: | March 31, 2015 | June 30, 2015 | September 30, 2015 | December 31, 2015 | March 31, 2016 |
|---|---|---|---|---|---|
| West | $848.6 | $972.7 | $949.3 | $1,077.3 | $1,283.8 |
| East | 962.9 | 935.7 | 810.9 | 756.3 | 724.2 |
| Energy | 331.8 | 290.6 | 289.6 | 254.3 | 186.7 |
| Total | $2,143.3 | $2,199.0 | $2,049.8 | $2,087.9 | $2,194.7 |
Backlog should not be considered a comprehensive indicator of future revenues, as a percentage of our revenues are derived from projects that are not part of a backlog calculation. The backlog estimates include amounts from estimated MSA revenues, but our customers are not contractually obligated to purchase an amount of services from us under the MSAs. Any of our contracts, MSA, fixed price or fixed unit price, may be terminated by our customers on relatively short notice. In the event of a project cancellation, we may be reimbursed for certain costs, but typically we have no contractual right to the total revenues reflected in backlog. Projects may remain in backlog for extended periods of time as a result of customer delays, regulatory requirements or project specific issues. Future revenues from projects completed under time-and-equipment, time-and-materials and cost-reimbursable-plus-fee contracts may not be included in our estimated backlog amount.
Liquidity and Capital Resources
Cash Needs
Liquidity represents our ability to pay our liabilities when they become due, fund business operations and meet our contractual obligations and execute our business plan. Our primary sources of liquidity are our cash balances at the beginning of each period and our net cash flow. If needed, we have availability under our lines of credit to augment liquidity needs. In order to maintain sufficient liquidity, we evaluate our working capital requirements on a regular basis. We may elect to raise additional capital by issuing common stock, convertible notes, term debt or increasing our credit facility as necessary to fund our operations or to fund the acquisition of new businesses.
Our cash and cash equivalents totaled $98.8 million at March 31, 2016 compared to $161.1 million at December 31, 2015. The primary reason for the decrease was to fund the working capital needs of construction projects and other operating needs of the Company. We anticipate that our cash and investments on hand, existing borrowing capacity under our credit facility and our future cash flows from operations will provide sufficient funds to enable us to meet our operating needs, our planned capital expenditures and our ability to grow for at least the next twelve months.
The construction industry is capital intensive, and we expect to continue to make capital expenditures to meet anticipated needs for our services. Historically, we have invested an amount that approximated the sum of depreciation and amortization expenses plus proceeds from equipment sales. During the three months ended March 31, 2016, capital expenditures were approximately $12.3 million while the amount of depreciation, amortization and equipment sales during this period was approximately $20.2 million. Capital expenses are expected to total $55 to $60 million for the 2016 year.
Cash Flows
Cash flows during the three months ended March 31, 2016 and 2015 are summarized as follows:
| Change in cash: | Three months Ended March 31, 2016 (Thousands) | 2015 |
|---|---|---|
| Net cash (used in) provided by operating activities | $(35,608) | $2,018 |
| Net cash (used in) investing activities | (13,057) | (35,562) |
| Net cash (used in) provided by financing activities | (13,648) | 97 |
| Net change in cash and cash equivalents | $(62,313) | $(33,447) |
29
Operating Activities
The source of our cash flow from operating activities and the use of that cash in our operations for the three months ended March 31, 2016 and 2015 were as follows:
| Operating Activities: | Three months Ended March 31, 2016 (Thousands) | 2015 | Change |
|---|---|---|---|
| Operating income | $6,619 | $4,245 | $2,374 |
| Depreciation and amortization | 16,905 | 15,505 | 1,400 |
| Stock-based compensation expense | 262 | 262 | — |
| Loss (gain) on sale of property and equipment | (736) | 510 | (1,246) |
| Changes in assets and liabilities | (54,955) | (15,931) | (39,024) |
| Net other income (expense) and tax provision | (3,703) | (2,573) | (1,130) |
| Net cash (used by) provided by operating activities | $(35,608) | $2,018 | $(37,626) |
The net change in assets and liabilities during the three months ended March 31, 2016 resulted in a use of cash of $55.0 million, compared to $15.9 million in the prior year, an increase in the usage of cash of $39.0 million. The $39.0 million change in assets and liabilities is outlined below:
- The increased use of cash relating to construction projects, which included the change in accounts receivable, customer retention deposits, costs and estimated earnings in excess of billings and billings in excess of costs and estimated earnings totaled $59.1 million. This increase in the use of cash was primarily due to the increase in revenues of $37.7 million for the three months ended March 31, 2016 compared to the same period in 2015 and a greater activity level at the end of March 2016 compared to December 2015 resulting in a greater level of unbilled revenues at the end of the first quarter.
The primary changes for the use of cash of $59.1 million from December 31, 2015 to March 31, 2016 were as follows:
- Accounts receivable increased by $20.5 million reflecting the higher revenues during the three months ended March 31, 2016 compared to the first quarter of 2015. The primary reason for the increase was the increase in accounts receivable for the large south Louisiana project. The customer was in compliance with the contractual terms at the end of the first quarter. At March 31, 2016 accounts receivable represented 30.6% of our total assets compared to 28.3% at the end of 2015. With the exception of two specific collection issues on two large projects (see the discussion in the “Receivable Collection Actions” below), we continue to maintain an excellent collection history, and we have certain lien rights that can provide additional security for collections;
- Costs and estimated earnings in excess of billings increased by $24.2 million. The increases are primarily associated with the time lag from when revenues were earned until the customer can be billed, which are the result of either contractual terms or the billing lag at the end of each month. The increase during the quarter was approximately $9.2 million for ARB, $7.2 million for PES, $5.4 million for Rockford and $2.4 million for the other operations; and
- Billings in excess of costs and estimated earnings decreased by $14.2 million reflecting the completion of work paid for in advance.
- Primarily as a result of increased revenues, accounts payable increased by $12.0 million in the first quarter of 2016, compared to a decrease in accounts payable of $8.5 million in the first quarter of 2015. This resulted in a decrease of $20.5 million of cash usage for the first quarter of 2016 compared to the same quarter in 2015.
- At March 31, 2016 there were no earn-out liabilities, which was a decrease of $5.0 million compared to the liability at March 31, 2015.
- Uninstalled inventory decreased by $0.5 million in the first quarter of 2016 compared to an increase of $2.5 million in the first quarter of 2015. This resulted in a decrease of $3.0 million of cash usage for the first quarter of 2016 compared to the same quarter in 2015.
- Accrued expenses and other current liabilities decreased by $3.5 million in the first quarter of 2016, compared to a decrease of $6.4 million in the first quarter of 2015. This resulted in an increase of $2.9 million of cash for the first quarter of 2016 compared to the same quarter in 2015.
Investing activities
During the three months ended March 31, 2016, we purchased property and equipment for $12.3 million in cash compared to $16.6 million during the same period in the prior year. We believe that ownership of equipment is generally preferable to renting equipment on a project-by-project basis, as ownership helps to ensure the equipment is available for our workloads when needed. Over the past years, ownership has resulted in lower overall equipment costs.
Historically, we have invested an amount that approximated the sum of depreciation and amortization expenses plus proceeds from equipment sales. Capital expenditures, primarily for construction equipment, are expected to total $55 million to $60 million for 2016 which would be in line with our historical practice.
We periodically sell and acquire equipment, typically to update our fleet. We received proceeds from the sale of used equipment of $3.3 million during the three months ending March 31, 2016 and $2.8 million during the same period in 2015.
On January 29, 2016, we purchased the net assets of Mueller for $4.1 million in cash and in the prior year, on February 28, 2015, we purchased the net assets of Aevenia for $22.3 million in cash.
Financing activities
Financing activities used cash of $13.6 million for the three months ended March 31, 2016, which was net of several transactions, which included:
- $12.0 million in repayment of long-term debt and the repayment of $0.3 million in capital leases;
- Dividend payments of $2.8 million to our stockholders during the three months ended March 31, 2016; and
- $1.4 million in proceeds from the issuance of 85,907 shares of common stock purchased by the participants in the Primoris Long-term Retention Plan.
Debt Activities
For a description of our credit agreements, see Note 10 — “Credit Agreements” in Item 1, Financial Statements of this First Quarter 2016 Report.
Related party transactions
Primoris has entered into leasing transactions with Stockdale Investment Group, Inc. (“SIGI”). Brian Pratt, our Chairman of the Board of Directors and our largest stockholder, holds a majority interest and is the chairman, president and chief executive officer and a director of SIGI. John M. Perisich, our Executive Vice President and General Counsel, is secretary of SIGI.
Primoris leases properties from SIGI at the following locations:
1. Bakersfield, California (lease expires October 2022)
2. Pittsburg, California (lease expires April 2023)
3. San Dimas, California (lease expires March 2019)
During the three months ended March 31, 2016 and 2015, the Company paid $0.21 million in both periods in lease payments to SIGI for the use of these properties.
Primoris leases a property from Roger Newnham, a former owner and current employee of our subsidiary, OnQuest Canada, ULC. The property is located in Calgary, Canada. During the three months ended March 31, 2016 and 2015, Primoris paid $0.06 million and $0.07 million, respectively, in lease payments. The current term of the lease is through December 31, 2017.
Primoris leases a property from Lemmie Rockford, one of the Rockford sellers, which commenced November 1, 2011. The property is located in Toledo, Washington. During the three months ended March 31, 2016 and 2015, Primoris paid $0.02 million in both periods in lease payments. The lease expires in January 2017.
Primoris leases a property from Quality RE Partners, owned by three of the Q3C selling shareholders, of whom two are current employees, including Jay Osborn, an operations president in the West Construction segment. The property is located in Little Canada, Minnesota. During the three months ended March 31, 2016 and 2015, the Company paid $0.07 million in both periods, in lease payments to Quality RE Partners. The lease expires in October 2022.
Primoris leases property from the sellers of the Mueller acquisition, which commenced January 29, 2016. The property is located in Iowa. During the three months ended March 31, 2016, the Company paid three thousand dollars in lease payments to the sellers.
Common stock
For a discussion of items affecting our common stock, please see Note 17 — “Stockholders’ Equity” in Item 1, Financial Statements of this First Quarter 2016 Report.
Contractual Obligations
As of March 31, 2016, we had $263.0 million of outstanding long-term debt and capital lease obligations and there were no short-term borrowings.
A summary of contractual obligations as of March 31, 2016 was as follows:
(In Thousands)
| Total | 1 Year | 2 - 3 Years | 4 - 5 Years | After 5 Years | |
|---|---|---|---|---|---|
| Long-term debt and capital lease obligations | $263,040 | $52,989 | $95,449 | $65,410 | $49,192 |
| Interest on long-term debt (1) | 28,582 | 7,145 | 10,602 | 6,006 | 4,829 |
| Equipment operating leases | 12,184 | 6,325 | 5,399 | 460 | — |
| Real property leases | 10,547 | 3,408 | 5,458 | 1,681 | — |
| Real property leases—related parties | 7,248 | 1,455 | 2,559 | 1,586 | 1,648 |
| $321,601 | $71,322 | $119,467 | $75,143 | $55,669 | |
| Letters of credit | $17,361 | $12,361 | $5,000 | $— | $— |
(1) The interest amount represents interest payments for our fixed rate debt assuming that principal payments are made as originally scheduled.
The table does not include obligations under multi-employer pension plans in which some of our employees participate. Our multi-employer pension plan contribution rates are generally specified in our collective bargaining agreements, and contributions are made to the plans based on employee payrolls. Our obligations for future periods cannot be determined because we cannot predict the number of employees that we will employ at any given time nor the plans in which they may participate.
We may also be required to make additional contributions to multi-employer pension plans if they become underfunded, and these contributions will be determined based on our union payroll. The Pension Protection Act of 2006 added special funding and operational rules for multi-employer plans that are classified as “endangered,” “seriously endangered” or “critical” status. Plans in these classifications must adopt measures to improve their funded status through a funding improvement or rehabilitation plan, which may require additional contributions from employers. The amounts of additional funds that we may be obligated to contribute cannot be reasonably estimated and is not included in the table above.
In November 2011, members of the Pipe Line Contractors Association “PLCA” including ARB, Rockford and Q3C (prior to the Company’s acquisition in 2012), withdrew from the Central States Southeast and Southwest Areas Pension Fund multiemployer pension plan (“Plan”). These withdrawals were made in order to mitigate additional liability in connection with the significantly underfunded Plan. The Company recorded a withdrawal liability of $7.5 million, which was increased to $7.6 million after the acquisition of Q3C, based on information provided by the Plan. The Plan asserted that the PLCA members did not affect a proper withdrawal in 2011, and in May 2014, the Plan asserted that the total liability for the Company was $11.8 million. A legal proceeding commenced, and a United States District Court ruled that the withdrawal of the PLCA members in 2011 was not effective. The PLCA appealed this decision, but as required by the Plan, the Company began making monthly payments, including interest, which totaled $1.8 million through December 31, 2015. The payments were expensed as they were made.
On September 2, 2015, the U.S. Court of Appeals for the 7th Circuit reversed the decision of the District Court and ruled that the withdrawal was effective in 2011 as had been asserted by the PLCA. The Plan provided the Company with a revised withdrawal liability amount which was approximately the amount originally accrued. During the first quarter of 2016, the Company received a revised payment schedule reflecting all the prior payments. Based on this schedule, the Company determined that its liability was $6,468 at March 31, 2016. While the Company and other members of the PLCA are engaged in arbitration to further reduce the amount owed, the Company will make payments as required by the Plan-provided payment schedule.
We have also excluded from the table any interest and fees associated with letters of credit and commitment fees under our credit facility since these amounts are variable.
Off-balance sheet transactions
As is common in our industry, we enter into certain off-balance sheet arrangements in the ordinary course of business that result in risks not directly reflected on our balance sheet. We have no off-balance sheet financing arrangement with variable interest entities. The following represent transactions, obligations or relationships that could be considered material off-balance sheet arrangements.
- Letters of credit issued under our lines of credit. At March 31, 2016, we had letters of credit outstanding of $17.4 million, primarily for international project engineering jobs in our Energy segment and for providing security to our insurance carriers. These letters of credit are used by some of our vendors to ensure reimbursement for amounts that they are disbursing on our behalf, such as beneficiaries under our self-funded insurance program. In addition, from time to time, certain customers require us to post a letter of credit to ensure payments to our subcontractors or guarantee performance under our contracts. Letters of credit reduce our borrowing availability under our Credit Agreement and Canadian Credit Facility. If these letters of credit were drawn on by the beneficiary, we would be required to reimburse the issuer of the letter of credit, and we may be required to record a charge to earnings for the reimbursement. As of the date of this First Quarter 2016 Report, we do not believe that it is likely that any material claims will be made under a letter of credit;
- We enter into non-cancellable operating leases for some of our facilities, equipment and vehicles, including leases with related parties. At March 31, 2016, equipment operating leases had a remaining commitment of $12.2 million and facility rental commitments were $17.8 million;
- In the ordinary course of our business, we may be required by our customers to post surety bid or completion bonds in connection with services that we provide. At March 31, 2016, we had $1.5 billion in outstanding bonds. As of the date of this First Quarter 2016 Report, we do not believe that it is likely that we would have to fund material claims under our surety arrangements;
- As discussed in the previous section, “Contractual Obligations”, certain of our subsidiaries are parties to collective bargaining agreements with unions which may create future obligations not recorded on our balance sheet;
- Other guarantees that we make from time to time, such as guaranteeing the obligations of our subsidiaries; and
- Employment agreements with executive officers or with executives from acquired companies may create obligations.
Receivable Collection Actions
At March 31, 2016, the Company is engaged in dispute resolution to enforce collection for two construction projects completed by the Company in 2014. For one project, a cost reimbursable contract, the Company has recorded a receivable of $32.9 million, and for the other project, the Company has a receivable balance due of $17.9 million. At March 31, 2016, the Company has not recorded revenues in excess of cost for these two projects; however, the Company has specific reserves for both projects of approximately $26 million included in “billings in excess of costs and estimated earnings.” At this time, the Company cannot predict the amount that it will collect nor the timing of any collection.
The dispute resolution for the $32.9 million receivable involves contractually required international arbitration for four separate construction projects. As part of the process of filing claims and counter-claims with the arbitration tribunal, the Company determined in the fourth quarter of 2015 that there were no remaining claims from the owner for two of the smaller projects for which the Company had been paid in full. As a result, the Company recorded approximately $2 million in revenues and margin in that quarter. During the three months ended March 31, 2016, the owner sought bankruptcy protection in U.S. bankruptcy court. In addition, the Company has pending litigation against the sureties who provided lien and stop payment release bonds for the total amount owed.
The second project (reflecting the balance due of $17.9 million) involved two small jobs (with separate contracts) that were part of the larger project. A dispute over the termination of these two small jobs was mediated by the owner and Company in April 2016. As a result of the mediation, the Company recorded additional revenue and profit of $0.5 million during the first quarter 2016.
Effects of Inflation and Changing Prices
Our operations are affected by increases in prices, whether caused by inflation or other economic factors. We attempt to recover anticipated increases in the cost of labor, equipment, fuel and materials through price escalation provisions in certain major contracts or by considering the estimated effect of such increases when bidding or pricing new work or by entering into back-to-back contracts with suppliers and subcontractors.
Market risk
As filed, 1,338 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
In the ordinary course of business, we are exposed to risks related to market conditions. These risks primarily include fluctuations in foreign currency exchange rates, interest rates and commodity prices. We may seek to manage these risks through the use of financial derivative instruments. These instruments may include foreign currency exchange contracts and interest rate swaps.
We do not execute transactions or use financial derivative instruments for trading or speculative purposes. We enter into transactions with counter parties that are generally financial institutions in a matter to limit significant exposure with any one party.
At March 31, 2016, we had no derivative financial instruments.
The carrying amounts for cash and cash equivalents, accounts receivable, short-term debt, accounts payable and accrued liabilities shown in the consolidated balance sheets approximate fair value at March 31, 2016 and December 31, 2015, due to the generally short maturities of these items. At March 31, 2016, we held no short term investments. In the periods where we have, we generally invest in in U.S. Treasury bills with various financial institutions that are backed by the federal government. We expect to hold our investments to maturity.
At March 31, 2016, all of our long-term debt was subject to fixed interest rates.
Controls and procedures
As filed, 2,029 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Disclosure Controls and Procedures
As of March 31, 2016, we carried out an evaluation, under the supervision and with the participation of our management, including our chief executive officer (“CEO”) and chief financial officer (“CFO”), of the effectiveness of the design and operation of our “disclosure controls and procedures”, as such term is defined under Exchange Act Rules 13a-15(e) and 15d-15(e).
Based on this evaluation, our CEO and CFO concluded that, at March 31, 2016, the disclosure controls and procedures were effective at the reasonable assurance level to ensure that information required to be disclosed by us in the reports we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the rules and forms of the SEC, and accumulated and communicated to our management, including our CEO and CFO, as appropriate to allow timely decisions regarding required disclosure.
In designing and evaluating the disclosure controls and procedures, our management recognized that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objectives. In reaching a reasonable level of assurance, our management necessarily was required to apply its judgment in evaluating the cost-benefit relationship of possible controls and procedures. The Company’s disclosure controls and procedures are designed to provide reasonable assurance of achieving their stated objectives. We anticipate continuing enhancement of our controls, especially as we complete the process of integrating our financial and operations information systems onto a common platform.
Changes in Internal Control Over Financial Reporting
During the fiscal quarter ended March 31, 2016, there were no changes to our internal control over financial reporting practices or processes that materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.
Risk factors
As filed, 602 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
In addition to the information set forth in this Report, you should carefully consider the factors discussed in the section entitled “Risk Factors” in our Annual Report on Form 10-K for the year ended December 31, 2015, which to our knowledge have not materially changed. Those risks, which could materially affect our business, financial condition or future results, are not the only risks we face. Additional risks and uncertainties not currently known to us or that we currently deem to be immaterial also may materially adversely affect our business, financial condition and/or operating results.
Figures reported in this filing
Standardized line items from the XBRL in this filing, for the period ended 2016-03-31. Comparative periods it repeats are left out.
| Line item | Period | Value | XBRL concept |
|---|---|---|---|
| Cost of revenue | 3 months2016-01-01 to 2016-03-31 | $391.2m | us-gaap:CostOfServices |
| Gross profit | 3 months2016-01-01 to 2016-03-31 | $39.3m | us-gaap:GrossProfit |
| Selling, general and administrative | 3 months2016-01-01 to 2016-03-31 | $32.7m | us-gaap:SellingGeneralAndAdministrativeExpense |
| Operating income | 3 months2016-01-01 to 2016-03-31 | $6.6m | us-gaap:OperatingIncomeLoss |
| Interest expense | 3 months2016-01-01 to 2016-03-31 | $2.3m | us-gaap:InterestExpense |
| Income tax | 3 months2016-01-01 to 2016-03-31 | $1.8m | us-gaap:IncomeTaxExpenseBenefit |
| Diluted EPS | 3 months2016-01-01 to 2016-03-31 | $0.05 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months2016-01-01 to 2016-03-31 | $0.05 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months2016-01-01 to 2016-03-31 | 51,881,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 3 months2016-01-01 to 2016-03-31 | −$35.6m | us-gaap:NetCashProvidedByUsedInOperatingActivitiesContinuingOperations |
| Capital expenditure | 3 months2016-01-01 to 2016-03-31 | $12.3m | us-gaap:PaymentsToAcquirePropertyPlantAndEquipment |
| Dividends paid | 3 months2016-01-01 to 2016-03-31 | $2.8m | us-gaap:PaymentsOfDividendsCommonStock |
| Cash and equivalents | At period end2016-03-31 | $98.8m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | At period end2016-03-31 | $672.7m | us-gaap:AssetsCurrent |
| Total assets | At period end2016-03-31 | $1.12bn | us-gaap:Assets |
| Current liabilities | At period end2016-03-31 | $407.6m | us-gaap:LiabilitiesCurrent |
| Total liabilities | At period end2016-03-31 | $629.7m | us-gaap:Liabilities |
| Long-term debt | At period end2016-03-31 | $210.0m | us-gaap:LongTermDebtNoncurrent |
| Current portion of debt | At period end2016-03-31 | $52.3m | us-gaap:LongTermDebtCurrent |
| Shareholders' equity | At period end2016-03-31 | $485.7m | us-gaap:StockholdersEquityIncludingPortionAttributableToNoncontrollingInterest |