Management's discussion and analysis

As filed, 63,626 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

You should read the following discussion and analysis of our financial condition and results of operations together with our unaudited condensed consolidated financial statements and the related notes thereto included in Part I, Item 1 of this Quarterly Report on Form 10-Q and the audited consolidated financial statements and notes thereto and management’s discussion and analysis of financial condition and results of operations for the year ended December 31, 2012 included in our Annual Report on Form 10-K for the year ended December 31, 2012 filed on March 18, 2013 with the U.S. Securities and Exchange Commission, or SEC. This Quarterly Report on Form 10-Q contains “forward-looking statements” within the meaning of Section 21E of the Securities Exchange Act of 1934, as amended, or the Exchange Act. All statements, other than statements of historical fact, including statements that refer to projections regarding our future financial performance, our anticipated growth and trends in our businesses, our future capital needs and capital expenditures; our future market position and competitive changes in the marketplace for our services; our ability to integrate new technologies into our services; our ability to access credit or capital markets; our reliance on subcontractors; potential acquisitions or divestitures; the continued availability of key personnel; and other characterizations of future events or circumstances are forward-looking statements. These statements are often, but not exclusively, identified by the use of words such as “may,” “will,” “expect,” “believe,” “anticipate,” “intend,” “could,” “estimate,” “target,” “project,” “predict” or “continue,” and similar expressions or variations. These forward-looking statements are based on current expectations and assumptions that are subject to risks, uncertainties and other factors that could cause actual results and the timing of certain events to differ materially and adversely from future results expressed or implied by such forward-looking statements. Risks, uncertainties and factors that could cause or contribute to such differences include, but are not limited to, those discussed in the section titled “Risk Factors,” set forth in Item 1A of our Annual Report on Form 10-K for the year ended December 31, 2012 and elsewhere in this Report. The forward-looking statements in this Quarterly Report on Form 10-Q represent our views as of the date of this Quarterly Report on Form 10-Q. Subsequent events and developments may cause our views to change. However, while we may elect to update these forward-looking statements at some point in the future, we undertake no obligation to do so except to the extent required by applicable law. You should, therefore, not rely on these forward-looking statements as representing our views as of any date subsequent to the date of this Quarterly Report on Form 10-Q.

Overview

Ameresco is a leading provider of energy efficiency solutions for facilities throughout North America. We provide solutions that enable customers to reduce their energy consumption, lower their operating and maintenance costs and realize environmental benefits. Our comprehensive set of services includes upgrades to a facility’s energy infrastructure and the construction and operation of small-scale renewable energy plants.

We report results under ASC 280, Segment Reporting, for four segments: U.S. federal, central U.S. region, other U.S. regions and Canada. Each segment provides customers with energy efficiency and renewable energy solutions. These segments do not include results of other activities, such as certain operations and maintenance, or O&M, and sales of renewable energy and certain other renewable energy products, that are managed centrally at our corporate headquarters, or corporate operating expenses not specifically allocated to the segments. See Note 12 to our unaudited condensed consolidated financial statements appearing in Part I, Item 1 of this Quarterly Report on Form 10-Q.

In addition to organic growth, strategic acquisitions of complementary businesses and assets have been an important part of our historical development. Since inception, we have completed numerous acquisitions, which have enabled us to broaden our service offerings and expand our geographical reach. Our acquisition of the energy services business of Duke Energy in 2002 expanded our geographical reach into Canada and the southeastern United States and enabled us to penetrate the federal government market for energy efficiency projects. The acquisition of the energy services business of Exelon in 2004 expanded our geographical reach into the Midwest. Our acquisition of the energy services business of Northeast Utilities in 2006 substantially grew our capability to provide services for the federal market and in Europe. Our acquisition of Southwestern Photovoltaic in 2007 significantly expanded our offering of solar energy products and services. Our acquisition of energy services company Quantum Engineering and Development, Inc., or Quantum, in 2010 expanded our geographical reach into the northwest U.S.

We made three acquisitions in 2011. Our acquisition of energy efficiency and demand side management consulting services provider Applied Energy Group, Inc., or AEG, expanded our service offering to utility customers. Our acquisition of APS Energy Services Company, Inc., which we renamed Ameresco Southwest, a company that provides a full range of integrated energy efficiency and renewable energy solutions, strengthened our geographical position in the southwest U.S. Our acquisition of the xChangePoint® and energy projects businesses from Energy and Power Solutions, Inc., which we operate as Ameresco Intelligent Systems, or AIS, expanded our service offerings to private sector commercial and industrial customers. AIS offers energy efficiency solutions to customers across North America encompassing the food and beverage, meat, dairy, paper, aerospace, oil and gas and REIT industries.

Our acquisition of infrastructure asset management solutions provider FAME Facility Software Solutions Inc. in 2012 expanded our asset planing consulting and software services offerings and our geographical position in western Canada. Our acquisition of the business of Ennovate Corporation, or Ennovate, in the first quarter of 2013 increased our footprint and penetration in the Rocky Mountain area.

Energy Savings Performance and Energy Supply Contracts

For our energy efficiency projects, we typically enter into energy savings performance contracts, or ESPCs, under which we agree to develop, design, engineer and construct a project and also commit that the project will satisfy agreed-upon performance standards that vary from project to project. These performance commitments are typically based on the design, capacity, efficiency or operation of the specific equipment and systems we install. Our commitments generally fall into three categories: pre-agreed, equipment-level and whole building-level. Under a pre-agreed energy reduction commitment, our customer reviews the project design in advance and agrees that, upon or shortly after completion of installation of the specified equipment comprising the project, the commitment will have been met. Under an equipment-level commitment, we commit to a level of energy use reduction based on the difference in use measured first with the existing equipment and then with the replacement equipment. A whole building-level commitment requires demonstration of energy usage reduction for a whole building, often based on readings of the utility meter where usage is measured. Depending on the project, the measurement and demonstration may be required only once, upon installation, based on an analysis of one or more sample installations, or may be required to be repeated at agreed upon intervals generally over up to 20 years.

Under our contracts, we typically do not take responsibility for a wide variety of factors outside our control and exclude or adjust for such factors in commitment calculations. These factors include variations in energy prices and utility rates, weather, facility occupancy schedules, the amount of energy-using equipment in a facility, and the failure of the customer to operate or maintain the project properly. Typically, our performance commitments apply to the aggregate overall performance of a project rather than to individual energy efficiency measures. Therefore, to the extent an individual measure underperforms, it may be offset by other measures that overperform during the same period. In the event that an energy efficiency project does not perform according to the agreed-upon specifications, our agreements typically allow us to satisfy our obligation by adjusting or modifying the installed equipment, installing additional measures to provide substitute energy savings, or paying the customer for lost energy savings based on the assumed conditions specified in the agreement. Many of our equipment supply, local design, and installation subcontracts contain provisions that enable us to seek recourse against our vendors or subcontractors if there is a deficiency in our energy reduction commitment. From our inception to March 31, 2013, our total payments to customers and incurred costs under our energy reduction commitments, after customer acceptance of a project, have been less than $100,000 in the aggregate. See “We may have liability to our customers under our ESPCs if our projects fail to deliver the energy use reductions to which we are committed under the contract” in Item 1A, Risk Factors in our Annual Report on Form 10-K.

Payments by the federal government for energy efficiency measures are based on the services provided and the products installed, but are limited to the savings derived from such measures, calculated in accordance with federal regulatory guidelines and the specific contract’s terms. The savings are typically determined by comparing energy use and other costs before and after the installation of the energy efficiency measures, adjusted for changes that affect energy use and other costs but are not caused by the energy efficiency measures.

For projects involving the construction of a small-scale renewable energy plant that we own and operate, we enter into long-term contracts to supply the electricity, processed landfill gas, or LFG, heat or cooling generated by the plant to the customer, which is typically a utility, municipality, industrial facility or other large purchaser of energy. The rights to use the site for the plant and purchase of renewable fuel for the plant are also obtained by us under long-term agreements with terms at least as long as the associated output supply agreement. Our supply agreements typically provide for fixed prices or prices that escalate at a fixed rate or vary based on a market benchmark. See “We may assume responsibility under customer contracts for factors outside our control, including, in connection with some customer projects, the risk that fuel prices will increase” in Item 1A, Risk Factors in our Annual Report on Form 10-K.

Project Financing

To finance projects with federal governmental agencies, we typically sell to third-party lenders our right to receive a portion of the long-term payments from the customer arising out of the project for a purchase price reflecting a discount to the aggregate amount due from the customer. The purchase price is generally advanced to us over the implementation period based on completed work or a schedule predetermined to coincide with the construction of the project. Under the terms of these financing arrangements, we are required to complete the construction or installation of the project in accordance with the contract with our customer, and the debt remains on our consolidated balance sheet until the completed project is accepted by the customer. Once the completed project is accepted by the customer, the financing is treated as a true sale and the related receivable and financing liability are removed from our consolidated balance sheet.

Institutional customers, such as state, provincial and local governments, schools and public housing authorities, typically finance their energy efficiency and renewable energy projects through either tax-exempt leases or issuances of municipal bonds. We assist in the structuring of such third-party financing.

In some instances, customers prefer that we retain ownership of the renewable energy plants and related project assets that we construct for them. In these projects, we typically enter into a long-term supply agreement to furnish electricity, gas, heat or cooling to the customer’s facility. To finance the significant upfront capital costs required to develop and construct the plant, we rely either on our internal cash flow or, in some cases, third-party debt. For project financing by third-party lenders, we typically establish a separate subsidiary, usually a limited liability company, to own the project assets and related contracts. The subsidiary contracts with us for construction and operation of the project and enters into a financing agreement directly with the lenders. Additionally, we will provide assurance to the lender that the project will achieve commercial operation. Although the financing is secured by the assets of the subsidiary and a pledge of our equity interests in the subsidiary, and is non-recourse to Ameresco, Inc., we may from time to time determine to provide financial support to the subsidiary in order to maintain rights to the project or otherwise avoid the adverse consequences of a default. The amount of such financing is included on our consolidated balance sheet.

In addition to project-related debt, we currently maintain a $100 million senior secured credit facility with a group of commercial banks to finance our working capital needs. See “—Senior Secured Credit Facility—Revolver and Term Loan” below.

Effects of Seasonality

We are subject to seasonal fluctuations and construction cycles, particularly in climates that experience colder weather during the winter months, such as the northern United States and Canada, or at educational institutions, where large projects are typically carried out during summer months when their facilities are unoccupied. In addition, government customers, many of which have fiscal years that do not coincide with ours, typically follow annual procurement cycles and appropriate funds on a fiscal-year basis even though contract performance may take more than one year. Further, government contracting cycles can be affected by the timing of, and delays in, the legislative process related to government programs and incentives that help drive demand for energy efficiency and renewable energy projects. As a result, our revenue and operating income in the third quarter are typically higher, and our revenue and operating income in the first quarter are typically lower, than in other quarters of the year. As a result of such fluctuations, we may occasionally experience declines in revenue or earnings as compared to the immediately preceding quarter, and comparisons of our operating results on a period-to-period basis may not be meaningful.

Our annual and quarterly financial results are also subject to significant fluctuations as a result of other factors, many of which are outside our control. See “Our operating results may fluctuate significantly from quarter to quarter and may fall below expectations in any particular fiscal quarter” in Item 1A, Risk Factors in our Annual Report on Form 10-K.

Backlog and Awarded Projects

Total construction backlog represents projects that are active within our ESPC sales cycle. Our sales cycle begins with the initial contact with the customer and ends, when successful, with a signed contract, also referred to as fully-contracted backlog. Historically, our sales cycle typically has averaged 12 to 36 months. Awarded backlog is created when a potential customer awards a project to Ameresco following a request for proposal. Once a project is awarded but not yet contracted, we typically conduct a detailed energy audit to determine the scope of the project as well as identify the savings that may be expected to be generated from upgrading the customer’s energy infrastructure. At this point, we also determine the sub-contractor, what equipment will be used, and assist in arranging for third party financing, as applicable. Historically, awarded projects typically have taken 6 to 12 months to result in a signed contract and thus convert to fully-contracted backlog. It may take longer, however, depending upon the size and complexity of the project. Further, at times in the past we have experienced periods during which the portion of the sales cycle for converting awarded project to signed contracts has lengthened. Recently, we have been experiencing an unusually sustained lengthening of conversion times. Continued U.S. federal fiscal uncertainty not only has contributed to a lengthening of our sales cycle for U.S. federal projects, but also has adversely affected both municipal and commercial customers across most geographic regions. We have observed among our existing and prospective customer base increased scrutiny of decisions about spending and about incurring debt to finance projects. For example, we have observed increased use of outside consultants and advisors, as well as adoption of additional approval steps, by many of our customers, which has resulted in a lengthening of the sales cycle. We expect this trend to continue in 2013. After the customer and Ameresco agree to the terms of the contract and the contract becomes executed, the project moves to fully-contracted backlog. The contracts reflected in our fully-contracted backlog typically have a construction period of 12 to 24 months and we typically expect to recognize revenue for such contracts over the same period. Fully-contracted backlog begins converting into revenue generated from backlog on a percentage-of-completion basis once construction has commenced. See “We may not recognize all revenue from our backlog or receive all payments anticipated under awarded projects and customer contracts” and “In order to secure contracts for new projects, we typically face a long and variable selling cycle that requires significant resource commitments and requires a long lead time before we realize revenue” in Item 1A, Risk Factors in our Annual Report on Form 10-K.

As of March 31, 2013, we had backlog of approximately $344 million in expected future revenue under signed customer contracts for the installation or construction of projects, which we sometimes refer to as fully-contracted backlog; and we also had been awarded projects for which we do not yet have signed customer contracts with estimated total future revenue of an additional $1.165 billion. As of March 31, 2012, we had fully-contracted backlog of approximately $413 million in expected future revenue under signed customer contracts for the installation or construction of projects; and we also had been awarded projects for which we had not yet signed customer contracts with estimated total future revenue of an additional $872 million.

Financial Operations Overview

Revenue

We derive revenue from energy efficiency and renewable energy products and services. Our energy efficiency products and services include the design, engineering and installation of equipment and other measures to improve the efficiency and control the operation of a facility’s energy infrastructure. Our renewable energy products and services include: the construction of small-scale plants that produce electricity, gas, heat or cooling from renewable sources of energy and the sale of such electricity, processed LFG, heat or cooling from plants that we own, which, for those plants that we own and operate, we refer to collectively as small scale infrastructure; and the sale and installation of photovoltaic solar energy products and systems, or integrated-PV.

While in any particular quarter a single customer may account for more than ten percent of revenue, for the three months ended March 31, 2013 and 2012, no one customer accounted for more than ten percent of our total revenue.

Direct Expenses and Gross Margin

Direct expenses include the cost of labor, materials, equipment, subcontracting and outside engineering that are required for the development and installation of our projects, as well as preconstruction costs, sales incentives, associated travel, inventory obsolescence charges, amortization of intangible assets related to customer contracts, and, if applicable, costs of procuring financing. A majority of our contracts have fixed price terms; however, in some cases we negotiate protections, such as a cost-plus structure, to mitigate the risk of rising prices for materials, services and equipment.

Direct expenses also include O&M costs for the small-scale renewable energy plants that we own, including the cost of fuel (if any) and depreciation charges.

As a result of several of our acquisitions, we now have intangible assets related to customer contracts; these are amortized over a period of approximately one to five years from the respective date of acquisition. This amortization is recorded as a direct expense for energy efficiency. Amortization expense for the three months ended March 31, 2013 and 2012, related to customer contracts was $0.2 million and $1.0 million, respectively, and is included in energy efficiency expenses in the condensed consolidated statements of (loss) income.

Gross margin, which is gross profit as a percent of revenue, is affected by a number of factors, including the type of services performed and the geographic region in which the sale is made. Renewable energy projects that we own and operate typically have higher margins than energy efficiency projects, and sales in the United States typically have higher margins than in Canada due to the typical mix of products and services that we sell there.

In addition, gross margin frequently varies across the construction period of a project. Our expected gross margin on, and expected revenue for, a project are based on budgeted costs. From time to time, a portion of the contingencies reflected in budgeted costs are not incurred due to strong execution performance. In that case, and generally at project completion, we recognize revenue for which there is no further corresponding direct expense. As a result, gross margin tends to be back-loaded for projects with strong execution performance; this explains the gross margin improvement that occurs from time to time at project closeout. We refer to this gross margin improvement at the time of project completion as a project closeout.

Operating Expenses

Operating expenses consist of salaries and benefits, project development costs, and general, administrative and other expenses.

Salaries and benefits. Salaries and benefits consist primarily of expenses for personnel not directly engaged in specific project or revenue generating activity. These expenses include the time of executive management, legal, finance, accounting, human resources, information technology and other staff not utilized in a particular project. We employ a comprehensive time card system which creates a contemporaneous record of the actual time by employees on project activity.

Project development costs. Project development costs consist primarily of sales, engineering, legal, finance and third-party expenses directly related to the development of a specific customer opportunity. This also includes associated travel and marketing expenses.

General, administrative and other expenses. These expenses consist primarily of rents and occupancy, professional services, insurance, unallocated travel expenses, telecommunications, office expenses and amortization of intangible assets not related to customer contracts. Professional services consist principally of recruiting costs, external legal, audit, tax and other consulting services. For the three months ended March 31, 2013 and 2012, the Company recorded amortization expense of $0.7 million and $0.7 million, respectively, related to customer relationships, non-compete agreements, technology and trade names. Amortization expense related to these intangible assets is included in general, administrative and other expenses in the condensed consolidated statements of (loss) income.

Other Expenses, Net

Other expenses, net consists primarily of interest income on cash balances, interest expense on borrowings, amortization of deferred financing costs and unrealized gains and losses on derivatives not accounted for as hedges. Interest expense will vary periodically depending on the amounts drawn on our revolving senior secured credit facility and the prevailing short-term interest rates.

Provision for Income Taxes

The provision for income taxes is based on various rates set by federal and local authorities and is affected by permanent and temporary differences between financial accounting and tax reporting requirements.

Critical Accounting Policies and Estimates

This discussion and analysis of our financial condition and results of operations is based upon our condensed consolidated financial statements, which have been prepared in accordance with accounting principles generally accepted in the United States. The preparation of these condensed consolidated financial statements requires management to make estimates and assumptions that affect the reported amounts of assets, liabilities, revenue, expense and related disclosures. The most significant estimates with regard to these condensed consolidated financial statements relate to estimates of final contract profit in accordance with long-term contracts, project development costs, project assets, impairment of goodwill, impairment of long-lived assets, fair value of derivative financial instruments, income taxes and stock-based compensation expense. Such estimates and assumptions are based on historical experience and on various other factors that management believes to be reasonable under the circumstances. Estimates and assumptions are made on an ongoing basis, and accordingly, the actual results may differ from these estimates under different assumptions or conditions.

The following are certain critical accounting policies that among others, affect our more significant judgments and estimates used in the preparation of our condensed consolidated financial statements. For a more complete discussion of our critical accounting policies and estimates, please read Item 7. “Management’s Discussion and Analysis of Financial Condition and Results of Operations” of our Annual Report on Form 10-K.

Revenue Recognition

For each arrangement we have with a customer, we typically provide a combination of one or more of the following services or products:

  • installation or construction of energy efficiency measures, facility upgrades and/or a renewable energy plant to be owned by the customer;
  • sale and delivery, under long-term agreements, of electricity, gas, heat, chilled water or other output of a renewable energy or central plant that we own and operate;
  • sale and delivery of photovoltaic, or PV, equipment and other renewable energy products for which we are a distributor, whether under our own brand name or for others; and
  • O&M services provided under long-term O&M agreements, as well as consulting services.

Often, we will sell a combination of these services and products in a bundled arrangement. We divide bundled arrangements into separate deliverables and revenue is allocated to each deliverable based on the relative selling price. The relative selling price is determined using third party evidence or management’s best estimate of selling price.

We recognize revenue from the installation or construction of a project on a percentage-of-completion basis. The percentage-of-completion for each project is determined on an actual cost-to-estimated final cost basis. In accordance with industry practice, we include in current assets and liabilities the amounts of receivables related to construction projects that are payable over a period in excess of one year. We recognize revenue associated with contract change orders only when the authorization for the change order has been properly executed and the work has been performed and accepted by the customer.

When the estimate on a contract indicates a loss, or claims against costs incurred reduce the likelihood of recoverability of such costs, our policy is to record the entire expected loss immediately, regardless of the percentage of completion.

Deferred revenue represents circumstances where (i) there has been a receipt of cash from the customer for work or services that have yet to be performed, (ii) receipt of cash where the product or service may not have been accepted by the customer or (iii) when all other revenue recognition criteria have been met, but an estimate of the final total cost cannot be determined. Deferred revenue will vary depending on the timing and amount of cash receipts from customers and can vary significantly depending on specific contractual terms. As a result, deferred revenue is likely to fluctuate from period to period. Unbilled revenue, presented as costs and estimated earnings in excess of billings, represent amounts earned and billable that were not invoiced at the end of the fiscal period.

We recognize revenue from the sale and delivery of products, including the output of our renewable energy plants, when produced and delivered to the customer, in accordance with the specific contract terms, provided that persuasive evidence of an arrangement exists, our price to the customer is fixed or determinable and collectability is reasonably assured.

We recognize revenue from O&M contracts and consulting services as the related services are performed.

For a limited number of contracts under which we receive additional revenue based on a share of energy savings, we recognize such additional revenue as energy savings are generated.

Project Assets

We capitalize interest costs relating to construction financing during the period of construction. The interest capitalized is included in the total cost of the project at completion. The amount of interest capitalized for the three months ended March 31, 2013 and 2012 was $0.5 million and $0.1 million, respectively.

Routine maintenance costs are expensed in the current year’s condensed consolidated statements of (loss) income to the extent that they do not extend the life of the asset. Major maintenance, upgrades and overhauls are required for certain components of our assets. In these instances, the costs associated with these upgrades are capitalized and are depreciated over the shorter of the life of the asset or until the next required major maintenance or overhaul period. Gains or losses on disposal of property and equipment are reflected in general, administrative and other expenses in the condensed consolidated statements of (loss) income.

We evaluate our long-lived assets for impairment as events or changes in circumstances indicate the carrying value of these assets may not be fully recoverable. We evaluate recoverability of long-lived assets to be held and used by estimating the undiscounted future cash flows before interest associated with the expected uses and eventual disposition of those assets. When these comparisons indicate that the carrying value of those assets is greater than the undiscounted cash flows, we recognize an impairment loss for the amount that the carrying value exceeds the fair value.

Derivative Financial Instruments

We account for our interest rate swaps as derivative financial instruments in accordance with the related guidance. Under this guidance, derivatives are carried on our consolidated balance sheet at fair value. The fair value of our interest rate swaps is determined based on observable market data in combination with expected cash flows for each instrument.

We follow the guidance which expands the disclosure requirements for derivative instruments and hedging activities.

In the normal course of business, we utilize derivative contracts as part of our risk management strategy to manage exposure to market fluctuations in interest rates. These instruments are subject to various credit and market risks. Controls and monitoring procedures for these instruments have been established and are routinely reevaluated. Credit risk represents the potential loss that may occur because a party to a transaction fails to perform according to the terms of the contract. The measure of credit exposure is the replacement cost of contracts with a positive fair value. We seek to manage credit risk by entering into financial instrument transactions only through counterparties that we believe to be creditworthy. Market risk represents the potential loss due to the decrease in the value of a financial instrument caused primarily by changes in interest rates. We seek to manage market risk by establishing and monitoring limits on the types and degree of risk that may be undertaken. As a matter of policy, we do not use derivatives for speculative purposes.

We are exposed to interest rate risk through our borrowing activities. A portion of our project financing includes four credit facilities, both project related and corporate, that utilize a variable rate swap instrument.

  • Prior to December 31, 2009, we entered into two 15-year interest rate swap contracts under which we agreed to pay an amount equal to a specified fixed rate of interest times a notional principal amount, and to, in turn, receive an amount equal to a specified variable rate of interest times the same notional principal amount.
  • During the year ended December 31, 2010, we entered into a 14-year interest rate swap contract under which we agreed to pay an amount equal to a specified fixed rate of interest times a notional principal amount, and to in turn receive an amount equal to a specified variable rate of interest times the same notional principal amount.
  • In July 2011, we entered into a five-year interest rate swap contract under which we agreed to pay an amount equal to a specified fixed rate of interest times a notional amount, and to in turn receive an amount equal to a specified variable rate of interest times the same notional principal amount. The 2011 swap covers an initial notional amount of approximately $38.6 million variable rate note at a fixed interest rate of 1.965% and expires in June 2016.
  • In October 2012, and in connection with a construction and term loan, we entered into two eight-year interest rate swap contracts under which we agreed to pay an amount equal to a specified fixed rate of interest times a notional principal amount, and to in turn receive an amount equal to a specified variable rate of interest times the same notional principal amount. The swaps have an initial notional amount of $16.8 million, which increases to $42.2 million on September 30, 2013, at a fixed rate of 1.71%, and expires in March 2020.
  • In October 2012, we also entered into two eight-year forward starting interest rate swap contracts under which the Company agreed to pay an amount equal to specified fixed rate of interest times a notional amount, and to in turn receive an amount equal to a specified variable rate of interest times the same notional principal amount. The swaps cover an initial notional amount of $25.4 million variable rate note at a fixed interest rate of 3.70%, with an effective date of March 31, 2020, and expires in June 2028.

We entered into each of the interest rate swap contracts as an economic hedge.

We recognize all derivatives in our condensed consolidated financial statements at fair value.

The interest rate swaps that we entered into prior to December 31, 2009 qualified, but were not designated as cash flow hedges until April 1, 2010. Accordingly, any changes in fair value through March 31, 2010 were reported in other income (expense) in our condensed consolidated statements of (loss) income at fair value, and in the condensed consolidated statements of comprehensive (loss) income thereafter. Cash flows from these derivative instruments are reported as operating activities on the condensed consolidated statements of cash flows.

The interest rate swap that we entered into in March 2010 was a floating-to-fixed interest rate swap. Effective March 29, 2013, the Company has designated the March 2010 interest rate swap as a hedge using the “long-haul” method. See Note 2, Restatement, of “Notes to Condensed Consolidated Financial Statements” appearing in Item 1 of this Form 10-Q.

The interest rate swaps that we entered into during 2011 and 2012 qualify, and have been designated, as cash flow hedges.

We recognize the fair value of derivative instruments designated as hedges in our consolidated balance sheets and any changes in the fair value are recorded as adjustments to other comprehensive income (loss).

Business Segments

We report four segments: U.S. federal, central U.S. region, other U.S. regions and Canada. Each segment provides customers with energy efficiency and renewable energy solutions. The other U.S. regions segment is an aggregation of four regions: northeast U.S., southeast U.S., southwest U.S. and northwest U.S. These regions have similar economic characteristics — in particular, expected and actual gross profit margins. In addition, they sell products and services of a similar nature, serve similar types of customers and use similar methods to distribute their products and services. Accordingly, these four regions meet the aggregation criteria set forth in ASC 280. The “all other” category includes activities, such as certain O&M and sales of renewable energy and certain other renewable energy products, that are managed centrally at our corporate headquarters. It also includes all amortization of intangible assets and all corporate operating expenses — salaries and benefits, project development costs, and general, administrative and other — not specifically allocated to the segments. We do not allocate any indirect expenses to the segments.

Results of Operations

Three Months Ended March 31, 2013 and 2012

The following table sets forth certain financial data from the condensed consolidated statements of (loss) income, that data expressed as a percentage of revenue and percentage changes in that data for the three months ended March 31, 2013 and 2012:

(in $’000s) Revenue: Three Months Ended March 31, 2013 (a) % of Revenue 2012 (Restated) (b) % of Revenue % change ((a-b)/b)
Energy efficiency revenue $69,820 63.4% $113,382 77.4% (38.4)%
Renewable energy revenue 40,315 36.6% 33,191 22.6% 21.5%
110,135 100.0% 146,573 100.0% (24.9)%
Direct expenses:
Energy efficiency expenses 55,455 89,619 (38.1)%
Renewable energy expenses 33,161 27,730 19.6%
88,616 80.5% 117,349 80.1% (24.5)%
Gross profit 21,519 19.5% 29,224 19.9% (26.4)%
Total operating expenses 23,601 21.4% 25,799 17.6% (8.5)%
Operating (loss) income (2,082) (1.9)% 3,425 2.3% (160.8)%
Other expenses, net 464 0.4% 1,108 0.8% (58.1)%
(Loss) income before (benefit) provision for income taxes (2,546) (2.3)% 2,317 1.6% (209.9)%
Income tax (benefit) provision (622) (0.6)% 582 0.4% (206.9)%
Net (loss) income $(1,924) (1.7)% $1,735 1.2% (210.9)%

35

Revenue

The following table sets forth a comparison of our revenue by mix for the three months ended March 31, 2013 and 2012:

(in $’000s) Revenue: Three Months Ended March 31, 2013 (a) 2012 (b) $ change (a-b) % change ((a-b)/b)
Energy efficiency revenue $69,820 $113,382 $(43,562) (38.4)%
Renewable energy revenue 40,315 33,191 7,124 21.5%
$110,135 $146,573 $(36,438) (24.9)%

Total revenue. We derive a majority of our revenue from energy efficiency products and services, which accounted for approximately 63.4% and 77.4% of total revenue for the first quarter of 2013 and 2012, respectively. Total revenue was down for the first quarter of 2013 compared to the first quarter of 2012 primarily due to the lagged effect of the unusually sustained lengthening of conversion times from awarded projects to signed contracts that we have been experiencing since 2012. We believe this has resulted from continued U.S. federal fiscal uncertainty, which not only has contributed to a lengthening of our sales cycle for U.S. federal projects, but also has adversely affected both municipal and commercial customers across most geographic regions. We have observed among our existing and prospective customer base increased scrutiny of decisions about spending and about incurring debt to finance projects. For example, we have observed increased use of outside consultants and advisors, as well as adoption of additional approval steps, by many of our customers, which has resulted in a lengthening of the sales cycle. We expect this trend to continue into 2013.

Energy efficiency revenue. Energy efficiency revenue decreased by $43.6 million, or 38.4%, in the first quarter of 2013 compared to the first quarter of 2012. Declines in our U.S. federal, central U.S. region, other U.S. regions and Canada segments of $8.8 million, $4.6 million, $15.4 million, and $4.6 million, respectively, during the first quarter reflect the lagged effect of delays in converting awarded projects to signed contracts.

Renewable energy revenue. Renewable energy revenue increased by 21.5%, or $7.1 million, in the first quarter of 2013 compared to the first quarter of 2012 primarily due to increases in the other U.S. regions and all other segments of $5.2 million and $1.8 million, respectively, attributable to renewable energy projects for customers, O&M and small-scale infrastructure, which more than offset a decline in revenue from integrated-PV.

Revenue from customers outside the United States, principally Canada, was $14.5 million in the first quarter of 2013, compared with $19.1 million in the first quarter of 2012.

Business Segment Revenue

The following table sets forth a comparison of our business segment revenue for the three months ended March 31, 2013 and 2012:

(in $’000s) Three Months Ended March 31, 2013 (a) 2012 (b) $ change (a-b) % change ((a-b)/b)
U.S. Federal $13,104 $21,735 $(8,631) (39.7)%
Central U.S. Region 10,910 15,448 (4,538) (29.4)%
Other U.S. Regions 36,100 50,566 (14,466) (28.6)%
Canada 13,660 17,635 (3,975) (22.5)%
All Other 36,361 41,189 (4,828) (11.7)%
Total $110,135 $146,573 $(36,438) (24.9)%
  • Total revenue for the U.S. federal segment decreased from the first quarter of 2012 to the first quarter of 2013 by $8.6 million, or 39.7%, to $13.1 million primarily due to the lagged effect of fewer projects entering the construction phase during 2012 and continuing in the first quarter of 2013 resulting from delays in converting awarded projects to signed contracts as discussed above.
  • Total revenue for the central U.S. region segment decreased from the first quarter of 2012 to the first quarter of 2013 by $4.5 million, or 29.4%, to $10.9 million primarily due to the timing of awarded conversion activity in 2012, which resulted in fewer newly signed contracts during the year to replace installation activity in the first quarter of 2013.
  • Total revenue for the other U.S. regions segment decreased from the first quarter of 2012 to the first quarter of 2013 by $14.5 million, or 28.6%, to $36.1 million, primarily due to most regions within the segment experiencing a lengthening of conversion times from awarded projects to signed contracts in the last half of 2012, partially offset by an increase from renewable projects under construction for customers.
  • Total revenue for the Canada segment decreased from the first quarter of 2012 to the first quarter of 2013 by $4.0 million, or 22.5%, to $13.7 million primarily due to the effects of fewer projects entering the construction phase and delays in converting both proposals to awarded projects and awarded projects to signed contracts arising from what we believe was continued government and municipal customer uncertainty related to the consequences of election outcomes.
  • Total revenue not allocated to segments and presented as all other decreased from the first quarter of 2012 to the first quarter of 2013 by $4.8 million, or 11.7%, to $36.4 million primarily due to a decrease in integrated-PV.

Direct Expenses and Gross Profit

The following table sets forth a comparison of our direct expenses and gross profit for the three months ended March 31, 2013 and 2012:

(in $’000s) Revenue: Three Months Ended March 31, 2013 (a) 2012 (b) $ change (a-b) % change ((a-b)/b)
Energy efficiency revenue $69,820 $113,382 $(43,562) (38.4)%
Renewable energy revenue 40,315 33,191 7,124 21.5%
110,135 146,573 (36,438) (24.9)%
Direct expenses:
Energy efficiency expenses 55,455 89,619 (34,164) (38.1)%
Renewable energy expenses 33,161 27,730 5,431 19.6%
88,616 117,349 (28,733) (24.5)%
Gross profit: $21,519 $29,224 $(7,705) (26.4)%
Energy efficiency gross margin 20.6% 21.0% (0.4)%
Renewable energy gross margin 17.7% 16.5% 1.2%
Gross profit % 19.5% 19.9% (0.4)%

Total direct expenses. The majority of our expenses are incurred in connection with energy efficiency projects for which expenses represented approximately 79.4% and 79.0% of corresponding revenue for the three months ended March 31, 2013 and 2012, respectively. Total direct expenses decreased by $28.7 million, or 24.5%, from the first quarter of 2012 to the first quarter of 2013, consistent with the decline in revenue.

Energy efficiency. Energy efficiency gross margin decreased from 21.0% in the first quarter of 2012 to 20.6% in the first quarter of 2013. The decrease was driven by a greater portion of lower margin projects within several regions, partially offset by margin improvement from project closeouts within our U.S. federal segment.

Renewable energy. Renewable energy gross margin increased from 16.5% in the first quarter of 2012 to 17.7% in the first quarter of 2013 primarily due to a project closeout.

Operating Expenses

The following table sets forth a comparison of our operating expenses as a percentage of revenue for the three months ended March 31, 2013 and 2012:

(in $’000s) Three Months Ended March 31, 2013 (a) % of Revenue 2012 (b) % of Revenue $ change (a-b) % change ((a-b)/b)
Revenue $110,135 $146,573
Operating expenses:
Salaries and benefits $11,013 10.0% $14,369 9.8% $(3,356) (23.4)%
Project development costs 4,281 3.9% 4,216 2.9% 65 1.5%
General, administrative and other 8,307 7.5% 7,214 4.9% 1,093 15.2%
$23,601 21.4% $25,799 17.6% $(2,198) (8.5)%

Salaries and benefits. Salaries and benefits decreased by $3.4 million, or 23.4%, from the first quarter of 2012 to the first quarter of 2013 primarily due to improved utilization rates and fine-tuning of the organization during 2012.

Project development costs. Project development costs increased slightly by $0.1 million, or 1.5%, from the first quarter of 2012 to the first quarter of 2013, reflecting our efforts to increase project development activity.

General, administrative and other. General, administrative and other expenses increased by $1.1 million, or 15.2%, from the first quarter of 2012 to the first quarter of 2013 primarily due to increased acquisition expenses, including amortization of intangible assets, as well as higher professional fees and development costs.

Other Expenses, Net

The following table shows the activity in other expenses, net for the three months ended March 31, 2013 and 2012:

(in $’000s) Three Months Ended March 31, 2013 2012
Unrealized gain from derivatives $(389) $(230)
Interest expense, net of interest income 769 1,205
Amortization of deferred financing costs 84 133
$464 $1,108

Other expenses, net, in the first quarter of 2013 decreased by $0.6 million from the first quarter of 2012 primarily due to a$0.4 million increase in interest capitalized in connection with the construction of project assets that we will own and operate.

(Loss) Income Before Taxes

The following table sets forth a comparison of our (loss) income before taxes for the three months ended March 31, 2013 and 2012:

(in $’000s) Three Months Ended March 31, 2013 (a) 2012 (b) $ change (a-b) % change ((a-b)/b)
U.S. Federal $660 $1,288 $(628) (48.8)%
Central U.S. Region (167) 790 (957) (121.1)%
Other U.S. Regions 3,895 8,531 (4,636) (54.3)%
Canada (730) 119 (849) (713.4)%
All Other (6,205) (8,411) 2,206 (26.2)%
Total $(2,547) $2,317 $(4,864) (209.9)%

38

(Loss) income before taxes decreased from the first quarter of 2012 to the first quarter of 2013 by $4.9 million, or 209.9%, due primarily to the decrease in revenue for the reasons described above.

Business Segment (Loss) Income Before Taxes

  • Income before taxes for the U.S. federal segment decreased from the first quarter of 2012 to the first quarter of 2013 by $0.6 million, or 48.8%, to $0.7 million. The decrease was primarily due to lower revenue as described above, partially offset by higher margin contribution from project closeouts.
  • (Loss) income before taxes for the central U.S. region segment decreased from the first quarter of 2012 to the first quarter of 2013 by $1.0 million, or 121.1%, to $(0.2) million. The decrease was due primarily to the decrease in revenue described above.
  • Income before taxes for the other U.S. regions segment decreased from the first quarter of 2012 to the first quarter of 2013 by $4.6 million, or 54.3%, to $3.9 million due primarily to the decrease in revenue described above.
  • (Loss) income before taxes for the Canada segment decreased from the first quarter of 2012 to the first quarter of 2013 by $0.8 million, or 713.4%, to $(0.7) million. The decrease was primarily due to the decline in revenue described above.
  • The loss before taxes not allocated to segments and presented as all other, decreased from the first quarter of 2012 to the first quarter of 2013 by $2.2 million, or 26.2%, to $(6.2) million. The decrease in revenue described above was more than offset by improved operating margin and a decline in unallocated corporate expenses.

Provision for Income Taxes

The (benefit) provision for income taxes was $(0.6) million in the first quarter of 2013, compared to $0.6 million for the first quarter of 2012. The estimated annual effective tax rate applied in the first quarter of 2013 was 24.5%, compared to 25.1% in 2012. The principal reasons for the difference between the statutory rate and the estimated annual effective rate were the effects of deductions permitted under Section 179D of the Internal Revenue Code, which relate to the installation of certain energy efficiency equipment in federal, state, provincial and local government-owned buildings, as well as tax credits to which we are entitled from plants we own.

Net (Loss) Income

Net (loss) income decreased in the first quarter of 2013 by $3.7 million, or 210.9% to a loss of $(1.9) million compared to $1.7 million in the first quarter of 2012 due to lower pre-tax income as explained above partly offset by a lower effective tax rate. Earnings per share in the first quarter of 2013 was $(0.04) per basic share, representing a decrease of $0.08, or 200.0%, and $(0.04) per diluted share, representing a decrease of $0.08, or 200.0%.

Liquidity and Capital Resources

Sources of liquidity. Since inception, we have funded operations primarily through cash flow from operations and various forms of debt. We believe that available cash and cash equivalents and availability under our revolving senior secured credit facility, combined with our access to credit markets, will be sufficient to fund our operations through 2013 and thereafter.

Three Months Ended March 31, 2013 and 2012

Cash flows from operating activities. Operating activities used $25.7 million of net cash during the three months ended March 31, 2013. During that period, we had a net loss of $1.9 million, which is net of non-cash compensation, depreciation, amortization, deferred income taxes and other non-cash items totaling $4.9 million. Federal ESPC financing (net of restricted cash draws), accounts receivable including retainage, inventory, project development costs, accounts payable, accrued expenses and other current liabilities, other liabilities and income taxes payable used $49.3 million. These were offset by net decreases in prepaid expenses and other current assets, total billings and costs in excess of estimated earnings, and other assets, which provided $20.6 million in cash.

Operating activities provided $33.2 million of net cash during the three months ended March 31, 2012. During that period, we had net income of $1.7 million, which is net of non-cash compensation, depreciation, amortization, deferred income taxes and other non-cash items totaling $3.9 million. Accounts receivable, accounts receivable retainage, total billings and costs in excess of estimated earnings, prepaid expenses and other current assets, and other liablilities and income taxes payable provided $53.2 million. These were offset by net decreases in Federal ESPC financing (net of restricted cash draws), inventory, project development costs, other assets, accounts payable and accrued expenses and other current liabilities used $25.7 million in cash. The first quarter of 2012 benefited from the receipt of remaining retainage, or holdback, related to the Savannah River project in the amount of $21.2 million. In addition, certain receivables of acquired companies that normally would have been collected during the fourth quarter of 2011 were received in the first quarter of 2012.

Cash flows from investing activities. Cash used for investing activities during the three months ended March 31, 2013 totaled $14.5 million. Development of our renewable energy plants used $12.9 million. In addition, we invested $1.1 million in purchases of other property and equipment, and $1.8 million was used for the acquisition of Ennovate. These were partially offset by $1.3 million relating to grant awards received on project assets.

Cash used for investing activities during the three months ended March 31, 2012 totaled $7.4 million. Development of our renewable energy plants, as well as our tire shredding facility to support our operation at Savannah River, used $10.0 million; in addition, $1.3 million related to purchases of other property and equipment. These were partially offset by $3.8 million relating to grant awards and rebates received in the first quarter of 2012.

Cash flows from investing activities primarily relate to capital expenditures to support our growth.

Cash flows from financing activities. Net cash used for financing activities during the three months ended March 31, 2013 totaled $3.6 million. Most of this was due to payments on long-term debt of $3.8 million, partially offset by proceeds from exercises of options of $0.9 million.

Net cash used by financing activities during the three months ended March 31, 2012 totaled $13.7 million. Most of this was due to the draw down of the $6.4 million term loan portion of our renewed senior secured credit facility (see Note 13 and the discussion below) and the settlement of the book overdraft of $7.3 million.

Senior Secured Credit Facility — Revolver and Term Loan

On June 30, 2011, we amended and restated the credit and security agreement with Bank of America, adding Webster Bank as an additional lender. The new credit facility extended and expanded our prior existing credit facility, and consists of a $60.0 million revolving credit facility and a $40.0 million term loan. At March 31, 2013, $30.0 million was outstanding under the term loan and there was no balance outstanding under the revolving credit facility. The revolving credit facility may be increased by up to an additional $25.0 million at our option, if the lenders agree. The term loan requires quarterly principal payments of $1.4 million, with the balance due at maturity. Ameresco, Inc. remains the sole borrower under the credit facility. The new credit facility is secured by a lien on all of our assets other than renewable energy projects that we own that were financed by others, and limits our ability to enter into other financing arrangements. Availability under the revolving credit facility is based on two times our EBITDA for the preceding four quarters, and we are required to maintain a minimum EBITDA of $40.0 million on a rolling four-quarter basis. EBITDA for purposes of the facility excludes the results of renewable energy projects that we own that were financed by others. In light of our results during the second half of 2012 and continuing into the first quarter of 2013, the minimum EBITDA covenant has been suspended for interim periods during 2013. The new credit facility matures on June 30, 2016, when all amounts will be due and payable in full.

Project Financing

Construction and Term Loans. We have entered into a number of construction and term loan agreements for the purpose of constructing and owning certain renewable energy plants. The physical assets and the operating agreements related to the renewable energy plants are owned by wholly owned, single member special purpose subsidiaries. These construction and term loans are structured as project financings made directly to a subsidiary, and upon acceptance of a project, the related construction loan converts into a term loan. While we are required under generally accepted accounting principles to reflect these loans as liabilities on our consolidated balance sheet, they are generally nonrecourse and not direct obligations of Ameresco, Inc. As of March 31, 2013, we had outstanding $87.6 million in aggregate principal amount under these loans, bearing interest at rates ranging from 6.1% to 8.7% and maturing at various dates from 2013 to 2028. One loan totaling $5.2 million, does require Ameresco, Inc. to provide assurance to the lender of the project performance. A second loan, entered into during 2012, totaling $37.8 million requires Ameresco, Inc. to provide assurance to the lender of construction completion with respect to those projects still in construction and of reimbursement upon any recapture of certain renewable energy government cash grants upon the occurrence of events that cause the recapture of such grants. As of December 31, 2012, we had outstanding $88.6 million in aggregate principal amount under these loans, bearing interest at rates ranging from 6.1% to 8.7% and maturing at various dates from 2013 to 2028.

Federal ESPC Receivable Financing. We have arrangements with certain lenders to provide advances to us during the construction or installation of projects for certain customers, typically federal governmental entities, in exchange for our assignment to the lenders of our rights to the long-term receivables arising from the ESPCs related to such projects. These financings totaled $90.8 million and $93.0 million in principal amounts at March 31, 2013 and December 31, 2012, respectively. Under the terms of these financing arrangements, we are required to complete the construction or installation of the project in accordance with the contract with our customer, and the debt remains on our consolidated balance sheet until the completed project is accepted by the customer.

Our revolving senior secured credit facility and construction and term loan agreements require us to comply with a variety of financial and operational covenants. As of March 31, 2013 we were in compliance with all of our financial and operational covenants. In addition, we do not consider it likely that we will fail to comply with these covenants during the term of these agreements.

Contractual Obligations

The following table summarizes our significant contractual obligations and commitments as of March 31, 2013:

(in $’000s) Senior Secured Credit Facility: Payments due by Period Total Less than One Year One to Three Years Three to Five Years More than Five Years
Revolver $— $— $— $— $—
Term Loan 30,000 5,714 24,286 — —
Project Financing:
Construction and term loans 87,565 5,029 8,859 8,614 65,063
Federal ESPC receivable financing (1) 90,849 — 90,849 — —
Interest obligations (2) 20,622 3,876 6,403 4,670 5,673
Operating leases 7,771 2,562 3,508 1,368 333
Total $236,807 $17,181 $133,905 $14,652 $71,069

(1 ) Federal ESPC receivable financing arrangements relate to the installation and construction of projects for certain customers, typically federal governmental entities, where we assign to the lenders our right to customer receivables. We are relieved of the financing liability when the project is completed and accepted by the customer. We typically expect to be relieved of the financing liability between one and three years from the date of project construction commencement. The table does not include, for our federal ESPC receivable financing arrangements, the difference between the aggregate amount of the long-term customer receivables sold by us to the lender and the amount received by us from the lender for such sale.

(2 ) For both the revolver and term loan portion of our senior secured credit facility, the table above assumes that the variable interest rate in effect at March 31, 2013 remains constant for the term of the facility.

Off-Balance Sheet Arrangements

We did not have during the periods presented, and we do not currently have, any off-balance sheet arrangements, as defined under SEC rules, such as relationships with unconsolidated entities or financial partnerships, which are often referred to as structured finance or special purpose entities, established for the purpose of facilitating financing transactions that are not required to be reflected on our balance sheet.

Recent Accounting Pronouncements

There have been no new accounting pronouncements during the three months ended March 31, 2013, as compared to the recent accounting pronouncements described in our Annual Report on Form 10-K for the fiscal year ended December 31, 2012, that are of significance, or potential significance, to us.

Market risk

As filed, 5,066 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

We are exposed to changes in interest rates and foreign currency exchange rates because we finance certain operations through fixed and variable rate debt instruments and denominate our transactions in U.S. and Canadian dollars. Changes in these rates may have an impact on future cash flows and earnings. We manage these risks through normal operating and financing activities and, when deemed appropriate, through the use of derivative financial instruments.

Interest Rate Risk

We had cash and cash equivalents totaling $21.0 million as of March 31, 2013 and $63.3 million as of December 31, 2012. Our exposure to interest rate risk primarily relates to the interest expense paid on our senior secured credit facility.

Derivative Instruments

We do not enter into financial instruments for trading or speculative purposes. However, through our subsidiaries we do enter into derivative instruments for purposes other than trading purposes. Certain of the term loans that we use to finance our renewable energy projects bear variable interest rates that are indexed to short-term market rates. We have entered into interest rate swaps in connection with these term loans in order to seek to hedge our exposure to adverse changes in the applicable short-term market rate. In some instances, the conditions of our renewable energy project term loans require us to enter into interest rate swap agreements in order to mitigate our exposure to adverse movements in market interest rates. The interest rate swaps that we have entered into qualify, and, effective as of March 29, 2013, have been designated, as fair value hedges. See Note 2.

By using derivative instruments, we are subject to credit and market risk. The fair market value of the derivative instruments is determined by using valuation models whose inputs are derived using market observable inputs, including interest rate yield curves, and reflects the asset or liability position as of the end of each reporting period. When the fair value of a derivative contract is positive, the counterparty owes us, thus creating a receivable risk for us. We are exposed to counterparty credit risk in the event of non-performance by counterparties to our derivative agreements. We minimize counterparty credit (or repayment) risk by entering into transactions with major financial institutions of investment grade credit rating.

Our exposure to market interest rate risk is not hedged in a manner that completely eliminates the effects of changing market conditions on earnings or cash flow.

Foreign Currency Risk

As a result of our operations in Canada, we have significant expenses, assets and liabilities that are denominated in a foreign currency. Also, a significant number of employees are located in Canada and we transact a significant amount of business in Canadian currency. Consequently, we have determined that Canadian currency is the functional currency for our Canadian operations. When we consolidate the operations of our Canadian subsidiary into our financial results, because we report our results in U.S. dollars, we are required to translate the financial results and position of our Canadian subsidiary from Canadian currency into U.S. dollars. We translate the revenues, expenses, gains, and losses from our Canadian subsidiary into U.S. dollars using a weighted average exchange rate for the applicable fiscal period. We translate the assets and liabilities of our Canadian subsidiary into U.S. dollars at the exchange rate in effect at the applicable balance sheet date. Translation adjustments are not included in determining net income for the period but are disclosed and accumulated in a separate component of consolidated equity until sale or until a complete or substantially complete liquidation of the net investment in our Canadian subsidiary takes place. Changes in the values of these items from one period to the next which result from exchange rate fluctuations are recorded in our consolidated statements of changes in stockholders’ equity as accumulated other comprehensive income (loss). For the three months ended March 31, 2013, due to changes in the U.S.-Canadian exchange rate that were unfavorable to the value of the Canadian dollar versus the U.S. dollar, our foreign currency translation resulted in a loss of $1.0 million which we recorded as a decrease in accumulated other comprehensive income. For the year ended December 31, 2012, due to changes in the U.S.-Canadian exchange rate that were favorable to the value of the Canadian dollar versus the U.S. dollar, our foreign currency translation resulted in a gain of $0.7 million, which we recorded as an increase in accumulated other comprehensive income.

As a consequence, gross profit, operating results, profitability and cash flows are impacted by relative changes in the value of the Canadian dollar. We have not repatriated earnings from our Canadian subsidiary, but have elected to invest in new business opportunities there. We do not hedge our exposure to foreign currency exchange risk.

Controls and procedures

As filed, 6,344 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Evaluation of Disclosure Controls and Procedures

Our management, with the participation of our principal executive officer and principal financial officer, evaluated the effectiveness of our disclosure controls and procedures as of March 31, 2013. The term “disclosure controls and procedures,” as defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act, means controls and other procedures of a company that are designed to ensure that information required to be disclosed by a company in the reports that it files or submits under the Exchange Act is recorded, processed, summarized and reported, within the time periods specified in the SEC’s rules and forms. Disclosure controls and procedures include, without limitation, controls and procedures designed to ensure that information required to be disclosed by a company in the reports that it files or submits under the Exchange Act is accumulated and communicated to the company’s management, including its principal executive and principal financial officer, as appropriate to allow timely decisions regarding required disclosure. Our management recognizes that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving their objectives and management necessarily applies its judgment in evaluating the cost-benefit relationship of possible controls and procedures. Our management, after evaluating the effectiveness of our disclosure controls and procedures as of the end of the period covered by this report, or the evaluation date, have concluded that as of the evaluation date, our disclosure controls and procedures were not effective due to material weaknesses in our internal control over financial reporting disclosed in our Annual Report on Form 10-K for the year ended December 31, 2012, filed with the SEC on March 18, 2013, and discussed below.

Changes in Internal Control over Financial Reporting

There were no changes in our internal control over financial reporting, other than those stated below, during our most recent fiscal quarter that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.

Material Weakness Discussion and Remediation

As previously disclosed in our Annual Report on Form 10-K for the year ended December 31, 2012, filed with the SEC on March 18, 2013, we identified two material weaknesses in our internal control over financial reporting:

  • insufficient personnel in place for an adequate amount of time and ineffectively operating internal control procedures to ensure timely and accurate reviews necessary to provide reasonable assurance that financial statements and related disclosures could be prepared in accordance with generally accepted accounting principles; and
  • inadequate and ineffective controls for reviewing and analyzing the quarterly and annual tax provision calculations, which creates the potential for misstatement of our income tax expense, income tax receivable and income tax payable accounts.

In connection with our fiscal 2012 audit, we concluded that we had not fully remediated the first weakness, which had been previously identified, and that we also had a material weakness regarding accounting for and disclosure of income taxes as described above.

We implemented the following changes in our internal control over financial reporting during 2012 that contributed to partially remediating the previously disclosed and continuing material weakness described above:

  • we hired directors of business services and project accounting and of financial reporting and compliance, both of whom began employment in the third quarter of 2012;
  • we have restructured our accounting organization to improve the efficiency and adequacy of review processes, which we began implementing in the third quarter of 2012;
  • we hired additional accounting and business services personnel, all of whom began employment during the fourth quarter of 2012; and
  • we provided further education and training on accounting systems, processes, policies and procedures to accounting and business services personnel.

During 2013, we expect to undertake the following additional actions to remediate the material weaknesses identified:

  • provide education and training on accounting processes, policies, procedures and systems to business unit personnel;
  • hire additional accounting and tax personnel;
  • continue to improve reconciliation and monitoring controls over significant balance sheet accounts;
  • continue to improve policies and procedures, including education and training, over accounting systems, processes, policies and procedures;
  • continue to automate our processes and enhance financial reporting systems;
  • reevaluate the design of income tax accounting processes and controls and implement new and improved processes and controls, if warranted; and
  • increase the frequency of review and discussion of significant tax matters and supporting documentation with senior finance management.

The Audit Committee has directed management to develop a detailed plan and timetable for the implementation of the foregoing remedial measures and will monitor their implementation. In addition, under the direction of the Audit Committee, management will continue to review and make necessary changes to the overall design of our internal control environment, as well as policies and procedures to improve the overall effectiveness of internal control over financial reporting.

Management is committed to continuous improvement of our internal control processes and will continue to diligently review our reporting controls and procedures. As management continues to evaluate and work to improve internal control over financial reporting, we may determine to take additional measures to address control deficiencies or determine to modify, or in appropriate circumstances not to complete, certain of the remediation measures described above. We expect that our remediation efforts will continue throughout fiscal year 2013.

For the near-term future, the matters identified above will continue to constitute material weaknesses in our internal control over financial reporting that could result in material misstatements in our financial statements not being prevented or detected.

Risk factors

As filed, 170 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

As of March 31, 2013, there have been no material changes to the risk factors described in Item 1A to our Annual Report on Form 10-K for the year ended December 31, 2012.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2013-03-31. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Revenue3 months2013-01-01 to 2013-03-31$110.1mus-gaap:SalesRevenueNet
Cost of revenue3 months2013-01-01 to 2013-03-31$88.6mus-gaap:CostOfGoodsAndServicesSold
Gross profit3 months2013-01-01 to 2013-03-31$21.5mus-gaap:GrossProfit
Operating income3 months2013-01-01 to 2013-03-31−$2.1mus-gaap:OperatingIncomeLoss
Interest expense3 months2013-01-01 to 2013-03-31$925.8kus-gaap:InterestExpense
Income tax3 months2013-01-01 to 2013-03-31−$622.7kus-gaap:IncomeTaxExpenseBenefit
Net income3 months2013-01-01 to 2013-03-31−$1.9mus-gaap:NetIncomeLoss
Diluted EPS3 months2013-01-01 to 2013-03-31−$0.04us-gaap:EarningsPerShareDiluted
Basic EPS3 months2013-01-01 to 2013-03-31−$0.04us-gaap:EarningsPerShareBasic
Diluted shares (weighted)3 months2013-01-01 to 2013-03-3146,220,748 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Operating cash flow3 months2013-01-01 to 2013-03-31−$25.7mus-gaap:NetCashProvidedByUsedInOperatingActivities
Capital expenditure3 months2013-01-01 to 2013-03-31$1.1mus-gaap:PaymentsToAcquirePropertyPlantAndEquipment
Cash and equivalentsAt period end2013-03-31$21.0mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2013-03-31$244.4mus-gaap:AssetsCurrent
Total assetsAt period end2013-03-31$630.9mus-gaap:Assets
Current liabilitiesAt period end2013-03-31$109.9mus-gaap:LiabilitiesCurrent
Long-term debtAt period end2013-03-31$197.7mus-gaap:LongTermDebtNoncurrent
Current portion of debtAt period end2013-03-31$10.7mus-gaap:LongTermDebtCurrent
Shareholders' equityAt period end2013-03-31$261.5mus-gaap:StockholdersEquityIncludingPortionAttributableToNoncontrollingInterest