Listed

Niocorp Developments Ltd: Form 10-Q for the period ended Sep 30, 2025

Filed with the SEC on Nov 13, 2025 and accepted by EDGAR at Nov 13, 2025, 16:27 ET.

Share

Management's discussion and analysis

As filed, 54,026 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following discussion and analysis should be read in conjunction with our historical interim condensed consolidated financial statements and related notes included elsewhere in this Quarterly Report on Form 10-Q and the Annual Report on Form 10-K filed with the Securities and Exchange Commission (the “SEC”) for the year ended June 30, 2025 filed on September 11, 2025 (the “Annual Report on Form 10-K”), which have been prepared in accordance with generally accepted accounting principles in the United States (“U.S. GAAP”). The Company uses certain non-GAAP financial measures. For a detailed description of each of the non-GAAP measures used herein, please refer to the discussion under “—Use of Non-GAAP Financial Measures and Reconciliations.”

This discussion and analysis contains forward-looking statements and forward-looking information that involve risks, uncertainties, and assumptions. Our actual results may differ materially from those anticipated in these forward-looking statements and information as a result of many factors, including, but not limited to, those set forth elsewhere in this Quarterly Report on Form 10-Q. See “—Note Regarding Forward-Looking Statements” below.

All currency amounts are stated in U.S. dollars unless noted otherwise.

As used in this Quarterly Report on Form 10-Q, unless the context otherwise indicates, references to “we,” “our,” the “Company,” “NioCorp,” and “us” refer to NioCorp Developments Ltd. and its subsidiaries, collectively.

Note Regarding Forward-Looking Statements

This Quarterly Report on Form 10-Q and the exhibits attached hereto contain “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended (the “Securities Act”), and Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), and “forward-looking information” within the meaning of applicable Canadian securities legislation (collectively, “forward-looking statements”). Such forward-looking statements concern our anticipated results and developments in the operations of the Company in future periods, planned exploration activities, the adequacy of the Company’s financial resources, and other events or conditions that may occur in the future.

Forward-looking statements have been based upon our current business and operating plans, as approved by the Board, and may include statements regarding, among other matters, the financial and business performance of NioCorp; NioCorp’s anticipated results and developments in the operations of NioCorp in future periods; NioCorp’s planned exploration activities; the adequacy of NioCorp’s financial resources; NioCorp’s ability to secure sufficient project financing to complete construction and commence operation of the Company’s niobium, scandium, and titanium project (the “Elk Creek Project”) located in southeastern Nebraska; NioCorp’s ability to receive a final commitment of financing from the Export-Import Bank of the United States (“EXIM”); the estimated total upfront capital expenditure for the Elk Creek Project; NioCorp’s expectation and ability to produce niobium, scandium, and titanium and the potential to produce rare earth elements at the Elk Creek Project; NioCorp’s plans to produce and supply specific products and market demand for those products; NioCorp’s ability to access the full amount of the expected net proceeds of the Standby Equity Purchase Agreement, dated January 26, 2023 (the “Yorkville Equity Facility Financing Agreement”) between the Company and YA II PN, Ltd., an investment fund managed by Yorkville Advisors Global, LP (“Yorkville”); NioCorp’s expectation that it will receive the full $10 million in reimbursement under the DoD Agreement (as defined below); the intended use of our cash balance as of September 30, 2025 as well as the proceeds from the October 2025 Offering (as defined below), the proceeds from the exercise of Common Share purchase warrants (“Warrants”) and the reimbursement payments pursuant to the DoD Agreement; the expected results of the 2025 Drilling Program (as defined below) at the Elk Creek Project; the expectation that the results of the 2025 Drilling Program will be used to update the feasibility study for the Elk Creek Project; the Elk Creek Project’s ability to produce multiple critical metals; the Elk Creek Project’s projected ore production and mining operations over its expected mine life; the completion of technical and economic analyses on the potential addition of magnetic rare earth oxides to NioCorp’s planned product suite; statements with respect to the estimation of mineral resources and mineral reserves; the exercise of options to purchase additional land parcels; the execution of contracts with engineering, procurement and construction companies; NioCorp’s ongoing evaluation of the impact of inflation, supply chain issues, tariffs, and geopolitical unrest on the Elk Creek Project’s economic model; and the creation of full time and contract construction jobs over the construction period of the Elk Creek Project.

Forward-looking statements are frequently, but not always, identified by words such as “expects,” “anticipates,” “believes,” “intends,” “estimates,” “potential,” “possible,” and similar expressions, or statements that events, conditions, or results “will,” “may,” “could,” or “should” (or the negative and grammatical variations of any of these terms) occur or be achieved. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, or future events or performance (often, but not always, using words or phrases such as “expects” or “does not expect,” “is expected,” “anticipates” or “does not anticipate,” “plans,” “estimates,” or “intends,” or stating that certain actions, events, or results “may,” “could,” “would,” “might,” or “will” be taken, occur or be achieved) are not statements of historical fact and may be forward-looking statements. Forward-looking statements reflect material expectations and assumptions, including, without limitation, expectations and assumptions relating to: NioCorp’s ability to receive sufficient project financing for the construction of the Elk Creek Project on acceptable terms, or at all; the future price of metals; the stability of the financial and capital markets; and current estimates and assumptions regarding the Yorkville Equity Facility Financing Agreement and its benefits. Such forward-looking statements reflect the Company’s current views with respect to future events and are subject to certain known and unknown risks, uncertainties, and assumptions. Many factors could cause actual results, performance, or achievements to be materially different from any future results, performance, or achievements that may be expressed or implied by such forward-looking statements, including, among others, risks related to the following: NioCorp’s requirement of significant additional capital; NioCorp’s ability to receive sufficient project financing for the construction of the Elk Creek Project on acceptable terms, or at all; NioCorp’s ability to achieve the required milestones and receive the full $10.0 million in reimbursement under the DoD Agreement; NioCorp’s ability to receive a final commitment of financing from EXIM or other debt financing or financial support on acceptable timelines, on acceptable terms, or at all; NioCorp’s ability to access the full amount of the expected net proceeds under the Yorkville Equity Facility Financing Agreement; NioCorp’s ability to continue to meet Nasdaq listing standards; risks relating to the common shares, no par value, of the Company (“Common Shares”), including price volatility, lack of dividend payments and dilution or the perception of the likelihood of any of the foregoing; the extent to which NioCorp’s level of indebtedness and/or the terms contained in agreements governing NioCorp’s indebtedness, if any, the Yorkville Equity Facility Financing Agreement or other agreements may impair NioCorp’s ability to obtain additional financing, on acceptable terms, or at all; covenants contained in agreements with NioCorp’s secured creditors that may affect its assets; NioCorp’s limited operating history; NioCorp’s history of losses; the material weaknesses in NioCorp’s internal control over financial reporting, NioCorp’s efforts to remediate such material weaknesses and the timing of remediation; the possibility that NioCorp may qualify as a “passive foreign investment company (“PFIC”) under the Internal Revenue Code of 1986, as amended (the “Code”); the potential that the 2023 Transactions could result in NioCorp becoming subject to materially adverse U.S. federal income tax consequences as a result of the application of Section 7874 and related sections of the Code; cost increases for NioCorp’s exploration and, if warranted, development projects; a disruption in, or failure of, NioCorp’s information technology systems, including those related to cybersecurity; equipment and supply shortages; variations in the market demand for, and prices of, niobium, scandium, titanium and rare earth products; current and future offtake agreements, joint ventures, and partnerships, including our ability to negotiate extensions to existing agreements or to enter into new agreements, on favorable terms or at all; NioCorp’s ability to attract qualified management; estimates of mineral resources and reserves; mineral exploration and production activities; feasibility study results; the results of metallurgical testing; the results of technological research; changes in demand for and price of commodities (such as fuel and electricity) and currencies; competition in the mining industry; changes or disruptions in the securities markets; legislative, political or economic developments, including changes in federal and/or state laws that may significantly affect the mining industry; trade policies and tensions, including tariffs; inflationary pressures; the impacts of climate change, as well as actions taken or required by governments related to strengthening resilience in the face of potential impacts from climate change; the need to obtain permits and comply with laws and regulations and other regulatory requirements; the timing and reliability of sampling and assay data; the possibility that actual results of work may differ from projections/expectations or may not realize the perceived potential of NioCorp’s projects; risks of accidents, equipment breakdowns, and labor disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining, or development activities; management of the water balance at the Elk Creek Project site; land reclamation requirements related to the Elk Creek Project; the speculative nature of mineral exploration and development, including the risks of diminishing quantities of grades of reserves and resources; claims on the title to NioCorp’s properties; potential future litigation; and NioCorp’s lack of insurance covering all of NioCorp’s operations.

Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described herein. This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements. Forward-looking statements are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties, and other factors, including without limitation those discussed under the heading “Risk Factors” in our Annual Report on Form 10-K, as well as other factors described elsewhere in this Quarterly Report on Form 10-Q and the Company’s other reports filed with the SEC.

The Company’s forward-looking statements contained in this Quarterly Report on Form 10-Q are based on the beliefs, expectations, and opinions of management as of the date of this Quarterly Report on Form 10-Q. The Company does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations, or opinions should change, except as required by law. For the reasons set forth above, investors should not attribute undue certainty to, or place undue reliance on, forward-looking statements.

Qualified Person

All technical and scientific information that forms the basis for the Elk Creek Project disclosure included in this Quarterly Report on Form 10-Q has been reviewed and approved by Scott Honan, M.Sc., SME-RM, NioCorp’s Chief Operating Officer. Mr. Honan is a “Qualified Person” as such term is defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects and subpart 1300 of Regulation S-K.

Company Overview

NioCorp is developing the Elk Creek Project, located in southeast Nebraska. The Elk Creek Project is a development-stage property that has disclosed niobium, scandium, and titanium reserves and resources and disclosed rare earth mineral resources. The Company is continuing technical and economic studies around the rare earths contained in the Elk Creek Project’s mineral resources in order to determine whether extraction of rare earth elements can be reasonably justified and economically viable after taking into account all relevant factors. Niobium has developing applications in the formulation of solid-state lithium-ion batteries, which may reduce charging times and increase battery safety. Niobium is used to produce various superalloys that are extensively used in high performance aircraft and jet turbines. It also is used in High-Strength, Low-Alloy steel, a stronger steel used in automobiles, bridges, structural systems, buildings, pipelines, and other applications that generally increases strength and/or reduces weight, which can result in environmental benefits, including reduced fuel consumption and material usage and fewer air emissions. Scandium can be combined with aluminum to make high-performance alloys with increased strength and improved corrosion resistance. Scandium also is a critical component of advanced solid oxide fuel cells, an environmentally preferred technology for high-reliability, distributed electricity generation. Titanium is a component of various superalloys and other applications that are used for aerospace applications, weapons systems, protective armor, medical implants, and many others. It also is used in pigments for paper, paint, and plastics. Rare earths are critical to electrification and decarbonization initiatives and can be used to manufacture the strongest permanent magnets commercially available.

Our primary business strategy is to advance our Elk Creek Project to commercial production. We are focused on carrying out our near-term planned work programs associated with securing the project financing package necessary to complete mine development and construction of the Elk Creek Project.

Recent Corporate Events

On July 18, 2025, the Company issued and sold 13,850,000 Common Shares, at an offering price of $3.25 per Common Share, in a registered offering (the “July 2025 Offering”) under the Company’s registration statement on Form S-3 (Registration No. 333-280176), pursuant to the Placement Agency Agreement between the Company and Maxim Group LLC (“Maxim”), dated July 17, 2025. The Company received net proceeds from the July 2025 Offering, after deducting placement agent fees and other offering expenses payable by the Company, of approximately $41.2 million.

On August 5, 2025, the Company announced that we entered into a Project Sub-Agreement (the “DoD Agreement”) with Advanced Technology International (“ATI”), an entity acting on behalf of the Defense Industrial Base Consortium under the authority of the U.S. Department of Defense (“DoD”). Subject to the terms and conditions of the DoD

Agreement, ECRC is entitled to receive up to an aggregate of approximately $10.0 million of reimbursement payments from the DoD upon the achievement of certain project milestones. These milestones include, among other matters, the completion of new drilling operations at the Elk Creek Project to support the conversion of a portion of the current indicated mineral resources into measured mineral resources and the subsequent conversion of a portion of the current probable mineral reserves into proven mineral reserves, the production of samples of scandium metal and scandium-aluminum master alloys, and the completion of a new feasibility study for the Elk Creek Project..

On September 19, 2025, the Company issued and sold 10,000,000 Common Shares, at an offering price of $5.00 per Common Share, in a registered direct offering (the “September 2025 Registered Direct Offering”) under the Company’s registration statement on Form S-3 (Registration No. 333-280176), pursuant to the Placement Agency Agreement between the Company and Maxim, dated September 17, 2025. The Company received net proceeds from the September 2025 Registered Direct Offering, after deducting placement agent fees and other offering expenses payable by the Company, of approximately $46.0 million.

On September 29, 2025, the Company issued and sold (a) 7,004,740 Common Shares at a public offering price of $6.15 per Common Share and (b) 2,755,260 pre-funded Warrants to purchase an aggregate of 2,755,260 Common Shares (the “September Pre-Funded Warrants”) at a public offering price of $6.1499 per September Pre-Funded Warrant in a confidentially marketed public offering (the “September 2025 Public Offering”) under the Company’s registration statement on Form S-3 (Registration No. 333-280176), pursuant to the Placement Agency Agreement between the Company and Maxim, dated September 26, 2025. On September 30, 2025, the Company issued 2,755,218 Common Shares in connection with the cashless exercise of all of the outstanding September Pre-Funded Warrants. The Company received net proceeds from the September 2025 Public Offering, after deducting placement agent fees and other offering expenses payable by the Company, of approximately $55.3 million.

On October 15, 2025, the Company issued and sold (a) 10,152,175 Common shares at an offering price of $9.34 per Common Share and (b) 5,925,000 pre-funded Warrants (the “October Pre-Funded Warrants”) to purchase up to an additional 5,925,000 Common Shares at an offering price of $9.3399 per October Pre-Funded Warrant in a registered offering (the “October 2025 Offering”) under the Company's registration statement on Form S-3 (Registration No. 333-290837), pursuant to the Placement Agency Agreement between the Company and Maxim, dated October 13, 2025. On October 17, 2025, the Company issued 5,924,942 Common Shares in connection with the cashless exercise of all of the outstanding October Pre-Funded Warrants. The Company received net proceeds from the October 2025 Offering, after deducting placement agent fees and other offering expenses payable by the Company, of approximately $139.1 million.

The Company intends to use the net proceeds from the July 2025 Offering, September 2025 Registered Direct Offering, September 2025 Public Offering, and October 2025 Offering for working capital and general corporate purposes, including to advance its efforts to launch construction of the Elk Creek Project and move it to commercial operation.

Elk Creek Project Update

On August 1, 2025, Elk Creek Resources Corp. (“ECRC”), an indirect, majority-owned subsidiary of the Company, closed on its option to purchase three parcels of land in Johnson County, Nebraska (the “August Properties”), pursuant to the terms of the Option to Purchase, dated as of December 4, 2009, as amended (the “2009 Option Agreement”), and the Option to Purchase, dated December 4, 2014, as amended (the “2014 Option Agreement” and together with the 2009 Option Agreement, the “August Option Agreements”), each between Roger and Nancy Woltemath and ECRC. Pursuant to the terms of the August Option Agreements, Roger and Nancy Woltemath sold, transferred, conveyed and assigned to ECRC all of their rights, privileges, title and interest in and to the surface rights with respect to one of the parcels (consisting of the property known as Woltemath80S) and to the surface rights and associated mineral rights with respect to a 1.66-acre parcel. The purchase price was approximately $2.7 million, including indirect costs of $35,000.

On September 8, 2025, the Company announced the successful completion of its previously announced drilling program at the Elk Creek Project (the “2025 Drilling Program”). The 2025 Drilling Program was divided into two phases. Phase I of the 2025 Drilling Program comprised 11 HQ diamond drill holes totaling approximately 7,339 meters and Phase II of the 2025 Drilling Program comprised four HQ diamond drill holes totaling approximately 2,235 meters. Two additional geomechanical drill holes totaling approximately 1,950 meters were also completed as part of an accelerated effort to support the underground mine design related to access ramp development. Assays of the drill holes completed during the 2025 Drilling Program are underway at external laboratories.

The 2025 Drilling Program and associated technical work is designed to support the conversion of a portion of the Elk Creek Project's Indicated Mineral Resources into Measured Mineral Resources and the subsequent conversion of a portion of its Probable Mineral Reserves into Proven Mineral Reserves. The 2025 Drilling Program was designed to help meet Mineral Resource and Mineral Reserve classification requirements associated with the ongoing review of the Company's application for up to $800 million in potential debt financing by EXIM, as further discussed under “—Liquidity and Capital Resources.”

On September 30, 2025, ECRC closed on its options to purchase two parcels of land in Johnson County, Nebraska, which include: (i) a portion of the property known as Woltemath002, consisting of approximately 105.77 acres of land (the “Woltemath002 Property”), pursuant to the terms of the 2009 Option Agreement and (ii) the property known as Woltemath003J, consisting of approximately 220 acres of land (the “Woltemath003J Property” and, together with the Woltemath002 Property, the “ September Properties”), pursuant to the terms of the Amended and Restated Option to Purchase, dated January 4, 2017, as amended, between Victor and Juanita Woltemath (together with Roger and Nancy Woltemath, the “Owners”) and ECRC (the “2017 Option Agreement” and, together with the 2009 Option Agreement, the “September Option Agreements”). Pursuant to the terms of the September Option Agreements, the Owners sold, transferred, conveyed and assigned to ECRC all of their respective rights, privileges, title and interest in and to the surface rights and associated mineral rights, which consisted of approximately 325.77 acres of the property. The aggregate purchase price was approximately $11.3 million, including indirect costs of $29,000. This acquisition provides NioCorp with ownership of all land that hosts the Elk Creek Project’s Mineral Resource and Mineral Reserve and all acreage necessary to commence construction once project financing is obtained.

On November 7, 2025, ECRC completed the acquisition of a 40-acre parcel of land and associated mineral rights (the “November Property”) located within the one-square-mile section that comprises the Elk Creek Project area. The acquisition was completed in exchange for (i) the transfer of surface rights to a separate 40-acre tract constituting a portion of the September Properties, which lies outside the Elk Creek Project section, (ii) cash consideration of $500, and (iii) the grant of a 2% net smelter return royalty on the November Property. As a result of this transaction, the Company now holds full ownership of all surface rights within the one-square-mile section in which it plans to construct both the underground critical minerals mine and integrated surface processing facility associated with the Elk Creek Project.

Other Activities

The Company continues to execute a work plan to further advance the development of the Elk Creek Project. In addition to the expected updates to Mineral Resources and Mineral Reserves, noted above, the Company expects to finalize engineering and costing of its new and more efficient production process which incorporates the potential addition of light and heavy magnetic rare earth oxides, the planned production of titanium in the form of titanium tetrachloride, and the potential to produce both ferroniobium and niobium oxide as commercial products. In addition, the Company is advancing engineering to potentially modify the design of the mine to incorporate a twin ramp for access along with a Railveyor system for material movement instead of utilizing vertical mining shafts. The updated mine design is expected to also incorporate updated costing. This work is expected to be summarized in an updated feasibility study for the Elk Creek Project.

In addition to the work plans noted above, as funds become available through the Company’s fundraising efforts, the Company expects to undertake the following activities to further advance the Elk Creek Project and the Company is assessing and prioritizing the timing of these efforts:

  • Continued evaluation of the potential to produce rare earth products and sell such products under offtake agreements;
  • Negotiation and completion of offtake agreements for the remaining uncommitted production of niobium, scandium, and titanium from the Elk Creek Project, including the potential sale of titanium as titanium tetrachloride, as well as potential rare earth element production;
  • Negotiation and completion of engineering, procurement, and construction agreements;
  • Hiring of personnel to manage the Company’s responsibilities for construction and operations;
  • Completion of the final detailed engineering for the underground portion of the Elk Creek Project;
  • Initiation and completion of the final detailed engineering for surface project facilities;
  • Construction of natural gas and electrical infrastructure to serve the Elk Creek Project site;
  • Completion of water supply agreements and related infrastructure to deliver fresh water to the Elk Creek Project site;
  • Continuation of mine groundwater investigation and control activities;
  • Initiation of long-lead equipment procurement activities;
  • Continuation of the Company’s efforts to secure additional federal, state, and local operating permits;

21

  • Completion of the characterization and testing of waste materials to support tailings impoundment and paste backfill plant designs; and
  • Continued engineering and costing of road improvements near the junction of Nebraska state highways 50 and 62, which are intended to facilitate access to the Elk Creek Project site and manage increased traffic in the project vicinity.

Financial and Operating Results

The Company has no revenues from mining operations. Operating expenses incurred primarily related to costs incurred for the advancement of the Elk Creek Project and the activities necessary to support corporate and shareholder duties and are detailed in the following table.

Operating expenses For the Three Months Ended September 30, 2025 2024
Employee-related costs $2,216 $330
Professional fees 875 450
Exploration expenditures 7,084 138
Other operating expenses 1,843 477
Total operating expenses 12,018 1,395
Change in fair value of Earnout Shares liability 14,496 816
Change in fair value of warrant liabilities 17,558 (56)
Change in fair values of convertible notes - 17
Interest expense - 44
Foreign exchange (gain) loss (5) 8
Interest income (560) -
Other gains - (122)
Income tax benefit - -
Net loss and comprehensive loss (43,507) (2,102)
Less: Loss attributable to noncontrolling interest (848) (31)
Net loss attributable to the Company $(42,659) $(2,071)
Net loss per share attributable to the Company $(0.53) $(0.05)
Adjusted net loss $(8,307) $(1,407)
Adjusted net loss per share $(0.07) $(0.03)

Three-month period ended September 30, 2025 compared to the three-month period ended September 30, 2024

Significant items affecting operating expenses are noted below:

Employee-related expenditures increased for the three-month period in 2025 as compared to 2024 primarily due to the timing of options issued to employees in 2025.

Professional fees increased for the three-month period in 2025 as compared to 2024, primarily due to higher costs incurred in 2025 related to the timing of legal services associated with the preparation of the Company’s SEC registration statements filed in October 2025.

Exploration expenditures increased for the three-month period in 2025 as compared to 2024, primarily due to expenditures associated with the 2025 Drilling Program.

Other operating expenses include costs related to investor relations, general office expenditures, shareholder services and proxy expenditures, board-related expenditures, and other miscellaneous costs. These costs increased for the three-month period in 2025 as compared to 2024 primarily due to the timing of fully vested options to purchase

Common Shares (“Options”) issued to board members and advisors in 2025 and increases in investor-facing services and stipend payments provided to board members.

Other significant items impacting the change in the Company’s net loss and net loss per share are noted below:

Change in fair value of Earnout Shares liability represents the changes in fair value related to the shares of Class B common stock of ECRC, the rights of the holders of which to exchange such shares into Common Shares are subject to certain vesting conditions (such shares of ECRC Class B common stock, the “Earnout Shares”). The 2025 expense represents the impact of an increase in the Company’s Common Share price on the financial modeling used to determine the period end fair values, whereas the 2024 gain represents the impact of a lower share price on the financial modeling results.

Change in fair value of warrant liabilities represents the changes in fair value of Warrants that are carried as liabilities in the condensed consolidated balance sheet. Expense for the three-month period ending September 30, 2025, reflects the impact of an increase in the Company’s Common Share price on the Black-Scholes modeling results for our outstanding Warrant liabilities, whereas the 2024 gain primarily represents the impact of a lower share price on the modeling at period end.

Interest income represents earnings from the investment of excess cash balances in a commercial money market account. The increase for the three-month period in 2025 as compared to 2024 is due to an increase in our cash balance resulting from our successful financing efforts during calendar year 2025.

Loss attributable to noncontrolling interest represents the portion of net loss in ECRC not owned by the Company. The increase in loss for the three-month period in 2025 as compared to 2024 is related to the increased exploration expenditures, as noted above, incurred by ECRC.

Adjusted net loss and adjusted net loss per share both increased for the three-month period in 2025, as compared to 2024, primarily due to the increase in exploration expenditures, as noted above, incurred by ECRC.

Liquidity and Capital Resources

We have no revenue generating operations from which we can internally generate funds. To date, our ongoing operations have been financed by the sale of our equity securities by way of public and private offerings, convertible securities issuances, the exercise of Options and Warrants, and related party loans. With respect to currently outstanding Options and Warrants, we believe that exercise of these instruments, and cash proceeds from such exercises, will not occur unless and until the market price for our Common Shares equals or exceeds the related exercise price of each instrument.

As discussed above under “—Recent Corporate Events”, the Company closed four equity offering transactions between July 18, 2025 and October 15, 2025. The combined net proceeds from these offerings were approximately $194.4 million, after deducting placement agency fees and other offering expenses payable by the Company. In addition, during the three-month period ended September 30, 2025, the Company issued an aggregate of 10,975,634 Common Shares through the exercise of Warrants and Options by their holders, for which the Company received proceeds totaling approximately $15.2 million. The Company expects to use these net proceeds for working capital and general corporate purposes, including to advance efforts to launch construction of the Elk Creek Project and move it to commercial operation.

As of September 30, 2025, the Company had cash of $162.8 million and working capital of $159.6 million, compared to cash of $25.6 million and working capital of $24.8 million on June 30, 2025.

We expect that the Company will operate at a loss for the foreseeable future. The Company’s current planned cash outflows are approximately $40.0 million to $50.0 million for the next twelve months. Our planned cash outflows over the next twelve months are expected to consist of expenditures relating to limited, incremental activities to advance certain aspects of the Elk Creek Project by NioCorp’s majority owned subsidiary, ECRC, corporate overhead costs, and estimated costs related to securing financing necessary for advancement of the Elk Creek Project. These planned expenditures include expenditures relating to the anticipated completion of an updated resource and reserve estimate and associated mine plan and an updated capital cost estimate in connection with the EXIM application process, ongoing engineering and metallurgical test work, environmental and permitting activities, community and stakeholder engagement programs, corporate and administrative overhead, and advisory costs related to securing project financing.

The Company will need to secure additional capital to finance construction and achieve commercial production to support its long-term business objectives. Until sufficient funding for construction is secured, the Company expects to limit activities to modest, value-preserving work and project readiness efforts. The Company also intends to evaluate strategies and potential investment opportunities that could reduce overall project costs, capital requirements, or execution risk.

The planned corporate overhead costs over the next twelve months are approximately $11.0 million, including Elk Creek property lease commitments, which are $65,000 through June 30, 2026, and the settlement of outstanding accounts payable as of September 30, 2025.

The estimated financing costs associated with the Elk Creek Project over the next twelve months include, but are not limited to, costs relating to the EXIM application process, the scope of which remains under discussion with EXIM. On June 6, 2023, the Company announced that it had submitted an application to EXIM for up to $800 million in debt financing (the “EXIM Financing”) to fund the project costs for the Elk Creek Project, under EXIM’s “Make More in America” initiative. The EXIM Financing is subject to, among other matters, the satisfactory completion of due diligence, the negotiation and settlement of final terms, and the negotiation of definitive documentation. The Company was informed that its application received approval by the first of three reviews by the EXIM Transaction Review Committee (the “TRC”) on October 2, 2023. In April 2024, EXIM provided the Company with a preliminary, non-binding indicative term sheet as part of a Preliminary Project Letter (the “PPL”), which also conveyed EXIM’s initial due diligence findings on the Company’s application for the EXIM Financing. The PPL identified additional project activities to be undertaken by the Company as part of EXIM’s due diligence process. These included, among other things, an updated mine plan and updated Elk Creek Project capital costs on a final or close-to-final basis reflecting updated process flows. The 2025 Drilling Program, which started in April 2025, was designed to help meet mineral resource and mineral reserve classification requirements necessary to complete certain of the additional project activities identified by the PPL. In addition, as previously disclosed, the Company took an additional step in the process by executing a professional services agreement with SLR Consulting to conduct an independent environmental and social review as part of EXIM’s ongoing project due diligence.

The Company continues to meet with EXIM, provide responses to requests for additional information from EXIM and to the consultants that are conducting due diligence on the Company’s application on behalf of EXIM and take steps to complete the additional project activities identified by the PPL. There can be no assurance as to what further project activities or matters EXIM may request in connection with the application process. We are currently unable to estimate how long the application process may take, and there can be no assurances that we will be able to successfully negotiate a final commitment of debt financing from EXIM.

We expect our cash balance as of September 30, 2025, as well as the net proceeds from the October 2025 Offering, the proceeds from Warrant and Option exercises that occurred since September 30, 2025, and the reimbursement payments pursuant to the DoD Agreement, to be sufficient to fund our planned expenditures for the next twelve months. However, additional work is required in order to advance the Elk Creek Project to construction, requiring additional financing. The technical report summary for the Elk Creek Project prepared in accordance with subpart 1300 of Regulation S-K (“S-K 1300”) and filed as Exhibit 96.1 to the Company’s Annual Report on Form 10-K for the fiscal year ended June 30, 2025, includes an estimated total upfront capital expenditure for the Elk Creek Project of approximately $1,141.0 million. The actual amount of capital expenditure required to successfully achieve commercial production at the Elk Creek Project is subject to, among other factors, the timing and actual cost of further exploration, preparing feasibility studies, permitting, engineering and the construction of infrastructure, mining and processing facilities. In addition, to the extent that EXIM requests further project activities to be undertaken in connection with the diligence process, the Company would require additional funding to complete such activities. As noted above, the Company’s ability to continue operations, fund our current work plan, and construct and operate the Elk Creek Project is dependent on management’s ability to secure additional financing. When available, the Yorkville Equity Facility Financing Agreement provides an opportunity for opportunistic share sales to help fund our current work plan. However, the Yorkville Equity Facility Financing Agreement will expire by its terms on April 1, 2026.

Except for the potential funding from advances under the Yorkville Equity Facility Financing Agreement, as discussed above, and the potential exercise of Options and Warrants, we currently have no further funding commitments or arrangements for additional financing at this time. Management currently anticipates that it will fund the upfront capital expenditure amount for the Elk Creek Project through a combination of debt and equity financing, with approximately two-thirds of such amount being funded from the net proceeds of debt financing, including the amount of debt that would be represented by the EXIM Financing, if any. Management is actively pursuing additional sources of debt and equity financing to meet its long-term funding requirements, and while it has been successful in doing so in the past, there is no assurance that we will be able to obtain any such additional financing on acceptable terms, if at all. Pursuant to the Exchange Agreement, dated as of March 17, 2023 (as amended, supplemented or otherwise modified, the “Exchange Agreement”), by and among NioCorp, ECRC and GX Sponsor II LLC, NioCorp is restricted from issuing equity or equity-linked securities (other than Common Shares) or any preferred equity or non-voting equity if such issuance would adversely impact the rights of the holders of the shares of Class B common stock of ECRC, without the consent of the holders of a majority of the shares of Class B common stock of ECRC. The various placement agency agreements entered into with Maxim in connection with the equity offerings described above under “—Recent Corporate Events,” including the October 2025 Placement Agency Agreement, also contain certain covenants that, among other things, limit NioCorp’s ability to enter into any variable rate transaction on or before November 28, 2025, including issuances of equity or debt securities that are convertible into Common Shares at variable rates and any equity line of credit, at-the-market offering agreement, or other continuous offering of Common Shares, other than with Maxim, subject to certain exceptions. Notwithstanding the restrictions set forth in the Exchange Agreement, as well as the various placement agency agreements, there is significant uncertainty that we would be able to secure any additional financing in the current equity or debt markets. The quantity of funds to be raised and the terms of any proposed equity or debt financing that may be undertaken will be negotiated by management as opportunities to raise funds arise. Management may pursue funding sources of both debt and equity financing, including but not limited to the issuance of equity securities in the form of Common Shares, Warrants, subscription receipts, or any combination thereof in units of the Company pursuant to private placements to accredited investors or pursuant to public offerings in the form of underwritten/brokered offerings, registered direct offerings, or other forms of equity financing and public or private issuances of debt securities, including secured and unsecured convertible debt instruments, or secured debt project financing. Management does not currently know the terms pursuant to which such financings may be completed in the future, but any such financings will be negotiated at arm’s-length. Future financings involving the issuance of equity securities or derivatives thereof will likely be completed at a discount to the then-current market price of the Company’s securities and will likely be dilutive to current shareholders. In addition, we could raise funds through the sale of interests in our mineral properties, although current market conditions and other recent worldwide events have substantially reduced the number of potential buyers/acquirers of any such interests. However, we cannot provide any assurances that we will be able to be successful in raising such funds.

As defined under S-K 1300, we are a development stage issuer and we have incurred losses since our inception. The Company will require additional capital to meet its long-term operating requirements. Uncertainty in capital markets, supply chain disruptions, increased interest rates and inflation, and the potential for geographic recessions have contributed to general global economic uncertainty. During the three-month period ended September 30, 2025, these events continued to create uncertainty with respect to overall project funding and timelines. The Company will need to secure additional capital to finance construction and achieve commercial production to support its long-term business objectives.

We have no exposure to any asset-backed commercial paper. Other than cash held by our subsidiaries for their immediate operating needs in Colorado and Nebraska, all of our cash reserves are on deposit with major U.S. and Canadian chartered banks. We do not believe that the credit, liquidity, or market risks with respect thereto have increased as a result of the current market conditions. However, in order to achieve greater security for the preservation of our capital, we have, of necessity, been required to accept lower rates of interest, which has also lowered our potential interest income.

Operating Activities

During the three months ended September 30, 2025, the Company’s operating activities consumed $6.7 million of cash (2024: $0.6 million). The cash used in operating activities for the three months ended September 30, 2025, reflects the Company’s funding of losses of $43.5 million, primarily resulting from increased fair value related to the Earnout

Shares and Warrant liabilities, share-based compensation, and other non-cash transactions. Overall, operational outflows during the three months ended September 30, 2025, increased from the corresponding period of 2024 due to costs and expenditures incurred in connection with the 2025 Drilling Program. Going forward, the Company’s working capital requirements are expected to increase substantially in connection with the development of the Elk Creek Project.

Investing Activities

During the three months ended September 30, 2025, the Company’s investing activities consumed $14.1 million of cash (2024: $0). The cash used in investing activities for the three months ended September 30, 2025, reflects the acquisition of additional land and mineral rights for the Elk Creek Project.

Financing Activities

Financing inflows were $158.0 million during the three months ended September 30, 2025 (2024 outflows: $1.2 million), with 2025 inflows reflecting the gross receipts of $155.0 million from the equity offerings, and $15.3 million from Warrant exercises, offset by $12.3 million of share issuance costs.

Cash Flow Considerations

The Company has historically relied upon debt and equity financings to finance its activities. Subject to the restrictions set forth in the Exchange Agreement and the various placement agency agreements with Maxim, the Company may pursue additional debt and/or equity financing in the medium term; however, there can be no assurance the Company will be able to obtain any required financing in the future on acceptable terms, or at all.

The Company has limited financial resources compared to its proposed expenditures, no source of operating income, and no assurance that additional funding will be available to it for current or future projects, although the Company has been successful in the past in financing its activities through the sale of equity securities.

The ability of the Company to arrange additional financing in the future will depend, in part, on the prevailing capital markets conditions, and its success in developing the Elk Creek Project. Any quoted market for the Common Shares may be subject to market trends generally, notwithstanding any potential success of the Company in creating revenue, cash flows, or earnings, and any depression of the trading price of the Common Shares could impact its ability to obtain equity financing on acceptable terms.

Historically, the Company has used net proceeds from issuances of Common Shares to provide sufficient funds to meet its near-term exploration and development plans and other contractual obligations when due. However, development and construction of the Elk Creek Project will require substantial additional capital resources. This includes funding for Elk Creek Project construction and other costs. See “—Liquidity and Capital Resources” above for the Company’s discussion of arrangements related to possible future financings.

Critical Accounting Estimates

There have been no material changes in our critical accounting estimates discussed in “Management’s Discussion and Analysis of Financial Condition and Results of Operations” under the heading “Critical Accounting Estimates and Recent Accounting Pronouncements” as of June 30, 2025, in the Annual Report on Form 10-K.

Use of Non-GAAP Financial Measures and Reconciliations

The Company has included certain non-GAAP financial measures in this Quarterly Report on Form 10-Q such as adjusted net loss and adjusted net loss per share. Adjusted net loss for presentation purposes is our net loss attributable to the Company plus non-cash items plus (gain)/loss on non-recurring items plus tax adjustments. Adjusted net loss per share is the impact of these adjustments on the per share net losses incurred. These non-GAAP measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance U.S. GAAP. Because these non-GAAP performance measures do not have any standardized meaning prescribed by U.S. GAAP, they may not be comparable to similar measures presented by other companies. The Company’s management believes that presenting adjusted net loss and adjusted net loss per share provides investors with additional insight into underlying operating performance by excluding the non-cash losses noted above. Our presentation of certain non-GAAP financial measures should not be construed to imply that our future results will be unaffected by the types of items excluded from the calculations of non-GAAP measures. These non-GAAP measures are not presented in accordance with U.S. GAAP and the use of these terms vary from others in our industry.

Reconciliations of net loss attributable to the Company to adjusted net loss and net loss per share attributable to the Company to adjusted net loss per share are presented below:

For the Three Months Ended September 30, 2025 2024
Net loss attributable to the Company $(42,659) $(2,071)
Adjustments:
Change in fair value of earnout liability 14,496 816
Change in fair value of warrant liability 17,558 (56)
Share based compensation 2,302 -
Other gains (4) (96)
Adjusted net loss $(8,307) $(1,407)
Net loss per share attributable to the Company $(0.53) $(0.05)
Adjustments:
Change in fair value of earnout liability 0.19 0.02
Change in fair value of warrant liability 0.24 -
Share based compensation 0.03 -
Other gains - -
Adjusted net loss per share $(0.07) $(0.03)

Certain U.S. Federal Income Tax Considerations

If NioCorp (or a subsidiary) is a PFIC for any taxable year (or portion thereof) that is included in the holding period of a U.S. holder of Common Shares or other NioCorp securities (as determined under applicable U.S. federal income tax law), then certain significant adverse tax consequences could apply to such U.S. holder, including requirements to treat any gain realized upon a disposition of Common Shares (or other securities) as ordinary income, to include certain “excess distributions” on Common Shares in income, and to pay an interest charge on a portion of any such gain or distribution. NioCorp believes that it was classified as a PFIC during the taxable years ended June 30, 2025 and 2024, and, based on the current composition of its income and assets, as well as current business plans and financial expectations, that it may be classified as a PFIC for its current taxable year or in future taxable years. No opinion of legal counsel or ruling from the Internal Revenue Service (the “IRS”) concerning the PFIC status of NioCorp or any subsidiary has been obtained or is currently planned to be requested. The determination of whether any corporation was, or will be, a PFIC for a taxable year depends, in part, on the application of complex U.S. federal income tax rules, which are subject to differing interpretations. In addition, whether any corporation will be a PFIC for any taxable year depends on the assets and income of such corporation over the course of each such taxable year and, as a result, cannot be predicted with certainty as of the date of this Quarterly Report on Form 10-Q. In addition, even if NioCorp concluded that it or any subsidiary was not classified as a PFIC, the IRS could challenge such determination and a court could sustain the challenge. Accordingly, there can be no assurance that NioCorp or any subsidiary will not be classified as a PFIC for any taxable year. Each holder of Common Shares or other NioCorp securities should consult its own tax advisors regarding the PFIC status of NioCorp and each subsidiary thereof and the resulting tax consequences to the holder, as well as any potential to mitigate such tax consequences through a “QEF” or “mark-to-market” election. See the “Risk Factors” section of the Annual Report on Form 10-K.

Other

The Company has one class of shares, being Common Shares. A summary of outstanding Common Shares, Options, and Warrants as of November 13, 2025, is set out below, on a fully diluted basis.

Common Shares Outstanding (Fully Diluted)
Common Shares 119,360,725
Vested shares of ECRC Class B common stock (1) 3,518,450
Options (2) 4,777,500
Warrants (3) 19,338,512

(1) Each exchangeable into one Common Share at any time, and from time to time, until March 17, 2033.

(2) Each exercisable into one Common Share.

(3) Includes 15,666,526 NioCorp Assumed Warrants that are each exercisable into 1.11829212 Common Shares and 3,671,986 Warrants that are each exercisable into one Common Share.

Market risk

As filed, 1,245 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Interest rate risk

The Company’s exposure to changes in market interest rates relates primarily to the Company’s earned interest income on cash deposits and short-term investments. The Company maintains a balance between the liquidity of cash assets and the interest rate return thereon. The carrying amount of financial assets, net of any provisions for losses, represents the Company’s maximum exposure to credit risk.

Foreign currency exchange risk

The Company incurs expenditures in both U.S. dollars and Canadian dollars. Canadian dollar expenditures are primarily related to certain Common Share-related costs and corporate professional services. As a result, currency exchange fluctuations may impact the costs of our operating activities. To reduce this risk, we maintain sufficient cash balances in Canadian dollars to fund expected near-term expenditures.

Commodity price risk

The Company is exposed to commodity price risk related to the elements associated with the Elk Creek Project. A significant decrease in the global demand for these elements may have a material adverse effect on our business. The Elk Creek Project is not in production, and the Company does not currently hold any commodity derivative positions.

Controls and procedures

As filed, 7,909 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Disclosure Controls and Procedures

The management of NioCorp Developments Ltd. has evaluated, under the supervision of and with the participation of the Chief Executive Officer (“CEO”) and the Chief Financial Officer (“CFO”), the effectiveness of our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act) as of September 30, 2025. Based on that evaluation, the CEO and the CFO have concluded that, as of September 30, 2025, our disclosure controls and procedures were not effective due to the material weaknesses in internal control over financial reporting described below.

Notwithstanding the material weaknesses in our internal control over financial reporting, our CEO and CFO have concluded that the interim condensed consolidated financial statements included in this Quarterly Report on Form 10-Q fairly present, in all material respects, our financial position, results of operations and cash flows for the periods presented in conformity with U.S. GAAP.

Material Weaknesses in Internal Control over Financial Reporting Existing as of September 30, 2025

The management of NioCorp Developments Ltd. is responsible for establishing and maintaining adequate internal control over financial reporting as defined in Rules 13a-15(f) and 15d-15(f) of the Exchange Act for the Company. Management assessed the effectiveness of our internal control over financial reporting as of September 30, 2025. In making this assessment, our management used the criteria set forth in the Internal Control - Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission (the “COSO Framework”). Based on that evaluation, the CEO and the CFO have concluded that, as of September 30, 2025, our internal control over financial reporting was not effective due to the material weaknesses in internal control over financial reporting described below.

Material Weaknesses

A material weakness is a deficiency, or a combination of deficiencies, in internal control over financial reporting, such that there is a reasonable possibility that a material misstatement of our annual or interim consolidated financial statements will not be prevented or detected on a timely basis.

Management concluded that the material weaknesses disclosed in the Company’s Annual Report on Form 10-K for the fiscal year ended June 30, 2025, continued to exist as of September 30, 2025. Specifically, management identified deficiencies in the principles associated with the control environment, risk assessment, control activities, and monitoring components of internal control, based on the criteria established by the COSO Framework, that constitute material weaknesses, either individually or in the aggregate.

  • Control Environment: The Company does not have sufficient personnel with the appropriate levels of knowledge, experience, and training in accounting and internal control over financial reporting commensurate with the complexity of the Company’s financing transactions and associated reporting requirements. This material weakness contributed to additional material weaknesses further described below.
  • Risk Assessment: The Company does not have a formal process to identify, update, and assess financial reporting risks due to changes in the Company’s business practices, including entering into increasingly complex transactions that could significantly impact the design and operation of the Company’s control activities.
  • Control Activities: Management did not maintain effective controls over:
  • monitoring and assessing the work of third-party specialists, including the evaluation of the appropriateness of accounting conclusions,
  • the evaluation of certain inputs and assumptions used to estimate the fair value of instruments and features associated with complex debt and equity transactions, and
  • the design and implementation of effective process-level control activities related to vendor banking information.
  • Monitoring Activities: Management did not appropriately:
  • select, develop, and perform ongoing evaluation to ascertain whether the components of internal controls are present and functioning, and
  • evaluate and communicate internal control deficiencies in a timely manner to those parties responsible for taking corrective action.

As previously disclosed, these material weaknesses resulted in errors that required the restatement of Company’s consolidated financial statements as of and for the fiscal years ended June 30, 2022 and 2021, as well as the restatement of the Company’s condensed consolidated financial statements as of and for the interim periods ended September 30, 2021, December 31, 2021, March 31, 2022, September 30, 2022, and December 31, 2022. Additionally, these material weaknesses could result in a misstatement of the account balances or disclosures that would result in a material misstatement to the annual or interim consolidated financial statements that would not be prevented or timely detected.

Remediation Plan for the Material Weaknesses

To address our material weaknesses existing as of September 30, 2025, we have implemented a detailed plan to address each individual material weakness identified, including the following:

  • We have and will continue to engage outside accounting and internal control consultants with subject matter expertise to supplement our level of knowledge, experience, and training in accounting and internal control over financial reporting.
  • We have developed a formal risk assessment process requiring periodic review and updates of current risks and internal controls, as well as a focus on potential future events that could result in additional risks and/or internal control lapses. This process is expected to enable us to effectively identify, develop, evolve, and implement controls and procedures to address risks, and results of this risk assessment process will be reviewed with the Audit Committee on a periodic basis.
  • We have hired additional personnel to assist with the monitoring and review of internal control functions.
  • We have developed an initial training plan to provide incremental training to accounting and finance personnel responsible for overall technical accounting and valuation-related transactions.
  • Management is developing a monitoring program to periodically evaluate and assess whether those responsible for controls are conducting their activities in accordance with their design, such that there is contemporaneous evidence that the components of internal control are present and functioning and will communicate internal control deficiencies in a timely manner to those parties responsible for taking corrective action.

The process of designing and maintaining effective internal control over financial reporting is a continuous effort that requires management to anticipate and react to changes in our business, economic, and regulatory environments and to expend significant resources. As we continue to evaluate our internal control over financial reporting, we may take additional actions to remediate the material weaknesses or modify the remediation actions described above.

While we continue to devote significant time and attention to these remediation efforts, the material weaknesses will not be considered remediated until management completes the design and implementation of the actions described above and the controls operate for a sufficient period of time, and management has concluded, through testing, that these controls are effective.

Changes in Internal Control over Financial Reporting

Other than as discussed above, there has been no change in our internal control over financial reporting during the quarter ended September 30, 2025, that has materially affected, or is reasonably likely to materially affect, our internal control over financial reporting.

Risk factors

As filed, 124 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

There have been no changes to the risk factors set forth under the heading “Risk Factors” in the Annual Report on Form 10-K.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2025-09-30. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Net income3 months2025-07-01 to 2025-09-30−$43.5mus-gaap:NetIncomeLoss
Operating cash flow3 months2025-07-01 to 2025-09-30−$6.7mus-gaap:NetCashProvidedByUsedInOperatingActivities
Cash and equivalentsAt period end2025-09-30$162.8mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2025-09-30$163.5mus-gaap:AssetsCurrent
Total assetsAt period end2025-09-30$194.7mus-gaap:Assets
Current liabilitiesAt period end2025-09-30$4.0mus-gaap:LiabilitiesCurrent
Total liabilitiesAt period end2025-09-30$43.2mus-gaap:Liabilities
Shareholders' equityAt period end2025-09-30$151.5mus-gaap:StockholdersEquity

Source: SEC EDGAR, the filing index for accession 0001539497-25-002940. Last ingested by Listed: Nov 11, 2026, 03:00 ET. Listed shows no prices and gives no investment advice.