Introduction

NioCorp Developments Ltd. (“NioCorp,” “we,” “us,” “our,” or the “Company”) was incorporated under the laws of the Province of British Columbia under the Business Corporations Act (British Columbia) on February 27, 1987, under the name “IPC International Prospector Corp.” On May 22, 1991, we changed our name to “Kingston Resources Ltd.” On June 29, 2001, we changed our name to “Butler Developments Corp.” On February 12, 2009, we changed our name to “Butler Resource Corp.” On March 4, 2010, we changed our name to “Quantum Rare Earth Developments Corp.” On March 4, 2013, we changed our name to “NioCorp Developments Ltd.”

NioCorp is a United States Securities and Exchange Commission (“SEC”) reporting company, and we are also a Canadian reporting issuer in British Columbia, Alberta, Saskatchewan, Ontario, and New Brunswick. Our registered and records office is located at 1133 Melville Street, Suite 3500, Vancouver, British Columbia V6E 4E5 (ATTN: Blake, Cassels & Graydon LLP). Our principal executive office is located at 7000 South Yosemite Street, Suite 115, Centennial, Colorado 80112.

Business Operations

NioCorp, through ECRC (as defined below), is developing a critical minerals project that, if and when developed, will produce niobium, scandium, titanium, and potentially, rare earth products. Known as the “Elk Creek Project,” it is located near Elk Creek, Nebraska, in the southeast portion of the state.

  • Niobium is used to produce various superalloys that are extensively used in high performance aircraft and jet turbines. It also is used in high-strength, low-alloy steel, a stronger steel used in automobiles, bridges, structural systems, buildings, pipelines, and other applications that generally enables those applications to be stronger and lighter in mass. This “lightweighting” benefit often results in environmental benefits, including reduced fuel consumption and material usage, which can result in fewer air emissions.
  • Scandium can be combined with aluminum to make super-high-performance alloys with increased strength and improved corrosion resistance. Scandium also is a critical component of advanced solid oxide fuel cells, an environmentally preferred technology for high-reliability, distributed electricity generation.
  • Titanium is a component of various superalloys and other applications that are used for aerospace applications, weapons systems, protective armor, medical implants and many others. It also is used in pigments for paper, paint, and plastics.
  • Rare earth elements are critical minerals that are needed in virtually all U.S. defense systems and across the electronics, manufacturing, high-technology, transportation, and energy sectors. Magnetic rare earths, such as neodymium, praseodymium, terbium, and dysprosium are critical to the making of neodymium-iron-boron magnets, which are used across a wide variety of defense and civilian applications.

Our primary business strategy is to advance our Elk Creek Project to commercial production. Based on the success of our recent fund-raising activities, as discussed below under Part II, Item 7, “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Liquidity and Capital Resources,” we are focused on carrying out our near-term planned work programs associated with securing the project financing necessary to complete detailed design, development, and construction of the Elk Creek Project, as well as the commencement of early elements of project construction.

Corporate Structure

The Company’s business operations are conducted primarily through ECRC. The table below provides an overview of the Company’s current subsidiaries and their activities:

Name State/Province of Formation Ownership Business
0896800 B.C. Ltd. (“0896800”) British Columbia 100% The only business of 0896800 is to hold the shares of Class A common stock of ECRC
Elk Creek Resources Corp. (“ECRC”) Delaware 80.42%(1) The business of ECRC is the development of the Elk Creek Project
NioCorp Technologies Limited United Kingdom 100% The business of NioCorp Technologies Limited is the research and development of aluminum-scandium alloys and other business opportunities

(1) Represents 100% of Class A common stock owned by 0896800, and 3,934,031 Vested Shares and 3,391,596 Earnout Shares (each as defined below) held by third parties, and outstanding as of June 30, 2025.

Historical Development of the Business

The acquisition of the carbonatite property located in Southeast Nebraska, USA (the “Elk Creek Property”) was closed in December 2010 and involved the purchase by NioCorp of all of the issued and outstanding common shares of a private British Columbia company, which in turn held 100% of the issued and outstanding shares of Elk Creek Resources Corp., a Nebraska corporation.

Between 2011 and 2020, the Company advanced the Elk Creek Project through the completion of field exploration programs, feasibility study development and reporting, updates to underground mine designs and supporting infrastructure, and the receipt of required permits from the State of Nebraska.

During fiscal year 2021, we obtained funding which allowed us to purchase land and mineral rights at the Elk Creek Property and continue early project execution activities. During fiscal year 2022, we focused efforts towards refining our Elk Creek Project mineral resource and mineral reserve estimates with respect to REEs. This work included additional assays of historical drill core to fill data gaps in the existing resource database and re-modeling. Based on this re-interpretation of the geologic data, an update to the mine plan was also completed. Based on this work, we issued the 2022 NI 43-101 Elk Creek Technical Report on June 28, 2022, and filed the S-K 1300 Elk Creek Technical Report Summary as an exhibit to our Annual Report on Form 10-K for the year ended June 30, 2022.

On March 17, 2023 (the “Closing Date”), the Company closed a series of transactions (the “GXII Transaction”), pursuant to the Business Combination Agreement, dated September 25, 2022 (the “Business Combination Agreement”), among the Company, GX Acquisition Corp. II (“GXII”), and Big Red Merger Sub Ltd (the “Closing”). At the Closing, the Company also closed convertible debt financings (the “Yorkville Convertible Debt Financing”) with YA II PN, Ltd., an investment fund managed by Yorkville Advisors Global, LP (together with YA II PN, Ltd., “Yorkville”), and the standby equity purchase facility with Yorkville (the “Yorkville Equity Facility Financing” and, together with the Yorkville Convertible Debt Financing, the “Yorkville Financings”) became effective. The transactions contemplated by or related to the Business Combination Agreement, including the GXII Transaction, the Yorkville Financings, and a 10-for-1 reverse stock split consummated in connection with the Closing, are referred to, collectively, as the “2023 Transactions.”

As a result of the 2023 Transactions, among other matters, GXII became and indirect, majority-owned subsidiary of NioCorp and changed its name to “Elk Creek Resources Corp.”, which we refer to as “ECRC,” and the Common Shares and the Warrants that were assumed by NioCorp from GXII (the “NioCorp Assumed Warrants”) were listed for trading on Nasdaq under the symbols “NB” and “NIOBW,” respectively.

Pursuant to the Business Combination Agreement, the Sponsor Support Agreement, dated September 25, 2022, among GX Sponsor II LLC (the “Sponsor”), GXII, the Company and the other persons party thereto, and the Exchange Agreement, dated as of March 17, 2023, by and among NioCorp, ECRC and the Sponsor (the “Exchange Agreement”), after the Closing, the shares of Class B common stock of ECRC are exchangeable into Common Shares on a one-for-one basis, subject to certain equitable adjustments, under certain conditions. Of the issued and outstanding shares of Class B common stock of ECRC, 4,565,808 shares (the “Vested Shares”) were vested as of the Closing Date and are exchangeable at any time, and from time to time, until the tenth anniversary of the Closing Date and 3,391,596 shares (the “Earnout Shares”) are exchangeable until the tenth anniversary of the Closing Date, subject to certain vesting conditions. See Note 9 to the consolidated financial statements included in Part II, Item 8 hereof for additional information regarding the Class B common stock of ECRC.

During fiscal year 2025, the Company initiated a drilling program at the Elk Creek Project to support the conversion of a portion of its current indicated resources into measured resources and the subsequent conversion of a portion of its current probable mineral reserves into proven mineral reserves. This drilling program is ongoing as of the date of this report. When completed, the results of the drilling program, along with other technical and economic analyses undertaken by the Company, will be used to update the feasibility study for the Elk Creek Project.

Recent Corporate Events

EXIM Bank Financing Process

As previously disclosed, on March 6, 2023, the Company announced the receipt of a Letter of Interest from the Export-Import Bank of the United States (“EXIM”) for potential debt financing through EXIM’s “Make More In America” initiative to fund a portion of the project costs of the Elk Creek Project (the “EXIM Financing”).

NioCorp submitted a formal application to EXIM for a loan under EXIM’s “Make More in America” initiative on June 6, 2023. The Company was informed that its application received approval by the first of three reviews by the EXIM Transaction Review Committee on October 2, 2023. EXIM deployed additional resources to the processing of the Company’s application during the quarter ended December 31, 2023, and has retained financial and legal consultants to support EXIM’s due diligence on the Elk Creek Project. On April 15, 2024, the Company received a Preliminary Project Letter (the “PPL”) from EXIM. The PPL is a summary of EXIM’s initial due diligence findings and also includes a preliminary Indicative Term Sheet. The PPL identified additional project activities to be undertaken by the Company in conjunction with the EXIM evaluation process. These include an updated mine plan and updated Elk Creek Project capital costs on a final or close-to-final basis reflecting updated process flows.

Management is working with EXIM to continue to advance the project through the next stages of EXIM’s due diligence and loan application process. We are currently unable to estimate how long the application process, including the additional project activities identified in the PPL, may take, and there can be no assurances that we will be able to successfully negotiate a final commitment of debt financing from EXIM.

April 2025 Offering

On April 21, 2025, the Company closed an underwritten, registered public offering (the “April 2025 Offering”), pursuant to the underwriting agreement, dated April 17, 2025, with Maxim Group LLC (“Maxim”), as underwriter, pursuant to which the Company issued and sold (i) 6,628,846 Common Shares at a public offering price of $2.60 per Common Share and (ii) 1,063,462 pre-funded Warrants (the “April 2025 Pre-Funded Warrants”) to purchase up to an additional 1,063,462 Common Shares at a public offering price of $2.5999. The April 2025 Pre-Funded Warrants have an exercise price of $0.0001 per underlying Common Share, are exercisable immediately, and do not have an expiration date. On April 17, 2025, Maxim partially exercised its over-allotment option to purchase 323,504 additional Common Shares at the closing. The net proceeds from the April 2025 Offering were approximately $18.7 million, after deducting underwriting discounts and offering expenses.

July 2025 Offering

On July 18, 2025, the Company closed a registered public offering (the “July 2025 Offering”), pursuant to a placement agency agreement, dated July 17, 2025 (the “Placement Agency Agreement”) with Maxim, as sole placement agent, pursuant to which the Company issued and sold 13,850,000 Common Shares at a public offering price of $3.25 per Common Share. The net proceeds from the July 2025 Offering were approximately $41.2 million, after deducting underwriting discounts and offering expenses.

DoD Agreement

On August 4, 2025, ECRC entered into a Project Sub-Agreement (the “DoD Agreement”) with Advanced Technology International (“ATI”), an entity acting on behalf of the Defense Industrial Base Consortium under the authority of the U.S. Department of Defense (“DoD”). Subject to the terms and conditions of the DoD Agreement,

ECRC is entitled to receive up to an aggregate of approximately $10.0 million of reimbursement payments from the DoD upon the achievement of certain project milestones related to feasibility study-level engineering and additional reserve drilling, as well as preparing updated cost estimates, for the Elk Creek Project.

Competitive Business Conditions

There is significant competition within the minerals industry to discover, acquire and obtain project financing for mineral properties considered to have commercial potential. We compete with others in efforts to obtain project financing and resources to advance the Elk Creek Project to construction and commercial operation, acquire and utilize mining and processing equipment, and hire qualified personnel. These other companies may be better capitalized than us and we may have difficulty in obtaining the financing and resources necessary to advance the Elk Creek Project to construction and commercial operation. In addition, in competing for qualified personnel, we may be required to pay compensation or benefits relatively higher than those paid in the past, and the availability of qualified personnel may be limited in high-demand periods.

Cycles

The mining business is subject to mineral price cycles. The marketability of minerals and mineral concentrates is also affected by worldwide economic cycles. Demand has in the past, and may in the future, be subject to those same worldwide economic cycles. Fluctuations in supply and demand in various regions throughout the world are common. In addition, the niobium, scandium, titanium, and potentially, rare earth products, that we intend to produce at the Elk Creek Project are subject to additional commodity-specific price cycles resulting from, among other factors, demand for specific products, export controls, taxes and other tariffs and fees.

The following table sets forth commodity prices for the last five calendar years for the ferroniobium, scandium trioxide, and titanium dioxide products the Company anticipates extracting from its Elk Creek Project. These pricing surveys may not be representative of the pricing that the Company anticipates achieving for its products if commercial production begins from its Elk Creek Project.

Year Ferroniobium U.S. Price ($/kg-Nb)(1) Sc2O3 U.S. Price ($/kg)(2) TiO2 U.S. Price ($/kg)(3)
2024 $46 $1,200 $1.31
2023 51 -(4) 1.46
2022 46 2,100 1.47
2021 44 2,200 1.30
2020 37 3,800 1.17

(1) Source: Argus Metal Prices, average annual ending price, 2024. Ferroniobium 65% niobium content, FOB U.S. warehouse.

(2) Source: United States Geological Service (“USGS”) Mineral Commodity Summary, 2024. Sc2O3, 99.99% purity, 5-kilogram (“kg”) lot size.

(3) Source: USGS Mineral Commodity Summary, 2024. Rutile mineral concentrate, bulk, minimum 95% TiO2, f.o.b. Australia.

(4) Pricing information was not provided by the USGS for 2023.

As NioCorp is a development stage issuer and has not yet generated any revenue from the operation of the Elk Creek Project, it is not currently significantly affected by changes in commodity demand and prices, except to the extent that these changes may impact the development of the Elk Creek Project. As it does not carry on production activities, NioCorp’s ability to fund ongoing exploration is affected by the availability of financing, which is, in turn, affected by the strength of the economy and other general economic factors.

Economic Dependence

Other than land and mineral right option agreements and agreements between NioCorp and third parties for the purchase and sale of products to be produced from the Elk Creek Project (“offtake agreements”), NioCorp’s business is not substantially dependent on any contract such as a contract to sell the major part of its product or services or to purchase the major part of its requirements for goods, services or its raw materials, or any franchise or license or other agreement to use a patent, formula, trade secret, process or trade name upon which its business depends.

Government Regulation

The exploration and development of a mining prospect is subject to regulation by a number of federal and state government authorities. These include the United States Environmental Protection Agency (the “EPA”) and the United States Army Corps of Engineers (the “USACE”) as well as the various state and local environmental protection agencies. The regulations address many environmental issues relating to air, soil, and water contamination, and apply to many mining related activities including exploration, mine construction, mineral extraction, ore milling, water use, waste disposal, and use of toxic substances. In addition, we are subject to regulations relating to labor standards, occupational health and safety, mine safety, general land use, export of minerals, taxation, data protection, and data security. Many of the regulations require permits or licenses to be obtained, the absence of which and/or inability to obtain such permits or licenses will adversely affect our ability to conduct our exploration, development, and operation activities. The failure to comply with the regulations and terms of permits and licenses may result in fines or other penalties or in revocation of a permit or license or loss of a prospect.

General

While none of the lands on which the Elk Creek Project is proposed to be built are owned by the U.S. Government, mining rights on public lands are governed by the General Mining Law of 1872, as amended, which allows for the location of mining claims on certain federal lands upon the discovery of a valuable mineral deposit and compliance with location requirements. The exploration of mining properties and development and operation of mines is governed by both federal and state laws. Federal laws that govern mining claim location and maintenance and mining operations on federal lands are generally administered by the Bureau of Land Management. Additional federal laws, governing mine safety and health, also apply. State laws also require various permits and approvals before exploration, development or production operations can begin. Among other things, a reclamation plan must typically be prepared and approved, with financial assurance provided in the amount of projected reclamation costs. The financial assurance is used to ensure that proper reclamation takes place and will not be released until that time. Local jurisdictions may also impose permitting requirements, such as conditional use permits or zoning approvals.

Environmental Regulation

Our mineral projects are subject to various federal, state, and local laws and regulations governing protection of the environment. These laws are continually changing and, in general, are becoming more restrictive. The development, operation, closure, and reclamation of mining projects in the U.S. requires numerous notifications, permits, authorizations, and public agency decisions. Compliance with environmental and related laws and regulations requires us to obtain permits issued by regulatory agencies and to file various reports and keep records of our operations. Certain of these permits require periodic renewal or review of their conditions and may be subject to a public review process during which opposition to our proposed operations may be encountered. We are currently operating under various permits for activities connected to mineral exploration, reclamation, and environmental considerations. Our policy is to conduct business in a way that safeguards public health and the environment. We believe that our operations are conducted in material compliance with applicable laws and regulations.

Changes to current local, state, or federal laws and regulations in the jurisdictions where we operate could require additional capital expenditures and increased operating and/or reclamation costs. Although we are unable to predict what additional legislation, if any, might be proposed or enacted, additional regulatory requirements could impact the economics of our projects.

Environmental Regulation - U.S. Federal Laws

The Comprehensive Environmental, Response, Compensation, and Liability Act (“CERCLA”), and comparable state statutes, impose strict, joint, and several liability on current and former owners and operators of sites and on persons who disposed of or arranged for the disposal of hazardous substances found at such sites. It is not uncommon for the government to file claims requiring clean-up actions and/or demands for reimbursement for government-incurred clean-up costs or natural resource damages. It is also not uncommon for neighboring landowners and other third parties to file claims for personal injury and property damage allegedly caused by hazardous substances released into the environment. The Resource Conservation and Recovery Act (“RCRA”), and comparable state statutes, govern the disposal of solid waste and hazardous waste and authorize the imposition of substantial fines and penalties for noncompliance, as well as requirements for corrective actions. CERCLA, RCRA, and comparable state statutes can impose liability for clean-up of sites and disposal of substances found on exploration, mining and processing sites long after activities on such sites have been completed.

The Clean Air Act, as amended (“CAA”), restricts the emission of air pollutants from many sources, including mining and processing activities. Any future mining operations by the Company may produce air emissions, including fugitive dust and other air pollutants from stationary equipment, storage facilities, and the use of mobile sources such as trucks and heavy construction equipment, which are subject to review, monitoring and/or control requirements under the CAA and state air quality laws. New facilities may be required to obtain permits before work can begin, and existing facilities may be required to incur capital costs in order to remain in compliance. In addition, permitting rules may impose limitations on our production levels or result in additional capital expenditures in order to comply with the rules.

The National Environmental Policy Act (“NEPA”) requires federal agencies to integrate environmental considerations into their decision-making processes by evaluating the environmental impacts of their proposed actions, including issuance of permits to mining facilities and assessing alternatives to those actions. If a proposed action could significantly affect the environment, the agency must prepare either a detailed statement known as an Environmental Impact Statement (“EIS”), or a less detailed statement known as an Environmental Assessment (“EA”). The EPA, other federal agencies, and any interested third parties can review and comment on the scope of the EIS or EA and the adequacy of any findings set forth in the draft and final EIS or EA. This process can cause delays in issuance of required permits or result in changes to a project to mitigate its potential environmental impacts, which can in turn impact the economic feasibility of a proposed project.

The Clean Water Act (“CWA”), and comparable state statutes, impose restrictions and controls on the discharge of pollutants into waters of the U.S. The discharge of pollutants into regulated waters is prohibited, except in accordance with the terms of a permit issued by the EPA or an analogous state agency. The CWA regulates storm water from mining facilities and requires a storm water discharge permit or Stormwater Pollution Prevention Plan for certain activities. Such a permit requires the regulated facility to monitor and sample storm water run-off from its operations. The CWA and regulations implemented thereunder also prohibit discharges of dredged and fill material in wetlands and other waters of the U.S. unless authorized by an appropriately issued permit. The CWA and comparable state statutes provide for civil, criminal, and administrative penalties for unauthorized discharges of pollutants, and impose liability on parties responsible for those discharges for the costs of cleaning up any environmental damage caused by the release and for natural resource damages resulting from the release.

The Safe Drinking Water Act (“SDWA”) and the Underground Injection Control (“UIC”) program promulgated thereunder, regulate the drilling and operation of subsurface injection wells. The EPA directly administers the UIC program in some states and in others the responsibility for the program has been delegated to the state. The program requires that a permit be obtained before drilling a disposal or injection well. Violation of these regulations and/or contamination of groundwater by mining-related activities may result in fines, penalties, and remediation costs, among other sanctions and liabilities under the SDWA and state laws. In addition, third-party claims may be filed by landowners and other parties claiming damages for alternative water supplies, property damages, and bodily injury.

Environmental Regulation − Nebraska

Nebraska has a well-developed set of environmental regulations and responsible agencies but does not have clearly defined regulations with respect to permitting mines. As such, review of the project and the issuance of permits by Nebraska agencies and regulatory bodies could potentially impact the total time to market for our Elk Creek Project. Other Nebraska regulations govern operating and design standards for the construction and operation of any source of air emissions and landfill operations. Any changes to these laws and regulations could have an adverse impact on our financial performance and results of operations by, for example, requiring changes to operating conditions, technical criteria, fees, or surety requirements. The most stringent permit related to air quality is known as a Prevention of Significant Deterioration (“PSD”) permit, which requires the applicant to demonstrate compliance with NAAQS and Best Available Control Technology (“BACT”) for the control of air emissions. If the facility exceeds the potential to emit thresholds for such a permit and is thus subject to PSD requirements, permanent construction at the project site may not begin until the responsible agency issues the PSD permit. For facilities in Nebraska with potential emissions below PSD thresholds, a state air construction permit is needed. The state permit also requires a demonstration of compliance with NAAQS but does not require a BACT demonstration and further allows construction at a subject facility to proceed ahead of permit issuance through an established variance process.

Human Capital

The Company’s ability to continue to progress the Elk Creek Project will depend on its ability to attract and retain individuals with (among other skills) financial, administrative, engineering, geological and mining skills, and knowledge of our industry and targeted markets. Much of the necessary specialized skills and knowledge required by the Company as a mineral exploration company are available from the Company’s current management team and Board of Directors (the “Board”). The Company retains outside consultants if additional specialized skills and knowledge are required.

As of June 30, 2025, we had seven full-time employees as well as one contract employee. In addition, we use consultants with specific skills to assist with various aspects of our corporate affairs, project evaluation, due diligence, corporate governance, and property management.

Our compensation programs are designed to align compensation of our employees with the Company’s performance and to provide the proper incentives to attract, retain, and motivate employees to achieve superior results. The structure of our compensation programs balances competitive wages and benefits and incentive earnings for both short-term and long-term performance.

Our priority to maintain a culture of ethical performance as a core value is reflected in the Company’s Code of Business Conduct and Ethics (the “Code of Conduct”) and other related policies. Oversight is provided by the Company’s Board and, for specific areas of performance, by committees of the Board. Employees are required to review the Code of Conduct on a periodic basis. Our compensation programs also include consideration of ethical performance in determining incentive awards.

The Company also provides a robust suite of benefits to our employees, including 401(k) participation, medical-insurance options, and programs to encourage and support the whole person.

Forward-Looking Statements

This Annual Report on Form 10-K and the exhibits attached hereto contain “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), and “forward-looking information” within the meaning of applicable Canadian securities legislation (collectively, “forward-looking statements”).

Forward-looking statements have been based upon our current business and operating plans, as approved by the Board, and may include statements regarding, among other matters, the financial and business performance of NioCorp; NioCorp’s anticipated results and developments in the operations of NioCorp in future periods; NioCorp’s planned exploration activities; the adequacy of NioCorp’s financial resources; NioCorp’s ability to secure sufficient project financing to complete construction and commence operation of the Elk Creek Project; NioCorp’s ability to receive a final commitment of financing from EXIM; the estimated total upfront capital expenditure for the Elk Creek Project; NioCorp’s expectation and ability to produce niobium, scandium, and titanium and the potential to produce rare earth elements at the Elk Creek Project; NioCorp’s plans to produce and supply specific products and market demand for those products; NioCorp’s ability to access the full amount of the expected net proceeds of the Yorkville Equity Facility Financing Agreement; NioCorp’s expectation that it will receive the full $10 million in reimbursement under the DoD Agreement; the intended use of our cash balance as of June 30, 2025 as well as the proceeds from the July 2025 Offering, the proceeds from Warrant exercise issuances, and the reimbursement payments pursuant to the DoD Agreement; the expected results of the drilling program at the Elk Creek Project; the expectation that the results of the drilling program will be used to update the feasibility study for the Elk Creek Project; the Elk Creek Project’s ability to produce multiple critical metals; the Elk Creek Project’s projected ore production and mining operations over its expected mine life; the completion of technical and economic analyses on the potential addition of magnetic rare earth oxides to NioCorp’s planned product suite; statements with respect to the estimation of mineral resources and mineral reserves; the exercise of options to purchase additional land parcels; the execution of contracts with engineering, procurement and construction companies; NioCorp’s ongoing evaluation of the impact of inflation, supply chain issues, tariffs, and geopolitical unrest on the Elk Creek Project’s economic model; and the creation of full time and contract construction jobs over the construction period of the Elk Creek Project.

Forward-looking statements are frequently, but not always, identified by words such as “expects,” “anticipates,” “believes,” “intends,” “estimates,” “potential,” “possible,” and similar expressions, or statements that events, conditions, or results “will,” “may,” “could,” or “should” (or the negative and grammatical variations of any of these terms) occur or be achieved. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, or future events or performance (often, but not always, using words or phrases such as “expects” or “does not expect,” “is expected,” “anticipates” or “does not anticipate,” “plans,” “estimates,” or “intends,” or stating that certain actions, events, or results “may,” “could,” “would,” “might,” or “will” be taken, occur or be achieved) are not statements of historical fact and may be forward-looking statements. Forward-looking statements reflect material expectations and assumptions, including, without limitation, expectations and assumptions relating to: NioCorp’s ability to receive sufficient project financing for the construction of the Elk Creek Project on acceptable terms, or at all; the future price of metals; the stability of the financial and capital markets; and current estimates and assumptions regarding the Yorkville Equity Facility Financing Agreement and its benefits. Such forward-looking statements reflect the Company’s current views with respect to future events and are subject to certain known and unknown risks, uncertainties, and assumptions. Many factors could cause actual results, performance, or achievements to be materially different from any future results, performance, or achievements that may be expressed or implied by such forward-looking statements, including, among others, risks related to the following: NioCorp’s ability to operate as a going concern; NioCorp’s requirement of significant additional capital; NioCorp’s ability to receive sufficient project financing for the construction of the Elk Creek Project on acceptable terms, or at all; NioCorp’s ability to achieve the required milestones and receive the full $10.0 million in reimbursement under the DoD Agreement; NioCorp’s ability to receive a final commitment of financing from EXIM or other debt financing or financial support on acceptable timelines, on acceptable terms, or at all; NioCorp’s ability to access the full amount of the expected net proceeds under the Yorkville Equity Facility Financing Agreement; NioCorp’s ability to continue to meet Nasdaq listing standards; risks relating to the Common Shares, including price volatility, lack of dividend payments and dilution or the perception of the likelihood of any of the foregoing; the extent to which NioCorp’s level of indebtedness and/or the terms contained in agreements governing NioCorp’s indebtedness, if any, the Yorkville Equity Facility Financing Agreement or other agreements may impair NioCorp’s ability to obtain additional financing, on acceptable terms, or at all; covenants contained in agreements with NioCorp’s secured creditors that may affect its assets; NioCorp’s limited operating history; NioCorp’s history of losses; the material weaknesses in NioCorp’s internal control over financial reporting, NioCorp’s efforts to remediate such material weaknesses and the timing of remediation; the possibility that NioCorp may qualify as a PFIC under the Code; the potential that the 2023 Transactions could result in NioCorp becoming subject to materially adverse U.S. federal income tax consequences as a result of the application of Section 7874 and related sections of the Code; cost increases for NioCorp’s exploration and, if warranted, development projects; a disruption in, or failure of, NioCorp’s information technology systems, including those related to cybersecurity; equipment and supply shortages; variations in the market demand for, and prices of, niobium, scandium, titanium and rare earth products; current and future offtake agreements, joint ventures, and partnerships, including our ability to negotiate extensions to existing agreements or to enter into new agreements, on favorable terms or at all; NioCorp’s ability to attract qualified management; estimates of mineral resources and reserves; mineral exploration and production activities; feasibility study results; the results of metallurgical testing; the results of technological research; changes in demand for and price of commodities (such as fuel and electricity) and currencies; competition in the mining industry; changes or disruptions in the securities markets; legislative, political or economic developments, including changes in federal and/or state laws that may significantly affect the mining industry; trade policies and tensions, including tariffs; inflationary pressures; the impacts of climate change, as well as actions taken or required by governments related to strengthening resilience in the face of potential impacts from climate change; the need to obtain permits and comply with laws and regulations and other regulatory requirements; the timing and reliability of sampling and assay data; the possibility that actual results of work may differ from projections/expectations or may not realize the perceived potential of NioCorp’s projects; risks of accidents, equipment breakdowns, and labor disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining, or development activities; management of the water balance at the Elk Creek Project site; land reclamation requirements related to the Elk Creek Project; the speculative nature of mineral exploration and development, including the risks of diminishing quantities of grades of reserves and resources; claims on the title to NioCorp’s properties; potential future litigation; and NioCorp’s lack of insurance covering all of NioCorp’s operations.

Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described herein. This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements. Forward-looking statements are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties, and other factors, including without limitation those discussed under Item 1A., Risk Factors below.

The Company’s forward-looking statements contained in this Annual Report on Form 10-K are based on the beliefs, expectations, and opinions of management as of the date of this Annual Report on Form 10-K. The Company does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations, or opinions should change, except as required by law. For the reasons set forth above, investors should not attribute undue certainty to, or place undue reliance on, forward-looking statements.

Available Information

We maintain a website at http://www.niocorp.com. Our Common Shares are currently registered under Section 12(b) of the Exchange Act, and we are currently required to file reports on Forms 10-K, 10-Q, or 8-K. Our Annual Report on Form 10-K (which includes our audited consolidated financial statements), Quarterly Reports on Form 10-Q, Current Reports on Form 8-K and amendments to reports filed or furnished pursuant to Sections 13(a) and 15(d) of the Exchange Act, are available on our website, free of charge, as soon as reasonably practicable after we electronically file such reports with, or furnish those reports to, the SEC. The SEC maintains an internet site that contains reports, proxy and information statements, and other information regarding issuers that file electronically with the SEC (http://www.sec.gov). We do not intend to send security holders a printed version of our Annual Report as it will be available online.

We maintain a Code of Conduct, a copy of which may be found on our website in the “About Us” section under the main title “Corporate Governance.” Our Code of Conduct contains information regarding whistleblower procedures.

We are not including the information contained on or accessible through our website or the SEC’s website as a part of, or incorporating it by reference into, this Annual Report on Form 10-K.

Risk factors

As filed, 71,721 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Our business activities are subject to significant risks, including those described below. You should carefully consider these risks. If any of the described risks occur, our business, financial position, and results of operations could be materially adversely affected. Such risks are not the only ones we face, and additional risks and uncertainties not presently known to us or that we currently deem immaterial may also affect our business. This report contains forward-looking statements that involve risks and uncertainties. Our actual results could differ materially from those anticipated in the forward-looking statements as a result of a number of factors, including the risks described below. See “Forward-Looking Statements” under Item 1., “Business.”

Risks Related to Our Business

Our ability to operate as a going concern is in doubt.

The notes that accompany our consolidated financial statements for the year ended June 30, 2025, disclose that substantial doubt exists as to our ability to continue as a going concern. The consolidated financial statements included in this Annual Report on Form 10-K have been prepared under the assumption that we will continue as a going concern. We are a development stage issuer and we have incurred losses since our inception.

As a development stage issuer, the Company has not yet commenced its mining operations and accordingly does not generate any revenue. The Company does not have sufficient cash on hand to fund planned operations as well as the construction necessary for mine development for the next twelve months. The Company is dependent on its ability to raise capital to fund future exploration and working capital requirements. Our plans for the long-term achievement of and continuation as a going concern include financing our future operations through sales of our Common Shares and/or debt and the potential profitable exploitation of our Elk Creek Project. Additionally, capital markets and general economic conditions in the U.S. and Canada may impose significant obstacles to raising the required funds. As discussed further below, while we have been successful in doing so in the past, there can be no assurance we will be able to raise funds in the future. These factors raise substantial doubt about our ability to continue as a going concern.

We will require significant additional capital to fund our business plan.

We will be required to make substantial capital expenditures to advance the Elk Creek Project to construction and commercial operation. We will also require funds for our ongoing capital needs and will be required to raise additional capital.

We expect that the Company will operate at a loss for the foreseeable future. The Company’s current planned cash needs are approximately $40.0 million to $50.0 million for the next twelve months. In addition to outstanding accounts payable and short-term liabilities, our planned expenditures over the next twelve months are expected to consist of expenditures relating to certain advancements of the Elk Creek Project by NioCorp’s majority owned subsidiary, ECRC, corporate overhead costs, and estimated costs related to securing financing necessary for advancement of the Elk Creek Project.

We expect to use our cash balance as of June 30, 2025, as well as the proceeds from the July 2025 Offering, the proceeds from the Warrant exercise issuances, and the reimbursement payments pursuant to the DoD Agreement, to fund our planned expenditures for the next twelve months. However, additional work is required in order to advance the Elk Creek Project, which will require additional financing. The S-K 1300 Elk Creek Technical Report Summary includes an estimated total upfront capital expenditure for the Elk Creek Project of approximately $1,141.0 million. The actual amount of capital expenditure required to successfully achieve commercial production at the Elk Creek Project is subject to, among other factors, the timing and actual cost of further exploration, preparing feasibility studies, permitting, engineering and the construction of infrastructure, mining and processing facilities. If the Company were able to obtain additional funding, the Company would be able to accelerate planned expenditures ahead of its current schedule. In addition, to the extent that EXIM requests further project activities to be undertaken in connection with the diligence process, the Company would require additional funding to complete such activities. The Company’s ability to continue operations and fund our current work plan is dependent on management’s ability to secure additional financing.

Except for the potential funding from advances under the Yorkville Equity Facility Financing Agreement, which is discussed below under Part II, Item 7. “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Liquidity and Capital Resources,” and the potential exercise of options to purchase Common Shares (“Options”) and Warrants, we currently have no further funding commitments or arrangements for additional financing at this time. In addition, agreements we enter into may contain restrictions on our ability to raise additional financing on reasonable terms or at all. For example, pursuant to the Exchange Agreement, NioCorp is restricted from issuing equity or equity-linked securities (other than Common Shares) or any preferred equity or non-voting equity if such issuance would adversely impact the rights of the holders of the shares of Class B common stock of ECRC, without the consent of the holders of a majority of the shares of Class B common stock of ECRC. Notwithstanding the restrictions set forth in the Exchange Agreement, there is significant uncertainty that we would be able to secure any additional financing in the current equity or debt markets.

Our ability to obtain necessary funding depends upon a number of factors, including the status of the national and worldwide economy and the price of the products we intend to produce. We are actively pursuing additional sources of debt and equity financing, and while we have been successful in doing so in the past, there can be no assurance we will be able to obtain any such additional financing on acceptable terms, if at all.

In addition, the potential EXIM Financing is subject to, among other matters, the satisfactory completion of due diligence, including the additional project activities identified in the PPL, the negotiation and settlement of final terms, and the negotiation of definitive documentation. There can be no assurance that the EXIM Financing will be completed on the terms described herein or at all.

Our inability to access sufficient capital for our operations could have a material adverse effect on our financial condition, results of operations, or prospects. Sales of substantial amounts of securities may have a highly dilutive effect on our ownership or share structure. Sales of a large number of Common Shares in the public markets, or the potential for such sales, could decrease the trading price of the Common Shares and could impair our ability to raise capital through future sales of Common Shares. We have not yet commenced commercial production at any of our properties and, as such, have not generated positive cash flows to date and have no reasonable prospects of doing so unless successful commercial production can be achieved at our Elk Creek Project. We expect to continue to incur negative investing and operating cash flows until such time as we enter into successful commercial production. This will require us to deploy our working capital to fund such negative cash flow and to seek additional sources of financing. There is no assurance that any such financing sources will be available or sufficient to meet our requirements. There is no assurance that we will be able to continue to raise equity capital or to secure additional debt financing, or that we will not continue to incur losses.

We have a limited operating history on which to base an evaluation of our business and prospects.

Since our inception, we have had no revenue from operations. We have no history of producing products from any of our properties. Our Elk Creek Project is a development stage property. Advancing our Elk Creek Project from a development stage property to a production stage property will require significant capital and time, and successful commercial production from the Elk Creek Property will be subject to permitting and construction of the mine, processing plants, roads, and other related works and infrastructure. As a result, we are subject to all of the risks associated with developing and establishing new mining operations and business enterprises including:

  • the timing and cost, which can be considerable, of further exploration, preparing feasibility studies, permitting, engineering and construction of infrastructure, mining, and processing facilities;
  • the availability and costs of drilling equipment, exploration personnel, skilled labor, and mining and processing equipment, if required;
  • the availability and cost of appropriate smelting and/or refining arrangements, if required;
  • compliance with environmental and other governmental approval and permit requirements;
  • the availability of funds to finance exploration, development, permitting, and construction activities, as warranted;
  • potential opposition from non-governmental organizations, local groups, or local residents that may delay or prevent development activities;
  • potential increases in exploration, construction, and operating costs due to changes in the cost of fuel, power, materials, and supplies; and
  • potential shortages of mining, mineral processing, hydrometallurgical, pyrometallurgical, construction, and other facilities-related supplies.

The costs, timing, and complexities of exploration, development, engineering, and construction activities may be increased by the location of our properties and competition from other mineral exploration and mining companies. It is common for exploration companies to experience unexpected problems and delays during development, if commenced, including engineering, procurement, construction, commissioning, and ramp-up. Accordingly, our activities may not result in profitable operations and we may not succeed in establishing operations or profitably producing products at any of our current or future properties, including our Elk Creek Project.

We have a history of losses and expect to continue to incur losses in the future.

We have incurred losses since inception, have negative cash flow from operating activities, and expect to continue to incur losses in the future. We incurred a net loss attributable to the Company of $17.4 million for the year ended June 30, 2025, and $11.4 million for the year ended June 30, 2024.

We expect to continue to incur losses unless and until such time as one of our properties enters into commercial production and generates sufficient revenues to fund continuing operations. We recognize that if we are unable to generate significant revenues from operations and dispositions of our properties, we will not be able to earn profits or continue operations. At this early stage of our operation, we also expect to face the risks, uncertainties, expenses, and difficulties frequently encountered by companies at the start-up stage of their business development. We cannot be sure that we will be successful in addressing these risks and uncertainties and our failure to do so could have a materially adverse effect on our financial condition.

Increased costs could affect our financial condition.

We anticipate that costs at our projects that we may explore or develop, including the Elk Creek Project, will frequently be subject to variation from one year to the next due to a number of factors, such as changing ore grade, metallurgical performance, and revisions to mine plans, if any, in response to the physical shape and location of the ore body. In addition, costs are affected by the price of commodities such as fuel, steel, aluminum, iron, chemicals, natural gas, fresh water, and electricity, as well as by government actions such as tariffs. Such commodities are at times subject to volatile price movements, including increases that could make production at certain operations less profitable or not profitable at all. For example, the S-K 1300 Elk Creek Technical Report Summary includes an estimated total upfront capital expenditure for the Elk Creek Project of approximately $1,141.0 million. The actual amount of capital expenditure required to successfully achieve commercial production at the Elk Creek Project is subject to, among other factors, the timing and actual cost of further exploration, preparing feasibility studies, permitting, engineering and the construction of infrastructure, mining, and processing facilities. A material increase in costs at any significant location could have a significant effect on our profitability.

A disruption in, or failure of our third-party service providers’ IT systems, including those related to cybersecurity, could adversely affect our business operations and financial performance.

We rely on the accuracy, capacity, and security of our third-party service providers’ IT systems for the operations of many of our business processes and to comply with regulatory, legal, and tax requirements. We are dependent on third parties to provide important IT services relating to, among other things, operational technology at our facilities, human resources, electronic communications, and certain finance functions. Despite the security measures that our third-party service providers have implemented, including those related to cybersecurity, we have experienced, and may experience in the future, cybersecurity incidents. Cybersecurity incidents and similar attacks vary in their form and can include the deployment of harmful malware or ransomware, denial-of-service attacks, and other attacks, which may affect business continuity and threaten the availability, confidentiality and integrity of our systems and information, and the systems and information of our third-party service providers. Cybersecurity incidents can also include employee or personnel failures, fraud, phishing or other social engineering attempts or other methods to cause confidential information, payments, account access or access credentials, or other data to be transmitted to an unintended recipient. Cybersecurity threat actors also may attempt to exploit vulnerabilities in software that is commonly used by companies in cloud-based services and bundled software. As previously disclosed, on February 14, 2025, we became aware of unauthorized third-party access to our information systems, including portions of its email systems, that resulted in misdirected vendor payments (the “Cybersecurity Incident”). To date, the Cybersecurity Incident has not had a material impact on our business operations or financial condition.

Though our third-party service providers have controls in place, we cannot provide assurance that a cybersecurity incident will not occur in the future. Furthermore, we may have little or no oversight with respect to security measures employed by third-party service providers, which may ultimately prove to be ineffective at countering threats. Cybersecurity threats or incidents or disruptions of our third-party service providers’ IT systems could interrupt our ability to manage and operate our business, impact data, and adversely affect our business operations and financial performance, including major disruptions to business operations, loss of intellectual property, release of confidential information, alteration or corruption of data or systems, costs related to remediation or the payment of ransom, and litigation including individual claims or consumer class actions, commercial litigation, administrative, and civil or criminal investigations or actions, regulatory intervention and sanctions or fines, investigation and remediation costs and possible prolonged negative publicity. In addition, we have incurred costs in connection with the remediation of the Cybersecurity Incident and we may be required to incur significant costs to protect against and, if required, remediate the damage caused by cybersecurity incidents, disruptions or system failures in the future.

A shortage of equipment and supplies could adversely affect our ability to operate our business.

We are dependent on various supplies and equipment to carry out our mining exploration and, if warranted, project development operations. The shortage of such supplies, equipment, and parts could have a material adverse effect on our ability to carry out our operations and could therefore limit, or increase the cost of, production. Ongoing disruptions to the world’s economy, including issues related to supply chains, inflation, tariffs and trade tensions, and increased raw material and labor costs, may delay our ability to secure supplies and equipment for the Elk Creek Project on a timely basis.

Joint ventures and other partnerships, including offtake arrangements, may expose us to risks.

We have entered into offtake agreements related to our Elk Creek Project as well as agreements related to the supply of natural gas and electricity to the project site, and may enter into joint ventures or partnership arrangements, including additional offtake agreements, with other parties in relation to the exploration, development, and production of certain of the properties in which we have an interest. Any failure of such other companies to meet their obligations to us or to third parties, or any disputes with respect to the parties’ respective rights and obligations, price fluctuations and termination provisions related to such agreements, or our ability to negotiate extensions to existing agreements or to enter into new agreements, on favorable terms or at all, could have a material adverse effect on us, the development and production at our properties, including the Elk Creek Project, the joint ventures, if any, or their properties and therefore could have a material adverse effect on our results of operations, financial performance, cash flows, and the price of our Common Shares.

We may experience difficulty attracting and retaining qualified management to meet the needs of our anticipated growth, and the failure to manage our growth effectively could have a material adverse effect on our business and financial condition.

We are dependent on a relatively small number of key employees, including our Chief Executive Officer. The loss of any officer could have an adverse effect on us. We have no life insurance on any individual, and we may be unable to hire a suitable replacement for them on favorable terms, should that become necessary.

The effect on the capital markets and the economy of recent global events, including inflation, volatility in commodity prices, supply chain uncertainty, tariffs and trade tensions, and increases in raw material and labor costs, could have an adverse effect on NioCorp’s business plans, financial condition, and liquidity.

Certain events have effected, and continue to effect, the global and United States economies, including increased inflation, volatility in commodity prices, supply chain uncertainty, tariffs and trade tensions, and increases in raw material and labor costs. We cannot predict how this will affect our business, but the impact may be adverse.

Although it is not possible to predict the ultimate impact of these factors on NioCorp’s business plans, financial position, or liquidity, such impacts that may be material include, but are not limited to: (i) delays in the completion of the mine and surface engineering designs and uncertainty regarding our ability to finalize necessary Engineering, Procurement, and Construction (“EPC”) agreements as a result of disruptions in the businesses of our engineering consultants and key contractors for the Elk Creek Project, (ii) reduced availability and increased costs of employees, (iii) a negative impact on our liquidity position, and (iv) increased costs and less ability to access funds in the capital markets. The full extent to which these factors may continue to impact our business will depend on future developments, which continue to be highly uncertain and cannot be predicted at this time.

In addition, we cannot predict the impact that recent global events, including inflation, volatility in commodity prices, supply chain uncertainty, tariffs and trade tensions, and increases in raw material and labor costs will have on our customers, suppliers, vendors, and other business partners, and each of their financial conditions; however, any material effect on these parties could adversely impact us.

It may be difficult to enforce judgments or bring actions outside the U.S. against us and certain of our directors.

We are a Canadian corporation and, as a result, it may be difficult or impossible for an investor to do the following:

  • enforce in courts outside the U.S. judgments obtained in U.S. courts based upon the civil liability provisions of U.S. federal securities laws against these persons and the Company; or
  • bring in courts outside the U.S. an original action to enforce liabilities based upon U.S. federal securities laws against these persons and the Company.

We may not recognize the full value of the Yorkville Equity Facility Financing Agreement and may not receive any proceeds from the exercise of our outstanding Warrants, and the potential adverse effect on the prevailing market prices for our Common Shares as a result of sales, or the perception of future sales, of Common Shares could adversely affect our ability to raise additional capital.

Although we have entered into the Yorkville Equity Facility Financing Agreement, we may not recognize the full value thereof. Specifically, our ability to sell Common Shares to Yorkville pursuant to the Yorkville Equity Facility Financing Agreement is subject to certain restrictions and limitations, which may prevent us from selling the full commitment amount prior to the expiration of the commitment period. Our ability to recognize the full value of the Yorkville Equity Facility Financing Agreement may be further impeded by the potential negative pressure on the market price of our Common Shares as a result of sales, or the perception of future sales, of Common Shares by us or by other security holders. As a result, there can be no assurance that we will receive all or even a significant portion of the proceeds that we expect to receive in connection with the Yorkville Equity Facility Financing Agreement.

In addition, upon exercise, we will receive the cash exercise price of our outstanding Warrants (assuming, that they are not exercised on a cashless basis, as applicable). We believe the likelihood that holders will exercise their Warrants, and therefore, the amount of cash proceeds that we would receive, is, among other things, dependent upon the market price of our Common Shares. For so long as the market price for our Common Shares is less than the applicable exercise price of the Warrants, we believe such holders will be unlikely to exercise their Warrants. The potential adverse effect on the prevailing market price of our Common Shares as a result of sales of Common Shares by us or by other security holders, or the perception that such sales may occur, could keep the market price for our Common Shares below the applicable exercise price of the Warrants. Accordingly, the holders of the Warrants may not exercise their Warrants before they expire, and we may not receive any proceeds from the exercise of the outstanding Warrants.

We may not recognize the full value of the DoD Agreement.

Subject to the terms and conditions of the DoD Agreement, the DoD will reimburse ECRC for a portion of the costs incurred by ECRC under the DoD Agreement and ECRC is entitled to receive up to an aggregate of approximately $10.0 million of reimbursement payments from the DoD upon the achievement of certain project milestones. If the Company is not successful in achieving the milestones required under the DoD Agreement or if the reimbursements sought by the Company are rejected or the DoD Agreement is terminated prior to completion of all milestones, the Company may not receive all or even a significant portion of the payments as reimbursements for expenses incurred as expected under the DoD Agreement.

The Company has identified material weaknesses in its internal control over financial reporting. If not remediated, the Company’s failure to establish and maintain effective disclosure controls and procedures and internal control over financial reporting could result in material misstatements in its financial statements and a failure to meet its reporting and financial obligations, each of which could have a material adverse effect on the Company’s financial condition and the trading price of the Common Shares.

Our management has identified material weaknesses in its internal control over financial reporting relating to deficiencies in the principles associated with the control environment, risk assessment, control activities, and monitoring components of internal control, based on the criteria established by the COSO Framework, that constitute material weaknesses, either individually or in the aggregate. A material weakness is a deficiency, or a combination of deficiencies, in internal control over financial reporting, such that there is a reasonable possibility that a material misstatement of a company’s annual or interim financial statements will not be prevented or detected on a timely basis.

As discussed in Item 9A, “Controls and Procedures,” of this Annual Report on Form 10-K, the Company’s management has assessed the effectiveness of its internal control over financial reporting and its disclosure controls and procedures and concluded that they were not effective as of June 30, 2025.

The Company is committed to remediating its material weaknesses as promptly as possible. Management is in the process of implementing its remediation plan. However, there can be no assurance as to when the material weaknesses will be remediated or that additional material weaknesses will not arise in the future. If the Company is unable to maintain effective internal control over financial reporting, its ability to record, process and report financial information timely and accurately could be adversely affected, which could subject the Company to litigation or investigations, require management resources, increase costs, negatively affect investor confidence and adversely impact the trading price of the Common Shares.

We may face litigation and other risks as a result of the material weaknesses in our internal control over financial reporting.

We identified material weaknesses in our internal control over financial reporting that exist as of June 30, 2025. As a result of such material weaknesses and other matters raised or that may in the future be raised by the SEC or the

Canadian securities regulators, we face potential for litigation or other disputes, which may include, among others, claims invoking the federal and state securities laws, contractual claims or other claims arising from the material weaknesses in our internal control over financial reporting and the preparation of our financial statements. As of the date of this Annual Report on Form 10-K, we have no knowledge of any such litigation or dispute. However, we can provide no assurance that such litigation or dispute will not arise in the future. Any such litigation or dispute, whether successful or not, could adversely affect our business, financial condition and results of operations.

Risks Related to Mining and Development

We face numerous uncertainties in estimating our mineral reserves and resources and inaccuracies in our estimates could result in lower than expected revenues, higher than expected costs, and decreased profitability.

A mineral is economically recoverable when the price at which we may sell the mineral exceeds the costs and expenses of mining and selling the mineral. Forecasts of our future performance are based on, among other things, estimates of our mineral reserves. We base our reserve and resource information on engineering, economic, and geological data assembled and analyzed by qualified persons, which include various engineers and geologists on our staff and with third parties. Our estimates are also subject to SEC regulations regarding classification of reserves and resources, including S-K 1300. Our reserve and resource estimates as to both quantity and quality are updated from time to time to reflect additional information received. There are numerous uncertainties inherent in estimating quantities and qualities of mineral reserves and resources, including many factors beyond our control.

Estimates of mineral reserves and resources necessarily depend upon a number of variable factors and assumptions, any one of which may, if incorrect, result in an estimate that varies considerably from actual results. These factors and assumptions include, but are not limited to:

  • geologic and mining conditions, which may not be fully identified by available exploration data and may differ from our experience;
  • demand for the minerals that we plan to produce;
  • current and future market prices for minerals and contractual arrangements;
  • current and future operating costs and capital expenditures may exceed estimates, notwithstanding that, under S-K 1300, operating cost and capital expenditure estimates in feasibility studies must have an accuracy level of at least ±15% and a contingency range not exceeding 10%;
  • additional capital expenditure related to the modification of the proposed surface plant related to the potential addition of rare earth elements;
  • severance and excise taxes, royalties and development and reclamation costs;
  • future mining technology improvements;
  • the effects of regulation by governmental agencies;
  • the ability to obtain, maintain and renew all required permits;
  • employee health and safety; and
  • historical production from the area compared with production from other producing areas.

The conversion of reported mineral resources to mineral reserves should not be assumed, and the reclassification of reported mineral resources from lower to higher levels of geological confidence should not be assumed. As such, actual mineral tonnage recovered from identified reserves, and revenues and expenditures with respect to our reserves, may vary materially from estimates. Thus, these estimates may not accurately reflect our actual reserves. Any material inaccuracy in our estimates related to our reserves could result in lower than expected revenues, higher than expected costs, or decreased profitability, which could materially and adversely affect our business, results of operations, financial position, and cash flows.

The nature of mineral exploration and production activities involves a high degree of risk and the possibility of uninsured losses.

Exploration for and the production of minerals is highly speculative and involves much greater risk than many other businesses. Most exploration programs do not result in the discovery of mineralization, and any mineralization discovered may not be of sufficient quantity or quality to be profitably mined. Our operations are, and any future development or mining operations we may conduct will be, subject to all of the operating hazards and risks normally incident to exploring for and developing mineral properties, such as, but not limited to:

  • economically insufficient mineralized material;
  • fluctuation in production costs that make production uneconomical;
  • labor disputes;
  • unanticipated variations in grade and other geologic problems;
  • environmental hazards;
  • water conditions;
  • difficult surface or underground conditions;
  • industrial accidents;
  • metallurgical, pyrometallurgical, and other processing problems;
  • mechanical and equipment performance problems;
  • failure of dams, stockpiles, wastewater transportation systems, or impoundments;
  • unusual or unexpected rock formations; and
  • personal injury, fire, flooding, cave-ins, and landslides.

Any of these risks can materially and adversely affect, among other things, the development of properties, production quantities and rates, costs and expenditures, potential revenues, and production dates. We currently have very limited insurance to guard against some of these risks. If we determine that capitalized costs associated with any of our mineral interests are not likely to be recovered, we would incur a write-down of our investment in these interests. All of these factors may result in losses in relation to amounts spent that are not recoverable, or that result in additional expenses.

We have no history of producing commercial products from our current mining properties and there can be no assurance that we will successfully establish mining operations or profitably produce minerals.

We have no history of producing commercial products from our current mining properties. We do not produce commercial products and do not currently generate operating earnings. While we seek to move our Elk Creek Project from a development stage property to a production stage property, such efforts will be subject to all of the risks associated with establishing new mining operations and business enterprises, including:

  • the timing and cost, which are considerable, of the construction of mining and processing facilities;
  • the availability and costs of skilled labor and equipment;
  • compliance with environmental and other governmental approval and permit requirements;
  • the availability of funds to finance construction and development activities;
  • potential opposition from non-governmental organizations, local groups, or local residents that may delay or prevent development activities; and
  • potential increases in construction and operating costs due to changes in the cost and availability of labor, fuel, power, materials, and equipment and supplies, and the time elapsed since the most recent estimates of cost and availability were made.

It is common in new mining and processing operations to experience unexpected problems and delays during engineering, procurement, construction, commissioning, and initial operations. In addition, our management and workforce will need to be expanded, and sufficient housing and other support systems for our workforce will have to be established. This could result in delays in the commencement of production and increased costs of production. Accordingly, we cannot assure you that our activities will result in profitable operations or that we will successfully establish mining and processing operations.

Results of metallurgical testing by us may not be favorable to, or as expected by, us.

We have completed significant bench, mini-pilot, and pilot scale metallurgical testing on material from the Elk Creek Project and will continue to complete necessary metallurgical testing at the bench, mini-pilot, and pilot scale as the exploration and, if warranted, development of the Elk Creek Project progresses. There can be no assurance that the results of such metallurgical testing will be favorable to, or will be as expected by, us. Furthermore, there can be no certainty that metallurgical recoveries obtained in bench or pilot scale tests will be achieved in either subsequent testing or commercial operations. The development of a complete metallurgical process to produce saleable final products from the Elk Creek Project is a complex and resource-intensive undertaking that may result in overall schedule delays and increased project costs for us.

Price volatility could have dramatic effects on our results of operations and our ability to obtain financing for the Elk Creek Project and execute our business plan.

The price of commodities varies on a daily basis. Niobium is a specialty metal and not a commonly traded commodity such as copper, zinc, gold, or iron ore. The price of niobium tends to be set through a limited long-term offtake market, contracted between very few suppliers and purchasers. The world’s largest supplier of niobium, Companhia Brasileira de Metalurgia e Mineração, supplies approximately 85% of the world’s niobium. Any attempt to suppress the price of niobium by such supplier, or an increase in production by any supplier in excess of any increased demand, would have negative consequences on the price of niobium and, potentially, on our value. The price of niobium may also be reduced by the discovery of new niobium deposits, which could not only increase the overall supply of niobium (causing downward pressure on its price) but could draw new firms into the niobium industry that would compete with us.

Sc2O3 is used in solid oxide fuel cells and has the potential to become a valuable alloy with aluminum in the aerospace and automotive industries. Supply of scandium has been sporadic in recent years, and there are no primary scandium mines in the world at present. Production primarily occurs as a by-product from existing metallurgical plants, primarily in Russia, Canada, the Philippines, and China. Our management believes the Elk Creek Project would significantly increase the world’s supply of scandium trioxide. Although the Company’s market studies indicate a positive outlook for demand, there is no assurance at present that the Company could sell all of its production. In addition, the sale of scandium represents a significant portion of the Elk Creek Project revenue; achieving the revenue projected in the Company’s studies is subject to market growth in scandium, which is a developing market with a risk of oversupply and/or undersupply disrupting pricing.

Titanium metal is used in various superalloys and other applications for aerospace applications, armor, and medical implants, and in oxide form is a key component of pigments used in paper, paint, and plastics. The Elk Creek Project would produce a small quantity of titanium dioxide relative to other producers. As a small producer, we would be subject to fluctuations in the price of TiO2 that would result from normal variations in supply and demand for this commodity.

In addition, the niobium, scandium, titanium, and potentially, rare earth products, that we intend to produce at the Elk Creek Project are also subject to additional commodity-specific price cycles resulting from, among other factors, export controls, taxes and other tariffs and fees. Volatility in the demand for, and prices of, the niobium, scandium, titanium, and potentially, rare earth products, that we intend to produce at the Elk Creek Project may adversely affect the overall value of the Elk Creek Project and impact our ability to obtain financing for the Elk Creek Project on acceptable terms, or at all.

We may not be able to establish a viable recovery process for REEs.

The market for rare earth products requires particular levels of purity and chemical form, which are achieved through the extraction and separation of individual REEs from each other as well as from the other constituents in the rare earth ore. At present, the Company has substantially completed the engineering and testing of a process for producing commercial rare earth products but has not completed all work necessary to declare a REE reserve estimate for the Elk Creek deposit. The completion of the work necessary to demonstrate an economically feasible rare earth recovery system will require additional expenditures of cash and time to complete. There is no guarantee that the Company will be successful in demonstrating positive economics for a rare earth recovery system tied to the Elk Creek Project, nor is there any guarantee that once constructed, the rare earth recovery system will operate as designed and produce saleable commercial products.

Estimates of resources and reserves are subject to evaluation uncertainties that could result in project failure.

Our exploration and future mining operations, if any, are and would be faced with risks associated with being able to accurately predict the quantity and quality of resources/reserves within the earth using statistical sampling techniques. Estimates of any resources/reserves on any of our properties would be made using samples obtained from appropriately placed trenches, test pits, underground workings, and intelligently designed drilling. There is an inherent variability of assays between check and duplicate samples taken adjacent to each other and between sampling points that cannot be reasonably eliminated. Additionally, there also may be unknown geologic details that have not been identified or correctly appreciated at the current level of accumulated knowledge about our properties. This could result in uncertainties that cannot be reasonably eliminated from the process of estimating resources/reserves. If these estimates were to prove to be unreliable, we could implement an exploitation plan that may not lead to commercially viable operations in the future.

Any material changes in mineral resource/reserve estimates and grades of mineralization will affect the economic viability of placing a property into production and a property’s return on capital.

Mineral resource/reserve estimates may require adjustments or downward revisions. In addition, the grade of ore ultimately mined, if any, may differ from that indicated by our feasibility studies and drill results. Minerals recovered in small scale tests may not be duplicated in large scale tests under on-site conditions or at commercial production scale.

The mineral resource and mineral reserve estimates included in the S-K 1300 Elk Creek Technical Report Summary and contained in this Annual Report on Form 10-K have been determined based on assumed future prices, cut-off grades, and operating costs that may prove to be inaccurate. Extended declines in market prices for our products may render portions of our resource/reserve estimates uneconomic and may result in reduced reported resources/reserves or may adversely affect any commercial viability determinations we may reach. Any material reductions in estimates of resources/reserves could have a material adverse effect on our Common Share price and on the value of our properties.

We face intense competition in the mining industry.

The mining industry is intensely competitive in all of its phases, and we compete with other companies for capital. As a result of this competition, some of which is with large established mining companies with substantial capabilities and with greater financial and technical resources than ours, we may be unable to obtain financing for the Elk Creek Project on terms we consider acceptable, or at all, or to acquire and develop additional properties in the future. In addition, we compete with others in efforts to obtain resources to advance the Elk Creek Project to construction and commercial operation, including mining and processing equipment, as well as qualified managerial and technical employees. If we are unable to successfully compete for required resources, including qualified employees, we may have difficulty in advancing the Elk Creek Project to construction and commercial operation. In addition, in competing for qualified personnel, we may be required to pay compensation or benefits relatively higher than those paid in the past, and the availability of qualified personnel may be limited in high-demand periods.

Difficulties in water balance management at our Elk Creek Project could negatively affect our potential production and economics at the project.

The Company has conducted three field investigations and two major technical studies into the hydrogeology of the Elk Creek carbonatite, which is the geologic formation which hosts the mineralized material that would be extracted by the Company’s mining operations. The Company expects to encounter significant amounts of water in the carbonatite, which will need to be pumped out of the formation to facilitate a mining operation. Water quality analyses have demonstrated that this water will have elevated temperature and salt content when compared to other water resources in the area. While the Company has developed plans to treat water produced from the mine for use in its operations, there is no guarantee that the permits needed for the treatment of the water or the disposal of the resultant waste products will be issued by the State of Nebraska, nor is there any guarantee that such permits will be issued in a timely fashion. Further, based on such plans, the operations will rely on a water treatment system to achieve zero discharge of wastewater, and there is no guarantee that this system will function as designed or achieve nameplate treatment capacity.

Title to our properties may be subject to other claims that could affect our property rights and claims.

There are risks that title to our properties may be challenged or impugned. Our Elk Creek Project is located in Nebraska and may be subject to prior unrecorded agreements or transfers or native land claims, and title may be affected by undetected defects. Our current land and/or mineral rights lease agreements between ECRC and individual landowners give us an option to purchase additional property (“OTP”), which, along with the property we already own, will allow us to construct the Elk Creek Project once sufficient project financing is obtained. The rights of the current owners to sell the property subject to these options may be subject to prior unrecorded or unknown claims to title. Further, our current OTP agreements, some of which are important for our planned operations, are of fixed duration and expire between December 2029 and May 2040, and we may incur additional cost and delays in securing renewals of such OTPs. We have investigated our rights to explore and exploit the Elk Creek Project resource/reserve and, to the best of our knowledge, our rights in relation to lands covering the Elk Creek Project resource/reserve are in good standing. However, there may be valid challenges to the title of our properties that, if successful, could impair development and/or operations.

Our properties and operations may be subject to litigation or other claims.

From time to time our properties or operations may be subject to disputes that may result in litigation or other legal claims. We may be required to assert or defend against these claims, which will divert resources and management time from operations. The costs of these claims or adverse filings may have a material effect on our business and results of operations.

We do not currently insure against all the risks and hazards of mineral exploration, development, and mining operations.

Exploration, development, mining, and surface operations involve various hazards, including environmental hazards, industrial accidents, metallurgical and other processing problems, unusual or unexpected rock formations, structural cave-ins or slides, flooding, fires, and periodic interruptions due to inclement or hazardous weather conditions. These risks could result in damage to or destruction of mineral properties, facilities, or other property, personal injury, environmental damage, delays in operations, increased cost of operations, monetary losses, and possible legal liability. We may not be able to obtain insurance to cover these risks at economically feasible premiums or at all. We may elect not to insure where premium costs are disproportionate to our perception of the relevant risks. The payment of such insurance premiums and of such liabilities would reduce the funds available for exploration and production activities.

Risks Related to Government Regulation

We may not be able to obtain or renew all required permits and licenses to place any of our properties into production.

Our current and future operations, including development activities and commencement of production, if warranted, on the Elk Creek Project, require permits from governmental authorities and such operations are and will be governed by laws and regulations governing prospecting, development, mining, production, exports, taxes, labor standards, occupational health, waste disposal, toxic substances, land use, environmental protection, mine safety, and other matters. Companies engaged in mineral property exploration and the development or operation of mines and related facilities generally experience increased costs, as well as delays in production and other schedules as a result of the need to comply with applicable laws, regulations, and permits. We cannot predict if all permits that we may require for continued exploration, development, or construction of mining facilities and conduct of mining operations will be obtainable or renewable on reasonable terms, if at all. Costs related to applying for and obtaining permits and licenses may be prohibitive and could delay our planned exploration and development activities. Failure to comply with applicable laws, regulations, and permitting requirements may result in enforcement actions, including orders issued by regulatory or judicial authorities causing operations to cease or be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment, or remedial actions.

Facilities associated with the Elk Creek Project, such as the mine, surface plant, tailings facilities, stockpiles and supporting infrastructure, are likely to either temporarily or permanently impact waterbodies and wetlands that are subject to regulation by the USACE as Waters of the United States (“WOUS”). We believe that we have obtained the necessary USACE permits to construct the project, but changes to the design or layout of the facility may trigger the USACE to require us to obtain and maintain additional permits for the Elk Creek Project. The duration of this permitting exercise is dictated by the USACE and would need to be completed before facilities that would impact WOUS could be constructed. We may experience delays or additional costs in relation to obtaining the necessary permits and these delays and additional costs could negatively affect the economics of the Elk Creek Project and our results of operations.

Parties engaged in mining operations may be required to compensate those suffering loss or damage by reason of the mining activities and may have civil or criminal fines or penalties imposed for violations of applicable laws or regulations. Amendments to current laws, regulations, and permits governing operations and activities of mining companies, or more stringent implementation thereof, could have a material adverse impact on our operations and cause increases in capital expenditures or production costs or reduction in levels of production at producing properties or require abandonment or delays in development of new mining properties.

We are subject to significant governmental regulations that affect our operations and costs of conducting our business.

Our current and future operations, including development of the Elk Creek Project, are and will be governed by laws and regulations, including:

  • laws and regulations governing mineral concession acquisition, prospecting, development, mining, and production;
  • laws and regulations related to exports, taxes, and fees;
  • labor standards and regulations related to occupational health and mine safety; and
  • environmental standards and regulations related to waste disposal, toxic substances, land use reclamation, and environmental protection.

Companies engaged in development activities often experience increased costs and delays in production and other schedules as a result of the need to comply with applicable laws, regulations, and permits. Failure to comply with applicable laws, regulations, and permits may result in enforcement actions, including the forfeiture of mineral claims or other mineral tenures and/or orders issued by regulatory or judicial authorities requiring operations to cease or be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment, or costly remedial actions. We may be required to compensate those suffering loss or damage by reason of our development activities and may have civil or criminal fines or penalties imposed for violations of such laws, regulations, and permits.

Existing and possible future laws, regulations, and permits governing operations and activities of mineral development companies, or more stringent implementation, could have a material adverse impact on our business and cause increases in capital expenditures or require abandonment or delays in development. Our Elk Creek Project is located in Nebraska, and while the State does have a comprehensive and modern set of environmental regulations, it does not have specific regulations with respect to permitting or reclaiming mines which could potentially impact the total time to market for the project.

Our activities are subject to environmental laws and regulations that may change, thereby increasing our costs of doing business and restricting our operations.

All phases of our operations are subject to environmental regulation in the jurisdictions in which we operate. Environmental legislation is evolving in a manner that may require stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of proposed projects, and a heightened degree of responsibility for companies and their officers, directors, and employees. These laws address emissions into the air, discharges into water, management of waste, management of hazardous substances, protection of natural resources, antiquities and endangered species, and reclamation of lands disturbed by mining operations. Compliance with environmental laws and regulations, and future changes in these laws and regulations, may require significant capital outlays and may cause material changes or delays in our operations and future activities. It is possible that future changes in these laws or regulations could have a significant adverse impact on our properties or some portion of our business, causing us to re-evaluate those activities at that time.

Regulations and pending legislation governing issues involving climate change could result in increased operating costs, which could have a material adverse effect on our business.

A number of governments or governmental bodies have introduced or are contemplating legislative and/or regulatory changes in response to concerns about the potential impact of climate change. Legislation and increased regulation regarding climate change could impose significant costs on us, on our future venture partners, if any, and on our suppliers, including costs related to increased energy requirements, capital equipment, environmental monitoring and reporting, and other costs necessary to comply with such regulations. Any adopted future climate change regulations could also negatively impact our ability to compete with companies situated in areas not subject to such limitations. Given the emotion, political significance, and uncertainty surrounding the impact of climate change and how it should be dealt with, we cannot predict how legislation and regulation will affect our financial condition, operating performance, and ability to compete. Furthermore, even without such regulation, increased awareness and any adverse publicity in the global marketplace about potential impacts on climate change by us or other companies in our industry could harm our reputation. The potential physical impacts of climate change on our operations are highly uncertain and could be particular to the geographic circumstances in areas in which we operate and may include changes in rainfall and storm patterns and intensities, water shortages, changing sea levels, and changing temperatures. These impacts may adversely impact the cost, production, and financial performance of our operations.

Land reclamation requirements for our properties may be burdensome and expensive.

Although variable depending on location and the governing authority, land reclamation requirements are generally imposed on mineral exploration companies (as well as companies with mining operations) in order to minimize long-term effects of land disturbance.

Reclamation may include requirements to:

  • control dispersion of potentially deleterious effluents;
  • treat ground and surface water to achieve water quality standards; and
  • reasonably re-establish pre-disturbance landforms and vegetation.

In order to carry out reclamation obligations imposed on us in connection with our potential development activities, we must allocate financial resources that might otherwise be spent on further exploration and development programs. We plan to set up a provision for our reclamation obligations on our properties, as appropriate, but this provision may not be adequate. If we are required to carry out unanticipated reclamation work, our financial position could be adversely affected.

Risks Related to Our Debt

The level of our indebtedness from time to time could impair our ability to obtain additional financing.

From time to time, we may enter into transactions to acquire assets or the shares of other companies or to fund development of the Elk Creek Project. These transactions may be financed partially or wholly with debt, which may increase our debt levels above industry standards. Our articles of incorporation do not limit the amount of indebtedness that we may incur. Our indebtedness could impair our ability to obtain additional financing in the future on a timely basis to take advantage of business opportunities that may arise. Our ability to service our debt obligations will depend on our future operations, which are subject to prevailing industry conditions and other factors, many of which are beyond our control.

Risks Related to the Common Shares

NioCorp may be a “passive foreign investment company” for the current taxable year and for one or more future taxable years, which may result in materially adverse U.S. federal income tax consequences for U.S. investors.

If NioCorp is a passive foreign investment company (“PFIC”) for any taxable year, or portion thereof, that is included in the holding period of a U.S. holder of Common Shares or other securities of NioCorp, such U.S. holder may be subject to certain adverse U.S. federal income tax consequences. These adverse tax consequences include requirements to treat any gain realized upon a disposition of Common Shares or other securities, or any “excess distribution” received on Common Shares, as ordinary income, to pay an interest charge on a portion of such gain or distribution, and certain additional reporting requirements. Such consequences may be mitigated with respect to Common Shares (but not with respect to Warrants or other securities of NioCorp) if the holder thereof makes a timely and effective “qualified electing fund” or “QEF” election or a “mark-to-market” election. A U.S. holder of Common Shares that makes a QEF election generally must include in income on a current basis for U.S. federal income tax purposes its share of NioCorp’s net capital gain and ordinary earnings for any taxable year in which it is a PFIC, whether or not NioCorp distributes any amount to its shareholders. A U.S. holder of Common Shares that makes a mark-to-market election generally must include as ordinary income each year the excess of the fair market value of the Common Shares over the taxpayer’s basis therein.

NioCorp generally will be classified as a PFIC for a taxable year if (a) 75% or more of its gross income for such year is “passive income” (generally, dividends, interest, rents, royalties, and gains from the disposition of assets producing passive income) or (b) at least 50% or more of the value of its assets produce, or are held for the production of, passive income, based on the quarterly average of the fair market value of such assets. NioCorp believes that it was classified as a PFIC for its taxable years ended June 30, 2025 and 2024 and, based on the current composition of its income and assets, as well as current business plans and financial expectations, may be classified as a PFIC for its current or future taxable years. Any conclusion regarding PFIC status is a factual determination that must be made annually at the close of each taxable year and, thus, is subject to change. In addition, even if NioCorp concluded it did not qualify as a PFIC, it is possible that the U.S. Internal Revenue Service (the “IRS”) could assert, and that a court could sustain, a determination that NioCorp is a PFIC. Accordingly, there can be no assurance that NioCorp will not be treated as a PFIC for any taxable year. The PFIC rules are complex and each holder of Common Shares or other securities of NioCorp should consult its own tax advisors regarding these rules and the U.S. federal income tax consequences of the acquisition, ownership, and disposition of such securities.

The 2023 Transactions could result in NioCorp becoming subject to materially adverse U.S. federal income tax consequences.

Section 7874 and related sections of the U.S. Internal Revenue Code of 1986, as amended (the “Code”), provide for certain adverse tax consequences when the stock of a U.S. corporation is acquired by a non-U.S. corporation in certain transactions in which former shareholders of the U.S. corporation come to own 60% or more of the stock of the non-U.S. corporation (by vote or value, and applying certain specific counting and ownership rules). These adverse tax consequences include (i) potential additional required gain recognition by the U.S. corporation, (ii) treatment of certain payments to the non-U.S. corporation that reduce gross income as “base erosion payments,” (iii) an excise tax on certain options and stock-based compensation of the U.S. corporation, (iv) disallowance of “qualified dividend” treatment for distributions by the non-U.S. corporation, and (v) if former shareholders of the U.S. corporation come to own 80% or more of the stock of the non-U.S. corporation, treatment of the non-U.S. corporation as a U.S. corporation subject to U.S. federal income tax on its worldwide income (in addition to any tax imposed by non-U.S. jurisdictions). If the 2023 Transactions result in the application of any of these, or any other, adverse tax consequences, NioCorp could incur significant additional tax costs. While NioCorp currently does not believe the 2023 Transactions will cause such adverse tax consequences as a result of Section 7874 and related sections of the Code, this determination is subject to significant legal and factual uncertainty. NioCorp has not sought and will not seek any rulings from the IRS as to the tax treatment of any of the 2023 Transactions. Further, there can be no assurance that your tax advisor, the IRS, or a court, will agree with the position that NioCorp is not subject to these adverse tax consequences.

Our Common Share price may be volatile and as a result you could lose all or part of your investment.

In addition to volatility associated with equity securities in general, the value of your investment could decline due to the impact of any of the following factors upon the market price of the Common Shares:

  • disappointing results from our exploration and/or, if warranted, project development efforts;
  • decline in demand for Common Shares;
  • downward revisions in securities analysts’ estimates or changes in general market conditions;
  • technological innovations by competitors or in competing technologies;
  • investor perception of our industry or our prospects; and
  • general economic trends.

From July 1, 2024, to the date of this report, the trading price of our stock on the Nasdaq has ranged from a low of $1.27 to a high of $5.19.

In addition, stock markets in general have experienced extreme price and volume fluctuations, and the market prices of securities have been highly volatile. These fluctuations are often unrelated to operating performance and may adversely affect the market price of the Common Shares. As a result, you may be unable to sell any Common Shares you acquire at a desired price.

We have never paid dividends on the Common Shares.

We have not paid dividends on the Common Shares to date, and we may not be in a position to pay dividends for the foreseeable future. Our ability to pay dividends with respect to the Common Shares will depend on our ability to successfully develop one or more properties and generate earnings from operations. Further, our initial earnings, if any, will likely be retained to finance our operations. Any future dividends on Common Shares will depend upon our earnings, our then-existing financial requirements, and other factors, and will be at the discretion of our Board.

Future sales, or the perception of future sales, of Common Shares by existing shareholders or by us, or future dilutive issuances of Common Shares by us, could adversely affect prevailing market prices for the Common Shares and cause investors to suffer dilution in their net book value per Common Share.

Sales of a substantial number of Common Shares in the public market could occur at any time, including issuances and sales of additional Common Shares by us and sales by other security holders. These sales, or the market perception that the holders of a large number of Common Shares or securities convertible, exercisable, or exchangeable into Common Shares intend to sell Common Shares, could reduce the prevailing market price of the Common Shares. The effect, if any, that future public sales of these securities or the availability of these securities for sale will have on the market price of the Common Shares is uncertain. If the market price of the Common Shares were to drop as a result, this might impede our ability to raise additional capital and might cause remaining shareholders to lose all or part of their investment.

The Articles of NioCorp, as amended, permit us to issue an unlimited number of Common Shares. Subject to the requirements of the British Columbia Business Corporations Act and Nasdaq, we will not be required to obtain the approval of the NioCorp shareholders for the issuance of additional Common Shares. We have issued Common Shares in the past and will continue to issue Common Shares to finance our activities in the future. In addition, outstanding Options and Warrants and securities convertible into or exchangeable for Common Shares may be exercised, converted, or exchanged resulting in the issuance of additional Common Shares. If we issue additional Common Shares or decide to enter into joint ventures with other parties in order to raise financing through the sale of equity securities, investors’ interests in the Company will be diluted and investors may suffer dilution in their net book value per Common Share depending on the price at which such securities are sold.

Additionally, pursuant to the Yorkville Equity Facility Financing Agreement, Yorkville has committed to purchase up to an additional $46.9 million of our Common Shares, at our direction from time to time during the remaining seven months of the commitment period, subject to certain limitations and the satisfaction of the conditions in the Yorkville Equity Facility Financing Agreement. We have filed a registration statement under the Securities Act covering resales by Yorkville of the Common Shares issuable pursuant to the Yorkville Equity Facility Financing Agreement. Accordingly, any Common Shares that we issue pursuant to the Yorkville Equity Facility Financing Agreement will be available for sale into the public market, subject to applicable securities laws, which could reduce the prevailing market price for the Common Shares.

We are subject to the continued listing criteria of the Nasdaq and our failure to satisfy these criteria may result in delisting of the Common Shares.

Our Common Shares are currently listed on the Nasdaq Global Market under the symbol “NB”. The public NioCorp Assumed Warrants are currently listed on Nasdaq under the symbol “NIOBW.” The Nasdaq Capital Market has rules for continued listing. In order to maintain the listings, we must maintain certain financial and share distribution targets, including maintaining a minimum number of public shareholders.

If Nasdaq delists the Common Shares, investors may face material adverse consequences, including, but not limited to, a lack of a trading market for the Common Shares, reduced liquidity, a determination that our Common Shares are a “penny stock,” decreased analyst coverage of the Company, and an inability for us to obtain additional financing to fund our operations.

If our Common Shares are considered a penny stock and are subject to the penny stock rules, broker-dealers may be discouraged from effecting transactions in Common Shares.

Our Common Shares have in the past, and may in the future, be considered a “penny stock.” The SEC has adopted Rule 15g-9 which generally defines “penny stock” to be any equity security that has a market price (as defined) less than $5.00 per share or an exercise price of less than $5.00 per share, subject to certain exceptions. Applicable penny stock rules impose additional sales practice requirements on broker-dealers who sell to persons other than established customers and “accredited investors.” The term “accredited investor” refers generally to institutions with assets in excess of $5.0 million or individuals with a net worth in excess of $1.0 million or annual income exceeding $200,000 or $300,000, jointly with their spouse. The penny stock rules require a broker-dealer, prior to a transaction in a penny stock not otherwise exempt from the rules, to deliver a standardized risk disclosure document in a form prepared by the SEC, which provides information about penny stocks and the nature and level of risks in the penny stock market. The broker-dealer also must provide the customer with current bid and offer quotations for the penny stock, the compensation of the broker-dealer and its salesperson in the transaction, and monthly account statements showing the market value of each penny stock held in the customer’s account. The bid and offer quotations, and the broker-dealer and salesperson compensation information, must be given to the customer orally or in writing prior to effecting the transaction and must be given to the customer in writing before or with the customer’s confirmation. In addition, the penny stock rules require that prior to a transaction in a penny stock not otherwise exempt from these rules, the broker-dealer must make a special written determination that the penny stock is a suitable investment for the purchaser and receive the purchaser’s written agreement to the transaction. If and when applicable, these disclosure requirements may have the effect of reducing the level of trading activity in the secondary market for the Common Shares. Consequently, these penny stock rules may affect the ability of broker-dealers to trade in the Common Shares.

Cybersecurity

As filed, 2,234 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Cybersecurity risk management is integrated into the Company’s enterprise-wide risk management. Our Board has overall oversight responsibility for our risk management and management is responsible for identifying, considering, and assessing material risks to the Company. Our Chief Financial Officer is responsible for assessing and managing cybersecurity risks; however, as a smaller reporting company, we currently do not have a dedicated cybersecurity team. Our Chief Financial Officer reports to the Board regarding financial and operating risks, including cybersecurity risks. Our Chief Financial Officer has experience in managing public companies and assessing financial and operating risks.

Our cybersecurity risk management is designed to provide a framework for assessing, identifying, and managing material risks from cybersecurity threats and to respond to cybersecurity incidents, including material risks associated with the use of services provided by third-party service providers. We rely on the cybersecurity protections of many of our third-party service providers. Our primary third-party service providers utilize two-factor authentication as well as login and password protections with email verifications.

We are in the process of evaluating our cybersecurity needs and developing appropriate measures to enhance our cybersecurity posture. Our goal is to establish a cybersecurity framework that is commensurate with our size, complexity, and nature of our operations.

For the year ended June 30, 2025, the Company had no material cybersecurity incidents or threats that have materially affected or were reasonably likely to materially affect our business strategy, results of operations or financial condition. Despite our efforts, we cannot eliminate all risks from cybersecurity threats or provide assurances that we have not experienced an undetected cybersecurity incident. As previously disclosed, on February 14, 2025, we became aware of unauthorized third-party access to our information systems, including portions of its email systems, that resulted in misdirected vendor payments. To date, the Cybersecurity Incident has not had a material impact on our business operations or financial condition.

Properties

As filed, 61,433 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Elk Creek Project, Nebraska

Our principal mineral property is the Elk Creek Property, a niobium, scandium and titanium development stage property. The Elk Creek Project has established indicated and inferred resources along with probable reserves and the Company has completed a feasibility study for the project. The below information is in part summarized or extracted from our S-K 1300 Elk Creek Technical Report Summary, which was filed as Exhibit 96.1 to the Company’s Annual Report on Form 10-K for the fiscal year ended June 30, 2022, and is incorporated by reference into this Annual Report on Form 10-K. The Company does not have any other material properties.

The qualified persons responsible for the S-K 1300 Elk Creek Technical Report Summary are Dahrouge Geological Consulting USA Ltd.; Understood Mineral Resources Ltd.; Optimize Group; Tetra Tech; Adrian Brown Consultants Inc.; Metallurgy Concept Solutions; Magemi Mining Inc.; L3 Process Development; A2GC; Scott Honan, M.Sc, SME-RM, NioCorp; Dumas Contracting Ltd.; Mahmood Khwaja, P.E., CDM Smith; and Wynand Marx, M.Eng, BBE Consulting. A matrix of the sections for which each qualified person is responsible is included in the S-K 1300 Elk Creek Technical Report Summary, except that Dumas Contracting Ltd., as evidenced by its consent filed as Exhibit 23.14 to this Annual Report on Form 10-K has reviewed, approved, and taken responsibility for Sections 13.7.1, 13.7.2, 13.7.3, 13.7.4, 13.7.9, 13.7.10, 13.7.11, 13.7.12, 13.7.13, 13.7.14, 15.1.3, 15.1.4 and 23.1.8 of the S-K 1300 Elk Creek Technical Report Summary. Except for Scott Honan, none of the qualified persons is affiliated with the Company. Mr. Honan is the Chief Operating Officer of the Company. The disclosure of scientific or technical information in this Annual Report on Form 10-K was reviewed and approved by Mr. Honan who is a qualified person as defined in NI 43-101, and Mr. Honan has verified the data disclosed herein.

Property Description and Location

The Elk Creek Property is a carbonatite deposit located in Johnson County, southeast Nebraska, USA. The carbonatite contains elements of economic significance, including niobium, titanium, and scandium, as well as potential economic significance for rare earth products. The Elk Creek Property is situated as shown below and is located within the USGS Tecumseh Quadrangle Nebraska SE (7.5 minute series) mapsheet in Sections 1-6, 9-11; Township 3N; Range 11E and Sections 19-23, 25-36; Township 4N, Range 11E, at approximately 40°16’ north and 96°11’ west in the State of Nebraska, in central USA. The Elk Creek Property is approximately 45 miles southeast of Lincoln, Nebraska, the state capital of Nebraska.

Title and Ownership

Land in the project area is exclusively owned by private entities, and there is no federal or state land in the project area. The Company has secured its rights to the project area by purchasing land from private landowners or by entering into agreements with the landowners as described below.

The Company currently owns approximately 227 acres of land and associated mineral rights, and an additional 80 acres of surface rights and 40 acres of mineral rights, all within the carbonatite footprint. The Elk Creek Project’s mine infrastructure and a portion of the supporting operations is planned to be located on this land. Ownership of the mineral rights discussed above includes a 2% NSR royalty and grants us access to more than 90% of the Elk Creek Project’s mineral resources and mineral reserves.

As of June 30, 2025, the total book value of the Elk Creek Property and associated buildings and equipment was $16.9 million.

On August 1, 2025, ECRC closed on its option to purchase three parcels of land in the project area, consisting of the property known as Woltemath80S and approximately 1.66 acres of the property known as Woltemath002, for an aggregate purchase price of approximately $2.7 million, pursuant to the terms of two OTPs.

The Company currently holds six OTPs that are associated with the Elk Creek Project and one perpetual easement on a land parcel adjacent to the Missouri River. The current optioned land package covers an area of 1,272 acres and is reflective of the land needed to secure the remaining mineral resources and mineral reserves held under the OTPs along with the land needed for the development and operations of the Elk Creek Project for its proposed 38-year operating life.

In general, exercise of an OTP is accomplished by paying the greater of a fixed amount per acre or a multiple of the appraised value at the time of purchase. If the land is not purchased by the Company during the term of the OTP and the land in question is needed for the project, the Company intends to negotiate a new OTP with the landowner. The OTP is accompanied by a negotiated payment to the landowner that is paid upon execution of the OTP by the Company and the landowner. As of June 30, 2025, the Company was obligated to make payments totaling approximately $101,000 over the next 15 years to maintain our rights under these OTPs. Details on the current OTPs held by the Company are shown in the table below.

Active Lease Agreements (OTPs) Covering the Elk Creek Project as of September 2025

Agreement Identifier Acres Agreement Expiry
Woltemath002 375.15 04-Dec-29
Heidemann005 196.57 16-Mar-30
Nielsen001 249.32 25-Jun-30
Woltemath003J 220.00 25-Mar-30
Beethe007 163.75 20-Jan-31
Shuey001 80.00 27-May-40

The OTPs are between NioCorp’s subsidiary ECRC and the individual landowners. Land subject to the OTP agreements is currently used for agricultural purposes, including growing row crops (corn and soybeans) and pasturing livestock. The land owned by ECRC houses the Company’s drill core inventory and geological sample repository in two steel core shed buildings and the Company maintains a cover crop (sorghum and rye) on portions of the property that were formerly used for growing row crops. The former landowner maintains a residence and several outbuildings on the property subject to a life estate that accompanied the purchase of the property by the Company in fiscal year 2021.

The agreements that involve mineral rights include a 2% NSR royalty attached with the OTP. The OTPs grant the Company an exclusive right to explore and evaluate the property for the term thereof, with an option to purchase the surface rights or a combination of the mineral and surface rights at any time during the term. As the Woltemath80S agreement was limited to an option to purchase the surface rights only, it does not contain an NSR provision.

Land Tenure Map as of September 2025

The current estimated mineral resource and reserve is wholly contained within land owned by the Company and parcel Woltemath003J. The Company considers these two properties to be the only properties on which the Company’s development of the Elk Creek Project is substantially dependent.

As part of the OTPs, where required, the Company has also secured surface rights, which allow for access to the land for drilling activities and associated mineral exploration and project development work.

Accessibility, Physiography, Climate and Infrastructure

The Elk Creek Property is easily accessible year-round as it is situated approximately 45 miles southeast of Lincoln, Nebraska, the state capital, and approximately 68 miles south of Omaha, Nebraska. Access to the site can be completed via road or from one of the regional airports. There are several regular flights to both Lincoln and Omaha; however, the Elk Creek Property is most easily accessible from Lincoln. From Lincoln Municipal Airport, the Elk Creek Property is accessed via paved roads on the main network and a secondary network of gravel roads. The drive from the Lincoln Municipal Airport to the property is typically 1 hour and 15 minutes, and from Omaha’s Eppley Airport, the drive is approximately 1 hour and 45 minutes.

The Elk Creek Property is immediately adjacent to paved Nebraska state highway 50, and the mineral resource and mineral reserve are centered in Township 4N, Range 11E, Section 33. This section is immediately southwest of the junction of Nebraska state highways 50 and 62. Rail access is available in the town of Elk Creek, which is located 3 miles east of the project area. Water is available at the project site from a well, as well as from Elk Creek, which crosses Section 33. Water is also available from the Johnson County Rural Water system, which has distribution infrastructure on the north side of the Section 33 and from the Pawnee County Rural Water system, which has distribution infrastructure on the south side of Section 33. Electricity is provided at the Company’s Core Storage sheds located on the west side of Section 33 on land owned by the Company from the Omaha Public Power District (“OPPD”). Personnel are available from the local surrounding towns, including Elk Creek (3 miles east), Tecumseh (6 miles north), Steinauer (5 miles south), Pawnee City (10 miles south) and Syracuse (27 miles north). Due to the project’s location in Nebraska, there are no ports nearby.

Southeast Nebraska is situated in a humid continental climate (Dfa) on the Köppen climate classification system. In eastern Nebraska, this climate is generally characterized by hot humid summers and cold winters. Average winter temperatures vary between 13°F to 35°F. Average summer temperatures vary between 64°F to 90°F. Exploration, construction and operational activities may be conducted all year round.

Average monthly precipitation (rain and snowfall) varies between 0.9 and 5.0 inches. Average yearly precipitation is between 31 and 33 inches with an average yearly snowfall of approximately 28 inches. Nebraska is located within an area known for tornadoes which runs through the central U.S. where thunderstorms are common in the spring and summer months. Tornadoes primarily occur during the spring and summer and may occur into the autumn months.

There are several local communities near the Elk Creek Property, including Elk Creek and Tecumseh, that will provide local housing for the Elk Creek Project. There are a number of other communities within driving distance and the large cities of Lincoln and Omaha are within reasonable driving distance. Mining activities currently taking place in the area are limited to limestone and aggregate operations to support the local cement manufacturing and construction industries.

The Elk Creek Project is expected to incorporate surface and underground infrastructure, as well as tailings storage facilities. The offsite infrastructure is expected to include a new high voltage transmission line constructed by the local utility company and providing power to an on-site primary sub-station and a natural gas pipeline built by the owner of the interstate pipeline. Water used for all on-site process needs and activities will be supplied from mine dewatering activities, local groundwater wells and from a local water utility. See “2022 Elk Creek Feasibility Study” below for additional information regarding proposed infrastructure related to the Elk Creek Project.

The local topography of eastern Nebraska is relatively low-relief with shallow rolling hills intersected by shallow river valleys. Elevation varies from about 1,066 to 1,280 ft above sea level. Bedrock outcrop exposure is nonexistent in the Elk Creek Project area.

The majority of the area around the Elk Creek Project is used for cultivation of corn and soybeans, along with uses as grazing land. Native vegetation typical of eastern Nebraska is upland tall-grass, prairie and upland deciduous forests.

Geology and Mineralization

Geology

The Elk Creek Property includes a carbonatite that has intruded older Precambrian granitic and low- to medium-grade metamorphic basement rocks. The carbonatite is an elliptical magmatic body with a northwest-trending long axis perpendicular to the strike of the Midcontinent Rift System, near the northern part of the Nemaha uplift. The carbonatite consists predominantly of dolomite, calcite and ankerite, with lesser chlorite, barite, phlogopite, pyrochlore, serpentine, fluorite, sulfides, bastnasite, monazite, and quartz. It is, however, believed from stratigraphic reconstruction based on drill core observation in the area that the carbonatite is unconformably overlain by approximately 200 m of essentially flat-lying Palaeozoic marine sedimentary rocks, including carbonates, sandstones and shales of Pennsylvanian age.

Mineralization

The property hosts niobium, titanium, and scandium mineralization as well as REE mineralization that occurs within the Elk Creek carbonatite. The current known extents of the carbonatite unit are approximately 950 m along strike, 300 m wide, and 750 m in dip extent, below the unconformity. Niobium, titanium, scandium, and rare earths are considered the main elements of interest.

The deposit contains significant concentrations of niobium. Based on the metallurgical testwork completed to date at a number of laboratories using QEMSCAN® analysis, the niobium mineralization is known to be fine grained, and that 77% of the niobium occurs in the mineral pyrochlore, while the balance occurs in an iron-titanium-niobium oxide mineral of varying composition.

Within the Elk Creek carbonatite, a host of other elements exist with varying degrees of concentration. The Company has completed both whole rock analysis and multi-element analysis on all samples for the 2014 drilling program, described below, plus resampling of selected historical core/pulps between 2011 and 2014.

Historical Exploration

Drilling at the Elk Creek Property was conducted in three phases. The first was during the 1970’s and 1980’s by the Molybdenum Company of America (“Molycorp”), the second in 2011 by Quantum Rare Earth Developments Corp (“Quantum” - NioCorp under its former name), and the third and latest program from 2014 to 2016 by NioCorp. To date, 129 diamond core holes have been completed for a total of 64,981 m over the entire geological complex. Of these, a total of 48 holes (33,909 m) have been completed to date in the mineralized area and are used in the current mineral resource and reserve estimates. Five additional holes, with a total length of 3,353.1 m, were drilled for hydrogeologic and geotechnical purposes in 2015. No sampling has been completed of these five holes to date and therefore they have not been considered for the mineral resource or reserve estimates.

All drilling has been completed using a combination of Tricone, Reverse Circulation (“RC”) or Diamond Drilling (“DDH”) in the upper portion of the hole within the Pennsylvanian sediments. All drilling within the underlying carbonatite has been completed using DDH methods.

Summary of Drilling Database within Elk Creek Deposit Area

Year Company Number of Holes Average Depth (m) Sum Length (m)
1973-1986 Molycorp 27 596.6 16,108.2
2011 Quantum 3 772.6 2,317.7
2014 to present NioCorp 18 845.4 15,482.8
Total 48 700.9 33,908.7

29

Molycorp, 1973-1986

Between 1973 and 1974, Molycorp completed six drillholes: EC-1 to EC-4, targeting the Elk Creek anomaly, and two other holes outside the Elk Creek anomaly area. Drillholes were typically carried out by RC drilling through the overlying sedimentary rocks and diamond drilling through the Ordovician-Cambrian basement rocks.

Molycorp continued their drill program from 1977 and, in May 1978, Molycorp made its discovery of the current mineral resource with drillhole EC-11. EC-11 is located on Section 33, Township 4N, and Range 11. The carbonatite hosting the Elk Creek Project was intersected at a vertical depth of 203.61 m (668 ft).

Molycorp continued its drilling program through to 1984, which mainly centered on the Elk Creek Project within a radius of roughly 2 km. By 1984, Molycorp had completed 57 drillholes within the Elk Creek gravity anomaly area, which included 25 drillholes over the Elk Creek Project area.

From 1984 to 1986, drilling was focused on the Elk Creek gravity anomaly area. The anomaly area is roughly 7 km in diameter and drilling was conducted on a grid pattern of approximately 610 m by 610 m (roughly 2,000 ft by 2,000 ft) with some closer spaced drillholes in selected areas.

By 1986, a total of 106 regional drillholes were completed for a total of approximately 46,797 m (153,532 ft). The deepest hole reached a depth of 1,038 m (3,406 ft) and bottomed in carbonatite.

Quantum, 2011

In April 2011, Quantum conducted a preliminary drill program (three holes) on the Elk Creek deposit and two REE exploration targets (two holes), which have been excluded from the current mineral resource and reserve estimation, as they do not intersect the Nb2O5 anomaly and are located to the east. The objectives of the drill program over the Elk Creek Property were to verify the presence of higher-grade niobium mineralization at depth, and to infill drill the known niobium deposit in order to upgrade the resource category of the previous resource estimate and expand the known resource. The drill program was also established to collect sufficient sample material for metallurgical characterization and process development studies of the niobium mineralization.

The 2011 program consisted of five inclined drillholes, totaling 3,420 m of NQ size diameter core. Inclusive of this total, three drillholes, totaling 2,318 m, were drilled into the known Elk Creek deposit.

NioCorp, 2014 to Present

NioCorp commenced drilling on the Elk Creek Property using a three-phased program. The three-phased program was originally based on 14 drillholes for approximately 12,150 m (announced in a press release on April 29, 2014), but was subsequently expanded during the program to 18 drillholes for approximately 15,482 m. Three of the 18 drillholes were drilled for the purpose of metallurgical characterization and process development studies. Two of these drillholes, NEC14-MET-01 and NEC14-MET-02, were not assayed, while NEC14-MET-03 was quarter cored with one quarter being assayed and the remainder used for metallurgical testwork. The drilling has been orientated to intersect the geological model from the southwest and northeast (perpendicular to the strike), with the exception of NEC14-011 and NEC14-012, which were oriented southeast and northwest, respectively.

During fiscal year 2022, NioCorp collected a total of 1,095 samples originating from 18 diamond drill holes completed by MolyCorp, as discussed above. These samples were collected, and subsequently assayed, in order to fill in gaps in our records regarding REE grades and tonnage that may exist in the deposit. Assaying was conducted at Actlabs in Ancaster, Ontario. The assay results were subjected to a Quality Assurance and Quality Control (“QA/QC”) program consistent with industry best practices.

Internal Controls

NioCorp integrated a series of routine QA/QC procedures throughout the sampling and analysis portion of the drilling programs to ensure the highest level of quality was maintained throughout the process leading to the estimate of mineral reserves and mineral resources for the Elk Creek Project. This included the insertion of duplicate samples taken from various stages of the process, insertion of known control samples (standard reference materials, certified reference materials (“CRM”), and blanks) and sending third-party pulps to a secondary lab (SGS Canada Inc.).

Sample tickets were assigned initially at the core shed using barcodes with duplicate tickets placed inside and on the outside of the bag. Sample identification was confirmed using barcode labelling and visual sample type comparisons before sample shipment. The use of barcoded samples ensured both shipment forms and analytical labs used accurate information. Multiple types of QC samples were inserted at this stage of the process, which includes the following:

  • Field quartz blanks (1 in 20, or 5%) were inserted within or immediately after samples collected from mineralized intervals, targeting zones of elevated visual mineralization, where possible.
  • CRMs (1 in 20, or 5%) were inserted in the field with the sample sequence.
  • Field quarter-core duplicates (1 in 20, or 5%) were inserted to test mineralization and sampling variability.

Additional details on the QA/QC program can be found in Section 8 of the S-K 1300 Elk Creek Technical Report Summary.

Mineral deposits, including the Elk Creek deposit, are inherently uncertain because of variability at all scales and sparse sampling. In addition to uncertainty associated with estimation, there are specific risks and sources of uncertainty associated with the Elk Creek deposit. See Item 1A., Risk Factors.

S-K 1300 and other similarly purposed International Codes (JORC, 2012; NI 43-101, 2014) are designed to require disclosure to the public of risks relating to mineral resource and reserve estimation as identified and evaluated by a qualified person. The qualified persons responsible for the S-K 1300 Elk Creek Technical Report Summary address the technical risks in various sections and consider that no material technical risks are identified. Additional descriptions of the risks and uncertainty associated with reported mineral reserves and resources can be found in Section 11 of the S-K 1300 Elk Creek Technical Report Summary.

2022 Elk Creek Feasibility Study

During fiscal year 2022, the Company launched geological, metallurgical, engineering, and other analyses to assess the feasibility of adding REE production to its plans once sufficient work has been completed. The Company and its consultants were required to complete additional assays of historical drill core to fill data gaps in the existing resource database to establish an REE mineral resource. The mine plan was also updated and the S-K 1300 Elk Creek Technical Report Summary was filed with the SEC as an exhibit to the Company’s Annual Report on Form 10-K for the fiscal year ended June 30, 2022. The S-K 1300 Elk Creek Technical Report Summary was based on the economic and process results of the feasibility study conducted by the qualified persons, which were also presented in the 2022 NI 43-101 Elk Creek Technical Report.

The Elk Creek Project is planned as an underground mining operation using a long-hole stoping mining method and paste backfill, operating with a processing rate of 2,764 tonnes per day. Expected total production over the 38-year mine life includes 171,140 tonnes of payable niobium, 3,676 tonnes of Sc2O3, and 431,793 tonnes of TiO2. Estimated up-front direct capital costs are $760 million, in addition to indirect costs of $187 million, pre-production capital costs of $92 million, an overall contingency of $102 million, and pre-production net revenue credit of $257 million.

Financial Analysis Included in the 2022 Elk Creek Feasibility Study

The metrics reported in the S-K 1300 Elk Creek Technical Report Summary are based on the cash flow model results. The metrics are on both a pre-tax and after-tax basis, on a 100% equity basis with no Elk Creek Project financing inputs and are in first quarter 2019 U.S. constant dollars. Foreign exchange impacts were deemed negligible as most, if not all, costs and revenues are denominated in U.S. dollars. Key criteria used in the analysis are discussed in detail throughout this section.

Principal Project Assumptions Included in the 2022 Elk Creek Feasibility Study

Description Pre-Production Period Process Plant Life Value 4 years 38 years
Mine Operating Days per Year 365
Mill Operating Days per Year 365
Discount Rate, End of Period @ 8%
Commercial Production Year 2025

Summary of Key Evaluation Metrics Included in the 2022 Elk Creek Feasibility Study

Description Value
Ore Mined (kt) 36,655
Ore Mining Rate (t/d) 2,764
Niobium Grade 0.81%
Scandium Grade (parts per million, “ppm”) 70.2
TiO2 Grade 2.92%
Contained Nb2O5 (kt) 297
Contained Sc (t) 2,573
Contained TiO2 (kt) 1,071
Total Ore Processed (kt) 36,655
Processing Rate (kt/y) 1,009
Average Recovery, Nb2O5 82.4%
Average Recovery Sc 93.1%
Average Recovery TiO2 40.3%
Recovered Nb2O5 (kt) 245
Recovered Sc (t) 2,395
Recovered TiO2 (kt) 432
Realized Market Prices
Nb ($/kg) $46.55
TiO2 ($/kg) $0.99
Sc2O3 ($/kg) $3,674
Payable Metal
Nb (t) 171,140
Sc2O3 (t) 3,676
TiO2 (t) 431,793

32

Summary Projected Economic Results Included in the 2022 Elk Creek Feasibility Study

Description Value ($000)
Total Gross Revenue $21,899,726
Operating Costs:
Mining Cost (1,553,325)
Process Cost (3,911,116)
Site G&A Cost (300,400)
Concentrate Freight Cost (10,472)
Other Infrastructure Costs (200,407)
Water Management Cost (609,195)
Tailings Management Cost (73,822)
Property Tax (217,540)
Royalties (300,503)
Annual Bond Premium (5,500)
Total Operating Costs (7,182,280)
Operating Margin (EBITDA(1)) 14,717,445
Effective Tax Rate 16.42%
Total Taxes (2,246,186)
Working Capital -
Operating Cash Flow $12,471,258

Totals may not sum due to rounding.

(1) The term “EBITDA” refers to earnings before interest, taxes depreciation and amortization. See “Non-GAAP Financial Performance Measures” below for a discussion of the use of non-GAAP financial measures.

Capital Cost Estimates Included in the 2022 Elk Creek Feasibility Study

The following table shows the breakout in LoM initial capital and sustaining capital cost estimates (excluding closure and reclamation of $44 million), which total $1,562 million. This includes a total initial capital cost of $1,141 million, including a 10% contingency.

Description Initial Sustaining Total
Capitalized Preproduction Expenses $ 77 $ - $ 77
Site Preparation and Infrastructure 41 15 56
Processing Plant 367 96 464
Water Management and Treatment 74 24 97
Mining Infrastructure 257 198 455
Tailings Management 21 79 100
Site Wide Indirects 7 - 7
Processing Indirects 96 - 96
Mining Indirects 41 - 41
Commissioning 15 - 15
Owner’s Costs 34 - 34
Mine Water Management Indirects 9 - 9
Contingency 102 9 111
Total Capital Costs $1,141 $422 $1,562

Totals may not sum due to rounding.

Operating Cost Estimates Included in the 2022 Elk Creek Feasibility Study

The following LoM unit operating costs include the pre-production and first/last years of production.

Description LoM $/t ore
Mining Cost $42.38
Process Cost 106.70
Water Management Cost 16.62
Site G&A Cost 8.20
Other Infrastructure 5.47
Tailings Management Cost 2.01
Other Expenses 6.22
Subtotal 187.59
Royalties/Annual Bond Premium 8.35
Total LoM Operating Costs $195.94

Totals may not sum due to rounding.

Planned Mining Operations

The Elk Creek Project is planned as an underground mining operation using a long-hole stoping mining method and paste backfill, with shaft access to minimize development through water bearing horizons. The mine will utilize jumbo drills for lateral development and tophammer and down-the-hole drills for vertical development and production stoping. Rock bolters will be used for ground support and probe holes will be used to support mine grouting where required. Ore will be remotely mucked from the bottom stope accesses using 14 tonne Load-Haul-Dump units (“LHD”). The LHDs will transport the ore to an ore pass directly or to remuck bays to maximize the efficiency of the stope mucking operations. When needed, a second LHD and a fleet of 40 tonne haul trucks will be used to transport ore from the remuck bays to the grizzly feeding the underground material handling system. Multiple remuck bays are used on each level to avoid interference between the LHD and the haul trucks. The ore is fed through the grizzlys with rock breakers into an underground crusher (the “Primary Crusher”) and via a material handling system to the surface.

Planned Processing Operations

Planned ore process operations include mineral processing, hydrometallurgical processing (“Hydromet”), and pyrometallurgical processing (“Pyromet”) housed in separate buildings.

The mineral processing building will house all of its equipment within a single large building. Ore from the Primary Crusher (located in the underground mine) will be fed to the secondary cone crusher system, operating in closed circuit with a double deck screen. The screen undersize from the cone crusher system will be fed to a high-pressure grinding roll unit (“HPGR”), operating in closed circuit with another double deck screen. The HPGR screen undersize is the comminution product that will report to the Hydromet process.

The Hydromet plant building will be a multi-level engineered steel structure, which will house equipment on two levels. Ore from mineral processing will be fed through 15 individual processes required to separate the three recoverable products. The purpose of the Hydromet processing steps is to leach the pay metals into solution using two separate acid leaches (Hydrochloric Acid Leach and Sulfuric Acid Bake), remove impurities, separate the three pay metals, and perform precipitation/processing to final solid oxide forms. Outputs from the Hydromet process include saleable TiO2 and Sc2O3, with Nb2O5 reporting to the Pyromet plant for final processing. The Hydromet plant will be supported by a Hydrochloric Acid Regeneration plant and a Sulfuric Acid Plant.

The Pyromet building will house most of its equipment within a single building. The purpose of the Pyromet plant is to reduce the Nb2O5 coming from the Hydromet plant by converting it into a saleable FeNb metal. Aluminum shots and iron oxide pellets will be introduced to an electric arc furnace on a continuous basis along with fluxing agents and Nb2O5 to produce a saleable ferroniobium metal.

Proposed Production Plan and Schedule

Based on the 2022 Elk Creek Feasibility Study, the operating mine life is approximately 38 years with a nominal processing rate of 2,764 tonnes per day. The Elk Creek Project timeline is based on 39 months to mechanical completion after Authorization to Proceed, plus an additional six months of commissioning and ramp-up to 100% of production capacity for a total of 45 months and assumes no financing constraints. The Board must approve a construction program and budget before construction of the Elk Creek Project can begin. This approval, along with the receipt of all required governmental permits and approvals and the completion of project financings, will determine whether and when construction of the Elk Creek Project can begin.

Proposed Tailings Storage

The tailings produced by the process plant will consist of filtered water leach residue, calcined excess oxide, and slag. Four engineered and lined tailings storage facilities (“TSFs”) will be constructed sequentially to contain the tailings over the life of the Elk Creek Project and would contain approximately 14.5 million tonnes of tailings. The tailings facilities have been designed to incorporate two independent areas: a composite-lined tailings solids storage area; and an area with double lined containment, including a leak collection and recovery system for management of stormwater runoff and drainage from the tailings solids. The TSFs will store predominantly dry (i.e., not in a slurry consistency) tailings from the plant with embankment construction based on a “downstream” construction method. Facility closure is considered in the design.

Proposed Salt Management

The crystalline salt produced as a waste product of heating and evaporating brine from the reverse osmosis (“RO”) water treatment plant will be transported by conveyor to the temporary salt staging area and then be transported by truck to the dedicated salt management cells (“SMC”). Two SMCs will be constructed sequentially to contain the salt over the life of the project and would contain approximately 1.63 million cubic meters of salt. The SMCs design will incorporate a composite-lined storage area with double-lined containment including a leak collection and recovery system for management of stormwater runoff and drainage.

Proposed Water Management

For the first several years of construction, the advancement of the shaft and underground workings will require limited dewatering, anticipated to be through lower-level sumping and pumping for surface collection and disposal. Initially, water will be stored in the lined SMC #1 during construction or will be trucked off-site for treatment at a local publicly owned treatment works. Excess water in the SMCs will be spray evaporated within the footprint of the SMC, to avoid the reintroduction of soluble salts into the water treatment system. Temporary on-site storage or off-site shipment and disposal of the crystallizer solid waste may be necessary until construction of SMC #1 is completed.

Once full operations commence, we anticipate a shortfall of approximately 3,700 gallons per minute of operational and processing water, as the underground mine dewatering is only expected to produce 1,000 gallons per minute. To make up this shortfall, we would purchase fresh water from a local utility and from local landowners.

Once tailings begin being deposited in the TSF, internal contact water (from residual moisture in the tailings and precipitation falling within the impoundment footprint) will need to be actively managed. This water will be collected and treated using lime softening to precipitate hydroxide and carbonate solid forms for many of the inorganic constituents. The treated water will be filtered to remove the solids (which will be returned to the TSF for disposal), and the clean water will be pumped to the process plant RO system for further treatment. The clean water from the process plant RO unit will be used in the process plant, and the reject concentrate will be crystallized and deposited into the SMCs.

Proposed Source of Power

The local power utility (Omaha Public Power District) will provide power from nearby transmission lines to the site. This will require that an approximate 18-mile transmission line be installed by the utility to provide the site sub-station with the required site power demand. The local power utility will also design and install the main substation that will be owned and maintained by the utility. This infrastructure will be paid back through rate charges on the electrical usage.

Proposed Source of Natural Gas

Natural gas, to be used throughout the Elk Creek Project during the construction and operation phases of the project, will be brought to the site via pipeline from the local utility company. NioCorp has a natural gas transportation contract with Tallgrass Energy, which operates the Rockies Express (“REX”) pipeline. Tallgrass will construct a 45 kilometer (28 mile) gas pipeline lateral from the main REX pipeline system in Kansas to the project site. The lateral will be sized to provide a minimum of 27.5 dekatherms of gas per day. Natural gas will be distributed to all on-site facilities utilizing buried high-density polyethylene natural gas distribution pipe. Natural gas piping above ground and located inside of facilities will consist predominately of carbon steel pipe. Maximum on-site pipeline distribution pressure will be 100 pounds per square inch gauge. Natural gas will be used for facility heating, water heating, and for gas-fired process equipment.

Markets

Market studies for niobium, TiO2, and Sc2O3 are an important part of the proposed Elk Creek operation. These commodities, especially niobium and Sc2O3, are thinly traded without an established publicly available price discovery mechanism. Hence, detailed third-party market studies provide the basis for assumptions used in the economic analysis.

The economic analysis in the 2022 Elk Creek Feasibility Study used the 2019 U.S. dollar base price of $47/kg Nb as the forward-looking price for steel grade (65%) ferroniobium based on published independent third-party reports. The base price is adjusted to a realized price to account for the discount provisions contained in the two ferroniobium offtake agreements that the Company has concluded.

NioCorp engaged OnG Commodities LLC (“OnG”) to produce a market assessment in April 2017. The study examines current scandium production trends (approximately 20 tons/year) from existing and emerging producers plus an outlook for supply to 2028. The outlook then reviewed the current and emerging applications for scandium, including fuel cells, aerospace, industrial and other uses, plus an outlook for demand to 2028. Based on these inputs, OnG provided pricing forecasts and global demand volumes by year to 2028 based estimated production costs and supply-demand balances. The pricing for the OnG Commodities report was updated for NioCorp in 2019.

No formal market study was done for TiO2 as it only represents 2% of overall revenue in the economic analysis. All market information for titanium and TiO2 is derived from USGS Commodity Market Summaries (Bedinger, 2019).

Taxation Rates Included in the 2022 Elk Creek Feasibility Study

Taxes that may be levied on the Elk Creek Project include corporate income tax rates of 21% for federal and 5.84% for Nebraska. The Elk Creek Project is eligible for federal depletion allowances and credits, as well as various state incentives. The calculated effective income tax rate for the Elk Creek Project is 16.42% for the 2022 Feasibility Study.

Design Considerations for Environmental Performance

The current mine design incorporates the following strategies and technologies designed to minimize environmental impacts of operation:

  • Zero Process Liquid Discharge: The Elk Creek facility will now operate as a “Zero Process Liquid Discharge” facility, with no releases of process liquids. Instead, both naturally occurring, brackish (slightly salty) water produced during mining operations, and water used in ore processing, will be treated on site for use in operations. A solid salt will be produced from water treatment operations which will be stored on site.
  • Additional Protection of Groundwater Resources Through Artificial Ground Freezing: The Elk Creek Project’s new mine design will utilize artificial ground freezing as part of the process of sinking the production and ventilation shafts. Artificial ground freezing creates a temporary frozen barrier that helps to protect groundwater resources in the area while shaft-sinking operations are underway.
  • Avoidance of Permanent Impacts to Federally Jurisdictional Waters: We designed the layout of the Elk Creek Project to minimize or avoid permanent impacts to any federally jurisdictional waters and/or wetlands on the

property. This reduced the expected environmental impacts and allowed the Elk Creek Project to secure a Clean Water Act Section 404 permit from the USACE under the Nationwide Permit Program, a much more efficient and less expensive process than an individual Section 404 permit. No other NEPA-level federal permits are now expected to be required for the Elk Creek Project.

  • Recycling of Reagents Used in Mineral Processing: Metallurgical and process advances made in 2016 and 2017 are expected to help reduce the volume of material planned for disposal in the Elk Creek Project’s tailings storage areas. As more of this material is recycled, the environmental footprint of the Elk Creek Project is reduced.
  • Utilizing Tailings as Underground Mine Backfill: We plan to fill underground voids concurrently with mining operations using a paste backfill material that contains mine waste material that typically would be stored in above-ground tailings storage areas.

The Company has not identified any significant encumbrances to the property it owns or holds under OTP agreements. The Company has not had any permit violations or fines since the filing of our Annual Report on Form 10-K for the fiscal year ended June 30, 2024.

Permitting requirements for the project have been identified. The Company holds an Air Construction Permit from the State of Nebraska and a Special Use Permit from Johnson County, both of which are necessary to allow the start of project construction. In addition, the Elk Creek Project will be required to obtain a series of permits for operations from federal, state, and local agencies. The majority of these permits are ministerial in nature and present minimal risk to the Company and typically involve the completion of an application and the payment of a nominal fee. Three permits from the state of Nebraska are discretionary in nature, where an application and fee are provided to the state and the state must make a decision as to whether or not the permit will be granted. While the risk involved in such permits is low, such discretionary permits require more processing time by the state and do require the state agency to make a decision in favor of issuance of the permit. These three permits include the following:

  • Solid Waste Permit;
  • Air Operating Permit; and
  • Radioactive Materials License.

The cost and schedule for obtaining both the discretionary and ministerial permits is included in the overall execution plan for the Elk Creek Project. Additional details on the project’s permitting requirements can be found in Section 17 of the S-K 1300 Elk Creek Technical Report Summary.

Mineral Reserves and Resources

The mineral reserves and mineral resources disclosed below are based on the S-K 1300 Elk Creek Technical Report Summary, which was originally filed as Exhibit 96.1 to the Company’s Annual Report on Form 10-K for the fiscal year ended June 30, 2022. Mineral reserves and mineral resources at the Elk Creek Project as of June 30, 2025, are summarized in the tables below. Further discussion and background regarding the approaches used to establish mineral reserves and mineral resources is contained in Chapters 11 and 12 of the S-K 1300 Elk Creek Technical Report Summary.

Elk Creek Project In Situ Mineral Resource Estimate (niobium, titanium, and scandium) Excluding Reserves

as of June 30, 2025

Class NSR Cutoff Tonnage (Mt)
Indicated $180 151.7 Nb2O5 (%) Nb2O5 (kt)
0.43 649.8
TiO2 (%) TiO2 (kt)
2.02 3,067
Sc (ppm) Sc (t)
56.42 8,558
Inferred $180 108.3 Nb2O5 (%) Nb2O5 (kt)
0.39 426.6
TiO2 (%) TiO2 (kt)
1.92 2,082
Sc (ppm) Sc (t)
52.28 5,660

Elk Creek Project In Situ Mineral Resource Estimate (rare earth oxides) Excluding Reserves

as of June 30, 2025

Class NSR Cut-off Tonnage (Mt)
Indicated $180 151.7 La2O3 (%) La2O3 (kt) Ce2O3 (%) Ce2O3 (kt) Pr2O3 (%) Pr2O3 (kt)
0.0766 116.2 0.1320 200.2 0.0140 21.3
Nd2O3 (%) Nd2O3 (kt) Sm2O3 (%) Sm2O3 (kt) Eu2O3 (%) Eu2O3 (kt)
0.0511 77.5 0.0116 17.6 0.0040 6.0
Gd2O3 (%) Gd2O3 (kt) Tb2O3 (%) Tb2O3 (kt) Dy2O3 (%) Dy2O3 (kt)
0.0096 14.6 0.0011 1.6 0.0044 6.7
Ho2O3 (%) Ho2O3 (kt) Er2O3 (%) Er2O3 (kt) Tm2O3(%) Tm2O3 (kt)
0.0006 1.0 0.0015 2.2 0.0002 0.3
Yb2O3 (%) Yb2O3 (kt) Lu2O3 (%) Lu2O3 (kt) Y2O3 (%) Y2O3 (kt)
0.0010 1.5 0.0001 0.2 0.0187 28.4
LREO (%) LREO (kt) HREO (%) HREO (kt) TREO (%) TREO (kt)
0.2737 415.2 0.0528 80.0 0.3265 495.2
Inferred $180 108.3 La2O3 (%) La2O3 (kt) Ce2O3 (%) Ce2O3 (kt) Pr2O3 (%) Pr2O3 (kt)
0.0943 102.1 0.1576 170.6 0.0163 17.7
Nd2O3 (%) Nd2O3 (kt) Sm2O3 (%) Sm2O3 (kt) Eu2O3 (%) Eu2O3 (kt)
0.0575 62.2 0.0116 12.6 0.0038 4.1
Gd2O3 (%) Gd2O3 (kt) Tb2O3 (%) Tb2O3 (kt) Dy2O3 (%) Dy2O3 (kt)
0.0090 9.8 0.0010 1.1 0.0042 4.6
Ho2O3 (%) Ho2O3 (kt) Er2O3 (%) Er2O3 (kt) Tm2O3(%) Tm2O3 (kt)
0.0006 0.7 0.0014 1.5 0.0002 0.2
Yb2O3 (%) Yb2O3 (kt) Lu2O3 (%) Lu2O3 (kt) Y2O3 (%) Y2O3 (kt)
0.0010 1.1 0.0001 0.1 0.0182 19.7
LREO (%) LREO (kt) HREO (%) HREO (kt) TREO (%) TREO (kt)
0.3257 352.6 0.0512 55.5 0.3769 408.1

Notes:

a. Classification of mineral resources in the above tables is in accordance with the S-K 1300 classification system. Mineral resources in this table are reported exclusive of mineral reserves.

b. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

c. The mineral resources are reported at a Diluted Net Smelter Return (NSR) Cut-off of $180/tonne.

d. The diluted NSR is defined as:

  • The diluted revenue from Nb2O5, TiO2, and Sc per block used the following factors:
  • Nb2O5 Revenue: a 94% grade recovery, a 0.696 factor to convert Nb2O5 to Nb, 82.36% assumption for plant recovery, and a $39.60 selling price per kg of ferroniobium as of June 30, 2022.
  • TiO2 Revenue: a 94% grade recovery, a 40.31% assumption for plant recovery, and an $0.88 kg selling price per kg of titanium oxide as of June 30, 2022.
  • Sc Revenue: a 94% grade recovery, a 1.534 factor to convert Sc to Sc2O3, 93.14% assumption for plant recovery, and a $3,675 selling price per kg of scandium oxide as of June 30, 2022.
  • The diluted tonnes are a 6% increase in the total tonnes of the block.

e. Price assumptions for FeNb, Sc2O3, and TiO2 as shown in note d, above, are based upon independent market analyses for each product.

f. Numbers may not sum due to rounding. The rounding is not considered to be material.

g. Rare Earth Oxides (REO) were evaluated as a potential by-product to the mining of niobium, titanium, and scandium; thus, the estimated values of the REOs are reported using the previously determined diluted NSR as derived from the Nb2O5, TiO2, and Sc mineral resources and are assigned a price of $0.

h. The stated Light Rare Earth Oxides (LREO) grade (%) is the summation of La2O3 (%), Ce2O3 (%), Pr2O3 (%), and Nd2O3 (%) estimates.

i. The stated Heavy Rare Earth Oxides (HREO) grade (%) is the summation of Sm2O3 (%), Eu2O3 (%), Gd2O3 (%), Tb2O3 (%), Dy2O3 (%), Ho2O3 (%), Er2O3 (%), Tm2O3 (%), Yb2O3 (%), Lu2O3 (%), and Y2O3 (%) estimates.

j. The stated Total Rare Earth Oxide (TREO) grade (%) is the summation of LREO (%) and HREO (%).

k. The effective date of the mineral resource, including by-products, is June 30, 2025.

Elk Creek Project Underground In Situ Mineral Reserves Estimate for Elk Creek

as of June 30, 2025

Classification Tonnage (kt) Nb2O5 Grade (%) Contained Nb2O5 (t) Payable Nb (t) TiO2 Grade (%) Contained TiO2 (t) Payable TiO2 (t) Sc Grade (ppm) Contained Sc (t) Payable Sc2O3 (t)
Proven - - - - - - - - - -
Probable 36,656 0.81 297,278 170,409 2.92 1,071,182 431,793 70.2 2,573 3,677
Total 36,656 0.81 297,278 170,409 2.92 1,071,182 431,793 70.2 2,573 3,677

All figures are rounded to reflect the relative accuracy of the estimates. Totals may not sum due to rounding.

  • The qualified person for the mineral reserve estimate is Optimize Group Inc. The estimate has an effective date of June 30, 2025.
  • The mineral reserve is based on the mine design, mine plan, and cash-flow model utilizing an average cut-off grade of 0.679% Nb2O5 with an NSR of $180/mt.
  • The estimate of mineral reserves may be materially affected by metal prices, environmental, permitting, legal, title, taxation, socio-political, marketing, infrastructure development, or other relevant issues.
  • The economic assumptions used to define mineral reserve cut-off grade are as follows:
  • Annual life of mine (LoM) production rate of ~7,450 tonnes of FeNb/annum during the years of full production.
  • Initial elevated five-year production rate ~ 7,500 tonnes of FeNb/annum when full production is reached.
  • Mining dilution of ~6% was applied to all stopes and development, based on 3% for the primary stopes, 9% for the secondary stopes, and 5% for ore development.
  • Mining recoveries of 95% were applied in longhole stopes and 62.5% in sill pillar stopes.
Parameter Value Unit
Mining Cost 42.38 $/t mined
Processing 106.70 $/t mined
Water Management and Infrastructure 16.62 $/t mined
Tailings Management 2.01 $/t mined
Other Infrastructure 5.47 $/t mined
General and Administrative 8.91 $/t mined
Royalties/Annual Bond Premium 8.34 $/t mined
Other Costs 6.29 $/t mined
Total Cost 196.72 $/t mined
Nb2O5 to Niobium Conversion 69.60%
Niobium Process Recovery 82.36%
Niobium Price 39.60 $/kg
TiO2 Process Recovery 40.31%
TiO2 Price 0.88 $/kg
Sc Process Recovery 93.14%
Sc to Sc2O3 Conversion 153.40%
Sc Price 3,675.00 $/kg
  • Price assumptions are as follows: FeNb $39.60/kg Nb, Sc2O3 $3,675/kg, and TiO2 $0.88/kg. Price assumptions are based upon independent market analyses for each product as of June 30, 2022.
  • Price and cost assumptions are based on the pricing of products at the “mine-gate,” with no additional down-stream costs required. The assumed products are ferroniobium (metallic alloy shots consisting of 65%Nb and 35% Fe), a titanium dioxide product in powder form, and scandium trioxide in powder form.
  • The mineral reserve has an average LoM NSR of $563.06/tonne.
  • Optimize Group has provided detailed estimates of the expected costs based on the knowledge of the style of mining (underground) and potential processing methods (by third-party qualified persons).
  • Mineral reserve effective date is June 30, 2025. The financial model was run after the estimate of the NSR above, which reflects a total cost per tonne of $196.72 versus $189.91. This is not considered a material change.
  • Price variances for commodities are based on independent market studies versus earlier projected pricing. The independent market studies do not have a negative effect on the reserve.

Comparison of Mineral Resources and Mineral Reserves

There were no changes in the Elk Creek Project mineral resource or reserve estimates as of June 30, 2025, as compared to the Elk Creek Project mineral resource and reserve estimates as of June 30, 2024.

Environmental and Social

A number of key permits and environmental management requirements have been identified for the Elk Creek Project, some of which need to be implemented as soon as practicable in order to maintain the proposed Elk Creek Project schedule.

  • While not necessarily complex, the timing generally required to complete permitting through any federal regulatory agency requires that NioCorp engage key agencies (in this case the USACE and possibly the EPA) early on in Elk Creek Project development and consider the siting and orientation of facilities carefully to minimize the risk of a protracted National Environmental Policy Act analysis of the Elk Creek Project. At the present time, the Company believes that we have completed the major federal permitting actions needed for project construction, although changes to the design or location of project facilities may require that additional federal permits be obtained.
  • Construction at the facility requires an Air Permit from the State of Nebraska, which was issued to the Company on June 2, 2020. The Air Permit describes all the prospective air emissions from the facility and required the completion of an air quality model that demonstrates compliance with the NAAQS. On April 15, 2022, the Company announced that the Nebraska Department of Environment and Energy advised the Company that periodic extensions to the Elk Creek Project’s Air Permit are no longer required because the Company has met the regulatory definition of “construction, reconstruction, or modification of the source” since the permit was issued.
  • A radioactive materials license will be needed from the Nebraska Department of Health and Human Services (“NDHHS”), Office of Radiological Health. Because of their limited experience with hard rock mining in the State of Nebraska, much less mining that includes Naturally Occurring Radioactive Material, the NDHHS may require additional information and more time to approve the Elk Creek Project under a Broad Scope License. The Company has been working with NDHHS on this aspect of project permitting since 2014.
  • Documentation of existing baseline environmental conditions at the Elk Creek Project site was initiated in 2014 and will continue as needed throughout the permitting process.
  • Surface water monitoring will continue throughout the permitting process and extend into construction and operations as part of the Environmental Management System and likely State of Nebraska permit requirements.
  • A wetland delineation and potential jurisdictional waters assessment was conducted in late 2014 to identify wetland and drainage features within the proposed Elk Creek Project boundary which resulted in a formal JD being issued by the USACE on September 6, 2016.
  • The major land-use authorization for the project was received from Johnson County, Nebraska, on December 24, 2019, in the form of a Special Use Permit for the project. This land-use permit is a necessary precursor to any project-related construction activities. County zoning permits will be required for individual buildings constructed at the site, and the County requirement is that such applications must be submitted five days before construction commences.
  • Closure costs for the Elk Creek Project have been estimated at just over $44 million, including approximately $13.5 million for reclamation and closure of the TSFs and $16.6 million for plant and building removal and reclamation.
  • Community engagement has occurred in parallel with Nebraska field operations and has included public meetings, presentations to public agencies, communications with local and state politicians, meetings with environmental groups, and one-on-one meetings with area landowners.

Other Elk Creek Project Activities

On October 30, 2024, the Company announced that it had completed bench-scale testwork at a demonstration-scale processing plant located in Trois-Rivieres, Quebec built by the Company and L3 Process Development (“L3”) and operated by L3 (the “Demonstration Plant”), that successfully demonstrated that the process developed for extracting and recovering rare earth oxides found in the ore at the Elk Creek Project can be used to recycle the rare earth content in rare earth permanent magnets. The L3 team was able to demagnetize and grind up permanent rare earth magnets and then leach the contained rare earth elements from the magnet. The successful outcome of this testing opens up the possibility of accepting mixed rare earth concentrate from other mines into the planned Elk Creek plant once it is constructed and operating to supplement the ore expected to be produced from the Elk Creek mine.

On April 23, 2025, the Company announced the launch of a drilling campaign (the “Campaign”) designed to support the conversion of a portion of its current Indicated Resources into Measured Resources and the subsequent conversion of a portion of its current Probable Mineral Reserves into Proven Mineral Reserves at the Elk Creek Project. On August 12, 2025, the Company announced the successful completion of the Campaign. The Campaign was inclusive of nine HQ diamond drillholes, totaling 6,817 meters of drilling. Core processing is currently underway with samples being sent to SGS USA for sample preparation and analysis. The Campaign supplemented previous exploratory drilling and operated under existing permits issued by the State of Nebraska. The Campaign was designed to complement other technical and economic analyses necessary to update the feasibility study for the Elk Creek Project. An updated feasibility study is necessary as part of the due diligence process for up to $800 million in potential debt financing that NioCorp is seeking from EXIM, as further discussed under “Part II, Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations—Liquidity and Capital Resources” below.

As a result of favorable outcomes from the Campaign in terms of schedule and budget, the Company has elected to add up to an additional six drillholes, totaling approximately 3,930 meters, which will form Phase II of the Campaign (“Phase II”). Phase II is designed to support the conversion of additional indicated resources into measured resources and the subsequent conversion of additional probable mineral reserves into proven mineral reserves, as well as capturing additional hydrogeologic and geomechanical data that will be used to continue derisking the underground mine design.

Proposed Activities

At present, the Company is maintaining the Elk Creek Property in anticipation of obtaining project financing that will facilitate the construction, commissioning, and operation of the Elk Creek Project. The property is characterized as a development stage property and is expected to move to a production stage property should financing be obtained.

As funds become available through the Company’s fundraising efforts, we expect to undertake the following activities:

  • Continuation of the Company’s efforts to secure federal, state and local operating permits;
  • Continued evaluation of the potential to produce rare earth products and sell such products under offtake agreements;
  • Negotiation and completion of offtake agreements for the remaining uncommitted production of Nb, Sc, and Ti from the project, including the potential sale of Ti as titanium tetrachloride, as well as potential REE production;
  • Negotiation and completion of engineering, procurement, and construction agreements;
  • Completion of the final detailed engineering for the underground portion of the Elk Creek Project;
  • Initiation and completion of the final detailed engineering for surface project facilities;
  • Construction of natural gas and electrical infrastructure under existing agreements to serve the Elk Creek Project site;
  • Completion of water supply agreements and related infrastructure to deliver fresh water to the project site;
  • Initiation of revised mine groundwater investigation and control activities;
  • Based on the results of the Company’s Demonstration Plant operations, update the characterization and testing of waste materials to support tailings impoundment and paste backfill plant designs;
  • Initiation of long-lead equipment procurement activities; and
  • Initiation of initial construction work at the project site.

Non-GAAP Financial Performance Measures

Non-GAAP financial performance measures are intended to provide additional information only and do not have any standard meaning prescribed by U.S. GAAP. These measures should not be considered in isolation or as a substitute for performance measures prepared in accordance with U.S. GAAP.

The S-K 1300 Elk Creek Technical Report Summary uses non-GAAP financial performance measures, such as EBITDA, Averaged Annual EBITDA, and Averaged EBITDA Margin, for purposes of projecting the economic results of the Elk Creek Project. We are unable to provide a reconciliation of these forward-looking non-GAAP measures to the most comparable U.S. GAAP financial performance measures because certain information needed to reconcile those non-GAAP measures to the most comparable U.S. GAAP financial performance measures is dependent on future events, some of which are outside the control of the Company, such as FeNb, Sc2O3, and TiO2 prices, interest rates, and exchange rates. Moreover, estimating such U.S. GAAP measures with the required precision necessary to provide a meaningful reconciliation is extremely difficult and could not be accomplished without unreasonable effort.

Corporate Headquarters

We lease our principal executive office space at 7000 South Yosemite Street, Suite 115, Centennial, Colorado.

As filed, 280 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

As of September 11, 2025, we are not a party to any legal proceedings that could have a material adverse effect on the Company’s business, financial condition, or operating results. Further, to the Company’s knowledge, no such proceedings have been threatened against the Company.

Management's discussion and analysis

As filed, 32,914 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following Management’s Discussion and Analysis (“MD&A”) provides information that management believes is relevant to an assessment and understanding of the consolidated financial condition and results of operations of NioCorp and subsidiaries. This item should be read in conjunction with our consolidated financial statements and the notes thereto included in this Annual Report on Form 10-K.

Summary of Consolidated Financial and Operating Performance

The Company had no revenues from mining operations during the fiscal years presented below. Operating expenses incurred related primarily to performing exploration and feasibility study related activities, as well as the activities necessary to support corporate and shareholder duties.

For the year ended June 30, 2025 2024
Operating expenses $11,958 $13,757
Net loss attributable to the Company (17,405) (11,435)
Net loss per share (basic and diluted) (0.36) (0.31)

The net loss attributable to the Company increased to $17.4 million for fiscal year 2025 from $11.4 million for fiscal year 2024. This increased net loss in fiscal year 2025 as compared to fiscal year 2024 is primarily due to the fiscal year 2025 recognition of non-cash losses related to the valuation of the Earnout Share and Warrant liabilities, partially offset by lower interest expense, financial instrument fair values, and operating expenses.

Results of Operations

The Company had no revenues from mining operations during the fiscal years presented below. Operating expenses incurred related primarily to performing exploration and feasibility study related activities, and the activities necessary to support corporate and shareholder duties, as detailed in the following table:

Operating expenses: For the year ended June 30, 2025 2024
Employee related costs $1,944 $3,509
Professional fees 2,237 3,533
Exploration expenditures 4,135 2,552
Other operating expenses 3,642 4,163
Total operating expenses 11,958 13,757
Change in fair value of earnout shares liability 2,063 (6,704)
Change in fair value of warrant liabilities 4,093 (1,875)
Change in fair value of convertible note 40 2,542
Interest expense 48 4,490
Foreign exchange gain (5) (31)
Interest income (94) -
Other gains (122) (147)
Loss on equity securities 1 5
Income tax benefit - (139)
Loss attributable to noncontrolling interest (577) (463)
Net loss attributable to the Company $(17,405) $(11,435)

Fiscal Year 2025 as Compared to Fiscal Year 2024

Significant items affecting operating expenses are noted below:

Employee-related expenditures decreased in fiscal year 2025 as compared to fiscal year 2024 primarily due to a reduction in the number of Options issued to employees and the impact of a lower stock price on the Black-Scholes modeling results.

Professional fees decreased for fiscal year 2025 as compared to fiscal year 2024, primarily due to higher costs incurred in 2024 related to the timing of legal services associated with the Company’s SEC registration statements filed in October 2023, as well as increased audit fees associated with the Company’s June 30, 2023 financial statements and increased review fees in connection with the Company’s September 30, 2023 financial statements.

Exploration expenditures increased for fiscal year 2025 as compared to 2024, as fiscal year 2025 costs include expenditures related to a drilling program initiated by the Company in April 2025 designed to support the conversion of a portion of the Company’s current Indicated Resources into Measured Resources and the subsequent conversion of a portion of current Probable Mineral Reserves into Proven Mineral Reserves. Fiscal year 2024 costs included expenses associated with the third-party owned and operated Demonstration Plant, for which testwork was completed during the third quarter of fiscal year 2024.

Other operating expenses decreased for fiscal year 2025 as compared to fiscal year 2024 primarily due to a decrease in director and officer insurance expense, the timing of fully vested Options issued to board members and advisors, and declines in scandium development initiatives and financial-related services, partially offset by the expense incurred in 2025 associated with a cybersecurity incident that resulted in misdirected vendor payments.

Other significant items impacting the change in the Company’s net loss are noted below:

Change in fair value of Earnout Shares liability represents the change in fair value related to the Earnout Shares based on the results of Monte Carlo financial modeling. Overall, the increased expense in fiscal year 2025 corresponds to an overall increase in our share value during fiscal year 2025.

Change in fair value of Warrant liability represents the change in fair value related to our liability-classified Warrant obligations. The increase in expense during fiscal year 2025 is due primarily to the increase in the ending market value of our Common Shares as of June 30, 2025.

Change in fair value of convertible notes represents the impact of the initial allocation of fair value to the April 2024 Notes (as defined below), which are carried at fair value, as well as the impact of fair value adjustments through final payoff.

Interest expense decreased in fiscal year 2025 as compared to fiscal year 2024 due to the impacts of convertible debenture interest expense incurred in fiscal year 2024. This convertible debt instrument was paid off in early fiscal year 2025.

Loss attributable to noncontrolling interest represents the portion of net loss in ECRC attributable to the Vested Shares, which are not owned by the Company.

Liquidity and Capital Resources

We have no revenue generating operations from which we can internally generate funds. To date, our ongoing operations have been financed by the sale of our equity securities by way of public and private offerings, convertible securities issuances, the exercise of incentive Options and Warrants, and related party loans. With respect to currently outstanding Options and Warrants, we believe that exercise of these instruments, and cash proceeds from such exercises, will not occur unless and until the market price for our Common Shares equals or exceeds the related exercise price of each instrument.

On April 12, 2024, the Company issued and sold to Yorkville and Lind Global Fund II (“Lind II” and, together with Yorkville, the “April 2024 Purchasers”), $8.0 million aggregate principal amount of unsecured notes (the “April 2024 Notes”), pursuant to a securities purchase agreement, dated April 11, 2024, between the Company and each of the April 2024 Purchasers. The Company also issued to the April 2024 Purchasers, in proportion to the aggregate principal amount of the April 2024 Notes issued to each April 2024 Purchaser, Warrants to purchase up to 615,385 Common Shares. All remaining amounts due to Lind II ($176,000) and Yorkville ($1.0 million) under the April 2024 Notes were repaid on January 6, 2025, and February 7, 2025, respectively.

On September 11, 2024, the Company and Mark Smith entered into the Loan Agreement, by and between the Company and Mark Smith (the “Smith Loan Agreement”), which provides for a $2.0 million non-revolving credit facility (the “Smith Loan”). A total of $504,000 was subsequently drawn down, and subsequently the Company repaid $508,000, representing the balance of the interest and principal outstanding under the Smith Loan, plus $41,000 related to the loan origination fees payable.

On November 5, 2024, the Company closed an underwritten public offering (the “November 2024 Registered Offering”), pursuant to the underwriting agreement, dated November 3, 2024, with Maxim, as underwriter, which consisted of 1,592,356 Common Shares, 1,672,090 Series A Warrants to purchase up to an additional 1,672,090 Common Shares and 836,045 Series B Warrants to purchase up to 836,045 Common Shares.

On November 13, 2024, the Company closed a non-brokered private placement (the “November 2024 Private Offering”) pursuant to binding subscription agreements with certain accredited investors as part of a non-brokered private placement of 2,199,602 units of the Company (the “November 2024 Units”). Each November 2024 Unit consists of one Common Share, one Series A Warrant to purchase up to an additional Common Share and one-half of one Series B Warrant to purchase up to one-half of one Common Share.

On January 31, 2025, the Company closed an underwritten public offering (the “January 2025 Offering”), pursuant to the underwriting agreement, dated January 29, 2025, with Maxim, as underwriter, which consisted of 2,577,320 Common Shares, 2,577,320 Series A Warrants to purchase up to an additional 2,577,320 Common Shares and 1,288,660 Series B Warrants to purchase up to 1,288,660 Common Shares.

On April 21, 2025, the Company closed an underwritten public offering (the “April 2025 Offering”), pursuant to an underwriting agreement dated April 17, 2025, with Maxim, as underwriter, pursuant to which the Company issued and sold an aggregate of 8,015,812 Common Shares (or pre-funded Warrants in lieu thereof), which includes 323,504 Common Shares issued and sold pursuant to Maxim’s partial exercise of its over-allotment option.

The combined gross proceeds from the November 2024 Registered Offering, the November 2024 Private Offering, the January 2025 Offering, and the April 2025 Offering were approximately $31.8 million, before deducting underwriting discounts and offering expenses. In addition, during fiscal year 2025, the Company issued an aggregate of 6,499,977 Common Shares under the Yorkville Equity Facility Financing Agreement and through the exercise of Warrants by their holders, as a result of which, the Company received cash totaling approximately $13.8 million. A portion of these proceeds were used for working capital and general corporate purposes, to repay amounts outstanding on the Smith Loan, to repay the April 2024 Notes, and to advance efforts to launch construction of the Elk Creek Project and move it to commercial operation.

As of June 30, 2025, the Company had cash of $25.6 million and working capital of $24.8 million, compared to cash of $2.0 million and a working capital deficit of $9.0 million on June 30, 2024.

We expect that the Company will operate at a loss for the foreseeable future. The Company’s current planned cash needs are approximately $40.0 million to $50.0 million for the next twelve months. In addition to outstanding accounts payable and short-term liabilities, our planned expenditures over the next twelve months are expected to consist of expenditures relating to certain advancements of the Elk Creek Project by NioCorp’s majority owned subsidiary, ECRC, corporate overhead costs, and estimated costs related to securing financing necessary for advancement of the Elk Creek Project. As discussed below, if the Company were able to obtain additional funding, the Company would be in a position to accelerate planned expenditures ahead of its current schedule.

The planned expenditures relating to the advancement of the Elk Creek Project over the next twelve months include, but are not limited to, an updated resource and reserve estimate and associated mine plan and an updated capital cost estimate in connection with the EXIM application process. The planned corporate overhead costs over the next twelve months include Elk Creek property lease commitments, which are $57,000 through June 30, 2026, and outstanding accounts payable.

The estimated financing costs associated with the Elk Creek Project over the next twelve months include, but are not limited to, costs relating to the EXIM application process, the scope of which remains under discussion with EXIM. On June 6, 2023, the Company announced that it had submitted an application to EXIM for up to $800 million in debt financing (the “EXIM Financing”) to fund the project costs for the Elk Creek Project, under EXIM’s “Make More in America” initiative. The EXIM Financing is subject to, among other matters, the satisfactory completion of due diligence, the negotiation and settlement of final terms, and the negotiation of definitive documentation. There can be no assurance that the EXIM Financing will be completed on the terms described herein or at all. The Company was informed that its application received approval by the first of three reviews by the EXIM Transaction Review Committee (the “TRC”) on October 2, 2023. During the fourth quarter of fiscal year 2025, EXIM continued to process the Company’s application for debt financing under EXIM’s Make More in America Program. The Company’s application sits at the TRC in the second step in EXIM’s four-step approval process. The Company continues to meet with EXIM as well as providing responses to requests for additional information from EXIM and to the consultants that are conducting due diligence on the Company’s application on behalf of EXIM. As part of the diligence process, EXIM has identified additional project activities to be undertaken, including, among other things, an updated mine plan and updated Elk Creek Project capital costs on a final or close-to-final basis reflecting updated process flows. However, there can be no assurance what further project activities or matters EXIM may request in connection with the application process. We are currently unable to estimate how long the application process may take, and there can be no assurances that we will be able to successfully negotiate a final commitment of debt financing from EXIM.

On July 18, 2025, the Company closed a public offering (the “July 2025 Offering”), pursuant to which the Company issued and sold 13,850,000 Common Shares at a public offering price of $3.25 per Common Share, for net proceeds of approximately $41.8 million after deducting placement agent fees discounts and prior to other offering expenses. Maxim acted as sole placement agent for the July 2025 Offering. The Company intends to use the net proceeds from the July 2025 Offering for working capital and general corporate purposes, including to advance its efforts to launch construction of the Elk Creek Project and move it to commercial operation. During the period from July 1, 2025 through September 11, 2025, the Company also issued 5,000,312 Common Shares through the exercise of Warrants and Options by their holders, and received cash totaling approximately $10.4 million.

On August 4, 2025, ECRC entered into the DoD Agreement with ATI, an entity acting on behalf of the Defense Industrial Base Consortium under the authority of the DoD. Subject to the terms and conditions of the DoD

Agreement, ECRC is entitled to receive up to an aggregate of approximately $10.0 million of reimbursement payments from the DoD upon the achievement of certain project milestones related to feasibility study-level engineering and additional reserve drilling, as well as preparing updated cost estimates, for the Elk Creek Project.

We expect to use our cash balance as of June 30, 2025, as well as the proceeds from the July 2025 Offering, the proceeds from the Warrant exercise issuances, and the reimbursement payments pursuant to the DoD Agreement, to fund our planned expenditures for the next twelve months. However, additional work is required in order to advance the Elk Creek Project, requiring additional financing. The S-K 1300 Elk Creek Technical Report Summary includes an estimated total upfront capital expenditure for the Elk Creek Project of approximately $1,141.0 million. The actual amount of capital expenditure required to successfully achieve commercial production at the Elk Creek Project is subject to, among other factors, the timing and actual cost of further exploration, preparing feasibility studies, permitting, engineering and the construction of infrastructure, mining and processing facilities. If the Company were able to obtain additional funding, the Company would be in a position to accelerate planned expenditures ahead of its current schedule. In addition, to the extent that EXIM requests further project activities to be undertaken in connection with the diligence process, the Company would require additional funding to complete such activities. The Company’s ability to continue operations and fund our current work plan is dependent on management’s ability to secure additional financing. When available, the Yorkville Equity Facility Financing Agreement provides an opportunity to actively manage the cash needs of the Company more closely, and the Company may also utilize the Yorkville Equity Facility Financing Agreement to potentially generate funds at a time when they are in need. Alternatively, the Company can also utilize the Yorkville Equity Facility Financing Agreement for opportunistic share sales. However, the Yorkville Equity Facility Financing Agreement will expire by its terms on April 1, 2026.

Except for the potential funding from advances under the Yorkville Equity Facility Financing Agreement, as discussed above, and the potential exercise of Options and Warrants, we currently have no further funding commitments or arrangements for additional financing at this time. Management currently anticipates that it will fund the upfront capital expenditure amount for the Elk Creek Project through a combination of debt and equity financing, with approximately two-thirds of such amount being funded from the net proceeds of debt financing, including the amount of debt that would be represented by the EXIM Financing, if any. Management is actively pursuing additional sources of debt and equity financing to meet its long-term funding requirements, and while it has been successful in doing so in the past, there is no assurance that we will be able to obtain any such additional financing on acceptable terms, if at all. Pursuant to the Exchange Agreement, NioCorp is restricted from issuing equity or equity-linked securities (other than Common Shares) or any preferred equity or non-voting equity if such issuance would adversely impact the rights of the holders of the shares of Class B common stock of ECRC, without the consent of the holders of a majority of the shares of Class B common stock of ECRC. On July 17, 2025, we entered into the Placement Agency Agreement with Maxim, which also contains certain covenants that, among other things, limit NioCorp’s ability to enter into any variable rate transaction on or before September 17, 2025, including issuances of equity or debt securities that are convertible into Common Shares at variable rates and any equity line of credit, ATM agreement, or other continuous offering of Common Shares, other than with Maxim, subject to certain exceptions. Notwithstanding the restrictions set forth in the Exchange Agreement and the Placement Agency Agreement, there is significant uncertainty that we would be able to secure any additional financing in the current equity or debt markets. The quantity of funds to be raised and the terms of any proposed equity or debt financing that may be undertaken will be negotiated by management as opportunities to raise funds arise. Management may pursue funding sources of both debt and equity financing, including but not limited to the issuance of equity securities in the form of Common Shares, Warrants, subscription receipts, or any combination thereof in units of the Company pursuant to private placements to accredited investors or pursuant to public offerings in the form of underwritten/brokered offerings, registered direct offerings, or other forms of equity financing and public or private issuances of debt securities, including secured and unsecured convertible debt instruments, or secured debt project financing. Management does not currently know the terms pursuant to which such financings may be completed in the future, but any such financings will be negotiated at arm’s-length. Future financings involving the issuance of equity securities or derivatives thereof will likely be completed at a discount to the then-current market price of the Company’s securities and will likely be dilutive to current shareholders. In addition, we could raise funds through the sale of interests in our mineral properties, although current market conditions and other recent worldwide events have substantially reduced the number of potential buyers/acquirers of any such interests. However, we cannot provide any assurances that we will be able to be successful in raising such funds.

Based on the conditions described within, management has concluded and the audit opinion and notes that accompany our consolidated financial statements for the year ended June 30, 2025, disclose that substantial doubt exists as to our ability to continue as a going concern. The consolidated financial statements included in this Annual Report on Form 10-K have been prepared under the assumption that we will continue as a going concern. As defined under S-K 1300, we are a development stage issuer, and we have incurred losses since our inception. The Company will require additional capital to meet its long-term operating requirements. Uncertainty in capital markets, supply chain disruptions, increased interest rates and inflation, and the potential for geographic recessions have contributed to general global economic uncertainty. During fiscal year 2025, these events continued to create uncertainty with respect to overall project funding and timelines. We believe that the going concern uncertainty cannot be alleviated with confidence until the Company has entered into a business climate where funding of its planned ongoing operating activities is secured. Therefore, these factors raise substantial doubt as to our ability to continue as a going concern.

We have no exposure to any asset-backed commercial paper. Other than cash held by our subsidiaries for their immediate operating needs in Colorado and Nebraska, all of our cash reserves are on deposit with major U.S. and Canadian chartered banks. We do not believe that the credit, liquidity, or market risks with respect thereto have increased as a result of the current market conditions. However, in order to achieve greater security for the preservation of our capital, we have, of necessity, been required to accept lower rates of interest, which has also lowered our potential interest income.

Operating Activities

During the year ended June 30, 2025, the Company’s operating activities consumed $10.7 million of cash (2024: $11.7 million). Overall, operational outflows during fiscal year 2025 decreased from the corresponding period of 2024 primarily due to the timing of vendor payments. Going forward, the Company’s working capital requirements are expected to increase substantially in connection with the development of the Elk Creek Project.

Investing Activities

The Company had minimal investing activities during the years ended June 30, 2025 and 2024, respectively.

Financing Activities

Net cash provided by financing activities was $34.2 million in fiscal year 2025 (2024: $11.4 million). This increase in financing inflows primarily reflects the timing of cash inflows from the financing transactions disclosed above under “Liquidity and Capital Resources.”

Cash Flow Considerations

The Company has historically relied upon debt and equity financing to finance its activities. Subject to the restrictions set forth in the Exchange Agreement, the Company may pursue additional debt and/or equity financing in the medium term; however, there can be no assurance the Company will be able to obtain any required financing in the future on acceptable terms.

The Company has limited financial resources compared to its proposed expenditures, no source of operating income, and no assurance that additional funding will be available to it for current or future projects, although the Company has been successful in the past in financing its activities through the sale of equity securities.

The ability of the Company to arrange additional financing in the future will depend, in part, on the prevailing capital market conditions, and its success in developing the Elk Creek Project. Any quoted market for the Common Shares may be subject to market trends generally, notwithstanding any potential success of the Company in creating revenue, cash flows, or earnings, and any depression of the trading price of the Common Shares could impact its ability to obtain equity financing on acceptable terms.

Historically, the Company has used net proceeds from issuances of Common Shares to provide sufficient funds to meet its near-term exploration and development plans and other contractual obligations when due. However, development and construction of the Elk Creek Project will require substantial additional capital resources. This includes near-term funding and, ultimately, funding for Elk Creek Project construction and other costs. See “Liquidity and Capital Resources” above, for the Company’s discussion of arrangements related to possible future financings.

Environmental

Our mining and exploration activities are subject to various federal and state laws and regulations governing the protection of the environment. We have made, and expect to make in the future, expenditures to comply with such laws and regulations, but cannot predict the full amount of such future expenditures. As of June 30, 2025 and 2024, we had accrued $48,000 and $48,000, respectively, related to estimated environmental obligations.

Forward-Looking Statements

The foregoing discussion and analysis, as well as certain information contained elsewhere in this Annual Report on Form 10-K, contain “forward-looking statements” within the meaning of Section 27A of the Securities Act and Section 21E of the Exchange Act, and are intended to be covered by the safe harbor created thereby. See the discussion in “Forward-Looking Statements” in Item 1., “Business.”

Accounting Developments

For a discussion of Recently Adopted Accounting Pronouncements and Recently Issued Accounting Pronouncements, see Note 3 to the consolidated financial statements included in this Annual Report on Form 10-K.

Critical Accounting Estimates and Recent Accounting Pronouncements

Our significant accounting policies are described in Note 3 to the Consolidated Financial Statements included in this Annual Report on Form 10-K. As described in Note 3, we are required to make estimates and assumptions that affect the reported amounts and related disclosures of assets, liabilities, revenue, and expenses. Our estimates are based on our experience and our interpretation of economic, political, regulatory, and other factors that affect our business prospects. Many of the inputs into our estimation process are subjective and are subject to uncertainty over time and therefore, actual results may differ significantly from our estimates. Note 3 also discloses recent accounting pronouncements applicable to the Company.

We believe that our most critical accounting estimates are related to the carrying value of our long term assets; accounting for income taxes and the valuation of deferred tax assets; and the valuation of liabilities associated with Warrants, convertible debt carried at fair value, and Earnout Shares, as they require us to make assumptions that are highly uncertain at the time the accounting estimates are made and changes in them are reasonably likely to occur from period to period. Management has discussed the development and selection of these critical accounting estimates with the Audit Committee of our Board (the “Audit Committee”), and the Audit Committee has reviewed the disclosures presented below. In addition, there are other items within our financial statements that require estimation, but are not deemed to be critical. However, changes in estimates used in these and other items could have a material impact on our consolidated financial statements.

Carrying Value of Long-Lived Assets

The recoverability of the carrying values of mineral properties is dependent upon economic reserves being discovered or developed on the properties, permitting, financing, start-up, and commercial production from, or the sale/lease of, or other strategic transactions related to these properties. Development and/or start-up of a project will depend on, among other things, management’s ability to raise sufficient capital for these purposes. We assess the carrying cost of our mineral properties for impairment whenever information or circumstances indicate the potential for impairment. Key inputs include events and circumstances such as our inability to obtain all the necessary permits, changes in the legal status of our mineral properties, government actions, the results of exploration activities and technical evaluations and changes in economic conditions, including the price of commodities or input prices. Many of these inputs are subjective and are subject to uncertainty over time. Such evaluations compare estimated future net cash flows with our carrying costs and future obligations on an undiscounted basis. If it is determined that the estimated future undiscounted cash flows are less than the carrying value of the property, an impairment loss will be recorded, measured by the amount by which the carrying amount of the assets exceeds the fair value of the assets. Where estimates of future net cash flows are not determinable and where other conditions indicate the potential for impairment, management uses available market information and/or third-party valuation experts to assess if the carrying value can be recovered and to estimate fair value.

We review and evaluate our long-lived assets, other than mineral properties, for impairment when events or changes in circumstances indicate that the related carrying amounts may not be recoverable. An impairment loss is measured and recorded based on the estimated fair value of the long-lived assets being tested for impairment and their carrying amounts.

Income Taxes

We have assets, hold interests, and conduct activities in the U.S. and Canada and are subject to their tax regimes. Tax laws are complex and continue to evolve. While we have a history of losses, our assumptions made in tax returns are subject to review and interpretation by taxing authorities and could be modified. Management judgment is required in determining our provision for income taxes, our deferred tax assets and liabilities, and any valuation allowance recorded against our deferred tax assets. We consider factors such as the cumulative income or loss in recent years; reversal of deferred tax liabilities; projected future taxable income exclusive of temporary differences; the character of the income tax asset, including income tax positions; tax planning strategies and the period over which we expect the deferred tax assets to be recovered in the determination of the valuation allowance. In the event that actual results differ from these estimates or we adjust our estimates in the future, we may need to adjust our valuation allowance, which could materially impact our financial position and results of operations.

Financial Instruments Carried at Fair Value

The fair values of our Earnout Shares, private Warrants, Contingent Consent Warrants, and convertible debt carried at fair value were determined using various significant unobservable inputs, including a discount rate and our best estimate of expected volatility and expected holding periods. Changes in the estimated fair values of these liabilities may have material impacts on our results of operations in any given period, as any increases in these liabilities have a corresponding negative impact on our U.S. GAAP results of operations. See Notes 8, 9, and 10c to our consolidated financial statements included in this Annual Report on Form 10-K for additional details.

Other

The Company has one class of shares, being Common Shares. A summary of outstanding Common Shares, Vested Shares, Options, and Warrants as of September 11, 2025, is set out below, on a fully diluted basis.

Common Shares Outstanding (fully diluted)
Common Shares 77,757,089
Vested Shares(1) 3,518,450
Options(2) 4,900,000
Warrants(3) 24,787,533

(1) Each exchangeable into one Common Share at any time, and from time to time, until the tenth anniversary of the Closing Date.

(2) Each exercisable for one Common Share.

(3) Includes 15,666,626 NioCorp Assumed Warrants that are each exercisable for 1.11829212 Common Shares, and 9,120,907 Warrants that are each exercisable into one Common Share.

Market risk

As filed, 1,239 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Interest rate risk

The Company’s exposure to changes in market interest rates, relates primarily to the Company’s earned interest income on cash deposits and short-term investments. The Company maintains a balance between the liquidity of cash assets and the interest rate return thereon. The carrying amount of financial assets, net of any provisions for losses, represents the Company’s maximum exposure to credit risk.

Foreign currency exchange risk

The Company incurs expenditures in both U.S. and Canadian dollars. Canadian dollar expenditures are primarily related to engineering and metallurgical expenses, as well as certain professional services. As a result, currency exchange fluctuations may impact the costs of our operating activities. To reduce this risk, we maintain sufficient cash balances in Canadian dollars to fund expected near-term expenditures.

Commodity price risk

The Company is exposed to commodity price risk related to the elements associated with the Elk Creek Project. A significant decrease in the global demand for these elements may have a material adverse effect on our business. The Elk Creek Project is not in production, and the Company does not currently hold any commodity derivative positions.

Controls and procedures

As filed, 8,778 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Evaluation of Disclosure Controls and Procedures

The management of NioCorp Developments Ltd. has evaluated, under the supervision and with the participation of our Chief Executive Officer (“CEO”) and Chief Financial Officer (“CFO”), the effectiveness of our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act) as of June 30, 2025. Based on that evaluation, the CEO and the CFO have concluded that, as of June 30, 2025, our disclosure controls and procedures were not effective due to the material weaknesses in internal control over financial reporting described below.

Notwithstanding the material weaknesses in our internal control over financial reporting, our CEO and CFO have concluded that the audited consolidated financial statements included in this Annual Report on Form 10-K fairly present, in all material respects, our financial position, results of operations and cash flows for the periods presented in conformity with U.S. GAAP.

The Company’s disclosure controls and procedures have been designed to ensure that: (i) information required to be disclosed by us in reports that we file or submit to the SEC under the Exchange Act is recorded, processed, summarized, and reported within the time periods specified in applicable rules and forms and (ii) material information required to be disclosed in our reports filed under the Exchange Act is accumulated and communicated to management, including the CEO and the CFO, as appropriate, to allow for accurate and timely decisions regarding required disclosures.

Management does not expect that our disclosure controls and procedures will prevent all error and all fraud. The effectiveness of our or any system of disclosure controls and procedures, however well designed and operated, can provide only reasonable assurance that the objectives of the system will be met and is subject to certain limitations, including the exercise of judgment in designing, implementing, and evaluating controls and procedures and the assumptions used in identifying the likelihood of future events.

Management’s Report on Internal Control over Financial Reporting

The management of NioCorp Developments Ltd. is responsible for establishing and maintaining adequate internal control over financial reporting as defined in Rules 13a-15(f) and 15d-15(f) of the Exchange Act for the Company. Management assessed the effectiveness of our internal control over financial reporting as of June 30, 2025. In making this assessment, our management used the criteria set forth in the Internal Control - Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission (the “COSO Framework”). Based on that evaluation, the CEO and the CFO have concluded that, as of June 30, 2025, our internal control over financial reporting was not effective due to the material weaknesses in internal control over financial reporting described below.

Material Weaknesses

A material weakness is a deficiency, or a combination of deficiencies, in internal control over financial reporting, such that there is a reasonable possibility that a material misstatement of our annual or interim consolidated financial statements will not be prevented or detected on a timely basis.

Management concluded that the material weaknesses disclosed in the Company’s Annual Report on Form 10-K for the fiscal year ended June 30, 2023, continued to exist as of June 30, 2025. Specifically, management identified deficiencies in the principles associated with the control environment, risk assessment, control activities, and monitoring components of internal control, based on the criteria established by the COSO Framework, that constitute material weaknesses, either individually or in the aggregate.

  • Control Environment: The Company does not have sufficient personnel with the appropriate levels of knowledge, experience, and training in accounting and internal control over financial reporting commensurate with the complexity of the Company’s financing transactions and associated reporting requirements. This material weakness contributed to additional material weaknesses further described below.
  • Risk Assessment: The Company does not have a formal process to identify, update, and assess financial reporting risks due to changes in the Company’s business practices, including entering into increasingly complex transactions that could significantly impact the design and operation of the Company’s control activities.
  • Control Activities: Management did not maintain effective controls over:
  • monitoring and assessing the work of third-party specialists, including the evaluation of the appropriateness of accounting conclusions,
  • the evaluation of certain inputs and assumptions used to estimate the fair value of instruments and features associated with complex debt and equity transactions, and
  • the design and implementation of effective process-level control activities related to vendor banking information.
  • Monitoring Activities: Management did not appropriately:
  • select, develop, and perform ongoing evaluation to ascertain whether the components of internal controls are present and functioning, and
  • evaluate and communicate internal control deficiencies in a timely manner to those parties responsible for taking corrective action.

As previously disclosed, these material weaknesses resulted in errors that required the restatement of Company’s consolidated financial statements as of and for the fiscal years ended June 30, 2022 and 2021, as well as the restatement of the Company’s condensed consolidated financial statements as of and for the interim periods ended September 30, 2021, December 31, 2021, March 31, 2022, September 30, 2022 and December 31, 2022. Additionally, these material weaknesses could result in a misstatement of the account balances or disclosures that would result in a material misstatement to the annual or interim consolidated financial statements that would not be prevented or timely detected.

Remediation Plan

To address our material weaknesses existing as of June 30, 2025, we have implemented a detailed plan to address each individual material weakness identified, including the following:

  • We have, and will continue, to engage outside accounting and internal control consultants with subject matter expertise to supplement our level of knowledge, experience, and training in accounting and internal control over financial reporting.
  • We have developed a formal risk assessment process requiring periodic review and updates of current risks and internal controls, as well as a focus on potential future events that could result in additional risks and/or internal control lapses. This process is expected to enable us to effectively identify, develop, evolve, and implement controls and procedures to address risks, and results of this risk assessment process will be reviewed with the Audit Committee on a periodic basis.
  • We have developed an initial training plan to provide incremental training to accounting and finance personnel responsible for overall technical accounting and valuation-related transactions.
  • Management is developing a monitoring program to periodically evaluate and assess whether those responsible for controls are conducting their activities in accordance with their design, such that there is contemporaneous evidence that the controls are present and functioning and will communicate internal control deficiencies in a timely manner to those parties responsible for taking corrective action.

The process of designing and maintaining effective internal control over financial reporting is a continuous effort that requires management to anticipate and react to changes in our business, economic and regulatory environments and to expend significant resources. As we continue to evaluate our internal control over financial reporting, we may take additional actions to remediate the material weaknesses or modify the remediation actions described above.

While we continue to devote significant time and attention to these remediation efforts, the material weaknesses will not be considered remediated until management completes the design and implementation of the actions described above and the controls operate for a sufficient period of time, and management has concluded, through testing, that these controls are effective.

Changes in Internal Control over Financial Reporting

Other than as discussed above, there has been no change in our internal control over financial reporting during the quarter ended June 30, 2025, that has materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2025-06-30. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Interest expense12 months2024-07-01 to 2025-06-30$48.0kus-gaap:InterestExpenseNonoperating
Income tax12 months2024-07-01 to 2025-06-30$0us-gaap:IncomeTaxExpenseBenefit
Net income12 months2024-07-01 to 2025-06-30−$18.0mus-gaap:NetIncomeLoss
Diluted EPS12 months2024-07-01 to 2025-06-30−$0.36us-gaap:EarningsPerShareDiluted
Basic EPS12 months2024-07-01 to 2025-06-30−$0.36us-gaap:EarningsPerShareBasic
Diluted shares (weighted)12 months2024-07-01 to 2025-06-3045,072,895 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Operating cash flow12 months2024-07-01 to 2025-06-30−$10.7mus-gaap:NetCashProvidedByUsedInOperatingActivities
Cash and equivalentsAt period end2025-06-30$25.6mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2025-06-30$26.7mus-gaap:AssetsCurrent
Total assetsAt period end2025-06-30$43.8mus-gaap:Assets
Current liabilitiesAt period end2025-06-30$1.9mus-gaap:LiabilitiesCurrent
Total liabilitiesAt period end2025-06-30$14.7mus-gaap:Liabilities
Shareholders' equityAt period end2025-06-30$28.3mus-gaap:StockholdersEquity

Source: SEC EDGAR, the filing index for accession 0001539497-25-002331. Last ingested by Listed: Nov 11, 2026, 03:00 ET. Listed shows no prices and gives no investment advice.