Management's discussion and analysis

As filed, 34,153 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

You should read the following discussion and analysis of our financial condition and results of operations together with our unaudited condensed consolidated financial statements and related notes included elsewhere in this Quarterly Report. This discussion contains forward‑looking statements based upon current plans, expectations and beliefs involving risks and uncertainties. Our actual results may differ materially from those anticipated in these forward‑looking statements as a result of various factors, including those set forth in Part II, Item 1A, “Risk Factors” and other factors set forth in other parts of this Quarterly Report.

Unless the context otherwise requires, references in this Quarterly Report to the “Company,” “Cipher,” “Cipher Mining,” “we,” “us” or “our” refers to Cipher Mining Inc. and its consolidated subsidiaries, unless otherwise indicated.

Overview

We develop, own and operate industrial-scale digital infrastructure to support high-performance computing (“HPC”) and purpose-built data centers for bitcoin mining applications. Our active portfolio and development pipeline consists of approximately 4.0 GW of capacity across 12 sites. We currently operate two wholly-owned bitcoin mining data centers, a 207 MW site located in Odessa, Texas that draws fixed priced power from a power purchase agreement with its electricity provider (the “Odessa Facility”), and a 300 MW data center in Wink, Texas, of which 150 MW is operational as a bitcoin mining data center, that draws power from the power grid (the “Black Pearl Facility”); have equity investments in three partially-owned 40 MW bitcoin mining data centers; and have a pipeline of approximately 3.2 GW of potential capacity suitable for HPC workloads. We have sourced and built five sites totaling 477 MW of capacity, all completed on time.

The Black Pearl Facility has recently been fully contracted for HPC hosting with bitcoin mining operations at the site expected to conclude as construction commences. We aim to be industry leaders in sourcing a pipeline of sites suitable for compute-intensive workloads, including the recent addition of a 1-gigawatt (“GW”) site to our portfolio in Texas, and to optimize those sites for commercial use. Through a subsidiary, Cipher is in the process of constructing a data center for HPC near Colorado City, Texas (the “Barber Lake Facility”). See “—Recent Developments.”

Our current intention is to continue expanding our business by developing and operating industrial-scale data centers for HPC and other compute-intensive applications, scaling pipeline capacity, continuing to execute our disciplined treasury management strategy and pursuing additional strategic arrangements, such as joint ventures, data center hosting and leasing agreements, or software licensing arrangements. We aim to be a market leader in developing next-generation digital infrastructure and providing best-in-class solutions to support various compute workloads.

Recent Developments

Fluidstack Lease

On September 25, 2025, we announced Cipher Barber Lake LLC (“Cipher Barber Lake”), our wholly owned indirect subsidiary, had entered into a Datacenter Lease (the “Fluidstack Lease”) with Fluidstack USA II Inc. (“Fluidstack”), which provides for the development of a data center facility on, and lease to Fluidstack of, the Barber Lake Facility located near Colorado City, Texas on the terms and subject to the conditions contained therein. The Facility is expected to provide 168 megawatts (MW) of critical IT load for high-performance computing data center operations. We expect to complete the development and construction of the facility and deliver the facility to Fluidstack by September 2026. Fluidstack’s obligations to pay rent under the Fluidstack Lease begin on the commencement date of the lease and will continue for a 10-year term.

Colchis Site Acquisition

On October 20, 2025, we purchased majority ownership of a 1-GW site in west Texas. The Colchis site includes a fully executed 1-GW Direct Connect Agreement with American Electric Power (“AEP”), under which AEP will construct the necessary dual interconnection facility for a targeted energization in 2028. Construction of the interconnection facility will proceed in parallel with ERCOT's final review and approval. The 620-acres of land under option sit adjacent to the existing substation, and the site has all the necessary characteristics for development of an HPC data center.

Amazon Web Services Lease

On October 29, 2025, we executed a 15-year data center campus lease with Amazon Web Services to provide turnkey space and power for artificial intelligence (“AI”) workloads. Under the terms of the lease agreement, Cipher will deliver

300 MW of capacity in 2026. The capacity will be delivered in two phases, expected to begin in July 2026 and complete in the fourth quarter of 2026, with rent commencing in August 2026.

Shareholder Approval to Increase Authorized Shares

On October 30, 2025, our shareholders approved an amendment to our Second Amended and Restated Certificate of Incorporation to increase the number of shares of common stock, par value $0.001 per share, authorized for issuance from 500,000,000 shares to 1,000,000,000 shares. The amendment became effective upon filing with the Delaware Secretary of State on October 30, 2025.

Factors Affecting Our Results of Operations

There have been no material changes to the “Factors Affecting Our Results of Operations” in the “Management’s Discussion and Analysis of Financial Condition and Results of Operations” section of our 2024 Form 10-K. Our financial position and results of operations depend to a significant extent on those factors.

Summary of Bitcoin Inventory

The following table presents information about our Bitcoin inventory for the nine months ended September 30, 2025, including bitcoin production and sales of bitcoin (dollar amounts in thousands):

Quantity Amounts
Opening balance 994 $92,651
Bitcoin received from equity investees 205 20,714
Bitcoin received from mining activities 1,334 139,858
Bitcoin received from loan 180 16,551
Bitcoin loan payments (2) (140)
Proceeds from sales of bitcoin (1,563) (150,226)
Realized gains on sale of bitcoin — 16,092
Unrealized losses on bitcoin(2) — (2,927)
Realized loss on bitcoin transferred to collateral, net — (3,195)
Bitcoin transferred from collateral, net 345 $40,925
Ending balance 1,493 $170,303

Components of our Results of Operations

For a description of the components of our results of operations, refer to the “Management’s Discussion and Analysis of Financial Condition and Results of Operations” section of our 2024 Form 10-K.

Results of Operations

The following table sets forth our results of operations for the periods indicated (in thousands):

Three Months Ended September 30, 2025 2024 Nine Months Ended September 30, 2025 2024
Revenue - bitcoin mining $71,707 $24,102 $164,231 $109,047
Costs and operating (expenses) income
Cost of revenue (26,733) (15,063) (56,957) (44,164)
Compensation and benefits (14,445) (14,738) (44,407) (44,058)
General and administrative (8,167) (8,919) (26,196) (23,362)
Depreciation and amortization (59,549) (28,636) (147,102) (66,131)
Change in fair value of power purchase agreement (9,030) (48,520) (17,180) (19,181)
Power sales 2,335 1,444 4,702 3,726
Equity in (losses) income of equity investees (1,479) 847 (8,472) 1,008
Unrealized gains (losses) on fair value of bitcoin 108 (22,156) (2,927) (2,778)
Realized gains on sale of bitcoin 7,535 20,245 16,092 25,114
Other operating gains (losses) 101 - (2,732) -
Total costs and operating expenses (109,324) (115,496) (285,179) (169,826)
Operating loss (37,617) (91,394) (120,948) (60,779)
Other income (expense)
Interest income 457 1,188 943 3,027
Interest expense (1,286) (346) (3,200) (1,118)
Change in fair value of warrant liability 31,860 - 31,860 250
Other income (expense) 3,000 (4) 4,064 (1,235)
Total other income 34,031 838 33,667 924
Loss before taxes (3,586) (90,556) (87,281) (59,855)
Current income tax benefit (expense) 767 (211) (1,157) (932)
Deferred income tax benefit (expense) (464) 4,013 399 (1,358)
Total income tax benefit (expense) 303 3,802 (758) (2,290)
Net loss $(3,283) $(86,754) $(88,039) $(62,145)

Comparative Results for the Three Months Ended September 30, 2025 and 2024

Revenue

Revenue for the three months ended September 30, 2025 was $71.7 million compared to $24.1 million for the three months ended September 30, 2024 and was generated from bitcoin mining operations at the Odessa and Black Pearl Facilities. The increase year over year was primarily driven by higher bitcoin prices in the current quarter compared to the prior year quarter, and an increase in total bitcoin mined attributable to the Black Pearl Facility coming online at the end of the second quarter of 2025.

Cost of revenue

Cost of revenue for the three months ended September 30, 2025 was $26.7 million, compared with $15.1 million for the three months ended September 30, 2024, and consisted primarily of power costs at our data centers. The increase in the three months ended September 30, 2025 is driven primarily by additional power costs from mining activities at the Black Pearl Facility, which commenced mining in the second quarter of 2025.

Compensation and benefits

Compensation and benefits for the three months ended September 30, 2025 was $14.4 million, consistent with $14.7 million for the three months ended September 30, 2024.The decrease is primarily due to certain performance-based stock-compensation being fully vested in 2024.

General and administrative

General and administrative expenses decreased by $0.7 million to $8.2 million during the three months ended September 30, 2025 from $8.9 million for the three months ended September 30, 2024. The decrease was primarily driven by decreased legal fees in the current quarter related to strategic initiatives.

Depreciation and amortization

Depreciation for the three months ended September 30, 2025 was $59.5 million, an increase of $30.9 million compared to Depreciation and amortization of $28.6 million for the three months ended September 30, 2024. The increase was primarily due to additional depreciation expense on miners acquired as part of the Odessa fleet upgrade, and assets at our Black Pearl Facility being placed into service.

Change in fair value of derivative asset

Change in fair value of derivative asset was a $9.0 million loss for the three months ended September 30, 2025 and was driven by the fair value of the Luminant Power Agreement. The estimated fair value of our derivative asset was derived from Level 2 and Level 3 inputs, and, due to a lack of quoted prices for similar type assets, is classified in Level 3 of the fair value hierarchy. Specifically, the discounted cash flow estimation models contain quoted spot and forward prices for electricity, as well as estimated usage rates consistent with the terms of the Luminant Power Agreement, the initial term of which is five years.

Power sales

At the Odessa Facility we sold excess electricity that was available under the Luminant Power Agreement back to the ERCOT market through Luminant. We sold power for proceeds of $2.3 million and $1.4 million for the three months ended September 30, 2025, and 2024, respectively. Power sales fluctuate each period based on power and bitcoin prices which are both volatile.

Equity in (losses) income of equity investees

Equity in losses of equity investees totaled $1.5 million for the three months ended September 30, 2025 compared to income of $0.8 million for the three months ended September 30, 2024. Equity in losses of equity investees consists of our 49% share in the earnings (losses) generated by our three partially-owned mining sites, and the accretion of the basis differences in our investments in the equity investees that resulted from contributions of miners during the year ended December 31, 2022. We are accreting these basis differences over the five-year useful life of the miners.

Unrealized (losses) gains on fair value of bitcoin

Unrealized gains on fair value of bitcoin totaled $0.1 million for the three months ended September 30, 2025, compared to losses of $22.2 million for the three months ended September 30, 2024. Unrealized (losses) gains on fair value of bitcoin is driven by the cost of bitcoin mined compared to the price of bitcoin at the end of the period. The current quarter’s ending bitcoin price was consistent with the average price over the period.

Realized (losses) gains on sale of bitcoin

Realized gains on sale of bitcoin totaled $7.5 million for the three months ended September 30, 2025 compared to $20.2 million for the three months ended September 30, 2024. Realized gains and losses on sale of bitcoin is a result of selling bitcoin at prices different from the cost basis.

Other income

Other income totaled $34.0 million for the three months ended September 30, 2025, compared to Other income of $0.8 million for three months ended September 30, 2024. The balance in the current quarter is primarily related to the gain on the mark to market of our Warrant liability.

Benefit for income taxes

For the three months ended September 30, 2025, we recorded a benefit for income taxes of $0.3 million primarily driven by net losses in the current period. For the three months ended September 30, 2024, we recorded a benefit for income taxes of $3.8 million.

Comparative Results for the Nine Months Ended September 30, 2025 and 2024

Revenue

Revenue for the nine months ended September 30, 2025 was $164.2 million, compared to $109.0 million for the nine months ended September 30, 2024, and was generated from bitcoin mining operations at the Odessa and Black Pearl Facilities. The increase year over year was primarily driven by an increase in the average bitcoin price in the current year, partially offset by a decrease in the amount of bitcoin mined as a result of the bitcoin halving in April 2024.

Cost of revenue

Cost of revenue for the nine months ended September 30, 2025 was $57.0 million, compared with $44.2 million for the nine months ended September 30, 2024, and consisted primarily of power costs at our data centers. The increase is primarily due to increased power costs at the Black Pearl Facility which commenced mining operations in July 2025.

Compensation and benefits

Compensation and benefits for the nine months ended September 30, 2025 was $44.4 million, consistent with $44.1 million for the nine months ended September 30, 2024.

General and administrative

General and administrative expenses for the nine months ended September 30, 2025 was $26.2 million, an increase of $2.8 million compared to $23.4 million for the nine months ended September 30, 2024. The increase was primarily driven by an increase in legal fees related to strategic initiatives.

Depreciation and amortization

Depreciation and amortization for the nine months ended September 30, 2025 was $147.1 million, an increase of $81.0 million compared to Depreciation and amortization of $66.1 million for the nine months ended September 30, 2024. The increase was primarily due to increased miners, and mining equipment at the Odessa Facility as a result of the Odessa fleet upgrade in the fourth quarter of 2024, increased fixed assets placed into service as a result of the Black Pearl Facility commencing operations in July 2025, and the change in the estimated useful life of our miners from five years to three years as of June 1, 2024.

Change in fair value of derivative asset

Change in fair value of derivative asset was a $17.2 million decrease for the nine months ended September 30, 2025 and was driven by the fair value of the Luminant Power Agreement. The estimated fair value of our derivative asset was derived from Level 2 and Level 3 inputs, and, due to a lack of quoted prices for similar type assets, is classified in Level 3 of the fair value hierarchy. Specifically, the discounted cash flow estimation models contain quoted spot and forward prices for electricity, as well as estimated usage rates consistent with the terms of the Luminant Power Agreement, the initial term of which is five years.

Power sales

At our Odessa Facility, we sell excess electricity that was available under the Luminant Power Agreement, but not needed in our mining operations, back to the ERCOT market through Luminant. We sold power for proceeds of $4.7 million and $3.7 million for the nine months ended September 30, 2025, and 2024, respectively. Power sales fluctuate each period based on power and bitcoin prices, which are volatile.

Equity in (losses) income of equity investees

Equity in losses of equity investees totaled $8.5 million for the nine months ended September 30, 2025 compared to income of $1.0 million for the nine months ended September 30, 2024. Equity in losses of equity investees consists of our 49% share in the earnings (losses) generated by our three partially-owned mining sites, and the accretion of the basis differences in our investments in the equity investees that resulted from contributions of miners during the year ended December 31, 2022. We are accreting these basis differences over the five-year useful life of the miners. For the nine months ended September 30, 2025, we recognized roughly $4.0 million as our 49% share of a one-time impairment charge on the miners of Alborz LLC, net of accretion.

Unrealized (losses) gains on fair value of bitcoin

Unrealized losses on fair value of bitcoin totaled $2.9 million for the nine months ended September 30, 2025, compared to Unrealized losses on fair value of bitcoin of $2.8 million for the nine months ended September 30, 2024. Unrealized (losses) gains on fair value of bitcoin is driven by the cost of bitcoin mined compared to the price of bitcoin at the end of the period.

Realized gains on sale of bitcoin

Realized gains on sale of bitcoin totaled $16.1 million for the nine months ended September 30, 2025 compared to $25.1 million in the prior year period. In both periods, this is driven by selling bitcoin above our cost basis.

Other expense (income)

Other expense totaled $33.7 million for the nine months ended September 30, 2025, compared to $0.9 million of Other income for the nine months ended September 30, 2024. The increase of Other expense in the current year is driven primarily from the mark to market on our Warrant liability in the current period.

Income tax benefit (expense)

For the nine months ended September 30, 2025, we recorded a provision for income taxes of $0.8 million as a result of projected income for the current year in the jurisdictions which we operate. For the nine months ended September 30, 2024, we recorded a provision for income taxes of $2.3 million.

Liquidity and Capital Resources

We had cash used in operations of $153.5 million for the nine months ended September 30, 2025. As of September 30, 2025, we had cash and cash equivalents of $1,207.4 million, total stockholders’ equity of $783.2 million and an accumulated deficit of $269.5 million. We fund operations primarily through a combination of at-the-market stock issuances, short-term and long-term financing arrangements, and bitcoin sales.

We have established an at-the-market sales agreement with Cantor Fitzgerald & Co., Canaccord Genuity LLC, Needham & Company, LLC, Compass Point Research & Trading, LLC, Keefe, Bruyette & Woods, Inc., Virtu Americas LLC, and BTIG, LLC (each, an “Agent” and, together, the “Agents”), pursuant to which we may, from time to time, sell shares of our common stock having an aggregate offering price of up to $725.7 million. For the three months ended September 30, 2025, we received net proceeds on sales of 6.0 million shares of common stock under the Amended and Restated Sales Agreement of approximately $31.7 million (net of commissions and expenses) at an average net selling price of $5.29 per share. For more information on our at-the-market sales agreement and our at-the-market offerings, see Note 15. Stockholders’ Equity.

We have a master loan agreement with Coinbase Credit, Inc., as lender, and Coinbase, Inc., as lending service provider. Pursuant to the master loan agreement, we currently have a secured line of credit up to $25.0 million (the “Coinbase Overnight Credit Facility”). We will not incur commitment fees for unused portions of the Coinbase Overnight Credit Facility. The borrowing rate on amounts drawn against the Coinbase Overnight Credit Facility is determined on the basis of the Federal Funds Target Rate - Upper Bound, plus 2.5%, calculated daily based on a 365-day year and payable monthly for the duration of the loan. Borrowings under the Coinbase Overnight Credit Facility are available on demand, open term, and collateralized by bitcoin transferred to the lending service provider’s platform. As of September 30, 2025 we had nothing drawn on the Coinbase Overnight Credit Facility.

We enter into agreements with Luxor Technology Corporation (“Luxor”) when needed to borrow bitcoin for short-term periods, which we are able to use as a source of short-term financing.

On May 22, 2025, we issued $172.5 million principal amount of convertible notes due in 2030 with an interest rate of 1.75% (the “2030 Convertible Notes”). The 2030 Convertible Notes are senior, unsecured obligations with interest due semiannually on May 15 and November 15 each year beginning on November 15, 2025.

On September 30, 2025, we issued an aggregate principal amount of $1,300 million of 0.00% Convertible Senior Notes due 2031 (the “2031 Convertible Notes” and together with the 2030 Convertible Notes, the “Convertible Notes”)). With the net proceeds of the 2031 Convertible Notes, we funded capped call transactions which are generally expected to reduce the potential dilution of the Company’s common stock that will initially underlie the 2031 Convertible Notes, and expect to use the remaining proceeds to finance a portion of the construction at the Company’s Barber Lake facility, accelerate the build-out of its high-performance computing strategy, continue to develop its sites, and forgeneral corporate purposes.

For more information on our 2030 Convertible Notes and 2031 Convertible Notes, see Note 14. Debt.

Management believes that our existing financial resources, combined with projected cash and bitcoin inflows from our data centers, our intent and ability to sell bitcoin received or earned, and our intent and ability to sell common stock through at-the-market offerings will be sufficient to enable us to meet our operating and capital requirements for at least 12 months from the date the condensed consolidated financial statements included in this Quarterly Report are issued and the foreseeable future.

Cash Flows

The following table summarizes our sources and uses of cash for the periods indicated (in thousands):

Nine months ended September 30, 2025 2024
Net cash used in operating activities $(153,506) $(58,533)
Net cash used in investing activities (131,454) (195,147)
Net cash provided by financing activities 1,486,202 207,309
Net increase (decrease) in cash and cash equivalents $1,201,242 $(46,371)

Operating Activities

Net cash used in operating activities increased by $95.0 million to $153.5 million for the nine months ended September 30, 2025 from $58.5 million for the nine months ended September 30, 2024. We incurred a net loss of $88.0 million for the nine months ended September 30, 2025, compared to a net loss of $62.1 million for the nine months ended September 30, 2024, representing an increase of $25.9 million. Cash flows used in operating activities was impacted by a $4.1 million increase in non-cash items, primarily driven by an $80.8 million increase in depreciation, an increase of $9.5 million in equity in losses of equity investees, partially offset by an increase of $54.7 million in non-cash consideration received for services and a decrease of $31.6 million in the change in fair value of our warrants. Additionally, changes in assets and liabilities resulted in an increase in cash used of $65.0 million between the nine months ended September 30, 2025 and 2024.

Investing Activities

Cash used in investing activities decreased by $63.7 million to $131.5 million of net cash used in investing activities for the nine months ended September 30, 2025 compared to $195.1 million of net cash used in investing activities for the nine months ended September 30, 2024. This change primarily related to a decrease of $134.3 million in deposits related to new miner purchases, an increase of $70.4 million in proceeds from sale of bitcoin, offset by an increase of $169.7 million increase in purchases of Property and equipment related to building out the Black Pearl facility and new miner purchases.

Financing Activities

Cash flows provided by financing activities increased by $1,278.9 million to $1,486.2 million net cash provided by financing activities for the nine months ended September 30, 2025 from $207.3 million net cash provided by financing activities for the nine months ended September 30, 2024. This change was primarily driven by a $50.0 million increase in proceeds from treasury stock reissued for PIPE investment and a $1,437.4 million increase in proceeds from issuance of convertible notes, net of issuance costs, partially offset by a $106.3 million decrease in proceeds from the issuance of common stock during the nine months ended September 30, 2025.

Contractual Obligations and Other Commitments

On December 17, 2021, we entered into a lease agreement for office space, amended in the second quarter of 2024, with a term through May 2029. Monthly rent payments associated with the amended lease are approximately $0.2 million.

We also entered into a series of agreements with affiliates of Luminant ET Services Company LLC (“Luminant”), including the Lease Agreement dated June 29, 2021, with amendment and restatement on July 9, 2021 (as amended and restated, the “Luminant Lease Agreement”). The Luminant Lease Agreement leases a plot of land to us where our data center, ancillary infrastructure and electrical system (the “Interconnection Electrical Facilities” or “substation”) have been set up for our Odessa Facility. We entered into the Luminant Lease Agreement and the Luminant Purchase and Sale Agreement to build the infrastructure necessary to support our planned operations. Management determined that the Luminant Lease Agreement and the Luminant Purchase and Sale Agreement should be combined for accounting purposes under ASC 842 (collectively, the “Combined Luminant Lease Agreement”) and that amounts exchanged under the combined contract should be allocated to the various components of the overall transaction based on relative fair values.

Our management determined that the Combined Luminant Lease Agreement contains two lease components; and the components should be accounted for together as a single lease component, because the effect of accounting for the land lease separately would be insignificant.

The Combined Luminant Lease Agreement commenced on November 22, 2022 and has an initial term of five years, with renewal provisions that are aligned with the Luminant Power Agreement. Financing for use of the land and substation is provided by Luminant affiliates. Despite lease commencement in November 2022, we had not been required by Luminant to make any lease payments for the substation prior to July 2023, therefore we accrued amounts due under the Combined Luminant Lease Agreement in accrued expenses and other current liabilities on its condensed consolidated balance sheet.

On August 23, 2023, we entered into a second amendment of the Luminant Lease Agreement, the terms of which included an amended payment schedule, reflecting monthly installments of principal and interest totaling $19.7 million on an undiscounted basis, due over the remaining four-year period starting in July 2023. This amendment did not have a material impact on our condensed consolidated financial statements.

At the end of the lease term for the Interconnection Electrical Facilities, the substation will be sold back to Luminant’s affiliate, Vistra Operations Company, LLC at a price to be determined based upon bids obtained in the secondary market.

Non-GAAP Financial Measures

We are providing supplemental financial measures for Adjusted Earnings (Loss) and Adjusted Earnings (Loss) per share - diluted, in each case that exclude the impact of (i) the non-cash change in fair value of derivative asset, (ii) share-based compensation expense, (iii) depreciation and amortization, (iv) deferred income tax expense, (v) nonrecurring gains and losses and (vi) the non-cash change in fair value of warrant liability. These supplemental financial measures are not measurements of financial performance under accounting principles generally accepted in the United States (“GAAP”) and, as a result, these supplemental financial measures may not be comparable to similarly titled measures of other companies. Management uses these non-GAAP financial measures internally to help understand, manage, and evaluate our business performance and to help make operating decisions. We believe the use of these non-GAAP financial measures can also facilitate comparison of our operating results to those of our competitors by excluding certain items that vary in our industry based on company policy.

Non-GAAP financial measures are subject to material limitations as they are not in accordance with, or a substitute for, measurements prepared in accordance with GAAP. For example, we expect that share-based compensation expense, which is excluded from the non-GAAP financial measure, will continue to be a significant recurring expense over the coming years and is an important part of the compensation provided to certain employees, officers and directors. Similarly, we expect that depreciation and amortization will continue to be a recurring expense over the term of the useful life of the related assets. Our non-GAAP financial measures are not meant to be considered in isolation and should be read only in conjunction with our condensed consolidated financial statements included elsewhere in this Quarterly Report, which have been prepared in accordance with GAAP. We rely primarily on such condensed consolidated financial statements to understand, manage and evaluate our business performance and use the non-GAAP financial measures only supplementally.

The following is a reconciliation of our Adjusted Earnings (loss) to the most directly comparable GAAP measure for the periods indicated (in thousands):

Reconciliation of Adjusted Earnings: Three Months Ended September 30, 2025 2024 Nine Months Ended September 30, 2025 2024
Net loss $(3,283) $(86,754) $(88,039) $(62,145)
Change in fair value of power purchase agreement 9,030 48,520 17,180 19,181
Share-based compensation expense 9,074 10,211 28,736 31,865
Depreciation and amortization 59,549 28,636 147,102 66,131
Deferred income tax (benefit) expense 464 (4,013) (399) 1,358
Other (losses) gains - nonrecurring (2,246) — 4,049 —
Change in fair value of warrant liability (31,860) — (31,860) (250)
Adjusted earnings (loss) $40,728 $(3,400) $76,769 $56,140

The following is a reconciliation of our Adjusted Earnings (loss) per share - diluted to the most directly comparable GAAP measure for the periods indicated:

Reconciliation of Adjusted Earnings per share - diluted: Three Months Ended September 30, 2025 2024 Nine Months Ended September 30, 2025 2024
Net loss per share - diluted $(0.01) $(0.26) $(0.23) $(0.20)
Change in fair value of power purchase agreement per diluted share 0.03 0.14 0.03 0.07
Share-based compensation expense per diluted share 0.02 0.03 0.08 0.10
Depreciation and amortization per diluted share 0.15 0.09 0.39 0.21
Deferred income tax (benefit) expense per diluted share — (0.01) — —
Other (losses) gains - nonrecurring per diluted share (0.01) — 0.01 —
Change in fair value of warrant liability per diluted share (0.08) — (0.08) —
Adjusted earnings (loss) per diluted share $0.10 $(0.01) $0.20 $0.18

Critical Accounting Policies, and Use of Estimates

For a description of our policies regarding our critical accounting estimates, see "Critical Accounting Policies and Estimates" of Part II, Item 7 "Management's Discussion and Analysis of Financial Condition and Results of Operations" in our 2024 Form 10-K. As of September 30, 2025, there were no significant changes in our critical accounting policies and estimates or the application or the results of the application of those policies to our unaudited condensed consolidated financial statements from those previously disclosed in our 2024 Form 10-K.

Recent Accounting Pronouncements

Information regarding recent accounting pronouncements applicable to us, adopted and not yet adopted as of the date of this report, is included in Note 2 to our unaudited condensed consolidated financial statements located in “Part I - Financial Information, Item 1. Financial Statements” in this Quarterly Report.

Market risk

As filed, 1,425 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

The following discussion of our market risks involves forward-looking statements. Actual results could differ materially from those projected in our forward-looking statements. For more information regarding the forward-looking statements used in this section and elsewhere in this Quarterly Report, see the Cautionary Note Regarding Forward-Looking Statements at the forepart of this Quarterly Report.

Our primary market risks are described below. We use various strategies to manage these risks; however, they may still from time to time impact our condensed consolidated financial statements.

Bitcoin Price Risk

We hold bitcoin on our inventory at fair value, and as such we are exposed to the impact of the change in bitcoin price. As of September 30, 2025, we had 1,493 bitcoin in inventory. A 10% decrease in the price of bitcoin would result in an estimated $17.0 million increase in Net loss for the nine months ended September 30, 2025.

Power Price Risk

The estimated fair value of our Derivative asset related to our power purchase agreement is derived from Level 2 and Level 3 inputs. Specifically, the discounted cash flow estimation models contain quoted spot and forward prices for electricity. A 10% decrease in power prices would result in an estimated $13.1 million decrease in the estimated fair value of the Derivative asset and increase in Net loss for the nine months ended September 30, 2025.

Controls and procedures

As filed, 4,918 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Limitations on Effectiveness of Controls and Procedures

In designing and evaluating our disclosure controls and procedures, management recognizes that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objectives. In addition, the design of disclosure controls and procedures must reflect the fact that there are resource constraints and that management is required to apply judgment in evaluating the benefits of possible controls and procedures relative to their costs.

Evaluation of Disclosure Controls and Procedures

We conducted an evaluation of the effectiveness of our “disclosure controls and procedures”, as defined by Rules 13a-15(e) and 15d-15(e) of the Exchange Act, as of September 30, 2025, the end of the period covered by this Quarterly Report. This evaluation was done under the supervision and with the participation of management, including our Chief Executive Officer and Chief Financial Officer. There are inherent limitations to the effectiveness of any system of disclosure controls and procedures. Accordingly, even effective disclosure controls and procedures can only provide reasonable assurance of achieving their control objectives. Based upon this evaluation, our Chief Executive Officer and Chief Financial Officer concluded that, our disclosure controls and procedures were not effective at the reasonable assurance level as of September 30, 2025.

Remediation of Material Weakness

As noted in the 2024 Form 10-K, during management’s assessment of internal controls over financial reporting, a material weakness was identified related to certain Information Technology General Controls (“ITGCs”) over change management controls.

As management is responsible for maintaining effective internal control over financial reporting, and for its assessment of the effectiveness of internal control over financial reporting, we understand the importance of developing a resolution plan aligned with management and overseen by the Audit Committee of our Board of Directors.

Since the material weakness related to certain ITGCs over change management controls and lack of related compensating automated process-level and manual controls was identified, management began implementing and has continued to implement and refine measures designed to ensure that control deficiencies contributing to the material weakness are remediated, such that these controls are designed, implemented, and operating effectively. During the three months ended September 30, 2025, management continued implementing its enhanced program change management controls for certain systems impacting the Company’s processes around revenue recognition and design of manual key reconciliation processes. The Company continued to make progress but work still remains to ensure reliability of such controls. Our plan continues to include the following, and management will continue to assess additional opportunities for remediation on an ongoing basis:

  • Continue advancing our remediation efforts by devoting resources throughout 2025 to key areas of financial reporting and information technology.
  • Maintain our engagement with advisory firms to support the evaluation and enhancement of the Company’s controls related to the material weakness described above.
  • Further implement and refine processes and controls and engage external resources as needed to ensure that controls are appropriately designed, implemented, and operating effectively.

We recognize that the material weakness in our internal control over financial reporting will not be considered remediated until the remediated controls operate for a sufficient period of time and can be tested and concluded by management to be designed and operating effectively. Because our remediation efforts involve our outsourced service providers, we cannot provide any assurance that these remediation efforts will be successful or that our internal control over financial reporting will be effective as a result of these efforts.

We continue to evaluate and work to improve our internal control over financial reporting related to the identified material weakness and management may determine to take additional measures to address control deficiencies or determine to modify the remediation plan described above. In addition, we report the progress and status of the above remediation efforts to the Audit Committee on a periodic basis.

Changes in Internal Control over Financial Reporting

Other than the remediation efforts described above, there were no changes in our internal control over financial reporting (as defined in Rules 13a-15(f) and 15d-15(f) under the Exchange Act) during the three months ended September 30, 2025 that have materially affected, or are reasonably likely to materially affect, our internal control over financial reporting.

Risk factors

As filed, 27,458 characters, with its headings, lists and tables. Extracted from the main document; charts and exhibits are in the original on sec.gov.

Our business, financial condition and operating results can be affected by a number of factors, whether currently known or unknown, including but not limited to the risk factors as previously disclosed in Part I, Item 1A, “Risk Factors” of our 2024 Form 10-K, which is incorporated herein by reference. Other than the additional risk factors herein, there have been no material changes to the risk factors previously disclosed in our 2024 Form 10-K.

Risks Relating to Our Business

If we are unable to complete the construction of our Barber Lake Facility in a timely manner or within our anticipated cost estimates, our business and results of operations could be adversely affected.

Our business depends upon the construction of our Barber Lake Facility. Until we complete construction of all of the facilities that are required by the Fluidstack Lease, we will not realize the full amount of projected revenue from such lease. We cannot guarantee we will complete construction (or any future strategic growth initiatives) on time or within our cost estimates, if at all, due in part to the ongoing challenges to the global supply chain, the implementation of new tariffs and more restrictive trade policies, increased inflation and changing conditions within the United States labor market. Under certain circumstances, our lessee will have the right to terminate the lease if there are significant delays in the completion of construction, subject to extension for force majeure events. If we experience delays in the construction process or are unable to complete construction within our anticipated costs estimates, we may not generate sufficient revenues to fund our liquidity needs, including payment of principal and interest on the notes.

Our business is exposed to construction risks.

Construction of our Barber Lake Facility exposes us to significant construction risks, including risks related to: construction delays; lack of availability of parts and/or labor, increased prices as a result, in part, of inflation, and delays for data center equipment; labor disputes and work stoppages, including interruptions in work due to pandemics, epidemics, and other health risks; unanticipated environmental issues and geological problems; delays related to permitting and approvals to commence operations from public agencies and utility companies; and delays in site readiness leading to our failure to meet commitments made in connection with such expansion. All construction-related projects depend on the skill, experience, and attentiveness of our personnel throughout the design and construction process. Should a designer, general contractor, significant subcontractor or key supplier experience financial difficulties or other problems during the design or construction process, we could experience significant delays, increased costs to complete the project and/or other negative impacts to our expected returns.

If we are unable to overcome these risks and additional pressures to complete our construction projects in a timely manner, if at all, we may not realize their anticipated benefits, and our business and financial condition may suffer as a result.

The Google Backstop will only be effective after rent commencement under the Fluidstack Lease and is only triggered by certain events of default under the Fluidstack Lease.

Google’s backstop of Fluidstack’s obligations under the Fluidstack Lease is only effective following the rent commencement date of the Fluidstack Lease. If the Fluidstack Lease does not commence as of its targeted rent commencement date, then the Google Backstop will not become effective until the completion of the Barber Lake Facility. If completion of the Barber Lake Facility is delayed by greater than 180 days, or greater than 300 days in the case of a force majeure event, as may be extended for tenant delay, Fluidstack will have the right to terminate the Fluidstack Lease. Such termination event would not trigger the Google Backstop. In addition, the Google Backstop is only triggered upon a payment or insolvency event of default under the Fluidstack Lease. While unlikely to occur, there are other events of default or termination events that may result in the termination of the Fluidstack Lease without triggering the Google

Backstop. In addition, if we have a disagreement with Google about whether the Google Backstop has been triggered, there can be no assurance that Google will honor the Google Backstop in a timely manner or at all.

Our HPC business strategy may not perform as planned.

We believe the potential for HPC hosting complements our current business model with expected stable, long-term and high margin revenue. However, the success of our HPC hosting services may not develop as anticipated, and may be affected by factors such as the reliability and timing of power supply, supply chain disruption (including local labor availability), the implementation of new tariffs and more restrictive trade regulations and changes in in-house specialized expertise to manage the business. A failure to successfully implement our HPC business strategy may adversely affect our business, prospects, or operations.

We may be unable to access sufficient additional capital for future strategic growth initiatives.

The expansion of our existing mining facilities and our digital infrastructure to support HPC hosting and colocation are capital-intensive projects, and we anticipate that future strategic growth initiatives will likewise continue to be capital-intensive. We expect to raise additional capital to fund these and other future strategic growth initiatives; however, we may be unable to do so in a timely manner, in sufficient quantities, or on terms acceptable to us, if at all. If we are unable to raise the additional capital needed to execute our future strategic growth initiatives, we may be less competitive in our industry and the results of our operations and financial condition may suffer, and the market price for our securities may be materially and adversely affected.

Enhanced tariff, import/export restrictions, or other trade barriers may have an adverse impact on global economic conditions.

There have been, and continue to be, uncertainties with respect to the global economy and trade relations between the U.S. and other countries globally, including trade policies, treaties, tariffs, and customs duties and taxes. Implementation of more restrictive trade policies or the renegotiation of existing U.S. trade agreements or trade agreements of other countries where we procure supplies and materials for our digital infrastructure could negatively impact our business results of operations, cash flows, and financial condition. Tariffs, sanctions and other barriers to trade could adversely affect the business of our business partners, such as suppliers, which could in turn negatively impact our net revenue and results of operations. If tariffs, trade restrictions or trade barriers are expanded or increased, then our exposure to future taxes and duties on imported products and components could be significant and could have a material effect on our financial results.

We cannot predict the extent to which the U.S. or other countries will impose new or additional quotas, duties, tariffs, taxes, or other similar restrictions upon the import of goods and services in the future, nor can we predict future trade policy or the terms of any renegotiated trade agreements and their impact on our business. The continuing adoption or expansion of trade restrictions, the occurrence of a trade war, or other governmental action related to tariffs or trade agreements or policies has the potential to adversely impact demand for our HPC data centers, our costs, our business partners, our suppliers, and the U.S. economy, which in turn could have a material adverse effect on our business, operating results, and financial condition.

We may be harmed by increased costs to procure power, prolonged power outages, shortages or capacity constraints as well as insufficient access to power.

Any power outages, shortages, capacity constraints or significant increases in the cost of power may have an adverse effect on our business and our results of operations.

We rely on third parties, third party infrastructure, governments, and global supplies to provide a sufficient amount of power to maintain our HPC data center operations to meet the needs of our current and future HPC hosting and colocation tenants. Any limitation on the delivered energy supply could limit our ability to operate our HPC data centers. These limitations could have a negative impact on the Barber Lake Facility or limit our ability to grow our business, which could negatively affect our financial performance and results of operations. Each new HPC data center requires access to significant quantities of electricity. Limitations on generation, transmission and distribution may limit our ability to obtain sufficient power capacity for potential expansion sites or existing markets. Utility companies may impose onerous operating conditions to any approval or provision of power or we may experience significant delays and substantial increased costs to provide the level of electrical service required by our current or future data center designs.

We depend on tenants for our HPC data centers.

Many factors, including global economic conditions, may cause current HPC data center tenants like Fluidstack or future tenants to experience a downturn in their businesses or otherwise experience a lack of liquidity, which may weaken their financial condition and impact our estimates as to the probability of collectability of payments, and ultimately result in their failure to make timely rental and other payments or their default under their agreements with us. Further, the development of new technologies, the adoption of new industry standards or other factors could render our HPC data center tenants’ current products and services obsolete or unmarketable and contribute to a downturn in their businesses, thereby increasing the likelihood that they default under their leases, become insolvent or file for bankruptcy. If a tenant defaults or fails to make timely rent or other payments (notwithstanding the Google Backstop with respect to the Fluidstack Lease), we may experience delays in enforcing our rights as landlord and may incur substantial costs in protecting our investment, which could adversely affect our financial condition and results of operations.

If a tenant becomes a debtor in a case under Title 11 of the United States Code, as amended (the “Bankruptcy Code”), we cannot evict the tenant solely because of the bankruptcy. In addition, the bankruptcy court might authorize the tenant to reject and terminate its contracts with us. Our claim against the tenant for unpaid, future rent and other payments would be subject to a statutory cap that might be substantially less than the remaining amounts actually owed under their agreements with us. In either case, our claim for unpaid rent and other amounts would likely not be paid in full. Our revenue could be materially adversely affected if a significant tenant were to become bankrupt or insolvent, suffer a downturn in its businesses, fail to renew its contract or renew on terms less favorable to us than its current terms.

Our contracts with HPC data center tenants could subject us to significant liability.

In the ordinary course of business, we aim to continuously enter into agreements with tenants pursuant to which we provide data center space, power, environmental controls, physical security and connectivity products to our HPC hosting and colocation tenants. These contracts typically contain indemnification and liability provisions, in addition to service level commitments, which could potentially impose a significant cost on us in the event of losses arising out of certain breaches of such agreements, services to be provided by us or our subcontractors or from third-party claims. HPC data center tenants increasingly are looking to pass through their regulatory obligations and other liabilities to their outsourced data center providers and we may not be able to limit our liability or damages in an event of loss suffered by such tenants whether as a result of our breach of an agreement or otherwise. If such an event of loss occurred, we could be liable for material monetary damages and could incur significant legal fees in defending against such an action, which could adversely affect our financial condition and results of operations.

We may also develop space specifically for HPC data center tenants pursuant to agreements signed prior to beginning or early in the development process. In those cases, if we fail to meet our development obligations under those agreements, these tenants may be able to terminate their agreements and we would be required to find a new tenant for this space. In addition, in certain circumstances we may lease HPC data center facilities prior to their completion. If we fail to complete the facilities in a timely manner, the tenant may be entitled to terminate its agreement, seek damages or penalties against us or pursue other remedies and we may be required to find a new tenant for the space. If we are not able to complete an HPC data center in a timely manner, if development costs are higher than we currently estimate, our financial condition, results of operations and cash flow could be materially adversely affected.

Additionally, a tenant’s decision to lease space and power in our HPC data center typically involves a significant commitment of resources and due diligence on the part of our tenants regarding the adequacy of our facilities. As a result, we may expend significant time and resources in pursuing a particular transaction that may not result in revenue. Economic conditions, including market downturns and the implementation of new tariffs and more restrictive trade regulations may impact tenants’ ability to plan future business activities, which could cause tenants to slow spending or delay decision-making. Our inability to adequately manage the risks associated with these developments may adversely affect our business, financial condition and results of operations.

The development and advancement in the efficiency of AI models presents risks and challenges that may adversely impact our business and operating results.

The introduction of, and advancement in the efficiency of AI models could potentially adversely affect data center usage by significantly reducing the computational power needed to train AI models, potentially leading to less demand for high-power density, liquid-cooled data center infrastructure and colocation facilities such as those we are building at the Barber Lake Facility. New advancements in AI models could also alter the way data centers are currently designed and utilized and may adversely affect our business and results of operations.

Risks Related to our Convertible Notes

Our indebtedness and liabilities could limit the cash flow available for our operations, expose us to risks that could adversely affect our business, financial condition and results of operations and impair our ability to satisfy our obligations under the Convertible Notes.

We incurred 172.5 million of additional indebtedness as a result of the 2030 Convertible Notes offering completed in May 2025 and $1,300.0 million principal amount of additional indebtedness as a result of the 2031 Convertible Notes offering completed in September 2025. We may also incur additional indebtedness to meet future financing needs. Our indebtedness could have significant negative consequences for our security holders and our business, results of operations and financial condition by, among other things:

  • increasing our vulnerability to adverse economic and industry conditions;
  • limiting our ability to obtain additional financing;
  • requiring the dedication of a substantial portion of our cash flow from operations to service our indebtedness, which will reduce the amount of cash available for other purposes;
  • limiting our flexibility to plan for, or react to, changes in our business;
  • diluting the interests of our existing stockholders as a result of issuing shares of our common stock upon conversion of the Convertible Notes; and
  • placing us at a possible competitive disadvantage with competitors that are less leveraged than us or have better access to capital.

Our ability to make scheduled payments of the principal of, to pay interest on or to refinance our indebtedness, including the Convertible Notes, depends on our future performance, which is subject to economic, financial, competitive and other factors beyond our control. Our business may not generate sufficient funds, and we may otherwise be unable to maintain sufficient cash reserves, to pay amounts due under our indebtedness, including the Convertible Notes, and our cash needs may increase in the future. In addition, future indebtedness that we may incur may contain financial and other restrictive covenants that limit our ability to operate our business, raise capital or make payments under our other indebtedness. If we fail to comply with these covenants or to make payments under our indebtedness when due, then we would be in default under that indebtedness, which could, in turn, result in that and our other indebtedness becoming immediately payable in full.

We may be unable to raise the funds necessary to repurchase the Convertible Notes for cash following a fundamental change or on a specified optional repurchase date or to pay any cash amounts due upon maturity or conversion of the Convertible Notes, and our other indebtedness may limit our ability to repurchase the Convertible Notes or to pay any cash amounts due upon their maturity or conversion.

Holders of the Convertible Notes may, subject to limited exceptions, require us to repurchase their Convertible Notes on May 15, 2028 (for the 2030 Convertible Notes) and on October 1, 2029 (for the 2031 Convertible Notes), and following a fundamental change, at a cash repurchase price generally equal to the principal amount of the Convertible Notes to be repurchased, plus accrued and unpaid special interest and additional interest, if any. Upon maturity of the Convertible Notes, we must pay their principal amount and accrued and unpaid special interest and additional interest, if any, in cash, unless they have been previously repurchased, redeemed or converted.

In addition, prior to the “reserved share effective date”, upon conversion, we will satisfy all of our conversion obligation in cash, subject to the “share settlement election exception”, and on or after the “reserved share effective date”, upon conversion, we will satisfy part or all of our conversion obligation in cash unless we elect to settle conversions solely in shares of our common stock.

We may not have enough available cash or be able to obtain financing at the time we are required to repurchase the Convertible Notes or pay any cash amounts due upon their maturity or conversion. In addition, applicable law, regulatory authorities and the agreements that we may have in the future governing our other indebtedness may restrict our ability to repurchase the Convertible Notes or to pay any cash amounts due upon their maturity or conversion. Our failure to repurchase Convertible Notes or to pay any cash amounts due upon their maturity or conversion when required will constitute a default under the indenture. A default under the indenture or the fundamental change itself could also lead to a default under agreements governing our other indebtedness, which may result in that other indebtedness becoming immediately payable in full. We may not have sufficient funds to satisfy all amounts due under the other indebtedness and the Convertible Notes.

Provisions in the Convertible Notes indentures could delay or prevent an otherwise beneficial takeover of us.

Certain provisions in the Convertible Notes and related indentures could make a third-party attempt to acquire us more difficult or expensive. For example, if a takeover constitutes a fundamental change, then noteholders will have the right to require us to repurchase their Convertible Notes for cash. In addition, if a takeover constitutes a make-whole fundamental change, then we may be required to temporarily increase the conversion rate. In either case, and in other cases, our obligations under the Convertible Notes and the indenture could increase the cost of acquiring us or otherwise discourage a third party from acquiring us or removing incumbent management, including in a transaction that noteholders or holders of our common stock may view as favorable.

The conditional conversion feature of the Convertible Notes, if triggered, may adversely affect our financial condition and operating results.

In the event the conditional conversion feature of the Convertible Notes is triggered, holders of such notes will be entitled to convert the Convertible Notes at any time during specified periods at their option. If one or more holders elect to convert their Convertible Notes, (i) if the conversion date for such conversion is before the “reserved share effective date ”, we will settle all of our conversion obligation through the payment of cash, subject to the “share settlement election exception”, and (ii) if the conversion date for such conversion is on or after the “reserved share effective date,” we may elect to settle all or a portion of our conversion obligation through the payment of cash, which could adversely affect our liquidity. In addition, even if holders do not elect to convert their Convertible Notes, we could be required under applicable accounting rules to reclassify all or a portion of the outstanding principal of the Convertible Notes as a current rather than long-term liability, which would result in a material reduction of our net working capital.

The accounting method for the Convertible Notes could adversely affect our reported financial condition and results.

The accounting method for the Convertible Notes may adversely affect our reported earnings and financial condition.

The issuance costs for the Convertible Notes are treated as a debt discount for accounting purposes and will be amortized into interest expense over the term of the Convertible Notes. As a result of this amortization, the interest expense that we expect to recognize for the Convertible Notes for accounting purposes will be greater than the cash special interest or additional interest payments, if any, we will pay on the Convertible Notes, which will result in lower reported income.

Furthermore, if any of the conditions to the convertibility of the Convertible Notes is satisfied, then we may be required under applicable accounting standards to reclassify the liability carrying value of the Convertible Notes as a current, rather than a long-term, liability. This reclassification could be required even if no investors convert their Convertible Notes and could materially reduce our reported working capital.

The issuance of shares of our common stock upon conversion of the Convertible Notes will dilute the ownership interests of our stockholders and could depress the trading price of our common stock.

Upon conversion of the Convertible Notes being offered in the 2030 Convertible Notes offering or the 2031 Convertible Notes offering, we will satisfy part or all of our conversion obligations in shares of our common stock, unless we elect to settle conversions solely in cash. The issuance of shares of our common stock upon conversion of the Convertible Notes will dilute the ownership interests of our stockholders, which could depress the trading price of our common stock. In addition, the market’s expectation that conversions may occur could depress the trading price of our common stock even in the absence of actual conversions. Moreover, the expectation of conversions could encourage the short selling of our common stock, which could place further downward pressure on the trading price of our common stock.

The capped call transactions may affect the value of the 2031 Convertible Notes and the market price of our common stock.

In connection with the issuance of the 2031 Convertible Notes, we entered into privately negotiated capped call transactions with certain financial institutions (collectively, the “option counterparties”). The capped call transactions are generally expected to reduce the potential dilution to our common stock upon any conversion of the 2031 Convertible Notes and/or offset any potential cash payments we are required to make in excess of the principal amount of converted 2031 Convertible Notes, with such reduction and/or offset subject to a cap. In connection with establishing their initial hedges of the capped call transactions, the option counterparties entered into various derivative transactions, which may be exited in the future.We are subject to counterparty risk with respect to the capped call transactions and these capped call transactions may not operate as planned.

The option counterparties are financial institutions, and we will be subject to the risk that any or all of them might default under the capped call transactions. Our exposure to the credit risk of the option counterparties will not be secured by any collateral. Past global economic conditions have resulted in the actual or perceived failure or financial difficulties of many financial institutions and could adversely affect the option counterparties’ performance under the capped call transactions. If an option counterparty becomes subject to insolvency proceedings, we will become an unsecured creditor in those proceedings with a claim equal to our exposure at that time under the capped call transactions with such option counterparty. Our exposure will depend on many factors but, generally, an increase in our exposure will be correlated to an increase in the market price and in the volatility of our common stock. In addition, upon a default by an option counterparty, we may suffer more dilution, the effect of which would not be compensated for, than we currently anticipate with respect to our common stock. We can provide no assurance as to the financial stability or viability of the option counterparties.

In addition, the terms of the capped call transactions are complex, and they may not operate as planned. For example, the terms of these may be subject to adjustment, modification or, in some cases, renegotiation in the event of certain corporate and other transactions. Accordingly, the capped call transactions may not operate as we intend in the event that we are required to adjust the terms of such instruments as a result of transactions in the future or in the event of other unanticipated developments that may adversely affect the functioning of the capped call transactions.

The capped call transactions are separate transactions (in each case entered into between us and the option counterparties), are not part of the terms of the 2031 Convertible Notes and will not change the holders’ rights under the 2031 Convertible Notes.

Figures reported in this filing

Standardized line items from the XBRL in this filing, for the period ended 2025-09-30. Comparative periods it repeats are left out.

Figures reported in this filing
Line itemPeriodValueXBRL concept
Revenue3 months2025-07-01 to 2025-09-30$71.7mus-gaap:Revenues
Revenue9 months2025-01-01 to 2025-09-30$164.2mus-gaap:Revenues
Cost of revenue3 months2025-07-01 to 2025-09-30$26.7mus-gaap:CostOfRevenue
Cost of revenue9 months2025-01-01 to 2025-09-30$57.0mus-gaap:CostOfRevenue
Operating income3 months2025-07-01 to 2025-09-30−$37.6mus-gaap:OperatingIncomeLoss
Operating income9 months2025-01-01 to 2025-09-30−$120.9mus-gaap:OperatingIncomeLoss
Interest expense3 months2025-07-01 to 2025-09-30$1.3mus-gaap:InterestExpenseNonoperating
Interest expense9 months2025-01-01 to 2025-09-30$3.2mus-gaap:InterestExpenseNonoperating
Income tax3 months2025-07-01 to 2025-09-30−$303.0kus-gaap:IncomeTaxExpenseBenefit
Income tax9 months2025-01-01 to 2025-09-30$758.0kus-gaap:IncomeTaxExpenseBenefit
Net income3 months2025-07-01 to 2025-09-30−$3.3mus-gaap:NetIncomeLoss
Net income9 months2025-01-01 to 2025-09-30−$88.0mus-gaap:NetIncomeLoss
Diluted EPS3 months2025-07-01 to 2025-09-30−$0.01us-gaap:EarningsPerShareDiluted
Diluted EPS9 months2025-01-01 to 2025-09-30−$0.23us-gaap:EarningsPerShareDiluted
Basic EPS3 months2025-07-01 to 2025-09-30−$0.01us-gaap:EarningsPerShareBasic
Basic EPS9 months2025-01-01 to 2025-09-30−$0.23us-gaap:EarningsPerShareBasic
Diluted shares (weighted)3 months2025-07-01 to 2025-09-30393,191,623 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Diluted shares (weighted)9 months2025-01-01 to 2025-09-30376,372,526 sharesus-gaap:WeightedAverageNumberOfDilutedSharesOutstanding
Operating cash flow9 months2025-01-01 to 2025-09-30−$153.5mus-gaap:NetCashProvidedByUsedInOperatingActivities
Capital expenditure9 months2025-01-01 to 2025-09-30$262.0mus-gaap:PaymentsToAcquirePropertyPlantAndEquipment
Share repurchases9 months2025-01-01 to 2025-09-30$7.3mus-gaap:PaymentsForRepurchaseOfCommonStock
Cash and equivalentsAt period end2025-09-30$1.21bnus-gaap:CashAndCashEquivalentsAtCarryingValue
Current assetsAt period end2025-09-30$1.42bnus-gaap:AssetsCurrent
Total assetsAt period end2025-09-30$2.84bnus-gaap:Assets
Current liabilitiesAt period end2025-09-30$570.2mus-gaap:LiabilitiesCurrent
Total liabilitiesAt period end2025-09-30$2.06bnus-gaap:Liabilities
Long-term debtAt period end2025-09-30$1.02bnus-gaap:LongTermDebtNoncurrent
Short-term borrowingsAt period end2025-09-30$0us-gaap:ShortTermBorrowings
Shareholders' equityAt period end2025-09-30$783.2mus-gaap:StockholdersEquity