Management's discussion and analysis

As filed, 6,028 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

construction of the Generation Assets. The aggregate cost of the Generation Assets, together with the cost to develop related transmission infrastructure (collectively, the “Contract Assets”), is currently estimated to be approximately $7 billion. The EPC Contracts provide certain protections against cost overruns, and any excess costs with respect to the EPC Contracts beyond those protections, or arising apart from the EPC Contracts are, unless otherwise agreed by the parties, shared by Customer and NIPSCO (for transmission) and GenCo (for generation). If the Contract Assets are delivered into service late or do not achieve certain performance-related milestones, Customer is entitled to liquidated damages, subject to a cap and offset against the regular charges paid by the Customer.

Either party may terminate the Data Center Contract upon certain defaults or failure to obtain necessary related approvals from the IURC and FERC. Customer may terminate the Data Center Contract for convenience following certain notice periods and also has a one-time option (exercisable no later than March 31, 2029) to halve the committed capacity under the Data Center Contract to 1,200 MW commencing January 31, 2032. If Customer terminates for convenience, exercises its reduction option or defaults, NIPSCO or its affiliates will be reimbursed for investment costs, subject to agreed caps based on cost estimates by year as of signing. NIPSCO’s aggregate liability, including liquidated damages, is subject to a cap.

NIPSCO’s and GenCo’s operations under the Data Center Contract will be regulated by the IURC in a different way from the regulatory mechanisms applicable to NIPSCO’s historical operations. The terms of the Data Center Contract were determined by commercial negotiation with the Customer. These terms include the charges we receive from the Customer and provisions that may result in adjustments to such charges, including those relating to certain liquidated damages that we may owe Customer in the event of construction delays or capacity shortfalls, the parties’ responsibility to share cost overruns, certain changes in law and force majeure events. The IURC will not regulate the commercial terms of the Data Center Contract; however, the IURC will maintain oversight under the Data Center Contract to ensure NIPSCO provides reliable service to the Customer at just and reasonable rates. In order to recover our investment costs and earn our return under the Data Center Contract, our subsidiaries must efficiently perform their own obligations and must look to the Customer (or its parent guarantor) to perform its obligations, rather than the IURC making use of its traditional rate-making process. In addition, under the Data Center Contract, NIPSCO has direct contractual obligations to the Customer to, among other things, construct the Contract Assets and deliver committed electric capacity in fixed amounts by certain dates.

Data Center Strategy

We continue to experience strong demand from potential data center customers in our northern Indiana service territory and are engaged in negotiations with potential counterparties. Through certain of our subsidiaries, we have entered into certain construction and equipment supply contracts in relation to additional generation and transmission assets that may be used to serve potential future data center customers. As we continue to evaluate our potential data center opportunities, we will continue to focus on the community, financial, operational and regulatory factors that must be managed effectively in order to succeed with our data center strategy. We believe data center development can enhance our local tax base, diversify the employment base across the state of Indiana, and provide greater value to existing customers and shareholders. We continually evaluate ways to effectively manage the potential power demand, generation sources, and transmission capabilities to meet potential further load growth from additional data center customers, while at the same time focusing on our environmental goals.

In order to perform under any further data center contracts, we expect that we would need to develop additional generation and transmission assets and obtain additional financing in connection with such development. For these and other reasons, our ability to successfully execute our data strategy is subject to a number of risks and uncertainties. Refer to Part II, Item 1A, “Risk Factors” for a discussion of certain risks relating to our data center strategy.

Energy Transition: We continue to advance our energy transition strategy, primarily through the continuation and enhancement of existing programs, such as implementing our plan to retire and replace remaining coal-fired electric generation by 2028 with a balanced mix of low- or zero-emission electric generation, ongoing pipe replacement and modernization programs, and deployment of advanced leak detection and repair. Our electric generation transition, initiated through our 2018 Integrated Resource Plan ("2018 Plan") is well underway, and we are continually adjusting to the dynamic energy landscape. As of September 30, 2025, we have placed in service owned renewable and storage projects with combined nameplate capacities of 1,950 MW and 101 MW respectively. Renewable PPA projects with a combined nameplate capacity of 1,000 MW have also been placed in service. In addition, a renewable BTA project with a nameplate capacity of 200 MW, and a renewable PPA project with a nameplate capacity of 195 MW were under development as of September 30, 2025, all of which have received IURC approval. For additional information, see Note 14, "Other Commitments and Contingencies - D. Other Matters". We are continuing to evaluate the development of federal and state executive orders, or other regulatory actions, with respect to our generation transition plans. Absent a directive to remain open, we remain on track to retire R.M. Schahfer's remaining two

Market risk

As filed, 197 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Quantitative and qualitative disclosures about market risk are reported in Item 2, "Management's Discussion and Analysis of Financial Condition and Results of Operations - Market Risk Disclosures."

Controls and procedures

As filed, 1,835 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Evaluation of Disclosure Controls and Procedures

Our chief executive officer and our chief financial officer are responsible for evaluating the effectiveness of our disclosure controls and procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)). Our disclosure controls and procedures are designed to provide reasonable assurance that the information required to be disclosed by us in reports that we file or submit under the Exchange Act is accumulated and communicated to our management, including our chief executive officer and chief financial officer, as appropriate, to allow timely decisions regarding required disclosure and is recorded, processed, summarized and reported within the time periods specified in the rules and forms of the SEC. Based upon that evaluation, our chief executive officer and chief financial officer concluded that, as of the end of the period covered by this report, our disclosure controls and procedures were effective at a reasonable assurance level.

Changes in Internal Controls

During the third quarter, we implemented the second and third phases of our three-phased Enterprise Asset Management ERP program. This implementation reflects our ongoing commitment to streamlining operations and enhancing logistics across the company. While there are inherent risks involved with the implementation of new systems and changes in internal controls associated with the transition to the new system, management believes it is adequately monitoring and managing the transition. Apart from this ERP implementation, there have been no changes in our internal control over financial reporting that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting during the most recently completed quarter covered by this report.

Risk factors

As filed, 6,619 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

existing indebtedness. The LLC Agreement and Amended LLC Agreement will allow for additional capital contributions from affiliates of Blackstone to NIPSCO Holdings II and Generation Holdings II in connection with such Blackstone affiliates’ minority interest investments in those entities. In addition, we may consider other funding sources, structures, or partnerships as market conditions and strategic considerations evolve. The amount of additional long-term debt or NiSource equity needed to support construction of the Contract Assets and any generation and transmission assets to support future data center contracts could increase, potentially significantly, from our current expectations if we experience construction delays or cost overruns.

External factors such as inflation, monetary policy or other market conditions could impact our cost of borrowing and could make it more difficult to obtain the financing that is required to construct the Contract Assets on favorable terms, or at all. The issuance of additional debt could negatively impact our credit ratings and overall cost of capital, which could in turn adversely affect our future results and liquidity. In addition, an economic downturn or uncertainty, market turmoil, changes in interest rates, changes in tax policy, challenges faced by financial institutions, or a change in investor sentiment toward us or the utilities industry or the cloud-computing, artificial intelligence and data center industry generally could adversely affect our ability to raise the necessary capital. Reduced access to capital markets, increased borrowing costs, and/or lower equity valuation levels could jeopardize our ability to complete construction of the Contract Assets on-time and within budget, and could reduce future earnings per share and cash flows. In addition, any rise in interest rates may lead to higher borrowing costs, which may adversely impact reported earnings, cost of capital and capital holdings.

Pursuit of our partnership with Customer creates significant opportunity costs and reduces our strategic and financial flexibility in the near term.

We expect to incur significant indebtedness to fund our construction of the Contract Assets. Doing so will reduce our ability to incur further indebtedness to pursue other strategic opportunities, such as partnerships with other large data center customers or strategic mergers and acquisitions, while at the same time maintaining our investment grade credit ratings, which may require us to rely to a greater degree on equity financing in connection with future data center contracts and also may increase our reliance on equity financing for future investments in our existing traditionally regulated utility business, each of which could lead to substantial dilution of our existing shareholders. In addition, our credit rating agencies consider the percentage of our business comprised of traditionally regulated utility operations in their analysis of our credit quality.

In addition to these factors relating to our financing and credit ratings, our partnership with Customer is expected to employ a significant amount of our existing excess transmission infrastructure, which will limit our ability to use these assets for other opportunities, including additional data center opportunities. Furthermore, effectively overseeing the construction and financing of the Contract Assets will require significant time and attention of our management, which could detract from their oversight of our existing business and ability to pursue other strategic opportunities.

The return structure and risk profile of Data Center Contract and related development of the Contract Assets differ from those of NIPSCO’s traditionally regulated utility operations. Any future data center contracts we enter into are expected to have a comparable structure and risk profile.

NIPSCO’s and GenCo’s operations under the Data Center Contract will be, and under future data center contracts are expected to be, regulated by the IURC in a different way from the regulatory mechanisms applicable to NIPSCO’s historical operations, which could affect the manner in which we recover our investment costs and earn a return on our investment. NIPSCO’s electric utility rates historically have been determined and approved in regulatory proceedings with the IURC based on an analysis of NIPSCO’s costs to provide utility service and a return on, and recovery of, NIPSCO’s investment in the utility business. Through the IURC rate-making process, retail rates may be adjusted over time, and NIPSCO may request additional revenue, in order to cover ongoing costs and investment and earn an adequate return.

In contrast, the terms of the Data Center Contract were, and the terms of any future data center contracts will be, determined by commercial negotiation with Customer. In the case of the Data Center Contract, these terms include the charges that we receive from Customer, which are designed to allow us to recover the costs that we incur to construct and operate the Contract Assets and earn a return, and provisions that may result in adjustments to those charges such as, among other factors, those relating to certain liquidated damages that we may owe Customer in the event of construction delays or capacity shortfalls and the parties’ responsibility to share cost overruns, among other provisions. These terms do not guarantee a specific overall rate of return, and the overall return we earn under the Data Center Contract may ultimately be lower than that of NIPSCO’s traditional utility operations. The IURC will not regulate the commercial terms of the Data Center Contract and is not expected to regulate the commercial terms of any future data center contracts; however, the IURC is expected to maintain oversight under the Data Center Contract and any future data center contracts to ensure NIPSCO provides reliable service to Customer and any future data center customers at just and reasonable rates. In order to recover our investment costs and earn our return under the Data Center Contract and any future data center contracts, our subsidiaries must efficiently perform their own obligations and must look to the Customer or future customers (or, if applicable, any parent guarantor) to perform its obligations, rather than the IURC making use of its traditional rate-making process. In addition, under the Data Center Contract, NIPSCO has direct contractual obligations to the Customer to, among other things, construct the Contract Assets and deliver committed electric

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2025-09-30. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Revenue3 months2025-07-01 to 2025-09-30$1.24bnus-gaap:RevenueFromContractWithCustomerExcludingAssessedTax
Revenue9 months2025-01-01 to 2025-09-30$4.64bnus-gaap:RevenueFromContractWithCustomerExcludingAssessedTax
Operating income3 months2025-07-01 to 2025-09-30$297.5mus-gaap:OperatingIncomeLoss
Operating income9 months2025-01-01 to 2025-09-30$1.32bnus-gaap:OperatingIncomeLoss
Interest expense3 months2025-07-01 to 2025-09-30$179.8mus-gaap:InterestExpenseNonoperating
Interest expense9 months2025-01-01 to 2025-09-30$451.7mus-gaap:InterestExpenseNonoperating
Income tax3 months2025-07-01 to 2025-09-30$20.6mus-gaap:IncomeTaxExpenseBenefit
Income tax9 months2025-01-01 to 2025-09-30$150.1mus-gaap:IncomeTaxExpenseBenefit
Net income3 months2025-07-01 to 2025-09-30$94.7mus-gaap:NetIncomeLoss
Net income9 months2025-01-01 to 2025-09-30$671.7mus-gaap:NetIncomeLoss
Diluted EPS3 months2025-07-01 to 2025-09-30$0.20us-gaap:EarningsPerShareDiluted
Diluted EPS9 months2025-01-01 to 2025-09-30$1.42us-gaap:EarningsPerShareDiluted
Basic EPS3 months2025-07-01 to 2025-09-30$0.20us-gaap:EarningsPerShareBasic
Basic EPS9 months2025-01-01 to 2025-09-30$1.42us-gaap:EarningsPerShareBasic
Diluted shares (weighted)3 months2025-07-01 to 2025-09-30473,700,000 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Diluted shares (weighted)9 months2025-01-01 to 2025-09-30472,800,000 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Operating cash flow9 months2025-01-01 to 2025-09-30$1.65bnus-gaap:NetCashProvidedByUsedInOperatingActivities
Capital expenditure9 months2025-01-01 to 2025-09-30$1.94bnus-gaap:PaymentsToAcquirePropertyPlantAndEquipment
Dividends paid9 months2025-01-01 to 2025-09-30$396.4mus-gaap:PaymentsOfDividendsCommonStock
Cash and equivalentsAt period end2025-09-30$95.0mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2025-09-30$1.85bnus-gaap:AssetsCurrent
Total assetsAt period end2025-09-30$34.40bnus-gaap:Assets
Current liabilitiesAt period end2025-09-30$3.53bnus-gaap:LiabilitiesCurrent
Short-term borrowingsAt period end2025-09-30$1.26bnus-gaap:ShortTermBorrowings
Shareholders' equityAt period end2025-09-30$9.12bnus-gaap:StockholdersEquity

Source: SEC EDGAR, the filing index for accession 0001111711-25-000055. Last ingested by Listed: Nov 10, 2026, 02:09 ET. Listed shows no prices and gives no investment advice.