We operate in the gold mining industry, primarily focused on advancing the Donlin Gold project in Alaska. The Donlin Gold project is held by Donlin Gold LLC (“Donlin Gold”), a limited liability company that is owned by wholly-owned subsidiaries of NOVAGOLD and Donlin Gold Holdings LLC, a subsidiary of Paulson Advantage Plus Master Ltd. and Paulson Partners LP (together, “Paulson”). Prior to June 3, 2025, Donlin Gold was owned equally by wholly-owned subsidiaries of NOVAGOLD and Barrick Mining Corporation (“Barrick”).
We do not produce gold or any other minerals, and do not currently generate operating earnings. Funding to explore our mineral properties and to operate the Company was acquired primarily through equity financings consisting of public offerings of our common shares and warrants and through previous debt financing consisting of convertible notes, and the sale of assets. We expect to continue to raise capital through additional equity and/or debt financings, through the exercise of stock options, and other such means.
We were incorporated by memorandum of association on December 5, 1984, under the Companies Act (Nova Scotia) as 1562756 Nova Scotia Limited. On January 14, 1985, we changed our name to NovaCan Mining Resources (1985) Limited and on March 20, 1987, we changed our name to NOVAGOLD RESOURCES INC. On May 29, 2013, our shareholders approved the continuance of the corporation into British Columbia. Subsequently, we filed the necessary documents in Nova Scotia and British Columbia, and we continued under the Business Corporations Act (British Columbia) effective as of June 10, 2013. The current addresses, telephone and facsimile numbers of our offices are:
| Executive office | Corporate office |
|---|---|
| 201 South Main Street, Suite 400 | 400 Burrard Street, Suite 1860 |
| Salt Lake City, UT, USA 84111 | Vancouver, BC, Canada V6C 3A6 |
| Telephone (801) 639-0511 | Toll free (866) 669-6227 |
| Facsimile (385) 342-4620 | Facsimile (604) 669-6272 |
8
Corporate Structure
As of November 30, 2025, we had the following material, direct and indirect, wholly-owned subsidiaries: NOVAGOLD Resources Alaska, Inc., NOVAGOLD US Holdings Inc., NOVAGOLD USA, Inc., and AGC Resources Inc. On December 1, 2024, NOVAGOLD (Bermuda) Alaska Limited, NOVAGOLD Resources (Bermuda) Limited and NOVAGOLD Argentina Inc. were amalgamated with NOVAGOLD RESOURCES INC.
The following chart depicts the corporate structure of the Company together with the jurisdiction of incorporation of each of our material subsidiaries and related holding companies as of November 30, 2025. All ownership is 100% unless otherwise indicated.
Human Capital Resources
On November 30, 2025, we had 12 full-time employees, of which four are located in Canada and eight are located in the United States. We also use consultants with specific skills to assist with various aspects of project evaluation, engineering, and corporate governance.
Company Values
Our company culture is the cornerstone of all our human capital programs. Empowering every employee to be their best, affording every employee the opportunity to make a difference, and giving every employee a chance to be heard are among the Company’s values. Our values extend to the communities in which we work. We have adopted a Human Rights Policy focused on our commitment to having a positive influence in the communities where we operate which includes ensuring that we respect human rights.
Diversity
As of the end of fiscal year 2025, 54% of our total workforce were women. Selection of individuals for executive and other positions with the Company is guided by the Company’s Code of Business Conduct and Ethics which “prohibits discrimination in any aspect of employment based on race, color, religion, sex, national origin, disability or age.” Our board of directors (the “Board”) and management acknowledge the importance of all aspects of diversity including gender, ethnic origin, business skills and experience, because it is right to do so and because it is good for our business. When considering candidates for executive positions, the Board’s evaluation considers the broadest possible assessment of each candidate’s skills and background with the overriding objective of ensuring that we have the appropriate balance of skills, experience, and capacity that the Company needs to be successful. In the context of this overriding objective, we have determined not to set targets for the percentage of women, or other aspects of diversity, in executive officer positions.
NOVAGOLD is committed to fostering, cultivating, and preserving a culture of diversity, equity and inclusion. Our employees are one of the most valuable assets we have. The collective sum of the individual differences, life experiences, knowledge, inventiveness, innovation, self-expression, unique capabilities, and talent that our employees invest in their work represents a significant part of our culture, reputation, and NOVAGOLD’s achievements.
NOVAGOLD is dedicated to creating an inclusive work environment for everyone. We embrace and celebrate the unique experiences, perspectives, and cultural backgrounds that each employee brings to our workplace. NOVAGOLD strives to foster an environment where our employees feel respected, valued, and empowered, and our team members are at the forefront in helping us promote and sustain an inclusive workplace.
NOVAGOLD’s diversity initiatives are applicable—but not limited—to our practices and policies on recruitment and selection; compensation and benefits; professional development and training; promotions; and the ongoing development of a work environment built on the premise of gender and diversity equity. To that end, we seek out qualified diverse candidates and encourage them to apply for open positions, either from within or outside of the Company. We also seek out opportunities to develop a pipeline of qualified diverse candidates in a particular profession when we are unable to find them ourselves. For example, in 2021 the Company established and continues to fund the NOVAGOLD Mining and Geological Engineering Scholarship at the University of Alaska to help support and encourage undergraduate students seeking bachelor’s degrees in mining or geological engineering, with a focus on supporting underrepresented students.
We encourage:
- Respectful communication and cooperation among all employees.
- Teamwork and employee participation, fostering the representation of all employee perspectives.
- Work/life balance through flexible work schedules to accommodate employees’ varying needs.
- Learning about and, where appropriate, aiding the communities near NOVAGOLD’s projects to promote a greater understanding and respect for diversity in those communities.
Health and Safety
NOVAGOLD’s primary objective is to ensure the health and safety of its employees, partners, and contractors, and is reflected in its Health and Safety Policy. Our focus on safety is also reflected at Donlin Gold where a wide-ranging set of policies are implemented at the project site and in the Anchorage office. In 2025, neither Donlin Gold nor NOVAGOLD had any recordable injuries or lost time incidents. Also see section Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations, below.
Recent Developments
Donlin Gold project
NOVAGOLD and Donlin Gold advanced key activities in 2025 to position the project to update technical work and cost estimates. Primary activities included 1) issuing a Request for Proposals (RFP) for a feasibility study to be prepared in accordance with S-K 1300 and NI 43-101, referred to herein as Bankable Feasibility Study (BFS), to top-tier engineering firms with the expertise to design what is expected to be the largest single gold mine in the United States. Proposals were received in October, and the Prime Contractor is expected to be selected in the first quarter of 2026. RFPs were also issued in the fourth quarter of 2025 for specialist contractors for the power plant, pipeline, and pressure oxidation and oxygen plant scopes of work; and 2) mine planning and resource conversion advanced through the completion of an 18,454-meter 2025 drill program. The work targeted three core objectives: grid drilling to refine mine planning parameters, in-pit exploration to strengthen geological modelling and resource conversion, and geotechnical drilling to inform the updated resource model, mine planning and assess material sites for the planned port access road. The program was successfully executed by a site team of approximately 80 locally hired staff and external contractors, with results providing critical inputs for engineering, mine planning, and resource modelling.
To support the advancement of the BFS and move the project toward construction and ultimately commercial operation, management has identified key project requirements and commenced recruiting for critical positions. Donlin Gold hired Frank Arcese as Project Director. Frank brings more than four decades of global project leadership to Donlin Gold and has deep experience in the execution of large-scale mining capital projects in both the U.S. and international jurisdictions. Most recently, he served as Capital Projects Business Leader for North American mining operations at WSP Global Inc., and Engineering, Procurement and Construction Management (EPCM) firm. Prior to that, he acted as Project Director on multiple large mining and power plant projects for Rio Tinto across the U.S., Mongolia, China, Australia, and Argentina, and brings extensive expertise in managing projects in remote environments, such as Teck Resource’s original Quebrada Blanca in Chile, BHP’s Escondida Phase 3 and SX-EW Plant in Chile, and recently Rio Tinto’s Rincon 3000 Lithium Project in Argentina.
During 2025, Donlin Gold participated in a wide range of community engagement and environmental initiatives. Representatives from Donlin Gold, NOVAGOLD, Paulson, and The Electrum Group LLC met with Calista Corporation (“Calista”), the Kuskokwim Corporation (TKC), and other stakeholders from the Yukon-Kuskokwim (Y-K) region. Additionally, Donlin Gold also hosted project site tours with stakeholders, investors, and analysts, followed by the owners’ tour which included meetings with key Alaska government officials – such as Governor Mike Dunleavy, Department of Natural Resources (ADNR) Commissioner John Boyle, and former Revenue Commissioner Adam Crum – to introduce the new ownership and discuss shared priorities. The team also met with principal stakeholders from government agencies, engineering firms, logistics providers and other pivotal parties with the capacity and experience to support critical project infrastructure as Donlin Gold advances the BFS and development activities after its construction decision, and held discussions with natural gas pipeline developers to explore opportunities benefiting the project and its stakeholders. Additionally, Donlin Gold hosted the fourth and fifth Subsistence Community Advisory Committee meetings in Anchorage and at the project site, offering a deep dive in different areas of the project’s development and operations, including camp and facility tours, aquatic resources monitoring and Snow Gulch restoration work. In addition, two new Shared Values Statements were finalized – bringing the total to 20 – with communities near the project. Environmental efforts advanced as well, including channel restoration work at Snow Gulch, a tributary of Donlin Creek historically mined for placer gold, to help restore natural habitat conditions and support aquatic life.
Donlin Gold’s board approved a fiscal 2026 budget of $131.4 million ($78.8 million NOVAGOLD’s share) which includes advancing the BFS, maintaining and securing outstanding permits, government affairs, community relations, workforce development, environmental activities and exploration.
For further information, see section Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations, below.
Reclamation
We will generally be required to mitigate long-term environmental impacts by stabilizing, contouring, re-sloping and re-vegetating various portions of a site after mining and mineral processing operations are completed. These reclamation efforts will be conducted in accordance with detailed plans, which are approved by the appropriate regulatory agencies. In addition, financial assurance acceptable to the regulatory authority with jurisdiction over reclamation must be provided in an amount and form that is determined to be sufficient by the authority to implement the approved reclamation plan in the event that the project owners fail to complete the work as provided in the plan.
Government and Environmental Regulations
Our exploration and development activities are subject to various national, state, and local laws and regulations in the United States, which govern prospecting, development, mining, production, exports, taxes, labor standards, occupational health, waste disposal, protection of the environment, mine safety, hazardous substances, disclosure requirements and other matters. We have obtained or have pending applications for those licenses, permits or other authorizations currently required to conduct our exploration and development programs. We believe that we are in compliance in all material respects with applicable mining, health, safety and environmental statutes and regulations in the United States. There are no existing orders or directions relating to our current activities with respect to the foregoing laws and regulations. For a more detailed discussion of the various government laws and regulations applicable to our operations and potential negative effects of these laws and regulations, see section Item 1A. Risk Factors, below.
Competition
We compete with other mineral resource exploration and development companies for financing, technical expertise, and the acquisition of mineral properties. Many of the companies with whom we compete have greater financial and technical resources. Accordingly, these competitors may be able to spend greater amounts on the acquisition, exploration, and development of mineral properties. This competition could adversely impact our ability to finance further exploration and to obtain the financing necessary for us to develop the Donlin Gold project.
Availability of Raw Materials and Skilled Employees
Most aspects of our business require specialized skills and knowledge. Such skills and knowledge include the areas of geology, drilling, resource estimating, metallurgy, mine planning, logistical planning, preparation of pre-feasibility and feasibility studies, permitting, engineering, construction and operation of a mine, financing, legal, human resources, accounting, investor relations, and community relations. Historically, we have found that we can locate and retain appropriate employees and consultants and we believe we will continue to be able to do so.
The raw materials we require to carry on our business are readily available through normal supply or business contracting channels in the United States and Canada. Historically, we have been able to secure the appropriate equipment and supplies required to conduct our contemplated programs. As a result, we do not believe that we will experience any shortages of required equipment or supplies in the foreseeable future.
Seasonality
Our business can be seasonal as our mineral exploration and development activities take place in southwestern Alaska. Due to the northern climate, work on the Donlin Gold project can be limited due to excessive snow cover and cold temperatures. In general, surface work often is limited to late spring through early fall, although work in some locations is more readily and efficiently completed during the winter months when the ground is frozen.
Gold Price History
The price of gold is volatile and is affected by numerous factors, all of which are beyond our control, such as the sale or purchase of gold by various central banks and financial institutions, inflation, recession, fluctuation in the relative values of the U.S. dollar and foreign currencies, changes in global and regional gold demand, in addition to international and national political and economic conditions.
The following table presents the annual high, low and average daily afternoon London Bullion Market Association (“LBMA”) Gold Price over the past five calendar years on the London Bullion Market ($/ounce):
| Year | High | Low | Average |
|---|---|---|---|
| 2021 | $1,943 | $1,684 | $1,799 |
| 2022 | $2,039 | $1,628 | $1,800 |
| 2023 | $2,078 | $1,811 | $1,941 |
| 2024 | $2,784 | $1,985 | $2,387 |
| 2025 | $4,482 | $2,632 | $3,436 |
| 2026 (through January 16) | $4,633 | $4,353 | $4,518 |
On January 16, 2026, the afternoon LBMA gold price was $4,611 per ounce.
Data Source: lbma.org.uk
Available Information
We maintain a website at www.novagold.com (http://www.novagold.com) and make available, through the Investors section of the website, our Annual Reports on Form 10-K, Quarterly Reports on Form 10-Q, Current Reports on Form 8-K, Section 16 filings and all amendments to those reports, as soon as reasonably practicable after such material is electronically filed with the SEC. These reports are also available at the SEC website at www.sec.gov (http://www.sec.gov). Certain other information, including but not limited to the Company’s Corporate Governance Guidelines, the charters of key committees of its Board of Directors and its Code of Business Conduct and Ethics are also available on the website. Our website and the information contained therein or connected thereto are not intended to be, and are not incorporated into this Annual Report on Form 10-K.
Risk factors
As filed, 57,881 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
You should carefully consider the following risk factors in addition to the other information included in this Annual Report on Form 10-K. Each of these risk factors could adversely affect our business, operating results and financial condition, as well as adversely affect the value of an investment in our common shares. The risks described below are not the only ones facing the Company. Additional risks that we are not presently aware of, or that we currently believe are immaterial, may also adversely affect our business, operating results and financial condition. We cannot assure you that we will successfully address these risks and caution that other unknown risks may exist or may arise that may affect our business.
An investment in our securities is speculative and involves a high degree of risk due to the nature of our business and the present stage of exploration and development of our mineral properties. The following risk factors, as well as risks not currently known to us, could materially adversely affect our future business, operations and financial condition and could cause them to differ materially from the estimates described in the forward-looking statements relating to us.
Risks Related to Our Business
We have no history of commercially producing precious metals from our mineral exploration properties and there can be no assurance that we will successfully establish mining operations or profitably produce precious metals.
The Donlin Gold project is not in production or currently under construction, and we have no ongoing mining operations or revenue from mining operations. Mineral exploration and development has a high degree of risk and few properties that are explored are ultimately developed into producing mines. The future development of the Donlin Gold project will require having the necessary permits and financing in place to support the construction and ongoing operation of mines, processing plants and related infrastructure. As a result, we are subject to all of the risks associated with establishing new mining operations and business enterprises, including:
- the need to obtain and maintain necessary environmental and other governmental approvals and permits, and the timing and conditions of those approvals and permits;
- the availability and cost of funds to finance construction and development activities;
- the timing and cost, which can be considerable, of the construction of mining and processing facilities as well as related infrastructure;
- potential opposition from NGOs, environmental groups or local groups which may delay or prevent development activities;
- potential increases in construction and operating costs due to changes in the cost of labor, fuel, power, materials and supplies, services, and foreign exchange rates;
- the availability and cost of skilled labor and mining and processing equipment; and
- the availability and cost of appropriate smelting and/or refining arrangements.
The costs, timing and complexities of mine construction and development are increased by the remote location of our mineral properties, with additional challenges related thereto, including access, water and power supply, and other support infrastructure. Cost estimates may increase significantly as more detailed engineering work and studies are completed. New mining operations commonly experience unexpected costs, problems and delays during development, construction, and mine start-up. In addition, delays in the commencement of mineral production often occur. Accordingly, there are no assurances that our activities will result in profitable mining operations, or that we will successfully establish mining operations, or profitably produce precious metals at the Donlin Gold project.
In addition, there is no assurance that our mineral exploration activities will result in any discoveries of new ore bodies. If further mineralization is discovered there is also no assurance that the mineralized material would be economical for commercial production. Discovery of mineral deposits is dependent upon a number of factors and significantly influenced by the technical skill of the exploration personnel involved. The commercial viability of a mineral deposit is also dependent upon a number of factors which are beyond our control, including the attributes of the deposit, commodity prices, government policies and regulation, and environmental protection requirements.
We are dependent on the cooperation of a third party in the exploration and development of our Donlin Gold project.
Our success with respect to the Donlin Gold project depends on the cooperation of the co-owner of Donlin Gold. We currently hold a 60% economic interest in Donlin Gold and the remaining 40% economic interest is held by a third party that is not under our control or direction. Furthermore, governance of Donlin Gold is shared on an equal basis, so we will continue to be dependent on the cooperation of a third party for the progress and development of the Donlin Gold project. The third party may have different priorities which could impact the timing and cost of development of the Donlin Gold project. If the third party defaults on its agreements with us, with or without our knowledge, it may put the mineral property and related assets at risk. The existence or occurrence of one or more of the following circumstances and events could have a material adverse impact on our ability to achieve our business plan, profitability, or the viability of our interests held with the third party, which could have a material adverse impact on our business, future cash flows, earnings, results of operations and financial condition: (i) disagreement with the third party on how to develop and operate the Donlin Gold project efficiently; (ii) disagreement with the third party on certain strategic decisions in respect of the Donlin Gold project; (iii) inability of the third party to meet their obligations to Donlin Gold or other parties; and (iv) litigation with the third party regarding joint business matters.
Despite our ownership of 60% of the membership interests of Donlin Gold, our voting interests are contractually reduced in the A&R LLC Agreement.
Consistent with the limited liability company agreement with Barrick Gold U.S. Inc. and Donlin Gold dated December 1, 2007, as amended from time to time, the funding for Donlin Gold is shared by both parties based on their percentage ownership. For example, since NOVAGOLD Resources Alaska, Inc. (“NGRA”) holds 60% of the membership interests of Donlin Gold, it will have the responsibility to fund 60% of the expenses of Donlin Gold; however, even though Paulson holds 40% of Donlin Gold, the parties have equal governance rights. This adjustment to the parties’ voting interests as set forth in the amended and restated limited liability company agreement entered into by NGRA, Donlin Holdings and Donlin Gold means that (i) NGRA’s voting percentage interests are defined as its participating interest from time to time less an absolute 10% and (ii) Paulson’s voting percentage interests are defined as its participating interest from time to time plus an absolute 10%. For this reason, even though NGRA holds 60% of the membership interests of Donlin Gold, the Company has a 50% voting interest at Donlin Gold, not 60%. These reduced voting rights may decrease the value attributed to our interest in Donlin Gold and reduces our ability to assert our proportionate rights at the project.
We identified a deficiency in our disclosure controls and procedures in the quarter ended August 31, 2025 which has been remediated. If we fail to maintain an effective system of disclosure controls, our ability to produce timely and accurate public disclosure or comply with applicable laws and regulations could be impeded.
During the quarter ended August 31, 2025, we did not timely file a Current Report on Form 8-K with respect to the resignation of a member of our Board of Directors. During the quarter, the Company took remedial action including (i) revising our written policies with respect to director and named executive officer resignation to require that resignations be tendered to specified personnel and (ii) instituting additional training on disclosure controls and procedures, particularly with respect to Form 8-K compliance, for members of the Board of Directors. We cannot be certain that the measures we have taken to date, and actions we may take in the future, will be sufficient to prevent or avoid potential future disclosure failures. Our current controls and any new controls that we develop may become inadequate because of changes in conditions in our business or otherwise. Further, weaknesses in our disclosure controls may be discovered in the future. Any failure to develop or maintain effective controls or any difficulties encountered in their implementation or improvement could harm our operating results or cause us to fail to meet our reporting obligations and may impact our ability to access capital markets on a timely basis, which may result in investors losing confidence in the accuracy and completeness of our periodic reports and adversely affect the market price of our common shares. As a result of the delinquent filing of the Form 8-K, we will not be eligible to use Form S-3 to register our securities with the SEC until July 2026.
We have a history of net losses and expect losses to continue for the foreseeable future.
The Donlin Gold project has not advanced to the commercial production stage and we have no history of earnings or cash flow from operations. We expect to continue to incur net losses unless and until such time the Donlin Gold project commences commercial production and generates sufficient revenues to fund continuing operations. The development of our mineral properties to achieve production will require the commitment of substantial financial resources. The amount and timing of expenditures will depend on a number of factors, including the progress of ongoing exploration and development, the results of consultants’ analyses and recommendations, the rate at which operating losses are incurred, the process of obtaining required government permits and approvals, the availability and cost of financing, the participation of our partners, and the execution of any sale or joint venture agreements with strategic partners. These factors, and others, are beyond our control. There is no assurance that we will be profitable in the future.
We have a limited property portfolio.
At present, our only material mineral property is the interest that we hold in the Donlin Gold project. Unless we acquire or develop additional mineral properties, we will be solely dependent upon this property. If no additional mineral properties are acquired by us, any adverse development affecting our operations and further development at the Donlin Gold project may have a material adverse effect on our financial condition and results of operations.
Our ability to continue the exploration, permitting and development of the Donlin Gold project, to complete the Bankable Feasibility Study for the Donlin Gold project, to fund construction of the Donlin Gold project, and to continue as a going concern, will depend in part on our ability to obtain suitable financing.
We have limited financial resources. We will need external financing to continue the exploration, permitting, and development of the Donlin Gold project, to complete the Bankable Feasibility Study for the Donlin Gold project and to construct and ultimately operate the Donlin Gold project. In addition, according to the S-K 1300 Report (as defined below), the total initial capital cost estimate for the Donlin Gold project is approximately $9,233 million which includes the costs related to the natural gas pipeline (100% basis). These cost estimates may change materially as our studies are updated. Our failure to obtain sufficient financing could result in the delay or indefinite postponement of the completion of the Bankable Feasibility Study or exploration, development, construction, or production at the Donlin Gold project. The cost and terms of such financing may significantly reduce the expected benefits from development of the Donlin Gold project and/or render such development uneconomic. There can be no assurance that additional capital or other types of financing will be available when needed or that, if available, the terms of such financing will be favorable. Our failure to obtain financing could have a material adverse effect on our growth strategy and results of operations and financial condition.
We intend to fund our near-term business plan from working capital. Longer term, our ability to continue future exploration, permitting, development, and construction activities, if any, will depend in part on our ability to obtain suitable equity, debt, or other forms of financing. If we raise additional funding by issuing additional equity securities or other securities that are convertible into equity securities, such financing may substantially dilute the interest of existing or future shareholders. Sales or issuances of a substantial number of securities, or the perception that such sales could occur, may adversely affect the prevailing market price for our common shares. With any additional sale or issuance of equity securities, investors will suffer dilution of their voting power and may experience dilution in earnings per share.
There can be no assurance that we will commence production at the Donlin Gold project or generate sufficient revenues to meet our obligations as they become due or obtain necessary financing on acceptable terms, if at all. Our failure to meet our ongoing obligations on a timely basis could result in the loss or substantial dilution of our interests (as existing or as proposed to be acquired) in the Donlin Gold project. In addition, should we incur significant losses in future periods, we may be unable to continue as a going concern, and realization of assets and settlement of liabilities in other than the normal course of business may be at amounts materially different than our estimates.
Actual capital costs, operating costs, production and economic returns may differ significantly from those we have anticipated and there are no assurances that any future development activities will result in profitable mining operations.
The capital costs to take the Donlin Gold project into production may be significantly higher than anticipated. As a result of the content updates included in the 2025 Technical Report (as defined below) and 2025 Technical Report Summary (as defined below), the total initial capital cost estimate for the Donlin Gold project is $9,233 million and the total sustaining capital estimate is $2,325 million.
We do not have an operating history upon which we can base estimates of future operating costs. Decisions about the development of the Donlin Gold project will ultimately be based upon feasibility studies. Feasibility studies derive estimates of cash operating costs based upon, among other things:
- anticipated tonnage, grades and metallurgical characteristics of the ore to be mined and processed;
- anticipated recovery rates of gold and other precious metals from the ore;
- cash operating costs of comparable facilities and equipment; and
- anticipated climatic conditions.
Capital costs, operating costs, production and economic returns, and other estimates contained in studies or estimates prepared by or for us may differ significantly from those anticipated by our current or future studies and estimates, and there can be no assurance that the initial capital costs incurred to construct, and the sustaining capital and operating costs incurred in operating the Donlin Gold project will not be higher than currently anticipated.
Changes in the market price of gold, which in the past has fluctuated widely, affect our financial condition.
Our profitability and long-term viability will depend, in large part, upon the market price of gold that may be produced from our Donlin Gold project. The market price of gold is volatile and is impacted by numerous factors beyond our control, including:
- global or regional consumption patterns;
- expectations with respect to the rate of inflation;
- the relative strength of the U.S. dollar and certain other currencies;
- interest rates;
- global or regional political or economic conditions, including interest rates and currency values;
- supply and demand for jewelry and industrial products containing gold; and
- sales or purchases by central banks and other holders, speculators, and producers of gold in response to any of the above factors.
We cannot predict the effect of these factors on the price of gold. A decrease in the market price of gold could affect our ability to finance the development of the Donlin Gold project, which would have a material adverse effect on our financial condition and results of operations. There can be no assurance that the market price of gold will remain at current levels or that such prices will improve. An increase in worldwide supply, and consequent downward pressure on prices, may result over the longer term from increased production from the development of new or expansion of existing mines. There is no assurance that if commercial quantities of gold are discovered, that a profitable market may exist or continue to exist for a production decision to be made or for the ultimate sale of gold.
General economic conditions may adversely affect our growth, future profitability and ability to finance.
Some key impacts which can contribute to financial market turmoil potentially impacting the mining industry include contraction in credit markets resulting in a widening of credit risk, imposition of trade tariffs among various countries, devaluations, high volatility in global equity, commodity, foreign exchange and precious metal markets and a lack of market liquidity. The prices of gold and gold mining company equities have experienced significant volatility over the past few years.
A decrease in the price of gold or tightening of credit in the financial markets or other economic conditions, including but not limited to, consumer spending, employment rates, business conditions, inflation, fuel and energy costs, consumer debt levels, lack of available credit, the state of the financial markets, interest rates and tax rates, may adversely affect our ability to finance development and construction of the Donlin Gold project. Specifically:
- global economic conditions could make other investment sectors more attractive, thereby affecting the cost and availability of financing to us and our ability to achieve our business plan;
- the imposition of protectionist or retaliatory trade tariffs by countries may impact our ability to import materials needed to construct our projects or conduct our operations, or to export our products, at prices that are economically feasible for our operations, or at all;
- the volatility of metal prices would impact the economic viability of the Donlin Gold project and any future revenues, profits, losses and cash flow;
- negative economic pressures could adversely impact demand for future production from the Donlin Gold project;
- construction related costs could increase and adversely affect the economics of the Donlin Gold project;
- volatile energy, commodity and consumables prices and currency exchange rates would impact our future production costs; and
- the devaluation and volatility of global stock markets would impact the valuation of our equity and other securities.
Opposition to our operations from local stakeholders or NGOs could have a material adverse effect on us.
There is ongoing public concern relating to the effect of mining production on its surroundings, communities, and environment. Local communities and NGOs, some of which oppose resource development, are often vocal critics of the mining industry. While we seek to operate in a socially responsible manner, opposition to extractive industries or our operations specifically or adverse publicity generated by local communities or NGOs related to extractive industries, or our operations specifically, could have an adverse effect on our reputation and financial condition or our relationships with the communities in which we operate. As a result of such opposition or adverse publicity, we may be unable to obtain permits necessary for our operations or to continue our operations as planned or at all. See “Recent Developments” above.
We require various permits to conduct our current and anticipated future operations, and delays or a failure to obtain such permits, or a failure to comply with the terms of any such permits that we have obtained, could have a material adverse impact on us.
Our current and anticipated future operations, including further exploration and development activities and commencement of production on the Donlin Gold project, require permits from various United States federal, state, and local governmental authorities. There can be no assurance that all permits that we require for the construction of mining facilities and to conduct mining operations will be obtainable on reasonable terms, or at all. Delays or a failure to obtain such permits, or a failure to comply with the terms of any such permits that we have obtained, could have a material adverse impact on us.
The duration and success of efforts to obtain and renew permits are contingent upon many variables not within our control. Shortage of qualified and experienced personnel in the various levels of government could result in delays or inefficiencies. Backlog within the permitting agencies could affect the permitting timeline of the various projects. Other factors that could affect the permitting timeline include (i) the number of other large-scale projects currently in a more advanced stage of development which could slow down the review process and (ii) significant public response regarding a specific project. Also, it can be difficult to assess what specific permitting requirements will ultimately apply to the Donlin Gold project.
The quantities for our mineral resources and mineral reserves are estimates based on interpretation and assumptions and may yield less mineral production under actual conditions than is currently estimated.
Unless otherwise indicated, mineralization quantities presented in this Annual Report on Form 10-K and in our other filings with securities regulatory authorities, press releases and other public statements that may be made from time to time are based upon estimates made by our personnel and independent professionals. In addition, these estimates depend upon geologic interpretation and statistical inferences drawn from drilling and sampling analysis available at the time of the estimate, and may change with further work.
Because we have not commenced commercial production at the Donlin Gold project, mineral resource estimates may require adjustments, including potential downward revisions based upon further exploration or development work, actual production experience, or changes in the price of gold. In addition, the grade of ore ultimately mined, if any, may differ from that indicated by drilling results. There can be no assurance that the percentage of minerals recovered in small-scale tests will be duplicated in large-scale tests under on-site conditions or at production scale.
Mineral resource estimates for mineral properties that have not commenced production are based, in many instances, on limited and widely spaced drill hole information, which is not necessarily indicative of the conditions between and around drill holes. Accordingly, such mineral resource estimates may require revision as more drilling information becomes available or as actual production experience is gained.
The estimating of mineral reserves and mineral resources is a subjective process that relies on the judgment and experience of the persons preparing the estimates. The process relies on the quantity and quality of available data and is based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. There can be no assurances that actual results will meet the estimates contained in studies.
Estimated mineral reserves or mineral resources may have to be revised based on changes in metal prices, further exploration or development activity, or actual production experience. In addition, if production costs increase, recovery rates decrease, if applicable laws and regulations are adversely changed, there is no assurance that the anticipated level of recovery will be realized or that mineral reserves or mineral resources as currently reported can be mined or processed profitably. This could materially and adversely affect estimates of the volume or grade of mineralization, estimated recovery rates or other important factors that influence mineral reserve or mineral resource estimates. The extent to which mineral resources may ultimately be reclassified as mineral reserves is dependent upon the demonstration of their profitable recovery. Any material changes in mineral resource estimates and grades of mineralization will affect the economic viability of placing a mineral property into production and a mineral property’s return on capital. We cannot provide assurance that mineral resources identified at the Donlin Gold project can or will be mined or processed profitably.
The mineral resource and mineral reserve estimates contained in this Annual Report on Form 10-K have been determined and valued based on assumed future prices, cut-off grades and operating costs that may prove to be inaccurate. Extended declines in market prices for gold may render portions of our mineral resource uneconomic and result in reduced reported mineral resources. Any material reductions in estimates of mineral resources, or of our ability to extract these mineral resources, could have a material adverse effect on our ability to implement our business strategy, the results of operations or our financial condition.
We have established the presence of proven and probable mineral reserves at the Donlin Gold project in accordance with the disclosure definition and standards contained in S-K 1300 and in NI 43-101. There can be no assurance that additional mineral resources will ultimately be reclassified as mineral reserves. The failure to increase mineral reserves could restrict our ability to successfully implement our strategies for long-term growth and could impact future cash flows, earnings, results of operation and financial condition.
Lack of infrastructure could delay or prevent us from developing the Donlin Gold project.
Completion of the development of the Donlin Gold project is subject to various requirements, including the availability and timing of acceptable arrangements for power, water, transportation, access, and facilities. The lack of availability on acceptable terms or the delay in the availability of any one or more of these items could prevent or delay development of the project. There can be no assurance that adequate infrastructure, including access and power supply, will be built, that it will be built in a timely manner or that the cost of such infrastructure will be reasonable or that it will be sufficient to satisfy the requirements of the project. If adequate infrastructure is not available in a timely manner, there can be no assurance that:
- the development of the Donlin Gold project will be commenced or completed on a timely basis, if at all;
- the resulting operations will achieve the anticipated production volume; or
- the construction costs and ongoing operating costs associated with the development of the Donlin Gold project will not be higher than anticipated.
Access to the Donlin Gold project is limited and there is no infrastructure that serves the project area. An approximately 507-kilometer natural gas pipeline is needed to supply fuel to the proposed on-site generating plant to provide power for the Donlin Gold project. The proposed pipeline would traverse generally undeveloped areas in Alaska that are difficult to access. Transportation of most of the supplies needed to construct and operate the Donlin Gold project would be accomplished by barging materials on the Kuskokwim River during the annual shipping season which typically occurs from late April to mid-October. Two ports would be needed on the Kuskokwim River, the first located in Bethel, Alaska, where ocean barges would transition materials to river barges; and the second located approximately 312 kilometers upriver from Bethel. A 44-kilometer access road from the upriver port to the project site is needed to deliver the materials. Additionally, an airstrip would be built to provide year-round access to the project. Terrain, geologic conditions, ground conditions, steep slopes, river levels, ice breakup, weather, climate change impacts and other natural conditions that are beyond our control along the pipeline and transportation routes present design, permitting, construction, and operational challenges for the project. Cost and schedule estimates may increase significantly as more detailed engineering work, geotechnical and geological studies are completed.
Title and other rights to our mineral properties are subject to agreements with other parties.
The subsurface mineral and surface rights at the Donlin Gold project are owned by Calista and TKC, respectively, two Native corporations. Donlin Gold operates on these lands pursuant to a mining lease with Calista (the “Calista Lease”) and a Surface Use Agreement (“SUA”) with TKC. The ability of Donlin Gold to continue to explore and develop the Donlin Gold project depends upon its continued compliance with the terms and conditions of the Calista Lease and SUA. Furthermore, our ability to continue to explore and develop other mineral properties may be subject to agreements with other third parties, including agreements with Native corporations, for instance.
Our largest shareholder has significant influence on us and may also affect the market price and liquidity of our securities.
Electrum Strategic Resources L.P. (“Electrum”) and its affiliate GRAT Holdings LLC hold in the aggregate 24.1% of our issued and outstanding common shares as of January 16, 2026. Accordingly, Electrum and its affiliates will have significant influence in determining the outcome of any corporate transaction or other matter submitted to the shareholders for approval, including mergers, consolidations, and the sale of all or substantially all of our assets and other significant corporate actions. Unless full participation of all shareholders takes place in such shareholder meetings, Electrum and its affiliates may be able to approve such matters itself. The concentration of ownership of the common shares by Electrum and its affiliates may: (i) delay or deter a change of control of the Company; (ii) deprive shareholders of an opportunity to receive a premium for their common shares as part of a sale of the Company; and (iii) affect the market price and liquidity of the common shares. In conjunction with the January 22, 2009 financing, we provided Electrum with the right to designate an observer at all meetings of the Board and any committee thereof so long as Electrum and its affiliates hold not less than 15% of our common shares. In November 2011, Dr. Thomas S. Kaplan, was appointed Chairman of our Board. Dr. Kaplan is also the Chairman, Chief Executive Officer, and Chief Investment Officer of The Electrum Group LLC. As long as Electrum and its affiliates maintain its shareholdings in the Company, Electrum will have significant influence in determining the members of the Board. Without the consent of Electrum, we could be prevented from entering into transactions that are otherwise beneficial to us. The interests of Electrum and its affiliates may differ from or be adverse to the interests of our other shareholders. The effect of these rights and Electrum’s influence may impact the price that investors are willing to pay for our shares. If Electrum or its affiliates sell a substantial number of our common shares in the public market, the market price of the common shares could be adversely impacted. The perception among the public that these sales will occur could also contribute to a decline in the market price of our common shares.
Some of the directors and officers have conflicts of interest as a result of their involvement with other natural resource companies.
Certain of our directors and officers also serve as directors, or have significant shareholdings in, other companies involved in natural resource exploration and development or mining-related activities. To the extent that such other companies may participate in ventures in which we may participate in or in ventures which we may seek to participate in, the directors and officers may have a conflict of interest. In all cases where the directors or officers have an interest in other companies, such other companies may also compete with us for the acquisition of mineral property investments. Any decision made by any of these directors and officers involving the Company will be made in accordance with their duties and obligations to deal fairly and in good faith with a view to the best interests of the Company. In addition, each of the directors is required to declare and refrain from voting on any matter in which these directors may have a conflict of interest in accordance with the procedures set forth in the Business Corporations Act (British Columbia) and other applicable laws. In appropriate cases, the Company will establish a special committee of independent directors to review a matter in which several directors, or management, may have a conflict. Nonetheless, as a result of these conflicts of interest, the Company may not have an opportunity to participate in certain transactions, which may have a material adverse effect on the Company’s business, profitability, financial condition, results of operation, and prospects.
We have ongoing reclamation on some of our mineral properties and may be required to fund additional work that could have a material adverse effect on our financial position.
Land reclamation requirements are generally imposed on mineral exploration companies (as well as companies with mining operations) to minimize long-term effects of land disturbance. Reclamation include requirements to:
- treat ground and surface water to applicable water standards;
- control dispersion of potentially deleterious effluents;
- reasonably re-establish pre-disturbance landforms and vegetation; and
- provide adequate financial assurance to ensure required reclamation of land affected by our activities.
Exploration and other activities at the Donlin Gold project site have created disturbance that must be reclaimed. Financial resources spent on reclamation might otherwise be spent on further exploration and development programs. In addition, regulatory changes could increase our obligations to perform reclamation and mine closure activities. There can be no assurance that we will not be required to fund additional reclamation work at the site that could have a material adverse effect on our financial position.
We are exposed to credit, liquidity, and interest rate risk.
Credit risk is the risk of an unexpected loss if a customer or third party to a financial instrument fails to meet its contractual obligations. Our cash equivalents and term deposit investments are held through large Canadian chartered banks with high investment-grade ratings. These investments mature at various dates over the current operating period. A portion of the proceeds from the sale of our Galore Creek assets include notes receivable from a subsidiary of Newmont Corporation (“Newmont”), a publicly traded company with investment-grade credit ratings. The notes receivable included a $75 million note receivable of which payment was received on July 27, 2021 and included a $25 million note receivable of which payment was received on July 27, 2023. An additional $75 million will be receivable if and when a Galore Creek project construction plan is approved by the owner(s). No value was assigned to the final $75 million contingent note receivable due to the uncertainty with regards to the approval of a Galore Creek project construction plan. The carrying amount of financial assets recorded in the financial statements, net of any allowances for losses, represents our maximum exposure to credit risk.
Liquidity risk is the risk that we will not be able to meet our financial obligations as they come due. We manage liquidity risk through regular cash flow forecasts to assess our current and future financial position as well as maintaining sufficient capital resources and a prudent capital structure. Accounts payable and accrued liabilities are due within one year from the balance sheet date.
Interest rate risk is the risk that the fair value or future cash flows of a financial instrument will fluctuate because of changes in market interest rates. The risk that we will realize a loss as a result of a decline in the fair value of the term deposit investments is limited because these investments have an original term of less than one year and are generally held to maturity. The promissory note owed to Barrick is variable with the U.S. prime rate. Based on the amount owing on the promissory note as of November 30, 2025, and assuming all other variables remain constant, a 1% change in the U.S. prime rate would result in an increase/decrease of approximately $1.6 million in the interest accrued on the promissory note per annum. For more detail with respect to the promissory note, see section Item 2, Properties – Donlin Gold Project, Alaska, below.
Risks Related to Our Industry
Mining is inherently risky and subject to conditions or events some of which are beyond our control, and which could have a material adverse effect on our business.
Mining involves various types of risks, including:
- environmental hazards;
- industrial accidents;
- metallurgical and other processing problems;
- unusual or unexpected geologic formations and conditions;
- structural cave-ins or slides;
- flooding;
- fires;
- power outages;
- labor disruptions;
- explosions;
- landslides and avalanches;
- mechanical equipment and facility performance problems;
- availability of materials and equipment;
- tailings storage facility failures;
- metals losses; and
- periodic interruptions due to inclement or hazardous weather conditions.
These risks could result in damage to, or destruction of, mineral properties, production facilities or other properties; personal injury or death, including to employees; environmental damage; delays in construction or mining operations; increased production costs; asset write downs; monetary losses; and possible legal liability. We may not be able to obtain insurance to cover these risks at economically feasible premiums or at all. Insurance against certain environmental risks, including potential liability for pollution or other hazards as a result of the disposal of waste products occurring from mineral production, is not generally available to us or to other companies within the mining industry. We may suffer a material adverse impact on our business if we incur losses related to any significant events that are not covered by our insurance policies.
Exploration, construction, and production activities may be limited or delayed by inclement weather and shortened exploration, construction and operating seasons. For example, Donlin Gold proposes to transport the bulk of the supplies required to operate the Donlin Gold project to the site from ports in the United States and Canada. This would require the supplies to be transported by barge on the Kuskokwim River which is free of ice and open for barge traffic for a limited period each year. Delays in the ice breakup or early freeze-up, low flow levels and water depths, or other conditions affecting the Kuskokwim River could delay or prevent Donlin Gold from transporting supplies to the site. Any such interference with the delivery of needed supplies to the Donlin Gold project could adversely affect the construction or operation of the project and/or the costs associated with these activities which, in turn, would adversely affect our business.
We are subject to significant governmental regulation.
Our operations, exploration and development activities in the United States, are subject to extensive federal, state and local laws and regulations governing various matters, including:
- environmental protection;
- management and use of toxic substances and explosives;
- management of tailings and other wastes generated by our operations;
- management of natural resources;
- exploration and development of mines, production and post-closure reclamation;
- exports;
- price controls;
- taxation, tariffs and mining royalties;
- regulations concerning business dealings with indigenous groups;
- availability and use of water resources;
- labor standards and occupational health and safety, including mine safety; and
- preservation of historic and cultural resources.
Failure to comply with applicable laws and regulations may result in civil or criminal fines or penalties or enforcement actions, including orders issued by regulatory or judicial authorities enjoining, curtailing or closing operations or requiring corrective measures, installation of additional equipment or remedial actions, any of which could result in us incurring significant expenditures. We may also be required to compensate private parties suffering loss or damage by reason of a breach of such laws, regulations or permitting requirements. It is also possible that future laws and regulations, or a more stringent enforcement of current laws and regulations by governmental authorities, could cause additional expense, capital expenditures, restrictions on or suspensions of our operations and delays in the exploration and development of our mineral properties.
Our activities are subject to environmental laws and regulations that may increase our costs of doing business and restrict our operations.
Our exploration, potential development and production activities in the United States are subject to regulation by governmental agencies under various environmental laws. To the extent that we conduct exploration activities or undertake new mining activities in other foreign countries, we will also be subject to environmental laws and regulations in those jurisdictions. These laws address emissions into the air, discharges into water, management of waste, management of hazardous substances, use of water, protection of natural resources, antiquities and endangered species, and reclamation of lands disturbed by mining operations. Environmental legislation and regulations continue to evolve, and the trend has been toward stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of proposed projects and increasing responsibility for companies and their officers, directors and employees. Compliance with environmental laws and regulations may require significant capital outlays on our behalf and may cause material changes or delays in our intended activities. There can be no assurance that future changes in environmental regulations will not adversely affect our business, and it is possible that future changes in these laws or regulations could have a significant adverse impact on some portion of our business, causing us to re-evaluate those activities at that time.
Environmental hazards may exist on our mineral properties that are unknown to us at the present time, and that have been caused by previous owners or operators or that may have occurred naturally. We may be liable for remediating such damage.
Failure to comply with applicable environmental laws, regulations and permitting requirements may result in enforcement actions thereunder, including orders issued by regulatory or judicial authorities, causing operations to cease or to be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment or remedial actions.
Our insurance will not cover all of the potential risks associated with mining operations.
Our business is subject to a number of risks and hazards generally including adverse environmental conditions, industrial accidents, labor disputes, unusual or unexpected geological conditions, ground or slope failures, cave-ins, changes in the regulatory environment and natural phenomena, such as inclement weather conditions, floods, hurricanes and earthquakes. Such occurrences could result in damage to mineral properties or production facilities, personal injury or death, environmental damage to our properties or the property of others, delays in construction or mining, monetary losses, and possible legal liability.
Although we maintain insurance to protect against certain risks in such amounts as we consider reasonable, our insurance will not cover all the potential risks associated with a mining company’s operations. We may also be unable to maintain insurance to cover these risks at economically feasible premiums. Insurance coverage may not continue to be available or may not be adequate to cover any resulting liability. Moreover, insurance against risks such as loss of title to mineral property, environmental pollution, or other hazards, as a result of exploration and production is not generally available to us or to other companies in the mining industry on acceptable terms. We might also become subject to liability for pollution or other hazards which may not be insured against or which we may elect not to insure against because of premium costs or other reasons. Losses from these events may cause us to incur significant costs that could have a material adverse effect on our financial performance and results of operations.
Title and other rights to our mineral properties cannot be guaranteed and may be subject to prior unregistered agreements, transfers or claims and other defects.
We cannot guarantee that title to our mineral properties will not be challenged. We may not have, or may not be able to obtain, all necessary surface rights to develop a mineral property. Title insurance is generally not available for mineral properties and our ability to ensure that we have obtained secure claim to individual mineral properties or mining concessions may be severely constrained. Our mineral properties may be subject to prior unregistered agreements, transfers or claims, and title may be affected by, among other things, undetected defects. We have not conducted surveys of all the mineral properties in which we hold direct or indirect interests. A successful challenge to the precise area and location of these mineral properties could result in us being unable to operate on our mineral properties as permitted or being unable to enforce our rights with respect to our mineral properties. This could result in us not being compensated for our prior investment relating to the mineral property.
Rising metal prices encourage mining exploration, development, and construction activity, which in the past has increased demand for and cost of contract mining services and equipment.
Increases in metal prices tend to encourage increases in mining exploration, development, and construction activities. During past expansions, demand for and the cost of contract exploration, development and construction services and equipment have increased as well. Increased demand for and cost of services and equipment could cause project costs to increase materially, resulting in delays if services or equipment cannot be obtained in a timely manner due to inadequate availability, and increased potential for scheduling difficulties and cost increases due to the need to coordinate the availability of services or equipment, any of which could materially increase project exploration, development, or construction costs, result in project delays, or both. There can be no assurance that increased costs may not adversely affect our development of our mineral properties in the future.
We may experience difficulty attracting and retaining qualified management and technical personnel to meet our business objectives, and the failure to manage our business effectively could have a material adverse effect on our business and financial condition.
We are dependent on the services of key executives including our President and Chief Executive Officer and other highly skilled and experienced executives and personnel focused on managing our interests and the advancement of the Donlin Gold project, in addition to the identification of new opportunities for growth and funding. Due to our relatively small size, the loss of these persons or our inability to attract and retain additional highly skilled employees required for the development of our activities may have a material adverse effect on our business or future operations.
We may be subject to legal proceedings.
Due to the nature of our business, we may be subject to a variety of regulatory investigations, claims, lawsuits, and other proceedings in the ordinary course of our business. The results of these legal proceedings cannot be predicted with certainty due to the uncertainty inherent in litigation, including the effects of discovery of new evidence or advancement of new legal theories, the difficulty of predicting decisions of judges and juries and the possibility that decisions may be reversed on appeal. There can be no assurances that these matters will not have a material adverse effect on our business.
General Risk Factors
Global climate change is an international concern and could impact our ability to conduct future operations.
Global climate change is an international issue and receives an enormous amount of publicity. We would expect that the imposition of international treaties or U.S. or Canadian federal, state, provincial, or local laws or regulations pertaining to mandatory reductions in energy consumption or emissions of greenhouse gasses could affect the feasibility of mining projects and increase operating costs.
The Donlin Gold project is not directly threatened by current predictions of sea level rise as it is located inland at elevations 150 meters to 640 meters above sea level. However, changes in sea levels could affect ocean and river transportation and shipping facilities, which would be used to transport supplies, equipment and personnel to the Donlin Gold project and products from the project to world markets. The Donlin Gold project proposes to deliver the vast majority of construction and operations equipment, supplies, consumables, and other required materials to the project site via the Kuskokwim River when it is ice-free. Historically, the Kuskokwim River has been ice-free from late April until mid-October and models based on historic weather and river flow records predict that there would be sufficient flow in the river to allow the transportation of the required materials to the project site annually. If climate changes alter the ice-free season or flow patterns of the Kuskokwim River, the current supply logistics plan for the project may need to be modified.
Climate changes also could affect the availability of water required to sustain operations at the Donlin Gold project. Also, management of water is an essential component of the project’s operating plans. Climate change could require modifications to the project’s water management plan, which may require additional capital investments or increase operating costs, if precipitation increases or decreases relative to historic records.
Extreme weather events (such as increased frequency or intensity of storms, increased snowpack, prolonged drought, and associated fire danger) have the potential to disrupt operations. Where appropriate the Donlin Gold project has developed contingency plans for managing extreme weather conditions; however, extended disruptions to supply lines due to extreme weather could result in interruption of activities at the project site, delay or increase the cost of construction of the project, or otherwise adversely affect our business.
The Company is dependent upon information technology systems, which are susceptible to disruption, damage, failure, and risks associated with implementation and integration.
The Company’s information technology systems used in its operations are subject to disruption, damage, or failure from a variety of sources, including, without limitation, computer viruses, security breaches, cyberattacks, natural disasters and defects in design. Cybersecurity incidents are evolving and include, but are not limited to, malicious software, attempts to gain unauthorized access to data or machines and equipment, and other electronic security breaches that could lead to disruptions in systems, unauthorized release of confidential or otherwise protected information, the corruption of data or the disabling, misuse or malfunction of machines and equipment. Various measures have been implemented to manage the Company’s risks related to information technology systems and network disruptions. However, given the unpredictability of the timing, nature and scope of information or operational technology disruptions, the Company could potentially be subject to the compromising of confidential or otherwise protected information, destruction or corruption of data, security breaches, other manipulation or improper use of our systems and networks or financial losses from remedial actions, any of which could have a material adverse effect on cash flows, financial condition or results of operations.
The Company could also be adversely affected by system or network disruptions if new or upgraded information technology systems are defective, not installed properly or not properly integrated into operations. Various measures have been implemented to manage the risks related to the system implementation and modification, but system modification failures could have a material adverse effect on the Company’s business, financial position, and results of operations.
The Company believes it was a passive foreign investment company for its fiscal year ended November 30, 2025 which could have negative tax consequences for U.S. investors.
U.S. Holders (as defined below under Item 5. Market for Registrant’s Common Equity, Related Shareholder Matters and Issuer Purchases of Equity Securities “Certain United States Federal Income Tax Considerations for U.S. Holders – U.S. Holders”) should be aware that the Company believes that it was a PFIC (as defined below under Item 5. Market for Registrant’s Common Equity, Related Shareholder Matters and Issuer Purchases of Equity Securities “Certain United States Federal Income Tax Considerations for U.S. Holders – Passive Foreign Investment Company Rules”) for the fiscal year ended November 30, 2025, and based on current business plans and financial expectations, may be a PFIC in the current tax year and future tax years. If the Company is a PFIC for any year during a U.S. Holder’s holding period of common shares, then such U.S. Holder generally will be required to treat any gain realized upon a disposition of the common shares or any so-called “excess distribution” received on its common shares as ordinary income, and to pay an interest charge on a portion of such gain or distribution. In certain circumstances, the sum of the tax and the interest charge may exceed the total amount of proceeds realized on the disposition, or the amount of excess distribution received, by the U.S. Holder. Subject to certain limitations, these tax consequences may be mitigated if a U.S. taxpayer makes a timely and effective QEF Election or Mark-to-Market Election (each as defined below under Item 5. Market for Registrant’s Common Equity, Related Shareholder Matters and Issuer Purchases of Equity Securities “Certain United States Federal Income Tax Considerations for U.S. Holders – Default PFIC Rules under Section 1291 of the Code”). A U.S. Holder who makes a timely and effective QEF Election generally must report on a current basis its share of the Company’s net capital gain and ordinary earnings for any year in which the Company is a PFIC, whether or not the Company distributes any amounts to its shareholders. A U.S. Holder who makes a Mark-to-Market Election in respect of its common shares generally must include as ordinary income each year the excess of the fair market value of the common shares over the U.S. Holder’s tax basis therein. This paragraph is qualified in its entirety by the discussion below under Item 5. Market for Registrant’s Common Equity, Related Shareholder Matters and Issuer Purchases of Equity Securities “Certain United States Federal Income Tax Considerations for U.S. Holders.” Each U.S. Holder should consult its own tax advisor regarding the PFIC rules and the U.S. federal income tax consequences of the acquisition, ownership, and disposition of common shares.
Cybersecurity
As filed, 4,802 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Risk Management and Strategy
The Company utilizes a sophisticated network monitoring service as a first line of defense to identify, assess, manage, mitigate and respond to cybersecurity threats, which is supplemented by employee training to ensure rapid internal responsiveness should an incident be detected. The Company regularly assesses the threat landscape and takes a holistic view of cybersecurity risks, with a layered cybersecurity strategy based on prevention, detection and mitigation.
Recognizing the complexity and evolving nature of cybersecurity threats, we have partnered with a third-party cybersecurity company to leverage specialized knowledge and insights, ensuring our cybersecurity strategies and processes remain at the forefront of industry best practices. Our cybersecurity partner works to continuously scan and monitor our networks for threats and vulnerabilities, alert management in real-time with high-risk cybersecurity incidents, provide quarterly management updates summarizing recent cybersecurity activity and provide access to a 24/7 incident response team. This partnership is actively managed by the Chief Financial Officer (“CFO”) to ensure effective implementation.
We recognize the importance of developing, implementing, and maintaining robust cybersecurity measures to safeguard our information systems and protect the confidentiality, integrity, and availability of our data. As a result, we have integrated cybersecurity risk management into our broader risk management framework to promote a holistic approach toward assessing, identifying, and managing material risks associated with cybersecurity threats. This integration ensures that cybersecurity considerations are an integral part of the decision-making processes throughout our organization.
As of the date of this Annual Report on Form 10-K, we have not identified risks from cybersecurity threats, including threats from any previous cybersecurity incidents, that have or are reasonably likely to materially affect us, including our operations, business strategy, results of operations, or financial condition. While we continually work to safeguard the information systems we use, and the proprietary, confidential and personal information residing therein, and mitigate potential risks, there can be no assurance that such actions will be sufficient to prevent cybersecurity incidents or mitigate all potential risks to such systems, networks and data or those of our third-party providers. For additional information, refer to Item 1A. Risk Factors – The Company is dependent upon information technology systems, which are susceptible to disruption, damage, failure, and risks associated with implementation and/or integration, above.
The Audit Committee has been delegated, by and on behalf of the Board, direct and primary oversight of the Company’s cybersecurity risk exposures and the steps taken by management to monitor, mitigate and manage/respond to cybersecurity risks and incidents. The CFO is responsible for overseeing NOVAGOLD’s cybersecurity program and other IT activities. No less than annually, the CFO briefs the Audit Committee on the effectiveness of the Company’s cyber risk management program on a wide range of topics, including recent developments, vulnerability assessments, the threat environment, technological trends and information security considerations arising with respect to the Company. The Board and the Audit Committee receive prompt and timely information regarding any cybersecurity incident that meets the SEC, Canadian Securities Administrators and stock exchange-established reporting thresholds, as well as ongoing updates and follow-up disclosures regarding any such incident until it has been wholly addressed and remediated.
Governance
Cybersecurity is an important part of our risk management processes and an area of focus for our Board and management team. Our Audit Committee is responsible for the Board-level oversight of risks from cybersecurity threats. Members of our Audit Committee receive updates from the CFO at least annually and more frequently if warranted, regarding Company practices, programs, and other developments related to cybersecurity, cyber threats and our cybersecurity risk management and strategy program. Our Audit Committee is comprised of Board members with diverse and relevant expertise in risk management and strategy, sufficient to oversee cybersecurity risks effectively.
We maintain a cybersecurity incident response team composed of professionals across various functions, including information technology, legal, finance, accounting, and risk. This team is trained in managing cybersecurity incidents and leverages the information technology expertise of our third-party cybersecurity partner.
Properties
As filed, 84,597 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
The Company has adopted the mining disclosure standards of *Subpart 229.1300 of Regulation S-K – Disclosure by Registrants Engaged in Mining Operations (“*S-K 1300”). The Company is subject to and required to disclose mineral resources and mineral reserves in accordance with S-K 1300. While the S-K 1300 rules are similar to NI 43-101 rules in Canada, they are not identical and therefore two reports have been produced for the Donlin Gold project. The information in Item 2, Properties, below is common to both reports and contains pertinent information required under S-K 1300.
Donlin Gold Technical Report (NI 43-101)
During 2025, the Company retained Wood Group USA Inc. (“Wood”) and Geosyntec Consultants International, Inc. (“Geosyntec”), unaffiliated third-party firms comprising mining experts, to update content in its previously filed “NI 43-101 Technical Report on the Donlin Gold Project, Alaska, USA,” with an effective date of June 1, 2021 (the “2021 Technical Report”). Wood and Geosyntec’s Qualified Persons (“QPs”) completed an exercise to verify which content in the 2021 Technical Report remains current, and what was required to update the report content with the latest information. Updated content includes legal agreements, drill hole database, geologic model, mineral resource estimates, mine plan, mineral reserve estimates, production schedule, operating costs, capital costs, tax law summary, long-term gold price, and the economic analysis. Additionally, work done on the property since 2021 with respect to exploration, drilling, permitting, and minor mine design changes as a result of recent permitting activities are summarized in the updated content. A data verification exercise was completed by each Wood and Geosyntec QP co-authoring the report. This included an August or September 2025 site visit by six of the report QPs; review of the drill and assay data, geologic data, geologic model, and resource model; review of metallurgical test work; review of designs for processing and infrastructure, including minor design updates; update of capital and operating cost estimates utilizing a combination of cost indices and vendor quotations; and updated mine designs, production schedule, and economic analysis. Canadian NI 43-101 Definitions, CIM Definition Standards for Mineral Resources and Mineral Reserves (“CIM Definition Standards”), adopted by CIM Council on May 10, 2014, and CIM Estimation of Mineral Resources and Mineral Reserves Best Practice Guidelines, November 29, 2019 (CIM MRMR Best Practice Guidelines) apply for this exercise.
The Wood and Geosyntec review determined that there was no material change to the mineral resources or mineral reserves as increases in operating costs since the 2021 Technical Report were generally offset by increases in the long-term gold price used in the study. On January 22, 2026, the Company filed an updated NI 43-101 technical report for the Donlin Gold project in Alaska, USA, and titled “NI 43-101 Technical Report on the Donlin Gold Project, Alaska, USA,” with an effective date of November 30, 2025 (the “2025 Technical Report”) reflecting the results of the above exercise. The 2025 Technical Report was prepared by Wood and Geosyntec. The 2025 Technical Report is available on the Company’s website and on SEDAR+ at www.sedarplus.ca (http://www.sedarplus.ca).
Donlin Gold Technical Report Summary (S-K 1300)
The Company is a registrant with the SEC and is reporting its exploration results, mineral resources or mineral reserves using the mining disclosure standards of S-K 1300. The Company requested that Wood and Geosyntec update content in its previously filed “S-K 1300 Technical Report Summary on the Donlin Gold Project, Alaska, USA”, with a report date of November 30, 2021 (the “2021 Technical Report Summary”). Material aspects of the 2021 Technical Report Summary were updated by Wood in 2025 and made current with “S-K 1300 Technical Report Summary on the Donlin Gold Project, Alaska, USA”, with a report date of November 30, 2025 (the “2025 Technical Report Summary”). As part of the update process, Wood’s subject matter experts completed an exercise to verify and update the content of the 2021 Technical Report Summary with the latest information under the supervision of Wood and Geosyntec’s QPs. Updated content includes legal agreements, drill hole database, geologic model, resource estimates, mine plan, mineral reserve estimates, production schedule, operating costs, capital costs, forecast long-term gold price and the economic analysis. Additionally, work done since 2021 on the property with respect to exploration, drilling, permitting and minor project design changes as a result of recent permitting activities are summarized in the 2025 Technical Report Summary. A data verification exercise was completed by Wood and Geosyntec QPs. Wood and Geosyntec QPs verified that the updated content of the 2021 Technical Report Summary met at least pre-feasibility level of study as defined in S-K 1300, and it supports the disclosure of exploration results, mineral resources, and mineral reserves using S-K 1300 standards. The 2025 S-K 1300 Technical Report Summary is available on the Company’s website and on EDGAR at www.sec.gov (http://www.sec.gov). None of Wood or Geosyntec or their QP employees are affiliated with the Company or Donlin Gold.
Results of the Donlin Gold Technical Report (NI 43-101) and Donlin Gold Technical Report Summary (S-K 1300 Technical Report Summary)
Wood and Geosyntec used the recent drilling results (through December 31, 2024), updated costs, and long-term forecast gold prices to update the geologic and mineral resource models and prepare mineral resource estimates that are current as of November 30, 2025. The 2025 mineral resource model was used in the updated mine plan, along with current technical and economic inputs to the modifying factors to generate updated mineral reserve estimates that are current as of November 30, 2025. A long-term gold price of US$2,400 per ounce was used for the mineral resource estimates, and US$2,100/oz for the mineral reserves. The difference in gold price is to ensure the mineral reserves are a sub-set of the mineral resources. A comparison of the 2021 mineral resources and mineral reserves to the 2025 mineral resources and mineral reserves shows no material change to the estimates. The increase in costs were generally offset by the increased gold prices.
Outside of verifying the mineral resource and mineral reserve estimates, the primary efforts in the 2025 Technical Report and the 2025 Technical Report Summary were to incorporate recent exploration drilling data and updated economic assumptions. This includes updates to estimated capital costs, operating costs, reclamation and closure costs, royalties, taxes, and economic analysis, as well as current status of the permits. Updated capital costs are based on fourth calendar quarter 2025 pricing (cost indices and current commodity pricing and equipment quotes) applied to the engineering designs and material take-offs from the “Donlin Creek Gold Project Alaska, USA NI 43-101 Technical Report on the Second Updated Feasibility Study,” effective November 18, 2011, and amended January 20, 2012 (the “2011 Mining Study”), except for minor changes made during permitting in the operations water treatment plant and the natural gas pipeline. As a result of the content updates, the total initial capital cost estimate is $9,233 million, which is an increase of 24.7% or $1,831 million compared to the 2021 Technical Report Summary total initial capital cost estimate. Likewise, the total sustaining capital estimate is $2,325 million, which is an increase of 34.9% or $602 million compared to the 2021 Technical Report Summary total sustaining capital estimate. The 2021 Technical Report Summary operating costs were updated to fourth calendar quarter 2025 by updating key cost drivers like energy, labor, consumables, and freight. The manning schedules and consumables remain largely unchanged. The updated estimated Life of Mine (“LOM”) operating costs total $24,504 million.
The economic evaluation of the Donlin Gold project in both the 2025 Technical Report and the 2025 Technical Report Summary was updated using the following inputs:
- An updated open pit production plan based on 53,500 t/d ore processing by means of crushing, grinding, flotation, pressure oxidation, cyanidation and doré production. The pit designs and mineral reserves were based on the measured and indicated mineral resource estimates. Annual LOM gold production averages 1.1 million ounces per year over a production life of 27 years, including 1.4 million ounces per year for the first five full years of production.
- $2,100/oz gold price
- Current land and royalty agreements
- Initial and sustaining capital costs, and operating costs updated to fourth calendar quarter 2025
- Tax payments in accordance with the Tax Cuts and Jobs Act (“TCJA”) enacted in December 2017 and largely effective January 1, 2018, and the One Big, Beautiful Bill Act (“OBBBA”) enacted in 2025, which extended or made permanent many TCJA provisions
- $423 million LOM contributions for reclamation, closure, and financial assurance
- Financing has been assumed on a 100%, all equity, stand-alone basis
- Escalation/inflation has been excluded
- No salvage is assumed at the end of operations
Based on the economic evaluation, the Donlin Gold project generates positive before and after-tax economic results. Total after-tax cash flow is $19,614 million, after-tax NPV at a 5% discount rate is $5,058 million, and the after-tax internal rate of return is 10.3%. After-tax payback is achieved 6.5 years following the start of production.
The following descriptions summarize selected information about the Company’s 60% interest in the Donlin Gold project located in Alaska, USA. Except for subsequent events or as otherwise noted, the disclosure in this Annual Report on Form 10-K of a scientific or technical nature for the Donlin Gold project is based on both the 2025 Technical Report and the 2025 Technical Report Summary, as of November 30, 2025. The 2025 Technical Report Summary meets at least a pre-feasibility level. The 2025 Technical Report and the 2025 Technical Report Summary do not incorporate the latest Donlin Gold drill program, optimization work on the geologic modeling concepts, or other optimization work since these assessments are still underway.
The 2025 Technical Report was filed on SEDAR+ on January 22, 2026. The 2025 Technical Report Summary was filed on EDGAR on January 22, 2026. The 2025 Technical Report and the 2025 Technical Report Summary were prepared by Wood and Geosyntec.
The 2025 Technical Report has been filed with securities regulatory authorities in each province of Canada and the 2025 Technical Report Summary has been filed with the SEC. Portions of the following information are based on assumptions, qualifications and procedures that are not fully described herein. Reference should be made to the full text of the 2025 Technical Report which is available for review on SEDAR+ at www.sedarplus.ca (http://www.sedarplus.ca) and the 2025 Technical Report Summary which is available for review on EDGAR at www.sec.gov (http://www.sec.gov).
Paul Chilson, P.E., a QP and an employee of the Company, has approved the mineral reserves and mineral resources included in this Annual Report on Form 10-K as of November 30, 2025 and reviewed the reserves and resources in the 2025 Technical Report and the 2025 Technical Report.
Donlin Gold Project, Alaska, USA
The Donlin Gold project (the “Project”) is a development-stage gold project held by Donlin Gold, a limited liability company that is owned 60% by the Company’s wholly-owned subsidiary, NOVAGOLD Resources Alaska Inc., and 40% by Donlin Gold Holdings LLC, a subsidiary of Paulson. The Company’s book value of its investment in the Donlin Gold project is $213.2 million as of November 30, 2025.
Prior to June 3, 2025, Donlin Gold was owned equally by wholly-owned subsidiaries of NOVAGOLD and Barrick since December 1, 2007 when the Company entered into the limited liability company agreement with Barrick (“LLC Agreement”). Pursuant to the LLC Agreement, the Company agreed to reimburse Barrick out of future mine production cash flow for a portion of Barrick’s prior expenditures on the Donlin Gold project. As of November 30, 2025, the promissory note, including accrued interest, amounted to approximately $166.3 million. Concurrent with the closing of the Donlin Gold transaction on June 3, 2025 whereby Barrick sold its 50% interest in Donlin Gold to Donlin Gold Holdings LLC and NOVAGOLD Resources Alaska, Inc., the Company entered into an amended and restated secured promissory note with Barrick that provides the Company with the option to prepay the promissory note in full for $100 million on or before December 3, 2026. For more information regarding the amended and restated secured promissory note, refer to “Amended and Restated Promissory Note” in Management’s Discussion and Analysis.
Except for events subsequent to the reports, or as otherwise stated or implied, the scientific and technical information regarding the Donlin Gold project in this Annual Report on Form 10-K is based on both the 2025 Technical Report and the 2025 Technical Report Summary.
Property Description and Location
The Donlin Gold deposits are situated approximately 61°86’ north latitude and 158°13’ west longitude, which is 450 km west of Anchorage and 250 km northeast of Bethel up the Kuskokwim River. The closest village is the community of Crooked Creek, approximately 20 km to the south, on the Kuskokwim River.
The resource areas are within T. 23 N., R. 49. W., Seward Meridian, Kuskokwim and Mt. McKinley Recording Districts, Crooked Creek Mining District, Iditarod A-5 USGS 1:63,360 topography map. The mineralization is centered on approximately 540222.50 east and 6878534.36 north, using the NAD 83 datum.
The Donlin Gold property is located in the Kuskokwim region of southwestern Alaska on private, Alaska Native-owned mineral and surface land and Alaska state mining claims. The property is under the Calista Lease for subsurface rights and some surface rights from Calista and SUA from TKC, two Alaska Native corporations. Calista is one of 13 regional Alaska Native corporations established as part of the Alaska Native Claims Settlement Act of 1971 (“ANCSA”) and under ANCSA has title to the subsurface estate and some surface rights in the region. TKC was formed in 1977 when the ANCSA village corporations of Lower Kalskag, Upper Kalskag, Aniak, Chuathbaluk, Napaimute, Crooked Creek, Red Devil, Georgetown, Sleetmute and Stony River, which are located along the middle region of the Kuskokwim River, merged. Under ANCSA, TKC has title to extensive surface estate in the region, including most of the project lands. The property hosts a gold deposit currently estimated at 32.8 million ounces of proven and probable mineral reserves averaging 2.02 grams per tonne. The Company believes that significant exploration potential remains in the Donlin Gold district, with prospects to increase mine life and/or justify future production expansions. See Mineral Reserve and Mineral Resource Estimate, below.
Other lands required for offsite infrastructure, such as the Jungjuk port site, the road from the port site to the mine site, and natural gas pipeline are categorized as Native, State of Alaska conveyed, or BLM lands. Rights-of-way are required from other Alaska Native corporations, the State of Alaska and BLM for the road and pipeline alignments that cross Native corporation, state, and federal lands.
Permits
The Project is subject to a rigorous permitting regime at federal, state, and local levels. Major permits obtained include the USACE Section 404/10 permit (with a JROD issued in 2018), the ADEC Integrated Waste Management Permit, Air Quality Control Permit, and APDES permit. Additional permits for water rights, dam safety, and fish habitat are in place or in process. BLM and ADNR have issued right-of-way (“ROW”) authorizations for the natural gas pipeline. The Project is working to secure a land agreement from Cook Inlet Region, Inc. (“CIRI”) for the remaining piece of the ROW for the natural gas pipeline.
All permits remain current, with renewals processed as required and no expirations to date. Several permits have been administratively extended, merged into other ROW permits, or are under review for extensions consistent with regulatory timelines and Project contingencies. The permitting process has included extensive agency and stakeholder consultation, and the Project is designed to comply with the NEPA Clean Water Act, Alaska Dam Safety Guidelines, and other applicable regulations.
Donlin Gold obtained the necessary permits and certifications that allowed for the exploration, environmental monitoring, and Environmental Impact Study (“EIS”) baseline data collection efforts. The current status of these permits is in line with the termination of the baseline data collection effort, temporary closure of the camp in May 2015, and the seasonal reopening of the site for the geological drill program from July to November 2017, the geotechnical drill program in 2019 and 2023 for the Alaska Dam Safety certificate applications, and the latest geological drill programs in 2020, 2021, 2022 and 2025. The active permits include Alaska Department of Natural Resources (“ADNR”) temporary use of water; ADNR Application for Permit to Mine in Alaska (approval for the 2020, 2021, 2022, 2023 and 2025 drill programs), the Corps individual 404 and nationwide 26 permits; Alaska Department of Environmental Conservation (“ADEC”) authorizations (landfill, septic system, multisector stormwater general permit – sector G, air permit); and Federal Aviation Administration approval. Other permits were either put on hold, closed, or allowed to expire.
On August 7, 2012, we announced that Donlin Gold commenced permitting of the project by submitting a draft Plan of Operations and Section 404 Clean Water Act (“CWA”) draft permit application to federal and state regulators. The Section 404 permit application initiated the environmental review process under the National Environmental Policy Act (“NEPA”) which involves preparation of an EIS. The Corps selected AECOM, formerly URS, an independent contractor, to prepare the EIS. The Notice of Intent for the EIS was published in the Federal Register on December 14, 2012, and the NEPA public scoping process was completed on March 29, 2013. During the remainder of 2013 and through 2014 and 2015, Donlin Gold worked to address the remaining data needs for the draft EIS. Donlin Gold also continued to provide application materials and maintained ongoing dialogue with the key permitting agencies. The Corps addressed the cooperating agency comments on the preliminary draft and filed the Notice of Availability for public release of the draft EIS in the Federal Register in November 2015. After the filing of the draft EIS, the Corps issued a schedule for public meetings on the Donlin Gold draft EIS in the Y-K region and Anchorage, Alaska. The Corps conducted, and at the end of May 2016 completed, a six-month public comment period for the draft EIS, including 17 public comment meetings in communities across the Y-K region and in Anchorage. The Corps received comments from federal and state agencies, local and tribal governments, Alaska Native organizations, businesses, special interest groups/NGOs, and individuals.
On April 27, 2018, the Notice of Availability of the Donlin Gold final EIS was published in the Federal Register. On August 13, 2018, the Corps and the BLM issued a joint Federal Record of Decision (“ROD”) for the Donlin Gold project. Along with the ROD, the Corps issued a combined permit under CWA Section 404 and Section 10 of the Rivers and Harbors Act. Additionally, the BLM issued the Offer to Lease for the state pipeline ROW for those portions of the natural gas pipeline that would cross federal lands. The Pipeline and Hazardous Materials Safety Administration previously issued a special permit for the natural gas pipeline on June 5, 2018. As a result of a legal challenge, discussed in further detail below, the Corp and BLM are undertaking a supplementation of the EIS to analyze the environmental impacts of a larger hypothetical release from the tailings storage facility. The CWA permits and BLM ROW remain in place during this supplementation, which is being undertaken under the Fixing America’s Transportation Act (“FAST-41”) program coordinated by the Federal Permitting Improvement Steering Council (“Permitting Council”). The Corp has submitted a schedule for completing the supplemental analysis by mid-2027 to the Federal Permitting Improvement Steering Council.
Several major State of Alaska permits were also issued and advanced during 2018 through 2023. After a public notice and comment period, ADEC issued a Certificate of Reasonable Assurance under CWA Section 401 on August 10, 2018, indicating that the CWA 404 permit complies with the state’s water quality standards. The Alaska Pollutant Discharge Elimination System (“APDES”) water discharge permit was issued by ADEC on May 24, 2018 and became effective on July 1, 2018. Donlin Gold submitted its application to ADEC for the regularly scheduled re-issuance of its APDES permit, which originally was to expire in January 2024, but has been administratively extended pending renewal. The State of Alaska Department of Fish and Game (“ADFG”) issued Title 16 Fish Habitat permits for the mine area and transportation corridor on August 30, 2018. The new air quality permit was issued by ADEC on July 1, 2023. The final approvals of the Donlin Gold Reclamation Plan and the Waste Management Permit were issued by ADNR and ADEC, respectively on January 18, 2019. On September 18, 2023, Donlin Gold submitted timely applications to ADEC and ADNR for renewal of the approval and permit. On October 17, 2023, ADEC administratively extended the Waste Management Permit pending renewal. The Reclamation Plan approval, which was also to expire in January 2024, has been administratively extended to January 2026. ADNR issued the easement, land leases, land use permits, and material site authorizations for the proposed transportation facilities, and easement for the fiber optic cable on state lands on January 2, 2020. On January 17, 2020, ADNR’s State Pipeline Coordinator Services issued the final state ROW authorization for the natural gas pipeline. On June 29, 2021, ADNR’s Division of Mining Land and Water issued 12 final Water Rights for the mine site and transportation corridor. On November 1, 2021, ADFG issued two Special Area Permits required for pipeline facilities located within the Susitna Flats State Game Refuge (“Refuge”). One permit authorizes the compressor station, and the other permit authorizes the section of the pipeline ROW in the Refuge. On November 1, 2022, ADNR finalized approval of the proposed re-location plan for public easements in the mine site and transportation facility areas.
The Project is working to secure a land agreement from CIRI for the remaining piece of the ROW for the natural gas pipeline. CIRI and Donlin Gold LLC have agreed on the terms of this lease and are working on finalizing the agreement. Other operational permits will be required immediately prior to construction, such as stream crossing from ADF&G, water sources from ADNR, and development from the Matanuska-Susitna borough. Legal challenges to ADNR’s issuance of the ROW are also complete with the Alaska Supreme Court issuing a ruling in November upholding ADNR’s issuance of the ROW.
On April 5, 2023, Earthjustice, representing Orutsararmiut Traditional Native Council (“ONC”), Kwethluk, and Tuluksak filed suit in the United States Federal Court for the District of Alaska, challenging BLM’s and the USACE’s issuance of the JROD.
On June 10, 2025, the District Court of Alaska issued an order remanding the matter to the federal agencies to supplement the EIS to include analysis of a larger hypothetical tailings release. The Court did not vacate the permits. Donlin Gold LLC has started working on the supplemental briefing while a Notice of Intent is expected from the Army Corp of Engineers in early 2026.
Mineral Tenure
The Calista Lease between Calista and Donlin Gold, includes subsurface (mineral) rights leased from Calista. Calista also owns the corresponding surface estate on a portion of these lands, the rights to which are also included in the Calista Lease. The Calista Lease provides Donlin Gold with rights to approximately 19,988 hectares of Calista-owned land. The Calista Lease was restated on February 11, 2011, to reflect all assignments and amendments made between its original execution on May 1, 1995 and February 11, 2011. The Calista Lease was amended once again effective June 6, 2014 (the “2014 Amendment”). The 2014 Amendment did not affect the lands subject to the Calista Lease as restated on February 11, 2011.
On June 6, 2014, the Company announced that Donlin Gold and TKC reached an updated long-term SUA for the Donlin Gold project. The SUA with TKC grants non-exclusive surface use rights to Donlin Gold for mining activities. TKC owns and contributed to the SUA the corresponding surface estate over most of Calista’s subsurface estate included in the Calista Lease as well as some additional surface estate. The SUA with TKC provides Donlin Gold with rights to approximately 16,923 hectares of TKC-owned land.
A small surface estate of 5.7 hectares to which the Lyman family has title, is within the Snow Gulch area lying immediately to the north of the Project’s pit shell. Lyman Resources in Alaska, Inc. (“Lyman Resources”), the Lyman family and Donlin Gold LLC executed a Surface Lease and Assignment of Mining Lease assigning the Lyman placer lease, located within the Calista Lease area, to Donlin Gold LLC for mining use (the “Lyman Lease”).
In addition to the leased land, Donlin Gold holds 493 State of Alaska mining claims comprising approximately 29,008 hectares in the Kuskokwim and Mt. McKinley Recording Districts. The mining claims abut and largely surround northern and western boundaries of the lands subject to the Calista Lease and TKC SUA. The mining claims are located on lands that are owned by the State of Alaska (409) and on state-selected lands from the BLM (84). All claims are approximately either 16.2 hectares or 64.8 hectares in size.
The terms for the Calista Lease and TKC SUA include various royalty and other payment provisions and considerations such as shareholder employment and contracting opportunities. The Lyman Lease provides for rent and certain other payments.
Royalty terms of the Calista Lease include:
- Annual advance minimum royalty (variable) to 2030;
- All advance minimum payments are recoverable as a credit against the net smelter return royalty and net proceeds payment;
- Net smelter return of 1.5% for the earlier of the first five years following commencement of commercial production or until initial capital payback;
- Conversion to a 4.5% net smelter return after the earlier of five years or initial capital payback; and
- Net proceeds royalty of 8% of the net proceeds realized by Donlin Gold LLC commencing with the first quarter in which net proceeds are first realized.
Payment terms of the TKC SUA include:
- Annual advance minimum payment (variable per milestones);
- All advance minimum payments are recoverable as a credit against the milled tonnage fee and net proceeds payment;
- Milled tonnage fee of $0.40 per tonne processed for the first 10 years of production;
- Conversion of the milled tonnage fee to $0.50 per tonne processed for all production after 10 years; and
- Net proceeds payment of 3% of the net proceeds realized by Donlin Gold LLC commencing with the first quarter in which net proceeds are first realized.
The term of the Calista Lease is to April 30, 2031 and extends automatically year to year thereafter, so long as either mining or processing operations are carried out on or with respect to the property in good faith on a continuous basis in such year, or Donlin Gold pays to Calista an advanced minimum royalty of $3.0 million (subject to adjustment for increases in the Consumer Price Index) for such year. The TKC SUA remains in effect through April 30, 2031, and on a year-to-year basis thereafter, so long as the Calista Lease remains in effect. The Lyman Lease has an initial term of 20 years but shall be extended while Donlin Gold conducts operations on the property.
Additional estimated costs associated with various landowner and lease agreements, not already covered in initial capital or G&A operating costs, average approximately $8.6 million per year during the six pre-production years and $2.5 million per year during the 27 operating years. Annual rent, labor expenditures and filings are required to maintain Alaska State mining claims on state land. Mining license tax payments may also apply.
Accessibility and Climate
The Kuskokwim River is a regional transportation route and is serviced by commercial barge lines. A 25-kilometer winter road, designated as an Alaska State Highway route and transportation corridor, accesses the property from the barge landing at the village of Crooked Creek. The Donlin Gold project currently has an all-season, soft-sided camp. An adjacent 1,500-meter airstrip is capable of handling aircraft as large as C-130 Hercules (with a payload of 18,000 kg), allowing efficient shipment of personnel, some heavy equipment, and supplies. The Donlin Gold project can be reached directly by charter air facilities out of Anchorage and Aniak, 80 kilometers to the west.
The project area is one of low topographic relief on the western flank of the Kuskokwim Mountains. Elevations range from 150 meters to 640 meters. Ridges are well rounded and easily accessible by all-terrain vehicle. Hillsides are forested with black spruce, tamarack, alder, birch and larch. Soft muskeg and discontinuous permafrost are common in poorly drained areas at lower elevations. The area has a relatively dry interior continental climate with typically less than 500 millimeters total annual precipitation. Summer temperatures are relatively warm and may exceed 30°C. Minimum temperatures may fall to well below -42°C during the cold winter months. Permafrost is sporadic, typically confined to valley bottom and mid-slope, with thickness ranging from 1.5 m to over 15 m (average ~4 m). The site is in a seismically active region of Alaska, influenced by the collision of the Pacific and North American plates.
Exploration History
A total of 1,737 core (456,450 m) and 387 RC (37,457 m) holes conducted since 1995, were used to inform the resource estimate. Results from the 2025 drilling were compared to the geologic model and resource model and were found to support the interpretation of geology and estimation.
A total of 2,145 core and RC holes of 516,779 m were completed from 1995 through 2025 as summarized below. Holes drilled by previous operators between 1995 and 2000 include 347 core holes (86,298 m) and 77 RC holes (16,338 m). Holes drilled by Donlin Gold LLC include 491 core holes (121,383 m) and more recently 10 dual rotary holes (630 m).
| Year | Company | Work Performed | Results |
|---|---|---|---|
| 1909-1956 | Various prospectors and placer miners | ● Gold discovered on Donlin Creek in 1909 ● Placer mining by hand, underground, and hydraulic methods | ● Total placer gold production of approximately 30,000 oz |
| 1970s-present | Robert Lyman and heirs | ● Resumed sluice mining in Donlin area and placer mined Snow Gulch | ● Small scale placer mining |
| 1974, 1975 | RAA | ● Regional mineral potential evaluation for Calista ● Soil grid and three bulldozer trenches in the Snow Gulch area | ● Anomalous gold values in soil, rock, and vein samples |
| 1984-1987 | Calista | ● Minor work | ● - |
| 1986 | Lyman Resources | ● Auger drilling for placer evaluation encounters sulfide-rich clay near Quartz Gulch | ● Initial discovery of Far Side (Carolyn) prospect |
| 1987 | Calista | ● Rock sampling of ridge tops and auger drill sampling of Far Side prospect | ● Anomalous gold values from auger holes |
| 1988, 1989 | WestGold | ● Airborne geophysics, ground geophysics, geological mapping, and soil sampling over most of Project area ● Trenching at all prospects First metallurgical tests and petrographic work | ● Initial work identified eight prospects (Snow, Dome, Quartz, Carolyn, Queen, Upper Lewis, Lower Lewis, and Rochelieu) ● Drilling at most of these prospects led to identification of the Lewis areas as having the best bulk-mineable potential ● Early resource estimate performed ● WestGold dissolved by early 1990 |
35
NOVAGOLD RESOURCES INC.
| Year | Company | Work Performed | Results |
|---|---|---|---|
| 1993 | Teck | ● Trenching and soil lines in Lewis area ● Petrographic, fluid inclusion, and metallurgical work | ● Identified new mineralized areas and expanded property, completed updated resource estimate ● Metallurgical tests not favorable, property dropped |
| 1995-2000 | Placer Dome Inc. | ● 87,383 m of core, 11,909 of RC drilling, and 8,493 m of trenching | ● Drilled the American Creek magnetic anomaly (ACMA), discovered the ACMA deposit ● Numerous Mineral Resource estimations |
| 2001, 2002 | DCJV (Placer Dome Inc. / NOVAGOLD) | ● 46,495 m of core including 89.5 m of geotechnical drilling, 11,589 m of RC drilling, and 268 m of water monitoring holes ● Mineral Resource estimate | ● Expanded the ACMA resource |
| 2003-2005 | DCJV (Placer Dome Inc. / NOVAGOLD) | ● 25,448 m of core and 5,979 m of RC drilling ● Calcium carbonate exploration drilling ● Induced polarized (IP) lines for facility condemnation studies | ● Infill drilled throughout the resource area demonstrated continuity ● Discovered a calcium carbonate resource ● Poor quality IP data not useful for facility studies |
| 2006 | DCJV (Barrick / NOVAGOLD) | ● 92,804 m of core drilling for resource conversion, slope stability, metallurgy, waste rock, carbonate exploration, facilities, and port road studies | ● Geological model and internal resource updates |
| 2007 | DCJV | ● Core drilling totaled 72,257 m and included resource delineation, geotechnical and engineering, and carbonate exploration ● 13 RC holes for monitor wells and pit pump tests totaled 1,043 m ● Updated Mineral Resource estimate | ● Improved pit slope parameters ● Positive hydrogeological results ● Exploration for carbonate mineral source was negative |
| 2008 | DCLLC | ● 108 core holes totaling 33,425 m for exploration and facility related geotechnical and condemnation studies ● Metallurgical testwork: flotation variability and cyanide (CN) leach ● 54 test pits and 37 auger holes completed for overburden characterization | ● Resource expansion indicated for East ACMA ● CN leach resource potential indicated for the main resource area, Snow, and Dome prospects ● Facility sites successfully condemned ● Updated resource estimates utilizing applicable data through 2007 |
| 2009 | Donlin Gold LLC (name change) | ● 19 geotechnical core holes totaling 950 m in facility sites and to address hydrology ● Mineral Reserve and Mineral Resource estimate update | ● - |
36
NOVAGOLD RESOURCES INC.
| Year | Company | Work Performed | Results |
|---|---|---|---|
| 2010 | Donlin Gold LLC | ● Six geotechnical core holes totaling 2,090 m to evaluate slope stability of expanded pit ● Drilled 90 auger holes totaling 585 m and dug 59 test pits to further evaluate overburden conditions and gravel supplies within TSF (as defined below) area ● Mineral Reserve and Mineral Resource estimate update | ● Pit slope stability of new pit design remained acceptable ● Evaluation of construction suitability of surficial materials in TSF (as defined below) is ongoing |
| 2017 | Donlin Gold LLC | ● 16 HQ core holes totaling 7,040 m drilled within the resource area ● Acoustic televiewer surveys were completed on 12 holes. Five of the holes were also logged by geotechnical engineering consultants for pit slope geotechnical data collection ● Metallurgical sample collection was also conducted | ● Geologic, geotechnical, and assay data were incorporated into project database for internal geologic modeling and optimization updates ● Metallurgical samples were tested in 2018, primarily for flotation optimization |
| 2019 | Donlin Gold LLC | ● 30 geotechnical core holes totaling 1,060 m were drilled as part of a site investigation program in support of detailed dam design | ● Geotechnical data were incorporated into a site investigation dataset to be utilized for detailed dam design and permitting once the field program is complete |
| 2020 | Donlin Gold LLC | ● 85 holes and 23,361 m HQ core drilling in ACMA and Lewis resource areas ● Objectives on this program were to validate and increase the confidence in recent geologic modelling concepts and support future resource updates ● Acoustic and optical televiewer surveying was completed on most of the holes ● Geotechnical logging was performed on core from 10 holes | ● Available geologic and assay data were incorporated into the project database for internal geologic modeling and optimization updates ● 2020 drilling geological logs generally agrees with the DC9 geological model while suggesting local adjustments |
| 2021 | Donlin Gold LLC | ● 79 core holes totaling 24,263 m in both the ACMA and Lewis deposits to validate recent geologic modeling ● Concepts and test for extensions of high-grade zones | ● 2021 drilling geological logs and preliminary assays results generally agree with the DC9 model while suggesting local adjustments |
37
NOVAGOLD RESOURCES INC.
| Year | Company | Work Performed | Results |
|---|---|---|---|
| 2022 | Donlin Gold LLC | ● 141 core holes totaling 42,331 m in both the ACMA and Lewis deposits in-pit and below pit in sparsely drilled areas ● Platform mapping, waste rock facility condemnation drilling and geotechnical drilling for the Alaska Dam Safety certificates | ● Mapping to confirm mineralization continuity and key geological controls in representative areas of the deposit and studies to support future mining study |
| 2023 | Donlin Gold LLC | ● 42 core holes totaling 1,833 m and 13 RC holes totaling 1,279 m were drilled as part of a site investigation program in support of detailed dam design, hydrogeologic studies and seismic surveys | ● Work supports the Alaska Dam Safety certificates and mine planning and design work |
| 2024 | Donlin Gold LLC | ● Metallurgical test work, field and geochemical data collection and advancement of the Donlin Gold mineral resource model | ● Work performed will support future mining studies including closure planning |
| 2025 | Donlin Gold LLC | ● 47 core holes totaling 18,056 m comprising of infill drilling, in-pit exploration and geotechnical drilling ● 26 holes totaling 399 m geotechnical drilling at Jungjuk Port Road material sites | ● Work performed will support future mining study |
Geology
Regional Geology
The Kuskokwim region of southwestern Alaska is predominately underlain by rocks of the Upper Cretaceous Kuskokwim Group that filled a subsided northeast-trending strike-slip basin between a series of amalgamated terranes. Intermediate composition volcano-plutonic complexes intrude and overlie Kuskokwim Group rocks throughout the region.
Local Geology
The Donlin Gold deposits lie between two regional, northeast-trending, right lateral fault systems: the Denali-Farewell fault system to the south and the Iditarod-Nixon Fork fault system to the north. Undivided Kuskokwim Group sedimentary rocks and granite porphyry complexes are the main rock units.
Property Geology
Greywacke is dominant in the northern part of the area (“northern resource area” comprising Lewis, Queen, Rochelieu, and Akivik), while shale-rich units are common in the southern part of the area (“southern resource area” comprising South Lewis and ACMA).
Gold deposits are associated with an extensive Late Cretaceous–Early Tertiary gold–arsenic–antimony–mercury hydrothermal system. Gold-bearing zones exhibit strong structural and host rock control along north–northeast-trending fracture zones and are best developed where those zones intersect relatively competent host rocks. Mineralized material is most abundant in intrusive dikes and sills, but sedimentary rocks are also mineralized within strong fracture zones.
Geotechnical and Hydrology
A number of geotechnical and hydrological studies have been completed in support of at least pre-feasibility and environmental reports for Donlin Gold, including geotechnical assessments for the engineering to support design of the port site, airstrip, plant site and interconnecting roads. BGC, Inc (“BGC”). Performed geotechnical analyses for the design of the pit, waste rock facility (“WRF”), and Tailings Storage Facility (“TSF”).
The site-wide surface water and groundwater models developed by BGC, are based on extensive drill data and climatic information for the area. The groundwater model is currently being updated based on the field work completed in 2023. BGC, CEMI, Hatch Ltd., and SRK, Inc. provided hydrologic studies, design criteria and associated test work for the water treatment plant requirements during construction, operations, and closure. Lorax Environmental performed water quality modeling for the post closure pit lake.
Exploration Potential
Exploration potential in the vicinity of the Project open pit designs include extensions to the south and west of ACMA and to the north and east of Lewis. Mineralization remains open at depth under the current pit limits. Mineralization also remains open to the north of the planned pit and has been tested by shallow trenching and soil sampling, with limited drilling undertaken to date.
Exploration potential also extends outside the areas that have been the subject of the mine design. Gold mineralization is associated with an overall north–northeasterly trending high level dike/sill complex and includes the Ophir, Dome, Far Side, Quartz/Duqum, and Snow prospects.
Mineralization
Southeast-dipping north-northeast-oriented fracture zones are the primary control on gold-bearing vein distribution within the north-northeast mineralized corridors. Composite vein zones or mineralized corridors range up to 30 meters in width and extend for hundreds of meters along strike. Intrusive rocks and to a lesser extent competent massive greywacke are the most favored host rocks, and act as a secondary control on the mineralization. Gold distribution in the deposit closely mimics the intrusive rocks. The more steeply dipping sills in the ACMA sill sequence host the highest-grade and most continuous igneous-hosted mineralized zones, particularly where intersected by northeast-striking “feeder” dikes and faults. Gold grade is directly proportional to vein density and intensity of overlapping disseminated sulfide vein aureoles. The dike-dominant Lewis deposit areas consist of sheeted veins with limited disseminated sulfide in the wall rocks and are characterized by lower-grade and less continuous mineralized zones.
Gold-bearing sulfides occur in both veins and disseminated zones in mafic igneous bodies, rhyodacite dikes and sills, and sedimentary rocks. Quartz-carbonate-sulfide (pyrite, stibnite, and arsenopyrite) veins are the primary mineralized features, but gold also occurs in thin, discontinuous sulfide fracture fillings.
Minor Elements and Deleterious Materials
The most abundant minor elements associated with gold-bearing material are iron, arsenic, antimony, and sulfur. They are contained primarily in the mineral suite associated with hydrothermal deposition of gold, including pyrite, arsenopyrite, realgar, native arsenic, and stibnite. Minor hydrothermal pyrrhotite, marcasite and syngenetic or sedimentary pyrite, also account for some of the iron and sulfur.
Three elements that have processing significance are mercury, chlorine, and fluorine. Graphitic carbon and carbonate minerals would also negatively affect the metallurgical process.
Metallurgy
Sufficient metallurgical test work was completed under the direction of Barrick personnel to support the S-K 1300 Report. Gold is mainly carried by arsenopyrite. Variation is observed in processing behavior between intrusive rocks and sedimentary rocks, but less so between the geographical sources.
Process testing generated development of the following conceptual flowsheet:
- conventional crushing and grinding;
- concentration by flotation;
- pressure oxidation of the concentrate in an autoclave;
- carbon-in-leach (“CIL”) cyanidation of the oxidized concentrate;
- carbon strip and regeneration circuits;
- gold electrowinning; and
- refining and production of doré bars.
This processing concept incorporates proven commercial unit operations.
Mineral Resource and Mineral Reserve Estimates
The mineral resources and mineral reserves for the Donlin Gold project were classified using criteria appropriate under the mining disclosure definitions and standards of NI 43-101 and S-K 1300 with an effective date of November 30, 2025.
The Mineral Resource model is based on 1,737 core holes (456,450 m) and 387 RC holes (37,457 m) drilled between 1995 and 2022. Trenches, auger holes, and water wells were not used for estimation. A total of 47 holes (18,056 m) were completed in 2025 within the resource area; however, they were not used in the development of the geologic or Mineral Resource model. All 2025 drilling results were checked against the geologic and Mineral Resource model with good correlation.
Mineral Resources exclusive of Mineral Reserves are summarized in the table below.
| Category | Donlin Gold – 100% Tonnage (kt) | Contained Au (koz) | Au Grade (g/t) | Attributable to NOVAGOLD – 60% Tonnage (kt) | Contained Au (koz) |
|---|---|---|---|---|---|
| Measured | 1,432 | 54 | 1.18 | 859 | 33 |
| Indicated | 175,224 | 7,439 | 1.32 | 105,134 | 4,463 |
| Total Measured and Indicated | 176,656 | 7,493 | 1.32 | 105,994 | 4,496 |
| Inferred | 74,426 | 4,483 | 1.87 | 44,656 | 2,690 |
Notes:
1. Mineral Resources are reported exclusive of Mineral Reserves. Mineral Resources are reported on a 100% ownership basis and a 60% ownership basis. The 60% basis is attributable to NOVAGOLD through their 60% ownership interest in the joint venture that owns the mineral rights and manages the Donlin Gold project property.
2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The Wood QP has a reasonable expectation that the majority of Inferred Mineral Resources could be updated to Indicated or Measured Mineral Resources with continued exploration.
3. The Mineral Resource estimate is current as of November 30, 2025. A Wood QP is responsible for the preparation of the Mineral Resource estimate.
4. Mineral Resources are prepared in accordance with the definitions of S-K 1300.
5. The cut-off date for the sample database used in the Mineral Resource estimate is December 31, 2024. However, more recent drilling data up to November 30, 2025 was used to validate the Mineral Resource model as remaining current.
6. The point of reference for the Mineral Resource estimate is in situ.
7. Mineral Resources are constrained within a pit shell using the following assumptions: gold price of $2,400/oz; reference mining cost of $2.68/t mined incremented $0.0041/t mined/m with depth from the 220 m elevation (equates to an average mining cost of $3.23/t mined); mining sustaining cost of $0.41/t mined; variable metallurgical recoveries by rock type and geological domain, ranging from 29.4% in oxide to 94.2% in intrusive rocks in the Akivik domain; process operating cost of $20.01/t processed; process sustaining cost of $2.14/t processed; G&A cost of $4.57/t processed; stockpile reclaim cost of $0.30/t processed assuming a reclaim percentage of 45%; refining recovery of 99.9%; selling cost of $1.71/oz gold; royalty considerations of 4.5% NSR and $0.50/t processed; and variable pit slope angles, ranging from 22 to 47°.
8. The NSR value for each block is determined using the gold grade, processing and refining recoveries, gold price, selling costs, and royalties.
9. The timeframe over which the gold price and operating costs is 24 years which is the expected timeframe over which the Mineral Resources will be mined. The long-term forecast gold price for Mineral Resources is based on industry consensus and is 15% higher than the price used for the Mineral Reserves to ensure the Mineral Reserves are a subset of the Mineral Resources.
10. Mineral Resources are reported using a marginal NSR cut-off value of $26.86/t based on a total process cost of $22.15/t processed, G&A operating cost of $4.57/t processed, and a stockpile reclaim cost of $0.30/t processed assuming a reclaim percentage of 45%.
11. The average LOM process recovery for Mineral Resources is 89.8%.
12. Tonnage and grade measurements are in metric units. Contained gold ounces are reported as troy ounces.
13. Rounding may result in summation differences between tonnes, grade, and contained metal content.
Mineral Resources inclusive of Mineral Reserves are summarized in the table below.
| Category | Donlin Gold – 100% Tonnage (kt) | Contained Au (koz) | Au Grade (g/t) | Attributable to NOVAGOLD – 60% Tonnage (kt) | Contained Au (koz) |
|---|---|---|---|---|---|
| Measured | 9,243 | 793 | 2.67 | 5,546 | 476 |
| Indicated | 550,727 | 39,195 | 2.21 | 330,436 | 23,517 |
| Total Measured and Indicated | 559,970 | 39,988 | 2.22 | 335,982 | 23,993 |
| Inferred | 88,886 | 5,812 | 2.03 | 53,332 | 3,487 |
Notes:
1. Mineral Resources are reported inclusive of Mineral Reserves. Mineral Resources are reported on a 100% ownership basis and a 60% ownership basis. The 60% basis is attributable to NOVAGOLD through their 60% ownership interest in the joint venture that owns the mineral rights and manages the Donlin Gold project property.
2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The Wood QP has a reasonable expectation that the majority of Inferred Mineral Resources could be updated to Indicated or Measured Mineral Resources with continued exploration.
3. The Mineral Resource estimate is current as of November 30, 2025. A Wood QP is responsible for the preparation of the Mineral Resource estimate.
4. Mineral Resources are prepared in accordance with the definitions in the S-K 1300.
5. The cut-off date for the sample database used in the Mineral Resource estimate is 31 December 2024. However, more recent drilling data up to 30 November 2025 was used to validate the Mineral Resource model as remaining current.
6. The point of reference for the Mineral Resource estimate is in situ.
7. Mineral Resources are constrained within a pit shell using the following assumptions: gold price of $2,400/oz; reference mining cost of $2.68/t mined incremented $0.0041/t mined/m with depth from the 220 m elevation (equates to an average mining cost of $3.23/t mined); mining sustaining cost of $0.41/t mined; variable metallurgical recoveries by rock type and geological domain, ranging from 29.4% in oxide to 94.2% in intrusive rocks in the Akivik domain; process operating cost of $20.01/t processed; process sustaining cost of $2.14/t processed; G&A cost of $4.57/t processed; stockpile reclaim cost of $0.30/t processed assuming a reclaim percentage of 45%; refining recovery of 99.9%; selling cost of $1.71/oz gold; royalty considerations of 4.5% NSR and $0.50/t processed; and variable pit slope angles, ranging from 22 to 47°.
8. The NSR value for each block is determined using the gold grade, processing and refining recoveries, gold price, selling costs, and royalties.
9. The timeframe over which the gold price and operating costs is 24 years which is the expected timeframe over which the Mineral Resources will be mined. The long-term forecast gold price for Mineral Resources is based on industry consensus and is 15% higher than the price used for the Mineral Reserves to ensure the Mineral Reserves are a subset of the Mineral Resources.
10. Mineral Resources are reported using a marginal NSR cut-off value of $26.86/t based on a total process cost of $22.15/t processed, G&A operating cost of $4.57/t processed, and a stockpile reclaim cost of $0.30/t processed assuming a reclaim percentage of 45%.
11. The average LOM process recovery for Mineral Resources is 89.8%.
12. Tonnage and grade measurements are in metric units. Contained gold ounces are reported as troy ounces.
13. Rounding may result in summation differences between tonnes, grade, and contained metal content.
Mineral Reserve Statement
Mineral Reserves are summarized in the table below. Using the proposed open pit mining method, modifying factors identified have been applied to the Measured and Indicated Mineral Resources to determine Proven and Probable Mineral Reserves, in accordance with the S-K 1300 definitions. Inferred Mineral Resources contained within the pit design are classified as waste with zero grade.
| Category | Donlin Gold – 100% Tonnage (kt) | Contained Au (koz) | Au Grade (g/t) | Attributable to NOVAGOLD – 60% Tonnage (kt) | Contained Au (koz) |
|---|---|---|---|---|---|
| Proven | 9,487 | 698 | 2.29 | 5,692 | 419 |
| Probable | 495,324 | 32,099 | 2.02 | 297,194 | 19,260 |
| Total Proven and Probable | 504,811 | 32,797 | 2.02 | 302,887 | 19,678 |
Notes:
1. Mineral Reserves are reported on a 100% ownership basis and a 60% ownership basis. The 60% basis is attributable to NOVAGOLD through their 60% ownership interest in the joint venture that owns the mineral rights and manages the Donlin Gold project property.
2. The Mineral Reserve estimate is current as of November 30, 2025. A Wood QP is responsible for the preparation of the Mineral Reserve estimate.
3. Mineral Reserves are prepared in accordance with the definitions of S-K 1300.
4. The point of reference for the Mineral Reserve estimate is at the point of delivery to the mill.
5. Mineral Reserves are constrained within an engineered pit design using the following assumptions: gold price of $2,100/oz; reference mining cost of $2.68/t mined incremented $0.0041/t mined/m with depth from the 220 m elevation (equates to an average mining cost of $3.23/t mined); mining sustaining cost of $0.41/t mined; variable metallurgical recoveries by rock type and geological domain, ranging from 29.4% in oxide to 94.2% in intrusive rocks in the Akivik domain; process operating cost of $20.01/t processed; process sustaining cost of $2.14/t processed; G&A cost of $4.57/t processed; stockpile reclaim cost of $0.30/t processed assuming a reclaim percentage of 45%; refining recovery of 99.9%; selling cost of $1.71/oz gold; royalty considerations of 4.5% NSR and $0.50/t processed; and variable pit slope angles, ranging from 22 to 47°.
6. The timeframe over which the gold price and operating costs was 27 years which is the expected timeframe over which the Mineral Reserves will be mined. The long-term forecast gold price for Mineral Reserves is based on industry consensus.
7. The NSR value for each block is determined using the gold grade, processing and refining recoveries, gold price, selling costs, and royalties. Mineral Reserves are reported using an economic NSR cut-off value of $29.95–32.36/t and an elevated gold cut-off grade of 0.75 g/t.
8. The average LOM process recovery for the Mineral Reserves is 90.0%.
9. Tonnage and grade measurements are in metric units. Contained gold ounces are reported as troy ounces.
10. Rounding may result in summation differences between tonnes, grade, and contained metal content.
Financial model parameters
The proposed Project will be a conventional, large-tonnage, open-pit operation designed to provide for a nominal process throughput of 53,500 t/d. The operating mine life is estimated at 24 years with an additional three years of stockpile reclaim based on the planned processing rate.
Base Case Project Sensitivity to Gold Price
| Gold price ($ per ounce) | After-tax cash flow ($ million) | After-tax NPV 5% ($ million) | After-tax IRR (%) | Payback (years) |
|---|---|---|---|---|
| 1,470 | 5,977 | (787) | 4.0 | 13.0 |
| 1,680 | 10,599 | 1,206 | 6.4 | 9.2 |
| 1,890 | 15,096 | 3,128 | 8.5 | 7.5 |
| 2,100 | 19,614 | 5,058 | 10.3 | 6.5 |
| 2,310 | 24,021 | 6,940 | 12.0 | 5.6 |
| 2,520 | 27,856 | 8,681 | 13.5 | 5.1 |
| 2,730 | 31,160 | 10,235 | 14.8 | 4.6 |
Based on the economic evaluation, the Project generates positive before and after-tax economic results. After tax NPV is $5,058 million at a 5% discount rate, an IRR of 10.3% and payback of 6.5 years from the start of production. The following table provides a summary of key evaluation metrics.
Summary of Key Evaluation Metrics
| Item Unit | Value |
|---|---|
| Total Mined Mt | 3,803 |
| Ore Treated Mt | 504.8 |
| Strip Ratio W/O | 6.5 |
| Gold Recovered Moz | 29.5 |
| Gold Recovery% | 90.0 |
| Gold Payable% | 99.9 |
| Gold Price $/oz | 2,100 |
| Total Before Tax Cash Flow $M | 25,415 |
| Total Before Tax NPV5% $M | 7,516 |
| Before Tax IRR% | 12.5 |
| Before Tax Payback Period years | 4.9 |
| Total After Tax Cash Flow $M | 19,614 |
| Total After Tax NPV5% $M | 5,058 |
| After Tax IRR% | 10.3 |
| After Tax Payback Period years | 6.5 |
| Gross Revenue $M | 61,952 |
| Selling Costs $M | 51 |
| Operating Costs (Inc. Royalties) $M | 24,504 |
| Initial Capital $M | 9,233 |
| Sustaining Capital $M | 2,325 |
| Total LOM Capital $M | 11,558 |
| Closure Costs $M | 423 |
| Taxes $M | 5,801 |
44
Operating Cost Estimates 1
The operating cost estimates were updated to fourth quarter 2025 pricing by updating key cost drivers like energy, labor, consumables, and freight. Mining costs have been updated to align with the new design and schedule. The level of accuracy for the estimate is ±25% of estimated final costs. The updated estimated LOM operating costs are $48.54/t processed.
| $ million | $ per tonne processed | |
|---|---|---|
| Mine operations | 11,946.7 | 23.67 |
| Processing operations | 7,718.3 | 15.29 |
| G&A | 2,070.4 | 4.10 |
| Land and Royalty Payments | 2,768.8 | 5.48 |
| 24,504.3 | 48.54 |
Notes:
1. Column totals may not total correctly due to rounding.
Capital Cost Estimates
The capital cost estimate is based on updated, fourth quarter 2025 pricing applied to the engineering designs and material take-offs (“MTOs”) from the 2011 Mining Study. The level of accuracy for the estimate is ±25% of estimated final costs, with a blended 13.8% contingency.
The total initial capital cost estimate is $9,233 million and total sustaining capital is $2,325 million.
Economic Analysis
The overall economic viability of the Project has been assessed using both undiscounted and discounted cash flow techniques. Undiscounted techniques include total net cash flow and payback period (measured from start of production). Discounted cash flow techniques include net present value (“NPV”) and internal rate of return (“IRR”). Discounted values are calculated using a 5% discount rate and a discrete end-of-year convention relative to Year-6, the start of basic and detailed engineering.
Based on the economic evaluation using a forecast long-term gold price of $2,100/oz, the Project generates positive before and after tax economic results. After tax NPV5 is $5,058 million and the after tax IRR is 10.3%. After tax payback is achieved 6.5 years following the start of production.
Sensitivity analyses performed on gold price, gold grade, operating costs, and capital costs showed the Project is most sensitive to changes in the gold price and gold grade.
Planned Mining Operations
The Donlin Gold project will be mined by a conventional truck-and-shovel operation. Initial pioneering and pit development will be undertaken to remove overburden, develop mine access roads suitable for large mining equipment, and “face-up” the initial pit for the large shovel and mining equipment.
Primary loading units for both bulk and selective mining in ore and waste will be large electric-hydraulic shovels, with large front-end loaders as secondary units. Large 363 tonne capacity haul trucks will be used for transporting both ore and waste out of the pit.
Blast hole drilling will be performed by medium-sized rotary and down-the-hole hammer drills with various hole diameters depending on bench height and desired mining selectivity. Reverse circulation (“RC”) drilling is planned for detailed geologic definition and grade control.
Support equipment will be used for road, bench, dump maintenance, and miscellaneous projects.
Planned Processing Operations
The Donlin Gold project ore will be processed by crushing and grinding, sulfide flotation concentration, concentrate treatment by pressure oxidation (“POX”) in an autoclave, CIL cyanide leaching of the oxidized concentrate, electrowinning, and refining to produce doré bars on site.
Due to gold being associated with sulfide mineralization, primarily arsenopyrite and pyrite, the ore is considered refractory and requires POX pre-treatment to liberate the gold prior to CIL leaching. Sulfide flotation concentration is required prior to POX to concentrate the sulfide content to a level sufficient to fuel the POX operation.
Concentrate is recovered from the primary rougher flotation followed by regrinding of the tailings prior to secondary rougher flotation. The secondary rougher concentrate is processed through a cleaner scavenger circuit producing a concentrate which is combined with the primary rougher concentrate for treatment by POX. The final tailings from the secondary rougher flotation tailings is thickened, and due to their neutralizing potential, is then utilized to modify the pH of the excess POX discharge solution prior to being transported to the TSF.
The oxidized concentrate from the POX operation would then be cyanide leached in a conventional CIL circuit to produce a pregnant (gold-bearing) solution. Gold from the solution is absorbed onto activated carbon, which is later stripped (gold desorbed from carbon) in an elution circuit. The pregnant solution after elution is fed through electrowinning (“EW”) cells, where cathodes are plated with gold-bearing materials, which are periodically removed, dried in a retort, and melted in an induction furnace to produce doré bars.
Tailings from the CIL circuit would be treated in a cyanide detoxification process using SO2/air technology prior to being recombined with the flotation tailings and transported to the TSF.
Mercury naturally occurs in the Donlin Gold project ores and mercury abatement controls will be installed in six areas of the process facilities including POX, hot cure, EW, retort, refinery furnace, and carbon regeneration kiln. In these control systems, mercury will be collected for off-site shipment and management. Chemicals will be added to tailings to limit the potential for mercury releases from the TSF. Based on the process design which includes mercury removal and abatement measures, the presence of the deleterious elements will not significantly affect potential economic extraction.
Proposed Waste Rock Facility (WRF)
Waste rock from open pit mining will be placed in an ex-pit WRF in the American Creek Valley, east of the pit area, or in a backfill dump in the ACMA pit. Approximately 2,318 Mt of waste rock (including overburden) will be placed in the WRF. The top lift of the WRF will be at an elevation of approximately 610 m amsl, resulting in a maximum dump height of about 430 m. Most of the WRF will be constructed in 30 m lifts. The toe of each subsequent lift will be set back 47 m from the crest of the previous lift, resulting in an overall dump slope of 3H:1V.
The facility will be constructed in lifts and will be reclaimed as soon as practical after each lift or portion of the facility is complete. After active dumping ceases on each lift, the slopes will be regraded to an overall 3H:1V slope or flatter.
A series of channels is required to collect and convey runoff from the surface of the reclaimed WRF to the pit lake during the closure period. The LCWD and UCWD will be removed, and surface runoff and seepage from the WRF will be directed to the ACMA pit. The seepage flows rom the WRF will be isolated by constructing concrete containment structures at the outlet of the rock drains for American Creek and Rob’s Gulch and piped to the pit bottom to promote stratification.
Concurrent reclamation of the waste rock facility will be undertaken during operations.
Proposed Tailings Storage Facility (TSF)
Before the end of operations, the tailings deposition procedure will be modified so that the operating pond will be directed to the southeast corner of the TSF. The TSF will be reclaimed with a multilayer cover system: 0.35 m of peat/organic growth medium over 0.3 m of colluvium or terrace gravel, and 1.0 m of competent rockfill to provide a capillary break. The TSF surface will be contoured to direct runoff toward the southeast corner, where a lined collection pond will store runoff for testing before discharge. A spillway will be excavated in the ridge between Anaconda Creek and Crevice Creek catchments, with an invert elevation of 254 meters above mean sea level (“amsl”) and designed for a PMF of 380 m³/s. Discharge to Crevice Creek will occur only after water meets applicable standards, which is anticipated to be around 10 years post-closure.
During the first year of closure, TSF pond water will be pumped to the pit via the reclaim pipeline. Over 5 years, the tailings surface will be progressively covered, while pumping continues to prevent pond redevelopment. From years 6 to 52, water from tailings consolidation and infiltration will be collected via drain sumps in manholes and pumped to the pit. Approximately 16.28 mm³ of void water is expected during consolidation. The SRS downstream of the TSF will remain active, pumping seepage (estimated at 102 m³/h) to the pit lake until water quality meets standards.
Water Diversion Dams
Water dams are required during the construction period and initial years of operation to protect the lined upstream face of the tailings-starter dam from a significant flood event, to provide a reliable source of fresh water during operation of the process plant, and to minimize runoff into the TSF.
Current and Planned On-Site Infrastructure
Current site infrastructure comprises an all-season, soft-sided camp with facilities consisting of kitchen, living quarters, equipment shop, drill shack and other buildings required for support of year-round exploration activities.
There is sufficient area within the project area to host an open pit mining operation, including the proposed open pit, waste rock facility, TSF and process facilities (primary and pebble crushers, coarse ore conveyor and coarse ore stockpile, concentrator, flotation, water treatment plants, POX, oxygen plant, boiler house, utility corridors, leach, refinery, cyanide destruct, and access walkways). Other planned site infrastructure is comprised of access roads, airstrip, accommodation camp, fuel tank farm, dual-fueled power plant, truck shop, truck wash, workshops and vehicle repair facilities, assay laboratory, administration facilities and change rooms. Donlin Gold has secured the surface rights for the areas that may host these facilities.
In nearby villages, Crooked Creek has approximately 105 residents and Aniak has a population of approximately 500. The workforce for the project would be sourced from the local area, from Alaskan regional centers and from other sources as required.
The project is a greenfield site. The on-site infrastructure for the project includes three main development sites in remote locations: the mine and plant site area (including the power plant), the permanent camp, and the airstrip. The plant site, power plant and fuel tank farm will be on a ridge above the proposed TSF. The layout of the plant site was designed to take maximum advantage of the natural topography. The layout also provides for efficient movement of equipment and material products around the site.
Planned Off-site Infrastructure
The off-site infrastructure for the project includes three main development sites in remote locations: the Jungjuk port site and mine access road, the natural gas pipeline, and the Bethel port facilities. The Jungjuk port site is situated upriver from Bethel on the Kuskokwim River near the mouth of Jungjuk creek. A port-to-mine access road, approximately 44 kilometers long, will traverse varied terrain from the Jungjuk port site to the mine site. A spur road, approximately 4.8 kilometers long, beginning at route km 8.7, will serve the proposed project airstrip. The mine permanent camp facilities will be located at 3.9 km from the mine site. There are 50 identified stream or drainage crossings along the road route, but only six of them are significant and will require bridging. Bridge lengths vary from 7.5-25 m.
The access road enables the transport of cargo, fuel, equipment, and personnel throughout both construction and operational phases. The road traverses remote upland terrain where no prior road connections or settlements exist. Short spur roads branch off to serve the airstrip, material borrow sites, and the permanent accommodation camp.
The natural gas pipeline is described under the “Power” heading below. The proposed Bethel port will be situated near the town of Bethel, a community of approximately 6,080 residents, that is the main existing port on the Kuskokwim River and is an administrative and transportation hub for the 56 villages in the Y-K region. The existing Bethel port is the northernmost medium-draft port in the United States and is served by ocean-going barges. The proposed port would serve as a trans-shipment point from ocean barges to river barges to supply the project during the summer ice-free period.
Power
Natural gas will be delivered to site by an approximately 507-kilometer, 356-millimeter diameter pipeline to supply an on-site power generation facility. The 2025 Technical Report Summary contemplates that the electric power for the site will be generated from a dual-fueled (natural gas and diesel), reciprocating engine power plant with a steam turbine utilizing waste heat recovery from the engines. The power plant consists of two equal halves, each consisting of six reciprocating engines, and a separate steam turbine. The total generation facility is nominally rated at 182 MW initially and will increase to 215 MW after four years with the addition of two more generators (one in each half) to allow for N+2 redundancy, thus allowing planned maintenance and predicted outages without cutting back production.
Operating costs are based on importing liquefied natural gas (“LNG”) by ship to Anchorage and total delivery cost to site which includes regasification of the LNG and delivery from Anchorage to the Donlin Gold project via the pipeline.
The pipeline would commence at the west end of the Beluga Gas Field, approximately 50 kilometers northwest of Anchorage at a tie-in near Beluga located in the Matanuska-Susitna Borough and would run to the mine site. The pipeline would receive booster compression supplied by one compressor station. No additional compression along the pipeline route would be required. The pipeline would have capacity to transport approximately 2 million cubic meters per day of natural gas.
Fuel sourced at refineries in the Pacific Northwest will be delivered by ocean barge to Dutch Harbor, where it will be stored in 49 ML fuel tanks to await onward transport to Bethel. The first shipments should leave the refineries in early May. Fuel will be shipped from Dutch Harbor to Bethel using an ocean barge with an 11 ML capacity. The barge will be loaded in a way to avoid the need to reduce draft before navigating the shallower sections downstream of Bethel. At Bethel, fuel will either be transferred to 38 ML storage tanks or loaded directly to a river barge for transport to Jungjuk. At Jungjuk, fuel will be offloaded into 9.5 ML storage tanks. From there, a fleet of tanker trucks with total capacity of 0.51 ML will deliver fuel to the mine site where it will be stored in fuel storage tanks with combined capacity of 142 ML. The fuel terminals at Dutch Harbor and Bethel, as well as the ocean and river barge fleets will be operated by third-party contractors.
Water
Water requirements for the proposed project have been summarized in a Water Resources Management Plan, which has been subject to review by state and federal agencies. Water primarily will be sourced from the two drainages (American and Anaconda Creeks) within the mine footprint and pit dewatering. In extremely dry years, the water supply from these sources may not be able to meet the makeup water requirements for the plant. In these circumstances, additional water will be obtained primarily from a proposed reservoir in Snow Gulch.
The source of water supply for the construction camp and, later, the plant site potable water systems is an array of eight deep wells south of Omega Gulch, near Crooked Creek. Water supply will be pumped to freshwater storage tanks and will be treated prior to consumption.
Markets
NOVAGOLD’s portion of gold production is likely to be sold on the spot market, by marketing experts retained by or on behalf of NOVAGOLD. Gold can be readily sold on numerous markets throughout the world and it is not difficult to ascertain its market price at any time, therefore there is no need for a preliminary marketing study to support the assumed gold price or market for the gold production from this Project.
The long-term forecast gold price of $2,100/oz used for mine planning and cash flow analysis was based on a combination of information derived from a number of reputable banks as well as cash flow prices used in technical reports filed in Canada over the previous 12-month period and historical price averaging.
Taxation
The following taxation summary was provided by NOVAGOLD for the Project.
U.S. Federal Corporate Income Tax
In accordance with the TCJA enacted in December 2017 and largely effective January 1, 2018, and the OBBBA enacted in 2025, which extended or made permanent many TCJA provisions:
- Corporate income tax rate is 21%.
- Post-2017 net operating loss (NOL) carryovers are limited to 80% of taxable income, while there is no limitation on pre-2018 NOL carryovers.
- The TCJA changed the NOL rules by limiting NOL deductions to 80% of taxable income, disallowing NOL carrybacks, and lifting the 20-year limit on NOL carryovers for post-2017 NOLs. The pre-TCJA NOL rules (80% limitation, disallowed carrybacks, 20-year carryover period) still apply to pre-2018 NOLs. The NOL rules were not meaningfully modified by the OBBBA.
- The alternative minimum tax (AMT) was eliminated, but the corporate alternative minimum tax (CAMT) replaced it with the enactment of the Inflation Reduction Act (“IRA”) in 2022. The CAMT generally only applies to corporations with average annual adjusted financial statement income in excess of $1 billion over a three-taxable-year period.
- A percentage depletion deduction is applied upon the commencement of production and sale of gold. Cost depreciation is not applicable as there is no Project tax basis for the mineral property.
- Bonus depreciation is not considered in the tax depreciation calculation.
Alaska Corporate Income Tax
- Alaska corporate income tax rate is 9.4%.
- Alaska conforms to U.S. federal tax treatment, and it imposes a state CAMT equal to 18% of the federal CAMT.
Alaska Mining License Tax
- Alaska mining license tax rate is 7%.
- Alaska mining license tax holiday is applied for the first 3 years from the start of production.
Financial results
The total initial capital cost estimate for the Donlin Gold project is approximately $9,233 million. The project’s estimated after-tax NPV at a 5% discount rate is $5,058 million with an IRR after-tax at 10.3% using the base case gold price of $2,100 per ounce. The undiscounted break-even gold price is $1,342 per ounce and at a 5% discount rate is $1,554 per ounce. In the 2025 Technical Report Summary, the overall economic viability of the project was evaluated by both discounted and undiscounted cash flow analyses, based on the engineering studies and cost estimates discussed in the 2025 Technical Report Summary.
Assumptions in the model comprised:
- Costs prior to project Year -6, the start of basic and detailed engineering, are considered sunk. For discounted cash flow (or NPV) purposes, the model commences in Year -6. Estimates were prepared for all the individual elements of cash revenue and cash expenditures for ongoing operations.
- Estimated cash flows from revenue are based on a gold price of $2,100 per ounce. The pit has been optimized at a gold price of $2,100 per ounce.
- Gold recovery is estimated to average 90.0% over the LOM based on work and testing performed for at least pre-feasibility study purposes.
- Doré refining and shipping charges were estimated at $1.56 per ounce based on escalating to 2025 the actual refining charges for large U.S.-based mining operations and a quotation for transportation and insurance costs from the Donlin Gold project site to a U.S.-based refinery utilized in 2011. In addition, 0.1% of gold produced from the mine is deducted as a cost of refining.
- The current hydrometallurgical process selection renders any contained silver into a greater refractory state, which provides less than 10% silver recovery through standard metal leaching. As a consequence, silver is not included in the Mineral Resource and Mineral Reserve estimates, and no silver credit has been applied to the Donlin Gold project.
- To fund the $1,721 million reclamation and closure costs, the Donlin Gold project provides $895 million at closure by contributing to a Trust Fund commencing in Year -5 and continuing through the end of operations with annual contributions of $11.6 million. In addition to the Trust Fund, financial assurance in the form of letters of credit and/or surety bonds is required to construct and operate the mine. Per the Donlin Gold Project Reclamation Plan Approval from ADNR, financial assurance in the amount of approximately $404 million must be submitted in a form and substance approved by ADNR. The cost to maintain this financial assurance is assumed to be 0.4% of the total assured amount, annually. This equates to approximately $1.6 million per year, paid from the start of construction through the end of operations.
- No salvage is assumed at the end of operations.
Current Activities
For information on current activities, see section Item 7, Management’s Discussion and Analysis of Financial Condition and Results of Operations, below.
Change in Mineral Resources and Reserves from 2024 to 2025
The following table is the variance of the Donlin Gold project’s Mineral Resources Exclusive of Reserves from November 30, 2024 to November 30, 2025.
| November 30, 2025 Tonnage (kt) | Cont. Au (koz) | November 30, 2024 Tonnage (kt) | Cont. Au (koz) | Difference Tonnage (kt) | Cont. Au (koz) | |
|---|---|---|---|---|---|---|
| Measured | 1,432 | 54 | 869 | 62 | +64.8% | -12.9% |
| Indicated | 175,224 | 7,439 | 69,402 | 5,435 | +152.5% | +36.9% |
| Total Measured & Indicated | 176,656 | 7,493 | 70,271 | 5,497 | +151.4% | +36.3% |
| Inferred | 74,426 | 4,483 | 92,216 | 5,993 | -19.3% | -25.2% |
There was no material change to the mineral resources as increases in operating costs since the 2021 Technical Report Summary were generally offset by increases in the long-term gold price used in the study. Changes to the inputs and assumptions influencing the Mineral Resource estimate include: updated geologic model and resource model to include exploration drilling through December 31, 2024, gold price used in estimating Mineral Resources increased from $1,500/oz to $2,400/oz, operating costs escalated from 2021 to 2025, revised pit slope parameters.
The following table is the variance of the Donlin Gold project’s Mineral Reserves from November 30, 2024 to November 30, 2025.
| November 30, 2025 Tonnage (kt) | Cont. Au (koz) | November 30, 2024 Tonnage (kt) | Cont. Au (koz) | Difference Tonnage (kt) | Cont. Au (koz) | |
|---|---|---|---|---|---|---|
| Proven | 9,487 | 698 | 7,683 | 573 | +23.5% | +21.8% |
| Probable | 495,324 | 32,099 | 497,128 | 33,276 | -0.4% | -3.5% |
| Total Proven & Probable | 504,811 | 32,797 | 504,811 | 33,849 | 0.0% | -3.1% |
There was no material change to the mineral reserves as increases in operating costs since the 2021 Technical Report Summary were generally offset by increases in the long-term gold price used in the study. Changes to the inputs and assumptions influencing the Mineral Reserve estimate include: updated geologic model and resource model to include exploration drilling through December 31, 2024, gold price used in estimating Mineral Reserves increased from $1,200/oz to $2,100/oz, operating costs escalated from 2021 to 2025, revised pit slope parameters, updated pit design and production schedule.
Mineral Resource and Reserve Internal Controls
The Company has internal controls for reviewing and documenting the information supporting the mineral resource and mineral reserve estimates, describing the methods used, and ensuring the validity of the estimates. These internal control processes were not materially impacted by the adoption of S-K 1300 in 2021. Information that is used in the mineral resource and mineral reserve estimation process was reviewed and approved by appropriate QPs that prepared the content of the NI 43-101 and S-K 1300 reports for the Donlin Gold project. The mineral resources and mineral reserves are subject to our internal review process on an annual basis, which includes review by NOVAGOLD’s QP based in our corporate office in Salt Lake City, Utah, USA.
Sample collection, preparation, analysis and security for all Donlin Gold core drill programs are in line with industry-standard methods for gold deposits.
- Drill programs included insertion of blank, duplicate and SRM samples.
- Quality Assurance/Quality Control program results do not indicate any problems with the analytical programs.
- Data is subject to validation, which includes checks on surveys, collar coordinates, lithology data, and assay data. The checks are appropriate, and consistent with industry standards.
- Independent data audits have been conducted and indicate that the sample collection and database entry procedures are acceptable.
- All core has been catalogued and stored in designated areas.
Modifications made to the 2025 quality control protocol include:
- Preparation of all samples at BV Fairbanks.
- Pulverization in Fairbanks rather than in Vancouver.
- Completion of multi-element analysis in BV Vancouver using their custom MD250 method.
- Re-introduction of a 250 g subsample at the crush stage rather than 1,000 g subsample.
- Pulp splits of an extra 250 g specifically for ALS to perform their work was discontinued; rather, the remaining pulp material following BV analysis was sent to ALS.
- Finally, 250 g archive pulp splits were created in BV during prep which Donlin Gold retain in long-term storage in Chugiak, AK.
Mineral resources and mineral reserves are estimates that are imprecise and depend upon geologic interpretation and statistical inferences drawn from drilling and sampling analysis, which may prove to be unreliable. See Risk Factors – “The quantities for our mineral resources and mineral reserves are estimates based on interpretation and assumptions and may yield less mineral production under actual conditions than is currently estimated.”
Legal proceedings
As filed, 653 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Periodically, we are a party to or otherwise involved in legal proceedings arising in the normal course of business. Management does not believe that there is any pending or threatened proceeding against the Company which, if determined adversely, would have a material adverse effect on our financial position, liquidity or results of operations. There are no material proceedings pursuant to which any of our directors, officers or affiliates or any owner of record or beneficial owner of more than 5% of our securities or any associate of any such director, officer or securityholder is a party adverse to us or has a material interest adverse to us.
Management's discussion and analysis
As filed, 48,897 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
The following Management’s Discussion and Analysis (“MD&A”) provides information that management believes is relevant to an assessment and understanding of the consolidated financial condition and results of operations of NOVAGOLD RESOURCES INC., incorporated in British Columbia, Canada, and its subsidiaries (collectively, “NOVAGOLD,” the “Company,” “our” and “we”). This item should be read in conjunction with our Consolidated Financial Statements and the notes thereto included in this annual report. References herein to $ refer to United States dollars and C$ to Canadian dollars, except as otherwise specified.
The following MD&A generally discusses our consolidated financial condition and results of operations for 2025 and year-over-year comparisons between 2025 and 2024. Discussions of our consolidated financial condition and results of operations for 2024 and year-over-year comparisons between 2024 and 2023 are included in Item 7, Management’s Discussion and Analysis of Financial Condition and Results of Operations, in the Company’s Annual Report on Form 10-K for the fiscal year ended November 30, 2024, filed with the Securities and Exchange Commission on January 23, 2025, are incorporated by reference into this MD&A.
Paulson Advantage Plus Master Ltd. and Paulson Partners LP (together, “Paulson”) are investment funds managed by Paulson Advisers LLC.
Paul Chilson, P.E., who is the Manager, Mine Engineering for NOVAGOLD and a “qualified person” under National Instrument 43-101 – *Standards of Disclosure for Mineral Projects (“*NI 43-101”) and the Securities and Exchange Commission’s (“SEC”) current mining disclosure rules has approved the scientific and technical information contained herein.
Highlights
On June 3, 2025, NOVAGOLD and Paulson, through wholly-owned subsidiaries, completed the $1 billion acquisition of Barrick’s 50% interest in Donlin Gold (the “Donlin Gold Transaction”), increasing NOVAGOLD’s economic stake in Donlin Gold LLC (“Donlin Gold”) to 60%. Paulson’s subsidiary acquired the remaining 40% of Donlin Gold. Both owners have equal governance rights in Donlin Gold. The Donlin Gold Transaction marks a significant milestone in a long-term strategy to advance Donlin Gold. NOVAGOLD’s portion of the acquisition was funded through a combination of a public equity offering and a concurrent private placement.
NOVAGOLD closed a $195.2 million underwritten public offering (issuing approximately 48 million common shares in the second quarter and approximately 7.2 million common shares as part of the exercise of the overallotment option early in the third quarter), and a $64.4 million private placement (issuing approximately 17.2 million common shares in the second quarter), representing a total of $260.4 million (an aggregate of approximately 72.2 million common shares). NOVAGOLD purchased the additional 10% interest in Donlin Gold LLC with proceeds from the offerings and will use the balance of the funds from the offerings for general corporate purposes, including its share of expenses associated with advancing the Donlin Gold Bankable Feasibility Study (the “BFS”).
Company Overview
We operate in the gold mining industry, primarily focused on advancing the Donlin Gold project in Alaska. The Donlin Gold project is held by Donlin Gold, a limited liability company which, following the closing of the Donlin Gold Transaction on June 3, 2025, is owned 60% by a wholly-owned subsidiary of NOVAGOLD and 40% by a wholly-owned subsidiary of Paulson. While NOVAGOLD has a 60% economic interest in Donlin Gold, governance of Donlin Gold is shared equally by NOVAGOLD and Paulson. We record our interest in the Donlin Gold project as an equity investment, which results in our 60% share of Donlin Gold’s expenses being recorded in the income statement as an operating loss.
Our corporate goals include completing the BFS and moving to a subsequent construction decision; maintaining a favorable reputation of NOVAGOLD and the Donlin Gold project among shareholders; promoting strong community outreach and a sustainability culture; maintaining strong safety and environmental performance; and managing the Company’s treasury effectively and efficiently. Our operations primarily relate to the delivery of project milestones, including the achievement of various technical, environmental, sustainable development, economic and legal objectives, obtaining necessary permits and maintaining those received in good standing, advancement to a BFS, preparation of engineering designs and maintaining sufficient capital resources to fund these objectives.
Overview of Donlin Gold Transaction and Financing Activities During 2025
As noted above, on June 3, 2025, the Company and Paulson, through wholly-owned subsidiaries, completed the Donlin Gold Transaction pursuant to the terms of the membership interest purchase agreement dated April 22, 2025 (the “MIPA”) among Barrick Gold U.S. Inc (“Barrick Gold”), Barrick, Paulson, Donlin Gold Holdings LLC, a subsidiary of Paulson (“Donlin Holdings”), and NOVAGOLD Resources Alaska, Inc. (“NGRA”), a subsidiary of the Company. NOVAGOLD, through NGRA, acquired an additional 10% interest in Donlin Gold for $200 million, increasing its stake to 60% of Donlin Gold, while Paulson, through Donlin Holdings, acquired the remaining 40% interest for $800 million.
Amended and Restated Limited Liability Company Agreement for Donlin Gold LLC
In connection with the closing of the Donlin Gold Transaction, NGRA, Donlin Holdings and Donlin Gold entered into an amended and restated limited liability company agreement (the “A&R LLC Agreement”) governing Donlin Gold, pursuant to which the Company and Paulson have equal governance rights. NGRA had previously entered into a limited liability company agreement with Barrick Gold and Donlin Gold (the “Prior LLC Agreement”) dated December 1, 2007, as amended from time to time. Pursuant to the terms of the A&R LLC Agreement, the primary amendments to the Prior LLC Agreement consist of the following:
- The deadlock provision contained in Article XVI of the Prior LLC Agreement has been replaced with a provision for non-binding mediation for dispute resolution.
- Consistent with the Prior LLC Agreement, the funding for Donlin Gold will be shared by both parties based on their percentage ownership. For example, since NGRA now holds 60% of the membership interests of Donlin Gold, it will have the responsibility to fund 60% of the expenses of Donlin Gold. However, regardless of the fact that Donlin Holdings holds 40% of Donlin Gold, Donlin Holdings and NGRA have equal governance rights. This adjustment to the parties’ voting interests, as set forth in the A&R LLC Agreement means that (i) NGRA’s voting percentage interests are defined as its membership interest from time to time less an absolute 10% and (ii) Donlin Holdings’ voting percentage interests are defined as its membership interest from time to time plus an absolute 10%. For this reason, although NGRA holds 60% of the membership interests of Donlin Gold, it only has a 50% voting interest.
- The parties agree to manage the operations of Donlin Gold in a manner to avoid adverse tax consequences to the parties, including pursuant to Section 4943 of the Internal Revenue Code.
- Certain provisions in the Prior LLC Agreement have been deleted or amended as a result of such provisions being outdated or no longer relevant due to the current development and permitting status of Donlin Gold.
Amended and Restated Promissory Note
Pursuant to the Prior LLC Agreement for Donlin Gold, the Company issued a promissory note to Barrick Gold to repay Barrick out of future mine production cash flow for a portion of Barrick’s prior expenditures on the Donlin Gold project. Concurrent with the Donlin Gold Transaction announcement on April 22, 2025, NOVAGOLD entered into a prepayment option agreement with Barrick, which provided the Company with an option to prepay the promissory note in full for $90 million prior to the closing of the Donlin Gold Transaction. The $90 million prepayment option was not exercised prior to closing. In connection with the closing of the Donlin Gold Transaction, on June 3, 2025 NGRA and Barrick Gold amended and restated the promissory note primarily to (i) modify the security package in order to exclude any property held by Donlin Gold or membership interest in Donlin Gold held by NGRA, but ensure it remains secured by NGRA’s right, title and interest to proceeds from Donlin Gold and (ii) provide the ability for NGRA to prepay and retire the promissory note for an aggregate of $100 million until December 3, 2026. In connection with the amended and restated promissory note, NGRA has made an irrevocable direction to Donlin Gold whereby Donlin Gold shall distribute to Barrick Gold, until the promissory note is fully repaid, 85% of distributed processed products, cash and other assets, and payments of 5% of certain net proceeds specified in the promissory note. As per the amended and restated promissory note, the principal amount owed is $158.9 million.
Backstop Agreement
In order to ensure available financing for the Company’s $200 million obligation under the MIPA, funding commitments of up to $170 million were obtained from Electrum Strategic Resources L.P. (“Electrum”), Paulson, and Kopernik Global Investors, LLC, on behalf of investment funds and accounts managed by them (“Kopernik”, together with Electrum and Paulson, the “Investors”) pursuant to a backstop agreement dated April 22, 2025 (“Backstop Agreement”). Pursuant to the Backstop Agreement, the Investors agreed to purchase, on a non-brokered, private placement basis, up to $170 million in the Company’s common shares at $3.00 per share, representing up to 56,666,667 common shares in the aggregate.
While the Company did not exercise its rights provided by the Backstop Agreement, in consideration for entering into the Backstop Agreement, the Company issued an aggregate of 25,500,000 warrants to purchase the Company’s common shares (the “Warrants”), with each Warrant entitling the holder thereof to purchase one common share (a “Warrant Share”) at an exercise price of $3.00 per Warrant Share for a period of five years from the date of issuance. The Warrants contain a “cashless exercise” feature, such that, in lieu of making the cash payment otherwise contemplated to be made to us upon such exercise of the Warrant, the holder may elect instead to receive upon such exercise (either in whole or in part) the net number of common shares determined according to a formula set forth in the Warrants. The Warrants were issued in the following amounts: (i) 12,750,000 Warrants to Paulson; (ii) 6,375,000 Warrants to Electrum; and (iii) 6,375,000 Warrants to Kopernik.
The Backstop Agreement further provided the Investors with registration rights, pursuant to which the Company had agreed to, among other things, file a registration statement with the SEC registering the resale of the Warrant Shares and to cause such registration statement to remain effective until the earlier of (a) three years from the issuance of the Subscribed Shares (which were not issued), (b) the date on which all of the Subscribed Shares and Warrant Shares shall have been sold, or (c) on the first date on which each Investor can sell all of its Subscribed Shares and/or Warrant Shares (or shares received in exchange therefor) under Rule 144 of the Securities Act without limitation as to the manner of sale or the amount of such securities that may be sold. The Backstop Agreement also contained customary indemnification and other provisions customary for registration rights of this type. Pursuant to discussions with the Investors and the Placement Investors (as defined below), the Company may file a resale registration statement in the future upon request of such investors with respect to the Warrant Shares or common shares issued pursuant to the Subscription Agreement (as defined below).
Public Offering and Concurrent Private Placement
On May 7, 2025, the Company entered into an underwriting agreement related to a public offering of 47,850,000 of the Company’s common shares at a public offering price of $3.75 per share (the “Underwriting Agreement”). In addition, the Company granted the underwriters an option exercisable for 30 days from the date of the Underwriting Agreement to purchase up to 7,177,500 of additional common shares of the Company (the “Overallotment Option”). The net proceeds from the public offering were approximately $169.7 million. The Overallotment Option was exercised in full on June 5, 2025, bringing the total net proceeds to the Company for the public offering and the Overallotment Option to approximately $195.2 million after deducting the underwriting discount and offering expenses. The Company made certain customary representations, warranties and covenants concerning the Company and the registration statement in the Underwriting Agreement and also agreed to indemnify the underwriters against certain liabilities, including liabilities under the Securities Act of 1933, as amended (the “Securities Act”).
Concurrently with the public offering announced in May 2025, the Company completed a private placement offering on May 9, 2025 of 17,173,853 common shares at a price equal to the public offering price for aggregate gross proceeds of approximately $64.4 million with Electrum and investments funds and accounts managed by Kopernik Global Investors, LLC (each a “Placement Investor”). The Company entered into a Subscription Agreement dated May 7, 2025 (the “Subscription Agreement”) with each of the Placement Investors setting out the terms of the concurrent private placement, which included similar resale registration rights as contained in the Backstop Agreement. The concurrent private placement closed on May 9, 2025.
Donlin Gold project
NOVAGOLD and Donlin Gold advanced key activities in 2025 to position the project to update technical work and cost estimates. Primary activities included 1) issuing a Request for Proposals (RFP) for its Bankable Feasibility Study (BFS) to top-tier engineering firms with the expertise to design what is expected to be the largest single gold mine in the United States. Proposals were received in October, and the Prime Contractor is expected to be selected in the first quarter of 2026. RFPs were also issued in the fourth quarter of 2025 for specialist contractors for the power plant, pipeline, and pressure oxidation and oxygen plant scopes of work; and 2) mine planning and resource conversion advanced through the completion of an 18,454-meter 2025 drill program. The work targeted three core objectives: grid drilling to refine mine planning parameters, in-pit exploration to strengthen geological modelling and resource conversion, and geotechnical drilling to inform the updated resource model, mine planning and assess sites for the planned port access road. The program was successfully executed by a site team of approximately 80 locally hired staff and external contractors, with results providing critical inputs for engineering, mine planning, and resource modelling.
To support the advancement of the BFS and move the project toward development, management has identified key project requirements and commenced recruiting for critical positions. Donlin Gold hired Frank Arcese as Project Director. Frank brings more than four decades of global project leadership to Donlin Gold and has deep experience in the execution of large-scale mining capital projects in both the U.S. and international jurisdictions. Most recently, he served as Capital Projects Business Leader for North and South American mining operations at WSP Global Inc., and Engineering, Procurement and Construction Management (EPCM) firm. Prior to that, he acted as Project Director on multiple large mining and power plant project for Rio Tinto across the U.S., Mongolia, China, Australia, and Argentina, and brings extensive expertise in managing projects in remote environments, such as Teck Resource’s original Quebrada Blanca in Chile, BHP’s Escondida Phase 3 and SX-EW Plant in Chile, and recently Rio Tinto’s Rincon 3000 Lithium Project in Argentina.
The Donlin Gold board must approve the BFS, construction program and budget before the Donlin Gold project can be developed. The timing of the required engineering work and the Donlin Gold board’s approval of an updated feasibility study, construction program and budget, the receipt of all required governmental permits and approvals, and the availability of financing, commodity price fluctuations, risks related to market events and general economic conditions among other factors, will affect the timing of and whether to develop the Donlin Gold project. Among other reasons, project delays could occur due to public opposition, litigation challenging permit decisions, requests for additional information or analysis, limitations in agency staff resources during regulatory review and permitting, or project changes made by Donlin Gold.
Stakeholder and government engagement
In collaboration with Calista Corporation (“Calista”) and The Kuskokwim Corporation (TKC), Donlin Gold LLC had engagement with local communities, stakeholders, and government representatives across the Y-K region, Alaska, and Washington, D.C., advancing project development and permitting. Our longstanding outreach efforts — includes decades of work with 62 Y-K region communities and has strengthened relationships, created knowledge-sharing opportunities, reinforced the project’s social license, and built considerable trust. The company and the Donlin Gold team remain committed to advancing the project responsibly through transparent, respectful, and lasting partnerships and engagement with both community and government entities.
To support these efforts, Donlin Gold maintained frequent engagement with numerous stakeholders throughout the Y-K region, Alaska, and Washington D.C. In 2025, NOVAGOLD and Donlin Gold staff traveled to Juneau and Washington, D.C., to meet with Alaska’s state legislators, the U.S. congressional delegations and staff, Federal officials, the Federal Permitting Council, and the National Security Council to provide project updates and its importance to Alaska and the Y-K region, discuss energy needs, and highlight the State’s environmental standards. Donlin Gold’s new General Manager and other team members also met with Governor Mike Dunleavy, Department of Interior representatives, Karen Kelleher, Alaska’s Bureau of Land Management acting Director, and other industry officials for an introduction and project update. Meetings also took place with former Alaska state legislators Senator Hughes, Representative Kopp, Representative Coulombe, and Representative Jimmie during the Donlin Gold’s Alaska Federation of Natives reception.
Donlin Gold hosted the fourth and fifth Subsistence Community Advisory Committee meetings in Anchorage and at the project site, offering a deep dive in different areas of the project’s development and operations, including camp and facility tours, as well as aquatic resources monitoring, and Snow Gulch restoration work.
Additionally, site tours were held with stakeholders, investors, and analysts, followed by the owners’ tour which included meetings with principal stakeholders, including Alaska Native landowners, government agencies, engineering firms, and logistics providers and other pivotal parties with the capacity and experience to support critical project infrastructure as Donlin Gold advances the BFS and development activities that follow its construction decision.
Donlin Gold and NOVAGOLD staff traveled to Crooked Creek on several occasions to meet with community members to share information and answer questions from attendees about the Donlin Gold project. Additionally, Donlin Gold and Calista traveled to Crooked Creek and Aniak to provide project updates.
As part of the owners’ site tour last summer, meetings were held with key Alaska government officials – including Governor Mike Dunleavy, former Department of Natural Resources Commissioner John Boyle, and former Revenue Commissioner Adam Crum among others – to introduce the new Donlin Gold ownership and to discuss shared priorities between the State of Alaska and the project. In addition, a series of discussions were held with natural gas pipeline developers to explore opportunities benefiting the project and its stakeholders.
Additionally, Donlin Gold hosted a site tour for State of Alaska representatives, state directors for all three U.S. delegation offices, and RDC staff. Donlin Gold also hosted an additional tour including staff from the offices of Senator Lisa Murkowski, Senator Dan Sullivan, and Representative Senator Nick Begich, as well as a Calista intern. The Donlin Gold team met with Representative Begich in Aniak, followed by the Director of the Bureau of Land Management and his staff in Alaska.
Representatives from Donlin Gold, Paulson and NOVAGOLD, as well as Alaska Gov. Mike Dunleavy participated in a keynote luncheon panel on the Donlin Gold project during the Alaska Miners Association Convention. Panelists discussed the project’s ongoing development, its importance to Alaska and the Y-K region, and how close collaboration among partners and stakeholders is advancing the project responsibly. During the Alaska Miners Association Convention, Donlin Gold’s Permitting and Environmental Manager Enric Fernandez was awarded the Alaska Miners Association Environmental Stewardship Award while the Donlin Gold team received the Alaska Miners Association Hard Hat Safety award – recognizing the team’s outstanding dedication to safety, teamwork and care for one another.
Environment and social investments
NOVAGOLD is committed to education, community wellness, cultural preservation, ecological stewardship, and best practices that enhance the economic, health, and social well-being of our employees, the people of the Y-K region, and surrounding communities. Donlin Gold supports these efforts through fisheries studies, environmental activities, subsistence initiatives, and grants, while recognizing the importance of the region’s traditions and subsistence way of life, where environmental health is paramount.
Meaningful collaboration was deepened with the Native Village of Napaimute, with Donlin Gold extending financial assistance to maintain the Kuskokwim River Ice Road — a pivotal winter infrastructure that ensures the safe transport of residents to community events and serves as a conduit of economic activity for the Kuskokwim River communities. Additionally, Donlin Gold pursued its support of and participation in the Alaska Safe Riders initiative, which promotes the secure use of snowmachines, all-terrain vehicles, and recreational off-road vehicles. Financial assistance was also provided to Camp Fire Alaska, an organization dedicated to offering summer camps and programs to youth in rural communities across Alaska. Activities included music, sports, science, field trips, and numerous outdoor recreation opportunities.
Donlin Gold continued its participation and support of the Kuskokwim River summer safety Program with NOVAGOLD team members, traveling with 2019 Iditarod champion and Donlin Gold employee, Pete Kaiser. Together, they visited seven villages in the Y-K region to distribute life jackets and promote water safety among local residents. That same month, Donlin Gold extended its support to 47 communities for the annual “Clean-up Greenup” program.
NOVAGOLD and Donlin Gold also provided financial support to the Alaska Community Foundation to aid community recovery efforts in the region following Typhoon Halong. They also partnered with the AVCP Regional Housing Authority to provide generators and insulation.
Over the year, Donlin Gold further engaged in a variety of community events and initiatives that celebrate cultural preservation, strengthen stakeholder relationships, and promote the economic and social well-being of the Y-K region. These included Calista’s Shareholder Relations Committee meetings, the Alaska Federation of Natives convention, village gatherings such as Napaimute’s annual event, Nikolai Elder Food Program and School Carnival, RuralCap McGrath’s Bluegrass Festival, the Alaska Native Heritage Center’s 2025 Garden Party, the Aniak Traditional Council Annual Fair, Kalskag’s Culture Camp, Calista’s Golf Tournament, the Kwethluk Church Event, and the Napaskiak Summer Festival.
Donlin Gold continues to support a range of educational programs, including Crooked Creek’s Traditional Council Summer Youth Employment Program, Alaska Resource Education, collaborating with the Lower Kuskokwim School District to host an annual College & Career Fair, EXCEL Alaska, and Covenant House Alaska’s Bethel Jobs for American Graduates program, which helps high school graduates transition to postsecondary education and employment.
Throughout the year, Donlin Gold supported local sports initiatives, including the Alaska School Activities Association, Special Olympics Alaska, the Donlin Gold Invitational Basketball Tournament at Bethel Regional High School, The Iditarod Sled Dog Trail Race, Iron Dog Race and Y-K mushers Isaac Underwood, Mike Williams Jr., and Pete Kaiser.
Donlin Gold also continued to build on the progress of its aquatic habitat restoration project at Snow Gulch, which began in 2021 and is improving access and habitat for resident fish in areas affected by historic placer mining. Further development and restoration of the inlet channel were carried out in 2025 to help restore natural habitat conditions in support of aquatic life.
Permitting
Donlin Gold is a federally permitted project on private land designated for mining activities by Calista Corporation, owner of the mineral rights, and The Kuskokwim Corporation (TKC) owner of the surface estate. Permitting in Alaska is a substantial undertaking supported by a diligent, thorough, transparent, and inclusive process for all involved, including stakeholders from the Y-K region.
Comments from ADNR on the preliminary design packages are anticipated in 2026. BGC Engineering has been appointed as the contractor for the Detailed Design Packages. The Detailed Design Packages are anticipated to be completed by the end of 2026/early 2027 with potential issuance of the Dam Safety Certificates in 2028.
Litigation
On September 20, 2021, Earthjustice, representing ONC, Cook Inletkeeper, and three Y-K villages, filed an appeal of the State pipeline ROW authorization in Alaska Superior Court. On April 12, 2023, the Alaska Superior Court affirmed the Alaska Department of Natural Resources’ (“ADNR”) issuance of the ROW lease in the Earthjustice case. Earthjustice appealed the Superior Court’s decision to the Alaska Supreme Court. On May 25, 2022, Earthjustice, representing ONC and five Y-K villages, filed an appeal of ADNR’s issuance of certain water rights permits to Donlin Gold in Alaska Superior Court. After briefing and oral argument, on September 1, 2023, the Alaska Superior Court affirmed ADNR’s decision on Donlin Gold’s water rights permits. On October 2, 2023, Earthjustice appealed the Superior Court’s decision to the Alaska Supreme Court. Earthjustice’s opening brief was submitted to the Alaska Supreme Court on January 4, 2024. Response briefs from the State of Alaska and Donlin Gold were completed in April 2024, and Earthjustice subsequently filed their reply brief in May 2024. Briefing on Earthjustice’s appeal of the Alaska Superior Court affirmation of ADNR’s issuance of the State pipeline ROW lease to the Alaska Supreme Court was completed in February 2024. On November 14, 2025, Donlin Gold welcomed the Alaska Supreme Court’s decision affirming both the project’s water rights permits for the mine and the Department of Natural Resources’ approval of the State’s ROW for the state-owned lands portion of the proposed 316-mile natural gas pipeline. The ruling validates the State of Alaska’s thorough review process and reinforces that the project can move forward in a manner that safeguards the lands, waters, and communities of the Yukon-Kuskokwim and southcentral regions.
NOVAGOLD continues to support the State of Alaska in defending the Department of Environmental Conservation’s (“ADEC”) Clean Water Act Section 401 Water Quality Certification (“401 Certification”), which is the only remaining challenge to Donlin Gold’s permits in state court. On May 6, 2025, the Alaska Superior Court upheld ADEC’s issuance of the 401 Certification. Earthjustice filed an appeal in the Alaska Supreme Court and filed their opening brief on September 16, 2025. Donlin Gold’s and the State of Alaska’s briefs were filed on November 25, 2025, and Earthjustice’s reply brief was filed on January 9, 2026.
On April 5, 2023, Earthjustice representing ONC and six Y-K villages filed suit against the U.S. government in the U.S. District Court for Alaska (the “Federal District Court”) asking the Federal District Court to invalidate the Donlin Gold JROD, which included the Corps’ issuance of the 404 permit and the Department of Interior, Bureau of Land Management’s issuance of the ROW lease for the portions of the pipeline on Federal lands. The U.S. Department of Justice (“DOJ”) is defending the issuance of the permits by those Federal agencies. The State of Alaska, Donlin Gold, and Calista were granted intervenor status in this case. The DOJ filed their brief supporting the issuance of the JROD and the sufficiency of the environmental analysis in the Final Environmental Impact Statement on April 2, 2024. Amicus briefs supporting the project were filed by the village of Crooked Creek and the Alaska federal Congressional delegation. Oral arguments were held on June 24, 2024, and the Federal District Court issued a decision on September 30, 2024. The decision rejected the plaintiffs’ arguments on two of the three issues raised in the litigation but agreed with plaintiffs that the federal agencies took too narrow of a view in analyzing the impact of a theoretical release from the tailings’ storage facility. The Federal District Court requested supplemental briefing on the appropriate remedy for addressing this issue. On October 7, 2024, the plaintiffs filed a request for reconsideration on one of the issues on which the Federal District Court had ruled against the plaintiffs and, at DOJ’s request, the Federal District Court suspended the schedule for briefing on the appropriate remedy until after the Federal District Court ruled on plaintiffs’ motion for reconsideration. On December 23, 2024, the Federal District Court denied plaintiffs’ request for reconsideration. Remedy briefing was completed in March 2025 and oral argument on remedy was held May 9, 2025. On June 10, 2025, the Federal District Court issued an order denying Earthjustice’s request to vacate the permits and remanding the case to the agencies to supplement the NEPA analysis on the narrow issue regarding the analysis of a potential larger release from the tailings storage facility. The Court retained jurisdiction over the case during the remand and ordered the agencies to file periodic status updates with the court. USACE, in consultation with BLM and other federal agencies, will be the lead agency for this Supplemental Environmental Impact Statement (“SEIS”) process to ensure a transparent, science-based review that provides the public and decision-makers with complete and accurate information. On October 27, 2025, Donlin Gold was also formally accepted into the FAST-41 program, a federal initiative that increases transparency, accountability, and predictability in permitting, and the project is now listed on the Federal Permitting Dashboard in connection with the SEIS. The USACE has submitted a schedule to the Permitting Council for completion of the supplemental analysis in mid-2027.
To date, all permits and approvals granted to Donlin Gold by federal and state agencies remain in place while the legal challenges described above proceed. We recognize the importance of preparedness and organization on these matters. Donlin Gold and its owners continue their unwavering support of the state and federal agencies in defending their thorough and diligent permitting processes, including working with the federal agencies and all stakeholders on an appropriate remedy to address the Federal District Court’s remand decision.
Other remediation
During 2025, $219,524 in remediation expenditures were incurred for fieldwork at the historic former New Gold House property in Nome, Alaska, including re-seeding, sampling and monitoring. Monitoring, sampling and maintenance work (as needed, based on monitoring results) is planned for the 2026 field season.
Functional Currency Change
The functional currency of the Company is the U.S. dollar. Prior to April 22, 2025, the functional currency of NOVAGOLD RESOURCES INC., the parent company, was the Canadian dollar. Management reassessed the functional currency of the parent company, NOVAGOLD RESOURCES INC., and determined that as of April 22, 2025, given the increasing prevalence of U.S. dollar denominated activities and financing transactions, its functional currency changed from the Canadian dollar to the U.S. dollar. Prior to April 22, 2025, the effects of translating the Company’s Canadian operations from the Canadian dollar to the U.S. dollar were recorded in Other comprehensive income (loss) and Accumulated other comprehensive loss. The change in functional currency was accounted for prospectively from April 22, 2025, and prior period consolidated financial statements were not restated. Previously recorded cumulative translation adjustments were not reversed.
Consolidated Financial Results for Fiscal 2025
The details of our Net loss are set forth below:
| Years ended November 30, 2025 | 2024 | Change | |
|---|---|---|---|
| Net loss | $(94,659) | $(45,621) | $(49,038) |
| Net loss per common share, basic and diluted | $(0.25) | $(0.14) | $(0.11) |
Net loss in fiscal 2025 increased by $49.0 million from the comparable prior year period primarily due to a $39.6 million non-cash, non-recurring charge related to warrants issued under a backstop commitment agreement signed on April 22, 2025 concurrent with the announcement of the Donlin Gold Transaction as well as $9.0 million of higher Donlin Gold field expenses. Other items leading to an increase in net loss in fiscal 2025 include higher general and administrative expenses and lower interest income on cash and term deposits.
Donlin Gold expenses recognized during fiscal 2025 were higher with increased site activity at Donlin Gold in 2025 compared to 2024 when field work activities were minimal and due to the Company’s share of Donlin Gold expenditures increasing by 10% to 60% starting in the third quarter. General and administrative expenses increased by $0.4 million in fiscal 2025 from the comparable prior year period primarily due to higher professional fees partially offset by lower share-based compensation. Professional fees increased by $0.9 million in fiscal 2025 as a result of the closing of the Donlin Gold Transaction as well as costs incurred to prepare updated NI 43-101 and S-K 1300 technical reports for the Donlin Gold project.
Costs of $9.1 million incurred during the second and third quarter mainly for investment banking and legal fees related to the Donlin Gold Transaction have been capitalized to the Company’s Investment in Donlin Gold along with $201.0 million of consideration paid to Barrick for the acquisition of an additional 10% interest in Donlin Gold.
2025 Fourth Quarter Results
Net loss during the fourth quarter of fiscal 2025 was $15.6 million which was $4.1 million higher than the comparative prior year period. The increase in net loss primarily resulted from higher Donlin Gold expenses recognized during fiscal 2025 and higher professional fees, both due to the same factors noted in the fiscal 2025 results above.
Liquidity and Capital Resources
Liquidity overview
The Company monitors its liquidity and capital resources on a regular basis to ensure it has sufficient liquidity and capital resources to meet its current operating and capital requirements.
As of November 30, 2025, the Company had cash resources comprising cash and cash equivalents, term deposits, and marketable securities totaling approximately $120 million, which are sufficient to cover the anticipated funding costs in respect of the Donlin Gold project and corporate general and administrative costs for at least the next twelve months.
In 2026, NOVAGOLD’s pro-rata share of Donlin Gold expenditures is expected to increase from fiscal 2025 levels over the coming two years with the commencement of work associated with its BFS. Depending on the timing of these costs and the Company’s decisions regarding when to commence detailed engineering and its option to prepay the Barrick promissory note, the Company expects to raise additional capital at some point to support these activities. As a result of a delinquent filing of a Form 8-K in June 2025, NOVAGOLD will not be eligible to use a Form S-3 registration statement to register its securities with the SEC until July 2026. This may adversely impact the Company’s ability to raise capital prior to that time.
Future funding to support fully developing the Donlin Gold project is anticipated to include, among of things, a combination of corporate debt and equity, project specific debt, and potentially a royalty, stream and government support. NOVAGOLD’s continued operations, in the longer term, are dependent on its ability to generate future cash flows and maintain sufficient capital resources. There is no assurance that the Company will be successful in its efforts to raise additional capital on favorable terms, or at all. For further information, see section Item 1A. Risk Factors – Our ability to continue the exploration, permitting, and development of the Donlin Gold project, to complete the Bankable Feasibility Study for the Donlin Gold project, to fund construction of the Donlin Gold project, and to continue as a going concern, will depend in part on our ability to obtain suitable financing.
NOVAGOLD’s anticipated expenditures in fiscal year 2026 are approximately $98.5 million, including $78.8 million to fund the Donlin Gold project, and $19.7 million for corporate general and administrative costs.
The Company’s financial position includes the following as of November 30, 2025:
- Cash and cash equivalents of $110,143, primarily held at three large Canadian chartered banks with investment grade credit ratings.
- Term deposits of $5,000 held at a large U.S. bank with investment grade credit ratings and maturities of less than one year.
- Marketable securities of $4,406 traded on active markets.
- Promissory note payable to Barrick of $166.3 million, including accrued interest at U.S. prime plus 2%, compounded semi-annually. The promissory note and accrued interest are payable from 85% of distributed processed products, cash and other assets, and payments of 5% of certain net proceeds specified in the promissory note. On June 3, 2025 the Company entered into an amended and restated secured promissory note with Barrick that provides the Company with an option to prepay the promissory note in full for $100 million on or before December 3, 2026. Absent a prepayment of the promissory note in 2026, at the current interest rate of 8.75%, interest on the note in fiscal year 2026 will total approximately $14.9 million.
Cash flows
During fiscal 2025, cash equivalents increased by $67.9 million primarily due to $270.8 million in proceeds from a public equity offering and concurrent private placement, net of $11.2 million of issuance costs and $54.0 million in net redemptions of term deposits partially offset by $210.1 million paid to complete the Donlin Gold Transaction, $22.5 million in Donlin Gold funding and corporate general and administrative costs.
Cash used in operating activities during fiscal 2025 was $1.4 million higher than the comparative prior year period. Cash used in investing activities during fiscal 2025 increased by $186.9 million from the comparative prior year period primarily due to $210.1 million paid to complete the Donlin Gold Transaction and $10.0 million in incremental Donlin Gold funding partially offset by $33.0 million in net redemptions of term deposits. Funding of Donlin Gold was higher in fiscal 2025 due to increased site activity than the comparative prior year period when field work activities were minimal and due to the Company’s 10% increased Donlin Gold funding obligation starting in the third quarter.
Cash generated from financing activities increased by $259.7 million primarily due to $243.8 million in proceeds from a May 2025 public equity offering and concurrent private placement, net of $9.7 million of issuance costs and $26.9 million in proceeds from the exercise of an underwriter’s overallotment option on the May 2025 equity offering, net of $1.4 million of issuance costs. The PSU awards that matured and vested in December 2024 at 25% of the grant amount were settled with the issuance of net common shares. The issuance of common shares in lieu of a cash payout represents a non-cash financing activity.
Outstanding share data
As of January 16, 2026, the Company had 406,994,531 common shares issued and outstanding. Also, as of January 16, 2026, the Company had: i) a total of 25,500,000 warrants outstanding with an exercise price of $3.00 per share; ii) a total of 9,504,633 stock options outstanding; 8,237,633 with a weighted-average exercise price of $5.36 per share and the remaining 1,267,000 of those stock options with a weighted-average exercise price of C$6.97 per share; and iii) 1,578,800 PSUs; and iv) 315,953 deferred share units outstanding. Upon exercise or pay out, as applicable, of the foregoing convertible securities, the Company would be required to issue a maximum of 37,688,786 common shares.
Related party transactions
The Company provided management and administrative services to Donlin Gold for $1.2 million in 2025 ($0.7 million in 2024). As of November 30, 2025, the Company had accounts receivable from Donlin Gold of $1.0 million (November 30, 2024: $0.2 million) included in Other current assets. Subsequent to November 30, 2025, the accounts receivable balance has been fully settled.
As consideration for providing a backstop commitment to the Company on April 22, 2025, NOVAGOLD issued Backstop Warrants (Note 11) to three institutional investors, one of which was Electrum. The Backstop Warrants have an estimated aggregate fair value of $39.6 million. Electrum received 6,375,000 Backstop Warrants having a fair value of approximately $9.9 million. Dr. Thomas Kaplan, NOVAGOLD’s Chairman of the Board, is the Chairman and Chief Executive Officer of The Electrum Group LLC, an affiliate of Electrum. Electrum is the largest shareholder of NOVAGOLD.
Additionally, Electrum was one of two institutional investors who participated in a private placement that closed concurrent with the May 2025 public equity offering at the same price as the public equity offering. Electrum purchased 13,333,334 shares of NOVAGOLD in the private placement.
Critical Accounting Policies
We believe the following accounting policies are critical to our financial statements due to the degree of uncertainty regarding the judgements or assumptions involved and/or the magnitude of the asset, liability, or expense being reported.
Contingent note receivable
A portion of the consideration from the Company’s 2018 sale of Galore Creek to a subsidiary of Newmont Corporation (“Newmont”) included a $75,000 note receivable, contingent upon the approval of a Galore Creek project construction plan by the owner(s) (see Note 4 to the financial statements). The Company has not assigned a value to the contingent note receivable as management determined that the approval of the Galore Creek project construction was not probable as of the closing of the Galore Creek sale or in subsequent periods. The contingent note will be recognized when, in management’s judgement, it is probable that the payment will occur, and that the amount recorded will not reverse in subsequent periods.
Investment in affiliates
Investments in unconsolidated ventures over which the Company has the ability to exercise significant influence, but does not control, are accounted for under the equity method and include the Company’s investment in the Donlin Gold project. The Company identified Donlin Gold as a Variable Interest Entity (“VIE”) as it is dependent on funding from its owners. Historically, all funding, ownership, voting rights, and power was shared equally on a 50/50 basis between the owners of the VIE. On June 3, 2025, the Company increased its ownership interest in Donlin Gold to 60% (see Note 5 to the financial statements) resulting in the funding and ownership being shared on a 60/40 basis between the Company and its new Donlin Gold partner. However, the power to exercise control and direct the activities of Donlin Gold continues to be shared equally on a 50/50 basis between the Company and its new Donlin Gold partner. As such, the Company has determined it continues to not be the primary beneficiary of the VIE.
The Company’s maximum exposure to loss is its investment in Donlin Gold of $213.2 million as of November 30, 2025. The Company reviews and evaluates its investment in the Donlin Gold project for other than temporary impairment when events or changes in circumstances indicate that the related carrying amounts may not be recoverable. Events that could indicate impairment of an investment in an affiliate include a significant decrease in long-term expected gold price, a significant increase in expected operating or capital costs, unfavorable exploration results or technical studies, a significant decrease in reserves, a loss of significant mineral claims, or a change in the development plan or strategy for the project. Management reviewed potential impairment indicators and determined that there were none as of November 30, 2025.
Share-based compensation
We grant share-based compensation awards in exchange for employee services, including a stock option plan and a performance share unit (“PSU”) plan. The fair value of awards granted under the plans are recognized in the Consolidated Statements of Loss over the related service period. The fair values of stock options are estimated at the time of each grant using a Black‐Scholes option pricing model, and the fair values of PSUs are measured at each grant date using a Monte Carlo valuation model. The fair value estimates may be impacted by certain variables including, but not limited to, stock price volatility, employee stock option exercise behaviors, additional stock option and PSU grants, estimates of forfeitures, the Company’s performance, and the Company’s performance in relation to its peers.
We grant members of the Board deferred share units (“DSUs”) whereby each DSU entitles the directors to receive one common share of the Company or the market value thereof in cash, at the Company’s option, when they retire from service with the Company. The fair value of the DSUs is measured at the date of the grant in amounts ranging from 50% to 100% of directors’ annual retainers at the election of the directors. The fair value is recognized in the Consolidated Statements of Loss at the time of grant over the related service period.
In 2025, we incurred $6.7 million in share-based compensation costs, a decrease of $0.5 million from the prior year primarily due to the timing of share-based compensation issuance and the forfeiture of options and performance share units following the departure of certain employees during the prior year.
During 2025, we had 408,400 PSU awards that vested at 25% of the grant amount and 79,065 DSU awards that vested and were settled with the issuance of common shares. As of November 30, 2025, we had $4.4 million of unrecognized compensation cost related to 5,308,654 non-vested stock options expected to be expensed and vest over a period of approximately 2.7 years. Also, as of November 30, 2025, we had 2,074,300 non-vested PSU awards outstanding of which 495,500 were fully expensed and vested in December 2025 without meeting the performance payout criteria. The remaining 1,578,800 non-vested PSU awards with $4.0 million of unrecognized compensation cost will be expensed over a period of approximately 2.4 years.
Market risk
As filed, 798 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Our financial instruments are exposed to certain financial risks, including credit and interest rate risks.
Credit risk
Concentration of credit risk exists with respect to our cash and cash equivalents, and term deposit investments. All term deposits are held at two Canadian chartered banks and one large U.S. bank with investment grade credit ratings and maturities of less than one year.
Interest rate risk
The interest rate on the promissory note owed to Barrick is variable with the U.S. prime rate. Based on the amount owing on the promissory note as of November 30, 2025, and assuming all other variables remain constant, a 1% change in the U.S. prime rate would result in an increase/decrease of approximately $1.7 million in the interest accrued on the promissory note per annum.
Controls and procedures
As filed, 3,117 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
An evaluation was performed under the supervision and with the participation of our management, including our principal executive officer and principal financial officer, of the effectiveness of our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e)) under the Exchange Act, as of the end of the period covered by this Annual Report on Form 10-K. Based on the foregoing, our management concluded that our disclosure controls and procedures are effective to ensure that information required to be disclosed by us in reports that we file or submit under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC rules and forms, and such information is accumulated and communicated to our management, including our principal executive officer and principal financial officer, to allow timely decisions regarding required disclosure.
There was no change in our internal control over financial reporting that occurred during the year ended November 30, 2025 that has materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.
REPORT OF MANAGEMENT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Our management is responsible for establishing and maintaining adequate internal control over financial reporting for the Company. Internal control over financial reporting is a process to provide reasonable assurance regarding the reliability of our financial reporting and the preparation of financial statements for external purposes in accordance with accounting principles generally accepted in the United States. Internal control over financial reporting includes maintaining records that in reasonable detail accurately and fairly reflect our transactions; providing reasonable assurance that transactions are recorded as necessary for preparation of our financial statements; providing reasonable assurance that receipts and expenditures of our assets are made in accordance with management’s authorization; and providing reasonable assurance that unauthorized acquisition, use or disposition of our assets that could have a material effect on the financial statements would be prevented or detected on a timely basis. Because of its inherent limitations, internal control over financial reporting is not intended to provide absolute assurance that a misstatement of our financial statements would be prevented or detected.
Management conducted its evaluation of the effectiveness of our internal controls over financial reporting based on criteria established in Internal Control-Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that our internal control over financial reporting was effective as of November 30, 2025.
The effectiveness of our assessment of internal control over financial reporting as of November 30, 2025 has been audited by PricewaterhouseCoopers LLP, an independent registered public accounting firm, as stated in their report which appears herein.
Figures reported in this filing
Standardized line items from the XBRL in this filing, for the period ended 2025-11-30. Comparative periods it repeats are left out.
| Line item | Period | Value | XBRL concept |
|---|---|---|---|
| Revenue | 12 months2024-12-01 to 2025-11-30 | $0 | us-gaap:Revenues |
| Operating income | 12 months2024-12-01 to 2025-11-30 | −$47.3m | us-gaap:OperatingIncomeLoss |
| Income tax | 12 months2024-12-01 to 2025-11-30 | $0 | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 12 months2024-12-01 to 2025-11-30 | −$94.7m | us-gaap:NetIncomeLoss |
| Basic EPS | 12 months2024-12-01 to 2025-11-30 | −$0.25 | us-gaap:EarningsPerShareBasic |
| Operating cash flow | 12 months2024-12-01 to 2025-11-30 | −$14.0m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Cash and equivalents | At period end2025-11-30 | $110.1m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | At period end2025-11-30 | $117.5m | us-gaap:AssetsCurrent |
| Total assets | At period end2025-11-30 | $335.9m | us-gaap:Assets |
| Current liabilities | At period end2025-11-30 | $4.9m | us-gaap:LiabilitiesCurrent |
| Total liabilities | At period end2025-11-30 | $172.1m | us-gaap:Liabilities |
| Shareholders' equity | At period end2025-11-30 | $163.8m | us-gaap:StockholdersEquity |