Ormat Technologies, Inc.: Form 10-K for the period ended Dec 31, 2019

Filed with the SEC on Mar 2, 2020 and accepted by EDGAR at Mar 2, 2020, 10:02 ET.

Share

Business

As filed, 161,439 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Overview

We are a leading vertically integrated company that is primarily engaged in the geothermal, and recovered energy power businesses. We are also expanding into the solar Photovoltaic (PV) and energy storage and management services business.

We design, develop, build, sell, own, and operate clean, environmentally friendly geothermal and recovered energy-based power plants, usually using equipment that we design and manufacture. Our objective is to become a leading global provider of renewable energy and we have adopted a strategic plan to focus on several key initiatives to expand our business.

We currently conduct our business activities in three business segments:

  • Electricity Segment. In the Electricity segment, which contributed 72.4% of our total revenues in 2019, we develop, build, own and operate geothermal, solar PV and recovered energy-based power plants in the United States and geothermal power plants in other countries around the world and sell the electricity they generate. In 2019, we derived 61.8% of our Electricity segment revenues from our operations in the U.S. and 38.2% from the rest of the world.
  • Product Segment. In the Product segment, which contributed 25.6% of our total revenues, we design, manufacture and sell equipment for geothermal and recovered energy-based electricity generation and remote power units and provide services relating to the engineering, procurement and construction of geothermal and recovered energy-based power plants. In 2019, we derived 16.0% of our Product segment revenues from our operations in the United States and 84.0% from the rest of the world.
  • Energy Storage and Management Services Segment. In the new Energy Storage and Management Services segment, which contributed 2.0% of our total revenues, we provide energy storage, demand response and energy management related services as well as services relating to the engineering, procurement, construction, operation and maintenance of energy storage units mainly through our Viridity business. In 2019, we derived 92.5% of our Energy Storage and Management Services segment from our operations in the United States.

The charts below show the relative contributions of each of our segments to our consolidated revenues and the geographical breakdown of our segment revenues for the fiscal year ended December 31, 2019.

The following chart sets forth a breakdown of our revenues for each of the years ended December 31, 2018 and 2019:

9

The following chart sets forth the geographical breakdown of revenues attributable to our Electricity, Product and Energy Storage and Management Services segments for each of the years ended December 31, 2018 and 2019:

Technology and products we use in our operations include geothermal, recovered energy, solar PV and energy storage:

Our owned geothermal power plants include both power plants that we have built and power plants that we have acquired. The substantial majority of the power plants that we currently own or operate produce electricity from geothermal energy sources. Geothermal energy is a clean, renewable and generally sustainable form of energy derived from the natural heat of the earth. Unlike electricity produced by burning fossil fuels, electricity produced from geothermal energy sources is produced without emissions of certain pollutants such as nitrogen oxide, and with far lower emissions of other pollutants such as carbon dioxide. As a result, electricity produced from geothermal energy sources contributes significantly less to global warming and local and regional incidences of acid rain than energy produced by burning fossil fuels. In addition, compared to power plants that utilize other renewable energy sources, such as wind or solar, geothermal power plants are generally available all year-long and all day-long and can therefore provide base-load electricity services. Geothermal power plants can also be custom built to provide a range of electricity services such as baseload, voltage regulation, reserve and flexible capacity. Geothermal energy is also an attractive alternative to other sources of energy, support of a diversification strategy to avoid dependence on any one energy source or politically sensitive supply sources. We recently launched our first geothermal and solar PV hybrid project, in which the electricity generated from a solar PV power plant is used to offset the equipment’s energy use at the geothermal facility, thus increasing the renewable energy delivered by the project to the grid.

In addition to our geothermal energy business, we manufacture and sell products that produce electricity from recovered energy or so-called “waste heat”. We also construct, own, and operate recovered energy-based power plants. We have built all of the recovered energy-based plants that we operate. Recovered energy comes from residual heat that is generated as a by-product of gas turbine-driven compressor stations, solar thermal units and a variety of industrial processes, such as cement manufacturing. Such residual heat, which would otherwise be wasted, may be captured in the recovery process and used by recovered energy power plants to generate electricity without burning additional fuel and without additional emissions.

In 2017, we entered the energy storage, demand response and energy management markets. We plan to accelerate long-term growth, expand our market presence in a growing market and further develop our energy storage and management services, including the VPower™ software platform.

10

Our Power Generation Business (Electricity Segment)

Each of our current geothermal power plants sells substantially all of its output pursuant to long-term, fixed price PPAs to various counterparties denominated in US dollars or Euros. These contracts had a total weighted average remaining term, based on contributions to segment revenue, of approximately 17 years at December 31, 2019. In addition, the counterparties to our PPAs in the United States had a credit rating of between Aa2 to Baa2. The purchasers of electricity from our foreign power plants are mainly state-owned entities in countries with below investment grade rating.

Power Plants in Operation

We own and operate 25 geothermal, REG and solar sites globally with an aggregate generating capacity of 914 MW. Geothermal comprises 93% of our generating capacity. In 2019, our geothermal and REG power plants generated at a capacity factor of 87% and 74%, respectively, which is higher than typical capacity factors for wind and solar producers that are usually at 20% to 30%.

The table below summarizes certain key non-financial information relating to our power plants and complexes as of February 25, 2020. The generating capacity of certain of our power plants and complexes listed below has been updated from our 2018 disclosure to reflect changes in the resource temperature and other factors that impact resource capabilities:

Type Region Plant Ownership(1) Generating capacity (MW) (2) PPA Tenor Capacity Factor
Geothermal California Ormesa Complex 100% 39 23
Heber Complex 100% 81 14
Mammoth Complex 100% 29 13 72%
Brawley 100% 13 12
West Nevada Steamboat Complex 100% 65 18 88%
Brady Complex 100% 26 16
East Nevada Tuscarora 100% 18 13
Jersey Valley 100% 10 13
McGinness Hills 100% 143 19 93%
Don A. Campbell 63.3% 36 16
Tungsten Mountain(4) 100% 27 24
North West Region Neal Hot Springs 60% 22(6) 19
Raft River 100% 11 13 92%
San Emidio 100% 11 19
Hawaii Puna 63.3% 38 33 NA%(7)
International Amatitlan (Guatemala) 100% 20 9
Zunil (Guatemala) 97% 20(10) 15
Olkaria III Complex (Kenya) 100% 150 15 88%
Bouillante (Guadeloupe Island, France) 63.75%(3) 15 11
Platanares (Honduras) 100% 38 13
Total Consolidated Geothermal 812 87%(8)
REG OREG 1 63.3% 22 12
OREG 2 63.3% 22 15
OREG 3 63.3% 5.5 10
OREG 4 100% 3.5(5) 10
Total REG 53 74%
solar Tungsten Mountain 100% 7(9) 24
Total solar 7
Unconsolidated Geothermal Indonesia Sarulla Complex 12.75% 42 28
Total Unconsolidated Geothermal 42
Total 914

11

1. We indirectly own and operate all of our power plants, although financial institutions hold equity interests in three of our subsidiaries: (i) Opal Geo subsidiaries, which own the McGinness Hills Phases 1 and 2 geothermal power plants, the Tuscarora and Jersey Valley power plants and the second phase of the Don A. Campbell power plant, all located in Nevada; (ii) ORNI 41, which owns the McGinness Hills Phase 3 located in Nevada; and (iii) ORNI 47, which owns the Tungsten Mountain geothermal power plant located in Nevada. In the table above, we list these power plants as being 100% owned because all of the generating capacity is owned by these subsidiaries and we control the operation of the power plants. The nature of the equity interests held by the financial institution is described below in Item 7 — “Management’s Discussion and Analysis of Financial Condition and Results of Operations” under the headings “Opal Transaction”, "McGinness Hills 3 Tax Monetization Transaction" and "Tungsten Mountain Tax Monetization Transaction.

Notwithstanding our 63.75% equity interest in the Bouillante power plant, 60% equity interest in the Neal Hot Spring power plant and 63.25% direct equity interest in the Puna plant, the first phase of Don A. Campbell, OREG 1, OREG 2 and OREG 3 power plants as well as the indirect interest in the second phase of the Don A. Campbell complex owned by our subsidiary, ORPD, we list 100% of the generating capacity of the Bouillante power plant, the Neal Hot Springs power plant and the power plants in the ORPD portfolio in the table above because we control their operations. We list our 12.75% share of the generating capacity of the Sarulla complex as we own a 12.75% minority interest. Revenues from the Sarulla complex are not consolidated and are presented under “Equity in earnings (losses) of investees, net” in our financial statements.

2. References to generating capacity generally refer to gross generating capacity less auxiliary power. We determine the generating capacity of these power plants by taking into account resource and power plant capabilities. In any given year, the actual power generation of a particular power plant may differ from that power plant’s generating capacity due to variations in ambient temperature, the availability of the geothermal resource, and operational issues affecting performance during that year.

3. We own 63.75%, CDC owns 21.25% and Sageos own 15.0% of the Bouillante power plant.

4. Tungsten Mountain is a Hybrid Geothermal and solar power plant that uses the solar energy for geothermal power plant auxiliary power. The solar power plant generates 7 MW and is presented separately in the table above.

5. The OREG 4 power plant is not operating at full capacity due to low run time of the compressor station that serves as the power plant’s heat source. This has resulted in lower power generation.

6. We own 60% and Enbridge owns 40% of the Neal Hot Springs power plant.

7. The Puna geothermal power plant has been shut down since May 3, 2018 when the Kilauea volcano located in close proximity to it erupted following a significant increase in seismic activity in the area. We continue efforts to resume its operation and we signed an amended PPA to extend its duration and expand its contract capacity as described below in Item 7 — “Management’s Discussion and Analysis of Financial Condition and Results of Operations” under the headings "Recent Development". In addition, we

8. The total availability of the geothermal power plants excludes the Puna power plant that is not in operation as discussed above.

9. Tungsten Mountain includes the 7AC MW Tungsten solar power plant that commenced commercial operation in July 2019.

10. In Zunil power plant revenues used to be calculated based on 24 MW generating capacity and was unrelated to the performance of the reservoir. In 2019 and onward, revenues are calculated based on the actual generation of the power plant, therefore the generating capacity was updated to reflect the current generating capacity.

12

New Power Plants

We are currently in various stages of construction of new power plants and expansion of existing power plants. Our construction and expansion plan include between 90 MW and 95 MW in generating capacity from geothermal and solar PV power plants in the United States. In addition, we have several geothermal and solar PV projects in the United States, Kenya and Guadeloupe that are either under initial stages of construction or under different stages of development with an aggregate capacity of between 71 MW and 76 MW.

We have substantial land positions across 31 prospects in the United States, and 10 prospects in Ethiopia, Guatemala, Honduras, Indonesia and New Zealand that we expect will support future geothermal development and on which we have started or plan to start exploration activity. These land positions are comprised of various leases, exploration concessions for geothermal resources and an option to enter into leases.

Our Product Business (Product Segment)

We design, manufacture and sell products for electricity generation and provide the related services described below. We primarily manufacture products to fill customer orders, but in some situations, we manufacture products as inventory for future projects that we will own and for future third party projects.

Power Units for Geothermal Power Plants

We design, manufacture and sell power units for geothermal electricity generation, which we refer to as OECs. In geothermal power plants using OECs, geothermal fluid (either hot water, also called brine, or steam or both) is extracted from the underground reservoir and flows from the wellhead to a vaporizer that heats a secondary working fluid, which is vaporized and used to drive the turbine. The secondary fluid is then condensed in a condenser, which may be cooled directly by air through an air cooling system or by water from a cooling tower and sent back to the vaporizer. The cooled geothermal fluid is then reinjected back into the reservoir. Our customers include contractors, geothermal power plant developers, owners and operators.

Power Units for Recovered Energy-Based Power Generation

We design, manufacture and sell power units used to generate electricity from recovered energy, or so-called “waste heat”. This heat is generated as a residual by-product of gas turbine-driven compressor stations, solar thermal units and a variety of industrial processes, such as cement manufacturing, and is not otherwise used for any purpose. Our existing and target customers include interstate natural gas pipeline owners and operators, gas processing plant owners and operators, cement plant owners and operators, and other companies engaged in other energy-intensive industrial processes.

EPC of Power Plants

We serve as an EPC contractor for geothermal and recovered energy power plants on a turnkey basis, using power units we design and manufacture. Our customers are geothermal power plant owners as well as our target customers for the sale of our recovered energy-based power units as described above. Unlike many other companies that provide EPC services, we believe that our competitive advantage is in using equipment that we manufacture allowing us better quality and control over the timing and delivery of required equipment and its related costs.

13

Remote Power Units and Other Generators

We design, manufacture and sell fossil fuel powered turbo-generators with capacities ranging from 200 watts to 5,000 watts, which operate unattended in extreme hot or cold climate conditions. Our customers include contractors who install gas pipelines in remote areas and offshore platform operators and contractors. In addition, we design, manufacture, and sell generators, including heavy duty direct-current generators, for various other uses.

Our Energy Storage and Management Services Segment

Our storage business currently manages, through the Viridity platform, curtailable customer loads across multiple sites under contracts with leading U.S. retail energy providers and directly with large C&I customers, including management of a portfolio of non-utility storage assets located in the northeastern United States . We serve our own energy storage assets and distributed customers through a NOC, which is operated 24/7 using our VPowerTM software platform and a SCADA platform. VPowerTM services are provided to customers using a SaaS model under which we receive license fees and/or a portion of the revenue and savings that are achieved for our customers.

We expect that the ecosystem we created, combining our Viridity's capabilities and legacy Ormat capabilities, including among other things, our global presence, experience in technology and system integration, development and EPC of power generation projects, flexible business models, and our reputation and experience in the geothermal and recovered energy sectors, will enable us to expand in the growing energy storage sector.

Our Viridity business obtained and maintains authorization from FERC to make wholesale purchase and sales of energy, capacity, and ancillary services at market-based rates, and we have confirmed membership status with eligibility to serve designated contractual functions within each of the following ISOs and RTOs: PJM, NYISO, ERCOT, MISO and ISONE. In the future, we may need to obtain and maintain similar membership and eligibility status with other ISO and RTO markets in which our Viridity business will operate, such as CAISO.

In 2019, we successfully brought on line two new Ormat/Viridity-owned BESS projects: 20MW/20 MWh in Alpha, NJ and 2 MW / 5 MWh in Hinesburg, Vermont. The Hinesburg project operates under an energy storage services agreement with the Vermont Electric Co-operative, under which we provide 1 MW of peak load reduction services several times a year. During the rest of the time, the Hinesburg project provides ancillary services to ISONE, thereby generating additional revenues.

We are currently in the commissioning stage of a project in Georgetown, Texas and developing a new project in California and a pilot system in Israel. We have a substantial pipeline for future development in the United States that and we expect to commission between 150 MW and 200 MW between 2020 and 2022. We plan to continue leveraging our worldwide experience in project development and finance, as well as our relationships with utilities and other market participants, to develop additional such BESS projects.

History

Ormat Technologies, Inc. was formed as a Delaware corporation in 1994 by our former parent company Ormat Industries. Ormat Industries was one of the first companies to focus on the development of equipment for the production of clean, renewable and generally sustainable forms of energy. On February 12, 2015, we successfully completed the acquisition of Ormat Industries in an all-stock merger, eliminating its majority ownership and control of Ormat Technologies.

Business Strategy

Our strategy is focused on further developing a geographically balanced portfolio of geothermal, solar (PV) and recovered energy assets and continuing our leading position in the geothermal energy market with the objective of becoming a leading global provider of renewable energy. Our strategy focuses on three main elements:

  • our core geothermal business in the United States as well as globally;
  • establishing a strong market position in the energy storage market; and
  • exploring opportunities in new areas by looking for synergistic growth opportunities utilizing our core competence, market reputation as a successful company and new market opportunities focused upon environmental solutions.

We intend to implement this strategy through:

  • Using Our Operational Capabilities to Increase Output from our Existing Geothermal Power Plants — increasing output from our existing geothermal power plants by adding additional generating capacity, upgrading plant technology, and improving geothermal reservoir operations, including improving methods of heat source supply and delivery.
  • Creating Cost Savings through Increased Operating Efficiency — increasing efficiencies in our operating power plants and manufacturing facility including procurement by adding new technologies, restructuring of management control, automating part of our manufacturing work and centralizing our operating power plants.
  • Diversifying our Customer Base — evaluating a number of strategies for expanding our customer base to the CCA and C&I markets. In the near term, however, we expect that substantial majority of our revenues will continue to be generated from our traditional electrical utility customer base for the Electricity segment.
  • Maintaining a Prudent and Flexible Capital Structure — we have various financing structures in place, including non-recourse project financings, the sale of differential membership interests and equity interests in certain subsidiaries, as well as revolving credit facilities and term loans. We believe our cash flow profile, the long-term nature of our contracts, and our ability to raise capital provide greater flexibility for optimizing our capital structure.

14

  • Improving our Technological Capabilities — investing in research and development of renewable energy technologies and leveraging our technological expertise to continuously improve power plant components, reduce operations and maintenance costs, develop competitive and environmentally friendly products for electricity generation and target new service opportunities. In addition, we are expanding our core geothermal competencies to provide high efficiency solutions for high enthalpy applications by utilizing our binary enhanced cycle and technology.
  • Development and Construction of New Geothermal Power Plants — continuously seeking out commercially exploitable geothermal resources, developing and constructing new geothermal power plants by either entering into long-term PPAs providing stable cash flows or selling in the "merchant" market in jurisdictions where the regulatory, tax and business environments encourage or provide incentives for such development;
  • Expanding our Geographical Reach — increasing our business development activities in an effort to grow our business in the global markets in all business segments. While we continue to evaluate global opportunities, we currently see the U.S., Kenya, Indonesia, and Ethiopia as attractive markets for our Electricity segment and New Zealand, Philippines, Turkey, Chile, Indonesia and China as attractive markets for our Product segment. We are actively looking at ways to expand our presence in those countries.
  • Acquisition of New Assets — expanding and accelerating growth through acquisition activities globally, aiming to acquire additional geothermal assets with long term PPAs or without a PPA as well as operating and development assets that can support our storage business.
  • Manufacturing and Providing Products and EPC Services Related to Renewable Energy — designing, manufacturing and contracting power plants for our own use and selling to third parties power units and other generation equipment for geothermal and recovered energy-based electricity generation;
  • Expanding into New Technologies - leveraging our technological capabilities over a variety of renewable energy platforms, including solar power generation and energy storage. We may acquire companies with integration and technological capabilities that we do not currently have, or develop new technology ourselves, where we can effectively leverage our expertise to implement this part of our strategic plan.

The map below shows our worldwide portfolio of operating geothermal, solar PV and recovered energy power plants as of February 25, 2020.

* In the Sarulla complex, we include our 12.75% share only.

15

The map below shows our portfolio of operating storage facilities as of February 25, 2020.

Industry Background

Geothermal Energy

There are several different sources or methods of obtaining geothermal energy, which are described below.

Hydrothermal geothermal-electricity generation — Hydrothermal geothermal energy is derived from naturally occurring hydrothermal reservoirs that are formed when water comes sufficiently close to hot rock to heat the water to temperatures of 300 degrees Fahrenheit or more. The heated water then ascends toward the surface of the earth where, if geological conditions are suitable for its commercial extraction, it can be extracted by drilling geothermal wells. Geothermal production wells are normally located within several miles of the power plant, as it is not economically viable to transport geothermal fluids over longer distances due to heat and pressure loss. The geothermal reservoir is a renewable source of energy if: (i) natural ground water sources and reinjection of extracted geothermal fluids are adequate over the long-term to replenish the geothermal reservoir following the withdrawal of geothermal fluids and (ii) the well field is properly operated. Geothermal energy power plants typically have higher capital costs (primarily because of the costs attributable to well field development) but tend to have significantly lower variable operating costs (principally consisting of maintenance expenditures) than fossil fuel-fired power plants that require ongoing fuel expenses.

16

EGS — An EGS is a subsurface system that may be artificially created to extract heat from hot rock where the permeability and aquifers required for a hydrothermal system are insufficient or non-existent. A geothermal power plant that uses EGS techniques recovers the thermal energy from the subsurface rocks by creating or accessing a system of open fractures in the rock through which water can be injected, heated through contact with the hot rock, returned to the surface in production wells and transferred to a power unit.

Co-produced geothermal from oil and gas fields, geo-pressurized resources — Another source of geothermal energy is hot water produced as a by-product of oil and gas extraction. When oil and gas wells are deep, the extracted fluids are often at high temperatures and if the water volume associated with the extracted fluids is significant, the hot water can be used for power generation in equipment similar to a geothermal power plant.

Geothermal Power Plant Technologies

Geothermal power plants generally employ either binary systems or conventional flash design systems, as briefly described below. In our geothermal power plants, we also employ our proprietary technology of combined geothermal cycle systems.

Binary System

In a geothermal power plant using a binary system, geothermal fluid (either hot water (also called brine) or steam or both) is extracted from the underground reservoir and flows from the wellhead through a gathering system of insulated steel pipelines to a vaporizer that heats a secondary working fluid. This is typically an organic fluid, such as pentane or butane, which is vaporized and is used to drive the turbine. The organic fluid is then condensed in a condenser, which may be cooled directly by air or by water from a cooling tower and sent back to the vaporizer through a pump. The cooled geothermal fluid is then reinjected back into the reservoir. The operation of our air-cooled binary geothermal power plant is depicted in the diagram below.

17

Flash Design System

In a geothermal power plant using flash design, geothermal fluid is extracted from the underground reservoir and flows from the wellhead through a gathering system of insulated steel pipelines to flash tanks and/or separators. There, the steam is separated from the brine and is sent to a demister, where any remaining water droplets are removed. This produces a stream of dry saturated steam, which drives a steam turbine generator to produce electricity. In some cases, the brine at the outlet of the separator is flashed a second time (dual flash), providing additional steam at lower pressure used in the low-pressure section of the steam turbine to produce additional electricity. Steam exhausted from the steam turbine is condensed in a surface or direct contact condenser cooled by cold water from a cooling tower. The non-condensable gases (such as carbon dioxide) are removed by means of a vacuum system in order to maintain the performance of the steam condenser. The resulting condensate is used to provide make-up water for the cooling tower. The hot brine remaining after separation of steam is injected (either directly or after passing through a binary plant to produce additional power from the residual heat remaining in the brine) back into the geothermal resource through a series of injection wells. The flash technology is depicted in the diagram below.

In some instances, the wells directly produce dry steam and the steam is fed directly to the steam turbine with the rest of the system similar to the flash technology described above.

Our Proprietary Technology

Our proprietary technology may be used either in power plants operating according to the ORC alone or in combination with various other commonly used thermodynamic technologies that convert heat to mechanical power, such as gas and steam turbines. It can be used with a variety of thermal energy sources, such as geothermal, recovered energy, biomass, solar energy and fossil fuels. Specifically, our technology involves original designs of turbines, pumps, and heat exchangers, as well as formulation of organic motive fluids (all of which are non-ozone-depleting substances). By using advanced computational fluid dynamics techniques and other computer aided design software as well as our test facilities, we continuously seek to improve power plant components, reduce operations and maintenance costs, and increase the range of our equipment and applications. We are always examining ways to increase the output of our plants by utilizing evaporative cooling, cold reinjection, configuration optimization, and topping turbines. In the geothermal as well as the recovered energy (waste heat) areas, we are examining two-level and three-level energy systems and other thermodynamic cycle alternations along with new motive fluids.

18

We also developed, patented and constructed GCCU power plants in which the steam first produces power in a backpressure steam turbine and is subsequently condensed in a vaporizer of a binary plant, which produces additional power. Our Geothermal Combined Cycle technology is depicted in the diagram below.

In the conversion of geothermal energy into electricity, our technology has a number of advantages over conventional geothermal steam turbine plants. A conventional geothermal steam turbine plant consumes significant quantities of water, causing depletion of the aquifer and requiring cooling water treatment with chemicals and consequently a need for the disposal of such chemicals. A conventional geothermal steam turbine plant also creates a significant visual impact in the form of an emitted plume from the cooling towers, especially during cold weather. By contrast, our binary and combined cycle geothermal power plants have a low profile with minimal visual impact and do not emit a plume when they use air-cooled condensers. Our binary and combined cycle geothermal power plants reinject all of the geothermal fluids utilized in the respective processes into the geothermal reservoir. Consequently, such processes generally have no emissions.

Other advantages of our technology include simplicity of operation and maintenance and higher yearly availability. For instance, the OEC employs a low speed and high efficiency organic vapor turbine directly coupled to the generator, eliminating the need for reduction gear. In addition, with our binary design, there is no contact between the turbine blade and geothermal fluids, which can often be very erosive and corrosive. Instead, the geothermal fluids pass through a heat exchanger, which is less susceptible to erosion and can adapt much better to corrosive fluids. In addition, with the organic vapor condensed above atmospheric pressure, no vacuum system is required.

We use the same elements of our technology in our recovered energy products. The heat source may be exhaust gases from a Brayton cycle gas turbine, low-pressure steam, or medium temperature liquid found in the process industries such as oil refining and cement manufacturing. In most cases, we attach an additional heat exchanger in which we circulate thermal oil or water to transfer the heat into the OEC’s own vaporizer in order to provide greater operational flexibility and control. Once this stage of each recovery is completed, the rest of the operation is identical to that of the OECs used in our geothermal power plants and enjoys the same advantages of using the ORC. In addition, our technology allows for better load following than conventional steam turbines, requires no water treatment (since it is air cooled and organic fluid motivated), and does not require the continuous presence of a licensed steam boiler operator on site.

19

Our REG technology is depicted in the diagram below.

Patents

As of February 25, 2020, we have 63 issued U.S. patents and four pending U.S. patents applications. These patents and patent applications cover our products (mainly power units based on the ORC) and systems (mainly geothermal power plants and industrial waste heat recovery plants for electricity production). The product-related patents cover components that include turbines, heat exchangers, air coolers, seals and controls as well as control of operation of geothermal production well pumps. The system-related patents cover not only particular components but as well as the overall energy conversion system from the “fuel supply” (e.g., geothermal fluid, waste heat, biomass or solar) to electricity production.

The system-related patents also cover subjects such as waste heat recovery related to gas pipeline compressors and industrial waste heat, solar power systems, disposal of non-condensable gases present in geothermal fluids, reinjection of other geothermal fluids ensuring geothermal resource sustainability, power plants for very high-pressure geothermal resources, two-phase fluids, low temperature geothermal brine as well as processes related to EGS. 55 of our patents cover combined cycle geothermal power plants, in which the steam first produces power in a backpressure steam turbine and is subsequently condensed in a vaporizer of a binary plant, which produces additional power. The remaining terms of our issued patents range from one year to 16 years. The loss of any single patent would not have a material effect on our business or results of operations.

Research and Development

We conduct research and development activities intended to improve plant performance, reduce costs, and increase the breadth of our product offerings. The primary focus of our research and development efforts is targeting power plant conceptual thermodynamic cycle and major equipment including continued performance, cost and land usage improvements to our condensing equipment, and development of new higher efficiency and higher power output turbines. New realms for innovation include implementation of predictive maintenance software and automation of power plants performance analysis. Based on vast experience and strong engineering and manufacturing assets, products for new markets are in early development stages within the R&D effort.

Our Viridity business continues to develop new optimization algorithms to optimize the life of a battery energy storage system (BESS), to optimize our and our customers’ economic return and to forecast the trends surrounding our customers’ electricity consumption and the electric grid including times of peak demands and the usage of ancillary services.

We have also focused our development efforts on the engineering and design of improved energy storage systems. These development efforts include, among others, building of an energy storage lab for testing of various batteries, inverters and the integration of both. Further efforts include the development of the control hardware and software for energy storage systems to follow electric grid and market signals and to optimize their delivery of energy into the markets .

20

We have developed, and continue to develop, system integration capabilities that match the appropriate system and system sizing with the appropriate battery chemistry, electrical and physical components to accommodate our needs or needs of the customers that will own such energy storage systems in light of the markets in which they will operate. We are searching for alternative chemistries, products and combinations of hybrid solutions to best address our energy storage product customers’ needs.

Additionally, we are continuing to evaluate investment opportunities in new companies with technology and/or product offerings for renewable energy and energy storage solutions.

Market Opportunities

Geothermal Market Opportunities

Renewable energy in general provides a sustainable alternative to the existing solutions to two major global issues: climate change and diminishing fossil fuel reserves. Renewable energy is sustainable, clean and decarbonizes the grid. These environmental benefits have led major countries to focus their efforts on the development of renewable energy sources in general and geothermal specifically.

Based on an announcement by the IGA in January 2020, geothermal power is generated in 29 countries with a total installed power generation capacity of 15,400 MW at the end of 2019. The leading countries are the U.S., Indonesia, Philippines, Turkey, Mexico and New Zealand. The IGA expects that 4,500 MW will be added by 2025.

Having realized the importance of renewable energy including geothermal alternatives, various governments have been preparing regulatory frameworks and policies, and providing incentives to develop the sector.

United States

Interest in geothermal energy in the United States remains strong for numerous reasons, including legislative support, RPS goals (as described below), coal, natural gas and nuclear power plant retirements, and an increasing awareness of the positive value of geothermal characteristics when compared to intermittent renewable technologies.

Today, electricity generation from geothermal resources is concentrated mainly in California, Nevada, Hawaii, Idaho, Oregon, and Utah, and we believe there are opportunities for expansion in other states such as New Mexico due to the potential of its geothermal resources.

Geothermal energy provides numerous benefits to the U.S. grid and economy. Geothermal development and operation bring economic benefits in the form of taxes and long term high-paying jobs, and it currently has one of the lowest LCOE of all power sources in the United States, according to the U.S. Energy Information Administration's report published in February 2019. Additionally, improvements in geothermal production make it possible to provide ancillary and on-demand services. This helps load serving entities avoid additional costs from purchasing and then balancing intermittent resources with storage or new transmission.

State level legislation

Many state governments have enacted an RPS program under which utilities are required to include renewable energy sources as part of their energy generation. Under an RPS, participating states have set targets for the production of their energy from renewable sources by specified dates. Renewable energy generation under RPS programs are tracked through the production of Renewable Energy Credits (RECs). Load serving entities track the RECs to ensure they are meeting the mandate prescribed by the RPS.

21

Currently in the United States, 42 states plus the District of Colombia and four territories have enacted an RPS, renewable portfolio goals, or similar laws (such as clean energy standards or goals) requiring or encouraging load serving entities in such states to generate or buy a certain percentage of their electricity from renewable energy or recovered heat sources. The vast majority of Ormat’s geothermal projects can be found in California, Nevada, and Hawaii which have some of the most stringent RPS programs in the country.

We see the impact of RPS and climate legislation as the most significant driver for us to expand existing power plants and to build new renewable projects.

Below are RPS targets in the states in which we are operating:

State RPS Target Year Remarks
California 60% 2030 RPS targets set for future years: 44% – 2024, 52% – 2027, and 60% – 2030. 100% zero carbon by 2045.
Nevada 50% 2030 RPS target of 50% by 2030 and 100% zero carbon by 2050. The state has a credit multiplier for photovoltaic and on peak energy savings.
Hawaii 100% 2045 RPS targets set for future years: 30% by 2020, 40% by 2030, and 70% by 2040
Oregon 25% 2025 Increased RPS of 50% by 2040 applies to IOUs who have a share of more than 3% of the state’s load; for utilities with a load-share of 1.5% – 3%, requirement is 10% in 2025, and for utilities with a load share of less than 1.5%, it is 5% in 2025

States also provide incentives to geothermal energy producers. Nevada provides a property tax abatement of up to 55% for real and tangible personal property used to generate electricity from geothermal sources. The abatement may extend up to twenty years if certain job creation requirements are met. The California Energy Commission provides favorable grants and loans to promote the development of new or existing geothermal resources and technologies within the state. In Idaho, geothermal energy producers are exempt from property tax and, in lieu, pay a tax of 3% of gross energy earnings.

Global

We believe the global markets continue to present growth and expansion opportunities in both established and emerging markets.

Operations outside of the United States may be subject to and/or benefit from increasing efforts by governments and businesses around the world to fight climate change and move towards a low carbon, resilient and sustainable future. According to a recent report by the International Renewable Energy Agency entitled Toward 100% Renewable Energy, in 2019, a total of 61 countries had set a 100% renewable energy target in at least one end-use sector, up from 60 countries in 2018.

We believe that several global initiatives will create business opportunities and support global growth of the renewable sector such as the historic agreement at the COP21 UN Climate Change Conference held in Paris, which, for the first time, created a commitment by 127 parties to setting nationally determined climate targets and reporting on their progress. Following this agreement, the EIB and other multilateral institutions have committed to provide $100 billion of new financing for climate action projects over the next five years to assist countries in reaching their targets. However, on June 1, 2017, President Donald J. Trump announced that the United States will withdraw from this agreement.

In addition, in 2015, a group of 20 countries, including the United States, United Kingdom, France, China and India, pledged to double their respective budgets for renewable energy technology over five years as part of a separate initiative called Mission Innovation. At the same time, the Breakthrough Energy Coalition was launched by a group of 28 private investors with the objective of bringing companies with the potential to deliver affordable, reliable and carbon free power from the research lab to the market.

We believe that as a general matter these developments and governmental plans will create growth and expansion opportunities for us internationally.

22

Outside of the United States, the majority of power generating capacity has historically been owned and controlled by governments. Since the early 1990s, however, many foreign governments have privatized their power generation industries through sales to third parties encouraging new capacity development and/or refurbishment of existing assets by independent power developers. These foreign governments have taken a variety of approaches to encourage the development of competitive power markets, including awarding long-term contracts for energy and capacity to independent power generators and creating competitive wholesale markets for selling and trading energy, capacity, and related products. Some foreign regions and countries have also adopted active government programs designed to encourage clean renewable energy power generation such as the following countries in which we operate, sell products and/or are conducting business development activities:

Europe

Europe has the fourth largest geothermal power capacity, the majority of which stems from Italy and Turkey. A significant part of our European operations is in Turkey. We are looking for opportunities to expand in Europe, particularly in Germany.

Turkey

Until recently, Turkey was the fastest growing geothermal market worldwide with the theoretical potential for 31 GW of geothermal capacity and with a proven geothermal capacity of 4.5 GW, according to the Turkish Mineral Technical Exploration Agency. Due to the economic situation in Turkey, there has been a slowdown.

Since 2004, we have established strong business relationships in the Turkish market and provided our range of solutions including our binary systems, to over 40 geothermal power plants with a total capacity of approximately 900 MW, of which six power plants are currently under construction.

In Turkey, the “National Renewable Energy Action Plan” proposes to increase the country's renewable energy generation capacity to 61 GW by 2023, including 1.5 GW of electricity generation from geothermal resources. This plan is supported by the European Bank for Reconstruction and Development. The plan aims to increase Turkish energy security by diversifying its energy supply, making greater use of domestic resources, protecting the environment by relying on clean, renewable and low carbon technologies and fostering energy market efficiency through private sector investment and integration.

The current regulation in Turkey, which is expected to expire on December 2020, support an incentivized FIT of 10.5 US cents per kWh and additional 1.8 US cents per kWh for local manufactured items. This regulation is expected to be changed, but it is not clear yet what will be the actual FIT and other factors related to the incentive plan. It is estimated that the FIT will be lower from the existing one and the structure of the incentivized local manufactured items will also change, to increase the locally made parts. Until this is cleared, and a new regulation will be in place with a new timetable, we estimate that the slowdown in development of new sites will continue.

Latin America

Several Latin American countries have renewable energy programs and pursue the development of the geothermal market. We currently operate in some countries in Latin America and are looking for opportunities in others.

Guatemala

In Guatemala, where our Zunil and Amatitlan power plants are located, the government approved and adopted the Energy Policy 2013-2027 that secure, among other things, a supply of electricity at competitive prices by diversifying the energy mix with an 80% renewable energy share target for 2027.

Honduras

In Honduras, where we operate our Platanares power plant, the government set a target to reach at least 80% renewable energy production by 2034.

Mexico

In Mexico, where we see long-term potential, the Mexican Congress passed, in December 2013, a constitutional reform in an attempt to increase the participation of private investors in the generation and commercialization of electric energy. We have not yet seen yet a notable progress in the development of new geothermal projects.

23

Caribbean

Many island nations in general and specifically the Caribbean nations, depend almost entirely on petroleum to meet their electricity needs. Caribbean nations have quite significant renewable energy potential, yet most have relatively small demand. Other than in Guadeloupe, where the geothermal power plant that we acquired has been operating since 1985, there are no other operating geothermal projects in the Caribbean region. Although few, we believe there are geothermal opportunities for us in the Caribbean islands of St. Kitts, Nevis, St. Lucia, Dominica, and Montserrat.

New Zealand

In New Zealand, where we have been actively providing geothermal power plant solutions since 1988, the government’s policies to fight climate change include a net zero GHG emissions reduction target by 2050 and a renewable electricity generation target of 90% of New Zealand’s total electricity generation by 2035. We continue selling power plant equipment to our New Zealand customers, secured two projects in the last two years and intensified our cooperation with other potential customers for adding more geothermal power generation capacity within the coming years.

Asia

Indonesia

In Indonesia, where we hold a 12.75% equity interest in the Sarulla complex, we are currently conducting exploration activity in the Ijen geothermal power plan in East Java, in which we own a 49% equity interest and whose first phase we plan to commission in either 2022 or 2023. The government intends to increase the share of renewable energy sources in the energy mix, aiming to meet a target of 23% of domestic energy demand by 2025, and announced its intention to reduce the country’s carbon dioxide emissions by 26% by 2020. Under the current local regulation, the tariff policy for geothermal PPAs is mainly determined based on the location of the relevant power plant.

We consider Indonesia an important geothermal market, where potential for future development is significant along with an active geothermal industry that is supported by regulatory incentives and commitment from the local government.

In addition to project development, we are also pursuing various supply opportunities in Indonesia, and in other countries in Southeast Asia, including several optimization projects.

China

In China, where we supplied our equipment to one of our clients’ geothermal projects, the National Energy Administration adopted the 13th Renewable Energy Development Five Year Plan that establishes targets for renewable energy deployment until 2020. Key objectives under the plan include, among others, to increase the share of non-fossil fuel energy in total primary energy consumption to 15% by 2020 and to 20% by 2030, and to increase installed renewable power capacity to 680 GW by 2020.

Japan

The installed capacity of Japan places ninth in the world, the potential output of 23,470 MW is third in the world after United States and Indonesia. In 2018, the Japanese government established as its goal a target of 22% to 24% renewable energy of the Japanese energy installed base by 2030. This outlook expects new geothermal plant installation in the range of 380 MW to 850 MW - 1,000 MW. State-owned resources agency JOGMEC will conduct test bores as part of the financially risky early phase of development on behalf of potential developers starting in the fiscal year from April 2020.

East Africa

In East Africa the geothermal potential along the Rift Valley is estimated at several thousand MW. The different countries along the Rift Valley are at different stages of development of their respective geothermal potential.

24

Kenya

In Kenya, there are already several geothermal power plants, including the only geothermal IPP in Africa, our 150 MW Olkaria III complex. The Kenyan government has identified the country's untapped geothermal potential as the most suitable indigenous source of electricity, and it aspires to reach 5 GW of geothermal power generation by 2030.

The Kenyan government is aiming to reach 22.7GW of power generating capacity by 2033, under the Least-Cost Power Development Plan 2013-33 with a target of 42% of such capacity generated from renewable energy sources (including large hydro but excluding solar).

We consider Kenya an important location for our future growth and we are pursuing geothermal and solar opportunities in the country.

Other Countries

The governments of Djibouti, Eritrea, Ethiopia, Tanzania, Uganda, Rwanda and Zambia are exploring ways to develop geothermal resources in their countries, mostly through the help of international development organizations such as the World Bank.

Ethiopia electrification targets for 2025 require additional investment in generation capacities. Such growth in demand was expected to be principally met with the Grand Ethiopian Renaissance Dam (GERD). However, IPP’s are encouraged to participate directly into the renewable development in order to meet expected local growth. Moreover, the current government sees electricity export to neighboring countries as a strategic asset. The country recently completed an interconnection with Kenya and plan to further increase connections to Djibouti, Sudan, South Sudan, Rwanda, Burundi. These exports will improve foreign exchange reserves in Ethiopia . We hold rights for four geothermal concessions in Ethiopia, for which we have completed initial exploration studies.

In January 2014, energy ministers and delegates from 19 countries committed to the creation of the Africa Clean Energy Corridor Initiative (Corridor), at a meeting in Abu Dhabi convened by the International Renewable Energy Agency. The Corridor will boost the deployment of renewable energy and aim to help meet Africa’s rising energy demand with clean, indigenous, cost-effective power from sources including hydro, geothermal, biomass, wind and solar.

Other Opportunities

Recovered Energy Generation

In addition to our geothermal power generation activities, we are pursuing recovered energy-based power generation opportunities in the United States and worldwide. We believe recovered energy-based power generation will ultimately benefit from the efforts to reduce GHG emissions. We have built 23 power plants in North America which generate electricity utilizing “waste heat” from gas turbine-driven compressor stations along interstate natural gas pipelines, from midstream and gas processing facilities, and from other applications.

Several states, and to some extent, the federal government, have recognized the environmental benefits of recovered energy-based power generation. For example, 18 states currently allow electric utilities to include recovered energy-based power generation in calculating such utilities' compliance with their mandatory or voluntary RPS and/or Energy Efficient Resources Standards. In addition, California modified the Self Generation Incentive Program to allow recovered energy-based power generation to qualify for a per watt incentive.

Recovery of waste heat is also considered “environmentally friendly” in western Canadian provinces. In 2016, the Canadian government ratified its commitments in the Paris Agreement, which features a commitment to reduce emissions by 30% from 2005 levels by 2030. Pursuant to the Greenhouse Gas Pollution Pricing Act, Canadian provinces must have an emission reduction plan in place or be subject to a federal carbon tax in 2018.

25

The government of Alberta has introduced the Technology Innovation and Emissions Reduction (TIER) regulation, a plan for reducing emissions, replacing the Carbon Competitiveness Incentive Regulation on January 1, 2020. The TIER regulation applies to Alberta’s large industrial facilities that emitted 100,000 tonnes CO2 or more per year of greenhouse gases in 2016, or a subsequent year. Facilities will be subject to a reduction requirement starting at a benchmark of 90% of their prior emissions, then increasing 1% per year after the first year of compliance starting in 2020.

On a federal level, in October 2016, the Government of Canada published the Pan-Canadian Approach to Pricing Carbon Pollution, setting a federal benchmark to ensure that carbon pricing applies to a broad set of emission sources throughout Canada in 2018 with increasing stringency over time. This approach would be flexible and recognize that provinces and territories have implemented or are developing their own carbon pollution pricing systems. The Environment and Climate Change Canada has developed a proposal for regulations pursuant to the Greenhouse Gas Pollution Pricing Act in force June 2018 to implement a carbon pricing system that will apply to facilities carrying out certain industrial activities.

This comprehensive climate policy, once fully implemented, will encourage the development of renewable energy technologies, including waste heat recovery, throughout Canada. We believe that Europe and other markets worldwide may offer similar opportunities in recovered energy-based power generation.

In summary, the market for the recovery of waste heat converted into electricity exists either when already available electricity is expensive or where the regulatory environment facilitates construction and marketing of power generated from recovered waste heat. However, such projects tend to be smaller than 9 MW and we expect any growth to be relatively slow and geographically scattered.

Energy Storage

Globally, there is an increase in the use of renewable energy, mainly due to the continued decline in solar PV prices. In the United States and Europe, this increase is placing strains on the electric grid because adding wind and particularly solar PV power creates situations where a significant amount of power plant capacity must be available to ramp up and down to accommodate wind and mostly solar PV daily output cycles and variations due to atmospheric conditions. Furthermore, the output from wind and solar PV power plants can change significantly over short periods of time due to environmental conditions like cloud movement and fog burn off and cause instability on the electric grid.

As a result, energy management, and especially energy storage is becoming a key component of the future grid. In parallel, we also see movement of C&I and communities toward direct purchases of electricity and an increased focus on reliability of electricity supply.

Energy storage systems utilize surplus, available electricity that enables utilities to optimize the operation of the grid, run generators closer to full capacity for longer periods, and operate the grid more efficiently and effectively. As penetration of wind and solar resources increases, so does the need for services that energy storage systems can provide to “balance the grid”, such as local capacity, frequency regulation, ramping, reactive power, black start and movement of energy from times of excess supply to times of high demand. Common applications for energy storage systems include ancillary services, wind/solar smoothing, peaker replacement, and transmission & distribution deferral.

The global energy storage market continues to evolve, with specific applications and geographies leading the market. According to Wood Mackenzie's (formerly GTM Research) Energy Storage Monitor for Q3 2019, approximately 1.1 GWh of new energy storage projects were installed in the United States in 2019 and this number is expected to triple in 2020 to approximately 3.3 GWh.

Significant growth in BESS deployment is already taking place and is expected to continue for both grid-connected (also referred to as “in front of the meter”) applications, as well as for “behind the meter” applications, where end-users benefit from savings through demand charge reductions and create revenues through active market participation, and via demand response programs. Many power systems are also undergoing significant changes such as grid aging, grid congestion, retirement of aging generators, implementation of greenhouse gas emission reduction rules and increasing penetration of variable renewable energy resources.

Grid-Connected BESS

We own and operate several grid-connected BESS facilities, where revenues come from selling energy, capacity and/or ancillary services in merchant markets like PJM Interconnect and ISO New England. We are pursuing the development of additional grid-connected BESS projects in multiple regions, with expected revenues coming from providing energy, capacity and/or ancillary services on a merchant basis, and/or through bilateral contracts with load serving entities, e.g. investor owned utilities, publicly owned utilities and community choice aggregators.

26

C&I

The electricity industry continues to shift from a purely centralized topology where electricity flows only in one direction from centralized power plants to consumers, into a more distributed architecture, that includes distributed energy resources and consumers selling excess electricity generated on-site to the grid. Many C&I companies are motivated to purchase renewable energy to meet sustainability goals and reduce costs. We see the C&I segment as a natural expansion of our customer base, though our focus is on utility-scale front-of-the-meter applications, where we expect to see higher growth.

solar PV

The solar PV market continues to grow, driven by constant decline in equipment prices and an increasing desire to replace conventional generation with renewable resources, commonly supported by favorable regulatory policies. We are monitoring market drivers with the potential to develop solar PV power plants in locations where we can offer competitively priced power generation. Our current focus is in adding solar PV systems in some of our operating geothermal power plants to reduce internal consumption loads, developing standalone solar PV projects in targeted regions where economics are favorable as well as developing combined solar PV and BESS projects. In 2019 we successfully placed in service a solar PV augmentation system at our Tungsten Mountain geothermal power plant in Churchill County, Nevada. We are also constructing the 20 MW(AC) Wister solar PV project in Imperial County, California, for which a power purchase agreement with San Diego Gas & Electric is in effect and we target commercial operation in 2021. Additional potential projects are undergoing feasibility analysis, and some are in earlier phases of development.

Operations of our Electricity Segment

How We Own Our Power Plants

We customarily establish a separate subsidiary to own interests in each of our power plants. This ensures that the power plant, and the revenues generated by it, will be the only source for repaying indebtedness, if any, incurred to finance the construction or the acquisition (or to refinance the construction or acquisition) of the relevant power plant. If we do not own all of the interest in a power plant, we enter into a shareholders’ agreement or a partnership agreement that governs the management of the specific subsidiary and our relationship with our partner in connection with the specific power plant. Our ability to transfer or sell our interests in certain power plants may be restricted by certain purchase options or rights of first refusal in favor of our power plant partners or the power plant’s power purchasers and/or certain change of control and assignment restrictions in the underlying power plant and financing documents. All of our domestic geothermal and REG power plants are Qualifying Facilities under the PURPA and are eligible for regulatory exemptions from most provisions of the FPA and certain state laws and regulations.

How We Explore and Evaluate Geothermal Resources

Since 2006, we have expanded our exploration activities, initially in the United States and in the last few years with an increasing focus internationally. It generally takes two to three years from the time we start active exploration of a particular geothermal resource to the time we have an operating production well, assuming we conclude the resource is commercially viable and determine to pursue its development. Exploration activities generally involve the phases described below.

Initial Evaluation

We identify and evaluate potential geothermal resources by sampling and studying new areas combined with information available from public and private sources. We generally adhere to the following process, although our process can vary from site to site depending on geological circumstances and prior evaluation:

  • We evaluate historic, geologic and geothermal information available from public and private databases, including geothermal, mining, petroleum and academic sources.
  • We visit sites, sampling fluids for chemistry if necessary, to evaluate geologic conditions.

27

  • We evaluate available data, and rank prospects in a database according to estimated size and perceived risk. For example, pre-drilled sites with extensive data are considered lower risk than “green field” sites. Both prospect types are considered critical for our continued growth.
  • We generally create a digital, spatial geographic information systems (GIS) database and 3D geologic model containing all pertinent information, including thermal water temperature gradients derived from historic drilling, geologic mapping information (e.g., formations, structure, alteration, and topography), and any available archival information about the geophysical properties of the potential resource.
  • We assess other relevant information, such as infrastructure (e.g., roads and electric transmission lines), natural features (e.g., springs and lakes), and man-made features (e.g., old mines and wells).

Our initial evaluation is usually conducted by our own staff, although we might engage outside service providers for some tasks from time to time. The costs associated with an initial evaluation vary from site to site, based on various factors, including the acreage involved and the costs, if any, of obtaining information from private databases or other sources. On average, our expenses for an initial evaluation range from approximately $10,000 to $50,000 including travel, chemical analyses, and data acquisition.

If we conclude, based on the information considered in the initial evaluation, that the geothermal resource could support a commercially viable power plant, taking into account various factors described below, we proceed to land rights acquisition.

Land Acquisition

We acquire land rights to any geothermal resources our initial evaluation indicates could potentially support a commercially viable power plant. For domestic power plants, we either lease or own the sites on which our power plants are located. For our foreign power plants, our lease rights for the power plant site are generally contained in the terms of a concession agreement or other contract with the host government or an agency thereof. In certain cases, we also enter into one or more geothermal resource leases (or subleases) or a concession or an option agreement or other agreement granting us the exclusive right to extract geothermal resources from specified areas of land, with the owners (or sublessors) of such land. In some cases, we first obtain the exploration license and once certain investment requirements are met, we can obtain the geothermal exploitation rights. This usually gives us the right to explore, develop, operate, and maintain the geothermal field, including, among other things, the right to drill wells (and if there are existing wells in the area, to alter them) and build pipelines for transmitting geothermal fluid. In certain cases, the holder of rights in the geothermal resource is a governmental entity and in other cases a private entity. Usually the duration of the lease (or sublease) and concession agreement corresponds to the duration of the relevant PPA, if any. In certain other cases, we own the land where the geothermal resource is located, in which case there are no restrictions on its utilization. The BLM and the Minerals Management Service regulate leasehold interests in federal land in the United States. These agencies have rules governing the geothermal leasing process as discussed below under “Description of Our Leases and Lands”.

For most of our current exploration sites in the United States, we acquire rights to use the geothermal resource through land leases with the BLM, with various states, or through private leases. Under these leases, we typically pay an up-front non-refundable bonus payment, which is a component of the competitive lease process. In addition, we undertake to pay nominal, fixed annual rent payments for the period from the commencement of the lease through the completion of construction. Upon the commencement of power generation, we begin to pay to the lessors long-term royalty payments based on the use of the geothermal resources as defined in the respective agreements. These payments are contingent on the power plant’s revenues. A summary of our typical lease terms is provided below under “Description of our Leases and Lands”. The up-front bonus and royalty payments vary from site to site and are based on, among other things, current market conditions.

Surveys

We conduct geological, geochemical, and/or geophysical surveys on the site we acquire. Following the acquisition of land rights for a potential geothermal resource, we conduct additional surface water analysis, soil surveys, and geologic mapping to determine proximity to possible heat flow anomalies and up-flow/permeable zones. We augment our digital database with the results of those analysis and create conceptual and digital geologic models to describe geothermal system controls. We then initiate a suite of geophysical surveys (e.g., gravity, magnetics, resistivity, magnetotellurics, reflection seismic, LiDAR, and spectral surveys) to assess surface and sub-surface structure (e.g., faults and fractures) and improve the geologic model of fluid-flow conduits and permeability controls. All pertinent geological and geophysical data are used to create three-dimensional geologic models to identify drill locations. These surveys are conducted incrementally considering relative impact and cost, and the geologic model is updated continuously.

28

We make a further determination of the commercial viability of the geothermal resource based on the results of this process, particularly the results of the geochemical surveys estimating temperature and the overall geologic model, including potential resource size. If the results from the geochemical surveys are poor (i.e., low derived resource temperatures or poor permeability) or the geologic model indicates small or deep resource, we re-evaluate the commercial viability of the geothermal resource and may not proceed to exploratory drilling. We generally only move forward with those sites that we believe have a high probability of successful development.

Exploratory Drilling

We drill one or more exploratory wells on the high priority, relatively low risk sites to confirm and/or define the geothermal resource. If we proceed to exploratory drilling, we generally use outside contractors to create access roads to drilling sites and related activities. We have continued efforts to reduce exploration costs and therefore, after obtaining drilling permits, we generally drill temperature gradient holes and/or core holes that are lower cost than slim holes (used in the past) using either our own drilling equipment, whenever possible, or outside contractors. If the obtained data supports a conclusion that the geothermal resource can support a commercially viable power plant, it will be used as an observation well to monitor and define the geothermal resource. If the core hole indicates low temperatures or does not support the geologic model of anticipated permeability, it may be plugged, and the area reclaimed. In undrilled sites, we typically step up from shallow (500-1000 feet) to deeper (2000-4000 feet) wells as confidence improves. Following proven temperature in core wells, we typically move to slim and/or full- size wells to quantify permeability.

Each year we determine and approve an exploration budget for the entire exploration activity in such year. We prioritize budget allocation between the various geothermal sites based on commercial and geological factors. The costs we incur for exploratory drilling vary from site to site based on various factors, including the accessibility of the drill site, the geology of the site, and the depth of the resource. However, on average, exploration costs, prior to drilling of a full-size well are approximately $1.0 million to $3.0 million for each site, not including land acquisition. We only reach such spending levels for sites that proved to be successful in the early stages of exploration.

At various points during our exploration activities, we re-assess whether the geothermal resource involved will support a commercially viable power plant based on information available at that time. Among other things, we consider the following factors:

  • New data and interpretations obtained concerning the geothermal resource as our exploration activities proceed, and particularly the expected MW capacity power plant the resource can be expected to support. The MW capacity can be estimated using analogous systems and/or quantitative heat in place estimates until results from drilling and flow tests quantify temperature, permeability, and resulting resource size.
  • Current and expected market conditions and rates for contracted and merchant electric power in the market(s) to be serviced.
  • Availability of transmission capacity.
  • Anticipated costs associated with further exploration activities and the relative risk of failure.
  • Anticipated costs for design and construction of a power plant at the site.
  • Anticipated costs for operation of a power plant at the site, particularly taking into account the ability to share certain types of costs (such as control rooms) with one or more other power plants that are, or are expected to be, operating near the site.

If we conclude that the geothermal resource involved will support a commercially viable power plant, we proceed to constructing a power plant at the site.

29

How We Construct Our Power Plants.

The principal phases involved in constructing one of our geothermal power plants are as follows:

  • Drilling production and injection wells.
  • Designing the well field, power plant, equipment, controls, and transmission facilities.
  • Obtaining any required permits, electrical interconnection and transmission agreements.
  • Manufacturing (or in the case of equipment we do not manufacture ourselves, purchasing) the equipment required for the power plant.
  • Assembling and constructing the well field, power plant, transmission facilities, and related facilities.

In recent years, it has taken us two to three years from the time we drill a production well until the power plant becomes operational.

Drilling Production and Injection Wells

We consider completing the drilling of the first production well to be the beginning of our construction phase for a power plant. However, this is not always sufficient for a full release for construction. The number of production wells varies from plant to plant depending on, among other things, the geothermal resource, the projected capacity of the power plant, the power generation equipment to be used and the way geothermal fluids will be re-injected through injection wells to maintain the geothermal resource and surface conditions. We generally drill the wells ourselves although in some cases we use outside contractors.

The cost for each production and injection well varies depending on, among other things, the depth and size of the well and market conditions affecting the supply and demand for drilling equipment, labor and operators. In the last five years, our typical cost for each production and injection well is approximately $3.3 million with a range of $1.0 million to $8.5 million.

Design

We usually use our own employees to design the well field and the power plant, including equipment that we manufacture and that will be needed for the power plant. In some cases, depending on complexity and location, we use third parties to help us with the design. The designs vary based on various factors, including local laws, required permits, the geothermal resource, the expected capacity of the power plant and the way geothermal fluids will be re-injected to maintain the geothermal resource and surface conditions.

Permits

We use our own employees and from time to time, depending on complexity and location, outside consultants to obtain any required permits and licenses for our power plants that are not already covered by the terms of our site leases. The permits and licenses required vary from site to site and are described below under “Environmental Permits”.

Manufacturing

Generally, we manufacture most of the power generating unit equipment we use at our power plants. Multiple sources of supply are generally available for all other equipment we do not manufacture.

Construction

We use our own employees to manage the construction work. For site grading, civil, mechanical, and electrical work we use subcontractors.

30

During fiscal year 2019, in the Electricity segment, we focused on the commencement of operations at Tungsten solar in Nevada and we began with construction of Heber Complex enhancement as well as with enhancement work in some of our operating power plants. During fiscal year 2018, we focused on the commencement of operations at McGinness Hills phase 3 in Nevada and at the Olkaria III plant expansion in Kenya and we began with construction of Steamboat Hills enhancement and Tungsten solar in Nevada as well as with enhancement work in some of our operating power plants. During fiscal year 2017, we focused on the commencement of operations at Platanares power plant in Honduras and Tungsten Mountain in Nevada. We began with construction of the Olkaria III plant expansion in Kenya and enhancement work in some of our operating power plants.

When deciding whether to continue holding lease rights and/or to pursue exploration activity, we diligently prioritize our prospective investments, taking into account resource and probability assessments in order to make informed decisions about whether a particular project will support commercial operation. As a result, during fiscal year 2019 we decided to discontinue our holding in two sites: at Glamis, California and at Lake View, Oregon. We did not have any costs that were capitalized in relation to these sites. During fiscal year 2018 we decided to discontinue our holding in one prospective site: Ruby Valley in Nevada. During fiscal year 2017 we discontinued exploration activities at four prospective sites: the Ungaran region in Indonesia, Glass Buttes - Midnight Point in Oregon and Tuscarora - phase 2 and Don A. Campbell - phase 3, in Nevada.

After conducting exploratory studies at those sites, we concluded that the respective geothermal resources would not support commercial operations. Costs associated with exploration activities at these sites were expensed accordingly (see “Write-off of Unsuccessful Exploration Activities” under Item 7 — “Management’s Discussion and Analysis of Financial Condition and Results of Operations”).

We added to our exploration inventory five prospective sites in 2019, six prospective sites in 2018 and two prospective sites in the year ended 2017 .

How We Operate and Maintain Our Power Plants

Our operations and maintenance practices are designed to minimize operating costs without compromising safety or environmental standards while maximizing plant flexibility and maintaining high reliability. Our operations and maintenance practices for geothermal power plants seek to preserve the sustainable characteristics of the geothermal resources we use to produce electricity and maintain steady-state operations within the constraints of those resources reflected in our relevant geologic and hydrologic studies. Our approach to plant management emphasizes the operational autonomy of our individual plant or complex managers and staff to identify and resolve operations and maintenance issues at their respective power plants; however, each power plant or complex draws upon our available collective resources and experience, and that of our subsidiaries. We have organized our operations such that inventories, maintenance, backup, and other operational functions are pooled within each power plant complex and provided by one operation and maintenance provider. This approach enables us to realize cost savings and enhances our ability to meet our power plant availability goals.

Safety is a key area of concern to us. We believe that the most efficient and profitable performance of our power plants can only be accomplished within a safe working environment for our employees. Our compensation and incentive program include safety as a factor in evaluating our employees, and we have a well-developed reporting system to track safety and environmental incidents, if any, at our power plants.

How We Sell Electricity

In the United States, the purchasers of power from our power plants are typically investor-owned electric utility companies or electric cooperatives including public owned utilities and recently we signed a PPA with CCAs. Outside of the United States, our purchasers are either state-owned utilities or privately-owned-entities and we typically operate our facilities under rights granted to us by a governmental agency pursuant to a concession agreement. In each case, we enter into long-term contracts (typically, PPAs) for the sale of electricity or the conversion of geothermal resources into electricity. Although previously our power plants’ revenues under a PPA generally consisted of two payments, energy payments and capacity payments, our recent PPAs provide for energy payments only. Energy payments are normally based on a power plant’s electrical output actually delivered to the purchaser measured in kWh, with payment rates either fixed or indexed to the power purchaser’s “avoided” power costs (i.e., the costs the power purchaser would have incurred itself had it produced the power it is purchasing from third parties) or rates that escalate at a predetermined percentage each year. Capacity payments are normally calculated based on the generating capacity or the declared capacity of a power plant available for delivery to the purchaser, regardless of the amount of electrical output actually produced or delivered. In addition, we have six domestic power plants located in California, Nevada and Hawaii that are eligible for capacity bonus payments under the respective PPAs upon reaching certain levels of generation, or subject to a capacity payment reduction if certain levels of generation are not reached.

31

How We Finance Our Power Plants

Historically we have funded our power plants with different sources of liquidity such as a non-recourse or limited recourse debt, lease financing, tax monetization transactions, internally generated cash, which includes funds from operation, as well as proceeds from loans under corporate credit facilities and the sale of equity interests and other securities. Such leveraged financing permits the development of power plants with a limited amount of equity contributions, but also increases the risk that a reduction in revenues could adversely affect a particular power plant’s ability to meet its debt obligations. Leveraged financing also means that distributions of dividends or other distributions by our power plant subsidiaries to us are contingent on compliance with financial and other covenants contained in the applicable financing documents.

Non-recourse debt or lease financing refers to debt or lease arrangements involving debt repayments or lease payments that are made solely from the power plant’s revenues (rather than our revenues or revenues of any other power plant) and generally are secured by the power plant’s physical assets, major contracts and agreements, cash accounts and, in many cases, our ownership interest in our affiliate that owns that power plant. These forms of financing are referred to as “project financing”.

In the event of a foreclosure after a default, our affiliate that owns the power plant would only retain an interest in the power plant assets, if any, remaining after all debts and obligations have been paid in full. In addition, incurrence of debt by a power plant may reduce the liquidity of our equity interest in that power plant because the equity interest is typically subject both to a pledge in favor of the power plant’s lenders securing the power plant’s debt and to transfer and change of control restrictions set forth in the relevant financing agreements.

Limited recourse debt refers to project financing as described above with the addition of our agreement to undertake limited financial support for our affiliate that owns the power plant in the form of certain limited obligations and contingent liabilities. These obligations and contingent liabilities may take the form of guarantees of certain specified obligations, indemnities, capital infusions and agreements to pay certain debt service deficiencies. Creditors of a project financing of a particular power plant may have direct recourse to us to the extent of these limited recourse obligations.

We have used financing structures to monetize PTCs and depreciation, such as our recent tax equity partnership transaction involving McGinness Hills phase 3, Tungsten, and an operating lease arrangement for our Puna complex power plants that recently expired in 2019.

We have also used a sale of equity interests in three of our geothermal assets and nine of our REG facilities to fund corporate needs including funding for the construction of new projects. We may use some of the same financing structures in the future.

How We Mitigate International Political Risk.

We generally purchase insurance policies to cover our equity exposure to certain political risks involved in operating in developing countries, as described below under “Insurance”. However, insurance may not cover all political risks or coverage amounts may not be sufficient.

Description of Our Leases and Lands

We have domestic leases on approximately 360,224 acres of federal, state, and private land in California, Hawaii, Nevada, New Mexico, Utah Idaho and Oregon. The approximate breakdown between federal, state and private leases and owned land is as follows:

  • 80% of the acreage under our control is leased from the U.S. government, acting mainly through the BLM;
  • 16% is leased or subleased from private landowners and/or leaseholders;
  • 3% is owned by us; and
  • 1% is leased from various states.

Each of the leases within each of the categories above has standard terms and requirements, as summarized below. Internationally, our land position includes approximately 60,903 acres.

32

BLM Geothermal Leases

Certain of our domestic project subsidiaries have entered into geothermal resources leases with the U.S. government, pursuant to which they have obtained the right to conduct their geothermal development and operations on federally-owned land. These leases are made pursuant to the Geothermal Steam Act and the lessor under such leases is the U.S. government, acting through the BLM.

BLM geothermal leases grant the geothermal lessee the right and privilege to drill for, extract, produce, remove, utilize, sell, and dispose of geothermal resources on certain lands, together with the right to build and maintain necessary improvements thereon. The actual ownership of the geothermal resources and other minerals beneath the land is retained in the federal mineral estate. The geothermal lease does not grant to the geothermal lessee the exclusive right to develop the lands, although the geothermal lessee does hold the exclusive right to develop geothermal resources within the lands. Since BLM leases do not grant to the geothermal lessee the exclusive right to use the surface of the land, BLM may grant rights to others for activities that do not unreasonably interfere with the geothermal lessee’s uses of the same land, including use, off-road vehicles, and/or wind or solar energy developments.

Typical BLM leases issued to geothermal lessees before August 8, 2005 have a primary term of ten years and will renew so long as geothermal resources are being produced or utilized in commercial quantities but cannot exceed a period of forty years after the end of the primary term. If at the end of the forty-year period geothermal steam is still being produced or utilized in commercial quantities and the lands are not needed for other purposes, the geothermal lessee will have a preferential right to renew the lease for a second forty-year term, under terms and conditions as the BLM deems appropriate.

BLM leases issued after August 8, 2005 have a primary term of ten years. If the geothermal lessee does not reach commercial production within the primary term, the BLM may grant two five-year extensions. If the lessee is drilling a well for the purposes of commercial production, the lease may be extended for five years and thereafter as long as steam is being produced and used in commercial quantities the lease may be extended for up to thirty-five years. If, at the end of the extended thirty-five-year term, geothermal steam is still being produced or utilized in commercial quantities and the lands are not needed for other purposes, the geothermal lessee will have a preferential right to renew the lease under terms and conditions as the BLM deems appropriate.

For BLM leases issued before August 8, 2005, the geothermal lessee is required to pay an annual rental fee (on a per acre basis), which escalates according to a schedule described therein, until production of geothermal steam in commercial quantities has commenced. After such production has commenced, the geothermal lessee is required to pay royalties (on a monthly basis) on the amount or value of (i) steam, (ii) by-products derived from production, and (iii) commercially de-mineralized water sold or utilized by the project (or reasonably susceptible to such sale or use).

For BLM leases issued after August 8, 2005, (i) a geothermal lessee who has obtained a lease through a non-competitive bidding process will pay an annual rental fee equal to $1.00 per acre for the first ten years and $5.00 per acre each year thereafter; and (ii) a geothermal lessee who has obtained a lease through a competitive process will pay a rental equal to $2.00 per acre for the first year, $3.00 per acre for the second through tenth year and $5.00 per acre each year thereafter. Rental fees paid before the first day of the year for which the rental is owed will be credited towards royalty payments for that year. For BLM leases issued, effective, or pending on August 5, 2005 or thereafter, royalty rates are fixed between 1.0-2.5% of the gross proceeds from the sale of electricity during the first ten years of production under the lease. The royalty rate set by the BLM for geothermal resources produced for the commercial generation of electricity but not sold in an arm’s length transaction is 1.75% for the first ten years of production and 3.5% thereafter. The royalty rate for geothermal resources sold by the geothermal lessee or an affiliate in an arm’s length transaction is 10.0% of the gross proceeds from the arm’s length sale.

In the event of a default under any BLM lease, or the failure to comply with any of the provisions of the Geothermal Steam Act or regulations issued under the Geothermal Steam Act or the terms or stipulations of the lease, the BLM may, 30 days after notice of default is provided to the relevant project, (i) suspend operations until the requested action is taken, or (ii) cancel the lease.

33

Private Geothermal Leases

Certain of our domestic project subsidiaries have entered into geothermal resources leases with private parties, pursuant to which they have obtained the right to conduct their geothermal development and operations on privately owned land. In many cases, the lessor under these private geothermal leases owns only the geothermal resource and not the surface of the land.

Typically, the leases grant our project subsidiaries the exclusive right and privilege to drill for, produce, extract, take and remove from the leased land water, brine, steam, steam power, minerals (other than oil), salts, chemicals, gases (other than gases associated with oil), and other products produced or extracted by such project subsidiary. The project subsidiaries are also granted certain non-exclusive rights pertaining to the construction and operation of plants, structures, and facilities on the leased land. Additionally, the project subsidiaries are granted the right to dispose geothermal fluid as well as the right to re-inject into the leased land water, brine, steam, and gases in a well or wells for the purpose of maintaining or restoring pressure in the productive zones beneath the leased land or other land in the vicinity. Because the private geothermal leases do not grant to the lessee the exclusive right to use the surface of the land, the lessor reserves the right to conduct other activities on the leased land in a manner that does not unreasonably interfere with the geothermal lessee’s uses of the same land, which other activities may include agricultural use (farming or grazing), recreational use and hunting, and/or wind or solar energy developments.

The leases provide for a term consisting of a primary term in the range of five to 30 years, depending on the lease, and so long thereafter as lease products are being produced or the project subsidiary is engaged in drilling, extraction, processing, or reworking operations on the leased land.

As consideration under most of our project subsidiaries’ private leases, the project subsidiary must pay to the lessor a certain specified percentage of the value “at the well” (which is not attributable to the enhanced value of electricity generation), gross proceeds, or gross revenues of all lease products produced, saved, and sold on a monthly basis. In certain of our project subsidiaries’ private leases, royalties payable to the lessor by the project subsidiary are based on the gross revenues received by the lessee from the sale or use of the geothermal substances, either from electricity production or the value of the geothermal resource “at the well”.

In addition, pursuant to the leases, the project subsidiary typically agrees to commence drilling, extraction or processing operations on the leased land within the primary term, and to conduct such operations with reasonable diligence until lease products have been found, extracted and processed in quantities deemed “paying quantities” by the project subsidiary, or until further operations would, in such project subsidiary’s judgment, be unprofitable or impracticable. The project subsidiary has the right at any time within the primary term to terminate the lease and surrender the relevant land. If the project subsidiary has not commenced any such operations on said land (or on the unit area, if the lease has been unitized), or terminated the lease within the primary term, the project subsidiary must pay to the lessor, in order to maintain its lease position, annually in advance, a rental fee until operations are commenced on the leased land.

If the project subsidiary fails to pay any installment of royalty or rental when due and if such default continues for a period of fifteen days specified in the lease, for example, after its receipt of written notice thereof from the lessor, then at the option of the lessor, the lease will terminate as to the portion or portions thereof as to which the project subsidiary is in default. If the project subsidiary defaults in the performance of any obligations under the lease, other than a payment default, and if, for a period of 90 days after written notice is given to it by the lessor of such default, the project subsidiary fails to commence and thereafter diligently and in good faith take remedial measures to remedy such default, the lessor may terminate the lease.

We do not regard any property that we lease as material unless and until we begin construction of a power plant on the property, that is, until we drill a production well on the property.

34

Description of Our Power Plants

Domestic Operating Power Plants

The following descriptions summarize certain industry metrics for our domestic operating power plants:

Power plants in the United States

Project Name Size(MW) Technology Resource Cooling Customer PPA Expiration
Brawley (1) 13 Geothermal water-cooled binary system Depends on the mix of used production wells SCE 2031
Brady Complex 26 Geothermal air and water-cooled binary system Brady - 2.6°F per year Desert Peak 2 - 2°F per year Brady — 2022 Desert Peak 2 — 2027
Don A. Campbell Complex (2) 36 Geothermal air cooled binary system Testing is in process to confirm the impact on temperature decline SCPPA Phase 1 - 2034 Phase 2 - 2036
Heber Complex (3) 81 Geothermal dual flash and binary systems using a water cooled system 1°F per year SCPPA Heber 1 — 2025 Heber 2 — 2023 Heber South — 2031
Jersey Valley 10 Geothermal air cooled binary system 3°F per year Nevada Power Company 2032
Mammoth Complex 29 Geothermal air cooled binary system Less than 0.5°F per year PG&E and Southern California Edison. G-1 and G-3 - 2034 G-2 plant - 2027
McGinness Hills Complex 143 Geothermal air cooled binary system Initial declined of 3°F observed in the past year Nevada Power Company and SCPPA. Phases 1 and 2 - 2033 Phase 3 - 2043.
Neal Hot Springs (4) 22 Geothermal air cooled binary system 1°F over the past year Idaho Power Company 2038
OREG 1 (2) 22 Geothermal air cooled binary system NA Basin Electric Power Cooperative 2031
OREG 2 (2) 22 Geothermal air cooled binary system NA Basin Electric Power Cooperative 2034
OREG 3 (2) 5.5 Geothermal air cooled binary system NA Great River Energy. 2029
OREG 4 3.5 Geothermal air cooled binary system NA Highline Electric Association. 2029
Ormesa Complex (5) 39 Geothermal water-cooled binary system and water-cooled flash system. Less than 1°F per year SCPPA under a single PPA. 2042
Puna Complex (2),(6) 38 Geothermal combined cycle and air cooled binary system The resource temperature was stable prior to the volcano eruption. The shut- down of the power plant resulted in some increase in temperature, and reservoir studies are underway to quantify any changes HELCO 2027

35

Raft River 11 Geothermal water-cooled binary system No cooling Idaho Power Company. 2032
San Emidio (7) 11 Geothermal- water-cooled binary system 3°F per year NV Energy. 2038
Steamboat Complex (8) 65 Geothermal air and water-cooled binary system and a single flash system Lower Steamboat - between 2°F to 3°F per year Steamboat Hills 4°F per year * Steamboat 2 & 3- Sierra Pacific Power Company * Galena1 & 3- Nevada Power Company * Galena 2 & Steamboat Hills- SCPPA Steamboat 2 and 3- 2022 Galena1- 2026 Steamboat Hills and Galena 2 - 2043 Galena 3- 2028
Tungsten Mountain Geothermal (9) 27 Geothermal air and water-cooled binary system 1°F per year SCPPA 2043
Tungsten Mountain solar 7 solar PV System NA SCPPA 2043
Tuscarora (10) 18 Geothermal water-cooled binary system We expect continued gradual decline in the cooling rate from less than 3°F per year to less than 1°F per year over the long term Nevada Power Company. 2032

Power plants in Rest of the World

Project Name Size (MW) Technology Resource Cooling Customer PPA Expiration
Amatitlan (Guatemala) (11) 20 Geothermal air cooled binary system and a small back pressure steam turbine (one MW) Stable INDE and another local purchaser. 2028.
Bouillante (France) (12) 15 Geothermal direct steam turbines. Stable EDF pursuant to a PPA. 2030
Olkaria III Complex (Kenya) 150 Geothermal air cooled binary system Less than1°F per year KPLC Plant 2 - 2033 Plant 1&3 - 2034 Plant 4 - 2036
Platanares (Honduras) (13) 38 Geothermal air cooled binary system 2°F per year ENEE pursuant to a PPA. 2047
Sarulla Complex - (Indonesia) (14) 330 (our share is 42) Geothermal Combined Cycle steam and binary systems Stable PLN 2047
Zunil (Guatemala) (15) 20 Geothermal air cooled binary system Stable ENDE 2034

36

(1) A new production well was drilled and added to the production header in 2019 and, as a result, we have seen an increase in generation.

(2) Indirectly owned 36.75% by Northleaf.

(3) We are currently in the process of enhancing the Heber 1 and Heber 2 power plants as discussed below.

(4) Owned 40% by Enbridge Inc. Upgrades to the power plant are in progress and expected to be completed in 2020.

(5) We are currently in the process of replacing old equipment at Ormesa with new technology equipment.

(6) On May 3, 2018, the Kilauea volcano located in close proximity to our Puna 38 MW geothermal power plant in the Puna district of Hawaii's Big Island erupted following a significant increase in seismic activity in the area. The power plant was shutdown immediately and has not been in operation since then. Following the lava flow stop, we have been working to bring the power plant back to operation, as discussed under “Recent Developments” under Item 7 - “Management’s Discussion and Analysis of Financial Condition and Results of Operations”. Recently, we have reached an agreement with HELCO and signed a new PPA that was filed with the local PUC for approval. The new PPA extends the current term until 2052 and increases the current contract capacity by 8 MW to 46MW. In addition, the new PPA has a fixed price with no escalation, regardless of changes to fossil fuel pricing, which impacts the majority of our current pricing under the existing PPA. See “Recent Developments” under Item 7 - “Management’s Discussion and Analysis of Financial Condition and Results of Operations”.

(7) A new production well was brought online in 2019, increasing the production temperature and flow.

(8) In Steamboat Hills we are replacing all the equipment and expect to add to the existing projects approximately 19MW, which is expected to be online in 2020. See below “Steamboat Hills Enhancement”.

(9) We installed a solar PV system in the Tungsten Mountain geothermal power plant to reduce internal load (i.e. parasitic).

(10) During 2019 the Tuscarora power plant was upgraded to utilize air cooling systems, which reduces the need for make-up water.

(11) Steam gathering system and heat exchangers at the Amatitlan power plant were improved in 2019.

(12) 85% of the Bouillante power plant is owned jointly by Ormat and CDC allocated 75% to Ormat and 25% to CDC.

(13) We hold the Platanares assets, including the project’s wells, land, permits and a PPA, under a BOT structure for 15 years from the date the Platanares plant commenced commercial operation on September 26, 2017. A portion of the land on which the project is located is held by us through a lease from a local municipality.

(14) The Sarulla complex experienced a reduction in generation due to well field issues at the NIL power plants.

(15) In January 2014, we signed an amendment to the PPA with INDE to extend its term by 15 years until 2034. The PPA amendment also transfers operation and management responsibilities of the Zunil geothermal field from INDE to Ormat for the term of the amended PPA in exchange for an increase in tariff. Additionally, INDE exercised its right under the PPA to become a partner in the Zunil power plant and to hold a 3% equity interest.

According to the PPA amendment, payments for the Zunil plant will be made as follows:

  • Capacity payment:
  • From 2019 and thereafter, the capacity payment will be based on actual delivered capacity and the capacity rate will be reduced.
  • Energy payment:
  • Energy payment will include a geothermal field operation and maintenance rate based on actual delivered energy in addition to the energy rate on actual delivered energy.
  • The energy rate on delivered energy will increase and will compensate the reduction in the capacity rate.

37

Future Projects

Projects Released for Construction

We have several projects in various stages of construction, including four projects that we have fully released for construction and one project that is in the early stage of construction.

These projects are expected to have a total geothermal generating capacity between 70 MW and 75 MW (representing our interest) and one 20 MW solar PV project.

Project Name Expected Size (MW) Technology Customer Expected COD Current Condition
Heber Complex 11 Geothermal air-cooled binary system SCE and SCPPA Early 2021 Permitting, Engineering and procurement ongoing. Manufacturing and construction commenced.
Steamboat Hills Enhancement 19 Geothermal air-cooled binary system SCPPA First half of 2020 Equipment delivered to site. Construction ongoing
CD4 30 Geothermal air-cooled binary system SCPPA - 16 MW 14MW Silicon Valley Clean Energy - 14 MW Monterey Bay Community Power - 14 MW End 2021 Engineering and procurement commenced
Wister solar 20 AC solar PV SDG&E 2021 Engineering and procurement ongoing
Carson Lake 10 - 15 Geothermal air-cooled binary system No PPA TBD Early stage of construction

Projects under Various Stages of Development that were not Released for Construction

We also have projects under various stages of development in the United States, Kenya and Guadeloupe. We expect to continue to explore these and other opportunities for expansion so long as they continue to meet our business objectives and investment criteria.

38

The following is a description of the projects currently under various stages of development and for which we are able to estimate their expected generating capacity. Upon completion of these projects, the generating capacity of our geothermal projects would increase by approximately between 71 MW to 76 MW (representing our interest). However, we prioritize our investments based on their readiness for continued construction and expected economics and therefore we are not planning to invest in all of such projects in 2020.

Project Location Technology Size (MW) Customer Expected COD
Bouillante power plant Guadeloupe Geothermal 10 Under discussion with EDF 2022
Dixie Meadows Nevada, U.S. Geothermal 15 TBD 2022
Steamboat solar Nevada, U.S. solar PV 5 AC SCPPA 2022
North Valley Nevada, U.S. Geothermal 15 - 20 SCPPA 2022
Puna Expansion Hawaii, U.S. Geothermal 8 HELCO 2022
Olkaria III Expansion Kenya Geothermal 10 KPLC 2022
McGinness Hills Expansion Nevada, U.S. Geothermal 8 SCPPA 2021

Future Prospects

We have a substantial land position that is expected to support future development and on which we have started or plan to start exploration activity. When deciding whether to continue holding lease rights and/or to pursue exploration activity, we diligently prioritize our prospective investments, taking into account resource and probability assessments in order to make informed decisions about whether a particular project will support commercial operation.

During fiscal year 2019, we discontinued holding a lease at two prospects at Glamis, California and at Lake View, Oregon. We added five new prospects in 2019, in the United States and Indonesia.

Our current land position is comprised of various leases, concessions and private land for geothermal resources of approximately 254,000 acres in 41 prospects including the following:

Nevada (22)

1. Alum Exploration studies in progress;
2. Baltazor Under exploration drilling;
3. Colado Under exploration drilling;
4. Crescent Valley Under exploration drilling;
5. Comstock (formerly Dixie Comstock) Under exploration drilling;
6. Edwards Creek Under exploration drilling;
7. Emigrant Exploration studies in progress;
8. Gerlach Under exploration drilling;
9. Horsehaven (formerly Beowawe) Exploration studies in progress;
10. Lee Hot Springs Exploration studies in progress;
11. Mary's River Exploration studies in progress;
12. North Valley Exploration studies in progress;
13. Juniper (formerly North Valley 2) Under exploration drilling;
14. New York Canyon Under exploration drilling;
15. Pearl Hot Springs Exploration studies in progress;
16. Pinto Hot Springs Exploration studies in progress;
17. Rhodes Marsh Exploration studies in progress;
18. South Brady Exploration studies in progress;
19. Trinity Exploration studies in progress;
20. Tungsten Mountain – Phase 2 Assessment for future expansion;
21. Tuscarora 2 Assessment for future expansion; and
22. Twin Buttes Lease acquired but no further action has been taken yet.

39

California (4)

1. Geysers Exploration studies in progress;
2. Rhyolite Plateau Exploration studies in progress;
3. Sandpiper Exploration studies in progress; and
4. Truckhaven Exploration studies in progress.

Oregon (2)

1. Crump Geyser Under exploration drilling; and
2. Vale Exploration studies in progress.

New Mexico (1)

1. Rincon Exploration studies in progress.

Utah (2)

1. Pavant Exploration studies in progress; and
2. Roosevelt Hot Springs Exploration studies in progress.

Guatemala (2)

1. Amatitlan Phase II Exploration studies in progress; and
2. Tecumburu Exploration studies in progress.

New Zealand (1)

1. Tikitere Signed BOT agreement; exploration activity is on hold.

Honduras (1)

1. San Ignacio (12 Tribes) Exploration studies in progress.

Indonesia (2)

1. Bitung Exploration studies in progress; and
2. Ijen Exploration studies in progress.

Ethiopia (4)

1. Boku Under exploration studies;
2. Dofan Under exploration studies;
3. Dugumo Fango Under exploration studies; and
4. Shashamane Under exploration studies.

40

Operations of our Product Segment

Power Units for Geothermal Power Plants

We design, manufacture, and sell power units for geothermal electricity generation, which we refer to as OECs. Our customers include contractors and geothermal plant owners and operators.

The power units are usually paid for in installments, in accordance with milestones set forth in the supply agreement. We also provide the purchaser with spare parts (either upon their request or our recommendation). We provide the purchaser with at least a 12-month warranty for such products. We provide the purchaser with performance guarantees (usually in the form of standby letters of credit), which partially terminates upon delivery of the equipment to the site and terminates in full at the end of the warranty period.

Power Units for Recovered Energy-Based Power Generation

We design, manufacture, and sell power units used to generate electricity from recovered energy or so-called “waste heat”. Our existing and target customers include interstate natural gas pipeline owners and operators, gas processing plant owners and operators, cement plant owners and operators, and other companies engaged in other energy-intensive industrial processes. We manufacture and sell the power units for recovered energy-based power generation to third parties for use in “inside-the-fence” installations or otherwise. Our customers include gas processing plant owners and operators, cement plant owners and operators and companies in the process industry.

Remote Power Units and other Generators

We design, manufacture and sell fossil fuel powered turbo-generators with capacities ranging from 200 watts to 5,000 watts, which operate unattended in extreme hot or cold climate conditions. The remote power units supply energy to remote unmanned installations and along communications lines and provide cathodic protection along gas and oil pipelines. Our customers include contractors installing gas pipelines in remote areas. In addition, we manufacture and sell generators, including heavy duty direct current generators, for various other uses. The terms for sale of the turbo-generators are similar to those for the power units we produce for power plants.

EPC of Power Plants

We engineer, procure and construct, as an EPC contractor, geothermal and recovered energy power plants on a turnkey basis, using power units we design and manufacture. Our customers are geothermal power plant owners as well as our target customers for the sale of our recovered-energy based power units described above. Unlike many other companies that provide EPC services, we believe that our advantage is in using our own manufactured equipment and thus have better quality and control over the timing and delivery of equipment and related costs. The consideration for such services is usually paid in installments, in accordance with milestones set forth in the EPC contract and related documents. We provide performance guarantees (usually in the form of standby letters of credit) securing our obligations under the contract.

In connection with the sale of our power units for geothermal power plants, power units for recovered energy-based power generation, remote power units and other generators, we enter into sales agreements, from time to time, with sales representatives for the marketing and sale of such products pursuant to which we are obligated to pay commissions to such representatives upon the sale of our products in the relevant territory covered by such agreements by such representatives or, in some cases, by other representatives in such territory.

Our manufacturing operations and products are certified ISO 9001, ISO 14001, American Society of Mechanical Engineers, and TÜV, and we are an approved supplier to many electric utilities around the world.

41

Backlog

We have a product backlog of approximately $141.9 million as of February 25, 2020, which includes revenues for the period between January 1, 2020 and February 25, 2020, compared to $216.8 million as of February 25, 2019, which included revenues for the period between January 1, 2019 and February 25, 2019.

The following is a breakdown of the Product segment backlog amount (in $ millions) by countries as of February 25, 2020:

Country Backlog Amount Percentage of Backlog
Turkey 64.0 45.1%
Chile 34.9 24.6%
New Zealand 34.1 24.0%
Taiwan 2.8 2.0%
U.S. 2.5 1.8%
Bolivia 2.4 1.7%
Others 1.2 0.8%
Total 141.9

The following is a breakdown of the Product segment backlog by technology as of February 25, 2020:

% of Total Backlog Latest Expected Completion
Geothermal 98.1% 2020
Recovered Energy 0.1% 2020
Other 1.8% 2020

Operations of our Energy Storage and Management Services Segment

Storage Projects

In addition to our Geothermal activity, we own and operate as well as working to develop energy storage projects in the United States including the following:

Under operation

Project Name Customer Location Size (MW) Duration (hours) Type of contract
ACUA PJM NJ 1 1 Merchant
Plumsted PJM NJ 20 1 Merchant
Stryker PJM NJ 20 1 Merchant
Hinesburg ISONE VT 2 2.5 Merchant

Under construction and development

Project Name Customer Location Size (MW) Duration (hours) Type of contract
Rabitt Hills ERCOT TX 10 1.25 Merchant
Valecito CAISO CA 10 4 Capacity PPA and Merchant

42

Energy Storage Pipeline

For an energy storage prospect to to move into the EPC phase, it requires an executed site control, interconnection agreement, permits from all authorities and a viable financial model. We have a substantial pipeline for future development in the United States that and we expect to commission between 150 MW and 200 MW between 2020 and 2022.

Competition

Electricity Segment

In our Electricity segment, we face competition from geothermal power plant owners and developers as well as other renewable energy providers and developers.

Competition in the Electricity segment is particularly marked in the very early stage of either obtaining the rights to the resource for development of future projects or acquiring a site already in a more advanced stage of development. From time to time and in different jurisdictions competing geothermal developers become our customers in the Product segment.

Our main competitors in the geothermal sector in the United States are CalEnergy, Calpine Corporation, Terra-Gen Power LLC, Enel Green Power S.p.A., Cyrq Energy Inc. and other smaller pure play developers. Outside the United States, in many cases our competitors are companies that are gaining experience developing geothermal projects in their own countries such as Mercury (formerly Mighty River Power) and Contact Energy in New Zealand, and local developers and steam turbine manufacturers in Indonesia. Some of our competitors are now seeking to take the local experience they have gained and develop geothermal projects in other countries. These competitors include Energy Development Corporation from the Philippines and Enel Green Power from Italy. Some Turkish developers are also focusing on the international market. Additionally, we face competition from small country-specific companies.

In obtaining new PPAs, we also face competition from companies engaged in the power generation business from other renewable energy sources, such as wind power, biomass, solar power and hydroelectric power. Increasingly we compete against these technologies combined with energy storage. In the last few years, competition from the wind and solar power generation developers has increased significantly.

As a geothermal company, we are focused on niche markets where our baseload and flexibility advantages can allow us to develop competitive projects.

Product Segment

In our Product segment, we face competition from power plant equipment manufacturers and system integrators as well as engineering or project management companies.

Our competitors among power plant equipment suppliers are divided by technology, steam turbines and binary power plant manufacturers. Our main steam turbines manufacturers competitors are industrial steam turbine manufacturers such as Mitsubishi Heavy Industries, Fuji Electric Co., Ltd. and Toshiba Corporation of Japan, GE/Nuovo Pignone brand and Ansaldo Energia of Italy.

Our binary technology competitors are binary systems manufacturers using the ORC such as Fuji Electric Co., Ltd of Japan, Mitsubishi Heavy Industries through Turboden, TICA, a Chinese air conditioning company who recently acquired Italian Exergy, Egesim, a Turkish electrical contractor who is collaborating with Atlas Copco mainly in the Turkish market and internationally, and Kaishan, a compressor manufacturer from China who develops its own projects. While we believe that we have a distinct competitive advantage based on our accumulated experience and current worldwide share of installed binary generation capacity (which is approximately 82%), an increase in competition, which we are currently experiencing, has started to affect our ability to secure new purchase orders from potential customers. The increased competition led to a reduction in the prices that we are able to charge for our binary equipment, which in turn impacted our profitability.

43

In the REG business, our competitors are other ORC manufacturers (such as GE, Exergy and Mitsubishi/Turboden), manufacturers that use Kalina technology (such as Geothermal Energy Research & Development Co., Ltd in Japan), other manufacturers of conventional steam turbines and small developers of small scale ORCs.

Currently, none of our competitors competes with us in both the Electricity and the Product segments.

In the case of proposed EPC projects we also compete with other service suppliers, such as project/engineering companies or big EPC contractors.

Energy Storage and Management Services Segment

In our Energy Storage and Management Service segment, we face competition from companies that already have established businesses in those technologies and markets as well as companies seeking to acquire established businesses and other new market entrants like us.

In the demand response markets, our Viridity business competes primarily with specialized demand management providers and traditional curtailment service providers. Viridity differentiates itself from its competitors by its proprietary software and analytical strengths, wider use cases, customer base, business model, and market presence.

The energy storage and energy management space is comprised of many companies divided into different verticals and sub verticals like independent power producers, project developers, system integrators, EPC providers, hardware suppliers (e.g. batteries, inverters, and balance of plant), scheduling coordinators, software suppliers, etc. Our proprietary software, analytical operational platform and experience in storage operation and integration with electricity markets, as well as our engineering capabilities, allow us to provide multiple value streams (value stacking) from a single storage installation. We have continued and plan to continue to grow our Viridity business in these markets.

Customers

All of our revenues from the sale of Electricity in the year ended December 31, 2019 were derived from fully-contracted energy and/or capacity payments under long-term PPAs with governmental or private utility entities. The percentage of total revenues above 5% is detailed in the table below:

Utility % of total revenues for the year ended December 31, 2019
NV Energy 17.1%
SCPPA 17.9%
KPLC 16.3%

Based on publicly available information, as of December 31, 2019, the credit ratings of our rated electric utility customers are as set forth below:

Issuer Standard & Poor’s Ratings Services Moody’s Investors Service Inc.
Southern California Edison BBB (Stable) Baa2 (Stable)
HELCO BBB- (Stable) Ratings withdrawn
Sierra Pacific Power Company A (Stable) Baa1 (Stable)
Nevada Power Company A (Stable) Baa1 (Stable)
SCPPA BBB+ (Stable) Aa2 (Stable)
PG&E D (NM) Ratings withdrawn
EDF A- (Negative) A3 (Stable)

44

The credit ratings of any power purchaser may change from time to time. There is no publicly available information with respect to the credit rating or stability of the power purchasers under the PPAs for our foreign power plants.

While we have historically been able to collect on substantially all of our receivable balances, we have received late payments and have amounts overdue from KPLC in Kenya related to our Olkaria III Complex and from ENEE in Honduras related to our Platanares power plant. We believe we will be able to collect all past due amounts.

Our revenues from the Product segment are derived from contractors, owners, or operators of power plants, process companies, and pipelines.

Raw Materials, Suppliers and Subcontractors

In connection with our manufacturing activities, we use raw materials such as steel and aluminum. We do not rely on any one supplier for the raw materials used in our manufacturing activities, as all of these raw materials are readily available from various suppliers.

We use subcontractors for some of the manufacturing activities with respect to our products components and for construction activities with respect to our power plants, which allows us to expand our construction and development capacity on an as-needed basis. We are not dependent on any one subcontractor and expect to be able to replace any subcontractor or assume such manufacturing and construction activities ourselves, if necessary or desirable, without adverse effect to our operations.

Employees

As of December 31, 2019, we employed 1,408 employees, of whom 584 were located in Israel, 578 were located in the United States and 246 were located in other countries. We expect that future growth in the number of our employees will be mainly attributable to the purchase and/or development of new power plants.

As of December 31, 2019, the only employees that are represented by a labor union are the employees of our recently acquired Bouillante power plant located in Guadeloupe. The employees in Guadeloupe are represented by the Confédération Générale du Travail de Guadeloupe. We have never experienced any labor dispute, strike or work stoppage. We consider our relations with our employees to be satisfactory. We believe our future success will depend on our continuing ability to hire, integrate, and retain qualified personnel.

In the United States, we currently do not have employees represented by unions that we recognize under collective bargaining agreements.

We have no collective bargaining agreements with respect to our Israeli employees. However, by order of the Israeli Ministry of Economy and Industry, the provisions of a collective bargaining agreement between the Histadrut (the General Federation of Labor in Israel) and the Coordination Bureau of Economic Organizations (which includes the Industrialists Association) may apply to some of our Israeli non-managerial, finance and administrative, and sales and marketing personnel. This collective bargaining agreement principally concerns cost of living pay increases, length of the workday, minimum wages and insurance for work-related accidents, annual and other vacation, sick pay, and determination of severance pay, pension contributions, and other conditions of employment. We currently provide such employees with benefits and working conditions, which are at least as favorable as the conditions specified in the collective bargaining agreement.

Insurance

We maintain business interruption insurance, casualty insurance, including flood, volcanic eruption, earthquake and cyber coverage as it relates to our property insurance policy, general liability, primary and excess liability, environmental and pollution liability, control of wells, drilling rigs, construction risks, as well as customary worker’s compensation and automobile, marine transportation insurance and such other commercial insurance as is generally carried by companies engaged in similar businesses and owning similar properties in the same general areas as us. To the extent any such casualty insurance covers us and/or any of our owned, controlled, direct or indirect affiliated or associated companies, subsidiary companies or corporations in an amount based upon the estimated replacement value and maximum foreseeable loss of our power plants (provided that earthquake, volcanic eruption and flood coverage may be subject to annual aggregate limits depending on the type and location of the power plant) and business interruption insurance coverage in an amount that also varies from power plant to power plant. As an exception, at this stage we have not secured business interruption coverage for our Puna power plant in Hawaii.

45

We generally purchase insurance policies to cover our equity exposure to certain political risks involved in operating in developing countries. We hold a global political risk insurance program for two to three years covering the significant political risk we identified as described below. This global program is issued by the global lead insurers in the private sector. Currently we hold such insurance for our Zunil, Amatitlan, Olkaria III, Platanares and Sarulla operating power plants. Such insurance policies generally cover, subject to the limitations and restrictions contained therein, losses derived from a specified governmental act, such as confiscation, expropriation, riots, and the inability to convert local currency into hard currency and, in certain cases, the breach of agreements with governmental entities, up to approximately 90% of our net equity investment.

Regulation of the Electric Utility Industry in the United States

The following is a summary overview of the electric utility industry and applicable federal and state regulations and should not be considered a full statement of the law or all issues pertaining thereto.

PURPA

PURPA and FERC's regulations thereunder exempt owners of small power production Qualifying Facilities that use geothermal resources as their primary source and other Qualifying Facilities that are 30 MW or under in size from regulation under the PUHCA 2005, from many provisions of the FPA and from state laws relating to the financial, organization and rate regulation of electric utilities.

PURPA provides the owners of power plants certain benefits described below if a power plant is a “Qualifying Facility.” A small power production facility is a Qualifying Facility if: (i) the facility does not exceed 80 MW; (ii) the primary energy source of the facility is biomass, waste, geothermal, or renewable resources, or any combination thereof, and at least 75% of the total energy input of the facility is from these sources, and fossil fuel input is limited to specified uses; and (iii) the facility, if larger than one megawatt, has filed with FERC a notice of self-certification of qualifying status, or has been certified as a Qualifying Facility by FERC. The 80 MW size limitation, however, does not apply to a facility if (i) it produces electric energy solely by the use, as a primary energy input, of solar, wind, waste or geothermal resources; and (ii) an application for certification or a notice of self-certification of qualifying status of the facility was submitted to not later than December 31, 1994, and construction of the facility commenced not later than December 31, 1999.

With respect to the FPA, FERC's regulations under PURPA do not exempt from the rate provisions of the FPA sales of energy or capacity from Qualifying Facilities larger than 20 MW in size that are made (a) pursuant to a contract executed after March 17, 2006 or (b) not pursuant to a state regulatory authority’s implementation of PURPA. The practical effect of these regulations is to require owners of Qualifying Facilities that are larger than 20 MW in size to obtain market-based rate authority from FERC if they seek to sell energy or capacity other than pursuant to a contract executed on or before March 17, 2006 or pursuant to a state regulatory authority’s implementation of PURPA.

In addition, provided that the purchasing electric utility has not been relieved from its mandatory purchase obligation, PURPA and FERC’s regulations under PURPA obligate electric utilities to purchase energy and capacity from Qualifying Facilities at either the electric utility’s avoided cost or a negotiated rate. FERC's regulations under PURPA allow FERC, upon request of a utility, to terminate a utility’s obligation to purchase energy from Qualifying Facilities upon a finding that Qualifying Facilities have nondiscriminatory access to: (i) independently administered, auction-based day ahead, and real time markets for electric energy and wholesale markets for long-term sales of capacity and electric energy; (ii) transmission and interconnection services provided by a FERC-approved regional transmission entity and administered under an open-access transmission tariff that affords nondiscriminatory treatment to all customers, and competitive wholesale markets that provide a meaningful opportunity to sell capacity, including long-term and short-term sales, and electric energy, including long-term, short-term, and real-time sales, to buyers other than the utility to which the Qualifying Facility is interconnected; or (iii) wholesale markets for the sale of capacity and electric energy that are at a minimum of comparable competitive quality as markets described in (i) and (ii) above. FERC regulations protect a Qualifying Facility’s rights under any contract or obligation involving purchases or sales that are entered into before FERC has determined that the contracting utility is entitled to relief from the mandatory purchase obligation. FERC has granted the request of California investor-owned utilities for a waiver of the mandatory purchase obligation for Qualifying Facilities larger than 20 MW in size. FERC is re-evaluating aspects of its PURPA regulations, including the 20 MW threshold.

46

We expect that our power plants in the U.S will continue to meet all of the criteria required for Qualifying Facility status under PURPA. However, since the Heber power plants have PPAs with Southern California Edison that require Qualifying Facility status to be maintained, maintaining Qualifying Facility status remains a key obligation. If any of the Heber power plants loses its Qualifying Facility status our operations could be adversely affected. Loss of Qualifying Facility status would eliminate the Heber power plants’ exemption from the FPA and thus, among other things, the rates charged by the Heber power plants in the PPAs with Southern California Edison and SCPPA would become subject to FERC regulation. Further, it is possible that the utilities that purchase power from the power plants could successfully obtain a waiver of the mandatory-purchase obligation in their service territories. For example, the three California investor-owned utilities have received such a waiver from FERC for projects larger than 20 MW. If a waiver of the mandatory purchase obligation is obtained, or if FERC reduces the 20 MW threshold or eliminates the mandatory purchase obligation, the power plants’ existing PPAs will not be affected, but the utilities will not be obligated under PURPA to renew or extend these PPAs or execute new PPAs upon the existing PPAs’ expiration.

PUHCA

Under PUHCA 2005, the books and records of a utility holding company, its affiliates, associate companies, and subsidiaries are subject to FERC and state commission review with respect to transactions that are subject to the jurisdiction of either FERC or the state commission or costs incurred by a jurisdictional utility in the same holding company system. However, if a company is a utility holding company solely with respect to Qualifying Facilities, exempt wholesale generators, or foreign utility companies, it will not be subject to review of books and records by FERC under PUHCA 2005. Qualifying Facilities or exempt wholesale generators that make only wholesale sales of electricity are not subject to state commissions’ rate regulations and, therefore, in all likelihood would not be subject to any review of their books and records by state commissions pursuant to PUHCA 2005 as long as the Qualifying Facility is not part of a holding company system that includes a utility subject to regulation in that state.

FPA

Pursuant to the FPA, FERC has exclusive jurisdiction over the rates for most wholesale sales of electricity and transmission in interstate commerce. These rates may be based on a cost of service approach or may be determined on a market basis through competitive bidding or negotiation. FERC can accept, reject or suspend rates. The rates can be suspended for up to five months, at which point the rates become effective subject to refund. FERC can order refunds for rates that are found to be “unjust and unreasonable” or “unduly discriminatory or preferential.”

Moreover, the loss of the Qualifying Facility status of any of our power plants selling energy to Southern California Edison could also permit Southern California Edison, pursuant to the terms of its PPA, to cease taking and paying for electricity from the relevant power plant and to seek refunds for past amounts paid and/or a reduction in future payments. In addition, the loss of any such status would result in the occurrence of an event of default under indenture for the OrCal Senior Secured Notes and hence would give the indenture trustee the right to exercise remedies pursuant to the indenture and the other financing documents.

Additionally, FERC possesses civil penalty authority, up to approximately $1.3 million per violation of the FPA per day. FERC can also require the disgorgement of unjust profits earned in connection with such violations of the FPA and revoke the right of the power plants to make sales at market-based rates.

Under the Energy Policy Act of 2005, the FPA was supplemented to empower FERC to ensure the reliability of the bulk electric system. Such authority required that FERC assume both oversight and enforcement roles. Pursuant to its new directive, FERC certified the North American Electric Reliability Corporation as the nation’s Electric Reliability Organization (ERO) to develop and enforce mandatory reliability standards to address medium and long-term reliability concerns. Today, enforcement of the mandatory reliability standards, including the protection of critical energy infrastructure, is a substantial function of the ERO and of FERC, which may impose penalties of up to approximately $1.3 million a day for violating mandatory reliability standards.

47

Thus, if any of the power plants were to lose Qualifying Facility status, the application of the FPA and other applicable state regulations to such power plants could require compliance with an increasingly complex regulatory regime that may be costly and greatly reduce our operational flexibility. Even if a power plant does not lose Qualifying Facility status, the owner of a Qualifying Facility/power plant in excess of 20 MW will become subject to rate regulation under the FPA for sales of energy or capacity pursuant to a contract executed after March 17, 2006 or not pursuant to a state regulatory authority’s implementation of PURPA. A decrease in existing rates or being ordered by FERC to pay refunds for rates found to be “unjust and unreasonable” or “unduly discriminatory or preferential” would likely result in a decrease in our future revenues.

State Regulation

Our power plants in California, Nevada, Oregon, and Idaho, by virtue of being Qualifying Facilities that make only wholesale sales of electricity, are not subject to rate, financial and organizational regulations applicable to electric utilities in those states. The power plants each sell or will sell their electrical output under PPAs to electric utilities (Sierra Pacific Power Company, Nevada Power Company, Southern California Edison, SCPPA and Idaho Power Company). All of the utilities except SCPPA are regulated by their respective state public utilities commissions. Sierra Pacific Power Company and Nevada Power Company, which merged and are doing business as NV Energy, are regulated by the PUCN. Southern California Edison is regulated by the CPUC.

Under Hawaii law, non-fossil generators are not subject to regulation as public utilities. Hawaii law provides that a geothermal power producer is to negotiate the rate for its output with the public utility purchaser. If such rate cannot be determined by mutual accord, the PUCH will set a just and reasonable rate. If a non-fossil generator in Hawaii is a Qualifying Facility, federal law applies to such Qualifying Facility and the utility is required to purchase the energy and capacity at its avoided cost. The rates for our power plant in Hawaii are established under a long-term PPA with HELCO.

Environmental Permits

U.S. environmental permitting regimes with respect to geothermal projects center upon several general areas of focus. The first involves land use approvals. These may take the form of Special Use Permits or Conditional Use Permits from local planning authorities or a series of development and utilization plan approvals and right of way approvals where the geothermal facility is entirely or partly on BLM or United States Forest Service lands. Certain federal approvals require a review of environmental impacts in conformance with the federal National Environmental Policy Act. In California, some local permit approvals require a similar review of environmental impacts under a state statute known as the California Environmental Quality Act. These federal and local land use approvals typically impose conditions and restrictions on the construction, scope and operation of geothermal projects.

The second category of permitting focuses on the installation and use of the geothermal wells themselves. Geothermal projects typically have three types of wells: (i) exploration wells designed to define and verify the geothermal resource, (ii) production wells to extract the hot geothermal liquids (also known as brine) for the power plant, and (iii) injection wells to inject the brine back into the subsurface resource. For example, on BLM lands in Nevada, California, Oregon, and Idaho, the well permits take the form of geothermal drilling permits for well installation. Approvals are also required to modify wells, including for use as production or injection wells. For all wells drilled in Nevada, a geothermal drilling permit must be obtained from the Nevada Division of Minerals. Those wells in Nevada to be used for injection will also require UIC permits from the Nevada Division of Environmental Protection and Bureau of Water Pollution Control. All geothermal wells drilled in Oregon require a geothermal well drilling permit from the Oregon Department of Geology and Mineral Industries. All geothermal wells drilled in Idaho require a well construction permit from the IDWR and injection wells also require UIC permitting through IDWR. Geothermal wells on private lands in California require drilling permits from the California Department of Conservation’s DOGGR. The eventual designation of these installed wells as individual production or injection wells and the ultimate closure of any wells is also reviewed and approved by DOGGR pursuant to a DOGGR-approved Geothermal Injection Program.

A third category of permits involves the regulation of potential air emissions associated with the construction and operation of wells and power plants and surface water discharges associated with construction and operations activities. Generally, each well and plant requires a preconstruction air permit and storm water discharge permit before earthwork can commence. In addition, in some jurisdictions the wells that are to be used for production require, and those used for injection may require air emissions permits to operate. Internal combustion engines and other air pollutant emissions sources at the projects may also require air emissions permits. For our projects, these permits are typically issued at the state or county level. Permits are also required to manage storm water during project construction and to manage drilling muds from well construction, as well as to manage certain discharges to surface impoundments, if any.

48

A fourth category of permits, required in Nevada, California, Oregon, and Idaho, includes ministerial permits such as building permits, hazardous materials storage and management permits, and pressure vessel operating permits. We are also required to obtain water rights permits in Nevada if water cooling is being used at the power plant. In addition to permits, there are various regulatory plans and programs that are required, including risk management plans (federal and state programs) and hazardous materials management plans (in California).

In some cases, our projects may also require permits, issued by the applicable federal agencies or authorized state agencies, regarding threatened or endangered species, permits to impact wetlands or other waters and notices of construction of structures which may have an impact on airspace. Environmental laws and regulations may change in the future that may modify the time to receive such permits and associated costs of compliance.

Our BESS projects are subject to similar permitting and regulatory compliance requirements. All of our current BESS projects are located on privately owned land and may require ministerial permits from local agencies as described above or undergo a state environmental permitting process (e.g., under the California Environmental Quality Act) with the city or county as the lead permitting agency. Storage projects are also required to comply with all applicable federal, state, and local laws and regulations, and similar to geothermal projects, storage projects may require various regulatory plans and programs including emergency action plans and fire response plans.

As of the date of this report, all of the material environmental permits and approvals currently required for our operating power plants and BESS projects have been obtained. We sometimes experience regulatory delays in obtaining various environmental permits and approvals required for projects in development and construction. These delays may lead to increases in the time and cost to complete these projects. Our operations are designed and conducted to comply with applicable environmental permit and approval requirements. Non-compliance with any such requirements could result in fines and penalties and could also affect our ability to operate the affected project.

Environmental Laws and Regulations

Our facilities and operations are subject to a number of federal, state, local and foreign environmental laws and regulations relating to development, construction and operation. In the U.S, these may include the Clean Air Act, the Clean Water Act, the Emergency Planning and Community Right-to-Know Act, the Endangered Species Act, the National Environmental Policy Act, the Resource Conservation and Recovery Act, and related state laws and regulations.

Our geothermal operations involve significant quantities of brine (substantially, all of which we reinject into the subsurface) and scale, both of which can contain materials (such as arsenic, antimony, lead, and naturally occurring radioactive materials) in concentrations that exceed regulatory limits used to define hazardous waste. We also use various substances, including isopentane and industrial lubricants that could become potential contaminants and are generally flammable. As a result, our projects are subject to domestic and foreign federal, state and local statutory and regulatory requirements regarding the generation, handling, transportation, use, storage, treatment, fugitive emissions, and disposal of hazardous substances. The cost of investigation and removal or remediation activities associated with a spill or release of such materials could be significant. Hazardous materials are also used in our equipment manufacturing operations in Israel.

Although we are not aware of any mismanagement of these materials, including any mismanagement prior to the acquisition of some of our power plants that has materially impaired any of the power plant sites, any disposal or release of these materials onto the power plant sites, other than by means of permitted injection wells, could lead to contamination of the environment and result in material cleanup requirements or other responsive obligations under applicable environmental laws.

Regulation Related to New Activity

Our recent entry into the energy storage space and planned provision of energy management and demand response require us to obtain and maintain certain additional authorizations and approvals. These include (1) authorization from FERC to make wholesale sales of energy, capacity, and ancillary services at market-based rates, and (2) membership status with eligibility to serve designated contractual functions in the ISO/RTOs of PJM, NYISO, and ERCOT. In the future, we may need to obtain and maintain similar membership and eligibility status with other ISO/RTOs in order to offer such services in their respective areas.

49

Regulation of the Electric Utility Industry in our Foreign Countries of Operation

The following is a summary overview of certain aspects of the electric industry in the foreign countries in which we have an operating geothermal power plant. As such, it should not be considered a full statement of the laws in such countries or all of the issues pertaining thereto.

Guatemala

The General Electricity Law of 1996, Decree 93-96, created a wholesale electricity market in Guatemala and established a new regulatory framework for the electricity sector. The law created a new regulatory commission, the CNEE, and a new wholesale power market administrator, the AMM, for the regulation and administration of the sector. The AMM is a private not-for-profit entity. The CNEE functions as an independent agency under the Ministry of Energy and Mines and is in charge of regulating, supervising, and controlling compliance with the electricity law, overseeing the market and setting rates for transmission services, and distribution to medium and small customers. All distribution companies must supply electricity to such customers pursuant to long-term contracts with electricity generators. Large customers can contract directly with the distribution companies, electricity generators or power marketers, or buy energy in the spot market. Guatemala has approved a Law of Incentives for the Development of Renewable Energy Power plants, Decree 52-2003, in order to promote the development of renewable energy power plants in Guatemala. This law provides certain benefits to companies utilizing renewable energy, including a 10-year exemption from corporate income tax and VAT on imports and customs duties. On September 16, 2008, CNEE issued a resolution that approved the Technical Norms for the Connection, Operation, Control and Commercialization of the Renewable Distributed Generation and Self-producers Users with Exceeding Amounts of Energy. This Technical Norm was created to regulate all aspects of generation, connection, operation, control and commercialization of electric energy produced with renewable sources to promote and facilitate the installation of new generation plants, and to promote the connection of existing generation plants which have exceeding amounts of electric energy for commercialization. It is applicable to projects with a capacity of up to 5 MW. At present, the General Electricity Law and the Law of Incentives for the Development or Renewable Energy Power Plants are still in force.

Kenya

The electric power sector in Kenya is regulated by the Kenyan Energy Act. Among other things, the Kenyan Energy Act provides for the licensing of electricity power producers and public electricity suppliers or distributors. KPLC is the major licensed public electricity supplier and has a virtual monopoly in the distribution of electricity in the country with the exception of a few off-grid, which have recently been licensed by the ERPA. The Kenyan Energy Act permits IPPs to install power generators and sell electricity to KPLC, which is owned by various private and government entities, and which currently purchases energy and capacity from other IPPs in addition to our Olkaria III complex. The electricity sector is regulated by the ERPA under the Kenyan Energy Act. KPLC’s retail electricity rates are subject to approval by the ERPA. The ERPA has an expanded mandate to regulate not just the electric power sector but the entire energy sector in Kenya. Transmission of electricity is now undertaken by KETRACO while another company, GDC, is responsible for geothermal assessment, drilling of wells and sale of steam for electricity operations to IPPs and KenGen. Both KETRACO and GDC are wholly owned by the government of Kenya. Renewable energy (principally solar, wind and biomass) is now one of the key energy sub-sectors in Kenya contributing significantly to the overall energy mix as a result of the implementation of the feed-in- tariff policy by the Ministry of Energy. Under the national constitution enacted in August 2010, formulation of energy policy (including electricity) and energy regulation are functions of the national government. However, the constitution lists the planning and development of electricity and energy regulation as a function of the county governments (i.e. the regional or local level where an individual power plant is or is intended to be located).

50

Indonesia

The 2009 Electricity Law divided the power business into two broad categories: (1) activities that supply electrical power, both public supply and captive supply (own use), such as electrical power generation, electrical power transmission, electrical power distribution and the sale of electrical power and (2) the activities involved in electrical power support such as service businesses (consulting, construction, installation, operation & maintenance, certification & training, testing etc.) and industry businesses (power tools & power equipment supply). Currently, power generation is dominated by PLN (state owned company), which controls around 70% of generating assets in Indonesia. Private sector participation is allowed through an IPP scheme . IPP appointment is done most often through tenders although IPPs can be directly appointed or selected. The law provides PLN priority rights to conduct its business nationwide . As the sole owner of transmission and distribution assets, PLN remains the only business entity involved in transmitting and distributing although the Law allows private participation. The Geothermal Law issued in 2014, endorses private participation as Geothermal IPP. The Geothermal IPP appointment is done through tender held by the Central Government. The Central Government also awards the tender winner a Geothermal License (IPB). Accordingly, the Geothermal License holder can conduct exploration and feasibility studies within five years subject to two one-year extensions, conduct well development and power plant construction and sell the electricity generated to PLN for a maximum of 30 years. Prior to the expiration of the Geothermal License, the IPP can propose to extend the license for an additional 20 years. Starting in 2017, the regulatory framework with respect to tariffs is based on PLN's existing average cost of generation (known by its Indonesian acronym, BPP) with respect to the relevant local grid cost of generation, excluding transmission and distribution costs. The Minister of Energy releases each year a list of local BPPs for each region, and the national BPP (which is an average of the local BPPs). The BPPs for a particular year are based on PLN's previous year audited generation costs. For 2017, the national BPP was set at Rp 983/kWh (equivalent to US$ cent 7.39/kWh at Rp 13,307/US$) based on PLN's 2016 audited generation costs. For geothermal, the tariff was assumed as follows: (i) if the local BPP is higher than the national BPP, the maximum tariff is the local BPP, (ii) if the local BPP is lower than or the same as the national BPP, the tariff is based on mutual agreement between PLN and the IPP. Presently, this tariff regulation has been revoked, and the government is assessing a plan to adopt a Feed in Tariff scheme for Geothermal and Renewable Energy IPP.

Guadeloupe

EDF is the transmission and distribution utility in Guadeloupe and also operates a significant portion of Guadeloupe’s fossil energy generation. There are also a number of IPPs in Guadeloupe, primarily producing renewable electricity. The electricity sector in Guadeloupe is regulated by the Commission Regulation of Energy (CRE), which also regulates EDF’s operations in mainland France and its other overseas territories. The electricity sector in Guadeloupe is characterized by both enabling features and obstacles with respect to renewable energy. One of the most influential enabling features is a French law requiring the utility to purchase power from any interconnected renewable generator. The major obstacle preventing further uptake of renewable electricity generation is the cap on variable generation at 30% of instantaneous system load.

Honduras

In 2014, Honduras approved its new Law of Electrical Industry (Decree 404-2013, and its Regulation, published in the Official Newspaper on November 18, 2015; and by Executive Accord 07-2015), which provides the legal framework for the electricity sector and replaces the previous Electricity Subsector Framework Law (Decree 158 of 1994, regulated by Accord 934 of 1997). The Law establishes technology-specific auctions for renewable energy. It creates the Regulatory Commission of Electric Power (CREE) as the entity in charge of supervising the bidding processes and the awarding of PPAs. The CREE is also responsible for granting study permits for the construction of generation projects that use renewable natural resources. Permits will have a maximum duration of two years, and will be revoked if no studies have been initiated within a period of six months and the reports required by the CREE have not been submitted. The new Law also establishes that all new capacity must be contracted through auctions and that the government can set a minimum quota for renewables in each auction. With respect to metering, after previous regulation applied legal incentives to renewable energy metering, the new law mandates utilities to buy excess power and credit it towards monthly bills and to install bi-directional meters.

Among others, the objectives of the law are to adapt the electricity sector’s legislation to the Framework Treaty for the Central American Electricity Market, which Honduras is a party to, and update the operating rules in the country’s electricity industry by incorporating structures and modern practices to increase the sector’s efficiency and competency in the production and marketing of electricity services.

With the passage of this new law, Honduras is moving into a new and open market. Under this legislation, all aspects of the market have been opened to private parties. This legislation is still being implemented within the market.

Honduras has also approved a Law of Incentives for Renewable Energy Projects, Decree 70-2007, further amended by Decree 138-2013, with additional incentives to solar PV projects, etc. The purpose, as in other countries of the region, is to promote the development of renewable energy power plants. Laws provide certain benefits to companies that generate power through renewable sources, including a 10-year exemption from corporate income tax and VAT on imports and customs duties, a fast track process for certain permits and a Sovereign Guaranty by the Central Government for the payments of the off-taker, the Public Utility Company, ENEE. At present, the Law of the Electrical Industry and the Laws of Incentives for Renewable Energy Projects are still in force.

51

Risk factors

As filed, 107,646 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following risk factors should be read carefully in connection with evaluating us and this Annual Report on Form 10-K. Certain statements in “Risk Factor” are forward-looking statements. See “Cautionary Note Regarding Forward-Looking Statements” elsewhere in the report:

Risks Related to the Company’s Business and Operation

Our financial performance depends on the successful operation of our geothermal and REG power plants, which are subject to various operational risks.

Our financial performance depends on the successful operation of our geothermal and REG power plants. In connection with such operations, we derived 72.4% of our total revenues for the year ended December 31, 2019 from the sale of electricity. The cost of operation and maintenance and the operating performance of our geothermal power and REG plants may be adversely affected by a variety of factors, including the following:

  • regular and unexpected maintenance and replacement expenditures;
  • shutdowns due to the breakdown or failure of our equipment or the equipment of the transmission serving utility;
  • labor disputes;
  • the presence of hazardous materials on our power plant sites;
  • continued availability of cooling water supply;
  • catastrophic events such as fires, explosions, earthquakes, volcanic activity, landslides, floods, releases of hazardous materials, severe weather storms or other weather events (including weather conditions associated with climate change), or similar occurrences affecting our power plants or any of the power purchasers or other third parties providing services to our power plants, such as the recent volcanic eruption that occurred in Hawaii's Big Island that impacted our Puna project, as discussed elsewhere in this Report;
  • the aging of power plants (which may reduce their availability and increase the cost of their maintenance); and
  • cyber attacks that may interrupt the operation of our power plants.

Any of these events could significantly increase the expenses incurred by our power plants or reduce the overall generating capacity of our power plants and could significantly reduce or entirely eliminate the revenues generated by one or more of our power plants, which in turn would reduce our net income and could materially and adversely affect our business, financial condition, future results and cash flows.

52

Our exploration, development, and operation of geothermal energy resources are subject to geological risks and uncertainties, which may result in decreased performance or increased costs for our power plants.

Our primary business involves the exploration, development, and operation of geothermal energy resources. These activities are subject to uncertainties that, in certain respects, are similar to those typically associated with oil and gas exploration, development, and exploitation, such as dry holes, uncontrolled releases, and pressure and temperature decline. Any of these uncertainties may increase our capital expenditures and our operating costs or reduce the efficiency of our power plants. We may not find geothermal resources capable of supporting a commercially viable power plant at exploration sites where we have conducted tests, acquired land rights, and drilled test wells, which would adversely affect our development of geothermal power plants. Further, since the commencement of their operations, several of our power plants have experienced geothermal resource cooling, uncontrolled flow and/or reservoir pressure decline in the normal course of operations. Because geothermal reservoirs are complex geological structures, we can only estimate their geographic area and sustainable output. The viability of geothermal power plants depends on different factors directly related to the geothermal resource (such as the temperature, pressure, storage capacity, transmissivity, and recharge) as well as operational factors relating to the extraction or reinjection of geothermal fluids. Our geothermal energy power plants may also suffer an unexpected decline in the capacity of their respective geothermal wells and are exposed to a risk of geothermal reservoirs not being sufficient for sustained generation of the electrical power capacity desired over time. A recent example is the Sarulla complex, which experienced a reduction in generation due to well field issues at the NIL power plant. The Sarulla complex is currently developing a remediation plan with a target to increase generation back to previous levels and we are following the remediation plans as well as assessing the accounting impact and its implication on our financial statements and our investment in the Sarulla complex.

Another aspect of geothermal operations is the management and stabilization of subsurface impacts caused by fluid injection pressures of production and injection fluids to mitigate subsidence. In the case of the geothermal resource supplying the Heber complex, pressure drawdown in the center of the well field has caused some localized ground subsidence, while pressure in the peripheral areas has caused localized ground inflation. Inflation and subsidence, if not controlled, can adversely affect farming operations and other infrastructure at or near the land surface. Costs of failing to stabilize site pressures in the Heber Complex area include repair and modification of gravity-based farm irrigation systems and municipal sewer piping and repair or replacement of a local road bridge spanning an irrigation canal.

Additionally, active geothermal areas, such as the areas in which our power plants are located, are subject to frequent low-level seismic disturbances. Also, volcanic eruptions and lava flows may happen in Hawaii, Guatemala and Indonesia. Serious seismic disturbances, volcanic eruptions and lava flows are possible and could result in damage to our power plants (or transmission lines used by customers who buy electricity from us) or equipment or degrade the quality of our geothermal resources to such an extent that we could not perform under the PPA for the affected power plant, which in turn could reduce our net income and materially and adversely affect our business, financial condition, future results and cash flow. If we suffer a serious seismic disturbance, volcanic eruptions and lava flows, our business interruption and property damage insurance may not be adequate to cover all losses sustained as a result thereof. In addition, insurance coverage may not continue to be available in the future in amounts adequate to insure against such seismic disturbances, volcanic eruptions and lava flows.

On May 3, 2018, the Kilauea volcano located in close proximity to our Puna 38 MW geothermal power plant in the Puna district of Hawaii's Big Island erupted following a significant increase in seismic activity in the area. Before it recently stopped flowing, the lava covered the wellheads of three geothermal wells, monitoring wells and the substation of the Puna complex and an adjacent warehouse that stored a drilling rig that was also consumed by the lava. Certain of the insurance companies disputed the start date for business interruption insurance coverage and we have filed a lawsuit against such insurers. We continue to coordinate with HELCO and local authorities to bring the power plant back to operation. Further details on the status of the power plant is described under "Recent Development" below. The Company continues to assess the accounting implications of this event on the assets and liabilities on its balance sheet and whether an impairment will be required. We currently expect commercial operation of the full generating capacity in the third quarter of 2020; however, this is dependent on receipt of permits, completion of the transmission network upgrade and successful field recovery. Our failure to achieve commercial operation on that timeline would adversely impact our results of operations.

In addition to our power plant in Puna, Hawaii, our power plant in Amatitlan, Guatemala is located in proximity to an active volcano. As a result of recent events impacting our Puna facility, we cannot be certain how investors will assess the risks to which our facilities are subject and whether this assessment will adversely impact perceptions of our business and our share price.

Furthermore, absent additional geologic/hydrologic studies, any increase in power generation from our geothermal power plants, failure to reinject the geothermal fluid or improper maintenance of the hydrological balance may affect the operational duration of the geothermal resource and cause it to decline in value over time and may adversely affect our ability to generate power from the relevant power plant.

53

We may decide not to implement, or may not be successful in implementing, one or more elements of our multi-year strategic plan, and the plan as implemented may not achieve its goal of enhancing shareholder value through the long-term growth of our Company

We are implementing a multi-year strategic plan to:

  • strengthen our core geothermal business in the United States as well as globally;
  • establishing market position in the energy storage market; and
  • exploring opportunities in new areas by looking for synergistic growth opportunities utilizing our core competence, market reputation as a successful company and new market opportunities focused upon environmental solution.

There are uncertainties and risks associated with our strategic plan, including with respect to implementation and outcome. We may decide to change, or to not implement, one or more elements of the plan over time or we may not be successful in implementing one or more elements of the plan, in each case for a number of reasons. For example, we may face significant challenges and risks expanding into the energy storage market (or expanding our core geothermal business), including:

  • our ability to compete with the large number of other companies pursuing similar business opportunities in energy storage and solar PV power generation, many of which already have established businesses in these areas and/or have greater financial, strategic, technological or other resources than we have;
  • our ability to obtain financing on terms we consider acceptable, or at all, which we may need, for example, to obtain any technology, personnel, intellectual property, or to acquire one or more existing businesses as a platform for our expansion, or to fund internal research and development, for energy storage and solar PV electric power generation products and services;
  • our ability to provide energy storage or solar power generation products or services that keep pace with rapidly changing technology, customer preferences, equipment costs, market conditions and other factors that are unknown to us now that will impact these markets;
  • Our ability to manage the risks and uncertainties associated with our operating storage facilities and future development of storage and geothermal projects which operate as "merchant" facilities without long-term sales agreements, including the variability of revenues and profitability of such projects;
  • our ability to devote the amount of management time and other resources required to implement this plan, while continuing to grow our core geothermal and recovered energy businesses; and
  • our ability to recruit appropriate employees.

Strengthening our core geothermal business to new customers and geographical areas will have many of the same risks and uncertainties as those outlined above.

Implementing the plan may also involve various costs, including, among other things:

  • opportunity costs associated with foregone alternative uses of our resources;
  • various expense items that will impact our current financial results; and
  • asset revaluations (for example, businesses or other assets acquired for new energy storage or solar PV power generation products or services may suffer impairment charges, as a result of rapidly changing technology, market conditions or otherwise).

These costs may not be recovered, in whole or in part, if one or more elements of the plan are not successfully implemented. These costs, or the failure to implement successfully one or more elements of the plan, could adversely affect our reputation and the reputation of our subsidiaries and could materially and adversely affect our business, financial condition, future results and cash flow.

54

Apart from the risks associated with implementing the plan, the plan itself will expose us to other risks and uncertainties once implemented. Expanding our customer base may expose us to customers with different credit profiles than our current customers. Expanding our geographic base will subject us to risks associated with doing business in new foreign countries in which we will have to learn the business and political environment. In addition, expanding into new technologies will expose us to new risks and uncertainties that are unknown to us now in addition to the risks and uncertainties that may be similar to those we now face. The success of the plan, once implemented, will depend, among other things, on our ability to manage these risks effectively.

The trading price of our common stock could decline if securities, industry analysts or our investors disagree with our strategic plan or the way we implement it accordingly, there is no assurance that the plan will enhance shareholder value through long-term growth of the Company to the extent currently anticipated by our management or at all.

Concentration of customers and regions may expose us to heightened financial exposure.

Our businesses often rely on a single customer to purchase all or a significant portion of a facility’s output. The financial performance of these facilities depends on such customer continuing to perform its obligations under a long-term agreement between the parties. A facility’s financial results could be materially and adversely affected if any of our customers fail to fulfill its contractual obligations and we are unable to find other customers to purchase at the same level of profitability. We cannot assure that such performance failures by our customers will not occur, or that if they do occur, such failures will not adversely affect the cash flows or profitability of our businesses.

For example, in the Electricity segment, we are exposed to the credit and financial condition of KPLC that buy the power generated from our Olkaria III in Kenya. In 2019, KPLC accounted for 16.3% of our total revenues. There has been a deterioration in the collection from KPLC that became slower than in the past, and as of December 31, 2019, the amount overdue from KPLC in Kenya was $40.7 million of which $24.2 million was paid in January and February of 2020. Any change in KPLC's financial condition may adversely affect us. Another example, we are exposed to the credit and financial condition of SCPPA and its municipal utility members that account for 17.9% of our total revenues, as customers that buy the output from seven of our geothermal power plants. Because our contracts with SCPPA are long-term, we may be adversely affected if the credit quality of any of these customers were to decline or if their respective financial conditions were to deteriorate or if they are otherwise unable to perform their obligations under our long-term contracts.

Another example, we are exposed to the credit and financial condition of ENEE in Honduras, which accounted for 4.6% of our total revenues in 2019. As of December 31, 2019, ENEE has an overdue amount of $20.1 million for the periods between October 2018 to April 2019, that was not paid to date. Due to obligations of the Honduran government to support our Company, we believe we will be able to collect all past due amounts, and therefore no provision for doubtful accounts has been recorded.

In the Product segment, 11.9% and 46.6%of our 2019 total revenues and Products segment revenue, respectively, were derived from our operations in Turkey and we rely on the continued geothermal development growth and government support for geothermal development in the country. Our revenue exposure to the Turkish market was significant in 2019 and we expect it to be reduced in 2020, due to slowdown in project development in the Turkish market. Adverse political developments in the relationship between Turkey and the U.S., adverse economic developments in this region including the 2018 failed coup, devaluation of the Turkish Lira, a general slowdown in the Turkish economy and an inability to obtain project and bank financing or a decline in government support for the development of geothermal power in the country could materially and adversely affect regional demand for the geothermal equipment and services we provide in the Turkish market or the prices we may charge for such equipment and services, which in turn could materially and adversely affect our Product segment profit margins and, consequently, our business, financial condition, future results and cash flows.

Ormat established a facility in Turkey in order to locally produce several power plant components that entitle our customer for increased incentives under the renewable energy laws. The use of local equipment in renewable energy based generating facilities in Turkey entitles such facilities to significant benefits under Turkish law, provided such facilities have obtained an RER Certificate from EMRA, which requires the issuance of a local certificate. If we do not obtain the local certificate, then some of our customers under the relevant supply agreements in Turkey may not be issued a RER Certificate based on the equipment we supply to them, and we will be required to make a payment to such customers equal to the amount of the expected lost benefit

55

Our international operations expose us to risks related to the application of foreign laws and regulations, any of which may adversely affect our business, financial condition, future results and cash flows.

Our foreign operations in Kenya, Turkey, Guadeloupe, Guatemala, Honduras and other countries are subject to regulation by various foreign governments and regulatory authorities and are subject to the application of foreign laws. Such foreign laws or regulations may not provide the same type of legal certainty and rights, in connection with our contractual relationships in such countries, as are afforded to our operations in the United States, which may adversely affect our ability to receive revenues or enforce our rights in connection with our foreign operations. The systems of some of these countries can be characterized by:

  • selective or inconsistent enforcement of laws or regulations, sometimes in ways that have been perceived as being motivated by political or financial considerations;
  • a perceived lack of judicial and prosecutorial independence from political, social and commercial forces;
  • a high degree of discretion on the part of the judiciary and governmental authorities;
  • legal and bureaucratic obstacles and corruption; and
  • rapid evolution of legal systems in ways that may not always coincide with market developments.

These characteristics give rise to investment risks that do not exist in countries with more established legal systems in more developed economies.

We face additional risks inherent in conducting business internationally, including compliance with laws and regulations of many jurisdictions that apply to our international operations. These laws and regulations include data privacy requirements, labor relations laws, tax laws, competition regulations, import and trade restrictions, economic sanctions, export requirements, the Foreign Corrupt Practices Act, and other local laws that prohibit corrupt payments to governmental officials or certain payments or remunerations to customers. Given the high level of complexity of these laws, there is a risk that some provisions may be breached by us, for example through fraudulent or negligent behavior of individual employees (or third parties acting on our behalf), our failure to comply with certain formal documentation requirements, or otherwise. Violations of these laws and regulations could result in fines, criminal sanctions against us, our officers or our employees, requirements to obtain export licenses, cessation of business activities in sanctioned countries, implementation of compliance programs and prohibitions on the conduct of our business. Any such violation could include prohibitions on our ability to offer our products in one or more countries and could materially damage our reputation, our brand, our ability to attract and retain employees, our business, our financial condition and our results of operations.

Furthermore, existing laws or regulations may be amended or repealed, and new laws or regulations may be enacted or issued. In addition, the laws and regulations of some countries may limit our ability to hold a majority interest in some of the power plants that we may develop or acquire, thus limiting our ability to control the development, construction and operation of such power plants, or our ability to import our products into such countries.

56

Political, economic and other conditions in the emerging economies where we operate may subject us to greater risk than in the developed U.S. economy, which may have a materially adverse effect on our business.

We have substantial operations outside of the United States, both in our Electricity segment and our Product segment. In 2019, 49.3% of our total revenues were derived from international operations, and our international operations were significantly more profitable than our U.S. operations. A substantial portion of international revenues came from Kenya and Turkey and, to a lesser extent, from Honduras, Guatemala, Guadeloupe and other countries. Thus, disturbances to and challenges facing our foreign operations, especially in Kenya and Turkey, could have impacts on our business ranging from moderate to severe. Our foreign operations subject us to significant political, economic and financial risks, which vary by country, and include:

  • changes in government policies or personnel;
  • changes in general economic conditions;
  • restrictions on currency transfer or convertibility;
  • the adoption or expansion of trade restrictions, the occurrence or escalation of a “trade war,” or other governmental action related to tariffs or trade agreements or policies among the governments of the United States and countries where we operate;
  • reduced protection for intellectual property rights in some countries;
  • changes in labor relations;
  • political instability and civil unrest, and risk of war;
  • changes in the local electricity and/or geothermal markets;
  • difficulties enforcing our rights against a governmental agency because of the doctrine of sovereign immunity and foreign sovereignty over international operations;
  • breach or repudiation of important contractual undertakings by governmental entities; and
  • expropriation and confiscation of assets and facilities, including without adequate compensation.

Electricity Segment. In 2019, the international operations of the Electricity segment accounted for 28% of our total revenues, but accounted for 52% of our gross profit, 59% of our net income and 48% of our EBITDA. A substantial portion of Electricity segment international revenues came from Kenya (which also contributed disproportionately to our gross profit and net income) and, to a lesser extent, from Guadeloupe, Guatemala and Honduras. In Kenya, any break-up or potential privatization of KPLC, the power purchase for our power plants located in Kenya, may adversely affect our Olkaria III complex and our overall results of operations. Additionally, in Guatemala the electricity sector was partially privatized, and it is currently unclear whether further privatization will occur in the future. Such developments may affect our Amatitlan and Zunil power plants if, for example, they result in changes to the prevailing tariff regime or in the identity and creditworthiness of our power purchasers.

Product Segment. With respect to our Product segment, 84% of our Product segment revenues in 2019 came from international sales, primarily Turkey. Since we primarily engage in sales in those markets where there is a geothermal reservoir, any such change might adversely affect geothermal developers in those markets and, subsequently, the ability of such developers to purchase our products.

Generally. Outbreaks of civil and political unrest and acts of terrorism have also occurred in several countries in Africa, the Middle East and Latin America, where we have significant operations, such as Kenya and Turkey. For instance, Kenya experienced numerous terrorist attacks in 2014 and 2015, and has experienced an upsurge in attacks in more recent years, including in early 2019, from extremist groups. Continued or escalated civil and political unrest and acts of terrorism in the countries in which we operate could result in our curtailing operations. In the event that countries in which we operate experience civil or political unrest or acts of terrorism, especially in events where such unrest leads to an unseating of the established government, our operations in such countries could be materially impaired. Although we generally obtain political risk insurance in connection with our foreign power plants, such political risk insurance does not mitigate all of the above-mentioned risks. In addition, insurance proceeds received pursuant to our political risk insurance policies, where applicable, may not be adequate to cover all losses sustained as a result of any covered risks and may at times be pledged in favor of the power plant lenders as collateral. Also, insurance may not be available in the future with the scope of coverage and in amounts of coverage adequate to insure against such risks and disturbances. Any or all of the changes discussed above could materially and adversely affect our business, financial condition, future results and cash flow.

57

Two of our facilities accounts for 29% of our revenues and contribute significantly to our profitability.

Our business relies significantly on the performance of our two largest projects, the McGinness Hills complex in East Nevada and Olkaria III Complex in Kenya, which together accounted for more than 30% of the total generating capacity of our Electricity segment in 2019. These two facilities accounted for 29% of our total revenues for the year ended December 31, 2019. Any disruption to the operation of these facilities would have a disproportionately adverse effect on our revenues and on our profitability.

Conditions in and around Israel, where the majority of our senior management and our main production and manufacturing facilities are located, may adversely affect our operations and may limit our ability to produce and sell our products or manage our power plants.

The majority of our senior management and our main production and manufacturing facilities are located in Israel approximately 26 miles from the border with the Gaza Strip. As such, political, economic and security conditions in Israel directly affect our operations.

The political instability and civil unrest in the Middle East and North Africa (including the ongoing civil war in Syria) as well as the increased tension between Iran and Israel have raised new concerns regarding security in the region and the potential for armed conflict or other hostilities involving Israel. We could be adversely affected by any such hostilities, the interruption or curtailment of trade between Israel and its trading partners, or a significant downturn in the economic or financial condition of Israel. In addition, the sale of products manufactured in Israel may be adversely affected in certain countries by restrictive laws, policies or practices directed toward Israel or companies having operations in Israel.

In addition, some of our employees in Israel are subject to being called upon to perform military service in Israel, and their absence may have an adverse effect upon our operations.

These events and conditions could disrupt our operations in Israel, which could materially and adversely affect our business, financial condition, future results, and cash flow.

We have significant operations globally, including in countries that may be adversely affected by political or economic instability, major hostilities or acts of terrorism, which exposes us to risks and challenges associated with conducting business internationally.

We have substantial operations outside of the U.S., both in our Electricity segment and our Product segment. Terrorist acts or other similar events could harm our business by limiting our ability to generate or transmit power and by delaying the development and construction of new generating facilities and capital improvements to existing facilities. These events, and governmental actions in response, could result in a material decrease in revenues and significant additional costs to repair and insure our assets, and could adversely affect operations by contributing to the disruption of supplies and markets for geothermal and recovered energy. Such events could also impair our ability to raise capital by contributing to financial instability and lower economic activity.

Some of our leases will terminate if we do not extract geothermal resources in “commercial quantities”, thus requiring us to enter into new leases or secure rights to alternate geothermal resources, none of which may be available on terms as favorable to us as any such terminated lease, if at all.

Most of our geothermal resource leases are for a fixed primary term, and then continue for so long as geothermal resources are extracted in “commercial quantities” or pursuant to other terms of extension. The land covered by some of our leases (approximately 293,000 acres in the U.S. and approximately 15,000 acres elsewhere) is undeveloped and has not yet produced geothermal resources in commercial quantities. Leases that cover land which remains undeveloped and does not produce, or does not continue to produce, geothermal resources in commercial quantities and leases that we allow to expire, may terminate. In the event that a lease is terminated and we determine that we will need that lease once the applicable power plant is operating, we would need to enter into one or more new leases with the owner(s) of the premises that are the subject of the terminated lease(s) in order to develop geothermal resources from, or inject geothermal resources into, such premises or secure rights to alternate geothermal resources or lands suitable for injection. We may not be able to do this or may not be able to do so without incurring increased costs, which could materially and adversely affect our business, financial condition, future results and cash flow.

58

Our BLM leases may be terminated if we fail to comply with any of the provisions of the Geothermal Steam Act or if we fail to comply with the terms or stipulations of such leases, which could materially and adversely affect our business, financial condition, future results and cash flow.

Pursuant to the terms of our BLM leases, we are required to conduct our operations on BLM-leased land in a workmanlike manner and in accordance with all applicable laws and BLM directives and to take all mitigating actions required by the BLM to protect the surface of and the environment surrounding the relevant land. Additionally, certain BLM leases contain additional requirements, some of which relate to the mitigation or avoidance of disturbance of any antiquities, cultural values or threatened or endangered plant, wildlife and species. In the event of a default under any BLM lease, or the failure to comply with such requirements, or any non-compliance with any of the provisions of the Geothermal Steam Act or regulations issued thereunder, the BLM may, 30 days after notice of default is provided to our relevant project subsidiary, suspend our operations until the requested action is taken or terminate the lease, either of which could materially and adversely affect our business, financial condition, future results and cash flow.

Some of our leases (or subleases) could terminate if the lessor (or sublessor) under any such lease (or sublease) defaults on any debt secured by the relevant property, thus terminating our rights to access the underlying geothermal resources at that location.

The fee interest in the land which is the subject of some of our leases (or subleases) may currently be or may become subject to encumbrances securing loans from third-party lenders to the lessor (or sublessor). Our rights as lessee (or sublessee) under such leases (or subleases) are or may be subject and subordinate to the rights of any such lender. Accordingly, a default by the lessor (or sublessor) under any such loan could result in a foreclosure on the underlying fee interest in the property and thereby terminate our leasehold interest and result in the shutdown of the power plant located on the relevant property and/or terminate our right of access to the underlying geothermal resources required for our operations.

Reduced levels of recovered energy required for the operation of our REG power plants may result in decreased performance of such power plants.

Our REG power plants generate electricity from recovered energy or so-called “waste heat” that is generated as a residual by-product of gas turbine-driven compressor stations and a variety of industrial processes. Any interruption in the supply of the recovered energy source, such as a result of reduced gas flows in the pipelines or reduced level of operation at the compressor stations, or in the output levels of the various industrial processes, may cause an unexpected decline in the capacity and performance of our recovered energy power plants.

Our business development activities may not be successful and our projects under construction may not commence operation as scheduled.

We are in the process of developing and constructing a number of new power plants. Our success in developing a project is contingent upon, among other things, negotiation of satisfactory engineering and construction agreements and obtaining PPAs and transmission services agreements, receipt of required governmental permits, obtaining adequate financing, and the timely implementation and satisfactory completion of field development, testing and power plant construction and commissioning. We may be unsuccessful in accomplishing any of these matters or doing so on a timely basis. Although we may attempt to minimize the financial risks attributable to the development of a project by securing a favorable PPA and applicable transmission services agreements, obtaining all required governmental permits and approvals and arranging, in certain cases, adequate financing prior to the commencement of construction, the development of a power project may require us to incur significant expenses for preliminary engineering, permitting and legal and other expenses before we can determine whether a project is feasible, economically attractive or capable of being financed.

59

Currently, we have geothermal projects and prospects under exploration, development or construction in the United States, as well as in Ethiopia, Guadeloupe, Guatemala, Honduras, Indonesia and New Zealand, and we intend to pursue the expansion of some of our existing plants and the development of other new plants. Our completion of these facilities is subject to substantial risks, including:

  • inability to secure a PPA;
  • inability to secure transmission services agreements;
  • inability to secure the required financing;
  • cost increases and delays due to unanticipated shortages of adequate resources to execute the project such as equipment, material and labor;
  • work stoppages resulting from force majeure event including riots, strikes and whether conditions;
  • inability to obtain permits, licenses and other regulatory approvals;
  • failure to secure sufficient land positions for the wellfield, power plant and rights of way;
  • failure by key contractors and vendors to timely and properly perform, including where we use equipment manufactured by others;
  • inability to secure or delays in securing the required transmission line and/or capacity;
  • adverse environmental and geological conditions (including inclement weather conditions);
  • adverse local business law;
  • our attention to other projects and activities, including those in the solar energy and energy storage sectors; and
  • changes in laws that mandate, incentivize or otherwise favor renewable energy sources.

Any one of these could give rise to delays, cost overruns, the termination of the plant expansion, construction or development or the loss (total or partial) of our interest in the project under development, construction, or expansion.

Our future growth depends, in part, on the successful enhancement of a number of our existing facilities.

Our current growth plans include enhancement and repowering of a number of our operating facilities, including the Heber, Steamboat, Ormesa, Mammoth and Puna complexes and involve replacement of old equipment and optimization of the geothermal field, including repair and enhancement of existing wells and drilling of new wells. Such enhancement and repowering are subject to geological risks and uncertainties and satisfactory completion of field development, testing, permitting and power plant construction and commissioning, which may result in delays and cost overruns.

We rely on power transmission facilities that we do not own or control.

We depend on transmission facilities owned and operated by others to deliver the power we sell from our power plants to our customers. If transmission is disrupted, or if the transmission capacity infrastructure is inadequate, of if there is a failure that requires long shutdown for repair, or if curtailment is required due to load system inefficiency, our ability to sell and deliver power to our customers may be adversely impacted and we may either incur additional costs or forego revenues. In addition, lack of access to new transmission capacity may affect our ability to develop new projects. Existing congestion of transmission capacity, as well as expansion of transmission systems and competition from other developers seeking access to expanded systems, could also affect our performance.

Our use of joint ventures may limit our flexibility with jointly owned investments.

60

We have partners in several of our plants and we may continue in the future to develop and/or acquire and/or hold properties in joint ventures with other entities when circumstances warrant the use of these structures. Ownership of assets in joint ventures is subject to risks that may not be present with other methods of ownership, including:

  • we could experience an impasse on certain decisions because we do not have sole decision-making authority, which could require us to expend additional resources on resolving such impasses or potential disputes, including arbitration or litigation;
  • our joint venture partners could have investment goals that are not consistent with our investment objectives, including the timing, terms and strategies for any investments in the projects that are owned by the joint ventures, which could affect decisions about future capital expenditures, major operational expenditures and retirement of assets, among other things;
  • our ability to transfer our interest in a joint venture to a third party may be restricted and the market for our interest may be limited;
  • our joint venture partners may be structured differently than us for tax purposes, and this could impact our ability to fully take advantage of federal tax incentives available for renewable energy projects;
  • our joint venture partners might become bankrupt, fail to fund their share of required capital contributions or fail to fulfill their obligations as a joint venture partner, which may require us to infuse our own capital into the venture on behalf of the partner despite other competing uses for such capital; and
  • our joint venture partners may have competing interests in our markets and investments in companies that compete directly or indirectly with us that could create conflict of interest issues.

Our operations could be adversely impacted by climate change.

Daily and seasonal fluctuations in temperature generally have a more significant impact on the generating capacity of geothermal energy plants than conventional power plants. Some of our power plants experience reduced generation in warm periods due to the lower heat differential between geothermal fluid and the ambient surroundings. While we generally account for the projected impact seasonal fluctuations in temperature based on our historic experience, the impact of climate change on traditional weather patterns has become more pronounced. This has reduced the certainty of our modelling efforts. For example, in 2019, we experienced prolonged elevated temperatures in the Western United States which impacted generating capacity at our facilities and adversely impacted our revenues in the fourth quarter of the year. To the extent weather conditions continue to be impacted by climate change, the generating capacity of certain of our facilities may be adversely impacted in a manner that we could not predict which may in turn adversely impact our results of operations.

Geothermal projects that we plan to develop in the future, may operate as "merchant" facilities without long-term PPAs and therefore such projects will be exposed to market fluctuations.

Geothermal projects that we plan to develop in the United States as part of our growth plans may operate as "merchant" facilities and sell electricity without long-term PPAs for some or all of their generating capacity and output. Such projects are exposed to market fluctuations. Without the benefit of long-term PPAs for these assets, we cannot be sure that we will be able to sell any or all of the power generated by these facilities at commercially attractive rates or that these facilities will be able to operate profitably. This could lead to future impairments of our property, plant and equipment resulting in economic losses and liabilities, which could have a material adverse effect on our results of operations, financial condition or cash flows.

Storage projects that we are operating, currently developing or plan to develop in the future, may operate as "merchant" facilities without long-term power services agreements for some or all of their generating capacity and output and therefore such projects will be exposed to market fluctuations.

Storage projects that we own and operate, are currently developing or plan to develop in the future, may operate as "merchant" facilities without long-term sales agreements for some or all of their generating capacity and output and therefore such projects are exposed to market fluctuations. Without the benefit of long-term services agreements for these assets, we cannot be sure that we will be able to sell any or all of the power and ancillary services provided by these facilities at commercially attractive rates or that these facilities will be able to operate profitably. This could lead to future impairments of our property, plant and equipment or to the closing of certain of our storage facilities, resulting in economic losses and liabilities, which could have a material adverse effect on our results of operations, financial condition or cash flows.

61

We may not be able to successfully integrate companies, which we acquired and may acquire in the future, which could materially and adversely affect our business, financial condition, future results and cash flow.

Our strategy is to continue to expand in the future, including through acquisitions. Integrating acquisitions is often costly, and we may not be able to successfully integrate our acquired companies with our existing operations without substantial costs, delays or other adverse operational or financial consequences. Integrating our acquired companies involves a number of risks that could materially and adversely affect our business, including:

  • failure of the acquired companies to achieve the results we expect;
  • inability to retain key personnel of the acquired companies;
  • risks associated with unanticipated events or liabilities; and
  • the difficulty of establishing and maintaining uniform standards, controls, procedures and policies, including accounting controls and procedures.

If any of our acquired companies suffers customer dissatisfaction or performance problems, this could adversely affect the reputation of our group of companies and could materially and adversely affect our business, financial condition, future results and cash flow.

The power generation industry is characterized by intense competition, and we encounter competition from electric utilities, other power producers, and power marketers that could materially and adversely affect our business, financial condition, future results and cash flow.

The power generation industry is characterized by intense competition from electric utilities, other power producers and power marketers. In recent years, there has been increasing competition in the sale of electricity, in part due to excess capacity in a number of United States markets and an emphasis on short-term or “spot” markets, and competition has contributed to a reduction in electricity prices. For the most part, we expect that power purchasers interested in long-term arrangements will engage in “competitive bid” solicitations to satisfy new capacity demands. This competition could adversely affect our ability to obtain and/or renew long-term PPAs and the price paid for electricity by the relevant power purchasers. There is also increasing competition between electric utilities. This competition has put pressure on electric utilities to lower their costs, including the cost of purchased electricity, and increasing competition in the future will put further pressure on power purchasers to reduce the prices at which they purchase electricity from us.

We face increasing competition from other companies engaged in the solar, energy storage, demand response and energy management sectors.

The solar power market is intensely competitive and rapidly evolving. We compete with many companies that have longer operating histories in this sector, larger customer bases, and greater brand recognition, as well as, in some cases, significantly greater financial and marketing resources than us. In some cases, these competitors are vertically integrated in the solar energy sector, manufacturing solar PV panels, silicon wafers, and other related products for the solar industry, which may give them an advantage in developing, constructing, owning and operating solar power projects. Our limited experience in the solar PV sector may affect our ability to successfully develop, construct, finance, and operate solar PV power projects.

We are experiencing intense competition in the energy storage, demand response and energy management markets. Our competitors in the energy storage, demand response and energy management markets include utilities, independent power producers, developers, new start-ups, and third-party investors, who compete more successfully in these markets than our Viridity business. If we are unable, as a result of increased competition, to expand our customer base or increase our market share in these rapidly growing markets, our business, financial condition, future results and cash flow could be materially and adversely affected.

62

Changes in costs and technology may significantly impact our business by making our power plants and products less competitive.

A basic premise of our business model is that generating baseload power at geothermal power plants produces electricity at a competitive price. However, traditional coal-fired systems and gas-fired systems may under certain economic conditions produce electricity at lower average prices than our geothermal plants. In addition, there are other technologies that can produce electricity such as hydroelectric systems, fuel cells, microturbines, wind turbines, energy storage systems and solar PV systems. Some of these alternative technologies currently produce electricity at higher average prices than our geothermal plants while others produce electricity at lower average prices. It is possible that technological advances and economies of scale will further reduce the cost of alternate methods of power generation. It is also possible that energy technologies will compete with our basic premise of a firm (non-intermittent) renewable baseload power source by combining renewable technologies with energy storage to provide an alternative to firm baseload energy. If this were to happen, the competitive advantage of our power plants may be significantly impaired.

Our intellectual property rights may not be adequate to protect our business.

Our existing intellectual property rights, including those we acquired in connection with the acquisition of our Viridity business, may not be adequate to protect our business. While we occasionally file patent applications. However, the patent prosecution process is expensive, time-consuming and complex and we may not be able to prepare, file, prosecute, maintain and enforce all necessary or desirable patent applications at a reasonable cost or in a timely manner. Patents may be invalidated and patents may not be issued on the basis of suchour patent applications or, if. Additionally, the scope of patent protection can be reinterpreted after issuance. Even if our patent applications do issue as patents are issued, they may not beissue in a form that is sufficiently broad to protect our technology, prevent competitors or other third parties from competing with us or otherwise provide us with any competitive advantage. In addition, any patents issued to us or for which we have use rights may be challenged, narrowed, invalidated or circumvented. Third parties may initiate opposition, interference, re-examination, post-grant review, inter partes review, nullification or derivation actions, or similar proceedings challenging the inventorship, validity, enforceability or scope of our patents. An adverse determination in any such proceeding or litigation could reduce the scope of, or invalidate our patent rights, allow third parties to commercialize our technology and compete directly with us, without payment to us, or result in our inability to commercialize our technology without infringing third-party patent rights. Such proceedings also may result in substantial cost and require significant time from our management, even if the eventual outcome is favorable to us. Our competitors or other third parties may also be able to circumvent our patents by developing similar or alternative technologies in a non-infringing manner. Consequently, we do not know whether any of our technology will be protectable or remain protected by valid and enforceable patents.

In order to safeguard our unpatented proprietary know-how, trade secrets and technology, we rely on a combination of trade secret protection and non-disclosure provisions in agreements with employees and third parties having access to confidential or proprietary information. These measures may not adequately protect us from disclosure, use, reverse engineering, infringement, misappropriation or other violation of our proprietary information and other intellectual property rights by third parties. Furthermore, non-disclosure provisions can be difficult to enforce and, even if successfully enforced, may not be entirely effective. In addition, we cannot guarantee that we have entered into non-disclosure agreements with all employees and third parties that have or may have had access to our trade secrets and other confidential or proprietary information.

Even if we adequately protect our intellectual property rights, litigation may be necessary to enforce these rights, which could result in substantial costs to us and a substantial diversion of management attention. Furthermore, attempts to enforce our intellectual property rights against third parties could also provoke these third parties to assert their own intellectual property or other rights against us, or result in a holding that invalidates or narrows the scope of our rights, in whole or in part. Our success and ability to compete also depends in part on our ability to operate without infringing, misappropriating or otherwise violating the intellectual or proprietary rights of third parties. While we have attempted to ensure that our technology and the operation of our business does not infringe other parties’ patents and other intellectual property or proprietary rights, our competitors or other third parties may assert that certain aspects of our business or technology infringe upon, misappropriate or otherwise violate their intellectual property or proprietary rights. In addition, former employers of our current, former or future employees may assert claims that such employees have improperly disclosed to us the confidential or proprietary information of these former employers. Infringement, misappropriation or other intellectual property violation claims, regardless of merit or ultimate outcome, can be expensive, hard to predict and time-consuming and can divert management’s attention from our core business. An assertion of an intellectual property infringement, misappropriation or other violation claim against us may result in adverse judgments, settlements on unfavorable terms or cause us to pay significant money damages, lose significant revenues, be prohibited from using the relevant technology or other intellectual property, or incur significant license, royalty or technology development expenses. Future litigation may also involve non-practicing entities or other intellectual property owners who have no relevant product offerings or revenue and against whom our own intellectual property may therefore provide little or no deterrence or protection.

We may experience difficulties implementing and maintaining our new enterprise resource planning system

We purchased a new enterprise resource planning (“ERP”) system and are currently in the initial phases of implementing the new system. ERP implementations are complex and time-consuming, and involve substantial expenditures on system software and implementation activities. The ERP system will be critical to our ability to provide important information to our management, obtain and deliver products, provide services and customer support, send invoices and track payments, fulfill contractual obligations, accurately maintain books and records, provide accurate, timely and reliable reports on our financial and operating results or otherwise operate our business. ERP implementations also require transformation of business and financial processes in order to reap the benefits of the ERP system; any such transformation involves risks inherent in the conversion to a new computer system, including loss of information and potential disruption to our normal operations. The implementation and maintenance of the new ERP system has required, and will continue to require, the investment of significant financial and human resources and the implementation may be subject to delays and cost overruns. In addition, we may not be able to successfully complete the implementation of the new ERP system without experiencing difficulties. Any disruptions, delays or deficiencies in the design and implementation or the ongoing maintenance of the new ERP system could adversely affect our ability to process orders, ship products, provide services and customer support, send invoices and track payments, fulfill contractual obligations, accurately maintain books and records, provide accurate, timely and reliable reports on our financial and operating results, or otherwise operate our business. Additionally, if we do not effectively implement the ERP system as planned or the system does not operate as intended, the effectiveness of our internal control over financial reporting could be adversely affected or our ability to assess it adequately could be delayed.

63

A cyber incident, cyber security breach, severe natural event or physical attack on our operational networks and information technology systems could have a material adverse effect on our financial condition, results of operations, liquidity and cash flows.

We rely on information technology systems that allow us to create, store, retain, transmit and otherwise process proprietary and sensitive or confidential information, including our business and financial information, and personal information regarding our employees and third-parties. We also rely on our operational technology systems to manufacture equipment for our energy projects, operate our power plants and provide our services. In addition, we often rely on third-party vendors to host, maintain, modify and update our systems.

Our and our third-party vendors’ technology systems can be damaged by malicious events such as cyber and physical attacks, computer viruses, malicious and destructive code, phishing attacks, denial of service or information, as well as security breaches, natural disasters, fire, power loss, telecommunications failures, employee misconduct, human error, and third parties such as traditional computer hackers, persons involved with organized crime or foreign state or foreign state-supported actors. Furthermore, our disaster recovery planning may not be sufficient for all situations. Any failure, disruptions to or decrease in the functionality of our or our third-party vendors’ operational and information technology networks could impact our ability to maintain effective internal controls over financial reporting, cause harm to the environment, the public or our employees, and significantly disrupt and damage our assets and operations or those of third parties.

We and our third-party vendors have been, and may in the future be, subject to breaches and attempts to gain unauthorized access to our information technology systems or sensitive or confidential data, or to disrupt our operations. To date, none of these breaches or attempts has, individually or in the aggregate, resulted in a security incident with a material effect on our operations or our financial condition, results of operations, liquidity, or cash flows. Despite implementation of security and control measures, we and our third-party vendors have not always been able to, and there can be no assurance that we or our third-party vendors will be able to in the future, anticipate or prevent unauthorized access to our or our third-party vendors’ operational technology networks, information technology systems or data, or the disruption of our or our third-partv vendors’ operations. The techniques used to obtain unauthorized access to our and our third-party vendors’ operational technology networks, information technology systems or data are constantly evolving and have become increasingly complex and sophisticated. Furthermore, such techniques change frequently and are often not detected until after they have been launched against a target. Therefore, we may be unable to anticipate these techniques and may not become aware in a timely manner of such a security breach, which could exacerbate any damage we experience. Such events could cause interruptions in the operation of our business, damage our operational technology networks and information technology systems, subject us to significant expenses, remediation costs, litigation, disputes, claims by third parties and regulatory actions or investigations that could result in damages, material fines and penalties, and harm to our reputation, any of which could have a material adverse effect on our financial condition, results of operations, liquidity, and cash flows. We may maintain cyber liability insurance that covers certain damages caused by cyber incidents. However, there is no guarantee that adequate insurance will continue to be available at rates that we believe are reasonable or that the costs of responding to and recovering from a cyber incident will be covered by insurance or recoverable in rates.

In addition, we are subject to various legislation, regulations, directives and guidelines from federal, state, local and foreign agencies, such as FERC, that are intended to strengthen cybersecurity measures required for information and operational technology and critical energy infrastructure and that apply to the collection, use, retention, protection, disclosure, transfer and other processing of personal information. These cybersecurity, data protection and privacy law regimes continue to evolve and may result in ever-increasing public scrutiny and escalating levels of capital expenditures, regulatory enforcement, sanctions and fines and increased costs for compliance. Failure to comply with any of these laws could result in enforcement action against us, including fines, imprisonment of company officials and public censure, any of which could harm our reputation and have a material adverse effect on our financial condition, results of operations, liquidity, and cash flows.

We previously identified a material weakness in our internal control over financial reporting and subsequently restated certain of our financial statements as a result of factors related to that weakness. This may adversely affect the accuracy and reliability of our financial statements and impact our reputation, business and the price of our common stock, as well as lead to a loss of investor confidence in us.

In connection with the change in our repatriation strategy and the related release of the U.S. income tax valuation allowance in the second quarter of 2017, we did not perform an effective risk assessment related to our internal controls over the accounting for income taxes. As a result, we identified a deficiency in the design of our internal control over financial reporting related to our accounting for income taxes, which affected the recording of income tax accounts by us in our interim and annual consolidated financial statements during 2017. Our management previously concluded that this deficiency constituted a material weakness in our internal control over financial reporting and, accordingly, our internal control over financial reporting and our disclosure controls and procedures were not effective as of December 31, 2017. A material weakness is a deficiency, or a combination of deficiencies, in internal control over financial reporting, such that there is a reasonable possibility that a material misstatement of our annual or interim consolidated financial statements will not be prevented or detected on a timely basis.

On May 16, 2018, we concluded that we would restate our previously issued consolidated financial statements as of and for the year ended December 31, 2017 to correct for (i) errors in our income tax provision, primarily related to our ability to utilize foreign tax credits in the United States prior to their expiration starting in 2027 and the resulting impact on the deferred tax asset valuation allowance, and (ii) the inappropriate netting of certain deferred income tax assets and deferred income tax liabilities across different tax jurisdictions that was not permissible under U.S. generally accepted accounting principles. In addition, we also concluded that we would revise our previously issued consolidated financial statements as of and for the years ended December 31, 2016 and December 31, 2015 to correct for errors in our income tax provision primarily related to the translation of deferred tax liabilities in a foreign subsidiary. These tax and tax-related errors also resulted in the restatement, for 2017, and revision, for 2016, of our previously issued unaudited condensed consolidated financial statements for the three months ended March 31, 2017, for the three and six months ended June 30, 2017 and 2016 and for the three and nine months ended September 30, 2017 and 2016.

64

We have made substantial progress in developing and implementing a remediation plan, as we are adding to and improving our internal processes. However, the material weakness will not be considered remediated until the applicable controls operate for a sufficient period of time and management has concluded, through testing, that these controls are operating effectively. As such, we have determined that we did not maintain an effective internal control over financial reporting as of December 31, 2019 and have a material weakness in internal control over financial reporting in accounting for income taxes. If we are unable to remediate this material weakness or we identify additional material weaknesses in our internal control over financial reporting in the future, our ability to analyze, record and report financial information accurately, to prepare our financial statements within the time periods specified by the rules and forms of the SEC and to otherwise comply with our reporting obligations under the federal securities laws, and in relation to covenants in certain debt facilities will likely be adversely affected. We may identify additional material weaknesses in our internal control over financial reporting in the future. The occurrence of, or failure to remediate, and any future material weaknesses in our internal control over financial reporting may adversely affect the accuracy and reliability of our financial statements, and our reputation, business and the price of our common stock or any other securities we may issue, as well as lead to a loss of investor confidence in us.

Risks Related to Governmental Regulations, Laws and Taxation

Our financial performance could be adversely affected by changes in the legal and regulatory environment affecting our operations.

All of our power plants are subject to extensive regulation, and therefore changes in applicable laws or regulations, or interpretations of those laws and regulations, could result in increased compliance costs, the need for additional capital expenditures or the reduction of certain benefits currently available to our power plants. The structure of domestic and foreign energy regulation currently is, and may continue to be, subject to challenges, modifications, the imposition of additional regulatory requirements, and restructuring proposals. We or our power purchasers may not be able to obtain all regulatory approvals that may be required in the future, or any necessary modifications to existing regulatory approvals, or maintain all required regulatory approvals. In addition, the cost of operation and maintenance and the operating performance of geothermal power plants may be adversely affected by changes in certain laws and regulations, including tax laws.

Any changes to applicable laws and regulations or interpretations of those laws and regulations could significantly increase the regulatory-related compliance, tax and other expenses incurred by the power plants and could significantly reduce or entirely eliminate the revenues generated by one or more of the power plants, which in turn would reduce our net income and could materially and adversely affect our business, financial condition, future results and cash flow. A recent example is the assessment letters we received from the KRA with respect to our operation in Kenya in relation to the 2013 to 2017 tax years in which the KRA demanded we pay approximately $228.0 million including interest and penalties ($177.0 million principal). We are currently at different stages of discussions with the KRA on the matters included in their letters of assessment and preliminary findings and believe our tax positions for the issues raised during the audit are sustainable based on technical merits under Kenyan tax law.

SEC rules related to conflict minerals require that we disclose the use of “conflict minerals” (including tantalum, tin, tungsten and gold) in our products. Such disclosure may force us to incur additional expenses and may damage our relationships with customers. If we utilize any of these minerals and they are necessary to the production or functionality of any of our products, we will need to conduct specified due diligence activities and file with the SEC a report disclosing, among other things, whether such minerals originate from the Democratic Republic of Congo or adjoining countries. The implementation of these SEC rules could adversely affect the sourcing, availability, and pricing of minerals used in the manufacture of certain components incorporated in our products. In addition, we expect to incur additional costs to comply with the disclosure requirements. Because our supply chain is complex, we may not be able to verify the origins of all of the minerals and metals used in our products through the diligence procedures, thus risking reputational harm. The inability to verify the origins of all mineral and metals may also create difficulties in satisfying customers who require that all of the components of our products are certified as conflict mineral free.

Pursuant to the terms of some of our PPAs with investor-owned electric utilities and publicly-owned electric utilities in states that have renewable portfolio standards, the failure to supply the contracted capacity and energy thereunder may result in the imposition of penalties.

Pursuant to the terms of certain of our PPAs, we may be required to make payments to the relevant power purchaser under certain conditions, such as shortfall in delivery of renewable energy and energy credits, and not meeting certain performance threshold requirements, as defined in the relevant PPA. The amount of payment required is dependent upon the level of shortfall in delivery or performance requirements and is recorded in the period the shortfall occurs. In addition, if we do not meet certain minimum performance requirements, the capacity of the relevant power plant may be permanently reduced. Any or all of these considerations could materially and adversely affect our business, financial condition, future results and cash flow.

65

If any of our domestic power plants loses its current Qualifying Facility status under PURPA, or if amendments to PURPA are enacted that substantially reduce the benefits currently afforded to Qualifying Facilities, our domestic operations could be adversely affected.

Most of our domestic power plants are Qualifying Facilities pursuant to PURPA, which largely exempts the power plants from the FPA, and certain state and local laws and regulations regarding rates and financial and organizational requirements for electric utilities.

If any of our domestic power plants were to lose its Qualifying Facility status, such power plant could become subject to the full scope of the FPA and applicable state regulation. The application of the FPA and other applicable state regulation to our domestic power plants could require our operations to comply with an increasingly complex regulatory regime that may be costly and greatly reduce our operational flexibility.

If a domestic power plant were to lose its Qualifying Facility status, it would become subject to full regulation as a public utility under the FPA, and the rates charged by such power plant pursuant to its PPAs may be subject to the review and approval of FERC. FERC, upon such review, may determine that the rates currently set forth in such PPAs are not appropriate and may set rates that are lower than the rates currently charged. In addition, FERC may require that the affected domestic power plant refund amounts previously paid by the relevant power purchaser to such power plant. Even if a power plant does not lose its Qualifying Facility status, pursuant to regulations issued by FERC for Qualifying Facility power plants above 20 MW, if a power plant’s PPA is terminated or otherwise expires, and the subsequent sales are not made pursuant to a state’s implementation of PURPA, that power plant will become subject to FERC’s ratemaking jurisdiction under the FPA. Moreover, a loss of Qualifying Facility status also could permit the power purchaser, pursuant to the terms of the particular PPA, to cease taking and paying for electricity from the relevant power plant or, consistent with FERC precedent, to seek refunds of past amounts paid. This could cause the loss of some or all of our revenues payable pursuant to the related PPAs, result in significant liability for refunds of past amounts paid, or otherwise impair the value of our power plants. If a power purchaser were to cease taking and paying for electricity or seek to obtain refunds of past amounts paid, there can be no assurance that the costs incurred in connection with the power plant could be recovered through sales to other purchasers or that we would have sufficient funds to make such payments. In addition, the loss of Qualifying Facility status would be an event of default under the financing arrangements currently in place for some of our power plants, which would enable the lenders to exercise their remedies and enforce the liens on the relevant power plant.

Pursuant to the Energy Policy Act of 2005, FERC also has the authority to prospectively lift the mandatory obligation of a utility under PURPA to offer to purchase the electricity from a Qualifying Facility if the utility operates in a workably competitive market. Our existing PPAs between a Qualifying Facility and a utility are not affected. If, in addition to the California utilities’ waiver of the mandatory purchase obligation for QF projects that exceed 20 MW described in the risk factor above, the utilities in the other regions in which our domestic power plants operate were to be relieved of the mandatory purchase obligation, they would not be required to purchase energy from the power plant in the region under Federal law upon termination of the existing PPA or with respect to new power plants, which could materially and adversely affect our business, financial condition, future results and cash flow. Moreover, FERC has the authority to modify its regulations relating to the utility’s mandatory purchase obligation under PURPA, which could result in the reduction in the purchase obligation of California and other utilities to a level below 20 MW, or the elimination of the purchase obligation. If that were to occur it could materially and adversely affect our business, financial condition, future results and cash flow.

The PURPA and QF described risks identified above are not likely to affect our Nevada based facilities that entered into PPAs with NV Energy as the off-taker after Nevada initially adopted its RPS in 2001. Those PPAs and the related rates agreed to for such facilities by the off-taker were not based upon PURPA or a QF mandated rate but were instead adopted as a result of a competitive bidding process and approved as part of the off-taker’s integrated resource planning process and in order for the off-taker to comply with Nevada’s RPS. While those PPAS were initially required to file for QF or EWG status with the FERC, the PPAs and their related prices for the term of the PPA were not approved by the FERC pursuant to PURPA. The PURPA and QF risks described above also are not likely to affect our Nevada and California based projects that have their PPAs with the SCPPA because SCPPA is not a regulated public utility under PURPA.

The reduction or elimination of government incentives could adversely affect our business, financial condition, future results and cash flows.

Construction and operation of our geothermal power plants and recovered energy-based power plants has benefited, and may benefit in the future, from public policies and government incentives that support renewable energy and enhance the economic feasibility of these projects in regions and countries where we operate. Such policies and incentives include PTCs (that are applicable for projects that begin construction by the end of 2020) and ITCs (for projects that begin construction by the end of 2021), accelerated depreciation tax benefits, renewable portfolio standards, carbon trading mechanisms, rebates, and mandated feed-in-tariffs, and may include similar or other incentives to end users, distributors, system integrators and manufacturers of geothermal, solar and other power products. Some of these measures have been implemented at the federal level, while others have been implemented by different states within the United States or countries outside the United States where we operate.In particular, the current U.S. presidential administration has made public statements that indicate that the administration may not be supportive of various clean energy programs and initiatives designed to curtail climate change, and has taken certain actions to eliminate or limit support for these programs and initiatives. For example, in June 2017, the administration announced that the United States would withdraw from participation in the 2015 Paris Agreement on climate change, which will become effective in November 2020. In addition, the administration has implemented and proposed policies supporting the exploration, production and use of fossil fuels and eliminating regulations enacted by the prior administration seeking to limit these activities.

66

The availability and continuation of these public policies and government incentives have a significant effect on the economics and viability of our development program and continued construction of new geothermal, recovered energy-based, solar PV facilities and, recently, energy storage projects. Any changes to such public policies, or any reduction in or elimination or expiration of such government incentives could affect us in different ways. For example, any reduction in, termination or expiration of renewable portfolio standards may result in less demand for generation from our geothermal and recovered energy-based, power plants. Any reductions in, termination or expiration of other government incentives could reduce the economic viability of, and cause us to reduce, the construction of new geothermal, recovered energy-based, solar PV or any other power plants. Policies supporting or deregulating the exploration, production and use of fossil fuels may create regulatory uncertainty in the renewable energy industry. Similarly, any such changes that affect the geothermal energy industry in a manner that is different from other sources of renewable energy, such as wind or solar, may put us at a competitive disadvantage compared to businesses engaged in the development, construction and operation of renewable power projects using such other resources. Any of the foregoing outcomes could have a material adverse effect on our business, financial condition, future results, and cash flows.

We are a holding company and our cash depends substantially on the performance of our subsidiaries and the power plants they operate, most of which is subject to restrictions and taxation on dividends and distributions.

We are a holding company whose primary assets are our ownership of the equity interests in our subsidiaries. We conduct no other business and, as a result, we depend entirely upon our subsidiaries’ earnings and cash flow.

The agreements pursuant to which some of our subsidiaries have incurred debt restrict the ability of these subsidiaries to pay dividends, make distributions or otherwise transfer funds to us prior to the satisfaction of other obligations, including the payment of operating expenses, debt service and replenishment or maintenance of cash reserves. In the case of some of our power plants that are owned jointly with other partners, there may be certain additional restrictions on dividend distributions pursuant to our agreements with those partners. In all of the foreign countries where our existing power plants are located, dividend payments to us may also be subject to withholding taxes. Each of the events described above may reduce or eliminate the aggregate amount of cash we can receive from our subsidiaries.

The costs of compliance with federal, state, local and foreign environmental laws and of obtaining and maintaining environmental permits and governmental approvals required for construction and/or operation may result in liabilities and costs (as well as any fines or penalties that may be imposed upon us in the event of any non-compliance with such laws or regulations) that could materially and adversely affect our business, financial condition, future results and cash flow and these liabilities and costs may increase in the future.

Our operations are subject to extensive environmental laws, ordinances and regulations, which may cause us to incur significant costs and liabilities. These laws, ordinances and regulations can be subject to change and such change could result in increased compliance costs, the need for additional capital expenditures, or otherwise adversely affect us. In addition, our power plants are required to comply with numerous federal, state, local and foreign statutory and regulatory environmental standards and to maintain numerous environmental permits and governmental approvals required for construction and/or operation. We may not be able to renew, maintain or obtain all environmental permits and governmental approvals required for the continued operation or further development of the power plants. We have not yet obtained certain permits and government approvals required for the completion and successful operation of power plants under construction or enhancement. Our failure to renew, maintain or obtain required permits or governmental approvals, including the permits and approvals necessary for operating power plants under construction or enhancement, could cause our operations to be limited or suspended. Finally, some of the environmental permits and governmental approvals that have been issued to the power plants contain conditions and restrictions, including restrictions or limits on emissions and discharges of pollutants and contaminants, or may have limited terms. If we fail to satisfy these conditions or comply with these restrictions, or with any statutory or regulatory environmental standards, we may become subject to regulatory enforcement action and the operation of the power plants could be adversely affected or be subject to fines, penalties or additional costs or other sanctions, including the imposition of investigatory or remedial obligations of the issuance of orders limiting or prohibiting our operations.

We could be exposed to significant liability for violations of hazardous substances laws because of the use or presence of such substances at our power plants.

Our power plants are subject to numerous domestic and foreign federal, regional, state and local statutory and regulatory standards relating to the generation, handling, transportation, use, storage, treatment and disposal of hazardous substances. We use butane, pentane, industrial lubricants, and other substances at our power plants which are or could become classified as hazardous substances. If any hazardous substances are found to have been released into the environment at or by the power plants in concentrations that exceed regulatory limits, we could become liable for the investigation and removal of those substances, regardless of their source and time of release. If we fail to comply with these laws, ordinances or regulations (or any change thereto), we could be subject to civil or criminal liability, the imposition of liens or fines, and cessation of operations, large expenditures to bring the power plants into compliance or other sanctions. Furthermore, under certain federal and states laws in the United States, we can be held liable for the cleanup of releases of hazardous substances at any of our current or former facilities or at any other locations where we arranged for disposal of those substances, even if we did not cause the release at that location or if the release complied with applicable law at the time it occurred. Liability under these laws can be joint and several. The cost of any remediation activities in connection with a spill or other release of such substances could be significant and could expose us to significant liability.

67

Current and future urbanizing activities and related residential, commercial, and industrial developments may encroach on or limit geothermal or solar PV activities in the areas of our power plants, thereby affecting our ability to utilize access, inject and/or transport geothermal resources on or underneath the affected surface areas.

Current and future urbanizing activities and related residential, commercial and industrial development may encroach on or limit geothermal activities in the areas of our power plants or construction and operation of solar PV facilities, thereby affecting our ability to utilize, access, inject, and/or transport geothermal resources on or underneath the affected surface areas or build solar PV facilities, which require large areas of relatively flat land. In particular, the Heber power plants rely on an area, which we refer to as the Heber Known Geothermal Resource Area, or Heber KGRA, for the geothermal resource necessary to generate electricity at the Heber power plants. Imperial County has adopted a “specific plan area” that covers the Heber KGRA, which we refer to as the “Heber Specific Plan Area”. The Heber Specific Plan Area allows commercial, residential, industrial and other employment-oriented development in a mixed-use orientation, which currently includes geothermal uses. Several of the landowners from whom we hold geothermal leases have expressed an interest in developing their land for residential, commercial, industrial or other surface uses in accordance with the parameters of the Heber Specific Plan Area. Currently, Imperial County’s Heber Specific Plan Area is coordinated with the cities of El Centro and Calexico. There has been ongoing underlying interest since the early 1990s to incorporate the community of Heber. While any incorporation process would likely take several years, if Heber were to be incorporated, the City of Heber could replace Imperial County as the governing land use authority, which, depending on its policies, could have a significant effect on land use and availability of geothermal resources.

Current and future development proposals within Imperial County and the City of Calexico, applications for annexations to the City of Calexico, and plans to expand public infrastructure may affect surface areas within the Heber KGRA, thereby limiting our ability to utilize, access, inject and/or transport the geothermal resource on or underneath the affected surface area that is necessary for the operation of our Heber power plants, which could adversely affect our operations and reduce our revenues.

Current construction works and urban developments in the vicinity of our Steamboat complex of power plants in Nevada may also affect future permitting for geothermal operations relating to those power plants. Such works and developments include plans for the construction of a new casino hotel and other commercial or industrial developments on land in the vicinity of our Steamboat complex.

Possible application of the new base erosion and anti-abuse tax in the United States may adversely affect us.

The Tax Act enacted in 2017 in the United States included BEAT, that could apply to us and, more importantly, could reduce the amount of tax equity that can be raised on geothermal projects on which PTCs will be claimed. The aim of the base erosion and anti-abuse tax is to prevent multinational companies from reducing their U.S. taxes by “stripping” earnings across the U.S. border by making payments to foreign affiliates that can be deducted in the United States An example of such a payment is interest on an intercompany loan or a payment to a back office in a foreign country for equipment or services. The goal of the BEAT is to ensure that multinational companies do not use cross-border payments to reduce their U.S. taxes to less than 10% (12.5% for years beginning after December 31, 2025) of an expanded definition of taxable income. BEAT requires an annual calculation. Generally, the tax only applies to certain corporations with at least $500 million in average annual gross receipts for the United States for the three prior taxable years before the calculation and with base erosion payments that account for at least 3 percent (2 percent for certain corporations) of their deductions for the taxable year. If the tax applies to us, our tax equity raised on geothermal projects on which PTCs can be claimed may be reduced, which in turn may materially and adversely affect our business, financial condition, future results and cash flow.

68

Risks Related to Economic and Financial Conditions

We may be unable to obtain the financing we need to pursue our growth strategy and any future financing we receive may be less favorable to us than our current financing arrangements, either of which may adversely affect our ability to expand our operations.

Most of our geothermal power plants generally have been financed using leveraged financing structures, consisting of non-recourse or limited recourse debt obligations. Each of our projects under development or construction and those projects and businesses we may seek to acquire, or construct will require substantial capital investment. Our continued access to capital on acceptable terms is necessary for the success of our growth strategy. Our attempts to obtain future financings may not be successful or on favorable terms.

Market conditions and other factors may not permit future project and acquisition financings on terms similar to those our subsidiaries have previously received. Our ability to arrange for financing on a substantially non-recourse or limited recourse basis, and the costs of such financing, are dependent on numerous factors, including general economic conditions, conditions in the global capital and credit markets, investor confidence, the continued success of current power plants, the credit quality of the power plants being financed, the political situation in the country where the power plant is located, and the continued existence of tax and securities laws which are conducive to raising capital. If we are not able to obtain financing for our power plants on a substantially non-recourse or limited recourse basis, we may have to finance them using recourse capital such as direct equity investments or the incurrence of additional debt by us.

Also, in the absence of favorable financing options, we may decide not to build new plants or acquire facilities from third parties. Any of these alternatives could have a material adverse effect on our growth prospects.

We may also need additional financing to implement our strategic plan. For example, our cash flow from operations and existing liquidity facilities may not be adequate to finance any acquisitions we may want to pursue or new technologies we may want to develop or acquire. Financing for acquisitions or technology development activities may not be available on the non-recourse or limited recourse basis we have historically used for our business, or on other terms we find acceptable.

Our foreign power plants and foreign manufacturing operations expose us to risks related to fluctuations in currency rates, which may reduce our profits from such power plants and operations.

Risks attributable to fluctuations in currency exchange rates can arise when any of our foreign subsidiaries incur operating or other expenses in one type of currency but receive revenues in another. In such cases, an adverse change in exchange rates can reduce such subsidiary’s ability to meet its debt service obligations, reduce the amount of cash and income we receive from such foreign subsidiary or increase such subsidiary’s overall expenses. In addition, the imposition by foreign governments of restrictions on the transfer of foreign currency abroad, or restrictions on the conversion of local currency into foreign currency, would have an adverse effect on the operations of our foreign power plants and foreign manufacturing operations, and may limit or diminish the amount of cash and income that we receive from such foreign power plants and operations.

Our power plants have generally been financed through a combination of our corporate funds and limited or non-recourse project finance debt and lease financing. If our project subsidiaries default on their obligations under such limited or non-recourse debt or lease financing, we may be required to make certain payments to the relevant debt holders, and if the collateral supporting such leveraged financing structures is foreclosed upon, we may lose certain of our power plants.

Our power plants have generally been financed using a combination of our corporate funds and limited or non-recourse project finance debt or lease financing. Limited recourse project finance debt refers to our additional agreement, as part of the financing of a power plant, to provide limited financial support for the power plant subsidiary in the form of limited guarantees, indemnities, capital contributions and agreements to pay certain debt service deficiencies. Non-recourse project finance debt or lease financing refers to financing arrangements that are repaid solely from the power plant’s revenues and are secured by the power plant’s physical assets, major contracts, cash accounts and, in many cases, our ownership interest in the project subsidiary. If our project subsidiaries default on their obligations under the relevant debt documents, creditors of a limited recourse project financing will have direct recourse to us, to the extent of our limited recourse obligations, which may require us to use distributions received by us from other power plants, as well as other sources of cash available to us, in order to satisfy such obligations. In addition, if our project subsidiaries default on their obligations under the relevant debt documents (or a default under such debt documents arises as a result of a cross-default to the debt documents of some of our other power plants) and the creditors foreclose on the relevant collateral, we may lose our ownership interest in the relevant project subsidiary or our project subsidiary owning the power plant would only retain an interest in the physical assets, if any, remaining after all debts and obligations were paid in full.

69

Possible fluctuations in the cost of construction, raw materials, commodities and drilling may materially and adversely affect our business, financial condition, future results, and cash flow.

Our manufacturing operations are dependent on the supply of various raw materials, including primarily steel and aluminum, commodities and industrial equipment components that we use. We currently obtain all such raw materials, commodities and equipment at prevailing market prices. We are not dependent on any one supplier and do not have any long-term agreements with any of our suppliers. Global events such as the ongoing corona-virus outbreak emanating from China at the beginning of 2020 that has resulted in extended shutdown of certain businesses in the region and may result in delays in the supply of raw materials and components that we purchase for our equipment manufacturing may lead to cost increases. Future cost increases of such raw materials, commodities and equipment, to the extent not otherwise passed along to our customers, could adversely affect our profit margins.

Risks Related to Force Majeure

The existence of a prolonged force majeure event or a forced outage affecting a power plant, or the transmission systems could reduce our net income and materially and adversely affect our business, financial condition, future results and cash flow.

The operation of our subsidiaries’ geothermal power plants is subject to a variety of risks discussed elsewhere in these risk factors, including events such as fires, explosions, earthquakes, landslides, floods, severe storms, volcanic eruptions, lava flow or other similar events. If a power plant experiences an occurrence resulting in a force majeure event, although our subsidiary that owns that power plant would be excused from its obligations under the relevant PPA the relevant power purchaser may not be required to make any capacity and/or energy payments with respect to the affected power plant for as long as the force majeure event continues and, pursuant to certain of our PPAs, will have the right to prematurely terminate the PPA. Additionally, to the extent that a forced outage has occurred, and if as a result the power plant fails to attain certain performance requirements under certain of our PPAs, the power purchaser may have the right to permanently reduce the contract capacity (and correspondingly, the amount of capacity payments due pursuant to such agreements in the future), seek refunds of certain past capacity payments, and/or prematurely terminate the PPA. As a consequence, we may not receive any net revenues from the affected power plant other than the proceeds from any business interruption insurance that applies to the force majeure event or forced outage after the relevant waiting period and may incur significant liabilities in respect of past amounts required to be refunded.

Threats of terrorism, natural catastrophes or public health crises and other catastrophic events may impact our operations in unpredictable ways and could adversely affect our business, financial condition, future results and cash flow.

We are subject to the potentially adverse operating and financial effects of terrorist acts and threats, natural disasters, public health crises, fire, power loss and telecommunication failures, as well as cyber-attacks, including, among others, malware, computer viruses and attachments to e-mails, phishing attacks, denial of service or information, remote interruption to the operation of our power plants and other disruptive activities of individuals or groups, including traditional computer hackers, persons involved with organized crime or foreign state or foreign state-supported actors. Our generation and transmission facilities, information technology systems and other infrastructure facilities, systems and physical assets, including our Viridity business’s VPowerTM software platform, as well as the information technology systems of our third-party vendors, could be directly or indirectly affected by such events or activities.

We operate in a highly regulated industry that requires the continued operation of sophisticated information technology systems and network infrastructure. Despite our implementation of security measures, all of our and our third-party vendors’ technology systems (and any programs or data stored thereon or therein) are vulnerable to security breaches, disruptions, failures, data leakage or unauthorized access due to such activities. Those breaches and events may result from acts of our employees, contractors or third parties. If our technology systems were to fail or be breached and we were unable to recover in a timely way, we would be unable to fulfill critical business functions, and sensitive confidential and other data could be compromised, which could adversely affect our business, financial condition, future results and cash flow. In addition, such events or activities could require significant management attention and resources and could adversely affect our reputation among customers and the public. The implementation of security guidelines and measures and maintenance of insurance, to the extent available, addressing such events or activities could significantly increase our costs. Furthermore, there is no guarantee that such security guidelines and measures will adequately anticipate or prevent such events or activities and our insurance may not cover any or all losses arising out of such events or activities.

70

A disruption of transmission or the transmission infrastructure facilities of third parties could negatively impact our business. Because generation and transmission systems are part of an interconnected system, we face the risk of possible loss of business due to a disruption caused by the impact of an event on the interconnected system within our systems or within a neighboring system. Any such disruption could adversely affect our business, financial condition, future results and cash flow.

U.S. federal income tax reform could adversely affect us.

On December 22, 2017, U.S. federal tax legislation, commonly referred to as the Tax Act was signed into law, significantly reforming the U.S. Internal Revenue Code. The Tax Act, among other things, reduces the U.S. federal corporate tax rate from the previous top marginal rate of 35% to a flat rate of 21%, imposes significant additional limitations on the deductibility of interest, allows for the expensing of certain capital expenditures, puts into effect the migration from a “worldwide” system of taxation to a territorial system and modifies or repeals many business deductions and credits, including modifying the treatment of net operating losses.

Under the Tax Act, the deductibility of “net interest” for a business is limited to 30% of adjusted taxable income. The new proposed regulations issued by Treasury applies regardless of whether the interest payment is made to a U.S. or foreign person, whether the interest recipient is related, or whether the interest recipient is exempt from U.S. tax. Further, any interest that cannot be deducted in a year can be carried forward indefinitely. For the year ended December 31, 2019 we determined to adopt the proposed regulations in advance and determined that $28.3 million of interest expense cannot be deducted in the current year but can be carried forward indefinitely.

We continue to examine the impact the Tax Act may have on our business. Notwithstanding the reduction in the corporate income tax rate, the overall impact of the Tax Act is uncertain, and our business, financial condition, future results and cash flow, as well as our stock price, could be adversely affected.

Risks Related to Our Stock

A substantial percentage of our common stock is held by stockholders whose interests may conflict with the interests of our other stockholders.

On July 26, 2017, ORIX purchased approximately 22% of our shares of common stock outstanding. Pursuant to the Governance Agreement between us and ORIX entered into in connection with this stock purchase transaction, ORIX has the right to designate three directors to our Board for as long as ORIX and its affiliates collectively hold at least 18% of the voting power of all of our outstanding voting securities, the right to representation on certain committees of our Board as well as preemptive rights pursuant to the Governance Agreement. In addition, the Governance Agreement provides ORIX preemptive rights in the event we issue common stock or other securities that entitle the holder to vote for the election of directors. ORIX may also exercise certain registration rights pursuant to the Registration Rights Agreement between us and ORIX.

As a result of these rights and ORIX’s beneficial ownership of our common stock, ORIX could exert influence through its Board representation on our and our subsidiaries’ business, operations and management, including our strategic plans, or, as a significant stockholder, on matters submitted to a vote of our stockholders, including mergers, consolidations and the sale of all or substantially all of our assets. This concentration of ownership of our common stock could delay or prevent proxy contests, mergers, tender offers, or other purchases of our common stock that might otherwise give our stockholders the opportunity to realize a premium over the then-prevailing market price for our shares. If ORIX exercises its registration rights to require us to register for sale the common stock held by ORIX or ORIX otherwise sells its common stock in the public markets, the price of our common stock may decline. This concentration of ownership may also adversely affect the liquidity of our common stock.

71

The price of our common stock may fluctuate substantially, and your investment may decline in value.

The market price of our common stock may be highly volatile and may fluctuate substantially due to many factors, including:

  • actual or anticipated fluctuations in our results of operations including as a result of seasonal variations in our Electricity segment-based revenues or variations from year-to-year in our Product segment-based revenues;
  • variance in our financial performance from the expectations of market analysts;
  • conditions and trends in the end markets we serve, and changes in the estimation of the size and growth rate of these markets;
  • our ability to integrate acquisitions;
  • announcements of significant contracts by us or our competitors;
  • changes in our pricing policies or the pricing policies of our competitors;
  • restatements of historical financial results and changes in financial forecasts;
  • loss of one or more of our significant customers;
  • legislation;
  • changes in market valuation or earnings of our competitors;
  • the trading volume of our common stock;
  • the trading of our common stock on multiple trading markets, which takes place in different currencies and at different times; and
  • general economic conditions.

In addition, the stock market in general, and the NYSE and the market for energy companies in particular, have experienced extreme price and volume fluctuations that have often been unrelated or disproportionate to the operating performance of particular companies affected. These broad market and industry factors may materially harm the market price of our common stock, regardless of our operating performance. In the past, following periods of volatility in the market price of a company’s securities, securities class-action litigation has often been instituted against that company. Such litigation, if instituted against us, such as the recent class action filed on June 2018 by Mac Costas and discussed elsewhere in this report, could result in substantial costs and a diversion of management’s attention and resources, which could materially harm our business, financial condition, future results and cash flow.

Properties

As filed, 968 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

We currently lease corporate offices at 6140 Plumas street Reno, Nevada 89519 to which we moved in the second quarter of 2018. We also occupy an approximately 807,000 square foot office and manufacturing facility located in the Industrial Park of Yavne, Israel, which we lease from the Israel Land Administration. See Item 13 — “Certain Relationships and Related Transactions”. In Turkey, we established and leased a facility to locally produce power plant components to our local customers. We also lease small offices in each of the countries in which we operate.

We believe that our current offices and manufacturing facilities will be adequate for our operations as currently conducted.

Each of our power plants is located on property leased or owned by us or one of our subsidiaries or is a property that is subject to a concession agreement.

Information and descriptions of our plants and properties are included in Item 1 — “Business”, of this annual report.

As filed, 245 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The information required with respect to this item can be found under “Commitments and Contingencies” in Note 22 of notes to the consolidated financial statements contained in this annual report and is incorporated by reference into this Item 8.

Management's discussion and analysis

As filed, 142,120 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

You should read the following discussion and analysis of our results of operations, financial condition and liquidity in conjunction with our consolidated financial statements and the related notes. Some of the information contained in this discussion and analysis or set forth elsewhere in this annual report including information with respect to our plans and strategies for our business, statements regarding the industry outlook, our expectations regarding the future performance of our business, and the other non-historical statements contained herein are forward-looking statements. See “Cautionary Note Regarding Forward-Looking Statements.” You should also review Item 1A — “Risk Factors” for a discussion of important factors that could cause actual results to differ materially from the results described herein or implied by such forward-looking statements.

General

Overview of Fiscal Year 2019 Revenues

For the year ended December 31, 2019, our total revenues increased by 3.7% (from $719.3 million to $746.0 million) over the previous year.

For the year ended December 31, 2019, Electricity segment revenues were $540.3 million, compared to $509.9 million for the year ended December 31, 2018, an increase of 6.0%. Product segment revenues for the year ended December 31, 2019 were $191.0 million, compared to $201.7 million for the year ended December 31, 2018, a decrease of 5.3%. Energy Storage and Management Services segment revenues for the year ended December 31, 2019 were $14.7 million, compared to $7.6 million for the year ended December 31, 2018.

During the years ended December 31, 2019 and 2018, our consolidated power plants generated 6,238,272 MWh and 5,857,963 MWh, respectively, an increase of 6.5%.

76

For the year ended December 31, 2019, our Electricity segment generated 72.4% of our total revenues (70.9% in 2018), while our Product segment generated 25.6% of our total revenues (28.0% in 2018), and our Energy Storage and Management Services segment generated 2.0% of our total revenues (1.1% in 2018).

For the year ended December 31, 2019, approximately 97.6% of our Electricity segment revenues were from PPAs with fixed energy rates which are not affected by fluctuations in energy commodity prices. We have variable price PPAs in California and Hawaii, which provide for payments based on the local utilities’ avoided cost, which is the incremental cost that the power purchaser avoids by not having to generate such electrical energy itself or purchase it from others, as follows:

  • The energy rates under the PPAs in California for each Heber 2 power plant in the Heber Complex and the G2 power plant in the Mammoth Complex, a total of between 30 to 40 MW, change primarily based on fluctuations in natural gas prices.
  • The prices paid for electricity pursuant to the 25 MW PPA for the Puna Complex in Hawaii change primarily as a result of variations in the price of oil as well as other commodities. We recently signed a new PPA related to Puna with fixed prices (see "Recent Developments" below).

To comply with obligations under their respective PPAs, certain of our project subsidiaries are structured as special purpose, bankruptcy remote entities and their assets and liabilities are ring-fenced. Such assets are not generally available to pay our debt, other than debt at the respective project subsidiary level. However, these project subsidiaries are allowed to pay dividends and make distributions of cash flows generated by their assets to us, subject in some cases to restrictions in debt instruments, as described below.

Electricity segment revenues are also subject to seasonal variations and are affected by higher-than-average ambient temperatures, as described below under “Seasonality”.

Revenues attributable to our Product segment are based on the sale of equipment, EPC contracts and the provision of various services to our customers. Product segment revenues may vary from period to period because of the timing of our receipt of purchase orders and the progress of our equipment manufacturing and execution of the relevant project.

Revenues attributable to our Energy Storage and Management Services segment are derived primarily from BSAAS systems, demand response and energy management services and may fluctuate between period to period. Pricing of such services and products are dependent on market supply and demand trends, market volatility, the need and price for ancillary services and other factors that may change over time.

Our management assesses the performance of our operating segments differently. In the case of our Electricity segment, when making decisions about potential acquisitions or the development of new projects, management typically focuses on the internal rate of return of the relevant investment, technical and geological matters and other business considerations. Management evaluates our operating power plants based on revenues, expenses, and EBITDA, and our projects that are under development based on costs attributable to each such project. Management evaluates the performance of our Product segment based on the timely delivery of our products, performance quality of our products, revenues and costs actually incurred to complete customer orders compared to the costs originally budgeted for such orders. We evaluate Energy Storage and Management Services segment performance similar to the Electricity segment with respect to projects that we own and operate and similar to the Product segment when we provide services to third parties.

Recent Developments

The most significant recent developments for our company and business during 2019 and 2020 to date are described below.

• In February 2020, we announced a transition of its senior management. Mr. Isaac Angel has decided to retire from his position as Chief Executive Officer, effective July 1, 2020, after six years of successful service to the Company, its employees and its shareholders. It is intended that Mr. Angel will become a member of Ormat’s Board of Directors before his retirement as Chief Executive Officer and will continue to be employed by the Company through December 31, 2020 in order to assist with the management transition. Ormat’s Board of Directors has appointed Mr. Blachar, the Company’s President and Chief Financial Officer, to succeed Mr. Angel. Mr. Blachar will assume the role of Chief Executive Officer on July 1, 2020 upon Mr. Angel’s retirement.
Mr. Blachar will be succeeded in his role as Chief Financial Officer by Assaf Ginzburg, effective May 10, 2020, at which point Mr. Blachar will serve as President of the Company until assuming his role as Chief Executive Officer on July 1, 2020. Mr. Ginzburg currently serves as Executive Vice President and Chief Financial Officer of Delek US Holdings, Inc. (NYSE: DK) and Delek Logistics Partners, LP (NYSE: DKL), and has over 15 years of experience in the energy industry. In his financial positions, Mr. Ginzburg supervised teams of senior financial professionals and has significant experience in all aspects of corporate finance, financial planning, tax, accounting and investor relations.
  • As of February 2020, the reconstruction efforts at Puna continue. Building permits that are required for the construction and operation of the substation were delayed and were received in mid February 2020. HELCO continue with their efforts to complete the upgrade of the transmission network. On the field side, we completed the drilling of one production well that was blocked immediately after flow test of the well. We continue our field recovery work, which includes redrilling of existing wells, cleanouts and drilling of new wells and we expect initial power generation for testing during the second quarter of 2020. Commercial operation of the full generating capacity of the Puna power plant is expected in the third quarter assuming all permits are received, transmission network upgrade is complete and field recovery is successfully achieved.

77

  • In January 2020, we signed two similar PPAs with Silicon Valley Clean Energy (SVCE) and Monterey Bay Community Power (MBCP). Under the PPAs, SVCE and MBCP will each purchase 7 MW (for a total of 14 MW) of power generated by the expected 30 MW Casa Diablo-IV (CD4) geothermal project located in Mammoth Lakes, California that is under construction. The PPAs are for a term of 10 years and have a fixed MWh price, which includes energy, capacity, environmental attributes, and all other ancillary benefits. The remaining 16 MW of generating capacity will be sold under an additional PPA with Southern California Public Power Authority, which was signed in early 2019. The CD4 power plant is expected to be on-line by the end of 2021, will be the first geothermal power plant built within the California Independent System Operator (CAISO) balancing authority in the last 30 years and will be the first in Ormat’s portfolio that will sell its output to a Community Choice Aggregator.
  • In December 2019, PGV and Hawaiian Electric’s Hawaii Electric Light subsidiary reached an agreement on an amended and restated PPA for dispatchable geothermal power sold from Ormat’s Puna complex, located on the Big Island of Hawaii. The new PPA extends the term until 2052 with an increased contract capacity of 46MW and a fixed price with no escalation, regardless of changes to fossil fuel pricing. The energy rate under the contract is fixed at $70 per MWh for all energy purchased during any contract year up to 227,000 MWh and $40 per MWh above 227,000 MWh. In addition, annual capacity payments under the contract are approximately $19.5 million. The amended PPA was filed with the Public Utilities Commission (PUC) on December 31, 2019 for its review and approval, which is anticipated during 2020. We are planning to replace ten 25-year-old steam units with two new Ormat binary units and to upgrade the existing auxiliary equipment. This upgraded facility will utilize the same amount of geothermal resource that the existing 38 MW facility requires. The COD of the new plant is expected during the first half of 2022. The existing PPA remains in effect, with current terms, until the expansion is completed, and the new plant reaches its COD.
  • In December 2019, the tax extenders package was signed into law and retroactively revived and extended the full PTC for geothermal facilities. The PTC rules provide a tax credit for each kWh of electricity produced by the taxpayer from qualified renewable energy facilities. The PTC for geothermal facilities that expired at the end of 2017 was retroactively revived and extended through 2020, continuing U.S. support for the geothermal industry. This extension will drive and enhance our development of geothermal projects. This support contributes to the ongoing creation of new jobs in the geothermal industry as well as to the nation’s energy independence.
  • In November 2019, we announced that Mr. Doron Blachar, our CFO, was appointed to serve as our President, effective immediately. As President, Mr. Blachar assists our CEO, Isaac Angel, with the Company’s strategic direction and operational management until he assumes Mr. Angel’s position in July 1, 2020.
  • In August 2019, we announced that one of our wholly owned subsidiaries that indirectly owns the 48MW McGinness Hills Phase 3 geothermal power plant entered into a partnership agreement with a private investor. Pursuant to the transaction agreement, the private investor acquired membership interests in the project for an initial purchase price of approximately $59.3 million and for which it will pay additional annual installments that are expected to amount to a total of approximately $9 million and can reach up to $22 million based on the actual generation. We will continue to consolidate, operate and maintain the power plant and will receive substantially all of the distributable cash flow generated by the power plant, and prior to December 2027 the private investor will receive substantially all of the tax attributes.
  • In July 2019, we commenced commercial operation of our first-ever geothermal and solar hybrid project, a 7MW AC solar expansion of our Tungsten Mountain geothermal project in Churchill County, Nevada. The electricity generated from the Tungsten solar power plant will be used to offset the equipment’s energy use at the Tungsten geothermal facility, thus increasing the renewable energy delivered by the project under the Southern California Public Power Authority ("SCPPA") portfolio contract. SCPPA and the Los Angeles Department of Water and Power had the vision to enable this development through their innovative portfolio contract, which sought to maximize the output of their renewable facilities and furthering the transition away from coal power while maintaining a reliable power supply for Los Angeles.

78

  • In July 2019 we announced that we signed and closed a set of agreements to acquire 49% of the Ijen geothermal project company, which is holding a PPA and geothermal license to develop the Ijen project in East Java, Indonesia, from a Medco Power subsidiary. Under the terms of the agreements, Ormat acquired 49% of the shares of the Ijen geothermal project company and committed to make additional funding for the project exploration and development, subject to specific conditions. A subsidiary of Medco Power retains 51% ownership of Our company. Ormat and Medco will develop the project jointly. The Ijen project assets, whose final capacity will be determined after exploration, include a geothermal concession and 30-year PPA for up to 110 MW capacity. The project is ready for exploration and development with some slim holes already drilled.
  • In May 2019, we completed the drawdown of $23.5 million under a non-recourse loan agreement with Siemens Financial Services for the financing of Plumsted and Stryker, two 20 MW battery energy storage projects located in New Jersey. The loan bears interest of three months U.S. LIBOR plus 3.5% margin and its final maturity date is May 30, 2026.
  • In March 2019, we entered into a first addendum (“First Addendum”) to the Migdal Loan Agreement with several entities within the Migdal Group, a leading Israeli insurance company and institutional investor in Israel. The First Addendum provides us with an additional loan by the lenders in an aggregate principal amount of $50.0 million that will be repaid in 15 semi-annual payments of $2.1 million each, commencing on September 15, 2021, with a final payment of $18.5 million on March 15, 2029. The $50.0 million loan bears interest at a fixed rate of 4.6% per annum, payable semi-annually.
  • In March 2019, we announced the signing of a PPA between one of our subsidiaries and SCPPA. Under the PPA, SCPPA will purchase 16MW of power generated by the expected 30MW Casa Diablo-IV (“CD4”) geothermal project located in Mammoth Lakes, California. SCPPA will resell the output to the City of Colton. The CD4 power plant will be the first geothermal power plant built within the California Independent System Operator (“CAISO”) balancing authority in the last 30 years. The 16MW of energy deliveries under the PPA will begin no later than the end of 2021 with an extension option. The PPA is for a term of 25 years and has a fixed price of $68 per MWh. We are in negotiations to sell the balance of 14MW to other offtakers or at the spot market.
  • In January 2019, we entered into a $41.5 million subordinated loan agreement with Deutsche Investitions-und Entwicklungsgesellschaft mbH (“DEG”) and on February 28, 2019, we completed a drawdown of the full loan amount, with a fixed interest rate of 6.04% for the duration of the loan. The loan is being repaid in 19 equal semi-annual principal installments, which commenced on June 21, 2019, with a final maturity date of June 21, 2028. Proceeds of the loan were used to refinance upgrades to Plant 1 of the Olkaria III Complex.

Opportunities, Trends and Uncertainties

Different trends, factors and uncertainties may impact our operations and financial condition, including many that we do not or cannot foresee. However, we believe that our results of operations and financial condition for the foreseeable future will be primarily affected by the following trends, factors and uncertainties that are from time to time also subject to market cycles:

  • There has been increased demand for energy generated from geothermal and other renewable resources in the United States as costs for electricity generated from renewable resources have become more competitive. Much of this is attributable to legislative and regulatory requirements and incentives, such as state RPS and federal tax credits such as PTCs or ITCs (which are discussed in more detail in the section entitled “Government Grants and Tax Benefits” below). We believe that future demand for energy generated from geothermal and other renewable resources in the United States will be driven primarily by further commitment to, and implementation of, state RPS and greenhouse gas reduction initiatives.
  • We accelerated our efforts to expand business development activities in developing countries where geothermal is considered a local resource that can provide a stable and cost effective solution to increase access to power. We expect that a variety of local governmental initiatives will create new opportunities for the development of new projects with the potential to realize higher returns on our equity as well as to create additional markets for our products. These initiatives include the award of long-term contracts to independent power generators, the creation of competitive wholesale markets for selling and trading energy, capacity and related energy products and the adoption of programs designed to encourage “clean” renewable and sustainable energy sources.

79

  • In the Electricity segment, we expect intense domestic competition from the solar and wind power generation industries to continue and increase as well as increased competition from the solar combined with storage projects. While we believe the expected demand for renewable energy will be large enough to accommodate increased competition, any such increase in competition, including increasing amounts of renewable energy under contract as well as any further decline in natural gas prices attributable to increased production and reduction in energy storage costs are contributing to a reduction in electricity prices. However, despite increased competition from the solar and wind power generation industries, we believe that firm and flexible, base-load electricity, such as geothermal-based energy, will continue to be an important source of renewable energy in areas with commercially viable geothermal resources.
  • In the Product segment, we see new opportunities in New Zealand, Turkey, the U.S., Asia Pacific and Central and South America. We have experienced increased competition from binary power plant equipment suppliers including the major steam turbine manufacturers. While we believe that we have a distinct competitive advantage based on our technology, accumulated experience and current worldwide share of installed binary generation capacity, an increase in competition may impact our ability to secure new purchase orders from potential customers. The increased competition may also leads to further reductions in the prices that we are able to charge for our binary equipment, as we recently experienced in Turkey, which in turn reduces our profitability. We are experiencing such competition in other locations where we operate which may have an adverse impact on the prices we can charge and our profitability.
  • The average price per MWh, which is one of the metrics some investors may use to evaluate power plant revenues, can fluctuate from period to period. Based on total Electricity segment, we earned, on average, $86.6 and $87.0 per MWh in 2019 and 2018, respectively. Oil and natural gas prices, together with other factors that affect our Electricity segment revenues, could cause changes in our average price per MWh in the future.
  • Turkey’s geothermal market is one of the fastest growing markets in the geothermal industry worldwide, mainly due to governmental and regulatory support. Turkey is ranked fourth globally with an installed geothermal capacity of over 1,600 MW. Our revenue exposure to the Turkish market remained significant in 2019 and expects to reduce in 2020, due to slowdown in project development in the Turkish market. The continued deterioration in the Turkish economy, devaluation in the Turkish Lira and increase in local interest rates or a decline in government support for the development of geothermal power in the country could affect local demand for the geothermal equipment and services we provide, collection from our customers or the prices we may charge for such equipment and services. In addition, the impact of threatened or actual U.S. sanctions on the Turkish economy and the straining of U.S.-Turkey diplomatic relations may harm regional demand or price competitiveness for the geothermal equipment and services we provide in the Turkish market, in turn decreasing our Product segment profit margins, cash flows and financial condition. For the year ended December 31, 2019, we derived 12% and 47% of our Total revenues and Product revenues, respectively, from our Turkish operations. We are monitoring any change in the political and business environments that may affect our future business and operations in the country.
  • Ormat established a manufacturing facility in Turkey in order to locally produce several power plant components that entitle our customer for increased incentives under the renewable energy laws. The use of local equipment in renewable energy based generating facilities in Turkey entitles such facilities to significant benefits under Turkish law, provided such facilities have obtained an RER Certificate from EMRA, which requires the issuance of a local certificate. If we do not obtain the local certificate, then some of our customers under the relevant supply agreements in Turkey may not be issued a RER Certificate based on the equipment we supply to them, and we will be required to make a payment to such customers equal to the amount of the expected lost benefit.
  • In Kenya, we received three letters of assessment and preliminary findings from the KRA in relation to its review of the 2013 to 2017 tax years in which the KRA demanded we pay approximately $228.0 million including interest and penalties ($177.0 million principal). We are currently in different stages of discussions with the KRA on the matters included in their letters of assessment and preliminary findings and believe our tax positions for the issues raised during the audit are sustainable based on the technical merits under Kenyan tax law. See further details under our Item 8 below.
  • While the recently enacted Tax Act reduces the corporate tax rate, it is also expected to increase the cost of capital for renewable energy projects. Such projects often rely on "tax equity" as a core financing tool. Tax equity is a form of financing that is repaid partly or wholly in tax benefits and sometimes partly in cash. There are two types of federal income tax benefits on renewable energy projects: a tax credit and depreciation, or the ability to deduct the cost of the project. The reduction in the corporate tax rate from 35 percent to 21 percent reduces the value of the depreciation. Therefore, less tax equity can be raised on projects. The gap in the capital structure must be filled with debt and/or more expensive sponsor equity. The Tax Act allowed the full cost of equipment placed in service between September 28, 2017 and December 31, 2022 to be deducted immediately. However, the tax equity market is not expected to take advantage of this tax benefit and, because of the way tax equity works, we have had to take depreciation on a straight-line basis over 12 years rather than on a front-loaded basis over five years in some tax equity transactions, which leads to some further erosion in the present value of the depreciation. Other effects of the Tax Act are discussed later under Note 18 – Income Taxes to our consolidated financial statements.

80

Revenues

Sources of Revenues

We generate our revenues from the sale of electricity from our geothermal and recovered energy-based power plants; the design, manufacture and sale of equipment for electricity generation; the construction, installation and engineering of power plant equipment; the sale of energy storage services from our operating facilities and the sale of BSAAS systems and demand response and energy management services.

Revenues attributable to our Electricity segment are derived from the sale of electricity from our power plants pursuant to long-term PPAs. While approximately 97.6% of our Electricity revenues for the year ended December 31, 2019 were derived from PPAs with fixed price components, we have variable price PPAs in California and Hawaii. Accordingly, our revenues from those power plants may fluctuate.

Our Electricity segment revenues are also subject to seasonal variations, as more fully described in “Seasonality” below.

Our PPAs generally provide for energy payments alone, or energy and capacity payments. Generally, capacity payments are payments calculated based on the amount of time and capacity that our power plants are available to generate electricity. Some of our PPAs provide for bonus payments in the event that we are able to exceed certain capacity target levels and the potential forfeiture of payments if we fail to meet certain minimum capacity target levels. Energy payments, on the other hand, are payments calculated based on the amount of electrical energy delivered to the relevant power purchaser at a designated delivery point. Our more recent PPAs generally provide for energy payments alone with an obligation to compensate the off-taker for its incremental costs as a result of shortfalls in our supply.

Revenues attributable to our Product segment fluctuate between periods, primarily based on our ability to receive customer orders, the status and timing of such orders, delivery of raw materials and the completion of manufacturing. Larger customer orders for our products are typically the result of our sales efforts, our participation in, and winning tenders or requests for proposals issued by potential customers in connection with projects they are developing and orders by returning customers. Such projects often take a significant amount of time to design and develop and are subject to various contingencies, such as the customer’s ability to raise the necessary financing for a project. Consequently, we are generally unable to predict the timing of such orders for our products and may not be able to replace existing orders that we have completed with new ones. As a result, revenues from our Product segment fluctuate (sometimes extensively) from period to period.

Revenues attributable to our Energy Storage and Management Services segment are derived primarily from BSAAS systems, demand response and energy management services and may fluctuate period to period.

81

BSAAS are battery storage deals that are financed, owned and operated by us. BSAAS revenues are a combination of sales of the electricity back to the utilities and energy markets based on the prevailing market price for the electricity or for the energy or ancillary services. The energy and ancillary services revenue includes frequency regulation, standby capacity, synchronized reserve, reactive power and other related services. Additionally, when providing a “behind the customer meter solution” we also generate revenue from sharing savings generated from reducing the customer’s utility bill. We also act as a general contractor on turnkey BESS for customers. BESS systems are owned by the customer and we provide the EPC for the project, delivering to the customer a fully operational system. Along with the BESS we also provide the management and operation of the battery for the customer for the life of the system which is typically 10 to 20 years. The EPC portion of the turnkey BESS revenue is a one-time charge and usually will be based on mile-stones or upon delivery.

Revenues attributable to our demand response and energy management services are derived by two methods. The first method is a fixed monthly or annual recurring fee for managing the customer’s energy assets and monetizing them in either the energy markets or through reducing the customer’s charges from their utility. The second method is through sharing the revenues or savings generated from monetizing their flexible electricity in the energy markets (revenue) or through reducing the customer’s bill from the utility (savings). The second method is subject to energy price fluctuations and the available flexible electricity.

Revenues attributable to our Software as a Service are based on a fixed monthly or annual fee for energy management information and analytical services. Contract periods are typically 12 months or more. To date, we have experienced minimal customer churn.

The following table sets forth a breakdown of our revenues for the years indicated:

Revenues: Revenues (dollars in thousands) Year Ended December 31, 2019 2018 2017 % of Revenues for Period Indicated Year Ended December 31, 2019 2018 2017
Electricity $540,333 $509,879 $465,593 72.4% 70.9% 67.2%
Product 191,009 201,743 224,483 25.6 28.0 32.4
Energy Storage and Management Services 14,702 7,645 2,736 2.0 1.1 0.4
Total revenues $746,044 $719,267 $692,812 100.0% 100.0% 100.0%

Geographic Breakdown of Results of Operations

The following table sets forth the geographic breakdown of the revenues attributable to our Electricity, Product and Energy Storage and Management Services segments for the years indicated:

Revenues in Thousands

Electricity Segment: Year Ended December 31, 2019 2018 2017 % of Revenues for Period Indicated Year Ended December 31, 2019 2018 2017
United States $333,797 $305,962 $295,484 61.8% 60.0% 63.5%
International 206,536 203,917 170,109 38.2 40.0 36.5
Total $540,333 $509,879 $465,593 100.0% 100.0% 100.0%
Product Segment:
United States $30,562 $14,999 $2,912 16.0% 7.4% 1.3%
International 160,447 186,744 221,571 84.0 92.6 98.7
Total $191,009 $201,743 $224,483 100.0% 100.0% 100.0%
Energy Storage and Management Services Segment:
United States $13,597 $7,645 $2,736 92.5% 100.0% 100.0%
International 1,105 — — 7.5 0.0 0.0
Total $14,702 $7,645 $2,736 100.0% 100.0% 100.0%

82

In 2019, 2018 and 2017, 49%, 54% and 57% of our revenues were derived from international operations, respectively, and our international operations were more profitable than our U.S. operations in each of those years. A substantial portion of international revenues came from Kenya and Turkey and, to a lesser extent, from Honduras, Guadeloupe, Guatemala and other countries. Our operations in Kenya contributed disproportionately to gross profit and net income. The contribution to combined pre-tax income of our domestic and foreign operations within our Electricity segment and Product segment differ in a number of ways.

Electricity Segment. Our Electricity segment domestic revenues were approximately 62%, 60% and 64% of our total Electricity segment for the years ended December 31, 2019, 2018 and 2017, respectively. However, domestic operations in our Electricity segment have higher costs of revenues and expenses than the foreign operations in our Electricity segment. Our foreign power plants are located in lower-cost regions, like Kenya, Guatemala, Honduras and Guadeloupe, which favorably impact payroll and maintenance expenses among other items. They are also newer than most of our domestic power plants and therefore tend to have lower maintenance costs and higher availability factors than our domestic power plants. Consequently, in 2019 the international operations of the segment accounted for 52% of our total gross profits, 59% of our net income and 48% of our EBITDA.

Product Segment. Our Product segment foreign revenues were 84%, 93% and 99% of our total Product segment revenues for the years ended December 31, 2019, 2018 and 2017, respectively. Our Product segment foreign activity also benefits from lower costs of revenues and expenses than Product segment domestic activity such as labor and transportation costs. Accordingly, our Product segment foreign activity contributes more than our Product segment domestic activity to our pre-tax income from operations.

Seasonality

Electricity generation from some of our geothermal power plants is subject to seasonal variations; in the winter, our power plants produce more energy primarily attributable to the lower ambient temperature, which has a favorable impact on the energy component of our Electricity segment revenues and the prices under many of our contracts are fixed throughout the year with no time-of-use impact. The prices paid for electricity under the PPAs for the Heber 2 power plant in the Heber Complex, the Mammoth Complex and the North Brawley power plant in California, the Raft River power plant in Idaho and the Neal Hot Springs power plant in Oregon, are higher in the months of June through September. The higher payments payable under these PPAs in the summer months partially offset the negative impact on our revenues from lower generation in the summer attributable to a higher ambient temperature. As a result, we expect the revenues in the winter months to be higher than the revenues in the summer months.

Breakdown of Cost of Revenues

Electricity Segment

The principal cost of revenues attributable to our operating power plants are operation and maintenance expenses comprised of salaries and related employee benefits, equipment expenses, costs of parts and chemicals, costs related to third-party services, lease expenses, royalties, startup and auxiliary electricity purchases, property taxes, insurance, depreciation and amortization and, for some of our projects, purchases of make-up water for use in our cooling towers. In our California power plants, our principal cost of revenues also includes transmission charges and scheduling charges. In some of our Nevada power plants we also incur transmission and wheeling charges. Some of these expenses, such as parts, third-party services and major maintenance, are not incurred on a regular basis. This results in fluctuations in our expenses and our results of operations for individual power plants from quarter to quarter. Payments made to government agencies and private entities on account of site leases where power plants are located are included in cost of revenues. Royalty payments, included in cost of revenues, are made as compensation for the right to use certain geothermal resources and are paid as a percentage of the revenues derived from the associated geothermal rights. Royalties constituted approximately 4.1% and 4.2% of Electricity segment revenues for the years ended December 31, 2019 and 2018, respectively.

83

Product Segment

The principal cost of revenues attributable to our Product segment are materials, salaries and related employee benefits, expenses related to subcontracting activities, and transportation expenses. Sales commissions to sales representatives are included in selling and marketing expenses. Some of the principal expenses attributable to our Product segment, such as a portion of the costs related to labor, utilities and other support services are fixed, while others, such as materials, construction, transportation and sales commissions, are variable and may fluctuate significantly, depending on market conditions. As a result, the cost of revenues attributable to our Product segment, expressed as a percentage of total revenues, fluctuates. Another reason for such fluctuation is that in responding to bids for our products, we price our products and services in relation to existing competition and other prevailing market conditions, which may vary substantially from order to order.

Energy Storage and Management Services Segment

The principal cost of revenues attributable to our Energy Storage and Management Services segment are direct costs attributable to providing services and equipment to our customers, direct costs associated with software development and the direct cost of operating batteries that are owned by Viridity. Direct costs include labor costs of our network operations center, the labor costs for engineering and implementation of services to customers, consulting services provided to customers and developing software and the labor associated with operations and maintenance for customer and our Viridity owned energy assets. Cost of revenues attributable to our Energy Storage and Management Services segment also include cost of equipment sold to customers in delivering our automated demand response and software services at a customer’s location, the cost of batteries or other associated equipment that is sold to customers and for any third party related costs such as local construction, local engineering or other similar costs incurred in implementing and managing the customers’ energy assets.

Critical Accounting Estimates and Assumptions

Our significant accounting policies are more fully described in Note 1 to our consolidated financial statements set forth in Item 8 of this annual report. However, certain of our accounting policies are particularly important to an understanding of our financial position and results of operations. In applying these critical accounting estimates and assumptions, our management uses its judgment to determine the appropriate assumptions to be used in making certain estimates. Such estimates are based on management’s historical experience, the terms of existing contracts, management’s observance of trends in the geothermal industry, information provided by our customers and information available to management from other outside sources, as appropriate. Such estimates are subject to an inherent degree of uncertainty and, as a result, actual results could differ from our estimates. Our critical accounting policies include:

  • Revenues and Cost of Revenues. Revenues generated from the construction of geothermal and recovered energy-based power plant equipment and other equipment on behalf of third parties (Product revenues) are recognized using the percentage of completion method, which requires estimates of future costs over the full term of product delivery. Such cost estimates are made by management based on prior operations and specific project characteristics and designs. If management’s estimates of total estimated costs with respect to our Product segment are inaccurate, then the percentage of completion is inaccurate resulting in an over- or under-estimate of gross margins. As a result, we review and update our cost estimates on significant contracts on a quarterly basis, and at least on an annual basis for all others, or when circumstances change and warrant a modification to a previous estimate. Changes in job performance, job conditions, and estimated profitability, including those arising from the application of penalty provisions in relevant contracts and final contract settlements, may result in revisions to costs and revenues and are recognized in the period in which the revisions are determined. Provisions for estimated losses relating to contracts are made in the period in which such losses are determined. Revenues generated from engineering and operating services and sales of products and parts are recorded once the service is provided or product delivery is made, as applicable.

84

  • Property, Plant and Equipment. We capitalize all costs associated with the acquisition, development and construction of power plant facilities. Major improvements are capitalized and repairs and maintenance (including major maintenance) costs are expensed. We estimate the useful life of our power plants to range between 25 and 30 years. Such estimates are made by management based on factors such as prior operations, the terms of the underlying PPAs, geothermal resources, the location of the assets and specific power plant characteristics and designs. Changes in such estimates could result in useful lives which are either longer or shorter than the depreciable lives of such assets. We periodically re-evaluate the estimated useful life of our power plants and revise the remaining depreciable life on a prospective basis.

We capitalize costs incurred in connection with the exploration and development of geothermal resources beginning when we acquire land rights to the potential geothermal resource. Prior to acquiring land rights, we make an initial assessment that an economically feasible geothermal reservoir is probable on that land using available data and external assessments vetted through our exploration department and occasionally outside service providers. Costs incurred prior to acquiring land rights are expensed. It normally takes two to three years from the time we start active exploration of a particular geothermal resource to the time we have an operating production well, assuming we conclude the resource is commercially viable.

In most cases, we obtain the right to conduct our geothermal development and operations on land owned by the BLM, various states or with private parties. In consideration for certain of these leases, we may pay an up-front non-refundable bonus payment which is a component of the competitive lease process. This payment and other related costs are capitalized and included in construction-in-process. Once we acquire land rights to the potential geothermal resource, we perform additional activities to assess the commercial viability of the resource. Such activities include, among others, conducting surveys and other analysis, obtaining drilling permits, creating access roads to drilling sites, and exploratory drilling which may include temperature gradient holes and/or slim holes. Such costs are capitalized and included in construction-in-process. Once our exploration activities are complete, we finalize our assessment as to the commercial viability of the geothermal resource and either proceed to the construction phase for a power plant or abandon the site. If we decide to abandon a site, all previously capitalized costs associated with the exploration project are written off.

Our assessment of economic viability of an exploration project involves significant management judgment and uncertainties as to whether a commercially viable resource exists at the time we acquire land rights and begin to capitalize such costs. As a result, it is possible that our initial assessment of a geothermal resource may be incorrect and we will have to write off costs associated with the project that were previously capitalized. Due to the uncertainties inherent in geothermal exploration, historical impairments may not be indicative of future impairments. Included in construction-in-process are costs related to projects in exploration and development of $84.6 million and $71.0 million at December 31, 2019 and 2018, respectively. Included in these amounts at December 31, 2019 and 2018, respectively, are $17.0 million and $17.0 million, respectively, which relate to up-front bonus payments.

  • Impairment of Long-Lived Assets and Long-Lived Assets to be Disposed of. We evaluate long-lived assets, such as property, plant and equipment and construction-in-process for impairment whenever events or changes in circumstances indicate that the carrying amount of an asset may not be recoverable. Factors which could trigger an impairment include, among others, significant underperformance relative to historical or projected future operating results, significant changes in our use of assets or our overall business strategy, negative industry or economic trends, a determination that an exploration project will not support commercial operations, a determination that a suspended project is not likely to be completed, a significant increase in costs necessary to complete a project, legal factors relating to our business or when we conclude that it is more likely than not that an asset will be disposed of or sold.

We test our operating plants that are operated together as a complex for impairment at the complex level because the cash flows of such plants result from significant shared operating activities. For example, the operating power plants in a complex are managed under a management combined operation generally with one central control room that controls and one maintenance group that services all of the power plants in a complex. As a result, the cash flows from individual plants within a complex are not largely independent of the cash flows of other plants within the complex. We test for impairment of our operating plants which are not operated as a complex, as well as our projects under exploration, development or construction that are not part of an existing complex, at the plant or project level. To the extent an operating plant becomes part of a complex in the future, we will test for impairment at the complex level.

Recoverability of assets to be held and used is measured by a comparison of the carrying amount of an asset to the estimated future net undiscounted cash flows expected to be generated by the asset. The significant assumptions that we use in estimating our undiscounted future cash flows include (i) projected generating capacity of the power plant and rates to be received under the respective PPA and (ii) projected operating expenses of the relevant power plant. Estimates of future cash flows used to test recoverability of a long-lived asset under development also include cash flows associated with all future expenditures necessary to develop the asset. If future cash flows are less than the assumptions we used in such estimates, we may incur impairment losses in the future that could be material to our financial condition and/or results of operations.

If our assets are considered to be impaired, the impairment to be recognized is the amount by which the carrying amount of the assets exceeds their fair value. Assets to be disposed of are reported at the lower of the carrying amount or fair value less costs to sell. We believe that for the year ended December 31, 2019, no impairment exists for any of our long-lived assets; however, estimates as to the recoverability of such assets may change based on revised circumstances. Estimates of the fair value of assets require estimating useful lives and selecting a discount rate that reflects the risk inherent in future cash flows.

85

  • Goodwill. Goodwill represents the excess of the fair value of consideration transferred in the business combination transactions over the fair value of tangible and intangible assets acquired, net of the fair value of liabilities assumed and the fair value of any noncontrolling interest in the acquisitions. Goodwill is not amortized but rather subject to a periodic impairment testing on an annual basis (on December 31 of each year) or if an event occurs or circumstances change that would more likely than not reduce the fair value of reporting unit below its carrying amount. Additionally, we are permitted to first assess qualitative factors to determine whether a quantitative goodwill impairment test is necessary. Further testing is only required if the entity determines, based on the qualitative assessment, that it is more likely than not that a reporting unit’s fair value is less than its carrying amount. Otherwise, no further impairment testing is required. An entity has the option to bypass the qualitative assessment for any reporting unit in any period and proceed directly to step one of the quantitative goodwill impairment test. This would not preclude the entity from performing the qualitative assessment in any subsequent period. The first step compares the fair value of the reporting unit to its carrying value, including goodwill. In January 2017, the FASB issued ASU 2017-04, Intangibles – Goodwill and Other (Topic 350), which was adopted by us in 2018, under which step two of the goodwill impairment test was eliminated. Step two measured a goodwill impairment test by comparing the implied fair value of reporting unit’s goodwill with the carrying amount of that goodwill. Under ASU 2017-04, Intangibles – Goodwill and Other, an entity should recognize an impairment charge for the amount by which the carrying amount of the reporting unit exceeds its fair value as calculated under step one described above. However, the loss recognized should not exceed the total amount of goodwill allocated to that reporting unit
  • Obligations Associated with the Retirement of Long-Lived Assets. We record the fair market value of legal liabilities related to the retirement of our assets in the period in which such liabilities are incurred. These liabilities include our obligation to plug wells upon termination of our operating activities, the dismantling of our power plants upon cessation of our operations, and the performance of certain remedial measures related to the land on which such operations were conducted. When a new liability for an asset retirement obligation is recorded, we capitalize the costs of such liability by increasing the carrying amount of the related long-lived asset. Such liability is accreted to its present value each period and the capitalized cost is depreciated over the useful life of the related asset. At retirement, we either settle the obligation for its recorded amount or report either a gain or a loss with respect thereto. Estimates of the costs associated with asset retirement obligations are based on factors such as prior operations, the location of the assets and specific power plant characteristics. We review and update our cost estimates periodically and adjust our asset retirement obligations in the period in which the revisions are determined. If actual results are not consistent with our assumptions used in estimating our asset retirement obligations, we may incur additional losses that could be material to our financial condition or results of operations.
  • Accounting for Income Taxes. Significant estimates are required to arrive at our consolidated income tax provision. This process requires us to estimate our actual current tax exposure and to make an assessment of temporary differences resulting from differing treatments of items for tax and accounting purposes. Such differences result in deferred tax assets and liabilities which are included in our consolidated balance sheets. For those jurisdictions where the projected operating results indicate that realization of our net deferred tax assets is not more likely than not, a valuation allowance is recorded.

We evaluate our ability to utilize the deferred tax assets quarterly and assess the need for the valuation allowance. In assessing the need for a valuation allowance, we estimate future taxable income, including the impacts of the passing of the Tax Act, considering the feasibility of ongoing tax planning strategies and the realization of tax credits and tax loss carryforwards. Valuation allowances related to deferred tax assets can be affected by changes in tax laws, statutory tax rates, and future taxable income. We have recorded a partial valuation allowance related to our U.S. deferred tax assets. In the future, if there is sufficient evidence that we will be able to generate sufficient future taxable income in the United States, we may be required to further reduce this valuation allowance, resulting in income tax benefits in our consolidated statement of operations.

In the ordinary course of business, there is inherent uncertainty in quantifying our income tax positions. We assess our income tax positions and record tax benefits for all years subject to examination based upon management’s evaluation of the facts, circumstances and information available at the reporting date. For those tax positions where it is more likely than not that a tax benefit will be sustained, which is greater than 50% likelihood of being realized upon ultimate settlement with a taxing authority that has full knowledge of all relevant information, we recognize between 0 to 100% of the tax benefit. For those income tax positions where it is not more likely than not that a tax benefit will be sustained, we do not recognize any tax benefit in the consolidated financial statements. Resolution of these uncertainties in a manner inconsistent with our expectations could have a material impact on our financial condition or results of operations.

86

New Accounting Pronouncements

See Note 1 to our consolidated financial statements set forth in Item 8 of this annual report for information regarding new accounting pronouncements.

Results of Operations

Our historical operating results in dollars and as a percentage of total revenues are presented below.

(Dollars in thousands, except per share data)

Revenues: Year Ended December 31, 2019 2018 2017
Electricity $540,333 $509,879 $465,593
Product 191,009 201,743 224,483
Energy storage and management services 14,702 7,645 2,736
Total revenues 746,044 719,267 692,812
Cost of revenues:
Electricity 312,835 298,255 266,840
Product 145,974 140,697 152,094
Energy storage and management services 17,912 9,880 5,426
Total cost of revenues 476,721 448,832 424,360
Gross profit (loss)
Electricity 227,498 211,624 198,753
Product 45,035 61,046 72,389
Energy storage and management services (3,210) (2,235) (2,690)
Total gross profit 269,323 270,435 268,452
Operating expenses:
Research and development expenses 4,647 4,183 3,157
Selling and marketing expenses 15,047 19,802 15,600
General and administrative expenses 55,833 47,750 42,881
Impairment charge — 13,464 —
Write-off of unsuccessful exploration activities — 126 1,796
Operating income 193,796 185,110 205,018
Other income (expense):
Interest income 1,515 974 988
Interest expense, net (80,384) (70,924) (54,142)
Derivatives and foreign currency transaction gains (losses) 624 (4,761) 2,654
Income attributable to sale of tax benefits 20,872 19,003 17,878
Other non-operating income (expense), net 880 7,779 (1,666)
Income from operations before income tax and equity in earnings (losses) of investees 137,303 137,181 170,730
Income tax (provision) benefit (45,613) (34,733) (21,664)
Equity in earnings (losses) of investees, net 1,853 7,663 (1,957)
Net Income 93,543 110,111 147,109
Net income attributable to noncontrolling interest (5,448) (12,145) (14,695)
Net income attributable to the Company's stockholders $88,095 $97,966 $132,414
Earnings per share attributable to the Company's stockholders:
Basic:
Net income $1.73 $1.93 $2.64
Diluted:
Net income $1.72 $1.92 $2.61
Weighted average number of shares used in computation of earnings per share attributable to the Company's stockholders:
Basic 50,867 50,643 50,110
Diluted 51,227 50,969 50,769

87

Results as a percentage of revenues

Revenues: Year Ended December 31, 2019 2018 2017
Electricity 72.4% 70.9% 67.2%
Product 25.6 28.0 32.4
Energy storage and management services 2.0 1.1 0.4
Total revenues 100.0 100.0 100.0
Cost of revenues:
Electricity 57.9 58.5 57.3
Product 76.4 69.7 67.8
Energy storage and management services 121.8 129.2 198.3
Total cost of revenues 63.9 62.4 61.3
Gross profit (loss)
Electricity 42.1 41.5 42.7
Product 23.6 30.3 32.2
Energy storage and management services (21.8) (29.2) (98.3)
Total gross profit 36.1 37.6 38.7
Operating expenses:
Research and development expenses 0.6 0.6 0.5
Selling and marketing expenses 2.0 2.8 2.3
General and administrative expenses 7.5 6.6 6.2
Impairment charge 0.0 1.9 0.0
Write-off of unsuccessful exploration activities 0.0 0.0 0.3
Operating income 26.0 25.7 29.6
Other income (expense):
Interest income 0.2 0.1 0.1
Interest expense, net (10.8) (9.9) (7.8)
Derivatives and foreign currency transaction gains (losses) 0.1 (0.7) 0.4
Income attributable to sale of tax benefits 2.8 2.6 2.6
Other non-operating income (expense), net 0.1 1.1 (0.2)
Income from continuing operations before income tax and equity in earnings (losses) of investees 18.4 19.1 24.6
Income tax (provision) benefit (6.1) (4.8) (3.1)
Equity in earnings (losses) of investees, net 0.2 1.1 (0.3)
Net Income 12.5 15.3 21.2
Net income attributable to noncontrolling interest (0.7) (1.7) (2.1)
Net income attributable to the Company's stockholders 11.8% 13.6% 19.1%

88

Comparison of the Year Ended December 31, 2019 and the Year Ended December 31, 2018

Total Revenues (Dollars in millions)

(Dollars in millions)

Year Ended December 31, 2019 Year Ended December 31, 2018 Change
Electricity segment revenues $540.3 $509.9 6%
Product segment revenues 191.0 201.7 (5)%
Energy Storage and Management Services segment revenues 14.7 7.6 92%
Total Revenues $746.0 $719.3 4%

Electricity Segment

Revenues attributable to our Electricity segment for the year ended December 31, 2019 were $540.3 million, compared to $509.9 million for the year ended December 31, 2018, representing a 6.0% increase from the prior period. This increase was primarily attributable to: (i) the commencement of commercial operation of the third phase of our McGinness Hills Complex in Nevada, effective December 2018, which generated total complex revenues of $96.9 million for the year ended December 31, 2019 compared to $65.1 million for the year ended December 31, 2018; (ii) the consolidation of USG which was acquired on April 24, 2018, and contributed $35.6 million for the year ended December 31, 2019, compared to $21.4 million for the year ended December 31, 2018; and (iii) the commencement of commercial operation of our Plant 1 expansion project in the Olkaria III Complex in Kenya, effective June 2018. The increase was partially offset by (i) the shutdown of our Puna power plant following the Kilauea volcanic eruption on May 3, 2018 which resulted in a reduction of $15.5 million in revenues compared to the year ended December 31, 2018; and (ii) a decrease in generation at some of our other power plants that were taken offline to address maintenance issues in the ordinary course of business as well as curtailments by the offtaker in the Olkaria complex.

Power generation in our power plants increased by 6.5% from 5,857,963 MWh in the year ended December 31, 2018 to 6,238,272 MWh in the year ended December 31, 2019, primarily because of an increase in generation due to the commencement of commercial operation of the third phase of our McGinness Hills Complex in Nevada, Plant 1 expansion in Kenya and the acquisition of USG. The increase was partially offset by (i) the shutdown of our Puna power plant following the Kilauea Volcanic Eruption and (ii) lower generation at some of our other power plants mainly due to higher ambient temperature and maintenance issues in the ordinary course of business as well as curtailments by the offtaker in the Olkaria III complex.

Product Segment

Revenues attributable to our Product segment for the year ended December 31, 2019 were $191.0 million, compared to $201.7 million for the year ended December 31, 2018, representing a 5.3% decrease from the prior period. The decrease in our Product segment revenues was mainly due to projects that were completed in Turkey in 2018, which accounted for $91.1 in Product segment revenues in the year ended December 31, 2018, which were partially offset by (i) the start of four new projects in Turkey, New Zealand and Chile in 2019, which provided $90.3 million in revenue for the year ended December 31, 2019; and (ii) other projects mainly in Turkey and the U.S., which were started in 2018, and provided $72.2 million in revenue for the year ended December 31, 2019 compared to $90.0 million for the year ended December 31, 2018.

89

Energy Storage and Management Services Segment

Revenues attributable to our Energy Storage and Management Services segment for the year ended December 31, 2019 were $14.7 million compared to $7.6 million for the year ended December 31, 2018. The increase was mainly driven by the start of operation of two energy storage facilities in the PJM market. The Energy Storage and Management Services segment includes revenues from the delivery of energy storage demand response and energy management services.

Total Cost of Revenues (Dollars in millions)

(Dollars in millions)

Year Ended December 31, 2019 Year Ended December 31, 2018 Change
Electricity segment cost of revenues $312.8 $298.3 4.9%
Product segment cost of revenues 146.0 140.7 3.8%
Energy Storage and Management Services segment cost of revenues 17.9 9.9 81.3%
Total Cost of Revenues $476.7 $448.8 6.2%

Electricity Segment

Total cost of revenues attributable to our Electricity segment for the year ended December 31, 2019 was $312.8 million, compared to $298.3 million for the year ended December 31, 2018, representing a 4.9% increase from the prior period. This increase was primarily attributable to: (i) additional cost of revenues from the commencement of commercial operation of the third phase of our McGinness Hills Complex plant in Nevada, effective December 2018 and (ii) commencement of commercial operation of our Plant 1 expansion project in the Olkaria III Complex in Kenya, effective June 2018. As a percentage of total Electricity revenues, the total cost of revenues attributable to our Electricity segment for the year ended December 31, 2019 was 57.9%, compared to 58.5% for the year ended December 31, 2018. This decrease was primarily attributable to an increase in gross profit due to the commencement of commercial operation of the third phase of our McGinness Hills Complex and from our assets that were acquired from USG and contributed partially in 2018, partly offset by the Puna power plant in Hawaii, for which we recorded cost of revenues with no associated revenues due to the shut-down of the power plant following the Kilauea volcanic eruption in May 3, 2018. The cost of revenues attributable to our international power plants was 23.6% of our Electricity segment cost of revenues.

Product Segment

Total cost of revenues attributable to our Product segment for the year ended December 31, 2019 was $146.0 million, compared to $140.7 million for the year ended December 31, 2018, representing a 3.8% increase from the prior period. This increase was primarily attributable to higher competition, different product scope and different margins in the various sales contracts we entered into for the Product segment during these periods, specifically related to two large but lower margin contracts in Turkey that had an impact on revenue and related cost of revenues in the year ended December 31, 2019. As a percentage of total Product segment revenues, our total cost of revenues attributable to our Product segment for the year ended December 31, 2019 was 76.4%, compared to 69.7% for the year ended December 31, 2018.

Energy Storage and Management Services Segment

Cost of revenues attributable to our Energy Storage and Management Services segment for the year ended December 31, 2019 were $17.9 million as compared to $9.9 million in the year ended December 31, 2018. The increase was mainly driven by the start of operation of two storage energy facilities in the PJM market. The Energy Storage and Management Services segment includes cost of revenues related to the delivery of energy storage, demand response and energy management services.

Research and Development Expenses

Research and development expenses for the year ended December 31, 2019 were $4.6 million, compared to $4.2 million for the year ended December 31, 2018.

90

Selling and Marketing Expenses

Selling and marketing expenses for the year ended December 31, 2019 were $15.0 million, compared to $19.8 million for the year ended December 31, 2018. This decrease was primarily due to the $5.0 million termination fee paid to NV Energy related to the termination of the Galena 2 PPA in the year ended December 31, 2018. Selling and marketing expenses constituted 2.0% of total revenues for the year ended December 31, 2019, compared to 2.1%, excluding the termination fee, for the year ended December 31, 2018.

General and Administrative Expenses

General and administrative expenses for the year ended December 31, 2019 were $55.8 million, compared to $47.8 million for the year ended December 31, 2018. The increase was primarily attributable to a $10.3 million income adjustment in the year ended December 31, 2018, in respect of an earn out related to the acquisition of our Viridity business, partially offset by (i) higher expenses in the year ended December 31, 2018 related to our identification of a material weakness related to taxes in the fourth quarter of 2017 and the restatement of 2017 financial statements; (ii) costs related to the acquisition of USG in 2018; and (iii) a decrease in professional fees. General and administrative expenses for the year ended December 31, 2019 constituted 7.5% of total revenues for such period, compared to 8.1%, excluding the earn out adjustment, for the year ended December 31, 2018.

Goodwill Impairment Charge

There was no goodwill impairment charge for the year ended December 31, 2019. Goodwill impairment charge for the year ended December 31, 2018 was $13.5 million related to the acquisition of our Viridity business.

Operating Income

Operating income for the year ended December 31, 2019 was $193.8 million, compared to $185.1 million for the year ended December 31, 2018, representing a 4.7% increase from the prior period. Operating income attributable to our Electricity segment for the year ended December 31, 2019 was $177.2 million compared to $155.5 million for the year ended December 31, 2018. Operating income attributable to our Product segment for the year ended December 31, 2019 was $23.2 million, compared to $38.1 million for the year ended December 31, 2018. Operating loss attributable to our Energy Storage and Management Services segment for the year ended December 31, 2019 was $6.6 million compared to $8.5 million for the year ended December 31, 2018.

Interest Expense, Net

Interest expense, net, for the year ended December 31, 2019 was $80.4 million, compared to $70.9 million for the year ended December 31, 2018, representing a 13.3% increase from the prior period. This increase was primarily due to (i) $100.0 million and $50.0 million of proceeds from a senior unsecured loan received on March 22, 2018 and March 25, 2019, respectively; (ii) $96.0 million debt as part of the acquisition of USG; (iii) $114.7 million of proceeds from a limited recourse loan received on October 29, 2018 from OPIC for financing the Honduras power plant; and (iv) $41.5 million of proceeds from a full recourse loan received on January 4, 2019 from DEG for financing the Kenya power plant, partially offset due to lower interest expense as a result of principal payments of long term debt.

Derivatives and Foreign Currency Transaction Gains (Losses)

Derivatives and foreign currency transaction gains for the year ended December 31, 2019 were $0.6 million, compared to losses of $4.8 million for the year ended December 31, 2018. Derivatives and foreign currency transaction gains for the year ended December 31, 2019 were attributable primarily to gains from foreign currency forward contracts, which were not accounted for as hedge transactions. Derivatives and foreign currency transaction losses for the year ended December 31, 2018 were primarily attributable to losses from foreign currency forward contracts, which were not accounted for as hedge transactions.

91

Income Attributable to Sale of Tax Benefits

Income attributable to the sale of tax benefits for the year ended December 31, 2019 was $20.9 million, compared to $19.0 million for the year ended December 31, 2018. Tax equity is a form of financing used for renewable energy projects. This income primarily represents the value of PTCs and taxable income or loss generated by certain of our power plants allocated to investors under tax equity transactions.

Other Non-Operating Income (Expense), Net

Other non-operating income, net for the year ended December 31, 2019 was $0.9 million, compared to other non-operating expense, net of $7.8 million for the year ended December 31, 2018. Other non-operating income for the year ended December 31, 2019 mainly includes an income of $1.0 million from the sale of PG&E receivables relating to the January 2019 monthly invoice which was not paid as it occurred before PG&E filed for reorganization under Chapter 11 bankruptcy. Other non-operating income for the year ended December 31, 2018 mainly includes income of a $7.2 million insurance settlement of our Puna power plant rig which was damaged by the Kilauea volcanic eruption.

Income from operations, before income taxes and equity in earnings of investees

Income from operations, before income taxes and equity in earnings of investees for the year ended December 31, 2019 was $137.3 million, compared to $137.2 million for the year ended December 31, 2018, representing an 0.1% increase from the prior period. The income is primarily attributable to our foreign operations.

Income Taxes

Income tax provision for the year ended December 31, 2019, was $45.6 million, an increase of $10.9 million compared to an income tax provision of $34.7 million for the year ended December 31, 2018. Our effective tax rate for the year ended December 31, 2019 and 2018, was 33.2% and 25.3%, respectively. Our effective tax rate is primarily based upon the composition of our income in different countries and changes related to valuation allowances in the United States. Our aggregate effective tax rate for the year ended December 31, 2019 differs from the 21% U.S. federal statutory tax rate primarily due to the impact of global intangible low tax income (GILTI) and the mix of business in various countries with higher and lower statutory rates than the federal rate, partially offset by the generation of additional foreign tax credits through amended tax returns of prior periods.

On December 22, 2017, the U.S. government signed into law the Tax Act. The Tax Act makes significant changes to the U.S. tax code, including, but not limited to, (1) reducing the U.S. federal corporate income tax rate from 35 percent to 21 percent; (2) the transition of U.S. international taxation from a worldwide tax system to a territorial system (GILTI, BEAT, Dividends Received Deduction); (3) one-time transition tax on undistributed earnings of foreign subsidiaries as of December 31, 2017; (4) eliminating the corporate alternative minimum tax (5) creating a new limitation on deductible interest expense; and (6) changing rules related to uses and limitations of net operating loss carryforwards created in tax years beginning after December 31, 2017.

Equity in Earnings (losses) of investees, net

Equity in earnings (losses) of investees, net in the year ended December 31, 2019 was $1.9 million, compared to $7.7 million in the year ended December 31, 2018. Equity in earnings of investees, net is primarily derived from our 12.75% share in the earnings or losses in the Sarulla complex. The decrease was mainly attributable to a decrease in gross margin due to well-field issues in the NIL power plant which resulted in lower generation.

92

Net Income

Net income for the year ended December 31, 2019 was $93.5 million, compared to $110.1 million for the year ended December 31, 2018, representing a decrease of $16.6 million from the prior period. This decrease in net income was primarily attributable to an increase in income tax provision of $10.9 million, an increase of $9.5 million in interest expense, net, a decrease of $6.9 million in other non-operating income, and a decrease of $5.8 million in equity in earnings of investees, net, partially offset by an increase of $8.7 million in operating income and an increase of $5.4 million in derivatives and foreign currency transaction gains, as discussed above.

Net Income attributable to the Company’s Stockholders

Net income attributable to the Company’s stockholders for the year ended December 31, 2019 was $88.1 million, compared to $98.0 million for the year ended December 31, 2018, which represents a decrease of $9.9 million. This decrease was attributable to the decrease in net income of $16.6 million, offset partially by a decrease of $6.7 million in net income attributable to noncontrolling interest mainly due to the shutdown of the Puna power plant in Hawaii, all as discussed above.

Comparison of the year ended December 31, 2018 and the year ended December 31, 2017

Total Revenues

Total revenues for the year ended December 31, 2018 were $719.3 million, compared to $692.8 million for the year ended December 31, 2017, representing a 3.8% increase from the prior period. This increase was attributable to our Electricity segment, in which revenues increased by $44.3 million or 9.5% compared to the corresponding period in 2017 and our Energy Storage and Management Services segment in which revenues increased by $4.9 million or 179.4%, as a result of revenues generated by our Viridity business from the delivery of energy storage, demand response and energy management services. This increase was partially offset by a decrease of $22.7 million, or 10.1% in our Product segment revenues compared to the corresponding period in 2017.

Electricity Segment

Revenues attributable to our Electricity segment for the year ended December 31, 2018, were $509.9 million, compared to $465.6 million for the year ended December 31, 2017, representing a 9.5% increase from the prior period. This increase was primarily attributable to: (i) the commencement of commercial operation of our Platanares power plant in Honduras, effective September 2017, with revenues of $34.4 million for the year ended December 31, 2018 compared to $10.0 million for the year ended December 31, 2017; (ii) the consolidation of USG which was acquired on April 24, 2018, with revenues of $21.4 million for the year ended December 31, 2018; (iii) the commencement of commercial operation of our Tungsten Mountain power plant in Nevada, effective December 2017, with revenues of $15.7 million for the year ended December 31, 2018 compared to $2.2 million for the year ended December 31, 2017; (iv) the commencement of commercial operation of our Plant 1 expansion project in the Olkaria III Complex in Kenya, effective June 2018; and (v) higher energy rates under the new Ormesa 1 PPA commencing in December 2017. The increase was partially offset due to (i) a decrease in revenues at our Puna power plant that was shut down immediately following the Kilauea volcanic eruption on May 3, 2018 and (ii) a decrease in generation at some of our other power plants that were taken offline to address maintenance issues and enhancements, high ambient temperature and curtailments.

Power generation in our power plants increased by 6.7% from 5,489,234 MWh in the year ended December 31, 2017 to 5,857,963 MWh in the year ended December 31, 2018, primarily because of an increase in generation due to the commencement of commercial operations of our Platanares power plant in Honduras, Tungsten Mountain power plant in Nevada, and Plant 1 expansion in Kenya and due to the acquisition of USG. The increase was partially offset by a decrease in generation at (i) our Puna power plant due to the Kilauea Volcanic Eruption and (ii) some of our other power plants mainly due to maintenance issues and high ambient temperature.

93

Product Segment

Revenues attributable to our Product segment for the year ended December 31, 2018 were $201.7 million, compared to $224.5 million for the year ended December 31, 2017, representing a 10.1% decrease from the prior period. We recognized approximately $31.4 million and $23.1 million in revenues, from the New Zealand and China projects, respectively, in the year ended December 31, 2017, compared to $8.8 million and $0.5 million in the year ended December 31, 2018. The projects were completed in 2018. The decrease in our Product segment revenues was also attributable to other projects in Turkey, which were completed in 2017, and by a decrease in revenues as a result of completion of our contracts for geothermal projects in Chile and the Sarulla project. The decrease was partially offset by the start of new projects in Turkey, which provided $154.3 million in revenue recognized during the year ended December 31, 2018.

Energy Storage and Management Services Segment

Revenues attributable to our Energy Storage and Management Services segment for the year ended December 31, 2018 were $7.6 million compared to $2.7 million for the year ended December 31, 2017. The Energy Storage and Management Services segment includes revenues from the delivery of energy storage demand response and energy management services by our Viridity business following the acquisition of substantially all of the business and assets of Viridity Energy, Inc. on March 15, 2017.

Total Cost of Revenues

Total cost of revenues for the year ended December 31, 2018 was $448.8 million, compared to $424.4 million for the year ended December 31, 2017, representing a 5.8% increase from the prior period. This increase was attributable to an increase of $31.4 million, or 11.8%, in cost of revenues from our Electricity segment and an increase of $4.5 million, or 82.1% from our Energy Storage and Management Services segment generated by our Viridity business. This increase was partially offset by a 7.5% decrease in our Product segment cost of revenues compared to the corresponding period in 2017. As a percentage of total revenues, our total cost of revenues for the year ended December 31, 2018 increased to 62.4%, compared to 61.3% for the year ended December 31, 2017.

Electricity Segment

Total cost of revenues attributable to our Electricity segment for the year ended December 31, 2018 was $298.3 million, compared to $266.8 million for the year ended December 31, 2017, representing a 11.8% increase from the prior period. This increase was primarily attributable to additional cost of revenues from the commencement of commercial operation of our Platanares power plant in Honduras, effective September 2017, our Tungsten Mountain power plant in Nevada, effective December 2017 and commencement of commercial operation of our Plant 1 expansion project in the Olkaria III Complex in Kenya, effective June 2018, (ii) approximately $8.0 million higher costs compared to the same period 2017 related to pump failures that we had to replace in some of our power plants and (iii) the consolidation of USG which we acquired on April 24, 2018. As a percentage of total Electricity segment revenues, the total cost of revenues attributable to our Electricity segment for the year ended December 31, 2018 was 58.5%, compared to 57.3% for the year ended December 31, 2017. The cost of revenues attributable to our international power plants was 24.7% of our Electricity segment cost of revenues.

Product Segment

Total cost of revenues attributable to our Product segment for the year ended December 31, 2018 was $140.7 million, compared to $152.1 million for the year ended December 31, 2017, representing a 7.5% decrease from the prior period. This decrease was primarily attributable to decrease in Product segment revenues, as discussed above. As a percentage of total Product segment revenues, our total cost of revenues attributable to the Product segment for the year ended December 31, 2018 was 69.7%, compared to 67.8% for the year ended December 31, 2017. This increase was primarily attributable to the higher competition, different product scope and different margins in the various sales contracts we entered into for the Product segment during these periods.

Energy Storage and Management Services Segment

Cost of revenues attributable to our Energy Storage and Management Services segment for the year ended December 31, 2018 were $9.9 million, compared to $5.4 million for the year ended December 31, 2017. The Energy Storage and Management Services segment includes cost of revenues related to the delivery of energy storage, demand response and energy management services by our Viridity business.

94

Research and Development Expenses

Research and development expenses for the year ended December 31, 2018 were $4.2 million, compared to $3.2 million for the year ended December 31, 2017.

Selling and Marketing Expenses

Selling and marketing expenses for the year ended December 31, 2018 were $19.8 million, compared to $15.6 million for the year ended December 31, 2017. This increase was primarily due to the $5.0 million termination fee paid to NV Energy related to the termination of the Galena 2 PPA. The increase was partially offset as a result of lower sales commissions related to our Product segment due to lower revenues and lower commissions due to the nature of the contracts. Selling and marketing expenses for the year ended December 31, 2018, excluding the termination fee, constituted 2.1% of total revenues for such year, compared to 2.3% for the year ended December 31, 2017.

General and Administrative Expenses

General and administrative expenses for the year ended December 31, 2018 were $47.8 million, compared to $42.9 million for the year ended December 31, 2017. This increase was primarily attributable to (i) general and administrative expenses resulting from first time inclusion of USG, (ii) general and administrative expenses from our Viridity business which we acquired on March 15, 2017; and (iii) an increase in costs associated with our identification of a material weakness related to taxes in the fourth quarter of 2017 and the additional work and controls to compensate for such material weakness as well as the restatement of second, third and fourth quarter financial statements and its full-year 2017 financial statements and related expenses. The increase was partially offset due to a $10.3 million adjustment in respect of an earn out related to the acquisition of our Viridity business. General and administrative expenses for the year ended December 31, 2017 included $2.1 million charge for stock-based compensation expense associated with the acceleration of the vesting period of the stock options previously held by our CEO and CFO and exercised in connection with ORIX’s acquisition of 22% of our Company.

Goodwill Impairment Charge

Goodwill impairment charge for the year ended December 31, 2018 was $13.5 million related to the acquisition of our Viridity business. There was no goodwill impairment charge for the year ended December 31, 2017.

Write-off of Unsuccessful Exploration Activities

Write-off of unsuccessful exploration activities for the year ended December 31, 2018 was $0.1 million, compared to $1.8 million for the year ended December 31, 2017. The write-off of unsuccessful exploration activities for the year ended December 31, 2017, included costs related to the Glass Buttes site in Oregon, which we determined in the fourth quarter of 2017, would not support commercial operations.

Operating Income

Operating income for the year ended December 31, 2018 was $185.1 million, compared to $205.0 million for the year ended December 31, 2017, representing a 9.7% decrease from the prior period. The decrease in operating income was primarily attributable to the $13.5 million goodwill impairment charge, the decrease in our Product segment gross margin, the $5.0 million termination fee of the Galena 2 PPA, and the increase in general and administrative expenses, as discussed above. The decrease was partially offset by an increase in our gross margin in our Electricity segment, also discussed above. Operating income attributable to our Electricity segment for the year ended December 31, 2018 was $155.5 million, compared to $157.6 million for the year ended December 31, 2017. Operating income attributable to our Product segment for the year ended December 31, 2018 was $38.1 million, compared to $50.5 million for the year ended December 31, 2017. Operating loss attributable to our Energy Storage and Management Services segment for the year ended December 31, 2018 was $8.5 million compared to a loss of $3.1 million for the year ended December 31, 2017.

95

Interest Expense, Net

Interest expense, net, for the year ended December 31, 2018 was $70.9 million, compared to $54.1 million for the year ended December 31, 2017, representing a 31.0% increase from the prior period. This increase was primarily due to: (i) $100.0 million of proceeds from a senior unsecured loan received on March 22, 2018; (ii) net increase in our revolving credit lines with commercial banks; and (iii) a $3.5 million increase related to a decrease in interest capitalized to projects; (iv) additional debt as part of the acquisition of USG, and (v) $4.3 million increase in interest related to the sale of tax benefits; and (vi) $114.7 million of proceeds from a limited recourse loan received on October 29, 2018 from OPIC for financing the Honduras power plant, offset partially due to lower interest expense as a result of principal payments of long term debt.

Derivatives and Foreign Currency Transaction Losses

Derivatives and foreign currency transaction losses for the year ended December 31, 2018 were $4.8 million, compared to gains of $2.7 million for the year ended December 31, 2017. Derivatives and foreign currency transaction losses for the year ended December 31, 2018 were attributable primarily to losses from foreign currency forward contracts, which were not accounted for as hedge transactions. Derivatives and foreign currency transaction gains for the year ended December 31, 2017 were primarily attributable to gains from foreign currency forward contracts, which were not accounted for as hedge transactions.

Income Attributable to Sale of Tax Benefits

Tax equity is a form of financing used for renewable energy projects. In such financings, the Company we may realize income when the financing is put in place or over time as a consequence of how the financing is structured. Income attributable to the sale of tax benefits to institutional equity investors (as described in our financial statements below under “OPC Transaction”, “ORTP Transaction” and “Opal Geo Transaction”) for the year ended December 31, 2018 was $19.0 million, compared to $17.9 million for the year ended December 31, 2017. This income primarily represents the value of PTCs and taxable income or loss generated by Opal Geo and Tungsten allocated to the investor in the year ended December 31, 2018 compared to the value of PTCs and taxable income or loss generated by Opal Geo allocated to the investors in the year ended December 31, 2017.

Other Non-Operating Income (loss)

Other non-operating income, net for the year ended December 31, 2018 was $7.8 million, compared to Other non-operating expense, net of $1.7 million for the year ended December 31, 2017. Other non-operating expense, net for the year ended December 31, 2018 includes an income of $7.2 million insurance settlement of our Puna power plant rig which was damaged by the Kilauea volcanic eruption. Other non-operating expense, net for the year ended December 31, 2017 includes a make whole premium of $1.9 million resulting from the prepayment of $14.3 million aggregate principal amount of our OFC Senior Secured Notes and $11.8 million aggregate principal amount of our DEG Loan.

Income from operations, before income taxes and equity in losses of investees

Income from operations, before income taxes and equity in losses of investees for the year ended December 31, 2018 was $137.2 million, compared to $170.7 million for the year ended December 31, 2017, representing a 19.7% decrease from the prior period. The income is primarily attributable to our foreign operations. This decrease was driven by the decrease in our domestic operations resulting mainly from the goodwill impairment charge relating to our Viridity business, the $5.0 million termination fee of the Galena 2 PPA, and the increase in general and administrative expenses, partially offset by an income of $7.2 million insurance settlement of our Puna power plant rig in the year ended December 31, 2018, as described above.

Income Taxes

Income tax provision for the year ended December 31, 2018, was $34.7 million, an increase of $13.0 million compared to an income tax provision of $21.7 million for the year ended December 31, 2017. The increase in income tax provision primarily resulted from the tax on global intangible low-tax income (GILTI), partially offset by a decrease in withholding tax on distribution of earnings, and the exclusion of other impacts of U.S. federal tax reform that resulted in a one-time tax impact for the year ended December 31, 2017. Our effective tax rate for the years ended December 31, 2018 and 2017, was 25.3% and 12.7%, respectively. Our effective tax rate at December 31, 2018 is principally based upon the composition of the income in different countries, tax on GILTI, accounting for intra-entity transfers of assets other than inventory, and changes related to valuation allowances. Our aggregate effective tax rate is higher than the 21% U.S federal statutory tax rate due to: (i) the impact of the newly enacted GILTI; (ii) higher tax rate in Kenya of 37.5% and Guadeloupe of 33.33% partially offset by a lower tax rate in Israel of 16 %; and (iii) withholding taxes on future distributions (see Note 18 - Income Taxes to the consolidated financial statements set forth in Item 8 of this annual report for further details regarding our income tax provision and the Tax Act).

96

For the years ended December 31, 2018 and 2017, we recorded a valuation allowance in the amount of approximately $22.4 million and $77.6 million, respectively, against our unutilized tax credits (FTCs and PTCs) and U.S. deferred tax assets related to state net operating loss (NOL) carryforwards. As of December 31, 2018, we had U.S. federal NOLs in the amount of approximately $230.5 million, state NOLs in the amount of approximately $269.1 million, and unutilized federal tax credits of approximately $149.0 million, some of which can be carried forward for 10-20 years. In addition, we had unutilized state tax credits of approximately 0.8 million, which can be carried forward for indefinite period. The related deferred tax assets totaled approximately $192.4 million after valuation allowance. Realization of these deferred tax assets and tax credits is dependent on generating sufficient taxable income in the United States prior to expiration of the NOL carryforwards and tax credits. The scheduled reversal of deferred tax liabilities, projected future taxable income, estimated impacts of tax reform and tax planning strategies were considered in determining the amount of valuation allowance. A valuation allowance in the amount of $22.4 million was recorded against the U.S. deferred tax assets as of December 31, 2018 because we believe it is more likely than not that the deferred tax assets will not be realized. If sufficient additional evidence of our ability to generate taxable income is established, we may be required to reduce or fully release the valuation allowance, resulting in income tax benefits in our consolidated statement of operations.

On December 22, 2017, the U.S. government signed into law the Tax Act. The Tax Act makes significant changes to the U.S. tax code, including, but not limited to, (1) reducing the U.S. federal corporate income tax rate from 35 percent to 21 percent; (2) the transition of U.S. international taxation from a worldwide tax system to a territorial system (GILTI, BEAT, Dividends Received Deduction); (3) one-time transition tax on undistributed earnings of foreign subsidiaries as of December 31, 2017; (4) eliminating the corporate alternative minimum tax (5) creating a new limitation on deductible interest expense; and (6) changing rules related to uses and limitations of net operating loss carryforwards created in tax years beginning after December 31, 2017.

We applied the guidance of SAB 118 for the effects of the Tax Act in 2017 and throughout 2018. The Deemed Repatriation Tax (Transition Tax) is a tax on previously untaxed accumulated and current earnings and profits (E&P) of certain foreign subsidiaries. To determine the amount of the Transition Tax, we determined, in addition to other factors, the amount of post-1986 E&P of the relevant subsidiaries, as well as the amount of non-U.S. income taxes paid on such earnings. As a result of our initial analysis of the impact of the Tax Act, we recorded a provisional amount of $71.6 million (gross) with respect to the inclusion of the transition tax at December 31, 2017. In addition, at December 31, 2017, we recorded a provisional benefit of $22.6 million relating to the remeasurement of deferred taxes from 35% to 21%.

As of December 31, 2018, we have completed our accounting for the tax effects of the Tax Reform Act. Subsequent adjustments to these amounts resulted in a reduction of $7.8 million to the transition tax and a decreased tax benefit of $3.5 million to the remeasurement of deferred taxes.

Under the Tax Act, the deductibility of net interest for a business is limited to 30% of adjusted taxable income. The new proposed regulations issued by Treasury applies regardless of whether the interest payment is made to a U.S. or foreign person, whether the interest recipient is related, or whether the interest recipient is exempt from U.S. tax. Further, any interest that cannot be deducted in a year can be carried forward indefinitely. We have not early adopted these proposed regulations and intend to adopt them during the 2019 tax year. For the year ended December 31, 2018, we have evaluated the impact and determined there is no limit on our interest deductibility for federal income tax purposes for the current period, but anticipates there could be significant limitations upon adoption.

We are also required to elect to either treat taxes due on future GILTI inclusions in United States taxable income as a current period expense when incurred or reflect such portion of the future GILTI inclusions in United States taxable income that relate to existing basis differences in our current measurement of deferred taxes. We have elected to treat the taxes due on future U.S. inclusions in taxable income under GILTI as a period cost when incurred. We have elected and applied the tax law ordering approach when considering GILTI as part of our valuation allowance.

We continue to monitor the impact of any additional guidance issued by Treasury. Notwithstanding the reduction in the corporate income tax rate, the overall impact of the Tax Act is uncertain, and our business, financial condition, future results and cash flow, as well as our stock price, could be adversely affected.

97

Equity in Earnings (losses) of Investees, Net

Equity in earnings (losses) of investees, net in the year ended December 31, 2018 was a profit of $7.7 million, compared to a loss of $2.0 million in the year ended December 31, 2017. Equity in earnings (losses) of investees, net derived from our 12.75% share in the losses of the Sarulla complex and from profits elimination.The increase was mainly attributable to utilization of carryforward losses and full year of commercial operations of SIL and NIL 1 and commercial operation of NIL 2 from May 2018.

Net Income

Net income for the year ended December 31, 2018 was $110.1 million, compared to $147.1 million for the year ended December 31, 2017, representing a decrease of $37.0 million from the prior period. This decrease in net income was primarily attributable to a decrease in operating income of $19.9 million, an increase of $16.8 million in interest expense, net and a decrease of $7.4 million in derivatives and foreign currency transaction gains and $13.1 million increase in income tax provision, partially offset due to an increase in Other non-operating income, net of $9.4 million, and an increase in equity in earnings of investees, net of $9.6 million, all as discussed above.

Net Income attributable to the Company’s Stockholders

Net income attributable to the Company’s stockholders for the year ended December 31, 2018 was $98.0 million, compared to $132.4 million for the year ended December 31, 2017, which represents a decrease of $34.4 million. This decrease was attributable to the decrease in net income of $37.0 million, offset partially by a decrease of $2.6 million in net income attributable to noncontrolling interest mainly due to the shutdown of the Puna power plant in Hawaii, all as discussed above.

Liquidity and Capital Resources

Our principal sources of liquidity have been derived from cash flows from operations, proceeds from third party debt such as borrowings under our credit facilities, private offerings and issuances of debt securities, equity offerings, project financing and tax monetization transactions, short term borrowing under our lines of credit, and proceeds from the sale of equity interests in one or more of our projects. We have utilized this cash to develop and construct power plants, fund our acquisitions, pay down existing outstanding indebtedness, and meet our other cash and liquidity needs.

As of December 31, 2019, we had access to: (i) $71.2 million in cash and cash equivalents, of which $59.2 million was held by our foreign subsidiaries; and (ii) $213.9 million of unused corporate borrowing capacity under existing lines of credit with different commercial banks.

Our estimated capital needs for 2020 include approximately $332 million for capital expenditures on new projects under development or construction including storage projects, exploration activity and maintenance capital expenditures for our existing projects. In addition, we expect $135.5 million for long-term debt repayments, which excludes $50.0 million of commercial papers and approximately $40.6 million for revolver that we assume will be renewed.

As of December 31, 2019, $213.8 million in the aggregate was outstanding under credit agreements with several banks as detailed below under “Credit Agreements”.

We expect to finance these requirements with: (i) the sources of liquidity described above; (ii) positive cash flows from our operations; and (iii) future project financings and re-financings (including construction loans and tax equity). Management believes that, based on the current stage of implementation of our strategic plan, the sources of liquidity and capital resources described above will address our anticipated liquidity, capital expenditures, and other investment requirements.

During 2019, we have revised our assertion to no longer indefinitely reinvest foreign funds held by our foreign subsidiaries, with the exception of a certain balance held in Israel and have accrued the incremental foreign withholding taxes. As a result, we have further liquidity to move funds freely.

Third-Party Debt

Our third-party debt consists of (i) non-recourse and limited-recourse project finance debt or acquisition financing that we or our subsidiaries have obtained for the purpose of developing and constructing, refinancing or acquiring our various projects and (ii) full-recourse debt incurred by us or our subsidiaries for general corporate purposes.

98

Non-Recourse and Limited-Recourse Third-Party Debt

Loan Issued Amount ($M) Outstanding Amount as of December 31, 2019 Interest Rate Maturity Date Related Projects Location
OFC 2 Senior Secured Notes – Series A 151.7 94.3 4.82% 2032 McGinness Hills phase 1 and Tuscarora United States
OFC 2 Senior Secured Notes – Series B 140.0 108.8 4.61% 2032 McGinness Hills phase 2 United States
Olkaria III Financing Agreement with OPIC – Tranche 1 85.0 51.9 6.34% 2030 Olkaria III Complex Kenya
Olkaria III Financing Agreement with OPIC – Tranche 2 180.0 111.2 6.29% 2030 Olkaria III Complex Kenya
Olkaria III Financing Agreement with OPIC – Tranche 3 45.0 29.6 6.12% 2030 Olkaria III Complex Kenya
Amatitlan Financing (1) 42.0 26.3 LIBOR+4.35% 2027 Amatitlan Guatemala
Don A. Campbell Senior Secured Notes 92.5 78.2 4.03% 2033 Don A. Campbell Complex United States
Prudential Capital Group Idaho Loan (2) 20.0 18.3 5.8% 2023 Neal Hot Springs and Raft River United States
U.S. Department of Energy loan (3) 96.8 44.9 2.61% 2035 Neal Hot Springs United States
Prudential Capital Group Nevada Loan 30.7 27.1 6.75% 2037 San Emidio United States
Platanares Loan with OPIC 114.7 104.5 7.02% 2032 Platanares Honduras
Viridity - Plumstriker 23.5 21.6 LIBOR+3.5% 2026 Plumsted+Striker United States
Geothermie Bouillante (4) 8.9 8.4 1.52% 2026 Geothermie Bouillante Guadeloupe
Geothermie Bouillante (4) 8.9 9.0 1.93% 2026 Geothermie Bouillante Guadeloupe
Total 1,039.7 734.1

(1) LIBOR Rate cannot be lower than 1.25%. Margin of 4.35% as long as the Company’s guaranty of the loan is outstanding (current situation) or 4.75% otherwise. Current interest is 6.29%.

(2) Secured by equity interest.

(3) Secured by the assets.

(4) Loan in Euros and issued amount is EUR 8.0 million

Full-Recourse Third-Party Debt

Loan Issued Amount ($M) Outstanding as of December 31, 2019 Interest Rate Maturity Date
Senior Unsecured Bonds Series 2 67.2 67.2 3.7% September 2020
Senior Unsecured Bonds Series 3 137.1 137.1 4.45% September 2022
Commercial Paper(1) 50.0 50.0 3 month LIBOR+0.75% (2)
Short term revolving credit lines with banks 40.6
Senior unsecured Loan 1 100.0 100.0 4.8% March 2029
Senior unsecured Loan 2 50.0 50.0 4.6% March 2029
DEG Loan 2 50.0 42.5 6.28% June 2028
DEG Loan 3 41.5 37.1 6.04% June 2028
Total 495.8 524.5

(1) Current interest rate is 2.69%.

(2) Issued for 90 days and extends automatically for additional periods of 90 days each for up to five years.

99

Letters of Credits under the Credit Agreements

Some of our customers require our project subsidiaries to post letters of credit in order to guarantee their respective performance under relevant contracts. We are also required to post letters of credit to secure our obligations under various leases and licenses and may, from time to time, decide to post letters of credit in lieu of cash deposits in reserve accounts under certain financing arrangements. In addition, our subsidiary, Ormat Systems is required from time to time to post performance letters of credit in favor of our customers with respect to orders of products.

Credit Agreements Issued Amount ($M) Issued and Outstanding as of December 31, 2019 Termination Date
MUFG 60.0 59.5 June 2020
HSBC 35.0 25.5 October 2020
Other Institutions 260.0 15.6 March 2020 – July 2022
Other Banks 1 150.0 103.1 September 2020 – July 2022
Other Banks 2 - 10.1 December 2020
Total 505.0 213.8

Restrictive covenants

Our obligations under the credit agreements, the loan agreements, and the trust instrument governing the bonds described above, are unsecured, but we are subject to a negative pledge in favor of the banks and the other lenders and certain other restrictive covenants. These include, among other things, a prohibition on: (i) creating any floating charge or any permanent pledge, charge or lien over our assets without obtaining the prior written approval of the lender; (ii) guaranteeing the liabilities of any third party without obtaining the prior written approval of the lender; and (iii) selling, assigning, transferring, conveying or disposing of all or substantially all of our assets, or a change of control in our ownership structure. Some of the credit agreements, the term loan agreements, and the trust instrument contain cross-default provisions with respect to other material indebtedness owed by us to any third party. In some cases, we have agreed to maintain certain financial ratios, which are measured quarterly, such as: (i) equity of at least $600 million and in no event less than 25% of total assets; (ii) 12-month debt, net of cash, cash equivalents, and short-term bank deposits to Adjusted EBITDA ratio not to exceed 6.0; and (iii) dividend distributions not to exceed 35% of net income in any calendar year. As of December 31, 2019: (i) total equity was $1,515.4 million and the actual equity to total assets ratio was 46.6% and (ii) the 12-month debt, net of cash, cash equivalents, to Adjusted EBITDA ratio was 2.99. During the year ended December 31, 2019, we distributed interim dividends in an aggregate amount of $22.4 million. The failure to perform or observe any of the covenants set forth in such agreements, subject to various cure periods, would result in the occurrence of an event of default and would enable the lenders to accelerate all amounts due under each such agreement.

As described above, we are currently in compliance with our covenants with respect to the credit agreements, the loan agreements and the trust instrument, and believe that the restrictive covenants, financial ratios and other terms of any of our full-recourse bank credit agreements will not materially impact our business plan or operations.

100

Future minimum payments

Future minimum payments under long-term obligations, excluding revolving credit lines with commercial banks, as of December 31, 2019, are detailed under the caption Contractual Obligations and Commercial Commitments, below.

Puna Power Plant Lease Transactions

In May 2005, our Hawaiian subsidiary, PGV, entered into lease transactions involving the original geothermal power plant of the Puna Complex located on the Big Island (the Puna Power Plant).

In connection with the execution of the new amended and restated PPA described under "Recent Developments" above, we paid $20.5 million to effectively terminate the lease transactions (the amount includes all future payments according to the original lease agreements) involving the original power plant in order to enter into and meet our obligations under the new PPA. As a result, we have no obligation for future minimum lease payments as of December 31, 2019.

Liquidity Impact of Uncertain Tax Positions

As discussed in Note 18 - Income Taxes, to our consolidated financial statements set forth in Item 8 of this annual report, we have a liability associated with unrecognized tax benefits and related interest and penalties in the amount of approximately $14.6 million as of December 31, 2019. This liability is included in long-term liabilities in our consolidated balance sheet, because we generally do not anticipate that settlement of the liability will require payment of cash within the next 12 months. We are not able to reasonably estimate when we will make any cash payments required to settle this liability.

Dividends

The following are the dividends declared by us during the past two years:

Date Declared Dividend Amount per Share Record Date Payment Date
March 1, 2018 $0.23 March 14, 2018 March 29, 2018
May 7, 2018 $0.10 May 21, 2018 May 30, 2018
August 7, 2018 $0.10 August 21, 2018 August 29, 2018
November 6, 2018 $0.10 November 20, 2018 December 4, 2018
February 26, 2019 $0.11 March 14, 2019 March 28, 2019
May 6, 2019 $0.11 May 20, 2019 May 28, 2019
August 7, 2019 $0.11 August 20, 2019 August 27, 2019
November 6, 2019 $0.11 November 20, 2019 December 4, 2019
February 25, 2020 $0.11 March 12, 2020 March 26, 2020

Historical Cash Flows

The following table sets forth the components of our cash flows for the relevant periods indicated:

(Dollars in thousands)

Year Ended December 31, 2019 2018 2017
Net cash provided by operating activities $236,493 $145,822 $245,575
Net cash used in investing activities (254,538) (342,434) (345,526)
Net cash provided by (used in) financing activities (5,765) 251,131 (67,882)
Translation adjustments on cash and cash equivalents (575) (660) —
Net change in cash and cash equivalents and restricted cash and cash equivalents $(24,385) $53,859 $(167,833)

101

For the Year Ended December 31, 2019

Net cash provided by operating activities for the year ended December 31, 2019 was $236.5 million, compared to $145.8 million for the year ended December 31, 2018. This increase of $99.1 million resulted primarily from (i) an increase in accounts payable and accrued expenses of $8.7 million in the year ended December 31, 2019, compared to a decrease of $56.7 million in the year ended December 31, 2018, driven by: (i) a withholding tax payment of approximately $14 million in the year ended December 31, 2019 compared to $44 million in the year ended December 31, 2018, because of a distribution from OSL (ii) the timing of payments to our suppliers and (iii) a decrease of $15.1 million in receivables in the year ended December 31, 2019 compared to $29.9 million in the year ended December 31, 2018 because of timing of collections from our customers.

Net cash used in investing activities for the year ended December 31, 2019 was $254.5 million, compared to $342.4 million for the year ended December 31, 2018. The principal factors that affected our net cash used in investing activities during the year ended December 31, 2019 were: (i) capital expenditures of $280.0 million, primarily for our facilities under construction; and (ii) an investment in an unconsolidated company of $10.7 million, partially offset by proceeds from insurance recoveries of $35.4 million.

Net cash used in financing activities for the year ended December 31, 2019 was $5.8 million, compared to $251.1 million provided by financing activities for the year ended December 31, 2018. The principal factors that affected the net cash used in financing activities during the year ended December 31, 2019 were: (i) net payment of $118.5 million from our revolving credit lines with commercial banks which were used for capital expenditures, (ii) the repayment of long-term debt in the amount of $93.8 million; (iii) a $22.4 million cash dividend payment and (iv) $9.7 million cash paid to a noncontrolling interest, partially offset by, (i) $50 million of proceeds from a senior unsecured loan, (ii) $41.5 million of proceeds from a term loan for our Olkaria III Complex plant 1 expansion, (iii) $23.5 million of proceeds for the financing of two 20 MW battery energy storage projects, (iv) $17.8 million of proceeds from limited and non-recourse loans for our Guadeloupe power plant, (v) $50.0 million of proceeds from issuance of commercial paper and (vi) proceeds from the sale of a limited liability company interest in McGinness Hills Phase 3, net of transaction costs of $58.3 million.

For the Year Ended December 31, 2018

Net cash provided by operating activities for the year ended December 31, 2018 was $145.8 million, compared to $245.6 million for the year ended December 31, 2017. This decrease of $99.8 million resulted primarily from a decrease in accounts payable and accrued expenses of $56.7 million in the year ended December 31, 2018, compared to an increase of $51.6 million in the year ended December 31, 2017, mainly due to a withholding tax payment of approximately $44 million due to a distribution from OSL, offset partially by approximately $14 million due to a distribution from OSL in 2018. The decrease was also due to timing of payments to our suppliers.

Net cash used in investing activities for the year ended December 31, 2018 was $342.4 million, compared to $345.5 million for the year ended December 31, 2017. The principal factors that affected our net cash used in investing activities during the year ended December 31, 2018 were: (i) capital expenditures of $258.5 million, primarily for our facilities under construction; (ii) cash paid for acquisition of controlling interest in USG, net of cash acquired of $95.1 million; and (iii) an investment in an unconsolidated company of $3.8 million.

Net cash used in financing activities for the year ended December 31, 2018 was $251.1 million, compared to $67.9 million provided by financing activities for the year ended December 31, 2017. The principal factors that affected the net cash provided by financing activities during the year ended December 31, 2018 were: (i) $100.0 million of proceeds from a senior unsecured loan, (ii) $114.7 million of proceeds from a limited and non-recourse loan; (iii) net proceeds of $107.5 million from our revolving credit lines with commercial banks which were used for capital expenditures, and (iv) proceeds from the sale of a limited liability company interest in Tungsten, net of transaction costs of $32.2 million, partially offset by: (i) the repayment of long-term debt in the amount of $62.8 million; (ii) a $26.8 million cash dividend paid; and (iii) $13.1 million of cash paid to noncontrolling interests.

102

Total EBITDA and Adjusted EBITDA

We calculate EBITDA as net income before interest, taxes, depreciation and amortization. We calculate Adjusted EBITDA as net income before interest, taxes, depreciation and amortization, adjusted for (i) termination fees, (ii) impairment of long-lived assets, (iii) write-off of unsuccessful exploration activities, (iv) any mark-to-market gains or losses from accounting for derivatives, (v) merger and acquisition transaction costs, (vi) stock-based compensation, (vii) gain or loss from extinguishment of liabilities, (viii) gain or loss on sale of subsidiary and property, plant and equipment and (ix) other unusual or non-recurring items. EBITDA and Adjusted EBITDA are not measurements of financial performance or liquidity under accounting principles generally accepted in the United States, or U.S. GAAP, and should not be considered as an alternative to cash flow from operating activities or as a measure of liquidity or an alternative to net earnings as indicators of our operating performance or any other measures of performance derived in accordance with U.S. GAAP. We use EBITDA and Adjusted EBITDA as a performance metric because it is a metric used by our Board of Directors and senior management in evaluating our financial performance. However, other companies in our industry may calculate EBITDA and Adjusted EBITDA differently than we do.

This information should not be considered in isolation from, or as a substitute for, or superior to, measures of financial performance prepared in accordance with GAAP or other non-GAAP financial measures.

Adjusted EBITDA for the year ended December 31, 2019 was $384.3 million, compared to $368.0 million for the year ended December 31, 2018 and $343.8 million for the year ended December 31, 2017.

The following table reconciles net income to EBITDA and adjusted EBITDA for the years ended December 31, 2019, 2018 and 2017:

(Dollars in thousands)

Year Ended December 31, 2019 2018 2017
Net income $93,543 $110,111 $147,109
Adjusted for:
Interest expense, net (including amortization of deferred financing costs) 78,869 69,950 53,154
Income tax provision (benefit) 45,613 34,733 21,664
Adjustment to investment in an unconsolidated company: our proportionate share in interest expense, tax and depreciation and amortization in Sarulla complex 13,089 9,184 (265)
Depreciation and amortization 143,242 127,732 108,693
EBITDA 374,356 351,710 330,355
Mark-to-market on derivative instruments (1,402) 2,032 (1,500)
Stock-based compensation 9,358 10,218 8,760
Insurance proceeds in excess of assets carrying value — (7,150) —
Termination fee — 3,142 —
Impairment of goodwill, net of reversal of a contingent liability — 4,973 —
Loss from extinguishment of liability 468 — 1,950
Merger and acquisition transaction costs 1,483 2,910 2,460
Write-off of unsuccessful exploration activities — 126 1,796
Adjusted EBITDA $384,263 $367,961 $343,821

Adjusted EBITDA excluding the impact of Puna related expenses of approximately $1.2 million for the year ended December 31, 2019 is $385.5 million.

EBITDA includes the proportionate share (12.75%) of net depreciation, interest and tax expenses from our unconsolidated investment in the Sarulla complex that is accounted for under the equity method.

On May 2014, the Sarulla consortium (“SOL”) closed $1,170 million in financing. As of December 31, 2019, the credit facility has an outstanding balance of $1,074.2 million. Our proportionate share in the SOL credit facility is $137.0 million.

103

Capital Expenditures

Our capital expenditures primarily relate to the enhancement of our existing power plants and the exploration, development and construction of new power plants.

We have budgeted approximately $359 million in capital expenditures for construction of new projects and enhancements to our existing power plants, of which we had invested $96.2 million as of December 31, 2019. We expect to invest approximately $134 million in 2020 and the remaining approximately $128 million thereafter.

In addition, we estimate approximately $198 million in additional capital expenditures in 2020 to be allocated as follows: (i) approximately $57 million for the exploration and development of new projects and enhancements of existing power plants that not yet released for full construction (ii) approximately $61 million for maintenance of capital expenditures to our operating power plants including drilling in our Puna power plant; (iii) approximately $65 million for the construction and development of storage projects; and (iv) approximately $15.0 million for enhancements to our production facilities.

In the aggregate, we estimate our total capital expenditures for 2020 to be approximately $332 million.

Exposure to Market Risks

Based on current conditions, we believe that we have sufficient financial resources to fund our activities and execute our business plans. However, the cost of obtaining financing for our project needs may increase significantly or such financing may be difficult to obtain.

We, like other power plant operators, are exposed to electricity price volatility risk. Our exposure to such market risk is currently limited because many of our long-term PPAs (except for the 25 MW PPA for the Puna Complex and the between 30 MW and 40 MW PPAs in the aggregate for the Heber 2 power plant in the Heber Complex and the G2 power plant in the Mammoth Complex) have fixed or escalating rate provisions that limit our exposure to changes in electricity prices. The energy payments under the PPAs of the Heber 2 power plant in the Heber Complex and the G2 power plant in Mammoth Complex are determined by reference to the relevant power purchaser’s SRAC. A decline in the price of natural gas will result in a decrease in the incremental cost that the power purchaser avoids by not generating its electrical energy needs from natural gas, or by reducing the price of purchasing its electrical energy needs from natural gas power plants, which in turn will reduce the energy payments that we may charge under the relevant PPA for these power plants. The Puna Complex is currently benefiting from energy prices which are higher than the floor under the 25 MW PPA for the Puna Complex as a result of the high fuel costs that impact HELCO’s avoided costs.

As of December 31, 2019, 95.9% of our consolidated long-term debt was fixed rate debt and therefore was not subject to interest rate volatility risk and 4.1% of our long-term debt was floating rate debt, exposing us to interest rate risk in connection therewith. As of December 31, 2019, $47.9 million of our long-term debt remained subject to some interest rate risk.

104

We currently maintain our surplus cash in short-term, interest-bearing bank deposits, money market securities and commercial paper with a minimum investment grade rating of AA by Standard & Poor’s Ratings Services.

Our cash equivalents are subject to interest rate risk. Fixed rate securities may have their market value adversely impacted by a rise in interest rates, while floating rate securities may produce less income than expected if interest rates fall. As a result of these factors, our future investment income may fall short of expectations because of changes in interest rates, or we may suffer losses in principal if we are forced to sell securities that decline in market value because of changes in interest rates.

We are also exposed to foreign currency exchange risk, in particular the fluctuation of the U.S. dollar versus the NIS in Israel and KES in Kenya. Risks attributable to fluctuations in currency exchange rates can arise when we or any of our foreign subsidiaries borrow funds or incur operating or other expenses in one type of currency but receive revenues in another. In such cases, an adverse change in exchange rates can reduce such subsidiary’s ability to meet its debt service obligations, reduce the amount of cash and income we receive from such foreign subsidiary, or increase such subsidiary’s overall expenses. In Kenya, the tax asset is recorded in KES similar to the tax liability, however any change in the exchange rate in the KES versus the USD has an impact on our financial results. Risks attributable to fluctuations in foreign currency exchange rates can also arise when the currency denomination of a particular contract is not the U.S. dollar. Substantially all of our PPAs in the international markets are either U.S. dollar-denominated or linked to the U.S. dollar except for our operations on Guadeloupe, where we own and operate the Boulliante power plant which sells its power under a Euro-denominated PPA with Électricité de France S.A. Our construction contracts from time to time contemplate costs which are incurred in local currencies. The way we often mitigate such risk is to receive part of the proceeds from the contract in the currency in which the expenses are incurred. Currently, we have forward contracts in place to reduce our foreign currency exposure and expect to continue to use currency exchange and other derivative instruments to the extent we deem such instruments to be the appropriate tool for managing such exposure. In the three months ended December 31, 2019, our exchange rate exposure in Kenya resulted in an expense of approximately $2.5 million.

We performed a sensitivity analysis on the fair values of our long-term debt obligations, and foreign currency exchange forward contracts. The foreign currency exchange forward contracts listed below principally relate to trading activities. The sensitivity analysis involved increasing and decreasing forward rates at December 31, 2019 and 2018 by a hypothetical 10% and calculating the resulting change in the fair values.

At this time, the development of our new strategic plan has not exposed us to any additional market risk. However, as the implementation of the plan progresses, we may be exposed to additional or different market risks.

The results of the sensitivity analysis calculations as of December 31, 2019 and 2018 are presented below:

(In thousands)

Risk Assuming a 10% Increase in Rates As of December 31, 2019 2018 Assuming a 10% Decrease in Rates As of December 31, 2019 2018 Change in the Fair Value of
Foreign Currency $(4,198) $(4,042) $5,131 $4,940 Foreign Currency Forward Contracts
Interest Rate $— $(113) $— $114 OrCal Senior Secured Notes
Interest Rate $(4,574) $(5,955) $4,723 $6,211 OFC 2 Senior Secured Notes
Interest Rate $(4,647) $(6,022) $4,812 $6,294 OPIC Loan
Interest Rate $(516) $(714) $534 $745 Amatitlan loan
Interest Rate $(1,797) $(3,054) $1,822 $3,118 Senior Unsecured Bonds
Interest Rate $(905) $(1,216) $934 $1,266 DEG 2 Loan
Interest Rate $(1,835) $(2,324) $1,906 $2,438 DAC 1 Senior Secured Notes
Interest Rate $(3,272) $(2,897) $3,363 $3,010 Migdal Loan and the Additional Migdal Loan
Interest Rate $(1,141) $(1,306) $1,207 $1,398 San Emidio Loan
Interest Rate $(776) $(1,153) $797 $1,197 DOE Loan
Interest Rate $(281) $(440) $286 $453 Idaho Holdings Loan
Interest Rate $(2,978) $(3,719) $3,099 $3,907 Platanares OPIC Loan
Interest Rate $(728) $— $749 $— DEG 3 Loan
Interest Rate $(342) $— $350 $— Plumstriker Loan
Interest Rate $(295) $— $298 $— Commercial Paper
Interest Rate $(201) $(143) $204 $148 Other long-term loans

In July 2019, the United Kingdom’s Financial Conduct Authority, which regulates LIBOR (London Interbank Offered Rate), announced that it intends to phase out LIBOR by the end of 2021. It is unclear whether or not LIBOR will cease to exist at that time and/or whether new methods of calculating LIBOR will be established such that it will continue to exist after 2021. The U.S. Federal Reserve, in conjunction with the Alternative Reference Rates Committee, a steering committee comprised of large U.S. financial institutions, is considering replacing U.S. dollar LIBOR with a new SOFR (Secured Overnight Financing Rate) index calculated by short-term repurchase agreements, backed by Treasury securities.

105

We have evaluated the impact of the transition from LIBOR, and currently believe that the transition will not have a material impact on our consolidated financial statements.

Effect of Inflation

We expect that inflation will not be a significant risk in the near term, given the current global economic conditions, however, that could change in the future. To address rising inflation some of our contracts include certain provisions that mitigate inflation risk.

In connection with the Electricity segment, none of our U.S. PPAs, including the SCPPA Portfolio PPA, are directly linked to the CPI. Inflation may directly impact an expense we incur for the operation of our projects, thereby increasing our overall operating costs and reducing our profit and gross margin. The negative impact of inflation would be partially offset by price adjustments built into some of our PPAs that could be triggered upon such occurrences. The energy payments pursuant to our PPAs for some of our power plants such as the Brady power plant, the Steamboat 2 and 3 power plants and the McGinness Complex, increase every year through the end of the relevant terms of such agreements, although such increases are not directly linked to the CPI or any other inflationary index. Lease payments are generally fixed, while royalty payments are generally calculated as a percentage of revenues and therefore are not significantly impacted by inflation. In our Product segment, inflation may directly impact fixed and variable costs incurred in the construction of our power plants, thereby increasing our operating costs in the Product segment. We are more likely to be able to offset all or part of this inflationary impact through our project pricing. With respect to power plants that we build for our own electricity production, inflationary pricing may impact our operating costs which may be partially offset in the pricing of the new long-term PPAs that we negotiate.

Contractual Obligations and Commercial Commitments

The following tables set forth our material contractual obligations as of December 31, 2019 (in thousands):

Payments Due by Period Remaining Total 2020 2021 2022 2023 2024 Thereafter
Long-term liabilities principal $1,167,912 $135,504 $76,259 $220,677 $98,982 $78,600 $557,890
Interest on long-term liabilities (1) 336,593 58,555 52,228 47,931 44,593 32,061 101,225
Finance lease obligations 19,854 4,251 3,948 3,873 2,758 906 4,118
Operating lease obligations 20,956 2,742 2,701 2,079 1,524 1,275 10,635
Benefits upon retirement (2) 19,803 4,780 1,434 1,768 89 500 11,232
Asset retirement obligation 50,183 — — — — — 50,183
Purchase commitments (3) 184,985 184,985 — — — — —
$1,800,286 $390,817 $136,570 $276,328 $147,946 $113,342 $735,283

(1) See interest rates and maturity dates under Liquidity and Capital Resources section above.

(2) The above amounts were determined based on employees’ current salary rates and the number of years’ service that will have been accumulated at their expected retirement date. These amounts do not include amounts that might be paid to employees that will cease working with us before reaching their expected retirement age.

(3) We purchase raw materials for inventories, construction-in-process and services from a variety of vendors. During the normal course of business, in order to manage manufacturing lead times and help assure adequate supply, we enter into agreements with contract manufacturers and suppliers that either allow them to procure goods and services based upon specifications defined by us, or that establish parameters defining our requirements. At December 31, 2019, total obligations related to such supplier agreements were approximately $185.0 million (approximately $59.5 million of which relate to construction-in-process). All such obligations are payable in 2020.

106

The table above does not reflect unrecognized tax benefits of $14.6 million, the timing of which is uncertain. Refer to Note 18 to our consolidated financial statements set forth in Item 8 of this annual report for additional discussion of unrecognized tax benefits. The above table also does not reflect a liability associated with the sale of tax benefits of $123.5 million, the timing of which is uncertain and other long-term liabilities of $6.8 million that are deemed immaterial. Refer to Note 13 to our consolidated financial statements as set forth in Item 8 of this annual report for additional discussion of our liability associated with the sale of tax benefits.

Concentration of Credit Risk

Our credit risk is currently concentrated with the following major customers: Sierra Pacific Power Company and Nevada Power Company (subsidiaries of NV Energy), KPLC and SCPPA. If any of these electric utilities fail to make payments under its PPAs with us, such failure would have a material adverse impact on our financial condition. Also, by implementing our multi-year strategic plan we may be exposed, by expanding our customer base, to different credit profile customers than our current customers.

Sierra Pacific Power Company and Nevada Power Company accounted for 17.1%, 16.1% and 18.1% of our total revenues for the three years ended December 31, 2019, 2018 and 2017, respectively.

KPLC accounted for 16.3%, 16.6%, and 15.9% of our total revenues for the three years ended December 31, 2019, 2018 and 2017, respectively.

SCPPA accounted for 17.9%, 15.2% and 10.1% of our total revenues for the three years ended December 31, 2019, 2018 and 2017, respectively.

We have historically been able to collect on substantially all of our receivable balances. As of December 31, 2019, the amount overdue from KPLC in Kenya was $40.7 million of which $24.2 million was paid in January and February of 2020. These amounts are an average of 70 days overdue, an increase of 10 days from September 30, 2019. In Honduras, we began collecting current charges from ENEE in May 2019; however, as of December 31, 2019, the amount overdue relating to the period from October 2018 to April 2019 is $20.1 million, none of which has been paid to date. Due to obligations of the Honduran government to support us, we believe we will be able to collect all past due amounts.

Government Grants and Tax Benefits

The U.S. federal government encourages production of electricity from geothermal resources or solar energy through certain tax subsidies:

  • PTC - the PTC rules provide an income tax credit for each kWh of electricity produced from certain renewable energy sources, including geothermal, and sold to an unrelated person during a taxable year. The PTC was first introduced in 1992 and has since been revised a number of times. The PTC, which in 2019 was 2.5 cents per kWh, is adjusted annually for inflation and may be claimed for 10 years on the net electricity output sold to third parties after the project is first placed in service. The tax extender package signed into law in December 2019 provides that any qualifying project that starts construction by December 31, 2020 would be eligible for PTC. The qualifying project must ordinarily be placed in service within four years after the end of the year in which construction started or show continued construction to qualify for PTC. The PTC is not available for power produced from geothermal resources for projects that started construction on or after January 1, 2021.
  • ITC - the ITC rules have been amended a number of times. A qualified new geothermal power plant in the United States that starts construction by the end of 2020 would be eligible to claim an ITC of 30% of the project cost. New solar projects that were under construction by December 2019 will qualify for a 30% ITC. The credit will phasedown to 26% for solar PV projects starting construction in 2020 and to 22% for solar PV projects starting construction in 2021. Projects that were under construction before these deadlines must be placed in service by December 31, 2023 to qualify for the ITC at these rates. solar projects placed in service after December 31, 2023 will only qualify for a 10% ITC. Under current tax rules, any unused tax credit has a one-year carry back and a twenty-year carry forward.

107

  • On December 22, 2017, the U.S. President signed into law the Tax Act, which made changes that have some impact on the renewable energy industry. Some of the key changes are as follows:
  • The U.S. corporate income tax rate was reduced from 35% to 21% beginning in 2018.
  • Bonus depreciation was increased from 40% expensing of qualified projects in year one to 100% beginning in on September 27, 2017. The 100% expensing is valid through 2022 and then declines through 2026.
  • The BEAT provision is a new tax intended to apply to companies that significantly reduce their U.S. tax liability by making cross-border payments to affiliates. The provision aims to circumvent earnings stripping by imposing a minimum tax of 10% of taxable income. ITC and PTC can be used to offset approximately 80% BEAT. See the discussion under Item 1A — “Risk Factors”.

We are also permitted to depreciate most of the cost of a new geothermal power plant. In cases where we claim the one-time 30% (or 10%) ITC, our tax basis in the plant that is eligible for depreciation is reduced by one-half of the ITC amount. In cases where we claim the PTC, there is no reduction in the tax basis for depreciation. Projects that were placed in service in 2016 and 2017 were eligible for “bonus” depreciation of 50% of the cost of that equipment in the year the power plant was placed in service. Following the Tax Act, projects that were or will be placed in service after September 27, 2017, could qualify for a 100% bonus depreciation with respect to its qualifying assets. After applying any depreciation bonus that is available, we can depreciate the remainder of our tax basis in the plant, if any, mostly over five years on an accelerated basis, meaning that more of the cost may be deducted in the first few years than during the remainder of the depreciation period. We will continue to analyze this new provision under the Act and determine if an election is appropriate as it relates to our business needs.

Ormat Systems received “Benefited Enterprise” status under Israel’s Law for Encouragement of Capital Investments, 1959 (the Investment Law), with respect to two of its investment programs through 2011. In January 2011, new legislation amending the Investment Law was enacted. Under the new legislation, a uniform rate of corporate tax will apply to all qualified income of certain industrial companies, as opposed to the previous law’s incentives that are limited to income from a “Benefited Enterprise” during their benefits period. As a result, we now pay a uniform corporate tax rate of 16% with respect to that qualified income.

Kenya tax audit

The Company received three letters from the Kenya Revenue Authority ("KRA") relating to certain findings in respect of its review of tax years 2013 to 2017 as described below:

The first Letter of Preliminary Findings was received in March 2019, which was followed by a Notice of Assessment during June 2019 in which the KRA demanded approximately $5.6 million from the Company, including interest and penalties in respect of two certain issues relating to its review of tax years 2014 to 2017. In July 2019, the Company responded to the KRA Notice of Assessment primarily objecting to one of the two issues raised in the assessment, consisting of approximately $4.4 million, and asked the KRA to vacate this issue as set forth in its tax assessment letter.

The Company received the second Letter of Preliminary Findings ("the Second Letter of Preliminary Findings") from the KRA in July 2019, which relates to findings from the KRA's audit review for tax years 2013 to 2017. In August 2019, the Company filed its response to the Second Letter of Preliminary Findings, contesting the KRA arguments and requesting that the KRA vacate all issues set forth in its Letter of Preliminary Findings. In December 2019, the KRA submitted its audit assessment letter in relation to the 2013 to 2017 tax years in which it demanded approximately $205 million from the Company, including interest and penalties in respect of the issues included in its Second Letter of Preliminary Findings. In January 2020, the Company responded to the KRA objecting to all the issues raised in the tax assessment for tax years 2013 to 2017 and asked the KRA to vacate all issues set forth in its tax assessment letter.

The Company received the third Letter of Preliminary Findings (the "Third Letter of Preliminary Findings") from the KRA in December 2019 relating to the same tax years in which the KRA set forth an additional demand for approximately $17 million, including interest and penalties, in relation to an additional audit finding which was not previously included in the KRA's assessments. In January 2020, the Company filed a formal objection to the Third Letter of Preliminary Findings, contesting the KRA's finding.

The Company is currently at different stages of discussions with the KRA on the matters included in the KRA letters of assessment and preliminary findings as described above and believes its tax positions for the issues raised during the audit period is more-likely-than-not sustainable based on technical merits under Kenyan tax law. As of December 31, 2019, the Company has not recorded any tax reserves related to these demands except for an immaterial amount included in the first Letter of Preliminary Findings.

Market risk

As filed, 173 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Information responding to Item 7A is included in Item 7 — “Management’s Discussion and Analysis of Financial Condition and Results of Operations” of this annual report.

108

Controls and procedures

As filed, 6,799 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Disclosure Controls and Procedures

Evaluation of disclosure controls and procedure. Our management, including our Chief Executive Officer and Chief Financial Officer, have conducted the evaluation of our disclosure controls and procedures (as such term is defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act) required by Rules 13a-15(b) or 15d-15(b) under the Exchange Act, as amended. Based on that evaluation, our management, including our Chief Executive Officer and Chief Financial Officer, concluded that our disclosure controls and procedures were not effective as of December 31, 2019 as a result of a material weakness in our internal control over financial reporting that existed at December 31, 2017 and has not been remediated by the end of the period covered by this Annual Report on Form 10-K.

Management’s Report on Internal Control over Financial Reporting

Our management, including our Chief Executive Officer and Chief Financial Officer, is responsible for establishing and maintaining adequate internal control over financial reporting as described in Rules 13a-15(f) and 15d-15(f) under the Securities Exchange Act of 1934, as amended, or the Exchange Act. Internal control over financial reporting is defined as a process designed by, or under the supervision of, the issuer’s principal executive and principal financial officers, or persons performing similar functions, and effected by the issuer’s board of directors, management and other personnel, to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles and includes those policies and procedures that: (1) pertain to the maintenance of records that in reasonable detail accurately and fairly reflect the transactions and dispositions of the assets of the issuer, (2) provide reasonable assurance that transactions are recorded as necessary to permit preparation of financial statements in accordance with generally accepted accounting principles, and that receipts and expenditures of the issuer are being made only in accordance with authorizations of management and directors of the issuer and (3) provide reasonable assurance regarding prevention or timely detection of unauthorized acquisition, use or disposition of the issuer’s assets that could have a material effect on the financial statements.

Because of its inherent limitations, internal control over financial reporting may not prevent or detect misstatements. Also, projections of any evaluation of effectiveness to future periods are subject to the risk that controls may become inadequate because of changes in our conditions, or that the degree of compliance with our policies or procedures may deteriorate.

Evaluation of effectiveness of internal control over financial reporting. Our management, under the supervision and participation of our Chief Executive Officer and our Chief Financial Officer, has conducted an evaluation of the effectiveness of our internal control over financial reporting as of December 31, 2019 using criteria established in Internal Control - Integrated Framework (2013) issued by the COSO and, based on this evaluation, concluded that our internal control over financial reporting was not effective as of December 31, 2019 as a result of the material weakness in our internal control over financial reporting discussed below. A material weakness is a deficiency, or a combination of deficiencies, in internal control over financial reporting, such that there is a reasonable possibility that a material misstatement of our annual or interim financial statements will not be prevented or detected on a timely basis.

Material weakness. In connection with the change in our repatriation strategy and the related release of the US income tax valuation allowance in the second quarter of 2017, we did not perform an effective risk assessment related to our internal controls over the accounting for income taxes. As a result, we identified a deficiency in the design of our internal control over financial reporting related to our accounting for income taxes, which resulted in the restatements of our unaudited condensed consolidated financial statements for the three and six months ended June 30, 2017, the three and nine months ended September 30, 2017, and the restatement of our consolidated financial statements for the year ended December 31, 2017. Our management has concluded that this deficiency constitutes a material weakness in our internal control over financial reporting.

179

The effectiveness of the Company’s internal control over financial reporting as of December 31, 2019 has been audited by Kesselman & Kesselman, Certified Public Accountants (Isr.), a member firm of PricewaterhouseCoopers International Limited, an independent registered public accounting firm, as stated in their report which appears in this Annual Report on Form 10-K.

Remediation Plan

Our management, with the oversight of the Audit Committee of the Board of Directors, has continued the process of remediating the material weakness. In connection with the remediation process, we have:

  • performed an enhanced risk assessment related to our internal controls over the accounting for income taxes;
  • recruited additional tax personnel throughout the year, including a VP of Tax in January 2019 and a Director of Tax in September 2019;
  • engaged an external tax and accounting firm to prepare and review our annual and quarterly income tax provision;
  • implemented specific control procedures for the review, analysis and reporting of our income tax accounts, including control procedures of projections that support the deferred tax assets and liabilities;
  • strengthened our income tax controls with improved documentation, communication and oversight.

We have made substantial progress in developing and implementing our remediation plan, as we are adding to and improving our internal processes. The remaining tasks of our remediation plan is the hiring of additional personnel, implement automation of the key elements of the tax provision and modify controls as applicable in respect of such tasks in order to reduce the risk of material misstatement. The material weakness will not be considered remediated until those controls operate for a sufficient period of time and management has concluded, through testing, that those controls are operating effectively.

Changes in Internal Control over Financial Reporting

There were no changes in our internal control over financial reporting in the fourth quarter of 2019 that have materially affected or are reasonably likely to materially affect our internal control over financial reporting.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2019-12-31. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Revenue3 months2019-10-01 to 2019-12-31$192.4mus-gaap:Revenues
Revenue12 months2019-01-01 to 2019-12-31$746.0mus-gaap:RevenueFromContractWithCustomerIncludingAssessedTax
Cost of revenue3 months2019-10-01 to 2019-12-31$117.9mus-gaap:CostOfGoodsAndServicesSold
Cost of revenue12 months2019-01-01 to 2019-12-31$476.7mus-gaap:CostOfGoodsAndServicesSold
Gross profit3 months2019-10-01 to 2019-12-31$74.5mus-gaap:GrossProfit
Gross profit12 months2019-01-01 to 2019-12-31$269.3mus-gaap:GrossProfit
Research and development3 months2019-10-01 to 2019-12-31$1.9mus-gaap:ResearchAndDevelopmentExpense
Research and development12 months2019-01-01 to 2019-12-31$4.6mus-gaap:ResearchAndDevelopmentExpense
Operating income3 months2019-10-01 to 2019-12-31$54.5mus-gaap:OperatingIncomeLoss
Operating income12 months2019-01-01 to 2019-12-31$193.8mus-gaap:OperatingIncomeLoss
Interest expense3 months2019-10-01 to 2019-12-31$17.6mus-gaap:InterestExpense
Interest expense12 months2019-01-01 to 2019-12-31$80.4mus-gaap:InterestExpense
Income tax3 months2019-10-01 to 2019-12-31$25.5mus-gaap:IncomeTaxExpenseBenefit
Income tax12 months2019-01-01 to 2019-12-31$45.6mus-gaap:IncomeTaxExpenseBenefit
Net income3 months2019-10-01 to 2019-12-31$12.6mus-gaap:NetIncomeLoss
Net income12 months2019-01-01 to 2019-12-31$88.1mus-gaap:NetIncomeLoss
Diluted EPS3 months2019-10-01 to 2019-12-31$0.24us-gaap:EarningsPerShareDiluted
Diluted EPS12 months2019-01-01 to 2019-12-31$1.72us-gaap:EarningsPerShareDiluted
Basic EPS3 months2019-10-01 to 2019-12-31$0.25us-gaap:EarningsPerShareBasic
Basic EPS12 months2019-01-01 to 2019-12-31$1.73us-gaap:EarningsPerShareBasic
Diluted shares (weighted)3 months2019-10-01 to 2019-12-3151,511,000 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Diluted shares (weighted)12 months2019-01-01 to 2019-12-3151,227,000 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Operating cash flow12 months2019-01-01 to 2019-12-31$236.5mus-gaap:NetCashProvidedByUsedInOperatingActivities
Capital expenditure12 months2019-01-01 to 2019-12-31$280.0mus-gaap:PaymentsToAcquirePropertyPlantAndEquipment
Dividends paid12 months2019-01-01 to 2019-12-31$22.4mus-gaap:PaymentsOfDividendsCommonStock
Cash and equivalentsAt period end2019-12-31$71.2mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2019-12-31$415.7mus-gaap:AssetsCurrent
Total assetsAt period end2019-12-31$3.25bnus-gaap:Assets
Current liabilitiesAt period end2019-12-31$376.5mus-gaap:LiabilitiesCurrent
Total liabilitiesAt period end2019-12-31$1.73bnus-gaap:Liabilities
Long-term debtAt period end2019-12-31$1.17bnus-gaap:LongTermDebt
Short-term borrowingsAt period end2019-12-31$50.0mus-gaap:CommercialPaper
Shareholders' equityAt period end2019-12-31$1.39bnus-gaap:StockholdersEquity

Source: SEC EDGAR, the filing index for accession 0001437749-20-004072. Last ingested by Listed: Nov 5, 2026, 13:18 ET. Listed shows no prices and gives no investment advice.