KBR, Inc.: Form 10-Q for the period ended Sep 30, 2015
Filed with the SEC on Nov 2, 2015 and accepted by EDGAR at Oct 30, 2015, 18:02 ET.
Management's discussion and analysis
As filed, 57,766 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
Introduction
The purpose of management’s discussion and analysis (“MD&A”) is to disclose material changes in our financial condition since the most recent fiscal year-end and results of operations during the current fiscal period as compared to the corresponding period of the preceding fiscal year. The MD&A should be read in conjunction with the condensed consolidated financial statements and accompanying notes and our 2014 Annual Report on Form 10-K.
Executive Overview
Business Reorganization
Following the completion of our strategic review, in December 2014, we reorganized our business into three segments, Technology & Consulting ("T&C"), Engineering & Construction ("E&C") and Government Services ("GS"), in order to focus on core strengths in global hydrocarbons and international government services. Our corporate expenses and other operations that do not individually meet the criteria for group presentation continue to be reported in our Other business segment, while operations we intend to sell or exit upon completion of our existing contracts are presented separately in the Non-strategic Business segment. Each business segment excluding “Other” reflects a reportable segment led by a separate business segment president who reports directly to our chief operating decision maker ("CODM"). We have revised our business segment reporting to reflect our current management approach and recast prior periods to conform to the current business segment presentation. See additional information on our business segments in Note 2 to our condensed consolidated financial statements.
Business Environment
Demand for our services depends primarily on the level of capital expenditure in our market sectors, which is driven generally by global and regional economic growth (primarily GDP growth) and more specifically by the demand for energy and derivative products and government services. While the decline in oil prices is having a near term adverse impact on the global hydrocarbons industry, we continue to see long-term growth in energy projects such as low cost production, shallow water, onshore production, subsea tiebacks and brownfields revamping. Low energy prices reflected in the current oil price provide opportunities in new brownfield liquefied natural gas ("LNG") and new petrochemicals, chemicals and fertilizer markets. We believe KBR has a balanced portfolio of upstream, midstream and downstream projects and recurring revenues in outsourced government services, which we believe provide us with less exposure to the oil price declines than some of our peers.
We expect LNG demand to grow annually mainly in Asia and demand in Europe to rebound. We expect global capacity coming online in the next 15 years to translate to the letting of two new LNG plants per year and we believe growth regions include the United States ("U.S.") Gulf Coast and the Asia-Pacific region, Canada and East Africa.
Three months ended September 30, 2015 compared to the three months ended September 30, 2014
Overview of Financial Results
Our results for the quarter ended September 30, 2015 were significantly improved from the third quarter of 2014 driven by strong operational performance, including a positive earnings contribution from power projects in our Non-strategic Business segment versus more than $30 million in charges taken in the third quarter of 2014. Continued steady progress towards the achievement of our strategic objectives also contributed to our results, including reduced overhead costs and de-risking of the business through the completion or near completion of loss projects.
Our E&C business segment, where we execute large engineering, procurement and construction ("EPC") projects, generated revenues of $828 million and gross profit of $48 million through continued operational performance and successful execution on two mega-LNG projects in Australia. This business segment continues to actively pursue opportunities for LNG, floating LNG ("FLNG"), oil & gas, ammonia and chemicals projects and expects increased growth in services contracts executed by our recently completed Brown & Root Industrial Services joint venture with Bernhard Capital Partners ("BCP"). We have substantially completed work on the seven Canadian pipe fabrication and module assembly projects. One of these projects is a master services-type agreement that provides our client with the right, but not the obligation, to place new pipe fabrication and module assembly orders until 2017. We have not received any new orders under this agreement since 2013. The majority of our Canadian pipe fabrication and module assembly business has now been contributed to a separate third party pipe fabrication entity as part of our minority ownership in that entity.
During the quarter, despite being challenged by reduced proprietary equipment sales and professional consulting services, our T&C business segment’s gross profits were relatively equal to the prior year.
Our GS business segment provides support services to the United Kingdom (“U.K.”) Ministry of Defence (“MoD”) related to maintenance of military facilities under multi-year contracts. Our business in support of the U.S. military continues to experience increased activity on the LogCAP IV and other international operating base contracts. However, this business segment continues to be adversely impacted by legal fees associated with LogCAP III and Restore Iraqi Oil (“RIO”) legacy projects executed during the Iraq wars. The GS business segment is well placed in sole source negotiations on two large-scale contracts for the U.K. MoD.
Our Non-strategic Business segment was created as a part of our restructuring initiative and is primarily composed of three EPC power projects, two of which are currently in loss positions. The execution and close out of projects within the Non-strategic segment is the responsibility of our E&C management team. During the third quarter of 2015, one project was completed, while the remaining two projects are scheduled for completion in 2016 and 2017, respectively. During the quarter ended September 30, 2015, this business segment benefited from improved performance and a favorable settlement with a major vendor.
Subsequent Event
Subsequent to September 30, 2015, we reached a definitive agreement for the sale of our U.S. Infrastructure business within the Non-strategic Business segment.
The information below is an analysis of our consolidated results for the three months ended September 30, 2015. See Results of Operations by Business Segment below for additional information describing the performance of each of our reportable segments.
Dollars in millions
| Revenues | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Revenues | $1,199 | $1,657 | $(458) | (28)% |
The decrease in consolidated revenues was primarily due to reduced activity within our E&C business segment from the substantial completion one of the major LNG projects in Australia. The decrease in revenues was also attributable to the completion or substantial completion of several projects in the U.S., Middle East and Canada. These decreases were partially offset by increased work or ramp up on chemicals and ammonia projects in the U.S. and a new oil and gas project in Europe. Our revenues were also impacted by activity within our Non-strategic Business segment, including the elimination of revenues related to the Building Group, which we sold at the end of the second quarter of 2015, and the continued wind-down on two power projects that are nearing completion. In addition, the decline in both proprietary equipment sales and awards of new consulting contracts from upstream oil related projects within our T&C business segment contributed to the decrease.
Dollars in millions
| Gross Profit | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Gross profit | $87 | $30 | $57 | 190% |
The increase in consolidated gross profit was primarily due to the non-recurrence of losses and charges in the third quarter of 2015 that were recognized during the corresponding period of 2014 on projects within our E&C and Non-strategic Business segments. Gross profit was also impacted by the recognition of favorable settlements in the third quarter of 2015 within our Non-strategic Business segment, ongoing execution on base operations and other contracts within our GS business segment and reduced overhead spending within our E&C business segment. This increase was partially offset by the non-recurrence of favorable settlements in the third quarter of 2015 related to dispute resolution activities in our GS segment recognized in the corresponding period of 2014 and reduced activity on the major LNG project discussed above.
Dollars in millions
| Equity in Earnings of Unconsolidated Affiliates | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Equity in earnings of unconsolidated affiliates | $35 | $38 | $(3) | (8)% |
The decrease in equity in earnings of unconsolidated affiliates was due to scheduled maintenance spending during the third quarter on a joint venture in our GS business segment that occurred in the fourth quarter of 2014.
Dollars in millions
| General and Administrative Expenses | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| General and administrative expenses | $(38) | $(58) | $(20) | (34)% |
The decrease in general and administrative expenses was primarily due to lower information technology support costs resulting from the cancellation of our enterprise resource planning ("ERP") implementation project in the fourth quarter of 2014, reduced overhead costs resulting from headcount reductions and other cost savings initiatives implemented at the end of 2014 and during 2015. General and administrative expenses in the third quarter of 2015 and 2014 included $27 million and $43 million, respectively, related to corporate activities and $11 million and $15 million, respectively, related to the business segments.
Dollars in millions
| Asset Impairment and Restructuring Charges | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Asset impairment and restructuring charges | $(15) | $— | $15 | 100% |
Asset impairment and restructuring charges in 2015 are primarily due to costs associated with the termination of leases related to our Canadian fabrication yard and partial impairment of our Canadian ERP assets as a result of the investment in the Brown & Root Industrial Services joint venture and EPIC Piping LLC within our E&C business segment. See Note 7 to our condensed consolidated financial statements for information related to these new investments.
Dollars in millions
| Gain on Disposition of Assets | Three Months Ended June 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Gain on disposition of assets | $6 | $— | $6 | 100% |
The gain on disposition of assets primarily reflects the gain recognized on the deconsolidation of our Industrial Services business in our E&C business segment for an interest in the Brown & Root Industrial Services joint venture.
Dollars in millions
| Non-operating Income | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Non-operating income | $3 | $34 | $(31) | (91)% |
Non-operating income includes interest income, interest expense, foreign exchange gains and losses and other non-operating income or expense items. The decrease in non-operating income was primarily due to the gain on a negotiated settlement with our former parent as well as the reversal of associated interest under a tax sharing agreement recognized in 2014 that did not recur in 2015.
Dollars in millions
| Benefit (provision) for Income Taxes | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Income before benefit (provision) for income taxes | $78 | $44 | $34 | 77% |
| Benefit (provision) for income taxes | $(19) | $1 | $(20) | n/m |
n/m - not meaningful
Our provision for income taxes for the quarter ended September 30, 2015 reflects a 24% tax rate. The benefit for income taxes for the quarter ended September 30, 2014 reflects lower income. Additionally, tax expense for the three months ending September 30, 2014 included a $5 million benefit from the settlement of a previously unrecognized tax benefit along with other discrete tax benefits. See an explanation of our effective tax rates for the quarter ended September 30, 2015 in Note 10 to our condensed consolidated financial statements.
Dollars in millions
| Net Income Attributable to Noncontrolling Interests | Three Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Net income attributable to noncontrolling interests | $(4) | $(15) | $(11) | (73)% |
The decrease in net income attributable to noncontrolling interests was primarily due to additional fees recognized on approved man hours on an LNG project joint venture in Australia in our E&C business segment in 2014 that did not recur in 2015.
Results of Operations by Business Segment
We analyze the financial results for each of our five business segments. The business segments presented are consistent with our reportable segments discussed in Note 2 to our condensed consolidated financial statements.
Dollars in millions
| Revenues | Three Months Ended September 30, 2015 | 2014 |
|---|---|---|
| Technology & Consulting | $79 | $94 |
| Engineering & Construction | 828 | 1,196 |
| Government Services | 176 | 178 |
| Other | — | — |
| Subtotal | 1,083 | 1,468 |
| Non-strategic Business | 116 | 189 |
| Total | $1,199 | $1,657 |
| Gross profit (loss) | ||
| Technology & Consulting | $17 | $18 |
| Engineering & Construction | 48 | 46 |
| Government Services | 8 | 24 |
| Other | — | — |
| Subtotal | 73 | 88 |
| Non-strategic Business | 14 | (58) |
| Total | $87 | $30 |
| Equity in earnings of unconsolidated affiliates | ||
| Technology & Consulting | $— | $— |
| Engineering & Construction | 26 | 26 |
| Government Services | 9 | 12 |
| Other | — | — |
| Subtotal | 35 | 38 |
| Non-strategic Business | — | — |
| Total | $35 | $38 |
| Total general and administrative expenses | $(38) | $(58) |
| Asset impairment and restructuring charges | $(15) | $— |
| Gain on disposition of assets | $6 | $— |
| Total operating income | $75 | $10 |
40
Technology & Consulting
T&C revenues decreased by $15 million, or 16%, to $79 million in the third quarter of 2015 compared to $94 million in the third quarter of 2014 due to a decrease in proprietary equipment sales and other technology and consulting projects primarily for upstream oil projects.
T&C gross profit decreased by $1 million, or 6%, to $17 million in the third quarter of 2015 compared to $18 million in the third quarter of 2014. This decrease was primarily driven by the reduction in activity discussed above.
Engineering & Construction
E&C revenue decreased by $368 million, or 31%, to $828 million in the third quarter of 2015 compared to $1.2 billion in the third quarter of 2014. This decrease was primarily due to reduced activity on one of the major LNG projects in Australia, a petrochemical project in the U.S., an oil and gas project in Europe and a chemical complex in the Middle East. In addition, the substantial completion of construction, EPC, petrochemical, maintenance and pipe fabrication and module assembly projects in the U.S. and Canada contributed to the overall decrease. This was partially offset by new ammonia and chemicals projects in the U.S. and a new oil and gas project in Europe.
E&C gross profit increased by $2 million, or 4% to $48 million in the third quarter of 2015 compared to $46 million in the third quarter of 2014. This increase was primarily due to the non-recurrence of losses in the third quarter of 2015 recognized on several projects in the U.S. and Canada during the corresponding period of 2014 and reduced spending in the U.S., a reduction in work on a major LNG projects in Australia and increased losses on a petrochemicals project in the third quarter of 2015.
E&C equity in earnings of unconsolidated affiliates remained flat in the third quarter of 2015 compared to the third quarter of 2014, at $26 million and was impacted improved utilization of the marine vessels related to our Mexican offshore maintenance joint venture which were out of service in the same period of 2014 as well as increased earnings on other joint ventures. These increases were offset by reduced earnings on an LNG project joint venture in Australia due to a decline in work.
Government Services
GS revenues decreased by $2 million, or 1%, to $176 million in the third quarter of 2015 compared to $178 million in the third quarter of 2014. This decrease was driven primarily by the reduction in support services due to the scale-back in military operations and reduction in troop numbers on U.K. MoD and North Atlantic Treaty Organization ("NATO") contracts in Afghanistan and the completion of several projects in early 2015. These were partially offset by increased activity on base support and other contracts with the U.S. government.
GS gross profit decreased by $16 million, or 67%, to $8 million in the third quarter of 2015 compared to $24 million in the third quarter of 2014. The decrease in gross profit was attributable to the non-recurrence of favorable settlements in the third quarter of 2015 related to dispute resolution activities compared to the corresponding period in 2014.
GS equity in earnings of unconsolidated affiliates decreased by $3 million, or 25%, to $9 million in the third quarter of 2015 compared to $12 million in the third quarter of 2014 primarily due to regularly scheduled maintenance activity related to joint venture project assets that occurred in the third quarter of 2015 as compared to the fourth quarter of 2014.
Non-strategic Business
Non-strategic Business revenue decreased by $73 million, or 39%, to $116 million in the third quarter of 2015 compared to $189 million in the third quarter of 2014. This decrease was due to the elimination of revenues resulting from the sale of the Building Group in the second quarter of 2015 and the near completion of two power projects and North American construction projects, partially offset by increased activity on a power project in 2015.
Non-strategic Business gross profit increased by $72 million to a profit of $14 million in the third quarter of 2015 compared to a loss of $58 million in the third quarter of 2014. This increase was due to the non-recurrence of charges recognized on a power project in the third quarter of 2014, improved performance and favorable settlements with a vendor in the third quarter of 2015 and overhead savings resulting from the sale of Building Group in the second quarter of 2015. This increase was partially offset by a small loss provision recognized on an infrastructure project in the third quarter of 2015.
Changes in Estimates
Information relating to our changes in estimates is discussed in Note 2 to our condensed consolidated financial statements.
Nine months ended September 30, 2015 compared to the nine months ended September 30, 2014
Overview of Financial Results
Our earnings for the nine months ended September 30, 2015 improved from the nine months ended September 30, 2014 driven by our E&C business segment which generated revenues of $2.8 billion and gross profit of $155 million during the nine months ended September 30, 2015. See discussion in the Overview of Financial Results for the quarter ended September 30, 2015 for information related to our Canadian pipe fabrication and module assembly projects.
Our T&C business segment results benefited from higher profitability on the mix of projects and a larger number of project milestones achieved during the nine month period.
Our GS business segment continues to be impacted by a reduction in troop numbers and other operations for the U.K. MoD and the U.S. government; however, we are experiencing increased activity in base operations with the U.S. government and other support contracts. Costs from the close out of contracts under the LogCAP III and RIO projects continue to impact our results.
Our Non-strategic Business segment continues to make progress toward completing the three EPC power projects. The sale of Building Group, successful project execution and the non-recurrence of losses and charges that we recognized in the corresponding period of 2014 positively impacted our results.
Prior Period Adjustment
During the second quarter of 2015, we corrected a cumulative error related to transactions between the unconsolidated affiliates associated with our Mexican offshore maintenance joint venture within our E&C business segment. The cumulative error occurred throughout the period beginning in 2007 and through the first quarter of 2015 and resulted in a $15 million favorable impact to "equity in earnings of unconsolidated affiliates" on our condensed consolidated statements of operations during the second quarter. We evaluated the cumulative error on both a quantitative and qualitative basis and determined that the cumulative impact of the error did not affect the trend of net income, cash flows or liquidity and therefore did not have a material impact to previously issued financial statements. Additionally, we do not expect our consolidated financial statements for the current annual period to be materially impacted by the error correction.
The information below is an analysis of our consolidated results for the nine months ended September 30, 2015. See Results of Operations by Business Segment below for additional information describing the performance of each of our reportable segments.
Dollars in millions
| Revenues | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Revenues | $4,016 | $4,949 | $(933) | (19)% |
The decrease in consolidated revenues was primarily driven by lower activity in the E&C business segment due to the completion or substantial completion of several projects including construction projects in the U.S. and Canada, the Canadian pipe fabrication and maintenance projects, two LNG/Gas to Liquids ("GTL") projects in Africa and a petrochemical project in the U.S. The decrease was also attributable to lower activity on a major LNG project in Australia, an offshore project in Europe and a petrochemical project in the U.S. as these projects continue to wind down. The elimination of revenues related to the second quarter 2015 sale of the Building Group and lower activity on two power projects within our Non-strategic Business segment also contributed to the decrease. In addition, the decrease in revenues was due to lower overall activity associated with our GS business segment's support and logistics contracts for the U.K. government in Afghanistan as well as the decline in both proprietary equipment sales and awards of new consulting contracts within our T&C business segment. These were offset by higher activity on a chemical complex in the Middle East as well as new ammonia and oil and gas projects in the U.S. and Europe, respectively within our E&C business segment.
Dollars in millions
| Gross Profit | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Gross profit | $231 | $97 | $134 | 138% |
The increase in consolidated gross profit was primarily due to the non-recurrence in the third quarter of 2015 of charges recognized in 2014 on certain projects within our Non-strategic Business segment as well as favorable settlements in 2015 compared to losses taken in 2014 related to our Canadian pipe fabrication and module assembly projects within our E&C business segment. Lower overhead costs resulting from reduced headcount and other cost saving initiatives following restructuring efforts beginning at the end of 2014 and during 2015 also contributed to the increase. The increase was partially offset by the impact of reduced activity on a major LNG project in Australia, the favorable settlement of certain claims on this project in 2014 which did not recur in the 2015 both within our E&C business segment as well as lower activity on the support and logistics contracts for the U.K. government in Afghanistan within our GS business segment.
Dollars in millions
| Equity in Earnings of Unconsolidated Affiliates | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Equity in earnings of unconsolidated affiliates | $123 | $118 | $5 | 4% |
The increase in equity in earnings of unconsolidated affiliates was primarily due to activities within our E&C business segment, including improved utilization of marine vessels in our Mexican offshore maintenance joint venture compared to 2014, and the $15 million adjustment in the second quarter of 2015 as well as increased progress on an LNG project joint venture. This increase was partially offset by the impact of interruptions in the supply of natural gas feedstock to our E&C business segment's ammonia plant joint venture in Egypt as well as the non-recurrence of insurance recovery and reduced costs in 2015 recognized in the corresponding period of 2014 on a joint venture for a U.K. MoD project within our GS business segment.
Dollars in millions
| General and Administrative Expenses | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| General and administrative expenses | $(119) | $(178) | $(59) | (33)% |
The decrease in general and administrative expenses was primarily due to lower information technology support costs resulting from the cancellation of our ERP implementation project in the fourth quarter of 2014, reduced overhead costs resulting from headcount reductions and other cost savings initiatives implemented at the end of 2014 and during 2015. General and administrative expenses in the nine months ended September 30, 2015 and 2014 included $87 million and $130 million, respectively, related to corporate activities and $32 million and $48 million, respectively, related to the business segments.
Dollars in millions
| Asset Impairment and Restructuring Charges | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Asset impairment and restructuring charges | $(34) | $— | $34 | 100% |
Asset impairment and restructuring charges are the result of additional severance costs within our E&C and Non-strategic Business segments related to the workforce reduction efforts during 2015 in addition to those recognized in the last quarter of 2014. Included in this amount is $20 million related to early termination of leases, impairment of associated leasehold improvements and other long-lived assets within our E&C and Other business segments.
Dollars in millions
| Gain on Disposition of Assets | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Gain on disposition of assets | $34 | $8 | $26 | n/m |
Gain on disposition of assets reflects the $28 million gain recognized in the second quarter of 2015, net a $1 million adjustment in the third quarter of 2015, on the sale of the Building Group subsidiary within our Non-strategic Business segment. In addition we recognized a $7 million gain on the deconsolidation of our Industrial Services business in our E&C business segment for an interest in the Brown & Root Industrial Services joint venture in the third quarter of 2015.
Dollars in millions
| Non-operating Income | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Non-operating income | $4 | $18 | $(14) | (78)% |
Non-operating income includes interest income, interest expense, foreign exchange gains and losses and other non-operating income or expense items. The decrease in income was primarily due to a gain on a negotiated settlement with our former parent as well as the reversal of associated interest pursuant to the terms of a tax sharing agreement in 2014 that did not recur in 2015. Also contributing to operating income were foreign exchange gains in 2015 due to the strengthening of the U.S. dollar against the majority of our foreign currencies compared to losses in 2014.
Dollars in millions
| Provision for Income Taxes | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Income before provision for income taxes | $239 | $63 | $176 | n/m |
| Provision for income taxes | $(61) | $(30) | $31 | 103% |
n/m - not meaningful
Our provision for income taxes for the nine months ended September 30, 2015 reflects a 26% tax rate. The provision for income taxes for nine months ended September 30, 2014 reflects lower income but was offset by an increase in our valuation allowance associated with losses recognized on our Canadian pipe fabrication and assembly projects. See an explanation of our effective tax rates for the nine months ended September 30, 2015 in Note 10 to our condensed consolidated financial statements.
Dollars in millions
| Net Income Attributable to Noncontrolling Interests | Nine Months Ended September 30, 2015 | 2014 | 2015 vs. 2014 $% | |
|---|---|---|---|---|
| Net income attributable to noncontrolling interests | $(17) | $(54) | $(37) | (69)% |
The decrease in net income attributable to noncontrolling interests was primarily due to additional fees recognized on approved man hours on an LNG project joint venture in Australia in our E&C business segment in 2014 that did not recur in 2015.
Results of Operations by Business Segment
We analyze the financial results for each of our five business segments. The business segments presented are consistent with our reportable segments discussed in Note 2 to our condensed consolidated financial statements.
Dollars in millions
| Revenues | Nine Months Ended September 30, 2015 | 2014 |
|---|---|---|
| Technology & Consulting | $231 | $285 |
| Engineering & Construction | 2,758 | 3,546 |
| Government Services | 489 | 527 |
| Other | — | — |
| Subtotal | 3,478 | 4,358 |
| Non-strategic Business | 538 | 591 |
| Total | $4,016 | $4,949 |
| Gross profit (loss) | ||
| Technology & Consulting | $57 | $48 |
| Engineering & Construction | 155 | 108 |
| Government Services | 3 | 28 |
| Other | — | — |
| Subtotal | 215 | 184 |
| Non-strategic Business | 16 | (87) |
| Total | $231 | $97 |
| Equity in earnings of unconsolidated affiliates | ||
| Technology & Consulting | $— | $— |
| Engineering & Construction | 87 | 63 |
| Government Services | 36 | 55 |
| Other | — | — |
| Subtotal | 123 | 118 |
| Non-strategic Business | — | — |
| Total | $123 | $118 |
| Total general and administrative expenses | $(119) | $(178) |
| Asset impairment and restructuring charges | $(34) | $— |
| Gain on disposition of assets | $34 | $8 |
| Total operating income | $235 | $45 |
45
Technology & Consulting
T&C revenues decreased by $54 million, or 19%, to $231 million in the nine months ended September 30, 2015 compared to $285 million in the same period of the prior year due to a decrease in proprietary equipment sales offset partially by an increase related to several petrochemicals, ammonia and refining projects.
T&C gross profit increased by $9 million, or 19%, to $57 million in the nine months ended September 30, 2015 compared to $48 million in the same period of the prior year primarily due to higher profitability on the mix of projects executed, a larger number of license milestones achieved and significant overhead reductions during the nine months ended September 30, 2015.
Engineering & Construction
E&C revenue decreased by $788 million, or 22%, to $2.8 billion in the nine months ended September 30, 2015 compared to $3.5 billion in the nine months ended September 30, 2014. This decrease was primarily due to reduced activity on a major LNG project in Australia, an oil and gas project in Europe and a petrochemical project in the U.S. This decrease was also attributable to lower activity resulting from the substantial completion of construction, EPC, petrochemical, maintenance and pipe fabrication and module assembly projects in the U.S. and Canada as well as LNG/GTL projects in Africa. This decrease was partially offset by increased project management activity on a chemical complex in the Middle East, new ammonia projects in the U.S., a new FLNG project in Africa and a new offshore platform in the Middle East.
E&C gross profit increased by $47 million, or 44%, to $155 million in the nine months ended September 30, 2015 compared to $108 million in the nine months ended September 30, 2014. This increase was due to profits resulting from negotiated settlements on our Canadian pipe fabrication and module assembly projects in the nine months ended September 30, 2015 compared to losses associated with these projects during the same period in 2014. Increased project management activity for a chemical complex in the Middle East as well as cost reductions in divisional overheads achieved during the nine months ended September 30, 2015 also contributed to this improvement. The increase was partially offset by the decline in work on one of the LNG projects in Australia, the net favorable settlement of certain claims on an LNG project in Africa that did not recur in the nine months ended September 30, 2015 as well as reduced activity on a petrochemical project in the U.S.
E&C equity in earnings of unconsolidated affiliates increased by $24 million, or 38%, to $87 million in the nine months ended September 30, 2015 compared to $63 million in the nine months ended September 30, 2014. The increase was due to increased earnings on our offshore maintenance joint venture in Mexico due to improved utilization of vessels, which were in dry dock during the same period of the prior year, and the $15 million adjustment in the second quarter of 2015, as well as increased progress on an LNG project joint venture in Australia. The increase was partially offset by reduced earnings from our ammonia plant joint venture in Egypt due to the limited availability of natural gas feedstock.
Government Services
GS revenues decreased by $38 million, or 7%, to $489 million in the nine months ended September 30, 2015 compared to $527 million in the same period in the prior year. This decrease was driven primarily by the reduction in support services due to the scale-back in military operations and reduction in troop numbers on U.K. MoD and NATO contracts in Afghanistan and the substantial completion of several projects in the first quarter of 2014 and early 2015. This decrease was offset by increased activity from new work or expansion in existing U.S. government contracts as well as the favorable settlement of disputes with the U.S. government on some of our legacy projects.
GS gross profit decreased by $25 million, or 89%, to $3 million in the nine months ended September 30, 2015 compared $28 million in the same period in the prior year. This decrease was primarily driven by the reduction in U.K. MoD support activities, the completion of projects discussed above and the recognition of $13 million in legal fees related to U.S. government legacy contracts during the nine months ended September 30, 2015. This decrease was partially offset by increased activity and favorable settlement with the U.S. government, also discussed above.
GS equity in earnings of unconsolidated affiliates decreased by $19 million, or 35%, to $36 million in the nine months ended September 30, 2015 compared to $55 million in the same period in the prior year. This decrease was driven primarily by insurance recovery and reduced costs on a joint venture for a U.K. MoD project in the prior year as well as regularly scheduled maintenance costs that occurred in the third quarter of 2015 as compared to the fourth quarter of 2014 related to joint venture project assets.
Non-strategic Business
Non-strategic Business revenue decreased by $53 million, or 9%, to $538 million in the nine months ended September 30, 2015 compared to $591 million in the nine months ended September 30, 2014. This decrease was due to the sale of Building Group in the second quarter of 2015 and the near completion of several power and construction projects and was offset by increased activity on power and infrastructure projects that began in the second half of 2014.
Non-strategic Business gross profit increased by $103 million to a profit of $16 million in the nine months ended September 30, 2015 compared to a loss of $87 million in the nine months ended September 30, 2014. This increase was due to the non-recurrence of charges recognized during 2014 on a power project, improved performance and favorable settlements on power projects in the third quarter of 2015 as well as overhead savings resulting from headcount reductions which began in late 2014.
Changes in Estimates
Information relating to our changes in estimates is discussed in Note 2 to our condensed consolidated financial statements.
Backlog of Unfilled Orders
Backlog generally represents the dollar amount of revenues we expect to realize in the future as a result of performing work on contracts and our pro-rata share of work to be performed by unconsolidated joint ventures. We generally include total expected revenues in backlog when a contract is awarded under a legally binding commitment. In many instances, arrangements included in backlog are complex, nonrepetitive and may fluctuate depending on estimated revenues and contract duration. Where contract duration is indefinite and clients can terminate for convenience at any time without having to compensate us for periods beyond the date of termination, projects included in backlog are limited to the estimated amount of expected revenues within the following twelve months. Certain contracts provide maximum dollar limits, with actual authorization to perform work under the contract agreed upon on a periodic basis with the customer. In these arrangements, only the amounts authorized are included in backlog. For projects where we act solely in a project management capacity, we only include the value of our services of each project in backlog. Previously, for long term contracts associated with the U.K. government's privately financed initiatives or projects (“PFIs”), the amount included in backlog was limited to five years. Effective in the second quarter of 2015, we modified our backlog policy and now record the estimated value of all work forecast to be performed under the PFI contracts. The reason for the change is that under these PFI contracts, the client is obligated to pay us certain amounts spanning periods beyond five years even if the client terminates the contracts for convenience. Also, recording the full value of PFIs into backlog is a relatively common industry practice. This change only relates to backlog of unfilled orders and does not alter our longstanding policies for revenue recognition; therefore, it has no impact on our financial statements. The $5 billion included in the change in policy column below represents our estimate of revenues related to payment obligations for periods beyond five years.
We have included in the table below our proportionate share of unconsolidated joint ventures' estimated revenues. However, because these projects are accounted for under the equity method, only our share of future earnings from these projects will be recorded in our results of operations. Our backlog for projects related to unconsolidated joint ventures totaled $9.1 billion, including the PFI change discussed above, at September 30, 2015 and $4.3 billion at December 31, 2014. We consolidate joint ventures which are majority-owned and controlled or are variable interest entities ("VIEs") in which we are the primary beneficiary. Our backlog included in the table below for projects related to consolidated joint ventures with noncontrolling interests includes 100% of the backlog associated with those joint ventures and totaled $423 million at September 30, 2015 and $928 million at December 31, 2014. Backlog attributable to unfunded government orders was none at September 30, 2015 and $36 million at December 31, 2014. The following table summarizes our backlog by business segment.
Dollars in millions
| December 31, 2014 | New Awards | Change in Policy (c) | Changes in scope on existing contracts (a) 2015 | Net Workoff (b) | September 30, | |
|---|---|---|---|---|---|---|
| Technology & Consulting | $400 | $231 | — | $23 | $(231) | $423 |
| Engineering & Construction | 7,788 | 1,335 | — | (537) | (2,846) | 5,740 |
| Government Services | 1,763 | 124 | 5,358 | 63 | (525) | 6,783 |
| Subtotal | 9,951 | 1,690 | 5,358 | (451) | (3,602) | 12,946 |
| Non-strategic Business | 908 | 49 | — | (66) | (537) | 354 |
| Total backlog | $10,859 | $1,739 | $5,358 | $(517) | $(4,139) | $13,300 |
(a) In addition to changes in scope, these amounts reflect the elimination of our proportionate share of non-partner costs related to our unconsolidated joint ventures and adjustments for changes in foreign exchange rates.
(b) These amounts include the workoff of our projects as well as our proportionate share of the workoff of our unconsolidated joint ventures' projects.
(c) Change in policy was implemented in the second quarter of 2015.
We estimate that as of September 30, 2015, 35% of our backlog will be executed within one year. As of September 30, 2015, 67% of our backlog was attributable to fixed-price contracts, including 47% related to our PFI contracts, and 33% of our backlog was attributable to cost-reimbursable contracts. For contracts that contain both fixed-price and cost-reimbursable components, we classify the individual components as either fixed-price or cost-reimbursable according to the composition of the contract; however, for smaller contracts, we characterize the entire contract based on the predominant component.
Liquidity and Capital Resources
Cash and equivalents totaled $768 million at September 30, 2015 and $970 million at December 31, 2014 and consisted of the following:
Dollars in millions
| September 30, 2015 | December 31, 2014 | |
|---|---|---|
| Domestic U.S. cash | $304 | $200 |
| International cash | 395 | 690 |
| Joint venture cash | 69 | 80 |
| Total | $768 | $970 |
Domestic cash relates to cash balances held by U.S. entities and is largely used to support obligations of those businesses as well as general corporate needs such as the payment of dividends to shareholders and potential repurchases of our outstanding common stock.
The international cash balances may be available for general corporate purposes but are subject to local restrictions, such as capital adequacy requirements and local obligations, such as maintaining sufficient cash balances to support our underfunded U.K. pension plan and other obligations incurred in the normal course of business by those foreign entities. Repatriated foreign cash may become subject to U.S. income taxes. In December 2014, we implemented a foreign cash repatriation strategy for which we have provided cumulative income taxes on certain foreign earnings.
Joint venture cash balances reflect the amounts held by joint venture entities that we consolidate for financial reporting purposes. Such amounts are limited to joint venture activities and are not readily available for general corporate purposes but portions of such amounts may become available to us in the future should there be distribution of dividends to the joint venture partners. We expect that the majority of the joint venture cash balances will be utilized for the corresponding joint venture projects.
Cash generated from operations is our primary source of operating liquidity. Our cash balances are held in numerous locations throughout the world. We believe that existing cash balances and internally generated cash flows are sufficient to support our day-to-day domestic and foreign business operations for at least the next 12 months.
Our operating cash flow can vary significantly from year to year and is affected by the mix, terms and percentage of completion of our engineering and construction projects. We sometimes receive cash through billings to our customers on our larger engineering and construction projects and those of our consolidated joint ventures in advance of incurring the related costs.
In other projects our net investment in the project costs may be greater than available project cash and we may utilize other cash on hand or availability under our Credit Agreement to satisfy any periodic operating cash requirements.
Engineering and construction projects generally require us to provide credit support for our performance obligations to our customers in the form of letters of credit, surety bonds or guarantees. Our ability to obtain new project awards in the future may be dependent on our ability to maintain or increase our letter of credit and surety bonding capacity, which may be further dependent on the timely release of existing letters of credit and surety bonds. As the need for credit support arises, letters of credit will be issued under our Credit Agreement or arranged with our banks on a bilateral, syndicated or other basis. We believe we have adequate letter of credit capacity under our existing Credit Agreement and bilateral lines, as well as adequate surety bond capacity under our existing lines to support our operations and current backlog for the next 12 months.
As of September 30, 2015, substantially all of our excess cash was held in commercial bank time deposits or interest bearing short-term investment accounts with the primary objectives of preserving capital and maintaining liquidity.
Dollars in millions
| Cash flows activities summary | Nine Months Ended September 30, 2015 | 2014 |
|---|---|---|
| Cash flows provided by (used in) operating activities | $(85) | $178 |
| Cash flows provided by (used in) investing activities | 48 | (37) |
| Cash flows used in financing activities | (128) | (178) |
| Effect of exchange rate changes on cash | (37) | (21) |
| Decrease in cash and equivalents | $(202) | $(58) |
Operating activities. Cash used in operations totaled $85 million in the first nine months in 2015 and resulted from changes in our working capital accounts, which includes $100 million to fund loss projects, partially offset by distributions of earnings received from our unconsolidated affiliates of $84 million. In addition, we used $40 million for net settlement of foreign exchange derivative hedging contracts and contributed $37 million to our pension funds.
Cash provided by operations totaled $178 million in the first nine months in 2014 and was primarily attributable to fluctuations in our working capital accounts as well as distributions of earnings received from our unconsolidated affiliates of $212 million. This increase in cash was partially offset by contributions of $37 million to our pension funds.
Investing activities. Cash provided by investing activities totaled $48 million in the first nine months in 2015 and was primarily due to $71 million in proceeds from the sale of assets or investments. This increase was partially offset by a payment of $15 million to acquire an investment in a partnership.
Cash used in investing activities totaled $37 million in the first nine months in 2014 and was primarily due to purchases of equipment associated with information technology projects which have now largely been stopped.
Financing activities. Cash used in financing activities totaled $128 million in the first nine months in 2015 and included $40 million for our purchase of the noncontrolling interest in a joint venture, $22 million for the purchase of treasury stock, $35 million for dividend payments to common shareholders, $21 million for distributions to noncontrolling interests, $7 million for principal payments on short-term and long-term borrowings consisting primarily of nonrecourse debt of our Fasttrax VIE and $4 million for other financing expenditures.
Cash used in financing activities totaled $178 million in the first nine months in 2014 and included $102 million for the purchase of treasury stock, $35 million for dividend payments to common shareholders, $49 million for distributions to noncontrolling interests and $7 million for principal payments on short-term and long-term borrowings consisting primarily of nonrecourse debt of our Fasttrax VIE. The uses of cash were partially offset by $10 million of investments from noncontrolling interests and $4 million of proceeds from the exercise of stock options.
Future sources of cash. Future sources of cash include cash flows from operations, cash derived from working capital management, sales of non-strategic and other businesses and cash borrowings under our Credit Agreement as well as potential litigation proceeds.
Future uses of cash. Future uses of cash will primarily relate to working capital requirements, capital expenditures, dividends, share repurchases and strategic investments. In addition, we will use cash to fund pension obligations, payments under operating leases and various other obligations, including potential litigation payments, as they arise. Our capital expenditures will be focused primarily on facilities and equipment to support our businesses.
Other factors potentially affecting liquidity
Power project losses. Our reserve for estimated losses on uncompleted contracts included in "other current liabilities" on our condensed consolidated balance sheets consists of $41 million primarily related to a power project at September 30, 2015. These accrued losses will result in future cash expenditures in excess of customer receipts. Based on current contracts and work authorizations, we anticipate completion of this project in 2017. See Note 2 to our condensed consolidated financial statements for more information related to changes in estimates.
Credit Agreement
On September 25, 2015, we entered into a new $1 billion, unsecured revolving credit agreement (the “Credit Agreement”) with a syndicate of banks replacing the previous agreement which was scheduled to mature in December 2016. The Credit Agreement is guaranteed by certain of the Company's domestic subsidiaries, matures in September 2020 and is available for cash borrowings and the issuance of letters of credit related to general corporate needs. Subject to certain conditions, we may request (i) that the aggregate commitments under the Credit Agreement be increased by up to an additional $500 million, and (ii) that maturity of the Credit Agreement be extended by two additional one-year terms.
Amounts drawn under the Credit Agreement will bear interest at variable rates, per annum, based either on (i) the London interbank offered rate (“LIBOR”) plus an applicable margin of 1.375% to 1.75%, or (ii) a base rate plus an applicable margin of 0.375% to 0.75%, with the base rate equal to the highest of (a) reference bank’s publicly announced base rate, (b) the Federal Funds Rate plus 0.5%, or (c) LIBOR plus 1%. The amount of the applicable margin to be applied will be determined by the Company’s ratio of consolidated debt to consolidated EBITDA for the prior four fiscal quarters, except for the period ended September 30, 2015, for which the prior three fiscal quarters are utilized, as defined in the Credit Agreement. The Credit Agreement provides for fees on letters of credit issued under the Credit Agreement at a rate equal to the applicable margin for LIBOR-based loans, except for performance letters of credit, which are priced at 50% of such applicable margin. KBR pays an annual issuance fee of 0.125% of the face amount of a letter of credit and pays a commitment fee of 0.225% to 0.25%, per annum, on any unused portion of the commitment under the Credit Agreement based on the Company's consolidated leverage ratio. As of September 30, 2015, there were $130 million in letters of credit and no cash borrowings outstanding.
The Credit Agreement contains customary covenants, as defined in the Credit Agreement, which include financial covenants requiring maintenance of a ratio of consolidated debt to consolidated EBITDA not greater than 3.5 to 1 and a minimum consolidated net worth of $1.2 billion plus 50% of consolidated net income for each quarter beginning September 30, 2015 and 100% of any increase in shareholders’ equity attributable to the sale of equity interests. As of September 30, 2015, we were in compliance with our financial covenants.
The Credit Agreement contains a number of other covenants restricting, among other things, our ability to incur additional liens and indebtedness, enter into asset sales, repurchase our equity shares and make certain types of investments. Our subsidiaries are restricted from incurring indebtedness, except if such indebtedness relates to purchase money obligations, capitalized leases, refinancing or renewals secured by liens upon or in property acquired, constructed or improved in an aggregate principal amount not to exceed $200 million outstanding at any time. Additionally, our subsidiaries may incur unsecured indebtedness not to exceed $200 million in aggregate outstanding principal amount at any time. We are also permitted to repurchase our equity shares, provided that no such repurchases shall be made from proceeds borrowed under the Credit Agreement, and that the aggregate purchase price and dividends paid after September 25, 2015, does not exceed the Distribution Cap (equal to the sum of $750 million plus the lesser of (1) $400 million and (2) the amount received by us in connection with the arbitration and subsequent litigation of the PEP contracts as discussed in Note 12 to our condensed consolidated financial statements). At September 30, 2015, the remaining availability under the Distribution Cap was approximately $750 million.
Nonrecourse Project Finance Debt
Information relating to our nonrecourse project debt is described in Note 9 to our condensed consolidated financial statements.
Off-Balance Sheet Arrangements
Letters of credit, surety bonds and guarantees. In connection with certain projects, we are required to provide letters of credit, surety bonds or guarantees to our customers. Letters of credit are provided to certain customers and counterparties in the ordinary course of business as credit support for contractual performance guarantees, advanced payments received from customers and future funding commitments. We have approximately $2.1 billion in committed and uncommitted lines of credit to support the issuance of letters of credit and as of September 30, 2015, we have utilized $530 million of our present capacity under lines of credit. Surety bonds are also posted under the terms of certain contracts to guarantee our performance. The letters of credit outstanding included $130 million issued under our Credit Agreement and $400 million issued under uncommitted bank lines as of September 30, 2015. Of the letters of credit outstanding under our Credit Agreement, none have expiry dates beyond the maturity date of the Credit Agreement. Of the total letters of credit outstanding, $237 million relate to our joint venture operations where the letters of credit are posted using our capacity to support our pro-rata share of obligations under various contracts executed by joint ventures of which we are a member. As the need arises, future projects will be supported by letters of credit issued under our Credit Agreement or other lines of credit arranged on a bilateral, syndicated or other basis. We believe we have adequate letter of credit capacity under our Credit Agreement and bilateral lines of credit to support our operations for the next 12 months.
Transactions with Joint Ventures
We perform many of our projects through incorporated and unincorporated joint ventures. In addition to participating as a joint venture partner, we often provide engineering, procurement, construction, operations or maintenance services to the joint venture as a subcontractor. Where we provide services to a joint venture that we control and therefore consolidate for financial reporting purposes, we eliminate intercompany revenues and expenses on such transactions. In situations where we account for our interest in the joint venture under the equity method of accounting, we do not eliminate any portion of our revenues or expenses. We recognize the profit on our services provided to joint ventures that we consolidate and joint ventures that we record under the equity method of accounting primarily using the percentage-of-completion method. See Note 7 to our condensed consolidated financial statements for more information.
Legal Proceedings
Information relating to various commitments and contingencies is described in Notes 11 and 12 to our condensed consolidated financial statements.
Market risk
As filed, 900 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
We invest excess cash and equivalents in short-term securities, primarily time deposits, which carry a fixed rate of return for a given duration of time. Additionally, a substantial portion of our cash balances are maintained in foreign countries.
We are exposed to market risk associated with changes in foreign currency exchange rates, which may adversely affect our results of operations and financial condition.
We are exposed to and use derivative instruments, such as foreign exchange forward contracts and options to hedge foreign currency risk related to non-functional currency assets and liabilities on our balance sheet. Each period, these balance sheet hedges are marked to market through earnings and the change in their fair value is offset by remeasurement of the underlying assets and liabilities. See Note 16 to our condensed consolidated financial statements for more information.
Controls and procedures
As filed, 1,469 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
In accordance with the Securities Exchange Act of 1934 Rules 13a-15 and 15d-15, as amended (the "Exchange Act"), we carried out an evaluation, under the supervision and with the participation of management, including our Chief Executive Officer and Chief Financial Officer, of the effectiveness of our disclosure controls and procedures as of the end of the period covered by this report. Based on that evaluation, our Chief Executive Officer and Chief Financial Officer concluded that our disclosure controls and procedures were effective as of September 30, 2015 to provide reasonable assurance that information required to be disclosed in our reports filed or submitted under the Exchange Act is recorded, processed, summarized, and reported within the time periods specified in the Securities and Exchange Commission’s rules and forms. Our disclosure controls and procedures include controls and procedures designed to ensure that information required to be disclosed in reports filed or submitted under the Exchange Act is accumulated and communicated to our management, including our Chief Executive Officer and Chief Financial Officer, as appropriate, to allow timely decisions regarding required disclosure.
During the three months ended September 30, 2015, there have been no changes in our internal controls over financial reporting that have materially affected, or are reasonably likely to materially affect, our internal controls over financial reporting.
Risk factors
As filed, 1,394 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.
We have updated certain risk factors affecting our business since those presented in our Annual Report on Form 10-K, Part I, Item 1A, for the fiscal year ended December 31, 2014. Except for the risk factors updated, there have been no material changes in our assessment of our risk factors from those set forth in our Annual Report on Form 10-K, which is incorporated herein by reference, for the year ended December 31, 2014. Our updated risk factors are included below.
Risks Related to Operations of our Business
A portion of our revenues is generated by large, recurring business from certain significant customers. A loss, cancellation or delay in projects by our significant customers in the future could negatively affect our revenues.
While we provide services to a diverse customer base, including international and national oil and gas companies, independent refiners, petrochemical producers, fertilizer producers and domestic and foreign governments, a considerable percentage of our revenues, particularly in our E&C business segment, is generated from transactions with certain significant customers. Revenues from Chevron represented 11% of our total consolidated revenues for the nine months ended September 30, 2015. The loss of our significant customers, or the cancellation or delay in their projects, could adversely affect our revenues and results of operations.
Figures reported in this filing
Standardized line items from the XBRL in this filing, for the period ended 2015-09-30. Comparative periods it repeats are left out.
| Line item | Period | Value | XBRL concept |
|---|---|---|---|
| Revenue | 3 months2015-07-01 to 2015-09-30 | $1.20bn | us-gaap:Revenues |
| Revenue | 9 months2015-01-01 to 2015-09-30 | $4.02bn | us-gaap:Revenues |
| Cost of revenue | 3 months2015-07-01 to 2015-09-30 | $1.11bn | us-gaap:CostOfServices |
| Cost of revenue | 9 months2015-01-01 to 2015-09-30 | $3.79bn | us-gaap:CostOfServices |
| Gross profit | 3 months2015-07-01 to 2015-09-30 | $87.0m | us-gaap:GrossProfit |
| Gross profit | 9 months2015-01-01 to 2015-09-30 | $231.0m | us-gaap:GrossProfit |
| Operating income | 3 months2015-07-01 to 2015-09-30 | $75.0m | us-gaap:OperatingIncomeLoss |
| Operating income | 9 months2015-01-01 to 2015-09-30 | $235.0m | us-gaap:OperatingIncomeLoss |
| Income tax | 3 months2015-07-01 to 2015-09-30 | $19.0m | us-gaap:IncomeTaxExpenseBenefit |
| Income tax | 9 months2015-01-01 to 2015-09-30 | $61.0m | us-gaap:IncomeTaxExpenseBenefit |
| Net income | 3 months2015-07-01 to 2015-09-30 | $55.0m | us-gaap:NetIncomeLoss |
| Net income | 9 months2015-01-01 to 2015-09-30 | $161.0m | us-gaap:NetIncomeLoss |
| Diluted EPS | 3 months2015-07-01 to 2015-09-30 | $0.38 | us-gaap:EarningsPerShareDiluted |
| Diluted EPS | 9 months2015-01-01 to 2015-09-30 | $1.11 | us-gaap:EarningsPerShareDiluted |
| Basic EPS | 3 months2015-07-01 to 2015-09-30 | $0.38 | us-gaap:EarningsPerShareBasic |
| Basic EPS | 9 months2015-01-01 to 2015-09-30 | $1.11 | us-gaap:EarningsPerShareBasic |
| Diluted shares (weighted) | 3 months2015-07-01 to 2015-09-30 | 144,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Diluted shares (weighted) | 9 months2015-01-01 to 2015-09-30 | 144,000,000 shares | us-gaap:WeightedAverageNumberOfDilutedSharesOutstanding |
| Operating cash flow | 9 months2015-01-01 to 2015-09-30 | −$85.0m | us-gaap:NetCashProvidedByUsedInOperatingActivities |
| Capital expenditure | 9 months2015-01-01 to 2015-09-30 | $8.0m | us-gaap:PaymentsToAcquireProductiveAssets |
| Dividends paid | 9 months2015-01-01 to 2015-09-30 | $35.0m | us-gaap:PaymentsOfDividendsCommonStock |
| Share repurchases | 9 months2015-01-01 to 2015-09-30 | $22.0m | us-gaap:PaymentsForRepurchaseOfCommonStock |
| Cash and equivalents | At period end2015-09-30 | $768.0m | us-gaap:CashAndCashEquivalentsAtCarryingValue |
| Current assets | At period end2015-09-30 | $1.96bn | us-gaap:AssetsCurrent |
| Total assets | At period end2015-09-30 | $3.65bn | us-gaap:Assets |
| Current liabilities | At period end2015-09-30 | $1.52bn | us-gaap:LiabilitiesCurrent |
| Total liabilities | At period end2015-09-30 | $2.68bn | us-gaap:Liabilities |
| Shareholders' equity | At period end2015-09-30 | $982.0m | us-gaap:StockholdersEquity |
Source: SEC EDGAR, the filing index for accession 0001357615-15-000217. Last ingested by Listed: Nov 12, 2026, 17:43 ET. Listed shows no prices and gives no investment advice.