Management's discussion and analysis

As filed, 57,976 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following discussion summarizes the financial position of Argan, Inc. and its subsidiaries as of April 30, 2021, and the results of their operations for the three-month periods ended April 30, 2021 and 2020, and should be read in conjunction with (i) the unaudited condensed consolidated financial statements and notes thereto included elsewhere in this Quarterly Report on Form 10-Q and (ii) the consolidated financial statements and accompanying notes included in our Annual Report on Form 10-K for Fiscal 2021 that was filed with the SEC on April 14, 2021 (the “Annual Report”).

Cautionary Statement Regarding Forward Looking Statements

The Private Securities Litigation Reform Act of 1995 provides a “safe harbor” for certain forward-looking statements. We have made statements in this Item 2 and elsewhere in this Quarterly Report on Form 10-Q that may constitute “forward-looking statements.” The words “believe,” “expect,” “anticipate,” “plan,” “intend,” “foresee,” “should,” “would,” “could,” or other similar expressions are intended to identify forward-looking statements. Our forward-looking statements, including those relating to the potential effects of the COVID-19 pandemic on our business, financial position and results of operations, are based on our current expectations and beliefs concerning future developments and their potential effects on us.

There can be no assurance that future developments affecting us will be those that we anticipate. All comments concerning our expectations for future revenues and operating results are based on our forecasts for existing operations and do not include the potential impact of any future acquisitions.

Our forward-looking statements, by their nature, involve significant risks and uncertainties (some of which are beyond our control) and assumptions. They are subject to change based upon various factors including, but not limited to, the risks and uncertainties described in this Quarterly Report on Form 10-Q and our Annual Report. Should one or more of these risks or uncertainties materialize, or should any of our assumptions prove to be incorrect, actual results may vary in material respects from those projected in the forward-looking statements. We undertake no obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events or otherwise.

Business Description

Argan is a holding company that conducts operations through its wholly-owned subsidiaries, GPS, APC, SMC and TRC. Through GPS and APC, we provide a full range of engineering, procurement, construction, commissioning, operations management, maintenance, development, technical and consulting services to the power generation market, including the renewable energy sector, for a wide range of customers, including independent power project owners, public utilities, equipment suppliers and global energy plant construction firms. GPS and APC represent our power industry services reportable segment. Through TRC, the industrial fabrication and field services reportable segment provides on-site services that support maintenance turnarounds, shutdowns and emergency mobilizations for industrial plants primarily located in the southeastern region of the US and that are based on its expertise in producing, delivering and installing fabricated steel components such as piping systems and pressure vessels. Through SMC Infrastructure Solutions, the telecommunications infrastructure services segment provides project management, construction, installation and maintenance services to commercial, local government and federal government customers primarily in the mid-Atlantic region of the US.

We intend to make additional opportunistic acquisitions and/or investments by identifying companies with significant potential for profitable growth and realizable synergies with one or more of our existing businesses. However, we may have more than one industrial focus depending on the opportunity. We expect that acquired companies will be maintained in separate subsidiaries that will be operated in a manner that best provides cash flows for the Company and value for our stockholders.

Overview

Operating Results

Consolidated revenues for the three months ended April 30, 2021 were $126.3 million, which represented an increase of $66.2 million, or 110.1%, from consolidated revenues of $60.1 million reported for the three months ended April 30, 2020.

The revenues of the power industry services segment increased by $48.6 million to $97.2 million for the three months ended April 30, 2021, from $48.6 million reported for the three months ended April 30, 2020. The revenues of this reportable segment of our business represented 76.9% of consolidated revenues for the three months ended April 30, 2021. For the three months ended April 30, 2020, the percentage share of consolidated revenues represented by this reportable segment was 80.8%. The industrial services business of TRC reported revenues of $26.7 million for the three months ended April 30, 2021. This amount represented an increase of $16.9 million, or 173.6%, from revenues of $9.7 million reported by TRC for the three months ended April 30, 2020. Revenues provided by this reportable business segment represented 21.1% and 16.2% of corresponding consolidated revenues for the three months ended April 30, 2021 and 2020, respectively.

Consolidated gross profit for the three-month period ended April 30, 2021 was $23.7 million, or 18.8% of the corresponding consolidated revenues, which reflected primarily the favorable impacts of the higher amount of consolidated revenues and favorable contributions from all three reportable business segments. For the three-month period ended April 30, 2020, the consolidated gross profit was $4.0 million, which represented approximately 6.7% of the corresponding amount of consolidated revenues and reflected $2.7 million of subcontract loss related to APC’s TeesREP project.

Selling, general and administrative expenses for the three months ended April 30, 2021 and 2020 were $9.9 million, or 7.8% of corresponding consolidated revenues, and $10.3 million, or 17.2% of corresponding consolidated revenues, respectively.

Due primarily to the consolidated pre-tax book income reported for the three-month period ended April 30, 2021 in the amount of $14.5 million, we reported income tax expense in the amount of $3.8 million for the period. For the three-month period ended April 30, 2020, we recorded an income tax benefit in the amount of $4.5 million which amount included primarily $4.2 million of the carryback benefit related to the net operating loss incurred by us for the year ended January 31, 2020.

For the three months ended April 30, 2021, our improved overall operating performance resulted in net income attributable to our stockholders in the amount of $10.8 million, or $0.67 per diluted share. Last year, despite the favorable effect of the net operating loss carryback benefit identified above, we reported a net loss attributable to our stockholders in the amount of $0.8 million, or $0.05 per dilutive share.

The primary drivers of our improved financial performance for the three-month period ended April 30, 2021 were the increasing revenues and steady gross margin contributions associated with the construction of the Guernsey Power Station by GPS. This project represented the major portion of our business for the period.

Engineering, Procurement and Construction Service Contracts

At April 30, 2021, the project backlog for the power industry services reporting segment was approximately $0.7 billion. The comparable backlog amount as of January 31, 2021 was approximately $0.8 billion. Our reported amount of project backlog at a point in time represents the total value of projects awarded to us that we consider to be firm as of that date less the amounts of revenues recognized to date on the corresponding projects (project backlog is larger than the value of remaining unsatisfied performance obligations, or RUPO, on active contracts; see Note 2 to the accompanying consolidated financial statements). Cancellations or reductions may occur that would reduce project backlog and our expected future revenues.

Typically, we include the total value of EPC services and other major construction contracts in project backlog when we receive a corresponding notice to proceed from the project owner. However, we may include the value of an EPC services contract prior to the receipt of a notice to proceed if we believe that it is probable that the project will commence within a reasonable timeframe, among other factors. Projects that are awarded to us may remain included in our backlog for extended periods of time as customers experience project delays.

A substantial amount of the project backlog amount at April 30, 2021 was represented by the Guernsey Power Station. The ramp-up of activity on this project since August 2019 has favorably impacted our consolidated operating results since then with its increasing revenues. Substantial completion of this project is currently scheduled to occur during the second half of the fiscal year ending January 31, 2023.

In January 2020, GPS entered into an EPC services contract with Harrison Power, LLC (“Harrison Power”) to construct a 1,085 MW natural gas-fired power plant in the Village of Cadiz, Harrison County, Ohio. The project is being developed by EmberClear, the parent company of Harrison Power. On March 12, 2020, we announced that GPS had entered into an EPC services contract with NTE Connecticut, LLC to construct the Killingly Energy Center, a 650 MW natural gas-fired power plant, in Killingly, Connecticut. The facility is being developed by NTE Energy, LLC. We anticipate adding the value of each of these new contracts to project backlog at times closer to their financial close and expected start dates. We are cautiously optimistic that the start of construction activities for these projects will occur before the end of our fiscal year ending January 31, 2022. However, we cannot predict with certainty when the projects will commence. The start dates for construction are generally controlled by the project owners.

In May 2019, GPS entered into an EPC services contract to construct a 625 MW power plant in Harrison County, West Virginia. Caithness is partnered with ESC Harrison County Power, LLC to develop this project. As a limited notice to proceed with certain preliminary activities was received from the owner of this project at the time, the value of the contract was added to our project backlog. However, meaningful construction activities for the facility are not likely to begin until financial close is achieved which will probably not occur before January 31, 2022.

As announced in Fiscal 2019, GPS entered into an EPC services contract to construct the Chickahominy Power Station, a 1,740 MW natural gas-fired power plant, in Charles City County, Virginia. Even though we have been providing financial and technical support to the project development effort through a consolidated VIE and significant project development milestones have been achieved, we have not included the value of this contract in our project backlog. Due to several factors that have interrupted the pace of the development of this project, including additional costs and time being required to secure the natural gas supply for the plant and to obtain the necessary equity financing, we currently cannot predict when construction will commence, if at all.

The aggregate rated electrical output amount for the natural gas-fired power plants for which we have signed EPC services contracts, including the Guernsey Power Station, is approximately 6.4 gigawatts with an aggregate initial contract value of approximately $3.0 billion and an aggregate unrealized contract value of approximately $2.6 billion as of April 30, 2021.

Despite our commitment to the construction of state-of-the-art, natural gas-fired power plants as important elements of our country’s electricity-generation mix in the future, we have been directing certain business development efforts to winning projects for the erection of utility-scale wind farms and solar fields and for the construction of hydrogen-based and other renewable energy projects. We have successfully completed these types of projects in the past and we renewed efforts to obtain new work in the renewable power sector that will complement our natural gas-fired EPC services projects going forward. During the year ended January 31, 2021, GPS began exclusive negotiations with the owners of several significant renewable projects for which we expect to begin EPC services contract activities during the fiscal year ending January 31, 2022 (“Fiscal 2022”). During the quarter ended April 30, 2021, GPS continued to provide pre-construction contract assistance, that commenced late last year, to one of these customers under a consulting services agreement.

Our efforts led to our announcement in May 2021 that GPS has entered into an EPC services contract with CPV Maple Hill Solar, LLC, an affiliate of Competitive Power Ventures, Inc. (“CPV”), to construct the Maple Hill Solar facility, which we believe will be among the largest solar-powered energy plants in Pennsylvania. Gemma also received notice to proceed with project activities immediately. Project completion is scheduled to occur during the second half of 2022. The unique Maple Hill Solar project, which is located in Cambria County, will be constructed using over 235,000 photovoltaic modules to generate approximately 100 megawatts of electrical power.

We have maintained that the delays in new business awards to GPS and the project construction starts of certain previously awarded projects relate to a variety of factors, especially in the northeastern and mid-Atlantic regions of the US. Currently, we believe that the ability of the owners of fully developed gas-fired power plant projects to close on equity and permanent debt financing was challenged by uncertainty in the capital markets caused by multiple factors including delayed capacity auctions and mounting public and political opposition to fossil-fuel energy projects.

The recent announcement by the PJM of a new capacity auction schedule may remove a certain amount of uncertainty for project developers in forecasting future streams of revenues. In fact, the results of the first capacity auction conducted by PJM in over 3 years were announced on May 2, 2021. Even though it may be disappointing for potential power plant owners to see pricing significantly lower than in prior years, over 5.6 GW of new combined cycle, gas-fired power plants cleared the auction, representing over 75% of all new capacity units. The remaining new capacity was comprised of solar and wind powered energy plants. These mixed results may result in new gas-fired power plant EPC projects continuing to be delayed until the visibility regarding future capacity revenue streams is further restored with the results of the upcoming December 2021 capacity auction for the PJM region.

However, other headwinds for future gas-fired power plant developments remain. Besides the downturn in the demand for electric power during the COVID-19 outbreak in the US that is referenced in the discussion below, factors to consider include an increase in the amount of power generating capacity provided by renewable energy assets, improvements and decreasing prices in renewable energy storage solutions including battery resources, increased environmental activism and the results of the recent presidential election in the US.

Protests against fossil-fuel related energy projects continue to garner media attention and stir public skepticism about new projects resulting in delays due to onsite protest demonstrations, indecision by local officials and lawsuits. Currently, we have a pending project for the construction of a gas-fired power plant project in Killingly, Connecticut. Although substantially all of the permits, approvals and other items necessary for the commencement of the project have been obtained by the project owner, including the securing of capacity auction payments, a financial close on project financing has not yet occurred. During this delay, opposition to the project has been voiced by various government officials and clean air advocates. We currently believe that the start of this project will occur before the end of Fiscal 2022.

In the New England and mid-Atlantic regions of the US, power plant operators are challenged by the requirements of the Regional Greenhouse Gas Initiative, or “RGGI,” which is a cooperative effort by states in these regions to cap and reduce power sector carbon dioxide emissions. In addition, various cities, counties and states have adopted clean energy and carbon-free goals or objectives with achievement expected by a certain future date, typically 10 to 30 years out. These aspirational goals may increase the risk of a new power plant becoming a stranded asset long before the end of its otherwise useful economic life, which is a risk that potential equity capital providers may be unwilling to take. The difficulty in obtaining project equity financing and the other factors identified above may be adversely impacting the planning and initial phases for the construction of new natural gas-fired power plants which continue to be deferred by project owners.

Perhaps the most significant uncertainty relates to the ambitious policies of President Biden who is proposing to make the electricity production in the US carbon free by 2035 and to put the country on the path to achieve net zero carbon emissions by 2050. As he pledged during his presidential campaign, Mr. Biden caused the US to re-join the Paris Climate Agreement and he has cancelled the permit allowing the Keystone XL Pipeline to cross the border from Canada into the US. In addition, Mr. Biden ordered a pause on the US government entering into new oil and natural gas leases on public lands or offshore waters to the extent possible, the launch of a rigorous review of all existing leasing and permitting practices related to fossil fuel development on public lands and waters, and the identification of steps that can be taken to double renewable energy production from offshore wind by 2030.

Market Outlook

The overall growth of our power business has been substantially based on the number of combined cycle gas-fired power plants built by us, as many coal-fired plants have been shut down. In 2010, coal-fired power plants accounted for about 45% of total electricity generation. By 2020, coal accounted for less than 20% of total electricity generation. On the other hand, natural-gas fired power plants provided approximately 39% of the electricity generated by utility-scale power plants in the US in 2020, representing an increase of 64% from the amount of electrical power generated by natural gas-fired power plants in 2010, which provided approximately 24% of net electricity generation for 2010. In the reference case of its Annual Energy Outlook 2021, the Energy Information Administration (“EIA”) projects that coal-fired generation will continue to decline through 2050, and will represent only 11% of the electricity generation mix by 2050. The projection for natural gas-fired plants is that they will supply 36% of the net electricity generation in the US for 2050. Undoubtedly, the long-term historic decline in the use of coal as a power source in the US has been caused, to a significant extent, by the plentiful supply of inexpensive natural gas which made it the fuel of choice for power plant developers over this period.

The share of electricity generation provided by natural gas is particularly reactive in the short term to changing natural gas prices. In recent publications, the EIA explains that natural gas prices have risen recently because of reduced supplies and higher winter heating demand. The increased natural gas prices in the US prompted firms controlling electricity generation facilities to switch fuel sources from gas to coal. The EIA states that coal-fired electrical power generation increased by nearly 40% in the US during the first four months of calendar year 2021 compared with the same period in 2020 and now accounts for 23% of total generation. However, natural gas electric power prices for 2020 were about 18% lower than prices in 2019, and they were approximately 33% lower than they were in 2018.

Nonetheless, a long-term rise in natural gas prices and the resulting reduction in the demand for natural gas-fired electricity generation, could have adverse effects on the ability of independent power producers to obtain construction and permanent financing for new natural gas-fired power plants.

The pace of the ten-year increase in the preference for natural gas as an electricity generating fuel source was energized by environmental activism and restrictive regulations targeting coal-fired power plants. Now, the environmentalist opposition against coal-fired power generation has expanded meaningfully and effectively to target all fossil fuel energy projects, including power plants and pipelines, and has evolved into powerful support for renewable energy sources.

The share of electricity generation in the US provided by utility-scale wind and solar photovoltaic facilities continues to rise meaningfully. Together, such power facilities provided approximately 8.8% and 10.6% of the total amount of electricity generated by utility-scale power facilities in 2019 and 2020, respectively. In EIA’s 2021 reference case, net electricity generation from all renewable power sources is expected to increase by more than 175%, representing over 42% of such generation, by 2050. Impetus for this growth is provided by public concerns about climate change and favorable economic factors. Environmental activism has resulted in the passage of laws and the establishment of regulations that discourage new fossil-fuel burning power plants and provide income tax advantages that promote the growth of wind and solar power. Declines in the amount of renewable power plant component and power storage costs and an increase in the scale of energy storage capacity (i.e., battery farms) have also occurred. Should the pace of development for renewable energy facilities, including wind and solar power plants, accelerate at faster rates than projected, the number of future natural gas-fired construction project opportunities may fall.

Over the next few years, EIA projects that new wind and photovoltaic solar capacity will continue to be added to the utility-scale power fleet in the US at a brisk pace substantially attributable to declining equipment costs and the availability of valuable tax credits. As these credits decline and then expire early in the next decade as currently scheduled, the wind capacity additions are expected to slow. Although the special tax incentives related to solar power also expire, the continuing decline in the cost of solar power equipment is predicted to sustain the growth of photovoltaic solar power generation facilities.

Nonetheless, we believe that persistently low natural gas prices over the long-term, lower power plant operating costs, higher energy generating efficiencies and the maintenance of grid resiliency should sustain the demand for modern combined cycle gas-fired power plants in the future. Natural gas is relatively clean burning, cost-effective and reliable; we believe that its benefits as a source of power are compelling. We continue to believe that the future long-term prospects for natural gas-fired power plant construction remain generally favorable as natural gas continues to be the primary source for power generation in our country. New gas-fired power plants incorporate major advances in gas-fired turbine technologies that have provided increased power plant efficiencies while providing the quick starting capabilities and the reliability that are necessary to balance the inherent intermittencies of wind and solar powered energy plants.

It has been reported that renewables currently provide approximately 36% of electricity generation in California. Yet, last summer’s experience is that the increasing dependence on intermittent renewable energy sources, especially solar, is making it harder to ensure reliable power in California as millions of its residents lost power during a late summer heat wave. Analysis of the causes of the recent widespread power outages in Texas during a frigid stretch of winter weather is complex. The residents of Texas suffered as the severe cold froze wind turbines and the lack of sun diminished the power contributions of solar powered facilities. However, natural gas-fired power plants in Texas were forced offline as well primarily due to frozen well-site equipment and the decisions by regulators to prioritize natural gas for residential use, which caused interruptions to the supply of natural gas to the plants. However, in both states, the significant amount of renewable power capacity failed to rise to the occasion.

A diversity lesson from both power crises may be that fossil-fuel electricity generation sources remain critical elements of the power generation mix in order to assure grid reliability and the avoidance of power outages.

The North American Electric Corp. (“NERC”), the designated electric reliability organization in the US, issued its 2021 Summer Reliability Assessment on May 26, 2021 that indicated that parts of North America are at elevated or high risk of energy shortfalls during peak summer conditions. NERC noted that the events of this past year and the outlook for summer are stark reminders that in the nation’s hurry to develop a cleaner resource base, reliability and energy adequacy have to be considered.

Additionally, solar and wind energy plant developers continue to confront the problems caused by grid congestion, often unsuccessfully. Many of these projects have been canceled because renewable plants need to be sited where the resources are optimal, often in remote locations where the transmission systems are not robust. The costs associated with the necessary grid upgrades may be prohibitive. US offshore wind projects progress inconsistently, facing challenges in the areas of environmental and fishery impacts, grid connection and capability and federal permitting processes. Further, projects are confronted by shipping regulations in the US that may limit the ability of developers to replicate successful European construction and installation models.

Major advances in the safe combination of horizontal drilling techniques and hydraulic fracturing led to the boom in natural gas supplies which have been available generally at consistently low prices. The abundant availability of cheap, less carbon-intense and higher efficiency natural gas should continue to be a significant factor in the economic assessment of future power generation capacity additions although the pace of new opportunities emerging may be restrained and the starts of awarded EPC projects may be delayed. We believe that it is also important to note that the plans for two of our contracted natural gas-fired power plant projects include the adoption of integrated green hydrogen solution packages developed by a major gas turbine manufacturer. While the plants will initially burn natural gas alone, it is planned by the respective project owners that the plants will eventually burn a mixture of natural gas and green hydrogen, thereby establishing power-generation flexibility for these plants.

We believe this is a winning combination that provides inexpensive and efficient power, enhances grid reliability and addresses the clean-air concerns of environmentalists. The building of state-of-the-art power plants with flex-fuel capability replaces coal-fired power plants in the short term with relatively clean gas-fired electricity generation. Further, such additions to the power generation fleet provide the potential for the plants to burn 100% green hydrogen gas, which would provide both base load power and long duration backup power, when the sun is not shining and the wind is not blowing, for extended periods of time and without certain harmful air emissions.

We are committed to the rational pursuit of new construction projects and the future growth of our revenues. This may result in our decision to make investments in the development and/or ownership of new projects. Because we believe in the strength of our balance sheet, we are willing to consider certain opportunities that include reasonable and manageable risks in order to assure the award of the related EPC services contracts to us. The competitive landscape in the EPC services market for natural gas-fired power plant construction has changed significantly over the last several years. While the market remains dynamic, we are moving into an era where there may be fewer competitors for new gas-fired power plant EPC services project opportunities. Several major competitors have exited the market for a variety of reasons or have been acquired. Others have announced intentions to avoid entering into fixed-price contracts. Nonetheless, the competition for new utility-scale gas-fired power plant construction opportunities is fierce and still includes multiple global firms.

We believe that the Company has a reputation as an accomplished and cost-effective provider of EPC and other large project construction contracting services. We are convinced that the latest series of new EPC projects awarded to us confirms the soundness of our belief. With the proven ability to deliver completed power facilities, particularly combined cycle, natural gas-fired power plants, we are focused on expanding our position in the power markets where we expect investments to be made based on forecasts of electricity demand covering decades into the future. We believe that our expectations are valid and that our plans for the future continue to be based on reasonable assumptions.

Confidence in our financial strength and the prospects for our business going forward prompted our board of directors to declare and to pay two special cash dividends during Fiscal 2021 in the amount of $1.00 per share each, to continue to pay regular cash dividends in the amount of $0.25 per share and to authorize the use of $25.0 million to repurchase shares of our common stock.

Comparison of the Results of Operations for the Three Months Ended April 30, 2021 and 2020

We reported net income attributable to our stockholders of $10.8 million, or $0.67 per diluted share, for the three months ended April 30, 2021. For the comparable period of the prior year, we reported a net loss attributable to our stockholders of approximately $0.8 million, or $0.05 per diluted share.

The following schedule compares our operating results for the three months ended April 30, 2021 and 2020 (dollars in thousands):

​ ​ ​ REVENUES ​ ​ ​ ​ Three Months Ended April 30, 2021 ​ ​ ​ ​ 2020 ​ ​ ​ ​ $ Change ​ ​ ​ ​ ​ % Change ​ ​ ​ ​ ​ ​
Power industry services ​ $97,172 ​ $48,612 ​ $48,560 99.9% ​
Industrial fabrication and field services ​ 26,658 ​ 9,744 ​ 16,914 173.6 ​ ​
Telecommunications infrastructure services ​ 2,511 ​ 1,792 ​ 719 40.1 ​ ​
Revenues ​ 126,341 ​ 60,148 ​ 66,193 110.1 ​ ​
COST OF REVENUES ​ ​ ​ ​ ​
Power industry services ​ 78,669 ​ 45,710 ​ 32,959 72.1 ​ ​
Industrial fabrication and field services ​ 21,969 ​ 8,982 ​ 12,987 144.6 ​ ​
Telecommunications infrastructure services ​ 1,989 ​ 1,447 ​ 542 37.5 ​ ​
Cost of revenues ​ 102,627 ​ 56,139 ​ 46,488 82.8 ​ ​
GROSS PROFIT ​ 23,714 ​ 4,009 ​ 19,705 491.5 ​ ​
Selling, general and administrative expenses ​ 9,892 ​ 10,344 ​ (452) (4.4) ​ ​
INCOME (LOSS) FROM OPERATIONS ​ 13,822 ​ (6,335) ​ 20,157 NM ​ ​
Other income, net ​ 712 ​ 1,088 ​ (376) (34.6) ​ ​
INCOME (LOSS) BEFORE INCOME TAXES ​ 14,534 ​ (5,247) ​ 19,781 NM ​ ​
Income tax (expense) benefit ​ (3,768) ​ 4,454 ​ (8,222) NM ​ ​
NET INCOME (LOSS) ​ 10,766 ​ (793) ​ 11,559 NM ​ ​
Net loss attributable to non-controlling interests ​ — ​ (30) ​ 30 (100.0) ​ ​
NET INCOME (LOSS) ATTRIBUTABLE TO ​ ​ ​ ​ ​
THE STOCKHOLDERS OF ARGAN, INC. ​ $10,766 ​ $(763) ​ $11,529 NM ​ ​

NM – Not meaningful.

Revenues

Power Industry Services

The revenues of the power industry services business increased by 99.9%, or $48.6 million, to $97.2 million for the three months ended April 30, 2021 compared with revenues of $48.6 million for the three months ended April 30, 2020. The revenues of this business represented approximately 76.9% of consolidated revenues for the quarter ended April 30, 2021 and 80.8% of consolidated revenues for the prior year quarter. The primary driver for the improved performance by this reportable segment for the three months ended April 30, 2021 was the increased revenues associated with the construction of the Guernsey Power Station as this project has reached its peak level of construction activity. The revenues associated with this project represented 67.8% of consolidated revenues for the three months ended April 30, 2021.

Last year, the revenues earned by GPS on the Guernsey Power Station project represented 60.6% of consolidated revenues as activities on this project were ramping up from its start in August 2019. Results for the three-month period ended April 30, 2020 also included a meaningful contribution from APC’s TeesREP project as its revenues represented 17.0% of consolidated revenues for the period. Activities on this project have diminished considerably as APC completed its subcontracted efforts during the three-month period ended April 30, 2021. Before the end of the first quarter, APC and its customer on the TeesREP subcontract executed an agreement that documents the termination of the subcontract. Future meaningful activities should be limited to the performance of the necessary services under its assurance-type warranty.

Industrial Fabrication and Field Services

The revenues of our industrial fabrication and field services segment (representing the business of TRC) provided 21.1% of consolidated revenues for the three-month period ended April 30, 2021, which reflected an increase in revenues of $16.9 million, or 173.6%, to $26.7 million for the period compared to revenues of $9.7 million for the three months ended April 30, 2020. TRC’s strong performance for the three-month period ended April 30, 2021 reflected a significant rise in revenues earned on field services activities during the period from the amount of revenues reported for the quarter ended April 30, 2020, as well as increases in revenues associated with pipe and vessel fabrication works. New project awards have increased TRC’s project backlog to approximately $67.1 million as of April 30, 2021 from $38.3 million as of April 30, 2020. The major customers of TRC include some of North America’s largest fertilizer producers, as well as other chemical, mining, forest products, construction and energy companies with plants, facilities and other sites located primarily in the southeastern region of the US.

Telecommunications Infrastructure Services

The revenue results of this business segment (representing the business of SMC) were $2.5 million for the three-month period ended April 30, 2021, increasing by 40.1% from $1.8 million for the three months ended April 30, 2020. Most of the increase in revenues between the quarters related to increased activities for inside-premises customers, an indication that concerns of project sponsors regarding the spread of COVID-19 threatening works performed indoors may be abating.

Cost of Revenues

With the increase in consolidated revenues for the three months ended April 30, 2021 compared with last year’s first quarter ended April 30, 2020, the consolidated cost of revenues also increased between the quarters. These costs were $102.6 million and $56.1 million for the three-month periods ended April 30, 2021 and 2020, respectively, representing an increase of approximately 82.8%.

For the three-month period ended April 30, 2021, we reported a consolidated gross profit of approximately $23.7 million, which represented a gross profit percentage of approximately 18.8% of corresponding consolidated revenues. The gross profit for the period reflected the consistent profit contribution of the construction activities related to the Guernsey Power Station project; it was also favorably impacted by the profit contributions of APC as the TeesREP project wound down towards completion. Works for this project performed during the quarter ended April 30, 2021 were profitable as they were completed pursuant to the time and materials arrangement of the subcontract, as amended. The gross profit percentages of corresponding revenues for the power industry services, industrial services and the telecommunications infrastructure segments were 19.0%, 17.6% and 20.8%, respectively, for the quarter ended April 30, 2021.

Our consolidated gross profit reported for the three-month period ended April 30, 2020 was $4.0 million, which represented a gross profit percentage of approximately 6.7% of corresponding consolidated revenues. Last year, the gross profit percentage for the first quarter period was adversely affected by the continuation of challenges that confronted the management of the TeesREP project, including a suspension of construction activities due to the COVID-19 outbreak, which resulted in our recording additional loss for this project in the amount of $2.7 million during the quarter.

Selling, General and Administrative Expenses

These costs were $9.9 million and $10.3 million for the three months ended April 30, 2021 and 2020, respectively, representing 7.8% and 17.2% of consolidated revenues for the corresponding periods, respectively. We expected these costs, expressed as a percentage of corresponding revenues, to trend favorably based on a quarter-to-quarter comparison due to the expected increase in consolidated revenues over the same periods. The reduction in actual costs between the quarters was due primarily to the increased utilization of staff by GPS on the Guernsey Power Station project. The amount for the three months ended April 30, 2020 included the costs of maintaining core members of the operations staff at GPS whose time is typically charged to active projects to a greater degree, and the costs of maintaining intact the key staff organizations at corporate headquarters, GPS, TRC and SMC.

Other Income

In April 2021 APC received a research and development credit payment from the government of the UK related to certain qualifying works performed on the TeesREP project during Fiscal 2019. Net of associated costs, the payment amount of $0.7 million, much like a grant, was included in other income for the three months ended April 30, 2021.

Typically, the amounts reported on this line include primarily income earned on funds maintained in money market accounts and interest income earned on CDs. Adverse economic reactions to the uncertainties of the COVID-19 pandemic commenced during the middle of last year’s first quarter ended April 30, 2020, including sharp reductions in investment interest rates. For the three months ended April 30, 2020, the net amount of other income was $1.1 million, including approximately $0.9 million in earnings on our temporary investments of excess cash. Other income for the three months ended April 30, 2021 was insignificant although the aggregate amount of invested funds increased between the quarters.

Income Taxes

We reported income tax expense for the three months ended April 30, 2021 in the amount of approximately $3.8 million. We estimate that our annual effective income tax rate for Fiscal 2022, before discrete items, will approximate 25.1%. This tax rate differs from the statutory federal tax rate of 21% due primarily to the unfavorable effects of state income taxes and permanent differences, including certain nondeductible executive compensation and the non-deductible portions of the out-of-pocket travel and living expenses incurred by the large numbers of our project and craft employees currently working offsite, and a write-off of certain deferred tax assets in the amount of $0.3 million. For the three months ended April 30, 2020, we recorded an income tax benefit in the amount of approximately $4.5 million, which reflected primarily the net operating loss carryback benefit amount of $4.2 million discussed above.

The wide-ranging CARES Act legislation was enacted in March 2020 as an emergency economic stimulus package including spending and tax breaks aimed at strengthening the US economy and funding a nationwide effort to curtail the effects of the outbreak of COVID-19. The tax changes of the CARES Act temporarily suspended the limitations on the future utilization of certain NOLs and re-established a carryback period for certain losses to five years. The losses eligible for carryback under the CARES Act include our consolidated NOL for the Fiscal 2020, which was approximately $39.5 million. With the filing of our consolidated federal income tax return for the year, we elected to apply the NOL against our taxable income for the years ended January 31, 2015, 2016 and 2017. The carryback provides a favorable rate benefit for us as the loss, which was incurred in a year where the statutory federal tax rate was 21%, will be carried back to tax years where the tax rate was higher.

Liquidity and Capital Resources as of April 30, 2021

At April 30, 2021 and January 31, 2021, our balances of cash and cash equivalents were $396.7 million and $366.7 million, respectively. During the three months between these dates, our working capital increased by $5.8 million to $276.0 million as of April 30, 2021 from $270.1 million as of January 31, 2021.

The net amount of cash provided by operating activities for the three months ended April 30, 2021 was $17.3 million. Our net income for the three months ended April 30, 2021, adjusted favorably by the net amount of non-cash income and expense items, represented a source of cash in the total amount of $13.8 million. The sources of cash from operations for the three months ended April 30, 2021 also included the temporary increase in the balance of contract liabilities associated with projects at GPS and TRC in the amount of $27.5 million. A reduction in the combined level of accounts payable and accrued expenses and an increase in the amount of accounts receivable during the three-month period ended April 30, 2021, in the respective amounts of $21.6 million and $3.7 million, represented uses of cash for the period.

Other primary sources of cash for the three months ended April 30, 2021 were the net maturities of short-term investments, certificates of deposit issued by the Bank, and the proceeds associated with the exercise of stock options in the amounts of $20.0 million and $1.0 million, respectively. Non-operating activities used cash during the three months ended April 30, 2021, including the payment of a regular cash dividend in the amount of $3.9 million, investment payments made to a solar energy fund in the amount of $3.5 million and capital expenditures in the amount of $0.8 million. As of April 30, 2021, there were no restrictions with respect to inter-company payments between GPS, TRC, APC, SMC and the holding company. However, certain loans made by Argan to APC have been determined to be uncollectible.

Last year, the net amount of cash provided by operating activities for the three months ended April 30, 2020 was $40.2 million. The sources of cash for the period included a temporary increase in the balance of contract liabilities, primarily associated with the early phases of a major construction project at GPS, and a reduction in the balances of accounts receivable, primarily at the TRC and APC operations, in the amounts of $37.1 million and $15.0 million, respectively. In addition, our net loss for the quarter ended April 30, 2020 was more than offset by the favorable adjustments related to non-cash income and expense items, which represented a net source of cash in the total amount of $9.9 million.

As described above, our income tax accounting for the quarter ended April 30, 2020 included an entry to record the carryback benefit related to our NOL incurred for Fiscal 2020 to previous tax years. The loss carryback should result in a refund of federal income taxes in the amount of $12.3 million. This tax refund receivable was included in the balance of other current assets as of April 30, 2020, which was the primary cause of the increase in this balance of $13.6 million during the quarter then ended, a use of cash.

The Company also used cash in operations during the three months ended April 30, 2020 in the amount of $8.6 million to reduce the level of accounts payable and accrued expenses.

Another primary source of cash for the three months ended April 30, 2020 was represented by the net maturities of short-term investments in the amount of $60.0 million. Non-operating activities used cash during the three months ended April 30, 2020, including the payment of a quarterly cash dividend in the total amount of $3.9 million and capital expenditures in the amount of $0.7 million.

At April 30, 2021, most of our balance of cash and cash equivalents was invested in government and prime money market funds with most of their total assets invested in cash, US Treasury obligations and repurchase agreements secured by US Treasury obligations. The major portion of our domestic operating bank account balances are maintained with the Bank. We do maintain certain Euro-based bank accounts in Ireland and certain pound sterling-based bank accounts in the UK in support of the operations of APC.

The original term of our Credit Agreement was scheduled to expire on May 31, 2021. During April 2021, negotiations with the Bank were completed which, among other items, extended the expiration date of the Credit Agreement, as amended, to May 31, 2024 and reduced the borrowing rate. The Credit Agreement, as amended, includes the following features, among others: a lending commitment of $50.0 million including a revolving loan with interest at the 30-day LIBOR plus 1.6% (reduced from 2.0%), and an accordion feature which allows for an additional commitment amount of $10.0 million, subject to certain conditions. We may use the borrowing ability to cover other credit instruments issued by the Bank for our use in the ordinary course of business as defined by the Bank. At April 30, 2021, we had $1.8 million of outstanding letters of credit issued under the Credit Agreement. Additionally, in connection with the current project development activities of the VIE, the Bank issued a letter of credit, outside the scope of the Credit Agreement, in the approximate amount of $3.4 million for which we have provided cash collateral.

We have pledged the majority of our assets to secure the financing arrangements. The Bank’s consent is not required for acquisitions, divestitures, cash dividends or significant investments as long as certain conditions are met. The Credit Agreement, as amended, requires that we comply with certain financial covenants at our fiscal year-end and at each fiscal quarter-end, and includes other terms, covenants and events of default that are customary for a credit facility of its size and nature, including a requirement to achieve positive adjusted earnings before interest, taxes, depreciation and amortization, as defined, over each rolling twelve-month measurement period. At April 30, 2021 and January 31, 2021, we were compliant with the covenants of the Credit Agreement.

In the normal course of business and for certain major projects, we may be required to obtain surety or performance bonding, to provide parent company guarantees, or to cause the issuance of letters of credit (or some combination thereof) in order to provide performance assurances to clients on behalf of one of our contractor subsidiaries.

If our services under a guaranteed project would not be completed or would be determined to have resulted in a material defect or other material deficiency, then we could be responsible for monetary damages or other legal remedies. As is typically required by any surety bond, we would be obligated to reimburse the issuer of any surety bond issued on behalf of a subsidiary for any cash payments made thereunder. The commitments under performance bonds generally end concurrently with the expiration of the related contractual obligation. Not all of our projects require bonding.

As of April 30, 2021, the value of the Company’s unsatisfied bonded performance obligations, covering all of its subsidiaries, was approximately $372 million. In addition, as of April 30, 2021, there were bonds outstanding in the aggregate amount of approximately $6.6 million covering other risks including warranty obligations related to projects completed by GPS; these bonds expire at various dates over the next twelve months.

On behalf of APC, Argan has provided a parent company performance guarantee to its customer, the EPC services contractor on the TeesREP project which was supported by a performance bond issued on behalf of the customer. In connection with the completion of the subcontract construction work, we expect the issuance of a warranty bond in the approximate amount of $4.2 million to replace the performance bond.

We have also provided a financial guarantee on behalf of GPS to an original equipment manufacturer in the amount of $3.6 million to support project developmental efforts.

When sufficient information about claims related to our performance on projects would be available and monetary damages or other costs or losses would be determined to be probable, we would record such guaranteed losses. As our subsidiaries are wholly-owned, any actual liability related to contract performance is ordinarily reflected in the financial statement account balances determined pursuant to the Company’s accounting for contracts with customers. Any amounts that we may be required to pay in excess of the estimated costs to complete contracts in progress as of April 30, 2021 are not estimable.

We believe that cash on hand, cash that will be provided from the maturities of short-term investments and cash generated from our future operations, with or without funds available under our Credit Agreement, as amended, will be adequate to meet our general business needs in the foreseeable future. Since the beginning of the COVID-19 pandemic, to assure an optimum level of liquidity during this period of uncertainty and to mitigate the market risks represented by the COVID-19 pandemic, management decided to temporarily maintain larger balances of cash and cash equivalents relative to short-term investments with minimal opportunity cost.

In general, we maintain significant liquid capital in our balance sheet to ensure the maintenance of our bonding capacity and to provide parent company performance guarantees for EPC and other construction projects. Any future acquisitions, or other significant unplanned cost or cash requirement, may require us to raise additional funds through the issuance of debt and/or equity securities. There can be no assurance that such financing will be available on terms acceptable to us, or at all.

Earnings before Interest, Taxes, Depreciation and Amortization (“EBITDA”)

We believe that EBITDA is a meaningful presentation that enables us to assess and compare our operating cash flow performance on a consistent basis by removing from our operating results the impacts of our capital structure, the effects of the accounting methods used to compute depreciation and amortization and the effects of operating in different income tax jurisdictions. Further, we believe that EBITDA is widely used by investors and analysts as a measure of performance.

The table following immediately below presents the determinations of EBITDA for the three months ended April 30, 2021 and 2020, respectively (amounts in thousands).

​ ​ ​ ​ ​ ​ ​ ​ ​ Three Months Ended April 30, 2021 ​ ​ ​ 2020 ​ ​ ​ ​
Net income (loss), as reported ​ $10,766 ​ $(793) ​
Income tax expense (benefit) ​ 3,768 ​ (4,454) ​
Depreciation ​ 882 ​ 937 ​
Amortization of purchased intangible assets ​ 228 ​ 225 ​
EBITDA ​ 15,644 ​ (4,085) ​
EBITDA of non-controlling interests ​ — ​ (30) ​
EBITDA attributable to the stockholders of Argan, Inc. ​ $15,644 ​ $(4,055) ​

31

However, as EBITDA is not a measure of performance calculated in accordance with US GAAP, we do not believe that this measure should be considered in isolation from, or as a substitute for, the results of our operations presented in accordance with US GAAP that are included in our condensed consolidated financial statements. In addition, our EBITDA does not necessarily represent funds available for discretionary use and is not necessarily a measure of our ability to fund our cash needs.

As we believe that our net cash flow provided by operations is the most directly comparable performance measure determined in accordance with US GAAP, the table below reconciles the amounts of EBITDA for the applicable three-month periods to the corresponding amounts of net cash flows provided by operating activities that are presented in our condensed consolidated statements of cash flows for the three months ended April 30, 2021 and 2020 (amounts in thousands).

​ ​ ​ ​ ​ ​ ​ ​ ​ ​ Three Months Ended April 30, 2021 ​ ​ ​ 2020 ​ ​ ​ ​
EBITDA ​ $15,644 ​ $(4,085) ​
Current income tax (expense) benefit ​ (3,169) ​ 12,668 ​
Stock compensation expense ​ 679 ​ 642 ​
Other non-cash items ​ 662 ​ 707 ​
(Increase) decrease in accounts receivable ​ (3,666) ​ 14,980 ​
Decrease (increase) in other assets ​ 765 ​ (13,600) ​
Decrease in accounts payable and accrued expenses ​ (21,552) ​ (8,609) ​
Change in contracts in progress, net ​ 27,983 ​ 37,484 ​
Net cash provided by operating activities ​ $17,346 ​ $40,187 ​

Critical Accounting Policies

Critical accounting policies are those related to the areas where we have made what we consider to be particularly subjective or complex judgments in arriving at estimates and where these estimates can significantly impact our financial results under different assumptions and conditions. These estimates, judgments, and assumptions affect the reported amounts of assets, liabilities and equity, the disclosure of contingent assets and liabilities at the date of financial statements and the reported amounts of revenues and expenses during the reporting periods. We base our estimates on historical experience and various other assumptions that we believe are reasonable under the circumstances, the results of which form the basis for making judgments about the carrying value of assets, liabilities and equity that are not readily apparent from other sources. Actual results and outcomes could differ from these estimates and assumptions.

We consider the accounting policies related to revenue recognition on long-term construction contracts; income tax reporting; the accounting for business combinations; the subsequent valuation of goodwill, other indefinite-lived assets and long-lived assets; the valuation of employee common stock-based awards; and the financial reporting associated with any significant claims or legal matters to be most critical to the understanding of our financial position and results of operations, as well as the accounting and reporting for special purpose entities including joint ventures and variable interest entities. An expanded discussion of our critical accounting policies is included in Item 7 of Part II of our Annual Report. During the three months ended April 30, 2021, there have been no material changes in the way we apply the critical accounting policies described therein.

Recently Issued Accounting Pronouncements

In December 2019, the FASB issued ASU 2019-12, Simplifying the Accounting for Income Taxes, which, among other changes, eliminates the exception to the general methodology for calculating income taxes in an interim period when a year-to-date loss exceeds the expected loss for the entire year. In these instances, the estimated annual effective income tax rate shall be used to calculate the tax without limitation. The new standard also requires the recognition of a franchise (or similar) tax that is partially based on income as an income-based tax and the recording of any incremental tax that is incurred by us as a non-income based tax. We do not expect that the requirements of this new guidance, effective for us on February 1, 2021, will alter our accounting for income taxes.

There are no other recently issued accounting pronouncements that have not yet been adopted that we consider material to our consolidated financial statements.

Market risk

As filed, 4,811 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

In the normal course of business, our results of operations may be subject to risks related to fluctuations in interest rates. As of April 30, 2021, we had no outstanding borrowings under our financing arrangements with the Bank, as amended (see Note 6 to the accompanying condensed consolidated financial statements), which provide a revolving loan with a maximum borrowing amount of $50.0 million that is available until May 31, 2024 with interest at 30-day LIBOR plus 1.6% going forward. During the three months ended April 30, 2021 and 2020, we did not enter into derivative financial instruments for trading, speculation or other purposes that would expose us to market risk.

Financial markets around the globe are preparing for the discontinuation of LIBOR at the end of 2021, which is the widely used indicator of basis for short-term lending rates. The transition from LIBOR is market-driven, not a change required by regulation. The US and other countries are currently working to replace LIBOR with alternative reference rates. We do not expect that the replacement of LIBOR as the basis for the determination of our short-term borrowing rate will have significant effects on the financial arrangements with the Bank, as amended, or our financial reporting.

We maintain a substantial amount of our temporarily investable cash in government and prime money market funds (see Note 3 of the accompanying condensed consolidated financial statements). The balance of these funds, which was included in cash and cash equivalents in our condensed consolidated balance sheet as of April 30, 2021, was $277.4 million with earnings based on a blended annual yield of 0.04%. The significant drop in interest rates during Fiscal 2021 has caused a substantial reduction in the investment returns earned on these funds by us.

As of April 30, 2021, the weighted average annual interest rate of our short-term investments of $70.0 million and money market funds of $277.4 million was 0.07%. To illustrate the potential impact of changes in interest rates on our results of operations, we present the following hypothetical analysis, which assumes that our condensed consolidated balance sheet as of April 30, 2021 remains constant, and no further actions are taken to alter our existing interest rate sensitivity, including reinvestments. The weighted average number of days until maturity for the short-term investments and money market funds is 356 days. As the blended weighted average interest rate on our short-term investments and money market funds was 0.07% at April 30, 2021, the largest decrease in the interest rates presented below is 7 basis points (dollars in thousands).

​ ​ Basis Point Change ​ ​ ​ ​ Increase (Decrease) in Interest Income ​ ​ ​ ​ Increase (Decrease) in Interest Expense ​ ​ ​ ​ Net Increase (Decrease) in Income (pre-tax)
Up 300 basis points ​ $8,888 ​ $— ​ $8,888
Up 200 basis points ​ ​ 5,925 ​ ​ — ​ ​ 5,925
Up 100 basis points ​ 2,963 ​ — ​ 2,963
Down 7 basis points ​ (122) ​ — ​ (122)

With the consolidation of APC, we are subject to the effects of translating the financial statements of APC from its functional currency (Euros) into our reporting currency (US dollars). Such effects are recognized in accumulated other comprehensive loss, which is net of tax when applicable. APC remeasures transactions and subsidiary financial statements denominated in local currencies to Euros. Gains and losses on the remeasurements are recorded in the other income line of our condensed consolidated statement of earnings.

In addition, we are subject to fluctuations in prices for commodities including copper, concrete, steel products and fuel. Although we attempt to secure firm quotes from our suppliers, we generally do not hedge against increases in prices for these commodities. Commodity price risks may have an impact on our results of operations due to the fixed-price nature of many of our contracts. We attempt to include the anticipated amounts of price increases or decreases in the costs of our bids. In times of increased supply cost volatility similar to those being experienced currently, we may take other steps to reduce our risks. For example, we may hold quotes related to materials in our industrial fabrication and field services segment for only three days. For major fixed price contracts in our power industry services segment, we may mitigate material cost risks by procuring the majority of the equipment and construction supplies during the early phases of a project. During the year ended April 30, 2021, the profitability of our active jobs did not suffer meaningfully from the global surge in construction material costs.

Controls and procedures

As filed, 1,714 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Evaluation of disclosure controls and procedures. Our management, with the participation of our chief executive officer and chief financial officer, evaluated the effectiveness of our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Securities Exchange Act of 1934 (the “Exchange Act”)) as of April 30, 2021. Management recognizes that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving their objectives, and management necessarily applies its judgment in evaluating the cost-benefit relationship of possible controls and procedures. Based on the evaluation of our disclosure controls and procedures as of April 30, 2021, our chief executive officer and chief financial officer concluded that, as of such date, our disclosure controls and procedures were effective to provide reasonable assurance that information required to be disclosed in our Exchange Act reports is recorded, processed, summarized, and reported within the time periods specified by the SEC, and the material information related to the Company and its consolidated subsidiaries is made known to management, including the chief executive officer and chief financial officer, to allow timely decisions regarding required disclosure in the reports.

Changes in internal controls over financial reporting. There have been no significant changes in our internal control over financial reporting (as defined in Rules 13a-15 and 15d-15 under the Exchange Act) during the fiscal quarter ended April 30, 2021 that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2021-04-30. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Revenue3 months2021-02-01 to 2021-04-30$126.3mus-gaap:RevenueFromContractWithCustomerExcludingAssessedTax
Cost of revenue3 months2021-02-01 to 2021-04-30$102.6mus-gaap:CostOfRevenue
Gross profit3 months2021-02-01 to 2021-04-30$23.7mus-gaap:GrossProfit
Selling, general and administrative3 months2021-02-01 to 2021-04-30$9.9mus-gaap:SellingGeneralAndAdministrativeExpense
Operating income3 months2021-02-01 to 2021-04-30$13.8mus-gaap:OperatingIncomeLoss
Income tax3 months2021-02-01 to 2021-04-30$3.8mus-gaap:IncomeTaxExpenseBenefit
Net income3 months2021-02-01 to 2021-04-30$10.8mus-gaap:NetIncomeLoss
Diluted EPS3 months2021-02-01 to 2021-04-30$0.67us-gaap:EarningsPerShareDiluted
Basic EPS3 months2021-02-01 to 2021-04-30$0.68us-gaap:EarningsPerShareBasic
Diluted shares (weighted)3 months2021-02-01 to 2021-04-3015,961,000 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Operating cash flow3 months2021-02-01 to 2021-04-30$17.3mus-gaap:NetCashProvidedByUsedInOperatingActivities
Capital expenditure3 months2021-02-01 to 2021-04-30$844.0kus-gaap:PaymentsToAcquirePropertyPlantAndEquipment
Cash and equivalentsAt period end2021-04-30$396.7mus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2021-04-30$559.0mus-gaap:AssetsCurrent
Total assetsAt period end2021-04-30$618.0mus-gaap:Assets
Current liabilitiesAt period end2021-04-30$283.1mus-gaap:LiabilitiesCurrent
Total liabilitiesAt period end2021-04-30$287.2mus-gaap:Liabilities
Shareholders' equityAt period end2021-04-30$329.1mus-gaap:StockholdersEquity