The following discussion should be read in conjunction with the financial statements contained in this Form 10-Q as well as Management’s Discussion and Analysis of Financial Condition and Results of Operations and Risk Factors contained in the Form 10-K. We intend for this discussion to provide the reader with information that will assist in understanding our financial statements, the changes in certain key items in those financial statements, and the primary factors that accounted for those changes, as well as how certain accounting principles affect our financial statements. The discussion also provides information about the financial results of the various segments of our business to provide a better understanding of how those segments and their results affect the financial condition and results of operations of Ameren as a whole.

OVERVIEW

Ameren Executive Summary

Ameren’s earnings in the second quarter and first six months of 2010 were lower compared with its earnings in the second quarter and first six months of 2009. Ameren’s earnings were lower during these periods because of reduced margins in Ameren’s Merchant Generation business as a result of lower power prices and higher fuel and related transportation costs, higher depreciation and amortization expenses as a result of infrastructure investment, and unfavorable net unrealized MTM activity related to non-qualified energy and fuel hedges. Additionally, a $13 million pre-tax charge for the impact on deferred taxes of changes in federal health care laws negatively impacted earnings in the first six months of 2010 compared with the year-ago period. Mitigating the impact of these factors in the second quarter and first six months of 2010 were increased sales of electricity to native load utility customers, which reflected improved economic conditions, the return to full capacity, in March 2010, of Noranda’s aluminum smelter plant, and warmer summer weather. Also benefiting earnings in the second quarter and first six months of 2010 were lower financing costs at Ameren’s rate-regulated utilities, reflecting increased regulatory recovery of such costs, and lower operations and maintenance expenses, despite a scheduled refueling and maintenance outage at UE’s Callaway nuclear plant in 2010. The Callaway plant did not have a refueling outage in 2009. The reduced expenses were attributable to disciplined cost management across all of Ameren’s business segments.

In May 2010, the MoPSC issued its order for UE’s retail electric rate increase request. The MoPSC authorized a $230 million increase in rates effective June 21, 2010. UE was able to settle many of the issues in the case. However, several key issues were decided by the MoPSC after hearings, including return on equity, the FAC, UE’s reliability tracking mechanisms and depreciation. While UE was disappointed with the 10.1% authorized return on equity, UE believes the overall order was fair. In a 2007 rate case settlement, UE agreed not to file a new natural gas delivery rate case before March 2010. As a result, UE’s natural gas business is currently earning significantly less than its allowed return on investment. Therefore, in June 2010, UE filed a request with the MoPSC to increase its annual revenues for gas delivery service by $12 million, and new rates are expected to be effective in May 2011. Further, UE plans to file a retail electric case by the end of September 2010. The primary driver of this electric rate filing is the need to begin recovering UE’s projected $600 million investment in the nearly complete Sioux plant scrubbers. This environmental control equipment is key to UE’s ability to meet increasingly strict air emissions standards, including the CATR recently proposed by the EPA.

In April 2010, and as corrected in May 2010, the ICC issued a disappointing rate order for the Ameren Illinois Utilities’ electric and natural gas delivery businesses, authorizing a net $15 million annual increase in delivery rates. In response, the Ameren Illinois Utilities significantly reduced planned spending levels to align their spending with the revenues and related cash flows provided by the ICC’s rate order while still maintaining safe and reliable service. In June 2010, the ICC agreed to rehear several key issues in the case, and the Ameren Illinois Utilities stand ready to restore reliability enhancements that they have cut from capital spending plans if they receive additional revenues as a result of the rehearing process.

On October 1, 2010, Ameren expects to complete the corporate reorganization combining CIPS, CILCO and IP into a single legal entity, which will be called Ameren Illinois Company, and to combine AERG, which is currently a subsidiary of CILCO, with Ameren’s Merchant Generation assets under Resources Company. Ameren has obtained all necessary regulatory approvals to effect this reorganization. This reorganization will bring Ameren’s legal structure in line with the way it operates its business. Ameren believes consolidation of the Ameren Illinois Utilities will, over time, lower costs and increase efficiency, provide greater convenience to the Ameren Illinois Utilities’ customers and improve financial reporting transparency for investors.

Ameren has identified more than $3 billion of transmission investment opportunities in Illinois and Missouri over the next 10 to 15 years, and Ameren is working aggressively, but prudently, to pursue these opportunities. Customers should benefit from improved reliability and a more efficient regional electric system. Ameren’s investors should benefit because Ameren expects to be able to earn attractive returns on investment. On August 2, 2010, Ameren announced the formation of a new subsidiary, the Ameren Transmission Company, which is dedicated to building regional greenfield electric transmission infrastructure under FERC regulation. Investments by the Ameren Transmission Company will be contingent upon pre-approval of supportive rate treatment of the projects by FERC. In addition, the projects would need to be approved by MISO. The Ameren Transmission Company expects to seek appropriate state approvals for the projects as well. The Ameren Transmission Company’s initial investments are expected to be the Grand Rivers projects, the first of which involves building a 345 KV line across the state of Illinois, from the Missouri border to the Indiana border. The investment could total more than $1.3 billion through 2021 with a potential investment of up to $125 million over the 2011 to 2014 period.

In July 2010, the EPA issued the CATR. The CATR is complex, contains alternatives, and is not expected to be finalized until the spring of 2011. As a result, Ameren is still studying the CATR and its potential impacts to its business segments. The Merchant Generation segment has been executing on a plan to install scrubbers to comply with the Illinois MPS. As a result, Ameren believes its Merchant Generation business is better positioned for compliance with the CATR than many of its MISO peers. Under the MPS, the Merchant Generation fleet is required to significantly reduce, by 2015, its emissions of SO2 and NOx to levels comparable to those required by the EPA’s original CAIR. Mercury emissions from Merchant Generation’s larger units in Illinois must be reduced by 90% by 2015. To comply with state and federal regulations, the Merchant Generation segment has taken a number of actions over the years to reduce emissions from its plants, including the installation of selective catalytic reduction and over-fire air systems to control NOx emissions and the use of activated carbon injection to control mercury emissions. In addition, Merchant Generation placed new scrubbers into service at the Duck Creek and Coffeen plants in 2009 and 2010. Further, the Merchant Generation segment has plans in place to install scrubbers at its Newton plant and equipment necessary to support dry sorbent injection at its Joppa plant. At Ameren’s Missouri Regulated segment, the Sioux plant scrubbers are expected to go into service in 2010. Ameren believes the Sioux scrubbers will significantly improve UE’s ability to comply with whatever form the CATR ultimately takes.

General

Ameren, headquartered in St. Louis, Missouri, is a public utility holding company under PUHCA 2005, administered by FERC. Ameren’s primary assets are the common stock of its subsidiaries. Ameren’s subsidiaries are separate, independent legal entities with separate businesses, assets, and liabilities. These subsidiaries operate, as the case may be, rate-regulated electric generation, transmission, and distribution businesses, rate-regulated natural gas transmission and distribution businesses, and merchant electric generation businesses in Missouri and Illinois. Dividends on Ameren’s common stock and the payment of expenses by Ameren depend on distributions made to it by its subsidiaries. Ameren’s principal subsidiaries are listed below.

  • UE operates a rate-regulated electric generation, transmission and distribution business, and a rate-regulated natural gas transmission and distribution business in Missouri.
  • CIPS operates a rate-regulated electric and natural gas transmission and distribution business in Illinois.
  • Genco operates a merchant electric generation business in Illinois and Missouri. Genco has an 80% ownership interest in EEI.
  • CILCO operates a rate-regulated electric transmission and distribution business, a merchant electric generation business (through its subsidiary, AERG) and a rate-regulated natural gas transmission and distribution business, all in Illinois.
  • IP operates a rate-regulated electric and natural gas transmission and distribution business in Illinois.

Ameren, through Genco, has an 80% ownership interest in EEI. Ameren and Genco consolidate EEI for financial reporting purposes. Effective January 1, 2010, as part of an internal reorganization, Resources Company transferred its 80% stock ownership interest in EEI to Genco through a capital contribution. The transfer of EEI to Genco was accounted for as a transaction between entities under common control, whereby Genco accounted for the transfer at the historical carrying value of the parent (Ameren) as if the transfer had occurred at the beginning of the earliest reporting period presented. Ameren’s historical cost basis in EEI included purchase accounting adjustments relating to Ameren’s acquisition of an additional 20% ownership interest in EEI in 2004. This transfer required Genco’s prior-period financial statements to be retrospectively combined for all periods presented. Consequently, Genco’s prior-period consolidated financial statements reflect EEI as if it had been a subsidiary of Genco.

On April 13, 2010, CIPS, CILCO and IP entered into a merger agreement under which CILCO and IP will be merged with and into CIPS as part of a two-step corporate reorganization of Ameren. The second step of the reorganization would involve the distribution of AERG common stock to Ameren and the subsequent contribution by Ameren of the AERG common stock to Resources Company. See Note 14 - Corporate Reorganization under Part I, Item 1, of this report for additional information.

In addition to presenting results of operations and earnings amounts in total, we present certain information in cents per share. These amounts reflect factors that directly affect Ameren’s earnings. We believe this per share information helps readers to understand the impact of these factors on Ameren’s earnings per share. All references in this report to earnings per share are based on average diluted common shares outstanding during the applicable period. All tabular dollar amounts are in millions, unless otherwise indicated.

RESULTS OF OPERATIONS

Earnings Summary

Our results of operations and financial position are affected by many factors. Weather, economic conditions, and the actions of key customers or competitors can significantly affect the demand for our services. Our results are also affected by seasonal fluctuations: winter heating and summer cooling demands. The vast majority of Ameren’s revenues are subject to state or federal regulation. This regulation has a material impact on the price we charge for our services. Merchant Generation sales are also subject to market conditions for power. We principally use coal, nuclear fuel, natural gas, and oil for fuel in our operations. The prices for these commodities can fluctuate significantly due to the global economic and political environment, weather, supply and demand, and many other factors. We have natural gas cost recovery mechanisms for our Illinois and Missouri gas delivery service businesses, purchased power cost recovery mechanisms for our Illinois electric delivery service businesses, and a FAC for our Missouri electric utility business. See Note 2—Rate and Regulatory Matters under Part I, Item 1, for a discussion of UE’s electric rate order issued in May 2010, as well as the combined electric and natural gas delivery service rate order issued in April 2010 for the Ameren Illinois Utilities. Fluctuations in interest rates and conditions in the capital and credit markets affect our cost of borrowing and our pension and postretirement benefits costs. We employ various risk management strategies to reduce our exposure to commodity risk and other risks inherent in our business. The reliability of our power plants and transmission and distribution systems and the level of purchased power costs, operating and administrative costs, and capital investment are key factors that we seek to control to optimize our results of operations, financial position, and liquidity.

Net income attributable to Ameren Corporation decreased to $152 million, or 64 cents per share, in the second quarter of 2010, from $165 million, or 77 cents per share, in the second quarter of 2009. Net income attributable to Ameren Corporation in the second quarter of 2010 decreased in the Merchant Generation segment by $77 million from the prior-year period, while net income attributable to Ameren Corporation in the Illinois Regulated and Missouri Regulated segments increased by $31 million and $31 million, respectively, from the same period in 2009.

Net income attributable to Ameren Corporation decreased to $254 million, or $1.07 per share, in the first six months of 2010 from $306 million, or $1.43 per share, in the first six months of 2009. Net income attributable to Ameren Corporation decreased in the Merchant Generation segment by $126 million in the first six months of 2010 compared to the prior-year period, while net income attributable to Ameren Corporation in the Illinois Regulated and Missouri Regulated segments increased by $39 million and $37 million, respectively, from the same period in 2009.

Earnings were negatively impacted in the second quarter and first six months of 2010, compared with the same periods in 2009, by:

  • lower realized electric margins in the Merchant Generation segment largely due to lower realized revenue per megawatthour sold and higher fuel and related transportation costs (22 cents per share and 46 cents per share, respectively);
  • unfavorable net unrealized MTM activity on energy-related transactions (13 cents per share and 18 cents per share, respectively);
  • higher dilution caused by an increase in the average number of common shares outstanding, largely because of the September 2009 common stock issuance (8 cents per share and 13 cents per share, respectively);
  • costs associated with the Callaway nuclear plant’s 56-day scheduled refueling and maintenance outage in the second quarter of 2010. There was no Callaway refueling and maintenance outage in 2009 (11 cents and 12 cents, respectively); and
  • increased depreciation and amortization expenses, primarily due to capital additions at the Merchant Generation segment and the impact of the January 2009 MoPSC electric rate order for UE (2 cents per share and 6 cents per share, respectively).

Earnings were favorably impacted in the second quarter and first six months of 2010, compared with the same periods in 2009, by:

  • the favorable impact on electric and natural gas margins in our rate-regulated businesses from higher weather-normalized sales volumes (exclusive of higher sales to Noranda discussed below), largely due to improved economic conditions and higher wholesale sales margins at UE because of additional customers and higher-priced wholesale sales contracts, among other things (8 cents per share and 20 cents per share, respectively);
  • lower operations and maintenance expenses, excluding the impact of the Callaway nuclear plant’s refueling and maintenance outage discussed above, as a result of the absence of major storms in 2010, the impact of the employee separation programs initiated in the fourth quarter of 2009, the recognition of regulatory assets at UE for previously-expensed costs as directed by the MoPSC May 2010 rate order, and cost management initiatives, among other things (15 cents per share and 19 cents per share, respectively);
  • higher electric rates in the Missouri Regulated segment pursuant to the MoPSC 2009 and 2010 electric rate orders effective March 1, 2009, and June 21, 2010, respectively (2 cents per share and 9 cents per share, respectively);
  • the impact of weather conditions on energy demand (estimated at 5 cents per share and 8 cents per share, respectively);
  • increased sales to Noranda as its smelter plant in southeast Missouri gradually returned to full capacity by the end of the first quarter of 2010, after a January 2009 severe ice storm significantly reduced the plant’s capacity (3 cents per share and 6 cents per share, respectively);
  • lower financing costs at our rate-regulated utilities. UE’s financing costs decreased as a result of the recognition of a regulatory asset for previously-expensed bank credit facility fees, as directed by the MoPSC May 2010 rate order, as well as an increase in allowance for funds used during construction associated with a project to install a scrubber at its Sioux plant. Illinois Regulated’s financing costs decreased primarily because of a mortgage bond maturity at IP in June 2009 (5 cents per share and 3 cents per share, respectively); and
  • higher electric delivery rates in the Illinois Regulated segment pursuant to the ICC April 2010 rate order, which became effective in May 2010 (3 cents per share for both periods).

In addition to the above items affecting both periods, earnings were negatively impacted in the first six months of 2010, compared with the same period in 2009, by a charge for the impact on deferred taxes from changes in federal health care laws (6 cents per share).

The cents per share information presented above is based on average shares outstanding in the second quarter and first six months of 2009. For further details regarding the second quarter and first six months of 2010 earnings, including explanations of Margins, Other Operations and Maintenance Expenses, Depreciation and Amortization, Taxes Other Than Income Taxes, Interest Charges, and Income Taxes, see the major headings in Results of Operations below.

Because it is a holding company, net income and cash flows attributable to Ameren Corporation are primarily generated by its principal subsidiaries: UE, CIPS, Genco, CILCO and IP. The following table presents the contribution by Ameren’s principal subsidiaries to net income attributable to Ameren Corporation for the three and six months ended June 30, 2010 and 2009:

Net income: Three Months 2010 2009 Six Months 2010 2009
UE $113 $82 $140 $103
CIPS 13 1 22 7
Genco 13 46 36 99
CILCO 12 31 31 64
IP 29 13 47 26
Other(a) (28) (8) (22) 7
Net income attributable to Ameren Corporation $152 $165 $254 $306

(a) Includes earnings from other merchant generation operations, as well as corporate general and administrative expenses, and intercompany eliminations.

Below is a table of income statement components by segment for the three and six months ended June 30, 2010 and 2009:

Three Months 2010: Missouri Regulated Illinois Regulated Merchant Generation Other / Intersegment Eliminations Total
Electric margin $583 $251 $148 $(3) $979
Natural gas margin 13 76 - (1) 88
Other revenues 1 - - (1) -
Other operations and maintenance (240) (137) (69) - (446)
Depreciation and amortization (92) (53) (37) (8) (190)
Taxes other than income taxes (68) (25) (7) - (100)
Other income and (expenses) 19 (1) 1 3 22
Interest charges (43) (33) (35) (4) (115)
Income (taxes) benefit (58) (30) (2) 7 (83)
Net income (loss) 115 48 (1) (7) 155
Noncontrolling interest and preferred dividends (2) (2) (1) 2 (3)
Net income (loss) attributable to Ameren Corporation $113 $46 $(2) $(5) $152
Three Months 2009:
Electric margin $534 $223 $259 $(7) $1,009
Natural gas margin 14 72 - - 86
Other revenues 1 - - (1) -
Other operations and maintenance (220) (153) (84) 6 (451)
Depreciation and amortization (90) (54) (31) (7) (182)
Taxes other than income taxes (66) (25) (7) 1 (97)
Other income and (expenses) 13 2 - (5) 10
Interest charges (57) (40) (23) (4) (124)
Income (taxes) benefit (45) (8) (39) 9 (83)
Net income (loss) 84 17 75 (8) 168
Noncontrolling interest and preferred dividends (2) (2) - 1 (3)
Net income (loss) attributable to Ameren Corporation $82 $15 $75 $(7) $165
Six Months 2010:
Electric margin $1,022 $468 $375 $(10) $1,855
Natural gas margin 42 190 - (1) 231
Other revenues 1 - - (1) -
Other operations and maintenance (458) (276) (142) 14 (862)
Depreciation and amortization (184) (107) (73) (13) (377)
Taxes other than income taxes (136) (66) (15) (1) (218)
Other income and (expenses) 38 (2) 1 - 37
Interest charges (102) (71) (69) (5) (247)
Income (taxes) benefit (80) (54) (33) 9 (158)
Net income (loss) 143 82 44 (8) 261
Noncontrolling interest and preferred dividends (3) (3) (2) 1 (7)
Net income (loss) attributable to Ameren Corporation $140 $79 $42 $(7) $254
Six Months 2009:
Electric margin $945 $416 $546 $(10) $1,897
Natural gas margin 41 183 - - 224
Other revenues 2 4 - (6) -
Other operations and maintenance (436) (289) (162) 15 (872)
Depreciation and amortization (176) (107) (59) (14) (356)
Taxes other than income taxes (128) (64) (14) (1) (207)
Other income and (expenses) 24 3 - (5) 22
Interest charges (110) (81) (48) (3) (242)
Income (taxes) benefit (56) (22) (93) 18 (153)
Net income (loss) 106 43 170 (6) 313
Noncontrolling interest and preferred dividends (3) (3) (2) 1 (7)
Net income (loss) attributable to Ameren Corporation $103 $40 $168 $(5) $306

77

Margins

The following table presents the favorable (unfavorable) variations in the registrants’ electric and natural gas margins in the three and six months ended June 30, 2010, compared with the same periods in 2009. Electric margins are defined as electric revenues less fuel and purchased power costs. Natural gas margins are defined as gas revenues less gas purchased for resale. We consider electric and natural gas margins useful measures to analyze the change in profitability of our electric and natural gas operations between periods. We have included the analysis below as a complement to the financial information we provide in accordance with GAAP. However, these margins may not be a presentation defined under GAAP and may not be comparable to other companies’ presentations or more useful than the GAAP information we provide elsewhere in this report.

Three Months Electric revenue change: Ameren(a) UE CIPS Genco CILCO IP
Effect of weather (estimate) $22 $19 $- $- $1 $2
Regulated rates:
Changes in base rates 19 9 4 - 1 5
Noranda sales 17 17 - - - -
Illinois pass-through power supply costs (37) - (13) - (6) (18)
Bad debt rider 4 - 1 - - 3
Power supply cost recovery 8 - 2 - 1 5
Sales price changes, including hedging effect (51) - - (20) (31) -
Off-system revenues (46) (46) - - - -
2007 Illinois Electric Settlement Agreement, net of reimbursement 6 - 1 2 2 1
Net unrealized MTM losses (14) - - - - -
Weather-normalized sales and other 90 13 1 6 8 5
Total electric revenue change $18 $12 $(4) $(12) $(24) $3
Fuel and purchased power change:
Fuel:
Production volume and other $(27) $(21) $- $(6) $(7) $(1)
FAC net under-recovery 72 72 - - - -
Net unrealized MTM losses (24) - - (19) (4) -
Price (20) - - (15) (5) -
Purchased power (86) (14) - 5 - -
Illinois pass-through power supply costs 37 - 13 - 6 18
Total fuel and purchased power change $(48) $37 $13 $(35) $(10) $17
Net change in electric margins $(30) $49 $9 $(47) $(34) $20
Natural gas margins change:
Effect of weather (estimate) $(3) $(1) $(1) $- $- $(1)
Bad debt rider 4 - 1 - 1 2
Rate decrease (2) - (1) - - (1)
Net unrealized MTM gains 2 - - - 2 -
Weather-normalized sales and other 1 - 1 - - 1
Net change in natural gas margins $2 $(1) $- $- $3 $1

78

Six Months Electric revenue change: Ameren(a) UE CIPS Genco CILCO IP
Effect of weather (estimate) $28 $23 $1 $- $1 $3
Regulated rates:
Changes in base rates 44 32 4 - 1 7
Noranda sales 28 28 - - - -
Illinois pass-through power supply costs (67) - (26) - (10) (31)
Bad debt rider 6 - 2 - - 4
Power supply cost recovery 9 - 2 - 1 6
Sales price changes, including hedging effect (113) - - (46) (67) -
Off-system revenues (101) (101) - - - -
2007 Illinois Electric Settlement Agreement, net of reimbursement 11 - 2 4 3 2
Net unrealized MTM losses (5) (1) - (1) - -
Weather-normalized sales and other 223 59 8 3 42 11
Total electric revenue change $63 $40 $(7) $(40) $(29) $2
Fuel and purchased power change:
Fuel:
Production volume and other $(48) $(28) $- $(7) $(18) $-
FAC net under-recovery 119 119 - - - -
Net unrealized MTM losses (51) (29) - (16) (4) -
Price (38) - - (28) (10) -
Purchased power (154) (25) - 4 - -
Illinois pass-through power supply costs 67 - 26 - 10 31
Total fuel and purchased power change $(105) $37 $26 $(47) $(22) $31
Net change in electric margins $(42) $77 $19 $(87) $(51) $33
Natural gas margins change:
Effect of weather (estimate) $- $- $- $- $- $-
Bad debt rider 5 - 1 - 1 3
Rate decrease (2) - (1) - - (1)
Weather-normalized sales and other 4 1 2 - 1 1
Net change in natural gas margins $7 $1 $2 $- $2 $3

(a) Includes amounts for Ameren registrant and nonregistrant subsidiaries and intercompany eliminations.

Ameren

Ameren’s electric margins decreased by $30 million, or 3%, and $42 million, or 2% for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had an unfavorable impact on Ameren’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Reductions in higher-margin sales at the Merchant Generation segment including the 2006 auction power supply agreements, which expired May 31, 2010, and lower market prices, which resulted in fewer opportunities for economic power sales ($51 million and $113 million, respectively).
  • 13% higher fuel prices for both the quarter and year-to-date periods, respectively, in the Merchant Generation segment primarily due to higher commodity and transportation costs associated with new contracts ($19 million and $36 million, respectively).
  • In the first quarter of 2009, the reversal of previously unrealized losses to regulatory assets resulted in the recognition of a $30 million net MTM gain on energy and fuel-related contracts at UE. After the implementation of UE’s FAC on March 1, 2009, the favorable or unfavorable impact of UE’s net MTM gains or losses no longer impact electric margins. See Note 7 - Derivative Financial Instruments under Part II, Item 8, of the Form 10-K for additional information.
  • Higher net fuel expense at UE due to favorable off-system sales margins in the first quarter of 2009 prior to the FAC becoming effective on March 1, 2009, and UE’s exposure to 5% of net fuel expenses under the FAC ($2 million and $12 million, respectively).
  • Net unrealized MTM activity at the Merchant Generation segment on fuel-related transactions primarily associated with financial instruments that were acquired to mitigate the risk of rising diesel fuel price adjustments embedded in coal transportation contracts ($23 million and $20 million, respectively).
  • Net unrealized MTM activity at the Merchant Generation segment on energy transactions (primarily at Marketing Company), primarily related to nonqualifying hedges of changes in market prices for electricity ($14 million and $4 million, respectively).

The following items had a favorable impact on Ameren’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Favorable weather conditions, as evidenced by a 29% and 28% increase in cooling degree-days, respectively ($20 million and $26 million, respectively).
  • Excluding the impact of UE’s increased sales to Noranda, higher weather-normalized end-use retail sales volumes (5% and 4%, respectively) and customer mix, which were largely due to improved economic conditions ($18 million and $33 million, respectively).
  • Higher electric rates at UE, effective March 1, 2009, and June 21, 2010 ($9 million and $32 million, respectively).
  • Increased UE sales to Noranda in 2010 as its smelter plant gradually returned to full capacity in mid-April 2010 after a January 2009 severe storm significantly reduced the plant’s capacity ($17 million and $28 million, respectively).
  • Higher wholesale sales margins at UE because of additional customers and higher-priced wholesale sales contracts ($1 million and $14 million, respectively).
  • Higher electric rates at the Ameren Illinois Utilities, effective in early May 2010, and at IP, effective October 1, 2009, as residential electric delivery rates were adjusted to recover the full increase of the 2008 ICC rate order ($10 million and $12 million, respectively).
  • A reduction in the impact of the 2007 Illinois Electric Settlement Agreement ($6 million and $11 million, respectively).
  • The recovery of power supply costs incurred at the Ameren Illinois Utilities, including an increase in supply cost adjustment factors as approved in the 2010 ICC electric rate order ($8 million and $9 million, respectively).
  • Initiation of billing for the bad debt rider at the Ameren Illinois Utilities effective March 2010 ($4 million and $6 million, respectively). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.

Ameren’s natural gas margins increased by $2 million, or 2%, and $7 million, or 3%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had a favorable impact on Ameren’s natural gas margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Initiation of billing for the bad debt rider at the Ameren Illinois Utilities effective March 2010 ($4 million and $5 million, respectively). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.
  • Higher weather-normalized sales volumes (13% and 3%, respectively), which was largely due to improved economic conditions (less than $1 million and $4 million, respectively).
  • Favorable weather conditions, as evidenced by a 1% increase in heating degree-days for the six-month period, which increased margins by less than $1 million. Additionally, a 47% decrease in heating-degree days during the second quarter reduced second quarter margins by $3 million.

Ameren’s natural gas margins were unfavorably impacted for the three and six months ended June 30, 2010, compared with the year-ago periods, by lower gas rates effective early May 2010 at the Ameren Illinois Utilities ($2 million and $2 million, respectively).

Missouri Regulated (UE)

UE’s electric margins increased by $49 million, or 9%, and $77 million, or 8%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had a favorable impact on UE’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Higher electric rates, effective March 1, 2009, and June 21, 2010 ($9 million and $32 million, respectively).
  • Favorable weather conditions, as evidenced by a 26% and 24% increase in cooling degree-days, respectively ($17 million and $21 million, respectively).
  • Excluding the impact of increased sales to Noranda, higher weather-normalized end-use retail sales volumes (1% and 2%, respectively) and customer mix, which were largely due to improved economic conditions ($14 million and $20 million, respectively).
  • Increased sales to Noranda in 2010 as its smelter plant gradually returned to full capacity in mid-April 2010 after a January 2009 severe storm significantly reduced the plant’s capacity ($17 million and $28 million, respectively).
  • Higher wholesale sales margins because of additional customers and higher-priced wholesale sales contracts ($1 million and $14 million, respectively).

The following items had an unfavorable impact on UE’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • In the first quarter of 2009, the reversal of previously unrealized losses to regulatory assets resulted in the recognition of a $30 million net MTM gain on energy and fuel-related contracts. After the implementation of UE’s FAC on March 1, 2009, the favorable or unfavorable impact of net MTM gains or losses no longer impact electric margins. See Note 7 - Derivative Financial Instruments under Part II, Item 8, of the Form 10-K for additional information.
  • Higher net fuel expense due to favorable off-system sales margins in the first quarter of 2009 prior to the FAC becoming effective on March 1, 2009, and UE’s exposure to 5% of net fuel expenses under the FAC ($2 million and $12 million, respectively).

UE’s natural gas margins decreased by $1 million, or 7%, in the second quarter of 2010 compared with the year-ago period and increased by $1 million, or 2%, for the six months ended June 30, 2010, compared with the same period in 2009. The following items impacted UE’s natural gas margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Unfavorable weather conditions, as evidenced by a 56% decrease in heating degree-days during the second quarter, which reduced margins by $1 million. However, heating degree-days were favorable by 3% for the year-to-date period, which resulted in an increase in margins of less than $1 million.
  • Lower weather-normalized sales volumes of 6% for the quarter, which reduced margins by less than $1 million; however, weather-normalized volumes increased by 3% for the year-to-date period, which increased margins by $1 million.

Illinois Regulated

Illinois Regulated’s electric margins increased by $28 million, or 13%, and $52 million, or 13%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. Illinois Regulated’s natural gas margins increased by $4 million, or 6%, and $7 million, or 4%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The Ameren Illinois Utilities have a cost recovery mechanism for power purchased on behalf of their customers. These pass-through power costs do not affect margins; however, the electric revenues and offsetting purchased power costs fluctuate primarily because of customer switching and usage. See below for explanations of electric and natural gas margin variances for the Illinois Regulated segment.

CIPS

CIPS’ electric margins increased by $9 million, or 13%, and $19 million, or 15%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had a favorable impact on CIPS’ electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Higher electric rates, effective early May 2010 ($4 million and $4 million, respectively).
  • The recovery of power supply costs incurred, including an increase in supply cost adjustment factors as approved in the 2010 ICC electric rate order ($2 million and $2 million, respectively).
  • Higher weather-normalized sales volumes (2% and 4%, respectively), which were largely due to improved economic conditions (less than $1 million and $3 million, respectively).
  • Initiation of billing for the bad debt rider effective March 2010 ($1 million and $2 million, respectively). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.
  • A reduction in the impact of the 2007 Illinois Electric Settlement Agreement ($1 million and $2 million, respectively).
  • Favorable weather conditions, as evidenced by a 27% increase in cooling degree-days during both the second quarter and year-to-date periods (less than $1 million and $1 million, respectively).

CIPS’ natural gas margins were flat for the quarter but increased $2 million, or 5%, for the six months ended June 30, 2010, compared with the same period in 2009. The following items had a favorable impact on CIPS’ natural gas margins for the three and six months ended June 30, 2010, compared with the year-ago periods:

  • Initiation of billing for the bad debt rider effective March 2010 ($1 million and $1 million, respectively). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.
  • 9% and 2% increase in weather-normalized sales, respectively, which were largely due to improved economic conditions ($1 million and $2 million, respectively).

CIPS’ natural gas margins were unfavorably impacted for the three and six months ended June 30, 2010, compared with the year-ago periods, by lower natural gas rates effective early May 2010 ($1 million and $1 million, respectively).

CILCO (Illinois Regulated)

The following table provides a reconciliation of CILCO’s change in electric margins by segment to CILCO’s total change in electric margins for the three and six months ended June 30, 2010, compared with the same periods in 2009:

Three Months Six Months
CILCO (Illinois Regulated) $(1) $-
CILCO (AERG) (33) (51)
Total change in electric margins $(34) $(51)

CILCO’s (Illinois Regulated) electric margins decreased by $1 million, or 3%, and were flat for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had a favorable impact on CILCO’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Higher weather-normalized sales volumes (5% and 7%, respectively), which were largely due to improved economic conditions (less than $1 million and $1 million, respectively).
  • Favorable weather conditions, as evidenced by a 40% increase in cooling degree-days for both the second quarter and year-to-date periods ($1 million and $1 million, respectively).
  • Higher electric rates, effective early May 2010 ($1 million and $1 million, respectively).
  • Initiation of billing for the bad debt rider effective March 2010 (less than $1 million for both the quarter and year-to-date). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.
  • A reduction in the impact of the 2007 Illinois Electric Settlement Agreement (less than $1 million and $1 million, respectively).
  • The recovery of power supply costs incurred, including an increase in supply cost adjustment factors as approved in the 2010 ICC electric rate order ($1 million and $1 million, respectively).

CILCO’s (Illinois Regulated) electric margins were unfavorably impacted for the three and six months ended June 30, 2010, compared with the year-ago periods, by a settlement associated with CILCO’s previous executory tolling agreement for the generation from the Medina Valley power plant ($3 million and $3 million, respectively).

See Merchant Generation below for an explanation of CILCO’s (AERG) change in electric margins for the three and six months ended June 30, 2010, as compared with the same periods in 2009.

CILCO’s (Illinois Regulated) natural gas margins increased $3 million, or 21%, and $2 million, or 5%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had a favorable impact on CILCO’s natural gas margins for the three and six months ended June 30, 2010, compared with the year-ago periods:

  • Net unrealized MTM losses on natural gas swaps in 2009 ($2 million and $- million, respectively).
  • Initiation of billing for the bad debt rider effective March 2010 ($1 million and $1 million, respectively). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.

IP

IP’s electric margins increased by $20 million, or 17%, and $33 million, or 15%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had a favorable impact on IP’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Higher weather-normalized sales volumes (12% and 8%, respectively), which were largely due to improved economic conditions ($5 million and $9 million, respectively).
  • Higher delivery service rates, effective in early May 2010, and effective October 1, 2009, as residential electric delivery rates were adjusted to recover the full increase of the 2008 ICC rate order ($5 million and $7 million, respectively).
  • The recovery of power supply costs incurred, including an increase in supply cost adjustment factors as approved in the 2010 ICC electric rate order ($5 million and $6 million, respectively).
  • Favorable weather conditions, as evidenced by a 34% increase in cooling degree-days for the quarter and year-to-date periods, respectively ($2 million and $3 million, respectively).
  • Initiation of billing for the bad debt rider effective March 2010 ($3 million and $4 million, respectively). See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.
  • A reduction in the impact of the 2007 Illinois Electric Settlement Agreement ($1 million and $2 million, respectively).

IP’s natural gas margins increased by $1 million, or 2%, and $3 million, or 3%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. This was primarily due to initiation of billing for the bad debt rider effective March 2010 which increased margins by $2 million and $3 million, for the three and six months ended June 30, 2010, respectively. See Operations and Maintenance in this section for additional information on the related offsetting increase in bad debt expense.

IP’s natural gas margins were unfavorably impacted for the three and six months ended June 30, 2010, compared with the year-ago periods, by lower gas rates effective early May 2010 ($1 million and $1 million, respectively).

Merchant Generation

Merchant Generation’s electric margins decreased by $111 million, or 43%, and $171 million, or 31%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009.

Genco

Genco’s electric margins decreased by $47 million, or 28%, and $87 million, or 25%, for the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had an unfavorable impact on Genco’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Lower revenues allocated to Genco under its power supply agreement (Genco PSA) with Marketing Company, due to a smaller pool of money to allocate, which was driven by reductions in higher-margin sales, including the 2006 auction power supply agreements, which expired May 31, 2010, and lower market prices. Genco was allocated a lower percentage of revenues from the pool in the 2010 periods compared with 2009 periods because of lower reimbursable expenses and lower generation relative to AERG in accordance with the Genco PSA.
  • 13% higher fuel prices for both the three and six months ended June 30, 2010, primarily due to higher commodity and transportation costs associated with new contracts ($15 million and $28 million, respectively).
  • Net unrealized MTM activity on fuel-related transactions primarily associated with financial instruments that were acquired to mitigate the risk of rising diesel fuel price adjustments embedded in coal transportation contracts ($19 million and $16 million, respectively).

The following items had a favorable impact on Genco’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • A reduction in the impact of the 2007 Illinois Electric Settlement Agreement ($2 million and $4 million, respectively).
  • Lower emission allowance costs because of lower market prices for emission allowances and reduced generation levels ($1 million and $3 million, respectively).
  • Increased power plant utilization. Genco’s baseload coal-fired generating plants’ average capacity factor increased to 69% in the second quarter 2010, compared with 65% in the second quarter 2009, and Genco’s equivalent availability factor increased to 87% in the second quarter 2010, compared with 83% in the second quarter 2009. Genco’s average capacity factor increased to 71% year-to-date 2010, compared with 68% year-to-date 2009, while Genco’s equivalent availability factor was 85% year-to-date in both 2010 and 2009. Both factors were impacted by the timing of plant outages.

CILCO (AERG)

AERG’s electric margins decreased by $33 million, or 42%, and $51 million, or 34%, in the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The following items had an unfavorable impact on AERG’s electric margins for the three and six months ended June 30, 2010 (except where a specific period is referenced), compared with the year-ago periods:

  • Lower revenues allocated to AERG under its power supply agreement (AERG PSA) with Marketing Company, due to a smaller pool of money to allocate, which was driven by reductions in higher-margin sales, including the 2006 auction power supply agreements, which expired May 31, 2010, and lower market prices. However, AERG was allocated a greater percentage of revenues from the pool in the 2010 periods compared with 2009 periods because of higher reimbursable expenses and higher generation relative to Genco in accordance with the AERG PSA.
  • 18% and 21% higher fuel prices, respectively, primarily due to higher commodity and transportation costs associated with new contracts ($5 million and $10 million, respectively).

AERG’s electric margins were favorably affected by increased power plant utilization, as AERG’s baseload coal-fired generating plants’ average capacity factor increased to 73% in the second quarter 2010, compared with 65% in the second quarter 2009, while AERG’s equivalent availability factor increased to 83% in the second quarter 2010, compared with 73% in the second quarter 2009. AERG’s average capacity factor increased to 76% year-to-date 2010, compared with 62% year-to-date 2009, while AERG’s equivalent availability factor increased to 85% year-to-date 2010, compared with 68% year-to-date 2009. Both factors were impacted by the timing of plant outages.

Other Merchant Generation

Electric margins from Ameren’s other Merchant Generation operations, primarily from Marketing Company, decreased by $31 million, or 258%, and $33 million, or 72%, in the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009. The decrease was primarily due to higher MISO and other costs, and unfavorable net unrealized MTM activity on energy-related transactions at Marketing Company primarily related to nonqualifying hedges of changes in market prices for electricity ($14 million and $3 million, respectively).

Operating Expenses and Other Statement of Income Items

Other Operations and Maintenance

Ameren

Three months - Other operations and maintenance expenses decreased $5 million in the second quarter of 2010, compared with the same period in 2009. Expenses were reduced by $11 million for a May 2010 MoPSC electric rate order, which resulted in UE recording regulatory assets related to employee severance costs and storm costs incurred in 2009. Additionally, labor costs were lower by $9 million, primarily because of staff reductions, and a gain on the sale of property at Genco was recognized in the second quarter of 2010. The absence of major storms in the second quarter, as had occurred in our Illinois Regulated service territory in the second quarter of 2009, also benefited other operations and maintenance expenses between periods by $13 million. There were several other items that unfavorably impacted the prior-year period that did not recur this year - a $5 million penalty was incurred for the termination of a heavy forgings contract associated with efforts to build a new nuclear unit at UE’s Callaway nuclear plant, a $5 million charge was recognized for the termination of a rail line extension project at a subsidiary of Genco, and a $5 million write-off of Ameren’s investment in a supply acquisition partnership was recorded. Reducing the benefit of the above items was an increase in plant maintenance and labor costs of $35 million associated with a refueling and maintenance outage at the Callaway nuclear plant in the second quarter of 2010. Distribution system reliability expenditures increased by $6 million, primarily because of increased vegetation control activities. Bad debt expense increased by $5 million, primarily because of amortization of regulatory assets set up in conjunction with the Illinois bad debt rate adjustment mechanism in 2009. Amortization expense associated with these regulatory assets is offset by increased revenues through collection from customers, with no overall impact on net income.

Six months - Other operations and maintenance expenses decreased $10 million in the six months ended June 30, 2010, compared with the first six months of 2009. Other operations and maintenance expenses were reduced by the recording of regulatory assets and the property sale gain in the second quarter of 2010, as noted above, and by a reduction in labor costs of $8 million, primarily because of staff reductions. Also, the absence in 2010 of major storms, which resulted in $25 million of expense in 2009 in both the Missouri and Illinois service territories, and the absence in 2010 of the forgings contract penalty, rail line project termination cost, and partnership investment write-off noted above resulted in a favorable change between periods. Reducing the favorable impact of these items was an increase in plant maintenance and labor costs of $39 million as a result of the Callaway nuclear plant refueling and maintenance outage and an increase of $11 million for other scheduled outages at coal-fired plants. Distribution system reliability expenditures increased by $8 million, primarily because of increased vegetation control activities.

Variations in other operations and maintenance expenses in Ameren’s and CILCO’s business segments and for the Ameren Companies for the three and six months ended June 30, 2010, compared with the same periods in 2009, were as follows:

Missouri Regulated (UE)

Three months - Other operations and maintenance expenses increased $20 million. Plant maintenance and labor costs increased by $35 million as a result of the Callaway nuclear plant refueling and maintenance outage. Reducing this unfavorable impact was the recording of regulatory assets in 2010 related to employee severance costs and storm costs incurred in 2009, and the absence of the forgings contract penalty in 2010, as noted above.

Six months - Other operations and maintenance expenses increased $22 million. Plant maintenance and labor costs increased by $39 million as a result of the Callaway nuclear plant refueling and maintenance outage and by $9 million for other scheduled coal-fired plant outages. Reducing the unfavorable impact of these items was the absence of major storms, as had occurred in the first quarter of 2009, which resulted in a decrease in other operations and maintenance expenses of $13 million. Additionally, the recording of regulatory assets in 2010 related to employee severance costs and storm costs incurred in 2009, and the absence of the forgings contract penalty in 2010, reduced other operations and maintenance expenses between periods, as noted above.

Illinois Regulated

Three and six months - Other operations and maintenance expenses decreased $16 million and $13 million, respectively, in the Illinois Regulated segment, as discussed below.

CIPS

Three and six months - Other operations and maintenance expenses decreased $13 million and $11 million, respectively, primarily because of the absence of major storms in 2010, as compared with storm costs of $10 million and $13 million, respectively, in 2009.

CILCO (Illinois Regulated)

Three and six months - Other operations and maintenance expenses were comparable between periods.

IP

Three months - Other operations and maintenance expenses were comparable between periods.

Six months - Other operations and maintenance expenses were comparable between periods as increased distribution system reliability expenditures for vegetation control were offset by a reduction in employee benefit costs due to actuarial adjustments.

Merchant Generation

Three and six months - Other operations and maintenance expenses decreased $15 million and $20 million, respectively, in the Merchant Generation segment, as discussed below.

Genco

Three and six months - Other operations and maintenance expenses decreased $13 million and $18 million, respectively, primarily because of lower labor costs due to staff reductions, the absence of expense in 2010 as had been incurred for the termination of the rail line extension project in the second quarter of 2009, and the property sale gain in the second quarter of 2010.

CILCO (AERG)

Three and six months - Other operations and maintenance expenses were comparable between periods.

Depreciation and Amortization

Ameren

Three and six months - Ameren’s depreciation and amortization expenses increased $8 million and $21 million in the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009, because of items noted below at the Ameren Companies.

Variations in depreciation and amortization expenses in Ameren’s and CILCO’s business segments and for the Ameren Companies for the three and six months ended June 30, 2010, compared with the same periods in 2009, were as follows:

Missouri Regulated (UE)

Three months - Depreciation and amortization expenses were comparable between periods.

Six months - Depreciation and amortization expenses increased $8 million, primarily because of capital additions and amortization of regulatory assets that resulted from UE’s electric rate case in 2009.

Illinois Regulated

Three and six months - Depreciation and amortization expenses were comparable between periods in the Illinois Regulated segment and at CIPS, CILCO (Illinois Regulated), and IP.

Merchant Generation

Three and six months - Depreciation and amortization expenses increased $6 million and $14 million, respectively, in the Merchant Generation segment, as discussed below.

Genco

Three and six months - Depreciation and amortization expenses increased $6 million and $11 million, respectively, primarily because of capital additions and increased depreciation rates resulting from depreciation studies performed in the first quarter of 2009.

CILCO (AERG)

Three and six months - Depreciation and amortization expenses were comparable between periods.

Taxes Other Than Income Taxes

Ameren

Three months - Taxes other than income taxes increased $3 million and $11 million in the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009, primarily because of higher gross receipts taxes, as discussed below. Higher property taxes at UE also contributed to the increase in the six-month period.

Variations in taxes other than income taxes in Ameren’s and CILCO’s business segments and for the Ameren Companies for the three and six months ended June 30, 2010, compared with the same periods in 2009, were as follows:

Missouri Regulated (UE)

Three months - Taxes other than income taxes were comparable between periods.

Six months - Taxes other than income taxes increased $8 million, primarily because of higher gross receipts and property taxes. Gross receipts taxes were higher primarily as a result of increased sales. Property taxes increased primarily because of higher assessed tax rates in Missouri.

Illinois Regulated

Three and six months - Taxes other than income taxes were comparable between periods in the Illinois Regulated segment and at CIPS, CILCO (Illinois Regulated), and IP.

Merchant Generation

Three and six months - Taxes other than income taxes were comparable between periods in the Merchant Generation segment and at Genco and CILCO (AERG).

Other Income and Expenses

Ameren

Three and six months - Other income and expenses increased $12 million and $15 million in the three and six months ended June 30, 2010, respectively, compared with the same periods in 2009, primarily because of higher allowance for funds used during construction at UE, as discussed below.

Variations in other income and expenses in Ameren’s and CILCO’s business segments and for the Ameren Companies for the three and six months ended June 30, 2010, compared with the same periods in 2009, were as follows:

Missouri Regulated (UE)

Three and six months - Other income and expenses increased $6 million and $14 million, respectively, primarily because of higher allowance for equity funds used during construction associated with a project to install a scrubber at one of UE’s coal-fired power plants.

Illinois Regulated

Three months - Other income and expenses were comparable between periods in the Illinois Regulated segment and at CIPS, CILCO (Illinois Regulated), and IP.

Six months - Other income and expenses decreased $5 million in the Illinois Regulated segment, primarily because of a reduction in interest income at CIPS. Other income and expenses were comparable between periods at CILCO (Illinois Regulated) and IP.

Merchant Generation

Three and six months - Other income and expenses were comparable between periods in the Merchant Generation segment and at Genco and CILCO (AERG).

Interest Charges

Ameren

Three and six months - Interest charges decreased $9 million in the second quarter of 2010, compared with the second quarter of 2009, but increased $5 million in the six months ended June 30, 2010, respectively, compared with the same period in 2009, because of items noted below at the Ameren Companies. The issuance of $425 million of senior notes at Ameren in May 2009 resulted in additional interest charges in each period.

Variations in interest charges in Ameren’s and CILCO’s business segments and for the Ameren Companies for the three and six months ended June 30, 2010, compared with the same periods in 2009, were as follows:

Missouri Regulated (UE)

Three months - Interest charges decreased $14 million. Interest charges were reduced by $10 million because of a May 2010 MoPSC electric rate order, which resulted in UE recording a regulatory asset related to bank credit facility fees incurred in 2009.

Six months - Interest charges decreased $8 million, primarily because of the effect of the MoPSC electric rate order and increased allowance for funds used during construction associated with a project to install a scrubber at one of UE’s coal-fired power plants, partially mitigated by increased expense associated with the issuance of $350 million of senior secured notes in March 2009.

Illinois Regulated

Three and six months - Interest charges decreased $7 million and $10 million, respectively, in the Illinois Regulated segment, as discussed below.

CIPS and CILCO (Illinois Regulated)

Three and six months - Interest charges were comparable between periods.

IP

Three and six months - Interest charges decreased $4 million and $7 million, respectively, primarily because of the maturity of $250 million of first mortgage bonds in June 2009.

Merchant Generation

Three and six months - Interest charges increased $12 million and $21 million, respectively, in the Merchant Generation segment, as discussed below.

Genco

Three and six months - Interest charges increased $7 million and $10 million, respectively, primarily because of the issuance of $250 million of senior unsecured notes in November 2009.

CILCO (AERG)

Three and six months - Interest charges increased $3 million and $7 million, respectively, primarily because of increased intercompany borrowings to provide cash needed for operations.

Income Taxes

The following table presents effective income tax rates by segment for the three and six months ended June 30, 2010 and 2009:

Three Months 2010 2009 Six Months 2010 2009
Ameren 35% 33% 38% 33%
Missouri Regulated 34 35 36 35
Illinois Regulated 39 32 40 34
Merchant Generation (a) 34 43 35

(a) Not measurable.

Ameren

Ameren’s effective tax rate in the second quarter and first six months of 2010 was higher than the effective tax rate for the same periods in the prior year. Legislation was passed in the first quarter of 2010 that results in retiree health care costs no longer being deductible for tax purposes to the extent an employer’s postretirement health care plan receives federal subsidies that provide retiree prescription drug benefits equivalent to Medicare prescription drug benefits. See Note 12 - Retirement Benefits under Part I, Item 1, of this report for additional information on the impact of the enactment of health care legislation. Additional variations are discussed below.

Variations in effective tax rates for Ameren’s and CILCO’s business segments and for the Ameren Companies for the three and six months ended June 30, 2010, compared with the same periods in 2009, were as follows:

Missouri Regulated (UE)

Three months - UE’s effective tax rate was lower, primarily because of higher favorable net amortization of property-related regulatory assets and liabilities.

Six months - UE’s effective tax rate was higher, primarily because of the change in tax treatment of retiree health care costs, offset by higher favorable net amortization of property-related regulatory assets and liabilities.

Illinois Regulated

The effective tax rate for the second quarter and first six months of 2010 was higher than the effective tax rate for the same periods in 2009 in the Illinois Regulated segment, because of items detailed below.

CIPS and CILCO (Illinois Regulated)

Three months - The effective tax rate increased, primarily because of the decreased impact of favorable net amortization of property-related regulatory assets and liabilities, investment tax credit amortization, and permanent items on higher pretax book income.

Six months - The effective tax rate increased, primarily because of the change in tax treatment of retiree health care costs, along with the items affecting the quarter noted above.

IP

Three months - The effective tax rate was lower, primarily because of the decreased impact of unfavorable permanent items on higher pretax book income.

Six months - The effective tax rate was comparable between periods.

Merchant Generation

The effective tax rate for the second quarter and first six months of 2010 was higher than the effective tax rate for the same periods in 2009 in the Merchant Generation segment, because of items detailed below.

Genco

Three months - The effective tax rate increased, primarily because of changes to reserves for uncertain tax positions and decreased Internal Revenue Code Section 199 production activity deductions.

Six months - The effective tax rate increased, primarily because of the change in tax treatment of retiree health care costs, along with items affecting the quarter noted above.

CILCO (AERG)

Three months - The effective tax rate was lower, primarily because of the impact of Internal Revenue Code Section 199 production activity deductions on lower pretax book income, partially offset by changes to reserves for uncertain tax positions.

Six months - The effective tax rate was lower, primarily because of the impact of changes to reserves for uncertain tax positions and Internal Revenue Code Section 199 production activity deductions on lower pretax book income, partially offset by the change in tax treatment of retiree health care costs.

LIQUIDITY AND CAPITAL RESOURCES

The tariff-based gross margins of Ameren’s rate-regulated utility operating companies (UE, CIPS, CILCO (Illinois Regulated) and IP) continue to be a principal source of cash from operating activities for Ameren and its rate-regulated subsidiaries. A diversified retail customer mix of primarily rate-regulated residential, commercial, and industrial classes and a commodity mix of natural gas and electric service provide a reasonably predictable source of cash flows for Ameren, UE, CIPS, CILCO (Illinois Regulated) and IP. For operating cash flows, Genco and AERG rely on power sales to Marketing Company, which sold power through financial contracts that were part of the 2007 Illinois Electric Settlement Agreement and various power procurement processes in the non-rate-regulated Illinois market. Marketing Company also sells power through other primarily market-based contracts with wholesale and retail customers. In addition to using cash flows from operating activities, the Ameren Companies use available cash, credit facility borrowings, money pool borrowings, or other short-term borrowings from affiliates to support normal operations and other temporary capital requirements. The use of operating cash flows and credit facility or short-term borrowings to fund capital expenditures and other investments may periodically result in a working capital deficit, as was the case at June 30, 2010, for CIPS, Genco and CILCO. The Ameren Companies may reduce their credit facility or short-term borrowings with cash from operations or, discretionarily, with long-term borrowings, or, in the case of Ameren subsidiaries, with equity infusions from Ameren. The Ameren Companies expect to incur significant capital expenditures over the next five years as they comply with environmental regulations and make significant investments in their electric and natural gas utility infrastructure to improve overall system reliability. Ameren intends to finance those capital expenditures and investments with a blend of equity and debt so that it maintains a capital structure in its rate-regulated businesses of approximately 50% to 55% equity. We plan to implement our long-term financing plans for debt, equity, or equity-linked securities in order to finance our operations appropriately, meet scheduled debt maturities, and maintain financial strength and flexibility.

The following table presents net cash provided by (used in) operating, investing and financing activities for the six months ended June 30, 2010 and 2009:

Net Cash Provided By Operating Activities 2010 2009 Variance Net Cash Provided By (Used In) Investing Activities 2010 2009 Variance Net Cash Provided By (Used In) Financing Activities 2010 2009 Variance
Ameren(a) $772 $871 $(99) $(560) $(882) $322 $(328) $170 $(498)
UE 287 132 155 (351) (453) 102 (112) 351 (463)
CIPS 91 125 (34) 8 (5) 13 (14) (110) 96
Genco 147 175 (28) (62) (163) 101 (84) (12) (72)
CILCO 124 144 (20) (27) (97) 70 (57) 17 (74)
IP 119 254 (135) (94) (75) (19) (73) (165) 92

(a) Includes amounts for Ameren registrant and nonregistrant subsidiaries and intercompany eliminations.

Cash Flows from Operating Activities

Ameren’s cash from operating activities decreased in the first six months of 2010, compared with the first six months of 2009. The following items contributed to the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A reduction in cash collected in 2010 from receivables originating from revenues earned in 2009, compared with 2008 revenues collected in 2009. At December 31, 2009, trade receivables and unbilled revenues were $142 million less than they were at December 31, 2008, primarily because of milder weather and lower natural gas commodity costs billed to our customers during the fourth quarter of 2009, compared with the same period in 2008.
  • Coal and transportation payments were $52 million higher in 2010, primarily due to price increases.
  • A $48 million net increase in collateral posted with counterparties due, in part, to the items discussed at the subsidiaries below.
  • Collections from customers, primarily in Illinois, utilizing our budget billing payment option decreased by $42 million as the over-collected balance generated in 2009 reduced collections in 2010.
  • Lower electric margins as discussed in Results of Operations.
  • A $25 million increase in payments related to the Callaway nuclear plant refueling and maintenance outage that occurred in 2010, but did not occur in 2009.
  • A $15 million increase in interest payments primarily due to higher interest rates on credit facility borrowings and other items discussed below. Also, Ameren’s senior secured notes issued in May 2009, required an interest payment in 2010, but did not in 2009.
  • A $12 million increase in property tax payments caused primarily by higher assessed tax rates in Missouri.
  • A $10 million one-time donation for customer assistance programs required by the 2009 Illinois energy legislation and approved by the ICC in February 2010.

At Ameren, the following items partially offset the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • Income tax refunds of $100 million in 2010, compared with income tax payments of $39 million in 2009. The change in income tax cash flows is discussed below.
  • A $104 million increase in cash from operating activities associated with the December 2005 Taum Sauk incident. The 2010 increase was a result of a $100 million reduction in cash payments and a $4 million increase in insurance recoveries compared with 2009. See Note 9 - Commitments and Contingencies under Part I, Item 1, of this report for additional Taum Sauk information.
  • Contributions to the pension and postretirement plans were $27 million lower in 2010. A postretirement plan contribution was made during the second quarter of 2009, but was not made until July of the current year.
  • A $23 million decrease in major storm restoration costs.
  • Improved collection results, primarily at the Ameren Illinois Utilities, as more utility customers were current on their bills as of June 30, 2010, compared with June 30, 2009.
  • A $17 million decrease in funding required under the terms of the 2007 Illinois Electric Settlement Agreement.

UE’s cash from operating activities increased in the first six months of 2010, compared with the first six months of 2009. The following items contributed to the increase in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A $104 million increase in cash from operating activities associated with the December 2005 Taum Sauk incident as discussed above.
  • Higher electric and natural gas margins as discussed in Results of Operations including the benefits of the MoPSC electric rate increase effective March 1, 2009.
  • A $67 million net increase in income tax refunds. The refund primarily was a result of accelerated deductions authorized by economic stimulus legislation and a change in tax treatment of electric generation plant expenditures.
  • A $12 million decrease in major storm restoration costs.
  • A $10 million net reduction in collateral posted with counterparties due, in part, to improved credit ratings.
  • Contributions to the pension and postretirement plans were $7 million lower in 2010, as discussed above.
  • Net collections from customers under the FAC were $4 million higher in 2010.
  • A $4 million decrease in research and development costs.

At UE, the following items partially offset the increase in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A $73 million reduction in net receipts from MISO’s Energy and Operating Reserves Market. The reduction was primarily a result of less output during the Callaway nuclear plant’s refueling and maintenance outage as well as hotter weather in the second quarter of 2010 resulting in less excess power to sell to MISO.
  • A $25 million increase in payments related to the Callaway nuclear plant refueling and maintenance outage that occurred in 2010, but did not occur in 2009.
  • Coal and transportation payments were $14 million higher in 2010, primarily due to price increases.
  • A $12 million increase in property tax payments caused primarily by higher assessed tax rates in Missouri.
  • A $9 million increase in interest payments primarily due to the senior secured notes issued in March 2009, which required an interest payment in 2010, but did not in 2009.
  • A $6 million increase in energy efficiency expenditures for new customer programs.

CIPS’ cash from operating activities decreased in the first six months of 2010, compared with the first six months of 2009. The following items contributed to the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A reduction in cash collected in 2010 from receivables originating from revenues earned in 2009, compared with 2008 revenues collected in 2009. At December 31, 2009, trade receivables and unbilled revenues were $51 million less than they were at December 31, 2008, primarily because of milder weather and lower natural gas commodity costs billed to our customers during the fourth quarter of 2009, compared with the same period in 2008.
  • Collections from customers utilizing CIPS’ budget billing payment option decreased by $12 million as the over-collected balance generated in 2009 reduced collections in 2010.
  • An $11 million net increase in collateral posted with counterparties due, in part, to changes in the market price of natural gas and power.
  • A $2 million one-time donation for customer assistance programs required by the 2009 Illinois energy legislation and approved by the ICC in February 2010.

At CIPS, the following items partially offset the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • Higher electric and natural gas margins as discussed in Results of Operations.
  • Income tax refunds of $1 million in 2010, compared with income tax payments of $10 million in 2009. The refund resulted primarily from storm damage deductions and accelerated deductions authorized by the economic stimulus legislation.
  • An $8 million decrease in major storm restoration costs.
  • Improved collection results as more utility customers were current on their bills as of June 30, 2010, compared with June 30, 2009.
  • A $4 million decrease in funding required under the terms of the 2007 Illinois Electric Settlement Agreement.

Genco’s cash from operating activities decreased in the first six months of 2010, compared with the first six months of 2009. The following items contributed to the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A $43 million reduction in receipts from Marketing Company under the Genco PSA primarily due to lower market prices as discussed in Results of Operations.
  • A $26 million increase in coal and transportation payments, primarily at EEI, where both the price and quantity of tons purchased increased.
  • A $4 million increase in interest payments primarily due to the senior unsecured notes issued in November 2009, which required an interest payment in 2010, but did not in 2009.

At Genco, the following items partially offset the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A $49 million net reduction in income taxes paid, primarily due to lower pretax book income.
  • Lower labor expenditures resulting from employee reductions.
  • A $4 million reduction in funding required by the 2007 Illinois Electric Settlement Agreement.

CILCO’s cash from operating activities decreased in the first six months of 2010, compared with the first six months of 2009. The following items contributed to the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • Lower electric margins as discussed in Results of Operations.
  • A reduction in cash collected in 2010 from receivables originating from revenues earned in 2009, compared with 2008 revenues collected in 2009. At December 31, 2009, trade receivables and unbilled revenues were $45 million less than they were at December 31, 2008, primarily because of milder weather and lower natural gas commodity costs billed to our customers during the fourth quarter of 2009, compared with the same period in 2008.
  • A $17 million reduction in receipts from Marketing Company under the AERG PSA primarily due to lower market prices as discussed in Results of Operations.
  • A $12 million net increase in collateral posted with counterparties due, in part, to changes in the market price of natural gas and power.
  • A $12 million increase in coal and transportation payments at AERG, where both the price and quantity of tons purchased increased.
  • Collections from customers utilizing CILCO’s budget billing payment option decreased by $7 million as the over-collected balance generated in 2009 reduced collections in 2010.
  • A $6 million increase in interest payments primarily due to incremental borrowings and higher interest rates at AERG.
  • A $2 million one-time donation for customer assistance programs required by the 2009 Illinois energy legislation and approved by the ICC in February 2010.

At CILCO, the following items partially offset the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • Income tax refunds of $1 million in 2010, compared with income tax payments of $32 million in 2009. The refund resulted primarily from storm damage deductions and accelerated deductions authorized by the economic stimulus legislation.
  • An $8 million increase in receipts that originated from services provided to CIPS ($4 million) and IP ($4 million) in December 2009 under the CILCO support services agreement.
  • Improved collection results as more utility customers were current on their bills as of June 30, 2010, compared with June 30, 2009.
  • A $4 million decrease in funding required under the terms of the 2007 Illinois Electric Settlement Agreement.
  • Contributions to the pension and postretirement plans were $4 million lower in 2010, as discussed above.

IP’s cash from operating activities decreased in the first six months of 2010, compared with the first six months of 2009. The following items contributed to the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • A reduction in cash collected in 2010 from receivables originating from revenues earned in 2009, compared with 2008 revenues collected in 2009. At December 31, 2009, trade receivables and unbilled revenues were $88 million less than they were at December 31, 2008, primarily because of milder weather and lower natural gas commodity costs billed to our customers during the fourth quarter of 2009, compared with the same period in 2008.
  • A $27 million net increase in collateral posted with counterparties due, in part, to changes in the market price of natural gas and power.
  • Collections from customers utilizing IP’s budget billing payment option decreased by $24 million as the over-collected balance generated in 2009 reduced collections in 2010.
  • A decrease in electric commodity costs over-recovered from customers under cost recovery mechanisms.
  • A $6 million one-time donation for customer assistance programs required by the 2009 Illinois energy legislation and approved by the ICC in February 2010.

At IP, the following items partially offset the decrease in cash from operating activities during the first six months of 2010, compared with the same period in 2009:

  • Higher electric and natural gas margins as discussed in Results of Operations.
  • Contributions to the pension and postretirement plans were $11 million lower in 2010, as discussed above.
  • A $10 million decrease in interest payments primarily due to the mortgage bond maturity in June 2009.
  • Improved collection results as more utility customers were current on their bills as of June 30, 2010, compared with June 30, 2009.
  • A $7 million net increase in income tax refunds. The refund resulted primarily from storm damage deductions and accelerated deductions authorized by the economic stimulus legislation.
  • An increase in natural gas costs over-recovered from customers under the PGA.
  • A $5 million decrease in funding required under the terms of the 2007 Illinois Electric Settlement Agreement.

Cash Flows from Investing Activities

Ameren used less cash for investing activities in the first six months of 2010, compared with the first six months of 2009. Net cash used for capital expenditures decreased in 2010 as a result of efforts to reduce, defer or cancel capital expenditure programs in light of economic conditions and projected financial returns as well as a $92 million reduction of capital expenditures related to the repair of severe storm damage. Additionally, costs associated with power plant scrubber projects decreased from 2009 as a result of the completion of projects in our Merchant Generation segment. Cash flows from investing activities also benefited from $18 million of proceeds received in connection with the sale of 25% of Genco’s Columbia CT facility.

UE’s cash used in investing activities decreased during the first six months of 2010, compared with the same period in 2009, principally because of a $107 million decrease in capital expenditures partially attributable to a $73 million reduction of capital expenditures to repair severe storm damage, as well as other reductions, deferrals or cancellations of capital expenditure programs.

CIPS’ investing activities during the first six months of 2010 generated positive cash flows, while such activities resulted in a net use of cash during the first six months of 2009. The change in cash flow was partially attributable to a $16 million reduction of capital expenditures to repair severe storm damage.

Genco’s cash used in investing activities decreased in the first six months of 2010, compared with the same period in 2009. Net cash used for capital expenditures decreased by $102 million primarily as a result of the completion of two power plant scrubber projects in November 2009 and February 2010. Cash flows from investing activities also benefited from the $18 million of proceeds Genco received in connection with the sale of 25% of its Columbia CT facility. The cash savings related to efforts to reduce, defer or cancel capital expenditure programs enabled Genco to contribute net money pool advances of $21 million during the 2010 period.

CILCO’s cash used in investing activities decreased in the first six months of 2010, compared with the same period in 2009. Net cash used for capital expenditures decreased primarily as a result of a $66 million decrease in capital expenditures at AERG primarily related to the completion of a power plant scrubber project in March 2009 as well as efforts to reduce, defer or cancel capital expenditure projects in response to lower cash flows from operating activities. Capital expenditures related to the maintenance and reliability of the transmission and distribution system at CILCO were comparable between periods.

IP’s cash used in investing activities increased in the first six months of 2010, compared with the same period in 2009 primarily as a result of money pool advances during the 2009 period. Advances to AITC for construction under a joint ownership agreement, primarily related to ongoing independent power producer transmission projects, decreased $22 million compared with the first six months of 2009. Capital expenditures related to the maintenance and reliability of the transmission and distribution system decreased in the first six months of 2010, compared with the same period in 2009, partially attributable to a $2 million reduction of capital expenditures to repair severe storm damage.

Capital Expenditures

Ameren’s Merchant Generation segment reduced its estimated capital costs by $440 million, compared to those disclosed in the Form 10-K. The reduction in estimated capital costs primarily related to a $420 million reduction in estimated costs to comply with state air quality implementation plans, the MPS, federal ambient air quality standards including ozone and fine particulates, and the federal Clean Air Visibility rule in the Merchant Generation segment. In addition, the Ameren Illinois Utilities reduced their estimated capital costs for 2010 by $60 million, compared to those disclosed in the Form 10-K, in an effort to synchronize their costs with revenues granted in the 2010 ICC rate order. UE is currently evaluating its capital expenditure plans for projects that may be eliminated or deferred to help customers with their future energy costs while also strengthening UE’s financial profile. Merchant Generation’s estimates shown in the table below could change depending upon additional federal or state requirements, the requirements under a MACT standard, the requirements under a finalized CATR, new technology, and variations in costs of material or labor, or alternative compliance strategies, among other factors. The estimates in the table below contain all of Merchant Generation’s known capital costs to comply with existing and known emissions-related regulations as of June 30, 2010.

The following table provides estimates as of June 30, 2010, of capital expenditures that are expected to be incurred by the Ameren Companies from 2010 through 2014, including construction expenditures, capitalized interest for our Merchant Generation business and allowance for funds used during construction for our rate-regulated utility businesses, and estimated expenditures for compliance with environmental standards. The reduced estimates for Ameren’s Merchant Generation segment and the Ameren Illinois Utilities described above are reflected in the table below. The estimates in the table below do not include impacts of the proposed CATR.

2010 2011 - 2014 Total
UE $695 $2,565- $3,465 $3,260- $4,160
CIPS 80 340- 460 420- 540
Genco 110 590- 950 700- 1,060
CILCO (Illinois Regulated) 50 250- 340 300- 390
CILCO (AERG) 5 130- 175 135- 180
IP 140 670- 910 810- 1,050
Other 50 125- 170 175- 220
Ameren(a) $1,130 $4,670- $6,470 $5,800- $7,600

(a) Includes amounts for Ameren registrant and nonregistrant subsidiaries.

See Note 9 - Commitments and Contingencies under Part I, Item 1, of this report for a discussion of future environmental capital expenditure estimates.

We continually review our generation portfolio and expected power needs. As a result, we could modify our plan for generation capacity, which could include changing the times when certain assets will be added to or removed from our portfolio, the type of generation asset technology that will be employed, and whether capacity or power may be purchased, among other things. Any changes that we may plan to make for future generating needs could result in significant capital expenditures or losses being incurred, which could be material.

Cash Flows from Financing Activities

During the first six months of 2010, Ameren used existing cash and credit facility borrowings to fund its working capital needs, fund $183 million of common stock dividends and repay $23 million of net generator advances for construction related to ongoing independent power producer transmission projects. Comparatively, during the first six months of 2009, Ameren issued $772 million of senior secured notes and used the proceeds to reduce short-term debt and pay $164 million of common stock dividends. In addition, Ameren received $37 million of net advances from generators in the second quarter of 2009.

Efforts to reduce, defer and cancel capital expenditures enabled UE to use existing cash to fund its working capital needs during the first six months of 2010. This allowed UE to increase common stock dividends $17 million during the first six months of 2010 compared with the first six months of 2009. Comparatively, during the second quarter of 2009, UE issued $349 million of senior secured notes and used the proceeds to reduce short-term debt and reduce borrowings under an intercompany note with Ameren.

CIPS’ net cash used in financing activities decreased during the six months ended June 30, 2010, compared with the first six months of 2009. This change was primarily a result of CIPS using existing cash to meet its working capital needs, make capital investments, and fund $16 million in common stock dividends. During the first six months of 2009, CIPS used existing cash to fund a net reduction in short-term debt and money pool borrowings.

Genco’s cash used in financing activities increased during the six months ended June 30, 2010, compared with the six months ended June 30, 2009, primarily as a result of a $130 million change in intercompany borrowings, which was further reduced by a $54 million reduction of common stock dividends. During 2010, Genco made net repayments of $84 million to Ameren on an intercompany note, while during 2009, Genco received $34 million in net money pool borrowings and $12 million in net note proceeds. Efforts to reduce, defer and cancel capital expenditures during the 2010 period have resulted in reduced Genco financing activities as Genco has been able to use existing cash to meet working capital needs, make capital investments, and reduce its borrowings.

CILCO’s financing activities during the first six months of 2010 resulted in a net use of cash, while such activities provided cash flows during the first six months of 2009. During 2010, CILCO used existing cash to fund its working capital needs, make capital investments, and fund a net repayment of intercompany borrowings with Ameren. During the first second quarter of 2009, CILCO used money pool borrowings and intercompany borrowings to meet its working capital needs and to repay short-term borrowings.

IP’s cash used in financing activities decreased during the first six months of 2010, compared with the first six months of 2009, primarily as the result of the maturity of IP’s 7.5% mortgage bonds during the 2009 period. No such maturities occurred during the 2010 period. Additionally, during 2010, IP used existing cash to fund its working capital needs, make capital investments, fund $42 million of common stock dividends, and repay $30 million of net generator advances. During 2009, IP received $35 million of net generator advances related to ongoing independent power producer transmission projects, and a $58 million capital contribution from Ameren. The capital contribution was made to ensure IP maintained a capital structure of approximately 50% to 55% to equity.

Credit Facility Borrowings and Liquidity

The liquidity needs of the Ameren Companies are typically supported through the use of available cash, short-term intercompany borrowings, or drawings under committed bank credit facilities. See Note 3 - Credit Facility Borrowings and Liquidity under Part I, Item 1, of this report for additional information on credit facilities, short-term borrowing activity, relevant interest rates, and borrowings under Ameren’s utility and non-state-regulated subsidiary money pool arrangements.

The following table presents the committed bank credit facilities of Ameren and the Ameren Companies, and availability under the facilities, as of June 30, 2010:

Credit Facility Ameren, UE and Genco: Expiration Amount Committed Amount Available
2009 Multiyear credit agreements(a)(b) July 2011 $1,300 $615 (c)
Ameren, CIPS, CILCO and IP:
2009 Illinois credit agreement June 2011 800 800
Ameren:
$20 million credit agreement June 2012 20 -

(a) The Ameren Companies may access these credit facilities through intercompany borrowing arrangements.

(b) Includes the 2009 Multiyear Credit Agreement and the 2009 Supplemental Credit Agreement. The 2009 Supplemental Credit Agreement expired in July 2010 with all commitments and all outstanding amounts consolidated with those under the 2009 Multiyear Credit Agreement, and the combined maximum amount available to all borrowers became $1.0795 billion with the UE and Genco borrowing sublimits remaining the same and Ameren’s changing to $1.0795 billion.

(c) In addition to amounts drawn on these facilities, the amount available is further reduced by standby letters of credit issued under the facilities. The amount of such letters of credit at June 30, 2010, was $15 million.

Another source of liquidity for the Ameren Companies from time to time is available cash and cash equivalents. At June 30, 2010, Ameren (on a consolidated basis), UE, CIPS, Genco, CILCO, and IP had cash and cash equivalents totaling $506 million, $91 million, $113 million, $7 million, $128 million, and $142 million, respectively.

The issuance of short-term debt securities by Ameren’s utility subsidiaries is subject to approval by FERC under the Federal Power Act. In March 2010, FERC issued an order authorizing the issuance of short-term debt securities subject to the following limits on outstanding balances: UE - $1 billion, CIPS - $300 million, and CILCO - $250 million. The authorization was effective as of April 1, 2010, and terminates on March 31, 2012. IP has unlimited short-term debt authorization from FERC.

On April 27, 2010, Genco filed an application with FERC requesting unlimited long and short-term debt issuance authorization. On July 16, 2010, FERC granted Genco’s request. AERG and EEI have unlimited short-term debt authorization from FERC.

The issuance of short-term debt securities by Ameren is not subject to approval by any regulatory body.

The Ameren Companies continually evaluate the adequacy and appropriateness of their liquidity arrangements given changing business conditions. When business conditions warrant, changes may be made to existing credit facilities or other short-term borrowing arrangements.

Long-term Debt and Equity

The following table presents the issuances of common stock and the issuances, redemptions, repurchases and maturities of long-term debt (net of any issuance discounts and including any redemption premiums) for the six months ended June 30, 2010 and 2009, for the Ameren Companies. For additional information, see Note 4 - Long-term Debt and Equity Financings under Part I, Item 1, of this report.

Issuances Long-term debt Ameren: Month Issued, Redeemed, Repurchased or Matured Six Months 2010 2009
8.875% Senior unsecured notes due 2014 May $- $423
UE:
8.45% Senior secured notes due 2039 March - 349
Total Ameren long-term debt issuances $- $772
Common stock
Ameren:
DRPlus and 401(k) Various $43 $47
Total common stock issuances $43 $47
Total Ameren long-term debt and common stock issuances $43 $819
Redemptions, Repurchases and Maturities
Long-term debt
IP:
7.50% Series mortgage bond due 2009 June - 250
Total Ameren long-term debt redemptions, repurchases and maturities $- $250

In November 2008, Ameren, as a well-known seasoned issuer, along with CIPS, Genco, CILCO and IP, filed a Form S-3 shelf registration statement registering the issuance of an indeterminate amount of certain types of securities, which expires in November 2011. In June 2008, UE, as a well-known seasoned issuer, filed a Form S-3 shelf registration statement registering the issuance of an indeterminate amount of certain types of securities, which expires in June 2011.

The following table presents information with respect to the Form S-3 shelf registration statements filed and effective for certain Ameren Companies as of June 30, 2010:

Effective Date Authorized Amount
Ameren November 2008 Not Limited
UE June 2008 Not Limited
CIPS November 2008 Not Limited
Genco November 2008 Not Limited
CILCO November 2008 Not Limited
IP November 2008 Not Limited

In July 2008, Ameren filed a Form S-3 registration statement with the SEC authorizing the offering of six million additional shares of its common stock under DRPlus. Shares of common stock sold under DRPlus are, at Ameren’s option, newly issued shares, treasury shares, or shares purchased in the open market or in privately negotiated transactions. Ameren is currently selling newly issued shares of its common stock under DRPlus.

Ameren is also currently selling newly issued shares of its common stock under its 401(k) plan pursuant to an effective SEC Form S-8 registration statement. Under DRPlus and its 401(k) plan, Ameren issued a total of 0.9 million new shares of common stock valued at $23 million and 1.7 million new shares valued at $43 million in the three and six months ended June 30, 2010.

Ameren, UE, CIPS, Genco, CILCO and IP may sell all or a portion of the securities registered under their effective registration statements if market conditions and capital requirements warrant such a sale. Any offer and sale will be made only by means of a prospectus that meets the requirements of the Securities Act of 1933 and the rules and regulations thereunder.

Indebtedness Provisions and Other Covenants

See Note 4 - Credit Facility Borrowings and Liquidity and Note 5 - Long-term Debt and Equity Financings in the Form 10-K for a discussion of covenants and provisions contained in our bank credit facilities and in certain of the Ameren Companies’ indenture agreements and articles of incorporation.

At June 30, 2010, the Ameren Companies were in compliance with their credit facilities, indenture, and articles of incorporation provisions and covenants.

We consider access to short-term and long-term capital markets a significant source of funding for capital requirements not satisfied by our operating cash flows. Inability to raise capital on favorable terms, particularly during times of uncertainty in the capital markets, could negatively affect our ability to maintain and expand our businesses. After assessing our current operating performance, liquidity, and credit ratings (see Credit Ratings below), we believe that we will continue to have access to the capital markets. However, events beyond our control may create uncertainty in the capital markets or make access to the capital markets uncertain or limited. Such events could increase our cost of capital and adversely affect our ability to access the capital markets.

Dividends

Ameren paid to its stockholders common stock dividends totaling $183 million, or 77 cents per share, during the first six months of 2010 (2009 - $164 million or 77 cents per share).

See Note 4 - Long-term Debt and Equity Financings under Part I, Item 1, of this report and Note 4 - Credit Facility Borrowings and Liquidity and Note 5 - Long-term Debt and Equity Financings in the Form 10-K for a discussion of covenants and provisions contained in certain of the Ameren Companies’ financial agreements and articles of incorporation that would restrict the Ameren Companies’ payment of dividends in certain circumstances. At June 30, 2010, none of these circumstances existed with respect to the Ameren Companies and, as a result, the Ameren Companies were allowed to pay dividends.

UE, CIPS, Genco, CILCO and IP as well as other certain nonregistrant Ameren subsidiaries are subject to Section 305(a) of the Federal Power Act, which makes it unlawful for any officer or director of a public utility, as defined in the Federal Power Act, to participate in the making or paying of any dividend from any funds “properly included in capital account.” The meaning of this limitation has never been clarified under the Federal Power Act or FERC regulations; however, FERC has consistently interpreted the provision to allow dividends to be paid as long as (1) the source of the dividends is clearly disclosed, (2) the dividend is not excessive and (3) there is no self-dealing on the part of corporate officials. At a minimum, Ameren believes that dividends can be paid by its subsidiaries that are public utilities from net income and retained earnings. In addition, under Illinois law, CIPS, CILCO and IP may not pay any dividend on their respective stock, unless, among other things, their respective earnings and earned surplus are sufficient to declare and pay a dividend after provision is made for reasonable and proper reserves, or unless CIPS, CILCO or IP has specific authorization from the ICC.

The following table presents common stock dividends paid by Ameren Corporation and by Ameren’s subsidiaries to their respective parents for the six months ended June 30, 2010 and 2009:

Six Months 2010 2009
UE $116 $99
CIPS 16 -
Genco - 43
CILCO 9 -
IP 42 -
Nonregistrants - 22
Dividends paid by Ameren $183 $164

Contractual Obligations

For a complete listing of our obligations and commitments, see Contractual Obligations under Part II, Item 7 and Note 15 - Commitments and Contingencies under Part II, Item 8 of the Form 10-K, and Other Obligations in Note 9 - Commitments and Contingencies under Part I, Item 1, of this report. See Note 12 - Retirement Benefits to our financial statements under Part I, Item 1, of this report for information regarding expected minimum funding levels for our pension plan.

At June 30, 2010, total other obligations related to the procurement of coal, natural gas, nuclear fuel, methane gas, electric capacity, equipment and meter reading services, and a tax credit obligation, among other agreements, at Ameren, UE, CIPS, Genco, CILCO and IP were $7,275 million, $4,035 million, $343 million, $1,096 million, $1,019 million, and $727 million, respectively. Also, the Ameren Illinois Utilities participated in RFPs to procure electric capacity, financial energy swaps, and renewable energy credits. The IPA procured electric capacity, financial energy swaps, and renewable energy credits through RFP processes on behalf of the Ameren Illinois Utilities. At June 30, 2010, obligations related to electric capacity, financial energy swaps, and renewable energy credits at the Ameren Illinois Utilities were $63 million, $497 million, and $3 million, respectively. Further, total other obligations related to unrecognized tax benefits, at June 30, 2010, for Ameren, UE, CIPS, Genco, CILCO and IP were $163 million, $113 million, $6 million, $18 million, $14 million, and $10 million, respectively.

Credit Ratings

The credit ratings for the Ameren Companies affect our liquidity, our access to the capital markets and credit markets, our cost of borrowing under our credit facilities and the need to post collateral under commodity contracts.

The following table presents the principal credit ratings of the Ameren Companies of Moody’s, S&P and Fitch effective on the date of this report:

Ameren: Moody’s S&P Fitch
Issuer/corporate credit rating Baa3 BBB - BBB
Senior unsecured debt Baa3 BB + BBB
UE:
Issuer/corporate credit rating Baa2 BBB - BBB +
Secured debt A3 BBB A
CIPS:
Issuer/corporate credit rating Baa3 BBB - BBB -
Secured debt Baa1 BBB + BBB +
Senior unsecured debt Baa3 BBB - BBB
Genco:
Issuer/corporate credit rating - BBB - BBB
Senior unsecured debt Baa3 BBB - BBB
CILCO:
Issuer/corporate credit rating Baa3 BBB - BBB -
Secured debt Baa1 BBB + BBB +
IP:
Issuer/corporate credit rating Baa3 BBB - BBB -
Secured debt Baa1 BBB BBB +

98

Collateral Postings and Cost of Borrowing

Any adverse change in the Ameren Companies’ credit ratings may reduce access to capital and trigger additional collateral postings and prepayments. Such changes may also increase the cost of borrowing and fuel, power and natural gas supply, among other things, resulting in a negative impact on earnings. Collateral postings and prepayments made with external parties, including postings related to exchange-traded contracts, at June 30, 2010, were $165 million, $24 million, $7 million, $13 million, and $40 million at Ameren, UE, CIPS, CILCO and IP, respectively. The amount of collateral external counterparties posted with Ameren was $3 million at June 30, 2010. Sub-investment-grade issuer or senior unsecured debt ratings (lower than “BBB-” or “Baa3” from S&P or Moody’s, respectively) at June 30, 2010, could have required Ameren, UE, CIPS, Genco, CILCO or IP to post additional collateral or other assurances for certain trade obligations amounting to $323 million, $101 million, $44 million, $22 million, $49 million, and $63 million, respectively.

In addition, changes in commodity prices could trigger additional collateral postings and prepayments at current credit ratings. If market prices were 15% higher than June 30, 2010, levels in the next twelve months and 20% higher thereafter through the end of the term of the commodity contracts, Ameren, UE, CIPS, Genco, CILCO or IP could be required to post additional collateral or other assurances for certain trade obligations up to approximately $70 million, $11 million, $- million, $- million, $- million, and $- million, respectively. If market prices were 15% lower than June 30, 2010, levels in the next twelve months and 20% lower thereafter through the end of the term of the commodity contracts, Ameren, UE, CIPS, Genco, CILCO or IP could be required to post additional collateral or other assurances for certain trade obligations up to approximately $159 million, $7 million, $18 million, $- million, $49 million, and $46 million, respectively.

The cost of borrowing under our credit facilities can increase or decrease depending upon the credit ratings of the borrower. A credit rating is not a recommendation to buy, sell or hold securities. It should be evaluated independently of any other rating. Ratings are subject to revision or withdrawal at any time by the rating organization.

OUTLOOK

Below are some key trends that may affect the Ameren Companies’ financial condition, results of operations, or liquidity for the remainder of 2010 and beyond.

Economy and Capital and Credit Markets

In 2008 and 2009, global capital and credit markets experienced extreme volatility. While these markets have stabilized and conditions have improved, we believe that these events have several continuing implications for our industry as a whole, including Ameren. They include the following:

  • Economic Conditions - Weak economic conditions have resulted in reduced power prices. Weak economic conditions also expose the Ameren Companies to greater risk of default by counterparties, potentially higher bad debt expenses, and the risk of impairment of goodwill and long-lived assets, among other things. Based on the results of the annual goodwill impairment test completed as of October 31, 2009, the estimated fair value of Ameren’s Merchant Generation reporting unit exceeded its carrying value by a nominal amount. The failure in the future of this reporting unit, or any reporting unit, to achieve forecasted operating results and cash flows, an unfavorable change in forecasted operating results and cash flows, or a further decline of observable industry market multiples may reduce its estimated fair value below its carrying value and would likely result in the recognition of a goodwill impairment charge. Economic conditions in our service territory have improved in 2010, contributing to higher weather-normalized end-use retail sales volume at Ameren’s rate-regulated utilities. We are unable to predict the ultimate impact of the weak economy on our results of operations, financial position, or liquidity.
  • Investment Returns - The disruption in the capital markets, coupled with weak global economic conditions, adversely affected financial markets. Through June 30, 2010, the actual return on investment of the pension plan assets and postretirement plan assets was lower than the expected return. Lower returns increase our future pension and postretirement expenses and pension funding levels. Our future expenses and funding levels will also be affected by future investment returns and future discount rate levels.
  • Operating and Capital Expenditures - The Ameren Companies will continue to make significant levels of investments and incur expenditures for their electric and natural gas utility infrastructure in order to improve overall system reliability, comply with environmental regulations, and improve plant performance. However, during both 2008 and 2009, in response to the significant level of disruption and uncertainties in the capital and credit markets and weak economic conditions that reduced power prices, we significantly reduced our planned capital expenditures for 2010 through 2014. In addition, during 2010, Ameren’s Merchant Generation segment reduced its estimated planned capital expenditures by an additional $440 million for 2010 through 2014 compared to those disclosed in the Form 10-K. The Ameren Illinois Utilities reduced their estimated planned capital costs for 2010 by $60 million, compared to those disclosed in the Form 10-K, in an effort to synchronize their costs with revenues granted in the ICC April 2010 rate order. Also, UE is currently evaluating its capital expenditure plans for projects that may be eliminated or deferred to help customers with their future energy costs while also strengthening UE’s financial profile. In addition, Ameren took steps to control operations and maintenance expenditures. Ameren is managing power plant outages and labor costs, among other things. In addition to the operations and maintenance expenditure reductions announced in the prior year, in May 2010, Ameren’s Merchant Generation segment announced the reduction of 75 full-time positions effective during the second quarter of 2010. The reduction of these positions, coupled with other planned spending reductions, is expected to reduce 2010 other operations and maintenance expenses to approximately $300 million in 2010. This is approximately 10% lower than other operations and maintenance expenses in 2009. Any expenditure control initiatives will be balanced against a continued long-term commitment to invest in our electric and natural gas infrastructure to provide safe, reliable electric and natural gas delivery services to our customers; to meet federal and state environmental, reliability, and other regulations; and the need to maintain a solid overall liquidity and credit ratings profile to meet our operating, capital, and financing needs.
  • Access to Capital Markets and Cost of Capital - The extreme disruption in the capital markets in 2008 and 2009 limited the ability of many companies, including the Ameren Companies, to freely access the capital and credit markets to support their operations and to refinance debt. Ameren and its subsidiaries continued to have access to the capital markets during the period. The cost of this access was at commercially acceptable, but higher, interest rates in the case of the issuance of certain debt securities in 2008 and 2009. During 2010, we have observed improved access to capital in the U.S. capital and credit markets and lower interest rates on new issuances of investment grade debt securities compared with 2008 and 2009. A future disruption in the capital markets could limit our ability to access the capital markets, which access our business depends on, and result in increased financing costs.
  • Credit Facilities - On June 30, 2009, Ameren and certain of its subsidiaries successfully reached definitive multiyear credit facility agreements. These facilities cumulatively provided $2.1 billion of credit capacity through July 14, 2010, and currently provide $1.8795 billion of credit capacity. Such capacity will decrease to $1.0795 billion on June 30, 2011, and expire on July 14, 2011. The costs of these credit facilities are significantly higher than the costs of the facilities they replaced. The costs to enter into the multiyear credit facility agreements were $40 million in the aggregate (UE - $11 million, CIPS - $3 million, Genco - $5 million, CILCO - $7 million, and IP - $7 million). The costs are being amortized over the term of the facilities. In addition, borrowing rates under the facilities increased significantly, including, in the case of Ameren, from LIBOR plus 0.5%, under the prior credit facilities, to LIBOR plus 2.75%. Ameren intends to replace or extend its credit facility agreements by the end of the third quarter of 2010.
  • Liquidity - At June 30, 2010, Ameren, on a consolidated basis, had available liquidity, in the form of cash on hand and amounts available under its existing credit facilities, of approximately $1.9 billion, which was $500 million more than the available liquidity at June 30, 2009.

We believe that our liquidity is adequate given our expected operating cash flows, capital expenditures, and related financing plans (including the replacement or extension of our existing credit facilities). However, there can be no assurance that significant changes in economic conditions, further disruptions in the capital and credit markets, or other unforeseen events will not materially affect our ability to execute our expected operating, capital or financing plans.

Current Capital Expenditure Plans

  • Between 2010 and 2017, Ameren expects to invest up to $1.43 billion, in the aggregate, to retrofit its coal-fired power plants with pollution control equipment in compliance with emissions-related environmental laws and regulations. Any pollution control investments will result in decreased plant availability during construction and significantly higher ongoing operating expenses. Approximately 30% of this investment is expected to be in our Missouri Regulated operations, and it is therefore expected to be recoverable from ratepayers, subject to prudency reviews. Regulatory lag may materially impact the timing of such recovery and, therefore, our cash flows and related financing needs. The recoverability of amounts expended in our Merchant Generation operations will depend on whether market prices for power adjust as a result of market conditions reflecting increased environmental costs for coal-fired generators.
  • Future federal and state legislation or regulations that mandate limits on emissions would result in significant increases in capital expenditures and operating costs. Excessive costs to comply with future legislation or regulations might force Ameren and other similarly situated electric power generators to close some coal-fired facilities. Investments to control emissions at Ameren’s coal-fired power plants to comply with future legislation or regulations would significantly increase future capital expenditures and operations and maintenance expenses, which if excessive could result in the closures of coal-fired power plants, impairment of assets, or otherwise materially adversely affect Ameren’s results of operations, financial position, and liquidity.
  • UE continues to evaluate its longer-term needs for new baseload and peaking electric generation capacity. UE’s integrated resource plan filed with the MoPSC in February 2008 included the expectation that new baseload generation capacity would be required in the 2018 to 2020 time frame. Due to the significant time required to plan, acquire permits for, and build a baseload power plant, UE continues to study future plant alternatives, including energy efficiency programs that could help defer new plant construction. UE introduced multiple energy efficiency programs in 2009 and 2010. The goal of these and future UE energy efficiency programs is to reduce usage by 540 megawatts by 2025, which is the equivalent of a medium-size coal-fired power plant. UE will consider all available and feasible generation options to meet future customer requirements as part of an integrated resource plan that UE will file with the MoPSC in 2011.
  • In July 2008, UE filed an application with the NRC for a combined construction and operating license for a new 1,600-megawatt nuclear unit at UE’s existing Callaway nuclear plant site. In June 2009, UE requested the NRC suspend review of the COLA and all activities related to the COLA. As of June 30, 2010, UE had capitalized approximately $67 million as construction work in progress related to the COLA. The incurred costs will remain capitalized while management assesses all options to maximize the value of its investment in this project. If all efforts are permanently abandoned with respect to the future construction of a new nuclear unit or management concludes it is probable the costs incurred will be disallowed in rates, it is possible that a charge to earnings could be recognized in a future period.
  • UE intends to submit a license extension application with the NRC to extend its existing Callaway nuclear plant’s operating license by 20 years so that the operating license will expire in 2044. UE cannot predict whether or when the NRC will approve the license extension.
  • Over the next few years, we expect to make significant investments in our electric and natural gas infrastructure and to incur increased operations and maintenance expenses to improve overall system reliability. We are committed to synchronizing our operations and maintenance spending and capital investments within our rate-regulated businesses with the revenue and related cash flow levels provided by our regulators. We expect these costs or investments at our rate-regulated businesses to be ultimately recovered in rates, subject to prudency reviews by regulators, although rate case outcomes and regulatory lag could materially impact the timing of such recovery and, therefore, our cash flows, related financing needs and the timing in which we are able to proceed with these projects. We are projecting labor and material costs for these capital expenditures will increase over time.
  • On August 2, 2010, Ameren announced the formation of Ameren Transmission Company, a new direct subsidiary dedicated to electric transmission infrastructure investment. Ameren Transmission Company intends to build projects initially within Illinois and Missouri, with the potential for expanding to other areas in the future. Ameren Services on behalf of Ameren Transmission Company, UE, CIPS, CILCO and IP, filed a petition with FERC in August 2010 requesting approval of certain rate treatments with respect to Ameren Transmission Company’s proposed initial portfolio of transmission projects, which consists of a potential $1.3 billion investment in a collection of high voltage transmission projects in Missouri and Illinois. The Ameren Transmission Company’s initial investments are expected to be the Grand Rivers projects, the first of which involves building a 345 KV line across the state of Illinois, from the Missouri border to the Indiana border. The investment could total more than $1.3 billion through 2021 with a potential investment of up to $125 million over the 2011 to 2014 period. Ameren Transmission Company expects to operate as a transmission-owning member of MISO.
  • Increased investments for environmental compliance, reliability improvement, and new baseload capacity will result in higher depreciation and financing costs.

Revenues

  • The earnings of UE, CIPS, CILCO and IP are largely determined by the regulation of their rates by state agencies. Rising costs, including labor, material, depreciation, and financing costs, coupled with increased capital and operations and maintenance expenditures targeted at enhanced distribution system reliability and environmental compliance, are expected. Ameren, UE, CIPS, CILCO and IP anticipate regulatory lag until their requests to increase rates to recover such costs on a timely basis are granted by state regulators. Ameren, UE, CIPS, CILCO and IP expect to file rate cases frequently. UE currently expects to file an electric rate case by the end of September 2010.
  • In future rate cases, UE, CIPS, CILCO and IP will continue to seek cost recovery and tracking mechanisms from their state regulators to reduce the effects of regulatory lag.
  • On May 6, 2010, the ICC amended its April 2010 rate order to correct a technical error in the calculation of cash working capital. The ICC consolidated rate order, as amended, approved a net increase in annual revenues for electric delivery service of $35 million in the aggregate (CIPS - $18 million increase, CILCO - $2 million increase, and IP - $15 million increase) and a net decrease in annual revenues for natural gas delivery service of $20 million in the aggregate (CIPS - $2 million decrease, CILCO - $7 million decrease, and IP - $11 million decrease). The rate changes became effective in May 2010. In response to the ICC consolidated rate order, the Ameren Illinois Utilities took immediate action to mitigate the financial pressures created on the respective companies by the rate order. See Note 2 - Rate and Regulatory Matters under Part I, Item 1, of this report. On May 28, 2010, the Ameren Illinois Utilities filed a rehearing request with the ICC relating to six issues of the rate order. On June 14, 2010, the ICC agreed to rehear three issues raised by the Ameren Illinois Utilities and one issue raised by intervenors. The issue raised by intervenors primarily relates to rate design. The issues raised by the Ameren Illinois Utilities could result in an additional increase in annual revenues of $55 million if approved by the ICC. In July 2010, the ICC staff recommended the Ameren Illinois Utilities should receive an additional increase in annual revenues of $11 million. The ICC has five months to complete the rehearing with a decision due in November 2010. The Ameren Illinois Utilities may subsequently appeal the ICC consolidated rate order. The Ameren Illinois Utilities cannot predict the outcome of the rehearing or whether court appeals will be filed and their ultimate outcome.
  • The ICC order confirmed the previously approved 80% allocation of fixed non-volumetric residential and commercial natural gas customer charges, and approved a higher percentage of recovery of fixed non-volumetric electric residential and commercial customer charges. The percentage of costs to be recovered through fixed non-volumetric electric residential and commercial customer and meter charges increased from 27% to 40%.
  • The ICC order also extended the amortization period of the IP integration-related regulatory asset, which was previously set to be fully amortized by December 2010. The new order extended the amortization for two years beginning in May 2010. This change will result in a pretax reduction to amortization expense of $7 million in 2010. The ICC order also created a $3 million regulatory asset, in the aggregate, for the Ameren Illinois Utilities’ costs incurred in 2009 for the voluntary and involuntary separation programs. These costs will be amortized over three years beginning in May 2010.
  • The ICC issued a consolidated rate order in September 2008 approving a net increase in annual revenues for electric delivery service. These rate changes were effective on October 1, 2008. The Ameren Illinois Utilities made a pledge to keep the overall residential electric bill increase resulting from these rate changes during the first year to less than 10% for each utility. As a result, IP did not recover approximately $10 million in revenue during the first year the electric delivery service rates were in effect. IP began to recover the full amount of the ICC-approved rate increase beginning October 1, 2009. As a result, IP recognized a $4 million increase in electric margins during the first six months of 2010 and expects to earn an additional $4 million during the remainder of 2010.
  • Ameren’s FERC jurisdictional electric transmission rates are updated on June 1 of each year. Based on transmission rate calculations that became effective on June 1, 2010, the Ameren Illinois Utilities recognized additional revenues of $2 million during June 2010, and anticipate additional revenues of approximately $20 million for the remaining six months of 2010, compared to the same periods in 2009. The increase is due, in part, to a significant increase in transmission assets placed into service during 2009, as well as higher equity levels as a result of Ameren’s capital contributions to CIPS, CILCO and IP in 2009.
  • On May 28, 2010, the MoPSC issued an order approving an increase for UE in annual revenues for electric service of approximately $230 million, including $119 million to cover higher fuel costs and lower revenue from sales outside UE’s system. See Note 2 - Rate and Regulatory Matters under Part I, Item 1, of this report for additional information about other significant provisions and appeal of the MoPSC’s order.
  • The provisions of the May 28, 2010 MoPSC order also resulted in the recognition of new regulatory assets. The new regulatory assets resulted in a $21 million reduction to 2010 pretax expense, largely for the reversal of expenses that were recognized before 2010. These new regulatory assets will be amortized over the next two to five years beginning July 2010, as described in Note 2 - Rate and Regulatory Matters under Part I, Item 1, of this report. The increased amortization of the regulatory assets and the increase in annual depreciation expense due to the adoption of the life span depreciation methodology is estimated to increase UE’s pretax expense by $10 million in the second half of 2010 ($20 million on an annual basis).
  • Even though Taum Sauk was not available to generate electricity for off-system revenues during 2009, UE included $19 million in the calculation of the FAC as if Taum Sauk had generated off-system revenues. Therefore, UE’s customers received the benefit of Taum Sauk’s historical off-system revenues even though the plant was not operational. Upon Taum Sauk’s return to service, which occurred in April 2010, UE’s earnings and cash flows from operations have increased since the adjustment factor has been eliminated from the FAC calculation. Taum Sauk is expected to increase UE’s 2010 margins by $16 million.
  • UE provides power to Noranda’s smelter plant in New Madrid, Missouri, which has historically used approximately four million megawatthours of power annually, making Noranda UE’s single largest customer. As a result of a severe ice storm in January 2009, Noranda’s smelter plant experienced a power outage related to non-UE lines that deliver power to the substation serving the plant. Electric sales to Noranda have gradually increased since the storm and, in March 2010, the plant was restored to full capacity. As a result, UE expects its margins from sales to Noranda will increase by approximately $40 million in 2010, compared with 2009. The MoPSC’s May 28, 2010 electric rate order created a mechanism that will prospectively address the significant lost revenues UE can incur due to future operational issues at Noranda’s smelter plant in southeast Missouri. The mechanism will permit UE, when a loss of service occurs at the Noranda plant, to sell the power not taken by Noranda and use the proceeds of those sales to offset the revenues lost from Noranda. UE would be allowed to keep the amount of revenues necessary to compensate UE for significant Noranda usage reductions but any excess revenues above the level necessary to compensate UE would be refunded to retail customers through the FAC.
  • UE filed a request with the MoPSC in June 2010 to increase its annual revenues for natural gas delivery service by approximately $12 million. The MoPSC proceeding relating to the proposed natural gas delivery service rate changes will take place over a period of up to 11 months, and a decision by the MoPSC in such proceeding is required by the end of May 2011.
  • As part of the 2007 Illinois Electric Settlement Agreement, the Ameren Illinois Utilities entered into financial contracts with Marketing Company (for the benefit of Genco and AERG), to lock in energy prices for 400 to 1,000 megawatts annually of their round-the-clock power requirements during the period June 1, 2008, to December 31, 2012, at then-relevant market prices. These financial contracts do not include capacity, are not load-following products, and do not involve the physical delivery of energy. Under the terms of the 2007 Illinois Electric Settlement Agreement, these financial contracts are deemed prudent, and the Ameren Illinois Utilities are permitted full recovery of their costs in rates.
  • Volatile power prices in the Midwest can affect the amount of revenues Ameren, Genco and CILCO (through AERG) generate by marketing power into the wholesale and spot markets and can influence the cost of power purchased in the spot markets. Spot market prices can be significantly affected by any prospect of global economic recovery, among other things.
  • With few scheduled maintenance outages in 2010 through 2012, the Merchant Generation segment expects to have available generation from its coal-fired plants of 35 million megawatthours in each year. However, the Merchant Generation segment’s actual generation levels will be significantly impacted by market prices for power in those years, among other things.
  • The availability and performance of Genco’s, AERG’s and EEI’s electric generation fleet can materially affect their revenues. The Merchant Generation segment expects to generate 30.5 million megawatthours of power from its coal-fired plants in 2010 (Genco - 15 million, AERG - 8 million, EEI - 7.5 million) based on expected power prices. Should power prices rise more than expected, the Merchant Generation segment has the capacity and availability to sell more generation.
  • The marketing strategy for the Merchant Generation segment is to optimize generation output in a low risk manner to minimize volatility of earnings and cash flow, while seeking to capitalize on its low-cost generation fleet to provide solid, sustainable returns. To accomplish this strategy, the Merchant Generation segment has established hedge targets for near-term years. Through a mix of physical and financial sales contracts, Marketing Company targets to hedge Merchant Generation’s expected output by 80% to 90% for the following year, 50% to 70% for two years out, and 30% to 50% for three years out. As of June 30, 2010, Marketing Company had hedged approximately 28.5 million megawatthours of Merchant Generation’s expected 2010 generation, at an average price of $47 per megawatthour. For 2011, Marketing Company had hedged approximately 23 million megawatthours of Merchant Generation’s forecasted generation sales at an average price of $46 per megawatthour. For 2012, Marketing Company had hedged approximately 14 million megawatthours of Merchant Generation’s forecasted generation sales at an average price of $52 per megawatthour. Marketing Company has also entered into capacity-only sales contracts for 2010, 2011, and 2012, resulting in expected capacity-only revenues related to these contracts of $65 million, $46 million, and $18 million, respectively. Any unhedged sales will be exposed to relevant market prices at the time of the sale.
  • The development of a capacity market in MISO could increase the electric margins of Genco and AERG. A capacity requirement obligates a load serving entity to acquire capacity sufficient to meet its obligations. MISO continues to refine its treatment of capacity supply and obligations, but development of a true capacity market could still be several years away.
  • Current and future energy efficiency programs developed by UE, CIPS, CILCO and IP and others could result in reduced demand for our electric generation and our electric and natural gas transmission and distribution services. Our regulated operations will seek a regulatory framework that allows either a return on these programs or recovery of their costs.

Fuel and Purchased Power

  • In 2009, 83% of Ameren’s electric generation (UE - 75%, Genco - 99%, AERG - 100%, EEI - 100%) was supplied by coal-fired power plants. About 96% of the coal used by these plants (UE - 96%, Genco - 99%, AERG - 89%, EEI - 100%) was delivered by rail from the Powder River Basin in Wyoming. In the past, deliveries from the Powder River Basin have occasionally been restricted because of rail maintenance, weather, and derailments. As of June 30, 2010, coal inventories for the Ameren Companies were at targeted levels. However, Merchant Generation is targeting a reduction in its coal inventories below historical levels by the end of 2010 in order to increase liquidity. Disruptions in coal deliveries could cause UE, Genco and AERG to pursue a strategy that could include reducing sales of power during low-margin periods, buying higher-cost fuels to generate required electricity, or purchasing power from other sources.
  • Ameren’s fuel costs (including transportation) are expected to increase in 2010 and beyond. As of June 30, 2010, the average cost of Merchant Generation’s baseload hedged fuel costs, which include coal, transportation, diesel fuel surcharges, and other charges, was approximately $22.50 per megawatthour in 2010, $25 per megawatthour in 2011, and $26 per megawatthour in 2012. See Item 3 - Quantitative and Qualitative Disclosures About Market Risk of this report for additional information about the percentage of fuel and transportation requirements that are price-hedged for 2010 through 2014.

Other Costs

  • In December 2005, there was a breach of the upper reservoir at UE’s Taum Sauk pumped-storage hydroelectric facility. This resulted in significant flooding in the local area, which damaged a state park. UE settled with FERC and the state of Missouri all issues associated with the December 2005 Taum Sauk incident. UE has property and liability insurance coverage for the Taum Sauk incident, subject to certain limits and deductibles. Insurance does not cover lost electric margins or penalties paid to FERC. UE received approval from FERC to rebuild the upper reservoir at its Taum Sauk plant. The rebuilt Taum Sauk plant became fully operational in April 2010. The cost to rebuild the upper reservoir was approximately $490 million. Under UE’s insurance policies, all claims by or against UE are subject to review by its insurance carriers. In June 2010, UE received $57 million, as the final property insurance settlement, from the three property insurance carriers that had previously filed a petition against Ameren in the Circuit Court of St. Louis County, Missouri in July 2009. That settlement resolved the lawsuit and Ameren’s counterclaim against these insurers. In June 2010, UE filed a lawsuit against an insurance company that provided UE with liability coverage on the date of the Taum Sauk incident. In the litigation, filed in the U.S. District Court for the Eastern District of Missouri, UE claims the insurance company breached its duty to indemnify UE for the losses experienced from the incident, and therefore, UE requests reimbursement and penalties consistent with the insurance policy terms and statutory law. Until Ameren’s remaining liability insurance claims and the related litigation are resolved, among other things, we are unable to determine the total impact the breach could have on Ameren’s and UE’s results of operations, financial position, and liquidity beyond those amounts already recognized. The recoverability of any Taum Sauk facility rebuild costs from customers is subject to the terms and conditions set forth in UE’s November 2007 State of Missouri settlement agreement. Certain costs associated with the Taum Sauk facility not recovered from property insurers may be recoverable from UE’s electric customers through rates established in rate cases filed subsequent to the in-service date of the rebuilt facility. As of June 30, 2010, UE had capitalized in property and plant Taum Sauk-related costs of $97 million that UE believes qualify for potential recovery in electric rates under the terms of the November 2007 State of Missouri settlement agreement. The inclusion of such costs in UE’s electric rates is subject to review and approval by the MoPSC in a future rate case. Any amounts not recovered in electric rates, or otherwise, could result in charges to earnings, which could be material. See Note 9 - Commitments and Contingencies under Part I, Item 1, of this report for further discussion of Taum Sauk matters.
  • UE’s Callaway nuclear plant had a scheduled refueling and maintenance outage during the second quarter of 2010, which lasted 56 days. Callaway’s next scheduled refueling and maintenance outage is in the fall of 2011. During a scheduled outage, which occurs every 18 months, maintenance and purchased power costs increase, and the amount of excess power available for sale decreases, compared with non-outage years.
  • Over the next few years, we expect rising employee benefit costs, as well as higher insurance premiums as a result of insurance market conditions and loss experience, among other things.

Other

  • A ballot initiative passed by Missouri voters in November 2008 created a renewable energy portfolio requirement. UE and other Missouri investor-owned utilities will be required to purchase or generate electricity from renewable energy sources equaling at least 2% of native load sales by 2011, with that percentage increasing in subsequent years to at least 15% by 2021, subject to a 1% limit on customer rate impacts. At least 2% of each portfolio requirement must be derived from solar energy. Compliance with the renewable energy portfolio requirement can be achieved through the procurement of renewable energy or renewable energy credits. Final rules implementing the renewable energy requirement were issued by the MoPSC in July 2010. UE expects that any related costs or investments would ultimately be recovered in rates. In August 2010, UE filed an appeal with the Circuit Court of Cole County, Missouri. UE cannot predict when the court will issue a ruling or the ultimate outcome of its appeal.
  • In July 2010, President Obama signed into law the “Wall Street Reform and Consumer Protection Act.” The new legislation will require additional government regulation of derivative and OTC transactions that could expand collateral requirements. Ameren is currently evaluating the new legislation to determine its impact to our results of operations, financial position, and liquidity. Depending on how the legislation is interpreted in subsequent rulemaking, it could reduce the effectiveness of hedging, increasing the volatility of earnings, and could require increased collateral postings.
  • In 2010, President Obama signed into law a health care reform bill that makes several fundamental changes to the U.S. health care system. In March 2010, Ameren recorded a $13 million charge relating to the taxation of the Medicare Part D subsidy. The Ameren Companies are currently evaluating the long-term effects of this reform and the health care benefits they currently offer their employees and retirees. Until that review is completed, Ameren is unable to estimate the effects of the new law on its results of operations, financial position, and liquidity.
  • Ameren and Genco are evaluating alternative operational modes for the Meredosia and Hutsonville plants.
  • In an attempt to improve access to capital, reduce financing costs, and enhance administrative efficiencies, among other things, in April 2010, CIPS, CILCO and IP entered into a merger agreement under which CILCO and IP will be merged with and into CIPS. As a result of the merger, in addition to the rate-regulated businesses of CILCO and IP, CIPS will also acquire CILCO’s merchant electric generation business, AERG. As one of a series of transactions that have been or will be taken to consolidate Ameren’s merchant electric generation businesses, following the effective time of the merger, CIPS will distribute all of its shares of AERG common stock to Ameren with the subsequent contribution by Ameren of the AERG common stock to Resources Company. See Note 14 - Corporate Reorganization under Part I, Item 1, of this report for additional information.

The above items could have a material impact on our results of operations, financial position, or liquidity. Additionally, in the ordinary course of business, we evaluate strategies to enhance our results of operations, financial position, or liquidity. These strategies may include acquisitions, divestitures, opportunities to reduce costs or increase revenues, and other strategic initiatives to increase Ameren’s stockholder value. We are unable to predict which, if any, of these initiatives will be executed. The execution of these initiatives may have a material impact on our future results of operations, financial position, or liquidity.

REGULATORY MATTERS

See Note 2 - Rate and Regulatory Matters under Part I, Item 1, of this report.

Market risk

As filed, 20,058 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Market risk is the risk of changes in value of a physical asset or a financial instrument, derivative or nonderivative, caused by fluctuations in market variables such as interest rates, commodity prices, and equity security prices. A derivative is a contract whose value is dependent on, or derived from, the value of some underlying asset. The following discussion of our risk management activities includes forward-looking statements that involve risks and uncertainties. Actual results could differ materially from those projected in the forward-looking statements. We handle market risks in accordance with established policies, which may include entering into various derivative transactions. In the normal course of business, we also face risks that are either nonfinancial or nonquantifiable. Such risks, principally business, legal, and operational risks, are not part of the following discussion.

Our risk management objective is to optimize our physical generating assets and pursue market opportunities within prudent risk parameters. Our risk management policies are set by a risk management steering committee, which is composed of senior-level Ameren officers.

Except as discussed below, there have been no material changes to the quantitative and qualitative disclosures about market risk in the Form 10-K. See Item 7A under Part II of the Form 10-K for a more detailed discussion of our market risks.

Interest Rate Risk

We are exposed to market risk through changes in interest rates. The following table presents the estimated increase in our annual interest expense and decrease in annual net income that would result if interest rates on variable-rate debt outstanding at June 30, 2010, were to increase by 1%:

Interest Expense Net Income(a)
Ameren(b) $10 $(6)
UE 2 (1)
CIPS (c) (c)
Genco 1 (1)
CILCO 2 (2)
IP (c) (c)

(a) Calculations are based on an effective tax rate of 38%.

(b) Includes intercompany eliminations.

(c) Less than $1 million.

The estimated changes above do not consider the potential reduced overall economic activity that would exist in such an environment. In the event of a significant change in interest rates, management would probably act to further mitigate our exposure to this market risk. However, due to the uncertainty of the specific actions that would be taken and their possible effects, this sensitivity analysis assumes no change in our financial structure.

Credit Risk

Credit risk represents the loss that would be recognized if counterparties fail to perform as contracted. Exchange-traded contracts are supported by the financial and credit quality of the clearing members of the respective exchanges and have nominal credit risk. In all other transactions, we are exposed to credit risk in the event of nonperformance by the counterparties to the transaction. See Note 6 - Derivative Financial Instruments under Part I, Item 1, of this report for information on the potential loss on counterparty exposure as of June 30, 2010.

Our revenues are primarily derived from sales or delivery of electricity and natural gas to customers in Missouri and Illinois. Our physical and financial instruments are subject to credit risk consisting of trade accounts receivable and executory contracts with market risk exposures. The risk associated with trade receivables is mitigated by the large number of customers in a broad range of industry groups who make up our customer base. At June 30, 2010, no nonaffiliated customer represented more than 10%, in the aggregate, of our accounts receivable. The risk associated with the Ameren Illinois Utilities’ electric and natural gas trade receivables is also mitigated by a rate adjustment mechanism that allows the Ameren Illinois Utilities to recover the difference between their actual bad debt expense and the bad debt expense included in their base rates. UE and the Ameren Illinois Utilities continue to monitor the impact of increasing rates and the current economic environment on customer collections. UE and the Ameren Illinois Utilities make adjustments to their allowance for doubtful accounts as deemed necessary, to ensure that such allowances are adequate to cover estimated uncollectible customer account balances.

UE, CIPS, Genco, CILCO, AERG, IP, AFS and Marketing Company may have credit exposure associated with interchange or wholesale purchase and sale activity with nonaffiliated companies. At June 30, 2010, UE’s, CIPS’, Genco’s, CILCO’s, AERG’s, IP’s, AFS’ and Marketing Company’s combined credit exposure to nonaffiliated non-investment-grade trading counterparties was $2 million, net of collateral (2009 - less than $1 million). We establish credit limits for these counterparties and monitor the appropriateness of these limits on an ongoing basis through a credit risk management program that involves daily exposure reporting to senior management, master trading and netting agreements, and credit support, such as letters of credit and parental guarantees. We also analyze each counterparty’s financial condition before we enter into sales, forwards, swaps, futures, or option contracts, and we monitor counterparty exposure associated with our leveraged lease. We estimate our credit exposure to MISO associated with the MISO Energy and Operating Reserves Market to be $47 million at June 30, 2010 (2009 - $5 million).

Equity Price Risk

Our costs of providing defined benefit retirement and postretirement benefit plans are dependent upon a number of factors, including the rate of return on plan assets. To the extent the value of plan assets declines, the effect would be reflected in net income and OCI or regulatory assets, and in the amount of cash required to be contributed to the plans.

Commodity Price Risk

We are exposed to changes in market prices for electricity, emission allowances, fuel, and natural gas. UE’s, Genco’s and AERG’s risks of changes in prices for power sales are partially hedged through sales agreements. Genco and AERG also seek to sell power forward to wholesale, municipal, and industrial customers to limit exposure to changing prices. We also attempt to mitigate financial risks through structured risk management programs and policies, which include forward-hedging programs, and the use of derivative financial instruments (primarily forward contracts, futures contracts, option contracts, and financial swap contracts). However, a portion of the generation capacity of UE, Genco and AERG is not contracted through physical or financial hedge arrangements and is therefore exposed to volatility in market prices.

The following table presents how Ameren’s cumulative net income might decrease if power prices were to decrease by 1% on unhedged economic generation for the remainder of 2010 through 2014:

Net Income(a)
Ameren(b) $(27)
UE (8)
Genco (16)
CILCO (AERG) (4)

(a) Calculations are based on an effective tax rate of 38%.

(b) Includes amounts for Ameren registrant and nonregistrant subsidiaries and intercompany eliminations.

Ameren also uses its portfolio management and trading capabilities both to manage risk and to deploy risk capital to generate additional returns. Due to our physical presence in the market, we are able to identify and pursue opportunities, which can generate additional returns through portfolio management and trading activities. All of this activity is performed within a controlled risk management process. We establish value at risk (VaR) and stop-loss limits that are intended to prevent any material negative financial impact.

We manage risks associated with changing prices of fuel for generation using techniques similar to those used to manage risks associated with changing market prices for electricity. Most UE, Genco and AERG fuel supply contracts are physical forward contracts. Genco and AERG do not have the ability to pass through higher fuel costs to their customers for electric operations. Prior to March 2009, UE did not have this ability either except through a general rate proceeding. As a part of the January 2009 MoPSC electric rate order, UE was granted permission to put a FAC in place, which became effective March 1, 2009. UE remains exposed to 5% of changes in its fuel and purchased power costs, net of off-system revenues. UE, Genco and AERG have entered into long-term contracts with various suppliers to purchase coal to manage their exposure to fuel prices. The coal hedging strategy is intended to secure a reliable coal supply while reducing exposure to commodity price volatility. Price and volumetric risk mitigation is accomplished primarily through periodic bid procedures, whereby the amount of coal purchased is determined by the current market prices and the minimum and maximum coal purchase guidelines for the given year. UE, Genco and AERG generally purchase coal up to five years in advance, but we may purchase coal beyond five years to take advantage of favorable deals or market conditions. The strategy also allows for the decision not to purchase coal to avoid unfavorable market conditions.

Transportation costs for coal and natural gas can represent a significant portion of fuel costs. UE, Genco and AERG typically hedge coal transportation forward to provide supply certainty and to mitigate transportation price volatility. Natural gas transportation expenses for Ameren’s gas distribution utility companies and the gas-fired generation units of UE and Genco are regulated by FERC through approved tariffs governing the rates, terms, and conditions of transportation and storage services. Certain firm transportation and storage capacity agreements held by the Ameren Companies include rights to extend the contracts prior to the termination of the primary term. Depending on our competitive position, we are able in some instances to negotiate discounts to these tariff rates for our requirements.

The following table presents the percentages of the projected required supply of coal and coal transportation for our coal-fired power plants, nuclear fuel for UE’s Callaway nuclear plant, natural gas for our CTs, and retail distribution, as appropriate, and purchased power needs of CIPS, CILCO and IP, which own no generation, that are price-hedged over the remainder of 2010 through 2014, as of June 30, 2010. The projected required supply of these commodities could be significantly affected by changes in our assumptions for such matters as customer demand for our electric generation and our electric and natural gas distribution services, generation output, and inventory levels, among other matters.

Ameren: 2010 2011 2012 - 2014
Coal 95% 79% 21%
Coal transportation 100 93 39
Nuclear fuel 100 100 78
Natural gas for generation 84 20 -
Natural gas for distribution(a) 66 35 16
Purchased power for Illinois Regulated(b) 100 78 22
UE:
Coal 95% 86% 24%
Coal transportation 100 100 44
Nuclear fuel 100 100 78
Natural gas for generation 100 13 -
Natural gas for distribution(a) 69 36 19
CIPS:
Natural gas for distribution(a) 62% 35% 17%
Purchased power(b) 100 78 22
Genco:
Coal 98% 71% 17%
Coal transportation 100 78 26
Natural gas for generation 73 20 -
CILCO:
Coal (AERG) 98% 72% 20%
Coal transportation (AERG) 100 100 56
Natural gas for distribution(a) 64 37 17
Purchased power(b) 100 78 22
IP:
Natural gas for distribution(a) 69% 34% 14%
Purchased power(b) 100 78 22

(a) Represents the percentage of natural gas price hedged for peak winter season of November through March. The year 2010 represents November 2010 through March 2011. The year 2011 represents November 2011 through March 2012. This continues each successive year through March 2015.

(b) Represents the percentage of purchased power price-hedged for fixed-price residential and small commercial customers with less than one megawatt of demand. Larger customers are purchasing power from the competitive markets. See Note 9 - Commitments and Contingencies under Part I, Item 1, of this report for a discussion of the Illinois power procurement process and for additional information on the Ameren Illinois Utilities’ purchased power commitments.

The following table shows how our cumulative fuel expense might increase and how our cumulative net income might decrease if coal and coal transportation costs were to increase by 1% on any requirements not currently covered by fixed-price contracts for the period 2010 through 2014.

Coal Fuel Expense Net Income(a) Transportation Fuel Expense Net Income(a)
Ameren $18 $(11) $17 $(11)
UE 10 (6) 8 (5)
Genco 6 (4) 8 (5)
CILCO (AERG) 2 (1) 1 (1)

(a) Calculations are based on an effective tax rate of 38%.

In addition, coal and coal transportation costs are sensitive to the price of diesel fuel as a result of rail freight fuel surcharges. Ameren utilizes a combination of swaps and purchased call options to price cap and price hedge this exposure. If diesel fuel costs were to increase or decrease by $0.25/gallon, and Ameren did not have these swaps and purchased call options, Ameren’s fuel expense could increase or decrease by $5 million for the remainder of 2010 (UE - $3 million, Genco - $1 million, AERG - $1 million). As of June 30, 2010, Ameren had a price cap for approximately 89% of expected fuel surcharges in 2010.

In the event of a significant change in coal prices, UE, Genco, and AERG would probably take actions to further mitigate their exposure to this market risk. However, due to the uncertainty of the specific actions that would be taken and their possible effects, this sensitivity analysis assumes no change in our financial structure or fuel sources.

With regard to exposure for commodity price risk for nuclear fuel, UE has both fixed-priced and base-price-with- escalation agreements. It also uses inventories that provide some price hedge to fulfill its Callaway nuclear plant needs for uranium, conversion, enrichment, and fabrication services. There is no fuel reloading scheduled for 2012. UE has price hedges for 88% of the 2010 to 2014 nuclear fuel requirements.

Nuclear fuel market prices remain subject to an unpredictable supply and demand environment. UE has continued to follow a strategy of managing inventory of nuclear fuel as an inherent price hedge. New long-term uranium contracts are almost exclusively market-price-related with an escalating price floor. New long-term enrichment contracts usually have some market-price-related component. UE expects to enter into additional contracts from time to time in order to supply nuclear fuel during the expected life of the Callaway nuclear plant, at prices which cannot now be accurately predicted. Unlike the electricity and natural gas markets, nuclear fuel markets have limited financial instruments available for price hedging, so most hedging is done through inventories and forward contracts, if they are available.

See Note 9 - Commitments and Contingencies under Part I, Item 1 of this report for additional information regarding the long-term commitments for the procurement of coal, natural gas, and nuclear fuel.

Fair Value of Contracts

Most of our commodity contracts that meet the definition of derivatives qualify for treatment as NPNS. We use derivatives principally to manage the risk of changes in market prices for natural gas, coal, diesel, electricity, uranium, and emission allowances. The following table presents the favorable (unfavorable) changes in the fair value of all derivative contracts marked-to-market during the three and six months ended June 30, 2010. We use various methods to determine the fair value of our contracts. In accordance with authoritative guidance for fair value hierarchy levels, our sources used to determine the fair value of these contracts were active quotes (Level 1), inputs corroborated by market data (Level 2), and other modeling and valuation methods that are not corroborated by market data (Level 3). All of these contracts have maturities of less than five years. See Note 7 - Fair Value Measurements under Part I, Item 1, of this report for additional information regarding the methods used to determine the fair value of these contracts.

Three Months Ameren(a) UE CIPS Genco CILCO IP
Fair value of contracts at beginning of period, net $(55) $14 $(218) $19 $(130) $(352)
Contracts realized or otherwise settled during the period (3) - 16 (2) 8 24
Changes in fair values attributable to changes in valuation technique and assumptions - - - - - -
Fair value of new contracts entered into during the period 12 (2) 7 (2) 3 10
Other changes in fair value (25) (18) 32 (3) 16 50
Fair value of contracts outstanding at end of period, net $(71) $(6) $(163) $12 $(103) $(268)
Six Months
Fair value of contracts at beginning of period, net $17 $16 $(155) $21 $(75) $(247)
Contracts realized or otherwise settled during the period - 1 28 (3) 14 45
Changes in fair values attributable to changes in valuation technique and assumptions - - - - - -
Fair value of new contracts entered into during the period 17 - 5 - 1 7
Other changes in fair value (105) (23) (41) (6) (43) (73)
Fair value of contracts outstanding at end of period, net $(71) $(6) $(163) $12 $(103) $(268)

(a) Includes amounts for Ameren registrant and nonregistrant subsidiaries and intercompany eliminations.

The following table presents maturities of derivative contracts as of June 30, 2010, based on the hierarchy levels used to determine the fair value of the contracts:

Sources of Fair Value Ameren: Maturity Less than 1 Year Maturity 1-3 Years Maturity 4-5 Years Maturity in Excess of 5 Years Total Fair Value
Level 1 $(8) $(9) $(1) $- $(18)
Level 2(a) 6 - - - 6
Level 3(b) (28) (21) (10) - (59)
Total $(30) $(30) $(11) $- $(71)
UE:
Level 1 $(4) $(3) $(2) $- $(9)
Level 2(a) 1 - - - 1
Level 3(b) 4 - (2) - 2
Total $1 $(3) $(4) $- $(6)
CIPS:
Level 1 $(1) $- $- $- $(1)
Level 2(a) - - - - -
Level 3(b) (70) (90) (2) - (162)
Total $(71) $(90) $(2) $- $(163)
Genco:
Level 1 $(1) $- $- $- $(1)
Level 2(a) - - - - -
Level 3(b) 8 5 - - 13
Total $7 $5 $- $- $12
CILCO:
Level 1 $(1) $(1) $- $- $(2)
Level 2(a) - - - - -
Level 3(b) (44) (54) (3) - (101)
Total $(45) $(55) $(3) $- $(103)
IP:
Level 1 $(2) $(2) $- $- $(4)
Level 2(a) - - - - -
Level 3(b) (110) (149) (5) - (264)
Total $(112) $(151) $(5) $- $(268)

(a) Principally fixed-price vs. floating over-the-counter power swaps, power forwards, and fixed-price vs. floating over-the-counter natural gas swaps.

(b) Principally power forward contract values based on a Black-Scholes model that includes information from external sources and our estimates. Level 3 also includes option contract values based on our estimates.

Controls and procedures

As filed, 1,387 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

(a) Evaluation of Disclosure Controls and Procedures

As of June 30, 2010, evaluations were performed under the supervision and with the participation of management, including the principal executive officer and principal financial officer of each of the Ameren Companies, of the effectiveness of the design and operation of such registrant’s disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) of the Exchange Act). Based upon those evaluations, the principal executive officer and principal financial officer of each of the Ameren Companies concluded that such disclosure controls and procedures are effective to provide assurance that information required to be disclosed in such registrant’s reports filed or submitted under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms and such information is accumulated and communicated to its management, including its principal executive and principal financial officers, to allow timely decisions regarding required disclosure.

(b) Change in Internal Controls

There has been no change in any of the Ameren Companies’ internal control over financial reporting during their most recent fiscal quarter that has materially affected, or is reasonably likely to materially affect, each of their internal control over financial reporting.

Source: SEC EDGAR, the filing index for accession 0001193125-10-183197. Last ingested by Listed: Nov 24, 2026, 22:58 ET. Listed shows no prices and gives no investment advice.